< Back to Current Version

Navy Columbia (SSBN-826) Class Ballistic Missile Submarine Program: Background and Issues for Congress

Changes from February 3, 2011 to March 10, 2011

This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.


Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Ronald O'Rourke Specialist in Naval Affairs February 3March 10, 2011 Congressional Research Service 7-5700 www.crs.gov R41129 CRS Report for Congress Prepared for Members and Committees of Congress Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Summary Ballistic missile submarines (SSBNs) carry submarine-launched ballistic missiles (SLBMs), which are large, long-range missiles armed with multiple nuclear warheads. The SSBNs’ basic mission is to remain hidden at sea with their SLBMs, so as to deter a nuclear attack on the United States by another country. Navy SSBNs The Navy’s ballistic missile submarines (SSBNs) form one leg of the U.S. strategic nuclear deterrent force, or “triad,” which also includes land-based intercontinental ballistic missiles (ICBMs) and landbasedland-based long-range bombers. The Navy currently operates 14 Ohio (SSBN-726) class SSBNs, the also known as Trident SSBNs, the first of which is projected to reach the end of its service life in 2027. The Navy is currently conducting development and design work on a planned class of 12 nextgeneration next-generation ballistic missile submarines, or SSBN(X)s, which the service wants to procure as replacements replacements for the 14 Ohio-class boats. The SSBN(X) program, is also known as the Ohio-class replacement program (ORP), received $497.4 million in research and development funding in the Navy’s FY2010 budget, and the replacement program (ORP). The Navy’s proposed FY2011 budget requested an additional $672.3 FY2012 budget requests $1,067 million in research and development funding for the program. Navy plans call for procuring the first SSBN(X) in FY2019, with advance procurement funding for the boat beginning in FY2015. The Navy in February 2010 preliminarily estimated the procurement cost of each SSBN(X) at $6 billion to $7 billion in FY2010 dollars—a figure equivalent to roughly one-half of the Navy’s budget each year for procuring new ships. In September 2010, the Department of Defense (DOD) stated that the Navy was. The Navy is now working to reduce the average unit procurement cost of ships 2 through boats 2-12 in the program to $5 billion in FY2010 dollars. Somea target figure of $4.9 billion each in FY2010 dollars. Even with this cost-reduction effort, some observers are concerned that procuring 12 12 SSBN(X)s during the 15-year period FY2019-FY2033, as called for in Navy plans, could lead to to reductions in procurement rates for other types of Navy ships during those years. Potential FY2011 issues for Congress include the following: • the accuracy of the Navy’s preliminary estimate of the procurement cost of each SSBN(X); • the prospective affordability of the SSBN(X) program and its potential impact on other Navy shipbuilding programs; • the impact of UK preferences for the design of its new SSBNs on U.S. consideration of SSBN(X) design options Potential oversight issues for Congress for the SSBN(X) program include the following: • the potential impact of a year-long continuing resolution (CR) for FY2011 at FY2010 funding levels on the Navy’s schedule for developing and procuring the SSBN(X); • the likelihood that the Navy will be able to reduce the average procurement cost of boats 2-12 in the program to the target figure of $4.9 billion each in FY2010 dollars; • the accuracy of the Navy’s estimate of the procurement cost of each SSBN(X); • the prospective affordability of the SSBN(X) program and its potential impact on other Navy shipbuilding programs; and • the question of which shipyard or shipyards will build SSBN(X)s. Options for reducing the cost of the SSBN(X) program or its potential impact on other Navy shipbuilding programs include procuring fewer than 12 SSBN(X)s; reducing the number of submarine-launched ballistic missiles (SLBMs) to be carried by each SSBN(X); designing the SSBN(X) to carry a smaller SLBM; stretching out the schedule for procuring SSBN(X)s and making greater use of split funding (i.e., two-year incremental funding) in procuring them; and funding the procurement of SSBN(X)s in a part of the Department of Defense (DOD) budget other than the Navy’s shipbuilding account; and increasing that is outside the Navy’s shipbuilding budget. This report focuses on the SSBN(X) as a Navy shipbuilding program. CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf, discusses the SSBN(X) as an element of future U.S. strategic nuclear forces in the context of strategic nuclear arms control agreements. Congressional Research Service Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Contents Introduction ................................................................................................................................1 Background ................................................................................................................................21 U.S. Navy SSBNs in General ................................................................................................21 Mission of SSBNs...........................................................................................................21 Current Ohio-Class SSBNs .............................................................................................32 Summary of U.S. SSBN Designs.....................................................................................4 U.S.-UK Cooperation on SLBMs ....................................................................................6 SSBN(X) Program ................................................................................................................7 Program Origin and Milestones .......................................................................................7 Procurement and Replacement Schedule .........................................................................9 SSBN(X) Design Features............................................................................................. 1110 Program Acquisition Cost ............................................................................................. 11 Common Missile Compartment (CMC)......................................................................... 1312 Program Funding .......................................................................................................... 1413 Issues for Congress ................................................................................................................... 14 Accuracy of Navy’s Estimated Unit Procurement Cost Near-Term Issue: Potential Impact of Year-Long Continuing Resolution........................................................ 15 Program Affordability and Impact on Other Navy Shipbuilding Programs .. 14 Likelihood That Navy Will Reach $4.9 Billion Target Cost.................................................. 16 Number of SSBN(X)s ...........14 Accuracy of Navy’s Estimated Unit Procurement Cost ............................................................. 15 Program Affordability and Impact on Other Navy Shipbuilding Programs ........................... 18 Design of SSBN(X)s ..............................16 Reducing the Planned Number of SSBN(X)s....................................................................... 20 17 Altering the Schedule for Procuring SSBN(X)s and Potential for Using Split to Make More Use of Incremental Funding ...................... 25 How Procurement of SSBN(X)s Is Funded in DOD’s Budget ........................................ 27 Potential for Increasing Shipbuilding Budget................................................................. 29 Impact of UK Preferences for Its SSBN on U.S. Consideration of SSBN(X) Design Options ................................................................................. 18 Procuring SSBN(X)s Outside Navy’s Shipbuilding Budget ........................................... 2920 Construction Shipyard(s)..................................................................................................... 3122 Building SSBN(X)s ...................................................................................................... 3122 Building CMCs for the UK’s SSBNs............................................................................. 33 Options for Congress ......24 Legislative Activity for FY2012 .......................................................................................................... 33 Legislative Activity for FY2012 24 Figures Figure 1. Ohio (SSBN-726) Class SSBN ................................................................................................ 334 Tables Table 1. U.S. SSBN Classes ........................................................................................................5 Table 2. Navy Schedule for Procuring SSBN(X)s and Replacing Ohio-Class SSBNs ................. 10 Table 3. SSBN(X) Program Funding ......................................................................................... 1413 Table 4. Navy SSBN(X) Procurement Schedule and a Notional Alternative Schedule ................ 2620 Table 5. Construction Shipyards of U.S. SSBNs ........................................................................ 3122 Table A-1. Congressional Action on FY2011 Funding Request Other than H.R. 3082/P.L. 111-322.................................................................................................................................. 3425 Congressional Research Service Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Appendixes Appendix. Legislative Activity for FY2011 ............................................................................... 3425 Contacts Author Contact Information ...................................................................................................... 3829 Congressional Research Service Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Introduction The Navy is currently conducting development and design work on a planned class of 12 nextgeneration ballistic missile submarines, or SSBN(X)s,1 which the service wants to procure as replacements for its current force of 14 Ohio-class ballistic missile submarines. The SSBN(X) program,This report provides background information and potential oversight issues for Congress on the Navy’s SSBN(X) program, a program to develop and procure 12 new ballistic missile submarines (SSBNs) as replacements for the Navy’s current force of 14 Ohio-class SSBNs. The SSBN(X) program is also known as the Ohio-class replacement program (ORP), received $497.4 million in research and development funding in the Navy’s FY2010 budget, and the. The Navy’s proposed FY2011 budget requested an additional $672.3 million in research and development funding for the program. Navy plans call for procuring the first SSBN(X) in FY2019, with advance procurement funding for the boat beginning in FY2015. The Navy in February 2010 preliminarily estimated the procurement cost of each SSBN(X) at $6 billion to $7 billion in FY2010 dollars—a figure equivalent to roughly one-half of the Navy’s budget each year for procuring new ships. In September 2010, the Department of Defense (DOD) stated that the Navy was working to reduce the average unit procurement cost of ships 2 through 12 in the program to $5 billion in FY2010 dollars. Some observers are concerned that the SSBN(X) program will significantly compound a challenge the Navy faces concerning the affordability of its long-term shipbuilding program. These observers are concerned that procuring 12 SSBN(X)s during the 15-year period FY2019-FY2033, as called for in Navy plans, could lead to reductions in procurement rates for other types of Navy ships during those years. The Navy’s report on its 30-year (FY2011-FY2040) shipbuilding plan states: “While the SSBN(X) is being procured, the Navy will be limited in its ability to procure other ship classes.”2 Potential FY2011 issues for Congress include the following: • the accuracy of the Navy’s preliminary estimate of the procurement cost of each SSBN(X); • the prospective affordability of the SSBN(X) program and its potential impact on other Navy shipbuilding programs; • the impact of UK preferences for the design of its new SSBNs on U.S. consideration of SSBN(X) design options; and • the question of which shipyard or shipyards will build SSBN(X)s. FY2011 options for Congress include approving, rejecting, or modifying the Navy’s FY2011 funding request for the program, and providing additional direction to the Navy or DOD concerning the SSBN(X) program. Congress’s decisions on the SSBN(X) program could significantly affect U.S. strategic nuclear capabilities, Navy funding requirements, the shipbuilding industrial base, and the UK’s program for replacing its own aging SSBNs. 1 In the designation SSBN(X), SS means submarine, B mean ballistic missile, and N means the ship is nuclear-powered (i.e., it uses a nuclear reactor to generate energy to propel the ship through the water and to power shipboard systems), and X means the design of the ship has not yet been determined. 2 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, pp. 24-25. Congressional Research Service 1 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress FY2012 budget requests $1,067 million in research and development funding for the SSBN(X) program. Decisions that Congress makes on the SSBN(X) program could substantially affect U.S. military capabilities and funding requirements, and the U.S. shipbuilding industrial base. This report focuses on the SSBN(X) as a Navy shipbuilding program. Another CRS report discusses the SSBN(X) as an element of future U.S. strategic nuclear forces in the context of strategic nuclear arms control agreements.31 Background U.S. Navy SSBNs in General Mission of SSBNs The U.S. Navy operates three kinds of submarines—nuclear-powered attack submarines (SSNs), nuclear-powered cruise missile submarines (SSGNs), and nuclear-powered ballistic missile submarines (SSBNs).42 The SSNs and SSGNs are multi-mission ships that perform a variety of peacetime and wartime missions.5 They do not carry nuclear weapons.6 The SSBNs, in contrast, perform a specialized mission of strategic nuclear deterrence, and carry submarine-launched ballistic missiles (SLBMs), which are large, long-range missiles armed with multiple nuclear warheads. SSBNs, which are sometimes referred to informally as “boomers,”7 launch their SLBMs from large-diameter vertical launch tubes located in the middle section of the boat.8 The SSBNs’ basic mission is to remain hidden at sea with their SLBMs, so as to deter a nuclear attack on the United States by another country by demonstrating to other countries that the United States has an assured second-strike capability, meaning a survivable system for carrying out a retaliatory nuclear attack. 3 CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf. 4 In the designation SSGN, the G stands for guided missile (such as a cruise missile). As shown by the “Ns” in SSN, 3 They do not carry nuclear weapons.4 1 CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf. In the designations SSN, SSGN, SSBN, and SSBN(X), the SS stands for submarine, N stands for nuclear-powered (meaning the ship is powered by a nuclear reactor), G stands for guided missile (such as a cruise missile), B stands for ballistic missile, and (X) means the design of the ship has not yet been determined. As shown by the “Ns” in SSN, SSGN, and SSBN, all U.S. Navy submarines are nuclear-powered. Other navies operate non-nuclear powered submarines, which are powered by energy sources such as diesel engines. A submarine’s use of nuclear or non-nuclear power as its energy source is not an indication of whether it is armed with nuclear weapons—a nuclear-powered submarine can lack nuclear weapons, and a non-nuclear-powered submarine can be armed with nuclear weapons. 53 These missions include covert intelligence, surveillance, and reconnaissance (ISR), much of it done for national-level (as opposed to purely Navy) purposes; covert insertion and recovery of special operations forces (SOF); covert strikes against land targets with the Tomahawk cruise missiles; covert offensive and defensive mine warfare; anti-submarine warfare (ASW); and anti-surface ship warfare. The Navy’s four SSGNs, which are converted former SSBNs, can carry larger numbers of Tomahawks and SOF personnel than can the SSNs. SSGN operations consequently may focus more strongly on Tomahawk and SOF missions than do SSN operations. For more on the Navy’s SSNs and SSGNs, see CRS Report RL32418, Navy Virginia (SSN-774) Class Attack Submarine Procurement: Background and Issues for Congress, by Ronald O'Rourke, and CRS Report RS21007, Navy Trident Submarine Conversion (SSGN) Program: Background and Issues for Congress, by Ronald O'Rourke. 64 The Navy’s non-strategic nuclear weapons—meaning all of the service’s nuclear weapons other than submarinelaunched ballistic missiles (SLBMs)—were removed from Navy surface ships and submarines under a unilateral U.S. nuclear initiative announced by President George H. W. Bush in September 1991. The initiative reserved a right to rearm SSNs at some point in the future with nuclear-armed Tomahawk land attack missiles (TLAM-Ns) should conditions warrant. Navy TLAM-Ns were placed in storage to support this option. DOD’s report on the 2010 Nuclear Posture Review (NPR), released on April 6, 2010, states that the Untied States will retire the TLAM-Ns. (Department of Defense, Nuclear Posture Review Report, April 2010, pp. xiii and 28.) 7 This informal name is a reference to the large boom that would be made by the detonation of an SLBM nuclear warhead. 8 SSBNs, like other Navy submarines, are also equipped with horizontal torpedo tubes in the bow for firing torpedoes or other torpedo-sized weapons. Congressional Research Service 2 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Navy SSBNs form one leg of the U.S. strategic nuclear deterrent force, or “triad,” which also includes land-based intercontinental ballistic missiles (ICBMs) and land-based long-range bombers. At any given moment, some of the Navy’s SSBNs are conducting nuclear deterrent patrols. The Navy’s report on its 30-year shipbuilding plan states: “These ships are the most survivable leg of the Nation’s strategic arsenal and provide the Nation’s only day-to-day assured nuclear response capability.”9 DOD’s report on the 2010 Nuclear Posture Review (NPR), released on April 6, 2010, states that “strategic nuclear submarines (SSBNs) and the SLBMs they carry represent the most survivable leg of the U.S. nuclear Triad.”10(continued...) 2 Congressional Research Service 1 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress The SSBNs, in contrast, perform a specialized mission of strategic nuclear deterrence. To perform this mission, SSBNs are armed with submarine-launched ballistic missiles (SLBMs), which are large, long-range missiles armed with multiple nuclear warheads. SSBNs launch their SLBMs from large-diameter vertical launch tubes located in the middle section of the boat.5 The SSBNs’ basic mission is to remain hidden at sea with their SLBMs, so as to deter a nuclear attack on the United States by another country by demonstrating to other countries that the United States has an assured second-strike capability, meaning a survivable system for carrying out a retaliatory nuclear attack. Navy SSBNs, which are sometimes referred to informally as “boomers,”6 form one leg of the U.S. strategic nuclear deterrent force, or “triad,” which also includes land-based intercontinental ballistic missiles (ICBMs) and land-based long-range bombers. At any given moment, some of the Navy’s SSBNs are conducting nuclear deterrent patrols. The Navy’s report on its FY2011 30year shipbuilding plan states: “These ships are the most survivable leg of the Nation’s strategic arsenal and provide the Nation’s only day-to-day assured nuclear response capability.”7 DOD’s report on the 2010 Nuclear Posture Review (NPR), released on April 6, 2010, states that “strategic nuclear submarines (SSBNs) and the SLBMs they carry represent the most survivable leg of the U.S. nuclear Triad.”8 Current Ohio-Class SSBNs The Navy currently operates 14 Ohio (SSBN-726) class SSBNs. The boats are commonly called Trident SSBNs or simply Tridents because they carry Trident SLBMs. A total of 18 Ohio-class SSBNs were procured in FY1974-FY1991. The ships entered service in 1981-1997. The boats were designed and built by General Dynamics’ Electric Boat Division (GD/EB) of Groton, CT, and Quonset Point, RI. They were originally designed for 30-year service lives but were later certified for 42-year service lives, consisting of two 20-year periods of operation separated by a two-year mid-life nuclear refueling overhaul, called an engineered refueling overhaul (ERO). The nuclear refueling overhaul includes both a nuclear refueling and overhaul work on the ship that is not related to the nuclear refueling, and costs roughly $260 million per ship. Ohio-class SSBNs each carry 24 SLBMs. The first eight boats in the class were originally armed with Trident I C-4 SLBMs; the final 10 were armed with larger and more-capable Trident II D-5 SLBMs. The Clinton Administration’s 1994 Nuclear Posture Review (NPR) recommended a (...continued) of Defense, Nuclear Posture Review Report, April 2010, pp. xiii and 28.) 5 SSBNs, like other Navy submarines, are also equipped with horizontal torpedo tubes in the bow for firing torpedoes or other torpedo-sized weapons. 6 This informal name is a reference to the large boom that would be made by the detonation of an SLBM nuclear warhead. 7 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 15. 8 Department of Defense, Nuclear Posture Review Report, April 2010, p. 22. The next sentence in the report states: “Today, there appears to be no viable near or mid-term threats to the survivability of U.S. SSBNs, but such threats—or other technical problems—cannot be ruled out over the long term.” The report similarly states on page 23: “Today, there appears to be no credible near or mid-term threats to the survivability of U.S. SSBNs. However, given the stakes involved, the Department of Defense will continue a robust SSBN Security Program that aims to anticipate potential threats and develop appropriate countermeasures to protect current and future SSBNs.” Congressional Research Service 2 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress strategic nuclear force for the START II strategic nuclear arms reduction treaty that included 14 Ohio-class SSBNs, all armed with D-5s. This recommendation prompted interest in the idea of converting the first four Ohio-class boats (SSBNs 726-729) into SSGNs, so as to make good use of the 20 years of potential operational life remaining in these four boats, and to bolster the U.S. SSN fleet. The first four Ohio-class boats were converted into SSGNs in 2002-2008,119 and the next next four (SSBNs 730-733) were backfitted with D-5 SLBMs in 2000-2005, producing the current current force of 14 Ohio-class SSBNs, all of which are armed with D-5 SLBMs. Eight of the 14 Ohio-class SSBNs are homeported at Bangor, WA, in Puget Sound; the other six are homeported at Kings Bay, GA, close to the Florida border. Unlike most Navy ships, which are operated by single crews, Navy SSBNs are operated by alternating crews (called the Blue and Gold crews) so as to maximize the percentage of time that 9 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 15. 10 Department of Defense, Nuclear Posture Review Report, April 2010, p. 22. The next sentence in the report states: “Today, there appears to be no viable near or mid-term threats to the survivability of U.S. SSBNs, but such threats—or other technical problems—cannot be ruled out over the long term.” The report similarly states on page 23: “Today, there appears to be no credible near or mid-term threats to the survivability of U.S. SSBNs. However, given the stakes involved, the Department of Defense will continue a robust SSBN Security Program that aims to anticipate potential threats and develop appropriate countermeasures to protect current and future SSBNs.” 11 For more on the SSGN conversion program, see CRS Report RS21007, Navy Trident Submarine Conversion (SSGN) Program: Background and Issues for Congress, by Ronald O'Rourke. Congressional Research Service 3 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress they spend at sea in deployed status. The Navy consequently maintains 28 crews to operate its 14 Ohio-class SSBNs. The first of the 14 Ohio-class SSBNs (SSBN-730) will reach the end of its 42-year service life in 2027. The remaining 13 will reach the ends of their service lives at a rate of roughly one ship per year thereafter, with the 14th reaching the end of its service life in 2040. The Navy has initiated a program to refurbish and extend the service lives of D-5 SLBMs to 2042 “to match the OHIO Class submarine service life.”12they spend at sea in deployed status. The Navy consequently maintains 28 crews to operate its 14 Ohio-class SSBNs. The first of the 14 Ohio-class SSBNs (SSBN-730) will reach the end of its 42-year service life in 2027. The remaining 13 will reach the ends of their service lives at a rate of roughly one ship per year thereafter, with the 14th reaching the end of its service life in 2040. The Navy has initiated a program to refurbish and extend the service lives of D-5 SLBMs to 2042 “to match the OHIO Class submarine service life.”10 Figure 1 shows an Ohio-class SSBN with the hatches to some of its SLBM launch tubes open. 9 For more on the SSGN conversion program, see CRS Report RS21007, Navy Trident Submarine Conversion (SSGN) Program: Background and Issues for Congress, by Ronald O'Rourke. 10 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 4. Congressional Research Service 3 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Figure 1. Ohio (SSBN-726) Class SSBN With the hatches to some of its SLBM launch tubes open Source: U.S. Navy file photo accessed by CRS on February 24, 2011, at http://www.navy.mil/management/ photodb/photos/101029-N-1325N-005.jpg. Summary of U.S. SSBN Designs The Navy has operated four classes of SSBNs since 1959. Table 1 compares the current Ohioclass SSBN design to the three earlier U.S. SSBN designs. As shown in the table, the size of U.S. SSBNs has grown over time, reflecting in part a growth in the size and number of SLBMs carried on each boat. (A longer SLBM can require a boat with a bigger beam [i.e., diameter], and more or larger-diameter SLBMs can require a boat with a greater length.) The Ohio-class design, at 18,750 tons submerged displacement, is more than twice the size of earlier U.S. SSBNs. The The Ohio class carries an SLBM (the D-5) that is much larger than the SLBMs carried by earlier U.S. SSBNs, and it carries 24 SLBMs, compared to the 16 on earlier U.S. SSBNs.13 12 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 4. 13 SSBNs.11 In part for these reasons, the Ohio-class design, with a submerged displacement of 18,750 tons, is more than twice the size of earlier U.S. SSBNs. 11 The larger size of the Ohio-class design also reflects a growth in size over time in U.S. submarine designs due to other reasons, such as providing increased interior volume for measures to quiet the submarine acoustically, so as to make it harder to detect. Congressional Research Service 4 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Table 1. U.S. SSBN Classes George Washington (SSBN-598) class Ethan Allen (SSBN-608) class Lafayette/Benjamin Franklin (SSBN616/640) class Ohio (SSBN-726) class 5 5 31 18/14 Fiscal years procured FY1958-FY1959 FY1959 and FY1961 FY1961-FY1964 FY1974-/FY1977 FY1991 Years in commission 1959-1985 1961-1992 1963-2002 1981/1984- - present Length 381.7 feet 410.5 feet 425 feet 560 feet Beam 33 feet 33 feet 33 feet 42 feet 6,700 tons 7,900 tons 8,250 tons 18,750 tons 16 16 16 24 Polaris A-3 Polaris A-3 Poseidon C-3/ Trident I C-4 Trident II D-5 Diameter of those SLBMs 54 inches 54 inches 74 inches 83 inches Length of those SLBMs 32.3 feet 32.3 feet 34 feet 44 feet Weight of each SLBM (pounds) 36,000 pounds 36,000 pounds 65,000/73,000 pounds ~130,000 pounds Range of SLBMs ~2,500 nm ~2,500 nm ~2,500 nm/~4,000 nm ~4,000 nm Number in class Submerged displacement Number of SLBMs Final type(s) of SLBM carried Sources: Prepared by CRS based on data in Norman Polmar, The Ships and Aircraft of the U.S. Fleet, Annapolis, Naval Institute Press, various editions, and (for SSBN decommissioning dates) U.S. Naval Vessel Register. Notes: Beam is the maximum width of a ship. For the submarines here, which have cylindrical hulls, beam is the diameter of the hull. The range of an SLBM can vary, depending on the number and weight of nuclear warheads it carries; actual ranges can be lesser or greater than those shown. The George Washington-class boats were procured as modifications of SSNs that were already under construction. Three of the boats were converted into SSNs toward the ends of their lives and were decommissioned in 1983-1985. The two boats that remained SSBNs throughout their lives were decommissioned in 1981. All five Ethan Allen-class boats were converted into SSNs toward the ends of their lives. The boats were decommissioned in 1983 (two boats), 1985, 1991, and 1992. Two of the Lafayette/Benjamin Franklin-class boats were converted into SSNs toward the ends of their lives and were decommissioned in 1999 and 2002. The 29 that remained SSBNs throughout their lives were decommissioned in 1986-1995. For 19 of the boats, the Poseidon C-3 was the final type of SLBM carried; for the other 12, the Trident I C-4 SLBM was the final type of SLBM carried. A total of 18 Ohio-class SSBNs were built. The first four, which entered service in 1981-1984, were converted into SSGNs in 2002-2008. The remaining 14 boats entered service in 1984-1997. Congressional Research Service 5 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress U.S.-UK Cooperation on SLBMs SSBNs are also operated by the United Kingdom, France, Russia, and China.1412 The UK’s four Vanguard-class SSBNs, which entered service in 1993-1999, each carry 16 Trident II D-5 SLBMs. (The nuclear warheads on UK D-5s are of UK design and manufacture.) Previous classes Previous classes of UK SSBNs similarly carried earlier-generation U.S. SLBMs.13 The UK’s use of U.S.-made SLBMs on its SSBNs is one element of a long-standing close cooperation between the two countries on nuclear-related issues that is carried out under the 1958 Agreement for Cooperation on the Uses of Atomic Energy for Mutual Defense Purposes (also known as the Mutual Defense Agreement). Within the framework established by the 1958 agreement, cooperation on SLBMs in particular is carried out under the 1963 Polaris Sales Agreement and a 1982 Exchange of Letters between the two governments.1514 The Navy testified in March 2010 that “the United States and the 14 12 India in July 2009 launched a nuclear-powered submarine that is equipped to carry several short-range SLBMs; the ship is not expected to enter service until 2011 at the earliest. 1513 Although the SLBMs on UK SSBNs are U.S.-made, the nuclear warheads on the missiles are of UK design and manufacture. 14 A March 18, 2010, report by the UK Parliament’s House of Commons Foreign Affairs Committee stated: During the Cold War, the UK’s nuclear co-operation with the United States was considered to be at the heart of the [UK-U.S.] ‘special relationship’. This included the 1958 Mutual Defence Agreement, the 1963 Polaris Sales Agreement (PSA) (subsequently amended for Trident), and the UK’s use of the US nuclear test site in Nevada from 1962 to 1992. The co-operation also encompassed agreements for the United States to use bases in Britain, with the right to store nuclear weapons, and agreements for two bases in Yorkshire (Fylingdales and Menwith Hill) to be upgraded to support US missile defence plans. In 1958, the UK and US signed the Mutual Defence Agreement (MDA). Although some of the appendices, amendments and Memoranda of Understanding remain classified, it is known that the agreement provides for extensive co-operation on nuclear warhead and reactor technologies, in particular the exchange of classified information concerning nuclear weapons to improve design, development and fabrication capability. The agreement also provides for the transfer of nuclear warhead-related materials. The agreement was renewed in 2004 for another ten years. The other major UK-US agreement in this field is the 1963 Polaris Sales Agreement (PSA) which allows the UK to acquire, support and operate the US Trident missile system. Originally signed to allow the UK to acquire the Polaris Submarine Launched Ballistic Missile (SLBM) system in the 1960s, it was amended in 1980 to facilitate purchase of the Trident I (C4) missile and again in 1982 to authorise purchase of the more advanced Trident II (D5) in place of the C4. In return, the UK agreed to formally assign its nuclear forces to the defence of NATO, except in an extreme national emergency, under the terms of the 1962 Nassau Agreement reached between President John F. Kennedy and Prime Minister Harold Macmillan to facilitate negotiation of the PSA. Current nuclear co-operation takes the form of leasing arrangements of around 60 Trident II D5 missiles from the US for the UK’s independent deterrent, and long-standing collaboration on the design of the W76 nuclear warhead carried on UK missiles. In 2006 it was revealed that the US and the UK had been working jointly on a new ‘Reliable Replacement Warhead’ (RRW) that would modernise existing W76-style designs. In 2009 it emerged that simulation testing at Aldermaston on dual axis hydrodynamics experiments had provided the US with scientific data it did not otherwise possess on this RRW programme. The level of co-operation between the two countries on highly sensitive military technology is, according to the written submission from Ian Kearns, “well above the norm, even for a close alliance relationship”. He quoted Admiral William Crowe, the former US Ambassador to London, who likened the UK-US nuclear relationship to that of an iceberg, “with a small tip of it sticking out, but beneath the water there is quite a bit of everyday business that goes on between our two governments in a fashion that’s unprecedented in the world.” Dr Kearns also commented that the personal bonds between the US/UK scientific and technical establishments were deeply rooted. (House of Commons, Foreign Affairs Committee, Sixth Report –Repor Global Security: UK-US Relations, March 18, 2010, paragraphs 131-135. The report is available online at ; http://www.publications.parliament.uk/pa/cm200910/ cmselect/cmfaff/114/11402.htm; paragraphs 131-135 are included in the section of the report available online at (continued...) Congressional Research Service 6 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress “the United States and the United Kingdom have maintained a shared commitment to nuclear deterrence through the Polaris Sales Agreement since April 1963. The U.S. will continue to maintain its strong strategic relationship with the UK for our respective follow-on platforms, based upon the Polaris Sales Agreement.”1615 The first Vanguard-class SSBN was originally projected to reach the end of its service life in 2024, but an October 2010 UK defense and security review report states that the lives of the Vanguard class ships will now be extended by a few years, so that the four boats will remain in service into the late 2020s and early 2030s.1716 The UK plans to replace the four Vanguard-class boats with three or four next-generation SSBNs. The October 2010 UK defense and security review report states that each new SSBN is to be equipped with 8 D-5 SLBMs, rather than 12 as previously planned. The report states that “‘Initial Gate’—a decision to move ahead with early stages of the work involved—will be approved and the next phase of the project will start by the end of [2010]. ‘Main Gate’—the decision to start building the submarines—is required around 2016.”1817 The first new boat is to be delivered by 2028, or about four years later than previously planned.1918 The UK has wanted their replacement SSBNs to carry D-5 SLBMs, and for any successor to the D-5 SLBM to be compatible with, or be capable of being made compatible with, the D-5 launch system. President George W. Bush, in a December 2006 letter to UK Prime Minister Tony Blair, invited the UK to participate in any program to replace the D-5 SLBMs, and stated that any successor to the D-5 system should be compatible with, or be capable of being made compatible with, the launch system for the D-5 SLBM. SSBN(X) Program Program Origin and Milestones Although the eventual need to replace the Ohio-class SSBNs has been known for many years, the SSBN(X) program can be traced more specifically to an exchange of letters in December 2006 between President George W. Bush and UK Prime Minister Tony Blair concerning the UK’s desire to participate in a program to extend the service life of the Trident II D-5 SLBM into the 2040s, and to have its next-generation SSBNs carry D-5s. Following this exchange of letters, and with an awareness of the projected retirement dates of the Ohio-class SSBNs and the time that would likely be needed to develop and field a replacement for them, DOD in 2007 began studies (...continued) available at http://www.publications.parliament.uk/pa/cm200910/cmselect/cmfaff/114/11406.htm.) 1615 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 6. 1716 Securing Britain in an Age of Uncertainty: The Strategic Defence and Security Review, Presented to Parliament by the Prime Minister by Command of Her Majesty, October 2010, p. 39. 1817 Securing Britain in an Age of Uncertainty: The Strategic Defence and Security Review, Presented to Parliament by the Prime Minister by Command of Her Majesty, October 2010, p. 5, 38-39. For more on the UK’s Successor SSBN program as it existed prior to the October 2010 UK defense and security review report, see Richard Scott, “Deterrence At A Discount?” Jane’s Defence Weekly, December 23, 2009: 26-31. 1918 Securing Britain in an Age of Uncertainty: The Strategic Defence and Security Review, Presented to Parliament by the Prime Minister by Command of Her Majesty, October 2010, p. 39. Congressional Research Service 7 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress on a next-generation sea-based strategic deterrent (SBSD).2019 The studies used the term sea-based strategic deterrent (SBSD) to signal the possibility that the new system would not necessarily be a submarine. An Initial Capabilities Document (ICD) for a new SBSD was developed in early 200821200820 and approved by DOD’s Joint Requirements Oversight Committee (JROC) on June 20, 2008.2221 In July 2008, DOD issued a Concept Decision providing guidance for an analysis of alternatives (AOA) for the program; an acquisition decision memorandum from John Young, DOD’s acquisition executive, stated the new system would, barring some discovery, be a submarine. 2322 The Navy established an SSBN(X) program office at about this same time. 2423 The AOA reportedly began in the summer or fall of 2008.25 The basic analysis for the AOA was completed in May 2009, and the final report on the AOA was completed in September 2009.26 As of March 2010, the AOA was being reviewed within the Navy;27 later in 2010, copies of the AOA were provided to the congressional defense committees. The program’s Milestone A review meeting was postponed from the spring of 201028 to December 9, 2011. On February 3, 2011, the Navy provided the following statement to CRS concerning the outcome of the December 9 24 The AOA was completed, with final brief to the Office of the Secretary of Defense (OSD), on May 20, 2009. The final AOA report was completed in September 2009. An AOA Sufficiency Review Letter was signed by OSD’s Director, Cost Assessment & Program Evaluation (CAPE) on December 8, 2009.25 The program’s Milestone A review meeting was held on December 9, 2010. On February 3, 2011, the Navy provided the following statement to CRS concerning the outcome of the December 9 meeting: The OHIO Replacement Program achieved Milestone A and has been approved to enter the Technology Development Phase of the Dept. of Defense Life Cycle Management System as of Jan. 10, 2011. This milestone comes following the endorsement of the Defense Acquisition Board (DAB), chaired by Dr. Carter (USD for Acquisition, Technology, and Logistics) who has signed the program’s Milestone A Acquisition Decision Memorandum (ADM). 20 The DAB endorsed replacing the current 14 Ohio-class Ballistic Missile Submarines (SSBNs) as they reach the end of their service life with 12 Ohio Replacement Submarines, each comprising 16, 87-inch diameter missile tubes utilizing TRIDENT II D5 Life Extended missiles (initial loadout). The decision came after the program was presented to the Defense Acquisition Board (DAB) on Dec. 9, 2010. 19 In February 2007, the commander of U.S. Strategic Command (STRATCOM) commissioned a task force to support an anticipated Underwater Launched Missile Study (ULMS). On June 8, 2007, the Secretary of the Navy initiated the ULMS. Six days later, the commander of STRATCOM directed that a Sea Based Strategic Deterrent (SBSD) capability-based assessment (CBA) be performed. In July 2007, the task force established by the commander of STRATCOM provided its recommendations regarding capabilities and characteristics for a new SBSD. (Source: Navy list of key events relating to the ULMS and SBSD provided to CRS and the Congressional Budget Office (CBO) on July 7, 2008.) 2120 On February 14, 2008, the SBSD ICD was approved for joint staffing by the Navy’s Resources and Requirements Review Board (R3B). On April 29, 2008, the SBSD was approved by DOD’s Functional Capabilities Board (FCB) to proceed to DOD’s Joint Capabilities Board (JCB). (Source: Navy list of key events relating to the ULMS and SBSD provided to CRS and the Congressional Budget Office (CBO) on July 7, 2008.) 2221 Navy briefing to CRS and CBO on the SBSD program, July 6, 2009. 2322 Navy briefing to CRS and CBO on the SBSD program, July 6, 2009. 2423 An August 2008 press report states that the program office, called PMS-397, “was established within the last two months.” (Dan Taylor, “Navy Stands Up Program Office To Manage Next-Generation SSBN,” Inside the Navy, August 17, 2008. 2524 “Going Ballistic,” Defense Daily, September 22, 2008, p. 1. 2625 Department of the NavyDefense Fiscal Year (FY) 20112012 Budget Estimates, Justification of Estimates, Research, Development, Navy, Justification Book Volume 2, Research, Development, Test & Evaluation, Navy, Budget Activity 4, entry for PE0603561N, Project 3220 (pdf page 433 of 1054). 27 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 6. 28 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 6. Congressional Research Service 8 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress The DAB endorsed replacing the current 14 Ohio-class Ballistic Missile Submarines (SSBNs) as they reach the end of their service life with 12 Ohio Replacement Submarines, each comprising 16, 87-inch diameter missile tubes utilizing TRIDENT II D5 Life Extended missiles (initial loadout). The decision came after the program was presented to the Defense Acquisition Board (DAB) on Dec. 9, 2010. 345 of 888). Congressional Research Service 8 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress The ADM validates the program’s Technology Development Strategy and allows entry into the Technology Development Phase during which warfighting requirements will be refined to meet operational and affordability goals. Design, prototyping, and technology development efforts will continue to ensure sufficient technological maturity for lead ship procurement in 2019. The first OHIO Replacement submarine will enter service in Fiscal Year 2029 as the existing OHIO submarines reach the end of their extended service life of 43 years.2926 A November 2010 DOD report to Congress on strategic nuclear weapon systems stated that: Current key milestones for the SSBN replacement program include: • Research, development, test, and evaluation (RDT&E) began in FY 2010 and continues with the goal of achieving 10 percent greater design maturity prior to starting procurement than the USS VIRGINIA class had before procurement started; • In FY 2015, the Navy will begin the detailed design and advanced procurement of critical components; • In FY 2019, the Navy will begin the seven-year construction period for the new SSBN lead ship; • In FY 2026, the Navy will begin the three-year strategic certification period for the lead ship; and • In FY 2029, the lead ship will commence active strategic at-sea service.3027 Procurement and Replacement Schedule Table 2 shows the Navy’s proposed schedule for procuring 12 SSBN(X)s, and for having SSBN(X)s replace Ohio-class SSBNs. As shown in the table, the Navy wants to procure the first SSBN(X) in FY2019 and have it enter service in FY2028FY2029. The remaining 11 would be procured between FY2022 and FY2033 and would enter service between FY2029FY2030 and FY2040. The Navy states that the schedule for procuring the 12 SSBN(X)s is inextricably linked to legacy [i.e., Ohio-class] SSBN retirements. The latest start for the lead SSBN(X) is FY 2019 and the replacements must start reaching the operational force by FY 2029. There is no leeway in this plan to allow a later start or any delay in the procurement plan.”31 The implication from this 2928 26 Source: E-mailEmail from Navy Office of Legislative Affairs to CRS, February 3, 2011. 27 November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10. 3128 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, (continued...) 30February 2010, p. 24. The report similarly states on page 5 that “the first boat in the class must be procured no later than FY 2019 to ensure that 12 operational ballistic missile submarines will always be available to perform the vital strategic deterrent mission.” Congressional Research Service 9 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress The implication from this statement is that deferring the procurement of one or more SSBN(X)s beyond the dates shown in Table 2 would result in an SSBN force that drops below 12 boats for some period of time. Table 2. Navy Schedule for Procuring SSBN(X)s and Replacing Ohio-Class SSBNs Fiscal Year Number of SSBN(X)s procured 2019 1 Cumulative number of SSBN(X)s in service Ohio-class SSBNs in service Combined number of Ohioclass SSBNs and SSBN(X)s in service 2020 2021 2022 1 2023 2024 1 Ohio-class SSBNs in service Combined number of Ohioclass SSBNs and SSBN(X)s in service 14 14 2020 14 14 2021 14 14 14 14 14 14 Fiscal Year Number of SSBN(X)s procured 2019 1 2022 Cumulative number of SSBN(X)s in service 1 2023 2024 1 14 14 2025 1 14 14 2026 1 14 14 2027 1 13 13 2028 1 1 12 13 2029 1 21 11 1312 2030 1 2 10 12 2031 1 3 9 12 2032 1 4 8 12 2033 1 5 7 12 2034 6 6 12 2035 7 5 12 2036 8 4 12 2037 9 3 12 2038 10 2 12 2039 11 1 12 2040 12 12 Source: Navy data provided by the Navy to CRS and the Congressional Budget Office on February 18, 2010, by Navy Office of Legislative Affairs. (...continued) February 2010, p. 24. The report similarly states on page 5 that “the first boat in the class must be procured no later than FY 2019 to ensure that 12 operational ballistic missile submarines will always be available to perform the vital strategic deterrent mission.” Congressional Research Service 10 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress SSBN(X) Design Features Although the design of the SSBN(X) has not yet been determined, intended or potential design features include the following: SSBN(X) Design Features Although the design of the SSBN(X) has not yet been fully determined, the boat’s design will reflect the following: Congressional Research Service 10 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress • The SSBN(X) is to be designed for a 40-year expected service life. 3229 • Unlike the Ohio-class design, which requires a mid-life nuclear refueling, the SSBN(X) is to be equipped with a life-of-the-ship nuclear fuel core (a nuclear fuel core that is sufficient to power the ship for its entire expected service life).3330 • The SSBN(X) is to be capable of launching D-5 SLBMs, and consequently is to have launch tubes as large as those on have SLBM launch tubes that are the same size as those on the Ohio class (i.e., tubes with a diameter of 87 inches and a length sufficient tom to accommodate a D-5 SLBM). This would will give the SSBN(X) a beam (i.e., diameter)3431 at least as great as the 42-foot beam of the Ohio-class design, and possibly a bit larger. • Instead of 24 D-5-capable tubes, as on the Ohio-class design, the SSBN(X) is to have 16 D-5-capable tubes. The Navy informed CRS in September 2010 that, as part of its effort to reduce the average unit procurement cost of boats 2 through 12 in the program to $5 billion in constant FY2010 dollars, the Navy was focusing on an SSBN(X) design with 16 tubes rather than 20.35 • A May 2010 CBO report states that “in a recent briefing to CBO and the Congressional Research Service, the Navy stated that an SSBN(X) would probably be about the same size and have roughly the same displacement as an Ohio class submarine, even though it might have only 16 or 20 missile tubes.”36SLBM launch tubes, as on the Ohio-class design, the SSBN(X) is to have 16 SLBM launch tubes. • Although the SSBN(X) is to have fewer launch tubes than the Ohio-class SSBN, it is to have a submerged displacement about the same as that of the Ohio-class design.32 • The Navy states that “owing to the unique demands of strategic relevance, [SSBN(X)s] must be fitted with the most up-to-date capabilities and stealth to ensure they are survivable throughout their full 40-year life span.”3733 Program Acquisition Cost Research and Development Cost A November 2010 DOD report to Congress on strategic nuclear weapon systems stated that research and development costs for the SSBN(X) program for the period FY2011-FY2020 are 32 estimated by DOD at about $11.6 billion in then-year dollars.34 This is not the total estimated research and development cost for the SSBN(X) program, as it excludes research and development costs for FY2010 and prior years (which are shown in Table 3), as well as research and development costs for FY2021 and subsequent years. Given the estimated cost of $11.6 billion in then-year dollars for the period FY2011-FY2020, it is conceivable that the total research 29 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 24. 3330 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 5. The two most recent classes of SSNs—the Seawolf (SSN-21) and Virginia (SSN-774) class boats—are built with cores that are expected to be sufficient for their entire 33-year expected service lives. 3431 Beam is the maximum width of a ship. For Navy submarines, which have cylindrical hulls, beam is the diameter of the hull. 35 Source: Navy information paper dated September 22, 2010, on SSBN(X) program cost reduction effort, provided to CRS by Navy Office of Legislative Affairs on September 23, 2010. 36 Congressional Budget Office, An Analysis of 32 A May 2010 CBO report states that “in a recent briefing to CBO and the Congressional Research Service, the Navy stated that an SSBN(X) would probably be about the same size and have roughly the same displacement as an Ohio class submarine, even though it might have only 16 or 20 missile tubes.” (Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2011 Shipbuilding Plan, May 2010, p. 16. 37) 33 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 24. Congressional Research Service 11 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress estimated by DOD at about $11.6 billion in then-year dollars.38 This is not the total estimated research and development cost for the SSBN(X) program, as it excludes research and development costs for FY2010 and prior years (which are shown in Table 3), as well as research and development costs for FY2021 and subsequent years. Given the estimated cost of $11.6 billion in then-year dollars for the period FY2011-FY2020, it is conceivable that the total research 34 November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10. Congressional Research Service 11 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress and development cost for the program as estimated by DOD might reachapproach $15 billion in then-year thenyear dollars. Procurement Cost The Navy in February 2010 preliminarily estimated the procurement cost of each SSBN(X) at $6 billion to $7 billion in FY2010 dollars—a figure equivalent to roughly one-half of the Navy’s budget each year for procuring new ships.39 On September 14, 2010, DOD stated that the Navy was working to reduce the average unit procurement cost of ships 2 through 12 in the program to $5 billion in FY2010 dollars. DOD stated that an average unit cost of $5 billion would represent a reduction of 27%, implying that the average unit procurement cost of ships 2 through 12 had earlier been estimated at about $6.85 billion in constant FY2010 dollars. DOD stated that, as of September 14, 2010, the cost-reduction effort had reduced the average unit procurement cost of ships 2 through 12 by 16%, implying that the effort as of that date had reduced the average unit procurement cost of the ships to about $5.75 billion. As part of the cost-reduction effort, the number of SLBM tubes on the ship has been reduced from a preliminary figure of 20 to a preliminary figure of 16, with the specific number of SLBM tubes to be determined as part of the program’s Milestone A review. 40 The November 2010 DOD report to Congress on strategic nuclear weapon systems stated that procurement costs for the SSBN(X) program for the period FY2011-FY2020 are estimated by DOD at about $17.8 billion in then-year dollars.41 Given DOD’s planned schedule for procuring SSBN(X)s (see Table 2), this figure likely includes much (but perhaps not all) of the procurement cost for the lead boat in the program, as well as a portion (in the form of advance procurement funding) of the procurement cost of the second boat in the program. A May 2010 CBO report—that is, a report that predates DOD’s September 2010 announcement of the effort to reduce the average unit procurement cost of boats 2 through 12 in the program to $5 billion in constant FY2010 dollars—stated that SSBN(X)s will cost more to procure than the Navy had at that point estimated, and that the program could have a total acquisition cost of more than $110 billion in constant FY2010 dollars: 38 November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10. 39 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 20. 40 Sources: Transcript of September, 14, 2010, DOD news briefing with Under Secretary Ashton Carter, with opening remarks by Secretary of Defense Robert Gates, available online at http://www.defense.gov/transcripts/transcript.aspx? transcriptid=4684, as clarified and elaborated by Navy information paper dated September 22, 2010, on SSBN(X) program cost reduction effort, provided to CRS by Navy Office of Legislative Affairs on September 23, 2010. 41 November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10. Congressional Research Service 12 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Overall, 12 SSBN(X)s would cost a total of about $99 billion [in constant FY2010 dollars to procure] in CBO’s estimation, or an average of $8.2 billion each. Another $10 billion to $15 billion [in constant FY2010 dollars] would be needed for research and development, for a total program cost of more than $110 billion [in constant FY2010 dollars].42 D-5 Missile Refurbishment Cost The above cost figures do not include costs for refurbishing D-5 SLBMs so as to extend their service lives to 2042. Common Missile Compartment (CMC) Current U.S. and UK plans call for the SSBN(X) and the UK’s replacement SSBN to use a missile compartment—the middle part of the boat with the SLBM launch tubes—of the same general design.43 As mentioned earlier (see “U.S.-UK Cooperation on SLBMs”), the UK’s version of this Common Missile Compartment (CMC) is to have 8 missile tubes rather than the 16 or 20 on U.S. version, but the missile tubes are to be the same in both versions. Since the UK’s first Vanguard-class SSBN was originally projected to reach the end of its service life in 2024—three years before the first Ohio-class SSBN is projected to reach the end of its service life—design work on the CMC began about three years sooner than would have been required to support the SSBN(X) program alone. This is the principal reason why the FY2010 budget included a substantial amount of research and development funding for the CMC. The UK is providing some of the funding for the design of the CMC, including a large portion of the initial funding. A March .35 Following the SSBN(X) program’s December 9, 2010, Milestone A acquisition review meeting (see “Program Origin and Milestones”), DOD issued an Acquisition Decision Memorandum (ADM) that, among other things, establishes a target average unit procurement cost for boats 2-12 in the program of $4.9 billion in FY2010 dollars.36 The Navy is working to achieve this target cost, and estimated that, as of early 2011, its cost-reduction efforts had reduced the estimated average unit procurement cost of boats 2-12 to $5.6 billion each in FY2010 dollars.37 The Navy is examining potential further measures to bring the cost of boats 2-12 closer to the $4.9 billion target cost.38 D-5 Missile Refurbishment Cost The above cost figures do not include costs for refurbishing D-5 SLBMs so as to extend their service lives to 2042. Common Missile Compartment (CMC) Current U.S. and UK plans call for the SSBN(X) and the UK’s replacement SSBN to use a missile compartment—the middle part of the boat with the SLBM launch tubes—of the same general design.39 As mentioned earlier (see “U.S.-UK Cooperation on SLBMs”), the UK’s SSBN is to be armed with eight SLBMs, or half the number to be carried by the SSBN(X). The modular design of the CMC will accommodate this difference. Since the UK’s first Vanguard-class SSBN was originally projected to reach the end of its service life in 2024—three years before the first 35 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 20. 36 Christopher J. Castelli, “DOD: New Nuclear Subs Will Cost $347 Billion To Acquire, Operate,” Inside the Navy, February 21, 2011; Elaine M. Grossman, “Future U.S. Nuclear-Armed Vessel to Use Attack-Submarine Technology,” Global Security Newswire, February 24, 2011; Jason Sherman, “Navy Working To Cut $7.7 Billion From Ohio Replacement Program,” Inside the Navy, February 28, 2011. 37 See, for example, Dan Taylor, “Stackley: Navy Will Constantly Seek Ways To Drive Out SSBN(X) Costs,” Inside the Navy, March 7, 2011; and Jason Sherman, “Navy Working To Cut $7.7 Billion From Ohio Replacement Program,” Inside the Navy, February 28, 2011. 38 Additional information on SSBN(X) procurement costs was presented in the November 2010 DOD report to Congress on strategic nuclear weapon systems. The report stated that procurement costs for the SSBN(X) program for the period FY2011-FY2020 were estimated by DOD at that time at about $17.8 billion in then-year dollars. (November 2010 Update to the National Defense Authorization Act of FY2010 Section 1251 Report New START Treaty Framework and Nuclear Force Structure Plans, undated but provided by DOD to CRS on November 18, 2010, p. 10.) Given DOD’s planned schedule for procuring SSBN(X)s (see Table 2), this figure likely includes much (but perhaps not all) of the procurement cost for the lead boat in the program, as well as a portion (in the form of advance procurement funding) of the procurement cost of the second boat in the program. 39 Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 6, which states: “The OHIO Replacement programs includes the development of a common missile compartment that will support both the OHIO Class Replacement and the successor to the UK Vanguard Class.” Congressional Research Service 12 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Ohio-class SSBN is projected to reach the end of its service life—design work on the CMC began about three years sooner than would have been required to support the SSBN(X) program alone. This is the principal reason why the FY2010 budget included a substantial amount of research and development funding for the CMC. The UK is providing some of the funding for the design of the CMC, including a large portion of the initial funding. A March 2010 GAO report stated: According to the Navy, in February 2008, the United States and United Kingdom began a joint effort to design a common missile compartment. This effort includes the participation of government officials from both countries, as well as industry officials from Electric Boat Corporation and BAE Systems. To date, the United Kingdom has provided a larger share of funding for this effort, totaling just over $200 million in fiscal years 2008 and 2009.4440 A May 2010 press report stated that “the UK has, to date, funded the vast majority of [the CMC’s] upfront engineering design activity and has established a significant presence in Electric Boat’s Shaw’s Cove CMC design office in New London, CT.”4541 Under the October 2010 UK defense and security review report (see “U.S.-UK Cooperation on SLBMs”), the UK now plans to deliver its first SSBN in 2028, or about four years later than previously planned. 42 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2011 Shipbuilding Plan, May 2010, p. 16. Statement of Rear Admiral Stephen Johnson, USN, Director, Strategic Systems Programs, Before the Subcommittee on Strategic Forces of the Senate Armed Services Committee [on] FY2011 Strategic Systems, March 17, 2010, p. 6, which states: “The OHIO Replacement programs includes the development of a common missile compartment that will support both the OHIO Class Replacement and the successor to the UK Vanguard Class.” 44 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-10388SP, March 2010, p. 152. 45 Sam LaGrone and Richard Scott, “Deterrent Decisions: US and UK Wait on Next Steps for SSBN Replacements,” Jane’s Navy International, May 2010, pp. 10-11. 43 Congressional Research Service 13 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Program Funding Table 3 shows funding for the SSBN(X) program. The table shows U.S. funding only; it does not include funding provided by the UK to help pay for the design of the CMC. As can be seen in the table, the SSBN(X) program received $497.4 million in research and development funding in the Navy’s FY2010 budget, and the Navy’s proposed FY2011 budget requested an additional $672.3 Navy’s proposed FY2012 budget requests $1,067 million in research and development funding for the program. Table 3. SSBN(X) Program Funding (Millions of then-year dollars, rounded to nearest tenth; totals may not add due to rounding) FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 (req.) FY12 (req.) FY13 (proj.) FY14 (proj.) FY15 (proj.) FY16 (proj.) Research and development (R&D ) funding PE0101221N/Project 3198 0 9.7 0 0 0 0 0 0 0 PE0603561N/Project 3220 0 0 385.9 493.0 755.9 830.8 1,044.4 597.3363.4 493.0 781.6 857.5 1,064.2 786.7 748.8 PE0603561N/Project 9999 4.9 3.2 4.0 0 0 0 0 0 0 PE0603570N/Project 3219 0 0 107.4 179.3 284.1 345.3 402.9 391.8 4.9 12.9 497.4 672.3 1,040.0 1,176.1 1,447.3 9895 179.3 285.4 347.1 405.5 394.7 394.3 4.9 12.9 474.9 672.3 1,067.0 1,204.6 1,469.7 1,181.4 1,143.1 0 0 0 0 0 0 0 954.6736.0 795.2 4.9 12.9 497.4474.9 672.3 1,040.0 1,176.1 1,447.3 1,943.7 Total R&D funding Procurement funding TOTAL all funding Source: Navy data provided to CRS on March 11, 2010, by Navy Office of Legislative Affairs. PE means Program Element, that is, a research and development line item. A Program Element may include several projects. Notes: PE0101221N/Project 3198 is Underwater Launch Missile System (ULMS) project within the PE for Strategic Submarine and Weapons System Support. PE0603561N/Project 3220 is SBSD project within the PE for Advanced Submarine System Development. PE0603561N/Project 9999 is Congressional funding additions within the PE for Advanced Submarine System Development. The figure shown for FY2010 includes two separate additions of $2.0 million each. PE0603570N/Project 3219 is SSBN(X) reactor plant project within the PE for Advanced Nuclear Power Systems. Procurement funding shown in FY2015 is advance procurement funding for first SSBN(X), which is scheduled to be procured in FY2019. Issues for Congress Potential FY2011 issues for Congress include the following: • the accuracy of the Navy’s estimated SSBN(X) unit procurement cost; • the prospective affordability of the SSBN(X) program and its potential impact on other Navy shipbuilding programs; • the impact of UK preferences for the design of its new SSBNs on U.S. consideration of SSBN(X) design options; and • the question of which shipyard or shipyards will build SSBN(X)s. Each of these issues is discussed below. Congressional Research Service 14 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Accuracy of Navy’s Estimated Unit Procurement Cost The accuracy of the Navy’s estimated SSBN(X) unit procurement cost is a key issue in assessing the potential affordability of the SSBN(X) program, including its potential impact on the Navy’s ability to procure other kinds of ships during the years of SSBN(X) procurement. The accuracy of the Navy’s estimate can be assessed in part by examining known procurement costs for other recent Navy submarines—including Virginia (SSN-774) class attack submarines (which are currently being procured), Seawolf (SSN-21) class attack submarines (which were procured prior to the Virginia class), and Ohio (SSBN-726) class ballistic missile submarines—and then adjusting these costs for the SSBN(X) program so as to account for factors such as differences in ship displacement and design features, changes over time in submarine technologies (which can either increase or reduce a ship’s procurement cost, depending on the exact technologies in question), advances in design for producibility (i.e., design features that are intended to make ships easier to build), advances in shipyard production processes (such as modular construction), and changes in submarine production economies of scale (i.e., changes in the total number of attack submarines and ballistic missile submarines under construction at any one time). A May 2010 CBO report on the potential cost of the Navy’s FY2011 30-year shipbuilding program—that is, a report that predates DOD’s September 2010 announcement of the effort to reduce the average unit procurement cost of boats 2 through 12 in the program to $5 billion in constant FY2010 dollars—estimated that a force of 12 SSBN(X)s would have an average unit procurement cost of $8.2 billion in constant FY2010 dollars, or about 14% more than the Navy’s estimate of $7.2 billion in constant FY2010 dollars. The report states: The design, cost, and capabilities of the SSBN(X), the submarine slated to replace the Ohio class, are among the most significant uncertainties in the Navy’s and CBO’s analyses of future shipbuilding. The Navy’s 2007 and 2008 plans assumed that the first SSBN(X) would cost $4.5 billion (in 2010 dollars) and that subsequent ships in the class would cost about $3.4 billion apiece. The 2009 plan explicitly excluded the costs of the SSBN(X) class, although it included 12 of those submarines in its projected inventories. The 2011 plan, in contrast, includes the costs of the SSBN(X) class—with an estimate that highlights the great expense of replacing current ballistic missile submarines and the effect that effort could have on other shipbuilding programs. Specifically, the Navy now estimates that the lead SSBN(X) will cost about $9 billion and that building 12 of the new submarines will cost $86 billion, or an average of about $7.2 billion apiece. The Navy’s 2011 report states that those estimates are “consistent with the escalated cost of the OHIO class SSBN.” However, escalating (that is, inflating) the actual costs of the Ohio class submarines would produce an average cost of only about $3.1 billion per submarine in 2010 dollars. Navy officials subsequently clarified that the service’s estimate is based on the cost to build Ohio class submarines in today’s industry conditions and with today’s technology. Under the 2011 plan, however, the first SSBN(X) would be authorized in 2019 (although advance procurement money would be needed starting in 2015 for items with long lead times). The second submarine would be purchased in 2022, followed by one per year from 2024 to 2033. In most of its recent naval analyses, CBO assumed that the SSBN(X) would be smaller and would carry fewer weapons than existing ballistic missile submarines—specifically, that it would have 16 missile tubes instead of the 24 on today’s SSBNs and would displace around 15,000 tons submerged, compared with 18,750 tons for an existing Ohio class submarine. But in a recent briefing to CBO and the Congressional Research Service, the Navy stated that an SSBN(X) would probably be about the same size and have roughly the same displacement Congressional Research Service 15 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress as an Ohio class submarine, even though it might have only 16 or 20 missile tubes. Over time, technological advancements tend to add weight to a submarine design (compared with the same submarine produced 30 years earlier). If the Ohio class was being built today with the same capability to launch ballistic missiles, it would actually be much larger than 18,750 tons. Thus, a new SSBN with fewer than 24 missile tubes would probably still be equivalent in displacement to an Ohio class submarine. For those reasons, in its analysis, CBO adopted the Navy’s assumption about the size of the SSBN(X). CBO estimates that the lead SSBN(X) will cost about $13 billion if it is purchased in 2019. Estimating the cost of that submarine is particularly difficult because it is not clear how much the Navy will need to spend on nonrecurring engineering and detail design. The Navy spent about $2 billion on those items—out of a total of more than $5 billion—for the lead Virginia class attack submarine, which is about 60 percent smaller than the first Ohio class submarine. CBO assumed that the cost of nonrecurring items would be proportional to the weight of the new submarine, so it estimated more than $4 billion for those items. (The Navy appears to have assumed that nonrecurring items for the lead SSBN(X) would cost about $2 billion.) The historical track record for the lead ship of new classes of submarines in the 1970s and 1980s implies little difference on a per-ton basis between a lead attack submarine (SSN) and a lead SSBN…. If that pattern continued, the per-ton cost of the SSBN(X) would be about the same as that of the first Virginia class SSN. Overall, 12 SSBN(X)s would cost a total of about $99 billion in CBO’s estimation, or an average of $8.2 billion each. Another $10 billion to $15 billion would be needed for research and development, for a total program cost of more than $110 billion. Those estimates appear to differ from the Navy’s mainly because the Navy priced the SSBN(X) as though it were being built today, whereas CBO incorporated the effects that higher shipbuilding inflation would have on submarines built 10 to 20 years from now.46 Program Affordability and Impact on Other Navy Shipbuilding Programs Some observers are concerned that the SSBN(X) program will significantly compound a challenge the Navy faces concerning the affordability of its long-term shipbuilding program. These observers are concerned that procuring 12 SSBN(X)s during the 15-year period FY2019FY2033, as called for in Navy plans, could lead to reductions in procurement rates for other types of Navy ships during those years.47 The Navy’s February 2010 report on its 30-year (FY2011FY2030067.0 1,204.6 1,469.7 1,917.4 1,938.3 Total R&D funding Procurement funding TOTAL all funding 40 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-10388SP, March 2010, p. 152. 41 Sam LaGrone and Richard Scott, “Deterrent Decisions: US and UK Wait on Next Steps for SSBN Replacements,” Jane’s Navy International, May 2010, pp. 10-11. Congressional Research Service 13 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Source: Navy FY2012 budget submission and (for FY2015 and FY2016 procurement funding) Navy data provided to CRS on February 25, 2010, by Navy Office of Legislative Affairs. Notes: PE means Program Element, that is, a research and development line item. A Program Element may include several projects. PE0101221N/Project 3198 is Underwater Launch Missile System (ULMS) project within the PE for Strategic Submarine and Weapons System Support. PE0603561N/Project 3220 is SBSD project within the PE for Advanced Submarine System Development. PE0603561N/Project 9999 is Congressional funding additions within the PE for Advanced Submarine System Development. PE0603570N/Project 3219 is SSBN(X) reactor plant project within the PE for Advanced Nuclear Power Systems. Procurement funding shown in FY2015 and FY2016 is advance procurement funding for first SSBN(X), which is scheduled to be procured in FY2019. Issues for Congress Potential FY2011 issues for Congress for the SSBN(X) program include the following: • the potential impact of a year-long continuing resolution (CR) for FY2011 at FY2010 funding levels on the Navy’s schedule for developing and procuring the SSBN(X); • the likelihood that the Navy will be able to reduce the average procurement cost of boats 2-12 in the program to the target figure of $4.9 billion each in FY2010 dollars; • the accuracy of the Navy’s estimate of the procurement cost of each SSBN(X); • the prospective affordability of the SSBN(X) program and its potential impact on other Navy shipbuilding programs; and • the question of which shipyard or shipyards will build SSBN(X)s. Each of these issues is discussed below. Near-Term Issue: Potential Impact of Year-Long Continuing Resolution One oversight issue for Congress is the potential impact of a year-long continuing resolution (CR) for FY2011 at FY2010 funding levels on the Navy’s schedule for developing and procuring the SSBN(X). As shown in Table 3, the amount of research and development funding requested for the SSBN(X) program for FY2011 ($672.3 million) is about 40% higher than the amount provided for FY2010 ($474.9 million). If SSBN(X) research and development work in FY2011 is funded at FY2010 funding levels, it would likely require the Navy to postpone to some of the work that was scheduled for FY2011. This could make it more difficult for the Navy to complete SSBN(X) development in time to support the procurement of the lead SSBN(X) in FY2019. As discussed earlier (see “Procurement and Replacement Schedule” in “Background”), delaying the procurement of the first boat beyond FY2019 could result in an SSBN force that drops below 12 boats at some point. Likelihood That Navy Will Reach $4.9 Billion Target Cost Another potential oversight issue for Congress is the likelihood that the Navy will be able to achieve DOD’s goal of reducing the average unit procurement cost of boats 2-12 in the program Congressional Research Service 14 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress to $4.9 billion each in FY2010 dollars. As mentioned earlier, as of early 2011, the Navy estimated that its cost-reduction efforts had reduced the average unit procurement cost of boats 2-12 to $5.6 billion each in FY2010 dollars, leaving another $700 million or so in cost reduction to reach the $4.9 billion target cost. Measures that the Navy has taken to reduce the average unit procurement cost of boats 2-12 to about $5.6 billion include, among other things, reducing the number of SLBM launch tubes from 20 to 16, and making the launch tubes no larger in diameter than those on the Ohio-class design. 42 The Navy is examining potential further measures to bring the cost of boats 2-12 closer to the $4.9 billion target cost. Potential oversight questions include the following: • How did DOD settle on the figure of $4.9 billion in FY2010 dollars as the target average unit procurement cost for boats 2-12 in the program? On what analysis was the selection of this figure based? • How difficult will it be for the Navy to reach this target cost? What options is the Navy examining to achieve the additional $700 million or so in unit procurement cost savings needed to reach it? • Would a boat costing $4.9 billion have sufficient capability to perform its intended missions? • What, if anything, does DOD plan to do if the Navy is unable to achieve the $4.9 billion target cost figure? If $4.9 billion is the target figure, is there a corresponding “ceiling” figure higher than $4.9 billion, above which DOD would not permit the SSBN(X) program to proceed? If no such figure exists, should DOD establish one? Accuracy of Navy’s Estimated Unit Procurement Cost Another oversight issue for Congress concerns the accuracy of the Navy’s estimate of the procurement cost of each SSBN(X). The accuracy of the Navy’s estimate is a key consideration in assessing the potential affordability of the SSBN(X) program, including its potential impact on the Navy’s ability to procure other kinds of ships during the years of SSBN(X) procurement. Some of the Navy’s ship designs in recent years, such as the San Antonio (LPD-17) class amphibious ship43 and the Littoral Combat Ship (LCS),44 have proven to be more expensive to build than the Navy originally estimated. The Congressional Budget Office (CBO) in recent years has issued procurement cost estimates for certain Navy ships that are higher than the Navy’s estimates for those ships. The accuracy of the Navy’s estimate can be assessed in part by examining known procurement costs for other recent Navy submarines—including Virginia (SSN-774) class attack submarines (which are currently being procured), Seawolf (SSN-21) class attack submarines (which were 42 The Navy had examined the option of equipping the SSBN(X) with tubes greater in diameter than those on the Ohioclass design, so as to support an option of arming the boats many years from now with a new SLBM that is larger in diameter than the D-5 SLBM. 43 For more on the LPD-17 program, see CRS Report RL34476, Navy LPD-17 Amphibious Ship Procurement: Background, Issues, and Options for Congress, by Ronald O'Rourke. 44 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background, Issues, and Options for Congress, by Ronald O'Rourke. Congressional Research Service 15 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress procured prior to the Virginia class), and Ohio (SSBN-726) class ballistic missile submarines— and then adjusting these costs for the SSBN(X) program so as to account for factors such as differences in ship displacement and design features, changes over time in submarine technologies (which can either increase or reduce a ship’s procurement cost, depending on the exact technologies in question), advances in design for producibility (i.e., design features that are intended to make ships easier to build), advances in shipyard production processes (such as modular construction), and changes in submarine production economies of scale (i.e., changes in the total number of attack submarines and ballistic missile submarines under construction at any one time). The Navy’s estimated unit procurement cost for the program at any given point will reflect assumptions in, among other things, which shipyard or shipyards will build the boats, and how much Virginia-class construction will be taking place in the years when SSBN(X)s are being built. Changing the Navy’s assumption about which shipyard or shipyards will build SSBN(X)s could reduce or increase the Navy’s estimated unit procurement cost for the boats. If shipbuilding affordability pressures result in Virginia-class boats being removed from the 30-year shipbuilding plan during the years of SSBN(X) procurement, the resulting reduction in submarine production economies of scale could make SSBN(X)s more expensive to build than the Navy estimates. Program Affordability and Impact on Other Navy Shipbuilding Programs Even with the Navy’s current effort to reduce the estimated unit procurement cost of the SSBN(X) toward DOD’s target figure, some observers are concerned that the SSBN(X) program could significantly compound a challenge the Navy faces concerning the affordability of its longterm shipbuilding program. These observers are concerned that procuring 12 SSBN(X)s during the 15-year period FY2019-FY2033, as called for in Navy plans, could lead to reductions in procurement rates for other types of Navy ships during those years.45 The Navy’s February 2010 report on its 30-year (FY2011-FY2030) shipbuilding plan states: Recapitalizing the SSBN force will impact the Navy in the mid-term as significant resources are allocated to the SSBN(X) recapitalization program ... these ships require significant resource commitment and they will impact the Navy’s ability to procure other shipbuilding requirements during the period when they are being procured.... The SSBN(X) procurements will be concurrent with wholesale end-of-service-life retirements of SSN 688 submarines, CG 47 class guided missile cruisers, DDG 51 class guided missile destroyers, and LSD 41/49 class dock landing ships. While the SSBN(X) is 46 47 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2011 Shipbuilding Plan, May 2010, pp. 15-16. See, for example, John M. Donnelly, “Cost Of Nuclear Subs Could Sink Navy Budget,” CQ Today, March 2, 2010. Congressional Research Service 16 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress being procured, the Navy will be limited in its ability to procure other ship classes. This slowdown in procurement will occur when the Navy needs to be procuring at least 10 ships per year to maintain its force level against the anticipated ship retirements from the 1980s and 1990s.4846 The report also states: 45 See, for example, John M. Donnelly, “Cost Of Nuclear Subs Could Sink Navy Budget,” CQ Today, March 2, 2010. U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, pp. 24-25. 46 Congressional Research Service 16 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Because of the high expected costs for these important national assets, yearly shipbuilding expenditures during the mid-term planning period [FY2021-FY2030] will average about $17.9B (FY2010$) [$17.9 billion in constant FY2010 dollars] per year, or about $2B more than the steady-state 30-year average. Even at this elevated funding level, however, the total number of ships built per year will inevitably fall because of the percentage of the shipbuilding account which must be allocated for the procurement of the SSBN. In the farterm planning period, average shipbuilding expenditures fall back to a more sustainable level of about $15.3B (FY2010$) average per year. Moreover, after the production run of SSBN(X)s comes to an end in FY 2033, the average number of ships built per year begins to rebound.4947 The Navy’s FY2011 30-year shipbuilding plan includes a total of 276 ships and states that the 12 SSBN(X)s are to be funded within the Navy’s shipbuilding budget.5048 An earlier draft of the 30year plan that was reported in December 2009 suggested that funding the 12 SSBN(X)s within the Navy’s shipbuilding budget without an offsetting increase to the shipbuilding budget would reduce the number of ships in the 30-year plan from 278 to 222—a reduction of 56 ships. The 56 eliminated ships included 19 destroyers, 15 Littoral Combat Ships (LCSs), four SSNs, three amphibious ships, and 15 auxiliary ships.51 In assessing the prospective affordability 49 In addition to making further changes in the design of the SSBN(X), options for reducing the cost of the SSBN(X) program and its potential impact on other Navy shipbuilding programs, Congress may consider the following factors, among others: • the total number of SSBN(X)s that are to be procured; • the design (and thus unit procurement cost) of the SSBN(X); • the program’s potential impact on the Navy’s ability to procure other kinds of ships in desired numbers include the following: • reducing the planned number of SSBN(X)s; • altering the schedule for procuring the SSBN(X)s and the potentialso as to create additional opportunities for using incremental funding for procuring the ships; andhowfunding the procurement of SSBN(X)’s outside the Navy’s shipbuilding budget. Each of these options is discussed below. Reducing the Planned Number of SSBN(X)s Some observers over the years have advocated or presented options for an SSBN force of fewer than 12 SSBNs. The Congressional Budget Office (CBO), for example, has at times in the past presented options for reducing the SSBN force to 10 boats as a cost-reduction measure. 50 A June 2010 report by a group known as the Sustainable Defense Task Force recommends reducing the 47 s is funded in DOD’s budget; and • the potential for increasing the Navy’s shipbuilding budget enough to procure SSBN(X)s without having to reduce procurement rates for other Navy ships. Each of these factors is discussed below. 48 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, pp. 24-25. 49 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 5. 5048 The report states that “funding for the SSBN(X) will be included in the SCN core budget.” (U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, p. 4.) SCN stands for the Shipbuilding and Conversion, Navy appropriation account—the Navy’s shipbuilding budget. 5149 See the tables of the 222- and 278-ship scenarios published in Inside the Navy on December 7, 2009, as well as Christopher J. Castelli, “Navy Confronts $80 Billion Cost Of New Ballistic Missile Submarines,” Inside the Pentagon, December 3, 2009. Congressional Research Service 17 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Number of SSBN(X)s U.S. strategic nuclear deterrence plans require a certain number of strategic nuclear warheads to be available for use on a day-to-day basis. After taking into account warheads on the other two legs of the strategic nuclear triad, as well as the number of warheads on an SSBN’s SLBMs, this translates into a requirement for a certain number of SSBNs to be on station (i.e., within range of expected targets) in Pacific and Atlantic waters at any given moment. The SSBN force is sized to support this requirement. Given the time needed for at-sea training operations, restocking SSBNs with food and other consumables, performing maintenance and repair work on the SSBNs, and transiting to and from deterrent patrol areas, only a fraction of the SSBN force can be on patrol at any given moment. The Navy states that the current requirement for having a certain number of SSBNs on patrol at any given moment translates into a need for 14 Ohio-class boats. The Navy’s report on its 30-year shipbuilding plan notes that the current planned total of 12 SSBN(X)s could change: Current plans call for 12 new SSBN(X)s with life-of-the-hull, nuclear reactor cores to replace the existing 14 OHIO-class SSBNs.... There are many factors influencing this new SSBN that will impact the ship’s maintenance cycle. Resolution of these factors will determine the number of ships required to maintain twelve operational submarines. As a result, until those decisions are made as part of the acquisition process, the procurement plan in this report supports a minimum inventory of 12 SSBNs, for this force. Should the ongoing Nuclear Posture Review change the SSBN requirements, the number of replacement ships may need to be adjusted to accommodate that outcome.... The number of these submarines was delineated by the Nuclear Posture Review 2001 which established the requirement of a force comprised of 12 operational SSBNs (with two additional in overhaul at any time). As highlighted previously, the replacement SSBN program inventory is assumed to be 12 total ships. The Nuclear Posture Review, which is expected to be completed in 2010 will validate the SSBN requirement and will be reflected in future reports.... The Navy has assumed, for the purposes of this report, that there will be no changes in the strategic deterrent posture for sea-based forces beyond those associated with the number of missile tubes in each SSBN(X) hull resulting from the Nuclear Posture Review that will complete in FY 2010.52 It is sometimes said that the current force of 14 Ohio-class boats supports 12 operational boats plus two other boats that are unavailable for operation because they are undergoing mid-life refueling overhauls. Some parts of the above-quoted passage can be read as consistent with that view. Current Navy plans, however, call for all 14 Ohio-class boats to remain in service even after the last Ohio-class mid-life refueling overhaul is completed around 2020, suggesting that maintenance work other than the mid-life refueling overhaul is a consideration. It can also be noted that while the SSBN(X) is to have a life-of-the-ship nuclear fuel core, thus avoiding the need for a mid-life refueling, the SSBN(X) might nevertheless require a lengthy mid-life nonrefueling overhaul. 52 U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010, pp. 5, 10, 15, 20 50 See, for example, Congressional Budget Office, Rethinking the Trident Force, July 1993, 78 pp.; and Congressional Budget Office, Budget Options, March 2000, p. 62. Congressional Research Service 18 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress DOD’s report on the 2010 NPR states: The NPR concluded that ensuring a survivable U.S. response force requires continuous atsea deployments of SSBNs in both the Atlantic and Pacific oceans, as well as the ability to surge additional submarines in crisis. To support this requirement, the United States currently has fourteen nuclear-capable Ohio-class SSBNs. By 2020, Ohio-class submarines will have been in service longer than any previous submarines. Therefore as a prudent hedge, the Navy will retain all 14 SSBNs for the nearterm. Depending on future force structure assessments, and on how remaining SSBNs age in the coming years, the United States will consider reducing from 14 to 12 Ohio-class submarines in the second half of this decade. This decision will not affect the number of deployed nuclear warheads on SSBNs.53 This passage suggests that DOD might consider converting the 13th and 14th Ohio-class SSBNs into submarines that do not carry SSBNs in the second half of this decade, or cancelling their mid-life refueling overhauls and removing them from service. Under current plans, the mid-life refueling overhauls for these two boats might be scheduled for authorization around FY2017 and FY2018. The removal of the 13th and 14th boats from service as SSBNs following the completion of the mid-life refueling overhauls on the other 12 SSBNs would be consistent with the idea that the current force of 14 Ohio-class boats supports 12 operational boats plus two other boats that are unavailable for operation because they are undergoing mid-life refueling overhauls. Some observers over the years have advocated or presented options for an SSBN force of fewer than 12 SSBNs. The Congressional Budget Office (CBO), for example, has at times in the past presented options for reducing the SSBN force to 10 boats as a cost-reduction measure. 54 A June 2010 report by a group known as the Sustainable Defense Task Force recommends reducing the SSBN force to 7 boats;55 and17 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress SSBN force to seven boats;51 a September 2010 report from the Cato Institute recommends reducing the SSBN force to 6 boats.56 A potential question for Congress issix boats.52 Views on whether a force of fewer than 12 SSBN(X)s would provide for an adequate number of SSBNs on deterrent patrol at any given moment. Views on that questionbe adequate could depend on, among other things, assessments of strategic nuclear threats to the United States and the role of SSBNs in deterring such threats as a part of overall U.S. strategic nuclear forces, as influenced by the terms of strategic nuclear arms control agreements.57 53 Reducing the number of SSBNs below 12 could also raise a question as to whether the force should continue to be homeported at both Bangor, WA, and Kings Bay, GA, or consolidated at a single location. DOD’s report on the 2010 NPR states: The NPR conducted extensive analysis of alternative force structures under a New START Treaty, and the Department of Defense will define its planned force structure under the 53 Department of Defense, Nuclear Posture Review Report, April 2010, p. 22. See, for example, Congressional Budget Office, Rethinking the Trident Force, July 1993, 78 pp.; and Congressional Budget Office, Budget Options, March 2000, p. 62. 55 Debt, Deficits, and Defense, A Way Forward[:] Report of the Sustainable Defense Task Force, June 11, 2010, pp. 19-20. 56 Benjamin H. Friedman and Christopher Preble, Budgetary Savings from Military Restraint, Washington, Cato Institute, September 23, 2010 (Policy Analysis No. 667), pp. 8. 57 For further discussion, see CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf. 54 Congressional Research Service 19 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Treaty after taking account of this work. The United States will retain the ability to adjust this posture under New START as needed to account for unexpected technological developments or operational vulnerabilities, or geo-political surprise.58 Design of SSBN(X)s A Design with Fewer Tubes There are many elements of the design of the SSBN(X) that could affect its procurement cost. Other things held equal, a design with fewer SLBM tubes would cost less to procure than a design with more SLBM tubes. The difference in procurement cost resulting from a reduction in the number of SLBM tubes, however, might be relatively modest, since much of the ship’s procurement cost is determined by other parts of the ship, such as the propulsion plant and the ship’s collection of sensors, computers, software, and display systems. Reducing the number of SLBM tubes in the design would likely result in relatively little reduction to the ship’s development and design cost.59 A Design Based on an SLBM Smaller than the D-5 An option that would more substantially reduce the procurement cost of the SSBN(X) would be to design the ship to carry an SLBM that is substantially smaller than the Trident II D-5 SLBM. Such a submarine could be substantially smaller than a submarine designed to carry an equal number of D-5-sized (or larger) SLBMs. A submarine designed to carry a smaller SLBM might be either a modified version of the Virginia-class SSN design60 or an all-new design. The ship could be armed with either newproduction Trident I C-4 SLBMs,61 new-design SLBMs that are about the same size as the Trident I C-4, or (for an all-new submarine design) new-design SLBMs that are larger than the C-4 but still substantially smaller than the D-5. The resulting options (along with the Navy’s current preferred option of a new-design SSBN armed with life-extended D-5s) would be as follows: • a Virginia-based SSBN armed with 16 or 20 new-construction C-4s; • a Virginia-based SSBN armed with 16 or 20 new-design SLBMs about the same size as the C-4; • a new-design SSBN armed with 16 or 20 new-construction C-4s; 58 Department of Defense, Nuclear Posture Review Report, April 2010, p. 25. It might also result in only a modest reduction in the design’s annual operating and support cost. 60 The Virginia-class design has a beam of 34 feet, which is 1 foot greater than the 33-foot beam of the Lafayette/Benjamin Franklin (SSBN-616/640) class SSBNs that carried the Trident I C-4 SLBM. 61 The Navy states that “there are no TRIDENT I (C4) SLBMs available for refurbishment because only a limited number of TRIDENT I (C4) rocket motors remain. TRIDENT I (C4) missile hardware, including equipment sections, nozzles, and avionics, has been disposed of or destroyed. The remaining TRIDENT I (C4) rocket motors are at or near end of life, due to aging solid propellant, and are planned for accelerated disposal due to safety concerns. The TRIDENT I (C4) rocket motors are no longer certified for deployment on manned platforms.” (Navy information paper on SSBNs and SLBMs dated March 24, 2010, and provided to CRS and CBO on March 25, 2010.) 59 Congressional Research Service 20 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress • a new-design SSBN armed with 16 or 20 new-design SLBMs about the same size as the C-4; • a new-design SSBN armed with 16 or 20 new-design SLBMs that are larger than the C-4 but still substantially smaller than the D-5; and • a new-design SSBN armed with 16 or 20 life-extended D-5s. The Navy reportedly has studied in detail the option of a Virginia-based SSBN armed with D-5s, but may not have studied in detail the option of a Virginia-based SSBN armed with newconstruction C-4s or new-design SLBMs about the same size as the C-4. The Navy may also not have studied in detail the option of a new-design SSBN armed with either new-construction C-4s, new-design SLBMs about the same size as the C-4, or new-design SLBMs that are larger than the C-4 but still substantially smaller than the D-5. Potential questions for Congress include the following: • What are the combined submarine and missile acquisition (i.e., development and procurement) costs of each of the six options listed above? • What are the combined submarine and missile development risks of each of the above six options? • What are the resulting capabilities of each of the above six options, and how do these capabilities compare to requirements for performing the strategic nuclear deterrence mission in coming years? • How well does the Navy understand the comparative acquisition costs, development risks, and resulting capabilities of the above six options if the Navy has not studied in detail the option of an SSBN designed for SLBMs about the same size as the C-4 (or larger than the C-4 but still substantially smaller than the D-5), and if it has not studied in detail the potential costs, risks, and capabilities of a new-design SLBM that is about the same size as the C-4, or larger than the C-4 but still substantially smaller than the D-5? A May 2010 press report states: So far, the USN is revealing little about the [SSBN(X)] AoA findings, although the service has ruled out suggestions that its Virginia-class attack submarine could for the template for a next-generation SSBN(X), according to sources familiar with the study. Proposals for a Virginia Block IV variant – with a missile compartment for the D5 ballistic nuclear missile or a successor weapon – were examined by officials but declared not feasible due to infrastructure and missile design costs, one source said. In particular, it was determined that inserting a new 30 m [30-meter] hull section into the existing Virginia design to accommodate Trident [SLBMs] would cost as much as developing an entirely new SSBN, another source added.62 62 Sam LaGrone and Richard Scott, “Deterrent Decisions: US and UK Wait on Next Steps for SSBN Replacements,” Jane’s Navy International, May 2010: 10-11. Congressional Research Service 21 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Regarding the option of a Virginia-based SSBN design (apparently one armed with D-5s, given the reference below to a stepped pressure hull), the Navy states that the VIRGINIA Class design could be modified into an SSBN that carries SLBMs. This would require designing a missile compartment insert with missile tubes and other supporting systems. The missile compartment would likely have a larger pressure hull diameter than the VIRGINIA pressure hull (34 feet), resulting in a stepped pressure hull configuration. However, a VIRGINIA Insert SSBN would require redesign of the VIRGINIA and would have technical and operational shortcomings and risks. The increase in ship size for the modified ship would result in a loss in speed. Ship systems such as electric power, air conditioning, and chill water would have limitations, and the propulsor would require redesign. The increase in ship length would limit maneuvering performance without redesign of stern control surfaces and the ship control system. The VIRGINIA Insert SSBN would also have shortcomings in meeting speed and stealth performance parameters and maintainability requirements for the strategic mission.63 At a July 22, 2010, hearing before the House Armed Services Committee on managing DOD in a time of tight budgets, the following exchange occurred between the Representative Ike Skelton, the chairman of the committee, and Robert Work, the Under Secretary of the Navy: SKELTON: …. Mr. Work, recently I asked the proposed price tag on a replacement vessel for the Ohioclass submarine. Has the Navy done any studies on whether a replacement, such as the Virginia-class submarine, can perform the same duties with obviously an alteration in the missiles and the ship somewhat? WORK: Yes, sir, we have. Secretary Mabus, when he came aboard last year, and I were first given the briefing on how much this boat could potentially cost, this became one of his focus items from day one. 63 Navy information paper on SSBNs and SLBMs dated March 24, 2010, and provided to CRS and CBO on March 25, 2010. The Navy states elsewhere in the paper that “the Sea Based Strategic Deterrent (SBSD) Analysis of Alternatives (AoA) investigated a series of options including modified VIRGINIA hulls and an updated OHIO Class design,” and that: Based on historical SSBN to SLBM and SLBM Length-to-Diameter (L/D) ratios, a 74-inch diameter SLBM is likely the largest diameter feasible for a new VIRGINIA-Class-based SLBM design in the 35 to 36 foot length range. This missile would be similar to a TRIDENT I (C4); however, the range would be substantially reduced relative to D5 performance. A VIRGINIA Insert SSBN would require redesign of the VIRGINIA and has shortcomings in meeting speed and stealth performance parameters and maintainability requirements for the strategic mission…. The VIRGINIA Class SSN was not designed to serve as a strategic deterrent platform. The Navy has considered a range of VIRGINIA Class Insert designs; however, early design studies concluded that they were not viable options as they would require redesign of the VIRGINIA and had shortcomings in meeting speed and stealth performance, and maintainability requirements for the strategic mission. Congressional Research Service 22 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress For the last year, the AOA, the Analysis of Alternatives for the submarines has occurred. The judgment is that, because we have elected to go with the D-5 missile, that using the Virginia is not the right way to go, that it is a much better and more efficient thing to exploit our existing infrastructure on a 42- or 43-foot diameter hull. Once that decision was made, Secretary Mabus has asked every single requirement, what is the basis for that requirement, and what is the thing that is driving the cost in the boat. I don't have a final answer for you, Mr. Chairman, but this is at Secretary Mabus’s level, and I can assure you that we will have an affordable boat that we can afford in the 20s. SKELTON: Well, what’s interesting, based upon your testimony today, the missile’s driving the boat. Have you asked engineers to redesign a missile that might fit on a Virginia-class submarine? This isn't brain surgery. Have you done that? WORK: Sir, I'll have to come back and see if we have done an actual costing, but at the office of the secretary of defense level, it really was [a question of: whether we] can we afford to design a whole new missile mount [sic], and the decision was to stick with the D-5 through about 2040. And that will sustain our solid rocket motor base industry. It will take advantage of all of the investments that we've had up to this point. And we believe that is the cheaper – excuse me, the most inexpensive and the right way to go.64 Regarding the potential cost to develop a new SLBM, the Navy states: Development of a new SLBM has not been priced because there is no Navy plan to develop a new nuclear capable SLBM and has no recent experience with an end-to-end missile development and production program.… The TRIDENT II (D5) missile, which achieved IOC [initial operational capability] in 1990, was the 6th generation of continuous strategic missile development programs since 1956. The development cost of the TRIDENT II (D5) missile in the 1980’s was $8.4B (in FY83 dollars)65 and included 19 missile land flat pad flights and 9 submarine launched flights using a fully experienced design and production industrial base. Detailed budgetary estimates for a new missile development program would require significant work to define performance needs before budget profiles and timelines could be developed. The development cost of TRIDENT II (D5) cannot be escalated as an estimate, as the industrial base and technology have changed substantially. No detailed SLBM design and development work has been conducted in over 20 years. In general, much of the SLBM production industrial base is available in a diminished form. The TRIDENT II (D5) was the fifth SLBM developed within the span of 25 years; the development of a new SLBM today would mark the first new U.S. SLBM developed since completion of D5 development in the early 1990‘s. Solid Rocket Motor production has 64 Source: Transcript of hearing. Although the Navy states later in this passage that “the development cost of TRIDENT II (D5) cannot be escalated as an estimate, as the industrial base and technology have changed substantially,” it can be noted, for reference purposes, that a figure of $8.4 billion in constant FY1983 dollars equates to about $16.1 billion in constant FY2011 dollars, using the deflator for RDT&E budget authority in Department of Defense, National Defense Budget Estimates, March 2010, Table 5-6 (page 47) . 65 Congressional Research Service 23 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress decreased substantially due to decreased demand from NASA, the U.S. Air Force and the U.S. Navy.66 At a May 6, 2010, hearing on Navy shipbuilding programs before the Seapower subcommittee of the Senate Armed Services Committee, Vice Admiral John Terence Blake, Deputy Chief of Naval Operations for Integration of Capabilities and Resources, discussed, in response to a question from Senator Jack Reed, the Navy’s desire to extend the service lives of the D-5 missiles and design the SSBN(X) to launch D-5s, rather than develop a new SLBM for the SSBN(X). The text of the exchange is as follows: SENATOR REED: I think there’s a temptation when you're looking at a new platform to make it capable of doing everything. That’s expensive, typically. So there’s always a trade-off between capability and expense. How are you dealing with those two issues? BLAKE: Well, one of the ways we're looking at it is we're looking to see, first of all, what capability we want to have in the vessel. Let me use the D-5 program as an example. We determined that based on the success of the D-5 program that we should take the D-5 program and put an extension program in place so that we would be able to utilize that system and the reliability and the security that it gave us out into the 2040 timeframe. And so what we—we also felt that if you go back in history and you look, you'll remember that the previous program, the C-4 program, was a less capable system, and the D-5 was then designed, if you will, in the late ‘70s and early ‘80s. So what we decided was in order to minimize risk, we would go to the D-5 [life-extension] program, as opposed to starting up [a new SLBM development effort], since we have not since the late ‘70s, early ‘80s done any missile design work with respect to a SSBN weapons system, and therefore we would continue down the path of using the D-5. So the idea was to keep it within an affordability [constraint], because if you go back in history, if we hadn't gone down that path [of extending the lives of the D-5s], then we were going to have to rebuild the [SLBM] infrastructure, the design and everything else [infrastructure], because we hadn't done that [i.e., designed a new SLBM] in several decades. So the idea was to make it affordable and to make it less risky, if you will. And that was— that’s just one example, if you will.67 The Trident I C-4 SLBM was less accurate and had substantially less range/payload than the Trident II D-5 SLBM. The Navy states that “the range of a TRIDENT II (D5) missile is approximately 45% greater than that of TRIDENT I (C4) for an equivalent payload. The D5 missile was also considerably more accurate than the C4 missile and can host a larger payload.”68 66 Navy information paper on SSBNs and SLBMs dated March 24, 2010, and provided to CRS and CBO on March 25, 2010. 67 Source: Transcript of hearing. 68 Navy information paper on SSBNs and SLBMs dated March 24, 2010, and provided to CRS and CBO on March 25, (continued...) Congressional Research Service 24 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress New-production C-4s or a new-design SLBM that is smaller than a D-5, however, might be equipped with a guidance system that is more modern and more accurate than the guidance system on the original C-4. Since a C-4 missile (or a new-design SLBM smaller than the D-5) would have less range/payload than a D-5, an SSBN armed with Trident I C-4 SLBMs or equivalent-sized missiles consequently could have less ability to hold at risk targets in other countries than would an SSBN armed with an equivalent number of Trident II D-5 SLBMs. Assessments of how the capabilities of the above six options listed earlier would compare to requirements for performing the strategic nuclear deterrence mission in coming years could depend on, among other things, assessments of strategic nuclear threats to the United States and the role of SSBNs in deterring such threats as a part of overall U.S. strategic nuclear forces, as influenced by the terms of strategic nuclear arms control agreements.69 Views on this issue could also depend on the accuracy of a new guidance system for the C-4 or a new-design SLBM, and on whether the range/payload capacity of the D-5 missile would need to be fully used to meet future requirements for nuclear deterrence. The Navy states that the range and accuracy of the D5 “make the D5 missile uniquely critical to supporting the requirements of USSTRATCOM as the supported Combatant Commander.”70 An additional consideration is how a decision to design the SSBN(X) around an SLBM smaller than the D-5 would affect the UK’s plan to have its replacement SSBNs carry D-5s, and U.S. costs for supporting that plan. Schedule for Procuring SSBN(X)s and Potential for Using Split single location. U.S. strategic nuclear deterrence plans require a certain number of strategic nuclear warheads to be available for use on a day-to-day basis. After taking into account warheads on the other two legs of the strategic nuclear triad, as well as the number of warheads on an SSBN’s SLBMs, this translates into a requirement for a certain number of SSBNs to be on station (i.e., within range of expected targets) in Pacific and Atlantic waters at any given moment. The SSBN force is sized to support this requirement. Given the time needed for at-sea training operations, restocking SSBNs with food and other consumables, performing maintenance and repair work on the SSBNs, and transiting to and from deterrent patrol areas, only a fraction of the SSBN force can be on patrol at any given moment. The Navy’s position is that the requirement for having a certain number of SSBNs on patrol at any given moment translates into a need for a force of 14 Ohio-class boats, and that this requirement can be met in the future by a force of 12 SSBN(X)s. Altering the Schedule for Procuring SSBN(X)s to Make More Use of Incremental Funding Another option for managing the potential impact of the SSBN(X) program on other Navy shipbuilding programs would be to stretch out the schedule for procuring SSBN(X)s and make greater use of split funding (i.e., two-year incremental funding) in procuring them.7154 This option would not reduce the total procurement cost of the SSBN(X) program—to the contrary, it might increase the program’s total procurement cost somewhat by reducing production learning curve benefits in the SSBN(X) program.7255 This option could, however, reduce the impact of the SSBN(X) program on the amount of funding available for the procurement of other Navy ships in certain individual years. This might reduce the amount of disruption that the SSBN(X) program causes to other shipbuilding programs in those years, which in turn might avoid certain disruption-induced cost increases for those other programs. The annual funding requirements for the SSBN(X) program might be further spread out by funding some of the SSBN(X)s with threeor four-year incremental funding.73 (...continued) 2010. 6956 51 Debt, Deficits, and Defense, A Way Forward[:] Report of the Sustainable Defense Task Force, June 11, 2010, pp. 19-20. 52 Benjamin H. Friedman and Christopher Preble, Budgetary Savings from Military Restraint, Washington, Cato Institute, September 23, 2010 (Policy Analysis No. 667), pp. 8. 53 For further discussion, see CRS Report RL33640, U.S. Strategic Nuclear Forces: Background, Developments, and Issues, by Amy F. Woolf. 70 Navy information paper on SSBNs and SLBMs dated March 24, 2010, and provided to CRS and CBO on March 25, 2010. 7154 Under split funding, a boat’s procurement cost is divided into two parts, or increments. The first increment would be provided in the fiscal year that the boat is procured, and the second would be provided the following fiscal year. 7255 Procuring one SSBN(X) every two years rather than at the Navy’s planned rate of one per year could result in a loss of learning at the shipyard in moving from production of one SSBN to the next. 7356 The Navy, with congressional support, currently uses split funding to procure large-deck amphibious assault ships (i.e., LHAs). The Navy currently is permitted by Congress to use four-year incremental funding only for procuring the first three Ford (CVN-78) class carriers (i.e., CVN-78, CVN-79, and CVN-80); the authority was granted in Section 121 of the FY2007 defense authorization act [H.R. 5122/P.L. 109-364 of October 17, 2006]).continued...) Congressional Research Service 2518 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Table 4 shows the Navy’s currently planned schedule for procuring 12 SSBN(X)s and a notional alternative schedule that would start two years earlier and end two years later than the Navy’s currently planned schedule. Although the initial ship in the alternative schedule would be procured in FY2017, it would be executed as it if were funded in FY2019. Subsequent ships in the alternative schedule that are funded earlier than they would be under the Navy’s currently planned schedule could also be executed as if they were funded in the year called for under the Navy’s schedule. Congress in the past has funded the procurement of ships whose construction was executed as if they had been procured in later fiscal years.7457 The ability to stretch the end of the procurement schedule by two years, to FY2035, could depend on the Navy’s ability to carefully husband the use of the nuclear fuel cores on the last two Ohio-class SSBNs, so as to extend the service lives of these two ships by one or two years. Alternatively, Congress could grant the Navy the authority to begin construction on the 11th boat a year before its nominal year of procurement, and the 12th boat two years prior to its nominal year of procurement. (...continued) (i.e., LHAs). The Navy currently is permitted by Congress to use four-year incremental funding for procuring the first three Ford (CVN-78) class carriers (i.e., CVN-78, CVN-79, and CVN-80); the authority was granted in Section 121 of the FY2007 defense authorization act [H.R. 5122/P.L. 109-364 of October 17, 2006]). 57 Congress funded the procurement of two aircraft carriers (CVNs 72 and 73) in FY1983, and another two (CVNs 74 and 75) in FY1988. Although CVN-73 was funded in FY1983, it was built on a schedule consistent with a carrier funded in FY1985; although CVN-75 was funded in FY1988, it was built on a schedule consistent with a carrier funded in FY1990 or FY1991. Congressional Research Service 19 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Table 4. Navy SSBN(X) Procurement Schedule and a Notional Alternative Schedule Fiscal year Navy’s Schedule Boat might be particularly suitable for 2-, 3-, or 4-year incremental funding 2017 Notional alternative schedule Boat might be particularly suitable for 2-, 3-, or 4-year incremental funding 1 X 1 X 1 X 1 X 2018 2019 1 X 2020 2021 2022 1 X 2023 2024 1 2025 1 1 2026 1 1 2027 1 1 2028 1 1 2029 1 1 X 2030 1 2031 1 X 1 X 2032 1 X 2033 1 X 1 X 1 X 2034 2035 Total 12 12 74 Congress funded the procurement of two aircraft carriers (CVNs 72 and 73) in FY1983, and another two (CVNs 74 and 75) in FY1988. Although CVN-73 was funded in FY1983, it was built on a schedule consistent with a carrier funded in FY1985; although CVN-75 was funded in FY1988, it was built on a schedule consistent with a carrier funded in FY1990 or FY1991. Congressional Research Service 26 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Source: Navy’s current plan is taken from U.S. Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2011, February 2010. Potential alternative plan prepared by CRS. Notes: Notional alternative schedule could depend on Navy’s ability to carefully husband the use of the nuclear fuel cores on the last two Ohio-class SSBNs, so as to extend the service lives of these two ships by one or two years. Alternatively, Congress could grant the Navy the authority to begin construction on the 11th boat a year before its nominal year of procurement, and the 12th boat two years prior to its nominal year of procurement. Under Navy’s schedule, boat to be procured un FY2031 might be particularly suitable for 4-year incremental funding, and boat to be procured in FY2032 might be particularly suitable for 3- or 4-year incremental funding. How Procurement of SSBN(X)s Is Funded in DOD’s Budget Procure SSBN(X)s Outside Navy’s Shipbuilding Budget Another option that some observers have suggested for reducing the potential impact of the SSBN(X) program on other Navy shipbuilding programs would be to fund the procurement of SSBN(X)s through a part of the DOD budget other than the Navy’s shipbuilding account. There would be some precedent for such an arrangement: Procuring SSBN(X)s Outside Navy’s Shipbuilding Budget Some observers have suggested funding the procurement of SSBN(X)s outside the Navy’s shipbuilding budget, so as to preserve Navy shipbuilding funds for other Navy shipbuilding programs. Among those who have raised this idea are Admiral Gary Roughead, the Chief of Naval Operations (CNO).58 There would be some precedent for such an arrangement: 58 See, for example, Jason Sherman, “Roughead Wants SSBN(X) Program Funding Outside Shipbuilding Budget,” Inside the Navy, February 14, 2011. Congressional Research Service 20 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress • DOD sealift ships and Navy auxiliary ships are funded in the National Defense Sealift Fund (NDSF), a part of DOD’s budget that is outside the Navy’s shipbuilding budget (and also outside the procurement title of the DOD appropriations act). • Most spending for ballistic missile defense (BMD) programs (including procurement-like activities) is funded through the Defense-Wide research and development account rather than through the research and development and procurement accounts of the individual military services. A rationale for funding DOD sealift ships in the NDSF is that DOD sealift ships perform a transportation mission that primarily benefits services other than the Navy, and therefore should not be forced to compete for funding in a Navy budget account that funds the procurement of ships central to the Navy’s own missions. A rationale for funding BMD programs together in the Defense-Wide research and development account is that this makes potential tradeoffs in spending among various BMD programs more visible and thereby helps to optimize the use of BMD funding. As a reference tool for better understanding DOD spending, DOD includes in its annual budget submission a presentation of the DOD budget reorganized into 11 program areas, of which one is strategic forces. The FY2011 budget submission, for example, shows that the strategic forces program area received about $12.6 billion in funding in FY2010, and that about $11.1 billion is requested for the program area for FY2011.7559 Supporters of funding the procurement of SSBN(X)s through a part of the DOD budget other than outside the Navy’s shipbuilding budget might argue that this could help protect funding for other Navy 75 Department of Defense, National Defense Budget Estimates For FY 2011, March 2010, Table 6-4, “Department of Defense TOA by Program,” page 79. See also Table 6-5 on page 80, which presents the same data in constant FY2011 dollars. The other 10 program areas in addition to strategic forces are general purpose forces; C3, intelligence and space; mobility forces; guard and reserve forces; research and development; central supply and management; training, medical and other; administration and associated; support of other nations; and special operations forces. (A 12th category—undistributed—shows relatively small amounts of funding.) Congressional Research Service 27 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress shipbuilding programs by avoiding the need for those other shipbuilding programs to compete for scarce Navy shipbuilding funds against a strategic nuclear forces program of high national priority. They might argue that this could help protect funding for other Navy shipbuilding programs. They could also argue that creating a new budget account for strategic nuclear forces of all kinds could help DOD better view potential tradeoffs in spending for various strategic nuclear forces forces programs and thereby help DOD better optimize the use of strategic forces funding. Skeptics of funding the procurement of SSBN(X)s through a part of the DOD budget other than outside the Navy’s shipbuilding budget could argue that it might do little to protect funding for other Navy shipbuilding programs, because if DOD were to move the SSBN(X)s out of the Navy’s shipbuilding budget, DOD might also remove from the shipbuilding budget remove the funding that was there for the SSBN(X)s. They might also argue that shifting SSBN(X)s out of the Navy’s shipbuilding budget would make it harder to track and maintain oversight over Navy shipbuilding activities, and that creating a new budget account for strategic nuclear forces of all kinds could endanger the SSBN(X) program by making it more visible to those who might support reduced spending on nuclear-weapon-related programs. A March 11, 2010, press report stated: “The massive cost of replacing the Navy’s nuclear ballistic missile submarines will be shouldered in the coming years by diverting funds from other naval and Pentagon programs and perhaps by boosting the defense budget, but the program should not get its own special funding stream, according to Deputy Defense Secretary William Lynn.”76 Shift SSBN(X) DD/NRE Costs Outside Navy’s Shipbuilding Budget A second option relating to where in the budget the procurement of SSBN(X)s are funded would be to fund the detailed design and nonrecurring engineering (DD/NRE) costs of the SSBN(X) program through the Navy’s research and development budget rather than the Navy’s shipbuilding budget. It is a long-standing budgeting practice in Navy shipbuilding to attach the DD/NRE costs of a Navy shipbuilding program to the procurement cost of the first ship in a class (or sometimes the first two ships in the class). DD/NRE work, however, might be viewed as research and development work that would be more suitably funded in the Navy’s research and development account. Since the DD/NRE costs of the SSBN(X) program will likely exceed $1 billion, shifting the funding of these costs to the Navy’s research and development account could reduce the procurement cost of the first SSBN(X) as it appears in the Navy’s shipbuilding budget. Shifting the SSBN(X) program’s DD/NRE costs to the Navy’s research and development account, however, could increase funding pressure on other Navy research and development programs. Opponents of this approach could also argue that this option would do nothing to reduce the procurement cost of the second and succeeding ships in the class. Shift SSBN(X) Nuclear Fuel Core Costs Outside Navy’s Shipbuilding Budget A third option relating to where in the budget the procurement of SSBN(X)s are funded would be to shift the cost of SSBN(X) nuclear fuel cores from the Navy’s shipbuilding account to the Operations and Maintenance, Navy (OMN) account or the Other Procurement, Navy (OPN) account. It is a long-standing budgeting practice in Navy shipbuilding to include the cost of the initial nuclear fuel core for a nuclear-powered ship in the procurement cost of that ship. A ship’s 76 Christopher J. Castelli, “Lynn: Navy, DOD To Shoulder SSBN(X) Cost Without Separate Fund,” Inside the Pentagon, March 11, 2010. Congressional Research Service 28 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress nuclear fuel core, however, is the functional equivalent of the fossil fuel used by a conventionally powered Navy ship. Fossil fuel is not included in the procurement cost of conventionally powered Navy ships; it is instead funded on an annual basis through the OMN account. Since an SSBN(X) nuclear fuel core will likely cost a few hundred million dollars,77 shifting the cost of SSBN(X) nuclear fuel cores from the Navy’s shipbuilding account to the OMN or OPN account could marginally reduce the procurement cost of each SSBN(X) as it appears in the Navy’s shipbuilding account. It could also, however, marginally increase funding pressure on other programs funded through the OMN or OPN account. Potential for Increasing Shipbuilding Budget Another factor for Congress to consider is the potential for increasing the Navy’s shipbuilding budget enough to procure SSBN(X)s without having to reduce procurement rates for other Navy ships. Supporters of this option could argue that SSBNs have a procurement cost comparable to that of aircraft carriers, and that the Navy’s shipbuilding budget in the past has sometimes been allowed to “spike” upward in the year that a carrier was procured, so as to permit the Navy to procure the carrier without having to reduce other Navy shipbuilding programs in that year. They could also argue that if the Navy’s shipbuilding budget is not increased to accommodate the cost of the SSBN(X)s, the resulting reductions to other Navy shipbuilding programs could be substantial enough to significantly reduce the Navy’s ability to carry out its other missions. Skeptics could argue that aircraft carries in recent years have been funded through incremental funding rather than allowing the Navy’s shipbuilding budget to “spike” upward in a single year, and that increasing the shipbuilding budget significantly for a period of about 15 years to accommodate the SSBN(X) program would not be the same as allowing the shipbuilding budget to spike upward for a single year. Skeptics could also argue that unless the Navy’s overall budget were increased, increasing the Navy’s shipbuilding account would require reducing funding for other Navy programs, such as aircraft procurement programs, and that such reductions could reduce the Navy’s ability to carry out its other missions. Impact of UK Preferences for Its SSBN on U.S. Consideration of SSBN(X) Design Options As mentioned earlier: • The SSBN(X) program can be traced to an exchange of letters in December 2006 between President George W. Bush and UK Prime Minister Tony Blair concerning the UK’s desire to participate in a program to extend the service life of the Trident II D-5 SLBM into the 2040s, and to have its next-generation SSBNs carry D-5s. 77 As of 2007, a nuclear fuel core for a Virginia-class SSN cost about $170 million in FY2007 dollars, and a nuclear fuel core for a reactor on a Nimitz (CVN-78) or Ford (CVN-78) class aircraft carrier cost about $330 million in FY2007 dollars. (Nimitz- and Ford-class carriers are each powered by two reactors, so the total cost for a set of nuclear fuel cores for each carrier would be about $660 million in FY2007 dollars.) (Source: Naval Reactors telephone conversation with CRS on March 8, 2007.) Congressional Research Service 29 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress • GAO reported in March 2010 that the joint U.S.-UK effort to design the Common Missile Compartment (CMC) for the SSBN(X) and the UK’s new SSBNs began in February 2008. • The SSBN(X) analysis of alternatives (AOA) reportedly began in the summer or fall of 2008. In addition, a May 2010 press report states that the SSBN(X)’s hull diameter, and the diameter of its SLBM launch tubes, “were agreed between the US and UK in 2008.”78 Potential oversight questions for Congress arising from the above points include the following: • Did the UK’s desire for its replacement SSBNs to carry D-5s, combined with the timing of the start of the CMC design effort relative to the start of the SSBN(X) AOA, exert too much, too little, or about the right amount of influence on the range of SSBN(X) design alternatives that the United States was interested in fully exploring? • More specifically, did the UK’s desire for its replacement SSBNs to carry D-5s, combined with the timing of the start of the CMC design effort relative to the start of the SSBN(X) AOA, prematurely incline the United States toward not exploring, or toward negative evaluations of, SSBN(X) design concepts featuring SLBM launch tubes smaller than those on the Ohio-class design? • Did the SSBN(X) AOA fully explore and analyze the option of an all-new SSBN design (as opposed to a modification of the Virginia-class design) featuring SLBM launch tubes smaller than those on the Ohio-class design? If not, was this in part because of the UK’s desire for its replacement SSBNs to carry D-5s and/or the timing of the start of the CMC design effort relative to the start of the SSBN(X) AOA? • Did the Navy rely too much, too little, or about the right amount on the UK’s preference for its replacement SSBNs to carry D-5s, and on the fact that the CMC design effort is now underway, as an argument for responding to questions about the Navy’s desire to design the SSBN(X) with SLBM launch tubes as large as those on the Ohio-class design? • Since the December 2006 exchange of letters between President George W. Bush and UK Prime Minister Tony Blair predates the late-2008 U.S. financial-sector crisis and the subsequent change in projected U.S. federal budget deficits (which in turn might influence future U.S. defense spending levels), should the views expressed in those letters be reexamined? 78 Sam LaGrone and Richard Scott, “Deterrent Decisions: US and UK Wait on Next Steps for SSBN Replacements,” Jane’s Navy International, May 2010: 10-11. Congressional Research Service 3060 59 Department of Defense, National Defense Budget Estimates For FY 2011, March 2010, Table 6-4, “Department of Defense TOA by Program,” page 79. See also Table 6-5 on page 80, which presents the same data in constant FY2011 dollars. The other 10 program areas in addition to strategic forces are general purpose forces; C3, intelligence and space; mobility forces; guard and reserve forces; research and development; central supply and management; training, medical and other; administration and associated; support of other nations; and special operations forces. (A 12th category—undistributed—shows relatively small amounts of funding.) 60 Christopher J. Castelli, “Lynn: Navy, DOD To Shoulder SSBN(X) Cost Without Separate Fund,” Inside the Pentagon, March 11, 2010. Congressional Research Service 21 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Construction Shipyard(s) Building SSBN(X)s Another potential issue for Congress regarding the SSBN(X) program is which shipyard or shipyards would build SSBN(X)s. Two U.S. shipyards are capable of building nuclear-powered submarines—General Dynamics’ Electric Boat Division of Groton, CT, and Quonset Point, RI (GD/EB), and the shipyard at Newport News, VA, that currently forms part of Northrop Grumman Grumman Shipbuilding (NGSB/NN). GD/EB’s primary business is building nuclear-powered submarines; it can also perform submarine overhaul work. NGSB/NN’s primary lines of business are building nuclear-powered aircraft carriers, building nuclear-powered submarines, and performing overhaul work on nuclear-powered aircraft carriers. Table 5 shows the numbers of SSBNs built over time by GD/EB, NGSB/NN, and two government-operated naval shipyards (NSYs)—Mare Island NSY, located in the San Francisco Bay area, and Portsmouth NSY of Portsmouth, NH, and Kittery, ME. Mare Island NSY is no longer in operation. NSYs have not built new Navy ships since the early 1970s; since that time, they have focused solely on overhauling and repairing Navy ships. As can be seen in the table, the Ohio-class boats were all built by GD/EB, and the three previous SSBN classes were built partly by GD/EB, and partly by NGSB/NN. GD/EB was the builder of the first boat in all four SSBN classes. The most recent SSBNs built by NGSB/NN were the George C. Marshall (SSBN-654) and George Washington Carver (SSBN-656), which were Lafayette/Benjamin Franklin-class boats that were procured in FY1964 and entered service in 1966. Table 5. Construction Shipyards of U.S. SSBNs George Washington (SSBN-598) class Ethan Allen (SSBN-608) class Lafayette/ Benjamin Franklin (SSBN616/640) class Ohio (SSBN-726) class FY58-FY59 FY59 and FY61 FY61-FY64 FY77-FY91 Number built by GD/EB 2 2 13 18 Number built by NGSB/NN 1 3 10 Number built by Mare Island NSY 1 6 Number built by Portsmouth NSY 1 2 Total number in class 5 Fiscal years procured 5 31 18 Source: Prepared by CRS based on data in Norman Polmar, The Ships and Aircraft of the U.S. Fleet, Annapolis, Naval Institute Press, various editions. NSY means naval shipyard. Notes: GD/EB was the builder of the first boat in all four SSBN classes. The George Washington-class boats were procured as modifications of SSNs that were already under construction. A total of 18 Ohio-class SSBNs were built; the first four were converted into SSGNs in 2002-2008, leaving 14 in service as SSBNs. There are at least five basic possibilities for building SSBN(X)s: • build all SSBN(X)s at GD/EB—the approach that was used for building the Ohio-class SSBNs; Congressional Research Service 3122 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress • build all SSBN(X)s at NGSB/NN; • build some SSBN(X)s GD/EB and some at NGSB/NN—the approach that was used for building the George Washington-, Ethan Allen-, and Lafayette/Benjamin Franklin-class SSBNs; • build each SSBN(X) jointly at GD/EB and NGSB/NN, with final assembly of the boats alternating between the yards—the approach currently being used for building Virginia-class SSNs;7961 and • build each SSBN(X) jointly at GD/EB and NGSB/NN, with one yard—either GD/EB or NGSB/NN—performing final assembly on every boat. In assessing these five approaches, policymakers may consider a number of factors, including their potential costs, their potential impacts on employment levels at GD/EB and NGSB/NN, and the relative value of preserving SSBN-unique construction skills (such as those relating to the construction and installation of SLBM compartments) at one shipyard or two. The relative costs of these five approaches could depend on a number of factors, including the following: • each yard’s share of SSBN(X) production work (if both yards are involved); • the number of SSNs procured during the years of SSBN(X) procurement (which can affect economies of scale in submarine production); • whether the current joint-production arrangement for the Virginia class remains in effect during those years (if the SSNs procured are Virginia-class boats);8062 and • the volume of non-submarine-construction work performed at the two shipyards during these years, which would include in particular aircraft carrier construction and overhaul work at NGSB/NN. A January 12, 2011, press report stated: 7961 Under the joint-production arrangement for Virginia-class boats, GD/EB builds certain parts of each boat, NGSB/NN builds certain other parts of each boat, and the two yards take turns building the reactor compartment and performing final assembly work. GD/EB is the final assembly yard for the first Virginia-class boat, the third one, and so on, while NGSB/NN is the final assembly yard for the second boat, the fourth one, and so on. The arrangement provides a roughly 50-50 split in profits between the two firms for the production of Virginia-class SSNs. The agreement governing the joint-production arrangement cannot be changed without the consent of both firms. Virginia-class SSNs are the first U.S. nuclear-powered submarines to be built jointly by two shipyards; all previous U.S. nuclear-powered submarines were built under the more traditional approach of building an entire boat within a single yard. The Virginia-class joint-production arrangement was proposed by the two shipyards, approved by the Navy, and then approved by Congress as part of its action on the FY1998 defense budget. A principal goal of the arrangement is to preserve submarine-construction skills at two U.S. shipyards while minimizing the cost of using two yards to build a class of submarines that is procured at a relatively low rate of one or two boats per year. Preserving submarineconstruction skills at two yards is viewed as a hedge against the possibility of operations at one of the yards being disrupted by a natural or man-made disaster. The joint-production arrangement is more expensive than single-yard strategy of building all Virginia-class boats at one shipyard (in part because the joint-production strategy splits the learning curve for reactor compartment construction and final assembly work on Virginia-class SSNs), but it is less expensive than a separate-yard strategy of building complete Virginia-class separately at both yards (in part because a separate-construction strategy splits the learning curve for all aspects of Virginia-class construction work, and because, in the absence of other submarine-construction work, a procurement rate of one or two Virginia-class boats per year is viewed as insufficient to sustain a meaningful competition between the two yards for contracts to build the boats). 8062 The agreement governing the joint-production arrangement for the Virginia class cannot be changed without the consent of both yards. Congressional Research Service 3223 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress While the [SSBN(X)] submarine-building contracts would likely be competitively bid, [Electric Boat President] Casey says he doubts any other company—even its attacksubmarine-building partner Northrop Grumman—can secure the work. Electric Boat built the existing Ohio-class fleet. “We have every intention of building every one of those ships,” he says. “There’s no one else [who was] involved in designing and building that [Ohio-class] platform.63 It’s up to us to convince people we can do it at the right price.”8164 Building CMCs for the UK’s SSBNs A related question is whether the CMCs for the UK’s replacement SSBNs should be built in the United States or the UK. Building them in the United States could reduce the procurement cost of CMCs produced for both countries’ SSBNs. It could also help maintain employment levels in U.S. shipyards. The UK, however, might prefer to build its CMCs in the UK in order to help maintain employment levels in UK shipyards or to preserve certain submarine-construction skills. An agreement to build the UK’s CMCs in the United States might include what is known as an “offset”—a corresponding agreement to have the UK build some portion of a defense item that is being procured for use by the U.S. military. Options for Congress Options for Congress include approving, rejecting, or modifying the Navy’s funding request for the program, and providing additional direction to the Navy or DOD concerning the SSBN(X) program. Legislative Activity for FY2012 The Administration is expected to submit its proposed FY2012 defense budget to Congress on or about February 14, 2011. 81 Legislative Activity for FY2012 As shown in Table 3, the Navy’s proposed FY2012 budget requests $1,067 million in research and development funding for the SSBN(X) program. 63 The bracketed words in this sentence were inserted by CRS following a February 8, 2011, telephone call to CRS from Electric Boat in which Electric Boat stated that sentence in Mr. Casey’s quote refers to Electric Boat being the sole designer and builder of the current Ohio-class SSBNs. 64 Michael Fabey, “Electric Boat Recruits Engineers For Ohio-Class Sub Replacement,” Aerospace Daily & Defense Report, January 12, 2011: 1-2. Congressional Research Service 3324 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Appendix. Legislative Activity for FY2011 FY2011 Further Continuing Appropriations Amendments (H.J.Res. 44/P.L. 112-4) P.L. 112-4 of March 2, 2011—the most recent FY2011 continuing resolution—generally funds government programs through March 18Continuing Appropriations and Surface Transportation Extensions Act (H.R. 3082/P.L. 111-322) The FY2011 Continuing Appropriations and Surface Transportation Extensions Act (H.R. 3082/P.L. 111-322 of December 22, 2010) generally funds government programs through March 4, 2011, at FY2010 funding levels. Congressional Action on FY2011 Funding Request Other Than P.L. 111-322112-4 Table A-1 summarizes other congressional action other than H.R. 3082/P.L. 111-322 on the Navy’s FY2011 funding request for the SSBN(X) program. Table A-1. Congressional Action on FY2011 Funding Request Other than H.R. 3082/P.L. 111-322 (Millions of then-year dollars, rounded to nearest tenth; totals may not add due to rounding) Authorization Appropriation Request HASC SASC PE0603561N/Project 3220 493.0 493.0 493.0 Not clear – see narrative discussion below PE0603570N/Project 3219 179.3 179.3 179.3 179.3 TOTAL 672.3 672.3 672.3 Not clear Conf. HAC SAC Conf. Sources: For request: Navy data provided to CRS on March 11, 2010, by Navy Office of Legislative Affairs. For congressional authorization and appropriation action: committee and conference reports. Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference report. PE means Program Element, that is, a research and development line item. A Program Element may include several projects. PE0603561N/Project 3220 is Sea Based Strategic Deterrent project within the PE for Advanced Submarine System Development. PE0603570N/Project 3219 is SSBN(X) reactor plant project within the PE for Advanced Nuclear Power Systems. FY2011 Defense Authorization Act (H.R. 6523/P.L. 111-383) House (H.R. 5136) The House Armed Services Committee, in its report (H.Rept. 111-491 of May 21, 2010) on the FY2011 defense authorization bill (H.R. 5136), recommends approval of the Navy’s FY2011 research and development funding request for the SSBN(X) program (page 147, line 41, and page Congressional Research Service 34 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress 148, line 45). Section 211(c) of H.R. 5136 as reported by committee would limit the obligation Congressional Research Service 25 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress and expenditure of FY2011 Navy research and development funding for the SSBN(X) until 30 days after the Navy submits a report on the SSBN(X) program. Section 211 states: SEC. 211. REPORT REQUIREMENTS FOR REPLACEMENT PROGRAM OF THE OHIO-CLASS BALLISTIC MISSILE SUBMARINE. (a) Findings- Congress makes the following findings: (1) The sea-based strategic deterrence provided by the ballistic missile submarine force of the Navy has been essential to the national security of the United States since the deployment of the first ballistic missile submarine, the USS George Washington SSBN 598, in 1960. (2) Since 1960, a total of 59 submarines have served the United States to provide the seabased strategic deterrence. (3) As of the date of the enactment of this Act, the sea-based strategic deterrence is provided by the tremendous capability of the 14 ships of the Ohio-class submarine force, which have been the primary sea-based deterrent force for more than two decades. (4) Ballistic missile submarines are the most survivable asset in the arsenal of the United States in the event of a surprise nuclear attack on the country because, being submerged for months at a time, these submarines are virtually undetectable to any adversary and therefore invulnerable to attack, thus providing the submarines with the ability to respond with significant force against any adversary who attacks the United States or its allies. (b) Sense of Congress- It is the sense of Congress that— (1) as Ohio-class submarines reach the end of their service life and are retired, the United States must maintain the robust sea-based strategic deterrent force that has the ability to remain undetected by potential adversaries and must have the capability to deliver a retaliatory strike of such magnitude that no rational actor would dare attack the United States; (2) the Secretary of Defense should conduct a comprehensive analysis of the alternative capabilities to provide the sea-based strategic deterrence that includes consideration of different types and sizes of submarines, different types and sizes of missile systems, the number of submarines necessary to provide such deterrence, and the cost of each alternative; and (3) prior to requesting more than $1,000,000,000 in research and development funding to develop a replacement for the Ohio-class ballistic missile submarine force in advance of a Milestone A decision, the Secretary of Defense should have made available to Congress the guidance issued by the Director of Cost Assessment and Performance Evaluation with respect to the analysis of alternative capabilities and the results of such analysis. (c) Limitation(1) REPORT- Of the funds authorized to be appropriated by this Act or otherwise made available for fiscal year 2011 for research and development for the Navy, not more than 50 percent may be obligated or expended to research or develop a submarine as a replacement for the Ohio-class ballistic missile submarine force unless— (A) the Secretary of Defense submits to the congressional defense committees a report including— Congressional Research Service 3526 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress (A) the Secretary of Defense submits to the congressional defense committees a report including— (i) guidance issued by the Director of Cost Assessment and Performance Evaluation with respect to the analysis of alternative capabilities to provide the sea-based strategic deterrence currently provided by the Ohio-class ballistic missile submarine force and any other guidance relating to requirements for such alternatives intended to affect the analysis; (ii) an analysis of the alternative capabilities considered by the Secretary to continue the seabased strategic deterrence currently provided by the Ohio-class ballistic missile submarine force, including— (I) the cost estimates for each alternative capability; (II) the operational challenges and benefits associated with each alternative capability; and (III) the time needed to develop and deploy each alternative capability; and (iii) detailed reasoning associated with the decision to replace the capability of sea-based deterrence provided by the Ohio-class ballistic missile submarine force with an alternative capability designed to carry the Trident II D5 missile; and (B) a period of 30 days has elapsed after the date on which the report under subparagraph (A) is submitted. (2) FORM- The report required by paragraph (1) shall be submitted in unclassified form, but may include a classified annex. The report states: Ohio-class replacement program The committee strongly supports a robust sea-based strategic deterrent force. The current 14 ships of the Ohio-class ballistic missile submarines are a national treasure and have helped keep the nation safe for over two decades. Like the ballistic missile submarine classes that preceded them, a percentage of these vessels remain in an alert posture, at sea, invulnerable to attack by potential enemies, ready to retaliate should the nation be attacked. The committee supports efforts to retain this capability into the future. However, the committee has questions concerning the current program to replace the Ohioclass ships. First, the basic requirement of how much and what type of deterrent capability is sufficient for the national military strategy has not been communicated to the committee. Second, the committee has not been afforded the opportunity to review the analysis of alternatives conducted by the Navy, which determined that a submarine large enough to support the Trident II D5 missile weapons system is the preferred vessel to continue deterrent capability. Third, the committee has concerns that the decision to proceed with a submarine program of similar size as the Ohio-class ships was made prior to the analysis of alternatives, and that a potential use of a modified Virginia-class submarine, in production today, was discounted in favor of maintaining the Trident II D5 weapons system. Because of these concerns, elsewhere in this Act the committee will authorize, but withhold authority to obligate more than 50 percent of the funds requested for development of this program until the Secretary of Defense certifies to the committee of the necessity to continue sea-based deterrence with the Trident II D5 weapons system. (Pages 77-78) Congressional Research Service 3627 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress Senate (S. 3454) The FY2011 defense authorization bill (S. 3454), as reported by the Senate Armed Services Committee (S.Rept. 111-201 of June 4, 2010), recommends approval of the Navy’s FY2011 research and development funding request for the SSBN(X) program (page 732, lines 41 and 45 of the printed bill). (The bill as reported recommends three funding additions to PE 0603561N [line 41] totaling $26 million, but these additions do not appear specific to the SSBN(X) program. See pages 62-64 of the committee’s report for discussions of these three recommended additions.) The committee’s report states: The committee notes that the current shipbuilding plan includes the cost of the SSBN (X) program and the committee encourages the Navy to closely scrutinize requirements for this program in order to minimize its impact on the recapitalization of the Navy’s battle force. (Page 40) The committee’s report also states: Strike study The budget request included $81.2 million in Research, Development, Test, and Evaluation, Navy, PE 11221N line 162 for strategic submarine and weapons systems support. The committee recommends a decrease of $10.0 million. Of the amount requested $10.0 million was for a study for ambiguity and other issues that associated with conventional and nuclear payloads on strategic ballistic missile submarines. The committee recommends no funds for the study. The committee notes that the National Academy of Sciences conducted an extensive study on this issue and the additional study would be redundant. (Page 71) Final Version (H.R. 6523/P.L. 111-383) H.R. 6523/P.L. 111-383 of January 7, 2011, contains no provisions relating specifically to the SSBN(X) program. The joint explanatory statement of the House and Senate Armed Services Committees on H.R. 6523 does not discuss the program. FY2011 DOD Appropriations Bill (S. 3800) Senate The Senate Appropriations Committee, in its report (S.Rept. 111-295 of September 16, 2010) on S. 3800, recommended reducing the Navy’s FY2011 research and development funding request for PE (Program Element) 0603561N, Advanced Submarine System Development, by $49.3 million for “execution delays” (page 150, line 41). The report does not discuss how much, if any, of this $49.3 million reduction is to be applied against Project 3220—the part of PE 0603561N that is for the SSBN(X) program. Since Project 3220 accounts for about 81% of the funding requested for PE 0603561N ($493.0 million of $608.6 million), it is possible that at least some of the $49.3 million reduction would be applied against Project 3220. The committee’s report also recommends seven funding additions to PE 0603561N totaling $25.5 million (page 150, line 41). The committee’s report does not discuss these additions in detail; they may not be specific to the SSBN(X) program. Congressional Research Service 3728 Navy SSBN(X) Ballistic Missile Submarine Program: Background and Issues for Congress The committee’s report recommends approving the Navy’s FY2011 research and development funding request for PE 0603570N, Advanced Nuclear Power Systems, which includes, in Project 3219, $179.3 million for the SSBN(X) program (page 145, line 45). Author Contact Information Ronald O'Rourke Specialist in Naval Affairs rorourke@crs.loc.gov, 7-7610 Congressional Research Service 3829