< Back to Current Version

Coast Guard Polar Security Cutter (Polar Icebreaker) Program: Background and Issues for Congress

Changes from March 26, 2013 to April 25, 2013

This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.


Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Ronald O'Rourke Specialist in Naval Affairs March 26April 25, 2013 Congressional Research Service 7-5700 www.crs.gov RL34391 CRS Report for Congress Prepared for Members and Committees of Congress Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Summary The Coast Guard’s proposed FY2013 budget submission requested $8 million in FY2013 acquisition funding to initiate survey and design activities for a new polar icebreaker, and projected an additional $852 million for acquiring the ship in FY2014-FY2017, including $120 million in FY2014. The Coast Guard’s FY2013 budget anticipated awarding a construction contract for the ship “within the next five years” and taking delivery on the ship “within a decade.” The project to design and build a polar icebreaker was a new acquisition project initiated in the FY2013 budget. The Coast Guard’s proposed FY2014 budget requests $2 million to continue survey and design activities for a new Coast Guard polar icebreaker, or $118 million less than the $120 million that was projected for FY2014 under the FY2013 budget. The proposed FY2014 budget anticipates awarding a construction contract for the ship “within the next four years.” Coast Guard polar icebreakers perform a variety of missions supporting U.S. interests in polar regions. The Coast Guard’s two existing heavy polar icebreakers—Polar Star and Polar Sea— have exceeded their originally intended 30-year service lives. Polar Star was placed in caretaker status on July 1, 2006. Congress in FY2009 and FY2010 provided funding to repair it and return it to service for an additional 7 to 10 years of service; the repair work was completed and the ship was reactivated on December 14, 2012. On June 25, 2010, the Coast Guard announced that Polar Sea had suffered an unexpected engine casualty; the ship was unavailable for operation after that. The Coast Guard placed Polar Sea in commissioned, inactive status on October 14, 2011. Section 222 of the Coast Guard and Maritime Transportation Act of 2012 (H.R. 2838/P.L. 112-213 of December 20, 2012) prohibits the Coast Guard from removing any part of Polar Sea and from transferring, relinquishing ownership of, dismantling, or recycling the ship until it submits a business case analysis of the options for and costs of reactivating the ship and extending its service life to at least September 30, 2022, so as to maintain U.S. polar icebreaking capabilities and fulfill the Coast Guard’s high latitude mission needs, as identified in the Coast Guard’s July 2010 High Latitude Study. The Coast Guard’s third polar icebreaker—Healy—entered service in 2000. Compared to Polar Star and Polar Sea, Healy has less icebreaking capability (it is considered a medium polar icebreaker), but more capability for supporting scientific research. The ship is used primarily for supporting scientific research in the Arctic. The Coast Guard’s proposed FY2013 budget includes $8 million in acquisition funding to initiate survey and design activities for a new polar icebreaker. The Coast Guard’s Five Year Capital Investment Plan includes an additional $852 million in FY2014-FY2017 for acquiring the ship. The Coast Guard anticipates awarding a construction contract for the ship “within the next five years” and taking delivery on the ship “within a decade.” The project to design and build a polar icebreaker is a new acquisition project initiated in the FY2013 budget. With the reactivation of Polar Star, the operational U.S. polar icebreaking fleet consists of one heavy polar icebreaker (Polar Star) and one medium polar icebreaker (Healy). The new polar icebreaker for which initial acquisition funding is requested in the FY2013 budget would replace Polar Star at about the time Polar Star’s 7- to 10-year reactivation period ends. Potential issues for Congress regarding Coast Guard polar icebreaker modernization include the numbers and capabilities of polar icebreakers the Coast Guard will need in the future; the disposition of Polar Sea; whether the new polar icebreaker initiated in the FY2013 budget should be funded with incremental funding (as proposed in the Coast Guard’s Five Year Capital Investment Plan) or full funding in a single year, as normally required under the executive branch’s full funding policy; whether new polar icebreakers should be funded entirely in the Coast Guard With the reactivation of Polar Star, the operational U.S. polar icebreaking fleet consists of one heavy polar icebreaker (Polar Star) and one medium polar icebreaker (Healy). The new polar icebreaker for which initial acquisition funding is requested in the FY2013 budget would replace Polar Star at about the time Polar Star’s 7- to 10-year reactivation period ends. Potential issues for Congress regarding Coast Guard polar icebreaker modernization include the following: • the impact on the project for a new polar icebreaker of the March 1, 2013, sequester on FY2013 funding; • the potential impact on the project for a new polar icebreaker of a possible sequester on FY2014 funding that might occur in late 2013 or early 2014 under the terms of the Budget Control Act of 2011; Congressional Research Service Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress • the sufficiency of the acquisition funding requested for FY2014 for the project for a new polar icebreaker; • the numbers and capabilities of polar icebreakers the Coast Guard will need in the future; • the disposition of Polar Sea; • whether the new polar icebreaker initiated in the FY2013 budget should be funded with incremental funding (as proposed in the Coast Guard’s Five Year Capital Investment Plan) or full funding in a single year, as normally required under the executive branch’s full funding policy; • whether new polar icebreakers should be funded entirely in the Coast Guard budget, or partly or entirely in some other part of the federal budget, such as the Department of Defense (DOD) budget, the National Science Foundation (NSF) budget, or both; whether to provide future icebreaking capability through construction of new ships or service life extensions of existing polar icebreakers; and whether future polar icebreakers should be acquired through a traditional acquisition or a leasing arrangement. Congressional Research Service Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Contents Introduction...................................................................................................................................... 1 Background ...................................................................................................................................... 1 Missions of U.S. Polar Icebreakers ........................................................................................... 1 Current U.S. Polar Icebreakers .................................................................................................. 2 Three Coast Guard Ships..................................................................................................... 2 One National Science Foundation Ship............................................................................... 6 Summary ............................................................................................................................. 6 Recent Studies Relating to Coast Guard Polar Icebreakers ....................................................... 8 Coast Guard High Latitude Study Provided to Congress in July 2011 ............................... 8 January 2011 DHS Office of Inspector General Report .................................................... 11 2010 U.S. Arctic Research Commission Report ............................................................... 13 2007 National Research Council Report ........................................................................... 14 Cost Estimates for Certain Modernization Options ................................................................. 16 New Replacement Ships.................................................................................................... 16 25-Year Service Life Extensions ....................................................................................... 17 Reactivate Polar Sea for Several Years ............................................................................. 17 Funding in FY2013 Budget for New Polar Icebreaker............................................................ 18 Recent Acquisition Steps ............for New Polar Icebreaker ............................................................................................. 20 December 1, 2011, Hearing .. 19 FY2013 Budget Submission................................................................................................... 22 Issues for Congress ...................... 19 FY2014 Budget Submission.................................................................................................. 22 Number and Capabilities of Future Polar Icebreakers 20 Recent Acquisition Steps ............................................................. 22 Factors to Consider............................................. 20 December 1, 2011, Hearing ............................................................... 22 Notional Arguments for Various Numbers ...................................... 22 Issues for Congress .................................. 24 Disposition of Polar Sea ......................................................................................................... 25 Incremental Funding vs. Full Funding ............... 23 Impact of March 1, 2013, Sequester on FY2013 Funding ..................................................................... 26 Funding Ships in Coast Guard Budget or Elsewhere .... 23 Potential Impact of Possible Late 2013/Early 2014 Sequester on FY2014 Funding............... 23 Amount of Acquisition Funding Requested for FY2014.......................................................... 27 New Construction vs. Service Life Extension ........ 23 Number and Capabilities of Future Polar Icebreakers................................................................. 28 Procurement vs. Leasing 23 Factors to Consider......................................................................................................... 29 Legislative Activity in 2012 Following Submission of Proposed FY2013 Budget ....................... 32 FY2013 Funding Request ........................................................................................................ 32 Coast Guard and Maritime Transportation Act of 2012 (H.R. 2838/P.L. 112-213) ................. 33 Coast Guard and Maritime Transportation Act of 2012 (H.R. 5887 of 112th Congress) ......... 35 House... 23 Notional Arguments for Various Numbers ........................................................................ 25 Disposition of Polar Sea .......................................................................................................... 26 Incremental Funding vs. Full Funding ..................................................... 35 Department of Defense, Military Construction and Veterans Affairs, and Full-Year Continuing Appropriations Act, 2013 (H.R. 933 of 113th Congress) ................................... 35 Version Passed by House on March 6, 2013 ................................. 27 Funding Ships in Coast Guard Budget or Elsewhere ................................................................... 35 Version Passed by Senate and House on March 20 and 21, 2013 ..................................... 36 FY2013 Department of Homeland Security Appropriations Act (H.R. 5855/S. 3216 of 112th Congress) ....................... 28 New Construction vs. Service Life Extension .............................................................................................. 36 House.................. 29 Procurement vs. Leasing ............................................................................................................... 36 Senate ........... 30 Legislative Activity for FY2014 ..................................................................................................................... 36 Conference ............ 33 FY2014 Funding Request ............................................................................................................ 37 Congressional Research Service Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress 33 Figures Figure 1. Polar Star and Polar Sea .................................................................................................. 3 Figure 2. Polar Sea .......................................................................................................................... 4 Figure 3. Healy ................................................................................................................................ 5 Congressional Research Service Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Tables Table 1. U.S. Polar Icebreakers........................................................................................................ 7 Table 2. Uses of Coast Guard Polar Icebreakers in FY2005-FY2007 ............................................. 7 Table 3. Funding for Acquisition of New Polar Icebreaker, FY2013-FY2017 .............................. 19 Table 4. Major Icebreakers Around the World ............................................................................... 2425 Appendixes Appendix A. Coast Guard Activities Since 2008 To Assess Requirements and Options for Polar Icebreakers ........................................................................................................................ 3834 Appendix B. Legislative Activity in 111th and 110th Congresses ................................................... 4137 Appendix C. Bill and Report Language Relating to Study of High-Latitude Operations ............. 6056 Appendix D. May 2008 Memorandum from DOD Combatant Commanders ............................... 6258 Contacts Author Contact Information........................................................................................................... 6359 Congressional Research Service Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Introduction This report provides background information and issues for Congress on the sustainment and modernization of the Coast Guard’s polar icebreaker fleet, which performs a variety of missions supporting U.S. interests in polar regions. The Coast Guard’s proposed FY2013FY2014 budget includes $8 million in acquisition funding to initiaterequests $2 million to continue survey and design activities for a new polar icebreaker. The Coast Guard’s Five Year Capital Investment Plan includes an additional $852 million in FY2014-FY2017 for acquiring the ship. The Coast GuardCoast Guard polar icebreaker, or $118 million less than the $120 million that was projected for FY2014 for the new polar icebreaker under the FY2013 budget. The proposed FY2014 budget anticipates awarding a construction contract for the ship “within the next five years” and taking delivery on the ship “within a decadefour years.” The issue for Congress is whether to approve, reject, or modify Coast Guard plans for sustaining and modernizing its polar icebreaking fleet. Congressional decisions on this issue could affect Coast Guard funding requirements, the Coast Guard’s ability to perform its polar missions, and the U.S. shipbuilding industrial base. Background Missions of U.S. Polar Icebreakers The missions of U.S. polar icebreakers can be summarized as follows: • conducting and supporting scientific research in the Arctic and Antarctic; • defending U.S. sovereignty in the Arctic by helping to maintain a U.S. presence in U.S. territorial waters in the region; • defending other U.S. interests in polar regions, including economic interests in waters that are within the U.S. exclusive economic zone (EEZ) north of Alaska; • monitoring sea traffic in the Arctic, including ships bound for the United States; and • conducting other typical Coast Guard missions (such as search and rescue, law enforcement, and protection of marine resources) in Arctic waters, including U.S. territorial waters north of Alaska. Operations to support National Science Foundation (NSF) research activities in the Arctic and Antarctic have accounted in the past for a significant portion of U.S. polar icebreaker operations.1 Supporting NSF research in the Antarctic has included performing—or, in more recent years, standing ready to assist in—an annual mission, called Operation Deep Freeze, to break through the Antarctic ice so as to resupply McMurdo Station, the large U.S. Antarctic research station located on the shore of McMurdo Sound, near the Ross Ice Shelf. 1 This passage, beginning with “The missions of…”, originated in an earlier iteration of this CRS report and was later transferred by GAO with minor changes to Government Accountability Office, Coast Guard[:]Efforts to Identify Arctic Requirements Are Ongoing, but More Communication about Agency Planning Efforts Would Be Beneficial, GAO-10870, September 2010, p. 53. Congressional Research Service 1 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Although polar ice is diminishing due to climate change, observers generally expect that this development will not eliminate the need for U.S. polar icebreakers, and in some respects might increase mission demands for them. Even with the diminishment of polar ice, there are still significant ice-covered areas in the polar regions. Diminishment of polar ice could lead in coming years to increased commercial ship, cruise ship, and naval surface ship operations, as well as increased exploration for oil and other resources, in the Arctic—activities that could require increased levels of support from polar icebreakers.2 Changing ice conditions in Antarctic waters have made the McMurdo resupply mission more challenging since 2000.3 An April 18, 2011, press report states that the Commandant of the Coast Guard, Admiral Robert Papp, sees plenty of reasons the United States will need polar icebreakers for the “foreseeable future,” despite speculation that thinning ice in the Arctic could make the icebreakers replaceable with other ice-hardened ships, the admiral said last week…. “I don’t see that causing us to back down on some minimal level of polar icebreakers,” Papp told Inside the Navy. “The fact of the matter is, there’s still winter ice that’s forming. It’s coming down pretty far. We don't need to get up there just during summer months when there’s open water.”4 Current U.S. Polar Icebreakers The U.S. polar icebreaker fleet currently includes four ships—three Coast Guard ships and one ship operated by the NSF. The ships are described briefly below. Three Coast Guard Ships The Coast Guard’s three polar icebreakers are multimission ships that can break through ice, support scientific research operations, and perform other missions typically performed by Coast Guard ships. Heavy Polar Icebreakers Polar Star and Polar Sea Polar Star (WAGB-10) and Polar Sea (WAGB-11),5 sister ships built to the same general design (Figure 1 and Figure 2), were procured in the early 1970s as replacements for earlier U.S. icebreakers. They were designed for 30-year service lives, and were built by Lockheed Shipbuilding of Seattle, WA, a division of Lockheed that also built ships for the U.S. Navy, but which exited the shipbuilding business in the late 1980s. 2 For more on changes in the Arctic due to diminishment of Arctic ice, see CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke. 3 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington, 2007, pp. 6-7, 14, 63. 4 Cid Standifer, “Adm. Papp: Coast Guard Still Needs Icebreakers For Winter, Antarctic,” Inside the Navy, April 18, 2011. 5 The designation WAGB means Coast Guard icebreaker. More specifically, W means Coast Guard ship, A means auxiliary, G means miscellaneous purpose, and B means icebreaker. Congressional Research Service 2 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The ships are 399 feet long and displace about 13,200 tons.6 They are among the world’s most powerful non-nuclear-powered icebreakers, with a capability to break through ice up to 6 feet thick at a speed of 3 knots. Because of their icebreaking capability, they are considered heavy polar icebreakers. In addition to a crew of 134, each ship can embark a scientific research staff of 32 people. Figure 1. Polar Star and Polar Sea Side by side in McMurdo Sound, Antarctica Source: Coast Guard photo accessed at http://www.uscg.mil/pacarea/cgcpolarsea/history.asp on April 21, 2011. Polar Star was commissioned into service on January 19, 1976, and consequently is now several years beyond its intended 30-year service life. Due to worn out electric motors and other problems, the Coast Guard placed the ship in caretaker status on July 1, 2006.7 Congress in FY2009 and FY2010 provided funding to repair Polar Star and return it to service for 7 to 10 years; the repair work, which reportedly cost about $57 million, was completed, and the ship was reactivated on December 14, 2012.8 The ship is to undergo testing during the summer of 2013, 6 By comparison, the Coast Guard’s new National Security Cutters—its new high-endurance cutters—are about 418 feel long and displace roughly 4,000 tons. 7 Source for July 1, 2006, date: U.S. Coast Guard email to CRS on February 22, 2008. The Coast Guard’s official term for caretaker status is “In Commission, Special.” 8 See, for example, Kyung M. Song, “Icebreaker Polar Star Gets $57 Million Overhaul,” Seattle Times, December 14, 2012. Congressional Research Service 3 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress and be ready for operations in FY2014.9 Although the repair work on the ship was intended to give it another 7 to 10 years of service, an August 30, 2010, press report quoted the Commandant of the Coast Guard, Admiral Robert Papp, as saying, “We’re getting her back into service, but it’s a little uncertain to me how many more years we can get out of her in her current condition, even after we do the engine repairs.”10 Figure 2. Polar Sea Source: Coast Guard photo accessed at http://www.uscg.mil/pacarea/cgcpolarsea/img/PSEApics/FullShip2.jpg on April 21, 2011. Polar Sea was commissioned into service on February 23, 1978, and consequently is also beyond its originally intended 30-year service life. In 2006, the Coast Guard completed a rehabilitation project that extended the ship’s expected service life to 2014. On June 25, 2010, however, the Coast Guard announced that Polar Sea had suffered an unexpected engine casualty, and the ship was unavailable for operation after that.11 The Coast Guard placed Polar Sea in commissioned, 9 Source: Email from Coast Guard Office of Legislative Affairs to CRS, February 23, 2012. Cid Standifer, “Papp: Refurbished Icebreaker Hulls Could Last ‘An Awful Long Time,’” Inside the Navy, August 30, 2010. 11 On June 25, 2010, the Coast Guard announced that POLAR SEA suffered an unexpected engine casualty and will be unable to deploy on its scheduled fall 2010 Arctic patrol and may be unavailable for Operation Deep Freeze [the annual mission to break through the Antarctic ice so as to resupply McMurdo Station], Dec. 20 to Jan 2, 2011. POLAR SEA will likely be in a maintenance status and unavailable for operation until at least January 2011…. Currently, the 420-foot CGC HEALY, commissioned in 1999, is the service’s sole operational polar region icebreaker. While the HEALY is capable of supporting a wide range of Coast Guard missions in the polar regions, it is a medium icebreaker capable of breaking ice up to 4.5-feet thick at three knots. The impact on POLAR SEA’s scheduled 2011 Arctic winter science deployment, scheduled for Jan. 3 to Feb. 23, 2011, is not yet known and depends on the scope of required engine repair. (“Icebreaker POLAR SEA Sidelined By Engine Troubles,” Coast Guard Compass (Official Blog of the U.S. Coast Guard), June 25, 2010.) (continued...) 10 Congressional Research Service 4 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress inactive status on October 14, 2011. The Coast Guard transferred certain major equipment from Polar Sea to Polar Star to facilitate Polar Star’s return to service.12 Medium Polar Icebreaker Healy Healy (WAGB-20) (Figure 3) was procured in the early 1990s as a complement to Polar Star and Polar Sea, and was commissioned into service on August 21, 2000. The ship was built by Avondale Industries, a shipyard located near New Orleans, LA, that built numerous Coast Guard and Navy ships, and which now forms part of Huntington Ingalls Industries (HII).13 Figure 3. Healy Source: Coast Guard photo accessed at http://www.uscg.mil/history/webcutters/Healy_CGC_1_300.jpg on April 21, 2011. Healy is a bit larger than Polar Star and Polar Sea—it is 420 feet long and displaces about 16,000 tons. Compared to Polar Star and Polar Sea, Healy has less icebreaking capability (it is considered a medium polar icebreaker), but more capability for supporting scientific research. (...continued) A June 25, 2010, report stated that “inspections of the Polar Sea’s main diesel engines revealed excessive wear in 33 cylinder assemblies. The Coast Guard is investigating the root cause and hopes to have an answer by August.” (“USCG Cancels Polar Icebreaker’s Fall Deployment,” DefenseNews.com, June 25, 2010.) Another June 25 report stated that “five of [the ship’s] six mighty engines are stilled, some with worn pistons essentially welded to their sleeves.” (Andrew C. Revkin, “America’s Heavy Icebreakers Are Both Broken Down,” Dot Earth (New York Times blog), June 25, 2010.) 12 Source: October 17, 2011, email to CRS from Coast Guard Congressional Affairs office. 13 HII was previously owned by Northrop Grumman, during which time it was known as Northrop Grumman Shipbuilding. Congressional Research Service 5 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The ship can break through ice up to 4½ feet thick at a speed of 3 knots, and embark a scientific research staff of 35 (with room for another 15 surge personnel and two visitors). The ship is used primarily for supporting scientific research in the Arctic. One National Science Foundation Ship The nation’s fourth polar icebreaker is Nathaniel B. Palmer, which was built for the NSF in 1992 by North American Shipbuilding, of Larose, LA. The ship, called Palmer for short, is owned by Edison Chouest Offshore (ECO) of Galliano, LA, a firm that owns and operates research ships and offshore deepwater service ships.14 NSF uses a contractor, Raytheon Polar Services Company (RPSC), to lease the ship from ECO.15 Palmer is considerably smaller than the Coast Guard’s three polar icebreakers—it is 308 feet long and has a displacement of about 6,500 tons. It is operated by a crew of about 22, and can embark a scientific staff of 27 to 37.16 Unlike the Coast Guard’s three polar icebreakers, which are multimission ships, Palmer was purpose-built as a single-mission ship for conducting and supporting scientific research in the Antarctic. It has less icebreaking capability than the Coast Guard’s polar icebreakers, being capable of breaking ice up to 3 feet thick at speeds of 3 knots. This capability is sufficient for breaking through the more benign ice conditions found in the vicinity of the Antarctic Peninsula, so as to resupply Palmer Station, a U.S. research station on the peninsula. Some observers might view Palmer not so much as an icebreaker as an oceanographic research ship with enough icebreaking capability for the Antarctic Peninsula. Palmer’s icebreaking capability is not considered sufficient to perform the McMurdo resupply mission. Summary In summary, the U.S. polar icebreaking fleet currently includes • two heavy polar icebreakers (Polar Star and Polar Sea), one of which is operational, that are designed to perform missions in either polar area, including the challenging McMurdo resupply mission; • one medium polar icebreaker (Healy) that that is used primarily for scientific research in the Arctic; and • one ship (Palmer) that is used for scientific research in the Antarctic. Table 1 summarizes the four ships. Table 2 shows the uses of the three Coast Guard polar icebreakers in FY2005-FY2007 by operational hours. 14 For more on ECO, see the firm’s website at http://www.chouest.com/. For more on RPSC, see the division’s website at http://rpsc.raytheon.com/. 16 Sources vary on the exact number of scientific staff that can be embarked on Palmer. For some basic information on the ship, see http://www.nsf.gov/od/opp/support/nathpalm.jsp, http://www.usap.gov/vesselScienceAndOperations/documents/prvnews_june03.pdfprvnews_june03.pdf, http://nsf.gov/od/opp/antarct/treaty/pdf/plans0607/15plan07.pdf, http://www.nsf.gov/pubs/1996/nsf9693/fls.htm, and http://www.hazegray.org/worldnav/usa/nsf.htm. 15 Congressional Research Service 6 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Table 1. U.S. Polar Icebreakers Polar Star Polar Sea Healy Palmer USCG USCG USCG NSF Yes Yes Yes Noa Yes (reactivated on December 14, 2012) No Yes Yes 1976 1978 2000 1992 Operator U.S.-Government owned? Currently operational? Entered service Length (feet) 399 399 420 308 Displacement (tons) 13,200 13,200 16,000 6,500 Icebreaking capability at 3 knots (ice thickness in feet) Ice ramming capability (ice thickness in feet) Operating temperature Crew (when operational) Additional scientific staff 6 feet 6 feet 4.5 feet 3 feet 21 feet 21 feet 8 feet n/a -60o Fahrenheit 155b 32 -60o Fahrenheit 155b 32 -50o Fahrenheit 85c 35d n/a 22 27-37 Sources: Prepared by CRS using data from U.S. Coast Guard, National Research Council, National Science Foundation, Department of Homeland Security (DHS) Office of Inspector General, and (for Palmer) additional online reference sources. n/a is not available. a. Owned by Edison Chouest Offshore (ECO) of Galliano, LA, and leased to NSF through Raytheon Polar Services Company (RPSC). b. Includes 24 officers, 20 chief petty officers, 102 enlisted, and 9 in the aviation detachment. c. Includes 19 officers, 12 chief petty officers, and 54 enlisted. d. In addition to 85 crew members 85 and 35 scientists, the ship can accommodate another 15 surge personnel and 2 visitors. Table 2. Uses of Coast Guard Polar Icebreakers in FY2005-FY2007 (in mission hours) Mission area SAR ATON Ice Ops MEP LMR PWCS DR Support Total Polar Star FY 06 FY 05 FY 07 Polar Sea FY 06 FY 05 FY 07 31 1,809 FY 05 Healy FY 06 FY 07 2 1,642 2,658 16 3,563 3,210 2,930 256 3,819 424 3,634 94 596 3,620 193 34 2,066 1,642 0 1 1 802 802 121 21 2,818 Source: U.S. Coast Guard data provided to CRS on June 12 and 20, 2008. Notes: SAR = search and rescue; ATON = aids to navigation; Ice Ops = ice operations, polar icebreaking and domestic ice; MEP = marine environmental protection; LMR = living marine resources; PWCS = ports, waterways, and coastal security; DR = defense readiness; Support = includes operations such as training, public affairs, cooperation with federal, state, and local agencies. Congressional Research Service 7 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Regarding the data shown in Table 2, the Coast Guard states further that for CGC [Coast Guard Cutter] HEALY, all of the Polar Operations hours are either transit to/from the operating area or scientific research. For CGC POLAR SEA/POLAR STAR, all of the Polar Operations hours are transit to/from the operating area, scientific research or mobility logistics (icebreaking for re-supply). We estimate 25% transit / 75% scientific research for HEALY and 50% transit / 10% scientific research / 40% mobility logistics for POLAR SEA/POLAR STAR. Recent Studies Relating to Coast Guard Polar Icebreakers A number of studies have been conducted in recent years to assess U.S. requirements for polar icebreakers and options for sustaining and modernizing the Coast Guard’s polar icebreaker fleet. This section presents the findings of some of these studies. Coast Guard High Latitude Study Provided to Congress in July 2011 In July 2011, the Coast Guard provided to Congress a study on the Coast Guard’s missions and capabilities for operations in high-latitude (i.e., polar) areas. The study, commonly known as the High Latitude Study, is dated July 2010 on its cover.17 The High Latitude Study concluded the following: [The study] concludes that future capability and capacity gaps will significantly impact four [Coast Guard] mission areas in the Arctic: Defense Readiness, Ice Operations, Marine Environmental Protection, and Ports, Waterways, and Coastal Security. These mission areas address the protection of important national interests in a geographic area where other nations are actively pursuing their own national goals.... The common and dominant contributor to these significant mission impacts is the gap in polar icebreaking capability. The increasing obsolescence of the Coast Guard’s icebreaker fleet will further exacerbate mission performance gaps in the coming years.... The gap in polar icebreaking capacity has resulted in a lack of at-sea time for crews and senior personnel and a corresponding gap in training and leadership. In addition to providing multi-mission capability and intrinsic mobility, a helicopter-capable surface unit would eliminate the need for acquiring an expensive shore-based infrastructure that may only be needed on a seasonal or occasional basis. The most capable surface unit would be a polar icebreaker. Polar icebreakers can transit safely in a variety of ice conditions and have the endurance to operate far from logistics bases. The Coast Guard’s polar icebreakers have conducted a wide range of planned and unscheduled Coast Guard missions in the past. Polar icebreakers possess the ability to carry large numbers of passengers, cargo, boats, and helicopters. Polar icebreakers also have substantial command, control, and communications capabilities. The flexibility and mobility of polar icebreakers would assist the Coast Guard in closing future mission performance gaps effectively.... Existing capability and capacity gaps are expected to significantly impact future Coast Guard performance in two Antarctic mission areas: Defense Readiness and Ice Operations. Future gaps may involve an inability to carry out probable and easily projected mission 17 For examples of bill and report language in recent years relating to the study of Coast Guard missions and capabilities for operations in high latitude areas, see Appendix C. Congressional Research Service 8 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress requirements, such as the McMurdo resupply, or readiness to respond to less-predictable events. By their nature, contingencies requiring the use of military capabilities often occur quickly. As is the case in the Arctic, the deterioration of the Coast Guard’s icebreaker fleet is the primary driver for this significant mission impact. This will further widen mission performance gaps in the coming years. The recently issued Naval Operations Concept 2010 requires a surface presence in both the Arctic and Antarctic. This further exacerbates the capability gap left by the deterioration of the icebreaker fleet.... The significant deterioration of the Coast Guard icebreaker fleet and the emerging mission demands to meet future functional requirements in the high latitude regions dictate that the Coast Guard acquire material solutions to close the capability gaps.... To meet the Coast Guard mission functional requirement, the Coast Guard icebreaking fleet must be capable of supporting the following missions: • Arctic North Patrol. Continuous multimission icebreaker presence in the Arctic. • Arctic West Science. Spring and summer science support in the Arctic. • Antarctic, McMurdo Station resupply. Planned deployment for break-in, supply ship escort, and science support. This mission, conducted in the Antarctic summer, also requires standby icebreaker support for backup in the event the primary vessel cannot complete the mission. • Thule Air Base Resupply and Polar Region Freedom of Navigation Transits. Provide vessel escort operations in support of the Military Sealift Command’s Operation Pacer Goose; then complete any Freedom of Navigation exercises in the region. In addition, the joint Naval Operations Concept establishes the following mission requirements: • Assured access and assertion of U.S. policy in the Polar Regions. The current demand for this mission requires continuous icebreaker presence in both Polar Regions. Considering these missions, the analysis yields the following findings: • The Coast Guard requires three heavy and three medium icebreakers to fulfill its statutory missions. These icebreakers are necessary to (1) satisfy Arctic winter and transition season demands and (2) provide sufficient capacity to also execute summer missions. Single-crewed icebreakers have sufficient capacity for all current and expected statutory missions. Multiple crewing provides no advantage because the number of icebreakers required is driven by winter and shoulder season requirements. Future use of multiple or augmented crews could provide additional capacity needed to absorb mission growth. • The Coast Guard requires six heavy and four medium icebreakers to fulfill its statutory missions and maintain the continuous presence requirements of the Naval Operations Concept. Consistent with current practice, these icebreakers are single-crewed and homeported in Seattle Washington. • Applying crewing and home porting alternatives reduces the overall requirement to four heavy and two medium icebreakers. This assessment of non-material solutions shows that the reduced number of icebreakers can be achieved by having all Congressional Research Service 9 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress vessels operate with multiple crews and two of the heavy icebreakers homeporting in the Southern Hemisphere. Leasing was also considered as a nonmaterial solution. While there is no dispute that the Coast Guard’s polar icebreaker fleet is in need of recapitalization, the decision to acquire this capability through purchase of new vessels, reconstruction of existing ships, or commercial lease of suitable vessels must be resolved to provide the best value to the taxpayer. The multi-mission nature of the Coast Guard may provide opportunities to conduct some subset of its missions with non government-owned vessels. However, serious consideration must be given to the fact that the inherently governmental missions of the Coast Guard must be performed using government-owned and operated vessels. An interpretation of the national policy is needed to determine the resource level that best supports the nation’s interests.... The existing icebreaker capacity, two inoperative heavy icebreakers and an operational medium icebreaker, does not represent a viable capability to the federal government. The time needed to augment this capability is on the order of 10 years. At that point, around 2020, the heavy icebreaking capability bridging strategy expires.18 At a July 27, 2011, hearing on U.S. economic interests in the Arctic before the Oceans, Atmosphere, Fisheries, and Coast Guard subcommittee of the Senate Commerce, Science, and Transportation Committee, the following exchange occurred: SENATOR OLYMPIA J. SNOWE: On the high latitude study, do you agree with—and those—I would like to also hear from you, Admiral Titley, as well, on these requirements in terms of Coast Guard vessels as I understand it, they want to have—I guess, it was a three medium ice breakers. Am in correct in saying that? Three medium ice breakers. ADMIRAL ROBERT PAPP, COMMANDANT OF THE COAST GUARD: I agree with the mission analysis and as you look at the requirements for the things that we might do up there, if it is in the nation’s interest, it identifies a minimum requirement for three heavy ice breakers and three medium ice breakers and then if you want a persistent presence up there, it would require—and also doing things such as breaking out (inaudible) and other responsibilities, then it would take up to a maximum six heavy and four medium. SNOWE: Right. Do you agree with that? PAPP: If we were to be charged with carrying out those full responsibilities, yes, ma’am. Those are the numbers that you would need to do it. SNOWE: Admiral Titley, how would you respond to the high latitude study and has the Navy conducted its own assessment of its capability? REAR ADMIRAL DAVID TITLEY, OCEANORGRAPHER AND NAVIGATOR OF THE NAVY: Ma’am, we are in the process right now of conducting what we call a capabilities based assessment that will be out in the summer of this year. We are getting ready to finish that—the Coast Guard has been a key component of the Navy’s task force on climate change, literally since day one when the Chief of Naval Operations set this up, that morning, we had the Coast Guard invited as a member of our executive steering committee. 18 United States Coast Guard High Latitude Region Mission Analysis Capstone Summary, July 2010, pp. 10-13, 15. Congressional Research Service 10 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress So we have been working very closely with the Coast Guard, with the Department of Homeland Security, and I think Admiral Papp—said it best as far as the specific comments on the high latitude study but we have been working very closely with the Coast Guard.19 January 2011 DHS Office of Inspector General Report A January 2011 report on the Coast Guard’s polar icebreakers from Department of Homeland Security (DHS) Office of the Inspector General stated: The Coast Guard does not have the necessary budgetary control over its [polar] icebreakers, nor does it have a sufficient number of icebreakers to accomplish its missions in the Polar Regions. Currently, the Coast Guard has only one operational [polar] icebreaker [i.e., Healy], making it necessary for the United States to contract with foreign nations to perform scientific, logistical, and supply activities. Without the necessary budgetary control and a sufficient number of icebreaking assets, the Coast Guard will not have the capability to perform all of its missions, will lose critical icebreaking expertise, and may be beholden to foreign nations to perform its statutory missions. The Coast Guard should improve its strategic approach to ensure that it has the long-term icebreaker capabilities needed to support Coast Guard missions and other national interests in the Arctic and Antarctic regions.20 Regarding current polar icebreaking capabilities for performing Arctic missions, the report states: The Coast Guard’s icebreaking resources are unlikely to meet future demands. [The table below] outlines the missions that Coast Guard is unable to meet in the Arctic with its current icebreaking resources. Arctic Missions Not Being Met Requesting Agency United States Coast Guard Missions Not Being Met —Fisheries enforcement in Bering Sea to prevent foreign fishing in U.S. waters and overfishing —Capability to conduct search and rescue in Beaufort Sea for cruise line and natural resource exploration ships —Future missions not anticipated to be met: 2010 Arctic Winter Science Deployment NASA Winter access to the Arctic to conduct oceanography and study Arctic currents and how they relate to regional ice cover, climate, and biology NOAA and NSF Winter research 19 Source: Transcript of hearing. Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 1 (Executive Summary). Report accessed September 21, 2011, at http://www.dhs.gov/xoig/assets/mgmtrpts/OIG_11-31_Jan11.pdf. 20 Congressional Research Service 11 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Department of Defense Assured access to ice-impacted waters through a persistent icebreaker presence in the Arctic and Antarctic21 The report also states: Should the Coast Guard not obtain funding for new icebreakers or major service life extensions for its existing icebreakers with sufficient lead-time, the United States will have no heavy icebreaking capability beyond 2020 and no polar icebreaking capability of any kind by 2029. Without the continued use of icebreakers, the United States will lose its ability to maintain a presence in the Polar Regions, the Coast Guard’s expertise to perform ice operations will continue to diminish, and missions will continue to go unmet.22 Regarding current polar icebreaking capabilities for performing Antarctic missions, the report states: The Coast Guard needs additional icebreakers to accomplish its missions in the Antarctic. The Coast Guard has performed the McMurdo Station resupply in Antarctica for decades, but with increasing difficulty in recent years. The Coast Guard’s two heavy-duty icebreakers [i.e., Polar Star and Polar Sea] are at the end of their service lives, and have become less reliable and increasingly costly to keep in service…. In recent years, the Coast Guard has found that ice conditions in the Antarctic have become more challenging for the resupply of McMurdo Station. The extreme ice conditions have necessitated the use of foreign vessels to perform the McMurdo break-in…. As ice conditions continue to change around the Antarctic, two icebreakers are needed for the McMurdo break-in and resupply mission. Typically, one icebreaker performs the breakin and the other remains on standby. Should the first ship become stuck in the ice or should the ice be too thick for one icebreaker to complete the mission, the Coast Guard deploys the ship on standby. Since the Polar Sea and Polar Star are not currently in service, the Coast Guard has no icebreakers capable of performing this mission. [The table below] outlines the missions that will not be met without operational heavy-duty icebreakers. Arctic Missions Not Being Met Requesting Agency Missions Not Being Met NSF Missions not anticipated to be met: 2010-2011 Operation Deep Freeze – McMurdo Station Resupply Department of State Additional inspections of foreign facilities in Antarctica to enforce the Antarctic Treaty and ensure facilities’ environment compliance23 21 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 9. 22 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 10. 23 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, pp. 10-11. Congressional Research Service 12 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The report’s conclusion and recommendations were as follows: Conclusion With an aging fleet of three icebreakers, one operational and two beyond their intended 30year service life, the Coast Guard is at a critical crossroads in its Polar Icebreaker Maintenance, Upgrade, and Acquisition Program. It must clarify its mission requirements, and if the current mission requirements remain, the Coast Guard must determine the best method for meeting these requirements in the short and long term. Recommendations We recommend that the Assistant Commandant for Marine Safety, Security, and Stewardship: Recommendation #1: Request budgetary authority for the operation, maintenance, and upgrade of its icebreakers. Recommendation #2: In coordination with the Department of Homeland Security, request clarification from Congress to determine whether Arctic missions should be performed by Coast Guard assets or contracted vessels. Recommendation #3: In coordination with the Department of Homeland Security, request clarification from Congress to determine whether Antarctic missions should be performed by Coast Guard assets or contracted vessels. Recommendation #4: Conduct the necessary analysis to determine whether the Coast Guard should replace or perform service-life extensions on its two existing heavy-duty icebreaking ships. Recommendation #5: Request appropriations necessary to meet mission requirements in the Arctic and Antarctic.24 The report states that The Coast Guard concurred with all five of the recommendations and is initiating corrective actions. We consider the recommendations open and unresolved. The Coast Guard provided information on some of its ongoing projects that will address the program needs identified in the report.25 2010 U.S. Arctic Research Commission Report A May 2010 report from the U.S. Arctic Research Commission (USARC) on goals and objectives for Arctic research for 2009-2010 stated: To have an effective Arctic research program, the United States must invest in human capital, research platforms, and infrastructure, including new polar class icebreakers, and 24 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 12. 25 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance, Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 13. Congressional Research Service 13 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress sustained sea, air, land, space, and social observing systems…. The Commission urges the President and Congress to commit to replacing the nation’s two polar class icebreakers.26 2007 National Research Council Report A 2007 National Research Council (NRC) report, Polar Icebreakers in a Changing World: An Assessment of U.S. Needs, assessed roles and future needs for Coast Guard polar icebreakers.27 The study was required by report language accompanying the FY2005 DHS appropriations act (H.R. 4567/P.L. 108-334).28 The study was completed in 2006 and published in 2007. Some sources refer to the study as the 2006 NRC report. The report made the following conclusions and recommendations: Based on the current and future needs for icebreaking capabilities, the [study] committee concludes that the nation continues to require a polar icebreaking fleet that includes a minimum of three multimission ships [like the Coast Guard’s three current polar icebreakers] and one single-mission [research] ship [like Palmer]. The committee finds that although the demand for icebreaking capability is predicted to increase, a fleet of three multimission and one single-mission icebreakers can meet the nation’s future polar icebreaking needs through the application of the latest technology, creative crewing models, wise management of ice conditions, and more efficient use of the icebreaker fleet and other assets. The nation should immediately begin to program, design, and construct two new polar icebreakers to replace the POLAR STAR and POLAR SEA. Building only one new polar icebreaker is insufficient for several reasons. First, a single ship cannot be in more than one location at a time. No matter how technologically advanced or efficiently operated, a single polar icebreaker can operate in the polar regions for only a portion of any year. An icebreaker requires regular maintenance and technical support from shipyards and industrial facilities, must reprovision regularly, and has to effect periodic crew 26 U.S. Arctic Research Commission, Report on Goals and Objectives for Arctic Research 2009–2010, May 2010, p. 4. Accessed online December 5, 2011, at http://www.arctic.gov/publications/usarc_2009-10_goals.pdf. 27 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington, 2007, 122 pp. 28 H.R. 4567/P.L. 108-334 of October 18, 2004. The related Senate bill was S. 2537. The Senate report on S. 2537 (S.Rept. 108-280 of June 17, 2004) stated: The Committee expects the Commandant to enter into an arrangement with the National Academy of Sciences to conduct a comprehensive study of the role of Coast Guard icebreakers in supporting United States operations in the Antarctic and the Arctic. The study should include different scenarios for continuing those operations including service life extension or replacement of existing Coast Guard icebreakers and alternative methods that do not use Coast Guard icebreakers. The study should also address changes in the roles and missions of Coast Guard icebreakers in support of future marine operations in the Arctic that may develop due to environmental change, including the amount and kind of icebreaking support that may be required in the future to support marine operations in the Northern Sea Route and the Northwest Passage; the suitability of the Polar Class icebreakers for these new roles; and appropriate changes in existing laws governing Coast Guard icebreaking operations and the potential for new operating regimes. The study should be submitted to the Committee no later than September 30, 2005. The conference report on H.R. 4567 (H.Rept. 108-774 of October 9, 2004) stated: As discussed in the Senate report and the Coast Guard authorization bill for fiscal year 2005, the conferees require the National Academy of Sciences to study the role of Coast Guard icebreakers. The earlier House report on H.R. 4567 (H.Rept. 108-541 of June 15, 2004) contained language directing a similar report from the Coast Guard rather than the National Academies. (See the passage in the House report under the header “Icebreaking.”) Congressional Research Service 14 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress changeouts. A single icebreaker, therefore, could not meet any reasonable standard of active and influential presence and reliable, at-will access throughout the polar regions. A second consideration is the potential risk of failure in the harsh conditions of polar operations. Despite their intrinsic robustness, damage and system failure are always a risk and the U.S. fleet must have enough depth to provide backup assistance. Having only a single icebreaker would necessarily require the ship to accept a more conservative operating profile, avoiding more challenging ice conditions because reliable assistance would not be available. A second capable icebreaker, either operating elsewhere or in homeport, would provide ensured backup assistance and allow for more robust operations by the other ship. From a strategic, longer-term perspective, two new Polar class icebreakers will far better position the nation for the increasing challenges emerging in both polar regions. A second new ship would allow the U.S. Coast Guard to reestablish an active patrol presence in U.S. waters north of Alaska to meet statutory responsibilities that will inevitably derive from increased human activity, economic development, and environmental change. It would allow response to emergencies such as search-and-rescue cases, pollution incidents, and assistance to ships threatened with grounding or damage by ice. Moreover, a second new ship will leverage the possibilities for simultaneous operations in widely disparate geographic areas (e.g., concurrent operations in the Arctic and Antarctic), provide more flexibility for conducting Antarctic logistics (as either the primary or the secondary ship for the McMurdo break-in), allow safer multiple-ship operations in the most demanding ice conditions, and increase opportunities for international expeditions. Finally, an up-front decision to build two new polar icebreakers will allow economies in the design and construction process and provide a predictable cost reduction for the second ship…. The [study] committee finds that both operations and maintenance of the polar icebreaker fleet have been underfunded for many years, and the capabilities of the nation’s icebreaking fleet have diminished substantially. Deferred long-term maintenance and failure to execute a plan for replacement or refurbishment of the nation’s icebreaking ships have placed national interests in the polar regions at risk. The nation needs the capability to operate in both polar regions reliably and at will. Specifically, the committee recommends the following: • The United States should continue to project an active and influential presence in the Arctic to support its interests. This requires U.S. government polar icebreaking capability to ensure year-round access throughout the region. • The United States should continue to project an active and influential presence in the Antarctic to support its interests. The nation should reliably control sufficient icebreaking capability to break a channel into and ensure the maritime resupply of McMurdo Station. • The United States should maintain leadership in polar research. This requires icebreaking capability to provide access to the deep Arctic and the ice-covered waters of the Antarctic. • National interests in the polar regions require that the United States immediately program, budget, design, and construct two new polar icebreakers to be operated by the U.S. Coast Guard. • To provide continuity of U.S. icebreaking capabilities, the POLAR SEA should remain mission capable and the POLAR STAR should remain available for reactivation until the new polar icebreakers enter service. Congressional Research Service 15 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress • The U.S. Coast Guard should be provided sufficient operations and maintenance budget to support an increased, regular, and influential presence in the Arctic. Other agencies should reimburse incremental costs associated with directed mission tasking. • Polar icebreakers are essential instruments of U.S. national policy in the changing polar regions. To ensure adequate national icebreaking capability into the future, a Presidential Decision Directive should be issued to clearly align agency responsibilities and budgetary authorities.29 The Coast Guard stated in 2008 that it “generally supports” the NRC report, and that the Coast Guard “is working closely with interagency partners to determine a way forward with national polar policy that identifies broad U.S. interests and priorities in the Arctic and Antarctic that will ensure adequate maritime presence to further these interests. Identification and prioritization of U.S. national interests in these regions should drive development of associated USCG [U.S. Coast Guard] capability and resource requirements.” The Coast Guard also stated: “Until those broad U.S. interests and priorities are identified, the current USG [U.S. Government] polar icebreaking fleet should be maintained in an operational status.”30 Cost Estimates for Certain Modernization Options New Replacement Ships The Coast Guard estimated in February 2008 that new replacement ships for the Polar Star and Polar Sea might cost between $800 million and $925 million per ship in 2008 dollars to procure.31 The Coast Guard said that this estimate is based on a ship with integrated electric drive, three propellers, and a combined diesel and gas (electric) propulsion plant. The icebreaking capability would be equivalent to the POLAR Class Icebreakers [i.e., Polar Star and Polar Sea] and research facilities and accommodations equivalent to HEALY. This cost includes all shipyard and government project costs. Total time to procure a new icebreaker [including mission analysis, studies, design, contract award, and construction] is eight to ten years.32 The Coast Guard further stated that this notional new ship would be designed for a 30-year service life. 29 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington, 2007, pp. 2-3. 30 Coast Guard point paper provided to CRS on February 12, 2008, and dated with the same date, providing answers to questions from CRS concerning polar icebreaker modernization. 31 Coast Guard point paper provided to CRS on February 12, 2008, and dated with the same date, providing answers to questions from CRS concerning polar icebreaker modernization. 32 The Coast Guard states further that the estimate is based on the procurement cost of the Mackinaw (WAGB-30), a Great Lakes icebreaker that was procured a few years ago and commissioned into service with the Coast Guard in June 2006. The Mackinaw is 240 feet long, displaces 3,500 tons, and can break ice up to 2 feet, 8 inches thick at speeds of 3 knots, which is suitable for Great Lakes icebreaking. The Coast Guard says it scaled up the procurement cost for the Mackinaw in proportion to its size compared to that of a polar icebreaker, and then adjusted the resulting figure to account for the above-described capabilities of the notional replacement ship and recent construction costs at U.S. Gulf Coast shipyards. Congressional Research Service 16 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The High Latitude Study provided to Congress in July 2011 states that the above figure of $800 million to $925 million in 2008 dollars equates to $900 million to $1,041 million in 2012 dollars. The study provides the following estimates, in 2012 dollars, of the acquisition costs for new polar icebreakers: • $856 million for 1 ship; • $1,663 million for 2 ships—an average of about $832 million each; • $2,439 million for 3 ships—an average of $813 million each; • $3,207 million for 4 ships—an average of about $802 million each; • $3,961 million for 5 ships—an average of about $792 million each; and • $4,704 million for 6 ships—an average of $784 million each. The study refers to the above estimates as “rough order-of-magnitude costs” that “were developed as part of the Coast Guard’s independent Polar Platform Business Case Analysis.”33 25-Year Service Life Extensions The Coast Guard stated in February 2008 that performing the extensive maintenance, repair, and modernization work needed to extend the service lives of the two ships by 25 years might cost roughly $400 million per ship. This figure, the Coast Guard said, is based on assessments made by independent contractors for the Coast Guard in 2004. The service life extension work, the Coast Guard said, would improve the two icebreakers’ installed systems in certain areas. Although the work would be intended to permit the ships to operate for another 25 years, it would not return the cutters to new condition.34 An August 30, 2010, press report stated that the Commandant of the Coast Guard, Admiral Robert Papp, estimated the cost of extending the lives of Polar Star and Polar Sea at about $500 million per ship; the article quoted Papp as stating that Polar Star and Polar Sea “were built to take a beating. They were built with very thick special steel, so you might be able to do a renovation on them and keep going…. I think there are certain types of steel that, if properly maintained, they can go on for an awful long time. What the limit is, I’m not sure.”35 Reactivate Polar Sea for Several Years Regarding the potential cost to repair Polar Sea and return it to service, at a December 1, 2011, hearing that focused on the polar icebreaker fleet (see “December 1, 2011, Hearing” below), Dave Whitcomb, the chief operating officer of Vigor Industrial—the owner of the shipyard that has conducted maintenance and repair work on Polar Sea and Polar Star for many years—testified that Polar Sea 33 United States Coast Guard High Latitude Region Mission Analysis Capstone Summary, July 2010, p. 13. Coast Guard point paper provided to CRS on February 12, 2008, and dated with the same date, providing answers to questions from CRS concerning polar icebreaker modernization. 35 Cid Standifer, “Papp: Refurbished Icebreaker Hulls Could Last ‘An Awful Long Time,’” Inside the Navy, August 30, 2010. Ellipsis as in original. 34 Congressional Research Service 17 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress can be restored to full mission readiness with a comparable longevity [to that of Polar Star] at relatively modest cost and in a reasonably short period of time. Vigor Industrial estimates that bringing the Polar Sea up to an operationally capable condition would require approximately 11 million dollars. We base this on the fact that we have done comparable work on the Polar Star already and are well aware of what is required.… This work would require approximately two years to complete and might well be finished faster depending on availability of key components.36 Whitcomb further testified that the above estimated cost of $11 million includes overhauling the ship’s diesel engines ($5 million), replacing the ship’s obsolete cranes ($3 million), and upgrading the ship’s propellers ($3 million). Whether the work described above includes everything that would be needed to return Polar Sea to service is not clear, particularly given that the Coast Guard transferred certain major equipment from Polar Sea to Polar Star to facilitate Polar Star’s return to service.37 At a March 7, 2012, hearing before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure on the proposed FY2013 budgets for the Coast Guard and maritime transportation programs, Representative Rick Larsen asked Admiral Papp about the possibility of returning Polar Sea. Papp replied: ADMIRAL PAPP: I don’t have room in my budget regardless of what it [the cost to repair Polar Sea] is. I think a lot of people underestimated how much it would cost to reactivate the Polar Sea. We’re actually having to use parts of Polar Sea... REPRESENTATIVE LARSEN: Right. ADMIRAL PAPP: ...to reactivate Polar Star. So I think there are some people who are enthusiastic about the potential for getting Polar Sea back out there, but the fact of the matter is I don’t have the money to operate it. And I think it’s much more expensive to reactivate it than some people are giving in terms of estimates. I would say it’s probably an [sic: in] excess of what we’re spending on Polar Star right now would be to get her back out there.38 Funding in FY2013 Budget for New Polar Icebreaker The Coast Guard’s proposed FY2013 budget includes $8 million in acquisition funding to initiate survey and design activities for a new polar icebreaker. The Coast Guard’s Five Year Capital Investment Plan includes an additional $852 million in FY2014-FY2017 for acquiring the ship. 36 Testimony [prepared statement] of Dave Whitcomb, Chief Operating Officer, Vigor Industrial, [before the] House Coast Guard and Maritime Transportation Subcommittee, December 1, 2011, p. 3. 37 Testimony [prepared statement] of Dave Whitcomb, Chief Operating Officer, Vigor Industrial, [before the] House Coast Guard and Maritime Transportation Subcommittee, December 1, 2011, p. 5. 38 Source: Transcript of hearing. Congressional Research Service 18 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Funding for New Polar Icebreaker FY2013 Budget Submission The Coast Guard’s proposed FY2013 budget requested $8 million in acquisition funding to initiate survey and design activities for a new polar icebreaker. The Coast Guard’s FY2013 Five Year Capital Investment Plan included an additional $852 million in FY2014-FY2017 for acquiring the ship. (This funding is located in the Coast Guard’s Acquisition, Construction, and Improvements Improvements (AC&I) appropriation account. ) The Coast Guard anticipates ’s FY2013 budget anticipated awarding a construction contract for the ship “within the next five years” and taking delivery on the ship “within a decade.” The project to design and build a polar icebreaker iswas a new acquisition project initiated in the FY2013 budget. Table 3 shows fundingthe funding that was in the Coast Guard’s FY2013-FY2017 Five Year Capital Investment Plan for the acquisition of a new polar icebreaker. This funding, which totalstotaled $860 million, doesdid not necessarily represent the entire acquisition cost of the ship; some additional funding might be have been required after FY2017. Prior estimates for the acquisition cost of a new polar icebreaker (see “Cost Estimates for Certain Modernization Options” above) and the bell-curvebellcurve-like funding profile shown in Table 3 suggest that if any additional funding is required after FY2017, the amount might be less than the FY2017 figure of $82 million. As shown in Table 3, the Coast Guard isin its FY2013 budget submission was proposing to fund the acquisition of this ship using incremental funding (i.e., through a series of annual funding increments). Table 3. Funding for Acquisition of New Polar Icebreaker, FY2013-FY2017 Millions of then-year dollars FY13 FY14 FY15 FY16 FY17 Total acquisition cost 8 120 380 270 82 TBD Source: Coast Guard FY2013-FY2017 Five Year Capital Investment Plan, as shown in U.S. Department of Homeland Security, Annual Performance Report, Fiscal Years 2011 – 2013, p. CG-AC&I-12 (pdf page 1,749 of 3,134). Regarding the $8 million requested for FY2013, the Department of Homeland Security, the parent department of the Coast Guard, statesstated: This funding will initiate survey and design activities for a new Coast Guard polar icebreaker, intended to provide continued U.S. Arctic icebreaking capability following the projected end of service life of the CGC POLAR STAR on or about 2022. This effort will build upon requirements analyses undertaken within the past three years, including the HighLatitude Mission Analysis Report, and the Polar Icebreaker Business Case Analysis. In recognition of emerging operational risks in the Arctic regions, the Coast Guard is committed to developing and implementing an acquisition plan that will ensure seamless and expeditious availability of icebreaking capacity to meet its missions. Specifically, the Coast Guard will deliver a fully operational polar icebreaker within a decade. Congressional Research Service 19 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress This funding will be used to develop programmatic planning documents required under the USCG Major Systems Acquisition Manual, including an Analysis of Alternatives, a Life Cycle Cost Estimate, a Cost Benefit Analysis (CBA), modeling simulation and testing (as required) to build a modern polar icebreaker. These efforts will lead to development of a formal icebreaker acquisition project, with the award for construction anticipated within the next five years. As conditions in the Arctic evolve, and maritime activity grows, the requirement for sustained surface presence, capable of operating in the ice-covered waters of the Polar Congressional Research Service 19 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress regions remains critical. This project will maintain a National icebreaking capability through an efficient, timely and cost effective acquisition.39 regions remains critical. This project will maintain a National icebreaking capability through an efficient, timely and cost effective acquisition.39 FY2014 Budget Submission The Coast Guard’s proposed FY2014 budget requests $2 million to continue survey and design activities for a new Coast Guard polar icebreaker, or $118 million less than the $120 million that was projected for FY2014 under the FY2013 budget. The Coast Guard states that This funding will be used to continue development of programmatic planning documents required under the USCG Major Systems Acquisition Manual, including an Analysis of Alternatives, a Life Cycle Cost Estimate, modeling simulation and testing (as required) to build a modern polar icebreaker. Together with funding provided in 2013, Coast Guard will complete the Mission Needs Statement, the Concept of Operations, and the Preliminary Operational Requirements Document. These efforts will lead to development of a formal icebreaker acquisition project, with the award for construction anticipated within the next four years.40 The Coast Guard testified on April 16, 2013, that it anticipates submitting its FY2014 Five Year (FY2014-FY2018) Capital Investment Plan on May 1, 2013.41 Recent Acquisition Steps A February 4, 2013, press report stated, “The Coast Guard last week issued a Request for Information (RFI) to conduct market research for candidate heavy polar icebreaker designs and shipyards in the United States capable of building a heavy polar icebreaker. The RFI is a first step toward a possible polar non-nuclear icebreaker procurement program to help the Coast Guard develop an acquisition strategy for such a vessel.”4042 A February 28, 2013 Coast Guard news release stated: 39 U.S. Department of Homeland Security, Annual Performance Report, Fiscal Years 2011 – 2013, p. CG-AC&I-40 (pdf page 1,777 of 3,134). 40 Department of Homeland Security, United States Coast Guard, Fiscal Year 2014 Congressional Justification, p. CGAC&I-32 (pdf page 204 of 403). 41 Source: Transcript of April 16, 2013, hearing before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee on the proposed FY2014 budget for the Coast Guard and maritime transportation. 42 “Wanted: Icebreaker Designs,” Defense Daily, February 4, 2013: 3. Congressional Research Service 20 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Long before any drawings are made or steel cut in the shipyard, the Coast Guard has taken a deliberative approach to defining its mission needs [for a new heavy polar icebreaker]. To drive the beginning stages of the acquisition project, the Coast Guard has assembled a 42member integrated project team (IPT) composed of experts from 28 different Coast Guard offices as well as representatives from eight other government agencies, including the National Science Foundation (NSF) and the Department of State. The project has relied on a small subset of IPT members from the Office of Cutter Forces, Office of Requirements and Analysis, Office of Waterways and Ocean Policy, and the Acquisition Directorate to draft preliminary documents that will direct activities under any future acquisition project. The IPT built off the mission gaps identified in the Mission Analysis Report and has now completed the Mission Needs Statement, which defines what is needed to address those gaps. Lt. Cmdr. Greg Daughtry, chief requirements officer in the Office of Requirements and Analysis, said the team has now begun work to develop the Concept of Operations (CONOPS). “The CONOPS will describe how the organization plans to utilize and maintain capability. It will describe how and where we intend to operate from a multi-mission standpoint, including defense readiness, search and rescue, law enforcement and scientific purposes,” Daughtry said. Recent International Collaboration On Feb. 7, 2013, members of the Canadian Coast Guard’s polar icebreaking program visited Coast Guard Headquarters in Washington, D.C., to meet with their counterparts in the Service’s acquisition community and discuss mutual interests. During the meeting, representatives signed an annex to a 2009 U.S.–Canadian shipbuilding memorandum of understanding, codifying ongoing cooperation between the two nations’ efforts to obtain a polar icebreaker. The Canadians announced their polar icebreaker acquisition project in 2008 and have completed the preliminary design phase as well as ice tank trials with three different models. In the next few months, they will choose a model to move forward into detailed design and 39 U.S. Department of Homeland Security, Annual Performance Report, Fiscal Years 2011 – 2013, p. CG-AC&I-40 (pdf page 1,777 of 3,134). 40 “Wanted: Icebreaker Designs,” Defense Daily, February 4, 2013: 3. Congressional Research Service 20 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress construction. During the week of Feb. 18th, 2013, IPT members traveled to Vancouver to observe the design selection process, said Cmdr. Tim Newton, the Acquisition Directorate’s heavy polar icebreaker assistant project manager. “We were able to see some of the challenges they’re having with setting up a single-ship program—something they haven’t done in many years. We were able to look at some of the issues they’ve dealt with and hopefully avoid some of those same problems,” Newton said. The Coast Guard has also reached out to the Finnish government for assistance. Finland has a wealth of icebreaking expertise, as 80 percent of their trade comes in through the icy Baltic Sea. The Finns have provided information on the state of today’s icebreaker market. Icebreaker Experience and Lessons Learned At the core of the IPT is Lt. Cmdr. Kristen Serumgard, polar icebreaker platform manager in the Office of Cutter Forces and sponsor’s representative for the heavy polar icebreaker project. Serumgard is approaching her 13th year of active duty with the Coast Guard, a third of which was served on icebreaking cutters. Congressional Research Service 21 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress On her first tour of duty, she served as deck watch officer aboard the 399-foot heavy polar icebreaker Coast Guard Cutter Polar Sea (WAGB 11), including two patrols to Antarctica as part of Operation Deep Freeze, an annual mission supporting the NSF to resupply McMurdo Station. She also served two years aboard Coast Guard Cutter Hollyhock (WLB 214), an icecapable 225-foot Juniper-class Seagoing Buoy Tender homeported in Port Huron, Mich. Serumgard’s icebreaking experience is a tremendous benefit at this point in the acquisition project lifecycle. “Much of the subject matter experts’ experience is in temperate waters,” she said. “So an understanding of polar conditions is very important and vital to the requirements gathering process.” In addition, her close relationship with the Coast Guard’s icebreaker community is a direct line to their input and expertise. The Service’s icebreaker fleet is small, and those who serve aboard these vessels consider themselves very much a family. “We have a very small group of operators and engineers who have actually served on these vessels and understand how they operate, what events are going on, and what needs to happen,” Serumgard said. The IPT is also leveraging the Service’s past experience by looking at lessons learned from two previous icebreaker acquisitions: Coast Guard Cutter Healy (WAGB 20), a 420-foot medium polar icebreaker that was commissioned in 1999 and now is the United States’ newest and most technologically advanced polar icebreaker, and Coast Guard Cutter Mackinaw (WLBB 30), a 240-foot Great Lakes icebreaker commissioned in 2006. Even though the acquisition strategy and construction process for a single hull is different than a cutter fleet, the team is also looking at how best practices and lessons learned from the Coast Guard’s National Security Cutter, Offshore Patrol Cutter, and Fast Response Cutter acquisitions could apply to the heavy polar icebreaker program.41 41 Coast Guard news release, “Coast Guard Heavy Polar Icebreaker Project Taking Shape,” February 28, 2013, accessed March 26, 2013, at http://www.uscg.mil/hq/cg9/newsroom/updates/icebreaker022813.asp. Congressional Research Service 21 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress43 December 1, 2011, Hearing On December 1, 2011, the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee held a hearing entitled “Protecting U.S. Sovereignty: Coast Guard Operations in the Arctic.” The primary (though not only) topic discussed at the hearing was the Coast Guard’s polar icebreaker fleet. Witnesses included the Commandant of the Coast Guard, the lieutenant governor of Alaska, a director from the Government Accountability Office (GAO), a deputy director from the NSF, the chief operating officer of a shipyard that has conducted maintenance and repair work on Polar Sea and Polar Star for many years, and a retired Coast Guard admiral who spent much of his career on Coast Guard polar icebreakers. The prepared statements of the witnesses and the subcommittee’s background memorandum for the hearing are available from the committee’s website.42 Issues for Congress The issue of Coast Guard polar icebreaker modernization presents several potential issues for Congress, including but not necessarily limited to those discussed below.44 43 Coast Guard news release, “Coast Guard Heavy Polar Icebreaker Project Taking Shape,” February 28, 2013, accessed March 26, 2013, at http://www.uscg.mil/hq/cg9/newsroom/updates/icebreaker022813.asp. 44 As of December 5, 2011, the materials were posted online at http://transportation.house.gov/hearings/ hearingdetail.aspx?NewsID=1458. Congressional Research Service 22 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Issues for Congress Impact of March 1, 2013, Sequester on FY2013 Funding One issue for Congress concerns the impact on the project for a new polar icebreaker of the March 1, 2013, sequester on FY2013 funding, particularly in terms of the Coast Guard’s ability to complete the survey and design activities for a new polar icebreaker that were planned for FY2013. Potential Impact of Possible Late 2013/Early 2014 Sequester on FY2014 Funding Another potential issue for Congress concerns the potential impact on the project for a new polar icebreaker of a possible sequester on FY2014 funding that might occur in late 2013 or early 2014 under the terms of the Budget Control Act of 2011 (S. 365/P.L. 112-25 of August 2, 2011). Amount of Acquisition Funding Requested for FY2014 Another potential issue for Congress concerns the sufficiency of the acquisition funding requested for FY2014 for the project for a new polar icebreaker. As noted earlier, the $2 million requested for FY2014 is $118 million less than the $120 million that was projected for FY2014 under the Coast Guard’s FY2013 budget submission. Potential oversight questions include the following: • Why was FY2014 funding for a new polar icebreaker reduced from a projected $120 million under the FY2013 budget submission to an actual request for $2 million under the FY2014 budget? • What activities in support of a new polar icebreaker that were projected for FY2014 under the FY2013 budget are no longer planned for FY2014 under the FY2014 budget? • In light of the steep reduction in FY2014 acquisition funding compared to what that funding was projected to be under the FY2013 budget, why is the Coast Guard confident that it will still be able to award a construction contract for the ship within the next four years? How much schedule risk, if any, does this reduction in FY2014 funding add to the project for acquiring a new polar icebreaker? Number and Capabilities of Future Polar Icebreakers Factors to Consider Another potential issue for Congress is how many polar icebreakers, with what capabilities, the Coast Guard will need in the future. In assessing this issue, factors that Congress may consider include, but are not limited to, the following: Congressional Research Service 23 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress • current and projected mission demands for Coast Guard polar icebreakers as analyzed in the High Latitude Study and other recent studies, including an assessment of how those demands might be affected by NSF decisions on how to acquire icebreaking services to support its research activities; • the potential for various mission demands (not just those conducted in support of NSF research activities) to be met by non-Coast Guard icebreakers, including leases or charters of icebreakers owned by foreign governments or private firms; and • the Coast Guard’s overall missions-vs.-resources situation, which includes the Coast Guard’s requirements to perform many non-polar missions and the Coast Guard’s desire to fund programs for performing these non-polar missions.4345 Regarding the first factor above, the NSF states that although Coast Guard polar icebreakers are very capable, the NSF is mandated by presidential directive to perform its research activities in the most cost-effective way possible, and that it can be more expensive for NSF to support its 42 As of December 5, 2011, the materials were posted online at http://transportation.house.gov/hearings/ hearingdetail.aspx?NewsID=1458. 43 For more on some of these other programs, see CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. Congressional Research Service 22 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress research activities with Coast Guard polar icebreakers than with charters of icebreakers crewed by contractor personnel. Although Coast Guard polar icebreakers in the past have performed the annual McMurdo break-in mission, the NSF in recent years has chartered Russian and Swedish contractor-operated icebreakers to perform the mission (with a Coast Guard polar icebreaker standing ready to assist if needed). The NSF has also noted that Healy, though very capable in supporting Arctic research, operates at sea for about 200 days a year, as opposed to about 300 days a year for foreign contractor-operated polar icebreakers. Regarding the second factor above, issues to consider would include, among other things, the potential availability of ships for lease, leasing costs, regulatory issues relating to long-term leases of capital assets for the U.S. government, and the ability of leased ships to perform the missions in question, including the mission of defending U.S. sovereignty in Arctic waters north of Alaska, the challenging McMurdo resupply mission, or missions that emerge suddenly in response to unexpected events.4446 Regarding the first two factors above, some observers note the size of the polar icebreaking fleets operated by other countries. Countries with interests in the polar regions have differing requirements for polar icebreakers, depending on the nature and extent of their polar activities. Table 4 shows a Coast Guard summary of major icebreakers around the world. 4445 For more on some of these other programs, see CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. 46 The potential for using leased ships, and the possible limitations of this option, are discussed at several points in the 2007 NRC report. The report argues, among other things, that the availability of icebreakers for lease in coming years is open to question, that leased ships are not optimal for performing sovereignty-related operations, and that some foreign icebreakers might be capable of performing the McMurdo resupply mission. See, for example, pages 80-81 of the NRC report. See also Jennifer Scholtes, “In Search of Frozen Assets,” CQ Weekly, October 10, 2011: 2074. Congressional Research Service 2324 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Table 4. Major Icebreakers Around the World As of September 10, 2012 Russia Total all types, in inventory (+ under construction + planned) In inventory, government owned or operated In inventory, privately owned and operated 10,000 to 19,999 BHP 20,000 to 44,999 BHP 45,000 or more BHP 10,000 to 19,999 BHP 20,000 to 44,999 BHP 34 (+ 4 + 9) 5 6 6 (all nuclear powered; 5 operational) 8 9 Sweden 7 4 Finland 8 2 3 Canada 6 (+0 +1) 4 (3 operational) 2 United States 5 (+0 +1) 1 (Healy) Denmark 4 Norway 1 (+0 +1) 1 China 1 (+0 +1) 1 Argentina 1 1 (not operational) Australia 1 1 Chile 1 1 Estonia 1 1 Germany 45,000 or more BHP 3 3 2 (Polar Sea and Polar Star – neither operational) 1 (Palmer) 1 (Aiviq – built for Shell Oil)) 4 1 (+0 +1) 1 Japan 1 1 South Korea 1 1 South Africa 1 1 Latvia 1 1 Source: Table prepared by CRS based on U.S. Coast Guard chart showing data compiled by the Coast Guard as of September 10, 2012, accessed online October 26, 2012, at http://www.uscg.mil/hq/cg5/cg552/ice.asp. Notes: Includes some icebreakers designed for use in the Baltic Sea. BHP is the brake horsepower of the ship’s power plant. A ship with 45,000 or more BHP might be considered a heavy polar icebreaker; a ship with 20,000 to 44,999 BHP might be considered a medium polar icebreaker, and a ship with 10,000 to 19,999 BHP might be considered a light polar icebreaker or an ice-capable polar ship. Notional Arguments for Various Numbers Advocates of a Coast Guard polar icebreaker fleet that includes two ships—Healy plus one heavy polar icebreaker—might argue that the Coast Guard operated with such a force between July 1, Congressional Research Service 2425 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress 2006 (when Polar Star went into caretaker status) until June 2010 (when Polar Sea suffered an engine casualty and was removed from service), that the Coast Guard, following the reactivation of Polar Sea on December 14, 2012, is once again operating with such a force, and that a force with Healy plus one heavy polar icebreaker would cost less than a larger polar icebreaker fleet and thereby permit the Coast Guard to better fund programs for performing its various non-polar missions. Advocates of a Coast Guard fleet that includes three ships—Healy plus two heavy polar icebreakers—might argue that the 2007 NRC report recommended a polar icebreaking fleet of three multimission polar icebreakers (i.e., Healy plus two additional polar icebreakers), that the Coast Guard operated with such a force from 2000, when Healy entered service, until July 1, 2006, when Polar Star went into caretaker status, that the 2006-2010 force of Healy and one heavy polar icebreaker made it more difficult for the Coast Guard to perform the McMurdo resupply mission using its own assets, that a force that includes two heavy polar icebreakers rather than one would provide more flexibility for responding to polar contingencies or dealing with mechanical problems on a heavy polar icebreaker, and that such a force would still be sufficiently affordable to permit the Coast Guard to adequately fund programs for performing non-polar missions. Advocates of a Coast Guard fleet that includes Healy plus three heavy polar icebreakers might argue that the High Latitude Study found that the Coast Guard requires three heavy (and three medium) icebreakers to fulfill its statutory missions, that a force with three heavy polar icebreakers would provide additional capability for responding to potentially increased commercial and military activities in the Arctic, that it would more strongly signal U.S. commitment to defending its sovereignty and other interests in the region, and that while such a force would be more expensive than a smaller polar icebreaker fleet, the added investment would be justified in light of the growing focus on U.S. polar interests. Disposition of Polar Sea Another potential issue for Congress concerns the disposition of Polar Sea. Section 222 of the Coast Guard and Maritime Transportation Act of 2012 (H.R. 2838/P.L. 112-213 of December 20, 2012) prohibits the Coast Guard from removing any part of Polar Sea and from transferring, relinquishing ownership of, dismantling, or recycling the ship until it submits a business case analysis of the options for and costs of reactivating the ship and extending its service life to at least September 30, 2022, so as to maintain U.S. polar icebreaking capabilities and fulfill the Coast Guard’s high latitude mission needs, as identified in the Coast Guard’s July 2010, High Latitude Study Mission Analysis Report. Options for the disposition of the ship include the following, among others: • keeping the ship in preservation status in the Maritime Administration’s (MARAD’s) National Defense Reserve Fleet (NDRF) for potential reactivation to meet increased polar icebreaking needs or to replace Polar Star, should that ship be removed from service before the end of its anticipated 7- to 10-year postreactivation service life due to an accident or the failure of critical equipment that cannot be cost-effectively repaired; • selling or transferring the ship to another government or to a private owner; and • dismantling the ship and recycling its scrap metal. Congressional Research Service 2526 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Incremental Funding vs. Full Funding Another potential oversight issue for Congress concerns the Coast Guard’s proposal to fund the acquisition of a new icebreaker using incremental funding (i.e., a series of annual funding increments—see “Funding in FY2013 Budget for New Polar Icebreaker” in “Background”) rather than full funding (i.e., placing most or all of the ship’s acquisition cost into a single year). Section 31.6 of Office of Management and Budget (OMB) Circular A-11451147 normally requires executive branch agencies to use full funding for acquiring capital assets such as a new ship. The Coast Guard appears to have received permission from OMB to propose the use of incremental funding for acquiring a new polar icebreaker; Congress may choose to approve, reject, or modify this proposal. Supporters of using incremental funding to acquire a new polar icebreaker could argue that funding this ship in a single year would create a one-year “spike” in Coast Guard funding requirements that could require offsetting and potentially disruptive one-year reductions in other Coast Guard programs, and that using incremental funding mitigates the spiking issue by spreading the ship’s cost over several years. Supporters could argue that avoiding such budget spikes is a principal reason why the Navy in recent years has been given permission by OMB and Congress to use incremental funding to procure aircraft carriers and amphibious assault ships,4648 and that a polar icebreaker is analogous to an aircraft carrier or an amphibious assault ship in being a very expensive (for the Coast Guard) ship that is procured once every several years. Supporters of using full funding to acquire a new polar icebreaker could argue that the acquisition cost of a polar icebreaker (roughly $900 million), though large by Coast Guard standards, is much less than that of an aircraft carrier (more than $11 billion) or an amphibious assault ship (more than $3 billion). They could argue that OMB believes using full funding reduces risks in the acquisition of capital assets,4749 and that permitting the use of incremental funding for the procurement of a polar icebreaker could weaken adherence to the policy by setting a precedent for using incremental funding for acquiring other capital assets costing less than $1 billion. 45 The issue of incremental funding as an alternative to full funding in the acquisition of Navy ships is discussed at length in other CRS reports.50 47 The text of OMB Circular A-11 is available online at http://www.whitehouse.gov/omb/ circulars_a11_current_year_a11_toc. 4648 See. for example, CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress, by Ronald O'Rourke. 4749 Appendix J to OMB Circular A-11 states, in explaining the requirement for using full funding, that Good budgeting requires that appropriations for the full costs of asset acquisition be enacted in advance to help ensure that all costs and benefits are fully taken into account at the time decisions are made to provide resources. Full funding with regular appropriations in the budget year also leads to tradeoffs within the budget year with spending for other capital assets and with spending for purposes other than capital assets. Full funding increases the opportunity to use performancebased fixed price contracts, allows for more efficient work planning and management of the capital project (or investment), and increases the accountability for the achievement of the baseline goals. When full funding is not followed and capital projects (or investments) or useful segments are funded in increments, without certainty if or when future funding will be available, the result is sometimes poor planning, acquisition of assets not fully justified, higher acquisition costs, cancellation of major investments, the loss of sunk costs, or inadequate funding to maintain and operate the assets. Congressional Research Service 26 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The issue of incremental funding as an alternative to full funding in the acquisition of Navy ships is discussed at length in other CRS reports.48 50 See CRS Report RL31404, Defense Procurement: Full Funding Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report RL32776, Navy Ship Procurement: Alternative (continued...) Congressional Research Service 27 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Funding Ships in Coast Guard Budget or Elsewhere Another potential issue for Congress, if it is determined that one or more new icebreakers should be procured by the government through a traditional acquisition, is whether the acquisition cost of those ships should be funded entirely through Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account, or partly or entirely through other parts of the federal budget, such as the Department of Defense (DOD) budget, the NSF budget, or both.4951 Within the DOD budget, possibilities include the Navy’s shipbuilding account, called the Shipbuilding and Conversion, Navy (SCN) account, and the National Defense Sealift Fund (NDSF), which is an account where DOD sealift ships and Navy auxiliary ships are funded. There is precedent for funding Coast Guard icebreakers in the DOD budget: The procurement of Healy was funded in FY1990 in the DOD budget—specifically, the SCN account.5052 Advocates of funding new icebreakers partly or entirely through the SCN account or the NDSF might argue that this could permit the funding of new icebreakers while putting less pressure on other parts of the Coast Guard’s budget. They might also argue that it would permit the new icebreaker program to benefit from the Navy’s experience in managing shipbuilding programs. Opponents might argue that funding new icebreakers in the SCN account or the NDSF might put pressure on these other two accounts at a time when the Navy and DOD are facing challenges funding their own shipbuilding and other priorities. They might also argue that having the Navy manage the Coast Guard’s icebreaker program would add complexity to the acquisition effort, and that it is unclear whether the Navy’s recent performance in managing shipbuilding programs is better than the Coast Guard’s, since both services have recently experienced problems in managing shipbuilding programs—the Coast Guard with the procurement of new Deepwater cutters, and the Navy in the Littoral Combat Ship (LCS) program and the LPD-17 class amphibious ship program.5153 The prepared statement of the GAO witness at the December 1, 2011, hearing states: Another alternative option addressed by the Recapitalization report would be to fund new icebreakers through the NSF. However, the analysis of this option concluded that funding a new icebreaker through the existing NSF budget would have significant adverse impacts on 48 See CRS Report RL31404, Defense Procurement: Full Funding Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report RL32776, Navy Ship Procurement: Alternative NSF operations and that the capability needed for Coast Guard requirements would exceed that needed by the NSF. The Recapitalization report noted that a funding approach similar to the approach used for the Healy, which was funded through the fiscal year 1990 DOD appropriations, should be (...continued) Funding Approaches—Background and Options for Congress, by Ronald O'Rourke. 4951 For more on the NSF, whose budget is normally funded through the annual Commerce, Justice, Science, and Related Agencies appropriations bill, see CRS Report 95-307, U.S. National Science Foundation: An Overview, by Christine M. Matthews. 5052 The FY1990 DOD appropriations act (H.R. 3072/P.L. 101-165 of November 21, 1989) provided $329 million for the procurement of Healy in the SCN account. (See pages 77 and 78 of H.Rept. 101-345 of November 13, 1989). The NDSF was created three years later, in FY1993, as a fund for procuring DOD sealift ships, among other purposes, and since FY2001 has been used to fund Navy auxiliary ships as well. 5153 For more on Deepwater acquisition programs and the LCS and LPD-17 programs, see CRS Report RL33753, Coast Guard Deepwater Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke; CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress, by Ronald O'Rourke; and CRS Report RL34476, Navy LPD-17 Amphibious Ship Procurement: Background, Issues, and Options for Congress, by Ronald O'Rourke. Congressional Research Service 2728 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress NSF operations and that the capability needed for Coast Guard requirements would exceed that needed by the NSF. The Recapitalization report noted that a funding approach similar to the approach used for the Healy, which was funded through the fiscal year 1990 DOD appropriations, should be considered. However, the report did not analyze the feasibility of this option. We have previously reported that because of the Coast Guard’s statutory role as both a federal maritime agency and a branch of the military, it can receive funding through both the Department of Homeland Security (DHS) and DOD. For example, as we previously reported, although the U.S. Navy is not expressly required to provide funding to the Coast Guard, the Coast Guard receives funding from the Navy to purchase and maintain equipment, such as self-defense systems or communication systems, because it is in the Navy’s interest for the Coast Guard systems to be compatible with the Navy’s systems when the Coast Guard is performing national defense missions in support of the Navy. However, according to a Coast Guard budget official, the Coast Guard receives the majority of its funding through the DHS appropriation, with the exception of reimbursements for specific activities. Also, as the Recapitalization plan acknowledges, there is considerable strain on the DOD budget. A recent DOD report on the Arctic also notes budgetary challenges, stating that the near-term fiscal and political environment will make it difficult to support significant new U.S. investments in the Arctic. Furthermore, DOD and the Coast Guard face different mission requirements and timelines. For example, DOD’s recent report states that the current level of human activity in the Arctic is already of concern to DHS, whereas the Arctic is expected to remain a peripheral interest to much of the national security community for the next decade or more. As a result, the Coast Guard has a more immediate need than DOD to acquire Arctic capabilities, such as icebreakers. For example, with preliminary plans for drilling activity approved in 2011, the Coast Guard must be prepared to provide environmental response in the event of an oil spill. Similarly, as cruise ship traffic continues to increase, the Coast Guard must be prepared to conduct search and rescue operations should an incident occur. For these reasons, it is unlikely that an approach similar to the one that was used to build the Healy would be feasible at this time.5254 At a March 6, 2012, hearing on the Coast Guard’s proposed FY2013 budget before the Homeland Security subcommittee of the House Appropriations Committee, Admiral Robert Papp, the Commandant of the Coast Guard, stated: But [would] I like to make a case, and this is just Papp’s opinion[,] that an icebreaker ought to be a shared cost across the government. The National Science Foundation needs it, the Department of Defense from time to time needs it. Yes, the Coast Guard needs it. But this is something that really begs for an across-government response, and I would say sharing as well.5355 New Construction vs. Service Life Extension Another potential issue for Congress is whether requirements for polar icebreakers over the next 25 to 30 years should be met by building new ships, by extending the service lives of existing polar icebreakers, or by pursuing some combination of these options. In assessing this question, 52factors to consider include the relative costs of these options, the capabilities that each option would provide, the long-term supportability of older ships whose service lives have been extended, and industrial-base impacts. 54 Government Accountability Office, Coast Guard[:] Observations on Arctic Requirements, Icebreakers, and Coordination with Stakeholders, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of Stephen L. Caldwell, Director, Homeland Security and Justice, GAO-12-254T, December 1, 2011, pp. 24-25. 5355 Source: Transcript of hearing. Congressional Research Service 2829 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress factors to consider include the relative costs of these options, the capabilities that each option would provide, the long-term supportability of older ships whose service lives have been extended, and industrial-base impacts. Regarding relative costs, as discussed in the “Background” section, the Coast Guard estimates that new icebreakers with a 30-year design life might cost $800 million to $925 million per ship in 2008 dollars, while a 25-year service life extension of Polar Star and Polar Sea might cost about $400 million per ship in 2008 dollars. (As mentioned earlier, an August 30, 2010, press report stated that the Commandant of the Coast Guard, Admiral Robert Papp, estimated the cost of extending the lives of Polar Star and Polar Sea at about $500 million per ship.)5456 These estimates, however, should be compared with caution: the estimate for building new ships depends in part on the capabilities that were assumed for those ships, and estimates for servicelife extension work can be very uncertain due to the potential for discovering new things about a ship’s condition once the ship is opened up for service-life-extension work. Regarding capabilities provided by each option, the new-construction option would provide entirely new ships with extensive use of new technology, while the service-life-extension option would provide ships that, although modernized and reconditioned, would not be entirely new and would likely make less extensive use of new technologies. Among other things, new-construction ships might be able to make more extensive use of new technologies for reducing crew size, which is a significant factor in a ship’s life cycle operating and support costs. Regarding long-term supportability of older ships, the Coast Guard has expressed concern about the ability to support ships whose service lives have been extended after FY2014, because some contracts that currently provide that support are scheduled to end that year.5557 Regarding potential impact on the industrial base, 25-year service life extensions would likely provide shipyards and supplier firms with less work, and also exercise a smaller set of shipyard construction skills, than would building new ships. Procurement vs. Leasing Another potential issue for Congress is whether future polar icebreakers should be acquired through a traditional acquisition (i.e., the government procuring the ship and owning it throughout its service life) or through a leasing arrangement (under which the icebreakers would be privately built and privately owned, leased to the Coast Guard, and crewed by an all-Coast Guard crew or a mix of Coast Guard personnel and civilian mariners). Factors to consider in assessing this issue include the comparative costs of the two options and the potential differences between them in terms of factors such as average number of days of operation each year and capability for performing various missions. Comparing the potential costs of leasing versus purchasing a capital asset often involves, among other things, calculating the net present value of each option. At a December 1, 2011, hearing that focused on the polar icebreaker fleet (see “December 1, 2011, Hearing” in “Background”), Admiral Robert Papp, the Commandant of the Coast Guard, stated: 54As far as we can determine, there are no icebreakers available—no heavy icebreakers available for leasing right now. They would have to be constructed [and then leased]. 56 Cid Standifer, “Papp: Refurbished Icebreaker Hulls Could Last ‘An Awful Long Time,’” Inside the Navy, August 30, 2010. Ellipsis as in original. 5557 CRS discussion with Coast Guard officials, January 30, 2008. Congressional Research Service 2930 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress As far as we can determine, there are no icebreakers available—no heavy icebreakers available for leasing right now. They would have to be constructed [and then leased]. If we were to lease an icebreaker, I’m sure that a company building an icebreaker outside of the government does not have to contend with the same federal acquisition rules that we have to if we were to construct an icebreaker. It could probably be done quicker. Personally, I’m ambivalent in terms of how we get an icebreaker for the Coast Guard. We’ve done the legal research. If we lease an icebreaker, we can put a Coast Guard crew on it and still have it as a U.S. vessel supporting U.S. sovereignty. But the—but they aren’t available right now. And the other challenge that we face is the federal acquisition rules and [Office of Management and Budget Circular] A-11 requirements that [direct how to] score the money [in the budget] for leasing. We’d have to put up a significant amount of upfront money even with a lease that we don’t have room for within our budget currently.5658 At another point in the hearing, Admiral Papp stated: We have looked at various business case scenarios, each and every time looking at, once again, from our normal perspective, the Coast Guard perspective, which has been owning ships forever. And generally, we keep ships 30-40 years or beyond. There is a point where leasing becomes more expensive, it’s at or about the 20-25-year timeline. I just don’t have the experience with leasing to be able to give you a good opinion on it. And once again, I'm ambivalent. We just need the icebreaking capability, I think it’s for people who can do the analysis, the proper analysis of—but also have to take into account the capabilities required and we need to get about the business of determining the exact capabilities that we need which would take into account National Science Foundation requirements, Coast Guard requirements, requirements to break-in at McMurdo, to come up with a capable ship.5759 At another point in the hearing, he stated: As I said, sir, I am truly ambivalent to this except from what I experienced. I do have now two points, yes the Navy leases some ships, but we've got a Navy that has well over 300 ships. So if they lose a leased vessel or something is pulled back or something happens, they have plenty of other ships they can fall back upon. Right now, all I am falling back on is the Coast Guard cutter Healy. And it feels good to know that we own that and that is our ship for 30 or 40 years and we can rely upon it. In terms of leasing, I don't know. My personal experience is I lease one of my two cars and I pay a lot of money leasing my car. But at the end of the lease period, I have no car and I've spent a lot of money. So I don’t know if that’s directly applicable to ships as well, but right now I got half my garage is empty because I just turned one in.58 5660 At another point in the hearing, he stated: 58 Source: Transcript of hearing. Source: Transcript of hearing. 5860 Source: Transcript of hearing. 5759 Congressional Research Service 3031 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress At another point in the hearing, he stated: We’ve looked through the legal considerations on this, as long as we have a Coast Guard crew. In fact, you can even make a mixed crew of civilians and Coast Guard people. But as long as it’s commanding by—commanded by [a] commissioned officer, you can assert sovereignty, you can take it into war zones and, in fact, the Navy does that as well.5961 Another witness at the hearing—Mead Treadwell, the lieutenant governor of Alaska—stated: [Regarding] The issue of the ships, the company that is building these ships for Shell [Oil] has visited with me and other state officials, and that’s why you heard us say in our testimony that we think the leasing option should be considered. We don’t have a way to judge the relative cost. But if on the face of it, it seems like it may be a way to get us the capability that the admiral needs.6062 Another witness at the hearing—Jeffrey Garrett, a retired Coast Guard admiral who spent much of his career on polar icebreakers—stated: The perspective I could offer was when I was a member of the Cameron [sic: Commandant’s?] staff back in the last ‘80s here in Washington, we were directed to pursue exactly the same sort of lease versus buy analysis, and in fact, the Coast Guard had a two track procurement strategy to compare leasing a new Polar icebreaker or buying it. And after over a year of analysis, studies, discussion with other agencies looking around, what became clear was, number one, there was no off-the-shelf asset readily available. And secondly, that in the long run, if you—when you cost it all out and the value of the stream of payments, leasing would actually cost more. And when we did the recapitalization analysis recently, we also reviewed leasing again, and the I think the findings in that report indicate more expensive over the life of the vessel by about 12 percent.6163 When asked why this was the finding, Garrett stated: A couple of technical things. First of all, whoever builds the ship—and again, this will have to be ship built for the Coast Guard since there’s not something off-the-shelf out there that you could lease. Whoever builds it has to raise capital, and nobody can raise capital more inexpensively than the federal government. Secondly, whoever leases the ship is obviously going to make—want to make a profit on that lease. So just like as Admiral Papp referred to leasing your car, you know, there’s going to be a profit involved. And so, if you take the net present value of all of those, of those payments, you got come out with the more expensive package for the same, if you're comparing the same vessel. 59 The other, the other issue I think is more intangible and that’s just the fact that we're really not talking about an auxiliary like the Naval, like the Navy leases a supply ship or something 61 Source: Transcript of hearing. Source: Transcript of hearing. The transcript reviewed by CRS attributes this quote to the GAO witness, Stephen Caldwell, but this appears to be a mistake, as the statement is made by a member of the first witness panel, which included the Commandant of the Coast Guard and the Lieutenant Governor. The GAO witness was a member of the second witness panel. The reference in the quote to “me and other state officials” indicates that the witness speaking was the Lieutenant Governor and not the Commandant. 6163 Source: Transcript of hearing. 6062 Congressional Research Service 3132 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The other, the other issue I think is more intangible and that’s just the fact that we're really not talking about an auxiliary like the Naval, like the Navy leases a supply ship or something like that. We're talking about a frontline Coast Guard capital asset, if you will, capital ship that’s going to be doing frontline government missions projecting U.S. sovereignty. And you know, the Navy doesn't lease those kinds of ships for its frontline fleet and the Coast Guard doesn't lease those kinds of ships for its mission capabilities, and that’s what we're really talking about in terms of the ship we need here. So while a lease may look attractive, I think there are several things that indicate it may not be the right way to go. And the—I think that’s what we came down to. And again, this is all documented in the past and that late ‘80s analysis was re-summarizing the president’s 1990 report to Congress which basically says leasing is more expensive and it’s not the way to go for a new ship. That was the ship that actually became the Healy then.6264 The prepared statement of Stephen Caldwell, the GAO witness at the hearing, states: The three reports discussed earlier in this [GAO] statement all identify funding as a central issue in addressing the existing and anticipated challenges related to icebreakers. In addition to the Coast Guard budget analysis included in the Recapitalization report, all three reports reviewed alternative financing options, including the potential for leasing icebreakers, or funding icebreakers through the National Science Foundation (NSF) or the Department of Defense (DOD). Although DOD has used leases and charters in the past when procurement funding levels were insufficient to address mission requirements and capabilities, both the Recapitalization report and the High Latitude Study determined that the lack of existing domestic commercial vessels capable of meeting the Coast Guard’s mission requirements reduces the availability of leasing options for the Coast Guard. Additionally, an initial costbenefit analysis of one type of available leasing option included in the Recapitalization report and the High Latitude Study suggests that it may ultimately be more costly to the Coast Guard over the 30-year icebreaker lifespan.6365 Legislative Activity in 2012 Following Submission of Proposed FY2013 Budget FY2013for FY2014 FY2014 Funding Request The Coast Guard’s proposed FY2013FY2014 budget includes $8 million in acquisition funding to initiate requests $2 million to continue survey and design activities for a new polar icebreaker. The Coast Guard’s Five Year Capital Investment Plan includes an additional $852 million in FY2014-FY2017 for acquiring the ship. The Coast Guard anticipates awarding a construction contract for the ship “within the next five years” and taking delivery on the ship “within a decade.” The project to design and build a polar icebreaker is a new acquisition project initiated in the FY2013 budget. 62 Source: Transcript of hearing. Government Accountability Office, Coast Guard[:] Observations on Arctic Requirements, Icebreakers, and Coordination with Stakeholders, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of Stephen L. Caldwell, Director, Homeland Security and Justice, GAO-12-254T, December 1, 2011, p. 24. 63 Congressional Research Service 32 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Coast Guard and Maritime Transportation Act of 2012 (H.R. 2838/P.L. 112-213) On December 5, 2012, the House agreed to Senate amendments to H.R. 2838 with an amendment pursuant to H.Res. 825. On December 12, 2012, the Senate by voice vote agreed to the House amendment to Senate amendment. On December 20, 2012, the bill was signed by the president and enacted as P.L. 112-213. Section 222 of H.R. 2838 as passed by the both the House and Senate states: SEC. 222. COAST GUARD POLAR ICEBREAKERS. (a) In General- The Secretary of the department in which the Coast Guard is operating shall conduct a business case analysis of the options for and costs of reactivating and extending the service life of the Polar Sea until at least September 30, 2022, to maintain United States polar icebreaking capabilities and fulfill the Coast Guard’s high latitude mission needs, as identified in the Coast Guard’s July 2010, High Latitude Study Mission Analysis Report, during the Coast Guard’s recapitalization of its polar class icebreaker fleet. The analysis shall include— (1) an assessment of the current condition of the Polar Sea; (2) a determination of the Polar Sea’s operational capabilities with respect to fulfilling the Coast Guard’s high latitude operating requirements if renovated and reactivated; (3) a detailed estimate of costs with respect to reactivating and extending the service life of the Polar Sea; (4) a life cycle cost estimate with respect to operating and maintaining the Polar Sea for the duration of its extended service life; and (5) a determination of whether it is cost-effective to reactivate the Polar Sea compared with other options to provide icebreaking services as part of a strategy to maintain polar icebreaking services. (b) Restrictions- The Secretary shall not remove any part of the Polar Sea until the Secretary submits the analysis required under subsection (a). (c) Deadline- Not later than 270 days after the date of enactment of this Act, the Secretary shall submit to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Commerce, Science, and Transportation of the Senate the analysis required under subsection (a). (d) Requirement for Reactivation of Polar Sea(1) SERVICE LIFE EXTENSION PLAN(A) IN GENERAL- If the Secretary determines based on the analysis required under subsection (a) that it is cost-effective to reactivate the Polar Sea compared with other options to provide icebreaking services, the Secretary shall develop a service life extension plan for such reactivation, including a timetable for such reactivation. Congressional Research Service 33 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress (B) UTILIZATION OF EXISTING RESOURCES- In the development of the plan required under subparagraph (A), the Secretary shall utilize to the greatest extent practicable recent plans, studies, assessments, and analyses regarding the Coast Guard’s icebreakers and high latitude mission needs and operating requirements. (C) SUBMISSION- The Secretary shall submit the plan required under subparagraph (A), if so required, to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Commerce, Science, and Transportation of the Senate not later than 180 days after the submission of the analysis required under subsection (a). (2) DECOMMISSIONING; BRIDGING STRATEGY- If the analysis required under subsection (a) is submitted in accordance with subsection (c) and the Secretary determines under subsection (a)(5) that it is not cost-effective to reactivate the Polar Sea, then not later than 180 days after the date on which the analysis is required to be submitted under subsection (c) the Commandant of the Coast Guard— (A) may decommission the Polar Sea; and (B) shall submit a bridging strategy for maintaining the Coast Guard’s polar icebreaking services until at least September 30, 2022, to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Commerce, Science, and Transportation of the Senate. (e) Restriction- Except as provided in subsection (d), the Commandant of the Coast Guard may not— (1) transfer, relinquish ownership of, dismantle, or recycle the Polar Sea or Polar Star; (2) change the current homeport of either of the vessels; or (3) expend any funds— (A) for any expenses directly or indirectly associated with the decommissioning of either of the vessels, including expenses for dock use or other goods and services; (B) for any personnel expenses directly or indirectly associated with the decommissioning of either of the vessels, including expenses for a decommissioning officer; (C) for any expenses associated with a decommissioning ceremony for either of the vessels; (D) to appoint a decommissioning officer to be affiliated with either of the vessels; or (E) to place either of the vessels in inactive status. (f) Definition- For purposes of this section— (1) the term `Polar Sea’ means Coast Guard Cutter Polar Sea (WAGB 11); and (2) the term `Polar Star’ means Coast Guard Cutter Polar Star (WAGB 10). (g) Repeal- This section shall cease to have effect on September 30, 2022. Congressional Research Service 34 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Coast Guard and Maritime Transportation Act of 2012 (H.R. 5887 of 112th Congress) House Section 304 of H.R. 5887 as introduced on June 1, 2012, states: SEC. 304. USCGC `POLAR SEA’. (a) In General- Not later than 180 days after the date of enactment of this Act, the Secretary of the department in which the Coast Guard is operating shall submit to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Commerce, Science, and Transportation of the Senate a report providing a business-case analysis of the options for and costs of reactivating and extending the service life of the USCGC Polar Sea until the estimated date on which a new polar-class icebreaker is commissioned. The Secretary shall include in the report— (1) an assessment of the current condition of the USCGC Polar Sea and a determination of the vessel’s operational capabilities with respect to fulfilling the Coast Guard’s high latitude operating requirements; (2) a detailed estimate of costs with respect to reactivating and extending the service life of the USCGC Polar Sea to a condition at least comparable to the condition of the USCGC Polar Star when it enters service in 2013; and (3) a life cycle cost estimate with respect to operating and maintaining the USCGC Polar Sea for the duration of its extended service life. (b) Restriction- The Secretary shall not remove any major equipment, systems, or other appurtenances from the USCGC Polar Sea for planned or potential work to refurbish the USCGC Polar Star until the Secretary submits the report required under subsection (a). Department of Defense, Military Construction and Veterans Affairs, and Full-Year Continuing Appropriations Act, 2013 (H.R. 933 of 113th Congress) Version Passed by House on March 6, 2013 H.R. 933 of the 113th Congress as passed by the House on March 6, 2013, includes, as Division C, a full-year continuing resolution for several parts of the federal government. Section 1101 of Division C would fund DHS at funding levels based on the FY2012 Department of Homeland Security Appropriations Act (Division D of H.R. 2055/P.L. 112-74 of December 23, 2011). Section 1104 of Division C states, “No appropriation or funds made available or authority granted pursuant to Section 1101 shall be used to initiate or resume any project or activity for which appropriations, funds, or other authority were not available during fiscal year 2012.” The prohibition in Section 1104, commonly known as the prohibition on new starts, might affect the Coast Guard’s ability to initiate a project in FY2013 for the acquisition of a polar icebreaker, since the project is proposed a new acquisition project initiated in the FY2013 budget. Congressional Research Service 35 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Version Passed by Senate and House on March 20 and 21, 2013 H.R. 933 of the 113th Congress as passed by the Senate on March 20, 2013, and the House on March 21, 2013, includes the FY2013 DHS appropriations act as Division D. Division D approves the Coast Guard’s request for $8 million in acquisition funding to initiate survey and design activities for a new polar icebreaker.64 The explanatory statement for Division D states: Polar Icebreaker As requested, $8,000,000 is provided to initiate survey and design activities for a new Coast Guard polar icebreaker. The Coast Guard is directed to provide the Committees with its Mission Needs Statement no later than 30 days after it receives Departmental approval and to brief the Committees on its timeline for completing a concept of operations, market research, specification development, and other acquisition milestones leading to a request for proposal and contract award.65 The explanatory statement for Division D also states: Infrastructure and Response Capabilities in the Arctic The Coast Guard is directed to report to the Committees within 90 days after the date of enactment of this Act on the actions taken to reach international agreements on ensuring adequate maritime transportation infrastructure and response capabilities in the Arctic.66 FY2013 Department of Homeland Security Appropriations Act (H.R. 5855/S. 3216 of 112th Congress) House The House Appropriations Committee, in its report (H.Rept. 112-492 of May 23, 2012) on H.R. 5855 of the 112th Congress, recommends approving the Coast Guard’s request for $8 million in FY2013 acquisition funding to initiate survey and design activities for a new polar icebreaker. (Pages 84 and 90) Senate The Senate Appropriations Committee, in its report (S.Rept. 112-169 of May 22, 2012) on S. 3216 of the 112th Congress, recommends approving the Coast Guard’s request for $8 million in FY2013 acquisition funding to initiate survey and design activities for a new polar icebreaker. (Page 83) The report states: POLAR ICEBREAKER 64 Explanatory statement for Division D of H.R. 933, pdf page 35 of 76. Explanatory statement for Division D of H.R. 933, pdf page 38 of 76. 66 Explanatory statement for Division D of H.R. 933, pdf page 32 of 76. 65 Congressional Research Service 36 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The recommendation includes $8,000,000, as requested, to initiate survey and design activities for a new Coast Guard polar icebreaker. The Coast Guard’s two heavy polar icebreakers (Polar Star and Polar Sea), the only U.S. vessels that have the capability to perform year-round operations in the polar regions, are currently inoperable, with the Polar Sea set to be decommissioned and Polar Star set to be reactivated in 2013 for an additional 7 to 10 years of service life. Both the Polar Sea and Polar Star were commissioned in the late 1970’s and have exceeded their expected service life of 30 years. The Coast Guard’s high latitude study, which was completed in 2010, concluded that additional icebreaking assets are necessary in the polar regions. This followed a National Academy of Science study that made similar conclusions. The Coast Guard has indicated that its mission needs statement [MNS] for this acquisition is to be completed by June 2012. The Coast Guard shall submit this document to the Committee no later than 30 days after it receives Departmental approval and brief the Committee on its timeline for completing a concept of operations, market research, specification development, and other acquisition milestones leading to a request for proposal and contract award. (Pages 87-88; material in brackets as in original) Conference For further action on the FY2013 Department of Homeland Security Appropriations Act, see H.R. 933 of the 113th Congress above. Congressional Research Service 37 activities for a new Coast Guard polar icebreaker, or $118 million less than the $120 million that was projected for FY2014 under the FY2013 budget. The Coast Guard testified on April 16, 2013, that it anticipates submitting its FY2014 Five Year (FY2014-FY2018) Capital Investment Plan on May 1, 2013.66 64 Source: Transcript of hearing. Government Accountability Office, Coast Guard[:] Observations on Arctic Requirements, Icebreakers, and Coordination with Stakeholders, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of Stephen L. Caldwell, Director, Homeland Security and Justice, GAO-12-254T, December 1, 2011, p. 24. 66 Source: Transcript of April 16, 2013, hearing before the Coast Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure Committee on the proposed FY2014 budget for the Coast Guard and maritime transportation. 65 Congressional Research Service 33 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Appendix A. Coast Guard Activities Since 2008 To Assess Requirements and Options for Polar Icebreakers This appendix presents information on Coast Guard activities since 2008 to assess requirements and acquisition options for polar icebreakers. The Coast Guard stated in February 2008 that it is awaiting the identification and prioritization of U.S. national policy in the Polar Regions in order to identify and develop the appropriate capability. In the meantime, the CG is proceeding with pre-acquisition activities, starting with project identification, to assess current capability gaps in Coast Guard mission performance in the high latitudes regions.67 In connection with this statement, it can be noted that a document establishing U.S. national policy in the Arctic—National Security Presidential Directive 66/Homeland Security Presidential Directive 25 (NSPD 66/HSPD 25)—was issued by the George W. Bush Administration on January 12, 2009.68 A March 24, 2008, press report stated that [Coast Guard] Commanders in Alaska plan to conduct an unprecedented expedition to the Arctic this summer, including a trip already underway by the Healy, to get a clear sense of their capabilities and problems operating above the Bering Strait. When that survey is finished, probably by August [2008], [then-Coast Guard Commandant Admiral Thad] Allen and the commander of District 17, Rear Adm. Arthur “Gene” Brooks, will be able to make their case to Congress for funding and new gear, Allen said.69 On July 16, 2008, then-Commandant of the Coast Guard Admiral Thad Allen, testified that Today, our nation is at a crossroads with Coast Guard domestic and international icebreaking capabilities. We have important decisions to make. And I believe we must address our icebreaking needs now, to ensure we will continue to prosper in the years and decades to come, whether on the Great Lakes, the critical waterways of the East Coast or the harsh operating environments of the polar region.70 An August 17, 2008, press report quoted Admiral Allen as stating that, in light of the time required to build a new polar icebreaker, “I think we’re at a crisis point on making a decision.”71 67 Coast Guard point paper provided to CRS on February 12, 2008, op cit. For more on NSPD 66/HSPD 25, see CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke. 69 Philip Ewing, “CG Steps Up Bid to Rescue Icebreaker Funding,” Navy Times, March 24, 2008. 70 Transcript of spoken remarks of Admiral Allen at July 16, 2008, hearing on Coast Guard icebreaking needs before the Coast Guard and Maritime transportation subcommittee of the House Transportation and Infrastructure Committee. 71 Andrew C. Revkin, “A Push To Increase Icebreakers In The Arctic,” New York Times, August 17, 2008. 68 Congressional Research Service 3834 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Almost two years later—on May 10, 2010—a press report quoted him as stating, “We need to be able to project U.S. sovereignty up there [i.e., the Arctic] and do the missions that we need to do. We need to have a serious discussion about icebreakers. It has not concluded. It’s not even started, and you can see me be a little more vocal on that on the 26th of May [2010] because my change of command [i.e., the end of his term in office as Commandant of the Coast Guard] is the 25th of May.”72 An August 30, 2010, press report stated that the current Commandant of the Coast Guard, Admiral Robert Papp, has not yet discussed the matter [of polar icebreakers] with Department of Homeland Security Secretary Janet Napolitano because he has been focused on dealing with the Deepwater Horizon oil spill since he took the helm of the Coast Guard in May. “I will have to make the case with my secretary on what I think the best way ahead [for icebreakers] is,” he said. “I’ve got my staff looking at those options and what we might do, and then once we discern what the best way ahead is, then we’re going to have to sell that to the administration and hopefully get the funding from Congress.”73 A September 2010 GAO report on the Coast Guard’s efforts to identify Arctic requirements in general stated: The Coast Guard has taken specific action to identify Arctic requirements and gaps while also collecting relevant information from routine operations. The High Latitude Study is the centerpiece of the agency’s efforts to determine its Arctic requirements. The Coast Guard has also established temporary operating locations in the Arctic and conducted biweekly Arctic overflights to obtain more information on the Arctic operating environment. In addition, information gathered during the Coast Guard’s routine missions––ice breaking, search and rescue, and others––also informs requirements. The agency’s preliminary efforts to identify its Arctic requirements generally align with key practices for agencies defining missions and desired outcomes. The Coast Guard faces Arctic challenges including limited information, minimal assets and infrastructure, personnel issues, and difficult planning and funding decisions, but is taking initial steps to address these challenges. Specifically, the Coast Guard does not currently have Arctic maritime domain awareness––a full understanding of variables that could affect the security, safety, economy, or environment in the Arctic––but is acquiring additional Arctic vessel tracking data, among other things, to address this issue. In addition, the Coast Guard’s Arctic assets and infrastructure are limited and not suitable for the harsh environment, but the agency is testing equipment and using alternative options to mitigate gaps. Finally, the Coast Guard faces uncertainty over the timing of predicted environmental changes in the Arctic, as well as over future funding streams. To address these challenges the 72 Cid Standifer, Dan Taylor and Zachary M. Peterson, “Notes From The Navy League’s Sea-Air-Space Conference And Exhibition, May 3-5, 2010, National Harbor, MD,” Inside the Navy, May 10, 2010. On May 1, 2010, Janet Napolitano, Secretary of the Department of Homeland Security, announced that Allen would serve as the National Incident Commander for the Administration’s response to the Deepwater Horizon oil spill in the Gulf of Mexico. Allen stepped down as Commandant on May 25, 2010, and retired from active duty service in the Coast Guard on June 30, 2010, but continued as a civilian in his role as the National Incident Commander for the oil spill. A September 27, 2010, press report states that Allen would step down as National Incident Commander on September 30, 2010. (Rick Jervis, “BP Spill Shapes Allen’s Legacy,” Navy Times.com, September 27, 2010. 73 Cid Standifer, “Papp: Refurbished Icebreaker Julls Could Last ‘An Awful Long Time,’” Inside the Navy, August 30, 2010. Congressional Research Service 3935 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Coast Guard obtains scientific data on Arctic climate change and is studying its Arctic resource requirements to support potential future funding needs.74 The report also stated: The Coast Guard has multiple efforts underway to better understand the agency’s future requirements and gaps in both the Arctic and Antarctic with its primary effort being the High Latitude Study, an effort undertaken in response to congressional direction. In August 2009, the Coast Guard contracted out the development of the High Latitude Study with the goal of producing three related mission analyses related to (1) Polar icebreaking needs, (2) all 11 Coast Guard missions in the Arctic region, and (3) all 11 Coast Guard missions in the Antarctic region. In carrying out the study, contractors have conducted literature reviews, held workshops to obtain Coast Guard stakeholder input, and conducted site visits and interviews with Coast Guard units in Alaska as well as with other stakeholders, including private sector, federal, state, local, Alaska Native, and international interest groups. Coast Guard officials estimate the study’s cost at $1.7 million and that all three volumes will be ready for Coast Guard internal review in summer 2010; however, they won’t be released publicly until a later date. The Arctic mission analysis piece of the High Latitude Study is expected to include • an analysis of the functional requirements to carry out the Coast Guard’s existing missions in the Arctic, • an analysis of how the Coast Guard might close any operational gaps, • solutions for a range of future demand scenarios such as a mass search and rescue incident or an Arctic oil spill (including looking at partnerships and opportunities to leverage resources), and • a rough order of magnitude cost estimate. According to Coast Guard officials, the High Latitude Study is not expected to detail specific recommended solutions or assets, but rather identify the types of capabilities needed in the Arctic. In addition, while not Arctic-specific, DHS and the Coast Guard have begun a comprehensive Fleet Mix Analysis—an analysis of the capabilities, number, and mix of assets it needs to fulfill the agency’s missions. According to Coast Guard officials, this analysis is due to be completed in December 2010 and is expected to include more specific fleet requirements for surface operations in the Bering Sea region of the Arctic but not above the Arctic Circle.75 The Coast Guard provided the above-cited High Latitude Study to Congress in July 2011. The study, dated July 2010 on its cover, analyzes and makes a series of findings relating to U.S. needs for polar icebreakers. (See “Coast Guard High Latitude Study Provided to Congress in July 2011” in “Background.”) 74 Government Accountability Office, Coast Guard[:]Efforts to Identify Arctic Requirements Are Ongoing, but More Communication about Agency Planning Efforts Would Be Beneficial, GAO-10-870, September 2010, summary page. 75 Government Accountability Office, Coast Guard[:]Efforts to Identify Arctic Requirements Are Ongoing, but More Communication about Agency Planning Efforts Would Be Beneficial, GAO-10-870, September 2010, pp. 24-26. Congressional Research Service 4036 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Appendix B. Legislative Activity in 111th and 110th Congresses This appendix presents information on legislative activity regarding polar icebreakers in the 111th and the 110th Congresses, beginning with legislative activity for FY2011 and working backwards. Headings below that lack Public Law (P.L.) numbers indicate bills that were not enacted into law by the end of the 111th and 110th Congresses. Details on the final legislative actions taken on these bills are available from the Legislative Information System (LIS). FY2011 DOD and Full-Year Continuing Appropriations Act (H.R. 1473/P.L. 112-10) The text of the FY2011 Department of Defense and Full-Year Continuing Appropriations Act (H.R. 1473/P.L. 112-10 of April 15, 2011) does not provide any funding specifically identified as being for polar icebreaker sustainment or refurbishment, or for acquisition of new polar icebreakers. FY2011 DHS Appropriations Bill (S. 3607) Senate The Senate Appropriations Committee, in its report (S.Rept. 111-222 of July 19, 2010) on S. 3607 of the 111th Congress, did not recommend any funding in the Coast Guard’s AC&I account for polar icebreaker sustainment or refurbishment, or for acquisition of new polar icebreakers (pages 82-83). The report states: POLAR ICEBREAKER SUSTAINMENT The Coast Guard shall continue to periodically brief the Committee on progress made to reactivate CGC Polar Star. According to the Coast Guard, reactivation work will be completed by 2013, increasing the fleet of operational polar icebreakers to three. As discussed in the “Operating Expenses” section of this report, the Committee expects sufficient funding to be requested in fiscal year 2012 to field a crew for the vessel. The Committee recently learned that the Polar Sea has been unexpectedly taken out of service due to excessive wear in its main diesel engines and will likely be in a maintenance status and unavailable for operations until at least January 2011. As a result of this situation, the scheduled fall 2010 Arctic patrol will be cancelled as will an Antarctic Operation Deep Freeze standby period (December 2010-January 2011). The Committee is aware of a rootcause failure-analysis into the underlying cause of the engine wear. The Committee is to be briefed on its results upon its completion and the Coast Guard’s plans to address them. (Page 86) Congressional Research Service 4137 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The report also states: POLAR OPERATIONS AND MAINTENANCE FUNDING The Committee notes the budget request once again does not transfer operating and maintenance funds for the polar icebreakers from the National Science Foundation [NSF] to the Coast Guard despite congressional direction to the contrary. P.L. 111-117 transfers $54,000,000 from the NSF to the Coast Guard for icebreaking services to cover all anticipated operation and maintenance costs for fiscal year 2010.76 For fiscal year 2012, the Committee expects the operating and maintenance budget authority and associated FTE to be included in the Coast Guard’s budget request. The Coast Guard expects the Polar Star to be reactivated in fiscal year 2013. In keeping with the standard practice of crewing ships in advance to ensure appropriate training and readiness, fielding a crew for the Polar Star is required in fiscal year 2012. The Committee expects sufficient funding to be included in the Coast Guard’s fiscal year 2012 request for this purpose. The Committee also notes that the Coast Guard’s analysis of national mission needs in the high latitude regions has yet to be completed. This effort was funded in fiscal year 2009 to inform the national polar policy debate. The results of this study are to be submitted expeditiously and include projected assets and resources necessary to address identified requirements. (Page 80; material in brackets as in original) Coast Guard Authorization Act of 2010 (H.R. 3619/P.L. 111-281) H.R. 3619 was passed by the House on October 23, 2009, and by the Senate on May 7, 2010. The Senate-passed version substituted the text of S. 1194 as reported by the Senate Commerce, Science, and Transportation Committee (see below), with modifications. The House and Senate resolved their differences and passed the final version of the bill on September 29 and 30, 2010. The bill was presented to the President on October 4, 2010, and signed into law as P.L. 111-281 on October 15, 2010. House The Coast Guard Authorization Act of 2010 (H.R. 3619) as reported by the House Committee on Transportation and Infrastructure (H.Rept. 111-303, Part 1, of October 16, 2009) contains two provisions relating to polar icebreaking—Section 311 and Section 1316. 76 The FY2010 Consolidated Appropriations Act (H.R. 3288/P.L. 111-117 of December 16, 2009) states, in the paragraph that appropriates funds for NSF research and related activities, that the funds are made available provided, among other things, “That from funds specified in the fiscal year 2010 budget request for icebreaking services, $54,000,000 shall be transferred to the U.S. Coast Guard ‘Operating Expenses’ within 60 days of enactment of this Act….” The conference report on H.R. 3288 (H.Rept. 111-366 of December 8, 2009) states: The conference agreement transfers $54,000,000 from NSF to the United States Coast Guard (USCG) for icebreaking services to cover all anticipated operation and maintenance costs for fiscal year 2010. The conferees expect that in future years all operation and maintenance budget authority for these USCG icebreakers will be requested by the Department of Homeland Security. (Page 766) Congressional Research Service 4238 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Section 311 states: SEC. 311. ARCTIC MARINE SHIPPING ASSESSMENT IMPLEMENTATION. (a) Purpose- The purpose of this section is to ensure safe, secure, and reliable maritime shipping in the Arctic including the availability of aids to navigation, vessel escorts, spill response capability, and maritime search and rescue in the Arctic. (b) International Maritime Organization Agreements- To carry out the purpose of this section, the Secretary of the department in which the Coast Guard is operating shall work through the International Maritime Organization to establish agreements to promote coordinated action among the United States, Russia, Canada, Iceland, Norway, and Denmark and other seafaring and Arctic nations to ensure, in the Arctic— (1) placement and maintenance of aids to navigation; (2) appropriate icebreaking escort, tug, and salvage capabilities; (3) oil spill prevention and response capability; (4) maritime domain awareness, including long-range vessel tracking; and (5) search and rescue. (c) Coordination by Committee on the Maritime Transportation System- The Committee on the Maritime Transportation System established under a directive of the President in the Ocean Action Plan, issued December 17, 2004, shall coordinate the establishment of domestic transportation policies in the Arctic necessary to carry out the purpose of this section. (d) Agreements and Contracts- The Secretary of the department in which the Coast Guard is operating may, subject to the availability of appropriations, enter into cooperative agreements, contracts, or other agreements with, or make grants to individuals and governments to carry out the purpose of this section or any agreements established under subsection (b). (e) Icebreaking- The Secretary of the department in which the Coast Guard is operating shall promote safe maritime navigation by means of icebreaking where needed to assure the reasonable demands of commerce. (f) Demonstration Projects- The Secretary of Transportation may enter into cooperative agreements, contracts, or other agreements with, or make grants to, individuals to conduct demonstration projects to reduce emissions or discharges from vessels operating in the Arctic. (g) Authorization of Appropriations- There are authorized to be appropriated— (1) to the Secretary of the department in which the Coast Guard is operating— (A) $5,000,000 for each of fiscal years 2011 through 2015 for seasonal operations in the Arctic; and (B) $10,000,000 for each of fiscal years 2012 through 2015 to carry out agreements established under subsection (d); and Congressional Research Service 4339 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress (2) to the Secretary of Transportation $5,000,000 for each of fiscal years 2011 through 2015 to conduct demonstration projects under subsection (f). (h) Icebreakers(1) ANALYSES- Not later than 90 days after the date of enactment of this Act or the date of completion of the ongoing High Latitude Study to assess Arctic polar ice-breaking mission requirements, which ever occurs later, the Commandant of the Coast Guard shall— (A) conduct a comparative cost-benefit analysis of— (i) rebuilding, renovating, or improving the existing fleet of icebreakers for operation by the Coast Guard, (ii) constructing new icebreakers for operation by the Coast Guard, and (iii) any combination of the activities described in clauses (i) and (ii), to carry out the missions of the Coast Guard; and (B) conduct an analysis of the impact on mission capacity and the ability of the United States to maintain a presence in the Arctic regions through the year 2020 if recapitalization of the icebreaker fleet, either by constructing new icebreakers or rebuilding, renovating, or improving the existing fleet of icebreakers, is not fully funded. (2) REPORTS TO CONGRESS(A) Not later than 90 days after the date of enactment of this Act or the date of completion of the ongoing High Latitude Study to assess Arctic ice-breaking mission requirements, which ever occurs later, the Commandant of the Coast Guard shall submit a report containing the results of the study, together with recommendations the Commandant deems appropriate under section 93(a)(24) of title 14, United States Code, to the Senate Committee on Commerce, Science, and Transportation and the House of Representatives Committee on Transportation and Infrastructure. (B) Not later than 1 year after the date of enactment of this Act, the Commandant shall submit reports containing the results of the analyses required under subparagraphs (A) and (B) of paragraph (1), together with recommendations the Commandant deems appropriate under section 93(a)(24) of title 14, United States Code, to the Senate Committee on Commerce, Science, and Transportation and the House of Representatives Committee on Transportation and Infrastructure. (i) Arctic Definition- In this section the term ‘Arctic’ has the same meaning as in section 112 of the Arctic Research and Policy Act of 1984 (15 U.S.C. 4111). Section 1316 states: SEC. 1316. ASSESSMENT OF NEEDS FOR ADDITIONAL COAST GUARD PRESENCE IN HIGH LATITUDE REGIONS. Within 270 days after the date of enactment of this Act, the Secretary of the department in which the Coast Guard is operating shall submit a report to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives assessing the need for additional Coast Guard prevention and response capability in the high latitude regions. The assessment shall address Congressional Research Service 4440 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress needs for all Coast Guard mission areas, including search and rescue, marine pollution response and prevention, fisheries enforcement, and maritime commerce. The Secretary shall include in the report— (1) an assessment of the high latitude operating capabilities of all current Coast Guard assets, including assets acquired under the Deepwater program; (2) an assessment of projected needs for Coast Guard forward operating bases in the high latitude regions; (3) an assessment of shore infrastructure, personnel, logistics, communications, and resources requirements to support Coast Guard forward operating bases in the high latitude regions; (4) an assessment of the need for high latitude icebreaking capability and the capability of the current high latitude icebreaking assets of the Coast Guard, including— (A) whether the Coast Guard’s high latitude icebreaking fleet is meeting current mission performance goals; (B) whether the fleet is capable of meeting projected mission performance goals; and (C) an assessment of the material condition, safety, and working conditions aboard high latitude icebreaking assets, including the effect of those conditions on mission performance; (5) a detailed estimate of acquisition costs for each of the assets (including shore infrastructure) necessary for additional prevention and response capability in high latitude regions for all Coast Guard mission areas, and an estimate of operations and maintenance costs for such assets for the initial 10-year period of operations; and (6) detailed cost estimates (including operating and maintenance for a period of 10 years) for high latitude icebreaking capability to ensure current and projected future mission performance goals are met, including estimates of the costs to— (A) renovate and modernize the Coast Guard’s existing high latitude icebreaking fleet; and (B) replace the Coast Guard’s existing high latitude icebreaking fleet. Senate On May 7, 2010, the Senate passed S.Amdt. 3912, which amended H.R. 3619 by substituting the text of S. 1194 as reported by the Senate Commerce, Science, and Transportation Committee (see below), with modifications. The Senate then passed H.R. 3619 the same day. Section 603 of the Senate-passed version of H.R. 3619 states: SEC. 603. ICEBREAKERS. (a) ANALYSES- Not later than 90 days after the date of enactment of this Act or the date of completion of the ongoing High Latitude Study to assess polar ice-breaking mission requirements, whichever occurs later, the Commandant of the Coast Guard shall require a nongovernmental, independent third party (other than the National Academy of Sciences) which has extensive experience in the analysis of military procurements to— Congressional Research Service 4541 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress (1) conduct a comparative cost-benefit analysis, taking into account future Coast Guard budget projections (which assume Coast Guard budget growth of no more than inflation) and other recapitalization needs, of— (A) rebuilding, renovating, or improving the existing fleet of polar icebreakers for operation by the Coast Guard, (B) constructing new polar icebreakers for operation by the Coast Guard, (C) construction of new polar icebreakers by the National Science Foundation for operation by the Foundation, (D) rebuilding, renovating, or improving the existing fleet of polar icebreakers by the National Science Foundation for operation by the Foundation, and (E) any combination of the activities described in subparagraph (A), (B), (C), or (D) to carry out the missions of the Coast Guard and the National Science Foundation; (2) conduct an analysis of the impact on mission capacity and the ability of the United States to maintain a presence in the polar regions through the year 2020 if recapitalization of the polar icebreaker fleet, either by constructing new polar icebreakers or rebuilding, renovating, or improving the existing fleet of polar icebreakers, is not fully funded; and (3) conduct a comprehensive analysis of the impact on all Coast Guard activities, including operations, maintenance, procurements, and end strength, of the acquisition of polar icebreakers described in paragraph (1) by the Coast Guard or the National Science Foundation assuming that total Coast Guard funding will not increase more than the annual rate of inflation. (b) Reports to Congress(1) Not later than one year and 90 days after the date of enactment of this Act or the date of completion of the ongoing High Latitude Study to assess polar ice-breaking mission requirements, whichever occurs later, the Commandant of the Coast Guard shall submit a report containing the results of the study, together with recommendations the Commandant deems appropriate under section 93(a)(24) of title 14, United States Code, to the Senate Committee on Commerce, Science, and Transportation and the House of Representatives Committee on Transportation and Infrastructure. (2) Not later than 1 year after the date of enactment of this Act, the Commandant shall submit reports containing the results of the analyses required under paragraphs (1) and (2) of subsection (a), together with recommendations the Commandant deems appropriate under section 93(a)(24) of title 14, United States Code, to the Senate Committee on Commerce, Science, and Transportation and the House of Representatives Committee on Transportation and Infrastructure. Final Version Section 307 of H.R. 3619/P.L. 111-281 states: SEC. 307. ARCTIC MARINE SHIPPING ASSESSMENT IMPLEMENTATION. Congressional Research Service 4642 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress (a) Purpose- The purpose of this section is to ensure safe and secure maritime shipping in the Arctic including the availability of aids to navigation, vessel escorts, spill response capability, and maritime search and rescue in the Arctic. (b) International Maritime Organization Agreements- To carry out the purpose of this section, the Secretary of the department in which the Coast Guard is operating is encouraged to enter into negotiations through the International Maritime Organization to conclude and execute agreements to promote coordinated action among the United States, Russia, Canada, Iceland, Norway, and Denmark and other seafaring and Arctic nations to ensure, in the Arctic— (1) placement and maintenance of aids to navigation; (2) appropriate marine safety, tug, and salvage capabilities; (3) oil spill prevention and response capability; (4) maritime domain awareness, including long-range vessel tracking; and (5) search and rescue. (c) Coordination by Committee on the Maritime Transportation System- The Committee on the Maritime Transportation System established under a directive of the President in the Ocean Action Plan, issued December 17, 2004, shall coordinate the establishment of domestic transportation policies in the Arctic necessary to carry out the purpose of this section. (d) Agreements and Contracts- The Secretary of the department in which the Coast Guard is operating may, subject to the availability of appropriations, enter into cooperative agreements, contracts, or other agreements with, or make grants to individuals and governments to carry out the purpose of this section or any agreements established under subsection (b). (e) Icebreaking- The Secretary of the department in which the Coast Guard is operating shall promote safe maritime navigation by means of icebreaking where necessary, feasible, and effective to carry out the purposes of this section. (f) Independent Ice Breaker Analyses(1) IN GENERAL- Not later than 90 days after the date of enactment of this Act, the Secretary of the department in which the Coast Guard is operating shall require a nongovernmental, independent third party (other than the National Academy of Sciences) that has extensive experience in the analysis of military procurements, to— (A) conduct a comparative cost-benefit analysis, taking into account future Coast Guard budget projections (which assume Coast Guard budget growth of no more than inflation) and other recapitalization needs, of— (i) rebuilding, renovating, or improving the existing fleet of polar icebreakers for operation by the Coast Guard; (ii) constructing new polar icebreakers for operation by the Coast Guard; Congressional Research Service 4743 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress (iii) construction of new polar icebreakers by the National Science Foundation for operation by the Foundation; (iv) rebuilding, renovating, or improving the existing fleet of polar icebreakers by the National Science Foundation for operation by the Foundation; and (v) any combination of the activities described in clause (i), (ii), (iii), or (iv) to carry out the missions of the Coast Guard and the National Science Foundation; and (B) conduct a comprehensive analysis of the impact on all Coast Guard activities, including operations, maintenance, procurements, and end strength, of the acquisition of polar icebreakers described in subparagraph (A) by the Coast Guard or the National Science Foundation assuming that total Coast Guard funding will not increase more than the annual rate of inflation. (2) REPORT- Not later than 1 year after the date of enactment of this Act, the Secretary of the department in which the Coast Guard is operating shall submit a report containing the results of the analyses required under paragraph (1), together with recommendations the Commandant considers appropriate under section 93(a)(24) of title 14, United States Code, to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives. (g) High-Latitude Study- Not later than 90 days after the date of enactment of this Act or the date of completion of the ongoing High-Latitude Study to assess polar icebreaking mission requirements for all Coast Guard missions including search and rescue, marine pollution response and prevention, fisheries enforcement, and maritime commerce, whichever occurs later, the Commandant of the Coast Guard shall submit a report containing the results of the study, together with recommendations the Commandant considers appropriate under section 93(a)(24) of title 14, United States Code, to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives. (h) Arctic Definition- In this section the term ‘Arctic’ has the same meaning as in section 112 of the Arctic Research and Policy Act of 1984 (15 U.S.C. 4111). FY2010 and FY2011 Coast Guard Authorization Bill (S. 1194) Senate The Senate Commerce, Science, and Transportation Committee reported S. 1194 on October 30, 2009 (S.Rept. 111-95 of October 30, 2009). Section 604 of S. 1194 as reported by the committee states: SEC. 604. ICEBREAKERS. (a) ANALYSES- Not later than 90 days after the date of enactment of this Act or the date of completion of the ongoing High Latitude Study to assess polar ice-breaking mission requirements, which ever occurs later, the Commandant of the Coast Guard shall— (1) conduct a comparative cost-benefit analysis of— (A) rebuilding, renovating, or improving the existing fleet of polar icebreakers for operation by the Coast Guard, Congressional Research Service 4844 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress (B) constructing new polar icebreakers for operation by the Coast Guard for operation by the Coast Guard, and (C) any combination of the activities described in subparagraphs (A) and (B), to carry out the missions of the Coast Guard; and (2) conduct an analysis of the impact on mission capacity and the ability of the United States to maintain a presence in the polar regions through the year 2020 if recapitalization of the polar icebreaker fleet, either by constructing new polar icebreakers or rebuilding, renovating, or improving the existing fleet of polar icebreakers, is not fully funded. (b) Reports to Congress(1) Not later than 90 days after the date of enactment of this Act or the date of completion of the ongoing High Latitude Study to assess polar ice-breaking mission requirements, which ever occurs later, the Commandant of the Coast Guard shall submit a report containing the results of the study, together with recommendations the Commandant deems appropriate under section 93(a)(24) of title 14, United States Code, to the Senate Committee on Commerce, Science, and Transportation and the House of Representatives Committee on Transportation and Infrastructure. (2) Not later than 1 year after the date of enactment of this Act, the Commandant shall submit reports containing the results of the analyses required under paragraphs (1) and (2) of subsection (a), together with recommendations the Commandant deems appropriate under section 93(a)(24) of title 14, United States Code, to the Senate Committee on Commerce, Science, and Transportation and the House of Representatives Committee on Transportation and Infrastructure. S.Rept. 111-95 summarizes Section 604 on pages 24-25. On May 7, 2010, the Senate passed S.Amdt. 3912, which amended H.R. 3619 (see above) by substituting the text of S. 1194 as reported by the Senate Commerce, Science, and Transportation Committee, with modifications. The Senate then passed H.R. 3619 the same day. Arctic Marine Shipping Assessment Implementation Act of 2009 (H.R. 2865/S. 1514/S. 1561) House H.R. 2865 was introduced on June 12, 2009. Section 8(1)(A) would authorize appropriations of $750 million per year in FY2011 and FY2012 for the construction of two polar capable icebreakers. Section 2 states that Congress finds and declares several things, including the following: The United States has continuing research, security, environmental, and commercial interests in the Arctic region that rely on the availability of icebreaker platforms of the Coast Guard. The Polar Class icebreakers commissioned in the 1970s are in need of replacement. and Congressional Research Service 4945 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Building new icebreakers, mustering international plans for aids to navigation and other facilities, and establishing coordinated shipping regulations and oil spill prevention and response capability through international cooperation, including the approval of the International Maritime Organization, requires long lead times. Beginning those efforts now, with the completion of an Arctic Marine Shipping Assessment by the eight-nation Arctic Council, is essential to protect United States interests given the extensive current use of the Arctic Ocean and adjacent seas by vessels of many nations. Section 3 states: To carry out the purpose of this Act, the Secretary of the department in which the Coast Guard is operating shall work through the International Maritime Organization to establish agreements to promote coordinated action among the United States, Russia, Canada, Iceland, Norway, and Denmark and other seafaring and Arctic nations to ensure, in the Arctic.... (2) appropriate icebreaking escort, tug, and salvage capabilities. Section 6 states, in its entirety: The Secretary of the department in which the Coast Guard is operating shall promote safe maritime navigation by means of icebreaking where needed to assure the reasonable demands of commerce. Senate S. 1514 was introduced on July 24, 2009. Section 8(1)(A) would authorize appropriations of $750 million per year in FY2011 and FY2012 for the construction of two polar capable icebreakers. Section 2 states that Congress finds and declares several things, including the following: The United States has continuing research, security, environmental, and commercial interests in the Arctic region that rely on the availability of icebreaker platforms of the Coast Guard. The Polar Class icebreakers commissioned in the 1970s are in need of replacement. and Building new icebreakers, mustering international plans for aids to navigation and other facilities, and establishing coordinated shipping regulations and oil spill prevention and response capability through international cooperation, including the approval of the International Maritime Organization, requires long lead times. Beginning those efforts now, with the completion of an Arctic Marine Shipping Assessment by the eight-nation Arctic Council, is essential to protect United States interests given the extensive current use of the Arctic Ocean and adjacent seas by vessels of many nations. Section 3 states: To carry out the purpose of this Act, the Secretary of the department in which the Coast Guard is operating shall work through the International Maritime Organization to establish agreements to promote coordinated action among the United States, Russia, Canada, and other seafaring and Arctic nations to ensure, in the Arctic… (2) appropriate icebreaking escort, tug, and salvage capabilities…. Congressional Research Service 5046 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Section 6 states, in its entirety: The Secretary of the department in which the Coast Guard is operating shall promote safe maritime navigation by means of icebreaking where needed to assure the reasonable demands of commerce. S. 1561 was introduced on August 3, 2009. Section 11(a)(1) would authorize appropriations of $40 million in FY2011 for the design of a new polar class icebreaker. Section 11(a)(2) would authorize appropriations of $800 million per year in FY2011 and FY2012 for the construction of two polar capable icebreakers. Section 2 states that Congress finds several things, including the following: The United States has continuing research, security, environmental, and commercial interests in the Arctic region that rely on the availability of polar class icebreakers of the Coast Guard that were commissioned in the 1970s and are in need of replacement. and Building new icebreakers, forward operating bases, aids to navigation, and other facilities, and establishing coordinated shipping regulations and oil spill prevention and response capability through international cooperation requires long lead times. Section 5 states: It is the sense of Congress that, to carry out the purpose of this Act, the Secretary of State, in consultation with the Secretary of Homeland Security, acting through the Commandant of the Coast Guard, should work to establish agreements to promote coordinated action among the United States, Russia, Canada, Iceland, Norway, and Denmark and other seafaring and Arctic nations with respect to… (4) appropriate icebreaking escort, tug, and salvage capabilities…. Section 6 states: (a) Submission of Report Analysis to Congress(1) REQUIREMENT FOR SUBMISSION- Not later than 90 days following the completion of the High Latitude Polar Ice-Breaking Mission Analysis Report, the Commandant of the Coast Guard shall submit to the appropriate committees of Congress— (A) such report; and (B) consistent with section 93(a)(24) of title 14, United States Code, any recommendations of the Commandant related to such report. (2) APPROPRIATE COMMITTEES OF CONGRESS DEFINED- In this subsection, the term ‘appropriate committees of Congress’ means the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives. (b) Mission Requirements Analysis- Congressional Research Service 5147 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress (1) MISSION REQUIREMENTS ANALYSIS- Not later than 90 days after the date of the enactment of this Act, the Commandant of the Coast Guard shall, subject to the availability of appropriations, execute a contract with an independent entity to— (A) conduct an analysis of future mission requirements of the Coast Guard in the Arctic and Antarctic; and (B) estimate the necessary resources to provide for such requirements. (2) SUBMISSION OF ANALYSIS AND ESTIMATE- Not later than 120 days after the date that the contract described in paragraph (1) is executed, the analysis and estimate described in subparagraph (A) and (B) of that paragraph shall be submitted to— (A) the appropriate committees of Congress; (B) the Commandant of the Coast Guard; and (C) the Comptroller General of the United States. (3) ADDITIONAL RECOMMENDATIONS- Not later than 90 days after the submission of the analysis and estimate described in paragraph (2)— (A) the Commandant of the Coast Guard shall submit to the appropriate committees of Congress, consistent with section 93(a)(24) of title 14, United States Code, any recommendations of the Commandant related to such analysis and estimate; and (B) the Comptroller General shall submit to the appropriate committees of Congress any recommendations of the Comptroller General related to such analysis and estimate. (4) APPROPRIATE COMMITTEES OF CONGRESS DEFINED- In this subsection, the term ‘appropriate committees of Congress’ means— (A) the Committee on Commerce, Science, and Transportation and the Committee on Homeland Security and Governmental Affairs of the Senate; and (B) the Committee on Homeland Security and the Committee on Transportation and Infrastructure of the House of Representatives. Section 10 states, in its entirety: Notwithstanding any other provision of law, the Director of the National Science Foundation shall transfer all amounts provided pursuant to any Act for the procurement of polar icebreaking services to the United States Coast Guard Appropriation Accounts, and such amounts shall remain available until expended for operating expenses, renovation, and improvement. Congressional Research Service 5248 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress FY2010 DHS Appropriations Act (H.R. 2892/P.L. 111-83) House The House Appropriations Committee, in its report (H.Rept. 111-157 of June 16, 2009) on H.R. 2892, did not recommend any funding in the Coast Guard’s AC&I account for polar icebreaker sustainment or acquisition of new polar icebreakers. The report stated: POLAR ICEBREAKING OPERATING AND MAINTENANCE COSTS AND FUTURE POLAR NEEDS The Committee continues to be concerned about Coast Guard’s ability to meet its polar operations mission requirements and provide the United States with the capability to support national interests in the polar regions. These interests extend well beyond the realm of scientific research. As such, last year the Committee directed the Coast Guard and the National Science Foundation (NSF) to renegotiate the existing agreement on polar icebreaking in order to return the budget for operating and maintaining these vessels to the Coast Guard for fiscal year 2010, and to provide a new joint plan for Coast Guard support of scientific research by NSF and other Federal agencies, which was to be included in the 2010 budget request. No agreement was reached, and no plan was submitted. Negotiations are apparently underway between the Coast Guard and NSF, but the budget has yet to be returned to the Coast Guard accounts. Therefore, the Committee directs the Coast Guard to continue negotiating the agreement for the return of icebreaking in the 2011 budget, and to provide the joint plan for Coast Guard support as soon as possible. The Committee further directs the Coast Guard to use existing appropriations to continue its analysis of national mission needs in the high latitude regions to inform national polar policy. (Pages 78-79) Senate The Senate Appropriations Committee, in its report (S.Rept. 111-31 of June 18, 2009) on the FY2010 DHS appropriation bill (S. 1298), recommended $32.5 million in the Coast Guard’s AC&I account for the reactivation and service life extension of Polar Star. Of this amount, $27.3 million is in an AC&I line item for polar icebreaker sustainment, and the remaining $5.2 million is included within a line item for AC&I direct personnel costs (page 76). The Senate included the provisions of S. 1298 in an amendment to H.R. 2892. The committee’s report on S. 1298 stated: POLAR ICEBREAKER SUSTAINMENT The Committee recommends $32,500,000 above the budget request to complete the reactivation and service life extension of Coast Guard Cutter Polar Star. Of this amount, $5,200,000 is funded in the AC&I direct personnel costs PPA [program, project, or activity]. Returning Polar Star to operational status is vital to ensuring the U.S. Government has the ability to project U.S. sovereignty and protect the broad range of security, economic, and environmental interests in the Arctic and Antarctic. Within this amount, the Coast Guard shall begin survey and design and conduct a business case analysis for either a new heavy polar icebreaker class or a major service life extension project for existing heavy icebreakers. The only existing heavy polar class icebreaker, the Polar Sea, has only 7 years remaining in its useful life. (Page 78) Congressional Research Service 5349 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress The report also stated: POLAR OPERATIONS AND MAINTENANCE FUNDING The Committee notes the budget request did not include transfer of operating and maintenance funds for the polar icebreakers from the National Science Foundation [NSF] to the Coast Guard as directed in the joint explanatory statement accompanying the Department of Homeland Security Appropriations Act, 2009 (Public Law 110–329). For fiscal year 2011, the Committee expects the operating and maintenance budget authority and associated FTE to be included in the Coast Guard’s request. The two agencies shall update the existing Memorandum of Agreement to reflect the change in budget authority. (page 73; material in brackets as in original) Conference The conference report (H.Rept. 111-298 of October 13, 2009) on H.R. 2892/P.L. 111-83 of October 28, 2009, provided $32.5 million to complete the reactivation and service life extension of Polar Star. Of this total, $27.3 million was provided in the AC&I account in a line item entitled “Polar Icebreaker sustainment” (Page 87). The conference report stated: Polar Icebreaker Sustainment The conference agreement provides an additional $32,500,000 to complete the reactivation and service life extension of the Coast Guard Cutter POLAR STAR as proposed by the Senate. No additional funding for this activity was proposed by the House. Of this amount, $5,200,000 is provided in the Acquisition, Construction, and Improvements direct personnel costs PPA [program, project, or activity]. Funds shall be applied as specified in the Senate report. The conferees believe returning POLAR STAR to operational status is vital to national interests in the polar regions. According to the Coast Guard the only existing operational heavy icebreaker, the POLAR SEA, has only five years of service life remaining. The absence of requested funding to complete fiscal year 2009 efforts to reactivate POLAR STAR, combined with the lack of compliance with standing Congressional direction on the polar icebreaking budget, implies a broader lack of commitment to sustaining polar capabilities and achieving longterm, strategic objectives in the Arctic. The conferees direct the Coast Guard to brief the Committees no later than December 15, 2009, on the program execution plan for reactivation of POLAR STAR and the status of resources required to achieve mission requirements for polar operations. (Page 89) The conference report also stated, the section on the Coast Guard’s Operating Expenses (OE) account: Polar Icebreaking Operations and Maintenance Funding The conferees expect polar icebreaking operations and maintenance budget authority and associated FTE to be included in the Coast Guard’s budget request for fiscal year 2011. The National Science Foundation and Coast Guard shall update the existing Memorandum of Agreement to reflect the change in budget authority as proposed by the Senate. Furthermore, the conferees direct the Coast Guard to follow the direction regarding the high latitude study as outlined in the House report. (Page 85) Congressional Research Service 5450 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress American Recovery and Reinvestment Act of 2009 (H.R. 1/P.L. 111-5) A Senate version of H.R. 1 (amendment in Senate, January 30, 2009) stated, in the section on the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) account, that of the funds provided in the bill for the AC&I account, “$87,500,000 shall be for the design of a new polar icebreaker or the renovation of an existing polar icebreaker, and major repair and maintenance of existing polar icebreakers.” The provision was not included in other House and Senate versions of the bill, or in the conference version of the bill, which was signed into law on February 17, 2009. FY2009 DHS Appropriations Act (H.R. 2638/P.L. 110-329) House The House Appropriations Committee, in its report (H.Rept. 110-862 of September 18, 2008) on the FY2009 DHS appropriations bill (H.R. 6947), stated: POLAR ICEBREAKING OPERATING AND MAINTENANCE COSTS AND FUTURE POLAR NEEDS The Committee is concerned about Coast Guard’s ability to meet its polar operations mission requirements and provide the United States with the capability to support national interests in the polar regions. The Committee provides $200,000, as requested, to conduct an analysis of national mission needs in the high latitude regions to inform the national polar policy debate. In fiscal year 2006 the Committees on Appropriations approved an Administration request for the National Science Foundation (NSF), the primary user of the three Coast Guard polar icebreaker vessels, to fund the costs of operating and maintaining these aging vessels. Because it has become more apparent that the national interest in the polar regions extends beyond scientific research, the Committee questions whether this arrangement should continue. Accordingly, the Committee directs Coast Guard and NSF to renegotiate the existing agreement in order to return the budget for operating and maintaining these vessels to Coast Guard for fiscal year 2010. This change is consistent with a new joint plan for Coast Guard support of scientific research by NSF and other Federal agencies, which also is to be included in the 2010 budget request. NSF shall retain responsibility for the contracting of scientific support services that Coast Guard does not have the capability to perform or cannot perform on a cost-competitive basis. The Committee is aware of a $4,000,000 funding shortfall related to the caretaker status of the POLAR STAR, and directs Coast Guard to address this shortfall within the amounts appropriated for fiscal year 2009. (Page 82) Senate The FY2009 DHS appropriations bill (S. 3181) as reported by the Senate appropriations committee would make available about $6.28 billion for the Coast Guard’s Operating Expenses (OE) account, provided, among other things, “that notwithstanding any other provision of law, $4,000,000 of the amounts made available under this heading may be available to maintain the USCGC POLAR STAR in caretaker status.” The Senate Appropriations Committee, in its report (S.Rept. 110-396 of June 23, 2008) on S. 3181, stated: Congressional Research Service 5551 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress POLAR ICEBREAKERS The Committee reiterates its concern with the Coast Guard’s ability to meet its current and projected polar operations responsibilities. According to correspondence from the Commandant on May 23, 2008, the Coast Guard will submit a report on polar mission requirements no later than August 31, 2008. The Committee expects this report to address the concerns detailed in the explanatory statement accompanying the Department of Homeland Security Appropriations Act, 2008. The Committee also expects all costs to operate the polar icebreakers for National Science Foundation [NSF] research, including unanticipated maintenance, will be reimbursed by NSF. However, the Committee notes that the NSF budget request states, “Effective with the fiscal year 2009 budget, NSF will no longer provide funds to maintain the USCGC Polar Star in caretaker status because NSF does not envision current or future use of this vessel in support of its mission.” Due to the changing environmental conditions and increased activity in the polar regions, as well as the Coast Guard’s multi-mission responsibilities in the polar regions that are not science related, the Committee includes statutory language making an additional $4,000,000 available to maintain the USCGC Polar Star in caretaker status. The Committee also notes that the forthcoming report on Coast Guard polar mission requirements will address the sustainability of the current operations and maintenance cost sharing arrangement between the Coast Guard and the NSF to support both current and projected polar icebreaker operations. (Page 81) Compromise The FY2009 DHS appropriations bill became Division D of H.R. 2638/P.L. 110-329 of September 30, 2008, a consolidated appropriations act. H.R. 2638 began as a DHS appropriations act and was then amended to become a consolidated appropriations act that contained that includes, among other things, the FY2009 DHS appropriations act. In lieu of a conference report, there was a compromise version of H.R. 2638 that was accompanied by an explanatory statement. Section 4 of H.R. 2638 stated that the explanatory statement “shall have the same effect with respect to the allocation of funds and implementation of this Act as if it were a joint explanatory statement of a committee of conference.” H.R. 2638 provided $30.3 million for polar icebreaker sustainment. The funding was provided in a new line item in the surface ships section of the Deepwater portion of the Coast Guard’s Acquisition, Construction, and Improvements (AC&I) appropriation account. The explanatory statement stated: Polar Icebreakers One of the Coast Guard’s missions is to provide the United States with the capability to support national interests in the polar regions. In a report recently submitted, the Coast Guard stated that the United States will need a maritime surface and air presence in the Arctic sufficient to support prevention and response regimes as well as diplomatic objectives. However, no funding has been requested for the Coast Guard’s aging icebreakers despite its inability to meet current and projected polar operations mission responsibilities. The Coast Guard is directed to follow House report direction regarding the polar icebreaking operating budget. The Coast Guard should work with the National Science Foundation in the coming year to renegotiate the existing polar icebreaking agreement in order to return the budget for operating and maintaining its polar icebreakers to the Coast Guard in fiscal year 2010. The AC&I appropriation includes $30,300,000 to reactivate the USCGC POLAR STAR for an additional 7-10 years of service life. Congressional Research Service 5652 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Coast Guard Authorization Act For FY2008 (H.R. 2830/S. 1892) House Section 422 of H.R. 2830 as passed by the House stated: SEC. 422. ASSESSMENT OF NEEDS FOR ADDITIONAL COAST GUARD PRESENCE IN HIGH LATITUDE REGIONS. Within 270 days after the date of enactment of this Act, the Secretary of the department in which the Coast Guard is operating shall submit a report to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives assessing the need for additional Coast Guard prevention and response capability in the high latitude regions. The assessment shall address needs for all Coast Guard mission areas, including search and rescue, marine pollution response and prevention, fisheries enforcement, and maritime commerce. The Secretary shall include in the report— (1) an assessment of the high latitude operating capabilities of all current Coast Guard assets, including assets acquired under the Deepwater program; (2) an assessment of projected needs for Coast Guard forward operating bases in the high latitude regions; (3) an assessment of shore infrastructure, personnel, logistics, communications, and resources requirements to support Coast Guard forward operating bases in the high latitude regions; (4) an assessment of the need for high latitude icebreaking capability and the capability of the current high latitude icebreaking assets of the Coast Guard, including— (A) whether the Coast Guard’s high latitude icebreaking fleet is meeting current mission performance goals; (B) whether the fleet is capable of meeting projected mission performance goals; and (C) an assessment of the material condition, safety, and working conditions aboard high latitude icebreaking assets, including the effect of those conditions on mission performance; (5) a detailed estimate of acquisition costs for each of the assets (including shore infrastructure) necessary for additional prevention and response capability in high latitude regions for all Coast Guard mission areas, and an estimate of operations and maintenance costs for such assets for the initial 10-year period of operations; and (6) detailed cost estimates (including operating and maintenance for a period of 10 years) for high latitude icebreaking capability to ensure current and projected future mission performance goals are met, including estimates of the costs to— (A) renovate and modernize the Coast Guard’s existing high latitude icebreaking fleet; and (B) replace the Coast Guard’s existing high latitude icebreaking fleet. Congressional Research Service 5753 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Senate Section 917 of S. 1892 as reported in the Senate stated: SEC. 917. ICEBREAKERS. (a) IN GENERAL—The Secretary of the department in which the Coast Guard is operating shall acquire or construct 2 polar icebreakers for operation by the Coast Guard in addition to its existing fleet of polar icebreakers. (b) NECESSARY MEASURES—The Secretary shall take all necessary measures, including the provision of necessary operation and maintenance funding, to ensure that— (1) the Coast Guard maintains, at a minimum, its current vessel capacity for carrying out ice breaking in the Arctic and Antarctic, Great Lakes, and New England regions; and (2) any such vessels that are not fully operational are brought up to, and maintained at full operational capability. (c) REIMBURSEMENT—Nothing in this section shall preclude the Secretary from seeking reimbursement for operation and maintenance costs of such polar icebreakers from other Federal agencies and entities, including foreign countries, that benefit from the use of the icebreakers. (d) AUTHORIZATION OF APPROPRIATIONS—There are authorized to be appropriated for fiscal year 2008 to the Secretary of the department in which the Coast Guard is operating such sums as may be necessary to acquire the icebreakers authorized by subsection (a), as well as maintaining and operating the icebreaker fleet as authorized in subsection (b). The Senate Commerce, Science, and Transportation Committee, in its report (S.Rept. 110-261 of February 5, 2008) on S. 1892, stated: Section 917 would require the Secretary to acquire or construct two new polar icebreakers for operation by the Coast Guard. It also would instruct the Coast Guard to maintain their existing polar icebreakers and return them to operational status, if not operational already. This section would authorize such sums as are necessary to carry out this section. Currently, the Coast Guard’s icebreaker fleet is funded by the National Science Foundation. However, the funding for these vessels has been inconsistent, allowing the Polar Star to fall behind on the maintenance necessary to keep the vessel in operating condition. With some climate models predicting an ice-free Arctic summer in the future, more international expeditions will be headed to the region to examine newly revealed oil and gas reserves and other natural resources. Canada, Russia, and other countries will begin to compete with the United States over jurisdiction and, without a strong polar icebreaker fleet, our Nation will suffer a severe disadvantage. A recent 2007 report by the National Academy of Sciences found that the United States needs to maintain polar icebreaking capacity and construct at least two new polar icebreakers. This provision follows those recommendations. (Page 29) In presenting the CBO’s estimate of the cost of Section 917 of S. 1892 as reported, the report stated: Assuming appropriation of the necessary amounts, CBO estimates that the USCG would spend about $1.4 billion over the next five years to purchase two icebreakers. (Costs to operate and maintain the two new vessels would total about $50 million a year beginning in 2013.) We estimate that an additional $50 million would be spent over the 2008-2010 period Congressional Research Service 5854 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress to recondition an existing USCG icebreaker, which is currently out of operation. Operating and maintaining that vessel would cost about $10 million in 2010 and about $25 million annually thereafter. This estimate is based on information provided by the Coast Guard regarding the cost of constructing, operating, and maintaining such vessels to agency specifications. (Page 8; see also pages 6 and 7) FY2008 Consolidated Appropriations Act (H.R. 2764/P.L. 110-161) FY2008 funding for the Department of Homeland Security (DHS), which includes the Coast Guard, was provided in the FY2008 Consolidated Appropriations Act (H.R. 2764/P.L. 110-161 of December 26, 2007). The explanatory statement for H.R. 2764/P.L. 110-161, which is intended to be the equivalent of a conference report for the bill, stated the following in its discussion of Division E (the FY2008 DHS appropriations act): National Interests in the Polar Regions The Committees on Appropriations are concerned about Coast Guard’s ability to meet its polar operations mission requirements and provide the United States with the capability to support national interests in the polar regions. These mission requirements include, but are not limited to: global reach to the North and South poles; monitoring of U.S.-bound vessel traffic transiting international waterways in the far north; support of the International Ice Patrol; and support of other governmental and scientific organizations in pursuit of marine and atmospheric science activities in the polar regions. The Committees on Appropriations are specifically concerned whether Coast Guard’s aging polar icebreaking fleet can meet current mission performance goals and whether this fleet and the service’s small cadre of specialized polar operations personnel are capable of meeting projected mission performance goals in light of changing environmental conditions and increased activity in the polar regions. The National Academy of Sciences made several recommendations in this regard in September 2006, but the Administration has taken no action to implement those recommendations. Therefore, the Commandant is directed to submit a comprehensive polar operations report that fully assesses the Coast Guard’s ability to meet current and projected polar mission requirements and includes an evaluation of how Coast Guard’s current capabilities and resources must be adapted or enhanced to account for changing environmental conditions and increased activity in the polar regions. This report is to include an analysis of the need for any permanent, forward operating presence in the polar regions in order to meet mission requirements and an assessment of the Coast Guard’s ability to meet the requirements of partner agencies operating in the polar regions, such as the National Science Foundation (NSF) and the Departments of Commerce and Defense, under current and projected environmental conditions. Finally, this report should include an appraisal of the sustainability of the current operations and maintenance cost sharing arrangement between the Coast Guard and NSF to support both current and projected polar icebreaker operations. Congressional Research Service 5955 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Appendix C. Bill and Report Language Relating to Study of High-Latitude Operations This appendix presents examples of bill and report language in recent years relating to the study of Coast Guard missions and capabilities for operations in high-latitude areas. These examples, which are taken from Appendix B, include the following: • The explanatory statement for the FY2008 Consolidated Appropriations Act (H.R. 2764/P.L. 110-161 of December 26, 2007), which included FY2008 funding for DHS, stated: “Therefore, the Commandant is directed to submit a comprehensive polar operations report that fully assesses the Coast Guard’s ability to meet current and projected polar mission requirements and includes an evaluation of how Coast Guard’s current capabilities and resources must be adapted or enhanced to account for changing environmental conditions and increased activity in the polar regions. This report is to include an analysis of the need for any permanent, forward operating presence in the polar regions in order to meet mission requirements and an assessment of the Coast Guard’s ability to meet the requirements of partner agencies operating in the polar regions, such as the National Science Foundation (NSF) and the Departments of Commerce and Defense, under current and projected environmental conditions. Finally, this report should include an appraisal of the sustainability of the current operations and maintenance cost sharing arrangement between the Coast Guard and NSF to support both current and projected polar icebreaker operations.” • Section 422 of the FY2008 Coast Guard Authorization Act (H.R. 2830) as passed by the House stated: “Within 270 days after the date of enactment of this Act, the Secretary of the department in which the Coast Guard is operating shall submit a report to the Committee on Commerce, Science, and Transportation of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives assessing the need for additional Coast Guard prevention and response capability in the high latitude regions. The assessment shall address needs for all Coast Guard mission areas, including search and rescue, marine pollution response and prevention, fisheries enforcement, and maritime commerce. The Secretary shall include in the report ... an assessment of the need for high latitude icebreaking capability and the capability of the current high latitude icebreaking assets of the Coast Guard.... ” • The House Appropriations Committee, in its report (H.Rept. 110-862 of September 18, 2008, page 82) on the FY2009 DHS Appropriations Act (H.R. 2638/P.L. 110-329 of September 30, 2008), stated: “The Committee provides $200,000, as requested, to conduct an analysis of national mission needs in the high latitude regions to inform the national polar policy debate.” • The Senate Appropriations Committee, in its report (S.Rept. 110-396 of June 23, 2008, page 81) on the FY2009 DHS Appropriations Act (S. 3181), stated: “According to correspondence from the Commandant on May 23, 2008, the Coast Guard will submit a report on polar mission requirements no later than August 31, 2008. The Committee expects this report to address the concerns detailed in the explanatory statement accompanying the Department of Homeland Security Appropriations Act, 2008.” Congressional Research Service 6056 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress • The House Appropriations Committee, in its report (H.Rept. 111-157 of June 16, 2009, pages 78-79) on the FY2010 DHS Appropriations Act (H.R. 2892/P.L. 111-83 of October 28, 2009), stated: “The Committee further directs the Coast Guard to use existing appropriations to continue its analysis of national mission needs in the high latitude regions to inform national polar policy.” • The Senate Appropriations Committee, in its report (S.Rept. 111-31 of June 18, 2009, page 78) on the FY2010 DHS Appropriations Act (S. 1298), stated: “Within this amount, the Coast Guard shall begin survey and design and conduct a business case analysis for either a new heavy polar icebreaker class or a major service life extension project for existing heavy icebreakers.” • The conference report (H.Rept. 111-298 of October 13, 2009, page 85) on the FY2010 DHS Appropriations Act (H.R. 2892/P.L. 111-83 of October 28, 20097), stated: “Furthermore, the conferees direct the Coast Guard to follow the direction regarding the high latitude study as outlined in the House report.” • Sections 311(h) and 1316 of the Coast Guard Authorization Act of 2010 (H.R. 3619) as reported by the House Committee on transportation and Infrastructure (H.Rept. 111-303, part 1, of October 16, 2009) (see Appendix B for the full texts of these sections). • Section 603 of the Coast Guard Authorization Act of 2010 (H.R. 3619) as passed by the Senate (see Appendix B for the full text of this section). • Sections 307(f) and 307(g) of the final version of the Coast Guard Authorization Act of 2010 (H.R. 3619/P.L. 111-281 of October 15, 2010) (see Appendix B for the full texts of these sections). • The Senate Appropriations Committee, in its report (S.Rept. 111-222 of July 19, 2010, page 80) on the FY2011 DHS Appropriations Act (S. 3607), stated: “The Committee also notes that the Coast Guard’s analysis of national mission needs in the high latitude regions has yet to be completed. This effort was funded in fiscal year 2009 to inform the national polar policy debate. The results of this study are to be submitted expeditiously and include projected assets and resources necessary to address identified requirements.” The High Latitude Study has a cover date of July 2010. The study was provided to Congress in July 2011. The Coast Guard states that the study was provided to Congress in response to the Coast Guard Authorization Act of 2010 (H.R. 3619/P.L. 111-281), which was enacted into law on October 15, 2010.77 77 Source: Email from Coast Guard Congressional Affairs office to CRS, August 1, 2011. Congressional Research Service 6157 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress Appendix D. May 2008 Memorandum from DOD Combatant Commanders This appendix reprints the text of a May 21, 2008, memorandum for the Chairman of the Joint Chiefs of Staff on the topic of icebreaker support signed by three DOD combatant commanders, each a 4-star general or flag officer.78 MEMORANDUM FOR CHAIRMAN, JOINT CHIEFS OF STAFF FROM: CDR USPACOM / CDR USTRANSCOM / CDR USNORTHCOM SUBJECT: Icebreaker Support 1. The United States has enduring national, strategic, and economic interests in the Arctic and Antarctic. In the north, the United States is an Arctic nation with broad and fundamental national security interests. In addition to the essential requirements for homeland security and maritime domain awareness, the effects of climate change and increasing economic activity require a more active presence in this maritime domain. In the south, the United States maintains three scientific stations. While the mission of the stations is largely scientific, their presence secures the United States’ influential role in the Antarctic Treaty decision making process and maintains the balance necessary to maintain our position on Antarctic sovereignty. 2. To assert our interests in these regions, the United States needs assured access with reliable icebreaking ships. Today, however, two of the three Coast Guard icebreakers are nearing the end of their service lives, with one relegated to caretaker status. Over the past 10 years some routine maintenance has been deferred and there is no service life extension program for these ships. As a result, the nation’s icebreaking capability has diminished substantially and is at risk of being unable to support our national interests in the Arctic regions. An example of our reduced icebreaking capability is last season’s McMurdo Station resupply mission where USNS GIANELLA spent 50 hours in pack-ice awaiting escort from a leased Swedish icebreaker. 3. In summary, icebreakers are essential instruments of United States policy in the polar regions. We therefore recommend Joint Chiefs of Staff support for the following: —A program for the construction of new polar icebreakers to be operated by the Coast Guard. —Coast Guard funding to keep existing icebreakers viable until the new ships enter service. —Sufficient Coast Guard operations funding to provide increased, regular and reliable icebreaker presence in the polar regions. 78 Memorandum for Chairman, Joint Chiefs of Staff, from CDR USPACOM / CDR USTRANSCOM / CDR USNOTHCOM, Subject: Icebreaker Support. The Navy Office of Legislative Affairs provided CRS with a copy of the memorandum on September 11, 2008. Congressional Research Service 6258 Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress [signed] Victor E. Renuart General, USAF Commander U.S. Northern Command Norton A. Schwartz General, USAF Commander U. S. Transportation Command Timothy J. Keating Admiral, USN Commander U.S. Pacific Command cc : Commandant, U.S. Coast Guard Author Contact Information Ronald O'Rourke Specialist in Naval Affairs rorourke@crs.loc.gov, 7-7610 Congressional Research Service 6359