U.S. Crude Oil and Natural Gas Production in
Federal and Non-Federal Areas
Marc Humphries
Specialist in Energy Policy
April 10, 20143, 2015
Congressional Research Service
7-5700
www.crs.gov
R42432
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
Summary
In 2013, the price of oil averaged $98 per barrel (West Texas Intermediate spot price), up from
$94 per barrel in 2012. Prices remain high in early 2014 (near $100 per barrel) and are projected
by the Energy Information Administration (EIA) to average in the mid-$90 per barrel range
through 2014. A number of proposals designed to increase domestic energy supply, enhance
security, and/or
amend the requirements of environmental statutes are before that apply to energy development were before
the 113th Congress.
and are likely to be reintroduced in the 114th Congress. A key question in this
discussion is how much oil and gas is produced in the United States each
year and how much of
that comes from federal versus non-federal areas. Oil production has
fluctuated on federal lands
over the past five fiscal years but has increased dramatically on nonfederalnon-federal lands. Non-federal
crude oil production has been rapidly increasing in the past few years
, partly due to favorable
geology and the relative ease of leasing from private parties, rising by 2.1
3.0 million barrels per day (mbd) between FY2009-FY2013FY2010 and
FY2014, causing the federal share of total U.S.
crude oil production to fall by nearly 11%.
Natural gas prices, on the other hand, have remained low for the past several years, allowing gas
to become much more competitive with coal for power generation. The shale gas boom has
crude oil production to fall from 36.4% to 21.4%.
Crude oil production on federal lands, particularly offshore, however, is likely to continue to
make a significant contribution to the U.S energy supply picture and could remain consistently
higher than previous decades, but still fall as a percent of total U.S. production, if production on
non-federal lands continues to rise at a faster rate.
The shale gas boom has resulted in rising supplies of natural gas. Overall, annual U.S. natural gas
production rose by
about four4.7 trillion cubic feet (tcf) (or 21%)or 19% since FY2009FY2010, while production on
federal lands
(onshore and offshore) fell by about 28%. 1.6 tcf, (or 31%) over the same time period.
Natural gas production on non-federal lands grew by
33 37% over the same time period. The big
shale gas plays arehave been primarily on non-federal lands and
are attracting have attracted a significant portion of investment for natural gas development.
The number of producing acres may or may not be a function of how many acres are leased, and
the number of acres leased may or may not correlate to the amount of production, but in recent
years, some members of Congress have proposed a $4/acre lease fee for non-producing leases.
This proposal grew out of the efforts to open more public land and water (offshore) for oil and
gas drilling and development when gasoline prices spiked in 2006-2008. Some in Congress noted
that there were many leases they believed were not being developed in a timely fashion, while at
the same time, others in Congress were pushing for greater access to areas off-limits (such as the
Arctic National Wildlife Refuge (ANWR) and areas under leasing moratoria offshore). Higher
rents for offshore leases were imposed by the Secretary of the Interior in 2009 to discourage
holding unused leases and to move more leases into production, if possible.
Another major issue that Congress may seek to address is streamlining the processing of
applications for permits to drill (APDs). Some members contend that this would be one way to
help boost energy production on federal lands. After a lease has been obtained, either
competitively or non-competitively, an APD must be approved for each oil and gas well. Despite
the new timeline for review (under the Energy Policy Act of 2005, P.L. 109-58), it took an
average of 307 days for all parties to process (approve or deny) an APD in 2011, up from an
average of 218 days in 2006. The difference, however, is that in 2006 it took the Bureau of Land
Management (BLM) an average of 127 days to process an APD, while in 2011 it took BLM 71
days. In 2006, the industry took an average of 91 days to complete an APD, but in 2011, industry
took 236 days. The BLM stated in its FY2012 and FY2013 budget justifications that overall
processing times per APD have increased because of the complexity of the process
of investment for natural gas development.
There is however, continued interest among some in Congress to open more federal lands for oil
and gas development (e.g., the Arctic National Wildlife Refuge (ANWR) and areas offshore) and
increase the speed of the permitting process. But having more lands accessible may not translate
into higher levels of production on federal lands, as industry seeks out the most promising
prospects and higher returns on more accessible non-federal lands.
Another major issue that Congress may address is streamlining the processing of applications for
permits to drill (APDs). Some Members contend that this would be one way to help boost energy
production on federal lands. After a lease has been obtained, either competitively or
noncompetitively, an application for a permit to drill must be approved for each oil and gas well.
It took an average of 307 days for all parties to process (approve or deny) an APD in FY2011, but
that has declined to an average of 227 days in FY2014 (up from 194 days in FY2013). The
Bureau of Land Management (BLM) stated in its annual budget justifications (FY2012 and
FY2016), that overall processing times per APD rose to such high levels in FY2011 and other
years because of the complexity of the process, but they expect shorter timeframes in the future.
The Energy Policy Act of 2005 (EPACT ’05) included a provision to initiate and fund (funding
authorized through FY2015) a pilot program at seven Bureau of Land Management (BLM) field
offices in an effort to streamline the permitting process for oil and gas leases on federal lands.
There were legislative proposals in the 113th Congress that would have established the
streamlining pilot program as a permanent program. This topic may be revisited in the 114th
Congress.
Congressional Research Service
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
Contents
Introduction...................................................................................................................................... 1
U.S. Crude Oil Production: Federal and Non-Federal Areas (Fiscal Year) ..................................... 1
U.S. Natural Gas Production: Federal and Non-Federal Areas (Fiscal Year) .................................. 3
EIA Projections.......................................................................................................................... 54
Oil and Natural Gas Lease Data for Federal Lands ................................................................... 5
Producing Acres......................................................................................................................... 6
Applications for Permits to Drill (APDs) .................................................................................. 7
Streamline Pilot ................................................................................................................... 9
Concerns over Non-Producing Leases ...................................................................................... 9
Figures
Figure 1. U.S. Crude Oil Production: Federal and Non-Federal Areas, FY2009-2013FY2010-2014 ................... 3
Figure 2. U.S. Natural Gas Production: Federal and Non-Federal Areas FY2009-FY2013FY2010-FY2014 ........... 4
Tables
Table 1. U.S. Crude Oil Production: Federal and Non-Federal Areas FY2009-FY2013FY2010-FY2014................. 2
Table 2. U.S. Natural Gas Production: Federal and Non-Federal Areas FY2009-FY2013FY2010-FY2014 ............ 4
Table 3. EIA Oil Production Projections.......................................................................................... 5
Table 4. EIA Natural Gas Production Projections ........................................................................... 5
Table 5. Oil and Gas Lease Data for Federal Lands, 20122014 .............................................................. 6
Table 6. Onshore Oil and Gas Drilling Permits (FY2006-FY2011FY2014) .................................................................... 8
Contacts
Author Contact Information........................................................................................................... 10
Congressional Research Service
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
Introduction1
In 20132014, the price of oil averaged $9892 per barrel (West Texas Intermediate spotaverage composite price), updown from
$94 $98 per
barrel in 20122013. Prices remain high in early 2014 (near $100 per barrel) and are projected
by the Energy Information Administration (EIA) to average in the mid-$90 per barrel range
through 2014. dropped dramatically in December 2014, and by January 2015 crude oil
prices were under $50 per barrel. The Energy Information Administration (EIA) projects crude oil
prices to average in the lower to upper $50 per barrel range through 2015. This lower price, if
sustained, may impact long term oil development and lower production volumes.
A number of proposals designed to increase domestic energy supply, enhance
security, and/or
amend the requirements of environmental statutes are before that apply to energy development were before
the 113th Congress.
and are likely to be reintroduced in the 114th Congress. A key question in this
discussion is how much oil and gas is produced in the United States each
year and how much of
that comes from federal versus non-federal areas. Oil production has
fluctuated on federal lands
over the past five fiscal years but has increased dramatically on nonfederalnon-federal lands. Non-federal
crude oil production has been rapidly increasing in the past few years,
partly due to favorable
geology and the ease of leasing, rising by 2.13.0 million barrels per day
(mbd) between FY2009 and FY2013FY2010 and
FY2014, causing the federal share of total U.S. crude oil production
to fall by nearly 11from 36.4% to 21.4%.
Natural gas prices, on the other hand, have remained low for the past several years, allowing gas
to become much more competitive with coal for power generation. The shale gas boom has
resulted in rising supplies of natural gas. Overall, annual U.S. natural gas production rose by
about four4.7 trillion cubic feet (tcf) (or 21%)or 19% since FY2009FY2010, while production on federal lands
(onshore and offshore) fell by about 28%. Natural gas 1.6 tcf (or 31%) over the same time period. Natural gas
production on non-federal lands grew by
33 37% over the same time period (see Table 2). The big
shale gas plays arehave been primarily on nonfederalnon-federal lands and are attractinghave attracted a significant portion
of investment for natural gas development.
This report examines U.S. oil and natural gas production data for federal and non-federal areas
with an emphasis on the past five fiscal years of production.2
U.S. Crude Oil Production: Federal and Non-Federal
Areas (Fiscal Year)
Historically, according to Department of the Interior (DOI) data, crude oil production on federal
lands was consistently under 20% of total U.S. production until the late 1990s. Annual production
then surged on federal lands (primarily offshore), rising to over 30% in the early 2000s and
reaching a high point of about 36% in FY2010.3 As a result of recent production increases on
non-federal lands, the question is raised whether non-federal lands might regain a more dominant
position of roughly 80%-85% of total U.S. crude oil production. The fact remains, however, that
there are 5.3 billion barrels of proved oil reserves located on federal acreage onshore and another
5.6 billion barrels of proved reserves offshore (nearly all in the Gulf of Mexico). Taken together,
1
For a broader analysis of offshore oil and gas leasing and resources, see CRS Report R40645, U.S. Offshore Oil and
Gas Resources: Prospects and Processes, by Marc Humphries and Robert Pirog.
2
For more information on U.S. oil development, see CRS Report R43148, An Overview of Unconventional Oil and
Natural Gas: Resources and Federal Actions, by Michael Ratner and Mary Tiemann; CRS Report R41132, Outer
Continental Shelf Moratoria on Oil and Gas Development, by Curry L. Hagerty;, and CRS Report R43429, Federal
Federal Lands and Natural Resources: Overview and Selected Issues for the 113th114th Congress, coordinated by Katie
Hoover.
3
The early data (1980 and 1990s) were taken from annual Mineral Revenue reports. The data used at that time were
accounting data which are considered by the Office of Natural Resources Revenue as not very reliable. The more useful
production volume data provided by ONRR now are based on fiscal year sales data.
Congressional Research Service
1
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
non-federal lands, the question is raised whether non-federal lands might regain a more dominant
position of roughly 80%-85% of total U.S. crude oil production. The fact remains, however, that
there are an estimated 5.3 billion barrels of proved oil reserves located on federal acreage onshore
and another 4.3 billion barrels of proved reserves offshore (nearly all in the Gulf of Mexico).
Taken together, U.S. federal oil reserves equal about 26U.S. federal oil reserves equal about 43% of all U.S. crude oil reserves, which are
estimated at 29
36.5 billion barrels, according to the EIA.4 Proved oil reserves are amounts
accessible under current
policy, prices, and technology. Higher prices often translate into higher
reserve estimates.
Crude oil production on federal lands, particularly offshore, is likely to continue to make a
significant contribution to the U.S energy supply picture and could remain consistently higher
than previous decades, but it could still fall as a percent of total U.S. production, if production on
non-federal lands continues to rise at a faster rate.
There is, however, continued interest among some in Congress to open more federal lands for oil
and gas development (e.g., the Arctic National Wildlife Refuge (ANWR) and areas offshore) and
increase the speed of the permitting process. But having more lands accessible may not translate
into higher levels of production on federal lands, as industry seeks out the most promising
prospects and higher returns on more accessible non-federal lands.
Table 1. U.S. Crude Oil Production: Federal and Non-Federal Areas FY2009-FY2013FY2010-FY2014
(Barrels per day)
Fiscal Year
U.S. Total
Non-Federal
Total Federal
(% of U.S. Total)
Federal
Offshore
Federal
Onshore
5,576,700
1,658,300
(23)
1,294,000
364,465
6,241,000
4,598,000
1,643,000
(26.3)
1,303,300
339,700
2011
5,552,000
3,826,500
1,725,500
(31)
1,415,600
309,900
2010
5,438,800
3,463,700
1,975,100
(36.3)
1,680,300
294,800
2009
5,233,000
3,464,400
1,768,600
(33.8)
1,482,900
285,700
Fiscal Year
U.S. Total
Non-Federal
2013
7,235,000
2012
2014
8,324,000
6,545,000
1,779,000 (21.4)
1,372,400
406,200
2013
7,261,200
5,583,300
1,677,900
(23)
1,303,300
374,600
2012
6,249,000
4,603,500
1,645,500 (26.3)
1,302,800
342,700
2011
5,550,200
3,775,700
1,774,400
(32)
1,454,300
320,100
2010
5,446,500
3,466,300
1,980,200 (36.4)
1,685,200
295,000
Source: Federal data obtained from the Office of Natural Resources Revenue (ONRR) Statistics, as of February
2014January 5,
2015, http://www.onrr.gov (using sales year data), March 20142015.
Notes: U.S. Fiscal Year Total data derived from EIA monthly production data contained in its publication
Petroleum and Other Liquids, U.S. Field Production of U.S. Crude Oil, March 28, 201430, 2015, http://www.eia.gov. Data
includes lease condensate, defined by EIA as a liquid hydrocarbon recovered from lease separators or field
facilities at associated and non-associated natural gas wells.
4
EIA, U.S. Crude Oil and Natural Gas Proved Reserves, 2011, August 20132013, December 2014, http://www.eia.gov.
Congressional Research Service
2
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
Figure 1. U.S. Crude Oil Production:
Federal and Non-Federal Areas, FY2009-2013FY2010-2014
Million barrels per day (Mb/d)
Million barrels per day
8
US Total
6
Non-Federal
4
2
Federal Offshore
Federal Onshore
0
2009
2010
2011
2012
2013
Source: Federal data obtained from ONRR Statistics, http://www.onrr.gov (using sales year data). Non-federal
from EIA. Figure created
by CRS.
U.S. Natural Gas Production: Federal and NonFederal
Non-Federal Areas (Fiscal Year)
Natural gas production in the United States overall has dramatically increased each year since
20092010, while production on federal lands has declined each year over the same period. Much of the
decline can be attributed to offshore production falling by about 50%. Onshore production
declines were less dramatic. Federal natural gas production has fluctuated from around 30% of
total total
U.S. production for much of the 1980s through the early 2000s (34% of U.S. total in 2003),
after after
which there began a steady decline through 20132014.5 This picture of natural gas production is
much much
different than that of federal crude oil in that federal natural gas had accounted for a much
larger larger
portion of total U.S. natural gas over that past few decades.
Any increase in production of natural gas on federal lands is likely to be easily outpaced by
increases on non-federal lands, particularly because shale plays are primarily situated on nonfederal lands and are where most of the growth in production is projected to occur.
U.S. dry gas proved reserves are estimated at about 334354 tcf by the EIA,6 of which the federal
share is about 2524% (69 tcf onshore, 16 tcf offshore). Nearly all of the offshore proved reserves are
located in the Central and Western Gulf of Mexico.
5
U.S. natural gas production on federal lands fell from about 7 trillion cubic feet in FY2003 to about 43.5 trillion cubic
feet in FY2013FY2014.
6
EIA, U.S. Crude Oil and Natural Gas Proved Reserves, 2011, August 20132013, December 2014, http://www.eia.gov. Dry gas is marketed
(continued...)
marketed production less extraction losses.
Congressional Research Service
3
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
Table 2. U.S. Natural Gas Production:
Federal and Non-Federal Areas FY2009-FY2013FY2010-FY2014
(billion cubic feet)
U.S. Total
Non-FederalFiscal Year
Total Federal
(% of U.S. Total)
Federal
Offshore
Federal
Onshore
2013
25,470
21,592
3,878 (15.2)
1,172
2,706
2012
25,208
20,938
4270 (16.9)
1,351
2,919
2011
23,539
18,953
4,586 (19.5)
1,668
2,918
2010
21,924
16,849
5,076 (23.2)
2,056
3,020
2009
21,612
16,241
5,372 (24.9)
2,205
3,167
Fiscal Year(13)
1,060
2,461
(15)
1,189
2,629
20,944
4,246 (16.9)
1,365
2,881
23,510
18,934
4,576 (19.5)
1,682
2,894
21,924
16,850
5,074
2,070
3,004
U.S. Total
Non-Federal
2014
26,679
23,158
3,521
2013
25,551
21,733
3,818
2012
25,190
2011
2010
(23)
Source: Federal data obtained from ONRR Statistics, http://www.onrr.gov (using sales year data as of January 5,
2015), March 2015), March 2014.
Notes: U.S. Fiscal Year Total data derived from EIA monthly production data in its publication “Natural Gas,
U.S. Natural Gas Marketed Production,” March 31, 201430, 2015, http://www.eia.gov.
Figure 2. U.S. Natural Gas Production:
Federal and Non-Federal Areas FY2009-FY2013
Billion cubic feet
30,000
US Total
25,000
Non-Federal
20,000
15,000
10,000
5,000
Federal Onshore
Federal Offshore
0
2009
2010
2011
2012
2013
Source: Federal data obtained from ONRR Statistics, http://www.onrr.gov (using sales year data). Figure created
by CRS.
(...continued)
production less extraction losses.
Congressional Research Service
4
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal AreasFY2010-FY2014
Source: Federal data obtained from ONRR Statistics, http://www.onrr.gov (using sales year data). Figure created
by CRS.
EIA Projections
While in the short-term, EIA estimates show oil production continuing to decline in federal
offshore areas, EIA’s longer-term estimates show a slight increase in federal offshore oil
production overall, from its nearly 1.41.1 mbd in 2013FY2014 to 1.6-2.0 mbd in 2040.7 Overall, the EIA projects U.S.
oil production to rise from 7.4 mbd in 2013 to about 7.5 mbd by 2040 (essentially equal to 2013
production levels) after reaching 9.0 mbd in 2025.8 According to these estimates, offshore
production in 2040 could range from 21% to 27% of total U.S. crude oil production. (See Table
7
EIA, Annual Energy Outlook 2014, December 2013. The release of the Annual Energy Outlook, 2015 is due later in
(continued...)
Congressional Research Service
4
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
projects in the short term, oil production reaching 9.5 mbd in 2016,8 but long-term estimates show
U.S. oil production falling to about 7.5 mbd by 2040 (essentially equal to 2013 production levels)
and at 9.0 mbd in 2025.9 According to these estimates, offshore production in 2040 could range
from 21% to 27% of total U.S. crude oil production. (See Table 3.)
Offshore natural gas production is projected to reverse a years-long decline in 2015, with annual
production rising as high as 2.9 tcf in 2040. Even though these projections are in calendar years,
2.9 tcf of natural gas is still likely more than a doubling ofnearly triple the current offshore production (provided
in fiscal years in
the earlier sections of this report) but would only account for about a 7.7% share
of total U.S.
production in 2040. (See Table 4.)
Table 3. EIA Oil Production Projections
(million barrels per day)
Year
U.S. Offshore
U.S. Total
2025
n/a1.6-2.0
9.0
2040
1.6-2.0
> 7.57.48
Source: EIA, Early Release Overview, 2014, Annual Energy Outlook, December 2013.
Table 4. EIA Natural Gas Production Projections
(trillion cubic feet per year)
Year
U.S. Offshore
U.S. Total
2025
n/a1.7-2.9
31.93
2040
1.7-2.9
37.61
Source: EIA, Early Release Overview, 2014 Annual Energy Outlook, December 2013.
Oil and Natural Gas Lease Data for Federal Lands9
CurrentlyLands
Based on the federal government’s inter-agency’s Phase III report, there are 113 million acres of
onshore federal lands open and accessible for oil and gas
development and about 166 million
acres off-limits or inaccessible.10 The Bureau of Land
7
EIA, Early Release Overview, 2014, Annual Energy Outlook, December 2013.
Ibid.
9
2013 data from BLM was not available at the time of this writing Management (BLM) is seeking to lease in
(...continued)
April 2015.
8
EIA, Short Term Energy Outlook, http://www.eia.gov/forecasts/steo, March 10, 2015.
9
Ibid.
10
U.S. Depts. of the Interior, Agriculture, and Energy, Inventory of Onshore Federal Oil and Natural Gas Resources
and Restrictions to Their Development (Phase III), May 2008, available on the BLM website at http://www.blm.gov/
wo/st/en/prog/energy/oil_and_gas/EPCA_III.html.
The availability of public lands for oil and gas leasing can be divided into three categories: lands open under standard
lease terms, open to leasing with restrictions, and closed to leasing. Areas are closed to leasing pursuant to land
withdrawals or other mechanisms. Much of this withdrawn land consists of wilderness areas, national parks and
monuments, and other unique and environmentally sensitive areas that are unlikely to ever be reopened to oil and gas
leasing. Some lands are closed to leasing pending land use planning or NEPA compliance, while other areas are closed
because of federal land management decisions on endangered species habitat or historical sites. Some of those
(continued...)(continued...)
8
Congressional Research Service
5
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
Management (BLM) is seeking to lease in areas where it anticipates fewer legal challenges; BLM
. The BLM also says it is addressing public
concerns prior to a lease sale at a higher rate than in the past. In
2012, 56% of the onshore acreage under federal lease and 45% of federal onshore leases were not
2014, 49% of onshore federal
leases and 37% of onshore federal acreage were not in production. Offshore, most of the 1.7
billion acres of federal water are no longer under leasing
and development moratoria. The current
five-year leasing program has lease sales scheduled in
Western and Central Gulf of Mexico
(GOM) and parts of Alaska.11 In the offshore areas, 7285% of
the acreage that is leased is not in
production, but may have an approved exploration or development planis leased and 75% of the leases are not in production.
According to the BLM and the Bureau of Ocean Energy Management (BOEM), there are
approximately 72.867 million acres of oil and gas leases in federal areas (onshore and offshore).
About 37.034.6 million acres are located onshore and an additional 35.832 million acres are offshore.
Approximately 11.112.7 million federal acres onshore and about 6.64.8 million federal acres offshore are
producing commercial volumes. (See Table 5.)
Table 5. Oil and Gas Lease Data for Federal Lands, 20122014
Onshore
Offshore
Acreage under lease
37.0 million acres
35.8 million acres
Acreage with approved exploration or development plan
(i.e., acreage in production or exploration)
16.334.6 million acres
10.132 million acres
Leased acres producing
11.112.7 million acres
6.64.8 million acres
Leased acres not in production or exploration
20.821.9 million acres
25.727.3 million acres
Number of Leases
49,213
6,62146,193
5,938
Producing Leases (or with approved DOCD)a
27,300
1,611
Source: DOI, Oil and Gas Utilization—Onshore and Offshore, Report to the President, May 2012.23,657
970
Percentage of producing leases
51
16
Source: Offshore data: DOI/BOEM, Combined Leasing Status Report, March 2015 (www.boem.gov). Onshore
data: DOI/BLM, Oil and Gas Statistics (www.blm.gov/wo/st/en)
a.
A DOCD is a Development Operations Coordination Document that must be submitted for approval to
BOEM before development activities begin.
Producing Acres
The number of federal producing acres may or may not be a function of how many acres are
leased, and the number of acres leased may or may not correlate to production levels, but it is
beyond the scope of this report to examine that issue thoroughly. In recent years, some members
of Congress have proposed a $4/acre lease fee for non-producing leases. This proposal grew out
of the efforts to open more public land and water (offshore) for oil and gas drilling and
development when gasoline prices spiked in 2006-2008. Some in Congress noted that there were
many leases they believed were not being developed in a timely manner, while at the same time,
others in Congress were advocating greater access to areas off-limits (such as ANWR and areas
(...continued)
withdrawals or other mechanisms. Much of this withdrawn land consists of wilderness areas, national parks and
monuments, and other unique and environmentally sensitive areas that are unlikely to ever be reopened to oil and gas
leasing. Some lands are closed to leasing pending land use planning or NEPA compliance, while other areas are closed
because of federal land management decisions on endangered species habitat or historical sites. Some of thoseunder leasing moratoria offshore). Higher rents for offshore leases were imposed by the Secretary
of the Interior in 2009 to discourage holding unused leases and to move more leases into
(...continued)
restricted areas may be opened by future administrative decisions.
11
TheNearly all of the Eastern GOM is under a leasing moratoriamoratorium until 2022 under the Gulf of Mexico Energy Security
Act, and the
North Aleutian Basin of Alaska was withdrawn from leasing under an executive order by the current Administration.
Congressional Research Service
6
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
under leasing moratoria offshore). Higher rents for offshore leases were imposed by the Secretary
of the Interior in 2009 to discourage holding unused leases and to move more leases into
Obama
Administration. Separately, President Obama withdrew selected parts of the Chukchi and Beaufort Seas of Alaska
indefinitely in January 2015.
Congressional Research Service
6
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
production, if possible. The escalation in annual rents is significant over time, as they rise from
$7/acre
to $28/acre (in year-8 forward) in water depths less than 200 meters, and increase from
$11/acre
to $44/acre (in year-8 forward) in water depths between 200 and 400 meters. However,
there was
no similar escalation for onshore leases, as they remain $1.50/acre for years 1-5, then
rise to
$2/acre thereafter.12 $2/acre thereafter.12 Legislative options to increase the rents and royalties on federal oil
and gas leases have been debated in Congress. A non-producing fee or an escalation of rents may
not increase production but
may reduce may increase the ratio of producing leases to active leases. Thus,
there might be fewer “idle” leases
and acreage not in production or exploration. The BLM can re-leaserelease acreage that has been
relinquished or passed over at a future lease sale.
Applications for Permits to Drill (APDs)
Another major issue that Congress may address is streamlining the processing of applications for
permits to drill (APDs). Some membersMembers contend that this would be one way to help boost energy
production on federal lands. After a lease has been obtained, either competitively or
noncompetitively, an application for a permit to drill must be approved for each oil and gas well.
As noted in the Mineral Leasing Act, Section 226 (g), “no permit to drill on an oil and gas lease
issued under this chapter may be granted without the analysis and approval by the Secretary
concerned of a plan of operations covering proposed surface-disturbing activities within the lease
area.” The application form (APD form 3160-3) must include, among other things, a drilling plan,
a surface use plan, and evidence of bond/surety coverage. The surface use plan should contain
information on drillpad location, pad construction, the method for containment and waste
disposal, and plans for surface reclamation.13
Prior to the Energy Policy Act of 2005 (P.L. 109-58, EPACT ’05), a major concern that prompted
the streamlining of permits debate was the lengthy timetable to process an APD. The BLM
attributed the longer timelines to the rewriting of outdated Resource Management Plans (RMPs).
There were several RMPs revised over the past decade. Leading up to the provisions in EPACT
’05 that attempted to streamline the permitting process, the BLM announced, in April 2003, new
strategies to expedite the APD process. The new strategies included processing and conducting
environmental analyses on multiple permit applications with similar characteristics, implementing
geographic area development planning for an oil or gas field or an area within a field, establishing
a standard operating practice agreement that identifies surface and drilling practices by oil and
gas operators, allowing for a block survey of cultural resources, promoting consistent procedures,
and revising relevant BLM manuals.14 EPACT ’05 Section 366 (Deadline for Consideration of
Application for Permits) provided a new timeline for BLM to process APDs.15
12
DOI, Oil and Gas Lease Utilization, Onshore and Offshore, Updated Report to the President, May 2012, p.18.
U.S. Department of the Interior, Bureau of Land Management (BLM), Surface Operating Standards and Guidelines
for Oil and Gas Exploration and Development, The Gold Book, Fourth Edition-Revised 2007, p. 8.
14
DOI/BLM Instruction Memorandum No. 2003-152, Application for Permit to Drill Process Improvement#1Comprehensive Strategies, April 14, 2003.
15
Within 10 days of receiving the application from the operator, BLM shall notify the operator as to whether the
application is complete and also schedule a site visit. If the application is not complete, the operator then has 45 days to
submit additional information to BLM to complete the application or the application is returned to the operator. Within
30 days of receiving a completed application the BLM will approve or defer the application. If deferred, the operator
has up to two years to take specified actions to complete the application or face the possibility of being denied a permit.
13
Congressional Research Service
7
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
While the current Administration processed more APDs than it received from 2009-20112013, it
received far fewer applications over that period than the previous Administration had received
had been received annually from 2006-2008.
Even though the number of pending applications has fallen steadily sincefrom 2008,
-2013, the ratio of
APDs pending to APDs processed was higher than during the period 2006-2008. In
addition,
there are 76,000 approved APDs that are not in the exploration or production stages
(approved but
not drilled).16 The BLM expected to process more thanover 5,000 APDs in each of the
fiscal years 2012 and 20132015 and
2016.
Table 6. Onshore Oil and Gas Drilling Permits (FY2006-FY2011FY2014)
Fiscal Year
New APDs Received
Total APDs Processed
APDs Pending at YearEnd
2014
5,316
4,924
4,121
2013
4,757
4,892
3,546
2012
5,240
5,861
3,683
2011
4,728
2011
4,278
5,200
4,309108
2010
4,251
5,237
4,603
2009
5,257
5,306
5,589
2008
7,884
7,846
5,638
2007
8,370
8,964
5,600
2006
10,492
8,854
6,194
Source: U.S. Department of the Interior, Oil and Gas DOI/ BLM, FY2016 Budget Justification for years FY2011-FY2016. For earlier years, see DOI, Oil and Gas
Utilization, Onshore and Offshore, May 2012.
It took an average of 307 days for all parties to process (approve or deny) an APD in 2011FY2011, but
that has declined to an average of 227 days in FY2014 (up from 194 days in 2013.17 In 2006FY2013).17 In
FY2006, it took the BLM an average of 127
days to process an APD, while in 2013FY2014 it took BLM 95 days. In 2006
BLM 133 days (up from 95 days in FY2013). In FY2006, the industry took an
average of 91 days
to complete an APD, but in 20132014, the industry took 99 days. The BLM stated
in its FY2012 and FY2013 budget justifications that overall processing times per APD rose to
such high levels in 2011 because of the complexity of the process; now the permit process is
improving, resulting in shorter timeframes133 days (up from 99 days in FY2013). The
BLM stated in its annual budget justifications for FY2012 and FY2016 that overall processing
times per APD rose to such high levels in FY2011 and other years because of the complexity of
the process, but they expect shorter timeframes in the future.
Some critics of this lengthy timeframe highlight the relatively speedy process for permit
processing on private lands. However, crude oil and gas development on federal lands takes place
in a
wholly different regulatory framework than that of oil development on private lands.18 State
agencies permit drilling activity on private lands within their states, with some approving permits
within 10 business days of submission. This faster approval rate does not necessarily diminish the
additional work required by the state to address other state requirements. But often, some surface
management issues are negotiated between the oil producer and the individual land/mineral
owner. A private versus federal permitting regime does not lend itself to an “apples-to-apples”
comparison.
development on private lands.18 State
16
U.S Department of the Interior, Oil and Gas Lease Utilization, Onshore and Offshore, Updated Report to the
President, May 2012, p. 14.
17
Bureau of Land Management, “Average Application for Permit to Drill (APD) Approval Timeframes: FY2005FY2012FY2005FY2014,” http://www.blm.gov/wo/st/en/prog/energy/oil_and_gas/statistics/apd_chart.html.
18
Under the Federal Land Policy and Management Act (FLPMA), Resource Management Plans or Land Use Plans (43
U.S.C. 1712) are required for tracts or areas of public lands prior to development. The Bureau of Land Management
(BLM) must consider environmental impacts during land-use planning when RMPs are developed and implemented.
RMPs can cover large areas, often hundreds of thousands of acres across multiple counties. Through the land-use
planning process, the BLM determines which lands with oil and gas potential will be made available for leasing.
Congressional Research Service
8
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
agencies permit drilling activity on private lands within their states, with some approving permits
within 10 business days of submission. This faster approval rate does not necessarily diminish the
additional work required by the state to address other state requirements. But often, some surface
management issues are negotiated between the producer and the individual land/mineral owner. A
private versus federal permitting regime does not lend itself to an “apples-to-apples” comparison.
Streamline Pilot
EPACT ’05 also included a provision to initiate and fund (funding authorized through FY2015) a
pilot program at seven BLM field offices in an effort to streamline the permitting process for oil
and gas leases on federal lands. ResultsInitial results from the pilot project were published according to the
the timetable required by EPACT ’05 (within three years after enactment). The conclusion was that
that the pilot made a difference in improving the processing times for APDs at the pilot offices overall
overall and increased the number of environmental inspections. The BLM noted that the National
Environmental Policy Act (NEPA) processing time for APDs and rights of way (ROW)
applications fell from 81 to 61 days or roughly 25% due to “colocation” of agency staff. BLM
reported that the number of environmental inspections went up by 78% from FY2006 to
FY2007.19 The BLM reported mixed results at the specific field offices. While some of the offices
processed more permits in 2007 than they did in 2005, all the pilot sites reported more completed
environmental inspections.20 There were legislative proposals in the 113th Congress that would
have established the streamlining pilot program as a permanent program. This topic may be
revisited in the 114th Congress.
Concerns over Non-Producing Leases
A number of concerns may arise in the oil and gas leasing process that could delay or prevent oil
and gas development from taking place, or might account for the relatively large number of leases
held in non-producing status. It should be noted that many leases expire without exploration or
production ever occurring.
Below is a list of often-cited issues which, individually or in combination, are usedcited by various
stakeholders to explain
why more leases are not producing.
•
Rig or equipment availability, particularly offshore;
•
Oil and natural gas prices;
•
High capital costs and available capital;
•
Skilled labor shortages;
•
Leases in the development cycle (e.g., conducting environmental reviews,
permitting, or exploring) but not producing;
•
Legal challenges that might delay or prevent development;
•
No commercial discovery on a lease tract;
19
Bureau of Land Management, BLM Year Two Report, Section 365 of EPACT 2005 Pilot Project to Improve Federal
Permit Coordination, February 2008.
20
Ibid.
Congressional Research Service
9
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
•
Holding leases (because of the lack of capital or as “speculators”) to sell or “farm
out” at a later date;
•
Ability to secure extensions on non-producing leases;
•
Securing and being able to hold large number of lease tracts, often contiguous, to
maximize return on their investment; and
•
The potential for inadequate coordination between the Department of the
Interior’s lease management and regulatory agencies (Bureau of Ocean Energy
Management and Bureau of Safety and Environmental Enforcement) and other
19
Bureau of Land Management, BLM Year Two Report, Section 365 of EPACT 2005 Pilot Project to Improve Federal
Permit Coordination, February 2008.
20
Ibid.
Congressional Research Service
9
U.S. Crude Oil and Natural Gas Production in Federal and Non-Federal Areas
federal agencies to ensure protection of federal areas encompassing coastal and
marine sanctuaries.
Author Contact Information
Marc Humphries
Specialist in Energy Policy
mhumphries@crs.loc.gov, 7-7264
Congressional Research Service
10