This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.
The Navy in 2017 initiated a new program, called the FFG(X) program, to build a class of 20 guided-missile frigates (FFGs). The Navy wants to procure the first FFG(X) in FY2020, the second in FY2021, and the remaining 18 at a rate of two per year in FY2022-FY2030. The Navy's proposed FY2019 budget requests $134.8 million in research and development funding for the program.
Although the Navy has not yet determined the specific design of the FFG(X), given the capabilities that the Navy wants the FFG(X) to have, the ship will likely be larger in terms of displacement, more heavily armed, and more expensive to procure than the Navy's Littoral Combat Ships (LCSs). The Navy envisages developing no new technologies or systems for the FFG(X)—the ship is to use systems and technologies that already exist or are already being developed for use in other programs.
The Navy's desire to procure the first FFG(X) in FY2020 does not allow enough time to develop a completely new design (i.e., a clean-sheet design) for the FFG(X). Consequently, the Navy intends to build the FFG(X) to a modified version of an existing ship design—an approach called the parent-design approach. The parent design could be a U.S. ship design or a foreign ship design. The Navy intends to conduct a full and open competition to select the builder of the FFG(X). Consistent with U.S. law, the ship is to be built in a U.S. shipyard, even if it is based on a foreign design. Multiple industry teams are reportedly competing for the program. Given the currently envisaged procurement rate of two ships per year, the Navy currently envisages using a single builder to build the ships. The Navy has not, however, ruled out the option of building the ships at two or three shipyards.
The FFG(X) program presents several potential oversight issues for Congress, including the following:
This report provides background information and discusses potential issues for Congress regarding the Navy's FFG(X) program, a program to procure a new class of 20 guided-missile frigates (FFGs). The Navy wants to procure the first FFG(X) in FY2020. The Navy's proposed FY2019 budget requests $134.8 million in research and development funding for the program.
The FFG(X) program presents several potential oversight issues for Congress. Congress's decisions on the program could affect Navy capabilities and funding requirements and the shipbuilding industrial base.
shipbuilding industrial base.
This report focuses on the FFG(X) program. A related Navy shipbuilding program, the Littoral
Combat Ship (LCS) program, is covered in a separate CRS report.1 Other CRS detail in CRS Report RL33741, Navy Littoral Combat
Ship (LCS) Program: Background and Issues for Congress, by Ronald O'Rourke. Other CRS
reports discuss the strategic context within which the FFG(X) program and other Navy
acquisition programs may be considered.2
In discussing its force-level goals and 30-year shipbuilding plans, the Navy organizes its surface
combatants into large surface combatants (LSCs), meaning the Navy'’s cruisers and destroyers,
and small surface combatants (SSCs), meaning the Navy'’s frigates, Littoral Combat ShipsLCSs, mine warfare ships,
and patrol craft.32 SSCs are smaller, less capable in some respects, and individually less expensive
to procure, operate, and support than LSCs.
SSCs can operate in conjunction with LSCs and other
Navy ships, particularly in higher-threat operating environments, or independently, particularly in
lower-threat operating environments.
In December 2016, the Navy released a goal to achieve and maintain a Navy of 355 ships,
including 52 SSCs, of which 32 are to be LCSs and 20 are to be FFG(X)s. Although patrol craft
are SSCs, they do not count toward the 52-ship SSC force-level goal, because patrol craft are not
considered battle force ships, which are the kind of ships that count toward the quoted size of the
Navy and the Navy'’s force-level goal.4
3
At the end of FY2018, the Navy'’s force of SSCs was projected to totaltotaled 27 battle force ships, including the following:
In contrast to cruisers and destroyers, which are designed to operate in higher-threat areas,
frigates are generally intended to operate more in lower-threat areas. U.S. Navy frigates perform
many of the same peacetime and wartime missions as U.S. Navy cruisers and destroyers, but
since frigates are intended to do so in lower-threat areas, they are equipped with fewer weapons,
less-capable radars and other systems, and less engineering redundancy and survivability than
cruisers and destroyers.5
4
The most recent class of frigates operated by the Navy was the Oliver Hazard Perry (FFG-7) class (
(Figure 1). A total of 51 FFG-7 class ships were procured between FY1973 and FY1984. The
ships entered service between 1977 and 1989, and were decommissioned between 1994 and 2015.
Figure 1. Oliver Hazard Perry (FFG-7) Class Frigate |
![]() |
Source: Photograph accompanying Dave Werner, |
.
In their final configuration, FFG-7s were about 455 feet long and had full load displacements of
roughly 3,900 tons to 4,100 tons. (By comparison, the Navy'’s Arleigh Burke [DDG-51] class
destroyers are about 510 feet long and have full load displacements of roughly 9,300 tons.)
Following their decommissioning, a number of FFG-7 class ships, like certain other decommissioned U.S. Navy ships, have been transferred to the navies of U.S. allied and partner countries.
In the program designation FFG(X), FF means frigate,65 G means guided-missile ship (indicating a
ship equipped with an area-defense AAW system),76 and (X) indicates that the specific design of
the ship has not yet been determined. FFG(X) thus means a guided-missile frigate whose specific
design has not yet been determined.8
The Navy notionally 7
Procurement Quantity
The Navy wants to procure a notional total of 20 FFG(X)s, which in combination with the Navy'’s planned total of
32 LCSs would meet the Navy'’s 52-ship SSC force-level goal. A total of 35 (rather than 32) LCSs
have been procured through FY2019, but Navy officials have stated that the Navy nevertheless
wants to procure 20 FFG(X)s.
The Navy’s 355-ship force-level goal is the result of a Force Structure Analysis (FSA) that the
Navy conducted in 2016. The Navy conducts a new or updated FSA every few years, and it is
currently conducting a new FSA that is scheduled to be completed by the end of 2019. Navy
officials have stated that this new FSA will likely not reduce the required number of small surface
combatants, and might increase it. Navy officials have also suggested that the Navy in coming
years may shift to a new fleet architecture that will include, among other things, a larger
proportion of small surface combatants.
Procurement Schedule
The Navy wants to procure the first FFG(X) in FY2020, the next 18 at a rate of two per year in
FY2021-FY2029, and the 20th in FY2030. Under the Navy’s FY2020 budget submission, the
first FFG(X) is scheduled to be delivered in July 2026, 72 months after the contract award date of
July 2020.
5
The designation FF, with two Fs, means frigate in the same way that the designation DD, with two Ds, means
destroyer. FF is sometimes translated less accurately as fast frigate. FFs, however, are not particularly fast by the
standards of U.S. Navy combatants—their maximum sustained speed, for example, is generally lower than that of U.S.
Navy aircraft carriers, cruisers, and destroyers. In addition, there is no such thing in the U.S. Navy as a slow frigate.
6 Some U.S. Navy surface combatants are equipped with a point-defense AAW system, meaning a short-range AAW
system that is designed to protect the ship itself. Other U.S. Navy surface combatants are equipped with an areadefense AAW system, meaning a longer-range AAW system that is designed to protect no only the ship itself, but other
ships in the area as well. U.S. Navy surface combatants equipped with an area-defense AAW system are referred to as
guided-missile ships and have a “G” in their designation.
7 When the ship’s design has been determined, the program’s designation might be changed to the FFG-62 program,
since FFG-61 was the final ship in the FFG-7 program. It is also possible, however, that the Navy could choose a
different designation for the program at that point. Based on Navy decisions involving the Seawolf (SSN-21) class
attack submarine and the Zumwalt (DDG-1000) class destroyer, other possibilities might include FFG-1000, FFG2000, or FFG-2100. (A designation of FFG-21, however, might cause confusion, as FFG-21 was used for Flatley, an
FFG-7 class ship.) A designation of FFG-62 would be consistent with traditional Navy practices for ship class
designations.
Congressional Research Service
3
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
s 52-ship SSC force-level goal.
The Navy's proposed FY2019 budget requested the procurement of the one LCS. This LCS was requested as the 32nd ship in the program. The Navy's proposed FY2019 budget, however, was submitted to Congress before Congress finalized its action on the Navy's FY2018 budget. In final action on the Navy's proposed FY2018 budget, Congress procured three LCSs, which was one more than the two that were requested for FY2018. The LCS that was requested in the Navy's proposed FY2019 budget thus became the 33rd potential LCS.
As part of its action on the Navy's proposed FY2019 budget, Congress procured three LCSs—two more than the one that was requested for FY2019. Thus, a total of 35 LCSs have been procured through FY2018—three more than the planned total of 32. The Navy has indicated that the procurement of three LCSs beyond the planned total of 32 will not reduce the its desired number of FFG(X)s—the Navy still wants to procure 20 FFG(X)s.
Following a planned final year of LCS procurement in FY2019, the Navy wants to procure the first FFG(X) in FY2020, the second in FY2021, and the remaining 18 at a rate of two per year in FY2022-FY2030.
Ship Capabilities and Design
As mentioned above, the (X) in the program designation FFG(X) means that the design of the
ship has not yet been determined. In general, the Navy envisages the FFG(X) as follows:
Given the above, the FFG(X) design will likely be larger in terms of displacement, more heavily
armed, and more expensive to procure than either the LCS or thean FF concept that emerged from
the February 2014 LCS program restructuring.
Figure 2 shows a January 2019 Navy briefing slide summarizing the FFG(X)’s planned
capabilities. For additional information on the FFG(X)’s planned capabilities, see the Appendix.8
Dual Crewing
To help maximize the time that each ship spends at sea, the Navy reportedly is considering
operating FFG(X)s with dual crews—an approach, commonly called blue-gold crewing, that the
Navy uses for operating its ballistic missile submarines and LCSs.9
8
RFI: FFG(X) - US Navy Guided Missile Frigate Replacement Program, accessed August 11, 2017, at
https://www.fbo.gov/index?s=opportunity&mode=form&tab=core&id=d089cf61f254538605cdec5438955b8e&
_cview=0.
9 See, for example, David B. Larter, “The US Navy Is Planning for Its New Frigate to Be a Workhorse,” Defense News,
January 30, 2018.
Congressional Research Service
4
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
the February 2014 LCS program restructuring.
A November 2, 2017, Navy information paper on the combat system to be used by the FFG(X) states the following:
In considering multiple options (Lockheed Martin's COMBATSS-21, General Dynamics' Integrated Combat Management System, and Raytheon's Ship Self Defense System) for the Frigate's Combat Management System (CMS), the following criteria were analyzed:
—Commonality—the degree to which the CMS was common across variants of LCS and the rest of the Navy.
—Performance—demonstrated ability to deliver a certifiable CMS able to meet LCS requirements, with respect to mission area capabilities.
—Cost—the total cost to design, develop, deliver, test and sustain the CMS.
A derivation of the AEGIS combat system widely used throughout the Navy and half of the LCS platforms, the Navy selected COMBATSS-21 as the Frigate CMS. It offered the highest level of commonality, best performance, and lowest cost of the three options.
Similar to the original FF, the primary mission areas for the FFG(X) will be Anti-Submarine Warfare, Surface Warfare, and Electromagnetic Maneuver Warfare. In addition, the FFG(X) will provide upgraded Air Warfare capability and improved lethality and survivability that include a scaled SPY-6 Fixed Array Radar, Standard Missile, Evolved Sea Sparrow Missile, full Surface Electronic Warfare Improvement Program Block 2 capability, and a Cooperative Engagement Capability. The CMS capabilities required to bring these enhancements are already included in Aegis; and thus, they are much simpler to cost effectively incorporate into COMBATSS-21.9
Figure 2 shows a January 2019 Navy briefing slide summarizing the FFG(X)'s planned capabilities.
To help maximize the time that each ship spends at sea, the Navy reportedly is considering operating FFG(X)s with dual crews—an approach, commonly called blue-gold crewing, that the Navy uses for operating its ballistic missile submarines and LCSs.10
The Navy wants the follow-on ships in the FFG(X) program (i.e., ships 2 through 20) to have an
average unit procurement cost of $800 million to $950 million each in constant 2018 dollars.11 The Navy reportedly believes that the ship's cost can be held closer to the $800 million figure.12 By way of comparison, the LCS that the Navy requested for FY2019 had an estimated average unit procurement cost of about $646 million (not including the cost of its embarked mission package), and the three DDG-51 class destroyers that the Navy has requested for FY2019 have an estimated average unit procurement cost of about $1,764 million each.
On July 10, 2017, the Navy released a Request for Information (RFI) to industry to solicit information for better understanding potential trade-offs between cost and capability in the FFG(X) design.13 On July 25, the Navy continued that effort by holding an industry day event. On July 28, the Navy posted its briefing slides for that event; some of those slides are reprinted in the Appendix.14 Responses to the RFI were due by August 24, 2017. The Navy states that it "received a very robust response to the FFG(X) RFI inclusive of [i.e., including] domestic and foreign ship designs and material vendor solutions."15 The Navy folded information gained through that RFI into its determination of the target unit procurement cost for the FFG(X).
The Navy has not yet established a target unit procurement cost for the lead ship in the program. As shown in Table 1 below, however, the Navy's FY2019 budget submission programs $1,228.2 million (i.e., about $1.2 billion) in procurement funding for FY2020, the year that the first FFG(X) is to be procured. The lead ship in the program will be considerably more expensive than the follow-on ships in the program, because the lead ship's procurement cost will incorporate most or all of the detailed design/nonrecurring engineering (DD/NRE) costs for the class. (It is a traditional Navy budgeting practice to attach most or all of the DD/NRE costs for a 10
See Sam LaGrone, “NAVSEA: New Navy Frigate Could Cost $950M Per Hull,” USNI News, January 9, 2018;
Richard Abott, “Navy Confirms New Frigate Nearly $1 Billion Each, 4-6 Concept Awards By Spring,” Defense Daily,
January 10, 2018: 1; Sydney J. Freedberg Jr., “Navy Says It Can Buy Frigate For Under $800M: Acquisition Reform
Testbed,” Breaking Defense, January 12, 2018; Lee Hudson, “Navy to Downselect to One Vendor for Future Frigate
Competition,” Inside the Navy, January 15, 2018; Richard Abott, “Navy Aims For $800 Million Future Frigate Cost,
Leveraging Modularity and Commonality,” Defense Daily, January 17, 2018: 3. The $800 million figure is the
objective cost target; the $950 million figure is threshold cost target. Regarding the $950 million figure, the Navy states
that
The average follow threshold cost for FFG(X) has been established at $950 million (CY18$). The
Navy expects that the full and open competition will provide significant downward cost pressure
incentivizing industry to balance cost and capability to provide the Navy with a best value solution.
FFG(X) cost estimates will be reevaluated during the Conceptual Design phase to ensure the
program stays within the Navy’s desired budget while achieving the desired warfighting
capabilities. Lead ship unit costs will be validated at the time the Component Cost Position is
10
Congressional Research Service
5
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
The Navy reportedly believes that the ship’s cost can be held closer to the $800 million figure.11
By way of comparison, the Navy estimates the average unit procurement cost of the three LCSs
procured in FY2019 at $523.7 million (not including the cost of each ship’s embarked mission
package), and the average unit procurement cost of the three DDG-51 class destroyers that the
Navy has requested for procurement in FY2020 at $1,821.0 million.
As shown in Table 1, the Navy’s proposed FY2020 budget requests $1,281.2 million for the
procurement of the first FFG(X). The lead ship in the program will be considerably more
expensive than the follow-on ships in the program, because the lead ship’s procurement cost
incorporates most or all of the detailed design/nonrecurring engineering (DD/NRE) costs for the
class. (It is a traditional Navy budgeting practice to attach most or all of the DD/NRE costs for a
new ship class to the procurement cost of the lead ship in the class.) As shown in Table 1, the
Navy’s FY2020 budget submission shows that subsequent ships in the class are estimated by the
Navy to cost roughly $900 million each in then-year dollars over the next few years.
The Navy’s FY2020 budget submission estimates the total procurement cost of 20 FFG(X)s at
$20,470.1 million (i.e., about $20.5 billion) in then-year dollars, or an average of about $1,023.5
million each. Since the figure of $20,470.1 million is a then-year dollar figure, it incorporates
estimated annual inflation for FFG(X)s to be procured out to FY2030.
new ship class to the procurement cost of the lead ship in the class.)
The Navy'Parent-Design Approach
The Navy’s desire to procure the first FFG(X) in FY2020 does not allow enough time to develop
a completely new design (i.e., a clean-sheet design) for the FFG(X). (Using a clean-sheet design
might defer the procurement of the first ship to about FY2023FY2024.) Consequently, the Navy intends
to build the FFG(X) to a modified version of an existing ship design—an approach called the
parent-design approach. The parent design could be a U.S. ship design or a foreign ship design.16
12
Using the parent-design approach can reduce design time, design cost, and technicalcost, schedule, and cost
technical risk in building the ship. The Coast Guard and the Navy are currently using the parent-designparentdesign approach for the Coast Guard'’s polar security cutter (i.e., polar icebreaker) program.17 The parent-design approach has also been used in the past for other Navy and Coast Guard ships, including Navy mine warfare ships18 and the Coast Guard'13 The
established in 3rd QTR FY19 prior to the Navy awarding the Detail Design and Construction
contract.
(Navy information paper dated November 7, 2017, provided by Navy Office of Legislative Affairs
to CRS and CBO on November 8, 2017.)
The Navy wants the average basic construction cost (BCC) of ships 2 through 20 in the program to be $495 million per
ship in constant 2018 dollars. BCC excludes costs for government furnished combat or weapon systems and change
orders. (Source: Navy briefing slides for FFG(X) Industry Day, November 17, 2017, slide 11 of 16, entitled “Key
Framing Assumptions.”)
11 See, for example, Justin Katz, “FFG(X) Follow-On Ships Likely yo Cost Near $800M, Down from $950M
Threshold,” Inside the Navy, January 21, 2019; Sam LaGrone, “Navy Squeezing Costs Out of GG(X) Program as
Requirements Solidify,” USNI News, January 22, 2019; David B. Larter, “The US Navy’s New, More Lethal Frigate Is
Coming into Focus,” Defense News, January 28, 2019.
12
For articles about reported potential parent designs for the FFG(X), see, for example, Chuck Hill, “OPC Derived
Frigate? Designed for the Royal Navy, Proposed for USN,” Chuck Hill’s CG [Coast Guard] Blog, September 15, 2017;
David B. Larter, “BAE Joins Race for New US Frigate with Its Type 26 Vessel,” Defense News, September 14, 2017;
“BMT Venator-110 Frigate Scale Model at DSEI 2017,” Navy Recognition, September 13, 2017; David B. Larter, “As
the Service Looks to Fill Capabilities Gaps, the US Navy Eyes Foreign Designs,” Defense News, September 1, 2017;
Lee Hudson, “HII May Offer National Security Cutter for Navy Future Frigate Competition,” Inside the Navy, August
7, 2017; Sydney J. Freedberg Jr., “Beyond LCS: Navy Looks To Foreign Frigates, National Security Cutter,” Breaking
Defense, May 11, 2017.
13 For more on the polar security cutter program, including the parent-design approach, see CRS Report RL34391,
Coast Guard Polar Security Cutter (Polar Icebreaker) Program: Background and Issues for Congress, by Ronald
Congressional Research Service
6
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
parent-design approach has also been used in the past for other Navy and Coast Guard ships,
including Navy mine warfare ships14 and the Coast Guard’s new Fast Response Cutters (FRCs).15
s new Fast Response Cutters (FRCs).19
As an additional measure for reducing technicalcost, schedule, and costtechnical risk in the FFG(X) program,
the Navy envisages developing no new technologies or systems for the FFG(X)—the ship is to
use systems and technologies that already exist or are already being developed for use in other
programs.
Number of Builders
Given the currently envisaged procurement rate of two ships per year, the Navy’s baseline plan
for the FFG(X) program envisages using a single builder to build the ships.2016 Consistent with U.S.
law,2117 the ship is to be built in a U.S. shipyard, even if it is based on a foreign design. Using a
foreign design might thus involve cooperation or a teaming arrangement between a U.S. builder
and a foreign developer of the parent design. The Navy has not, however, ruled out the option of
building the ships at two or three shipyards. At a December 12, 2018, hearing on Navy readiness
before two subcommittees (the Seapower subcommittee and the Readiness and Management
Support subcommittee, meeting jointly) of the Senate Armed Services Committee, the following
exchange occurred:
SENATOR ANGUS KING (continuing):
Talking about industrial base and acquisition, the frigate, which we'’re talking about, there
are 5 yards competing, there are going to be 20 ships. As I understand it, the intention now
is to award all 20 ships to the winner, it'’s a winner take all among the five. In terms of
industrial base and also just spreading the work, getting the—getting the work done faster,
talk to me about the possibility of splitting that award between at least two yards if not
three.
SECRETARY OF THE NAVY RICHARD SPENCER:
You bring up an interesting concept. There'’s two things going on here that need to be
weighed out. One, yes, we do have to be attentive to our industrial base and the ability to
keep hands busy and trained. Two, one thing we also have to look at, though, is the
balancing of the flow of new ships into the fleet because what we want to avoid is a spike
because that spike will come down and bite us again when they all go through regular
maintenance cycles and every one comes due within two or three years or four years. It gets very crowded. It's not off the table because we've not awarded anything yet, but we will—we will look at how best we can balance with how we get resourced and, if we have
O'Rourke
14 The Navy’s Osprey (MCM-51) class mine warfare ships are an enlarged version of the Italian Lerici-class mine
warfare ships.
15 The FRC design is based on a Dutch patrol boat design, the Damen Stan Patrol Boat 4708.
16 See, for example, Lee Hudson, “Navy to Downselect to One Vendor for Future Frigate Competition,” Inside the
Navy, January 15, 2018.
17 10 U.S.C. 7309 requires that, subject to a presidential waiver for the national security interest, “no vessel to be
constructed for any of the armed forces, and no major component of the hull or superstructure of any such vessel, may
be constructed in a foreign shipyard.” In addition, the paragraph in the annual DOD appropriations act that makes
appropriations for the Navy’s shipbuilding account (the Shipbuilding and Conversion, Navy account) typically contains
these provisos: “ ... Provided further, That none of the funds provided under this heading for the construction or
conversion of any naval vessel to be constructed in shipyards in the United States shall be expended in foreign facilities
for the construction of major components of such vessel: Provided further, That none of the funds provided under this
heading shall be used for the construction of any naval vessel in foreign shipyards.... ”
Congressional Research Service
7
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
gets very crowded. It’s not off the table because we’ve not awarded anything yet, but we
will—we will look at how best we can balance with how we get resourced and, if we have
the resources to bring expedition, granted, we will do that.18
Competing Industry Teams
At least five industry teams are reportedly competing for the FFG(X) program. Two of these
teams are offering designs for the FFG(X) that are modified versions of the two Littoral Combat
Ship (LCS) designs that the Navy has procured in prior years. The other three industry teams are
offering designs for the FFG(X) that are based on other existing ship designs. One of these three
other industry teams is proposing to build its design at one of the LCS shipyards.
the resources to bring expedition, granted, we will do that.22
The Navy intends to conduct a full and open competition to select the builder of the FFG(X), including proposals based on either U.S. or foreign parent designs. On February 16, 2018, the Navy awarded five FFG(X) conceptual design contracts with a value
of $15.0 million each to
A February 16, 2018, press report states the following:
"These conceptual designs will reduce FFG(X) risk by enabling industry to mature designs to meet the approved FFG(X) capability requirements," read a late Friday [February 16] statement from Naval Sea Systems Command.
"The contracts based on these requirements will facilitate maturing multiple designs during the 16 months of the conceptual design phase, and will allow the Navy to better understand the cost and capability drivers across the various design options. Furthermore, this will inform the final specifications for a full and open competition with a single source award in FY20 for Detail Design and Construction (DD&C) of the FFG(X)."...
The Navy would not confirm how many groups bid for the work. At least one U.S.-German team that was not selected for a design contract, Atlas USA and ThyssenKrupp Marine Systems, told USNI News they had submitted for the competition....
competition....
During last month'’s Surface Navy Association [annual symposium], several shipbuilders
outlined their designs for the FFG(X) competition.
Austal USA
Austal USA Shipyard: Austal USA in Mobile, Ala.
Parent Design: Independence-class [i.e., LCS-2 class] Littoral Combat Ship
One of the two Littoral Combat Ship builders, Austal USA has pitched an upgunned variant
of the Independence-class LCS as both a foreign military sales offering and as the answer
to the Navy'’s upgunned small surface combatant and then frigate programs. Based on the
3,000-ton aluminum trimaran design, the hull boasts a large flight deck and space for up to
16 Mk-41 Vertical Launching System (VLS) cells.
18
Source: Transcript of hearing posted at CQ.com.
Department of Defense, Contracts, Press Operations, Release No: CR-032-18, February 16, 2018 (i.e., the DOD
contracts award page for February 16, 2018). See also Ben Werner, “Navy Exercises Options For Additional Future
Frigate Design Work,” USNI News, July 31, 2018; Rich Abott, “Navy Awards Mods To FFG(X) Design Contracts,”
Defense Daily, August 1, 2018; Kris Osborn, “The Navy Is Moving Fast to Build a New Frigate. Here Is What We
Know,” National Interest, August 1, 2018.
19
Congressional Research Service
8
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Fincantieri Marine Group
Fincantieri Marine Group
Shipyard: Fincantieri Marinette Marine in Marinette, Wisc.
Parent Design: Fincantieri Italian FREMM
As part of the stipulations of the FFG(X) programs, a contractor can offer just one design
in the competition as a prime contractor but may also support a second bid as a
subcontractor. Fincantieri elected to offer its 6,700-ton Italian Fregata europea multi-missionemultimissione (FREMM) design for construction in its Wisconsin Marinette Marine shipyard,
as well as partner with Lockheed Martin on its Freedom-class pitch as a subcontractor. The
Italian FREMM design features a 16-cell VLS as well as space for deck-launched anti-ship
missiles.
General Dynamics Bath Iron Works
Shipyard: Bath Iron Works in Bath, Maine
Parent Design: Navantia Álvaro de Bazán-class F100 Frigate
The 6,000-ton air defense guided-missile frigates fitted with the Aegis Combat System
have been in service for the Spanish Armada since 2002 and are the basis of the Australian
Hobart-class air defense destroyers and the Norwegian Fridtjof Nansen-class frigates. The
Navantia partnership with Bath is built on a previous partnership from the turn of the
century. The F100 frigates were a product of a teaming agreement between BIW, Lockheed
Martin and Navantia predecessor Izar as part of the Advanced Frigate Consortium from
2000.
Huntington Ingalls Industries
Shipyard: Ingalls Shipbuilding in Pascagoula, Miss.
Parent Design: Unknown
Out of the competitors involved in the competition, HII was the only company that did not
present a model or a rendering of its FFG(X) at the Surface Navy Association symposium
in January. A spokeswoman for the company declined to elaborate on the offering when
contacted by USNI News on Friday. In the past, HII has presented a naval version of its
Legend-class National Security Cutter design as a model at trade shows labeled as a "Patrol Frigate."
Lockheed Martin
“Patrol Frigate.” Lockheed Martin Shipyard: Fincantieri Marinette Marine in Marinette, Wisc.
Parent Design: Freedom-class [i.e., LCS-1 class] Littoral Combat Ship
Of the two LCS builders, Lockheed Martin is the first to have secured a foreign military
sale with its design. The company'’s FFG(X) bid will have much in common with its
offering for the Royal Saudi Navy'’s 4,000-ton multi-mission surface combatant. The new
Saudi ships will be built around an eight-cell Mk-41 vertical launch system and a 4D air
search radar. Lockheed has pitched several other variants of the hull that include more VLS
cells.
"
“We are proud of our 15-year partnership with the U.S. Navy on the Freedom-variant
Littoral Combat Ship and look forward to extending it to FFG(X),"” said Joe DePietro,
Lockheed Martin vice president of small combatants and ship systems in a Friday evening
statement.
"
Congressional Research Service
9
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
“Our frigate design offers an affordable, low-risk answer to meeting the Navy'’s goals of a
larger and more capable fleet.”20
larger and more capable fleet."24
The Navy wants to release a request for proposals (RFP) in the fourth quarter of FY2019 and award a detailed design and construction (DD&C) contract for the program in fourth quarter of FY2020.25 Being a recipient of a conceptual design contract is not a requirement for competing for the DD&C contract.
Block Buy Contracting
As a means of reducing their procurement cost, the Navy envisages using one or more fixed-price
block buy contracts to procure the ships.26
21
Program Funding
Table 1 shows funding for the FFG(X) program under the Navy's FY2019’s FY2020 budget submission.
Table 1. FFG(X) Program Funding
Millions of then-year dollars, rounded to nearest tenth.
Research and development
Procurement
Prior
years
FY18
FY19
84.6
137.7
132.8
59.0
85.3
75.4
70.7
72.1
0
0
0
1,281.2
2,057.0
1,750.4
1,792.1
1,827.9
(1)
(2)
(2)
(2)
(2)
FY20
(Procurement quantity)
FY21
FY22
FY23
FY24
Source: Navy FY2020 budget submission.
Notes: Research and development funding is located in PE (Program Element) 0603599N, Frigate Development,
which is line 54 in the FY2020 Navy research and development account.
Issues for Congress
FY2020 Funding Request
One issue for Congress is whether to approve, reject, or modify the Navy’s FY2020 funding
request for the program. In assessing this question, Congress may consider, among other things,
whether the work the Navy is proposing to do in the program in FY2020 is appropriate, and
Millions of then-year dollars, rounded to nearest tenth.
Prior years |
FY17 |
FY18 |
FY19 |
FY20 |
FY21 |
FY22 |
FY23 |
|
Research and development |
18.9 |
83.1 |
141.1 |
134.8 |
75.4 |
77.6 |
70.5 |
72.0 |
Procurement |
0 |
0 |
0 |
0 |
1,228.2 |
849.1 |
1,791.9 |
1,792.0 |
(Procurement quantity) |
(1) |
(1) |
(2) |
(2) |
Source: Navy FY2019 budget submission and (for FY2018) explanatory statement for FY2018 DOD appropriations act (Division C of H.R. 1625/P.L. 115-141 of March 23, 2018).
Notes: Research and development funding is located in PE (Program Element) 0603599N, Frigate Development (Navy research and development account line 57 in the FY2019 budget submission), and additionally (for prior years only), PE 0603581, Littoral Combat Ship.
One potential oversight issue for Congress is whether to approve, reject, or modify the Navy's FY2019 funding request for the program. In assessing this question, Congress may consider, among other things, whether the work the Navy is proposing to do in the program in FY2019 is appropriate, and whether the Navy has accurately priced that work.
Another potential oversight issue for Congress is whether the Navy has accurately identified the capability gaps and mission needs to be addressed by the program, particularly in light of recent changes in the international security environment and debate over the future U.S. role in the world,27 and whether the Navy has performed a formal, rigorous analysis of this issue, as opposed to relying solely on the subjective judgments of Navy and DOD leaders.
Subjective judgments can be helpful, particularly in terms of capturing knowledge and experience that is not easily reduced to numbers, in taking advantage of the "wisdom of the crowd," and in coming to conclusions and making decisions quickly. On the other hand, a process that relies heavily on subjective judgments can be vulnerable to groupthink (i.e., a situation in which a group acts in a way that discourages creativity or individual responsibility), can overlook counterintuitive results regarding capability gaps and mission needs (i.e., results that go against the conventional wisdom), and, depending on the leaders involved, can emphasize those leaders' understanding of the Navy's needs in the nearer term, as opposed to what a formal intelligence projection of future adversary capabilities—such as those used in formal, rigorous analyses—might indicate what the Navy will need years from now, when the new ships will actually be in the fleet.
A May 18, 2018, Navy information paper states the following:
The analytics behind the requirement for a Small Surface Combatant (SSC) with the above capabilities and characteristics started with work completed during the SSC Task Force (SSCTF)between February and November 2014, which recommended improvements to LCS in order to provide a more lethal and survivable SSC. The SSCTF culminated in a CNO and Joint Requirements Oversight Council (JROC) validated LCS Flight 0+ Frigate Increment Capabilities Development Document (CDD) in April 2016....
Subsequent to the SSCTF effort, the FY16 NDAA directed three independent 2030 Future Fleet Architecture (FFA) analysis studies. The three NDAA mandated studies were conducted by CSBA (Center for Strategic and Budgetary Assessments), the MITRE Corporation, and the Navy Project Team. Each presented different visions of a 2030 FFA across platforms and missions, but all coalesced around the need for a multi-mission SSC with specific capabilities/characteristics, forward stationed and rotationally crewed to support forward presence, deterrence, and lethal distributed operations within budgetary constraints....
The requirements for a future Small Surface Combatant (SSC) or Guided Missile Frigate (FFG) proposed in the three NDAA mandated FFA studies were validated through a series of table top exercises (TTX) and campaign analyses conducted by OPNAV N81 in support of N9....
In January 2017, the Navy convened the FFG Requirements Evaluation Team to analyze the capabilities needed above those prescribed by the FF CDD [Capability Development Document] to include Air Warfare (Local Air Defense), survivability (reduced susceptibility and vulnerability), and EMW to support DMO in a contested environment. This update to the FF CDD reflected a maturing of the three FFG concepts presented in the NDAA studies coupled with a thorough analysis of capability gaps and mission needs that are reflected in the draft FFG(X) CDD requirements. To date, these requirements have been continually refined and recent Future Surface Combatant and FFA wargames have also confirmed and refined the necessity for a SSC with the capability required by the FFG(X) CDD.28
A December 4, 2017, press report states the following:
Rear Adm. Ron Boxall [the Navy's director of surface warfare] told USNI News today at the American Society of Naval Engineers' annual Combat Systems Symposium that the 60-day effort by the FFG Requirements Evaluation Team helped each stakeholder understand how their needs interacted with others' to affect cost, schedule, operational effectiveness and more..
"I was very pleased with where we came out because some of the decisions were much more about the concept of what we're getting instead of the actual platform we're getting," Boxall told USNI News during a question and answer period after his remarks....
... Boxall said the process the 60-day requirements evaluation teams have used is also very exciting for the requirements community. In some past cases, such as the CG(X) next-generation cruiser, requirements officers have spent years on a program, only to have it ultimately canceled.29 With this new process that brings together all stakeholders right at the start, along with computer tools that allow them to generate numerous iterations of a ship design, the Navy can work through a program's requirements much faster and come up with a more mature and technologically informed set of requirements.
"What's exciting about this [is] we're starting to create a repository of knowledge that we can use to reiterate as we need to go along," he told USNI News after the event.
"We've not done a good job of doing that in the past, it's was kind of resident in the requirements officers and the acquisition team; now we're actually doing it with the models—here's what this combination of capabilities proves to get to us, and as we learn things or technology improves or costs more or less, we can make adjustments a lot more quickly."
Asked about applying this methodology to more programs, like the Future Surface Combatant family of systems that followed the canceled CG(X), Boxall said those discussions have already begun.
"We actually took some of the work we're doing with Future Surface Combatant and brought that back (to the FFG Requirements Evaluation Team); we said hey, the Future Surface Combatant is about where we're going with the whole family of ships, so if we're going to be producing an FFG of the future that's going to be kind of at the small surface combatant size, then we don't want that to be disconnected," he said. And moving forward with the large, small and unmanned surface combatants the Navy is considering for the Future Surface Combatant family, Boxall said the designs that have already been iterated can be used as a good starting point for future efforts.30
A December 5, 2017, press report, reporting on the same symposium, stated the following:
The Navy is convening a team similar to one used to help create the guided-missile future frigate FFG(X) to also alter the direction of the Zumwalt-class [DDG-1000] destroyers, Rear Adm. Ronald Boxall, director of Surface Warfare, said here at the 2017 Combat Systems Symposium organized by the American Society of Naval Engineers (ASNE)....
When working out new frigate requirements, the Navy looked to see what capabilities they could take from its predecessor, the Littoral Combat Ship (LCS) to help make it ready to be on contract by fiscal year (FY) 2020. He said that process involved meetings involving officials in the Navy's requirements, acquisition, and fleet teams.
Personnel "learned why they were stupid" from the perspective of the other components, he said. Each component thought the other made serious mistakes, but also learned what those teams thought of them.
Boxall said the fleet personnel would say what the warfighters need to accomplish a certain mission, the acquisition teams would draw up what they asked for and more, "then the price goes through the roof."
He said to resolve the high price versus requirements problems there has to be a voice of "hey, I want that but it's really expensive. And you say, well, here's where we can get 'tastes great and less filling'" to balance priorities and price.
Boxall said he was very pleased with the decisions the Navy made going into the FFG(X) requirements and now they decided to try it again with the Zumwalt-class.31
Another potential oversight issue for Congress is whether procuring a new class of FFGs is the best or most promising general approach for addressing the identified capability gaps and mission needs, and whether the Navy has performed a formal, rigorous analysis of this issue, as opposed to relying solely on subjective judgments of Navy or DOD leaders. Similar to the points made in the previous section, subjective judgments, though helpful, can overlook counterintuitive results regarding the best or most promising general approach. Potential alternative general approaches for addressing identified capability gaps and mission needs in this instance include (to cite a few possibilities) modified LCSs, FFs, destroyers, aircraft, unmanned vehicles, new weapons, new operational concepts, or some combination of these things.
A formal, rigorous analysis to determine the best or most promising general approach for addressing a set of capability gaps or mission needs was in the past sometimes referred to as an analysis of multiple concepts (AMC), or more generally as competing the mission. It could also be called an analysis of alternatives (AOA), though that term can also be applied to an analysis for refining the desired capabilities of the best or most promising approach that has been identified by an AMC.
As discussed in CRS reports on the LCS program over the years, the Navy did not perform a formal, rigorous analysis of this kind prior to announcing the start of the LCS program in November 2001, and this can be viewed as a root cause of much of the debate and controversy the that attended the LCS program, and of the program's ultimate restructurings in February 2014 and December 2015.32
See also the passages from the May 18, 2018, Navy information paper and the December 4 and 5, 2017, press reports that are quoted in the previous section.
Another potential oversight issue for Congress whether the Navy has chosen the appropriate amount of growth margin to whether the Navy has accurately priced that work.
Cost, Capabilities, and Growth Margin
Another issue for Congress is whether the Navy has appropriately defined the cost, capabilities,
and growth margin of the FFG(X).
Analytical Basis for Desired Ship Capabilities
One aspect of this issue is whether the Navy has an adequately rigorous analytical basis for its
identification of the capability gaps or mission needs to be met by the FFG(X), and for its
Sam LaGrone and Megan Eckstein, “Navy Picks Five Contenders for Next Generation Frigate FFG(X) Program,”
USNI News, February 16, 2018. See also David B. Larter, “Navy Awards Design Contracts for Future Frigate,”
Defense News, February 16, 2018; Lee Hudson, “Navy Awards Five Conceptual Design Contracts for Future Frigate
Competition,” Inside the Navy, February 19, 2018.
21 For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy
Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz.
20
Congressional Research Service
10
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
decision to meet those capability gaps or mission needs through the procurement of a FFG with
the capabilities outlined earlier in this CRS report. The question of whether the Navy has an
adequately rigorous analytical basis for these things was discussed in greater detail in earlier
editions of this CRS report.22
Balance Between Cost and Capabilities
Another potential aspect of this issue is whether the Navy has arrived at a realistic balance
between its desired capabilities for the FFG(X) and the its estimated procurement cost for the
ship. An imbalance between these two could lead to an increased risk of cost growth in the
program. The Navy could argue that a key aim of the five FFG(X) conceptual design contracts
and other preliminary Navy interactions with industry was to help the Navy arrive at a realistic
balance by informing the Navy’s understanding of potential capability-cost tradeoffs in the
FFG(X) design.
Number of VLS Tubes
Another potential aspect of this issue concerns the planned number of Vertical Launch System
(VLS) missile tubes on the FFG(X). The VLS is the FFG(X)’s principal (though not only) means
of storing and launching missiles. As shown in Figure 2 (see the box in the upper-left corner
labeled “AW,” meaning air warfare), the FFG(X) is to be equipped with 32 Mark 41 VLS tubes.
(The Mark 41 is the Navy’s standard VLS design.)
Supporters of requiring the FFG(X) to be equipped with a larger number of VLS tubes, such as
48, might argue that the FFG(X) is to be roughly half as expensive to procure as the DDG-51
destroyer, and might therefore be more appropriately equipped with 48 VLS tubes, which is onehalf the number on recent DDG-51s. They might also argue that in a context of renewed great
power competition with potential adversaries such as China, which is steadily improving its naval
capabilities,23 it might be prudent to equip the FFG(X)s with 48 rather than 32 VLS tubes, and
that doing so might only marginally increase the unit procurement cost of the FFG(X).
Supporters of requiring the FFG(X) to have no more than 32 VLS tubes might argue that the
analyses indicating a need for 32 already took improving adversary capabilities (as well as other
U.S. Navy capabilities) into account. They might also argue that the FFG(X), in addition to
having 32 VLS tubes, is also to have a separate, 21-cell Rolling Airframe Missile (RAM) missile
launcher (see again the “AW” box in the upper-left corner of Figure 2), and that increasing the
number of VLS tubes from 32 to 48 would increase the procurement cost of a ship that is
intended to be an affordable supplement to the Navy’s cruisers and destroyers.
Potential oversight questions for Congress might be: What would be the estimated increase in unit
procurement cost of the FFG(X) of increasing the number of VLS tubes from 32 to 48? What
would be the estimated increase in unit procurement cost of equipping the FFG(X) with 32 VLS
tubes but designing the ship so that the number could easily be increased to 48 at some point later
in the ship’s life?
22
See, for example, the version of this report dated February 4, 2019.
For more on China’s naval modernization effort, see CRS Report RL33153, China Naval Modernization:
Implications for U.S. Navy Capabilities—Background and Issues for Congress, by Ronald O'Rourke.
23
Congressional Research Service
11
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Growth Margin
Another potential aspect of this issue is whether, beyond the specific question of the number of
VLS tubes, the Navy more generally has chosen the appropriate amount of growth margin to
incorporate into the FFG(X) design. As shown in the Appendixincorporate into the FFG(X) design. As shown in the Appendix, the Navy wants the FFG(X)
design to have a growth margin (also called service life allowance) of 5%, meaning an ability to
accommodate upgrades and other changes that might be made to the ship'’s design over the course
of its service life that could require up to 5% more space, weight, electrical power, or equipment
cooling capacity. As shown in the AppendixAppendix, the Navy also wants the FFG(X) design to have an
additional growth margin (above the 5% factor) for accommodating a future directed energy
system (i.e., a laser or high-power microwave device) or an active electronic attack system (i.e.,
electronic warfare system).
Supporters could argue that a 5% growth margin is traditional for a ship like a frigate, that the
FFG(X)'’s 5% growth margin is supplemented by the additional growth margin for a directed
energy system or active electronic attack system, and that requiring a larger growth margin could
make the FFG(X) design larger and more expensive to procure.
Skeptics might argue that a larger growth margin (such as 10%—a figure used in designing
cruisers and destroyers) would provide more of a hedge against the possibility of greater-than-anticipatedthananticipated improvements in the capabilities of potential adversaries such as China,33 that a limited
growth margin was a concern in the FFG-7 design,3424 and that increasing the FFG(X) growth
margin from 5% to 10% would have only a limited impact on the FFG(X)'’s procurement cost.
Another
A potential oversight issue for Congress concerns the Navy's proposed acquisition strategy for the program, including the Navy's intent to use a parent-design approach for the question for Congress might be: What would be the estimated increase in
unit procurement cost of the FFG(X) of increasing the ship’s growth margin from 5% to 10%?
Parent-Design Approach
Another potential oversight issue for Congress concerns the parent-design approach for the
program. One alternative would be to use a clean-sheet design approach, under which
procurement of the FFG(X) would begin about FY2023FY2024 and procurement of LCSs might be
extended through about 2022.
2023.
As mentioned earlier, using the parent-design approach can reduce design time, design cost, and
technical, schedule, and cost risk in building the ship. A clean-sheet design approach, on the other
hand, might result in a design that more closely matches the Navy'’s desired capabilities for the
FFG(X), which might make the design more cost-effective for the Navy over the long run. It
might also provide more work for the U.S. ship design and engineering industrial base.
Another possible alternative would be to consider frigate designs that have been developed, but
for which there are not yet any completed ships. This approach might make possible
consideration of designs, such as (to cite just one possible example) the UK'’s new Type 26 frigate
design, production of which was in its early stages in 2018. Compared to a clean-sheet design
approach, using a developed-but-not-yet-built design would offer a reduction in design time and
cost, but might not offer as much reduction in technical, schedule, and cost risk in building the
ship as would be offered by use of an already-built design.
24
See, for example, See U.S. General Accounting Office, Statement of Jerome H. Stolarow, Director, Procurement and
Systems Acquisition Division, before the Subcommittee on Priorities and Economy in Government, Joint Economic
Committee on The Navy’s FFG-7 Class Frigate Shipbuilding Program, and Other Ship Program Issues, January 3,
1979, pp. 9-11.
Congressional Research Service
12
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Cost, Schedule, and Technical Risk
Another potential oversight issue for Congress concerns cost, schedule, and technical risk in the
FFG(X) program. The Navy can argue that the program’s cost, schedule, and technical risk has
been reduced by use of the parent-design approach and the decision to use only systems and
technologies that already exist or are already being developed for use in other programs, rather
than new technologies that need to be developed.
Skeptics, while acknowledging that point, might argue that lead ships in Navy shipbuilding
programs inherently pose cost, schedule, and technical risk, because they serve as the prototypes
for their programs, and that, as detailed by CBO25 and GAO,26 lead ships in Navy shipbuilding
programs in many cases have turned out to be more expensive to build than the Navy had
estimated. An April 2018 report from the Government Accountability Office on the status of
various Department of Defense (DOD) acquisition programs states the following about the
FFG(X) program:
Current Status
In May 2017, the Navy shifted away from its plan for a new frigate derived from minor
modifications to an LCS design and now plans to select a new frigate design and
shipbuilder through a full and open competition that is not limited to LCS derivatives. The
program intends to leverage the proposed capabilities of the original frigate program and
ship as would be offered by use of an already-built design.
Another potential oversight issue for Congress is whether to approve, reject, or modify the Navy's plan to procure a final LCS in FY2019 and shift to procurement of FFG(X)s starting in FY2020. As noted earlier, the Navy's plan to end LCS procurement in FY2019 and shift to FFG(X) procurement starting in FY2020 would achieve the Navy's 52-ship SSC force-level goal by about 2035. The Navy's plan would also have implications for workloads and employment levels at the two LCS shipyards and their supplier firms
There are many possible alternatives to the Navy's plan to end LCS procurement in FY2019 and shift to FFG(X) procurement starting in FY2020. One of these, for example, would be to select a winner in the FFG(X) competition and begin procuring that design in FY2020, as the Navy currently plans, but also produce FFG(X)s at one or both of the LCS yards. Under this option, if the winner of the FFG(X) competition is one of the LCS builders, that builder might build more than half of the FFG(X)s to its winning design, and the other LCS yard would build less than half of the FFG(X)s to its own nonwinning (but presumably still-capable) FFG(X) design. Alternatively, if the winner of the FFG(X) competition is neither of the LCS builders, the winning bidder build might build the largest share of the FFG(X)s to its winning design, and the two LCSs yards would each build a smaller number of FFG(X)s to their own nonwinning (but presumably still-capable) designs.
Supporters of this option might argue that it could
Opponents of this plan might argue that it could
Another possible alternative to the Navy's plan to end LCS procurement in FY2019 and shift to FFG(X) procurement starting in FY2020 would be would be to select a winner in the FFG(X) competition and begin procuring that design in FY2020, as the Navy currently plans, but shift Navy shipbuilding work at one of the LCS yards (if the other wins the FFG(X) competition) or at both of the LCS yards (if neither wins the FFG(X) competition) to the production of sections of larger Navy ships (such as DDG-51 destroyers or amphibious ships) that undergo final assembly at other shipyards. Under this option, in other words, one or both of the LCS yards would be converted into feeder yards supporting the production of larger Navy ships that undergo final assembly at other shipyards. This option might help maintain workloads and employment levels at one or both of the LCS yards, and might alleviate capacity constraints at other shipyards, permitting certain parts of the Navy's 355-ship force-level objective to be achieved sooner.
The concept of feeder yards in naval shipbuilding was examined at length in a 2011 RAND report.36 The Navy in recent years has made some use of the concept:
The above options are only two of many possible alternatives to the Navy's plan to end LCS procurement in FY2019 and shift to FFG(X) procurement starting in FY2020.
Another potential oversight issue concerns technical risk in the FFG(X) program. An April 2018 report from the Government Accountability Office on the status of various DOD acquisition programs states the following about the FFG(X) program:
Current Status
In May 2017, the Navy shifted away from its plan for a new frigate derived from minor modifications to an LCS design and now plans to select a new frigate design and shipbuilder through a full and open competition that is not limited to LCS derivatives. The program intends to leverage the proposed capabilities of the original frigate program and expand upon them to create a more lethal and survivable ship.
expand upon them to create a more lethal and survivable ship.
In fiscal year 2018, the FFG(X) program plans to focus on system specifications
development and approval, acquisition program documentation needs, test strategy
development, and combat management system integration. The program released a request
for conceptual design proposals in November 2017 and plans to award multiple contracts
in 2018 in an effort to reduce risk by maturing industry designs to meet FFG(X) capability
needs.
Consistent with statute and knowledge-based practices, the Navy has scheduled a
preliminary design review prior to a development start decision in February 2020. To
support the development start decision, the program expects to complete an independent
cost estimate, affordability and should-cost analyses, and an independent technical risk
assessment. Although the number of planned frigates remains uncertain due to previous
Secretary of Defense direction to cap the combined total of LCS and frigates at 40 ships,
the program plans to award what the Navy refers to as a "“block buy"” contract for FFG(X)
detail design and construction in September 2020. This block buy contract, which the Navy
plans to award to a single shipbuilder, is intended to achieve more favorable pricing, but
as planned, would require the Navy to commit to more than 1 year'’s worth of procurement
in a single contract. If the Navy requests congressional authorization during 2019 for the
planned fiscal year 2020 block buy, the Navy will lack key knowledge, such as an
independent cost estimate, to support its request.
Program Office Comments
We provided a draft of this assessment to the program office for review and comment. The
program stated that conceptual design allows the Navy to mature multiple designs and
better understand cost and capability drivers across design options before a detail design
See Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2019 Shipbuilding Plan, October 2018, p.
25, including Figure 10.
26 See Government Accountability Office, Navy Shipbuilding[:] Past Performance Provides Valuable Lessons for
Future Investments, GAO-18-238SP, June 2018, p. 8.
25
Congressional Research Service
13
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
and construction award, as well as inform final specifications that will achieve a best value
solution.27
Procurement of LCSs in FY2020 as Hedge against FFG(X) Delay
Another potential issue for Congress is whether any additional LCSs should be procured in
FY2020 as a hedge against potential delays in the FFG(X) program. Supporters might argue that,
as detailed by GAO,28 lead ships in Navy shipbuilding programs in many cases encounter
schedule delays, some quite lengthy, and that procuring additional LCSs in FY2020 could hedge
against that risk at reasonable cost by taking advantage of hot LCS production lines. Skeptics
might argue that the Navy does not have a requirement for any additional LCSs, and that funding
the procurement of additional LCSs in FY2020 could reduce FY2020 funding available for other
Navy or DOD programs, with an uncertain impact on net Navy or DOD capabilities.
Potential Industrial-Base Impacts of Shifting Procurement from
LCSs to FFG(X)s
Another issue for Congress concerns the potential industrial-base impacts of the Navy’s plan to
shift procurement of small surface combatants from LCSs to FFG(X)s starting in FY2020,
particularly in terms of future workloads and employment levels at the two LCS shipyards, if one
or both of these yards are not involved in building FFG(X)s.
If a design proposed for construction at one of the LCS shipyards is chosen as the winner of the
FFG(X) competition, then other things held equal (e.g., without the addition of new work other
than building LCSs), workloads and employment levels at the other LCS shipyard (the one not
chosen for the FFG(X) program), as well as supplier firms associated with that other LCS
shipyard, would decline over time as the other LCS shipyard’s backlog of prior-year-funded
LCSs is completed and not replaced with new FFG(X) work. If no design proposed for
construction at an LCS shipyard is chosen as the FFG(X)—that is, if the winner of the FFG(X)
competition is a design to be built at a shipyard other than the two LCS shipyards—then other
things held equal, employment levels at both LCS shipyards and their supplier firms would
decline over time as their backlogs of prior-year-funded LCSs are completed and not replaced
with FFG(X) work.29
As mentioned earlier, the Navy’s current baseline plan for the FFG(X) program is to build
FFG(X)s at a single shipyard. One possible alternative to this baseline plan would be to build
FFG(X)s at two or three shipyards, including one or both of the LCS shipyards. This alternative is
discussed further in the following section. Another possible alternative would be would be to shift
Navy shipbuilding work at one of the LCS yards (if the other wins the FFG(X) competition) or at
both of the LCS yards (if neither wins the FFG(X) competition) to the production of sections of
larger Navy ships (such as DDG-51 destroyers or amphibious ships) that undergo final assembly
at other shipyards. Under this option, in other words, one or both of the LCS yards would
27
Government Accountability Office, Weapon Systems Annual Assessment[:] Knowledge Gaps Pose Risks to
Sustaining Recent Positive Trends, GAO-18-360SP, p. 115.
28 See Government Accountability Office, Navy Shipbuilding[:] Past Performance Provides Valuable Lessons for
Future Investments, GAO-18-238SP, June 2018, p. 9.
29 For additional discussion, see, for example, Roxana Tiron, “Shipyards Locked in ‘Existential’ Duel for Navy’s New
Frigate,” Bloomberg, February 20, 2019; Paul McLeary, “Saudis Save Wisconsin Shipbuilder: Fills Gap Between LCS
& Frigates At Marinette,” Breaking Defense, January 17, 2019.
Congressional Research Service
14
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
function as feeder yards supporting the production of larger Navy ships that undergo final
assembly at other shipyards. This option might help maintain workloads and employment levels
at one or both of the LCS yards, and might alleviate capacity constraints at other shipyards,
permitting certain parts of the Navy’s 355-ship force-level objective to be achieved sooner. The
concept of feeder yards in naval shipbuilding was examined at length in a 2011 RAND report.30
Number of FFG(X) Builders
Another issue for Congress whether to build FFG(X)s at a single shipyard, as the Navy’s baseline
plan calls for, or at two or three shipyards. As mentioned earlier, one possible alternative to the
Navy’s current baseline plan for building FFG(X)s at a single shipyard would be to build them at
two or three yards, including potentially one or both of the LCS shipyards. The Navy’s FFG-7
class frigates, which were procured at annual rates of as high as eight ships per year, were built at
three shipyards.31 Supporters of building FFG(X)s at two or three yards might argue that it could
boost FFG(X) production from the currently planned two ships per year to four
or more ships per year, substantially accelerating the date for attaining the Navy’s
small surface combatant force-level goal;
permit the Navy to use competition (either competition for quantity at the margin,
or competition for profit [i.e., Profit Related to Offers, or PRO, bidding])32 to
30
Laurence Smallman et al., Shared Modular Build of Warships, How a Shared Build Can Support Future
Shipbuilding, RAND, Santa Monica, CA, 2011 (report TR-852), 81 pp. The Navy in recent years has made some use of
the concept:
All Virginia-class attack submarines have been produced jointly by General Dynamics’ Electric Boat division
(GD/EB) and Huntington Ingalls Industries’ Newport News Shipbuilding (HII/NNS), with each yard in effect
acting as a feeder yard for Virginia-class boats that undergo final assembly at the other yard.
Certain components of the Navy’s three Zumwalt (DDG-1000) class destroyers were produced by HII’s
Ingalls Shipyard (HII/Ingalls) and then transported to GD’s Bath Iron Works (GD/BIW), the primary builder
and final assembly yard for the ships.
San Antonio (LPD-17) class amphibious ships were built at the Ingalls shipyard at Pascagoula, MS, and the
Avondale shipyard near New Orleans, LA. These shipyards were owned by Northrop and later by HII. To
alleviate capacity constraints at Ingalls and Avondale caused by damage from Hurricane Katrina in 2005,
Northrop subcontracted the construction of portions of LPDs 20 through 24 (i.e., the fourth through eighth
ships in the class) to other shipyards on the Gulf Coast and East Coast, including shipyards not owned by
Northrop.
For more on the Virginia-class joint production arrangement, see CRS Report RL32418, Navy Virginia (SSN-774)
Class Attack Submarine Procurement: Background and Issues for Congress, by Ronald O'Rourke. Regarding the LPD17 program, see Laurence Smallman et al., Shared Modular Build of Warships, How a Shared Build Can Support
Future Shipbuilding, RAND, Santa Monica, CA, 2011 (report TR-852), pp. 45-48. See also David Paganie, “Signal
International positions to capture the Gulf,” Offshore, June 1, 2006; Peter Frost, “Labor Market, Schedule Forces
Outsourcing of Work,” Newport News Daily Press, April 1, 2008; Holbrook Mohr, “Northrop Gets LPD Help From
General Dynamics,” NavyTimes.com, April 1, 2008; and Geoff Fein, “Northrop Grumman Awards Bath Iron Works
Construction Work On LPD-24,” Defense Daily, April 2, 2008.
31 The 51 FFG-7s were procured from FY1973 through FY1984 in annual quantities of 1, 0, 3, 6, 8, 8, 8, 5, 6, 3, 2, and
1. The three FFG-7 builders were GD/BIW, Todd Shipyards/San Pedro, CA, and Todd Shipyards/Seattle, WA. The two
Todd shipyards last built Navy ships in the latter 1980s. (See, for example, U.S. Navy, Report to Congress on the
Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year 2020, March 2019, p. 16.) Todd/San Pedro
closed at the end of the 1980s. Todd/Seattle was purchased by and now forms part of Vigor Shipyards, a firm with
multiple facilities in the Puget Sound area and in Portland, OR. Vigor’s work for the Navy in recent years has centered
on the overhaul and repair of existing Navy ships, although it also builds ships for other customers.
32 For more on PRO bidding, see Statement of Ronald O’Rourke, Specialist in Naval Affairs, Congressional Research
Service, before the House Armed Services Committee on Case Studies in DOD Acquisition: Finding What Works, June
24, 2014, p. 7.
Congressional Research Service
15
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
help restrain FFG(X) prices and ensure production quality and on-time deliveries;
and
perhaps complicate adversary defense planning by presenting potential
adversaries with multiple FFG(X) designs, each with its own specific operating
characteristics.
Opponents of this plan might argue that it could
weaken the current FFG(X) competition by offering the winner a smaller
prospective number of FFG(X)s and perhaps also essentially guaranteeing the
LCSs yard that they will build some number of FFG(X)s;
substantially increase annual FFG(X) procurement funding requirements so as to
procure four or more FFG(X)s per year rather than two per year, which in a
situation of finite DOD funding could require offsetting reductions in other Navy
or DOD programs; and
reduce production economies of scale in the FFG(X) program by dividing
FFG(X) among two or three designs, and increase downstream Navy FFG(X)
operation and support (O&S) costs by requiring the Navy to maintain two or
three FFG(X) logistics support systems.
Potential Impact on Requirements for Cruisers and Destroyers
Another potential oversight issue for Congress is whether the FFG(X) program has any
implications for required numbers or capabilities of U.S. Navy cruisers and destroyers. The
Navy’s goal to achieve and maintain a force of 104 cruisers and destroyers and 52 small surface
combatants was determined in 2016, and may reflect an earlier plan to procure FFs, rather than
the current plan to procure more-capable FFG(X)s. If so, a question might arise as to whether the
current plan to procure FFG(X)s would permit a reduction in the required number of cruisers and
destroyers, or in the required capabilities of those cruisers and destroyers.
As mentioned earlier, Navy officials have stated that the new Force Structure Assessment (FSA)
being conducted by the Navy may shift the Navy to a new fleet architecture that will include,
among other thing, a larger proportion of small surface combatants—and, by implication, a
smaller proportion of large surface combatants (i.e., cruisers and destroyers). A September 7,
2018, press report stated the following:
Ahead of the Navy's next force-structure assessment [FSA], the service aims to “pull
together something” quicker to help inform the fiscal year 2020 budget request, according
to the Navy's top requirements officer….
[Vice Adm. William Merz, deputy chief of naval operations for warfare systems,] said
Sept. 5 he'll be paying attention to the mix of large and small surface combatants.
“A lot of that will depend on our perception of what is this next frigate really going to look
like,” he said, referring to the future frigate, FFG(X). “How much capability and
modernization are we actually going to be able to do to that ship? That could influence how
much of another kind of ship we need.”33
A January 15, 2019, press report states:
Justin Katz, “Ahead of FSA, Navu Will Send Quicl Look to Congress to Inform FY-20 Budget,” Inside the Navy,
September 7, 2018.
33
Congressional Research Service
16
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
The Navy plans to spend this year taking the first few steps into a markedly different future,
which, if it comes to pass, will upend how the fleet has fought since the Cold War. And it
all starts with something that might seem counterintuitive: It’s looking to get smaller.
“Today, I have a requirement for 104 large surface combatants in the force structure
assessment; [and] I have [a requirement for] 52 small surface combatants,” said Surface
Warfare Director Rear Adm. Ronald Boxall. “That’s a little upside down. Should I push
out here and have more small platforms? I think the future fleet architecture study has
intimated ‘yes,’ and our war gaming shows there is value in that.”34
An April 8, 2019, press report states that Navy discussions about the future surface fleet include
the upcoming construction and fielding of the [FFG(X)] frigate, which [Vice Admiral Bill
Merz, the deputy chief of naval operations for warfare systems] said is surpassing
expectations already in terms of the lethality that industry can put into a small combatant.
“The FSA may actually help us on, how many (destroyers) do we really need to modernize,
because I think the FSA is going to give a lot of credit to the frigate—if I had a crystal ball
and had to predict what the FSA was going to do, it’s going to probably recommend more
small surface combatants, meaning the frigate … and then how much fewer large surface
combatants can we mix?” Merz said.
An issue the Navy has to work through is balancing a need to have enough ships and be
capable enough today, while also making decisions that will help the Navy get out of the
top-heavy surface fleet and into a better balance as soon as is feasible.
“You may see the evolution over time where frigates start replacing destroyers, the Large
Surface Combatant [a future cruiser/destroyer-type ship] starts replacing destroyers, and in
the end, as the destroyers blend away you’re going to get this healthier mix of small and
large surface combatants,” he said—though the new FSA may shed more light on what that
balance will look like and when it could be achieved.35
Legislative Activity for FY2020
Summary of Congressional Action on FY2020 Funding Request
Table 2 summarizes congressional action on the Navy’s FY2020 funding request for the LCS
program.
Table 2. Congressional Action on FY2020 FFG(X) Program Funding Request
Millions of dollars, rounded to nearest tenth.
Authorization
Request
Research and development
Procurement
(Procurement quantity)
HASC
SASC
Appropriation
Conf.
HAC
SAC
Conf.
59.0
1,281.2
(1)
David B. Larter, “US Navy Moves Toward Unleashing Killer Robot Shps on the World’s Oceans,” Defense News,
January 15, 2019.
35 Megan Eckstein, “Navy Sees No Easy Answer to Balance Future Surface Fleet,” USNI News, April 8, 2019. Ellipse
as in original.
34
Congressional Research Service
17
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Source: Table prepared by CRS based on FY2020 Navy budget submission, committee and conference reports,
and explanatory statements on the FY2020 National Defense Authorization Act and the FY2020 DOD
Appropriations Act.
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is
House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference agreement.
Research and development funding is located in PE (Program Element) 0603599N, Frigate Development, which is
line 54 in the FY2020 Navy research and development account.
Congressional Research Service
18
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Appendix. Navy Briefing Slides from July 25, 2017,
FFG(X) Industry Day Event
This appendix reprints some of the briefing slides that the Navy presented at its July 25, 2017,
industry day event on the FFG(X) program, which was held in association with the Request for
Information (RFI) that the Navy issued on July 25, 2017, to solicit information for better
understanding potential trade-offs between cost and capability in the FFG(X) design. The
reprinted slides begin on the next page.
Congressional Research Service
19
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Slides from Navy FFG(X) Industry Day Briefing
Congressional Research Service
20
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Congressional Research Service
21
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Congressional Research Service
22
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Congressional Research Service
23
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Source: Slides from briefing posted on July 28, 2017, at RFI: FFG(X) - US Navy Guided Missile Frigate
Replacement Program, https://www.fbo.gov/index?s=opportunity&mode=form&tab=core&id=
d089cf61f254538605cdec5438955b8e&_cview=0, accessed August 11, 2017.
Author Information
Ronald O'Rourke
Specialist in Naval Affairs
Congressional Research Service
24
Navy Frigate (FFG[X]) Program: Background and Issues for Congress
Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.
Congressional Research Service
R44972 · VERSION 23 · UPDATED
25
better understand cost and capability drivers across design options before a detail design and construction award, as well as inform final specifications that will achieve a best value solution.39
Another potential oversight issue for Congress is whether the FFG(X) program has any implications for required numbers or capabilities of U.S. Navy cruisers and destroyers. The Navy's goal to achieve and maintain a force of 104 cruisers and destroyers and 52 small surface combatants was determined in 2016, and may reflect an earlier plan to procure FFs, rather than the current plan to procure more-capable FFG(X)s. If so, a question might arise as to whether the current plan to procure FFG(X)s would permit a reduction in the required number of cruisers and destroyers, or in the required capabilities of those cruisers and destroyers. A September 7, 2018, press report stated the following:
Ahead of the Navy's next force-structure assessment [FSA], the service aims to "pull together something" quicker to help inform the fiscal year 2020 budget request, according to the Navy's top requirements officer….
[Vice Adm. William Merz, deputy chief of naval operations for warfare systems,] said Sept. 5 he'll be paying attention to the mix of large and small surface combatants.
"A lot of that will depend on our perception of what is this next frigate really going to look like," he said, referring to the future frigate, FFG(X). "How much capability and modernization are we actually going to be able to do to that ship? That could influence how much of another kind of ship we need."40
A January 15, 2019, press report states:
The Navy plans to spend this year taking the first few steps into a markedly different future, which, if it comes to pass, will upend how the fleet has fought since the Cold War. And it all starts with something that might seem counterintuitive: It's looking to get smaller.
"Today, I have a requirement for 104 large surface combatants in the force structure assessment; [and] I have [a requirement for] 52 small surface combatants," said Surface Warfare Director Rear Adm. Ronald Boxall. "That's a little upside down. Should I push out here and have more small platforms? I think the future fleet architecture study has intimated 'yes,' and our war gaming shows there is value in that."41
Table 2 summarizes congressional action on the Navy's FY2019 funding request for the LCS program.
Table 2. Congressional Action on FY2019 FFG(X) Program Funding Request
Millions of dollars, rounded to nearest tenth.
Authorization |
Appropriation |
||||||
Request |
HASC |
SASC |
Conf. |
HAC |
SAC |
Conf. |
|
Research and development |
134.8 |
134.8 |
134.8 |
134.8 |
132.8 |
134.8 |
132.8 |
Procurement |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Source: Table prepared by CRS based on FY2019 Navy budget submission, committee and conference reports, and explanatory statements on the FY2019 National Defense Authorization Act and the FY2019 DOD Appropriations Act.
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference agreement. Research and development funding is located in PE (Program Element) 0603599N, Frigate Development, which is line 57 in the Navy's FY2019 research and development account.
The House Armed Services Committee, in its report (H.Rept. 115-676 of May 15, 2018) on H.R. 5515, recommended the funding levels for the FFG(X) program shown in the HASC column of Table 2.
Section 129 of H.R. 5515 as reported by the committee states the following:
SEC. 129. Frigate class ship program.
(a) Technical data.—
(1) REQUIREMENT.—As part of the solicitation for proposals for the procurement of any frigate class ship, the Secretary of the Navy shall require that an offeror submit a proposal that provides for conveying technical data as part of the proposal for the frigate.
(2) RIGHTS OF THE UNITED STATES.—The Secretary of the Navy shall ensure that the Government's rights in technical data for any frigate class ship are sufficient to allow the Government to—
(A) by not later than the date on which funds are obligated for the last covered frigate, use the technical data to conduct a full and open competition (pursuant to section 2304 of title 10, United States Code) for any subsequent procurement of a frigate class ship; and
(B) transition the frigate class ship combat systems to Government-furnished equipment to achieve open architecture and foster competition to modernize future systems.
(b) Definitions.—In this section:
(1) The term "covered frigate" means each of the first 10 frigate class ships procured after January 1, 2020.
(2) The term "technical data" means a compilation of detailed engineering plans and specifications for the construction of a frigate class ship.42
H.Rept. 115-676 states the following:
Frigate
The committee is aware that the Navy awarded five contracts for conceptual design for its new guided missile frigate program, FFG(X), with multiple shipbuilders currently developing their respective designs to compete for a detail design and construction contract award planned for September 2020. This pursuit represents a significant shift from the Navy's previous plans to award a contract in fiscal year 2018 for a frigate derived from minor modifications to a Littoral Combat Ship (LCS) design. The FFG(X) program intends to leverage the proposed capabilities of the previous frigate plans and expand upon them to create a more lethal and survivable ship to meet the Small Surface Combatant (SSC) requirement.
Toward that end, the committee encourages the Secretary of the Navy to emphasize concepts of risk reduction, commonality with existing platform equipment, and reduced acquisition and life cycle and sustainment costs to provide a best value solution for this critical platform. FFG(X) represents a significant investment, with the Navy's fiscal year 2019 long-range shipbuilding plan estimating over $5.5 billion through fiscal year 2023 for the first 6 frigates, and a total of 20 frigates planned through fiscal year 2030.
Since 2005, the Comptroller General of the United States has reported extensively on the LCS program, the predecessor small surface combatant. Considering the lessons learned during the LCS program, the committee directs the Comptroller General of the United States conduct a review of the FFG(X) program and provide a report to the congressional defense committees by March 1, 2019. The report shall include, at a minimum, analysis on the following:
(1) conceptual design plans and activities to support the advancement of multiple ship designs for a full and open competition in fiscal year 2020;
(2) activities to establish requirements and system specifications, and to develop the program's overall acquisition approach, including cost and schedule estimates, as well as a test strategy; and
(3) plans for the detail design and construction award contract, to include a review of the implications of a potential request by the Navy for a block buy award. (Page 17)
The Senate Armed Services Committee, in its report (S.Rept. 115-262 of June 5, 2018) on S. 2987, recommended the funding levels for the FFG(X) program shown in the SASC column of Table 2.
S.Rept. 115-262 states the following:
Guided missile frigate (FFG(X))
The committee applauds the Navy's decision to procure a guided missile frigate (FFG(X)) with increased lethality, survivability, and endurance to meet the requirement for Small Surface Combatants within the most recent Navy Force Structure Assessment. While maintaining the Navy's "high/low" mix of ships, the FFG(X) program greatly expands upon the capabilities of the Littoral Combat Ship program, returning many of the multi-mission warfighting attributes of Oliver Hazard Perry-class frigates to the fleet and enabling operations in more contested environments.
As the Navy refines FFG(X) concept designs with industry through fiscal year 2019, the committee continues to support a full and open competition with a single source detail design and construction award in fiscal year 2020. The committee also supports the Navy's approach to commonality with existing Navy platforms, such as the Mark-41 Vertical Launch System and Enterprise Air Surveillance Radar, to reduce acquisition and sustainment costs. The committee encourages the Navy not to trade-off warfighting capability for other considerations. (Page 44)
The conference report (H.Rept. 115-874 of July 25, 2018) on H.R. 5515/P.L. 115-232 of August 13, 2018 recommended the funding levels for the FFG(X) program shown in the authorization conference column of Table 2.
Section 128 of H.R. 5515 states the following:
SEC. 128. FRIGATE CLASS SHIP PROGRAM.
(a) IN GENERAL.—As part of the solicitation for proposals for the procurement of any frigate class ship in any of fiscal years 2019, 2020, or 2021, the Secretary of the Navy shall require that offerors submit proposals under which the offeror agrees to convey technical data to the Federal Government in the event the offeror is awarded the frigate construction contract associated with the proposal.
(b) TECHNICAL DATA DEFINED.—In this section, the term ''technical data'' means a compilation of detailed engineering plans and specifications for the construction of a frigate class ship.
Regarding Section 128, H.Rept. 115-874 states the following:
Frigate class ship program (sec. 128)
The House bill contained a provision (sec. 129) that would require, as part of the solicitation for proposals for the procurement of any frigate class ship, that the Secretary of the Navy require offerors to submit proposals that provide for conveying technical data to the government. Additionally, this provision would require the Secretary of the Navy to ensure that the government's technical data rights are sufficient to allow for specified follow-on activities.
The Senate amendment contained no similar provision.
The Senate recedes with an amendment that would remove the requirement for the Secretary of the Navy to ensure that the government's technical data rights are sufficient to allow for specified follow-on activities and clarify the conditions under which technical data shall be provided to the government.
The conferees' intent is to obtain sufficient technical data to ensure the Navy has the option to compete the winning frigate design in the future for production by at least one additional shipbuilder, if the Navy's inventory objective for FFG(X)-class ships merits such expansion. The conferees note that the benefits of two shipbuilders building the same ship design have been demonstrated in both the DDG–51 and CG–47 classes. The conferees do not intend for the winning frigate offeror to provide technical data beyond what is needed for a single-design, multiple-shipbuilder frigate acquisition strategy or otherwise authorized by law. (Page 802)
The House Appropriations Committee, in its report (H.Rept. 115-769 of June 20, 2018) on H.R. 6157, recommended the funding levels for the FFG(X) program shown in the HAC column of Table 2. The recommended reduction of $2.0 million is for "Testing delays." (Page 248)
The Senate Appropriations Committee, in its report (S.Rept. 115-290 of June 28, 2018) on S. 3159, recommended the funding levels for the FFG(X) program shown in the SAC column of Table 2.
In final action, the FY2019 DOD Appropriations Act became Division A of the Department of Defense and Labor, Health and Human Services, and Education Appropriations Act, 2019, and Continuing Appropriations Act, 2019 (H.R. 6157/P.L. 115-245 of September 28, 2018).
The joint explanatory statement for H.R. 6157/P.L. 115-245 specified the funding levels shown in the appropriations conference column of Table 2. The reduction of $2.0 million is for "Testing and engineering delays." (PDF page 276 of 559)
This appendix reprints some of the briefing slides that the Navy presented at its July 25, 2017, industry day event on the FFG(X) program, which was held in association with the RFI that the Navy issued on July 25 to solicit information for better understanding potential trade-offs between cost and capability in the FFG(X) design (see "Unit Procurement Cost"). The reprinted slides begin on the next page.
Slides from Navy FFG(X) Industry Day Briefing
|
Author Contact Information
1. |
See CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress, by Ronald O'Rourke. |
2. |
See CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke; CRS Report R43838, A Shift in the International Security Environment: Potential Implications for Defense—Issues for Congress, by Ronald O'Rourke; and CRS Report R44891, U.S. Role in the World: Background and Issues for Congress, by Ronald O'Rourke and Michael Moodie. |
3. |
See, for example, CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke. |
4. |
For additional discussion of battle force ships, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke. |
5. |
Compared to cruisers and destroyers, frigates can be a more cost-effective way to perform missions that do not require the use of a higher-cost cruiser or destroyer. In the past, the Navy's combined force of higher-capability, higher-cost cruisers and destroyers and lower-capability, lower-cost frigates has been referred to as an example of a so-called high-low force mix. High-low mixes have been used by the Navy and the other military services in recent decades as a means of balancing desires for individual platform capability against desires for platform numbers in a context of varied missions and finite resources. Peacetime missions performed by frigates can include, among other things, engagement with allied and partner navies, maritime security operations (such as anti-piracy operations), and humanitarian assistance and disaster response (HA/DR) operations. Intended wartime operations of frigates include escorting (i.e., protecting) military supply and transport ships and civilian cargo ships that are moving through potentially dangerous waters. In support of intended wartime operations, frigates are designed to conduct anti-air warfare (AAW—aka air defense) operations, anti-surface warfare (ASuW) operations (meaning operations against enemy surface ships and craft), and antisubmarine warfare (ASW) operations. U.S. Navy frigates are designed to operate in larger Navy formations or as solitary ships. Operations as solitary ships can include the peacetime operations mentioned above. |
6. |
The designation FF, with two Fs, means frigate in the same way that the designation DD, with two Ds, means destroyer. FF is sometimes translated less accurately as fast frigate. FFs, however, are not particularly fast by the standards of U.S. Navy combatants—their maximum sustained speed, for example, is generally lower than that of U.S. Navy aircraft carriers, cruisers, and destroyers. In addition, there is no such thing in the U.S. Navy as a slow frigate. |
7. |
Some U.S. Navy surface combatants are equipped with a point-defense AAW system, meaning a short-range AAW system that is designed to protect the ship itself. Other U.S. Navy surface combatants are equipped with an area-defense AAW system, meaning a longer-range AAW system that is designed to protect no only the ship itself, but other ships in the area as well. U.S. Navy surface combatants equipped with an area-defense AAW system are referred to as guided-missile ships and have a "G" in their designation. |
8. |
When the ship's design has been determined, the program's designation might be changed to the FFG-62 program, since FFG-61 was the final ship in the FFG-7 program. It is also possible, however, that the Navy could choose a different designation for the program at that point. Based on Navy decisions involving the Seawolf (SSN-21) class attack submarine and the Zumwalt (DDG-1000) class destroyer, other possibilities might include FFG-1000, FFG-2000, or FFG-2100. (A designation of FFG-21, however, might cause confusion, as FFG-21 was used for Flatley, an FFG-7 class ship.) A designation of FFG-62 would be consistent with traditional Navy practices for ship class designations. |
9. |
Navy information paper dated November 2, 2017, provided to CRS and CBO by Navy Legislative Affairs Office on November 15, 2017. |
10. |
See, for example, David B. Larter, "The US Navy Is Planning for Its New Frigate to Be a Workhorse," Defense News, January 30, 2018. |
11. |
See Sam LaGrone, "NAVSEA: New Navy Frigate Could Cost $950M Per Hull," USNI News, January 9, 2018; Richard Abott, "Navy Confirms New Frigate Nearly $1 Billion Each, 4-6 Concept Awards By Spring," Defense Daily, January 10, 2018: 1; Sydney J. Freedberg Jr., "Navy Says It Can Buy Frigate For Under $800M: Acquisition Reform Testbed," Breaking Defense, January 12, 2018; Lee Hudson, "Navy to Downselect to One Vendor for Future Frigate Competition," Inside the Navy, January 15, 2018; Richard Abott, "Navy Aims For $800 Million Future Frigate Cost, Leveraging Modularity and Commonality," Defense Daily, January 17, 2018: 3. The $800 million figure is the objective cost target; the $950 million figure is threshold cost target. Regarding the $950 million figure, the Navy states that The average follow threshold cost for FFG(X) has been established at $950 million (CY18$). The Navy expects that the full and open competition will provide significant downward cost pressure incentivizing industry to balance cost and capability to provide the Navy with a best value solution. FFG(X) cost estimates will be reevaluated during the Conceptual Design phase to ensure the program stays within the Navy's desired budget while achieving the desired warfighting capabilities. Lead ship unit costs will be validated at the time the Component Cost Position is established in 3rd QTR FY19 prior to the Navy awarding the Detail Design and Construction contract. (Navy information paper dated November 7, 2017, provided by Navy Office of Legislative Affairs to CRS and CBO on November 8, 2017.) The Navy wants the average basic construction cost (BCC) of ships 2 through 20 in the program to be $495 million per ship in constant 2018 dollars. BCC excludes costs for government furnished combat or weapon systems and change orders. (Source: Navy briefing slides for FFG(X) Industry Day, November 17, 2017, slide 11 of 16, entitled "Key Framing Assumptions.") |
12. |
See, for example, Justin Katz, "FFG(X) Follow-On Ships Likely yo Cost Near $800M, Down from $950M Threshold," Inside the Navy, January 21, 2019; Sam LaGrone, "Navy Squeezing Costs Out of GG(X) Program as Requirements Solidify," USNI News, January 22, 2019; David B. Larter, "The US Navy's New, More Lethal Frigate Is Coming into Focus," Defense News, January 28, 2019. |
13. |
|
14. |
RFI: FFG(X) - US Navy Guided Missile Frigate Replacement Program, accessed August 11, 2017, at https://www.fbo.gov/index?s=opportunity&mode=form&tab=core&id=d089cf61f254538605cdec5438955b8e&_cview=0. |
15. |
Email dated September 22, 2017, from Navy Office of Legislative Affairs to CRS and CBO. For additional discussion of the RFI, the industry day event, and the Navy's preliminary concepts for the frigate, see David B. Larter, "Frigate Competition Wide Open: Navy Specs Reveal Major Design Shift," Defense News, July 10, 2017; Sydney J. Freedberg Jr., "Navy Steers Well Away From An LCS Frigate," Breaking Defense, July 10, 2017; David B. Larter, "Exclusive Interview: The Navy's Surface Warfare Director Talks Frigate Requirements," Defense News, July 11, 2017; Megan Eckstein, "Navy Hosts Guided-Missile Frigate Industry Day; Analysts Worried About Early FFG(X) Requirements," USNI News, July 27, 2017; and David B. Larter, "Experts Question the US Navy's Ideas for A New Frigate, Defense News, July 28, 2017. For earlier reports, see Christopher P. Cavas, "US Navy Considers A More Powerful Frigate, Defense News, April 10, 2017; and Sydney J. Freedberg Jr., "Beyond LCS: Navy Looks To Foreign Frigates, National Security Cutter," Breaking Defense, May 11, 2017. |
16. |
For articles about reported potential parent designs for the FFG(X), see, for example, Chuck Hill, "OPC Derived Frigate? Designed for the Royal Navy, Proposed for USN," Chuck Hill's CG [Coast Guard] Blog, September 15, 2017; David B. Larter, "BAE Joins Race for New US Frigate with Its Type 26 Vessel," Defense News, September 14, 2017; "BMT Venator-110 Frigate Scale Model at DSEI 2017," Navy Recognition, September 13, 2017; David B. Larter, "As the Service Looks to Fill Capabilities Gaps, the US Navy Eyes Foreign Designs," Defense News, September 1, 2017; Lee Hudson, "HII May Offer National Security Cutter for Navy Future Frigate Competition," Inside the Navy, August 7, 2017; Sydney J. Freedberg Jr., "Beyond LCS: Navy Looks To Foreign Frigates, National Security Cutter," Breaking Defense, May 11, 2017. |
17. |
For more on the polar security cutter program, including the parent-design approach, see CRS Report RL34391, Coast Guard Polar Security Cutter (Polar Icebreaker) Program: Background and Issues for Congress, by Ronald O'Rourke |
18. |
The Navy's Osprey (MCM-51) class mine warfare ships are an enlarged version of the Italian Lerici-class mine warfare ships. |
19. |
The FRC design is based on a Dutch patrol boat design, the Damen Stan Patrol Boat 4708. |
20. |
See, for example, Lee Hudson, "Navy to Downselect to One Vendor for Future Frigate Competition," Inside the Navy, January 15, 2018. |
21. |
10 U.S.C. 7309 requires that, subject to a presidential waiver for the national security interest, "no vessel to be constructed for any of the armed forces, and no major component of the hull or superstructure of any such vessel, may be constructed in a foreign shipyard." In addition, the paragraph in the annual DOD appropriations act that makes appropriations for the Navy's shipbuilding account (the Shipbuilding and Conversion, Navy account) typically contains these provisos: " ... Provided further, That none of the funds provided under this heading for the construction or conversion of any naval vessel to be constructed in shipyards in the United States shall be expended in foreign facilities for the construction of major components of such vessel: Provided further, That none of the funds provided under this heading shall be used for the construction of any naval vessel in foreign shipyards.... " |
22. |
Source: Transcript of hearing posted at CQ.com. |
23. |
Department of Defense, Contracts, Press Operations, Release No: CR-032-18, February 16, 2018 (i.e., the DOD contracts award page for February 16, 2018). See also Ben Werner, "Navy Exercises Options For Additional Future Frigate Design Work," USNI News, July 31, 2018; Rich Abott, "Navy Awards Mods To FFG(X) Design Contracts," Defense Daily, August 1, 2018; Kris Osborn, "The Navy Is Moving Fast to Build a New Frigate. Here Is What We Know," National Interest, August 1, 2018. |
24. |
Sam LaGrone and Megan Eckstein, "Navy Picks Five Contenders for Next Generation Frigate FFG(X) Program," USNI News, February 16, 2018. See also David B. Larter, "Navy Awards Design Contracts for Future Frigate," Defense News, February 16, 2018; Lee Hudson, "Navy Awards Five Conceptual Design Contracts for Future Frigate Competition," Inside the Navy, February 19, 2018. |
25. |
Source: Presentation by Dr. Reagan Campbell, "FFG(X) Update, National Symposium—Surface Navy Association," January 15, 2019, briefing slides 5 and 7, posted at InsideDefense.com (subscription required), January 22, 2019. |
26. |
For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz. |
27. |
For additional discussion of changes in the international security environment and debate over the U.S. role in the world, see CRS Report R43838, A Shift in the International Security Environment: Potential Implications for Defense—Issues for Congress, by Ronald O'Rourke, and CRS Report R44891, U.S. Role in the World: Background and Issues for Congress, by Ronald O'Rourke and Michael Moodie. |
28. |
Navy information paper on the FFG(X), May 18, 2018, provided to CRS by Navy Office of Legislative Affairs on May 18, 2018. |
29. |
The CG(X) program was canceled in 2010. For more on the CG(X) cruiser program, see CRS Report RL34179, Navy CG(X) Cruiser Program: Background for Congress, by Ronald O'Rourke. This report was archived in January 2011. |
30. |
Megan Eckstein, "New Requirements for DDG-1000 Focus on Surface Strike," USNI News, December, 4, 2017. |
31. |
Richard Abott, "Navy Will Focus Zumwalt On Offensive Surface Strike," Defense Daily, December 5, 2017. |
32. |
See, for example, CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress, by Ronald O'Rourke. |
33. |
For more on China's naval modernization effort, see CRS Report RL33153, China Naval Modernization: Implications for U.S. Navy Capabilities—Background and Issues for Congress, by Ronald O'Rourke. |
34. |
See, for example, See U.S. General Accounting Office, Statement of Jerome H. Stolarow, Director, Procurement and Systems Acquisition Division, before the Subcommittee on Priorities and Economy in Government, Joint Economic Committee on The Navy's FFG-7 Class Frigate Shipbuilding Program, and Other Ship Program Issues, January 3, 1979, pp. 9-11. |
35. |
For more on PRO bidding, see Statement of Ronald O'Rourke, Specialist in Naval Affairs, Congressional Research Service, before the House Armed Services Committee on Case Studies in DOD Acquisition: Finding What Works, June 24, 2014, p. 7. |
36. |
Laurence Smallman, et al., Shared Modular Build of Warships, How a Shared Build Can Support Future Shipbuilding, RAND, Santa Monica, CA, 2011 (report TR-852), 81 pp. |
37. |
For more on the Virginia-class joint production arrangement, see CRS Report RL32418, Navy Virginia (SSN-774) Class Attack Submarine Procurement: Background and Issues for Congress, by Ronald O'Rourke. |
38. |
See Laurence Smallman, et al., Shared Modular Build of Warships, How a Shared Build Can Support Future Shipbuilding, RAND, Santa Monica, CA, 2011 (report TR-852), pp. 43-48. See also David Paganie, "Signal International positions to capture the Gulf," Offshore, June 1, 2006; Peter Frost, "Labor Market, Schedule Forces Outsourcing of Work," Newport News Daily Press, April 1, 2008; Holbrook Mohr, "Northrop Gets LPD Help From General Dynamics," NavyTimes.com, April 1, 2008; and Geoff Fein, "Northrop Grumman Awards Bath Iron Works Construction Work On LPD-24," Defense Daily, April 2, 2008. |
39. |
Government Accountability Office, Weapon Systems Annual Assessment[:] Knowledge Gaps Pose Risks to Sustaining Recent Positive Trends, GAO-18-360SP, p. 115. |
40. |
Justin Katz, "Ahead of FSA, Navu Will Send Quicl Look to Congress to Inform FY-20 Budget," Inside the Navy, September 7, 2018. |
41. |
David B. Larter, "US Navy Moves Toward Unleashing Killer Robot Shps on the World's Oceans," Defense News, January 15, 2019. |
42. |
See also Rich Abott, "House Panel Pushing Navy For Three LCSs And Procuring Frigate technical Data Rights," Defense Daily, April 26, 2018: 3-5; Megan Eckstein, "HASC Subcommittee Marks Recommend Additional Navy Ship Buys, Multi-Year Aircraft Deals," USNI News, April 25, 2018. |