Mixed-Oxide Fuel Fabrication Plant and
Plutonium Disposition: Management and
Policy Issues
Mark Holt
Specialist in Energy Policy
Mary Beth D. Nikitin
Specialist in Nonproliferation
March 28, 2014
Congressional Research Service
7-5700
www.crs.gov
R43125
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
Summary
Policy Issues
March 2, 2015
(R43125)
Summary
The Mixed Oxide Fuel Fabrication Facility (MFFF) in South Carolina has been a key component
of the current U.S. strategy for disposing of surplus weapons plutonium from the Cold War. That
strategy called for the surplus plutonium, in oxide form, to be blended with uranium oxide to
make mixed oxide (MOX) fuel for U.S. commercial nuclear reactors. The plutonium in MOX
fuel would be mostly destroyed in the reactors by fission (splitting into other isotopes). At the
same time, isotopes of plutonium undesirable for weapons would be created, along with highly
radioactive fission products. As a result, after several years in a reactor, spent MOX fuel would
have less total plutonium than when it was freshly loaded, and the remaining plutonium would be
degraded for weapons purposes. Moreover, the fission products would make the material difficult
to handle, in case of future attempts to use the plutonium.
Because of sharply rising cost estimates for the MOX project, the Obama Administration
is
proposingproposed in its FY2015 budget request to place MFFF in
“"cold standby
”" and study other plutonium disposition options.
The
However, Congress authorized and appropriated $345 million for FY2015 to continue construction at a reduced level and required the Department of Energy (DOE) to procure an independent cost and schedule estimate for MFFF and alternative disposition approaches. Pending the results of those analyses, DOE requested $345 million for FY2016 to continue construction at the FY2015 level.
The federal plutonium disposition program is run by the National Nuclear Security Administration
(NNSA), a semiautonomous agency of
the Department of Energy (DOE)DOE. NNSA estimated in
2002 that MFFF would cost about $1 billion to design and build. DOE said in its budget
justification for FY2014 that the MFFF contractor had estimated the project
’'s total construction
cost would rise to $7.78 billion, and that construction would not be completed until November
2019. DOE
’'s FY2015 budget justification said the life-cycle cost estimate for the MOX program
had risen to $30 billion.
Disposition of surplus plutonium is required by a 1998 agreement, amended in 2010, between the
United States and Russia. Each country agreed to convert 34 metric tons of surplus
weaponsgradeweapons-grade plutonium to a form that could not be returned to nuclear weapons. The two countries
agreed to begin plutonium disposition in 2018.
TheAfter disposition begins, the United States is to pay a maximum of $400
million to support the Russian plutonium disposition effort. The Russian government is to fund
the remainder of Russia
’'s approximately $2.5 billion in estimated costs.
The United States and
Russia are now negotiating a verification agreement and a “Milestones” plan that would outline
how the U.S. contribution of $400 million to the Russian program would be spent.
Differing sharply from the U.S. MOX strategy, Russia is planning to use its BN-600 and BN-800
fast breeder reactors for plutonium disposition. According to the World Nuclear Association, the
BN-800
construction is expected to
“start up in
2014 and be operational in 2015,”2015, and the reactor
is
“"capable of burning 1.7 metric tons of plutonium per year from dismantled weapons.
”" The
DOE FY2015
budget includesand FY2016 budget requests included no funds for support of the Russian plutonium disposition
program. As in FY2014
and FY2015, NNSA plans to use prior-year funds to support these activities in
FY2015. The $400 million in U.S. assistance is to be paid to Russia after FY2018 when
plutonium disposition is to begin.
The Administration’s review of the FY2016.
The debate over U.S. plutonium disposition strategy raises several issues for
Congress. A fundamental question is whether the rising cost estimates for MFFF are sustainable
in the current budget environment. And if the MFFF is not sustainable, what should replace it?
However, any delay or major change to the program could affect the planned disposition of
Russian weapons plutonium. The effects of
budget cuts on DOE’alternative disposal options on DOE's Savannah River Site in South
Carolina, where MFFF is located, will also be an important element of the debate.
Congressional Research Service
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
Contents
Introduction...................................................................................................................................... 1
Russian Program .............................................................................................................................. 2
U.S. Program ................................................................................................................................... 4
Management and Cost ............................................................................................................... 5
MOX and Nonproliferation ............................................................................................................. 6
Issues for Congress .......................................................................................................................... 7
Tables
Table 1. Funding for the NNSA Russian Plutonium Disposition Program ...................................... 3
Table 2. Defense Nuclear Nonproliferation Appropriations FY2007-FY2015 .............................. 10
Contacts
Author Contact Information........................................................................................................... 11
Congressional Research Service
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
Introduction
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition: Management and Policy Issues
Introduction
With the end of the Cold War and breakup of the Soviet Union in the early 1990s, control of
surplus nuclear weapons material became an urgent U.S. foreign policy goal. Particular U.S.
concern focused on plutonium from Soviet nuclear warheads, which it was feared posed a major
nuclear weapons proliferation risk. The United States supported a successful effort to consolidate
the storage of Soviet nuclear weapons and materials in Russia, and then began negotiating
reductions in weapons material stockpiles.
Congress has been closely involved in formulating U.S. policy on surplus plutonium disposition,
as well as funding the necessary facilities, operations, and Russian assistance to implement the
program. Congressional debate is now focusing on the U.S. program’s escalating costs and the
Obama Administration’s FY2015 proposal to halt construction of plutonium disposition facilities
in South Carolina and prepare a new strategy.
program. Because of sharply rising cost estimates for plutonium disposition facilities under construction in South Carolina, the Obama Administration proposed in its FY2015 budget request to suspend construction and consider other plutonium disposition options. However, Congress voted to continue construction in FY2015 and require a new, independent cost study. The Administration proposes to continue construction at the same level in FY2016, pending the outcome of the study.
In September 1998, the United States and Russia each agreed to convert 34 metric tons of surplus
weapons-grade plutonium to a form that could not be returned to nuclear weapons under the
Plutonium Management and Disposition Agreement (PMDA). The agreement was designed to
ease concerns about the possible theft or diversion of weapons-grade plutonium by nations or
others seeking to develop their own nuclear weapons. According to the agreement, the parties
could use two methods for disposing of the plutonium—they could either convert it to mixed
oxide (MOX) fuel for nuclear power reactors or immobilize it and dispose of it in a way that
would preclude its use in nuclear weapons. However, Russia has expressed little interest in the
permanent immobilization and disposal of plutonium, or burning it in conventional reactors,
preferring to use the material as fuel for its civilian fast reactor program. The United States
initially intended to pursue both immobilization and MOX fuel for conventional reactors.
However, after reviewing U.S. nonproliferation policies in 2001, the Bush Administration
concluded that the dual approach would be too costly. Instead, it outlined a plan for the United
States to convert almost all its surplus plutonium to MOX fuel.
The PMDA was amended with a Protocol which entered into force on July 13, 2011. The PMDA
Protocol
renewsrenewed the commitment of each side to dispose of 34 metric tons of weapons-grade
plutonium. It also
layslaid out conditions for Russian use of the plutonium as fast reactor fuel,
including restrictions on breeding additional plutonium in fast reactors.
11 The two countries agreed
to begin plutonium disposition in 2018. The United States
ispledged to pay $400 million to support the
Russian plutonium disposition. The Russian government is to fund the remainder of the
approximately $2.5 billion in estimated costs. The plutonium disposition program, including U.S.
assistance for the Russian program, is administered by the National Nuclear Security
Administration (NNSA), a semiautonomous agency of the Department of Energy (DOE).
A key component of the U.S. strategy for disposing of surplus weapons plutonium has been the
Mixed Oxide Fuel Fabrication Facility (MFFF) at DOE
’'s Savannah River Site in South Carolina.
NNSA estimated in 2002 that MFFF would cost about $1 billion to design and build. That
estimate had risen to $4.8 billion when the construction of MFFF began in 2007. According to
DOE’ DOE's FY2014 budget request, the MFFF contractor then estimated that the project
’s total
1
2000 Plutonium Management and Disposition Agreement as amended by the 2010 Protocol, Article III,
http://fissilematerials.org/library/PMDA2010.pdf.
Congressional Research Service
1
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
's total construction cost would rise to $7.78 billion, and that construction would not be completed until
November 2019. DOE
has slowed construction during FY2013 and FY2014 while other
disposition options
arewere evaluated.
DOE’
DOE's FY2015 budget justification
sayssaid the total lifecycle cost of the MOX fuel program for
plutonium disposition—including construction, operations, waste management, and facility
decommissioning—
hashad risen to $30 billion. Because of that increase, according to DOE,
“the
"the MOX fuel approach is not viable within the available resources.
”" DOE
plansplanned to put MFFF and
related facilities currently under construction in
“"cold standby,
”" reducing funding for the U.S.
plutonium disposition program from $560.3 million in FY2014 to $286 million in FY2015. DOE
plans to “ planned to "further analyze options to complete the plutonium disposition mission more
efficiently.”2
Russian Program
The Russian Surplus Fissile Materials Disposition program, run by NNSA, is to provide $400
million to help Russia dispose of its surplus weapons plutonium.3 The DOE FY2015
congressional budget request says that putting the U.S. facility in cold standby “does not
diminish” the commitment to the U.S.-Russia Plutonium Management and Disposition
Agreement (PMDA), and that the United States will continue to work with Russia to achieve the
program’s primary goal of Russian disposition of equal quantities of plutonium.
The United States and Russia, along with the International Atomic Energy Agency (IAEA), are
negotiating an agreement on verification of plutonium disposition in each country. IAEA will
have a role in verifying the quantities of weapons-grade plutonium converted to fuel in both
countries. The United States and Russia are also negotiating a “Milestones” plan, which would
outline how the U.S. assistance to the Russian plutonium disposition effort would be spent.
Negotiations related to the plutonium disposition agreement are led by the Department of State’s
Bureau of International Security and Nonproliferation together with NNSA. According to DOE’s
FY2015 budget request, Russia has made “significant progress” toward its PMDA commitments.4
Russia is planning to use its BN-600 and BN-800 fast neutron reactors for plutonium disposition.
According to the World Nuclear Association, the BN-800 construction is “well-advanced,” and
the reactor is “capable of burning 1.7 metric tons of plutonium per year from dismantled
weapons.”5
As shown in Table 1, DOE requested $10.174 million for the Russian plutonium disposition
program for FY2012. The Senate Appropriations Committee recommended $1 million for
2
DOE, FY 2015 Congressional Budget Request, Vol. 1, March 2014, pp. 523, 525, 543, http://energy.gov/sites/prod/
files/2014/03/f12/Volume%201%20NNSA.pdf.
3
This is a sub-program of the NNSA’s Defense Nuclear Nonproliferation budget, Fissile Materials Disposition
program.
4
DOE, FY 2015 Congressional Budget Request, Vol. 1, March 2014, p. 536, http://energy.gov/sites/prod/files/2014/03/
f12/Volume%201%20NNSA.pdf.
5
The reactor’s rated thermal power is 2,100 megawatts (MWt), generating 880 megawatts of electricity (MWe),
http://www.world-nuclear.org/info/Current-and-Future-Generation/Fast-Neutron-Reactors/.
Congressional Research Service
2
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
FY2012, and that level was enacted. The Senate Committee included this reasoning in its report
(S.Rept. 112-75):
efficiently."2
Congress rejected the Administration's plan to put MFFF in "cold standby." The FY2015 National Defense Authorization Act (P.L. 113-29) and the FY2015 Consolidated and Further Continuing Appropriations Act (P.L. 113-235) each required DOE to conduct independent cost and schedule estimates for MFFF and analyze alternative disposition approaches. The two acts authorized and appropriated $345 million to continue MFFF construction at a reduced level from FY2014. DOE's FY2016 budget justification said that Aerospace Corporation had been contracted to carry out the required analyses, which are to be completed during FY2015, after which "a decision will be reached on outyear funding levels for plutonium disposition." Pending that decision, DOE requested $345 million for FY2016 to continue MFFF construction at the FY2015 level.3
Russian Program
The DOE FY2016 congressional budget request says that NNSA will continue supporting the U.S.-Russia PMDA and that the United States will continue to work with Russia to achieve the program's primary goal of Russian disposition of equal quantities of plutonium to the U.S. amount.
The United States and Russia, along with the International Atomic Energy Agency (IAEA), are negotiating an agreement on verification of plutonium disposition in each country. IAEA will have a role in verifying the quantities of weapons-grade plutonium converted to fuel in both countries. The United States and Russia are also negotiating a "Milestones" plan, which would outline how the U.S. assistance to the Russian plutonium disposition effort would be spent. Negotiations related to the plutonium disposition agreement are led by the Department of State's Bureau of International Security and Nonproliferation together with NNSA.
Russia is planning to use its BN-600 and BN-800 fast neutron reactors for plutonium disposition. According to the World Nuclear Association, the BN-800 construction is "well-advanced," and the reactor is "capable of burning 1.7 metric tons of plutonium per year from dismantled weapons."4
The Russian Surplus Fissile Materials Disposition program, run by NNSA, is to provide $400 million to help Russia dispose of its surplus weapons plutonium.5 However, no funds have been requested since FY2013. As shown in Table 1, DOE requested $10.174 million for the Russian plutonium disposition program for FY2012. The Senate Appropriations Committee recommended $1 million for FY2012, and that level was enacted. The Senate committee included this reasoning in its report (S.Rept. 112-75):
Russian Surplus Materials Disposition.—The Committee recommends $1,000,000, a
reduction of $9,174,000. No funding shall be used to support research and development of
the Gas Turbine-Modular Helium Reactor in Russia. The Committee understands that the
United States committed $400,000,000, subject to future appropriations, to help Russia
dispose of 34 metric tons of excess weapon-grade plutonium, but the Committee will not
provide funding for this effort until NNSA can explain how the United States would spend
the $400,000,000 and the milestones that Russia must meet before the United States releases
any of those funds.
The FY2013 budget justification said that the requested funds would be used to
“provide
"provide technical support to the DOE in meeting U.S. obligations to support disposition of weapon-grade
plutonium in Russia; provide U.S. technical oversight of work in Russia associated with the
disposition of surplus Russian weapon-grade plutonium in the BN-600 and BN-800 fast reactors;
and support the implementation of IAEA verification activities in both the U.S. and Russia.
”
The FY2014 and FY2015"
The FY2014, FY2015, and FY2016 budget requests included no funds for the Russian plutonium
disposition program. NNSA plans to use prior year funds to support these activities in FY2015.
The $400 million in U.S. assistance is to be paid to Russia after FY2018, when plutonium
disposition is to begin. The Russian Federation is to fund the remaining costs of
roughly $2 billion,
including through
possible contributions from other international donors
under the G8 Global Partnership.
.
Table 1. Funding for the NNSA Russian Plutonium Disposition Program
(in $ thousands)
FY2012
FY2013
FY2016FY2019
(projected)
FY2015
Request
FY2014
DOE Request
10,174
3,788
0
0
30,000
Senate
Appropriation
1,000
3,788
n/a
n/a
n/a
House
Appropriation
10,174
0
n/a
n/a
n/a
1,000
922
n/a
n/a
n/a
Enacted
Source:
(in $ thousands)
FY2012
|
FY2013
|
FY2014
|
FY2015
|
FY2016 Request
|
DOE Request
|
10,174
|
3,788
|
0
|
0
|
0
|
Senate Appropriation
|
1,000
|
3,788
|
n/a
|
n/a
|
n/a
|
House Appropriation
|
10,174
|
0
|
n/a
|
n/a
|
n/a
|
Enacted
|
1,000
|
922
|
n/a
|
0
|
0
|
Source: Department of Energy Congressional Budget Justifications; S.Rept. 112-164
, , H.Rept. 112-462
.
.
Notes: All of the above funds are to be spent in the United States. Appropriations for FY2013, FY2014, and
FY2015 are to be supported from prior-year uncosted balances.
Congressional Research Service
3
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
U.S. Program
n/a: not available or not specified.
U.S. Program
The U.S. Plutonium Disposition Program is also conducted by NNSA. The program had long
planned to blend surplus plutonium from the U.S. nuclear weapons program with uranium to
make MOX fuel for commercial nuclear reactors. After fueling a reactor for several years, the
plutonium in MOX fuel would be mostly destroyed by fission, and remaining plutonium would
be isotopically undesirable for weapons use. In addition, the used MOX fuel would contain highly
radioactive fission products that would make it difficult to divert for weapons purposes.
Initially, the U.S. program planned to dispose of 34 metric tons of surplus weapons plutonium in
this manner—
“"enough for thousands of nuclear weapons,
”" according to NNSA.
66 NNSA
subsequently proposed making MOX fuel from an additional 7.1 metric tons of plutonium from
retired nuclear weapons and another 6 metric tons of weapons-useable plutonium from other
sources, for a total of 47.1 metric tons.
7
The comment period on the proposed additional plutonium disposal closed on October 10, 2012.7
The first step in the plutonium disposition process is to disassemble the plutonium
“"pits,
”" or
cores, from nuclear weapons or other sources. Then the plutonium metal must be converted to
plutonium oxide to be useable as nuclear reactor fuel. NNSA announced in 2012 that it had
produced 442 kilograms of plutonium oxide at Los Alamos National Laboratory in New Mexico
and had begun plutonium oxide production at the Savannah River Site.
8
8 DOE's budget justification says 100 kilograms will be converted at Los Alamos and 250 kilograms at Savannah River during FY2016.
Under the MOX disposition approach, the plutonium oxide produced at Los Alamos and
Savannah River would be blended with uranium, placed in fuel rods, and connected into fuel
assemblies for standard commercial power reactors
(light water reactors). This fuel fabrication process would take
place at the Mixed Oxide Fuel Fabrication Facility. After receiving a construction permit from the
Nuclear Regulatory Commission (NRC) in 2005, MFFF
began constructionconstruction began in August 2007.
9
9 MFFF is designed to convert up to 3.5 metric tons of plutonium per year into MOX fuel and
would operate for about 20 years.
10
10
Getting utilities to commit to loading MOX fuel into their reactors has been a major problem for
the plutonium disposition program. Although MOX fuel has been routinely used in Europe, it has
enough differences from the conventional uranium fuel currently used by U.S. nuclear plants that
it would require separate NRC licensing and special handling. The use of MOX fuel would also
probably create public controversy. Two utilities that had previously planned to use the MOX
fuel, Dominion and Duke, are no longer involved. The Tennessee Valley Authority (TVA)
subsequently entered into an agreement with DOE
“"to evaluate the use of mixed oxide fuel in
reactors at TVA
’'s Browns Ferry and Sequoyah Nuclear Plants.
” However, TVA has not yet
6
NNSA, “Plutonium Disposition,” http://nnsa.energy.gov/aboutus/ourprograms/nonproliferation/programoffices/
fissilematerialsdisposition/plutoniumdisposition.
7
NNSA, “Surplus Plutonium Disposition Supplemental Environmental Impact Statement,”
http://www.nnsa.energy.gov/aboutus/ouroperations/generalcounsel/nepaoverview/nepa/spdsupplementaleis.
8
NNSA, “NNSA Completes Milestones for Initial Steps in Plutonium Disposition,” press release, November 16, 2012,
http://nnsa.energy.gov/mediaroom/pressreleases/oxideprod111612. A somewhat smaller amount of plutonium metal
would be used as feed material for the plutonium oxide, depending on isotopic composition.
9
NNSA, “NNSA’s MOX Fuel Fabrication Facility and U.S. Plutonium Disposition Program,” fact sheet, February 14,
2011, http://www.nnsa.energy.gov/mediaroom/factsheets/mox.
10
Shaw Areva MOX Services, “MOX Fuel Fabrication Facility Construction,” http://www.moxproject.com/
construction.
Congressional Research Service
4
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
" However, TVA has not yet committed to using MOX fuel, or indicated which of its reactors would be used.
1111 The selection
of reactors is important, because MOX fuel assemblies must be fabricated to fit particular
reactors.
ParticularlyEspecially significant are the design differences between fuel assemblies for boiling
water reactors, such as Browns Ferry, and pressurized water reactors, such as Sequoyah.
Management and Cost
NNSA’
NNSA's initial February 2002 report to Congress for the MOX plutonium disposition program
estimated construction of MFFF would begin in FY2004 and cost about $1 billion to design and
build. By July 2005, the design and construction cost estimate had risen to $3.5 billion, according
to the DOE Office of Inspector General (OIG). OIG identified numerous management
weaknesses that contributed to the rising costs. However, NNSA contended that much of the cost
increase resulted from changes in project scope, such as increases in up-front design work, and
delays in Russia over liability issues, which caused parallel delays in the U.S. program.
12
12
By the time MFFF construction began in 2007, the construction cost estimate had risen to $4.8
billion. About $100 million of that cost increase was caused by congressional funding holdups,
according to NNSA.
1313 For example, the Bush Administration requested $653.1 million for fissile
materials disposition in FY2006, while Congress appropriated $473.5 million. But for FY2004, in
contrast, Congress approved the full request of $656.5 million.
Congress required in 2002 that MFFF produce at least 1 metric ton of MOX fuel by the end of
2008 and complete the then-planned program of 34 metric tons of plutonium conversion by
January 1, 2019 (P.L. 107-314, Section 3182). Section 3116 of the National Defense
Authorization Act for FY2013 (P.L. 112-239) extended the deadline for starting MOX production
to January 1, 2014 (50 U.S.C. 2566).
DOE announced a major reevaluation of the plutonium disposition program in its FY2014 budget
submission to Congress. According to the budget request, the MFFF contractor then estimated
that the project
’'s total construction cost would rise from $4.8 billion to $7.78 billion, and that
construction would not be completed until November 2019. Moreover, MFFF
’'s operating costs
were estimated at $543 million per year, up from $100.5 million estimated in 2002.
1414 The
Government Accountability Office (GAO) in a February 2014 report said NNSA had provided
several major reasons for the most recent cost increases, including DOE
’'s approval of a cost and
schedule estimate in 2007 when the overall design was only about 58% complete. Other problems
included higher-than-anticipated equipment installation costs, difficulties in finding qualified
suppliers, high staff turnover, and further changes in project scope.
15 GAO had found in 2010 that
11
NNSA, “Surplus Plutonium Disposition Supplemental Environmental Impact Statement,” op. cit.
DOE Office of Inspector General, Audit Report: Status of the Mixed Oxide Fuel Fabrication Facility, DOE/IG-0713,
December 2005, http://energy.gov/sites/prod/files/igprod/documents/CalendarYear2005/ig-0713.pdf.
13
Daniel Horner, “Hill-Imposed Delay in MOX Program Costing $115 Million, DOE Says,” NuclearFuel, April 23,
2007.
14
DOE, FY 2007 Congressional Budget, Vol. 1, p. 558, http://energy.gov/sites/prod/files/FY07Volume1.pdf.
15
GAO, Plutonium Disposition Program: DOE Needs to Analyze the Root Causes of Cost Increases and Develop
Better Cost Estimates, GAO-14-231, February 2014, http://www.gao.gov/assets/670/660927.pdf.
12
Congressional Research Service
5
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
15 GAO had found in 2010 that MFFF had experienced consistent delays during the previous two years, partly because of the
installation of nearly 4,000 tons of substandard reinforcing bars.
16
16
Because of the cost increases, the Obama Administration slowed the project in FY2013 and
FY2014 to consider
“"alternative plutonium disposition strategies.
”" A Plutonium Disposition
Working Group established by the Secretary of Energy began comparing the MOX option with
plutonium destruction in fast neutron reactors and non-reactor disposal options, such as blending
and spiking with highly radioactive materials.
DOE’
DOE's FY2015 budget justification
sayssaid the total lifecycle cost of the MOX disposition option
has had risen to $30 billion—from $24.2 billion in April 2013.
17 “17 "Due to these increases, the MOX
fuel approach is not viable within available resources,
”" according to the DOE justification.
“"As a
result, the MOX project will be placed in cold stand-by while we further study implementation
and costs of options to complete the plutonium disposition mission more efficiently.
”
Total funding for plutonium disposition would drop from $560.3 million in FY2014 to $286.1
million in FY2015, under the Administration’s request. No funding would be provided for
operations and maintenance related to the MOX Waste Solidification Building, plutonium
disposition and infrastructure, and management and integration. Preparation of plutonium
material for disposition would continue. Construction funding for MFFF would be cut from
$402.7 million (including reprogrammed funds) to $196.0 million as the facility is placed into
“cold standby,” or indefinite suspension. Contract personnel at the MOX project declined from
2,271 at the beginning of April 2013 to 1,523 by the end of December, according to the budget
justification.18
MOX and Nonproliferation
The extent to which the plutonium disposition programs help or harm nonproliferation goals has
been debated since their inception. Some analysts have criticized the MOX option on the
principle of opposing any use of plutonium in power generation. From this point of view, nations
that do not possess nuclear weapons could use a plutonium-based fuel cycle for power reactors as
a cover for developing nuclear weapons. If weapons states such as Russia and the United States
used plutonium for power generation, according to this argument, it would be more difficult to
persuade non-weapons states not to do so.
Another issue has been whether the Russian disposition program that will make fuel for fast
reactors will result in more or less plutonium in the long run. Fast reactors can “breed” or “burn”
plutonium as a net output. The reactor acts as a breeder (producing more plutonium than it
destroys) if the core includes sufficient amounts of uranium-238, which can absorb a neutron and
then decay into the fissile isotope plutonium-239. Without uranium-238, the reactor would
consume the original plutonium fuel without producing new plutonium in its place. The potential
for breeding new plutonium was a major concern of the United States in negotiations over the
16
GAO, “Nuclear Nonproliferation: DOE Needs to Address Uncertainties with and Strengthen Independent Safety
Oversight of Its Plutonium Disposition Program,” GAO-10-378, March 2010, p. 9, http://www.gao.gov/assets/310/
302279.pdf.
17
GAO, 2014, op. cit.
18
DOE, FY 2015 Congressional Budget Request, op. cit.
Congressional Research Service
6
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
PMDA Protocol and resulted in restrictions on producing new plutonium in these fast reactors
using this material. The verification agreement negotiations include discussions of how to
technically verify this. In the 2010 Protocol, Russia agreed to restrictions on the reactors that are
intended to prevent the creation of more plutonium than is destroyed.19
An additional criticism of the program from a nonproliferation perspective is that the high cost
required to date for the plutonium disposition program in the United States is funded out of the
Defense Nuclear Nonproliferation budget. There is concern that money is being taken away from
other programs which some consider to have a more direct impact on preventing the proliferation
of weapons-usable nuclear materials. Programs cited include the Second Line of Defense border
"
The Plutonium Disposition Working Group issued its report in April 2014, providing life-cycle cost and schedule estimates for the following options:18
- Irradiation of MOX fuel in light water reactors (current program): $31 billion including costs already expended (sunk costs), estimated completion by 2043;
- Irradiation in fast (advanced) reactors: $58 billion including sunk costs, estimated completion by 2075;
- Immobilization with high level (highly radioactive) waste: $36 billion including sunk costs, estimated completion by 2060;
- Downblending and disposal (potentially in the existing Waste Isolation Pilot Plant repository in New Mexico): $16 billion including sunk costs; estimated completion by 2046; and
- Deep borehole disposal: costs unknown, estimated completion by 2051.
Under the Administration's FY2015 request, construction funding for MFFF would have been cut from $402.7 million (including reprogrammed funds) to $196.0 million as the facility was placed into "cold standby," or indefinite suspension. Contract personnel at the MOX project declined from 2,271 at the beginning of April 2013 to 1,523 by the end of December 2013, according to the budget justification.19
However, as noted above, Congress rejected the Administration's plan to put MFFF in "cold standby." Instead, Congress appropriated $345 million to continue MFFF construction at a reduced level from FY2014 and required DOE within 120 days to conduct an "independently verified lifecycle cost estimate for the option to complete construction and operate the MOX facility and the option to downblend and dispose of the material in a repository." DOE requested $345 million for FY2016 to continue MFFF construction at the FY2015 level, pending a decision based on the new study. The MFFF project currently has about 1,700 workers, according to NNSA.20
MOX and Nonproliferation
The extent to which the plutonium disposition programs help or harm nonproliferation goals has been debated since their inception. Some analysts have criticized the MOX option on the principle of opposing any use of plutonium in power generation. From this point of view, nations that do not possess nuclear weapons could use a plutonium-based fuel cycle for power reactors as a cover for developing nuclear weapons. If weapons states such as Russia and the United States used plutonium for power generation, according to this argument, it would be more difficult to persuade non-weapons states not to do so.
Another issue has been whether the Russian disposition program that will make fuel for fast reactors will result in more or less plutonium in the long run. Fast reactors can "breed" or "burn" plutonium as a net output. The reactor acts as a breeder (producing more plutonium than it destroys) if the core includes sufficient amounts of uranium-238, whose nuclei can absorb a neutron and then decay into the fissile isotope plutonium-239. Without uranium-238, the reactor would consume the original plutonium fuel without producing new plutonium in its place. The potential for breeding new plutonium was a major concern of the United States in negotiations over the PMDA Protocol and resulted in restrictions on producing new plutonium in the fast reactors using this material. The verification agreement negotiations include discussions of how to technically verify this. In the 2010 Protocol, Russia agreed to restrictions on the reactors that are intended to prevent the creation of more plutonium than is destroyed.21
An additional criticism of the program from a nonproliferation perspective is that the high cost required to date for the plutonium disposition program in the United States is funded out of the Defense Nuclear Nonproliferation budget. There is concern that money is being taken away from other programs which some consider to have a more direct impact on preventing the proliferation of weapons-usable nuclear materials. Programs cited include the Second Line of Defense border security program or the Global Threat Reduction Initiative.22security program or the Global Threat Reduction Initiative. Non-governmental nonproliferation
experts have made recent public statements.
2023 For example, Joe Cirincione of the Ploughshares
Fund has said,
“"funding for the plutonium fuel facility falls within the nuclear nonproliferation
budget. That means that every dollar spent on unnecessary programs like MOX is one dollar less
for vital nonproliferation programs that keep nuclear material and technology out of the hands of
terrorists.
”21"24 In light of this concern, in June 2012 the House passed an amendment to the FY2013
Energy and Water Appropriations bill proposed by Representative Fortenberry to reprogram
money from the U.S. MOX program to the Global Threat Reduction Initiative.
2225 The provision
ultimately was not enacted, however.
Other observers, including within the executive branch, note that the purpose of this program is
nonproliferation—rendering weapons-grade plutonium unusable for nuclear weapons on the basis
of mutual verification. The American Nuclear Society has come out strongly in favor of the
program for nonproliferation reasons.
23
26
Issues for Congress
Recent public debate surrounding the U.S. plutonium disposition program has centered on the
budget trade-offs of funding the U.S. plutonium disposition program in light of sequestration and
other funding limitations. Local concerns have focused on potential economic losses
in the region
around the MFFF project and the possibility that plutonium brought to Savannah River for use as nuclear fuel will end up
being stored there indefinitely. National concerns have been raised that a halt or serious delay to
the U.S. program would cause the Russians to reconsider their obligations to dispose of their
excess weapons plutonium.
19
Governments of the United States and the Russian Federation, 2000 Plutonium Management and Disposition
Agreement as Amended by the 2010 Protocol, Article III.3, http://fissilematerials.org/library/PMDA2010.pdf.
20
Reif Kingston, “New Obama Budget Slashes Nonproliferation,” The Center for Arms Control and Non-Proliferation,
March 6, 2014, http://armscontrolcenter.org/issues/nuclearterrorism/articles/
new_obama_budget_slashes_nonproliferation/.
21
Joe Cirincione, “The Federal Government’s $10 Billion Plutonium Boondoggle,” The Atlantic, April 27, 2012,
http://www.theatlantic.com/politics/archive/2012/04/the-federal-governments-10-billion-plutonium-boondoggle/
256470/.
22
“House Accepts Fortenberry Measure to Strengthen Nuclear Security Efforts,” Press Release, Office of
Representative Jeff Fortenberry, June 6, 2012, http://fortenberry.house.gov/index.php?option=com_content&view=
article&id=3662:house-accepts-fortenberry-measure-to-strengthen-nuclear-security-efforts&catid=41:press-releases&
Itemid=2; “House Bill Shifts Money from MOX Plant to Nuclear Security,” Global Security Newswire, June 7, 2012.
23
American Nuclear Society, Position Statement 47, http://www.new.ans.org/pi/ps/docs/ps47.pdf.
Congressional Research Service
7
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
excess weapons plutonium.
Due to the cost and management challenges of the MOX program, others have raised the
possibility of finding an alternative to MOX fuel production as a means to fulfill the U.S.-Russian
PMDA.
2427 Supporters, however, counter that sunk costs in the current program would make
pursuing an alternative path more expensive in the long run.
25
28
In testimony before Congress
in early 2013, Obama Administration officials reiterated their
commitment to the PMDA agreement with Russia.
2629 The FY2014 and FY2015 DOE budget
justifications
statestated that
“"NNSA remains committed to the plutonium disposition mission.
”
" However, as noted above, the Administration is now considering alternative strategies for
achieving that mission.
2730 According to the 2010 Protocol amending the PMDA, the United States
would have to obtain written agreement with Russia to implement any alternative to irradiating
plutonium in nuclear reactors.
28
31
In its report on the National Defense Authorization Act for FY2014 (H.R. 1960
, , H.Rept.
113102113-102), the House Committee on Armed Services expressed concern about MFFF
’s “continuing
's "continuing escalating costs
”" but suggested that the Administration
’'s proposed budget cuts
“"may not actually
reduce costs to the taxpayer and will likely delay the disposition of 34 metric tons of weapons
grade plutonium.
” The Committee" The committee directed NNSA to study potential cost savings, consider
adding international partners to the program, and study
“"the potential for achieving greater
economic efficiencies by designating additional supplies of surplus plutonium for disposition
through the MOX facility.
”" However, the bill as approved by the
Committeecommittee retained the
Administration’ Administration's proposed construction funding cut.
The Senate Armed Services Committee approved its version of the
FY2014 defense authorization measure
( (S. 1034) on June 14, 2013. The
Committeecommittee voted to boost authorized funding for surplus nuclear
materials disposition by $80 million over the Administration request.
2932 Congress appropriated
$526.1 million for Fissile Materials Disposition for FY2014, a cut of $136.7 million from the
FY2013 level. However, the FY2014 appropriation was bolstered by a $59.2 million
reprogramming from the International Material Protection and Cooperation account, according to
DOE’ DOE's FY2015 justification.
The State of South Carolina filed a lawsuit on March 18, 2014, to block DOE from placing MFFF
in cold standby and to require that construction continue in FY2014. The suit
maintainsmaintained that the
Bob Stump National Defense Authorization Act for Fiscal Year 2003 (P.L. 107-314
) "was enacted to codify the commitments of the United States and DOE to the State of South Carolina that while plutonium may be placed in South Carolina, such placement was not final disposition for long-term storage of plutonium in the State, but rather a temporary storage to implement the disposition method of MOX processing in the MOX Facility."33
Some South Carolina lawmakers and officials have also stressed that South Carolina agreed to accept surplus plutonium from other weapons complex facilities with the understanding that it would be removed under a definite schedule. Plutonium that is made into MOX fuel, they point out, would be shipped off-site to commercial nuclear power plants, while alternatives such as immobilization in glass would provide no clear path for removal, given the current lack of a federal high-level waste central storage facility or underground repository.34
Section 3181 of the Bob Stump Defense Authorization (50 U.S.C. 2566) would penalize DOE if it misses various MOX fuel fabrication deadlines. As amended by Section 3116 of the National ) “was enacted
24
Frank von Hippel, Rodney Ewing, Richard Garwin, Alison MacFarlane, “Time to Bury Plutonium,” Nature, May 10,
2012. For DOE’s analyzed MOX alternatives, see Draft Surplus Plutonium Disposition Supplemental Environmental
Impact Statement, summary, DOE/EIS-0283-S2, July 2012, http://nnsa.energy.gov/sites/default/files/nnsa/07-12inlinefiles/Summary.pdf.
25
http://us.arevablog.com/2013/02/19/answers-to-questions-about-funding-mox-project-budget/.
26
House Appropriations Subcommittee on Energy and Water Development Hearing on the Proposed Fiscal 2014
Appropriations for the Energy Department's Nuclear Nonproliferation and Naval Reactor Programs and the National
Nuclear Security Administration, February 26, 2013.
27
DOE, FY 2014 Congressional Budget Request, Vol. 1, April 2013, p. DN-119, http://energy.gov/sites/prod/files/
2013/04/f0/Volume1.pdf.
28
2000 Plutonium Management and Disposition Agreement as amended by the 2010 Protocol, Article III,
http://fissilematerials.org/library/PMDA2010.pdf.
29
Senate Committee on Armed Services, “Senate Committee on Armed Services Completes Markup of the National
Defense Authorization Act for Fiscal Year 2014,” June 14, 2013, http://www.armed-services.senate.gov/press/releases/
upload/SASC_NDAA_061413.pdf.
Congressional Research Service
8
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
to codify the commitments of the United States and DOE to the State of South Carolina that while
plutonium may be placed in South Carolina, such placement was not final disposition for longterm storage of plutonium in the State, but rather a temporary storage to implement the
disposition method of MOX processing in the MOX Facility.”30
Some South Carolina lawmakers and officials have also stressed that South Carolina agreed to
accept surplus plutonium from other weapons complex facilities with the understanding that it
would be removed under a definite schedule. Plutonium that is made into MOX fuel, they point
out, would be shipped off-site to commercial nuclear power plants, while alternatives such as
immobilization in glass would provide no clear path for removal, given the current lack of a
federal high-level waste central storage facility or underground repository.31
Section 3181 of the Bob Stump Defense Authorization (50 U.S.C. 2566) would penalize DOE if it
misses various MOX fuel fabrication deadlines. As amended by Section 3116 of the National
Defense Authorization Act for 2013 (P.L. 112-239), which delayed the previous deadlines by two
years, the act requires that at least one ton of MOX fuel be produced each year, starting in 2014,
or plutonium transfers into the state must be halted. If plutonium brought into the state since 2002
is not processed into MOX fuel by 2022, DOE must pay the state up to $100 million per year
until it is removed.
DOE said in its FY2015 budget justification that it would not meet the 2014 MOX production
deadline in P.L. 112-239. In light of the act
’'s requirements, DOE said that it had
“"suspended any
further transfers of defense plutonium and defense plutonium materials to be processed at the
MOX facility in the State of South Carolina.
”" DOE also said that it
“"will submit a report to
Congress on options for removing an amount of defense plutonium or defense plutonium
materials from the State of South Carolina equal to the amount of defense plutonium or defense
plutonium materials transferred to the State of South Carolina after April 15, 2002.”
30
State of South Carolina v. United States Department of Energy, United States District Court, District of South
Carolina, Aiken Division, March 18, 2014, http://2hsvz0l74ah31vgcm16peuy12tz.wpengine.netdna-cdn.com/wpcontent/uploads/2014/03/MOX-complain-3.18.2014-00269474xD2C78.pdf.
31
Rob Pavey, “Sen. Lindsey Graham Says Reducing MOX Costs Could Save the Project,” Augusta Chronicle, April
25, 2013, http://chronicle.augusta.com/news/government/2013-04-25/sen-lindsey-graham-says-reducing-mox-costscould-save-project.
Congressional Research Service
9
Table 2. Defense Nuclear Nonproliferation Appropriations FY2007-FY2015
(in $ thousands)
FY07
FY08
FY09
FY10
FY11
FY12
FY13
FY14
Enacted
FY14
Reprograma
FY15
Request
Fissile Materials
Disposition
470,062
66,235
41,774
701,900
802,198
685,386
663,754
526,057
585,300
311,125
U.S. Surplus
Materials
Disposition
470,062
66,235
40,774
700,900
802,173
684,386
662,832
526,057
585,300
311,125
U.S. Pu
Disposition
57,415
0
0
91,659
200,400
205,632
189,480
157,557
157,557
85,000
U.S. Uranium
Disposition
86,898
66,235
39,274
34,691
25,985
26,000
23,958
25,000
25,000
25,000
Supporting
Activities
14,960
0
1,500
312
0
0
0
0
0
0
Construct.
310,789
0
0
574,238
575,788
452,754
449,394
343,500
402,743
201,125
262,500
0
0
504,238
501.788
435,172
400,990
343,500
402,743
196,000
Pit Dis.
32,789
0
0
0
17.000
0
0
0
0
0
Waste Solid.
15,500
0
0
70,000
57.000
17,582
48,404
0
0
5,125
0
0
1,000
1,000
25
1,000
922
0
0
0
MOX Fuel Fab
Russian Materials
Disposition
Source: plutonium materials transferred to the State of South Carolina after April 15, 2002."
Table 2. Defense Nuclear Nonproliferation Appropriations FY2007-FY2015 and FY2016 Request
(in $ thousands)
FY07
|
FY08
|
FY09
|
FY10
|
FY11
|
FY12
|
FY13
|
FY14 Enacted
|
FY14 Repro-grama
FY15
|
FY16 Request
|
Fissile Materials Disposition
|
470,062
|
66,235
|
41,774
|
701,900
|
802,198
|
685,386
|
663,754
|
526,057
|
585,300
|
430,000
|
427,584
|
U.S. Surplus Materials Disposition
|
470,062
|
66,235
|
40,774
|
700,900
|
802,173
|
684,386
|
662,832
|
526,057
|
585,300
|
311,125
|
82,584
|
U.S. Pu Disposition
|
57,415
|
0
|
0
|
91,659
|
200,400
|
205,632
|
189,480
|
157,557
|
157,557
|
60,000
|
50,504
|
U.S. Uranium Disposition
|
86,898
|
66,235
|
39,274
|
34,691
|
25,985
|
26,000
|
23,958
|
25,000
|
25,000
|
25,000
|
31,080
|
Supporting Activities
|
14,960
|
0
|
1,500
|
312
|
0
|
0
|
0
|
0
|
0
|
0
|
1,000
|
Construct.
|
310,789
|
0
|
0
|
574,238
|
575,788
|
452,754
|
449,394
|
343,500
|
402,743
|
345.000
|
MOX Fuel Fab
|
262,500
|
0
|
0
|
504,238
|
501.788
|
435,172
|
400,990
|
343,500
|
402,743
|
345,000
|
345,000
|
Pit Dis.
|
32,789
|
0
|
0
|
0
|
17.000
|
0
|
0
|
0
|
0
|
0
|
0
|
Waste Solid.
|
15,500
|
0
|
0
|
70,000
|
57.000
|
17,582
|
48,404
|
0
|
0
|
0
|
0
|
Russian Materials Disposition
|
0
|
0
|
1,000
|
1,000
|
25
|
1,000
|
922
|
0
|
0
|
0
|
0
|
Source: CRS-compiled information from DOE annual budget requests to Congress, H.Rept. 112-118, and S.Rept. 112-75
.
a.
CRS-10
.
a. Reflects a reprogramming of $59,242,760 from FY2013 International Material Protection and Cooperation funding to Fissile Material Disposition in
FY 2014.
Mixed-Oxide Fuel Fabrication Plant and Plutonium Disposition
Author Contact Information
Mark Holt
Specialist in Energy Policy
mholt@crs.loc.gov, 7-1704
Congressional Research Service
Mary Beth D. Nikitin
Specialist in Nonproliferation
mnikitin@crs.loc.gov, 7-7745
11
FY2014.
Footnotes
1.
|
2000 Plutonium Management and Disposition Agreement as amended by the 2010 Protocol, Article III, http://fissilematerials.org/library/PMDA2010.pdf.
|
2.
|
DOE, FY 2015 Congressional Budget Request, Vol. 1, March 2014, pp. 523, 525, 543, http://energy.gov/sites/prod/files/2014/03/f12/Volume%201%20NNSA.pdf.
|
3.
|
DOE, FY 2016 Congressional Budget Request, Vol. 1, February 2015, pp. 561-569, http://energy.gov/cfo/downloads/fy-2016-budget-justification.
|
4.
|
The reactor's rated thermal power is 2,100 megawatts (MWt), generating 880 megawatts of electricity (MWe), http://www.world-nuclear.org/info/Current-and-Future-Generation/Fast-Neutron-Reactors/.
5.
|
This is a sub-program of the NNSA's Defense Nuclear Nonproliferation budget. In the FY2016 request, this program is in the Material Disposition subaccount under the Office of Material Management and Minimization. It was formerly in the Fissile Material Disposition account.
|
6.
|
NNSA, "Plutonium Disposition," http://nnsa.energy.gov/aboutus/ourprograms/nonproliferation/programoffices/fissilematerialsdisposition/plutoniumdisposition.
|
7.
|
NNSA, "Surplus Plutonium Disposition Supplemental Environmental Impact Statement," http://www.nnsa.energy.gov/aboutus/ouroperations/generalcounsel/nepaoverview/nepa/spdsupplementaleis.
|
8.
|
NNSA, "NNSA Completes Milestones for Initial Steps in Plutonium Disposition," press release, November 16, 2012, http://nnsa.energy.gov/mediaroom/pressreleases/oxideprod111612. A somewhat smaller amount of plutonium metal would be used as feed material for the plutonium oxide.
|
9.
|
NNSA, "NNSA's MOX Fuel Fabrication Facility and U.S. Plutonium Disposition Program," fact sheet, February 14, 2011, http://www.nnsa.energy.gov/mediaroom/factsheets/mox.
|
10.
|
Shaw Areva MOX Services, "MOX Fuel Fabrication Facility Construction," http://www.moxproject.com/construction.
|
11.
|
NNSA, "Surplus Plutonium Disposition Supplemental Environmental Impact Statement," op. cit.
|
12.
|
DOE Office of Inspector General, Audit Report: Status of the Mixed Oxide Fuel Fabrication Facility, DOE/IG-0713, December 2005, http://energy.gov/sites/prod/files/igprod/documents/CalendarYear2005/ig-0713.pdf.
|
13.
|
Daniel Horner, "Hill-Imposed Delay in MOX Program Costing $115 Million, DOE Says," NuclearFuel, April 23, 2007.
|
14.
|
DOE, FY 2007 Congressional Budget, Vol. 1, p. 558, http://energy.gov/sites/prod/files/FY07Volume1.pdf.
|
15.
|
GAO, Plutonium Disposition Program: DOE Needs to Analyze the Root Causes of Cost Increases and Develop Better Cost Estimates, GAO-14-231, February 2014, http://www.gao.gov/assets/670/660927.pdf.
|
16.
|
GAO, "Nuclear Nonproliferation: DOE Needs to Address Uncertainties with and Strengthen Independent Safety Oversight of Its Plutonium Disposition Program," GAO-10-378, March 2010, p. 9, http://www.gao.gov/assets/310/302279.pdf.
|
17.
|
GAO, 2014, op. cit.
|
18.
|
DOE, Plutonium Disposition Working Group, Analysis of Surplus Weapon-Grade Plutonium Disposition Options, April 2014, http://nnsa.energy.gov/aboutus/ourprograms/dnn/fmd/plutonium/pudispositionoptions.
|
19.
|
DOE, FY 2015 Congressional Budget Request, op. cit.
|
20.
|
Pete Hanlon, NNSA Assistant Deputy Administrator for Material Management and Minimization, meeting with CRS analysts, February 20, 2015.
|
21.
|
Governments of the United States and the Russian Federation, 2000 Plutonium Management and Disposition Agreement as Amended by the 2010 Protocol, Article III.3, http://fissilematerials.org/library/PMDA2010.pdf.
|
22.
|
For FY2016, NNSA proposes to divide the Global Threat Reduction Initiative between Material Management and Minimization and Global Material Security.
|
23.
|
Reif Kingston, "New Obama Budget Slashes Nonproliferation," The Center for Arms Control and Non-Proliferation, March 6, 2014, http://armscontrolcenter.org/issues/nuclearterrorism/articles/new_obama_budget_slashes_nonproliferation/.
24.
|
Joe Cirincione, "The Federal Government's $10 Billion Plutonium Boondoggle," The Atlantic, April 27, 2012, http://www.theatlantic.com/politics/archive/2012/04/the-federal-governments-10-billion-plutonium-boondoggle/256470/.
25.
|
"House Accepts Fortenberry Measure to Strengthen Nuclear Security Efforts," Press Release, Office of Representative Jeff Fortenberry, June 6, 2012, http://fortenberry.house.gov/index.php?option=com_content&view=article&id=3662:house-accepts-fortenberry-measure-to-strengthen-nuclear-security-efforts&catid=41:press-releases&Itemid=2; "House Bill Shifts Money from MOX Plant to Nuclear Security," Global Security Newswire, June 7, 2012.
|
26.
|
American Nuclear Society, Position Statement 47, http://www.new.ans.org/pi/ps/docs/ps47.pdf.
|
27.
|
Frank von Hippel, Rodney Ewing, Richard Garwin, Alison MacFarlane, "Time to Bury Plutonium," Nature, May 10, 2012. For DOE's analyzed MOX alternatives, see Draft Surplus Plutonium Disposition Supplemental Environmental Impact Statement, summary, DOE/EIS-0283-S2, July 2012, http://nnsa.energy.gov/sites/default/files/nnsa/07-12-inlinefiles/Summary.pdf.
|
28.
|
http://us.arevablog.com/2013/02/19/answers-to-questions-about-funding-mox-project-budget/.
29.
|
House Appropriations Subcommittee on Energy and Water Development Hearing on the Proposed Fiscal 2014 Appropriations for the Energy Department's Nuclear Nonproliferation and Naval Reactor Programs and the National Nuclear Security Administration, February 26, 2013.
|
30.
|
DOE, FY 2014 Congressional Budget Request, Vol. 1, April 2013, p. DN-119, http://energy.gov/sites/prod/files/2013/04/f0/Volume1.pdf.
|
31.
|
2000 Plutonium Management and Disposition Agreement as amended by the 2010 Protocol, Article III, http://fissilematerials.org/library/PMDA2010.pdf.
|
32.
|
Senate Committee on Armed Services, "Senate Committee on Armed Services Completes Markup of the National Defense Authorization Act for Fiscal Year 2014," June 14, 2013, http://www.armed-services.senate.gov/press/releases/upload/SASC_NDAA_061413.pdf.
|
33.
|
State of South Carolina v. United States Department of Energy, United States District Court, District of South Carolina, Aiken Division, March 18, 2014, http://2hsvz0l74ah31vgcm16peuy12tz.wpengine.netdna-cdn.com/wp-content/uploads/2014/03/MOX-complain-3.18.2014-00269474xD2C78.pdf.
|
34.
|
Rob Pavey, "Sen. Lindsey Graham Says Reducing MOX Costs Could Save the Project," Augusta Chronicle, April 25, 2013, http://chronicle.augusta.com/news/government/2013-04-25/sen-lindsey-graham-says-reducing-mox-costs-could-save-project.
|