Judicial Review and the National Environmental Policy Act of 1969

Judicial Review and the National
August 4, 2022
Environmental Policy Act of 1969
Nina M. Hart
The National Environmental Policy Act (NEPA), enacted in 1969, requires federal agencies to
Legislative Attorney
integrate environmental considerations into their decisionmaking processes. It also directs

agencies to use interdisciplinary approaches in these processes and, for specified actions, to
prepare a “detailed statement” about the actions’ effects on the human environment. Because

NEPA applies to many different kinds of agency actions, including construction, land
management, permitting, and funding, it plays a significant role in the administration of many federal programs.
The Council on Environmental Quality (CEQ), an executive branch entity, has issued regulations that instruct agencies on
how to comply with NEPA, and many agencies have promulgated agency-specific regulations that supplement CEQ’s
regulations. Together, these regulations require agencies to prepare different environmental documents depending on the
degree to which a proposed action may cause significant effects to the human environment. If a proposed action will not
cause significant effects, no further analysis is required. In that case, an agency may also rely on a categorical exclusion to
document its determination that the project falls within a category of actions without significant effects. If an agency is
unclear about whether a proposed action will have significant effects, it must prepare an environmental assessment (EA). An
EA showing no significant effects allows an agency to issue a Finding of No Significant Impact (FONSI), while an EA
showing significant effects requires an agency to prepare an environmental impact statement (EIS). An EIS is required for all
proposed actions that have significant effects.
The federal courts have been instrumental in guiding agency compliance with NEPA. Although NEPA contains no provision
for judicial review, courts allow plaintiffs to challenge agency compliance with NEPA by filing challenges under the
Administrative Procedure Act (APA). Plaintiffs often allege that an agency acted “arbitrarily or capriciously” when taking
steps to comply with NEPA, and they seek a variety of remedies, including declarations that an agency violated the APA;
court orders remanding a decision to the agency for further consideration; and preliminary or permanent injunctions that
prevent an agency from implementing disputed actions.
Plaintiffs challenge the steps that agencies take to comply with NEPA in a number of different ways. Some of the more
frequently litigated issues are the following:
Improper Type or Level of NEPA Review. Plaintiffs sometimes allege that an agency improperly relied on a categorical
exclusion because the proposed action would have significant effects. When agencies prepare EAs and then issue FONSIs,
plaintiffs also may allege that the agencies violated the APA by concluding that the project would have no significant effects
and that the agencies therefore should have prepared an EIS.
Failure to Prepare a Supplemental Environmental Review. Agencies must prepare supplemental documents to EAs or
EISs when they learn of new information or make changes to a proposed action that may affect their decisionmaking process.
Plaintiffs challenging an agency’s failure to prepare a supplemental environmental document tend to focus on whether such
new information or changes are sufficient to trigger an agency’s duty to prepare a supplemental document.
Inadequacy of NEPA Review. Plaintiffs often challenge the sufficiency of an agency’s analysis of particular effects in EAs
or EISs. Sometimes, these challenges allege that an agency violated the APA by failing to obtain or analyze sufficient data.
Other challenges focus on the types of effects that CEQ set out in its 1978 regulations—direct effects, indirect effects, and
cumulative impacts—and allege that an agency failed to consider one or more of these specific types of effects. Courts often
consider claims that agencies failed to consider a reasonable range of alternatives to their proposed actions, as required by
NEPA. Plaintiffs also challenge the adequacy of an agency’s NEPA compliance by arguing that an agency failed to consult
with other relevant federal or state agencies or with public stakeholders.

Congressional Research Service


link to page 4 link to page 4 link to page 4 link to page 5 link to page 6 link to page 7 link to page 7 link to page 9 link to page 9 link to page 10 link to page 10 link to page 11 link to page 11 link to page 12 link to page 14 link to page 14 link to page 15 link to page 15 link to page 16 link to page 17 link to page 17 link to page 17 link to page 20 link to page 21 link to page 13 link to page 22 Judicial Review and the National Environmental Policy Act of 1969

Contents
Introduction ..................................................................................................................................... 1
Statutory and Regulatory Background ............................................................................................ 1

NEPA ......................................................................................................................................... 1
CEQ and Agency Regulations ................................................................................................... 2
Major Federal Actions......................................................................................................... 3
Determining Significance: Which Level of Environmental Review Is
Appropriate? .................................................................................................................... 4
Supplemental Environmental Review ................................................................................. 6
Judicial Review of NEPA: An Overview......................................................................................... 6
Limits on Judicial Review ......................................................................................................... 7
Standing .............................................................................................................................. 7
Statute of Limitations .......................................................................................................... 8
Exhaustion .......................................................................................................................... 8

Remedies in NEPA Litigation ................................................................................................... 9
Selected Issues in NEPA Litigation ................................................................................................ 11
Confirming When NEPA Review Is Required ......................................................................... 11
Assessing Significance of Impacts .......................................................................................... 12
Use of Categorical Exclusions .......................................................................................... 12
Use of EA/FONSI Instead of EIS ..................................................................................... 13
Supplemental Environmental Review ..................................................................................... 14
Adequacy of an EA or EIS ...................................................................................................... 14

Failure to Adequately Consider Effects in an EA or EIS .................................................. 14
Failure to Consider Alternatives ....................................................................................... 17
Insufficient Consultation with the Public .......................................................................... 18

Tables
Table 1. NEPA Litigation Injunctions, 2001-2011......................................................................... 10

Contacts
Author Information ........................................................................................................................ 19

Congressional Research Service


Judicial Review and the National Environmental Policy Act of 1969

Introduction
The National Environmental Policy Act (NEPA), enacted in 1969, generally requires federal
agencies to integrate environmental considerations into their decisionmaking processes. Because
this requirement applies to a wide range of federal actions, including both the government’s own
activities and its decisions to allow or to fund other parties’ activities, NEPA plays a significant
role in the administration of many federal programs.
NEPA directs agencies to use interdisciplinary approaches in considering environmental effects
and, for specified actions, requires them to prepare a “detailed statement” about the actions’
effects on the human environment. NEPA also created the Council on Environmental Quality
(CEQ), an entity within the Executive Office of the President. CEQ oversees agency compliance
with NEPA, and, as directed by executive order, has issued regulations used by the agencies for
complying with NEPA. Agencies have also created their own regulations that supplement the
CEQ regulations.
The federal courts have been instrumental in guiding agency compliance with NEPA. Although
NEPA contains no provision addressing the availability of judicial review, courts have long
allowed plaintiffs to challenge an agency’s compliance with NEPA under the Administrative
Procedure Act (APA). This report focuses on the role of the federal courts in reviewing agency
compliance with NEPA. First, the report provides an overview of the relevant statutory and
regulatory framework. Next, it discusses how judicial review works in the NEPA context. Finally,
the report provides an overview of selected issues that arise often in litigation or tend to generate
controversy about NEPA.
Statutory and Regulatory Background
NEPA
NEPA imposes a general directive that, “to the fullest extent possible, [] the policies, regulations,
and public laws of the United States shall be interpreted and administered in accordance” with the
Act.1 It further directs all federal agencies to
(A) utilize a systematic, interdisciplinary approach which will insure the integrated use of
the natural and social sciences and the environmental design arts in planning and in
decisionmaking which may have an impact on man’s environment;
(B) identify and develop methods and procedures, in consultation with the Council on
Environmental Quality . . . which will insure that presently unquantified environmental
amenities and values may be given appropriate consideration in decisionmaking along with
economic and technical considerations;
(C) include in every recommendation or report on proposals for legislation and other major
Federal actions significantly affecting the quality of the human environment, a detailed
statement by the responsible official . . . .2

1 42 U.S.C. § 4332(1). National Environmental Policy Act of 1969, Pub. L. 91-190, 83 Stat. 852 (1970). For more
information on NEPA, see CRS In Focus IF11549, The Legal Framework of the National Environmental Policy Act.
2 Id. § 4332(2).
Congressional Research Service

1

Judicial Review and the National Environmental Policy Act of 1969

The “detailed statement,” now commonly known as an “environmental impact statement” or
“EIS,” must discuss five types of information:
1. the environmental impact of the proposed action;
2. any adverse environmental effects that cannot be avoided should the proposal be
implemented;
3. alternatives to the proposed action;
4. the relationship between local short-term uses of man’s environment and the
maintenance and enhancement of long-term productivity; and
5. any irreversible and irretrievable commitments of resources that would be
involved in the proposed action should it be implemented.3
While creating a detailed statement, agencies must consult and obtain comments from other
federal agencies with jurisdiction or “special expertise with respect to any environmental impact
involved.”4 Agencies must provide copies of the detailed statement and any comments received
during the environmental review process to the President, CEQ, and the public.5
NEPA also created CEQ within the Executive Office of the President.6 CEQ comprises three
members appointed by the President with the advice and consent of the Senate, and one of the
members is designated by the President as Chair.7 NEPA directs CEQ to, among other things,
develop and recommend to the President national policies that further environmental quality;
perform a continuing analysis of changes or trends in the national environment; review and
appraise programs of the federal government to determine their contributions to sound
environmental policy; and oversee implementation of NEPA.8
CEQ and Agency Regulations
CEQ has been instrumental in implementing NEPA by developing regulations that provide more
details about what agencies must do when creating a detailed statement or taking other actions to
comply with NEPA. President Carter ordered CEQ to develop regulations to implement NEPA.9
The 1978 regulations10 created the baseline for agencies structuring their own NEPA procedures
and regulations. The Trump Administration amended parts of these regulations in 2020.11 In
October 2021, the Biden Administration proposed to reinstate some provisions of the 1978

3 Id. § 4332(2)(C)(i)-(v).
4 Id. § 4332(2)(C).
5 Id.
6 Id. § 4342.
7 Id.
8 Id. § 4344.
9 Exec. Order No. 11514, 3 C.F.R. 902 (1970 Comp.), as amended by Exec. Order No. 11991, 3 C.F.R. 123 (1977
Comp.).
10 National Environmental Policy Act—Regulations; Implementation of Procedural Provisions, 43 Fed. Reg. 55,978
(Nov. 29, 1978) (codified at 40 C.F.R. pts. 1500-1508).
11 Update to the Regulations Implementing the Procedural Provisions of the National Environmental Policy Act, 85
Fed. Reg. 43,304 (July 16, 2020) (codified at 40 C.F.R. pts. 1500-1508).
Congressional Research Service

2

Judicial Review and the National Environmental Policy Act of 1969

regulations that the 2020 rulemaking amended or eliminated.12 The Biden Administration
finalized part of its revisions (“Phase One”) in April 2022.13
Major Federal Actions
While NEPA applies to all agencies, as discussed above, it imposes requirements on those
agencies only when they undertake major federal actions.14 NEPA does not define what qualifies
as “major federal actions,” prompting one Supreme Court Justice to note that the statute could
thus “hardly be termed precise.”15 However, federal courts have interpreted the phrase, and
CEQ’s 2020 regulations (informed by that case law) listed actions that tend to qualify as major
federal actions and those that do not. As CEQ’s 2020 rule stated, the list reflects the court
decisions regarding whether actions are “major federal actions” that CEQ chose to include in the
regulations.16
First, the regulations describe what “may” qualify as a major federal action: (1) new and
continuing activities, including projects and programs entirely or partly financed, assisted,
conducted, regulated, or approved by federal agencies; (2) new or revised agency rules,
regulations, plans, policies, or procedures; and (3) legislative proposals.17
Second, the regulations list categories of actions that do not qualify or that “tend” to qualify as
major federal actions. Categories of actions that do not qualify are
 extraterritorial activities or decisions, which means agency activities or decisions
with effects located entirely outside of the jurisdiction of the United States;
 activities or decisions that are nondiscretionary and made in accordance with the
agency’s statutory authority;
 activities or decisions that do not result in final agency action under the
Administrative Procedure Act or another statute that includes a finality
requirement;18
 judicial or administrative civil or criminal enforcement actions;
 funding assistance solely in the form of general revenue sharing funds with no
federal agency control over the subsequent use of such funds;
 nonfederal projects with minimal federal funding or minimal federal involvement
where the agency does not exercise sufficient control and responsibility over the
outcome of the project; and

12 National Environmental Policy Act Implementing Regulations Revisions; Notice of Proposed Rulemaking, 86 Fed.
Reg. 55,757 (Oct. 7, 2021).
13 National Environmental Policy Act Implementing Regulations Revisions; Final Rule, 87 Fed. Reg. 23,453 (Apr. 20,
2022).
14 42 U.S.C. § 4332(c) (“major Federal actions significantly affecting the quality of the human environment”).
15 Kleppe v. Sierra Club, 427 U.S. 390, 420-21 (1976) (Marshall, J., concurring in part and dissenting in part).
16 Update to the Regulations Implementing the Procedural Provisions of the National Environmental Policy Act, 85
Fed. Reg. 43,345-43,346 (July 16, 2020).
17 40 C.F.R. § 1508.1(q)(2). These lists were amended or included in the Biden Administration’s “Phase One”
revisions.
18 Under the Administrative Procedure Act (APA) and some other statutes, an agency action must be “final” before an
individual affected by an agency’s actions may seek judicial review of the action. The Supreme Court defines as “final”
actions that (1) mark the “consummation” of an agency’s decisionmaking process and (2) determine rights or
obligations or result in legal consequences. Bennett v. Spear, 520 U.S. 154, 177-78 (1997).
Congressional Research Service

3

Judicial Review and the National Environmental Policy Act of 1969

 loans, loan guarantees, or other forms of financial assistance where the federal
agency does not exercise sufficient control and responsibility over the effects of
such assistance.19
Categories of proposed actions that “tend” to qualify as major federal actions are
 adoption of official policy, such as rules, regulations, and interpretations adopted
under the APA or other statutes;
 implementation of treaties and international conventions or agreements,
including those implemented pursuant to statute or regulation;
 formal documents establishing an agency’s policies which will result in or
substantially alter agency programs;
 adoption of formal plans, such as official documents prepared or approved by
federal agencies, which prescribe alternative uses of federal resources, upon
which future agency actions will be based;
 adoption of programs, such as a group of concerted actions to implement a
specific policy or plan;
 systematic and connected agency decisions allocating agency resources to
implement a specific statutory program or executive directive; and
 approval of specific projects, such as construction or management activities
located in a defined geographic area, including those approved by permit or other
regulatory decision as well as federal and federally assisted activities.20
The types of actions that might fall within the scope of major federal actions reach a wide variety
of proposals considered by federal agencies. Examples of major federal actions include
development of wildlife management plans; issuance of commercial use permits within federally
managed lands; construction of new rail lines or facilities; approval of airport layouts; and natural
gas pipeline approvals.21
Determining Significance: Which Level of Environmental Review Is
Appropriate?

Whether a proposed major federal action is expected to cause significant effects on the human
environment determines the level of environmental review an agency must complete to
demonstrate that it has met the requirements of NEPA. Depending on whether the potential
effects are or are not significant, agencies proceed in one of three ways: (1) categorical exclusion;
(2) environmental assessment (EA); or (3) environmental impact statement (EIS). In general,
agencies’ NEPA regulations set out certain types of actions that they consider to be subject to each
of these levels of review, based on their experiences and other analyses. CEQ estimates that

19 40 C.F.R. § 1508.1(q)(1).
20 Id. § 1508.1(q)(3).
21 See, e.g., National Park Service, NEPA Handbook,
https://www.nps.gov/subjects/nepa/upload/NPS_NEPAHandbook_Final_508.pdf; FERC, Environmental Documents,
https://www.ferc.gov/industries-data/natural-gas/environmental-overview/environmental-documents-2022; U.S. Dep’t
of Transportation, Order 5610.1D, Procedures for Considering Envt’l Impacts (draft),
https://www.transportation.gov/office-policy/transportation-policy/dot-order-56101d-procedures-considering-
environmental-impacts.
Congressional Research Service

4

Judicial Review and the National Environmental Policy Act of 1969

agencies demonstrate NEPA compliance through categorical exclusions for 95% of actions that
are subject to NEPA; EAs for approximately 4%; and EISs for 1%.22
No Significant Impacts: Categorical Exclusions
When a proposed action will not have significant impacts, an agency may use a categorical
exclusion to demonstrate that NEPA does not require detailed analysis. Agencies identify types of
actions that normally do not result in significant impacts and thus require no environmental
review, and list these categorical exclusions in their NEPA regulations.23 In these regulations,
agencies also include provisions for addressing when actions that typically fall into a categorical
exclusion require environmental review due to “extraordinary circumstances.”24 Congress may
also identify categorical exclusions in the first instance.25
Significant Impacts Uncertain: Environmental Assessment
For proposed federal actions that may have some impacts—but potentially not significant
impacts—agencies may prepare an EA, although they may proceed directly to an EIS instead.
The process of preparing an EA can help an agency determine whether to make a Finding of No
Significant Impact (FONSI) or, alternatively, instead prepare a full EIS.26 While preparing an EA,
an agency must involve stakeholders “to the extent practicable.”27 In addition, when a proposed
action is similar to those that typically require an EIS or is unprecedented in nature, an agency
must release a draft FONSI for public review before making its final determination.28
Significant Impacts: Environmental Impact Statement
Proposed actions with significant environmental impacts require an agency to prepare an EIS
(i.e., the “detailed statement” required by NEPA).29 This statement is generally the most
comprehensive of the types of environmental review documents that an agency may use to
comply with NEPA. Although the CEQ regulations require each EIS to be either (1) less than 150
pages or (2) less than 300 pages for projects of “unusual scope or complexity,” unless an
appropriate official authorizes a longer page limit,30 it is common for an EIS to exceed this
length.31
As detailed above, NEPA requires each EIS to analyze the five types of information listed in the
statute. While preparing an EIS, an agency must also submit a draft EIS to the public for review32

22 U.S. Government Accountability Office, National Environmental Policy Act: Little Information Exists on NEPA
Analyses
, GAO-14-370 at 7 (Apr. 2014) (citing CEQ statistics).
23 40 C.F.R. § 1501.4.
24 Id. § 1501.4(b).
25 See, e.g., 42 U.S.C. § 15492. Congress sometimes also provides direction about how an agency should make
categorical exclusion determinations. See, e.g., 49 U.S.C. § 304.
26 40 C.F.R. § 1501.5.
27 Id.
28 Id. § 1501.6(a)(2).
29 Id. pt. 1502.
30 Id. § 1502.7.
31 Council on Envt’l Quality, Length of Envt’l Impact Statements (2013-2018) (June 2020),
https://ceq.doe.gov/docs/nepa-practice/CEQ_EIS_Length_Report_2020-6-12.pdf.
32 Id. § 1503.1.
Congressional Research Service

5

Judicial Review and the National Environmental Policy Act of 1969

and respond to comments received.33 Once an agency completes an EIS, it must issue a Record of
Decision (ROD), which identifies the agency’s decision regarding the proposed action, alternative
actions considered, and any mitigation measures that will be implemented.34
Supplemental Environmental Review
Although NEPA does not expressly require an agency to perform a supplemental review, the
Supreme Court has indicated that NEPA implies such a requirement in some cases.35 CEQ’s
regulations codify this requirement. Specifically, agencies must prepare supplemental analyses
when major federal action remains to occur and (1) “the agency makes substantial changes to the
proposed action that are relevant to environmental concerns” or (2) “there are significant new
circumstances or information relevant to environmental concerns and bearing on the proposed
action or its impacts.”36 An agency may also prepare a supplemental EIS whenever it determines
that doing so furthers NEPA’s purposes.37
Judicial Review of NEPA: An Overview
NEPA contains no provision addressing the availability of judicial review. Instead, plaintiffs may
challenge an agency’s compliance with NEPA under the APA.38 The APA generally establishes
how courts review final agency actions, including the appropriate standards of review. Among
other things, courts may find an agency action unlawful and set it aside if it was “arbitrary,
capricious, an abuse of discretion, or otherwise not in accordance with law.”39 In the NEPA
context, plaintiffs often allege that an agency’s actions were arbitrary or capricious, and thus
violate the APA. Reviewing courts generally interpret this to mean that they must consider
whether an agency took a “hard look” at the environmental consequences of their proposed
actions, considered alternatives, and publicly disclosed such information before reaching a final
decision.40 Thus, a court may not “substitute its judgment for that of the agency.”41 In other
words, neither NEPA, nor the courts, direct agencies to prioritize certain values over others or to
reach specific outcomes. It “prohibits uninformed—rather than unwise—agency action.”42

33 Id. § 1503.4.
34 Id. § 1505.2.
35 Marsh v. Or. Nat. Res. Council, 490 U.S. 360, 370-71 (1989) (“The subject of postdecision supplemental
environmental impact statements is not expressly addressed in NEPA. Preparation of such statements, however, is at
times necessary to satisfy the Act’s ‘action-forcing’ purpose.”).
36 40 C.F.R. § 1502.9(d)(1).
37 Id. § 1502.9(d)(2).
38 See, e.g., Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 882 (1990) (“Respondent does not contend that . . . NEPA
provides a private right of action for violations of its provisions. Rather, respondent claims a right to judicial review
under § 10(a) of the APA.”).
39 5 U.S.C. § 706. For more information about the APA, see CRS Legal Sidebar LSB10558, Judicial Review Under the
Administrative Procedure Act (APA)
.
40 Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989).
41 Kleppe v. Sierra Club, 427 U.S. 390, 410 n.21 (1976).
42 Methow Valley Citizens Council, 490 U.S. at 351.
Congressional Research Service

6

Judicial Review and the National Environmental Policy Act of 1969

Limits on Judicial Review
The Constitution, the courts, and Congress may limit judicial review of actions taken to comply
with NEPA. This section provides an overview of some of these limitations.
Standing
A plaintiff must have standing to bring a case. Article III of the Constitution requires a plaintiff to
demonstrate an injury in fact that is caused by the alleged statutory violation and that can be
remedied by a court.43 In the NEPA context, injuries are generally procedural in nature (i.e., a
plaintiff is harmed by an agency’s failure to follow NEPA procedures), but to meet the Article III
injury threshold, a plaintiff must allege that the agency’s action will harm the plaintiff’s concrete
interest and that the relevant procedure is designed to protect that interest. For example, in
Cantrell v. City of Long Beach, plaintiffs alleged the Navy did not comply with NEPA in
proposing to convert a closed naval station to a commercial marine container terminal.44 The
plaintiffs were “birdwatchers,” residents of Long Beach and Lakewood, CA, who opposed the
Navy’s plans.45 The U.S. Court of Appeals for the Ninth Circuit held that plaintiffs sufficiently
alleged an injury by pleading that the naval station was currently home to bird habitats, which
plaintiffs enjoyed recreationally as birdwatchers, and that their ability to enjoy the habitats would
be impaired by the proposed conversion.46
The Constitution also prohibits courts from addressing alleged injuries that are “generalized
grievances,” as these do not present “cases” or “controversies,” as required by Article III.47 For
example, plaintiffs asserting “generalized harm to the forest or the environment” lack a concrete
or particularized injury. By contrast, if they assert that harm “affects the recreational or even
the[ir] mere esthetic interests,” then plaintiffs may satisfy the Constitution’s standing
requirements.48
Finally, plaintiffs must demonstrate that the type of injury alleged falls within the “zone of
interests” of the statute invoked.49 The Supreme Court has held that NEPA protects a broad range
of harms, including recreational or aesthetic enjoyment of the environment.50 However, NEPA
does not reach purely economic injuries.51 As the Third Circuit explained:
To accept NEPA litigants whose interests accidentally overlap with the statute’s intended
purpose would not only create a class of plaintiffs far larger than Congress originally
intended, it also would serve to distort the effect of NEPA itself.52

43 Friends of the Earth v. Laidlaw, 528 US 167, 180-81 (2000); Lujan v. Defenders of Wildlife, 504 U.S. 555, 560
(1992).
44 Cantrell v. City of Long Beach, 241 F.3d 674 (9th Cir. 2001).
45 Id. at 676-77.
46 Id. at 682.
47 Lexmark Int’l, Inc. v. Static Control Components, Inc., 572 U.S. 118, 127 n.3 (2014).
48 Summers v. Earth Island Inst., 555 U.S. 488, 494 (2009).
49 Id. at 127-28. The Supreme Court previously described this requirement as part of its “prudential standing” doctrine,
but in Lexmark, recharacterised the requirement as a question of statutory interpretation. Id.
50 Lujan v Nat’l Wildlife Fed’n, 497 US 871 (1990).
51 See, e.g., Maiden Creek Assoc. LP v. U.S. Dep’t of Transp., 823 F.3d 184, 194 (3d Cir. 2016); Ashley Creek
Phosphate Co. v. Norton, 420 F.3d 934, 940 (9th Cir. 2005).
52 Maiden Creek Assoc. LP, 823 F.3d at 194.
Congressional Research Service

7

Judicial Review and the National Environmental Policy Act of 1969

Nonetheless, plaintiffs who allege both environmental and economic injuries may satisfy the
“zone of interests” test.53 Further, plaintiffs who assert environmental injuries, but whose primary
motive for bringing a case is economic interest, also “routinely satisfy” this test.54
Aside from individuals who bring NEPA cases, organizations often bring cases on behalf of their
members. They may do so if (1) at least one of the members has standing; (2) the interests that the
organization seeks to protect are germane to its purposes; and (3) neither the claim nor the type of
relief sought would require the individual members to actively participate in the litigation.55
Statute of Limitations
NEPA does not include a statute of limitations—i.e., a time by which a plaintiff must file a
lawsuit. As discussed above, plaintiffs generally bring NEPA claims using the APA. Courts have
generally held that the statute requiring civil claims against the United States to be brought within
six years applies to APA claims.56 Congress may legislate other time limitations for NEPA claims
if it so chooses. For example, in the Fixing America’s Surface Transportation Act, Congress
imposed a two-year statute of limitations on certain infrastructure projects that require
environmental review under NEPA.57
Exhaustion
Courts generally require plaintiffs to raise their issues with the relevant agency during the
appropriate comment period for the proposed agency action, and if plaintiffs do not do so, the
courts may bar them from later filing a claim involving those issues.58 Nonetheless, the Supreme
Court has suggested that flaws in an EA or EIS “might be so obvious that there is no need for a
commentator to point them out specifically in order to preserve its ability to challenge a proposed
action.”59 Some federal appellate courts follow the Supreme Court’s dicta, allowing some NEPA
challenges to move forward even if the issues were not raised during the public comment
period.60
CEQ’s 2020 regulations state that comments on issues not raised during the public comment
period “shall be considered unexhausted and forfeited.”61 That was a departure from CEQ’s 1978
regulations, which did not expressly limit judicial review of an agency’s NEPA compliance to

53 Centr. S. Dak. Co-op Grazing Dist. v. Sec’y of U.S. Dep’t of Agric., 266 F.3d 889, 895-96 (8th Cir. 2001).
54 Nat’l Ass’n of Home Builders v. U.S. Army Corps of Eng’rs, 417 F.3d 1272, 1287 (D.C. Cir. 2005).
55 Sierra Club v. Morton, 405 U.S. 727, 739-40 (1972); Sierra Club v. FERC, 827 F.3d 59, 65 (D.C. Cir. 2016) (citing
Hunt v. Wash. State Apple Adver. Comm’n, 432 U.S. 333, 343 (1977)).
56 See, e.g., Jersey Hgts. Neighborhood Ass’n v. Glendening, 174 F.3d 180, 186 (4th Cir. 1999); Sierra Club v. Slater,
120 F.3d 623, 630-31 (6th Cir. 1997); Sierra Club v. Penfold, 857 F.2d 1307, 1315 (9th Cir. 1988). Accord Sierra Club
v. U.S. Army Corps of Eng’rs, 446 F.3d 808, 815 (8th Cir. 2006) (noting without deciding that other courts use the six-
year statute of limitations). 28 U.S.C. § 2401(a) states that “every civil action commenced against the United States
shall be barred unless the complaint is filed within six years after the right of action first accrues.”
57 42 U.S.C. § 4370m-6; id. § 4370m(6) (defining “covered project”).
58 Vt. Yankee Nuclear Power Corp. v. Nat. Res. Def. Council, 435 U.S. 519, 553 (1978).
59 Dep’t of Transp. v. Pub. Citizen, 541 U.S. 752, 765 (2004).
60 See, e.g., Friends of Tims Ford v. Tenn. Valley Auth., 585 F.3d 955, 964 (6th Cir. 2009) (allowing a NEPA challenge
to proceed because the agency had not shown why the “deficient” EIS “was not so obvious that [plaintiffs] needed to
comment to preserve its right to appeal”).
61 40 C.F.R. § 1503.3(b) (2020).
Congressional Research Service

8

Judicial Review and the National Environmental Policy Act of 1969

issues raised through public comment, and may be in tension with the Supreme Court’s dicta.62 In
any event, Congress may also legislate on the issue of exhaustion, providing either that potential
plaintiffs must or need not comment during administrative proceedings to preserve an issue for
judicial review.63
Remedies in NEPA Litigation
Plaintiffs ask for a variety of remedies in NEPA litigation. In general, when a plaintiff prevails in
a NEPA case, a court grants declaratory relief and may remand the disputed action to the agency.
The agency then must either abandon its proposed action or take steps to remedy the APA
violations by producing an environmental review that demonstrates that it has complied with
NEPA in selecting that action.
Courts often vacate an agency’s final action in addition to remanding to the agency, meaning that
the agency’s original decision is declared void and ineffective. When a court finds that an agency
violated the APA, the statute directs the court to “set aside”—i.e., vacate—the agency’s action.64
Thus, in NEPA cases, courts have recognized that vacatur is the “ordinary” remedy.65
Nonetheless, courts have created an equitable exception, sometimes ordering remand without
vacatur. That remedy allows the agency’s original action or decision to remain in place while the
agency corrects a deficiency in its NEPA compliance. The leading articulation of this exception is
Allied-Signal, Inc. v. Nuclear Regulatory Commission.66 In this case, the D.C. Circuit stated that
not all actions that violate the APA must be vacated; rather, the court should consider (1) “the
seriousness of the order’s deficiencies” and (2) “the disruptive consequences of” vacatur.67
Applying this test, one court of appeals declined to vacate the Federal Energy Regulatory
Commission’s environmental review on the ground that the agency was “likely to remedy any
deficiencies in its orders on remand, and because vacating the orders would imperil Intervenors’
ability to obtain funding necessary to complete the projects in a timely fashion.”68 By contrast,
another court of appeals affirmed a district court’s decision to vacate a U.S. Army Corps of
Engineers’ decision on the ground that the Corps had previously failed to remedy APA violations
and comply with NEPA.69
According to some legal scholars, the use of the “remand without vacatur” remedy has increased
since the 1970s, particularly in the D.C. Circuit and primarily in cases involving the Clean Air
Act rather than NEPA.70 Judges and practitioners continue to debate whether that remedy is legal

62 See id. § 1503.3 (2019) (detailing specificity of public and agency comments). It is unclear whether the Biden
Administration will seek to amend this provision in its “Phase Two” reforms to CEQ’s regulations.
63 See, e.g., 42 USC 4370m-6(a)(1)(B).
64 5 U.S.C. § 706(2).
65 Black Warrior Riverkeeper v. U.S. Army Corps of Eng’rs, 781 F.3d 1271, 1290 (11th Cir. 2015) (discussing history
of remand without vacatur).
66 988 F.2d 146 (D.C. Cir. 1993).
67 Id. at 150-51.
68 Vecinos para el Bienestar de al Comunidad Costera v. Fed. Energy Reg. Comm’n, 6 F.4th 1321, 1332 (D. C. Cir.
2021).
69 Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 985 F.3d 1032, 1050-53 (D.C. Cir. 2021).
70 Stephanie J. Tatham, The Unusual Remedy of Remand Without Vacatur, Administrative Conference of the United
States at 30-36 (Jan. 3, 2014),
https://www.acus.gov/sites/default/files/documents/Remand%20Without%20Vacatur%20Final%20Report.pdf.
Congressional Research Service

9

link to page 13 Judicial Review and the National Environmental Policy Act of 1969

and appropriate, however, because it is in tension with the APA’s textual instruction that courts
“set aside” unlawful agency actions and because it is inconsistently granted by the courts.71
In some cases, parties request permanent injunctive relief in addition to the types of remedies
discussed above. Vacatur often has the same practical effect as a permanent injunction in that,
once an agency’s final decision is set aside, an agency cannot proceed with the proposed action.
However, while vacatur generally leaves an agency free to make a new decision without further
court supervision, an injunction may provide a more specific direction to an agency prohibiting it
from proceeding with part or all of a proposed action until the agency comes into compliance
with NEPA.72 In choosing between those two remedies, the Supreme Court has stressed there is
no “thumb on the scales” in favor of an injunction.73 Instead, the Court affirmed that the
traditional requirements for permanent injunctive relief apply in the NEPA context:
A plaintiff must demonstrate: (1) that it has suffered an irreparable injury; (2) that remedies
available at law, such as monetary damages, are inadequate to compensate for that injury;
(3) that, considering the balance of hardships between the plaintiff and defendant, a remedy
in equity is warranted; and (4) that the public interest would not be disserved by a
permanent injunction.74
CEQ data on NEPA litigation from 2001 to 2011 indicates that the number of injunctions varied
significantly, although never reaching above 18 per year (Table 1).75
Table 1. NEPA Litigation Injunctions, 2001-2011
Preliminary Injunctions Granted Per Year
Permanent Injunctions Issued Per Year
Year
Number
Year
Number
2001
5
2001
0
2002
4
2002
8
2003
4
2003
2
2004
6
2004
1
2005
18
2005
7
2006
8
2006
16
2007
10
2007
18
2008
6
2008
10
2009
2
2009
15
2010
5
2010
4
2011
5
2011
3
Source: Created by CRS with data from CEQ.

71 See id. at 9-18.
72 See, e.g., Minn. Pub. Interest Research Grp. v. Butz, 358 F. Supp. 584 (D. Minn. 1973) (issuing injunction after
Forest Service indicated it would continue to log approximately 3,000 acres despite the court’s ruling that the Service’s
EIS on the logging project was deficient).
73 Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 157 (2010).
74 Id. at 156-57 (quoting eBay Inc. v. MercExchange L.L.C., 547 U.S. 388, 391 (2006)).
75 CEQ, NEPA Litigation Surveys: 2001-2013, https://ceq.doe.gov/docs/ceq-reports/nepa-litigation-surveys-2001-
2013.pdf. CEQ did not report on whether courts granted any requests for permanent injunctions in 2012 or 2013.
Congressional Research Service

10

Judicial Review and the National Environmental Policy Act of 1969

When plaintiffs file a complaint, they sometimes request a preliminary injunction, which is an
order prohibiting an agency from implementing the action in dispute while the litigation is
ongoing.
The Supreme Court most recently addressed what a party seeking a preliminary injunction must
demonstrate in Winter v. Natural Resources Defense Council. In that case, the Court emphasized
its “frequently reiterated standard” for obtaining a preliminary injunction:
A plaintiff seeking a preliminary injunction must establish that he is likely to succeed on
the merits, that he is likely to suffer irreparable harm in the absence of preliminary relief,
that the balance of equities tips in his favor, and that an injunction is in the public interest.76
Selected Issues in NEPA Litigation
NEPA litigation involves a wide range of agencies and raises issues involving agency choices and
determinations. This section provides an overview of selected issues raised in NEPA litigation
that may be of interest to Congress.
Confirming When NEPA Review Is Required
Courts must occasionally address what happens when an agency is faced with a potential conflict
between NEPA and other statutory mandates. As discussed above, the requirements of NEPA
apply “to the fullest extent possible.”77 In other words, as the Supreme Court has held, NEPA was
not intended to repeal any other statute by implication. Thus, when “a clear and unavoidable
conflict in statutory authority exists, NEPA must give way.”78 Such a conflict may exist, for
example, if the period for implementing a statutory mandate is too short for an agency to
complete environmental review under NEPA.79
Related to this point, an agency need include in its environmental analyses only those alternatives
it has discretion to select. As the Supreme Court described, agencies should be guided by a “rule
of reason” when taking steps to comply with NEPA, and such a rule is not served by requiring
agencies to evaluate the effects of actions it lacks legal authority to prevent.80 In Department of
Transportation v. Public Citizen
, the Supreme Court considered whether the Federal Motor
Carrier Safety Administration (FMCSA) failed to satisfy NEPA by not considering the
environmental effects related to increased entry of trucks from Mexico into the United States. The
Court held that the FMCSA did not violate NEPA because the agency lacked any statutory ability
to regulate or prevent the cross-border traffic, which had been ordered by the President in
response to a ruling from an arbitral panel convened under the North American Free Trade
Agreement.81
Some courts also hold NEPA does not apply when an agency’s actions to comply with other
statutes are “functionally equivalent” to NEPA. This requires courts to assess, on a case-by-case
basis, what an agency must take into account when complying with other statutes, especially

76 Winter, 555 U.S. at 20-21.
77 42 U.S.C. § 4332(2).
78 Flint Ridge Dev. Corp. v. Scenic Rivers Ass’n of Okla., 426 U.S. 776, 788 (1976).
79 Id. at 788-89 (“inconceivable” that an agency could comply with NEPA within 30-day deadline for issuance of
statement of record under Disclosure Act).
80 Dep’t of Transp. v. Pub. Citizen, 541 U.S. 762, 767-68 (2004).
81 Id. at 768; see also Ala. Wilderness League v. Jewell, 788 F.3d 1212, 1225-26 (9th Cir. 2015).
Congressional Research Service

11

Judicial Review and the National Environmental Policy Act of 1969

environmental effects or considerations.82 Other courts do not use the “functional equivalent”
approach, instead asking whether another statute has “displaced” NEPA.83
Assessing Significance of Impacts
Plaintiffs sometimes challenge an agency’s assessment of whether an action will have significant
impacts, arguing that an agency inappropriately relied on a categorical exclusion or should have
prepared an EIS instead of an EA.
Use of Categorical Exclusions
When an agency relies on a categorical exclusion (CX) to determine that further NEPA analysis is
not required, plaintiffs may argue that the agency (1) improperly used a CX for a specific action
or (2) created an improperly scoped CX.
In disputes involving challenges to specific uses of CXs, plaintiffs have raised different theories
under the APA. For instance, in some cases, plaintiffs have alleged that an agency failed to
document its determination to use a CX. In Wilderness Watch & Public Employees for
Environmental Responsibility v. Mainella
, plaintiffs alleged that the National Park Service’s
decision to use a CX to authorize tourist operation of motor vehicles on protected “wilderness
areas” violated the APA because the agency failed to document its decision.84 The Park Service
argued it did not need to document its decision because requiring any such written evidence
would “defeat the purpose of the exclusion.”85 The Eleventh Circuit rejected that argument,
holding that the agency’s failure to provide any documents to indicate why use of a CX was
appropriate made it “difficult for a reviewing court to determine if the application of an exclusion
is arbitrary and capricious.”86
In other cases, plaintiffs challenge whether an agency reasonably determined that no
“extraordinary circumstances” existed that would have prevented the agency from relying on a
CX. For instance, in Alaska Center for the Environment v. U.S. Forest Service, the Forest Service
relied on a CX to issue one-year licenses for commercial helicopter activities in National Forest
lands.87 Plaintiffs sued, alleging that such activities would have significant environmental impacts
and fell within the “extraordinary circumstances” exception to the CX.88 The Ninth Circuit
affirmed the district court’s decision that the Forest Service acted arbitrarily and capriciously
when issuing certain licenses because it merely restated the CX and failed to provide reasons for
why the CX applied.89

82 See, e.g., Envtl. Def. Fund, Inc. v. Envtl. Protection Agency, 489 F.2d 1247 (D.C. Cir. 1973) (holding FIFRA the
functional equivalent of NEPA since the statute required the agency to take environmental effects into account and
consider public comments about such effects). See also Pac. Legal Fndtn. v. Andrus, 657 F.2d 829, 834 (6th Cir. 1981)
(discussing lower court practice applying the “functional equivalent” test).
83 See, e.g., San Luis & Delta-Mendota Water Auth. v. Jewell, 747 F.3d 581, 650-51 (9th Cir. 2014) (Section 7 of the
Endangered Species Act does not displace NEPA requirements and agency must comply with both statutes).
84 375 F.3d 1085, 1094 (11th Cir. 2004).
85 Id.
86 Id. See also California v. Norton, 311 F.3d 1162 (9th Cir. 2002).
87 189 F.3d 851 (9th Cir. 1999).
88 Id. at 854.
89 Id. at 859.
Congressional Research Service

12

Judicial Review and the National Environmental Policy Act of 1969

As noted above, plaintiffs sometimes seek to invalidate an agency’s adoption of a CX. In Sierra
Club v. Bosworth
, the plaintiffs alleged that the Forest Service violated by the APA by
categorically excluding all fuel reduction projects of up to 1,000 acres and burn projects of up to
4,500 acres.90 The Ninth Circuit concluded that the Forest Service’s CX violated the APA because
the Service (1) collected data only to justify, rather than assess, the appropriateness of a CX; (2)
failed to explain why the cumulative effect of each project would not have significant
environmental effects; and (3) failed to specify criteria for each project that would ensure they
had no significant environmental effects.91
Use of EA/FONSI Instead of EIS
Agencies and plaintiffs sometimes disagree about whether an agency should have prepared an
EIS in instances when an agency had prepared an EA, concluded that the project would not result
in significant environmental effects, and then issued a FONSI.
Some plaintiffs assert that an agency failed to take the requisite “hard look” by reasonably
assessing the evidence before it. For example, in O’Reilly v. U.S. Army Corps of Engineers, the
Fifth Circuit considered whether the Corps reasonably issued an EA and FONSI when it had
allegedly failed to explain how mitigation measures would offset environmental damage.92 The
Fifth Circuit found that “the EA provides only cursory detail as to what those measures are and
how they serve to reduce those impacts to a less-than-significant level,” and thus the agency did
not comply with NEPA.93 By contrast, in Spiller v. White, the Fifth Circuit upheld a FONSI for a
project approving use of a pre-existing pipeline to transport petroleum products, subject to
specific mitigation measures.94 Specifically, the court found that the “exhaustive and extensive”
EA demonstrated that the agencies adequately considered and explained the proposed mitigation
measures and how such measures could offset the environmental impacts caused by the pipeline’s
use.95
Other disputes involve questions about an agency’s reliance on certain types of information. As
discussed above, one of NEPA’s objectives is to ensure that agencies are informed about the
environmental consequences of their actions. Litigation thus arises about whether an agency
inappropriately relied on outdated information. In Native Ecosystems Council v. U.S. Forest
Service
, the Forest Service had prepared an EA for a resource management plan covering parts of
the Helena National Forest as a means of reducing the number of high-intensity, stand-replacing
fires. Based in part on a 1996 EIS it had prepared for a larger-scale version of the newly proposed
resource management plan, the Forest Service concluded that the management techniques would
not create significant environmental impacts. Plaintiff argued that the Forest Service erred in
relying on the 1996 EIS in part because subsequent data showed that the 1996 project eliminated
one pair of goshawks (a bird species inhabiting the area). The Ninth Circuit rejected plaintiff’s
claim, finding that the Forest Service took a “hard look” by considering this fact against other

90 510 F.3d 1016 (9th Cir. 2007).
91 Id. at 1026-33.
92 477 F.3d 225 (5th Cir. 2007).
93 Id. at 234.
94 352 F.3d 235 (5th Cir. 2003).
95 Id. at 241-44.
Congressional Research Service

13

Judicial Review and the National Environmental Policy Act of 1969

data showing that goshawks change nesting sites each year and nest near logged sites before
concluding that the proposed project would not have significant effects on the goshawks.96
Courts that determine an agency violated the APA when issuing a FONSI must decide whether to
remand with the specific instruction to prepare a new EA or a full EIS. As explained by the Fifth
and Ninth Circuits, a deficient EA does not necessarily warrant such an instruction. Rather, such
an instruction may be warranted if “the evidence in a complete administrative record
demonstrates that the project or regulation may have a significant impact.”97 By contrast, when a
court cannot determine whether a proposed action will have significant impacts, it may remand
with instructions for the agency to comply with NEPA through the appropriate environmental
review process.98 For example, in O’Reilly v. U.S. Army Corps of Engineers, the Fifth Circuit
remanded with instructions to prepare a new EA or an EIS, as appropriate, because the court
could not determine, based on the agency’s deficient explanations, whether or not the proposed
mitigation measures would eliminate significant environmental effects.99
Supplemental Environmental Review
Plaintiffs sometimes claim that an agency failed to prepare an appropriate supplemental
environmental review. These disputes tend to center on whether new information or changes to a
proposed action trigger additional NEPA requirements. For example, in DuBois v. U.S.
Department of Agriculture
, the Forest Service issued a permit for expansion of a ski facility in a
national forest, approving “Alternative 6” in the final EIS.100 Plaintiffs challenged the permit,
arguing that Alternative 6 appeared for the first time in the final EIS and represented a substantial
change from the original proposal and other alternatives listed in the draft EIS, thus requiring the
Forest Service to prepare a supplemental EIS. The First Circuit agreed with plaintiffs, finding that
Alternative 6 was sufficiently different from the other alternatives considered in the EIS that
“public commenters might have pointed out, if given the opportunity—and the Forest Service
might have seriously considered—wholly new problems posed.”101 Based on these findings, the
court ordered the Forest Service to prepare a supplemental EIS.
Adequacy of an EA or EIS
Plaintiffs sometimes challenge the procedural or substantive adequacy of an EA or EIS, with
issues ranging from an agency’s alleged failure to consider certain effects or alternative proposals
to an agency’s alleged failure to consult adequately with the public.
Failure to Adequately Consider Effects in an EA or EIS102
In some cases, plaintiffs allege that an agency failed to analyze adequately all relevant effects in
an EA or EIS and therefore violated the APA. In these cases, courts review the agency’s analysis

96 Id. at 1243-44.
97 Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172, 1225 (9th Cir. 2008); see also
O’Reilly v. U.S. Army Corps of Eng’rs, 477 F.3d 225, 239 (5th Cir. 2007).
98 Id.
99 O’Reilly, 477 F.3d at 240-41.
100 102 F.3d 1273 (1st Cir. 1996).
101 Id. at 1292-93.
102 This section was prepared by CRS Legislative Attorney Adam Vann.
Congressional Research Service

14

Judicial Review and the National Environmental Policy Act of 1969

to determine whether the agency’s decision to limit or exclude consideration of particular effects
was arbitrary or capricious. Plaintiffs frame these claims in a variety of ways.
For example, some plaintiffs argue that an agency’s evaluation of a particular effect was
insufficient because the agency lacked enough data to make a reasoned decision. The Tenth
Circuit considered this type of claim in Colorado Environmental Coalition v. Dombeck. In that
case, plaintiffs argued that the Forest Service failed to gather sufficient data about the effects of
expansion of a ski area on the lynx population and failed to disclose in the EIS that such
information was unavailable.103 The Tenth Circuit disagreed with plaintiffs, holding that the
record demonstrated that the Service collected and analyzed the “best available data” while also
explaining the data’s limitations, and held that plaintiffs’ claim amounted to nothing more than an
effort to impose additional data gathering requirements on the agency.104
Other cases involve allegations that an agency failed to assess the cumulative impacts of proposed
actions. Cumulative impacts “result from the incremental effects of the action when added to the
effects of other past, present, and reasonably foreseeable actions regardless of what agency
(Federal or non-Federal) or person undertakes such other actions.”105 Agencies retain some
discretion as to how to make these assessments, and the courts examine whether the methodology
or explanation was reasonable. For example, the Sixth Circuit concluded that the U.S. Army
Corps of Engineers could reasonably look at the effects of prior permits for mining activities that
discharged dredged or fill material into U.S. waterways “in the aggregate” as a method of
performing a cumulative impacts analysis.106 The court concluded, however, that the Corps did
not comply with the cumulative impact analysis requirement because the Corps described its
methodology but then “failed to identify any impact—aggregate or otherwise—of past
actions.”107 By contrast, the Ninth Circuit upheld a Bureau of Reclamation EA with regard to its
consideration of past events that may have cumulative impacts on the proposed action.
Specifically, the court held that although the agency’s discussion in the “cumulative effects” part
of the EA was vague and cursory, the EA overall included “quantified or detailed information”
relevant to cumulative impacts and satisfied NEPA’s requirements.108
Another set of cases involves allegations that an agency failed to consider all relevant indirect
effects
arising from a proposed action. Recent federal litigation involving indirect effects has
addressed how agencies should consider the effects of climate change in their NEPA analyses. In
2017, the D.C. Circuit issued a significant decision assessing the Federal Energy Regulatory
Commission’s duty to consider the climate-change-related impacts of upstream and downstream
activities associated with a proposed pipeline.109 In Sierra Club v. FERC, the court reviewed

103 185 F.3d 1162 (10th Cir. 1999).
104 Id. at 1172-73.
105 40 C.F.R. § 1508.1(g)(3). CEQ’s 1978 definition of cumulative impact was substantively the same as the definition
currently in force, and adopted by the Biden Administration. The 1978 definition, which was applied by the courts in
the decisions discussed here, states as follows: cumulative impacts are “the impact on the environment which results
from the incremental impact of the [proposed] action when added to other past, present, and reasonably foreseeable
future actions.” 40 C.F.R. §§ 1508.7, 1508.9(b) (1978).
106 Ky. Riverkeeper, Inc. v. Rowlette, 714 F.3d 402, 408 (6th Cir. 2013).
107 Id.; see also Nat. Res. Defense Council, Inc. v. Hodel, 865 F.2d 288 (D.C. Cir. 1988) (holding Secretary of the
Interior failed to discuss any cumulative impacts in FEIS).
108 Ctr. for Envtl. Law and Pol’y v. U.S. Bur. of Reclamation, 655 F.3d 1000, 1008-09 (9th Cir. 2011).
109 When an agency approves a project, the “upstream” and “downstream” impacts of that project are those that will
result from the project and other activities that may increase as a result of the project. For example, in a case involving
approval for an offshore oil and drilling pipeline, the Ninth Circuit described these effects as follows:
“Upstream emissions are those that result directly from the project itself (e.g., construction and operation),
Congressional Research Service

15

Judicial Review and the National Environmental Policy Act of 1969

FERC’s decision to issue a certificate of public convenience and necessity for the proposed
Southeast Market Pipelines Project and the Sabal Trail pipeline. Environmental groups and
landowners challenged the decision, arguing among other things that the EIS prepared by FERC
“failed to adequately consider the project’s contribution to greenhouse-gas emissions.”110 The
court agreed:
[G]reenhouse-gas emissions are an indirect effect of authorizing this project, which FERC
could reasonably foresee, and which the agency has legal authority to mitigate. The EIS
accordingly needed to include a discussion of the “significance” of this indirect effect, as
well as “the incremental impact of the action when added to other past, present, and
reasonably foreseeable future actions.”
Quantification would permit the agency to compare the emissions from this project to
emissions from other projects, to total emissions from the state or the region, or to regional
or national emissions-control goals. Without such comparisons, it is difficult to see how
FERC could engage in “informed decision making” with respect to the greenhouse-gas
effects of this project, or how “informed public comment” could be possible.111
Two years later, the same court elaborated on agencies’ obligation to evaluate upstream and
downstream impacts on climate change in Birckhead v. FERC.112 In this case, a number of local
stakeholders challenged FERC’s decision to issue a certificate of public convenience and
necessity for the construction and operation of a natural gas compression facility in Tennessee.
The court dismissed that claim on procedural grounds, but nonetheless noted that agencies must
attempt to obtain information needed to fulfill their statutory obligations, which in that case
included consideration of indirect upstream and downstream environmental effects related to the
proposed facility.113
The same court considered FERC’s responsibility to evaluate climate change impacts during a
NEPA review in Vecinos para el Bienestar de la Comunidad Costera v. FERC. In that case, the
D.C. Circuit heard a challenge to FERC’s decision to issue certificates for the construction and
operation of three export LNG terminals and associated pipeline facilities in Texas. FERC
concluded in its EISs that it had been “unable to determine the significance of the Project’s
contribution to climate change” because “there is not universally accepted methodology to
attribute discrete, quantifiable, physical effects on the environment” of a particular project.114 The
petitioners claimed, among other things, that in that situation CEQ regulations require an agency
to “include within the environmental impact statement … [t]he agency’s evaluation of such
impacts based on theoretical approaches or research methods generally accepted in the scientific
community.”115 The court agreed, finding that FERC was required to use the social cost of carbon
or some other generally accepted methodology to assess the impact of the projects’ greenhouse
gas emissions.116

and downstream emissions are those that result from the consumption of the oil produced by the project (e.g., heating
homes or fueling cars).” Ctr. for Biological Diversity v. Bernhardt, 982 F.3d 723, 735 (9th Cir. 2020).
110 Sierra Club v. FERC, 867 F.3d 1357 (D.C. Cir. 2017).
111 Id. at 1363.
112 925 F.3d 510 (D.C. Cir. 2019).
113 Id. at 520.
114 Vecinos para el Bienestar de la Comunidad Costera v. FERC, 6 F.4th 1321, 1328 (D.C. Cir. 2021).
115 Id. at 1328.
116 Id. at 1329. See also Ctr. for Biological Diversity v. Bernhardt, 982 F.3d 723 (9th Cir. 2020). Cf. 350 Montana v.
Bernhardt, 443 F. Supp. 3d 1185, 1196 (D. Mont. 2020) (holding agency was not required to use the social cost of
Congressional Research Service

16

Judicial Review and the National Environmental Policy Act of 1969

Failure to Consider Alternatives
NEPA requires agencies to consider alternatives to their proposed actions as part of the
environmental review process. Courts and CEQ often refer to this requirement as the “heart” of
the environmental review.117 Agencies need not analyze every idea; rather, “the concept of
alternatives must be bounded by some notion of feasibility.”118 Thus, agencies must exercise
“common sense” when determining which proposals to include in an EIS, and courts will not find
an EIS insufficient “simply because the agency failed to include every alternative device and
thought conceivable by the mind of man.”119
Challenges to an agency’s consideration of alternatives to the proposed action arise in a variety of
ways. Some case law requires the courts to determine whether an agency impermissibly narrowed
the purpose of its project to predetermine what reasonable alternatives to the proposed action
existed. For example, in Simmons v. U.S. Army Corps of Engineers, the Seventh Circuit held that
the Corps unreasonably narrowed the range of feasible alternatives by defining the project’s
purpose as “supplying two users (Marion and the Water District) from a single source—namely, a
new lake.”120 The court found that the Corps failed to study and therefore to appropriately justify
whether addressing water shortage problems in Marion and the Water District was well-served by
a single-source project, and thereby improperly narrowed the parameters of the project and its
consideration of alternatives only to single-source options.121 By contrast, the Ninth Circuit in
Muckleshoot Indian Tribe v. U.S. Forest Service held that the agency did not improperly narrow
the scope of the project and thereby unreasonably limit the alternatives it considered. There,
plaintiffs alleged that the statement of purpose—to “consolidate ownership and enhance future
resource conservation and management by exchanging parcels of National Forest System and
Weyerhaeuser land”—impermissibly predetermined the contours of the project and dictated the
alternatives that the agency could consider.122 The Ninth Circuit agreed that the statement of
purpose read in isolation might impermissibly restrict the range of alternatives. However, the
court concluded that the narrow statement was part of the agency’s broader, more general
objective of “creat[ing] consolidated land ownership patterns where consistent management
mandates, policies and objectives apply across large blocks of land.”123
In other cases, plaintiffs have contended that an agency failed to assess adequately the alternatives
on their merits. For instance, plaintiffs sometimes argue that an agency improperly refused to
include or improperly eliminated from consideration a proposed alternative that would meet the
agency’s stated purpose. The Ninth Circuit rejected such an argument in Northern Alaska
Environmental Center v. Kempthorne
. In that case, the court held that the Bureau of Land
Management (BLM) reasonably refused to analyze an alternative proposed by the Audubon

carbon protocol when agency gave reasons that the protocol was too indeterminate to be helpful for decisionmaking).
117 See, e.g., 40 C.F.R. § 1502.14(f) (1988); CEQ, A Citizen’s Guide to the NEPA 16 (Dec. 2007) (“The identification
and evaluation of alternative ways of meeting the purpose and need of the proposed action is the heart of the NEPA
analysis.”); Wyoming v. U.S. Dep’t of Agric., 661 F.3d 1209, 1243 (10th Cir. 2011); City of Carmel-By-The-Sea v.
U.S. Dep’t of Transp., 123 F.3d 1142, 1155 (9th Cir. 1997); Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190,
194 (D.C. Cir. 1991).
118 Vt. Yankee Nuclear Power Corp. v. Nat. Res. Defense Council, Inc., 435 U.S. 519, 551 (1978).
119 Id.
120 120 F.3d 664, 666-67 (7th Cir. 1997).
121 Id. at 667.
122 177 F.3d 800, 811 (9th Cir. 1999).
123 Id. at 812-13.
Congressional Research Service

17

Judicial Review and the National Environmental Policy Act of 1969

Society in the EIS because (1) BLM determined that its inclusion “was inconsistent with the
[Nuclear Waste Power Act] project and statutory mandates,” and (2) BLM included aspects of the
Audubon Society’s proposal in the preferred alternative, suggesting the agency carefully
evaluated the proposal.124 By contrast, the Tenth Circuit held that the Department of
Transportation violated the APA by removing an alternative proposal from the EIS, ostensibly
because of its high costs, without providing a verified cost estimate to support its conclusion.125
Insufficient Consultation with the Public
In addition to encouraging informed agency decisionmaking, one of NEPA’s purposes is to
provide for public disclosure and participation. Plaintiffs sometimes allege that an agency failed
to consult with the public to the extent that NEPA requires for a particular decision.
In general, claims involving the consultation requirements for EISs allege that an agency denied
the public a meaningful opportunity to comment by (1) failing to give sufficient information
about the project; (2) failing to disclose certain aspects of a proposed action; or (3) failing to
provide timely disclosures. For example, in State of California v. Block, California challenged the
U.S. Forest Service’s EIS for classifying roadless national forest management land into three
management categories, arguing that the Service failed to provide adequate opportunity for public
comment because it did not disclose all contours of the proposed action until the final EIS.126 The
Ninth Circuit agreed, holding that the agency’s final proposed action was so different in
substance from the alternatives considered in the draft EIS that the public could not have
provided meaningful input on the proposed action before the final EIS.127 Similarly, in Idaho v.
Kempthorne
, the federal district court held that the Forest Service violated the APA when
preparing an EIS for a rule to preserve roadless forest system land because (1) the Service did not
present maps or other concrete data to the public during the public comment period and (2)
Service officials “were ill-prepared to answer the questions and concerns of the general public”
during hearings.128
In preparing an EA, an agency must involve the public to the extent practicable,129 and cases
involving EAs likewise raise questions about the sufficiency of an agency’s disclosure of
information. For example, in a challenge to the U.S. Army Corps of Engineers’ EA for proposed
surface mines that required the Corps to issue dredge and fill permits, a federal court held that the
Corps failed to disseminate significant and “substantive information concerning compensatory
mitigation” in public notices about the EA.130
Because preparation of an EA requires agencies to involve the public only to the extent
practicable, however, agencies retain greater discretion as to when and how to fulfill this
mandate. In Theodore Roosevelt Conservation Partnership v. Salazar, the D.C. Circuit considered
whether BLM satisfied its obligation to involve the public while preparing EAs for natural gas
drilling permits. The D.C. Circuit stressed that an agency “need not include the public in the
preparation of every EA”; rather, an agency may involve the public at different stages as

124 457 F.3d 969, 978 (9th Cir. 2006).
125 Utahns for Better Transp. v. U.S. Dep’t of Transp., 305 F.3d 1152, 1164-65 (10th Cir. 2002).
126 690 F.2d 753, 769-70 (9th Cir. 1982). This case involved CEQ guidelines about public consultation, which were
later incorporated into CEQ’s 1978 regulations.
127 Id. at 772.
128 142 F. Supp. 2d 1248, 1260-61 (D. Idaho 2001).
129 40 C.F.R. § 1501.5(e); id. § 1501.4(b) (1978).
130 Ohio Valley Envtl. Coal. v. U.S. Army Corps of Eng’rs, 674 F. Supp. 2d 783, 809-10 (S.D. W. Va. 2009).
Congressional Research Service

18

Judicial Review and the National Environmental Policy Act of 1969

appropriate.131 Applying this flexible standard, the court upheld BLM’s public involvement for
several reasons. First, BLM posted notices of its intent to prepare EAs for the permits, and even
though it did not expressly seek comments, plaintiffs had ample time to submit comments before
BLM issued final EAs, according to the court. Second, BLM provided copies of the draft EAs to
plaintiffs when they requested copies and responded to comments from plaintiffs in the final
EAs.132

Author Information

Nina M. Hart

Legislative Attorney



Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.


131 616 F.3d 497, 519 (D.C. Cir. 2010).
132 Id. at 519-20.