

 
Navy Ford (CVN-78) Class Aircraft Carrier 
Program: Background and Issues for Congress 
Updated July 12, 2024 
Congressional Research Service 
https://crsreports.congress.gov 
RS20643 
 
  
 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Summary 
The aircraft carriers CVN-78, CVN-79, CVN-80, CVN-81, and CVN-82 are the first five ships in 
the Navy’s new Gerald R. Ford (CVN-78) class of nuclear-powered aircraft carriers (CVNs). The 
Navy’s proposed FY2025 budget requests $2,143.9 million (i.e., about $2.1 billion) in 
procurement funding for Ford-class ships, including $236.0 million for CVN-79, $1,186.9 million 
for CVN-80, and $721.0 million for CVN-81. The Navy’s FY2025 budget submission proposes 
deferring the procurement of the fifth ship in the class, CVN-82, by two years, from FY2028 to 
FY2030, with advance procurement (AP) for the ship beginning in FY2027. 
CVN-78 (Gerald R. Ford) was procured in FY2008. The ship was commissioned into service on 
July 22, 2017, and achieved initial operational capability in December 2021. The ship’s first 
deployment began in October 2022, more than five years after the ship was commissioned into 
service. 
CVN-79 (John F. Kennedy) was procured in FY2013. The Navy’s FY2025 budget submission 
states that the ship is scheduled for delivery in July 2025. 
CVN-80 (Enterprise) was procured in FY2018. On April 2, 2024, the Navy announced delays in 
the scheduled deliveries of several of its shipbuilding programs, including CVN-80, whose 
delivery, the Navy stated, will be delayed approximately 18 to 26 months. The Navy’s FY2025 
budget submission, which was submitted to Congress in March 2024, shows the ship’s scheduled 
delivery date as September 2029, or 18 months later than the March 2028 date shown in the 
Navy’s FY2024 budget submission, which was submitted to Congress in March 2023. 
CVN-81 (Doris Miller) is treated in this report as a ship that was procured in FY2019, consistent 
with congressional action on the Navy’s FY2019 budget. (The Navy’s FY2025 budget 
submission, like its FY2021-FY2024 submissions, shows CVN-81 as a ship that was procured in 
FY2020.) The ship is scheduled for delivery to the Navy in February 2032. 
CVN-82, as noted above, is programmed for procurement in FY2030 under the Navy’s FY2025 
budget submission. Procuring CVN-82 two years earlier, in FY2028, could involve providing 
roughly $550 million in AP funding for the ship in FY2025.  
CVN-80 and CVN-81 were procured under a two-ship block buy contract that was authorized by 
Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/P.L. 115-232 of August 13, 2018). The use of the two-ship block buy contract reduced 
the combined estimated procurement cost of the two ships. 
Oversight issues for Congress for the CVN-78 program include the following: 
•  whether to procure CVN-82 in FY2030 (as proposed in the Navy’s FY2025 
budget submission), in FY2028 (as scheduled in prior-year Navy budget 
submissions), or in FY2029; 
•  whether to procure CVN-82 and a subsequent aircraft carrier (which would be 
CVN-83) as a two-ship buy that would similar to the two-ship buy that was used 
for procuring CVN-80 and CVN-81; 
•  the future aircraft carrier force level; 
•  CVN-78 program issues that were raised in a January 2024 report from the 
Department of Defense’s (DOD’s) Director of Operational Test and Evaluation 
(DOT&E) and a June 2023 Government Accountability Office (GAO) report on 
DOD weapon systems; and 
•  the procurement of aircraft carriers after CVN-81 or CVN-82.
Congressional Research Service 
 link to page 5  link to page 5  link to page 5  link to page 5  link to page 5  link to page 5  link to page 6  link to page 7  link to page 7  link to page 7  link to page 8  link to page 8  link to page 8  link to page 8  link to page 9  link to page 10  link to page 11  link to page 11  link to page 11  link to page 12  link to page 12  link to page 12  link to page 13  link to page 13  link to page 13  link to page 13  link to page 16  link to page 16  link to page 17  link to page 17  link to page 23  link to page 24  link to page 25  link to page 25  link to page 26  link to page 26  link to page 27  link to page 27  link to page 9  link to page 10 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Contents 
Introduction ..................................................................................................................................... 1 
Background ..................................................................................................................................... 1 
Current Navy Aircraft Carrier Force ......................................................................................... 1 
Statutory Requirements for Carriers and Carrier Air Wings ..................................................... 1 
Requirement to Maintain Not Less Than 11 Carriers ......................................................... 1 
Prohibition on Retiring Nuclear-Powered Aircraft Carriers Prior to Refueling .................. 1 
Requirement to Maintain a Minimum of Carrier Air Wings ............................................... 2 
Navy’s Aircraft Carrier Force-Level Goal ................................................................................ 3 
Projected Number of Aircraft Carriers ...................................................................................... 3 
Incremental Funding Authority for Aircraft Carriers ................................................................ 3 
Aircraft Carrier Construction Industrial Base ........................................................................... 4 
Gerald R. Ford (CVN-78) Class Program ................................................................................. 4 
Overview ............................................................................................................................. 4 
CVN-78 (Gerald R. Ford) .................................................................................................. 4 
CVN-79 (John F. Kennedy) ................................................................................................ 5 
CVN-80 (Enterprise) .......................................................................................................... 6 
CVN-81 (Doris Miller) ....................................................................................................... 7 
CVN-82 ............................................................................................................................... 7 
Two-Ship Block Buy Contract for CVN-80 and CVN-81 .................................................. 7 
Interest in Potential Two-Ship Block Buy Contract for CVN-82 and CVN-83 and 
“2-3-4” Approach for Procuring Aircraft Carriers ........................................................... 8 
Program Procurement Cost Cap .......................................................................................... 8 
Program Procurement Funding ........................................................................................... 9 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget .............................. 9 
Issues for Congress .......................................................................................................................... 9 
Procurement Date for CVN-82 ................................................................................................. 9 
Procuring CVN-82 and CVN-83 as a Two-Ship Buy ............................................................. 12 
Future Aircraft Carrier Force Level ........................................................................................ 12 
Issues Raised in DOT&E and GAO Reports .......................................................................... 13 
January 2024 DOT&E Report .......................................................................................... 13 
June 2024 GAO Report ..................................................................................................... 19 
Procurement of Aircraft Carriers After CVN-81 or CVN-82 .................................................. 20 
Legislative Activity for FY2025 .................................................................................................... 21 
Summary of Congressional Action on FY2025 Funding Request .......................................... 21 
FY2025 National Defense Authorization Act (H.R. 8070) ..................................................... 22 
House ................................................................................................................................ 22 
FY2025 DOD Appropriations Act (H.R. 8774) ...................................................................... 23 
House ................................................................................................................................ 23 
 
Figures 
Figure 1. USS Gerald R. Ford (CVN-78) ....................................................................................... 5 
Figure 2. USS Gerald R. Ford (CVN-78) ....................................................................................... 6 
  
Congressional Research Service 
 link to page 14  link to page 15  link to page 25  link to page 28  link to page 31 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Tables 
Table 1. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2028 ........................... 10 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 ........................... 11 
Table 3. Congressional Action on FY2024 Procurement Funding Request .................................. 21 
  
Appendixes 
Appendix. Background Information on Two-Ship Block Buy for CVN-80 and CVN-81 ............ 24 
 
Contacts 
Author Information ........................................................................................................................ 27 
 
Congressional Research Service 
 link to page 5 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Introduction 
This report provides background information and potential oversight issues for Congress on the 
Gerald R. Ford (CVN-78) class nuclear-powered aircraft carrier (CVN) aircraft carrier program. 
The Navy’s proposed FY2024 budget requests $2,143.9 million (i.e., about $2.1 billion) in 
procurement funding for the program. Congress’s decisions on the CVN-78 program could 
substantially affect Navy capabilities and funding requirements and the shipbuilding industrial 
base. 
Background 
Current Navy Aircraft Carrier Force 
The Navy’s current aircraft carrier force consists of 11 CVNs,1 including 10 Nimitz-class ships 
(CVNs 68 through 77) that entered service between 1975 and 2009, and one Gerald R. Ford 
(CVN-78) class ship that was commissioned into service on July 22, 2017.2  
Statutory Requirements for Carriers and Carrier Air Wings 
Requirement to Maintain Not Less Than 11 Carriers 
10 U.S.C. 8062(b) requires the Navy to maintain a force of not less than 11 operational aircraft 
carriers.3 The requirement for the Navy to maintain not less than a certain number of operational 
aircraft carriers was established by Section 126 of the FY2006 National Defense Authorization 
Act (H.R. 1815/P.L. 109-163 of January 6, 2006), which set the number at 12 carriers. The 
requirement was changed from 12 carriers to 11 carriers by Section 1011(a) of the FY2007 John 
Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006).4 
Prohibition on Retiring Nuclear-Powered Aircraft Carriers Prior to Refueling 
Section 1054 of the FY2021 National Defense Authorization Act (NDAA) (H.R. 6395/P.L. 116-
283) amended 10 U.S.C. 8062 to create a new subsection (which is now subsection [g]) stating: 
“A nuclear powered aircraft carrier may not be retired before its first refueling.’’ 
 
1 The Navy’s last remaining conventionally powered carrier (CV), Kitty Hawk (CV-63), was decommissioned on 
January 31, 2009. 
2 The commissioning into service of CVN-78 on July 22, 2017, ended a period during which the carrier force had 
declined to 10 ships—a period that began on December 1, 2012, with the inactivation of the one-of-a-kind nuclear-
powered aircraft carrier Enterprise (CVN-65), a ship that entered service in 1961. 
3 10 U.S.C. 8062 was previously numbered as 10 U.S.C. 5062. It was renumbered as 10 U.S.C. 8062 by Section 807 of 
the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-232 of August 13, 
2018), which directed a renumbering of sections and titles of Title 10 relating to the Navy and Marine Corps. (Sections 
806 and 808 of P.L. 115-232 directed a similar renumbering of sections and titles relating to the Air Force and Army, 
respectively.) 
4 As mentioned in footnote 2, the carrier force dropped from 11 ships to 10 ships between December 1, 2012, when 
Enterprise (CVN-65) was inactivated, and July 22, 2017, when CVN-78 was commissioned into service. Anticipating 
the gap between the inactivation of CVN-65 and the commissioning of CVN-78, the Navy asked Congress for a 
temporary waiver of 10 U.S.C. 8062(b) to accommodate the period between the two events. Section 1023 of the 
FY2010 National Defense Authorization Act (H.R. 2647/P.L. 111-84 of October 28, 2009) authorized the waiver, 
permitting the Navy to have 10 operational carriers between the inactivation of CVN-65 and the commissioning of 
CVN-78. 
Congressional Research Service  
 
1 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Requirement to Maintain a Minimum of Carrier Air Wings 
10 U.S.C. 8062(e), which was added by Section 1042 of the FY2017 National Defense 
Authorization Act (S. 2943/P.L. 114-328 of December 23, 2016), requires the Navy to maintain a 
certain minimum number of carrier air wings.5 
 
5 10 U.S.C. 8062(e) states: 
(e) The Secretary of the Navy shall ensure that- 
(1) the Navy maintains a minimum of 9 carrier air wings until the earlier of- 
(A) the date on which additional operationally deployable aircraft carriers can fully support a 10th 
carrier air wing; or 
(B) October 1, 2025; 
(2) after the earlier of the two dates referred to in subparagraphs (A) and (B) of paragraph (1), the 
Navy maintains a minimum of 10 carrier air wings; and 
(3) for each such carrier air wing, the Navy maintains a dedicated and fully staffed headquarters. 
Section 121 of the FY2024 National Defense Authorization Act (H.R. 2670/P.L. 118-31 of December 22, 2023) states: 
SEC. 121. MODIFICATION OF REQUIREMENTS FOR MINIMUM NUMBER OF CARRIER 
AIR WINGS OF THE NAVY. 
(a) Modification of Requirements.-- 
(1) In general.--Subsection (e) of section 8062 of title 10, United States Code, is amended to read as 
follows-- 
``(e) The Secretary of the Navy shall ensure that-- 
``(1) the Navy maintains a minimum of 9 carrier air wings; and 
``(2) for each such carrier air wing, the Navy maintains a dedicated and fully staffed headquarters.' . 
(2) Effective date.-- 
The amendment made by paragraph (1) shall take effect one year after the date on which the 
Secretary of the Navy submits to Congress the report required under subsection (b)(3).  
The Secretary of the Navy shall notify the Law Revision Counsel of the House of Representatives 
of the submission of the report so that the Law Revision Counsel may execute the amendment 
made by paragraph (1) in accordance with the preceding sentence. 
(b) Analysis and Report.-- 
(1) In general.--The Secretary of the Navy shall conduct an analysis of potential approaches to the 
manning, operation, and deployment of a 10th aircraft carrier and associated carrier air wing to 
determine how the Navy can mobilize such a carrier and air wing if required by operational needs. 
(2) Elements.--The analysis under paragraph (1) shall address the following: 
(A) The timeline associated with removing an aircraft carrier from each the following maintenance 
availability types: 
(i) Complex Overhaul. 
(ii) Selected Restricted Availability. 
(iii) Docking Selected Restricted Availability. 
(iv) Planned Incremental Availability. 
(v) Docking Planned Incremental Availability. 
(B) The potential for establishing a reserve component air wing capable of mobilization as a 10th 
carrier air wing. 
(C) The timeline for activation of such a reserve component carrier air wing. 
(D) The costs associated with establishing and maintaining a 10th active carrier air wing versus 
establishing and maintaining a reserve component air wing as described in subparagraph (B). 
(E) The potential for deployment of a 10th aircraft carrier without a fully manned carrier air wing 
in the event the Navy only operates and crews 9 carrier air wings at the time deployment of a 10th 
aircraft carrier is required. 
(continued...) 
Congressional Research Service  
 
2 
 link to page 14 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Navy’s Aircraft Carrier Force-Level Goal 
The Navy wants to achieve and maintain in coming years a fleet of 381 manned battle force ships, 
including 12 aircraft carriers. The Biden Administration has not explicitly endorsed the Navy’s 
desired 381-ship force-level objective or any other ship force-level objective for the Navy as a 
whole.6 
Projected Number of Aircraft Carriers 
The Navy’s FY2025 30-year (FY2025-FY2054) shipbuilding plan, which is designed to support 
the eventual attainment of a fleet of about 381 ships, projects that, if the plan were implemented, 
the Navy’s carrier force would include a total of 12 carriers in only three years within the 30-year 
period, with the force including 
•  11 carriers in FY2025-FY2036 (except for FY2025, FY2029, and FY2032, when 
it would include 12 carriers), 
•  10 or 11 carriers in FY2037-FY2046, and 
•  9 carriers in FY2047-FY2054 (except for FY2052, when it would include 10 
carriers). 
Incremental Funding Authority for Aircraft Carriers 
Congress since the 1990s has authorized DOD to use incremental funding for procuring certain 
Navy ships, most notably aircraft carriers.7 Under incremental funding, some of the funding 
needed to fully fund a ship is provided in one or more years after the year in which the ship is 
procured.8 
 
(F) The potential for additional forward deployed squadrons that could support an aircraft carrier 
during theater operations that may not have a fully embarked air wing at the time of embarkation. 
(3) Report.--Following completion of the analysis required under paragraph (1), Secretary of the 
Navy shall submit to the congressional defense committees a report on the results of the analysis. 
6 For additional discussion, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and 
Issues for Congress, by Ronald O'Rourke. 
7 The provisions providing authority for using incremental funding for procuring Ford-class carriers are as follows: 
Section 121 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 
2006) granted the Navy the authority to use four-year incremental funding for CVNs 78, 79, and 80. Under this 
authority, the Navy could fully fund each of these ships over a four-year period that includes the ship’s year of 
procurement and three subsequent years. 
Section 124 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 112-81 of December 31, 2011) 
amended Section 121 of P.L. 109-364 to grant the Navy the authority to use five-year incremental funding for CVNs 
78, 79, and 80. Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice originally applied to 
CVNs 79 and 80, although as discussed in the footnote to Table 1, the Navy made use of the authority in connection 
with an FY2020 reprogramming action that reprogrammed $86.0 million of funding into FY2012 for CVN-78. 
Section 121 of the FY2013 National Defense Authorization Act (H.R. 4310/P.L. 112-239 of January 2, 2013) amended 
Section 121 of P.L. 109-364 to grant the Navy the authority to use six-year incremental funding for CVNs 78, 79, and 
80. Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice applies to CVNs 79 and 80. 
Section 121(c) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-
232 of August 13, 2018) authorized incremental funding to be used for making payments under the two-ship block buy 
contract for the construction of CVN-80 and CVN-81. This provision does not limit the total number of years across 
which incremental funding may be used to procure either ship. 
8 For more on full funding and incremental funding, see CRS Report RL31404, Defense Procurement: Full Funding 
(continued...) 
Congressional Research Service  
 
3 
 link to page 9  link to page 10 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Aircraft Carrier Construction Industrial Base 
All U.S. aircraft carriers procured since FY1958 have been built by Huntington Ingalls 
Industries/Newport News Shipbuilding (HII/NNS), of Newport News, VA. HII/NNS is the only 
U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The aircraft carrier 
construction industrial base as of 2019 also included roughly 2,000 supplier firms in 46 states.9 
Gerald R. Ford (CVN-78) Class Program 
Overview 
The Gerald R. Ford (CVN-78) class carrier design (Figure 1 and Figure 2) is the successor to the 
Nimitz-class carrier design. The Ford-class design uses the basic Nimitz-class hull form but 
incorporates several improvements, including features permitting the ship to generate more 
aircraft sorties per day, more electrical power for supporting ship systems, and features permitting 
the ship to be operated by several hundred fewer sailors than a Nimitz-class ship, reducing 50-
year life-cycle operating and support (O&S) costs for each ship by about $4 billion compared to 
the Nimitz-class design, the Navy estimates. Navy plans call for procuring at least five Ford-class 
carriers—CVN-78, CVN-79, CVN-80, CVN-81, and CVN-82. 
CVN-78 (Gerald R. Ford) 
CVN-78, which was named Gerald R. Ford in 2007,10 was procured in FY2008. The ship’s final 
procurement cost was $13,316.5 million (i.e., about $13.3 billion) in then-year dollars. The ship 
was commissioned into service on July 22, 2017, and achieved initial operational capability 
(IOC) in December 2021.11 The ship’s first deployment, which was delayed by a need to complete 
work on the ship’s weapons elevators and correct other technical problems aboard the ship, began 
in October 2022, more than five years after the ship was commissioned into service.12 The ship 
reportedly began its first full-length deployment on May 2, 2023.13 
 
Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report 
RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by 
Ronald O'Rourke. 
9 Source: Jennifer Boykin, president of HII/NNS, as quoted in Marcus Weisgerber, “US Navy Places First 2-Carrier 
Order in Three Decades,” Defense One, January 31, 2019. 
10 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of 
Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced that 
CVN-78 would be so named. CVN-78 and other carriers built to the same design are consequently referred to as Ford 
(CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for 
Congress, by Ronald O'Rourke. 
11 See, for example, Marcus Weisgerber, “Surprise! The Navy Declared Its Newest Carrier Battle-Ready Last Year,” 
Defense One, April 5, 2022. 
12 See, for example, Nick Wilson, “First-in-Class Ford Aircraft Carrier Completes Inaugural Deployment,” Inside 
Defense, November 29, 2022; Sam LaGrone, “Video: USS Gerald R. Ford Back in Norfolk After Two Months in the 
Atlantic,” USNI News, November 26 (updated November 27), 2022; Diana Stancy Correll, “USS Gerald R Ford Slated 
to Wrap Up First Deployment,” Navy Times, November 23, 2022. 
13 See, for example, Diana Stancy Correll, “USS Gerald R Ford Leaves Norfolk for First Full-Length Deployment,” 
Navy Times, May 2, 2023; Aaron-Matthew Lariosa, “Aircraft Carrier USS Gerald R. Ford Departs Norfolk for 
Worldwide Deployment,” USNI News, May 2, 2023. 
Congressional Research Service  
 
4 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Figure 1. USS Gerald R. Ford (CVN-78) 
 
Source: Cropped version of U.S. Navy photograph 240105-N-HJ055-1591, showing CVN-78 transiting the 
Strait of Gibraltar on January 5, 2024. Accessed April 15, 2024, at https://www.navy.mil/Resources/Photo-
Gallery/igphoto/2003370046/.  
CVN-79 (John F. Kennedy) 
CVN-79, which was named John F. Kennedy on May 29, 2011,14 was procured in FY2013. The 
Navy’s proposed FY2025 budget estimates the ship’s procurement cost at $12,936.0 million (i.e., 
$12.9 billion) in then-year dollars. On August 10, 2023, the Navy notified the congressional 
defense committees that, using authority granted by Section 121 of the FY2020 National Defense 
Authorization Act (S. 1790/P.L. 116-92 of December 20, 2019), the Navy was increasing the cost 
limitation baseline (aka cost cap) for CVN-79 by $236 million, to $12,936 million, to support full 
ship delivery efforts. (For further information on procurement cost caps for the CVN-78 program, 
see “Program Procurement Cost Cap” below.) CVN-79 is being built with an improved shipyard 
fabrication and assembly process that incorporates lessons learned from the construction of CVN-
78. The Navy’s FY2025 budget submission states that the ship is scheduled for delivery in July 
2025. 
 
14 See “Navy Names Next Aircraft Carrier USS John F. Kennedy,” Navy News Service, May 29, 2011, accessed online 
on June 1, 2011, at http://www.navy.mil/search/display.asp?story_id=60686. See also Peter Frost, “U.S. Navy’s Next 
Aircraft Carrier Will Be Named After The Late John F. Kennedy,” Newport News Daily Press, May 30, 2011. CVN-79 
is the second ship to be named for President John F. Kennedy. The first, CV-67, was the last conventionally powered 
carrier procured for the Navy. CV-67 was procured in FY1963, entered service in 1968, and was decommissioned in 
2007. 
Congressional Research Service  
 
5 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Figure 2. USS Gerald R. Ford (CVN-78) 
 
Source: Cropped version of photograph accompanying Megan Eckstein, “Navy Removes Ford Carrier Program 
Manager, Citing Performance Over Time,” USNI News, July 2, 2020. The caption credits the photograph to the 
U.S. Navy and states that it shows CVN-78 on June 4, 2020. 
CVN-80 (Enterprise) 
CVN-80, which was named Enterprise on December 1, 2012,15 was procured in FY2018. The 
Navy’s proposed FY2025 budget estimates the ship’s procurement cost at $13,719.9 million (i.e., 
about $13.7 billion) in then-year dollars. On April 2, 2024, the Navy announced delays in the 
scheduled deliveries of several of its shipbuilding programs due to shipyard workforce and supply 
chain challenges and other issues, including CVN-80, whose delivery, the Navy stated, will be 
delayed approximately 18 to 26 months.16 The Navy’s FY2025 budget submission, which was 
 
15 The Navy made the announcement of CVN-80’s name on the same day that it deactivated the 51-year-old aircraft 
carrier CVN-65, also named Enterprise. (“Enterprise, Navy’s First Nuclear-Powered Aircraft Carrier, Inactivated,” 
Navy News Service, December 1, 2012; Hugh Lessig, “Navy Retires One Enterprise, Will Welcome Another,” Newport 
News Daily Press, December 2, 2012.) CVN-65 was the eighth Navy ship named Enterprise; CVN-80 is to be the 
ninth. 
16 See, for example, Megan Eckstein, “US Navy Ship Programs Face Years-Long Delays amid Labor, Supply Woes,” 
(continued...) 
Congressional Research Service  
 
6 
 link to page 14  link to page 28 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
submitted to Congress in March 2024, shows the ship’s scheduled delivery date as September 
2029, or 18 months later than the March 2028 date shown in the Navy’s FY2024 budget 
submission, which was submitted to Congress in March 2023. 
CVN-81 (Doris Miller) 
CVN-81, which was named Doris Miller on January 20, 2020,17 is treated in this report as a ship 
that was procured in FY2019, consistent with congressional action on the Navy’s FY2019 budget. 
(The Navy’s FY2025 budget submission, like its FY2021-FY2024 submissions, shows CVN-81 
as a ship that was procured in FY2020.) The Navy’s FY2025 budget submission estimates the 
ship’s procurement cost at $14,015.6 million (i.e., about $14.0 billion) in then-year dollars. The 
ship is scheduled for delivery to the Navy in February 2032. 
CVN-82 
Prior to the Navy’s FY2025 budget submission, Navy budget submissions showed CVN-82 as 
programmed for procurement in FY2028. The Navy’s FY2025 budget submission proposes 
deferring the procurement of the ship by two years, from FY2028 to FY2030, with advance 
procurement (AP) for the ship beginning in FY2027. Procuring CVN-82 in FY2028, as 
previously scheduled, could involve providing roughly $550 million in AP funding for the ship in 
FY2025.18 
Two-Ship Block Buy Contract for CVN-80 and CVN-81 
CVN-80 and CVN-81 were procured under a two-ship block buy contract that was authorized by 
Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/P.L. 115-232 of August 13, 2018). The provision permitted the Navy to add CVN-81 
to the existing contract for building CVN-80 after DOD made certain certifications to Congress. 
DOD made the certifications on December 31, 2018, and the Navy announced the award of the 
contract on January 31, 2019. Prior to the awarding of the two-ship block buy contract, CVN-81 
was scheduled to be procured in FY2023. The use of the two-ship block buy contract reduced the 
combined estimated procurement cost of the two ships.19 
 
Defense News, April 2, 2024; Justin Katz, “Navy Lays Out Major Shipbuilding Delays, in Rare Public Accounting,” 
Breaking Defense, April 2, 2024; Nick Wilson, “Navy Shipbuilding Review Details Delays across Submarine and Ship 
Acquisition Portfolio,” Inside Defense, April 2, 2024; Cal Biesecker, “Navy Confirms Delays In Shipbuilding 
Programs As Part Of Ongoing Review,” Defense Daily, April 3, 2024. 
17 Doris Miller was an African American enlisted sailor who received the Navy Cross for his actions during the 
Japanese attack on Pearl Harbor on December 7, 1941. For further discussion of the naming of CVN-81 for Doris 
Miller, see CRS Report RS22478, Navy Ship Names: Background for Congress, by Ronald O'Rourke. 
18 Source: CRS estimate. As shown in Table 1, the Navy has programmed $580.7 million in AP funding for CVN-82 in 
FY2027 to support the procurement of the ship in FY2030. Accelerating this AP funding by two years, to FY2025, to 
support the procurement of CVN-82 in FY2028, and deflating the amount into FY2025 dollars produces an adjusted 
figure of roughly $550 million. 
19 Compared to the estimated procurement costs for CVN-80 and CVN-81 in the Navy’s FY2019 budget submission, 
the Navy estimated under its FY2020 budget submission that the two-ship block buy contract will reduce the cost of 
CVN-80 by $246.6 million and the cost of CVN-81 by $2,637.3 million, for a combined reduction of $2,883.9 million 
(i.e., about $2.9 billion). (DOD characterized the combined reduction as “nearly $3 billion.”) Using higher estimated 
baseline costs for CVN-80 and CVN-81 taken from a December 2017 Navy business case analysis, the Navy estimated 
under its FY2020 budget submission that the two-ship contract will reduce the cost of CVN-80 by about $900 million 
and the cost of CVN-81 by about $3.1 billion, for a combined reduction of about $4.0 billion. These figures are all 
expressed in then-year dollars, meaning dollars that are not adjusted for inflation. For additional background 
information on the two-ship block buy contract, see the Appendix. 
Congressional Research Service  
 
7 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Interest in Potential Two-Ship Block Buy Contract for CVN-82 and CVN-83 
and “2-3-4” Approach for Procuring Aircraft Carriers 
Some observers reportedly are interested in the option of using another two-ship block buy 
contract to procure CVN-82 and a sixth Ford-class carrier, which would be CVN-83.20 More 
broadly, some observers have argued in favor of a “2-3-4” approach for procuring carriers that 
would include two-carrier buys, three years (rather than two years) of advanced procurement 
funding for each carrier, and four-year centers for building carriers (i.e., starting construction of 
each carrier four years after the start of the previous carrier’s construction). In association with 
the 2-3-4 approach, these observers have argued that delaying the procurement of CVN-82 
beyond FY2028 could damage the CVN construction industrial base.21 
Section 132 of the FY2023 NDAA (H.R. 7776/P.L. 117-263 of December 23, 2022) required the 
Navy to submit a report to the congressional defense committees not later than March 1, 2023, on 
advance procurement funding for CVN-82 and CVN-83 under single-carrier and two-carrier 
acquisition strategies. 
Program Procurement Cost Cap 
Congress established and subsequently amended procurement cost caps for Ford-class aircraft 
carriers.22 
 
20 See, for example, Megan Eckstein, “US Navy Mulls Timing of New Double-Carrier Award Amid Enterprise Delay,” 
Defense News, October 26, 2023; Loren Thompson, “The Right Way To Buy The U.S. Navy’s New Generation Of 
Supercarriers,” Forbes, September 30, 2022; Mike Gooding, “Block-Buy for New Aircraft Carriers Will Save 
Taxpayers Billions of Dollars,” 13 News Now, August 30 (updated August 31), 2022; Megan Eckstein, “Navy, HII 
Pitch Congress for Another Two-Carrier Contract,” Defense News, August 29, 2022; Sam LaGrone, “HII Argues for 
Aircraft Carrier Block Buy as New Enterprise Takes Shape,” USNI News, August 28, 2022; Justin Katz, “Ahead of 
Shipyard Ceremony, Navy and Industry Advocate for Another Aircraft Carrier ‘Block Buy,’” Breaking Defense, 
August 26, 2022. 
21 Rich Abott, “HII Argues For Two Carrier Block Buys With Three Years Advance Work, Warns If CVN-82 
Delayed,” Defense Daily, January 8, 2024; Audrey Decker, “Delaying Aircraft Carrier Order Would Hurt Supply 
Chain, Shipbuilder Says,” Defense Daily, January 8, 2024; Megan Eckstein, “HII Warns of Potential Carrier, Amphib 
Issues in Fy25 Budget Request,” Defense News, January 8, 2024; Brett Davis, “Delay to CVN 82 Buy Could Endanger 
Industrial Base, New Industry Report Says,” Seapower, January 17, 2024. 
22 The provisions that established and later amended the cost caps are as follows: 
Section 122 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 
2006) established a procurement cost cap for CVN-78 of $10.5 billion, plus adjustments for inflation and other factors, 
and a procurement cost cap for subsequent Ford-class carriers of $8.1 billion each, plus adjustments for inflation and 
other factors. The conference report (H.Rept. 109-702 of September 29, 2006) on P.L. 109-364 discusses Section 122 
on pages 551-552. 
Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 113-66 of December 26, 2013) 
amended the procurement cost cap for the CVN-78 program to provide a revised cap of $12,887.0 million for CVN-78 
and a revised cap of $11,498.0 million for each follow-on ship in the program, plus adjustments for inflation and other 
factors (including an additional factor not included in original cost cap). 
Section 122 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015) further 
amended the cost cap for the CVN-78 program to provide a revised cap of $11,398.0 million for each follow-on ship in 
the program, plus adjustment for inflation and other factors, and with a new provision stating that, if during 
construction of CVN-79, the Chief of Naval Operations determines that measures required to complete the ship within 
the revised cost cap shall result in an unacceptable reduction to the ship’s operational capability, the Secretary of the 
Navy may increase the CVN-79 cost cap by up to $100 million (i.e., to $11.498 billion). If such an action is taken, the 
Navy is to adhere to the notification requirements specified in the cost cap legislation. 
Section 121(a) of the FY2018 National Defense Authorization Act (H.R. 2810/P.L. 115-91 of December 12, 2017) 
further amended the cost cap for the CVN-78 program to provide a revised cap of $12,568.0 million for CVN-80 and 
(continued...) 
Congressional Research Service  
 
8 
 link to page 14  link to page 15 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Program Procurement Funding 
Table 1 shows procurement funding for CVNs 78, 79, 80, and 81 through FY2028, the final year 
of funding programmed for CVN-81, under the Navy’s FY2024 budget submission. As shown in 
the table, the Navy’s proposed FY2024 budget requests $2,540.4 million (i.e., about $2.5 billion) 
in procurement funding for Ford-class ships, including $624.6 million for CVN-79, $1,115.3 
million for CVN-80, and $800.5 million for CVN-81. 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget 
Table 2 shows changes in the estimated procurement costs of CVNs 78, 79, 80, and 81 since the 
budget submission for FY2008—the year of procurement for CVN-78. 
Issues for Congress 
Procurement Date for CVN-82 
One issue for Congress is whether to procure CVN-82 in FY2030 (as proposed in the Navy’s 
FY2025 budget submission), in FY2028 (as scheduled in prior-year Navy budget submissions), or 
in FY2029. As noted earlier, procuring CVN-82 in FY2028 could involve providing roughly $550 
million in advance procurement (AP) funding for the ship in FY2025. 
The Navy argues that its proposal to defer procurement of CVN-82 by two years, from FY2028 to 
FY030, was made necessary by limits on the Navy’s budget topline and competing Navy program 
priorities, and that providing AP funding for CVN-82 starting in FY2025 could reduce funding 
available for those other program priorities.23 Supporters of procuring CVN-82 in FY2028, as 
previously scheduled, could argue that deferring the ship’s procurement will pose challenges for 
firms in the aircraft carrier supplier base due to the lengthened interval between the procurement 
of CVN-81 (procured in FY2019) and CVN-82,24 and increase the ship’s cost in real terms for 
both that reason and due to loss of production learning curve benefits at the shipbuilder, HII/NNS. 
 
 
subsequent ships in the program, plus adjustment for inflation and other factors. (The cap for CVN-79 was kept at 
$11,398.0 million, plus adjustment for inflation and other factors.) The provision also amended the basis for adjusting 
the caps for inflation, and excluded certain costs from being counted against the caps. 
Section 121 of the FY2020 National Defense Authorization Act (S. 1790/P.L. 116-92 of December 20, 2019) further 
amended the cost cap for the CVN-78 program to provide revised caps of $13,224.0 million for CVN-78, $11,398.0 
million for CVN–79, $12,202.0 million for CVN–80, and $12,451.0 million for CVN–81. The provision directs the 
Navy to exclude from these figures costs for CVN–78 class battle spares, interim spares, and increases attributable to 
economic inflation after December 1, 2018. 
23 Source: Navy briefing for CBO and CRS on the Navy’s proposed FY2025 budget, March 12, 2024. 
24 See, for example, Bryan McGrath, “The US Is Not Serious about Aircraft Carriers—or Their Industrial Base,” 
Defense One, March 12, 2024; Abby Shepherd, “Carrier Delays Concern Industry Members, Congress,” Inside 
Defense, March 20, 2024. 
Congressional Research Service  
 
9 
 link to page 7 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 1. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2028 
(Millions of then-year dollars, rounded to nearest tenth) 
FY 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
CVN-82 
Total 
FY01 
21.7 (AP) 
0 
0 
0 
0 
21.7 
FY02 
135.3 (AP) 
0 
0 
0 
0 
135.3 
FY03 
395.5 (AP) 
0 
0 
0 
0 
395.5 
FY04 
1,162.9 (AP) 
0 
0 
0 
0 
1,162.9 
FY05 
623.1 (AP) 
0 
0 
0 
0 
623.1 
FY06 
618.9 (AP) 
0 
0 
0 
0 
618.9 
FY07 
735.8 (AP) 
52.8 (AP) 
0 
0 
0 
788.6 
FY08 
2,685.0 (FF) 
123.5 (AP) 
0 
0 
0 
2,808.5 
FY09 
2,687.0 (FF) 
1,210.6 (AP) 
0 
0 
0 
3,897.6 
FY10 
851.3 (FF) 
482.9 (AP) 
0 
0 
0 
1,334.2 
FY11  
1,848.1 (FF) 
902.5 (AP) 
0 
0 
0 
2,750.6 
FY12  
86.0 (FF)** 
554.8 (AP) 
0 
0 
0 
640.8 
FY13 
0 
491.0 (FF) 
0 
0 
0 
491.0 
FY14  
588.1 (CC) 
917.6 (FF) 
0 
0 
0 
1,505.7 
FY15 
663.0 (CC) 
1,219.4 (FF) 
0 
0 
0 
1,882.4 
FY16 
123.8 (CC) 
1,569.5 (FF) 
862.4 (AP) 
0 
0 
2,555.7 
FY17  
0 
1,241.8 (FF) 
1,370.8 (AP) 
0 
0 
2,612.6 
FY18 
20.0 (CC) 
2,556.4 (FF) 
1,569.6 (FF) 
0 
0 
4,146.0 
FY19 
0 
0 
929.1 (FF) 
643.0 (FF) 
0 
1,572.1 
FY20 
0 
0 
1,062.0 (FF) 
1,214.5 (FF) 
0 
2,276.5 
FY21 
71.0 (CC) 
0 
958.9 (FF) 
1,606.4 (FF) 
0 
2,636.3 
FY22 
0 
291.0 (CC) 
1,062.0 (FF) 
1,287.7 (FF) 
0 
2,640.7 
FY23 
0 
461.7 (CC) 
1,465.9 (FF) 
1,052.0 (FF) 
0 
2,995.2 
FY24 
0 
624.6 (CC) 
1,104.4 (FF)* 
800.5 (FF) 
0 
2,529.5* 
FY25 (requested) 
0 
236.0 (CC) 
1,186.9 (FF) 
721.0 (FF) 
0 
2,143.9 
FY26 (programmed) 
0 
0 
1,135.4 (FF) 
2,052.7 (FF) 
0 
3,188.1 
FY27 (programmed) 
0 
0 
1,001.4 (FF) 
2,569.1 (FF) 
580.7 (AP) 
4,151.2 
FY28 (programmed) 
0 
0 
0 
2,068.6 (FF) 
2,574.2 (AP) 
4,642.8 
FY29 (programmed) 
0 
0 
0 
0 
2,744.2 (AP) 
 
Total 
13,316.5 
12,936.0 
13,719.9* 
14,015.6 
n/a 
n/a 
Source: Table prepared by CRS based on Navy’s FY2025 budget submission and prior-year submissions. 
Notes: Figures may not add due to rounding. * In addition, the total for CVN-80 does not add because the Navy 
used requested FY2024 funding figures in preparing the FY2025 budget submission, and the enacted figure for 
FY2024 for CVN-80 ($1,104.4 mil ion) differs from the requested figure ($1,115.3 mil ion). AP is advance 
procurement funding; FF is ful  funding; CC is cost-to-complete funding (i.e., funding to cover cost growth), 
which is sometimes abbreviated in Navy documents as CTC. Regarding the ** notation for the FY2012 funding 
figure for CVN-78, even though FY2012 is after FY2011 (CVN-78’s original final year of ful  funding), the Navy 
characterizes the $86.0 mil ion reprogrammed into FY2012 as ful  funding rather than cost-to-complete funding 
on the grounds that in the years since FY2011, as discussed earlier in this report (see footnote 7), the authority 
to use incremental funding for procuring aircraft carriers has been expanded by Congress to permit more than 
the four years of incremental funding that were permitted at the time that CVN-78 was initially funded. 
Congressional Research Service  
 
10 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 
(As shown in FY2008-FY2024 budgets, in millions of then-year dollars) 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
Est. 
Scheduled/
Est. 
Scheduled/ 
Est. 
Scheduled/
Est. 
Scheduled/
proc. 
actual FY 
proc. 
actual FY 
proc. 
actual FY 
proc. 
actual FY 
Budget 
cost 
of proc. 
cost 
of proc. 
cost 
of proc. 
cost 
of proc. 
FY08 
10,488.9 
FY08 
9,192.0 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY09 
10,457.9 
FY08 
9,191.6 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY10 
10,845.8 
FY08 
n/a 
FY13 
n/a 
FY18 
n/a 
FY23 
FY11 
11,531.0 
FY08 
10,413.1 
FY13 
13,577.0 
FY18 
n/a 
FY23 
FY12 
11,531.0 
FY08 
10,253.0 
FY13 
13,494.9 
FY18 
n/a 
FY23 
FY13 
12,323.2 
FY08 
11,411.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY14 
12,829.3 
FY08 
11,338.4 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY15 
12,887.2 
FY08 
11,498.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY16 
12,887.0 
FY08 
11,347.6 
FY13 
13,472.0 
FY18 
n/a 
FY23 
FY17 
12,887.0 
FY08 
11,398.0 
FY13 
12,900.0 
FY18 
n/a 
FY23 
FY18 
12,907.0 
FY08 
11,377.4 
FY13 
12,997.6 
FY18 
n/a 
FY23 
FY19 
12,964.0 
FY08 
11,341.4 
FY13 
12,601.7 
FY18 
15,088.0 
FY19 
FY20 
13,084.0 
FY08 
11,327.4 
FY13 
12,335.1 
FY18 
12,450.7 
FY19 
FY21 
13,316.5 
FY08 
11,397.7 
FY13 
12,321.3 
FY18 
12,450.7 
FY19 
FY22 
13,316.5 
FY08 
11,929.7 
FY13 
12,405.5 
FY18 
12,483.6 
FY19 
FY23 
13,316.5 
FY08 
12,700.0 
FY13 
12,832.9 
FY18 
12,930.0 
FY19 
FY24 
13,316.5 
FY08 
12,700.0 
FY13 
12,812.9 
FY18 
12,929.1 
FY19 
FY25 
13,316.5 
FY08 
12,936.0 
FY13 
13,719.9 
FY18 
14,015.6 
FY19 
Annual % change 
FY08 to FY09 
-0.3 
 
0% 
 
0% 
 
n/a 
 
FY09 to FY10 
+3.7 
 
n/a 
 
n/a 
 
n/a 
 
FY10 to FY11 
+6.3 
 
n/a 
 
n/a 
 
n/a 
 
FY09 to FY11 
 
 
 
 
+26.7% 
 
 
 
FY11 to FY12 
0% 
 
-1.5% 
 
-0.1% 
 
n/a 
 
FY12 to FY13 
+6.9% 
 
+11.3% 
 
+2.8% 
 
n/a 
 
FY13 to FY14 
+4.1% 
 
-0.6% 
 
0% 
 
n/a 
 
FY14 to FY15 
+0.5% 
 
+1.4% 
 
0% 
 
n/a 
 
FY15 to FY16 
0% 
 
-1.3% 
 
-2.9% 
 
n/a 
 
FY16 to FY17 
0% 
 
+0.4% 
 
-4.2% 
 
n/a 
 
FY17 to FY18 
+0.2% 
 
-0.2% 
 
+0.7% 
 
n/a 
 
FY18 to FY19 
+0.4% 
 
-0.3% 
 
-3.0% 
 
n/a 
 
FY19 to FY20 
+0.9% 
 
-0.1% 
 
-2.1% 
 
-17.5% 
 
FY20 to FY21 
+1.8% 
 
+0.6% 
 
-0.1% 
 
0% 
 
FY21 to FY22 
0% 
 
+4.7% 
 
+0.7% 
 
+0.3% 
 
FY22 to FY23 
0% 
 
+6.5% 
 
+3.4% 
 
+3.6% 
 
FY23 to FY24 
0% 
 
0% 
 
-0.2% 
 
-0.007% 
 
FY24 to FY25 
0% 
 
+1.9% 
 
+7.1% 
 
+8.4% 
 
Cumulative % change through FY24 from actual procurement dates of FY08, FY13, FY18, and FY19 
Since FY08 
+27.0% 
 
+40.7% 
 
+28.0% 
 
n/a 
 
Since FY13 
 
 
+13.4% 
 
 
 
 
 
Since FY18 
 
 
 
 
+5.6% 
 
 
 
Since FY19 
 
 
 
 
 
 
-7.1% 
 
Source: Table prepared by CRS based on Navy’s FY2025 budget submission and prior-year submissions. 
Congressional Research Service  
 
11 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Notes: n/a means not available. The FY2010 budget submission did not show estimated procurement costs or 
scheduled years of procurement for CVNs 79 and 80. The scheduled years of procurement for CVNs 79 and 80 
shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for procuring 
carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference regarding 
recommendations for the FY2010 defense budget. 
Procuring CVN-82 and CVN-83 as a Two-Ship Buy 
Another issue for Congress is whether to procure CVN-82 and a subsequent aircraft carrier 
(which would be CVN-83) as a two-ship buy that would similar to the two-ship buy that was used 
for procuring CVN-80 and CVN-81. Such a two-ship buy could take place in FY2030 (the Navy’s 
programmed year for procuring CVN-82 under its FY2025 budget submission), FY2028 (the 
Navy’s programmed year for procuring CVN-82 under its prior-year budget submissions), or 
FY2029. Procuring CVN-82 and CVN-83 as a two-ship buy in FY2028 could involve increasing 
the amount of advance procurement (AP) funding provided for the aircraft program in FY2025 to 
something more than the figure of roughly $550 million discussed in the previous section. 
Opponents of procuring CVN-82 and CVN-83 as a two-ship buy could argue that it could be 
premature to commit to the procurement of another Ford-class carrier after CVN-81, given 
ongoing changes in military technologies and concepts of operation, and that the additional near-
term procurement funding requirements of a two-ship buy could crowd out funding available for 
other Navy program priorities. 
Supporters of procuring CVN-82 and CVN-83 as a two-ship buy could argue that Ford-class 
carriers will continue to be needed, notwithstanding changes in military technologies and 
concepts of operation, and that a two-ship buy would help support the aircraft carrier industrial 
base by providing a known quantity of carrier-construction work for years to come, and 
substantially reduce the combined procurement cost of the two ships, releasing Navy funding for 
use in meeting other program priorities. 
Future Aircraft Carrier Force Level 
Another issue for Congress concerns the future aircraft carrier force level. Decisions on this issue 
could have implications for the service lives of existing aircraft carriers and/or plans for procuring 
new aircraft carriers. The future aircraft carrier force level has been a frequent matter of 
discussion over the years, and (correctly or not) is often the starting point or the center of broader 
discussions over the future size and composition of the Navy. Factors involved in discussions 
about the future aircraft carrier force level include but are not limited to the following: 
•  the capabilities and costs (including procurement costs and life-cycle operation 
and support [O&S] costs) of aircraft carriers and their embarked air wings, and 
how those capabilities and costs compare to those of other U.S. military forces; 
•  the prospective survivability of aircraft carriers in conflicts against adversaries 
(such as China) with highly capable anti-ship missiles; 
•  the numbers of carriers needed to support policymaker-desired levels of day-to-
day aircraft carrier forward presence in various regions around the world; and 
•  the utility of carriers for purposes other than high-end combat, including 
deterrence of potential regional adversaries, reassurance of allies and partners, 
signaling U.S. commitment and resolve, and noncombat operations such as 
humanitarian assistance/disaster response (HA/DR) operations. 
As noted earlier: 
Congressional Research Service  
 
12 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
•  10 U.S.C. 8062(b) requires the Navy to maintain a force of not less than 11 
operational aircraft carriers.  
•  The Navy wants to achieve and maintain in coming years a fleet of 381 manned 
battle force ships, including 12 aircraft carriers. The Biden Administration has 
not explicitly endorsed the Navy’s desired 381-ship force-level objective or any 
other ship force-level objective for the Navy as a whole.  
•  The Navy’s FY2025 30-year (FY2025-FY2054) shipbuilding plan, which is 
designed to support the eventual attainment of a fleet of about 381 ships, projects 
that, if the plan were implemented, the Navy’s carrier force would include fewer 
than 12 carriers in all but three years within the 30-year period. 
Issues Raised in DOT&E and GAO Reports 
Another oversight issue for Congress concerns CVN-78 program issues raised in a January 2024 
report from DOD’s Director, Operational Test and Evaluation (DOT&E)—DOT&E’s annual 
report for FY2023—and in the 2023 edition of the Government Accountability Office’s (GAO’s) 
annual report surveying selected DOD weapon acquisition programs, which was published in 
June 2023. 
January 2024 DOT&E Report 
Regarding the CVN-78 program, the January 2024 DOT&E report stated the following in part: 
TEST ADEQUACY 
The Navy began CVN 78 IOT&E [Initial Operational Test & Evaluation]  in September 
2022  and  is  conducting  it  in accordance  with  TEMP  [Test  and  Evaluation  Master  Plan] 
Revision E and the DOT&E-approved portions of the IOT&E test plan. However, analysis 
of  the  data  provided  to  DOT&E  to  date  revealed  gaps  in  data  collection,  which,  if  not 
rectified, could result in insufficient data to inform conclusive assessments of reliability, 
maintainability, logistics and/or availability (RMLA) for some key subsystems. In addition 
to  affecting  suitability  assessments,  these  data  gaps  could  also  affect  effectiveness 
assessments due to the on-demand nature of many key subsystems and the reliance upon 
accurate  RMLA  data  in  both  the  self-defense  and  SGR  models.  The  Navy  has 
acknowledged these shortcomings, committed to improve data collection, and will update 
the IOT&E test plan for the major remaining tests such as SGR [sortie generation rate] , 
self-defense, and cyber survivability tests. In April 2023, DOT&E submitted a classified 
CVN  78  Ford-class  Aircraft  Carrier  EFR  [early  fielding  report]  to  Congress,  detailing 
operational and live fire test results to date. 
Prior to deployment, CVN 78 conducted two significant underway periods during IOT&E 
that  included  fixed-wing  flight  operations,  both  of  which  were  in  accordance  with  the 
DOT&E-approved  test  plan  and  observed  by  DOT&E.  A  brief  summary  is  below,  and 
detailed results of the underway periods can be found in DOT&E’s classified EFR. 
In the first significant underway period of  IOT&E, CVN 78 executed a service-retained 
early employment from October 4 to November 26, 2022, as part of CSG 12 [Carrier Strike 
Group 12] that included Tailored Ship’s Training Availability (first deployment work-up 
integrated with CSG); port calls in Halifax, Canada and Portsmouth, England; and multiple 
operations with allies and partners. The early employment was the first time the air wing, 
destroyer squadron staff, and CSG staff embarked on the ship together, and the first period 
of  consistent  cyclic  flight  operations  for  the  Ford  class,  which  resulted  in  896  arrested 
landings (not including carrier qualifications). During the early employment, the maximum 
air wing compliment was approximately 75 percent of the full air wing. 
Congressional Research Service  
 
13 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
In  the  second  significant  underway  period  of  IOT&E,  CVN  78  completed  its  first 
COMPTUEX  [Composite  Training  Unit  Exercise]  (final  pre-deployment  workup)  from 
March 2 to April 2, 2023, off the U.S. east coast. Administered by CSG 4, COMPTUEX 
was  the  first  time  CVN  78  operated  with  an  operationally  representative  air  wing 
embarked, conducting consistent, combat-representative scenarios. During COMPTUEX, 
CVN 78 executed 1,600 total arrested landings, including 1,185 arrested landings during 
cyclic and alert flight operations. At the end of COMPTUEX, CVN 78 had conducted a 
total  of 14,177  catapult  launches  and  arrested  landings  since  its  commissioning. In  July 
2023, the second of three planned CVN 78 land-based cyber survivability operational tests 
was  completed  on  SSDS,  CEC,  and  SEWIP  [Surface  Electronic  Warfare  Improvement 
Program]. The test was conducted in accordance with the DOT&E-approved test plan and 
observed  by  DOT&E.  These  land-based  tests  are  intended  both  to  inform  planning  for 
shipboard  testing  and  to  perform  testing  deemed  too  risky  to  conduct  during  shipboard 
cyber survivability tests prescribed by TEMP Revision E.  
Many systems specific to CVN 78 have yet to undergo any operational cyber survivability 
assessments.  In  June  2023,  the  Navy  updated  its  cyber  survivability  testing  strategy  by 
replacing  the  third  land-based  cyber  survivability  test  with  additional  testing  during 
shipboard cyber assessments after deployment. The third land-based test was scheduled for 
late FY23, and its focus was on hull, mechanical, and electrical systems. This change in 
strategy was primarily due to a lack of existing, robust cyber survivability testing facilities 
for shipboard industrial control systems. The Navy needs to conduct the shipboard tests to 
assess CVN 78’s overall cyber survivability and enable post hoc accreditation of the test 
facilities  used  in  completed  land-based  cyber  survivability  tests.  The  Navy  is  still 
developing these shipboard cyber survivability test plans. 
The CVN 78 Total Ship Survivability Trial (TSST) has been delayed by approximately one 
year, until 4QFY24 [fourth quarter of FY2024], due to the ship’s deployment being earlier 
than planned. The TSST is an onboard, extensive damage-control test to demonstrate how 
the ship design enables the crew to perform its recoverability-related procedures. For the 
CVN 78 TSST to be adequate, the testing will require at-sea execution with participation 
of an embarked air wing. Planning is ongoing to ensure that this adequacy requirement is 
met. 
In  1QFY24,  the  Navy  intends  to  publish  two  vulnerability  assessment  reports  (VARs) 
examining  the  class’s  survivability  against  above-water  and  underwater  kinetic  threats.  
These  reports  will  include  findings  from  survivability  testing  and  modeling  of  the  ship 
conducted since 2007. However, these reports as drafted do not accurately model the ship 
as built and do not include findings from more recent testing. Without updating the models, 
the analysis in the VARs will not support conclusions on the survivability of the CVN 78 
class against threat weapons. The Navy intends to issue a final survivability assessment 
report  that  will  include  the  findings  from  recent  testing  and  update  model-based 
survivability analysis by 4QFY25. If the survivability modeling and simulation (M&S) is 
updated to accurately model the ship as built, this assessment will support DOT&E’s report 
on the survivability of the class against threat weapons. 
Together the CVN 78 TEMP Revision E and the Capstone Enterprise Air Warfare Ship 
Self-Defense (AW SSD) TEMP 1714 of March 2008 provide for a series of live missile 
fire events aboard CVN 78 against specific types of ASCM threat surrogates to assess the 
ship’s anti-air warfare capabilities. The Navy intends to execute these tests in FY25. These 
live  tests  are  necessary  to  assess  ship  self-defense  capability  of  the  as-built,  deployed 
combat system, and to provide validation data for the M&S suite of the CVN 78 combat 
system. While these live fire tests, as planned, are adequate, DOT&E has concerns with 
the Navy’s ability to adequately resource them. The M&S is intended to assess the Navy’s 
PRA  KPP  [Probability  of  Raid  Annihilation  Key  Performance  Parameter].  These  tests, 
combined with those conducted on the self-defense test ship, and the PRA model runs are 
required to determine CVN 78’s operational effectiveness against specific types of ASCM 
Congressional Research Service  
 
14 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
[anti-ship  cruise  missile]  threats.  In  FY23,  the  Navy  continued  to  develop  a  draft  new 
Enterprise  TEMP  in  support  of  SSDS  Mk  2  Baseline  12  and  SPY-6  V(2)  and  V(3) 
platforms [ships equipped with SPY-6 V(2) and V(3) radars] (TEMP 1910) that includes 
FOT&E [Follow-on Operational Test and Evaluation] on CVN 79. While CVN 79 self-
defense  test  design  will  mature  during  the  TEMP  1910  development,  any  delay  in  the 
current timeline for testing the CVN 79 combat systems will be challenged by the planned 
deactivation timeline for the self-defense test ship, the ex-USS Paul F. Foster. The Navy 
should maintain the capability of the self-defense test ship, currently provided by the ex-
USS Paul F. Foster. 
The CVN 78 SGR evaluation comprises M&S (for both Ford and Nimitz class), a four-day 
sustained  test  on  CVN  78,  a  one-day  surge  test  on  CVN  78,  and  flight  operations 
observations on a Nimitz-class carrier. Development of the M&S suite intended to evaluate 
the SGR,  the Sea  Strike/Sea  Basing Aviation Model (SSAM), is ongoing. The CVN 78 
SGR tests are incomplete. The CVN 78 sustained SGR test was originally scheduled for 
the first COMPTUEX; however, due to COMPTUEX syllabus changes, ship and air wing 
schedule  changes,  and  resourcing,  it  was  deferred  to  the  second  COMPTUEX,  now 
expected to occur in FY25. The Navy plans to apply lessons from the CVN 78 sustained 
SGR  test  to  the  surge  SGR  test  which  is  currently  unscheduled.    A  Nimitz-class 
COMPTUEX to collect flight operations data to support a Nimitz-class SGR M&S suite 
(part  of  SSAM)  for  comparative  analysis  is  planned  for  FY24.  DOT&E  approved  these 
deferments in Revision 1 to the IOT&E test plan. The Navy needs to provide an updated 
test plan prior to conducting these events. 
PERFORMANCE 
EFFECTIVENESS 
Insufficient  data  are  available  to  determine  CVN  78’s  operational  effectiveness  due  to 
IOT&E being incomplete. Observations based on testing to date are below. 
Combat System 
Self-defense  testing  against  unmanned  aerial  vehicles  (UAVs)  and  high-speed 
maneuvering  surface  targets  (small  boats)  was  conducted  in  July  2022.  Details  can  be 
found  in  DOT&E’s  classified  EFR.  The  Navy  is  developing  fixes  to  combat  system 
deficiencies identified in DOT&E’s classified USS Gerald R. Ford (CVN 78) Self-Defense 
Interim  Assessment  report  dated  April  2022.  However,  to  date  the  fixes  remain  largely 
unfunded.  
Sortie Generation 
In FY23, CVN 78 conducted almost as many flight operations (as measured by the number 
of  aircraft  launch  and  recoveries)  as  it  had  in  the  previous  five  years  combined  since 
commissioning. From the first arrested landing on CVN 78 in July 2017 until the end of 
FY22, CVN 78 had conducted 10,826 arrested landings. In FY23 alone, CVN 78 conducted 
9,266 arrested landings. The reliability and maintainability of CVN 78’s EMALS and AAG 
continue  to  adversely  affect  sortie  generation  and  flight  operations,  which  remains  the 
greatest risk to demonstrating operational effectiveness and suitability in IOT&E. Despite 
these  continuing  reliability  challenges,  DOT&E  observed  general  increases  in  crew 
proficiency and decreases in some repair times. While this has improved sortie generation 
compared to previous years, SGR tests have not been completed yet nor have training sortie 
rates  flown  to  date  approached  that  of  the  KPP  requirement.  CVN  78  earned  the  flight 
operations  efficiency  portion  of  its  Blue  Water  Certification  as  part  of  the  Navy’s 
deployment  certification  process.  Observations  during  COMPTUEX  suggests  that  the 
Ford-class flight deck design improves the efficiency of aircraft turnarounds compared to 
that of a Nimitz-class flight deck. Additional details on sortie generation effectiveness can 
be found in DOT&E’s classified EFR. Executing the planned SGR testing, as outlined in 
TEMP  Revision  E,  will  be  crucial  to  evaluating  the  ship’s  combat  effectiveness  and 
Congressional Research Service  
 
15 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
accrediting the high-fidelity SSAM which is an essential tool for evaluating the SGR KPP 
and supporting life-of-class upgrades. 
Electromagnetic Spectrum Compatibility 
Developmental  testing  identified  significant  electromagnetic  radiation  hazard  and 
interference problems. The Navy implemented some mitigation measures and conducted 
follow-on characterization testing during independent steaming events in developmental 
test, but some operational limitations and restrictions are expected to persist into IOT&E 
and  deployment.  The  Navy  should  verify  developmental  test  electromagnetic  spectrum 
compatibility during operational test, particularly when integrated with CSG operations in 
an  advanced  electronic  attack  environment.  This  will  enable  capability  assessments  at 
differing levels of system use to inform decisions on system employment. 
SUITABILITY 
Insufficient data are available to determine CVN 78’s operational suitability. However, the 
following  four  new  CVN  78  systems  have  shown  low  or  unproven  reliability  and  are 
highlighted as the most significant challenge to flight operations. 
AAG 
During FY23, DOT&E observed AAG reliability similar to recent developmental testing 
(115  mean  cycles  between  operational  mission  failures  [MCBOMF]  in  FY21  and  460 
MCBOMF  in  FY22).  Despite  some  software  and  hardware  improvements  in  AAG, 
reliability has not appreciably changed because the FY23 data reflects many short-duration 
failures  that  were  unreported  in  developmental  test,  as  well  as  system-of-systems 
degradations, all of which would have prevented landing. Naval Air Systems Command 
(NAVAIR) delivered hardware updates after early employment and before COMPTUEX, 
along with a software update before deployment. NAVAIR continues to work on short- 
and long-term improvements to address AAG reliability degraders. However, difficulties 
such as obtaining replacement parts and the reliance on off-ship technical support remain 
a challenge. The Navy is also using IOT&E to inform the decision of whether to retrofit 
the fourth AAG engine on Ford-class aircraft carriers (as designed, which would make it 
similar to the arresting gear engine/wire configuration on CVN 76 and CVN 77). The fourth 
AAG engine was not installed as a cost savings measure. In a 2016 requirements review 
board,  the  Navy  committed  to  informing  a  potential  retrofit  decision  with  the  results  of 
IOT&E. The criteria on which to base a potential retrofit decision were not specified, and 
with changes to the IOT&E schedule, more data will be available before the end of IOT&E. 
The fourth engine  would improve the reliability and availability of AAG, improve pilot 
boarding rate, and restore barricade redundancy. Additional details on AAG suitability can 
be found in DOT&E’s classified EFR. 
EMALS 
During  FY23,  DOT&E  observed  EMALS  reliability  remained  consistent  with  recent 
developmental  test  (460  MCBOMF  in  FY21  and  614  MCBOMF  in  FY22).  Despite 
engineering  upgrades  to  hardware  and  software,  reliability  has  not  appreciably  changed 
from prior years and reliance on off-ship technical support remains a challenge. As part of 
an  effort  to  provide  short-  and  long-term  improvements  to  address  EMALS  reliability 
degraders, NAVAIR delivered a software update and upgraded all catapult position sensor 
blocks  prior  to  CVN  78’s  deployment  and  is  continuing  development  on  further 
improvements.  Furthermore,  a  situational  awareness  display  was  added  in  the  EMALS 
Maintenance  Workstation  that  facilitates  troubleshooting  during  operations.  Additional 
details can be found in DOT&E’s classified EFR.  
Advanced Weapons Elevators (AWEs) 
The  early  employment  and  COMPTUEX  provided  CVN  78’s  first  operationally 
representative  opportunities  to  demonstrate  ordnance  movement  during  cyclic  flight 
Congressional Research Service  
 
16 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
operations. The AWEs met operational mission needs during these underway periods, but 
preliminary data suggest AWE is unlikely to meet its operational availability requirement 
of 99.7 percent. Of note, the crew is reliant on off-ship technical support for correction of 
hardware  and  software  failures.  As  of  the  end  of  COMPTUEX,  the  ship  had  conducted 
23,042 total AWE  cycles. The Navy has yet to build and transfer ordnance to the flight 
deck  at  combat-representative  rates.  DOT&E  expects  the  SGR  tests  to  be  the  first 
operationally representative demonstration of high ordnance throughput. Additional details 
can be found in DOT&E’s classified EFR. 
DBR 
During  COMPTUEX,  DBR  availability  was  observed  to  be  lower  than  that  during 
developmental testing. This is in part due to the operational expectation of continuous radar 
coverage. Reliability concerns are amplified due to the one-of-a-kind nature of the DBR. 
The  radar  relies  on  embarked  contractor  support  and  there  is  uncertainty  on  sourcing 
replacement  parts  as  the  system  ages.  The  Navy  should  ensure  replacement  parts  are 
manufactured and available for the life of the system or develop a timeline and strategy for 
replacing DBR with EASR [Enterprise Air Surveillance Radar25] on CVN 78 to bring it in 
line with CVN 79’s radar configuration. Additional details on DBR suitability can be found 
in DOT&E’s classified EFR. 
Manning and Berthing 
Per the Navy’s Shipboard Habitability Program, all new ships are required to have a growth 
allowance  of  10  percent  of  ship’s  company  when  the  ship  delivers.  This  Service  Life 
Allowance provides both empty bunks to allow for changes in the crew composition over 
the ship’s life and berthing to support crew turnover, visitors, and personnel temporarily 
assigned to the ship for repairs, inspections, test, and training. However, sufficient berthing 
is not installed for CVN 78 to conduct combat operations with all hands assigned a bed. 
While the ship’s company manning is reduced from Nimitz-class carriers by approximately 
500  personnel,  the  lack  of  berthing  capacity  is  driven  by  embarked  units.  Based  on  the 
composition  of  the  ship  and  embarked  units  during  COMPTUEX  and  their  respective 
manning documents, if each was at 100 percent manning, the ship would have a shortfall 
of 159 beds. These berthing shortfalls will affect quality of life onboard and could reduce 
the Navy’s operational flexibility in employing the ship across its full spectrum of missions 
and logistical support roles for the CSG. Furthermore, there is potential that the berthing 
shortfalls could increase as the air wing diversifies to include CMV-22, F-35, and MQ-25, 
none of which are on CVN 78 today. Additional details on manning and berthing can be 
found in DOT&E’s classified EFR. 
SURVIVABILITY 
An adequate survivability assessment of the CVN 78 class depends upon a combination of 
FSST,  TSST,  and  related  modeling  of  the  class  supported  by  component  and  surrogate 
testing.  To  date,  the  Navy  has  completed  all  planned  LFT&E  [Live  Fire  Test  and 
Evaluation], with the exception of TSST, the VARs, and the final survivability assessment. 
From June to August 2021, the Navy conducted FSST on CVN 78, including three shock 
events  of  increasing  severity.  In  December  2022,  DOT&E  published  a  classified  FSST 
report  that details  findings  from  the  trial,  and  in  July  2023,  the  Navy  published  its own 
FSST report. Both reports identify deficiencies that, if addressed, will improve the class’s 
survivability against weapon events. 
The  survivability  of  CVN  78  in  a  cyber-contested  environment  has  not  yet  been  fully 
evaluated. Results from the land-based cyber survivability tests will inform the shipboard 
 
25 The term Enterprise in this instance is not a reference to CVN-80; it instead means a piece of equipment that is to be 
installed on multiple types of ships across the Navy (i.e., across the naval enterprise). 
Congressional Research Service  
 
17 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
cyber  survivability  tests.  Some  systems  specific  to  CVN  78  have  yet  to  undergo  any 
operational cyber survivability assessments. 
The  survivability  of  CVN  78  in  contested  and  congested  electromagnetic  spectrum 
environments  has  not  been  evaluated.  Discussions  on  how  to  evaluate  CVN  78 
survivability in these environments are ongoing with the Navy. 
RECOMMENDATIONS 
The Navy should: 
1.  Improve  the  suitability  of  AAG,  EMALS,  AWE,  and  DBR  while  minimizing  the 
requirement for off-ship and/or contractor technical support. 
2.  Reevaluate the timeline and better define the criteria for a decision to retrofit the fourth 
AAG engine. 
3.  Collect data in accordance with the test plan for the remainder of IOT&E. 
4.  Resource and execute the testing per Enterprise AW SSD TEMP 1714 and CVN 78 
TEMP,  including  the  planned  SGR  testing,  along  with  completing,  verifying,  and 
validating the SGR M&S suite; shipboard cyber survivability testing; and self-defense tests 
and PRA modeling. 
5.  Address the recommendations in DOT&E’s classified self-defense interim assessment 
report from April 2022, and the additional recommendations in DOT&E’s classified EFR 
from April 2023. 
6.  Develop a plan to sustain DBR on CVN 78 or replace it as soon as possible with the 
EASR configuration on CVN 79 and subsequent Ford-class carriers. 
7.  Re-examine  manning  and  berthing  for  future  ships  of  the  class  to  ensure  sufficient 
berthing is available and that 10 percent Service Life Allowance is allocated to allow future 
growth. 
8.  Submit for DOT&E approval a test plan revision to update the test plan schedule. 
9.  Continue  to  develop  more  robust  capabilities  to  test  the  cyber  survivability  of 
shipboard industrial control systems. 
10.  Execute the TSST with an embarked air wing in FY24. 
11.  Prioritize  and  correct deficiencies  identified  in  DOT&E’s  classified  FSST  report  of 
December 2022. 
12.  Produce a project schedule to complete required updates to the vulnerability modeling 
and simulation by 4QFY24 to support accurate vulnerability reporting in the CVN 78 final 
survivability assessment report in 4QFY25. 
13.  Submit for DOT&E approval in 1QFY25 an update of the CVN 78 TEMP, aligned 
with the new Enterprise TEMP 1910, that provides the test strategy and test resources to 
determine operational effectiveness of new and/or upgraded capabilities on CVN 79. 
14.  Ensure the availability of the capability provided by ex-USS Paul F. Foster, the Navy’s 
self-defense test ship, to support combat system testing. 
15.  To  better  inform  effectiveness  and  survivability,  verify  developmental  test 
electromagnetic  spectrum  compatibility  during  operational  test,  particularly  when 
integrated with CSG operations in an advanced electronic attack environment.26 
 
26 Director, Operational Test & Evaluation, FY 2023 Annual Report, January 2024, pp. 177-182. 
Congressional Research Service  
 
18 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
June 2024 GAO Report 
A June 2023 GAO report—the 2024 edition of GAO’s annual report assessing selected major 
weapon acquisition programs—stated the following about the CVN-78 program: 
Technology Maturity, Design Stability, and Testing 
Twenty-four years after the program started, CVN 78’s 12 critical technologies are mature 
and the design is stable, though the program replaced the Ford class’s original Dual Band 
Radar with the new Enterprise Air Surveillance Radar (EASR) on CVN 79 and later ships. 
Program officials stated that they plan to begin EASR testing on CVN 79 in 2024. The 
program also anticipates that the transition to a digital design tool will enhance construction 
efficiency. 
The  Navy  began  operational  testing  on  CVN  78  in  August  2022,  but  extended  the  test 
period by 16 months to March 2025, and the Office of the Director, Operational Test and 
Evaluation  (DOT&E)  reported  an  additional  delay  into  fiscal  year  2027.  According  to 
program officials, two factors caused this test extension. First, the program needs additional 
time to plan and prepare for one of the ship’s final test events that will also demonstrate 
CVN  78’s  ability  to  launch  and  recover  aircraft  more  quickly  than  Nimitz  class  ships. 
Second, the Navy moved CVN 78’s first operational deployment from 2024 to 2023 in 
support of operations in the Middle East, which also delayed test events. DOT&E identified 
a  third  factor:  the  time  to  incorporate  data  on  aircraft  launch  and  recovery  testing,  run 
associated models, and analyze results. 
Cybersecurity 
According to program officials, the CVN 78 program completed a second cybersecurity 
vulnerability assessment in February 2023, and they plan for a third to be completed in 
February 2024. Program officials also said the third assessment will use data from prior 
assessments to conduct an adversarial assessment on live ship systems. 
Other Program Issues 
Since our last assessment, the Navy increased the CVN 79 cost limitation baseline by $236 
million to support full ship delivery efforts. According to Navy documentation, this amount 
does  not  reflect  new  costs  for  the  program  because  the  Navy  previously  planned  and 
budgeted  this  amount for post-delivery  activities.  As  of  December  2023,  CVN  79  is  90 
percent  complete,  according  to  program  officials.  This  change  moves  work  originally 
planned  to  occur  after  delivery—such  as  modifications  to  support  the  F-35—to  the 
construction phase. Program officials told us they based this decision on lessons learned 
from  CVN  78,  which  had  more  post-delivery  work  than  expected,  resulting  in  schedule 
delays and cost growth. The Navy anticipates that this  will decrease the time required to 
resolve discrepancies discovered during the ship’s trials. 
The shipbuilder is now scheduled to deliver CVN 79 in July 2025 instead of September 
2024. Program officials stated this change did not result in new program costs. However, 
it  did  move  planned  post-delivery  costs  into  CVN  79’s  construction  cost  limitation 
baseline, resulting in an increase to $12.9 billion—more than $1.5 billion over the same 
baseline since 2021. As we reported last year, CVN 79 costs increased $1.3 billion largely 
due to contract overruns. 
Construction  delays  are  emerging  for  CVN  80  because  of  ongoing  industrial  base 
challenges. Program officials project that the ship will not meet its planned March 2028 
delivery  and  are  conducting  a  schedule  assessment  with  the  shipbuilder.  CVN  80  is  36 
percent complete and facing supply chain delays, as well as challenges with shipyard and 
vendor workforces. Program officials explained that the shipbuilder is struggling with a 
smaller, inexperienced workforce that is less efficient at completing work, especially after 
many skilled, senior workers retired during the COVID-19 pandemic. The Navy reported 
Congressional Research Service  
 
19 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
that the contractor is taking steps to mitigate these issues by using contracting incentives 
to improve shipyard facilities to better attract and support workers and expanding the dry 
dock to enable simultaneous construction of two carriers. While these mitigations can help 
the  Ford  class  more  broadly,  they  are  unlikely  to  improve  CVN  80  construction 
performance because they are not yet in place. 
Program officials do not expect industrial base issues to affect CVN 81, based on planned 
shipyard  improvements.  CVN  81  keel  laying  is  planned  for  2026  and delivery  in  2032. 
Further, officials are considering a two-ship contract for planned CVNs 82 and 83, like the 
Navy reported awarding for CVNs 80 and 81. They are examining potential acquisition 
strategies to inform the fiscal year 2025 budget submission. 
Program Office Comments 
We provided a draft of this assessment to the program office for review and comment. It 
provided technical comments, which we incorporated where appropriate. 
The Navy noted that CVN 78’s first operational deployment was accelerated from 2024 to 
2023, and that the ship returned from the eastern Mediterranean in January 2024 after an 
extended deployment that included working with 17 nations, sailing 83,476 nautical miles, 
conducting  10,396  sorties,  and  logging  17,826  flight  hours.  Program  officials  did  not 
provide  additional  details  on DOT&E’s  reported  delay  of  the  end  of  operational  testing 
except to note that they are evaluating the schedule of remaining test events. The program 
stated that CVN 79’s delivery strategy is expected to lead to a more capable ship at delivery 
and  prepare  it  as  the  first  Ford  class  carrier  to  operate  in  the  Indo-Pacific  region  while 
decreasing post-delivery time at the shipyard. It added that the Navy and the shipbuilder 
are upgrading shipyard facilities and assessing shipbuilder and vendor resources to improve 
efficiency and schedule performance. The program stated that it expects initiatives such as 
a digital shipbuilding model and shipyard improvement incentives to improve planning and 
construction efficiency.27 
Procurement of Aircraft Carriers After CVN-81 or CVN-82 
Another issue for Congress concerns the procurement of aircraft carriers after CVN-81 or CVN-
82. The question of whether the Navy should shift at some point from procuring CVNs like the 
Ford-class carriers to procuring smaller and perhaps nonnuclear-powered aircraft carriers has 
been a recurrent matter of discussion and Navy study over the years. 
Although the Navy wants to achieve and maintain in coming years a fleet of 381 manned battle 
force ships, including 12 aircraft carriers, force-structure studies done by the Navy that eventually 
led to the 381-ship goal showed future Navy force structures that included 8 to 12 carriers, to be 
supplemented (in the case of the lower end of that range) by up to 6 light aircraft carriers (CVLs). 
The Navy does not currently operate CVLs. The Navy in recent years has experimented with the 
concept of using an LHA-type amphibious assault ship with an embarked group of F-35B Joint 
Strike Fighters as a CVL.28 
Advocates of smaller carriers traditionally have argued that they are individually less expensive 
to procure, that the Navy might be able to employ competition between shipyards in their 
procurement (something that the Navy cannot do with large-deck, nuclear-powered carriers like 
 
27 Government Accountability Office, Weapon Systems Annual Assessment[:] DOD Is Not Yet Well-Positioned to Field 
Systems with Speed, GAO-24-106831, June 2024, p. 132. 
28 See CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship Programs: Background and Issues for 
Congress, by Ronald O'Rourke; Megan Eckstein, “Light Carrier Studies Already Underway As Navy Considers Role 
for CVLs in Future Fleet,” USNI News, February 1, 2021. See also Joseph Trevithick, “Navy Looking At America And 
Ford Class Derivatives In New Light Aircraft Carrier Studies,” The Drive, February 2, 2021. 
Congressional Research Service  
 
20 
 link to page 25 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
the Ford-class carrier, because only one U.S. shipyard, HII/NNS, can build aircraft carriers of that 
size), and that today’s aircraft carriers concentrate much of the Navy’s striking power into a 
relatively small number of expensive platforms that adversaries could focus on attacking in time 
of war. 
Supporters of CVNs traditionally have argued that smaller carriers, though individually less 
expensive to procure, are less cost-effective in terms of dollars spent per aircraft embarked or 
aircraft sorties that can be generated; that it might be possible to use competition in procuring 
certain materials and components for large-deck, nuclear-powered aircraft carriers; and that 
smaller carriers, though perhaps affordable in larger numbers, would be individually less 
survivable in time of war than CVNs.29 
Section 128(d) of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of 
November 25, 2015) required the Navy to submit a report on potential requirements, capabilities, 
and alternatives for the future development of aircraft carriers that would replace or supplement 
the Ford-class aircraft carrier. The report, which was conducted for the Navy by the RAND 
Corporation, was delivered to the congressional defense committees in classified form in July 
2016. An unclassified version of the report was then prepared and issued in 2017 as a publicly 
released RAND report.30 The question of whether to shift to smaller aircraft carriers was also 
addressed in three studies on future fleet architecture that were required by Section 1067 of the 
FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015). 
Legislative Activity for FY2025 
Summary of Congressional Action on FY2025 Funding Request 
Table 3 summarizes congressional action on the FY2025 procurement funding request for the 
CVN-78 program. The request for CVN-79 is for cost-to-complete (CC) funding to cover cost 
growth on CVN-79 following the completion in FY2018 of the ship’s original full funding. 
Table 3. Congressional Action on FY2024 Procurement Funding Request 
(Millions of dollars, rounded to nearest tenth)  
Authorization 
Appropriation 
 
Request 
HASC 
5ASC 
Enacted 
HAC 
SAC 
Enacted 
CVN-79 
236.0 
236.0 
 
 
236.0 
 
 
CVN-80 
1,186.9 
986.9 
 
 
1,123.1 
 
 
CVN-81 
721.0 
721.0 
 
 
674.9 
 
 
CVN-82 
0 
0 
 
 
0 
 
 
CVN-82 and CVN-83 
0 
100.0 
 
 
0 
 
 
Total  
2,143.9 
2,043.9 
 
 
2,034.0 
 
 
Source: Table prepared by CRS based on Navy’s FY2025 budget submission, committee and conference 
reports, and explanatory statements on FY2025 National Defense Authorization Act and FY2025 DOD 
Appropriations Act. 
 
29 See, for example, Talbot Manvel, “The Lightning Carrier Isn’t Either,” U.S. Naval Institute Proceedings, July 2023. 
30 Bradley Martin and Michael McMahon, Future Aircraft Carrier Options, Santa Monica, CA, RAND Corporation, 
2017, 87 pp. 
Congressional Research Service  
 
21 
 link to page 25 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is 
House Appropriations Committee; SAC is Senate Appropriations Committee. The request for CVN-79 is for 
cost-to-complete (CC) funding to cover cost growth on CVN-79 fol owing the completion in FY2018 of the 
ship’s original ful  funding. 
FY2025 National Defense Authorization Act (H.R. 8070) 
House 
The House Armed Services Committee, in its report (H.Rept. 118-529 of May 31, 2024) on H.R. 
8070, recommended the funding levels shown in the HASC column of Table 3. The 
recommendation for Ford-class carriers other than CVN-81 (which has its own funding line item) 
includes a recommended increase of $100.0 million for “Advance Procurement for CVN 82 and 
83,” and a recommended reduction of $200.0 million for “Rephasing of incremental funding.” 
(Page 425) 
Section 131 of H.R. 8070 would modify a requirement for an annual report on cost targets for 
Ford-class carriers to include carriers after CVN-81, and to include certain additional cost 
information. 
Section 138 would express the sense of the Congress that 
•  DOD and the Navy should implement aircraft carrier acquisition strategies that 
maximize benefits to operational commanders while simultaneously protecting 
the interests of the taxpayer and supporting the national nuclear shipbuilding 
industrial base; 
•  DOD and the Navy should review and revise the acquisition strategy, including a 
two-ship buy of CVN-82 and 21 CVN-83, for Ford-class aircraft carriers in the 
DOD’s FY2026 budget submission to ensure it is consistent with accepted 
shipbuilding industrial base analyses, prior DOD recommendations, reports to 
Congress, congressional resolutions, 10 U.S.C. 8062, and national security 
interests; and 
•  DOD should request procurement of CVN-82 not later than FY2028. 
Section 218 would modify a requirement for the Nimitz-class carrier CVN-73 to be modified to 
support the fielding of the MQ-25 carrier-based unmanned aerial vehicle (UAV). 
H.Rept. 118-529 states: 
Support for stable procurement schedules of Ford-class aircraft carriers 
The committee notes that the future years defense program accompanying the President’s 
budget request for fiscal years 2023 and 2024 forecast procurement of the fifth ship in the 
Gerald R. Ford-class of nuclear-powered aircraft carriers—CVN 82—in 2028. 
The committee also notes that the fiscal year 2024 30-year shipbuilding plan recognizes 
the  importance  of  stability  and  predictability  to  the  fragile  Navy  shipbuilding  industry, 
particularly  the  Navy’s  nuclear  shipbuilding  industry,  and  that  without  consistent  and 
continuous commitment to steady and executable acquisition profiles the industrial base 
will continue to struggle. 
The  committee  acknowledges  that  the  Secretary  of  the  Navy  submitted  a  report  to  the 
congressional defense committees, in accordance with section 132 of the National Defense 
Authorization  Act  for  Fiscal  Year  2023  (Public  Law  117–263),  highlighting  the 
overwhelming  benefits  of  a  stable,  executable  Ford-class  acquisition  profile  to  the 
Congressional Research Service  
 
22 
 link to page 25 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
development  and  retention  of  highly-skilled  workforces  and  investment  in  world-class 
manufacturing and shipbuilding facilities. 
Consistent with this report, the committee remains supportive of acquisition strategies that 
maximize  benefits  to  operational  commanders  while  simultaneously  protecting  the 
interests of the taxpayer and supporting the nuclear shipbuilding industrial base. 
The committee reaffirms that section 8062 of title 10, United States Code, mandates that 
the  naval  combat  forces  of  the  Navy  shall  include  not  less  than  11  operational  aircraft 
carriers, and that section 123 of the National Defense Authorization Act for Fiscal Year 
2019 (Public Law 115–232) conveyed a Sense of Congress that the United States should 
accelerate the production of aircraft carriers to rapidly achieve the Navy’s goal of having 
12 operational aircraft carriers. 
The  committee  recognizes  that  attaining  and  maintaining  this  force  structure  requires  a 
stable and predictable acquisition strategy to replace Nimitz-class aircraft carriers prior to 
inactivation.  
The committee is displeased, therefore, that the President’s budget request for fiscal year 
2025 delays CVN 82 procurement until 2030, in direct  contrast with prior years’ budget 
requests and contrary to guidance outlined in the Navy’s 30-year shipbuilding plans and 
associated reports to Congress. 
The  committee  is  similarly  concerned  with  the  detrimental  and  potentially  long-lasting 
impacts  of  this  unstable  and  unpredictable  acquisition  strategy  on  the  industrial  base, 
mandatory aircraft carrier force structure levels and national security. 
As such, the committee strongly encourages the Navy to review and revise the future Ford-
class acquisition strategy, starting with CVN 82, in the President’s budget request for fiscal 
year  2026  to  ensure  it  is  consistent  with  accepted  shipbuilding  industrial  base  analyses, 
prior  departmental  recommendations,  congressional  resolutions,  title  10  mandates,  and 
national security interests. (Pages 25-26) 
FY2025 DOD Appropriations Act (H.R. 8774) 
House 
The House Appropriations Committee, in its report (H.Rept. 118-557 of June 17, 2024) on H.R. 
8774, recommended the funding levels shown in the HAC column of Table 3. The recommended 
reduction of $63.749 million for CVN-80 includes a reduction of $41.456 million for “Early to 
need,” and a reduction of $22.293 million for “Unjustified cost growth.” (Page 129) The 
recommended reduction of $46.115 million for CVN-81 is for “early to need.” (Page 129) 
 
Congressional Research Service  
 
23 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Appendix. Background Information on Two-Ship 
Block Buy for CVN-80 and CVN-81 
This appendix presents additional background information on the two-ship block buy contract for 
CVN-80 and CVN-81. 
The option for procuring two Ford-class carriers under a two-ship block buy contract had been 
discussed in this CRS report since April 2012.31 In earlier years, the discussion focused on the 
option of using a block buy contract for procuring CVN-79 and CVN-80. In subsequent years, 
interest among policymakers focused on the option of using a block buy contract for procuring 
CVN-80 and CVN-81. 
On March 19, 2018, the Navy released a request for proposal (RFP) to Huntington Ingalls 
Industries/Newport News Shipbuilding (HII/NNS) regarding a two-ship buy of some kind for 
CVN-80 and CVN-81. A March 20, 2018, Navy News Service report stated the following: 
The Navy released a CVN 80/81 two-ship buy Request for Proposal (RFP) to Huntington 
Ingalls Industries—Newport News Shipbuilding (HII-NNS) March 19 to further define the 
cost savings achievable with a two-ship buy. 
With lethality and affordability a top priority, the Navy has been working with HII-NNS 
over the last several months to estimate the total savings associated with procuring CVN 
80 and CVN 81 as a two-ship buy. 
“In keeping with the National Defense Strategy, the Navy developed an acquisition strategy 
to  combine  the  CVN  80  and  CVN  81  procurements  to  better  achieve  the  Department’s 
objectives of building a more lethal force with greater performance and affordability,” said 
James F. Geurts, Assistant Secretary of the Navy, Research Development and Acquisition. 
“This  opportunity  for  a  two-ship  contract  is  dependent  on  significant  savings  that  the 
shipbuilding  industry  and  government  must  demonstrate.  The  Navy  is  requesting  a 
proposal from HII-NNS in order to evaluate whether we can achieve significant savings.” 
The two-ship buy is a contracting strategy the Navy has effectively used in the 1980s to 
procure  Nimitz-class  aircraft  carriers  and  achieved  significant  acquisition  cost  savings 
compared  to  contracting  for  the  ships  individually.  While  the  CVN  80/81  two-ship  buy 
negotiations transpire, the Navy is pursuing contracting actions necessary to continue CVN 
80 fabrication in fiscal year (FY) 2018 and preserve the current schedule. The Navy plans 
to award the CVN 80 construction contract in early FY 2019 as a two-ship buy pending 
Congressional approval and achieving significant savings.32 
Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/P.L. 115-232 of August 13, 2018) permitted the Navy, after DOD made certain 
certifications to Congress, to add CVN-81 to the existing contract for building CVN-80. DOD 
provided the required certification on December 31, 2018. On January 31, 2019, the Navy 
 
31 See the section entitled “Potential Two-Ship Block Buy on CVN-79 and CVN-80” in the April 4, 2012, version of 
CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress, by 
Ronald O'Rourke. In more recent years, this section was modified to discuss the option in connection with CVN-80 and 
CVN-81. 
32 Naval Sea Systems Command Public Affairs, “Navy Seeks Savings, Releases Two-Carrier RFP,” Navy News, March 
20, 2018. See also Megan Eckstein, “UPDATED: Navy, Newport News Taking Steps Towards Two-Carrier Buy,” 
USNI News, March 19, 2018. 
Congressional Research Service  
 
24 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
announced that it had awarded a two-ship fixed-price incentive (firm target) (FPIF) contract for 
CVN-80 and CVN-81 to HII/NNS.33 
The two-ship contract for CVN-80 and CVN-81 can be viewed as a block buy contract because 
the two ships were procured in different fiscal years (CVN-80 was procured in FY2018 and 
CVN-81 was procured in FY2019 [or, according to the Navy’s FY2021-FY2024 budget 
submissions, in FY2020]).34 The Navy’s previous two-ship aircraft carrier procurements occurred 
in FY1983 (for CVN-72 and CVN-73) and FY1988 (for CVN-74 and CVN-75). In each of those 
two earlier cases, however, the two ships were fully funded within a single fiscal year, making 
each of these cases a simple two-ship purchase (akin, for example, to procuring two Virginia-
class attack submarines or two DDG-51 class destroyers in a given fiscal year) rather than a two-
ship block buy (i.e., a contract spanning the procurement of end items procured across more than 
one fiscal year). 
Compared to DOD’s estimate that the two-ship block buy contract for CVN-80 and CVN-81 
would produce savings of $3.9 billion (as measured from estimated costs for the two ships in the 
December 2017 Navy business case analysis), DOD states that “the Department of Defense’s 
Office of Cost Assessment and Program Evaluation (CAPE) developed an Independent Estimate 
of Savings for the two-ship procurement and forecast savings of $3.1 billion ([in] Then-Year 
[dollars]), or approximately 11 percent.... The primary differences between [the] CAPE and Navy 
estimates of savings are in Government Furnished Equipment35 and production change orders.”36 
Within the total estimated combined reduction in cost, HII/NNS reportedly expects to save up to 
$1.6 billion in contractor-furnished equipment.37 
A November 2018 DOD report to Congress that was submitted as an attachment to DOD’s 
December 31, 2018, certification stated the following regarding the sources of cost reduction for 
the two-ship contract: 
The  CVN  80  and  CVN  81  two-ship  buy  expands  and  improves  upon  the  affordability 
initiatives  identified  in  the  Annual  Report  on  Cost  Reduction  Efforts  for  JOHN  F. 
KENNEDY (CVN 79) and ENTERPRISE (CVN 80) as required by section 126(c) of the 
National  Defense  Authorization  Act  for  Fiscal  Year  2017  (P.L.  114-328).  Production 
saving initiatives for single-ship buys included use of unit families in construction, pre-
outfitting  and  complex  assemblies  which  move  work  to  a  more  efficient  workspace 
environment,  reduction  in  the  number  of  superlifts,38  and  facility  investments  which 
improve the shipbuilder trade effectiveness. A two-ship buy assumes four years between 
 
33 See Office of the Navy Chief of Information, “Navy Awards Contract for Construction of Two Carriers,” Navy News 
Service, January 31, 2019; Megan Eckstein, “UPDATED: Navy Awards 2-Carrier Contract to Newport News 
Shipbuilding,” USNI News, January 31, 2019; Marcus Weisgerber, “US Navy Places First 2-Carrier Order in Three 
Decades,” Defense One, January 31, 2019; David B. Larter, “US Navy Signs Mammoth Contract with Huntington 
Ingalls for Two Aircraft Carriers,” Defense News, January 31, 2019; Rich Abott, “Navy Awards HII $15 Billion In 
Two Carrier Buy,” Defense Daily, February 1, 2019. 
34 For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy 
Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke. 
35 Government-furnished equipment (GFE) is equipment that the government purchases from supplier firms and then 
provides to the shipbuilder for incorporation into the ships. 
36 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 8-9. 
37 Rich Abott, “Navy Awards HII $15 Billion In Two Carrier Buy,” Defense Daily, February 1, 2019. Contractor-
furnished equipment (CFE) is equipment that the contractor (in this case, HII/NNS) purchases from supplier firms for 
incorporation into the ships. 
38 A superlift is the use of a crane to move a very large section of the ship from the land into its final position on the 
ship. 
Congressional Research Service  
 
25 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
ship  deliveries  which  allows  more  schedule  overlap,  and  therefore  more  shop-level  and 
assembly-level production efficiencies than two single-ship buys. 
Procuring two ships to a single technical baseline reduces the requirement for engineering 
labor  hours  when  compared  to  single-ship  estimates.  The  ability  to  rollover  production 
support  engineering  and  planning  products  maximizes  savings  while  recognizing  the 
minimum amount of engineering labor necessary to address obsolescence and regulatory 
changes on CVN 81. The two-ship agreement with the shipbuilder achieves a 55 percent 
reduction in construction support engineering hours on CVN 81 and greater than 18 percent 
reduction in production support and planning hours compared to single ship procurements. 
The two-ship procurement strategy allows for serial production opportunities that promote 
tangible learning and reduced shop and machine set-up times. It allows for efficient use of 
production facilities, re-use of production jigs and fixtures, and level loading of key trades. 
The continuity of work allows for reductions in supervision, services and support costs. 
The result of these efficiencies is a production man-hours step down that is equivalent to 
an 82 percent learning curve since CVN 79. 
Key  to  achieving  these  production  efficiencies  is  Integrated  Digital  Shipbuilding  (iDS). 
The Navy’s Research, Development, Test, and Evaluation (RDT&E) and the shipbuilder’s 
investment  in  iDS,  totaling  $631  million,  will  reduce  the  amount  of  production  effort 
required to build FORD Class carriers. The two-ship buy will accelerate the benefits of this 
approach. The ability to immediately use the capability on CVN 81 would lead to a further 
reduction in touch labor and services in affected value streams. The two-ship agreement 
with  the  shipbuilder  represents  a  production man-hours reduction  of  over  seven  percent 
based  on  iDS  efficiencies.  Contractual  authority  for  two  ships  allows  the  shipbuilder  to 
maximize  economic  order  quantity  material  procurement.  This  allows  more  efficient 
ordering and scheduling of material deliveries and will promote efficiencies through earlier 
ordering,  single  negotiations,  vendor  quotes,  and  cross  program  purchase  orders.  These 
efficiencies  are  expected  to  reduce  material  costs  by  about  six  percent  more  when 
compared  to  single-ship  estimates.  Improved  material  management  and  flexibility  will 
prevent costly production delays. Furthermore, this provides stability within the nuclear 
industrial base, de-risking the COLUMBIA and VIRGINIA Class programs. The two-ship 
buy would provide economic stability to approximately 130,000 workers across 46 States 
within the industrial base. 
Change  order  requirements  are  likewise  reduced  as  Government  Furnished  Equipment 
(GFE) providers will employ planning and procurement strategies based on the common 
technical baseline that minimize configuration changes that must be incorporated on the 
follow ship. Change order budget allocations have been reduced over 25 percent based on 
two-ship strategies. 
In addition to the discrete savings achieved with the shipbuilder, the two-ship procurement 
authority provides our partner GFE providers a similar opportunity to negotiate economic 
order quantity savings and achieve cross program savings when compared to single-ship 
estimates.39 
An April 16, 2018, press report stated the following: 
If  the  Navy  decides  to  buy  aircraft  carriers  CVN-80  and  81  together,  Newport  News 
Shipbuilding will be able to maintain a steady workload that supports between 23,000 and 
25,000 workers at the Virginia yard for the next decade or so, the shipyard president told 
reporters last week. 
 
39 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 6-7. 
Congressional Research Service  
 
26 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Part of the appeal of buying the two carriers together is that the Navy would also buy them 
a bit closer together: the ships would be centered about three-and-a-half or four years apart, 
instead of the five-year centers for recent carrier acquisition, Newport News Shipbuilding 
President Jennifer Boykin told reporters. 
Boykin said the closer ship construction centers would allow her to avoid a “labor valley” 
where the workforce levels would dip down after one ship and then have to come back up, 
which is disruptive for employees and costly for the company. 
If this two-carrier buy goes through, the company would avoid the labor valley altogether 
and ensure stability in its workforce, Boykin said in a company media briefing at the Navy 
League’s  Sea  Air  Space  2018  symposium.  That  workforce  stability  contributes  to  an 
expected $1.6 billion in savings on the two-carrier buy from Newport News Shipbuilding’s 
portion of the work alone, not including government-furnished equipment.... 
Boykin said four main things contribute to the expected $1.6 billion in savings from the 
two-carrier buy. First, “if you don’t have the workforce valley, there’s a labor efficiency 
that represents savings.” 
Second,  “if  you  buy  two  at  once,  my  engineering  team  doesn’t  have  to  produce  two 
technical baselines, two sets of technical products; they only have to produce one, and the 
applicability is to both, so there’s savings there. When we come through the planning, the 
build plan of how we plan to build the ship, the planning organization only has to put out 
one plan and the applicability is to both, so there’s savings there.” 
The third savings  is a value of money over time issue, she said, and fourth is economic 
order quantity savings throughout the entire supply chain.40 
 
 
Author Information 
 
Ronald O'Rourke 
   
Specialist in Naval Affairs 
    
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan 
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and 
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other 
than public understanding of information that has been provided by CRS to Members of Congress in 
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not 
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in 
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or 
material from a third party, you may need to obtain the permission of the copyright holder if you wish to 
copy or otherwise use copyrighted material. 
 
 
40 Megan Eckstein, “Newport News Would Save $1.6 Billion, Maintain Stable Workforce of 25,000 Under 2 Proposed 
Carrier Buy,” USNI News, April 16, 2018. See also Rich Abott, “HII Sees Two Carrier Buy Saving $1.6 Billion Before 
GFE,” Defense Daily, April 11, 2018: 10-11. 
Congressional Research Service  
RS20643 · VERSION 286 · UPDATED 
27