 
 
 
 
Statement of 
Ronald O'Rourke 
Specialist in Naval Affairs 
Before 
Committee on Commerce, Science, and Transportation 
Subcommittee on Oceans, Atmosphere, Fisheries, and Coast Guard 
U.S. Senate 
Hearing on 
“Building the Fleets of the Future: Coast 
Guard and NOAA Fleet Recapitalization” 
October 11, 2018 
Congressional Research Service 
https://crsreports.congress.gov 
TE10029 
 
  
 
 link to page 14  link to page 15  link to page 16  link to page 18  link to page 3  link to page 2 
Congressional Research Service 
1 
Chairman Sullivan, Ranking Member Baldwin, distinguished members of the subcommittee, thank you 
for the opportunity to appear before you today to testify on Coast Guard and NOAA fleet recapitalization. 
Ship acquisition has been a major focus of my work as a CRS analyst on naval issues for the past 34 
years. I have covered Coast Guard ship acquisition for Congress for 20 years1 and last testified before this 
committee on the issue in 2005.2 My biography is shown i
n Appendix A. 
My CRS reports on Coast Guard cutter procurement and polar icebreaker procurement provide extensive 
discussions of the Coast Guard’s National Security Cutter (NSC) program, Offshore Patrol Cutter (OPC) 
program, Fast Response Cutter (FRC) program and polar icebreaker program (recently renamed the Polar 
Security Cutter, or PSC, program).3 As requested by the subcommittee, this statement provides some 
focused observations regarding these programs as well as the Coast Guard’s Waterways Commerce Cutter 
(WCC) program and NOAA’s fleet recapitalization effort. 
Appendix B to this statement presents a general summary of some lessons learned in government 
shipbuilding
. Appendix C presents some considerations relating to the use of warranties in government 
shipbuilding
. Appendix D presents some considerations relating to avoiding procurement cost growth vs. 
minimizing procurement costs in government shipbuilding. 
Coast Guard Fleet Recapitalization 
Adequacy of Planned Quantities of NSCs, OPCs, and FRCs 
The Coast Guard’s 91-ship program of record (POR) for general-purpose cutters—which dates to 2004 
and calls for a force of 8 NSCs, 25 OPCs, and 58 FRCs—will provide substantially more capability than 
the force of older-generation cutters it will replace. At the same time, it can be useful to recall that Coast 
Guard studies have concluded that the planned total of 91 NSCs, OPCs, and FRCs would provide only 
61% of the NSCs, OPCs, and FRCs that would be needed to fully perform the service’s statutory missions 
in coming years, in part because Coast Guard mission demands are expected to be greater in coming years 
than they were in the past. As shown i
n Table 1, the Coast Guard’s 2011 Fleet Mix Analysis (FMA) Phase 
2—the last general analysis of future Coast Guard ship force structure requirements to be publicly 
released by the Coast Guard—concluded that fully performing the Coast Guard’s statutory missions in 
coming years would require a total of 149 NSCs, OPCs, and FRCs.4 This point may be particularly salient 
                                                 
1 See, for example: 
  CRS Report 98-830 F, 
Coast Guard Integrated Deepwater System: Background and Issues for Congress, by Ronald 
O’Rourke, first version October 5, 1998, final (i.e., archived) version June 1, 2001; 
  CRS Report RS21019, 
Coast Guard Deepwater Program: Background and Issues for Congress, by Ronald O’Rourke, 
first version September 25, 2001, final (i.e., archived) version December 8, 2006;  
  CRS Report RL33753, 
Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for 
Congress, by Ronald O'Rourke, first version December 18, 2006, final (i.e., archived) version January 20, 2012; 
  CRS Report R42567, 
Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke, 
first version June 13, 2012, current version August 3, 2018; and 
  CRS Report RL34391, 
Coast Guard Polar Icebreaker Program: Background and Issues for Congress, by Ronald 
O'Rourke, first version February 26, 2008, current version August 3, 2018. 
2 See Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, before the Senate 
Commerce, Science, and Transportation Committee, subcommittee on Fisheries and the Coast Guard, hearing on The Coast 
Guard’s Revised Deepwater Implementation Plan, June 21, 2005, 15 pp. 
3 See the final two reports cited above in footno
te 1. 
4 For additional discussion, see Appendix A of CRS Report R42567, 
Coast Guard Cutter Procurement: Background and Issues 
for Congress, by Ronald O'Rourke. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
2 
right now in connection with the NSC and FRC programs, procurement of which would end soon under 
the POR figures. 
Table 1. Program of Record Compared to Fleet Mix Analysis Phase 2 (2011) 
Refined Objective Mix 
Program of 
from Fleet Mix Analysis, 
Ship Type 
Record 
Phase 2 (2011) 
NSC 
8 
9 
OPC 
25 
49 
FRC 
58 
91 
Total 
91 
149 
Source: Coast Guard Fleet Mix Analysis, Phase 2, 2011, Table ES-2 on p. iv. For additional discussion, see Appendix A of 
CRS Report R42567, 
Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke. 
PC&I Account Funding Levels 
There has been some discussion recently of how certain Coast Guard procurement programs would not be 
affordable if the Coast Guard’s Procurement, Construction, and Improvements (PC&I) account in coming 
years were limited to an average of about $1.1 billion per year.5 An average PC&I funding level of about 
$1.1 billion per year would have that effect. In 2013, then-Coast Guard Commandant Robert Papp 
testified that an annual PC&I funding level of about $1 billion per year “almost creates a death spiral for 
the Coast Guard.”6 The notion that the PC&I funding level will be limited to an average of about $1.1 
billion per year, however, is no longer strongly supported by recent data on Coast Guard annual funding 
requests,7 annual enacted funding levels,8 or projected future annual funding requests as shown in Coast 
Guard five-year Capital Investment Plans (CIPs).9 
                                                 
5 See Government Accountability Office, 
Coast Guard Acquisitions[:] Actions Needed to Address Longstanding Portfolio 
Management Challenges, GAO-18-454, July 2018, Figure 4 on page 22, and GAO’s spoken testimony during the question-and-
answer portion of a July 24, 2018, hearing on Coast Guard acquisition programs and mission balance and effectiveness before the 
Coast Guard and Maritime Transportation subcommittee of the House Transportation Committee, during which Figure 4, which 
depicts a funding funnel, was shown on the hearing room’s display screens. (The funnel, which compares an annual PC&I 
account funding figure of $1.1 billion to a higher figure of $2 billion consistent with the Coast Guard’s preferred PC&I account 
annual funding level, is not drawn to scale: Although $1.1 billion is 55% of $2 billion, the narrower $1.1-billion bottom of the 
funnel has an opening with a diameter than is no more than 22% as wide as that of the larger, $2-billion top of the funnel.) In 
report GAO-18-454, see also Figure 3 on page 15, which indicates an average requested funding level of about $1.1 billion per 
year for the period FY2014-FY2018, as well as the discussion on pages 13-14. 
6 Admiral Papp’s spoken testimony during a May 14, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the 
Homeland Security subcommittee of the Senate Appropriations Committee, as reflected in the transcript for the hearing. 
7 While the Coast Guard’s annual budget submissions for the five-year period FY2014 through FY2018 requested an average of 
about $1,065 million per year for the PC&I account, the Coast Guard’s most recent request for the account—the request in its 
proposed FY2019 budget—is for $1,886.8 million (a figure that reflects a late addition of $720 million to the request for the polar 
icebreaker program), and the Coast Guard’s annual budget submissions for the five-year period FY2009-FY2013 requested an 
average of about $1,322 million for the account. 
8 Over the last 10 fiscal years (FY2009-FY2018), enacted funding levels for the PC&I account (including rescissions of 
unobligated balances) have averaged about $1,560 million per year. Only once during this period, in FY2015, was the enacted 
figure less than $1,200 million (it was $1,166.6 million that year). In the other nine years, it was more than $1,200 million, and 
sometimes substantially more. The figures for the three most recent fiscal years—FY2016, FY2017, and FY2018—were $1,928.4 
million, $1,370.0 million, and $2,282.4 million, respectively. 
9 Although the projected funding requests in the FY2014, FY2015, and FY2016 CIPs (showing figures for FY2014-FY2018, 
FY2015-FY2019, and FY2016-FY2020, respectively), averaged about $1,114.8 million per year, the projected funding requests 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
3 
In assessing future funding levels for executive branch agencies, a common practice is to assume or 
predict that the figure in coming years will likely be close to where it has been in previous years. While 
this method can be of analytical and planning value, for an agency like the Coast Guard, which goes 
through periods with less acquisition of major platforms and periods with more acquisition of major 
platforms, this approach might not always be the best approach, at least for the PC&I account. 
More important, in relation to maintaining Congress’s status as a co-equal branch of government, 
including the preservation and use of congressional powers and prerogatives, an analysis that assumes or 
predicts that future funding levels will resemble past funding levels can encourage an artificially narrow 
view of congressional options regarding future funding levels, which could deprive Congress of agency in 
the exercise of its constitutional power to set funding levels and determine the composition of federal 
spending. 
As one example of how past funding levels were not the best guide to future funding levels, and of how 
Congress has exercised its constitutional power to set funding levels and determine the composition of 
federal spending, during the period FY2008-FY2015, when the Navy’s shipbuilding account averaged 
about $14.7 billion per year in then-year dollars, there was recurring discussion about the challenge of 
increasing the account to the substantially higher annual funding levels that would soon be needed to 
begin implementing the Navy’s 30-year shipbuilding plan. Projections were prepared by CBO showing 
the decline in the size of the Navy that would occur over time if funding levels in the shipbuilding 
account did not increase substantially from the average level of about $14.7 billion per year. Congress, 
after assessing the situation, increased the shipbuilding account to $18.7 billion in FY2016, $21.2 billion 
in FY2017, $23.8 billion in FY2018, and $24.2 billion in FY2019. These increasing funding levels 
occurred even though the Budget Control Act, as amended, remained in operation during those years. At 
the most recent figure of $24.2 billion, the Navy’s shipbuilding account is now 74% greater in then-year 
dollars than it was as recently as FY2010. 
Coast Guard’s Non-Use of Multiyear Contracting 
In connection with my work on ship acquisition, I maintain the CRS report on multiyear procurement 
(MYP) and block buy contracting.10 In both that report and in testimony I have given to other committees 
in recent years on Coast Guard ship acquisition,11 I have noted the stark contrast between the Navy—
which uses multiyear contracting (in the form of MYP or block buy contracting) extensively to reduce its 
ship- and aircraft-procurement costs by billions of dollars—and the Coast Guard, which to date has never 
used multiyear contracting in one of its ship or aircraft acquisition programs. 
The Navy in recent years, with congressional approval, has used multiyear contracting for, among other 
things, all three of its year-to-year shipbuilding programs—the Virginia-class attack submarine program, 
the DDG-51 destroyer program, and the Littoral Combat Ship (LCS) program.12 The Navy has been using 
multiyear contracting for the Virginia-class and DDG-51 programs more or less continuously since the 
1990s. Savings from the use of MYP recently have, among other things, helped Congress and the Navy to 
                                                 
in the FY2017 CIP (for the period FY2017-FY2021) averaged about $1,427.5 million, and those in the FY2018 CIP (for the 
period FY2018-FY2022) averaged about $1,533.1 million. 
10 CRS Report R41909, 
Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and 
Issues for Congress, by Ronald O'Rourke and Moshe Schwartz. 
11 See, for example, CRS Testimony TE10020, 
Building a 21st Century Infrastructure for America: Coast Guard Sea, Air, and 
Land Capabilities: Part II, by Ronald O'Rourke, and CRS Testimony TE10004, 
The Status of Coast Guard Cutter Acquisition 
Programs, by Ronald O'Rourke. 
12 The term year-to-year shipbuilding program is used here to mean a shipbuilding program in which at least one ship of that kind 
is procured each year. The Coast Guard plans to execute the OPC program as a year-to-year shipbuilding program. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
4 
convert a nine-ship buy of DDG-51 class destroyers in FY2013-FY2017 into a 10-ship buy, and a nine-
ship buy of Virginia-class attack submarines in FY2014-FY2018 into a 10-ship buy. The Navy is also now 
using block buy contracting in the John Lewis (TAO-205) class oiler program, and is considering or 
anticipating using them for procuring LPD-17 Flight II amphibious ships, FFG(X) frigates, and 
Columbia-class ballistic missile submarines. The Navy’s use or prospective use of multiyear contracting 
for its year-to-year shipbuilding programs is arguably now almost more of a rule than an exception in 
Navy shipbuilding. For Congress, granting approval for using multiyear contracting involves certain 
tradeoffs, particularly in connection with retaining year-to-year control of funding.13 In the case of Navy 
shipbuilding, Congress has repeatedly accepted these tradeoffs.  
In contrast with Navy practice, the Coast Guard often uses contracts with options in its ship-procurement 
programs. Contracts with options can be referred to as 
multiple-year contracts, but they are not 
multiyear contracts. Instead, contracts with options operate more like annual contracts, and they cannot achieve the 
kinds of savings that are possible with multiyear contracts.14 Like the other military services, the Coast 
Guard has statutory authority to use MYP contracting and can be granted authority by Congress to use 
block buy contracting. 
National Security Cutter (NSC) Program 
The NSCs were procured at irregular rather than regular intervals, and they were procured with annual 
rather than multiyear contracts. Both of these aspects of their acquisition made the ships more expensive. 
If NSCs had instead been procured at regular intervals under multiyear contracts that included authority 
for economic order quantity (EOQ) purchases (i.e., up-front batch orders of selected components for some 
or all of the ships covered under the contract), the reduction in their combined procurement cost could 
have been substantial—possibly enough (or even more than enough) to have paid for one of the 11 NSCs 
that have been fully funded through FY2018. 
As discussed below in the section on the OPC program, building additional NSCs is one option for 
acquiring replacements for retiring medium-endurance cutters more quickly than currently planned, so as 
to close more quickly any gap in time between retirements of the medium-endurance cutters and the entry 
into service of their replacements. The NSCs are bigger and in some respects more capable than OPCs, 
and they would individually be more expensive to procure and to operate and support than OPCs. The 
difference in size, capability, and cost between the NSC and OPC design is not insignificant, but neither is 
it a night-and-day difference. With an estimated full-load displacement of 3,500 to 3,730 tons,15 for 
example, OPCs are to be roughly 80% as large as NSCs, which have a full load displacement of about 
                                                 
13 From a congressional perspective, tradeoffs in making greater use of multiyear contracting include the following: reduced 
congressional control over year-to-year spending and tying the hands of future Congresses; reduced flexibility for making 
changes in acquisition programs in response to unforeseen changes in strategic or budgetary circumstances (which can cause any 
needed funding reductions to fall more heavily on acquisition programs not covered by multiyear contracts); a potential need to 
shift funding from later fiscal years to earlier fiscal years to fund EOQ purchases of components; the risk of having to make 
penalty payments to shipbuilders if multiyear contracts need to be terminated due to unavailability of funds needed for the 
continuation of the contracts; and the risk that materials and components purchased for ships to be procured in future years might 
go to waste if those ships are not eventually procured. Congress has considered these tradeoffs in deciding whether to grant the 
Navy authority for using multiyear contracting in the service’s shipbuilding and other acquisition programs. 
14 For additional discussion, see CRS Report R41909, 
Multiyear Procurement (MYP) and Block Buy Contracting in Defense 
Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz, particularly the section entitled 
“MYP and BBC vs. Contracts with Options.” 
15 As of May 26, 2017, the OPC’s light ship displacement (i.e., its “empty” displacement, without fuel, water, ballast, stores, and 
crew) was preliminarily estimated at about 2,640 to 2,800 tons, and its full load displacement was preliminarily estimated at 
about 3,500 to 3,730 tons. (Source: Figures provided to CRS by Coast Guard liaison office, May 26, 2017.) 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
5 
4,500 tons.16 In terms of size, capability, and cost, the OPC is a lot closer to the NSC than it is to the FRC, 
which is a large patrol craft with a full load displacement of 353 tons. 
Procurement of NSCs for replacing retiring Hamilton-class high-endurance cutters is approaching its end. 
If additional NSCs were procured in the near term in parallel with OPC procurement as part of a strategy 
for more quickly replacing retiring medium-endurance cutters, the additional NSCs could be built using 
the currently open NSC production line, avoiding a break in that production line and thereby maximizing 
production learning curve benefits. The procurement cost of any additional NSCs might be further 
reduced by procuring them at regular intervals and using an MYP contract. 
OPC Program 
The Coast Guard is using a contract with options to procure the first nine OPCs. As stated earlier, 
although a contract with options might look like a multiyear contract, it is not a form of multiyear 
contracting. A contract with options operates more like annual contracting and cannot achieve the kinds of 
savings that are possible with multiyear contracting.17 
Using multiyear contracting in the 25-ship OPC program—specifically, block buy contracting with EOQ 
authority for the initial ships in the program, followed by either block buy contracting with EOQ authority 
or MYP contracting for later ships in the program—rather than annual contracting might reduce the total 
acquisition cost of the program by about $1 billion. This potential savings of $1 billion—a figure equal to 
or greater than the acquisition cost of either a polar icebreaker or a 35-ship Waterways Commerce Cutter 
program—represents a rare opportunity for using multiyear contracting to reduce the cost of an individual 
Coast Guard acquisition program by such an amount. 
Acquiring the first nine ships in the OPC program under the current contract with options could forego 
roughly $350 million of the $1 billion in potential savings. Much of this $350 million in potential savings 
might be recaptured by renegotiating the current contract so as to convert it, with congressional approval, 
into a block buy contract with EOQ authority. If acquisition regulations prohibit such a renegotiation, the 
Coast Guard alternatively could choose to not exercise most of the options in the current contract and 
hold a new competition for building the current NSC design under a block buy contract. The current OPC 
builder—Eastern Shipbuilding of Panama City, FL—would be well positioned to win such a competition, 
since it would involve building Eastern’s own design and Eastern would already have moved down the 
initial (i.e., the steepest) part of the learning curve for building the design. 
The current planned procurement profile for the OPC, which reaches a maximum projected rate of two 
ships per year, would deliver OPCs many years after the end of the originally planned service lives of the 
medium-endurance cutters that they are to replace. Coast Guard officials have testified that the service 
plans to extend the service lives of the medium-endurance cutters until they are replaced by OPCs. There 
will be maintenance and repair expenses associated with extending the service lives of medium-endurance 
cutters, and if the Coast Guard does not also make investments to increase the capabilities of these ships, 
the ships may have less capability in certain regards than OPCs. 
One possible option for addressing this situation would be to increase the maximum annual procurement 
rate of the replacement ships from the currently planned two ships per year to a higher figure. Increasing 
the rate to three or four ships per year, for example, could result in the 25th ship being delivered about 
four years or six years sooner, respectively, than under the currently planned maximum rate. Increasing 
                                                 
16 Source for figure of 4,500 tons: Coast Guard NSC fact sheet, accessed October 3, 2018, at: 
https://www.dcms.uscg.mil/Portals/10/CG-9/Acquisition%20PDFs/Factsheets/NSC.pdf?ver=2017-04-24-142526-023. 
17 For additional discussion, see CRS Report R41909, 
Multiyear Procurement (MYP) and Block Buy Contracting in Defense 
Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz, particularly the section entitled 
“MYP and BBC vs. Contracts with Options.” 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 3 
Congressional Research Service 
6 
the procurement rate would require a substantial increase to the Coast Guard’s AC&I account, which gets 
back to the issue discussed earlier of future funding levels for that account and Congress’s agency in 
setting funding levels and determining the composition of federal spending. 
From a production point of view, there are at least three options for increasing the annual procurement 
rate of replacement ships from the currently planned two ships per year to a higher rate, so as to close any 
gap in time between the retirements of medium-endurance cutters and the entry into service of their 
replacements. These options are as follows: 
  increasing the annual OPC production rate at Eastern Shipbuilding, if Eastern’s capacity 
would permit this; 
  building additional OPCs at one or two additional shipyards, such as Bollinger Shipyards 
of Lockport, LA and/or General Dynamics’ Bath Iron Works (GD/BIW) of Bath, ME—
the two other finalists in the OPC competition; and 
  building additional NSCs at Huntington Ingalls Industries/Ingalls Shipbuilding 
(HII/Ingalls). 
These three options are not mutually exclusive—they could be pursued in combination. Additional OPCs 
built at Bollinger and/or GD/BIW could be built to the OPC designs that those two shipbuilders submitted 
for the OPC competition. (Those designs are presumably optimized for the production facilities at 
Bollinger and GD/BIW. The Coast Guard, moreover, currently does not have data rights for the complete 
vessel design for Eastern’s OPC design.18) Building additional OPCs at Bollinger and/or GD/BIW to the 
designs developed by those two shipbuilders would result in a fleet with two or three classes of OPCs, a 
situation that would increase OPC life-cycle operation and support costs and complicate the training and 
assignment of OPC crew members. These additional life-cycle costs and complications, however, might 
be deemed acceptable in return for avoiding the costs and risks of extending the service lives of medium-
endurance cutters and shortening any gap in time between the retirement of medium-endurance cutters 
and the entry into service of their replacements. The Navy decided in 2010 to fill its requirement for LCSs 
by building two different LCS designs at the same time, and did so knowing that this would result in some 
additional life-cycle operation and support costs and crewing-related complications compared to the 
option of building all LCSs to a single design.19 The option of building additional NSCs as replacements 
for retiring medium-endurance cutters was discussed above in the section on the NSC program. 
FRC Program 
With 50 FRCs procured through FY2018 and four more requested for FY2019, the FRC is approaching 
the 58-ship figure called for in the Coast Guard’s program of record. As shown earlier i
n Table 1, 
however, the Coast Guard’s 2011 Fleet Mix Analysis Phase II concluded that a total of 91 FRCs would be 
needed as part of an overall force of 149 general-purpose cutters to fully perform the service’s statutory 
missions in coming years. 
Procuring additional FRCs beyond the 58th would require additional procurement funding, which gets 
back to the issue discussed earlier of future funding levels for the PC&I account and Congress’s agency in 
setting funding levels and determining the composition of federal spending. As with the option discussed 
earlier of procuring additional NSCs, procuring additional FRCs immediately following the procurement 
of the 58th FRC would permit them to be built using the currently open NSC production line, avoiding a 
break in that production line and thereby maximizing production learning curve benefits. And as with the                                                  
18 Source regarding data rights: Email from Coast Guard liaison office to CRS, September 6, 2017. 
19 For additional discussion of the LCS program, see CRS Report RL33741, 
Navy Littoral Combat Ship (LCS) Program: 
Background and Issues for Congress, by Ronald O'Rourke. A total of 35 LCSs have been funded through FY2019. Of these 35 
ships, 17 will be built to one of the LCS designs, and 18 will be built to the other. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
7 
NSC option discussed earlier, the cost of any such additional FRCs could be reduced by procuring them 
under an MYP or block buy contract. The resulting increase in Coast Guard force structure from 58 FRCs 
to some higher number would increase long-term Coast Guard operation and support costs above 
currently planned levels. 
Polar Security Cutter (PSC) (aka Polar Icebreaker) 
Reduction in Estimated Procurement Cost and Business Case 
One of the most notable changes in the PSC program over the last year or two has been the reduction in 
the estimated unit procurement cost of the ships. The procurement cost of a new heavy polar icebreaker 
had earlier been estimated informally at roughly $1 billion, but the Coast Guard and Navy informed CRS 
and CBO in March 2018 that they now believe that three polar icebreakers could be acquired for a total 
cost of about $2.1 billion, or an average of about $700 million per ship.20 (The first ship will cost more 
than the other two because it will incorporate design costs for the class and be at the start of the 
production learning curve for the class.) Other information identifies a smaller reduction in procurement 
cost, to something more than $900 million per ship.21 Other things held equal, reductions in the estimated 
unit procurement cost of the polar icebreaker strengthen the business case for the program. A reduction in 
estimated unit procurement cost to an average of $700 million per ship would strengthen it substantially. 
Option for Block Buy Contract 
The baseline plan for the PSC program calls for acquiring the ships using a contract with options, but 
Coast Guard and Navy officials are open to the idea of instead using a block buy contract to acquire at 
least some of the ships, and requested information on this possibility as part of the request for proposals 
(RFP) for the PSC program that was released on March 2, 2018. Using the above $2.1 billion estimated 
cost for a three-ship procurement of PSCs, and based on savings estimates provided by the Navy in the 
past for Navy shipbuilding programs that were being proposed for multiyear contracting, using a block 
buy contract that included EOQ purchases rather than a contract with options might reduce the combined 
acquisition cost of three PSCs by upwards of 7%, which could equate to a savings of upwards of $150 
million. 
A congressionally mandated July 2017 National Academies of Sciences, Engineering, and Medicine 
(NASEM) report on acquisition and operation of polar icebreakers states (emphasis as in original): 
3.  Recommendation:  USCG  should  follow  an  acquisition  strategy  that  includes  block  buy 
contracting with a fixed price incentive fee contract and take other measures to ensure best 
value for investment of public funds. 
Icebreaker  design  and  construction  costs  can  be  clearly  defined,  and  a  fixed  price  incentive  fee 
construction  contract  is  the  most  reliable  mechanism  for  controlling  costs  for  a  program  of  this 
complexity. This technique is widely used by the U.S. Navy. To help ensure best long-term value, 
                                                 
20 Source: March 16, 2018, Coast Guard-Navy briefing to CRS and CBO on the polar icebreaker program. For further discussion, 
see the section entitled “Estimated Acquisition Cost Has Declined Substantially” in CRS Report RL34391, 
Coast Guard Polar 
Icebreaker Program: Background and Issues for Congress, by Ronald O'Rourke. 
21 May 2018 GAO report states that the acquisition program baseline (APB) approved for the polar icebreaker program in 
January 2018 estimated the program’s acquisition cost at $3.207 million, and that the “current estimate” of the program’s 
acquisition as of January 2018 was $2,789 million, or an average of about $930 million per ship. (Government Accountability 
Office, 
Homeland Security Acquisitions[:] Leveraging Programs’ Results Could Further DHS’s Progress to Improve Portfolio 
Management, GAO-18-339SP, May 2018, p. 85.) See also Government Accountability Office, 
Coast Guard Acquisitions[:] 
Actions Needed to Address Longstanding Portfolio Management Challenges, GAO-18-454, July 2018, which states on page 18 
that “The polar icebreaker program has an estimated total acquisition cost of more than $3 billion….” 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 15 
Congressional Research Service 
8 
the  criteria  for  evaluating  shipyard  proposals  should  incorporate  explicitly  defined  lifecycle  cost 
metrics.... 
A block buy authority for this program will need to contain specific language for economic order 
quantity  purchases  for  materials,  advanced  design,  and  construction  activities.  A  block  buy 
contracting program with economic order quantity purchases enables series construction, motivates 
competitive bidding, and allows for volume purchase and for the timely acquisition of material with 
long  lead  times.  It  would  enable  continuous  production,  give  the  program  the  maximum  benefit 
from the learning curve, and thus reduce labor hours on subsequent vessels.... 
If advantage is taken of learning and quantity discounts available through the recommended block 
buy contracting acquisition strategy, the average cost per heavy icebreaker is approximately $791 
million, on the basis of the acquisition of four ships.22 
Although Coast Guard officials have expressed interest in using a block buy contract for procuring PSCs, 
they are considering the option of procuring the first PSC under a single-ship contract and then using a 
block buy contract to procure subsequent PSCs. In support of that option, Coast Guard officials have 
noted the risks involved in building a lead ship and the fact that the United States has not built a heavy 
polar icebreaker in more than 40 years. Opponents of including the first PSC in a block buy contract 
might argue, for example, that problems with the design of PSC components might be transmitted from 
the first PSC to later PSCs by up-front EOQ purchases of those components made under a block buy 
contract. They might additionally argue that excluding the first PSC from a block buy contract preserves 
more government flexibility on whether and when to procure a second PSC, which could be advantageous 
for responding to potential changes in operational needs or budgetary circumstances. 
Supporters of including the first PSC in a block buy contract could argue that block buy contracting was 
invented to a large degree expressly to permit a lead ship to be included in the contract, that the Navy has 
included lead ships in block buy contracts in the Virginia-class attack submarine program and the TAO-
205 class oiler program, and that the Navy is considering using a block buy contract that includes the lead 
ship for procuring the initial ships in the Columbia-class ballistic missile submarine program. The 
comparison with the Navy’s plans for the Columbia class, they could argue, is of particular note, because 
the United States has not procured the lead ship of a new class of ballistic missile submarines in more 
than 40 years, the Columbia-class design is more complex in certain regards than the PSC design, and the 
Columbia-class design will incorporate a new-design electric-drive propulsion plant—something that the 
United States has never before done on a series-production nuclear-powered submarine. 
The lead ship in the PSC program will carry a risk of requiring design changes to fix problems in the 
design that are only discovered as a result of building the design. That risk, however, will exist regardless 
of whether the lead ship is built under a single-ship contract of a block buy contract, and it is not clear 
how much more chance there would be under a block buy contract of transmitting any such design 
problems to the second PSC, because the Coast Guard’s notional schedule for the PSC program calls for 
procuring the second ship about 18 months after the first (i.e., while construction of the first PSC is still in 
progress). To the extent that there would be a greater chance of transmitting design problems to the 
second PSC under a block buy contract, the question would then become one of weighing the potential 
cost of fixing those design problems against the added economies of including the first PSC in a block 
buy contract. Supporters of including the lead ship in a block buy contract could argue that the risks of 
encountering a design problem in the first ship have been mitigated by the industry’s shift since the last 
polar icebreakers were built from paper designs to computer-aided design, by the Navy’s involvement in 
the PSC program, and by the PSC program’s strategy of using a parent design (i.e., an existing polar-
capable icebreaker design) as the basis for the PSC design. As shown i
n Appendix B, a key lesson-
                                                 
22 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation Research 
Board, 
Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with cover letter dated July 
11, 2017, pp. 14, 15. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 20 
Congressional Research Service 
9 
learned in government shipbuilding is to bring the design of the ship in question to a high level of 
completion before beginning construction of the ship, precisely so as to minimize the risk of design 
problems. Supporters of including the lead ship in a block buy contract could argue that if there is a 
significant risk of substantial design problems in the lead ship, that is not an argument against including 
the lead ship in a block buy contract—it is an argument against beginning construction of the ship under 
any form of contract. 
Risk of Delayed Delivery of Lead Ship 
GAO has identified a risk of the first PSC being delivered late.23 I agree with that assessment. The Navy’s 
experience in building lead ships suggests that there is a substantial risk of the lead PSC being delivered 
late—perhaps as much as a year or more later than scheduled. A late delivery could equate to an increase 
in the cost of building the ship, because it could reflect having to use more labor hours to build the ship 
than had been estimated, and because the ship will absorb more of the shipyard’s overhead costs by 
remaining in the shipyard for a longer period of time. The government can insulate itself against the risk 
of such cost growth by using a fixed-price contract to build the ship (which the Coast Guard and Navy 
plan to do). 
The possibility of a late delivery is something the Coast Guard and Congress may consider preparing for 
in terms of investments for maintaining 
Polar Star as an operational ship and/or seeking a short-term 
bridging charter of a foreign polar icebreaker. To the extent that a delay in delivering the lead ship would 
extend a gap in time between the retirement of 
Polar Star and the entry into service of the first PSC, that 
could become an argument for starting construction of the lead PSC as soon as its design is brought to a 
high level of completion and the ship is otherwise ready to begin construction. 
Option for Using a Common Design for Heavy and Medium PSCs 
The Coast Guard envisages procuring up to three new medium icebreakers after it procures three new 
heavy polar icebreakers—a plan known as 3+3. The July 2017 NASEM report concluded that notional 
operational requirements for new medium polar icebreakers would result in ships that would not be too 
different in size from new heavy polar icebreakers. (That is not be particularly surprising—the Coast 
Guard’s current medium polar icebreaker, 
Healy, is actually somewhat larger than the Coast Guard’s 
heavy polar icebreaker, 
Polar Star. 
Healy has less icebreaking capability than 
Polar Star, but more 
capacity for supporting onboard science operations.) Given this probable similarity in size, the NASEM 
report recommended building a single medium polar icebreaker to the same common design as the three 
new heavy polar icebreakers (i.e., 4+0), and operating these four new ships in conjunction with 
Healy to 
produce a five-ship polar icebreaker fleet. The 4+0 production strategy, the report concluded, would 
reduce the cost of the medium icebreaker by avoiding the cost of developing a second icebreaker design 
and making the medium polar icebreaker the fourth ship on an existing production learning curve rather 
than the first ship on a new production learning curve. An abstract from the NASEM report on this 
proposal is shown i
n Appendix E to this statement. 
If policymakers decide to procure a second or third new medium polar icebreaker, the same general 
approach recommended by the NASEM report could be followed, leading to a 5+0 or 6+0 acquisition. 
The potential percentage savings under a five- or six-ship block buy contract with EOQ authority could be 
greater than the figure of upwards of 7% mentioned earlier for a three-ship block buy—they could be 
                                                 
23 See GAO’s spoken testimony during the question-and-answer portion of a July 24, 2018, hearing on Coast Guard acquisition 
programs and mission balance and effectiveness before the Coast Guard and Maritime Transportation subcommittee of the House 
Transportation Committee, as reflected in the transcript of the hearing. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
10 
closer to 10%. Building a single common icebreaker design rather than two designs to meet needs for 
heavy and medium polar icebreakers might also reduce life-cycle operation and support costs. 
An April 12, 2018, press report states: 
As the Coast Guard prepares to review industry bids for a new heavy polar icebreaker, the service 
is  keeping  its  options  open  for  the  right  number  and  mix  of  polar  icebreakers  it  will  need  in  the 
future, Adm. Paul Zukunft, the [then-]commandant of the Coast Guard, said on Wednesday [April 
11]. 
The Coast Guard’s program of record is for three heavy and three medium polar icebreakers but 
Zukunft said the “jury is still out” whether that will remain so. Right now, the service is aiming 
toward building three new heavy icebreakers, but it might make sense just to keep building these 
ships, he told reporters at a Defense Writers Group breakfast in Washington, D.C. 
Zukunft said that “when you start looking at the business case after you build three, and then you 
need to look at what is the economy of scale when you start building heavy icebreakers, and would 
it  be  less  expensive  to  continue  to  build  heavies  and  not  mediums.”  He  added  that  the  heavy 
icebreakers provide  more  capability, and if the  price  is  “affordable”  and in “the  same  range” as 
building medium icebreakers, then “maybe you end up with one class of heavy icebreakers.” 
Building  only  one  class  of  ships  has  a  number  of  advantages  in  terms  of  maintenance,  crew 
familiarity, configuration management, and more, he said. A decision on what the future icebreaker 
fleet will consist of is “still probably several years out …. but that’s one option that we want to keep 
open going forward,” Zukunft said.24 
WCC Program 
The WCC program—the program to replace the Coast Guard’s current 35-ship inland waterways fleet—is 
a smaller program than those discussed above. With a notional procurement cost of roughly $25 million 
per cutter, a 35-ship replacement program might have a total acquisition cost of roughly $900 million.25 
Although the scale of the program is more modest than that of the NSC, OPC, and FRC programs, the 
WCC program is of importance in terms of its economic benefit to the nation (by supporting waterborne 
commerce) and the bidding opportunity it will provide to U.S. shipyards that are not capable of building 
larger Coast Guard cutters. 
As the Coast Guard begins to develop the details of this program, potential oversight issues for the 
subcommittee could include, among other things, the planned number of replacement cutters (which has 
not yet been determined and could turn out to be something other than 35), planned annual procurement 
quantities and the resulting schedule for replacing the existing ships, whether to develop a new design or 
instead use a parent design, the number of shipyards to be used to build the ships, and the contracting 
strategy, including whether to use multiyear contracting. 
                                                 
24 Calvin Biesecker, “Coast Guard Leaving Options Open For Future Polar Icebreaker Fleet Type,” Defense Daily, April 12, 
2018. Ellipsis as in original. 
25 Source for $25 million figure: Spoken testimony of Coast Guard Commandant Karl Schultz during the question-and-answer 
portion of a September 16, 2018, hearing on Coast Guard modernization and recapitalization before the Coast Guard and 
Maritime Transportation subcommittee of the House transportation and Infrastructure Committee, as reflected in the transcript of 
the hearing. The Commandant stated: “I'm loathed to put a number out, but I think you're talking a $25 million, plus or minus, 
[cost per] ship.” The planned number of new replacement WCCs has not yet been determined and could turn out to be something 
other than 35. GAO states that “according to Coast Guard officials, the preliminary rough order of magnitude estimate for total 
acquisition cost is $1.1 billion.” Government Accountability Office, 
Coast Guard Acquisitions[:] Actions Needed to Address 
Longstanding Portfolio Management Challenges, GAO-18-454, July 2018, p. 19. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
11 
NOAA Fleet Recapitalization 
NOAA is now in the opening stages of its effort to procure eight new ships to replace eight aged ships 
within its 16-ship research fleet. Current plans call for the eight-ship recapitalization effort to be level-
funded at $75 million per year. Building these ships could provide work to shipyards that are not capable 
of building larger Navy or Coast Guard ships. They could also help a shipyard involved in building larger 
Navy or Coast Guard ships to fill in temporary dips in their Navy or Coast Guard workloads, which might 
permit the Navy or Coast Guard ships in question to be built at lower cost. With procurement of the eight 
new NOAA ships now beginning, the effort presents some potential oversight issues for the 
subcommittee. 
Unit Procurement Cost and Total Program Procurement Cost 
One of these concerns the visibility of the estimated unit procurement costs of the new ships and the 
estimated total procurement cost of the eight-ship effort. These figures—which are basic points of 
information for Congress for supporting potential consideration of budget tradeoffs and for use as 
baselines in monitoring program execution—are not clearly visible in NOAA’s FY2019 budget 
justification book. It is difficult, moreover, to calculate what the unit procurement cost might be using the 
information in the budget justification book, since the program is level-funded at $75 million per year, 
there is a different combination of activities to be funded each year under that funding figure, and the 
individual costs of these activities are not broken out. One option the subcommittee may wish to consider 
would be to request or direct NOAA to include the ships’ estimated unit procurement costs and the 
program’s estimated total procurement cost in its annual budget justification book. 
Number of New Designs 
A second potential oversight issue for the subcommittee concerns the number of new designs that NOAA 
is planning to use for building for the eight new ships. NOAA is currently planning to build the new ships 
to four designs, meaning an average of two ships per design. Compared to a strategy of building the eight 
ships to fewer than four designs, NOAA’s planned approach could increase total design costs, reduce 
opportunities for achieving shipyard production learning curve benefits, and reduce economies of scale in 
life-cycle operation and support costs. 
In a telephone consultation with CRS, NOAA officials stated that the option of building the eight ships to 
a smaller number of designs was considered for exactly these reasons, but that the decision was to instead 
plan for four different designs because of the differing operational requirements of the eight ships. 
Building a common design capable of handling these differing requirements, NOAA stated, would result 
in a design that would be bigger—and thus more expensive both to procure and to operate and support—
than would be needed for some of the eight ships, and these additional procurement and life-cycle 
operation and support costs were greater than the potential savings of building the ships to a smaller 
number of designs.26 That explanation is quite plausible. One option the subcommittee may wish to 
consider would be to request or direct NOAA to provide the details of its analysis on the comparative 
design, procurement, and life-cycle operation and support costs of building four designs vs. a smaller 
number of designs, so that the subcommittee, as a matter of due diligence, can examine the Coast Guard’s 
analysis of this issue. 
                                                 
26 Source: Telephone conversation between CRS and NOAA September 28, 2018. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
12 
Multiple-Ship Buys or Block Buy Contracting 
NOAA’s current plan is to use a series of contracts with options to procure the eight new ships.27 There 
could, for example, be four contracts (one for each design), with each contract being for the design and 
construction of one ship, with an option for building a second. This approach would preserve more 
government flexibility in deciding whether to procure a second ship to a given design, provide multiple 
bidding opportunities for shipyards interested in building the ships, and create a potential for building the 
ships in multiple shipyards, all of which policymakers may view as benefits. On the other hand, this 
approach would forego the potential savings that might be realized through multiple-ship buys (e.g., 
procuring two ships of a given design in a single year) or block buy contacting. One option the 
subcommittee may wish to consider would be to request or direct NOAA to devise and share with the 
subcommittee options (including estimates of potential savings) for making use of multiple-ship buys and 
block buy contracting while staying, as much as possible, within the level funding profile of $75 million 
per year. 
Life-Cycle Support 
NOAA has not yet begun to scope out in detail the life-cycle support plan for the eight new ships—that 
work, NOAA officials stated, may start a couple of years from now. 28 One option the subcommittee may 
wish to consider would be to request that NOAA keep the subcommittee apprised of its efforts to develop 
a life-cycle support plan for the ships. 
 
Chairman Sullivan, this concludes my statement. Thank you again for the opportunity to testify, and I will 
be pleased to respond to any questions the subcommittee may have. 
                                                 
27 Source: Telephone conversation between CRS and NOAA September 28, 2018. 
28 Source: Telephone conversation between CRS and NOAA September 28, 2018. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
13 
Appendix A. Biography—Ronald O’Rourke 
Mr. O'Rourke is a Phi Beta Kappa graduate of the Johns Hopkins University, from which he received his 
B.A. in international studies, and a valedictorian graduate of the University's Paul Nitze School of 
Advanced International Studies, where he received his M.A. in the same field. 
Since 1984, Mr. O'Rourke has worked as a naval analyst for CRS. He has written many reports for 
Congress on various issues relating to the Navy, the Coast Guard, defense acquisition, China’s naval 
forces and maritime territorial disputes, the Arctic, the international security environment, and the U.S. 
role in the world. He regularly briefs Members of Congress and Congressional staffers, and has testified 
before Congressional committees on many occasions. 
In 1996, he received a Distinguished Service Award from the Library of Congress for his service to 
Congress on naval issues. 
In 2010, he was honored under the Great Federal Employees Initiative for his work on naval, strategic, 
and budgetary issues. 
In 2012, he received the CRS Director’s Award for his outstanding contributions in support of the 
Congress and the mission of CRS. 
In 2017, he received the Superior Public Service Award from the Navy for service in a variety of roles at 
CRS while providing invaluable analysis of tremendous benefit to the Navy for a period spanning 
decades. 
Mr. O'Rourke is the author of several journal articles on naval issues, and is a past winner of the U.S. 
Naval Institute's Arleigh Burke essay contest. He has given presentations on naval, Coast Guard, and 
strategy issues to a variety of U.S. and international audiences in government, industry, and academia. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
14 
Appendix B. A Summary of Some Acquisition Lessons 
Learned for Government Shipbuilding 
This appendix presents a general summary of lessons learned in government shipbuilding, reflecting 
comments made repeatedly by various sources over the years.29 These lessons learned include the 
following: 
  
At the outset, get the operational requirements for the program right. Properly 
identify the program’s operational requirements at the outset. Manage risk by not trying 
to do too much in terms of the program’s operational requirements, and perhaps seek a 
so-called 70%-to-80% solution (i.e., a design that is intended to provide 70%-80% of 
desired or ideal capabilities). Achieve a realistic balance up front between operational 
requirements, risks, and estimated costs. 
  
Impose cost discipline up front. Use realistic price estimates, and consider not only 
development and procurement costs, but life-cycle operation and support (O&S) costs. 
  
Employ competition where possible in the awarding of design and construction 
contracts. 
  
Use a contract type that is appropriate for the amount of risk involved, and structure 
its terms to align incentives with desired outcomes. 
  
Minimize design/construction concurrency by developing the design to a high level of 
completion before starting construction and by resisting changes in requirements (and 
consequent design changes) during construction. 
  
Properly supervise construction work. Maintain an adequate number of properly 
trained Supervisor of Shipbuilding (SUPSHIP) personnel. 
  
Provide stability for industry, in part by using, where possible, multiyear procurement 
(MYP) or block buy contracting. 
  
Maintain a capable government acquisition workforce that understands what it is 
buying, as well as the above points. 
Identifying these lessons is arguably not the hard part—most if not all these points have been cited for 
years. The hard part, arguably, is living up to them without letting circumstances lead program-execution 
efforts away from these guidelines. 
                                                 
29 This appendix is adapted from Appendix J of CRS Report RL32665, 
Navy Force Structure and Shipbuilding Plans: 
Background and Issues for Congress, by Ronald O'Rourke. See also Government Accountability Office, 
Navy Shipbuilding[:] 
Past Performance Provides Valuable Lessons for Future Investments, GAO-18-238SP, June 2018, 36 pp. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
15 
Appendix C. Some Considerations Relating to 
Warranties in Government Shipbuilding and Other 
Government Acquisition 
This appendix presents some considerations relating to warranties in shipbuilding and other defense 
acquisition.30 
In discussions of government shipbuilding, one question that sometimes arises is whether including a 
warranty in a shipbuilding contract is preferable to not including one.  The question can arise, for 
example, in connection with a GAO finding that “the Navy structures shipbuilding contracts so that it 
pays shipbuilders to build ships as part of the construction process and then pays the same shipbuilders a 
second time to repair the ship when construction defects are discovered.”31 
Including a warranty in a shipbuilding contract (or a contract for building some other kind of end item), 
while potentially valuable, might not always be preferable to not including one—it depends on the 
circumstances of the acquisition, and it is not necessarily a valid criticism of an acquisition program to 
state that it is using a contract that does not include a warranty (or a weaker form of a warranty rather than 
a stronger one). 
Including a warranty generally shifts to the contractor the risk of having to pay for fixing problems with 
earlier work. Although that in itself could be deemed desirable from the government’s standpoint, a 
contractor negotiating a contract that will have a warranty will incorporate that risk into its price, and 
depending on how much the contractor might charge for doing that, it is possible that the government 
could wind up paying more in total for acquiring the item (including fixing problems with earlier work on 
that item) than it would have under a contract without a warranty. 
When a warranty is not included in the contract and the government pays later on to fix problems with 
earlier work, those payments can be very visible, which can invite critical comments from observers. But 
that does not mean that including a warranty in the contract somehow frees the government from paying 
to fix problems with earlier work. In a contract that includes a warranty, the government will indeed pay 
something to fix problems with earlier work—but it will make the payment in the less-visible (but still 
very real) form of the up-front charge for including the warranty, and that charge might be more than what 
it would have cost the government, under a contract without a warranty, to pay later on for fixing those 
problems. 
From a cost standpoint, including a warranty in the contract might or might not be preferable, depending 
on the risk that there will be problems with earlier work that need fixing, the potential cost of fixing such 
problems, and the cost of including the warranty in the contract. The point is that the goal of avoiding 
highly visible payments for fixing problems with earlier work and the goal of minimizing the cost to the 
government of fixing problems with earlier work are separate and different goals, and that pursuing the 
first goal can sometimes work against achieving the second goal.32 
                                                 
30 This appendix is adapted from Appendix K of CRS Report RL32665, 
Navy Force Structure and Shipbuilding Plans: 
Background and Issues for Congress, by Ronald O'Rourke. 
31 See Government Accountability Office, 
Navy Shipbuilding[:] Past Performance Provides Valuable Lessons for Future 
Investments, GAO-18-238SP, June 2018, p. 21. A graphic on page 21 shows a GAO finding that the government was financially 
responsible for shipbuilder deficiencies in 96% of the cases examined by GAO, and that the shipbuilder was financially 
responsible for shipbuilder deficiencies in 4% of the cases. 
32 It can also be noted that the country’s two largest builders of Navy ships—General Dynamics (GD) and Huntington Ingalls 
Industries (HII)—derive about 60% and 96%, respectively, of their revenues from U.S. government work. (See General 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
16 
The Department of Defense’s guide on the use of warranties states the following: 
Federal Acquisition Regulation (FAR) 46.7 states that  “the use of warranties is not mandatory.” 
However,  if  the  benefits  to  be  derived  from  the  warranty  are  commensurate  with  the  cost  of  the 
warranty,  the  CO  [contracting  officer]  should  consider  placing  it  in  the  contract.  In  determining 
whether a warranty is appropriate for a specific acquisition, FAR Subpart 46.703 requires the CO 
to  consider  the  nature  and  use  of  the  supplies  and  services,  the  cost,  the  administration  and 
enforcement, trade practices, and reduced requirements. The rationale for using a warranty should 
be documented in the contract file.... 
In determining the value of a warranty, a CBA [cost-benefit analysis] is used to measure the life 
cycle  costs  of  the  system  with  and  without  the  warranty.  A  CBA  is  required  to  determine  if  the 
warranty will be cost beneficial. CBA is an economic analysis, which basically compares the Life 
Cycle Costs (LCC) of the system with and without the warranty to determine if warranty coverage 
will improve the LCCs. In general, five key factors will drive the results of the CBA: cost of the 
warranty  +  cost  of  warranty  administration  +  compatibility  with  total  program  efforts  +  cost  of 
overlap  with  Contractor  support  +  intangible  savings.  Effective  warranties  integrate  reliability, 
maintainability,  supportability,  availability,  and  life-cycle  costs.  Decision  factors  that  must  be 
evaluated include the state of the weapon system technology, the size of the warranted population, 
the  likelihood  that  field  performance  requirements  can  be  achieved,  and  the  warranty  period  of 
performance.33 
                                                 
Dynamics, 
2016 Annual Report, page 9 of Form 10-K [PDF page 15 of 88]) and Huntington Ingalls Industries, 
2016 Annual 
Report, page 5 of Form 10-K [PDF page 19 of 134]). Thus, even if a warranty in a shipbuilding contract with one of these firms 
were to somehow mean that the government did not have pay under the terms of that contract—either up front or later on—for 
fixing problems with earlier work done under that contract, there would still be a question as to whether the government would 
nevertheless wind up eventually paying much of that cost as part of the price of one or more future contracts the government may 
have that firm. 
33 Department of Defense, 
Department of Defense Warranty Guide, Version 1.0, September 2009, accessed July 13, 2017, at 
https://www.acq.osd.mil/dpap/pdi/uid/docs/departmentofdefensewarrantyguide[1].doc. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
17 
Appendix D. Some Considerations Relating to Avoiding 
Procurement Cost Growth vs. Minimizing Procurement 
Costs 
This appendix presents some considerations relating to avoiding procurement cost growth vs. minimizing 
procurement costs in shipbuilding and other government acquisition.34 
The affordability challenge posed by the Navy’s shipbuilding plans can reinforce the strong oversight 
focus on preventing or minimizing procurement cost growth in Navy shipbuilding programs, which is one 
expression of a strong oversight focus on preventing or minimizing cost growth in DOD acquisition 
programs in general. This oversight focus may reflect in part an assumption that avoiding or minimizing 
procurement cost growth is always synonymous with minimizing procurement cost. It is important to 
note, however, that as paradoxical as it may seem, avoiding or minimizing procurement cost growth is not 
always synonymous with minimizing procurement cost, and that a sustained, singular focus on avoiding 
or minimizing procurement cost growth might sometimes lead to higher procurement costs for the 
government. 
How could this be? Consider the example of a design for the lead ship of a new class of Navy ships. The 
construction cost of this new design is uncertain, but is estimated to be likely somewhere between Point A 
(a minimum possible figure) and Point D (a maximum possible figure). (Point D, in other words, would 
represent a cost estimate with a 100% confidence factor, meaning there is a 100% chance that the cost 
would come in at or below that level.) If the Navy wanted to avoid cost growth on this ship, it could 
simply set the ship’s procurement cost at Point D. Industry would likely be happy with this arrangement, 
and there likely would be no cost growth on the ship. 
The alternative strategy open to the Navy is to set the ship’s target procurement cost at some figure 
between Points A and D—call it Point B—and then use that more challenging target cost to place pressure 
on industry to sharpen its pencils so as to find ways to produce the ship at that lower cost. (Navy officials 
sometimes refer to this as “pressurizing” industry.) In this example, it might turn out that industry efforts 
to reduce production costs are not successful enough to build the ship at the Point B cost. As a result, the 
ship experiences one or more rounds of procurement cost growth, and the ship’s procurement cost rises 
over time from Point B to some higher figure—call it Point C. 
Here is the rub: Point C, in spite of incorporating one or more rounds of cost growth, might nevertheless 
turn out to be lower than Point D, because Point C reflected efforts by the shipbuilder to find ways to 
reduce production costs that the shipbuilder might have put less energy into pursuing if the Navy had 
simply set the ship’s procurement cost initially at Point D. 
Setting the ship’s cost at Point D, in other words, may eliminate the risk of cost growth on the ship, but 
does so at the expense of creating a risk of the government paying more for the ship than was actually 
necessary. DOD could avoid cost growth on new procurement programs starting tomorrow by simply 
setting costs for those programs at each program’s equivalent of Point D. But as a result of this strategy, 
DOD could well wind up leaving money on the table in some instances—of not, in other words, 
minimizing procurement costs. 
DOD does not have to set a cost precisely at Point D to create a potential risk in this regard. A risk of 
leaving money on the table, for example, is a possible downside of requiring DOD to budget for its 
                                                 
34 This appendix is adapted from Appendix L of CRS Report RL32665, 
Navy Force Structure and Shipbuilding Plans: 
Background and Issues for Congress, by Ronald O'Rourke. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
18 
acquisition programs at something like an 80% confidence factor—an approach that some observers have 
recommended—because a cost at the 80% confidence factor is a cost that is likely fairly close to Point D. 
Procurement cost growth is often embarrassing for DOD and industry, and can damage their credibility in 
connection with future procurement efforts. Procurement cost growth can also disrupt congressional 
budgeting by requiring additional appropriations to pay for something Congress thought it had fully 
funded in a prior year. For this reason, there is a legitimate public policy value to pursuing a goal of 
having less rather than more procurement cost growth. 
Procurement cost growth, however, can sometimes be in part the result of DOD efforts to use lower initial 
cost targets as a means of pressuring industry to reduce production costs—efforts that, notwithstanding 
the cost growth, might be partially successful. A sustained, singular focus on avoiding or minimizing cost 
growth, and of punishing DOD for all instances of cost growth, could discourage DOD from using lower 
initial cost targets as a means of pressurizing industry, which could deprive DOD of a tool for controlling 
procurement costs. 
The point here is not to excuse away cost growth, because cost growth can occur in a program for reasons 
other than DOD’s attempt to pressurize industry. Nor is the point to abandon the goal of seeking lower 
rather than higher procurement cost growth, because, as noted above, there is a legitimate public policy 
value in pursuing this goal. The point, rather, is to recognize that this goal is not always synonymous with 
minimizing procurement cost, and that a possibility of some amount of cost growth might be expected as 
part of an optimal government strategy for minimizing procurement cost. Recognizing that the goals of 
seeking lower rather than higher cost growth and of minimizing procurement cost can sometimes be in 
tension with one another can lead to an approach that takes both goals into consideration. In contrast, an 
approach that is instead characterized by a sustained, singular focus on avoiding and minimizing cost 
growth may appear virtuous, but in the end may wind up costing the government more. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
19 
Appendix E. NASEM Report Recommendation for 
Building Heavy and Medium Polar Icebreakers to a 
Common Design 
Regarding its proposal to build heavy and medium polar icebreakers to a common design, the July 2017 
NASEM report stated (emphasis as in original): 
2. Recommendation: The United States Congress should fund the construction of four polar 
icebreakers of common design that would be owned and operated by the United States Coast 
Guard (USCG). 
The current Department of Homeland Security (DHS) Mission Need Statement... contemplates a 
combination of medium and heavy icebreakers. The committee’s recommendation is for a single 
class of polar icebreaker with heavy icebreaking capability. Proceeding  with a single class means 
that only one design will be needed, which will provide cost savings. The committee has found that 
the fourth heavy icebreaker could be built for a lower cost than the lead ship of a medium icebreaker 
class.... 
The DHS Mission Need Statement contemplated a total fleet of “potentially” up to six ships of two 
classes—three heavy and three medium icebreakers. Details appear in the High Latitude Mission 
Analysis Report. The Mission Need Statement indicated that to fulfill its statutory missions, USCG 
required three heavy and three medium icebreakers; each vessel would have a single crew and would 
homeport in Seattle. The committee’s analysis indicated that four heavy icebreakers will meet the 
statutory mission needs gap identified by DHS for the lowest cost.... 
4. Finding: In developing its independent concept designs and cost estimates, the committee 
determined  that  the  costs  estimated  by  USCG  for  the  heavy  icebreaker  are  reasonable. 
However, the committee believes that the costs of medium icebreakers identified in the High 
Latitude Mission Analysis Report are significantly underestimated.... 
Although USCG has not yet developed the operational requirements document for a medium polar 
icebreaker, the committee was able to apply the known principal characteristics of the USCG Cutter 
Healy  to  estimate  the  scope  of  work  and  cost  of  a  similar  medium  icebreaker.  The  committee 
estimates that a first-of-class medium icebreaker will cost approximately $786 million. The fourth 
ship  of  the  heavy  icebreaker  series  is  estimated  to  cost  $692  million.  Designing  a  medium-class 
polar icebreaker in a second shipyard would incur the estimated engineering, design, and planning 
costs of $126 million and would forgo learning from the first three ships; the learning curve would 
be restarted with the first medium design. Costs of building the fourth heavy icebreaker would be 
less than the costs of designing and building a first-of-class medium icebreaker.... 
6. Recommendation: USCG should ensure that the common polar icebreaker design is science-
ready and that one of the ships has full science capability. 
All four proposed ships would be designed as “science-ready,” which will be more cost-effective 
when  one  of  the  four  ships—most  likely  the  fourth—is  made  fully  science  capable.  Including 
science readiness in the common polar icebreaker design is the most cost-effective way of fulfilling 
both the USCG’s polar missions and the nation’s scientific research polar icebreaker needs.... The 
incremental costs of a science-ready design for each of the four ships ($10 million to $20 million 
per ship) and of full science  capability for one of the ships at the initial build (an additional $20 
million to $30 million) are less than the independent design and build cost of a dedicated research 
medium  icebreaker....  In  briefings  at  its  first  meeting,  the  committee  learned  that  the  National 
Science Foundation and other agencies do not have budgets to support full-time heavy icebreaker 
access  or  the  incremental  cost  of  design,  even  though  their  science  programs  may  require  this 
capability. Given the small incremental cost, the committee believes that the science capability cited 
above should be included in the acquisition costs.
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
20 
 
Science-ready  design  includes  critical  elements  that  cannot  be  retrofitted  cost-effectively  into  an 
existing ship and that should be incorporated in the initial design and build. Among these elements 
are structural supports, appropriate interior and exterior spaces, flexible accommodation spaces that 
can embark up to 50 science personnel, a hull design that accommodates multiple transducers and 
minimizes  bubble  sweep  while  optimizing  icebreaking  capability,  machinery  arrangements  and 
noise dampening to mitigate interference with sonar transducers, and weight and stability latitudes 
to  allow  installation  of  scientific  equipment.  Such  a  design  will  enable  any  of  the  ships  to  be 
retrofitted for full science capability in the future, if necessary.... 
Within the time frame of the recommended build sequence, the United States will require a science-
capable polar icebreaker to replace the  science capabilities  of the Healy  upon  her retirement. To 
fulfill this need, one of the heavy polar icebreakers would be procured at the initial build with full 
science capability; the ability to fulfill other USCG missions would be retained. The ship would be 
outfitted with oceanographic overboarding equipment and instrumentation and facilities comparable 
with  those  of  modern  oceanographic  research  vessels.  Some  basic  scientific  capability,  such  as 
hydrographic  mapping  sonar,  should  be  acquired  at  the  time  of  the  build  of  each  ship  so  that 
environmental data that are essential in fulfilling USCG polar missions can be collected.35 
 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff 
to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of 
Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of 
information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. 
CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United 
States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, 
as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the 
permission of the copyright holder if you wish to copy or otherwise use copyrighted material. 
 
                                                 
35 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation Research 
Board, 
Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with cover letter dated July 
11, 2017, pp. 2, 4-6. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
TE10029