Civil responsibilities of the U.S. Army Corps of Engineers (USACE) include undertaking federal water resource development projects and assisting nonfederal environmental infrastructure (EI, typically municipal water and wastewater) projects, among others. This report discusses the processes for USACE projects and assistance.
Authorization and Appropriations. Congress often considers new USACE authorization legislation biennially and discretionary USACE appropriations annually. The authorization bill is typically titled a Water Resources Development Act (WRDA). After inclusion of a study, project, project modification, or EI assistance authorization in an enacted WRDA, USACE action on the authorization usually requires federal funding. Congress typically funds a subset of the authorized USACE EI activities through annual Energy and Water Development appropriations acts.
Federal Water Resource Projects. USACE develops federal water resource projects principally to (1) improve navigable channels, (2) reduce flood risks along rivers and coasts, and (3) restore aquatic ecosystems. These federal projects may have additional project benefits; for example, some multipurpose projects may serve water supply storage, hydropower, and recreation purposes, among others.
Standard Process for |
Source: Congressional Research Service. |
The standard process for a USACE project consists of four phases: study, design, construction, and operations, as shown in the figure. This process generally requires two separate congressional authorizations—one for studying feasibility and a subsequent one for undertaking the project (e.g., construction)—as well as appropriations for each phase. An exception to the required two-authorization process is smaller projects (i.e., typically projects with a federal cost less than $15 million) that can be performed under USACE's continuing authorities programs; these projects also largely follow the process described in this report.
For most activities, Congress requires a nonfederal sponsor to share some portion of study and construction costs and to provide the necessary real estate interests for the project (e.g., lands, rights-of-way). The standard study and construction cost-share requirements vary by project type.
Assistance for Nonfederal Environmental Infrastructure. In addition to authorizing federal water resource projects, Congress has authorized USACE to assist with the design and construction of certain nonfederal publicly owned and operated water-related infrastructure (i.e., EI assistance). WRDAs have contained EI assistance authorizations mostly related to water distribution works, stormwater management, surface water protection, and environmental restoration in specified municipalities, counties, and states. Following authorization, appropriations for EI assistance are required before USACE can proceed, generally at a 75% federal cost share. USACE provides assistance typically by contracting for design and/or construction work of the nonfederal project.
The U.S. Army Corps of Engineers (USACE) is an agency within the Department of Defense with both military and civil works responsibilities. As part of USACE's civil works responsibilities, the agency undertakes federal water resource projects that are authorized and funded by appropriations acts passed by Congress. Figure 1 describes the three primary purposes of most federal water resource projects performed by USACE—navigation, flood risk management, and aquatic ecosystem restoration. In addition to one of these three primary purposes, USACE projects may have additional benefits; for example, some multipurpose projects may serve water supply storage, hydropower, and recreation purposes, as well as one or more of the three primary USACE project purposes. In legislation since 1992, Congress has authorized USACE to provide assistance to nonfederal, public environmental infrastructure (EI) projects, consisting primarily of design and construction of municipal water and wastewater infrastructure; this USACE assistance for others' projects is not shown in Figure 1, which is focused on USACE projects' primary purposes.
The Assistant Secretary of the Army for Civil Works (ASACW) provides civilian oversight of USACE's civil works projects. A military Chief of Engineers commands USACE's civil and military operations. The agency's responsibilities are organized into regional divisions, which are further divided into local districts.1 Many of the districts and divisions perform both military and civil works activities and are led by Army officers.2
Congress typically legislates on authorization of most USACE federal water resource projects and USACE assistance for nonfederal EI through Water Resources Development Acts (WRDAs).3 Congress often considers a WRDA biennially. Appropriations are typically provided through annual Energy and Water Development appropriations acts and are at times provided through supplemental appropriations acts.
This report summarizes the processes for both USACE federal water resource projects and USACE assistance for nonfederal EI.4 After a primer on the range of USACE activities and their characteristics, this report discusses the process for USACE to
USACE's water resource activities have evolved with the changing needs of the nation. In the 19th century, Congress first authorized USACE to undertake federal projects to improve navigation channels, thereby facilitating the movement of goods between states and for import and export. In the mid-20th century, Congress began charging the agency to undertake congressionally authorized projects to reduce the damages from riverine floods and coastal storms. Since the 1990s, Congress has authorized USACE to undertake federal projects to restore aquatic ecosystems. Local stakeholders and Members of Congress often are particularly interested in USACE pursuing a federal water resource project, because these projects can have significant local and regional economic benefits and environmental effects. The agency typically works with nonfederal project sponsors in the development of these federal water resource projects. The nonfederal demand for USACE projects and congressional authorization of these projects often exceed available federal appropriations for USACE to complete construction on all authorized projects. In addition to studying and constructing projects, USACE operates and maintains various types of assets. For example, USACE operates more than 700 federally owned dams and improves and maintains roughly 25,000 miles of navigable waterways, channels, and harbors.5
While USACE civil works projects and authorities have been concentrated on three principal purposes—navigation, flood risk management, and aquatic ecosystem restoration—some USACE activities may support additional purposes, such as water supply storage (e.g., for agricultural use or municipal and industrial use), hydroelectric generation, fish and wildlife, and recreation. The most common way that USACE infrastructure supports water supply is through storage at a USACE reservoir.6 Congress passed the Grace F. Napolitano Priority for Water Supply, Water Conservation, and Drought Resiliency Act of 2024, as Title I, Subtitle B, of Division A of the Thomas R. Carper Water Resources Development Act of 2024 (WRDA 2024; P.L. 118-272). The act's water supply provisions included a declaration of U.S. policy for USACE to maximize opportunities for water supply and conservation measures and drought resilience efforts at and in the operation of the agency's water resource projects. The act also directed the Secretary of the Army to give full consideration to requests and proposals by nonfederal sponsors for USACE to use its authorities to further such measures and efforts in alignment with the authorized purposes of the agency's projects. WRDA 2024 also authorized USACE to conduct specific single-purpose water supply feasibility studies (e.g., to assess the feasibility of USACE projects with water supply as the studies' only purpose, rather than water supply as part of a multipurpose study).7 How implementation of the act may affect USACE water supply activities remains to be seen.
In legislation since 1992, Congress has authorized and funded USACE to assist with the design and construction of certain publicly owned and operated water-related infrastructure (i.e., EI assistance). EI assistance is mostly related to projects for water supply and distribution, stormwater management, surface water protection, and environmental restoration, among other purposes. These projects typically are authorized for specified municipalities, counties, or states. Local interests and Members of Congress often pursue cost-shared USACE EI assistance as an alternative to applying for assistance from other federal programs.
The USACE civil works mission also encompasses the agency's regulatory activities pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) and the Rivers and Harbors Act of 1899 (33 U.S.C. §403),8 as well as the agency's administration of the Formerly Utilized Sites Remedial Action Program (FUSRAP). Through FUSRAP, USACE remediates radiological contamination at nonfederal sites that were used during the early years of the U.S. nuclear weapons program.9 Neither FUSRAP nor USACE regulatory activities are addressed in this report. USACE also has authorities to provide technical assistance; these authorities are largely beyond the scope of this report. This report focuses on the processes for USACE federal water resource projects and USACE assistance for nonfederal EI, rather than these other roles and responsibilities.
USACE implements federal water resource projects for navigation, flood risk management, aquatic ecosystem restoration and for other purposes associated with these projects (e.g., recreation, water supply storage, hydropower). These various federal projects, regardless of which purpose they serve, often follow fairly similar processes for their development and authorization. In contrast, USACE's EI assistance is for work on nonfederal projects; as a result, much of the process for EI assistance is distinct from the process for USACE federal water resource projects. Figure 2 depicts some basic differences in the authorization processes for federal projects and assistance with nonfederal EI projects. USACE implements federal water resource projects pursuant to either project-specific congressional authorizations or without additional congressional authorization for smaller projects (i.e., often less than $15 million of federal costs) under preexisting CAP authorities. For assistance with nonfederal EI projects, Congress must authorize USACE to perform the assistance; that is, Congress authorizes not the nonfederal projects themselves but the assistance for certain nonfederal projects that qualify under the authority. EI assistance authorizations specify the types of projects that may receive assistance and the eligible geographic location of projects. Table 1 provides information on various characteristics for federal water resource projects, small federal water resource projects under CAPs, and EI assistance.
Figure 2. Congressional Authorization for USACE Federal Projects and USACE Assistance for Nonfederal Environmental Infrastructure |
Source: Congressional Research Service. |
Table 1. Characteristics of USACE Federal Water Resource Projects and Assistance for Nonfederal Environmental Infrastructure
(typical characteristics are shown; exceptions may apply for some nonfederal sponsors)
Characteristic |
Federal Water Resource Project |
Small Projects Under CAPs |
Assistance for Nonfederal EI |
Minimum authorization action by Congress |
Study authorization and |
None for projects within a CAP; most CAPs have limits for annual program appropriations and federal costs per project |
Authorization for design and/or construction assistance for a nonfederal EI project or EI program |
Primary project purposes |
Navigation FRM AER |
Specified in authorization; typically related to navigation, FRM, or AER |
Municipal water, sewer, and resource protection and development; other purposes as specified in authorization |
Federal and nonfederal role in project |
Federal project with NFS (no NFS for inland and intracoastal navigation) |
Federal project with NFS |
Nonfederal project receiving federal assistance (e.g., USACE contracts for work on nonfederal project) |
Nonfederal study cost sharing |
After first federal $100,000, feasibility study shared 50% |
After first federal $100,000, feasibility study shared 50% under most CAPs, except for §204 CAP (33 U.S.C. §2326) and §111 CAP (33 U.S.C. §426i) |
— |
Nonfederal design cost sharing |
PED same as construction cost sharing |
PED same as construction cost sharing |
25% |
Nonfederal construction cost sharing |
Varies by CAP |
25% |
|
Responsibility for operation, maintenance, repair, replacement, and rehabilitation |
Navigation: USACE |
Nonfederal under most CAPs, except for §107 CAP (33 U.S.C. §577) |
Nonfederal |
Nonfederal sponsor eligibility (42 U.S.C. §1962d-5b(b); 33 U.S.C. §2241) |
Public body (including Indian tribe, tribal organization, and inter-tribal consortium); nonprofit entity with local government consent |
Typically legally constituted public body; some eligibility variation across CAPs regarding other entities |
Typically public entity, although some eligibility varies based on authority |
Source: Congressional Research Service. Appropriations amounts are derived from the FY2023 work plans.
Notes: AER = aquatic ecosystem restoration; CAP = continuing authorities program; EI = environmental infrastructure; FRM = flood risk management; NFS = nonfederal sponsor; PED = preconstruction engineering and design; USACE = U.S. Army Corps of Engineers.
For USACE federal water resource projects, congressional authorization and appropriations processes are critical actions in a multistep process to deliver a USACE project for navigation, flood risk management, and aquatic ecosystem restoration. This section describes the standard delivery process for USACE federal water resource projects.
Nonfederal project sponsors typically share in study, design, and construction costs of USACE federal projects. The division of these costs and other responsibilities is set out in agreements signed by USACE and the nonfederal sponsors—feasibility cost-share agreements, design agreements, and project partnership agreements (PPAs), respectively. Among the other nonfederal responsibilities for many USACE projects are (1) the provision of land and other real estate interests for most projects and (2) operation, maintenance, repair, rehabilitation, and replacement (OMRR&R). Nonfederal project sponsors generally are state, tribal, or territorial organizations; political subparts of a state or group of states (e.g., local governments); or quasi-public organizations chartered under state law (e.g., port authorities).10 Congress has authorized that some USACE activities can have nonprofit organizations with local government consent as nonfederal sponsors and that an interstate agency created by compact can serve as a nonfederal sponsor for a navigation project.11 The sponsor must have the legal and financial capability to fulfill the requirements of cost sharing and local cooperation.
The standard USACE project delivery consists of USACE leading the study, design, and construction of congressionally authorized federal water resource projects, as shown in Figure 3. The process shown in Figure 3 is not automatic. Appropriations are required in order to initiate and complete studies, preconstruction engineering and design (PED), and construction; that is, both authorization and appropriations are needed for USACE to proceed. Appropriations are typically provided through annual Energy and Water Development Appropriations acts; at times, they are provided through supplemental appropriations acts. For USACE federal water resource projects, the report accompanying annual appropriations typically identifies with a line item the specific studies and projects to be funded for construction and operations. Congress also may provide additional funding that the Administration can apply to specific congressionally authorized studies and projects pursuant to the accompanying congressional direction. The Administration typically allocates this funding in work plans that are subsequently provided to Congress.
During the operations phase, there may be interest in modifying the USACE project. Modification may take the form of restarting the process shown in Figure 3 (although a new study authority may not be required), or it may entail a nonfederal entity pursuing a nonfederal project that alters the existing federal water resource project.
The remainder of this section describes in more detail the four phases shown in Figure 3. The section then describes how, after construction, USACE can study whether to modify an existing project, or an entity other than USACE can ask permission to modify a USACE project. The section also briefly addresses deauthorization of studies and projects.
The study phase consists of various planning activities to develop enough information to decide whether to recommend to Congress project implementation. This phase includes the development of alternative plans, initial design and cost estimating, economic analysis,12 environmental analyses, and real estate evaluations, among other activities. Table 2 provides an overview of the study phase.
To proceed with a study, USACE must have an authorization for the study. Congress generally authorizes USACE studies in WRDAs. (See the text box titled "How Studies Are Considered for Inclusion in a WRDA" for information on the process for identifying studies to be included in a WRDA.) The congressional authorizing committees—the House Transportation and Infrastructure Committee and the Senate Environment and Public Works Committee—also may use a committee resolution to direct USACE to reexamine or restudy a geographic area previously studied by USACE for a similar purpose (33 U.S.C. §542). USACE may initiate studies that review the operations of completed USACE projects without obtaining additional congressional authorization under its general reexamination authority (33 U.S.C. §549a).
How Studies Are Considered for Inclusion in a Water Resources Development Act (WRDA) To develop WRDAs, including identifying studies to include in a WRDA, the authorizing committees for the U.S. Army Corps of Engineers (USACE) typically hold hearings to receive testimony from stakeholders, review reports transmitted by the Administration, and solicit input from Members of Congress. Also, in Section 7001 of the Water Resources Reform and Development Act of 2014 (WRRDA 2014; P.L. 113-121), Congress established a process that may assist congressional authorizing committees in identifying USACE studies for congressional authorization. In Section 7001, as amended, Congress requires the Administration to transmit an annual report to the authorizing committees on publicly submitted USACE study proposals that require congressional authorization. Inclusion of a proposal in a Section 7001 report provides neither congressional authorization nor appropriation; rather, inclusion facilitates congressional consideration of the proposal's authorization. For more on the Section 7001 process, see CRS Insight IN11118, U.S. Army Corps of Engineers: Section 7001 Report on Future Studies and Projects, by Anna E. Normand. For information on how Congress develops a WRDA, see CRS Insight IN11810, U.S. Army Corps of Engineers Civil Works: Primer and Resources, by Anna E. Normand and Nicole T. Carter. |
The study process consists of the following steps:
Once the final feasibility report is available and if it is favorable, the Chief of Engineers signs a recommendation on the project, known as the Chief's report. USACE submits the completed Chief's reports to the congressional authorizing committees (33 U.S.C. §2282a). The Chief of Engineers also transmits the reports to the ASACW and the Office of Management and Budget (OMB) for Administration review.13 Since the mid-1990s, Congress has authorized many projects based on Chief's reports prior to completion of project review by the ASACW and OMB.
As part of its consideration of alternatives, USACE evaluates whether a plan is technically feasible, economically justified, and environmentally acceptable. For flood risk reduction projects and navigation projects, USACE performs a benefit-cost analysis to compare the economic benefits of project alternatives to the investment costs of those alternatives. For ecosystem restoration projects, USACE performs a cost-effectiveness analysis to evaluate for each project alternative its associated costs and anticipated environmental benefits.
The USACE feasibility study process often occurs concurrently with the agency's efforts to comply with the National Environmental Policy Act of 1969 (NEPA; 42 U.S.C. §§4321 et seq.). NEPA requires federal agencies to fully consider a federal action's significant impacts on the quality of the human environment—and to inform the public of those impacts—before making a final decision. Often USACE integrates into a single document a project's feasibility report and its NEPA documents.
There is no current, definitive, comprehensive, publicly available list of all authorized USACE water resource studies and projects. The status of existing authorizations for a given project or geographic area can be determined by reviewing enacted legislation, deauthorization actions (e.g., construction project deauthorization lists published in the Federal Register), and other relevant documents.
Although a USACE federal water resource project generally must have navigation, flood risk management, or aquatic ecosystem restoration as a primary project purpose, many USACE projects are multipurpose. Other purposes can include recreation, fish and wildlife enhancement, hydropower, agricultural water supply storage, and municipal and industrial water supply storage.
Component |
Description of Typical Applicability to USACE Federal Projects |
Purpose |
Inform federal decisions on whether there is a federal interest in authorizing a USACE construction project. The objective of the feasibility study is to formulate and recommend solutions to the identified water resource problem. |
Authorities |
Congress generally authorizes USACE studies in WRDAs. Authorizing committees also may use a committee resolution to restudy a geographic area previously studied by USACE for a similar purpose (33 U.S.C. §542). Some studies that review the operations of completed USACE projects may proceed under a reexamination authority (33 U.S.C. §549a). |
Agreement |
An entity willing to act as the nonfederal sponsor has to be identified and must sign a feasibility cost-share agreement with USACE in order to proceed with the feasibility study. |
Cost Share |
After the first $100,000, which is federally funded, feasibility studies typically are cost shared 50% federal and 50% nonfederal, with some exceptions. Feasibility studies for inland and intracoastal waterway projects are performed at 100% federal cost. Congress requires that most feasibility studies be completed within four years of initiation and have a maximum federal cost of $5 million, unless an exception is provided. |
Cost-Share Exceptionsa |
For territories, Indian tribes or tribal organizations, and certain Indigenous-related organizations, the first $658,000 in costs associated with USACE water resource activities are 100% federal (33 U.S.C. §2310). The waiver amount is annually adjusted to account for inflation; $658,000 reflects adjustment for FY2025. |
Conduct of Study |
USACE typically performs the study. Alternatively, under certain authorities, nonfederal entities may assume study responsibility and may seek application of credit for the study costs toward the construction cost share. |
Recommendation to Congress |
Once the final feasibility report is available and if it is favorable, the Chief of Engineers signs a recommendation on the selected plan for the project, known as the Chief's report. USACE submits completed Chief's reports to the congressional authorizing committees. |
Source: Congressional Research Service.
Notes: USACE = U.S. Army Corps of Engineers; WRDA = Water Resources Development Act.
a. Section 118(b) of WRDA 2020 (Division AA of P.L. 116-260, 33 U.S.C. §2201 note) directed the Secretary of the Army to establish a pilot program for feasibility studies for flood risk management and hurricane and storm damage risk reduction projects for economically disadvantaged communities at 100% federal cost. The Secretary is to annually publish in the Federal Register a notice for requests for nonfederal proposals for the pilot program, provide technical assistance with proposal formulation, and review and select 10 feasibility studies annually to be carried out by USACE. As of August 2025, USACE had not developed the guidance documents for implementing the program.
In addition, and separate from the above discussion of the study phase of a USACE federal water resource project, USACE has some technical assistance authorities. These authorities allow the agency to conduct other types of studies and provide technical assistance to nonfederal entities on water resource topics (see text box titled "USACE Technical Assistance, Including Studies and Information"). The information and studies produced pursuant to these authorities generally are not intended to justify a USACE federal water resource project; that is, they generally do not lead to a USACE federal water resource project. These studies and authorities are not discussed further in this report.
USACE Technical Assistance, Including Studies and Information Separate from the traditional study phase for U.S. Army Corps of Engineers (USACE) federal water resource projects, USACE also may provide technical assistance to nonfederal entities. Some USACE technical assistance authorities are for the provision of information, and others are for the performance of studies. These studies do not typically lead to recommendations for USACE projects; that is, they are not feasibility studies. Below are a few examples of USACE authorities to perform federally funded or cost-shared technical assistance, including some studies such as watershed assessments.
|
USACE preconstruction engineering and design consists of finalizing a project's design, preparing construction plans and specifications, and drafting construction contracts. PED may begin on a project before the project has obtained congressional authorization for construction.14 PED begins once federal funds are provided to the PED activity and a design agreement is executed between USACE and the nonfederal sponsor. Once funded, the average duration of PED is two years, but the duration varies widely depending on the project's size and complexity. PED costs are shared between the federal and nonfederal sponsor in the same proportion as the cost-share arrangement for the construction phase (see "Construction Phase" discussion below for information on the construction cost-share requirements). During PED, USACE districts prepare a design documentation report, which records the post-feasibility phase final design. The report is the technical basis for the plans and specifications.
After Congress authorizes a project (typically in a WRDA), federal funds for construction are needed for USACE to proceed with these activities. USACE and the nonfederal sponsor enter into a project partnership agreement for construction of a water resource project. The PPA describes the project and the responsibilities of the government and the nonfederal sponsor in the cost sharing and execution of project construction. Once federal construction funds are available, USACE typically functions as the project manager; that is, USACE staff usually are responsible for leading on construction. Table 3 provides an overview of the USACE construction phase.
Component |
Description of Typical Applicability to USACE Federal Projects |
Purpose |
Construction of congressionally authorized federal water resource projects |
Authorities |
Congressional project authorization typically included in a Water Resources Development Act (WRDA) |
Agreement |
Nonfederal sponsor signs a project partnership agreement with USACE in order to proceed with construction. The agreement sets out the parties' responsibilities during the construction phase, such as nonfederal cost sharing and nonfederal responsibility for providing land, easements, rights-of-way, relocations, and disposal (LERRDs). |
Cost Share |
Typically specified in the documents identified as part of the project's WRDA authorization. Generally, cost sharing follows requirements set out in statute as shown in Table 4 and Table 5. Deviations can be recommended as part of the decision document transmission to Congress; Congress must authorize cost-share deviations. A nonfederal sponsor typically pays USACE its cost share as funds are needed (i.e., as construction proceeds). When payments are deferred, interest is charged.a Some of the nonfederal cost share typically can be met with credit for LERRDs or in-kind work. |
Typically managed by USACE using contracts with the private sector to complete the physical work. Alternatively, under certain authorities, nonfederal entities may assume construction responsibility and may seek reimbursement or credit from USACE for the federal share. |
Source: Congressional Research Service.
Notes: LERRD = land, easements, rights-of-way, relocations, and disposals; PPA = project partnership agreement; USACE = U.S. Army Corps of Engineers; WRDA = Water Resources Development Act.
a. USACE annually publishes a memorandum on deferred payment interest rates and payment calculations. For example, see USACE, Federal Interest Rates for Corps of Engineers Projects for Fiscal Year 2025, Economic Guidance Memorandum 25-01, October 9, 2024. The FY2025 memorandum describes how in practice budget constraints may limit USACE participation in projects with deferred payments.
Although project management is generally performed by USACE personnel, physical construction is contracted out to private engineering and construction contractors. There are authorities for nonfederal entities to lead on construction of authorized projects (e.g., 33 U.S.C. §2232); however, nonfederal leadership of a project's construction is much less common than USACE leadership.
Table 4 provides the standard construction and operations phase cost-share requirements for the primary project purposes of navigation, flood risk management, and aquatic ecosystem restoration. The table also identifies whether USACE or the nonfederal sponsor is the responsible entity for the operations phase. Table 5 provides the standard construction and operations phase cost-share requirements for other purposes at USACE multipurpose projects; that is, the purposes shown in Table 5 generally are added to a project that has at least one of the three primary purposes of navigation, flood risk management, and aquatic ecosystem restoration. Deviation from the standard cost-sharing arrangements for individual projects often requires specific authorization by Congress.15
In addition to USACE accepting the nonfederal cost share as required by statute and a project's authorization, USACE has authorities to accept funds from nonfederal sponsors to expedite the delivery of federal water resource projects. These may be advanced funds, accelerated funds, or contributed funds.16
Table 4. Standard Cost Share and Responsible Entity by Project Purpose for USACE Project Construction and Operations Phases
Project Purpose |
Nonfederal Share of Construction Phasea |
Responsible Entity for Operations Phase |
Nonfederal Share of Operations Phase |
||
Navigation |
|||||
Coastal Navigation Channels and Coastal and Inland Harbors |
|||||
Improvements less than 20 ft. deep |
10%, plus 10% over a period not to exceed 30 years |
USACE |
|||
Improvements between 20 ft. and 50 ft. deep |
25%, plus 10% over a period not to exceed 30 years |
USACE |
0% nonfederal; |
||
Improvements greater than 55 ft. deep |
50%, plus 10% over a period not to exceed 30 years |
USACE |
|||
Inland and Intracoastal Waterways |
No nonfederal |
USACE |
0% |
||
Flood Risk Management |
|||||
Riverine Structural Flood Control |
35%-50%d |
Nonfederal |
100% |
||
Nonstructural and Natural or Nature-Based Features |
35% |
Nonfederal |
100% |
||
Coastal Hurricane and Storm Damage Reduction |
35% |
Nonfederal |
100% |
||
Aquatic Ecosystem Restoration |
35% |
Nonfederal |
100% |
Source: Congressional Research Service, using 33 U.S.C. §§2211-2213, unless otherwise specified below.
Notes: HMTF = Harbor Maintenance Trust Fund; USACE = U.S. Army Corps of Engineers.
a. Nonfederal share may be met through provision of land, easements, rights-of-way, relocations, and disposals, unless otherwise noted.
b. The majority of federal support for harbor maintenance is derived from the HMTF, which receives collections from a harbor maintenance tax principally applied to commercial cargo imports at federally maintained ports. For maintaining improvements up to 55 feet in depth, the maximum federal share is 100%; for maintaining improvements over 55 feet deep, the costs are split 50% federal and 50% nonfederal.
c. Monies from the Inland Waterways Trust Fund, which is funded by a fuel tax on vessels engaged in commercial transport on designated waterways, are used for 35% of all new or ongoing construction projects after October 1, 2022.
d. 33 U.S.C. §2213 identifies 65% federal as the maximum share and 50% as the maximum nonfederal share; 5% of the nonfederal share must be paid during construction.
e. Congressionally authorized beach nourishment components of coastal storm damage reduction projects consist of periodic placement of sand on beaches and dunes. Most nourishment activities remain in the construction phase for 50 years, with the possibility for extension (42 U.S.C. §1962d-5f). The nonfederal share for new periodic beach nourishment projects generally is 50% nonfederal for shores open to the public, 100% nonfederal for private shores with access limited to private interests, and 0% nonfederal for federally owned shores (33 U.S.C. §2213).
Table 5. Standard Cost Shares for Other Project Purposes of USACE Multipurpose Projects for USACE Project Construction and Operations Phases
Project Purpose |
Nonfederal Share of Construction Phase |
Nonfederal Share of Operations Phase |
Hydroelectric Power |
100%a |
100% |
Municipal and Industrial Water Supply Storage |
100% |
100% |
Agricultural Water Supply Storage (typically irrigation water storage)b |
35% |
100% |
Recreation at USACE Facilities |
50% |
100% |
Aquatic Plant Control |
Not Applicable |
50% |
Source: Congressional Research Service, using 33 U.S.C. §2213, unless otherwise specified below.
Note: USACE = U.S. Army Corps of Engineers.
a. Construction costs initially are federally funded; they are 100% repaid by fees collected from power customers.
b. Unlike other USACE project components, 100% of nonfederal agricultural water supply construction costs are initially federally funded if the USACE project is in the 17 western states where reclamation law applies. Repayment of these costs by nonfederal water users over extended terms is subject to conditions under the federal reclamation laws.
Figure 3 shows a project moving from construction to operations without additional reports required. For many projects, issues may arise during the construction phase that result in USACE developing a post-authorization change report (PACR). That is, a project may undergo some changes after authorization, such as cost increases or the addition of a project purpose (e.g., recreation). USACE may evaluate and document such changes in a PACR. There are various types of PACRs that end in different types of decisions, and approval authority varies based on what has changed, what needs to be analyzed, and whether new congressional authorization is required. If additional congressional authorization is necessary for the changes captured in a PACR, Congress typically authorizes these modifications in a WRDA. For less significant modifications, additional authorization often is not necessary. Section 902 of WRDA 1986, as amended (33 U.S.C. §2280), generally allows for increases in total project costs of up to 20% (after accounting for inflation of construction costs) without additional congressional authorization. If USACE needs more funds to complete a project than the combined 20%- and inflation-adjusted amount, an increase in the congressional authorization of appropriations is likely needed to proceed with the project; for these projects, USACE generally does not pursue additional contracts until Congress has adjusted the authorization of appropriations.
USACE and the nonfederal sponsor enter into a feasibility cost-share agreement to produce these reports. USACE may undertake three types of PACRs during the construction phase: general reevaluation reports (GRRs), limited reevaluation reports (LRRs), and engineering documentation reports (EDRs).
Post-construction operations and upkeep responsibilities depend on the type of project. When construction is complete, USACE may own and operate the constructed project (e.g., navigation projects) or operations responsibilities may transfer to the nonfederal sponsor (e.g., most flood damage reduction projects and aquatic ecosystem restoration projects). The responsible entity and the cost-share responsibilities during the operations phase vary by project purpose, as shown in Table 4 and Table 5.
USACE generally uses the term operation and maintenance for the operations phase of federally operated projects and the term operation, maintenance, repair, replacement, and rehabilitation (OMRR&R) for the operations phase of nonfederally operated projects. OMRR&R consists of the suite of activities necessary to maintain the project in sound operating condition. For nonfederally operated projects, USACE prepares an OMRR&R manual for the nonfederal sponsor. During the operations phase, the nonfederal sponsor completes operations reports on a regular basis (e.g., semiannual reports), and USACE periodically inspects the project to assess and evaluate the project's performance and safety during its operating life. For nonfederal flood risk management projects, USACE operates a rehabilitation program to support with federal funding the repair of certain damaged flood control and storm damage reduction facilities, as discussed in the next section.
USACE operates a repair program—the P.L. 84-99 Rehabilitation Program—for nonfederal flood control works, including federal water resource projects for which the nonfederal sponsor has assumed OMRR&R. Through the program, USACE can fund the repair of damage by "other than ordinary" water, wind, or wave action to (1) certain nonfederal flood control works (e.g., levees, dams) and (2) federally constructed hurricane and shore protection projects. To be eligible for this assistance, the damaged project must be eligible for and active in the rehabilitation program and the project must have been in an acceptable condition, as inspected and assessed by USACE, at the time of damage. USACE regularly inspects the 1,600 nonfederal levee systems (consisting of 13,000 miles of levees) that participate in the program. The damage rehabilitation program does not fund repairs associated with regular OMRR&R.
During a USACE project's operations phase, nonfederal sponsors and other stakeholders may be interested in modifications to the existing project. Often, there is interest in having USACE modify an existing project (e.g., by deepening a federal navigation channel). In some circumstances, a nonfederal entity is interested in undertaking its own modification.
USACE can review the operations of completed USACE projects under a reexamination authority (33 U.S.C. §549a), established by Section 216 of the Flood Control Act of 1970 (P.L. 91-611). These reviews are often referred to as Section 216 studies. The reexamination authority allows for review of the operation of USACE-constructed projects for navigation, flood control, water supply, and related purposes when advisable due to significantly changed physical or economic conditions. These USACE studies result in a report to Congress with recommendations on the advisability of modifying the structures or their operation and for improving the quality of the environment in the overall public interest. Congress would need to authorize the changes for USACE to proceed.
If a nonfederal entity is interested in altering a USACE civil works project after construction, the entity generally must obtain permission from USACE. USACE's authority to allow alterations to its projects derives from Section 14 of the Rivers and Harbors Act of 1899, also known as Section 408 (based on its codification at 33 U.S.C. §408). This provision states that the Secretary of the Army may "grant permission for the alteration or permanent occupation or use of any of the aforementioned public works when in the judgment of the Secretary such occupation or use will not be injurious to the public interest and will not impair the usefulness of such work."19 To reach a decision on a Section 408 permission, USACE conducts a technical review of the proposed alteration's effects on the USACE project. Section 408 permissions may be required not only for projects operated and maintained by USACE but also for federally authorized projects that are operated by nonfederal project sponsors (e.g., many USACE-constructed, locally maintained levees).20 At the end of the Section 408 process, USACE chooses to approve or deny permission for the alteration. USACE may attach conditions to its Section 408 permission.
At times, Congress deauthorizes specific USACE projects or project elements. USACE may conduct a Section 216 study to determine whether to recommend deauthorizing a completed USACE project that no longer serves its congressionally authorized project purposes. If Congress deauthorizes the project, USACE will proceed with a divestiture process.21 For example, a few inland waterway locks and dams that no longer support commercial navigation have been deauthorized and divested to nonfederal interests.
Congress also has used WRDAs to deauthorize unconstructed projects and project elements and to deauthorize studies. In previous WRDAs, Congress established various processes to deauthorize existing study and project authorities meeting certain criteria. Some of these deauthorization processes have since been repealed. For example, previously enacted study deauthorizations were repealed by WRDA 2020 (Division AA of P.L. 116-260). Current statutes for deauthorization processes consist of the following:
USACE can plan, design, and implement certain types of water resource projects without project-specific congressional authorization under CAPs established by Congress. Under CAPs, USACE has authority to plan and implement projects of limited size, cost, scope, and complexity. For most CAP authorities, Congress has limited the project's federal cost and scope, as shown in Table 6.23 Once funded, CAP projects generally take two to three years for the study phase, and the construction phase often takes two to five years. CAPs typically are referred to by the section number in the bill in which the CAP was first authorized.
CAP projects move through phases: study (feasibility), design and construction, and operations. During the study phase, USACE identifies alternative project plans and develops initial cost estimations, environmental impact analyses, and a real estate evaluation, among other actions to formulate a project. The study phase typically consists of developing a feasibility report as the decision document, in which USACE identifies the preferred project alternative. For CAP projects, USACE can proceed directly to design and construction after the study phase without obtaining specific congressional project authorization. The design and construction phase includes the final project design and specifications, nonfederal real estate acquisition, project contracting, and physical construction.
The study phase is initially federally funded up to $100,000, and then the study cost sharing for most CAPs is 50% nonfederal after executing a feasibility cost-share agreement (see Table 6), with two exceptions. Studies under the Section 204 CAP (i.e., regional sediment management to reduce storm damage) are 0% nonfederal. For studies under Section 111 (prevention/mitigation of shore damage by federal navigation projects), after the first $100,000 in costs, which are federally funded, costs are shared the same as construction of the navigation project causing the damage.
The design and construction phase consists of actions to implement the project, such as design, preparation of contract plans and specifications, permitting, real estate acquisition, contracting, and construction. Near the beginning of the design and construction phase, USACE and the nonfederal sponsor sign a project partnership agreement. Costs for the construction phase are shared as specified in the authorizing legislation for the CAP, as shown in Table 6. Under CAPs, the operations phase is a nonfederal responsibility, except for general navigation feature improvements under the Section 107 CAP.
Although USACE does not need any additional authorization to perform projects under CAPs, Congress in some WRDA bills has included references to specific CAP projects, such as noting that the Secretary shall expedite completion of certain CAP projects.
CAPs are often funded as a program (which leaves USACE with the discretion of which CAP projects to fund); at times, Congress has directed funding to specific CAP projects. As part of the annual Energy and Water Development appropriations process, CAP authorities typically are funded through inclusion of a line item for each CAP in the USACE Construction account in the report accompanying the legislation. At times, some CAPs have been funded through supplemental appropriations (e.g., flood-related CAPs funded in flood-related or disaster-related supplemental appropriations acts).
Common Name of CAP Authority |
Eligible Activities and U.S. Code Citation |
Nonfederal Construction Cost Share |
Per Project Federal Limit |
Annual Federal Program Limit |
§14 |
Streambank and shoreline erosion of public works and nonprofit services |
35%-50%a |
$15.0 |
$50.0 |
§103 |
Beach erosion/hurricane storm damage reduction |
35% |
$15.0 |
$62.5 |
§107 |
Navigation improvements |
Varies |
$15.0 |
$62.5 |
§111 |
Mitigation (and prevention) of shore damage by federal navigation projects |
Same percentage as the project causing the damage |
$15.0 |
No limit specified |
§204 |
Beneficial use of dredged material |
35%b |
$15.0b |
$90.0 |
§205 |
Flood damage reduction, including prevention of ice jams (accumulations of river ice that obstruct streamflow) |
35%-50% for structural,a |
$15.0 |
$90.0 |
§206 |
Aquatic ecosystem restoration and drought resilience through wetlands restoration or invasive species removal |
35%, except 15% for projects for anadromous fish (which migrate from freshwater rivers to the ocean and back to spawn) |
$15.0 |
$75.0 |
§208 |
Removal of obstructions (snagging) and clearing of channels for flood damage reduction |
35% |
$1.0 for any tributary in a fiscal year |
$15.0 |
§1135 |
Project modifications for improvement of the environment |
25% |
$15.0 |
$62.0 |
Source: Congressional Research Service, using statutes and USACE, Continuing Authorities Program, Engineer Pamphlet 1105-2-58, March 1, 2019, https://www.publications.usace.army.mil/Portals/76/EP_1105-2-58.pdf?ver=2019-04-30-105428-920.
Notes: CAP = continuing authorities program; USACE = U.S. Army Corps of Engineers. CAPs that have not been funded in the most recent five fiscal years are not shown.
a. 33 U.S.C. §2213 identifies 65% as the maximum federal share and 50% as the maximum nonfederal share; 5% of the nonfederal share must be paid during construction.
b. Projects consist of regional sediment management to reduce storm damage, protect aquatic ecosystems, and improve environmental conditions (§204) and beneficial use of dredged material from federal water resource projects (§204(d)). Limit of 35% nonfederal cost share for costs beyond the base disposal plan cost (which is 100% federal cost of the least costly typical disposal), $15.0 million federal limit per construction activity, and $15.0 million per beneficial use/placement under §204(d). Multiple placements allowed under §204(d).
Apart from the regularly funded CAPs previously discussed, Congress has established other authorities that share many CAP characteristics or are authorized in conjunction with CAPs. Below are a few authorities allowing USACE to perform work without project-specific study or project authorization if federal project costs are below a specified amount; the list of programs below is not comprehensive. Although some of these authorities have received funding (e.g., Tribal Partnership Program [TPP]), others have not been funded. A number of these authorities reference economically disadvantaged communities; USACE has developed implementation guidance that defines this term and related criteria,24 and this guidance applies unless more specific direction is provided in law.
Two authorities that have received funding are the TPP and the Community Revitalization Program for Small Projects for Economically Disadvantaged Communities.
Other authorities have been enacted in statute but have not received appropriations in recent years or since being enacted.
Congress has authorized and appropriated funding for USACE EI assistance for the design and construction of certain nonfederal infrastructure in specified municipalities, counties, and states. These authorizations typically appear in a WRDA.
The authorized assistance supports different nonfederal projects at publicly owned and operated facilities. These nonfederal projects often may include construction of water distribution works, stormwater management, surface water protection, and environmental restoration, among other activities. CRS estimates that there are 600 EI assistance authorities with cumulative authorizations of appropriations totaling approximately $18 billion.29
USACE evaluates a proposed EI activity's eligibility for assistance by identifying whether an EI assistance authorization exists for the nonfederal project's geographic area and whether the proposed work is an eligible type of assistance provided for in the specific EI authorization. The EI authorization's specifics determine the nature of USACE's involvement and the nonfederal cost share. USACE is typically authorized to perform design or design and construction work with USACE funds. For certain programmatic authorities, USACE may use appropriated funds to reimburse nonfederal sponsors for work they perform.
Most USACE EI assistance requires cost sharing at 75% federal and 25% nonfederal, and the nonfederal sponsor—the owner of the constructed facility—is responsible for operation and maintenance. Unlike traditional USACE water resource projects, EI assistance is not subject to the USACE planning process (e.g., it does not require a feasibility study); however, other federal laws, including NEPA, apply to EI assistance. USACE and the nonfederal sponsors sign either a design cost-share agreement or a design and construction cost-share agreement before EI assistance may be initiated.
For more information on USACE EI assistance, including a list of authorities and appropriations information, see CRS Report R47162, Overview of U.S. Army Corps of Engineers Environmental Infrastructure (EI) Assistance, by Anna E. Normand.
Congress regularly considers during its WRDA deliberations various topics related to the processes for USACE federal water resource projects and USACE assistance with nonfederal EI. Some examples of process-related topics include nonfederal responsibilities, USACE's role in water supply and conservation, and the future of USACE EI assistance.
Nonfederal sponsors are often interested in altering their responsibilities associated with USACE federal water resource projects. Among the changes that some stakeholders support are reducing the nonfederal cost share for specific projects or certain types of projects (e.g., projects that benefit economically disadvantaged communities). Some stakeholders view the current nonfederal cost-share requirements as prohibitive or burdensome. Other stakeholders support nonfederal beneficiaries continuing to contribute to the costs of USACE projects, as set out in current statute, as a lowering of nonfederal cost sharing may reduce the number of studies and projects that USACE can perform with available federal appropriations.
As described in this report, Congress primarily directs USACE's flood risk management through geographically specific study and project authorizations. The current process for USACE flood risk management projects at times raises questions regarding how effectively, efficiently, and equitably the agency's planned and funded projects are reducing the nation's current and future flood risk.30 For example, in a 2024 report on community relocation away from environmentally high-risk areas, the National Academies of Sciences, Engineering, and Medicine stated, "the requirement that USACE seek congressional authorization to address flood risk in a specific locality, with no organic statute governing overall authority of USACE to determine its own agenda, has resulted in piecemeal and inequitable distribution of [flood risk management] projects."31 Others also have questioned whether the USACE project process favors certain types of approaches to reducing flood risk, such as structural approaches rather than nonstructural or nature-based approaches.
Pursuant to Section 221 of WRDA 2020, USACE delivered a report to Congress on the benefits and consequence of including water supply and water conservation as a primary USACE mission.32 As previously noted, WRDA 2024 included multiple provisions on USACE's water supply activities. This interest in the role that USACE's projects have in addressing the demands on existing water supplies may continue. How the agency integrates recent WRDAs' water-supply provisions into its project planning and development processes and the level to which these actions are supported by federal appropriations may shape the future portfolio and purposes of USACE projects.
Congress since 1992 has continued to expand the suite of locations where USACE can provide EI assistance to nonfederal projects; for example, WRDA 2022 included over 600 EI assistance authorizations. The increased authorizations have resulted in expanded eligibility for many more nonfederal projects. Nonetheless, EI assistance is not available nationwide and is limited to authorized geographic areas. In addition, the authorization amounts of EI assistance vary widely, from a few thousand dollars to hundreds of millions of dollars. Although some of the larger EI authorities rival the size of individual USACE federal water resource project authorizations, the process for EI assistance remains distinct from the process for federal water resource projects; this distinction is due in part to the nonfederal nature of this infrastructure.
Congress may consider whether to add, amend, or deauthorize EI assistance authorities. It also may consider altering the scope of EI assistance authorities (e.g., geographic area, authorization of appropriations, activities). Further, Congress may consider whether to define prioritization for EI assistance (e.g., for economically disadvantaged communities) or whether to establish a more formal program (e.g., a competitive program or a program with national eligibility).
1. |
For more on the organization of the U.S. Army Corps of Engineers (USACE) and its offices' responsibilities and boundaries, see CRS Report R48322, U.S. Army Corps of Engineers Civil Works: FAQs on Organization and Efficiency Reviews, by Nicole T. Carter. |
2. |
Across both its military and civil works programs, USACE consists of around 36,000 civilian employees (with roughly 11,000 employees supporting the military program and the remainder in the civil works program) and almost 800 uniformed military personnel (roughly 300 related to civil works). An officer typically is in a specific district or division leadership position for two to three years; a Chief of Engineers often serves for roughly four years. |
3. |
Water Resources Development Acts (WRDAs) are distinguished from each other by referencing the year of enactment; that is, WRDA 1986 refers to the act passed in 1986 (P.L. 99-662). |
4. |
The discussion of environmental infrastructure (EI) assistance herein is brief; more details are available in CRS Report R47162, Overview of U.S. Army Corps of Engineers Environmental Infrastructure (EI) Assistance, by Anna E. Normand. |
5. |
USACE, Strategic Asset Management Plan, August 2022, pp. 10-11, https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll6/id/2358. |
6. |
For more on USACE water-supply-related authorities and activities, see CRS Report R46471, Federally Supported Projects and Programs for Wastewater, Drinking Water, and Water Supply Infrastructure, coordinated by Jonathan L. Ramseur. |
7. |
Section 1201(a) included five single-purpose water supply feasibility studies (which were located in Michigan, New Mexico, Oklahoma, Tennessee, and Texas/Oklahoma) and a feasibility study for "alternate water supply" in Pennsylvania. |
8. |
Section 404 permits are related to the discharge of dredged or fill material into waters of the United States, and Section 10 permits are related to the obstruction or alteration of navigable waters. USACE also administers Section 103 of the Marine Protection, Research, and Sanctuaries Act of 1972, as amended (33 U.S.C. §1413) related to the issue of permits for the transportation of dredged material for dumping in ocean waters. |
9. |
The U.S. Department of Energy (DOE) established the Formerly Utilized Sites Remedial Action Program (FUSRAP) program in 1974, under the Atomic Energy Act of 1954, as amended. The program addresses radiological and chemical contamination at some of the smaller sites associated with the legacy production of nuclear weapons and nuclear energy research for civilian purposes; 10 U.S.C. §2701 note sets out USACE's authorities related to FUSRAP. For each FUSRAP site, USACE investigates the extent of environmental contamination, identifies a response, performs the cleanup work, and disposes of waste. After cleanup work is completed at each site, USACE transfers responsibility for long-term monitoring to DOE. |
10. |
42 U.S.C. §1962d-5b(b). |
11. |
42 U.S.C. §1962d-5b(b); 33 U.S.C. §2241. |
12. |
For flood risk reduction, Congress established federal policy for evaluating USACE projects in the Flood Control Act of 1936 (49 Stat. 1570) by stating that a project should be undertaken "if the benefits to whomsoever they may accrue are in excess of the estimated costs" and if a project is needed to improve the lives and security of the people. |
13. |
The Office of Management and Budget's (OMB's) review stems in part from Executive Order 12322 of September 17, 1981, "Water Resources Projects," 46 Federal Register 46561, September 21, 1981, as amended by Executive Order 12608 of September 9, 1987, "Elimination of Unnecessary Executive Orders and Technical Amendments to Others," 52 Federal Register 34617, September 14, 1987. According to the amended order, before submission to Congress—or to any committee or member thereof—for approval, appropriations, or legislative action, any report, proposal, or plan relating to a federal or federally assisted water project or program, such report, proposal, or plan shall be submitted to the Director of OMB and reviewed. OMB shall advise the agency of the project's relationship to the policy and programs of the President, as well as of water resource project study guidance and other laws, regulations, and requirements related to planning. |
14. |
In general, subject to appropriation, preconstruction engineering and design begins after the transmittal of the Chief's report to the Assistant Secretary of the Army for Civil Works (ASACW; 33 U.S.C. §2287). Some USACE guidance indicates design may initiate after the Division Engineer's transmittal of the feasibility report to USACE headquarters. |
15. |
Congress established that cost shares shall be subject to a nonfederal sponsor's ability to pay (33 U.S.C. §2213(m)(2)); this authority has rarely been employed. The regulation related to this provision (33 C.F.R. Part 241) does not reflect various statutory amendments. USACE has indicated plans for a rulemaking to amend the regulations. |
16. |
Advanced, accelerated, and contributed funds must be voluntarily offered and provided. |
17. |
Advanced funds are in addition to funds provided to meet any required nonfederal cost share. USACE guidance indicates that an offer to provide advanced funds must include a nonfederal commitment to provide all funds to complete either project construction or a separable element of the project (USACE, Acceptance of Contributed Funds, Advanced Funds, and Accelerated, Director's Policy Memorandum FY2020, CECW-P [2020-01], December 2019, https://planning.erdc.dren.mil/toolbox/library/MemosandLetters/DPM_AcceptanceofFunds_19Dec2019.pdf). Advanced funds may be provided by Indian tribes or a state or political subdivision thereof, inclusive of several states, the District of Columbia, the commonwealths, territories, and possessions of the United States. |
18. |
Contributed funds can be applied to study, design, or construction or to operation and maintenance of federal water resource projects. Contributed funds may be accepted from a nonfederal interest, as defined in Section 221(b) of the Flood Control Act of 1970, as amended (42 U.S.C. §1962d-5b(b)). USACE acceptance of contributed funds is to be in connection with funds appropriated by the United States. To meet this requirement, in general, there are two main points at which appropriated funds must have been provided: study initiation and project construction initiation. |
19. |
On September 30, 2018, Engineer Circular (EC) 1165-2-220, Policy and Procedural Guidance for Processing Requests to Alter US Army Corps of Engineers Civil Works Projects Pursuant to 33 USC 408, replaced the 2015 EC 1165-2-216. |
20. |
EC 1165-2-220 provides that the regulation applies principally to alterations proposed within the real property identified and acquired for the USACE project, with potential exceptions. |
21. |
There currently is no formal process for a nonfederal entity to submit a proposal for congressional deauthorization of a project. Some nonfederal project sponsors have proposed deauthorizations through the annual report process established by Section 7001 of WRRDA 2014 (P.L. 113-121). The Administration has stated in its Section 7001 annual reports to Congress that the submitted deauthorization proposals do not qualify pursuant to the congressional direction in Section 7001(c)(1)(A) of WRRDA 2014 (33 U.S.C. §2282d(c)(1)(A)). |
22. |
In WRDA 2020, Congress repealed the ASACW's existing deauthorization process authorities and enacted new deauthorization provisions, including a one-time deauthorization authority (33 U.S.C. §579d–2). In WRDA 2022 (Division H, Title LXXXI, of P.L. 117-263), Congress amended WRDA 2020 in various ways. Whereas the WRDA 2020 process would have concluded with automatic deauthorization of projects after a two-year period for congressional review of a deauthorization project list transmitted by the ASACW to Congress, the WRDA 2022 amendments conclude the deauthorization authority with the ASACW's submission of the deauthorization list to Congress for review of the list (i.e., no automatic deauthorization). |
23. |
USACE, Continuing Authorities Program, Engineer Pamphlet 1105-2-58, March 1, 2019, https://www.publications.usace.army.mil/Portals/76/EP_1105-2-58.pdf?ver=2019-04-30-105428-920. |
24. |
USACE, Implementation Guidance for Section 160 of the Water Resources Development Act of 2020, Definition of Economically Disadvantaged Community, March 14. 2023, https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll5/id/36002. According to the guidance, an economically disadvantaged community is defined as meeting one or more of the following criteria: low per capita income (i.e., the area has a per capita income of 80% or less of the national average); unemployment rate above national average (i.e., the area has an unemployment rate that is, for the most recent 24-month period for which data are available, at least 1% greater than the national average unemployment rate); Indian country, as defined in 18 U.S.C. §1151, or in the proximity of an Alaska Native village; U.S. territories; or communities identified as disadvantaged by the Council on Environmental Quality's Climate and Economic Justice Screening Tool. As of August 2025, USACE's guidance has not been adjusted to reflect that the screening tool is no longer available on the federal websites that previously hosted the tool. |
25. |
For more on determining the cost sharing for this program, see USACE, Tribal Partnership Program Reduced Cost Share Eligibility Criteria (Ability to Pay), Economic Guidance Memorandum 24-04, January 29, 2024, https://planning.erdc.dren.mil/toolbox/library/EGMs/EGM24-04-2.pdf. The program is authorized through FY2033. |
26. |
USACE, "Army Announces Civil Works Investments in Small, Disadvantaged Communities," press release, August 29, 2024, https://www.usace.army.mil/Media/News/NewsSearch/Article/3890408/army-announces-civil-works-investments-in-small-disadvantaged-communities/. |
27. |
USACE, Implementation Guidance for Section 155 of the Water Resources Development Act of 2020, Small Water Storage Projects, April 22, 2022, https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll5/id/35987. |
28. |
An acre-foot is a unit of volume equivalent to approximately 43,560 cubic feet. |
29. |
CRS analysis of enacted legislation likely to include EI assistance authorities. |
30. |
A 2024 Government Accountability Office (GAO) report identified options to enhance the resilience of USACE's flood risk management infrastructure projects (GAO, Climate Change: Options to Enhance the Resilience of Federally Funded Flood Risk Management Infrastructure, GAO-24-105496, January 2024, https://www.gao.gov/assets/gao-24-105496.pdf). |
31. |
National Academies of Sciences, Engineering, and Medicine, Community-Driven Relocation: Recommendations for the U.S. Gulf Coast Region and Beyond (Washington, DC: National Academies Press, 2024), p. 290. |
32. |
USACE, Water Resources Development Act of 2020, Section 221: Study on Water Supply and Water Conservation at Water Resources Development Projects, August 2023, https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll5/id/37142. |