link to page 1  link to page 1 
 
 
  
August 3, 2018
The James Webb Space Telescope
Introduction 
Academy of Sciences 2001 decadal survey of astronomy 
The National Aeronautics and Space Administration 
and astrophysics. 
(NASA) reported in March 2018 that it expects to breach 
the $8 billion cost cap established by Congress for 
Among the new technologies developed for JWST is a 
formulation and development of the James Webb Space 
multilayer sunshield (the large flat structure i
n Figure 1) 
Telescope (JWST). If that occurs, NASA would have to 
that is designed to fold up for launch and unfold in orbit to 
stop work on the project unless Congress enacts legislation 
approximately the size of a tennis court. The sunshield is 
authorizing it to continue. In addition, an independent 
needed to protect the telescope optics and instruments from 
review of JWST in May 2018 identified a number of 
the heat of the sun, which would otherwise prevent 
technical and management challenges. 
effective infrared observations. 
This CRS In Focus provides information on JWST, the cost 
NASA plans to launch JWST in March 2021 on an Ariane 5 
cap, and the independent review. It concludes with a brief 
rocket, provided by the European Space Agency as an in-
discussion of issues that Congress may face as it considers 
kind contribution to the project. The launch date has slipped 
the future of JWST. 
several times. As recently as September 2017, the launch 
was expected to occur in October 2018. 
Figure 1. The James Webb Space Telescope. 
The Cost Cap 
When the National Academy of Sciences endorsed the 
project in 2001, it estimated that the total cost would be $1 
billion. After several years of project formulation work, 
NASA designated JWST as a development project in 2006. 
In FY2009, it formally committed to a baseline JWST 
budget and schedule with an estimated life-cycle cost of 
$4.964 billion (including $4.381 billion for formulation and 
development and $582 million for operations) and a launch 
date in June 2014. 
In October 2010, an independent review (known as the 
Casani report after its chair, John Casani of the Jet 
Propulsion Laboratory) concluded that these estimates were 
unachievable. In July 2011, the House Committee on 
Appropriations recommended cancelling JWST. NASA 
  developed a revised plan for the project, with a life-cycle 
Source: NASA. 
cost of $8.835 billion and a launch date in FY2018. In 
Note: Artist’s impression. Not yet launched. 
November 2011, in the conference agreement on FY2012 
appropriations, Congress approved continued funding, 
What Is JWST? 
subject to a cap of $8 billion on the cost of JWST 
NASA and its prime contractor, Northrop Grumman, are 
formulation and development.  
developing JWST as a successor to the Hubble Space 
Telescope, which has been operating since 1990. The main 
The cost cap appeared in the Consolidated and Further 
scientific goals of JWST are to study the formation of 
Continuing Appropriations Act, 2012 (P.L. 112-55) and has 
galaxies, stars, and planets. Unlike Hubble, which orbits the 
been repeated in annual appropriations acts ever since. The 
Earth at an altitude of 353 miles, JWST is designed to 
statutory language ties the $8 billion cap to existing cost 
operate in deep space, about 1 million miles from Earth. Its 
control requirements and procedures in 51 U.S.C. §30104. 
primary mirror (the gold structure i
n Figure 1) is larger 
If the responsible NASA official determines that JWST’s 
than Hubble’s, and its instruments are optimized for 
development cost is likely to exceed the cap, he or she must 
infrared rather than visible light. This is expected to allow it 
immediately notify the NASA Administrator; the 
to observe galaxies and other objects that are farther away 
Administrator must notify Congress within 15 days; and 
and further back in time, as well as relatively cool objects 
starting 18 months after Congress is notified, NASA must 
such as protostars and protoplanetary disks. The likelihood 
cease spending funds on the program, other than for 
of important scientific discoveries made JWST the highest-
termination costs, unless Congress enacts legislation that 
priority large project recommended by the National 
authorizes the program to continue. 
https://crsreports.congress.gov 
The James Webb Space Telescope 
The FY2012 appropriations conference report (H.Rept. 
In June 2018, NASA responded to the IRB, indicating that 
112-284) also mandated ongoing oversight of the JWST 
it agreed with most of the IRB’s recommendations and 
project by the Government Accountability Office (GAO), 
“agreed with the intent” of the remainder. NASA has 
including annual reports on “key issues relating to program 
established March 2021 as the new launch date and now 
and risk management; achievement of cost and schedule 
estimates a life-cycle cost of $9.663 billion, including 
goals; and program technical status.” As recently as 
$8.803 billion ($803 million more than the cap) for 
December 2016, GAO found that “JWST is meeting its cost 
formulation and development. 
commitments despite technical and workforce challenges.” 
In December 2017, however, GAO testified that “funding 
Issues for Congress 
available under the $8 billion congressional cost cap … 
As Congress considers the future of the JWST project, it 
may be inadequate,” and in February 2018 it reported that 
may face the following issues. 
“JWST is still resolving technical challenges and work 
continues to take longer than planned to complete. As a 
Authorize or Terminate? 
result, the project is at risk of exceeding its $8 billion 
If Congress decides that NASA should complete the 
formulation and development cost cap.” 
development, launch, and operation of JWST, it would need 
to enact legislation authorizing the continuation of the 
On March 26, 2018, NASA notified Congress that JWST is 
project despite the breach of the cost cap. To avoid 
likely to breach the cost cap. 
suspension of the project, this legislation would need to be 
enacted within 18 months of March 26, 2018, when NASA 
The Independent Review Board 
officially notified Congress about the likelihood of the cap 
In early April 2018, the agency convened an Independent 
being breached. Alternatively, if Congress decides to 
Review Board (IRB) to review the JWST project and 
terminate the project, it may wish to make that decision 
evaluate factors influencing the likelihood of JWST’s 
before the 18 months expire, to minimize the further 
mission success. The IRB was chaired by Tom Young, a 
expenditure of funds on the project (although most of the $8 
leading aerospace executive, former president and chief 
billion capped amount has already been spent). 
operating officer of Martin Marietta, and former director of 
NASA’s Goddard Space Flight Center. 
Recover Costs? 
At a House hearing on July 25-26, 2018, Members and 
The IRB issued its report at the end of May 2018. It noted a 
witnesses discussed the possibility of recovering some of 
number of JWST’s accomplishments, including the delivery 
JWST’s cost increases from the project’s prime contractor, 
of all flight hardware and the successful integration and 
Northrop Grumman. The JWST contract is a cost-plus 
testing of the optical telescope and science instrument 
contract, in which Northrop Grumman is reimbursed for the 
module. It cited the development of the sunshield as a 
costs it incurs and receives award fees (its profit) based on 
noteworthy “first” with no significant technological 
performance. NASA Administrator Jim Bridenstine 
precedent. On the other hand, it identified serious risks in 
testified that the JWST award fees have already been 
two phases of the project that are yet to be completed: the 
reduced based on the contractor’s performance to date. 
remainder of the integration and test phase before launch 
Some Members suggested going further, such as asking 
and the commissioning phase after launch, in which the 
Northrop Grumman to pay all costs in excess of the cap. 
spacecraft and sunshield are to be deployed. 
Oversight of IRB Recommendations 
The IRB recommended a launch date in March 2021 and 
If Congress decides to allow NASA to complete JWST, it 
identified five factors that have led to the delays since the 
would likely wish to assess the ongoing implementation of 
2011 re-plan: 
the IRB’s recommendations by NASA and its contractors. 
In addition to hearings and other direct congressional 
  human errors, such as using an incorrect voltage during 
oversight, this process could include continuing the regular 
an electrical wiring test; 
monitoring of the project by GAO. 
  embedded problems, i.e., problems with completed 
Effect on Other NASA Programs 
hardware that are not discovered until much later (for 
If JWST is continued, the additional cost may result in less 
example, improperly installed fasteners inside the 
funding being available for other NASA activities, 
sunshield that came loose several months later during a 
especially in FY2020 and FY2021. Which activities would 
vibration test); 
be affected would ultimately depend on Congress’s 
decisions in appropriations legislation, but the NASA 
  lack of experience with unique technologies such as the 
Administrator and others have suggested that slowing down 
sunshield; 
work on the Wide-Field Infrared Survey Telescope 
(WFIRST), another large space telescope, would be a likely 
  excessive optimism; and 
option. WFIRST was the highest-priority large project of 
the 2010 decadal survey. Its status was already a matter of 
  systems complexity. 
debate before it was linked to the continuation of JWST. 
The Administration’s FY2019 budget proposed terminating 
The IRB made 32 recommendations to address the 
WFIRST “due to its significant cost and higher priorities 
challenges it identified. Despite those challenges, it 
within NASA,” but the House and Senate appropriations 
advocated continuing the project to completion. 
bills for FY2019 would both continue funding it.
https://crsreports.congress.gov 
The James Webb Space Telescope 
 
Daniel Morgan, Specialist in Science and Technology 
Policy   
IF10940
 
 
Disclaimer This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to 
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. 
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has 
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the 
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be 
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include 
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you 
wish to copy or otherwise use copyrighted material. 
 
https://crsreports.congress.gov | IF10940 · VERSION 2 · NEW