Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Changes from December 22, 2014 to March 3, 2015

This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Ronald O'Rourke Specialist in Naval Affairs December 22, 2014March 3, 2015 Congressional Research Service 7-5700 www.crs.gov RS20643 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Summary CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN78) class of nuclear-powered aircraft carriers (CVNs). The Navy’s proposed FY2016 budget requests procurement or advance procurement (AP) funding for all three ships—a rare occurrence of the Navy requesting procurement or AP funding for three aircraft carriers in a single year. CVN-78 was procured in FY2008. The Navy’s proposed FY2015FY2016 budget estimates the ship’s procurement cost at $12,887.20 million (i.e., about $12.9 billion) in then-year dollars. The ship received advance procurement funding in FY2001-FY2007 and was fully funded in FY2008FY2011 using congressionally authorized four-year incremental funding. The Navy did not request any procurement funding for the ship in FY2012 and FY2013. To help cover cost growth To help cover cost growth on the ship, the ship received an additional $588.1 million in procurement funding in FY2014, and the Navy is requesting another $663.0 million in procurement funding for FY2015. CVN-79 was procured in FY2013. The ship received advance procurement funding in FY2007FY2012, and the Navy plans to fully fund the ship in FY2013-FY2018 using congressionally authorized six-year incremental funding. The Navy’s proposed FY2015 budget estimates CVN79’s procurement cost at $11,498.0 million (i.e., about $11.5 billion) in then-year dollars, and requests $1,300 million in procurement funding for the ship. CVN-80 is scheduled to be procured in FY2018. The Navy’s proposed FY2015 budget estimates the ship’s procurement cost at $13,874.2 million (i.e., about $13.9 billion) in then-year dollars. Under the Navy’s proposed FY2015 budget, the ship is to receive advance procurement funding in FY2016-FY2017 and be fully funded in FY2018-FY2023 using congressionally authorized six-year incremental funding. Oversight issues for Congress for the CVN-78 program include the following: • cost growth in the CVN-78 program; • CVN-78 program issues that were raised in a January 2014 report from the Department of Defense’s (DOD’s) Director of Operational Test and Evaluation (DOT&E); and • the potential for a two-ship block buy on CVN-79 and CVN-80. An additional issue relating to aircraft carriers that has been raised by the Navy’s proposed FY2015 budget concerns funding for the mid-life nuclear refueling overhaul of the aircraft carrier George Washington (CVN-73)FY2014 and $663.0 million in FY2015 in so-called cost-to-complete procurement funding. As a final planned increment of cost-to-complete procurement funding, the Navy is requesting $123.8 million for the ship in FY2016. The ship is scheduled for delivery to the Navy in March 2016. CVN-79 was procured in FY2013. The Navy’s proposed FY2016 budget estimates the ship’s procurement cost at $11,347.6 million (i.e., about $11.3 billion) in then-year dollars. The ship received advance procurement funding in FY2007-FY2012, and the Navy plans to fully fund the ship in FY2013-FY2018 using congressionally authorized six-year incremental funding. The Navy’s proposed FY2016 budget requests $1,634.7 million in procurement funding for the ship. The ship is scheduled for delivery to the Navy in June 2022. CVN-80 is scheduled to be procured in FY2018. The Navy’s proposed FY2016 budget estimates the ship’s procurement cost at $13,472.0 million (i.e., about $13.5 billion) in then-year dollars. The Navy plans to request AP funding for the ship in FY2016 and FY2017, and then fully fund the ship in FY2018-FY2023 using congressionally authorized six-year incremental funding. The Navy’s proposed FY2016 budget requests $874.7 million in AP funding for the ship. Oversight issues for Congress for the CVN-78 program include the following: • cost growth in the CVN-78 program, Navy efforts to stem that growth, and Navy efforts to manage costs so as to stay within the program’s cost caps; and • CVN-78 program issues that were raised in a January 2015 report from the Department of Defense’s (DOD’s) Director of Operational Test and Evaluation (DOT&E). Congressional Research Service Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Contents Introduction...................................................................................................................................... 1 Background ...................................................................................................................................... 1 The Navy’s Aircraft Carrier Force ............................................................................................. 1 Statutory Requirement to Maintain Not Less Than 11 Carriers ................................................ 1 Origin of Requirement ........................................................................................................ 1 Waiver for Period Between CVN-65 and CVN-78 ............................................................. 1 Funding and Procuring Aircraft Carriers ................................................................................... 2 Some Key Terms ................................................................................................................. 2 Incremental Funding Authority for Aircraft Carriers .......................................................... 2 Aircraft Carrier Construction Industrial Base............................................................................ 3 Gerald R. Ford (CVN-78) Class Program ................................................................................. 3 CVN-78 ............................................................................................................................... 4 CVN-79 ............................................................................................................................... 54 CVN-80 ............................................................................................................................... 54 Program Procurement Funding ........................................................................................... 5 IncreasesChanges in Estimated Unit Procurement Costs Since FY2008 Budget .............................. 5 6 Program Procurement Cost Cap .......................................................................................... 87 Issues for Congress .......................................................................................................................... 8 Cost Growth...............................................................................7 Cost Growth and Managing Costs Within Program Cost Caps ................................................ 87 Overview ............................................................................................................................. 8 December 2014 CBO Report ......7 February 2015 Department of the Navy Testimony ........................................................................................ 9 November 2014 GAO Report ............................. 9 January 2015 Press Report .............................................................. 10 Navy Response to November 2014 GAO Report ............................................................. 11 March 2014 GAO 10 December 2014 CBO Report .................................................................................................. 13 March 2013 Navy Report to Congress (Released May 2013).... 10 November 2014 GAO Report ....................................... 15 May 2013 Navy Testimony ............................................................................................... 15 March 2012 Navy Letter to Senator McCain . 11 Navy Response to November 2014 GAO Report ................................................................... 17 Issues Raised in January 2014 DOT&E Report ................... 12 March 2014 GAO Report ................................................... 22 Potential Two-Ship Block Buy on CVN-79 and CVN-80 ....................................................... 27 Legislative Activity for FY2015 ......................................... 14 March 2013 Navy Report to Congress (Released May 2013)........................................................... 32 FY2015 Funding Request ...... 16 May 2013 Navy Testimony .................................................................................................. 32 FY2015 National Defense Authorization Act (H.R. 3979)...................................................... 32 House................................................................................................................................. 32 Senate ................................................................................................................................ 33 Final Version ..................................................................................................................... 36 FY2015 DOD Appropriations Act (Division C of H.R. 83/P.L. 113-235)............................... 37 House................................................................................................................................. 37 Senate ............... 16 March 2012 Navy Letter to Senator McCain .................................................................... 18 Issues Raised in January 2015 DOT&E Report ...................................................................... 24 Potential for Combined Material Purchase for CVNs 80 and 81 ...................................... 28 Legislative Activity for FY2016 ................................................................................................................. 38 Final Version ............. 30 FY2016 Funding Request ........................................................................................................ 3930 Figures Figure 1. Navy Illustration of CVN-78 ............................................................................................ 4 Congressional Research Service Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress3 Tables Table 1. Procurement Funding for CVNs 78, 79, and 80 Through FY2019FY2020 .................................... 65 Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, and 80................................... 7 Appendixes Appendix A6 Congressional Research Service Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Appendixes Appendix. March 2013 Navy Report to Congress on Construction Plan for CVN-79 .............. 40 Appendix B. Refueling Complex Overhaul (RCOH) for George Washington (CVN-73)............. 58.... 31 Contacts Author Contact Information........................................................................................................... 6249 Congressional Research Service Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Introduction This report provides background information and potential oversight issues for Congress on the Gerald R. Ford (CVN-78) class aircraft carrier program. Congress’s decisions on the CVN-78 program could substantially affect Navy capabilities and funding requirements and the shipbuilding industrial base. An additional issue relating to aircraft carriers that has been raised by the Navy’s proposed FY2015 budget concerns funding for the mid-life nuclear refueling overhaul of the aircraft carrier George Washington (CVN-73). This issue is discussed in Appendix BThe Navy’s proposed FY2016 budget requests a total of $2,633.1 million in procurement and advance procurement (AP) funding for CVN-78, CVN-79, and CVN-80, the first three ships in the program. Congress’s decisions on the CVN-78 program could substantially affect Navy capabilities and funding requirements and the shipbuilding industrial base. Background The Navy’s Aircraft Carrier Force The Navy’s current aircraft carrier force consists of 10 nuclear-powered Nimitz-class ships (CVNs 68 through 77) that entered service between 1975 and 2009. Until December 2012, the Navy’s aircraft carrier force included an 11th aircraft carrier—the one-of-a-kind nuclear-powered Enterprise (CVN-65), which entered service in 1961. CVN-65 was inactivated on December 1, 2012, reducing the Navy’s carrier force from 11 ships to 10. The most recently commissioned carrier, George H. W. Bush (CVN-77), the final Nimitz-class ship, was procured in FY2001 and commissioned into service on January 10, 2009. CVN-77 replaced Kitty Hawk (CV-63), which was the Navy’s last remaining conventionally powered carrier.1 Statutory Requirement to Maintain Not Less Than 11 Carriers Origin of Requirement 10 U.S.C. 5062(b) requires the Navy to maintain a force of not less than 11 operational aircraft carriers. The requirement for the Navy to maintain not less than a certain number of operational aircraft carriers was established by Section 126 of the FY2006 National Defense Authorization Act (H.R. 1815/P.L. 109-163 of January 6, 2006), which set the number at 12 carriers. The requirement was changed from 12 carriers to 11 carriers by Section 1011(a) of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006). Waiver for Period Between CVN-65 and CVN-78 As mentioned above, the carrier force dropped from 11 ships to 10 ships when Enterprise (CVN65) was inactivated on December 1, 2012. The carrier force is to return to 11 ships when its replacement, Gerald R. Ford (CVN-78), is commissioned into service. CVN-78 was originally scheduled to be delivered in September 2015, but its construction has been running behind schedule, and the Navy in May 2013 announced that the ship’s delivery date had been postponed 1 The Kitty Hawk was decommissioned on January 31, 2009. Congressional Research Service 1 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress to February 2016.2 The Navy’s FY2015 budget submission shows a delivery date of March 2016. Anticipating the gap Anticipating the gap between the inactivation of CVN-65 and the commissioning of CVN-78, the Navy asked Congress for a temporary waiver of 10 U.S.C. 5062(b) to accommodate the period between the two events. Section 1023 of the FY2010 National Defense Authorization Act (H.R. 2647/P.L. 111-84 of October 28, 2009) authorized the waiver, permitting the Navy to have 10 operational operational carriers between the inactivation of CVN-65 and the commissioning of CVN-78. 1 The Kitty Hawk was decommissioned on January 31, 2009. Congressional Research Service 1 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Funding and Procuring Aircraft Carriers Some Key Terms The Navy procures a ship (i.e., orders the ship) by awarding a full-ship construction contract to the firm building the ship. Part of a ship’s procurement cost might be provided through advance procurement (AP) funding. AP funding is funding provided in one or more years prior to (i.e., in advance of) a ship’s year of procurement. AP funding is used to pay for long-leadtime components that must be ordered ahead of time to ensure that they will be ready in time for their scheduled installation into the ship. AP funding is also used to pay for the design costs for a new class of ship. These design costs, known more formally as detailed design/non-recurring engineering (DD/NRE) costs, are traditionally incorporated into the procurement cost of the lead ship in a new class of ships. Fully funding a ship means funding the entire procurement cost of the ship. If a ship has received AP funding, then fully funding the ship means paying for the remaining portion of the ship’s procurement cost. The full funding policy is a Department of Defense (DOD) policy that normally requires items acquired through the procurement title of the annual DOD appropriations act to be fully funded in the year they are procured. In recent years, Congress has authorized DOD to use incremental funding for procuring certain Navy ships, most notably aircraft carriers. Under incremental funding, some of the funding needed to fully fund a ship is provided in one or more years after the year in which the ship is procured.32 Incremental Funding Authority for Aircraft Carriers Section 121 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006) granted the Navy the authority to use four-year incremental funding for CVNs 78, 79, and 80. Under this authority, the Navy could fully fund each of these ships over a four-year period that includes the ship’s year of procurement and three subsequent years. 2 Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for FY2014, May 2013, p. 13. For more on full funding, incremental funding, and AP funding, see CRS Report RL31404, Defense Procurement: Full Funding Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by Ronald O'Rourke. 3 Congressional Research Service 2 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Section 124 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 112-81 of December 31, 2011) amended Section 121 of P.L. 109-364 to grant the Navy the authority to use five-year incremental funding for CVNs 78, 79, and 80. Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice applied to CVNs 79 and 80. Section 121 of the FY2013 National Defense Authorization Act (H.R. 4310/P.L. 112-239 of January 2, 2013) amended Section 121 of P.L. 109-364 to grant the Navy the authority to use sixyear incremental funding for CVNs 78, 79, and 80. Since CVN-78 was fully funded in FY2008FY2011, the provision in practice applies to CVNs 79 and 80. 2 For more on full funding, incremental funding, and AP funding, see CRS Report RL31404, Defense Procurement: Full Funding Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by Ronald O'Rourke. Congressional Research Service 2 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Aircraft Carrier Construction Industrial Base All U.S. aircraft carriers procured since FY1958 have been built by Newport News Shipbuilding (NNS), of Newport News, VA, a shipyard that is part of Huntington Ingalls Industries (HII). NNS is the only U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The aircraft carrier construction industrial base also includes hundreds of subcontractors and suppliers in various states. Gerald R. Ford (CVN-78) Class Program The Gerald R. Ford (CVN-78) class carrier design (Figure 1) is the successor to the Nimitz-class carrier design.4 4 The CVN-78 class was earlier known as the CVN-21 class, which meant nuclear-powered aircraft carrier for the 21st century. Congressional Research Service 3 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 3 Figure 1. Navy Illustration of CVN-78 Source: Navy image accessed at http://www.navy.mil/management/photodb/photos/060630-N-0000X-001.jpg on April 20, 2011. The Ford-class design uses the basic Nimitz-class hull form but incorporates several improvements, including features permitting the ship to generate about 25% more aircraft sorties per day, more electrical power for supporting ship systems, and features permitting the ship to be operated by several hundred fewer sailors than a Nimitz-class ship, significantly reducing lifecycle operating and support (O&S) costs. 3 The CVN-78 class was earlier known as the CVN-21 class, which meant nuclear-powered aircraft carrier for the 21st century. Congressional Research Service 3 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Navy plans call for procuring at least three Ford-class carriers—CVN-78, CVN-79, and CVN-80. CVN-78 CVN-78, which was named for President Gerald R. Ford in 2007,54 was procured in FY2008. The Navy’s proposed FY2015FY2016 budget estimates the ship’s procurement cost at $12,887.20 million (i.e., about $12.9 billion) in then-year dollars. Of the ship’s total procurement cost, about $3.3 billion is for detailed design/non-recurring engineering (DD/NRE) costs for the class, and about $9.6 billion is for construction of the ship itself. 5 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced that CVN-78 would be so named. CVN-78 and other carriers built to the same design will consequently be referred to as Ford (CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for Congress, by Ronald O’Rourke. Congressional Research Service 4 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress CVN-78 received advance procurement funding in FY2001-FY2007 and was fully funded in FY2008-FY2011 using congressionally authorized four-year incremental funding. The Navy did not request any procurement funding for the ship in FY2012 and FY2013. To help cover cost To help cover cost growth on the ship, the ship received an additional $588.1 million in procurement funding in FY2014, and the Navy is requesting another $663.0 million in procurement funding for FY2015FY2014 and $663.0 million in FY2015 in so-called cost-to-complete procurement funding. As a final planned increment of cost-to-complete procurement funding, the Navy is requesting $123.8 million for the ship in FY2016. The ship is scheduled for delivery to the Navy in March 2016. CVN-79 CVN-79, which was named for President John F. Kennedy on May 29, 2011,65 was procured in FY2013. The Navy’s proposed FY2016 budget estimates the ship’s procurement cost at $11,347.6 million (i.e., about $11.3 billion) in then-year dollars. The ship received advance procurement funding in FY2007-FY2012, and the Navy plans to fully fund the ship in FY2013-FY2018 using congressionally authorized six-year incremental funding. The Navy’s proposed FY2015 budget estimates CVN-79’s procurement cost at $11,498.0 million (i.e., about $11.5 billion) in then-year dollars, and requests $1,300 million in procurement funding for the shipFY2016 budget requests $1,634.7 million in procurement funding for the ship. The ship is scheduled for delivery to the Navy in June 2022. CVN-80 CVN-80, which was named Enterprise on December 1, 2012,76 is scheduled to be procured in FY2018. The Navy’s proposed FY2014FY2016 budget estimates the ship’s procurement cost at $13,874.2472.0 million (i.e., about $13.95 billion) in then-year dollars. Under the Navy’s proposed FY2015 budget, the ship is to receive advance procurement funding in FY2016-FY2017 and be fully funded in FY2018-FY2023 using congressionally authorized six-year incremental funding. Program Procurement Funding Table 1 shows procurement funding for CVNs 78, 79, and 80 through FY2018. 6 The Navy plans to request AP funding for the ship in FY2016 and FY2017, and then fully fund the ship in FY2018-FY2023 using 4 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced that CVN-78 would be so named. CVN-78 and other carriers built to the same design will consequently be referred to as Ford (CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for Congress, by Ronald O’Rourke. 5 See “Navy Names Next Aircraft Carrier USS John F. Kennedy,” Navy News Service, May 29, 2011, accessed online on June 1, 2011 at http://www.navy.mil/search/display.asp?story_id=60686. See also Peter Frost, “U.S. Navy’s Next Aircraft Carrier Will Be Named After The Late John F. Kennedy,” Newport News Daily Press, May 30, 2011. CVN-79 is the second ship to be named for President John F. Kennedy. The first, CV-67, was the last conventionally powered carrier procured for the Navy. CV-67 was procured in FY1963, entered service in 1968, and was decommissioned in 2007. 76 The Navy made the announcement of CVN-80’s name on the same day that it deactivated the 51-year-old aircraft carrier CVN-65, also named Enterprise. (“Enterprise, Navy’s First Nuclear-Powered Aircraft Carrier, Inactivated,” Navy News Service, December 1, 2012; Hugh Lessig, “Navy Retires One Enterprise, Will Welcome Another,” Newport News Daily Press, December 2, 2012.) CVN-65 was the eighth Navy ship named Enterprise; CVN-80 is to be the ninth. Congressional Research Service 54 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress congressionally authorized six-year incremental funding. The Navy’s proposed FY2016 budget requests $874.7 million in AP funding for the ship. Program Procurement Funding Table 1 shows procurement funding for CVNs 78, 79, and 80 through FY2020. Table 1. Procurement Funding for CVNs 78, 79, and 80 Through FY2019FY2020 (Millions of then-year dollars, rounded to nearest tenth) FY CVN-78 CVN-79 CVN-80 Total FY01 21.7 (AP) 0 0 21.7 FY02 135.3 (AP) 0 0 135.3 FY03 395.5 (AP) 0 0 395.5 FY04 1,162.9 (AP) 0 0 1,162.9 FY05 623.1 (AP) 0 0 623.1 FY06 618.9 (AP) 0 0 618.9 FY07 735.8 (AP) 52.8 (AP) 0 788.6 FY08 2,685.0 (FF) 123.5 (AP) 0 2,808.6 FY09 2,684.6 (FF) 1,210.6 (AP) 0 3,895.1 FY10 737.0 (FF) 482.9 (AP) 0 1,219.9 FY11 1,712.5 (FF) 903.3 (AP) 0 2,615.8 FY12 0 554.8 (AP) 0 554.8 FY13 0 491.0 (FF) 0 491.0 FY14 588.1 (CC) 917.6 (FF) 0 1,505.7 FY15 (requested) 663.0 (CC) 1,300.0219.4 (FF) 0 1,963.0882.4 FY16 (projected) 124.0 (CC) 2,193.0 (FF) 683.2 (AP) 3,000.2requested) 123.8 (CC) 1,634.7 (FF) 874.7 (AP) 2,633.1 FY17 (projected) 0 1,245.6829.0 (FF) 1,045.2126.1 (AP) 2,290.8955.1 FY18 (projected) 0 2,023.8 (FF) 825.5 (FF) 2,849.3 FY19 (projected) 0 0 1,864.5 (FF) 1,864.51929.0 (FF) 1,601.8 (FF) 3,530.8 FY19 (projected) 0 0 2,076.0 (FF) 2,076.0 FY20 (projected) 0 0 873.3 (FF) 873.3 Source: Table prepared by CRS based on FY2009-FY2015FY2016 Navy budget submissions. Notes: Figures may not add due to rounding. “AP” is advance procurement funding; “FF” is full funding; “CC” is cost to complete funding (i.e., funding to cover cost growth). IncreasesChanges in Estimated Unit Procurement Costs Since FY2008 Budget Table 2 shows changes in the estimated procurement costs of CVNs 78, 79, and 80 since the FY2008 budget submission.8 8 7 7 CBO in 2008 and the Government Accountability Office (GAO) in 2007 questioned the accuracy of the Navy’s cost estimate for CVN-78. CBO reported in June 2008 that it estimated that CVN-78 would cost $11.2 billion in constant FY2009 dollars, or about $900 million more than the Navy’s estimate of $10.3 billion in constant FY2009 dollars, and that if “CVN-78 experienced cost growth similar to that of other lead ships that the Navy has purchased in the past 10 years, costs could be much higher still.” CBO also reported that, although the Navy publicly expressed confidence in its cost estimate for CVN-78, the Navy had assigned a confidence level of less than 50% to its estimate, meaning that the Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office, Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in August 2007 that: Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate, which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for construction was 22 percent higher than the Navy’s cost target, which was based on the budget. Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage issues that affect cost suffers from insufficient cost surveillance. Without effective cost (continued...) Congressional Research Service 6(continued...) Congressional Research Service 5 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, and 80 (As shown in FY2008-FY2015FY2016 budgets, in millions of then-year dollars) Budget FY08 budget FY09 budget FY10 budget FY11 budget FY12 budget FY13 budget FY14 budget FY15 budget FY16 budget % change: FY08 budget to FY09 budget FY09 budget to FY10 budget FY10 budget to FY11 budget FY11 budget to FY12 budget FY12 budget to FY13 budget FY13 budget to FY14 budget FY14 budget to FY15 budget FY08 budget to FY15 budget CVN-78 Estimated Scheduled procurement fiscal year of cost procurement 10,488.9 FY08 10,457.9 FY08 10,845.8 FY08 11,531.0 FY08 11,531.0 FY08 12,323.2 FY08 12,829.3 FY08 12,887.2 FY08 -0.312,887.0 FY08 CVN-79 Estimated Scheduled procurement fiscal year of cost procurement 9,192.0 FY12 9,191.6 FY12 FY13b n/aa 10,413.1 FY13 10,253.0 FY13 11,411.0 FY13c 11,338.4 FY13 11,498.0 FY13 11,347.6 FY13 CVN-80 Estimated Scheduled procurement fiscal year of cost procurement 10,716.8 FY16 10,716.8 FY16 n/aa FY18b 13,577.0 FY18 13,494.9 FY18 13,874.2 FY18c 13,874.2 FY18 13,874.2 FY18 13,472.0 FY18 No change +3.7 Almost no change n/a +6.3 n/a n/a No change - 1.5 - 0.1 +6.9% +11.3% +2.8% +4.1% - 0.6% No change +0.5% +1.4% No change +22.9% +25.1% +29.5% n/a Source: Table prepared by CRS based on FY2008-FY2015 Navy budget submissions. a. n/a means not available; the FY2010 budget submission did not show estimated procurement costs for CVNs 79 and 80. b. The FY2010 budget submission did not show scheduled years of procurement for CVNs 79 and 80; the dates shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for procuring carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference regarding recommendations for the FY2010 defense budget. (...continued)-0.3 n/a (...continued) Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office, Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in August 2007 that: Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate, which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for construction was 22 percent higher than the Navy’s cost target, which was based on the budget. Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage issues that affect cost suffers from insufficient cost surveillance. Without effective cost surveillance, the Navy will not be able to identify early signs of cost growth and take necessary corrective action. (Government Accountability Office, Defense Acquisitions[:] Navy Faces Challenges Constructing the Aircraft Carrier Gerald R. Ford within Budget, GAO-07-866, August 2007, summary page. See also Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), p. 15.) Congressional Research Service 76 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Budget FY15 budget to FY16 budget FY08 budget to FY15 budget CVN-78 Almost no change +22.9% CVN-79 CVN-80 -1.3% -2.9% +23.5% +25.7% Source: Table prepared by CRS based on FY2008-FY2016 Navy budget submissions. a. n/a means not available; the FY2010 budget submission did not show estimated procurement costs for CVNs 79 and 80. b. The FY2010 budget submission did not show scheduled years of procurement for CVNs 79 and 80; the dates shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for procuring carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference regarding recommendations for the FY2010 defense budget. c. Although the FY2013 budget did not change the scheduled years of procurement for CVN-79 and CVN-80 compared to what they were under the FY2012 budget, it lengthened the construction period for each ship by two years (i.e., each ship is scheduled to be delivered two years later than under the FY2012 budget). Program Procurement Cost Cap Section 122 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006) established a procurement cost cap for CVN-78 of $10.5 billion, plus adjustments for inflation and other factors, and a procurement cost cap for subsequent Fordclass carriers of $8.1 billion each, plus adjustments for inflation and other factors. The conference report (H.Rept. 109-702 of September 29, 2006) on P.L. 109-364 discusses Section 122 on pages 551-552. Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 113-66 of December 26, 2013) amended the procurement cost cap for the CVN-78 program to provide a revised cap of $12,887.0 million for CVN-78 and a revised cap of $11,498.0 million for each follow-on ship in the program, plus adjustments for inflation and other factors (including an additional factor not included in original cost cap). Issues for Congress Cost Growth Overview Cost growth has been a continuing oversight issue for Congress on the CVN-78 program. As and Managing Costs Within Program Cost Caps Overview Cost growth in the CVN-78 program, Navy efforts to stem that growth, and Navy efforts to manage costs so as to stay within the program’s cost caps have been continuing oversight issues for Congress on the CVN-78 program. As shown in Table 2, the estimated procurement costs of CVNs 78, 79, and 7980 have grown 22.9%, 23.5%, and 25.7 and 25.1%, respectively, since the submission of the FY2008 budget. As also shown in the table, CVNs 78, 79, and 80 experienced little or no cost growth from the FY2014 budget to the FY2015 budget. As shown in Table 1, cost growth on CVN-78 has prompted the Navy to program $1,375.1 million in additional cost-to-complete procurement funding for the ship in FY2014FY2016. the FY2008 budget. Cost growth on CVN-78 required the Navy to program $1,374.9 million in cost-to-complete procurement funding for the ship in FY2014-FY2016 (see Table 1). As also shown in Table 2, however, • while the estimated cost of CVN-78 grew considerably between the FY2008 budget (the budget in which CVN-78 was procured) and the FY2014 budget, it has remained stable in the FY2015 and FY2016 budgets; Congressional Research Service 7 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress • while the estimated cost of CVN-79 grew considerably between the FY2008 budget and the FY2013 budget (in part because the procurement date for the ship was deferred by one year in the FY2010 budget),8 it has decreased a bit since the FY2013 budget; and • while the estimated cost of CVN-79 grew considerably between the FY2008 budget and the FY2011 budget (in part because the procurement date for the ship was deferred by two years in the FY2010 budget),9 it has decreased a bit since the FY2011 budget. Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 113-66 of December 26, 2013), in addition to amending the procurement cost cap for the CVN-78 program (see previous section), requires the Navy to submit on a quarterly basis a report setting forth the most current cost estimate for the aircraft carrier designated as CVN-79 (as estimated by the program manager). Each cost estimate shall include the current percentage of completion of the program, the total costs incurred, and an estimate of costs at completion for ship construction, Government-furnished equipment, and engineering and support costs. Section 121 also states that The Secretary [of the Navy] shall ensure that each prime contract for the aircraft carrier designated as CVN-79 includes an incentive fee structure that will, throughout the period of performance of the contract, provide incentives for each contractor to meet the portion of the cost of the ship, as limited by subsection (a)(2) and adjusted pursuant to subsection (b) [i.e., Congressional Research Service 8 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress the amended procurement cost cap for the program], for which the contractor is responsible.’. Navy officials have stated that they are working to control the cost of CVN-79 by using a build strategy for the ship that incorporates improvements over the build strategy that was used for CVN-78. These improvements, Navy officials have said, include the following items, among others: • achieving a higher percentage of outfitting of ship modules before modules are stacked together to form the ship; • achieving “learning inside the ship,” which means producing similar-looking ship modules in an assembly line-like series, so as to achieve improved production learning curve benefits in the production of these modules; and • more economical ordering of parts and materials including greater use of batch ordering of parts and materials, as opposed to ordering parts and materials on an individual basis as each is needed. The following sections present discussions of the cost growth issue from the Department of Defense (DOD), the Navy, the Congressional Budget Office (CBO), and the Government Accountability Office (GAO). 8 Deferring the ship’s procurement from FY2012 to FY2013 put another year of inflation into the ship’s estimated cost in then-year dollars (which are the type of dollars shown in Table 2), and may have reduced production learning curve benefits in shifting from production of CVN-78 to production of CVN-79. 9 Deferring the ship’s procurement from FY2016 to FY2018 put additional years of inflation into the ship’s estimated cost in then-year dollars (which are the type of dollars shown in Table 2), and may have reduced production learning curve benefits in shifting from production of CVN-79 to production of CVN-80. Congressional Research Service 8 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress The following sections present discussions of cost growth in the CVN-78 program, Navy efforts to stem that growth, and Navy efforts to manage costs so as to stay within the program’s cost caps from the Department of Defense (DOD), the Navy, the Congressional Budget Office (CBO), and the Government Accountability Office (GAO). February 2015 Department of the Navy Testimony At a February 25, 2015, hearing on Department of the Navy acquisition programs, Department of the Navy officials testified: The Navy is committed to delivering CVN 78 within the $12.887 billion Congressional cost cap. Sustained efforts to identify cost reductions and drive improved cost and schedule on this first-of-class aircraft carrier have resulted in highly stable performance since 2011. Parallel efforts by the Navy and shipbuilder are driving down and stabilizing aircraft carrier construction costs for the future John F Kennedy (CVN 79) and estimates for the future Enterprise (CVN 80). As a result of the lessons learned on CVN 78, the approach to carrier construction has undergone an extensive affordability review. The Navy and the shipbuilder have made significant changes on CVN 79 to reduce the cost to build the ship as detailed in the 2013 CVN 79 report to Congress. The benefits of these changes in build strategy and resolution of first-of-class impacts on CVN 79 are evident in metrics showing significantly reduced man-hours for completed work from CVN 78. These efforts are ongoing and additional process improvements continue to be identified. The Navy extended the CVN 79 construction preparation contract into 2015 to enable continuation of ongoing planning, construction, and material procurement while capturing lessons learned associated with lead ship construction and early test results. The continued negotiations of the detail design and construction (DD&C) contract afford an opportunity to incorporate further construction process improvements and cost reduction efforts. Award of the DD&C contract is expected in third quarter FY 2015. This will be a fixed price-type contract. Additionally, the Navy will deliver the CVN 79 using a two-phased strategy. This enables select ship systems and compartments to be completed in a second phase, wherein the work can be completed more efficiently through competition or the use of skilled installation teams responsible for these activities. This approach, key to delivering CVN 79 at the lowest cost, also enables the Navy to procure and install shipboard electronic systems at the latest date possible. The FY 2014 NDAA adjusted the CVN 79 and follow ships cost cap to $11,498 million to account for economic inflation and non-recurring engineering for incorporation of lead ship lessons learned and design changes to improve affordability. In transitioning from first-ofclass to first follow ships, the Navy has maintained Ford class requirements and the design is highly stable. Similarly, we have imposed strict interval controls to drive changes to the way we do business in order to ensure CVN 79 is delivered below the cost cap. To this same end, the FY 2016 President’s Budget request aligns funding to the most efficient build strategy for this ship and we look for Congress’ full support of this request to enable CVN 79 to be procured at the lowest possible cost. Enterprise (CVN 80) will begin long lead time material procurement in FY 2016. The FY 2016 request re-phases CVN 80 closer to the optimal profile, therefore reducing the overall ship cost. The Navy will continue to investigate and will incorporate further cost reduction initiatives, engineering efficiencies, and lessons learned from CVN 78 and CVN 79. Future Congressional Research Service 9 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress cost estimates for CVN 80 will be updated for these future efficiencies as they are identified.10 January 2015 Press Report A January 12, 2015, press report stated that The Navy in a recent written response to questioning from [Senator John] McCain (R-AZ) acknowledged that the approaching critical shipboard test phase of the lead ship in the class, the Gerald Ford (CVN-78), could impact the vessel's current $12.9 billion cost cap.... “CVN-78 is entering the critical shipboard test phase of the program,” according to the information submitted to McCain.... “This is the single area of risk that could affect the cost cap.” The Navy emphasized that design of the Gerald Ford is largely complete and anticipates no additional risk to the funding for design efforts, according to the response.11 December 2014 CBO Report A December 2014 CBO report on the potential cost of the Navy’s FY2015 30-year shipbuilding plan states: The Navy currently projects that the total cost of the lead ship of the CVN-78 class will be $12.9 billion in nominal dollars over the period from 2001 to 2016, an amount equal to the Congressional cost cap.20 Using the Navy’s inflation index for naval shipbuilding, CBO converted that figure to $14.3 billion in 2014 dollars. That amount is 23 percent more than the amount requested in the President’s budget when the ship was first authorized in 2008. The Navy’s estimate does not include $4.7 billion in research and development costs that apply to the entire class. CBO estimates that the total cost of the lead ship of the CVN-78 class will be $13.5 billion in nominal dollars and $14.8 billion in 2014 dollars. To generate that estimate, CBO used the actual costs of the previous carrier—the CVN-77—and adjusted them for the higher costs of government-furnished equipment in the newer configuration and for more than $3 billion in costs for nonrecurring engineering and detail design (the plans, drawings, and other one-time items associated with the first ship of a new class). Subsequent ships of the CVN-78 class will not require as much funding for onetime items, although they will incur the same costs for government-furnished equipment. All together, CBO estimates the average cost of the 6 carriers in the 2015 plan at $12.8 billion, compared with the Navy’s estimate of $12.5 billion.... 10 Statement of the Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and Acquisition) and Vice Admiral Joseph P. Mulloy, Deputy Chief of Naval Operations for Integration of Capabilities and Resources and Lieutenant General Kenneth J. Glueck, Jr., Deputy Commandant, Combat Development and Integration & Commanding General, Marine Corps Combat Development Command, Before the Subcommittee on Seapower and Projection Forces of the House Armed Services Committee on Department of the Navy Seapower and Projection Forces Capabilities, February 25, 2015, pp. 5-6. 11 Lara Seligman, “Navy Tells McCain CVN-78 Carrier Shipboard Tests May Impact Cost Caps,” Inside the Navy, January 12, 2015. Congressional Research Service 10 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress The final cost of the CVN-78 could be higher or lower than CBO’s estimate. Possible reasons for a higher cost include the following: — The costs of many lead ships built in the past 20 years have increased by more than 30 percent from the original budgeted estimates. CBO’s estimate of the cost of the CVN-78 incorporates an amount of growth that falls within the range of historical cost growth for lead ships, and the costs reported for the roughly 80 percent of construction completed to date Congressional Research Service 9 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress are consistent with that estimate—but costs have tended to rise more in the latter stages of ship construction, when systems are being installed and integrated. For example, the test program for the carrier could reveal one or more major and possibly expensive problems. — The Navy has stated that there is a 50 percent probability that the cost of the CVN-78 will exceed its estimate. Specifically, in its most recent selected acquisition report, the Navy stated that it has budgeted an amount for the CVN-78 that covers up to the 50th percentile of possible cost outcomes. Possible reasons for a lower cost than CBO’s estimate include the following: — The Navy and the builder of the CVN-78 recognize that cost growth for lead ships is a significant concern, and they are actively managing the CVN-78 program to restrain costs. — All of the materials for the CVN-78 have been purchased, and much of the equipment for the vessel is being purchased under fixed-price contracts; those factors essentially eliminate the risk of further cost growth for about half of the projected cost of the carrier. — The test program might reveal only minor problems. In that case, the cost of the ship would probably be less than CBO’s estimate, although it might still exceed the Navy’s estimate. The next carrier following the CVN-78 will be the CVN-79, the John F. Kennedy. Funding for that ship began in 2007, the Congress officially authorized its construction in 2013, and appropriations for it are expected to be complete by 2018. The Navy estimates that the ship will cost $11.5 billion in nominal dollars ($160 million more than the estimate under the President’s 2014 budget) and $10.6 billion in 2014 dollars. In its selected acquisition report on the CVN-79, the Navy describes its cost estimate as an “aggressive but achievable target.” In contrast, CBO estimates that the cost of the ship will be $12.6 billion in nominal dollars and $11.5 billion in 2014 dollars, about 8 percent more than the Navy’s estimate.912 November 2014 GAO Report A November 2014 GAO report on the CVN-78 program stated: The extent to which the lead Ford-class ship, CVN 78, will be delivered by its current March 2016 delivery date and within the Navy’s $12.9 billion estimate is dependent on the Navy’s plan to defer work and costs to the post-delivery period. Lagging construction progress as well as ongoing issues with key technologies further exacerbate an already compressed schedule and create further cost and schedule risks. With the shipbuilder embarking on one of the most complex phases of construction with the greatest likelihood for cost growth, cost 12 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2015 Shipbuilding Plan, December 2014, pp. 21, 23. Congressional Research Service 11 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress increases beyond the current $12.9 billion cost cap appear likely. In response, the Navy is deferring some work until after ship delivery to create a funding reserve to pay for any additional cost growth stemming from remaining construction risks. This strategy will result in the need for additional funding later, which the Navy plans to request through its postdelivery and outfitting budget account. However, this approach obscures visibility into the true cost of the ship and results in delivering a ship that is less complete than initially planned. 9 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2015 Shipbuilding Plan, December 2014, pp. 21, 23. Congressional Research Service 10 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress CVN 78 will deploy without demonstrating full operational capabilities because it cannot achieve certain key requirements according to its current test schedule. Key requirements— such as increasing aircraft launch and recovery rates—will likely not be met before the ship is deployment ready and could limit ship operations. Further, CVN 78 will not meet a requirement that allows for increases to the size of the crew over the service life of the ship. In fact, the ship may not even be able to accommodate the likely need for additional crew to operate the ship without operational tradeoffs. Since GAO’s last report in September 2013, post-delivery plans to test CVN 78’s capabilities have become more compressed, further increasing the likelihood that CVN 78 will not deploy as scheduled or will deploy without fully tested systems. The Navy is implementing steps to achieve the $11.5 billion congressional cost cap for the second ship, CVN 79, but these are largely based on ambitious efficiency gains and reducing a significant amount of construction, installation, and testing—work traditionally completed prior to ship delivery. Since GAO last reported in September 2013, the Navy extended CVN 79’s construction preparation contract to allow additional time for the shipbuilder to reduce cost risks and incorporate lessons learned from construction of CVN 78. At the same time, the Navy continues to revise its acquisition strategy for CVN 79 in an effort to ensure that costs do not exceed the cost cap, by postponing installation of some systems until after ship delivery, and deferring an estimated $200 million - $250 million in previously planned capability upgrades of the ship’s combat systems to be completed well after the ship is operational. Further, if CVN 79 construction costs should grow above the legislated cost cap, the Navy may choose to use funding intended for work to complete the ship after delivery to cover construction cost increases. As with CVN 78, the Navy could choose to request additional funding through post-delivery budget accounts not included in calculating the ship’s end cost. Navy officials view this as an approach to managing the cost cap. However, doing so impairs accountability for actual ship costs.1013 Navy Response to November 2014 GAO Report A Navy information paper responding to the November 2014 GAO report states (bold font as in original): — The Navy cost estimate to complete CVN 78 is $12.887B. Cost performance on the ship has been stable since this estimate was established in 2011, thus providing confidence that the Navy will deliver the ship within the cost cap. — This cost estimate accounts for inflation and cost growth associated with completing the ship design, ship construction (material and labor), and government furnished equipment. The inflation impact (cost associated with economic impacts during the period of performance, 2006-2016) was not included in the original $10.5B cost cap. 13 Government Accountability Office, Ford-Class Aircraft Carrier[:] Congress Should Consider Revising Cost Cap Legislation to Include All Construction Costs, GAO-15-22, November 2014, summary page. Congressional Research Service 12 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress — Performance-related cost growth is largely due to the lack of maturity of the design and development at the point in time when the estimate was established and the impact of concurrency of design, development and construction in the early stages of this first of class aircraft carrier. — The significant new design features incorporated in the CVN 78 class provide for increased warfighting capability, increased survivability, increased service life margins to handle weapons of the future, and most notably, reduced operating and support cost 10 Government Accountability Office, Ford-Class Aircraft Carrier[:] Congress Should Consider Revising Cost Cap Legislation to Include All Construction Costs, GAO-15-22, November 2014, summary page. Congressional Research Service 11 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress throughout the carrier‘s life. The advanced design enables increased sortie generation rates (SGR) and a reduction of up to 1200 crew and airmen which, alongside other new design features, results in an estimated $4B reduction per aircraft carrier in its service life. Current Navy SGR model results and manpower analysis indicate these requirements will be met. — The Navy has provided monthly reports to Congress since the fall of 2011 and has testified regarding progress on the ship’s completion, including the risk of future cost growth associated with shipboard testing of the significant new capabilities designed into this first of class carrier. The Navy believes it has an effective plan to mitigate the risk, which places primary emphasis on a ‘build-to-test’ strategy for completing the highest risk systems, but cannot discount that there is potential for test issues that could impact the carrier’s completion. — In order to alleviate some of the cost and schedule pressures associated with completing CVN 78, the Navy has identified certain areas of the ship whose completion is not required for delivery—such as berthing spaces for the aviation detachment—and has removed this work from the shipbuilder’s contract. This deferred work will be completed within the ship’s budgeted end cost and is included within both the $12.887B cost estimate and cost cap. — By performing this deferred work in the post-delivery period using CVN 78 end cost funding, it can be competed and accomplished at lower cost and risk to the overall ship delivery schedule. Importantly, this action uniquely introduces competition within the otherwise sole-source cost-plus environment at the shipyard and is the type of action necessary to complete the ship at the lowest cost possible. — The Navy intends to continue to seek these types of opportunities to drive down the cost and risk of aircraft carrier new construction. — Outfitting/Post Delivery funding will not be used to accomplish this deferred work on CVN 78. — The cost estimate and cost cap for CVN 79 was established in 2006. This estimate did not include adjustment for the near-decade of inflation that would occur between 2006 and the timeframe when CVN 79 would be procured. The CY$2006 $8.1B estimate for CVN 79, escalated to the ships actual years of procurement, equates to the $11.498B budget and cost cap established for CVN 79. The cost cap established in 2006 for CVN 79 and follow ships did not account for: — Potential revision to the cost estimate as a result of experience gained through completion of design, development, construction, and test of the first of class ship, or — Potential upgrades, modernization, or new requirements subsequent to establishing the 2006 CVN 78 design baseline. — The Navy is proceeding with a two-phased plan to deliver CVN 79 as an operationally deployable CVN 78-like repeat under the $11.498M cost cap. The twophasedtwo- Congressional Research Service 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress phased strategy will allow the basic ship to be constructed and tested in the most efficient manner by the shipbuilder (phase I) while enabling select ship systems and compartments to be completed in a second phase wherein the work can be completed more efficiently through competition or the use of skilled installation teams responsible for these activities. Critically, this two-phased approach also enables the Navy to procure and install at the latest date possible shipboard electronic systems which otherwise would be subject to obsolescence prior to CVN 79’s first deployment in the 2027 timeframe. Both phase I and phase II are Congressional Research Service 12 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress funded within the CVN 79 budgeted end cost and are included within both the $11.498B cost estimate and cost cap. — Outfitting/Post Delivery funding will not be used to procure or install systems planned for phase II on CVN 79. — Capability beyond that contained in CVN 78 will be considered using established Navy procedures for ship modernization. — Navy will take these actions consistent with the Congressional cost cap and existing regulations, and will continue to do so with full transparency to ensure there is no cause for confusion or concern regarding obscuring the cost of our aircraft carriers. — The Navy strongly recommends against any change by Congress that would include Post-Delivery and Outfitting within the cost cap because of the potential direct and deleterious impact this may have on training, certification and making these ships ready for operations and deployment. Separate and distinct from ship ‘end cost’, funding is budgeted within a centrally managed account for Navy ships to provide for ship’s outfitting material and spares, crew support and certifications, shipyard services and support (pier services, material handling, security, technical assistance, etc), and correction of government responsible test and trial deficiencies during the post-Delivery period. In certain cases, modernization may be conducted during this post-Delivery period to update/upgrade ship systems based on requirements that have emerged since the ship was originally contracted. This Outfitting/Post Delivery fund is highly variable, by-hull, is not used for ship completion, and accordingly is not included by Congress in the ship’s cost cap.1114 March 2014 GAO Report A March 2014 GAO report assessing major DOD weapon acquisition programs stated the following regarding the status of the CVN-78 program, including the potential for cost growth: Technology Maturity According to the Navy, 7 of the 13 critical technologies for CVN 78 are mature, and the remaining 6 are approaching maturity. To meet required installation dates aboard CVN 78, the Navy produced several of these technologies, such as the volume search radar (VSR), prior to demonstrating their maturity—a strategy GAO’s prior work has shown introduces risk of late and costly design changes and rework. The VSR is a component of the dual band radar (DBR), which has been delivered to CVN 78, and is undergoing design modifications needed to complete shipboard integration. According to the Navy, testing in the spring of 2015 will show whether these modifications were successful or a more extensive redesign of 14 Navy information paper entitled “Navy Response to GAO Report on CVN 78 Class (GAO 15-22, Nov [20]14),” December 3, 2014, provided by Navy Office of Legislative Affairs to CRS and CBO on December 17, 2014. See also Jason Sherman, “Navy To Seek OSD Approval To Revamp CVN-79 Acquisition In Wake Of ‘Affordability’ Review,” Inside the Navy, December 1, 2014. Congressional Research Service 14 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress the system is required, which could delay DBR deliveries by up to 4 years. Deficiencies affecting water twister components—used to absorb energy when arresting aircraft—of the advanced arresting gear (AAG) technology continue to disrupt the system’s development. Recent water twister redesign proved unsuccessful in testing last year. The Navy resolved problems with the redesign and is planning for concurrent testing. Despite these steps, the Navy forecasts AAG land-based testing to be complete in August 2016—a new delay of nearly two years—and after the Navy has accepted CVN 78 delivery. The electromagnetic 11 Navy information paper entitled “Navy Response to GAO Report on CVN 78 Class (GAO 15-22, Nov [20]14),” December 3, 2014, provided by Navy Office of Legislative Affairs to CRS and CBO on December 17, 2014. See also Jason Sherman, “Navy To Seek OSD Approval To Revamp CVN-79 Acquisition In Wake Of ‘Affordability’ Review,” Inside the Navy, December 1, 2014. Congressional Research Service 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress aircraft launch system (EMALS) has successfully launched aircraft during land-based testing using a single launcher and four motor generators. The shipboard system will employ a more complex configuration with more launchers and generators sharing a power interface. Design Maturity CVN 78 completed its 3D product model in November 2009—over a year after the construction contract award. While the model is now considered functionally complete, maintaining design stability depends on technologies fitting within the space, weight, cooling, and power reservations allotted them. Shipboard testing may reveal a need for design changes. Also, as construction progresses, the shipbuilder is discovering “first-ofclass” type design changes, which it is using to update the model prior to CVN 79 construction. Production Maturity According to program officials, CVN 78 is approximately 70 percent complete. Lead ship procurement costs for the lead ship have grown by over 22 percent since construction authorization in fiscal year 2008 due in part to problems encountered in construction. Out-ofsequence work driven largely by material shortfalls, engineering challenges, and delays developing and installing certain critical technologies the Navy provides to the shipbuilder for installation has affected construction progress. Other Program Issues The Navy deferred award of the CVN 79 detail design and construction contract from late fiscal year 2013 to the first quarter of fiscal year 2015. According to the Navy, continuing contract negotiations provide an opportunity to incorporate process improvements into construction plans. The Navy has undertaken an in-depth review of CVN 79 requirements and capabilities to identify cost trades, which it hopes can facilitate an agreement on contract terms. These actions are consistent with recommendations we made in September 2013 to defer the CVN 79 construction contract and to conduct a cost-benefit analysis on Ford-class capability requirements and the time and money needed to field systems to provide these capabilities. Program Office Comments According to the program office, CVN 78 displaced 77,000 tons and was 70 percent complete at launch—the highest levels achieved in aircraft carrier new construction. The program office also reported that labor inefficiencies during ship erection are past and the principal risk remaining is in shipboard testing. Concerns over system integration within platform space, weight, and power reservations have been resolved. Land based testing for EMALS and DBR has progressed enough that program officials do not anticipate significant redesign. Further, the AAG test schedule remains on track to support ship delivery and sea trials. Lastly, the Navy plans to modify the CVN 79 construction preparation contract to Congressional Research Service 15 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress extend the terms of the contract and avoid a production break during negotiations on the detail design and construction contract without delaying ship delivery. Program officials also provided technical comments that were incorporated where deemed appropriate.12 12 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-14340SP, March 2014, p. 74. Congressional Research Service 14 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress15 March 2013 Navy Report to Congress (Released May 2013) A March 2013 report to Congress on the Navy’s plan for building CVN-79 that was released to the public on May 16, 2013, states in its executive summary: As a result of the lessons learned on CVN 78, the approach to carrier construction has undergone an extensive affordability review and the Navy and the shipbuilder have made significant changes on CVN 79 that will significantly reduce the cost to build the ship. These include four key construction areas: — CVN 79 construction will start with a complete design and a complete bill of material — CVN 79 construction will start with a firm set of stable requirements — CVN 79 construction will start with the development complete on a host of new technologies inserted on CVN 78 ranging from the Electromagnetic Aircraft Launch System (EMALS), the Dual Band Radar, and the reactor plant, to key valves in systems throughout the ship — CVN 79 construction will start with an ‘optimal build’ plan that emphasizes the completion of work and ship outfitting as early as possible in the construction process to optimize cost and ultimately schedule performance. In addition to these fundamentals, the Navy and the shipbuilder are tackling cost through a series of other changes that when taken over the entire carrier will have a significant impact on construction costs. The Navy has also imposed cost targets and is aggressively pursuing cost reduction initiatives in its government furnished systems. A detailed accounting of these actions is included in this report. The actions discussed in this report are expected to reduce the material cost of CVN 79 by 10-20% in real terms from CVN 78, to reduce the number of man-hours required to build the CVN 79 by 15-25% from CVN 78, and to reduce the cost of government furnished systems by 5-10% in real terms from CVN 78.1316 For the full text of the navy’s report, see Appendix Athe Appendix. May 2013 Navy Testimony In its prepared statement for a May 8, 2013, hearing on Navy shipbuilding programs before the Seapower subcommittee of the Senate Armed Services Committee, the Navy stated that In 2011, the Navy identified spiraling cost growth [on CVN-78] associated with first of class non-recurring design, contractor and government furnished equipment, and ship production issues on the lead ship. The Navy completed an end-to-end review of CVN 78 construction in December 2011 and, with the shipbuilder, implemented a series of corrective actions to stem, and to the extent possible, reverse these trends. While cost performance has stabilized, incurred cost growth is irreversible.... 13 15 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-14340SP, March 2014, p. 74. 16 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, p. 3. An annotation on the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013. Congressional Research Service 1516 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress In 2011, the Navy identified spiraling cost growth [on CVN-78] associated with first of class non-recurring design, contractor and government furnished equipment, and ship production issues on the lead ship. The Navy completed an end-to-end review of CVN 78 construction in December 2011 and, with the shipbuilder, implemented a series of corrective actions to stem, and to the extent possible, reverse these trends. While cost performance has stabilized, incurred cost growth is irreversible.... As a result of lessons learned on CVN 78, the approach to carrier construction has undergone an extensive affordability review; and the Navy and the shipbuilder have made significant changes on CVN 79 that will reduce the cost to build the ship. CVN 79 construction will start with a complete design, firm requirements, and material economically procured and on hand in support of production need. The ship’s build schedule also provides for increased completion levels at each stage of construction with resulting improved production efficiencies.... Inarguably, this new class of aircraft carrier brings forward tremendous capability and lifecycle cost advantages compared to the NIMITZ-class it will replace. However, the design, development and construction efforts required to overcome the technical challenges inherent to these advanced capabilities have significantly impacted cost performance on the lead ship. The Navy continues implementing actions from the 2012 detailed review of the FORD-Class build plan to control cost and improve performance across lead and follow ship contracts. This effort, taken in conjunction with a series of corrective actions with the shipbuilder on the lead ship, will not recover costs to original targets for GERALD R. FORD [CVN-78], but should improve performance on the lead ship while fully benefitting CVN 79 and following ships of the class.1417 In the discussion portion of the hearing, Sean Stackley, the Assistant Secretary of the Navy for Research, Development and Acquisition (i.e., the Navy’s acquisition executive), testified that First, the cost growth on the CVN-78 is unacceptable. The cost growth dates back in time to the very basic concepts that went into take in the Nimitz-class and doing a total redesign of the Nimitz class to get to a level of capability and to reduce operating and support cost for the future carrier. Far too much risk was carried into the design of the first of the Ford-class. Cost growth stems to the design was moving at the time production started. The vendor base that was responsible for delivering new components and material to support the ship production was (inaudible) with new developments in the vendor base and production plan do not account for the material ordering difficulties, the material delivery difficulties and some of the challenges associated with building a whole new design compared to the Nimitz.... Sir, for CVN-79, we have—we have held up the expenditures on CVN-79 as we go through the details of—one, ensuring that the design of the 78 is complete and repeated for the 79s [sic] that we start with a clean design. Two, we're going through the material procurement. We brought a third party into assessment material-buying practices at Newport News to bring down the cost of material. 17 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and Acquisition) and Vice Admiral Allen G. Myers, Deputy Chief of Naval Operations for Integration of Capabilities and Resources and Vice Admiral Kevin M. McCoy, Commander, Naval Sea Systems Command, Before the Subcommittee on Seapower of the Senate Armed Services Committee on Department of the Navy Shipbuilding Programs, May 8, 2013, p. 8. Congressional Research Service 17 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress And we're metering out the dollars for buying material until it hits the objectives that we're setting for CVN-79 through rewriting the build plan on CVN-79. If you take a look at how the 78 is being constructed, far too much work is being accomplished late in the build cycle. So we are rewriting the build plan for CVN-79, do more work in the shops where it’s more efficient, more work in the buildings where it’s more efficient, less work in the dry dock, less work on the water. And then we're going after the 14 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and Acquisition) and Vice Admiral Allen G. Myers, Deputy Chief of Naval Operations for Integration of Capabilities and Resources and Vice Admiral Kevin M. McCoy, Commander, Naval Sea Systems Command, Before the Subcommittee on Seapower of the Senate Armed Services Committee on Department of the Navy Shipbuilding Programs, May 8, 2013, p. 8. Congressional Research Service 16 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress rates—the labor rates and the investments needed by the shipbuilder to achieve these efficiencies.1518 Later in the hearing, Stackley testified that the history in shipbuilding is since you don't have a prototype for a new ship, the first of class referred to as the lead ship is your prototype. And so you carry a lot of risk into the construction of that first of class. Also, given the nature that there’s a lengthy design development and build span associated with ships, so there is a certain amount of overlap or concurrency that occurs between the development of new systems that need to be delivered with the first ship, the incorporation of the design of those new systems and the actual construction. And so to the extent that there is change in a new ship class then the risk goes up accordingly. In the case of the CVN-78, the degree of change compared to the Nimitz was fairly extraordinary all for good reasons, good intentions, increased capability, increased survivability, significant reduction in operating and support costs. So there was a determination that will take on this risk in order to get those benefits, and the case of the CVN-78, those risks are driving a lot of the cost growth on the lead ship. When you think about the follow ships, now you've got a stable design, now your vendor base has got a production line going to support the production. Now you've got a build plan and a workforce that has climbed up on the learning curve to drive cost down. So you can look at—you can look at virtually every shipbuilding program and you'll see a significant drop-off in cost from that first of class to the follow ships. And then you look for a stable learning curve to take over in the longer term production of a ship class. Carriers are unique for a number of reasons, one of which we don't have an annual procurement of carriers. They're spread out over a five and, in fact, in the case of 78 as much as seven-year period. So in order to achieve that learning, there are additional challenges associated with achieving that learning. And so we're going at it very deliberately on the CVN-79 through the build plan with the shipbuilder to hit the line that we've got to have— the cost reductions that we've got to have on the follow ships of the class.1619 March 2012 Navy Letter to Senator McCain Secretary of the Navy Ray Mabus, in a letter with attachment sent in late March 2012 to Senator John McCain on controlling cost growth in CVN-78, stated: 18 19 Transcript of hearing. Transcript of hearing. Congressional Research Service 18 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Dear Senator McCain: Thank you for your letter of March 21, 2012, regarding the first-of-class aircraft carrier, GERALD R. FORD (CVN 78). Few major programs carry greater importance or greater impact on national security, and no other major program comprises greater scale and complexity than the Navy’s nuclear aircraft carrier program. Accordingly, successful execution of this program carries the highest priority within the Department of the Navy. 15 16 Transcript of hearing. Transcript of hearing. Congressional Research Service 17 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress I have shared in the past my concern when I took office and learned the full magnitude of new technologies and design change being brought to the FORD. Requirements drawn up more than a decade prior for this capital ship drove development of a new reactor plant, propulsion system, electric plant and power distribution system, first of kind electromagnetic aircraft launching system, advanced arresting gear, integrated warfare system including a new radar and communications suite, air conditioning plant, weapons elevators, topside design, survivability improvements, and all new interior arrangements. CVN 78 is a neartotal redesign of the NIMITZ Class she replaces. Further, these major developments, which were to be incrementally introduced in the program, were directed in 2002 to be integrated into CVN 78 in a single step. Today we are confronting the cost impacts of these decisions made more than a decade ago. In my August 29, 2011 letter, I provided details regarding these cost impacts. At that time, I reported the current estimate for the Navy’s share of the shipbuilder’s construction overrun, $690 million, and described that I had directed an end-to-end review to identify the changes necessary to improve cost for carrier design, material procurement, planning, build and test. The attached white paper provides the findings of that review and the steps we are taking to drive affordability into the remaining CVN 78 construction effort. Pending the results of these efforts, the Navy has included the ‘fact of life’ portion of the stated overrun in the Fiscal Year 2013 President’s Budget request. The review also highlighted the compounding effects of applying traditional carrier build planning to a radically new design; the challenges inherent to low-rate, sole-source carrier procurement; and the impact of external economic factors accrued over 15 years of CVN 78 procurement—all within the framework of costplus contracts. The outlined approach for ensuring CVN 79 and follow ship affordability focuses equally upon tackling these issues while applying the many lessons learned in the course of CVN 78 procurement. As always, if I may be of further assistance, please let me know. Sincerely, [signed] Ray Mabus Attachment: As stated Copy to: The Honorable Carl Levin, Chairman [Attachment] Improving Cost Performance on CVN 78 CVN 78 is nearing 40 percent completion. Cost growth to-date is attributable to increases in design, contractor furnished material, government furnished material (notably, the Electromagnetic Aircraft Launching System (EMALS), Advanced Arresting Gear (AAG), and the Dual Band Radar (DBR)), and production labor performance. To achieve the best case outcome, the program must execute with zero additional cost growth in design and material procurement, and must improve production performance. The Navy and the shipbuilder have implemented a series of actions and initiatives in the management and oversight of CVN 78 that cross the full span of contracting, design, material procurement, Congressional Research Service 19 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress government furnished equipment, production planning, production, management and oversight. CVN 78 is being procured within a framework of cost-plus contracts. Within this framework, however, the recent series of action taken by the Navy to improve contract effectiveness are achieving the desired effect of incentivizing improved cost performance and reducing government exposure to further cost growth. Congressional Research Service 18 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress • CVN 78 design has been converted from a ‘level of effort, fixed fee’ contract to a completion contract with a firm target and incentive fee. Shipbuilder cost performance has been on-target or better since this contract was changed. • CVN 78 construction fee has been retracted, consistent with contract performance. However, the shipbuilder is incentivized by the contract shareline to improve upon current performance to meet agreed-to cost goals. • Contract design changes are under strict control; authorized only for safety, damage control, mission-degrading deficiencies, or similar. Adjudicated changes have been contained to less than 1 percent of contract target price. • The Navy converted the EMALS and AAG production contract to a firm, fixed price contract, capping cost growth to that system and imposing negative incentives for late delivery. • Naval Sea Systems Command is performing a review of carrier specifications with the shipbuilder, removing or improving upon overly burdensome or unneeded specifications that impose unnecessary cost on the program. The single largest impact to cost performance to-date has been contractor and government material cost overruns. These issues trace to lead ship complexity and CVN 78 concurrency, but they also point to inadequate accountability for carrier material procurement, primarily during the ship’s advance procurement period (2002-2008). These effects cannot be reversed on CVN 78, but it is essential to improve upon material delivery to the shipyard to mitigate the significant impact of material delays on production performance. Equally important, the systemic material procurement deficiencies must be corrected for CVN 79. To this end, the Navy and shipbuilder have taken the following actions. • The Navy has employed outside supply chain management experts to develop optimal material procurement strategies. The Navy and the shipbuilder are reviewing remaining material requirements to employ these best practices (structuring procurements to achieve quantity discounts, dual-sourcing to improve schedule performance and leverage competitive opportunities, etc.). • The shipbuilder has assigned engineering and material sourcing personnel to each of their key vendors to expedite component qualifications and delivery to the shipyard. • The shipbuilder is inventorying all excess material procured on CVN 78 for transfer to CVN 79 (cost reduction to CVN 78), as applicable. • The Program Executive Officer (Carriers) is conducting quarterly flag-level government furnished equipment summits to drive cost reduction opportunities and ensure on-time delivery of required equipment and design information to the shipbuilder. Congressional Research Service 20 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress The most important finding regarding CVN 78 remaining cost is that the CVN 78 build plan, consistent with the NIMITZ class, focuses foremost on completion of structural and critical path work to support launching the ship on-schedule. This emphasis on structure comes at the expense of completing ship systems, outfitting, and furnishing early in the build process and results in costly, labor-intensive system completion activity during later; more costly stages of production. Achieving the program’s cost improvement targets will require that Congressional Research Service 19 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress CVN 78 increase its level of completion at launch, from current estimate of 60 percent to no less than 65 percent. To achieve this goal and drive greater focus on system completion: • the Navy fostered a collaborative build process review by the shipbuilder with other Tier 1 private shipyards in order to benchmark its performance arid identify fundamental changes that would yield marked improvement; • the shipbuilder has established specific launch metrics by system (foundations, machinery, piping, power panels, vent duct, lighting, etc.) and increased staffing for waterfront engineering and material expediters to support meeting these metrics; • the shipbuilder has linked all of these processes within a detailed integrated master schedule, providing greater visibility to current performance and greater ability to control future cost and schedule performance across the shipbuilding disciplines; • the Navy and shipbuilder are conducting Unit Readiness Reviews of CVN 78 erection units to ensure that the outfitted condition of each hull unit being lifted into the dry-dock contains the proper level of outfitting. These initiatives, which summarize a more detailed list of actions being implemented and tracked as result of the end-to-end review, are accompanied by important management changes. • The shipbuilder has assigned a new Vice President in charge of CVN 78, a new Vice President in charge of material management and purchasing, and a number of new general shop foreman to strengthen CVN 78 performance. • The Navy has assigned a second tour Flag Officer with considerable carrier operations, construction, and program management experience as the new Program-Executive Officer (PEO). • The PEO and shipyard president conduct bi-weekly launch readiness reviews focusing on cost performance, critical path issues and accomplishment of the target for launch completion. • The Assistant Secretary of the Navy (Research, Development, and Acquisition) conducts a monthly review of program progress and performance with the PEO and shipbuilder, bringing to bear the full weight of the Department, as needed, to ensure that all that can be done to improve on cost performance is being done. Early production performance improvements can be traced directly to these actions, however, significant further improvement is required. To this end, the Navy is conducting a line-by-line review of all ‘cost to-go’ on CVN 78 to identify further opportunity to reduce cost and to mitigate risk. Improving Cost Performance on CVN 79 Congressional Research Service 21 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress CVN 79 Advance Procurement commenced in 2007 with early construction activities following in 2011. Authorization for CVN 79 procurement is requested in Fiscal Year 2013 President’s Budget request with the first year of incremental funding. Two years have been added to the CVN 79 production schedule in this budget request, afforded by the fact that CVN 79 will replace CVN 68 when she inactivates. To improve affordability for CVN 79, the Navy plans to leverage this added time by introducing a fundamental change to the Congressional Research Service 20 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress carrier procurement approach and a corresponding shift to the carrier build plan, while incorporating CVN 78 lessons learned. The two principal ‘documents’ which the Navy and shipbuilder must ensure are correct and complete at the outset of CVN 79 procurement are the design and the build plan. Design is governed by rules in place that no changes will be considered for the follow ship except changes necessary to correct design deficiencies on the lead ship, fact of life changes to correct obsolescence issues, or changes that will result in reduced cost for the follow ship. Exceptions to these rules must be approved by the JROC, or designee. Accordingly, the Navy is requesting procurement authority for CVN 79 with the Design Product Model complete and construction drawings approximately 95 percent complete (compared to approximately 30 percent complete at time of lead ship authorization). As well, first article testing and certification will be complete for virtually all major new equipments introduced in the FORD Class. At this point in time, the shipbuilder has developed a complete bill of material for CVN 79. The Navy is working with the shipbuilder to ensure that the contractor’s material estimates are in-line with Navy ‘should cost’ estimates; eliminating non-recurring costs embedded in lead ship material, validating quantities, validating escalation indices, incorporating lead ship lessons learned. The Navy has increased its oversight of contractor furnished material procurement, ensuring that material procurement is competed (where competition is available); that it is fixed priced; that commodities are bundled to leverage economic order quantity opportunities; and that the vendor base capacity and schedule for receipt supports the optimal build plan being developed for production. In total, the high level of design maturity and material certification provides a stable technical baseline for material procurement cost and schedule performance, which are critical to developing and executing an improved, reliable build plan. In order to significantly improve production labor performance, based on timely receipt of design and material, the Navy and shipbuilder are reviewing and implementing changes to the CVN 79 build plan and affected facilities. The guiding principles are: • maximize planned work in the shops and early stages of construction; • revise sequence of structural unit construction to maximize learning curve performance through ‘families of units’ and work cells; • incorporate design changes to improve FORD Class producibility; • increase the size of erection units to eliminate disruptive unit breaks and improve unit alignment and fairness; • increase outfitting levels for assembled units prior to erection in the dry-dock; • increase overall ship completion levels at each key event. Congressional Research Service 22 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress The shipbuilder is working on detailed plans for facility improvements that will improve productivity, and the Navy will consider incentives for capital improvements that would provide targeted return on investment, such as: • increasing the amount of temporary and permanent covered work areas; Congressional Research Service 21 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress • adding ramps and service towers for improved access to work sites and the dry-dock; • increasing lift capacity to enable construction of larger, more fully outfitted super-lifts: An incremental improvement to carrier construction cost will fall short of the improvement necessary to ensure affordability for CVN 79 and follow ships. Accordingly, the shipbuilder has established aggressive targets for CVN 79 to drive the game-changing improvements needed for carrier construction. These targets include: • 75 percent Complete at Launch (15 percent> [i.e., 15 percent greater than] FORD); • 85-90 percent of cable pulled prior to Launch (25-30 percent> FORD); • 30 percent increase in front-end shop work (piping details, foundations, etc); • All structural unit hot work complete prior to blast and paint; • 25 percent increase to work package throughput; • 100 percent of material available for all work packages in accordance with the integrated master schedule; • zero delinquent engineering and planning products; • resolution of engineering problems in < 8 [i.e., less than 8] hours. In parallel with efforts to improve shipbuilder costs, the PEO is establishing equally aggressive targets to reduce the cost of government furnished equipment for CVN 79; working equipment item by equipment item with an objective to reduce overall GFE costs by ~$500 million. Likewise, the Naval Sea Systems Command is committed to continuing its ongoing effort to identify specification changes that could significantly reduce cost without compromising safety and technical rigor. The output of these efforts comprises the optimal build plan for CVN 79 and follow, and will be incorporated in the detail design and construction baseline for CVN 79. CVN 79 will be procured using a fixed price incentive contract.17 Issues Raised in January 2014 DOT&E Report Another issue for Congress concerns CVN-78 program issues that were raised in a January 201420 20 Letter and attachment from Secretary of the Navy Ray Mabus to Senator John McCain, undated but posted at InsideDefnse.com (subscription required) on March 27, 2012. InsideDefense.com’s description of the letter states that it is dated March 26, 2012. Congressional Research Service 23 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Issues Raised in January 2015 DOT&E Report Another oversight issue for Congress concerns CVN-78 program issues raised in a January 2015 report from DOD’s Director, Operational Test and Evaluation (DOT&E)—DOT&E’s annual report for FY2013. The report stated the following in its section on the CVN-78 program: Assessment Test Planning 17 Letter and attachment from Secretary of the Navy Ray Mabus to Senator John McCain, undated but posted at InsideDefnse.com (subscription required) on March 27, 2012. InsideDefense.com’s description of the letter states that it is dated March 26, 2012. Congressional Research Service 22 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress • The current state of the VCVN [Virtual CVN] model does not fully provide for an accurate accounting of SGR [Sortie Generation Rate] due to a lack of fidelity regarding manning and equipment/aircraft availability. Spiral development of the VCVN model continues in order to ensure that the required fidelity will be available to support the SGR assessment during IOT&E [Initial Operational Test and Evaluation]. • A new TEMP [Test and Evaluation Master Plan] is under development to address problems with the currently-approved TEMP. The current TEMP does not adequately address platform-level developmental testing. The Program Office has begun to refine the Post Delivery Test and Trials schedule, but that schedule still lacks sufficient details to ensure reasonable developmental testing. Lack of platform-level developmental testing significantly raises the likelihood of the discovery of platform-level problems during IOT&E. • The Navy plans to deliver CVN-78 in February 2016. The ship’s post-shipyard shakedown availability will follow delivery in 2016. During the post-shipyard shakedown availability installations of some systems will be completed. The first at-sea operational test and evaluation of CVN-78 will begin in JulyFY2014. The report stated the following in its section on the CVN-78 program: Assessment Test Planning • A new TEMP [Test and Evaluation Master Plan for the CVN-78 program] is under development to address problems with the currently-approved TEMP. The TEMP in the approval process improves integrated platform-level developmental testing, reducing the likelihood that platform-level problems will be discovered during IOT&E [Initial Operational Test and Evaluation]. In addition, the Program Office is in the process of refining the post-delivery schedule to further integrate testing. • The current state of the VCVN [Virtual CVN] model does not fully provide for an accurate accounting of SGR [Sortie Generation Rate] due to a lack of fidelity regarding manning and equipment/aircraft availability. Spiral development of the VCVN model continues in order to ensure that the required fidelity will be available to support the SGR assessment during IOT&E. • The Navy plans to take delivery CVN-78 in March 2016. The ship’s post-shipyard shakedown availability will follow delivery in late 2016. During the post-shipyard shakedown availability installations of some systems will be completed. The first at-sea operational test and evaluation of CVN-78 will begin in September 2017. Reliability • CVN-78 includes several systems that are new to aircraft carriers; four of these systems stand out as being critical to flight operations: EMALS [Electromagnetic Aircraft LaunchLaunching System], AAG [Advanced Arresting Gear], DBR [Dual BandBan d Radar], and the Advanced Weapons Elevators (AWEs). Overall, the uncertain reliability of these four systems is the most significant risk to the CVN-78 IOT&E. All four of these systems will be tested for the first time in their shipboard configurations aboard CVN-78. Reliability estimates derived from test data are availablewere provided last year for EMALS and AAG and are discussed below. For DBR and AWE, estimates based on test data are not available and only engineering reliability estimates are available. SGR • It is unlikely that CVN-78 will achieve its SGR requirement. The target threshold is based on unrealistic assumptions including fair weather and unlimited visibility, and that aircraft emergencies, failures of shipboard equipment, ship maneuvers (e.g., to avoid land), and manning shortfalls will not affect flight operations. DOT&E plans to assess CVN-78 performance during IOT&E by comparing to the demonstrated performance of the Nimitz class carriers. A demonstrated SGR less than the requirement but equal to or greater than the performance of the Nimitz class could potentially be acceptable. • During the operational assessment, DOT&E conducted an analysis of past aircraft carrier operations in major conflicts. The analysis concludes that the CVN-78 SGR requirement is well above historical levels and that CVN-78 is unlikely to achieve that requirement. There are concerns with the reliability of key systems that support sortie generation on CVN-78. Poor reliability of these critical systems could cause a cascading series of delays during flight operations that would affect CVN-78’s ability to generate sorties, make the ship more vulnerable to attack, or create limitations during routine operations. DOT&E assesses the poor or unknown reliability of these critical subsystems will be the most significant risk to CVN-78’s successful completion of IOT&E. The analysis also considered the operational implications of a shortfall and concluded that as long as CVN-78 is able to generate sorties Congressional Research Service 23 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress comparable to Nimitz class carriers, the operational implications of CVN-78 will be similar to that of a Nimitz class carrier.18 Manning • Current manning estimates have shortages of bunks for Chief Petty Officers (CPOs) and do not provide the required 10 percent SLA. Per Office of the Chief of Naval Operations Instruction 9640.1B, Shipboard Habitability Program, all new ships are required to have a growth allowance of 10 percent of the ship’s company when the ship delivers. The SLA provides empty bunks to allow for changes in the crew composition over CVN-78’s expected 50-year lifespan and provides berthing for visitors and Service members temporarily assigned to the ship. EMALS • EMALS is one of the four systems critical to flight operations. While testing to date has demonstrated that EMALS should be able to launch aircraft planned for CVN-78’s air wing, the system’s reliability is uncertain. At the Lakehurst, New Jersey, test site, over 1,967 launches have been conducted and 201 chargeable failures have occurred. Based on available data, the program estimates that EMALS has approximately 240 Mean Cycles Between Critical Failure in the shipboard configuration, where a cycle represents the launch of one aircraft. Based on expected reliability growth, the failure rate is presently five times higher than should be expectedThe Navy has stated that in the last year, they did not assess EMALS and AAG reliability due to systems’ redesign and investigative and developmental testing. For DBR and AWE, estimates based on test data are not available and only engineering reliability estimates are available. EMALS • EMALS is one of the four systems critical to flight operations. While testing to date has demonstrated that EMALS should be able to launch aircraft planned for CVN- 78’s air wing, present limitations on F/A-18E/F and EA-18G configurations as well as the system’s reliability remains uncertain. As of December 2013, at the Lakehurst, New Jersey, test site, over 1,967 launches had been conducted with 201 chargeable failures. At that time, the program estimates that EMALS has approximately 240 Mean Cycles Between Critical Failure in the shipboard configuration, where a cycle represents the launch of one aircraft. Based on expected reliability growth, the failure rate for the last reported Mean Cycles Between Critical Failure was five times higher than should have been expected. As of August 2014, the Navy has reported that over 3,017 launches have been conducted at the Congressional Research Service 24 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Lakehurst test site, but have not provided DOT&E with an update of failures. The Navy intends to provide DOT&E an update of failures in December 2014. AAG • AAG is another system critical to flight operations. Testing to date has demonstrated that AAG should be able to recover aircraft planned for the CVN-78 air wing, but as with EMALS, AAG’s reliability is uncertain. At the Lakehurst, New Jersey test site, 71 arrestments were conducted earlier this yearearly in 2013 and 9 chargeable failures occurred. The Program Office estimates that AAG has approximately 20 last provided reliability data in December 2013 and estimated that AAG had approximately 20 Mean Cycles Between Operational Mission Failure in the shipboard configuration, where a cycle represents the recovery of one aircraft. Following these tests, the Navy modified the system and has yet to score reliability of AAG. Based on expected reliability growth as of 2013, the failure rate is presentlywas 248 times higher than should behave been expected. DBR • Previous testing of Navy combat systems similar to CVN-78’s revealed numerous integration problems that degrade the performance of the combat system. Many of these problems are expected to exist on CVN-78. The previous results emphasize the necessity of maintaining a DBR/CVN-78 combat system asset at Wallops Island. The Navy is considering long-term plans (i.e., beyond FY15) for testing DBR at Wallops Island, Virginia, but it is not clear if resources and funding will be available. Such plans are critical to delivering a fully-capable combat system and ensuring lifecyclelife-cycle support after CVN-78 delivery in 2016. JPALS [Joint Precision Approach and Landing System] • The Navy has proposed to the USD(AT&L) Milestone Decision Authority that the program be restructured from its current, land- and sea-based, multiple-increment structure to a single 18 The issue of the sortie generation rate was also discussed in Tony Capaccio, “Hagel Told New Carrier Unlikely to Meet Aircraft Goals,” Bloomberg News, January 10, 2014. Congressional Research Service 24 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress increment focusing on sea-based requirements primarily supporting JSF [Joint Strike Fighter; aka F-35] and future Unmanned Carrier Launched Airborne Surveillance and Strike aircraft. Under this proposed restructuring scheme, there will be no retrofitting of JPALS on legacy aircraft and the Navy will need to maintain both the legacy approach and landing system and JPALS onboard each aircraft-capable ship. JSF • The arresting hook system remains an integration risk as the JSF delivery in 2016. SGR • It is unlikely that CVN-78 will achieve its SGR requirement. The target threshold is based on unrealistic assumptions including fair weather and unlimited visibility, and that aircraft emergencies, failures of shipboard equipment, ship maneuvers, and manning shortfalls will not affect flight operations. DOT&E plans to assess CVN-78 performance during IOT&E by comparing it to the SGR requirement as well as to the demonstrated performance of the Nimitz class carriers. • During the operational assessment, DOT&E conducted an analysis of past aircraft carrier operations in major conflicts. The analysis concludes that the CVN-78 SGR requirement is well above historical levels and that CVN 78 is unlikely to achieve that requirement. There are concerns with the reliability of key systems that support sortie generation on CVN-78. Poor reliability of these critical systems could cause a cascading series of delays during flight operations that would affect CVN-78’s ability to generate sorties, make the ship more vulnerable to attack, or create limitations during routine operations. DOT&E assesses the poor or unknown reliability of these critical subsystems will be the most significant risk to CVN-78’s successful completion of IOT&E. The analysis also considered the operational implications of a shortfall and concluded that as long as CVN-78 is able to generate sorties comparable to Nimitz class carriers, the operational implications of CVN-78 will be similar to that of a Nimitz class carrier. Manning • Current manning estimates have shortages of bunks for Chief Petty Officers (CPOs) and do not provide the required 10 percent SLA for all berthing. The Navy plans to redesignate/design some officer rooms as CPO berthing spaces. Per the Office of the Chief of Naval Operations Instruction 9640.1B, Shipboard Habitability Program, all new ships are required to have a growth allowance of 10 percent of the ship’s company when the ship delivers. The SLA provides empty bunks to allow for changes in the crew composition over Congressional Research Service 25 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress CVN 78’s expected 50-year lifespan and provides berthing for visitors and Service members temporarily assigned to the ship. JPALS • As the Navy reformulates the JPALS Test and Evaluation Master Plan, it faces significant challenges in defining how it will demonstrate the operational effectiveness and operational suitability of the restructured system without a representative aircraft platform. F-35 • The arresting hook system remains an integration risk as the F-35 development schedule leaves no time for discovering new problems. The redesigned tail hook has an increased downward force as well as sharper design that may induce greater than anticipated wear on the flight deck. • JSFF-35 noise levels remain moderate to high risk in JSFF-35 integration and will require modifi ed modified carrier flight deck procedures. -- Flight operations normally locate some flight deck personnel in areas where double hearing hearing protection would be insufficient during F-35 operations. To partially mitigate noise concerns, the Navy will procure new hearing protection with active noise reduction for flight deck deck personnel. -- Projected noise levels one level below the flight deck (03 level), which includes mission planning spaces, will require at least single hearing protection that will make mission planning difficult. The Navy is working to mitigate the effects of the increased noise levels adjacent to the flight deck. • Storage of the JSFF-35 engine is limited to the hangar bay, which will affect hangar bay operations. The impact on the JSFF-35 logistics footprint is not yet known. • Lightning protection of JSFF-35 aircraft while on the flight deck will require the Navy to modify nitrogen carts to increase their capacity. Nitrogen is used to fillfilled in fuel tank cavities while while aircraft are on the flight deck or hangar bay. • F-35. • JSF remains unable to share battle damage assessment and non-traditional Intelligence, Surveillance, and Reconnaissance information captured on the aircraft portable memory device or cockpit voice recorder in real- time. In addition, the CVN-78 remains unable to receive and display imagery transmitted through Link 16 because of bandwidth limitations. ; this problem is not unique to F-35. These capability gaps were identified in DOT&E’s FY12 Annual Report. The Combatant Commanders have requested these capabilities to enhance decision-making. LFT&E [Live Fire Test and& Evaluation] • While the Navy has made substantial effort in component and surrogate testing, this work does not obviate the need to conduct the FSST [Full Ship Shock Trial] to gain the critical empirical data that past testing has repeatedly demonstrated are required to rigorously evaluate the ship’s ability to withstand shock and survive in combat. Shock Trials conducted on both the Nimitz class aircraft carrier and the San Antonio class Amphibious Transport Dock demonstrated the need for and substantial value of conducting the FSST. Postponing the FSST until CVN-79 would cause a five- to seven-year delay in obtaining the data critical to evaluating the survivability of the CVN-78 and would preclude timely modification of subsequent ships of this class to assure their survivability. • CVN-78 has many new critical systems that have not undergone shock trials on other platforms. Unlike past tests on other new classes of ships with legacy systems, the performance of CVN-78’s new critical systems under test is unknown. Congressional Research Service 25The Navy has made substantial progress on defining the scope of the TSST and the Analytical Bridge task. While these portions of the LFT&E Management Plan were adequately defined in the Revision B document, DOT&E returned the LFT&E Management Plan to the Navy solely on the basis of the FSST on CVN 79 verses CVN-78. • CVN-78 has many new critical systems, such as EMALS, AAG, and DBR, that have not undergone shock trials on other platforms. Unlike past tests on other new classes of ships with legacy systems, the performance of CVN-78’s new critical systems is unknown. Congressional Research Service 26 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress • The Navy proposes delaying the shock trial by five to seven years because of the approximately four- to six- month delay required to perform the FSST. The benefit of having test data to affect the design of future carriers in the class outweighs the delay in delivery of CVN-78 to the fleet to conduct this test. The delay is not a sufficient reason to postpone the shock trial. Recommendations • Status of Previous Recommendations. The Navy should continue to address the seveneight remaining FY10, FY11, and FY13 and FY11 recommendations. 1. Adequately test and address integration challenges with JSFF-35; specifically: -- Logistics (unique concerns for storage and transportation) -- Changes required to JBDs [Jet Blast Deflectors] - -- Changes to flight deck procedures due to heat and noise -- Autonomic Logistics Information System integration 2. Finalize plans that address CVN-78 Integrated Warfare System engineering and ship’s self-defense system discrepancies prior to the start of IOT&E. 3. Continue aggressive EMALS and AAG risk-reduction efforts to maximize opportunity for successful system design and test completion in time to meet required in-yard dates for shipboard installation of components. 4. Continue development of a realistic model for determining CVN-78’s SGR, while utilizing realistic assumptions regarding equipment availability, manning, and weather conditions for use in the IOT&E. 5. Provide scheduling, funding, and execution plans to DOT&E for the live SGR test event during the IOT&E. 6. Continue to work with the Navy’s Bureau of Personnel to achieve adequate depth and breadth of required personnel to sufficiently meet Navy Enlisted Classification fit/fill manning requirements of CVN-78. 7. Conduct system-of-systems developmental testing to preclude discovery of deficiencies during IOT&E. • FY13 Recommendations. The Navy should: 1. Address the uncertain reliability of EMALS, AAG, DBR, and AWE. These systems are critical to CVN-78 flight operations, and are the largest risk to the program. 2. Conduct fully integrated, robust, end-to-end testing of the proposed JPALS, to include operations in neutral and potentially hostile electronic warfare environments.19 19 Department of Defense, Director, Operational Test & Evaluation, FY2013 Annual Report, released January 2014, pp. 157-159. See also Olga Belogolova, “Navy Pushes Back On DOT&E Reliability Concerns For Ford-Class Carrier,” Inside the Navy, February 24, 2014. Congressional Research Service 26 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Potential Two-Ship Block Buy on CVN-79 and CVN-80 Another issue for Congress concerns the potential for procuring CVN-79 and CVN-80 together in a two-ship block buy. The Navy currently plans to procure CVN-79 and CVN-80 separately, as one-ship procurements. Procuring the two ships together in a block buy could reduce their combined procurement cost. Procuring two aircraft carriers together in a two-ship block buy has been done on two previous occasions. The Navy procured two Nimitz (CVN-68) class aircraft carriers (CVN-72 and CVN73) together in a block buy in FY1983, and procured another two Nimitz-class aircraft carriers (CVN-74 and CVN-75) together in a block buy in FY1988. The Navy proposed these block buys in the FY1983 and FY1988 budget submissions.20 When the FY1983 block buy was proposed, the Navy estimated that the block buy would reduce the combined cost of CVN-72 and CVN-73 by 5.6% in real terms.21 When the FY1988 block buy was proposed, the Navy estimated that the block buy would reduce the combined cost of CVN-74 and CVN-75 by a considerably larger percentage. GAO stated that the savings would be considerably less than the Navy estimated, but agreed that a two-ship acquisition strategy is less expensive than a single-ship acquisition strategy, and that some savings would occur in a twoship strategy for CVN-74 and CVN-75.22 20 It can also be noted that the Air Force is procuring two Advanced EHF (AEHF) satellites under a two-satellite block buy that the Air Force proposed and Congress approved in FY2012. 21 See General Accounting Office, Request to Fully Fund Two Nuclear Aircraft Carriers in Fiscal Year 1983, MASAD-82-87 (B-206847), March 26, 1982, 10 pp. The figure of 5.6% was derived by dividing $450 million in noninflation cost avoidance shown on page 5 by the combined estimated cost of the two ships (absent a block buy) of $8,024 million shown on page 4. 22 See General Accounting Office, Procurement Strategy For Acquiring Two Nuclear Aircraft Carriers, Statement of Frank Conahan, Assistant Comptroller General, National Security and International Affairs Division, Before the Conventional Forces and Alliance Defense Subcommittee and Projection Forces and Regional Defense Subcommittee of the Senate Armed Services Committee, April 7, 1987, T-NSIAD-87-28, 5 pp. The testimony states on page 2 that “A single ship acquisition strategy is more expensive because materials are bought separately for each ship rather than being combined into economic order quantity buys under a multi-ship procurement.” The report discounted the Navy’s estimated savings of $1,100 million based on this effect on the grounds that if CVN-74 and CVN-75 were not procured in the proposed two-ship block buy, with CVN-74 procured in FY1990 and CVN-75 procured FY1993, it was likely that CVN-74 and CVN-75 would subsequently be procured in a two-ship block buy, with CVN-74 procured in FY1994 and CVN-75 procured in FY1996. For the discussion here, however, the comparison is between the Navy’s current plan to procure CVN-79 and CVN-80 separately and the potential alternative of procuring them together in a block buy. The GAO report commented on an additional $700 million in savings that the Navy estimated would be derived from improving production continuity between CVN-73, CVN-74, and CVN-75 by stating on page 3 that “It is logical to assume that savings are possible through production continuity but the precise magnitude of such savings is difficult to calculate because of the many variables that affect the outcome.” It is not clear how significant savings from production continuity might be in a two-ship block buy for CVN-79 and CVN-80 if the procurement dates for the two ships (FY2013 and FY2018, respectively) are not changed. The GAO report noted that the Navy estimated $500 million in additional savings from avoided configuration changes on CVN-74 and CVN-75 if the ships were procured in FY1990 and FY1993 rather than FY1994 and FY1996. It is not clear how significant the savings from avoided configuration changes might be for a two-ship block buy for CVN-79 and CVN-80. See also CRS Issue Brief IB87043, Aircraft Carriers (Weapons Facts), 13 pp., updated February 10, 1988, and archived March 24, 1988, by Ronald O’Rourke. The report includes a discussion of the above GAO report. The report is out of print and available directly from the author. Congressional Research Service 27 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress The FY1983 and FY1988 block buys each involved procuring two aircraft carriers in a single year. Procuring two carriers in the same year, however, is not mandatory for a two-ship aircraft carrier block buy. The Navy, for example, proposed the block buy for CVN-74 and CVN-75 in the FY1988 budget submission as something that would involve procuring CVN-74 in FY1990 and CVN-75 in FY1993. (Congress, in acting on the FY1988 budget, decided to not only approve the two-ship block buy, but also accelerate the procurement of both CVN-74 and CVN-75 to FY1988.)23 A block buy on CVN-79 and CVN-80 could leave intact the FY2013 procurement date for CVN-79 and the FY2018 procurement date for CVN-80. This would permit the funding for the two ships to be spread out over the same fiscal years as currently planned, although the amounts of funding in individual years would likely change. It is too late to implement a complete block buy on CVN-79 and CVN-80, because some of CVN79, particularly its propulsion plant, has already been purchased. Consequently, the option would be to implement a partial block buy that would include the remaining part of CVN-79 and all of CVN-80. To illustrate the notional scale of the savings that might result from using a block buy strategy on CVN-79 and CVN-80, it can be noted that if such a block buy were to achieve one-third as much percentage cost reduction as the FY1983 block buy—that is, if it were to reduce the combined procurement cost of CVN 79 and 80 by about 1.9%—that would equate to a savings of roughly $470 million on the currently estimated combined procurement cost of CVN-79 and CVN-80. More refined estimates might be higher or lower than this notional figure of $470 million. At a March 19, 2012, briefing for CRS and CBO on the CVN-78 program, CRS asked the Navy whether it was considering the possibility of a block buy on CVN-79 and CVN-80. The Navy stated that it had looked into a narrower option of doing joint purchases of some materials for the two ships. Implementing a block buy on CVN-79 and CVN-80 would require committing to the procurement of CVN-80. Whether Congress would want to commit to the procurement of CVN80, particularly in light of current uncertainty over future levels of defense spending, is a factor that Congress may consider in assessing the option of doing a block buy. If budgetary circumstances were to lead to a decision to end procurement of Ford-class carriers after CVN-79, then much or all of the funding spent procuring materials for CVN-80 could go to waste. At a March 29, 2012, hearing on Navy shipbuilding programs before the Seapower and Projection Forces subcommittee of the House Armed Services Committee, Sean Stackley, the Assistant Secretary of the Navy for Research, Development, and Acquisition (i.e., the Navy’s acquisition executive), stated the following when asked by Representative Robert Wittman about the possibility of a two-ship block buy on CVN-79 and CVN-80: Yes, sir. Let me focus on affordability of the CVN-78 class. We are right now about 40 percent complete construction of the CVN-78 and we’re running into some very difficult cost growth issues across the full span—design, material procurement, and production— material procurement on both contractor and government side. 23 See CRS Issue Brief IB87043, Aircraft Carriers (Weapons Facts), 13 pp., updated February 10, 1988, and archived March 24, 1988, by Ronald O’Rourke. The report is out of print and available directly from the author. Congressional Research Service 28 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress So our first focus right now is to stabilize the lead ship. Let’s get cost under control so we can complete this ship as close to schedule at the lowest cost possible. But in parallel, the Navy is working very closely with the shipbuilder to take a step back and say, one, what are all the lessons we just learned on CVN-78? Two, CVN-78 is a very different ship from the Nimitz [CVN-68]; we cannot expect to build the [CVN-]78 the way we build the [CVN-]68 and—and get to an affordable ship construction plan. So we’re pressing on the way the carrier is built—the build plan for the carrier—to arrive at a more affordable CVN-79. Now, in the process of doing that we’ll take a hard look at what opportunity there is across [CVN-]79 and [CVN-]80, recognizing that we’re going to be limited, again, by [budget] top line. But there are going to be some opportunities that jump out at us. We don’t want to have to replan each carrier. We have a vendor base that is stretched out with the carrier build cycle that for some components that are carrier-unique, that vendor base is—is just struggling to hold on between the five-year gaps. So we have to take a hard look at where does it make sense after we’ve gotten to what I’m calling an optimal build plan for CVN-79 and then be able to come back and—and say, OK, here—on CVN-79 here are some opportunities that if we could, in fact, reach out to CVN-80 we can either avoid a gap in a production line or avoid unnecessary cost growth on that follow ship.24 Later in the hearing, the following exchange occurred: REPRESENTATIVE RICK LARSEN: Finally, we had some discussion about this question with regard to CVNs and trying to find a way to squeeze some costs out, and one of the ideas was to do some—do block buy of certain components of—of—of CVN components. And have you considered that, and what’s your thought on that on block buy on components from [CVN-]79 to [CVN-]80, or whatever, [CVN-]79, [CVN-]79 to [CVN-]80, and so on? ASSISTANT SECRETARY OF THE NAVY SEAN STACKLEY: Yes, sir. At this point in time the Navy and the shipbuilder are sitting side by side putting together a build plan for CVN-79. We’re 40 percent complete construction of the [CVN-]78; we’ve got a lot that we’ve got to, I’ll say, do different on the [CVN-]79 and follow from the lead ship. It’s a very different ship class [compared to the Nimitz class]. So we’re taking a hard look at the build plan [for CVN-78]. We need to get that locked down. And associated with that is the complete bill of materials for the Ford class. At that point in time we'll be able to take a look at... LARSEN: On this, call it bill of materials, what does it make sense—what makes sense in terms of looking long term, beyond the immediate ship? STACKLEY: 24 Source: transcript of hearing. Congressional Research Service 29 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Right. LARSEN: Are there areas of the industrial base that are stressed to the point that it does make sense to look at coupling the CVN-79 and CVN-80 buy? STACKLEY: We’re not at that point yet. I described earlier that I think after we get through this build plan review then we'll be able to come back in ‘14 [FY2014] and identify potential critical items that warrant a block buy approach.25 Later in the hearing, Matthew Mulherin, president of NNS and corporate vice president of HII, stated the following when asked by Representative Robert Wittman about the possibility of a twoship block buy on CVN-79 and CVN-80: Yes, sir. You know, historically you go back, you were exactly right, if you look at the contracts that bought the CVN- 72 and [CVN-]73 there was huge savings that flowed to the second ship, both in the ability to go buy materials, a block buy and get—get discounts there, but also that you did the engineering up front the first time for both hulls so the second ship you really just had the answer, problem, paper [sic] and some of those kind of things the— the kind of the normal course of business to support the waterfront. So I wouldn’t see any different. I think if we were able to do it both for material, for—for the engineering to be able to go pump out drawings that had two-ship applicability—plus, I think it brings the—the—the CVN—if we were to do a two-ship buy for [CVN-]79 and [CVN-]80 it would ensure CVN-80 was a copy of CVN-79, no change into the contract or very minimal, you’re not having a—on the material side you get economic order savings, you don’t have to deal with obsolescence. So absolutely. I think there’s huge opportunity to go do that. You know, you talk to the—the vendor base. They would love to see it. It gives them the ability to go look at—at what investments they need, what work is out in front of them, and go invest in—in training and tools to—to be able to go support that.26 At the March 19, 2012, briefing for CRS and CBO on the CVN-78 program, CRS asked the Navy to examine the option of a block buy on CVN-79 and CVN-80, and inform CRS and CBO of the Navy’s estimate of how much it might reduce the combined procurement cost of CVN-79 and CVN-80. The Navy’s response, dated April 22, 2012, was sent to CRS on May 10, 2012 (i.e., just after the House Armed Services Committee completed its markup of H.R. 4310, the FY2013 National Defense Authorization Act). The response stated: There are several options for procuring aircraft carriers that differ from the current practice; two ship buys and block buys. Navy experience with aircraft carrier two ship buys includes procurement of the CVN 72 and CVN 73 (awarded in FY83), and the CVN 74 and CVN 75 (awarded in FY88). The actual cost returns for these procurements support significant savings compared to other NIMITZ Class single ship buys. This conclusion is based on a comparison of the NIMITZ Class two ship buys (CVN72, 73, 74 & 75) with single ship buys 25 26 Source: Transcript of hearing. Source: Transcript of hearing. Congressional Research Service 30 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress (CVN71 and CVN76). The total ship man-hour comparison shows a 9% reduction. The total ship material comparison in constant dollars shows an 8% reduction. The NIMITZ- Class two ship buys took advantage of a single year of full funding for the combined procurement, and less than three years between the deliveries of each ship. Having both ships fully funded in one year enabled the Navy and shipbuilder to take advantage of two ship-set Economic Order Quantity (EOQ) market savings for material items, and also allowed the shipbuilder to optimize production trades management. The short time between deliveries also resulted in design stability, minimized potential obsolescence, and greater opportunities for learning. Given hard budget constraints in FY13 and FY14, CVN 79 and CVN 80 cannot benefit from a multiyear construct, similar to those requested in PB13 for VIRGINIA Class Submarine and ARLIEGH BURKE Class Destroyers. By the end of FY14, 75% of CVN 79 material will be under contract with suppliers, leaving limited opportunities to implement material savings with multiyear incremental funding. 75% of CVN 80 material would also be incapable of achieving savings, as the material purchases would be placed after CVN 79. CVN 80/81 would present the first opportunity to potentially consider this strategy.27 The Navy’s response states, “Having both ships fully funded in one year enabled the Navy and shipbuilder to take advantage of two ship-set Economic Order Quantity (EOQ) market savings for material items.... ” It can be noted that ships funded in separate years can also take advantage of EOQ savings, provided that the authorizing legislation permits the use of EOQ, and that the FY1988 block buy of CVN-74 and CVN-75 was originally proposed by the Navy as a block buy in which CVN-74 would be procured in FY1990 and CVN-75 in FY1993. The Navy’s response states, “Given hard budget constraints in FY[20]13 and FY[20]14, CVN 79 and CVN 80 cannot benefit from a multiyear construct, similar to those requested in PB[20]1328 for VIRGINIA Class Submarine and ARLIEGH BURKE Class Destroyers.” It can be noted that a block buy on CVN-79 and CVN-80 would not necessarily be a multiyear procurement (MYP) contract, like those requested for the Virginia-class submarine program and the Arleigh Burke (DDG-51) destroyer programs. It can also be noted that Congress may decide to work within budget constraints for FY2013 and FY2014 that might differ from those on which is DOD basing its planning. The Navy’s response states, “By the end of FY14, 75% of CVN 79 material will be under contract with suppliers, leaving limited opportunities to implement material savings with multiyear incremental funding. 75% of CVN 80 material would also be incapable of achieving savings, as the material purchases would be placed after CVN 79.” CRS on May 10, 2012, asked the Navy what percent of the material for CVN-79 would be under contract by the end of FY2012. The Navy’s response, dated May 22, 2012, was sent to CRS on May 25, 2012 (i.e., the same day that the House Appropriations Committee reported H.R. 5856, the FY2013 DOD Appropriations Act). The response stated, “Approximately 47% of CVN 79 direct material will be under contract by the end of FY[20]12.”29 The Navy’s response states that “CVN 80/81 would present the first opportunity to potentially consider this [block buy] strategy.” This statement appears to refer to a strategy of a complete 27 Navy information paper dated April 25, 2012, sent to CRS on May 10, 2012. This is a reference to the President’s budget for FY2013—that is, the Administration’s requested budget for FY2013. 29 Navy information paper dated May 22, 2012, sent to CRS on May 25, 2012. 28 Congressional Research Service 31 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress block buy involving 100% of the material for both carriers. Based on the Navy’s response dated May 22, 2012, a partial block buy on CVN-79 and CVN-80 involving as much as 53% of the material on CVN-79 might be possible, if the block buy were authorized and implemented as part of the FY2013 defense budget. Legislative Activity for FY2015 FY2015 Funding Request As shown in Table 1, the Navy’s proposed FY2014 budget requested $663.0 million in procurement funding to cover cost growth on CVN-78, and $1,300.0 million in procurement funding for CVN-79. The Navy’s request for $663.0 million in procurement funding to cover cost growth on CVN-78 forms part of a request for $1,007.3 million in cost-to-complete funding for various prior-year-funded Navy shipbuilding programs. FY2015 National Defense Authorization Act (H.R. 3979) House CVN-78 Program The House Armed Services Committee, in its report (H.Rept. 113-446 of May 13, 2014) on the FY2015 National Defense Authorization Act (H.R. 4435), recommends approving the Navy’s request for FY2015 procurement funding for the CVN-78 program. (Page 395, line 001, and page 396, line 021). CVN-73 RCOH The report also recommends $483.6 million for the refueling complex overhaul (RCOH) of the aircraft carrier George Washington (CVN-73). (Page 395, line 004.) As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as an issue in Congress’s review of DOD’s proposed FY2015 budget. Section 1024 of H.R. 4435 as reported states: SEC. 1024. LIMITATION ON EXPENDITURE OF FUNDS UNTIL COMMENCEMENT OF PLANNING OF REFUELING AND COMPLEX OVERHAUL OF THE U.S.S. GEORGE WASHINGTON. Not more than 50 percent of the funds authorized to be appropriated or otherwise made available under section 301 of this Act for the Office of the Secretary of Defense for fiscal year 2015 may be obligated or expended until the Secretary of Defense obligates funds to commence the planning and long lead time material procurement associated with the refueling and complex overhaul of the U.S.S. George Washington (CVN-73). Congressional Research Service 32 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Senate CVN-78 Program The Senate Armed Services Committee, in its report (S.Rept. 113-176 of June 2, 2014) on the FY2015 National Defense Authorization Act (S. 2410), recommends approving the Navy’s request for FY2015 procurement funding for the CVN-78 program. (Page 323, line 1, and page 324, line 21). CVN-73 RCOH The report recommends in effect transferring from the Operation and Maintenance, Navy (OMN) account to the Shipbuilding and Conversion, Navy (SCN) account the Navy’s request for $46 million in FY2015 funding for defueling the aircraft carrier George Washington (CVN-73), so as to support a refueling complex overhaul (RCOH) for that ship. (Page 323, line 04.) As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as an issue in Congress’s review of DOD’s proposed FY2015 budget. Regarding this transfer of funds, S.Rept. 113-176 states: Aircraft carrier defueling planning funds The budget request included $46.0 million in the Operation and Maintenance, Navy (OMN) account for advance planning funding for defueling of the USS George Washington (CVN– 73) in fiscal year 2017. It is the committee’s intent that the Navy proceed with the refueling and complex overhaul of the USS George Washington (CVN–73) should additional funds be made available in fiscal year 2015 for that purpose. Therefore, the committee recommends a reduction of $46.0 million in OMN, and an increase of $46.0 million for CVN Refueling Overhauls in the Shipbuilding and Conversion, Navy account. (Page 72) Section 123 of S. 2410 as reported states: SEC. 123. AUTHORITY TO TRANSFER CERTAIN FUNDS FOR REFUELING OF AIRCRAFT CARRIER AND CONSTRUCTION OF AMPHIBIOUS SHIP. (a) In General- To the extent provided in appropriations Acts, upon a determination described in subsection (b), the Secretary of the Navy is authorized to transfer funds available in Shipbuilding and Conversion, Navy or any other Navy procurement account for either or both of the following purposes: (1) Up to $650,000,000 to conduct a refueling and complex overhaul of the U.S.S. George Washington (CVN-73). (2) Up to $650,000,000 for the ship construction of a San Antonio class amphibious ship. (b) Determination- A determination described in this subsection is a determination by the Secretary of the Navy that— Congressional Research Service 33 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress (1) unobligated balances are available in the program or programs from which funds will be transferred pursuant to subsection (a) due to slower than expected program execution; and (2) the transfer of funds will fill a high priority military need and is in the best interest of the Department of the Navy. (c) Contingent Authorization- The Secretary of the Navy is authorized to enter into a contract for the procurement of one San Antonio class amphibious ship beginning in fiscal year 2015, and to use incremental funding for the procurement of that ship, if additional funds are made available for such purpose in fiscal year 2015 and the Secretary determines that such procurement will fill a high priority military need and is in the best interests of the Department of the Navy. (d) Effect on Authorization Amounts- A transfer made from one account to another under the authority of this section shall be deemed to increase the amount authorized for the account to which the amount is transferred by an amount equal to the amount transferred. (e) Construction of Authority- The transfer authority under this section is in addition to any other transfer authority provided in this Act. Regarding Section 123, S.Rept. 113-176 states: Authority to transfer certain funds for refueling of aircraft carrier and construction of amphibious ship (sec. 123) The committee recommends a provision that would authorize the Secretary of the Navy to transfer funds available in the Shipbuilding and Conversion, Navy (SCN), or other Navy procurement account for either or both of the following purposes: (1) Up to $650.0 million to conduct a refueling and complex overhaul of the USS George Washington (CVN–73). (2) Up to $650.0 million to build a San Antonio-class amphibious ship. The provision would require that the Secretary make a determination that unobligated balances to be transferred are available due to slower than expected program execution, and the transfer of funds will fill a high priority military need and is in the best interest of the Department of the Navy. It is the committee’s intent that the Navy proceed with the refueling and complex overhaul of the USS George Washington (CVN–73) should additional funds be made available in fiscal year 2015 for that purpose. Finally, the provision would authorize the Secretary to use incremental funding for a San Antonio-class ship if additional funds are made available in fiscal year 2015 for that purpose and the Secretary determines that such procurement will fill a high priority military need and is in the best interest of the Department of the Navy. The committee expects that, if the Secretary chooses to transfer funds for the San Antonioclass program in fiscal year 2015, the Secretary will use funds from fiscal year 2015 and fiscal year 2016 to fully fund any new San Antonio-class ship put on contract during fiscal year 2015 or fiscal year 2016. (Pages 8-9) Section 1021 of S. 2410 as reported states: Congressional Research Service 34 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress SEC. 1021. LIMITATION ON USE OF FUNDS FOR INACTIVATION OF U.S.S. GEORGE WASHINGTON. No funds authorized to be appropriated by this Act or otherwise made available for fiscal year 2015 for the Navy may be obligated or expended to conduct tasks connected to the inactivation of the U.S.S. George Washington (CVN-73) unless such tasks are identical to tasks that would be necessary to conduct a refueling and complex overhaul of the vessel. Regarding Section 1021, S.Rept. 113-176 states: Limitation on use of funds for inactivation of U.S.S. George Washington (sec. 1021) The committee recommends a provision that would prevent the Navy from obligating or expending any funds in fiscal year 2015 on inactivating the U.S.S. George Washington (CVN–73) unless such obligation or expenditure is to support tasks that are identical to tasks that would be necessary to conduct a refueling complex overhaul (RCOH) of the ship. The Navy had planned to conduct an RCOH on CVN–73, beginning in fiscal year 2016. The fiscal year 2015 budget request altered that plan to drop the RCOH and inactivate CVN–73. Congress has already authorized and appropriated $329.7 million for the CVN–73 RCOH. The plan for fiscal year 2015 submitted with the fiscal year 2014 budget for the Navy was to request another $491.1 million for advance procurement of the CVN–73 RCOH. In lieu of the plan, the fiscal year 2015 budget request and the future years defense program (FYDP) supports inactivation of CVN–73. Department of Defense (DOD) officials have stated DOD will defer the decision until 2016 on whether to refuel and maintain CVN–73 or inactivate the ship. The committee is concerned that DOD submitted a fiscal year 2015 budget request and FYDP that are inconsistent with DOD’s stated intent to defer a decision on the refueling, and with the requirement of section 5062(b) of title 10, United States Code, that the Navy maintain 11 operational aircraft carriers. In testimony, Secretary of Defense Charles Hagel confirmed that 11 carriers are a statutory requirement saying, “We follow the authorization and appropriations direction of Congress. We follow the law.” Secretary Hagel explained the dichotomy between an avowed plan to maintain 11 operational aircraft carriers and the FYDP by saying he was waiting for a sign from someone, presumably Congress, that DOD would get the partial relief from the effects of sequestration reflected in the FYDP. The committee has seen no evidence that the requirement for maintaining 11 operational carriers has diminished. In fact, senior Navy leaders have repeatedly stated the need for 11 carriers as the minimum number required to execute the President’s National Military Strategy. Senior military officers have testified that global requirements argue for an even larger number of aircraft carriers. The Commander of U.S. Pacific Command noted that, “Based on the world as it is, about 11 aircraft carriers is just—is just barely making it today.” The aircraft carrier remains the most visible projection of military force abroad and is an effective instrument for shaping the perception of allies and potential foes alike. The committee is concerned that inactivating an aircraft carrier with 20 to 30 years of useful service life remaining is a very inefficient use of defense resources and would be inconsistent with implementing the administration’s strategic shift toward the Asia-Pacific region, and such an action would send the wrong signals about our determination to support that shift. Congressional Research Service 35 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Complying with the letter of this section requires that the administration either submit a budget that supports a fleet with 11 operational aircraft carriers or submit a legislative proposal to amend title 10 to readjust the requirement. The administration has done neither. This provision would ensure that the Navy maintains a path of obligations and expenditures consistent with the statutory requirement to maintain 11 operational aircraft carriers. The committee directs the Secretary of the Navy to report on the effect on capabilities for power projection and global engagement, as it affects the Navy’s ability to meet the Defense Strategic Guidance, moving to a permanent force structure of fewer than 11 operational carriers. This report should include a classified annex that describes the Navy’s ability to meet the combatant commanders’ requirements, both at the current force level and the impact of a force level with fewer than the required 11 operational carriers. This report should also specify what the effects of such action would be on operational deployments, overall readiness, and on sailors and their families. The report should identify potential effects on the shipbuilding industrial base, on the remainder of the RCOH program, on other shipbuilding programs, and on other acquisition programs. The Secretary of the Navy should submit that report with the fiscal year 2016 budget request. (Pages 164-165) Final Version CVN-78 Program The joint explanatory statement for the FY2015 National Defense Authorization Act (H.R. 3979) recommends approving the Navy’s request for FY2015 procurement funding for the CVN-78 program (PDF page 375 of 513, lines 001 and 021). CVN-73 RCOH The joint explanatory statement also recommends $483.6 million for the refueling complex overhaul (RCOH) of the aircraft carrier George Washington (CVN-73) (PDF page 375 of 513, line 004). As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as an issue in Congress’s review of DOD’s proposed FY2015 budget. Section 1023 of H.R. 3979 states: SEC. 1023. LIMITATION ON USE OF FUNDS FOR INACTIVATION OF U.S.S. GEORGE WASHINGTON. No funds authorized to be appropriated by this Act or otherwise made available for fiscal year 2015 for the Navy may be obligated or expended to conduct tasks connected to the inactivation of the U.S.S. George Washington (CVN-73) unless such tasks are identical to tasks that would be necessary to conduct a refueling and complex overhaul of the vessel. Regarding Section 1023, the joint explanatory statement states: Limitation on use of funds for inactivation of U.S.S. George Washington (sec. 1023) The House bill contained a provision (sec. 1024) that would prohibit spending more than 50 percent of the funds authorized and appropriated for the Office of the Secretary of Defense until the Secretary of Defense obligates funds for commencing, planning, and buying long lead time materials for the refueling and complex overhaul of the USS George Washington (CVN-73). Congressional Research Service 36 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress The Senate committee-reported bill contained a similar provision (sec. 1021) that would prohibit spending any funds for inactivation of the USS George Washington unless such tasks are identical to tasks that would be necessary to conduct a refueling and complex overhaul of the vessel. The agreement includes the Senate provision. We note that the administration did not include a budget request to support the nuclear refueling and complex overhaul of the USS George Washington (CVN-73) in fiscal year 2015. In a report to Congress titled “Estimated Impacts of Sequestration- Level Funding” dated April 2014, the Department of Defense indicated that “if Congress acts to support outyear funding at the PB15 level, the additional $6.3B necessary to retain CVN 73 would be reflected in next year’s budget.” Consistent with section 5062 of title 10, United States Code, and multiple testimonies from the combatant commanders, we believe that Congress has been unambiguous about the support of 11 operational aircraft carriers and have provided sufficient authorization of appropriations in this Act to maintain this carrier force structure. We fully anticipate that the administration will support a budget request for fiscal year 2016 that is consistent with title 10, United States Code. (PDF pages 155-156 of 513.) FY2015 DOD Appropriations Act (Division C of H.R. 83/P.L. 113235) House CVN-78 Program The House Appropriations Committee, in its report (H.Rept. 113-473 of June 13, 2014) on the FY2015 DOD Appropriations Act (H.R. 4870), recommends reducing by $10.575 million the Navy’s request for FY2015 procurement funding for the CVN-78 program, with the reduction being for “CANES [Consolidated Afloat Networks and Enterprise Services] cost growth” ($2.051 million); “CANES system engineering growth” ($1.543 million); “Digital modular radio cost growth” ($1.092 million); “IFF [Identification Friend or Foe system] cost growth” ($1.573 million); SPN-46 [radar] cost growth” ($1.473 million); and “Technical engineering services growth” ($2.843 million). (Page 163, lines 1 and 21, and page 164, line 1.) CVN-73 RCOH The report recommends $491.1 million for the refueling complex overhaul (RCOH) of the aircraft carrier George Washington (CVN-73). (Page 163, unnumbered line below line 3, and page 164, line 5.) As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as an issue in Congress’s review of DOD’s proposed FY2015 budget. H.Rept. 113-473 states: AIRCRAFT CARRIER REFUELING The Navy includes no funding in the fiscal year 2015 budget request for the refueling of the aircraft carrier USS George Washington (CVN–73). While the Secretary of the Navy Congressional Research Service 37 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress explained this as a cost saving measure and a deferral of the actual refueling decision, the Committee believes it to be a shortsighted position since the Congress has already appropriated in excess of $500,000,000 towards the effort. The George Washington will have half of its service life remaining after being refueled. Nearly $3,000,000,000 was invested for the construction of the George Washington in 1983, and the Committee believes that walking away from the George Washington halfway through its service life is shortsighted. The Committee is also concerned with the Navy’s lack of budgetary discipline, sending a fiscally broken program to Congress for the second consecutive year. Last year, the Secretary of the Navy did not fully fund the procurement of the two submarines requested, forcing Congress to provide nearly $1,000,000,000 to fully fund the program. Again this year, the Committee must provide $789,300,000 to maintain the CVN–73 refueling schedule, despite the Navy’s claim it can simply defer the decision to fiscal year 2016. Therefore, the Committee provides $789,300,00030 to maintain the CVN–73 refueling schedule, and directs the Secretary of the Navy to fully fund the remaining cost of the CVN– 73 refueling in fiscal year 2016. (Pages 165-166) Senate CVN-78 Program The Senate Appropriations Committee, in its report (S.Rept. 113-211 of July 7, 2014) on H.R. 4870, recommends reducing by $70 million the Navy’s request for FY2015 procurement funding for the CVN-78 program (page 138, line 1), with the reduction being for “Restoring acquisition accountability: Contracting efficiencies” (page 139, line1). S.Rept. 113-211 states: CVN 79.—The Committee understands that in light of significant cost overruns on CVN 78, USS Ford, the Navy is working diligently to reduce costs of the follow-on ship of the class, CVN 79, USS Kennedy. The Committee further understands that this includes innovative contracting strategies leading to greater competition. The Committee commends the Navy for this approach and believes that additional savings could be achieved as a result of increased competitive acquisition strategies. (Page 140) CVN-73 RCOH The report recommends $483.6 million for the refueling complex overhaul (RCOH) of the aircraft carrier George Washington (CVN-73). (Page 138, unnumbered line below line 3, and page 139, line 5.) As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as an issue in Congress’s review of DOD’s proposed FY2015 budget. S.Rept. 113-211 states: CVN 73 REFUELING AND COMPLEX OVERHAUL [RCOH] The fiscal year 2015 budget request includes no funds to continue the refueling and complex overhaul of CVN 73, USS George Washington. The Committee notes that $329,700,000 has previously been appropriated in the Shipbuilding and Conversion, Navy account for the CVN 73 RCOH to support the aircraft carrier’s drydock induction in September 2016. With 30 This figure includes $491.1 million in the Shipbuilding and Conversion, Navy (SCN) appropriation account plus additional funding elsewhere in the Navy’s budget that supports the CVN-73 RCOH. Congressional Research Service 38 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress the fiscal year 2015 budget submission, the Navy announced its intention to make a decision with the fiscal year 2016 budget submission as to whether to refuel or prematurely retire CVN 73. The Committee understands that deferring this decision creates significant programmatic and operational schedule delays for the RCOH. CVN 73 has more than 20 years of service life remaining, and the Navy cannot meet all U.S. combatant commanders’ requirements with the current aircraft carrier fleet. Furthermore, U.S. law requires the Navy to maintain not less than 11 operational aircraft carries. The Committee notes that contrary to its previously stated position, the Navy has now decided to immediately continue CVN 73 RCOH with previously appropriated funds. The Committee fully supports this decision. Therefore, the Committee recommendation includes an additional $849,800,000 in the Navy’s military personnel, operation and maintenance, shipbuilding, and other procurement accounts to fully fund the fiscal year 2015 requirement for CVN 73 RCOH, which will mitigate the schedule delays caused by the Navy’s inaction. The Committee expects the Navy to include all remaining funds required to complete the CVN 73 RCOH in the Future Years Defense Program accompanying the fiscal year 2016 budget submission. (Page 10) Final Version CVN-78 Program The explanatory statement for the FY2015 DOD Appropriations Act (Division C of H.R. 83/P.L. 113-235 of December 16, 2014) reduces the Navy’s request for FY2015 procurement funding for the CVN-78 program by $80.575 million, consisting of $2.051 million for “CANES [Consolidated Afloat Networks and Enterprise Services] cost growth,” $1.543 million for “CANES system engineering growth,” $1.092 million for “Digital modular radio cost growth,” $1.573 million for “IFF [Identification Friend or Foe system] cost growth,” $1.473 million for “SPN-46 [radar] cost growth,” $2.843 million for “Technical engineering services growth,” and $70 million for “Contracting efficiencies” (PDF page 162 of 368, line 1 [where the reductions occurred] and line 21). CVN-73 RCOH The explanatory statement for Division C of H.R. 83/P.L. 113-235 provides $483.6 million for the refueling complex overhaul (RCOH) of the aircraft carrier George Washington (CVN-73) (PDF 162 of 368, line 5). As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as an issue in Congress’s review of DOD’s proposed FY2015 budget. Congressional Research Service 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Appendix A. March 2013 Navy Report to Congress on Construction Plan for CVN-79 This appendix reprints a March 2013 Navy report to Congress on the Navy’s construction plan for CVN-79.31 318. Address the uncertain reliability of EMALS, AAG, DBR, and AWE. These systems are critical to CVN-78 flight operations, and are the largest risk to the program. • FY14 Recommendations. The Navy should: 1. Aggressively fund and address a solution for the excessive EMALS holdback release dynamics during F/A-18E/F and EA-18G catapult launches with wing-mounted 480-gallon EFTs. Congressional Research Service 27 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 2. Plan for fully integrated, robust, end-to-end testing of the restructured JPALS onboard both manned high-performance and unmanned aircraft, including operations in neutral and potentially hostile electronic warfare environments.21 Potential for Combined Material Purchase for CVNs 80 and 81 Another potential issue for Congress is the possibility of reducing the procurement costs of CVN80 and CVN-81 (a carrier scheduled for procurement in FY2023) through the use of combined purchases of materials and components for the two ships. The issue was discussed at a February 25, 2015, hearing on Department of the Navy acquisition programs before the Seapower and Projection Forces subcommittee of the House Armed Services Committee. At this hearing, the following exchange occurred: REPRESENATIVE WITTMAN (continuing): Secretary Stackley, traditionally, as you look at aircraft carrier advice, we've done them in two-ship procurements....22 We've seen with Arleigh Burke-class destroyers as we purchase ships in groups [i.e., under multiyear procurement contracts], we've seen about 15 percent savings when we do that just because of certainties especially for our suppliers for those ships especially aircraft carriers. Is there any consideration given to grouping advance procurement on CVN 80 and CVN 81...? SEAN STACKLEY, ASSISTANT SECRETARY OF THE NAVY FOR RESEARCH, DEVELOPMENT, AND ACQUISITION: Let me start with the advance procurement for CVN 80 and CVN 81. There's strong argument for why that makes great sense. When you're procuring an aircraft carrier about once every five years and you're relying on a very unique industrial base to do that what you don't want to do is go through the start-stop-start-stop cycle over a stretched period of time and that's a big cost impact. But the challenge is by the same token, the build cycle for our carrier is greater than 10 years. So CVN 79, for example, she started her advance procurement in [FY]2009 and then she will be delivering to the Navy in 2022. So that's a 13-year period. So when you talk about doubling down and buying material to support two carriers five years apart that have a 13-year build span, you're trying to buy material as much as 18 years ahead of when the carrier went through the fleet. So it's a—it makes great sense looking at just from the program's perspective on why we want to do that to drive the cost of the carrier down, there's risk associated with things like not necessarily obsolescence but change associated with the carrier because the threat changes and that brings change. 21 Department of Defense, Director, Operational Test & Evaluation, FY2014 Annual Report, released January 2015, pp. 168-170. 22 This appears to be a reference to the two-ship aircraft carrier buys of FY1983 (CVNs 72 and 73) and FY1988 (CVNs 74 and 75). Congressional Research Service 28 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress And then the investment that far in advance when the asset actually interests the fleet. As the acquisition guy, I will argue for why we need to do that but getting through -- carrying that argument all the way through to say that we're going to take the [CVN] 80 which is in [FY]2018 ship, the [CVN] 81 which is at [sic:an] [FY]2023 ship, buy material early for that 2023 ship delivering to the Navy in the mid 2030s. That's going to be a hard—it's going to be hard for me to carry the day in terms of our budget process. WITTMAN: So we have to have the compelling case for the specific things that from industrial base perspective from a move the needle from a cost perspective justify the combined buys of [CVN] 80 and [CVN] 81 together. Well, it seems like even if the scale is an issue as far as how much you've have to expand to do that and manage that within the budget, you could at least then identify those critical suppliers and look for certainty to make sure that they can continue providing those specialty parts and if you can at least pair it down, again, at a critical mass where you can demonstrate economies scale saving that you get at least say, these are the areas we need to maintain this industrial base especially for small scale suppliers that rely on certainty to continue that effort. So have you all given any thoughts to be able to scale at least within that area maybe not to get 15 percent savings but still create certainty, make sure the suppliers are there but also gain saving. STACKLEY: Yes, sir. We have a very conservative effort going on for the Navy and Newport News [Shipbuilding] on all things cost related to the CVN 78 class for all the right reasons. We are looking ahead at [CVN] 80 which is a 2016— the advance procurement starts in 2016 for the [CVN] 80, most of that could be nuclear material. But Newport News [Shipbuilding] has bought the initiative to the table in terms of combined buys from material and now we have to sort out can we in fact come up with the right list of material that make sense to buy early, to buy combined, to get the savings and not just savings people promising savings in the (inaudible) but to actually to be able to book the savings so we can drive down the cost to those carriers. So we are—I would say that we're working with industry on that. We've got a long way to go to be able to carry the day inside the budget process. First inside the building and then again, I will tell you, we're going to have some challenges convincing some folks on the Hill that this makes sense to invest this early in the future aircraft carrier.23 23 Source: transcript of hearing. Earlier versions of this CRS report discussed the possibility for reducing the procurement costs of CVN-79 and CVN-80 through the use of a block buy of the two ships. Congressional Research Service 29 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Legislative Activity for FY2016 FY2016 Funding Request As shown in Table 1, the Navy’s proposed FY2016 budget requests $123.8 million in cost-tocomplete procurement funding to cover cost growth on CVN-78, $1,634.7 million in procurement funding for CVN-79, and $874.7 million in advance procurement (AP) funding for CVN-80. Congressional Research Service 30 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Appendix. March 2013 Navy Report to Congress on Construction Plan for CVN-79 This appendix reprints a March 2013 Navy report to Congress on the Navy’s construction plan for CVN-79.24 24 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, 17 pp. An annotation on the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013. Congressional Research Service 40 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 41 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4231 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4332 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4433 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4534 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4635 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4736 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4837 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 4938 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 5039 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 5140 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 5241 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 5342 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 5443 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 5544 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 56 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 57 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Appendix B. Refueling Complex Overhaul (RCOH) for George Washington (CVN-73) An additional issue relating to aircraft carriers that has been raised by the Navy’s proposed FY2015 budget concerns funding for the mid-life nuclear refueling overhaul of the aircraft carrier George Washington (CVN-73). This appendix presents background information and potential oversight questions for Congress relating to this issue. To operate for a full 50-year life, existing Nimitz (CVN-68) class nuclear-powered carriers are given a mid-life nuclear refueling overhaul, called a refueling complex overhaul (RCOH), when they are 20 to 25 years old, which is when their original nuclear fuel core has been exhausted. The RCOH gives the ship a new nuclear fuel core sufficient to power the ship for the remainder of its 50-year life. The RCOH also involves a significant amount of other overhaul, repair, and modernization work on the ship. An RCOH requires about 44 months from contract award to delivery. RCOHs are funded through the Navy’s shipbuilding account (the Shipbuilding and Conversion, Navy [SCN] appropriation account). RCOHs are done primarily at Huntington Ingalls Industries/Newport News Shipbuilding (HII/NNS) in Newport News, VA, and form a significant part of HII/NNS’s business base, along with construction of new nuclear-powered aircraft carriers and construction of new nuclearpowered submarines. RCOHs in recent years have been scheduled in a more or less heel-to-toe fashion at HII/NNS—when one RCOH is done, the next one is scheduled to begin soon thereafter. RCOHs are done in a particular dry dock at HII/NNS, so a carrier undergoing an RCOH in that dry dock must have its work finished and depart the dry dock before the following carrier can be moved into the dry dock for its RCOH. The next carrier scheduled for an RCOH is the George Washington (CVN-73). The total estimated cost of the CVN-73 RCOH in the Navy’s FY2014 budget submission was $4,738.2 million (i.e., about $4.7 billion). Until the FY2015 budget submission, the CVN-73 RCOH was scheduled for FY2016. The CVN73 RCOH received $12 million in advance procurement (AP) funding in FY2012, $69.9 million in AP funding in FY2013, and $245.8 million in AP funding in FY2014. Under the Navy’s FY2014 budget submission, another $491.1 million in AP funding was projected for FY2015, and the balance of the RCOH’s estimated cost of $4,738.2 million was to be provided in FY2016 and FY2017. As part of its FY2015 budget submission, DOD removed funding for the CVN-73 RCOH from the FY2015-FY2019 Future Years Defense Plan (FYDP) and is proposing to defer the question of whether to proceed with the CVN-73 RCOH until next year, when Congress will consider the FY2016 defense budget. The Navy’s proposed FY2015 budget includes about $46 million in funding in the Operation and Maintenance, Navy (OMN) appropriation account to defuel CVN73. Defueling the ship (i.e., removing the original nuclear fuel core) is an initial step to be performed on the ship at NNS, regardless of whether the ship is to undergo an RCOH or be inactivated. DOD and Navy officials state that if Congress provides an indication this year that it supports the defense spending levels in the FY2015-FY2019 FYDP, which are higher than those called for in the Budget Control Act of 2011 as amended, then the FYDP would be reformulated for FY2016 Congressional Research Service 58 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress and subsequent years to include the roughly $7.0 billion in additional funding that would be needed over the FYDP to fund the CVN-73 RCOH and keep the ship and its associated carrier air wing in service.32 Of this $7.0 billion in additional funding, $796.2 million would be required in FY2015.33 DOD and Navy officials state that if Congress does not provide an indication this year that it supports the defense spending levels in the FYDP, CVN-73 would instead be inactivated (i.e., permanently retired from service), and its associated air wing would be disestablished. Other things held equal, inactivating CVN-73 would reduce the Navy’s carrier force to 10 ships for the next 25 years or so (i.e., the period of time that CVN-73 would have remained in service if it had received an RCOH). The Navy states that, of the funding for the CVN-73 RCOH that was provided in FY2012 and FY2013, $20.6 million represent sunk costs that would not be recoverable if CVN-73 were not to receive an RCOH. The Navy states that this $20.6 million “primarily supported prime contractor and government initial planning efforts for the refueling overhaul as well as some initial modernization GFI [government-furnished information] development efforts.”34 Navy officials state that deferring until next year the decision on whether to proceed with the CVN-73 RCOH would mean that the RCOH, if were to occur, would be delayed some number of months from the schedule shown in the Navy’s FY2014 budget submission, and consequently would likely become an FY2017 action rather than an FY2016 action. Navy officials state that if the delay in the start of the RCOH were not more than a certain number of months, it would not cause a cascading delay in the schedule for the following RCOH (to be done on CVN-74), because there is currently some slack time on the back end of the CVN-73 RCOH period to absorb some delay in the CVN-73 RCOH without affecting the schedule for the CVN-74 RCOH. 10 U.S.C. 5062(b) states that “The naval combat forces of the Navy shall include not less than 11 operational aircraft carriers.” The requirement as stated in this statute is not contingent on the DOD budget being at a certain level in coming years. To the contrary, the central purpose of 10 U.S.C. 5062(b) is to act as a mandate to the executive branch to support force of not less than 11 carriers in executive branch planning, regardless of budgetary or other circumstances. DOD has not, as part of its FY2015 budget submission, requested that 10 U.S.C. 5062(b) be amended or repealed. Potential oversight questions for Congress include the following: • Is DOD’s proposal to treat the issue of whether to proceed with the CVN-73 RCOH (and consequently whether there are to be 10 or 11 carriers for the next 25 32 The estimated total cost to perform the CVN-73 RCOH and retain the carrier and its associated air wing is about $8.1 billion. (This figure includes about $5.9 to perform the RCOH and keep the ship in service, about $1.4 billion to retain the air wing, and about $800 million for associated logistics, manpower, and training costs.) The FY2015-FY2019 FYDP currently includes about $1.1 billion to support the inactivation of CVN-73. Reprogramming this $1.1 billion in inactivation funding to support the RCOH would leave a requirement for about $7.0 billion in additional funding. Source: Navy information paper provided to CRS by Navy Office of Legislative Affairs on April 7, 2014. 33 The total estimated requirement for FY2015 is $842.2 million. This figure includes the $46 million currently in the budget for the ship’s defueling, leaving a net requirement of $796.2 million in additional funding for FY2015. Source: Navy information paper provided to CRS by Navy Office of Legislative Affairs on April 7, 2014. 34 Source: Navy information paper dated March 13, 2014, and provided to CRS by the Navy Office of Legislative Affairs on April 17, 2014. Congressional Research Service 59 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress years or so) as a question to be decided next year, depending on indications of congressional support for a certain DOD budget level in coming years, consistent with 10 U.S.C. 5062(b)? Does DOD’s proposal in effect treat the 11-carrier requirement in 10 U.S.C. 5062(b) as an optional matter rather than a mandate? If so, would this create a precedent for the executive branch to treat similar provisions in the U.S. Code as optional matters rather than mandates? For example, would it create a precedent for DOD, if it so desired, to begin treating as an optional matter the long-standing requirement in 10 U.S.C. 5063(a) that the Marine Corps “shall be so organized as to include not less than three combat divisions and three air wings, and such other land combat, aviation, and other services as may be organic therein?” If the executive branch were to begin treating statutory provisions like 10 U.S.C. 5062(b) as optional matters rather than mandates, what implications might this have for policy and program execution, and for Congress’s power to legislatively establish policy and program goals? • What would be the operational impact for the Navy of reducing the carrier force to 10 ships for the next 25 years or so (and also eliminating its associated carrier air wing)? What impact would it have on the Navy’s ability to fulfill its missions? • If the FDYP were reformulated to include the $7 billion in additional funding needed to keep CVN-73 and its associated air wing, what other defense programs would have their funding reduced, and what would be the impact of these reductions on DOD’s ability to fulfill its missions? • What would be the impact on HII/NNS and the other parts of the aircraft carrier industrial base if CVN-73 were inactivated rather than given an RCOH? What impact, if any, would this have on the cost of other work performed at NNS during these years, and on the eventual cost of the CVN-74 RCOH?35 A July 7, 2014, press report states: The Navy will move forward with the refueling of the aircraft carrier George Washington, reversing a previous plan to decide next year whether to retire the vessel. “We are moving forward to begin the [refueling and complex overhaul] process,” a Navy official told Inside the Navy July 1. “We have had several senators express interest in the carrier and therefore we are able to move forward.”36 A July 11, 2014, press report states: The U.S. Navy’s chief shipbuilder told Congress the service plans to reshuffle $7 billion in funds to refuel and maintain the nuclear aircraft carrier USS George Washington (CVN-73). 35 For press reports discussing the industrial-base aspects of the issue, see Lara Seligman, “Shipbuilder: Navy’s Timeline For CVN-73 ‘Not In Accordance With Our Plan,’” Inside the Navy, March 24, 2014; Olga Belogolova, “PEO Carriers: A Cut From 11 To 10 Carriers Would Impact Industrial Base,” Inside the Navy, February 24, 2014; Michael Fabey, “Foregoing Carrier RCOH Won’t Disrupt Future Work, HII CEO Says,” Aerospace Daily & Defense Report, March 25, 2014: 4; Rick Giannini and Darrell Grow, “Why Aircraft Carrier Workers Deserve a Better Plan from the Pentagon,” Defense One (www.defenseone.com), March 23, 2014. 36 Lara Seligman, “Navy Reverses Course, Plans To Begin GW Carrier Refueling Process,” Inside the Navy, July 7, 2014. Congressional Research Service 60 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress The fate of the carrier was an open question at the start of the year due to ongoing military funding pressures. “We are today making every effort to replan near $7 billion required across the [Future Years Defense Plan] to refuel the carrier plus maintain its airwing, manpower and support,” Sean Stackley, Assistant Secretary of the Navy for Research, Development & Acquisition (RDA), told the House Armed Services Subcommittee on Seapower and Projection Forces in a Thursday [July 10] hearing. “We’ve released the balance of advance procurement funding for 2014 to continue planning efforts in order to best maintain our options and retain skilled labor at the shipyard while we await determination by Congress regarding sequestration in 2016. Yet, this also increases the pressure on other programs.”... Stackley said since Hagel’s February announcement there were enough positive signs from Congress to allow the Navy to go ahead with the RCOH plan as part of its FY 2016 budget— currently being prepared by the service. “The signal today is strong enough that says we need to go ahead and proceed to the next step of releasing funding and go into the negotiations with the ship yard to start the planning effort per the refueling portion of a complex overhaul,” Stackley told USNI News following the Thursday hearing. “We’re in the middle of the 2016 budget bill today and we’re in the process of building a budget that anticipates Congress’ action that will support a change to BCA and sequestration. We’re moving out in anticipation of a future congressional action because we can’t wait until a year from now to build that budget.[”]... Representatives from Huntington Ingalls Industries, the company the contractor for the four year RCOH, was cautiously optimistic following Stackley’s comments. “While we are pleased to see positive momentum toward funding the RCOH, however this is a complex process that we will continue to monitor,” according to a HII statement provided to USNI News.37 An August 11, 2014, press report states: The [Navy] has released the balance of fiscal year 2014 funds appropriated for the advanced planning contract, and expects to execute the full refueling and complex overhaul (RCOH) for the ship in March 2017, Navy spokesman Dale Eng wrote in a statement emailed to Inside the Navy on Aug. 4. “The Department of the Navy has released the balance of FY-14 funds appropriated for the advanced planning contract for USS George Washington (CVN-73) and awarded the contract for this effort. Pending authorization and appropriation of future year funding, we expect to execute the George Washington [RCOH] in March 2017,” Eng wrote.38 37 Sam LaGrone, “Stackley: Navy Plans to Refuel Carrier George Washington,” USNI News (http://news.usni.org), July 10 (updated July 11), 2014. See also Christopher P. Cavas, “A Reprieve for GW?” Defense News (www.defensenews.com), June 30, 2014. 38 Lara Seligman, “Navy Awards HII $49.6 Million Contract To Begin Work On Carrier Defueling,” Inside the Navy, August 11, 2014. Congressional Research Service 6145 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 46 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 47 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Congressional Research Service 48 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress Author Contact Information Ronald O'Rourke Specialist in Naval Affairs rorourke@crs.loc.gov, 7-7610 Congressional Research Service 6249