https://crsreports.congress.gov
Updated February 3, 2025
The Army’s current self-propelled artillery system, the M- 109 Paladin, first entered service in the 1960s and has been upgraded numerous times. The Army has two types of artillery: self-propelled, a howitzer mounted on a tracked or wheeled vehicle, or towed, a howitzer towed by a vehicle and then dismounted to fire. In 1994, the Army began to develop the Crusader, an advanced self-propelled 155- millimeter (mm) howitzer and an accompanying resupply vehicle. The Crusader was canceled in May 2002 when then-Secretary of Defense Donald Rumsfeld stated that future enemy threats did not require the Crusader and that the Department of Defense wanted instead to invest in other emergent technologies. The Army’s second attempt to develop a new self-propelled artillery system, the Non- Line-of-Sight Cannon (NLOS-C), was to be developed as part of the Army’s Future Combat System (FCS) program, which started in 1999 and was canceled in 2009 when then- Secretary of Defense Robert Gates restructured the program and canceled its associated vehicles. The third attempt for a new system was the Extended Range Cannon Artillery (ERCA) program (see Figure 1).
Figure 1. ERCA Prototype
Source: U.S. Army, “ERCA Autoloader is being tested for first time at YUMA Proving Ground,” August 15, 2019.
The ERCA program started in 2018 and reportedly was intended to
extend the range of artillery fire from 30 kilometers to 70 kilometers (43.5 miles). This would have given the Army a significant advantage on the battlefield. Unfortunately, the new design, which featured a 30-foot gun tube mounted on a Paladin M109 chassis, experienced problems during live- fire testing. These issues prevented the ERCA from reaching its projected range and forced the Army to abandon the project.
Reportedly, the major testing issue was excessive wear on the gun tube after firing a relatively low number of rounds. The Army discontinued the ERCA program in April 2024.
The SPH-M effort was previously known as the Next Generation Howitzer (NGH) Program. The SPH-M Effort replaces the ERCA program and is the fourth attempt to develop a new self-propelled howitzer. In the aftermath of the ERCA cancellation, the Army initiated a new conventional fires study in 2023 to determine the way ahead for artillery modernization. The study was completed in March 2024 and reportedly determined “the service should focus on more autonomous artillery systems with greater range and improved mobility.”
According to Army FY2025 budget documents,
The Next-Generation Howitzer (NGH) will provide highly mobile, survivable, versatile, transportable, longer range fire support under a broad set of challenging operational conditions against current and emerging, small to large scale threats through 2040 and beyond. NGH reduces emplacement and displacement times, provides increased crew survivability and better cross-country mobility, adds overall effectiveness, and affords improved fire support capability for field artillery formations well beyond what towed howitzer systems can provide.
The Army reportedly conducted a number of successful tests with the ERCA before cancelling the program; those past testing activities are to inform the SPH-M program. For example, in 2022, ERCA hit a target at 70 kilometers (43 miles) with an M-982 Excalibur extended-range guided artillery shell.
On August 28, 2024, the Army issued a request for information (RFI) to industry to
identify and preliminarily review the maturity of potentially offered self-propelled howitzer systems. The U.S. Government (USG) is interested in systems that have high maturity and minimize or eliminate development time. Additionally, the USG is interested in understanding the possible future modernization options for those systems. Any information received in response to this survey will be used by the USG to assess the viability of potential future acquisition strategies. When responding, the USG encourages industry to present
The Army’s Self-Propelled Howitzer Modernization (SPH-M) Program
https://crsreports.congress.gov
both mature systems that are in service as well as systems that could be in service by 2026, absent any USG investment.
Army Awards SPH-M Demonstration Contracts On October 14, 2024 the Army announced,
The awarding of five contracts for the Army’s upcoming Self-Propelled Howitzer Performance Demonstration. The contracts were awarded to: American Rheinmetall Vehicles, BAE BOFORS, Hanwha Defense USA, General Dynamics Land Systems, and Elbit Systems USA. The contracts were awarded under Other Transaction Agreements (OTA) and the total award value for all contracts is approximately $4 million … The Army intends to complete all vendor performance demonstrations by the end of 2024 with the goal of determining if operationally suitable solutions exist to progress into a follow-on competitive evaluation that may lead to a future production contract.
Completion of SPH-M Demonstration Reportedly, the Army is plans to conclude its performance demonstrations “to assess five vendors’ mobile tactical cannon solutions by mid-December 2024,” with follow on efforts continuing in 2025. Army officials have reportedly noted that there is a “sense of urgency” involved with the overall SPH-M effort, suggesting that “potential adversaries now can outgun the Army when it comes to range. The goal is to extend current cannon ranges from around 30 kilometers to 50 to 70 kilometers by 2030.”
Army to Launch SPH-M Competition Reportedly, the Army has decided to launch a full and open competition with a planned “release of a Phase I request for proposal in mid-February [2025].” This decision suggests that the Army will not pursue an original design and choose from existing systems. Army program officials outlining program plans further elaborated that
• Phase I is intended to be “the ‘get to test’ phase which
includes further testing of mature platforms, and it will not be a vendor downselect.”
• The Army then plans to select an unspecified number of
companies to proceed and award Phase I contracts around the July to September (2025) timeframe. Those vendors are to participate in additional competitive evaluation testing running through FY2026.
• Army leaders plan to “evaluate competing systems on
range, precision, and volume, as well as the platform characteristics like mobility and supportability.”
• Test data from Phase I is to be used to inform evaluation
in Phase II. “If all goes as planned, that second round of downselects will occur in early fiscal year 2027 ahead of initial fielding in the 2030 timeframe—but possibly with multiple self-propelled howitzer lines of effort, as the Army reexamines its force structure.”
Some Members of Congress are concerned about the Army’s fourth attempt to develop a new self-propelled howitzer. S.Rept. 118-188 to accompany S. 4638, the National Defense Authorization Act for Fiscal Year 2025, notes, on page 29,
Though the Army cancelled its Extended Range Cannon Artillery (ERCA) program, a recently conducted tactical fires study validated the capability gap that the ERCA sought to fill. Observations from Ukraine reinforce the critical role of mobile cannon artillery. The extensive employment of unmanned aerial systems and near ubiquitous sensing only increase the risks to the Armored Brigade Combat Team (ABCT) and the Stryker Brigade Combat Team (SBCT) on the modern battlefield. The committee is interested in how the Army is seeking to rapidly identify and field improved cannon artillery to these formations. The committee supports Army efforts to achieve requirements by identifying currently available capabilities or rapidly improving our own systems. Accordingly, the committee directs the Secretary of the Army to provide a briefing to the Committees on Armed Services of the Senate and the House of Representatives, not later than March 31, 2025, on its long-range cannon modernization effort. The briefing should include
(1) An assessment of how current ABCTs and SBCTs long-range cannon fires capabilities would perform in a scenario such as Ukraine;
(2) A description of what new vehicles or programs are being considered to fill the stated requirement; and
(3) A comparison of cost to modernize through employment of, or modification to, existing platforms versus the cost to a new start program. A new start program estimate should consider total costs, including developmental, acquisition,
sustainment, and operational costs.
Congress may consider the following issue:
Estimated Total Program Cost When the Army downselects candidate systems, it should be possible to establish a preliminary estimated total program cost. The Army could also identify any related artillery munitions developmental efforts and develop a preliminary cost estimate. The early establishment of a preliminary estimated total program cost for SPH-M and associated ammunition could greatly facilitate congressional oversight and consideration of whether the estimated cost is appropriate for the capabilities being acquired.
Andrew Feickert, Specialist in Military Ground Forces
IF12772
The Army’s Self-Propelled Howitzer Modernization (SPH-M) Program
https://crsreports.congress.gov | IF12772 · VERSION 10 · UPDATED
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you wish to copy or otherwise use copyrighted material.