
 
Updated March 25, 2024
Coast Guard Waterways Commerce Cutter (WCC) Program: 
Background and Issues for Congress
Introduction 
rivers in question are referred to by the Coast Guard as the 
The Coast Guard’s Waterways Commerce Cutter (WCC) 
western rivers. 
program envisages procuring 30 replacements for the Coast 
Guard’s 35 aging river buoy tenders (WLRs), inland 
As of 2019, the 13 WLICs were based at cities along the 
construction tenders (WLICs), and inland buoy tenders 
U.S. East and Gulf coasts in Alabama, Florida (three 
(WLIs). The Coast Guard wants to have the first new WCC 
cutters), Louisiana (two cutters), Maryland, North Carolina, 
be in service by 2025. The Coast Guard’s proposed FY2025 
South Carolina, Texas (three cutters), and Virginia. As of 
budget requests $135.0 million in procurement funding for 
2019, the four WLIs were based at locations in Alaska, 
the program. The Coast Guard’s FY2025 unfunded 
Michigan, Oregon, and North Carolina. 
priorities list (UPL) includes an item for $40.0 million in 
additional procurement funding for accelerating WCC 
Rationale for Building New WCCs 
production. 
The Coast Guard states in its FY2025 budget submission 
that it wants to replace the 35 existing waterways cutters 
Terminology 
with new WCCs because “[i]n addition to age concerns and 
Cutters are Coast Guard vessels that are more than 65 feet 
the associated equipment obsolescence issues, the legacy 
long and have accommodations for a crew. (Those less than 
fleet presents other sustainment challenges, including 
65 feet long are called boats.) Waterways refers here to the 
hazardous materials stemming from the use of asbestos and 
intra-coastal waterways along the U.S. East and Gulf 
lead paint during construction of these assets. Outdated 
coasts, and to U.S. inland waterways such as the 
technology and vessel designs have also led to crew safety 
Mississippi River. Tenders are vessels whose primary 
concerns, maintenance cost increases, and non-compliance 
mission is to maintain or repair something. Coast Guard 
with environmental regulations. Finally, legacy vessel 
tender designations begin with WL, meaning Coast Guard 
configuration does not allow the assignment of mixed 
vessel (W) and tender (L). (The W in the acronym WCC, 
gender crews in accordance with the Coast Guard’s 
however, stands for waterways.) 
workforce goals.” 
WCC Missions 
WCC Program 
WCCs perform three primary missions under the Coast 
Guard’s statutory role of providing aids to navigation 
Program Initiation and Name 
(ATON): river buoy tending; inland construction tending 
The WCC program was initiated in the Coast Guard’s 
(which involves driving and removing piles and erecting 
FY2018 budget submission. It was earlier called the Inland 
and repairing range towers and major lights); and inland 
Waterways and Western Rivers Tender (or Cutter) program. 
buoy tending. WCCs are used for maintaining more than 
28,200 marine aids to navigation on 12,000 miles of inland 
Acquisition Strategy 
waterways on which 630 million tons of cargo move each 
The Coast Guard wants to replace the 35 existing waterway 
year. Additional WCC missions include search and rescue 
commerce cutters with 30 new WCCs, including 16 WLRs, 
(SAR), marine safety, marine environmental protection, and 
11 WLICs, and 3 WLIs. The Coast Guard states 
ports, waterways, and coastal security. 
The [16] River Buoy Tender [WLR] and [11] Inland 
Existing Waterways Cutters 
Construction  Tender  [WLIC]  variants  will  be 
The Coast Guard’s 35 existing WCCs—including 18 
acquired  on  one  contract;  these  variants  will 
WLRs, 13 WLICs, and 4 WLIs—were built to nine 
maximize commonality with notable exceptions for 
different designs and are now generally old or very old, 
hull  length,  working  deck  layout,  and  deck 
having been commissioned into service in 1990-1991 (2 of 
equipment, including the crane. 
them), 1976 (4), 1960-1970 (25), 1954 (2), and 1944-1945 
The  [3]  Inland  Buoy  Tender[s]  [WLIs]  will  be 
(2). 
acquired separately from the other two variants. In 
Geographic Distribution 
June  2021,  the  WCC  Program  began  partnering 
with  the  U.S.  Army  Corps  of  Engineers  Marine 
As of 2019, the 18 WLRs were based at cities along the 
Design  Center,  which  has  experience  with  similar 
Mississippi and other inland rivers in Alabama, Arkansas, 
Illinois, Iowa (two cutters), Kentucky (two cutters), 
acquisitions,  to  develop  a  Government-led  design 
Mississippi (three cutters), Missouri, Nebraska, Oklahoma, 
for  the  Inland  Buoy  Tender  variant.  The  Inland 
Pennsylvania, and Tennessee (four cutters). Although these 
Buoy Tender will be contractor-built. 
locations are in the central and eastern United States, the 
https://crsreports.congress.gov 
 link to page 2  link to page 2 

Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for Congress 
(U.S.  Coast  Guard,  “Waterways  Commerce 
and  inland  construction  tenders  [WLRs  and 
Cutter,” accessed January 18, 2024.) 
WLICs]. The initial award is worth $28.49 million. 
The  contract  includes  options  for  the  construction 
Figure 1 and Figure 2 show renderings of WCCs. The 
of a total of 16 river buoy tenders [WLRs] and 11 
winner of the WLR/WLIC contract (see below) will be able 
to compete for the WLI contract. 
inland construction tenders [WLICs]. If all contract 
line items are exercised, the total contract value is 
Figure 1. Notional Rendering of WLIC and WLR 
estimated at $1.19 billion. 
A total contract value of $1.19 billion for 27 WLRs and 
WLICs equates to an average cost of about $44.1 million 
each. Birdon states that its subcontractors include Bollinger 
Shipyards (Lockport, LA), for the WCCs’ bare hulls; 
Master Boat Builders, Inc. (Coden, AL) for their 
superstructures; Incat Crowther (an Australian firm with a 
U.S. office in Lafayette, LA) for design work; Kern Martin 
Services, Inc. (Coden, AL); Hiller Marine (Mobile, AL); 
Techcrane International (Covington, LA); Beier Integrated 
Systems (Gray, LA); LeBlanc Associates (Houma, LA); 
and Cummins (Charleston, SC). 
 
Source: Notional vendor rendering of WLIC (left) and WLR (right), 
April 2023 GAO Report 
shown at U.S. Coast Guard, “Waterways Commerce Cutter,” 
The April 2023 GAO report states: “The program plans to 
accessed March 23, 2023. 
achieve initial operational capability (IOC) before 
Figure 2. Coast Guard Notional Designs for WLR, 
adjudicating the full results of initial operational testing. 
WLIC, and WLI 
This raises the possibility of rework if testing identifies 
problems, such as design flaws, on cutters that have already 
been produced. The Coast Guard plans to mitigate this risk 
by using the preliminary results from initial testing to 
inform its initial operational capability decision.” (GAO 
Report 23-106701, p. 52; see page 53 for additional 
discussion.) 
Funding 
The Coast Guard’s proposed FY2024 budget requested 
$98.0 million in procurement funding for the WCC 
program. The House Appropriations Committee, in its 
report (H.Rept. 118-123 of June 27, 2023) on the FY2024 
DHS Appropriations Act (H.R. 4367), recommended 
approving the funding request. The Senate Appropriations 
Committee, in its report (S.Rept. 118-85 of July 27, 2023) 
on the FY2024 DHS Appropriations Act (S. 2625), 
recommended denying the funding request. H.Rept. 118-
 
123 states, “The Committee is disappointed in the lack of 
Source: Coast Guard il ustration showing indicative (i.e., notional) 
professionalism demonstrated by acquisition staff 
designs for the WLI (top), WLIC (middle), and WLR (bottom), 
responsible for this project and expects the Coast Guard to 
shown at U.S. Coast Guard, “Waterways Commerce Cutter,” 
take substantive action to improve the quality of its 
accessed March 23, 2023. 
acquisition work and related communications” (pp. 49-50). 
The explanatory report for the enacted version of the 
Procurement Cost 
FY2024 DHS Appropriations Act (Division C of H.R. 
An April 2023 Government Accountability Office (GAO) 
2882/P.L. 118-47 of March 23, 2024) provides $1.0 million 
report on major Department of Homeland Security (DHS) 
in procurement funding for the WCC program, a reduction 
acquisition programs states that as of June 2022, the WCC 
of $97.0 million from the requested amount (PDF page 96 
program’s total estimated procurement cost was $922 
of 125). 
million, or an average of about $30.7 million per cutter. 
The Coast Guard’s proposed FY2025 budget requests 
(GAO Report 23-106701, p. 52.) 
$135.0 million in procurement funding for the WCC 
Contract Award 
program. The Coast Guard’s FY2025 unfunded priorities 
On October 5, 2022, the Coast Guard announced that it 
list (UPL) includes an item for $40.0 million in additional 
procurement funding for accelerating WCC production. 
today awarded Birdon America, Inc. of Denver, an 
indefinite-delivery,  indefinite-quantity  firm  fixed 
Ronald O'Rourke, Specialist in Naval Affairs   
price contract with economic price adjustments for 
IF11672
the detail design and construction of its river buoy 
https://crsreports.congress.gov 
Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for Congress 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to 
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. 
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has 
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the 
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be 
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include 
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you 
wish to copy or otherwise use copyrighted material. 
 
https://crsreports.congress.gov | IF11672 · VERSION 42 · UPDATED