The Army's XM-30, previously known as the Optionally Manned Fighting Vehicle (OMFV), is being designed to replace the M-2 Bradley Infantry Fighting Vehicle (IFV) (see Figure 1 for a notionalconceptual example). Optionally manned means the OMFV is to have the capability to conduct remotely controlled operations while a crew is not in the vehicle. The M-2 Bradley, which has been in service since 1981, transports infantry on the battlefield, provides fire support to dismounted troops, and can destroy enemy fighting vehicles. Updated numerous times since its introduction, the M-2 Bradley is widely considered to have reached the technological limits of its capacity to accommodate new electronics, armor, and defensive systems. Two past efforts to replace the M-2 Bradley—the Future Combat System (FCS) Program and the Ground Combat Vehicle (GCV) Program—were cancelled for programmatic and cost-associated reasons.
|
Source:
|
On June 26, 2023, on the completion of the initial digital design phase, the Army redesignated the OMFV as the XM-30 Mechanized Infantry Combat Vehicle.
According to the 2024 Department of Defense (DOD) FY 2025 FY2025 Program Acquisition Costs by Weapons Systems
The XM-30Cost by Weapon System (DOD is "using a secondary Department of War designation," under Executive Order 14347 dated September 5, 2025),
[t]he XM30 Combat Vehicle (previously OMFV), as part of an Armored Brigade Combat Team (ABCT), will replace the Bradley Infantry Fighting Vehicle to provide the capabilities required to defeat a future near-peer competitor's force. The XM-30XM30 is an optionally manned platform that maneuvers soldiersSoldiers to a point of positional advantage to engage in close combat and deliver decisive lethality during the execution of combined arms maneuver. It is designed to operate with and may operate without a crew and soldiersSoldiers under armor based on the commander's decision.
The XM-30 is a Middle Tier Acquisition Rapid Prototyping (MTA-RP) program. The XM-30 is to be the Army's first ground combat vehicle designed using state-of-the-art digital engineering tools and techniques. It is to be designed from the onset as a Modular Open Systems Architected (MOSA) platform based on an Army-defined and -owned open standard. As technology and software evolve, MOSA could facilitate rapid XM-30 modernization at a reduced cost. The open architecture of the XM-30 could also offer more opportunities for industry competition and innovations as the XM-30 is upgraded.
The Army is conducting a five-phase acquisition approach to design, prototype, test, and produce the XM-30:
The Army announced the award of five firm-fixed price contracts for XM-30 Phase 2 Concept Design Phase using full and open competitive procedures on July 23, 2021. The contracts were awarded to Point Blank Enterprises, Inc. (Miami Lakes, FL); Oshkosh Defense, LLC (Oshkosh, WI); BAE Systems Land and Armaments L.P. (Sterling Heights, MI); General Dynamics Land Systems (GDL), Inc. (Sterling Heights, MI); and American Rheinmetall Vehicles, LLC (Sterling Heights, MI). The total award value for all five contracts was approximately $299.4 million. In this phase, competing firms were asked to develop digital designs.
On June 26, 2023, the Army announced
[t]hethe award of two firm-fixed price contracts for the Optionally Manned Fighting Vehicle [XM-30] Phase 3III and 4IV Detailed Design and Prototype Build and Testing phases, using full and open competitive procedures. The contracts were awarded to General Dynamics Land Systems Inc. [GDLS] (Sterling Heights, MIMichigan) and American Rheinmetall Vehicles LLC (Sterling Heights, MIMichigan). The total award value for both contracts is approximately $1.6 billion.
Reportedly, General Dynamics Land SystemsGDLS and American Rheinmetall Vehicles completed their PDR in August 2024, and and, after a critical design review, development of physical prototypes was planned to begin after a critical design review. According to Defense News
Prototypes,
[p]rototypes will take 18 to 20 months to construct after the critical design reviews wrap up. Once prototypes are delivered, the Army will move into a test and evaluation phase with both competitors before deciding on a winner in FY2027[FY]2027. The first vehicles are expected to be fielded in FY2029[FY]2029.
In June 2025, the U.S. Army reportedly approved Milestone B for the XM-30 program, advancing it into the engineering manufacturing development phase after both competitors completed critical design reviews. In February 2026, Army leadership reportedly opted not to sign documentation finalizing the Milestone B decision to avoid locking the service into a specific design or a slow acquisition path, effectively pausing formal program transition and prompting a reevaluation of the program's approach.
According to the Department of Defense (DOD) FY 2026 Program Acquisition Costs by Weapons Systems
The XM30 is an MTA-RP program. Milestone B was approved in June 2025, and Milestone C is targeted for first quarter FY 2028. The Army Transformation Initiative will accelerate this program. [In FY2026 the Army] continues to fund prototype vehicle designs from Preliminary Design Review (PDR) through CDR in preparation for both physical prototype builds and tests.
According to the February 2026 report, the then Chief of Staff of the Army General Randy George and thethen Secretary of the Army Dan Driscoll decided not to sign off on the Milestone B decision "to leave the door open to a major reworking of the XM-30 Mechanized Infantry Combat Vehicle program." Reportedly, regarding the pause, an Army spokesman stated the following:
"We are actively assessing multiple, competing designs for the XM-30XM30 to foster a truly competitive environment.… We continue to look for partners who can deliver cutting-edge solutions now, not decades from now."
According to Army Budget documents, the Army is requesting $547 million in procurement funding for 19 prototype vehicles for evaluation. The Army notes that prime contractor(s)contractors have yet to be identified, but award decisions for the 19 vehicles will be based on contractor performance during the MTA-RP phase and testing and operational evaluations.
Reportedly, the 1st Cavalry Division at Fort Hood, TX, in Texas is to be the first unit to receive new prototypes of the XM-30 this fall. Reportedly
The,
[t]he Army's largest division will take on two platoons of the XM-30XM30, designed to replace the Bradley Fighting Vehicle, and one platoon of M-1E3M1E3 Abrams tanks by the end of the year. From there, soldiers will be "shooting, moving and communicating" at the National Training Center [NTC] at Fort Irwin, CA, through March [2027].
As part of this operational testing, the Army Test and Evaluation Command (ATEC) reportedly is Reportedly, Rheinmetall delivered its first prototype, known as the Lynx, on September 1, 2026, and GDLS delivered its first prototype, the Wolf, at the end of August 2026. These prototypes and the remaining protypes are intended to support Fort Hood operational testing scheduled for fall 2026."to "work in conjunction with the division to monitor the assessments from 1st Cavalry soldiers, who will provide feedback to engineers for 'minor adjustments.'"
First XM-30 Prototypes Delivered
"
Potential oversight issues could include the following:
With General George's retirement in April 2026 and Secretary Driscoll's reported resignation on August 31, 2026, the Army is presently without Senate-confirmed senior leadership. At some point in the future, a new Secretary of the Army and Chief of Staff of the Army are likely to be nominated for confirmation. Once confirmed, a new Secretary of the Army and Chief of Staff could have differing views on the requirements for a Bradley replacement, the current XM-30 program, and Army modernization priorities altogether. Once new Army leadership is confirmed, Congress might decide to seek clarification from the Army on its views on the future of the XM-30 program.
XM-30 Organic Counter Uncrewed Aerial Systems (C-UAS) CapabilityWhile the Army has stated that the XM-30 is to have an organic active protection system (APS) that can detect, track, and neutralize anti-tank threats by means of kinetic and passive countermeasures, it is not clear if the XM-30 also will have an organic C-UAS capability. Some have suggested that UAS, loitering munitions, and one-way attack drones could make armored fighting vehicles (AFVs) obsolete; others contend new technologies are needed to improve AFV survivability against UAS and other aerial systems. Congress might decide to examine the Army's approach to provideproviding organic protection to the XM-30 against aerial threats.