INSIGHTi
Corps Water Infrastructure Financing
Program (CWIFP)
Updated June 20, 2024
The Water Infrastructure Finance and Innovation Act of 2014 (WIFIA 2014, Title V, Subtitle C, of P.L.
113-121; 33 U.S.C. §§3901-3915, as amended) authorized the U.S. Army Corps of Engineers (USACE)
to provide credit assistance—direct loans or loan guarantees—to eligible entities for water resource
projects. USACE’s program is called the Corps Water Infrastructure Financing Program (CWIFP). WIFIA
2014 also authorized an analogous Environmental Protection Agency (EPA) program for water projects
outside of USACE mission areas.
CWIFP Authority, Implementation, and Funding
WIFIA 2014 authorized USACE credit assistance for projects with the following purposes:
• reduction of riverine or coastal storm flood damage,
• restoration of aquatic ecosystems,
• improvement of the inland and intracoastal waterways navigation system,
• improvement of navigation at a U.S. harbor, or
• a combination of purposes supported by USACE and EPA WIFIA authorities (e.g.,
drinking water, wastewater, and/or stormwater system improvements).
USACE describes some CWIFP benefits for borrowers as interest rates near U.S. Treasury rates, possible
matching of repayment schedules with anticipated cash flows, and repayment periods up to 35 years after
construction completion. In FY2021, Congress created a USACE Water Infrastructure Finance and
Innovation Program (WIFIP) account and first funded the CWIFP to provide credit assistance. Of the
$110.8 million in enacted funding to date, Congress has indicated (see Table 1) that
• $81.0 million supports credit assistance for dam safety projects,
• $2.2 million supports credit assistance for dam safety and levee projects, and
• $27.6 million supports program administration.
Eligible dams are those identified as nonfederally owned in the National Inventory of Dams.
Congressional Research Service
https://crsreports.congress.gov
IN12021
CRS INSIGHT
Prepared for Members and
Committees of Congress
link to page 2 link to page 2 link to page 2 Congressional Research Service
2
Table 1. Water Infrastructure Finance and Innovation Program (WIFIP) Account
(dollars in millions, nominal)
Public Law Funding
WIFIP Account and
Support for
Program
Project Type Statutory Limitations for
FY2025 Request
Credit Assistance Administration
Credit Assistance
P.L. 116-260
$12.0
$2.2
Nonfederal dam safety projectsa
P.L. 117-58
$64.0
$11.0
Nonfederal dam safety projects
P.L. 117-103
$5.0
$2.2
Nonfederal dam safety projectsa
P.L. 117-328
$0
$7.2
—
P.L. 118-42
$2.2
$5.0
Nonfederal dam safety and levee projectsa
FY2025 Budget request
$2.0
$5.0
Nonfederal dam safety projects
Source: CRS.
a. Congressional direction specifies credit in accordance with 85 Federal Register 39189.
In May 2023, USACE published a final CWIFP implementation rule that reflected enacted appropriations
through FY2023, which limited lending to nonfederal dam safety projects (88 Federal Register 32661). In
September 2023, USACE solicited preliminary applications from prospective CWIFP borrowers for
nonfederal dam safety projects (88 Federal Register 64892). After evaluating the preliminary
applications, which were due in December 2023, USACE plans to invite selected prospective borrowers
to complete their applications. Applicants are responsible for application fees and fees for processing
CWIFP credit assistance.
According to the 2023 rule, CWIFP-eligible entities include state, local, and tribal government entities
and various private entities (e.g., corporations, partnerships, and trusts) that are publicly sponsored (33
U.S.C. §3907(a)(4)); federal entities are ineligible. An eligible project needs to cost more than $20 million
and be creditworthy, technically sound, economically justified, and environmentally acceptable. USACE’s
rule identifies dam removal as eligible. The final rule added selection criteria to the statutory criteria (e.g.,
the extent that a project serves and spurs economic opportunity for economically disadvantaged
communities and their populations). For a project, the maximum CWIFP credit assistance is 49% of
eligible project costs, or up to 80% for projects serving economically disadvantaged communities.
Loan Volume
The volume of loans and loan guarantees that CWIFP can provide is determined primarily by the
appropriated amount for credit assistance and the subsidy rate for each loan. Under the Federal Credit
Reform Act of 1990 (P.L. 101-508), appropriations for federal credit programs primarily cover long-term
credit subsidy costs (2 U.S.C. §661a). Subsidy costs reflect potential losses to the government from loan
defaults. Projects with lower credit risk would consume less credit subsidy than higher credit risk
projects. The subsidy cost typically is presented as a percentage (i.e., a subsidy rate). USACE calculates
subsidy costs on a project-by-project basis at the time of loan obligation. USACE may support up to $7.5
billion in loans with the appropriations available through FY2023. Actual total CWIFP loan volume may
differ, given each project’s subsidy rate and other factors affecting loan amounts.
Issues for Congress
Policy issues shaping CWIFP include how future congressional direction may determine eligible project
types and at what level Congress appropriates for CWIFP credit assistance. With FY2024 appropriations,
link to page 2 Congressional Research Service
3
Congress expanded the scope of eligible projects to include nonfederal levee projects. P.L. 118-42
specified that to be eligible for CWIFP’s FY2024 credit assistance, a levee must be certified as not being
federally owned by the Secretary of the Army. Implementation of this provision may clarify whether new
nonfederal work on levees originally constructed by USACE and operated by a nonfederal entity is
CWIFP eligible. The House Appropriations Committee, in explanatory text accompanying P.L. 116-260,
had encouraged the Secretary of the Army to issue “guidance to clarify, as Congress intended … that the
financial assistance program authorized in WIFIA applies to all non-Federal projects and any authorized
project that is non-federally owned, operated, and maintained.†A related question is the CWIFP eligibility
of nonfederal costs of authorized USACE construction projects. Many congressionally authorized
USACE projects have purposes that are CWIFP eligible pursuant to WIFIA 2014. Congress has required
that nonfederal sponsors share in the cost of many USACE projects and assume responsibility for the
projects and their costs after construction. A June 30, 2020, Federal Register notice―“Water
Infrastructure Finance and Innovation Act Program (WIFIA) Criteria Pursuant to the Further Consolidated
Appropriations Act, 2020†(85 Federal Register 39189)―identified congressionally authorized USACE
(and Bureau of Reclamation) projects as federal assets and as ineligible for WIFIA assistance. As noted in
Table 1, Congress has often referenced the 2020 Federal Register notice when funding USACE’s WIFIP
account. The discussion in USACE’s 2023 final rule references the applicability of the 2020 Federal
Register notice, thereby maintaining that congressionally authorized USACE projects are federal assets.
Thus, the 2023 final rule indicates that nonfederal costs associated with congressionally authorized
USACE projects are ineligible for CWIFP assistance.
Author Information
Nicole T. Carter
Specialist in Natural Resources Policy
Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff
to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of
Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of
information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role.
CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United
States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However,
as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the
permission of the copyright holder if you wish to copy or otherwise use copyrighted material.
IN12021 · VERSION 5 · UPDATED