 
 Keystone XL Pipeline Project: Key Issues 
Paul W. Parfomak
 
Keystone XL Pipeline Project: Key Issues 
Paul W. Parfomak 
Specialist in Energy and Infrastructure Policy 
Robert Pirog 
Specialist in Energy Economics 
Linda Luther 
Analyst in Environmental Policy 
Adam Vann 
Legislative Attorney 
December 2, 2013 
Congressional Research Service 
7-5700 
www.crs.gov 
R41668 
 
Keystone XL Pipeline Project: Key Issues 
 
Summary 
TransCanada’s proposed Keystone XL Pipeline would transport oil sands crude from Canada and 
shale oil produced in North Dakota and Montana to a market hub in Nebraska for further delivery 
to Gulf Coast refineries. The pipeline would consist of 875 miles of 36-inch pipe with the 
capacity to transport 830,000 barrels per day. Because it would cross the Canadian-U.S. border, 
construction of Keystone XL requires a Presidential Permit from the State Department. A decision 
to issue or deny a Presidential Permit is based on a determination that a project would serve the 
national interest, considering potential impacts on the environment, the economy, energy security, 
foreign policy, and other factors. Environmental impacts are evaluated and documented in an 
Environmental Impact Statement (EIS) under the National Environmental Policy Act (NEPA). 
TransCanada originally applied for a Presidential Permit for the Keystone XL Pipeline in 2008. 
The initial proposal included a southern segment from Oklahoma to the Gulf Coast. A key issue 
that arose during the permit review was concern over environmental impacts in the Sand Hills 
region of Nebraska. This concern led the Nebraska legislature to enact new state pipeline siting 
requirements that would alter the pipeline route through Nebraska. In January 2012, the State 
Department concluded that it would not have sufficient information to evaluate an altered 
pipeline route before a deadline imposed by Congress and denied the permit. The southern 
segment of the original Keystone XL proposal, now called the Gulf Coast Project, was 
subsequently separated from the original proposal because it did not require a Presidential Permit. 
It has been approved by the relevant states and is currently under construction. 
In May 2012, TransCanada reapplied to the State Department for a Presidential Permit to build 
the northern, cross-border segment of Keystone XL. The new permit application initiated a new 
NEPA process. The governor of Nebraska approved a new route through the state avoiding the 
Sand Hills on January 22, 2013. On March 6, 2013, notice was published in the 
Federal Register that the State Department draft EIS for the reconfigured Keystone XL Project was available for 
public comment. The department is in the process of addressing these comments as it prepares a 
final EIS. When the final EIS is issued, a 90-day public review period for the national interest 
determination begins. The department has not stated when it plans to complete this process. 
Development of Keystone XL has been controversial. Proponents base their arguments primarily 
on increasing the diversity of the U.S. petroleum supply and economic benefits, especially jobs. 
Pipeline opposition stems in part from concern regarding the greenhouse gas emissions associated 
with the development of Canadian oil sands, continued U.S. dependency on fossil fuels, and the 
risk of a potential release of heavy crude. 
In light of the State Department’s denial of the 2008 permit application, some in Congress seek 
other means to support development of the pipeline. The Energy Production and Project Delivery 
Act of 2013 (S. 17) would eliminate the Presidential Permit requirement for the reconfigured 
Keystone XL Project. The Keystone for a Secure Tomorrow Act (H.R. 334) and a Senate bill to 
approve the Keystone XL Project (S. 582) would directly approve Keystone XL under the 
authority of Congress to regulate foreign commerce. The Northern Route Approval Act (H.R. 3) 
would eliminate the Presidential Permit requirement for Keystone XL, among other provisions. 
The Senate passed an amendment to the Fiscal 2014 Senate Budget Resolution (S.Con.Res. 8) 
that would provide for the approval and construction of the Keystone XL Project (S.Amdt. 494). 
The North American Energy Infrastructure Act (H.R. 3301) would transfer permit authority for 
oil pipelines from the State Department to the Department of Commerce and would make other 
changes to the pipeline permitting process. 
Congressional Research Service 
Keystone XL Pipeline Project: Key Issues 
 
 
Congressional Research Service 
Keystone XL Pipeline Project: Key Issues 
 
Contents 
Introduction ...................................................................................................................................... 1 
Description of the Keystone Pipeline System .................................................................................. 2 
The Keystone and Keystone XL Pipelines ................................................................................ 2 
Marketlink for Bakken Oil Production ...................................................................................... 4 
Presidential Permit Applications ...................................................................................................... 5 
Consideration of Environmental Impacts Under NEPA ............................................................ 7 
EPA Rating of the Environmental Impact Statement .......................................................... 8 
The National Interest Determination ....................................................................................... 11 
State Siting and Additional Environmental Requirements ...................................................... 13 
Legislative Efforts to Change Permitting Authority ................................................................ 15 
Arguments For and Against the Pipeline ....................................................................................... 16 
Impact on U.S. Energy Security .............................................................................................. 17 
Canadian Oil Imports in the Overall U.S. Supply Context ............................................... 18 
Oil Sands, Keystone XL, and the U.S. Oil Market ........................................................... 19 
Economic Impact of the Pipeline............................................................................................. 26 
Lifecycle Greenhouse Gas Emissions ..................................................................................... 27 
Private Land Use and Oil Spill Impacts .................................................................................. 28 
Issues with the Original Pipeline Route Across the Sand Hills ............................................... 30 
 
Figures 
Figure 1. Existing Keystone Pipeline and Proposed Keystone Expansions .................................... 3 
Figure 2. The Keystone XL Project and Gulf Coast Pipeline .......................................................... 4 
Figure 3. Proposed Enbridge Flanagan South Pipeline Route ....................................................... 23 
Figure 4. Keystone XL Project—Pipeline Route in Nebraska ....................................................... 32 
 
Tables 
Table 1. Milestones in the NEPA process for the Keystone XL Project ........................................ 10 
Table 2. Milestones in National Interest Determination Process for the 2008 Keystone XL 
Pipeline ....................................................................................................................................... 13 
Table 3. U.S. Oil Imports ............................................................................................................... 19 
 
Appendixes 
Appendix A. Presidential Permitting Authority ............................................................................. 33 
Appendix B. Details of the Initial NEPA Review .......................................................................... 35 
 
Congressional Research Service 
Keystone XL Pipeline Project: Key Issues 
 
Contacts 
Author Contact Information........................................................................................................... 38 
Acknowledgments ......................................................................................................................... 38 
 
Congressional Research Service 
Keystone XL Pipeline Project: Key Issues 
 
Introduction1 
In 2008, TransCanada (a Canadian company) submitted to the U.S. Department of State an 
application for a Presidential Permit authorizing construction and operation of pipeline facilities 
for the importation of crude oil at the United States-Canada border. The Keystone XL Pipeline 
system would transport Canadian oil sands crude extracted in Alberta, Canada, and crude 
produced from the Bakken region in North Dakota and Montana to a market hub in Nebraska for 
further delivery to Gulf Coast refineries. A decision to issue or deny the Presidential Permit would 
be based on the State Department’s determination of whether the pipeline system would serve the 
national interest. 
By August 2011, the State Department had compiled data necessary to begin the required 90-day 
public review period for making its national interest determination. During that period, one key 
issue that arose pertained to potential impacts associated with the construction and operation of 
the proposed pipeline segment across the Sand Hills region of Nebraska. This concern led the 
Nebraska legislature to enact new state pipeline siting requirements that would alter the pipeline 
route through Nebraska. As a result, in November 2011, the State Department announced that it 
would need additional time to gather information needed to assess a new pipeline route avoiding 
the Sand Hills. However, the Temporary Payroll Tax Cut Continuation Act of 2011 (P.L. 112-78), 
enacted on December 23, 2011, included provisions requiring the Secretary of State (hereinafter 
the Secretary) to issue a permit for the project within 60 days, unless the President determined the 
project not to be in the national interest. Citing insufficient time to meet the deadline established 
by Congress, the State Department, with the President’s consent, denied the permit for the 
Keystone XL Project. 
TransCanada and Nebraska have since agreed upon an alternative pipeline route avoiding the 
Sand Hills. In May 2012, TransCanada submitted an application to the State Department for a 
Presidential Permit to build a newly configured cross-border segment of Keystone XL Pipeline 
system.2 This report describes the Keystone XL Project as it is proposed in the 2012 Presidential 
Permit application and the process that the State Department is obligated to complete to issue or 
deny that application. To the extent that they may affect the State Department’s decision to issue 
or deny the current permit application, this report discusses selected issues related to the project 
proposed in 2008 and issues that have arisen since the State Department denied the initial permit 
application in 2012. This report also summarizes key arguments that have been raised, both for 
and against the pipeline, by the pipeline’s developers, state and federal agencies, environmental 
groups, private property owners, and other stakeholders. Finally, the report discusses the 
constitutional basis for the State Department’s authority to issue a Presidential Permit, and 
opponents’ possible challenges to this authority. 
                                                 
1 This report provides an overview of the Keystone XL project, permit review process, and general policy issues. For 
more detailed legal analysis, see CRS Report R42124, 
Proposed Keystone XL Pipeline: Legal Issues, by Adam Vann, 
Kristina Alexander, and Kenneth R. Thomas. For more analysis of U.S.-Canada energy trade, see CRS Report R41875, 
The U.S.-Canada Energy Relationship: Joined at the Well, by Paul W. Parfomak and Michael Ratner. For additional 
environmental analysis associated with Canadian oil sands, see CRS Report R42537, 
Canadian Oil Sands: Life-Cycle 
Assessments of Greenhouse Gas Emissions, by Richard K. Lattanzio. For more analysis of Presidential Permits, see 
CRS Report R43261, 
Presidential Permits for Border Crossing Energy Facilities, by Adam Vann and Paul W. 
Parfomak.  
2 The southern segment of the original Keystone XL proposal, now called the Gulf Coast Project, was separated from 
the original proposal because it does not require a Presidential Permit. It is currently under construction. 
Congressional Research Service 
1 
Keystone XL Pipeline Project: Key Issues 
 
Description of the Keystone Pipeline System 
In 2005, TransCanada announced a plan to address expected increases in Western Canadian 
Sedimentary Basin production by constructing the Keystone Pipeline System. When complete, 
the system would transport crude oil from Hardisty, Alberta, to U.S. markets in the Midwest and 
Gulf Coast. The pipeline system was proposed as two distinct phases—the Keystone Pipeline 
(complete and in service) and the Keystone XL Pipeline.  
The Keystone and Keystone XL Pipelines 
The Keystone Pipeline was completed in two segments—the Keystone Mainline and the Cushing 
Extension. The Mainline is 1,353 miles of 30-inch pipeline from Hardisty, Alberta, to the United 
States refineries in Wood River and Patoka, Illinois. The U.S. portion of the pipeline runs 1,086 
miles and begins at the international border in Cavalier County, ND, and has been in service since 
June 2010. The Cushing Extension is 298 miles of 36-inch pipeline and associated facilities that 
run from Steele City, NE (near the Kansas border), to existing crude oil terminals and tanks farms 
in Cushing, OK. The Cushing Extension has been in service since February 2011.  
The original Keystone XL Pipeline Project is now also being developed in two project segments, 
as follows: 
•  
The Gulf Coast Pipeline Project, 485 miles of 36-inch pipeline and associated 
facilities linking the Cushing, OK, tank farms to refineries in Houston and Port 
Arthur, TX. This segment includes the Cushing Marketlink project that will 
provide receipt facilities to transport U.S. crude oil to the Gulf Coast. 
TransCanada anticipates this segment to be in service by 2014. 
•  
The Keystone XL Pipeline Project, 875 miles of 36-inch pipeline and 
associated facilities linking Hardisty, Alberta, to Steele City, NE. This segment 
also includes the Bakken Marketlink in Baker, MT—a pipeline lateral that can 
transport crude oil from the Williston Basin to Steele City (further discussed 
below).  
In the 2008 Presidential Permit application, the “Keystone XL Project” referred to both pipeline 
segments. For the 2012 Presidential Permit application, the “Keystone XL Project” refers to only 
the northern, cross-border pipeline segment. 
The existing Keystone Pipeline has the capacity to deliver up to 590,000 bpd of Canadian crude 
oil to U.S. refineries and export terminals. Both the Keystone XL and Gulf Coast pipelines would 
have a capacity of 830,000 bpd. As a result, the entire Keystone Pipeline System may ultimately 
have the capacity to deliver up to 1.3 million bpd of crude oil. The existing Keystone Pipeline and 
proposed expansions are illustrated in 
Figure 1. The proposed Keystone XL Project and 
associated pipeline segments are illustrated in 
Figure 2. 
Congressional Research Service 
2 
 Keystone XL Pipeline Project: Key Issues 
 
Figure 1. Existing Keystone Pipeline and Proposed Keystone Expansions  
 
Source:
Keystone XL Pipeline Project: Key Issues 
 
Figure 1. Existing Keystone Pipeline and Proposed Keystone Expansions  
 
Source: U.S. State Department, March 2013, Draft EIS for the Keystone XL Project, 
Section 1.2 “Overview of Proposed Project,” p. 1.2-5. 
TransCanada has estimated the capital cost of the U.S. portion of the 2012 Keystone XL Project, 
from the U.S. border to Steele City, NE, would be $5.3 billion.3 This figure is higher than the cost 
estimate when the 2008 permit application was filed, reportedly due to currency swings, changing 
regulatory requirements, and permitting delays.4 
                                                 
3 TransCanada Keystone Pipeline, L.P., “Application of TransCanada Keystone Pipeline L.P. for a Presidential Permit 
Authorizing the Construction, Operation, and Maintenance of Pipeline Facilities for the Importation of Crude Oil to be 
Located at the United States-Canada Border,” submitted to the U.S. Department of State, May 4, 2012, p. 39, available 
at http://keystonepipeline-xl.state.gov/proj_docs/permitapplication/index.htm. 
4 “TransCanada Expects $1-Billion Cost Escalation for Keystone XL Pipeline,” Canadian Press, February 17, 2011. 
Congressional Research Service 
3 
 Keystone XL Pipeline Project: Key Issues 
 
Figure 2. The Keystone XL Project and Gulf Coast Pipeline 
 
Source:
Keystone XL Pipeline Project: Key Issues 
 
Figure 2. The Keystone XL Project and Gulf Coast Pipeline 
 
Source: U.S.
 State Department, March 2013, Draft EIS for the Keystone XL 
Project. Section 1.2 “Overview of Proposed Project,” p. 1.2-3. 
Marketlink for Bakken Oil Production  
The Bakken Formation is a large unconventional petroleum and natural gas resource underlying 
parts of North Dakota, Montana, and the Canadian provinces of Saskatchewan and Manitoba. 
Although the region has been producing since 1951, it is only since 2006 that prices and 
technology have made it economic for industry to increase production. In March 2012, Bakken 
production exceeded 500,000 bpd the first time.5 However, production has been increasing 
steadily, with average daily output in August 2013 exceeding 900,000 bpd.6 To date, 
infrastructure to transport oil produced from the Bakken Formation has not kept up with the 
                                                 
5 North Dakota Department of Mineral Resources, “North Dakota Monthly Oil Production Statistics,” Bismarck, ND, 
November 2013, https://www.dmr.nd.gov/oilgas/stats/historicaloilprodstats.pdf. 
6 Ibid. 
Congressional Research Service 
4 
Keystone XL Pipeline Project: Key Issues 
 
increased production. Bakken crude oil is transported to refineries by rail and truck, in addition to 
more economical transport by pipeline.7 
As stated earlier, the proposed Keystone XL Project would include a lateral pipeline, the Bakken 
Marketlink, to provide crude oil transportation service from Baker, MT, to Cushing, OK, via the 
proposed Keystone XL Pipeline and from Cushing to Texas via the proposed Gulf Coast 
Pipeline.8 Keystone Marketlink9 estimates that the project will cost $140 million and have the 
ability to deliver approximately 100,000 bpd of crude oil to the proposed Keystone XL Pipeline.10 
Thus, of the Keystone Pipeline’s 830,000 bpd ultimate capacity, up to 12% has been set aside to 
transport Bakken crude oil. Keystone Marketlink currently has firm, long-term contracts to 
transport 65,000 bpd of the 100,000 bpd.11  
The Bakken contracts improve the economics for Keystone XL Pipeline, raising the amount of oil 
slated to flow through the pipeline.12 Lower transportation costs and access to new markets may 
support further investment in the Bakken. However, TransCanada is not the only company adding 
pipeline capacity in the region. Notably, Enbridge, another Canadian pipeline company, has 
proposed the Bakken Pipeline Project, which would add 120,000 bpd of transport capacity to 
move Bakken oil to Midwest markets.13 According to Enbridge, sufficient pipeline capacity has 
been slow to emerge in the region because “they’re smaller players in the Bakken. They are not 
able to make the 20-year commitments and it’s been a lot of work to get them to commit to the 
level that [is] required to underwrite a major project out of the Bakken.”14 Rail transport capacity 
has also been expanding.15 
Presidential Permit Applications  
Federal agencies ordinarily have no authority to site oil pipelines, even interstate pipelines.16 The 
primary siting authority for oil pipelines generally would be established under applicable state 
law. However, the construction, connection, operation, and maintenance of a pipeline that 
connects the United States with a foreign country requires executive permission conveyed 
through a Presidential Permit.  
                                                 
7 For more analysis, see CRS Report R42032, 
The Bakken Formation: Leading Unconventional Oil Development, by 
Michael Ratner et al. 
8 The Bakken Marketlink project is described in the August 2011 final EIS for the 2008 Presidential Permit application 
in Section 2.5.3, available at http://keystonepipeline-xl.state.gov/documents/organization/182012.pdf. 
9 Keystone Marketlink, LLC, is a wholly owned subsidiary of TransCanada Pipelines Limited. 
10 2012 Application of TransCanada Keystone Pipeline, L.P. for a Presidential Permit (footnote 3), p. 16. 
11 Ibid. 
12 Vanderklippe, 2011. 
13 Enbridge, “Bakken Pipeline Project—Project Overview,” press release, http://www.enbridge.com/
BakkenPipelineProjects/BakkenPipelineProjectUS.aspx. 
14 Lauren Krugel, “TransCanada attracts support for Montana-to-Oklahoma crude pipeline,” 
The Canadian Press, 
January 20, 2011. 
15 Energy Information Administration, “Rail Delivery of U.S. Oil and Petroleum Products Continues to Increase, but 
Pace Slows,” July 10, 2013, http://www.eia.gov/todayinenergy/detail.cfm?id=12031. 
16 This is in contrast to interstate natural gas pipelines, which, under Section 7(c) (15 USC §717f(c)) of the Natural Gas 
Act, must obtain a “certificate of public convenience and necessity” from the Federal Energy Regulatory Commission.  
Congressional Research Service 
5 
Keystone XL Pipeline Project: Key Issues 
 
Executive Order 13337 delegates to the Secretary the President’s authority to receive applications 
for Presidential Permits.17 Issuance of a Presidential Permit depends on a State Department 
determination that the project would serve the “national interest.” The term is not defined in the 
Executive Orders or elsewhere. Regarding its interpretation of the term, the State Department has 
asserted that, consistent with the President’s broad discretion in the conduct of foreign affairs, it 
has significant discretion in deciding the factors it will examine in making a national interest 
determination.18 The State Department will not necessarily evaluate the same factors for each 
project seeking a permit. However, for the 2008 Keystone XL Project, the State Department 
identified the following as key factors it considered when making determinations for previous 
applications for pipeline permits: 
•  Environmental impacts of the proposed projects; 
•  Impacts of the proposed projects on the diversity of supply to meet U.S. crude oil 
demand and energy needs; 
•  The security of transport pathways for crude oil supplies to the United States 
through import facilities constructed at the border relative to other modes of 
transport; 
•  Stability of trading partners from whom the United States obtains crude oil; 
•  Relationship between the United States and various foreign suppliers of crude oil 
and the ability of the United States to work with those countries to meet overall 
environmental and energy security goals; 
•  Impact of proposed projects on broader foreign policy objectives, including a 
comprehensive strategy to address climate change; 
•  Economic benefits to the United States of constructing and operating proposed 
projects; and 
•  Relationships between proposed projects and goals to reduce reliance on fossil 
fuels and to increase use of alternative and renewable energy sources.19 
The State Department identifies and considers environmental impacts of a project within the 
context of its obligation to comply with the National Environmental Policy Act (NEPA).20 NEPA 
requires federal agencies to consider the environmental impacts of an action (e.g., granting or 
denying a Presidential Permit) before proceeding with them and to inform the public of those 
potential impacts. 
                                                 
17 See Executive Order 13337, “Issuance of Permits With Respect to Certain Energy-Related Facilities and Land 
Transportation Crossings on the International Boundaries of the United States,” 69 
Federal Register 25299, May 5, 
2004, as amended, and Department of State Delegation of Authority No. 118-2 of January 26, 2006. The source of 
Permitting Authority for relevant Executive Orders is discussed further in the 
0. 
18 U.S. Department of State, “Final Environmental Impact Statement for the Proposed Keystone XL Project,” August 
2011, p. 1-4.  
19 Ibid. It was noted that this list is not exhaustive and that the State Department may consider additional factors in its 
national interest determination process. 
20 In processing Presidential Permit applications, the State Department is also explicitly directed to review the project’s 
compliance with the National Historic Preservation Act (16 U.S.C. §470f), the Endangered Species Act (16 U.S.C. 
§1531 et seq.), and Executive Order 12898 of February 11, 1994 (59 
Federal Register 7629), concerning environmental 
justice.  
Congressional Research Service 
6 
Keystone XL Pipeline Project: Key Issues 
 
The State Department has discretion in determining what additional factors it will examine to 
inform its national interest determination and, ultimately, whether a proposed project is in the 
national interest. However, the State Department is required to consult with and seek the views of 
the Secretaries of Defense, the Interior, Commerce, Transportation, Energy, and Homeland 
Security; the Attorney General; and the Administrator of the Environmental Protection Agency. 
The department is also required to solicit input from affected local, tribal, and state agencies and 
to invite public comment in arriving at its determination. 
Consideration of Environmental Impacts Under NEPA 
To ensure that environmental impacts are considered before final agency decisions are made, an 
Environmental Impact Statement (EIS) must be prepared for every major federal action that may 
have a “significant” impact upon the environment.21 With respect to the Presidential Permit 
applications submitted by TransCanada for Keystone XL, the State Department concluded that 
approval of a permit requires the preparation of an EIS.22  
Preparing an EIS is the responsibility of a designated “lead agency,” in this case, the State 
Department. In developing an EIS for a private party applicant (TransCanada) the State 
Department may use a third-party contractor. Consistent with regulations implementing NEPA, 
such a contractor is one that is selected by and works under the direction of the State Department, 
but is being paid by the applicant.23 
An EIS is generally prepared in two stages resulting in a draft and final EIS. Among other 
requirements, an EIS must include a statement of the purpose and need for an action, a 
description of all reasonable alternatives to meet that purpose and need, a description of the 
environment to be affected by those alternatives, and an analysis of the direct and indirect effects 
of the alternatives, including cumulative impacts.24 Accordingly, the State Department EIS must 
demonstrate that it has identified and considered potential environmental impacts of the entire 
pipeline project (including the construction, operation, and maintenance of the pipeline and its 
associated facilities), not just the facilities at the border crossing. 
For the 2008 Presidential Permit application, the State Department prepared a draft, supplemental 
draft, and final EIS. If the State Department modified its final EIS for the 2008 Presidential 
Permit application and continued its national interest determination, as it originally proposed in 
November 2011, it could have completed the NEPA process with only the publication of a 
supplemental final EIS that included analysis of new routes through Nebraska. However, denial 
of the Presidential Permit ended the NEPA process for the 2008 project. With the new Presidential 
                                                 
21 42 U.S.C. §4332(2)(C). 
22 U.S. Department of State, “Notice of Intent to Prepare a Supplemental Environmental Impact Statement (SEIS) and 
To Conduct Scoping and To Initiate Consultation Under Section 106 of the National Historic Preservation Act for the 
Proposed TransCanada Keystone XL Pipeline Proposed To Extend From Phillips, MT (the Border Crossing) to Steele 
City, NE,” 77 
Federal Register 36032, June 15, 2012. 
23 U.S. Department of State, “Interim Guidance for the Use of Third-Party Contractors in Preparation of Environmental 
Documents by the Department of State,” available online at http://www.state.gov/documents/organization/190304.pdf. 
24 In preparing an EIS associated with a Presidential Permit, NEPA regulations promulgated by both the Council of 
Environmental Quality (CEQ) and the State Department would apply. CEQ regulations implementing NEPA (under 40 
C.F.R. §§1500-1508) apply to all federal agencies. NEPA regulations applicable to State Department actions, which 
supplement the CEQ regulations, are found at 22 C.F.R. Part 161. 
Congressional Research Service 
7 
Keystone XL Pipeline Project: Key Issues 
 
Permit application, the State Department was required to begin a new NEPA process and, 
eventually, determine whether that project would serve the national interest. 
To prepare an EIS, the State Department is required to obtain input from “cooperating agencies,” 
which include any agency with jurisdiction by law or with special expertise regarding any 
environmental impact associated with the project.25 Cooperating agencies for the Keystone XL 
Project include the U.S. Environmental Protection Agency (EPA); the Department of 
Transportation’s Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of 
Pipeline Safety (OPS); the Department of the Interior’s Bureau of Land Management, U.S. Fish 
and Wildlife Service, and National Park Service; the U.S. Army Corps of Engineers; the U.S. 
Department of Agriculture’s Farm Service Agency, Natural Resources Conservation Service, and 
Rural Utilities Service; the Department of Energy’s Western Area Power Administration; and state 
environmental agencies. 
On March 1, 2013, the State Department released the draft EIS for the 2012-proposed Keystone 
XL Project as a supplement to the final EIS prepared for the 2008 Presidential Permit application 
(released in August 2011).26 The draft EIS evaluates potential impacts associated with the route 
from Montana to Steele City, NE, that avoids the Nebraska Sand Hills and excludes the proposed 
Gulf Coast Project. According to the State Department, the 2013 draft EIS includes a 
“comprehensive review of the new route in Nebraska as well as any significant new 
circumstances or information that is now available on the largely unchanged route in Montana 
and South Dakota. It also expands and updates information that had been included in the 2011 
Final Environmental Impact Statement that was prepared for the previous Keystone XL 
application.”27 
EPA Rating of the Environmental Impact Statement 
In addition to its role as a cooperating agency, EPA is also required to review and comment 
publicly on the EIS and rate both the adequacy of the EIS itself and the level of environmental 
impact of the proposed project.28 Rating the EIS takes place after the draft is issued. The EIS 
could be rated either “Adequate,” “Insufficient Information,” or “Inadequate.” EPA’s rating of a 
project’s environmental impacts may range from “Lack of Objections” to “Environmentally 
Unsatisfactory.” In rating the impact of the action itself, EPA would specify one of the following: 
“Lack of Objections,” “Environmental Concerns,” “Environmental Objections,” or 
                                                 
25 40 C.F.R. §1508.5. Also, Executive Order 13337 directs the Secretary to refer an application for a Presidential Permit 
to other specifically identified federal departments and agencies on whether granting the application would be in the 
national interest. 
26 See U.S. Department of State, “New Keystone XL Pipeline Application” webpage at http://www.keystonepipeline-
xl.state.gov/. On March 8, 2013, EPA listed the draft EIS in its weekly “Environmental Impacts Statements; Notice of 
Availability,” in the 
Federal Register, see 78 
Federal Register 15012. The State Department refers to the EIS released 
in March 2013 as a “Draft Supplemental” EIS. This reference apparently reflects the fact that the 2013 draft EIS draws 
largely from (or supplements) documentation and analysis included in the final EIS issued for the Keystone XL Project 
in 2011. However, for purposes of NEPA compliance, the submission of a new permit application in May 2012 started 
the NEPA process anew. While it may draw from the 2011 final EIS, the 2013 draft EIS is a new NEPA document—
not a supplement to an EIS prepared for a different, albeit similar, Presidential Permit application. 
27 See footnote 26. 
28 For more information, see the U.S. Environmental Protection Agency’s “Environmental Impact Statement (EIS) 
Rating System Criteria” at http://www.epa.gov/compliance/nepa/comments/ratings.html. 
Congressional Research Service 
8 
Keystone XL Pipeline Project: Key Issues 
 
“Environmentally Unsatisfactory.” The federal agency, in this case the Department of State, 
would then be required to respond to EPA’s rating, as appropriate.  
The State Department accepted public comments on the draft EIS until April 22, 2013. “Public” 
comments could come from a range of interested stakeholders, including local, state, tribal, or 
federal agencies. EPA reviewed the draft EIS and submitted comments on it to the State 
Department.29 EPA’s comments are on its assessment of the proposed project’s impacts and the 
adequacy of the draft EIS itself. It rated the draft EIS as “EO-2” (Environmental Objections—
Inadequate Information). EPA states that, while the agency believes the draft EIS strengthens the 
analysis presented to date in the NEPA process, it recommends several improvements to the 
analysis of the proposed project’s impacts and to mitigate certain impacts. Specifically, EPA 
recommended the following:  
•  
Greenhouse Gas Emissions—use monetized estimates of the social cost of the 
greenhouse gas (GHG) emissions from a barrel of oil sands crude compared to 
average U.S. crude. EPA noted that TransCanada’s market analysis and its 
conclusion that oil sands crude will find a way to market with or without the 
Project are central to the draft EIS conclusions regarding the Project’s potential 
GHG emissions. As a result, the agency asserts that the final EIS should be based 
on an updated energy-economic modeling effort. The final EIS should also 
explore specific ways the United States might work with Canada to promote 
efforts to reduce GHG emissions from oil sands crude production. 
•  
Pipeline Safety—in the wake of a 2010 Enbridge spill of oil sands crude in 
Michigan, incorporate into its permit conditions various steps intended to 
improve potential oil spill response and cleanup. 
•  
Pipeline Routes Across the Ogallala Aquifer—provide in the final EIS more 
detail on pipeline route alternatives that would parallel the existing Keystone 
Pipeline, and likely further reduce potential environmental impacts to 
groundwater resources, or explain why these alternatives were not considered.  
•  
Community and Environmental Justice Impacts—document in its permit 
conditions TransCanada’s commitments to conduct cleanup and restoration and 
to provide alternative water supplies to affected communities in the event of an 
oil discharge affecting surface waters or groundwater. 
Now that EPA and other public and agency comments have been submitted, the State Department 
must respond to those comments and possibly modify the draft EIS to address them. After it does 
so, the State Department may issue a final EIS. The time it may take the department to do so will 
depend on various factors, including the scope and the nature of the comments to which it must 
respond. After the final EIS is issued, the State Department may begin the 90-day period to make 
the national interest determination. 
Major milestones in the NEPA process, for both the 2008 and 2012 Presidential Permit 
applications, are listed in 
Table 1, below. (For discussion of NEPA milestones associated with the 
2008 permit application, see 
Appendix B.) 
                                                 
29 Letter from the U.S. Environmental Protection Agency’s Cynthia Giles, Assistant Administrator for Enforcement and 
Compliance Assurance to Jose Fernandez and Kerri-Ann Jones, Assistant Secretaries, U.S. Department of State, 
available online at http://epa.gov/compliance/nepa/keystone-xl-project-epa-comment-letter-20130056.pdf. 
Congressional Research Service 
9 
Keystone XL Pipeline Project: Key Issues 
 
Table 1. Milestones in the NEPA process for the Keystone XL Project 
Federal, State, and Company Actions Relevant to the NEPA Compliance Process 
Date Party 
Description 
NEPA Compliance Milestones Relevant to TransCanada’s 2008 Presidential Permit Application 
Sept. 
TransCanada 
Application for a Presidential Permit submitted to the State Department to 
2008 
authorize the Keystone XL Pipeline Project.  
Apr. 16, 
State 
Draft EIS for the proposed Keystone XL Pipeline project released for public 
2010 
Department 
comment. 
July 16, 
EPA 
Agency rates the draft EIS as “Inadequate,” noting that potential y significant 
2010 
impacts were not evaluated, that more information and analysis was needed, and 
the draft EIS would need revision and again be made available for public review. 
Apr. 15, 
State 
Supplemental draft EIS issued. 
2011 
Department 
June 6, 
EPA 
Agency rates the supplemental draft EIS as having “Insufficient Information” and 
2011 
the action as having “Environmental Objections”; recommends additional 
analysis on a range of issues to be addressed in the final EIS. 
Aug. 26, 
State 
Final EIS issued; 90-day public comment related to the national interest 
2011 
Department 
determination process begins. 
Nov. 22, 
Governor of 
Signed legislation passed during special session directing the Nebraska 
2011 
Nebraska 
Department of Environmental Quality (DEQ) to col aborate with the State 
Department to gather information necessary for a supplemental EIS.  
Nov. 
Nebraska 
Agencies begin to negotiate a Memorandum of Understanding (MOU) regarding 
2011 
DEQ/State 
their col aboration on the supplemental final EIS. Nebraska DEQ hires a 
Department 
contractor to delineate the “Sand Hills” region alternative routes must avoid. 
Dec. 23, 
Congress 
The Temporary Payrol  Tax Cut Continuation Act of 2011 (P.L. 112-78) 
2011 
requires the Secretary to issue a permit for the project within 60 days, unless 
the President determines the project is not in the national interest.  
Jan. 18, 
State 
Department denies the Presidential Permit for Keystone XL asserting that the 
2012 
Department 
60-day deadline under P.L. 112-78 did not provide sufficient time to obtain 
information necessary to assess the project’s national interest. 
Feb. 3, 
State 
Formal permit denial issued; State Department and Nebraska DEQ suspend 
2012 
Department 
work on MOU regarding a supplemental EIS. 
Feb. 
TransCanada 
State Department is informed of the company’s intent to continue with the Gulf 
2012 
Coast Project (a pipeline that would 
not require an EIS if constructed apart from 
the lager project that requires authorization via a Presidential Permit). 
April 19, 
TransCanada 
Submits to Nebraska DEQ, 
Initial Report Identifying Alternative and Preferred 
2012 
Corridors for Nebraska Reroute; public meetings on newly proposed routes fol ow. 
NEPA Compliance Milestones Relevant to TransCanada’s 2013 Presidential Permit Application 
May 4, 
TransCanada 
Application for a Presidential Permit submitted to the State Department to 
2012 
authorize the reconfigured Keystone XL Pipeline Project with a Nebraska route. 
June, 15, 
State 
Publishes in the 
Federal Register: “Notice of Intent To Prepare a Supplemental 
2012 
Department 
Environmental Impact Statement (SEIS) and To Conduct Scoping and To Initiate 
Consultation Under Section 106 of the National Historic Preservation Act for 
the Proposed TransCanada Keystone XL Pipeline Proposed To Extend From 
Phillips, MT (the Border Crossing) to Steele City, NE.” 
March 1, 
State 
Releases draft EIS for the 2012 Keystone XL Project for public comment. 
2013 
Department 
Congressional Research Service 
10 
Keystone XL Pipeline Project: Key Issues 
 
Date Party 
Description 
April 22, 
State 
Deadline for submission of public comments on the draft EIS. 
2013 
Department 
April 23, 
EPA 
The proposed project and draft EIS is rated “EO-2,” meaning EPA has 
2012 
“Environmental Objections,” regarding the project’s impacts, and that the draft 
EIS includes “Insufficient Information”; recommends mitigation efforts to address 
project impacts and additional analysis that should be included in the final EIS. 
Source: Congressional Research Service, based on a review of events during, and affecting, the NEPA process 
conducted for the 2008 and 2012 Presidential permit applications for the Keystone XL Project. 
The National Interest Determination 
Generally, after a final EIS is issued, a federal agency may issue a final record of decision (ROD) 
for the project. However, for a Presidential Permit, issuance of the final EIS represents the 
beginning of a 90-day public review period during which the State Department gathers 
information from those necessary to inform its national interest determination. Ultimately, a 
decision regarding issuance of a Presidential Permit for a pipeline project would be reflected in a 
combined “Record of Decision and National Interest Determination,” issued by the State 
Department.30 That document, required under elements of both NEPA and E.O. 11424, formalizes 
the selection of a project alternative.  
During the 90-day public review period for the 2008 Presidential Permit application, the State 
Department held public meetings in each of the six states through which the proposed pipeline 
would pass and in Washington, DC.31 The meetings were intended to give members of the public 
additional opportunity to voice their opinions on issues they thought should be taken into account 
in determining whether granting or denying the Presidential Permit would be in the national 
interest. During the review period, the State Department received input from state, local, and 
tribal officials as well as members of the public. 
On November 10, 2011, during the public review period for the 2008 permit application, the State 
Department stated that it received public comments on a wide range of issues including the 
project’s potential impact on jobs, pipeline safety, health concerns, the societal impact of the 
project, and oil extraction in Canada.32 Concern regarding the proposed pipeline route through the 
Sand Hills area of Nebraska was identified as one of the most common issues raised. Comments 
regarding that pipeline route were consistent with the environmental impacts identified in the 
final EIS with regard to the unique combination of characteristics of the Sand Hills region (e.g., a 
high concentration of wetlands of special concern, a sensitive ecosystem, and extensive areas of 
very shallow groundwater). Further, the Nebraska legislature convened a special session to 
consider the legislation that would establish regulations applicable to pipeline siting within the 
state.  
                                                 
30 For example, see U.S. Department of State, “Record of Decision and National Interest Determination, TransCanada 
Keystone Pipeline, LP Application for Presidential Permit,” February 25, 2008, http://www.cardnoentrix.com/keystone/
project/SignedROD.pdf. 
31 U.S. Department of State press release, “Keystone XL Final Environmental Impact Statement Released; Public 
Meetings Set,” August 26, 2011, http://www.state.gov/r/pa/prs/ps/2011/08/171082.htm. 
32 U.S. Department of State, “Keystone XL Pipeline Project Review Process: Decision to Seek Additional 
Information,” Media Note, PRN 2011/1909, Office of the Spokesperson, November 10, 2011. 
Congressional Research Service 
11 
Keystone XL Pipeline Project: Key Issues 
 
Facing the prospect of new state pipeline siting regulations applicable to the Sand Hills, together 
with the concern about the Keystone XL pipeline’s specific “preferred” route, the State 
Department announced that it needed additional information about alternative pipeline routes 
avoiding the environmentally sensitive Sand Hills area in Nebraska before moving forward with 
its national interest determination.33 Although the State Department did not decide that 
environmental issues led to a determination that the proposed project was not in the national 
interest, environmental issues identified in the final EIS, and further stressed in public comments, 
led to its decision to delay that determination until it gathered this information. In a concurrent 
press release, President Obama stated 
Because this permit decision could affect the health and safety of the American people as 
well as the environment, and because a number of concerns have been raised through a 
public process, we should take the time to ensure that all questions are properly addressed 
and all the potential impacts are properly understood.34 
Subsequently, TransCanada announced that it would work with the State Department and the 
Nebraska Department of Environmental Quality (DEQ) to conduct an environmental assessment 
to define the best location for the Keystone XL pipeline in Nebraska. Further, the company stated 
that it would “cooperate with these agencies and provide them with the information they need to 
complete a thorough review that addresses concerns regarding the Sandhills region.”35 
As noted previously, on December 23, 2011, the Temporary Payroll Tax Cut Continuation Act of 
2011 was enacted (P.L. 112-78). Under Section 501, “Permit for Keystone XL Pipeline,” the 
Secretary was required to grant the Presidential Permit for the Keystone XL pipeline project 
within 60 days, unless the President determined that the pipeline would not be in the national 
interest. On January 18, 2012, the State Department announced, with the President’s concurrence, 
that the Presidential Permit for the proposed Keystone XL Pipeline would be denied at that time 
because it was determined not to serve the national interest. That recommendation “was 
predicated on the fact that the Department does not have sufficient time to obtain the information 
necessary to assess whether the project, in its current state, is in the national interest.”36  
The process of determining a project’s national interest illustrates the distinctly different, yet 
interrelated requirements applicable to the NEPA process and the Presidential Permit application 
process. Under NEPA, the State Department (or any other federal agency considering an action) 
must fully assess the environmental consequences of an action and potential project alternatives 
before making a final decision. NEPA does not prohibit a federal action that has adverse 
environment impacts; it requires only that a federal agency be fully 
aware of and 
consider those 
adverse impacts before selecting a final project alternative. That is, NEPA is intended to be part of 
the decision-making process, not dictate a particular outcome. By contrast, issuance of a 
Presidential Permit is predicated on the Secretary’s finding that the proposed project would serve 
the national interest. Milestones in the State Department’s process to make its national interest 
determination for the 2008 permit application are summarized in 
Table 2.                                                  
33 Ibid. 
34 The White House, Office of the Press Secretary, “Statement by the President on the State Department’s Keystone XL 
Pipeline Announcement,” November 10, 2011. 
35 See TransCanada Corp., Media Advisory, “State of Nebraska to Play Major Role in Defining New Keystone XL 
Route Away From the Sandhills,” November 14, 2011, available at http://www.transcanada.com/5896.html.  
36 U.S. Department of State, Media Note, “Denial of the Keystone XL Pipeline Application,” January 18, 2012, 
available at http://www.state.gov/r/pa/prs/ps/2012/01/181473.htm.  
Congressional Research Service 
12 
Keystone XL Pipeline Project: Key Issues 
 
Table 2. Milestones in National Interest Determination Process for the 2008 
Keystone XL Pipeline 
Date Party 
Description 
Aug.-
State 
The 90-day public review period for national interest determination begins; 
Oct. 
Department 
State Department holds public meetings in the six states through which the 
2011 
proposed pipeline would pass and in Washington, DC. 
Oct. 
Congress 
Fourteen Members of Congress request the State Department Office of 
2011 
Inspector General (IG) to investigate the department’s handling of the EIS and 
national interest determination for the Keystone XL project. 
Oct. 24, 
Governor of 
The governor calls the Nebraska legislature into a special session to determine if 
2011 
Nebraska 
siting legislation can be crafted and passed for pipeline routing in Nebraska.  
Nov. 4, 
State 
IG announces it is initiating a special review to determine to what extent the 
2011 
Department 
department and all other parties involved complied with Federal laws and 
regulations relating to the Keystone XL pipeline permit process. 
Nov. 10, 
State 
The agency announces that additional information will be needed regarding 
2011 
Department 
alternative pipeline routes that would avoid the Nebraska Sand Hills before 
national interest determination can be made. Officials suggest that analysis 
needed to prepare the supplemental EIS, including additional public comment, 
could be completed as early as the first quarter of 2013. 
Nov. 14, 
TransCanada 
The company announces that it will work with the Nebraska Department of 
2011 
Environmental Quality (DEQ) to identify a potential pipeline route that would 
avoid the Nebraska Sand Hills. 
Nov. 22, 
Governor of 
The governor signs legislation passed during the special session directing the 
2011 
Nebraska 
Nebraska DEQ to work col aboratively with the State Department to gather 
information necessary for a supplemental EIS.  
Nov. 
Nebraska 
The agencies begin negotiating a Memorandum of Understanding (MOU) to 
2011 
DEQ/State 
col aborate on the supplemental EIS. Nebraska DEQ hires a contractor to 
Department 
delineate the “Sand Hills” region that alternative routes must avoid. 
Dec. 23, 
Congress 
The Temporary Payrol  Tax Cut Continuation Act of 2011 (P.L. 112-78) 
2011 
requires the Secretary to issue a permit for the project within 60 days, unless 
the President determines the project is not in the national interest. 
Jan. 18, 
State 
The agency announces that it will deny the Keystone XL permit. 
2012 
Department 
Source: Congressional Research Service, based on a review of events during, and affecting, the State Department’s 
national interest determination for the 2008 Presidential Permit application for the Keystone XL pipeline project. 
State Siting and Additional Environmental Requirements 
As the NEPA compliance process for TransCanada’s permit application moves forward, it is 
helpful to understand the distinction between what is required under NEPA itself and what may be 
required pursuant to other environmental requirements identified within the context of the NEPA 
process. NEPA itself requires federal agencies to identify the environmental impacts of an action 
before proceeding with them and to involve the public in that process when environmental 
impacts are significant. In the process of identifying a proposed project’s environmental impacts, 
within the context of preparing the EIS, the lead agency should identify any compliance 
obligations (licenses, permits, or approvals) established under additional state, tribal, and federal 
law applicable to the portion of the project constructed in the United States. 
Congressional Research Service 
13 
Keystone XL Pipeline Project: Key Issues 
 
As noted above, the federal government does not currently exercise siting authority over oil 
pipelines. Instead, pipeline siting for the Keystone XL Project must comply with any applicable 
state law—which can vary from state to state. South Dakota, for example, required TransCanada 
to apply for a permit for the Keystone XL Project from the state public utility commission, which 
issued the permit on April 25, 2010.37 Montana requires a certificate from the state’s Department 
of Environmental Quality.38  
At the time of TransCanada’s initial application for a Presidential Permit, Nebraska did not have 
any permitting requirements that applied specifically to the construction and operation of oil 
pipelines, although a state statute did include an “eminent domain” provision to grant eminent 
domain authority to oil pipeline companies unable to obtain the necessary property rights from 
the relevant property owners.39 However, due to the controversy surrounding the Keystone XL 
Project, Nebraska’s governor called a special session of its legislature to enact legislation to assert 
state authority over pipeline siting. Subsequently, the state enacted two laws—one that would 
affect the siting of the Keystone XL pipeline and one that outlines procedures for siting any future 
oil pipeline in Nebraska.40 The latter requires an oil pipeline carrier proposing to construct a 
major oil pipeline in Nebraska to file an application with the state’s Public Service Commission 
and receive approval before beginning construction. Additionally, the law authorized the 
commission to follow certain procedures before deciding whether a proposed oil pipeline would 
serve the public interest. 
Although there are limited federal requirements applicable to oil pipeline 
siting, there are 
numerous local, state, tribal, and federal requirements applicable to pipeline construction, 
operation, and maintenance. For example, the 2013 draft EIS for the Keystone XL Project lists 
major permits, licenses, approvals, and consultation requirements for the proposed project that 
would be required by federal, state, and local agencies prior to implementation of the project.41 
Following are selected requirements included on that list: 
•  The U.S. Army Corps of Engineers—issuance of a permit for sections of the 
project that require placement of dredge and fill material in waters of the United 
States, including wetlands (pursuant to Section 404 of the Clean Water Act), or 
for pipeline crossings of navigable waters (pursuant to Section 10 of the Rivers 
and Harbors Act);  
•  The Environmental Protection Agency—review and issue National Pollutant 
Discharge Elimination System permits for the discharge of pollutants in state 
waters (pursuant to Section 402 of the Clean Water Act);  
•  The Bureau of Land Management—grant temporary use permits for portions of 
the project that would encroach on federal lands;  
                                                 
37 South Dakota Public Utilities Commission, Final Decision and Order; Notice of Entry Before the Public Utilities 
Commission of the State of South Dakota, In the Matter of the Application by TransCanada Keystone Pipeline, LP for 
a Permit Under the South Dakota Energy Conversion and Transmission Facilities Act to Construct the Keystone 
Pipeline Project, HP07-001, http://puc.sd.gov/commission/orders/HydrocarbonPipeline/2008/hp07-001.pdf. 
38 Montana Major Facility Siting Act, Title 75, Chapter 20. 
39 Nebraska Rev. Stat. §57-1101. 
40 See Nebraska governor Dave Heineman’s November 23, 2011, statement “Common Sense Solution,” available at 
http://www.governor.nebraska.gov/columns/2011/11/23_solution.html.  
41 U.S. Department of State, March 2013, Draft EIS, Section 1.9, “Permits, Approvals, and Regulatory Requirements.” 
Congressional Research Service 
14 
Keystone XL Pipeline Project: Key Issues 
 
•  U.S. Fish and Wildlife Service—consider impacts to federally listed endangered 
species (pursuant to the Endangered Species Act) and provide a Biological 
Opinion if the project is likely to adversely affect federally listed species. 
•  Multiple state/county agencies—consult on and/or consider issuance of permits 
for projects that cross navigable waters or state highways, or involve work 
potentially affecting state streams, cultural resources, or natural resources.  
The time it took to complete the NEPA process was a focus of attention for the 2008 Presidential 
Permit application. However, for past pipeline projects, obtaining all required local, state, tribal, 
and federal permits, approvals, and licenses took a similar amount of time. By way of example, 
for the Alberta Clipper pipeline project (another oil sands pipeline) completion of the NEPA 
process, the national interest determination, and issuance of a Presidential Permit took 
approximately two years. Obtaining the necessary permits, approvals, and licenses for 
construction of the pipeline took an additional two years. 
Legislative Efforts to Change Permitting Authority 
In light of the State Department’s denial of the 2008 permit application for the Keystone XL 
Project, some in Congress have sought alternative means to support development of the pipeline. 
There were a number of legislative proposals in the 112th Congress to change the federal 
permitting authority for the pipeline. H.R. 3548 would have transferred the permitting authority 
over the Keystone XL Project from the State Department to the Federal Energy Regulatory 
Commission (FERC), requiring the commission to issue a permit for the project within 30 days of 
enactment.42 Other proposals, such as H.R. 3811 and S. 3445, would have directly shifted 
permitting authority to Congress, effectively approving upon enactment the permit applications 
filed by TransCanada in 2008 and 2012, respectively.  
Similar legislation has been proposed in the 113th Congress, including legislative proposals from 
the prior Congress that have been reintroduced. The Energy Production and Project Delivery Act 
of 2013 (S. 17) would eliminate the Presidential Permit requirement for the reconfigured 
Keystone XL Project. The Keystone for a Secure Tomorrow Act (H.R. 334) and a Senate bill to 
approve the Keystone XL Project (S. 582) would directly approve the Keystone XL Project under 
the authority of Congress to regulate foreign commerce. The Northern Route Approval Act (H.R. 
3) would eliminate the Presidential Permit requirement for Keystone XL and require issuance of 
permits for water crossings by the Army Corps of Engineers within 90 days of an application, 
among other provisions. The Senate passed an amendment to the Fiscal 2014 Senate Budget 
Resolution (S.Con.Res. 8) that would provide for the approval and construction of the Keystone 
XL Project (S.Amdt. 494). The North American Energy Infrastructure Act (H.R. 3301) would 
transfer permit authority for oil pipelines from the State Department to the Department of 
Commerce; would require agencies to approve applications within 120 days of submission unless 
they determine the project is not in the national 
security interest (as opposed to “national interest” 
more generally); and would eliminate the need for new or revised Presidential Permits for 
pipeline modifications (e.g., reversal of flow direction), among other provisions. 
                                                 
42 The Surface Transportation Extension Act of 2012, Part II (H.R. 4348), which passed in the House on April 18, 
2012, also contained these provisions, but they were subsequently dropped from the bill in conference committee with 
the Senate. 
Congressional Research Service 
15 
Keystone XL Pipeline Project: Key Issues 
 
Changing, or eliminating altogether, the State Department’s role in issuing cross-border 
infrastructure permits may raise questions about the President’s executive authority (further 
discussed in
 Appendix A). In response to H.R. 3548, for example, the State Department’s key 
official on Keystone XL testified before Congress: 
The legislation raises serious questions about existing legal authorities, questions the 
continuing force of much of the federal and all of the state and local environmental and land 
use management authority over the pipeline, and overrides foreign policy and national 
security considerations implicated by a cross border permit, which are properly assessed by 
the State Department.43 
Such proposals may also raise some administrative and legal challenges for FERC or other 
federal agencies. A senior FERC official testified that a proposal like H.R. 3548 would not 
provide enough time for an “adequate” public record, provides no clear authority for enforcing 
measures required in the EIS, does not articulate a process for authorizing alterations to the 
pipeline route, and is unclear about permits required from other federal agencies, among other 
concerns.44 For additional analysis of associated legal issues, see CRS Report R42124, 
Proposed 
Keystone XL Pipeline: Legal Issues, by Adam Vann, Kristina Alexander, and Kenneth R. Thomas; 
and CRS Report R43261, 
Presidential Permits for Border Crossing Energy Facilities, by Adam 
Vann and Paul W. Parfomak. 
Given the State Department’s initial permit denial, and opposition from various environmental 
groups and stakeholders along the pipeline route, legal challenges are a possibility. However, in 
the event of a challenge based on an environmental issue, the distinction between State 
Department actions required under NEPA and those required under its authority to issue a 
Presidential Permit would be relevant. NEPA does not create a private right of action. Instead, 
judicial challenges to a federal agency action under NEPA are brought pursuant to the 
Administrative Procedure Act (APA, 5 U.S.C. §§706 et seq.). Presidential actions, however, are 
not subject to judicial review under the APA.45 That is, the final agency action reflected in an 
ROD is subject to judicial review, but the State Department’s national interest determination, 
made under its authority to issue a Presidential Permit, is not. For more analysis of the State 
Department’s authority to grant a Presidential Permit, see 
Appendix A.  
Arguments For and Against the Pipeline 
Proponents of the Keystone XL Pipeline, including Canadian agencies and U.S. and Canadian 
petroleum industry stakeholders, base their arguments supporting the pipeline primarily on 
increasing the security and diversity of the U.S. petroleum supply and economic benefits, 
                                                 
43 Kerri-Ann Jones, Assistant Secretary of State for Oceans and International Environmental and Scientific Affairs, 
Testimony before the House Energy and Commerce Committee, Subcommittee on Energy and Power Hearing on the 
North American Energy Access Act, January 25, 2012. 
44 Jeff Wright, Director, Office of Energy Projects, Federal Energy Regulatory Commission, Testimony before the 
House Energy and Commerce Committee, Subcommittee on Energy and Power Hearing on the North American Energy 
Access Act, January 25, 2012. 
45 While the APA’s definition of “agency” does not specifically exclude or include the president, the Supreme Court 
has held that exercises of presidential authority are not subject to judicial review because the president is not an agency 
(
Dalton v. Specter, 511 U.S. 462, 470 (1994)). The Court has also held that the APA does not apply to the president 
based on separation of powers principles (
Franklin v. Massachusetts, 505 U.S. 788, 800-01 (1992)). 
Congressional Research Service 
16 
Keystone XL Pipeline Project: Key Issues 
 
especially jobs. Pipeline opponents are generally environmental organizations and community 
groups. Their concerns stem from issues that can be broadly categorized as the pipeline’s global 
or community environmental impacts. “Global” impacts stem primarily from concern regarding 
the lifecycle greenhouse gas (GHG) emissions associated with the development of Canadian oil 
sands, compared to conventional oil or renewable fuels.46 Although the concern regarding GHG 
emissions is focused primarily on the extraction process, opponents also argue that use of the oil 
sands crude promotes continued U.S. dependency on fossil fuels. Concern over adverse 
community impacts of the pipeline stems primarily from the risk of a potential release of heavy 
crude, and the operators’ ability to respond to a release, particularly in remote areas. Communities 
along the pipeline route are also concerned about impacts associated with the pipeline’s 
construction and long-term use on private land—particularly its potential to affect farming and 
cattle grazing. 
Impact on U.S. Energy Security 
In its Presidential Permit application, TransCanada asserts that constructing the proposed 
Keystone XL Pipeline is in the U.S. national interest to maintain adequate crude oil supplies for 
U.S. refineries. The application argues that the pipeline will allow U.S. refiners to substitute 
Canadian supply for other foreign crude supply and to obtain direct pipeline access to secure and 
growing Canadian crude output. In particular, the application asserts that the pipeline would allow 
the United States to decrease its dependence on crude oil from Mexico and Venezuela, the two 
largest oil exporters into the U.S. Gulf Coast.47 Consistent with this argument, some proposals 
would seek to ensure that any crude oil and bitumen transported by the Keystone XL Pipeline, or 
any resulting refined products, would have to remain in U.S. markets subject to a presidential 
waiver allowing foreign export.48 Depending upon the circumstances, however, such restrictions 
could raise concerns with respect to international trade agreements, among other considerations. 
Energy security arguments have taken on additional weight in light of the recent geopolitical 
tensions in the Middle East and North Africa. However, it is worth noting that even if Keystone 
XL is built, prices for the crude oil it carries as well as for domestically produced oil from 
elsewhere will continue to be affected by international events. The oil market is globally 
integrated and events in major producer and consumer countries can affect prices everywhere.49 
For example, the disruption of Libyan supply in early 2011 contributed to higher crude oil prices 
in the United States, even though the United States imported almost no oil from Libya before the 
unrest broke out.50  
                                                 
46 For additional analysis of greenhouse gas issues associated with Canadian oil sands crudes, see CRS Report R42537, 
Canadian Oil Sands: Life-Cycle Assessments of Greenhouse Gas Emissions, by Richard K. Lattanzio.  
47 TransCanada Keystone Pipeline, L.P., September 19, 2008, pp. 6-8. 
48 On February 7, 2012, the House Energy and Committee rejected an amendment to H.R. 3548 offered by 
Representative Edward Markey containing export restrictions. 
49 This is the case unless the oil is stranded due to transport bottlenecks. Ironically, the bottleneck for crude oil flowing 
south from the Midwest to the Gulf Coast—which Keystone XL would help alleviate—helped insulate Midwestern 
crude oil prices from the impacts of unrest in the Middle East and North Africa. However, as is discussed below, this 
may have benefited Midwestern refiners but probably did not significantly reduce costs for U.S. consumers.  
50 For more about this, see CRS Report R41683, 
Middle East and North Africa Unrest: Implications for Oil and 
Natural Gas Markets, by Michael Ratner. 
Congressional Research Service 
17 
Keystone XL Pipeline Project: Key Issues 
 
Canadian Oil Imports in the Overall U.S. Supply Context51 
Gross U.S. imports of crude oil and petroleum products averaged 10.6 million bpd (Mbpd) in 
2012.52 U.S. oil exports averaged 3.2 Mbpd (almost entirely refined petroleum products), leaving 
net imports at 7.4 Mbpd.53 U.S. net imports have fallen by 5.1 Mbpd or 41% since they peaked in 
2005 as a result of lower total oil consumption and higher domestic production. Some of this 
decline could be mitigated in the near term as oil demand recovers from the recession. However, 
there is increasing sentiment among forecasters that U.S. oil imports have passed their high water 
mark already and may remain relatively flat or fall in the foreseeable future.54 
Among the largest sources of U.S. gross oil imports are Canada (2.9 Mbpd), the Persian Gulf (2.1 
Mbpd), Mexico (1.0 Mbpd), and Venezuela (0.9 Mbpd). Imports from the latter two sources have 
decreased in recent years in part due to lower need for imports described above and in part due to 
developments in those countries.
 Mexican production has been falling since 2004 because new oil 
developments have not been able to offset depletion at Mexico’s giant Cantarell field. Imports 
from Venezuela, another key source of U.S. imports, have also fallen. Venezuelan production 
never fully recovered after a strike at its national oil company, 
Petróleos de Venezuela, in 2002-
2003. Venezuelan production today is nearly 1 Mbpd less than that achieved in 2001. In recent 
years, Venezuela has also been trying to diversify business away from the United States, for 
example, by increasing exports to China.55 
Meanwhile, Canadian production and exports to the United States have increased, primarily due 
to growing output from the oil sands in western Canada. Energy markets in the United States and 
Canada are well integrated by pipeline infrastructure; nearly all Canadian energy exports go to the 
United States.56 Canadian oil production has increased about 0.7 Mbpd since 2005 and exports to 
the United States have increased by 0.77 Mbpd (see
 Table 3).57 Some expect Canadian oil 
production to grow by nearly 2 Mbpd by 2025 due to increased output from the oil sands.58 
                                                 
51 For a primer on the oil market, see CRS Video Brief 
Introduction to the Oil Market, at http://www.crs.gov/analysis/
Pages/WVB00002.aspx.  
52 All data in this section are from the U.S. Energy Information Administration’s (EIA’s) 
Petroleum & Other Liquids (http://www.eia.gov/petroleum/data.cfm), 
International Energy Statistics (http://tonto.eia.doe.gov/cfapps/ipdbproject/
IEDIndex3.cfm), and the 
Short Term Energy Outlook (http://www.eia.gov/forecasts/steo/). 
53 For context, the United States consumed 18.8 Mbpd in 2011, more than 20% of the world’s oil market. Net imports 
are gross or total imports less total exports. This section will focus on gross imports, though it should be noted that 
among U.S. petroleum exports about 0.2 Mbpd of petroleum products go to Canada and 0.4 Mbpd to Mexico. 
54 For more analysis, see CRS Report R42465, 
U.S. Oil Imports and Exports, by Robert Pirog. 
55 U.S. Energy Information Administration, “Country Analysis Brief: Venezuela,” February 2010, 
http://www.eia.doe.gov/emeu/cabs/Venezuela/Oil.html. 
56 For further analysis of U.S.-Canada energy trade, see CRS Report R41875, 
The U.S.-Canada Energy Relationship: 
Joined at the Well, by Paul W. Parfomak and Michael Ratner. 
57 As in the United States, Canadian consumption fell due to economic downturn. This allowed the increment in exports 
to be higher than the increment in production.  
58 Canadian Association of Petroleum Producers (CAPP), 
Crude Oil: Forecast, Markets, and Pipelines, June 2011, p. 
2, http://www.capp.ca/forecast/Pages/default.aspx. 
Congressional Research Service 
18 
Keystone XL Pipeline Project: Key Issues 
 
Table 3. U.S. Oil Imports 
(millions of barrels per day) 
 
2005  2006 2007 2008 2009 2010 2011 2012 
Canada 
2.18 2.35 2.45 2.49 2.47 2.53 2.79 2.95 
Mexico 
1.66 1.70 1.53 1.30 1.21 1.28 1.20 1.03 
Persian 
Gulf 
OPEC 
2.33 2.21 2.16 2.37 1.68 1.71 1.86 2.15 
Other 
OPEC 
3.25 3.30 3.82 3.58 3.09 3.19 2.69 2.10 
Rest 
of 
the 
World 4.29 4.14 3.50 3.17 3.24 3.08 2.96 2.36 
Total 
13.71 13.70 13.46 12.91 11.69 11.79 11.50 10.59 
Source: Energy Information Administration, http://www.eia.doe.gov 
Notes: Table 3 contains data for gross oil and petroleum product imports. 
Oil Sands, Keystone XL, and the U.S. Oil Market 
Oil sands (also referred to as tar sands) are a mixture of clay, sand, water, and heavy black 
viscous oil known as bitumen. Oil sands require more processing than conventional crude oil. Oil 
sands are processed to extract the bitumen, which can then be sent to refineries in one of two 
forms. Bitumen can be upgraded into “syncrude,” a light crude that is suitable for pipeline 
transport and is relatively easy to refine. Alternatively, bitumen can be blended with lighter 
hydrocarbons to form a heavy crude (diluted bitumen or “dilbit”) that can be transported by 
pipeline. The bulk of oil sands supply growth is expected to be in the form of the latter.59  
Most oil sands imports into the United States currently go to the Midwest, where refineries have 
been investing in complex refining capacity to process growing volumes of heavy Canadian 
crude.60 The U.S. Gulf Coast region already has a large amount of complex refining capacity and 
is well suited for processing Canadian heavy crude oil. Gulf Coast refiners currently process 
heavy crudes from Venezuela, Mexico, and elsewhere. Complex refineries in the Gulf Coast may 
be best equipped to handle a large increase of heavy oil sands crude, though some may still need 
to adjust processes and make new capital investments in equipment to accommodate particular 
crudes’ characteristics,61 especially if the new Canadian crudes will be used in large amounts.62 
There are 58 refineries in the Gulf Coast region (potentially served by the proposed Gulf Coast 
Project) that could process heavy crude oil similar in composition to the oil that Keystone XL 
pipeline would carry from Alberta.63 Crudes from the U.S. Bakken formation are light crudes. 
                                                 
59 CAPP, 2011, p. 7. 
60 CAPP, 2011, p. 13. According to CAPP, refineries adding capacity to process more heavy oil in the Midwest include 
those in Roxana, IL; Whiting, IN, and Detroit, MI.  
61 Baker Hughes, 
Planning Ahead for Effective Canadian Crude Processing, Baker Petrolite White Paper, 2010, 
http://www.bakerhughes.com/assets/media/whitepapers/4c2a3c8ffa7e1c3c7400001d/file/28271-
canadian_crudeoil_update_whitepaper_06-10.pdf.pdf&fs=1497549. 
62 For a description of which units refineries may need to add (or have added) to be able to process more Canadian oil 
sands supply, see Praveen Gunaseelan and Christopher Buehler, “Changing US Crude Imports Are Driving Refinery 
Upgrades,” 
Oil and Gas Journal, August 10, 2009. 
63 TransCanada Keystone Pipeline, L.P., May 2012 Presidential Permit application submitted to the U.S. Department of 
State (see footnote 3), p. 14. 
Congressional Research Service 
19 
Keystone XL Pipeline Project: Key Issues 
 
Oil production from the oil sands is increasing, as is production from the Bakken and other areas 
of the U.S. Midwest.64 Transport options to carry crude from the Midwest to the Gulf Coast are 
limited. (In the past, crude oil had been shipped up from the Gulf Coast to Midwestern refineries.) 
The resulting abundance of crude oil in the Midwest has driven down crude oil prices in that 
region relative to Gulf Coast and international crude markets. Midwestern refiners benefit from 
the lower cost of crude, but it does not translate to substantially lower consumer prices for 
gasoline or other products in the region. The Midwest still brings in refined products from the 
Gulf Coast, which keeps refined products prices in line with national and international levels.65  
Oil sands producers are interested in Keystone XL because it would expand their market reach 
into the Gulf Coast. The Gulf Coast region holds half of U.S. refining capacity, including a 
substantial amount of technologically advanced capacity capable of processing heavy sour crudes 
in large volumes. Reaching a larger market and one with more advanced refining capacity could 
increase the price these producers receive for their crude. For their part, Gulf Coast refiners are 
interested in the Keystone XL pipeline because it increases the supply of heavy sour crude in the 
Gulf Coast region, potentially bringing down their input costs relative to the options they 
currently have available. Canadian Natural Resources Limited, an oil sands producer, and Valero 
Energy Corporation, a large U.S. refiner, are among those that contracted for shipping capacity on 
the Keystone XL pipeline. 
With expanded pipeline capacity extending to the U.S. Gulf Coast, Canadian oil sands crude may 
compete with other heavy crudes such as those from Mexico, Venezuela, and elsewhere.66 It is 
difficult to predict precisely how this competition will play out, but it may take place through 
shifting discounts or premiums on crude oils from various sources.67 It may be possible for 
Canadian oil supplies to effectively “push out” waterborne shipments from other countries, 
although this depends on a wide range of market conditions. Waterborne crudes may more easily 
go to other destinations than Canadian crudes, though like Canadian crudes they can be tied to 
specialized refining capacity, as is true for Venezuelan heavy crudes.  
There is concern that increased supply of crude to the Gulf Coast may result in larger petroleum 
product exports rather than contributing to lower domestic fuel cost. Although the United States is 
a net importer of oil and petroleum products, it does export some petroleum products. U.S. 
petroleum product exports rose when domestic demand declined in the wake of the recession 
while foreign demand for certain fuels, such as diesel, remained relatively robust. Issues around 
potential export of Canadian crude oil carried on Keystone XL or export of products made from 
that crude oil are addressed in CRS Report R42465, 
U.S. Oil Imports and Exports, by Robert 
Pirog. 
If Keystone XL secures growing oil sands output for the United States, it could push out seaborne 
crudes from elsewhere, regardless of where the product is ultimately sold. If the absence of the 
pipeline encourages Canadian oil sands producers and pipeline companies to find an alternate                                                  
64 See increased U.S. crude oil production in the Midwest under the PADD2 heading at the following source: Energy 
Information Administration, U.S. Department of Energy, 
Crude Oil Production (by PADD), Petroleum & Other 
Liquids, http://www.eia.gov/dnav/pet/pet_crd_crpdn_adc_mbblpd_a.htm. 
65 Adjusted for transport costs and other regional differences.  
66 Center for Energy Economics and Bureau of Economic Geology, 
Overview of the Alberta Oil Sands, University of 
Texas at Austin, 2006, p. 16, http://www.beg.utexas.edu/energyecon/documents/overview_of_alberta_oil_sands.pdf. 
67 For more about the U.S. refining system, see CRS Report R41478, 
The U.S. Oil Refining Industry: Background in 
Changing Markets and Fuel Policies, by Anthony Andrews et al. 
Congressional Research Service 
20 
Keystone XL Pipeline Project: Key Issues 
 
export route through the Canadian West Coast, Canadian supplies may displace heavy oil supplies 
in other markets and potentially allow relatively more overseas imports coming into the Gulf 
Coast. This possibility is discussed further below.  
It should be noted that Keystone XL aims to alleviate two potential bottlenecks in the pipeline 
transportation system: Between Western Canada and the United States, and between the U.S. 
Midwest and the Gulf Coast. Existing pipelines between Canada and the United States have spare 
capacity to carry rising Canadian production for the time being. According to some estimates, 
additional capacity, such as Keystone XL, may not be needed until 2019.68 The latter bottleneck, 
between the Midwest and the Gulf Coast, is already at capacity and, as described above, has 
resulted in a discount for crude oil in the Midwest (though not for petroleum products). The Gulf 
Coast Pipeline Project, the lower leg of originally proposed Keystone XL pipeline, would address 
this second bottleneck and help alleviate the discount for Midwestern crudes.  
Other Pipeline Projects 
Apart from Keystone XL, several other pipeline proposals could help carry growing Canadian 
crude oil supplies to the U.S. Gulf Coast. On October 16, 2011, Enbridge announced it would 
purchase ConocoPhillips’ share of the Seaway pipeline and reverse its direction to bring crude oil 
from the Midwest to the Gulf Coast. ConocoPhillips had kept the pipeline running northward to 
serve its refinery in Ponca City, OK. However, the glut of oil in the Midwest had resulted in the 
pipeline running at low volumes. Nonetheless, ConocoPhillips had been uninterested in reversing 
the pipeline. ConocoPhillips, which is spinning off its refining business,69 sold its share of 
Seaway to Enbridge. Enbridge and Seaway shareholder Enterprise Products Partners L.P. reversed 
the direction of crude oil flows on the Seaway pipeline to enable it to transport oil from Cushing, 
OK, to the U.S. Gulf Coast. The pipeline began running southward at an initial capacity of 
150,000 bpd in 2012, with capacity expected to increase to 400,000 bpd in 2013. The reversal and 
expansion are expected to reduce the glut of crude oil in the Midwest and reconnect Midwestern 
crude prices to global prices (driving the U.S. Benchmark West Texas Intermediate crude 
higher).70  
Prior to the Seaway sale, Enbridge had reported significant commitments for two new pipeline 
projects: Flanagan South, which would carry oil from Illinois to Oklahoma, and Wrangler, which 
would carry oil from Oklahoma to Texas.71 According to Enbridge, the project would duplicate 
existing routes and would not cross an international border, so it would not require a Presidential 
Permit. Enbridge already has cross border pipeline capacity connecting Alberta to Illinois. 
However, according to press reports, Wrangler has been canceled in light of the Seaway purchase 
and reversal.72 Enbridge is moving forward with the Flanagan South project, which will have an 
initial capacity of about 600,000 bpd and run alongside Enbridge’s existing Spearhead pipeline 
                                                 
68 Testimony of Jim Burkhard, U.S. Congress, Senate Committee on Energy and Natural Resources, 
US and Global 
Energy Outlook for 2012, 112th Cong., 2nd sess., January 31, 2012. 
69 ConocoPhillips, “ConocoPhillips Pursuing Plan to Separate into Two Stand-Alone, Publicly Traded Companies,” 
press release, July 14, 2011, http://www.conocophillips.com/EN/newsroom/news_releases/2011news/Pages/07-14-
2011.aspx. 
70 Jenny Gross, “NYMEX Oil Gets Boost From Pipeline Reversal,” 
Wall Street Journal, April 22, 2012.  
71 Bradley Olson, “Enbridge Pursuing Alternative to Transcanada’s Keystone XL,” 
Bloomberg, November 9, 2011. 
72 Ben Lefebvre, “Enterprise Products Cancels Wrangler Pipeline,” Dow Jones Newswires, November 16, 2011. 
Congressional Research Service 
21 
Keystone XL Pipeline Project: Key Issues 
 
(see 
Figure 3).73 Like Keystone XL/Gulf Coast Project, Flanagan South and a southbound 
Seaway may facilitate increased flow of Canadian crude to the U.S. Gulf Coast. 
In February 2013, Enbridge also announced a proposal to convert segments of existing natural 
gas pipeline owned by Trunkline Gas Company to carry crude oil from western Canada and North 
Dakota to refineries in the eastern Gulf of Mexico. The pipeline conversion could potentially 
carry up to 660,000 bpd from the market hub at Patoka, IL, more than 700 miles to St. James, 
LA.74 
 
                                                 
73 Enbridge, “Flanagan South Project Fact Sheet,” April 1, 2012, http://www.enbridge.com/
FlanaganSouthPipeline.aspx. 
74 Enbridge, “Enbridge and Energy Transfer Join to Provide Crude Oil Pipeline Access to Eastern Gulf Coast Market,” 
press release, February 15, 2013. 
Congressional Research Service 
22 
 Figure 3. Proposed Enbridge Flanagan South Pipeline Route 
 
Source:
 
Figure 3. Proposed Enbridge Flanagan South Pipeline Route 
 
Source: Enbridge, “Flanagan South Project Fact Sheet,” April 1, 2012, http://www.enbridge.com/FlanaganSouthPipeline.aspx. 
CRS-23 
Keystone XL Pipeline Project: Key Issues 
 
Rail Transportation 
While the oil industry has been making substantial investments in pipeline capacity to relieve 
transportation bottlenecks for Canadian crudes, there has also been a substantial increase in oil 
transportation from the region by rail. As the State Department’s 2013 DEIS for the Keystone XL 
project states: 
In the past 2 years, there has been exponential growth in the use of rail to transport crude oil 
throughout North America, primarily originating from the Bakken in North Dakota and 
Montana, but also increasingly utilized in other production areas, including the [Western 
Canadian Sedimentary Basin]. Because of the flexibility of rail delivery points, once loaded 
onto trains the crude oil could be delivered to refineries, terminals, and/or port facilities 
throughout North America, including the Gulf Coast area.75 
Consistent with this view, both Canadian National Railway and Canadian Pacific Railway 
reportedly have long been pursuing a “pipeline on rails” business strategy, including new track 
investments, to move Canadian crudes to new markets throughout North America.76 While the 
potential volumes associated with rail transportation of crude would likely be lower than pipeline 
volumes, they could still be significant. Increasing cross-border movements of crude oil by rail 
does not require State Department approval, so such an approach seeks to avoid regulatory 
delays. 
As rail volumes have increased, some policy makers have expressed concern about the potential 
safety of crude transport by rail compared to pipelines. These concerns have been exacerbated by 
several significant accidents in the United States and Canada involving rail transport of crude 
oil.77 The most serious accident was the July 2013 derailment and explosion of a rail-borne crude 
oil shipment through Lac-Mégantic, Quebec, Canada, which killed 47 people and burned much of 
the downtown area.78 Some analysts in the Keystone XL Pipeline debate have asserted that these 
rail accidents underscore the need for a new pipeline as, in their view, a safer mode of 
transportation for Canadian crudes.79 However, safety comparisons between the two 
transportation modes are complicated by spill frequency vs. spill volume issues, which leave 
assertions about relative safety open to debate.80 
Canadian Oil to East and West Coast Markets 
There are proposals to increase the capacity for oil from Alberta to reach the Canadian east and 
west coast. Currently, nearly all of Canada’s oil exports go to the United States, mostly through                                                  
75 U.S. Department of State, March 2013, Draft EIS, Section 5.1, “No Action Alternatives.” 
76 Nathan Vanderklippe, “CN, CP Push for a ‘Pipeline on Rails,’” 
The Globe and Mail, February 7, 2011. 
77 See, for example, David Sheppard and Jeffrey Jones, “Train Hauling Canadian Oil Derails in Minnesota,” 
Reuters, 
March 27, 2013. 
78 Brian Mann, “Lac-Mégantic Blast Leaves Impact on Town, Rail Industry,” National Public Radio, October 14, 2013. 
79 Diana Furchtgott-Roth and Kenneth P. Green, 
Intermodal Safety in the Transport of Oil, Fraser Institute, October 
2013, http://www.fraserinstitute.org/uploadedFiles/fraser-ca/Content/research-news/research/publications/intermodal-
safety-in-the-transport-of-oil.pdf. 
80 See, for example: Rory Johnston, “Train vs. Pipeline: What’s the Safest Way to Transport Oil?” 
Christian Science 
Monitor, Energy Voices blog, October 22, 2013, http://www.csmonitor.com/Environment/Energy-Voices/2013/1022/
Train-vs.-pipeline-What-s-the-safest-way-to-transport-oil. 
Congressional Research Service 
24 
Keystone XL Pipeline Project: Key Issues 
 
north-south pipelines. Only one major oil pipeline extends from Alberta to Canada’s west coast: 
the Trans Mountain Pipeline, which is owned by Houston-based Kinder Morgan and has a 
capacity of 300,000 bpd. Some of the oil from the Trans Mountain Pipeline is loaded onto tankers 
and shipped from Vancouver. Nearly all of the quantities shipped by sea go to the United States, 
with a small amount going to China and other Asian countries.81 Proposals for additional east and 
westbound capacity include the following. 
•  Kinder Morgan has plans to expand the Trans Mountain Pipeline to 850,000 bpd 
by 2017, more than doubling its existing capacity, and expanding west coast 
shipping facilities.82 The expansion has received the necessary commitments 
from parties interested in shipping additional crude volumes. Some shippers are 
interested in using the additional capacity to export more Canadian crude oil to 
Asia. Kinder Morgan still needs regulatory approvals from Canadian authorities 
and is working to gain the support of stakeholders.83 There is some opposition to 
the project, including from groups concerned about additional tanker traffic near 
Vancouver and potential oil spill risks.84  
•  Enbridge has proposed a new pipeline: the Northern Gateway project would have 
a 525,000 bpd capacity to send oil from Edmonton to Kitimat, British 
Columbia.85 However, Northern Gateway faces opposition from groups including 
some First Nations communities and environmental groups.86  
•  Several projects are considering moving oil east rather than to the west coast. 
According to reports, TransCanada is considering a pipeline project sending oil 
east from Alberta to Quebec and New Brunswick, which could also carry crude 
bound for export.87 Enbridge is also interested in expanding eastbound capacity 
by reversing its Line 9 Pipeline.88 Some suggest this could potentially lead to oil 
sands crude traveling east, through Montreal and then through another pipeline to 
Portland, ME, from which point it could be exported.89 As with other pipeline 
projects, these also face opposition from environmental groups concerned about 
oil spill risks and/or generally opposed to oil sands development.  
                                                 
81 According to the Global Trade Atlas, about 0.5% of Canadian crude exports went to China in 2011 (accessed April 
25, 2012).  
82 Christopher Smith, “KMEP Advances Trans Moutain Crude Pipeline Expansion,” 
Oil & Gas Journal, April 6, 2012.  
83 David Ebner and Justine Hunter, “U.S. Company Plans Billion-Dollar Expansion of Trans Mountain Pipeline,” 
The 
Global and Mail, April 13, 2012.  
84 Jeff Lee, “Vancouver Council, Park Board to Formally Oppose Kinder Morgan Pipeline Expansion,” 
Vancouver Sun, 
April 24, 2012. 
85 Enbridge, “Northern Gateway at a Glance,” press release, 2011, http://www.northerngateway.ca/project-info/
northern-gateway-at-a-glance. The project would also include a pipeline to allow the import of 193,000 bpd of 
condensate, a light hydrocarbon that can be blended with bitumen to allow pipeline transport. 
86 “Northern Gateway Pipeline: Alberta, B.C. Agree to Drop Compensation Issue from their Talks,” Canadian Press, 
November 5, 2013. 
87 Nathan Vanderklippe and Shawn McCarthy, “TransCanada Looks East as Gateway Pipeline Gets Bogged Down,” 
The Globe and Mail, March 22, 2012. 
88 “Enbridge Pipelines Inc. - Line 9 Reversal Phase I Project (OH-005-2011),” (Project Application), National Energy 
Board (Government of Canada), http://www.neb-one.gc.ca/clf-nsi/rthnb/pplctnsbfrthnb/nbrdgln9phs1/nbrdgln9phs1-
eng.html. 
89 Matt Dodge, “Court Decision Affects South Portland-Montreal Pipeline,” 
Maine Biz, April 3, 2012; Yadullah 
Hussain, “Pipeline Plan to Send Crude from Montreal to Maine Raises Ire in New England,” 
Financial Post, May 22. 
2013. 
Congressional Research Service 
25 
Keystone XL Pipeline Project: Key Issues 
 
These projects reflect anticipated growth of western Canadian oil production and an interest by 
Canadian oil producers to diversify their available markets beyond U.S. customers, especially to 
reach rapidly growing Asian oil demand.  
Canadian interests assert that Canadian oil sales to Asian markets, where oil demand is growing 
rapidly, are more likely if greater shipments to the United States are not possible.90 A study 
commissioned by the U.S. Department of Energy suggested that  
if pipeline projects to the [British Columbia] coast are built, they are likely to be utilized. 
This is because of the relatively short marine distances to major northeast Asia markets, 
future expected growth there in refining capacity and increasing ownership interests by 
Chinese companies especially in oil sands production. Such increased capacity would alter 
global crude trade patterns. Western Canadian Sedimentary Basin (WCSB) crudes would be 
“lost” from the USA, going instead to Asia. There they would displace the world’s balancing 
crude oils, Middle Eastern and African predominantly OPEC grades, which would in turn 
move to the USA. The net effect would be substantially higher U.S. dependency on crude 
oils from those sources versus scenarios where capacity to move WCSB crudes to Asia was 
limited.91 
Economic Impact of the Pipeline 
In addition to supply diversity arguments, some Keystone XL pipeline proponents support the 
project based on economic benefits associated with expanding U.S. pipeline infrastructure. A 
study by the Energy Policy Research Foundation, for example, concludes that “the Keystone 
expansion would provide net economic benefits from improved efficiencies in both the 
transportation and processing of crude oil of $100 million-$600 million annually, in addition to an 
immediate boost in construction employment.”92 A 2009 report from the Canadian Energy 
Research Institute (CERI) commissioned by the American Petroleum Institute similarly 
concludes that 
As investment and production in oil sands ramps up in Canada, the pace of economic activity 
quickens and demand for US goods and services increase rapidly, resulting in an estimated 
343 thousand new US jobs between 2011 and 2015. Demand for U.S. goods and services 
continues to climb throughout the period, adding an estimated $34 billion to US GDP in 
2015, $40.4 billion in 2020, and $42.2 billion in 2025.93 
These CERI estimates apply to the entire oil sands industry, however, not only the Keystone XL 
project, and they are derived from a proprietary economic analysis which has not been subject to 
external review. Some stakeholders point to State Department and other studies reporting much 
lower anticipated economic benefits.94 In July 2013, President Obama reportedly stated that the                                                  
90 Edward Welsch, “TransCanada: Oil Sands Exports Will Go to Asia if Blocked in U.S.,” Dow Jones Newswires, June 
30, 2010.  
91 EnSys Energy & Systems, Inc., 
Keystone XL Assessment: Final Report, Prepared for the U.S. Department of Energy, 
Office of Policy & International Affairs, December 23, 2010, p. 118. 
92 Energy Policy Research Foundation, Inc., The Value of the Canadian Oil Sands (….to the United States): An 
Assessment of the Keystone Proposal to Expand Oil Sands Shipments to Gulf Coast Refiners, Washington, DC, 
November 29, 2010, p. 2, http://www.eprinc.org/pdf/oilsandsvalue.pdf. 
93 Canadian Energy Research Institute, 
The Impacts of Canadian Oil Sands Development on the United States’ 
Economy, Final Report, Calgary, Alberta, October 2009, p. vii. 
94 See, for example, Cornell University Global Labor Institute, 
Pipe Dreams? Jobs Gained, Jobs Lost by the 
(continued...) 
Congressional Research Service 
26 
Keystone XL Pipeline Project: Key Issues 
 
Keystone XL pipeline might create 2,000 temporary construction jobs and 50 to 100 permanent 
jobs.95 With the separation of the Gulf Coast Project from the northern segment of the original 
proposal, the potential economic impact of the reconfigured Keystone XL project has clearly 
changed. Consequently, it is difficult to determine what specific economic and employment 
impacts may ultimately be attributable to the Keystone XL pipeline. Nonetheless, given the 
physical scale of the project, it could be expected to increase employment and investment at least 
during construction. 
Lifecycle Greenhouse Gas Emissions 
Oil production from oil sands is controversial because it has significant environmental impacts, 
including emissions of greenhouse gases during extraction and processing, disturbance of mined 
land, and impacts on wildlife and water quality.96 In a June 2013 speech about climate change, 
President Obama remarked 
Allowing the Keystone [XL] pipeline to be built requires a finding that doing so would be in 
our nation’s interest. And our national interest will be served only if this project does not 
significantly exacerbate the problem of carbon pollution.97 
Thus, of the environmental factors under consideration, greenhouse gas emissions attributed to 
the development of Keystone XL may be the key determinant of whether the project will be 
granted a Presidential Permit. 
Because bitumen in oil sands cannot be pumped from a conventional well, it must be either 
mined, usually using strip mining or open pit techniques, or extracted with underground heating 
methods.98 Large amounts of water and natural gas are also required (for heating) during the 
extraction process.99 The magnitude of the environmental impacts of oil sands production, in 
absolute terms and compared to conventional oil production, has been the subject of numerous, 
and sometimes conflicting, studies and policy papers.100 Some stakeholders who object to oil 
sands projects oppose the Keystone XL pipeline because it expands access to new markets for the 
oil produced by those projects, thereby encouraging what they consider to be further 
environmentally destructive oil sands development. As discussed earlier, however, if oil sands 
                                                                  
(...continued) 
Construction of Keystone XL, September 28, 2011; National Wildlife Federation, “TransCanada Exaggerating Jobs 
Claims for Keystone XL,” November 9, 2010, http://www.dirtyoilsands.org/files/Keystone_XL_Jobs_11-09-10.pdf. 
95 Glenn Kessler, “President Obama’s Low-Ball Estimate for Keystone XL Jobs,” 
Washington Post, July 30, 2013. 
96 For more analysis of oil sands and their environmental impacts, see CRS Report RL34258, 
North American Oil 
Sands: History of Development, Prospects for the Future, by Marc Humphries.  
97 President Barack Obama, “Remarks by the President on Climate Change,” Georgetown University, Washington, DC, 
June 25, 2013, http://www.whitehouse.gov/the-press-office/2013/06/25/remarks-president-climate-change. 
98 U.S. Bureau of Land Management, “About Tar Sands,” web page, January 11, 2011, http://ostseis.anl.gov/guide/
tarsands/index.cfm. 
99 Cecilia Jamasmie, “The Challenges and Potential of Canada’s Oil Sands,” 
Mining, September-October 2010, pp. 7-8. 
100 For an example of contrasting views, see IHS CERA Inc., 
Oil Sands, Greenhouse Gases, and US Oil Supply, 
Getting the Numbers Right, 2010; and Natural Resources Defense Council, “Setting the Record Straight: Lifecycle 
Emissions of Tar Sands,” November 2010. 
Congressional Research Service 
27 
Keystone XL Pipeline Project: Key Issues 
 
production can be diverted to other markets (e.g., Asia), preventing the Keystone XL project may 
not necessarily limit oil sands development.101 
Some stakeholders object to the Keystone XL pipeline because it would increase U.S. supplies of 
oil, and thereby perpetuate the nation’s dependence on imported fossil fuels and increase carbon 
emissions from the transportation sector.102 Acknowledging this concern, in a public forum on 
October 20, 2010, Secretary of State Clinton reportedly remarked that “we’re either going to be 
dependent on dirty oil from the [Persian] Gulf or dirty oil from Canada … until we can get our act 
together as a country and figure out that clean, renewable energy is in both our economic interests 
and the interests of our planet.”103 Critics of the State Department’s draft and supplemental draft 
EIS assert that the environmental review overlooks the pipeline project’s overall impact on 
greenhouse gas emissions, for example, from the extraction and refining processes. To address 
those potential emissions, EPA recommended that the final EIS include discussion of mitigation 
approaches for greenhouse gas emissions from extraction activities that are either currently used 
or could be employed to help lower lifecycle greenhouse gas emissions.104 However, others have 
argued that whether the Keystone XL Pipeline is constructed would have little bearing on 
greenhouse gas emissions as there are likely to be other export routes available for Canadian oil 
sands crude, and therefore, the same crude oils would still be transported and refined, albeit in 
different locations.105 For further analysis of greenhouse gas emissions associated with the 
Canadian oil sands, see CRS Report R42537, 
Canadian Oil Sands: Life-Cycle Assessments of 
Greenhouse Gas Emissions, by Richard K. Lattanzio. 
Private Land Use and Oil Spill Impacts 
For the proposed Keystone XL Project, approximately 88% of the land affected by pipeline 
construction and operation would be privately owned, with the remaining 12% primarily state and 
federal land.106 Private land uses along the proposed pipeline routes are primarily agricultural—
farming and cattle ranching. The pipeline’s construction and continued operation would involve a 
50-foot-wide permanent right-of-way along the length of the pipeline. Keystone agreed to 
compensate landowners for losses on a case-by-case basis. However, a concern among 
landowners and communities along the route is the potential for their land or water (used for 
drinking, irrigation, or recreation) to be contaminated by an accidental release (spill) of oil. That 
concern is heightened in areas where the pipeline will be located near or would cross water or is 
in a remote location.  
                                                 
101 For more analysis of oil sands, including the environmental effects of its extraction, see CRS Report RL34258, 
North American Oil Sands: History of Development, Prospects for the Future, by Marc Humphries. 
102 See, for example: Natural Resources Defense Council, 
Tar Sands Invasion: How Dirty and Expensive Oil from 
Canada Threatens America’s New Energy Economy, May 2010. 
103 See Secretary of State Hillary Clinton’s “Remarks on Innovation and American Leadership to the Commonwealth 
Club,” San Francisco, CA, October 15, 2010, available at http://www.state.gov/secretary/rm/2010/10/149542.htm. 
104 See EPA’s July 16, 2010, letter to the U.S. Department of State rating the supplemental EIS for the Keystone XL 
pipeline project, available at http://yosemite.epa.gov/oeca/webeis.nsf/%28PDFView%29/20100126/$file/
20100126.PDF. Discussion of the analysis of GHG emissions is included on pp. 3-4. 
105 EnSys Energy & Systems 2010, p. 116. 
106 U.S. Department of State, March 2013, Draft EIS: “Section 4.9, Land Use, Recreation, and Visual Resources,” p. 
4.9-2. 
Congressional Research Service 
28 
Keystone XL Pipeline Project: Key Issues 
 
A primary environmental concern of any oil pipeline is the risk of an oil spill. In estimating 
potential environmental impacts, several factors will be important—including the size and 
location of the release, leak, or spill, and how quickly it is remediated. An oil spill on land would 
not necessarily result in surface or groundwater contamination. The potential for a spill to reach 
water would depend on factors such as its proximity to a water source (e.g., on or near a creek or 
stream or located on land where the groundwater table is close to the surface) and the 
characteristics of the environment into which the crude oil is released (e.g., porous underlying 
soils), and the volume of the spill, its duration, and the viscosity and density of the crude oil 
involved.  
The size of potential spills and the type of oil that would likely be released from the Keystone XL 
Pipeline have been issues of concern to opponents of the project. In its July 16, 2010, comments 
on the draft EIS for the Keystone XL Project, EPA expressed particular concern over the potential 
adverse impacts to surface and ground water from pipeline leaks or spills. That concern stemmed 
from two areas—the toxicity of chemical diluents that may be used to allow bitumen to be 
transported by pipeline and the lack of risk assessment for potential “serious or significant spills,” 
including an evaluation of spill response procedures in the wake of such a spill. 
Concerns reflected in EPA’s letter were realized 10 days later when the Enbridge Energy Partners’ 
Alberta Pipeline ruptured near Marshall, MI. The resulting spill released crude into a tributary 
creek of the Kalamazoo River and traveled approximately 40 miles downstream in the 
Kalamazoo River. Initially estimated by Enbridge as a release of approximately 800,000 gallons 
of crude, EPA subsequently estimated that over 1.1 million gallons were released. The spill 
resulted in over 220 areas of moderate-to-heavy contamination, including over 200 acres of 
submerged oil on the river bottom and over 300 solidified oil deposits.107 Enbridge estimates that 
cleanup will cost approximately $700 million. 
The Enbridge spill highlighted several issues of concern among environmental groups and 
communities along the pipeline route—in particular, the nature of the heavy crude likely carried 
by the Keystone XL Pipeline. The heavy crude (diluted bitumen, or dilbit) in the Enbridge spill 
had been diluted with benzene and other hazardous constituents. Following the spill, high levels 
of benzene in the air prompted the issuance of voluntary evacuation of residents in the area. 
Concern over the presence of similarly toxic constituents, particularly the degree to which the 
level of toxic constituents may be unknown at the time of a release, has been an ongoing concern 
among environmental and community groups.  
The Enbridge spill was considered a “very large spill” and not necessarily one that would be 
likely along the Keystone XL pipeline route. However, in its first year of operation, 
TransCanada’s Keystone pipeline experienced 14 spills. Although mostly minor, one spill at the 
Ludden, ND, pump station resulted in the release of 21,000 gallons of oil. Like the Enbridge 
release, that release was first reported by local citizens, not as a result of the Keystone’s release 
detection equipment. A March 29, 2013, release of oil sands crude from an Exxon Mobil pipeline 
in Mayflower, AR, has continued to draw attention to the risk of potential spills from crude oil 
pipelines.108 These incidents have made pipeline opponents concerned that such spills may be 
                                                 
107 For more information see EPA’s regarding the response to the Enbridge oil spill at http://www.epa.gov/
enbridgespill/. 
108 Arkansas Department of Environmental Quality, “Mayflower Oil Spill Response,” fact sheet, March 30, 2013, 
http://www.adeq.state.ar.us/hazwaste/mayflower_oil_spill_2013/files/mayflower_pipeline-_fact_sheet.pdf. 
Congressional Research Service 
29 
Keystone XL Pipeline Project: Key Issues 
 
significant and that, absent a witness to a spill, a leak in a remote area could potentially go 
undetected for a long period.  
The Enbridge spill also demonstrates that cleanup of oil sands dilbit presents certain challenges. 
Dilbit is a relatively heavy crude oil mixture compared to other crude oils. In general, heavier oils 
are more persistent and present greater technical challenges in removal after a spill compared to 
lighter oils. Over two years after the Enbridge spill, cleanup efforts continue. After the spill, 
public access to 39 miles of the river system was banned to protect public health and safety. In 
March 2013, the EPA ordered Enbridge to implement containment and dredging of submerged oil 
to prevent continued migration of oil downstream to the Kalamazoo River.109 The first three-mile 
segment of river reopened to the public on April 27, 2012. Elements of the cleanup are expected 
to last until 2015. For further analysis of environmental issues associated with the Keystone XL 
project, see CRS Report R42611, 
Oil Sands and the Keystone XL Pipeline: Background and 
Selected Environmental Issues, coordinated by Jonathan L. Ramseur. 
Regardless of design, construction, and safety measures, the Keystone XL pipeline will likely 
have some number of spills over the course of its operating life. The unique oil spill response 
efforts necessary for heavy crudes like dilbit make an accurate assessment of potential oil spill 
risk particularly relevant when addressing concerns expressed by opponents to the Keystone XL 
Pipeline. The need for more conclusive analysis of potential risks associated with the transport of 
dilbit was addressed, in part, in the Pipeline Safety, Regulatory Certainty, and Job Creation Act of 
2011 (P.L. 112-90, enacted January 16, 2012). In particular, under Section 16, “Study of 
transportation of diluted bitumen,” the Secretary of Transportation is required to conduct an 
analysis to determine whether there is any increased risk of a release for pipeline facilities 
transporting diluted bitumen. In response to that directive, the PHMSA contracted with the 
National Academy of Sciences to conduct a full and independent study of this topic. The 
Academy’s report “did not find any pipeline failures unique to the transportation of diluted 
bitumen or evidence of physical or chemical properties of diluted bitumen shipments that are 
outside the range of those of other crude oil shipments.”110 
Issues with the Original Pipeline Route Across the Sand Hills 
In the process of examining factors necessary to determine whether the Presidential Permit for the 
original Keystone XL Project was in the national interest, the State Department decided that it 
needed to assess potential alternative pipeline routes that would avoid the Sand Hills region of 
Nebraska. Unique characteristics of the Sand Hills—including its high concentration of wetlands, 
extensive areas of very shallow groundwater, and its sensitive ecosystem—were identified as 
factors that resulted in increasing public concern over the proposed pipeline location. For these 
reasons, TransCanada announced it would work with the Nebraska DEQ to identify a potential 
pipeline route that would avoid the Sand Hills. New pipeline routes through Nebraska, identified 
in the 2013 draft EIS, reflect the work between TransCanada and Nebraska DEQ. 
                                                 
109 Environmental Protection Agency, “Re: Order pursuant to §311(c) of the Clean Water Act (Docket No. CWA 1321-
5-13-001) for Recovery of Submerged Oil from the En bridge Line 6B Discharge near Marshall, MI,” Cover letter, 
March 14, 2013, http://www.epa.gov/enbridgespill/ar/enbridge-AR-1719.pdf.  
110 National Research Council, 
Effects of Diluted Bitumen on Crude Oil Transmission Pipelines, TRB Special Report 
311, June 25, 2013. 
Congressional Research Service 
30 
Keystone XL Pipeline Project: Key Issues 
 
To understand concerns about the potential environmental impacts of a pipeline crossing the Sand 
Hills (also referred to as the Sandhills), an understanding of the unique size and structure of the 
region is useful. The Sand Hills region is a 19,600 square mile sand dune formation stabilized by 
native grasslands that cover 95% of its surface. The surface is highly susceptible to wind erosion 
if the grassland is disturbed.111 Below its surface lie hundreds of feet of coarse sand and gravel. 
Essentially, the porous soil acts like a giant sponge that quickly absorbs precipitation, allowing 
very little to run off. In some areas, the water table reaches the land surface—a characteristic that 
creates lakes that dot the region as well as 1.3 million acres of wetlands. The loose, porous soil 
and sensitivity to wind erosion have been factors contributing to a lack of development on the 
Sand Hills. As a result, the region contains the most intact natural habitat of the Great Plains of 
the United States. The porosity of the soil is also relevant because the Sand Hills sits atop the 
Ogallala Aquifer—one of the largest freshwater aquifer systems in the world.112 
The highly porous soil of the Sand Hills makes it a significant recharge zone in the northern 
Ogallala Aquifer. That is, the sandy, porous soil of the Sand Hills allows a significant amount of 
surface water to enter (recharge) the aquifer system. Water from the aquifer also accounts for a 
significant amount of water use—78% of the region’s public water, 83% of irrigation water in 
Nebraska, and 30% of water used in the United States for irrigation and agriculture. 
Potential impacts to the Ogallala Aquifer and the Sand Hills identified in the final EIS for 
TransCanada’s original permit application included groundwater contamination after an 
accidental spill or leak of crude oil during the construction or operation of the proposed pipeline. 
Along the preferred route of the originally proposed pipeline configuration, areas in the Sand 
Hills region were identified as locations where the water table may be close to the surface. The 
depth to groundwater was less than 10 feet for approximately 65 miles of the preferred pipeline 
route in Nebraska. Both the soil porosity and the close proximity of groundwater to the surface 
increase the potential that a release of oil from the pipeline could contaminate groundwater in the 
region.113  
On January 13, 2013, the governor of Nebraska approved a proposed reroute of the Keystone XL 
pipeline through Nebraska.114 The new route alternatives proposed for the Nebraska section of the 
Keystone XL pipeline avoids the Sand Hills and certain areas nearby with similar soil properties.  
                                                 
111 For more information, see the Department of the Interior’s U.S. Fish and Wildlife Service web page on the Sand 
Hills at http://www.fws.gov/mountain-prairie/pfw/ne/ne4.htm.  
112 The entire Ogallala Aquifer system stretches across eight states generally from north to south to include South 
Dakota, Nebraska, Wyoming, Colorado, Kansas, Oklahoma, New Mexico, and Texas and underlies about 174,000 
square miles. 
113 Generally, a release of crude oil to land would not necessarily result in groundwater contamination. In addition to 
the depth from the land surface to groundwater and the characteristics of the environment into which the crude oil is 
released (e.g., characteristics of the underlying soils), the potential for crude oil to reach groundwater would depend on 
factors such as the volume of the spill, the duration of the release, and the viscosity and density of the crude oil.  
114 See U.S. Department of State, March 2013, Draft EIS: “Volume III. Appendix A. Governor Approval of the 
Keystone XL Project in Nebraska.” 
Congressional Research Service 
31 
 Keystone XL Pipeline Project: Key Issues 
 
Figure 4. Keystone XL Project—Pipeline Route in Nebraska
Keystone XL Pipeline Project: Key Issues 
 
Figure 4. Keystone XL Project—Pipeline Route in Nebraska 
Comparison of Currently and Previously Proposed Project Segments 
 
Source: State Department, March 2013, “Draft Supplemental 
Environmental Impact Statement for the Keystone XL Project: Executive 
Summary,” p. ES-7.  
 
 
Congressional Research Service 
32 
Keystone XL Pipeline Project: Key Issues 
 
Appendix A. Presidential Permitting Authority115 
The executive branch has exercised permitting authority over the construction and operation of 
“pipelines, conveyor belts, and similar facilities for the exportation or importation of petroleum, 
petroleum products” and other products at least since the promulgation of Executive Order 11423 
in 1968.116 Executive Order 13337 amended this authority and the procedures associated with the 
review, but did not substantially alter the exercise of authority or the delegation to the Secretary 
in E.O. 11423.117 However, the source of the executive branch’s permitting authority is not 
entirely clear from the text of these Executive Orders. Generally, powers exercised by the 
executive branch are authorized by legislation or are inherent presidential powers based in the 
Constitution. E.O. 11423 makes no mention of any authority, and E.O. 13337 refers only to the 
“Constitution and the Laws of the United States of America, including Section 301 of title 3, 
United States Code.”118 Section 301 simply provides that the President is empowered to delegate 
authority to the head of any department or agency of the executive branch.  
The legitimacy of this permitting authority has been addressed by federal courts. In 
Sisseton v. 
United States Department of State, the plaintiff Tribes filed suit and asked the court to suspend or 
revoke the Presidential Permit issued under E.O. 13337 for the TransCanada Keystone 
Pipeline.119 The U.S. District Court for the District of South Dakota found that the plaintiffs 
lacked standing because they would be unable to prove their injury could be redressed by a 
favorable decision.120 The court determined that even if the plaintiff’s injury could be redressed, 
“the President would be free to disregard the court’s judgment,” as the case concerned the 
President’s “inherent Constitutional authority to conduct foreign policy,” as opposed to statutory 
authority granted to the President by Congress.121  
The court further found that even if the Tribes had standing, the issuance of the Presidential 
Permit was a presidential action, not an agency action subject to judicial review under the 
Administrative Procedure Act (APA).122 The court stated that the authority to regulate the cross-
border pipeline lies with either Congress or the President.123 The court found that “Congress has 
failed to create a federal regulatory scheme for the construction of oil pipelines, and has delegated 
this authority to the states. Therefore, the President has the sole authority to allow oil pipeline 
border crossings under his inherent constitutional authority to conduct foreign affairs.”124 The 
                                                 
115 For a more expansive treatment of this topic, see CRS Report R42124, 
Proposed Keystone XL Pipeline: Legal 
Issues, by Adam Vann, Kristina Alexander, and Kenneth R. Thomas, and CRS Report R43261, 
Presidential Permits 
for Border Crossing Energy Facilities, by Adam Vann and Paul W. Parfomak. 
116 
Providing for the performance of certain functions heretofore performed by the President with respect to certain 
facilities constructed and maintained on the borders of the United States, 33 
Federal Register 11741, August 16, 1968. 
117 
Issuance of Permits With Respect to Certain Energy-Related Facilities and Land Transportation Crossings on the 
International Boundaries of the United States, 69 
Federal Register 25299, May 5, 2004. 
118 Ibid. 
119 659 F. Supp. 2d 1071, 1078 (D. S.D. 2009). 
120 Ibid. at 1078. 
121 Ibid. at 1078, 1078 n.5. 
122 See ibid. at 1080-81. 
123 Ibid. at 1081. 
124 Ibid.  
Congressional Research Service 
33 
Keystone XL Pipeline Project: Key Issues 
 
President could delegate his permitting authority to the U.S. Department of State, but delegation 
did not transform the permit’s issuance into an agency action reviewable under the APA.125 
In 
Sierra Club v. Clinton,126 the plaintiff Sierra Club challenged the Secretary’s decision to issue a 
Presidential Permit authorizing the Alberta Clipper pipeline. Among the plaintiff’s claims was an 
allegation that issuance of the permit was unconstitutional because the President had no authority 
to issue the permits referenced in E.O. 13337 (in this case, for the importation of crude oil from 
Canada via pipeline).127 The defendant responded that the authority to issue Presidential Permits 
for these border-crossing facilities “does not derive from a delegation of congressional authority 
... but rather from the President’s constitutional authority over foreign affairs and his authority as 
Commander in Chief.”128 The U.S. District Court for the District of Minnesota agreed, noting that 
the defendant’s assertion regarding the source of the President’s authority has been “well 
recognized” in a series of Attorney General opinions, as well as a 2009 judicial opinion.129 The 
court also noted that these permits had been issued many times before and that “Congress has not 
attempted to exercise any exclusive authority over the permitting process. Congress’s inaction 
suggests that Congress has accepted the authority of the President to issue cross-border 
permits.”130 Based on the historical recognition of the President’s authority to issue these permits 
and Congress’s implied approval through inaction, the court found the Presidential Permit 
requirement for border facilities constitutional. 
                                                 
125 Ibid. at 1082. 
126 689 F.Supp.2d 1147 (D. Minn. 2010). 
127 Ibid. at 1162. 
128 Ibid. 
129 Ibid. at 1163 (citing 38 U.S. Atty Gen. 162 (1935); 30 U.S. Op. Atty. Gen. 217 (1913); 24 U.S. Op. Atty. Gen. 100; 
and Natural Resources Defense Council (NRDC) v. U.S. Department of State, 658 F.Supp.2d 105, 109 (D.D.C. 2009)). 
The court in 
NRDC held that the State Department’s issuance of a presidential permit under Executive Order 13337 
was not subject to judicial review under the Administrative Procedure Act for abuse of discretion because “the issuance 
of presidential permits is ultimately a presidential action.” 658 F. Supp. 2d at 109, 111-12. The court said that to allow 
judicial review of such decisions would raise separation of powers concerns. Ibid.
 at 111. 
130 Ibid.; see also Youngstown Sheet and Tube Co. v. Sawyer, 343 U.S. 579 (1952) (establishing a three-part test for 
analyzing the validity of presidential actions in relation to constitutional and congressional authority). 
Congressional Research Service 
34 
Keystone XL Pipeline Project: Key Issues 
 
Appendix B. Details of the Initial NEPA Review 
The NEPA process for TransCanada’s 2008 Presidential Permit application for the Keystone XL 
pipeline project included several significant milestones (summarized in 
Table 1). These events, 
and resulting documents, will likely have varying degrees of influence over TransCanada’s 2012 
permit application. 
Draft EIS issued 
The State Department released its draft EIS for the proposed Keystone XL Pipeline project for 
public comment on April 16, 2010.131 The draft EIS identified TransCanada’s “preferred 
alternative” for the project as well as other alternatives considered. On July 16, 2010, EPA rated 
the draft EIS “Inadequate.”132 EPA found that potentially significant impacts were not evaluated 
and that the additional information and analysis needed was of such importance that the draft EIS 
would need to be formally revised and again made available for public review. Additional 
criticism of the State Department’s implementation of the NEPA process followed an October 21, 
2010, statement by Secretary Clinton that, while analysis of the project was not complete and a 
final decision had not been made, the State Department was “inclined to” approve the project.133 
Critics of the project, including some Members of Congress, stated that the Secretary’s statement 
appeared to prejudge its permit approval for the pipeline proposal as a foregone conclusion.134  
Supplemental Draft EIS Issued 
The State Department issued a supplemental draft EIS on April 15, 2011. In addition to 
addressing issues associated with EPA’s inadequacy rating, the supplemental draft EIS addressed 
comments received from other agencies and the public. On June 6, 2011, EPA sent a letter to the 
State Department that rated the supplemental draft EIS as having “Insufficient Information” and 
having “Environmental Objections” to the proposed action.135 EPA acknowledged that the State 
Department had “worked diligently” to develop additional information in response to EPA’s 
comments and the large number of other comments on the draft EIS. However, EPA believed that 
additional analysis needed to be included in the final EIS to fully respond to its earlier comments.                                                  
131 Documents submitted for the initial 2008 Presidential Permit application have now been archived by the State 
Department. Documents related to that original application are available at http://keystonepipeline-xl.state.gov/archive/
index.htm. 
132 U.S. Environmental Protection Agency’s July 16, 2010, letter to the U.S. Department of State commenting on the 
draft EIS for the Keystone XL project is available at http://yosemite.epa.gov/oeca/webeis.nsf/%28PDFView%29/
20100126/$file/20100126.PDF. 
133 See Secretary of State Hillary Clinton, “Remarks on Innovation and American Leadership to the Commonwealth 
Club,” San Francisco, CA, October 15, 2010, available at http://www.state.gov/secretary/rm/2010/10/149542.htm. The 
statement by Secretary Clinton was actually made in response to a question about the Alberta Clipper pipeline project 
which received a Presidential Permit from the State Department in 2009; a State Department spokesman later clarified 
that the Secretary was referring to the Keystone XL pipeline permit approval. 
134 For example, see the October 21, 2010, letter from Senator Mike Johanns to Secretary Clinton expressing his 
concern that her statement gave the appearance that approval of the pipeline was a foregone conclusion, 
http://johanns.senate.gov/public/?a=Files.Serve&File_id=8b090aa5-76fe-41ca-a674-ae9e37db8d36. 
135 U.S. Environmental Protection Agency’s June 6, 2011, letter to the U.S. Department of State commenting on the 
supplemental draft EIS for the Keystone XL project is available at http://yosemite.epa.gov/oeca/webeis.nsf/
%28PDFView%29/20110125/$file/20110125.PDF?OpenElement.  
Congressional Research Service 
35 
Keystone XL Pipeline Project: Key Issues 
 
Among other items, EPA recommended that the State Department should do the following: 
improve the analysis of the potential oil spill risks, including additional analysis of other 
reasonable alternatives to the proposed pipeline route; provide additional analysis of potential oil 
spill impacts, health impacts, and environmental justice concerns to communities along the 
pipeline route and adjacent refineries; and improve its characterization of lifecycle greenhouse 
gas emissions associated with Canadian oil sands crude. 
In its June 6 letter to the State Department, EPA refers to agreements with the State Department 
that certain deficiencies identified in the supplemental draft EIS would be addressed in the final 
EIS. Further, in its conclusion, EPA stated that it would carefully review the final EIS to 
determine if it fully reflects those agreements and if measures to mitigate adverse environmental 
impacts are fully evaluated. 
Final EIS Issued 
On August 26, 2011, the State Department issued the final EIS for the proposed Keystone XL 
Pipeline. Among other elements of the final EIS, it identified various major pipeline route 
alternatives and an environmental analyses of potential impacts associated with those 
alternatives.136 
In October 2011, 14 Members of Congress wrote to the State Department’s Office of Inspector 
General requesting an investigation of the department’s handling of the EIS and national interest 
determination for the Keystone XL project.137 The request was prompted, in part, by press reports 
suggesting bias or potential conflicts of interest in the State Department’s hiring of an outside 
contractor to perform the EIS and in its communications with the pipeline’s developer, 
TransCanada.138 On November 4, the Inspector General’s Office (IG) announced that, in response 
to this request, it was initiating a special review “to determine to what extent the Department and 
all other parties involved complied with Federal laws and regulations relating to the Keystone XL 
pipeline permit process.”139 On February 9, 2012, the IG released its findings, reporting that the 
State Department “did not violate its role as an unbiased oversight agency,” among other specific 
findings generally supportive of the department’s Keystone XL permit review process.140 
Public Review and National Interest Determination  
Following the release of the Keystone XL project’s final EIS, a review period began to determine 
if the proposed project was in the national interest. As part of the process for the Keystone XL 
project, the State Department held public meetings in each of the six states through which the 
                                                 
136 Environmental analysis associated with pipeline project alternatives is provided in Volumes 1 and 2 of the final EIS.  
137 U.S. Senator Bernard Sanders, et al., Letter to The Honorable Harold W. Geisel, Office of Inspector General, U.S. 
Department of State, October 26, 2011. 
138 See. for example, Elisabeth Rosenthal and Dan Frosch, “Pipeline Review Is Faced with Question of Conflict,” 
New 
York Times, October 7, 2011. 
139 Harold W. Geisel, United States Department of State, Office of Inspector General, “Information Memo for Deputy 
Secretary Burns,” November 4, 2011, http://sanders.senate.gov/imo/media/doc/
Special%20Review%20Keystone%20XL%20Pipeline%20Nov%2020112.pdf. 
140 Harold W. Geisel, United States Department of State, Office of Inspector General
, Special Review of the Keystone 
XL Pipeline Permit Process, AUD/SI-12-28, February 2012. 
Congressional Research Service 
36 
Keystone XL Pipeline Project: Key Issues 
 
proposed pipeline would pass and in Washington, DC.141 The meetings were intended to give 
members of the public additional opportunity to voice their opinions on issues they thought 
should be taken into account in determining whether granting or denying the Presidential Permit 
would be in the national interest.142 During the review period, the State Department received input 
from state, local, and tribal officials as well as members of the public. 
After the public review period, the State Department issued a statement regarding the public 
comments and its response to those comments.143 The State Department stated that it received 
comments on a wide range of issues, including the Keystone XL project’s potential impact on 
jobs, pipeline safety, health concerns, the societal impact of the project, and oil extraction in 
Canada. Concern regarding the proposed pipeline route through the Sand Hills area of Nebraska 
was identified as one of the most common issues raised. Comments regarding that pipeline route 
were consistent with the environmental impacts identified in the final EIS with regard to the 
unique combination of characteristics of the Sand Hills region.  
In the final EIS, the preferred pipeline route through Nebraska would have been located entirely 
above the Ogallala Aquifer. Potential impacts to the Ogallala Aquifer and the Sand Hills 
identified in the final EIS include potential groundwater contamination after a release (e.g., a spill 
or leak from a hole or damaged portion of the pipeline) of crude oil during the construction or 
operation of the proposed pipeline. Both the soil porosity and the close proximity of groundwater 
to the surface increase the potential that a release of oil from the pipeline could contaminate 
groundwater in the region. 
During the public review period, the governor of Nebraska called a special session of the 
legislature to determine if siting legislation could be crafted and passed for pipeline routing in 
Nebraska. Facing the prospect of new state pipeline siting regulations applicable to the Sand 
Hills, together with the concern about the Keystone XL pipeline’s specific “preferred” route, the 
State Department announced that it would require additional information about alternative 
pipeline routes avoiding the environmentally sensitive Sand Hills area in Nebraska before moving 
forward with its national interest determination.144 Although the State Department did not decide 
that environmental issues led to a determination that the proposed project was not in the national 
interest, environmental issues identified in the final EIS, and further stressed in public comments, 
led to its decision to delay that determination until it gathered this information.  
Although no new decision deadline was established, State Department officials suggested that it 
would be “reasonable to expect that this process including a public comment period on a 
supplement to the final EIS consistent with NEPA could be completed as early as the first quarter 
of 2013.”145 In a prior press interview, President Obama also appeared to suggest that, 
                                                 
141 U.S. Department of State press release, “Keystone XL Final Environmental Impact Statement Released; Public 
Meetings Set,” August 26, 2011, http://www.state.gov/r/pa/prs/ps/2011/08/171082.htm. 
142 These additional public meetings are not part of the NEPA process. Considering the strong public interest in the 
pipeline proposal (both opposed and in favor), the public hearings were part of the State Department’s national interest 
determination. 
143 U.S. Department of State, November 10, 2011. 
144 U.S. Department of State, “Keystone XL Pipeline Project Review Process: Decision to Seek Additional 
Information,” Media Note, PRN 2011/1909, Office of the Spokesperson, November 10, 2011. 
145 U.S. Department of State, November 10, 2011. 
Congressional Research Service 
37 
Keystone XL Pipeline Project: Key Issues 
 
notwithstanding the delegation of Presidential Permit authority to the State Department, he would 
be personally involved in the final decision on the Keystone XL Pipeline permit application.146 
Directive to the President to Approve or Deny the Permit 
In the wake of the State Department determination that supplemental analysis was needed, 
Congress directed the President to make a determination on the Presidential permit application for 
the Keystone XL pipeline. Specifically, the Temporary Payroll Tax Cut Continuation Act of 2011 
(P.L. 112-78), enacted on December 23, 2011, included provisions requiring the Secretary to issue 
a permit for the project within 60 days, unless the President publicly determined the project to be 
not in the national interest.  
Subsequently, the State Department, with the President’s consent, announced that it would deny 
the Keystone XL permit on January 18, 2012. In its announcement the department stated that its 
decision “was predicated on the fact that [P.L. 112-78] ... passed in December does not provide 
sufficient time to obtain the information that we think is necessary to assess whether the project, 
in its current state, is in the national interest.”147 However, the department also stated that its 
decision did not preclude TransCanada from reapplying for a Presidential Permit in the future, 
although such a reapplication “will trigger ... a completely new review process.”148 
As a result of that denial, instead of developing a supplemental EIS incorporating analysis 
applicable to a new pipeline route through Nebraska, a new Presidential permit application 
process will be required. As a result, a “new” NEPA process will be required. Although much of 
the analysis and documentation will likely be the same, issuance of a draft and final EIS, and 
corresponding public and agency comment periods, will be required. 
 
Author Contact Information 
 Paul W. Parfomak 
  Linda Luther 
Specialist in Energy and Infrastructure Policy 
Analyst in Environmental Policy 
pparfomak@crs.loc.gov, 7-0030 
lluther@crs.loc.gov, 7-6852 
Robert Pirog 
  Adam Vann 
Specialist in Energy Economics 
Legislative Attorney 
rpirog@crs.loc.gov, 7-6847 
avann@crs.loc.gov, 7-6978 
 
Acknowledgments 
The authors would like to acknowledge the contributions of Kristina Alexander, Vanessa Burrows, and Jim 
Uzel to the content of this report. 
                                                 
146 KETV NewsWatch 7, “Uncut: KETV’s Rob McCartney Interviews President Obama,” Omaha, NE, November 1, 
2011, http://www.ketv.com/video/29652519/detail.html. 
147 U.S. Department of State, January 18, 2012. 
148 Ibid. 
Congressional Research Service 
38