link to page 1  link to page 1 
  
Updated December 23, 2019
Army Corps of Engineers: FY2020 Appropriations
Congress generally funds the civil works activities of the 
of new construction projects and new studies (e.g., six 
U.S. Army Corps of Engineers (USACE) in annual Energy 
projects and six studies using FY2020 appropriations).  
and Water Development appropriations acts. These 
activities include planning and construction of water 
Since the 112th Congress, earmark moratorium policies 
resource projects and operation and maintenance of 
have limited congressional direction of funding of site-
navigation improvements and certain multipurpose and 
specific projects (i.e., 
congressionally directed spending or 
flood control works (e.g., dams). For USACE civil works in 
earmarks). Beginning in FY2012, Congress has provided 
FY2020, President Trump requested $4.96 billion, inclusive 
additional funding for categories of USACE work. In 
of a May 13, 2019, amendment to the original request. As 
FY2020, Congress provided $2.53 billion in additional 
shown in
 Figure 1, Congress typically funds USACE above 
funding for 26 categories of USACE activities. After 
the President’s request. For FY2020, Congress provided 
Congress enacts USACE’s appropriations, the 
$7.65 billion (54% above the FY2020 request and 9% 
Administration develops a work plan for the fiscal year. In 
above FY2019 enacted) in Division C, Title I of H.R. 1865, 
the work plan, the Administration identifies the authorized 
Further Consolidated Appropriations Act, 2020, as signed 
USACE projects receiving the additional funding.  
by the President on December 20, 2019.  
Figure 2. USACE Account Funding, FY2014-FY2020 
Figure 1. Annual USACE Funding, FY2006-FY2020 
(nominal $ in billions) 
(nominal $ in billions) 
 
Source: CRS using congressional appropriations documents and 
President’s FY2020 budget request. 
Notes: Req = Budget request. ASA = Assistant Secretary of the 
Army. Regulatory = Permit program for nonfederal activities affecting 
  regulated waters and wetlands. FUSRAP = Formerly Utilized Sites 
Source: Congressional Research Service (CRS) using President’s 
Remedial Action Program. Congress did not adopt the request’s 
budget requests and congressional appropriations documents. 
proposal to create new USACE navigation-related accounts and did 
not transfer FUSRAP to the Department of Energy as requested. The 
USACE Funding and FY2020 Request 
figure shows the FY2020 request using traditional USACE accounts. 
Unlike federal agencies that distribute funds by formula or 
through competitive grant programs, USACE directly 
Selected FY2020 Topics of Deliberation 
engages in project planning and construction. It uses most 
of its appropriations for work on specific studies and 
Navigation Funding 
projects authorized by Congress. These activities are often 
In FY2019, total USACE funding for navigation-related 
cost shared with nonfederal project sponsors or users.  
activities from various USACE budget accounts was 
roughly $3.3 billion. The FY2020 request was $2.3 billion. 
The FY2020 request prioritized maintaining performance of 
The FY2020 work plan will determine FY2020 navigation 
existing infrastructure, as reflected by the shares of funds 
funding. Congress provided $378 million in FY2020 
requested for construction and operations and maintenance 
construction funds for a multiyear regional dredge 
(O&M; 
see Figure 2). The request would have initiated no 
demonstration program for deep-draft navigation in the 
new studies or construction projects (referred to as 
new 
Gulf of Mexico. Congress directed that the program explore 
starts). In response to similar requests in recent years, 
innovative means of executing dredging through combining 
Congress has required USACE to start a specified number 
work across multiple projects and construction and O&M. 
https://crsreports.congress.gov 
Army Corps of Engineers: FY2020 Appropriations 
Receipts from federal taxes on navigation interests are 
Construction Backlog and Upcoming Projects 
deposited in the Harbor Maintenance Trust Fund (HMTF) 
The FY2020 request sought to fund only ongoing 
and the Inland Waterways Trust Fund (IWTF). The trust 
navigation and flood risk reduction construction projects 
funds are used in the discretionary appropriations process to 
with benefit-cost ratios (BCRs) greater than 2.5 to 1 (i.e., 
pay for some USACE navigation activities. The HMTF 
benefits at least two and a half times project costs) or 
receives receipts from the Harbor Maintenance Tax (HMT) 
projects that addressed safety concerns. Many 
imposed on importers and domestic shippers using coastal 
congressionally authorized USACE projects do not have 
and Great Lakes ports. Harbor O&M appropriations have 
BCRs that meet the Administration’s 2.5 BCR threshold for 
not kept pace with HMT collections, resulting in an HMTF 
budget development. A persistent challenge for USACE 
balance of more than $9 billion. Stakeholders and 
and decisionmakers is how to address the agency’s backlog 
policymakers continue to discuss options and proposals for 
of $98 billion in authorized USACE construction activities, 
how to manage the HMTF balance and more closely align 
including those projects with BCRs below the 2.5 threshold. 
HMT collections and HMTF spending.  
A question for policymakers is whether—and, if so, how—
to advance projects in the backlog. The size of the backlog 
For inland waterways, the federal government pays for 
is determined in part by the level of appropriations and in 
most O&M. Most inland waterway construction and major 
part by additional project authorizations. USACE is 
rehabilitation costs are shared by the federal government 
currently planning various projects that each may cost 
(50%) and commercial users through the IWTF (50%). 
multiple billions of dollars to construct. The scale of the 
Availability of IWTF funds has at times constrained 
investments required to accomplish the authorized projects 
spending on waterway construction. IWTF monies derive 
and the projects being studied may further challenge the 
primarily from a $0.29 per gallon fuel tax on commercial 
current approach to federal participation in water resource 
vessels on designated federal waterways. IWTF receipts 
projects. Nonfederal project sponsors and federal 
and interest in FY2019 were $121 million. The FY2020 
policymakers are exploring options for project financing 
request was for $56 million from the IWTF. For FY2020, 
and for sharing costs and responsibilities among project 
Congress provided for $131 million from the IWTF and 
sponsors and beneficiaries. 
included language reducing the IWTF contribution for the 
Chickamauga Lock construction in Tennessee to 35%. 
Alternative Financing and Delivery 
Congress did not adopt the Administration’s proposal to 
Recent Congresses have authorized enhanced nonfederal 
apply an annual user fee on inland waterway commercial 
and private participation in USACE projects. Congress has 
vessels to be used for waterway construction and for 10% 
expanded the agency’s authorities to reimburse or credit 
of waterway O&M. 
nonfederal project sponsors for nonfederal work completed 
on authorized projects. In addition to post-construction 
Ecosystem Restoration and Flood Risk Reduction  
reimbursement, Congress in Section 1043 of the Water 
The May 2019 amendment to the FY2020 request sought 
Resources Reform and Development Act 2014 (WRRDA 
increased restoration funding for the Everglades from $69 
2014; P.L. 113-121) authorized the transfer of federal funds 
million to $205 million. The amendment brought the 
to nonfederal entities to use for the construction of 
request’s FY2020 total for USACE aquatic ecosystem 
authorized USACE projects. The FY2020 request proposed 
restoration efforts to $324 million. The FY2020 work plan 
to transfer $150 million to these entities. It also proposed to 
will determine which restoration activities receive 
accelerate project construction by applying $150 million in 
additional funding and the total restoration funding for the 
federal funds in conjunction with excess or advanced 
year.  
funding by nonfederal entities. Congress adopted neither 
proposal. Projects using alternative delivery approaches 
Recently, Congress has provided more funding for 
remain eligible for the additional funds provided by 
USACE’s flood risk reduction projects through 
Congress. 
supplemental appropriations than through annual 
appropriations. Together, P.L. 115-123 and P.L. 116-20 
For FY2020, neither the Administration nor Congress 
funded USACE’s
provided almost $16 billion in emergency supplemental 
 implementation of the Water 
appropriations for construction of USACE flood risk 
Infrastructure Finance and Innovation Act (WIFIA), 
reduction projects in qualifying states and territories. The 
authorized in WRRDA 2014. The U.S. Environmental 
FY2020 request for flood risk reduction was $1.0 billion, of 
Protection Agency (EPA) has an operating WIFIA program, 
which $209 million would have been for construction. The 
which issued its first loan in 2018. In P.L. 115-270, 
FY2020 work plan will determine the total FY2020 flood 
Congress authorized EPA to enter into interagency 
risk reduction funding. 
agreements to administer WIFIA programs for other 
agencies. Congress’s consideration of water resource 
Continuing Authorities Programs 
project financing and delivery may continue during 
Congress consistently has funded multiple USACE 
deliberations on future USACE appropriations and 
Continuing Authorities Programs (CAPs) to plan and 
authorizations on broader infrastructure initiatives. For 
construct projects of limited scope and cost. The FY2020 
more information on USACE funding, see CRS Report 
budget request proposed $4 million in aggregate for four 
R45326, 
Army Corps of Engineers Annual and 
CAPs. Congress provided almost $72 million for nine CAP 
Supplemental Appropriations: Issues for Congress. 
authorities for FY2020. (See CRS In Focus IF11106, 
Army 
Nicole T. Carter, Specialist in Natural Resources Policy   
Corps of Engineers: Continuing Authorities Programs.)  
Anna E. Normand, Analyst in Natural Resources Policy   
IF11137
https://crsreports.congress.gov 
Army Corps of Engineers: FY2020 Appropriations 
 
 
Disclaimer This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to 
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. 
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has 
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the 
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be 
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include 
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you 
wish to copy or otherwise use copyrighted material. 
 
https://crsreports.congress.gov | IF11137 · VERSION 3 · UPDATED