

Coast Guard Polar Security Cutter
(Polar Icebreaker) Program: Background and
Issues for Congress
Updated May 22, 2024
Congressional Research Service
https://crsreports.congress.gov
RL34391
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Summary
Required number of polar icebreakers. A 2023 Coast Guard fleet mix analysis concluded that
the service will require a total of eight to nine polar icebreakers, including four to five heavy
polar icebreakers and four to five medium polar icebreakers, to perform its polar (i.e., Arctic and
Antarctic) missions in coming years.
Current operational polar icebreaker fleet. The operational U.S. polar icebreaking fleet
currently consists of one heavy polar icebreaker, Polar Star, and one medium polar icebreaker,
Healy. A second Coast Guard heavy polar icebreaker, Polar Sea. Polar Sea, suffered an engine
casualty in June 2010 and has been nonoperational since then. Polar Star and Polar Sea entered
service in 1976 and 1977, respectively, and are now well beyond their originally intended 30-year
service lives. The Coast Guard plans to extend Polar Star’s service life until the delivery of at
least the second Polar Security Cutter (PSC; see next paragraph).
Polar Security Cutter (PSC). The Coast Guard Polar Security Cutter (PSC) program aims to
acquire four or five new PSCs (i.e., heavy polar icebreakers), to be followed at some later point
by the acquisition of new Arctic Security Cutters (ASCs) (i.e., medium polar icebreakers). The
Coast Guard in 2021 estimated PSC procurement costs in then-year dollars as $1,297 million (i.e.,
about $1.3 billion) for the first ship, $921 million for the second ship, and $1,017 million (i.e.,
about $1.0 billion) for the third ship, for a combined estimated cost of $3,235 million (i.e., about
$3.2 billion). The PSC program has received a total of about $1,731.8 million in procurement
funding through FY2024. The Coast Guard’s proposed FY2025 budget requests no procurement
funding for the PSC program. One oversight issue concerns the accuracy of the PSC’s estimated
procurement cost, given the PSC’s size and internal complexity as well as cost growth in other
Navy and Coast Guard shipbuilding programs. If substantial cost growth occurs in the PSC
program, it could raise a question regarding whether to grant some form of contract relief to the
PSC shipbuilder. Another oversight issue concerns the delivery date for the first PSC: the Coast
Guard originally aimed to have the first PSC delivered in 2024, but the ship’s estimated delivery
date has been delayed repeatedly and may now occur no earlier than 2029.
Commercially available polar icebreaker (CAPI). The Coast Guard’s proposed FY2024 budget
requested, and the FY2024 Department of Homeland Security (DHS) Appropriations Act
(Division C of H.R. 2882/P.L. 118-47 of March 23, 2024) provided, $125.0 million in
procurement funding for the purchase of an existing commercially available polar icebreaker
(CAPI) that would be modified to become a Coast Guard medium polar icebreaker. The ship the
Coast Guard intends to purchase and modify is Aiviq, a U.S.-registered ship that was originally
built to serve as an Arctic oil-exploration support ship, and which has an icebreaking capability
sufficient for the ship to serve following modification as a Coast Guard medium polar icebreaker.
The Coast Guard’s proposed FY2025 budget requests no procurement funding for the CAPI
program. The Coast Guard’s FY2025 Unfunded Priorities List (UPL) includes an item for $25.0
million in procurement funding for the ship.
Great Lakes icebreaker (GLIB). The Coast Guard’s FY2024 budget initiated a program for
procuring a new Great Lakes icebreaker (GLIB) that would have capabilities similar to those of
Mackinaw, the Coast Guard’s existing heavy GLIB. The FY2024 DHS Appropriations Act
(Division C of H.R. 2882/P.L. 118-47 of March 23, 2024) provided $20.0 million in procurement
funding for the GLIB program. The Coast Guard’s proposed FY2025 budget requests no
procurement funding for the program. The Coast Guard’s FY2025 UPL includes an item for $25.0
million in procurement funding for the program.
Congressional Research Service
link to page 5 link to page 5 link to page 5 link to page 5 link to page 6 link to page 6 link to page 7 link to page 8 link to page 9 link to page 9 link to page 17 link to page 18 link to page 18 link to page 18 link to page 20 link to page 22 link to page 22 link to page 22 link to page 23 link to page 25 link to page 26 link to page 27 link to page 28 link to page 28 link to page 29 link to page 31 link to page 31 link to page 33 link to page 36 link to page 37 link to page 37 link to page 38 link to page 39 link to page 40 link to page 40 link to page 40 link to page 41 link to page 41 link to page 41 link to page 42 link to page 43 link to page 11 link to page 12 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Contents
Introduction ..................................................................................................................................... 1
Background ..................................................................................................................................... 1
Missions of Coast Guard Polar Icebreakers .............................................................................. 1
Statutory Duties and Missions ............................................................................................ 1
Multiple Missions (Not Just Icebreaking) ........................................................................... 2
Polar (Not Just Arctic) Operations ...................................................................................... 2
Current Coast Guard Polar Icebreakers ..................................................................................... 3
Required Numbers of Coast Guard Polar Icebreakers .............................................................. 4
Coast Guard Polar Icebreaker Programs ................................................................................... 5
Polar Security Cutters (PSCs) ............................................................................................. 5
Commercially Available Polar Icebreaker (CAPI) ............................................................ 13
Service Life Extension for Polar Star .............................................................................. 14
Coast Guard Great Lakes Icebreakers ..................................................................................... 14
Current Fleet ..................................................................................................................... 14
New Great Lakes Icebreaker (GLIB) ................................................................................ 16
Issues for Congress ........................................................................................................................ 18
PSC Program: Cost Growth .................................................................................................... 18
Increase in Estimated Procurement Costs Since April 2019 Contract Award ................... 18
Factors that Could Further Increase Estimated Procurement Costs .................................. 19
CBO May 2024 Cost Estimate .......................................................................................... 21
PSC Program: Schedule Delay ................................................................................................ 22
PSC Program: Technical Risk ................................................................................................. 23
Parent Design and PSC Design ......................................................................................... 24
May 2024 GAO Testimony ............................................................................................... 24
July 2023 GAO Testimony ............................................................................................... 25
July 2023 GAO Report ..................................................................................................... 27
April 2023 GAO Report.................................................................................................... 27
PSC Program: Contract with Options vs. Block Buy Contract ............................................... 29
PSCs and ASCs: Using a Common Design ............................................................................. 32
PSCs and ASCs: Using a Foreign Shipyard ............................................................................ 33
Overview ........................................................................................................................... 33
Laws Relating to Building Ships in Foreign Shipyards .................................................... 34
CAPI: Total Cost to Purchase and Modify .............................................................................. 35
Legislative Activity for FY2024 and FY2025 ............................................................................... 36
Summary of Appropriation Action on FY2024 Funding Request ........................................... 36
Summary of Appropriation Action on FY2025 Funding Request ........................................... 36
FY2024 DHS Appropriations Act (H.R. 4367/S. 2625/Division C of H.R. 2882/P.L.
118-47) ................................................................................................................................. 37
House ................................................................................................................................ 37
Senate ................................................................................................................................ 38
Enacted .............................................................................................................................. 39
Figures
Figure 1. Rendering of Halter Marine Design for PSC ................................................................... 7
Figure 2. Model of Halter Marine Design for PSC ......................................................................... 8
Congressional Research Service
link to page 12 link to page 13 link to page 13 link to page 15 link to page 19 link to page 44 link to page 45 link to page 46 link to page 48 link to page 49 link to page 49 link to page 51 link to page 51 link to page 10 link to page 17 link to page 40 link to page 40 link to page 41 link to page 41 link to page 50 link to page 53 link to page 44 link to page 52 link to page 73 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Figure 3. Rendering of Halter Marine Design for PSC ................................................................... 8
Figure 4. Rendering of Halter Marine Design for PSC ................................................................... 9
Figure 5. Rendering of Halter Marine Design for PSC ................................................................... 9
Figure 6. Rendering of SDC Concept Design for Polarstern II ..................................................... 11
Figure 7. Great Lakes Icebreaker Mackinaw ................................................................................. 15
Figure A-1. Polar Star and Polar Sea ........................................................................................... 40
Figure A-2. Polar Sea .................................................................................................................... 41
Figure A-3. Healy .......................................................................................................................... 42
Figure A-4. Nathaniel B. Palmer ................................................................................................... 44
Figure A-5. Laurence M. Gould .................................................................................................... 45
Figure A-6. Sikuliaq ...................................................................................................................... 45
Figure A-7. Commercial Ship Aiviq .............................................................................................. 47
Figure A-8. Commercial Ship Aiviq .............................................................................................. 47
Tables
Table 1. Estimated PSC Procurement Costs as of 2021 .................................................................. 6
Table 2. Procurement Funding for PSC Program Through FY2024 ............................................. 13
Table 3. Summary of Congressional Appropriations Action on FY2024 Procurement
Funding Request ......................................................................................................................... 36
Table 4. Summary of Congressional Appropriations Action on FY2025 Procurement
Funding Request ......................................................................................................................... 37
Table A-1. Coast Guard and NSF Polar Ships ............................................................................... 46
Table B-1. Major Polar Icebreakers as of April 4, 2022 ................................................................ 49
Appendixes
Appendix A. Current U.S. Polar Icebreakers and Polar Research Ships ....................................... 40
Appendix B. Required Numbers of U.S. Polar Icebreakers .......................................................... 48
Contacts
Author Information ........................................................................................................................ 69
Congressional Research Service
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Introduction
This report provides background information and issues for Congress three Coast Guard
icebreaker acquisition programs:
• the Polar Security Cutter (PSC) program—a program for acquiring four to
five new heavy polar icebreakers to be known as PSCs;
• the commercially available polar icebreaker (CAPI) program—a program to
purchase an existing CAPI that would be modified to become a Coast Guard
polar icebreaker; and
• the Great Lakes icebreaker (GLIB) program—a program to procure a new
heavy GLIB to augment the Coast Guard’s current GLIB fleet.
The Coast Guard’s proposed FY2025 budget requests no procurement funding for the PSC,
CAPI, and GLIB programs. The Coast Guard’s FY2025 Unfunded Priorities list (UPL) includes
an item for $25.0 million in procurement funding for the CAPI program and another item for
$25.0 million in procurement funding for the GLIB program.
The issue for Congress is whether to approve, reject, or modify the Administration’s procurement
funding requests and acquisition strategies for the PSC, CAPI, and GLIB programs.
On May 7, 2024, CRS provided testimony on Coast Guard ship acquisition programs, particularly
the PSC program, to the House Homeland Security Committee subcommittee on Transportation
and Maritime Security.1 Separate CRS reports cover acquisition of general-purpose cutters for the
Coast Guard2 and waterways commerce cutters for the Coast Guard.3 Another CRS report
provides an overview of various issues relating to the Arctic.4
Background
Missions of Coast Guard Polar Icebreakers
Statutory Duties and Missions
The permanent statute that sets forth the Coast Guard’s primary duties—14 U.S.C. §102—states
that among other things, the Coast Guard shall (emphasis added) “develop, establish, maintain,
and operate, with due regard to the requirements of national defense, aids to maritime navigation,
icebreaking facilities, and rescue facilities for the promotion of safety on, under, and over the
high seas and waters subject to the jurisdiction of the United States,” and “pursuant to
international agreements, develop, establish, maintain, and operate icebreaking facilities on,
under, and over waters other than the high seas and waters subject to the jurisdiction of the United
States.”5
1 CRS Testimony TE10100, Building the Fleet: Assessing the Department of Homeland Security’s Role in the United
States Coast Guard’s Acquisitions Process, by Ronald O'Rourke.
2 CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke.
3 CRS In Focus IF11672, Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for
Congress, by Ronald O'Rourke.
4 CRS Report R41153, Changes in the Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke.
5 14 U.S.C. §102(4) and §102(5), respectively. This statute was previously 14 U.S.C. §2; it was renumbered as 14
(continued...)
Congressional Research Service
1
link to page 6 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
In addition, Section 888(a) of the Homeland Security Act of 2002 (H.R. 5005/P.L. 107-296 of
November 25, 2002)—the law that established the Department of Homeland Security (DHS) and
transferred the Coast Guard from the Department of Transportation to DHS—sets forth 11
specific missions for the Coast Guard (often referred to as the Coast Guard’s 11 statutory
missions), including the mission of “ice operations.”6
Multiple Missions (Not Just Icebreaking)
The Coast Guard’s polar icebreakers do not simply break ice—they are multimission cutters7 that
conduct a variety of other operations that are conducted in lower-latitude waters by the Coast
Guard’s general-purpose cutters. U.S. polar ice operations conducted in large part by the Coast
Guard’s polar icebreakers support 9 of the Coast Guard’s 11 statutory missions.8 The roles of U.S.
polar icebreakers can be summarized as follows:
• conducting and supporting scientific research in the Arctic and Antarctic;
• defending U.S. sovereignty in the Arctic by helping to maintain a U.S. presence
in U.S. territorial waters in the region;
• defending other U.S. interests in polar regions, including economic interests in
waters that are within the U.S. exclusive economic zone (EEZ) north of Alaska;
• monitoring sea traffic in the Arctic, including ships bound for the United States;
and
• conducting other typical Coast Guard missions (such as search and rescue, law
enforcement, and protection of marine resources) in Arctic waters, including U.S.
territorial waters north of Alaska.9
Polar (Not Just Arctic) Operations
The Coast Guard’s large icebreakers are called polar icebreakers rather than Arctic icebreakers
because they perform missions in both the Arctic and Antarctic. Operations to support National
Science Foundation (NSF) research activities in both polar regions account for a significant
portion of U.S. polar icebreaker operations.
Supporting NSF research in the Antarctic focuses on performing an annual mission, called
Operation Deep Freeze (ODF), to break through Antarctic sea ice so as to reach and resupply
McMurdo Station, the large U.S. Antarctic research station located on the shore of McMurdo
Sound, near the Ross Ice Shelf. The Coast Guard stated in 2018 that Polar Star, the Coast
Guard’s only currently operational heavy polar icebreaker, “spends the [northern hemisphere]
U.S.C. §102 by Section 103 of the Frank LoBiondo Coast Guard Authorization Act of 2018 (S. 140/P.L. 115-282 of
December 4, 2018). (Title I of P.L. 115-282, consisting of Sections 101-124, specified a general reorganization of Title
14.)
6 The 11 missions set forth in Section 888(a) are marine safety; search and rescue; aids to navigation; living marine
resources (fisheries law enforcement); marine environmental protection; ice operations; ports, waterways and coastal
security; drug interdiction; migrant interdiction; defense readiness; other law enforcement.
7 Cutters are commissioned Coast Guard vessels greater than 65 feet in length.
8 For a list of the 11 missions, see footnote 6. The two statutory missions not supported by polar ice operations are
illegal drug interdiction and undocumented migrant interdiction. (Department of Homeland Security, Polar Icebreaking
Recapitalization Project Mission Need Statement, Version 1.0, approved by DHS June 28, 2013, p. 10.)
9 This passage, beginning with “The roles of ... ,” originated in an earlier iteration of this CRS report and was later
transferred by the Government Accountability Office (GAO) with minor changes to GAO, Coast Guard[:]Efforts to
Identify Arctic Requirements Are Ongoing, but More Communication About Agency Planning Efforts Would Be
Beneficial, GAO-10-870, September 2010, p. 53.
Congressional Research Service
2
link to page 44 link to page 45 link to page 44 link to page 46 link to page 44 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
winter [i.e., the southern hemisphere summer] breaking ice near Antarctica in order to refuel and
resupply McMurdo Station. When the mission is complete, the Polar Star returns to dry dock [in
Seattle] in order to complete critical maintenance and prepare it for the next ODF mission. Once
out of dry dock, it’s back to Antarctica, and the cycle repeats itself.”10 In terms of the maximum
thickness of the ice to be broken, the annual McMurdo resupply mission generally poses the
greatest icebreaking challenge for U.S. polar icebreakers, though Arctic ice can frequently pose
its own significant icebreaking challenges for U.S. polar icebreakers. The Coast Guard’s medium
polar icebreaker, Healy, spends most of its operational time in the Arctic supporting NSF research
activities and performing other operations.
Although polar ice is diminishing due to climate change, observers generally expect that this
development will not eliminate the need for U.S. polar icebreakers, and in some respects might
increase mission demands for them. Even with the diminishment of polar ice, there are still
significant ice-covered areas in the polar regions, and diminishment of polar ice could lead in
coming years to increased commercial ship, cruise ship, and naval surface ship operations, as well
as increased exploration for oil and other resources, in the Arctic—activities that could require
increased levels of support from polar icebreakers, particularly since waters described as “ice
free” can actually still have some amount of ice.11 A 2007 National Research Council report
stated that changing ice conditions in Antarctic waters had made the McMurdo resupply mission
more challenging since 2000.12 The Coast Guard’s Arctic strategic outlook document, released in
April 2019, states
In order to prosecute its missions in the Arctic, the Coast Guard must fully understand and
operate freely in this vast and unforgiving environment. Effective capability requires
sufficient heavy icebreaking vessels, reliable high-latitude communications, and
comprehensive Maritime Domain Awareness. In order to respond to crises in the Arctic,
our Nation must also muster adequate personnel, aviation, and logistics resources in the
region. The Coast Guard is the sole provider and operator of the U.S. polar capable fleet
but currently does not have the capability or capacity to assure access in the high latitudes.
Closing the gap requires persistent investment in capabilities and capacity for polar
operations, including the Polar Security Cutter.13
Current Coast Guard Polar Icebreakers
The operational U.S. polar icebreaking fleet currently consists of two ships—one heavy polar
icebreaker, Polar Star (Figure A-1 and Figure A-2 in Appendix A), and one medium polar
icebreaker, Healy (Figure A-3 in Appendix A). In addition to Polar Star, the Coast Guard has a
second heavy polar icebreaker, Polar Sea. Polar Sea, however, suffered an engine casualty in
June 2010 and has been nonoperational since then.
Polar Star and Polar Sea entered service in 1976 and 1977, respectively, and are now well
beyond their originally intended 30-year service lives. The Coast Guard in recent years has
invested millions of dollars to overhaul, repair, and extend the service life of Polar Star, but as a
result of its advancing age, the ship’s material condition has nevertheless become increasingly
10 NyxoLyno Cangemi, “Coast Guard Icebreaker Crew Completes Second Arctic Mission; U.S. Interests in Arctic
Domain Depends [sic] on Fleet Recapitalization,” DVIDS (Defense Visual Information Distribution System), October
19, 2018.
11 For more on changes in the Arctic due to diminishment of Arctic ice, see CRS Report R41153, Changes in the
Arctic: Background and Issues for Congress, coordinated by Ronald O'Rourke.
12 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington,
2007, pp. 6-7, 14, 63.
13 United States Coast Guard, Arctic Strategic Outlook, April 2019, p. 6.
Congressional Research Service
3
link to page 44 link to page 52 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
fragile, if not precarious. During its annual deployments to McMurdo Station in Antarctica,
shipboard equipment frequently breaks, and shipboard fires have occurred.14 Replacements for
many of the ship’s components are no longer commercially available. To help keep Polar Star
operational, the Coast Guard is using Polar Sea as a source of replacement parts.
In February 2023, the Coast Guard issued a request for information (RFI) from companies
interested in conducting a service life extension project (SLEP) for Healy that would begin in
December 2025.15 Responses to the RFI were due by March 16, 2023.16
For additional background information on current U.S. polar icebreakers and polar research ships,
see Appendix A.
Required Numbers of Coast Guard Polar Icebreakers
The Coast Guard testified in April, June, and November 2023 that a new Coast Guard fleet mix
analysis concluded that the service will require a total of eight to nine polar icebreakers, including
four to five heavy polar icebreakers and four to five medium polar icebreakers, to perform its
polar (i.e., Arctic and Antarctic) missions in coming years.17 Prior to this new fleet mix analysis,
the Coast Guard had stated that it would need at least six polar icebreakers, including three heavy
polar icebreakers.
At a March 14, 204, hearing before the Senate Armed Services Committee, Air Force General
Gregory M. Guillot, the Commander of the U.S. Northern Command (USNORTHCOM), when
asked to comment about numbers of U.S. icebreakers for supporting U.S. operations in the Arctic
in a context, stated that “we’re severely outnumbered,” and that “we do appreciate that the Coast
Guard is—is procuring more icebreakers. But even with those, we will be severely outnumbered.
And that does limit our freedom of maneuver in that region.”18
For additional background information on required numbers of U.S. polar icebreakers, see
Appendix B.
14 See, for example, Richard Read, “Meet the Neglected 43-Year-Old Stepchild of the U.S. Military-Industrial
Complex,” Los Angeles Times, August 2, 2019; Melody Schreiber, “The Only Working US Heavy Icebreaker Catches
Fire Returning from Antarctica,” Arctic Today, March 2, 2019; Calvin Biesecker, “Fire Breaks Out on Coast Guard’s
Aging, and Only, Heavy Icebreaker,” Defense Daily, March 1, 2019.
15 The project is envisaged as being accomplished through five annual work periods, each beginning in December of a
given year and ending in April of the following year, with the first period beginning in December 2025 and ending in
April 2026, and the fifth period beginning in December 2029 and ending in April 2030.
16 See “Healy Service Life Extension Project (SLEP),” accessed July 20, 2023, at https://sam.gov/opp/
63af5d5f7b9e492dbdc6b106210f5716/view.
17 Spoken testimony, as reflected in CQ hearing transcripts, of
•
Admiral Linda L. Fagan, Commandant of the Coast Guard, at an April 18, 2023, hearing on the Coast
Guard’s proposed FY2024 budget before the Coast Guard and Maritime Transportation subcommittee of the
House Transportation and Infrastructure Committee, for the total figure of eight to nine polar icebreakers;
•
Admiral Steven D. Poulin, Vice Commandant of the Coast Guard, at a June 21, 2023, hearing before the
same subcommittee on the on the Coast Guard’s emerging challenges and statutory needs, again for the total
figure of eight to nine polar icebreakers; and
•
Vice Admiral Peter Gautier, Coast Guard Deputy Commandant for Operations, at a November 29, 2023,
hearing before the House Homeland Security Committee on how U.S. Arctic strategy impacts homeland
security, for both the total figure of eight to nine polar icebreakers and how that total includes four to five
heavy polar icebreakers and four to five medium polar icebreakers.
18 CQ transcript of hearing. See also Ella Sherman, “The US Military Doesn’t Have the Icebreakers to Compete in the
Arctic and Is ‘Severely Outnumbered’ by Russia, Commander Warns,” Business Insider, March 14, 2024.
Congressional Research Service
4
link to page 10 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Coast Guard Polar Icebreaker Programs
Polar Security Cutters (PSCs)
Overview
The PSC program was initiated in the Coast Guard’s FY2013 budget submission, and envisages
the acquisition of four to five new PSCs (i.e., heavy polar icebreakers), to be followed at some
later point by the acquisition of new ASCs (i.e., medium polar icebreakers).
Program Name and Name of First Ship
The PSC program was previously known as the polar icebreaker (PIB) program. Changing the
program’s name to the PSC program is intended to call attention to the fact that the Coast Guard’s
polar icebreakers perform a variety of missions relating to national security, not just
icebreaking.19 Although it is now called the PSC program, observers as a matter of convenience
might refer to it as the polar icebreaker program.
On February 24, 2022, the Coast Guard announced that the first PSC will be named Polar
Sentinel, and that the Coast Guard has candidate names in mind for the second and third PSCs.20
Home Port
On June 17, 2019, the Coast Guard announced that it intends to homeport its PSCs at Seattle,
WA, where the Coast Guard’s current polar icebreakers are homeported.21
Coast Guard-Navy Integrated Program Office (IPO)
The PSC program is managed by a Coast Guard-Navy Integrated Program Office (IPO). A key
aim in establishing the IPO was to permit the Navy to share its ship-procurement best practices
with the Coast Guard so as to help the Coast Guard reduce the time and cost needed to design and
procure the PSCs.
Lead Ship Delivery Date
The Coast Guard originally aimed to have the first PSC delivered in 2024, but the ship’s
estimated delivery date has been delayed repeatedly, and as discussed in more detail later in this
report, may now occur no earlier than 2029.
Estimated Procurement Cost
As shown in Table 1, the Coast Guard in 2021 estimated PSC procurement costs in then-year
dollars as $1,297 million (i.e., about $1.3 billion) for the first ship, $921 million for the second
19 See, for example, Ben Werner and Sam LaGrone, “Coast Guard Renames New Icebreaker Program ‘Polar Security
Cutter,’” USNI News, September 27, 2018. See also Sydney J. Freedberg Jr., “With Funding In Peril, Coast Guard
Pushes Icebreaker as ‘Polar Security Cutter,’” Breaking Defense, October 29, 2018.
20 See, for example, Richard R. Burgess, “Commandant Names Future Polar Security Cutter ‘Polar Sentinel,’”
Seapower, February 24, 2022.
21 See, for example, Ben Werner, “Coast Guard Polar Security Cutter Will Be Homeported in Seattle,” USNI News,
June 17, 2019; Navy Times Staff, “Coast Guard Picks Homeport for New Icebreaker Fleet,” Navy Times, June 17,
2019.
Congressional Research Service
5
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
ship, and $1,017 million (i.e., about $1.0 billion) for the third ship, for a combined estimated cost
of $3,235 million (i.e., about $3.2 billion).22 The shipbuilder’s contract-award costs for the ships,
which relate to the shipbuilder’s portion of the total procurement cost of the ships, are discussed
in the next section.
Table 1. Estimated PSC Procurement Costs as of 2021
(In millions of then-year dollars)
Cost element
1st PSC
2nd PSC
3rd PSC
Total
Ship construction
899
612
605
2,116
Nonrecurring cost
155
0
0
155
Recurring cost
744
612
605
1,961
Other program costs, including GFE
322
232
333
887
Post-delivery costs
48
49
50
147
Costs for Navy-Type, Navy-Owned (NTNO) equipment
28
28
29
85
TOTAL
1,297
921
1,017
3,235
Source: U.S. Coast Guard email to CRS, March 26, 2024, which states that costs shown are from the PSC 2021
LCCE v3 (Life Cycle Cost Estimate, version 3). The Coast Guard stated in the email that the 2021 LCCE v3 is
the Coast Guard’s current model for estimated PSC procurement costs.
Notes: The nonrecurring cost of $155 mil ion for the 1st PSC includes $118 mil ion for detail design costs for
the class and $37 mil ion for initial spares and repair parts for the 1st PSC. GFE is government-furnished
equipment, meaning equipment that the government procures directly from supplier firms, and then provides to
the shipbuilder for incorporation into the ship.
Competition and Contract Award
On April 23, 2019, the Coast Guard-Navy Integrated Program Office for the PSC program
awarded a $745.9 million fixed-price, incentive-firm contract for the detail design and
construction (DD&C) of the first PSC to Halter Marine Inc. of Pascagoula, MS, a shipyard that
was owned by Singapore Technologies (ST) Engineering. Halter Marine was the leader of one of
three industry teams that competed for the DD&C contract; the other two bidders reportedly were
Bollinger Shipyards of Lockport, Louisiana, and a partnership between Philly Shipyard of
Philadelphia and Fincantieri/Marinette Marine, of Marinette, WI.23 The DD&C contract includes
options for building the second and third PSCs. If both of these options are exercised, the total
value of the contract would increase to $1,942.8 million (i.e., about $1.9 billion).24
The above figures of $745.9 million, $552.7 million, and $1,942.8 million cover only the
shipbuilder’s portion of the PSCs’ total procurement cost; they do not include the cost of
government-furnished equipment (or GFE, meaning equipment that the government purchases
22 A GAO report that was released on April 20, 2023, and that reports on the status of major DHS acquisition programs
as of September 30, 2022, states that as of June 2022, the combined estimated procurement cost of the three PSCs was
$2,789 million. (GAO, DHS Annual Assessment[:] Major Acquisition Programs Are Generally Meeting Goals, but
Cybersecurity Policy Needs Clarification, GAO-23-106701, April 2023, p. 50.)
23 “Mississippi Shipyard Gets $746M Contract for Icebreaker,” Associated Press, April 23, 2019.
24 See Naval Sea Systems Command, “Polar Security Cutter Contract Awarded to Recapitalize Nation’s Arctic
Capabilities,” April 23, 2019; Department of Defense, “Contracts for April 23, 2019” (Release No. CR-076-19); Sam
LaGrone, “VT Halter Marine to Build New Coast Guard Icebreaker,” USNI News, April 23, 2019; Maria Armental,
“U.S. Orders First Heavy Icebreaking Vessel in Decades, as Rivals Expand Arctic Presence,” Wall Street Journal,
April 23, 2019; “Mississippi Shipyard Gets $746M Contract for Icebreaker,” Associated Press, April 23, 2019.
Congressional Research Service
6
link to page 11 link to page 12 link to page 12 link to page 13 link to page 13 
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
and then provides to the shipbuilder for incorporation into the ship), post-delivery costs, costs for
Navy-specific equipment, or government program-management costs. On December 29, 2021,
the Coast Guard exercised a $552.7 million fixed price incentive option to its contract with Halter
Marine Inc. for the second PSC.25
In November 2022, ST Engineering sold Halter Marine to Louisiana-based Bollinger Shipyards.
The former Halter Marine is now called Bollinger Mississippi Shipbuilding.26 The shipyard’s
former name of Halter Marine occurs in the remainder of this report in connection with
developments prior to November 2022.
Ship Design
Figure 1, Figure 2, Figure 3, Figure 4, and Figure 5 show renderings and a photograph of
Halter Marine’s design for the PSC.
Figure 1. Rendering of Halter Marine Design for PSC
Source: Il ustration accompanying Sam LaGrone, “UPDATED: VT Halter Marine to Build New Coast Guard
Icebreaker,” USNI News, April 23, 2019, updated April 24, 2019. The caption to the il ustration states “An
artist’s rendering of VT Halter Marine’s winning bid for the U.S. Coast Guard Polar Security Cutter. VT Halter
Marine image used with permission.”
The PSC program is using the parent design approach, meaning that the design of the PSC is
based on an existing icebreaker design. A key aim in using the parent design approach is to reduce
cost, schedule, and technical risk in the PSC program.
25 U.S. Coast Guard, “Polar Security Cutter Integrated Program Office Exercises Option for Second Cutter,” U.S. Coast
Guard, December 30, 2021; Department of Defense, “Contracts for December 29, 2021.”
26 See, for example, Sam LaGrone, “Bollinger Closes $15M Acquisition of Halter Marine, New Name: ‘Bollinger
Mississippi Shipbuilding,’” USNI News, November 14, 2022; Cal Biesecker, “Bollinger Completes Acquisition of
Halter Marine,” Defense Daily, November 14, 2022; Justin Katz, “Why a Small Shipyard Merger Could Signal Bigger
Problems for the US Military,” Breaking Defense, November 14, 2022; Sam LaGrone, “Updated: Bollinger to Buy
Halter Marine Shipyard, Oversee Coast Guard Polar Security Cutter Program,” USNI News, November 6, 2022.
Congressional Research Service
7


Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Figure 2. Model of Halter Marine Design for PSC
(Photograph of model displayed at 2021 trade show)
Source: Cropped version of photograph accompanying Peter Ong, “USGC’s Polar Security Cutters to Receive
Mark 38 Mod 4 Guns,” Naval News, April 21, 2022. The article credits the photograph to Naval News at the Sea
Air Space exposition 2021.
Figure 3. Rendering of Halter Marine Design for PSC
Source: Il ustration posted by Robert A. Socha, Senior Vice President, Halter Marine, accessed May 6, 2019, at
https://www.linkedin.com/feed/update/urn:li:activity:6526621529113976832.
An April 25, 2019, press report states that “the Coast Guard and Navy said VT Halter Marine’s
winning design for the new PSC “‘meets or exceeds all threshold requirements’ in the ship
specification” for the PSC program.27
27 Rich Abott, “Polar Icebreaker Winner Meets Threshold Requirements, Has Incentives for Early Delivery,” Defense
Daily, April 25, 2019.
Congressional Research Service
8


Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Figure 4. Rendering of Halter Marine Design for PSC
Source: Technology Associates, Inc. (cropped version of rendering posted at http://www.navalarchitects.us/
pictures.html, accessed June 10, 2020). A similar image was included in Halter Marine press release, “VT Halter
Marine Awarded the USCG Polar Security Cutter,” May 7, 2019, accessed May 8, 2019, at http://www.vthm.com/
public/files/20190507.pdf.
Figure 5. Rendering of Halter Marine Design for PSC
Source: Photograph accompanying Connie Lee, “New Coast Guard Icebreaker Remains on Tight Schedule,”
National Defense, May 21, 2020. The article credits the photograph to Technology Associated, Inc.
A May 7, 2019, press release from Halter Marine about its design for the PSC (which Halter
Marine updated on May 29 to provide a corrected figure for the design’s full load displacement)
stated the following:
Congressional Research Service
9
link to page 15 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
VT Halter Marine is teamed with Technology Associates, Inc. [TAI] as the ship designer
and, for over two years, has participated in the U.S. Coast Guard’s Heavy Polar Icebreaker
Industry Study. The ship design is an evolution from the mature “Polar Stern II” [German
icebreaker] currently in design and construction; the team has worked rigorously to
demonstrate its maturity and reliability. During the study, TAI incrementally adjusted the
design and conducted a series of five ship model tank tests to optimize the design. The
vessels are 460 feet in length with a beam of 88 feet overall, a full load displacement of
approximately 22,900 long tons at delivery. The propulsion will be diesel electric at over
45,200 horse power and readily capable of breaking ice between six to eight feet thick. The
vessel will accommodate 186 personnel comfortably for an extended endurance of 90 days.
In addition to TAI, VT Halter Marine has teamed with ABB/Trident Marine for its Azipod
propulsion system,28 Raytheon for command and control systems integration, Caterpillar
for the main engines, Jamestown Metal Marine for joiner package, and Bronswerk for the
HVAC system. The program is scheduled to bring an additional 900 skilled craftsman and
staff to the Mississippi-based shipyard.29
The German icebreaker design referred to in Halter Marine’s press release, Polar Stern II (also
spelled Polarstern II) (Figure 6),30 is to be built as the replacement for Polarstern, Germany’s
current polar research and supply icebreaker.31 A May 9, 2019, press report states that Polarstern
II was designed by Germany’s Ship Design & Consult (SDC), a firm based in Hamburg,
Germany.32 SDC states that its concept design for Polarstern II has a length of 133 meters (about
436.4 feet) long, a beam of 27 meters (about 88.6 feet), and a draft of 10.5 meters (about 34.4
feet), but does not provide the design’s displacement.33 A briefing on a preliminary version of the
ship’s design stated that the design at that point was somewhat larger, with a length of 145 meters
(about 476 feet), a beam of 27.3 meters (about 89.6 feet), a draft of about 11 meters (about 36.1
feet), and a displacement (including payload) of about 26,000 tons.34 These figures suggest that
28 ABB is ASEA Brown Boveri, a multinational corporation headquartered in Zurich, Switzerland, that is, among other
things, a leading maker of electric-drive propulsion systems for ships. (ASEA is an acronym for Allmänna Svenska
Elektriska Aktiebolaget [i.e., General Swedish Electrical Limited Company], which merged with Brown, Boveri & Cie
[BBC] in 1988 to create ABB.) Azipod is ABB’s term for its azimuthing (i.e., swiveling) podded propulsors.
29 Halter Marine press release, “VT Halter Marine Awarded the USCG Polar Security Cutter,” May 7, 2019, updated
May 29, accessed June 12, 2019, at http://vthm.com/wp-content/uploads/2019/05/Press-Release_USCG-
PSC_Singapore-Exchange-FINAL_updatedMay29.pdf. The original (May 7) version of the press release stated that the
design’s full load displacement at delivery would be approximately 33,000 tons.
30 Polarstern is the German word for Polar Star—coincidentally, the same name as the U.S. Coast Guard’s operational
heavy polar icebreaker.
31 On February 14, 2020, the Alfred Wegener Institute (AWI), Helmholtz Centre for Polar and Marine Research,
announced that “the [German] Federal Ministry of Education and Research (BMBF) today cancelled the Europe-wide
call for tenders for the procurement of a new polar research vessel, Polarstern II, for legal reasons.” (Alfred Wegener
Institute, Helmholtz Centre for Polar and Marine Research, “Call for Fender Procedure for the Construction of a
Successor to the Icebreaker Polarstern Has Been Cancelled,” February 14, 2020.) On June 3, 2022, however, AWI
stated that “now that the federal budget for 2022 was approved by the German Bundestag on 3 June 2022, the
construction procurement procedure for Polarstern II can begin. The AWI plans to promptly launch the Europe-wide
procurement procedure so that the competitive bidding can start promptly as the first step. The handover of the
completed ship is slated for 2027.” (Alfred Wegener Institute, Helmholtz Centre for Polar and Marine Research,
“Polarstern II: German Bundestag Greenlights the Construction of New Icebreaker,” June 3, 2022. See also Eurasia
Review, “Polarstern II: German Bundestag Green-Lights Construction Of New Icebreaker,” Eurasia Review, June 4,
2022; Michael Wenger, “Germany’s ‘Pola[r]stern II’ Becomes Reality,” Polar Journal, June 6, 2022.)
32 Calvin Biesecker, “Long-Lead Funding in FY ‘20 for Second Polar Security Cutter Would Help with Planning,
Shipbuilder Says,” Defense Daily, May 9, 2019.
33 SDC Ship Design & Consult GmbH, design SDC2187, 133m Research Vessel, accessed May 9, 2019, at
http://www.shipdesign.de/html/index.php?navi=3&navi2=80&navi3=115.
34 Briefing entitled “Shipboard Polar Research, 32 Years Polarstern and the Requirement for Polarstern II,” accessed
(continued...)
Congressional Research Service
10

Coast Guard Polar Security Cutter (Polar Icebreaker) Program
SDC’s somewhat smaller concept design for Polarstern II might have a displacement (including
payload) of something less than 26,000 tons, and perhaps closer to 23,000 tons. The May 9, 2019,
press report states that
VT Halter’s teammates on the PSC include ship designer Technology Associates, Inc.
(TAI), which has been involved in the design for over two years and has made “a lot of
modifications” in a number of areas to meet Coast Guard requirements, [Ronald
Baczkowski, president and CEO of VT Halter Marine] said. The team went through six
design spirals to refine the design and the major modifications include changes in the hull
form to enhance the ship’s icebreaking capabilities and keep the ice clear from the
propulsors and sensors, habitability improvements for comfort particularly in open water,
easier access to different areas of the ship, and maintenance and endurance capabilities….
Raytheon [RTN] is the integrator for C5I capabilities35 on the ship and the main engines
will be supplied by Caterpillar [CAT]. Switzerland-based ABB and Netherlands-based
Trident are supplying the Azipod propulsion system, Florida-based Jamestown Metal
Marine is supplying the joiner package, and Netherlands-based Bronswerk the heating,
ventilation and cooling system.36
Figure 6. Rendering of SDC Concept Design for Polarstern II
Source: Cropped version of SDC Ship Design & Consult GmbH, design SDC2187, 133m Research Vessel,
accessed May 9, 2019, at http://www.shipdesign.de/html/index.php?navi=3&navi2=80&navi3=115. The image is
enlarged at http://www.shipdesign.de/html/detail.php?id=396.
May 8, 2019, at http://www.ervo-group.eu/np4/np4/%7B$clientServletPath%7D/?newsId=43&fileName=
Pr_sentation_Markterkundung_09.09.14_fin.pdf. The briefing is undated but includes a statement on one of its slides
that refers in the past tense to an event that took place in January 2016.
35 C5I stands for command, control, communications, computers, collaboration, and intelligence.
36 Calvin Biesecker, “Long-Lead Funding in FY ‘20 for Second Polar Security Cutter Would Help with Planning,
Shipbuilder Says,” Defense Daily, May 9, 2019. Abbreviations for firm names in brackets as in original.
Congressional Research Service
11
link to page 50 link to page 11 link to page 12 link to page 17 link to page 17 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Halter Marine’s 22,900-ton design for the PSC is considerably larger than the Coast Guard’s
current polar icebreakers. As shown in tons in Table A-1, the Coast Guard’s largest polar
icebreaker, Healy, is 420 feet long and has a full load displacement of 16,000 tons. Halter
Marine’s 460-foot design for the PSC is 40 feet longer than Healy, and its 22,900-ton
displacement is about 43% greater than Healy’s.
The horsepower generated by the propulsion plant in Halter Marine’s design—more than 45,200,
according to the earlier-quoted May 7, 2019 press release from Halter Marine—is roughly one-
quarter less than the 60,000 shaft horsepower of the propulsion plant in the Coast Guard’s heavy
polar icebreaker, Polar Star. As shown in Figure 1 and Figure 3, however, Halter Marine’s
design includes a centerline shafted propeller flanked by two azimuthing (i.e., swiveling) podded
propulsors—an arrangement that, along with other modern icebreaker hull design features, is
expected to give Halter Marine’s design a capability for breaking ice comparable to that of Polar
Star. A May 8, 2019, press report states the following:
“We picked the most modern icebreaker that was on the market, soon to be production-
level design that roughly met the Coast Guard’s requirements, and we took it and modified
it,” Baczkowski said.
“It has a contoured shape. The shape of the hull does the icebreaking. Instead of being a
mass breaking ice, this actually slices the ice. The shape of the hull pushed the broken ice
aside, so it doesn’t interfere with your propulsion systems, with your instrumentation that’s
on the other side of the ship.”
The design of the cutter is optimized for seakeeping to support the long voyage from its
homeport in Washington State to as far away as the Antarctic, he said.
“It’s an optimum design between icebreaking and seakeeping.”
“With the propulsors, with one fixed and two steerable, we were able to optimize the
seakeeping capability so when you’re going on long transits from Washington to Antarctica
the crew is not beat to a pulp or heavily fatigued because of the stability characteristics in
open water.”37
Procurement Funding Through FY2024
As shown in Table 2, the PSC program has received a total of about $1,731.8 million in
procurement funding through FY2024. This total reflects a rescission of $150.0 million in
unobligated prior-year funding in the Coast Guard’s Procurement, Construction, and
Improvements (PC&I) account that was made by Section 543(10) of the FY2024 DHS
Appropriations Act (Division C of H.R. 2882/P.L. 118-47 of March 23, 2024). The Coast Guard
applied the rescission to the PSC program’s FY2021 PC&I account appropriation, reducing it
from the originally enacted figure of $555.0 million to the figure shown in Table 2 of $405.0
million.
FY2025 Procurement Funding Request
The Coast Guard’s proposed FY2025 budget requests no procurement funding for the PSC
program.
37 Sam LaGrone, “VT Halter Marine Details Coast Guard Icebreaker Bid,” USNI News, May 8, 2019.
Congressional Research Service
12
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Table 2. Procurement Funding for PSC Program Through FY2024
(In millions of dollars)
Appropriated
Requested by
Fiscal
Coast Guard
Coast Guard
year
funding
Navy funding
Total funding
for that year
FY13
7.609
7.609
8.0
FY14
2.0
2.0
2.0
FY15
0.0
0.0
6.0
FY16
36.0
36.0
4.0
FY17
25.0
150.0
175.0
147.6
FY18
19.0
150.0
169.0
19.0
FY19
675.0
675.0
750.0
FY20
135.0
135.0
35.0
FY21
405.0
405.0
405.0
FY22
80.0
80.0
170.0
FY23
47.2
47.2
167.2
FY24
0
0
170.0
Total
1,431.809
300.0
1,731.809
n/a
Source: U.S. Coast Guard and Navy budget data. Figures reflect post-enactment adjustments due to
reprogramming actions or recissions.
Notes: Coast Guard procurement funding shown in the table was provided through the PC&I account. (Prior to
FY2019, the PC&I account was called the Acquisition, Construction, and Improvements [AC&I] account.) Navy
procurement funding shown in the table was provided through the Shipbuilding and Conversion, Navy (SCN)
account (i.e., the Navy’s shipbuilding account). All procurement funding requested over the years for the PSC
program has been requested by the Coast Guard for the Coast Guard’s AC&I/PC&I account. The Navy
procurement funding provided in FY2017 and FY2018 was not requested by the administration and was added by
Congress in marking up the Navy’s proposed FY2017 and FY2018 shipbuilding budgets. The FY2016 figure of
$36.0 mil ion includes $30.0 mil ion that was added after enactment through a reprogramming action, as noted in
the Coast Guard’s FY2018 budget submission. Section 543(10) of the FY2024 DHS Appropriations Act (Division
C of H.R. 2882/P.L. 118-47 of March 23, 2024) rescinded $150.0 mil ion in unobligated prior-year funding for the
Coast Guard’s Procurement, Construction, and Improvements (PC&I) account. The Coast Guard applied the
rescission to the PSC program’s FY2021 PC&I account appropriation, reducing it from the originally enacted
figure of $555.0 mil ion to the figure shown in the table of $405.0 mil ion.
Commercially Available Polar Icebreaker (CAPI)
The Coast Guard intends to purchase an existing commercially available polar icebreaker (CAPI)
that would be modified to become a Coast Guard medium polar icebreaker, so as to help augment
the Coast Guard’s current polar icebreaking capacity until the new PSCs enter service, and to
continue augmenting the Coast Guard’s polar icebreaking capacity after the PSCs enter service.
Under the Coast Guard’s proposal, the ship would enter service 18 to 24 months after being
acquired. The total cost to purchase the ship and then modify it to meet Coast Guard mission
needs is uncertain.
Prior to 2021, the Coast Guard plans did not include the acquisition of such a ship. The Coast
Guard’s FY2022 UPL, dated June 29, 2021, however, included a $150.0 million item for the lease
or purchase of a commercially available vessel to provide polar icebreaking capability until the
Congressional Research Service
13
link to page 44 link to page 19 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
future delivery of PSCs.38 The following year, the Coast Guard as part of its proposed FY2023
budget requested $125.0 million in procurement funding for the purchase of an existing CAPI.
Congress, in acting on the Coast Guard’s proposed FY2023 budget, denied the request. The Coast
Guard once again requested the $125.0 million as part of its proposed FY2024 budget, and the
FY2024 Department of Homeland Security (DHS) Appropriations Act (Division C of H.R.
2882/P.L. 118-47 of March 23, 2024) approved the request. The Coast Guard’s proposed FY2025
budget requests no procurement funding for the CAPI program. The Coast Guard’s FY2025 UPL
includes an item for $25.0 million in procurement funding for the program.
On March 1, 2024, the Coast Guard announced that it intends to solicit, on a sole-source basis, for
a Firm-Fixed-Price contract to Offshore Service Vessels, LLC, for the purchase of the ship.39 The
ship to be purchased is Aiviq, a U.S.-registered ship that was originally built to serve as an Arctic
oil-exploration support ship, and which has an icebreaking capability sufficient for the ship to
serve following modification as a Coast Guard medium polar icebreaker. The ship is discussed
further in Appendix A.
Service Life Extension for Polar Star
The Coast Guard plans to extend the service life of Polar Star until the delivery of at least the
second PSC.40 The Coast Guard estimated the cost of Polar Star’s service life extension work at
$75 million, a sum that was funded at a rate of $15 million per year for five years, with the final
$15 million increment being provided in FY2023. The funding was included in the vessels
portion of the Coast Guard’s PC&I account, in a line item called “Polar Sustainment” that is
separate from the line items for the PSC and CAPI programs.
Coast Guard Great Lakes Icebreakers
Current Fleet
The Coast Guard’s current Great Lakes icebreaker (GLIB) fleet consists of nine cutters:
• one heavy icebreaker—Mackinaw (WLBB-30), a 240-foot ship displacing 3,500
tons (Figure 7);
• six 140-foot Bay-class icebreaking tugs displacing 662 tons each; and
38 U.S. Coast Guard, FY 2022 Unfunded Priorities List, Report to Congress, June 29, 2021, p. 3.
39 “Synopsis: USCG Intent to Sole Source Commercially Available Polar Icebreaker (Updated),” SAM.gov, accessed
March 14, 2024, at https://sam.gov/opp/a12ad39d150d4df0ab6e4773d1cf17d0/view. See also Cal Biesecker, “Coast
Guard Moves Closer to Acquiring Commercial Polar Icebreaker,” Defense Daily, March 4, 2024; Joseph Trevithick,
“Coast Guard Poised to Buy Badly Needed Private Icebreaker,” The War Zone, March 4, 2024; Malte Humpert, “U.S.
Coast Guard Looking to Acquire Commercial Icebreaker ‘Aiviq,’” gCaptain, March 5, 2024; Maritime Executive,
“U.S. Coast Guard Plans to Buy Edison Chouest's Icebreaker Aiviq,” Maritime Executive, March 5, 2024.
40 In February 2020, for example, the Coast Guard testified that
The Coast Guard also understands that we must maintain our existing heavy and medium
icebreaking capability while proceeding with recapitalization.... Maintenance of POLAR STAR
will be critical to sustaining this capability until the new PSCs are delivered. Robust planning
efforts for a service life extension project on POLAR STAR are already underway and initial work
for this project will begin in 2020, with phased industrial work occurring annually from 2021
through 2023. The end goal of this process will be to extend the vessel’s service life until delivery
of at least the second new PSC.
(Testimony of Admiral Charles W. Ray, Coast Guard Vice Commandant, on “Arctic Security
Issues,” before the House Homeland Security Subcommittee on Transportation & Maritime
Security, February 5, 2020, p. 9.)
Congressional Research Service
14

Coast Guard Polar Security Cutter (Polar Icebreaker) Program
• two 225-foot Juniper-class seagoing buoy tenders displacing about 2,000 tons
each that have a light icebreaking capability.41
Figure 7. Great Lakes Icebreaker Mackinaw
Source: U.S. Coast Guard, “USCGC Mackinaw,” accessed September 11, 2019, at
https://www.atlanticarea.uscg.mil/Our-Organization/District-9/Ninth-District-Staff/Prevention-Division/Cutters/
MACKINAW/.
Although Mackinaw is referred to as a heavy icebreaker, the word heavy in this instance is being
used in the context of Great Lakes icebreaking—Mackinaw is much larger and has more
icebreaking capability than the eight other Great Lakes icebreaking ships listed above.42
Mackinaw would not, however, qualify as a heavy polar icebreaker, as it is much smaller and has
much less icebreaking capability than a heavy polar icebreaker.43
41 Source: U.S. Coast Guard, “Ninth Coast Guard District Units,” accessed December 12, 2023, at
https://www.atlanticarea.uscg.mil/Atlantic-Area/Units/District-9/Ninth-District-Units/. A total of 10 cutters are
assigned to the Ninth District, which is responsible for the Great Lakes, the Saint Lawrence Seaway, and parts of the
surrounding states. The 10th cutter assigned to the Ninth District is a 100-foot inland buoy tender whose primary
missions do not include icebreaking.
42 At continuous speeds of 3 knots, Mackinaw can break ice up to 32 inches thick, the 140-foot icebreaking tugs can
break ice up to 22 inches thick, and the 225-foot seagoing buoy tenders can break ice up to 14 inches thick.
43 As discussed earlier in this report, the Coast Guard’s two heavy polar icebreakers—the operational Polar Star and
the nonoperational Polar Sea—are 399 feet long and displace about 13,200 tons each. Polar Star can break ice up to
six feet (72 inches) thick at a continuous speed of 3 knots. The Coast Guard states that Mackinaw is equivalent to the
Canadian Coast Guard ship Samuel Risley, a Great Lakes-homeported icebreaker and buoy tender that Canada
classifies as a light icebreaker in a comparison conducted across its entire icebreaking fleet, including its Arctic
icebreakers. (U.S. Coast Guard, Great Lakes Icebreaking Mission Analysis, Fiscal Year 2016 Report to Congress,
August 30, 2016, p. 5.)
Congressional Research Service
15
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
New Great Lakes Icebreaker (GLIB)
Overview
Since at least 2009, some Members of Congress have expressed interest in bolstering the Coast
Guard’s Great Lakes icebreaking fleet by procuring a second icebreaker with capabilities
generally similar to those of Mackinaw.44 Prior to October 2021, the Coast Guard generally stated
that it did not view the procurement of additional GLIBs as an urgent near-term acquisition need,
given the capabilities of the current Great Lakes icebreaking fleet, the relatively young age of
Mackinaw (which entered service in 2006), service life extension work being done on the ice-
breaking tugs that is designed to add 15 years to their service lives, and Canada’s own Great
Lakes icebreaking capabilities.45 In October 2021, then-Commandant of the Coast Guard Admiral
Karl Schultz expressed support for procuring an additional heavy GLIB as part of a budget
reconciliation bill.46
The Coast Guard’s FY2024 budget initiated a program for procuring a new GLIB that would have
capabilities similar to those of Mackinaw. The ship’s total acquisition cost, the Coast Guard
estimates, might be roughly $350 million, depending in part on the exact design that is developed
for the ship.47 (In January 2024, the Government Accountability Office [GAO] reported that the
Coast Guard’s 2022 Mission Need Statement for domestic icebreaking estimated the procurement
cost of a heavy domestic icebreaker at $216.3 million as of 2020.48)
44 See, for example, H.R. 1747 of the 111th Congress, the Great Lakes Icebreaker Replacement Act, which was
introduced on March 26, 2009, reported by the Committee on Transportation and Infrastructure on April 21, 2009
(H.Rept. 111-81), and agreed to by the House by voice vote on April 27, 2009. A similar bill, S. 1024, was introduced
in the Senate on May 12, 2009.
45 A 2016 Coast Guard report to Congress on the Great Lakes icebreaking mission, for example, stated the following:
The current mix of heavy and medium [Great Lakes] icebreakers is capable of managing priorities
and requests for icebreaking in Tier 1 and 2 waterways. When a severe ice season stresses Coast
Guard asset capabilities, the existing agreement and partnership with Canada fills the capability gap
and brings in extra heavy-icebreaking resources to manage the ice.... [T]he 2014 and 2015 ice
seasons were a 20-year anomaly, consuming almost twice as many cutter resource hours as in any
other year since 2005.
The Coast Guard cannot reliably predict the economic impact of maintaining a single heavy Great
Lakes icebreaker. Additionally, given the extreme conditions when ice coverage exceeds 90
percent, it is not clear that shipping delays would be significantly mitigated by an increase in
icebreaking capability. Delays can be associated with several factors such as slow transit speeds,
availability of pilots, and simultaneous and competing demand signals for icebreaking services
across the Great Lakes.
(U.S. Coast Guard, Great Lakes Icebreaking Mission Analysis, Fiscal Year 2016 Report to
Congress, August 30, 2016, p. 11. The report was required by S.Rept. 114-68 of June 18, 2015, the
Senate Appropriations Committee’s report on S. 1619, the Department of Homeland Security
Appropriations Bill, 2016 (see page 75).)
46 Admiral Schultz expressed support for procuring an additional heavy Great Lakes icebreaker as part of a budget
reconciliation bill as part of his testimony at an October 19, 2021, hearing on Coast Guard oversight before the Oceans,
Fisheries, Climate Change, and Manufacturing subcommittee of the Senate Commerce, Science, and Transportation
Committee.
47 Source: Coast Guard email to CRS, May 1, 2024.
48 GAO, Coast Guard: Improved Reporting on Domestic Icebreaking Performance Could Clarify Resource Needs and
Tradeoffs, GAO-24-106619, January 16, 2024, Table 1 on page 8. In a footnote to the table, GAO states that “the actual
costs [for items shown in the table] are likely to be higher than reported because the estimates do not include other
costs, such as shore infrastructure costs at port locations that the Coast Guard has not yet determined.”
Congressional Research Service
16
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
March 1, 2024, Hearing
On March 1, 2024, the Oceans, Fisheries, Climate Change, and Manufacturing subcommittee of
the Senate Commerce, Science, and Transportation Committee held a field hearing in Green Bay,
WI, on the importance of Great Lakes icebreaking to the regional economy.49 At this hearing,
Admiral Linda Fagan, Commandant of the Coast Guard, testified:
The Coast Guard recently completed a Fleet Mix Analysis which recommended a future
fleet of in-kind capacity to replace [the Coast Guard’s] current [Great Lakes icebreaking]
fleet. The results showed a need for another heavy domestic icebreaker to meet future
service needs across the Great Lakes. The ability to achieve continued success in this
mission and reliably facilitate navigation within the MTS [marine transportation system]
year-round requires sustainment and modernization of the Coast Guard’s domestic
icebreaking fleet, and I am committed to developing the next system of icebreaking assets.
Consistent with Congressional direction, we are focused on acquiring a second heavy
domestic icebreaker, at least as capable as CGC [Coast Guard cutter] Mackinaw. We
established a Great Lakes Icebreaking Program Management Office to analyze
requirements for the next generation of domestic icebreaking capability and have
completed pre-acquisition activities, readying the Service to advance upon receipt of an
appropriation. The FY 2024 President’s Budget requests $55 million to fund initial
acquisition activities and prepare for the purchase of long lead time materials for a second
heavy domestic icebreaker. I look forward to continuing to work with Congress to support
this acquisition.50
The FY2024 DHS Appropriations Act (Division C of H.R. 2882/P.L. 118-47 of March 23, 2024)
provided $20.0 million in procurement funding for the GLIB program (i.e., $35 million less than
the requested amount of $55.0 million mentioned in the above-quoted testimony from Admiral
Fagan). The Coast Guard’s proposed FY2025 budget requests no procurement funding for the
GLIB program. The Coast Guard’s FY2025 UPL includes an item for $25.0 million in
procurement funding for the ship.
January 2024 GAO Report
A January 16, 2024, GAO report on U.S. domestic icebreaking performance stated
The Coast Guard conducts domestic icebreaking operations in three of its nine districts—
the Great Lakes, New England, and the Mid-Atlantic.
In the Great Lakes, 55 percent of the regional economy is dependent on key shipping
channels, according to the Coast Guard. In 2020, industries shipped 100 million tons of
iron ore, limestone, coal, and other commodities through the Great Lakes, according to
data from the Army Corps of Engineers Waterborne Commerce Statistics Center. Some
industry stakeholders who rely on these shipping channels have raised questions about
whether the Coast Guard has adequate icebreaking resources available to facilitate
commerce.
Section 11212 of the James M. Inhofe National Defense Authorization Act for Fiscal Year
2023 [H.R. 7776/P.L. 117-263 of December 23, 2022] includes a provision for GAO to
review Coast Guard icebreaking operations in the Great Lakes and examine proposed
performance standards for the Coast Guard’s Great Lakes icebreaking program. This report
49 For details on this hearing, see https://www.commerce.senate.gov/2024/3/importance-of-great-lakes-icebreaking-to-
the-regional-economy.
50 Testimony of Admiral Linda L. Fagan, Commandant, U.S. Coast Guard, on “The Importance of Great Lakes
Icebreaking to the Regional Economy” before the Senate Committee on Commerce, Science, and Transportation
Subcommittee on Oceans, Fisheries[,] Climate Change, and Manufacturing, March 1, 2024, p. 4.
Congressional Research Service
17
link to page 10 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
discusses the associations between ice coverage on the Great Lakes and effects on certain
economic indicators, the Coast Guard’s icebreaking resource needs, and the potential
effects of the proposed standards on the Coast Guard’s icebreaking efforts.
Key Takeaways
•
Great Lakes vessel-based commerce declines during the winter, primarily due to lock
closures and weather conditions. We found that the amount of ice coverage on the
Great Lakes was generally not associated with selected economic indicators we
examined, such as regional unemployment rates and unfilled orders for steel
production. Industries may mitigate the effects of delays caused by ice coverage, such
as stockpiling iron ore inventory to maintain steel production throughout the winter.
•
The Coast Guard identified heavy icebreaking capability gaps and its reliance on an
aging fleet as risks to its ability to conduct its domestic icebreaking mission. As a
result, the Coast Guard anticipates needing at least $3 billion in lifecycle costs to
replace and acquire new vessels for domestic icebreaking.
•
The proposed standards for the Coast Guard’s domestic icebreaking program will
largely not have an operational impact. The proposed standards may lead to
improvements in data collection and reporting, which could help the Coast Guard
better communicate its resource needs and tradeoffs. However, the data collection
efforts may increase operating costs and information sharing needs with industry,
according to the Coast Guard.
•
We recommend that the Coast Guard, using data it already collects, report more
complete information on its icebreaking performance to better articulate its resource
needs and tradeoffs.51
Issues for Congress
PSC Program: Cost Growth52
One oversight issue for Congress concerns cost growth in the PSC program.
Increase in Estimated Procurement Costs Since April 2019 Contract Award
Coast Guard and Navy estimates of PSC procurement costs have increased about 39%
since the April 2019 PSC program contract award:
• At a March 28, 2019, hearing on the Coast Guard’s proposed FY2020 budget,
then-Coast Guard Commandant Admiral Karl Schultz testified that as of that
date, the cost of the first PSC was estimated at $925 million to $940 million, and
that the cost of the second and third PSCs would be in the range of $700 million
each,53 producing an estimated three-ship total of about $2,325 million to $2,340
million (i.e., about $2.3 billion).
• As shown in Table 1, the most recent estimate provided by the Coast Guard to
CRS is for the first PSC to cost $1,297 million (i.e., about $1.3 billion), the
second PSC to cost $921 million, and the third PSC to cost $1,017 million (i.e.,
51 GAO, Coast Guard: Improved Reporting on Domestic Icebreaking Performance Could Clarify Resource Needs and
Tradeoffs, GAO-24-106619, January 16, 2024, pp. 1-2.
52 This section is adapted from CRS Testimony TE10100, Building the Fleet: Assessing the Department of Homeland
Security’s Role in the United States Coast Guard’s Acquisitions Process, by Ronald O'Rourke
53 Source: CQ transcript of the hearing.
Congressional Research Service
18
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
about $1.0 billion), producing an estimated three ship total $3,235 million (i.e.,
about $3.2 billion),54 a total that is about 39% higher than the total from the
March 28, 2019, testimony.
Factors that Could Further Increase Estimated Procurement Costs
Even with the above 39% increase, PSC procurement costs still appear to still be significantly
underestimated. At least five potential factors could increase estimated PSC procurement costs
from the March 2019 figures to figures that are significantly above the current estimate:
• The actual PSC design is larger than the government’s indicative design. The
design chosen for the PSC is about 35% larger in terms of light-ship
displacement than the indicative design (i.e., the government’s in-house notional
design) that informed earlier Navy and Coast Guard cost estimating for the
program. Adjusting for this larger design might incur an approximate 35%
increase in estimated PSC procurement costs over the costs estimated at the time
of the April 2019 PSC contract award.
• The Navy has frequently underestimated lead ship costs. As detailed by the
Congressional Budget Office (CBO)55 and the Government Accountability Office
(GAO),56 the costs of lead ships in Navy shipbuilding programs have exceeded
the Navy’s estimates. Cost growth on Navy lead ships, CBO analysis shows, has
ranged from a few percent to about 150%, with the weighted average figure for
the 19 ship classes examined by CBO being 25%, and the unweighted average
being 40%.57 Many of these 19 cases involve lead ships whose light-ship
displacements were not underestimated, meaning that the cost growth resulted
from factors other than the one described in the previous bullet point.
• Recent inflation in shipbuilding. Shipbuilding, like other sectors of defense
procurement and the U.S. economy in general, has experienced significant
inflation since the start of the COVID-19 pandemic due to supply chain
disruptions and other impacts. The Navy states that “the residual effects of
inflationary pressures of the past few years, workforce challenges, plus increased
labor and supply costs across the defense enterprise, all drove costs associated
with our shipbuilding account up roughly 20% over the last couple of years.”58
This inflation has increased the estimated procurement costs of multiple Navy
shipbuilding programs. Within Coast Guard shipbuilding, the estimated unit
procurement cost of an FRC has increased from $60 million in the Coast Guard’s
enacted FY2021 appropriation to $100 million in the Coast Guard’s FY2024
unfunded requirements list and FY2025 budget submission, although not all of
the increase is necessarily due to the recent inflation in shipbuilding.
• Potential need for additional increases in worker wages and benefits.
Shipyards and associated supplier firms face challenges in recruiting and
54 Source: U.S. Coast Guard email to CRS, March 26, 2024, which stated that costs shown are from the PSC 2021
LCCE v3 (Life Cycle Cost Estimate, version 3). The Coast Guard stated in the email that the 2021 LCCE v3 is the
Coast Guard’s current model for estimated PSC procurement costs.
55 See CBO, An Analysis of the Navy’s Fiscal Year 2024 Shipbuilding Plan, October 2023, p. 34 (Figure 10).
56 See Government Accountability Office, Navy Shipbuilding[:] Past Performance Provides Valuable Lessons for
Future Investments, GAO-18-238SP, June 2018, p. 8.
57 See CBO, An Analysis of the Navy’s Fiscal Year 2024 Shipbuilding Plan, October 2023, p. 34 (Figure 10).
58 Department of the Navy, Highlights of the Department of the Navy FY 2025 Budget, 2024, page 1-12.
Congressional Research Service
19
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
retaining new workers, in part because wages and benefits in service and retail
jobs have grown more in recent years than have wages and benefits at
shipbuilders and supplier firms.59 As a result, workers are now more likely to
choose service and retail jobs, where the work, while paying less than
shipbuilding work, is more likely to be done in air-conditioned indoor settings,
involve less heavy lifting or risk of serious injury, and take place in locations
offering easier daily commutes.60 Reestablishing a larger differential in wages
and benefits between shipbuilding jobs and service and retail jobs could require
substantially increasing total wages and benefits for shipbuilding workers. Such a
change could, in turn, substantially increase procurement costs for ships such as
the PSC, since shipyard labor can account for roughly 40% of a military ship’s
total procurement cost. Increases in worker wages and benefits could also result
from shipyards along the Gulf Coast competing against one another for available
shipbuilding workers.61
• Labor hours and absorption of fixed overhead costs. Construction delays due
to lower-than-anticipated shipyard worker productivity, supply chain issues, or
other causes could increase the cost of the PSC because of the ship requiring a
larger-than-anticipated number of labor hours to build (if worker productivity is
an issue), and because the ship would absorb a portion of the shipyard’s monthly
fixed overhead costs for an increased number of months (an effect somewhat like
the meter in a taxi continuing to run even when the taxi is stuck in traffic).
A simple (not compounded) sum of the potential percentage cost increases described in the first
three bullet points above (using the 25% and 40% figures from the second bullet) comes to a
potential percentage cost increase, if all three factors were to come fully into play, of 80% to 95%
above the March 2019 figures.
Increasing the March 2019 figures by 80% would result in an estimated cost of $1,665 million to
$1,692 million (i.e., about $1.7 billion) for the lead ship and $1,260 million (i.e., about $1.3
billion) each for the second and third ships, producing an estimated three-ship total of $4,185
59 See, for example, Paul McLeary and Lee Hudson, “Navy Shipyards Compete with Fast Food, and Are Losing,”
Politico Pro, April 9, 2024.
60 Ibid.
61 A January 22, 2024, press report states:
Rear Adm. Chad Jacoby, the assistant commandant of the Coast Guard for acquisition, said this
month workforce challenges—specifically, needing more highly trained welders and design
engineers—are contributing to delays on the Polar Security Cutter program at Bollinger
Mississippi, formerly VT Halter Marine.
“If you look across all of our construction programs, every shipyard says they’re going to hire
1,000 or 2,000 more people prior to executing the contracts that we have in place. They all happen
to be on the Gulf Coast, so if you add up all those numbers, it’s probably physically impossible for
every one of those individual shipyards to hire 2,000 more people” to support on-time ship
deliveries, Jacoby said on a Jan. 11 panel at the Surface Navy Association annual conference.
He told Defense News after the panel he is specifically concerned about Bollinger Mississippi in
Pascagoula and its Polar Security Cutter; Eastern Shipbuilding Group in Panama City, Florida,
which is building the first four Offshore Patrol Cutters; Austal USA in Mobile, Alabama, which
will build the next 11 OPCs; and Birdon America, a Denver-based company that will build the
Waterways Commerce Cutters with a number of Louisiana- and Alabama-based companies.
“It is one workforce across many states,” the admiral said of the Gulf Coast region. “As each
shipyard says they’re going to hire people, they’re definitely competing against each other.”
(Megan Eckstein, “Coast Guard Ship Programs Facing Delays amid National Worker Shortage,”
Defense News, January 22, 2024.)
Congressional Research Service
20
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
million to $4,212 million (i.e., about $4.2 billion). This total is about 30% higher than the
currently estimated total of $3,235 million.
Increasing the March 2019 figures by 95% would result in an estimated cost of $1,804 million to
$1,833 million (i.e., about $1.8 billion) for the lead ship and $1,365 million (i.e., about $1.4
billion) each for the second and third ships, producing an estimated three-ship total of $4,534
million to $4,563 million (i.e., about $4.5 billion to $4.6 billion). This total is about 40% higher
than the currently estimated total of $3,235 million.
The cost figures in the two previous paragraphs do not include any increases cost resulting from
the factors outlined in the fourth and fifth bullet points above.
Percentage increases in estimated ship procurement costs comparable to the potential 80%-95%
increase discussed above have recently occurred in certain Navy shipbuilding programs. The
estimated procurement cost of the lead ship in the Navy’s TAGOS-25 ocean surveillance ship
program increased about 82% between the Navy’s FY2023 and FY2024 budget submissions;62
the estimated procurement cost of the lead ship in the Navy’s medium landing ship (LSM)
program increased 43% between the Navy’s FY2024 and FY2025 budget submissions;63 and the
estimated procurement cost of the lead ship in the Navy’s light replenishment oiler (TAOL)
program increased 202% between the Navy’s FY2024 and FY2025 budget submissions. An April
2024 CBO report on the procurement costs of LSMs estimates that LSMs will cost roughly 127%
to 187% more than the Navy estimates.64
A procurement cost for the first PSC that is closer to $2 billion than to $1 billion would be
comparable to the procurement cost of a Navy LPD-17 Flight II class amphibious ship, which is
about $2.0 billion. The LPD-17 Flight II design a little larger than the PSC design and has more
expensive combat system equipment than the PSC.65
The Coast Guard could respond to potential PSC program cost growth by granting contract relief
to the PSC shipbuilder, Bollinger Mississippi Shipbuilding, through a request for equitable
adjustment (REA) or pursuant to P.L. 85-804 (as done for the builder of the first four OPCs,
Eastern Shipbuilding Group).66
CBO May 2024 Cost Estimate
At a May 7, 2024, hearing on Coast Guard ship acquisition programs, particularly the PSC
program, before the House Homeland Security Committee subcommittee on Transportation and
Maritime Security, the Congressional Budget Office (CBO) estimated that, in constant FY2024
62 For more on the TAGOS-25 program, see CRS In Focus IF11838, Navy TAGOS-25 Ocean Surveillance Shipbuilding
Program: Background and Issues for Congress, by Ronald O'Rourke.
63 For more on the LSM program, see CRS Report R46374, Navy Medium Landing Ship (LSM) (Previously Light
Amphibious Warship [LAW]) Program: Background and Issues for Congress, by Ronald O'Rourke.
64 Congressional Budget Office, Acquisition Costs of the Navy’s Medium Landing Ship, April 2024, p. 1. For further
discussion, see CRS Report R46374, Navy Medium Landing Ship (LSM) (Previously Light Amphibious Warship
[LAW]) Program: Background and Issues for Congress, by Ronald O'Rourke.
65 Another consideration in comparing cost estimates for the first PSC and the LPD-17 Flight II design is that the first
PSC is at the top of the learning curve for building the PSC design, while the cost of the LPD-17 Flight II design
reflects learning curve benefits from producing earlier LPD-17 Flight I class ships. For more on the LPD-17 Flight II
class program, see CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship Programs: Background and
Issues for Congress, by Ronald O'Rourke.
66 For more on P.L. 85-804 and the contract relief granted in the OPC program to Eastern Shipbuilding Group under
that law, see CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald
O'Rourke.
Congressional Research Service
21
link to page 24 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
dollars, the procurement cost of the first PSC at $1.9 billion, and the procurement costs of
subsequent PSCs at about $1.6 billion each. Given these estimates, CBO testified that “the
procurement cost of three PSCs would be about $5.1 billion. That amount is 60 percent greater
than the Coast Guard’s most recent publicly released estimate for the procurement cost of three
heavy icebreakers, which was provided to CBO by the Coast Guard in March 2024.”67
PSC Program: Schedule Delay68
Another oversight issue for Congress concerns schedule delay in the PSC program. The Coast
Guard originally aimed to have the first PSC delivered in 2024, but the ship’s estimated delivery
date has been delayed repeatedly and is now expected to occur no earlier than FY2029.
A principal cause of the delay has been the time needed to achieve design maturity (i.e., to
complete the detail design of the ship). The parent design strategy used for the PSC program (i.e.,
the strategy of creating the PSC design by modifying the design of an existing polar-capable ship)
was intended by the Coast Guard and Navy to reduce the PSC’s design time. Five years after
contract award, the expected reduction in design time does not appear have been realized. The
time needed to mature the PSC design suggests that the parent design used for the PSC
program—the design for the new German polar icebreaker Polar Stern II—might now more
closely resemble a parent design in name only (PDINO).69 In this regard, the PSC program
appears somewhat similar to the Navy’s Constellation (FFG-62) class frigate program, which the
Navy initiated as a program that would use a parent design, but which observers might now
characterize as having moved over time toward a PDINO situation.70 Limited numbers of
available naval architects and design engineers within the United States also appear to have
contributed to delays in maturing the PSC design.71
A principal option for substantially accelerating the construction of polar icebreakers for the
Coast Guard would be to complete the maturation of the PSC design; begin building PSCs at the
program’s current shipbuilder, Bollinger Mississippi Shipbuilding; and at some later point
introduce a second shipbuilder to build additional PSCs in parallel to those being built by
Bollinger. As mentioned earlier, the Coast Guard has testified that its most recent fleet mix
67 Eric J. Labs, The Cost of the Coast Guard’s Polar Security Cutter, Congressional Budget Office, Testimony Before
the Subcommittee on Transportation and Maritime Security Committee on Homeland Security, U.S. House of
Representatives, April 30, 2024 (for hearing of May 7, 2024), p. 2 (PDF page 3 of 4).
68 Parts of this section are adapted from CRS Testimony TE10100, Building the Fleet: Assessing the Department of
Homeland Security’s Role in the United States Coast Guard’s Acquisitions Process, by Ronald O'Rourke.
69 The phrase parent design in name only (with the resulting acronym PDINO) is only one possible shorthand way of
referring to the situation. One possible way to pronounce the acronym PDINO would be pa-DEE-no.
70 For more on the FFG-62 program, see CRS Report R44972, Navy Constellation (FFG-62) Class Frigate Program:
Background and Issues for Congress, by Ronald O'Rourke. On the issue of the FFG-62’s parent design strategy, the
report states:
An April 2, 2024, press report states: “At one point the Constellation design shared about 85
percent commonality with the original [Italian-French] FREMM [Fregata Europea Multi-Missione
parent] design, but the alterations [incorporated into the FFG-62 design] have brought that
commonality down to under 15 percent, a person familiar with the changes told USNI News.” If the
FFG-62 design shares less than 15% commonality with the FREMM design, then some observers
might characterize the FFG-62 program as having moved over time toward what might be termed a
parent design in name only (PDINO) design approach.
71 The January 22, 2024, press report quoted in footnote 61 mentions states (emphasis added): “Rear Adm. Chad
Jacoby, the assistant commandant of the Coast Guard for acquisition, said this month workforce challenges—
specifically, needing more highly trained welders and design engineers—are contributing to delays on the Polar
Security Cutter program at Bollinger Mississippi, formerly VT Halter Marine.”
Congressional Research Service
22
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
analysis calls for a total of eight to nine polar-capable icebreakers, including four to five heavy
polar icebreakers (i.e., PSCs), and four to five medium polar icebreakers. Given these figures and
Bollinger’s current contract to build up to three PSCs, one possible approach might be to
introduce a second shipbuilder to build the fourth and fifth PSCs while Bollinger completes the
first three. Another possible approach would be to have Bollinger build all four or five PSCs
while accelerating the start date of the timeline for designing and building the medium polar
icebreakers. This second approach could accelerate the date for completing the larger total of
eight to nine heavy and medium polar icebreakers. These two alternatives are not the only
possible approaches.
A January 22, 2024, press report states
Rear Adm. Chad Jacoby, the assistant commandant of the Coast Guard for acquisition, said
this month workforce challenges—specifically, needing more highly trained welders and
design engineers—are contributing to delays on the Polar Security Cutter program at
Bollinger Mississippi, formerly VT Halter Marine.
“If you look across all of our construction programs, every shipyard says they’re going to
hire 1,000 or 2,000 more people prior to executing the contracts that we have in place. They
all happen to be on the Gulf Coast, so if you add up all those numbers, it’s probably
physically impossible for every one of those individual shipyards to hire 2,000 more
people” to support on-time ship deliveries, Jacoby said on a Jan. 11 panel at the Surface
Navy Association annual conference.
He told Defense News after the panel he is specifically concerned about Bollinger
Mississippi in Pascagoula and its Polar Security Cutter; Eastern Shipbuilding Group in
Panama City, Florida, which is building the first four Offshore Patrol Cutters [OPCs];
Austal USA in Mobile, Alabama, which will build the next 11 OPCs; and Birdon America,
a Denver-based company that will build the Waterways Commerce Cutters with a number
of Louisiana- and Alabama-based companies.
“It is one workforce across many states,” the admiral said of the Gulf Coast region. “As
each shipyard says they’re going to hire people, they’re definitely competing against each
other.”72
A March 20, 2024, press report states
The Coast Guard is currently working with the shipbuilder, Bollinger Shipyards, to
“rebaseline [the program],” which will result in a new program schedule that is expected
to be completed “later this year and will be critical to informing future budget requests,” a
service spokesperson wrote in an email….
… the reevaluation of the program means that the entire program schedule will be
revamped, and that schedule will not be made available until later this year, the service
said.73
See also the comments about the first ship’s delivery date from the GAO testimony and reports
discussed in the following section.
PSC Program: Technical Risk
Another potential oversight issue for Congress concerns technical risk in the PSC program .
72 Megan Eckstein, “Coast Guard Ship Programs Facing Delays amid National Worker Shortage,” Defense News,
January 22, 2024.
73 Allyson Park, “Coast Guard Reevaluating Polar Security Cutter Schedule,” National Defense, March 20, 2024.
Congressional Research Service
23
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Parent Design and PSC Design
One potential aspect of the issue of technical risk in the PSC program relates to the parent design
for the PSC design. Some observers have questioned the value of using parent designs in military
shipbuilding programs. A 2015 journal article, for example, states
The U.S. Navy has experimented with many approaches to design and build its ships. Using
an existing design as the “parent” design, also referred to as “modified-repeat” design, is
on its face an attractive option. Many acquisition executives, program managers and some
ship design engineers believe that a design based on a parent has fewer technical risks than
a new “clean sheet of paper” design and therefore the time and cost to design and build it
will be reduced. They assume early in the ship acquisition program that “the design is
mature” and because of that fewer problems will be encountered in completing the design
and savings will thus be accrued. Yet, a number of naval ships based on a parent design
have in fact experienced unanticipated cost and schedule growth during construction as
well as technical problems during their in-service life. The authors will examine some of
these ship designs which were based on an existing design and/or prototypes and highlight
the fallacies of such beliefs and assumptions.74
Potential oversight questions for Congress include the following:
• How fully developed was Polarstern II’s design at the time that it was adopted as
the parent design for developing the PSC design? How much of Polarstern II’s
detail design and construction plan was completed at that time?
• To what degree has Polarstern II’s design in practice served as the parent design
for the PSC design? In developing the PSC’s design, how many changes have
been made from Polarstern II’s design? What technical, schedule, and cost risks,
if any, might arise for the PSC program as a result of differences between the
PSC’s design and Polarstern II’s design?
May 2024 GAO Testimony
May 7, 2024, GAO testimony to the Transportation and Maritime Security subcommittee
of the House Homeland Security Committee regarding Coast Guard ship acquisition
stated:
The U.S. Coast Guard manages its major shipbuilding programs—generally those with cost
estimates of $1 billion or greater—using the Department of Homeland Security’s (DHS)
acquisition framework. GAO’s prior work found that the Coast Guard continues to face
challenges in its highest priority shipbuilding acquisition programs—the Offshore Patrol
Cutter and the Polar Security Cutter.
Design instability. The shipbuilders have yet to stabilize their designs, which has
contributed to schedule delays and cost growth for both programs. For example, the
Offshore Patrol Cutter program began ship construction without a matured critical
technology, which led to redesign of portions of the ship and contributed to delays of the
lead ship by almost 4 years. GAO recommended in June 2023 that the program mature this
same critical technology before moving forward through design on the next set of ships.
DHS did not concur. GAO closed this recommendation in April 2024 after the Coast Guard
74 Robert G. Keane, Jr. and Barry F. Tibbitts, “The Fallacy of Using a Parent Design: ‘The Design Is Mature,’”
Transactions (Society of Naval Architects and Marine Engineers [SNAME]), 2015, No. 1 (January): 91-104, with
additional discussion from the authors and other commentators on pages 105-122. The quoted passage appears at the
start of the article, on page 91, where it forms part of an abstract or summary for the article.
Congressional Research Service
24
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
approved a design review without maturing the critical technology. However, GAO stands
by the intent of the recommendation to minimize risk to the program.
Program oversight. Both programs lack key milestones in their acquisition program
baselines—a document that sets the program’s cost, schedule, and performance goals—to
ensure adequate program oversight and accountability. For example, the Coast Guard did
not include the delivery date of the last Polar Security Cutter in its acquisition program
baseline. If included as a key event, failure to meet this date would trigger a formal
assessment by DHS. In July 2023, GAO recommended that DHS and the Coast Guard
include this delivery date in the acquisition program baseline, and the department
concurred. Coast Guard officials told GAO they plan to include ship delivery dates in its
revised baseline….
In May 2024, GAO identified leading practices in ship design, such as using iterative
design to accelerate design maturity and employing robust in-house ship design capabilities
and tools. These practices build on previous leading practices that GAO identified in
product development and shipbuilding. Over the past decade, GAO has recommended
numerous actions to the Coast Guard and DHS reflecting those practices—such as attaining
design stability and developing solid business cases—to achieve successful shipbuilding
outcomes.75
July 2023 GAO Testimony
July 27, 2023, GAO testimony to the Coast Guard and Maritime Transportation subcommittee of
the House Transportation and Infrastructure Committee regarding the PSC program and the Coast
Guard’s OPC program76 states
The Coast Guard’s shipbuilding programs—specifically the OPC and PSC programs—
have struggled with achieving elements for a good business case. As a result of neither
maturing technologies nor achieving design stability when called for by leading practices,
both programs are well behind schedule. In addition, both programs’ cost estimates have
increased by billions of dollars for several reasons, including that their initial estimates
were either not comprehensive or not well-informed.
Technology maturity and design stability. The Coast Guard’s OPC and PSC programs
did not follow shipbuilding leading practices with regards to conducting, demonstrating,
and achieving technology readiness and design stability….
Years after we first identified these deficiencies with the OPC and PSC programs, the Coast
Guard still has not gained the requisite knowledge for its technologies and designs:…
• PSC: In September 2018, we found that the Coast Guard did not conduct a technology
readiness assessment of PSC’s key technologies, nor did it hold a preliminary design
review, prior to approving its program baselines. Coast Guard officials said that a
technology readiness assessment was not necessary because the technologies they plan to
employ had been proven on other ships. However, according to leading practices, such
technologies can still pose risks when applied to a different program or operational
environment. The program subsequently conducted a technology readiness assessment and
established revised baselines in May 2021 after holding its preliminary design review in
response to our recommendations.
75 Government Accountability Office, Coast Guard Acquisitions[:] Opportunities Exist to Improve Shipbuilding
Outcomes, Testimony Before the Subcommittee on Transportation and Maritime Security, Committee on Homeland
Security, House of Representatives, Statement of Shelby S. Oakley, Director, Contracting and National Security
Acquisitions, GAO-24-107488, May 7, 2024, highlights page.
76 For more on the OPC program, see CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues
for Congress, by Ronald O'Rourke.
Congressional Research Service
25
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
As of March 2023, the PSC program reported that the functional design was considerably
below the desired levels that officials expect to inform a decision to proceed with
construction. As of April 2023, program officials said they anticipate holding the
production readiness reviews to evaluate design maturity by March 2024. However, since
September 2021, with about 49 percent functional design completed, our analysis indicated
that the shipyard is completing, on average, approximately three percent of functional
design every 6 months. This means that it would take the shipyard approximately 8 years
to complete 100 percent of functional design. Therefore, to reach the program’s goal of
completing functional design completed prior to March 2024, the shipyard would need to
increase its design completion rate significantly. Coast Guard officials said that design
completion is further along than the metrics show because the metrics do not factor in
progress made on design components that are not complete.
We also found that the program is experiencing challenges with the design. According to
program officials, the design challenges are related to (1) U.S. industry’s general lack of
experience designing and building icebreakers, (2) the complexity of PSC’s design, and (3)
significant changes from the original design, among other things. Given that there are still
portions of the design that are immature, we recommended that the Coast Guard complete
functional design prior to approving construction for the lead ship, in line with our
recommendation to OPC and Coast Guard policy, as a whole. The Coast Guard concurred
with the recommendations, and we will monitor its progress in addressing them.
Cost. Both the OPC and PSC have incurred cost growth above their initial estimates, in
part because the programs initially underestimated costs….
• PSC: From 2018 to 2021, the program’s total life-cycle cost estimate increased by about
35 percent, from $9.8 billion to $13.3 billion. Most of the cost increase was driven by
increased operations and maintenance costs, resulting from the increased ship size and use
of additional historical data to reevaluate projected annual maintenance costs in the later
estimate. The program’s additional analysis of historical maintenance costs in its January
2021 cost estimate addressed, in part, a recommendation we made in 2018 to update the
cost estimate in accordance with leading practices in cost estimating. Specifically, in
September 2018, we found that the PSC’s life-cycle cost estimate that informed the
program’s $9.8 billion cost baseline substantially met GAO’s leading practices for being
comprehensive, well-documented, and accurate, but only partially met leading practices
for being credible.15 The cost estimate did not quantify the range of possible costs over
the entire life of the program. As a result, the cost estimate was not fully reliable and may
have underestimated the cost. Consequently, the Coast Guard may have provided decision
makers with incomplete data to make a decision on total funding needed for the program.
Schedule. The Coast Guard relied on optimistic schedules for both the PSC and OPC
programs, and both have experienced schedule delays of 2 years or more…. The two
programs’ schedule challenges have been exacerbated by a lack of reliable schedule data
from the contractors responsible for building these ships….
• PSC: In September 2018, we found that the PSC’s planned delivery dates were not
informed by a realistic assessment of shipbuilding activities. Instead, the schedule was
driven by the potential gap in icebreaking capabilities once the Coast Guard’s only
operating heavy polar icebreaker—the Polar Star—reaches the end of its service life. We
recommended that the program develop a schedule in accordance with leading practices
for project schedules to set realistic schedule goals for all three PSCs before the lead ship
contract option was awarded. However, we closed the recommendation as not implemented
because the program proceeded with the award in April 2019 without developing a realistic
schedule. In July 2023, we found the program had yet to establish a realistic schedule. The
program’s current schedule estimates that delivery of the lead ship will occur in 2027,
Congressional Research Service
26
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
which is 3 years later than its previous estimate, but this could further slip after the
contractor reassesses and revises its schedule.77
July 2023 GAO Report
A GAO report on the PSC program that was released on July 27, 2023, similarly states
The Polar Security Cutter’s (PSC) design is not yet mature, which has led to an extended
design phase and contributed to a 3-year schedule delay in the shipyard, with construction
of the first cutter now planned for March 2024. Coast Guard officials attribute the extended
design phase to various challenges. For example, icebreaking hulls require thick steel—up
to twice as thick as a non-icebreaker—and a dense framing structure that has been
challenging to plan for the PSC. Additionally, Coast Guard officials stated that U.S.-based
shipbuilders have limited expertise designing and building heavy polar icebreakers….
Starting construction with an immature design is contrary to leading practices. In another
ongoing Coast Guard program, GAO found that construction started before the design was
mature, resulting in costly rework and schedule delays.
The PSC program likely has unreliable schedule and cost estimates. The primary reasons
are:
• The acquisition program baseline includes a delivery date for the first PSC but not for the
third PSC. At a minimum, without a delivery date for the third cutter, the Department of
Homeland Security (DHS) may have fewer opportunities for oversight if the program
experiences schedule delays in the years before the program is expected to be declared
fully operational.
• Key shipyard business systems that track labor hours, costs, and schedule performance
were determined not to be acceptable for use, which affects the reliability of data. The
Coast Guard and shipyard are taking steps to address the data limitations and GAO will
continue to monitor progress.
The Coast Guard intends for its sole remaining, almost 50-year-old heavy polar icebreaker,
the Polar Star, to be available until at least the second PSC is operational. The Coast Guard
has efforts underway to maintain and extend the life of this cutter. However, the Polar
Star’s deteriorating systems present challenges, with top issues related to propulsion and
electrical systems. The Coast Guard’s assessments of the hull found it in good structural
condition.78
April 2023 GAO Report
A GAO report that was released on April 20, 2023, and which reports on the status of major DHS
acquisition programs as of September 30, 2022, states the following about the PSC program:
Key Findings
• Schedule. The program no longer considers a May 2025 delivery date for the lead ship
realistic. However, the program does not have enough information from the shipbuilder to
determine a new delivery date or whether schedule goals will likely be breached.
77 GAO, Coast Guard Recapitalization[:] Actions Needed to Better Manage Acquisition Programs and Address
Affordability Concerns, Statement of Marie A. Mak, Director, Contracting and National Security Acquisitions,
Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on Transportation and
Infrastructure, House of Representatives, July 27, 2023, GAO 23-106948, pp. 6-12.
78 GAO, Coast Guard Acquisitions[:] Polar Security Cutter Needs to Stabilize Design Before Starting Construction
and Improve Schedule Oversight, GAO 23-105949, July 2023, highlights page.
Congressional Research Service
27
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
• Design and construction. Design immaturity and the shipbuilder’s inexperience working
with the specialized steel needed for hull construction remain the program’s top risks,
according to program officials. To help train the shipbuilder’s workforce, the program is
planning for an early production phase prior to completion of the design, contrary to GAO
leading practices. The critical design review, scheduled for December 2022, will likely
need to be postponed given the status of design progress.
• Management. Oversight of the program is hampered. The shipbuilder’s deficient
business systems are not producing reliable accounting, schedule, and cost data. The Coast
Guard is working with the shipbuilder to address these challenges....
Cost and Schedule Status
In 2021, DHS approved PSC’s revised acquisition program baseline (APB), which
reflected a delayed schedule and higher life-cycle costs than the previously approved 2018
APB. However, as of August 2022, Coast Guard officials stated that they do not have
reliable schedule information from the shipbuilder, Halter Marine, Inc., to determine
whether it is likely to breach the schedule goals. For example, the contract delivery date
for the lead ship is May 2025, which is 1 year later than initially planned. However,
officials stated that May 2025 is no longer realistic because of challenges such as COVID-
19 effects and the shipbuilder’s inexperience with large government acquisitions. The
program does not have enough information to determine and assess a new delivery date
until Halter Marine, Inc., develops a new schedule, anticipated by March 2023. The
program requested an adjustment to its schedule goals due to the effects of COVID-19 and
is awaiting DHS approval.
According to Coast Guard officials, the program’s top schedule risks are PSC’s design
immaturity, Halter Marine, Inc.’s inexperience with shaping the specialized steel needed
for the hulls, and Halter Marine, Inc.’s contractor labor challenges. Coast Guard officials
stated they are mitigating some of these risks by conducting studies on the specialized steel
and planning for an early production phase. This phase will allow the shipbuilder to start
constructing up to eight (out of 85) selected modules of the ship deemed to be low-risk
prior to completing the ship’s design. While this approach is intended to train the
shipbuilder’s workforce in working with the steel, starting construction prior to completing
design is contrary to shipbuilding leading practices identified by GAO. If design changes
are discovered after the modules are already constructed, the program may face costly
rework and schedule delays.
Coast Guard officials stated that the program’s main tool in mitigating cost risks is the
contract type for design and construction of the cutters—fixed-price incentive (firm-target)
with economic price adjustment. This type of contract provides the shipbuilder with an
incentive to control costs.
Performance and Testing
Design maturity continues to be a top risk identified by the program. Coast Guard officials
stated that, as of August 2022, Halter Marine, Inc., had completed about 41 percent of the
overall design. The program had planned to conduct a critical design review by December
2022 to further evaluate design maturity. However, Coast Guard officials stated that given
the design progress, they will likely postpone the review to anywhere from May to
December 2023. Coast Guard officials stated that they do not plan to authorize Halter
Marine, Inc., to enter into the early production phase until after an initial critical design
review and designs for the selected modules are mature.
Coast Guard officials stated that the program conducted a cyber resilience early operational
assessment in May 2022 and deemed the results as sensitive. Coast Guard officials
established two working groups to address cybersecurity issues, and cyber risks are
managed as part of the program’s risk management team.
Congressional Research Service
28
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Program Management
The Coast Guard established an integrated program office and ship design team with the
Navy. The Coast Guard also established a project residence office at the shipbuilder’s
facility in Pascagoula, Mississippi, to provide oversight of shipbuilding efforts. However,
the shipbuilder’s deficient business systems are hindering the Coast Guard’s oversight of
the program. In June 2022, an independent audit found that Halter Marine, Inc.’s
accounting system had significant deficiencies that affected the reliability of billing and
pricing information produced. Further, in July 2022, an independent compliance review
found that Halter Marine, Inc.’s earned value management system had significant
deficiencies that hampers the program’s ability to monitor cost and schedule progress and
develop a reliable schedule. Coast Guard officials stated that they are working with Halter
Marine, Inc., to address these deficiencies.
In September 2018, GAO made six recommendations to DHS, the Coast Guard, and the
U.S. Navy to address risks identified with the PSC program. As of September 2022, two
of the six recommendations remain open. For additional information, see [GAO report]
GAO-18-600.79
Program Office Comments
We provided a draft of this assessment to the program office for review and comment. The
program office provided technical comments, which we incorporated where appropriate.
According to the program office, the PSC is the first heavy polar icebreaker built in the
U.S. in over 40 years and will be one of the most complex vessels ever built by the Coast
Guard. Program officials stated that they have worked closely with the shipbuilder to
mature the design of the ship and mitigate production risk. Officials added that ongoing
challenges with supply chain disruptions and COVID-19 have affected this effort.80
PSC Program: Contract with Options vs. Block Buy Contract
Another potential issue for Congress is whether to use a contract with options or a block buy
contract to acquire at least some of the PSCs. The detail design and construction (DD&C)
contract that the Coast Guard awarded to Halter Marine (now Bollinger Mississippi Shipbuilding)
is a contract with options. Coast Guard and Navy officials, however, have expressed openness to
the idea of using a block buy contract to acquire at least some of the ships (particularly the second
and third PSCs), and requested information on the possibility of using block buy contracting as
part of the request for proposals (RFP) for the PSC program that the Coast Guard released on
March 2, 2018. Section 311 of the Frank LoBiondo Coast Guard Authorization Act of 2018 (S.
140/P.L. 115-282 of December 4, 2018) provides permanent authority for the Coast Guard to use
block buy contracting with economic order quantity (EOQ) purchases (i.e., up-front batch
purchases) of components in its major acquisition programs. The authority is now codified at 14
U.S.C. §1137.
Although a contract with options covers multiple years, it operates more like a form of annual
contracting, and it does not generate the kinds of savings that are possible with a block buy
contract. Compared with a contract with options, a block buy contract would reduce the
government’s flexibility regarding whether and when to acquire the second and third ships, and
79 GAO, Coast Guard Acquisitions[:] Polar Icebreaker Program Needs to Address Risks before Committing Resources,
GAO-18-600, September 2018, 68 pp.
80 GAO, DHS Annual Assessment[:] Major Acquisition Programs Are Generally Meeting Goals, but Cybersecurity
Policy Needs Clarification, GAO-23-106701, April 2023, pp. 50-51.
Congressional Research Service
29
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
what design to build them to,81 and in return reduce the combined acquisition cost of the ships
covered by the contract. The Navy has used block buy contracts to reduce procurement costs of
Virginia-class attack submarines and (in more recent years) Littoral Combat Ships (LCSs) and
John Lewis (TAO-205) class oilers.82 Compared to costs using a contract with options, using a
block buy contract that included EOQ purchases (i.e., up-front batch purchases) of materials and
components for three heavy polar icebreakers could reduce the combined acquisition cost of three
PSCs by a few or several percent.
A congressionally mandated July 2017 National Academies of Sciences, Engineering, and
Medicine (NASEM) report on acquisition and operation of polar icebreakers states the following
(emphasis as in original):
3. Recommendation: USCG should follow an acquisition strategy that includes block
buy contracting with a fixed price incentive fee contract and take other measures to
ensure best value for investment of public funds.
Icebreaker design and construction costs can be clearly defined, and a fixed price incentive
fee construction contract is the most reliable mechanism for controlling costs for a program
of this complexity. This technique is widely used by the U.S. Navy. To help ensure best
long-term value, the criteria for evaluating shipyard proposals should incorporate explicitly
defined lifecycle cost metrics....
A block buy authority for this program will need to contain specific language for economic
order quantity purchases for materials, advanced design, and construction activities. A
block buy contracting program with economic order quantity purchases enables series
construction, motivates competitive bidding, and allows for volume purchase and for the
timely acquisition of material with long lead times. It would enable continuous production,
give the program the maximum benefit from the learning curve, and thus reduce labor hours
on subsequent vessels....
If advantage is taken of learning and quantity discounts available through the
recommended block buy contracting acquisition strategy, the average cost per heavy
icebreaker is approximately $791 million, on the basis of the acquisition of four ships.83
Section 8111 of the Elijah E. Cummings Coast Guard Authorization Act of 2020 (Division G of
FY2021 National Defense Authorization Act [H.R. 6395/P.L. 116-283]) states
81 Stated more fully, from a congressional perspective, trade-offs in using block buy contracting include the following:
—reduced congressional control over year-to-year spending, and tying the hands of future Congresses;
—reduced flexibility for making changes in Coast Guard acquisition programs in response to unforeseen changes
in strategic or budgetary circumstances (which can cause any needed funding reductions to fall more heavily on
acquisition programs not covered by multiyear contracts);
—a potential need to shift funding from later fiscal years to earlier fiscal years to fund economic order quantity
(EOQ) purchases (i.e., up-front batch purchases) of components;
—the risk of having to make penalty payments to shipbuilders if multiyear contracts need to be terminated due to
unavailability of funds needed to the continue the contracts; and
—the risk that materials and components purchased for ships to be acquired in future years might go to waste if
those ships are not eventually acquired.
82 See CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition:
Background and Issues for Congress, by Ronald O'Rourke; CRS Report RL33741, Navy Littoral Combat Ship (LCS)
Program: Background and Issues for Congress, by Ronald O'Rourke; and CRS Report R43546, Navy John Lewis
(TAO-205) Class Oiler Shipbuilding Program: Background and Issues for Congress, by Ronald O'Rourke.
83 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation
Research Board, Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with
cover letter dated July 11, 2017, pp. 14, 15.
Congressional Research Service
30
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
SEC. 8111. POLAR ICEBREAKERS.
(a) IN GENERAL.—Section 561 of title 14, United States Code, is amended to read as
follows:
‘‘§ 561. Icebreaking in polar regions
‘‘(a) PROCUREMENT AUTHORITY.—
‘‘(1) IN GENERAL.—The Secretary may enter into one or more contracts for the
procurement of—
‘‘(A) the Polar Security Cutters approved as part of a major acquisition program as of
November 1, 2019; and
‘‘(B) 3 additional Polar Security Cutters.
‘‘(2) CONDITION FOR OUT-YEAR CONTRACT PAYMENTS.—A contract entered
into under paragraph (1) shall provide that any obligation of the United States to make a
payment under the contract during a fiscal year after fiscal year 2019 is subject to the
availability of appropriations or funds for that purpose for such later fiscal year.
‘‘(b) PLANNING.—The Secretary shall facilitate planning for the design, procurement,
maintenance, deployment, and operation of icebreakers as needed to support the statutory
missions of the Coast Guard in the polar regions by allocating all funds to support
icebreaking operations in such regions, except for recurring incremental costs associated
with specific projects, to the Coast Guard.
‘‘(c) REIMBURSEMENT.—Nothing in this section shall preclude the Secretary from
seeking reimbursement for operation and maintenance costs of the Polar Star, Healy, or
any other Polar Security Cutter from other Federal agencies and entities, including foreign
countries, that benefit from the use of those vessels.
‘‘(d) RESTRICTION.—
‘‘(1) IN GENERAL.—The Commandant may not—
‘‘(A) transfer, relinquish ownership of, dismantle, or recycle the Polar Sea or Polar Star;
‘‘(B) change the current homeport of the Polar Sea or Polar Star; or
‘‘(C) expend any funds—
‘‘(i) for any expenses directly or indirectly associated with the decommissioning of the
Polar Sea or Polar Star, including expenses for dock use or other goods and services;
‘‘(ii) for any personnel expenses directly or indirectly associated with the
decommissioning of the Polar Sea or Polar Star, including expenses for a decommissioning
officer;
‘‘(iii) for any expenses associated with a decommissioning ceremony for the Polar Sea or
Polar Star;
‘‘(iv) to appoint a decommissioning officer to be affiliated with the Polar Sea or Polar Star;
or
‘‘(v) to place the Polar Sea or Polar Star in inactive status.
‘‘(2) SUNSET.—This subsection shall cease to have effect on September 30, 2022.
‘‘(e) LIMITATION.—
‘‘(1) IN GENERAL.—The Secretary may not expend amounts appropriated for the Coast
Guard for any of fiscal years 2015 through 2024, for—
Congressional Research Service
31
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
‘‘(A) design activities related to a capability of a Polar Security Cutter that is based solely
on an operational requirement of a Federal department or agency other than the Coast
Guard, except for amounts appropriated for design activities for a fiscal year before fiscal
year 2016; or
‘‘(B) long-lead-time materials, production, or postdelivery activities related to such a
capability.
‘‘(2) OTHER AMOUNTS.—Amounts made available to the Secretary under an agreement
with a Federal department or agency other than the Coast Guard and expended on a
capability of a Polar Security Cutter that is based solely on an operational requirement of
such Federal department or agency shall not be treated as amounts expended by the
Secretary for purposes of the limitation under paragraph (1).
‘‘(f) ENHANCED MAINTENANCE PROGRAM FOR THE POLAR STAR.—
‘‘(1) IN GENERAL.—Subject to the availability of appropriations, the Commandant shall
conduct an enhanced maintenance program on the Polar Star to extend the service life of
such vessel until at least December 31, 2025.
‘‘(2) AUTHORIZATION OF APPROPRIATIONS.—The Commandant may use funds
made available pursuant to section 4902(1)(A), to carry out this subsection.
‘‘(g) DEFINITIONS.—In this section:
‘‘(1) POLAR SEA.—The term ‘Polar Sea’ means Coast Guard Cutter Polar Sea (WAGB
11).
‘‘(2) POLAR STAR.—The term ‘Polar Star’ means Coast Guard Cutter Polar Star (WAGB
10).
‘‘(3) HEALY.—The term ‘Healy’ means Coast Guard Cutter Healy (WAGB 20).’’.
(b) CONTRACTING FOR MAJOR ACQUISITIONS PROGRAMS.—Section 1137(a) of
title 14, United States Code, is amended by inserting ‘‘and 3 Polar Security Cutters in
addition to those approved as part of a major acquisition program on November 1, 2019’’
before the period at the end.
(c) REPEALS.—
(1) COAST GUARD AND MARITIME TRANSPORTATION ACT OF 2006.—Section
210 of the Coast Guard and Maritime Transportation Act of 2006 (14 U.S.C. 504 note) is
repealed.
(2) COAST GUARD AND MARITIME TRANSPORTATION ACT OF 2012.—Section
222 of the Coast Guard and Maritime Transportation Act of 2012 (Public Law 112–213)
is repealed.
(3) HOWARD COBLE COAST GUARD AND MARITIME TRANSPORTATION ACT
OF 2014.—Section 505 of the Howard Coble Coast Guard and Maritime Transportation
Act of 2014 (Public Law 113–281) is repealed.
(4) FRANK LOBIONDO COAST GUARD AUTHORIZATION ACT OF 2018.—Section
821 of the Frank LoBiondo Coast Guard Authorization Act of 2018 (Public Law 115–282)
is repealed.
PSCs and ASCs: Using a Common Design
Another potential issue for Congress is whether to procure the Coast Guard’s envisioned fleet of
PSCs (i.e., heavy polar icebreakers) and ASCs (i.e., medium polar icebreakers) to a common
basic design. A congressionally mandated July 2017 report from NASEM on the acquisition and
operation of polar icebreakers concluded that notional operational requirements for new medium
Congressional Research Service
32
link to page 50 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
polar icebreakers would result in ships that would not be too different in size from new heavy
polar icebreakers. (As shown in Table A-1, the Coast Guard’s current medium polar icebreaker,
Healy, is actually somewhat larger than the Coast Guard’s heavy polar icebreaker, Polar Star.)
Given what it concluded as the probable similarity in size between future U.S. heavy and medium
polar icebreakers, the NASEM report recommended building a single medium polar icebreaker to
the same common design as three new heavy polar icebreakers. This approach, the report
concluded, would reduce the cost of the medium icebreaker by avoiding the cost of developing a
new design and by making the medium polar icebreaker the fourth ship on an existing production
learning curve rather than the first ship on a new production learning curve.84 If policymakers
were to decide to procure a second new ASC or a third new ASC, the same general approach
recommended by the NASEM report could be followed—a second ASC and third ASC could be
built to the same common design used for the three new PSCs and the first new ASC.
At a November 29, 2023, hearing before the House Homeland Security Committee on how U.S.
Arctic strategy impacts homeland security, Vice Admiral Peter Gautier, Coast Guard Deputy
Commandant for Operations, stated that the Coast Guard in coming years will need to have “a
mix of heavy icebreakers like the Polar Star and the Polar Security Cutters that we’re building
now, and medium icebreakers like the Healy that have shallower drafts and can get into tighter
spaces and shallower areas.”85 Procuring ASCs as ships that have shallower drafts than PSCs for
getting into tighter spaces and shallower areas could make it difficult or impossible for PSCs and
ASCs to be built to the same common design: A ship’s draft is a basic design characteristic, and it
might be difficult or impossible to reduce the PSC design’s draft enough to meet the Coast
Guard’s desire to have ASCs be able to get into tighter spaces and shallower areas without
making changes to the PSC design that would effectively make it a different design.
PSCs and ASCs: Using a Foreign Shipyard
Overview
Another potential issue for Congress concerns the possibility of building polar icebreakers for the
U.S. Coast Guard in a foreign shipyard. Shipyards in Finland, for example, reportedly have
84 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation
Research Board, Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with
cover letter dated July 11, 2017, pp. 2, 4-6. See also Calvin Biesecker, “Coast Guard Leaving Options Open for Future
Polar Icebreaker Fleet Type,” Defense Daily, April 12, 2018. Section 8108 of the Elijah E. Cummings Coast Guard
Authorization Act of 2020 (Division H/Division G of FY2021 National Defense Authorization Act [H.R. 6395/P.L.
116-283]) states
SEC. 8108. POLAR SECURITY CUTTER ACQUISITION REPORT.
Not later than 1 year after the date of the enactment of this Act, the Commandant shall submit to
the Committees on Transportation and Infrastructure and Armed Services of the House of
Representatives, and the Committees on Commerce, Science, and Transportation and Armed
Services of the Senate a report on—
(1) the extent to which specifications, key drawings, and detail design for the Polar Security Cutter
are complete before the start of construction;
(2) the extent to which Polar Security Cutter hulls numbers one, two, and three are science ready;
and
(3) what actions will be taken to ensure that Polar Security Cutter hull number four is science
capable, as described in the National Academies of Sciences, Engineering, and Medicine’s
Committee on Polar Icebreaker Cost Assessment letter report entitled ‘‘Acquisition and Operation
of Polar Ice breakers: Fulfilling the Nation’s Needs’’ and dated July 11, 2017.
85 CQ transcript of hearing.
Congressional Research Service
33
link to page 53 link to page 53 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
expressed interest in building polar icebreakers for the U.S. Coast Guard.86 Some observers
believe the acquisition cost of Coast Guard PSCs could be reduced, perhaps substantially, by
building them in a foreign shipyard, such as a shipyard in Finland or in one of the other Nordic
countries that is experienced in building icebreakers. Other observers question whether icebreaker
designs offered by foreign shipbuilders would meet (or be a cost-effective way of providing) the
Coast Guard’s desired capabilities for PSCs, which include capabilities for performing Coast
Guard missions other than icebreaking. An October 9, 2017, press report states
Finland, the world leader in icebreaker design and construction, could help pull the United
States out of its icebreaker crisis, a diplomat said at a business conference in Anchorage
last week.
“The U.S. is now in dire straits about its own icebreaker fleet. They only have two and they
are both seriously outdated. We can help,” Stefan Lindstrom, Finland’s Los Angeles-based
consul general, said in a presentation at last week’s Arctic Ambitions conference held by
the World Trade Center of Alaska....
If the U.S. makes a decision to buy a replacement from overseas, Finnish shipbuilders could
respond quickly, Lindstrom said.
In Finland, a shipyard can build and deliver a polar-class icebreaker within 24 months after
a contract is signed—a sharp contrast, Lindstrom said, to the extended discussions that the
U.S. Coast Guard and Congress have had over planning for potential new icebreakers.
And the costs for a Finnish-designed and Finnish-built polar-class icebreaker is about 200
million to 220 million Euros ($235 [million] to [$]258 million), he said. That’s far lower
than the price tag being discussed in the US.
“I have serious difficulties, however, understanding how you can pay a billion for an
icebreaker that costs one-fifth of it if you order it from abroad,” Lindstrom said. “But I'm
not going to go into those political situations.”87
It is unclear from the above-quoted remarks whether the €220-million polar-class icebreaker
being referred to would qualify as a heavy, medium, or light polar icebreaker, or to what degree it
would meet the Coast Guard’s desired capabilities for PSCs, which include capabilities for
performing Coast Guard missions other than icebreaking. Of the six Russian heavy polar
icebreakers shown in Table B-1 (all of which are nuclear-powered), four were built in Russia,
while the other two—sister ships named Taymyr and Vaygach that entered service around 1989
and 1990—were mostly built in Finland and then moved to a Russian shipyard for the installation
of their nuclear reactors. All other Finnish-built icebreakers shown in Table B-1 (whether
operated by Finland or other countries) could be considered, based on their brake horsepower
(BHP), to be medium or light polar icebreakers.
Laws Relating to Building Ships in Foreign Shipyards
Some observers have suggested that a U.S. law known as the Jones Act prevents the U.S. Coast
Guard from buying or operating a foreign-built polar icebreaker. The Jones Act, however, does
not prevent the U.S. Coast Guard from buying or operating a foreign-built polar icebreaker.88 Two
86 See, for example, Yereth Rosen, “Can the U.S. Benefit from Finland and Russia’s Icebreaker Expertise?” Arctic
Now, October 9, 2017. See also Jim Paulin, “Finland Wants In on US Icebreaker Investment,” Alaska Dispatch News,
September 8, 2015.
87 Yereth Rosen, “Can the U.S. Benefit from Finland and Russia’s Icebreaker Expertise?” Arctic Now, October 9, 2017.
88 The Jones Act (Section 27 of the Merchant Marine Act of 1920, P.L. 66-261) applies to vessels transporting
“merchandise” from one U.S. point to another U.S. point. It requires that such transportation be performed in U.S.-built
(continued...)
Congressional Research Service
34
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
other laws, however, are of note in connection with the idea of building a U.S. Coast Guard polar
icebreaker in a foreign shipyard. One is 14 U.S.C. §1151, which states the following:
§1151. Restriction on construction of vessels in foreign shipyards
(a) Except as provided in subsection (b), no Coast Guard vessel, and no major component
of the hull or superstructure of a Coast Guard vessel, may be constructed in a foreign
shipyard.
(b) The President may authorize exceptions to the prohibition in subsection (a) when the
President determines that it is in the national security interest of the United States to do so.
The President shall transmit notice to Congress of any such determination, and no contract
may be made pursuant to the exception authorized until the end of the 30-day period
beginning on the date the notice of such determination is received by Congress.
The other is 10 U.S.C. §8679, which states the following:
§8679. Construction of vessels in foreign shipyards: prohibition
(a) Prohibition.-Except as provided in subsection (b), no vessel to be constructed for any
of the armed forces,89 and no major component of the hull or superstructure of any such
vessel, may be constructed in a foreign shipyard.
(b) Presidential Waiver for National Security Interest.-(1) The President may authorize
exceptions to the prohibition in subsection (a) when the President determines that it is in
the national security interest of the United States to do so.
(2) The President shall transmit notice to Congress of any such determination, and no
contract may be made pursuant to the exception authorized until the end of the 30-day
period beginning on the date on which the notice of the determination is received by
Congress.
(c) Exception for Inflatable Boats.-An inflatable boat or a rigid inflatable boat, as defined
by the Secretary of the Navy, is not a vessel for the purpose of the restriction in subsection
(a).
CAPI: Total Cost to Purchase and Modify
Another potential issue for Congress concerns the total cost to purchase a CAPI and modify it for
use as a Coast Guard polar icebreaker. Potential oversight questions for Congress include the
following:
vessels owned by U.S. citizens and registered in the United States; U.S. registration, in turn, requires that crew
members be U.S. citizens. Merchandise is defined to include “merchandise owned by the U.S. Government, a State, or
a subdivision of a State; and valueless material” (46 U.S.C. §55102). Merchandise is further defined at 19 U.S.C.
§1401(c) to mean “goods, wares, and chattels of every description.” It is the waterborne transportation of merchandise
domestically that triggers the Jones Act. A vessel wishing to engage in such transportation would apply to the U.S.
Coast Guard for a “coastwise endorsement.” Thus, an icebreaker strictly performing the task it is designed for and not
transporting cargo from one U.S. point to another would not be subject to the Jones Act.
The federal agency in charge of deciding what kind of maritime activity must comply with the Jones Act, U.S. Customs
and Border Protection (CBP), has confirmed that icebreaking is not one of those activities. In a 2006 ruling, which
appears to be its most recent ruling on the subject, CPB informed Alcoa, Inc. that it could use foreign-built and foreign-
flagged vessels for icebreaking on the Hudson River in New York State. CBP reasoned that the transporting of
equipment, supplies, and materials used on or from the vessel in effecting its service is not coastwise trade, provided
that these articles are necessary for the accomplishment of the vessel’s mission and are usually carried aboard the
vessel as a matter of course. The 2006 ruling cited earlier rulings in 1974, 1985, and 2000 as precedent.
89 14 U.S.C. §101, which establishes the Coast Guard, states the following: “The Coast Guard, established January 28,
1915, shall be a military service and a branch of the armed forces of the United States at all times.”
Congressional Research Service
35
link to page 40 link to page 41 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
• Is the $125.0 million in FY2024 procurement funding provided for the CAPI
program intended to cover the total estimated cost to purchase the ship and make
all modifications needed to meet the Final Operational Capability (FOC)
requirements for the ship?
• If not, how much additional funding does the Coast Guard anticipate requesting
in subsequent fiscal years for completing the modifications needed to meet the
FOC requirements?
As mentioned earlier, the Coast Guard’s FY2025 UPL includes an item for $25.0 million in
procurement funding for the CAPI program “for survey and design activities, modifications, and
integrated logistics support required to advance towards full operational capability.”90
Legislative Activity for FY2024 and FY2025
Summary of Appropriation Action on FY2024 Funding Request
Table 3 summarizes congressional appropriation action on the Coast Guard’s FY2024
procurement funding requests for icebreakers.
Table 3. Summary of Congressional Appropriations Action on
FY2024 Procurement Funding Request
(In millions of dollars)
Request
HAC
SAC
Enacted
Polar Security Cutter (PSC)
170.0
144.194
0
0
Commercially available polar icebreaker (CAPI)
125.0
125.0
0
125.0
Commercially available polar icebreaker (CAPI) (emergency)
0
0
125.0
0
Great Lakes icebreaker (GLIB)
55.0
55.0
0
20.0
Great Lakes icebreaker (GLIB) (emergency)
0
0
55.0
0
Source: Table prepared by CRS, based on Coast Guard’s FY2024 budget submission, HAC and SAC committee
reports, and explanatory report on FY2024 DHS Appropriations Act.
Notes: HAC is House Appropriations Committee; SAC is Senate Appropriations Committee. S. 2625 as
reported by SAC states, “That of the amounts made available [for the Coast Guard’s Procurement,
Construction, and Improvements account], $1,118,322,000 is designated by the Congress as being for an
emergency requirement pursuant to section 251(b)(2)(A)(i) of the Balanced Budget and Emergency Deficit
Control Act of 1985.” In relation to the Balanced Budget and Emergency Deficit Control Act of 1985, S.Rept.
118-85 states: “Consistent with the funding recommended in the bil for disaster relief and for emergency
requirements in accordance with subparagraphs (D) and (A)(i) of the Balanced Budget and Emergency Deficit
Control Act of 1985, the Committee anticipates that the Budget Committee wil provide, at the appropriate
time, a 302(a) allocation for the Committee on Appropriations reflecting a net upward adjustment of
$24,561,000,000 in budget authority plus the associated outlays.” (Page 129, table note.)
Summary of Appropriation Action on FY2025 Funding Request
Table 4 summarizes congressional appropriation action on the Coast Guard’s FY2025
procurement funding requests for icebreakers.
90 U.S. Coast Guard, FY 2025 Unfunded Priorities List, Report to Congress, March 11, 2024, p. 2.
Congressional Research Service
36
link to page 41 link to page 41 link to page 40 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Table 4. Summary of Congressional Appropriations Action on
FY2025 Procurement Funding Request
(In millions of dollars)
Request
HAC
SAC
Final
Polar Security Cutter (PSC)
0
Commercially available polar icebreaker (CAPI)
0a
Great Lakes icebreaker (GLIB)
0a
Source: Table prepared by CRS, based on Coast Guard’s FY2025 budget submission, HAC and SAC committee
reports, and conference report or explanatory report on FY2025 DHS Appropriations Act.
a. The Coast Guard’s FY2025 Unfunded Priorities list (UPL) includes an item for $25.0 mil ion in procurement
funding for the CAPI program and another item for $25.0 mil ion in procurement funding for the GLIB
program.
FY2024 DHS Appropriations Act (H.R. 4367/S. 2625/Division C of
H.R. 2882/P.L. 118-47)
House
The House Appropriations Committee, in its report (H.Rept. 118-123 of June 27, 2023) on H.R.
4367, recommends the funding levels shown in the HAC column of Table 3. The recommended
reduction of $25.806 million for the PSC program is for LLTM. (Page 48.) H.Rept. 118-123 states
Commercially Available Polar Icebreaker (CAPI).—The recommendation provides the
requested $125,000,000 for the CAPI program. The Committee feels strongly that the
nation needs additional surface presence in the Arctic to protect economic and national
security interests in the high latitudes, particularly given the ongoing delays with the PSC
acquisition program….
Polar Security Cutter (PSC).—The Committee provides $144,194,000 for the PSC
program, a reduction of $25,806,000 below the request. The Committee recognizes the
strategic importance of an expanded U.S. presence in the polar regions, especially in the
Arctic. The Committee directs the Coast Guard to continue to provide additional program
and schedule details, as described in the joint explanatory statement accompanying Public
Law 117–103, as part of the required quarterly acquisition briefings. While the Committee
is frustrated by the delays in the PSC program, the Committee is pleased with recent
improvements in design maturity and continues strong support of the PSC program. Not
later than 60 days after the date of enactment, the Coast Guard is directed to provide to the
Committee a rebaselined schedule that fully accounts for the yearslong delays in the
program. The Committee fully expects this rebaseline to include realistic projections of
key milestones and delivery dates….
Great Lakes Icebreaker.—The recommendation includes the requested funding of
$55,000,000 for the analyze and select phase of the acquisition for a Great Lakes
Icebreaker. Icebreaking capabilities are important to the economy of the Great Lakes
region. The Committee notes that icebreaking technology has advanced since the
acquisition of the CGC MACKINAW and urges the Coast Guard to consider innovative
technologies and advances in ship design as the program management office works to
complete the necessary pre-acquisition activities. This may include, but is not limited to,
the use of ultra-high frequency sonic air cannon technology, drag-on bubblers, and
environmentally safe anti-freezes in combination with a ship that features a low-drag hull
shape. Additionally, the Committee suggests the Coast Guard consider the limitations in
the CGC MACKINAW’s maneuverability and whether such limitations adversely impact
Congressional Research Service
37
link to page 40 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
the vessel’s capability. Further, in order for the Coast Guard to leverage the capacity of the
nation’s industrial base, including the Coast Guard’s organic vessel repair capacity at the
Coast Guard Yard, the Committee expects the vessel to be able to fully exit the Great Lakes.
(Pages 48-49)
Senate
The Senate Appropriations Committee, in its report (S.Rept. of July 27, 2023) on S. 2625,
recommends the funding levels shown in the SAC column of Table 3. S. 2625 as reported by the
committee states (emphasis added)
PROCUREMENT, CONSTRUCTION, AND IMPROVEMENTS
For necessary expenses of the Coast Guard for procurement, construction, and
improvements, including aids to navigation, shore facilities (including facilities at
Department of Defense installations used by the Coast Guard), and vessels and aircraft,
including equipment related thereto, $1,143,322,000, to remain available until September
30, 2028; of which $20,000,000 shall be derived from the Oil Spill Liability Trust Fund to
carry out the purposes of section 1012(a)(5) of the Oil Pollution Act of 1990 (33 U.S.C.
2712(a)(5)): Provided, That of the amounts made available under this heading,
$1,118,322,000 is designated by the Congress as being for an emergency requirement
pursuant to section 251(b)(2)(A)(i) of the Balanced Budget and Emergency Deficit
Control Act of 1985.
In relation to the above-mentioned Balanced Budget and Emergency Deficit Control Act of 1985,
S.Rept. 118-85 states
Consistent with the funding recommended in the bill for disaster relief and for emergency
requirements in accordance with subparagraphs (D) and (A)(i) of the Balanced Budget and
Emergency Deficit Control Act of 1985, the Committee anticipates that the Budget
Committee will provide, at the appropriate time, a 302(a) allocation for the Committee on
Appropriations reflecting a net upward adjustment of $24,561,000,000 in budget authority
plus the associated outlays. (Page 129, table note)
S.Rept. 118-85 also states
Fleet Mix Analysis.—The Committee continues to be interested in the Fleet Mix Analysis
required in the Joint Explanatory Statement accompanying Public Law 117–103, and
appreciates the Coast Guard’s periodic status updates. The Committee reiterates its
expectation, as stated in the requirement, that the analysis be truly comprehensive and
include all classes of vessels, even those whose mission might not have a direct bearing on
the workload of other vessel classes.
Full-Funding Policy.—The Committee again directs an exception to the current acquisition
policy that requires the Coast Guard to attain the total acquisition cost for a vessel,
including long lead time materials [LLTM], production costs, and post-production costs,
before a production contract can be awarded. This policy has the potential to make
shipbuilding less efficient, to force delayed obligation of production funds, and to require
post-production funds far in advance of when they will be used. The Department should
position itself to acquire vessels in the most efficient manner within the guidelines of strict
governance measures.
Funded Projects.—The Committee expects that when it funds specific projects, those
projects shall be executed expeditiously and responsibly. The Coast Guard shall be
transparent with respect to cost increases, executability concerns, and any other issues that
may increase the risk profile of a project, and shall provide the Committee sufficient time
to consider the issue and respond in an appropriate manner….
Congressional Research Service
38
link to page 40 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Polar Security Cutter [PSC].—No funding is provided to the PSC program. The
Committee remains concerned with the progress of the PSC program, but is hopeful that
the Coast Guard will show progress towards a design and a plan for future construction.
Within 90 days of the date of enactment of this act, the Coast Guard shall brief the
Committee on the program’s progress, and shall provide a timeline for the completion of a
detailed design and the construction of PSC 1.
Great Lakes Icebreaker [GLIB].—The Committee provides $55,000,000, as requested, for
the procurement of a new GLIB that is at least as capable as the USCG MACKINAW.
Commercially Available Polar Icebreaker.—The Committee provides $125,000,000 for
the acquisition of a commercially available polar icebreaker, as requested. (Pages 75-76)
Enacted
The explanatory report for Division C of H.R. 2882/P.L. 118-47 of March 23, 2024, provides the
funding levels shown in the “Enacted” column of Table 3.
Section 543(10) of Division C of H.R. 2882/P.L. 118-47 rescinds $150.0 million in unobligated
prior-year funding for the Coast Guard’s Procurement, Construction, and Improvements (PC&I)
account. (As mentioned earlier in this report, the Coast Guard applied the rescission to the PSC
program’s FY2021 PC&I account appropriation.)
The explanatory statement states
Polar Security Cutter (PSC).—The Coast Guard is directed to keep the Committees fully
informed of the PSC program’s progress both with regular quarterly updates and, in the
case of emergent or time sensitive issues, as soon as possible.
In addition, within 120 days of the date of enactment of this Act, the Coast Guard is directed
to provide a report that assesses the viability of reactivating Coast Guard Cutter Polar Sea.
The report shall include an analysis of the material condition of the hull and cost and
timeline estimates for a full overhaul of the vessel, including the renewal of the cutter’s
propulsion, mechanical, electrical, communication, and support systems. (PDF page 31 of
125)
Congressional Research Service
39
link to page 44 link to page 45 
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Appendix A. Current U.S. Polar Icebreakers and
Polar Research Ships
This appendix provides background information on current U.S. polar icebreakers and polar
research ships.
Three Coast Guard Polar Icebreakers
Two Heavy Polar Icebreakers—Polar Star and Polar Sea
Polar Star (WAGB-10) and Polar Sea (WAGB-11),91 sister ships built to the same general design
(Figure A-1 and Figure A-2), were acquired in the early 1970s as replacements for earlier U.S.
icebreakers. They were designed for 30-year service lives, and were built by Lockheed
Shipbuilding of Seattle, WA, a division of Lockheed that also built ships for the U.S. Navy, but
which exited the shipbuilding business in the late 1980s.
Figure A-1. Polar Star and Polar Sea
(Side by side in McMurdo Sound, Antarctica)
Source: Coast Guard photograph that was accessed on April 21, 2011, at http://www.uscg.mil/pacarea/
cgcpolarsea/history.asp (link no longer active). The photograph accompanies Kyung M. Song, “Senate Passes
Cantwell Measure to Postpone Scrapping of Polar Sea Icebreaker,” Seattle Times, September 22, 2012, posted at
http://blogs.seattletimes.com/politicsnorthwest/2012/09/22/senate-passes-cantwell-measure-to-postpone-
scrapping-of-polar-sea-icebreaker/.
91 The designation WAGB means Coast Guard icebreaker. More specifically, W means Coast Guard ship, A means
auxiliary, G means miscellaneous purpose, and B means icebreaker.
Congressional Research Service
40

Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Figure A-2. Polar Sea
Source: Coast Guard photograph that was accessed April 21, 2011, at http://www.uscg.mil/pacarea/cgcpolarsea/
img/PSEApics/Ful Ship2.jpg (link no longer active). The photograph accompanies Associated Press, “Reprieve for
Seattle-Based Icebreaker Polar Sea,” KOMO News, June 15, 2012, posted at https://komonews.com/news/local/
reprieve-for-seattle-based-icebreaker-polar-sea.
The ships are 399 feet long and displace about 13,200 tons.92 They are among the world’s most
powerful nonnuclear-powered icebreakers, with a capability to break through ice up to 6 feet
thick at a speed of 3 knots. Because of their icebreaking capability, they are considered (in U.S.
parlance) heavy polar icebreakers. In addition to a crew of 134, each ship can embark a scientific
research staff of 32 people.
Polar Star was commissioned into service in 1976, and consequently is now more than 15 years
beyond its originally intended 30-year service life. Due to worn-out electric motors and other
problems, the Coast Guard placed the ship in caretaker status on July 1, 2006.93 Congress in
FY2009 and FY2010 provided funding to repair Polar Star and return it to service for 7 to 10
years; the repair work, which reportedly cost about $57 million, was completed, and the ship was
reactivated on December 14, 2012.94
Polar Sea was commissioned into service in 1977, and consequently is also more than 15 years
beyond its originally intended 30-year service life. In 2006, the Coast Guard completed a
rehabilitation project that extended the ship’s expected service life to 2014. On June 25, 2010,
however, the Coast Guard announced that Polar Sea had suffered an engine casualty, and the ship
was unavailable for operation after that.95 The Coast Guard placed Polar Sea in commissioned,
92 By comparison, the Coast Guard’s new National Security Cutters—its new high-endurance cutters—are about 418
feet long and displace roughly 4,000 tons.
93 Source for July 1, 2006, date: U.S. Coast Guard email to CRS on February 22, 2008. The Coast Guard’s official term
for caretaker status is “In Commission, Special.”
94 See, for example, Kyung M. Song, “Icebreaker Polar Star Gets $57 Million Overhaul,” Seattle Times, December 14,
2012.
95 “Icebreaker POLAR SEA Sidelined by Engine Troubles,” Coast Guard Compass (Official Blog of the U.S. Coast
Guard), June 25, 2010. See also “USCG Cancels Polar Icebreaker’s Fall Deployment,” DefenseNews.com, June 25,
2010; Andrew C. Revkin, “America’s Heavy Icebreakers Are Both Broken Down,” Dot Earth (New York Times blog),
June 25, 2010.
Congressional Research Service
41
link to page 46 link to page 52 
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
inactive status on October 14, 2011. The Coast Guard transferred certain major equipment from
Polar Sea to Polar Star to facilitate Polar Star’s return to service.96
Although the Coast Guard in recent years has invested millions of dollars to overhaul, repair, and
extend the service life of Polar Star, the ship’s material condition, as a result of its advancing age,
has nevertheless become increasingly fragile, if not precarious. During its annual deployments to
McMurdo Station in Antarctica, shipboard equipment frequently breaks, and shipboard fires
sometimes occur.97 Replacements for many of the ship’s components are no longer commercially
available. To help keep Polar Star operational, the Coast Guard continues to use Polar Sea as a
source of replacement parts.
One Medium Polar Icebreaker—Healy
Healy (WAGB-20) (Figure A-3) was funded in the early 1990s as a complement to Polar Star
and Polar Sea, and was commissioned into service on August 21, 2000.
Figure A-3. Healy
Source: Coast Guard photograph accessed August 12, 2019, at https://www.history.uscg.mil/US-Coast-Guard-
Photo-Gallery/igphoto/2002136680/.
96 Source: October 17, 2011, email to CRS from Coast Guard Congressional Affairs office. Section 222 of the Coast
Guard and Maritime Transportation Act of 2012 (H.R. 2838/P.L. 112-213 of December 20, 2012) prohibited the Coast
Guard from removing any part of Polar Sea and from transferring, relinquishing ownership of, dismantling, or
recycling the ship until it submitted a business case analysis of the options for and costs of reactivating the ship and
extending its service life to at least September 30, 2022, so as to maintain U.S. polar icebreaking capabilities and fulfill
the Coast Guard’s high latitude mission needs, as identified in the Coast Guard’s July 2010 High Latitude Study. The
business case analysis was submitted to Congress with a cover date of November 7, 2013. For more on the High
Latitude Study, see Appendix B.
97 See, for example, Richard Read, “Meet the Neglected 43-Year-Old Stepchild of the U.S. Military-Industrial
Complex,” Los Angeles Times, August 2, 2019; Melody Schreiber, “The Only Working US Heavy Icebreaker Catches
Fire Returning from Antarctica,” Arctic Today, March 2, 2019; Calvin Biesecker, “Fire Breaks Out on Coast Guard’s
Aging, and Only, Heavy Icebreaker,” Defense Daily, March 1, 2019.
Congressional Research Service
42
link to page 48 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
The procurement of Healy was funded largely (about 89%) through the Navy’s shipbuilding
account (i.e., the Shipbuilding and Conversion, Navy, or SCN account).98
The ship was built by Avondale Industries, a shipyard located near New Orleans, LA, that built
numerous Coast Guard and Navy ships, and which eventually became part of Huntington Ingalls
Industries (HII). (HII subsequently wound down shipbuilding activities at Avondale, and the
facility no longer builds ships.)
Although it is referred to (in U.S. parlance) as a medium polar icebreaker, Healy is actually larger
than Polar Star and Polar Sea—it is 420 feet long and displaces about 16,000 tons. Compared to
Polar Star and Polar Sea, Healy has less icebreaking capability (which is why it is referred to as
a medium polar icebreaker rather than a heavy polar icebreaker), but more capability for
supporting scientific research. The ship can break through ice up to 4½ feet thick at a speed of 3
knots, and embark a scientific research staff of 35 (with room for another 15 surge personnel and
2 visitors). The ship is used primarily for supporting scientific research and conducting other
operations in the Arctic.
Three National Science Foundation (NSF) Polar Research Ships
Nathaniel B. Palmer
Nathaniel B. Palmer (Figure A-4) was built for the NSF in 1992 by North American
Shipbuilding, of Larose, LA. Called Palmer for short, it is operated for NSF by Edison Chouest
Offshore (ECO) of Galliano, LA, a firm that owns and operates research ships and offshore
deepwater service ships.99 Palmer is 308 feet long and has a displacement of about 6,500 tons. It
has a crew of 22 and can embark a scientific staff of 27 to 37.100 It was purpose-built as a single-
mission ship for conducting and supporting scientific research in the Antarctic. It is capable of
breaking ice up to 3 feet thick at speeds of 3 knots, which is sufficient for breaking through the
ice conditions found in the vicinity of the Antarctic Peninsula, so as to resupply Palmer Station, a
U.S. research station on the peninsula. The ship might be considered less an icebreaker than an
oceanographic research ship with enough icebreaking capability for the Antarctic Peninsula.
98 The somewhat complicated funding history for the ship is as follows: The Coast Guard’s proposed FY1990 budget
requested $244 million for the acquisition of an icebreaker. The FY1990 DOD Appropriations Act (H.R. 3072/P.L.
101-165 of November 21, 1989) provided $329 million for the ship in the SCN account. (See pages 77 and 78 of
H.Rept. 101-345 of November 13, 1989.) This figure was then reduced by $4.2 million by a sequester carried out under
the Balanced Budget And Emergency Deficit Control Act of 1985, also known as the Gramm-Rudman-Hollings Act
(H.J.Res. 372/P.L. 99-177 of December 12, 1985). Another $50 million was rescinded by the Dire Emergency
Supplemental Appropriations for Disaster Assistance, Food Stamps, Unemployment Compensation Administration,
and Other Urgent Needs, and Transfers, and Reducing Funds Budgeted for Military Spending Act of 1990 (H.R.
4404/P.L. 101-302 of May 25, 1990). An additional $59 million for the ship was then appropriated in the FY1992 DOD
Appropriations Act (H.R. 2521/P.L. 102-172 of November 26, 1991). Also, an additional $40.4 million in procurement
funding for the ship was provided through a series of annual appropriations in the Coast Guard’s Acquisition,
Construction, and Improvements (AC&I) account (as it was known prior to FY2019) from FY1988 through FY2001.
The resulting net funding for the ship was thus $374.2 million, of which $333.8 million, or 89.2%, was DOD funding,
and $40.4 million, or 10.8%, was Coast Guard procurement funding. (Source: Undated Coast Guard information paper
provided to CRS by Coast Guard legislative liaison office, March 3, 2016.)
99 For more on ECO, see the firm’s website at http://www.chouest.com/.
100 Sources vary on the exact number of scientific staff that can be embarked on the ship. For some basic information
on the ship, see http://www.nsf.gov/od/opp/support/nathpalm.jsp; http://www.usap.gov/vesselScienceAndOperations/
documents/prvnews_june03.pdfprvnews_june03.pdf; http://nsf.gov/od/opp/antarct/treaty/pdf/plans0607/15plan07.pdf;
http://www.nsf.gov/pubs/1996/nsf9693/fls.htm; and http://www.hazegray.org/worldnav/usa/nsf.htm.
Congressional Research Service
43
link to page 49 link to page 49 
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Palmer’s icebreaking capability is not considered sufficient to perform the McMurdo resupply
mission.
Figure A-4. Nathaniel B. Palmer
Source: Photograph accompanying Peter Rejcek, “System Study, LARISSA Takes Unique Approach for Research
on Ice Shelf Ecosystem,” Antarctic Sun (U.S. Antarctic Program), September 18, 2009. A caption to the
photograph states “Photo Courtesy: Adam Jenkins.”
Laurence M. Gould
Like Palmer, the polar research and supply ship Laurence M. Gould (Figure A-5) was built for
NSF by North American Shipping. It was completed in 1997 and is operated for NSF on a long-
term charter from ECO. It is 230 feet long and has a displacement of about 3,800 tons. It has a
crew of 16 and can embark a scientific staff of 26 to 28 (with a capacity for 9 more in a berthing
van). It can break ice up to 1 foot thick with continuous forward motion. Like Palmer, it was built
to support NSF operations in the Antarctic, particularly operations at Palmer Station on the
Antarctic Peninsula.
Sikuliaq
Sikuliaq (see-KOO-lee-auk; Figure A-6), which is used for scientific research in polar areas, was
built by Marinette Marine of Marinette, WI, and entered service in 2015. It is operated for NSF
by the College of Fisheries and Ocean Sciences at the University of Alaska Fairbanks as part of
the U.S. academic research fleet through the University National Oceanographic Laboratory
System (UNOLS). Sikuliaq is 261 feet long and has a displacement of about 3,600 tons. It has a
crew of 22 and can embark an additional 26 scientists and students. The ship can break ice 2½ or
3 feet thick at speeds of 2 knots. The ship is considered less an icebreaker than an ice-capable
research ship.
Congressional Research Service
44


Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Figure A-5. Laurence M. Gould
Source: Photograph accompanying Alchetron, “RV Laurence M. Gould,” updated August 25, 2018, accessed
August 7, 2019, at https://alchetron.com/RV-Laurence-M.-Gould#-.
Figure A-6. Sikuliaq
Source: Photograph accompanying Lauren Frisch, “UAF Joins International Consortium of Icebreaker
Operators,” UAF [University of Alaska Fairbanks] News and Information, February 6, 2018. A caption to the
photograph states in part: “Photo by Mark Teckenbrock. The research vessel Sikuliaq navigates through Arctic
ice in summer 2016.”
Congressional Research Service
45
link to page 50 link to page 50 link to page 50 link to page 50 link to page 50 link to page 50 link to page 50 link to page 51 link to page 51 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Summary of Above Ships
Table A-1 summarizes the above six ships.
Table A-1. Coast Guard and NSF Polar Ships
Coast Guard
NSF
Laurence
Polar Star
Polar Sea
Healy
Palmer
M. Gould
Sikuliaq
Currently operational?
Yes
No
Yes
Yes
Yes
Yes
Entered service
1976
1977
2000
1992
1997
2015
Length (feet)
399
399
420
308
230
261
Displacement (tons)
13,200
13,200
16,000
6,500
3,780
3,665
Icebreaking capability
6 feet
6 feet
4.5 feet
3 feet
1 foot at
2.5 or 3
(ice thickness in feet) at
continuous
feet at 2
3 knots or other speed
forward
knots
motion
Icebreaking capability
21 feet
21 feet
8 feet
n/a
n/a
n/a
using back and ram (ice
thickness in feet)
Operating temperature
-60o Fahrenheit
-60o
-50o
n/a
n/a
n/a
Fahrenheit
Fahrenheit
Crew (when operational)
155a
155a
85b
22
16
22
Additional scientific staff
32
32
35c
27-37
26 to 28d
26
Sources: Prepared by CRS using data from U.S. Coast Guard, National Research Council, National Science
Foundation, DHS Office of Inspector General, and (for Palmer) additional online reference sources.
Notes: n/a is not available.
a. Includes 24 officers, 20 chief petty officers, 102 enlisted, and 9 in the aviation detachment.
b. Includes 19 officers, 12 chief petty officers, and 54 enlisted.
c. In addition to 85 crew members 85 and 35 scientists, the ship can accommodate another 15 surge
personnel and 2 visitors.
d. Plus 9 more in a berthing van.
Commercial Ship Aiviq (Ship to Be Purchased Under CAPI
Program)
In addition to the ships shown in Table A-1, another U.S.-registered polar ship with icebreaking
capability—the 360-foot Arctic oil-exploration support ship Aiviq (Figure A-7 and Figure A-8)—
was used by Royal Dutch Shell oil company to support an oil exploration and drilling effort (now
ended) in Arctic waters off Alaska. The ship, which completed construction in 2012, is owned by
ECO. It was used primarily for towing and laying anchors for drilling rigs, but is also equipped
for responding to oil spills. As discussed earlier in this report, the Coast Guard, under the
Commercially Available Polar Icebreaker (CAPI) program, intends to purchase Aiviq and modify
it for use as a Coast Guard medium polar icebreaker.
Congressional Research Service
46


Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Figure A-7. Commercial Ship Aiviq
Source: “AIVIQ - IMO 9579016,” Shipspotting.com, undated, accessed April 29, 2022, at
https://www.shipspotting.com/photos/1523039. The photograph, dated March 24, 2012, is credited to
PJBlackbird.
Figure A-8. Commercial Ship Aiviq
Source: Cropped version of photograph accompanying “Aiviq,” Wikipedia, accessed April 29, 2022, which states
that the photograph is dated December 30, 2012, and credits the photograph to U.S. Coast Guard Petty Officer
3rd Class Chris Usher.
Congressional Research Service
47
link to page 53 Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Appendix B. Required Numbers of U.S. Polar
Icebreakers
This appendix provides additional background information on required numbers of U.S. polar
icebreakers.
2023 Coast Guard Fleet Mix Analysis
As mentioned above, the Coast Guard testified in April, June, and November 2023 that a new
Coast Guard fleet mix analysis concluded that the service will require a total of eight to nine polar
icebreakers, including four to five heavy polar icebreakers and four to five medium polar
icebreakers, to perform its polar (i.e., Arctic and Antarctic) missions in coming years.101 Prior to
this new fleet mix analysis, the Coast Guard had stated that it would need at least six polar
icebreakers, including three heavy polar icebreakers.
Polar Icebreakers Operated by Other Countries as of 2022
In discussions of U.S. polar icebreakers, observers sometimes note the sizes of polar icebreaking
fleets operated by other countries. Table B-1 shows a Coast Guard summary of major polar
icebreakers around the world.
Some observers highlight the difference between the number of U.S. polar icebreakers and the
much larger number of Russian polar icebreakers, and characterize the situation as an “icebreaker
gap.”102 Other observers question the relevance of that comparison and characterization.103 In
101 Spoken testimony, as reflected in CQ hearing transcripts, of
•
Admiral Linda L. Fagan, Commandant of the Coast Guard, at an April 18, 2023, hearing on the Coast
Guard’s proposed FY2024 budget before the Coast Guard and Maritime Transportation subcommittee of the
House Transportation and Infrastructure Committee, for the total figure of eight to nine polar icebreakers;
•
Admiral Steven D. Poulin, Vice Commandant of the Coast Guard, at a June 21, 2023, hearing before the
same subcommittee on the on the Coast Guard’s emerging challenges and statutory needs, again for the total
figure of eight to nine polar icebreakers; and
•
Vice Admiral Peter Gautier, Coast Guard Deputy Commandant for Operations, at a November 29, 2023,
hearing before the House Homeland Security Committee on how U.S. Arctic strategy impacts homeland
security, for both the total figure of eight to nine polar icebreakers and how that total includes four to five
heavy polar icebreakers and four to five medium polar icebreakers.
102 See, for example, Mike Glenn, “U.S. Icebreaker Gap with Russia a Growing Concern as Arctic ‘Cold War’ Heats
Up,” Washington Times, September 23, 2021; Lin A. Mortensgaard and Kristian Søby Kristensen, “The ‘Icebreaker-
Gap’—How US Icebreakers Are Assigned New, Symbolic Roles as Part of an Escalating Military Competition in the
Arctic,” Safe Seas, January 5, 2021; Christopher Woody, “As US Tries to Close ‘Icebreaker Gap’ with Russia, Its Only
Working Icebreaker Is Making a Rare Trip North,” Business Insider, November 9, 2020; Peter Kikkert, Gaps and
Bridges: The Case for American Polar Icebreakers, North American Arctic Defence and Security Network, August 12,
2020, 5 pp.; Marc Lanteigne, “So What Is the ‘Icebreaker Gap’ Anyway?” Over the Circle, March 3, 2019; Charlie
Gao, “The ‘Icebreaker Gap’: How Russia Is Planning to Build More Icebreakers to Project Power in the Arctic,”
National Interest, August 19, 2018; Dermot Cole, “The US Is Finally Picking Up the Pace to Build a Modern Heavy
Icebreaker,” ArcticToday, April 21, 2018; Craig H. Allen Sr., “Addressing the US Icebreaker Shortage,” Pacific
Maritime, December 2017: 30-33; Adam Lemon and Brian Slattery, “Standoff in the Arctic: Closing the Icebreaker
Gap,” Newsweek, August 14, 2016; Franz-Stefan Gady, “Will the US Coast Guard Close the ‘Icebreaker Gap’?”
Diplomat, January 14, 2016; Jen Judson, “The Icebreaker Gap,” Politico, September 1, 2015.
103 See, for example, Robert D. English, “Why an Arctic Arms Race Would Be a Mistake,” ArcticToday, June 18,
2020; Paul C. Avey, “The Icebreaker Gap Doesn’t Mean America Is Losing in the Arctic,” War on the Rocks,
November 28, 2019; Chuck Hill, “Horrors, It’s the Icebreaker Gap (cringe),” Chuck Hill’s CG Blog, December 21,
(continued...)
Congressional Research Service
48
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
considering the number of Russian polar icebreakers, factors that may be considered include the
length of Russia’s Arctic coastline and Russia’s use of maritime transportation along its Arctic
coastline to support numerous Russian Arctic communities. (Russia’s Arctic population is roughly
2 million.)104 Countries with interests in the polar regions have differing requirements for polar
icebreakers, depending on the nature and extent of their polar interests and activities. (The term
icebreaker gap is also sometimes used to refer to a potential gap in time between the end of Polar
Star’s service life and the entry into service of the first PSC, or to discuss options, such as leasing
existing icebreakers, for bolstering U.S. polar icebreaking capability prior to the entry into service
of the first PSC.)105
Table B-1. Major Polar Icebreakers as of April 4, 2022
Government owned or operated
Privately owned and operated
PC1, PC2,
PC3, PC4,
PC5, PC6,
PC1, PC2,
PC3, PC4, PC5, PC6,
or equiv.
or equiv.
or equiv.
or equiv.
or equiv.
or equiv.
Total
Russia
6
22
8
9
6
51
[+2 unavailable]
[+2 unavailable]
Canada
2
10
12
Finland
7
2
9
United States
1 (Polar Star)
1 (Healy)
1 (Aiviq)
2 (Sikuliaq
5
[+1
and Palmer)
[+1
nonoperational
nonoperational]
(Polar Sea)]
Sweden
4
4
China
1
3
4
Denmark
3
3
Norway
1
1
2
Estonia
2
2
France
1
1
2
United Kingdom
1
1
Japan
1
1
Australia
1
1
Italy
1
1
Latvia
1
1
South Korea
1
1
South Africa
1
1
Argentina
1
1
Chile
1
1
Germany
1
1
Source: Table prepared by CRS based on U.S. Coast Guard graphic of homeports of major polar icebreakers,
updated April 4, 2022; provided to CRS by U.S. Coast Guard on August 11, 2022. (An earlier version of the
2017; Jeremy Hsu, “U.S. Icebreaker Fleet Is Overdue for an Upgrade,” Scientific American, June 1, 2017; Andreas
Kuersten, “Icebreakers and U.S. Power: Separating Fact from Fiction,” War on the Rocks, October 11, 2016; Andreas
Kuersten, “The Dangerous Myth of an ‘Icebreaker Gap,’” Defense One, September 6, 2016; Andrew C. Revkin, “The
U.S. Icebreaker Gap Is About Arctic Needs, Not About Chasing Russia,” New York Times (Dot Earth New York Times
Blog), September 1, 2015.
104 For additional discussion, see the “Background” section of CRS Report R41153, Changes in the Arctic: Background
and Issues for Congress, coordinated by Ronald O'Rourke.
105 See, for example, Liz Ruskin, “Trump Administration May Hire Private Ship to Fill Arctic ‘Icebreaker Gap’ by
Year’s End,” Alaska Public Media, December 14, 2020; GAO, Coast Guard Acquisitions[:] Polar Icebreaker Program
Needs to Address Risks before Committing Resources, GAO-18-600, September 2018, summary page; Norton A.
Schwartz and James G. Stavridis, “A Quick Fix for the U.S. ‘Icebreaker Gap,’” Wall Street Journal, February 3, 2016.
Congressional Research Service
49
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
graphic, reflecting data as of May 1, 2017, was posted at https://www.dco.uscg.mil/Portals/9/
DCO%20Documents/Office%20of%20Waterways%20and%20Ocean%20Policy/
20170501%20major%20icebreaker%20chart.pdf?ver=2017-06-08-091723-907 as of September 21, 2022.) The
U.S. Coast Guard states that the vessels shown in the graphic “were selected and organized based on IACS Polar
Class notation [see note below], or best equivalent based on publicly available estimates. All vessels included are
believed to be capable of independent Arctic or Antarctic operations.” The Coast Guard graphic includes the
two unavailable Russian government-owned or -operated PC1 or PC2 icebreakers shown above, but it does not
include the U.S. nonoperational PC1 or PC2 icebreaker Polar Sea, which was added by CRS.
Notes: PC1 through PC6 are IACS (International Association of Classification Societies) classifications for polar-
class ships. PC1 through PC5 are ships capable of year-round operation in all polar waters (PC1); moderate
multiyear ice conditions (PC2); second-year ice, which may include multiyear ice inclusions (PC3); thick first-year
ice, which may include old ice inclusions (PC4); or medium first-year ice, which may include old ice inclusions
(PC5). PC6 are ships capable of summer/autumn operation in medium first-year ice, which may include old ice
inclusions. (An additional category not shown in the table, PC7, are ships capable of summer/autumn operation
in thin first-year ice, which may include old ice inclusions.) Source: Requirements concerning Polar Class,
International Association of Classification Societies, undated, including Revision 4 of December 2019, Table 1,
entitled Polar Class descriptions, p. I1-2.
June 9, 2020, Presidential Memorandum
On June 9, 2020, President Trump issued a memorandum, “Memorandum on Safeguarding U.S.
National Interests in the Arctic and Antarctic Regions,” which states
Memorandum for the Secretary of State, the Secretary of Defense, the Secretary of
Commerce, the Secretary of Energy, the Secretary of Homeland Security, the Director of
the Office of Management and Budget, [and] the Assistant to the President for National
Security Affairs
Subject: Safeguarding U.S. National Interests in the Arctic and Antarctic Regions
To help protect our national interests in the Arctic and Antarctic regions, and to retain a
strong Arctic security presence alongside our allies and partners, the United States requires
a ready, capable, and available fleet of polar security icebreakers that is operationally tested
and fully deployable by Fiscal Year 2029. Accordingly, by the authority vested in me as
President by the Constitution and the laws of the United States of America, I hereby direct
the following:
Section 1. Fleet Acquisition Program. The United States will develop and execute a polar
security icebreaking fleet acquisition program that supports our national interests in the
Arctic and Antarctic regions.
(a) The Secretary of Homeland Security, in coordination with the Secretary of State, the
Secretary of Defense, the Secretary of Commerce, and the Director of the Office of
Management and Budget (OMB), shall lead a review of requirements for a polar security
icebreaking fleet acquisition program to acquire and employ a suitable fleet of polar
security icebreakers, and associated assets and resources, capable of ensuring a persistent
United States presence in the Arctic and Antarctic regions in support of national interests
and in furtherance of the National Security Strategy and the National Defense Strategy, as
appropriate. Separately, the review shall include the ability to provide a persistent United
States presence in the Antarctic region, as appropriate, in accordance with the Antarctic
Treaty System. The Secretary of Homeland Security and the Director of OMB, in executing
this direction, shall ensure that the United States Coast Guard’s (USCG) Offshore Patrol
Cutter acquisition program is not adversely impacted.
(b) The Secretary of Homeland Security, acting through the Commandant of the Coast
Guard, in coordination with the Secretary of Defense, acting through the Secretary of the
Navy, and the Secretary of Energy, as appropriate, shall conduct a study of the comparative
operational and fiscal benefits and risks of a polar security icebreaking fleet mix that
consists of at least three heavy polar-class security cutters (PSC) that are appropriately
Congressional Research Service
50
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
outfitted to meet the objectives of this memorandum. This study shall be submitted to the
President, through the Director of OMB and the Assistant to the President for National
Security Affairs, within 60 days from the date of this memorandum and at a minimum shall
include:
(i) Use cases in the Arctic that span the full range of national and economic security
missions (including the facilitation of resource exploration and exploitation and undersea
cable laying and maintenance) that may be executed by a class of medium PSCs, as well
as analysis of how these use cases differ with respect to the anticipated use of heavy PSCs
for these same activities. These use cases shall identify the optimal number and type of
polar security icebreakers for ensuring a persistent presence in both the Arctic and, as
appropriate, the Antarctic regions;
(ii) An assessment of expanded operational capabilities, with estimated associated costs,
for both heavy and medium PSCs not yet contracted for, specifically including the
maximum use of any such PSC with respect to its ability to support national security
objectives through the use of the following: unmanned aviation, surface, and undersea
systems; space systems; sensors and other systems to achieve and maintain maritime
domain awareness; command and control systems; secure communications and data
transfer systems; and intelligence-collection systems. This assessment shall also evaluate
defensive armament adequate to defend against threats by near-peer competitors and the
potential for nuclear-powered propulsion;
(iii) Based on the determined fleet size and composition, an identification and assessment
of at least two optimal United States basing locations and at least two international basing
locations. The basing location assessment shall include the costs, benefits, risks, and
challenges related to infrastructure, crewing, and logistics and maintenance support for
PSCs at these locations. In addition, this assessment shall account for potential burden-
sharing opportunities for basing with the Department of Defense and allies and partners, as
appropriate; and
(iv) In anticipation of the USCGC POLAR STAR’s operational degradation from Fiscal
Years 2022-2029, an analysis to identify executable options, with associated costs, to
bridge the gap of available vessels as early as Fiscal Year 2022 until the new PSCs required
to meet the objectives of this memorandum are operational, including identifying
executable, priced leasing options, both foreign and domestic. This analysis shall
specifically include operational risk associated with using a leased vessel as compared to a
purchased vessel to conduct specified missions set forth in this memorandum.
(c) In the interest of securing a fully capable polar security icebreaking fleet that is capable
of providing a persistent presence in the Arctic and Antarctic regions at the lowest possible
cost, the Secretary of State shall coordinate with the Secretary of Homeland Security in
identifying viable polar security icebreaker leasing options, provided by partner nations, as
a near- to mid-term (Fiscal Years 2022-2029) bridging strategy to mitigate future
operational degradation of the USCGC POLAR STAR. Leasing options shall contemplate
capabilities that allow for access to the Arctic and Antarctic regions to, as appropriate,
conduct national and economic security missions, in addition to marine scientific research
in the Arctic, and conduct research in Antarctica in accordance with the Antarctic Treaty
System. Further, and in advance of any bid solicitation for future polar security icebreaker
acquisitions, the Secretary of State shall coordinate with the Secretary of Homeland
Security to identify partner nations with proven foreign shipbuilding capability and
expertise in icebreaker construction.
(d) The Secretary of Defense shall coordinate with the Secretary of State and the Secretary
of Homeland Security to continue to provide technical and programmatic support to the
USCG integrated program office for the acquisition, outfitting, and operations of all classes
of PSCs.
Congressional Research Service
51
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Sec. 2. General Provisions. (a) Nothing in this memorandum shall be construed to impair
or otherwise affect:
(i) the authority granted by law to an executive department or agency, or the head thereof;
or
(ii) the functions of the Director of OMB relating to budgetary, administrative, or
legislative proposals.
(b) This memorandum shall be implemented consistent with applicable law and subject to
the availability of appropriations.
(c) This memorandum is not intended to, and does not, create any right or benefit,
substantive or procedural, enforceable at law or in equity by any party against the United
States, its departments, agencies, or entities, its officers, employees, or agents, or any other
person.106
A September 10, 2020, press report states
The White House dropped a surprise directive in June calling for a new strategy in the High
North, a move applauded by Arctic watchers who've been waiting for an administration to
make the issue a priority….
Yet a month after the report was due to the White House, it’s not clear when, or if, anyone
will see it.
The report, which was to include new designs for a fleet of possibly nuclear-powered
icebreakers, has been submitted to the National Security Council. Yet an NSC
spokesperson did not respond to a query on the timing of a release, and would only say the
report is “under review.”107
A December 3, 2020, press report states
The Coast Guard and its partners are assessing options for additional polar icebreaking
capacity in the next decade beyond current plans pursuant to a directive from the Trump
administration, Coast Guard Commandant Adm. Karl Schultz said on Thursday [December
3].
The Coast Guard’s current polar strategy calls for six new icebreakers, at least three of
them heavy, and one immediately, and now “The good news is there’s been a conversation
beyond the 6-3-1 strategy,” Schultz said during a virtual address hosted by the Navy
League. “The president and his team have pressed us here since this past summer pulling
together the energy of five cabinet level officials and OMB [Office of management and
Budget] about saying, ‘Hey, what does more capacity for high-latitude work between now
and 2029 look like?’”…
The Coast Guard hasn’t looked favorably in the past on leasing options for ice breakers, at
least not as a permanent solution to its polar requirements. But Schultz said leasing could
fill near-term gaps.
“We clearly don’t want to be looking at leasing options as a replacement for the
procurement of ships that are going to serve us for decades to come, but there might be
106 White House, “Memorandum on Safeguarding U.S. National Interests in the Arctic and Antarctic Regions,” June 9,
2020, accessed June 10, 2020, at https://www.whitehouse.gov/presidential-actions/memorandum-safeguarding-u-s-
national-interests-arctic-antarctic-regions/. For press reports about the memorandum, see, for example, David B. Larter,
Joe Gould, and Aaron Mehta, “Trump Memo Demands New Fleet of Arctic Icebreakers Be Ready by 2029,” Defense
News, June 9, 2020; Paul McLeary, “White House Orders New Icebreaker Strategy For Coast Guard,” Breaking
Defense, June 9, 2020; Cal Biesecker, “Trump Wants Review of Polar Security Cutter Needs in Arctic, Antarctic,”
Defense Daily, June 9, 2020.
107 Sarah Cammarata, “Trump’s Arctic Plan Stuck in the Ice,” Politico Pro, September 10, 2020.
Congressional Research Service
52
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
some bridging strategies and some leasing options,” he said. “So, we’re working really
hard on that, answering some deliverables over to the White House and hope we can keep
some momentum.”
A Coast Guard spokesman told Defense Daily following Schultz’s speech that the service
and the Navy “have formed a joint working group to assess available foreign and domestic
vessels that would meet short-term mission needs in the Arctic. The Coast Guard is
continuing to evaluate all options and provide detailed analysis of icebreaker capacity,
lease options, and long-term strategies to protect vital economic and national security
interests in the Polar Regions.”108
A December 16, 2020, press report stated
The White House National Security Adviser and the Navy may be on the verge of agreeing
to move forward shortly with a plan to lease medium polar icebreakers to fill a near-term
gap in the Coast Guard’s icebreaking needs, Alaska Sen. Dan Sullivan (R) said last week.
Sullivan, during a Dec. 8 hearing that he chaired that morning on the Coast Guard’s
capabilities in the Arctic, said he spoke earlier that day with White House National Security
Adviser Robert O’Brien, who told him that the U.S. is looking at leasing polar icebreakers
from Finland.
“My understanding is the White House National Security Adviser [and] possibly the Navy
with regard to some of their funding, are looking at moving forward on leases soon,
hopefully as early as the end of this month,” Sullivan told Adm. Charles Ray, vice
commandant of the Coast Guard.
Ray replied that discussions on leasing are part of a presidential directive issued in June,
noting that a joint Coast Guard and Navy group are looking into this.
Later during the hearing, in response to a question from Sen. Mike Lee (R-Utah) about
potentially buying polar icebreakers from NATO allies or friendly Arctic nations, Ray said
the “The bridging strategy that makes the most sense to the Coast Guard at this point is this
potential to lease one of these icebreakers.”
Ray pointed out to Sullivan that the potential leasing strategy is not in place of the Coast
Guard eventually acquiring new polar icebreakers.
A Coast Guard spokesman on Wednesday told Defense Daily that the exact number if
icebreakers that would be leased hasn’t been determined and “depends on individual vessel
availability and capabilities, crew availability, funding, and other factors.” He also said the
options only included medium icebreakers because no heavy icebreakers are currently
available that meet the service’s minimum requirements.…
The Coast Guard spokesman said a bridging strategy is being examined because the first
PSC won’t begin operations until 2027. Any leased vessels, which potentially could be
domestic or foreign flagged, would operate in the Arctic “to project U.S. sovereignty;
protect vital economic and national security interests; and conduct maritime domain
awareness, search and rescue, and other Coast Guard missions,” he wrote in an email
response to questions.…
Ray said that a key shortfall of leasing commercial polar icebreakers is they aren’t built to
military
specifications,
highlighting
communications,
damage
control
and
compartmentalization in case of an incident.
“They’re a different cat,” Ray said. “We would have to do some work to them. It’s not just,
take one off the shelf. If it was, we probably would have done that a long time ago. So,
108 Cal Biesecker, “Coast Guard, Partners Assessing Options for More Polar Icebreaking Capacity,” Defense Daily,
December 3, 2020.
Congressional Research Service
53
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
there will be some work required to make these for the Coast Guard. But with that said, it
is the commandant’s position and our position we will certainly consider this and work to
see what makes sense to bridge this gap.”109
July 2017 National Academies (NASEM) Report
A July 2017 report on the acquisition and operation of polar icebreakers by the National
Academies of Sciences, Engineering, and Medicine (NASEM) that was directed by Congress in
Section 604 of the Coast Guard Authorization Act of 2015 (H.R. 4188/P.L. 114-120 of February
8, 2016) concluded the following:
INTRODUCTION
The United States has strategic national interests in the polar regions. In the Arctic, the
nation must protect its citizens, natural resources, and economic interests; assure
sovereignty, defense readiness, and maritime mobility; and engage in discovery and
research. In the Antarctic, the United States must maintain an active presence that includes
access to its research stations for the peaceful conduct of science and the ability to
participate in inspections as specified in the Antarctic Treaty. The committee’s charge...
was to advise the U.S. House of Representatives and the U.S. Senate on an assessment of
the costs incurred by the federal government in carrying out polar icebreaking missions
and on options that could minimize lifecycle costs. The committee’s consensus findings
and recommendations are presented below. Unless otherwise specified, all estimated costs
and prices for the future U.S. icebreakers are expressed in 2019 dollars, since that is the
year in which the contracts are scheduled to be made. Supporting material is found in the
appendices.
FINDINGS AND RECOMMENDATIONS
1. Finding: The United States has insufficient assets to protect its interests, implement
U.S. policy, execute its laws, and meet its obligations in the Arctic and Antarctic
because it lacks adequate icebreaking capability.
For more than 30 years, studies have emphasized the need for U.S. icebreakers to maintain
presence, sovereignty, leadership, and research capacity—but the nation has failed to
respond.... The strong warming and related environmental changes occurring in both the
Arctic and the Antarctic have made this failure more critical. In the Arctic, changing sea
ice conditions will create greater navigation hazards for much of the year, and expanding
human industrial and economic activity will magnify the need for national presence in the
region. In the Antarctic, sea ice trends have varied greatly from year to year, but the annual
requirements for access into McMurdo Station have not changed. The nation is ill-equipped
to protect its interests and maintain leadership in these regions and has fallen behind other
Arctic nations, which have mobilized to expand their access to ice-covered regions. The
United States now has the opportunity to move forward and acquire the capability to fulfill
these needs....
2. Recommendation: The United States Congress should fund the construction of four
polar icebreakers of common design that would be owned and operated by the United
States Coast Guard (USCG).
The current Department of Homeland Security (DHS) Mission Need Statement (DHS
2013) contemplates a combination of medium and heavy icebreakers. The committee’s
recommendation is for a single class of polar icebreaker with heavy icebreaking capability.
Proceeding with a single class means that only one design will be needed, which will
109 Cal Biesecker, “Senator Says Decision Could Come Soon to Lease Icebreakers for Coast Guard,” Defense Daily,
December 16, 2020. See also Liz Ruskin, “Trump Administration May Hire Private Ship to Fill Arctic ‘Icebreaker
Gap’ by Year’s End,” Alaska Public Radio, December 14, 2020.
Congressional Research Service
54
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
provide cost savings. The committee has found that the fourth heavy icebreaker could be
built for a lower cost than the lead ship of a medium icebreaker class....
The DHS Mission Need Statement contemplated a total fleet of “potentially” up to six ships
of two classes—three heavy and three medium icebreakers. Details appear in the High
Latitude Mission Analysis Report. The Mission Need Statement indicated that to fulfill its
statutory missions, USCG required three heavy and three medium icebreakers; each vessel
would have a single crew and would homeport in Seattle. The committee’s analysis
indicated that four heavy icebreakers will meet the statutory mission needs gap identified
by DHS for the lowest cost. Three of the ships would allow continuous presence in the
Arctic, and one would service the Antarctic.
As noted in the High Latitude Report, USCG’s employment standard is 185 days away
from home port (DAFHP) for a single crew. Three heavy icebreakers in the Arctic provide
555 DAFHP, sufficient for continuous presence. In addition, the medium icebreaker USCG
Cutter Healy’s design service life runs through 2030. If greater capacity is required, USCG
could consider operating three ships with four crews, which would provide 740 DAFHP.
The use of multiple crews in the Arctic could require fewer ships while providing a
comparable number of DAFHP. For example, two ships (instead of the recommended
three) operating in the Arctic with multiple crews could provide a similar number of annual
operating days at a lower cost, but such an arrangement may not permit simultaneous
operations in both polar regions and may not provide adequate redundancy in capability.
More important, an arrangement under which fewer boats are operated more often would
require more major maintenance during shorter time in port, often at increasing cost. In
addition, if further military presence is desired in the Arctic, USCG could consider ice-
strengthening the ninth national security cutter.
One heavy icebreaker servicing the Antarctic provides for the McMurdo breakout and
international treaty verification. The availability of the vessel could be extended by
homeporting in the Southern Hemisphere. If the single vessel dedicated to the Antarctic is
rendered inoperable, USCG could redirect an icebreaker from the Arctic, or it could rely
on support from other nations. The committee considers both options to be viable and
believes it difficult to justify a standby (fifth) vessel for the Antarctic mission when the
total acquisition and lifetime operating costs of a single icebreaker are projected to exceed
$1.6 billion. Once the four new icebreakers are operational, USCG can reasonably be
expected to plan for more distant time horizons. USCG could assess the performance of
the early ships once they are operational and determine whether additional capacity is
needed.
USCG is the only agency of the U.S. government that is simultaneously a military service,
a law enforcement agency, a marine safety and rescue agency, and an environmental
protection agency. All of these roles are required in the mission need statement for a polar
icebreaker. USCG, in contrast to a civilian company, has the authorities, mandates, and
competencies to conduct the missions contemplated for the polar icebreakers. Having one
agency with a multimission capability performing the range of services needed would be
more efficient than potentially duplicating effort by splitting polar icebreaker operations
among other agencies.
The requirement for national presence is best accomplished with a military vessel. In
addition, USCG is fully interoperable with the U.S. Navy and the nation’s North Atlantic
Treaty Organization partners. USCG is already mandated to operate the nation’s domestic
and polar icebreakers. Continuing to focus this expertise in one agency remains the logical
approach....
Government ownership of new polar icebreakers would be less costly than the use of lease
financing (see Appendix C). The government has a lower borrowing cost than any U.S.-
based leasing firm or lessor. In addition, the lessor would use higher-cost equity (on which
it would expect to make a profit) to cover a portion of the lease financing. The committee’s
Congressional Research Service
55
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
analysis shows that direct purchase by the government would cost, at a minimum, 19
percent less than leasing on a net present value basis (after tax). There is also the risk of
the lessor going bankrupt and compromising the availability of the polar icebreaker to
USCG. For its analysis, the committee not only relied on its extensive experience with
leveraged lease financing but also reviewed available Government Accountability Office
reports and Office of Management and Budget rules, examined commercial leasing
economics and current interest rates, and validated its analysis by consulting an outside
expert on the issue....
Chartering (an operating lease) is not a viable option.... The availability of polar icebreakers
on the open market is extremely limited. (The committee is aware of the sale of only one
heavy icebreaker since 2010.) U.S. experience with chartering a polar icebreaker for the
McMurdo resupply mission has been problematic on two prior charter attempts. Chartering
is workable only if the need is short term and mission specific. The committee notes that
chartering may preclude USCG from performing its multiple missions....
In the committee’s judgment, an enlarged icebreaker fleet will provide opportunities for
USCG to strengthen its icebreaking program and mission. Although the number of billets
that require an expert is small compared with the overall number of billets assigned to these
icebreakers, more people performing this mission will increase the pool of experienced
candidates. This will provide personnel assignment officers with a larger pool of candidates
when the more senior positions aboard icebreakers are designated, which will make
icebreaking more attractive as a career path and increase the overall level of icebreaking
expertise within USCG. Importantly, the commonality of design of the four recommended
heavy icebreakers will reduce operating and maintenance costs over the service life of these
vessels through efficiencies in supporting and crewing them. Having vessels of common
design will likely improve continuity of service, build icebreaking competency, improve
operational effectiveness, and be more cost-efficient....
3. Recommendation: USCG should follow an acquisition strategy that includes block
buy contracting with a fixed price incentive fee contract and take other measures to
ensure best value for investment of public funds.
Icebreaker design and construction costs can be clearly defined, and a fixed price incentive
fee construction contract is the most reliable mechanism for controlling costs for a program
of this complexity. This technique is widely used by the U.S. Navy. To help ensure best
long-term value, the criteria for evaluating shipyard proposals should incorporate explicitly
defined lifecycle cost metrics....
A block buy authority for this program will need to contain specific language for economic
order quantity purchases for materials, advanced design, and construction activities. A
block buy contracting program with economic order quantity purchases enables series
construction, motivates competitive bidding, and allows for volume purchase and for the
timely acquisition of material with long lead times. It would enable continuous production,
give the program the maximum benefit from the learning curve, and thus reduce labor hours
on subsequent vessels.
The acquisition strategy would incorporate (a) technology transfer from icebreaker
designers and builders with recent experience, including international expertise in design,
construction, and equipment manufacture; (b) a design that maximizes use of commercial
off-the-shelf (COTS) equipment, applies Polar Codes and international standards, and only
applies military specifications (MIL-SPEC) to the armament, aviation, communications,
and navigation equipment; (c) reduction of any “buy American” provisions to allow the
sourcing of the most
suitable and reliable machinery available on the market; and (d) a program schedule that
allows for completion of design and planning before the start of construction. These
Congressional Research Service
56
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
strategies will allow for optimization of design, reduce construction costs, and enhance
reliability and maintainability....
4. Finding: In developing its independent concept designs and cost estimates, the
committee determined that the costs estimated by USCG for the heavy icebreaker are
reasonable. However, the committee believes that the costs of medium icebreakers
identified in the High Latitude Mission Analysis Report are significantly
underestimated.
The committee estimates the rough order-of-magnitude (ROM) cost of the first heavy
icebreaker to be $983 million. (See Appendix D, Table D-6.) Of these all-in costs, 75 to 80
percent are shipyard design and construction costs; the remaining 20 to 25 percent cover
government-incurred costs such as government-furnished equipment and government-
incurred program expenses. If advantage is taken of learning and quantity discounts
available through the recommended block buy contracting acquisition strategy, the average
cost per heavy icebreaker is approximately $791 million, on the basis of the acquisition of
four ships. The committee’s analysis of the ship size to incorporate the required
components (stack-up length) suggests an overall length of 132 meters (433 feet) and a
beam of 27 meters (89 feet). This is consistent with USCG concepts for the vessel.
Costs can be significantly reduced by following the committee’s recommendations.
Reduction of MIL-SPEC requirements can lower costs by up to $100 million per ship with
no loss of mission capability.... The other recommended acquisition, design, and
construction strategies will control possible cost overruns and provide significant savings
in overall life-cycle costs for the program.
Although USCG has not yet developed the operational requirements document for a
medium polar icebreaker, the committee was able to apply the known principal
characteristics of the USCG Cutter Healy to estimate the scope of work and cost of a similar
medium icebreaker. The committee estimates that a first-of-class medium icebreaker will
cost approximately $786 million. The fourth ship of the heavy icebreaker series is
estimated to cost $692 million. Designing a medium-class polar icebreaker in a second
shipyard would incur the estimated engineering, design, and planning costs of $126 million
and would forgo learning from the first three ships; the learning curve would be restarted
with the first medium design. Costs of building the fourth heavy icebreaker would be less
than the costs of designing and building a first-of-class medium icebreaker... . In
developing its ROM cost estimate, the committee agreed on a common notional design and
basic assumptions.... Two committee members then independently developed cost
estimating models, which were validated internally by other committee members. These
analyses were then used to establish the committee’s primary cost estimate....
5. Finding: Operating costs of new polar icebreakers are expected to be lower than
those of the vessels they replace.
The committee expects the operating costs for the new heavy polar icebreakers to be lower
than those of USCG’s Polar Star. While USCG’s previous experience is that operating
costs of new cutters are significantly higher than those of the vessels they replace, the
committee does not believe this historical experience applies in this case. There is good
reason to believe that operating costs for new ships using commercially available modern
technology will be lower than costs for existing ships.... The more efficient hull forms and
modern engines will reduce fuel consumption, and a well-designed automation plant will
require fewer operation and maintenance personnel, which will allow manning to be
reduced or freed up for alternative tasks. The use of COTS technology and the
minimization of MIL-SPEC, as recommended, will also reduce long-term maintenance
costs, since use of customized equipment to meet MIL-SPEC requirements can reduce
reliability and increase costs. A new vessel, especially over the first 10 years, typically has
significantly reduced major repair and overhaul costs, particularly during dry-dock periods,
compared with existing icebreakers—such as the Polar Star—that are near or at the end of
Congressional Research Service
57
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
their service life.... The Polar Star has many age-related issues that require it to be
extensively repaired at an annual dry-docking. These issues will be avoided in the early
years of a new ship. However, the committee recognizes that new ship operating costs can
be higher than those of older ships if the new ship has more complexity to afford more
capabilities. Therefore, any direct comparisons of operating costs of newer versus older
ships would need to take into account the benefits of the additional capabilities provided
by the newer ship.
USCG will have an opportunity to evaluate the manning levels of the icebreaker in light of
the benefits of modern technology to identify reductions that can be made in operating
costs....
6. Recommendation: USCG should ensure that the common polar icebreaker design
is science-ready and that one of the ships has full science capability.
All four proposed ships would be designed as “science-ready,” which will be more cost-
effective when one of the four ships—most likely the fourth—is made fully science
capable. Including science readiness in the common polar icebreaker design is the most
cost-effective way of fulfilling both the USCG’s polar missions and the nation’s scientific
research polar icebreaker needs.... The incremental costs of a science-ready design for each
of the four ships ($10 million to $20 million per ship) and of full science capability for one
of the ships at the initial build (an additional $20 million to $30 million) are less than the
independent design and build cost of a dedicated research medium icebreaker.... In
briefings at its first meeting, the committee learned that the National Science Foundation
and other agencies do not have budgets to support full-time heavy icebreaker access or the
incremental cost of design, even though their science programs may require this capability.
Given the small incremental cost, the committee believes that the science capability cited
above should be included in the acquisition costs.
Science-ready design includes critical elements that cannot be retrofitted cost-effectively
into an existing ship and that should be incorporated in the initial design and build. Among
these elements are structural supports, appropriate interior and exterior spaces, flexible
accommodation spaces that can embark up to 50 science personnel, a hull design that
accommodates multiple transducers and minimizes bubble sweep while optimizing
icebreaking capability, machinery arrangements and noise dampening to mitigate
interference with sonar transducers, and weight and stability latitudes to allow installation
of scientific equipment. Such a design will enable any of the ships to be retrofitted for full
science capability in the future, if necessary....
Within the time frame of the recommended build sequence, the United States will require
a science-capable polar icebreaker to replace the science capabilities of the Healy upon her
retirement. To fulfill this need, one of the heavy polar icebreakers would be procured at the
initial build with full science capability; the ability to fulfill other USCG missions would
be retained. The ship would be outfitted with oceanographic overboarding equipment and
instrumentation and facilities comparable with those of modern oceanographic research
vessels. Some basic scientific capability, such as hydrographic mapping sonar, should be
acquired at the time of the build of each ship so that environmental data that are essential
in fulfilling USCG polar missions can be collected.
7. Finding: The nation is at risk of losing its heavy polar icebreaking capability—
experiencing a critical capacity gap—as the Polar Star approaches the end of its
extended service life, currently estimated at 3 to 7 years.
The Polar Star, built in 1976, is well past its 30-year design life. Its reliability will continue
to decline, and its maintenance costs will continue to escalate. Although the ship went
through an extensive life-extending refit in 2011–2012, the Polar Star’s useful life is
estimated to end between 2020 and 2024. As USCG has recognized, the evaluation of
Congressional Research Service
58
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
alternative arrangements to secure polar icebreaking capacity is important, given the
growing risks of the Polar Star losing its capability to fulfill its mission....
8. Recommendation: USCG should keep the Polar Star operational by implementing
an enhanced maintenance program (EMP) until at least two new polar icebreakers
are commissioned.
Even if the committee’s notional schedule for new polar icebreakers is met, the second
polar icebreaker would not be ready until July 2025.... The committee’s proposed EMP
could be designed with planned—and targeted—upgrades that allow the Polar Star to
operate every year for its Antarctic mission. The necessary repairs could be performed in
conjunction with the ship’s current yearly dry-docking schedule within existing annual
expenditures, estimated to average $5 million. In particular, the EMP would require
improvements in the ship’s operating systems, sanitary system, evaporators, main
propulsion systems, and controllable pitch propellers. In the committee’s judgment, the
EMP could be accomplished within USCG’s average annual repair expenditures for the
Polar Star, which currently range between $2 million and $9 million.110
June 2013 DHS Polar Icebreaker Mission Need Statement
DHS in June 2013 approved a Mission Need Statement (MNS) for the polar icebreaker
recapitalization project. The MNS states the following (emphasis added):
This Mission Need Statement (MNS) establishes the need for polar icebreaker capabilities
provided by the Coast Guard, to ensure that it can meet current and future mission
requirements in the polar regions....
Current requirements and future projections based upon cutter demand modeling, as
detailed in the HLMAR [High Latitude Mission Analysis Report], indicate the Coast
Guard will need to expand its icebreaking capacity, potentially requiring a fleet of up
to six icebreakers (3 heavy and 3 medium) to adequately meet mission demands in the
high latitudes.... The analysis took into account both the Coast Guard statutory mission
requirements and additional requirements for year-round presence in both polar regions
detailed in the Naval Operations Concept (NOC) 2010.... The analysis also evaluated
employing single and multi-crewing concepts.... Strategic home porting analysis based
upon existing infrastructure and distance to operational areas provided the final input to
determine icebreaker capacity demand.111
While the MNS can be viewed as an authoritative U.S. government statement regarding required
numbers of U.S. polar icebreakers, it can be noted that the key sentence in the above-quoted
passage from the MNS (i.e., the sentence in bold) includes the terms “potentially” and “up to.”
These terms, which are often overlooked in discussions of required numbers of U.S. polar
icebreakers, make the key sentence less ironclad as a requirements statement than it would have
been if the terms had not been included, and could be interpreted as an acknowledgment that the
requirement might amount to something less than three heavy and three medium polar
icebreakers.
It can also be noted, as stated in the above-quoted passage from the MNS, that the MNS was
informed by the High Latitude Mission Analysis Report (HILMAR), and that the HLMAR took
into account not only Coast Guard statutory mission requirements, but additional DOD
110 National Academies of Sciences, Engineering, and Medicine, Division on Earth and Life Studies and Transportation
Research Board, Acquisition and Operation of Polar Icebreakers: Fulfilling the Nation’s Needs, Letter Report, with
cover letter dated July 11, 2017, pp. 9-20.
111 Department of Homeland Security, Polar Icebreaking Recapitalization Project Mission Need Statement, Version
1.0, approved by DHS June 28, 2013, pp. 1, 2, 9, 10, 11, 12.
Congressional Research Service
59
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
requirements for year-round presence in both polar regions as detailed in the 2010 Naval
Operations Concept (NOC). This is potentially significant, because DOD appears to have
subsequently dropped its 2010 requirement for year-round presence in the polar regions.112
The use in the MNS of the terms “potentially” and “up to,” combined with DOD’s decision to
drop its requirement for year-round presence in the polar regions, together raise a question, other
things held equal, as to whether required numbers of U.S. polar icebreakers might be something
less than three heavy and three medium polar icebreakers. It is also possible, however, that there
have been other changes since the MNS was issued in 2013 that would have the effect, other
things held equal, of increasing U.S. requirements for polar icebreakers. The net result of this
situation appears uncertain.
In recent years, Coast Guard officials have tended to refer simply to a total Coast Guard
requirement for three heavy and three medium polar icebreakers. For example, in the October 25,
2016, summary of an RFI that the Coast Guard released the next day to receive industry feedback
on its notional polar icebreaker acquisition approach and schedule, the Coast Guard states that
“the United States Coast Guard has a need for three Heavy Polar Icebreakers and three Medium
Polar Icebreakers with the priority being Heavy Polar Icebreakers.”113 A requirement for three
heavy and three medium polar icebreakers is often abbreviated as 3+3.
Short of a 3+3 requirement, Coast Guard officials in the past have sometimes stated that, as a bare
minimum number of heavy polar icebreakers, the Coast Guard needs two such ships. For
example, at a November 17, 2015, hearing before the Europe, Eurasia, and Emerging Threats
subcommittee and the Western Hemisphere subcommittee of the House Foreign Affairs
Committee, then-Vice Admiral Charles Michel, the Vice Commandant of the Coast Guard, stated
during the discussion portion of the hearing that the “Coast Guard needs at least two heavy
icebreakers to provide year-round assured access and self-rescueability in the polar regions.”114
Similarly, at a June 14, 2016, hearing before the Coast Guard and Maritime Transportation
subcommittee of the House Transportation and Infrastructure Committee, Admiral Michel
testified that “our commandant also testified that we need self-rescue capability for our heavy
icebreaker and that includes the existing Polar Star that we have out there now. So that means at
112 A September 25, 2017, GAO report on polar icebreakers states the following (emphasis added):
In December 2016, DOD reported to Congress that it had no specific defense requirement for
icebreaking capability because Navy Arctic requirements are met by undersea and air assets which
can provide year-round presence.
—DOD reported in April 2017 that its only potential defense requirement—for the Thule Air Force
Base resupply [mission] in Greenland—is met by the Canadian Coast Guard through a
Memorandum of Understanding with USCG.
—USCG’s 2013 Polar Icebreaker Mission Needs Statement identified polar icebreaker capacity
needs as partly based on the 2010 Naval Operations Concept—[a document that provides] joint
maritime security strategy implementation guidance for the Navy, Marine Corps, and USCG—
which stated that U.S. naval forces had a demand for year-round polar icebreaking presence in the
Arctic and Antarctic.
—In April 2017, DOD joint staff officials confirmed that DOD and Naval defense strategy had
been updated and does not include icebreaking requirements. DOD officials in charge of operations
in the Pacific said that although they do not have a requirement for a heavy icebreaker, icebreakers
play a key role in aiding the icebreaking mission to McMurdo.
(GAO, Coast Guard: Status of Polar Icebreaking Fleet Capability and Recapitalization Plan,
GAO-17-698R, September 25, 2017, p. 20 (briefing slide 11).)
113 Summary of RFI, October 25, 2016, page 2, accessed November 10, 2016, at https://www.uscg.mil/acquisition/
icebreaker/pdf/Acquisition-Strategy-RFI.pdf.
114 Transcript of hearing.
Congressional Research Service
60
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
least two [ships], [and] the High Latitude study says three heavy polar icebreakers is what the
Coast Guard’s requirement is. So that’s kind of where we’re talking about for heavy
icebreakers.”115
A September 25, 2017, GAO report on polar icebreakers states that
the Coast Guard has been unable to address all polar icebreaking requests since 2010. For
example, the Coast Guard reported fulfilling 78 percent (25 of 32) of U.S. government
agency requests for polar icebreaking services during fiscal year 2010 through 2016. Coast
Guard officials cited various factors affecting the Coast Guard’s ability to meet all requests,
particularly the unavailability of its heavy polar icebreakers.116
A July 2018 GAO report stated that
the Coast Guard operates one medium icebreaker, the Healy, which has an expected end of
service life in 2029. Despite the requirement for three medium icebreakers, Coast Guard
officials said they are not currently assessing acquisition of the medium polar icebreakers
because they are focusing on the heavy icebreaker acquisition and plan to assess the costs
and benefits of acquiring medium polar icebreakers at a later time.117
In addition to the HILMAR, a number of other studies have been conducted in recent years to
assess U.S. requirements for polar icebreakers and options for sustaining and modernizing the
Coast Guard’s polar icebreaker fleet.
Coast Guard High Latitude Study Provided to Congress in
July 2011
In July 2011, the Coast Guard provided to Congress a study on the Coast Guard’s missions and
capabilities for operations in high-latitude (i.e., polar) areas. The study, commonly known as the
High Latitude Study, is dated July 2010 on its cover. The High Latitude Study concluded the
following:
[The study] concludes that future capability and capacity gaps will significantly impact
four [Coast Guard] mission areas in the Arctic: Defense Readiness, Ice Operations, Marine
Environmental Protection, and Ports, Waterways, and Coastal Security. These mission
areas address the protection of important national interests in a geographic area where other
nations are actively pursuing their own national goals....
The common and dominant contributor to these significant mission impacts is the gap in
polar icebreaking capability. The increasing obsolescence of the Coast Guard’s icebreaker
fleet will further exacerbate mission performance gaps in the coming years....
The gap in polar icebreaking capacity has resulted in a lack of at-sea time for crews and
senior personnel and a corresponding gap in training and leadership. In addition to
providing multi-mission capability and intrinsic mobility, a helicopter-capable surface unit
would eliminate the need for acquiring an expensive shore-based infrastructure that may
only be needed on a seasonal or occasional basis. The most capable surface unit would be
a polar icebreaker. Polar icebreakers can transit safely in a variety of ice conditions and
have the endurance to operate far from logistics bases. The Coast Guard’s polar icebreakers
have conducted a wide range of planned and unscheduled Coast Guard missions in the past.
115 Transcript of hearing.
116 GAO, Coast Guard: Status of Polar Icebreaking Fleet Capability and Recapitalization Plan, GAO-17-698R,
September 25, 2017, pp. 2-3. A similar statement appears on page 4.
117 GAO, Coast Guard Acquisitions[:] Actions Needed to Address Longstanding Portfolio Management Challenges,
GAO-18-454, July 2018, p. 13.
Congressional Research Service
61
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Polar icebreakers possess the ability to carry large numbers of passengers, cargo, boats,
and helicopters. Polar icebreakers also have substantial command, control, and
communications capabilities. The flexibility and mobility of polar icebreakers would assist
the Coast Guard in closing future mission performance gaps effectively....
Existing capability and capacity gaps are expected to significantly impact future Coast
Guard performance in two Antarctic mission areas: Defense Readiness and Ice Operations.
Future gaps may involve an inability to carry out probable and easily projected mission
requirements, such as the McMurdo resupply, or readiness to respond to less-predictable
events. By their nature, contingencies requiring the use of military capabilities often occur
quickly. As is the case in the Arctic, the deterioration of the Coast Guard’s icebreaker fleet
is the primary driver for this significant mission impact. This will further widen mission
performance gaps in the coming years. The recently issued Naval Operations Concept 2010
requires a surface presence in both the Arctic and Antarctic. This further exacerbates the
capability gap left by the deterioration of the icebreaker fleet....
The significant deterioration of the Coast Guard icebreaker fleet and the emerging mission
demands to meet future functional requirements in the high latitude regions dictate that the
Coast Guard acquire material solutions to close the capability gaps....
To meet the Coast Guard mission functional requirement, the Coast Guard icebreaking
fleet must be capable of supporting the following missions:
• Arctic North Patrol. Continuous multimission icebreaker presence in the Arctic.
• Arctic West Science. Spring and summer science support in the Arctic.
• Antarctic, McMurdo Station resupply. Planned deployment for break-in, supply
ship escort, and science support. This mission, conducted in the Antarctic summer,
also requires standby icebreaker support for backup in the event the primary vessel
cannot complete the mission.
• Thule Air Base Resupply and Polar Region Freedom of Navigation Transits.
Provide vessel escort operations in support of the Military Sealift Command’s
Operation Pacer Goose; then complete any Freedom of Navigation exercises in the
region.
In addition, the joint Naval Operations Concept establishes the following mission
requirements:
• Assured access and assertion of U.S. policy in the Polar Regions. The current
demand for this mission requires continuous icebreaker presence in both Polar
Regions.
Considering these missions, the analysis yields the following findings:
• The Coast Guard requires three heavy and three medium icebreakers to fulfill
its statutory missions. These icebreakers are necessary to (1) satisfy Arctic winter
and transition season demands and (2) provide sufficient capacity to also execute
summer missions. Single-crewed icebreakers have sufficient capacity for all current
and expected statutory missions. Multiple crewing provides no advantage because the
number of icebreakers required is driven by winter and shoulder season requirements.
Future use of multiple or augmented crews could provide additional capacity needed
to absorb mission growth.
• The Coast Guard requires six heavy and four medium icebreakers to fulfill its
statutory missions and maintain the continuous presence requirements of the
Naval Operations Concept. Consistent with current practice, these icebreakers are
single-crewed and homeported in Seattle Washington.
Congressional Research Service
62
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
• Applying crewing and home porting alternatives reduces the overall requirement
to four heavy and two medium icebreakers. This assessment of nonmaterial
solutions shows that the reduced number of icebreakers can be achieved by having all
vessels operate with multiple crews and two of the heavy icebreakers homeporting in
the Southern Hemisphere.
Leasing was also considered as a nonmaterial solution. While there is no dispute that the
Coast Guard’s polar icebreaker fleet is in need of recapitalization, the decision to acquire
this capability through purchase of new vessels, reconstruction of existing ships, or
commercial lease of suitable vessels must be resolved to provide the best value to the
taxpayer. The multi-mission nature of the Coast Guard may provide opportunities to
conduct some subset of its missions with non government-owned vessels. However,
serious consideration must be given to the fact that the inherently governmental missions
of the Coast Guard must be performed using government-owned and operated vessels. An
interpretation of the national policy is needed to determine the resource level that best
supports the nation’s interests....
The existing icebreaker capacity, two inoperative heavy icebreakers and an operational
medium icebreaker, does not represent a viable capability to the federal government. The
time needed to augment this capability is on the order of 10 years. At that point, around
2020, the heavy icebreaking capability bridging strategy expires.118
At a July 27, 2011, hearing on U.S. economic interests in the Arctic before the Oceans,
Atmosphere, Fisheries, and Coast Guard subcommittee of the Senate Commerce, Science, and
Transportation Committee, the following exchange occurred:
SENATOR OLYMPIA J. SNOWE: On the high latitude study, do you agree with—and
those—I would like to also hear from you, Admiral Titley, as well, on these requirements
in terms of Coast Guard vessels as I understand it, they want to have—I guess, it was a
three medium ice breakers. Am in correct in saying that? Three medium ice breakers.
ADMIRAL ROBERT PAPP, COMMANDANT OF THE COAST GUARD: I agree with
the mission analysis and as you look at the requirements for the things that we might do up
there, if it is in the nation’s interest, it identifies a minimum requirement for three heavy
ice breakers and three medium ice breakers and then if you want a persistent presence up
there, it would require—and also doing things such as breaking out (inaudible) and other
responsibilities, then it would take up to a maximum six heavy and four medium.
SNOWE: Right. Do you agree with that?
PAPP: If we were to be charged with carrying out those full responsibilities, yes, ma’am.
Those are the numbers that you would need to do it.
SNOWE: Admiral Titley, how would you respond to the high latitude study and has the
Navy conducted its own assessment of its capability?
REAR ADMIRAL DAVID TITLEY, OCEANORGRAPHER AND NAVIGATOR OF
THE NAVY: Ma’am, we are in the process right now of conducting what we call a
capabilities based assessment that will be out in the summer of this year.
We are getting ready to finish that—the Coast Guard has been a key component of the
Navy’s task force on climate change, literally since day one when the Chief of Naval
Operations set this up, that morning, we had the Coast Guard invited as a member of our
executive steering committee.
118 United States Coast Guard High Latitude Region Mission Analysis Capstone Summary, July 2010, pp. 10-13, 15.
Congressional Research Service
63
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
So we have been working very closely with the Coast Guard, with the Department of
Homeland Security, and I think Admiral Papp—said it best as far as the specific comments
on the high latitude study but we have been working very closely with the Coast Guard.119
January 2011 DHS Office of Inspector General Report
A January 2011 report on the Coast Guard’s polar icebreakers from the DHS Office of the
Inspector General stated the following:
The Coast Guard does not have the necessary budgetary control over its [polar] icebreakers,
nor does it have a sufficient number of icebreakers to accomplish its missions in the Polar
Regions. Currently, the Coast Guard has only one operational [polar] icebreaker [i.e.,
Healy], making it necessary for the United States to contract with foreign nations to
perform scientific, logistical, and supply activities. Without the necessary budgetary
control and a sufficient number of icebreaking assets, the Coast Guard will not have the
capability to perform all of its missions, will lose critical icebreaking expertise, and may
be beholden to foreign nations to perform its statutory missions. The Coast Guard should
improve its strategic approach to ensure that it has the long-term icebreaker capabilities
needed to support Coast Guard missions and other national interests in the Arctic and
Antarctic regions.120
Regarding current polar icebreaking capabilities for performing Arctic missions, the report states
the following:
The Coast Guard’s icebreaking resources are unlikely to meet future demands. [The table
below] outlines the missions that Coast Guard is unable to meet in the Arctic with its
current icebreaking resources.
Arctic Missions Not Being Met
Requesting Agency
Missions Not Being Met
United States Coast Guard
—Fisheries enforcement in Bering Sea
to prevent foreign fishing in U.S.
waters and overfishing
—Capability to conduct search and
rescue in Beaufort Sea for cruise line
and natural resource exploration ships
—Future missions not anticipated to
be met: 2010 Arctic Winter Science
Deployment
NASA
Winter access to the Arctic to conduct
oceanography and study Arctic
currents and how they relate to
regional ice cover, climate, and
biology
NOAA and NSF
Winter research
119 Source: Transcript of hearing.
120 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance,
Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 1 (Executive Summary). Report accessed September
21, 2011, at https://www.oig.dhs.gov/assets/Mgmt/OIG_11-31_Jan11.pdf.
Congressional Research Service
64
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Department of Defense
Assured access to ice-impacted waters
through a persistent icebreaker
presence in the Arctic and Antarctic121
The report also states the following:
Should the Coast Guard not obtain funding for new icebreakers or major service life
extensions for its existing icebreakers with sufficient lead-time, the United States will have
no heavy icebreaking capability beyond 2020 and no polar icebreaking capability of any
kind by 2029. Without the continued use of icebreakers, the United States will lose its
ability to maintain a presence in the Polar Regions, the Coast Guard’s expertise to perform
ice operations will continue to diminish, and missions will continue to go unmet.122
Regarding current polar icebreaking capabilities for performing Antarctic missions, the report
states the following:
The Coast Guard needs additional icebreakers to accomplish its missions in the Antarctic.
The Coast Guard has performed the McMurdo Station resupply in Antarctica for decades,
but with increasing difficulty in recent years. The Coast Guard’s two heavy-duty
icebreakers [i.e., Polar Star and Polar Sea] are at the end of their service lives, and have
become less reliable and increasingly costly to keep in service....
In recent years, the Coast Guard has found that ice conditions in the Antarctic have become
more challenging for the resupply of McMurdo Station. The extreme ice conditions have
necessitated the use of foreign vessels to perform the McMurdo break-in....
As ice conditions continue to change around the Antarctic, two icebreakers are needed for
the McMurdo break-in and resupply mission. Typically, one icebreaker performs the break-
in and the other remains on standby. Should the first ship become stuck in the ice or should
the ice be too thick for one icebreaker to complete the mission, the Coast Guard deploys
the ship on standby. Since the Polar Sea and Polar Star are not currently in service, the
Coast Guard has no icebreakers capable of performing this mission. [The table below]
outlines the missions that will not be met without operational heavy-duty icebreakers.
Arctic Missions Not Being Met
Requesting Agency
Missions Not Being Met
NSF
Missions not anticipated to be met: 2010-2011
Operation Deep Freeze – McMurdo Station
Resupply
Department of State
Additional inspections of foreign facilities in
Antarctica to enforce the Antarctic Treaty and
ensure facilities’ environment compliance123
The report’s conclusion and recommendations were as follows:
Conclusion
121 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance,
Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 9.
122 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance,
Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 10.
123 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance,
Upgrade, and Acquisition Program, OIG-11-31, January 2011, pp. 10-11.
Congressional Research Service
65
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
With an aging fleet of three icebreakers, one operational and two beyond their intended 30-
year service life, the Coast Guard is at a critical crossroads in its Polar Icebreaker
Maintenance, Upgrade, and Acquisition Program. It must clarify its mission requirements,
and if the current mission requirements remain, the Coast Guard must determine the best
method for meeting these requirements in the short and long term.
Recommendations
We recommend that the Assistant Commandant for Marine Safety, Security, and
Stewardship:
Recommendation #1: Request budgetary authority for the operation, maintenance, and
upgrade of its icebreakers.
Recommendation #2: In coordination with the Department of Homeland Security, request
clarification from Congress to determine whether Arctic missions should be performed by
Coast Guard assets or contracted vessels.
Recommendation #3: In coordination with the Department of Homeland Security, request
clarification from Congress to determine whether Antarctic missions should be performed
by Coast Guard assets or contracted vessels.
Recommendation #4: Conduct the necessary analysis to determine whether the Coast
Guard should replace or perform service-life extensions on its two existing heavy-duty
icebreaking ships.
Recommendation #5: Request appropriations necessary to meet mission requirements in
the Arctic and Antarctic.124
The report states that
The Coast Guard concurred with all five of the recommendations and is initiating corrective
actions. We consider the recommendations open and unresolved. The Coast Guard
provided information on some of its ongoing projects that will address the program needs
identified in the report.125
2010 U.S. Arctic Research Commission Report
A May 2010 report from the U.S. Arctic Research Commission (USARC) on goals and objectives
for Arctic research for 2009-2010 stated the following:
To have an effective Arctic research program, the United States must invest in human
capital, research platforms, and infrastructure, including new polar class icebreakers, and
sustained sea, air, land, space, and social observing systems.... The Commission urges the
President and Congress to commit to replacing the nation’s two polar class icebreakers.126
124 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance,
Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 12.
125 Department of Homeland Security, Office of Inspector General, The Coast Guard’s Polar Icebreaker Maintenance,
Upgrade, and Acquisition Program, OIG-11-31, January 2011, p. 13.
126 U.S. Arctic Research Commission, Report on Goals and Objectives for Arctic Research 2009-2010, May 2010, p. 4.
Accessed online December 5, 2011, at https://storage.googleapis.com/arcticgov-static/publications/goals/
usarc_goals_2009-10.pdf.
Congressional Research Service
66
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
2007 National Research Council Report
A 2007 National Research Council (NRC) report, Polar Icebreakers in a Changing World: An
Assessment of U.S. Needs, assessed roles and future needs for Coast Guard polar icebreakers.127
The study was required by report language accompanying the FY2005 DHS appropriations act
(H.R. 4567/P.L. 108-334).128 The study was completed in 2006 and published in 2007. Some
sources refer to the study as the 2006 NRC report. The report made the following conclusions and
recommendations:
Based on the current and future needs for icebreaking capabilities, the [study] committee
concludes that the nation continues to require a polar icebreaking fleet that includes a
minimum of three multimission ships [like the Coast Guard’s three current polar
icebreakers] and one single-mission [research] ship [like Palmer]. The committee finds that
although the demand for icebreaking capability is predicted to increase, a fleet of three
multimission and one single-mission icebreakers can meet the nation’s future polar
icebreaking needs through the application of the latest technology, creative crewing
models, wise management of ice conditions, and more efficient use of the icebreaker fleet
and other assets. The nation should immediately begin to program, design, and construct
two new polar icebreakers to replace the POLAR STAR and POLAR SEA.
Building only one new polar icebreaker is insufficient for several reasons. First, a single
ship cannot be in more than one location at a time. No matter how technologically advanced
or efficiently operated, a single polar icebreaker can operate in the polar regions for only a
portion of any year. An icebreaker requires regular maintenance and technical support from
shipyards and industrial facilities, must reprovision regularly, and has to effect periodic
crew changeouts. A single icebreaker, therefore, could not meet any reasonable standard
of active and influential presence and reliable, at-will access throughout the polar regions.
A second consideration is the potential risk of failure in the harsh conditions of polar
operations. Despite their intrinsic robustness, damage and system failure are always a risk
and the U.S. fleet must have enough depth to provide backup assistance. Having only a
single icebreaker would necessarily require the ship to accept a more conservative
operating profile, avoiding more challenging ice conditions because reliable assistance
127 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington,
2007, 122 pp.
128 H.R. 4567/P.L. 108-334 of October 18, 2004. The related Senate bill was S. 2537. The Senate report on S. 2537
(S.Rept. 108-280 of June 17, 2004) stated the following:
The Committee expects the Commandant to enter into an arrangement with the National Academy
of Sciences to conduct a comprehensive study of the role of Coast Guard icebreakers in supporting
United States operations in the Antarctic and the Arctic. The study should include different
scenarios for continuing those operations including service life extension or replacement of existing
Coast Guard icebreakers and alternative methods that do not use Coast Guard icebreakers. The
study should also address changes in the roles and missions of Coast Guard icebreakers in support
of future marine operations in the Arctic that may develop due to environmental change, including
the amount and kind of icebreaking support that may be required in the future to support marine
operations in the Northern Sea Route and the Northwest Passage; the suitability of the Polar Class
icebreakers for these new roles; and appropriate changes in existing laws governing Coast Guard
icebreaking operations and the potential for new operating regimes. The study should be submitted
to the Committee no later than September 30, 2005.
The conference report on H.R. 4567 (H.Rept. 108-774 of October 9, 2004) stated the following:
As discussed in the Senate report and the Coast Guard authorization bill for fiscal year 2005, the
conferees require the National Academy of Sciences to study the role of Coast Guard icebreakers.
The earlier House report on H.R. 4567 (H.Rept. 108-541 of June 15, 2004) contained language directing a similar
report from the Coast Guard rather than the National Academies. (See the passage in the House report under the header
“Icebreaking.”)
Congressional Research Service
67
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
would not be available. A second capable icebreaker, either operating elsewhere or in
homeport, would provide ensured backup assistance and allow for more robust operations
by the other ship.
From a strategic, longer-term perspective, two new Polar class icebreakers will far better
position the nation for the increasing challenges emerging in both polar regions. A second
new ship would allow the U.S. Coast Guard to reestablish an active patrol presence in U.S.
waters north of Alaska to meet statutory responsibilities that will inevitably derive from
increased human activity, economic development, and environmental change. It would
allow response to emergencies such as search-and-rescue cases, pollution incidents, and
assistance to ships threatened with grounding or damage by ice. Moreover, a second new
ship will leverage the possibilities for simultaneous operations in widely disparate
geographic areas (e.g., concurrent operations in the Arctic and Antarctic), provide more
flexibility for conducting Antarctic logistics (as either the primary or the secondary ship
for the McMurdo break-in), allow safer multiple-ship operations in the most demanding
ice conditions, and increase opportunities for international expeditions. Finally, an up-front
decision to build two new polar icebreakers will allow economies in the design and
construction process and provide a predictable cost reduction for the second ship....
The [study] committee finds that both operations and maintenance of the polar icebreaker
fleet have been underfunded for many years, and the capabilities of the nation’s icebreaking
fleet have diminished substantially. Deferred long-term maintenance and failure to execute
a plan for replacement or refurbishment of the nation’s icebreaking ships have placed
national interests in the polar regions at risk. The nation needs the capability to operate in
both polar regions reliably and at will. Specifically, the committee recommends the
following:
• The United States should continue to project an active and influential presence in the
Arctic to support its interests. This requires U.S. government polar icebreaking
capability to ensure year-round access throughout the region.
• The United States should continue to project an active and influential presence in the
Antarctic to support its interests. The nation should reliably control sufficient
icebreaking capability to break a channel into and ensure the maritime resupply of
McMurdo Station.
• The United States should maintain leadership in polar research. This requires
icebreaking capability to provide access to the deep Arctic and the ice-covered waters
of the Antarctic.
• National interests in the polar regions require that the United States immediately
program, budget, design, and construct two new polar icebreakers to be operated by
the U.S. Coast Guard.
• To provide continuity of U.S. icebreaking capabilities, the POLAR SEA should remain
mission capable and the POLAR STAR should remain available for reactivation until
the new polar icebreakers enter service.
• The U.S. Coast Guard should be provided sufficient operations and maintenance
budget to support an increased, regular, and influential presence in the Arctic. Other
agencies should reimburse incremental costs associated with directed mission tasking.
• Polar icebreakers are essential instruments of U.S. national policy in the changing
polar regions. To ensure adequate national icebreaking capability into the future, a
Congressional Research Service
68
Coast Guard Polar Security Cutter (Polar Icebreaker) Program
Presidential Decision Directive should be issued to clearly align agency responsibilities
and budgetary authorities.129
The Coast Guard stated in 2008 that it “generally supports” the NRC report, and that the Coast
Guard “is working closely with interagency partners to determine a way forward with national
polar policy that identifies broad U.S. interests and priorities in the Arctic and Antarctic that will
ensure adequate maritime presence to further these interests. Identification and prioritization of
U.S. national interests in these regions should drive development of associated USCG [U.S. Coast
Guard] capability and resource requirements.” The Coast Guard also stated the following: “Until
those broad U.S. interests and priorities are identified, the current USG [U.S. Government] polar
icebreaking fleet should be maintained in an operational status.”130
Author Information
Ronald O'Rourke
Specialist in Naval Affairs
Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.
129 National Research Council, Polar Icebreakers in a Changing World, An Assessment of U.S. Needs, Washington,
2007, pp. 2-3.
130 Coast Guard point paper provided to CRS on February 12, 2008, and dated with the same date, providing answers to
questions from CRS concerning polar icebreaker modernization.
Congressional Research Service
RL34391 · VERSION 261 · UPDATED
69