Coast Guard Cutter Procurement: Background and Issues for Congress

Changes from July 24, 2013 to February 27, 2014

This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.


Coast Guard Cutter Procurement: Background and Issues for Congress Ronald O'Rourke Specialist in Naval Affairs July 24, 2013February 27, 2014 Congressional Research Service 7-5700 www.crs.gov R42567 CRS Report for Congress Prepared for Members and Committees of Congress Coast Guard Cutter Procurement: Background and Issues for Congress Summary The Coast Guard’s program of record (POR) calls for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs) as replacements for 90 aging Coast Guard cutters and patrol craft. The NSC, OPC, and FRC programs have a combined estimated acquisition cost of about $21.1 billion, and the Coast Guard’s proposed FY2014 budget requests a total of $716 million in acquisition funding for the three programs. NSCs are the Coast Guard’s largest and most capable general-purpose cutters. They have an estimated average procurement cost of about $684 million per ship. The first three are now in service, the fourth, fifth, and sixth and fifth are under construction, and the sixth has been funded. The Coast long lead time materials (LLTM) for the seventh are being procured. The Coast Guard’s proposed FY2014 budget requests $616 million in acquisition funding for the seventh NSC; it does not request any funding for long lead time materials (LLTM) for the eighth NSC, which is scheduled to be procured in FY2015. OPCs are to be smaller, less expensive, and in some respects less capable than NSCs. They have an estimated average procurement cost of about $484 million per ship. The first OPC is to be procured in FY2017. The Coast Guard’s proposed FY2014 budget requests $25 million in acquisition funding for the OPC program. FRCs are considerably smaller and less expensive than OPCs. They have an estimated average procurement cost of about $73 million per boat. A total of 1824 have been funded through FY2012, and the first six had been delivered as of May 18, 2013. The Coast Guard’s proposed FY2014 FY2013. As of February 7, 2014, the first seven had been commissioned into service as of November 16, 2013. The eighth was delivered to the Coast Guard on December 10, 2013. The Coast Guard’s proposed FY2014 budget requests $75 million in acquisition funding for two FRCs and associated program costs. Potential oversight issues for Congress regarding the NSC, OPC, and FRC programs include the following: • the impact on the NSC, OPC, and FRC programs of the March 1, 2013, sequester on FY2013 funding; • the potential adequacy of the Coast Guard’s planned NSC, OPC, and FRC procurement quantities; • the impact on the NSC, OPC, and FRC programs of a possible sequester on FY2014 funding that might occur in late 2013 or early 2014 under the terms of the Budget Control Act of 2011; • the adequacy of the Coast Guard’s planned NSC, OPC, and FRC procurement quantitiesthe March 1, 2013, sequester on FY2013 funding; • the lack of a request in the Coast Guard’s proposed FY2014 budget for acquisition funding for long lead time materials (LLTM) to support the procurement of an eighth NSC in FY2015; • the Coast Guard’s FY2014 request for acquisition funding for two (rather than six) FRCs; • delays, cost growth, and testing issues in the FRC program; • the $25 million in acquisition funding requested for FY2014 for the OPC program, which is one-half of the $50 million that was projected for FY2014 under the Coast Guard’s FY2013 budget submission; • the Coast Guard’s acquisition strategy for the OPC; Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress • the potential for using multiyear procurement (MYP) in acquiring new cutters; Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress • whether 8 NSCs, 25 OPCs, and 58 FRCs is the best mix of cutters that could be procured for roughly the same total amount of acquisition funding; and • the adequacy of information available to Congress to support review and oversight of Coast Guard procurement programs, including cutter procurement programs. Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress Contents Introduction...................................................................................................................................... 1 Background ...................................................................................................................................... 1 Older Ships to Be Replaced by NSCs, OPCs, and FRCs .......................................................... 1 Missions of NSCs, OPCs, and FRCs ......................................................................................... 2 NSC Program............................................................................................................................. 3 OPC Program............................................................................................................................. 5 FRC Program ............................................................................................................................. 78 NSC, OPC, and FRC Funding in FY2013 Five-Year Capital Investment Plan ......................... 9 10 Issues for Congress ........................................................................................................................ 10 Impact of March 1, 2013, Sequester on FY2013 Funding ........11 Adequacy of Planned NSC, OPC, and FRC Procurement Quantities .............................................. 10 Potential Impact of Possible Late 2013/Early 2014 11 Impact of March 1, 2013, Sequester on FY2014FY2013 Funding ................................ 10 Adequacy of Planned NSC, OPC, and FRC Procurement Quantities ..................................... 1019 NSC Program: No Funding Requested in FY2014 for Long Lead Time Materials (LLTM) for Eighth Ship ....................................................................................................... 1920 FRC Program: FY2014 Request for Two (Rather than Six) Ships .......................................... 2021 FRC Program: Delays, Cost Growth, and Testing ................................................................... 2223 OPC Program: FY2014 Funding Request Less than Projected Under FY2013 Budget ......... 2425 OPC Program: Cost, Design, and Acquisition Strategy........................................................... 2425 2012 Testimony ................................................................................................................. 2526 2013 Testimony ................................................................................................................. 2627 September 2012 GAO Report ........................................................................................... 2829 Multiyear Procurement (MYP)................................................................................................ 3132 Alternative Force Mixes Equal in Cost to Program of Record ................................................ 3233 Information for Supporting Congressional Oversight of Procurement Programs ................... 3536 Legislative Activity for FY2014 .................................................................................................... 3738 Summary of Appropriations Action on FY2014 Acquisition Funding Request ...................... 3738 FY2014 DHS Appropriations Act (H.R. 2217) Division F of H.R. 3547/P.L. 113-76) ............................. 39 House.......................................................................................................... 38 House....................... 39 Senate ..................................................................................................................... 38 Senate ........... 42 Final Version ..................................................................................................................... 4246 Figures Figure 1. National Security Cutter ................................................................................................... 3 Figure 2. Offshore Patrol Cutter (Generic Conceptual Rendering) ................................................. 5 Figure 3. Fast Response Cutter ........................................................................................................ 8 Figure 4. Projected Mission Demands vs. Projected Capability/Performance .............................. 1314 Figure B-1. Budget Item Justification Sheet (Exhibit P-40) .......................................................... 4951 Figure B-2. Weapon System Cost Analysis Sheet (Exhibit P-5) ................................................... 5052 Figure B-3. Ship Production Schedule (Exhibit P-27)................................................................... 5153 Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress Tables Table 1. NSC Acquisition Funding, by Hull .................................................................................... 4 Table 2. FRC Acquisition Funding, by Hull .................................................................................... 89 Table 3. NSC, OPC, and FRC Funding in FY2013 and FY2014 Five-Year Capital Investment Plans (CIPs) ............................................................................................................... 9 10 Table 4. Program of Record Compared to Objective Fleet Mix .................................................... 1112 Table 5. POR Compared to FMAs 1 Through 4 ............................................................................ 12 Table 6. Force Mixes and Mission Performance Gaps .................................................................. 1213 Table 7. POR Compared to Objective Mixes in FMA Phases 1 and 2........................................... 1415 Table 8. Alternative Force Mixes Examined in DHS Cutter Study ............................................... 3334 Table 9. Summary of Appropriations Action on FY2014 Acquisition Funding Request............... 38 Table C-1. Navy Ship Force Structure Goal .................................................................................. 5254 Table D-1. Navy FY2014 Five-Year (FY2014-FY2018) Shipbuilding Plan ................................. 5355 Table E-1. Navy FY2014 30-Year (FY2014-FY2043) Shipbuilding Plan..................................... 5456 Table E-2. Projected Force Levels Resulting from FY2014 30-Year (FY2014-FY2043) Shipbuilding Plan ....................................................................................................................... 5557 Appendixes Appendix A. Findings and Recommendations of DHS Cutter Study ............................................ 4648 Appendix B. P-5, P-40, and P-27 Data Exhibits for Littoral Combat Ship (LCS) Program.......... 4850 Appendix C. Navy Ship Force Structure Objective ....................................................................... 5254 Appendix D. Navy FY2014 Five-Year Shipbuilding Plan............................................................. 5355 Appendix E. Navy FY2014 30-Year Shipbuilding Plan ................................................................ 5456 Contacts Author Contact Information........................................................................................................... 5658 Congressional Research Service Coast Guard Cutter Procurement: Background and Issues for Congress Introduction This report provides background information and potential oversight issues for Congress on the Coast Guard’s programs for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 58 Fast Response Cutters (FRCs). These 91 planned cutters are intended as replacements for 90 aging Coast Guard cutters and patrol craft. The Coast Guard began procuring NSCs and FRCs a few years ago, and the first few NSCs and FRCs are now in service. The Coast Guard plans to begin procuring OPCs within the next few years. The NSC, OPC, and FRC programs have a combined estimated acquisition cost of about $21.1 billion, and the Coast Guard’s proposed FY2014 budget requestsrequested a total of $716 million in acquisition funding for the three programs. The issue for Congress is whether to approve, reject, or modify the Coast Guard’s funding requests and acquisition strategies for the NSC, OPC, and FRC programs. Congress’s decisions on these three programs could substantially affect Coast Guard capabilities and funding requirements, and the U.S. shipbuilding industrial base. The NSC, OPC, and FRC programs have been subjects of congressional oversight for several years, and were previously covered in an earlier CRS report that is now archived.1 The Coast Guard’s plans for modernizing its fleet of polar icebreakers are covered in a separate CRS report.2 Background Older Ships to Be Replaced by NSCs, OPCs, and FRCs The 91 planned NSCs, OPCs, and FRCs are intended to replace 90 older Coast Guard ships—the service’s 12 high-endurance cutters (WHECs), 29 medium-endurance cutters (WMECs), and 49 110-foot patrol craft (WPBs).3 The Coast Guard’s 12 Hamilton (WHEC-715) class highendurance cutters entered service between 1967 and 1972.4 The Coast Guard’s 29 mediumendurance cutters include 13 Famous (WMEC-901) class ships that entered service between 1983 1 The earlier report was CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald O'Rourke. From the late 1990s until 2007, the Coast Guard’s efforts to acquire NSCs, OPCs, and FRCs were parts of a larger, integrated Coast Guard acquisition effort aimed at acquiring several new types of cutters and aircraft that was called the Integrated Deepwater System (IDS) program, or Deepwater for short. In 2007, the Coast Guard broke up the Deepwater effort into a series of individual cutter and aircraft acquisition programs, but continued to use the term Deepwater as a shorthand way of referring collectively to these now-separated programs. In its FY2012 budget submission, the Coast Guard stopped using the term Deepwater entirely as a way of referring to these programs. Congress, in acting on the Coast Guard’s proposed FY2012 budget, did not object to ending the use of the term Deepwater. Reflecting this development, CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress was archived in early 2012, following final congressional action on the FY2012 budget, and remains available to congressional readers as a source of historical reference information on Deepwater acquisition efforts. 2 CRS Report RL34391, Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress, by Ronald O'Rourke. 3 In the designations WHEC, WMEC, and WPB, W means Coast Guard ship, HEC stands for high-endurance cutter, MEC stands for medium-endurance cutter, and PB stands for patrol boat. 4 Hamilton-class cutters are 378 feet long and have a full load displacement of about 3,400 tons. Congressional Research Service 1 Coast Guard Cutter Procurement: Background and Issues for Congress and 1991,5 14 Reliance (WMEC-615) class ships that entered service between 1964 and 1969,6 and two one-of-a-kind cutters that originally entered service with the Navy in 1944 and 1971 and were later transferred to the Coast Guard.7 The Coast Guard’s 49 110-foot Island (WPB-1301) class patrol boats entered service between 1986 and 1992.8 Many of these 90 ships are manpower-intensive and increasingly expensive to maintain, and have features that in some cases are not optimal for performing their assigned missions. Some of them have already been removed from Coast Guard service: eight of the Island-class patrol boats were removed from service in 2007 following an unsuccessful effort to modernize and lengthen them to 123 feet; the one-of-a-kind cutter that originally entered service with the Navy in 1944 was decommissioned in 2011; and Hamilton-class cutters are being decommissioned as new NSCs enter service. A July 2012 Government Accountability Office (GAO) report discusses the generally poor physical condition and declining operational capacity of the Coast Guard’s older high-endurance cutters, medium-endurance cutters, and 110-foot patrol craft.9 Missions of NSCs, OPCs, and FRCs NSCs, OPCs, and FRCs, like the ships they are intended to replace, are to be multimission ships for routinely performing 7 of the Coast Guard’s 11 statutory missions, including • search and rescue (SAR); • drug interdiction; • migrant interdiction; • ports, waterways, and coastal security (PWCS); • protection of living marine resources; • other/general law enforcement; and • defense readiness operations.10 5 Famous class cutters are 270 feet long and have a full load displacement of about 1,800 tons. Reliance class cutters are 210 feet long and have a full load displacement of about 1,100 tons. 7 The two one-of-a-kind cutters are the Acushnet (WMEC-167), which originally entered service with the Navy in 1944, and the Alex Haley (WMEC-39), which originally entered service with the Navy in 1971. The Acushnet served in the Navy from until 1946, when it was transferred to the Coast Guard. The ship was about 214 feet long and had a displacement of about 1,700 tons. The Alex Haley served in the Navy until 1996. It was transferred to the Coast Guard in 1997, converted into a cutter, and re-entered service with the Coast Guard in 1999. It is 282 feet long and has a full load displacement of about 2,900 tons. 8 Island-class boats are 110 feet long and have a full load displacement of about 135 to 170 tons. 9 Government Accountability Office, Coast Guard[:]Legacy Vessels’ Declining Conditions Reinforce Need for More Realistic Operational Targets, GAO-12-741, July 2012, 71 pp. 10 The four statutory Coast Guard missions that are not to be routinely performed by NSCs, OPCs, and FRCs are marine safety, aids to navigation, marine environmental protection, and ice operations. These missions are performed primarily by other Coast Guard ships. The Coast Guard states, however, that “while [NSCs, OPCs, and FRCs] will not routinely conduct [the] Aids to Navigation, Marine Safety, or Marine Environmental Protection missions, they may periodically be called upon to support these missions (i.e., validate the position of an Aid to Navigation, transport personnel or serve as a Command and Control platform for a Marine Safety or Marine Environmental Response mission, etc.).” (Source: Coast Guard information paper provided to CRS on June 1, 2012.) 6 Congressional Research Service 2 Coast Guard Cutter Procurement: Background and Issues for Congress Smaller Coast Guard patrol craft and boats contribute to the performance of some of these seven missions close to shore. NSCs, OPCs, and FRCs perform them both close to shore and in the deepwater environment, which generally refers to waters more than 50 miles from shore. NSC Program National Security Cutters (Figure 1), also known as Legend (WMSL-750) class cutters,11 are the Coast Guard’s largest and most capable general-purpose cutters.12 The Coast Guard’s program of record (POR)—the service’s list, established in 2004, of planned procurement quantities for various new types of ships and aircraft—calls for procuring 8 NSCs as replacements for the service’s 12 Hamilton class high-endurance cutters. Figure 1. National Security Cutter Source: U.S. Coast Guard photo accessed May 2, 2012, at http://www.flickr.com/photos/coast_guard/ 5617034780/sizes/l/in/set-72157629650794895/. Although the NSC program’s official total acquisition cost estimate is $4.749 billion, or an average of about $594 million per ship,13 the Coast Guard more recently estimated the combined 11 In the designation WMSL, W means Coast Guard ship and MSL stands for maritime security cutter, large. NSCs are being named for legendary Coast Guard personnel. 12 The Coast Guard’s three polar icebreakers are much larger than NSCs, but are designed for a more specialized role of operations in polar waters. 13 Department of Homeland Security, United States Coast Guard, Fiscal Year 2013 Congressional Justification, p. CGAC&I-12 (pdf page 166 of 400). Congressional Research Service 3 Coast Guard Cutter Procurement: Background and Issues for Congress procurement cost of the eight ships at $5.474 billion, or an average of about $684 million per ship, assuming the seventh and eighth ships were funded in FY2014 and FY2015, respectively.14 The first three NSCs are now in service, the fourth, fifth, and sixth and fifth are under construction, and the sixth was funded in FY2013long lead time materials (LLTM) for the seventh are being procured. NSCs are larger and technologically more advanced than Hamilton-class cutters.15 The Coast Guard states that Of the Coast Guard’s white-hull patrol cutter fleet, the NSC is the largest and most technologically sophisticated in the Coast Guard. Each NSC is capable of operating in the most demanding open ocean environments, including the hazardous fisheries of the North Pacific and the vast approaches of the Southern Pacific where much of the American narcotics traffic occurs. With robust Command, Control, Communication, Computers, Intelligence, Surveillance and Reconnaissance (C4ISR) equipment, stern boat launch and aviation facilities, as well as long-endurance station keeping, the NSCs are afloat operational-level headquarters for complex law enforcement and national security missions involving multiple Coast Guard and partner agency participation.16 NSCs are built by Ingalls Shipbuilding of Pascagoula, MS, a shipyard that forms part of Huntington Ingalls Industries (HII). Table 1 summarizes acquisition funding for the first six NSCs. Table 1. NSC Acquisition Funding, by Hull Millions of then-year dollars, rounded to nearest million Hull Fiscal years funded Total acquisition funding (millions) Production contract award date Entered service 1 FY02-FY09 and FY15 $701 FY04 August 2008 2 FY04-FY09 and FY15 $528 FY05 May 2010 March 2012 3 FY04-FY09 $551 FY07 4 FY04-FY10, FY13, FY15-FY16 $690 FY11 (1st Quarter) 5 FY10-FY11 $697 FY11 (4th Quarter) 6 FY12 and FY13 $735a Source: Coast Guard e-mail to CRS, December 9, 2011, and FY2013 Coast Guard budget submission. a. Includes $77 million in FY2012 and $658 million requested for FY2013. The FY2013 funding request for the NSC program also includes $25 million for post-production activities for the fourth NSC to replace $25 million in funding for post-production activities provided in FY2010. The Coast Guard’s proposed FY2014 budget requestsrequested $616 million in acquisition funding for the the seventh NSC; it does not request any funding for long lead time materials (LLTM) for the eighth eighth NSC, which is scheduled to be procured in FY2015. 14 Source: Coast Guard information paper on NSC procurement costs provided to CRS on May 14, 2012. The NSC design is 418 feet long and has a full load displacement of about 4,500 tons. The displacement of the NSC design is about equal to that of Navy’s Oliver Hazard Perry (FFG-7) class frigates, which are 453 feet long and have a full load displacement of about 4,200 tons. 16 U.S. Coast Guard description of the NSC, accessed April 26, 2013, at http://www.uscg.mil/acquisition/nsc/ features.asp. 15 Congressional Research Service 4 Coast Guard Cutter Procurement: Background and Issues for Congress OPC Program Offshore Patrol Cutters (Figure 2) are to be smaller, less expensive, and in some respects less capable than NSCs. The Coast Guard’s POR calls for procuring 25 OPCs as replacements for the service’s 29 medium-endurance cutters. Under the Coast Guard’s FY2013FY2014 five-year (FY2013FY2017FY2014FY2018) capital investment plan, the first OPC wasis to be procured in FY2017. Figure 2. Offshore Patrol Cutter (Generic Conceptual Rendering) Source: U.S. Coast Guard generic conceptual rendering accessed May 3, 2012, at http://www.uscg.mil/hq/cg9/ opc/default.asp. The Coast Guard estimates the OPC program’s total acquisition cost at $12.101 billion, or an average of about $484 million per ship. These figures reflect a revised OPC program baseline that was approved in April 2012; they represent a 49% increase over the previous figures of $8.098 billion and $324 million, respectively.17 A September 2012 GAO report states that The initial Deepwater baseline included an $8 billion estimate for the Offshore Patrol Cutter program. However, program officials stated they did not have good data for how the lead systems integrator for the Deepwater program generated the original estimate, and that the current estimate approved by DHS in April 2012—with a threshold of approximately $12 billion—is higher likely because the original estimate was developed before the program requirements were established. Program officials also cited delays in the program, and the corresponding inflation associated with those delays, as additional reasons for the cost increase. Even though the Coast Guard used the original 2007 Deepwater Baseline estimate of $8 billion to characterize the expected cost of the program multiple times to Congress, it 17 Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, p. 13 (Figure 13). Congressional Research Service 5 Coast Guard Cutter Procurement: Background and Issues for Congress now characterizes the revised acquisition program baseline as the initial cost estimate for the program.18 The Coast Guard’s Request for Proposal (RFP) for the program, released on September 25, 2012, establishes an affordability requirement for the program of an average unit price of $310 million per ship, or less, in then-year dollars (i.e., dollars that are not adjusted for inflation) for ships 4 through 9 in the program.19 This figure represents the shipbuilder’s portion of the total cost of the ship; it does not include the cost of government-furnished equipment (GFE) on the ship,20 or other program costs—such as those for program management, system integration, and logistics— that contribute to the above-cited figure of $484 million per ship.21 The service states that OPCs will complement the Coast Guard’s current and future fleet to extend the service’s operational capabilities. The OPC will replace the service’s 210-foot and 270-foot Medium Endurance Cutters. It will feature increased range and endurance, powerful weapons, a larger flight deck, and improved command, control, communications, computers, intelligence, surveillance and reconnaissance (C4ISR) equipment. The OPC will accommodate aircraft and small boat operations in all weather.22 At least eight shipyards have expressed interest in the program.23 The Coast Guard’s acquisition strategy for the first 9 to 11 ships in the program is as follows: The OPC procurement shall implement a two-phase down select strategy. Phase I entails a full and open competition for Preliminary and Contract Design (P&CD) awarded to a maximum of three offerors. The Coast Guard intends to competitively award the Phase I contract in Fiscal Year (FY) 2013. P&CD will culminate in a Contract Design Review (KDR). After KDR, the three contractors will submit proposals which will result in a down selection to one contractor to continue with Phase II. (h) Phase II award is planned for FY.... Phase II’s down selection will be accomplished by exercising one option with a single contractor for Detail Design (DD) with additional options for Long Lead Time Materials, lead ship and eight to ten follow ships. DD will start after option exercise and be complete upon delivery of the first ship. The contractor will present the OPC design at the Initial Critical Design Reviews (ICDR) and Final Critical Design Review (FCDR) followed by a Production Readiness Review (PRR). During Phase II contract performance, the contractor will be encouraged to submit a fixed price proposal (before construction begins on the Hull #6) for option Hulls #6 through #11 (LRIP 2). If the priced effort is deemed fair and reasonable the contractor shall be eligible for Hulls #10 and #11. If not, the contract will continue with the FPI structure and the contract will end with Hull #9.23 At least eight shipyards expressed interest in the program. The firms were: 18 Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, p. 15. 19 Source: Section C.5 of the RFP, accessed October 31, 2012, at http://www.uscg.mil/ACQUISITION/newsroom/ updates/opc092512.asp. 20 GFE is equipment that the government procures and then delivers to the shipyard for installation on the ship. 21 Source: Coast Guard emails to CRS dated June 25, 2013. 22 Coast Guard fact sheet on the OPC accessed April 26, 2013, at http://www.uscg.mil/acquisition/opc/pdf/opc.pdf. 23 The firms are General Dynamics Bath Iron Works (GD/BIW) of Bath, ME; Bollinger Shipyards of St. Rose, LA; Source: Section C.1 of the RFP, accessed March 26, 2013, at http://www.uscg.mil/ACQUISITION/newsroom/ updates/opc092512.asp. Congressional Research Service 6 Coast Guard Cutter Procurement: Background and Issues for Congress • Bollinger Shipyards of Lockport, LA; • Eastern Shipbuilding Group of Panama City, FL; • General Dynamics Bath Iron Works (GD/BIW) of Bath, ME; • Huntington Ingalls Industries (HII) of Pascagoula, MS; Marinette • Marinette Marine Corporation of Marinette, WS; General Dynamics National Steel and Shipbuilding Company (GD/NASSCO) of of San Diego, CA; Vigor Shipyards of Seattle, WA; and VT Halter Marine of Pascagoula, MS. Source: U. S. Coast Guard Offshore Patrol Cutter (OPC) List of Interested Contractors Updated July 2012, accessed online October 23, 2012, at http://www.uscg.mil/ACQUISITION/opc/pdf/companiesinterested.pdf; and Kevin Brancato and Anne Laurent, Coast Guard’s $12 Billion Cutter Competition Spurs Eight Shipyards to Dive In, Bloomberg Government Study, November 8, 2012, 6 pp. The Coast Guard document states that these firms “expressed interest in the Offshore Patrol Cutter acquisition and have agreed to their names provided on the Coast Guard website.” The Bloomberg Government Study states that “Marinette Marine, owned by Italian shipbuilder Fincantieri, may build its bid based on its version of the Littoral Combat Ship for the U.S. Navy. Vigor Industrial will propose a derivative of a commercial curved-hull design by Norwegian ship maker Ulstein. VT Halter will use Paris-based DCNS as design partner.” See also Stew Magnuson, “New Coast Guard Cutter Sparks Fierce Competition Among Shipbuilders,” National Defense (www.nationaldefensemagazine.org), April 2013, accessed March 26, 2013, at http://www.nationaldefensemagazine.org/archive/2013/April/Pages/ NewCoastGuardCutterSparksFierceCompetitionAmongShipbuilders.aspx. Congressional Research Service 6 Coast Guard Cutter Procurement: Background and Issues for Congress (h) Phase II award is planned for FY.... Phase II’s down selection will be accomplished by exercising one option with a single contractor for Detail Design (DD) with additional options for Long Lead Time Materials, lead ship and eight to ten follow ships. DD will start after option exercise and be complete upon delivery of the first ship. The contractor will present the OPC design at the Initial Critical Design Reviews (ICDR) and Final Critical Design Review (FCDR) followed by a Production Readiness Review (PRR). During Phase II contract performance, the contractor will be encouraged to submit a fixed price proposal (before construction begins on the Hull #6) for option Hulls #6 through #11 (LRIP 2). If the priced effort is deemed fair and reasonable the contractor shall be eligible for Hulls #10 and #11. If not, the contract will continue with the FPI structure and the contract will end with Hull #9.24 The Coast Guard’s proposed FY2014 budget requests24 On February 11, 2014, the Coast Guard announced that it had awarded Phase I Preliminary and Contract Design (P&CD) contracts to Bollinger, Eastern, and GD/BIW. A February 11, 2014, Coast Guard news release on the award stated: The U.S. Coast Guard today awarded three firm fixed-price contracts for preliminary and contract design (P&CD) for the Offshore Patrol Cutter (OPC) acquisition project. The contracts were awarded to Bollinger Shipyards Lockport LLC (Lockport, La.), Eastern Shipbuilding Group Inc. (Panama City, Fla.), and General Dynamics, Bath Iron Works (Bath, Maine). The total value of the award is approximately $65 million. Awarding multiple design contracts ensures that competition is continued through to a potential down-select for detailed design and construction, establishes a fixed-price environment for the remainder of the contract, and incorporates a strategy to maximize affordability. This strategy was developed by analyzing lessons learned from other major government shipbuilding programs and through collaboration with industry on how to best design and produce the most affordable OPC.... The Coast Guard issued the P&CD Request for Proposal (RFP) Sept. 25, 2012. Responses were received in January 2013, and the Coast Guard conducted a thorough evaluation of proposals based on technical, management, past performance and price factors. To support the effort to acquire an affordable OPC, the Coast Guard engaged industry prior to RFP release through industry day events, one-on-one meetings and providing opportunities for potential offerors to review and comment on OPC draft technical packages, specifications and solicitation language.25 24 Source: U. S. Coast Guard Offshore Patrol Cutter (OPC) List of Interested Contractors Updated July 2012, accessed online October 23, 2012, at http://www.uscg.mil/ACQUISITION/opc/pdf/companiesinterested.pdf; and Kevin Brancato and Anne Laurent, Coast Guard’s $12 Billion Cutter Competition Spurs Eight Shipyards to Dive In, Bloomberg Government Study, November 8, 2012, 6 pp. The Coast Guard document states that these firms “expressed interest in the Offshore Patrol Cutter acquisition and have agreed to their names provided on the Coast Guard website.” See also Stew Magnuson, “New Coast Guard Cutter Sparks Fierce Competition Among Shipbuilders,” National Defense (www.nationaldefensemagazine.org), April 2013, accessed March 26, 2013, at http://www.nationaldefensemagazine.org/archive/2013/April/Pages/ NewCoastGuardCutterSparksFierceCompetitionAmongShipbuilders.aspx. 25 U.S. Coast Guard news release entitled, “Acquisition Update: U.S. Coast Guard Awards Three Contracts for Offshore Patrol Cutter Preliminary and Contract Design,” February 11, 2014, accessed February 14, 2014, at http://www.uscg.mil/hq/cg9/newsroom/updates/opc021114.asp. Congressional Research Service 7 Coast Guard Cutter Procurement: Background and Issues for Congress A February 26, 2014, press report states that HII on February 25 filed a protest of the Coast Guard’s February 11 award decision, and that GAO’s ruling on the protest is expected in early June.26 The Coast Guard’s proposed FY2014 budget requested $25 million in acquisition funding for the OPC program, to be used for technical and project management. FRC Program Fast Response Cutters (Figure 3), also called Sentinel (WPC-1101) class patrol boats, are considerably smaller and less expensive than OPCs, but are larger than the Coast Guard’s older patrol boats.2527 The Coast Guard’s POR calls for procuring 58 FRCs as replacements for the service’s 49 Island-class patrol boats. Figure 3. Fast Response Cutter (With an older Island-class patrol boat behind) Source: U.S. Coast Guard photo accessed May 4, 2012, at http://www.flickr.com/photos/coast_guard/ 6871815460/sizes/l/in/set-72157629286167596/. 26 27 Christopher P. Cavas, “Ingalls Protesting US Coast Guard Cutter Contract,” DefenseNews.com, February 26, 2014. FRCs are 154 feet long and have a full load displacement of 353 tons. Congressional Research Service 8 Coast Guard Cutter Procurement: Background and Issues for Congress The Coast Guard states that The planned fleet of FRCs will conduct primarily the same missions as the 110’ patrol boats being replaced. In addition, the FRC will have several increased capabilities enhancing overall mission execution. The FRC is designed for rapid response, with approximately a 28 knot speed capability, and will typically operate in the coastal zones. Examples of missions that FRCs will complete include SAR, Migrant Interdiction, Drug Interdiction and Ports Waterways and Coastal Security. FRCs will provide enhanced capabilities over the 110’s including improved C4ISR capability and interoperability; stern launch and recovery (up through sea state 4) of a 40 knot, Over-the-Horizon, 7m cutter boat; a remote operated, gyro stabilized MK38 Mod 2, 25mm main gun; improved sea keeping; and enhanced crew habitability.2628 The Coast Guard estimates the FRC program’s total acquisition cost at $4.243 billion, or an average of about $73 million per boat.2729 A total of 18 FRCs24 have been funded through FY2012. The first entered service on April 14, 2012, and a total of six had been delivered as of May 18, 2013. FRCs are currently built by Bollinger Shipyards of Lockport, LA. Bollinger’s contract with the Coast Guard originally included options to build up to 34 FRCs, but some of the options were not 24 Source: Section C.1 of the RFP, accessed March 26, 2013, at http://www.uscg.mil/ACQUISITION/newsroom/ updates/opc092512.asp. 25 FRCs are 154 feet long and have a full load displacement of 353 tons. 26 Department of Homeland Security, United States Coast Guard, Fiscal Year 2013 Congressional Justification, p. CGAC&I-28 (pdf page 182 of 400). 27 Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, p. 13 (Figure 13). Congressional Research Service 7 Coast Guard Cutter Procurement: Background and Issues for Congress FY2013. As of February 7, 2014, the first seven had been commissioned into service as of November 16, 2013. The eighth was delivered to the Coast Guard on December 10, 2013. On September 18, 2013, the FRC program received approval from DHS to enter full-rate production.30 On September 25, 2013, the Coast Guard exercised an option for six FRCs (numbers 19-24 in the program).31 FRCs are currently built by Bollinger Shipyards of Lockport, LA. Bollinger’s contract with the Coast Guard originally included options to build up to 34 FRCs, but some of the options were not fully exercised by the Coast Guard, so Bollinger’s contract can now cover up to 30 FRCs. The builder of the remaining 28 planned FRCs has not yet been determined. The Coast Guard holds the data rights for the Sentinel-class design and plans to hold a competition in 2015 for the contract to build the remaining boats in the class.28 Figure 3. Fast Response Cutter (With an older Island-class patrol boat behind) Source: U.S. Coast Guard photo accessed May 4, 2012, at http://www.flickr.com/photos/coast_guard/ 6871815460/sizes/l/in/set-72157629286167596/. 32 Table 2 summarizes acquisition funding for the first 18 FRCs. Table 2. FRC Acquisition Funding, by Hull Millions of then-year dollars, rounded to nearest million 28 Quantity Hulls Fiscal years funded Total acquisition funding (millions) Average unit cost (millions) 0 n/a FY07 and prior years $2 n/a 4 1 to 4 FY05, FY07, FY09 $267 $66.75 4 5 to 8 FY2010 $243 $60.75 4 9 to 12 FY2011 $240 $60.00 4a 13 to 16a FY2012 $358b $59.00b 28 Department of Homeland Security, United States Coast Guard, Fiscal Year 2013 Congressional Justification, p. CGAC&I-28 (pdf page 182 of 400). 29 Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, p. 13 (Figure 13). 30 “Acquisition Update: Sentinel-class Fast Response Cutter Project Achieves Acquisition Milestone,” September 18, 2013, accessed November 18, 2013, at http://www.uscg.mil/acquisition/newsroom/updates/frc092413.asp. 31 “Acquisition Update: Contract Option Exercised for Six More Fast Response Cutters,” September 25, 2013, accessed November 18, 2013, at http://www.uscg.mil/acquisition/newsroom/updates/frc092513.asp. 32 Mike McCarthy, “House Markup Would Avoid Slipping USCG’s New Cutters,” Defense Daily, May 15, 2012: 3. Congressional Research Service 89 Coast Guard Cutter Procurement: Background and Issues for Congress Source: Coast Guard e-mail to CRS, December 9, 2011, and FY2013 Coast Guard budget submission. a. The FY2012 budget funded the procurement of six boats (numbers 13 through 18). The Coast Guard’s FY2013 budget proposed deferring the procurement of boats 17 and 18 to FY2013, which would reduce the FY2012 figure to 4 boats (hulls 13 to 16). Under this proposal, of the $358 million provided for the program in FY2012, $95 million provided for boats 17 and 18 would be, in effect, transferred to FY2013. b. Includes $27 million for FRC reprocurement data and licensing package (RDLP) and $95 million to be used for procuring two additional FRCs (numbers 17 and 18) in FY2013. These two sums are excluded from the unit cost calculation. The Coast Guard’s proposed FY2014 budget requestsrequested $75 million in acquisition funding for two FRCs, associated contact line items, and project management costs. NSC, OPC, and FRC Funding in FY2013 Five-Year Capital Investment Plan Table 3 shows annual acquisition funding for the NSC, OPC, and FRC programs in the Coast Guard’s FY2013 and FY2014 Five Year Capital Investment Plans (CIPs). Table 3. NSC, OPC, and FRC Funding in FY2013 and FY2014 Five-Year Capital Investment Plans (CIPs) (millions of then-year dollars) FY2013 FY2014 FY2015 FY2016 FY2017 683a 0 0 0 0 616 710 38 0 +616 +710 +38 0 50 40 200b 530c FY14 CIP 25 65 200 530 Difference (common years) -25 +25 0 0 360 360 360 360 75 110 110 110 -285 -250 -250 -250 410 400 560 890 716 885 348 640 +306 +485 -212 -250 FY2018 NSC program FY13 CIP FY14 CIP Difference (common years) 45 OPC program FY13 CIP 30 430 FRC program FY13 CIP 139d FY14 CIP Difference (common years) 110 Total FY13 CIP FY14 CIP Difference (common years) 852 585 Source: FY2013 CIP, as shown in Department of Homeland Security, United States Coast Guard, Fiscal Year 2013 Congressional Justification, p. CG-AC&I-12 (pdf page 166 of 400); and FY2014 CIP, accessed May 13, 2013, at http://www.uscg.mil/posturestatement/docs/USCG_Capital%20Investment%20Plan_FY14-18.pdf. a. Includes $658 million to complete acquisition funding for the sixth NSC, and $25 million in post-production activities for the fourth NSC. Congressional Research Service 910 Coast Guard Cutter Procurement: Background and Issues for Congress b. Includes funding for detailed design and long-lead time materials for the first OPC. c. Includes funding to complete the acquisition cost of the first OPC. d. The Coast Guard’s FY2013 budget proposes to shift an additional $95 million in FY2012 funding to FY2013, resulting in a total of $234 million available to the FRC program in FY2013. Issues for Congress Impact of March 1, 2013, Sequester on FY2013 Funding One issue for Congress concerns the impact on NSC, OPC, and FRC programs of the March 1, 2013, sequester on FY2013 funding, particularly in terms of the Coast Guard’s ability to execute construction work on the sixth NSC and the FRCs that were funded in FY2013. Potential Impact of Possible Late 2013/Early 2014 Sequester on FY2014 Funding Another potential issue for Congress concerns the potential impact on the NSC, OPC, and FRC programs of a possible sequester on FY2014 funding that might occur in late 2013 or early 2014 under the terms of the Budget Control Act of 2011 (S. 365/P.L. 112-25 of August 2, 2011). Adequacy of Planned NSC, OPC, and FRC Procurement Quantities AnotherAdequacy of Planned NSC, OPC, and FRC Procurement Quantities One oversight issue for Congress concerns the adequacy of the Coast Guard’s planned NSC, OPC, and FRC procurement quantities. The POR’s planned force of 91 NSCs, OPCs, and FRCs is about equal in number to the Coast Guard’s legacy force of 90 high-endurance cutters, mediumendurance cutters, and 110-foot patrol craft. NSCs, OPCs, and FRCs, moreover, are to be individually more capable than the older ships they are to replace. Even so, Coast Guard studies have concluded that the planned total of 91 NSCs, OPCs, and FRCs would be considerably fewer ships than the number that would be needed to fully perform the service’s statutory missions in coming years, in part because Coast Guard mission demands are expected to be greater in coming years than they were in the past. CRS first testified about this issue in 2005.2933 The Coast Guard estimates that with the POR’s planned force of 91 NSCs, OPCs, and FRCs, the service would have capability or capacity gaps30gaps34 in 6 of its 11 statutory missions—search and rescue (SAR); defense readiness; counter-drug operations; ports, waterways, and coastal security (PWCS); protection of living marine resources (LMR); and alien migrant interdiction operations (AMIO). The Coast Guard judges that some of these gaps would be “high risk” or “very high risk.” 29 See Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the Senate Commerce, Science, and Transportation Committee, Subcommittee on Fisheries and the Coast Guard, Hearing on The Coast Guard’s Revised Deepwater Implementation Plan, June 21, 2005, pp. 1-5. 30 The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed. Congressional Research Service 10 Coast Guard Cutter Procurement: Background and Issues for Congress Public discussions of the POR frequently mention the substantial improvement that the POR force would represent over the legacy force. Only rarely, however, have these discussions explicitly acknowledged the extent to which the POR force would nevertheless be smaller in number than the force that would be required, by Coast Guard estimate, to fully perform the Coast Guard’s statutory missions in coming years. Discussions that focus on the POR’s improvement over the legacy force while omitting mention of the considerably larger number of cutters that would be required, by Coast Guard estimate, to fully perform the Coast Guard’s statutory missions in coming years could encourage audiences to conclude, contrary to Coast Guard estimates, that the POR’s planned force of 91 cutters would be capable of fully performing the Coast Guard’s statutory missions in coming years. In a study completed in December 2009 called the Fleet Mix Analysis (FMA) Phase 1, the Coast Guard calculated the size of the force that in its view would be needed to fully perform the service’s statutory missions in coming years. The study refers to this larger force as the objective 33 See Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the Senate Commerce, Science, and Transportation Committee, Subcommittee on Fisheries and the Coast Guard, Hearing on The Coast Guard’s Revised Deepwater Implementation Plan, June 21, 2005, pp. 1-5. 34 The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed. Congressional Research Service 11 Coast Guard Cutter Procurement: Background and Issues for Congress fleet mix. Table 4 compares planned numbers of NSCs, OPCs, and FRCs in the POR to those in the objective fleet mix. Table 4. Program of Record Compared to Objective Fleet Mix From Fleet Mix Analysis Phase 1 (2009) Ship type Program of Record (POR) Objective Fleet Mix compared to POR Objective Fleet Mix From FMA Phase 1 Number % NSC 8 9 +1 +13% OPC 25 57 +32 +128% FRC 58 91 +33 +57% Total 91 157 +66 +73% Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13. As can be seen in Table 4, the objective fleet mix includes 66 additional cutters, or about 73% more cutters than in the POR. Stated the other way around, the POR includes about 58% as many cutters as the objective fleet mix. As intermediate steps between the POR force and the objective fleet mix, FMA Phase 1 calculated three additional forces, called FMA-1, FMA-2, and FMA-3. (The objective fleet mix was then relabeled FMA-4.) Table 5 compares the POR to FMAs 1 through 4. Congressional Research Service 11 Coast Guard Cutter Procurement: Background and Issues for Congress Table 5. POR Compared to FMAs 1 Through 4 From Fleet Mix Analysis Phase 1 (2009) Ship type Program of Record (POR) FMA-1 FMA-2 FMA-3 FMA-4 (Objective Fleet Mix) NSC 8 9 9 9 9 OPC 25 32 43 50 57 FRC 58 63 75 80 91 Total 91 104 127 139 157 Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13. FMA-1 was calculated to address the mission gaps that the Coast Guard judged to be “very high risk.” FMA-2 was calculated to address both those gaps and additional gaps that the Coast Guard judged to be “high risk.” FMA-3 was calculated to address all those gaps, plus gaps that the Coast Guard judged to be “medium risk.” FMA-4—the objective fleet mix—was calculated to address all the foregoing gaps, plus the remaining gaps, which the Coast Guard judge to be “low risk” or “very low risk.” Table 6 shows the POR and FMAs 1 through 4 in terms of their mission performance gaps. Congressional Research Service 12 Coast Guard Cutter Procurement: Background and Issues for Congress Table 6. Force Mixes and Mission Performance Gaps From Fleet Mix Analysis Phase 1 (2009)—an X mark indicates a mission performance gap Risk levels of these performance gaps Program of Record (POR) Search and Rescue (SAR) capability Very high X Defense Readiness capacity Very high X Counter Drug capacity Very high X Ports, Waterways, and Coastal Security (PWCS) capacitya High X X Living Marine Resources (LMR) capability and capacitya High X X PWCS capacityb Medium X X X LMR capacityc Medium X X X Alien Migrant Interdiction Operations (AMIO) capacityd Low/very low X X X X PWCS capacitye Low/very low X X X X Missions with performance gaps FMA-1 FMA-2 FMA-3 FMA-4 (Objective Fleet Mix) [all gaps addressed] Source: Fleet Mix Analysis Phase 1, Executive Summary, page ES-11 through ES-13. Notes: In the first column, The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed. a. This gap occurs in the Southeast operating area (Coast Guard Districts 7 and 8) and the Western operating area (Districts 11, 13, and 14). Congressional Research Service 12 Coast Guard Cutter Procurement: Background and Issues for Congress b. This gap occurs in Alaska. c. This gap occurs in Alaska and in the Northeast operating area (Districts 1 and 5). d. This gap occurs in the Southeast and Western operating areas. e. This gap occurs in the Northeast operating area. Figure 4, taken from FMA Phase 1, depicts the overall mission capability/performance gap situation in graphic form. It appears to be conceptual rather than drawn to precise scale. The black line descending toward 0 by the year 2027 shows the declining capability and performance of the Coast Guard’s legacy assets as they gradually age out of the force. The purple line branching up from the black line shows the added capability from ships and aircraft to be procured under the POR, including the 91 planned NSCs, OPCs, and FRCs. The level of capability to be provided when the POR force is fully in place is the green line, labeled “2005 Mission Needs Statement.” As can be seen in the graph, this level of capability is substantially below a projection of Coast Guard mission demands made after the terrorist attacks of September 11, 2001 (the red line, labeled “Post-9/11 CG Mission Demands”), and even further below a Coast Guard projection of future mission demands (the top dashed line, labeled “Future Mission Demands”). The dashed blue lines show future capability levels that would result from reducing planned procurement quantities in the POR or executing the POR over a longer time period than originally planned. Congressional Research Service 13 Coast Guard Cutter Procurement: Background and Issues for Congress Figure 4. Projected Mission Demands vs. Projected Capability/Performance From Fleet Mix Analysis Phase 1, Executive Summary Source: Fleet Mix Analysis Phase 1, Executive Summary, Figure ES-1 on p. ES-2. FMA Phase 1 was a fiscally unconstrained study, meaning that the larger force mixes shown in Table 5 were calculated primarily on the basis of their capability for performing missions, rather than their potential acquisition or life-cycle operation and support (O&S) costs. Although the FMA Phase 1 was completed in December 2009, the figures shown in Table 5 were generally not included in public discussions of the Coast Guard’s future force structure needs Congressional Research Service 13 Coast Guard Cutter Procurement: Background and Issues for Congress until April 2011, when GAO presented them in testimony.3135 GAO again presented them in a July 2011 report.3236 The Coast Guard completed a follow-on study, called Fleet Mix Analysis (FMA) Phase 2, in May 2011. Among other things, FMA Phase 2 includes a revised and updated objective fleet mix called the refined objective mix. Table 7 compares the POR to the objective fleet mix from FMA Phase 1 and the refined objective mix from FMA Phase 2. 35 Government Accountability Office, Coast Guard[:]Observations on Acquisition Management and Efforts to Reassess the Deepwater Program, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of John P. Hutton, Director Acquisition and Sourcing Management, GAO-11-535T, April 13, 2011, p. 10. 36 Government Accountability Office, Coast Guard[:]Action Needed As Approved Deepwater Program Remains Unachievable, GAO-11-743, July 2011, p. 46. Congressional Research Service 14 Coast Guard Cutter Procurement: Background and Issues for Congress Table 7. POR Compared to Objective Mixes in FMA Phases 1 and 2 From Fleet Mix Analysis Phase 1 (2009) and Phase 2 (2011) Ship type Program of Record (POR) Objective Fleet Mix from FMA Phase 1 Refined Objective Mix from FMA Phase 2 NSC 8 9 9 OPC 25 57 49 FRC 58 91 91 Total 91 157 149 Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13, and Fleet Mix Analysis Phase 2, Table ES-2 on p. iv. As can be seen in Table 7, compared to the objective fleet mix from FMA Phase 1, the refined objective mix from FMA Phase 2 includes 49 OPCs rather than 57. The refined objective mix includes 58 additional cutters, or about 64% more cutters than in the POR. Stated the other way around, the POR includes about 61% as many cutters as the refined objective mix. Compared to the POR, the larger force mixes shown in Table 5 and Table 7 would be more expensive to procure, operate, and support than the POR force. Using the average NSC, OPC, and FRC procurement cost figures presented earlier (see “Background”), procuring the 58 additional cutters in the Refined Objective Mix from FMA Phase 2 might cost an additional $10.7 billion, of which most (about $7.8 billion) would be for the 24 additional FRCs. (The actual cost would depend on numerous factors, such as annual procurement rates.) O&S costs for these 58 additional cutters over their life cycles (including crew costs and periodic ship maintenance costs) would require billions of additional dollars.3337 The larger force mixes in the FMA Phase 1 and 2 studies, moreover, include not only increased numbers of cutters, but also increased numbers of Coast Guard aircraft. In the FMA Phase 1 study, for example, the objective fleet mix included 479 aircraft—93% more than the 248 aircraft 31 Government Accountability Office, Coast Guard[:]Observations on Acquisition Management and Efforts to Reassess the Deepwater Program, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of John P. Hutton, Director Acquisition and Sourcing Management, GAO-11-535T, April 13, 2011, p. 10. 32 Government Accountability Office, Coast Guard[:]Action Needed As Approved Deepwater Program Remains Unachievable, GAO-11-743, July 2011, p. 46. 33 The FMA Phase 1 and Phase 2 studies present acquisition and life-cycle ownership cost calculations for force mixes that include not only larger numbers of NSC, OPCs, and FRCs, but corresponding larger numbers of Coast Guard aircraft. Congressional Research Service 14 Coast Guard Cutter Procurement: Background and Issues for Congress in the POR mix. A decision to procure larger numbers of cutters like those shown in Table 5 and Table 7 might thus also imply a decision to procure, operate, and support larger numbers of Coast Guard aircraft, which would require billions of additional dollars. The FMA Phase 1 study estimated the procurement cost of the objective fleet mix of 157 cutters and 479 aircraft at $61 billion to $67 billion in constant FY2009 dollars, or about 66% more than the procurement cost of $37 billion to $40 billion in constant FY2009 dollars estimated for the POR mix of 91 cutters and 248 aircraft. The study estimated the total ownership cost (i.e., procurement plus life-cycle O&S cost) of the objective fleet mix of cutters and aircraft at $201 billion to $208 billion in constant FY2009 dollars, or about 53% more than the total ownership cost of $132 billion to $136 billion in constant FY2009 dollars estimated for POR mix of cutters and aircraft.34 38 37 The FMA Phase 1 and Phase 2 studies present acquisition and life-cycle ownership cost calculations for force mixes that include not only larger numbers of NSC, OPCs, and FRCs, but corresponding larger numbers of Coast Guard aircraft. 38 Fleet Mix Analysis Phase 1, Executive Summary, Table ES-11 on page ES-19, and Table ES-10 on page ES-18. The life-cycle O&S cost was calculated through 2050. Congressional Research Service 15 Coast Guard Cutter Procurement: Background and Issues for Congress The POR was originally defined in 2004 as the optimal mix of assets that could be acquired for a total estimated acquisition cost of about $24 billion, and the $24 billion figure is often referenced as a baseline in discussing Coast Guard plans for acquiring new deepwater-capable ships and aircraft. GAO’s July 2011 report, for example, notes that the total estimated acquisition cost of the POR has grown to as much as $29.3 billion, or about $5 billion more than the original estimate of $24.2 billion, and that there could be additional cost growth beyond that figure.3539 GAO has expressed strong doubts, given growth in the estimated acquisition cost of the POR and the amounts of acquisition funding that the Coast Guard has received in recent years, about the Coast Guard’s ability to afford the POR, let alone any larger force mix, and has recommended in its July 2011 report and subsequent work that the Coast Guard instead examine force mixes that are smaller than the POR.3640 Force mixes that are smaller than the POR might lead to overall capability levels similar to those shown by the dashed blue lines in Figure 4, and mission performance gaps that are greater in magnitude than those indicated for the POR force in Table 6. At a March 7, 2012, hearing before the Oceans, Atmosphere, Fisheries, and Coast Guard subcommittees of the Senate Commerce, Science, and Transportation Committee, Admiral Robert J. Papp, the Commandant of the Coast Guard, in commenting on GAO’s July 2011 report, stated in part: And I think part of the GAO report as I read it was also saying maybe we need to recalculate getting fewer ships or whatever else. But what I don’t have is people taking—giving us fewer missions. Our missions continue to increase so I remain committed to the original baseline of the eight national security cutters, the 25 OPCs and others [other systems] as they are in the projects [sic: POR?].3741 Similarly, in commenting on a draft version of a September 2012 GAO report, the Coast Guard stated in part: 34 Fleet Mix Analysis Phase 1, Executive Summary, Table ES-11 on page ES-19, and Table ES-10 on page ES-18. The life-cycle O&S cost was calculated through 2050. 35 The assets required to meet Coast Guard statutorily required missions do not change on the basis of budgetary constraints. While changes in the fiscal environment may impact the rate and efficiency at which the Coast Guard can acquire new cutters, aircraft, boats and C4ISR systems to replace aging and failing equipment, it does not reduce or otherwise change the needs of the Service.42 The September 2012 GAO report refers multiple times to a need for the Coast Guard, in managing its acquisition programs, to work within “realistic fiscal constraints” and “expected funding levels,” which the report appears to define as an amount of acquisition funding level similar to the Coast Guard’s FY2013 request and to the amounts that the Coast Guard received in 39 Government Accountability Office, Coast Guard[:]Action Needed As Approved Deepwater Program Remains Unachievable, GAO-11-743, July 2011, summary page. 3640 See, for example, Government Accountability Office, Coast Guard[:]Action Needed As Approved Deepwater Program Remains Unachievable, GAO-11-743, July 2011, p. 46; and Government Accountability Office, Observations on the Coast Guard’s and the Department of Homeland Security’s Fleet Studies, GAO-12-751R, May 31, 2012. 37 Source: Transcript of hearing. Congressional Research Service 15 Coast Guard Cutter Procurement: Background and Issues for Congress The assets required to meet Coast Guard statutorily required missions do not change on the basis of budgetary constraints. While changes in the fiscal environment may impact the rate and efficiency at which the Coast Guard can acquire new cutters, aircraft, boats and C4ISR systems to replace aging and failing equipment, it does not reduce or otherwise change the needs of the Service.38 The September 2012 GAO report refers multiple times to a need for the Coast Guard, in managing its acquisition programs, to work within “realistic fiscal constraints” and “expected funding levels,” which the report appears to define as an amount of acquisition funding level similar to the Coast Guard’s FY2013 request and to the amounts that the Coast Guard received in the five years prior to FY2013.3941 Source: Transcript of hearing. 42 Letter dated September 13, 2012, from Jim H. Crumpacker, Director, [DHS] Departmental GAO-OIG Liaison Office, to John P. Hutton, Director, Acquisition Sourcing Management, U.S. Government Accountability Office, as reprinted in Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, p. 53. Congressional Research Service 16 Coast Guard Cutter Procurement: Background and Issues for Congress the five years prior to FY2013.43 Although the annual amounts of acquisition funding that the Coast Guard has received in recent years are one potential guide to what Coast Guard acquisition funding levels might or should be in coming years, there may be other potential guides. For example, one could envision potential guides that focus on whether Coast Guard funding for ship acquisition and sustainment is commensurate with Coast Guard funding for the personnel that in many cases will operate the ships. Observations that might be made in connection with this example include the following: • The Coast Guard has about 12.9% as many active-duty personnel as the Navy.4044 If the amount of funding for surface ship acquisition and sustainment in the Coast Guard’s budget were equivalent to 12.9% of the amount of funding in the Navy’s shipbuilding account, it would be about $1.8 billion per year, or about 142% more than the $743.0 million that the Coast Guard is requesting for FY2014 for surface ship acquisition and sustainment programs.4145 • Funding in the Navy’s shipbuilding account is equivalent to about 51% of the Navy’s funding for active-duty personnel.4246 If Coast Guard funding for surface ship acquisition and sustainment were equivalent to 51% of Coast Guard funding for military pay and allowances, it would be about $1.7 billion per year.4347 It is not clear whether either of the two above observations would be appropriate as guides for determining appropriate levels of funding for Coast Guard surface ship acquisition and sustainment in coming years, or more appropriate than other guides. But it might also be argued that it is not clear that recent Coast Guard acquisition funding levels are the sole or most appropriate guide for determining appropriate levels of such funding in coming years, particularly since the Coast Guard has entered a period where it is seeking to replace multiple classes of 38 Letter dated September 13, 2012, from Jim H. Crumpacker, Director, [DHS] Departmental GAO-OIG Liaison Office, to John P. Hutton, Director, Acquisition Sourcing Management, U.S. Government Accountability Office, as reprinted in Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, p. 53. 39assets. Although prior-year funding levels are often used in federal budgeting to determine what might be a realistic funding level for a program area for coming years, it might also be argued that a sole reliance on such a standard could short-circuit the policymaking process and limit options available to congressional (and executive branch) policymakers by in effect ruling out the option of deciding, as a matter of policy, that a program area is a high-enough priority that funding for it should be increased above prior-year levels, even while overall federal funding remains constrained. Supporters of this perspective might argue that what constitutes a realistic level of funding in coming years for a given program area is a policy question for congressional (and executive branch) policymakers to decide, and that an unvarying approach of basing futureyear funding for various program areas on their prior-year funding levels would hamper the ability of the congressional (and executive branch) policymakers to alter the composition of the federal budget over time to meet changing federal needs. 43 Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, p. 22-23, including Figure 7 on p. 23. 4044 The Coast Guard for FY2014 appears to be requesting an active-duty end strength—the number of active-duty military personnel—of 41,594 (measured by the Coast Guard in full-time equivalent [FTE] positions); the Navy for FY2014 is requesting an active-duty end strength of 323,600. 4145 The Navy’s proposed FY2014 budget requests $14,078 million for the Shipbuilding and Conversion, Navy (SCN) appropriation account. 4246 The Navy’s proposed FY2014 budget requests $27,824 million for the Military Personnel, Navy (MPN) appropriation account. 4347 The Coast Guard’s proposed FY2014 budget requests $3,425.3 million for military pay and allowances. Congressional Research Service 16 Coast Guard Cutter Procurement: Background and Issues for Congress assets. Although prior-year funding levels are often used in federal budgeting to determine what might be a realistic funding level for a program area for coming years, it might also be argued that a sole reliance on such a standard could short-circuit the policymaking process and limit options available to congressional (and executive branch) policymakers by in effect ruling out the option of deciding, as a matter of policy, that a program area is a high-enough priority that funding for it should be increased above prior-year levels, even while overall federal funding remains constrained. Supporters of this perspective might argue that what constitutes a realistic level of funding in coming years for a given program area is a policy question for congressional (and executive branch) policymakers to decide, and that an unvarying approach of basing futureyear funding for various program areas on their prior-year funding levels would hamper the ability of the congressional (and executive branch) policymakers to alter the composition of the federal budget over time to meet changing federal needs. 17 Coast Guard Cutter Procurement: Background and Issues for Congress At an October 4, 2011, hearing on the Coast Guard’s major acquisition programs before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, the following exchange occurred: REPRESENATIVE FRANK LOBIONDO: Can you give us your take on what percentage of value must be invested each year to maintain current levels of effort and to allow the Coast Guard to fully carry out its missions? ADMIRAL ROBERT J. PAPP, COMMANDANT OF THE COAST GUARD: I think I can, Mr. Chairman. Actually, in discussions and looking at our budget—and I’ll give you rough numbers here, what we do now is we have to live within the constraints that we’ve been averaging about $1.4 billion in acquisition money each year. If you look at our complete portfolio, the things that we’d like to do, when you look at the shore infrastructure that needs to be taken care of, when you look at renovating our smaller icebreakers and other ships and aircraft that we have, we’ve done some rough estimates that it would really take close to about $2.5 billion a year, if we were to do all the things that we would like to do to sustain our capital plant. So I’m just like any other head of any other agency here, as that the end of the day, we’re given a top line and we have to make choices and tradeoffs and basically, my tradeoffs boil down to sustaining frontline operations balancing that, we’re trying to recapitalize the Coast Guard and there’s where the break is and where we have to define our spending.4448 An April 18, 2012, blog entry stated: If the Coast Guard capital expenditure budget remains unchanged at less than $1.5 billion annually in the coming years, it will result in a service in possession of only 70 percent of the assets it possesses today, said Coast Guard Rear Adm. Mark Butt. Butt, who spoke April 17 [2012] at [a] panel [discussion] during the Navy League Sea Air Space conference in National Harbor, Md., echoed Coast Guard Commandant Robert Papp in stating that the service really needs around $2.5 billion annually for procurement.45 44 Source: Transcript of hearing. David Perera, “The Coast Guard Is Shrinking,” FierceHomelandSecurity.com, April 18, 2012, accessed July 20, (continued...) 45 Congressional Research Service 17 Coast Guard Cutter Procurement: Background and Issues for Congress At a May 9, 2012, hearing on the Coast Guard’s proposed FY2013 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified, “I’ve gone on record saying that I think the Coast Guard needs closer to $2 billion dollars a year [in acquisition funding] to recapitalize—[to] do proper recapitalization.”46 49 At a May 9, 2012, hearing on the Coast Guard’s proposed FY2013 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified, “I’ve gone on record saying that I think the Coast Guard needs closer to $2 billion dollars a year [in acquisition funding] to recapitalize—[to] do proper recapitalization.”50 48 Source: Transcript of hearing. David Perera, “The Coast Guard Is Shrinking,” FierceHomelandSecurity.com, April 18, 2012, accessed July 20, 2012, at http://www.fiercehomelandsecurity.com/story/coast-guard-shrinking/2012-04-18. 50 Source: transcript of hearing. Papp may have been referring to remarks he made to the press before giving his annual state of the Coast Guard speech on February 23, 2012, in which reportedly stated that the Coast Guard would require about $2 billion per year in acquisition funding to fully replace its current assets. (See Adam Benson, “Coast Guard Cutbacks Will Cost 1,000 Jobs,” Norwich Bulletin, February 23, 2012, accessed May 31, 2012, at http://www.norwichbulletin.com/news/x1138492141/Coast-Guard-cutbacks-will-cost-1-000-jobs#axzz1wSDAFCzX. See also “Coast Guard Leader Calls For More Ships,” MilitaryFeed.com, February 24, 2012, accessed May 31, 2012, at http://militaryfeed.com/coast-guard-leader-calls-for-more-ships-5/; Associated Press, “Coast Guard Commandant Calls for New Ships,” TheLog.com, March 10, 2012, accessed May 31, 2012, at http://www.thelog.com/SNW/Article/CoastGuard-Commandant-Calls-for-New-Ships-to-Replace-Aging-Fleet; Mickey McCarter, “Congress Poised to Give Coast (continued...) 49 Congressional Research Service 18 Coast Guard Cutter Procurement: Background and Issues for Congress Potential oversight questions for Congress include the following: • Under the POR force mix, how large a performance gap, precisely, would there be in each of the missions shown in Table 6? What impact would these performance gaps have on public safety, national security, and protection of living marine resources? • How sensitive are these performance gaps to the way in which the Coast Guard translates its statutory missions into more precise statements of required mission performance? • Given the performance gaps shown in Table 6, should planned numbers of Coast Guard cutters and aircraft be increased, or the Coast Guard’s statutory missions reduced, or both? • How much larger would the performance gaps in Table 6 be if planned numbers of Coast Guard cutters and aircraft are reduced below the POR figures? • Has the executive branch made sufficiently clear to Congress the difference between the number of ships and aircraft in the POR force and the number that would be needed to fully perform the Coast Guard’s statutory missions in coming years? Why has public discussion of the POR focused mostly on the capability improvement it would produce over the legacy force, and rarely on the performance gaps it would have in the missions shown in Table 6? • Why was the POR designed to fit within an originally estimated acquisition cost of about $24 billion? What analysis led to the selection of $24 billion as the appropriate total acquisition cost target for the POR? • Are recent Coast Guard acquisition funding levels the sole or most appropriate guide in determining future Coast Guard acquisition funding levels? If recent Coast Guard acquisition funding levels are used as a guide in setting future Coast Guard acquisition funding levels, how would that affect Coast Guard ship and (...continued) 2012, at http://www.fiercehomelandsecurity.com/story/coast-guard-shrinking/2012-04-18. 46 Source: transcript of hearing. Papp may have been referring to remarks he made to the press before giving his annual state of the Coast Guard speech on February 23, 2012, in which reportedly stated that the Coast Guard would require about $2 billion per year in acquisition funding to fully replace its current assets. (See Adam Benson, “Coast Guard Cutbacks Will Cost 1,000 Jobs,” Norwich Bulletin, February 23, 2012, accessed May 31, 2012, at http://www.norwichbulletin.com/news/x1138492141/Coast-Guard-cutbacks-will-cost-1-000-jobs#axzz1wSDAFCzX. See also “Coast Guard Leader Calls For More Ships,” MilitaryFeed.com, February 24, 2012, accessed May 31, 2012, at http://militaryfeed.com/coast-guard-leader-calls-for-more-ships-5/; Associated Press, “Coast Guard Commandant Calls for New Ships,” TheLog.com, March 10, 2012, accessed May 31, 2012, at http://www.thelog.com/SNW/Article/CoastGuard-Commandant-Calls-for-New-Ships-to-Replace-Aging-Fleet; Mickey McCarter, “Congress Poised to Give Coast aircraft force levels, and consequently Coast Guard mission capability and capacity, over the long run? Impact of March 1, 2013, Sequester on FY2013 Funding Another issue for Congress concerns the impact on NSC, OPC, and FRC programs of the March 1, 2013, sequester on FY2013 funding, particularly in terms of the Coast Guard’s ability to execute construction work on the sixth NSC and the FRCs that were funded in FY2013. (...continued) Guard More Money Than Requested for FY 2013,” HSToday.us, May 10, 2012, accessed May 31, 2012, at http://www.hstoday.us/focused-topics/customs-immigration/single-article-page/congress-poised-to-give-coast-guardmore-money-than-requested-for-fy-2013.html.) See also “Interview, Adm. Robert Papp, US Coast Guard Commandant,” Defense News, November 11, 2013: 30. Congressional Research Service 1819 Coast Guard Cutter Procurement: Background and Issues for Congress aircraft force levels, and consequently Coast Guard mission capability and capacity, over the long run? NSC Program: No Funding Requested in FY2014 for Long Lead Time Materials (LLTM) for Eighth Ship Another potential oversight issue for Congress is the lack of a request in the Coast Guard’s proposed FY2014 budget for acquisition funding for long lead time materials (LLTM) to support the procurement of an eighth NSC in FY2015. Providing this funding—which might amount to about $77 million, based on the amount of LLTM funding provided in FY2012 for NSC 6— would improve the construction sequence for NSC 8 and thereby reduce its total acquisition cost by $30 million to $35 million, the Coast Guard estimates.4751 At an April 16, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security subcommittee of the House Appropriations Committee, the following exchange occurred: REPRESENTATIVE DAVID PRICE: Thank you. I‘m certainly not inclined to question your commitment to the National Security Cutter number seven and giving that priority. Are we mistaken though to see the omission of the long lead time materials [for the eighth NSC] as a—as a setback or at least a—a—an omission that—that really is going to—if not throw number eight into doubt, at least greatly increases the [ship’s] cost and the delay the timeframe [for building it]. ADMIRAL ROBERT PAPP, COMMANDANT OF THE COAST GUARD: Now, there’s no doubt that the omission of long lead money for number eight will increase the [ship’s] cost. We had the same discussion last year and I was very grateful that the Subcommittee put in the long lead money for number seven. It helped us out greatly. It kept the project going. It’s predictability for the shipyard and enables them to give us a better prices we negotiate [sic]. And we have negotiated some very good prices on number six and I know we will on number seven. So it’s a disappointment to me that we‘re unable to put the long lead for number eight in there but it’s just one of those tough decisions I had to make based upon priorities on other projects that we have ongoing.4852 Similarly, at an April 16, 2013, hearing before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee on the FY2014 budget for the Coast Guard and maritime transportation, Admiral Papp testified: So I'm grateful for the fact that we now have the money for National Security Cutter number seven in the budget. But that was helped quite frankly last year by both the House and the Senate, providing long lead money for number seven. Getting long lead money in the construction of the National Security Cutter saves us money in the long run, gives the shipyard predictability so they can—they can plan out economically and helps us in our negotiating position when we—when we work towards the contract on the next cutter.49 4753 Similarly, at a May 14, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified: 51 Source: Coast Guard briefing to CRS, June 14, 2013. Transcript of hearing. 4953 Transcript of hearing. 4852 Congressional Research Service 1920 Coast Guard Cutter Procurement: Background and Issues for Congress Similarly, at a May 14, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified: The—the wisdom of having [funding for] long lead materials is demonstrated though [the budget request for] this year. We had long lead materials for [NSC number] seven. In the F.Y. ‘12 budget, we were able to take that $30 million in cost avoidance and we actually worked that into our computations when we produced the ‘14 budget and the—and the level that we asked for to do the construction on number seven. So, that—that validation that long lead materials works, but I will take the money for the ship [i.e., NSC number eight] whatever way I can get it, and, right now, it’s—it’s with the full funding in next year’s budget [i.e., FY2015].5054 FRC Program: FY2014 Request for Two (Rather than Six) Ships Another potential oversight issue for Congress concerns the Coast Guard’s FY2014 request for acquisition funding for two (rather than six) FRCs. At an April 16, 2013, hearing before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee on the FY2014 budget for the Coast Guard and maritime transportation, Admiral Robert Papp, the Commandant of the Coast Guard, stated the following when asked where the Coast Guard would apply any additional acquisition funding, above the Coast Guard’s FY2014 request, that Congress might make available: Well, I'd be happy to address at least a large portion of that, sir. You know, first of all, last year when we sign up the capital improvement plan, there was no National Security Cutter number seven in it for the ‘14 budget, none for National Security Cutter number eight in a subsequent budget.... After that, of course, the Fast Response Cutter. The shipyard is set up to construct six or receive orders for six Fast Response Cutters a year. We only had money for to the last year. We're grateful for the Congress, put money for four more so that we are potentially able to order six in fiscal year ‘13. But as the stance now, I only have enough money left within our (inaudible) accounts to offer up two. Next dollars I would spend would be on the Fast Response Cutter because ordering two per year, first of all is below the minimum quantity. We have to renegotiate the contract, which ultimately ends up in higher cost, building them in a slower rate and stretches out that program probably over the course of about 15 years at a much higher cost as our current patrol boat fleet is failing us rapidly and we're not getting the number of hours we need on them. So continuing the construction on the National Security Cutter and the Fast Response Cutters are my next highest priority.5155 Similarly, at an April 16, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security subcommittee of the House Appropriations Committee, the following exchange occurred: 50 51 Transcript of hearing. Transcript of hearing. Congressional Research Service 20 Coast Guard Cutter Procurement: Background and Issues for Congress REPRESENTATIVE JOHN CARTER (continuing): Let me ask a couple of questions about the Fast Response Cutter. Your FY ‘14 budget request includes just two Fast Response Cutters even though Congress denied the same short sighted—sort of short sighted proposal 54 55 Transcript of hearing. Transcript of hearing. Congressional Research Service 21 Coast Guard Cutter Procurement: Background and Issues for Congress last year. We bailed out the flawed request and fully funded all six cutters. I guess that’s maybe what some others anticipating they want us to do this year. As I understand it, by only requesting two cutters, you're squandering up to 30 million [dollars] in savings per year when compared to the procurement of six per year. Can you explain why you made this decision and you have to some extent already and do you plan to increase the procurement in our out-years so that we do not continue to squander savings and delay capability. The current requirements to patrol boat hours is 174,000 per year, but this budget supports less than half that requirement. Will we ever close the capability gap from what is funded to what is required for patrol boat hours, also what areas are most impacted by these gaps? ADMIRAL PAPP: Sir, I'd like to be maximizing our production of the Fast Response Cutter, I understand fully and I agree and I agree that it costs more when we don't order an economic order quantities. Where our contract calls for a minimum order of four, maximum order of six, the shipyard is geared up to do six a year. They—they have to have some sort of consistency and predictability in terms of their production rate. But once again, this was one of those tough decisions that I face in the current fiscal environment putting in as many as I can while trying to keep other projects going and being focused on my highest priority. Fast Response Cutter is one of my highest priorities. Now [sic: National] Security Cutter is my highest priority, so starting with that, I was only able to fit two Fast Response Cutters in. That gives us two options. We could renegotiate the contract to change the minimum order to two and as you recognized that ends up being a more expensive proposition. In analyzing the FY ‘13 appropriation and the multi-year nature of the funding for those six, I believe we can spread out evenly an order of four in FY ‘13 and order—and take two of the funding for two and move that into FY ‘14 and do four per year. That’s my second option at this point.5256 Later in the hearing, when asked where the Coast Guard would apply would apply any additional acquisition funding, above the Coast Guard’s FY2014 request, that Congress might make available, Admiral Papp replied: Well, Sir, clearly, if there were additional funds, the first thing I would them to is the Fast Response Cutter. We absolutely need that boat. We—I acknowledge the patrol boat hour gap but the the hour gap is sort of species argument in my estimation because we assign so many hours per the number of hulls that we have out there. Frankly, some of those hulls particularly on the Island class are not able to do all the hours that they are supposed to do. In fact, we have one [Island class] boat right now, the Chinkatig (ph) [sic: Chincoteague], which is laid up. It is—the hull is so deformed, we can't operate the ship. It would cost $3 million to get the ship back in condition so it could operate and that’s just not money that’s wisely spent. Yet, we've been unable to decommission any of the older patrol boats simply 52 Transcript of hearing. Congressional Research Service 21 Coast Guard Cutter Procurement: Background and Issues for Congress because we're trying to keep our numbers which then feed sort of—an artificial—artificial level of patrol boat hours that are out there. 56 Transcript of hearing. Congressional Research Service 22 Coast Guard Cutter Procurement: Background and Issues for Congress What we really need are the hulls. And ultimately, we need to get all 58 of those fast response cutters built, not only because they performed the patrol boat mission but because they're also more capable ship. They interface with the Offshore Patrol Cutter which is our next big project and the National Security Cutter which ultimately give us fewer large ships in the offshore environment. But hopefully with a little bit more capability from these patrol boats, we'd be able to eliminate that gap.5357 Similarly, at a May 14, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified: The first option is to award those six [FRCs] in F.Y. ‘13, which was our original intent, and then renegotiate with the shipyard to see if we can go to a minimal order—[a] quantity of two for F.Y. ‘14. We're at that point now where we can renegotiate. The fact of the matter is that renegotiating to build only two a year will increase the price. Our—our estimate [of the increase] is probably anywhere between $10 million and $20 million per ship. More when we go down to only two. Plus—plus it pushes out the replacement program to 18 years to get all those boats built. We'll be having to put the first one through a mid-life renovation before the last one is constructed. So that’s just the realities of what we're confronted with. The other—the other option is to try and balance out [the procurement rate at] four [FRCs] per year [in FY2013 and FY2014] and I understand that’s a little unfair to the ship builder, because they gear up, they bring people on board, they invest in their infrastructure based upon the—the prediction of six per year. And, as—as I've said in the past, we think if we build six a year our estimate is we get at least $30 million in cost avoidance. I—I wanted to make sure that I was very clear and understood that, and I've had my people go back and take a look [as the estimated cost avoidance at a procurement rate of six per year]. I really think it’s more than $30 million a year, but we start getting into competition sensitive information and things like that when we get any more detailed than that, but it’s clear that when you use the economic order quantity, you will get those savings.5458 As mentioned earlier (see “FRC Program” in “Background”), on September 25, 2013, the Coast Guard exercised an option for six FRCs (numbers 19-24 in the program). FRC Program: Delays, Cost Growth, and Testing Another potential oversight issue for Congress concerns delays, cost growth, and testing issues in the FRC program. A March 2012 report on the FRC program by Office of the Inspector General (OIG) of the Department of Homeland Security (DHS—the parent department of the Coast Guard) stated: The Coast Guard’s oversight of the Fast Response Cutter acquisition has helped ensure that the provisions of the contract reflect the Coast Guard’s operational requirements and that the 53 5457 58 Transcript of hearing. Transcript of hearing. Congressional Research Service 2223 Coast Guard Cutter Procurement: Background and Issues for Congress contractor is meeting the contract’s provisions. However, the Coast Guard has executed an aggressive, schedule-driven strategy that allowed construction of the Fast Response Cutters to start before operational, design, and technical risks were resolved. Consequently, six cutters under construction required rework that resulted in at least 270 days of schedule delays for each cutter and a total cost increase of $6.9 million for the acquisition. This aggressive acquisition strategy also allowed the Coast Guard to procure 12 Fast Response Cutters before testing the lead cutter in actual operations. It is uncertain whether the Fast Response Cutter will perform as intended until it completes operational test and evaluation in actual maritime environments. If operational test and evaluation on the lead Fast Response Cutter reveals deficiencies, the Fast Response Cutters may incur additional costly rework and delays, or the Coast Guard may have to accept Fast Response Cutters that do not fully meet its mission requirements. This may hinder the Coast Guard’s ability to fill the critical shortages in its patrol boat fleet.5559 The report also stated: Recommendations We recommend that the Assistant Commandant for Acquisitions, U.S. Coast Guard: Recommendation #1: Ensure that future acquisitions employ a knowledge-based acquisition strategy to the maximum extent practicable by revising the U.S. Coast Guard’s Major Systems Acquisition Manual to allow for a schedule-driven acquisition strategy to be employed only when it is properly authorized and supported by the results of a risk assessment and cost-benefit analysis. Recommendation #2: Improve low-rate initial production decisions for the U.S. Coast Guard Surface Acquisition programs by issuing a policy memorandum that requires that it achieve a specific level of design maturity at Critical Design Review. Recommendation #3: Issue a policy memorandum that requires authorization to proceed with low-rate initial production be supported by the reported results of operational assessments. Recommendation #4: Revise the Coast Guard’s acquisition policy to require a documented risk assessment when low-rate initial production quantity exceeds 10%, or other Coast Guard established minimum, of the total quantity approved for the acquisition. Recommendation #5: Mitigate risk by executing plans for an operational assessment prior to delivery of the lead FRC and take immediate action to implement recommendations from the operational assessment. Any recommendations not implemented should be supported by the results of a risk assessment and cost-benefit analysis.56 5560 59 Department of Homeland Security, Office of Inspector General, U.S. Coast Guard’s Acquisition of the Sentinel Class – Fast Response Cutter, OIG-12-68, March 2012, p. 1. Accessed June 29, 2012, at http://www.oig.dhs.gov/assets/ Mgmt/2012/OIG_12-68_Mar12.pdf. See also Calvin Biesecker, “Coast Guard’s Aggressive Schedule On FRC Carries Technical Risks, IG Cautions,” Defense Daily, April 13, 2012: 3-4. 5660 Department of Homeland Security, Office of Inspector General, U.S. Coast Guard’s Acquisition of the Sentinel Class – Fast Response Cutter, OIG-12-68, March 2012, p. 13. Congressional Research Service 2324 Coast Guard Cutter Procurement: Background and Issues for Congress The Coast Guard partially concurred with the first three recommendations and concurred with the final two.5761 OPC Program: FY2014 Funding Request Less than Projected Under FY2013 Budget Another potential oversight issue for Congress concerns the $25 million in acquisition funding requested for FY2014 for the OPC program. This figure is one-half of the $50 million that was projected for FY2014 under the Coast Guard’s FY2013 budget submission. Compared to the FY2013 CIP, the FY2014 CIP in effect shifts $25 million in OPC acquisition funding from FY2014 to FY2015 (see Table 3). The Coast Guard states that this change in the funding profile reflects a refined estimate of the cost of the work to be done on the OPC program in FY2014 and FY2015, and does not change the program’s schedule.5862 OPC Program: Cost, Design, and Acquisition Strategy Another potential oversight issue for Congress concerns the Coast Guard’s acquisition strategy for the Offshore Patrol Cutter. Potential oversight questions for Congress include the following: • Has the Coast Guard fully incorporated into the OPC acquisition strategy lessons learned from the NSC and FRC programs? What, in the Coast Guard’s view, are those lessons? • As mentioned earlier, the Coast Guard’s RFP for the OPC program establishes an affordability requirement of an average unit price of $310 million per ship, or less, in then-year dollars for ships 4 through 9 in the program. How was the $310 million figure determined? • What process is the Coast Guard using to evaluate tradeoffs in OPC performance features against this target construction price? What performance features have been reduced or eliminated to meet the target construction price? • How much confidence does the Coast Guard have that the OPC that emerges from the tradeoff process could be built within the Coast Guard’s target construction price? • As mentioned earlier, the Coast Guard plans to award preliminary and contract design (P&CD) contracts as many as three competitors in FY2013. Is the number of potential P&CD contracts too high, too low, or about right? How did the Coast Guard arrive at this number? • As also mentioned earlier, the Coast Guard plans to evaluate the P&CD efforts and then award one of the competitors a contract for detailed design development and ship construction. What process does the Coast Guard plan to use in evaluating the P&CD efforts? What evaluation factors does the Coast Guard plan to use, and how much weight will be assigned to each? 5761 Department of Homeland Security, Office of Inspector General, U.S. Coast Guard’s Acquisition of the Sentinel Class – Fast Response Cutter, OIG-12-68, March 2012, pp. 14-17. 5862 Source: Coast Guard briefing to CRS, June 14, 2013. Congressional Research Service 2425 Coast Guard Cutter Procurement: Background and Issues for Congress 2012 Testimony Some of the above questions have been discussed over the past two years at hearings on the Coast Guard’s proposed FY2013 and FY2014 budgets. For example, at a March 6, 2012, hearing on the Coast Guard’s proposed FY2013 budget before the Homeland Security Committee of the House Appropriations Committee, Admiral Robert J. Papp, Jr., the Commandant of the Coast Guard, stated: When I came in as commandant, I realized that this [the OPC program] was the most expensive project that the Coast Guard has ever taken on, honestly, as each [of the] 25 ships are a significant investment. And I also understood looking out at the horizon and seeing the storm clouds that restrict the budgets coming up there we needed to build a ship that was affordable. We rescrubbed the requirements. We have battled ourselves within the Coast Guard to make sure we're asking for just exactly what we need, nothing more nothing less. And I have said three things to my staff as we go on forward—affordable, affordable, affordable. And now I'm very pleased to say that just last week that the department [DHS] has reviewed—we passed a major milestone with acquisition decision event number two which validated our requirements for the type of cutter that we’re looking for and we are ready to go towards the preliminary and contract design work this next year.5963 Later in the hearing, the following exchange occurred: ADERHOLT: And there has been a discussion as to the capability of the OPC with objective design being more capable than the—than the threshold capability.6064 What is the current plan and capability of the OPC and what capability thresholds are you considering? PAPP: We—the driving one as I said is affordability, but having said that—and I’m not—I’m not trying to be funny here, but the—the sea-keeping capability being, you know, to operate in Sea State 5 is probably the most important to us right now because with fewer national security cutters, at least fewer than the hindrance posed that we have right now. None of our medium endurance cutters—the 210 foot and 270 foot [medium-endurance] cutters that we have—can operate in the Gulf of Alaska and the Bering Sea and they do not have the long legs to be able to send them out in the—on some of the longer deployments that we do in the Pacific. So it has to be able to launch the aircraft and boats in Sea State 5, you know, which is standard offset in the Bering Sea and also have endurance that we’ll be able to keep it out there on station. And I believe it was 45 days [of operation at sea] we’re looking for without refueling.61 5965 63 Source: Transcript of hearing. In the design of many U.S. weapon systems, threshold refers to a minimally acceptable level of capability, and objective refers to a higher (but also more expensive or technically challenging) level of capability. 6165 Source: Transcript of hearing. At a March 7, 2012, hearing on the proposed FY2013 budgets for the Coast Guard and (continued...) 6064 Congressional Research Service 2526 Coast Guard Cutter Procurement: Background and Issues for Congress 2013 Testimony At an April 16, 2013, hearing before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee on the FY2014 budget for the Coast Guard and maritime transportation, the following exchange occurred: REPRESENTATIVE DON YOUNG: Admiral, I understand this morning you told the corporation you're going to reconsider the requirement for the Offshore Patrol Cutter and reopen the design competition; if that is correct, how long will this delay construction of much of the needy cutters, I mean, how long was—what will happen? ARMIRAL ROBERT PAPP, COMNMANDANT OF THE COAST GUARD: Sir, that wasn't quite an accurate report, I said that we remain committed to the Offshore Patrol Cutter and I was asked if the ability to operate in Sea State-5 was hard and fast and I said the highest requirement for the Offshore Patrol Cuter is affordability and as we evaluate the candidate vessels we may need to go back and look at some of the requirements, I'm hopeful that we don't have to. I think we hammered off these requirements, in fact reduce some of them when I came in as (inaudible) [sic: Commandant?] because I want to make sure this ship is affordable and I've (...continued) maritime transportation programs before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee, the following similar exchange occurred: REPRESENATIVE LARSEN: Admiral Papp, some questions about the offshore patrol cutter. Obviously, we’re—we’re a little bit (inaudible) before that’s operational. And I have a question about whether or not the requirements for the OPC will prioritize one set of factors over a different set of factors. (inaudible) and Endurance, that might be more helpful in the Pacific versus speed, armament, and other requirements. How are you approaching the requirement—setting requirements to the OPC? PAPP: Sir, realizing that this is going to be the largest acquisition project that the Coast Guard has ever done and recognizing that these ships are going to last us 40 years, we’re taking the law beyond this [sic: a long look at this?]. And I realize there are some people that feel like we have dragged our feet a little bit or pushed this to the right a little bit, and I would say that’s just not the case. It is a little delayed from where we started out. But when I came in as commandant, I realized that we were going to be facing constrained budgets. So I had the staff take a look at the OPC once again, scrub the requirements with a direction that the primary requirement is affordability. We just could not afford everything that was in the requirements before, so we set new thresholds for it. But the most important is the sea-keeping capability because with a reduced number of national security cutters, if we only have eight national security cutters replacing the 12 Hamilton class cutters, we have to have a ship that’s capable of going up into the Gulf of Alaska, the Bering Sea, the Western Pacific. Our medium endurance cutters right now, and speaking as a captain of a 270-foot cutter, we cannot—those ships cannot perform in the extreme weather conditions that you find sometimes in the North Atlantic much less the Arctic, and the—the Bering Sea. So keeping the requirements for sea state five for helicopter launching and boat launching, and the Endurance were most important. And I'm really pleased to say that we have finally passed that hurdle. We went through acquisition decision event number two with the Department of Homeland Security last week, and they approved our requirements so we’re—we’re stepping out smartly now, moving ahead. (Transcript of hearing) Congressional Research Service 2627 Coast Guard Cutter Procurement: Background and Issues for Congress reported to this subcommittee and other sub-committees that we are intent on making this an affordable ship for the Coast Guard. If we had opened it up to revise the see keeping capability there probably would be a delay but I have no intent to open that up at this point, we'd have to evaluate all the candidates that we have and I'm hopeful that we'll find three candidates that look affordable because we're going to need to operate this ship in Alaska and it’s going to need to be able to launch and recover boats and aircraft while operating the barring sea.6266 Similarly, at an April 16, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland Security subcommittee of the House Appropriations Committee, the following exchange occurred: REPRESENTATIVE (UNKNOWN):6367 Thank you, Mr. Chairman. Admiral, there’s been much discussion as to the capability of the OPC specifically the requirement to operate at sea state 5. Admiral, why is this requirement important? And if the current proposals come in too high, will you decrease the sea state requirement in order to meet the target price? ADMIRAL PAPP: I would not like to do that because that would probably delay the process, but we may have to recomplete the request for proposals by changing that standard. The reason we need the standard is because we'll have only eight National Security Cutters and while they are tremendously capable ships, they can't be in the same places as 12 high endurance cutters were that they are replacing. We've been comfortable with 12 high endurance cutters because that gave us enough to operate in the Bering Sea and in the Gulf of Alaska and the broad ranges of the—of the Pacific given the fact that we'll have fewer ships, in fact, we'll only have six National Security Cutters out on the West Coast because we need to keep two on the East Coast. We need to make sure that the offshore patrol cutters are capable of operating in Alaska. The 270-foot medium endurance cutters that we have were originally intended to be able to operate everywhere. We've tried to operate them in Alaska. You can't launch and recover boats and you can't launch and recover aircraft. They just aren't—cannot survive the sea state up there. And that is our—that is our world of work. We have to be able to launch boats for our boarding teams to go aboard fishing vessels. We need to be able to launch helicopters for search and rescue. So this requirement for sea state 5 has been our highest priority on that ship. I'm sorry. It’s not been the highest priority. The highest priority has been affordability. And when people have asked me what are the three most important things about the offshore patrol cutter, I've constantly said, affordability, affordability, affordability. So that will be the driving factor on our down select for these three candidates and I'm hopeful that all three will not only be affordable but be able to survive in sea state 5—I'm sorry, not survive, but operate in sea state 5.64 6268 66 Transcript of hearing. The transcript of the hearing shows the speaker as “unknown.” 6468 Transcript of hearing. 6367 Congressional Research Service 2728 Coast Guard Cutter Procurement: Background and Issues for Congress September 2012 GAO Report Regarding the Coast Guard’s requirements development process for the OPC, a September 2012 GAO report states: Coast Guard Took Positive Steps to Improve Requirements Development and Consider Affordability for the Offshore Patrol Cutter The Coast Guard took some steps to improve the requirements development process for the Offshore Patrol Cutter—the largest acquisition in DHS’s acquisitions portfolio and, according to officials, the first acquisition in the Deepwater surface fleet in which the Coast Guard had complete control over the requirements development process. The Coast Guard undertook studies and analysis that, in part, considered the measurability and testability as required by guidance of the following four key performance parameters: operating range, operational sustainment and crew, speed, and patrol endurance. For example, the range requirement, which is the distance the cutter can travel between refueling, is clearly stated as a minimum acceptable requirement of 8,500 nautical miles at a constant speed of 14 knots to a maximum level of 9,500 nautical miles. Although cutters typically transit at various speeds over the course of a patrol, the Coast Guard conducted analysis to determine that the 14 knots speed at the minimum and maximum ranges would provide enough days between refueling given the percentage of time that the Coast Guard normally operates at certain speeds. By developing a measurable range requirement, the Coast Guard helped to promote a clear understanding of Offshore Patrol Cutter performance by potential shipbuilders and sought to balance the cost of additional range with the value that it provides. Furthermore, officials at the independent test authority—the Navy’s Commander Operational Test and Evaluation Force—told us that they have been actively involved through the requirements development process and many of their questions regarding testability have been resolved. Two other key performance parameters—seakeeping and interoperability—are not as consistent with the Coast Guard’s guidelines of measurability and testability as identified in the Major Systems Acquisition Manual. For example the seakeeping key performance parameter described in the requirements document states that the Offshore Patrol Cutter shall be able to launch small boats and helicopters in 8.2- to 13.1-foot waves. However, in the specifications document, which is used to translate the requirements document into a level of detail from which contractors can develop a reasonably priced proposal, the Coast Guard states that the Offshore Patrol Cutter shall be able to launch small boats and helicopters in no more than 10.7 foot waves while transiting in a direction that minimizes the pitch and roll of the vessel—an important detail not specified in the requirements document. Further, the interoperability key performance parameter states that the Coast Guard must be able to exchange voice, video, and data with the Department of Defense and Homeland Security agencies. However, it does not list specific external partners or substantial details regarding the systems required to exchange data and the types and size of these data that could be examples of measurability and testability. This key performance parameter does not make this distinction between parts of the military that the Coast Guard operates with most often, such as the U.S. Navy and the intelligence community, and simply requires interoperability with all of DOD. Similarly, the interoperability key performance parameter does not specify the DHS agencies for which the Coast Guard must exchange data with, which makes this parameter difficult to test. Coast Guard’s independent testing officials agreed that this key performance parameter, as currently written, is not testable in a meaningful way and stated that there are ongoing efforts to improve the clarity of this requirement. During the requirements development process for the Offshore Patrol Cutter, the Coast Guard also made some decisions with respect to affordability. The following are examples where the Coast Guard made capability trades that are expected to help lower the program’s acquisition cost: Congressional Research Service 2829 Coast Guard Cutter Procurement: Background and Issues for Congress • Speed—after a series of analyses, the Coast Guard decided to reduce the minimum acceptable speed from 25 to 22 knots thereby, according to officials, potentially eliminating the need for two diesel engines. According to a study completed by the Coast Guard, this trade could reduce the acquisition cost of each cutter by $10 million. • Stern Launch—the Coast Guard removed the stern launch ramp capability from the Offshore Patrol Cutter design. While this trade-off may inhibit the launch and recovery of small boats in certain conditions, such as substantial roll or side-to-side movement of the vessel, Coast Guard officials stated that it will reduce the cost of the cutter because a stern launch ramp requires the cutter to be heavier, thus adding cost. • C4ISR—the Coast Guard eliminated a minimum requirement for an integrated C4ISR system and instead is requiring a system built with interfaces to communicate between different software programs. According to Coast Guard officials, the Coast Guard now plans to use a Coast Guard-developed software system—Seawatch—rather than the more costly lead systems integrator-developed software system currently installed on the National Security Cutter, even though this system does not provide the Coast Guard with the capability to exchange near real-time battle data with DOD assets. The improvements and affordability decisions that the Coast Guard has made in its requirements development process for the Offshore Patrol Cutter are even more evident when compared with the process for generating requirements for its other major cutter—the National Security Cutter. Due to the nature of the lead systems integrator strategy that the Coast Guard initially used to buy the National Security Cutter, Integrated Coast Guard Systems developed the requirements, designed, and began producing the National Security Cutter before the requirements document was completed. The Coast Guard did not have an operational requirements document at the time the Coast Guard awarded the construction contract for the first cutter in 2004, but the Coast Guard documented the requirements in 2006. Further, even as the third National Security Cutter was in production, Coast Guard was refining the requirements and, in January 2010, made the decision to clarify some key performance parameters such as anti-terrorism/force protection and underwater mine detection because the existing requirements were not testable. To further remedy the lack of clear requirements, Coast Guard officials stated that they are currently developing a second version of the requirements document that improves the specificity and definition of many of the National Security Cutter’s requirements and will be used as criteria during operational testing. To date, the Coast Guard has not reduced the National Security Cutter’s capability for the purpose of affordability as it has done for the Offshore Patrol Cutter. However, according to Coast Guard officials, there is a revised acquisition program baseline under review which will reflect an ongoing effort to lower the acquisition cost of the vessel.6569 Regarding the potential accuracy of the Coast Guard’s estimated procurement cost for the OPC, given the known procurement cost of the NSC, the September 2012 GAO report states: Major Cutter Requirements and Missions Have Similarities, but Costs Vary Greatly and Concerns Remain about Affordability The requirements and missions for the National Security Cutter and the Offshore Patrol Cutter programs have similarities, but the actual cost for one National Security Cutter compared to the estimated cost of one Offshore Patrol Cutter varies greatly. Even though the Coast Guard took steps to consider affordability while developing the requirements for the 6569 Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, pp. 28-31. Congressional Research Service 2930 Coast Guard Cutter Procurement: Background and Issues for Congress Offshore Patrol Cutter, those affordability decisions do not explain the magnitude in the difference between these two costs.... This comparison raises questions whether the Offshore Patrol Cutter could be a less expensive, viable substitute for the National Security Cutter or whether there are assumptions built into the Offshore Patrol Cutter cost estimate, not related to requirements, which are driving the estimated costs down. With respect to the first, DHS, motivated by concerns about the affordability of the National Security Cutter program, completed a Cutter Study in August 2011 which included an analysis to examine the feasibility of varying the combination of objective—or optimal performing—Offshore Patrol Cutters and National Security Cutters in the program of record. Through this analysis, DHS found that defense operations is a key factor in determining the quantity of National Security Cutters needed and that the Coast Guard only needs 3.5 National Security Cutters per year to fully satisfy the planned requirement for defense-related missions. DHS concluded that with six National Security Cutters the Coast Guard can meet its goals for defense operations and mitigate some of the near-term capacity loss of the five National Security Cutter fleet modeled in the Cutter Study. DHS Program Analysis and Evaluation officials stated that this, in conjunction with other information, helped to inform the decision to not include the last two National Security Cutter hulls—hulls 7 and 8—in the fiscal years 2013-2017 capital investment plan. However, the DHS Cutter Study also notes that the time line for the two acquisitions makes a trade-off between the National Security Cutter and the Offshore Patrol Cutter difficult since the National Security Cutter program is in production whereas the Offshore Patrol Cutter program is only in the design phase. Similarly, we have reported that the Coast Guard may face an operational gap in its ability to perform missions using major cutters due to the condition of the legacy fleet. With respect to the second possibility that there are assumptions built into the Offshore Patrol Cutter cost estimate that are driving the estimated costs down, the Coast Guard included three key assumptions in the Offshore Patrol Cutter’s life cycle cost estimate, generally not related to the cutter’s key requirements, which lower the estimated cost in comparison to the actual cost of the National Security Cutter. These three assumptions are: • Learning Curve. The Coast Guard assumes that the shipyard(s) will generally continue to reduce the labor hours required to build the Offshore Patrol Cutter through the production of all 25 vessels. This may prove optimistic, particularly for later ships in the class, because the amount of additional learning per vessel–or efficiencies gained during production due to improving the manufacturing process to build the ship in a way that requires fewer labor hours–typically decreases over time in a shipbuilding program. • Military versus Commercial Standards. The life cycle cost estimate assumes that certain areas of the Offshore Patrol Cutter’s construction and material would reflect an average of 55 percent commercial standards—or construction standards that are typically used for military sealift ships that provide ocean transportation—and 45 percent military standards—or construction standards typically used for Navy combat vessels. Any changes in this assumption could have a significant effect on the cost estimate because military standards require more sophisticated construction applications, particularly in the areas of shock hardening and signature reduction, to prepare a ship to survive battle. Such sensitivity could help to explain the difference in costs between the Offshore Patrol Cutter program and the National Security Cutter program and officials stated that the latter program is being built to about 90 percent military standards. • Production Schedule. The cost estimate reflects the Coast Guard’s plan to switch from building one Offshore Patrol Cutter per year to building two Offshore Patrol Cutters per year beginning with the fourth and fifth vessel in the class. If the Coast Guard cannot Congressional Research Service 3031 Coast Guard Cutter Procurement: Background and Issues for Congress achieve or maintain this build rate due to budget constraints, it may choose to stretch the schedule for the program which in turn could increase costs. Coast Guard program officials generally agreed that these three variables are important to the cost of the Offshore Patrol Cutter and are key reasons why the Coast Guard expects one Offshore Patrol Cutter to cost less than half of one National Security Cutter. However, these officials recognized that the cost estimate for the Offshore Patrol Cutter is still uncertain since the cutter has yet to be designed—thus, the National Security Cutter’s actual costs are more reliable. Coast Guard program officials also added that the cost estimate for the Offshore Patrol Cutter is optimistic in that it assumes that the cutter will be built in accordance with the current acquisition strategy and planned schedule. They noted that any delays, design issues, or contract oversight problems—all of which were experienced during the purchase of the National Security Cutter—could increase the eventual price of the Offshore Patrol Cutter.6670 Multiyear Procurement (MYP) Another potential oversight issue for Congress concerns the potential for using multiyear procurement (MYP), also known as multiyear contracting, in acquiring new cutters. With congressional approval, certain Department of Defense (DOD) programs for procuring ships, aircraft, and other items employ MYP as a way of reducing procurement costs. As part of its Navy’s FY2013 budget submission, for example, the Navy requested (and Congress approved) authority for using MYP arrangements for DDG-51 destroyers to be procured in FY2013FY2017, for Virginia-class submarines to be procured in FY2014-FY2018, and for V-22 Osprey tilt-rotor aircraft to be procured in FY2013-FY2017. Compared to the standard or default approach of annual contracting, MYP has the potential for reducing procurement costs by several percent.6771 The statute that governs the use of MYP—10 U.S.C. 2306b—makes MYP available with congressional approval not only to DOD, but to other government departments, including DHS, the parent department of the Coast Guard.6872 Unlike the Navy and other DOD services, however, the Coast Guard is not using MYP for any of its ship or aircraft procurement programs. A May 10, 2013, press report quotes Michael Petters, the CEO of Huntington Ingalls Industries (the builder of NSCs), as stating: We basically have proposed that if we really want to save some money, we should do multiyears on [the] National Security Cutter. We’ve not had any commitment to that from the Congress, and so those [contracts] are one ship at a time.6973 Potential oversight questions for Congress include the following: 6670 Government Accountability Office, Coast Guard[:] Portfolio Management Approach Needed to Improve Major Acquisition Outcomes, GAO-12-918, September 2012, pp. 31, 33-35. 6771 For more on MYP, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz. 6872 10 U.S.C. 2306b(b)(2)(B). 6973 Michael Fabey, “HII: U.S. Non-Nuclear Shipbuilding Facing More Uncertainty Than Nuclear,” Aerospace Daily & Defense Report, May 10, 2013: 4. Congressional Research Service 3132 Coast Guard Cutter Procurement: Background and Issues for Congress • Has the Coast Guard considered using MYP for procuring NSCs, OPCs, or FRCs? If not, why not? • What would be the potential savings of using MYP for procuring the final two or three NSCs, for procuring OPCs, or for procuring FRCs? • What are the potential risks or downsides of using MYP for procuring NSCs, OPCs, or FRCs? Alternative Force Mixes Equal in Cost to Program of Record Another potential oversight issue for Congress is whether 8 NSCs, 25 OPCs, and 58 FRCs is the best mix of cutters that could be procured for the roughly the same total amount of acquisition funding. This issue was explored in a DHS Cutter Study that was completed in August 2011.7074 The study’s synopsis states that In 2010, DHS was directed to conduct a study of USCG’s major cutter recapitalization plan. The goal of this study was to evaluate whether an alternative cutter fleet mix could improve USCG’s performance while maintaining current acquisition costs of the recapitalization program of record (POR). This question was motivated by the current fiscal environment and the increasing cost of the National Security Cutter (NSC), which in turn generated questions about its affordability and cost-effectiveness. However, the desired outcome was to provide insight into determining the most cost-effective fleet to execute USCG missions both near term and well into the future.... The study was led by DHS Program Analysis and Evaluation (PA&E) with contract support from Center for Naval Analysis (CNA) and MicroSystems Integration (MSI).... The starting assumption for this study was that available USCG recapitalization funding is fixed at the cost of the POR. The study then identified and assessed the performance of alternative cutter fleets of equal acquisition cost, and compared the performance of these alternatives to the POR.7175 The DHS Cutter Study examined force mixes that included not only NSCs, OPCs, and FRCs, but also two other ship-acquisition options—a modernized version of the Coast Guard’s 270-foot Famous (WMEC-901) class medium-endurance cutter (“Mod-270” for short), and the Navy’s Littoral Combat Ship (LCS).7276 (In recent years, some observers have suggested that the Coast Guard should procure the LCS in lieu of planned cutters, while other observers have suggested that the Navy should procure a modified version of the NSC in lieu of the LCS.) Table 8 shows the nine alternative force mixes examined by the DHS Cutter Study, along with the POR mix. 7074 Alarik Fritz, Raymond Gelhaus, and Kent Nordstrom, Options for the Future USCG Cutter Fleet, Performance Trade-Offs with Fixed Acquisition Cost, IPR 14297, August 2011, 392 pp., accessed online October 23, 2012, at http://assets.fiercemarkets.net/public/sites/govit/dhscoastguardcutterstudy.pdf. 7175 Alarik Fritz, Raymond Gelhaus, and Kent Nordstrom, Options for the Future USCG Cutter Fleet, Performance Trade-Offs with Fixed Acquisition Cost, IPR 14297, August 2011, Synopsis of Results, p. 1. 7276 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress, by Ronald O'Rourke. Congressional Research Service 3233 Coast Guard Cutter Procurement: Background and Issues for Congress Table 8. Alternative Force Mixes Examined in DHS Cutter Study Group A Group B Group C Ship type POR Fleet 1 Fleet 2 Fleet 3 Fleet 4 Fleet 5 Fleet 6 Fleet 7 Fleet 8 Fleet 9 NSC 8 5 7 9 5 7 8 8 8 8 OPC 25 30 26 23 0 0 0 22 19 16 Mod270 0 0 0 0 41 37 34 0 0 0 LCS 0 0 0 0 0 0 0 3 6 9 FRC 58 58 62 59 60 58 58 58 58 58 Source: Alarik Fritz, Raymond Gelhaus, and Kent Nordstrom, Options for the Future USCG Cutter Fleet, Performance Trade-Offs with Fixed Acquisition Cost, IPR 14297, August 2011, p. 2 Regarding these alternative force mixes, the synopsis stated: Several alternative fleets were found to improve performance in certain missions and regions when compared to the POR. However, any improvements in mission performance over the POR came at a cost to mission performance in other areas. Thus, the study found that if DHS is willing to accept lower performance than the POR in selected missions and regions, it has two alternatives to the major cutter recapitalization POR: [Fleet 1]: Increase Offshore Patrol Cutter (OPC) fleet size in lieu of acquiring NSCs 6-8. [Fleet 6]: Increase OPC fleet size while selectively reducing OPC capability.7377 The synopsis stated that exercising both of the above alternatives in tandem would lead to Fleet 4.7478 The synopsis stated that Both alternatives [Fleets 1 and 6] improve several end-state Coast Guard-wide measures of performance... without increasing USCG’s major cutter acquisition costs. Moreover, these options are not mutually exclusive, and can be implemented in tandem. However, both alternatives require tradeoffs, and before selecting an alternative fleet recapitalization plan, DHS must determine whether the general performance benefits... are sufficient to offset these particular tradeoffs.... Compared to the POR, the increased performance for these alternatives would likely not be seen, until the early 2030s, whereas some of the decreases in capability for [Fleet 1] would begin in 2018 and for [Fleet 6] by 2020. Also, [Fleet 1’s] cumulative performance improvement will not meet and exceed the POR’s until 2055.... 73 While the study did not model the performance of a six-NSC fleet, the near-term impacts were analyzed. Adding a sixth NSC to [Fleet 1] mitigates some of the near-term capacity loss when compared to the Program of Record, and mitigates some risk to performance of Defense Operations and Homeland Security Contingency response. 77 Alarik Fritz, Raymond Gelhaus, and Kent Nordstrom, Options for the Future USCG Cutter Fleet, Performance Trade-Offs with Fixed Acquisition Cost, IPR 14297, August 2011, Synopsis of Results, pp. 1-2. 7478 Alarik Fritz, Raymond Gelhaus, and Kent Nordstrom, Options for the Future USCG Cutter Fleet, Performance Trade-Offs with Fixed Acquisition Cost, IPR 14297, August 2011, Synopsis of Results, p. 2. Congressional Research Service 3334 Coast Guard Cutter Procurement: Background and Issues for Congress While the study did not model the performance of a six-NSC fleet, the near-term impacts were analyzed. Adding a sixth NSC to [Fleet 1] mitigates some of the near-term capacity loss when compared to the Program of Record, and mitigates some risk to performance of Defense Operations and Homeland Security Contingency response. This study also evaluated the potential for Navy’s Littoral Combat Ship (LCS) to costeffectively replace or augment the OPC fleet. An analysis of alternative cutter fleets that incorporated small numbers of LCS in the most favorable operating conditions showed that the LCS is not well-suited to USCG operations due to its limited range and ensuing inability to maintain effective presence. While the LCS has advanced capabilities, most notably its top-end speed, this does not offset its reduced presence. Therefore, based on acquisition costs used in this study, the OPC is clearly more cost-effective at executing USCG’s major cutter mission set.7579 GAO reviewed the DHS Cutter Study, as well as the Coast Guard’s FMA Phase 1 and Phase 2 studies, and provided some observations on the three studies in a May 2012 report.7680 GAO states that “DHS PA&E and OMB [Office of Management and Budget] have so far used the Cutter Study to inform the fiscal year 2013 budget. For example, DHS PA&E officials stated that the Cutter Study provided information that DHS and OMB used, in conjunction with other information sources, to inform the decision to not include the last two NSC hulls—hulls 7 and 8—in the FY2013-2017 capital investment plan.”7781 GAO further states that In the Cutter Study, the Center for Naval Analysis (CNA) recommends that DHS explore additional fleet mix options, including looking at a mid-capability OPC. The mid-capability OPC would reduce the speed and range of the objective OPC but otherwise maintain its presence capabilities including an ability to operate in sea state 5. A CNA official responsible for the analysis stated that other characteristics of this midcapability OPC could include removing or reducing the following from the objective OPC without affecting presence: • Sensitive Compartmentalized Information Facility • Air Search and Fire Control Radars (acquire the positions of targets and provide these data to a ship’s command and control and weapon systems) • Electronic Warfare Support Measures • Berthing space (114 instead of 122) • Weapons suite (e.g., 25mm gun instead of 57mm) 75 The CNA official also stated that CNA has not studied whether these changes to the objective OPC would otherwise affect mission performance.82 Potential oversight questions for Congress include the following: 79 Alarik Fritz, Raymond Gelhaus, and Kent Nordstrom, Options for the Future USCG Cutter Fleet, Performance Trade-Offs with Fixed Acquisition Cost, IPR 14297, August 2011, Synopsis of Results, pp. 2-3. 7680 Government Accountability Office, Observations on the Coast Guard’s and the Department of Homeland Security’s Fleet Studies, GAO-12-751R, May 31, 2012. 7781 Government Accountability Office, Observations on the Coast Guard’s and the Department of Homeland Security’s Fleet Studies, GAO-12-751R, May 31, 2012, p. 3. Congressional Research Service 34 Coast Guard Cutter Procurement: Background and Issues for Congress The CNA official also stated that CNA has not studied whether these changes to the objective OPC would otherwise affect mission performance.78 Potential oversight questions for Congress include the following: 82 Government Accountability Office, Observations on the Coast Guard’s and the Department of Homeland Security’s Fleet Studies, GAO-12-751R, May 31, 2012, briefing slide 18. Congressional Research Service 35 Coast Guard Cutter Procurement: Background and Issues for Congress • What role, exactly, did the DHS Cutter Study play in the executive branch decision to not include funding for the seventh and eighth NSC in the Coast Guard’s FY2013 five-year capital investment plan? Does the DHS Cutter Study provide a sufficient analytical basis for such a decision? • Is the Coast Guard’s currently planned mix of 8 NSCs, 25 OPCs, and 58 FRCs the best mix of cutters that could be procured for the roughly the same amount of acquisition funding? What were the conclusions of the DHS Cutter Study regarding the levels of overall mission effectiveness of the nine alternative forces mixes relative to one another, and to the POR mix? • What is the Coast Guard’s assessment of the option of developing and procuring a modified version of the 270-foot Famous-class medium-endurance cutter? • What is the Coast Guard’s assessment of the option suggested by the CNA official for acquiring a “mid-capability OPC” as described in the GAO report? Information for Supporting Congressional Oversight of Procurement Programs Another oversight issue for Congress concerns the adequacy of information available to Congress to support review and oversight of Coast Guard procurement programs, including cutter procurement programs. The Coast Guard has entered a period where, like the Navy, it is requesting significant funding each year from Congress to execute multiple ship procurement and modernization programs. Congress, however, lacks ready access to basic information exhibits on Coast Guard shipbuilding programs that are equivalent to those that support congressional review and oversight of Navy ship procurement programs. Basic information exhibits readily available to Congress that support congressional review and oversight of Navy ship procurement programs include but are not limited to the following: • annual Budget Item Justification Sheets (P-40 Exhibits), Weapon System Cost Analysis sheets (P-5 Exhibits), and Ship Production Schedules (P-27 Exhibits) for each Navy shipbuilding program—exhibits that present detailed information on year-to-year program funding, unit procurement costs, and production schedules (see Appendix B for examples); • annual Selected Acquisition Reports (SARs) that DOD prepares for major DOD acquisition programs, which present supplementary data on program cost estimates, annual funding, and contract; 78 Government Accountability Office, Observations on the Coast Guard’s and the Department of Homeland Security’s Fleet Studies, GAO-12-751R, May 31, 2012, briefing slide 18. Congressional Research Service 35 Coast Guard Cutter Procurement: Background and Issues for Congress • a concise statement of the Navy’s ship force structure goal—the Navy’s current force structure goal is to achieve and maintain a fleet of about 310-316 battle force ships, consisting of certain types and numbers of ships (see Appendix C); • an annual five-year Navy shipbuilding plan that shows planned annual procurement quantities for each type of ship being procured (see Appendix D); and • an annual 30-year Navy shipbuilding plan that shows annual procurement quantities and projected Navy ship force levels over the next 30 years (see Appendix E). Congressional Research Service 36 Coast Guard Cutter Procurement: Background and Issues for Congress These information exhibits assist Congress in doing the following, among other things, in reviewing and conducting oversight on Navy shipbuilding programs: • identifying and evaluating cost growth and schedule delays in the execution of shipbuilding programs; • understanding the relationship between annual procurement rates and unit procurement cost; • evaluating whether programs are achieving satisfactory production learning curves over time; • evaluating whether proposed sequences of annual procurement quantities for programs would be efficient to execute from an industrial standpoint; • evaluating stability in Navy shipbuilding planning by tracking year-to-year changes in the five-year shipbuilding plan; • identifying potential financial and industrial-base linkages between shipbuilding programs that are being funded in overlapping years; • identifying and evaluating Navy assumptions concerning service lives and retirement dates for existing ships; • evaluating whether ship procurement needs are being pushed into the future, potentially creating an expensive ship procurement “bow wave” in coming years; and • understanding when the Navy will achieve its ship force level goals, and whether the Navy will experience ship inventory shortfalls relative to those goals that could affect the Navy’s ability to perform its missions in coming years. Although the Coast Guard and the Department of Homeland Security submit substantial budgetrelated information to Congress each year, Congress lacks ready access to the five sources of detailed program information listed above: • Although the Coast Guard’s annual budget submission includes a budgetjustification book,7983 the entries in that book for the Coast Guard’s ship procurement programs do not present information as detailed and structured as that presented in the P-40, P-5, and P-27 exhibits. 79 For the FY2013 budget, this is Department of Homeland Security, United States Coast Guard, Fiscal Year 2012 Congressional Justification, 400 pp. Congressional Research Service 36 Coast Guard Cutter Procurement: Background and Issues for Congress • Reports on Coast Guard programs equivalent to DOD’s SAR reports are not readily available to Congress. • The Coast Guard’s POR is a statement of desired procurement quantities for certain procurement programs, but not a concise statement of the Coast Guard’s overall ship force structure objective, which would take into account continued service of existing ships that are not in need of immediate replacement. • The Coast Guard’s five-year capital investment plan shows annual funding amounts for individual programs, but not annual procurement quantities, and 83 For the FY2013 budget, this is Department of Homeland Security, United States Coast Guard, Fiscal Year 2012 Congressional Justification, 400 pp. Congressional Research Service 37 Coast Guard Cutter Procurement: Background and Issues for Congress annual procurement quantities are not always easy to discern from annual funding amounts. • The Coast Guard’s budget submission does not include an equivalent of the Navy’s 30-year shipbuilding plan. A lack of ready access to these five sources of detailed program information can make it more difficult for Congress to conduct similar evaluations of Coast Guard programs. As a consequence, programs might, for example, be more likely to be reviewed over shorter time horizons, or in isolation from one another. A potential issue for Congress is whether to require the Coast Guard and the Department of Homeland Security to provide equivalents to some or all of the five information sources listed above. Opponents of this option might argue that the Coast Guard and DHS already provide substantial budget-justification information to Congress, and that preparing Coast Guard equivalents to some or all of these five information sources would be an expensive and timeconsuming proposition. Supporters of this option might argue that the cost of preparing and submitting this information would be small relative to the combined total acquisition cost the NSC, OPC, and FRC programs, and that information of this kind has proven to be of value in supporting congressional review and oversight of Navy shipbuilding programs. Legislative Activity for FY2014 Summary of Appropriations Action on FY2014 Acquisition Funding Request Table 9 summarizes appropriations action on the Coast Guard’s request for FY2014 acquisition funding for the NSC, OPC, and FRC programs. Congressional Research Service 37 Coast Guard Cutter Procurement: Background and Issues for Congress Table 9. Summary of Appropriations Action on FY2014 Acquisition Funding Request Figures in millions of dollars, rounded to nearest tenth Request House Appropriations Committee Senate Appropriations Committee Final NSC program 616 603.6a 632b 629 OPC program 25 25 25 23 FRC program 75 205c 310d 310 TOTAL 716 833.6 967 962 Request Conference Source: For House Appropriations Committee: H.Rept. 113-91 of May 29, 2013, p. 71; for. For Senate Appropriations Committee: S.Rept. 113-77 of July 18, 2013, p. 84. For Final: Explanatory statement for Divisions D, E, and F for H.R. 3547, pdf page 254 of 270. a. The exact figure is $603.553 million. Within this total, $77 million is to be used for long lead time materials (LLTM) for NSC 8. b. Within this total, $77 million is to be used for long lead time materials (LLTM) for NSC 8. c. Recommended increase of $130 million is for two additional FRCs. d. Recommended increase of $235 million is for four additional FRCs. FY2014 DHS Appropriations Act (H.R. 2217Congressional Research Service 38 Coast Guard Cutter Procurement: Background and Issues for Congress FY2014 DHS Appropriations Act (Division F of H.R. 3547/P.L. 113-76) House In addition to recommending the funding amounts shown in Table 9, the House Appropriations Committee states the following in its report (H.Rept. 113-91 of May 29, 2013) on the FY2014 DHS Appropriations Act (H.R. 2217)H.R. 2217: The President’s fiscal year 2014 budget for DHS’s fiscal year 2014 proposes to [among other things]: • Reduce Coast Guard staffing by—850 military personnel; [and]... • Reduce the Coast Guard’s recapitalization and acquisitions by—40 percent;.... Beyond these proposed reductions, further analysis reveals that the President’s fiscal year 2014 budget request for DHS will have the following performance impacts [among others]: • The lowest level of drug interdiction effectiveness in the past five years; [and] • A complete inability of the Coast Guard to fulfill its patrol boat mission requirements;... In short, the fiscal year 2014 budget request for DHS proposes to not only reduce the immediate resources of the Department’s most critical frontline components, it proposes to substantially diminish the long-term security capabilities of our Nation. The Committee categorically rejects this flawed budget request for DHS. ... the bill [as reported] supports essential security operations by [among other things]: Congressional Research Service 38 Coast Guard Cutter Procurement: Background and Issues for Congress • Restoring nearly all of the proposed reductions to the Coast Guard’s operating and acquisition budgets and increases funding for counternarcotics operations and sustainment of aging assets;... (Pages 4-5) The report also states: Over the last several years, the Department has continually requested a substantial reduction in funding that would degrade the Coast Guard’s operational capabilities and military workforce without proposing a compensatory proposal to rebuild the depleted capacity in the long term by investing in recapitalized assets. Those proposals had obvious, adverse implications for the Coast Guard’s critical statutory missions of maritime safety, coastal security, and drug interdiction; ignored current threat activity and the ramifications for the Department’s broader security and response efforts; and were resoundingly rejected by Congress. The fiscal year 2014 proposal is even more egregious, and gives the impression that this Administration does not appropriately value the work of the Coast Guard. It includes the lowest level of drug interdiction effectiveness in the past five years and reduces recapitalization funding to unsustainable levels. Over the past decade when our Nation has called for help, the Coast Guard has responded: they responded on the morning of 9/11 by helping untold numbers of people evacuate the devastation of lower Manhattan; they Congressional Research Service 39 Coast Guard Cutter Procurement: Background and Issues for Congress responded during the aftermath of Katrina by saving survivors stranded on rooftops; they responded by being the first to arrive in Haiti after an earthquake hit the country and killed thousands; and more recently, they responded to the worst oil spill in the history of our Nation. If the country intends for the Coast Guard of tomorrow to be as effective as the Coast Guard we have today, and have depended on for decades, these reductions must be resoundingly rejected. Within the recommendation, the Committee has made targeted increases to address the inadequacy of the Department’s request—adding capacity to the Coast Guard for today and for tomorrow. (Pages 66-67) The report also states: Mission Needs Statement No Administration has ever proposed a budget that begins to close the mission hour gap the Coast Guard created on paper when it rebaselined its acquisition programs after 9/11. As highlighted by the GAO, the Coast Guard acquisition program is unachievable—particularly if the Coast Guard will be limited to a Capital Investment Plan (CIP) that is less than $1,000,000,000 per year for the next five years as is provided in the current plan. The Coast Guard’s acquisition budget has grown dramatically in the years since 9/11, but, particularly in light of the steep and dramatic cuts proposed in this year’s CIP, there is no reason to believe the gaping space between the 1998 baseline and the 2004 baseline will ever close in any significant way for aircraft or patrol boats. The mission hour target dropped for major cutters in the 2004 rebaselining, but remains unattainable through 2030 since it appears to assume the production of two Offshore Patrol Cutters (OPC) per year. However, even if the OPC currently under source selection meets the requirements laid out in the Coast Guard’s Operational Requirements Document, it seems unlikely at the levels included in the CIP that such a program would be sustainable. Therefore, the Committee directs the Coast Guard to begin the process of developing a new mission needs statement that takes into account today’s fiscal environment. If the Administration truly plans for the Coast Guard funding level to be what was presented in the Fiscal Year 2014 CIP, then this process should also address what missions the Coast Guard will no longer be able to achieve. The Committee notes that in the Fiscal Year 2014 Coast Guard Budget Hearing, the Commandant commented that the patrol boat hour requirement was “specious”. The Committee cannot continue to accept a requirements document that is doubted by the senior leader of the Coast Congressional Research Service 39 Coast Guard Cutter Procurement: Background and Issues for Congress Guard. In order to plan for the future, the Coast Guard must match requirements to resources and provide an achievable plan. (Pages 67-68) Regarding the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account, the report states: The Committee recommends significant restructuring of numerous programs to align funding with the requirements in the fiscal year of need.8084 Further, the recommendation provides funding for programs that have a proven track record, are low risk, have known costs, and provide increased capability. The Committee recommends a net reduction of $12,447,000 requested for the National Security Cutter (NSC).... The Committee recommends the following increases [among others] above the amount requested: an increase of $130,000,000 above the amount requested for two additional FRCs; ... and an increase of $77,000,000 for long lead time materials for NSC 8. (Pages 70 and 71) 84 The report similarly states on page 7 that “The Committee continues to press reform of inefficient budgeting for Coast Guard acquisitions by aligning funding to requirements based on the fiscal year of need.” Congressional Research Service 40 Coast Guard Cutter Procurement: Background and Issues for Congress The funding table on page 71 of the committee’s report shows a total of $603.553 million for the NSC program, reflecting the above-mentioned net reduction of $12.447 million from the Coast Guard’s request. The implication is that the $77 million in funding for LLTM for NSC 8 is not in addition to, but rather forms part of, the total recommended appropriation for the NSC program of $603.553 million. This appears to be confirmed by another passage from the committee’s report, which states: National Security Cutter The Committee recommends $603,553,000 for the NSC program to include long lead time material for NSC 8, $12,447,000 below the amount requested and $75,068,000 below the amount provided in fiscal year 2013. The recommendation includes a decrease of $12,447,000 for contract savings associated with the contract for the sixth NSC. The recommendation also defers funding for post-delivery activities that are requested unnecessarily ahead of need. Fast Response Cutter The Committee recommends $205,000,000 for the acquisition of four FRCs, $130,000,000 above the amount requested and $129,665,000 below the amount provided in fiscal year 2013. The fiscal year 2014 budget request included funding for only two FRCs. This represents almost $30,000,000 in savings that will not be realized and delays the delivery of much needed capability. This is the same type of budget gimmickry the Department proposed and Congress rejected in fiscal year 2013. It is unclear as to how the Department plans to close the various gaps in needed capability if it continues to make such ineffective and unjustified budget requests. (Page 73) The section of H.R. 2217 as reported that appropriates funds for the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account includes several provisos, including the following: ... Provided, That the funds provided by this Act shall be immediately available and allotted to contract for the production of the seventh National Security Cutter notwithstanding the 80 The report similarly states on page 7 that “The Committee continues to press reform of inefficient budgeting for Coast Guard acquisitions by aligning funding to requirements based on the fiscal year of need.” Congressional Research Service 40 Coast Guard Cutter Procurement: Background and Issues for Congress availability of funds for post-production costs: Provided further, That the funds provided by this Act shall be immediately available and allotted to contract for long lead time materials, components, and designs for the eighth National Security Cutter notwithstanding the availability of funds for production costs or post-production costs:... Section 516 of the bill as reported states: Sec. 516. Any funds appropriated to Coast Guard `Acquisition, Construction, and Improvements’ for fiscal years 2002, 2003, 2004, 2005, and 2006 for the 110-123 foot patrol boat conversion81conversion85 that are recovered, collected, or otherwise received as the result of negotiation, mediation, or litigation, shall be available until expended for the Fast Response Cutter program. Section 568 of the bill as reported rescinds certain prior-year Coast Guard Acquisition, Construction, and Improvement (AC&I) account funding. Regarding these rescissions, the committee’s report states: 85 This is a reference to a canceled Coast Guard program to modernize the Coast Guard’s 110-foot Island class patrol boats with a work package that would, among other things, lengthen the boats to 123 feet. Congressional Research Service 41 Coast Guard Cutter Procurement: Background and Issues for Congress The Committee recommends the following rescissions [among others] in Title V of this bill [Section 568 as reported] from prior year accounts:... from funds provided in fiscal year 2011,... $12,612,000 for excessive antecedent liability and economic price adjustment funding in the Fast Response Cutter (FRC) program; from funds provided in fiscal year 2012,... $29,500,000 from funds for the FRC to include $22,500,000 for excessive antecedent liability and economic price adjustment funding; and from funds provided in fiscal year 2013, $22,000,000 for excessive antecedent liability and economic price adjustment funding in the FRC program, $10,480,000 from the NSC program to include $5,000,000 for a post shakedown availability for NSC 4, $1,882,000 for a gantry crane and davit for NSC 6, and $3,598,000 for waterfront changes associated with NSC 6. (Page 71) The committee’s report also states: Full Funding The Committee included a new general provision in fiscal year 2013 to address the lack of clarity in certain programs with respect to budgeting for long lead-time materials, end items, outfitting, post-delivery activities, spares, program management, and contract closeout. However, it is clear that the Department has chosen to ignore that direction based on this year’s request for the NSC. Similar to the fiscal year 2013 request, the fiscal year 2014 request for the NSC includes funding for post-delivery activities of the seventh NSC that will not occur until fiscal year 2019 and does not request funding for the long lead time materials for NSC 8, even though the Department plans to procure an eighth NSC in fiscal year 2015. Section 557 of Public Law 113–6 specifically addressed these issues by mandating the Department develop a fiscal policy that prescribes budgetary policies, procedures, and technical direction necessary to comply with the section’s definitions of full funding. To further address this issue, the Committee includes a new provision in Title V of this bill [Section 548 as reported] directing the Department to provide a report with the submission of the President’s fiscal year 2015 budget that details its compliance with section 557 of Public Law 113–6. (Pages 72-73) 81 This is a reference to a canceled Coast Guard program to modernize the Coast Guard’s 110-foot Island class patrol boats with a work package that would, among other things, lengthen the boats to 123 feet. Congressional Research Service 41 Coast Guard Cutter Procurement: Background and Issues for Congress Senate In addition to recommending the funding amounts shown in Table 9, the Senate Appropriations Committee states the following in its report (S.Rept. 113-77 of July 18, 2013) on the FY2014 DHS Appropriations Act (H.R. 2217)H.R. 2217: NATIONAL SECURITY CUTTER The Coast Guard operates a fleet of 378-foot high endurance cutters [HECs] that are over 43 years old on average, and are increasingly unreliable and expensive to maintain. By comparison, the average Navy ship is 20 years old. The Coast Guard’s program of record is to acquire 8 national security cutters [NSCs] to replace 12 HECs (of which 3 have been decommissioned with the arrival of the first 3 NSCs). To date, approximately $3,848,000,000 has been appropriated for six NSCs and long lead time materials [LLTM] for NSC–7. Three NSCs have been delivered to the Coast Guard, the fourth is expected to be delivered in fiscal year 2014, the fifth in fiscal year 2015, and the sixth in 2017. As noted in prior years, the Committee strongly supports the procurement of one national security cutter per year until all eight planned ships are procured. The continuation of production without a break will ensure that these ships, which are vital to the Coast Guard’s mission, are procured at the lowest cost, and that they enter the Coast Guard fleet as soon as possible. The Committee is concerned that the Administration’s current acquisition policy Congressional Research Service 42 Coast Guard Cutter Procurement: Background and Issues for Congress requires the Coast Guard to attain total acquisition cost for a vessel, including long lead time materials, production costs, and post-production costs, before a production contract can be awarded. This has the potential to create shipbuilding inefficiencies, force delayed obligation of production funds, and require postproduction funds far in advance of when they will be used. As an example of such inefficiency, the fiscal year 2013 budget request proposed a rescission and reappropriation of $25,000,000 in funds previously appropriated for NSC–4 post-production that would have expired before they could be spent. The Department should be in a position to acquire NSCs in the most efficient manner within the guidelines of strict governance measures. Therefore, the Committee includes language in the bill specifying that funds made available by this act shall be available to contract for long lead time materials for Coast Guard vessels, notwithstanding the availability of funds for production costs or postproduction costs. For NSC–7, the Committee includes $12,000,000 for Segment 2 of LLTM. The Committee recommendation also includes $540,000,000, as requested, for production and $3,000,000 for postproduction costs. Funding for post-production costs is $61,000,000 below the request due to the fact that these funds are not necessary until fiscal years 2016 through 2018. The request includes no funding for LLTM for NSC–8. The Committee disagrees with this proposal. Procuring these materials in advance will save substantial time and money by ensuring that supplies and components that require a long time to obtain are available to the manufacturer when they are needed. By providing LLTM for NSC–6 in advance, the Coast Guard was able to save $30,000,000 in the total cost of the ship. Therefore the bill includes $77,000,000 for LLTM for NSC–8. According to the Department, this will accelerate the production schedule for the cutter and result in direct savings of up to $40,000,000 compared to delaying long lead acquisition to fiscal year 2015. FAST RESPONSE CUTTER The Committee recommends $310,000,000 for the Coast Guard’s Fast Response Cutter [FRC]. This funding will allow the Coast Guard to acquire six FRC hulls (25–30). Procuring six FRCs in fiscal year 2014 will maximize the production line and generate cost savings of at least $5,000,000 per hull for a total savings to the taxpayers of $30,000,000. Funding six Congressional Research Service 42 Coast Guard Cutter Procurement: Background and Issues for Congress boats instead of two will also allow the Coast Guard to advance the replacement of the aging 110-foot island class patrol boats, which are already beyond the end of their projected service lives and very expensive to maintain. Each FRC will provide 2,500 annual operating hours and improved sea keeping ability, resulting in better habitability and full-mission capability in higher sea states. OFFSHORE PATROL CUTTER The recommendation includes $25,000,000 for the Offshore Patrol Cutter [OPC], as requested. Funding is provided for pre-acquisition design work of the OPC, which is intended to replace the Coast Guard’s aging fleet of medium endurance cutters. The Coast Guard expects to award preliminary and contract designs to three competing contractors in fiscal year 2013. A final detailed design and construction award is expected in fiscal year 2016. The OPC’s initial capabilities to control and direct aircraft as well as execute interdiction missions should, to the maximum extent feasible, be equivalent to that of the NSC to facilitate maximum savings to the Federal Government, rather than being deferred to future upgrades that add to total cost of ownership. The Committee urges the Coast Guard to maximize, to the greatest extent practicable, such systems’ commonality between the OPC and the NSC to reduce total acquisition cost and lifecycle costs facilitated by savings in life Congressional Research Service 43 Coast Guard Cutter Procurement: Background and Issues for Congress cycle logistics management, integration costs, and personnel training efficiencies. (Pages 8788; material in brackets as in original) The report also states: COMMITTEE RECOMMENDATIONS The President’s fiscal year 2014 discretionary budget request proposes to reduce funding for the Coast Guard by 8 percent, including the reduction of over 850 military billets, the movement of 1,050 reservists to inactive status resulting in the smallest reserve force since 1957, the decommissioning of critical operational assets, and a 38 percent reduction in capital expenditures to a level not seen since 2003. When testifying before the subcommittee on the fiscal year 2014 budget request, the Commandant of the Coast Guard said that the proposed budget reductions could cause a “death spiral”, as the agency would be forced to sustain cutters that average over 46 years of age instead of having funding to procure new vessels and aircraft. If the budget request were to be enacted, the Coast Guard’s ability to carry out its 11 statutory missions would be seriously hampered. The recommended level provided for in this bill includes targeted increases above the President’s request to ensure that Coast Guard personnel serving on the front lines have the resources and assets to fulfill their many missions in fiscal year 2014 and in the future. (Pages 73-74) The report also states: OPERATIONAL ENHANCEMENTS High Endurance Cutters.—The budget request proposes to decommission two high endurance cutters [HECs] and 368 associated billets. These cutters average 46 years in age and have become increasingly unreliable. The Committee, however, is concerned that the decommissioning of two cutters in fiscal year 2014 would result in a significant cutter hour gap before new National Security Cutters [NSCs] are delivered to replace them. To date, four HECs have been decommissioned and the Coast Guard has delivered three NSCs. The fourth NSC is under production and scheduled for delivery in late fiscal year 2014 and the fifth NSC is under contract and scheduled for delivery in fiscal year 2015. Historically, HECs Congressional Research Service 43 Coast Guard Cutter Procurement: Background and Issues for Congress provide the greatest resource hour contribution to the counterdrug mission, both in the Eastern Pacific and Western Hemisphere. In fiscal year 2012, the Coast Guard seized 107 metric tons of cocaine, more than all other Federal agencies combined. The proposed reduction of two HECs with only one national security cutter delivered in fiscal year 2014 will result in a diminished presence and fewer opportunities for interdictions. Therefore, the recommendation includes an additional $8,000,000 and 184 positions to maintain one of the two HECs proposed to be decommissioned in the request, saving 1,665 major cutter hours (3,330 hours annualized) that otherwise would have been cut. (Page 76; material in brackets as in original) The report also states: LEGACY PATROL BOATS A total of six fast response cutters [FRCs] are funded within the “Acquisition, Construction, and Improvements” appropriation, four boats and $235,000,000 above the request. This will bring the total amount funded to 30 boats, 12 of which will be in-service by the end of 2014. FRCs are replacing aging 110-foot Island Class Patrol Boats, which are already beyond the end of their projected service lives and very expensive to maintain. The Committee has learned that two of these patrol boats have such severe hull deterioration, it has become cost prohibitive to maintain them beyond fiscal year 2013. Given the fact that the bill increases Congressional Research Service 44 Coast Guard Cutter Procurement: Background and Issues for Congress the number of new patrol boats by four, providing for 10,000 additional operational hours, the Committee expects the Coast Guard to decommission two legacy patrol boats that are in the worst material condition, achieving savings of $2,763,000. (Page 80; material in brackets as in original) The report also states: INFRASTRUCTURE AND RESPONSE CAPABILITIES IN THE ARCTIC The Committee is concerned about the lack of assets available for the Coast Guard’s Arctic mission. No later than 120 days after the date of enactment of this act, the Commandant is directed to submit a report to the Committee comparing the costs of facility renovations to homeport and support an NSC in Alaska with the annual costs of transit time to Alaska area of operations for deployments and days lost to casualty repairs. (Pages 80-81) The report also states: ACQUISITION PORTFOLIO REVIEW The fiscal year 2014 CIP [Five Year Capital Investment Plan] that was submitted to the Committee on April 19, 2013, calls for a radical change to Coast Guard recapitalization efforts in future years. The funding levels suggested in the plan would decrease the number of fast response cutters to a level that jeopardizes the program, stop the acquisition of new aircraft, delay completion of the offshore patrol cutter, put the acquisition of a new polar icebreaker at risk, and scale back investment in deteriorating shore facilities. If enacted, this investment plan would have dire consequences on the Coast Guard’s ability to carry out its missions, such as: interdicting drugs in the transit zone; managing a mass migration event; responding to oil spills; fisheries enforcement; and the need to increase U.S. presence in the Arctic. The CIP states that DHS will conduct a comprehensive portfolio review in 2013 that will help develop revised acquisition program baselines and direct key acquisition decision events to reflect acquisition priorities and operational requirements achievable within the funding projections contained in the fiscal year 2014 CIP. A major flaw in the fiscal year 2014 CIP is the Department’s conclusion that the funding levels it contains for the Congressional Research Service 44 Coast Guard Cutter Procurement: Background and Issues for Congress “Acquisition, Construction, and Improvements” appropriation are consistent with the presequester caps imposed on discretionary budget authority through 2021 under the Budget Control Act of 2011. The reality is that the fiscal year 2014 budget request for the “Acquisition, Construction, and Improvements” appropriation is 38 percent below the fiscal year 2013 enacted level, after factoring out emergency supplemental funding, while total discretionary spending under the Budget Control Act of 2011 increases by 1.4 percent between fiscal year 2013 and fiscal year 2014. In conducting the portfolio review described in the CIP, the Department shall use more appropriate outyear funding levels that are reflective of the fiscal year 2013 enacted level for the “Acquisition, Construction, and Improvements” appropriation, as adjusted by the pre-sequester caps set in the Budget Control Act of 2011. Finally, the review is to include acquisition cost, asset capability and quantity tradeoffs, and the overall impact to the Coast Guard’s ability to carry out all of its statutory missions. The results of the review shall be validated by an independent third party selected by the Secretary and the Commandant to ensure that a realistic budget outlook does not censor necessary data on mission needs and tradeoffs. The report by the independent third party shall be provided to the Committee in conjunction with the President’s fiscal year 2015 budget request. (Pages 85-86) The section of H.R. 2217 as reported that appropriates funds for the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account includes several provisos, including the following: Congressional Research Service 45 Coast Guard Cutter Procurement: Background and Issues for Congress ... Provided, That the funds provided by this Act shall be immediately available and allotted to contract for the production of the seventh National Security Cutter notwithstanding the availability of funds for post-production costs: Provided further, That the funds provided by this Act shall be immediately available and allotted to contract for long lead time materials, components, and designs for the eighth National Security Cutter notwithstanding the availability of funds for production costs or post-production costs:... Section 517 of the bill as reported states: Sec. 517. Any funds appropriated to Coast Guard `Acquisition, Construction, and Improvements' for fiscal years 2002, 2003, 2004, 2005, and 2006 for the 110-123 foot patrol boat conversion that are recovered, collected, or otherwise received as the result of negotiation, mediation, or litigation, shall be available until expended for the Fast Response Cutter program. Section 570 of the bill as reported rescinds certain prior-year Coast Guard Acquisition, Construction, and Improvement (AC&I) account funding. S.Rept. 113-77 includes a table on page 189 showing these rescissions; the table does break down the rescinded amounts by individual line items within the AC&I account. Congressional Research Service 45Final Version The final version of the FY2014 DHS appropriations act (Division F of H.R. 3547/P.L. 113-76) provides the funding amounts shown in Table 9. Section 517 of Division F states: Sec. 517. Any funds appropriated to `Coast Guard Acquisition, Construction, and Improvements’ for fiscal years 2002, 2003, 2004, 2005, and 2006 for the 110-123 foot patrol boat conversion that are recovered, collected, or otherwise received as the result of negotiation, mediation, or litigation, shall be available until expended for the Fast Response Cutter program. Section 553 of Division F states: Sec. 553. The Secretary of Homeland Security shall submit to the Committees on Appropriations of the Senate and the House of Representatives, not later than April 15, 2014, a report detailing the fiscal policy that prescribes Coast Guard budgetary policies, procedures, and technical direction necessary to comply with subsection (a) of section 557 of division D of P.L. 113-6 (as required to be developed under subsection (b) of such section).86 86 Section 557(a) of division D of H.R. 933/P.L. 113-6 of March 26, 2013 (the FY2013 Consolidated and Further Continuing Appropriations Act) states: Sec. 557. (a) Notwithstanding Office of Management and Budget Circular A-11, funds made available in fiscal year 2013, or any fiscal year thereafter, under Department of Homeland Security, Coast Guard, `Acquisition, Construction, and Improvements’ for— (1) long lead time materials, components, and designs of a vessel of the Coast Guard shall be immediately available and allotted to make a contract award notwithstanding the availability of funds for production, outfitting, post-delivery activities, and spare or repair parts; and (2) production of a vessel of the Coast Guard shall be immediately available and allotted to make a contract award notwithstanding the availability of funds for outfitting, post-delivery activities, and spare or repair parts. Congressional Research Service 46 Coast Guard Cutter Procurement: Background and Issues for Congress The explanatory statement for Divisions D, E, and F of H.R. 3547 states: Acquisition Portfolio Review and Mission Needs As directed in the Senate report, in conducting the portfolio review described in the Capital Investment Plan, the Department shall use more appropriate outyear funding levels that are reflective of the fiscal year 2013 enacted level for the Acquisition, Construction, and Improvements appropriation, as adjusted by the pre-sequester caps set in the Budget Control Act of 2011. The review is to include acquisition cost, asset capability and quantity tradeoffs, the overall impact to the Coast Guard’s ability to carry out all of its statutory missions, and how it addresses gaps in capability based on the most recent mission needs statement. The results of the review shall be validated by an independent third party selected by the Secretary and the Commandant to ensure that a realistic budget outlook does not censor necessary data on mission needs and tradeoffs. The portfolio review and independent third party assessment shall be provided to the Committees not later than April 15, 2014.... National Security Cutter A total of $629,000,000 is provided for the NSC program. Of this amount, $540,000,000 is for the production of NSC-7, $12,000,000 is for the second segment of long lead time materials for NSC-7, and $77,000,000 is to acquire long lead time materials for the production of NSC-8. (pdf pages 209 and 210 of 270) Congressional Research Service 47 Coast Guard Cutter Procurement: Background and Issues for Congress Appendix A. Findings and Recommendations of DHS Cutter Study This appendix reprints the findings and recommendations of the August 2011 DHS Cutter study. They are as follows: Findings These are our major findings: • Replacing some NSCs with OPCs has a small, positive impact on OpEff [operational effectiveness]. Differences are on the order of 5 percent from POR [the program of record] and scale with the difference in cutter availability. • Replacing all OPCs with mod-270 has a significant positive impact on OpEff. It increases drug interdiction by roughly 20 percent over POR. The increase in performance is much less than the increase in cutters. Performance in missions other than counter-drug and in regions outside the southeast is comparable to or slightly below POR. • Replacing OPCs with LCSs reduces OpEff significantly. Given that LCS acquisition cost will be at least as much as OPC, we cannot construct a cost-effective way to use LCS to increase UCSG mission performance. • Moving away from POR adds uncertainty. Reducing the number of NSCs may limit USCG ability to support defense operations (DEFOPS), and switching to a mod-270 [cutter design] creates a fleet that has trouble operating in poor weather. • Long-term total ownership cost is similar for all excursions. Group B [alternative fleets 4, 5, and 6] is most expensive, due to higher personnel costs. • Updated or changed assumptions could change OpEff significantly. More efficient patrol patterns could increase POR OpEff by 5 percentage points at no cost, while a potential “mid-capability” OPC could narrow the OpEff gap between group B and POR by another 5 percentage points. With both changes, group A [alternative fleets 1, 2, and 3] and group B should have about equal OpEff. Recommendations Based on our findings, we make the following recommendations. • USCG should quantify the DEFOPS requirement to assess the impact of reducing NSC numbers. A 2.0 NSC presence will be difficult to support with only 5 NSC if they are also supporting other missions. • DHS PA&E should work with USCG to quantify distant, poor-weather operating areas to inform or mitigate the limitations of the mod-270. Additional NSCs could offset some of the range and seakeeping deficiencies of the mod-270. Further study is necessary to see if it would be cost-effective. Congressional Research Service 4648 Coast Guard Cutter Procurement: Background and Issues for Congress • DHS PA&E should explore additional fleet mix options. Cost data should be updated as new information becomes available to confirm that the modeled excursions are still feasible. New options, such as a “mid-capability” OPC could improve fleet OpEff or decrease cost. • USCG should optimize its cutter basing and CONOPS. Choosing cutter homeports and operating patterns to maximize on-station patrol time will get the most out of a costlimited fleet. • DHS PA&E should commission a similar study for aircraft. This study did not consider changes in aviation, which could have significant impact on performance. There may be opportunities to trade off air and surface assets to maximize total OpEff. • DHS PA&E should track long-term acquisition profiles and recapitalization priorities. The multi-year spending profile for cutter acquisition has periods of significantly higher- and lower-than-average expenditure, which could have significant interplay with other DHS acquisition priorities.82 8287 87 Alarik Fritz, Raymond Gelhaus, and Kent Nordstrom, Options for the Future USCG Cutter Fleet, Performance Trade-Offs with Fixed Acquisition Cost, IPR 14297, August 2011, pp. 2-3. Congressional Research Service 4749 Coast Guard Cutter Procurement: Background and Issues for Congress Appendix B. P-5, P-40, and P-27 Data Exhibits for Littoral Combat Ship (LCS) Program This appendix presents the Budget Item Justification Sheet (Exhibit P-40), Weapon System Cost Analysis sheet (Exhibit P-5), and Ship Production Schedule (Exhibit P-27) for the Navy’s Littoral Combat Ship (LCS) program, as examples of the kind of information that is available each year to support congressional review and oversight of Navy shipbuilding programs. Congressional Research Service 48 Coast Guard Cutter Procurement: Background and Issues for Congress 50 Figure B-1. Budget Item Justification Sheet (Exhibit P-40) For Navy Littoral Combat Ship (LCS) Program Source: Department of the Navy Fiscal Year (FY) 2013 Justification of Estimates, Shipbuilding and Conversion, Navy, February 2012, p. 11-1 (pdf page 156 of 246). CRS-49 Coast Guard Cutter Procurement: Background and Issues for Congress 51 Figure B-2. Weapon System Cost Analysis Sheet (Exhibit P-5) For Navy Littoral Combat Ship (LCS) Program Source: Department of the Navy Fiscal Year (FY) 2013 Justification of Estimates, Shipbuilding and Conversion, Navy, February 2012, p. 11-2 (pdf page 157 of 246). CRS-50 Coast Guard Cutter Procurement: Background and Issues for Congress 52 Figure B-3. Ship Production Schedule (Exhibit P-27) For Navy Littoral Combat Ship (LCS) Program Source: Department of the Navy Fiscal Year (FY) 2013 Justification of Estimates, Shipbuilding and Conversion, Navy, February 2012, p. 11-2 (pdf page 159 of 246). CRS-5153 Coast Guard Cutter Procurement: Background and Issues for Congress Appendix C. Navy Ship Force Structure Objective Table C-1 presents the Navy’s current ship force structure objective. Table C-1. Navy Ship Force Structure Goal Ship type Force Structure Objective Ballistic missile submarines (SSBNs) 12 Cruise missile submarines (SSGNs) 0 Attack submarines (SSNs) 48 Aircraft carriers 11 Cruisers and destroyers 88 Littoral Combat Ships (LCSs) 52 Amphibious ships 33 Combat logistics (resupply) ships 29 Joint High Speed Vessels (JHSVs) 10 Other (includes support ships) 23 Total battle force ships 306 Sources: Department of the Navy, Report to Congress [on] Navy Combatant Vessel Force Structure Requirement, January 2013, 3 pp. The cover letters for the report were dated January 31, 2013. Congressional Research Service 5254 Coast Guard Cutter Procurement: Background and Issues for Congress Appendix D. Navy FY2014 Five-Year Shipbuilding Plan Table D-1 presents the Navy’s FY2014 five-year (FY2014-FY2018) shipbuilding plan. Table D-1. Navy FY2014 Five-Year (FY2014-FY2018) Shipbuilding Plan (Battle force ships—i.e., ships that count against 306-ship goal) Ship type FY14 FY15 FY16 FY17 Ford (CVN-78) class aircraft carrier FY18 Total 1 1 Virginia (SSN-774) class attack submarine 2 2 2 2 2 10 Arleigh Burke (DDG-51) class destroyer 1 2 2 2 2 9 Littoral Combat Ship (LCS) 4 4 2 2 2 14 LHA(R) amphibious assault ship 0 0 0 1 0 1 Fleet tug (TATF) 0 0 0 2 1 3 Mobile Landing Platform (MLP)/Afloat Forward Staging Base (AFSB) 1 0 0 0 0 1 TAO(X) oiler 0 0 1 0 1 2 TOTAL 8 8 7 9 9 41 Source: FY2014 Navy budget submission. Notes: The MLP/AFSB is a variant of the MLP with additional features permitting it to serve in the role of an AFSB. Congressional Research Service 5355 Coast Guard Cutter Procurement: Background and Issues for Congress Appendix E. Navy FY2014 30-Year Shipbuilding Plan Table E-1 shows the Navy’s proposed FY2014 30-year (FY2014-FY2043) shipbuilding plan. Table E-1. Navy FY2014 30-Year (FY2014-FY2043) Shipbuilding Plan FY 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 CVN 1 1 1 1 1 1 LSC 1 2 2 2 2 2 2 2 3 3 2 3 2 3 3 3 2 2 2 2 2 2 2 2 3 3 3 3 3 2 SSC 4 4 2 2 2 3 3 3 3 3 3 3 1 1 1 1 1 4 4 4 4 4 3 3 SSN 2 2 2 2 2 2 2 2 2 2 1 2 1 2 1 1 1 2 1 1 1 1 1 2 2 1 2 1 2 1 SSBN AWS CLF Supt 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 2 1 1 2 2 3 2 1 1 1 2 2 3 2 2 Total 8 8 7 9 9 10 10 10 11 14 11 11 6 8 10 8 9 9 11 9 7 5 4 8 10 8 11 8 9 8 Source: FY2014 30-year (FY2014-FY2043) shipbuilding plan. Key: FY = Fiscal Year; CVN = aircraft carriers; LSC = surface combatants (i.e., cruisers and destroyers); SSC = small surface combatants (i.e., Littoral Combat Ships [LCSs]); SSN = attack submarines; SSGN = cruise missile submarines; SSBN = ballistic missile submarines; AWS = amphibious warfare ships; CLF = combat logistics force (i.e., resupply) ships; Supt = support ships. Congressional Research Service 5456 Coast Guard Cutter Procurement: Background and Issues for Congress Table E-2 shows the Navy’s projection of force levels for FY2014-FY2043 that would result from implementing the FY2014 30-year (FY2014-FY2043) shipbuilding plan shown in Table E1. Table E-2. Projected Force Levels Resulting from FY2014 30-Year (FY2014-FY2043) Shipbuilding Plan CVN LSC SSC SSN SSGN SSBN AWS CLF Supt Total 11 88 52 48 0 12 33 29 33 306 FY14 10 85 26 55 4 14 31 31 26 282 FY15 10 78 23 55 4 14 28 29 29 270 FY16 11 82 27 53 4 14 29 29 31 280 FY17 11 83 29 50 4 14 30 29 33 283 FY18 11 84 33 52 4 14 31 29 33 291 FY19 11 86 38 52 4 14 31 29 35 300 FY20 11 87 37 49 4 14 31 29 33 295 FY21 11 88 37 49 4 14 31 29 33 296 FY22 12 87 39 48 4 14 31 29 33 297 FY23 12 87 38 48 4 14 31 29 34 297 FY24 12 89 40 48 4 14 32 29 34 302 FY25 11 88 42 47 4 14 34 29 34 303 FY26 11 89 45 46 2 14 33 29 33 302 FY27 11 91 48 45 1 13 33 29 33 304 306 ship plan FY28 11 90 51 43 0 12 33 29 33 302 FY29 11 88 52 42 0 11 33 29 33 299 FY30 11 86 52 43 0 11 32 29 33 297 FY31 11 82 52 44 0 11 32 29 33 294 FY32 11 81 52 45 0 10 32 29 34 294 FY33 11 81 52 46 0 10 33 29 34 296 FY34 11 80 52 47 0 10 34 29 34 297 FY35 11 82 52 48 0 10 33 29 34 299 FY36 11 84 52 50 0 10 33 29 34 303 FY37 11 86 52 51 0 10 34 29 33 306 FY38 11 88 52 50 0 10 33 29 34 307 FY39 11 90 52 50 0 10 33 29 33 308 FY40 10 90 52 50 0 10 32 29 33 308 FY41 10 90 52 49 0 11 33 29 33 307 FY42 10 88 52 51 0 12 32 29 33 307 FY43 10 88 52 51 0 12 31 29 33 306 Source: FY2014 30-year (FY2014-FY2043) shipbuilding plan. Note: Figures for support ships include five JHSVs transferred from the Army to the Navy and operated by the Navy primarily for the performance of Army missions. Congressional Research Service 5557 Coast Guard Cutter Procurement: Background and Issues for Congress Key: FY = Fiscal Year; CVN = aircraft carriers; LSC = surface combatants (i.e., cruisers and destroyers); SSC = small surface combatants (i.e., frigates, Littoral Combat Ships [LCSs], and mine warfare ships); SSN = attack submarines; SSGN = cruise missile submarines; SSBN = ballistic missile submarines; AWS = amphibious warfare ships; CLF = combat logistics force (i.e., resupply) ships; Supt = support ships. Author Contact Information Ronald O'Rourke Specialist in Naval Affairs rorourke@crs.loc.gov, 7-7610 Congressional Research Service 5658