Order Code IB10122
CRS Issue Brief for Congress
Received through the CRS Web
Hydropower Licenses and Relicensing Conditions:
Current Issues and Legislative Activity
Updated November 4, 2004
Kyna Powers
Resources, Science, and Industry Division
Congressional Research Service ˜
The Library of Congress
CONTENTS
SUMMARY
MOST RECENT DEVELOPMENTS
BACKGROUND AND ANALYSIS
Licensing Authority
Federal Power Act §4(e) and §18 License Conditions
License Conditions for Projects on Federal Reservations (FPA §4(e))
Fishway Provisions (FPA §18)
License Conditioning Agencies and the Relicensing Process
Pre-Application Phase
Post-Application Phase
Cost of Mandatory Conditions
Proposed Changes to the License-Conditioning Process
Hydroelectric Relicensing Legislation in the 108th Congress
Discussion
Length of Process
Environmental Issues
Effectiveness of the Integrated Licensing Process (ILP)
Participation in the Conditioning Process
Conclusion
LEGISLATION
CONGRESSIONAL HEARINGS, REPORTS, AND DOCUMENTS
Hearings
FOR ADDITIONAL READING
CRS Reports
Other Documents
IB10122
11-04-04
Hydropower Licenses and Relicensing Conditions:
Current Issues and Legislative Activity
SUMMARY
In the next ten years, more than 40% of
authority. On November 17, 2003, a confer-
the nation’s non-federal hydropower projects
ence agreement was reached on H.R. 6. It
will require new federal licenses to continue
passed the House the next day, but has not
operating. New licenses will establish facili-
passed the Senate. Other energy bills have
ties’ operating parameters for the next 30 to
been introduced. One version, H.R. 4503, was
50 years. These operating parameters will
introduced in the House on June 3, 2004, and
affect the total quantity and timing of electric-
passed the House on June 15, 2004. H.R.
ity production. They will also affect flood
4503/H.R. 6 would allow stakeholders to pro-
control, irrigation, municipal water supplies,
pose alternative license conditions and would
recreation, fish and wildlife habitat, and trans-
require federal agencies to consider alterna-
portation.
tives proposed by license applicants, but not
any other stakeholder. The legislation would
Under the 1920 Federal Power Act
also require an agency to accept the appli-
(FPA), the Federal Energy Regulatory Com-
cant’s proposed alternative if it found that the
mission (FERC) has primary responsibility for
alternative (1) provides for the adequate pro-
balancing multiple water uses and evaluating
tection and utilization of the federal reserva-
licensing and relicensing applications. How-
tion, or will be no less protective of the fish
ever, the FPA also creates a role in the licens-
resource than the fishway initially prescribed,
ing process for federal agencies that are re-
and (2) costs less to implement, and/or will
sponsible for managing fisheries or federal
result in improved operation of the project for
reservations (e.g., national forests, etc.).
electricity production.
Specifically, sections 4(e) and 18 of the FPA
give certain federal agencies the authority to
Response to the proposed legislation has
attach conditions to FERC licenses. For
been mixed. While FERC and the hydro-
example, federal agencies may require appli-
power industry generally support the legisla-
cants to: build fish passageways, schedule
tion, some environmental organizations op-
periodic water releases for recreation, release
pose the bills, and officials within some con-
minimum flows of water for fish migration, or
ditioning agencies have expressed concerns.
control water release rates to reduce erosion.
Opponents of the legislation argue that re-
Once an agency issues such conditions, FERC
source agencies are taking adequate steps to
must include them in any license it issues.
improve the conditioning process, and that the
While these conditions often generate envi-
legislation could increase relicensing time,
ronmental or recreational benefits, they may
weaken environmental protections, give appli-
also require construction expenditures and
cants undue standing in the conditioning
may increase generation costs by reducing
process, and weaken FERC’s new Integrated
operational flexibility.
Licensing Process. On the other hand, propo-
nents of the legislation argue that it would
Reflecting recommendations by FERC
create accountability on the part of condition-
and the hydropower industry, legislation has
ing agencies, decrease the cost of license
been passed by both chambers of the 108th
conditions without diminishing agencies’
Congress, as part of various energy bills, to
conditioning authority, and enhance FERC’s
alter federal agencies’ license-conditioning
licensing processes.
Congressional Research Service ˜
The Library of Congress
IB10122
11-04-04
MOST RECENT DEVELOPMENTS
Conferees on the House and Senate comprehensive energy bills (H.R. 6) met on
November 17, 2003, and approved a conference report that contained provisions on
hydroelectric facilities. The Senate conferees voted 10-3 to approve an offer to the House
conferees. The House conferees approved a counteroffer by voice vote, and the House
conferees’ counteroffer was accepted by eight of the Senate conferees. The House approved
the conference report November 18, 2003. At the end of 2003, the Senate had not approved
the conference report. S. 2095, a shorter version of H.R. 6, was introduced in the Senate on
February 12, 2004, but a vote on this bill has not been held. Another version, H.R. 4503, was
introduced in the House on June 3, 2004. H.R. 4503 passed the House on June 15, 2004, and
has been received in the Senate. On September 9, 2004, the Department of Interior released
a proposed rule that would allow hydropower license applicants to appeal its license
conditions.
BACKGROUND AND ANALYSIS
Hydropower is one of the multiple benefits the nation’s waters provide. It accounts for
nearly 7% of all electricity produced in the United States and 15% or more of the electricity
produced in Idaho (27%), Maine (15%), Montana (34%), Oregon (43%), South Dakota
(30%), Vermont (37%), and Washington (44%).1 Hydroelectric power is generated by
releasing water through a set of turbines; thus, it does not produce air pollutants and maybe
turned on or off in a matter of minutes. By storing water behind dams and controlling water
releases, some hydropower facilities can generate electricity during periods of high energy
demand (so called peaking power).
While these facilities are important sources of clean peaking power, the construction
and management of dams are contentious because dams affect other beneficial water uses
and resources. The construction of dams alters the river by blocking downstream flows and
creating reservoirs. While reservoirs can provide recreational opportunities and habitat for
certain fish species, they increase the effort migratory fish must exert to travel up or down
river and increase the exposure of young fish to predators. Once a hydropower facility is
built, its management also affects water uses. For example, the decision of when, how, and
how much water to release from a hydroelectric facility affects flood control, irrigation,
municipal water supplies, recreation, fish and wildlife habitats, and transportation (See CRS
Report RL31536,
Licensing of Non-Federal Hydroelectric Projects: Background and
Current Issues).
In order to make sure that navigable waters are managed for the public interest,
Congress oversees the construction and operation of hydroelectric facilities. Congress
directly authorizes federal hydropower projects and requires that private hydropower projects
1 Department of Energy Report DOE/EIA-0214,
State Energy Data Report 1999, Table 3, “Energy
Consumption Estimates by Source,” at [http://www.eia.doe.gov/emeu/sedr/contents.html].
CRS-1
IB10122
11-04-04
obtain federal licenses.2 This issue brief summarizes federal licensing and license-
conditioning authority for non-federal projects, discusses key arguments for and against
changing the process through which federal resource agencies issue license conditions, and
reviews current legislative proposals to revise federal licensing authority.
Licensing Authority
Through the 1920
Federal Power Act (FPA) (16 U.S.C. 792), Congress created the
Federal Power Commission (FPC), later renamed the Federal Energy Regulatory
Commission (FERC), which licenses all non-federal hydropower facilities. Using this
authority, FERC granted 30 to 50 year licenses to projects located in 45 states (excluding
Delaware, Hawaii, Mississippi, North Dakota, and South Dakota which have no non-federal
dams). Many of the licenses for these projects were issued during the 1950s and 1960s, and
are now expiring. In the next 10 years, 218 projects, or about 40% of all non-federal
hydropower facilities, will need new licenses to continue operating.3
In order to help ensure that FERC licenses protect migratory fish and federally reserved
lands (e.g., lands, such as Indian reservations and national forests, that are set apart by the
federal government for a special purpose), Congress created a role in the licensing process
for certain federal agencies. The FPA requires that FERC include certain agency-established
operating conditions in its licenses. For example, section 18 of the FPA (16 U.S.C. 811)
stipulates that the Secretary of the Interior or the Secretary of Commerce may develop license
conditions that direct the applicant to construct and maintain a passageway, called a fishway,
through which fish can travel around barriers created by the dam. Furthermore, section 4(e),
authorizes certain department secretaries to develop license conditions for facilities located
in the federal reservations they manage (16 U.S.C. 797(e)). Under section 4(e), a secretary
may stipulate provisions that are necessary to maintain the reservation for its federally
designated purposes. Conditioning authority is not limited to FERC and Federal agencies.
The 1970 Federal Water Pollution Control Act, commonly known as the Clean Water Act
(CWA) (33 U.S.C. 1341) extends conditioning authority to state pollution-control agencies.
Under the CWA, a FERC-issued license must include any conditions that the state deems
necessary to maintain state-designated uses or water quality standards.
Federal Power Act §4(e) and §18 License Conditions
As noted above, sections 4(e) and 18 of the FPA grant federal agencies the authority to
issue license conditions designed to preserve or enhance federally reserved lands, and to help
fish travel around barriers created by hydropower facilities. The type of conditions issued
pursuant to FPA sections 4(e) and 18 are described below.
License Conditions for Projects on Federal Reservations (FPA §4(e)).
Section 4(e) of the FPA applies to hydropower facilities located on federally reserved lands
(e.g., Indian reservations and national forests, etc.). Under this section, the Secretary of the
2 Managers of federal dams may implement operational changes similar to those contained in
hydropower licenses.
3 Federal Energy Regulatory Commission,
Hydroelectric Projects Under Commission License,
updated March 11, 2003, at [http://www.ferc.gov/industries/hydropower/gen-info/projlic.pdf].
CRS-2
IB10122
11-04-04
department with jurisdiction over the reserved land has the authority to issue any license
conditions necessary to maintain the reservation. Depending on the purpose of the
reservation, the agency’s conditions may address a range of goals including the preservation
or enhancement of recreation, federal lands, and aquatic habitat. Specifically, the Secretary
could require the applicant to: schedule periodic water releases for recreation (white-water
releases), release minimum quantities of water for fish migration (minimum flows), control
the rate of water release to reduce habitat disruption (ramping requirements), and limit
reservoir fluctuations to reduce erosion and maintain habitat (reservoir fluctuation limits).
The Department of the Interior reports that the Bureau of Indian Affairs, Bureau of
Reclamation, National Park Service, and Bureau of Land Management issued section 4(e)
conditions for 6% of the projects relicensed between 1995 and 2000.
Fishway Provisions (FPA §18). Under section 18 of the FPA, the Secretary of the
Interior and the Secretary of Commerce may require applicants to construct and operate a
physical structure, facility, or levee, called a fishway,4 that allows fish to pass around barriers
created by the hydropower project. Fishways provide young migratory fish with somewhat
safer passage around the dam on their way downstream. Without a fishway, migratory fish
have no alternative to the more dangerous passage over the dam via spill or through the
project’s turbines. Adult fish may also use fishways, such as fish ladders, to get past the dam
on their way upstream to spawn. Without fishways, a hydropower project may block
upstream migration. In order to preserve and enhance fish resources, the Fish and Wildlife
Service (USFWS) issued section 18 conditions for 20% of the projects relicensed between
1995 and 2000. The Department of Commerce, through the National Marine Fisheries
Service (NMFS) issued section 18 conditions for 7.6% of the projects licensed between 1995
and 2000. In some cases, the NMFS and the USFWS issued conditions for the same
projects.5
License Conditioning Agencies and the Relicensing Process
Federal resource agencies establish FPA section 4(e) and 18 license conditions by
working through and alongside FERC’s licensing processes. FERC’s regulations allow three
licensing processes: a structured process known as the Traditional Licensing Process (TLP),
a collaborative process known as the Alternative Licensing Process (ALP), and a new
licensing process, called the Integrated Licensing Process (ILP), that is both structured and
collaborative. Each of these processes has two phases: a pre-application phase led by the
applicant and a post-application analysis phase led by FERC.6 As described below,
conditioning agencies participate in both licensing phases.
4 Environmental Protection Agency,
Notice of Proposed Interagency Policy on the Prescription of
Fishways under Section 18 of the Federal Power Act, 65
Fed.Reg. 80898 (December 22, 2000). See
also 16 U.S.C. §811.
5 Letter by William D. Bettenberg (Interior) to David P. Boergers (FERC),
Hydroelectric Licensing
Policies, Procedures, and Regulations: Comprehensive Review, entered into FERC Docket No.
PL01-1-000 on April 16, 2001.
6 The Notice of Proposed Rulemaking is available under RM02-16-000 at [http://www.ferc.gov/
industries/hydropower/indus-act/hydro-rulemaking-nopr.pdf] on August 27, 2003. (Hereafter
referred to as FERC’s NOPR.)
CRS-3
IB10122
11-04-04
Pre-Application Phase. In order for FERC and other agencies to evaluate a project
and develop license conditions, they need information on how the project affects various
resources. FERC and conditioning agencies generally obtain this information from the
applicant who conducts studies before submitting its license application.7 Specifically,
FERC’s licensing process requires an applicant to consult with stakeholders, including
conditioning agencies, before the applicant decides which studies to undertake.
The pre-application process can be delayed when the applicant disagrees with the
conditioning agencies regarding the need for, or content of, particular studies. Agencies,
unlike FERC, do not have the authority to require applicants to conduct studies. However,
agencies’ authority to issue license conditions does provide applicants with an incentive to
resolve study disagreements. Applicants and conditioning agencies may utilize voluntary
mechanisms for resolving these study disputes. Under the ALP, for example, conditioning
agencies and applicants may use FERC’s Dispute Resolution Service (DRS). The DRS is
a FERC service that mediates license disputes. The DRS does not provide recommendations,
but it may bring in FERC experts to help clarify issues. When agencies and the applicant do
not resolve their disagreements using the DRS, the agency’s study request may be deferred
until FERC evaluates the application.
Under the ILP, applicants and stakeholders first try to resolve disputes through
voluntary discussions. If this voluntary process fails, then the conditioning agencies, under
the ILP, have the opportunity to initiate a “formal study dispute resolution process.” Under
the ILP, FERC becomes involved during the pre-application phase and has the final say
regarding the applicant’s study development plan. (For more information on this process see
CRS Report RL31903.
Relicensing of Non-Federal Hydroelectric Projects: Summary and
Discussion of Procedural Reform Proposals)
Post-Application Phase. Once the applicant completes its studies and submits its
license application, FERC evaluates the study results and develops its license. FERC’s role
is to develop a license that balances hydropower, recreation, ecological, cultural, and other
benefits influenced by the project. This license may include conditions proposed by various
resource agencies. At present, agencies develop license conditions that may or may not
incorporate suggestions from other stakeholders. After the agency submits its conditions,
FERC must include them in its license unless FERC finds that the conditions are unrelated
to the agencies’ FPA jurisdiction. If the conditions are outside the agencies’ jurisdiction,
FERC may refuse to include them in its license. A key issue prompting legislative proposals
is that under the current processes, applicants and other stakeholders have little opportunity
to contest agencies’ conditions. In September of 2004, the Department of the Interior
released a proposed rule that would establish an administrative appeals process for license
applicants, but no other stakeholders.8
Another issue is that delay in the license-conditioning process may occur when the
agency has insufficient information to evaluate the project. Specifically, some officials
7 In some cases, FERC requests additional studies after the applicant has submitted the license
application.
8 General Printing Office, “Procedures for Review of Mandatory Conditions and Prescriptions in
FERC Hydropower Licenses.” 69
Fed. Reg. 174 (Washington, DC; Sept. 9, 2004).
CRS-4
IB10122
11-04-04
within conditioning agencies have voiced concern that applicants do not always provide
sufficient information in their license applications for agencies to develop conditions.
Insufficient information is often the result of unresolved study disputes. If a study is not
conducted during the pre-application phase, a conditioning agency may ask FERC to require
that the applicant conduct the study. The agency may also conduct the study itself, or may
issue license conditions in the absence of full information. However, conducting studies
often requires significant financial resources and the imposition of conditions without the
underlying studies may lead to litigation. Therefore, a major goal of the proposed ILP is to
resolve study disputes early in the pre-application phase.
Cost of Mandatory Conditions
Through the relicensing process, FERC and federal agencies often establish license
conditions designed to preserve and enhance the resources affected by hydropower projects.
While these conditions often generate environmental, recreational, or other benefits, they
may also require that the applicant incur costs. FERC calculated the median cost of a
license’s protection, mitigation, and enhancement measures, including state agency
conditions, as $246 per kilowatt (kW) of capacity under the TLP and as $58 per kW under
the ALP. However, these figures have been criticized by the General Accounting Office
because they are based on a sample of projects that submitted their costs to FERC and not
on a representative sample.9
License conditions may result in two types of costs: fixed capital costs such as
construction of installations, and variable costs that arise from changes in management
techniques. For example, license conditions may require applicants to purchase or construct
installations including fishways, boat ramps, and fish screens. Changing facility operations
may also decrease total hydropower production. For example, minimum flow requirements,
white water releases, or fishway releases may reduce the facility’s total generation when the
water is not released through turbines. According to FERC, conditions placed in the license
for environmental protection reduce average annual hydropower generation by 1.59%. While
these conditions may decrease total electricity generation, they may also reduce the facility
operator’s leeway to store water behind the dam for release during periods of peak demand.10
If hydropower is removed from the supply of peaking power, additional generation by other
higher cost producers may be required. At the same time, FERC estimates that efficiency
improvements made during relicensing increase capacity by an average of 4.06%.
While hydropower license conditions often generate costs, other stakeholders would
face costs if such conditions were not applied. For example, fishway requirements and
minimum flow requirements reduce the dam’s harm to migratory fish populations. Without
such requirements, Native Americans, the commercial fishing industry, and individuals who
fish for recreation would continue to pay the costs of decreased fish populations. Likewise,
constraints on reservoir height fluctuations and water release rates may reduce stream-bank
and reservoir-bank erosion. Without such conditions, taxpayers, as owners of national
9 General Accounting Office Report, GAO-01-499,
Licensing Hydropower Projects: Better Time and
Cost Data Needed to Reach Informed Decisions about Process Reforms, May 2, 2001.
10 Not all dams have storage capacity. Some facilities, known as run of river projects, have little
storage, thus they depend on daily water inflows to generate hydropower.
CRS-5
IB10122
11-04-04
forests, and other owners of shoreline or river-front property may continue to pay the costs
of such erosion. Depending on the project’s characteristics, license conditions may benefit
a wide array of stakeholders that use the water for irrigation, transportation, fishing, and
boating.
Proposed Changes to the License-Conditioning Process
A number of issues emerged as the first wave of hydropower projects were relicensed
throughout the 1990s. These issues have prompted Congress to hold hearings and take other
actions to examine the licensing process. The 106th Congress directed FERC to conduct a
comprehensive review of the policies, procedures, and regulations guiding the licensing
process and report to Congress (section 603 of the Energy Act of 2000, P.L.106-469). FERC
responded in May 2001, with recommendations on how to reduce the length and expense of
obtaining a new license.11 In addition to administrative proposals, which are the subject of
CRS Report RL31903, the Section 603 Report proposed legislative changes to the relicensing
process. One class of proposals focuses on agencies’ mandatory conditioning authority. For
example, FERC suggested that Congress grant it the authority to reject or modify resource
agencies’ conditions and that Congress require agencies to better support their license
conditions. While the hydropower industry tends to support these FERC recommendations,
environmental organizations, and officials within federal and state agencies oppose these
suggestions and any other proposed reduction in current license-conditioning authority.
Opponents of FERC’s legislative proposal argue that administrative reforms, such as FERC’s
proposed rule establishing the ILP and the development of agencies’ administrative review
processes, are adequate to improve the relicensing process.
Legislative proposals incorporating some of these suggestions have been introduced in
Congress in recent years, but none has been enacted. For example, hydroelectric titles passed
both chambers during the 107th Congress. (H.R. 4, the Securing America’s Future Energy
Act, passed the House August 2, 2001 and the Energy Policy Act, also H.R. 4, passed the
Senate April 25, 2002.) Title III of each of these bills would have allowed license applicants
to propose alternatives to agencies’ mandatory conditions under the Federal Power Act.
While a compromise was not achieved at the end of the 107th Congress, this legislation is the
basis of all relicensing legislation proposed in the 108th Congress.
Hydroelectric Relicensing Legislation
in the 108th Congress
Title III of H.R. 4 (107th Congress) was incorporated into the Senate-passed energy bill,
H.R. 6 (Senate H.R. 6), in the nature of a substitute. Title III of H.R. 6 also passed the House
11 Federal Energy Regulatory Commission,
Report to Congress on Hydroelectric Licensing Policies,
Procedures, and Regulations — Comprehensive Review and Recommendations Pursuant to Section
603 of the Energy Act of 2000, Section 603 Report (Washington, DC: May 2001). Available at
[http://www.ferc.gov/legal/ferc-regs/land-docs/ortc_final.pdf] on August 27, 2003.
CRS-6
IB10122
11-04-04
(House H.R. 6), though with substantive differences.12 The conference agreement on H.R.
6, which passed the House on November 18, 2003, contains similar language to the House-
passed bill. Similar language was introduced in S. 2095 on February 12, 2004, and in H.R.
4503 on June 3, 2004.
Each of these bills13 has a title that focuses on federal agencies’ license conditioning
authority under section 4(e) or 18 of the FPA. H.R. 6/S. 2095/H.R. 4503 would provide
license applicants, but not other interest groups, with the opportunity for a trial-type hearing
on facts related to agency-proposed license conditions. Furthermore, each bill would change
the license-conditioning process by allowing stakeholders, including applicants, to propose
alternative conditions. When the license applicant proposes an alternative, the conditioning
agency would be required to consider it, and to adopt the alternative if it meets certain
environmental and cost criteria. Specifically, the agency would have to accept an applicant’s
proposed alternative if it found that the alternative: 1) “provides for the adequate protection
and utilization of the reservation” (§33 (a)(2)(A) of the Federal Power Act as amended by
the conference agreement on H.R. 6), and/or “will be no less protective of the fish resources
than the fishway initially prescribed” (§33 (b)(2)(A) of the Federal Power Act as amended
by the conference agreement on H.R. 6); and 2) costs less to implement, and/or will result
in improved operation of the project for electricity production (§33 (a)(2)(B) and §33
(b)(2)(B)of the Federal Power Act as amended by the conference agreement on H.R. 6).
The House-passed conference agreement, S. 2095, and H.R. 4503 would also require
that the conditioning agency justify its decision to accept or reject the alternative after giving
equal consideration to the effect of its condition and the alternative condition on a broad
range of factors. These factors include energy supply, distribution, cost, and use; flood
control; navigation; water supply; and air quality (in addition to the preservation of other
aspects of environmental quality) (§33 (a)(3)of the Federal Power Act as amended by the
conference agreement on H.R. 6). This section of the proposed legislation differs from the
earlier Senate-passed bill, which would have required the agency to include such factors in
its justification, but not to consider them equally.
The bills also differ from the Senate-passed bill by establishing a system for reviewing
the agency’s condition when it rejects the applicant’s alternative. Specifically, the House-
passed conference agreement states that FERC could refer the agency’s decision to its
Dispute Resolution Service (DRS). Unlike the DRS’ mediation role under the alternative
licensing process (ALP), the proposed legislation would require the DRS to review the facts
and issue a non-binding advisory. The Secretary of the conditioning agency would then
reconsider his or her decision and may or may not accept the advisory.
Discussion
Response to the relicensing legislation in the 108th Congress is mixed. FERC and the
hydroelectric industry support the hydropower relicensing legislation, but some
12 “A bill to enhance energy conservation and research and development, to provide for security and
diversity in the energy supply for the American people, and for other purposes.”
13 Two additional bills, H.R. 1013 and S. 14 (§511) were introduced in the 108th Congress and
contain hydropower licensing titles that are identical to those in the House-passed bill.
CRS-7
IB10122
11-04-04
environmental organizations and some officials within relevant government agencies have
expressed concerns. While the National Hydropower Association is more supportive of the
House-passed conference agreement than the Senate-passed bill, some environmental
organizations view the Senate-passed bill as a modest improvement over the House-passed
bill. According to FERC, the House-passed bills would provide accountability by making
agencies justify their conditions in light of the proposed alternatives and the conditions’
effects on multiple resources. The hydropower industry argues that this legislation would
decrease the cost of license conditions. On the other hand, environmental organizations and
officials within conditioning agencies have expressed concerns that the legislation would
further increase the length of the relicensing process, diminish environmental protection,
reduce the effectiveness of FERC’s new ILP, and give license applicants more authority in
the license conditioning process than other stakeholders. These issues are discussed below.
Length of Process. If enacted, any of the bills would add additional steps to the
licensing process. Specifically, they would require that federal agencies determine whether
or not a proposed alternative meets the environmental and cost criteria described above, and
determine how the alternative and agencies’ conditions affect energy supply, distribution,
cost, and use; flood control; navigation; water supply; and air quality (in addition to the
preservation of other aspects of environmental quality). The House-passed conference
agreement, S. 2095, or H.R. 4503 would also allow license applicants to initiate a trial-type
hearing on issues of material fact. Both of these provisions could add an undetermined
amount of time to the licensing process. The legislation passed in the House and included
in the conference agreement, would also establish a 90-day process for the DRS and FERC
to review the agency’s conditions. This provision was not included in the Senate-passed
H.R. 6.
From the perspective expressed by industry and FERC, the House-passed bill would
most improve the license conditions, thus justifying additional process time. Furthermore,
supporters of the legislation argue that additional procedure on the front end could decrease
delays at the end of the process. However, some environmental organizations, such as the
Hydropower Reform Coalition, argue that the administrative hearings called for in the
House-passed bill could take up to ten years. Furthermore, some opponents of the legislation
argue that new administrative appeals processes and FERC’s July 2003 rule establishing the
ILP will sufficiently improve the relicensing process.
Environmental Issues. Under the FPA, Congress granted FERC the authority to
issue hydropower licenses, but gave federal land and water management agencies the
responsibility for protecting federal reservations and maintaining fish resources. When
issuing license conditions to fulfill their responsibilities under sections 4(e) and 18 of the
FPA, conditioning agencies are not currently required to solicit stakeholder
recommendations. Under the House and Senate-passed bills, the agency “must consider” the
alternative conditions offered by the license applicant. After such consideration, the agency
would not be required to accept the alternative if it found that the proposal does not meet
specified environmental and cost criteria (e.g., the proposed alternative does not adequately
protect the resource).
Although federal conditioning agencies could reject an alternative condition that did not
meet either bills’ environmental and cost criteria, environmental organizations are concerned
that the House-passed bill and conference agreement would distract agencies from their focus
CRS-8
IB10122
11-04-04
on protecting fish and federal reservations. These opponents argue that the bill would require
conditioning agencies to expand their focus to give equal consideration to the conditions’
effects on energy supply, distribution, cost, and use; flood control; navigation; water supply;
and air quality (in addition to the preservation of other aspects of environmental quality).
They further argue that the agencies do not have adequate resources to conduct these
additional studies. However, supporters of the bills argue that requiring agencies to balance
the multiple effects of their conditions would help ensure that license conditions are
established in the public interest.
While the equal consideration clause may expand the agencies’ focus, the effect of this
language on the conditions designed to protect fish and federally reserved lands would
depend on how the agencies interpret the phrase “no less protective of fish resources,” and
the phrase “adequate protection and utilization of the reservation.” Environmental
organizations are concerned that the language contained in the conference agreement, “no
less protective of the fish resource than the fishway14 initially prescribed,” could open the
door for applicants to propose non-fishway alternatives to fishway conditions.15 For
example, environmental organizations are concerned that the legislation would allow the
applicant to propose maintaining fish populations by stocking the river with hatchery fish or
through other mechanisms that do not move native fish. Environmental organizations
generally find these other mechanisms to be less successful than fishways in maintaining
migratory fish populations. However, industry representatives argue that such concerns
regarding the effectiveness of alternative conditions are unwarranted. Specifically,
proponents of the legislation point out that it preserves agencies’ authority to reject
alternatives which are “less protective of the fish resources than the agencies’ alternative.”
Therefore, the applicant’s ability to substitute other mechanisms for fishways, would depend
on the agency’s determination of the protectiveness of the alternative.
Effectiveness of the Integrated Licensing Process (ILP). Environmental
organizations and some officials within conditioning agencies also assert that proposed
legislation, namely the House-passed bill, could weaken the new Integrated Licensing
Process by reducing the incentives for applicants to engage actively in early consultations
with resource agencies. Specifically, opponents of the legislation argue that license
applicants would be less willing to consult and negotiate with resource agencies if the
agencies do not have the authority to issue final license conditions. Conversely, FERC and
the hydropower industry argue that this legislation would not reduce agencies’ conditioning
authority, and thus would not alter an applicant’s incentive to negotiate with agencies. (For
more information on the ILP, see CRS Report RL31536,
Licensing of Non-Federal
Hydroelectric Projects: Background and Current Issues.)
Participation in the Conditioning Process. Under current law, the
recommendations of industry and non-industry stakeholders are given similar weight in
agencies’ conditioning process. A key concern of environmentalists and other nonutility
stakeholder groups is that the bills would increase the applicant’s input relative to other
14 See footnote 4.
15 See the Hydropower Reform Coalition’s press release regarding the energy bill at
[http://www.amrivers.org/index.php?module=HyperContent&func=display&cid=963], available on
March 9, 2004. The Coalition’s line by line critique is no longer available online.
CRS-9
IB10122
11-04-04
stakeholders. Specifically, the House-passed conference agreement, S. 2095, and H.R. 4503
entitle license applicants, but not other stakeholders, to “a determination on the record, after
opportunity for an agency trial-type hearing on any disputed issues of material fact.”
Furthermore, either bill would require that agencies consider the applicant’s alternative
conditions but not the conditions offered by “other interested parties.”16 Some non-industry
stakeholders would prefer to see this section expanded to require that agencies consider
alternatives offered by any stakeholder. However, some officials within conditioning
agencies are concerned that they may have insufficient resources to consider all industry-
proposed alternatives let alone other stakeholder-proposed alternatives.
The bills state that the agency shall accept the applicant’s alternative if it meets the bills’
environmental and cost requirements. Therefore, opponents are concerned that the
legislation would require the conditioning agency to accept a proposed alternative condition
with little regard for its effect on other water resource uses (e.g., recreation, flood control,
irrigation, etc.). However, FERC and the hydropower industry point out that FERC already
has the responsibility to balance multiple water uses, and that the bill could decrease the cost
of meeting agencies’ section 4(e) and 18 objectives.17
Conclusion
Enactment of H.R. 6, S. 2095, or H.R. 4503 would affect the conditioning process in
a number of ways. Any versions of the bills would allow stakeholders to offer alternative
license conditions. The House-passed bill and the conference agreement would also create
a mechanism for reviewing the decision of conditioning agencies and would entitle license
applicants to a trial-type hearing on facts related to the agency’s conditions. These changes
could lengthen the conditioning process. H.R. 6, S. 2095, or H.R. 4503 could also increase
the influence of applicants relative to other stakeholders. The effect of these bills on fish
resources and on federal reservations is unclear and would depend on how conditioning
agencies interpret the terms “adequate protection and utilization of the reservation” and “no
less protective of the fish resources.” The effect of the House-passed conference agreement
and S. 2095 on other resources could depend on how the agencies balance their obligation
to accept the applicant’s alternative (i.e., if it meets the two criteria) relative to their
responsibility to justify the conditions they select based on equal consideration of multiple
effects. It appears that these issues could lead to further review.
16 U.S. Congress, House, Energy and Commerce Committee, Subcommittee on Energy and
Commerce, testimony of Leon Szeptycki, General Council of Trout Unlimited, on the Role of the
Federal Government in Licensing Hydropower Dams, hearing, March 12, 2003.
17 U.S. Congress, House, Energy and Commerce Committee, Subcommittee on Energy and
Commerce, testimony of J. Mark Robinson, Director, Office of Energy Products, Federal Energy
Regulatory Commission, hearing, March 12, 2003.
CRS-10
IB10122
11-04-04
LEGISLATION
H.R. 6 (Tauzin)
Language in Title III, Section 13001 is identical to H.R. 1013. Introduced April 7,
2003; referred to the House Energy and Commerce Committee. Introduced in the Senate
April 7, 2003; referred to multiple committees. Passed House April 11, 2003; passed Senate
July 31, 2003. Conference agreement reached on November 17, 2003. Conference report
passed by House on November 18, 2003.
H.R. 1013 (Radanovich)
Establishes new requirements for federal agencies that set conditions or fishway
prescriptions for hydroelectric licenses under sections 4(e) and 18 of the Federal Power Act.
Allows license applicants to initiate a trial-type hearing on factual issues related to the
agency’s conditions. Requires federal agencies to consider alternative conditions proposed
by the license applicant and accept the proposed alternative if it (1) provides for the adequate
protection and utilization of the reservation, or will be “no less protective of the fish
resources than the fishway initially prescribed” and (2) will either cost less, and/or will
improve the project’s operational efficiency. Requires the agency to justify its decision to
accept or to reject the alternative after giving equal consideration to both conditions’ effects
on a broad range of factors. Establishes a system for reviewing an agency’s decision when
it rejects the applicant’s alternative. Introduced February 27, 2003; referred to House
Committee on Energy and Commerce, Subcommittee on Energy and Air Quality.
H.R. 4503 (Barton)
Section 231 is identical to H.R. 1013 and Title III, Section 13001 of the House-passed
bill, H.R. 6. Introduced June 3, 2004. Passed by the House June 15, 2004 and received by
the Senate June 17, 2004.
S. 14 (Domenici)
Section 511 is identical to H.R. 1013 and Title III, Section 13001 of the House-passed
bill, H.R. 6. Introduced April 30, 2003; returned to the Senate’s Legislative Calendar on July
31, 2003. In lieu of S. 14, the Senate passed H.R. 6, as amended, with language from H.R.
4 of the 107th Congress in the nature of a substitute. Title III of this Senate-passed bill
establishes new requirements for federal agencies that set conditions or fishway prescriptions
for hydroelectric licenses under sections 4(e) and 18 of the Federal Power Act. It requires
federal agencies to consider alternative conditions proposed by the license applicant and
accept the proposed alternative if it (1) provides for the adequate protection and utilization
of the reservation, or will be “no less protective of the fish resources than the fishway
initially prescribed” and (2) will either cost less, and/or will improve the project’s operational
efficiency as compared to the condition initially deemed necessary by the Secretary. Title
III requires the agency to explain the basis for its decision to accept or to reject the alternative
and to describe both conditions’ effects on a broad range of factors.
S. 2095 (Domenici)
Section 231 of Title II is identical to Title III Section 13001 of H.R. 6. Introduced
February 12, 2004.
CRS-11
IB10122
11-04-04
CONGRESSIONAL HEARINGS, REPORTS, AND DOCUMENTS
Hearings
U.S. Congress. House. Committee on Energy and Commerce. Subcommittee on Energy
and Air Quality. Hearing, March 12, 2003, on comprehensive energy policy at
[http://energycommerce.House.gov/108/Hearings/03122003hearing819/hearing.htm].
U.S. Congress. House. Committee on Energy and Commerce. Subcommittee on Energy and
Air Quality.
Hydroelectric Relicensing and Nuclear Energy. Hearing, June 27, 2001.
107th Congress, 1st session. 185p. (H.Rept. 107-55)
U.S. Congress. Senate. Committee on Energy and Natural Resources.
National Energy
Issues. Hearing, July 19, 2001. 107th Congress, 1st session. 202 p.(S.Rept. 107-144)
FOR ADDITIONAL READING
CRS Reports
CRS Report RL31536.
Licensing of Non-Federal Hydroelectric Projects: Background and
Current Issues.
CRS Report RL31903.
Relicensing of Non-Federal Hydroelectric Projects: Summary and
Discussion of Procedural Reform Proposals.
Other Documents
Federal Energy Regulatory Commission.
Hydroelectric License Regulations under the
Federal Power Act: Notice Requesting Comments and Establishing Public Forums and
Procedures and Schedule, FERC Docket No. RM02-16-000 (Washington, DC:
September 12, 2002)
Federal Energy Regulatory Commission.
Notice Requesting Comments and Establishing
Public Forums and Procedures and Schedule pursuant to (18 CFR Parts 4 and 16),
Docket No. RM02-16-000 (Washington, DC: February 20, 2003).
[http://www.ferc.gov/industries/hydropower/indus-act/hydro-rulemaking-nopr.pdf]
CRS-12