February 5, 2025

Data Centers and Cloud Computing: Information Technology Infrastructure for Artificial Intelligence

The advancement of artificial intelligence (AI), a “critical and emerging technology,” presents policy considerations for U.S. leadership, with implications for economic competitiveness and national security. AI systems, including their development, model training, deployment, operation, applications, and servicesData Centers and Cloud Computing: Information Technology Infrastructure for Artificial Intelligence

Updated November 16, 2026 (IF12899)
Artificial intelligence (AI) systems, including their development, deployment, and operation, rely on an information technology (IT) infrastructure with components of hardware, software, networks, data, and facilities. Data centers are the primary means to house much of this IT backbone. Internet-based remote computing services (i.e., cloud computing) enable AI developers and users to access computing resources hosted in geographically distributed data centers. Not only may AI innovation and competition hinge on the availability of and access to advanced, secure, and sustainable computing resources, but such IT infrastructure may also be deemed “a strategic national asset.” Related issues have attracted congressional attention in recent years (e.g., a Senate committee hearing on advanced computing research and a House committee hearing on “powering AI”).

The U.S. government has increasingly focused on policy directions to support building a robust, domestic AI infrastructure. For example, President Biden issued Executive Order (E.O.) 14141, “Advancing United States Leadership in Artificial Intelligence Infrastructure,” on January 14, 2025, providing a federal plan to build AI infrastructure in the United States. On January 21, 2025, President Trump announced a private joint venture with potential investment of up to $500 billion to fund AI infrastructure, including plans to build up to 20 data centers in the country. The National Telecommunications and Information Administration (NTIA), a Department of Commerce agency serving as the President’s principal advisor on telecommunication and information policies, issued a request for comments (RFC) to inform policymaking for “sustainable, resilient and secure” growth of data centers to power critical and emerging technologies, including AI. The RFC received 58 comments, ranging from the importance of allocating an estimated $175 billion of potential funds to U.S.-backed global AI infrastructure projects to challenges faced by domestic data centers, such as regulatory obstacles for siting new facilities and access to energy, supply chains, and operational workforce.

This In Focus introduces the use of data center and cloud computing infrastructure for AI development and AI- enabled services and selected policy issues for congressional consideration. For more on AI technologies and policies, see CRS Report R47644, Artificial Intelligence: Overview, Recent Advances, and Considerations for the 118th Congress; for more on energy

issues related to selected data centers, see CRS Report R45863, Bitcoin, Blockchain, and the Energy Sector.

Overview of Data Centers In its simplest form, a data center is a facility that houses and powers a large computer system. Data centers have evolved to house multiple enterprise-level, interconnected computer servers (e.g., a cluster of servers called a server farm). Personal computers and smart devices connect users to these servers to access online services (e.g., websites, emails, and file sharing). Many data centers have expanded to support cloud computing services, allowing users to remotely access computing resources such as data processing chips, software, data storage, networks, and applications and services hosted by these centers.

The term data center has been defined in federal laws in the context of energy efficiency and federal use of data centers. For instance, the Energy Independence and Security Act of 2007 (P.L. 110-140, §453(a)(1)) defines a data center as a facility that “contains electronic equipment used to process, store, and transmit digital information.” In its guidance (M- 25-03) for federal agencies to implement the Federal Data Center Enhancement Act of 2023 (P.L. 118-31, §5302), the Office of Management and Budget specified that a data center (1) is composed of permanent structures and operates in a fixed location; (2) houses IT equipment, including servers and other high-performance computing devices, or data storage devices; and (3) hosts information and information systems accessed by other systems or by users on other devices.

Data Centers for AI The ever-increasing demand for data storage and processing capacities, especially for intensive computational tasks such as AI training, has led to construction and operation of hyperscale data centers. According to industry analysts, to be considered a hyperscale data center, a facility must contain at least 5,000 servers and occupy at least 10,000 square feet of physical space, with a power demand exceeding 100 megawatts (MW). If a data center had a continuous power demand of 100 MW for 24 hours, it would consume 2,400 MW-hours (MWh) of energy.

These large facilities provide powerful computing resources (such as memories, central processing units [CPUs], and graphics processing units [GPUs]) to handle vast amounts of data and large-scale workloads. (CPU and GPU are two major types of computing chips found in most personal computers and servers.) General-purpose workloads typically require only a CPU, while a GPU is generally considered better than a CPU to handle AI computational tasks. According to the chip manufacturer Nvidia, an AI-

Data Centers and Cloud Computing: Information Technology Infrastructure for Artificial Intelligence

https://crsreports.congress.gov

ready data-center server can support one to eight high- performance GPUs, each of which consumes hundreds of watts of electricity. Cutting-edge chip technologies also support high-speed (at the gigabit-per-second level) GPU- to-GPU data communication among hundreds of GPUs across multiple servers, enabling the creation of a massive AI server farm in a data center.

In E.O. 14141, the term AI data center means a data center used primarily to develop or operate AI, and the term frontier AI data center means an AI data center capable of being used to develop an AI model that matches or surpasses the state-of-the-art AI model with regard to its performance or computational resources used in its development. These frontier AI models and related services typically require more power than traditional IT operations supported by data centers (e.g., data storage, retrieval, and transmission). For example, ChatGPT was estimated to use 2.9 watt-hours to respond to a user query, while a traditional Google search query uses about 0.3 watt-hours.

Multiple industry reports indicate that data processing demands of AI and related cloud computing services have spurred new construction and upgrades of data centers. The computing resources hosted by these centers would in turn lead to increased power demand. For example, one report estimated that the computing capacity (measured by the power demand) of data centers under construction in North America in the first half of 2024 reached a record-high 3,872 MW, up by 69% from a year earlier. Nearly 80% of this capacity has been pre-leased, with AI and cloud service providers contributing to significant portions of such demand. A report commissioned by the Department of Energy estimated that data centers accounted for about 4.4% of total U.S. electricity consumption (or about 176 million MWh) in 2023, “equivalent to the average annual consumption of 14 million households.” According to another report, new hyperscale data centers have been built with capacities from 100 to 1,000 MW, “roughly equivalent to the load from 80,000 to 800,000 homes.”

Investments in AI Infrastructure Many experts believe that AI development and operation require significant capital investment. According to the annual AI Index Report 2024, costs of training large foundation models alone could “run into millions of dollars and are rising.” Given rental prices charged by major cloud service providers for accessing computing hardware, the report estimated that training costs in 2023 for OpenAI’s GPT-4 and Google’s Gemini Ultra were around $78 million and $191 million, respectively (excluding other costs, such as data acquisition and labor). In a January 24, 2025, Facebook post, Meta’s CEO revealed that the company was building a 2,000-MW data center and planned to spend $60- $65 billion in AI capital expenditures and acquire over 1.3 million GPUs by the end of 2025. Three days earlier at the White House, a group of companies announced a joint venture called Stargate, planning to invest up to $500 billion over the next four years to build AI infrastructure in the United States. Stargate’s first data center, reportedly under construction, would be used by OpenAI and operated by Oracle (one of the largest cloud-based database vendors).

The tech industry and financial market have raised questions about large investments in AI infrastructure, due to the emergence of high-performing AI models developed by the less-known Chinese company DeepSeek. The company claimed in a non-peer-reviewed technical report that it has developed a large language model (LLM) called DeepSeek-V3 using efficient and cost-effective approaches. The model required 2.8 million GPU hours (equal to about 57 days) for its full training on a cluster of 2,048 Nvidia H800 GPUs. Assuming the cloud rental price at $2 per GPU hour, DeepSeek reported its total training cost for the model was $5.6 million—a fraction of what is currently spent by leading U.S. AI companies (e.g., $78 million for GPT-4). Nvidia reportedly developed the H800 chip in March 2023 as a modified version of its more powerful H100 GPU to comply with U.S. export control regulations. It is no longer permissible to export the H800 chip since the Department of Commerce’s Bureau of Industry and Security updated its rules on advanced computing chips in October 2023 (see Category 3A090 in Supplement No. 1 to 15 C.F.R. Part 774).

According to its report, DeepSeek evaluated its V3 model against several leading LLMs, including those developed by Alibaba, Meta, OpenAI, and Anthropic. In six benchmark tests in language understanding, graduate-level science and mathematics questions, high school-level math competition questions, coding, and memory-chip security, the company claimed that DeepSeek-V3 outperformed the competitors in three and ranked second in the other three. The widely reported relatively low-cost advancement in AI model training has raised questions about the necessity of large AI investments, the efficiency of AI development, and U.S. leadership in the field.

Selected Policy Issues for Congress AI infrastructure, including data centers, cloud computing services, and energy resources, is vital for AI development and operation. The criticality of such infrastructure raises policy issues such as data security, infrastructure access and security, energy reliability and efficiency, and costs of building such infrastructure, all of which implicate national security interests. Investment, construction, and operation of AI infrastructure may impact job and workforce development opportunities, and the economies and natural resources hosting facilities (these components are collectively known as AI compute). Data centers, physical facilities that house and run large computer systems, are the primary means to store much of this AI compute. Cloud computing, an internet-based IT service model, enables AI developers and users to remotely access AI models and tools as well as computing resources hosted in data centers. Some AI researchers have suggested that the performance of certain AI models (e.g., large language models) improves with the scaling of three factors: the number of model parameters, the size of the training datasets, and the amount of computing resources used for training. Collectively known as AI scaling laws, these patterns drive the current paradigm of AI development: More capable AI systems require larger models, more data, and more computing resources. Researchers assert that these scaling requirements have led to "unprecedented" capital investment in AI infrastructure, the magnitude and speed of which "have surpassed previous investment booms" in U.S. history. The rush to build AI data centers has raised several public concerns, including the energy and water consumption needed for data center operations; the associated potential impacts on power grids, utility bills, and environment effects; and a lack of disclosure and public involvement in the decisionmaking process. Several cloud service providers (CSPs) leverage loans to support AI infrastructure build-out, and some experts assert that this debt is contributing to increasing financial risks in stock and lending markets.

This In Focus introduces concepts of data centers and cloud computing and policy considerations for Congress. It focuses on the roles of data centers and cloud computing as AI infrastructure. For data center-related energy and water issues, see CRS Report R48646, Data Centers and Their Energy Consumption: Frequently Asked Questions; CRS Report R49326, Data Centers and the Electricity Grid: Frequently Asked Questions; and CRS Report R49057, Data Centers and Water: Frequently Asked Questions.

From General IT Data Centers to AI Data Centers

The term data center has been defined in federal laws. For instance, in the Energy Independence and Security Act of 2007, Congress defined it as any physical facility that "primarily contains [IT] equipment used to process, store, and transmit digital information" (P.L. 110-140 §453).

Since the early 2000s, data centers have served as an important IT resource for the operation of organizations, for example, in telecommunications, financial services, health care, and government sectors. An increasing number of private and public entities use data centers to support their expanding IT needs, particularly as data volumes continue to grow. The United States reportedly has over 5,000 data centers in operation. Many of them serve general IT functions. General IT or traditional data centers connect consumers with access to online services and content such as websites, emails, file sharing, and video streaming. Many CSPs build and operate geographically distributed but interconnected general IT data centers to allow their users to remotely access a shared pool of computing resources and services, such as data processing chips, data storage devices, databases, software, and networks, as well as web hosting, data analytics, and application deployment.

AI data centers are different from general IT data centers in workload type, primary hardware, and power demand. General IT data centers performing routine, sequential computing tasks such as hosting and managing enterprise and consumer data typically use general-purpose central processing units (CPUs). Since the current AI development cycle started in late 2022, the demand for high-performance, specialized computing chips, such as graphics processing units (GPUs) and high-bandwidth memory (HBM), has grown rapidly in order to handle large-scale AI workloads. These chips, along with datasets, algorithms, and software required for AI, are largely housed in data centers often managed by CSPs. A data center primarily used for AI model training and inference may require tens of thousands of GPUs or other specialized chips designed for complex computational tasks.

Leading AI developers and some industry analysts have argued that existing data center capacities cannot meet the AI demand due to intensive computational tasks in model training and surging inference requests (i.e., running a trained model) as a result of the increasing AI adoption, use, and proliferation of agentic AI. Billions of dollars in private investment have been reportedly announced to fund the construction or expansion of over 1,000 data centers throughout the country. This data center surge is likely driven by two factors: AI scaling laws and the associated expectation of a lasting computing shortage and the view that controlling AI infrastructure is a strategic competitive advantage and key to market dominance.

Defining AI Data Centers

An advanced GPU designed for AI data centers can draw up to 1,000 watts of electricity when operating at its full capacity. The electrical energy entering the chip is converted into a matching amount of thermal energy (i.e., heat). A data center's cooling system (either air or liquid based) must use additional power to dissipate the heat in order to keep the housed chips from overheating. By comparison, a typical data-center CPU draws about one-fourth of that power (and therefore requires less cooling). The sheer number of GPUs and supporting power distribution and cooling infrastructure require more physical space in an AI data center than in a traditional one.

Because chips in an AI data center require massive amounts of power to run, the facility's maximum computing capacity is directly bound by its available power supply. In turn, how much electric power the data center can draw at its peak workload—measured in megawatts (MW; 1 MW = 1 million watts) or gigawatts (GW; 1 GW = 1,000 MW)—has become the primary metric when referring to its scale. For example, according to some industry analysts, to be considered a "hyperscale data center," the facility should be able to draw over 100 MW of power at any moment, house at least 5,000 computer servers, and occupy at least 10,000 square feet. A data center running at a continuous demand of 100 MW for 24 hours would consume 2,400 MW-hours (MWh) of energy. That single-day electricity consumption is roughly equal to the daily use of 80,000 average U.S. households.

Lawmakers have introduced several bills addressing various public concerns associated with AI data centers, using power demand thresholds to define covered facilities. These power thresholds vary, suggesting that it may be a legislative challenge to differentiate between traditional and AI data centers. Some bills introduced in the 119th Congress provided definitions of AI data centers using power demand thresholds between 20 MW and 100 MW along with other characteristics, such as the proportion of computing resources used for AI purposes. For example, the Artificial Intelligence Data Center Moratorium Act (H.R. 9442/S. 4214) set the threshold as "a maximum rated power capacity or total peak power load in excess of 20 [MW]." In the Artificial Intelligence Environmental Impacts Act of 2026 (H.R. 9183/S. 4727), a covered data center "has a maximum rated power capacity or total peak power load in excess of 50 [MW]." The RECLAIM Act (S. 5689) set the threshold as "a contracted peak power demand of not less than 100 [MW]."

Policy Considerations for Congress

Several dynamics define the current landscape of AI data centers and associated cloud computing services. First, the investment and build-out, if fully realized, could happen at a massive scale. Figure 1 illustrates data centers over 100 MW—either operational, under construction, or planned—across the country. Some data center projects have surpassed 1 GW, and the five largest CSPs were expected to commit approximately $4.6 trillion in AI capital expenditure between 2022 and 2030.

Second, data centers and cloud computing are becoming strategically important infrastructure for AI. They were recently at the center of the global AI race debate following the 2026 Nvidia controversy over alleged export-control workarounds. After data centers in third-party countries acquired large numbers of advanced GPUs, AI developers located in countries subject to U.S. export controls were reportedly able to access those computing resources remotely through CSPs located there. This widely reported loophole raises important questions related to national and economic security.

Figure 1. U.S. Locations of Data Center Projects Over 100 Megawatts

Source: CRS, based on data downloaded from Jillian Bommarito and Michael James Bommarito, "Data Center Policy Across the 50 States: A Survey of Incentives, Land Use, and Energy Regulation," June 18, 2026, Server Country.

Notes: Server Country uses primary sources such as company announcements, regulatory filings, and news reports to identify data center projects. This information should be considered illustrative rather than comprehensive. The operational category includes existing data centers with planned expansions.

Lastly, there is public opposition to AI data centers. AI infrastructure development and operation may have various impacts on natural resources and the economies of local communities near data centers. The land use, permits, and construction of data centers are largely subject to state and local regulation, though some federal requirements may apply. Federal and state authorities and local communities all potentially influence AI data center development. Leading AI developers and CSPs may also align their data center projects with public interests and policy goals.

AI infrastructure, including data centers and cloud computing services, is vital for AI development and operation. The criticality of such infrastructure raises policy issues such as infrastructure access and security, energy reliability and efficiency, and costs of building such infrastructure, all of which implicate national security interests. These issues and the current policy landscape present some legislative considerations. For example, Congress may consider how to facilitate enhancing AI compute to support innovation and maintain U.S. leadership in AI. Congress may consider legislation to ensure that data center construction, expansion, or operation aligns with public interests, such as community benefits, disclosure of natural resource consumption and environmental impacts, and regional and national economic development. Congress may also consider leveraging data centers to pace AI development, such as through legislation that pauses AI data center construction until other laws are enacted to regulate the release of AI products, address economic and workforce impacts of AI, and ensure AI data centers meet specified criteria (as proposed in H.R. 9442/S. 4214).

of local communities near data centers.

Previous Congresses saw bills to assess, understand, and address potential impacts of growth in AI, data centers, and needs for advanced computing resources. For example, the Department of Energy AI Act (S. 4664, 118th Congress) would have required the Secretary of Energy to report to Congress on data centers for advanced computing, their hardware and software needs for AI, and national security risks. The Remote Access Security Act (H.R. 8152, 118th Congress) would have expanded export controls to include remote access (e.g., through a cloud computing service) to a commodity, software, or technology for purposes such as training AI models.

Ling Zhu, Analyst in Telecommunications Policy

IF12899

Data Centers and Cloud Computing: Information Technology Infrastructure for Artificial Intelligence

https://crsreports.congress.gov | IF12899 · VERSION 1 · NEW

Disclaimer

This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you wish to copy or otherwise use copyrighted material.