Policymakers have recently been considering several legislative options to help finance water infrastructure projects, including projects to build and upgrade wastewater and drinking water treatment systems. This report examines one particular option, a "Water Infrastructure Finance and Innovation Act" (WIFIA) program, which Congress included in the Water Resources Reform and Development Act of 2014 (WRRDA). As enacted (P.L. 113-121), the legislation created a WIFIA pilot program based on provisions in Senate-passed S. 601, P.L. 113-121).
The WIFIA concept is modeled after a similar program that assists transportation projects, the Transportation Infrastructure Finance and Innovation Act (TIFIA) program. Proponents of the WIFIA approach, including water utility organizations, cite several potential benefits:
On the other hand, opponents of the WIFIA approach, including organizations that represent state environmental agency officials, citehave cited several concerns:
Implementation of WIFIA will not occurwas delayed until Congress appropriatesappropriated funds to cover the subsidy cost of the program, which has not yet happened, but the President's FY2017 budget requested $15 million for the Environmental Protection Agency (EPA) to begin making loans. EPA funding bills (H.R. 5538 and S. 3068) include $45 million and $25 million, respectively, for initial loans. EPAoccurred in the Further Continuing and Security Assistance Appropriations Act, 2017 (P.L. 114-254) in December 2016. Using the $20 million in that act, the Environmental Protection Agency (EPA) expects to issue its first WIFIA loans in FY2017.
Although WIFIA has not yet been implemented, interest2017.
Interest in using itWIFIA as a model for other infrastructure financing programs is apparent. Several legislative proposalsbills in the 114th Congress wouldproposed to establish a WIFIA-type program for water reclamation and reuse projects in western states. These proposals areNone of these proposals, which were included in S. 176/H.R. 291, S. 1837, S. 1894, S. 2533/H.R. 5247, and H.R. 6022, were enacted.
Policymakers have recently been considering several legislative options to help finance water infrastructure projects, including projects to build and upgrade wastewater and drinking water treatment facilities. This report examines one particular option, a "Water Infrastructure Finance and Innovation Act" (WIFIA) program, which was included in the Water Resources Reform and Development Act of 2014 (WRRDA, P.L. 113-121). Title V, Subtitle C, of thethat legislation created a five-year WIFIA pilot program.1
Localities are primarily responsible for providing water infrastructure services. According to the most recent estimates by states and the Environmental Protection Agency (EPA), funding needs for such facilities total $655 billion over a 20-year period.2 While some analysts and stakeholders debate these estimates and whether they understate or overstate capital needs, most agree that communities face formidable challenges in providing adequate and reliable water infrastructure services.
Capital investments in water infrastructure are necessary to maintain high quality service that protects public health and the environment, and capital facilities are a major investment for local governments. Almost all capital projects are debt-financed (i.e., they are not financed on a pay-as-you-go basis from ongoing revenues to the water utility). The principal financing tool that local governments use is issuance of tax-exempt municipal bonds—at least 70% of U.S. water utilities rely on municipal bonds and other debt to some degree to finance capital investments. In 2011, bonds issued for water, sewer, and sanitation projects totaled $29.6 billion, of which $14.2 billion was new-money financing; the remainder was for refunding to refinance prior governmental bonds.3 Beyond municipal bonds, federal assistance through grants and loans is available for some projects but is insufficient to meet all needs. Finally, public-private partnerships, or P3s, which are long-term contractual arrangements between a public utility and a private company, currently provide only limited capital financing in the water sector. While they are increasingly used in transportation and some other infrastructure sectors, especially P3s that involve private sector debt or equity investment in a project, most P3s for water infrastructure involve contract operations for operation and maintenance.
The WIFIA approach for supporting investment in water infrastructure is modeled after an existing Transportation Infrastructure Finance and Innovation Act (TIFIA) program. As the name suggests, only transportation projects are eligible for TIFIA assistance, but operation of the TIFIA program generated interest in creating a similar program for water infrastructure.4
TIFIA was enacted in 1998 as part of the Transportation Equity Act for the 21st Century (TEA-21; P.L. 105-178) and was reauthorized in July 2012 in the Moving Ahead for Progress in the 21st Century Act (MAP-21; P.L. 112-141). TIFIA provides federal credit assistance up to a maximum of 49% of project costs in the form of secured loans, loan guarantees, and lines of credit (23 U.S.C. 601 et seq.). Transportation projects costing at least $50 million (or at least $25 million in rural areas) are eligible for TIFIA financing.5 Projects must also have a dedicated revenue stream to be eligible for credit assistance. TIFIA can provide senior or subordinated debt. With the enactment of MAP-21, funding authorized for the TIFIA program increased from $122 million annually to $750 million in FY2013 and $1 billion in FY2014 and FY2015. However, the Fixing America's Surface Transportation Act (FAST Act, P.L. 114-94), enacted in December 2015, reduced the amount available to support TIFIA loans and other credit assistance under the TIFIA program. Under the FAST Act, the annual amount is $275 million in each of FY2016 and FY2017, $285 million in FY2018, and $300 million in each of FY2019 and FY2020.
Prior to the enactment of MAP-21, a project seeking TIFIA assistance had to satisfy a number of eligibility criteria, such as project cost and planning requirements. Projects were then selected by the Department of Transportation (DOT) from among those eligible based on eight weighted factors: private participation (20%), environmental impact (20%), national or regional significance (20%), project acceleration (12.5%), creditworthiness (12.5%), environmental impact, national or regional significance, project acceleration, creditworthiness, use of new technologies (5%), reduced federal grant assistance (5%), and consumption of budget authority (5%). MAP-21 eliminated these selection criteria, and TIFIA now provides assistance based purely on a project's eligibility. One of the key eligibility criteria is the creditworthiness of the project. To be eligible, a project's senior debt obligations and the federal credit instrument must receive an investment-grade rating from at least one nationally recognized credit agency. The TIFIA assistance must also be determined to have several beneficial effects: fostering a public-private partnership (if appropriate), enabling the project to proceed more quickly, and reducing the contribution of federal grant funding. Other eligibility criteria include satisfying planning and environmental review requirements and being ready to contract out construction within 90 days after the obligation of assistance.
Since TIFIA's beginning in 1998, it has provided assistance to 5865 projects, mostly in the form of direct loans. Loan amounts have ranged from $4042 million to $1.9 billion. Total credit assistance provided over the life of the program amounted to $22.825.7 billion as of FebruaryDecember 2016. The amount of credit assistance is much larger than the appropriated amount over this period because the appropriated funds need only cover the administrative and subsidy cost of the program. (See below for a more detailed discussion of this point.) Projects involving TIFIA amount to $8392.5 billion in total project costs.6 TIFIA typically provides financing to fill a gap in a much larger financial package that sometimes involves private equity and private debt. For example, the $2.6 billion IH-635 Managed Lanes project in Dallas, TX, is being financed with $615 million in private activity tax-exempt bonds, a $664 million equity contribution from the private sector partner, $17 million in toll revenues, $490 million in public funds, and an $850 million TIFIA loan.7
In the 113th Congress, a WIFIA pilot program was included as part of the Water Resources Reform and Development Act of 2014 (WRRDA).8 Title X of Senate-passed S. 601 included a WIFIA pilot program, while House-passed H.R. 3080 included no similar provisions. The President signed the bill into law on June 10, 2014 (P.L. 113-121). The legislation authorized a five-year WIFIA pilot program. EPA is authorized to provide credit assistance (secured/direct loans or loan guarantees) for a range of drinking water and wastewater projects, and the U.S. Army Corps of Engineers (the Corps) is authorized to provide similar assistance for water resource projects, such as flood control or hurricane and storm damage reduction.
Under the legislation as enacted, EPA and the Corps are each authorized a total of $175 million over five years (beginning with $20 million for each agency in FY2015 and increasing to $50 million in FY2019) to provide assistance. Projects are required to be $20 million or larger in costs to be eligible for credit assistance, except that projects in rural areas (population 25,000 or less) must have eligible project costs of $5 million or more. WIFIA credit assistance is to be available to project sponsors (a corporation; partnership; joint venture; trust; or a federal, state, local, or tribal government) or to state infrastructure financing authorities for a group of projects. In the case of projects carried out by private entities, such projects are to be publicly sponsored. To meet this requirement, the legislation allows a project applicant to demonstrate to the Corps or EPA that the affected state, local, or tribal government supports the project. To ensure that ownership of the water project does not become private (which would limit availability of some other sources of federal financing), the maximum amount of a loan is to be 49% of eligible project costs, but the legislation authorizes EPA or the Corps to make available up to 25% of available funds each year for credit assistance in excess of 49% of project costs. Except for certain projects in rural areas, the total amount of federal assistance (i.e., WIFIA and other sources) shallmay not exceed 80% of a project's cost.
Activities eligible for assistance under the WIFIA pilot program include project development and planning, construction, acquisition of real property, and carrying costs during construction. Categories eligible for assistance by the Corps would include flood control or hurricane and storm damage reduction projects, environmental restoration, coastal or inland harbor navigation improvement, or inland and intracoastal waterways navigation improvement. Categories eligible for assistance by EPA include projects at wastewater treatment and community drinking water facilities, projects for enhanced energy efficiency of a public water system or wastewater treatment works, repair or rehabilitation of aging wastewater and drinking water systems, desalination or water recycling projects, or a combination of eligible projects. The Secretary of the Army or EPA administrator, as appropriate, is to determine eligibility based on a project's creditworthiness and dedicated revenue sources for repayment. Selection criteria include the national or regional significance of the project, extent of public or private financing in addition to WIFIA assistance, use of new or innovative approaches, the amount of budget authority required to fund the WIFIA assistance, the extent to which a project serves regions with significant energy development or production areas, and the extent to which a project serves regions with significant water resources challenges.
Responding to concerns from some groups that WIFIA could impair and diminish support for clean water and drinking water State Revolving Fund (SRF) programs under the Clean Water Act and Safe Drinking Water Act (see discussion below), the legislation included language requiring the EPA administrator, when the agency receives applications for WIFIA assistance, to give state infrastructure financing authorities a "right of first refusal" to assist the project through SRF monies.
WIFIA-assisted projects must use American-made iron and steel products ("Buy America" provisions), and wastewater treatment works projects must comply with the prevailing wage requirements of the Davis-Bacon Act in the same manner that they would under the SRF provisions of the Clean Water Act.
P.L. 113-121 requiredrequires EPA and the Corps to provide information on a website concerning applications and projects that have received assistance, and it directed the Government Accountability Office to report to Congress on the pilot programs in four years, along with recommendations for continuing, changing, or terminating the WIFIA program. As discussed below, EPA held listening sessions in several U.S. cities, seeking public input about procedures for evaluating WIFIA applications and selection criteria in anticipation of making loans.
From the federal perspective, an advantage of TIFIA is that it can provide a large amount of credit assistance relative to the amount of budget authority provided. The volume of loans and other types of credit assistance that TIFIA can provide is determined by the size of congressional appropriations and calculation of the subsidy cost.9 The subsidy cost largely determines the amount of money that can be made available to project sponsors.10 For example, in 2012, DOT estimated that after administrative costs and other deductions, it would have $690 million for credit subsidy support in FY2013 and $920 million in FY2014.11 Assuming an average subsidy cost of 10%, this could provide DOT with the capacity to lend $6.9 billion in FY2013 and $9.2 billion in FY2014. If the subsidy cost for water projects averages 10% and is the only charge against available budget authority, a $20 million budgetary allocation theoretically supports $200 million in loans. In federal budgetary terms, WIFIA (or TIFIA) assistance has much less of an impact than a water infrastructure grant, which is not repaid to the U.S. Treasury.
Proponents of WIFIA have argued that loans for water projects could be even less risky than transportation projects, because water rates are an established repayment mechanism; thus the subsidy cost would be lower and the amount of credit assistance higher (per dollar of budget authority).12 HoweverThe Office of Management and Budget will establish a subsidy rate for the entire WIFIA program, but individual subsidy rates also will be determined for each project that is approved to receive credit assistance. EPA, in developing a credit subsidy model for implementing WIFIA, estimated that a $20 million appropriation, with $15 million used for credit reserve, would allow EPA to make up to $1 billion in loans.13 Adding caution, however, analysts note that, even with stable rate mechanisms, some communities and water utilities have recently experienced problems with borrowing and bond repayments, so repayment of a WIFIA loan is not a certainty.13
One of the main benefits of the TIFIA program is that it provides capital at a low cost to the borrower, because even though the interest on 30-year Treasury securities is taxable, Treasury rates can be less expensive than rates on traditional tax-exempt municipal debt. Moreover, TIFIA financing is often characterized as patient capital, because loan repayment does not need to begin until five years after substantial completion of a project, the loan can be for up to 35 years from substantial completion, and the amortization schedule can be flexible. In addition, there is less perceived investment risk, because the project has been determined to be creditworthy (i.e., there is a revenue stream for repayment). The WIFIA legislation was likewise intended to provide these benefits. As total TIFIA assistance cannot exceed 49% of project costs, it is intended to encourage nonfederal and private sector financing. P.L. 113-121, with a similar 49% cap on WIFIA assistance (and limits on all sources of federal assistance to no more than 80% of a project's cost), would likely encourage some nonfederal financing, including from the private sector, but how much is unclear.
AnotherIt has also been argued that another possible benefit of the WIFIA program is that it is intended to not duplicate existing water infrastructure financing tools. Many arguehave argued that the principal federal programs that assist local wastewater and drinking projects—SRF programs under the Clean Water Act and Safe Drinking Water Act—are useful primarily for smaller communities and smaller projects. This might argue for expanding the SRF program while keeping WIFIA solely for larger projects. Arguably, then, the $20 million minimum threshold for credit assistance contained in the new lawunder WIFIA could be about the right level so as not to duplicate assistance from SRFs.1415 The legislation, however, also provided access to WIFIA financing for smaller projects by grouping, or aggregating, them through an SRF to meet the $20 million threshold, and it set a lower threshold ($5 million) for projects in rural areas. One possible downside of providing smaller projects access to WIFIA financing, grouped or not, is the time and expense of administering the program.
A major source of debate among opponents and proponents has been and continues to be potential adverse impacts of WIFIA on funds for the Clean Water Act and Safe Drinking Water Act SRF programs. Several groups representing state environmental officials opposed the WIFIA provisions of the 113th Congress legislation because, they said, it could result in reduced spending on the SRF programs, which are capitalized by federal appropriations. States are concerned that WIFIA would likely be funded (through congressional appropriations) to the detriment of the SRF programs.1516 On the other hand, water utility groups that support WIFIA arguehave argued that it would complement, not harm, existing SRF programs. In their view, WIFIA will provide a new funding opportunity for large water infrastructure projects that are unlikely to receive SRF assistance.1617 As described above, in part to address concerns about impacts of WIFIA on the SRF programs, the enacted legislation gave state infrastructure financing authorities a "right of first refusal" to provide SRF funds for a project when EPA receives an application for WIFIA assistance. Nevertheless, some states and environmental advocacy groups remain concerned that WIFIA will compete with SRFs for congressional funding and that WIFIA will not prioritize public health or affordability, as the SRFs can.
The WIFIA program may shift some decisionmaking for financing water infrastructure projects from the state and local level to the federal level, specifically to the EPA or the Army Corps, a change that concernsraised concerns with some stakeholders. Indeed, in a letter to the conferee managers, the Obama Administration expressed concerns with the WIFIA proposal in S. 601 during Senate consideration of that bill, "which asserting that it "would expand the Environmental Protection Agency's and the Corps' role in local water infrastructure projects and not provide Federal assistance in the most efficient manner."1718
Another perceived benefit of the TIFIA program from the federal perspective is that it potentially limits the federal government's exposure to default by relying on market discipline through creditworthiness standards and encouraging private capital investment. WIFIA supporters see the same benefit from the WIFIA program. On the other hand, the Congressional Budget Office (CBO) argueshas argued that the federal government underestimates the cost of providing credit assistance under programs such as TIFIA.1819 This is because it excludes
the cost of market risk—the compensation that investors require for the uncertainty of expected but risky cash flows. The reason is that the [Federal Credit Reform Act] requires analysts to calculate present values by discounting expected cash flows at the interest rate on risk-free Treasury securities (the rate at which the government borrows money). In contrast, private financial institutions use risk-adjusted discount rates to calculate present values.19
Enacting the WIFIA program raised another federal budgetary and revenue issue. Legislation reported by congressional committees is typically scored by the CBO for the effects on discretionary and mandatory, or direct, spending and by the Joint Committee on Taxation (JCT) for effects on revenue. The initial CBO cost estimate for S. 601, as approved by the Environment and Public Works Committee in April 2013, concluded that the WIFIA provisions would cost $260 million over five years. In addition, it would result in certain revenue loss to the U.S. Treasury; thus, pay-as-you-go procedures would apply to the bill.2021 CBO cited the JCT estimate that enactment of the bill would reduce revenues by $135 million over 10 years, because states would be expected to issue tax-exempt bonds for water projects in order to acquire additional funds not covered by WIFIA assistance.2122 To avoid the pay-as-you-go problem in the bill, the committee added a provision to S. 601 to prohibit recipients of WIFIA assistance from issuing tax-exempt bonds for the non-WIFIA portions of project costs. CBO re-estimated the bill and concluded that, because the change would make the WIFIA program less attractive to entities, most of which rely on tax-exempt bonds for project financing, the cost of the bill would be $200 million less over five years. CBO also said that the bill would have no impact on revenues, because the demand for federal credit would be lower without the option of using tax-exempt financing.2223 P.L. 113-121 retained the bar on tax-exempt financing for WIFIA-assisted projects. Thus, the apparent solution to one problem in the legislation—potential revenue loss to the U.S. Treasury—raised a different kind of problem for entities seeking WIFIA credit assistance, because tax-exempt municipal bonds are the principal mechanism used by local governments to finance water infrastructure projects.
The restriction was widely criticized by potential users of WIFIA assistance. In their view, the bond financing restriction in WRRDA, together with the provision that caps WIFIA assistance at 49% of project costs, would make it very difficult to finance needed projects. Congressional interest in addressing the tax-exempt bond restriction has beenwas soon evident. For example, H.R. 1710 in the 114th Congress wouldproposed to make an exception from the limitation on use of tax-exempt bonds for WIFIA loans made to finance water infrastructure projects in states in which the governor has issued a state of drought emergency declaration.
More generally, in July 2015, the Senate passed H.R. 22, a bill to reauthorize highway and transportation programs for six years. It included repeal of the provision in P.L. 113-121 that limits any project receiving federal credit assistance under the WIFIA program from being financed with tax-exempt bonds. However, repeal of the provision raised similar revenue questions to those that arose in connection with P.L. 113-121. CBO's report on S. 1647 (the Senate Environment and Public Works Committee's bill, which was the basis of Senate-passed H.R. 22)2324 stated that the Joint Committee on Taxation (JCT) estimated that repealing the WIFIA limitation would increase states' issuance of tax-exempt bonds for water projects and would decrease federal revenues by $17 million over the FY2016-FY2025 period. Further, CBO estimated that the change would increase demand for federal credit under the WIFIA program, resulting in additional spending stemming from the appropriation levels authorized in P.L. 113-121. Consequently, CBO estimated that implementing the WIFIA program would cost $146 million over the FY2016-FY2025 period.
The problem of identifying offsets, or "pay-fors," for the estimated federal revenue loss was apparently solved in the conference agreement on H.R. 22, the FAST Act (P.L. 114-94). CBO estimated that the conference agreement includesincluded offsets to fully cover the cost of the bill by reducing spending or raising revenues.2425 Thus, the conference report retained the provision from Senate-passed H.R. 22 repealing the tax-exempt bond financing restriction on WIFIA assistance.
EPA has beenbegan preparing for implementation of the WIFIA program, including through a series of public listening sessions in several U.S. cities in 2014. The intended audience was municipal, state, and regional water utility officials, private sector financing professionals, and other interested organizations and parties. The purpose was to discuss project ideas, potential selection and evaluation criteria, and numerous other implementation issues.25 Funding uncertainty iswas one of several implementation challenges that have already beenwas quickly identified. Another earlierinitial concern over the law's provision that barred cities from supplementing WIFIA funds with money from tax-exempt municipal bonds was addressed in the FAST Act, as described above. Nevertheless, some observers believe that while WIFIA financing may be helpful in limited instances, tax-exempt bonds will continue to be the principal financing tool used by municipalities for water infrastructure projects, along with low-interest SRF loans, where available.
Early in 2016 EPA officials began work on two rules Although the two rules are intended to clarify many aspects of EPA's implementation of WIFIA, other implementation challenges presented by provisions of the law itself—such as the 49% cap—would need to be resolved in new legislation. Implementation of WIFIA—i.e., making project loans—was delayed for more than two years but can now occur following enactment of the Further Continuing and Security Assistance Appropriations Act, 2017 (P.L. 114-254) in December 2016, providing the first appropriation of funds to cover the subsidy cost of the program. Twice before that measure, in FY2015 and FY2016, Congress had provided small amounts of funding to EPA ($2.2 million) for hiring and staffing to implement the new program. P.L. 114-254 appropriates $20 million to EPA to begin making loans and allows the agency to use up to $3 million of the total for administrative purposes. Under the legislation, these funds are available to subsidize not to exceed $2.1 billion in WIFIA assistance. EPA now expects to make the first WIFIA loans in 2017. Congress has not yet appropriated funds that would allow the Army Corps to begin preparations or begin making WIFIA loans under the authority in the 2014 statute. As authorized in WRRDA, WIFIA is a pilot program that is scheduled to expire after FY2019. Several bills in the 114th Congress included provisions that would eliminate the "pilot" designation of the program and make it permanent. The Senate passed one such bill, S. 2848, in 2016. S. 2848 also would have made several limited changes to WIFIA. It would have added eligibility for certain types of desalination or water recycling projects that the Corps could assist and drought mitigation or resilience projects that EPA could assist. It would have allowed communities to pay loan fees from the loan itself, and allowed in-kind contributions and project costs incurred before receiving a loan to count towards the nonfederal share of project costs. Further, S. 2848 included "sense of the Senate" language that appropriations to support WIFIA should supplement not replace SRF funding under the CWA and Safe Drinking Water Act. In December 2016, Congress enacted the Water Infrastructure Improvements for the Nation (WIIN) Act (P.L. 114-322); it included many of the provisions of Senate-passed S. 2848, but the only WIFIA-related provision from that bill that was carried forward into WIIN is the "sense of the Senate" language about appropriations.that willintended to explain and clarify some provisions of the program and establish guidelines for the application process. Both rules were issued in mid-December. One is an interim final rule that sets guidelines for the application and selection of projects, defines the requirements for credit assistance, and defines reporting requirements and the fee collection structure.26 In this rule, EPA said that it initially will give funding priority to four types of projects: adaptation to extreme weather and climate change; enhanced energy efficiency of wastewater treatment works and public water systems; green infrastructure; and repair, rehabilitation, and replacement of infrastructure and conveyance systems. The second is a proposed rule that addresses the fee structure for WIFIA (application fee, credit processing fee, and servicing fee).27 It states EPA's intention to require a non-refundable fee for each project that is invited to submit a full WIFIA application. The proposed application fee is $100,000, or $25,000 for projects serving small communities. The fee would not be required in connection with submission of letters of interest, but would be required for projects that EPA expects might reasonably proceed to closing.
explain and clarify some provisions of the program and establish guidelines for the application process. EPA anticipates that the rules will address a number of questions that have been raised, such as defining eligible projects, determining selection criteria, developing a ranking system, and determining project creditworthiness. Implementation challenges presented by provisions of the law itself—such as the 49% cap—would need to be resolved in new legislation.
In May 2016 EPA published a Federal Register notice asking for public comment on the types of information that it plans to require from applicants for WIFIA credit assistance.26 EPA was seeking to evaluate several issues: whether the proposed collection of information from applicants is necessary, the accuracy of the agency's estimate of the burden of the information collection, and how to minimize the information burden. The notice was accompanied by a draft "letter of interest" that EPA plans to require from applicants, describing project details and its financial plan, as well as how the project will meet selection criteria of the program.
In mid-August, EPA sent two draft WIFIA rules to the Office of Management and Budget for review. One is an interim final rule that would set guidelines for the application and selection of projects, define the requirements for credit assistance, and define reporting requirements and the fee collection structure.27 The second draft rule, building on information gathered in response to the May 2016 Federal Register notice, addresses the fee structure for WIFIA. In that May notice, EPA said that it was proposing a $100,000 application fee for WIFIA loans. In response, water utility organizations and others told EPA that such a proposed application fee would be prohibitively expensive for municipalities, especially without modification such as refunding the fee for unsuccessful applications or rolling the fee into the loan itself.
The agency's goal is to be ready for making the first loans in FY2017.
Implementation of WIFIA—i.e., making project loans—will not occur until Congress appropriates funds to cover the subsidy cost of the program, which has not yet happened. In the Consolidated and Further Continuing Appropriations Act, 2015 (P.L. 113-235), Congress provided EPA with $2.2 million for hiring and staffing to implement the new program. Similarly, in the Consolidated Appropriations Act, 2016 (P.L. 114-113), Congress again appropriated $2.2 million to EPA to continue preparing for the WIFIA program. Neither bill provided start-up funds for the Corps, and neither act appropriated funds to actually make loans or finance projects.
The President's FY2017 budget, announced on February 9, 2016, sought $15 million for EPA to begin making WIFIA loans. The budget estimated that this level of budget authority will support $980 million in direct loan activity in 2017. The budget also requested $5 million for related EPA administrative costs. FY2017 appropriations bills for EPA endorse the President's request to allow EPA to being making loans. H.R. 5538, passed by the House on July 14, includes $45 million for loans and $5 million for EPA's administrative expenses, while S. 3068, reported by the Senate Appropriations Committee in June, includes $25 million for loans and $5 million for EPA's administrative expenses.
The President's budget did not include a similar request that would allow the Army Corps to begin making WIFIA loans, nor have the House and Senate Appropriations Committees included WIFIA funding in FY2017 funding bills for the Corps (H.R. 5055 and S. 2804), putting Corps implementation considerably behind EPA's.
As authorized in WRRDA, WIFIA is a pilot program that is scheduled to expire after FY2019. To the extent that appropriations for making loans are not provided, the window of time for testing and evaluating the program will be limited. Supporters could then find it difficult to argue for extending or making the program permanent. However, bills in the 114th Congress include provisions that would eliminate the "pilot" designation of the program and make it permanent even before operations have begun (S. 2821 and S. 2848, which the Senate passed on September 15, 2016,28 include such provisions).
Although the WIFIA program has not yet been implemented, interest in using it as a model for other infrastructure financing programs is apparent. For example, several legislative proposals in the 114th Congress would establish a WIFIA-type program for water reclamation and reuse projects in western states. These proposals, sometimes referred to as "Reclamation for WIFIA," or RIFIA, are included in S. 176/H.R. 291 (the Water in the 21st Century Act), S. 1837 (Drought Recovery and Resiliency Act), S. 1894 (the California Emergency Drought Relief Act of 2015), S. 2533/H.R. 5247 (California Long-Term Provisions for Water Supply and Short-Term Provisions for Emergency Drought Relief Act), and H.R. 6022 (the New WATER Act).
Most stakeholders in the debate about water infrastructure financing acknowledge that there is no single solution or alternative that will fit all needs for all communities and all types of projects. Most also recognize that financing is not new revenue. Investment via a particular financing tool, such as WIFIA, could simply displace existing mechanisms rather than increase total investment in water infrastructure. Whatever the source of funds for a project, communities and other sponsors must still identify a stream of revenue to repay whatever debt is incurred for a given investment. One of the challenges going forward is to ensure that financing is available for all needed projects.
Author Contact Information
1. |
WIFIA is one of several legislative approaches to help finance water infrastructure that have been proposed. For discussion of WIFIA and several other options, see CRS Report R42467, Legislative Options for Financing Water Infrastructure, by [author name scrubbed], [author name scrubbed], and [author name scrubbed]. |
|
2. |
EPA's most recent estimate of capital needs for wastewater infrastructure was published in 2016. See EPA, Clean Watersheds Needs Survey 2012, Report to Congress, EPA-830-R-15005, January 2016. The most recent EPA needs estimate for drinking water infrastructure was issued in 2013. See EPA, Drinking Water Infrastructure Needs Survey and Assessment, EPA-816-R-13-006, April 2013. |
|
3. |
Thomson-Reuters, The Bond Buyer 2012 Yearbook, p. 159. |
|
4. |
For example, see American Water Works Association, Water Environment Federation, and Association of Metropolitan Water Agencies, "A Cost Effective Approach to Increasing Investment in Water Infrastructure, The Water Infrastructure Financing Innovations Authority (WIFIA)," http://www.awwa.org/portals/0/files/legreg/documents/wifia.pdf. |
|
5. |
The threshold for Intelligent Transportation Systems projects is $15 million. |
|
6. |
Federal Highway Administration, "Projects Financed by TIFIA," http://www.transportation.gov/tifia/projects-financed. |
|
7. |
Federal Highway Administration, "IH 635 Managed Lanes," http://www.transportation.gov/tifia/financed-projects/ih-635-managed-lanes. |
|
8. |
A standalone measure to create a WIFIA program also was introduced in the 113th Congress. S. 335 proposed to empower the EPA Administrator to provide credit assistance to drinking water and wastewater infrastructure projects. It was not a pilot program, as in P.L. 113-121. |
|
9. |
According to the Federal Credit Reform Act of 1990, the subsidy cost is the "estimated long-term cost to the Government of a direct loan or loan guarantee, calculated on a net present value basis, excluding administrative costs" (104 Stat. 1388-610). The Federal Credit Reform Act of 1990 was enacted as part of the Omnibus Budget Reconciliation Act of 1990 (P.L. 101-508). |
|
10. |
Douglas J. Elliott, Budgeting for Credit Programs: A Primer, Center for Federal Financial Institutions, April 2004, http://www.coffi.org/pubs/Budgeting%20Primer.pdf. |
|
11. |
U.S. Department of Transportation, "Letters of Interest for Credit Assistance Under the Transportation Infrastructure Finance and Innovation Act (TIFIA) Program," 77 Federal Register 45411-45415, July 31, 2012, http://www.fhwa.dot.gov/ipd/pdfs/tifia/fy2013_tifia_nofa_073112.pdf. |
|
12. |
Testimony of Aurel Arndt, in U.S. Congress, House Committee on Transportation and Infrastructure, Subcommittee on Water Resources and Environment, hearing on Innovative Funding of Water Infrastructure of the United States, 112th Cong., 2nd sess., February 28, 2012, http://republicans.transportation.house.gov/Media/file/TestimonyWater/2012-02-28-Arndt.pdf. Hereinafter, Testimony of Aurel Andt. |
|
13. |
U.S. Congress, House Committee on Appropriations, Subcommittee on Interior, Environment, and Related Agencies, Budget Hearing: Environmental Protection Agency, Questions for the Record—Administrator of the Environmental Protection Agency, 114th Cong., 2nd sess., March 22, 2016.
|
|
Testimony of Aurel Arndt. |
||
Letter from Association of Clean Water Administrators, Association of State Drinking Water Administrators, Environmental Council of the States et al. to Honorable Bill Shuster, Chairman, Committee on Transportation and Infrastructure, and Honorable Nick J. Rahall II, ranking Member, Committee on Transportation and Infrastructure, October 24, 2013. |
||
Letter from American Water Works Association, Association of Metropolitan Water Agencies, and Water Environment Federation to Honorable Barbara Boxer, Chairman, Committee on Environment and Public Works, September 9, 2013. |
||
Letter from Jo-Ellen Darcy, Assistant Secretary of the Army, Civil Works, to Senator Barbara Boxer, Senator David Vitter, Representative Bill Shuster, and Representative Nick J. Rahall II, December 11, 2013. |
||
For more on this topic generally, see Congressional Budget Office, Fair-Value Accounting for Federal Credit Programs, March 2012, http://www.cbo.gov/sites/default/files/cbofiles/attachments/03-05-FairValue_Brief.pdf. |
||
Congressional Budget Office (CBO), "Estimating the Value of Subsidies for Federal Loans and Loan Guarantees," August 2004, p. 2, http://www.cbo.gov/ftpdocs/57xx/doc5751/08-19-CreditSubsidies.pdf. |
||
"Pay-as-you-go," or PAYGO, is a budget rule requiring that, relative to current law, any tax cuts or entitlement and other mandatory spending increases must be paid for by a tax increase or a cut in mandatory spending. See CRS Report RL31943, Budget Enforcement Procedures: The Senate Pay-As-You-Go (PAYGO) Rule, by [author name scrubbed] |
||
CBO, Cost Estimate for S. 601, Water Resources Development Act of 2013, April 9, 2013, p. 6. |
||
CBO, Cost Estimate for S. 601, Water Resources Development Act of 2013, April 17, 2013, p. 7. |
||
U.S. Congress, Senate Committee on Environment and Public Works, Developing A Reliable and Innovative Vision for the Economy (DRIVE) Act, Report to accompany S. 1647, 114th Cong., 1st sess., July 15, 2015, S.Rept. 114-80 (Washington: GPO, 2015), pp. 27-33. |
||
Letter from Keith Hall, Director, CBO, to Honorable Bill Shuster, Chairman, and Peter DeFazio, |
||
25. |
Material from an EPA presentation on WIFIA is available on EPA's website: http://www.epa.gov/sites/production/files/2015-09/documents/wifia-04-01-15-webcast-2.pdf. |
|
26. |
U.S. Environmental Protection Agency, "Proposed Information Collection Request; Comment Request; EPA Application Materials for the Water Infrastructure Finance and Innovation Act," 81 Federal Register 32327-32328, May 23, 2016. |
|
27. | 26. U.S. Environmental Protection Agency, "Credit Assistance for Water Infrastructure Projects, interim final rule; request for public comments," 81 Federal Register 91822-91839, December 19, 2016. An interim final rule is one that is adopted without prior public comment and which is made effective immediately, although federal agencies typically request comments and can alter the interim rule if warranted by public comments. |
|
|