Defense Cleanup and Environmental Programs: Authorization and Appropriations for FY2003

The Department of Defense (DOD) administers five environmental programs in response to various requirements under federal environmental laws. These programs include environmental cleanup, environmental compliance, pollution prevention, environmental technology, and conservation. Additionally, the Department of Energy (DOE) is responsible for managing defense nuclear waste and cleaning up contaminated nuclear weapons sites. The Administration requested a total of $11.17 billion for these programs in FY2003, about $390 million more than the FY2002 funding level of $10.78 billion. Some of the ongoing issues associated with these programs are the adequacy, cost, and pace of cleanup, whether DOD and DOE adequately comply with environmental laws and regulations, and the extent to which environmental requirements encroach upon military readiness.

Order Code RL31456
CRS Report for Congress
Received through the CRS Web
Defense Cleanup and Environmental Programs:
Authorization and Appropriations for FY2003
Updated July 24, 2003
David M. Bearden
Environmental Policy Analyst
Resources, Science, and Industry Division
Congressional Research Service ˜ The Library of Congress

Defense Cleanup and Environmental Programs:
Authorization and Appropriations for FY2003
Summary
The Department of Defense (DOD) administers five environmental programs
in response to various requirements under federal environmental laws. These
programs include environmental cleanup, environmental compliance, pollution
prevention, environmental technology, and conservation.
Additionally, the
Department of Energy (DOE) is responsible for managing defense nuclear waste and
cleaning up contaminated nuclear weapons sites. Congress appropriated a total of
$11.07 billion for these programs for FY2003, approximately $100 million less than
the Administration’s request of $11.17 billion, but about $280 million more than the
FY2002 funding level of $10.79 billion. Some of the ongoing issues associated with
these programs are the adequacy, cost, and pace of cleanup, whether DOD and DOE
adequately comply with environmental laws and regulations, and the extent to which
environmental requirements encroach upon military readiness.
The 107th Congress completed consideration of legislation to authorize funding
for national defense programs for FY2003, including defense-related environmental
programs. The National Defense Authorization Act for FY2003 (P.L. 107-314, H.R.
4546) authorized $1.32 billion for environmental cleanup at current and former
military installations. It also authorized $565 million for base closure activities, most
of which was intended for environmental cleanup. As in past years, funding was
authorized for DOD’s other environmental activities as part of several larger
accounts. The law authorized a total of $6.76 billion for DOE’s defense nuclear
waste management and cleanup responsibilities.
The final authorization also
included an interim exemption from the Migratory Bird Treaty Act for military
readiness activities, which DOD had requested as part of a Readiness and Range
Preservation Initiative (RRPI) to address the impacts of environmental requirements
on combat training needs. Portions of the RRPI that would have included targeted
exemptions from other environmental laws were not included in the final bill.
The 107th Congress also completed consideration of the FY2003 appropriations
bills for DOD and Military Construction, which fund DOD’s environmental
programs. The Department of Defense Appropriations Act for FY2003 (P.L. 107-
248, H.R. 5010) provided $1.31 billion for cleanup at current and former military
installations, slightly less than authorized. As in defense authorization legislation,
funding was provided for other environmental activities as part of several larger
accounts. The Military Construction Appropriations Act for FY2003 (P.L. 107-249,
H.R. 5011) provided $561 million for base closure activities, most of which was to
be used for cleanup, slightly less than authorized as well.
Debate over FY2003 appropriations for DOE’s management and cleanup of
defense nuclear waste was not completed during the 107th Congress.
Final
appropriations for these activities were enacted early in the 108th Congress. The
Consolidated Appropriations Resolution for FY2003 (P.L. 108-7, H.J.Res. 2)
included an omnibus appropriations package that provided a total of $6.72 billion for
DOE’s defense nuclear waste management and cleanup responsibilities, slightly less
than authorized.

Contents
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Department of Defense . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Environmental Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Oversight of Cleanup Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Cleanup Status and Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Appropriations Account Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Overseas Military Installations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Environmental Compliance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Compliance Requirements under Federal Law . . . . . . . . . . . . . . . . . . . 7
Funding Trends . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Fines for Violations of Environmental Requirements . . . . . . . . . . . . . . 7
Other Environmental Programs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Military Readiness Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Department of Energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Oversight of Cleanup and Waste Management Activities . . . . . . . . . . . . . . 12
Cleanup Status and Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Appropriations Account Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Yucca Mountain . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Formerly Utilized Sites Remedial Action Program . . . . . . . . . . . . . . . . . . . 16
Authorizing Legislation for FY2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Department of Defense . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Environmental Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Military Readiness Issues . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Procurement Practices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Natural Resource Conservation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Use and Disposal of Obsolete Naval Vessels . . . . . . . . . . . . . . . . . . . 21
Department of Energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Appropriations for FY2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Department of Defense . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Military Construction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Energy and Water Development . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
Selected References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
List of Figures
Figure 1. Funding for Defense Cleanup and Environmental Programs:
FY1990 to FY2003 Enacted . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Figure 2. Cleanup Status at Current, Former, and Closing Military Installations
in the United States as of September 30, 2002 . . . . . . . . . . . . . . . . . . . . . . . 5
Figure 3. Cleanup Status at DOE Nuclear Waste Management and
Environmental Restoration Sites as of September 30, 2002 . . . . . . . . . . . . 13

Figure 4. Cleanup Status under the Formerly Utilized Sites
Remedial Action Program as of June 2003 . . . . . . . . . . . . . . . . . . . . . . . . . 16
List of Tables
Table 1. Fines and Penalties Assessed and Paid for
Environmental Violations from FY1997 to FY2001 . . . . . . . . . . . . . . . . . . . 8

Defense Cleanup and Environmental
Programs: Authorization and
Appropriations for FY2003
Introduction
The Department of Defense (DOD) administers five environmental programs
that address the cleanup of past contamination on military installations, compliance
with environmental laws that apply to ongoing military operations, pollution
prevention, environmental cleanup and waste management technologies, and the
conservation of military lands. In addition to DOD’s environmental programs, the
Department of Energy (DOE) is responsible for managing defense nuclear waste, and
cleaning up contaminated nuclear weapons sites. The Environmental Protection
Agency (EPA) and the states provide oversight to enforce applicable laws. Some of
the ongoing issues are the adequacy, cost, and pace of cleanup, whether DOD and
DOE adequately comply with environmental laws, and the extent to which
environmental requirements restrict military readiness.
Congress authorizes defense-related environmental programs in the annual
authorization bill for National Defense, but it funds these programs under three
appropriations bills. Cleanup activities at currently active and former military
installations, environmental compliance, pollution prevention, environmental
technology, and conservation primarily receive funding in the annual appropriations
bill for the Department of Defense, but cleanup at base closure sites is funded in the
annual appropriations bill for Military Construction.
DOE’s cleanup and
management of defense nuclear waste is funded in the annual appropriations bill for
Energy and Water Development.
For FY2003, Congress appropriated a total of $11.07 billion for all defense-
related environmental programs. This amount is approximately $100 million less
than the Administration’s request of $11.17 billion, but is about $280 million more
than the FY2002 funding level of $10.79 billion. FY2003 appropriations for DOD’s
environmental programs were enacted during the 107th Congress. However, debate
over FY2003 appropriations for DOE’s management and cleanup of defense nuclear
waste extended into the 108th Congress, and were provided as part of an omnibus
appropriations package under the Consolidated Appropriations Resolution for
FY2003 (P.L. 108-7, H.J.Res. 2). Figure 1 provides a funding history since FY1990.
This report provides background information on defense-related environmental
programs, analyzes various implementation issues, and examines final versions of
legislation to authorize and appropriate funding for FY2003 to support defense-
related environmental programs.





































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































































CRS-2
Figure 1. Funding for Defense Cleanup and Environmental Programs:
FY1990 to FY2003 Enacted
Billions of Dollars
14.00
12.00
10.51
10.63
10.82
10.79
11.07
9.93
9.97
10.19
10.31
10.26
9.92
10.00
7.36
8.00
5.25
6.00
3.05
4.00
2.00
0.00
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
Environmental Technology
n/a
n/a
n/a
0.43
0.41
0.28
0.22
0.21
0.21
0.26
0.29
0.29
0.23
0.23
Pollution Prevention
n/a
n/a
n/a
0.30
0.34
0.29
0.25
0.26
0.26
0.23
0.28
0.21
0.23
0.22
Natural Resource Conservation
n/a
n/a
n/a
0.12
0.10
0.15
0.11
0.09
0.14
0.13
0.16
0.18
0.16
0.16
Base Closure Cleanup
n/a
0.37
0.62
0.49
0.54
0.64
0.85
0.68
0.83
0.76
0.36
0.79
0.61
0.54
Current and Former Site Cleanup
0.60
1.07
1.13
1.64
1.97
1.48
1.41
1.31
1.30
1.27
1.30
1.31
1.27
1.31
Environmental Compliance
0.79
1.11
1.93
2.12
1.98
2.04
2.23
2.02
1.91
1.89
1.66
1.63
1.67
1.75
Corps of Engineers FUSRAP
n/a
n/a
n/a
n/a
n/a
n/a
n/a
n/a
0.14
0.14
0.15
0.14
0.14
0.14
Department of Energy Cleanup
1.66
2.70
3.68
4.83
5.17
5.09
5.56
5.62
5.52
5.58
5.72
6.27
6.48
6.72
Prepared by the Congressional Research Service using data from enacted appropriations, Operation and Maintenance Overviews of the
Department of Defense, and congressional budget justifications of the Department of Energy. N/A = account or program not yet established.
FUSRAP = Formerly Utilized Sites Remedial Action Program.

CRS-3
Department of Defense
DOD administers five environmental programs to comply with various federal
environmental laws.1 In terms of funding, the two largest programs focus on cleaning
up past contamination and on complying with environmental laws and regulations
that apply to ongoing operations. Three other programs have smaller budgets. They
focus on pollution prevention, environmental technology, and conservation. For
FY2003, Congress appropriated a total of $4.20 billion for all five of DOD’s
environmental programs, about $90 million more than the Administration’s request
of $4.11 billion, and about $45 million more than the FY2002 funding level of nearly
$4.16 billion. (Refer to page 17 for a discussion of authorizing legislation and
appropriations for FY2003.) Background information on each program and an
analysis of major implementation issues are discussed below.
Environmental Cleanup
In 1975, DOD established an Installation Restoration Program to investigate and
clean up sites on military lands where past waste management practices had led to
environmental contamination. A few years later, the Comprehensive Environmental
Response, Compensation, and Liability Act of 1980 (CERCLA) created the
Superfund program to clean up hazardous waste sites that pose the greatest risk to
public health and the environment in the United States, and it created the National
Priorities List (NPL) to track them.2 The law also established a formal framework
for the identification, investigation, and cleanup of hazardous substances. Initially,
the extent to which DOD had to comply with these requirements was unclear.
However, the Superfund Amendments and Reauthorization Act of 1986 (SARA)
specified that DOD and all other federal agencies are subject to CERCLA’s
requirements for identifying, evaluating, and cleaning up NPL sites under their
jurisdiction.3 The Resource Conservation and Recovery Act (RCRA) also requires
DOD and all other federal agencies to perform corrective actions to clean up
contamination at sites with active hazardous waste management or solid waste
disposal facilities operating with permits issued under RCRA.4
In addition to specifying the applicability of CERCLA, SARA expanded the
Installation Restoration Program, and renamed it the Defense Environmental
Restoration Program, to centralize DOD’s efforts in cleaning up hazardous waste
sites at domestic military installations where past actions led to contamination.5 As
a complement to this program, DOD established a Military Munitions Response
Program to fulfill requirements under Sections 311 and 312 of the National Defense
Authorization Act for FY2002 (P.L. 107-107) to identify, investigate, and clean up
1 For additional information on each program, refer to the Defense Environmental Network
and Information Exchange (DENIX) web site at [http://www.denix.osd.mil].
2 42 U.S.C. 9601 et. seq.
3 42 U.S.C. 9620
4 42 U.S.C. 6901 et seq.
5 10 U.S.C. 2701

CRS-4
unexploded ordnance (UXO) and other munitions at nonoperational training ranges
in the United States. This program is in its initial stage, and only a portion of
contaminated sites have been identified thus far. As DOD continues to identify
additional sites and investigate the extent of contamination, more information will
be available on the actions and costs that will be necessary to address the safety and
environmental hazards presented by UXO. The following sections explain the role
of EPA and the states in conducting oversight of DOD’s cleanup activities, indicate
cleanup status and costs, explain appropriations account structure, and discuss
cleanup efforts at overseas military installations.
Oversight of Cleanup Activities. While DOD is responsible for funding
and conducting cleanup actions at its sites, EPA and the states conduct oversight of
these actions to determine whether DOD complies with the law. Generally, EPA
takes the lead in performing oversight of DOD sites being cleaned up under
CERCLA, and EPA delegates federal authority to the states for conducting oversight
of corrective actions taken under RCRA. However, cleanup requirements under
CERCLA and RCRA apply only within the United States.
The cleanup of
contamination at overseas military installations is subject to requirements specified
within the Status of Forces Agreement with each host nation. These requirements are
generally not as strict as CERCLA and RCRA, and their stringency varies widely
from country to country. Unlike domestic cleanup actions, EPA does not have the
authority to conduct oversight at military installations abroad. Rather, overseeing
DOD’s actions to ensure that the requirements of a Status of Forces Agreement are
met is the responsibility of each host nation.
Cleanup Status and Costs. Until FY1994, DOD primarily concentrated its
cleanup efforts on identifying and investigating contaminated sites to determine the
level of remediation that would be necessary to protect human health and the
environment. As the majority of sites were identified and subsequent investigations
were completed, DOD began to focus the bulk of its efforts on actual cleanup. In
FY1996, DOD also developed specific cleanup goals to prioritize its sites, based on
threats of exposure. As indicated in Figure 2, DOD had identified a total of 29,696
contaminated sites as of the end of FY2002.6 As of that time, DOD had completed
cleanup at 20,491 of those sites (69% of total sites) at a cost of $20.2 billion, and
reported that almost $30.2 billion would be necessary to finish cleanup at the
remaining 9,205 sites (31% of total sites) from FY2003 to site completion.
Even though less than 1/3 of contaminated sites are still in need of cleanup, the
above estimates of future cleanup costs are substantially higher than has already been
spent due to the severity of contamination at these remaining sites and the resources
that likely will be necessary to address UXO contamination. DOD expects that
estimates of funding needs will likely increase in future years as additional sites with
UXO contamination are identified and the extent of such contamination is
determined. Funding needs for cleanup also may rise in future years as additional
military bases are selected for closure. The National Defense Authorization Act for
FY2002 (P.L. 107-107) authorized a new round of military base closings in 2005.
6 Department of Defense. Defense Environmental Restoration Program Annual Report to
Congress for FY2002.
April 2003. p. B-6-1, p. C-5-1.

CRS-5
The amount of funding that would be necessary to accelerate cleanup at new base
closure sites, and transfer them to other uses, would depend on the type and extent
of contamination present at such installations. Costs to accelerate cleanup could be
high if the bases selected for closure contain some of the more severely contaminated
sites that are on the NPL and are subject to cleanup under CERCLA.
Figure 2. Cleanup Status at Current, Former, and Closing Military
Installations in the United States as of September 30, 2002
Total Number of Sites = 29,696
31.0%
Response in Progress
9,205 Sites
Response Complete
20,491 Sites
69.0%
Prepared by the Congressional Research Service using data from the Department of Defense,
FY2002 Defense Environmental Restoration Program Annual Report to Congress,
April 2003, p. B-6-1, p. C-5-1.
Appropriations Account Structure. Cleanup costs at domestic military
sites are funded by several centralized accounts structured by category of installation.
Funding for cleanup at current and former military installations is authorized under
five Defense Environmental Restoration Accounts in the annual authorization bill for
National Defense, and is appropriated to these accounts in the annual appropriations
bill for the Department of Defense. Three of these accounts reserve funding for the
Army, Navy, and Air Force. One devotes funding to a more general category of
Defense-Wide sites, and another is dedicated to cleaning up Formerly Used Defense
Sites (FUDS).7 Typically, FUDS are sites on properties that DOD owned or leased
7 Congress first appropriated funding to the Defense Environmental Restoration Account in
FY1984. Subsequently, the National Defense Authorization Act for FY1997 (P.L. 104-201)
divided the account into four subaccounts: Army, Navy, Air Force, and Defense-Wide.
Since then, Congress also has specified the amount of funding reserved for cleaning up
FUDS sites, and the National Defense Authorization Act for FY2001 (P.L. 106-398)
established a FUDS subaccount to conform with this budgetary practice.

CRS-6
in the past and are now devoted to civilian uses. Many of the FUDS sites were used
during the World War II era and prior years.
The Department of Defense Appropriations Act for FY2003 (P.L. 107-248)
provided a total of $1.31 billion for all five Defense Environmental Restoration
Accounts, about $30 million more than the Administration’s request of $1.28 billion,
and nearly $40 million more the FY2002 funding level of $1.27 billion. The increase
in funding was reserved for improving the pace of cleanup at FUDS sites, which has
been criticized for proceeding more slowly than cleanup at currently active
installations. (Refer to page 22 for further discussion of P.L. 107-248.)
Cleanup at base closure sites is authorized separately under the Base
Realignment and Closure (BRAC) Account in the annual authorization bill for
National Defense. Appropriations for base closure activities are provided under the
BRAC account in the annual appropriations bill for Military Construction. Congress
authorized four rounds of base closures in 1988, 1991, 1993, and 1995, and
established a separate BRAC account for each round. These sites are separate from
former military properties, known as FUDS, which are discussed above. The
Military Construction Appropriations Act for FY2003 (P.L. 107-249) provided $561
million for the BRAC account, from which DOD allocated $540 million for cleanup
activities at base closure sites. This amount is about $69 million less than the
FY2002 cleanup allocation of $609 million. (Refer to page 23 for further discussion
of P.L. 107-249.)
Overseas Military Installations. As discussed above, there are several
centralized accounts to fund cleanup activities at domestic military installations.
However, there are no line-item accounts in the President’s annual budget
submission, or in annual defense authorization legislation or appropriations, to
conduct cleanup actions at overseas military installations. Rather, these projects are
funded on an installation-by-installation basis out of the general operational budget
for each foreign base, and DOD does not have the authority to transfer funding from
the cleanup accounts for domestic installations to address contamination abroad.
Further, DOD is not required to report to Congress on the status of cleanup actions
at overseas military installations, as the agency is required to do for domestic
facilities in its annual report on the Defense Environmental Restoration Program.
The only type of information that DOD is required to submit to Congress regarding
overseas cleanup is a statement of the amounts expended, and anticipated to be
expended, as part of its annual report to Congress on the Defense Environmental
Quality Program. The most recent version of this report indicated that DOD spent
a total of $19.6 million in FY2001 on overseas environmental cleanup. The report
also indicated that $13.1 million was available from appropriations in FY2002, and
that in FY2003, $18.2 million would be required for overseas cleanup obligations.8
8 Department of Defense. Defense Environmental Quality Program Annual Report to
Congress for FY2001.
September 2002. p. 29.

CRS-7
Environmental Compliance
DOD and all other federal agencies are required to comply with environmental
laws and regulations to the same extent as any other entity. Typically, environmental
compliance projects at military installations include routine operations such as
storing and disposing of solid and hazardous waste, upgrading and monitoring waste
water treatment plants, and testing and replacing underground storage tanks. The
following sections provide information on environmental compliance requirements
under federal law, examine funding trends for military compliance activities, and
indicate the amount of fines and penalties assessed against, and paid by, DOD for
environmental violations.
Compliance Requirements under Federal Law.
The federal
environmental statutes that most commonly apply to the military’s routine operations
include the Clean Air Act, Clean Water Act, Resource Conservation and Recovery
Act (RCRA), and Safe Drinking Water Act. The Federal Facility Compliance Act
of 1992 amended RCRA to clarify in detail that DOD and all other federal facilities
are subject to penalties, fines, permit fees, reviews of plans or studies, and inspection
and monitoring of facilities in connection with federal, state, interstate, or local solid
or hazardous waste regulatory programs.9 The Act also authorized and directed EPA
to take enforcement actions under RCRA against any federal agency to the same
extent that it would against any other entity. Although the Safe Drinking Water Act
includes similar language, other federal environmental laws do not include the same
clarification of compliance requirements.
Funding Trends. DOD did not begin to comprehensively track the amount
of funding spent on environmental compliance activities until FY1990. However,
there are no centralized accounts for these activities in annual defense authorization
legislation or appropriations bills, as there are for environmental cleanup activities.
Instead, funding for compliance primarily comes from the accounts for Operation and
Maintenance, Military Construction, and Procurement.
DOD’s budget for
environmental compliance has ranged from $790 million in FY1990 to a high of
$2.23 billion in FY1996. For FY2003, DOD allocated $1.75 billion for compliance
activities from the available accounts identified above, about $80 million more than
the FY2002 funding level of $1.67 billion. In the FY2003 budget request, DOD had
indicated that an increase in funding for compliance would be allocated primarily to
meet environmental requirements for certain Air Force activities, and to implement
waste water and drinking water treatment projects at the Massachusetts Military
Reservation in Falmouth, Massachusetts. The safety of drinking water has been an
ongoing concern among communities surrounding the reservation, since groundwater
contamination was discovered in private and municipal drinking water wells.
Fines for Violations of Environmental Requirements. Although DOD
is required to comply with environmental laws and regulations, and has a dedicated
budget for such activities, the extent to which DOD fulfills these responsibilities has
been a longstanding issue. As explained above, federal environmental laws require
federal facilities to comply with all federal, state, interstate, and local environmental
9 42 U.S.C. 6961

CRS-8
requirements, and such laws authorize EPA, the states, and local governments to
assess fines against DOD for violations. However, a fine is not always paid in the
same year that it is assessed, and in some cases, DOD does not make a cash payment
to satisfy a fine. Instead, DOD may agree to perform a Supplemental Environmental
Project (SEP) in lieu of a cash payment. Under such an agreement, DOD not only
corrects its actions to comply with the environmental requirement at hand, but also
performs an additional project that enhances environmental quality. Regulatory
agencies frequently prefer the performance of SEPs to cash payments due to the
environmental benefits reaped from such projects.
The National Defense Authorization Act for FY2000 required DOD to include
information on environmental fines in its annual report to Congress on the Defense
Environmental Quality Program.10 This information must include the amount of
fines assessed and paid during the fiscal year for which the report is submitted, as
well as the past four fiscal years. As indicated in Table 1, EPA, the states, and local
governments assessed $11.8 million in fines against DOD for environmental
violations from FY1997 to FY2001.11 During this same period, DOD paid $11.6
million in cash payments and SEPs as compensation for its violations.12
Table 1. Fines and Penalties Assessed and Paid for
Environmental Violations from FY1997 to FY2001
Fiscal Year
Fines and Penalties Assessed
Cash Paid and Cost of SEPs
FY1997
$2,627,828
$5,231,955
FY1998
$2,915,198
$157,920
FY1999
$982,224
$3,298,810
FY2000
$3,656,136
$156,100
FY2001
$1,638,688
$2,761,279
Total
$11,820,074
$11,606,064
Prepared by the Congressional Research Service with data from the Department of Defense.
Defense Environmental Quality Program Annual Report to Congress for FY2001.
September 2002. Appendix J. p. 19 and p. 23.
However, the total amount indicated above for assessed fines does not include
a penalty of $16 million that EPA raised against the U.S. Army in FY2000 for
violations of the Clean Air Act at Fort Wainwright in Alaska. The appropriateness
of the amount of the fine is currently in dispute, and it is the single largest penalty
that EPA has ever assessed against DOD for an environmental violation. EPA used
the criteria of “economic benefit of noncompliance” and “size-of-business” to
determine the amount of the fine, which are ordinarily applied to private businesses.
The Army argued that “because federal facilities receive their funds from
10 P.L. 106-65, Section 322.
11 Department of Defense. Defense Environmental Quality Program Annual Report to
Congress for FY2001
. September 2002. Appendix J. p. 19.
12 Ibid., Appendix J. p. 23.

CRS-9
appropriations and must spend the money for the purpose for which it was
appropriated, a federal facility cannot realize an economic benefit from non-
compliance.”13 The Army also argued that the size-of-business criteria should not be
applied, since military facilities are not net assets in the traditional sense and could
not be used as a financial resource to pay a fine. On April 30, 2002, the presiding
EPA administrative law judge rejected the Army’s arguments, and ruled that EPA
could apply the criteria of economic benefit of noncompliance and size-of-business
to the Army. The Army requested that the Environmental Appeals Board review this
decision.
Other Environmental Programs
In addition to environmental cleanup and compliance, DOD administers three
other programs that focus on pollution prevention, environmental technology, and
conservation. The purpose of the pollution prevention program is to reduce or
eliminate solid or hazardous waste from being generated and prevent environmental
problems before they occur. The environmental technology program supports
research, development, testing, and demonstration of more efficient and less costly
methods to clean up and manage solid and hazardous waste. The conservation
program aims to protect the natural, historical, and cultural resources of the 25
million acres of public land that DOD administers, including the protection of
endangered species.
DOD began tracking the budget for these programs in FY1993. Although these
programs are an integral part of DOD’s environmental strategy, their funding is
significantly smaller than the programs for environmental cleanup and compliance.
Like compliance, there are no centralized accounts for pollution prevention,
environmental technology, or conservation in annual defense authorization legislation
or appropriations bills. Instead, DOD allocates funding for these activities primarily
from the accounts for Operation and Maintenance, Procurement, and Research and
Development.
From FY2003 appropriations for the above accounts, DOD allocated a relatively
small increase in funding for conservation, but slightly decreased its budget for
pollution prevention and environmental technology.
For conservation, DOD
budgeted $160.3 million for FY2003, a $3.8 million increase above the FY2002
funding level of $156.5 million. The budget for pollution prevention declined by
$6.3 million from $226.1 million in FY2002 to $219.8 million in FY2003. For
environmental technology projects, DOD allocated $226.5 million for FY2003, a
$1.6 million decrease from the FY2002 budget of $228.1 million. While the overall
FY2003 budget for environmental technology declined slightly, DOD had indicated
in its FY2003 budget request that funding within the technology program would be
increased for developing new ways to detect and clean up UXO and other munitions.
The development of such technologies will likely be crucial in efforts to accurately
identify and assess contaminated sites under the new Military Munitions Response
Program, discussed earlier.
13 Ibid., Appendix K. p. 10.

CRS-10
Military Readiness Issues
A major issue associated with the implementation of DOD’s environmental
programs is the extent to which environmental requirements restrict military
readiness capabilities. While most federal environmental laws specify their
applicability to federal facilities, Congress included exemptions in several statutes
to ensure that military training needs would not be restricted to the extent that
national security would be compromised. 14 These exemptions provide the President
with the authority to suspend compliance requirements for actions at federal facilities
on a case-by-case basis. Such exemptions may be granted if doing so would be either
in the “paramount interest of the United States” or in the “interest of national
security”. Most of these exemptions are limited to one year, but can be renewed.
The Safe Drinking Water Act does not impose a time limit on exemptions from
compliance. Under the Endangered Species Act, a special committee “shall grant”
an exemption if the Secretary of Defense finds it necessary for national security. This
committee may place a time limit on an exemption, but it is not required to do so
under the law.
The adequacy of existing exemptions to meet national security needs has
become a controversial issue. DOD argues that existing exemptions are too onerous
and time-consuming to obtain on a case-by-case basis due to the vast number of
training exercises that it conducts on hundreds of military installations across the
country. DOD also argues that the time limitations placed upon most exemptions are
not compatible with many training activities, due to their ongoing or recurring nature.
Instead, DOD favors modifications to numerous environmental statutes that would
provide greater flexibility for conducting combat training and other readiness
activities without restriction or delay. However, some states and environmental
organizations have opposed such modifications and argue that existing exemptions
are sufficient to accommodate combat training needs.
The cumulative effect of environmental requirements on military readiness
capabilities is difficult to determine due to the lack of a system to comprehensively
track individual cases in which training has been restricted or compromised. The
General Accounting Office (GAO) has found that DOD’s readiness reports do not
indicate the extent to which environmental requirements restrict combat training
activities, and that such reports indicate a high level of readiness overall.15 However,
GAO noted individual instances of environmental encroachment at numerous
military installations, and in light of this fact, recommended that DOD’s reporting
14 Specific exemptions from compliance requirements for federal facilities are included in
the Clean Air Act [42 USC 7418(b)], Clean Water Act [33 USC 1323(a)], Comprehensive
Environmental Response, Compensation, and Liability Act [42 USC 9620(j)], Endangered
Species Act [16 USC 1536(j)], Noise Control Act [42 USC 4903], Resource Conservation
and Recovery Act [42 USC 6961(a)], and Safe Drinking Water Act [42 USC 300(j)(6)]. For
additional information, refer to CRS Report RS21217, Exemptions for Military Activities
in Federal Environmental Laws
, by Robert Meltz.
15 General Accounting Office. Military Training: DOD Needs a Comprehensive Plan to
Manage Encroachment on Training Ranges
. GAO-02-727T. May 2002. p. 2.

CRS-11
system be improved to more accurately identify any shortfalls in training that might
be attributed to restrictions imposed by environmental requirements.
Oversight hearings were held during the 107th Congress to examine the impact
of environmental requirements on military readiness, and this issue was debated in
legislation as well. The National Defense Authorization Act for FY2003 (P.L. 107-
314) included an interim exemption for military readiness activities from the
Migratory Bird Treaty Act. In addition to this exemption, the House had proposed
modifications to the Endangered Species Act, and a targeted exemption from the
Wilderness Act, which were not adopted in conference.
DOD had requested an exemption from the Migratory Bird Treaty Act as part
of a Readiness and Range Preservation Initiative (RRPI) submitted to Congress in
April 2002. DOD submitted its RRPI to Congress in response to concerns over the
perceived increase in training restrictions imposed by environmental requirements.
The initiative proposed targeted exemptions for military readiness activities from
certain requirements under five other statutes as well, including the Clean Air Act,
Comprehensive Environmental Response, Compensation, and Liability Act,
Endangered Species Act, Marine Mammal Protection Act, and Solid Waste Disposal
Act. DOD’s request for targeted exemptions from these five laws were not included
in the final FY2003 defense authorization bill. (Refer to page 17 for further
discussion of P.L. 107-314.)
DOD submitted its RRPI to Congress again in the spring of 2003, and it has
been subject to debate in FY2004 defense authorization legislation.16 Oversight of
the issue of environmental encroachment will likely continue in the future, as DOD
continues to balance military readiness needs with requirements to comply with
environmental laws.
Department of Energy
In the late 1980s, the United States ceased its production of radioactive
materials used in the construction of nuclear weapons due to military projections that
the nuclear weapons stockpile was sufficient to protect national security and respond
to future threats. However, environmental problems associated with producing and
storing these radioactive materials continue to pose a risk to human health and safety
today. Since the beginning of the U.S. atomic energy program, DOE and its
predecessors have been responsible for managing defense nuclear weapons and
related waste. In later years, DOE expanded its efforts to include the environmental
restoration of radioactive sites, and those with other hazardous contamination, to
ensure their safety for future uses. In 1989, the Bush Administration established an
Environmental Management Program within DOE to consolidate the agency’s efforts
16 For information on the debate of the RRPI in FY2004 defense authorization legislation,
refer to CRS Report RL31805, Authorization and Appropriations for FY2004: Defense, by
Amy Belasco and Stephen Daggett.

CRS-12
in cleaning up contamination from defense nuclear waste, as well as waste from
civilian nuclear energy research.17
The following sections discuss program oversight, cleanup status and costs,
appropriations, and related topics such as the selection of Yucca Mountain for an
underground nuclear waste repository, and the cleanup of smaller radioactive waste
sites that were transferred from DOE to the Army Corps of Engineers.
Oversight of Cleanup and Waste Management Activities
The Atomic Energy Act of 1954 is the primary authority governing the
management of defense nuclear waste. The law requires DOE to safely store,
process, transport, and dispose of radioactive and other hazardous waste resulting
from the production of defense nuclear materials.18 Waste disposal typically involves
cleanup actions, such as the decontamination of buildings and structures and the
removal of contaminated soil. DOE is also subject to requirements under various
federal environmental laws in carrying out its responsibilities under the Atomic
Energy Act. CERCLA and RCRA are the two main federal environmental statutes
that apply to cleanup activities at defense nuclear waste sites. CERCLA primarily
applies to cleanup actions at inactive waste sites which present the highest risk of
exposure and are listed on the NPL. RCRA requires DOE to clean up contamination
at sites with active solid and hazardous waste disposal facilities for which an
operating permit has been issued under RCRA. EPA and the states are responsible
for conducting oversight of DOE’s actions in order to determine compliance with
environmental laws and assess fines and penalties if violations occur. Generally,
EPA takes the lead in performing oversight of cleanup actions at DOE sites required
under CERCLA, and EPA delegates federal authority to the states for conducting
oversight of actions required under RCRA.
DOE has completed compliance
agreements with EPA and the states for each of its cleanup and waste management
sites, which specify schedules and time frames for specific response actions.19
Cleanup Status and Costs
The pace and cost of cleanup at defense nuclear waste sites has been a long-
standing issue. GAO has conducted numerous audits of DOE’s Environmental
Management Program, which in many cases have assessed cleanup schedules and
cost estimates as being overly optimistic. GAO’s assessment of DOE’s 1998 strategy
to accelerate cleanup concluded that cleanup schedules and estimates of funding
needs are sometimes inaccurate because they are based on project assumptions that
may change, such as the capacity to pack and ship vast quantities of waste for
disposal, cleanup levels that have yet to be finalized under regulatory agreements, the
17 For additional information, refer to DOE’s Web site at [http://www.em.doe.gov].
18 42 U.S.C. 2121
19
For information on each compliance agreement, refer to DOE’s Web site at
[http://www.em.doe.gov/compliance.html].

CRS-13
types of waste management and cleanup technologies that will be used, and the
exclusion of additional costly activities related to cleanup.20
Figure 3. Cleanup Status at DOE Nuclear Waste Management and
Environmental Restoration Sites as of September 30, 2002
Total Number of Sites = 114
34.2%
Response in Progress
39 Sites
Response Complete
75 Sites
65.8%
Prepared by the Congressional Research Service using data from the Department of Energy.
Office of Management, Budget, and Evaluation.
FY2004 Congressional Budget Request.
February 2003. Volume 5. p. 36.
As indicated in Figure 3, above, DOE reports that there are 114 large
geographic sites where the past production of atomic materials used to construct
nuclear weapons led to severe contamination.21 These sites encompass a total land
area of over 2 million acres, which is equal to the States of Rhode Island and
Delaware combined. As of the end of FY2002, DOE reports that it had completed
all response actions at 75 sites, at a cost of over $60 billion, and that response actions
were underway at the remaining 39 sites.22 DOE expects to complete cleanup at two
additional sites by the end of FY2003. While response actions are complete at about
66% of total sites, these sites are relatively small and are among the least hazardous.
The sites where cleanup is underway contain some of the most severely contaminated
areas. DOE estimates that cleanup at the remaining 39 sites may take 70 years to
complete, and that total cleanup costs may range from $220 billion to $300 billion
if program reforms are not initiated, substantially higher than the estimate of $147
20 General Accounting Office. Nuclear Waste: DOE’s Accelerated Cleanup Strategy Has
Benefits But Faces Uncertainties
. RCED-99-129. April 1999. 21 p.
21 Department of Energy. Office of Management, Budget, and Evaluation. FY2004
Congressional Budget Request
. February 2003. Volume 5, p. 36.
22 Ibid. One of the remaining sites, the Waste Isolation Pilot Plant in New Mexico, is a
waste disposal facility rather than a cleanup site that requires response actions.

CRS-14
billion made in 1998.23
DOE contends that these costs could be reduced by $50
billion to $100 billion through the use of risk-based approaches to accelerate cleanup
schedules. However, DOE’s past implementation of risk-based approaches has been
criticized as ineffective, and questions have been raised as to how these goals would
be accomplished without weakening environmental standards.
Appropriations Account Structure
Congress authorizes funding for DOE’s defense environmental restoration and
waste management activities in the annual authorization bill for National Defense,
and appropriates funding for them in the annual appropriations bill for Energy and
Water Development. Congress has traditionally provided this funding under three
centralized accounts. First, the Defense Environmental Restoration and Waste
Management Account funds cleanup and waste management activities at nuclear
weapons sites where all response actions are projected to continue beyond 2006.
Second, the Defense Facilities Closure Projects Account supports cleanup and waste
management activities at sites where all response actions are scheduled to be
complete by the end of 2006. Third, the Defense Environmental Management
Privatization Account reserves funding for cleanup projects that have been completed
under “privatization” contracts.24
The Consolidated Appropriations Resolution for FY2003 (P.L. 108-7) provided
a total of $6.72 billion for all three of the above accounts (including the 0.65%
across-the-board rescission), approximately $240 million more than the FY2002
funding level of $6.48 billion. The Administration had requested $6.91 billion for
FY2003 to support DOE’s defense environmental restoration and waste management
activities.
Of the $6.72 billion that Congress appropriated for FY2003, about $5.43 billion
was reserved for the Defense Environmental Restoration and Waste Management
Account, $1.13 billion was set aside for the Defense Facilities Closure Projects
Account, and $157 million was allocated to the Defense Environmental Management
Privatization Account. Congress did not approve DOE’s request to establish an
Environmental Management Cleanup Reform Account that would focus on risk
reduction to improve program efficiency and reduce costs.
While there have been ongoing concerns in Congress regarding the pace and
cost of cleanup, some Members expressed concern about how the funding for the
23 Department of Energy. A Review of the Environmental Management Program. February
2002. p. ES-1.
24 Under privatization contracts, a private entity is responsible for financing the entire cost
of a cleanup project, and is not paid by DOE until the project is completed and performed
according to contractually specified requirements. This type of contract differs from the
traditional approach of paying a contractor a fixed amount upfront and offering additional
cash incentives to encourage the completion of a project within a certain time frame.
Privatization contracts have the potential to provide the contractor with a greater incentive
to control costs, work more efficiently, and finish a project successfully, since payment is
not rendered until performance is complete and the cleanup objective has been achieved.

CRS-15
proposed reform account would have been allocated among various sites. There also
were concerns regarding how the goals of accelerated cleanup and reduced costs
would be accomplished without compromising environmental protection.
In
response to these concerns, Congress instead increased the Administration’s request
for the existing Defense Environmental Restoration and Waste Management Account
to honor letters of intent to accelerate cleanup that DOE had previously signed with
EPA and state regulators, the funding for which would be allocated according to
existing categories of sites. (For further discussion, refer to page 24.)
Yucca Mountain
A prominent issue related to DOE’s Environmental Management Program is the
perceived need for a long-term centralized repository for high-level defense nuclear
waste. While the Waste Isolation Pilot Plant in New Mexico serves as a centralized
repository for low-level and transuranic (plutonium-contaminated) defense nuclear
waste, high-level waste is currently stored at individual sites. Many interests have
argued that centrally storing high-level waste in a location that lacks a potential
pathway for immediate exposure would be safer and more secure from potential
terrorist threats. In response to such concerns, the Nuclear Waste Policy Act of 1982,
as amended in 1987, required DOE to study the suitability of Yucca Mountain in
Nevada for constructing an underground geological repository for high-level defense
nuclear waste, as well as civilian radioactive waste generated by nuclear power
plants. The federal government and the nuclear power industry contribute funding
to support the study and development of such a repository.
The State of Nevada has strongly opposed the selection of Yucca Mountain for
an underground repository due to numerous safety concerns, such as the possibility
of seismological disturbances and underground flooding, and the potential for
groundwater contamination over time.
DOE contends that scientific evidence
indicates that the conditions at Yucca Mountain would likely be suitable for long-
term underground waste storage and that efforts to study the site should continue.
Environmental organizations have opposed the development of a centralized
repository due to concerns over the safety of transporting high-level radioactive waste
across many states to one location and the potential for terrorist threats, along with
environmental concerns about the site that are similar to those of the State of Nevada.
Taking these concerns into consideration, President Bush recommended Yucca
Mountain for site selection on February 8, 2002. However, Nevada Governor Kenny
Guinn submitted a notice of disapproval to Congress on April 8, 2002, as permitted
under the Nuclear Waste Policy Act. The House passed a resolution (H.J.Res. 87)
on May 8, 2002, to overturn the “state veto”, and the Senate passed H.J.Res. 87 on
July 9, 2002. The President signed H.J.Res. 87 into law (P.L. 107-200) on July 23,
2002, clearing the way for DOE to proceed with its plans to prepare and submit a
license application to the Nuclear Regulatory Commission for the construction of a
nuclear waste repository at Yucca Mountain.
DOE plans to submit a license
application in 2004, and expects to begin receiving waste shipments in 2010. Despite
congressional approval, opponents of the development of Yucca Mountain may
attempt to halt or delay the project through other avenues, including the
appropriations process, oversight of the Nuclear Regulatory Commission’s review

CRS-16
of the license application for the site, and litigation over numerous aspects of the site
characterization and development process.25
Formerly Utilized Sites Remedial Action Program
In addition to the federal facilities that are being cleaned up under DOE’s
Environmental Management Program, there are other smaller sites contaminated with
low-level radiation from the processing and storage of uranium and thorium ores
during the early years of the U.S. nuclear weapons program from the 1940s to the
1960s. The majority of these sites were owned and operated by private contractors,
and cleanup at these sites is performed under the Formerly Utilized Sites Remedial
Action Program (FUSRAP). The Atomic Energy Commission, DOE’s predecessor
agency, established the program in 1974 under authorities provided in the Atomic
Energy Act, and actual cleanup began in 1979. In response to concerns over the pace
and cost of cleanup, Congress included provisions in the Energy and Water
Development Appropriations Act for FY1998 (P.L. 105-62) to transfer the FUSRAP
program to the Army Corps of Engineers. This transfer was considered potentially
advantageous since the Corps had extensive experience in cleaning up hazardous
waste at former defense sites that were in operation during this same time period.
Figure 4. Cleanup Status under the Formerly Utilized Sites
Remedial Action Program as of June 2003
Total Number of Sites = 49
Response in Progress
24 Sites
49.0%
Response Complete
25 Sites
51.0%
Prepared by the Congressional Research Service using data from the U.S. Army Corps of
Engineers. Formerly Utilized Sites Remedial Action Program Update. June 2003. p. 2.
25 For further information on this issue, refer to CRS Issue Brief IB92059, Civilian Nuclear
Waste Disposal
, by Mark Holt.

CRS-17
The Energy and Water Development Appropriations Act for FY1999 (P.L. 105-
245), requires the Corps to follow CERCLA’s requirements in cleaning up sites
under the program. DOE collaborates with the Corps to determine the eligibility of
new sites, since it must perform the historical research to ascertain whether such sites
were part of the early nuclear weapons program. Once all response actions at a site
are complete, the Corps is responsible for monitoring and maintaining cleanup
remedies for 2 years. After that time, the site is transferred back to DOE for
continuing any necessary monitoring and maintenance.
As indicated in Figure 4 above, the Corps reports that a total of 49 sites have
been identified with contamination requiring response actions. Cleanup is complete
at 25 of these sites, and is underway or planned at the remaining 24 sites.26 Before
FY1998, cleanup at these sites was funded out of available funds under DOE’s
Defense Environmental Restoration and Waste Management Account, and the prior
Atomic Energy Defense Activities Account. Since the creation of a dedicated
account for FUSRAP and transfer of the program to the Corps in FY1998, Congress
has provided approximately $140 million in annual funding. The Consolidated
Appropriations Resolution for FY2003 (P.L. 108-7) provided $144 million for the
FUSRAP program, about $3 million more than the Administration’s request of $141
million, and about $4 million more than the FY2002 funding level of $140 million.
Authorizing Legislation for FY2003
The second session of the 107th Congress completed consideration of legislation
to authorize funding for national defense programs in FY2003. This legislation, the
Bob Stump National Defense Authorization Act for FY2003 (P.L. 107-314, H.R.
4546) included authorization of funding for environmental programs administered
by DOD and for the management and cleanup of defense nuclear waste administered
by DOE. Major environmental provisions of this law are discussed below.
Department of Defense
P.L. 107-314 authorized specific funding levels for the cleanup of
environmental contamination at current, former, and closing military installations.
However, there are no line-item accounts for DOD’s other environmental activities,
including compliance, pollution prevention, environmental technology, and
conservation. Funding for these activities was authorized as part of the Operation
and Maintenance, Procurement, and Research and Developments Accounts. The law
also includes several other environmental provisions, which address military
readiness issues, natural resource conservation, procurement practices, and the use
and disposal of obsolete naval vessels.
Environmental Cleanup. Section 301 of P.L. 107-314 authorized a total of
$1.32 billion for environmental cleanup at current and former military installations.
26 U.S. Army Corps of Engineers. Formerly Utilized Sites Remedial Action Program
Update
. June 2003. p. 2. For further information, refer to the Army Corps of Engineers
web site at [http://www.hq.usace.army.mil/cecw/fusrap].

CRS-18
This amount is approximately $40 million more than Administration’s FY2003
request of $1.28 billion and is about $50 million more than the FY2002 funding level
of $1.27 billion. The increase in authorization was devoted to the cleanup of FUDS
sites. The pace of cleanup at these sites has been an ongoing concern, since cleanup
activities have historically proceeded more slowly than at currently active
installations. Regarding the use of defense funds for cleanup, Section 313 requires
the Secretary of Defense to fund environmental cleanup projects only with
environmental restoration funds, and not as military construction projects.
Section 2404 authorized $565 million for base closure activities, which includes
the cleanup of environmental contamination at such sites. This amount is $20
million more than the Administration’s FY2003 request of $545 million, and is $68
million less than the enacted FY2002 appropriation of $633 million. The conference
report indicated that the increase in authorization above the request is only to be used
for environmental cleanup, rather than general activities related to closure. For the
sake of clarity, there also appears to be conflicting language in the conference report
regarding the amount authorized for base closure activities.
Although report
language indicates an amount of $561 million, the law specified $565 million, which
would be the actual authorization since it is stipulated in statutory language.
In addition to comprehensive funding for cleanup at military facilities, Section
301 authorized the requested amount of $25 million for the Kaho’olawe Island
Conveyance, Remediation, and Environmental Restoration Trust Fund. DOD ceased
its use of Kaho’olawe Island as a training range in 1995, and subsequently returned
the land to the State of Hawaii. The trust fund provides support for environmental
cleanup and the removal of UXO and other munitions.
Related to the cleanup of UXO in general, Section 312 requires the Secretary
of Defense to establish a program manger who will serve as the single point of
contact for policy and budgeting issues involved in characterizing, remediating, and
managing UXO and other munitions at defense sites. The conferees also included
report language which directs DOD to submit a consolidated budget proposal for
each of the next four fiscal years on the amount of funding that would be necessary
to address the environmental impacts of UXO. As discussed earlier, DOD has
established a Military Munitions Response Program to address the cleanup of UXO.
DOD is in the process of identifying contaminated sites and estimating the amount
of funding that will be necessary for environmental restoration.
Military Readiness Issues.
The extent to which environmental
requirements restrict or delay military readiness activities was a significant issue in
the debate over H.R. 4546. As discussed earlier, DOD requested exemptions from,
or modifications to, several environmental statutes as part of a Readiness and Range
Preservation Initiative submitted to Congress in April 2002. DOD argued that certain
exemptions and modifications are needed to provide greater compliance flexibility,
in order to prevent environmental requirements from imposing restrictions on
military readiness capabilities. Some Members of Congress, certain states, and
numerous environmental organizations opposed the initiative and argued that existing
exemption authorities are adequate to protect training needs.

CRS-19
In passing H.R. 4546, the House approved an exemption from the Migratory
Bird Treaty Act and modifications to the Endangered Species Act, which were
requested as part of DOD’s proposed initiative. The House also approved a targeted
exemption from the Wilderness Act for military overflights on the Utah Test and
Training Range. The Senate did not propose any environmental exemptions in
passing its version of the bill. The conference committee on H.R. 4546 did not adopt
the provisions regarding the Endangered Species Act or the Wilderness Act, but did
approve a modified version of the exemption from the Migratory Bird Treaty Act,
which is contained in Section 315 of P.L. 107-314.27
Conflicts between military training needs and the protection of migratory birds
arose as a result of a federal court ruling, which indicated that the Navy had violated
the Migratory Bird Treaty Act by incidentally taking migratory birds without a permit
during training exercises in Guam. The Migratory Bird Treaty Act was established
to control the mass slaughter of migratory birds for commercial purposes and to
promote the sustainable management of such birds.28
The law authorizes the
Secretary of the Interior to regulate the taking of migratory birds, but current
regulations may only authorize permits for intentional takings for specific purposes,
such as hunting within designated seasons as well as numerous other activities.
To address the lack of permit authority for incidental takings and prevent
possible restrictions on training in the future, Section 315 of P.L. 107-314 requires
the Secretary of the Interior to “prescribe” regulations, within one year of enactment,
that would exempt military readiness activities from the protections under the
Migratory Bird Treaty Act.
The conference report did not explain whether
“prescribe” means propose or finalize, however, it appears that “prescribe” means
final promulgation of the regulations, when the section is read as a whole. The law
defines readiness activities as all training and operations of the Armed Forces that are
related to combat, as well as the adequate and realistic testing of military equipment,
vehicles, weapons, and sensors for proper operation and suitability for combat use.
While the new regulations are being developed, the law grants an interim
exemption from the Migratory Bird Treaty Act in order to allow any potentially
affected training operations to proceed. During the interim period, the Secretary of
Defense is required to consult with the Secretary of the Interior to monitor, minimize,
and mitigate any adverse impacts on migratory birds, whenever practicable. Interim
exemption authority will expire when the new regulations become effective and all
litigation challenging them has been resolved. To restrict the amount of time during
which legal challenges could be raised, the law limits judicial review by a federal
court to 120 days from the date that the regulations are published.
Although P.L. 107-314 does not include modifications to the Endangered
Species Act, the conference report on H.R. 4546 expressed concern that designating
additional critical habitat areas on training ranges could adversely affect military
27 For a legal analysis, refer to CRS Report RL31415, The Endangered Species Act,
Migratory Bird Treaty Act, and Department of Defense Readiness Activities: Current Law
and Legislative Proposals
, by Pamela Baldwin.
28 16 U.S.C. 703 et. seq.

CRS-20
readiness capabilities. The House originally would have amended the Endangered
Species Act to prohibit the designation of new critical habitat areas on military
installations for which an Integrated Natural Resource Management Plan (INRMP)
has been approved under the Sikes Act, if the plan “addresses special management
considerations or protection”.29 The conferees expressed their support for the level
of cooperation between DOD and the Department of the Interior to prepare effective
INRMPs to protect threatened and endangered species, and indicated their concerns
about questions as to whether INRMPs provide sufficient protection to eliminate the
need for further critical habitat designations.
The conferees encouraged the
Department of the Interior and DOD to cooperate in the management of natural and
cultural resources on military lands, and directed the Secretary of Defense to
recommend legislative proposals to accomplish these goals.
Procurement Practices. Various laws, regulations, and executive orders
require federal agencies to procure recycled or environmentally preferable items
whenever it is practical to do so. Section 314 requires the Secretary of Defense to
establish a tracking system to identify the extent to which the Defense Logistics
Agency procures items that are environmentally preferable or are made with
recovered materials. This provision also requires the Secretary of Defense to assess
the need for training and educating military personnel to ensure that they are aware
of any requirements, preferences, or goals for the procurement of environmentally
preferable items, or those made with recovered materials. Related to procurement,
Section 827 authorizes multi-year authority for procuring services related to the
cleanup of environmental contamination on military installations. Since, many types
of cleanup remedies are long-term actions, multi-year authority is often more
practical than annual authorizations.
Natural Resource Conservation. P.L. 107-314 includes two natural
resource conservation provisions that address the impacts of land development on
military installations. In many areas, wildlife populations have increased on military
lands as surrounding open spaces and habitat have diminished due to property
development. DOD argues that environmental requirements to protect endangered
and threatened species have risen as a consequence, and that such requirements have
placed limitations on the use of certain lands. To prevent further land development
and help ease the burden of habitat preservation on military lands, Section 2811
authorizes the Secretary of Defense to enter cooperative agreements with states and
private entities to acquire or obtain interest in nearby properties to preserve open
space and protect critical habitat. Such properties would serve as a buffer to help
eliminate or relieve restrictions on training, testing, or other operations, that might
otherwise be imposed if the availability of open space and wildlife habitat were
limited to military lands due to surrounding property development. To meet this
same objective, Section 2812 authorizes the Secretary of Defense to convey surplus
29 As amended in 1997, the Sikes Act (16 U.S.C. 670a) requires DOD to develop an INRMP
for each military installation in the United States, unless the Secretary of Defense
determines that the absence of significant natural resources on a particular installation
makes the preparation of such a plan inappropriate. The law requires DOD to cooperate
with the U.S. Fish and Wildlife Service and state fish and wildlife agencies in the
preparation of these plans to reach a mutual agreement on the conservation, protection, and
management of fish and wildlife resources.

CRS-21
property to state or local governments, or non-profit conservation organizations, to
preserve open space or natural resources in perpetuity.
Use and Disposal of Obsolete Naval Vessels. Section 3504 authorizes
financial assistance to states for preparing obsolete vessels from the National Defense
Reserve Fleet for use as artificial reefs. The law does not specify how much funding
is authorized, and the amount of assistance would depend on the availability of
appropriations. Eligible activities include removing hazardous materials from a
vessel, towing it to the target location, and sinking it. The amount of assistance
awarded to a state would depend on numerous factors, such as the cost-effectiveness
of “reefing” a vessel compared to other disposal options. No later than September
30, 2003, the Maritime Administration and EPA are required to jointly develop
environmental best management practices to serve as a national guideline for
preparing vessels as artificial reefs. In addition to the use of artificial reefs as a
disposal option, Section 3504 directs the Maritime Administration to carry out a pilot
program to explore alternatives for exporting obsolete naval vessels abroad to be
dismantled and recycled. The Maritime Administration already has the authority to
export vessels for these purposes, and the pilot program is intended to identify more
effective and safer practices for disposal abroad.
Department of Energy
Section 3101 authorized a total of $6.76 billion for DOE’s management of
defense nuclear waste and cleanup of contaminated nuclear weapons sites. The
authorization is about $150 million less than the Administration’s amended request
of $6.91 billion, and is approximately $280 million more than the FY2002
appropriation of $6.48 billion. Of the authorization of $6.76 billion, approximately
$4.51 billion was reserved for the Defense Environmental Restoration and Waste
Management Account, nearly $1.11 billion was allocated to the Defense Facilities
Closure Projects Account, and about $158 million was aside for the Defense
Environmental Management Privatization Account.
The remaining authorization of $982 million was devoted to a new Defense
Environmental Management Cleanup Reform Account.
This amount is
approximately $100 million less than the Administration’s amended request of $1.1
billion. However, Congress chose not appropriate any funding for this account in the
Energy and Water Development Appropriations Act for FY2003, as discussed on
page 24. As noted earlier, the Administration had requested funding for this account
to support a new initiative that would accelerate cleanup schedules and reduce costs.
Although there have been long-standing concerns over the pace and cost of cleanup
at defense nuclear waste sites, some Members of Congress criticized DOE for not
providing adequate information on how the goals of accelerated cleanup and lowered
costs would be achieved under this initiative. There also were concerns regarding
how these goals could be attained without weakening cleanup standards or other
environmental protections.
While Congress chose not to appropriate any funding for the newly authorized
account primarily due to the above concerns, appropriations were increased for the
existing Defense Environmental Restoration and Waste Management Account to
support efforts at sites where DOE had already signed letters of intent with EPA and

CRS-22
state regulators to work toward the acceleration of cleanup. In distributing cleanup
acceleration funds among the sites, Section 3145 of P.L. 107-314 requires the
Secretary of Energy to submit a Performance Management Plan to Congress for each
affected site prior to the allocation of funds. Once allocated to a site, funds could not
be obligated or expended until 30 days after the Secretary of Energy submits to
Congress a description of the activities to be carried out under the Performance
Management Plan. To provide opportunities for additional oversight, Section 3179
requires the Secretary of Energy to submit a report to Congress on the progress of
activities to accelerate the reduction of environmental risks at defense nuclear waste
sites that have helped to increase the pace of cleanup and reduce costs. The law
directs the Secretary to submit this report along with DOE’s budget justification for
FY2004.
Appropriations for FY2003
In addition to authorizing funding for FY2003, the second session of the107th
Congress completed consideration of the two appropriations bills that fund DOD’s
environmental programs.
The Department of Defense Appropriations Act for
FY2003 (P.L. 107-248, H.R. 5010) provided funding for environmental cleanup at
current and former military installations, as well as numerous other environmental
activities. The Military Construction Appropriations Act for FY2003 (P.L. 107-249,
H.R. 5011) provided funding for the cleanup of environmental contamination at
military base closure sites. The 107th Congress did not complete action on FY2003
appropriations for DOE’s management and cleanup of defense nuclear waste. Final
appropriations for these activities were enacted early in the 108th Congress under the
Consolidated Appropriations Resolution for FY2003 (P.L. 108-7, H.J.Res. 2).
Defense-related environmental provisions in each law are examined below.
Department of Defense
The Department of Defense Appropriations Act for FY2003 (P.L. 107-248, H.R.
5010) provided specific funding levels for environmental cleanup activities, but as
in defense authorization legislation, there are no comprehensive line-item accounts
for DOD’s other environmental activities, including compliance, pollution
prevention, conservation, and environmental technology. As discussed earlier, DOD
determined its FY2003 budget for these programs mostly from funds appropriated
to the accounts for Operation and Maintenance, Procurement, and Research and
Development.
P.L. 107-248 provided a total of $1.31 billion for the cleanup of environmental
contamination at current and former military installations, about $6 million less than
the enacted authorization of $1.32 billion, approximately $30 million more than the
Administration’s request of $1.28 billion, and nearly $40 million more than the
FY2002 funding level of $1.27 billion. The increase was to be devoted to increasing
the pace of cleanup at FUDS sites, which has been criticized for proceeding more
slowly than cleanup at currently active installations. The law provided an additional
$75 million to clean up unexploded ordnance on Kaho’olawe Island in Hawaii, $50
million more than the enacted authorization and the Administration’s request of $25

CRS-23
million. The law provided another $10 million to mitigate the environmental impacts
of military activities on Indian lands, the same as the Administration requested.
On a cleanup-related matter, the law limits the use of “indefinite
delivery/indefinite quantity” contracts to no more than 35% of the total funding
obligated for environmental cleanup projects in FY2003. The law also includes
another environmental provision that prohibits the use of FY2003 funds to upgrade
the 939th Combat Search and Rescue Wing of the Air Force Reserve, until the
Secretary of the Air Force certifies to Congress that certain conditions are met.
Among these conditions are the requirement that any new aircraft assigned to the unit
must comply with local environmental and noise standards.
The law does not include two environmental provisions that were considered
during the debate over H.R. 5010. First, the law does not include the Senate
provision that would have provided up to $2.5 million to dispose of sediments at
inland sites from dredging operations at Earle Naval Station in New Jersey.
Sediments from dredging operations are typically disposed of in the ocean, due to the
comparatively high costs of inland disposal. Interest in inland disposal has been
rising due to concerns over the potentially adverse effects of ocean disposal on
coastal water quality. Second, the law does not include the House provision that
would have established a commission to assess the “adverse impacts” of
encroachment factors, including environmental requirements, on military training.
Military Construction
The Military Construction Appropriations Act for FY2003 (P.L. 107-249, H.R.
5011) allocated $561 million to the BRAC account for base realignment and closure
activities in the United States, $4 million less than the enacted authorization of $565
million, and about $72 million less than the FY2002 enacted appropriation of $633
million. The Administration had requested $545 million. Funding under this
account includes support for the cleanup of environmental contamination in order to
prepare these properties for transfer to other uses. Of the enacted appropriation of
$561 million, $20 million was reserved for a new Environmental Cleanup
Acceleration Initiative to address the backlog of
environmental remediation
requirements that have not been met. The funding for the initiative was to be
allocated accordingly: $11 million to the Navy, $6 million to the Air Force, and $3
million to the Army.
As in FY2002, the law does not place a limitation on how much funding can be
spent on environmental cleanup. Prior to FY2002, Congress had traditionally placed
a limitation on environmental cleanup funding under the BRAC account. The
departure from this practice is intended to provide DOD with greater flexibility in
allocating funding for cleanup needs. For FY2003, DOD allocated $540 million for
environmental cleanup from the available appropriation of $561 million for the
BRAC account, which is about $69 million less than the amount of $609 million
allocated from the FY2002 BRAC appropriation of $633 million. Related to cleanup
funding, the law directs DOD to accurately reflect the anticipated costs of
environmental restoration, waste management, and compliance activities in future
budget requests for base closure activities. This provision was included to address

CRS-24
the issue of funding needs for environmental activities that DOD had not adequately
identified in previous budget submissions.
In addition to specifying funding for base closure activities, the law includes a
provision which provides greater flexibility for the payment of environmental
cleanup costs associated with the upkeep of certain types of military housing. The
law limits the cost of maintaining and repairing general and flag officer quarters to
$35,000 per unit annually, unless Congress is notified 30 days in advance that costs
will exceed this amount.
However, if the additional costs are solely for
environmental cleanup activities that could not be reasonably anticipated at the time
of the budget submission, the law authorizes DOD to notify Congress of the
additional costs “after-the-fact”. Providing an exception from early notification
requirements for unforseen environmental costs could help to ensure that cost
limitations do not prevent DOD from taking timely action to comply with
requirements to remove hazardous materials or reduce the threat of exposure.
Energy and Water Development
The Consolidated Appropriations Resolution for FY2003 (P.L. 108-7, H.J.Res.
2) provided a total of $6.72 billion for all three accounts that support DOE’s defense
nuclear waste management and cleanup activities (including the 0.65% across-the-
board rescission). The FY2003 appropriation is approximately $4 million less than
the enacted authorization of $6.76 billion, $190 million less than the
Administration’s request of $6.91 billion, but $240 million more than the FY2002
funding level of $6.48 billion. Of the amount of $6.72 billion enacted for FY2003,
approximately $5.43 billion was allocated to the Defense Environmental Restoration
and Waste Management Account, $1.13 billion was set aside for the Defense
Facilities Closure Projects Account, and the remaining $157 million was reserved for
the Defense Environmental Management Privatization Account.
As discussed earlier, Congress did not appropriate any funding for DOE’s
proposed Environmental Management Cleanup Reform Account, which was
authorized in the National Defense Authorization Act for FY2003. Instead, Congress
increased funding for the existing Defense Environmental Restoration and Waste
Management Account by $926 million above the Administration’s request of $4.54
billion, in order to honor the letters of intent to accelerate cleanup that DOE had
already signed with EPA and state regulators. The increase was to be allocated
according to the existing structure of site categories within the account.
Many concerns were raised about the Administration’s cleanup reform initiative
during the FY2003 appropriations debate. DOE would have budgeted the majority
of the funding for the proposed account by decreasing support for cleanup at sites that
are funded under the Defense Environmental Restoration and Waste Management
Account. Under this approach, funding would have been restored at these sites only
if compliance agreements with EPA and the states were renegotiated to accelerate
cleanup schedules and project milestones.
DOE contends that many of the requirements under its existing compliance
agreements are too costly, ineffective, and unnecessarily time-consuming, and that
its agreements need to be re-examined to explore ways to increase the pace of

CRS-25
cleanup and reduce costs. Questions were raised as to whether EPA and the states
might agree to weaker cleanup standards, rather than face the possibility of losing
funding that site managers need to fulfill existing agreements. While DOE signed
letters of intent with EPA and state regulators to accelerate cleanup at its major sites,
Performance Management Plans had not been developed for all sites to establish how
cleanup would be accelerated while ensuring that environmental protection is not
compromised.
Similar to provisions in the National Defense Authorization Act for FY2003,
Section 315 of P.L. 108-7 indicates that none of the funding for environmental
management activities may be obligated at individual sites that would be in excess
of the amount obligated in FY2002 or requested for FY2003, whichever is greater,
unless a Performance Management Plan has been completed for that site that is
consistent with the intent of DOE’s environmental management and cleanup reform
initiative.
In addition to funding for DOE, P.L. 108-7 also appropriated $144 million for
the FUSRAP program, administered by the Army Corps of Engineers. This amount
is $3 million more than the Administration’s request of $141 million, and is $4
million more than the FY2002 funding level of $140 million. As discussed earlier,
the FUSRAP program addresses low-level radioactive contamination at sites that
were primarily owned by private contractors who processed and stored uranium and
thorium ores during the early years of the U.S. nuclear weapons program.
Selected References
Department of Defense. Defense Environmental Quality Program Annual Report to
Congress for FY2001. September 2002.
Department of Defense. Defense Environmental Restoration Program Annual
Report to Congress for FY2002. April 2003.
Department of Defense. Operation and Maintenance Overview for FY2004. April
2003.
Department of Energy. A Review of the Environmental Management Program.
February 2002.
General Accounting Office. Waste Cleanup: Status and Implications of DOE’s
Compliance Agreements. GAO-02-567. May 2002.
General Accounting Office. Military Training: DOD Needs a Comprehensive Plan
to Manage Encroachment on Training Ranges. GAO-02-727T. May 2002