Statement of 
Ronald O'Rourke 
Specialist in Naval Affairs 
Before 
Committee on Armed Services 
Subcommittee on Oversight and Investigations 
U.S. House of Representatives 
Hearing on 
Oversight Review of the U.S. Navy’s Littoral 
Combat Ship (LCS) Program 
December 8, 2016 
Congressional Research Service 
https://crsreports.congress.gov 
TE10013 
 
  
 
Congressional Research Service 
1 
Chairwoman Hartzler, Ranking Member Speier, distinguished members of the subcommittee, thank you 
for the opportunity to appear before you today to discuss the Navy’s Littoral Combat Ship/Frigate 
(LCS/Frigate) program, a program that I have tracked for CRS since its inception 15 years ago.1 In my 32 
years as a naval issues analyst for CRS, no program has been more complex to track, or has posed more 
potential oversight issues for Congress, than the LCS program. 
A Program at a Crossroads for Multiple Reasons 
The LCS/Frigate program is at a crossroads not only because of the Navy’s proposal to shift from 
production of the baseline LCS design to production of the frigate variant of the LCS, but also because of 
three significant additional factors: 
  the rapidly shifting international security environment, which could alter requirements for 
U.S. naval forces, including small surface combatants such as the frigate variant of the 
LCS; 
  the possibility that the incoming Trump administration might make significant changes in 
U.S. foreign and security policy—changes that might further alter requirements for U.S. 
naval forces, including small surface combatants such as the frigate variant of the LCS; 
and 
  the Trump campaign organization’s announced objective of building the Navy toward a 
goal of 350 ships, rather than the Navy’s current 308-ship force-level objective, which if 
adopted as policy by the incoming Trump administration, could alter the Navy’s desired 
numbers of small surface combatants such as the frigate variant of the LCS. 
These three factors—particularly the rapidly shifting international security environment and possibility of 
significant changes in U.S. foreign and security policy—profoundly affect the circumstances for 
conducting oversight of U.S. defense programs, including the LCS/Frigate program. They introduce 
oversight issues and considerations that differ from those that have characterized oversight of U.S. 
defense programs, including the LCS/Frigate program, in recent years. In short, for U.S. defense 
programs, including the LCS/Frigate program, the ground beneath us is shifting in a fundamental way, 
complicating the task of conducting oversight. A number of the comments that follow reflect this 
challenging situation. 
Issue for Congress 
Regarding the future of the LCS/Frigate program, the Government Accountability Office (GAO) has 
framed the question as follows: “A more basic oversight question today is whether a ship that costs twice 
as much [as originally estimated] yet delivers less capability than planned warrants an additional 
investment of nearly $14 billion.”2 That is one way to frame the question. Another would be: “What 
capability gaps will the Navy have in coming years, what are the likely costs and capabilities of the 
frigate variant of the LCS, and is the Navy’s proposal for procuring the frigate variant of the LCS 
                                                 
1 See, for example, the current CRS report on the program—CRS Report RL33741, 
Navy Littoral Combat Ship (LCS)/Frigate 
Program: Background and Issues for Congress, by Ronald O'Rourke—as well as two earlier CRS reports on the program, CRS 
Report RL32109, 
Navy DDG-1000 (DD(X)), CG(X), and LCS Ship Acquisition Programs: Oversight Issues and Options for 
Congress, by Ronald O’Rourke (this report now focuses on the DDG-51 and DDG-1000 destroyer programs), and CRS Report 
RS21305, 
Navy Littoral Combat Ship (LCS): Background and Issues for Congress, by Ronald O’Rourke. 
2 Government Accountability Office, 
Littoral Combat Ship Program: Congress Faced with Critical Acquisition Decisions, GAO-
17-262T, December 1, 2016 (Testimony Before the Committee on Armed Services, U.S. Senate, Statement of Paul L. Francis, 
Managing Director, Acquisition and Sourcing Management), summary page. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 14 
Congressional Research Service 
2 
consequently the most cost-effective approach for addressing those capability gaps?” These are not the 
only two ways of framing the question. 
Analytical Foundation 
A key oversight issue for the Navy’s proposal for procuring the frigate variant of the LCS concerns its 
analytical foundation. The question of a program’s analytical foundation is not a mere academic matter. 
Rather, it gets to whether the service has a rigorously formed and compelling basis for what it is 
proposing to do. In this case, the service (the Navy) is proposing to build a certain number of LCS 
variants (twelve), to a certain design (the currently envisioned frigate design), at a certain annual rate (as 
shown in the Navy’s shipbuilding plan), using a certain acquisition strategy (a single shipyard chosen in a 
down select between the two current LCS shipyards). 
Some observers might refer to a program’s analytical foundation as its business case, although that term 
can also be used to mean other things. Creating a rigorous analytical foundation involves performing 
disciplined, structured analyses. Such analyses may either confirm intuitions and subjective judgments 
that policymakers and uniformed officials may have about a proposed program, or instead produce 
unanticipated or counterintuitive results that challenge those intuitions and judgments. Indeed, a major 
reason for performing rigorous analyses is to uncover unanticipated or counterintuitive results. Another 
major reason is to provide the service with a strong case for convincing others about the merits of the 
service’s proposed program. 
As a result of how the LCS/Frigate program was restructured twice in less than two years at the direction 
of two Secretaries of Defense, the Navy’s proposal for procuring the frigate variant of the LCS now 
appears to have three potential weaknesses in its analytical foundation: 
  The first and second apparent potential weaknesses, which arise from the absence of an 
analytically rigorous capability gap analysis (what might also be called a mission-need 
analysis) and the absence of an analytically rigorous analysis of multiple concepts (an 
analysis of broadly different potential approaches for filling the identified capability 
gaps), resulted from the way in which then-Secretary of Defense Hagel directed the 
program’s first restructuring in 2014. In short, Secretary Hagel’s direction to the Navy in 
2014 appears to have left the Navy with little opportunity to perform these two analyses. 
  The third apparent potential weakness concerns the absence of a detailed analytical 
foundation for the decision by Secretary of Defense Carter in the program’s second 
restructuring in 2015 to reduce planned procurement in the LCS/Frigate program from a 
total of 52 ships to 40 ships, resulting in a planned procurement of 12 frigate variants 
(and 28 baseline LCSs), rather than 20 frigate variants (and 32 baseline and transitional 
LCSs). 
Although the 2014 restructuring of the program left the Navy with little opportunity to perform an 
analytically rigorous capability gap analysis and an analytically rigorous analysis of multiple concepts, 
the Navy did perform an analytically rigorous analysis of alternatives (AoA), which is the third study that 
would follow a capability gap analysis and an analysis of multiple concepts. (For further details on the 
above situation, se
e Appendix A of this statement, which is adapted from the CRS report on the 
LCS/Frigate program.) 
The fact that the 2014 and 2015 restructurings of the program created these three apparent potential 
weaknesses in the program’s analytical foundation does not mean that the changes to the program made in 
these two restructurings were wrong—they might very well have been the right changes to make. Nor 
does it mean that the Navy’s proposal for procuring the frigate variant of the LCS is not the most cost 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
3 
effective approach for meeting the Navy’s future needs—it might very well be the most cost effective 
approach.  
These three apparent potential weaknesses do, however, reduce the Navy’s ability to demonstrate to 
others that its proposal for procuring the frigate variant of the LCS is the most cost effective approach. 
They also create additional room for skeptics to question the Navy’s proposal using arguments that might 
themselves lack a firm analytical foundation. A situation where there are weaknesses in the service’s 
analytical foundation for defending its proposal, and parallel weaknesses in the analytical foundation of 
the skeptics’ arguments for questioning the service’s proposal, can lead to a sprawling and disorganized 
debate that can make it difficult to keep key issues in focus and reach a well-founded conclusion 
regarding the merits of the service’s proposal. 
As I discuss in the CRS report on the LCS/Frigate program, the Navy 15 years ago did not perform a 
rigorous analysis of multiple concepts prior to announcing the original version of the LCS program. The 
Navy acknowledged this in testimony to the then-Projection Forces subcommittee of the House Armed 
Services Committee in April 2003. This created a weakness in the analytical foundation of the original 
version of the program that can be viewed as the root cause of some (perhaps much) of the controversy 
over the program’s cost effectiveness that continued from the program’s inception until its 2014 
restructuring. 
The rapidly shifting international security environment and the possibility of significant changes in U.S. 
foreign and security policy compound the three existing apparent potential weaknesses in the analytical 
foundation for the Navy’s proposal for procuring the frigate variant of the LCS. This compounded 
situation does not prove that the Navy’s proposal is not the most cost effect approach for meeting the 
Navy’s future needs. It might very well be the most cost effective approach. But as a result of these 
compounded weaknesses, the Navy now has less of a basis for being certain that its proposal is the most 
cost effective approach, and less ability to demonstrate this compellingly to others. 
The rapidly shifting international security environment and the possibility of significant changes in U.S. 
foreign and security policy also, however, create a fresh opportunity for the Navy to create a new 
analytical foundation for the effort that is both rigorous and fully up to date. Following the development 
of an updated national military strategy that reflects the incoming Trump administration’s foreign and 
security policy goals, the Navy would have an updated basis for performing a rigorous capability gap 
analysis, a rigorous analysis of multiple concepts, and a rigorous new AoA for procuring small surface 
combatants. These analyses would take some time to perform, but performing them would not prevent 
some variant of the LCS from being procured in FY2017 and FY2018 while the analyses were being 
done. 
The LCS/Frigate program is by no means the only DOD program affected by the situation created by the 
rapidly shifting international security environment and the possibility of significant changes in U.S. 
foreign and security policy. But it is one of the programs that are affected. 
The shifting international security environment involves the ending of the post-Cold War era that first 
took shape in the late 1980s and early 1990s, and its replacement by a new international security situation 
featuring renewed great power competition. As such, the shifting of the international security environment 
can be viewed as a once-in-a-generation event. The changes in U.S. foreign and security policy that some 
observers, noting comments made on the campaign trail, believe might be implemented by the incoming 
Trump administration would, in the view of some of these observers, have the potential of being the 
largest changes since World War II. The combination of an approximately 25-year event and (in the view 
of some observers) a potential 70-year event, respectively, would create a situation for conducting 
oversight of defense programs that in fundamental ways would not be business as usual. A key current 
challenge in conducting oversight of DOD programs, including the LCS/Frigate program, is to be fully 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 19 
Congressional Research Service 
4 
cognizant of how current circumstances are shifting the ground under our feet and potentially changing 
familiar oversight frameworks. 
Program Quantity 
As part of its vision for national defense, the Trump campaign organization announced an objective of 
“Rebuild[ing] the U.S. Navy toward a goal of 350 ships, as the bipartisan [2014] National Defense Panel 
[NDP] has recommended.”3 The Trump campaign organization did not specify the composition of this 
350-ship fleet. 
A CRS report on the idea of a bigger Navy provides a notional composition for a fleet of about 350-
ships.4 This notional fleet, which happens to total 349 ships, is not based on any analysis of Navy mission 
requirements; it was derived by simply scaling up the Navy’s 308-ship force structure proportionately 
(while holding the planned number of ballistic missile submarines constant) and adjusting some of the 
resulting numbers so that they would reflect numbers for certain categories of ships that have appeared in 
Navy plans in recent years for fleets of 300 to 400 ships. 
This notional 349-ship fleet may be of value as a point of departure for those interested in discussing the 
idea of a 350-ship fleet. It may also be of value as a tool for quickly understanding how other proposals 
for 350-ship fleets depart from a proportional scaling up of the Navy’s 308-ship fleet. And it can serve as 
a placeholder, pending a proposal from the incoming Trump administration that provides a detailed 
composition of its desired 350-ship fleet. 
The notional 349-ship fleet presented in the CRS report includes 56 small surface combatants—four more 
than the 52 small surface combatants included in the Navy’s 308-ship force-level objective. The CRS 
report shows a notional procurement profile for achieving a force level of 56 small surface combatants 
over a 30-year shipbuilding period. This notional profile is shown i
n Appendix B of this statement. 
Compared to the Navy’s FY2017 30-year shipbuilding plan, this notional profile would add 17 small 
surface combatants in the period FY2017-FY2025 and remove five small surface combatants in the period 
FY2029-FY2035, for a net addition of 12 small surface combatants through FY2035. 
A key oversight issue regarding an objective of building the Navy toward a goal of 350 ships is that there 
currently is no rigorous, up-to-date analytical basis for a fleet of 350 ships. As noted above, the Trump 
campaign organization’s announced objective regarding a 350-ship fleet references the recommendation 
of the 2014 NDP. As discussed in the CRS report on the idea of a bigger Navy, the 2014 NDP, in making 
its recommendation, referenced DOD’s 1993 Bottom-Up Review (BUR), a major review that reshaped 
U.S. defense strategy, plans, and programs in response to the end of the Cold War and the start of the 
post-Cold War era.5 
The analytical foundation of the 346-ship fleet called for in the 1993 BUR reflected the international 
security environment of the early post-Cold War era, as well as Navy ship types, technologies, operational 
concepts, basing arrangements, and deployment cycles of that time, all of which have changed over the 
                                                 
3 Source: National Defense, Donald J. Trump’s Vision, accessed December 5, 2016, at: 
https://www.donaldjtrump.com/policies/national-defense. 
4 CRS Report R44635, 
Navy Force Structure: A Bigger Fleet? Background and Issues for Congress, by Ronald O'Rourke. 
5 For more on the 1993 BUR, see Department of Defense, 
Report on the Bottom-Up Review, Les Aspin, Secretary of Defense, 
October 1993, 109 pp. See also CRS Report R43838, 
A Shift in the International Security Environment: Potential Implications 
for Defense—Issues for Congress, by Ronald O'Rourke. See also CRS Report 93-839 F, 
Defense Department Bottom-Up Review: 
Results and Issues, October 6, 1993, 6 pp., by Edward F. Bruner, and CRS Report 93-627 F, 
Defense Department Bottom-Up 
Review: The Process, July 2, 1993, 9 pp., by Cedric W. Tarr, Jr. (both out of print but available to congressional clients upon 
request from the author of this testimony). 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 6 

Congressional Research Service 
5 
past 20-plus years. The analytical foundation for the 1993 BUR’s 346-ship fleet consequently is now out 
of date. (It can also be noted that a detailed composition of the 1993 BUR’s 346-ship fleet was not 
presented to Congress; when the Navy eventually provided Congress with a detailed composition of its 
planned fleet, the numbers added to a total of 331 to 341 ships rather than 346.6) 
The absence of a rigorous, up-to-date analytical basis for a fleet of 350 ships doesn’t prove that a 350-ship 
fleet would be inappropriate for meeting the Navy’s future mission demands. But the case for a 350-ship 
fleet would be more compelling if it had a rigorous, up-to-date analytical basis. The Navy’s Force 
Structure Analysis (FSA) process provides a mechanism for creating a rigorous, up-to-date analytical 
basis for the Navy’s force-level objectives. The FSA takes inputs from U.S. regional combatant 
commanders for desired Navy capabilities for warfighting and day-to-day forward-deployed presence, 
and then translates those desired capabilities into ship quantities based on ship capabilities, basing 
arrangements, and deployment cycles
. Figure 1 summarizes the FSA process. 
Figure 1. Navy Force Structure Analysis (FSA) Process 
 
Source: Navy briefing on Navy force-level requirements, October 11, 2013. 
The development of an updated national military strategy reflecting the foreign policy and security goals 
of the incoming Trump administration would permit U.S. regional combatant commanders to provide 
                                                 
6 See Table B-1 in CRS Report RL32665, 
Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, 
by Ronald O'Rourke.  
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 19 
Congressional Research Service 
6 
updated inputs to the FSA concerning their desired Navy capabilities for warfighting and day-to-day 
forward-deployed presence. The FSA could then translate those updated inputs into updated desired 
quantities for various ships types, including small surface combatants such as baseline LCSs and frigate-
variant LCSs. The result could be a force-level goal for a fleet of about 350 ships, less than 350 ships, or 
more than 350 ships. 
Down Select 
Another oversight issue concerning the Navy’s proposal for procuring the frigate variant of the LCS 
concerns the plan (directed by Secretary of Defense Carter as part of the program’s 2015 restructuring) to 
conduct a down select between the two LCS designs and build all the frigate-variant LCSs to a single 
design. This is generally understood as meaning that the 12 planned frigate-variant LCSs would all be 
built by a single shipyard. 
As shown i
n Appendix B, building up to a notional force of 56 small surface combatants over the next 
several years could notionally involve increasing the small combatant procurement rate to three or four 
ships per year during the period FY2017-FY2025. A similar profile might result from building up to a 
notional force of 52 small surface combatants—the number included in the Navy’s 308-ship force-level 
objective. In terms of industrial base capacity, it might be easier to execute a procurement rate of three or 
four LCS variants per year with two LCS builders rather than one. 
As discussed in the next section, whether the 12 planned frigate-variant LCSs would be acquired via 
annual contracting or block buy contracting is not yet settled. If the ships are acquired with annual 
contracting, then depending on the annual procurement rate, maintaining two LCS builders might enhance 
the Navy’s ability to use competition effectively in the procurement of all 12 ships. This might be true 
even if the procurement rate were no more than two ships per year. Under that scenario, the Navy could 
allocate one ship per year to each shipyard and use Profit Related to Offer (PRO) bidding (i.e., 
competition for profit) to generate competitive leverage for the government.7 Conversely, conducting a 
down select to a single shipyard and using annual contracting could limit the government’s ability to use 
competitive pressures in procuring frigate-variant LCSs, potentially increasing procurement costs for 
those ships. 
Block Buy Contracting 
As mentioned above, another oversight question concerns whether to use annual contracting or block buy 
contracting for procuring the frigate variants of the LCS. Annual contracting preserves flexibility for 
Congress regarding whether and when to procure follow-on units in an ongoing procurement program, 
while multiyear contracting in the form of block buy contracting or multiyear procurement (MYP) 
reduces that flexibility in return for reducing the procurement costs of the units being procured.8 
                                                 
7 For more on PRO bidding, see Statement of Ronald O’Rourke, Specialist in Naval Affairs, Congressional Research Service, 
Before the House Armed Services Committee on Case Studies in DOD Acquisition: Finding What Works, June 24, 2014, p. 7. 
8 Stated more fully, from a congressional perspective, trade-offs in using block buy contracting include the following: 
 
reduced congressional control over year-to-year spending, and tying the hands of future Congresses; 
 
reduced flexibility for making changes in acquisition programs in response to unforeseen changes in strategic or 
budgetary circumstances (which can cause any needed funding reductions to fall more heavily on acquisition programs 
not covered by multiyear contracts); 
 
a potential need to shift funding from later fiscal years to earlier fiscal years to fund economic order quantity (EOQ) 
purchases (i.e., up-front batch purchases) of components; 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
7 
One question that sometimes arises in connection with the LCS/Frigate program, which has used block 
buy contracting for units 5 through 26, is the relationship between the past cost growth in the procurement 
of LCSs and the use of block buy contracts to procure LCSs. The relationship can be summarized as 
follows: The growth in the procurement cost of LCSs came primarily, if not entirely, before the use of 
block buy contracts. Procurement costs under the block buy contracts appear to have stabilized. The block 
buy contracts are fixed price incentive contracts, which limits the government’s exposure to cost growth. 
The block buy contracts may have reduced LCS procurement costs, perhaps by upwards of about five 
percent, due to cost reductions at shipyards that are possible when shipyards, viewing a commitment by 
the government to procure ships over a period of several years, have the confidence in future business 
needed to make investments in their work force and capital plant that can better optimize the shipyards for 
production of the ships covered by the contract. 
Another question is whether the use of block buy contracts would reduce Congress’ ability to conduct 
effective oversight of the Navy’s activities for procuring frigate variants of the LCS. In connection with 
this question, it can be noted that the LCS program has been executed under block buy contracts since 
December 2010. In the period since then, the LCS program has been a recurring topic of oversight 
questions at annual hearings on the Navy’s budget, the subject of numerous legislative provisions and 
instances of report language in annual national defense authorization acts, and the subject of multiple 
oversight reports from GAO. Additional oversight on the program has been provided in GAO’s annual 
report assessing selected DOD weapon programs, the periodically updated CRS report on the program, 
and reports from the Congressional Budget Office (CBO) that discuss potential costs for the program. 
Although the use of a block buy contract reduces the government’s flexibility regarding whether and 
when to procure follow-on units in the program, Congress and the executive branch retain the ability to 
terminate a block buy contract should circumstances dictate. A block buy contract can be written to 
exclude a termination penalty, and a block buy contract can be implemented without the use of an up-
front batch order of components intended for ships to be procured in fiscal years after the first year of the 
contract. (The block buy contracts that the Navy has used for procuring Virginia-class submarines, LCSs, 
and TAO-205 class oilers have not used up-front batch orders of components.) 
Congress or the executive branch might wish to terminate or suspend procurement of a ship class due to 
causes such as cost growth, schedule slippage, problems in production quality, or changes in the 
government’s need for the ships. Block buy contracts can be (and in the LCS program, have been) fixed 
price contracts, reducing the government’s exposure to cost growth. If one or more of the other factors 
just mentioned emerge as a problem serious enough to convince Congress or the executive branch that 
procurement of the ships should be terminated or suspended, the question is how much more difficult it 
would be to terminate or suspend procurement if the ships were being procured under a block buy 
contract rather than annual contracts. Supporters of annual contracts could argue that block buy contracts 
by design make it more difficult for the government to change its plan to procure the ships. Supporters of 
block buy contracts, while acknowledging this, might argue that the relative rarity of terminations or 
suspensions of DOD procurement programs suggests that the primary source of reluctance to terminate or 
suspend procurement arises from the fact that procurement has begun, regardless of the contract type 
being used, and that using a block buy contract might add to that reluctance in a secondary or marginal 
manner. 
                                                 
 
the risk of having to make penalty payments to shipbuilders if multiyear contracts need to be terminated due to 
unavailability of funds needed to the continue the contracts; and 
 
the risk that materials and components purchased for ships to be acquired in future years might go to waste if those 
ships are not eventually acquired. 
For more on block buy contracting, see CRS Report R41909, 
Multiyear Procurement (MYP) and Block Buy Contracting in 
Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz.  
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
8 
Another question concerns the signal that could be sent to other DOD acquisition programs by not 
agreeing to a Navy request (should the Navy make one) to use a block buy contract for procuring the 
frigate variants of the LCS. The effective cost of sending that signal might be upwards of $400 million in 
terms of savings under a block buy contract for 12 frigate-variant LCSs that would not be realized. There 
would also be a question of the signal that would be received by other DOD acquisition programs. Would 
the signal received be the (presumably) intended one that Congress will not tolerate poorly performing 
programs? Would the signal received instead be a (presumably) unintended one—that even when DOD 
and a military service take actions to restructure a program so as to avoid a recurrence of the problems 
experienced by the original version of the program, the restructured program might still be penalized for 
the problems of the original version of the program? Would the signal received be something else? 
An additional consideration concerns the relationship between the contracting approach for the frigate-
variant LCSs and the currently planned down select. As noted in the previous section, down selecting to a 
single LCS design (and consequently to a single LCS shipyard) and then using annual contracting could 
limit the government’s ability to use competitive pressures in procuring frigate-variant LCSs, potentially 
increasing procurement costs for the ships. 
Survivability 
Another oversight issue for the LCS/Frigate program concerns ship survivability, meaning the ship’s 
ability to avoid, withstand, and recover from battle damage. The issue has been a matter of debate in 
connection with both baseline LCSs and the proposed frigate-variant LCSs. 
It is important to note that in terms of oversight, the survivability issue encompasses two questions. One 
is whether tests of the ship’s survivability against its designed survivability standard accurately emulate 
threats and operating circumstances the ship might face, and whether the tests demonstrate that the ship is 
meeting its survivability design standard. The other question is whether the designed survivability 
standard itself is appropriate, given the ship’s projected uses. This is a requirements question rather than a 
test-and-evaluation question. These two questions have sometimes been conflated in discussions of the 
survivability of LCSs. 
The baseline LCS was designed to what used to be called a Level 1+ survivability standard, meaning that 
the ship was designed to something more than what used to be called Level 1 survivability standard.9 The 
choice of the Level 1+ survivability standard might be viewed as a reflection of how baseline LCSs are 
intended to perform missions previously performed by ships such as patrol combatants and mine warfare 
ships, which were designed to a Level 1 standard, as well as missions performed by frigates, which were 
designed to the higher Level 2 standard. (Ships designed to the old Level 3 standard, the Navy’s highest 
                                                 
9 In an April 2011 briefing on LCS survivability, the Navy summarized the baseline LCS’s Level 1+ survivability standard as 
follows: 
[The] LCS design includes Level 1 [survivability] plus tailored survivability enhancements (“Level 1+”), 
such as: 
– Electro-magnetic pulse (EMP) hardening 
– Individual Chemical, Biological, Radiological protection with decontamination stations 
– Shock hardening of damage control (DC) and propulsion systems 
– Redundant, automated firefighting systems 
– Select fragmentation armor 
– Ability to survive in sea state 8 
(Navy briefing on LCS survivability, April 29, 2011, slide 2.) 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
9 
survivability standard, include aircraft carriers, cruisers, and destroyers.)10 The Navy’s Level 1/2/3 
nomenclature for ship survivability standards was replaced in 2012 by a new and different framework for 
discussing surface ship survivability, but ships designed under the old Level 1/2/3 nomenclature, such as 
the baseline LCS, are still discussed in connection with the old nomenclature.11 
The frigate-variant of the LCS has some survivability improvements compared to the baseline LCS, but 
apparently not enough to qualify under the old survivability nomenclature as a ship with Level 2 
survivability. One might say that, in terms of its intended survivability standard, the frigate variant of the 
LCS under the old survivability nomenclature might be considered a Level 1++ ship. It might be possible 
to change the design of the frigate variant of the LCS to further increase its survivability. Whether such 
changes would be enough to convert the frigate variant of the LCS into a Level 2 ship under the old 
survivability nomenclature is not clear, but the changes could make the ship more expensive to procure. 
Whether the current survivability standard for the frigate variant of the LCS is appropriate is a question 
that should now be evaluated in the context of the rapidly changing international security environment 
and possible significant changes in U.S. foreign and security policy. 
Mine Countermeasures (MCM) Mission Module 
Much of the oversight activity related to the LCS/Frigate program in recent years concerns the 
development and testing of the mine countermeasures (MCM) mission module. The fielding of the MCM 
mission module has been delayed several years compared to earlier schedules, and these delays have 
contributed significantly to the debate and controversy over the LCS program. 
Much of the oversight of regarding the MCM module has focused on the question of whether the module 
is meeting its stated performance requirements. This is a key oversight question. In focusing on this 
question, however, it is possible to lose track of another question, which is whether the MCM module, 
even if it is not meeting its stated performance requirements, is nevertheless demonstrating a level of 
performance that is better than the legacy MCM capability that forward-deployed Navy forces have today. 
                                                 
10 A table showing the survivability standards for various categories of Navy ships is presented in OPNAVINST 9070.1, 
Survivability Policy for Surface Ships of the U.S. Navy, September 23, 1988, Enclosure 3, Survivability Protection Requirements 
by Ship Class. 
11 The Navy’s old Level 1/2/3 nomenclature for surface ship survivability standards is outlined in OPNAVINST 9070.1 of 
September 23, 1988. This document was superseded by OPNAVINST 9070.1A of September 13, 2012, which sets forth the 
Navy’s new framework for discussing surface ship survivability policy and standards. Under the old Level 1/2/3 nomenclature, 
Levels 1, 2, and 3 were defined as follows: 
Level I represents the least severe environment anticipated and excludes the need for enhanced survivability 
or designated ship classes to sustain operations in the immediate area of an engaged Battle Group or in the 
general war-at-sea region. In — this category, the minimum design capability required shall, in addition to 
the inherent sea keeping mission, provide for EMP and shock hardening, individual protection for CBR, 
including decontamination stations, the DC/FF capability to control and recover from conflagrations and 
include the ability to operate in a high latitude environment. 
Level II represents an increase of severity to include the ability for sustained operations when in support of a 
Battle Group and in the general war-at-sea area. This level shall provide the ability for sustained combat 
operations following weapons impact. Capabilities shall include the requirements of Level I plus primary and 
support system redundancy, collective protection system, improved structural integrity and subdivision, 
fragmentation protection, signature reduction, conventional and nuclear blast protection and nuclear 
hardening. 
Level III, the most severe environment projected for combatant Battle Groups, shall include the requirements 
of Level II plus the ability to deal with the broad degrading effects of damage from anti-ship cruise missiles 
(ASCMS), torpedoes and mines. 
(OPNAVINST 9070.1, Survivability Policy for Surface Ships of the U.S. Navy, September 23, 1988, 
Enclosure 2, Definition of Survivability Levels for Surface Ships.) 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 20 
Congressional Research Service 
10 
In the absence of a significant mine threat to forward-deployed Navy forces, this second question might 
not be very important. But if Navy forces are exposed to such a threat, as they might be when operating, 
for example, in the Persian Gulf region, this second question can take on greater importance. Congress 
and the Navy have an interest in seeking to ensure that the MCM module meets its stated performance 
requirements as much as possible. But Congress and the Navy also have a potential interest seeking to 
ensure that forward-deployed Navy forces facing a significant mine threat are not deprived of a new 
MCM capability that performs better than the legacy MCM capability, should the new capability 
demonstrate such a level of performance, on the grounds that the new capability has not met its stated 
performance requirements. 
A second point concerning the MCM module is that the Navy does not plan to use the frigate variants of 
the LCS for the MCM mission. (The Navy plans to use only baseline LCSs for the MCM mission.) In this 
sense, problems experienced in developing and testing the MCM module might not speak directly to the 
merits of the Navy’s proposal for procuring frigates variants of the LCS. 
A third point is that problems experienced in developing and testing the MCM module appear to relate 
more to the MCM systems themselves than to the ship from which they are being deployed (i.e., the 
LCS). To the extent that these same MCM systems would be used by other Navy ships that could be 
assigned the MCM mission, terminating procurement of LCSs and procuring some other ship for the 
MCM mission might not do that much to directly improve the situation. In this sense, the challenges the 
Navy currently faces with the MCM module may be less an LCS issue than an MCM issue that would 
exist whether the Navy procures LCSs or some other type of ship. 
Propulsion Equipment Problems 
The multiple propulsion equipment problems (aka propulsion equipment casualties) experienced by 
commissioned LCSs raise a number of potential oversight questions for Congress, including the 
following: 
  How many of these casualties were due to design problems? How many were due to 
production quality issues? How many were due to issues relating to crew training and 
operation? 
  Are there any common factors linking most or all of the casualties? 
  What are the costs associated with fixing the damage to the LCSs caused by these 
casualties? Who is responsible for paying these costs? 
  Are propulsion casualties on LCSs more common, less common, or about as common as 
propulsion casualties on other classes of Navy surface ships? If they are more common, 
what are the reasons why? 
  What is the Navy’s plan for reducing the frequency of propulsion casualties on LCSs? 
When does the Navy expect to see results from this plan? 
The Navy’s December 1 written testimony to the Senate Armed Services Committee regarding the 
propulsion casualties, which addresses some of these questions, is shown i
n Appendix C of this 
statement. 
New Crewing and Operating Approach 
In September 2016, the Navy announced a new approach for crewing and operating the first 28 baseline 
LCSs. This new approach is referred to as the Blue/Gold approach (because it involves maintaining two 
crews, known as the Blue and Gold crews, for certain individual LCSs), or as the 7-4-3 approach (because 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
 link to page 22 
Congressional Research Service 
11 
it involves maintaining a total of seven crews for each four-ship group of LCSs, with three of the LCSs in 
each group forward deployed). The 7-4-3 approach replaces the previous 3-2-1 approach, so-called 
because it involved maintaining three crews for every two LCSs, so that one of those two LCSs would 
always be available for deployment. The 7-4-3 approach is summarized i
n Appendix D of this statement. 
The Navy states that the 7-4-3 approach is intended to: 
  reduce disruptions to the deployment cycles of LCSs that were being caused by LCS 
mission module testing under the 3-2-1 approach; 
  improve training and proficiency of LCS crews; 
  enhance each LCS crew’s sense of ownership of (and thus responsibility for taking good 
care of) the ship it operates; and 
  achieve a percentage of LCSs in deployed status, and numbers of forward-stationed 
LCSs, similar to or greater than what the Navy aimed to achieve under the 3-2-1 plan. 
Potential oversight questions regarding the 7-4-3 approach include the following: 
  How was this new approach developed?  
  Why does the Navy believe the new approach is the best approach? 
  How fully developed is the new approach this point? If further details need to be 
developed, when does the Navy anticipate developing them? 
  How will the new approach affect the total number of personnel needed to operate the 
Navy’s force of LCSs? 
  How will it affect projected life cycle operation and support (O&S) costs for LCSs? 
  What is the Navy’s schedule for transitioning to the new approach? 
  When does the Navy expect to start seeing benefits from the new approach? 
  How does the Navy intend to measure the effectiveness of the new approach? 
  What was the thinking behind the previous 3-2-1 approach for crewing and operating 
LCSs, and what turned out to be wrong with this thinking? 
  How likely is it that the Navy at some point in the future might need to again change its 
approach for crewing and operating LCSs? 
Defense-Acquisition Policy Lessons Learned12 
Another oversight issue for Congress concerns what defense-acquisition policy lessons, if any, the LCS 
program may offer to policymakers, particularly in terms of the rapid acquisition strategy that the Navy 
pursued for the LCS program, which aimed at reducing acquisition cycle time (i.e., the amount of time 
between starting the program and getting the first ship into service). One possible perspective is that the 
LCS program demonstrated that reducing acquisition cycle time can be done. Supporters of this 
perspective might argue that under a traditional Navy ship acquisition approach, the Navy might have 
spent five or six years developing a design for a new frigate or corvette, and perhaps another five years 
building the lead ship, for a total acquisition cycle time of perhaps 10 to 11 years. For a program 
announced in November 2001, this would have resulted in the first ship entering service in between late 
2011 and late 2012. In contrast, supporters of this perspective might argue, LCS-1 entered service on 
November 8, 2008, about seven years after the program was announced, and LCS-2 entered service on 
January 16, 2010, a little more than eight years after the program announced. Supporters of this                                                  
12 This section is adapted from a section in CRS Report RL33741, 
Navy Littoral Combat Ship (LCS)/Frigate Program: 
Background and Issues for Congress, by Ronald O'Rourke. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
12 
perspective might argue that this reduction in acquisition cycle time was accomplished even though the 
LCS incorporates major innovations compared to previous larger Navy surface combatants in terms of 
reduced crew size, “plug-and fight” mission package modularity, high-speed propulsion, and (in the case 
of LCS-2) hull form and hull materials. 
Another possible perspective is that the LCS program demonstrated the risks or consequences of 
attempting to reduce acquisition cycle time. Supporters of this perspective might argue that the program’s 
rapid acquisition strategy resulted in design-construction concurrency (i.e., building the lead ships before 
their designs were fully developed), a practice long known to increase risks in defense acquisition 
programs. Supporters of this perspective might argue that the cost growth, design issues, and 
construction-quality issues experienced by the first LCSs were due in substantial part to design-
construction concurrency, and that these problems embarrassed the Navy and reduced the Navy’s 
credibility in defending other acquisition programs. They might argue that the challenges the Navy has 
faced in terms of developing an LCS concept of operations (CONOPS), LCS manning and training 
policies, and LCS maintenance and logistics plans were increased by the rapid acquisition strategy, 
because these matters were partly deferred to later years (i.e., to today) while the Navy moved to put 
LCSs into production. Supporters of this perspective might argue that the costs of the rapid acquisition 
strategy are not offset by very much in terms of a true reduction in acquisition cycle time, because the 
first LCS to be equipped with a mission package that had reached IOC (initial operational capability) did 
not occur until 2014. Supporters of this perspective could argue that the Navy could have avoided many 
of the program’s early problems and current challenges—and could have had a fully equipped first ship 
enter service in 2011 or 2012—if it had instead pursued a traditional acquisition approach for a new 
frigate or corvette. They could argue that the LCS program validated, for defense acquisition, the 
guideline from the world of business management that if an effort aims at obtaining something fast, 
cheap, and good, it will succeed in getting no more than two of these things,13 or, more simply, that the 
LCS program validated the general saying that haste makes waste.  
A third possible perspective is that the LCS program offers few if any applicable defense-acquisition 
policy lessons because the LCS differs so much from other Navy ships and the Navy and DOD are 
unlikely to attempt a program like the LCS in the future. Supporters of this perspective might argue that 
the risks of design-construction concurrency have long been known, and that the experience of the LCS 
program did not provide a new lesson in this regard so much as a reminder of an old one. They might 
argue that the cost growth and construction delays experienced by LCS-1 were caused not simply by the 
program’s rapid acquisition strategy, but by a variety of factors, including an incorrectly made reduction 
gear from a supplier firm that forced the shipbuilder to build the lead ship in a significantly revised and 
sub-optimal construction sequence. 
 
Chairwoman Hartzler, this concludes my statement. Thank you again for the opportunity to testify, and I 
will be pleased to respond to any questions the subcommittee may have. 
                                                 
13 The guideline is sometimes referred to in the business world as “Fast, cheap, good—pick two.” 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
13 
Appendix A. Analytical Foundation 
This appendix presents additional discussion on the issue of the analytical foundation for the Navy’s 
proposal for procuring the frigate variant of the LCS. It is adapted from the CRS report on the 
LCS/Frigate program. 
Three Analyses That Can Strengthen an Analytical Foundation 
The analytical foundation for an acquisition program can be strengthened by performing three formal, 
rigorous analyses prior to the start of the program: 
  an analysis to identify capability gaps or mission needs;14 
  an analysis to compare potential general approaches for filling those capability gaps or 
mission needs, so as to identify the best or most promising approach;15 and 
  an analysis to refine the approach selected as the best or most promising.16 
Original LCS Program Lacked One of These Analyses Prior to 
Announcement of Program 
As discussed in CRS reports covering the LCS program going back more than a decade, the Navy, prior to 
announcing the establishment of the LCS program on November 2001, performed the first and third 
studies listed above, but it did not perform the second. In other words, the Navy, prior to announcing the 
establishment of the LCS program on November 1, 2001, did not perform a formal, rigorous analysis to 
show that a small, fast modular ship was not simply one way, but rather the best or most promising way, 
to fill the three littoral warfare capability gaps (for countering mines, small boats, and diesel-electric 
submarines) that the Navy had identified. Instead of performing such an analysis, which at the time might 
have been called an analysis of multiple concepts, the Navy selected the concept of a small, fast, modular 
ship based on the judgment of senior Navy leaders.17 In testimony to the House Armed Services 
                                                 
14 Such a study might be referred to under the defense acquisition system as a Capabilities-Based Assessment (CBA), as 
referenced, for example, on page A-1 of Chairman of the Joint Chiefs of Staff Instruction (CJCSI) 3170.01H of January 10, 2012, 
entitled “Joint Capabilities Integration and Development System.” Such analysis might lead to a “validated capability 
requirements document” or “equivalent requirements document” as referenced on page 5 of DOD Instruction (DODI) 5000.02 of 
January 7, 2015, entitled “Operation of the Defense Acquisition System.” An example of such a requirements document is an 
Initial Capabilities Document (ICD), which is also mentioned on page 5, although that might not be the correct term to use in this 
instance, which concerns an effort to acquire ships in the latter portion of an existing shipbuilding program. For additional 
background discussion on the defense acquisition system, see CRS Report RL34026, 
Defense Acquisitions: How DOD Acquires 
Weapon Systems and Recent Efforts to Reform the Process, by Moshe Schwartz. 
15 Such a study, like the third study listed above, might be referred to under the defense acquisition system as an Analysis of 
Alternatives (AoA). (In earlier years, a study like the second of the three studies listed above might have been referred to as an 
Analysis of Multiple Concepts, or AMC.) In discussing the AoA for a new acquisition program, it can be helpful to understand 
whether the AoA was more like the second or third of the studies listed here. 
16 Such a study, like the second study listed above, might be referred to under the defense acquisition system as an AoA. In 
discussing the AoA for a new acquisition program, it can be helpful to understand whether the AoA was more like the second or 
third of the studies listed here. 
17 For example, the October 28, 2004, version of a CRS report covering the DD(X) (aka, DDG-100) and LCS programs stated: 
In contrast to the DD(X), which reflects the outcome of a formal analysis intended to identify the best or most 
promising way to perform certain surface combatant missions (the SC-21 COEA of 1995-1997), the Navy 
prior to announcing the start of the LCS program in November 2001 did not conduct a formal analysis—
which would now be called an analysis of multiple concepts (AMC)—to demonstrate that a ship like the LCS 
would be more cost-effective than potential alternative approaches for performing the LCS’s stated missions. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
14 
Committee in April 2003, the Navy acknowledged that, on the question of what would be the best 
approach to perform the LCS’s stated missions, “The more rigorous analysis occurred after the decision to 
move to LCS.”18 This issue may have led to some of the controversy that the program experienced in 
subsequent years,19 which in turn formed the backdrop for Secretary of Defense Chuck Hagel’s February 
24, 2014, announcement of the program’s restructuring. 
2014 Restructuring of LCS Program Appears to Have Been Announced 
Without Two of These Analyses 
The Navy’s restructured plan for the frigate design appears to have potential weaknesses in its analytical 
foundation due to two formal, rigorous analyses that do not appear to have been conducted prior to 
Secretary of Defense Chuck Hagel’s announcement on February 24, 2014, of the effort to restructure the 
program. Specifically, neither the Office of the Secretary of Defense nor the Navy has presented 
  a formal, rigorous analysis to identify capability gaps or mission needs that was done 
prior to the Secretary of Defense Hagel’s February 24, 2014, announcement, or 
  a formal, rigorous analysis that identified “a capable and lethal small surface combatant, 
generally consistent with the capabilities of a frigate” as not simply one way, but rather 
the best or most promising way, to fill those capability gaps or mission needs that was 
done prior to the February 24, 2014, announcement. 
Given a July 31, 2014, deadline for the Navy to complete its work, the Navy’s Small Surface Combatant 
Task Force (SSCTF) charged with analyzing options for “a capable and lethal small surface combatant,                                                  
Potential alternative approaches for performing the LCS’s stated missions include (1) manned aircraft, (2) 
submarines equipped with UVs, (3) a larger (perhaps frigate-sized) surface combatant equipped with UVs 
and operating further offshore, (4) a noncombat littoral support craft (LSC) equipped with UVs, or (5) some 
combination. An AMC is often performed before a service starts a major acquisition program. 
The absence of an AMC raises a question regarding the analytical basis for the Navy’s assertion that the LCS 
is the most cost-effective approach for performing the LCS’s stated missions, particularly given the Navy’s 
pre-November 2001 resistance to the idea of a smaller combatant. As a result, the issue of whether a ship like 
the LCS represents the best or most promising approach has become a subject of some debate. 
(CRS Report RL32109, Navy DD(X) and LCS Ship Acquisition Programs: Oversight Issues and Options for 
Congress, by Ronald O’Rourke. The title of this report is now 
Navy DDG-51 and DDG-1000 Destroyer 
Programs: Background and Issues for Congress.) 
18 Spoken testimony of Vice Admiral John Nathman, Deputy Chief of Naval Operations (Warfare Requirements and Programs), 
at an April 3, 2003, hearing on Navy programs before the Projection Forces subcommittee of the House Armed Services 
Committee. At this hearing, the chairman of the subcommittee, Representative Roscoe Bartlett, asked the Navy witnesses about 
the Navy’s analytical basis for the LCS program. The witnesses defended the analytical basis of the LCS program but 
acknowledged that “The more rigorous analysis occurred after the decision to move to LCS.” See U.S. Congress, House 
Committee on Armed Services, Subcommittee on Projection Forces, Hearing on National Defense Authorization Act for Fiscal 
Year 2004—H.R. 1588, and Oversight of Previously Authorized Programs. 108th Cong., 1st sess., Mar. 27, and Apr. 3, 2003, 
(Washington: GPO, 2003), p. 126. For an article discussing the exchange, see Jason Ma, “Admiral: Most LCS Requirement 
Analysis Done After Decision To Build,” 
Inside the Navy, April 14, 2003. 
19 A January 2015 journal article on the lessons of the LCS program stated: 
As Ronald O’Rourke of the Congressional Research Service described it early on [at a presentation at the 
Surface Navy Association annual symposium in January 2003], the LCS had come about through an 
“analytical virgin birth… that is going to be a problem for this program down the road.” This can be argued 
to be the root cause of the subsequent LCS woes. One hopes that the new surface combatant [i.e., the Navy’s 
design for the frigate] won’t suffer the same problem. 
(Gregory V. Cox, “Lessons Learned from the LCS,” 
U.S. Naval Institute Proceedings, January 2015: 37-38 
(ellipse as in original), citing (for the quoted remark) Hunter Keeter, “O’Rourke: Lack Of Pedigree May 
Haunt LCS Program,” 
Defense Daily, January 16, 2003.) 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
15 
generally consistent with the capabilities of a frigate” apparently did not have enough time to conduct 
either of the two above analyses. Instead, the task force surveyed Navy fleet commanders to collect their 
judgments on capability gaps and mission needs, and to get their judgments on what capabilities would be 
the best to have in “a capable and lethal small surface combatant, generally consistent with the 
capabilities of a frigate.”20 
In addition to permitting the task force to complete its work by July 31, 2014, surveying fleet 
commanders offered the advantage of collecting the “wisdom of the crowd” on the issues of capability 
gaps and mission needs and what features “a capable and lethal small surface combatant, generally 
consistent with the capabilities of a frigate” should have. One potential disadvantage of this approach is 
that it deprived the Navy of a chance to uncover the kind of counterintuitive results that a formal analysis 
can uncover. (Indeed, this is a key reason why formal, rigorous analyses are done.) Another potential 
disadvantage is that fleet commanders can be focused on what they see the Navy needing today, based on 
current Navy operations, which might not be the same in all respects as what the Navy will need in the 
future, given the evolving international security environment, potential changes in technology, and 
resulting potential changes in the nature of warfare and operational concepts. The risk, in other words, is 
of fielding years from now the best possible improved LCS for the world of 2014. 
Using the results it had gathered from surveying fleet commanders, the SSCTF then performed the third 
of the three above-listed studies—a formal, rigorous analysis to refine the concept for “a capable and 
lethal small surface combatant, generally consistent with the capabilities of a frigate.” 
A question for Congress is whether the analytical foundation for the frigate design will provide sufficient 
stability for acquiring those ships in coming years. Navy officials stated that, having refined the design 
concept for the modified LCS design, the Navy will now define and seek approval for the operational 
requirements for the ship.21 Skeptics might argue that definition and approval of operational requirements 
should come first, and conceptual design should follow, not the other way around. One possible 
alternative to the Navy’s approach would be to put the announced design concept for the modified LCS 
                                                 
20 A January 8, 2014, press report, for example, states that “The task force canvassed fleet commanders for ways to improve” the 
baseline LCS design. (Tony Capaccio, “Navy Fixes Won’t Much Help Littoral Ship, Tester Says,” 
Bloomberg News, January 8, 
2015. A January 16, 2015, press report similarly states: 
Fleet commanders told Navy officials over the past year that they see anti-submarine warfare, surface warfare 
and ship self-defense as the most important capabilities for a new small surface combatant, Surface Warfare 
Director Rear Adm. Peter Fanta said Jan. 13 during the Surface Navy Association’s annual symposium. This 
feedback led the Navy to its decision to move to a modified LCS that will have enhanced weapons, sensors 
and armor—along with increased weight and a slower top speed. 
“What we did first was we went and asked all the warfighters ... what do you want most?” [said] Fanta, who 
served as one of the co-chairs of the small surface combatant task force that was stood up last year to provide 
the defense secretary with alternatives for a more lethal and survivable LCS. “They said ‘well, we'd like a 
small surface combatant that does a lot of ASW work, covers our mine mission and still does a lot of surface 
engagements depending on different parts of the world.” 
(Lara Seligman, “Upgunned LCS Will Trade Speed, Weight For Offensive Capabilities,” 
Inside the Navy, 
January 16, 2015 [with additional reporting by Lee Hudson] Ellipse as in original.) 
21 A January 11, 2014, press report, for example, quotes Sean Stackley, the Assistant Secretary of the Navy for Research, 
Development, and Acquisition (i.e., the Navy’s acquisition executive) as stating “We’ve gone from ‘here’s the concept,’ now we 
have to go through the formal requirements review board... to define requirements in terms of updating the capabilities 
document.” (As quoted in Christopher Cavas, “Small Combatant Effort Cranks Up,” 
Defense News, January 11, 2015. [Ellipse as 
in original.]) A January 16, 2015, press report similarly states: “The Navy needs to take all the task force’s concepts for 
capabilities and translate them into specific, formal requirements, Stackley explained. Those requirements then need approval by 
a Resources and Requirements Review Board (R3B).” (Sydney J. Freedberg Jr., “What’s In A name? Making The LCS ‘Frigate’ 
Reality,” 
Breaking Defense, January 16, 2015.) A January 26, 2015, press report similarly states that “the Navy needs to firm up 
the concept for the new ship’s capabilities and translate them into formal requirements, Stackley explained. Those requirements 
then need to each be approved by a Resources and Requirements Review Board, which is set to occur in the spring.” (Lara 
Seligman, “Navy Working To Iron Out Details Of Plan For Backfitting LCS Upgrade,” 
Inside the Navy, January 26, 2015.) 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
16 
design on hold, and perform both a formal, rigorous analysis of capability gaps/mission needs and a 
formal, rigorous analysis of general approaches for meeting those identified capability gaps/mission 
needs, and be prepared to follow the results of those analyses, whether they lead back to the announced 
design concept for the modified LCS design, or to some other solution (which might still be a design of 
some kind for a modified LCS). 
Potential Oversight Questions Regarding December 2015 Restructuring 
of LCS/Frigate Program 
Regarding the analytical foundation for the December 2015 restructuring of the LCS/Frigate program, 
potential oversight questions for Congress include the following: 
  What is the Office of the Secretary of Defense’s (OSD’s) analytical basis for directing the 
Navy to reduce the LCS/Frigate program from 52 ships to 40, and to redirect the savings 
from this action to the other Navy program priorities shown in the December 14, 2015, 
memorandum from the Secretary? What is the analytical basis for directing the Navy to 
reduce the LCS/Frigate program to 40 ships, as opposed to some other number smaller 
than 52? What studies were done within OSD to form the analytical foundation for the 
directions in the memorandum? 
  What are the potential operational advantages and disadvantages of reducing the 
LCS/Frigate program from 52 ships to 40 ships and redirecting funding to the other Navy 
program priorities? 
  How would unit procurement costs for LCSs/Frigates be affected by reducing the 
program’s procurement rate to two ships in FY2017, one ship per year in FY2018-
FY2020 and two ships in FY2021? 
  How much is OSD’s direction to the Navy to reduce the LCS/Frigate program from 52 
ships to 40 ships and redirect funding to the other Navy program priorities dependent on 
an assumption that limits on defense spending under the Budget Control Act of 2011 (S. 
365/P.L. 112-25 of August 2, 2011), as amended, will remain in place? How might the 
merits of this direction be affected, if at all, by a decision to further amend or repeal these 
limits? 
  Between the program’s 2014 restructuring and the direction in the December 14, 2015, 
memorandum, the program has now been changed by OSD substantially twice in a period 
of two years. Although these changes are intended by OSD to improve program 
effectiveness and better optimize Navy spending, what impact might changing the 
program substantially twice in a period of two years have on program’s stability and the 
ability of the Navy and industry to implement the program efficiently? 
At a February 25, 2016, hearing before the Seapower and Projection Forces subcommittee of the House 
Armed Services Committee, the Navy testified that 
The 2014 FSA update [i.e., the Navy’s most recently completed Force Structure Assessment for 
determining the Navy’s force-level goals for ships] outlines the requirement for 52 Small Surface 
Combatants  (SSCs)  and  determined  a  need  for  26  deployed  SSCs  to  meet  the  Navy’s  global 
peacetime  and  wartime  requirement.  The  Navy’s  2016  Long  Range  Shipbuilding  Plan  and  the 
FY2016  Future  Years  Defense  Plan  (FYDP)  included  procurement  of  14  LCS/Fast  Frigate  (FF) 
ships in FY2017-2021. In order to balance current and future capability needs within the FY 2017 
top line constraints, the procurement plan for LCS/FF was reduced to seven ships within the FYDP 
and the overall inventory objective was reduced from 52 to 40 ships. The Navy will evaluate the 
risk  associated  with  this  budget  decision,  in  the  broader  context  of  total  large  and  small  surface 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
17 
combatant  ship  inventory,  in  the  course  of  the  2016  FSA  update  to  inform  future  shipbuilding 
plans.22 
A February 26, 2016, press report states: 
During  hearings  on  the  budget  held  Thursday  on  Capitol  Hill,  top  Defense  Department  officials 
revealed a stark difference of opinion over the direction of the Littoral Combat Ship (LCS) program, 
which was slashed from 52 to 40 ships in the fiscal year 2017 budget request. 
Defense Secretary Ashton Carter told House appropriators Thursday afternoon that the decision to 
move to 40 ships—which was dictated to the service through a December memo written by Carter—
was driven by longterm national security considerations. 
But in a House Armed Services Committee seapower and projection force subcommittee hearing 
that afternoon, the Navy’s top acquisition official Sean Stackley painted a very different picture. 
“This  budget  cycle,  the  decision  was  made  [to  cut  the  program],”  he  said.  “It  comes  down  to 
reductions in the budget. Reductions in the budget drove trades in terms of capability in the near 
term, and long term. The decision was made not based on a force structure assessment.” 
The latest force structure assessment, which lays out the size and shape of the Navy, was published 
in 2014 and stated a 52-vessel small surface combatant requirement, which would be made up of 40 
LCS and 12 of the “fast frigate” variant of the ship. That requirement has not changed, Stackley 
said. 
“The Navy’s analysis is captured by the force structure analysis, which still requires 52 small surface 
combatants,”  he  said.  “The  decision to go  from 52 to 40 becomes a  budget-driven decision and 
accepts risk.”... 
In the House Appropriations defense subcommittee hearing, Carter characterized the reduced buy 
differently. 
“The Littoral Combat Ship is a successful program. It is an excellent ship,” he said. “The Navy’s 
warfighting analysis concluded 40 of them were enough. And, yes we did want to apply resources 
elsewhere to the lethality of our ships. That’s critically important, that we not only have enough 
ships…but that they’re the very best.”23 
A March 6, 2016, press report states: 
A controversial request to cap the Littoral Combat Ship (LCS) and follow-on frigate programme at 
40  hulls,  instead  of  52,  was  made  because  Pentagon  officials  felt  the  lower  number  was  still 
sufficient for a ‘presence’ role and funding was prioritised elsewhere. 
“A fleet  of 40 of those  is going to be  fully capable  of providing  more  presence than the  fleet  it 
replaces,”  Jamie  Morin,  director  of  the  Department  of  Defense’s  (DoD's)  Cost  Assessment  and 
Program  Evaluation  office,  said  during  a  7  March  briefing  at  the  Center  for  Strategic  and 
International Studies.... 
Morin said the navy had a 52-ship total for LCSs because that accounted for replacing ‘warfighting’ 
requirements as well as ‘presence’ requirements, but the Pentagon believes it can do both with fewer 
ships and thereby free resources to buy more advanced munitions, bolster USN aviation, and protect 
investments for readiness and for future capabilities.24 
                                                 
22 Statement of the Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and Acquisition) and 
Vice Admiral Joseph P. Mulloy, Deputy Chief of Naval Operations for Integration of Capabilities and Resources and Lieutenant 
General Robert S. Walsh, Deputy Commandant, Combat Development and Integration & Commanding General, Marine Corps 
Combat Development Command, Before the Subcommittee on Seapower and Projection Forces of the House Armed Services 
Committee on department of the Navy Seapower and Projection Forces Capabilities, February 25, 2016, p. 15. 
23 Valerie Insinna, “On Capitol Hill, OSD and Navy Officials at Odds Over LCS,” 
Defense Daily, February 26, 2016: 1-2. 
24 Daniel Wasserbly, “US Official: 40 LCSs Sufficient for Navy’s ‘Presence’ Role,” 
IHS Jane’s Defence Weekly, March 6, 2015. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
18 
Appendix B. Notional Procurement Profile for a Force of 
56 Small Surface Combatants 
This appendix shows a notional procurement profile for achieving a force of 56 small surface combatants, 
and compares it to the procurement profile for small surface combatants in the Navy’s FY2017 30-year 
shipbuilding plan. The notional profile is shown in the table below, which appears in the CRS report on 
the idea of a bigger Navy.25 
Table B-1. Frigate and LCS procurement profiles 
Current 30-
Notional 
year 
profile for 
shipbuilding 
56-ship 
Annual 
Cumulative 
Fiscal year 
plan 
force 
difference 
difference 
17 
2 
3 
+1 
+1 
18 
1 
3 
+2 
+3 
19 
1 
4 
+3 
+6 
20 
1 
4 
+3 
+9 
21 
2 
4 
+2 
+11 
22 
2 
4 
+2 
+13 
23 
2 
4 
+2 
+15 
24 
2 
3 
+1 
+16 
25 
1 
2 
+1 
+17 
26 
 
 
 
 
27 
 
 
 
 
28 
 
 
 
 
29 
1 
 
-1 
+16 
30 
 
 
 
 
31 
1 
 
-1 
+15 
32 
1 
 
-1 
+14 
33 
1 
1 
0 
+14 
34 
2 
1 
-1 
+13 
35 
2 
1 
-1 
+12 
Source: Table prepared by CRS based on U.S. Navy data. 
                                                 
25 CRS Report R44635, 
Navy Force Structure: A Bigger Fleet? Background and Issues for Congress, by Ronald O'Rourke. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
19 
Appendix C. December 1 Navy Testimony on LCS 
Propulsion Casualties 
This appendix presents the Navy’s written testimony on LCS propulsion casualties for a December 1, 
2016, hearing on the LCS program before the Senate Armed Services Committee. The Navy’s testimony 
states: 
As we increase our operational experience with LCS, we are closely monitoring material readiness 
and making changes, as warranted to improve operational availability. In total, LCS readiness as 
reflected in operational availability and casualty report metrics is consistent with other combatant 
ship classes. However, we are quickly and strongly addressing issues as they emerge to raise the 
system reliability to yet higher levels sooner in this new class. Of particular concern, five LCS class 
ships  have  been  operationally  impacted  by  propulsion  casualties  in  the  past  year.  The  Navy  has 
conducted  formal  engineering  reviews  and  command  investigations  to  assess  the  root  cause  and 
corrective  action  for  each  of  the  casualties.  In  general,  the  root  causes  can  be  broken  into  three 
separate  categories:  procedural  non-compliance  (failure  to  follow  approved  engineering 
procedures); design related deficiencies; or production-related deficiencies. 
Two of the five engineering casualties were related to procedural (non-) compliance: 
The first such casualty occurred onboard USS FORT WORTH while [it was] inport [at] Singapore, 
after 12 months of her 14 month maiden deployment. As a result of improper alignment of the lube 
oil service system (as outlined by the ship’s Engineering Operating Procedures), three of the five 
bearings in the Combining Gear were damaged and USS FORT WORTH was unable to continue 
her  mission in the  western Pacific. Upon completion of repairs, the  ship departed Singapore and 
returned to San Diego in early October 2016. 
The second casualty related to procedural (non-) compliance occurred onboard USS FREEDOM 
while inport San Diego. Improper corrective action following the routine failure of FREEDOM’s 
Main  Propulsion  Diesel  Engine  (MPDE)  attached  seawater  pump  mechanical  seal  resulted  in 
seawater  contamination  of  the  engine.  Upon  subsequent  inspection,  significant  corrosion  and 
damage  was  discovered  inside  the  MPDE.  The  affected  engine  is  planned  for  replacement 
commencing December 2016. 
In response to these procedural compliance issues, the Type Commander has  conducted a formal 
investigation  and  root  cause  analysis  on  both  casualties.  The  Commander,  Naval  Surface  Forces 
directed an engineering stand down for all LCS Class crews to review, evaluate, and renew their 
commitment  to  safe  ship  operation,  procedural  compliance,  and  good  engineering  practices. 
Additionally, the Navy’s Surface Warfare Officer’s School Command is revising the current LCS 
training  program,  to  include  LCS  specific  engineering  training  and  related  proficiency 
examinations. In parallel, the Naval Sea Systems Command (NAVSEA) is reviewing design details 
for potential design enhancements that may mitigate the possibility of such operator errors. 
One of the five engineering casualties was specifically design-related: 
While operating USS MILWAUKEE (LCS 5) on all four engines at full power during transit in the 
Atlantic, an emergency stop of the gas turbine engines led to excessive wear of the high speed clutch 
causing damage to the high speed clutch and combining gear. Root cause analysis is in progress, but 
the combining gear on LCS 5 and follow is a new design (prior manufacturer ceased operations), 
and changes to the control logic for the de-clutch sequence and clutch piston release speed associated 
with  the  new  design  are  apparent  causes.  Design  modifications  based  on  root  causes  have  been 
developed and are being tested by Lockheed Martin and RENK (the gear manufacturer), in parallel 
with ongoing root cause analysis efforts. Pending satisfactory testing this month (December 2016), 
the  associated  high  speed  clutch  modifications  and  machinery  control  software  updates  will  be 
applied  to  LCS  9  and  follow  prior  to  delivery  and  LCS  5  and  7  during  their  Post  Shakedown 
Availabilities (PSAs). LCS 1 and LCS 3 gear sets are not affected. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
20 
The remaining two engineering casualties trace to deficiencies in the ship construction process: 
USS  CORONADO  (LCS  4)  experienced  a  failure  of  the  flexible  shaft  coupling  between  the 
starboard MPDE reduction gear and stern tube during transit from Hawaii to Singapore. A failure 
review board  was convened, and  while  material testing of the failed coupling is still in progress, 
shaft  misalignment  has  been  identified  as  a  contributing  factor  in  the  root  cause  analysis.  An 
alignment  summit  with  the  shipbuilder,  NAVSEA  design  engineers,  the  Original  Equipment 
Manufacturer, the Supervisor of Shipbuilding, and the Program Office has since been conducted to 
review, validate, and better document waterborne alignment procedures. The coupling in LCS 4 was 
replaced with a new coupling design in Hawaii. USS CORONADO is now on station in Singapore 
on  her  maiden  deployment.  This  new  coupling  design  has  already  been  installed  on  LCS  6  and 
follow ships. 
USS  MONTGOMERY  (LCS  8)  experienced  a production  deficiency  related  propulsion  casualty 
shortly  after  sail  away  from  the  new  construction  shipyard.  Prior  to  getting  underway,  the  crew 
discovered seawater contamination in the steering hydraulic system for one of the four waterjets. 
The shipbuilder drained the system, replaced the system’s seawater cooler, and flushed the system 
restoring full waterjet functionality. The root cause assessment determined that the cooler had not 
failed, but rather contamination was introduced into the system most likely in conjunction with the 
repair  of  a  component  external  to  the  hull  in  the  period  between  delivery  and  sailaway  from  the 
building  yard.  The  shipbuilder  has  since  implemented  an  improved  procedure  for  waterborne 
waterjet hydraulic work. 
The Navy has taken a consistent and rigorous approach in assessing and addressing root causes of 
equipment casualties in LCS. Early deficiencies in the designs of each variant have been addressed 
in follow  ships, but there is still  work to be done in increasing the operational availability of the 
ships in-service. In response, NAVSEA has initiated a comprehensive engineering review of both 
propulsion trains, to include logistics and training, and will report their findings upon completion of 
the review.26 
                                                 
26 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and Acquisition) and 
VADM Thomas S. Rowden, Commander, Naval Surface Forces, Before the Senate Armed Services Committee on the Littoral 
Combat Ship, December 1, 2016, pp. 8-10. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
21 
Appendix D. New Crewing and Operating Approach 
This appendix presents additional background information on the Navy’s new 7-4-3 approach for crewing 
and operating LCSs. It is adapted from the CRS report on the LCS/Frigate program. 
In September 2016, the Navy announced a new approach for crewing and operating the first 28 baseline 
LCSs. This new approach is referred to as the Blue/Gold approach (because it involves maintaining two 
crews, known as the Blue and Gold crews, for certain individual LCSs), or as the 7-4-3 approach (because 
it involves maintaining a total of seven crews for each four-ship group of LCSs, with three of the LCSs in 
each group forward deployed). Key elements of the 7-4-3 approach include the following:27 
  the first four LCSs (LCSs 1 through 4) will each by operated by a single crew and be 
dedicated to testing and evaluating LCS mission packages (though they could be 
deployed as fleet assets if needed on a limited basis); 
  the other 24 LCSs (LCSs 5 through 28) will be divided into six divisions (i.e., groups) of 
four ships each; 
  three of the divisions (i.e., 12 of the 24 ships), all of them built to the LCS-1 design, will 
be homeported at Mayport, FL; 
  the other three divisions (i.e., the remaining 12 ships), all of them built to the LCS-2 
design, will be homeported at San Diego, CA; 
  among the three divisions on each coast, one division will focus on MCM, one will focus 
on ASW, and one will focus on SUW; 
  in each of the six divisions, one ship will be operated by a single crew, and will focus on 
training the crews of the other three ships in the division; 
  the other three ships in each division will each be operated by dual crews (i.e., Blue and 
Gold crews), like the Navy’s ballistic missile submarines; 
  the crews for the 24 ships in the six divisions will be unified crews—the distinction 
between core crew and mission package crew will be eliminated; 
  the 24 ships in the six divisions will experience changes in their mission packages (and 
thus in their mission orientations) infrequently, if at all; and 
  13 of the 24 ships in the six divisions (i.e., more than 50%) are to be forward stationed at 
any given point for periods of 24 months, with three at Singapore, three at another 
Western Pacific location, such as Sasebo, Japan, and seven at Bahrain. 
The Navy states that the 12 frigates to be procured after the 28 baseline LCSs will also use this new 
crewing and operating approach,28 and that as the fleet continues to accumulate experience in operating 
and maintaining LCSs, elements of this new plan might be modified.29 
 
                                                 
27 Source: Navy briefing on new LCS crewing and operating approach given to CRS and CBO, September 26, 2016. See also 
“Navy Adjusts LCS Class Crewing, Readiness and Employment,” 
Navy News Service, September 8, 2016; Sam LaGrone, 
“Results of New LCS Review is Departure from Original Vision,” 
USNI News, September 8, 2016; Sydney J. Freedberg Jr., 
“Navy Sidelines First 4 LCS; Overhauls Deployment, Crewing,” 
Breaking Defense, September 8, 2016; Justin Doubleday, “Navy 
Introduces Major Change to Littoral Combat Ship Operations,” 
Inside the Navy, September 9, 2016; David B. Larter, “Rebooting 
LCS: Hundreds More Sailors Needed in Sweeping Overhaul,” 
Navy Times, September 9, 2016; Justin Doubleday, “Navy Begins 
Implementing Changes to Littoral Combat Ship Program,” 
Inside the Navy, October 10, 2016. 
28 See “Navy Adjusts LCS Class Crewing, Readiness and Employment,” 
Navy News Service, September 8, 2016. 
29 See, for example, Sydney J. Freedberg Jr., “Navy Sidelines First 4 LCS; Overhauls Deployment, Crewing,” 
Breaking Defense, 
September 8, 2016. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
Congressional Research Service 
22 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff 
to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of 
Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of 
information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. 
CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United 
States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, 
as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the 
permission of the copyright holder if you wish to copy or otherwise use copyrighted material. 
CRS TESTIMONY 
Prepared for Congress ————————————————————————————————— 
TE10013