< Back to Current Version

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Changes from October 5, 2007 to March 28, 2008

This page shows textual changes in the document between the two versions indicated in the dates above. Textual matter removed in the later version is indicated with red strikethrough and textual matter added in the later version is indicated with blue.


Order Code RL33741 Navy Littoral Combat Ship (LCS) Program: Background, Oversight Issues, and Options for Congress Updated October 5, 2007March 28, 2008 Ronald O’Rourke Specialist in National DefenseNaval Affairs Foreign Affairs, Defense, and Trade Division Navy Littoral Combat Ship (LCS) Program: Background, Oversight Issues, and Options for Congress Summary The Littoral Combat Ship (LCS) is a small, fast surface combatant that is to be equipped with modular mission packages, including unmanned vehicles (UVs). The basic version of the LCS, without any mission packages, is referred to as the LCS sea frame. The first LCS (LCS-1) was procured in FY2005, another three (LCSs 2, 3, and 4) were procured in FY2006, and two more (LCSs 5 and 6) were procured in FY2007. The Navy’s proposed FY2008 budget, submitted to Congress in February 2007, requested $910.5 million in procurement funding for three more LCSs. Navy plans call for procuring a total of 55 LCSs. In response to significant cost growth in the building of the first LCSs, the Navy in January 2007 placed a 90-day stop-work order on LCS-3 and in March 2007 announced a proposed plan for restructuring the LCS program. The plan would: ! ! ! ! ! ! ! cancel the two LCSs funded in FY2007 (LCSs 5 and 6) and use the funding to pay for cost overruns on earlier LCSs; lift the stop-work order on LCS-3 — provided that the Navy reached an agreement by April 12 with the Lockheed-led industry team building LCS-3 to restructure the contract that the Lockheed team has for building LCSs 1 and 3 from a cost-plus type contract into a fixed price incentive (FPI)-type contract; alternatively, terminate construction of LCS-3 — if an agreement on a restructured contract for LCS-1 and LCS-3 could not be reached with the Lockheed team by April 12; seek to restructure the contract for building LCSs 2 and 4 (which are being built by a second industry team led by General Dynamics) into an FPI-type contract — if LCSs 2 and 4 experience cost growth comparable to that of LCSs 1 and 3; reduce the number of LCSs requested for FY2008 from three to two (for the same requested FY2008 procurement funding of $910.5 million), and the number to be requested for FY2009 from six to three; conduct an operational evaluation to select a favored design for LCSs to be procured in FY2010 and beyond; and conduct a full and open competition among bidders for the right to build that design. On April 12, 2007, the Navy announced that the Navy and Lockheed had not reached an agreement on a restructured contract for LCS-1 and LCS-3, and that the Navy consequently was terminating construction of LCS-3. On May 10, 2007, it was reported that the Navy would ask Congress to increase the procurement cost cap for the fifth and sixth LCSs to $460 million each in FY2008 dollars. A primary issue for Congress at this point is whether to approve, reject, or modify the Navy’s proposed restructuring plan. Congress has several potential options regarding the LCS program. This report will be updated as events warrant. Contents Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Littoral Combat Ship (LCS) Program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 March 2007 Program Restructuring Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 April 2007 Termination of LCS-3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 September 2007 Report of Negotiations on LCSs 2 and 4 . . . . . . . . . . . . . . 8 Proposed Common Combat System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Potential Oversight Issues for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Cost Increase on LCS Sea Frames . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 Cost Cap on Fifth and Sixth Ships . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 Total Program Acquisition Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Termination of LCS-3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 Operational Evaluation and Competition for Production . . . . . . . . . . . . . . 21 Proposed Common Combat System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 Pace of Mission Package Procurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 Mission Packages Funded in OPN Account . . . . . . . . . . . . . . . . . . . . . . . . 24 Options for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 FY2008 Legislative Activity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 FY2008 Defense Authorization Bill (H.R. 1585/S. 1547) . . . . . . . . . . . . . . 26 FY2008 Defense Appropriations Bill (H.R. 3222) . . . . . . . . . . . . . . . . . . . 35 List of Tables Table 1. LCS Program Funding in FY2007 Budget . . . . . . . . . . . . . . . . . . . . . . . 4 Table 2. Projected Procurement Of LCSs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 Table 3. LCS Sea Frame Unit Procurement Costs . . . . . . . . . . . . . . . . . . . . . . . 11 Navy Littoral Combat Ship (LCS) Program: Background, Oversight Issues, and Options for Congress Introduction The Navy is procuring a new type of surface combatant called the Littoral Combat Ship (LCS). The LCS is a small, fast ship that is to be equipped with modular “plug-and-fight” mission packages, including unmanned vehicles (UVs). The basic version of the LCS, without any mission packages, is referred to as the LCS sea frame. The first LCS (LCS-1) was procured in FY2005, another three (LCSs 2, 3, and 4) were procured in FY2006, and two more (LCSs 5 and 6) were procured in FY2007. The Navy’s proposed FY2008 budget, submitted to Congress in February 2007, requested $910.5 million in procurement funding for three more LCSs. Navy plans call for procuring a total of 55 LCSs. In response to significant cost growth in the building of the first LCSs, the Navy in January 2007 placed a 90-day stop-work order on LCS-3 and in March 2007 announced a proposed plan for restructuring the LCS program that would, among other things, cancel LCSs 5 and 6 and use the funding for those two ships to pay for cost overruns on earlier LCSs, and reduce the number of LCSs to be procured in FY2008 from three to two. On April 12, 2007, the Navy announced that it was terminating construction of LCS-3, leaving only LCSs 1, 2, and 4 under construction. On May 10, 2007, it was reported that the Navy would ask Congress to increase the procurement cost cap for the fifth and sixth LCSs to $460 million each in FY2008 dollars. A primary issue for Congress at this point is whether to approve, reject, or modify the Navy’s proposed restructuring plan. Congress has several potential options regarding the LCS program. Background Littoral Combat Ship (LCS) Program Announcement of LCS Program. The LCS program was announced on November 1, 2001, when the Navy stated that it was launching a Future Surface Combatant Program aimed at acquiring a family of next-generation surface CRS-2 combatants. This new family of surface combatants, the Navy stated, would include three new classes of ships: ! a destroyer called the DD(X) — later redesignated the DDG-1000 — for the precision long-range strike and naval gunfire mission,1 ! a cruiser called the CG(X) for the air defense and ballistic missile mission,2 and ! a smaller combatant called the Littoral Combat Ship (LCS) to counter submarines, small surface attack craft, and mines in heavily contested littoral (near-shore) areas. The LCS In Brief. The LCS is a small, fast surface combatant that is to be equipped with modular “plug-and-fight” mission packages, including unmanned vehicles (UVs). Rather than being a multimission ship like the Navy’s larger surface combatants, the LCS is to be a focused-mission ship equipped to perform one or two missions at any one time. The ship’s mission orientation is to be changed by changing out its mission packages. The basic version of the LCS, without any mission packages, is referred to as the LCS sea frame. The LCS’s primary intended missions are shallow-water antisubmarine warfare, mine countermeasures, countering small boats, and intelligence, surveillance, and reconnaissance (ISR). Secondary intended missions include homeland defense, maritime interception, and support of special operations forces. The LCS is to displace about 3,000 tons — about the size of a corvette or Coast Guard cutter. It is to have a maximum speed of about 45 knots, compared to Navy is procuring a new type of surface combatant called the Littoral Combat Ship (LCS). The Navy substantially restructured the LCS program in 2007 in response to significant cost growth and schedule delays in the program. The Navy’s proposed FY2009 budget requests $920 million in procurement funding for the procurement of two LCSs, which would be the fourth and fifth ships in the restructured LCS program. The LCS is a small, fast, relatively inexpensive combat ship that is to be equipped with modular “plug-and-fight” mission packages, including unmanned vehicles (UVs). The basic version of the LCS, without any mission packages, is referred to as the LCS sea frame. The Navy wants to procure a total of 55 LCSs. Congress originally funded a total of six LCS sea frames (LCSs 1 through 6) in the FY2005, FY2006, and FY2007 defense budgets. In 2007, as Congress was considering the proposed FY2008 defense budget, the Navy canceled LCSs 3 though 6 as part of its restructuring of the program, leaving only LCSs 1 and 2 under construction. As part of its final action on the FY2008 defense budget, Congress did the following, among other things, regarding the LCS program: accepted the Navy’s cancellation of LCSs 3 through 6; funded the procurement one additional LCS in FY2008 (which the Navy now calls LCS-5); significantly reduced the Navy’s FY2008 funding request for the LCS program; amended the LCS sea frame unit procurement cost cap (something the Navy had requested, though not in the exact form that Congress eventually legislated); required the Navy to use fixed-price-type contracts for the construction of LCSs procured in FY2008 and subsequent years (something the Navy had stated an intention to do as part of its plan for restructuring the LCS program); criticized the execution of the LCS program; expressed concerns for the program; and expressed support for continuing with the program in restructured form. The issue for Congress for FY2009 is whether to approve, reject, or modify the Navy’s restructured LCS program. The LCS program raises potential oversight issues for Congress relating to cost growth, total program acquisition cost, the procurement cost cap, operational evaluation and competition for production, a proposed common combat system, and coordination of sea frames and mission packages. This report will be updated as events warrant. Contents Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 LCS Program in Brief . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 2007 Program Restructuring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 March 2008 Navy Testimony on Acquisition Strategy . . . . . . . . . . . . . . . . . 8 Cost Growth on LCS Sea Frames . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Potential Oversight Issues for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 Cost Growth on LCS Sea Frames . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 Total Program Acquisition Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 Procurement Cost Cap . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 Operational Evaluation and Competition for Production . . . . . . . . . . . . . . 19 Proposed Common Combat System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 Coordination of Sea Frames and Mission Packages . . . . . . . . . . . . . . . . . . 20 Options for Congress . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 FY2009 Legislative Activity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 List of Tables Table 1. Actual and Planned LCS Procurement Through FY2013 . . . . . . . . . . . . 5 Table 2. LCS Program Acquisition Funding, FY2007-FY2013 . . . . . . . . . . . . . . 6 Navy Littoral Combat Ship (LCS) Program: Background, Oversight Issues, and Options for Congress Introduction The Navy is procuring a new type of surface combatant called the Littoral Combat Ship (LCS). The Navy substantially restructured the LCS program in 2007 in response to significant cost growth and schedule delays in the program. The Navy’s proposed FY2009 budget requests $920 million in procurement funding for the procurement of two LCSs, which would be the fourth and fifth ships in the restructured LCS program. The LCS is a small, fast, relatively inexpensive combat ship that is to be equipped with modular “plug-and-fight” mission packages, including unmanned vehicles (UVs). The basic version of the LCS, without any mission packages, is referred to as the LCS sea frame. The Navy wants to procure a total of 55 LCSs. The Navy’s planned force of 55 LCSs accounts for about 18% of its planned fleet of 313 ships of all types.1 Congress originally funded a total of six LCS sea frames (LCSs 1 through 6) in the FY2005, FY2006, and FY2007 defense budgets. In 2007, as Congress was considering the proposed FY2008 defense budget, the Navy canceled LCSs 3 though 6 as part of its restructuring of the program, leaving only LCSs 1 and 2 under construction. The reduction of the LCS program in a single year from six prior-yearfunded ships to two due to cost growth and schedule delays was an occurrence with few parallels in the recent history of Navy shipbuilding. As part of its action on the FY2008 defense budget, Congress did the following, among other things, regarding the LCS program: ! ! accepted the Navy’s cancellation of LCSs 3 through 6, funded the procurement one additional LCS in FY2008 (which the Navy now calls LCS-5),2 1 For more on the Navy’s planned 313-ship fleet, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O’Rourke. 2 The Navy apparently calls this ship LCS-5 because the original LCS-5 and LCS-6 were canceled by the Navy before they were replaced under contract, leaving LCS-4 as last LCS under contract to have been canceled. In spite of its designation, LCS-5 will be the third (continued...) CRS-2 ! ! ! ! ! ! significantly reduced the Navy’s FY2008 funding request for the LCS program, amended the LCS sea frame unit procurement cost cap (something the Navy had requested, though not in the exact form that Congress eventually legislated), required the Navy to use fixed-price-type contracts for the construction of LCSs procured in FY2008 and subsequent years (something the Navy had stated an intention to do as part of its plan for restructuring the LCS program), criticized the execution of the LCS program, expressed concerns for the program, and expressed support for continuing with the program in restructured form. Developments in the LCS program in 2007 have caused some observers, particularly those associated with the LCS program, to express concern about the program’s future. The Navy has stated repeatedly that, the developments of 2007 notwithstanding, the Navy remains committed to a 55-ship LCS program. As mentioned above, although Congress has criticized the execution of the program, it has expressed support for continuing with the program in restructured form. None of the congressional defense-oversight committees, in marking up the FY2008 budget, recommended terminating the LCS program or reducing the Navy’s planned 55-ship total. The issue for Congress for FY2009 is whether to approve, reject, or modify the Navy’s restructured LCS program. Decisions that Congress makes on this issue could affect future Navy capabilities and funding requirements, and the shipbuilding industrial base. Background LCS Program in Brief Announcement of LCS Program. The LCS program was announced on November 1, 2001, when the Navy stated that it was launching a Future Surface Combatant Program aimed at acquiring a family of next-generation surface combatants. This new family of surface combatants, the Navy stated, would include three new classes of ships: ! a destroyer called the DD(X) — later redesignated the DDG-1000 — for the precision long-range strike and naval gunfire mission,3 2 (...continued) LCS in the restructured LCS program, and the seventh to have been funded by Congress. 3 For more on the DDG-1000 program, see CRS Report RL32109, Navy DDG-1000 Destroyer Program: Background, Oversight Issues, and Options for Congress, by Ronald (continued...) CRS-3 ! a cruiser called the CG(X) for the air defense and ballistic missile mission,4 and ! a smaller combatant called the Littoral Combat Ship (LCS) to counter submarines, small surface attack craft, and mines in heavily contested littoral (near-shore) areas. The LCS. The LCS is a small, fast, relatively inexpensive surface combatant that is to be equipped with modular “plug-and-fight” mission packages, including unmanned vehicles (UVs). Rather than being a multimission ship like the Navy’s larger surface combatants, the LCS is to be a focused-mission ship equipped to perform one or two missions at any one time. The ship’s mission orientation is to be changed by changing out its mission packages. The basic version of the LCS, without any mission packages, is referred to as the LCS sea frame. The LCS’s primary intended missions are shallow-water antisubmarine warfare, mine countermeasures, countering small boats, and intelligence, surveillance, and reconnaissance (ISR). Secondary intended missions include homeland defense, maritime intercept operations, and support of special operations forces. The LCS is to displace about 3,000 tons, making it about the size of a corvette or Coast Guard cutter. It is to have a maximum speed of about 45 knots, compared to something more than 30 knots for the Navy’s larger surface combatants. The LCS is to have a shallower draft than the Navy’s larger surface combatants, permitting it to operate in certain coastal waters and visit certain ports that are not accessible to the Navy’s larger surface combatants. The LCS is to employ automation to achieve a reduced “core” crew of 40 sailors. Up to 35 or so additional sailors are to operate the ship’s embarked aircraft and mission packages, making for a total crew of about 75, compared to more than 200 for the Navy’s larger surface combatantsfrigates and 300 or more for the Navy’s current destroyers and cruisers. As mentioned earlier, Navy plans call for procuring a total of 55 LCSs. The Navy currently plans to procure a total of 64 mission packages for the 55 ships. Earlier Navy plans anticipated procuring between 90 and 110 mission packages for a 55-ship fleet. Summary Of Congressional Action forIn FY2005-FY2007FY2008. FY2005. In FY2005, Congress approved the Navy’s plan to fund the construction of the first two LCSs using 1 For more on the DDG-1000 program, see CRS Report RL32109, Navy DDG-1000 Destroyer Program: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. 2 For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser Program: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. CRS-3 construction of the first two LCS sea frames using research and development funds rather than shipbuilding funds, funded the first LCS’s construction cost, required the second LCS to be built to a different design construction cost of the first LCS (LCS-1), required the second LCS (LCS-2) to be built (when funded in FY2006) to a different design from the first, prohibited the Navy from requesting funds in FY2006 to build a third LCS, and required all LCSs built after the lead ships of each design to be funded in 3 (...continued) O’Rourke. 4 For more on the CG(X) program, see CRS Report RL34179, Navy CG(X) Cruiser Program: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. CRS-4 design to be funded in the SCN account rather than the Navy’s research and development account. FY2006. In FY2006, Congress funded the procurement of the second, third, and fourth LCSs. LCSs 2, 3, and 4. (The Navy requested one LCS for FY2006, consistent with Congress’s FY2005 FY2005 action. Congress funded that ship and provided funding for two additional ships.) Congress in FY2006 also established a $220-million unit procurement cost limit on the fifth and sixth LCSs sixth LCS sea frames of $220 million per ship, plus adjustments for inflation and other factors (Section 124 of the FY2006 defense authorization bill [H.R. 1815/P.L. 109-163] of January 6, 2006), required an annual report on LCS mission packages, and made procurement of more than four LCSs contingent on the Navy certifying that there there exists a stable design for the LCS. FY2007. In FY2007, Congress funded the procurement of the fifth and sixth LCSsLCSs 5 and 6. (The Navy canceled these two ships in 2007 before they were placed under contract for construction.) FY2008. In FY2008, as mentioned earlier, Congress accepted the Navy’s cancellation of LCSs 3 through 6; funded the procurement one additional LCS in FY2008 (which the Navy now calls LCS-5); significantly reduced the Navy’s FY2008 funding request for the LCS program; amended the LCS sea frame unit procurement cost cap to $460 million per ship for LCSs procured in FY2008 and subsequent years (Section 125 of the conference report [H.Rept. 110-477 of December 6, 2007] on H.R. 1585, the FY2008 defense authorization bill, which was enacted as H.R. 4986/P.L. 110-181 of January 28, 2008); and required the Navy to use fixed-price-type contracts for the construction of LCSs procured in FY2008 and subsequent years. The Navy in 2007 requested that Congress amend the existing unit procurement cost cap for the fifth and sixth ships to $460 million, plus adjustments for inflation and other factors. Congress amended the cost cap to $460 million, but applied it not only to the fifth and sixth LCSs, but to all LCSs procured in FY2008 and subsequent years. The use of fixed-price contracts for future LCSs was something that the Navy had stated an intention to do as part of its plan for restructuring the LCS program. Two Industry Teams, Each With Its Own Design. On May 27, 2004, the Navy awarded contracts to two industry teams — one led by Lockheed Martin, the other by General Dynamics (GD) — to design two versions of the LCS, with options for each team to build up to two LCSs each. The two teams’ LCS designs are quite different — Lockheed’s uses a semi-planing steel monohull, while GD’s uses an aluminum trimaran hull. The Lockheed team was assigned LCS-1 and (the nowcanceled) LCS-3, while the GD team was assigned LCS-2 and (the now-canceled) LCS-4. Lockheed announced plans to build its LCSs at Marinette Marine of Marinette, WI, and Bollinger Shipyards of Lockport, LA. (LCS1, with LCS-1 being built by Marinette and LCS-3 was scheduled to have been built by Bollinger.) GD GD announced plans to build its LCSs at the Austal USA shipyard of Mobile, AL.3 Program Funding. Table 1 shows LCS funding through FY2011 as reflected in the FY2007 budget submitted to Congress in February 2006. CRS in February 2007 requested updated (FY2008-FY2013) budget information from the Navy, but the Navy Office of Legislative Affairs informed CRS by telephone on March 28, 2007, that in light of the Navy’s proposed plan for restructuring the LCS program, updated FY2008-FY2013 funding figures were not available. With Congress’s permission, the Navy procured the first and second LCSs through the Navy’s research and development account. Subsequent LCSs are being procured through the Navy’s ship-procurement account, called the Shipbuilding and Conversion, Navy (SCN) account. The Navy is procuring LCS mission packages through the Other Procurement, Navy (OPN) account. 3 Austal USA was created in 1999 as a joint venture between Austal Limited of Henderson, Western Australia and Bender Shipbuilding & Repair Company of Mobile, AL. The Lockheed LCS team also includes GD/BIW as prime contractor to provide program management and planning, provide technical management, and to serve as “LCS system production lead.” CRS-4 Table 1. LCS Program Funding in FY2007 Budget (Funding as shown in FY2007 budget submitted to Congress in February 2006; millions of then-year dollars; totals may not add due to rounding) FY03 FY04 FY05 FY06 FY07 FY08 Research, Development, Test & Evaluation, Navy (RDT&EN) account 0 0 206.7 59.2 8.5 0 Ship 1 construction (qty) (1) Ship 2 construction 0 0 16.0 207.1 55.0 0 (qty) (1) Ships 1and 2 outfit0 0 0 8.7 36.7 36.8 ting/post delivery LCS ship development 35.3 160.1 228.0 86.0 57.0 60.3 LCS mission package 0 0 0 213.0 162.3 90.4 project (qty) (3) (1) 35.3 160.1 450.8 574.0 319.6 187.6 Subtotal RDT&EN Shipbuilding and Conversion, Navy (SCN) account 0 0 0 440.0 Ships 3-27 520.7 947.6 (2) construction (2) (3) (qty) Outfitting & post 0 0 0 0 13 37 delivery 0 0 0 440.0 533.7 984.6 Subtotal SCN Other Procurement, Navy (OPN) account (for LCS mission packages) 0 0 0 40.1 79.1 207.6 Subtotal OPN (qty) (0) (1) (3) Weapons Procurement, Navy (WPN) account 0 0 0 0 0 12.5 Subtotal WPN 35.3 160.1 450.8 1054.1 919.3 1355.3 TOTAL FY09 FY10 FY11 Total thru FY11 0 0 0 274..5 0 0 0 278.1 7.1 0 0 89.3 43.2 82.5 43.9 100.1 22.4 40.8 132.8 144.1 63.2 736.2 689.2 (4) 2067.3 1764.3 1774.2 1825.4 (6) (6) (6) 7272.3 (25) 70 122 337 1834.3 1869.2 1947.4 7609.3 652.3 (13) 95 656.2 (12) 720.2 (15) 2355.5 (44) 39.1 91.0 134.2 276.8 2588.5 2665.6 2743.0 12308.9 Source: Navy Office of Legislative Affairs (NOLA), March 6 and April 17, 2006, based on figures from FY2007 budget submitted to Congress in February 2006. CRS in February 2007 requested updated (FY2008) budget information from the Navy, but NOLA informed CRS by telephone on March 28, 2007, that in light of the Navy’s proposed plan for restructuring the LCS program, updated FY2008 funding figures are not available. Potential Total Acquisition Cost. The Navy has not provided an estimated total acquisition (i.e., development plus procurement) cost for the LCS program. CRS estimates that the LCS program (including mission packages) might have a total acquisition cost of roughly $23.8 billion to $29.6 billion. This estimate includes $2.5 billion in research and development costs (including the construction of first two sea frames and the procurement of the first four mission packages), procurement of 53 CRS-5 additional sea frames at a cost of $350 million to $460 million each,4 and 64 mission packages procured at an average cost of about $42.3 million each.5 30-Year Procurement Profile. Table 2 shows projected procurement of LCSs as shown in a Navy 30-year shipbuilding plan submitted to Congress in February 2007. This plan does not take into account the Navy’s proposal to cancel LCSs 5 and 6, its decision to terminate construction of LCS-3, and its proposal to reduce planned procurement of LCSs to two ships in FY2008 and three ships in FY2009. March 2007 Program Restructuring Plan In response to significant cost growth in the building of the first LCSs that first came to light in January 2007, the Navy in March 2007 announced a proposed plan for restructuring the LCS program. The Navy’s proposed restructuring would: ! cancel the two LCSs funded in FY2007 (LCSs 5 and 6) and use the funding to pay for cost overruns on earlier LCSs; ! lift the 90-day stop-work order that the Navy placed on LCS-3 in January 2007 — provided that the Navy reached an agreement by April 12 with the Lockheed-led industry team building LCS-3 to restructure the contract that the Lockheed team has for building LCSs 1 and 3 from a cost-plus type contract into a fixed price incentive (FPI)-type contract; ! alternatively, terminate construction of LCS-3 — if an agreement on a restructured contract for LCS-1 and LCS-3 could not be reached with the Lockheed team by April 12; ! seek to restructure the contract for building LCSs 2 and 4 (which are being built by a second industry team led by General Dynamics) into an FPI-type contract — if LCSs 2 and 4 experience cost growth comparable to that of LCSs 1 and 3; ! reduce the number of LCSs requested for FY2008 from three to two (for the same requested FY2008 procurement funding of $910.5 4 The figure of $350 million is based on Navy statements in early 2007 that LCS-1 might cost $350 million to $375 million; the figure of $460 million is based on the Navy’s request to have Congress amend the procurement cost cap on the fifth and sixth LCSs to $460 million per ship. 5 The Navy reportedly wants to procure 24 mine warfare mission packages at an average cost of $68 million each, 16 antisubmarine warfare packages at an average cost of $42.3 million each, and 24 surface warfare packages at an average cost of $16.7 million each. (Emelie Rutherford, Littoral Combat Ship Mission Packages Range In Costs, Features,” Inside the Navy, September 3, 2007; for similar figures, see Christopher P. Cavas, “First LCS Mission Package Ready For Delivery,” DefenseNews.com, August 29, 2007.) CRS-6 million), and the number to be requested for FY2009 from six to three; ! conduct an operational evaluation to select a favored design for the LCS — to be procured in FY2010 and subsequent years; and ! conduct a full and open competition among bidders for the right to build that design.6 Table 2. Projected Procurement Of LCSs FY 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 LCSa 3 6 6 6 6 5 6 6 5 1 2 3 4 6 6 6 6 Source: U.S. Department of the Navy, Report to Congress on Annual Long-Range Plan for Construction of Naval Vessels for FY 2008, February 2007. Table 3 on page 6. a. Plus one LCS procured in FY2005, three more in FY2006, and two more in FY2007. 6 Source: Navy briefing to CRS and Congressional Budget Office (CBO) on Navy’s proposed LCS program restructuring plan, March 21, 2007. CRS-7 Although the Navy intends to conduct an operational evaluation to support the selection of a single LCS design to be procured in FY2010 and beyond, the Navy also stated in an August 2007 report to Congress on the LCS program that the Navy may elect to continue production of both seaframes should each design present a unique operational advantage. The Navy carefully considered the two primary alternatives for LCS seaframe acquisition in FY 2010 and beyond; (1) selecting a single seaframe design and (2) continuing to procure two seaframe designs. Selecting a single Flight 1 design [i.e., a design to be procured in FY2010 and beyond] achieves commonality in hull, mechanical, and electrical (HM&E) and C4I systems in the LCS class. This alternative also allows the Navy to move more easily to a common combat system and C4I suite7 for the class. One seaframe design with a common combat system and C4I suite is projected to reduce life cycle cost with reduced logistics and training costs. To maintain competitive pricing pressure for Flight 1, the Navy intends to conduct a full and open competition for procurement in FY 2010 and beyond. This may result in some additional non-recurring start up costs in the near-term, but expanding potential sources increases competitive pricing pressure and enables higher production rates in the outyears needed to procure a 55-ship LCS class and achieve the CNO’s [the Chief of Naval Operation’s] force structure objective of [a total Navy fleet] of 313 ships. Continued procurement of two seaframe designs into FY2010 and beyond is also an alternative since both ships are currently assessed as being capable of meeting all the Key Performance Parameter and critical requirements. Existing Navy and industry nonrecurring investments would be leveraged to the maximum extent under continuation of Flight 0 ship [i.e., ships procured prior to FY2010] production with the current primes [prime contractors]. Additionally, the common combat system and C4I suite would be included in the alternative. The Navy’s decision to move to Flight I procurement in FY 2010 allows these ships to more easily incorporate lessons learned from the operational evaluation. The implementation of a common combat system and C4I suite as part of Flight 1 would reduce lifecycle cost of the common warfare system, but does not achieve the savings in seaframe HM&E [hull, mechanical, and electrical systems], crew training, and logistics costs anticipated from selecting a single seaframe design.8 April 2007 Termination of LCS-3 On April 12, 2007, the Navy announced that the Navy and Lockheed had not reached an agreement on a restructured contract for LCS-1 and LCS-3, and that the Navy consequently was terminating construction of LCS-3. (The Navy subsequently began referring to the ship as having been partially terminated — a reference to the 7 8 C4I stands for command, control, communications, computers, and intelligence. Report to Congress, Littoral Combat Ship, Prepared by Deputy Assistant Secretary of the Navy, Ships, Washington, DC 20350, August 2007, p. 7. See also p. 3. CRS-8 fact that Lockheed was allowed to continue procuring certain components for LCS-3, so that a complete set of these components would be on hand to be incorporated into the next LCS built to the Lockheed design.) The Navy’s April 12, 2007 announcement of the termination decision stated: Secretary of the Navy Donald C. Winter announced today that the Department of the Navy is terminating construction of the third Littoral Combat Ship (LCS 3) for convenience under the Termination clause of the contract because the Navy and Lockheed Martin could not reach agreement on the terms of a modified contract. The Navy issued a stop-work order on construction on LCS 3 in January following a series of cost overruns on LCS 1 and projection of cost increases on LCS 3, which are being built by Lockheed Martin under a cost-plus contract. The Navy announced in March that it would consider lifting the stop-work order on LCS 3 if the Navy and Lockheed Martin could agree on the terms for a fixed price incentive agreement by mid-April. The Navy worked closely with Lockheed Martin to try to restructure the agreement for LCS 3 to more equitably balance cost and risk, but could not come to terms and conditions that were acceptable to both parties. The Navy remains committed to completing construction on LCS 1 under the current contract with Lockheed Martin. LCS 2 and 4 are under contract with General Dynamics, and the Navy will monitor their cost performance closely. The Navy intends to continue with the plan to assess costs and capabilities of LCS 1 and LCS 2 and transition to a single seaframe configuration in fiscal year 10 after an operational assessment and considering all relevant factors. General Dynamics’ ships will continue on a cost-plus basis as long as its costs remain defined and manageable. If the cost performance becomes unacceptable, then General Dynamics will be subject to similar restructuring requirements. “LCS continues to be a critical warfighting requirement for our Navy to maintain dominance in the littorals and strategic choke points around the world,” said Winter. “While this is a difficult decision, we recognize that active oversight and strict cost controls in the early years are necessary to ensuring we can deliver these ships to the fleet over the long term.”9 September 2007 Report of Negotiations on LCSs 2 and 4 In late-September 2007, it was reported that the Navy on September 19 had sent a letter to General Dynamics to initiate negotiations on restructuring the contract for building LCSs 2 and 4 into an FPI-type contract. The negotiations reportedly are to be completed by October 19, 2007 — 30 days from September 19.10 If the 9 Department of Defense News Release No. 422-07, April 12, 2007, “Navy Terminates Littoral Combat Ship 3.” 10 Geoff Fein, “Navy Seeking To Negotiate FPI Contract With General Dynamics,” Defense Daily, September 24, 2007; Geoff Fein, “Navy, General Dynamics Meet To Discuss New LCS Fixed Price Structure,” Defense Daily, September 27, 2007; Tony Capaccio, “General Dynamics Urged To Take Fixed Price On Warship Contract,” Bloomberg News, September (continued...) CRS-9 negotiations do not result in an agreement by October 19, it is possible the Navy could terminate construction of LCS-4, just as it terminated construction of LCS-3 when Lockheed and the Navy failed to reach agreement within 30 days on terms for restructuring the contract for building LCSs 1 and 3 into an FPI-type contract. Proposed Common Combat System The two LCS designs currently use two different, contractor-furnished combat systems.11 As an added element of its restructuring of the LCS program, the Navy is proposing to shift to a common, government-furnished combat system for LCSs procured in FY2010 and beyond. The Navy testified in July 2007 that: The LCS Flight 0 ships [i.e., the LCSs procured prior to FY2010] acquisition strategy allowed the industry teams to design and acquire the combat system/C4I suite. As a result, each team developed a combat system whose components varied greatly from those found in other Navy combat systems as well as being significantly different from each other. The lack of commonality between the two current designs and Navy components negatively impacts the expected combat systems ownership costs to support these ship variants: i.e., materiel logistics, training programs, maintenance, system upgrades and technology refreshment. Additionally, some system components are foreign and/or proprietary designs that may not convey with Government Purpose Rights, limiting sources for obtaining component support. To minimize impacts to the combat systems ownership costs to acquire, operate, and maintain the LCS 1 Class, the Navy is amending its acquisition strategy for acquiring the LCS combat system beginning with FY 2010 Flight 1 procurements [i.e., LCS procured starting in FY2010]. The Navy intends to transition from Contractor Furnished Equipment (CFE) designs to a single common combat system that will be provided as Government Furnished Equipment (GFE)/Government Furnished Information (GFI). This strategy will incorporate, wherever possible, existing Navy programs of record combat system components. Where no Navy program of record or fleet-common component exists that meet LCS requirements, a full and open competition will be conducted. This strategy allows the Navy to establish commonality of LCS combat system components across all Flight 1 ships in the class, preserve Government Purpose Rights for the Navy, and assure that required capabilities are met with a set of combat system components that optimizes performance, acquisition and ownership costs. The current Flight 0 combat system solutions consist of eight major elements: an open architecture combat management system, volume search radar, identification friend or foe system, electronic surveillance system, medium caliber gun, gun fire control system, electro-optical/infrared sighting system, and 10 (...continued) 28, 2007; Jason Sherman, “Navy, General Dynamics Discuss Fixed-Price Contract For LCS,” Inside the Navy, October 1, 2007. 11 A ship’s combat system typically includes its sensors, computers, displays, and weapon launchers. The discussion here refers to the part of the LCS combat system that is permanently built into each sea frame, and not to the part that would be added by a modular mission package. CRS-10 a close-in/self-defense weapon system. The common combat system that the Navy will provide as GFE/GFI is comprised of these same elements. The Navy is not developing a new LCS combat system or adding elements to the current solution configuration. Rather, for Flight 1 the Navy is replacing the two unique sets of Flight 0 combat system components with a single set of combat system components. During the FY 2008-09 timeframe, ship design changes from the common combat system/C4I suite, lessons learned from LCS Flight 0 production, developmental/operational testing and at-sea testing will be incorporated into a Government-furnished design package. The Government-furnished design package provides the technical baseline for FY 2010 Flight 1 full and open competitive solicitation and subsequent Flight 1 ship production contract awards.12 The Navy is proposing to begin work on the common combat system in FY2007 using some of the prior-year LCS program funding that the Navy has requested Congress to reprogram. Potential Oversight Issues for Congress Cost Increase on LCS Sea Frames The Navy originally spoke of building LCS sea frames for about $220 million each, but estimated procurement costs for LCS sea frames have risen substantially above that figure. Cost growth in building the first LCS sea frames is the primary issue underpinning the Navy’s proposed plan for restructuring the LCS program and the Navy’s decision to terminate construction of LCS-3. The cost growth issue was the focus of an oversight hearing held before the Seapower and Expeditionary Forces subcommittee of the House Armed Services Committee on February 8, 2007, and was also a focus of an additional hearing on Navy surface combatant programs held before the same subcommittee on July 24, 2007. Estimated LCS sea frame unit procurement costs have increased twice — in early 2006, and again in 2007. The discussion below summarizes both increases. Increase Reported in Early 2006. The proposed FY2007 Navy budget submitted to Congress in February 2006 showed that LCS sea frame procurement costs had grown substantially from figures in the FY2006 budget submitted a year earlier. The estimate for the first LCS increased from $212.5 million in the FY2006 budget to $274.5 million in the FY2007 budget, an increase of about 29%. The estimate for the second LCS increased from $256.5 million to $278.1 million, an increase of about 8%. As shown in Table 3, the estimate for follow-on ships to be procured in FY2009-FY2011, when the LCS program is to reach its maximum 12 Statement of VADM Paul Sullivan, et al, Before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee on Surface Combatant Construction Update, July 24, 2007, p. 8. CRS-11 annual procurement rate of six ships per year, increased from $223.3 million to $298 million, an increase of about 33%. Table 3. LCS Sea Frame Unit Procurement Costs (costs in millions of then-year dollars) FY07 FY2006 budget submission Procurement cost 542.4 Number of ships 2 Unit procurement cost 271.2 FY2007 budget submission Procurement cost 520.7 Number of ships 2 Unit procurement cost 260.4 % change in unit pro(4%) curement cost, FY07 compared to FY06 FY08 FY09 FY10 FY11 FY09FY11 779.7 3 259.9 1,127.2 5 225.4 1,112.3 5 222.5 1,110.3 5 222.1 3,349.8 15 223.3 947.6 3 315.9 21% 1,764.3 6 294.1 30% 1,774.2 6 295.7 33% 1,825.4 6 304.2 37% 5,363.9 18 298.0 33% Source: Prepared by CRS using Navy data from FY2006 and FY2007 Navy budget submissions. The Navy stated in early 2006 that the cost increase from the FY2006 budget to the FY2007 budget was due mostly to the fact that LCS procurement costs in the FY2006 budget did not include items that are traditionally included in the so-called end cost — the total budgeted procurement cost — of a Navy shipbuilding program, such as Navy program-management costs, an allowance for changes, and escalation (inflation). The absence of these costs from the FY2006 LCS budget submission raised potential oversight issues for Congress, including the following: ! Why were these costs excluded? Was this a budget-preparation oversight? If so, how could such an oversight occur, given the many people involved in Navy budget preparation and review, and why did it occur on the LCS program but not other programs? Was anyone held accountable for this oversight, and if so, how? If this was not an oversight, then what was the reason? ! Did the Navy believe there was no substantial risk of penalty for submitting to Congress a budget presentation for a shipbuilding program that, for whatever reason, significantly underestimated procurement costs? ! Do LCS procurement costs in the budget now include all costs that, under traditional budgeting practices, should be included? If not, what other costs are still unacknowledged? CRS-12 ! Have personnel or other resources from other Navy programs been used for the LCS program in any way? If so, have the costs of these personnel or other resources been fully charged to the LCS program and fully reflected in LCS program costs shown in the budget? Further Increase Reported in 2007. On January 11, 2007, the Navy reported that LCS-1 was experiencing “considerable cost overruns.” The Navy subsequently stated that the estimated shipyard construction cost of LCS-1 is $350 million to $375 million. This suggested that the end cost of LCS-1 — the ship’s total budgeted procurement cost, which also includes costs for things such as Navy program-management costs and an allowance for changes — could be in excess of $400 million. The Navy has not publicly provided precise cost overrun figures for LCSs 2 and 4, but the Navy has stated that the cost overrun on LCSs 1 and 2 is somewhere between 50% and 75%, depending on the baseline that is used to measure the overrun. As discussed in the section below on the LCS procurement cost cap, it was reported on May 10, 2007, that the Navy would ask Congress to increase the procurement cost cap for the fifth and sixth LCSs to $460 million each in FY2008 dollars. This figure is roughly 53% higher than the approximate figure of roughly $300 million for follow-on LCSs in the FY2007 budget, as shown in Table 3. CBO July 2007 Estimate. At the July 24, 2007, hearing on Navy surface combatant programs, the Congressional Budget Office (CBO) presented its own estimates of potential LCS procurement costs: Several months ago, press reports indicated that the cost could well exceed $400 million each for the first two LCS sea frames. Recently, the Navy requested that the cost cap for the fifth and sixth sea frames be raised to $460 million, which suggests that the Navy’s estimate of the acquisition cost for the first two LCSs would be around $600 million apiece.... As of this writing, the Navy has not publicly released an estimate for the LCS program that incorporates the most recent cost growth, other than its request to raise the cost caps for the fifth and sixth ships. CBO estimates that with that growth included, the first two LCSs would cost about $630 million each, excluding mission modules but including outfitting, postdelivery, and various nonrecurring costs associated with the first ships of the class. As the program advances, with a settled design and higher annual rates of production, the average cost per ship is likely to decline. Excluding mission modules, the 55 LCSs in the Navy’s plan would cost an average of $450 million each, CBO estimates.13 13 Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J. Labs, Senior Analyst, [on] The Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the Subcommittee on Seapower and Expeditionary Forces Committee on Armed Services U.S. House of Representatives, July 24, 2007, p. 18. CRS-13 Lockheed Perspective on Cost Growth14. Lockheed said in February 2007 that cost growth on LCS-1 was due primarily to three factors: ! manufacturing issues that are typically discovered in the construction of a lead ship of a class; ! problems with vendors supplying components and materials for the ship; and ! changes in ship-construction standards directed by the Navy. A major vendor issue, Lockheed said, were the ship’s reduction gears, which link the ship’s gas-turbine engines to its waterjets (i.e., its propellers). Due to a faulty tool at the manufacturer (General Electric), the gears were manufactured incorrectly, causing a 27-week delay in delivery that forced a major resequencing of construction work on LCS-1. A second vendor issue concerned HSLA-80, a kind of steel used to build the bottom half of the ship’s hull.15 The same kind of steel is in demand for up-armoring U.S. Army and Marine Corps Humvees used in Iraq, leading to delays in obtaining it for the LCS program. The issue of ship-construction standards involves building the LCS to a standard called Naval Vessel Rules (NVR). Lockheed said it submitted its LCS bid in January 2004, using a combination of the high-speed naval craft (HSNC) rules issued by the American Bureau of Shipping (ABS) and a draft version of the NVR that the Navy had issued. The LCS design in the January 2004 bid, Lockheed said, was the design accepted by the Navy. The final version of the NVR, Lockheed said, was issued by the Navy in May 2004 and was much more extensive than the draft version. The final version, Lockheed said, impacted 75% of the completed design products for LCS-1, resulted in about 25% additional drawings, and required the ship to include more rugged construction and more capable components in various places. Lockheed believes that the lead-ship manufacturing issues and the faulty manufacturing of the reduction gears will not recur on follow-on Lockheed-built LCSs, but that the NVR issue will increase the cost of follow-on Lockheed-built LCSs. Lockheed said it took several actions in response to the situation concerning LCS-1, including: ! co-locating Lockheed management and the LCS’s naval architects (from the naval architectural firm of Gibbs & Cox) at the shipyard; 14 This section is based on a Lockheed briefing on the status of the LCS program presented to CRS on February 1, 2007. 15 HSLA means high-strength, low-alloy, and 80 is a measurement of the strength of the steel. CRS-14 ! ! ! ! ! ! increasing the number of Lockheed personnel at the shipyard through the addition of production managers with Navy shipbuilding experience; instituting process improvements at the shipyard; establishing new metrics for measuring performance on work packages at the shipyard; integrating the American Bureau of Shipping and the on-scene Navy supervisor of shipbuilding (SUPSHIP) into daily production meetings; strengthening the earned-value management system (EMVS) and financial-management processes for the program; and replacing senior management at the shipyard. Lockheed reportedly warned the Navy about increasing costs on LCS-1 on multiple occasions since March 2006 — a month after the FY2007 budget was submitted to Congress. Navy Perspective on Cost Growth16. The Navy testified in July 2007 that it established a Program Management Assist Group (PMAG) to conduct a review of cost growth associated with LCS 1, and to review projected costs for LCS 2, LCS 3 and LCS 4. The PMAG assessment was completed, and identified the following root causes of cost growth: • Aggressive cost goal and schedule • Pressure to build to schedule was strongly emphasized and generated cost growth. • The ambitious schedule relied upon concurrent design and construction that was not achieved. • For LCS 1, the timing of LM’s bid to the finalization of Naval Vessel Rules resulted in underestimated efforts for design and construction by the contractor. • The competitive environment created disincentive for the contractor to surface execution challenges to the Navy. The PMAG made several recommendations based on the assessment of LCS root causes: • Emphasize rigorous risk management for high risk programs, including incorporation of risk mitigation strategies directly into shipbuilding contracts. • ASN(RD&A)17 issue guidance highlighting critical program management functions and emphasizing chain of command notification of unexpected results, including details surrounding changes in contract baselines. • Conduct formal independent cost estimates before exercising future options or contracts in LCS. Incorporate appropriate risk margins in budgets for future LCS procurements. 16 This section is based in part on a Navy briefing on the status of the LCS program presented to CRS on February 5, 2007. 17 The Assistant Secretary of the Navy (Research, Development, and Acquisition) — the Navy’s acquisition executive. CRS-15 • Implement organizational changes across supporting offices: improving timing and staffing levels of on-site government oversight (Supervisor of Shipbuilding, SUPSHIP) to better match construction schedules; providing adequate resources and manning to the acquisition program office and supporting NAVSEA18 offices; and improving experience and training levels of the program managers and their staffs. • Implement contractual and acquisition policy changes to improve visibility and performance expectations. Responses to these recommendations will be addressed in the following discussion of the revised LCS program plan, and in a later overview of changes being made to prevent reoccurrence of LCS lessons across all Navy acquisition programs.19 GAO Perspective on Cost Growth. GAO testified in July 2007 that according to its own analysis of Navy data, the combined cost of LCSs 1 and 2 had increased from $472 million to $1,075 — an increase of 128%.20 GAO testified its LCSs at the Austal USA shipyard of Mobile, AL.5 5 Austal USA was created in 1999 as a joint venture between Austal Limited of Henderson, (continued...) CRS-5 Planned Procurement. As shown in Table 1, following the restructuring of the program in 2007, the Navy wants to procure a total of 21 LCSs through FY2013. Table 1. Actual and Planned LCS Procurement Through FY2013 (following restructuring of program in 2007) FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 1 1a 0a 1 2 3 3 4 6 Source: Navy FY2009 budget submission. a. Four additional LCSs originally that were funded by Congress in FY2007 and FY2008 (two in each year) were canceled by the Navy as part of the 2007 restructuring of the LCS program. Program Funding. Table 2 shows LCS acquisition (i.e., research and development plus procurement) funding for FY2007 through FY2013 as reflected in the FY2009 budget submission. The figures in the table reflect reprogramming of prior-year program funding undertaken as part of the Navy’s 2007 restructuring of the LCS program. In addition to the funding shown in the table, the LCS program also received about $1.7 billion in acquisition funding between FY2003 and FY2006. With Congress’s permission, the Navy procured the first and second LCSs through the Navy’s research and development account. Subsequent LCSs are being procured through the Navy’s ship-procurement account, called the Shipbuilding and Conversion, Navy (SCN) account. The Navy is procuring LCS mission packages through the Other Procurement, Navy (OPN) account. Total Acquisition Cost. The Navy has not provided an estimated total acquisition (i.e., development plus procurement) cost for the LCS program. CRS estimates that the LCS program (including mission packages) might have a total acquisition cost of roughly $29.6 billion. This estimate includes $2.5 billion in research and development costs (including the construction of first two LCS sea frames and the procurement of the first four mission packages), procurement of 53 additional LCS sea frames at a cost of $460 million each, and 64 mission packages procured at an average cost of about $42.3 million each.6 This estimates does not include costs for LCS-related aircraft procurement or weapon procurement, such as those shown in the APN and WPN rows of Table 2. 5 (...continued) Western Australia and Bender Shipbuilding & Repair Company of Mobile, AL. The GD LCS team also includes GD/BIW as prime contractor to provide program management and planning, provide technical management, and to serve as “LCS system production lead.” 6 The Navy reportedly wants to procure 24 mine warfare mission packages at an average cost of $68 million each, 16 antisubmarine warfare packages at an average cost of $42.3 million each, and 24 surface warfare packages at an average cost of $16.7 million each. (Emelie Rutherford, Littoral Combat Ship Mission Packages Range In Costs, Features,” Inside the Navy, September 3, 2007; for similar figures, see Christopher P. Cavas, “First LCS Mission Package Ready For Delivery,” DefenseNews.com, August 29, 2007.) CRS-6 Table 2. LCS Program Acquisition Funding, FY2007-FY2013 (millions of dollars; figures rounded to nearest million) Budget accounta FY07 FY08 FY09 FY10 FY11 FY12 FY13 Total for FY07 thru FY13 664 304 371 281 139 168 116 2044 SCN 93 337 920 1380 1380 1840 2760 8709 APN 37 37 55 73 76 96 103 478 WPN 0 0 3 25 47 45 11 131 OPN 79 0 131 235 242 252 227 1167 RDT&EN TOTAL 873 678 1480 1994 1884 2401 3217 12529 Source: Navy FY2009 budget submission. Figures may not add due to rounding. The program also received about $1.7 billion in acquisition funding between FY2003 and FY2006. a. RDT&EN = Research, Development, Test, and Evaluation, Navy account; SCN = Shipbuilding and Conversion, Navy account; APN = Aircraft Procurement, Navy account; WPN = Weapons Procurement, Navy account; OPN = Other Procurement, Navy account. 2007 Program Restructuring March 2007 Navy Restructuring Plan. In response to significant cost growth and schedule delays in the building of the first LCSs that first came to light in January 2007 (see next section), the Navy in March 2007 announced a plan for restructuring the LCS program that: ! canceled the two LCSs funded in FY2007 (LCSs 5 and 6) and redirected the funding for those two ships to pay for cost overruns on earlier LCSs; ! announced an intention to lift a 90-day stop-work order that the Navy had placed on LCS-3 in January 2007 — provided that the Navy reached an agreement with the Lockheed-led industry team by April 12, 2007, to restructure the contract for building LCSs 1 and 3 from a cost-plus type contract into a fixed price incentive (FPI)type contract — or terminate construction of LCS-3 if an agreement on a restructured contract could not be reached with the Lockheed team by April 12, 2007; ! announced an intention to seek to restructure the contract with the General Dynamics-led industry team for building LCSs 2 and 4 into an FPI-type contract — if LCSs 2 and 4 experienced cost growth comparable to that of LCSs 1 and 3 — and, if such a restructuring were sought, terminate construction of LCS-4 if an agreement on a restructured contract for LCS-2 and LCS-4 could not be reached; CRS-7 ! reduced the number of LCSs requested for FY2008 from three to two (for the same requested FY2008 procurement funding of $910.5 million), and the number to be requested for FY2009 from six to three; and ! announced an intention to conduct an operational evaluation to select a favored design for the LCS that would be procured in FY2010 and subsequent years, and to conduct a full and open follow-on competition among bidders for the right to build that design.7 April 2007 Termination of LCS-3. On April 12, 2007, the Navy announced that it had not reached an agreement with Lockheed on a restructured FPI-type contract for LCS-1 and LCS-3, and consequently was terminating construction of LCS-3.8 (The Navy subsequently began referring to the ship as having been partially terminated — a reference to the fact that Lockheed was allowed to continue procuring certain components for LCS-3, so that a complete set of these components would be on hand to be incorporated into the next LCS built to the Lockheed design.) November 2007 Termination of LCS-4. In late-September 2007, it was reported that the Navy on September 19 had sent a letter to General Dynamics to initiate negotiations on restructuring the contract for building LCSs 2 and 4 into an FPI-type contract. The negotiations reportedly were to be completed by October 19, 2007 — 30 days from September 19.9 On November 1, 2007, the Navy announced that it had not reached an agreement with General Dynamics on a restructured FPItype contract for LCS-2 and LCS-4, and consequently was terminating construction of LCS-4.10 July 2007 Navy Testimony on Common Combat System. The two LCS designs currently use two different, contractor-furnished combat systems.11 As an added element of its restructuring of the LCS program, the Navy testified in July 7 Source: Navy briefing to CRS and Congressional Budget Office (CBO) on Navy’s proposed LCS program restructuring plan, March 21, 2007. 8 Department of Defense News Release No. 422-07, April 12, 2007, “Navy Terminates Littoral Combat Ship 3.” 9 Geoff Fein, “Navy Seeking To Negotiate FPI Contract With General Dynamics,” Defense Daily, September 24, 2007; Geoff Fein, “Navy, General Dynamics Meet To Discuss New LCS Fixed Price Structure,” Defense Daily, September 27, 2007; Tony Capaccio, “General Dynamics Urged To Take Fixed Price On Warship Contract,” Bloomberg News, September 28, 2007; Jason Sherman, “Navy, General Dynamics Discuss Fixed-Price Contract For LCS,” Inside the Navy, October 1, 2007. 10 Department of Defense News Release No. 1269-07, November 1, 2007, “Navy Terminates Littoral Combat Ship (LCS 4) Contract.” 11 A ship’s combat system typically includes its sensors, computers, displays, and weapon launchers. The discussion here refers to the part of the LCS combat system that is permanently built into each sea frame, and not to the part that would be added by a modular mission package. CRS-8 2007 that it wants to shift to a common, government-furnished combat system for LCSs procured in FY2010 and beyond.12 The Navy proposed to begin work on the common combat system in FY2007 using some of the prior-year LCS program funding that the Navy has requested Congress to reprogram. August 2007 Navy Report on Acquisition Strategy. Although the Navy in its March 2007 restructuring plan announced an intention to conduct an operational evaluation to support the selection of a single LCS design to be procured in FY2010 and beyond, the Navy stated in an August 2007 report to Congress on the LCS program that “the Navy may elect to continue production of both seaframes should each design present a unique operational advantage.”13 March 2008 Navy Testimony on Acquisition Strategy The Navy testified in March 2008 that: The Navy believes that active oversight and strict cost controls are needed to deliver these ships [LCSs] to the fleet over the long run. The Navy demonstrated strong oversight when it terminated the contracts for LCS-3 and LCS-4 in 2007. It is vital that the Navy continue through first-of-class construction challenges to complete LCS 1 and LCS 2. When these ships are delivered, the Department [of the Navy] will be able to better evaluate their costs and capabilities. LCS 1 and LCS 2 are currently scheduled to deliver to the Navy in 2008. Both LCS 1 and LCS 2 will conduct post-delivery test and trials in 2009.... The FY 2009 President’s Budget request includes $920 million for two additional LCS seaframes. The Navy also intends to execute the FY 2008 appropriation for one seaframe, utilizing the remaining funding and material from the terminated ships. The Navy will also seek congressional support for the reprogramming of these funds for the FY 2008 procurement. Under an acquisition strategy approved in January 2008 by the Defense Acquisition Executive, the FY 2008 and 2009 awards will be for fixed-price incentive fee contracts, based on a limited competition between the current LCS seaframe prime contractors. These ships will be designated as Flight 0+ and will include all existing approved engineering changes developed from lessons learned, along with any current improvements to construction or fabrication procedures. The Navy will incorporate further lessons learned from LCS 1 and 2 sea trials into these ships prior to production. Any such changes will be minimized to those essential for safety and/or operability. Acquisition strategies for FY 2010 and follow ships are under Navy review. OSD will conduct a Milestone B prior to FY 2010 procurement. The Navy and 12 Statement of VADM Paul Sullivan et al., Before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee on Surface Combatant Construction Update, July 24, 2007, p. 8. 13 Report to Congress, Littoral Combat Ship, Prepared by Deputy Assistant Secretary of the Navy, Ships, Washington, DC 20350, August 2007, p. 7. See also p. 3. CRS-9 OSD will consider the questions of single seaframe assessment and competition plans as part of the FY 2010 acquisition strategy deliberations.14 Cost Growth on LCS Sea Frames Summary of Cost Growth. The Navy originally spoke of building LCS sea frames for about $220 million each — a figure that was later stated by the Navy to be expressed in constant FY2005 dollars. Estimated LCS sea frame procurement costs have since grown substantially above that figure. The estimate for LCS-1 has grown from $212.5 million in the FY2006 budget to $531 million in the FY2009 budget. The estimate for LCS-2 has grown from $256.5 million in the FY2006 budget to $507 million in the FY2009 budget. The figures of $531 million and $507 million in the previous paragraph are endcost figures. End cost is the figure often reported as the total procurement cost of a Navy ship. It is a fairly comprehensive figure for a ship’s procurement cost, but it does exclude certain cost elements. The FY2009 budget submission states that when additional costs for outfitting and post delivery and for “final system design/mission systems and ship integration team” are included, the total estimated procurement costs of LCS-1 and LCS-2 become $631 million and $636 million, respectively. The FY2009 budget submission also shows that the estimated cost of follow-on LCS sea frames has increased to $460 million each — the same figure that Congress used in 2007 in amending the unit procurement cost cap for LCS sea frame procurement. A March 2008 press report suggests that the cost of LCS-2 might increase by $41 million above the figures reported in the FY2009 budget submission. This increase, if realized, would increase the cost of LCS-2 to $548 million (end cost) or $677 million (more broadly defined cost). CBO testified in March 2008 that it estimates that the cost of LCS-1 and LCS-2 (more broadly defined) could increase to about $700 million each, and that the cost of follow-on LCSs could increase to about $550 million each. Review of Cost Growth Over Time. Estimated LCS sea frame procurement costs can be viewed as having increased three times — in early 2006, early 2007, and early 2008. Early 2006. The proposed FY2007 Navy budget, submitted in February 2006, showed that the estimate for the first LCS had increased from $212.5 million in the FY2006 budget to $274.5 million in the FY2007 budget, an increase of about 29%; that the estimate for the second LCS increased from $256.5 million in the FY2006 14 Statement of Vice Admiral Barry McCullough, Deputy Chief of Naval Operations For Integration of Capabilities and Resources, and Ms. Allison Stiller, Deputy Assistant Secretary of the Navy (Ship Programs), before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee on Navy Force Structure and Shipbuilding, March 14, 2008, pp. 3-4. CRS-10 budget to $278.1 million, an increase of about 8%; and that the estimate for followon ships scheduled for FY2009-FY2011, when the LCS program was to have reached a planned maximum annual procurement rate of six ships per year, had increased from $223.3 million to $298 million, an increase of about 33%. The Navy stated in early 2006 that the cost increase from the FY2006 budget to the FY2007 budget was due mostly to the fact that LCS procurement costs in the FY2006 budget did not include items that are traditionally included in the so-called end cost — the total budgeted procurement cost — of a Navy shipbuilding program, such as Navy program-management costs, an allowance for changes, and escalation (inflation). The absence of these costs from the FY2006 LCS budget submission raised certain potential oversight issues for Congress.15 Early 2007. On January 11, 2007, the Navy reported that LCS-1 was experiencing “considerable cost overruns.” The Navy subsequently stated that the estimated shipyard construction cost of LCS-1 had grown to $350 million to $375 million. This suggested that the end cost of LCS-1 — which also includes costs for things such as Navy program-management costs and an allowance for changes — could be in excess of $400 million. The Navy did not publicly provide a precise cost overrun figure for LCS 2, but it stated that the cost overrun on LCSs 1 and 2 was somewhere between 50% and 75%, depending on the baseline that is used to measure the overrun. The Government Accountability Office (GAO) testified in July 2007 that according to its own analysis of Navy data, the combined cost of LCSs 1 and 2 had increased from $472 million to $1,075 — an increase of 128%.16 The Congressional Budget Office (CBO) testified in July 2007 that: 15 These oversight issues included the following: — Why were these costs excluded? Was this a budget-preparation oversight? If so, how could such an oversight occur, given the many people involved in Navy budget preparation and review, and why did it occur on the LCS program but not other programs? Was anyone held accountable for this oversight, and if so, how? If this was not an oversight, then what was the reason? — Did the Navy believe there was no substantial risk of penalty for submitting to Congress a budget presentation for a shipbuilding program that, for whatever reason, significantly underestimated procurement costs? — Do LCS procurement costs in the budget now include all costs that, under traditional budgeting practices, should be included? If not, what other costs are still unacknowledged? — Have personnel or other resources from other Navy programs been used for the LCS program in any way? If so, have the costs of these personnel or other resources been fully charged to the LCS program and fully reflected in LCS program costs shown in the budget? 16 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), pp. 4 and 22. CRS-11 Several months ago, press reports indicated that the cost could well exceed $400 million each for the first two LCS sea frames. Recently, the Navy requested that the cost cap for the fifth and sixth sea frames be raised to $460 million, which suggests that the Navy’s estimate of the acquisition cost for the first two LCSs would be around $600 million apiece.... As of this writing, the Navy has not publicly released an estimate for the LCS program that incorporates the most recent cost growth, other than its request to raise the cost caps for the fifth and sixth ships. CBO estimates that with that growth included, the first two LCSs would cost about $630 million each, excluding mission modules but including outfitting, postdelivery, and various nonrecurring costs associated with the first ships of the class. As the program advances, with a settled design and higher annual rates of production, the average cost per ship is likely to decline. Excluding mission modules, the 55 LCSs in the Navy’s plan would cost an average of $450 million each, CBO estimates.17 Early 2008. As mentioned above, the proposed FY2009 budget, submitted in February 2008, showed that the estimated end costs of LCS-1 and LCS-2 had increased to $531 million and $507 million, respectively (or to $631 million and $636 million, respectively, when certain additional costs are included), and that the estimated unit cost of follow-on ships in the program has increased to $460 million. On March 14, 2008, the Navy testified that The end costs included in the FY 2009 President’s Budget request for LCS reflects [sic] the current estimates for LCS 1 and LCS 2 end cost. However, on February 25, 2008, after the submission of the President’s Budget to Congress, General Dynamics submitted to the Navy and over target baseline request for LCS 2. The Navy is reviewing the request prior to granting approval for General Dynamics to implement. The details of the request are business sensitive and proprietary. The Navy will continue to actively monitor LCS 1 and 2 cost and schedule performance and to keep the Office of the Secretary of Defense and Congress informed of those estimated costs. The Navy will seek congressional support to complete the reprogramming of FY 2007 LCS shipbuilding funds to complete LCS 1 and 2.18 A March 26, 2008, press report stated that the cost of LCS-2 will increase $41 million “for the year ending Sept. 30,” according to “a defense official with knowledge of the increase.”19 The press report characterized the $41-million increase 17 Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J. Labs, Senior Analyst, [on] The Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the Subcommittee on Seapower and Expeditionary Forces Committee on Armed Services U.S. House of Representatives, July 24, 2007, p. 18. 18 Statement of Vice Admiral Barry McCullough, Deputy Chief of Naval Operations For Integration of Capabilities and Resources, and Ms. Allison Stiller, Deputy Assistant Secretary of the Navy (Ship Programs), before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee on Navy Force Structure and Shipbuilding, March 14, 2008, p. 4. 19 Tony Capaccio, “General Dynamics Littoral Combat Ship Cost Jumps 9.3 Percent,” (continued...) CRS-12 as an increase of 9.3% in the ship’s estimated basic construction cost of $440 million. Basic construction cost is a component of ship end cost. When measured against the ship’s estimated end cost or its more broadly defined procurement cost as shown in the FY2009 budget ($507 million or $636 million, respectively), an increase of $41 million would equate to an increase of about 8.1% or about 6.4%, respectively. CBO testified on March 14, 2008 that: Historical experience indicates that cost growth in the LCS program was likely. In particular, historical cost-to-weight relationships using the lead ship of the FFG-7 Oliver Hazard Perry class frigate as an analogy indicate that the Navy’s original cost target for the LCS of $260 million in 2009 dollars (or $220 million in 2005 dollars) was optimistic. The first FFG-7 cost about $670 million in 2009 dollars to build, or about $250 million per thousand tons, including its combat systems. Applying that metric to the LCS program suggests the lead ships would cost about $600 million apiece, including the cost of one mission module. Thus, in this case, the use of an historical cost-to-weight relationship produces an estimate that is less than the actual costs of the first LCSs to date but substantially greater than the Navy’s original estimate. Based on the actual costs the Navy is incurring for the LCS program, CBO estimates that the first two LCSs could cost about $700 million each, including outfitting and postdelivery and various nonrecurring costs associated with first ships of a class, but excluding mission modules. That estimate is consistent with the estimate CBO provided to this Subcommittee last summer. However, as of December 2007, LCS-1 was 79 percent complete and LCS-2 was 65 percent complete. Thus, additional cost growth is possible, and CBO’s estimate reflects that cost risk. Overall, CBO estimates that the LCSs in the Navy’s plan would cost about $550 million each, on average, excluding mission modules. That estimate assumes that the Navy selects one of the two existing designs and makes no changes. As the program advances with a settled design and higher annual rates of production, average ship costs would probably decline, CBO estimates. If the Navy decides to make changes to that design in building future ships, however, the costs of those ships could be higher than what CBO estimates now.20 Reasons for Cost Growth. Navy and industry officials have attributed some of the cost growth on the LCS sea frames to an underestimation of the cost impact of applying new Naval Vessel Rules (NVR) — essentially, new rules specifying the construction standards for the ship — to the LCS program. The timing of NVR relative to LCS construction, Navy and industry officials have testified, created a situation of concurrency between design and construction in the LCS program, meaning that the ship was being designed at the same time that the shipyard was attempting to build it — a situation long known to be a potential cause of cost 19 (...continued) Bloomberg News, March 26, 2008. 20 Statement of Eric J. Labs, Senior Analyst, [on] Current and Projected Navy Shipbuilding Programs, before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, U.S. House of Representatives, March 14, 2008, p. 24. CRS-13 growth. This concurrency, Navy officials testified, was a consequence of the compressed construction schedule for the LCS program, which in turn reflected an urgency about getting LCSs into the fleet to meet critical mission demands. Regarding LCS-1 itself, Navy and industry officials testified that cost growth was also due to a main reduction gear that was incorrectly manufactured and had to be replaced, forcing a reordering of the construction sequence for the various major sections of LCS-1. In addition to NVR and the reduction gear issue, the Navy and industry might also have simply underestimated the baseline construction cost of the LCS. Shipyard performance is another potential cause of cost growth. A February 4, 2008, press report stated: Marinette Marine, the Wisconsin shipyard building the first Littoral Combat Ship, never received proper certification to manage the project, which has suffered severe cost growth and schedule delays, according to an internal naval audit obtained by sister publication Inside the Pentagon [ITP]. The interim report is the most damning account yet of the LCS program’s failure to use earned value management (EVM). Pentagon officials and contractors are supposed to use the process to manage the cost, schedule and performance of acquisition efforts. The idea is to coordinate key project goals and objectively measure progress. In prepared testimony for his Senate confirmation hearing last October, Pentagon acquisition executive John Young noted that EVM was a “serious deficiency” in the LCS program. The audit reveals how this deficiency has undermined work on the Freedom (LCS-1), which Marinette Marine is building for Lockheed Martin. The review, which began a year ago, is still ongoing. However, ITP obtained a redacted copy of the Jan. 7 interim report, originally stamped “for official use only,” through the Freedom of Information Act.... The review reveals Marinette Marine’s poor management and faults the Navy, the Defense Contract Management Agency (DCMA) and Lockheed for failing to notice and fix the problem. The press report also states: Robert Herre, the president and general manager of Manitowoc Marine Group, which operates the shipyard, told ITP in an interview that Marinette Marine never worked on a project before that required the robust EVM needed for the Freedom contract. The management software that the shipyard acquired several years ago was not up to the task. Marinette Marine tried to adapt for the Freedom project by using a manual system, too, Herre said, but it became “more of a cumbersome process than first thought.” Lockheed spokesman Craig Quigley blamed “cost and schedule baseline disconnects” on the Navy for making big changes to the Freedom without CRS-14 agreeing, until last November, to rebaseline both the program’s cost and schedule. Previously only the schedule had been rebaselined, he said. Lockheed’s team has maintained an EVM system baseline on the program and accurately reported monthly variances, he said. “Not having the cost and schedule baseline in synchronization prohibits accurate system predictions, but that was accounted for via adjunct reports,” he added. The report says DCMA and Naval Sea Systems Command did not provide sufficient oversight to ensure proper management of the contract; the Navy’s Gulf Coast-based shipbuilding office and industry did not effectively review the EVM, or lack thereof; and the program office and the shipyard “placed limited emphasis” on the implementation of EVM for the contract. DCMA initially granted a “conditional approval” for Marinette Marine’s EVM system in April 2006, the report says. The conditional nod was based on a Navy-led EVM system review conducted the year before. However, Pentagon policy does not allow for a “conditional approval” of a contractor’s EVM system. DCMA only recognized its error 10 months later, in February 2007, according to the report. The agency then alerted the program office, Lockheed and Marinette Marine that the “conditional approval” had been inappropriate. Now all agree Marinette Marine lacks a DCMA-validated EVM system, a problem that must be fixed. The report says Marinette Marine’s EVM system did not provide valid and reliable cost, schedule, and technical performance data to support the LCS program office’s decision-making. Auditors found the shipyard was not following 24 of the Pentagon’s 32 EVM rules. DCMA failed to check whether the 32 rules were being followed. Further, the Navy and DCMA failed to perform formal surveillance to ensure the shipyard heeded the rules, the report says. And Marinette Marine failed to use EVM as an integrated program management tool. As a result, the Navy is “not receiving full value for program management services and information paid for under this contract,” the report states. The press report also states: The report describes a “significant breakdown in internal controls.” Navy decision-makers are not receiving accurate and reliable earned value data for the Freedom, the review says. The shipyard’s projected estimates-at-completion for the Freedom contract are “not supported.” Further, the program office “did not have visibility” for project work totaling approximately $51 million. The lack of oversight left the Navy’s financial interest in the ship’s construction unprotected, the review concludes.... Auditors recommended eight fixes. The report says four remain to be done, but Quigley said two remain to be done. Last November, the Navy completed a new estimate for the cost of completing the Freedom contract, conducted a schedule review and had the program develop a new baseline for the ship. Officials have also had Lockheed start work on a plan to fix the problems. CRS-15 Quigley said officials have reviewed, approved and monitored Lockheed’s plan. He also said the shipyard’s efforts are now being checked continuously against the 32 rules. In March [2008], the Navy plans to review the new baseline. And DCMA is due to conduct a review to ensure the shipyard is following the rules by year’s end, the report says. Quigley said that last step could take 18 months. Unlike Marinette Marine, Lockheed and Gibbs & Cox (another team member), have EVM certification, he said. Young’s predecessor, Kenneth Krieg, warned in a memo last summer that the Pentagon’s EVM efforts were “insufficient, especially given the number of major defense programs experiencing execution problems.”21 GAO testified in July 2007 that: We have frequently reported on the wisdom of using a solid, executable business case before committing resources to a new product development effort.... A sound business case would establish and resource a knowledge-based approach at the outset of a program. We would define such a business case as firm requirements, mature technologies, and an acquisition strategy that provides sufficient time and money for design activities before construction start. The business case is the essential first step in any acquisition program that sets the stage for the remaining stages of a program, namely the business or contracting arrangements and actual execution or performance. If the business case is not sound, the contract will not correct the problem and execution will be subpar. This does not mean that all potential problems can be eliminated and perfection achieved, but rather that sound business cases can get the Navy better shipbuilding outcomes and better return on investment. If any one element of the business case is weak, problems can be expected in construction. The need to meet schedule is one of the main reasons why programs cannot execute their business cases. This pattern was clearly evident in both the LPD 17 [amphibious ship] and LCS programs. In both cases, the program pushed ahead with production even when design problems arose or key equipment was not available when needed. Short cuts, such as doing technology development concurrently with design and construction, are taken to meet schedule. In the end, problems occur that cannot be resolved within compressed, optimistic schedules. 18 Naval Sea Systems Command — the branch of the Navy with lead responsibility for acquisition of ships. 19 Statement of VADM Paul Sullivan, et al, Before the Subcommittee on Seapower and Expeditionary Forces of the House Armed Services Committee on Surface Combatant Construction Update, July 24, 2007, pp. 9-10. 20 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), pp. 4 and 22. CRS-16 Ultimately, when a schedule is set that cannot accommodate program scope, delivering an initial capability is delayed and higher costs are incurred.... What happens when the elements of a solid business case are not present? Unfortunately, the results have been all too visible in the LPD 17 and the LCS. Ship construction in these programs has been hampered throughout by design instability and program management challenges that can be traced back to flawed business cases. The Navy moved forward with ambitious schedules for constructing LPD 17 and LCS despite significant challenges in stabilizing the designs for these ships. As a result, construction work has been performed out 21 Christopher J. Castelli, “Audit Exposes Failed Management of Troubled Littoral Warship,” Inside the Navy, February 4, 2008. CRS-16 of sequence and significant rework has been required, disrupting the optimal construction sequence and application of lessons learned for follow-on vessels in these programs.... In the LCS program, design instability resulted from a flawed business case as well as changes to Navy requirements. From the outset, the Navy sought to concurrently design and construct two lead ships in the LCS program in an effort to rapidly meet pressing needs in the mine countermeasures, antisubmarine warfare, and surface warfare mission areas. The Navy believed it could manage this approach, even with little margin for error, because it considered each LCS to be an adaptation of an existing high-speed ferry design. It has since been realized that transforming a high-speed ferry into a capable, networked, survivable warship was quite a complex venture. Implementation of new Naval Vessel Rules (design guidelines) further complicated the Navy’s concurrent design-build strategy for LCS. These rules required program officials to redesign major elements of each LCS design to meet enhanced survivability requirements, even after construction had begun on the first ship. While these requirements changes improved the robustness of LCS designs, they contributed to out of sequence work and rework on the lead ships. The Navy failed to fully account for these changes when establishing its $220 million cost target and 2-year construction cycle for the lead ships. Complicating LCS construction was a compressed and aggressive schedule. When design standards were clarified with the issuance of Naval Vessel Rules and major equipment deliveries were delayed (e.g., main reduction gears), adjustments to the schedule were not made. Instead, with the first LCS, the Navy and shipbuilder continued to focus on achieving the planned schedule, accepting the higher costs associated with out of sequence work and rework. This approach enabled the Navy to achieve its planned launch date for the first Littoral Combat Ship, but required it to sacrifice its desired level of outfitting. Program officials report that schedule pressures also drove low outfitting levels on the second Littoral Combat Ship design as well, although rework requirements have been less intensive to date. However, because remaining work on the first two ships will now have to be completed out-of-sequence, the initial schedule gains most likely will be offset by increased labor hours to finish these ships. The difficulties and costs discussed above relate to the LCS seaframe only. This program is unique in that the ship’s mission equipment is being developed and funded separately from the seaframe. The Navy faces additional challenges integrating mission packages with the ships, which could further increase costs and delay delivery of new antisubmarine warfare, mine countermeasures, and surface warfare capabilities to the fleet. These mission packages are required to meet a weight requirement of 180 metric tons or less and require 35 personnel or less to operate them.c However, the Navy estimates that the mine CRS-17 countermeasures mission package may require an additional 13 metric tons of weight and 7 more operator personnel in order to deploy the full level of promised capability. Because neither of the competing ship designs can accommodate these increases, the Navy may be forced to reevaluate its planned capabilities for LCS.21 Potential Oversight Issues. Potential oversight issues raised by the reported further increase in LCS sea frame unit procurement costs include the following: 21 ! When did various Navy leaders first learn of the cost increase on LCS-1? Why did the Navy wait until January 2007 to publicly reveal the cost increase? Lockheed testified at the February 8, 2007 hearing that it sends monthly reports with LCS cost information to the Navy. In which of these monthly reports did Lockheed first attempt to alert the Navy regarding the potential for significant cost growth on LCS1? ! When will the Navy announce its estimates of cost overruns on LCSs 2 and 4? ! How much of the cost increase on LCSs 1, 2 and 4 attributable to prime contractor performance? To performance by supplier firms? To Navy actions in managing the 22 22 Defense Acquisitions[:] Realistic Business Cases Needed to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and Sourcing Management (continued...) CRS-17 Potential Oversight Issues for Congress Cost Growth on LCS Sea Frames Potential oversight issues concerning cost growth on LCS sea frames include the following: 22 ! Are the actions taken by the Navy as part of its restructuring of the LCS program sufficient to prevent further growth in estimated LCS sea frame unit procurement costs? ! How much of the cost increases on LCSs 1 and 2 are attributable to prime contractor performance? To shipyard performance? To performance by supplier firms? To Navy actions in managing the program? ! Concurrency in design and construction has long been known as a source of risk in shipbuilding and other weapon-acquisition programs. Eliminating concurrency forms part of DOD’s effort to move toward best practices in acquisition. In retrospect, did the Navy make a good decision in letting its sense of urgency about the LCS override the known risks of concurrency in design and construction? ! When will the Navy have a sense of whether corrective actions taken by the Navy and industry in response to the cost growth are succeeding in controlling LCS construction costs? ! Do the estimated costs of LCSs 1, 2, and 42 reflect systems, components, or materials provided by vendors at reduced prices as part of an effort by those vendors to secure a role in the 55-ship LCS program? If so, how much more expensive might these systems, components, or materials become on later LCSs? Is this a source of concern concern regarding the potential for cost growth on follow-on LCSs? ! In light of cost growth LCSson LCS sea frames, where does the LCS program now stand in relation to the Nunn-McCurdy provision (10 U.S.C. §2433), Ibid, pp. 8-11. CRS-18 which requires certain actions to be taken if the cost of a defense acquisition program rises above certain thresholds? ! How might the increase in LCS unit procurement costs affect the number of LCSs that the Navy can afford to procure each year, and the total number it can afford to procure over the long run? ! Is the Navy planning to financefinancing cost growth on LCS sea frames by reducing reducing funding for the procurement of LCS mission packages? For For example, is cost growth on LCS sea frames linked in some way to to the reduction in the planned number of LCS mission packages from the from (...continued) Team, Testimony Before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), pp. 8-11. CRS-18 an earlier figure of 90 to 110 to the current figure of 64? If the Navy Navy is financing cost growth on LCS sea frames by reducing funding for the procurement of LCS mission packages, how might this reduce the capabilities of the planned 55-ship LCS fleet? ! In light of the cost growth, is the LCS program still cost-effective? For follow-on LCSs, what is the unit procurement cost, in FY2008 dollars, above which the Navy would no longer consider the LCS program cost-effective? ! If Congress had known in 2004, when it was acting on the FY2005 budget that contained funding to procure LCS-1, that LCS sea frame unit procurement costs would increase to the degree that they have, how might that have affected Congress’s views on the question of approving the start of LCS procurement? ! How might the increase in LCS unit procurement costs affect the affordability and executability of the Navy’s overall shipbuilding program?2223 ! What implications, if any, does the increase in LCS unit procurement costs have for estimated procurement costs of other new Navy ship classes?23 22 On this point, CRS testified in July 2007: “LCS cost growth reported since January 2007 is one of three developments in recent months that have increased the risks associated with implementing the Navy’s 30-year shipbuilding plan.” (Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the House Armed Services Committee Subcommittee on Seapower and Expeditionary Forces Hearing on Surface Combatant Construction Programs, July 24, 2007, p. 1) For further discussion of this issue, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O’Rourke. 23 On this point, CBO testified in July 2007: “The relatively simple design of the LCS and the large cost increases that have occurred in the program suggest that the Navy may also have trouble meeting its cost targets for the larger, much more complex surface combatants in its shipbuilding plan, such as the DDG-1000 and the CG(X).” (Statement of J. Michael Gilmore, Assistant Director for National Security, and Eric J. Labs, Senior Analyst, [on] The Navy’s 2008 Shipbuilding Plan and Key Ship Programs, before the Subcommittee on (continued...) CRS-19 Cost Cap on Fifth and Sixth Ships A second issue for Congress concerns the Navy’s request to amend the current procurement cost cap on the fifth and sixth LCSs.24 On May 10, 2007, it was reported that the Navy would ask Congress to increase the procurement cost cap for the fifth and sixth LCSs to $460 million each in FY2008 dollars. This $460-million figure applies to end cost — the total budgeted procurement cost of the ship. The Navy’s request that Congress increase the procurement cost cap for the fifth and sixth LCSs to $460 million each in FY2008 dollars raises potential questions for Congress, including the following: ! Given the Navy’s termination of LCS-3 and its proposal to cancel the two LCSs funded in FY2007, which LCSs should now be considered the fifth and sixth ships? ! Is $460 million per ship in FY2008 dollars a reasonable figure to use for the cost cap? ! Should the cost cap be amended so that it applies not only to the fifth and sixth LCSs, but to some or all subsequent ships in the program? In connection with the second question above, CRS testified in July 2007 that: One potential issue for the subcommittee is whether $460 million would be an excessive figure to use in amending the LCS cost cap. Prior to the May 10 news report, Navy testimony and other public statements had suggested that LCSs might cost upwards of $400 million each, or perhaps a bit more than $400 million each, to procure. The Chief of Naval Operations testified in February [207] that he was “embarrassed” by cost growth on the LCS program. In light of this, one question is whether Navy settled on the $460-million figure in part 23 (...continued) Seapower and Expeditionary Forces Committee on Armed Services U.S. House of Representatives, July 24, 2007, p. 18.) 24 Navy officials stated to CRS in 2006 that LCSs 5 and 6 would meet the legislated cost cap for those two ships of $220 million per ship because the hands-on construction costs of the ships, when adjusted for inflation, would fall within the $220-million figure. (Source: Information paper provided to CRS by Navy Office of Legislative Affairs, April 3, 2006) The Navy’s explanation suggested that the Navy was interpreting the LCS cost cap as something that applied to the hands-on construction costs of the ships, rather than to end cost — the larger procurement costs of the ships as they appear in the budget, which include costs for other items, such as Navy program-management costs and allowance for changes. The LCS cost cap (Sec. 124 of H.R. 1815/P.L. 109-163) refers to “the total amount obligated or expended for procurement of the fifth and sixth vessels....” The Navy’s explanation on this issue at the time raised certain potential oversight questions for Congress, including the following: Does the Navy’s apparent interpretation of the meaning of the LCS cost cap mean that the Navy will interpret cost caps on other Navy shipbuilding programs the same way, so as to exclude budgeted procurement costs other than the actual hands-on construction costs of the ships? Is the Navy’s apparent interpretation of the LCS cost cap consistent with how the Navy interpreted past legislated cost caps on ships such as the Seawolf-class submarines and the aircraft carrier CVN-77? CRS-20 because it would permit the LCS program to experience some additional (albeit unanticipated or unwanted) cost growth without causing the Navy the additional embarrassment of exceeding a cost cap that Congress had amended at the Navy’s request. From the Navy’s perspective at least, there would be value in avoiding such additional embarrassment. At the same time, however, if the $460-million figure is somewhat higher than what the Navy currently expects the fifth and sixth ships to cost, then amending the cost cap to the $460-million level could create a situation in which additional cost growth to the $460-million figure might be viewed by some as acceptable. Such a view might not be conducive to rigorous cost control on the program.25 When asked at the same hearing whether the $460 million figure was the correct figure to use to amend the cost cap, the Navy testified: We think that the $460 million cost cap is the right number. We’ve worked that through our cost estimating and budget process, and we’ve had that approved by the CNO and the Secretary [of the Navy] that we believe that’s what these ships are going to cost to produce in FY08 dollars as an end cost.26 In connection with the third question above, CRS testified in July 2007 that: Another potential issue for the subcommittee is whether the LCS cost cap should be amended to apply not just to the fifth and sixth ships in the program, but to subsequent ships in the class as well. The cost cap on the CVN-78 aircraft carrier program (Section 122 of the FY2007 defense authorization act [H.R. 5122/P.L. 109-364 of October 17, 2006]) includes caps for both the lead ship (CVN-78) and for any follow-on ships in the class. The cost cap on the LHA-6 (LHA[R]) amphibious ship program (Section 125 of the FY2007 defense authorization act) applies to any ship constructed under the program. The cost cap for the LPD-17 program (Section 126 of the FY2007 defense authorization act) includes individual caps for ships six through nine in the program — the final four ships that the Navy plans to procure.27 Total Program Acquisition Cost Although this CRS report estimates that a 55-ship LCS program with 64 mission packages might have a total acquisition cost of roughly $23.8 billion to $29.6 billion, the potential total acquisition cost of the LCS program is uncertain. Supporters could argue that total program acquisition cost will become clearer as the Navy works 25 Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the House Armed Services Committee Subcommittee on Seapower and Expeditionary Forces Hearing on Surface Combatant Construction Programs, July 24, 2007, pp. 3-4. 26 Transcript of spoken remarks of Rear Admiral Barry McCullough at July 24, 2007, hearing before House Armed Services Committee Subcommittee on Seapower and Expeditionary Forces Hearing on Surface Combatant Construction Programs. 27 Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the House Armed Services Committee Subcommittee on Seapower and Expeditionary Forces Hearing on Surface Combatant Construction Programs, July 24, 2007, p. 4. CRS-21 through the details of the program. Critics could argue that a major acquisition program like the LCS program should not proceed at full pace until its potential total acquisition costs are better understood. Termination of LCS-3 Another potential issue for Congress concerns the Navy’s decision to terminate construction of LCS-3. Potential questions raised by this decision include the following: ! What were the remaining differences between the Lockheed and Navy positions that prevented an agreement on a restructured contract? Were the negotiating positions of one or both sides unreasonable? Would the two sides have been more likely to come to an agreement if the Navy had provided more than 30 days of negotiating time? ! What are the termination costs associated with terminating construction of LCS-3? How do these costs compare with the potential cost of building LCS-3 under cost plus-type or FPI-type contracting terms? ! How much unexpended LCS-3 funding is available for potentially covering cost overruns on LCSs 1, 2, and 4? ! How will the decision to terminate LCS-3 affect Bollinger, the shipyard firm that was to build the ship? ! Where would be the next Lockheed-designed LCS be built — at Marinette or Bollinger? ! What implications, if any, does the termination of LCS-3 have for the Navy’s planned operational evaluation for selecting a favored LCS design to procure in FY2010 and beyond? (For more discussion on this question, see the next section.) ! Does the Navy’s decision to terminate LCS-3 send a signal to Congress or industry about Navy or Department of Defense (DOD) contracting approaches or other acquisition issues, and if so, what signal? Was the Navy’s decision to terminate LCS-3 intended in part to send a signal? Operational Evaluation and Competition for Production Potential for Keeping Two Designs in Production. As mentioned in the Background section, although the Navy intends to conduct an operational evaluation to support the selection of a single LCS design to be procured in FY2010 and beyond, the Navy also stated in an August 2007 report to Congress on the LCS program that it may “elect to continue production of both seaframes should each design present a CRS-22 unique operational advantage.” Potential oversight questions for Congress include the following: ! What are the potential comparative production and life-cycle operation and support (O&S) costs of procuring a single design vs. procuring both designs in FY2010 and beyond? ! What unique operational advantages might each design have, and how would these advantages compare to the additional costs of keeping both LCS designs in production in FY2010 and beyond? Potential Implications of LCS-3 Termination.28 Lockheed is concerned that the Navy’s decision to terminate construction of LCS-3 will create a bias against the Lockheed LCS design in the operational evaluation that the Navy plans to conduct to select a favored design for procurement in FY2010 and beyond, and also a bias against the Lockheed-led industry team in the planned follow-on competition to determine which firm or firms should build the winning LCS design. Lockheed is concerned about a potential bias against its design in the LCS operational evaluation for two reasons. The first is that LCS-3 would have incorporated one modification of the design used for LCS-1. Lockheed is concerned that, without LCS-3 in built form, the Navy will not be able to confirm through realworld tests the improvement in ship performance resulting from this or other potential design modifications that LCS-3 would have incorporated. The second is that without building LCS-3, the Navy at the time of the evaluation will lack a data point showing improvement in production costs for the Lockheed design in moving down the learning curve from LCS-1 to LCS-3. Lockheed believes this second data point would increase Navy confidence in the potential production costs of follow-on LCSs built to the Lockheed design. Lockheed is concerned about a potential bias against the Lockheed-led industry team in the follow-on competition to determine which firm or firms should build the winning LCS design because, without LCS-3, the Lockheed-led team’s LCS design staff, shipyards, and suppliers will go “cold,” compared to the General Dynamics-led industry team’s design staff, shipyard, and suppliers, who will build LCS-4 after LCS-2, and will consequently remain “hot.”29 The Navy’s position is that since the LCS operational evaluation will be determined by fundamental differences between the two LCS designs, the additional performance resulting from design modifications planned for LCS-3 will not be a critical factor. The Navy says that since the fleet will make the flyoff decision based 28 This section is adapted from Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the House Armed Services Committee Subcommittee on Seapower and Expeditionary Forces Hearing on Surface Combatant Construction Programs, July 24, 2007, pp. 4-5. 29 The paragraphs summarizing Lockheed’s position are based on consultations with Lockheed officials on July 17, 2007, and previous dates, and are presented with Lockheed’s permission. CRS-23 on the operational performance of the two designs, and not on acquisition-related factors such as potential construction cost, the absence of a second data point on the Lockheed LCS production cost learning curve will not be a factor in the decision. The Navy’s position on the follow-on competition to determine which firm or firms will build the winning design is that the Lockheed-led industry team would be brought back into a “hot” status in time for the competition if Congress funds the LCSs that the Navy wants to procure in FY2008 and FY2009 and some of those ships are then awarded to the Lockheed-led team.30 Treatment of LCSs Built to Losing Design. Under the Navy’s restructured plan for the LCS program, a total of eight LCSs are to be procured through FY2009. Depending on how LCSs procured in FY2008 and FY2009 are awarded between the two competing industry teams, three to five of these eight LCSs might be built to the design that is not chosen by the Navy as a result of the operational evaluation. Compared to the LCSs built to the winning design, these three to five LCSs will likely have some unique operation and support (O&S) costs. The Navy could choose to operate these ships with their unique O&S costs, or sell them to foreign buyers, or modify their combat systems or other features so as to make them more like the Navy’s other LCSs in terms of their O&S requirements. Potential Oversight Questions. Potential oversight questions for Congress include the following: 30 ! How does the Navy intend to conduct the operational evaluation of the two LCS designs? Does the termination of LCS-3 create a bias against the Lockheed design in the operational evaluation, or against the Lockheed-led industry team in the subsequent competition to select a firm or firms to build the winning design? How might this issue be affected by Congress’s decision regarding the Navy’s request for funding to procure two LCSs in FY2008? ! If firms that designed the winning LCS design are not among those selected to build it, what message might that send to industry regarding stability in Navy shipbuilding plans, and the potential benefits of investing industry funds in the design of Navy ships, and in facilities to produce them? ! When does the Navy anticipate being able to report to Congress on its strategy regarding the three to five LCSs built to what turns out to be the design that is not chosen by the Navy as a result of the operational evaluation? The paragraphs summarizing the Navy’s position are based on consultations with Navy officials on July 16, 2007, and are presented with the Navy’s permission. CRS-24 Proposed Common Combat System As mentioned in the Background section, the Navy is proposing to shift to a common, government-furnished combat system for LCSs procured in FY2010 and beyond, and is proposing to begin work on the common combat system in FY2007 using some of the prior-year LCS program funding that it has requested Congress to reprogram. Some observers believe that the common combat system amounts to a new start (i.e., starting a new acquisition effort), and that new starts should not be initiated through a reprogramming of prior-year funding, since that can bypass the normal process for Congress to fully review a proposed new start prior to deciding whether to grant initial approval for it. The Navy argues that the common combat system would not amount to a new start because the effort would simply replace unique components of the two existing contractor-furnished combat systems with a single set of combat system components. Potential oversight questions for Congress 24 Total Program Acquisition Cost Although this CRS report estimates that a 55-ship LCS program with 64 mission packages might have a total acquisition cost of roughly $29.6 billion, the potential total acquisition cost of the LCS program is uncertain. Supporters could argue that total program acquisition cost will become clearer as the Navy works through the details of the program. Critics could argue that a major acquisition program like the LCS program should not proceed at full pace until its potential total acquisition costs are better understood. Procurement Cost Cap Unlike cost caps for certain other Navy shipbuilding programs that Congress has established in recent years, the amended cost cap for the LCS program (Section 125 23 For a discussion of the potential affordability of the Navy’s overall shipbuilding program, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O’Rourke. 24 On this point, CBO testified in March 2008: “The relatively simple design of the LCS and the substantial cost increases that have occurred in the program suggest that the Navy may also have trouble meeting its cost targets for the larger, much more complex surface combatants in its shipbuilding plan, such as the DDG-1000 and the CG(X).” (Statement of Eric J. Labs, Senior Analyst, [on] Current and Projected Navy Shipbuilding Programs, before the Subcommittee on Seapower and Expeditionary Forces, Committee on Armed Services, U.S. House of Representatives, March 14, 2008, p. 24.) CRS-19 of the conference report [H.Rept. 110-477 of December 6, 2007] on H.R. 1585, the FY2008 defense authorization bill, which was enacted as H.R. 4986/P.L. 110-181 of January 28, 2008) does not include a provision allowing the cost cap to be increased over time in response to inflation. The Navy testified in February 2008 that it anticipates asking Congress at some point to amend the cost cap to permit the cap to be adjusted over time for inflation.25 Operational Evaluation and Competition for Production As mentioned in the Background section, although the Navy intends to conduct an operational evaluation to support the selection of a single LCS design to be procured in FY2010 and beyond, the Navy also stated in an August 2007 report to Congress on the LCS program that it may “elect to continue production of both seaframes should each design present a unique operational advantage.” Depending on how LCSs procured in FY2008 and FY2009 are awarded between the two competing industry teams, a couple of LCSs might be built to the design that is not chosen by the Navy as a result of the operational evaluation. Compared with the LCSs built to the winning design, these other LCSs will likely have some unique operation and support (O&S) costs. The Navy could choose to operate these ships with their unique O&S costs, sell them to foreign buyers, or modify their combat systems or other features so as to make them more like the Navy’s other LCSs in terms of their O&S requirements. Potential oversight questions for Congress include the following: 25 ! How does the Navy intend to conduct the operational evaluation of the two LCS designs? ! Does the Navy’s schedule provide enough time to evaluate LCS-1 and LCS-2 adequately before making a decision on which design or designs to build in FY2010 and beyond? ! What are the potential comparative production and life-cycle operation and support (O&S) costs of procuring a single design vs. procuring both designs in FY2010 and beyond? ! What unique operational advantages might each design have, and how would these advantages compare to the additional costs of keeping both LCS designs in production in FY2010 and beyond? ! If firms that designed the winning LCS design are not among those selected to build it, what message might that send to industry regarding stability in Navy shipbuilding plans, and the potential Source: transcript of spoken remarks of Allison Stiller at February 27, 2008 hearing on Navy shipbuilding before the Defense subcommittee of the House Appropriations Committee. CRS-20 benefits of investing industry funds in the design of Navy ships, and in facilities to produce them? ! When does the Navy anticipate being able to report to Congress on its strategy regarding LCSs built to a design that is not chosen by the Navy as a result of the operational evaluation? Proposed Common Combat System As mentioned in the Background section, the Navy testified in July 2007 that it wants to shift to a common, government-furnished combat system for LCSs procured in FY2010 and beyond, and proposed to begin work on the common combat system in FY2007 using some of the prior-year LCS program funding that it had requested Congress to reprogram. Some observers believe that the common combat system amounts to a new start (i.e., starting a new acquisition effort), and that new starts should not be initiated through a reprogramming of prior-year funding, since that can bypass the normal process for Congress to fully review a proposed new start prior to deciding whether to grant initial approval for it. The Navy argued that the common combat system would not amount to a new start because the effort would simply replace unique components of the two existing contractor-furnished combat systems with a single set of combat system components. Potential oversight questions for Congress include the following: ! What are the potential costs and operational benefits of maintaining one or both of the current contractor-furnished combat systems vs. shifting to a common, government-furnished combat system? ! Does the Navy’s plan to shift to a common, government-furnished combat system amount to a new start, and if so, would it be acceptable to fund that new start with reprogrammed prior-year funds? Pace of Mission Package Procurement The Navy’s decision to terminate construction of LCS-3 and its proposal to cancel LCSs 5 and 6 and reduce planned procurements of LCSs in FY2008 and FY2009 would reduce the number of LCSs that wouldCoordination of Sea Frames and Mission Packages The termination of construction of LCSs 3 through 6 reduced the number of LCSs that will be delivered to the fleet over the next few years. This, in turn, could reduce the number of LCS mission packages the Navy wouldwill need to have in inventory in the near term. This raises a potential oversight issue for Congress regarding whether the Navy’s planned schedule for procuring LCS sea frames is properly coordinated with its planned schedule for procuring LCS mission packages. Mission Packages Funded in OPN Account As mentioned in the Background section, the Navy plans to procure LCS mission packages through the Other Procurement, Navy (OPN) appropriation account rather than the Navy’s ship-procurement account. The OPN account, as its name suggests, is a large, “grab-bag” appropriation account for procuring a wide variety of items, many of them miscellaneous in nature. Supporters of the Navy’s plan can argue that it is consistent with the traditional practice of procuring ship weapons (e.g., missiles and gun shells) through the Weapon Procurement, Navy (WPN) appropriation account or the Procurement of Ammunition, Navy and Marine Corps (PANMC) appropriation account rather than the ship-procurement account. LCS mission packages, they could argue, are the CRS-25 payload of the LCS, just as missiles and gun shells are the payload of other types of surface combatants, and should therefore be funded outside the ship-procurement account. Those skeptical of the Navy’s plan to fund LCS mission packages through the OPN account could argue that the LCS mission packages are not comparable to missiles and gun shells. Missiles and gun shells, they could argue, are expendable items that are procured for use by various classes of ships while the LCS mission packages will incorporate sensors as well as weapons, are not intended to be expendable in the way that missiles and gun shells are, and are to be used largely, if not exclusively, by LCSs, making them intrinsic to the LCS program. In light of this, they could argue, it would be more consistent to fund LCS mission packages in the ship-procurement account rather than the OPN account. Potential oversight questions for Congress include the following: ! Are LCS mission packages analogous to missiles and gun shells that are procured through the WPN and PANMC appropriation accounts? ! Does the Navy’s plan to fund the LCS mission packages through this account effectively obscure a significant portion of the total LCS program acquisition cost by placing them in a part of the Navy’s budget where they might be less visible to Congress? If so, was this the Navy’s intention? ! Does funding a significant portion of the LCS program’s total procurement cost through the OPN account give the LCS program an unfair advantage in the competition for limited ship-procurement funding by making the LCS program, as it appears in the shipprocurement account, look less expensive? If so, was this the Navy’s intention? Options for Congress A primary issue for Congress at this point is whether to approve, reject, or modify the Navy’s proposed LCS program restructuring plan, and what additional actions, if any, should be taken in response to the Navy’s decision to terminate construction of LCS-3. Potential options for Congress include but are not limited to the following: ! Number of ships procured in FY2008. Congress could approve the Navy’s amended request to procure two LCSs in FY2008, or approve funding for the procurement of a lesser or greater number. ! Cost cap. Congress could approve the Navy’s request to amend the cost cap on the fifth and sixth LCSs to $460 million, or approve a CRS-26 different dollar figure, or apply the cost cap to LCSs beyond numbers five and six. ! LCS-3. Congress could direct the Navy to reinstate procurement of LCS-3, or legislate terms or conditions regarding the way in which the Navy executes the termination of LCS-3. ! LCS-4. Congress could direct the Navy to terminate procurement of LCS-4, or legislate terms or conditions regarding the way in which procurement of LCS-4 is to proceed. ! LCSs 5 and 6. Congress could approve the Navy’s request to cancel LCSs 5 and 6 and use the funding for the two ships to pay for cost growth on earlier LCSs and other LCS program costs, or direct the Navy to proceed with the procurement of one or both ships, or specify how the funding for one or both of the ships is to be used. ! Contracting. Congress could provide instructions to the Navy regarding the types of contracts to be used in procuring LCSs or executing other aspects of the program. ! Mission packages. Congress could approve the Navy’s FY2008 request for funding for procurement of LCS mission packages, or approve a different amount, or specify terms and conditions regarding procurement of mission packages. ! Research and development funding. Congress could approve the Navy’s FY2008 request for funding for research and development work on the LCS program, or approve a different amount, or specify terms and conditions for how the funding is to be used. ! Operational evaluation and production competition. Congress could establish terms and conditions for the LCS operational evaluation and the subsequent production competition. ! Reporting requirements. Congress could impose new reporting requirements for the program so as to facilitate congressional oversight on issues such as cost growth. FY2008 Legislative Activity FY2008 Defense Authorization Bill (H.R. 1585/S. 1547) House. The House Armed Services Committee, in its report (H.Rept. 110-146 of May 11, 2007) on the FY2008 defense authorization bill (H.R. 1585): ! recommends $710.5 million in the Shipbuilding and Conversion, Navy (SCN) account for the procurement of two LCSs — a $200- CRS-27 million reduction from the Navy’s FY2008 request of $910.5 million, which was originally requested by the Navy to fund the procurement of three LCSs and later amended by the Navy to fund the procurement of two LCSs; ! directs the Secretary of the Navy to submit a report on several aspects of the LCS program; and ! recommends $20.3 million in the Other Procurement, Navy (OPN) account for the procurement of LCS mission modules — a $60million reduction from the Navy’s original FY2008 request. The committee’s report states: The committee notes with concern the significant cost growth experienced within the LCS program, which has recently led to a termination of a contract option to construct the third ship of the class. In testimony before the Subcommittee on Seapower and Expeditionary Forces on February 8, 2007, Navy and industry witnesses agreed that the original ship construction schedule for the lead ship was overly aggressive and that Navy and industry program managers sought to maintain schedule performance, rather than cost performance, to the detriment of cost-effective construction. The witnesses also agreed that additional major cost drivers on the lead ship were caused by the inclusion of the new naval vessel rules into the design of the ship without a pause in the construction schedule. Additionally, a necessary component for the propulsion system arrived late to the construction yard changing the most efficient construction sequence for the vessel. The committee commends the Secretary of the Navy for taking action to identify the issues discussed above; however the committee remains concerned that recent Navy decisions to terminate the option for the third ship may eliminate the benefit of a competitive environment for this program. The proposed 55 ship class represents a significant portion of the Chief of Naval Operations plan for a 313 ship Navy. If the Secretary cannot maintain affordability in this vital program, the 313 ship fleet cannot be realized. The committee believes it is imperative that the Navy pursue all reasonable means to control costs in the LCS program. The committee believes that a key component of cost control is competition. The committee strongly encourages the Navy to avoid defaulting to a single design acquisition strategy for fiscal years 2008 and 2009 and expects the Navy to take all reasonable steps necessary to ensure continued competition between the two LCS designs. The committee is convinced that the capability that this vessel will bring to the Navy is of the utmost urgency for responding to asymmetric threats. The committee understands that in order to cover the cost increases of the first three ships, the Secretary intends to submit to Congress an above threshold reprogramming requesting for the appropriations for the two ships authorized in fiscal year 2007. Further, the Secretary has communicated a request that the committee only authorize two of the three ships submitted in the budget for fiscal year 2008. CRS-28 The committee recommends $710.5 million, a decrease of $200.0 million from the budget request, for the construction of two ships in fiscal year 2008. The committee directs the Secretary of the Navy to submit a report to the congressional defense committees by August 1, 2007, on the analysis of the root causes of the LCS cost overruns; the methods and procedures put in place throughout the various Program Executive Offices ensuring these mistakes are not repeated in other programs; the structure of the Navy’s current contractual agreements with both LCS prime contractors along with justification for differences between the two, if any; an explanation of the Navy’s plan for testing of the two different ship variants; and an analysis of alternatives for future procurement and deployment of the LCS. (Pages 78-79) The House-reported version of H.R. 1585 contains a provision (Section 127) that would require that construction of a first ship in a shipbuilding program not start until the Secretary of the Navy has certified that the detailed design of the ship is completed and approved by the relevant design certification agents, to a level determined by the Secretary to be acceptable for commencement of construction. The provision states: SEC. 127. LIMITATION ON CONCURRENT DESIGN AND CONSTRUCTION ON FIRST SHIP OF A SHIPBUILDING PROGRAM. (a) In General- For any shipbuilding program that is a major defense acquisition program under section 2430 of title 10, United States Code, the start of construction of a first ship (as defined in subsection (b)) may not occur until the Secretary of the Navy certifies to the congressional defense committees that the detailed design of the ship is completed and approved by the relevant design certification agents, to a level determined by the Secretary to be acceptable for commencement of construction, via a report described in subsection (d). (b) First Ship- For purposes of subsection (a), a ship is a first ship if — (1) the ship is the first ship to be constructed under that shipbuilding program; (2) the shipyard at which the ship is to be constructed has not previously started construction on a ship under that shipbuilding program; or (3) the ship is the first ship to be constructed following a major design change, characterized as a change in flight, under that shipbuilding program. (c) Start of Construction- For purposes of subsection (a), start of construction means the beginning of fabrication of the hull and superstructure of the ship. (d) Report- The Secretary of the Navy shall provide the certification required by subsection (a) in a report that provides an assessment of each of the following: (1) The degree of completion of the detailed design drawings and specifications for the ship. (2) The readiness of the shipyard facilities and workforce to begin construction. CRS-29 (3) The maturity level of research and development efforts of any new technologies that will be used in the ship’s command and control systems, weapons systems, sensor systems, mechanical or electrical systems, or hull. (4) The ability to meet cost and schedule estimates within the applicable program baseline. (e) Applicability(1) NEW SHIPBUILDING PROGRAMS- This section applies to each shipbuilding program beginning after the date of the enactment of this Act. (2) MAJOR DESIGN CHANGES FOR EXISTING SHIPBUILDING PROGRAMS- In addition, subsection (b)(3) applies to any major design change occurring after the date of the enactment of this Act to any shipbuilding program in existence as of the date of the enactment of this Act. The House-reported version of H.R. 1585 also contains a provision (Section 822) requiring federal agencies that award more than $1 billion in contracts per year to develop and implement plans to maximize the use of fixed-price contracts. The section states: SEC. 822. MAXIMIZING FIXED-PRICE PROCUREMENT CONTRACTS. (a) Plans Required- Subject to subsection (c), the head of each executive agency covered by title III of the Federal Property and Administrative Services Act of 1949 (41 U.S.C. 251 et seq.) or, in the case of the Department of Defense, the Under Secretary of Defense for Acquisition, Technology, and Logistics, shall develop and implement a plan to maximize, to the fullest extent practicable, the use of fixed-price type contracts for the procurement of goods and services by the agency or department concerned. The plan shall contain measurable goals and shall be completed and submitted to the Committee on Oversight and Government Reform of the House of Representatives, the Committee on Homeland Security and Governmental Affairs of the Senate, and the Committees on Appropriations of the House of Representatives and the Senate and, in the case of the Department of Defense and the Department of Energy, the Committees on Armed Services of the Senate and the House of Representatives, with a copy provided to the Comptroller General, not later than 1 year after the date of the enactment of this Act. (b) Comptroller General Review- The Comptroller General shall review the plans provided under subsection (a) and submit a report to Congress on the plans not later than 18 months after the date of the enactment of this Act. (c) Requirement Limited to Certain Agencies- The requirement of subsection (a) shall apply only to those agencies that awarded contracts in a total amount of at least $1,000,000,000 in the fiscal year preceding the fiscal year in which the report is submitted. Senate. Section 132 of the Senate-passed version of H.R. 1585, which was added by floor amendment as part of the Senate’s consideration of S. 1547/H.R. CRS-30 1585, as reported by the Senate Armed Services Committee,31 makes certain findings about the importance of the LCS program and about the causes of cost growth in the construction of the first LCSs; increases the procurement cost cap for the fifth and sixth LCSs to $460 million each, plus adjustments for certain factors; requires the Navy to use fixed-price contracts for the construction of the fifth and subsequent ships in the program; and limits the government’s cost liability for the fifth and sixth ships in the program to $460 million each. The section states: SEC. 132. LITTORAL COMBAT SHIP (LCS) PROGRAM. (a) Findings- Congress makes the following findings: (1) The plan of the Chief of Naval Operations to recapitalize the United States Navy to at least 313 battle force ships is essential for meeting the long-term requirements of the National Military Strategy. (2) Fiscal challenges to the plan to build a 313-ship fleet require that the Navy exercise discipline in determining warfighter requirements and responsibility in estimating, budgeting, and controlling costs. (3) The 55-ship Littoral Combat Ship (LCS) program is central to the shipbuilding plan of the Navy. The inability of the Navy to control requirements and costs on the two lead ships of the Littoral Combat Ship program raises serious concerns regarding the capacity of the Navy to affordably build a 313-ship fleet. (4) According to information provided to Congress by the Navy, the cost growth in the Littoral Combat Ship program was attributable to several factors, most notably that — (A) the strategy adopted for the Littoral Combat Ship program, a so-called `concurrent design-build’ strategy, was a high-risk strategy that did not account for that risk in the cost and schedule for the lead ships in the program; (B) inadequate emphasis was placed on `bid realism’ in the evaluation of contract proposals under the program; (C) late incorporation of Naval Vessel Rules into the program caused significant design delays and cost growth; (D) the Earned Value Management System of the contractor under the program did not adequately measure shipyard performance, and the Navy program organizations did not independently assess cost performance; (E) the Littoral Combat Ship program organization was understaffed and lacking in the experience and qualifications required for a major defense acquisition program; 31 Section 132 was added by S.Amdt 3077 to S.Amdt 2011 to H.R. 1585. S.Amdt 3077 was agreed to by unanimous consent on September 27, 2007. S.Amdt. 2011 to H.R. 1585 was agreed to by unanimous consent on October 1, 2007. CRS-31 (F) the Littoral Combat Ship program organization was aware of the increasing costs of the Littoral Combat Ship program, but did not communicate those cost increases directly to the Assistant Secretary of the Navy in a time manner; and (G) the relationship between the Naval Sea Systems Command and the program executive offices for the program was dysfunctional. (b) Requirement- In order to halt further cost growth in the Littoral Combat Ship program, costs and government liability under future contracts under the Littoral Combat Ship program shall be limited as follows: (1) LIMITATION OF COSTS- The total amount obligated or expended for the procurement costs of the fifth and sixth vessels in the Littoral Combat Ship (LCS) class of vessels shall not exceed $460,000,000 per vessel. (2) PROCUREMENT COSTS- For purposes of paragraph (1), procurement costs shall include all costs for plans, basic construction, change orders, electronics, ordnance, contractor support, and other costs associated with completion of production drawings, ship construction, test, and delivery, including work performed post-delivery that is required to meet original contract requirements. (3) CONTRACT TYPE- The Navy shall employ a fixed-price type contract for construction of the fifth and following ships of the Littoral Combat Ship class of vessels. (4) LIMITATION OF GOVERNMENT LIABILITY- The Navy shall not enter into a contract, or modify a contract, for construction of the fifth or sixth vessel of the Littoral Combat Ship class of vessels if the limitation of the Government’s cost liability, when added to the sum of other budgeted procurement costs, would exceed $460,000,000 per vessel. (5) ADJUSTMENT OF LIMITATION AMOUNT- The Secretary of the Navy may adjust the amount set forth in paragraphs (1) and (4) for either vessel referred to in such paragraph by the following: (A) The amounts of increases or decreases in costs attributable to compliance with changes in Federal, State, or local laws enacted after September 30, 2007. (B) The amounts of outfitting costs and costs required to complete post-delivery test and trials. (c) Repeal of Superseded Authority- Section 124 of the National Defense Authorization Act for Fiscal Year 2006 (Public Law 109-163; 119 Stat. 3157) is repealed. The Senate Armed Services Committee, in its report (S.Rept. 110-77 of June 5, 2007) on the FY2008 defense authorization bill (S. 1547): ! recommends $480 million in the Shipbuilding and Conversion, Navy (SCN) account for the procurement of one LCS — a reduction of $430.5-million and one ship from the Navy’s amended FY2008 request of $910.5 million for two LCSs — but “directs that funds authorized for a fiscal year 2008 LCS ship may only be used when CRS-32 combined with LCS SCN funds appropriated in prior years, to solicit, on a competitive basis, bids for two fixed price LCS ship construction contracts, one for each of the two competing LCS variants”; ! directs the Secretary of Defense to submit a report on the acquisition strategy for the LCS program; and ! recommends $15.3 million in the Other Procurement, Navy (OPN) account for the procurement of LCS mission modules — a $65 million reduction from the Navy’s original FY2008 request. With regard to SCN funding for the program and the report to be done by the Secretary of Defense on the program’s acquisition strategy, the committee’s report states: The first ship (LCS-1) was scheduled to deliver in late 2006. The Navy is now estimating that the first ship will deliver sometime in the middle of 2008. The LCS-1 contractor team had barely started on their second ship (LCS-3) when the program ran into major cost problems earlier this year. The Navy then issued a stop work order on LCS-3 in order to reduce expenditures and limit further cost exposure on the program while it separately re-evaluated program cost estimates. The Navy entered into negotiations with the LCS-1 team to sign up to a fixed price contract on the two ships or face outright cancellation on the second ship. These negotiations occurred during this past spring. When the stop work order was nearly ready to expire, the Navy announced that it and the LCS-1 contractor team were unable to reach an agreement and that the Navy was terminating the contract for LCS-3 for the convenience of the Government. It is too early to precisely estimate the termination costs, but the Navy has reported that significant funds for LCS-3 are on hold pending completion of the termination negotiations. The second contractor team has a contract to build two LCS vessels of another design (LCS-2 and LCS-4). The Navy awarded this contract later, so LCS-2 is roughly 1 year behind the LCS-1. Unfortunately, it appears that this team is experiencing similar cost problems. The Navy has not issued the same ultimatum to this contractor team, but has claimed that the Navy will do so if the cost of LCS-2 continues to grow toward the Navy’s estimate. Meanwhile, the Navy is proceeding with the start of construction on LCS-4, although it is not clear that the root causes for early cost growth on LCS-2 have been addressed. The committee is disappointed that the cost of the lead ship has more than doubled and the delivery schedule has slipped several times. The committee commends the Secretary of the Navy for exercising oversight and for trying to bring cost and schedule discipline to this troubled program. The committee is also interested in supporting the Secretary’s efforts to improve the Navy’s acquisition process. Reviewing this LCS situation will undoubtedly result in a new set of “lessons learned” that the acquisition community will dutifully try to implement. However, the committee has previously expressed concerns about the LCS concept and the LCS acquisition strategy. The LCS situation may be more a case of “lessons lost.” Long ago, we CRS-33 knew that we should not rush to sign a construction contract before we have solidified requirements. We also knew that the contractors will respond to incentives, and that if the incentives are focused on maintaining schedules and not on controlling cost, cost growth on a cost-plus contract should surprise no one. After the fact, everyone appears ready to agree that the original ship construction schedule for the lead ship was overly aggressive. The Navy has said that the capability that this vessel will bring to the fleet is of the utmost urgency for responding to asymmetric threats. The committee believes that if the Navy really believed that the threat were that urgent, it might have taken more near-term steps to address it. For example, the Navy might not have cancelled the remote minehunting system (RMS) capability on a number of the DDG-51 class destroyers, ships that will be available to the combatant commanders much sooner than LCS. The Navy might also have taken this modular capability slated for the LCS and packaged those modules to deploy sooner on ships of opportunity. Rather, the Navy is waiting on a shipbuilding program to deliver that capability (in a useful quantity) at some future date. The Navy now proposes to use the funds requested in fiscal year 2008 to award contracts for two LCS vessels, rather than the three originally envisioned. Given the uncertainty about what is happening with the earlier ships in the program and uncertainties about the options for an acquisition strategy that will remain available to the Navy next year, the Navy does not intend to award these two contracts until late in fiscal year 2008. In summary: (1) a high degree of cost uncertainty will continue to overshadow the LCS program until the two lead ships execute test and trials, starting late in 2007. (2) the Navy’s current estimate is that the approximately $1.6 billion appropriated for the first six ships will be required to complete the three ships currently under contract, with significant additional funding being held for termination of a fourth ship. (3) if the Navy’s estimates are correct, or low, then the Navy will be engaging in fixed price negotiations with the second prime contractor for LCS-2 and LCS-4 late in 2007, with the distinct possibility that LCS-4 would be terminated. (4) if the Navy’s estimates are high, then sufficient funding from within previous appropriations should be available for a newly procured LCS. (5) the Navy has yet to formulate its acquisition strategy for the LCS program, however, the challenges inherent to fair competition between two dissimilar ship designs have become LCS-3 (or potential termination of LCS-4). (6) the Navy has announced a delay for conducting a program downselect decision until 2010, at which time it also plans to revise the LCS combat system, which raises concerns regarding the infrastructure and life cycle support costs for the three or four ships of the LCS variant not selected for “full rate production.” (7) program delays have pushed the next notional contract award until late in fiscal year 2008. (8) termination negotiations for LCS-3 will likely be proceeding at the same time the prime contractor is being solicited for a proposal to build another LCS ship, in which case the material procured for LCS-3 would likely revert back to the contractor for this new procurement. The net effect is that the current LCS-3 obligations that are fenced for termination costs would sufficiently cover the contractor’s fiscal year 2008 obligations for a newly procured LCS. CRS-34 The committee recommends $480.0 million for LCS in fiscal year 2008, a decrease of $430.5 million. We cannot relive the early days of the LCS program and remember “lessons learned,” but we have the opportunity to take positive steps now to right the program. Before awarding contracts for additional ships in the LCS program, we need to maintain focus on delivering the most capability possible for the $1.6 billion invested thus far for six ships. This would require that we impose accountability for the quality of program estimates; halt further changes to program requirements; and ensure that the contracts provide effective incentives for cost performance. The Secretary of the Navy has advised the committee that the Navy’s estimates appear to be quite conservative based on contractor performance over the past quarter, as measured against recently revised baselines. Although further risk is acknowledged, the Navy has expressed confidence that the program will be able to improve on the Navy’s worst case estimates and avoid further termination action. If the Navy and industry are successful in managing costs going forward, this should allow four ships to be delivered within previously appropriated funds. The committee notes that the LCS-1 contractor was awarded a lead ship contract that targeted a significantly lower price and a significantly more aggressive schedule for starting construction. The risks inherent in this aggressive schedule were exacerbated by changes to Navy requirements. These factors may have contributed to the decision to terminate LCS-3 — an outcome referred to as “winner-loses.” The resultant imbalance between the two competing shipbuilders jeopardizes the Navy’s ultimate goal for a competitive downselect in 2010, followed by full and open competition for the winning LCS variant. Therefore, the committee directs that funds authorized for a fiscal year 2008 LCS ship may only be used when combined with LCS SCN funds appropriated in prior years, to solicit, on a competitive basis, bids for two fixed price LCS ship construction contracts, one for each of the two competing LCS variants. The Secretary of the Navy may waive this requirement only if: he determines that there is only one acceptable LCS variant, based on completion of acceptance trials on the two LCS variants; and he notifies the congressional defense committees 30 days before releasing a solicitation based on that waiver determination. The committee believes that the history of the LCS acquisition strategy has been one of documenting decisions, rather than guiding and informing decisions. Therefore, the Secretary of Defense is directed to submit a report on the approved acquisition strategy for the LCS program at least 90 days prior to issuing any solicitation or requests for proposal, but no later than December 1, 2008. (Pages 97-100) With regard to OPN funding for the program, the committee’s report states: As described elsewhere in this report, the LCS program has run into serious problems. The committee sees no particular reason to acquire mission modules at the pace planned by the Navy, since there have been significant delays in the ship program. The committee recommends a decrease of $65.0 million for LCS modules. (Page 100) CRS-35 FY2008 Defense Appropriations Bill (H.R. 3222) House. The House Appropriations Committee, in its report (H.Rept. 110-279 of July 30, 2007) on the FY2008 defense authorization bill (H.R. 3222), recommends: ! $339.5 million in the Shipbuilding and Conversion, Navy (SCN) account for the procurement of one LCS — a $571 million reduction from the Navy’s FY2008 request of $910.5 million, which was originally requested by the Navy to fund the procurement of three LCSs and later amended by the Navy to fund the procurement of two LCSs; ! zero funding in the Other Procurement, Navy (OPN) account for the procurement of LCS mission modules — a $80.3 million reduction from the Navy’s original FY2008 request; and ! $229.0 million in the Navy’s research and development account for the LCS program — an $11.5 million increase over the requested amount, with the additional funding to be used for “Anti-Submarine Warfare (ASW) Contact Management Mission Planning Improvement” ($3.5 million), “LCS Mission Package Enterprise” ($5 million), and “Remote Multi-Mission Vehicle Anti-Submarine Warfare (ASW) Mission Module for LCS” ($3 million). With regard to ship-procurement funding, the committee’s report states: The Littoral Combat Ship (LCS) was conceived as a low cost, flexible, rapidly fielded platform to counter asymmetric littoral threats and conduct coastal missions. With a stated requirement of 55 vessels, the LCS will comprise a significant portion of the Navy’s 313 ship fleet. However, this program has been plagued by cost growth and schedule delays. Although many variables have contributed to this growth, the underlying reason can be attributed to concurrency between ship design and ship construction. Through fiscal year 2007, the Congress has appropriated funds for the construction of six LCS vessels. The Navy has terminated the contract for one of these ships and has proposed using the funding for two more ships to pay for cost growth within the program. The end result will be that the funding originally appropriated for six ships will actually only procure three vessels. The Committee is disturbed by the revelation that the recent efforts of the Congress to improve the Navy’s shipbuilding program via the LCS program have not borne fruit. In light of the recent LCS problems, the Committee believes that the best course of action is to allow the program to stabilize, finalize the design, obtain actual program costs, and firm up the outyear acquisition strategy. Therefore, the Committee provides $339,482,000 for the procurement of a single LCS, a reduction of $571,000,000. This funding is to be combined with the materials purchased in prior years for the LCS whose contract was terminated [LCS-3], which the Committee understands to be approximately $120,000,000. This allows the Navy to have sufficient funding/materials to purchase a ship at the proposed fiscal year 2008 LCS cost cap value of $460,000,000. (Page 229; see also page 227) The report also states: CRS-36 Outfitting funds [in the Navy’s shipbuilding account] are used to acquire on-board repair parts, equipage and other secondary items to fill the ships initial allowances. The request includes $4,900,000 in fiscal year 2007 and $4,900,000 in fiscal year 2008 to satisfy outfitting requirements for LCS-3. Since the construction contract for LCS-3 was terminated by the Navy, these funds are excess to requirement. The fiscal year 2007 funds will carry forward and be used to satisfy fiscal year 2008 requirements for other ships. Therefore, the fiscal year 2008 outfitting account is reduced by $9,800,000. Additionally, since the delivery date of LCS-4 has been delayed, the outfitting account also contains an excess of $5,000,000 that was appropriated in fiscal year 2007 and can now be used to satisfy other ship requirements. Therefore, the fiscal year 2008 outfitting program can be reduced an additional $5,000,000 to account for this delay. (Page 230) With regard to mission package procurement funding, the report states: The Littoral Combat Ship (LCS) is a small surface combatant and will operate with the flexibility to be configured with one of a variety of three different mission modules depending on the tasking. The Navy plan for mission modules is to procure a total of 64 LCS modules for the 55 ship class. The request includes $80,324,000 for the procurement of two mission modules and associated procurement support as well as $2,900,000 for spare parts. At the time of the submission, funding had been appropriated for the procurement of six ships and six mission modules through fiscal year 2007. Since the submission of the request, only three of these six ships will actually be constructed. The Committee believes the six mission modules purchased in prior years will be more than sufficient to satisfy near term LCS requirements considering the reduced near term LCS construction quantity. Therefore, no funding is provided for the procurement of LCS mission modules and associated spares. (Pages 242243) The report also states: The Vertical Take-off Unmanned Aerial Vehicle (VTUAV) will provide real-time Intelligence, Surveillance and Reconnaissance (ISR) data to tactical users without the use of manned aircraft or national assets. The VTUAV program will initially satisfy mission requirements for the Littoral Combat Ship (LCS). However, the LCS program is experiencing significant program delays and only three of the six ships appropriated through fiscal year 2007 will actually be constructed. With this slowdown in the LCS program, the Committee believes it is prudent to slow the procurement of LCS-associated equipment and therefore provides no funding for the three VTUAV aircraft (and associated support equipment) requested in the budget. (Page 210) The committee’s recommended additions to the LCS program’s requested FY2008 research and development funding appear on page 336 of the committee’s report. Senate. The Senate Appropriations Committee, in its report (S.Rept. 110-155 of September 14, 2007) on H.R. 3222, recommends: ! zero funding in the Shipbuilding and Conversion, Navy (SCN) account for the procurement of additional LCSs in FY2008 — a CRS-37 $910.5-million reduction from the Navy’s FY2008 request, which was originally requested by the Navy to fund the procurement of three LCSs and later amended by the Navy to fund the procurement of two LCSs; ! $75 million in additional FY2008 advance procurement funding in the SCN account for the procurement of a Flight 1 LCS in FY2009; ! cancelling construction of LCS-4, and rescinding $300 million in prior-year funding for the ship (the rescission is written into Section 8401 of the bill); ! $15 million in funding in the Other Procurement, Navy (OPN) account for the procurement of LCS mission modules — a $65.3 million reduction from the Navy’s original FY2008 request; and ! $300.5 million in the Navy’s research and development account for the LCS program — an $83 million increase over the requested amount, with the additional funding to be used for fully funding the construction of LCSs 1 and 2, which were originally procured through the Navy’s research and development account ($81 million), and for “new payloads and sensors unmanned surface vehicle program” ($2 million). With regard to ship-procurement funding, the committee’s report states: The Committee supports the capability envisioned by the LCS program. The LCS program is extremely important and will provide the Navy with the necessary tools to face the asymmetric threats of the future. The Committee notes that the LCS does not replace a current capability in the fleet but provides a new capability for future commanders. The Committee strongly supports the development of a surface combatant vessel that can be acquired in affordable volume production. The LCS program, planned as a 55 ship class, is an integral component of the Navy’s future shipbuilding plan. Unfortunately, the LCS program has been plagued with significant cost growth and schedule slip. Time has shown that the initial acquisition strategy of the LCS was ill-conceived. The short history of the LCS program, as outlined in the report to accompany S. 1547, the National Defense Authorization Act for Fiscal Year 2008 [S.Rept. 110-77 of June 5, 2007], has been a case study in how not to acquire ships. The Committee has concluded that a fundamental change needs to be made to the current LCS acquisition strategy in order to develop a ship that meets future naval requirements and can be affordably procured. The Committee also believes that the Navy will require additional time to correct the cost, schedule and performance issues with the LCS mission modules and the new start development of a common combat system. Therefore, the Committee makes the following recommendations: CRS-38 — no funding for additional LCS seaframes, a reduction of $910,500,000; — a rescission of $300,000,000 in fiscal year 2007 LCS funding, cancelling LCS-4; — an addition of $75,000,000 in advance procurement funding for one LCS Flight 1 seaframe in fiscal year 2009; and — full funding for the development and construction of LCS 1 and 2. Due to the significant uncertainty surrounding the LCS program, the Committee does not believe that funding for additional seaframes in fiscal year 2008 is justified. The Committee believes that only one ship of each design is required for the Navy to conduct a comprehensive evaluation of the competing designs that will result in the down select of one design for the Flight 1 LCS seaframe. The cancellation of LCS-4 will leave the Navy with one ship of each design for operational performance testing by the fleet. The Committee understands that both LCS-1 and LCS-2 will deliver in the third quarter of fiscal year 2008. Upon delivery of both ships, the Navy is directed to proceed with a comprehensive evaluation of both designs as soon as practicable. This will allow the Navy sufficient time to conduct operational performance testing of both ships and make a down-select decision in late fiscal year 2008. The Committee has every confidence that the Secretary of the Navy will ensure that a fair competition takes place between the two ship designs. The Committee further directs the Navy to include in the fiscal year 2009 budget submission a new acquisition strategy for the future procurement of the LCS class. The Committee expects the Navy to proceed with an acquisition strategy that includes a full and open competition for the Flight 1 ships. The Committee further expects the Navy to continue with its plan providing “contract design packages” to industry and conducting a new competition for Flight 1 ships. The Committee directs the Navy to include lead and follow shipyards and open this competition to shipyards not currently involved in the LCS program. The Committee also directs the Navy to use fixed priced incentive contracting for all Flight 1 ships. (Pages 133-134) With regard to mission package procurement funding, the report states: Due to disruptions in the LCS program, as well as technical challenges to several components of the mission modules, the Committee recommends $15,000,000, a reduction of $65,324,000. The Committee recommended amount provides for one Remote Minehunting Vehicle to maintain production facilities and one Airborne Laser Mine Detection System in anticipation of an accelerated initial operational capability. The Committee urges the Navy to reexamine the future years’ schedule for production of mission packages to reflect the delays crsphpgw in the LCS program. (Page 145) procuring LCS mission packages. On the issue of coordination of sea frames and mission packages, an October 2007 GAO report stated: The Navy has made progress developing individual mine countermeasures systems and the Littoral Combat Ship.... However, significant challenges remain to fielding new capabilities. • Operational testing plans for four systems in limited production will not provide a complete understanding of how the systems will perform when CRS-21 operated from the Littoral Combat Ship. Other ships will be used in testing to inform full-rate production decisions on the individual systems. While other ships may serve as platforms for the anti-mine systems, the Littoral Combat Ship is their primary platform, and it will have different launch, recovery, and handling systems. In addition, Navy plans call for testing these systems in smooth, uncluttered environments, although operating environments are expected to be less favorable. • The first two Littoral Combat Ships have encountered design and production challenges. Costs are expected to more than double from initial estimates, and the Navy anticipates lead ship delivery nearly 18 months later than first planned. This may slow the planned transition from current mine countermeasures platforms. • The Navy has reduced its investments in intelligence preparation of the environment capabilities — including the capability to locate and map minefield boundaries — even though improvements in this area could reduce mine countermeasures mission timelines by 30 to 75 percent. These capabilities are especially important for the Littoral Combat Ship, as it must stand clear of suspected minefields. The Navy has refined its concepts of operation for the Littoral Combat Ship, increasing awareness of operational needs. However, the Navy has not yet reconciled these concepts with the ship’s physical constraints, and the trade-offs involved ultimately will determine the ship’s capabilities. For example, operation of mine countermeasures systems is currently expected to exceed the personnel allowances of the ship, which could affect the ship’s ability to execute this mission. In addition, the Littoral Combat Ship will have only limited capability to conduct corrective maintenance aboard. However, because the Navy recently reduced the numbers of certain mission systems from two to one per ship, operational availability for these systems may decrease below current projections. Moreover, the mine countermeasures mission package currently exceeds its weight limitation, which may require the Navy to accept a reduction in speed and endurance capabilities planned for the Littoral Combat Ship. It is important that the Navy assess these uncertainties and determine whether it can produce the needed mine countermeasures capabilities from the assets it is likely to have and the concepts of operation it can likely execute.26 Options for Congress A primary issue for Congress in 2008 is whether to approve, reject, or modify the Navy’s restructured LCS program as presented in the proposed FY2009 budget. Potential options for Congress include but are not limited to the following: ! 26 FY2009 budget request. Congress could approve, reject, or modify the Navy’s FY2009 budget request for the LCS program in areas Government Accountability Office, Defense Acquisitions[:] Overcoming Challenges Key to Capitalizing on Mine Countermeasures Capabilities, GAO-08-13, October 2007, summary page. CRS-22 such as research and development funding, sea frame procurement, or mission package procurement. ! Operational evaluation and production competition. Congress could establish terms and conditions for the LCS operational evaluation and the subsequent production competition. ! Reporting requirements. Congress could impose new reporting requirements for the program so as to facilitate congressional oversight on issues such as cost growth. Some observers, including some Members of Congress, have expressed interest in the idea of using common hulls for Navy and Coast Guard ships, so as to improve economies of scale in the construction of these ships and thereby reduce their procurement costs. In earlier years, this interest focused on using a common hull for the LCS and the Offshore Patrol Cutter (OPC), a cutter displacing roughly 3,000 tons that is to be procured under the Coast Guard’s Deepwater acquisition program.27 More recently, this interest has focused on using a common hull for the LCS and the National Security Cutter (NSC), a cutter displacing about 4,300 tons that is also being acquired under the Deepwater program. In January 2008, it was reported that Northrop Grumman, the builder of the NSC, had submitted an unsolicited proposal to the Navy to build a version of the NSC for the Navy as a complement to, rather than a replacement for, the LCS. One press report stated: Northrop Grumman Corp said on Wednesday [January 16, 2008, that] a proposal to turn its 418-foot Coast Guard cutter into a new class of Navy frigates is sparking some interest among U.S. Navy officials and lawmakers. Northrop is offering the Navy a fixed price for the new ship of under $400 million and could deliver the first one as early as 2012 to help out with maritime security, humanitarian aid and disaster response, among other things, said Eric Womble, vice president of Northrop Grumman Ship Systems. So far, the officials briefed have found Northrop’s offer “intriguing,” Womble told Reuters in an interview. “They like the fact that we’re putting an option on the table. No one has told us, ‘Go away, don’t come back, we don’t want to hear this’,” Womble said. At the same time, the Navy says it remains committed to another class of smaller, more agile ships — the Littoral Combat Ships (LCS) being built by Lockheed Martin Corp (LMT.N: Quote, Profile, Research) and General Dynamics Corp (GD.N: Quote, Profile, Research) — amid huge cost overruns. “There currently is no requirement for a frigate,” Navy spokesman Lt. Clay Doss said. He said the Navy and Coast Guard had discussed a common hull 27 For more on the Deepwater program, see CRS Report RL33753, Coast Guard Deepwater Program: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke. CRS-23 during the initial stage of the LCS competition, but agreed that was “not a likely course of action due to the unique mission capabilities.” For now, he said the Navy was proceeding as quickly as it could with the 55-ship LCS program as well as design work on a new DDG-1000 destroyer, and a planned cruiser, CG-X.... The report also stated: Virginia-based defense consultant Jim McAleese said the fixed-price offer could be good news for the Navy, which has typically borne the risk of cost-based shipbuilding contracts. “That is a potential catalyst that could have a huge impact on the way the Navy buys small- and mid-sized surface combatants,” McAleese said. Northrop says its new Coast Guard cutter also experienced some cost growth, but says that was mainly due to requirements added after the Sept. 11, 2001, hijacking attacks. The first of the new ships is due to be delivered to the Coast Guard in March, followed by one ship annually over the next few years. Northrop said it could offer the Navy a fixed price on the frigate because design work on the ships is already largely completed. Its price excludes government-furnished equipment that would still have to be put on board. “We’re not advocating an LCS replacement,” said spokesman Randy Belote. “But after listening to the Navy leadership and studying the new maritime strategy, we think we can get hulls and capabilities into the water at a much faster pace.” Womble said Northrop analysts and an outside consultant studied the Navy’s needs and concluded the Navy could use another ship that can operate in shallow water, be forward deployed, has the range and endurance to operate independently, and can work with U.S. allies, if needed. The press report also stated: The proposed ship can be deployed for 60 days without new supplies, has a range of 12,000 nautical miles, and can travel at 29 knots, fast enough to keep up with other warships. That compares to 20 days and a range of 3,500 miles for LCS. Northrop began sharing a PowerPoint presentation about the proposal with Navy officials and lawmakers at the end of December, and has already met with several senior officials, including Chief of Naval Operations Adm. Gary Roughead. It could deliver the first frigate by 2012, if the Navy was able to add $75 million for long lead procurement items into the fiscal 2009 budget proposal to be sent to Congress next month, Northrop said. The frigate is about 75 percent compliant with special requirements that apply only to U.S. Navy ships. Northrop said it believed it could qualify for CRS-24 waivers on the remaining 25 percent because similar waivers were granted in the past.28 Another press report stated: The U.S. Navy is stumbling to build the ship it wants — the Littoral Combat Ship (LCS) — so shipbuilder Northrop Grumman is urging the service to turn to a ship it can get sooner and cheaper: a patrol frigate version of the Coast Guard’s National Security Cutter (NSC). “We have listened to what the Navy has said — to be more efficient, be innovative and produce affordable and capable ships,” said Phil Teel, president of Northrop’s Ship Systems sector. “The patrol frigate is a response to that, and to the Navy’s new National Maritime Strategy.” Northrop’s analysts have studied remarks and themes oft repeated by senior Navy leaders and concluded a de facto requirement exists for a frigate-size ship capable of handling a range of low- and mid-intensity missions. Those missions, said Eric Womble, head of Ship Systems’ Advanced Capabilities Group, are detailed in the Navy’s new Maritime Strategy and include forward presence, deterrence, sea control, maritime security, humanitarian assistance and disaster response. “You don’t want a high-end Aegis ship to handle those missions,” Womble said, “you want something cheaper and smaller.” The National Security Cutter (NSC) as configured for the Coast Guard could easily handle those roles, Womble said. The first NSC, the Bertholf, successfully carried out its initial trials in early December and will be commissioned this year by the Coast Guard. Womble said a Navy version would avoid the first-of-class issues that have plagued numerous Navy programs, including both designs being built for the LCS competition. Northrop in late December began briefing select Navy leaders on its unsolicited proposal. The company is taking pains to avoid presenting the ship as an LCS alternative, instead calling it an LCS “complement,” which is being built under a competition between Lockheed Martin and General Dynamics. Key features of Northrop’s concept are: — The ship is based on a proven design already under construction. — The NSC’s weapons, sensors and systems already have a high degree of commonality with Navy systems, increasing affordability. — While the NSC is 15 knots slower than the 45-knot LCS, the cutter can stay at sea up to two months, much longer than the LCS. 28 Andrea Shalal-Esa, “Northrop Offers US Navy New Ship For Fixed Price,” Reuters, January 17, 2008. CRS-25 The report also stated: Northrop is claiming it can deliver the first ship at the end of 2012 at an average cost of less than $400 million per ship, exclusive of government-furnished equipment, in fiscal 2007 dollars. That’s close to the $403 million contract cost of the third NSC, which incorporates all current design upgrades. A major element of Northrop’s proposal, Womble said, is that the Navy should make no changes to the current Block 0 design. “That’s the only way we can deliver the ship at this price.” The design, however, has plenty of room for upgrades, Womble claimed, and Northrop is proposing future upgrades be handled in groups, or blocks, of ships, rather than modifying individual ones. Those upgrades could include non-line-of-sight missiles, SeaRAM missile launchers and more capabilities to handle unmanned systems. The design even has room for an LCS-like reconfigurable mission area under the flight deck, he claimed. Northrop admits the ships are deficient in one significant Navy requirement: full compatibility with the Naval Vessel Rules (NVR), essentially building codes developed by the Naval Sea Systems Command and the American Bureau of Shipping. The belated application of the NVR to both LCS designs was a major factor in the cost growth on those ships. Most of the NSC design already is NVR-compatible, Womble said, but upgrading the entire design to NVR standards would involve a fundamental redesign and eliminate the proposal’s cost and construction time attributes. “We’d need a waiver [from the NVR rules] to make this proposal work,” he said. Navy Response: ‘No Requirement’ The official response from the Navy to Northrop’s proposal so far is unenthusiastic. “There is currently no requirement for such a combatant,” said Lt. Clay Doss, a Navy spokesman at the Pentagon. The Navy’s other surface ship programs, he said, “address specific requirements.” Doss did note that “the Navy and Coast Guard have considered a common platform for the LCS and the Coast Guard’s National Security Cutter. However, due to the unique mission requirements of each service, a common hull is not a likely course of action.” The report also stated: Problems with the LCS have caused some observers to predict the program’s demise, but the Navy “is completely committed to the LCS program,” Doss said. “We need 55 Littoral Combat Ships sooner rather than later, and we need them now to fulfill critical, urgent war-fighting gaps.” CRS-26 Northrop however, is not alone in proposing the NSC as an LCS alternative. Coast Guard Capt. James Howe, writing in the current issue of the U.S. Naval Institute’s Proceedings magazine, is urging Navy leaders to consider the NSC. “I think the Navy should look at it,” he said Jan. 10. “Northrop is building a naval combatant here. It has standard U.S. Navy weapon systems as part of its packages. Its communications are interoperable. It can handle underway replenishment. If there’s a possibility it could be a cost saver or a good deal for the Navy, it needs to be explored.” Howe, who said he was unaware of Northrop’s patrol frigate proposal, agreed the NSC is capable of further enhancements. “There’s a lot of space on that ship,” he said. ‘Potential Game-changer’ Northrop likely is facing an uphill battle with its patrol frigate, as the Navy culturally prefers to dictate requirements based on its own analysis. But the Navy is having trouble defending the affordability of its shipbuilding plan to Congress and bringing programs in on budget. One congressional source noted the service “can’t admit their plan won’t work.” An unsolicited proposal, the source said, “opens the way for someone else to come up with a potential game-changer.” Northrop’s plan, the source said, may be an unexpected opportunity. “Northrop is listening to the people who have been criticizing the Navy’s shipbuilding plan,” the source said. “They’ve gotten a sense that maybe the Navy is looking for a solution, and the Navy can’t produce a solution because it might be too embarrassing.” One more aspect that could be at work in the Northrop proposal: “I think there’s something coy going on here,” the source said. “They may be promoting this as an LCS complement, but their idea might be part of a strategic plan to replace the LCS.”29 FY2009 Legislative Activity The Navy’s proposed FY2009 budget was submitted to Congress in early February 2008. crsphpgw 29 Christopher P. Cavas, “Northrop Offers NSC-Based Vessel To Fill LCS Delays,” Defense News, January 14, 2008.