Navy Columbia (SSBN-826) Class Ballistic Missile Submarine Program: Background and Issues for Congress

Changes from June 3, 2011 to April 5, 2012

This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.


. Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program: Background and Issues for Congress Ronald O'Rourke Specialist in Naval Affairs June 3, 2011April 5, 2012 Congressional Research Service 7-5700 www.crs.gov R41129 CRS Report for Congress Prepared for Members and Committees of Congress . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Summary The Navy’s ballistic missile submarines (SSBNs) form one leg of the U.S. strategic nuclear deterrent force, or “triad,” which also includes land-based intercontinental ballistic missiles (ICBMs) and land-based long-range bombers. The Navy currently operates 14 Ohio (SSBN-726) class SSBNs, also known as Trident SSBNs, the first of which is projected to reach the end of its service life in 2027. The Navy is conducting development and design work on a planned class of 12 next-generation ballistic missile submarines, or SSBN(X)s, which the service wants to procure as replacements for the 14 Ohio-class boats. The SSBN(X) program is also known as the Ohio replacement program (ORP). The Navy’s proposed FY2012 budget requests $1,067 million in research and development funding for the program. Navy plans call for procuring the first SSBN(X) in FY2019, with advance procurement funding for the boat beginning in FY2015. The Navy estimates the average procurement cost of boats 2 through 12 in the program at $5.6 billion each in FY2010 dollars, and is now working to reduce that figure to a target of $4.9 billion each in FY2010 dollars. Even with this cost-reduction effort, some observers are concerned that procuring 12 SSBN(X)s during the 15-year period FY2019-FY2033, as called for in Navy plans, could lead to reductions in procurement rates for other types of Navy ships during those years. Potential oversight issues for Congress for the SSBN(X) program include the following: proposed FY2013 budget requests $564.9 million for continued research and development work on the Ohio replacement program (ORP), a program to design and build a new class of 12 ballistic missile submarines (SSBNs) to replace the Navy’s current force of 14 Ohioclass SSBNs. The Ohio replacement program is also known as the SSBN(X) program. Under the Navy’s FY2012 budget, the first Ohio replacement boat was scheduled to be procured in FY2019, and Ohio replacement boats were to enter service on a schedule that would maintain the Navy’s SSBN force at 12 boats. The Navy’s proposed FY2013 budget defers the procurement of the first Ohio replacement boat by two years, to FY2021. As a result of this deferment, the Navy’s SSBN force will drop to 10 boats during most of the 2030s. The Navy estimates the average procurement cost of boats 2 through 12 in the Ohio replacement program at $5.6 billion each in FY2010 dollars, and is working to reduce that figure to a target of $4.9 billion each in FY2010 dollars. Even with this cost-reduction effort, observers are concerned about the impact the Ohio replacement program will have on the Navy’s ability to procure other types of ships at desired rates in the 2020s and early 2030s. Potential oversight issues for Congress for the Ohio replacement program include the following: • the reasons for deferring the start of SSBN(X) procurement by two years, to FY2021, the cost and operational impact of this decision, and whether it would be feasible and cost effective to restore the start of procurement to FY2019, as planned under the FY2012 budget; • the plan to design the SSBN(X) with 16 SLBM tubes rather than 20; • the plan to procure 12 SSBN(X)s rather than 13 or 14; • the likelihood that the Navy will be able to reduce the average procurement cost of boats 2-12 in the program to the target figure of $4.9 billion each in FY2010 dollars; • the accuracy of the Navy’s estimate of the procurement cost of each SSBN(X); • the prospective affordability of the SSBN(X)Ohio replacement program and its potential impact on other Navy shipbuilding programs; • where in the budget to fund the program’s detailed design/nonrecurring engineering (DD/NRE costs); and • the question of which shipyard or shipyards will build SSBN(X)s. Options for reducing the cost of the SSBN(X) program or its potential impact on other Navy shipbuilding programs (other than the Navy’s current cost-reduction effort) include procuring fewer than 12 SSBN(X)s; reducing the number of submarine-launched ballistic missiles (SLBMs) to be carried by each SSBN(X) from 16 to a lower number, such as 12; stretching out the schedule for procuring SSBN(X)s and making greater use of split funding (i.e., two-year incremental funding) in procuring them; and funding the procurement of SSBN(X)s in a part of the Department of Defense (DOD) budget that is outside the Navy’s budget. This report focuses on the SSBN(X) funding available for other Navy shipbuilding programs; and • the question of which shipyard or shipyards will build SSBN(X)s. This report focuses on the Ohio replacement program as a Navy shipbuilding program. CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf, discusses the SSBN(X) as an element of future U.S. strategic nuclear forces in the context of strategic nuclear arms control agreements. Congressional Research Service . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Contents Introduction .................................................................................................................................1 Background ..... 1 Background...................................................................................................................................... 1 U.S. Navy SSBNs in General .................................................................................................... 1 Mission of SSBNs ............................................................................................................... 1 Current Ohio-Class SSBNs ................................................................................................. 2 Summary of U.S. SSBN Designs ........................................................................................ 4 U.S.-UK Cooperation on SLBMs ....................................................................................... 6 Ohio Replacement Program6 SSBN(X) Program ................................................................................................................ 7 Program Origin and Early Milestones ....................................................................................... 7 Procurement and Replacement Schedule ............................................................................ 9 SSBN(X) Design Features ................................................................................................ 10 Program Acquisition Cost ............................................................................................. 11.... 12 Common Missile Compartment (CMC)......................................................................... 12 Program Funding ... 13 Program Funding.............................................................................................................. 13. 14 Issues for Congress ................................................................................................................... 14 A Design with 16 vs. 20 SLBM Tubes......... 14 Two-Year Deferral in Start of Procurement............................................................................. 15 Plan to Procure 12 Boats Rather Than 13 or 14.............A Design with 16 vs. 20 SLBM Tubes ....................................................... 19 Likelihood That Navy Will Reach $4.9 Billion Target Cost.................................................. 19 Accuracy of Navy’s Estimated Unit Procurement Cost 17 Plan to Procure 12 Boats Rather Than 13 or 14 ........................................................ 20 Program Affordability and Impact on Other Navy Shipbuilding Programs ........................... 21 Reducing the Planned Number of SSBN(X)s........................... 21 Likelihood That Navy Will Reach $4.9 Billion Target Cost.................................................... 22 Altering the Schedule for Procuring SSBN(X)s to Make More Use of Incremental Funding ......Accuracy of Navy’s Estimated Unit Procurement Cost ............................................................................................................... 23 Procuring SSBN(X)s Outside Navy’s Shipbuilding Budget ........................................... 24 Detailed Design/Nonrecurring Engineering (DD/NRE) Costs .............................................. 26 Construction Shipyard(s) 23 Program Affordability and Impact on Other Navy Shipbuilding Programs ............................ 25 Reducing the Planned Number of SSBN(X)s ................................................................................. 26 Altering Procurement Schedule to Make More Use of Incremental Funding.................... 27 Building 27 Procuring SSBN(X)s ............Outside Navy’s Shipbuilding Budget ............................................. 29 Construction Shipyard(s)............................................. 27 Building CMCs for the UK’s SSBNs............................................................................. 30 Legislative Activity for FY2012 ................................................................................................ 30 FY2012 Funding Request.................................................................................................... 30 FY2012 Defense Authorization Bill (H.R. 1540) ................................................................. 30 House ............................................................................... 31 Legislative Activity for FY2013 .................................................................................................... 33 FY2013 Funding Request........................................................................................................ 3033 Figures Figure 1. Ohio (SSBN-726) Class SSBN ........................................................................................ 4 Tables Table 1. U.S. SSBN Classes ............................................................................................................ 5 Table 2. Navy Schedule for Procuring SSBN(X)s and Replacing Ohio-Class SSBNs ................. 10 Table 3. SSBN(X) Program Funding ........Ohio Replacement Program Funding................................................................................. 14 Congressional Research Service . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program 14 Table 4. Navy SSBN(X) Procurement Schedule and a Notional Alternative Schedule ................. 2428 Table 5. Construction Shipyards of U.S. SSBNs ........................................................................... 32 Congressional Research Service Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Contacts Author Contact Information..... 28 Table A-1. Congressional Action on FY2011 Funding Request .................................................. 35 Appendixes Appendix. Legislative Activity for FY2011 ............................................................................... 35 Contacts Author Contact Information ...................................................................................................... 3934 Congressional Research Service . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Introduction This report provides background information and potential oversight issues for Congress on the Navy’s SSBN(X) programOhio replacement program (ORP), a program to develop and procure 12 new ballistic design and build a new class of 12 ballistic missile submarines (SSBNs) as replacements for (SSBNs) to replace the Navy’s current force of 14 Ohio-class SSBNs. The SSBN(X) Ohio replacement program is also known as the Ohio replacement program (ORP)SSBN(X) program. The Navy’s proposed FY2012 budget requests $1,067 million in research and development funding for the SSBN(X) program. FY2013 budget requests $564.9 million for continued research and development work on the Ohio replacement program. Decisions that Congress makes on the SSBN(X) program Ohio replacement program could substantially affect U.S. military capabilities and funding requirements, and the U.S. shipbuilding industrial base. This report focuses on the SSBN(X)Ohio replacement program as a Navy shipbuilding program. Another CRS report discusses the SSBN(X) as an element of future U.S. strategic nuclear forces in the context of strategic nuclear arms control agreements.1 Background U.S. Navy SSBNs in General Mission of SSBNs The U.S. Navy operates three kinds of submarines—nuclear-powered attack submarines (SSNs), nuclear-powered cruise missile submarines (SSGNs), and nuclear-powered ballistic missile submarines (SSBNs).2 The SSNs and SSGNs are multi-mission ships that perform a variety of peacetime and wartime missions.3 They do not carry nuclear weapons.4 1 CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf. In the designations SSN, SSGN, SSBN, and SSBN(X), the SS stands for submarine, N stands for nuclear-powered (meaning the ship is powered by a nuclear reactor), G stands for guided missile (such as a cruise missile), B stands for ballistic missile, and (X) means the design of the ship has not yet been determined. As shown by the “Ns” in SSN, SSGN, and SSBN, all U.S. Navy submarines are nuclear-powered. Other navies operate non-nuclear powered submarines, which are powered by energy sources such as diesel engines. A submarine’s use of nuclear or non-nuclear power as its energy source is not an indication of whether it is armed with nuclear weapons—a nuclear-powered submarine can lack nuclear weapons, and a non-nuclear-powered submarine can be armed with nuclear weapons. 3 These missions include covert intelligence, surveillance, and reconnaissance (ISR), much of it done for national-level (as opposed to purely Navy) purposes; covert insertion and recovery of special operations forces (SOF); covert strikes against land targets with the Tomahawk cruise missiles; covert offensive and defensive mine warfare; anti-submarine warfare (ASW); and anti-surface ship warfare. The Navy’s four SSGNs, which are converted former SSBNs, can carry larger numbers of Tomahawks and SOF personnel than can the SSNs. SSGN operations consequently may focus more strongly on Tomahawk and SOF missions than do SSN operations. For more on the Navy’s SSNs and SSGNs, see CRS Report RL32418, Navy Virginia (SSN-774) Class Attack Submarine Procurement: Background and Issues for Congress, by Ronald O'Rourke, and CRS Report RS21007, Navy Trident Submarine Conversion (SSGN) Program: Background and Issues for Congress, by Ronald O'Rourke. 4 The Navy’s non-strategic nuclear weapons—meaning all of the service’s nuclear weapons other than submarinelaunched ballistic missiles (SLBMs)—were removed from Navy surface ships and submarines under a unilateral U.S. nuclear initiative announced by President George H. W. Bush in September 1991. The initiative reserved a right to rearm SSNs at some point in the future with nuclear-armed Tomahawk land attack missiles (TLAM-Ns) should conditions warrant. Navy TLAM-Ns were placed in storage to support this option. DOD’s report on the 2010 Nuclear Posture Review (NPR), released on April 6, 2010, states that the Untied States will retire the TLAM-Ns. (Department (continued...) 2 Congressional Research Service 1 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program The SSBNs, in contrast, perform a specialized mission of strategic nuclear deterrence. To perform this mission, SSBNs are armed with submarine-launched ballistic missiles (SLBMs), which are large, long-range missiles armed with multiple nuclear warheads. SSBNs launch their SLBMs from large-diameter vertical launch tubes located in the middle section of the boat.5 The SSBNs’ basic mission is to remain hidden at sea with their SLBMs, so as to deter a nuclear attack on the United States by another country by demonstrating to other countries that the United States has an assured second-strike capability, meaning a survivable system for carrying out a retaliatory nuclear attack. Navy SSBNs, which are sometimes referred to informally as “boomers,”6 form one leg of the U.S. strategic nuclear deterrent force, or “triad,” which also includes land-based intercontinental ballistic missiles (ICBMs) and land-based long-range bombers. At any given moment, some of the Navy’s SSBNs are conducting nuclear deterrent patrols. The Navy’s report on its FY2011 30year shipbuilding plan states: “These ships are the most survivable leg of the Nation’s strategic arsenal and provide the Nation’s only day-to-day assured nuclear response capability.”7 The Department of Defense’s (DOD’s) report on the 2010 Nuclear Posture Review (NPR), released on April 6, 2010, states that “strategic nuclear submarines (SSBNs) and the SLBMs they carry represent the most survivable leg of the U.S. nuclear Triad.”8 Current Ohio-Class SSBNs The Navy currently operates 14 Ohio (SSBN-726) class SSBNs. The boats are commonly called Trident SSBNs or simply Tridents because they carry Trident SLBMs. A total of 18 Ohio-class SSBNs were procured in FY1974-FY1991. The ships entered service in 1981-1997. The boats were designed and built by General Dynamics’ Electric Boat Division (GD/EB) of Groton, CT, and Quonset Point, RI. They were originally designed for 30-year service lives but were later certified for 42-year service lives, consisting of two 20-year periods of operation separated by a two-year mid-life nuclear refueling overhaul, called an engineered refueling overhaul (ERO). The nuclear refueling overhaul includes both a nuclear refueling and overhaul work on the ship that is not related to the nuclear refueling. Ohio-class SSBNs each carry 24 SLBMs. The first eight boats in the class were originally armed with Trident I C-4 SLBMs; the final 10 were armed with larger and more-capable Trident II D-5 SLBMs. The Clinton Administration’s 1994 Nuclear Posture Review (NPR) recommended a (...continued) (...continued) conditions warrant. Navy TLAM-Ns were placed in storage to support this option. DOD’s report on the 2010 Nuclear Posture Review (NPR), released on April 6, 2010, states that the Untied States will retire the TLAM-Ns. (Department of Defense, Nuclear Posture Review Report, April 2010, pp. xiii and 28.) 5 SSBNs, like other Navy submarines, are also equipped with horizontal torpedo tubes in the bow for firing torpedoes or other torpedo-sized weapons. 6 This informal name is a reference to the large boom that would be made by the detonation of an SLBM nuclear warhead. 7 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 15. 8 Department of Defense, Nuclear Posture Review Report, April 2010, p. 22. The next sentence in the report states: “Today, there appears to be no viable near or mid-term threats to the survivability of U.S. SSBNs, but such threats—or other technical problems—cannot be ruled out over the long term.” The report similarly states on page 23: “Today, there appears to be no credible near or mid-term threats to the survivability of U.S. SSBNs. However, given the stakes involved, the Department of Defense will continue a robust SSBN Security Program that aims to anticipate potential threats and develop appropriate countermeasures to protect current and future SSBNs.” Congressional Research Service 2 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Ohio-class SSBNs each carry 24 SLBMs. The first eight boats in the class were originally armed with Trident I C-4 SLBMs; the final 10 were armed with larger and more-capable Trident II D-5 SLBMs. The Clinton Administration’s 1994 Nuclear Posture Review (NPR) recommended a strategic nuclear force for the START II strategic nuclear arms reduction treaty that included 14 Ohio-class SSBNs, all armed with D-5s. This recommendation prompted interest in the idea of converting the first four Ohio-class boats (SSBNs 726-729) into SSGNs, so as to make good use of the 20 years of potential operational life remaining in these four boats, and to bolster the U.S. SSN fleet. The first four Ohio-class boats were converted into SSGNs in 2002-2008,9 and the next four (SSBNs 730-733) were backfitted with D-5 SLBMs in 2000-2005, producing the current force of 14 Ohio-class SSBNs, all of which are armed with D-5 SLBMs. Eight of the 14 Ohio-class SSBNs are homeported at Bangor, WA, in Puget Sound; the other six are homeported at Kings Bay, GA, close to the Florida border. Unlike most Navy ships, which are operated by single crews, Navy SSBNs are operated by alternating crews (called the Blue and Gold crews) so as to maximize the percentage of time that they spend at sea in deployed status. The Navy consequently maintains 28 crews to operate its 14 Ohio-class SSBNs. The first of the 14 Ohio-class SSBNs (SSBN-730) will reach the end of its 42-year service life in 2027. The remaining 13 will reach the ends of their service lives at a rate of roughly one ship per year thereafter, with the 14th reaching the end of its service life in 2040. The Navy has initiated a program to refurbish and extend the service lives of D-5 SLBMs to 2042 “to match the OHIO Class submarine service life.”10 Figure 1 shows an Ohio-class SSBN with the hatches to some of its SLBM launch tubes open. 9 For more on the SSGN conversion program, see CRS Report RS21007, Navy Trident Submarine Conversion (SSGN) Program: Background and Issues for Congress, by Ronald O'Rourke. 10 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 4. Congressional Research Service 3 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Figure 1. Ohio (SSBN-726) Class SSBN With the hatches to some of its SLBM launch tubes open Source: U.S. Navy file photo accessed by CRS on February 24, 2011, at http://www.navy.mil/management/ photodb/photos/101029-N-1325N-005.jpg. Summary of U.S. SSBN Designs The Navy has operated four classes of SSBNs since 1959. Table 1 compares the current Ohioclass SSBN design to the three earlier U.S. SSBN designs. As shown in the table, the size of U.S. SSBNs has grown over time, reflecting in part a growth in the size and number of SLBMs carried on each boat. The Ohio class carries an SLBM (the D-5) that is much larger than the SLBMs carried by earlier U.S. SSBNs, and it carries 24 SLBMs, compared to the 16 on earlier U.S. SSBNs.11 In part for these reasons, the Ohio-class design, with a submerged displacement of 18,750 tons, is more than twice the size of earlier U.S. SSBNs. 11 The larger size of the Ohio-class design also reflects a growth in size over time in U.S. submarine designs due to other reasons, such as providing increased interior volume for measures to quiet the submarine acoustically, so as to make it harder to detect. Congressional Research Service 4 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Table 1. U.S. SSBN Classes George Washington (SSBN-598) class Ethan Allen (SSBN-608) class Lafayette/Benjamin Franklin (SSBN616/640) class Ohio (SSBN-726) class 5 5 31 18/14 Fiscal years procured FY1958-FY1959 FY1959 and FY1961 FY1961-FY1964 FY1974/FY1977 FY1991 Years in commission 1959-1985 1961-1992 1963-2002 1981/1984 - present Length 381.7 feet 410.5 feet 425 feet 560 feet Beam 33 feet 33 feet 33 feet 42 feet 6,700 tons 7,900 tons 8,250 tons 18,750 tons 16 16 16 24 Polaris A-3 Polaris A-3 Poseidon C-3/ Trident I C-4 Trident II D-5 Diameter of those SLBMs 54 inches 54 inches 74 inches 83 inches Length of those SLBMs 32.3 feet 32.3 feet 34 feet 44 feet Weight of each SLBM (pounds) 36,000 pounds 36,000 pounds 65,000/73,000 pounds ~130,000 pounds Range of SLBMs ~2,500 nm ~2,500 nm ~2,500 nm/~4,000 nm ~4,000 nm Number in class Submerged displacement Number of SLBMs Final type(s) of SLBM carried Sources: Prepared by CRS based on data in Norman Polmar, The Ships and Aircraft of the U.S. Fleet, Annapolis, Naval Institute Press, various editions, and (for SSBN decommissioning dates) U.S. Naval Vessel Register. Notes: Beam is the maximum width of a ship. For the submarines here, which have cylindrical hulls, beam is the diameter of the hull. The range of an SLBM can vary, depending on the number and weight of nuclear warheads it carries; actual ranges can be lesser or greater than those shown. The George Washington-class boats were procured as modifications of SSNs that were already under construction. Three of the boats were converted into SSNs toward the ends of their lives and were decommissioned in 1983-1985. The two boats that remained SSBNs throughout their lives were decommissioned in 1981. All five Ethan Allen-class boats were converted into SSNs toward the ends of their lives. The boats were decommissioned in 1983 (two boats), 1985, 1991, and 1992. Two of the Lafayette/Benjamin Franklin-class boats were converted into SSNs toward the ends of their lives and were decommissioned in 1999 and 2002. The 29 that remained SSBNs throughout their lives were decommissioned in 1986-1995. For 19 of the boats, the Poseidon C-3 was the final type of SLBM carried; for the other 12, the Trident I C-4 SLBM was the final type of SLBM carried. A total of 18 Ohio-class SSBNs were built. The first four, which entered service in 1981-1984, were converted into SSGNs in 2002-2008. The remaining 14 boats entered service in 1984-1997. Congressional Research Service 5 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program U.S.-UK Cooperation on SLBMs SSBNs are also operated by the United Kingdom, France, Russia, and China.12 The UK’s four Vanguard-class SSBNs, which entered service in 1993-1999, each carry 16 Trident II D-5 SLBMs. Previous classes of UK SSBNs similarly carried earlier-generation U.S. SLBMs.13 The UK’s use of U.S.-made SLBMs on its SSBNs is one element of a long-standing close cooperation between the two countries on nuclear-related issues that is carried out under the 1958 Agreement for Cooperation on the Uses of Atomic Energy for Mutual Defense Purposes (also known as the Mutual Defense Agreement). Within the framework established by the 1958 agreement, cooperation on SLBMs in particular is carried out under the 1963 Polaris Sales Agreement and a 1982 Exchange of Letters between the two governments.14 The Navy testified in March 2010 that 12 India in July 2009 launched a nuclear-powered submarine that is equipped to carry several short-range SLBMs; the ship is not with four vertical launch tubes for launching 12 short-range SLBMs or cruise missiles; the ship is expected to enter service until 2011 at the earliestin 2012. 13 Although the SLBMs on UK SSBNs are U.S.-made, the nuclear warheads on the missiles are of UK design and manufacture. 14 A March 18, 2010, report by the UK Parliament’s House of Commons Foreign Affairs Committee stated: During the Cold War, the UK’s nuclear co-operation with the United States was considered to be at the heart of the [UK-U.S.] ‘special relationship’. This included the 1958 Mutual Defence Agreement, the 1963 Polaris Sales Agreement (PSA) (subsequently amended for Trident), and the UK’s use of the US nuclear test site in Nevada from 1962 to 1992. The co-operation also encompassed agreements for the United States to use bases in Britain, with the right to store nuclear weapons, and agreements for two bases in Yorkshire (Fylingdales and Menwith Hill) to be upgraded to support US missile defence plans. In 1958, the UK and US signed the Mutual Defence Agreement (MDA). Although some of the appendices, amendments and Memoranda of Understanding remain classified, it is known that the agreement provides for extensive co-operation on nuclear warhead and reactor technologies, in particular the exchange of classified information concerning nuclear weapons to improve design, development and fabrication capability. The agreement also provides for the transfer of nuclear warhead-related materials. The agreement was renewed in 2004 for another ten years. The other major UK-US agreement in this field is the 1963 Polaris Sales Agreement (PSA) which allows the UK to acquire, support and operate the US Trident missile system. Originally signed to allow the UK to acquire the Polaris Submarine Launched Ballistic Missile (SLBM) system in the 1960s, it was amended in 1980 to facilitate purchase of the Trident I (C4) missile and again in 1982 to authorise purchase of the more advanced Trident II (D5) in place of the C4. In return, the UK agreed to formally assign its nuclear forces to the defence of NATO, except in an extreme national emergency, under the terms of the 1962 Nassau Agreement reached between President John F. Kennedy and Prime Minister Harold Macmillan to facilitate negotiation of the PSA. Current nuclear co-operation takes the form of leasing arrangements of around 60 Trident II D5 missiles from the US for the UK’s independent deterrent, and long-standing collaboration on the design of the W76 nuclear warhead carried on UK missiles. In 2006 it was revealed that the US and the UK had been working jointly on a new ‘Reliable Replacement Warhead’ (RRW) that would modernise existing W76-style designs. In 2009 it emerged that simulation testing at Aldermaston on dual axis hydrodynamics experiments had provided the US with scientific data it did not otherwise possess on this RRW programme. The level of co-operation between the two countries on highly sensitive military technology is, according to the written submission from Ian Kearns, “well above the norm, even for a close alliance relationship”. He quoted Admiral William Crowe, the former US Ambassador to London, who likened the UK-US nuclear relationship to that of an iceberg, “with a small tip of it sticking out, but beneath the water there is quite a bit of everyday business that goes on between our two governments in a fashion that’s unprecedented in the world.” Dr Kearns also commented that the personal bonds between the US/UK scientific and technical establishments were deeply rooted. (House of Commons, Foreign Affairs Committee, Sixth ReporReport Global Security: UK-US Relations, March 18, 2010, paragraphs 131-135; http://www.publications.parliament.uk/pa/cm200910/ cmselect/cmfaff/114/11402.htm; paragraphs 131-135 are included in the section of the report (continued...) Congressional Research Service 6 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program “the United States and the United Kingdom have maintained a shared commitment to nuclear deterrence through the Polaris Sales Agreement since April 1963. The U.S. will continue to maintain its strong strategic relationship with the UK for our respective follow-on platforms, based upon the Polaris Sales Agreement.”15 The first Vanguard-class SSBN was originally projected to reach the end of its service life in 2024, but an October 2010 UK defense and security review report states that the lives of the Vanguard class ships will now be extended by a few years, so that the four boats will remain in service into the late 2020s and early 2030s.16 The UK plans to replace the four Vanguard-class boats with three or four next-generation SSBNs. The October 2010 UK defense and security review report states that each new SSBN is to be equipped with 8 D-5 SLBMs, rather than 12 as previously planned. The report states that “‘Initial Gate’—a decision to move ahead with early stages of the work involved—will be approved and the next phase of the project will start by the end of [2010]. ‘Main Gate’—the decision to start building the submarines—is required around 2016.”17 The first new boat is to be delivered by 2028, or about four years later than previously planned.18 The UK has wanted their replacement SSBNs to carry D-5 SLBMs, and for any successor to the D-5 SLBM to be compatible with, or be capable of being made compatible with, the D-5 launch system. President George W. Bush, in a December 2006 letter to UK Prime Minister Tony Blair, invited the UK to participate in any program to replace the D-5 SLBMs, and stated that any successor to the D-5 system should be compatible with, or be capable of being made compatible with, the launch system for the D-5 SLBM. SSBN(X)Ohio Replacement Program Program Origin and Early Milestones Although the eventual need to replace the Ohio-class SSBNs has been known for many years, the SSBN(X)Ohio replacement program can be traced more specifically to an exchange of letters in December 2006 2006 between President George W. Bush and UK Prime Minister Tony Blair concerning the UK’s desire to participate in a program to extend the service life of the Trident II D-5 SLBM into the 2040s, and to have its next-generation SSBNs carry D-5s. Following this exchange of letters, and with an awareness of the projected retirement dates of the Ohio-class SSBNs and the time that would likely be needed to develop and field a replacement for them, DOD in 2007 began studies (...continued) available at http://www.publications.parliament.uk/pa/cm200910/cmselect/cmfaff/114/11406.htm.) 15 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 6. 16 Securing Britain in an Age of Uncertainty: The Strategic Defence and Security Review, Presented to Parliament by the Prime Minister by Command of Her Majesty, October 2010, p. 39. 17 Securing Britain in an Age of Uncertainty: The Strategic Defence and Security Review, Presented to Parliament by the Prime Minister by Command of Her Majesty, October 2010, p. 5, 38-39. For more on the UK’s Successor SSBN program as it existed prior to the October 2010 UK defense and security review report, see Richard Scott, “Deterrence At A Discount?” Jane’s Defence Weekly, December 23, 2009: 26-31. 18 Securing Britain in an Age of Uncertainty: The Strategic Defence and Security Review, Presented to Parliament by the Prime Minister by Command of Her Majesty, October 2010, p. 39. Congressional Research Service 7 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program on a next-generation sea-based strategic deterrent (SBSD).19 The studies used the term sea-based strategic deterrent (SBSD) to signal the possibility that the new system would not necessarily be a submarine. An Initial Capabilities Document (ICD) for a new SBSD was developed in early 200820 and approved by DOD’s Joint Requirements Oversight Committee (JROC) on June 20, 2008.21 In July 2008, DOD issued a Concept Decision providing guidance for an analysis of alternatives (AOA) for the program; an acquisition decision memorandum from John Young, DOD’s acquisition executive, stated the new system would, barring some discovery, be a submarine. 22 The Navy established an SSBN(X)Ohio replacement program office at about this same time. 23 The AOA reportedly began in the summer or fall of 2008.24 The AOA was completed, with final brief to the Office of the the Secretary of Defense (OSD), on May 20, 2009. The final AOA report was completed in September 2009. An AOA Sufficiency Review Letter was signed by OSD’s Director, Cost Assessment & Program Evaluation (CAPE) on December 8, 2009.25 The program’s Milestone A review meeting was held on December 9, 2010. On February 3, 2011, the Navy provided the following statement to CRS concerning the outcome of the December 9 meeting: The OHIO Replacement Program achieved Milestone A and has been approved to enter the Technology Development Phase of the Dept. of Defense Life Cycle Management System as of Jan. 10, 2011. This milestone comes following the endorsement of the Defense Acquisition Board (DAB), chaired by Dr. Carter (USD for Acquisition, Technology, and Logistics) who has signed the program’s Milestone A Acquisition Decision Memorandum (ADM). The DAB endorsed replacing the current 14 Ohio-class Ballistic Missile Submarines (SSBNs) as they reach the end of their service life with 12 Ohio Replacement Submarines, each comprising 16, 87-inch diameter missile tubes utilizing TRIDENT II D5 Life Extended missiles (initial loadout). The decision came after the program was presented to the Defense Acquisition Board (DAB) on Dec. 9, 2010. 19 In February 2007, the commander of U.S. Strategic Command (STRATCOM) commissioned a task force to support an anticipated Underwater Launched Missile Study (ULMS). On June 8, 2007, the Secretary of the Navy initiated the ULMS. Six days later, the commander of STRATCOM directed that a Sea Based Strategic Deterrent (SBSD) capability-based assessment (CBA) be performed. In July 2007, the task force established by the commander of STRATCOM provided its recommendations regarding capabilities and characteristics for a new SBSD. (Source: Navy list of key events relating to the ULMS and SBSD provided to CRS and the Congressional Budget Office (CBO) on July 7, 2008.) 20 On February 14, 2008, the SBSD ICD was approved for joint staffing by the Navy’s Resources and Requirements Review Board (R3B). On April 29, 2008, the SBSD was approved by DOD’s Functional Capabilities Board (FCB) to proceed to DOD’s Joint Capabilities Board (JCB). (Source: Navy list of key events relating to the ULMS and SBSD provided to CRS and the Congressional Budget Office (CBO)CBO on July 7, 2008.) 21 Navy briefing to CRS and CBO on the SBSD program, July 6, 2009. 22 Navy briefing to CRS and CBO on the SBSD program, July 6, 2009. 23 An August 2008 press report states that the program office, called PMS-397, “was established within the last two months.” (Dan Taylor, “Navy Stands Up Program Office To Manage Next-Generation SSBN,” Inside the Navy, August 17, 2008. 24 “Going Ballistic,” Defense Daily, September 22, 2008, p. 1. 25 Department of Defense Fiscal Year (FY) 2012 Budget Estimates, Navy, Justification Book Volume 2, Research, Development, Test & Evaluation, Navy Budget Activity 4, entry for PE0603561N, Project 3220 (pdf page 345 of 888). Congressional Research Service 8 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program The ADM validates the program’s Technology Development Strategy and allows entry into the Technology Development Phase during which warfighting requirements will be refined to meet operational and affordability goals. Design, prototyping, and technology development efforts will continue to ensure sufficient technological maturity for lead ship procurement in 2019. The first OHIO Replacement submarine will enter service in Fiscal Year 2029 as the existing OHIO submarines reach the end of their extended service life of 43 years.26 A November 2010 DOD report to Congress on strategic nuclear weapon systems stated that: Current key milestones for the SSBN replacement program include: • Research, development, test, and evaluation (RDT&E) began in FY 2010 and continues with the goal of achieving 10 percent greater design maturity prior to starting procurement than the USS VIRGINIA class had before procurement started; • In FY 2015, the Navy will begin the detailed design and advanced procurement of critical components; • In FY 2019, the Navy will begin the seven-year construction period for the new SSBN lead ship; • In FY 2026, the Navy will begin the three-year strategic certification period for the lead ship; and • In FY 2029, the lead ship will commence active strategic at-sea service.27 Procurement and Replacement Schedule Table 2 shows the Navy’s proposed schedule for procuring 12 SSBN(X)s, and for having SSBN(X)s replace Ohio-class SSBNs. As shown in the table, the Navy wants to procure the first SSBN(X) in FY2019 and have it enter service in FY2029. The remaining 11 would be procured between FY2022 and FY2033 and would enter service between FY2030 and FY2040. The Navy states that the schedule for procuring the 12 SSBN(X)s is inextricably linked to legacy [i.e., Ohio-class] SSBN retirements. The latest start for the lead SSBN(X) is FY 2019 and the replacements must start reaching the operational force by FY 2029. There is no leeway in this plan to allow a later start or any delay in the procurement plan.28 26 Source: Email from Navy Office of Legislative Affairs to CRS, February 3, 2011. 27 November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10. 28 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 24. The report similarly states on page 5 that “the first boat in the class must be procured no later than FY 2019 to ensure that 12 operational ballistic missile submarines will always be available to perform the vital strategic deterrent mission.” Congressional Research Service 9 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program The implication from this statement is that deferring the procurement of one or more SSBN(X)s beyond the dates shown in Table 2 would result in an SSBN force that drops below 12 boats for some period of time. Table 2. Navy Schedule for Procuring SSBN(X)s and Replacing Ohio-Class SSBNs Ohio-class SSBNs in service Combined number of Ohioclass SSBNs and SSBN(X)s in service 14 14 2020 14 14 2021 14 14 14 14 14 14 Fiscal Year Number of SSBN(X)s procured 2019 1 2022 Cumulative number of SSBN(X)s in service 1 2023 2024 1 14 14 2025 1 14 14 2026 1 14 14 2027 1 13 13 2028 1 12 13 2029 1 1 11 12 2030 1 2 10 12 2031 1 3 9 12 2032 1 4 8 12 2033 1 5 7 12 2034 6 6 12 2035 7 5 12 2036 8 4 12 2037 9 3 12 2038 10 2 12 2039 11 1 12 2040 12 12 Source: Navy data provided by the Navy to CRS and the Congressional Budget Office on February 18, 2010, by Navy Office of Legislative Affairs26 Procurement and Replacement Schedule Table 2 shows the Navy’s proposed schedule for procuring 12 SSBN(X)s, and for having SSBN(X)s replace Ohio-class SSBNs. As shown in Table 2, under the Navy’s FY2012 budget, the first Ohio replacement boat was scheduled to be procured in FY2019, and Ohio replacement boats were to enter service on a schedule that would maintain the Navy’s SSBN force at 12 boats. As also shown in Table 2, the Navy’s proposed FY2013 budget defers the procurement of the first Ohio replacement boat by two years, to FY2021. As a result of this deferment, the Navy’s SSBN force will drop to 10 boats during most of the 2030s. 26 Source: Email from Navy Office of Legislative Affairs to CRS, February 3, 2011. Congressional Research Service 9 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Table 2. Navy Schedule for Procuring SSBN(X)s and Replacing Ohio-Class SSBNs Schedule in FY2012 Budget Schedule under FY2013 Budget Ohioclass SSBNs in service Combined number of Ohio-class SSBNs and SSBN(X)s in service 14 2020 2021 Fiscal Year Number of SSBN(X)s procured each year 2019 1 2022 Cumulative number of SSBN(X)s in service 1 2023 Ohioclass SSBNs in service Combined number of Ohio-class SSBNs and SSBN(X)s in service 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 Number of SSBN(X)s procured each year Cumulative number of SSBN(X)s in service 1 2024 1 14 14 1 2025 1 14 14 2026 1 14 14 1 14 14 2027 1 13 13 1 13 13 2028 1 12 13 1 12 12 2029 1 1 11 12 1 11 11 2030 1 2 10 12 1 1 10 11 2031 1 3 9 12 1 2 9 11 2032 1 4 8 12 1 2 8 10 2033 1 5 7 12 1 3 7 10 2034 6 6 12 1 4 6 10 2035 7 5 12 1 5 5 10 2036 8 4 12 6 4 10 2037 9 3 12 7 3 10 2038 10 2 12 8 2 10 2039 11 1 12 9 1 10 2040 12 12 10 0 10 2041 12 12 11 0 11 2042 12 12 12 0 12 Source: Navy FY2012 and FY2013 budget submissions. SSBN(X) Design Features Although the design of the SSBN(X) has not yet been fully determined, the boat’s design will reflect the following: Congressional Research Service 10 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program • The SSBN(X) is to be designed for a 40-year expected service life.2927 • Unlike the Ohio-class design, which requires a mid-life nuclear refueling, the SSBN(X) is to be equipped with a life-of-the-ship nuclear fuel core (a nuclear fuel core that is sufficient to power the ship for its entire expected service life).3028 Although the SSBN(X) will not need a mid-life nuclear refueling, it will likely still need a mid-life overhaul, like the Ohio-class design, to operate over its full 40-year life.29 • The SSBN(X) is to be equipped with an electric-drive propulsion plant, as opposed to the mechanical-drive propulsion plant used on other Navy submarines. The electric-drive plant is expected to be quieter (i.e., stealthier) than a mechanical-drive plant.3130 • The SSBN(X) is to have SLBM launch tubes that are the same size as those on the Ohio class (i.e., tubes with a diameter of 87 inches and a length sufficient to accommodate a D-5 SLBM). This will give the SSBN(X) a beam (i.e., diameter)3231 at least as great as the 42-foot beam of the Ohio-class design, and possibly a bit larger. • Instead of 24 SLBM launch tubes, as on the Ohio-class design, the SSBN(X) is to have 16 SLBM launch tubes. • Although the SSBN(X) is to have fewer launch tubes than the Ohio-class SSBN, it is to have a submerged displacement about the same as that of the Ohio-class design.3332 • The Navy states that “owing to the unique demands of strategic relevance, [SSBN(X)s] must be fitted with the most up-to-date capabilities and stealth to ensure they are survivable throughout their full 40-year life span.”34 Program Acquisition Cost Research and Development Cost A November 2010 DOD report to Congress on strategic nuclear weapon systems stated that research and development costs for the SSBN(X) program for the period FY2011-FY2020 are estimated by DOD at about $11.6 billion in then-year dollars.35 This is not the total estimated 29 33 27 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 24. 30 28 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 5. The two most recent classes of SSNs—the Seawolf (SSN-21) and Virginia (SSN-774) class boats—are built with cores that are expected to be sufficient for their entire 33-year expected service lives. 3129 As mentioned earlier (see “Current Ohio-Class SSBNs”), the Ohio-class boats receive a mid-life nuclear refueling overhaul, called an Engineered Refueling Overhaul (ERO), which includes both a nuclear refueling and overhaul work on the ship that is not related to the nuclear refueling. 30 Source: Spoken testimony of Admiral Kirkland Donald, Deputy Administrator for Naval Reactors, and Director, Naval Nuclear Propulsion, National Nuclear Security Administration, at a March 30, 2011, hearing before the Strategic Forces Subcommittee of the Senate Armed Services Committee, as shown in the transcript of the hearing. 3231 Beam is the maximum width of a ship. For Navy submarines, which have cylindrical hulls, beam is the diameter of the hull. 3332 A May 2010 CBO report states that “in a recent briefing to CBO and the Congressional Research Service, the Navy stated that an SSBN(X) would probably be about the same size and have roughly the same displacement as an Ohio class submarine, even though it might have only 16 or 20 missile tubes.” (Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2011 Shipbuilding Plan, May 2010, p. 16.) 3433 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 24. 35 November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START (continued...) Congressional Research Service 11 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program research and development cost for the SSBN(X) program, as it excludes research and development costs for FY2010 and prior years (which are shown in Table 3), as well as research and development costs for FY2021 and subsequent years. Given the estimated cost of $11.6 billion in then-year dollars for the period FY2011-FY2020, it is conceivable that the total research and development cost for the program as estimated by DOD might approach $15 billion in thenyear dollars. Procurement Cost The Navy in February 2010 preliminarily estimated the procurement cost of each SSBN(X) at $6 billion to $7 billion in FY2010 dollars.36 Following the SSBN(X) program’s December 9, 2010, Milestone A acquisition review meeting (see “Program Origin and Milestones”), DOD issued an Acquisition Decision Memorandum (ADM) that, among other things, establishes a target average unit procurement cost for boats 2-12 in the program of $4.9 billion in FY2010 dollars.37 The Navy is working to achieve this target cost, and estimated that, as of early 2011, its cost-reduction efforts had reduced the estimated average unit procurement cost of boats 2-12 to $5.6 billion each in FY2010 dollars.38 The Navy is examining potential further measures to bring the cost of boats 2-12 closer to the $4.9 billion target cost.39 D-5 Missile Refurbishment Cost The above cost figures do not include costs for refurbishing D-5 SLBMs so as to extend their service lives to 2042. Common Missile Compartment (CMC) Current U.S. and UK plans call for the SSBN(X) and the UK’s replacement SSBN to use a missile compartment—the middle part of the boat with the SLBM launch tubes—of the same (...continued) Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10. 36 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 20. 37 Program Acquisition Cost A March 2012 GAO report assessing major DOD weapon acquisition programs states that the estimated total acquisition cost of the SSBN(X) program is $90,433.5 million (about $90.4 billion) in constant FY2012 dollars, including $11,142.8 million (about $11.1 billion) in research and development costs and $79,290.7 million (about $79.3 billion) in procurement costs.34 The Navy estimates the procurement cost of the lead ship in the program at $11.7 billion in constant FY2012 dollars, including $4.5 billion in detailed design and nonrecurring engineering (DD/NRE) costs for the entire class, and $7.2 billion in hands-on construction costs for the ship itself.35 (It is a traditional budgeting practice for Navy shipbuilding programs to attach the DD/NRE costs for a new class of ships to the procurement cost of the lead ship in the class.) The Navy in February 2010 preliminarily estimated the procurement cost of each Ohio replacement boat at $6 billion to $7 billion in FY2010 dollars.36 Following the Ohio replacement program’s December 9, 2010, Milestone A acquisition review meeting (see “Program Origin and Early Milestones”), DOD issued an Acquisition Decision Memorandum (ADM) that, among other things, established a target average unit procurement cost for boats 2-12 in the program of $4.9 billion in constant FY2010 dollars.37 The Navy is working to achieve this target cost, and estimates that, as of early 2012, its cost-reduction efforts have reduced the estimated average unit procurement cost of boats 2-12 to $5.6 billion each in constant FY2010 dollars.38 The Navy is examining potential further measures to bring the cost of boats 2-12 closer to the $4.9 billion target cost. The Navy’s FY2013 30-year (FY2013-FY2042) shipbuilding plan, submitted to Congress on March 28, 2012, expresses costs in constant FY2012 dollars. The plan translates the above target cost of $4.9 billion in constant FY2010 dollars to $5.3 billion in constant FY2012 dollars, and states: This plan assumes the average recurring affordability target for the second through twelfth SSBN(X)s will be $6.025B [billion] per boat. This cost reflects a concerted DoN [Department of the Navy] effort to rationalize the boat’s requirements, which cut the projected cost for the boats by nearly $1 billion. The SSBN(X) Milestone A Acquisition Decision Memorandum established an even lower affordability target of $5.3B per boat. While DoN cannot yet state with certainty it will achieve this aggressive target, it is committed to meeting this goal. Indeed, the DoN PB2012 budget submission [the President’s budget for FY2012—that is, that Navy’s proposed FY2012 budget] added $150M [million] 34 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapons Programs, GAO-12400SP, March 2012, p. 152. The report states on page 161 that cost figures in the report are presented in constant FY2012 dollars. 35 Department of the Navy, Annual Report to Congress on Long-Range Plan for Construction of Naval Vessels for FY2013, April 2012, p. 15. 36 Department of the Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 20. 37 Christopher J. Castelli, “DOD: New Nuclear Subs Will Cost $347 Billion To Acquire, Operate,” Inside the Navy, February 21, 2011; Elaine M. Grossman, “Future U.S. Nuclear-Armed Vessel to Use Attack-Submarine Technology,” Global Security Newswire, February 24, 2011; Jason Sherman, “Navy Working To Cut $7.7 Billion From Ohio Replacement Program,” Inside the Navy, February 28, 2011. 38 See, for example, Dan Taylor, “Stackley: Navy Will Constantly Seek Ways To Drive Out SSBN(X) Costs,” Inside the Navy, March 7, 2011; and Jason Sherman, “Navy Working To Cut $7.7 Billion From Ohio Replacement Program,” Inside the Navy, February 28, 2011. 39 Additional information on SSBN(X) procurement costs was presented in the November 2010 DOD report to Congress on strategic nuclear weapon systems. The report stated that procurement costs for the SSBN(X) program for the period FY2011-FY2020 were estimated by DOD at that time at about $17.8 billion in then-year dollars. (November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10.) Given DOD’s planned schedule for procuring SSBN(X)s (see Table 2), this figure likely includes much (but perhaps not all) of the procurement cost for the lead boat in the program, as well as a portion (in the form of advance procurement funding) of the procurement cost of the second boat in the program. Congressional Research Service 12 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program See also Christopher J. Castelli, “DOD Puts ‘Should-Cost’ Pressure On Major Weapons Programs,” Inside the Navy, May 2, 2011. 38 Source: Navy briefing for CRS and Congressional Budget Office on Navy submarine programs, March 16, 2012. Congressional Research Service 12 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program in research and development dollars to explore ways to drive down the recurring costs for follow-on boats.39 The above cost figures do not include costs for refurbishing D-5 SLBMs so as to extend their service lives to 2042. Common Missile Compartment (CMC) Current U.S. and UK plans call for the SSBN(X) and the UK’s replacement SSBN to use a missile compartment—the middle part of the boat with the SLBM launch tubes—of the same general design.40 As mentioned earlier (see “U.S.-UK Cooperation on SLBMs”), the UK’s SSBN is to be armed with eight SLBMs, or half the number to be carried by the SSBN(X). The modular design of the CMC will accommodate this difference. Since the UK’s first Vanguard-class SSBN was originally projected to reach the end of its service life in 2024—three years before the first Ohio-class SSBN is projected to reach the end of its service life—design work on the CMC began about three years sooner than would have been required to support the SSBN(X)Ohio replacement program alone. This is the principal reason why the FY2010 budget included a substantial amount of research research and development funding for the CMC. The UK is providing some of the funding for the design design of the CMC, including a large portion of the initial funding. A March 2010 Government Accountability office (GAO) report stated: According to the Navy, in February 2008, the United States and United Kingdom began a joint effort to design a common missile compartment. This effort includes the participation of government officials from both countries, as well as industry officials from Electric Boat Corporation and BAE Systems. To date, the United Kingdom has provided a larger share of funding for this effort, totaling just over $200 million in fiscal years 2008 and 2009.41 A March 2011 GAO report stated: The main focus of OR [Ohio Replacement program] research and development to date has been the CMC. The United Kingdom has provided $329 million for this effort since fiscal year 2008. During fiscal years 2009 and 2010, the Navy had allocated about $183 million for the design and prototyping of the missile compartment.42 A May 2010 press report stated that “the UK has, to date, funded the vast majority of [the CMC’s] upfront engineering design activity and has established a significant presence in Electric Boat’s Shaw’s Cove CMC design office in New London, CT.”43 Under the October 2010 UK defense and security review report (see “U.S.-UK Cooperation on SLBMs”), the UK now plans to deliver its first SSBN in 2028, or about four years later than previously planned. Program Funding Table 3 shows funding for the SSBN(X) program. The table shows U.S. funding only; it does not include funding provided by the UK to help pay for the design of the CMC. As can be seen in the table, the Navy’s proposed FY2012 budget requests $1,067 million in research and development funding for the program. 40 39 Department of the Navy, Annual Report to Congress on Long-Range Plan for Construction of Naval Vessels for FY2013, April 2012, pp. 15-16. 40 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 6, which states: “The OHIO Replacement programs includes the development of a common missile compartment that will support both the OHIO Class Replacement and the successor to the UK Vanguard Class.” 41 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-10388SP, March 2010, p. 152. 42 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-11233SP, March 2011, p. 147. 43 43 Sam LaGrone and Richard Scott, “Deterrent Decisions: US and UK Wait on Next Steps for SSBN Replacements,” Jane’s Navy International, May 2010, pp. 10-11. Congressional Research Service 13 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Table 3. SSBN(X)Under the October 2010 UK defense and security review report (see “U.S.-UK Cooperation on SLBMs”), the UK now plans to deliver its first SSBN in 2028, or about four years later than previously planned. Program Funding Table 3 shows funding for the Ohio replacement program. The table shows U.S. funding only; it does not include funding provided by the UK to help pay for the design of the CMC. As can be seen in the table, Navy’s proposed FY2013 budget requests $564.9 million for continued research and development work on the program. Table 3. Ohio Replacement Program Funding (Millions of then-year dollars, rounded to nearest tenth; totals may not add due to rounding) FY08 FY09 FY10 FY11 (req.)a FY12 FY12 FY13 (req.) FY13FY14 (proj.) FY14FY15 (proj.) FY15FY16 (proj.) FY16FY17 (proj.) Research and development (R&D) funding PE0101221N/Project 3198 0 9.7 0 0 0 0 0 0 0 0 PE0603561N/Project 3220 0 0 363.4 493.0 781.6 857.5 1,064.2 786.7 748.8431.4 781.6 483.1 793.5 861.4 1,037.4 708.9 PE0603561N/Project 9999 4.9 3.2 4.0 0 0 0 0 0 0 0 PE0603570N/Project 3219 0 0 107.5 179.3 285.4 347.1 405.5 394.7 394.3 Total R&D funding178.3 285.4 81.8 296.0 360.4 420.8 409.7 4.9 12.9 474.9 672.3 1,067.0 1,204.6 1,469.7 1,181.4 1,143.1609.7 1,067.0 564.9 1,089.5 1,221.8 1,458.2 1,118.6 0 0 0 0 0 0 0 736.0 795.20 0 777.8 4.9 12.9 474.9 672.3 1,067.0 1,204.6 1,469.7 1,917.4 1,938.3 609.7 1,067.0 564.9 1,089.5 1,221.8 1,458.2 1,896.4 Total R&D funding Procurement funding TOTAL all funding Source: Navy FY2012 budget submission and (for FY2015 and FY2016 procurement funding) Navy data provided to CRS on February 25, 2010, by Navy Office of Legislative AffairsFY2013 budget submission. Notes: PE means Program Element, that is, a research and development line item. A Program Element may include several projects. PE0101221N/Project 3198 is Underwater Launch Missile System (ULMS) project within the PE for Strategic Submarine and Weapons System Support. PE0603561N/Project 3220 is SBSD project within the PE for Advanced Submarine System Development. PE0603561N/Project 9999 is Congressional funding additions within the PE for Advanced Submarine System Development. PE0603570N/Project 3219 is SSBN(X) reactor plant project within the PE for Advanced Nuclear Power Systems. Procurement funding shown in FY2015 and FY2016FY2017 is advance procurement funding for first SSBN(X), which is scheduled to be procured in FY2019. a. For final action on the FY2011 funding request, see the Appendix. Issues for Congress Potential oversight issues for Congress for the SSBN(X) program include the following: scheduled to be procured in FY2021. Issues for Congress Potential oversight issues for Congress for the Ohio replacement program include the following: • the reasons for deferring the start of SSBN(X) procurement by two years, to FY2021, the cost and operational impact of this decision, and whether it would be feasible and cost effective to restore the start of procurement to FY2019, as planned under the FY2012 budget; • the plan to design the SSBN(X) with 16 SLBM tubes rather than 20; • the plan to procure 12 SSBN(X)s rather than 13 or 14; Congressional Research Service 14 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program • the likelihood that the Navy will be able to reduce the average procurement cost of boats 2-12 in the program to the target figure of $4.9 billion each in FY2010 dollars; • the accuracy of the Navy’s estimate of the procurement cost of each SSBN(X); • the prospective affordability of the SSBN(X)Ohio replacement program and its potential impact on funding available for other Navy shipbuilding programs; and • the question of which shipyard or shipyards will build SSBN(X)s. Each of these issues is discussed below. Two-Year Deferral in Start of Procurement One oversight issue for Congress concerns the reasons for deferring the start of SSBN(X) procurement by two years, to FY2021, the cost and operational impact of this decision, and whether it would be feasible and cost effective to restore the start of procurement to FY2019, as planned under the FY2012 budget. The two-year deferral reduced funding requirements for the Ohio replacement program within the FY2013-FY2017 Future Years Defense Program (FYDP); its effect on the program’s total research and development cost and its total procurement cost over the longer run is less clear. As shown in Table 2, the two year deferral would reduce the SSBN force to 10 boats during most of the 2030s. In explaining the two-year deferral, Secretary of Defense Leon Panetta stated on January 26, 2012, that “our review determined that we could achieve better cost control by delaying the nextgeneration ballistic missile submarine for two years without harming the survivability of our nuclear deterrent.”44 In a follow-on briefing that same day, Aston Carter, the Under Secretary of Defense for Acquisition, Technology, and Logistics (i.e., DOD’s acquisition executive) stated that the twoyear deferral is not a strategic decision; this is a managerial decision made partly for budgetary reasons but mostly because that puts the Ohio class replacement on a more predictable and stable schedule.... With respect to the schedule [for the program], the schedule as it was [under the FY2012 budget], was an aggressive one, maybe even verging on optimistic. So I—all I'm saying is this is a safer schedule; we're sure we can make this schedule. So it’s a little more secure; so, from a managerial point of view, a better place to be.45 At a February 16, 2012, hearing before the House Armed Services Committee on the Department of the Navy’s proposed FY2013 budget, the following exchange occurred: 44 Source: Transcript of “Major Budget Decisions Briefing from the Pentagon,” January 26, 2012, available online at http://www.defense.gov/transcripts/transcript.aspx?transcriptid=4962. 45 Source: Transcript of “Major Budget Decisions Briefing at the Pentagon,” January 26, 2012, available online at http://www.defense.gov/transcripts/transcript.aspx?transcriptid=4963 • where in the budget to fund the program’s detailed design/nonrecurring engineering (DD/NRE costs); and • the question of which shipyard or shipyards will build SSBN(X)s. Congressional Research Service 14 . 15 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Each of these issues is discussed below. A Design with 16 vs. 20 SLBM Tubes One oversight issue for Congress concerns the plan to design the SSBN(X) with 16 SLBM tubes rather than 20—one of several decisions made to reduce the estimated average procurement cost of boats 2 through 12 in the program to $5.6 billion in FY2010 dollars.44REPRESENTATIVE MIKE MCINTYRE: Admiral, I wanted to ask you, with the Ohio Class SSBNs scheduled to begin retiring in 2027, how will delaying the Ohio Class replacement program by two years affect the Navy’s ability to meet STRATCOM’s [U.S. Strategic Command’s] at-sea requirements [for nuclear deterrent forces]? ADMIRAL JONATHAN GREENERT, CHIEF OF NAVAL OPERATIONS: Well, what we'll have to do, we—we owe a certain number of submarines in a certain number of time. [sic] I can't give you those numbers specifically due to the classification. But the point here is we have to measure the ability to meet that operational availability during that timeframe. We’ve done that. We’ve evaluated it. And it is equivalent to that—the operational availability of SSBNs that we provide today. Today’s numbers are acceptable to Strategic Command. We'll work with them in the future, but they look the same. REPRESENTATIVE MCINTYRE: And would you say in all candor that the delay in the Ohio Class replacement program is being done solely for budget reasons? ADMIRAL GREENERT: Predominantly budget reasons, but there is an advantage to this, and that is the design feature will be much more mature when we get to construction.46 Potential oversight questions for Congress include the following: 46 • What impact does the two-year deferral have on the Ohio replacement program’s estimated total research and development cost and its estimated total procurement cost? • How much risk was there in the program’s development schedule under the FY2012 budget, and how much mitigation of that risk is achieved by the twoyear deferral? • What would be the operational impact, particularly in terms of meeting requirements for at-sea strategic nuclear deterrent forces, of reducing the SSBN force to 10 boats during most of the 2030s? • What is the potential for restoring the FY2019 procurement date for the first Ohio replacement boat, and how quickly would a decision need to be made on this issue before the potential for restoring the FY2019 date would be lost? What would be the impact on Ohio replacement program funding requirements in FY2013 and within the FY2013-FY2017 FYDP of a decision to restore the FY2019 date? Source: Transcript of hearing. Congressional Research Service 16 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program A Design with 16 vs. 20 SLBM Tubes Another oversight issue for Congress concerns the plan to design the SSBN(X) with 16 SLBM tubes rather than 20—one of several decisions made to reduce the estimated average procurement cost of boats 2 through 12 in the program to $5.6 billion in FY2010 dollars.47 Some observers are concerned that designing the SSBN(X) with 16 tubes rather than 20 would create a risk that U.S. strategic nuclear forces might not have enough capability in the 2030s and beyond to fully perform their deterrent role. These observers note that to comply with the New Start Treaty limiting strategic nuclear weapons, DOD plans to operate in coming years a force of 14 Trident SSBNs, each with 20 operable SLBM tubes (four of the 24 tubes on each boat are to be rendered inoperable), for a total of 240 tubes, whereas the Navy in the SSBN(X)Ohio replacement program is planning a force of 12 SSBNs each with 16 tubes, for a total of 192 tubes, or 20% less than 240. These These observers also cite the uncertainties associated with projecting needs for strategic deterrent forces forces out to the year 2080, when the final SSBN(X) is scheduled to leave service. These observers have asked whether the plan to design the SSBN(X) with 16 tubes rather than 20 is fully supported within all parts of DOD, including U.S. Strategic Command (STRATCOM). In response, Navy and other DOD officials have stated that the decision to design the SSBN(X) with 16 tubes rather than 20 was carefully considered within DOD, and that they believe a boat with 16 tubes will give U.S. strategic nuclear forces enough capability to fully perform their deterrent role in the 2030s and beyond. At a March 1, 2011, hearing before the House Armed Services Committee, Admiral Gary Roughead, the then-Chief of Naval Operations, stated: 44 I’m very comfortable with where we're going with SSBN-X. The decision and the recommendation that I made with regard to the number of tubes—launch tubes are consistent with the new START treaty. They’re consistent with the missions that I see that ship having 47 At a March 30, 2011, hearing before the Strategic Forces subcommittee of the Senate Armed Services Committee, Admiral Kirkland Donald, Deputy Administrator for Naval Reactors and Director, Naval Nuclear Propulsion, National Nuclear Security Administration, when asked for examples cost efficiencies that are being pursued in his programs, stated: The—the Ohio replacement [program] has been one that we’ve obviously been focused on here for—for several years now. But in the name of the efficiencies, and one of the issues as we work through the Defense Department’s acquisition process, we were the first program through that new process that Dr. [Aston] Carter [the DOD acquisition executive] headed up. But we were challenged to—to drive the cost of that ship down, and as far as our part was concerned, one of the key decisions that was made that—that helped us in that regard was a decision to go from 20 missile tubes to 16 missile tubes, because what that allowed us to do was to down rate the—the propulsion power that was needed, so obviously, it’s a – it’s a small[er] the reactor that you would need. But what it also allowed us to do was to go back [to the use of existing components]. The size [of the ship] fell into the envelope where we could go back and use components that we had already designed for the Virginia class [attack submarines] and bring those into this design, not have to do it over again, but several of the mechanical components, to use those over again. And it enabled us to drive the cost of that propulsion plant down and rely on proven technology that’s—pumps and valves and things like that don’t change like electronics do. So we’re pretty comfortable putting that in ship that’ll be around ‘til 2080. But we were allowed to do that. (Source: Transcript of hearing.) Congressional Research Service 15 . 17 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program I’m very comfortable with where we're going with SSBN-X. The decision and the recommendation that I made with regard to the number of tubes—launch tubes are consistent with the new START treaty. They’re consistent with the missions that I see that ship having to perform. And even though it may be characterized as a cost cutting measure, I believe it sizes the ship for the missions it will perform.4548 At a March 2, 2011, hearing before the Strategic Forces subcommittee of the House Armed Services Committee, the following exchange occurred: REPRESENTATIVE TURNER: General Kehler, thank you so much for your continued thoughts and of course your leadership. One item that we had a discussion on was the triad, of looking to—of the Navy and the tube reductions of 20 to 16, as contained in other hearings on the Hill today. I would like your thoughts on the reduction of the tubes and what you see driving that, how you see it affecting our strategic posture and any other thoughts you have on that? AIR FORCE GENERAL C. ROBERT KEHLER, COMMANDER, U.S. STRATEGIC COMMAND Thank you, Mr. Chairman. Well, first of all, sir, let me say that the—in my mind anyway, the discussion of Trident and Ohio-class replacement is really a discussion in the context of the need to modernize the entire triad. And so, first of all, I think that it’s important for us to recognize that that is one piece, an important piece, but a piece of the decision process that we need to go through. Second, the issue of the number of tubes is not a simple black-and-white answer. So let me just comment here for a minute. First of all, the issue in my mind is the overall number of tubes we wind up with at the end, not so much as the number of tubes per submarine. Second, the issue is, of course, we have flexibility and options with how many warheads per missile per tube, so that’s another consideration that enters into this mixture. Another consideration that is important to me is the overall number of boats and the operational flexibility that we have with the overall number of boats, given that some number will need to be in maintenance, some number will need to be in training, et cetera. And so those and many other factors—to include a little bit of foresight here, in looking ahead to 20 years from now in antisubmarine warfare environment that the Navy will have to operate in, all of those bear on the ultimate sideways shape configuration of a follow-on to the Ohio. At this point, Mr. Chairman, I am not overly troubled by going to 16 tubes. As I look at this, given that we have that kind of flexibility that I just laid out; given that this is an element of the triad and given that we have some decision space here as we go forward to decide on the ultimate number of submarines, nothing troubles me operationally here to the extent that I would oppose a submarine with 16 tubes. 45 Source: Transcript of hearing. Congressional Research Service 16 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program I understand the reasons for wanting to have 20. I understand the arguments that were made ahead of me. But as I sit here today, given the totality of the discussion, I am—as I said, I am 48 Source: Transcript of hearing. Congressional Research Service 18 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program not overly troubled by 16. Now, I don’t know that the gavel has been pounded on the other side of the river yet with a final decision, but at this point, I am not overly troubled by 16.4649 At an April 5, 2011, hearing before the Strategic Forces subcommittee of the House Armed Services Committee, the following exchange occurred: REPRESENTATIVE LARSEN: General Benedict, we have had this discussion, not you and I, I am sorry. But the subcommittee has had a discussion in the past with regards to the Ohio-class replacement program. The new START, though, when it was negotiated, assumed a reduction from 24 missile tubes per hole to, I think, a maximum a maximum of 20. The current configuration [for the SSBN(X)], as I understand it, would move from 24 to 16. Can you discuss, for the subcommittee here, the Navy’s rationale for that? For moving from 24 to 16 as opposed to the max of 20? NAVY REAR ADMIRAL TERRY BENEDICT, DIRECTOR, STRATEGIC SYSTEMS PROGRAMS (SSP): Sir, as part—excuse me, as part of the work-up for the milestone A [review for the SSBN(X) program] with Dr. Carter in OSD, SSP supported the extensive analysis at both the OSD level as well as STRATCOM’s analysis. Throughout that process, we provided, from the SWS [strategic weapon system] capability, our perspective. Ultimately that was rolled up into both STRATCOM and OSD and senior Navy leadership and in previous testimony, the secretary of the Navy, the CNO, and General Chilton have all expressed their confidence that the mission of the future, given their perspectives, is they see the environment today can be met with 16. And so, as the acquisition and the SWS provider, we are prepared to support that decision by leadership, sir. REPRESENTATIVE LARSEN: Yes. And your analysis supports—did your analysis that fed into this, did you look at specific numbers then? REARD ADMIRAL BENEDICT: Sir, we looked at the ability of the system, again, SSP does not look at specific targets with... REPRESENTATIVE LARSEN: 46 Right. Yes, yes, yes. 49 Source: Transcript of hearing. Congressional Research Service 17 . 19 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Right. Yes, yes, yes. REAR ADMIRAL BENEDICT: Our input was the capability of the missile, the number of re-entry bodies and the throw weight that we can provide against those targets and based on that analysis, the leadership decision was 16, sir.4750 At an April 6, 2011, hearing before the Strategic Forces subcommittee of the Senate Armed Services Committee, the following exchange occurred: SENATOR SESSIONS: Admiral Benedict, according to recent press reports, the Navy rejected the recommendations of Strategic Command to design the next generation of ballistic missile submarines with 20 missile tubes instead of opting for only 16 per boat. What is the basis for the Navy’s decision of 16? And I'm sure cost is a factor. In what ways will that decision impact the overall nuclear force structure associated with the command? NAVY REAR ADMIRAL TERRY BENEDICT, DIRECTOR, STRATEGIC SYSTEMS PROGRAMS (SSP): Yes, sir. SSP supported the Navy analysis, STRATCOM’s analysis, as well as the OSD analysis, as we proceeded forward and towards the milestoneMilestone A decision [on the SSBN(X) program] that Dr. Carter conducted. Based on our input, which was the technical input as the—as the director of SSP, other factors were considered, as you stated. Cost was one of them. But as the secretary, as the CNO, and I think as General Kehler submitted in their testimony, that given the threats that we see today, given the mission that we see today, given the upload capability of the D-5, and given the environment as they saw today, all three of those leaders were comfortable with the decision to proceed forward with 16 tubes, sir. SENATOR SESSIONS: And is that represent your judgment? To what extent were you involved—were you involved in that? REAR ADMIRAL BENEDICT: Sir, we were involved from technical aspects in terms of the capability of the missile itself, what we can throw, our range, our capability. And based on what we understand the capability of the D-5 today, which will be the baseline missile for the Ohio Replacement Program, as the director of SSP I’m comfortable with that decision.48 47 4851 Section 242 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 112-81 of December 31, 2011) requires DOD to submit a report on the Ohio replacement program that includes, among other things, an assessment of various combinations of boat quantities and numbers of SLBM launch tubes per boat. The text of the section is as follows: 50 51 Source: Transcript of hearing. Source: Transcript of hearing. Congressional Research Service 18 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program 20 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program SEC. 242. REPORT AND COST ASSESSMENT OF OPTIONS FOR OHIO-CLASS REPLACEMENT BALLISTIC MISSILE SUBMARINE. (a) Report Required- Not later than 180 days after the date of the enactment of this Act, the Secretary of the Navy and the Commander of the United States Strategic Command shall jointly submit to the congressional defense committees a report on each of the options described in subsection (b) to replace the Ohio-class ballistic submarine program. The report shall include the following: (1) An assessment of the procurement cost and total life-cycle costs associated with each option. (2) An assessment of the ability for each option to meet— (A) the at-sea requirements of the Commander that are in place as of the date of the enactment of this Act; and (B) any expected changes in such requirements. (3) An assessment of the ability for each option to meet— (A) the nuclear employment and planning guidance in place as of the date of the enactment of this Act; and (B) any expected changes in such guidance. (4) A description of the postulated threat and strategic environment used to inform the selection of a final option and how each option provides flexibility for responding to changes in the threat and strategic environment. (b) Options Considered- The options described in this subsection to replace the Ohio-class ballistic submarine program are as follows: (1) A fleet of 12 submarines with 16 missile tubes each. (2) A fleet of 10 submarines with 20 missile tubes each. (3) A fleet of 10 submarines with 16 missile tubes each. (4) A fleet of eight submarines with 20 missile tubes each. (5) Any other options the Secretary and the Commander consider appropriate. (c) Form- The report required under subsection (a) shall be submitted in unclassified form, but may include a classified annex. Plan to Procure 12 Boats Rather Than 13 or 14 Another oversight issue for Congress concerns the plan to procure 12 SSBN(X)s rather than 13 or 14. Navy and other DOD officials have suggested that a force of 12 SSBN(X)s will be sufficient to replace the current force of 14 Ohio-class SSBNs because SSBN(X)s are to be equipped with life-of-the-ship nuclear fuel cores and consequently will not need a mid-life nuclear refueling. The Ohio-class boats, in contrast, require a mid-life refueling, and during the middle years of the Congressional Research Service 21 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Ohio class life cycle, two Ohio-class boats are unavailable for service at any given point because they are in the midst of lengthy mid-life refueling overhauls, leaving 12 Ohio-class boats available to support the needed number of boats continuously at sea on deterrent patrols. Skeptics might argue that although a life-of-the-ship core will eliminate the need for a mid-life refueling for the SSBN(X)s, the Navy has not stated that it has been able to eliminate the need for a mid-life overhaul for the SSBN(X)s to repair and refurbish other parts of the boats, and that consequently, during the middle years of the SSBN(X) class life cycle, one or two SSBN(X)s might be unavailable for service at any given point because they are in the midst of lengthy midlife non-refueling overhauls. If so, this would leave 10 or 11 SSBN(X)s available for deterrent patrols—potentially not enough to support the needed number of boats that are to be continuously at sea on deterrent patrols. As a consequence, skeptics might argue, policymakers might face a choice of either procuring 13 or 14 SSBN(X)s rather than 12, or reducing requirements for at-sea deterrent patrols during the middle years of the SSBN(X) class life cycle. Likelihood That Navy Will Reach $4.9 Billion Target Cost Another oversight issue for Congress is the likelihood that the Navy will be able to achieve DOD’s goal of reducing the average unit procurement cost of boats 2-12 in the program to $4.9 billion each in FY2010 dollars. As mentioned earlier, as of early 2011, the Navy estimated that its cost-reduction efforts had reduced the average unit procurement cost of boats 2-12 to $5.6 billion each in FY2010 dollars, leaving another $700 million or so in cost reduction to reach the $4.9 billion target cost. Measures that the Navy has taken to reduce the average unit procurement cost of boats 2-12 to about $5.6 billion include, among other things, reducing the number of SLBM launch tubes from 20 to 16, and making the launch tubes no larger in diameter than those on the Ohio-class design. 4952 The Navy is examining potential further measures to bring the cost of boats 2-12 closer to the $4.9 billion target cost. Potential oversight questions include the following: • How did DOD settle on the figure of $4.9 billion in FY2010 dollars as the target average unit procurement cost for boats 2-12 in the program? On what analysis was the selection of this figure based? • How difficult will it be for the Navy to reach this target cost? What options is the Navy examining to achieve the additional $700 million or so in unit procurement cost savings needed to reach it? 49 The Navy had examined the option of equipping the SSBN(X) with tubes greater in diameter than those on the Ohioclass design, so as to support an option of arming the boats many years from now with a new SLBM that is larger in diameter than the D-5 SLBM. Congressional Research Service 19 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program • Would a boat costing $4.9 billion have sufficient capability to perform its intended missions? • What, if anything, does DOD plan to do if the Navy is unable to achieve the $4.9 billion target cost figure? If $4.9 billion is the target figure, is there a corresponding “ceiling” figure higher than $4.9 billion, above which DOD would not permit the SSBN(X)Ohio replacement program to proceed? If no such figure exists, should DOD establish one? should DOD establish one? 52 The Navy had examined the option of equipping the SSBN(X) with tubes greater in diameter than those on the Ohioclass design, so as to support an option of arming the boats many years from now with a new SLBM that is larger in diameter than the D-5 SLBM. Congressional Research Service 22 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Accuracy of Navy’s Estimated Unit Procurement Cost Another oversight issue for Congress concerns the accuracy of the Navy’s estimate of the procurement cost of each SSBN(X). The accuracy of the Navy’s estimate is a key consideration in assessing the potential affordability of the SSBN(X)Ohio replacement program, including its potential impact on the Navy’s ability to procure other kinds of ships during the years of SSBN(X) procurement. Some of the Navy’s ship designs in recent years, such as the Gerald R. Ford (CVN78) class aircraft carrier,53 the San Antonio (LPD-17) class amphibious ship50ship54 and the Littoral Combat Ship (LCS),5155 have proven to be substantially more expensive to build than the Navy originally estimated. The Congressional Budget Office (CBO) in recent years has issued procurement cost estimates for certain Navy ships that are higher than the Navy’s estimates for those ships. originally estimated. The accuracy of the Navy’s estimate can be assessed in part by examining known procurement costs for other recent Navy submarines—including Virginia (SSN-774) class attack submarines (which are currently being procured), Seawolf (SSN-21) class attack submarines (which were procured prior to the Virginia class), and Ohio (SSBN-726) class ballistic missile submarines— and then adjusting these costs for the SSBN(X)Ohio replacement program so as to account for factors such as as differences in ship displacement and design features, changes over time in submarine technologies (which can either increase or reduce a ship’s procurement cost, depending on the exact technologies in question), advances in design for producibility (i.e., design features that are intended to make ships easier to build), advances in shipyard production processes (such as modular construction), and changes in submarine production economies of scale (i.e., changes in the total number of attack submarines and ballistic missile submarines under construction at any one time). The Navy’s estimated unit procurement cost for the program at any given point will reflect assumptions inon, among other things, which shipyard or shipyards will build the boats, and how much Virginia-class construction will be taking place in the years when SSBN(X)s are being built. Changing the Navy’s assumption about which shipyard or shipyards will build SSBN(X)s could reduce or increase the Navy’s estimated unit procurement cost for the boats. If shipbuilding affordability pressures result in Virginia-class boats being removed from the 30-year shipbuilding plan during the years of SSBN(X) procurement, the resulting reduction in submarine production economies of scale could make SSBN(X)s more expensive to build than the Navy estimates. 50 A June 2011 Congressional Budget Office (CBO) report on the cost of the Navy’s shipbuilding programs stated (with cost figures expressed in constant FY2011 dollars): The design, cost, and capabilities of the SSBN(X), the submarine slated to replace the Ohio class, are among the most significant uncertainties in the Navy’s and CBO’s analyses of future shipbuilding. The Navy’s [FY]2007 and [FY]2008 shipbuilding plans included an assumption that the first SSBN(X) would cost $4.6 billion (in [FY]2011 dollars) and that subsequent ships in the class would cost about $3.5 billion apiece. The [FY]2011 plan, in contrast, estimated the costs of the SSBN(X) class at an average of $7.4 billion. That figure 53 For more on the CVN-78 program, see CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress, by Ronald O'Rourke. 54 For more on the LPD-17 program, see CRS Report RL34476, Navy LPD-17 Amphibious Ship Procurement: Background, Issues, and Options for Congress, by Ronald O'Rourke. 51 55 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background, Issues, and Options for Congress, by Ronald O'Rourke. Congressional Research Service 20 . 23 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Program Affordability and Impact on Other Navy Shipbuilding Programs Another oversight issue for Congress concerns the prospective affordability of the SSBN(X) program and its potential impact on other Navy shipbuilding programs. Even with the Navy’s current effort to reduce the estimated unit procurement cost of the SSBN(X) toward DOD’s target figure, some observers are concerned that the SSBN(X) program could significantly compound a challenge the Navy faces concerning the affordability of its long-term shipbuilding program. These observers are concerned that procuring 12 SSBN(X)s during the 15-year period FY2019FY2033, as called for in Navy plans, could lead to reductions in procurement rates for other types of Navy ships during those years.52 The Navy’s February 2010 report on its 30-year (FY2011FY2030) shipbuilding plan states: Recapitalizing the SSBN force will impact the Navy in the mid-term as significant resources are allocated to the SSBN(X) recapitalization program ... these ships require significant resource commitment and they will impact the Navy’s ability to procure other shipbuilding requirements during the period when they are being procured.... The SSBN(X) procurements will be concurrent with wholesale end-of-service-life retirements of SSN 688 submarines, CG 47 class guided missile cruisers, DDG 51 class guided missile destroyers, and LSD 41/49 class dock landing ships. While the SSBN(X) is being procured, the Navy will be limited in its ability to procure other ship classes. This slowdown in procurement will occur when the Navy needs to be procuring at least 10 ships per year to maintain its force level against the anticipated ship retirements from the 1980s and 1990s.53 The report also states: Because of the high expected costs for these important national assets, yearly shipbuilding expenditures during the mid-term planning period [FY2021-FY2030] will average about $17.9B (FY2010$) [$17.9 billion in constant FY2010 dollars] per year, or about $2B more than the steady-state 30-year average. Even at this elevated funding level, however, the total number of ships built per year will inevitably fall because of the percentage of the shipbuilding account which must be allocated for the procurement of the SSBN. In the farterm planning period, average shipbuilding expenditures fall back to a more sustainable level of about $15.3B (FY2010$) average per year. Moreover, after the production run of SSBN(X)s comes to an end in FY 2033, the average number of ships built per year begins to rebound.54 The Navy’s FY2011 30-year shipbuilding plan includes a total of 276 ships and states that the 12 SSBN(X)s are to be funded within the Navy’s shipbuilding budget.55 An earlier draft of the 30year plan that was reported in December 2009 suggested that funding the 12 SSBN(X)s within 52 See, for example, John M. Donnelly, “Cost Of Nuclear Subs Could Sink Navy Budget,” CQ Today, March 2, 2010. 53 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, pp. 24-25. 54 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 5. 55 The report states that “funding for the SSBN(X) will be included in the SCN core budget.” (U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 4.) SCN stands for the Shipbuilding and Conversion, Navy appropriation account—the Navy’s shipbuilding budget. Congressional Research Service 21 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program the Navy’s shipbuilding budget without an offsetting increase to the shipbuilding budget would reduce the number of ships in the 30-year plan from 278 to 222—a reduction of 56 ships. The 56 eliminated ships included 19 destroyers, 15 Littoral Combat Ships (LCSs), four SSNs, three amphibious ships, and 15 auxiliary ships.56 In addition to making further changes in the design of the SSBN(X), options for reducing the cost of the SSBN(X) program and the program’s potential impact on the Navy’s ability to procure other kinds of ships in desired numbershighlights the great expense of replacing current ballistic missile submarines and the effect that effort could have on other shipbuilding programs or programs beyond shipbuilding.... Over the past year, the Navy has sought to refine its SSBN(X) design, particularly to reduce the cost of the ships. The Navy’s cost estimate in the [FY]2011 plan was based on a submarine similar in size to the Ohio class and on the cost to build Ohio class submarines in today’s industry conditions and with today’s technology. The Navy states that it was able to reduce the estimated cost of the SSBN(X) between [the FY]2011 [plan] and [the FY]2012 [plan] by making the following changes: • Using a less expensive basic design (with greater specificity, eliminating some costs in last year’s estimate that were associated with uncertainty); • Reducing the number of missile tubes from 20 to 16; • Reducing the diameter of the missile tubes from 97 inches to 87 inches; • Reducing the capability of the torpedo room, the capability of various arrays, and the sail mast; and • Increasing the use of Virginia class components. Despite those changes, the Navy’s estimate of the cost of the lead SSBN(X) increased between [the FY]2011 [plan] and [the FY]2012 [plan], from $9.0 billion to $11.6 billion. However, the Navy’s estimate of the average cost of follow-on ships decreased from $6.9 billion to $5.8 billion, and the Navy has stated an objective of reducing that cost to $5.0 billion. All told, the Navy estimates that building 12 of the submarines would cost $75 billion, or an average of $6.1 billion each. In comparison, CBO estimates that the lead SSBN(X) will cost about $13.3 billion on the basis of its scheduled purchase in [FY]2019. Estimating the cost of the first submarine of a class is particularly difficult because it is not clear how much the Navy will need to spend on nonrecurring engineering and detail design. The Navy spent about $2 billion on those items for the lead Virginia class attack submarine. The historical track record for the lead ship of new classes of submarines in the 1970s and 1980s indicates that there is little difference on a per-ton basis between a lead attack submarine (SSN) and a lead SSBN.... In addition, CBO assumed that the cost of nonrecurring items is proportional to the weight of submarines. Therefore, CBO estimated that nonrecurring items would cost about $5 billion for the lead SSBN(X), which will be approximately the size of an Ohio class submarine and thus about 2½ times the size of a Virginia class submarine. The increase in the Navy’s estimate for the lead SSBN(X) reflects the fact that the service now also estimates that nonrecurring costs will be about $5 billion. Under the [FY]2011 plan, the Navy appeared to assume that those costs would be about $2 billion. Overall, 12 SSBN(X)s would cost a total of about $86 billion in CBO’s estimation, or an average of $7.2 billion each. That average includes the $13.3 billion estimated cost of the lead ship and a $6.5 billion average estimated cost for the 2nd through 12th ships. Research and development would cost another $10 billion to $15 billion, for a total program cost of $96 billion to $101 billion. CBO’s estimate under the [FY]2011 plan was an average of $8.3 billion per submarine. The decline in CBO’s estimate stems from two factors: the changes in the Navy’s design and the narrowing of the projected gap between inflation in the economy overall and inflation in the shipbuilding industry. The change in design accounts for about 60 Congressional Research Service 24 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program percent of the reduction in cost, and the change in the projected inflation differential accounts for the remainder.56 Program Affordability and Impact on Other Navy Shipbuilding Programs Another oversight issue for Congress concerns the prospective affordability of the Ohio replacement program and its potential impact on funding available for other Navy shipbuilding programs. Even with the Navy’s current effort to reduce the estimated unit procurement cost of the SSBN(X) toward DOD’s target figure, observers are concerned that the Ohio replacement program could crowd out funding for other Navy shipbuilding programs in the 2020s and early 2030s. The Navy’s March 2012 report on its FY2013 30-year (FY2013-FY2042) shipbuilding plan acknowledges the issue, stating: This high cost for replacing the nation’s secure, second-strike nuclear deterrent force will have a disproportionate impact on DoN [Department of the Navy] shipbuilding plans and associated costs throughout the mid-term planning period [FY2023-FY2032] and into the early years of the far-term planning period [FY2033-FY2042].... Obviously, spending $5-6B [billion] per year for a single ship over a 10 to 12-year period will strain the DoN’s yearly shipbuilding accounts, since the Department must continue to build other ships through this period to maintain the overall battle force inventory at about 300 ships.57 A March 2012 GAO report assessing major DOD weapon acquisition programs states: Affordability has been an early focus of the [Ohio Replacement (OR)] program. Due to its high cost, Navy officials have stated the OR program could stress Navy shipbuilding budgets in the 2020 to 2030 time frame. Program officials stated that they are trying to reduce the average procurement unit cost from an estimated $5.6 billion to $4.9 billion (in fiscal year 2010 dollars). The program is considering procuring OR [boats] as part of a block buy with the Virginia-class [attack] submarine to reduce procurement costs by an estimated 13 percent, and is lining up its production schedule to match that program in case this option is pursued. The Navy also decided to use 16 87-inch diameter tubes per submarine, which, while fewer than the Ohio-class, is expected to reduce costs while meeting the anticipated future strategic requirement based on arms reduction trends. According to the [OR] program [office], a four-way competition is ongoing to develop prototype tubes and efficient manufacturing processes for outfitting these tubes into the hull, including the use of a “quad pack” configuration that could reduce cost and construction time.... [OR] Program officials said they plan to have the three-dimensional design [for the boat] complete prior to starting construction on the lead ship to minimize rework, delays, and the potential for cost growth.58 56 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2012 Shipbuilding Plan, June 2011, pp. 14, 1617. 57 Department of the Navy, Annual Report to Congress on Long-Range Plan for Construction of Naval Vessels for FY2013, April 2012, pp. 15-16. 58 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapons Programs, GAO-12400SP, March 2012, p. 152. Congressional Research Service 25 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program In addition to making further changes and refinements in the design of the SSBN(X), options for reducing the cost of the Ohio replacement program and the program’s potential impact on funding available for other Navy shipbuilding programs include the following: • reducing the planned number of SSBN(X)s; • altering the schedule for procuring the SSBN(X)s so as to create additional opportunities for using incremental funding for procuring the ships; and • funding the procurement of SSBN(X)’s outside the Navy’s shipbuilding budget. Each of these options is discussed below. Reducing the Planned Number of SSBN(X)s Some observers over the years have advocated or presented options for an SSBN force of fewer than 12 SSBNs. The Congressional Budget Office (CBO)CBO, for example, has at times in the past presented options for reducing the SSBN force to 10 boats as a cost-reduction measure. 5759 A June 2010 report by a group known as the Sustainable Defense Task Force recommends reducing the SSBN force to seven boats;58 a 60 a September 2010 report from the Cato Institute recommends reducing the SSBN force to six boats.5961 Views on whether a force of fewer than 12 SSBN(X)s would be adequate could depend on, among other things, assessments of strategic nuclear threats to the United States and the role of SSBNs in deterring such threats as a part of overall U.S. strategic nuclear forces, as influenced by the terms of strategic nuclear arms control agreements.6062 Reducing the number of SSBNs below 12 could also raise a question as to whether the force should continue to be homeported at both Bangor, WA, and Kings Bay, GA, or consolidated at a single location. U.S. strategic nuclear deterrence plans require a certain number of strategic nuclear warheads to be available for use on a day-to-day basis. After taking into account warheads on the other two legs of the strategic nuclear triad, as well as the number of warheads on an SSBN’s SLBMs, this translates into a requirement for a certain number of SSBNs to be on station (i.e., within range of expected targets) in Pacific and Atlantic waters at any given moment. The SSBN force is sized to 56 See the tables of the 222- and 278-ship scenarios published in Inside the Navy on December 7, 2009, as well as Christopher J. Castelli, “Navy Confronts $80 Billion Cost Of New Ballistic Missile Submarines,” Inside the Pentagon, December 3, 2009. 57support this requirement. Given the time needed for at-sea training operations, restocking SSBNs with food and other consumables, performing maintenance and repair work on the SSBNs, and transiting to and from deterrent patrol areas, only a fraction of the SSBN force can be on patrol at any given moment. The Navy’s position is that the requirement for having a certain number of SSBNs on patrol at any given moment translates into a need for a force of 14 Ohio-class boats, and that this requirement can be met in the future by a force of 12 SSBN(X)s. 59 See, for example, Congressional Budget Office, Rethinking the Trident Force, July 1993, 78 pp.; and Congressional Budget Office, Budget Options, March 2000, p. 62. 5860 Debt, Deficits, and Defense, A Way Forward[:] Report of the Sustainable Defense Task Force, June 11, 2010, pp. 19-20. 59 61 Benjamin H. Friedman and Christopher Preble, Budgetary Savings from Military Restraint, Washington, Cato Institute, September 23, 2010 (Policy Analysis No. 667), pp. 8. 60 62 For further discussion, see CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf. Congressional Research Service 22 . 26 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program support this requirement. Given the time needed for at-sea training operations, restocking SSBNs with food and other consumables, performing maintenance and repair work on the SSBNs, and transiting to and from deterrent patrol areas, only a fraction of the SSBN force can be on patrol at any given moment. The Navy’s position is that the requirement for having a certain number of SSBNs on patrol at any given moment translates into a need for a force of 14 Ohio-class boats, and that this requirement can be met in the future by a force of 12 SSBN(X)s. Altering the Schedule for Procuring SSBN(X)s Altering Procurement Schedule to Make More Use of Incremental Funding Another option for managing the potential impact of the SSBN(X)Ohio replacement program on other Navy Navy shipbuilding programs would be to stretch out the schedule for procuring SSBN(X)s and make make greater use of split funding (i.e., two-year incremental funding) in procuring them.61 This option 63 This option would not reduce the total procurement cost of the SSBN(X)Ohio replacement program—to the contrary, it might increase the program’s total procurement cost somewhat by reducing production learning curve benefits in the SSBN(X)Ohio replacement program.6264 This option could, however, reduce the impact of the SSBN(X) Ohio replacement program on the amount of funding available for the procurement of other Navy ships in certain individual years. This might reduce the amount of disruption that the SSBN(X)Ohio replacement program causes to other shipbuilding programs in those years, which in turn might avoid certain disruption-induced cost increases for those other programs. The annual funding requirements for the SSBN(X) the Ohio replacement program might be further spread out by funding some of the SSBN(X)s with threeorthree- or four-year incremental funding.6365 Table 4 shows the Navy’s currently planned schedule for procuring 12 SSBN(X)s and a notional alternative schedule that would start two years earlier and end two years later than the Navy’s currently planned schedule. Although the initial ship in the alternative schedule would be procured in FY2017, it wouldFY2019, it could be executed as it if were funded in FY2019FY2021. Subsequent ships in the the alternative schedule that are funded earlier than they would be under the Navy’s currently planned planned schedule could also be executed as if they were funded in the year called for under the Navy’s schedule. Congress in the past has funded the procurement of ships whose construction was was executed as if they had been procured in later fiscal years.6466 The ability to stretch the end of the the procurement schedule by two years, to FY2035, could depend on the Navy’s ability to carefully carefully husband the use of the nuclear fuel cores on the last two Ohio-class SSBNs, so as to extend the service lives of these two ships by one or two years. Alternatively, Congress could grant the Navy the authority to begin construction on the 11th boat a year before its nominal year of procurement, and the 12th boat two years prior to its nominal year of procurement. 61 63 Under split funding, a boat’s procurement cost is divided into two parts, or increments. The first increment would be provided in the fiscal year that the boat is procured, and the second would be provided the following fiscal year. 62 64 Procuring one SSBN(X) every two years rather than at the Navy’s planned rate of one per year could result in a loss of learning at the shipyard in moving from production of one SSBN to the next. 6365 The Navy, with congressional support, currently uses split funding to procure large-deck amphibious assault ships (i.e., LHAs). The Navy currently is permitted by Congress to use four-year incremental funding for procuring the first three Ford (CVN-78) class carriers (i.e., CVN-78, CVN-79, and CVN-80); the authority was granted in Section §121 of the the FY2007 defense authorization act [H.R. 5122/P.L. 109-364 of October 17, 2006]). 6466 Congress funded the procurement of two aircraft carriers (CVNs 72 and 73) in FY1983, and another two (CVNs 74 and 75) in FY1988. Although CVN-73 was funded in FY1983, it was built on a schedule consistent with a carrier funded in FY1985; although CVN-75 was funded in FY1988, it was built on a schedule consistent with a carrier funded in FY1990 or FY1991. Congressional Research Service 23 . 27 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Table 4. Navy SSBN(X) Procurement Schedule and a Notional Alternative Schedule Fiscal year Fiscal year 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 Total Navy’s Schedule Boat might be particularly suitable for 2-, 3-, or 4-year incremental funding 2017 Notional 1 X 1 X 1 1 1 1 1 1 1 1 1 1 X X X 12 Notional alternative schedule Boat might be particularly suitable for 2-, 3-, or 4-year incremental funding 1 X 1 X 1 X 1 X 2018 2019 1 X 2020 2021 2022 1 X 2023 2024 1 2025 1 1 2026 1 1 2027 1 1 2028 1 1 2029 1 1 X 2030 1 2031 1 X 1 X 2032 1 X 2033 1 X 1 X 1 X 2034 2035 Total 12 121 1 1 1 1 X 1 X 1 X 1 12 X Source: Navy’s current plan is taken from U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010the Navy’s Fy2013 budget submission. Potential alternative plan prepared by CRS. Notes: Notional alternative schedule could depend on Navy’s ability to carefully husband the use of the nuclear fuel cores on the last two Ohio-class SSBNs, so as to extend the service lives of these two ships by one or two years. Alternatively, Congress could grant the Navy the authority to begin construction on the 11th boat a year before its nominal year of procurement, and the 12th boat two years prior to its nominal year of procurement. Under Navy’s schedule, the boat to be procured un FY2031in FY2033 might be particularly suitable for 4-year incremental funding, and boat to be procured in FY2032 might be particularly suitable for 3- or 4-year incremental funding. FY2034 might be particularly suitable for 3- or 4-year incremental funding. A December 19, 2011, press report states: The Office of Management and Budget’s Nov. 29[, 2011,] passback memorandum to the Defense Department [regarding the FY2013 DOD budget] warns that the effort to build replacements for aging Ohio-class submarines is not exempt from rules requiring each new vessel to be fully funded in a single year.... Spreading the cost of a big-ticket ship over more than one year—an approach referred to as “incremental funding”—is only allowed when a program meets three criteria, OMB writes.... “OMB does not anticipate that the OHIO Replacement program will meet these criteria,” the passback memo states.67 67 Christopher J. Castelli, “White House Opposes Incremental Funding For Multibillion-Dollar Sub,” Inside the Navy, December 19, 2011. Congressional Research Service 28 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Procuring SSBN(X)s Outside Navy’s Shipbuilding Budget Some observers have suggested funding the procurement of SSBN(X)s outside the Navy’s shipbuilding budget, so as to preserve Navy shipbuilding funds for other Navy shipbuilding programs. Among those who have raised this idea iswas Admiral Gary Roughead, the Chief of Naval Naval Operations (CNO).65 until September 2011.68 There would be some precedent for such an arrangement: 65 See, for example, Jason Sherman, “Roughead Wants SSBN(X) Program Funding Outside Shipbuilding Budget,” Inside the Navy, February 14, 2011. Congressional Research Service 24 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program arrangement: • DOD sealift ships and Navy auxiliary ships are funded in the National Defense Sealift Fund (NDSF), a part of DOD’s budget that is outside the Navy’s budget (Shipbuilding and Conversion, Navy (SCN) appropriation account, and also outside the procurement title of the DOD appropriations act). • Most spending for ballistic missile defense (BMD) programs (including procurement-like activities) is funded through the Defense-Wide research and development account rather than through the research and development and procurement accounts of the individual military services. A rationale for funding DOD sealift ships in the NDSF is that DOD sealift ships perform a transportation mission that primarily benefits services other than the Navy, and therefore should not be forced to compete for funding in a Navy budget account that funds the procurement of ships central to the Navy’s own missions. A rationale for funding BMD programs together in the Defense-Wide research and development account is that this makes potential tradeoffs in spending among various BMD programs more visible and thereby helps to optimize the use of BMD funding. As a reference tool for better understanding DOD spending, DOD includes in its annual budget submission a presentation of the DOD budget reorganized into 11 program areas, of which one is strategic forces. The FY2011 budget submission, for example, shows that the strategic forces program area received about $12.6 billion in funding in FY2010, and that about $11.1 billion is requested for the program area for FY2011.6669 Supporters of funding the procurement of SSBN(X)s outside the Navy’s shipbuilding budget might argue that this could help protect funding for other Navy shipbuilding programs. They could also argue that creating a new budget account for strategic nuclear forces of all kinds could help DOD better view potential tradeoffs in spending for various strategic nuclear forces programs and thereby help DOD better optimize the use of strategic forces funding. Skeptics of funding the procurement of SSBN(X)s outside the Navy’s shipbuilding budget could argue that it might do little to protect funding for other Navy shipbuilding programs, because if DOD were to move the SSBN(X)s out of the Navy’s shipbuilding budget, DOD might also remove the funding that was there for the SSBN(X)s. They might also argue that shifting SSBN(X)s out of the Navy’s shipbuilding budget would make it harder to track and maintain oversight over Navy shipbuilding activities, and that creating a new budget account for strategic nuclear forces of all kinds could endanger the SSBN(X) program by making it more visible to those who might support reduced spending on nuclear-weapon-related programs. A March 11, 2010, press report stated: “The massive cost of replacing the Navy’s nuclear ballistic missile submarines will be shouldered in the coming years by diverting funds from other naval and Pentagon programs and perhaps by boosting the defense budget, but the program should not get its own special funding stream, according to Deputy Defense Secretary William Lynn.”67 66 Department of Defense, National Defense Budget Estimates For FY 2011, March 2010, Table 6-4, “Department of Defense TOA by Program,” page 79. See also Table 6-5 on page 80, which presents the same data in constant FY2011 dollars. The other 10 program areas in addition to strategic forces are general purpose forces; C3, intelligence and space; mobility forces; guard and reserve forces; research and development; central supply and management; training, medical and other; administration and associated; support of other nations; and special operations forces. (A 12th category—undistributed—shows relatively small amounts of funding.) 67 Christopher J. Castelli, “Lynn: Navy, DOD To Shoulder SSBN(X) Cost Without Separate Fund,” Inside the Pentagon, March 11, 2010. Congressional Research Service 25 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program 68 See, for example, Jason Sherman, “Roughead Wants SSBN(X) Program Funding Outside Shipbuilding Budget,” Inside the Navy, February 14, 2011. 69 Department of Defense, National Defense Budget Estimates For FY 2011, March 2010, Table 6-4, “Department of Defense TOA by Program,” page 79. See also Table 6-5 on page 80, which presents the same data in constant FY2011 dollars. The other 10 program areas in addition to strategic forces are general purpose forces; C3, intelligence and space; mobility forces; guard and reserve forces; research and development; central supply and management; training, medical and other; administration and associated; support of other nations; and special operations forces. (A 12th category—undistributed—shows relatively small amounts of funding.) Congressional Research Service 29 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program SSBN(X)s out of the Navy’s shipbuilding budget would make it harder to track and maintain oversight over Navy shipbuilding activities, and that creating a new budget account for strategic nuclear forces of all kinds could endanger the Ohio replacement program by making it more visible to those who might support reduced spending on nuclear-weapon-related programs. A March 11, 2010, press report stated: “The massive cost of replacing the Navy’s nuclear ballistic missile submarines will be shouldered in the coming years by diverting funds from other naval and Pentagon programs and perhaps by boosting the defense budget, but the program should not get its own special funding stream, according to Deputy Defense Secretary William Lynn.”70 A March 28, 2011, press report stated that SSBN(X)s will be funded within the shipbuilding account, not in a separate account as the sea service’s top admiral has advocated, according to Pentagon acquisition chief Ashton Carter. “It’s been in the shipbuilding account and our plan is it’s going to stay in the shipbuilding account,” Carter told Inside the Pentagon March 21 in a brief interview. “We just have to make it so that it is digestible for the Navy in the context of other shipbuilding needs. And we want the same things they want. We can manage through that path for decades.”6871 At an April 13, 2011, hearing on DOD acquisition before the Defense subcommittee of the House Appropriations Committee, the following exchange took place: REPRESNTATIVE CRENSHAW: Dr. Carter, I want to ask about Abrams tanks, kind of the modification of the start and stop. But – but real quick, we – we talked about the ballistic missiles submarines and was encouraged to hear that we’ve got a handle on the cost. We spent a lot of money on the development. I think we start construction in 2019. But even – even if we – you end up with a boat that costs $5 billion and we have 12 of those, that’s $60 billion. And we talked about the difficult choices that’s going to present in terms of surface ships, I just want to pose the question, if – is it under consideration to consider those submarines like a national asset? For instance, we – we fund the ballistic missile defense outside of the budget of the services because it’s truly a national asset. And I wondered, it’s a lot of money. And – and it’s – those – those submarines are one-third of our nuclear triad. Is consideration being given to consider those being funded as a national asset outside the ship-building program which would take away some of the difficult choice in terms of the service ships versus the submarines? ASHTON CARTER, UNDER SCRETARY OF DEFENSE FOR ACQUISITON, TECHNOLOLGY, AND LOGISTICS: The – the best I can do is cite something that Secretary Gates said which is that he had considered that, then was not attracted to that idea. I’m paraphrasing, but I think their basic reason was, “Look, the money is going to show up somewhere anyway. And we’re not going to hide $60 billion by re-labeling. So, let’s keep it in a way we’ve – we’ve done it.” And I think it was the gist of the secretary’s response. So – so, Secretary Gates had considered it and was not attracted to the idea. Although he – he thoroughly recognizes the premise of your question which is there’s a lot of money. And as a practical matter it will compete with those things in the defense budget. And that’s one of the reasons why we’ve got to get the cost down.69 Detailed Design/Nonrecurring Engineering (DD/NRE) Costs Another oversight issue for Congress concerns where in the Navy’s budget the detailed design/nonrecurring engineering (DD/NRE) cost of the SSBN(X) program should be funded. 68 70 Christopher J. Castelli, “Lynn: Navy, DOD To Shoulder SSBN(X) Cost Without Separate Fund,” Inside the Pentagon, March 11, 2010. 71 Christopher J. Castelli, “Carter: Multibillion-Dollar Nuclear Subs Will Stay In Shipbuilding Account,” Inside the Navy, March 28, 2011. 69 Source: Transcript of hearing. Congressional Research Service 26 . 30 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Traditionally, the DD/NRE cost for a new class of ships is attached to the procurement cost of the lead ship in the class, and is therefore funded through the Navy’s shipbuilding procurement account. That practice has been followed in the SSBN(X) program. At an April 28, 2011, briefing for CRS and CBO on the SSBN(X) program, however, CRS and CBO asked why the amount of procurement funding programmed for the SSBN(X) program in FY2015 changed from $954.6 million in the FY2011 budget submission to $736.0 million in the FY2012 budget submission—a decrease of roughly $200 million. In response, Navy officials explained that, to meet an OSD desire to smooth out the research and development funding profile for the SSBN(X) program— something that OSD believes will help reduce execution risk in the program—the Navy, with OSD permission, transferred roughly $200 million in FY2015 SSBN(X) DD/NRE costs from the Navy’s shipbuilding procurement account to the Navy’s research and development account. This, the Navy explained, is the main reason why the amount of procurement funding programmed for the SSBN(X) program in FY2015 changed from $954.6 million in the FY2011 budget submission to $736.0 million in the FY2012 budget submission. Although the practice of attaching the DD/NRE cost of a new class of ships to the procurement cost of the lead ship in the class is traditional for Navy shipbuilding programs, it is not followed in other areas of defense procurement. The practice, though traditional for Navy shipbuilding programs, can make it more difficult to understand the relationship between the estimated procurement cost of the lead ship in the program and the estimated procurement costs of the second and subsequent ships in the program, particularly since the DD/NRE component of the lead ship’s procurement cost can be quite significant and is not often broken out in DOD budget presentations. Potential oversight questions for Congress include the following: • To retain consistency in budgeting practices between the SSBN(X) program and other Navy shipbuilding programs, should the $200 million or so in DD/NRE costs be transferred back to the Navy’s procurement account? • Conversely, if it is acceptable to transfer $200 million or so in SSBN(X) DD/NRE costs from the procurement account to the research and development account, then should all SSBN(X) DD/NRE costs be transferred to the research and development account, so as to keep the program’s DD/NRE costs all in one place, and make the procurement cost of the lead ship more easily comparable to the procurement costs of the second and subsequent ships in the program? And if this were done for the SSBN(X) program, then should Navy shipbuilding in general be made more similar to other areas of defense procurement in terms of budgeting practices by having DD/NRE costs in the future be regularly funded through the research and development account, rather than attached to the procurement cost of lead ships? Construction Shipyard(s) Building SSBN(X)s Another potential issue for Congress regarding the SSBN(X) program is which shipyard or And I think it was the gist of the secretary’s response. So – so, Secretary Gates had considered it and was not attracted to the idea. Although he – he thoroughly recognizes the premise of your question which is there’s a lot of money. And as a practical matter it will compete with those things in the defense budget. And that’s one of the reasons why we’ve got to get the cost down.72 An August 1, 2011, press report stated: [Admiral Jonathan Greenert, who became the Chief of Naval Operations in September 2011, told] Sen. Jack Reed (D-R.I.) discussions are still underway in the Pentagon to have the defense-wide budget share with the Navy some of the costs of the Ohio-class SSBN(X) nextgeneration ballistic missile submarine, which is projected to dominate the Navy’s shipbuilding budget starting at the end of this decade. “If confirmed, I intend to try to continue those discussions,” Greenert [said] during his confirmation hearing. “In the [2020s], we have a phenomenon, an unfortunate one, where many of the ships built in the [1980s] will now come due for retirement. That’s right when the Ohio replacement comes in. So we’ll work very hard to make sure we got the requirements right. We’ll work very hard with the acquisition community to drive that cost down but we may even so need some assistance, I believe, in the shipbuilding budget if we’re going to meet our goals.”73 Construction Shipyard(s) Another potential issue for Congress regarding the Ohio replacement program is which shipyard or shipyards would build SSBN(X)s. Two U.S. shipyards are capable of building nuclear-powered submarines—General Dynamics’ Electric Boat Division (GD/EB) of Groton, CT, and Quonset Point, RI, and Newport News Shipbuilding (NNS), of Newport News, VA, which forms part of Huntington Ingalls Industries (HII). (HII was previously owned by Northrop Grumman, during which time it was known as Northrop Grumman Shipbuilding.) GD/EB’s primary business is Congressional Research Service 27 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program GD/EB’s primary business is building nuclear-powered submarines; it can also perform submarine overhaul work. NNS’s primary lines of business are building nuclear-powered aircraft carriers, building nuclear-powered submarines, and performing overhaul work on nuclear-powered aircraft carriers. Table 5 shows the numbers of SSBNs built over time by GD/EB, NNS, and two governmentoperated naval shipyards (NSYs)—Mare Island NSY, located in the San Francisco Bay area, and Portsmouth NSY of Portsmouth, NH, and Kittery, ME. Mare Island NSY is no longer in operation. NSYs have not built new Navy ships since the early 1970s; since that time, they have focused solely on overhauling and repairing Navy ships. As can be seen in the table, the Ohio-class boats were all built by GD/EB, and the three previous SSBN classes were built partly by GD/EB, and partly by NNS. GD/EB was the builder of the first boat in all four SSBN classes. The most recent SSBNs built by NNS were the George C. Marshall (SSBN-654) and George Washington Carver (SSBN-656), which were Lafayette/Benjamin Franklin-class boats that were procured in FY1964 and entered service in 1966. 72 73 Source: Transcript of hearing. “Boomer Sharing,” Defense Daily, August 1, 2011: 1-2. Congressional Research Service 31 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Table 5. Construction Shipyards of U.S. SSBNs George Washington (SSBN-598) class Ethan Allen (SSBN-608) class Lafayette/ Benjamin Franklin (SSBN616/640) class Ohio (SSBN-726) class FY58-FY59 FY59 and FY61 FY61-FY64 FY77-FY91 Number built by GD/EB 2 2 13 18 Number built by NNS 1 3 10 Number built by Mare Island NSY 1 6 Number built by Portsmouth NSY 1 2 Total number in class 5 Fiscal years procured 5 31 18 Source: Prepared by CRS based on data in Norman Polmar, The Ships and Aircraft of the U.S. Fleet, Annapolis, Naval Institute Press, various editions. NSY means naval shipyard. Notes: GD/EB was the builder of the first boat in all four SSBN classes. The George Washington-class boats were procured as modifications of SSNs that were already under construction. A total of 18 Ohio-class SSBNs were built; the first four were converted into SSGNs in 2002-2008, leaving 14 in service as SSBNs. There are at least five basic possibilities for building SSBN(X)s: • build all SSBN(X)s at GD/EB—the approach that was used for building the Ohio-class SSBNs; • build all SSBN(X)s at NNS; • build some SSBN(X)s GD/EB and some at NNS—the approach that was used for building the George Washington-, Ethan Allen-, and Lafayette/Benjamin Franklin-class SSBNs; Congressional Research Service 28 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program • build each SSBN(X) jointly at GD/EB and NNS, with final assembly of the boats alternating between the yards—the approach currently being used for building Virginia-class SSNs;70 and • build each SSBN(X) jointly at GD/EB and NNS, with one yard—either GD/EB or NNS—performing final assembly on every boat. In assessing these five approaches, policymakers may consider a number of factors, including their potential costs, their potential impacts on employment levels at GD/EB and NNS, and the relative value of preserving SSBN-unique construction skills (such as those relating to the construction and installation of SLBM compartments) at one shipyard or two. The relative costs of these five approaches could depend on a number of factors, including the following: • each yard’s share of SSBN(X) production work (if both yards are involved); • the number of SSNs procured during the years of SSBN(X) procurement (which can affect economies of scale in submarine production); • whether the current joint-production arrangement for the Virginia class remains in effect during those years (if the SSNs procured are Virginia-class boats);71 and • the volume of non-submarine-construction work performed at the two shipyards during these years, which would include in particular aircraft carrier construction and overhaul work at NNS. A January 12, 2011, press report stated: While the [SSBN(X)] submarine-building contracts would likely be competitively bid, [Electric Boat President John] Casey says he doubts any other company—even its attacksubmarine-building partner Northrop Grumman [now NNS]—can secure the work. Electric Boat built the existing Ohio-class fleet. 7074 and 74 Under the joint-production arrangement for Virginia-class boats, GD/EB builds certain parts of each boat, NNS builds certain other parts of each boat, and the two yards take turns building the reactor compartment and performing final assembly work. GD/EB is the final assembly yard for the first Virginia-class boat, the third one, and so on, while NNS is the final assembly yard for the second boat, the fourth one, and so on. The arrangement provides a roughly 5050 split in profits between the two firms for the production of Virginia-class SSNs. The agreement governing the jointproduction arrangement cannot be changed without the consent of both firms. Virginia-class SSNs are the first U.S. nuclear-powered submarines to be built jointly by two shipyards; all previous U.S. nuclear-powered submarines were built under the more traditional approach of building an entire boat within a single yard. The Virginia-class joint-production arrangement was proposed by the two shipyards, approved by the Navy, and then approved by Congress as part of its action on the FY1998 defense budget. A principal goal of the arrangement is to preserve submarine-construction skills at two U.S. shipyards while minimizing the cost of using two yards to build a class of submarines that is procured at a relatively low rate of one or two boats per year. Preserving submarineconstruction skills at two yards is viewed as a hedge against the possibility of operations at one of the yards being disrupted by a natural or man-made disaster. The joint-production arrangement is more expensive than single-yard strategy of building all Virginia-class boats at one shipyard (in part because the joint-production strategy splits the learning curve for reactor compartment construction and final assembly work on Virginia-class SSNs), but it is less expensive than a separate-yard strategy of building complete Virginia-class separately at both yards (in part because a separate-construction strategy splits the learning curve for all aspects of Virginia-class construction work, and because, in the absence of other submarine-construction work, a procurement rate of one or two Virginia-class boats per year is viewed as insufficient to sustain a meaningful competition between the two yards for contracts to build the boats). 71 The agreement governing the joint-production arrangement for the Virginia class cannot be changed without the consent of both yards.(continued...) Congressional Research Service 29 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program “We have every intention of building every one of those ships,” he says. “There’s no one else [who was] involved in designing and building that [Ohio-class] platform.72 It’s up to us to convince people we can do it at the right price.”73 Building CMCs for the UK’s SSBNs A related question is whether the CMCs for the UK’s replacement SSBNs should be built in the United States or the UK. Building them in the United States could reduce the procurement cost of CMCs produced for both countries’ SSBNs. It could also help maintain employment levels in U.S. shipyards. The UK, however, might prefer to build its CMCs in the UK in order to help maintain employment levels in UK shipyards or to preserve certain submarine-construction skills. An agreement to build the UK’s CMCs in the United States might include what is known as an “offset”—a corresponding agreement to have the UK build some portion of a defense item that is being procured for use by the U.S. military. Legislative Activity for FY2012 FY2012 Funding Request As shown in Table 3, the Navy’s proposed FY2012 budget requests $1,067.0 million in research and development funding for the SSBN(X) program, including $781.6 million in PE0603561N/Project 3220, and $285.4 million in PE0603570N/Project 3219. FY2012 Defense Authorization Bill (H.R. 1540) House The House Armed Services Committee, in its report (H.Rept. 112-78 of May 17, 2011) on H.R. 1540, recommended a $9 million increase to the amount requested for PE0603561N, and approval of the amount requested for PE0603570N (page 399). The committee’s report states: Perhaps the most worrisome aspect of the shipbuilding program is that it will be difficult to fund and maintain the current plan once the Navy begins to acquire replacements for the Ohio-class ballistic missile submarine fleet. In testimony before the Subcommittee on Seapower and Projection Forces, Navy officials suggested that there may be options to fund these boats outside of the Shipbuilding and Conversion, Navy account. The committee believes that the industrial teaming arrangement has been successful on the Virginia-class submarine program and would encourage the Secretary of the Navy to use the capabilities of both submarine shipbuilders in crafting an affordable acquisition strategy for the Ohio-class Replacement Program. (Pages 33-34) 72 The bracketed words in this sentence were inserted by CRS following a February 8, 2011, telephone call to CRS from Electric Boat in which Electric Boat stated that sentence in Mr. Casey’s quote refers to Electric Boat being the sole designer and builder of the current Ohio-class SSBNs. 73 Michael Fabey, “Electric Boat Recruits Engineers For Ohio-Class Sub Replacement,” Aerospace Daily & Defense Report, January 12, 2011: 1-2. Congressional Research Service 30 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program The report also states: The committee notes that the Department of Defense and Full-Year Continuing Appropriations Act, 2011 (Public Law 112-10) reduced fiscal year 2011 funding for Naval Reactors by $108.4 million, or 10 percent, from the fiscal year 2011 budget request. The committee is concerned that this reduction will delay design and procurement of critical naval reactors, particularly for the Ohio-class submarine replacement, and lead to an unacceptable delay in deployment of the Ohio-class submarine replacement. This replacement submarine is critical to the long-term viability of the nation’s nuclear deterrent, and the committee encourages full funding for Naval Reactors in the future. (Page 316) Regarding the number of SLBM launch tubes on the SSBN(X), Section 213 of H.R. 1540 as reported by the committee states: SEC. 213. LIMITATION ON AVAILABILITY OF FUNDS FOR OHIO-CLASS BALLISTIC MISSILE SUBMARINE REPLACEMENT PROGRAM. (a) Findings- Congress finds the following: (1) On May 13, 2010, the President submitted to Congress the report required under section 1251 of the National Defense Authorization Act for Fiscal Year 2010 (P.L. 111-84; 123 Stat. 2549) that stated, `The Secretary of Defense, based on recommendations from the Joint Chiefs of Staff, has established a baseline nuclear force structure that fully supports U.S. security requirements and conforms to the New START limits ... The United States will reduce the number of SLBM launchers (launch tubes) from 24 to 20 per SSBN, and deploy no more than 240 SLBMs at any time.’. (2) On January 10, 2011, the Under Secretary of Defense for Acquisition, Technology, and Logistics issued an acquisition decision memorandum for the Ohio-class submarine replacement program whereby the Navy received Milestone A approval to proceed with a replacement design based on 16 missile tubes. (3) Consistent with the reductions and limitations established in the New START Treaty, which entered into force on February 5, 2011, more than two-thirds of the deployed nuclear deterrent force of the United States are planned to be carried on ballistic missile submarines. (4) The Commander of the United States Strategic Command testified on March 2, 2011, that, `The issue of the number of tubes is not a simple black and white answer,’ but rather it is comprised of several issues including, `the overall number of tubes we wind up with at the end ... flexibility and options with how many warheads per missile per tube ... the overall number of boats ... and many other factors.’. He further stated that, `Sixteen [missile tubes per submarine] will meet STRATCOM’s requirements, given that we are sitting here 20 years in advance.’. (b) Sense of Congress- It is the sense of Congress that— (1) the long-term ability of the United States to maintain a nuclear force sufficient to address the range of mission requirements necessary to deter, dissuade, and defeat potential adversaries and assure allies and partners must not be comprised solely on the basis of the promise of potential cost savings resulting from the decision of the Secretary of Defense to reduce the planned number of missile tubes per Ohio-class ballistic missile submarine from 24 to 16; and Congressional Research Service 31 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program (2) because the planned Ohio-class replacement ballistic submarine is expected to be in operation through 2080, near-term design decisions should take into consideration uncertainties in the future threat and strategic environment. (c) Limitation(1) IN GENERAL- Of the funds authorized to be appropriated by this Act or otherwise made available for fiscal year 2012 for research, development, test, and evaluation, Navy, for the Ohio-class ballistic submarine replacement program, not more than 90 percent may be obligated or expended until the date on which the Secretary of Defense submits to the congressional defense committees a report containing— (A) a summary of the analysis conducted to support the acquisition decision memorandum, including any assessment of the threat and strategic environment and mission requirements that informed the decision to reduce the planned number of missile tubes per submarine from 20 (as stated in the report submitted to Congress under section 1251 of the National Defense Authorization Act for Fiscal Year 2010 (P.L. 111-84; 123 Stat. 2549)) to 16 (as stated in the acquisition decision memorandum); (B) a description of the threat and strategic environment assumed by the Secretary throughout the expected operational lifetime of the program, including how the Secretary would address significant changes to such threat and strategic environment; (C) a description of any other assumptions made by the Secretary throughout the expected operational lifetime of the program that provides the rationale of the Secretary to reduce the planned number of missile tubes per submarine to 16, including assumptions regarding— (i) changes in nuclear policy and strategy; (ii) changes in the role of ballistic missile submarines as a part of the overall nuclear forces of the United States; and (iii) further nuclear reductions, whether conducted under an international agreement or unilaterally; (D) an identification of key risks to missions or requirements that may be increased because of the Secretary’s decision to reduce the planned number of missile tubes per submarine to 16, including whether the Secretary plans to accept or mitigate such risks; and (E) a summary of the rigorous cost comparison of the designs for 16 missile tubes per submarine and 20 missile tubes per submarine, consistent with the direction provided in the acquisition decision memorandum, including the accuracy of the cost estimate of the procurement cost of each submarine. (2) FORM- The report under paragraph (1) shall be submitted in unclassified form, but may include a classified annex. (d) Definitions- In this section: (1) The term `acquisition decision memorandum’ means the acquisition decision memorandum regarding the Ohio-class submarine replacement program issued by the Under Secretary of Defense for Acquisition, Technology, and Logistics on January 10, 2011. Congressional Research Service 32 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program (2) The term `New START Treaty’ means the Treaty between the United States of America and the Russian Federation on Measures for the Further Reduction and Limitation of Strategic Offensive Arms, signed on April 8, 2010, and entered into force on February 5, 2011. Regarding Section 213, the committee’s report states: This section would contain four findings concerning the number of submarine launched ballistic missile (SLBM) launchers (missile tubes) planned for the Ohio-class ballistic missile submarine (SSBN) replacement, the composition of the deployed nuclear deterrent force of the United States planned under the New Strategic Arms Reduction Treaty (New START), and recent testimony by the commander of the United States Strategic Command. This section would express a sense of Congress that: (1) The long-term ability of the United States to maintain a nuclear force sufficient to address the range of mission requirements necessary to deter, dissuade, and defeat potential adversaries and assure allies and partners must not be comprised solely on the basis of the promise of potential cost savings resulting from the Department’s decision to reduce the planned number of missile tubes per Ohio-class ballistic missile submarine from 24 to 16; and (2) The planned Ohio-class ballistic submarine replacement is expected to be in operations through 2080 and therefore near-term design decisions should take into consideration uncertainties in the future threat and strategic environment. This section would also limit the obligation and expenditure of funds authorized to be appropriated or otherwise made available for fiscal year 2012 for the Ohio-class ballistic missile submarine replacement program to not more than 90 percent until the Secretary of Defense submits to the congressional defense committees a report summarizing the analysis that supported the Department’s decision to reduce the planned number of missile tubes per submarine to 16. Reporting elements would include: a description of the assumed threat and strategic environment throughout the expected operational lifetime of the program; a description of any assumptions regarding changes in nuclear policy and strategy, and further nuclear reductions; an identification of any missions or requirements that may have increased risk; and a summary of the cost comparison between 16 and 20 missile tube designs, including the accuracy of the cost estimate. Over the course of the last year, the committee has received inconsistent information on the number of missile tubes per hull planned for the Ohio-class ballistic missile submarine replacement. In a May 13, 2010, report to Congress, required by section 1251 of the National Defense Authorization Act for Fiscal Year 2010 (Public Law 111–84), the President outlined his SSBN force structure plans: ‘‘The Secretary of Defense, based on recommendations from the Joint Chiefs of Staff, has established a baseline nuclear force structure that fully supports U.S. security requirements and conforms to the New START limits.... The United States will reduce the number of SLBM launchers (launch tubes) from 24 to 20 per SSBN, and deploy no more than 240 SLBMs at any time.’’ These plans for 20 missile tubes per SSBN were reaffirmed in the joint Department of Energy and Department of Defense February 16, 2011, update to the report required by section 1251. However, on January 10, 2011, the Under Secretary of Defense for Acquisition, Technology, and Logistics issued an acquisition decision memorandum for the Ohio-class submarine replacement program whereby the Navy received milestone A approval to proceed with a design based on 16 missile tubes. The committee remains unclear as to the analysis and assumptions that informed the Department’s decision to reduce the planned number of missile tubes per SSBN from 24 to Congressional Research Service 33 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program 16, and the rationale for its deviation from the baseline force structure of 20 missile tubes per SSBN outlined in the report required by section 1251, other than the promise of potential cost savings. The committee seeks to hold the Department accountable to providing it with such information. (Pages 89-90) Congressional Research Service 34 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Appendix. Legislative Activity for FY2011 Summary of Congressional Action on FY2011 Funding Request Table A-1 summarizes congressional action on the Navy’s FY2011 funding request for the SSBN(X) program. Table A-1. Congressional Action on FY2011 Funding Request (Millions of then-year dollars, rounded to nearest tenth; totals may not add due to rounding) Authorization Appropriation Request HASC SASC Finala HACb SAC FInal PE0603561N/ Project 3220 493.0 493.0 493.0 n/aa n/ab Not clear – see narrative discussion below Not clear – see narrative discussion below PE0603570N/ Project 3219 179.3 179.3 179.3 n/aa n/ab 179.3 179.3 TOTAL 672.3 672.3 672.3 n/aa n/ab Not clear Not clear Sources: For request: Navy data provided to CRS on March 11, 2010, by Navy Office of Legislative Affairs. For congressional authorization and appropriation action: committee reports, joint explanatory statement on H.R. 6523 of the 111th Congress (for authorization final), and funding tables posted by the House Rules Committee in conjunction with H.R. 1473 of the 112th Congress (for appropriation final). Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is House Appropriations Committee; SAC is Senate Appropriations Committee; Final is the final version of the bill. PE means Program Element, that is, a research and development line item. A Program Element may include several projects. PE0603561N/Project 3220 is Sea Based Strategic Deterrent project within the PE for Advanced Submarine System Development. PE0603570N/Project 3219 is SSBN(X) reactor plant project within the PE for Advanced Nuclear Power Systems. n/a is not available. a. The joint explanatory statement on H.R. 6523, the final version of the bill, includes funding figures at the full account level, but not at the line-item level. b. The full House Appropriations Committee did not file an official, numbered committee report on the FY2011 DOD appropriations bill. FY2011 DOD and Full-Year Continuing Appropriations Act (H.R. 1473/P.L. 112-10) According to line-item funding tables posted by the House Rules Committee,74 the FY2011 Department of Defense and Full-Year Continuing Appropriations Act (H.R. 1473/P.L. 112-10 of April 15, 2011) reduces the Navy’s FY2011 research and development funding request for PE (Program Element) 0603561N, Advanced Submarine System Development, by $49.3 million for “execution delays.” The tables do not show how much, if any, of this $49.3 million reduction is to be applied against Project 3220—the part of PE 0603561N that is for the SSBN(X) program. 74 The funding tables were posted at http://rules.house.gov/Legislation/legislationDetails.aspx?NewsID=244. Congressional Research Service 35 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Since Project 3220 accounts for about 81% of the funding requested for PE 0603561N ($493.0 million of $608.6 million), it is possible that at least some of the $49.3 million reduction would be applied against Project 3220. According to the funding tables, H.R. 1473 fully funds the Navy’s FY2011 research and development funding request for PE 0603570N, Advanced Nuclear Power Systems, which includes, in Project 3219, $179.3 million for the SSBN(X) program. FY2011 DOD Appropriations Bill (S. 3800) Senate The Senate Appropriations Committee, in its report (S.Rept. 111-295 of September 16, 2010) on S. 3800 of the 111th Congress, recommended reducing the Navy’s FY2011 research and development funding request for PE (Program Element) 0603561N, Advanced Submarine System Development, by $49.3 million for “execution delays” (page 150, line 41). The report does not discuss how much, if any, of this $49.3 million reduction is to be applied against Project 3220— the part of PE 0603561N that is for the SSBN(X) program. Since Project 3220 accounts for about 81% of the funding requested for PE 0603561N ($493.0 million of $608.6 million), it is possible that at least some of the $49.3 million reduction would be applied against Project 3220. The committee’s report also recommends seven funding additions to PE 0603561N totaling $25.5 million (page 150, line 41). The committee’s report does not discuss these additions in detail; they may not be specific to the SSBN(X) program. The committee’s report recommends approving the Navy’s FY2011 research and development funding request for PE 0603570N, Advanced Nuclear Power Systems, which includes, in Project 3219, $179.3 million for the SSBN(X) program (page 145, line 45). FY2011 Ike Skelton National Defense Authorization Act (H.R. 6523/P.L. 111-383) House (H.R. 5136) The House Armed Services Committee, in its report (H.Rept. 111-491 of May 21, 2010) on the FY2011 defense authorization bill (H.R. 5136), recommends approval of the Navy’s FY2011 research and development funding request for the SSBN(X) program (page 147, line 41, and page 148, line 45). Section 211(c) of H.R. 5136 as reported by committee would limit the obligation and expenditure of FY2011 Navy research and development funding for the SSBN(X) until 30 days after the Navy submits a report on the SSBN(X) program. Section 211 states: SEC. 211. REPORT REQUIREMENTS FOR REPLACEMENT PROGRAM OF THE OHIO-CLASS BALLISTIC MISSILE SUBMARINE. (a) Findings- Congress makes the following findings: (1) The sea-based strategic deterrence provided by the ballistic missile submarine force of the Navy has been essential to the national security of the United States since the deployment of the first ballistic missile submarine, the USS George Washington SSBN 598, in 1960. Congressional Research Service 36 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program (2) Since 1960, a total of 59 submarines have served the United States to provide the seabased strategic deterrence. (3) As of the date of the enactment of this Act, the sea-based strategic deterrence is provided by the tremendous capability of the 14 ships of the Ohio-class submarine force, which have been the primary sea-based deterrent force for more than two decades. (4) Ballistic missile submarines are the most survivable asset in the arsenal of the United States in the event of a surprise nuclear attack on the country because, being submerged for months at a time, these submarines are virtually undetectable to any adversary and therefore invulnerable to attack, thus providing the submarines with the ability to respond with significant force against any adversary who attacks the United States or its allies. (b) Sense of Congress- It is the sense of Congress that— (1) as Ohio-class submarines reach the end of their service life and are retired, the United States must maintain the robust sea-based strategic deterrent force that has the ability to remain undetected by potential adversaries and must have the capability to deliver a retaliatory strike of such magnitude that no rational actor would dare attack the United States; (2) the Secretary of Defense should conduct a comprehensive analysis of the alternative capabilities to provide the sea-based strategic deterrence that includes consideration of different types and sizes of submarines, different types and sizes of missile systems, the number of submarines necessary to provide such deterrence, and the cost of each alternative; and (3) prior to requesting more than $1,000,000,000 in research and development funding to develop a replacement for the Ohio-class ballistic missile submarine force in advance of a Milestone A decision, the Secretary of Defense should have made available to Congress the guidance issued by the Director of Cost Assessment and Performance Evaluation with respect to the analysis of alternative capabilities and the results of such analysis. (c) Limitation(1) REPORT- Of the funds authorized to be appropriated by this Act or otherwise made available for fiscal year 2011 for research and development for the Navy, not more than 50 percent may be obligated or expended to research or develop a submarine as a replacement for the Ohio-class ballistic missile submarine force unless— (A) the Secretary of Defense submits to the congressional defense committees a report including— (i) guidance issued by the Director of Cost Assessment and Performance Evaluation with respect to the analysis of alternative capabilities to provide the sea-based strategic deterrence currently provided by the Ohio-class ballistic missile submarine force and any other guidance relating to requirements for such alternatives intended to affect the analysis; (ii) an analysis of the alternative capabilities considered by the Secretary to continue the seabased strategic deterrence currently provided by the Ohio-class ballistic missile submarine force, including— (I) the cost estimates for each alternative capability; (II) the operational challenges and benefits associated with each alternative capability; and Congressional Research Service 37 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program (III) the time needed to develop and deploy each alternative capability; and (iii) detailed reasoning associated with the decision to replace the capability of sea-based deterrence provided by the Ohio-class ballistic missile submarine force with an alternative capability designed to carry the Trident II D5 missile; and (B) a period of 30 days has elapsed after the date on which the report under subparagraph (A) is submitted. (2) FORM- The report required by paragraph (1) shall be submitted in unclassified form, but may include a classified annex. The report states: Ohio-class replacement program The committee strongly supports a robust sea-based strategic deterrent force. The current 14 ships of the Ohio-class ballistic missile submarines are a national treasure and have helped keep the nation safe for over two decades. Like the ballistic missile submarine classes that preceded them, a percentage of these vessels remain in an alert posture, at sea, invulnerable to attack by potential enemies, ready to retaliate should the nation be attacked. The committee supports efforts to retain this capability into the future. However, the committee has questions concerning the current program to replace the Ohioclass ships. First, the basic requirement of how much and what type of deterrent capability is sufficient for the national military strategy has not been communicated to the committee. Second, the committee has not been afforded the opportunity to review the analysis of alternatives conducted by the Navy, which determined that a submarine large enough to support the Trident II D5 missile weapons system is the preferred vessel to continue deterrent capability. Third, the committee has concerns that the decision to proceed with a submarine program of similar size as the Ohio-class ships was made prior to the analysis of alternatives, and that a potential use of a modified Virginia-class submarine, in production today, was discounted in favor of maintaining the Trident II D5 weapons system. Because of these concerns, elsewhere in this Act the committee will authorize, but withhold authority to obligate more than 50 percent of the funds requested for development of this program until the Secretary of Defense certifies to the committee of the necessity to continue sea-based deterrence with the Trident II D5 weapons system. (Pages 77-78) Senate (S. 3454) The FY2011 defense authorization bill (S. 3454), as reported by the Senate Armed Services Committee (S.Rept. 111-201 of June 4, 2010), recommends approval of the Navy’s FY2011 research and development funding request for the SSBN(X) program (page 732, lines 41 and 45 of the printed bill). (The bill as reported recommends three funding additions to PE 0603561N [line 41] totaling $26 million, but these additions do not appear specific to the SSBN(X) program. See pages 62-64 of the committee’s report for discussions of these three recommended additions.) The committee’s report states: The committee notes that the current shipbuilding plan includes the cost of the SSBN (X) program and the committee encourages the Navy to closely scrutinize requirements for this program in order to minimize its impact on the recapitalization of the Navy’s battle force. (Page 40) Congressional Research Service 38 . Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program The committee’s report also states: Strike study The budget request included $81.2 million in Research, Development, Test, and Evaluation, Navy, PE 11221N line 162 for strategic submarine and weapons systems support. The committee recommends a decrease of $10.0 million. Of the amount requested $10.0 million was for a study for ambiguity and other issues that associated with conventional and nuclear payloads on strategic ballistic missile submarines. The committee recommends no funds for the study. The committee notes that the National Academy of Sciences conducted an extensive study on this issue and the additional study would be redundant. (Page 71) Final Version (H.R. 6523/P.L. 111-383) H.R. 6523/P.L. 111-383 of January 7, 2011, contains no provisions relating specifically to the SSBN(X) program. The joint explanatory statement of the House and Senate Armed Services Committees on H.R. 6523 does not discuss the program. Author Contact Information Ronald O'Rourke Specialist in Naval Affairs rorourke@crs.loc.gov, 7-7610 Congressional Research Service 3932 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program • build each SSBN(X) jointly at GD/EB and NNS, with one yard—either GD/EB or NNS—performing final assembly on every boat. In assessing these five approaches, policymakers may consider a number of factors, including their potential costs, their potential impacts on employment levels at GD/EB and NNS, and the relative value of preserving SSBN-unique construction skills (such as those relating to the construction and installation of SLBM compartments) at one shipyard or two. The relative costs of these five approaches could depend on a number of factors, including the following: • each yard’s share of SSBN(X) production work (if both yards are involved); • the number of SSNs procured during the years of SSBN(X) procurement (which can affect economies of scale in submarine production); • whether the current joint-production arrangement for the Virginia class remains in effect during those years;75 and • the volume of non-submarine-construction work performed at the two shipyards during these years, which would include in particular aircraft carrier construction and overhaul work at NNS. A January 12, 2011, press report stated: While the [SSBN(X)] submarine-building contracts would likely be competitively bid, [Electric Boat President John] Casey says he doubts any other company—even its attacksubmarine-building partner Northrop Grumman [now NNS]—can secure the work. Electric Boat built the existing Ohio-class fleet. “We have every intention of building every one of those ships,” he says. “There’s no one else [who was] involved in designing and building that [Ohio-class] platform.76 It’s up to us to convince people we can do it at the right price.”77 Legislative Activity for FY2013 FY2013 Funding Request As shown in Table 3, the Navy’s proposed FY2013 budget requests $564.9 million in research and development funding for the Ohio replacement program, including $483.1 million in PE0603561N/Project 3220, and $81.8 million in PE0603570N/Project 3219. (...continued) work, a procurement rate of one or two Virginia-class boats per year is viewed as insufficient to sustain a meaningful competition between the two yards for contracts to build the boats). 75 The agreement governing the joint-production arrangement for the Virginia class cannot be changed without the consent of both yards. 76 The bracketed words in this sentence were inserted by CRS following a February 8, 2011, telephone call to CRS from Electric Boat in which Electric Boat stated that sentence in Mr. Casey’s quote refers to Electric Boat being the sole designer and builder of the current Ohio-class SSBNs. 77 Michael Fabey, “Electric Boat Recruits Engineers For Ohio-Class Sub Replacement,” Aerospace Daily & Defense Report, January 12, 2011: 1-2. Congressional Research Service 33 Navy Ohio Replacement (SSBN[X]) Ballistic Missile Submarine Program Author Contact Information Ronald O'Rourke Specialist in Naval Affairs rorourke@crs.loc.gov, 7-7610 Congressional Research Service 34