< Back to Current Version

Coast Guard Cutter Procurement: Background and Issues for Congress

Changes from January 27, 2016 to March 22, 2016

This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.


Coast Guard Cutter Procurement: Background and Issues for Congress

March 22, 2016 (R42567) Jump to Main Text of Report

Contents

Summary

The Coast Guard's acquisition
Coast Guard Cutter Procurement: Background and Issues for Congress Ronald O'Rourke Specialist in Naval Affairs January 27, 2016 Congressional Research Service 7-5700 www.crs.gov R42567 Coast Guard Cutter Procurement: Background and Issues for Congress Summary The Coast Guard’s program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The NSC, OPC, and FRC programs have a combined estimated acquisition cost of about $21.1 billion, and the Coast Guard’Coast Guard's proposed FY2016FY2017 budget requestedrequests a total of $449.9467 million in acquisition funding for the three programs. the NSC, OPC, and FRC programs. NSCs are the Coast Guard's largest and most capable general-purpose cutters. They have an estimated average procurement cost of about $684 million per ship. The first five are now in service. The sixth, seventh, and eighth are under construction and scheduled for delivery in 2016, 2018, and 2019, respectively. A ninth ship in the class, which was not requested by the Coast Guard, was funded by Congress in FY2016. (The Coast Guard's proposed FY2016FY2017 budget requested $91.4 requests $127 million in acquisition funding for the NSC program for structural enhancements on the first two NSCs and post-delivery activities on NSCs 5 through 8.) post-delivery activities on NSCs 4 through 8, program close-out, follow-on test and evaluation, program support, and procurement of small unmanned aerial systems (sUASs) for NSCs. OPCs are to be smaller, less expensive, and in some respects less capable than NSCs. They have an estimated average procurement cost of about $484 million per ship. The first OPC is to be procured in FY2018. Three shipyards—Bollinger Shipyards of Lockport, LA, Eastern Shipbuilding Group of Panama City, FL, and General Dynamics Bath Iron Works (GD/BIW) of Bath, ME—are competing for the contract to build the first 9 to 11 ships in the class. The Coast Guard’ Guard's proposed FY2016FY2017 budget requested $18.5requests $100 million in acquisition funding for the OPC program. program for technical review of detail design (DD) deliverables and procurement of long lead time material (LLTM) for the first ship. FRCs are considerably smaller and less expensive than OPCs. They have an estimated average procurement cost of about $73 million per boat. A total of 38 have been funded through FY2016. The 14th16th was commissioned into service on October 16, 2015. The 15th and 16th were accepted by the Coast Guard on October 20 and December 23, 2015, and are scheduled for commissioning in January and March 2016, respectivelyMarch 11, 2016. The Coast Guard's proposed FY2016 budget requested $340FY2017 budget requests $240 million in acquisition funding for the FRC program. for the construction of four more FRCs. The NSC, OPC, and FRC programs pose several oversight issues for Congress. Congress’s decisions on these programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base. Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress Contents Introduction ..................................................................................................................................... 1 Background ..................................................................................................................................... 1 Older Ships to Be Replaced by NSCs, OPCs, and FRCs .......................................................... 1 Missions of NSCs, OPCs, and FRCs ........................................................................................ 2 NSC Program ............................................................................................................................ 3 OPC Program ............................................................................................................................ 4 FRC Program ............................................................................................................................ 7 NSC, OPC, and FRC Funding in FY2013-FY2016 Budget Submissions ................................ 9 Issues for Congress ........................................................................................................................ 10 Planned NSC, OPC, and FRC Procurement Quantities .......................................................... 10 Funding Level of Coast Guard’s Acquisition Account ............................................................ 16 Multiyear Procurement (MYP) and Block Buy Contracting................................................... 20 OPC Program: FY2016 Funding Request ............................................................................... 21 OPC Program: Cost, Design, and Acquisition Strategy .......................................................... 22 NSC Program: Initial Testing .................................................................................................. 23 NSC Program: Rotational Crewing ......................................................................................... 24 FRC Program: Operational Testing ......................................................................................... 25 Legislative Activity for FY2016 .................................................................................................... 28 Summary of Appropriations Action on FY2016 Acquisition Funding Request ...................... 28 FY2016 Department of Homeland Security (DHS) Appropriations Act (H.R. 3128/S. 1619/H.R. 2029)................................................................................................................... 28 House ................................................................................................................................ 28 Senate ................................................................................................................................ 29 Conference ........................................................................................................................ 33 Coast Guard Authorization Act of 2015 (H.R. 1987/S. 1611/H.R. 4188) ............................... 33 House ................................................................................................................................ 33 Senate ................................................................................................................................ 35 Conference ........................................................................................................................ 36 Figures Figure 1. National Security Cutter................................................................................................... 3 Figure 2. Offshore Patrol Cutter (Generic Conceptual Rendering) ................................................. 5 Figure 3. Fast Response Cutter ........................................................................................................ 8 Figure 4. Projected Mission Demands vs. Projected Capability/Performance .............................. 13 Tables Table 1. NSC, OPC, and FRC Funding in FY2013-FY2016 Budget Submissions ....................... 10 Table 2. Program of Record Compared to Objective Fleet Mix ..................................................... 11 Table 3. POR Compared to FMAs 1 Through 4 ............................................................................ 12 Table 4. Force Mixes and Mission Performance Gaps .................................................................. 12 Table 5. POR Compared to Objective Mixes in FMA Phases 1 and 2 .......................................... 14 Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress Table 6. Funding in AC&I Account in FY2013-FY2016 Budgets ................................................ 16 Table 7. Summary of Appropriations Action on FY2016 Acquisition Funding Request .............. 28 Contacts Author Contact Information .......................................................................................................... 37 Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress Introduction This report provides background information and potential oversight issues for Congress on the Coast Guard’s programs for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs). These 91 planned cutters are intended as replacements for 90 aging Coast Guard cutters and patrol craft. The Coast Guard began procuring NSCs and FRCs a few years ago, and several NSCs and FRCs are now in service. The Coast Guard plans to begin procuring OPCs within the next few years. The NSC, OPC, and FRC programs have a combined estimated acquisition cost of about $21.1 billion, and the Coast Guard’s proposed FY2016 budget requested a total of $449.9 million in acquisition funding for the three programs. The issue for Congress is whether to approve, reject, or modify the Coast Guard’s funding requests and acquisition strategies for the NSC, OPC, and FRC programs. Congress’s decisions on these three programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base. The NSC, OPC, and FRC programs have been subjects of congressional oversight for several years, and were previously covered in an earlier CRS report that is now archived.1 The Coast Guard’s plans for modernizing its fleet of polar icebreakers are covered in a separate CRS report.2 Background Older Ships to Be Replaced by NSCs, OPCs, and FRCs The 91 planned NSCs, OPCs, and FRCs are intended to replace 90 older Coast Guard ships—12 high-endurance cutters (WHECs), 29 medium-endurance cutters (WMECs), and 49 110-foot patrol craft (WPBs).3 The Coast Guard’s 12 Hamilton (WHEC-715) class high-endurance cutters entered service between 1967 and 1972.4 The Coast Guard’s 29 medium-endurance cutters include 13 Famous (WMEC-901) class ships that entered service between 1983 and 1991,5 14 Reliance (WMEC-615) class ships that entered service between 1964 and 1969,6 and two one-of1 The earlier report was CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald O'Rourke. From the late 1990s until 2007, the Coast Guard’s efforts to acquire NSCs, OPCs, and FRCs were parts of a larger, integrated Coast Guard acquisition effort aimed at acquiring several new types of cutters and aircraft that was called the Integrated Deepwater System (IDS) program, or Deepwater for short. In 2007, the Coast Guard broke up the Deepwater effort into a series of individual cutter and aircraft acquisition programs, but continued to use the term Deepwater as a shorthand way of referring collectively to these now-separated programs. In its FY2012 budget submission, the Coast Guard stopped using the term Deepwater entirely as a way of referring to these programs. Congress, in acting on the Coast Guard’s proposed FY2012 budget, did not object to ending the use of the term Deepwater. Reflecting this development, CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald O'Rourke, was archived in early 2012, following final congressional action on the FY2012 budget, and remains available to congressional readers as a source of historical reference information on Deepwater acquisition efforts. 2 CRS Report RL34391, Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress, by Ronald O'Rourke. 3 In the designations WHEC, WMEC, and WPB, W means Coast Guard ship, HEC stands for high-endurance cutter, MEC stands for medium-endurance cutter, and PB stands for patrol boat. 4 Hamilton-class cutters are 378 feet long and have a full load displacement of about 3,400 tons. 5 Famous class cutters are 270 feet long and have a full load displacement of about 1,800 tons. 6 Reliance class cutters are 210 feet long and have a full load displacement of about 1,100 tons. Congressional Research Service 1 Coast Guard Cutter Procurement: Background and Issues for Congress a-kind cutters that originally entered service with the Navy in 1944 and 1971 and were later transferred to the Coast Guard.7 The Coast Guard’s 49 110-foot Island (WPB-1301) class patrol boats entered service between 1986 and 1992.8 Many of these 90 ships are manpower-intensive and increasingly expensive to maintain, and have features that in some cases are not optimal for performing their assigned missions. Some of them have already been removed from Coast Guard service: eight of the Island-class patrol boats were removed from service in 2007 following an unsuccessful effort to modernize and lengthen them to 123 feet; the one-of-a-kind cutter that originally entered service with the Navy in 1944 was decommissioned in 2011; and Hamilton-class cutters are being decommissioned as new NSCs enter service. A July 2012 Government Accountability Office (GAO) report discusses the generally poor physical condition and declining operational capacity of the Coast Guard’s older high-endurance cutters, medium-endurance cutters, and 110-foot patrol craft.9 Missions of NSCs, OPCs, and FRCs NSCs, OPCs, and FRCs, like the ships they are intended to replace, are to be multimission ships for routinely performing 7 of the Coast Guard’s 11 statutory missions, including        search and rescue (SAR); drug interdiction; migrant interdiction; ports, waterways, and coastal security (PWCS); protection of living marine resources; other/general law enforcement; and defense readiness operations.10 Smaller Coast Guard patrol craft and boats contribute to the performance of some of these seven missions close to shore. NSCs, OPCs, and FRCs perform them both close to shore and in the deepwater environment, which generally refers to waters more than 50 miles from shore. 7 The two one-of-a-kind cutters are the Acushnet (WMEC-167), which originally entered service with the Navy in 1944, and the Alex Haley (WMEC-39), which originally entered service with the Navy in 1971. The Acushnet served in the Navy from until 1946, when it was transferred to the Coast Guard. The ship was about 214 feet long and had a displacement of about 1,700 tons. The Alex Haley served in the Navy until 1996. It was transferred to the Coast Guard in 1997, converted into a cutter, and re-entered service with the Coast Guard in 1999. It is 282 feet long and has a full load displacement of about 2,900 tons. 8 Island-class boats are 110 feet long and have a full load displacement of about 135 to 170 tons. 9 Government Accountability Office, Coast Guard[:]Legacy Vessels’ Declining Conditions Reinforce Need for More Realistic Operational Targets, GAO-12-741, July 2012, 71 pp. 10 The four statutory Coast Guard missions that are not to be routinely performed by NSCs, OPCs, and FRCs are marine safety, aids to navigation, marine environmental protection, and ice operations. These missions are performed primarily by other Coast Guard ships. The Coast Guard states, however, that “while [NSCs, OPCs, and FRCs] will not routinely conduct [the] Aids to Navigation, Marine Safety, or Marine Environmental Protection missions, they may periodically be called upon to support these missions (i.e., validate the position of an Aid to Navigation, transport personnel or serve as a Command and Control platform for a Marine Safety or Marine Environmental Response mission, etc.).” (Source: Coast Guard information paper provided to CRS on June 1, 2012.) Congressional Research Service 2 Coast Guard Cutter Procurement: Background and Issues for Congress NSC Program issues for Congress, including the following:
  • whether to fund the acquisition of a 10th NSC in FY2017;
  • whether to fund the acquisition of four FRCs in FY2017, as requested, or some other number, such as six, which was the number projected for FY2017 under the Coast Guard's FY2016 budget submission;
  • whether to use annual or multiyear contracting for procuring FRCs;
  • whether to use annual or multiyear contracting for procuring OPCs;
  • planned procurement quantities for NSCs, OPCS, and FRCs;
  • the cost, design, and acquisition strategy for the OPC;
  • initial testing of the NSC; and
  • rotational crewing of the NSC.

Congress's decisions on these programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base.

Coast Guard Cutter Procurement: Background and Issues for Congress

Introduction

This report provides background information and potential oversight issues for Congress on the Coast Guard's programs for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs). These 91 planned cutters are intended as replacements for 90 aging Coast Guard cutters and patrol craft. The Coast Guard's proposed FY2017 budget requests a total of $467 million in acquisition funding for the three programs.

The issue for Congress is whether to approve, reject, or modify the Coast Guard's funding requests and acquisition strategies for the NSC, OPC, and FRC programs. Congress's decisions on these three programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base.

The NSC, OPC, and FRC programs have been subjects of congressional oversight for several years, and were previously covered in an earlier CRS report that is now archived.1 CRS testified on the Coast Guard's cutter acquisition programs on February 3, 2016.2 The Coast Guard's plans for modernizing its fleet of polar icebreakers are covered in a separate CRS report.3

Background Older Ships to Be Replaced by NSCs, OPCs, and FRCs

The 91 planned NSCs, OPCs, and FRCs are intended to replace 90 older Coast Guard ships—12 high-endurance cutters (WHECs), 29 medium-endurance cutters (WMECs), and 49 110-foot patrol craft (WPBs).4 The Coast Guard's 12 Hamilton (WHEC-715) class high-endurance cutters entered service between 1967 and 1972.5 The Coast Guard's 29 medium-endurance cutters include 13 Famous (WMEC-901) class ships that entered service between 1983 and 1991,6 14 Reliance (WMEC-615) class ships that entered service between 1964 and 1969,7 and two one-of-a-kind cutters that originally entered service with the Navy in 1944 and 1971 and were later transferred to the Coast Guard.8 The Coast Guard's 49 110-foot Island (WPB-1301) class patrol boats entered service between 1986 and 1992.9

Many of these 90 ships are manpower-intensive and increasingly expensive to maintain, and have features that in some cases are not optimal for performing their assigned missions. Some of them have already been removed from Coast Guard service: eight of the Island-class patrol boats were removed from service in 2007 following an unsuccessful effort to modernize and lengthen them to 123 feet; the one-of-a-kind cutter that originally entered service with the Navy in 1944 was decommissioned in 2011; and Hamilton-class cutters are being decommissioned as new NSCs enter service. A July 2012 Government Accountability Office (GAO) report discusses the generally poor physical condition and declining operational capacity of the Coast Guard's older high-endurance cutters, medium-endurance cutters, and 110-foot patrol craft.10

Missions of NSCs, OPCs, and FRCs

NSCs, OPCs, and FRCs, like the ships they are intended to replace, are to be multimission ships for routinely performing 7 of the Coast Guard's 11 statutory missions, including

  • search and rescue (SAR);
  • drug interdiction;
  • migrant interdiction;
  • ports, waterways, and coastal security (PWCS);
  • protection of living marine resources;
  • other/general law enforcement; and
  • defense readiness operations.11

Smaller Coast Guard patrol craft and boats contribute to the performance of some of these seven missions close to shore. NSCs, OPCs, and FRCs perform them both close to shore and in the deepwater environment, which generally refers to waters more than 50 miles from shore.

NSC Program
National Security Cutters (Figure 1), also known as Legend (WMSL-750) class cutters,1112 are the Coast Guard's largest and most capable general-purpose cutters.1213 The Coast Guard’s's acquisition program of record (POR)—the service's list, established in 2004, of planned procurement quantities for various new types of ships and aircraft—calls for procuring 8 NSCs as replacements for the service’ service's 12 Hamilton class high-endurance cutters. The Coast Guard's FY2016 five-year Capital Investment Plan (CIP) estimates the total acquisition cost of the eight ships at $5.559 billion, or an average of about $695 million per ship. Figure 1. National Security Cutter Source: U.S. Coast Guard photo accessed May 2, 2012, at http://www.flickr.com/photos/coast_guard/ 5617034780/sizes/l/l/in/set-72157629650794895/. . NSCs are larger and technologically more advanced than Hamilton-class cutters.1314 The Coast Guard states that Of the Coast Guard's white-hull patrol cutter fleet, the NSC is the largest and most technologically sophisticated in the Coast Guard. Each NSC is capable of operating in the most demanding open ocean environments, including the hazardous fisheries of the North 11 In the designation WMSL, W means Coast Guard ship and MSL stands for maritime security cutter, large. NSCs are being named for legendary Coast Guard personnel. 12 The Coast Guard’s three polar icebreakers are much larger than NSCs, but are designed for a more specialized role of operations in polar waters. 13 The NSC design is 418 feet long and has a full load displacement of about 4,500 tons. The displacement of the NSC design is about equal to that of Navy’s Oliver Hazard Perry (FFG-7) class frigates, which are 453 feet long and have a full load displacement of about 4,200 tons. Congressional Research Service 3 Coast Guard Cutter Procurement: Background and Issues for Congress Pacific and the vast approaches of the Southern Pacific where much of the American narcotics traffic occurs. With robust Command, Control, Communication, Computers, Intelligence, Surveillance and Reconnaissance (C4ISR) equipment, stern boat launch and aviation facilities, as well as long-endurance station keeping, the NSCs are afloat operational-level headquarters for complex law enforcement and national security missions involving multiple Coast Guard and partner agency participation. 14 15 NSCs are built by Ingalls Shipbuilding of Pascagoula, MS, a shipyard that forms part of Huntington Ingalls Industries (HII). The first five are now in service (the fifth was commissioned into service on August 8, 2015).15 16 The sixth, seventh, and eighth are under construction and scheduled for delivery in 2016, 2018, and 2019, respectively.1617 A ninth ship in the class, which was not requested by the Coast Guard, was funded in FY2016. ( The Coast Guard's proposed FY2016FY2017 budget requested $91.4requests $127 million in acquisition funding for the NSC program for structural enhancements on the first two NSCs and post-delivery activities on NSCs 5 through 8.) OPC Program post-delivery activities on NSCs 4 through 8 ($98.367 million), program close-out, follow-on test and evaluation, and program support ($22.633 million), and procurement of small unmanned aerial systems (sUASs) for NSCs ($6 million). OPC Program Offshore Patrol Cutters (Figure 2) are to be smaller, less expensive, and in some respects less capable than NSCs. The Coast Guard's POR calls for procuring 25 OPCs as replacements for the service’ service's 29 medium-endurance cutters. Under the Coast Guard’s FY2015 five-year CIP, it appears (based on programmed annual funding levels) that theThe first OPC is to be procured in FY2018. The FY2016 CIP estimates the total acquisition cost of the 25 ships at $10.523 billion, or an average of about $421 million per ship. The Coast Guard’ Coast Guard officials have described the OPC program as the service's top acquisition priority.

The service states that OPCs

will complement the Coast Guard's current and future fleet to extend the service's operational capabilities. The OPC will replace the service's 210-foot and 270-foot Medium Endurance Cutters. It will feature increased range and endurance, powerful weapons, a larger flight deck, and improved command, control, communications, computers, intelligence, surveillance and reconnaissance (C4ISR) equipment. The OPC will accommodate aircraft and small boat operations in all weather.18

The Coast Guard'
s Request for Proposal (RFP) for the program, released on September 25, 2012, establishes an affordability requirement for the program of an average unit price of $310 million per ship, or less, in then-year dollars (i.e., dollars that are not adjusted for inflation) for ships 4 through 9 in the program.1719 This figure represents the shipbuilder's portion of the total cost of the ship; it does not include the cost of government-furnished equipment (GFE) on the ship,18 or 20 or other program costs—such as those for program management, system integration, and logistics— that contribute to the above-cited figure of $421 million per ship.19 14 U.S. Coast Guard description of the NSC, accessed April 26, 2013, at http://www.uscg.mil/acquisition/nsc/ features.asp. 15 “Acquisition Update: Coast Guard Commissions Fifth National Security Cutter,” August 10, 2015, accessed September 24, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/nsc081015.asp. 16 “Acquisition Update: Sixth National Security Cutter Launched,” September 15, 2015, accessed September 24, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/nsc091515.asp. See also “Acquisition Update: Coast Guard Christens Sixth National Security Cutter,” November 16, 2015, accessed January 27, 2016, at http://www.uscg.mil/acquisition/newsroom/updates/nsc111615.asp. 17 Source: Section C.5 of the RFP, accessed October 31, 2012, at http://www.uscg.mil/ACQUISITION/newsroom/ updates/opc092512.asp. 18 GFE is equipment that the government procures and then delivers to the shipyard for installation on the ship. 19 Source: Coast Guard emails to CRS dated June 25, 2013. Congressional Research Service 4 Coast Guard Cutter Procurement: Background and Issues for Congress that contribute to the above-cited figure of $421 million per ship.21 Figure 2. Offshore Patrol Cutter (Generic Conceptual Rendering) Source: U.S. Coast Guard generic conceptual rendering accessed May 3, 2012, at http://www.uscg.mil/hq/cg9/ opc/default.asp. The Coast Guard'default.asp. The service states that OPCs will complement the Coast Guard’s current and future fleet to extend the service’s operational capabilities. The OPC will replace the service’s 210-foot and 270-foot Medium Endurance Cutters. It will feature increased range and endurance, powerful weapons, a larger flight deck, and improved command, control, communications, computers, intelligence, surveillance and reconnaissance (C4ISR) equipment. The OPC will accommodate aircraft and small boat operations in all weather.20 The Coast Guard’s acquisition strategy for the first 9 to 11 ships in the program is as follows: The OPC procurement shall implement a two-phase down select strategy. Phase I entails a full and open competition for Preliminary and Contract Design (P&CD) awarded to a maximum of three offerors. The Coast Guard intends to competitively award the Phase I contract in Fiscal Year (FY) 2013. P&CD will culminate in a Contract Design Review (KDR). After KDR, the three contractors will submit proposals which will result in a down selection to one contractor to continue with Phase II. (h) (h)Phase II award is planned for FY16.... Phase II's down selection will be accomplished by exercising one option with a single contractor for Detail Design (DD) with additional options for Long Lead Time Materials, lead ship and eight to ten follow ships. DD will start after option exercise and be complete upon delivery of the first ship. The contractor will present the OPC design at the Initial Critical Design Reviews (ICDR) and Final Critical Design Review (FCDR) followed by a Production Readiness Review (PRR). During Phase II contract performance, the contractor will be encouraged to submit a fixed price proposal (before construction begins on the Hull #6) for option Hulls 20 Coast Guard fact sheet on the OPC accessed April 26, 2013, at http://www.uscg.mil/acquisition/opc/pdf/opc.pdf. Congressional Research Service 5 Coast Guard Cutter Procurement: Background and Issues for Congress #6 through #11 (LRIP 2). If the priced effort is deemed fair and reasonable the contractor shall be eligible for Hulls #10 and #11. If not, the contract will continue with the FPI structure and the contract will end with Hull #9.21 22 At least eight shipyards expressed interest in the OPC program.23 On February 11, 2014, the Coast Guard announced that it had awarded Phase I Preliminary and Contract Design (P&CD) contracts to three of those eight firms—Bollinger Shipyards of Lockport, LA; Eastern Shipbuilding Group of Panama City, FL; and General Dynamics' Bath Iron Works (GD/BIW) of Bath, ME. A February 11, 2014, Coast Guard news release on the award stated: program. The firms were the following:         Bollinger Shipyards of Lockport, LA; Eastern Shipbuilding Group of Panama City, FL; General Dynamics Bath Iron Works (GD/BIW) of Bath, ME; Huntington Ingalls Industries (HII) of Pascagoula, MS; Marinette Marine Corporation of Marinette, WS; General Dynamics National Steel and Shipbuilding Company (GD/NASSCO) of San Diego, CA; Vigor Shipyards of Seattle, WA; and VT Halter Marine of Pascagoula, MS.22 On February 11, 2014, the Coast Guard announced that it had awarded Phase I Preliminary and Contract Design (P&CD) contracts to Bollinger, Eastern, and GD/BIW. A February 11, 2014, Coast Guard news release on the award stated: The U.S. Coast Guard today awarded three firm fixed-price contracts for preliminary and contract design (P&CD) for the Offshore Patrol Cutter (OPC) acquisition project. The contracts were awarded to Bollinger Shipyards Lockport LLC (Lockport, La.), Eastern Shipbuilding Group Inc. (Panama City, Fla.), and General Dynamics, Bath Iron Works (Bath, Maine). The total value of the award is approximately $65 million. Awarding multiple design contracts ensures that competition is continued through to a potential down-select for detailed design and construction, establishes a fixed-price environment for the remainder of the contract, and incorporates a strategy to maximize affordability. This strategy was developed by analyzing lessons learned from other major government shipbuilding programs and through collaboration with industry on how to best design and produce the most affordable OPC.... The Coast Guard issued the P&CD Request for Proposal (RFP) Sept. 25, 2012. Responses were received in January 2013, and the Coast Guard conducted a thorough evaluation of proposals based on technical, management, past performance and price factors. To support the effort to acquire an affordable OPC, the Coast Guard engaged industry prior to RFP release through industry day events, one-on-one meetings and providing opportunities for potential offerors to review and comment on OPC draft technical packages, specifications and solicitation language. 23 21 Source: Section C.1 of the RFP, accessed March 26, 2013, at http://www.uscg.mil/ACQUISITION/newsroom/ updates/opc092512.asp. 22 Source: U. S. Coast Guard Offshore Patrol Cutter (OPC) List of Interested Contractors Updated July 2012, accessed online October 23, 2012, at http://www.uscg.mil/ACQUISITION/opc/pdf/companiesinterested.pdf; and Kevin Brancato and Anne Laurent, Coast Guard’s $12 Billion Cutter Competition Spurs Eight Shipyards to Dive In, Bloomberg Government Study, November 8, 2012, 6 pp. The Coast Guard document states that these firms “expressed interest in the Offshore Patrol Cutter acquisition and have agreed to their names provided on the Coast Guard website.” See also Stew Magnuson, “New Coast Guard Cutter Sparks Fierce Competition Among Shipbuilders,” National Defense (www.nationaldefensemagazine.org), April 2013, accessed March 26, 2013, at http://www.nationaldefensemagazine.org/archive/2013/April/Pages/ NewCoastGuardCutterSparksFierceCompetitionAmongShipbuilders.aspx. 23 “Acquisition Update: U.S. Coast Guard Awards Three Contracts for Offshore Patrol Cutter Preliminary and Contract (continued...) Congressional Research Service 6 Coast Guard Cutter Procurement: Background and Issues for Congress HII and VT Halter Marine reportedly filed protests of the Coast Guard’s award decision on February 24 and 25, respectively. The Coast Guard issued stop work orders to Bollinger, Eastern, and GD/BIW pending GAO’s rulings on the protests.24 On June 5, 2014, it was reported that GAO had rejected the protests, and that the Coast Guard had directed Bollinger, Eastern, and GD/BIW to resume their work.25 technical packages, specifications and solicitation language.24 The Coast Guard states that it plans to award the Phase 2 contract (i.e., select a winner from among the three competing firms) by the end of fiscal year 2016.26 The Coast Guard’s proposed FY2016 budget requested $18.5 million in acquisition funding for the OPC program for technical and project management ($4.7 million) and design and development work ($13.8 million). The Coast Guard stated, “The Administration’s [FY2016 budget] request includes a [proposed legislative] General Provision permitting a transfer [of additional funding] to the OPC project if the program is ready to award the next phase of vessel acquisition in FY 2016.”27 GAO testified on May 14, 2015, that The Coast Guard currently plans to begin construction on the lead ship in fiscal year 2018—one year later than planned in its most recent program baseline—and deliver this ship in 2022. The Coast Guard attributes the schedule delay to procurement delays, including a bid protest. The fiscal year 2016 Capital Investment Plan has $1.5 billion in funding for the OPC, which funds the design work and construction of the first three vessels. After the first 3 of the planned fleet of 25 OPCs are built, the Coast Guard plans to increase its purchase to 2 OPCs per year until the final asset is delivered, currently scheduled for fiscal year 2035.28 FRC Program 2016.25

Section 223 of the Howard Coble Coast Guard and Maritime Transportation Act of 2014 (S. 2444/P.L. 113-281 of December 18, 2014) states:

SEC. 223. MULTIYEAR PROCUREMENT AUTHORITY FOR OFFSHORE PATROL CUTTERS.

In fiscal year 2015 and each fiscal year thereafter, the Secretary of the department in which the Coast Guard is operating may enter into, in accordance with section 2306b of title 10, United States Code, multiyear contracts for the procurement of Offshore Patrol Cutters and associated equipment.

The Coast Guard's proposed FY2017 budget requests $100 million in acquisition funding for the OPC program for technical and project management ($28.5 million) and procurement of long lead time material (LLTM) for the first ship ($71.5 million).

FRC Program
Fast Response Cutters (Figure 3), also called Sentinel (WPC-1101) class patrol boats, are considerably smaller and less expensive than OPCs, but are larger than the Coast Guard's older patrol boats.2926 The Coast Guard's POR calls for procuring 58 FRCs as replacements for the service’ service's 49 Island-class patrol boats. The FY2016 CIP estimates the total acquisition cost of the 58 cutters at $3.764 billion, or an average of about $65 million per cutter. (...continued) Design,” February 11, 2014, accessed February 14, 2014, at http://www.uscg.mil/hq/cg9/newsroom/updates/ opc021114.asp. 24 Calvin Biesecker, “Coast Guard Issues Stop Work Orders On OPC Following Protests,” Defense Daily, February 28, 2014: 2-3. See also Christopher P. Cavas, “Ingalls Protesting US Coast Guard Cutter Contract,” DefenseNews.com, February 26, 2014. 25 Calvin Biesecker, “Coast Guard Directs Design Work Continue On OPC After GAO Denies Protests,” Defense Daily, June 5, 2014: 1; Christopher P. Cavas, “US Coast Guard Cutter Award Upheld,” Defense News (www.defensenews.com), June 5, 2014. For the text of the decision, see Government Accountability Office, Decision in the Matter of Huntington Ingalls Industries, Inc.; VT Halter Marine, Inc., June 2, 2014. 26 “Offshore Patrol Cutter,” last modified May 27, 2015, accessed September 24, 2015, at http://www.uscg.mil/ acquisition/opc/default.asp. 27 Department of Homeland Security, United States Coast Guard, Fiscal Year 2016 Congressional Justification, p. CGAC&I-30. 28 Government Accountability Office, Coast Guard Acquisitions[:] As Major Assets Are Fielded, Overall Portfolio Remains Unaffordable, GAO-15-620T, May 14, 2015, p. 9. 29 FRCs are 154 feet long and have a full load displacement of 353 tons. Congressional Research Service 7 Coast Guard Cutter Procurement: Background and Issues for Congress Figure 3. Fast Response Cutter (With an older Island-class patrol boat behind) Source: U.S. Coast Guard photo accessed May 4, 2012, at http://www.flickr.com/photos/coast_guard/ 6871815460/sizes/l/in/set-72157629286167596/. 58 cutters at $3.764 billion, or an average of about $65 million per cutter. The Coast Guard states that The planned fleet of FRCs will conduct primarily the same missions as the 110' patrol boats being replaced. In addition, the FRC will have several increased capabilities enhancing overall mission execution. The FRC is designed for rapid response, with approximately a 28 knot speed capability, and will typically operate in the coastal zones. Examples of missions that FRCs will complete include SAR, Migrant Interdiction, Drug Interdiction and Ports Waterways and Coastal Security. FRCs will provide enhanced capabilities over the 110's including improved C4ISR capability and interoperability; stern launch and recovery (up through sea state 4) of a 40 knot, Over-the-Horizon, 7m cutter boat; a remote operated, gyro stabilized MK38 Mod 2, 25mm main gun; improved sea keeping; and enhanced crew habitability. 30 27 The FRC program received approval from DHS to enter full-rate production on September 18, 2013.3128 A total of 38 FRCs have been funded through FY2016. The 14th16th was commissioned into service on October 16, 2015.32 The 15th and 16th were accepted by the Coast Guard on October 20 30 Department of Homeland Security, United States Coast Guard, Fiscal Year 2013 Congressional Justification, p. CGAC&I-28 (pdf page 182 of 400). 31 “Acquisition Update: Sentinel-class Fast Response Cutter Project Achieves Acquisition Milestone,” September 18, 2013, accessed November 18, 2013, at http://www.uscg.mil/acquisition/newsroom/updates/frc092413.asp. 32 “Acquisition Update: Coast Guard Commissions 14th Fast Response Cutter,” October 19, 2015, accessed November 17, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/frc101915.asp. Congressional Research Service 8 Coast Guard Cutter Procurement: Background and Issues for Congress and December 23, 2015, and are scheduled for commissioning in January and March 2016, respectively.33 service on March 11, 2016.29 Figure 3. Fast Response Cutter

(With an older Island-class patrol boat behind)

Source: U.S. Coast Guard photo accessed May 4, 2012, at http://www.flickr.com/photos/coast_guard/6871815460/sizes/l/in/set-72157629286167596/.
FRCs are currently built by Bollinger Shipyards of Lockport, LA. Bollinger's contract with the Coast Guard originally included annual options for building a total of up to 34 FRCs through FY2014, but some of the annual options were not exercised by the Coast Guard to their maximum possible quantities, and Bollinger's contract wound up covering the 32 FRCs. (The Coast Guard on February 27, 2015, exercised a final option under the contract with Bollinger for ships 31 and 32.)3430 Ship awards under that contract are now completed. The Coast Guard holds the data rights for the Sentinel-class design and on February 27, 2015, issued a Request for Proposals (RFP) for a contract that will include options for the acquisition of up to 26 FRCs (i.e., the remaining 26 ships in the program). Proposals from bidders were due by June 5, 2015.35 31 The Coast Guard's proposed FY2016FY2017 budget requested $340requests $240 million in acquisition funding for the FRC program. NSC, OPC, and FRC for the procurement of four more FRCs. Funding in FY2013-FY2016 Budget Submissions FY2017 Budget Submissions Table 1 shows annual acquisition funding for the NSC, OPC, and FRC programs in the Coast Guard’ Guard's FY2013-FY2016 budget submissions. 33 “Acquisition Update: 15th Fast Response Cutter Delivered To Coast Guard,” October 21, 2015, accessed November 17, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/frc102115.asp; and “Acquisition Update: Sixteenth FRC Delivered To Coast Guard,” December 24, 2015, accessed January 27, 2016, at http://www.uscg.mil/acquisition/newsroom/updates/frc122315.asp. 34 “Acquisition Update: Coast Guard Exercises Contract Option for Fast Response Cutters 31 And 32,” February 27, 2015, accessed March 6, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/frc022815.asp. 35 “Acquisition Update: Coast Guard Issues Request for Proposal for Fast Response Cutters 33-58,” February 27, 2015, accessed March 6, 2015, http://www.uscg.mil/acquisition/newsroom/updates/frc022915.asp. Congressional Research Service 9 Coast Guard Cutter Procurement: Background and Issues for Congress FY2017 budget submissions. Table 1. NSC, OPC, and FRC Funding in FY2013-FY2016FY2017 Budget Submissions (millions of then-year dollars) NSC program FY13 budget FY14 budget FY15 budget FY16 budget OPC program FY13 budget FY14 budget FY15 budget FY16 budget FRC program FY13 budget FY14 budget FY15 budget FY16 budget Total FY13 budget FY14 budget FY15 budget FY16 budget FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020 683 0 616 0 710 638 0 38 75 91.4 0 0 130 132 45 30 95 47 30 15 200 200 90 18.5 530 530 100 100 430 530 530 430 430 430 360 110 340 340 360 110 220 325 110 220 240 315 240 325 560 348 505 449.9 890 640 450 557 585 780 865 792 700 370 30 139 852 50 25 360 75 410 716 40 65 20 360 110 110 400 885 768 Source: FY2013-FY2016 budget submissions. Issues for Congress Planned NSC, OPC, and FRC Procurement Quantities One potential oversight issue for Congress concerns the Coast Guard’s planned NSC, OPC, and FRC procurement quantities. The POR’s planned force of 91 NSCs, OPCs, and FRCs is about equal in number to the Coast Guard’s legacy force of 90 high-endurance cutters, mediumendurance cutters, and 110-foot patrol craft. NSCs, OPCs, and FRCs, moreover, are to be individually more capable than the older ships they are to replace. Even so, Coast Guard studies have concluded that the planned total of 91 NSCs, OPCs, and FRCs would be considerably fewer ships than the number that would be needed to fully perform the service’s statutory missions in coming years, in part because Coast Guard mission demands are expected to be greater in coming years than they were in the past. CRS first testified about this issue in 2005.36 The Coast Guard estimates that with the POR’s planned force of 91 NSCs, OPCs, and FRCs, the service would have capability or capacity gaps37 in 6 of its 11 statutory missions—search and rescue (SAR); defense readiness; counter-drug operations; ports, waterways, and coastal security (PWCS); protection of living marine resources (LMR); and alien migrant interdiction operations 36 See Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the Senate Commerce, Science, and Transportation Committee, Subcommittee on Fisheries and the Coast Guard, Hearing on The Coast Guard’s Revised Deepwater Implementation Plan, June 21, 2005, pp. 1-5. 37 The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed. Congressional Research Service 10 Coast Guard Cutter Procurement: Background and Issues for Congress (AMIO). The Coast Guard judges that some of these gaps would be “high risk” or “very high risk.” Public discussions of the POR frequently mention the substantial improvement that the POR force would represent over the legacy force. Only rarely, however, have these discussions explicitly acknowledged the extent to which the POR force would nevertheless be smaller in number than the force that would be required, by Coast Guard estimate, to fully perform the Coast Guard’s statutory missions in coming years. Discussions that focus on the POR’s improvement over the legacy force while omitting mention of the considerably larger number of cutters that would be required, by Coast Guard estimate, to fully perform the Coast Guard’s statutory missions in coming years could encourage audiences to conclude, contrary to Coast Guard estimates, that the POR’s planned force of 91 cutters would be capable of fully performing the Coast Guard’s statutory missions in coming years. In a study completed in December 2009 called the Fleet Mix Analysis (FMA) Phase 1, the Coast Guard calculated the size of the force that in its view would be needed to fully perform the service’s statutory missions in coming years. The study refers to this larger force as the objective fleet mix. Table 2 compares planned numbers of NSCs, OPCs, and FRCs in the POR to those in the objective fleet mix. Table 2. Program of Record Compared to Objective Fleet Mix From Fleet Mix Analysis Phase 1 (2009) Ship type Program of Record (POR) Objective Fleet Mix compared to POR Objective Fleet Mix From FMA Phase 1 Number % NSC 8 9 +1 +13% OPC 25 57 +32 +128% FRC 58 91 +33 +57% Total 91 157 +66 +73% Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13. As can be seen in Table 2, the objective fleet mix includes 66 additional cutters, or about 73% more cutters than in the POR. Stated the other way around, the POR includes about 58% as many cutters as the objective fleet mix. As intermediate steps between the POR force and the objective fleet mix, FMA Phase 1 calculated three additional forces, called FMA-1, FMA-2, and FMA-3. (The objective fleet mix was then relabeled FMA-4.) Table 3 compares the POR to FMAs 1 through 4. Congressional Research Service 11 Coast Guard Cutter Procurement: Background and Issues for Congress Table 3. POR Compared to FMAs 1 Through 4 From Fleet Mix Analysis Phase 1 (2009) Ship type Program of Record (POR) FMA-1 FMA-2 FMA-3 FMA-4 (Objective Fleet Mix) NSC 8 9 9 9 9 OPC 25 32 43 50 57 FRC 58 63 75 80 91 Total 91 104 127 139 157 Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13. FMA-1 was calculated to address the mission gaps that the Coast Guard judged to be “very high risk.” FMA-2 was calculated to address both those gaps and additional gaps that the Coast Guard judged to be “high risk.” FMA-3 was calculated to address all those gaps, plus gaps that the Coast Guard judged to be “medium risk.” FMA-4—the objective fleet mix—was calculated to address all the foregoing gaps, plus the remaining gaps, which the Coast Guard judge to be “low risk” or “very low risk.” Table 4 shows the POR and FMAs 1 through 4 in terms of their mission performance gaps. Table 4. Force Mixes and Mission Performance Gaps From Fleet Mix Analysis Phase 1 (2009)—an X mark indicates a mission performance gap Risk levels of these performance gaps Program of Record (POR) Search and Rescue (SAR) capability Very high X Defense Readiness capacity Very high X Counter Drug capacity Very high X Ports, Waterways, and Coastal Security (PWCS) capacitya High X X Living Marine Resources (LMR) capability and capacitya High X X PWCS capacityb Medium X X X LMR capacityc Medium X X X Alien Migrant Interdiction Operations (AMIO) capacityd Low/very low X X X X PWCS capacitye Low/very low X X X X Missions with performance gaps FMA-1 FMA-2 FMA-3 FMA-4 (Objective Fleet Mix) [all gaps addressed] Source: Fleet Mix Analysis Phase 1, Executive Summary, page ES-11 through ES-13. Notes: In the first column, The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed. a. This gap occurs in the Southeast operating area (Coast Guard Districts 7 and 8) and the Western operating area (Districts 11, 13, and 14). b. This gap occurs in Alaska. c. This gap occurs in Alaska and in the Northeast operating area (Districts 1 and 5). Congressional Research Service 12 Coast Guard Cutter Procurement: Background and Issues for Congress d. e. This gap occurs in the Southeast and Western operating areas. This gap occurs in the Northeast operating area. Figure 4, taken from FMA Phase 1, depicts the overall mission capability/performance gap situation in graphic form. It appears to be conceptual rather than drawn to precise scale. The black line descending toward 0 by the year 2027 shows the declining capability and performance of the Coast Guard’s legacy assets as they gradually age out of the force. The purple line branching up from the black line shows the added capability from ships and aircraft to be procured under the POR, including the 91 planned NSCs, OPCs, and FRCs. The level of capability to be provided when the POR force is fully in place is the green line, labeled “2005 Mission Needs Statement.” As can be seen in the graph, this level of capability is substantially below a projection of Coast Guard mission demands made after the terrorist attacks of September 11, 2001 (the red line, labeled “Post-9/11 CG Mission Demands”), and even further below a Coast Guard projection of future mission demands (the top dashed line, labeled “Future Mission Demands”). The dashed blue lines show future capability levels that would result from reducing planned procurement quantities in the POR or executing the POR over a longer time period than originally planned. Figure 4. Projected Mission Demands vs. Projected Capability/Performance From Fleet Mix Analysis Phase 1, Executive Summary Source: Fleet Mix Analysis Phase 1, Executive Summary, Figure ES-1 on p. ES-2. FMA Phase 1 was a fiscally unconstrained study, meaning that the larger force mixes shown in Table 3 were calculated primarily on the basis of their capability for performing missions, rather than their potential acquisition or life-cycle operation and support (O&S) costs. Although the FMA Phase 1 was completed in December 2009, the figures shown in Table 3 were generally not included in public discussions of the Coast Guard’s future force structure needs Congressional Research Service 13 Coast Guard Cutter Procurement: Background and Issues for Congress until April 2011, when GAO presented them in testimony.38 GAO again presented them in a July 2011 report.39 The Coast Guard completed a follow-on study, called Fleet Mix Analysis (FMA) Phase 2, in May 2011. Among other things, FMA Phase 2 includes a revised and updated objective fleet mix called the refined objective mix. Table 5 compares the POR to the objective fleet mix from FMA Phase 1 and the refined objective mix from FMA Phase 2. Table 5. POR Compared to Objective Mixes in FMA Phases 1 and 2 From Fleet Mix Analysis Phase 1 (2009) and Phase 2 (2011) Ship type Program of Record (POR) Objective Fleet Mix from FMA Phase 1 Refined Objective Mix from FMA Phase 2 NSC 8 9 9 OPC 25 57 49 FRC 58 91 91 Total 91 157 149 Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13, and Fleet Mix Analysis Phase 2, Table ES-2 on p. iv. As can be seen in Table 5, compared to the objective fleet mix from FMA Phase 1, the refined objective mix from FMA Phase 2 includes 49 OPCs rather than 57. The refined objective mix includes 58 additional cutters, or about 64% more cutters than in the POR. Stated the other way around, the POR includes about 61% as many cutters as the refined objective mix. Compared to the POR, the larger force mixes shown in Table 3 and Table 5 would be more expensive to procure, operate, and support than the POR force. Using the average NSC, OPC, and FRC procurement cost figures presented earlier (see “Background”), procuring the 58 additional cutters in the Refined Objective Mix from FMA Phase 2 might cost an additional $10.7 billion, of which most (about $7.8 billion) would be for the 24 additional FRCs. (The actual cost would depend on numerous factors, such as annual procurement rates.) O&S costs for these 58 additional cutters over their life cycles (including crew costs and periodic ship maintenance costs) would require billions of additional dollars.40 The larger force mixes in the FMA Phase 1 and 2 studies, moreover, include not only increased numbers of cutters, but also increased numbers of Coast Guard aircraft. In the FMA Phase 1 study, for example, the objective fleet mix included 479 aircraft—93% more than the 248 aircraft in the POR mix. Stated the other way around, the POR includes about 52% as many aircraft as the objective fleet mix. A decision to procure larger numbers of cutters like those shown in Table 3 38 Government Accountability Office, Coast Guard[:]Observations on Acquisition Management and Efforts to Reassess the Deepwater Program, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of John P. Hutton, Director Acquisition and Sourcing Management, GAO-11-535T, April 13, 2011, p. 10. 39 Government Accountability Office, Coast Guard[:]Action Needed As Approved Deepwater Program Remains Unachievable, GAO-11-743, July 2011, p. 46. 40 The FMA Phase 1 and Phase 2 studies present acquisition and life-cycle ownership cost calculations for force mixes that include not only larger numbers of NSC, OPCs, and FRCs, but corresponding larger numbers of Coast Guard aircraft. Congressional Research Service 14 Coast Guard Cutter Procurement: Background and Issues for Congress and Table 5 might thus also imply a decision to procure, operate, and support larger numbers of Coast Guard aircraft, which would require billions of additional dollars. The FMA Phase 1 study estimated the procurement cost of the objective fleet mix of 157 cutters and 479 aircraft at $61 billion to $67 billion in constant FY2009 dollars, or about 66% more than the procurement cost of $37 billion to $40 billion in constant FY2009 dollars estimated for the POR mix of 91 cutters and 248 aircraft. The study estimated the total ownership cost (i.e., procurement plus life-cycle O&S cost) of the objective fleet mix of cutters and aircraft at $201 billion to $208 billion in constant FY2009 dollars, or about 53% more than the total ownership cost of $132 billion to $136 billion in constant FY2009 dollars estimated for POR mix of cutters and aircraft.41 A December 7, 2015, press report states: The Coast Guard’s No. 2 officer said the small size and advanced age of its fleet is limiting the service’s ability to carry out crucial missions in the Arctic and drug transit zones or to meet rising calls for presence in the volatile South China Sea. “The lack of surface vessels every day just breaks my heart,” VADM Charles Michel, the Coast Guard’s vice commandant, said Dec. 7. Addressing a forum on American Sea Power sponsored by the U.S. Naval Institute at the Newseum, Michel detailed the problems the Coast Guard faces in trying to carry out its missions of national security, law enforcement and maritime safety because of a lack of resources. “That’s why you hear me clamoring for recapitalization,” he said. Michel noted that China’s coast guard has a lot more ships than the U.S. Coast Guard has, including many that are larger than the biggest U.S. cutter, the 1,800-ton [sic:4,800ton] National Security Cutter. China is using those white-painted vessels rather than “gray-hull navy” ships to enforce its claims to vast areas of the South China Sea, including reefs and shoals claimed by other nations, he said. That is a statement that the disputed areas are “so much our territory, we don’t need the navy. That’s an absolutely masterful use of the coast guard,” he said. The superior numbers of Chinese coast guard vessels and its plans to build more is something, “we have to consider when looking at what we can do in the South China Sea,” Michel said. Although they have received requests from the U.S. commanders in the region for U.S. Coast Guard cutters in the South China Sea, “the commandant had to say ‘no’. There’s not enough to go around,” he said.42 Potential oversight questions for Congress include the following:   Under the POR force mix, how large a performance gap, precisely, would there be in each of the missions shown in Table 4? What impact would these performance gaps have on public safety, national security, and protection of living marine resources? How sensitive are these performance gaps to the way in which the Coast Guard translates its statutory missions into more precise statements of required mission performance? 41 Fleet Mix Analysis Phase 1, Executive Summary, Table ES-11 on page ES-19, and Table ES-10 on page ES-18. The life-cycle O&S cost was calculated through 2050. 42 Otto Kreisher, “’Not Enough’ USCG Vessels to Meet Demand for Presence in South China Sea, Arctic,” Seapower, December 7, 2015. Congressional Research Service 15 Coast Guard Cutter Procurement: Background and Issues for Congress    Given the performance gaps shown in Table 4, should planned numbers of Coast Guard cutters and aircraft be increased, or should the Coast Guard’s statutory missions be reduced, or both? How much larger would the performance gaps in Table 4 be if planned numbers of Coast Guard cutters and aircraft are reduced below the POR figures? Has the executive branch made sufficiently clear to Congress the difference between the number of ships and aircraft in the POR force and the number that would be needed to fully perform the Coast Guard’s statutory missions in coming years? Why has public discussion of the POR focused mostly on the capability improvement it would produce over the legacy force and rarely on the performance gaps it would have in the missions shown in Table 4? Funding Level of Coast Guard’s Acquisition Account Another potential oversight issue for Congress concerns the funding level in the Coast Guard’s acquisition account, known formally as the Acquisition, Construction, and Improvements (AC&I) account. The Coast Guard has testified that acquiring the ships and aircraft in its POR on a timely basis while also adequately funding other Coast Guard acquisition programs would require a funding level for the AC&I account of roughly $1.5 billion to $2.5 billion per year. As shown in Table 6 below, the Administration’s FY2013 budget submission programmed an average of about $1.5 billion per year in the AC&I account. As also shown in the table, subsequent budget submissions have reduced that figure to between $1 billion and $1.2 billion per year. Table 6. Funding in AC&I Account in FY2013-FY2016 Budgets Millions of dollars, rounded to nearest tenth FY13 budget FY13 FY14 FY15 FY16 FY17 1,217.3 1,429.5 1,619.9 1,643.8 1,722.0 951.1 1,195.7 901.0 1,024.8 1,030.3 1,084.2 1,103.0 1,128.9 1,180.4 1,228.7 1,017.3 1,125.3 1,255.7 1,201.0 FY14 budget FY15 budget FY16 budget FY18 FY19 FY20 Avg. 1,526.5 1,020.6 1,145.0 1,294.6 1,178.8 Source: Coast Guard FY2013-FY2016 budget submissions. At a June 26, 2013, hearing on Coast Guard acquisition before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, CRS testified that The Coast Guard’s FY2014 Five Year (FY2014-FY2018) CIP includes a total of about $5.1 billion in acquisition funding, which is about $2.5 billion, or about 33%, less than the total of about $7.6 billion that was included in the Coast Guard’s FY2013 Five Year (FY2013-FY2017) CIP. (In the four common years of the two plans—FY2014FY2017—the reduction in funding from the FY2013 CIP to the FY2014 CIP is about $2.3 billion, or about 37%.) This is one of the largest percentage reductions in funding that I have seen a five-year acquisition account experience from one year to the next in many years. About twenty years ago, in the early 1990s, Department of Defense (DOD) five-year procurement plans were reduced sharply in response to the end of the Cold War—a largescale change in the strategic environment that led to a significant reduction in estimated Congressional Research Service 16 Coast Guard Cutter Procurement: Background and Issues for Congress future missions for U.S. military forces. In contrast to that situation, there has been no change in the Coast Guard’s strategic environment since last year that would suggest a significant reduction in estimated future missions for the Coast Guard.43 The Coast Guard has testified that funding the AC&I account at a level of about $1 billion to $1.2 billion per year would make it difficult to fund various Coast Guard acquisition projects, including a new polar icebreaker, and improvements to Coast Guard shore installations. Coast Guard plans call for procuring OPCs at an eventual rate of two per year. If each OPC costs roughly $400 million, procuring two OPCs per year in an AC&I account of about $1 billion to $1.2 billion per year would leave about $200 million to $400 million per year for all other AC&Ifunded programs. At an October 4, 2011, hearing on the Coast Guard’s major acquisition programs before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, the following exchange occurred: REPRESENATIVE FRANK LOBIONDO: Can you give us your take on what percentage of value must be invested each year to maintain current levels of effort and to allow the Coast Guard to fully carry out its missions? ADMIRAL ROBERT J. PAPP, COMMANDANT OF THE COAST GUARD: I think I can, Mr. Chairman. Actually, in discussions and looking at our budget—and I’ll give you rough numbers here, what we do now is we have to live within the constraints that we’ve been averaging about $1.4 billion in acquisition money each year. If you look at our complete portfolio, the things that we’d like to do, when you look at the shore infrastructure that needs to be taken care of, when you look at renovating our smaller icebreakers and other ships and aircraft that we have, we’ve done some rough estimates that it would really take close to about $2.5 billion a year, if we were to do all the things that we would like to do to sustain our capital plant. So I’m just like any other head of any other agency here, as that the end of the day, we’re given a top line and we have to make choices and tradeoffs and basically, my tradeoffs boil down to sustaining frontline operations balancing that, we’re trying to recapitalize the Coast Guard and there’s where the break is and where we have to define our spending.44 An April 18, 2012, blog entry stated: If the Coast Guard capital expenditure budget remains unchanged at less than $1.5 billion annually in the coming years, it will result in a service in possession of only 70 percent of the assets it possesses today, said Coast Guard Rear Adm. Mark Butt. Butt, who spoke April 17 [2012] at [a] panel [discussion] during the Navy League Sea Air Space conference in National Harbor, Md., echoed Coast Guard Commandant Robert Papp in stating that the service really needs around $2.5 billion annually for procurement.45 43 Statement of Ronald O’Rourke, Specialist in Naval Affairs, Congressional Research Service, before the House Transportation and Infrastructure Committee, Subcommittee on Coast Guard and Maritime Transportation, Hearing on Coast Guard Readiness: Examining Cutter, Aircraft, and Communications Needs, June 26, 2013, p. 1. 44 Source: Transcript of hearing. 45 David Perera, “The Coast Guard Is Shrinking,” FierceHomelandSecurity.com, April 18, 2012, accessed July 20, 2012, at http://www.fiercehomelandsecurity.com/story/coast-guard-shrinking/2012-04-18. Congressional Research Service 17 Coast Guard Cutter Procurement: Background and Issues for Congress At a May 9, 2012, hearing on the Coast Guard’s proposed FY2013 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified, “I’ve gone on record saying that I think the Coast Guard needs closer to $2 billion dollars a year [in acquisition funding] to recapitalize—[to] do proper recapitalization.”46 At a May 14, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security Subcommittee of the Senate Appropriations Committee, Admiral Papp stated the following regarding the difference between having about $1.0 billion per year rather than about $1.5 billion per year in the AC&I account: Well, Madam Chairman, $500 million—a half a billion dollars—is real money for the Coast Guard. So, clearly, we had $1.5 billion in the [FY]13 budget. It doesn't get everything I would like, but it—it gave us a good start, and it sustained a number of projects that are very important to us. When we go down to the $1 billion level this year, it gets my highest priorities in there, but we have to either terminate or reduce to minimum order quantities for all the other projects that we have going. If we're going to stay with our program of record, things that have been documented that we need for our service, we're going to have to just stretch everything out to the right. And when we do that, you cannot order in economic order quantities. It defers the purchase. Ship builders, aircraft companies—they have to figure in their costs, and it inevitably raises the cost when you're ordering them in smaller quantities and pushing it off to the right. Plus, it almost creates a death spiral for the Coast Guard because we are forced to sustain older assets—older ships and older aircraft—which ultimately cost us more money, so it eats into our operating funds, as well, as we try to sustain these older things. So, we'll do the best we can within the budget. And the president and the secretary have addressed my highest priorities, and we'll just continue to go on the—on an annual basis seeing what we can wedge into the budget to keep the other projects going. 47 At a March 12, 2014, hearing on the Coast Guard’s proposed FY2015 budget before the Homeland Security subcommittee of the House Appropriations Committee, Admiral Papp stated: Well, that’s what we've been struggling with, as we deal with the five-year plan, the capital investment plan, is showing how we are able to do that. And it will be a challenge, particularly if it sticks at around $1 billion [per year]. As I've said publicly, and actually, I said we could probably—I've stated publicly before that we could probably construct comfortably at about 1.5 billion [dollars] a year. But if we were to take care of all the 46 Source: transcript of hearing. Papp may have been referring to remarks he made to the press before giving his annual state of the Coast Guard speech on February 23, 2012, in which reportedly stated that the Coast Guard would require about $2 billion per year in acquisition funding to fully replace its current assets. (See Adam Benson, “Coast Guard Cutbacks Will Cost 1,000 Jobs,” Norwich Bulletin, February 23, 2012, accessed May 31, 2012, at http://www.norwichbulletin.com/news/x1138492141/Coast-Guard-cutbacks-will-cost-1-000-jobs#axzz1wSDAFCzX. See also “Coast Guard Leader Calls For More Ships,” MilitaryFeed.com, February 24, 2012, accessed May 31, 2012, at http://militaryfeed.com/coast-guard-leader-calls-for-more-ships-5/; Associated Press, “Coast Guard Commandant Calls for New Ships,” TheLog.com, March 10, 2012, accessed May 31, 2012, at http://www.thelog.com/SNW/Article/CoastGuard-Commandant-Calls-for-New-Ships-to-Replace-Aging-Fleet; Mickey McCarter, “Congress Poised to Give Coast Guard More Money Than Requested for FY 2013,” HSToday.us, May 10, 2012, accessed May 31, 2012, at http://www.hstoday.us/focused-topics/customs-immigration/single-article-page/congress-poised-to-give-coast-guardmore-money-than-requested-for-fy-2013.html.) See also “Interview, Adm. Robert Papp, US Coast Guard Commandant,” Defense News, November 11, 2013: 30. 47 Transcript of hearing. The remarks were made in response to a question from Senator Mary Landrieu. Congressional Research Service 18 Coast Guard Cutter Procurement: Background and Issues for Congress Coast Guard’s projects that are out there, including shore infrastructure that that fleet that takes care of the Yemen [sic: inland] waters is approaching 50 years of age, as well, but I have no replacement plan in sight for them because we simply can't afford it. Plus, we need at some point to build a polar icebreaker. Darn tough to do all that stuff when you're pushing down closer to 1 billion [dollars per year], instead of 2 billion [dollars per year]. As I said, we could fit most of that in at about the 1.5 billion [dollars per year] level, but the projections don't call for that. So we are scrubbing the numbers as best we can. 48 At a March 24, 2015, hearing on the Coast Guard’s proposed FY2016 budget before the Homeland Security subcommittee of the House Appropriations Committee, Admiral Paul Zukunft, Admiral Papp’s successor as Commandant of the Coast Guard, stated: I look back to better years in our acquisition budget when we had a—an acquisition budget of—of $1.5 billion. That allows me to move these programs along at a much more rapid pace and, the quicker I can build these at full-rate production, the less cost it is in the long run as well. But there’s an urgent need for me to be able to deliver these platforms in a timely and also in an affordable manner. But to at least have a reliable and a predictable acquisition budget would make our work in the Coast Guard much easier. But when we see variances of—of 30, 40% over a period of three or four years, and not knowing what the Budget Control Act may have in store for us going on, yes, we are treading water now but any further reductions, and now I am—I am beyond asking for help. We are taking on water.49 Although the annual amounts of acquisition funding that the Coast Guard has received in recent years are one potential guide to what Coast Guard acquisition funding levels might or should be in coming years, there may be other potential guides. For example, one could envision potential guides that focus on whether Coast Guard funding for ship acquisition and sustainment is commensurate with Coast Guard funding for the personnel that in many cases will operate the ships. Observations that might be made in connection with this example based on the Coast Guard and Navy budget submissions include the following:  Using figures from the FY2014 budget submission, the Coast Guard has about 12.9% as many active-duty personnel as the Navy.50 If the amount of funding for the surface ship acquisition and sustainment part of the AC&I account were equivalent to 12.9% of the amount of funding in the Navy’s shipbuilding account, the surface ship acquisition and sustainment part of the AC&I account would be about $1.8 billion per year.51 Navy surface ship acquisition, unlike Coast Guard surface ship acquisition, includes substantial numbers of large and complex ships, including nuclear-powered aircraft carriers, highly capable surface combatants, and large amphibious and auxiliary ships. Accounting for this difference in Navy and Coast Guard surface ship acquisition by reducing the $1.8 billion figure by, say, one-half or one-third would produce an adjusted figure of about $900 million to about $1.2 billion per year for surface ship acquisition and sustainment. 48 Transcript of hearing. Transcript of hearing. The remarks were made in response to a question from Representative John Culberson. 50 The Coast Guard for FY2014 appears to be requesting an active-duty end strength—the number of active-duty military personnel—of 41,594 (measured by the Coast Guard in full-time equivalent [FTE] positions); the Navy for FY2014 is requesting an active-duty end strength of 323,600. 51 The Navy’s proposed FY2014 budget requests $14,078 million for the Shipbuilding and Conversion, Navy (SCN) appropriation account. 49 Congressional Research Service 19 Coast Guard Cutter Procurement: Background and Issues for Congress  Again using figures from the FY2014 budget submission, funding in the Navy’s shipbuilding account is equivalent to about 51% of the Navy’s funding for activeduty personnel.52 If Coast Guard funding for surface ship acquisition and sustainment were equivalent to 51% of Coast Guard funding for military pay and allowances, the surface ship acquisition and sustainment part of the AC&I account would be about $1.7 billion per year.53 Reducing the $1.8 billion figure by, say, one-half or one-third to account for differences in the types of surface ships acquired by the Navy and Coast Guard (see previous bullet point) would produce an adjusted figure of about $850 million to about $1.1 billion per year for surface ship acquisition and sustainment. Multiyear Procurement (MYP) and Block Buy Contracting Another potential oversight issue for Congress concerns the potential for using multiyear contracting (i.e., multiyear procurement (MYP) or block buy contracting) in acquiring new cutters. With congressional approval, certain Department of Defense (DOD) programs for procuring ships, aircraft, and other items employ MYP or block buy contracting to reduce procurement costs. Compared to the standard or default approach of annual contracting, MYP and block buy contracting have the potential for reducing procurement costs by several percent.54 The statute that governs the use of MYP—10 U.S.C. 2306b—makes MYP available with congressional approval not only to DOD, but to other government departments, including DHS, the parent department of the Coast Guard.55 Congress also has the option of providing the Coast Guard with authority to use block buy contracting, as it has done for the Navy. All three of the Navy’s year-to-year shipbuilding programs—the Virginia-class attack submarine program, the DDG-51 destroyer program, and the Littoral Combat Ship (LCS) program—currently use MYP or block buy contracting. In contrast, the Coast Guard has not used MYP or block buy contracting for any of its cutter procurement programs. Section 223 of the Howard Coble Coast Guard and Maritime Transportation Act of 2014 (S. 2444/P.L. 113-281 of December 18, 2014) states: SEC. 223. MULTIYEAR PROCUREMENT AUTHORITY FOR OFFSHORE PATROL CUTTERS. In fiscal year 2015 and each fiscal year thereafter, the Secretary of the department in which the Coast Guard is operating may enter into, in accordance with section 2306b of title 10, United States Code, multiyear contracts for the procurement of Offshore Patrol Cutters and associated equipment. Potential oversight questions for Congress include the following:  Has the Coast Guard considered using MYP or block buy contracting for procuring NSCs, OPCs, or FRCs? If not, why not? 52 The Navy’s proposed FY2014 budget requested $27,824 million for the Military Personnel, Navy (MPN) appropriation account. 53 The Coast Guard’s proposed FY2014 budget requested $3,425.3 million for military pay and allowances. 54 For more on MYP and block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz. 55 10 U.S.C. 2306b(b)(2)(B). Congressional Research Service 20 Coast Guard Cutter Procurement: Background and Issues for Congress   What would be the potential savings of using MYP or block buy contracting for procuring the final two or three NSCs, for procuring OPCs, or for procuring FRCs? What are the potential risks or downsides of using MYP or block buy contracting for procuring NSCs, OPCs, or FRCs? OPC Program: FY2016 Funding Request Another potential oversight issue for Congress for FY2016 concerned the FY2016 funding request for the OPC program. As shown in Table 1, the amount requested—$18.5 million—was $71.5 million less than the $90 million that was projected for the OPC program for FY2016 under the FY2015 budget submission. As also noted earlier, the Coast Guard stated, “The Administration’s [FY2016 budget] request includes a [proposed legislative] General Provision permitting a transfer [of additional funding] to the OPC project if the program is ready to award the next phase of vessel acquisition in FY 2016.” Potential oversight questions for Congress included the following:    Why was the program’s FY2016 funding request reduced from the $90 million projected under the FY2015 budget submission to $18.5 million? Who will determine whether “the OPC project if the program is ready to award the next phase of vessel acquisition in FY 2016”? What criteria will be used to make this determination? If additional funding is not transferred to the OPC program, what effect will this have on the program’s schedule? At a March 24, 2015, hearing on the Coast Guard’s proposed FY2016 budget before the Homeland Security subcommittee of the House Appropriations Committee, the following exchange occurred: REPRESENTATIVE JOHN CARTER, CHAIRMAN (continuing): Now, I‘ve got a question about this offshore patrol cutter situation. I told you in my opening remarks that it’s going to be one of the largest, if not the largest, acquisition ever completed by DHS. Over $130 million has been appropriated to the program since 2004, yet we will not see an operational [O]PC until 2021. I am confused by your (inaudible) support of the (inaudible) acquisition but there are no funding requests in the [FY]'16 budget. Why are there no funds requested for a PC [sic: OPC] in [FY]'16? Your acquisition plans indicates a contract award by late ‘16—FY ‘16. What would it impact if the contract award needed to be shifted to FY ‘17? ADMIRAL PAUL ZUKUNFT, COMMANDANT, U.S. COAST GUARD: So we have partial funding to do—do final construction and design work for the OPC. The work would actually begin following that. We're working very closely with the Department of Homeland Security to provide the offset that will be needed to do full design work for the offshore patrol cutter in [FY]2016. The underlying criteria is affordability. We have adhered to very stable requirements. I revisited those and—and I am convinced that—that we will be able to produce an affordable offshore patrol cutter using fixed priced contracting and we have three very highly incentivized contractors competing to get this largest contract in Coast Guard history. CARTER: So that’s the reason there’s no fund[ing] request in the [FY]'16 (inaudible). ZUKUNFT: Congressional Research Service 21 Coast Guard Cutter Procurement: Background and Issues for Congress No, sir. I requested full funding [for the OPC program]. I'm short about $69 million to proceed forward with the final design of this. But, again, working very closely and with the great support of our secretary of Homeland Security to move this forward in [FY]2016. As you mentioned, I cannot afford to let this date lapse. I need relief ships for our 50-year-old ships today that will be 55-years-old by the time their relief arrives. 56 A bit later in the hearing, the following exchange occurred: REPRESENTATIVE LUCILLE ROYBAL-ALLARD, RANKING MEMBER: The FY 2016 request for continued development of the offshore patrol cutter is $18.5 million which is substantially below the planned spending level in the FY 2015 CIP [i.e., five-year Capital Investment Plan] which is the most recently CIP that we have. The budget request proposes new bill language that would provide unlimited authority to transfer funding to the Coast Guard for the OPC project. What can you tell us about the need for this new transfer authority and the likelihood that the department would actually use it? And if there is a reasonable expectation that more funding for the OPC will be needed, why not just include the funding in the request? ZUKUNFT: Yes, first and foremost, we have great support from the department and so that transfer authority would be imperative for us to be able to have full funding in [FY]2016 to be able to move this project forward. You will hear from our secretary two days from now, I believe, he is testifying as well and—and, clearly, counterterrorism in the homeland is always a highest priority for our Department of Homeland Security. But at the same time so is recapitalizing in the Coast Guard, in the offshore patrol cutter. I have a very open and frank dialogue with our secretary and I need to demonstrate to him that—that we can produce an affordable offshore patrol cutter and I remain confident that I will be able to do that. And, with that, the transfer authority would be very critical for us to meet this very important timeline short of an additional appropriation for full funding to move this project forward.57 OPC Program: Cost, Design, and Acquisition Strategy Another potential oversight issue for Congress concerns the Coast Guard’s acquisition strategy for the Offshore Patrol Cutter. Potential oversight questions for Congress include the following:    56 57 Has the Coast Guard fully incorporated into the OPC acquisition strategy lessons learned from the NSC and FRC programs? What, in the Coast Guard’s view, are those lessons? As mentioned earlier, the Coast Guard’s RFP for the OPC program establishes an affordability requirement of an average unit price of $310 million per ship, or less, in then-year dollars for ships 4 through 9 in the program (for the shipbuilder’s portion of the total cost of the ship). How was the $310 million figure determined? What process is the Coast Guard using to evaluate tradeoffs in OPC performance features against this target construction price? What performance features have been reduced or eliminated to meet the target construction price? Transcript of hearing. Transcript of hearing. Congressional Research Service 22 Coast Guard Cutter Procurement: Background and Issues for Congress   How much confidence does the Coast Guard have that the OPC that emerges from the tradeoff process could be built within the Coast Guard’s target construction price? As mentioned earlier, the Coast Guard plans to evaluate the preliminary and contract design (P&CD) proposals and then award one of the competitors a contract for detailed design development and ship construction. What process does the Coast Guard plan to use in evaluating the P&CD efforts? What evaluation factors does the Coast Guard plan to use, and how much weight will be assigned to each? A January 16, 2015, press report states Coast Guard Commandant Adm. Paul Zukunft on Thursday [January 15] said that his staff is currently reviewing the requirements for its Offshore Patrol Cutter (OPC) with affordability in mind. The “biggest challenge that we’re facing right now is that this will not be affordable,” Zukunft said at the annual Surface Navy Association conference in Arlington, Va. “I’ve turned it back to industry…bring me a capable platform that is also affordable.” Zukunft, who became commandant last May, is doing more than leave it to industry to design and produce a new and affordable medium endurance cutter for the Coast Guard. He told Defense Daily after his speech that he directed his “staff do a deep scrub on every one of the line items and so there are some line items in there that struck me.” For example, he said, what is the required water pressure for firefighting? If the requirement is set too high, that affects “piping, it affects weight, [and] how big of a pump do you need.” Zukunft said it’s this level of detail that is being scrubbed to figure out what is needed. Zukunft describe[d] the requirements review as an “open dialogue” that is “fully transparent” with the shipbuilders competing for the 25-ship OPC buy free to weigh in. The “competitors are very incentivized to come up with an affordable product for us as well,” Zukunft said.58 NSC Program: Initial Testing Another potential oversight issue for Congress concerns the results of initial testing of the NSC. A January 2016 GAO report stated: The U.S. Navy, the Coast Guard’s independent test agent, completed initial testing for the National Security Cutter (NSC) in April 2014 and rated the NSC as operationally effective and suitable. Still, testing revealed 10 major deficiencies.... Initial testing is an event designed to verify performance of critical systems to ensure assets are capable of meeting mission requirements. The event tests critical operational issues and key performance parameters. The NSC fully met 12 of 19 key performance parameters. Tests of one key performance parameter, as well as other critical systems, were deferred to follow-on testing. The Coast Guard and the U.S. Navy disagree on the NSC’s requirements for cutter boat operations. Without clear requirements the Navy and Coast Guard will not have a basis for determining actions to resolve any performance issues. Coast Guard officials acknowledged that clarifying these requirements would be beneficial. 58 Calvin Biesecker, “With Affordability In Mind, Zukunft Reviewing OPC Requirements,” Defense Daily, January 16, 2015: 4. Congressional Research Service 23 Coast Guard Cutter Procurement: Background and Issues for Congress The Coast Guard plans to begin follow-on testing in fall 2016. It must submit corrective action plans to the U.S. Navy to close any deficiencies. According to Coast Guard documentation, it may choose not to correct all deficiencies due to the cost of changes. Department of Homeland Security (DHS) acquisition guidance does not specify the timing of follow-on testing or the actions to be taken in response to the findings. Without a definite time frame DHS risks encountering the same problems as the NSC program experienced with future acquisitions and fielding assets without knowing the full capabilities. During operations, the NSC has experienced performance issues that were not identified during initial testing, and the Coast Guard has planned design changes to some of the cutters’ equipment.... However, the Coast Guard has not yet found the causes for problems affecting the NSC’s propulsion systems. As a result of these and other equipment failures, the NSC has been operating in a degraded condition in some mission areas. DHS has no plans for additional acquisition review boards for the NSC, which would provide oversight going forward. Continued management-level oversight by DHS would help ensure that problems identified during testing and operations are addressed.59 NSC Program: Rotational Crewing A March 2015 GAO report stated that The Coast Guard has delayed the feasibility test for using the crew rotation concept (CRC) to achieve increased operational days at sea with its National Security Cutters (NSC) until 2019. In 2006, the Coast Guard decided to use the CRC for its NSCs and that implementation would begin in 2011. However, the Coast Guard has postponed CRC testing because of delays in NSC deliveries and needed structural enhancements. In fiscal year 2013, the Coast Guard began implementing an interim plan to increase the NSCs’ operational performance, not by rotating crews, but by adding crew members to help bear the increased workload. However, the added crew members do not have the skill mix recommended by a 2011 manpower requirements analysis. Without the appropriate crew members with the right skill mix, the NSCs may not be able to complete all mission requirements or required maintenance. The Coast Guard has not fully addressed a variety of risks that could affect the success of its planned CRC feasibility test and goal to increase NSC operational days away from home port (DAFHP) from 185 to 230 days per year using the CRC. Further, the Coast Guard could not provide us with complete details about whether the CRC plan, to be completed by the end of 2017, will include actions to address and effectively mitigate various risks, to include • determining the appropriate number and skill mix of NSC crew members and support personnel and whether they will be in place in time for the CRC test; • incorporating actual NSC maintenance needs when developing NSC maintenance schedules and goals; • testing the CRC under realistic circumstances, such as addressing the misalignment of the crewing concept to be tested as compared to the NSC homeporting plan; • addressing the potential impacts of wide variations between alternative deployment schedules using the CRC; and 59 Government Accountability Office, National Security Cutter[:]Enhanced Oversight Needed to Ensure Problems Discovered during Testing and Operations Are Addressed, GAO-16-148, January 2016, summary page. Congressional Research Service 24 Coast Guard Cutter Procurement: Background and Issues for Congress • implementing a training infrastructure and providing training support for off-cycle rotating crews. As the Coast Guard continues to develop its CRC plan, establishing interim milestones for carrying out the actions needed to address and effectively mitigate these risks would help ensure that it addresses the risks in a timely manner. The Coast Guard’s current measure does not accurately quantify the operational performance of the NSC fleet. The Coast Guard primarily uses the DAFHP measure across its major cutter fleet; however, this measure includes days when a cutter is undergoing maintenance away from its home port and, as a result, will likely overstate the number of operational days. The Coast Guard has known of the measure’s limitation for years and is exploring alternatives. However, since the CRC plan is premised on achieving 230 DAFHP per year—and that other Coast Guard vessels, such as the Offshore Patrol Cutter, also plan to use the DAFHP metric—implementing alternative measures prior to CRC testing will better ensure the test results are benchmarked against a more appropriate goal to quantify the operational performance of its fleet of NSCs and its planned fleet of Offshore Patrol Cutters. 60 FRC Program: Operational Testing Another potential oversight issue for Congress concerns the results of operational testing of the FRC. A June 2014 report on Coast Guard acquisition programs states that DHS approved the Fast Response Cutter and [the] HC-144 [maritime patrol aircraft] for full-rate production in September 2013 and October 2012, respectively. However, neither asset met all key requirements during initial operational testing. The Fast Response Cutter partially met one of six key requirements while the HC-144 met or partially met four of seven. The Fast Response Cutter was found to be operationally effective (with the exception of its cutter boat) though not operationally suitable, and the HC-144 was found to be operationally effective and suitable. As we have previously found for Department of Defense (DOD) programs, continuing with full-rate production before ensuring that assets meet key requirements risks replicating problems in each new asset until such problems are corrected. DHS officials stated that they approved both assets for full-rate production because the programs had plans in place to address most major issues identified during testing, such as supplying the Fast Response Cutter with a small boat developed for the National Security Cutter. However, DHS and Coast Guard acquisition guidance are not clear regarding when the minimum performance standards should be met, such as prior to entering full-rate production. For example, DHS and Coast Guard guidance provide that the Coast Guard should determine if the capability meets the established minimum performance standards, but do not specify when this determination should be made. By comparison, DOD acquisition guidance requires that specific minimum performance standards, which are defined at the time assets are approved for system development, be met prior to entering full-rate production. In addition, DHS and Coast Guard acquisition guidance do not clearly specify how agency officials determine when a breach occurs and what triggers the need for a program manager to submit a performance breach memo. According to DHS and Coast Guard acquisition guidance, when programs fail to meet key performance parameters, program managers are required to file breach memorandums stating that the program did not demonstrate the required capability. Even though threshold key performance parameters on the HC-144 and Fast Response Cutter were not met during operational 60 Government Accountability Office, Coast Guard[:] Timely Actions Needed to Address Risks in Using Rotational Crews, GAO-15-195, summary page. Congressional Research Service 25 Coast Guard Cutter Procurement: Background and Issues for Congress testing, the Coast Guard did not report that a breach had occurred. Acquisition guidance is unclear as to whether or not failing to meet key requirements during operational testing constitutes a breach. According to Coast Guard officials, if the Coast Guard plans to retest or re-design a deficiency in order to meet the threshold value, then a breach has not yet occurred. For example, the Fast Response Cutter small boat did not meet the threshold seakeeping requirement, but a new cutter small boat has since been tested on its own and fielded to all Fast Response Cutters. The Coast Guard plans to test this new cutter small boat with the Fast Response Cutter during follow on testing. Program officials are confident that the cutter’s new small boat meets this requirement and that— therefore—a breach has not occurred. DHS acquisition guidance specifies the performance criteria used to determine whether or not a breach has occurred, but does not identify a triggering event for determining when a breach occurs. DHS’s Program Accountability and Risk Management officials stated that a program breach is not necessarily related to its performance during initial operational testing, which they state is a snapshot of a single asset’s performance during a defined test period. Without clear acquisition guidance, it is difficult to determine when or by what measure an asset has breached the threshold values of its key performance parameters and—therefore—when to notify DHS and certain congressional committees.... COTF [Commander, Operational Test and Evaluation Force] determined in July 2013 that the Fast Response Cutter, without the cutter’s small boat, is operationally effective— meaning that testers determined that the asset enables mission success. The cutter’s small boat was determined to not be seaworthy in minimally acceptable sea conditions and— therefore—could not support the cutter’s mission set. Further, COTF determined that the Fast Response Cutter is not operationally suitable because a key engine part failed, which lowered the amount of time the ship was available for missions to an unacceptable level. Despite the mixed test results, COTF and DHS testers as well as Coast Guard program officials all agree that the Fast Response Cutter is a capable vessel. Ultimately, COTF recommended that the Coast Guard proceed to field the vessel, but also recommended that the issues with the cutter’s small boat be remedied expeditiously and that follow-on operational testing be conducted once corrective actions have been implemented. Since the test, the Coast Guard has delivered a new small boat that meets the Fast Response Cutter’s needs and determined that the engine part failure was an isolated event. The Navy also examined the extent to which the Fast Response Cutter meets key requirements. The test demonstrated that it partially met only one out of its six key requirements; the other five requirements did not meet minimum performance levels or were not tested. Table 2 displays each key performance parameter for the Fast Response Cutter, the test results, and a discussion of these results. Congressional Research Service 26 Coast Guard Cutter Procurement: Background and Issues for Congress The Coast Guard proactively sought to test the Fast Response Cutter early in the acquisition process, but early testing limited the ability to fully examine the vessel. For example, the Coast Guard did not test the top speed of the vessel due to a fuel oil leak. As noted above, DHS approved the Fast Response Cutter for full-rate production, but directed the program to develop corrections for the issues identified during operational testing and to verify those corrections through follow-on operational testing by the end of fiscal year 2015.61 GAO testified on May 14, 2015, that As we reported in June 2014, operational testers within the Department of the Navy determined in July 2013 that the FRC, without the cutter’s small boat, is operationally effective—meaning that testers determined that the asset enables mission success. However, these operational testers also determined that the FRC is not operationally suitable because a key engine part failed, which lowered the amount of time the ship was available for missions to an unacceptable level. Despite the mixed test results, Navy and DHS testers as well as Coast Guard program officials all agreed that the FRC is a capable vessel, and the Coast Guard plans to confirm that it has resolved these issues during follow-on testing planned to be completed by the end of fiscal year 2015.62 61 Government Accountability Office, Coast Guard Acquisitions[:] Better Information on Performance and Funding Needed to Address Shortfalls, GAO-14-450, June 2014, pp. 13-16. 62 Government Accountability Office, Coast Guard Acquisitions[:] As Major Assets Are Fielded, Overall Portfolio Remains Unaffordable, GAO-15-620T, May 14, 2015, pp. 8-9. Congressional Research Service 27 Coast Guard Cutter Procurement: Background and Issues for Congress Legislative Activity for FY2016 Summary of Appropriations Action on FY2016 Acquisition Funding Request Table 7 summarizes appropriations action on the Coast Guard’s request for FY2016 acquisition funding for the NSC, OPC, and FRC programs. Table 7. Summary of Appropriations Action on FY2016 Acquisition Funding Request Figures in millions of dollars, rounded to nearest tenth Request NSC program OPC program FRC program TOTAL Request 91.4 18.5 340.0 449.9 House Appropriations Committee 103.4 89.0 340.0 532.4 Senate Appropriations Committee 731.4 18.5 230.0 979.9 Final 743.4 89.0 340.0 1,172.4 Source: For request: Coast Guard FY2016 budget submission. For House Appropriations Committee: H.Rept. 114-215, p. 61. For Senate Appropriations Committee: S.Rept. 114-68, p. 80. For final: explanatory statement for Division F of H.R. 2029, PDF page 47 of 118. FY2016 Department of Homeland Security (DHS) Appropriations Act (H.R. 3128/S. 1619/H.R. 2029) House Section 516 of H.R. 3128 as reported by the House Appropriations Committee (H.Rept. 114-215 of July 21, 2015) states: Sec. 516. Any funds appropriated to “Coast Guard, Acquisition, Construction, and Improvements” for fiscal years 2002, 2003, 2004, 2005, and 2006 for the 110–123 foot patrol boat conversion that are recovered, collected, or otherwise received as the result of negotiation, mediation, or litigation, shall be available until expended for the Fast Response Cutter program. H.Rept. 114-215 states: Recommendation The Committee recommends $1,301,289,000 for Acquisition, Construction, and Improvements (AC&I), $284,020,000 above the amount requested and $76,066,000 above the amount provided in fiscal year 2015. The Committee is alarmed by the significant decrease in the President’s budget request for AC&I. The Coast Guard continues to communicate publicly that its fleets of aircraft and vessels are in desperate need of recapitalization. Many vessels are decades beyond their useful life. Though the need for recapitalization programs is apparent, the budget request fails to meet the requirement. The Committee recommends a significant increase to the AC&I request and expects the Department and the Administration to provide a more realistic AC&I budget request in the future. (Page 60) H.Rept. 114-215 also states: Congressional Research Service 28 Coast Guard Cutter Procurement: Background and Issues for Congress National Security Cutter The Committee recommends $103,400,000 for the National Security Cutter (NSC) program, $12,000,000 above the amount requested and $529,447,000 below the amount provided in fiscal year 2015. The increase above the request will support the top-side engineering design work required for the permanent installation of small UAS, along with associated testing activities and critical spares. The fiscal year 2015 appropriation provided sufficient funding to acquire the eighth NSC, which is the final NSC of record. The Committee notes that funding for additional NSCs beyond the program of record would be neither operationally necessary nor warranted, would create potentially unsustainable operational funding requirements in the future, and could potentially threaten funding for other Coast Guard acquisition priorities. Fast Response Cutter The Committee recommends $340,000,000 to acquire six additional Fast Response Cutters (FRCs), as requested, and $230,000,000 above the amount provided in fiscal year 2015. Offshore Patrol Cutter The Committee recommends $89,000,000 for the Offshore Patrol Cutter (OPC) program, $70,500,000 above the request and $69,000,000 above the amount provided in fiscal year 2015. The fiscal year 2016 budget request did not include funding for the detailed design and construction of the high priority OPC, even though the Coast Guard’s acquisition schedule includes a projected contract award date during fiscal year 2016. Instead, the budget proposed open-ended transfer authority without clear direction as to the source of funding when the award is made in fiscal year 2016. The Coast Guard has repeatedly communicated that the OPC is its highest acquisition priority, yet this is not reflected in the budget request. The Committee recommends the appropriate level of funding to ensure the OPC contract can be awarded, and the Coast Guard can begin the process of recapitalizing its aging fleet of medium endurance vessels. The planned OPC program will be the Department’s largest acquisition program ever, and the Administration should make this a top priority by requesting the appropriate level of future funding to ensure success. (Page 62) Senate In S. 1619 as reported by the Senate Appropriations Committee (S.Rept. 114-68 of June 18, 2015), the paragraph that appropriates funds for the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account includes a provision that states: Provided, That, of the funds provided by this Act, not less than $640,000,000 shall be immediately available and allotted to contract for the production of the ninth National Security Cutter notwithstanding the availability of funds for postproduction costs.... Section 516 of the bill as reported states: Sec. 516. Any funds appropriated to “Coast Guard, Acquisition, Construction, and Improvements” for fiscal years 2002, 2003, 2004, 2005, and 2006 for the 110–123 foot patrol boat conversion that are recovered, collected, or otherwise received as the result of negotiation, mediation, or litigation, shall be available until expended for the Fast Response Cutter program. Section 559 of the bill as reported states: Sec. 559. Notwithstanding the limitations as to threshold, time, and condition of section 503 of this Act, the Secretary may propose to reprogram or transfer to the Coast Guard Congressional Research Service 29 Coast Guard Cutter Procurement: Background and Issues for Congress for the Offshore Patrol Cutter Project: (1) discretionary appropriations made available by this Act, to remain available until September 30, 2017, and (2) the unobligated balances of discretionary appropriations made available by prior Department of Homeland Security Appropriations Acts: Provided, That any amounts proposed for reprogramming or transfer under this section shall not be available for obligation until the Committees on Appropriations of the Senate and the House of Representatives approve of such reprogramming or transfer: Provided further, That this section shall not apply to amounts that were (1) classified as being in the revised security category, as defined under section 250(c)(4)(D) of the Balanced Budget and Emergency Deficit Control Act of 1985, as amended (BBEDCA); (2) designated by the Congress for Overseas Contingency Operations/Global War on Terrorism or as an emergency requirement pursuant to the Concurrent Resolution on the Budget or BBEDCA; or (3) designated as being for disaster relief pursuant to section 251(b)(2)(D) of BBEDCA. S.Rept. 114-68 states: As an extension of our border security needs, the Coast Guard’s vessel and air fleets are vital. Yet, the age of those fleets and their antiquated capabilities beg recapitalization and modernization. Year after year, the President’s budget requests short-change Coast Guard’s acquisition needs and year after year, the Coast Guard’s Commandants indicate before Congress that their annual acquisition budget is insufficient. As the Coast Guard proceeds towards selecting a final design for the Offshore Patrol Cutter [OPC], the Committee sees an opportunity for a ninth National Security Cutter [NSC] in the interim. The most capable vessel ever commissioned by the Coast Guard, the NSC will replace aging high endurance cutters which were state-of-the-art nearly a half-century ago. In addition to cutter needs, the Committee continues its acquisition and sustainment investments in the Coast Guard’s icebreaking fleet, directs further guidance from the Coast Guard on their air fleet mix, and increases investments in critical shore facilities. (Page 6) S.Rept. 114-68 also states: BERING SEA COVERAGE The Committee is concerned that adequate cutter coverage in the Bering Sea and Arctic Region will become increasingly difficult to achieve as the medium endurance cutter Alex Haley and high endurance cutter Munro have both exceeded 40 years of service life under extremely demanding conditions. Not later than 60 days after the date on enactment of this act, the Secretary shall submit to Congress a report on the plans of the Coast Guard to ensure that at least one cutter capable of operating in and patrolling the Bering Sea and Arctic Region maintains a presence in the Bering Sea and Arctic Region at all times during the 10-year period beginning on the date of such submittal. This report shall include the following: (1) For each cutter of the Coast Guard involved in patrolling the Bering Sea and Arctic Region on the day before the date of enactment of this act that the Secretary considers a legacy cutter, the date on which the Secretary expects to decommission the cutter; (2) For each cutter described in (1), the date on which the Secretary expects to replace the cutter; (3) The Committee expects the replacement cutters to meet or exceed the current capabilities of the legacy assets, keeping in mind the growing presence of China and Russia; and (4) The Coast Guard’s plan to ensure there are no gaps in coverage during this 10-year period. (Pages 75-76) Congressional Research Service 30 Coast Guard Cutter Procurement: Background and Issues for Congress S.Rept. 114-68 also states: COMMITTEE RECOMMENDATIONS The Committee recommends $1,573,269,000 for Acquisition, Construction, and Improvements, including $24,500,000 from the Oil Spill Liability Trust Fund. This is $556,000,000 above the amount requested and $348,046,000 above the amount provided in fiscal year 2015. The increase above the President’s request is a reflection of what the Committee views as an underfunded recapitalization effort which simply cannot provide new assets at the pace required. The sheer age of the Coast Guard’s assets is staggering, including high endurance cutters from the 1960s, a dry dock at the Coast Guard Yard which had its heyday during World War II, and C–130H aircraft which will continue to age without necessary upgrades as they await transfer or replacement. The Coast Guard cutter Reliance celebrated its 50th anniversary in 2014 and in 2015 was at the Coast Guard Yard in the dry dock Oakridge for repairs. The combined age of these two assets was over 120 years. This poses questions about not only mission efficacy but also of crew safety. In addition to recapitalizing aging infrastructure and vessels, the Committee is concerned about the Coast Guard’s air fleet mix. While the Coast Guard inducts the C–27J it has prudently paused the C–144A but has not indicated to Congress whether it still requires additional C–130Js. How the Coast Guard expects to transition to an all ‘‘J’’ fleet by the mid-2020s is unclear, and the Coast Guard’s Capital Investment Plan [CIP] for 2016– 2020 is silent. Similarly troubling is the neglect of the unmanned aircraft systems [UAS] procurement. The Coast Guard will procure its first operational UAS in 2015 at the direction of Congress despite having already commissioned four National Security Cutters with which they should be paired. (Pages 79-80) S.Rept. 114-68 also states: NATIONAL SECURITY CUTTER The National Security Cutter [NSC] is the largest and most technologically advanced cutter the Coast Guard has ever placed into service. Built to replace the aging 378-foot high endurance cutters commissioned in the late 1960s and early 1970s, the NSC has no peer within the Coast Guard and is effectively a floating sector, equally capable of search and rescue in the Bering Sea or counternarcotics enforcement in the South Pacific. It is also currently the only vessel within the Coast Guard capable of detecting and defending its crew against chemical, biological and radiological attacks and its suite of sensors and secure communications capabilities make its domain awareness unmatched in the fleet. Since commissioning of the first NSC in 2008 the Legend-class cutters have demonstrated their efficacy continuously. In 2012, a newly commissioned NSC was dispatched to the Arctic tasked with monitoring exploratory drilling and performing domain awareness, operational response, and command and control functions. In subsequent years, the NSC had led multinational coalitions in the biannual Rim of the Pacific Exercise and continues to seize thousands of pounds of illicit drugs bound for the United States. In 2011, a cutter study commissioned by the Coast Guard indicated that ‘‘the NSC has a mature design, stable requirements, demonstrated operational performance and predictable costs’’. And given the Coast Guard’s experience with its current fleet of high endurance cutters with an average age of 46 years old, it’s likely that the Coast Guard will have the NSCs it procures now for decades to come. The Coast Guard has also stated that central to its plan to replace its legacy high endurance cutters is a new crew rotation concept [CRC] which would ultimately increase days away from home port for the new NSCs. Unfortunately, the Coast Guard has yet to fully test the CRC and will not understand its feasibility until 2019 meaning that the Coast Guard’s goal of meeting or Congressional Research Service 31 Coast Guard Cutter Procurement: Background and Issues for Congress exceeding operational performance of the legacy high endurance cutters within the NSCs Program of Record may fall well short of mission needs. For these reasons, the Committee recommends $640,000,000 for award and production costs associated with a ninth National Security Cutter, notwithstanding future costs for post-delivery activities. FULL FUNDING POLICY The Committee again directs an exception to the administration’s current acquisition policy that requires the Coast Guard to attain total acquisition cost for a vessel, including long lead time materials [LLTM], production costs, and post-production costs, before a production contract can be awarded. This has the potential to create shipbuilding inefficiencies, force delayed obligation of production funds, and require post-production funds far in advance of when they will be used. The Department should be in a position to acquire vessels in the most efficient manner within the guidelines of strict governance measures. The Committee expects the administration to adopt a similar policy for the acquisition of the Offshore Patrol Cutter [OPC]. FAST RESPONSE CUTTER The Committee recommends $230,000,000 for the Coast Guard’s Fast Response Cutter [FRC]. This funding will allow the Coast Guard to acquire four FRC hulls (33–36) and supports base award of the phase II re-compete FRC production contract. This contract will allow options for four, five, or six cutters. OFFSHORE PATROL CUTTER The recommendation includes $18,500,000 for the OPC, as requested. Funding is provided to support Preliminary and Contract Design [P&CD] deliverables to complete the P&CD phase and related support for the acquisition. The Committee also includes language whereby the Department may propose a reprogramming or transfer of $70,500,000 to award Detailed Design, should the Coast Guard be prepared to award in fiscal year 2016.... UNMANNED AIRCRAFT SYSTEMS The Committee is concerned that the Coast Guard will commission its fifth NSC in the summer of 2015, but have only one UAS pair to support deployments. Since the early days of Coast Guard recapitalization under the Deepwater Program, UAS were integral to the overall ‘‘system of systems.’’ Over a decade later, the Coast Guard still appears unsure of how to incorporate UAS technology despite examples of such integration within DHS and across the Federal Government. The Committee expects the Coast Guard to continue its longstanding plan to conduct vertical take-off and landing UAS flight demonstrations. The Coast Guard has reported to the Committee that this system would enhance the surveillance capabilities of the NSC and estimates a significant increase in the number of prosecutions achieved by the cutter. The Committee continues to be very supportive of the use of vertical take-off UAS aboard Coast Guard cutters and strongly encourages the Coast Guard to ensure that the acquisition schedule is not delayed for this enhanced surveillance capability. The Committee is encouraged by the successful results of the Coast Guard’s cutter-based testing and evaluation completed in December, 2014. The Coast Guard is directed to provide a report outlining its plans to acquire and utilize this capability with the fiscal year 2017 budget request. (Pages 82-83) Congressional Research Service 32 Coast Guard Cutter Procurement: Background and Issues for Congress Conference The FY2016 DHS appropriations act is Division F of H.R. 2029, the Consolidated Appropriations Act, 2016. The paragraph in Division F that appropriates funds for the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account includes a provision that states: Provided, That of the funds provided by this Act, not less than $640,000,000 shall be immediately available and allotted to contract for the production of the ninth National Security Cutter notwithstanding the availability of funds for post-production costs.... Section 516 of Division F of H.R. 2029 states: SEC. 516. Any funds appropriated to ‘‘Coast Guard, Acquisition, Construction, and Improvements’’ for fiscal years 2002, 2003, 2004, 2005, and 2006 for the 110–123 foot patrol boat conversion that are recovered, collected, or otherwise received as the result of negotiation, mediation, or litigation, shall be available until expended for the Fast Response Cutter program. The explanatory statement for Division F of H.R. 2029 states: ACQUISITION, CONSTRUCTION, AND IMPROVEMENTS A total of $1,945,169,000 is provided for AC&I, a significant increase above the request that reflects the pressing need for recapitalization of the Coast Guard’ss shore infrastructure and its fleets of aircraft and vessels. Although the Coast Guard continues to communicate publicly that its fleets are in desperate need of recapitalization, and many vessels are decades beyond their expected service life, the budget request failed to adequately address that requirement. The Department and the Administration are expected to provide more realistic AC&I budget requests in the future.... National Security Cutter A total of $743,400,000 is provided for the National Security Cutter (NSC) program. The total includes $640,000,000 for award and production costs associated with a ninth National Security Cutter, notwithstanding future costs for post-delivery activities. In addition, $12,000,000 is included for the necessary top-side engineering design work to support the deployment of small UAS equipment on NSCs. Offshore Patrol Cutter A total of $89,000,000 is provided for the Offshore Patrol Cutter (OPC) program. Within that amount, $70,500,000 is included to exercise the option for Detail Design and commence Phase II of the OPC acquisition. Fast Response Cutter A total of $340,000,000 is provided for the Fast Response Cutter program. This amount is for the acquisition of six cutters. (PDF pages 47-49 of 118) Coast Guard Authorization Act of 2015 (H.R. 1987/S. 1611/H.R. 4188) House Section 206 of H.R. 1987 as reported by House Transportation and Infrastructure Committee (H.Rept. 114-115 of May 15, 2015) states: SEC. 206. Long-term major acquisitions plan. Section 2903 of title 14, United States Code, as redesignated and otherwise amended by this Act, is further amended— Congressional Research Service 33 Coast Guard Cutter Procurement: Background and Issues for Congress (1) by redesignating subsection (e) as subsection (f); and (2) by inserting after subsection (d) the following: “(e) Long-Term major acquisitions plan.—Each report under subsection (a) shall include a plan that describes for the upcoming fiscal year, and for each of the 20 fiscal years thereafter— “(1) the numbers and types of cutters and aircraft to be decommissioned; “(2) the numbers and types of cutters and aircraft to be acquired to— “(A) replace the cutters and aircraft identified under paragraph (1); or “(B) address an identified capability gap; and “(3) the estimated level of funding in each fiscal year required to— “(A) acquire the cutters and aircraft identified under paragraph (2); “(B) acquire related command, control, communications, computer, intelligence, surveillance, and reconnaissance systems; and “(C) acquire, construct, or renovate shoreside infrastructure.”. Regarding Section 206, H.Rept. 114-115 states: Sec. 206. Long term major acquisitions plan. Under current law, the Navy provides Congress with a long-term plan for its shipbuilding requirements. The Coast Guard does not conduct a similar long-term planning effort for its major assets. This section would improve oversight of the Coast Guard’s effort to recapitalize its major assets by requiring the Service to develop a long-term plan for its acquisition needs and the funding levels to support them. (Page 30) H.Rept. 114-115 also states: Investment in Coast Guard capabilities The Committee has long had concerns about the adequacy of capital investment in Coast Guard assets and infrastructure. Enforcing federal laws in, under, over the high seas and waters subject to the jurisdiction of the United States is a complicated task requiring a workforce that is highly trained in many areas from marine and aviation operations to marine safety. It also requires a substantial number of physical assets from cutters and aircraft, to buoys and shoreside facilities. The Coast Guard and GAO have both done estimates of what is required in annual Coast Guard capital investment. These estimates range from $1.5 to more than $2.0 billion depending on whether the goal is to maintain existing capability or to achieve capabilities closer to those imagined in the 2005 Mission Need Statement (MNS), or in the approved acquisition program of record. In recent years, administration budget requests have fallen woefully short of even meeting minimum needs and appropriations have only been able to make up a fraction of the shortfall. In fiscal year 2016, the President is requesting $1 billion for the Coast Guard’s Acquisition, Construction, and Improvement (AC&I) account. This represents a cut of over $200 million or 17 percent from the FY 2015 enacted level. Section 215 of P.L. 113–28163 requires the submission of a revised MNS which explains how each major acquisition program addresses identified mission hour gaps, and describes the missions the Coast Guard will be unable to fully achieve for each gap identified. The Committee will do oversight based on this MNS when it is submitted in 63 S. 2444/P.L. 113-281, the Howard Coble Coast Guard and Maritime Transportation Act of 2014 of December 18, 2014. Congressional Research Service 34 Coast Guard Cutter Procurement: Background and Issues for Congress July 2015. Pending that updated information, H.R. 1987 authorizes the Coast Guard’s AC&I account at $1.5 billion for each of the fiscal years 2016 and 2017, approximately $500 million more than the President’s FY 2016 request. The Committee believes longterm funding at this level will allow the Coast Guard to maintain current mission capability. However, the Committee acknowledges that even at the level of capital funding proposed in this authorization, certain Coast Guard missions simply will not be done or will be done at an operations tempo far short of what is needed to adequately carry them out. The Committee looks forward to continuing to work with the Coast Guard for the remainder for the 114 th Congress to determine how to better align missions and assets under current budget constraints and to identify those missions which may be best handled by other entities. As mentioned, section 215 of P.L. 113–281 requires the Coast Guard to update its 2005 MNS which provides the underlying justification for its asset recapitalization program. H.R. 1987, as amended, builds on that requirement by adding a review of Coast Guard manpower needs. Without a sufficient number of trained servicemembers operating assets, readiness and mission performance suffers. Without trained Coast Guard inspectors and environmental responders, maritime safety and environmental response regulations have no real world effect. The Committee believes these documents will assist in our oversight and our efforts to improve Coast Guard mission performance. (Pages 21-22) H.Rept. 114-115 also states: Section 101. Authorizations This section authorizes $8.7 billion in discretionary funds for the Coast Guard for each of the fiscal years 2016 and 2017. This is the same level of funding that was authorized for the Coast Guard in section 101 of P.L. 113–281. It also authorizes an end-of-year strength for active duty Coast Guard personnel of 43,000 and sets military training student loads for each of the fiscal years 2016 and 2017. The President’s budget for FY 2016 includes a request to transfer an undefined amount of money from an undefined source within the Department of Homeland Security to the Coast Guard to complete detailed design of the Offshore Patrol Cutter (OPC). The Committee is very concerned with this erratic approach to budgeting. This approach is especially troubling for the OPC as the need for the cutter has been well and thoroughly documented and the requirements for which have been widely and extensively vetted. Failure to enter into a contract for detailed design of the OPC before the end of FY 2016 will significantly increase the cost and substantially delay this vital acquisition. The Committee is very concerned that further delays in the initiation of the procurement will only exacerbate existing gaps in Coast Guard mission capabilities. This section authorizes sufficient funds within the Coast Guard’s AC&I account to enter into a contract for detailed design of the OPC in FY 2016. The Committee expects the Coast Guard to ensure, to the maximum extent practicable, that it awards a contract for detailed design of the OPC at the earliest possible date. (Pages 28-29) Senate In its report (S.Rept. 114-168 of November 30, 2015) on S. 1611, the Senate Commerce, Science, and Transportation Committee states: WESTERN HEMISPHERE STRATEGY In 2014, the USCG released its Western Hemisphere Strategy that identified three of the USCG’s priorities over the coming decade: combating networks, securing borders, and safeguarding commerce. This strategy includes proactive engagement with domestic and international partners and stakeholders in order to defeat transnational organized crime Congressional Research Service 35 Coast Guard Cutter Procurement: Background and Issues for Congress networks, which may be responsible for more than $750 billion in losses per year to the global economy. 8 This effort will require an effective offshore interdiction capability, supported by the continued modernization of the USCG’s operational assets, particularly, its fleet of aging cutters. (Page 3) S.Rept. 114-168 also states: MAJOR ASSET RECAPITALIZATION The Coast Guard Authorization Act of 2015 authorizes $1.5 billion for the funding of acquisition, construction, and improvement (AC&I) related activities for the USCG for each of FYs 2016 and 2017. The USCG’s FY 2016 budget request included $1.02 billion for AC&I of USCG assets and facilities, a nearly 17 percent decrease from the FY 2015 enacted budget. Of this amount, $533.9 million is for vessels and ongoing fleet recapitalization and in-service vessel sustainment projects. This is a decrease of over 35 percent, or nearly $300 million. Budget pressures, particularly with respect to the funding of USCG acquisitions, have slowed the USCG’s efforts to upgrade its assets and infrastructure. Many of the USCG’s cutters are operating beyond their planned service life and are ‘‘manpower-intensive and increasingly expensive to maintain, and have features that in some cases are not optimal for performing their assigned missions.’’ The average age of the USCG’s medium endurance cutters, ‘‘the backbone of the offshore fleet,’’ is almost 50 years. In 2014, as a result of significant mechanical malfunctions, four cutters headed to sea in support of the USCG’s counter-drug mission were forced to return to port for emergency dry-docking. The USCG’s high endurance cutters have been in service since the 1960s. A 2014 DHS Inspector General report found that ‘‘the declining readiness’’ of the USCG’s high endurance cutters ‘‘continues to pose significant challenges to mission performance’’. The USCG’s fleet of 12 high-endurance cutters is being replaced by 8 National Security Cutters (NSC); 4 NSCs have been commissioned, and the remaining 4 are still under construction at an average cost of $684 million per ship. The Offshore Patrol Cutter (OPC), which will replace the current fleet of medium endurance cutters, will become the USCG’s highest priority as the NSC acquisition ends. In February 2014, 3 contracts for preliminary design of the OPC were awarded—25 of these vessels are planned to replace the existing fleet of 28 medium endurance cutters. Their estimated cost is $484 million per ship. The final design was scheduled for selection during the fourth quarter of FY 2016, but the USCG’s FY 2016 budget request is short the $69 million required to fully fund the program. The FY 2016 budget request would only provide $18.5 million to complete the OPCs design phase—and contains ‘‘language that would permit but not require a transfer of funding to the OPC program if it meets affordability requirements.’’... A major challenge to the USCG’s modernization effort continues to be the budget. A five year capital investment plan (CIP) for FY 2013 included $7.6 billion. However, the agency’s five year CIP for FY 2014 was reduced by one third to $5.1 billion. AC&I funding of just over $1 billion per year will certainly slow the USCG’s recapitalization efforts and result in the continued degradation of overall mission performance. (Pages 35) Conference H.R. 4188, as described by Representative Garamendi (Congressional Record, daily edition, December 10, 2015, p. H9240), was “developed over the course of several months of negotiation within this House and with that other body [i.e., the Senate].” H.R. 4188 was introduced in the Congressional Research Service 36 Coast Guard Cutter Procurement: Background and Issues for Congress House on December 8, 2015, and considered and passed by the House under suspension of the rules on December 10, 2015. Section 204 of H.R. 4188 includes acquisition reform measures. Section 204(c) states: (c) Days away from homeport.—Not later than 1 year after the date of the enactment of this Act, the Commandant of the Coast Guard shall— (1) implement a standard for tracking operational days at sea for Coast Guard cutters that does not include days during which such cutters are undergoing maintenance or repair; and (2) notify the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Commerce, Science, and Transportation of the Senate of the standard implemented under paragraph (1). Section 204(e) states: (e) Long-Term major acquisitions plan.—Section 2903 of title 14, United States Code, as redesignated and otherwise amended by this Act, is further amended— (1) by redesignating subsection (e) as subsection (g); and (2) by inserting after subsection (d) the following: “(e) Long-Term major acquisitions plan.—Each report under subsection (a) shall include a plan that describes for the upcoming fiscal year, and for each of the 20 fiscal years thereafter— “(1) the numbers and types of cutters and aircraft to be decommissioned; “(2) the numbers and types of cutters and aircraft to be acquired to— “(A) replace the cutters and aircraft identified under paragraph (1); or “(B) address an identified capability gap; and “(3) the estimated level of funding in each fiscal year required to— “(A) acquire the cutters and aircraft identified under paragraph (2); “(B) acquire related command, control, communications, computer, intelligence, surveillance, and reconnaissance systems; and “(C) acquire, construct, or renovate shoreside infrastructure. Author Contact Information Ronald O'Rourke Specialist in Naval Affairs rorourke@crs.loc.gov, 7-7610 Congressional Research Service 37

(millions of then-year dollars)

 

FY13

FY14

FY15

FY16

FY17

FY18

FY19

FY20

FY21

NSC program

     

FY13 budget

683

0

0

0

0

       

FY14 budget

 

616

710

38

0

45

     

FY15 budget

   

638

75

130

30

47

   

FY16 budget

     

91.4

132

95

30

15

 

FY17 budget

       

127

n/a

n/a

n/a

n/a

OPC program

     

FY13 budget

30

50

40

200

530

       

FY14 budget

 

25

65

200

530

430

     

FY15 budget

   

20

90

100

530

430

   

FY16 budget

     

18.5

100

530

430

430

 

FY17 budget

       

100

n/a

n/a

n/a

n/a

FRC program

     

FY13 budget

139

360

360

360

360

       

FY14 budget

 

75

110

110

110

110

     

FY15 budget

   

110

340

220

220

315

   

FY16 budget

     

340

325

240

240

325

 

FY17 budget

       

240

n/a

n/a

n/a

n/a

Total

     

FY13 budget

852

410

400

560

890

       

FY14 budget

 

716

885

348

640

585

     

FY15 budget

   

768

505

450

780

792

   

FY16 budget

     

449.9

557

865

700

370

 

FY17 budget

       

467

n/a

n/a

n/a

n/a

Source: Table prepared by CRS based on FY2013-FY2017 budget submissions. n/a means not available.

Issues for Congress Whether to Fund a 10th NSC in FY2017

One issue for Congress is whether to fund the acquisition of a 10th NSC in FY2017. The Coast Guard is not requesting procurement of a 10th NSC. Consequently, fully funding the acquisition of a 10th NSC in FY2017 would require providing roughly $700 million in unrequested acquisition funding.

Opponents of funding the acquisition of a 10th NSC in FY2017 could argue that the Coast Guard's program of record calls for only 8 NSCs, that the Coast Guard's fleet mix analyses (see "Planned NSC, OPC, and FRC Procurement Quantities" below, as well as Appendix A) have not shown a potential need for more than 9 NSCs, and that providing roughly $700 million in unrequested acquisition funding for a 10th NSC could require making offsetting reductions in other Coast Guard or DHS programs, potentially adversely affecting those programs, and resultant Coast Guard or DHS capabilities. Supporters of funding the acquisition of a 10th NSC in FY2017 could argue that the program of record requests only about 58% as many new cutters as the Coast Guard has calculated would be required to fully perform the Coast Guard's anticipated missions in coming years (see "Planned NSC, OPC, and FRC Procurement Quantities" below, as well as Appendix A), that a 10th NSC funded in FY2017 could be produced in an efficient heel-to-toe manner with the 9th NSC that was funded in FY2016, that a 10th NSC could be acquired together with the 9th NSC under a block buy contract,32 reducing acquisition costs for both ships, and that it could be more difficult to secure funding for the acquisition of a 10th NSC in FY2018 and beyond, due to funding requirements in those years for acquisition of OPCs. Number of FRCs to Fund in FY2017 Another issue for Congress is whether to fund the acquisition of four FRCs in FY2017, as requested, or some other number, such as six, which was the number projected for FY2017 under the Coast Guard's FY2016 budget submission. As shown in Table 1, the Coast Guard's FY2017 budget requests $240 million for the procurement of four FRCs, rather than the $325 million for the procurement of six more FRCs that was projected for FY2017 in the Coast Guard's FY2016 budget submission.

Supporters of funding the acquisition of six rather than four FRCs in FY2017 could argue that the Coast Guard's FY2016 budget submission projected the acquisition of six FRCs in FY2017, that procuring six rather than four would increase production economies of scale and thus reduce the unit acquisition cost of the ships, and that procuring six rather than four will help the Coast Guard to close more quickly a gap in patrol boat capacity that is limiting the Coast Guard's ability to interdict illegal drugs and carry out other missions.

Supporters of funding the acquisition of four FRCs in FY2017, as requested by the Coast Guard, could argue that adding the $85 million funding that would be needed to increase the FY2017 buy to six ships could require making offsetting reductions in other Coast Guard or DHS programs, potentially adversely affecting those programs, and resultant Coast Guard or DHS capabilities.

Annual or Multiyear Contracting for FRCs

Another issue for Congress is whether acquire the final 20 or 26 FRCs33 using annual contracting or multiyear contracting in the form of multiyear procurement (MYP) or block buy contracting. The Coast Guard currently plans to use a contract with options for procuring the final 26 FRCs. A contract with options may look like a form of multiyear contracting, but operates more like a series of annual contracts. Contracts with options do not achieve the reductions in acquisition costs that are possible with MYP and block buy contracting. Congress would need to grant authority to the Coast Guard to use MYP or block buy contracting in the FRC program.

At a February 3, 2016, hearing on Coast Guard cutter acquisition before the Coast Guard and Maritime Transportation Subcommittee of the House Transportation and Infrastructure Committee, CRS testified that using MYP or block buy contracting rather than a contract with options to procure the final 20 or 26 FRCs could reduce the total FRC acquisition costs by more than $100 million. CRS also testified that, as a general matter, using MYP or block buy contracting involves accepting certain tradeoffs, such as the following: reduced congressional control over year-to-year spending, and tying the hands of future Congresses; reduced flexibility for making changes in Coast Guard acquisition programs in response to unforeseen changes in strategic or budgetary circumstances (which can cause any needed funding reductions to fall more heavily on acquisition programs not covered by multiyear contracts); a potential need to shift funding from later fiscal years to earlier fiscal years to fund economic order quantity (EOQ) purchases (i.e., up-front batch purchases) of components; the risk of having to make penalty payments to shipbuilders if multiyear contracts need to be terminated due to unavailability of funds needed for the continuation of the contracts; and the risk that materials and components purchased for ships to be procured in future years might go to waste if those ships are not eventually procured.34

Annual or Multiyear Contracting for OPCs

Another issue for Congress, similar to the FRC issue above, is whether acquire OPCs using annual contracting or multiyear contracting in the form of multiyear procurement (MYP) or block buy contracting. The Coast Guard currently plans to use a contract with options for procuring the first 9 to 11 OPCs. As stated in the FRC section above, a contract with options may look like a form of multiyear contracting, but operates more like a series of annual contracts. Contracts with options do not achieve the reductions in acquisition costs that are possible with MYP and block buy contracting.

As noted earlier, Section 223 of the Howard Coble Coast Guard and Maritime Transportation Act of 2014 (S. 2444/P.L. 113-281 of December 18, 2014) grants authority to use MYP in the OPC program. MYP typically cannot be used on the first several ships in a shipbuilding program because the law that regulates MYP (10 USC 2306b) requires a stable design for an acquisition program to qualify for MYP. In a shipbuilding program, a stable design is typically demonstrated by completing the construction of the first ship in the class, by which time the first several ships in the class typically have been funded and put under contract. Block buy contracting, by comparison, can be used at the start of a shipbuilding program, beginning with the first ship. As with MYP, authority for using block buy contracting must be granted by Congress. Since Section 223 of P.L. 113-281 grants authority to use MYP but not block buy contracting, Congress would need to grant authority to the Coast Guard to use block buy contracting in the OPC program.35

At a February 3, 2016, hearing on Coast Guard cutter acquisition before the Coast Guard and Maritime Transportation Subcommittee of the House Transportation and Infrastructure Committee, CRS testified that if the Coast Guard were to use block buy contracting with economic order quantity (EOQ) purchases of components for acquiring the first several OPCs, and either MYP or block buy contracting with EOQ purchases for acquiring the remaining ships in the program, then the savings on the total acquisition cost of the 25 OPCs (compared to costs under contracts with options) could amount to roughly $1 billion. As with the FRCs discussed above, using MYP or block buy contracting involves accepting certain tradeoffs, such as the following: reduced congressional control over year-to-year spending, and tying the hands of future Congresses; reduced flexibility for making changes in Coast Guard acquisition programs in response to unforeseen changes in strategic or budgetary circumstances (which can cause any needed funding reductions to fall more heavily on acquisition programs not covered by multiyear contracts); a potential need to shift funding from later fiscal years to earlier fiscal years to fund economic order quantity (EOQ) purchases (i.e., up-front batch purchases) of components; the risk of having to make penalty payments to shipbuilders if multiyear contracts need to be terminated due to unavailability of funds needed for the continuation of the contracts; and the risk that materials and components purchased for ships to be procured in future years might go to waste if those ships are not eventually procured.36

Planned NSC, OPC, and FRC Procurement Quantities Another issue for Congress concerns the Coast Guard's planned NSC, OPC, and FRC procurement quantities. The POR's planned force of 91 NSCs, OPCs, and FRCs is about equal in number to the Coast Guard's legacy force of 90 high-endurance cutters, medium-endurance cutters, and 110-foot patrol craft. NSCs, OPCs, and FRCs, moreover, are to be individually more capable than the older ships they are to replace. Even so, Coast Guard studies have concluded that the planned total of 91 NSCs, OPCs, and FRCs would provide 58% of the cutters that would be needed to fully perform the service's statutory missions in coming years, in part because Coast Guard mission demands are expected to be greater in coming years than they were in the past. For further discussion of this issue, about which CRS first testified 2005,37 see Appendix A. Funding Level of Coast Guard's Acquisition Account

Another potential oversight issue for Congress concerns the funding level in the Coast Guard's acquisition account, known formally as the Acquisition, Construction, and Improvements (AC&I) account. The Coast Guard has testified that acquiring the ships and aircraft in its POR on a timely basis while also adequately funding other Coast Guard acquisition programs would require a funding level for the AC&I account of roughly $1.5 billion to $2.5 billion per year.

As shown in Table 2 below, the Administration's FY2013 budget submission programmed an average of about $1.5 billion per year in the AC&I account. As also shown in the table, subsequent budget submissions have reduced that figure to between $1 billion and $1.2 billion per year. Table 2. Funding in AC&I Account in FY2013-FY2017 Budgets

Millions of dollars, rounded to nearest tenth

 

FY13

FY14

FY15

FY16

FY17

FY18

FY19

FY20

FY21

Avg.

% change compared to avg. for FY13 budget

FY13 budget

1,217.3

1,429.5

1,619.9

1,643.8

1,722.0

       

1,526.5

FY14 budget

 

951.1

1,195.7

901.0

1,024.8

1,030.3

     

1,020.6

-33.1%

FY15 budget

   

1,084.2

1,103.0

1,128.9

1,180.4

1,228.7

   

1,145.0

-25.0%

FY16 budget

     

1,017.3

1,125.3

1,255.7

1,201.0

1,294.6

 

1,178.8

-22.8%

FY17 budget

       

1,136.8

n/a

n/a

n/a

n/a

n/a

n/a

Source: Table prepared by CRS based on Coast Guard FY2013-FY2017 budget submissions. n/a means not available.

At a June 26, 2013, hearing on Coast Guard acquisition before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, CRS testified that

The Coast Guard's FY2014 Five Year (FY2014-FY2018) CIP includes a total of about $5.1 billion in acquisition funding, which is about $2.5 billion, or about 33%, less than the total of about $7.6 billion that was included in the Coast Guard's FY2013 Five Year (FY2013-FY2017) CIP. (In the four common years of the two plans—FY2014-FY2017—the reduction in funding from the FY2013 CIP to the FY2014 CIP is about $2.3 billion, or about 37%.) This is one of the largest percentage reductions in funding that I have seen a five-year acquisition account experience from one year to the next in many years.

About twenty years ago, in the early 1990s, Department of Defense (DOD) five-year procurement plans were reduced sharply in response to the end of the Cold War—a large-scale change in the strategic environment that led to a significant reduction in estimated future missions for U.S. military forces. In contrast to that situation, there has been no change in the Coast Guard's strategic environment since last year that would suggest a significant reduction in estimated future missions for the Coast Guard.38

For further discussion of this issue, see Appendix B. OPC Program: Cost, Design, and Acquisition Strategy

Another potential oversight issue for Congress concerns the cost, design, and acquisition strategy for the OPC. Potential oversight questions for Congress include the following:

  • Has the Coast Guard fully incorporated into the OPC acquisition strategy lessons learned from the NSC and FRC programs? What, in the Coast Guard's view, are those lessons?
  • As mentioned earlier, the Coast Guard's RFP for the OPC program establishes an affordability requirement of an average unit price of $310 million per ship, or less, in then-year dollars for ships 4 through 9 in the program (for the shipbuilder's portion of the total cost of the ship). How was the $310 million figure determined?
  • What process is the Coast Guard using to evaluate tradeoffs in OPC performance features against this target construction price? What performance features have been reduced or eliminated to meet the target construction price?
  • How much confidence does the Coast Guard have that the OPC that emerges from the tradeoff process could be built within the Coast Guard's target construction price?
  • As mentioned earlier, the Coast Guard plans to evaluate the preliminary and contract design (P&CD) proposals and then award one of the competitors a contract for detailed design development and ship construction. What process does the Coast Guard plan to use in evaluating the P&CD efforts? What evaluation factors does the Coast Guard plan to use, and how much weight will be assigned to each?

A January 16, 2015, press report states

Coast Guard Commandant Adm. Paul Zukunft on Thursday [January 15] said that his staff is currently reviewing the requirements for its Offshore Patrol Cutter (OPC) with affordability in mind.

The "biggest challenge that we're facing right now is that this will not be affordable," Zukunft said at the annual Surface Navy Association conference in Arlington, Va. "I've turned it back to industry…bring me a capable platform that is also affordable."

Zukunft, who became commandant last May, is doing more than leave it to industry to design and produce a new and affordable medium endurance cutter for the Coast Guard. He told Defense Daily after his speech that he directed his "staff do a deep scrub on every one of the line items and so there are some line items in there that struck me."

For example, he said, what is the required water pressure for firefighting? If the requirement is set too high, that affects "piping, it affects weight, [and] how big of a pump do you need." Zukunft said it's this level of detail that is being scrubbed to figure out what is needed.

Zukunft describe[d] the requirements review as an "open dialogue" that is "fully transparent" with the shipbuilders competing for the 25-ship OPC buy free to weigh in.

The "competitors are very incentivized to come up with an affordable product for us as well," Zukunft said.39

NSC Program: Initial Testing

Another potential oversight issue for Congress concerns the results of initial testing of the NSC. A January 2016 GAO report stated:

The U.S. Navy, the Coast Guard's independent test agent, completed initial testing for the National Security Cutter (NSC) in April 2014 and rated the NSC as operationally effective and suitable. Still, testing revealed 10 major deficiencies.... Initial testing is an event designed to verify performance of critical systems to ensure assets are capable of meeting mission requirements. The event tests critical operational issues and key performance parameters. The NSC fully met 12 of 19 key performance parameters. Tests of one key performance parameter, as well as other critical systems, were deferred to follow-on testing. The Coast Guard and the U.S. Navy disagree on the NSC's requirements for cutter boat operations. Without clear requirements the Navy and Coast Guard will not have a basis for determining actions to resolve any performance issues. Coast Guard officials acknowledged that clarifying these requirements would be beneficial.

The Coast Guard plans to begin follow-on testing in fall 2016. It must submit corrective action plans to the U.S. Navy to close any deficiencies. According to Coast Guard documentation, it may choose not to correct all deficiencies due to the cost of changes. Department of Homeland Security (DHS) acquisition guidance does not specify the timing of follow-on testing or the actions to be taken in response to the findings. Without a definite time frame DHS risks encountering the same problems as the NSC program experienced with future acquisitions and fielding assets without knowing the full capabilities.

During operations, the NSC has experienced performance issues that were not identified during initial testing, and the Coast Guard has planned design changes to some of the cutters' equipment.... However, the Coast Guard has not yet found the causes for problems affecting the NSC's propulsion systems. As a result of these and other equipment failures, the NSC has been operating in a degraded condition in some mission areas. DHS has no plans for additional acquisition review boards for the NSC, which would provide oversight going forward. Continued management-level oversight by DHS would help ensure that problems identified during testing and operations are addressed.40

NSC Program: Rotational Crewing

A March 2015 GAO report stated that

The Coast Guard has delayed the feasibility test for using the crew rotation concept (CRC) to achieve increased operational days at sea with its National Security Cutters (NSC) until 2019. In 2006, the Coast Guard decided to use the CRC for its NSCs and that implementation would begin in 2011. However, the Coast Guard has postponed CRC testing because of delays in NSC deliveries and needed structural enhancements. In fiscal year 2013, the Coast Guard began implementing an interim plan to increase the NSCs' operational performance, not by rotating crews, but by adding crew members to help bear the increased workload. However, the added crew members do not have the skill mix recommended by a 2011 manpower requirements analysis. Without the appropriate crew members with the right skill mix, the NSCs may not be able to complete all mission requirements or required maintenance.

The Coast Guard has not fully addressed a variety of risks that could affect the success of its planned CRC feasibility test and goal to increase NSC operational days away from home port (DAFHP) from 185 to 230 days per year using the CRC. Further, the Coast Guard could not provide us with complete details about whether the CRC plan, to be completed by the end of 2017, will include actions to address and effectively mitigate various risks, to include

• determining the appropriate number and skill mix of NSC crew members and support personnel and whether they will be in place in time for the CRC test;

• incorporating actual NSC maintenance needs when developing NSC maintenance schedules and goals;

• testing the CRC under realistic circumstances, such as addressing the misalignment of the crewing concept to be tested as compared to the NSC homeporting plan;

• addressing the potential impacts of wide variations between alternative deployment schedules using the CRC; and

• implementing a training infrastructure and providing training support for off-cycle rotating crews.

As the Coast Guard continues to develop its CRC plan, establishing interim milestones for carrying out the actions needed to address and effectively mitigate these risks would help ensure that it addresses the risks in a timely manner.

The Coast Guard's current measure does not accurately quantify the operational performance of the NSC fleet. The Coast Guard primarily uses the DAFHP measure across its major cutter fleet; however, this measure includes days when a cutter is undergoing maintenance away from its home port and, as a result, will likely overstate the number of operational days. The Coast Guard has known of the measure's limitation for years and is exploring alternatives. However, since the CRC plan is premised on achieving 230 DAFHP per year—and that other Coast Guard vessels, such as the Offshore Patrol Cutter, also plan to use the DAFHP metric—implementing alternative measures prior to CRC testing will better ensure the test results are benchmarked against a more appropriate goal to quantify the operational performance of its fleet of NSCs and its planned fleet of Offshore Patrol Cutters.41

Legislative Activity for FY2017 Summary of Appropriations Action on FY2017 Acquisition Funding Request Table 3 summarizes appropriations action on the Coast Guard's request for FY2017 acquisition funding for the NSC, OPC, and FRC programs. Table 3. Summary of Appropriations Action on FY2016 Acquisition Funding Request

Figures in millions of dollars, rounded to nearest tenth

Request

Request

House Appropriations Committee

Senate Appropriations Committee

Final

NSC program

127.0

     

OPC program

100.0

     

FRC program

240.0

     

TOTAL

467.0

     

Source: Table prepared by CRS based on Coast Guard's FY2017 budget submission and committee and conference reports.

Appendix A. Planned NSC, OPC, and FRC Procurement Quantities

This appendix provides further discussion on the issue of the Coast Guard's planned NSC, OPC, and FRC procurement quantities.

The Coast Guard estimates that with the POR's planned force of 91 NSCs, OPCs, and FRCs, the service would have capability or capacity gaps42 in 6 of its 11 statutory missions—search and rescue (SAR); defense readiness; counter-drug operations; ports, waterways, and coastal security (PWCS); protection of living marine resources (LMR); and alien migrant interdiction operations (AMIO). The Coast Guard judges that some of these gaps would be "high risk" or "very high risk."

Public discussions of the POR frequently mention the substantial improvement that the POR force would represent over the legacy force. Only rarely, however, have these discussions explicitly acknowledged the extent to which the POR force would nevertheless be smaller in number than the force that would be required, by Coast Guard estimate, to fully perform the Coast Guard's statutory missions in coming years. Discussions that focus on the POR's improvement over the legacy force while omitting mention of the considerably larger number of cutters that would be required, by Coast Guard estimate, to fully perform the Coast Guard's statutory missions in coming years could encourage audiences to conclude, contrary to Coast Guard estimates, that the POR's planned force of 91 cutters would be capable of fully performing the Coast Guard's statutory missions in coming years.

In a study completed in December 2009 called the Fleet Mix Analysis (FMA) Phase 1, the Coast Guard calculated the size of the force that in its view would be needed to fully perform the service's statutory missions in coming years. The study refers to this larger force as the objective fleet mix. Table A-1 compares planned numbers of NSCs, OPCs, and FRCs in the POR to those in the objective fleet mix. Table A-1. Program of Record Compared to Objective Fleet Mix

From Fleet Mix Analysis Phase 1 (2009)

Ship type

Program of Record (POR)

Objective Fleet Mix From FMA Phase 1

Objective Fleet Mix compared to POR

     

Number

%

NSC

8

9

+1

+13%

OPC

25

57

+32

+128%

FRC

58

91

+33

+57%

Total

91

157

+66

+73%

Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13.

As can be seen in Table A-1, the objective fleet mix includes 66 additional cutters, or about 73% more cutters than in the POR. Stated the other way around, the POR includes about 58% as many cutters as the objective fleet mix. As intermediate steps between the POR force and the objective fleet mix, FMA Phase 1 calculated three additional forces, called FMA-1, FMA-2, and FMA-3. (The objective fleet mix was then relabeled FMA-4.) Table A-2 compares the POR to FMAs 1 through 4. Table A-2. POR Compared to FMAs 1 Through 4

From Fleet Mix Analysis Phase 1 (2009)

Ship type

Program of Record (POR)

FMA-1

FMA-2

FMA-3

FMA-4 (Objective Fleet Mix)

NSC

8

9

9

9

9

OPC

25

32

43

50

57

FRC

58

63

75

80

91

Total

91

104

127

139

157

Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13.

FMA-1 was calculated to address the mission gaps that the Coast Guard judged to be "very high risk." FMA-2 was calculated to address both those gaps and additional gaps that the Coast Guard judged to be "high risk." FMA-3 was calculated to address all those gaps, plus gaps that the Coast Guard judged to be "medium risk." FMA-4—the objective fleet mix—was calculated to address all the foregoing gaps, plus the remaining gaps, which the Coast Guard judge to be "low risk" or "very low risk." Table A-3 shows the POR and FMAs 1 through 4 in terms of their mission performance gaps. Table A-3. Force Mixes and Mission Performance Gaps

From Fleet Mix Analysis Phase 1 (2009)—an X mark indicates a mission performance gap

Missions with performance gaps

Risk levels of these performance gaps

Program of Record (POR)

FMA-1

FMA-2

FMA-3

FMA-4 (Objective Fleet Mix)

Search and Rescue (SAR) capability

Very high

X

       

Defense Readiness capacity

Very high

X

       

Counter Drug capacity

Very high

X

        Ports, Waterways, and Coastal Security (PWCS) capacitya

High

X

X

      Living Marine Resources (LMR) capability and capacitya

High

X

X

   

[all gaps addressed]

PWCS capacityb

Medium

X

X

X

    LMR capacityc

Medium

X

X

X

    Alien Migrant Interdiction Operations (AMIO) capacityd

Low/very low

X

X

X

X

  PWCS capacitye

Low/very low

X

X

X

X

 

Source: Fleet Mix Analysis Phase 1, Executive Summary, page ES-11 through ES-13.

Notes: In the first column, The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed.

a. This gap occurs in the Southeast operating area (Coast Guard Districts 7 and 8) and the Western operating area (Districts 11, 13, and 14). b. This gap occurs in Alaska. c. This gap occurs in Alaska and in the Northeast operating area (Districts 1 and 5). d. This gap occurs in the Southeast and Western operating areas. e. This gap occurs in the Northeast operating area. Figure A-1, taken from FMA Phase 1, depicts the overall mission capability/performance gap situation in graphic form. It appears to be conceptual rather than drawn to precise scale. The black line descending toward 0 by the year 2027 shows the declining capability and performance of the Coast Guard's legacy assets as they gradually age out of the force. The purple line branching up from the black line shows the added capability from ships and aircraft to be procured under the POR, including the 91 planned NSCs, OPCs, and FRCs. The level of capability to be provided when the POR force is fully in place is the green line, labeled "2005 Mission Needs Statement." As can be seen in the graph, this level of capability is substantially below a projection of Coast Guard mission demands made after the terrorist attacks of September 11, 2001 (the red line, labeled "Post-9/11 CG Mission Demands"), and even further below a Coast Guard projection of future mission demands (the top dashed line, labeled "Future Mission Demands"). The dashed blue lines show future capability levels that would result from reducing planned procurement quantities in the POR or executing the POR over a longer time period than originally planned.

Figure A-1. Projected Mission Demands vs. Projected Capability/Performance

From Fleet Mix Analysis Phase 1, Executive Summary

Source: Fleet Mix Analysis Phase 1, Executive Summary, Figure ES-1 on p. ES-2.

FMA Phase 1 was a fiscally unconstrained study, meaning that the larger force mixes shown in Table A-2 were calculated primarily on the basis of their capability for performing missions, rather than their potential acquisition or life-cycle operation and support (O&S) costs. Although the FMA Phase 1 was completed in December 2009, the figures shown in Table A-2 were generally not included in public discussions of the Coast Guard's future force structure needs until April 2011, when GAO presented them in testimony.43 GAO again presented them in a July 2011 report.44 The Coast Guard completed a follow-on study, called Fleet Mix Analysis (FMA) Phase 2, in May 2011. Among other things, FMA Phase 2 includes a revised and updated objective fleet mix called the refined objective mix. Table A-4 compares the POR to the objective fleet mix from FMA Phase 1 and the refined objective mix from FMA Phase 2. Table A-4. POR Compared to Objective Mixes in FMA Phases 1 and 2

From Fleet Mix Analysis Phase 1 (2009) and Phase 2 (2011)

Ship type

Program of Record (POR)

Objective Fleet Mix from FMA Phase 1

Refined Objective Mix from FMA Phase 2

NSC

8

9

9

OPC

25

57

49

FRC

58

91

91

Total

91

157

149

Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13, and Fleet Mix Analysis Phase 2, Table ES-2 on p. iv.

As can be seen in Table A-4, compared to the objective fleet mix from FMA Phase 1, the refined objective mix from FMA Phase 2 includes 49 OPCs rather than 57. The refined objective mix includes 58 additional cutters, or about 64% more cutters than in the POR. Stated the other way around, the POR includes about 61% as many cutters as the refined objective mix. Compared to the POR, the larger force mixes shown in Table A-2 and Table A-4 would be more expensive to procure, operate, and support than the POR force. Using the average NSC, OPC, and FRC procurement cost figures presented earlier (see "Background"), procuring the 58 additional cutters in the Refined Objective Mix from FMA Phase 2 might cost an additional $10.7 billion, of which most (about $7.8 billion) would be for the 24 additional FRCs. (The actual cost would depend on numerous factors, such as annual procurement rates.) O&S costs for these 58 additional cutters over their life cycles (including crew costs and periodic ship maintenance costs) would require billions of additional dollars.45 The larger force mixes in the FMA Phase 1 and 2 studies, moreover, include not only increased numbers of cutters, but also increased numbers of Coast Guard aircraft. In the FMA Phase 1 study, for example, the objective fleet mix included 479 aircraft—93% more than the 248 aircraft in the POR mix. Stated the other way around, the POR includes about 52% as many aircraft as the objective fleet mix. A decision to procure larger numbers of cutters like those shown in Table A-2 and Table A-4 might thus also imply a decision to procure, operate, and support larger numbers of Coast Guard aircraft, which would require billions of additional dollars. The FMA Phase 1 study estimated the procurement cost of the objective fleet mix of 157 cutters and 479 aircraft at $61 billion to $67 billion in constant FY2009 dollars, or about 66% more than the procurement cost of $37 billion to $40 billion in constant FY2009 dollars estimated for the POR mix of 91 cutters and 248 aircraft. The study estimated the total ownership cost (i.e., procurement plus life-cycle O&S cost) of the objective fleet mix of cutters and aircraft at $201 billion to $208 billion in constant FY2009 dollars, or about 53% more than the total ownership cost of $132 billion to $136 billion in constant FY2009 dollars estimated for POR mix of cutters and aircraft.46

A December 7, 2015, press report states:

The Coast Guard's No. 2 officer said the small size and advanced age of its fleet is limiting the service's ability to carry out crucial missions in the Arctic and drug transit zones or to meet rising calls for presence in the volatile South China Sea.

"The lack of surface vessels every day just breaks my heart," VADM Charles Michel, the Coast Guard's vice commandant, said Dec. 7.

Addressing a forum on American Sea Power sponsored by the U.S. Naval Institute at the Newseum, Michel detailed the problems the Coast Guard faces in trying to carry out its missions of national security, law enforcement and maritime safety because of a lack of resources.

"That's why you hear me clamoring for recapitalization," he said.

Michel noted that China's coast guard has a lot more ships than the U.S. Coast Guard has, including many that are larger than the biggest U.S. cutter, the 1,800-ton [sic:4,800-ton] National Security Cutter. China is using those white-painted vessels rather than "gray-hull navy" ships to enforce its claims to vast areas of the South China Sea, including reefs and shoals claimed by other nations, he said.

That is a statement that the disputed areas are "so much our territory, we don't need the navy. That's an absolutely masterful use of the coast guard," he said.

The superior numbers of Chinese coast guard vessels and its plans to build more is something, "we have to consider when looking at what we can do in the South China Sea," Michel said.

Although they have received requests from the U.S. commanders in the region for U.S. Coast Guard cutters in the South China Sea, "the commandant had to say 'no'. There's not enough to go around," he said.47

Potential oversight questions for Congress include the following:

Under the POR force mix, how large a performance gap, precisely, would there be in each of the missions shown in Table A-3? What impact would these performance gaps have on public safety, national security, and protection of living marine resources?
  • How sensitive are these performance gaps to the way in which the Coast Guard translates its statutory missions into more precise statements of required mission performance?
  • Given the performance gaps shown in Table A-3, should planned numbers of Coast Guard cutters and aircraft be increased, or should the Coast Guard's statutory missions be reduced, or both? How much larger would the performance gaps in Table A-3 be if planned numbers of Coast Guard cutters and aircraft are reduced below the POR figures? Has the executive branch made sufficiently clear to Congress the difference between the number of ships and aircraft in the POR force and the number that would be needed to fully perform the Coast Guard's statutory missions in coming years? Why has public discussion of the POR focused mostly on the capability improvement it would produce over the legacy force and rarely on the performance gaps it would have in the missions shown in Table A-3?Appendix B. Funding Levels in AC&I Account

    This appendix provides further discussion of the issue of funding levels in the Coast Guard's Acquisition, Construction, and Improvements (AC&I) account.

    The Coast Guard has testified that funding the AC&I account at a level of about $1 billion to $1.2 billion per year would make it difficult to fund various Coast Guard acquisition projects, including a new polar icebreaker, and improvements to Coast Guard shore installations. Coast Guard plans call for procuring OPCs at an eventual rate of two per year. If each OPC costs roughly $400 million, procuring two OPCs per year in an AC&I account of about $1 billion to $1.2 billion per year would leave about $200 million to $400 million per year for all other AC&I-funded programs.

    At an October 4, 2011, hearing on the Coast Guard's major acquisition programs before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, the following exchange occurred:

    REPRESENATIVE FRANK LOBIONDO:

    Can you give us your take on what percentage of value must be invested each year to maintain current levels of effort and to allow the Coast Guard to fully carry out its missions?

    ADMIRAL ROBERT J. PAPP, COMMANDANT OF THE COAST GUARD:

    I think I can, Mr. Chairman. Actually, in discussions and looking at our budget—and I'll give you rough numbers here, what we do now is we have to live within the constraints that we've been averaging about $1.4 billion in acquisition money each year.

    If you look at our complete portfolio, the things that we'd like to do, when you look at the shore infrastructure that needs to be taken care of, when you look at renovating our smaller icebreakers and other ships and aircraft that we have, we've done some rough estimates that it would really take close to about $2.5 billion a year, if we were to do all the things that we would like to do to sustain our capital plant.

    So I'm just like any other head of any other agency here, as that the end of the day, we're given a top line and we have to make choices and tradeoffs and basically, my tradeoffs boil down to sustaining frontline operations balancing that, we're trying to recapitalize the Coast Guard and there's where the break is and where we have to define our spending.48

    An April 18, 2012, blog entry stated:

    If the Coast Guard capital expenditure budget remains unchanged at less than $1.5 billion annually in the coming years, it will result in a service in possession of only 70 percent of the assets it possesses today, said Coast Guard Rear Adm. Mark Butt.

    Butt, who spoke April 17 [2012] at [a] panel [discussion] during the Navy League Sea Air Space conference in National Harbor, Md., echoed Coast Guard Commandant Robert Papp in stating that the service really needs around $2.5 billion annually for procurement.49

    At a May 9, 2012, hearing on the Coast Guard's proposed FY2013 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified, "I've gone on record saying that I think the Coast Guard needs closer to $2 billion dollars a year [in acquisition funding] to recapitalize—[to] do proper recapitalization."50

    At a May 14, 2013, hearing on the Coast Guard's proposed FY2014 budget before the Homeland Security Subcommittee of the Senate Appropriations Committee, Admiral Papp stated the following regarding the difference between having about $1.0 billion per year rather than about $1.5 billion per year in the AC&I account:

    Well, Madam Chairman, $500 million—a half a billion dollars—is real money for the Coast Guard. So, clearly, we had $1.5 billion in the [FY]13 budget. It doesn't get everything I would like, but it—it gave us a good start, and it sustained a number of projects that are very important to us.

    When we go down to the $1 billion level this year, it gets my highest priorities in there, but we have to either terminate or reduce to minimum order quantities for all the other projects that we have going.

    If we're going to stay with our program of record, things that have been documented that we need for our service, we're going to have to just stretch everything out to the right. And when we do that, you cannot order in economic order quantities. It defers the purchase. Ship builders, aircraft companies—they have to figure in their costs, and it inevitably raises the cost when you're ordering them in smaller quantities and pushing it off to the right.

    Plus, it almost creates a death spiral for the Coast Guard because we are forced to sustain older assets—older ships and older aircraft—which ultimately cost us more money, so it eats into our operating funds, as well, as we try to sustain these older things.

    So, we'll do the best we can within the budget. And the president and the secretary have addressed my highest priorities, and we'll just continue to go on the—on an annual basis seeing what we can wedge into the budget to keep the other projects going.51

    At a March 12, 2014, hearing on the Coast Guard's proposed FY2015 budget before the Homeland Security subcommittee of the House Appropriations Committee, Admiral Papp stated:

    Well, that's what we've been struggling with, as we deal with the five-year plan, the capital investment plan, is showing how we are able to do that. And it will be a challenge, particularly if it sticks at around $1 billion [per year]. As I've said publicly, and actually, I said we could probably—I've stated publicly before that we could probably construct comfortably at about 1.5 billion [dollars] a year. But if we were to take care of all the Coast Guard's projects that are out there, including shore infrastructure that that fleet that takes care of the Yemen [sic: inland] waters is approaching 50 years of age, as well, but I have no replacement plan in sight for them because we simply can't afford it. Plus, we need at some point to build a polar icebreaker. Darn tough to do all that stuff when you're pushing down closer to 1 billion [dollars per year], instead of 2 billion [dollars per year].

    As I said, we could fit most of that in at about the 1.5 billion [dollars per year] level, but the projections don't call for that. So we are scrubbing the numbers as best we can.52

    At a March 24, 2015, hearing on the Coast Guard's proposed FY2016 budget before the Homeland Security subcommittee of the House Appropriations Committee, Admiral Paul Zukunft, Admiral Papp's successor as Commandant of the Coast Guard, stated:

    I look back to better years in our acquisition budget when we had a—an acquisition budget of—of $1.5 billion. That allows me to move these programs along at a much more rapid pace and, the quicker I can build these at full-rate production, the less cost it is in the long run as well. But there's an urgent need for me to be able to deliver these platforms in a timely and also in an affordable manner. But to at least have a reliable and a predictable acquisition budget would make our work in the Coast Guard much easier. But when we see variances of—of 30, 40% over a period of three or four years, and not knowing what the Budget Control Act may have in store for us going on, yes, we are treading water now but any further reductions, and now I am—I am beyond asking for help. We are taking on water.53

    Although the annual amounts of acquisition funding that the Coast Guard has received in recent years are one potential guide to what Coast Guard acquisition funding levels might or should be in coming years, there may be other potential guides. For example, one could envision potential guides that focus on whether Coast Guard funding for ship acquisition and sustainment is commensurate with Coast Guard funding for the personnel that in many cases will operate the ships. Observations that might be made in connection with this example based on the Coast Guard and Navy budget submissions include the following:

    • Using figures from the FY2014 budget submission, the Coast Guard has about 12.9% as many active-duty personnel as the Navy.54 If the amount of funding for the surface ship acquisition and sustainment part of the AC&I account were equivalent to 12.9% of the amount of funding in the Navy's shipbuilding account, the surface ship acquisition and sustainment part of the AC&I account would be about $1.8 billion per year.55 Navy surface ship acquisition, unlike Coast Guard surface ship acquisition, includes substantial numbers of large and complex ships, including nuclear-powered aircraft carriers, highly capable surface combatants, and large amphibious and auxiliary ships. Accounting for this difference in Navy and Coast Guard surface ship acquisition by reducing the $1.8 billion figure by, say, one-half or one-third would produce an adjusted figure of about $900 million to about $1.2 billion per year for surface ship acquisition and sustainment.
    • Again using figures from the FY2014 budget submission, funding in the Navy's shipbuilding account is equivalent to about 51% of the Navy's funding for active-duty personnel.56 If Coast Guard funding for surface ship acquisition and sustainment were equivalent to 51% of Coast Guard funding for military pay and allowances, the surface ship acquisition and sustainment part of the AC&I account would be about $1.7 billion per year.57 Reducing the $1.8 billion figure by, say, one-half or one-third to account for differences in the types of surface ships acquired by the Navy and Coast Guard (see previous bullet point) would produce an adjusted figure of about $850 million to about $1.1 billion per year for surface ship acquisition and sustainment.

    Author Contact Information

    [author name scrubbed], Specialist in Naval Affairs ([email address scrubbed], [phone number scrubbed])

    Footnotes

    1.

    The earlier report was CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by [author name scrubbed]. From the late 1990s until 2007, the Coast Guard's efforts to acquire NSCs, OPCs, and FRCs were parts of a larger, integrated Coast Guard acquisition effort aimed at acquiring several new types of cutters and aircraft that was called the Integrated Deepwater System (IDS) program, or Deepwater for short. In 2007, the Coast Guard broke up the Deepwater effort into a series of individual cutter and aircraft acquisition programs, but continued to use the term Deepwater as a shorthand way of referring collectively to these now-separated programs. In its FY2012 budget submission, the Coast Guard stopped using the term Deepwater entirely as a way of referring to these programs. Congress, in acting on the Coast Guard's proposed FY2012 budget, did not object to ending the use of the term Deepwater. Reflecting this development, CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by [author name scrubbed], was archived in early 2012, following final congressional action on the FY2012 budget, and remains available to congressional readers as a source of historical reference information on Deepwater acquisition efforts.

    2.

    See CRS Testimony TE10004, The Status of Coast Guard Cutter Acquisition Programs, by [author name scrubbed].

    3.

    CRS Report RL34391, Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress, by [author name scrubbed].

    4.

    In the designations WHEC, WMEC, and WPB, W means Coast Guard ship, HEC stands for high-endurance cutter, MEC stands for medium-endurance cutter, and PB stands for patrol boat.

    5.

    Hamilton-class cutters are 378 feet long and have a full load displacement of about 3,400 tons.

    6.

    Famous class cutters are 270 feet long and have a full load displacement of about 1,800 tons.

    7.

    Reliance class cutters are 210 feet long and have a full load displacement of about 1,100 tons.

    8.

    The two one-of-a-kind cutters are the Acushnet (WMEC-167), which originally entered service with the Navy in 1944, and the Alex Haley (WMEC-39), which originally entered service with the Navy in 1971. The Acushnet served in the Navy from until 1946, when it was transferred to the Coast Guard. The ship was about 214 feet long and had a displacement of about 1,700 tons. The Alex Haley served in the Navy until 1996. It was transferred to the Coast Guard in 1997, converted into a cutter, and re-entered service with the Coast Guard in 1999. It is 282 feet long and has a full load displacement of about 2,900 tons.

    9.

    Island-class boats are 110 feet long and have a full load displacement of about 135 to 170 tons.

    10.

    Government Accountability Office, Coast Guard[:]Legacy Vessels' Declining Conditions Reinforce Need for More Realistic Operational Targets, GAO-12-741, July 2012, 71 pp.

    11.

    The four statutory Coast Guard missions that are not to be routinely performed by NSCs, OPCs, and FRCs are marine safety, aids to navigation, marine environmental protection, and ice operations. These missions are performed primarily by other Coast Guard ships. The Coast Guard states, however, that "while [NSCs, OPCs, and FRCs] will not routinely conduct [the] Aids to Navigation, Marine Safety, or Marine Environmental Protection missions, they may periodically be called upon to support these missions (i.e., validate the position of an Aid to Navigation, transport personnel or serve as a Command and Control platform for a Marine Safety or Marine Environmental Response mission, etc.)." (Source: Coast Guard information paper provided to CRS on June 1, 2012.)

    12.

    In the designation WMSL, W means Coast Guard ship and MSL stands for maritime security cutter, large. NSCs are being named for legendary Coast Guard personnel.

    13.

    The Coast Guard's three polar icebreakers are much larger than NSCs, but are designed for a more specialized role of operations in polar waters.

    14.

    The NSC design is 418 feet long and has a full load displacement of about 4,500 tons. The displacement of the NSC design is about equal to that of Navy's Oliver Hazard Perry (FFG-7) class frigates, which are 453 feet long and have a full load displacement of about 4,200 tons.

    15.

    U.S. Coast Guard description of the NSC, accessed April 26, 2013, at http://www.uscg.mil/acquisition/nsc/features.asp.

    16.

    "Acquisition Update: Coast Guard Commissions Fifth National Security Cutter," August 10, 2015, accessed September 24, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/nsc081015.asp.

    17.

    "Acquisition Update: Sixth National Security Cutter Launched," September 15, 2015, accessed September 24, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/nsc091515.asp. See also "Acquisition Update: Coast Guard Christens Sixth National Security Cutter," November 16, 2015, accessed January 27, 2016, at http://www.uscg.mil/acquisition/newsroom/updates/nsc111615.asp.

    18.

    Coast Guard fact sheet on the OPC accessed April 26, 2013, at http://www.uscg.mil/acquisition/opc/pdf/opc.pdf.

    19.

    Source: Section C.5 of the RFP, accessed October 31, 2012, at http://www.uscg.mil/ACQUISITION/newsroom/updates/opc092512.asp.

    20.

    GFE is equipment that the government procures and then delivers to the shipyard for installation on the ship.

    21.

    Source: Coast Guard emails to CRS dated June 25, 2013.

    22.

    Source: Section C.1 of the RFP, accessed March 26, 2013, at http://www.uscg.mil/ACQUISITION/newsroom/updates/opc092512.asp.

    23.

    The firms were the following: Bollinger Shipyards of Lockport, LA; Eastern Shipbuilding Group of Panama City, FL; General Dynamics Bath Iron Works (GD/BIW) of Bath, ME; Huntington Ingalls Industries (HII) of Pascagoula, MS; Marinette Marine Corporation of Marinette, WS; General Dynamics National Steel and Shipbuilding Company (GD/NASSCO) of San Diego, CA; Vigor Shipyards of Seattle, WA; and VT Halter Marine of Pascagoula, MS. (Source: U. S. Coast Guard Offshore Patrol Cutter (OPC) List of Interested Contractors Updated July 2012, accessed online October 23, 2012, at http://www.uscg.mil/ACQUISITION/opc/pdf/companiesinterested.pdf; and Kevin Brancato and Anne Laurent, Coast Guard's $12 Billion Cutter Competition Spurs Eight Shipyards to Dive In, Bloomberg Government Study, November 8, 2012, 6 pp. The Coast Guard document states that these firms "expressed interest in the Offshore Patrol Cutter acquisition and have agreed to their names provided on the Coast Guard website." See also Stew Magnuson, "New Coast Guard Cutter Sparks Fierce Competition Among Shipbuilders," National Defense (www.nationaldefensemagazine.org), April 2013, accessed March 26, 2013, at http://www.nationaldefensemagazine.org/archive/2013/April/Pages/NewCoastGuardCutterSparksFierceCompetitionAmongShipbuilders.aspx.)

    24.

    "Acquisition Update: U.S. Coast Guard Awards Three Contracts for Offshore Patrol Cutter Preliminary and Contract Design," February 11, 2014, accessed February 14, 2014, at http://www.uscg.mil/hq/cg9/newsroom/updates/opc021114.asp.

    HII and VT Halter Marine reportedly filed protests of the Coast Guard's award decision on February 24 and 25, respectively. The Coast Guard issued stop work orders to Bollinger, Eastern, and GD/BIW pending GAO's rulings on the protests. (Calvin Biesecker, "Coast Guard Issues Stop Work Orders On OPC Following Protests," Defense Daily, February 28, 2014: 2-3. See also Christopher P. Cavas, "Ingalls Protesting US Coast Guard Cutter Contract," DefenseNews.com, February 26, 2014.) On June 5, 2014, it was reported that GAO had rejected the protests, and that the Coast Guard had directed Bollinger, Eastern, and GD/BIW to resume their work. (Calvin Biesecker, "Coast Guard Directs Design Work Continue On OPC After GAO Denies Protests," Defense Daily, June 5, 2014: 1; Christopher P. Cavas, "US Coast Guard Cutter Award Upheld," Defense News (www.defensenews.com), June 5, 2014. For the text of the decision, see Government Accountability Office, Decision in the Matter of Huntington Ingalls Industries, Inc.; VT Halter Marine, Inc., June 2, 2014.)

    25.

    "Offshore Patrol Cutter," last modified May 27, 2015, accessed September 24, 2015, at http://www.uscg.mil/acquisition/opc/default.asp.

    26.

    FRCs are 154 feet long and have a full load displacement of 353 tons.

    27.

    Department of Homeland Security, United States Coast Guard, Fiscal Year 2013 Congressional Justification, p. CG-AC&I-28 (pdf page 182 of 400).

    28.

    "Acquisition Update: Sentinel-class Fast Response Cutter Project Achieves Acquisition Milestone," September 18, 2013, accessed November 18, 2013, at http://www.uscg.mil/acquisition/newsroom/updates/frc092413.asp.

    29.

    "Acquisition Update: Coast Guard Commissions 16th Fast Response Cutter," March 14, 2016, accessed March 22, 2016, at http://www.uscg.mil/acquisition/newsroom/updates/frc031416.asp.

    30.

    "Acquisition Update: Coast Guard Exercises Contract Option for Fast Response Cutters 31 And 32," February 27, 2015, accessed March 6, 2015, at http://www.uscg.mil/acquisition/newsroom/updates/frc022815.asp.

    31.

    "Acquisition Update: Coast Guard Issues Request for Proposal for Fast Response Cutters 33-58," February 27, 2015, accessed March 6, 2015, http://www.uscg.mil/acquisition/newsroom/updates/frc022915.asp.

    32.

    For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress, by [author name scrubbed] and [author name scrubbed], and CRS Testimony TE10004, The Status of Coast Guard Cutter Acquisition Programs, by [author name scrubbed].

    33.

    The difference between 20 and 26 relates to whether the six FRCs funded in FY2016 are included in this discussion.

    34.

    See CRS Testimony TE10004, The Status of Coast Guard Cutter Acquisition Programs, by [author name scrubbed].

    35.

    36.

    See CRS Testimony TE10004, The Status of Coast Guard Cutter Acquisition Programs, by [author name scrubbed].

    37.

    See Statement of [author name scrubbed], Specialist in National Defense, Congressional Research Service, Before the Senate Commerce, Science, and Transportation Committee, Subcommittee on Fisheries and the Coast Guard, Hearing on The Coast Guard's Revised Deepwater Implementation Plan, June 21, 2005, pp. 1-5.

    38.

    Statement of [author name scrubbed], Specialist in Naval Affairs, Congressional Research Service, before the House Transportation and Infrastructure Committee, Subcommittee on Coast Guard and Maritime Transportation, Hearing on Coast Guard Readiness: Examining Cutter, Aircraft, and Communications Needs, June 26, 2013, p. 1.

    39.

    Calvin Biesecker, "With Affordability In Mind, Zukunft Reviewing OPC Requirements," Defense Daily, January 16, 2015: 4.

    40.

    Government Accountability Office, National Security Cutter[:]Enhanced Oversight Needed to Ensure Problems Discovered during Testing and Operations Are Addressed, GAO-16-148, January 2016, summary page.

    41.

    Government Accountability Office, Coast Guard[:] Timely Actions Needed to Address Risks in Using Rotational Crews, GAO-15-195, summary page.

    42.

    The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed.

    43.

    Government Accountability Office, Coast Guard[:]Observations on Acquisition Management and Efforts to Reassess the Deepwater Program, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of John P. Hutton, Director Acquisition and Sourcing Management, GAO-11-535T, April 13, 2011, p. 10.

    44.

    Government Accountability Office, Coast Guard[:]Action Needed As Approved Deepwater Program Remains Unachievable, GAO-11-743, July 2011, p. 46.

    45.

    The FMA Phase 1 and Phase 2 studies present acquisition and life-cycle ownership cost calculations for force mixes that include not only larger numbers of NSC, OPCs, and FRCs, but corresponding larger numbers of Coast Guard aircraft.

    46.

    Fleet Mix Analysis Phase 1, Executive Summary, Table ES-11 on page ES-19, and Table ES-10 on page ES-18. The life-cycle O&S cost was calculated through 2050.

    47.

    Otto Kreisher, "'Not Enough' USCG Vessels to Meet Demand for Presence in South China Sea, Arctic," Seapower, December 7, 2015.

    48.

    Source: Transcript of hearing.

    49.

    David Perera, "The Coast Guard Is Shrinking," FierceHomelandSecurity.com, April 18, 2012, accessed July 20, 2012, at http://www.fiercehomelandsecurity.com/story/coast-guard-shrinking/2012-04-18.

    50. Source: transcript of hearing. Papp may have been referring to remarks he made to the press before giving his annual state of the Coast Guard speech on February 23, 2012, in which reportedly stated that the Coast Guard would require about $2 billion per year in acquisition funding to fully replace its current assets. (See Adam Benson, "Coast Guard Cutbacks Will Cost 1,000 Jobs," Norwich Bulletin, February 23, 2012, accessed May 31, 2012, at http://www.norwichbulletin.com/news/x1138492141/Coast-Guard-cutbacks-will-cost-1-000-jobs#axzz1wSDAFCzX. See also "Coast Guard Leader Calls For More Ships," MilitaryFeed.com, February 24, 2012, accessed May 31, 2012, at http://militaryfeed.com/coast-guard-leader-calls-for-more-ships-5/; Associated Press, "Coast Guard Commandant Calls for New Ships," TheLog.com, March 10, 2012, accessed May 31, 2012, at http://www.thelog.com/SNW/Article/Coast-Guard-Commandant-Calls-for-New-Ships-to-Replace-Aging-Fleet; Mickey McCarter, "Congress Poised to Give Coast Guard More Money Than Requested for FY 2013," HSToday.us, May 10, 2012, accessed May 31, 2012, at http://www.hstoday.us/focused-topics/customs-immigration/single-article-page/congress-poised-to-give-coast-guard-more-money-than-requested-for-fy-2013.html.) See also "Interview, Adm. Robert Papp, US Coast Guard Commandant," Defense News, November 11, 2013: 30. 51.

    Transcript of hearing. The remarks were made in response to a question from Senator Mary Landrieu.

    52.

    Transcript of hearing.

    53.

    Transcript of hearing. The remarks were made in response to a question from Representative John Culberson.

    54.

    The Coast Guard for FY2014 appears to be requesting an active-duty end strength—the number of active-duty military personnel—of 41,594 (measured by the Coast Guard in full-time equivalent [FTE] positions); the Navy for FY2014 is requesting an active-duty end strength of 323,600.

    55.

    The Navy's proposed FY2014 budget requests $14,078 million for the Shipbuilding and Conversion, Navy (SCN) appropriation account.

    56.

    The Navy's proposed FY2014 budget requested $27,824 million for the Military Personnel, Navy (MPN) appropriation account.

    57.

    The Coast Guard's proposed FY2014 budget requested $3,425.3 million for military pay and allowances.