.
Everglades Restoration: Federal Funding and
Implementation Progress
Charles V. Stern
Specialist in Natural Resources Policy
February 26, 2013November 18, 2014
Congressional Research Service
7-5700
www.crs.gov
R42007
CRS Report for Congress
Prepared for Members and Committees of Congressc11173008
Everglades Restoration: Federal Funding and Implementation Progress
.
Summary
The Everglades is a unique network of subtropical wetlands in South Florida that is
approximately half of its historical size, due in part to degradation from federal water projects. In
2000, Congress authorized a 30-year plan, termed the Comprehensive Everglades Restoration
Plan Plan
(CERP), for the restoration of the Everglades ecosystem in southern Florida. When
originally originally
authorized, it was estimated that CERP would cost a total of $8.2 billion and take
approximately approximately
30 years to complete. More recent estimates indicate that the plan would take
approximately 50
years to implement, and would cost $13.5 billionapproximately $1.63 billion more than originally thought,
plus additional adjustments for inflation.
Under CERP, the federal government (through the U.S. Army Corps of Engineers and the
Department of the Interior) is required to fund half of the costs for restoration, with an array of
state, tribal, and local agencies paying the other half. In addition to activities under CERP, a
number of otherongoing federal and state efforts that pre-date CERP (known collectively as “non-CERP”
nonCERP,” or “Foundation” activities) also contribute to Everglades restoration. While non-CERP
efforts are
technically not included in CERP, the two sets of activities are widely viewed as
complementary.
Since passage of CERP in 2000, the federal investment in the Everglades restoration has increased.
As of the
end of FY2012FY2014, the federal government had provided more than $1 billion in funding
for CERP, with the
state providing matching funds for CERP projects, as well as advanced
funding for land
acquisition and construction for expected future CERP projects. Federal funding
for non-CERP
activities (most of which pre-date CERP) has also continued over this time period. These efforts
Together with CERP, all Everglades restoration efforts are estimated to totalhave totaled more than $3 billion as of 20115
billion since FY1993. While estimates of nonfederal (i.e., state)
funding contributions to CERP
and related restoration efforts vary widely depending on what
methodology is employedand assumptions are
used, most agree that, to date, the Statestate of Florida has spent significantly
more on Everglades
restoration than has the federal government.
Progress has been made on a number of Everglades restoration projects, although overall progress
to date has fallen short of initial goals. As of 2012, the late 2014, eight CERP projects were authorized, the
majority of the land necessary for
restoration projects under CERP had been acquired, and
significant progress has been made on
non-CERP activities (including improved water deliveries
to Everglades National Park).
Construction has alsohad been initiated on four CERP projects, and studies
have been completed or
are underway for a number of other CERP projects. Despite this progress, some
projects have
seen setbacks in the form of schedule delays and cost escalations. Additionally, new
or revised
authorizations will be required for many projects to go forward. These impediments may have the
effect of further delaying restoration effortsother major CERP projects, such as the Central
Everglades Planning Project (CEPP), to go forward. These and other impediments have been
noted as possible causes of further delays to restoration benefits in the future.
Reductions to state funding and the lack of new Everglades CERPenactment of four new CERP project authorizations in the Water
Resources Development Act have
Water Resources Reform and Development Act (WRRDA, P.L. 113-121) in June 2014 have
increased attention to the congressional role in Everglades
facilitating Everglades restoration. Debate and
resolution of these issues has implications, both for ecosystem restoration
in the Everglades and
for large-scale restoration initiatives elsewhere.
This report provides information on federal appropriations
funding for Everglades restoration and
provides a brief summary of accomplishments and potential challenges for Everglades
restoration.. It also provides an overview of the federal role in Everglades
restoration, including funding structures and major accomplishments to date.
c11173008
Congressional Research Service
Everglades Restoration: Federal Funding and Implementation Progress
.
Contents
Introduction...................................................................................................................................... 1
Everglades Projects: CERP and Non-CERP .................................................................................... 1
Funding for Everglades Restoration ................................................................................................ 2
DOI Funding.............................................................................................................................. 3
U.S. Army Corps of Engineers Funding .................................................................................... 43
Funding Trends .......................................................................................................................... 4
Comparing Federal and State Funding ...................................................................................... 5
Implementation Progress/Challenges .............................................................................................. 6
Accomplishments Status and Accomplishments .......................................................................................................................... 7
Selected Non-CERP Accomplishments 6
Foundational Elements: Land Acquisition and Pilot Efforts, and
Non-CERP Projects .......................................................................................................... 7
Generation 1 CERP Projects ............................................................................................... 8
Generation 2 CERP Projects ............................................................................................... 8
Generation 3 CERP Projects .......................................................................................... 7..... 8
Challenges ................................................................................................................................. 79
Figures
Figure 1. Estimated Federal Everglades Restoration Expenditures Corps/DOI Funding for Everglades Restoration .............................................................. 5
Tables
Table 1. Corps and DOI Funding for Everglades Restoration, FY2010-FY2015 ............................... 3
Table 2. Corps and DOI Funding for Everglades Restoration, FY2007-FY2015 .......................... 311
Contacts
Author Contact Information............................................................................................................. 8 12
c11173008
Congressional Research Service
Everglades Restoration: Federal Funding and Implementation Progress
.
Introduction
The Florida Everglades is a unique network of subtropical wetlands that is now half its historical
size. The federal government has had a long history of involvement in the Everglades, beginning
in in
the 1940s with the U.S. Army Corps of Engineers (hereinafter referred to as the Corps)
the Corps) constructing flood control projects
that shunted water away from the Everglades to make way for
agricultural and urban
development. Additional factors, including nonfederal development efforts,
have contributed to
the shrinking and altering of the Everglades ecosystem.
In recognition of the unique ecosystem services provided by the Everglades, federal and state
agencies began ecosystem restoration activities in the Everglades in the early 1990s. However, it
was not until 2000 that federal and state restoration activities were coordinated under an
integrated plan. In the Water Resources Development Act of 2000 (WRDA 2000, P.L. 106-541),
Congress approved the Comprehensive Everglades Restoration Plan (CERP) as a framework for
Everglades restoration and authorized an initial round of projects by the Corps and the
Department of the Interior (DOI). According to the process, additional Everglades projects are to
be presented to Congress for authorization as their planning is completed. In WRDA 2007 (P.L.
110-114), four additional projects were authorized. As of early 2013, four other projects had
feasibility studies completed but were not yet authorizedTo date, eight CERP
projects have been authorized, including one in WRDA 2000, three in WRDA 2007 (P.L. 110114), and four in the Water Resources Reform and Development Act of 2014 (WRRDA, P.L. 113121). Pilot projects authorized in WRDA 1999 and WRDA 2000 have also been installed. Other
projects are undergoing study and pending authorization.
To date, some progress has been made on Everglades restoration, but much more time and
funding will be required to complete restoration as currently contemplated. Previously, some have
highlighted the overall slow pace of restoration as an argument for expedited support. Conversely,
others have argued that restoration activities in the Everglades already receive too much funding
relative to other priorities, and that the level of support provided for these activities is not appropriate
appropriate given larger fiscal concerns and the uncertainty of results.
Stakeholders involved with planning other large-scale restoration initiatives look to the
Everglades as a model and a test case. Some believe the types of activities funded and the level of
funding for the Everglades may set a precedent for other restoration initiatives, and should thus be
a priority. Others assert that Everglades restoration efforts have been disproportionately favored
relative to similar projects, and should be subject to the same cost-cutting efforts as other areas of
the budget.
This report summarizes historical and current funding trends for Everglades restoration, with a
focus on
federal funding totals and issues forand recent issues facing Congress. It also summarizes some provides a brief summary of some
of the major
accomplishments in Everglades restoration since the enactment of CERP in 2000, as
well as
ongoing challenges facing the effort.
Everglades Projects: CERP and Non-CERP
Federal CERP funding was first authorized in WRDA 2000, with a focus on increasing storage
and treatment of of
excess water in the rainy season to provide more water during the dry season for
the ecosystem
and for urban and agricultural users. It is estimated that CERP will take more than 50 years and
As of 2010, it was estimated that CERP will
c11173008
Congressional Research Service
1
Everglades Restoration: Federal Funding and Implementation Progress
.
take more than 50 years and $13.5 billion to complete.1 The federal government is expected to pay half of CERP’s costs, and
1
This figure represents the estimated cost to the federal government in October 2009 dollars according to the Corps.
(continued...)
Congressional Research Service
1
Everglades Restoration: Federal Funding and Implementation Progress
pay half of CERP’s costs, and an array of state, tribal, and local agencies (i.e., nonfederal
sponsors) will pay the other half. This
same cost -share is expected to apply to all project
operation and maintenance costs.
WRDA 2000 authorized initial projects (including pilots), established federal/nonfederal cost-sharingcostsharing ratios for
Everglades restoration, and created a process for additional projects to be
authorized as part of the
CERP framework. WRDA 2007 authorized an additional three CERP
projects. Four other projects
have completed the study phase and are ready for construction authorization. The status of these
in 2012 and were authorized for
construction in WRRDA 2014, while two other CERP projects remained in the study phase and
were thus not yet authorized. The status of these projects is discussed later in this report.
Federal Everglades restoration activities not authorized under CERP are often referred to as “nonCERP” or “Foundation” activities. This includes, among other things, work related to the
Modified Water Deliveries Project, which is expected to augment flows to Everglades National
Park. Depending on how broadly this category is defined, it can
encompass a wide variety of
Everglades restoration activities undertaken by multiple agencies.2
Most (but not all) of the
authorities for this funding predate the enactment of CERP in 2000.
However, similar to CERP
funding, most funding for non-CERP Everglades restoration is
provided to the Department of the
Interior and the Corps of Engineers. Thus, the Corps and DOI
are often the focal point for
funding debates surrounding the Everglades.
Funding for Everglades Restoration
Federal funding for Everglades restoration is largely provided through DOI and the Corps, and is
concentrated in two appropriations bills—the Interior and Environment appropriations bill (which
provides funds to DOI) and the Energy and Water Development appropriations bill (which
provides funds to the Corps). Additionally, some funding in other appropriations bills is
sometimes sometimes
noted as contributing to Everglades restoration, but is not formally tracked under the
Administration’s non-CERP totals.3
Appropriations laws and conference reports typically do not specify appropriations levels for
most Everglades restoration activities. Rather, the Administration’s budget request identifies
restoration funding totals for the Administration’s request and for the previous fiscal year.4 Actual
Although the Administration’s budget request identified restoration funding totals for CERP and
non-CERP in the budget request, appropriations laws and conference reports typically do not
specify appropriations levels for Everglades restoration activities (including CERP and nonCERP totals). Rather, actual expenditure information for previous appropriations is tracked by the
South Florida Ecosystem
Restoration Task Force. A summary of funding for both CERP and non-CERPnonCERP activities within
DOI and the Corps for recent years is provided below in Table 1.
(...continued)1
This figure represents the estimated cost to the federal government in October 2009 dollars according to the Corps.
See U.S. Army Corps of Engineers, Comprehensive Everglades Restoration Plan, 2010 Report to Congress. Available
at http://www.sfrestore.org/documents/index.html. Hereinafter 2010 CERP Report to Congress. More recent estimates
are not available.
2
In addition to the Corps and DOI, the South Florida Ecosystem Restoration Task Force also tracks funds that are
provided to the National Oceanic and Atmospheric Administration, the U.S. Environmental Protection Agency, and the
U.S. Department of Agriculture, among others. However, in its annual budget request, the Administration typically
only tracks “nonCERP” funding for the Corps and DOI.
3
As previously noted, some funds not discussed in this report are tracked under the “non-CERP” heading because of
their contribution to Everglades restoration. This includes funds for the Environmental Protection Agency (also in the
Interior and Environment appropriations bill), the National Oceanic and Atmospheric Administration (Commerce,
Justice, and State, the Judiciary, and Related Agencies appropriations bill), and the U.S. Department of Agriculture
(U.S. Department of Agriculture and Related Agencies appropriations). For additional information, see crosscut budget
documents available at http://www.sfrestore.org/documents/index.html.
4
Thus, these totals often lag behind final enacted appropriations.
Congressional Research Service
2
Everglades Restoration: Federal Funding and Implementation Progressnon-CERP” funding for the Corps and DOI. For additional information, see crosscut budget documents
available at http://www.sfrestore.org/documents/index.html.
c11173008
Congressional Research Service
2
Everglades Restoration: Federal Funding and Implementation Progress
.
Table 1. Corps and DOI Funding for Everglades Restoration, FY2010-FY2015
(thousands of dollars)
FY2010
FY2011
FY2012
FY2013
FY2014
FY2015
Proposed
DOI
79,424
70,600
99,884
66,355
70,452
62,000
CERP
8,449
8,401
8,347
7,883
8,376
8,000
70,975
62,199
91,537
58,472
62,076
54,000
Corps
167,364
131,066
142,486
96,008
47,616
66,000
CERP
119,966
79,860
57,886
76,212
38,499
61,000
47,398
41,108
84,600
19,796
9,117
5,000
246,788
201,666
242,370
158,683
118,068
128,000
Non-CERP
Non-CERP
Total
Source: FY2015 Congressional Budget Justifications for the U.S. Department of the Interior and Army Corps of
Engineers and the South Florida Ecosystem Restoration Crosscut Budget Report for FY2014.
Notes: “ARRA” represents funding under the American Recovery and Reinvestment Act (P.L. 110-5).
DOI Funding
Funding within the Interior and Environment bill is allotted to four agencies within DOI: the
National Park Service (NPS), the Fish and Wildlife Service (FWS), the U.S. Geological Survey
(USGS), and the Bureau of Indian Affairs (BIA). Within these agencies, two types of Everglades
funding are often highlighted: funding for CERP and funding for the Modified Waters DeliveryWater Deliveries
Project for Everglades National Park (also known as the “Mod Waters” project). The latter is a
non-CERP project that has received significant attention from Congress, and that aims to improve
water deliveries to Everglades National Park by removing barriers in and around the Tamiami
Trail. DOI’s CERP funding is ). 5 Funding for CERP is
typically provided to NPS and FWS, while funding for the
Modified Waters deliveries project is
provided to NPS.project has been provided to NPS in recent years.3 Although Mod Waters is
technically a non-CERP project, it is widely
considered to be a keystone project for Everglades
restoration, including CERP. DOI funding
totals for FY2006-FY2013with an important nexus to CERP. Recent DOI funding totals are shown in Table 1.
The FY2013FY2015 Administration request for Everglades funding included $71was $62 million in DOI funding
for Everglades restoration, including an increase of approximately $8 million for the Modified
Waters Delivery Project. This funding has been provided directly to the Department of the
Interior since FY2009.6
Table 1. Corps and DOI Funding for Everglades Restoration
(thousands of dollars)
FY2010
FY2011
FY2012
FY2013
Proposed
23,264
79,424
70,600
99,831
70,748
9,459
-
8,449
8,401
8,347
8,392
78,972
119,403
23,264
70,975
62,199
91,484
62,356
[13,330]
[14,299]
[60.000]
[21,052]
[8,400]
[8,000]
[7,987]
[8,000]
Corps
157,553
112,694
115,712
95,412
167,364
131,066
142,486
153,000
CERP
64,000
64,000
83,640
87,896
119,966
79,860
57,886
91,000
Non-CERP
93,553
48,694
32,072
7,516
47,398
41,108
84,600
62,000
[35,000]
[9,840]
-
-
-
-
-
-
232,705
200,049
244,574
118,676
246,788
201,666
242,317
223,748
FY2007
FY2008
FY2009
75,152
87,355
128,862
8,481
8,383
Non-CERP
66,671
[DOI Mod
Waters]
DOI
CERP
[Mod Waters]
Total
ARRA
Source: Congressional Budget Justifications for the U.S. Department of the Interior and Army Corps of
Engineers, FY2006-FY2013.
Notes: DOI funding includes funding for the National Park Service, the Fish and Wildlife Service, the U.S.
Geological Survey, and the Bureau of Indian Affairs. “ARRA” represents funding under the American Recovery
and Reinvestment Act (P.L. 110-5). Mod Waters totals represent a subset of non-CERP funding.
5
The Modified Waters Deliveries Project is an ecosystem restoration project in south Florida designed to improve
water delivery to Everglades National Park.
6
Prior to FY2009, this funding was provided both to the Corps and to DOI.
Congressional Research Service
3
Everglades Restoration: Federal Funding and Implementation Progress for
Everglades restoration, including $8 million for CERP projects and $54 million for non-CERP
projects. No funding was requested for the Mod Waters project, as the initial construction of its
1-mile bridge component was completed.4
U.S. Army Corps of Engineers Funding
Funding for Corps Everglades restoration projects in the Energy and Water Development bill is
listed under project-level headings inwithin the Corps Construction account. Currently, these projects
projects include the Central and Southern Florida Project, Kissimmee River Restoration, project,
and Everglades
and South Florida Restoration. Historically, funding was also included for two other areas,
Florida Keys Water Quality Improvement and the Modified Waters Deliveries Project.7 Corps
3
4
c11173008
Originally, this funding was provided to the Corps.
For additional information on this project, see the “Challenges” section at the end of this report.
Congressional Research Service
3
Everglades Restoration: Federal Funding and Implementation Progress
.
other areas, Florida Keys Water Quality Improvement and Modified Waters Deliveries Project.5
Corps funding is directed toward planning and construction of projects authorized under CERP and
and other authorities. Within Corps totals, funding for CERP is considered a key benchmark for
Everglades restoration commitment and progress.
Table 1 shows funding totals for the Corps in
Corps Everglades restoration in recent fiscal years and the FY2012 President’s request.
Funding Trends
Federal funding totals for restoration activities in the Everglades ecosystem have been collected
since the early 1990s. Overall, since FY1993, the federal investment in Everglades restoration is
estimated to have exceeded $4 billion, and has increased in recent years. From FY1993 through
FY2000, federal appropriations for Everglades restoration activities totaled more than $1.2
billion. More recently, from the enactment of CERP in FY2000 through FY2012, total federal
funding exceeded $3.1 billion, with more than $900 million of that total going to federal CERP
projects. Overall, average federal funding since the enactment of CERP has increased, from
approximately $159 million per year before enactment of CERP to $259 million per year since
CERP was enacted.8 Figure 1 shows all Everglades funding since 2001, breaking these totals
down between CERP and non-CERP funding.
7
As noted above, in recent years Mod Waters funding has been provided solely to DOI. Florida Keys Water Quality
Improvement was completed in FY2009.
8
CRS analysis of departmental data for FY1993-FY2011. These totals are for Corps and DOI restoration work only.
Congressional Research Service
4
Everglades Restoration: Federal Funding and Implementation Progress
Figure 1. Estimated Federal Everglades Restoration Expenditures
400
350
Funding ($- millions)
300
250
Federal Non-CERP
200
Federal CERP
150
100
50
0
Fiscal Year
Source: Estimated Federal CERP Expenditures.
Notes: FY2010 includes additional funding under P.L. 111-5 (ARRA). Some totals for non-CERP funding may not
match with previous totals due to inconsistencies in reported funding levels between the President’s budget and
the crosscut budget documents.
Comparing Federal and State Funding
Exact comparisons between federal and state funding levels are complicated for a number of
reasons. As previously noted, CERP funding is to be cost-shared equally between the federal
government and nonfederal entities in the state of Florida. Many view the status and amount of
federal CERP funding relative to nonfederal funding for this initiative as an important indicator of
the federal government’s commitment to Everglades restoration. While the state has invested
considerable funding in CERP, much of this funding is for land acquisition related to the expected
“footprints” of future CERP projects. Thus, exact comparisons between federal and state funding
levels are complicated.
Nonfederal CERP expenditures are ostensibly tracked in several reports, including a crosscut
budget report prepared annually by the South Florida Ecosystem Restoration Task Force.
However, this funding is not formally “credited” by the Corps toward CERP project cost shares
until a number of requirements have been met. These requirements include completion of a
project implementation report (PIR) and authorization for construction of the project by
Congress, as well as signing of a project partnership agreement, or PPA. Thus, although some
may reference large nonfederal contributions toward CERP, the proportion of these expenditures
that have been formally credited toward CERP is actually much smaller. Indeed, it is possible
Congressional Research Service
5
Everglades Restoration: Federal Funding and Implementation Progress
that, depending on subsequent actions of the Corps and Congress, some of the aforementioned
funds will never be credited under CERP.
The magnitude of the difference between initial state expenditures and the amounts actually
credited under CERP results in a wide range of reported state funding levels for CERP. For
instance, the State of Florida’s annual crosscut budget previously estimated that from 2001 to
2011, it spent approximately $3 billion for its CERP costs. However, actual credited expenditures
from federal and state entities have been noted by the Corps to be roughly even to date, and a
2012 National Research Council (NRC) review noted that all state expenditures for authorized
CERP projects (i.e., projects authorized in WRDA 2000 and WRDA 2007) only exceeded federal
expenditures by $270 million as of 2011.9
In its 2012 report to Congress, the NRC estimated that another $584 million in state expenditures
would be available for crediting if the next “round” of CERP authorized projects is authorized.
The total amount expended by the State of Florida that may be credited to all future CERP
projects ranges widely, depending on which assumptions are used.10 Future legislative actions,
including project authorizations, would be an important factor in determining the exact amount
eligible for cost shares. (For more information, see “Challenges”, below.)
Implementation Progress/Challenges
Congress has mandated several major reports that include detailed evaluations of Everglades
restoration. NRC reviews of Everglades restoration are published biennially and a report was
most recently published in 2012; CERP reports to Congress are published every five years and a
report was most recently completed in 2010.11 Both reports outline accomplishments and
challenges related to CERP and non-CERP projects.
Since passage of CERP in 2000, progress has been made on Everglades restoration for both
CERP and non-CERP projects, including construction of pilot projects and initiation of several
other construction projects. As discussed below, some of the non-CERP “Foundation” projects are
nearing completion. Additionally, in recent years many have noted an increase in momentum for
Everglades restoration as several projects moved from the planning to construction phase. Most
of these projects have seen increases in federal appropriations. In addition to progress on
construction, baseline information and processes have also been established, the scientific
understanding of many of the uncertainties associated with Everglades restoration has improved,
and a programmatic structure is in place to facilitate future projects. Selected CERP and nonCERP accomplishments as of 2013 are noted below.
9
Committee on Independent Scientific Review of Everglades Restoration, National Research Council, Progress
Toward Restoring the Everglades: The Fourth Biennial, Washington, DC, 2012, http://www.nap.edu/catalog.php?
record_id=13422. Hereafter Fourth Biennial Review.
10
A number of potential CERP projects benefited from land purchases by the State of Florida but have yet to receive a
Chief’s Report or be authorized by Congress. Correspondence with Steve Kopecky, Corps, May 11, 2011.
11
See footnotes 1 and 9.
Congressional Research Service
6
Everglades Restoration: Federal Funding and Implementation Progress
Accomplishments12
•
Purchase of more than 60% of total land required under CERP.
•
Design and installation of four CERP pilot projects authorized in WRDA 2000.
•
Initiation of construction on the Picayune Strand restoration project (authorized
in WRDA 2007), which is expected to restore 55,000 acres of wetlands. The first
phase of this project is expected to be complete in 2013.
•
Initiation of construction on the Site 1 Impoundment Project (authorized in
WRDA 2007), which is expected to provide for 13,280 acre-feet of water storage
and prevent saltwater intrusion. The first phase of this project is expected to be
completed in 2013.
•
Initiation of construction for the C-44 Reservoir and Stormwater Treatment Area
(STA) component of the Indian River Lagoon-South Project (authorized in
WRDA 2007), which is expected to store approximately 50,000 acre-feet of
stormwater. This project is expected to be completed in 2018.
•
Completion of PIRs by the Corps for four projects: the C-111 Spreader Canal;
Biscayne Bay Coastal Wetlands; C-43 West Basin Storage Reservoir, and
Broward County water preserve areas.
•
Initiation of expedited construction by the State of Florida on four projects:
Loxahatchee River Watershed, Lakeside Ranch STA, C-111 Spreader Canal, and
Biscayne Bay Coastal Wetlands.
Selected Non-CERP Accomplishments
•
Initiation of construction of the 1-mile bridge component of the Mod Waters
Project, which is expected to improve water deliveries to Everglades National
Park. This project is expected to be completed in 2013.
•
Completion of three of four phases of the Kissimmee River Restoration Project,
which is expected to reconnect the river with its historical flood plain and better
restore more natural flows.
Challenges
Outside reviewers, including the NRC, have noted the relatively slow pace of Everglades
restoration compared to the ambitious timetables laid out in original program documents.13 These
observers have acknowledged that while there has been some progress in the Everglades,
implementation of actual restoration projects receiving federal and state funds has been
considerably slower than expected. At the same time, estimated costs for Everglades restoration
have gone up significantly. While CERP was originally estimated to cost a total of $8.2 billion
(2000 dollars) in funding over 30 years, more recent estimates indicate that CERP will cost $13.5
12
Accomplishments noted are as of 2013.
See for example, Committee on Independent Scientific Review of Everglades Restoration, National Research
Council, Progress Toward Restoring the Everglades: The Third Biennial Review, Washington, DC, 2010, pp 64-68,
https://download.nap.edu/catalog.php?record_id=12988. Hereinafter referred to as the Third Biennial Review.
13
Congressional Research Service
7
Everglades Restoration: Federal Funding and Implementation Progress
billion (2009 dollars), and have extended the expected timeline for implementation to 50 years.14
Stated reasons for these cost and schedule changes include inflation, changes to project design,
and funding streams that were less than originally expected.
As of 2013, no major CERP project receiving federal funds had been completed, and the majority
of projects described in earlier plans had yet to be initiated. Many of the projects envisioned in
earlier program documents are either unauthorized, or else require amendments to their original
authorization to proceed further.15 As of 2013, 10 of the 45 project implementation reports
expected under CERP had been finalized or completed in draft form. Of these 10 projects, only
four have been authorized by Congress and have had construction initiated. In several cases,
CERP projects have yet to be authorized by Congress, but nonfederal construction work has
begun.
Another challenge going forward for Everglades restoration may be the status of potential new
project authorizations under the Water Resources Development Act (WRDA). Originally, CERP
envisioned regular enactment of WRDAs and associated inclusion of CERP projects as they were
studied and recommended to Congress. However, since 2000, one WRDA has been enacted
(2007). Absent new authorizations, there is no clear way for federal work on Everglades
restoration to proceed, and construction may slow considerably from its current pace as existing
projects wind down and the Corps is not able to match prior state expenditures for unauthorized
projects. Such a scenario would likely delay CERP further relative to the current expected
timeline.
Other challenges to Everglades restoration have been noted by outside reviewers and others.
These challenges include ongoing issues associated with water quality in the Everglades and
south Florida, the adequacy of some restoration efforts in recreating historical hydrologic
conditions, and ongoing degradation of species and ecosystems in south Florida, which has in
some cases accelerated in recent years.
Author Contact Information
Charles V. Stern
Specialist in Natural Resources Policy
cstern@crs.loc.gov, 7-7786
14
According to the Corps, the increased cost estimates since 2000 are attributed to (1) $3.63 billion in inflation
adjustments; and (2) $1.63 billion in price /scope changes.
15
While WRDA 2000 conditionally authorized 10 projects, these projects will reportedly need to have their
authorizations amended due to substantive changes in project scope.
Congressional Research Service
8
FY2015 President’s request. For FY2014, the enacted amount for Corps Everglades restoration
work for FY2014 was $47.6 million, and the FY2015 requested level for the Corps was $66
million. This funding level was below previous years due to a number of factors, including the
availability of unobligated funds from prior years, the drawdown of needed funding for
authorized, ongoing projects, and the lack of new and modified project authorizations prior to the
enactment of WRRDA in June 2014.
Funding Trends
The federal government has funded restoration of the Everglades in some form since at least the
early 1990s. Overall, from FY1993 to FY2014, the total federal investment in Everglades
restoration (including agencies other than the Corps and DOI) is estimated to have exceeded $5
billion. From FY1993 through FY2000, prior to the enactment of CERP, federal appropriations
for Everglades restoration activities totaled more than $1.2 billion. More recently, since the
enactment of CERP (i.e., since FY2001), total federal funding from all agencies is estimated to
have exceeded $4 billion, with Corps and DOI funding for Everglades restoration accounting for
more than $3.15 billion of that amount.6
As previously noted, Everglades funding for the Corps and DOI typically receives the most
attention from Congress. Figure 1 shows Everglades funding since 2001 for those two agencies,
including CERP and non-CERP totals. As shown in that figure, while overall funding for
Everglades restoration by these agencies has remained somewhat constant since the enactment of
CERP, the distribution between CERP and non-CERP funding has changed over time. CERP
projects gradually increased from FY2001 to FY2010 (including ARRA). Over the same period,
funding for non-CERP projects (such as Mod Waters) decreased from their earlier levels. Finally,
over the last two years, overall spending in both categories has decreased. Total funding for
CERP projects from FY2001 to FY2014 is estimated to have exceeded $1 billion.
Fluctuations in Everglades federal funding can be explained by a number of factors. For instance,
after authorization in FY2007, federal funding for “Generation 1” CERP projects increased as
project construction commenced, and began declining in FY2012. The subsequent decrease in
funding for CERP beginning at that time was a combined result of “Generation 1” CERP Projects
(i.e., projects authorized in WRDA 2007) winding down certain construction activities while
“Generation 2” projects (i.e., projects with completed project implementation reports that were
proposed and eventually authorized in WRRDA 2014) were awaiting authorizing legislation
before they could be funded. For non-CERP projects, more recent decreases in funding can in part
be attributed to the completion of the initial phases of construction on the Mod Waters project.
5
As noted above, in recent years Mod Waters funding has been provided solely to DOI. Florida Keys Water Quality
Improvement was completed in FY2009.
6
CRS analysis of departmental data for FY1993-FY2014.
c11173008
Congressional Research Service
4
Everglades Restoration: Federal Funding and Implementation Progress
.
Figure 1. Corps/DOI Funding for Everglades Restoration
400
350
Funding ($- millions)
300
250
Federal Non-CERP
200
Federal CERP
150
100
50
0
Fiscal Year
Source: CRS estimates based on Corps and DOI budget documents from FY2001-FY2015.
Notes: Does not include agency funding for non-CERP activities outside of the Corps and DOI. FY2010 includes
additional funding under P.L. 111-5 (ARRA).
Comparing Federal and State Funding
Many view the status and amount of federal CERP funding relative to nonfederal funding for this
initiative as an important indicator of the federal government’s commitment to Everglades
restoration, and there is widespread agreement that the state has invested more funding in CERP
than has the federal government. However, comparisons between federal and state funding levels
for Everglades restoration are complicated for a number of reasons.
As previously noted, CERP funding is to be cost-shared equally between the federal government
and nonfederal entities in Florida. Notably, much of the nonfederal funding for Everglades
restoration efforts has been for land acquisition related to the expected “footprint” of future CERP
projects, rather than construction funding for federal projects that have been authorized by
Congress. That is, state CERP funding has anticipated or accelerated multiple Everglades
restoration projects that have yet to be federally approved.7
7
Funding is not formally “credited” by the Corps toward CERP project cost-shares until a number of requirements
have been met. These requirements include completion of a project implementation report (PIR) and authorization for
construction of the project by Congress, as well as signing of a project partnership agreement, or PPA.
c11173008
Congressional Research Service
5
Everglades Restoration: Federal Funding and Implementation Progress
.
Although some reference large nonfederal contributions toward CERP, the proportion of these
expenditures that have been formally credited toward CERP is actually much smaller. Indeed, it is
possible that, depending on subsequent actions of the Corps and Congress, some of the
aforementioned nonfederal funds will never be credited to federal CERP projects. Thus, the size,
scope, and priority of new federal CERP projects and their relation to previous state expenditures
receives significant attention, and may in some cases be a matter of disagreement.
Differences between initial reported state expenditures and the amounts actually credited under
CERP result in a wide range of state funding levels being attributed to Everglades restoration. For
instance, in its annual crosscut budget the South Florida Ecosystem Restoration Task Force
previously estimated that from 2001 to 2011, it spent approximately $3 billion on CERP, or
considerably more than the federal government spent over that time. However, actual credited
state and federal expenditures over the same period were comparable.
In recent years, the state of Florida’s funding on CERP has decreased due to a number of factors,
including a decline in state tax revenues and a focus on other aspects of Everglades restoration,
such as funding for projects under its Restoration Strategies Regional Water Quality Plan, which
is intended to address EPA narrative and numeric nutrient criteria in the Everglades.8 It is unclear
whether state funding for CERP will return to previous levels in the future. Previous estimates
indicated that approximately $584 million in previous state expenditures would be “available” for
crediting when the “Generation 2” projects were authorized by Congress (as occurred in June
2014). Assuming no major influx of new funding by the state of Florida in the near future, the
status of federal authorizing legislation for subsequent Everglades restoration projects may
receive added attention.
Implementation Progress/Challenges
Congress has mandated several reports that regularly evaluate Everglades restoration. Pursuant to
congressional direction, the National Research Council (NRC) publishes reviews of Everglades
restoration biennially, with the most recent report published in 2014.9 Separately, a report to
Congress focusing specifically on CERP is published every five years, with the most recent report
completed in 2010.10 Both reports outline accomplishments and challenges related to both CERP
and non-CERP projects.
Status and Accomplishments
Since passage of CERP in 2000, progress has been made on Everglades restoration for both
CERP and non-CERP projects. Significant actions have included the construction of pilot
projects, the completion of studies, and the initiation of several construction projects (including
completion of the initial phases of some projects). As discussed below, some of the non-CERP
“foundation” projects are nearing completion, and some Generation 1 CERP projects are expected
8
These efforts, which began in 2012, are being undertaken in response to a court-ordered Amended Determination by
the EPA.
9
Committee on Independent Scientific Review of Everglades Restoration, National Research Council, Progress
Toward Restoring the Everglades: The Fifth Biennial Review, Washington, DC, 2014.
10
2010 CERP Report to Congress.
c11173008
Congressional Research Service
6
Everglades Restoration: Federal Funding and Implementation Progress
.
to be completed in the near future. In addition to progress on construction, baseline information
and processes have also been established, and the scientific understanding of many of the issues
associated with Everglades restoration has improved. Tangible ecosystem benefits resulting from
progress to date are for the most part yet to be realized or noted. In many cases, these benefits are
expected to lag several years behind project construction and restoration of hydrologic conditions,
and are expected to require extensive monitoring and adaptive management to confirm and refine.
Selected CERP and non-CERP accomplishments as of 2014 are discussed below.
Foundational Elements: Land Acquisition and Pilot Efforts, and
Non-CERP Projects
As noted above, as of 2014, Everglades restoration had achieved several milestones. Major
achievements included accomplishment of several foundational steps required for the eventual
completion of larger restoration projects. This includes the purchase by nonfederal project
sponsors of most of the land expected to be required for CERP projects (a necessary first step in
project construction by the Corps). As discussed previously, many of these projects are expected
to be credited toward the nonfederal cost-share for individual projects.
Early pilot projects that will influence the eventual prioritization and construction of larger CERP
projects are also largely completed. Specifically, design and installation of six pilot projects
authorized in WRDA 1999 and WRDA 2000 have taken place in recent years. Examples include
Aquifer Storage and Recovery (ASR) Pilot projects, authorized in WRDA 1999 and WRDA 2000,
which assessed the feasibility of this technology at specific sites as they applied to Everglades
restoration. Based on the findings from these projects (published in 2013), ASR is expected to be
among the options considered for future water storage projects in South Florida. Other projects
are achieving benefits already and may be added to in future years. A pilot groundwater seepage
barrier to the southeast of the Mod Waters project was completed and has been found to be
successful in blocking subsurface migration of groundwater. This pilot project may be expanded
in the future.
As previously noted, non-CERP projects are a key part of Everglades restoration that pre-date
CERP and are therefore in several cases more established than CERP projects. Some non-CERP
accomplishments as of 2013 included the completion of the Florida Keys Water Quality
Improvement Project, as well as the NPS-constructed 1-mile bridge component of the Modified
Water Deliveries project, which may be expanded in the future.11 Another major restoration
project that pre-dated CERP, the Kissimmee River Project (authorized in 1992 and initiated in
1999), was nearing completion. Some outside observers have noted that this project has already
resulted in significant benefits that demonstrate the potential for planned CERP projects.12
Another project, the Seminole Big Cypress Reservation Water Conservation Plan Critical Project,
was expected to be complete by 2015.
11
Another planning project, known as the Next Steps project, is being directed by the National Park Service and may
eventually lead to the bridging of up to an additional 5.5 miles of the roadway.
12
Committee on Independent Scientific Review of Everglades Restoration, National Research Council, Progress
Toward Restoring the Everglades, the Fourth Biennial Review, Washington, DC, 2014, p 102. Hereinafter referred to
as the Fourth Biennial Review.
c11173008
Congressional Research Service
7
Everglades Restoration: Federal Funding and Implementation Progress
.
Generation 1 CERP Projects
Among the “Generation 1” CERP projects authorized in WRDA 2007 (Picayune Strand
Restoration, Site 1 Impoundment, Indian River Lagoon-South or IRL-South, and the
programmatic authority for Melaleuca Eradication that was authorized by Congress in WRDA
2000), as of 2014 planning/design was complete and construction was underway to some extent
for all four projects. However, none of these projects is fully operational, and two of them
(Picayune Strand and Site 1 Impoundment) may require additional congressional authorization in
the near future.
Generation 2 CERP Projects
As previously noted, the Water Resources Reform and Development Act of 2014 (WRRDA 2014,
P.L. 113-121) authorized four additional “Generation 2” CERP projects with completed project
implementation reports: the C-111 Spreader Canal, Biscayne Bay Coastal Wetlands, C-43 West
Basin Storage Reservoir, and Broward County Water Preserve Areas (WPAs). Congressional
authorization of WRRDA will allow construction to be initiated on two new projects (C-43
Reservoir and Broward County WPAs) and will allow federal funding to flow toward two other
projects (the C-111 Spreader Canal and Biscayne Bay Coastal Wetlands) whose construction was
previously initiated by the state. At the time of their authorization, these four projects were
expected to have a total cost of approximately $1.9 billion.
Generation 3 CERP Projects
Two other CERP projects, the Central Everglades Planning Project (CEPP) and the Loxahatchee
River Watershed Project, were still in the study process when WRRDA 2014 was enacted and
were thus not authorized for federal construction. These “Generation 3” projects are currently
expected to be among the next CERP projects authorized for construction. CEPP in particular is
widely considered to be a high-priority project for Everglades restoration, and its status has
received considerable attention (see box below).
The exact path to authorization for Generation 3 projects remains uncertain. Notably, pursuant to
a new process established in WRRDA 2014, these projects could potentially be approved outside
of the traditional authorization process for water resources projects.13 However, if this process is
not available in the future, federal work on these projects could not take place until they receive
full federal authorization.
13
For more information, see CRS Report R43298, Water Resources Reform and Development Act of 2014:
Comparison of Select Provisions, by Nicole T. Carter et al.
c11173008
Congressional Research Service
8
Everglades Restoration: Federal Funding and Implementation Progress
.
Central Everglades Planning Project
The Central Everglades Planning Project (or CEPP) is an Everglades restoration study under the CERP framework
that was initiated in 2011 by the Corps and the Department of the Interior, with the state of Florida. It is expected to
recommend a suite of restoration projects in the central Everglades that would be a part of the broader CERP
program aiming to address problems associated with the timing and distribution of freshwater flows in the central
Everglades.
CEPP was initiated due to a perceived need to prioritize restoration projects in the central portion of the Everglades
ecosystem and enhance the prospects for Everglades restoration overall. To date, most restoration projects in the
Everglades have focused on the periphery of the historic Everglades (rather than flows to the Central Everglades).
CEPP would incorporate multiple CERP projects that were envisioned in the original 1999 plan, at a preliminary
estimated cost of approximately $1.9 billion.
Due to the interest in expediting CEPP’s authorization and construction, the Corps included this study among those
investigations being undertaken as part of its National Planning Pilot Program. The aim of this effort is to complete
feasibility studies in less time than is traditional for Corps investigations. Among other goals, studies initiated under
the pilot are expected to adhere to a “3x3x3” rule, which means that feasibility studies will be completed with no
more than $3 million in federal costs, in three years or less, and with the involvement of the three levels of Corps
review (districts, divisions, and Headquarters). Initially, final approval of CEPP was envisioned for December 2013.
However, the Chief’s Report was delayed and the project was not authorized with the other Generation 2 Everglades
projects in WRRDA 2014. Thus, the status of CEPP moving forward will depend on how (and when) Congress
approaches water resources project authorizations.
Challenges
Despite the achievement of some milestones, outside reviewers have frequently noted the
relatively slow overall pace of Everglades restoration compared to the ambitious timetables laid
out in original program documents in 1999 and, more recently, in 2011. These observers have
pointed out that while there has been some progress toward restoring the Everglades, project
implementation has been considerably slower than expected due to a number of factors, such as
inadequate appropriations and delayed project authorization.14 At the same time, estimated costs
for Everglades restoration have gone up. While CERP was originally estimated to cost a total of
$8.2 billion, the 2010 update to these estimates indicated that it would take 50 years to complete,
at a cost of $13.5 billion. According to the report, approximately $1.63 billion of the increased
costs since the initial estimates could be attributed to price/scope changes (i.e., costs other than
inflation).15
Individually, some CERP projects have been implemented more slowly than anticipated. As of
2014, no major CERP project receiving federal funds had been completed, and many of the
projects and schedules envisioned in earlier program documents have proven to be inaccurate.16
Only a fraction of the project implementation reports originally envisioned under CERP have
been finalized or completed in draft form. Further, of these, only eight projects have been
authorized by Congress and four have had federal construction initiated.17
14
The lack of project authorizations in a WRDA appears to have occurred mostly during the 2012-2014 time period,
since PIRs for three projects were completed and awaiting congressional authorization beginning in 2012.
15
According to the Corps, the increased cost estimates since 2000 are attributed to (1) $3.63 billion in inflation
adjustments; and (2) $1.63 billion in price /scope changes.
16
While WRDA 2000 conditionally authorized 10 projects, many of these projects will need to have their
authorizations amended due to substantive changes in project scope.
17
In several other cases, CERP projects have yet to be authorized by Congress, but nonfederal construction work has
begun.
c11173008
Congressional Research Service
9
Everglades Restoration: Federal Funding and Implementation Progress
.
Reviewers have noted that funding has been a challenge for authorized Everglades restoration
projects, and this challenge could grow in future years. Recently authorized Generation 2 CERP
projects will presumably have to compete for funds with ongoing Generation 1 and non-CERP
projects, as well as with other water resource projects and appropriations priorities. Even if
funding were to stay at current levels, project implementation could slow if funding is spread out
among multiple projects. Attaining new state funding where required for project cost-shares may
also be challenging in light of decreased funding and the shift toward other restoration priorities
by the state of Florida in recent years. If these trends continue, the pace of implementation for
some projects could slow further.
Another challenge for Everglades restoration may be the status of potential new project
authorizations under Water Resources Development Acts (WRDAs). CERP originally anticipated
regular enactment of WRDAs and related Everglades restoration projects as they were studied
and recommended to Congress. However, since 2000, only two WRDAs have been enacted, in
2007 and 2014. With enactment of WRRDA 2014, attention has largely shifted to the status of a
large CERP project in the Central Everglades, the Central Everglades Planning Project, whose
current path to authorization is unclear. Absent new authorizations, federal work on Everglades
restoration could slow considerably if ongoing projects wind down and the Corps is not
authorized to expend funds and match prior state expenditures for some projects (as was the case
in recent years). Such a scenario would likely delay CERP further relative to the current expected
timeline.
Once construction projects are complete, ecological benefits associated with restoration are not
expected immediately, and they will be dependent on a number of factors. While preliminary
benefits in the early stages of project operations are possible, it will likely take time for projects
to individually and collectively refine their operations and demonstrate maximum positive effects
on species and the environment. In many cases, benefits may depend on the successful
completion of one or more other projects, further highlighting the interconnected nature of the
overall restoration effort. Thus, completion of project construction represents only one hurdle for
Everglades restoration, with refined operations and monitoring of performance representing
challenges in their own right.
Other challenges to Everglades restoration have been widely noted. These challenges include
ongoing issues associated with water quality in the Everglades and south Florida that are being
addressed by the state, the adequacy of some restoration efforts in recreating historical hydrologic
conditions, and ongoing degradation of species and ecosystems in south Florida, which has in
some cases accelerated in recent years. The interaction of one or more of these factors may
impact the operational status of federal restoration projects. For instance, although construction
has been completed on the 1-mile bridge portion of the Mod Waters project, a number of other
hurdles related to water quality, land easements, and operational planning must be overcome
before the project can actually be operated to achieve the flows and benefits that were originally
expected. Similar variables and complications could impact the implementation of other
Everglades restoration projects in the future.
c11173008
Congressional Research Service
10
.
Table 2. Corps and DOI Funding for Everglades Restoration, FY2007-FY2015
(thousands of dollars)
FY2007
FY2008
FY2009
ARRA
FY2010
FY2011
FY2012
FY2013
FY2014
FY2015
Proposed
DOI
75,152
87,355
128,862
23,264
79,424
70,600
99,884
66,355
70,452
62,000
CERP
8,481
8,383
9,459
—
8,449
8,401
8,347
7,883
8,376
8,000
66,671
78,972
119,403
23,264
70,975
62,199
91,537
58,472
62,076
54,000
157,553
112,694
115,712
95,412
167,364
131,066
142,486
96,008
47,616
66,000
CERP
64,000
64,000
83,640
87,896
119,966
79,860
57,886
76,212
38,499
61,000
Non-CERP
93,553
48,694
32,072
7,516
47,398
41,108
84,600
19,796
9,117
5,000
232,705
200,049
244,574
118,676
246,788
201,666
242,370
158,683
118,068
128,000
Non-CERP
Corps
Total
Source: CRS estimates based on Congressional Budget Justifications for the U.S. Department of the Interior and Army Corps of Engineers, FY2007-FY2015.
Notes: DOI funding includes funding for the National Park Service, the Fish and Wildlife Service, the U.S. Geological Survey, and the Bureau of Indian Affairs. “ARRA”
represents funding under the American Recovery and Reinvestment Act (P.L. 110-5). For FY2013, no funding breakdown for CERP and Non-CERP funding for the Corps
was available.
c11173008
CRS-11
Everglades Restoration: Federal Funding and Implementation Progress
.
Author Contact Information
Charles V. Stern
Specialist in Natural Resources Policy
cstern@crs.loc.gov, 7-7786
c11173008
Congressional Research Service
12