Navy Constellation (FFG-62) Class Frigate
Program: Background and Issues for Congress
Updated December 20, 2023
Congressional Research Service
https://crsreports.congress.gov
R44972
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Summary
The Navy began procuring Constellation (FFG-62) class frigates (FFGs) in FY2020, and a total
of four have been procured through FY2023, at a rate of one ship per year. Current Navy plans
call for procuring a total of 20 FFG-62s. The Navy’s proposed FY2024 budget requests $2,173.7
million (i.e., about $2.2 billion) for the procurement of the fifth and sixth ships in the program.
The Navy’s FY2024 budget submission programs the procurement of an additional six FFG-62s
during the period FY2025-FY2028 in annual quantities of 1-2-1-2.
FFG-62s are being built by Fincantieri/Marinette Marine (F/MM) of Marinette, WI. F/MM was
awarded a fixed-price incentive (firm target) contract for Detail Design and Construction
(DD&C) for up to 10 ships in the program—the lead ship plus nine option ships.
The FFG-62 program presents several potential oversight issues for Congress, including the
following:
• the Navy’s emerging force-level goal for frigates and other small surface
combatants, and the potential impact this might have on the total number of FFG-
62s to be procured and annual FFG-62 procurement quantities;
• the potential for cost growth in the FFG-62 program, particularly after the first 10
ships in the program;
• whether and when to introduce a second shipyard into the FFG-62 program;
• the number of vertical launch system (VLS) missile tubes in the FFG-62 design;
and
• technical risk in the FFG-62 program.
Congressional Research Service
link to page 5 link to page 5 link to page 5 link to page 5 link to page 5 link to page 5 link to page 6 link to page 6 link to page 6 link to page 7 link to page 9 link to page 9 link to page 10 link to page 14 link to page 14 link to page 14 link to page 14 link to page 16 link to page 18 link to page 20 link to page 20 link to page 21 link to page 22 link to page 25 link to page 25 link to page 25 link to page 25 link to page 25 link to page 26 link to page 26 link to page 26 link to page 26 link to page 7 link to page 8 link to page 8 link to page 9 link to page 12 link to page 10 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Contents
Introduction ..................................................................................................................................... 1
Background ..................................................................................................................................... 1
Navy’s Force of Small Surface Combatants (SSCs) ................................................................. 1
SSCs in General .................................................................................................................. 1
SSC Force Level at End of FY2022 ................................................................................... 1
Current and Potential Future SSC Force-Level Goal .......................................................... 1
U.S. Navy Frigates in General .................................................................................................. 2
FFG-62 Class Program .............................................................................................................. 2
Program Name .................................................................................................................... 2
Ship Capabilities and Crewing ............................................................................................ 3
Procurement Quantities and Schedule ................................................................................ 5
Procurement Cost ................................................................................................................ 5
Acquisition Strategy............................................................................................................ 6
Competition and Contract Award ...................................................................................... 10
Issues for Congress ........................................................................................................................ 10
Future SSC Force-Level Goal ................................................................................................. 10
Potential for Cost Growth, Particularly After First 10 Ships .................................................. 10
Number of FFG-62 Builders ................................................................................................... 12
Number of VLS Tubes ............................................................................................................ 14
Technical Risk ......................................................................................................................... 16
June 2023 GAO Report ..................................................................................................... 16
January 2023 DOT&E Report .......................................................................................... 17
2022 Press Reports ............................................................................................................ 18
Legislative Activity for FY2024 .................................................................................................... 21
Summary of Congressional Action on FY2024 Funding Request .......................................... 21
FY2024 National Defense Authorization Act (H.R. 2670/S. 2226) ........................................ 21
House ................................................................................................................................ 21
Senate ................................................................................................................................ 21
Conference ........................................................................................................................ 22
FY2024 DOD Appropriations Act (H.R. 4365/S. 2587) ......................................................... 22
House ................................................................................................................................ 22
Senate ................................................................................................................................ 22
Figures
Figure 1. Oliver Hazard Perry (FFG-7) Class Frigate ..................................................................... 3
Figure 2. Constellation (FFG-62) Class Frigate .............................................................................. 4
Figure 3. Constellation (FFG-62) Class Frigate .............................................................................. 4
Figure 4. Constellation (FFG-62) Class Frigate .............................................................................. 5
Figure 5. FFG-62 Design Compared to FREMM Design ............................................................... 8
Tables
Table 1. Programmed and Actual Annual FFG-62 Procurement Quantities ................................... 6
Congressional Research Service
link to page 25 link to page 28 link to page 30 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Table 2. Congressional Action on FY2024 Procurement Funding Request .................................. 21
Appendixes
Appendix. Guaranty vs. Warranty in Construction Contract ......................................................... 24
Contacts
Author Information ........................................................................................................................ 26
Congressional Research Service
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Introduction
This report provides background information and discusses potential issues for Congress
regarding the Navy’s Constellation (FFG-62) class frigate program, a program to procure a new
class of 20 guided-missile frigates (FFGs). The Navy’s proposed FY2024 budget requests
$2,173.7 million (i.e., about $2.2 billion) for the procurement of the fifth and sixth ships in the
program. FFG-62s are being built by Fincantieri/Marinette Marine (F/MM) of Marinette, WI.
The FFG-62 program presents several potential oversight issues for Congress. Congress’s
decisions on the program could affect Navy capabilities and funding requirements and the U.S.
shipbuilding industrial base.
Background
Navy’s Force of Small Surface Combatants (SSCs)
SSCs in General
In discussing its force-level goals and 30-year shipbuilding plans, the Navy organizes its surface
combatants into large surface combatants (LSCs), meaning the Navy’s cruisers and destroyers,
and small surface combatants (SSCs), meaning the Navy’s frigates, Littoral Combat Ships
(LCSs), mine warfare ships, and patrol craft.1 SSCs are smaller, less capable in some respects,
and individually less expensive to procure, operate, and support than LSCs. SSCs can operate in
conjunction with LSCs and other Navy ships, particularly in higher-threat operating
environments, or independently, particularly in lower-threat operating environments.
SSC Force Level at End of FY2022
The Navy’s force of SSCs at the end of FY2022 included no frigates, 24 LCSs, and 8 mine
warfare ships.
Current and Potential Future SSC Force-Level Goal
Current SSC Force-Level Goal Within 355-Ship Plan of December 2016
In December 2016, the Navy released a goal to achieve and maintain a Navy of 355 ships,
including 52 SSCs, of which 32 are to be LCSs and 20 are to be FFG-62s. Although patrol craft
are SSCs, they do not count toward the 52-ship SSC force-level goal, because patrol craft are not
considered battle force ships, which are the kind of ships that count toward the quoted size of the
Navy and the Navy’s force-level goal.2
Successor Force-Level Goal to Replace 355-Ship Goal of 2016
The Navy and the Department of Defense (DOD) have been working since 2019 to develop a
successor for the 355-ship force-level goal. The Navy’s FY2023 30-year (FY2023-FY2052)
1 See, for example, CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for
Congress, by Ronald O'Rourke.
2 For more on the 355-ship plan and additional discussion of battle force ships, see CRS Report RL32665, Navy Force
Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke.
Congressional Research Service
1
link to page 7 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
shipbuilding plan, released on April 20, 2022, includes a table summarizing the results of studies
that have been conducted on the successor force-level goal. These studies outline potential future
fleets with 40 to 60 SSCs.3
U.S. Navy Frigates in General
In contrast to cruisers and destroyers, which are designed to operate in higher-threat areas,
frigates are generally intended to operate more in lower-threat areas. U.S. Navy frigates perform
many of the same peacetime and wartime missions as U.S. Navy cruisers and destroyers, but
since frigates are intended to do so in lower-threat areas, they are equipped with fewer weapons,
less-capable radars and other systems, and less engineering redundancy and survivability than
cruisers and destroyers.4
The most recent class of frigates operated by the Navy was the Oliver Hazard Perry (FFG-7) class
(Figure 1). A total of 51 FFG-7s were procured between FY1973 and FY1984. The ships entered
service between 1977 and 1989, and were decommissioned between 1994 and 2015. In their final
configuration, FFG-7s were about 455 feet long and had full load displacements of roughly 3,900
tons to 4,100 tons. (By comparison, the Navy’s Arleigh Burke [DDG-51] class destroyers are
about 510 feet long and have full load displacements of roughly 9,700 tons.5) Following their
decommissioning, a number of FFG-7s, like certain other decommissioned U.S. Navy ships, have
been transferred to the navies of U.S. allied and partner countries.
FFG-62 Class Program
Program Name
The FFG-62 program was previously known as the FFG(X) program.6 On October 7, 2020, the
Navy announced that FFG-62 would be named Constellation, in honor of the first U.S. Navy
3 For additional discussion, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and
Issues for Congress, by Ronald O'Rourke.
4 Compared to cruisers and destroyers, frigates can be a more cost-effective way to perform missions that do not require
the use of a higher-cost cruiser or destroyer. In the past, the Navy’s combined force of higher-capability, higher-cost
cruisers and destroyers and lower-capability, lower-cost frigates has been referred to as an example of a so-called high-
low force mix. High-low mixes have been used by the Navy and the other military services in recent decades as a
means of balancing desires for individual platform capability against desires for platform numbers in a context of
varied missions and finite resources.
Peacetime missions performed by frigates can include, among other things, engagement with allied and partner navies,
maritime security operations (such as anti-piracy operations), and humanitarian assistance and disaster response
(HA/DR) operations. Intended wartime operations of frigates include escorting (i.e., protecting) military supply and
transport ships and civilian cargo ships that are moving through potentially dangerous waters. In support of intended
wartime operations, frigates are designed to conduct anti-air warfare (AAW—aka air defense) operations, anti-surface
warfare (ASuW) operations (meaning operations against enemy surface ships and craft), and antisubmarine warfare
(ASW) operations. U.S. Navy frigates are designed to operate in larger Navy formations or as solitary ships. Operations
as solitary ships can include the peacetime operations mentioned above.
5 This is the displacement for the current (Flight III) version of the DDG-51 design.
6 In the designation FFG(X), FF meant frigate, G meant guided-missile ship (indicating a ship equipped with an area-
defense anti-air warfare [AAW] system), and (X) indicated that the specific design of the ship had not yet been
determined. FFG(X) thus meant a guided-missile frigate whose specific design has not yet been determined.
The designation FF, with two Fs, means frigate in the same way that the designation DD, with two Ds, means
destroyer. FF is sometimes translated less accurately as fast frigate. FFs, however, are not particularly fast by the
standards of U.S. Navy combatants—their maximum sustained speed, for example, is generally lower than that of U.S.
(continued...)
Congressional Research Service
2
link to page 8 link to page 8 link to page 9 
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
ships authorized by Congress in 1794—the six heavy frigates United States, Constellation,
Constitution, Chesapeake, Congress, and President. FFG(X)s henceforth became known as
Constellation (FFG-62) class ships.
Figure 1. Oliver Hazard Perry (FFG-7) Class Frigate
Source: Photograph accompanying Dave Werner, “Fighting Forward: Last Oliver Perry Class Frigate
Deployment,” Navy Live, January 5, 2015, accessed September 21, 2017, at http://navylive.dodlive.mil/2015/01/05/
fighting-forward-last-oliver-perry-class-frigate-deployment/.
Ship Capabilities and Crewing
FFG-62s (Figure 2, Figure 3, and Figure 4) are to be multimission small surface combatants
capable of conducting anti-air warfare (AAW), anti-surface warfare (ASuW), antisubmarine
warfare (ASW), and electromagnetic warfare (EMW) operations. They are to be capable of
operating in both blue water (i.e., mid-ocean) and littoral (i.e., near-shore) areas, and capable of
operating either independently (when that is appropriate for their assigned missions) or as part of
larger Navy formations.
To help maximize the time that each ship spends at sea, the Navy reportedly is considering
operating FFG-62s eventually with dual crews—an approach, commonly called blue-gold
crewing, that the Navy uses for operating its ballistic missile submarines and LCSs.7 The Navy
plans to operate the first few FFG-62s, however, with single crews.8
The FFG-62 design is based on the design of the Italian-French FREMM (Fregata Europea Multi-
Missione) frigate, a ship that has been built in two variants, one for the Italian navy and one for
the French navy. The FREMM design, in other words, served as what is known as the “parent”
Navy aircraft carriers, cruisers, and destroyers. In addition, there is no such thing in the U.S. Navy as a slow frigate.
Some U.S. Navy surface combatants are equipped with a point-defense AAW system, meaning a short-range AAW
system that is designed to protect the ship itself. Other U.S. Navy surface combatants are equipped with an area-
defense AAW system, meaning a longer-range AAW system that is designed to protect no only the ship itself, but other
ships in the area as well. U.S. Navy surface combatants equipped with an area-defense AAW system are referred to as
guided-missile ships and have a “G” in their designation.
7 See, for example, David B. Larter, “The US Navy Is Planning for Its New Frigate to Be a Workhorse,” Defense News,
January 30, 2018.
8 Richard R. Burgess, “CNO: First Few New Frigates to Have Single Crews,” Seapower, January 11, 2021.
Congressional Research Service
3


Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
design for the FFG-62 design. The use of a parent design for the FFG-62 program is discussed
further in the section below on the FFG-62 program’s acquisition strategy.
Figure 2. Constellation (FFG-62) Class Frigate
Artist’s rendering of F/MM design
Source: Cropped version of il ustration accompanying Fincantieri Marinette Marine, “Fincantieri Marinette
Marine Awarded Second Constel ation-class Frigate,” May 20, 2021.
Figure 3. Constellation (FFG-62) Class Frigate
Computer rendering of F/MM design
Source: Fincantieri/Marinette Marine, screen capture from video entitled “Constel ation Class Frigate 360°
View,” posted at https://futurefrigate.com/, accessed December 8, 2020.
Congressional Research Service
4
link to page 10 
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Figure 4. Constellation (FFG-62) Class Frigate
Computer rendering of F/MM design
Source: U.S. Navy rendering shown on slide 2 of in Navy briefing entitled “Guided Missile Frigate (FFG 62)
Update, Sea Air Space [Exposition],” Captain Kevin Smith, April 5, 2022.
Procurement Quantities and Schedule
Total Procurement Quantity
The Navy wants to procure 20 FFG-62s, which in combination with a force of 32 LCSs would
meet the Navy’s 52-ship SSC force-level goal within the Navy’s current 355-ship plan. A total of
35 LCSs were procured, but the Navy has proposed early retirements for a number of them.
Congress has prohibited some of these proposed early retirements but has not blocked others, and
as a consequence, the LCS force will be reduced over time to something less than 32 ships.9
Given a force of less than 32 LCSs, a 52-ship SSC force-level goal could be met by increasing the
planned total number of FFG-62s to something higher than 20 and/or eventually procuring a new
SSC design that is different from the LCS or FFG-62 designs.
Annual Procurement Quantities
Table 1 shows programmed and actual annual procurement quantities for the FFG-62 program.
Procurement Cost
FFG-62s generally have a budgeted procurement cost of between $1.0 billion and $1.1 billion
each. Congress funded the procurement of the first FFG-62 in FY2020 at a cost of $1,281.2
million (i.e., about $1.3 billion), the second FFG-62 in FY2021 at a cost of $1,053.1 million, the
third in FY2022 at a cost of $1,090.9 million, and the fourth at a cost of $1.135.2 million. The
lead ship in the program has a higher estimated procurement cost than the follow-on ships
because the lead ship is at the top of the production learning curve for the class, and because the
lead ship’s procurement cost incorporates much the detailed design/nonrecurring engineering
9 For further discussion of the proposed early retirements of LCSs, see CRS Report RL32665, Navy Force Structure
and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke.
Congressional Research Service
5
link to page 10 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
(DD/NRE) costs for the class. (It is a traditional Navy budgeting practice to attach most or all of
the DD/NRE costs for a new ship class to the procurement cost of the lead ship in the class.)
The eight ships programmed for procurement during the five-year period FY2024-FY2028 (i.e.,
the two requested for procurement in FY2024, pus six more programmed for procurement in
FY2025-FY2028) have an average programmed procurement cost of $1,030.3 million each in
then-year dollars. The 20-ship program as a whole has a total programmed procurement cost of
$21,421.8 million (i.e., about $21.4 billion) in then-year dollars, or an average of $1,071.1 million
each.
Table 1. Programmed and Actual Annual FFG-62 Procurement Quantities
FY20
FY21
FY22
FY23
FY24
FY25
FY26
FY27
FY28
Programmed
FY2020 budget submission
1
2
2
2
2
FY2021 budget submission
1
1
2
2
3
Dec. 9, 2020, shipbuilding document
1
3
3
4
4
FY2022 budget submission
1
n/a
n/a
n/a
n/a
FY2023 budget submission
1
2
1
2
1
FY2024 budget submission
2
1
2
1
2
Actual
1
1
1
1
Source: Table prepared by CRS based on Navy’s FY2020-FY2024 budget submissions; December 9, 2020, long-
range Navy shipbuilding document; and enacted National Defense Authorization Acts (NDAAs) and DOD
Appropriations Acts for FY2020 and subsequent years.
Note: n/a means not available. DOD’s FY2022 budget submission was a single-year budget that did not contain
line-item details for subsequent fiscal years.
Acquisition Strategy
Number of Builders
The Navy’s baseline plan for the FFG-62 program envisages using a single builder at any one
time to build FFG-62s, but Navy officials have also spoken about the option of bringing a second
shipyard into the program at some point, particularly if annual procurement rates for FFG-62s rise
above two ships per year. The annual procurement quantities of three and four ships per year that
are shown in Table 1 under the December 9, 2020, long-range Navy shipbuilding document
would have been executed by two shipyards.10 An August 3, 2021, press report quoting a Navy
official states
“It’s pre-decisional in the Navy right now but we do have in our contract a Technical Data
Package (TDP) that we can exercise that option all the way into the 10th ship. So our intent
is that, at some point based on a profile, we can exercise that TDP and then work with
candidate yards interested and then start building up on a second source and doing a
competition in the future,” [Capt. Kevin Smith, program manager of the new frigate class,
10 The December 9, 2020, document states that the shipbuilding plan presented in the document “makes investments in
FY2022 in long lead time material and the stand up of a ‘follow yard’ [i.e., a second shipyard] in FY2023 to increase
FFG 62 production to three ships in FY2023 and to four ships by FY2025.” (U.S. Navy, Report to Congress on the
Annual Long-Range Plan for Construction of Naval Vessels, December 9, 2020, p. 6.)
Congressional Research Service
6
link to page 12 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
PMS-51] said during a briefing at the Navy League’s annual 2021 Sea Air Space expo
Monday [August 2] here.11
Parent-Design Approach
As noted earlier, FFG-62s are to be built to a modified version of an existing ship design—an
approach, called the parent-design approach, that can reduce design time, design cost, and cost,
schedule, and technical risk in building the ship. The Coast Guard and the Navy are currently
using the parent-design approach for the Coast Guard’s Polar Security Cutter (i.e., polar
icebreaker) program.12 The parent-design approach has also been used in the past for other Navy
and Coast Guard ships, including Navy mine warfare ships13 and the Coast Guard’s new Fast
Response Cutters (FRCs).14
Figure 5 shows a U.S. Navy briefing slide summarizing what the U.S. Navy says are the
“primary differences between the FFG 62 Class [design] and the FREMM Parent design.” The
Navy states that the design differences “were proposed by [the shipbuilding firm] Fincantieri and
incorporated [into Fincantieri’s proposed design for the FFG-62] prior to [the Navy’s] contract
award [for the FFG-62 program to Fincantieri].”15
An August 4, 2021, press report states
The Navy has chosen to elongate and widen the hull of its next-generation Constellation-
class frigate relative to the [FREMM] parent design, but the officer overseeing its
production says the internal layout will largely remain the same.
“The Italians did a very good job in the design of the internal spaces, and the flow of a lot
of those spaces,” Capt. Kevin Smith, program manager for the Constellation class, told
attendees at the Sea Air Space exposition on Monday [August 2]. “You could say we
bought a bigger house, [but] from a modeling and simulation perspective, it’s exactly the
same.”…
While some changes are to be expected to meet the Navy’s needs, enlarging the hullform
itself has the potential to change where components in the ship must be placed, as well as
the overall cost.
Asked about how possible changes in the ship’s hull could affect the internal design, Smith
said Fincantieri Marinette Marine, the Constellation’s prime contractor, worked with Naval
Surface Warfare Center Carderock to develop a scale model of the ship and that most
elements will stay true to the parent design. He cited the bridge and propulsion plant as
areas where the Navy has not made any significant changes to the layout.16
11 Rich Abott, “Navy Outlines Plan For Second Frigate Shipyard,” Defense Daily, August 3, 2021.
12 For more on the polar security cutter program, including the parent-design approach, see CRS Report RL34391,
Coast Guard Polar Security Cutter (Polar Icebreaker) Program: Background and Issues for Congress, by Ronald
O'Rourke.
13 The Navy’s Osprey (MCM-51) class mine warfare ships are an enlarged version of the Italian Lerici-class mine
warfare ships.
14 The FRC design is based on a Dutch patrol boat design, the Damen Stan Patrol Boat 4708.
15 Source: Navy information paper dated August 18, 2021, on differences between FFG-62 design and FREMM parent
design, provided to CRS and the Congressional Budget Office (CBO) by Navy Office of Legislative Affairs on August
27, 2021.
16 Justin Katz, “Navy Says Constellation Hull Change Won’t Affect Internal Design,” Breaking Defense, August 4,
2021.
Congressional Research Service
7

Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Figure 5. FFG-62 Design Compared to FREMM Design
Source: Navy briefing slide provided to CRS and Congressional Budget Office (CBO) by Navy Office of
Legislative Affairs, August 27, 2021, with accompanying Navy information paper dated August 18, 2021.
No New Technologies or Systems
As an additional measure for reducing cost, schedule, and technical risk in the FFG-62 program,
the Navy envisages developing no new technologies or systems for FFG-62s—the ships are to use
systems and technologies that already exist or are already being developed for use in other
programs.
FY2021 Legislation Regarding Land-Based Test Program for Engineering Plant
Section 125 of the FY2021 National Defense Authorization Act (H.R. 6395/P.L. 116-283 of
January 1, 2021) requires the Navy to commence, prior to the delivery of the first FFG-62, a land-
based test program for the FFG-62 engineering plant (i.e., its propulsion system and related
machinery). The provision specifies how the test program is to be conducted and requires the
Navy to complete the test program not later than the date on which the first FFG-62 is scheduled
to be available for tasking by operational military commanders.17
17 Regarding Section 125, the conference report (H.Rept. 116-617 of December 3, 2020) on H.R. 6395/P.L. 116-283 of
January 1, 2021 states
Given that the Constellation-class will play a significant role in the Navy battle force for many
(continued...)
Congressional Research Service
8
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Legislation Regarding U.S. Content Requirements for Components
Section 856 of the FY2020 National Defense Authorization Act (S. 1790/P.L. 116-92 of
December 20, 2019) states
SEC. 856. APPLICATION OF LIMITATION ON PROCUREMENT OF GOODS
OTHER THAN UNITED STATES GOODS TO THE FFG–FRIGATE PROGRAM.
Notwithstanding any other provision of law, amounts authorized to carry out the FFG–
Frigate Program may be used to award a new contract that provides for the acquisition of
the following components regardless of whether those components are manufactured in the
United States:
(1) Auxiliary equipment (including pumps) for shipboard services.
(2) Propulsion equipment (including engines, reduction gears, and propellers).
(3) Shipboard cranes.
(4) Spreaders for shipboard cranes.
Section 8100(b) of Division C of the FY2023 DOD Appropriations Act (H.R. 2617/P.L. 117-328
of December 29, 2022) states
SEC. 8100....
(b) None of the funds provided in this Act for the FFG(X) Frigate program shall be used to
award a new contract that provides for the acquisition of the following components unless
those components are manufactured in the United States: Air circuit breakers;
gyrocompasses; electronic navigation chart systems; steering controls; pumps; propulsion
and machinery control systems; totally enclosed lifeboats; auxiliary equipment pumps;
shipboard cranes; auxiliary chill water systems; and propulsion propellers: Provided, That
the Secretary of the Navy shall incorporate United States manufactured propulsion engines
decades and the current program of record calls for building 20 frigates, the conferees believe a
strong technical foundation for this program is critically important.
The conferees note that the winning Constellation-class ship design is based on a foreign design.
While recognizing an existing parent design can reduce design, technical, and integration risks, the
conferees are concerned that significant risks remain in the FFG-62 program, including: cost
realism; shifting to predominantly U.S. component suppliers instead of the mainly foreign suppliers
used in the parent vessel design; and a complex Combined Diesel Electric and Gas Hull,
Mechanical and Electrical (HM&E) drive train that has not previously been used on U.S. Navy
ships.
The conferees believe land based engineering and test sites (LBETS) are critical resources for the
Department of Defense, particularly for Navy ship HM&E systems.…
Since 1972, NSWCPD LBETS testing has reduced the acquisition risk of five of the seven Navy
surface combatant classes (Spruance-class, Oliver Hazard Perry-class, Ticonderoga-class, Arleigh
Burke-class, and Zumwalt-class).… The littoral combat ship (LCS) classes, the Freedom- and
Independence-classes, are the two recent classes that have not had the benefit of a LBETS. Since
lead ship deliveries in 2008 and 2010, both LCS classes have encountered significant, costly, and
debilitating engineering failures. The conferees believe many of these LCS engineering failures
would have been discovered, analyzed, and corrected faster with less negative operational impact
had the Navy established a LCS LBETS.
Accordingly, the provision would require the Secretary of the Navy to establish a FFG-62 class
LBETS as soon as possible.…
In addition, the conferees direct the Secretary to submit to the congressional defense committees a
plan to implement this section with the budget materials that accompany the President’s Budget
request for fiscal year 2022. This plan shall include the costs, activities, and test plan necessary to
meet the requirements under this section. (Pages 1523-1524)
Congressional Research Service
9
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
and propulsion reduction gears into the FFG(X) Frigate program beginning not later than
with the eleventh ship of the program.
Provisions similar to Section 8100(b) were included in the FY2020, FY2021, and FY2022 DOD
Appropriations Acts.18
Competition and Contract Award
Four industry teams competed for the FFG-62 program. On April 30, 2020, the Navy announced
that it had awarded the FFG-62 contract to the team led by Fincantieri/Marinette Marine (F/MM)
of Marinette, WI. F/MM was awarded a fixed-price incentive (firm target) contract for Detail
Design and Construction (DD&C) for up to 10 ships in the program—the lead ship plus nine
option ships. The other three industry teams reportedly competing for the program were led by
Austal USA of Mobile, AL; General Dynamics/Bath Iron Works (GD/BIW) of Bath, ME; and
Huntington Ingalls Industries/Ingalls Shipbuilding (HII/Ingalls) of Pascagoula, MS.
Under the DD&C contract, the Navy has the option of recompeting the program at any point prior
to the 10th ship. The Navy also has the option of seeking to convert the DD&C at some point into
a multiyear contract known as a block buy contract to procure the ships.19
Issues for Congress
Future SSC Force-Level Goal
One issue for Congress concerns the Navy’s emerging force-level goal for frigates and other
small surface combatants, and the potential impact this emerging force-level goal might have on
the total number of FFG-62s to be procured and annual FFG-62 procurement quantities. As noted
earlier, the Navy and the Department of Defense (DOD) have been working since 2019 to
develop a successor for the 355-ship force-level goal. The Navy’s FY2023 30-year (FY2023-
FY2052) shipbuilding plan, released on April 20, 2022, includes a table summarizing the results
of studies that have been conducted on the successor force-level goal. These studies outline
potential future fleets with 40 to 60 SSCs. An SSC force-level goal closer to the high end of that
range could increase the likelihood of the Navy increasing its desired number of FFG-62s to
something higher than 20, and its desired FFG-62 procurement rate to something more than two
ships per year.
Potential for Cost Growth, Particularly After First 10 Ships
Another potential issue for Congress concerns the potential for cost growth in the FFG-62
program, particularly after the first 10 ships in the program, which are to be procured under a
fixed-price incentive (firm target) contract. As discussed in greater detail in earlier versions of
this CRS report,20 CRS and CBO analyses done in 2020 suggested that that if FFG-62s were to
18 See Section 8113(b) of the FY2020 DOD Appropriations Act (Division A of H.R. 1158/P.L. 116-93 of December 20,
2019) and Section 8113(b) of the FY2021 DOD Appropriations Act (Division C of H.R. 133/P.L. 116-260 of
December 27, 2020), and Section 8103(b) of the FY2022 DOD Appropriations Act (Division C of H.R. 2471/P.L. 117-
103 of March 15, 2022).
19 For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy
Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke.
20 See, for example, the version dated December 21, 2022, or earlier versions dating back to the version of May 4,
2020.
Congressional Research Service
10
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
wind up costing about the same to construct per thousand tons of displacement as other recent
U.S. military surface combatants, then FFG-62s could cost substantially more to build than their
budgeted unit procurement costs. The preliminary CRS analysis, done by CRS following the
Navy’s April 30, 2020, contract award in the FFG-62 program, suggested that if FFG-62s were to
wind up costing about the same to construct per thousand tons of displacement as other recent
U.S. military surface combatants, then the third and subsequent FFG-62s could cost 17% to 56%
more than the budgeted estimates for those ships in the Navy’s FY2021 budget submission. A
follow-on and more refined analysis of the issue that was done by CBO and released on October
13, 2020,21 and which also compared the Navy’s FFG-62 budgeted cost estimate to actual costs
for building other recent U.S. military surface combatants, estimated that the first 10 FFG-62s
would cost 40% more to build than the Navy estimates. An October 2023 CBO report on the cost
of the Navy’s FY2024 30-year shipbuilding plan, based on updated Navy and CBO figures,
estimated that FFG-62s on average will cost 10% to 20% more than the Navy estimates.22
Depending on the exact terms of the fixed-price incentive (firm target) contract that the Navy
awarded to F/MM for the first 10 ships in the FFG-62 program, some portion (perhaps much) of
any cost growth that might occur on the first 10 FFG-62s could be borne by F/MM rather than the
Navy, although F/MM under such a circumstance might also have the option of seeking some
form of contractual relief from the Navy, which if granted could shift at least some of the cost
growth back to the government.23 If F/MM were to bear most or all of any cost growth that might
occur on the first 10 FFG-62s, then cost growth in the FFG-62 program, if it were to occur, might
not affect Navy budgeting substantially until the 11th ship in the program. Under the Navy’s
FY2024 budget submission, the 11th ship in the program is to be the second of the two ships that
are programmed for procurement in FY2028.
Potential oversight questions for Congress include the following:
• What is the Navy’s basis for its view that FFG-62s—ships that are to be about
three-quarters as large as U.S. Navy’s new Flight III Arleigh Burke (DDG-51)
class destroyers24 in terms of displacement, and with installed capabilities that are
21 Congressional Budget Office, The Cost of the Navy’s New Frigate, October 2020, 11 pp.
22 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2024 Shipbuilding Plan, October 2023, Table 8
on pp. 26-27. CBO states that the new estimated difference between CBO and the Navy of 10% to 20%, as opposed to
the 40% difference from CBO’s October 2020 report, is due to four factors: (1) an increase by the Navy since October
2020 in its estimated costs for building FFG-62s; (2) a decrease by CBO since October 2020 in its estimated costs for
building FFG-62s due to an updated treatment of inflation; (3) a shift by CBO from estimating the cost of ships 1
through 10 in CBO’s October 2020 report to ships 5 through 20 in CBO’s October 2023 report, which among other
things eliminated from the analysis the cost of the lead ship, where there is a fairly substantial difference between the
CBO and Navy estimates; and (4) the rounding off in CBO’s reports of Navy and CBO estimates to the nearest tenth of
a billion dollars per ship, which can shift calculations of the percent difference in cost. (Source: CBO telephone call
with CRS, November 14, 2023.)
23 For example, in 2019, Eastern Shipbuilding Group of Panama City, FL, requested and received contractual relief for
Offshore Patrol Cutters (OPCs) that it is building for the Coast Guard. The relief was granted under P.L. 85-804 as
amended (50 U.S.C. 1431-1435), a law that authorizes certain federal agencies to provide certain types of extraordinary
relief to contractors who are encountering difficulties in the performance of federal contracts or subcontracts relating to
national defense. ESG reportedly submitted a request for extraordinary relief on June 30, 2019, after ESG’s
shipbuilding facilities were damaged by Hurricane Michael, which passed through the Florida panhandle on October
10, 2018. For additional discussion of the OPC program, including the contractual relief provided under P.L. 85-804,
see CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald
O'Rourke. See also Congressional Budget Office, The Cost of the Navy’s New Frigate, October 2020, p. 11.
24 For more on the DDG-51 program, see CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs:
Background and Issues for Congress, by Ronald O'Rourke.
Congressional Research Service
11
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
in many cases similar to those of DDG-51s—can be procured for about one-half
the cost of Flight III DDG-51s?
• Under the terms of the fixed-price incentive (firm target) contract that the Navy
awarded to F/MM for the FFG-62 program, what portion of any cost growth that
might occur on the first 10 FFG-62s might be borne by F/MM, and what portion
might be borne by the Navy?
• If the budgeted procurement costs of FFG-62s rise substantially starting with the
11th ship in the program, what impact, if any, would that have on the Navy’s
ability to afford other Navy program priorities? What impact, if any, would it
have on the cost effectiveness of the FFG-62 program relative to other Navy
investments?
Number of FFG-62 Builders
Another issue for Congress is whether and when to introduce a second shipyard into the FFG-62
program. The Navy’s FFG-7s, which were procured at annual rates of as high as eight ships per
year, were built at three shipyards. In considering whether to build FFG-62s at a single shipyard
or at two shipyards, Congress may consider several factors, including but not limited to the
annual FFG-62 procurement rate, shipyard production capacities and production economies of
scale, the potential costs and benefits in the FFG-62 program of employing recurring competition
between multiple shipyards, and how the number of FFG-62 builders might fit into a larger
situation involving the production of other Navy and Coast Guard ships, including Navy DDG-51
destroyers, Navy amphibious ships, and Coast Guard Offshore Patrol Cutters (OPCs).25
The Navy stated in 2022 that in terms of having a technical data package ready for a second
builder, the Navy could introduce a second builder into the FFG-62 program with a ship procured
as early as FY2024.26 At an April 18, 2023, hearing before the Senate Armed Services Committee
on the Navy’s proposed FY2024 budget, the following exchange occurred:
SENATOR ROGER WICKER (continuing):
And Secretary Del Toro, let’s talk briefly about frigates. Now we’re building those in
Wisconsin now.
THEN-SECRETARY OF THE NAVY CARLOS DEL TORO:
That’s correct, sir.
WICKER:
And—and the decision has been made to—to build the frigates there and at another
shipyard. Is that correct?
DEL TORO:
No, sir, not as of right now. The decis—
WICKER:
25 For more on the DDG-51 program, see CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs:
Background and Issues for Congress, by Ronald O'Rourke. For more on Navy amphibious shipbuilding programs, see
CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship Programs: Background and Issues for
Congress, by Ronald O'Rourke. For more on the OPC program, see CRS Report R42567, Coast Guard Cutter
Procurement: Background and Issues for Congress, by Ronald O'Rourke.
26 Source: Navy FY2023 program briefing for CRS and CBO, May 10, 2022.
Congressional Research Service
12
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
—That has not been made?
DEL TORO:
No, sir. That decision has not been made.
WICKER:
Ok, well, where are we on that?
DEL TORO:
We’re actually waiting for the completion of the [FFG-62] technical design package, which
is expected by the end of this year. Once that technical design package is fully mature and
submitted for review, we will review it. And at that point, we’ll make a decision on whether
we have the ability to actually take that technical data package and make sure that it’s
mature enough to actually compete, perhaps compete with another shipyard, so that we can
have two shipyards building the Constellation class—
WICKER:
Well, we’re going to need four years, is that right?
DEL TORO:
I’m sorry, sir?
WICKER:
We’re going to need four frigates a year. And that—that concept is a way to get that, is that
correct?
DEL TORO:
No, sir. Right now, the president’s budget recommends [a] sawtooth [FFG-62
procurement] pattern [with annual quantities] of two, one, two, one, moving forward. So
it’s two frigates a year that we will initially need.
WICKER:
How—Admiral Gilday, how important would it be to—to move to [a procurement rate of]
four [per year]?
THEN-CHIEF OF NAVAL OPERATIONS MICHAEL M. GILDAY:
I think very important, based on the comments both you and the chairman [made] at the
opening of the committee [hearing]. If we could get to a second shipyard, and [procure]
two a year from each shipyard, [while also procuring from other shipyards] two destroyers,
two to three destroyers a year, we’d be in a much better place. We are catching up, and you
can’t buy back time, sir, with the seven shipyards that we have [currently involved in
building the Navy’s larger and more complex ships], relative to the 30 [shipyards that
existed in the United States] that we had years ago.
WICKER:
It’s going to be hard to get to four a year, without designating two shipyards, do you agree?
GILDAY:
I agree. I also agree with—with the secretary’s comments. I think two—two shipyards is
in the plan. We want to make sure that we’re measuring twice and cutting once [regarding
the correctness of the details of the FFG-62 design] before that decision is made.27
27 Source: CQ transcript. See also Sam LaGrone, “CNO: ‘Very Important’ to Add 2nd Constellation-class Shipyard,
(continued...)
Congressional Research Service
13
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
The explanatory statement for the FY2022 DOD Appropriations Act (S. XXXX) that the Senate
Appropriations Committee released on October 18, 2021, stated (emphasis added)
While the Committee recognizes the significant role that CCF [Constellation-class frigate]
will have in the future Navy battle force, and is based on a proven hull design and mature
shipboard technologies, it remains a new class and presents typical first-in-class production
challenges. The Committee notes the past challenges of the Navy and shipbuilding
industrial base in managing costs, technical concurrency, design changes, and schedule of
lead ships of a class. The Committee is concerned that prematurely adding a second CCF
shipyard before the first shipyard has identified and corrected technical and production
issues will inject unneeded risk and complexity into the program. Therefore, prior to
award of a contract for a second CCF shipyard, the Committee directs the Secretary
of the Navy to prioritize the following objectives: technology maturation and risk
reduction for critical shipboard components; major systems integration; full ship
technical data package creation; and successful operationally realistic testing for the
first ship. The Committee also understands that setting up the CCF manufacturing
capacity, workforce, and supply chain requires consistent year-over-year funding to meet
the demand for production ramp up. Therefore, the Committee directs the Secretary of the
Navy to submit a report not later than 90 days prior to awarding a contract for the second
CCF shipyard to the congressional defense committees outlining the acquisition strategy
for achieving the full Frigate Program of Record and meeting these technology maturation
and risk reduction objectives. (PDF page 108 of 253)
The Navy stated in 2022 that the above report language, particularly the requirement for
successful operationally realistic testing for the first ship, could be read as barring the
introduction of a second builder into the FFG-62 until sometime after the first FFG-62 ship is
delivered,28 which is scheduled under the Navy’s FY2024 budget submission for September 2026.
Under that schedule, operationally realistic testing of the ship might begin in 2027, a year when
Congress will consider the Navy’s proposed FY2028 budget. Another possible perspective on the
above report language is that it would bar the introduction of a second builder into the program
until the Secretary of the Navy prioritizes the objective of successful operationally realistic
testing of the first ship, which is not the same as conducting successful operationally realistic
testing. Under this interpretation, prioritizing this objective (i.e., designating it as an important
objective) is something that the Secretary of the Navy could do immediately.
Number of VLS Tubes
Another potential oversight issue for Congress concerns the number of vertical launch system
(VLS) missile tubes in the FFG-62 design. The VLS is the FFG-62’s principal (though not only)
means of storing and launching missiles. FFG-62s are to each be equipped with 32 Mark 41 VLS
tubes. (The Mark 41 is the Navy’s standard VLS design.)
Supporters of requiring each FFG-62 to be equipped with a larger number of VLS tubes, such as
48, might argue that FFG-62s are to be roughly three-quarters as large, and at least half as
expensive to procure, as the Navy’s DDG-51 class destroyers, and might therefore be more
appropriately equipped with at least 48 VLS tubes, which is one-half the number on recent DDG-
51s. They might also argue that in a context of renewed great power competition with potential
Build 4 Frigates a Year,” USNI News, April 18, 2023; Rich Abott, “CNO Says ‘Very Important To Get Second Frigate
Shipyard and Build Four Per Year,” Defense Daily, April 19, 2023.
28 Source: Navy FY2023 program briefing for CRS and CBO, May 10, 2022.
Congressional Research Service
14
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
adversaries such as China, which is steadily improving its naval capabilities,29 it might be prudent
to equip each FFG-62 with 48 rather than 32 VLS tubes each, and that doing so might only
marginally increase FFG-62 unit procurement costs. They might also argue that equipping each
FFG-62 with 48 rather than 32 VLS tubes will permit the Navy to more fully offset a substantial
reduction in VLS tubes that the Navy’s surface fleet is projected to experience when the Navy’s
22 Ticonderoga (CG-47) class cruisers, which are each equipped with 122 VLS tubes, are
retired,30 and provide a hedge against the possibility that Navy plans to field VLS tubes on Large
Unmanned Surface Vehicles (LUSVs)31 will be slowed or curtailed for technical or other reasons.
Supporters of having each FFG-62 be equipped with 32 VLS tubes might argue that the analyses
indicating a need for 32 VLS tubes already took improving adversary capabilities (as well as
other U.S. Navy capabilities) into account. They might also argue that FFG-62s, in addition to
having 32 VLS tubes, will also to have separate, deck-mounted box launchers for launching 16
anti-ship cruise missiles, as well as a separate, 21-cell Rolling Airframe Missile (RAM) AAW
missile launcher; that Navy plans continue to call for eventually deploying additional VLS tubes
on LUSVs, which are to act as adjunct weapon magazines for the Navy’s manned surface
combatants; and that increasing the number of VLS tubes on each FFG-62 from 32 to 48 would
increase (even if only marginally) the procurement cost of a ship that is intended to be an
affordable supplement to the Navy’s cruisers and destroyers.
A May 14, 2019, Navy information paper on expanding the cost impact of expanding the FFG-62
VLS capacity from 32 cells to 48 cells states
To grow from a 32 Cell VLS to a 48 Cell VLS necessitates an increase in the length of the
ship with a small beam increase and roughly a 200-ton increase in full load displacement.
This will require a resizing of the ship, readdressing stability and seakeeping analyses, and
adapting ship services to accommodate the additional 16 VLS cells.
A change of this nature would unnecessarily delay detail design by causing significant
disruption to ship designs. Particularly the smaller ship designs. Potential competitors have
already completed their Conceptual Designs and are entering the Detail Design and
Construction competition with ship designs set to accommodate 32 cells.
The cost is estimated to increase between $16M [million] and $24M [million] per ship.
This includes ship impacts and additional VLS cells.32
Compared to an FFG-62 follow-on ship unit procurement cost of about $1.0 billion, the above
estimated increase of $16 million to $24 million would equate to an increase in unit procurement
cost of about 1.6% to about 2.4%.
29 For more on China’s naval modernization effort, see CRS Report RL33153, China Naval Modernization:
Implications for U.S. Navy Capabilities—Background and Issues for Congress, by Ronald O'Rourke.
30 See, for example, Megan Eckstein and Joe Gould, “Lawmakers Crunching the Numbers on Potential Surface Navy
Additions to FY22 Spending Plan,” Defense News, June 17, 2021; Mallory Shelbourne, “Lawmakers Probe Navy’s
Plan to Decommission Cruisers, Navy Says Cuts Will Save $5B Across FYDP,” USNI News, June 17 (updated June
18), 2021; Megan Eckstein, “Lawmakers Are Worried About the US Navy’s Spending Plan and a Near-Term China
Threat,” Defense News, June 15, 2021; Mallory Shelbourne, “CNO Gilday: Flat or Declining Navy Budgets ‘Will
Definitely Shrink’ the Fleet,” USNI News, June 15, 2021; Blake Herzinger, “The Budget (and Fleet) That Might Have
Been,” War on the Rocks, June 10, 2021; David B. Larter, “As the US Navy Scrambles to Field More Missiles in Asia,
a Tough Decision Looms for Aging Cruisers,” Defense News, April 12, 2021.
31 For more on the LUSV program, see CRS Report R45757, Navy Large Unmanned Surface and Undersea Vehicles:
Background and Issues for Congress, by Ronald O'Rourke.
32 Navy information paper entitled “FFG(X) Cost to Grow to 48 cell VLS,” dated May 14, 2019, received from Navy
Office of Legislative Affairs on June 14, 2019.
Congressional Research Service
15
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Technical Risk
Another potential oversight issue for Congress concerns technical risk in the FFG-62 program.
The Navy can argue that the program’s technical risk has been reduced by use of the parent-
design approach, by the decision to use only systems and technologies that already exist or are
already being developed for use in other programs, rather than new technologies that need to be
developed, and by the congressionally mandated requirement to conduct a land-based test
program for the ship’s engineering plant. Skeptics, while acknowledging these points, might
argue that lead ships in Navy shipbuilding programs nevertheless pose technical risk, because
they serve as the prototypes for their programs.
June 2023 GAO Report
A June 2023 GAO report on the status of various DOD acquisition programs states the following
about the FFG-62 program:
Technology Maturity, Design Stability, and Production Readiness
The Navy identified no critical technologies for FFG 62. The program uses existing mature
systems for its combat and mission systems. However, the Navy expects that integrating
its new Enterprise Air Surveillance Radar (EASR) with the latest baseline of the Aegis
combat system on FFG 62 may present challenges. To mitigate the risks associated with
integration, the Navy procured an EASR emulator to integrate and test with relevant Aegis
system equipment in a lab environment. The program office stated it also expects to use
lessons learned from planned integration and testing of EASR capabilities on multiple other
ship classes—such as the Ford class aircraft carriers—before the radar’s installation on
FFG 62. Once the radar is installed on the lead ship, the program plans to begin testing the
radar interfaces and interoperability with other systems in early 2025. Even with these tests,
as we previously reported, the program’s test plan and 2026 delivery schedule for the lead
ship leaves little margin to address any issues identified in onboard integration testing
without risk of costly and time-intensive rework.
Since the Navy competitively awarded a detail design and construction contract for the
lead ship in April 2020, the FFG 62 program has been working to complete the functional
and detail design of the ship. The overall design incorporates significant changes compared
with the parent design for FFG 62. As we reported last year, these changes include a
lengthened hull, revised bow, and other changes to incorporate combat and mission
systems.
Program officials stated that over 90 percent of the FFG 62 functional design and 80
percent of the detail design—which adds 3D modeling to show the configuration of
equipment on the ship—were completed when construction began on the lead ship in
August 2022. They noted that these results align with the Navy’s general expectations for
design maturity needed before construction begins. However, beginning construction with
an incomplete functional design is inconsistent with leading practices and increases the risk
of costly design changes and rework. Such cost risk adds to existing cost growth challenges
with the lead ship. Specifically, the program office stated the contract’s estimated cost for
the lead ship has increased above the contract’s ceiling price due to a variety of factors,
including defense industrial base issues. March 2023 cost reporting shows the contract’s
estimated costs for the second and third ships are trending in a similar direction.
Program officials stated that the majority of the remaining functional design work is related
to incomplete software. They added that, before the program begins construction for any
of the ship’s 31 design zones, it will complete the detail design of the zone.
Software and Cybersecurity
Congressional Research Service
16
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Program officials stated that planned approval of the software development plan—which
we reported last year was delayed 11 months to February 2022—is now delayed to spring
2023. They noted that a lack of required information on contractor-furnished equipment
contributed to this additional delay. They also stated that they are working with the
shipbuilder on refining the plan based on Navy feedback.
Program officials said that they plan to inform software development with feedback from
formal testing performed by system operators. The program office added that it is using
early integration testing efforts and a land-based test site for hull, mechanical, and electrical
systems to manage potential software development risks.
The program office stated that it revised FFG 62 test plans to include a combined war
game-like exercise in late 2022 that tested cyber capabilities and supported an
interoperability assessment for ship systems. The program also scheduled early integration
testing events in fiscal years 2024 and 2025 at available land-based test sites. According to
the program, these events are intended to assess network cybersecurity controls and reduce
shipboard integration risks for government- and contractor-furnished equipment. The
program plans to complete a major subsystem cybersecurity assessment in fall 2024 and a
full system assessment in 2027 following delivery of the lead ship.
Program Office Comments
We provided a draft of this assessment for program office review and comment. The
program office provided technical comments, which we incorporated where appropriate.
The program office stated that the critical design review and production readiness review—
both conducted in 2022—validated the design and shipyard readiness before moving into
the production phase in August 2022 with the start of construction on the first ship. It added
that these reviews assessed sufficient design maturity—with an 80 percent overall level of
completion—and assessed that the shipyard was ready to begin construction. According to
the program office, the second ship of the class will begin construction in mid-2023.
The program office also stated that it is establishing various test sites to demonstrate FFG
62 propulsion systems and to reduce combat system development and schedule risk
through systems integration testing. It added that it is implementing a system to enhance
ship maintenance and supply planning. The program office also noted its implementation
of a collaborative DOD initiative focused on the development and implementation of data
analysis and sustainment technology capabilities.33
January 2023 DOT&E Report
A January 2023 report from DOD’s Director, Operational Test and Evaluation (DOT&E)—
DOT&E’s annual report for FY2022—stated the following regarding the FFG-62 program:
PERFORMANCE
EFFECTIVENESS
Not enough data are yet available to assess operational effectiveness due to the ship’s early
stage of development.
Preliminary assessment from the EOA [early operational assessment] suggest:
• Reduced developmental risk primarily due to the inclusion of previously fielded systems
in the FFG 62 ship design.
• Some areas that could provide integration and/or performance challenges:
33 Government Accountability Office, Weapon Systems Annual Assessment[:] Programs Are Not Consistently
Implementing Practices That Can Help Accelerate Acquisitions, GAO-23-106059, June 2023, p. 148.
Congressional Research Service
17
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
− FFG 62 will not include a tracker illuminator system typically installed on other Aegis
platforms.
− In FY22, the Navy modified the FFG 62 design to include the foreign-designed, Thales
CAPTAS-4 system, a variable depth sonar. While the Navy believes the integration of the
CAPTAS-4 to the AN/SQQ-89 [antisubmarine warfare system] and the platform is low
risk, DOT&E is unable to assess the integration risk at this time.
− FFG 62 crew size is limited to an estimated 193 officers and enlisted sailors with an
additional 27 personnel that serve in the embarked aviation detachment. Mission success
and sustainability will depend upon effective system autonomy/automation and human
system interfaces.
DOT&E will submit a classified EOA report upon completion of analysis, expected in
2QFY23 [the second quarter of FY2023].
SUITABILITY
Not enough data are yet available to assess operational suitability due to the ship’s early
stage of development.
SURVIVABILITY
Not enough data are yet available to assess ship survivability.
Ongoing LFT&E [live fire test and evaluation] testing, which include near-contact
explosive testing, extended distance multiple plate ballistic testing, and large scale
underwater explosion testing, have closed outstanding vulnerability knowledge gaps and
are expected to enable M&S validation.
In FY22, the Navy continued to update M&S [modeling and simulation] to incorporate
new capabilities, including improvements to their blast and whipping codes. DOT&E
continues to work with the Navy on M&S plans that will support validation and
accreditation of these tools to support the Detail Design Survivability Assessment Report
in FY25.
RECOMMENDATIONS
The Navy should:
1. Provide an update to the FFG 62 TEMP [test and evaluation master plan] that includes
the strategy to test anti-air warfare mission capability by FY24.
2. Procure available and appropriate CAPTAS-4 technical data to mitigate performance
risk and potentially reduce scope of operational testing.
3. In collaboration with operators and operational testers, closely monitor the development
of the mission system autonomy/automation components in the ship design to minimize
risk to mission performance and system maintenance capability.34
2022 Press Reports
April 2022 Press Report Regarding Date for Starting Construction
An April 13, 2022, press report stated
The Navy will begin construction on the first Constellation-class frigate this summer or
fall, later than the program’s goal to begin construction in April.
34 Department of Defense, Director, Operational Test & Evaluation, FY2022 Annual Report, January 2023, pp. 187-
188.
Congressional Research Service
18
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
The program won’t start construction until the critical design review is completed,
according to Capt. Kevin Smith, the frigate program manager.
“You may say, ‘you've been working on design for a while.’ We want to make sure we get
it right before we start cutting steel. Lead ships are hard,” Smith said last week at the Navy
League’s Sea-Air-Space conference.35
March 2022 Press Report Regarding Ship’s Variable Depth Sonar
Following an announcement earlier this week that the Navy would cancel a key anti-
submarine warfare effort bound for the Littoral Combat Ship, the service today also said it
would replace that technology with an alternative system onboard the new Constellation-
class frigate.
Rear Adm. Casey Moton, a senior officer overseeing both ship classes, told a small group
of reporters that “following an assessment,” the Navy chose the CAPTAS-4 variable depth
sonar (VDS) made by Advanced Acoustics Concepts, a subsidiary of DRS and Thales, as
the new frigate VDS.
“The Navy assessed CAPTAS-4 as a low risk VDS option for FFG-62 due to its proven
performance, overall technical readiness level, low risk integration with the SQQ-89 ASW
combat system, ability to integrate with the frigate platform design and ability to meet the
in-yard need date for FFG-62,” Moton said....
The consequences for the last-minute change to the Navy’s contract with Raytheon are still
being worked out, Moton said, but he added that the company had been “professional”
throughout the process to date. The admiral also said he does not anticipate “very much of
a change” to the ship’s cost as a result of the new VDS.36
January 2022 Press Report Regarding Changes to Parent Design
A January 2022 press report about whether changes made to FREMM parent design introduce
technical risk to the FFG-62 program stated
Experts told Breaking Defense that not all changes [from a parent design] are as inherently
risky as they might seem, and the Navy appears to have heeded lessons from previous
controversies....
“In terms of changes from a parent design… as you start to drive further away from a parent
design, there is the risk of cost increase, especially if you have immature equipment that
requires testing or fails testing,” said Steven Wills, a Navy strategy and policy expert at
CNA, a federally funded research and development center that provides advice to the
Pentagon....
When asked this month at the Surface Navy Association’s annual symposium about how
those changes could impact the program’s risk calculus, Capt. Kevin Smith, the
Constellation-class program manager, said the parent design is a starting point, but nothing
more.
“I think it was clear to everyone in Navy leadership as well as congressional leadership
that the parent is there as just that… think of it as a DNA,” he said. “But you do have to
take US Navy standards and apply those, and also the requirements.”...
35 Audrey Decker, “Frigate Construction Pushed Back from April Target Start Date,” Inside Defense, April 13, 2022.
36 Justin Katz, “Navy to Swap Sonar on New Frigate Following Years of Struggles with Testing,” Breaking Defense,
March 31, 2022. See also Megan Eckstein, “US Navy to Terminate DART Sonar Development with Raytheon,”
Defense News, March 31, 2022; Rich Abott, “Navy Cites Reasons For Ditching DART Sonar For LCS, Frigate,”
Defense Daily, September 1, 2022.
Congressional Research Service
19
link to page 28 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
“The only thing that we’ve [the Navy] done actually—it’s a change to the requirements—
is buy American, because that was a statute from Congress,” Smith said, referring to
legislation mandating certain parts and percentages of US warships be manufactured
domestically....
But CNA’s Wills said one major difference between the FREMM and the Constellation,
the elongated hull form, is not surprising because of differences in how Europeans and the
United States go about building warships.
“You don’t incur a lot of costs in making the ship bigger. That shouldn’t slow you down.
That shouldn’t cause testing to fail,” he said. “You’re going to have to buy more steel and
there will be some changes. The benefit that they seem to be going for… is they’re looking
for some additional margins throughout the life of the ship.”
Matthew Collette, who teaches naval architecture and marine engineering at the University
of Michigan, said fully adopting a parent design without modification is “exceptionally
rare” especially for the US Navy, which has developed standards for internal layouts and
adheres to congressional policy dictating supply chain options.
“Changing the overall dimensions of the ship is probably lowering the overall risk to the
program, not raising it,” Collette told Breaking Defense. “Given that we are changing the
internals of the design, adhering strictly to the old hull form would actually increase the
overall risk to the program, as you end up adding complexity by trying to shoehorn in
components in a less-than-ideal layout.”
He cited the Ticonderoga-class cruisers and Whidbey Island-class dock landing ships as
examples where Navy programs have historically suffered because the service attempted
to maintain the ships’ external design while altering its internal layout.
Collette said there are three principles a shipbuilding program should follow to reduce the
risk of modifying a parent design. The first is choosing proven systems when swapping out
components. In the Constellation’s case, the Navy has done just that by choosing systems
such as Aegis, the Mk 41 Vertical Launching System and the SLQ-32 from the Surface
Electronic Warfare Improvement Program.
The second principle is to thoroughly test new components ashore, a requirement Congress
codified in law after finding out the Navy failed to do this on other systems that proved
troublesome for the Ford.
The last principle is having a completed definition of the parent design, such as a 3D model,
a parameter for which Collette and other analysts have no way of assessing from outside
the Navy’s program office.
“Even with some changes, the program is still benefiting from access to the original design
models, and the knowledge gained in building and operating vessels that are highly similar,
but no longer exactly the same, to the US Navy variant,” Collette said.37
See also the Appendix regarding the Navy’s use of a guaranty rather than a warranty in the Detail
Design and Construction (DD&C) contract for the first 10 ships in the FFG-62 program.
37 Justin Katz, “For Navy’s New Frigate, Design Changes Carry Risks and Rewards,” Breaking Defense, January 24,
2022.
Congressional Research Service
20
link to page 25 link to page 25 link to page 25 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Legislative Activity for FY2024
Summary of Congressional Action on FY2024 Funding Request
Table 2 summarizes congressional action on the Navy’s FY2024 funding request for the FFG-62
program.
Table 2. Congressional Action on FY2024 Procurement Funding Request
Millions of dollars, rounded to nearest tenth.
Authorization
Appropriation
Request
HASC
SASC
Final
HAC
SAC
Final
Procurement
2,173.7
2,163.7
2,173.7
2,163.7
2,133.9
2,223.7
Advance procurement (AP)
0
0
0
0
0
0
(Procurement quantity)
(2)
(2)
(2)
(2)
(2)
(2)
Source: Table prepared by CRS based on FY2024 Navy budget submission, committee and conference reports,
and explanatory statements on the FY2024 National Defense Authorization Act and the FY2024 DOD
Appropriations Act.
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is
House Appropriations Committee; SAC is Senate Appropriations Committee.
FY2024 National Defense Authorization Act (H.R. 2670/S. 2226)
House
The House Armed Services Committee, in its report (H.Rept. 118-125 of June 30, 2023) on H.R.
2670, recommended the funding levels shown in the HASC column of Table 2. The
recommended reduction of $10.0 million is for “Insufficient justification.” (Page 445)
Senate
The Senate Armed Services Committee, in its report (S.Rept. 118-58 of July 12, 2023) on S.
2226, recommended the funding levels shown in the SASC column of Table 2.
S.Rept. 118-58 states
Frigate second shipyard study
The committee notes that the Department of the Navy will not be able to reach the policy
goal of 355 battle force ships unless it expands production. The U.S. Navy’s 30-year
shipbuilding plan, dated December 9, 2020, anticipated standing up a second shipyard for
the FFG–62 Constellation-class frigate in fiscal year 2023 and procuring four frigates in
fiscal year 2025. The committee further notes that the statement accompanying the
Consolidated Appropriations Act for Fiscal Year 2022 (Public Law 117–103) paused plans
for a second shipyard until the U.S. Navy proved the frigate design. With the first four
ships of the class due to start construction before the close of fiscal year 2024, the
committee believes the time is appropriate to study the requirements and schedule for a
second shipyard.
The committee directs the Secretary of the Navy to develop a plan for a second shipyard
to produce the Constellation-class frigate. The plan shall address: (1) The stability of
Congressional Research Service
21
link to page 25 link to page 25 link to page 25 Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
program requirements and maturity of ship design; (2) A schedule for ordering a mature
technical data package; (3) The contracting strategy to include how the U.S. Navy plans to
compete the second shipyard; (4) Funding requirements by fiscal year; and (5) Capacity of
the shipbuilding industrial base to support two construction yards for frigates to include
available workforce.
The Secretary of the Navy shall provide an interim briefing on such a plan to the
congressional defense committees not later than February 1, 2024. (Page 229)
Conference
The conference report (H.Rept. 118-301 of December 6, 2023) on H.R. 2670 recommended the
funding levels shown in the authorization final column of Table 2. The recommended reduction
of $10.0 million is for “Insufficient justification.” (Page 1412)
FY2024 DOD Appropriations Act (H.R. 4365/S. 2587)
House
The House Appropriations Committee, in its report (H.Rept. 118-121 of June 27, 2023) on H.R.
4365, recommended the funding levels shown in the HAC column of Table 2. The recommended
reduction of $39.837 million is for “GFE [government-furnished equipment] unjustified growth”
($30.287 million) and “Change orders unjustified growth” ($9.550 million). (Page 145)
Section 8093(b) of H.R. 4365 states
SEC. 8093….
(b) None of the funds provided in this Act for the FFG(X) Frigate program shall be used to
award a new contract that provides for the acquisition of the following components unless
those components are manufactured in the United States: Air circuit breakers;
gyrocompasses; electronic navigation chart systems; steering controls; pumps; propulsion
and machinery control systems; totally enclosed lifeboats; auxiliary equipment pumps;
shipboard cranes; auxiliary chill water systems; and propulsion propellers: Provided, That
the Secretary of the Navy shall incorporate United States manufactured propulsion engines
and propulsion reduction gears into the FFG(X) Frigate program beginning not later than
with the eleventh ship of the program.
Senate
The Senate Appropriations Committee, in its report (S.Rept. 118-81 of July 27, 2023) on S. 2587,
recommended the funding levels shown in the SAC column of Table 2. The recommended
increase of $50.0 million is for “Program increase: Frigate industrial base and workforce
development.” (Page 135)
Section 8095(b) of S. 2587 states
SEC. 8095.…
(b) None of the funds provided in this Act for the FFG(X) Frigate program shall be used to
award a new contract that provides for the acquisition of the following components unless
those components are manufactured in the United States: Air circuit breakers;
gyrocompasses; electronic navigation chart systems; steering controls; pumps; propulsion
and machinery control systems; totally enclosed lifeboats; auxiliary equipment pumps;
shipboard cranes; auxiliary chill water systems; and propulsion propellers: Provided, That
the Secretary of the Navy shall incorporate United States manufactured propulsion engines
Congressional Research Service
22
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
and propulsion reduction gears into the FFG(X) Frigate program beginning not later than
with the eleventh ship of the program.
Congressional Research Service
23
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
Appendix. Guaranty vs. Warranty in Construction
Contract
This appendix presents background information regarding the Navy’s use of a guaranty rather
than a warranty in the Detail Design and Construction (DD&C) contract for the first 10 ships in
the FFG-62 program. An August 2019 GAO report on the FFG-62 program states
The Navy plans to use a fixed-price incentive contract for FFG(X) detail design and
construction. This is a notable departure from prior Navy surface combatant programs that
used higher-risk cost-reimbursement contracts for lead ship construction. The Navy also
plans to require that each ship has a minimum guaranty of $5 million to correct shipbuilder-
responsible defects identified in the 18 months following ship delivery. However, Navy
officials discounted the potential use of a warranty—another mechanism to address the
correction of shipbuilder defects—stating that their use could negatively affect
shipbuilding cost and reduce competition for the contract award. The Navy provided no
analysis to support these claims and has not demonstrated why the use of warranties is not
a viable option. The Navy’s planned use of guarantees helps ensure the FFG(X) shipbuilder
is responsible for correcting defects up to a point, but guarantees generally do not provide
the same level of coverage as warranties. GAO found in March 2016 that the use of a
guaranty did not help improve cost or quality outcomes for the ships reviewed. GAO also
found the use of a warranty in commercial shipbuilding and certain Coast Guard ships
improves cost and quality outcomes by requiring the shipbuilders to pay to repair defects.
The FFG(X) request for proposal offers the Navy an opportunity to solicit pricing for a
warranty to assess the cost-effectiveness of the different mechanisms to address ship
defects.38
As discussed in another CRS report,39 in discussions of Navy (and also Coast Guard)
shipbuilding, a question that sometimes arises is whether including a warranty in a shipbuilding
contract is preferable to not including one. The question can arise, for example, in connection
with a GAO finding that “the Navy structures shipbuilding contracts so that it pays shipbuilders
to build ships as part of the construction process and then pays the same shipbuilders a second
time to repair the ship when construction defects are discovered.”40
Including a warranty in a shipbuilding contract (or a contract for building some other kind of
defense end item), while potentially valuable, might not always be preferable to not including
one—it depends on the circumstances of the acquisition, and it is not necessarily a valid criticism
of an acquisition program to state that it is using a contract that does not include a warranty (or a
weaker form of a warranty rather than a stronger one).
Including a warranty generally shifts to the contractor the risk of having to pay for fixing
problems with earlier work. Although that in itself could be deemed desirable from the
government’s standpoint, a contractor negotiating a contract that will have a warranty will
incorporate that risk into its price, and depending on how much the contractor might charge for
doing that, it is possible that the government could wind up paying more in total for acquiring the
38 Government Accountability Office, Guide Missile Frigate[:] Navy Has Taken Steps to Reduce Acquisition Risk, but
Opportunities Exist to Improve Knowledge for Decision Makers, GAO-19-512, August 2019, summary page.
39 See CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by
Ronald O'Rourke.
40 See Government Accountability Office, Navy Shipbuilding[:] Past Performance Provides Valuable Lessons for
Future Investments, GAO-18-238SP, June 2018, p. 21. A graphic on page 21 shows a GAO finding that the
government was financially responsible for shipbuilder deficiencies in 96% of the cases examined by GAO, and that
the shipbuilder was financially responsible for shipbuilder deficiencies in 4% of the cases.
Congressional Research Service
24
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
item (including fixing problems with earlier work on that item) than it would have under a
contract without a warranty.
When a warranty is not included in the contract and the government pays later on to fix problems
with earlier work, those payments can be very visible, which can invite critical comments from
observers. But that does not mean that including a warranty in the contract somehow frees the
government from paying to fix problems with earlier work. In a contract that includes a warranty,
the government will indeed pay something to fix problems with earlier work—but it will make
the payment in the less-visible (but still very real) form of the up-front charge for including the
warranty, and that charge might be more than what it would have cost the government, under a
contract without a warranty, to pay later on for fixing those problems.
From a cost standpoint, including a warranty in the contract might or might not be preferable,
depending on the risk that there will be problems with earlier work that need fixing, the potential
cost of fixing such problems, and the cost of including the warranty in the contract. The point is
that the goal of avoiding highly visible payments for fixing problems with earlier work and the
goal of minimizing the cost to the government of fixing problems with earlier work are separate
and different goals, and that pursuing the first goal can sometimes work against achieving the
second goal.41
DOD’s guide on the use of warranties states the following:
Federal Acquisition Regulation (FAR) 46.7 states that “the use of warranties is not
mandatory.” However, if the benefits to be derived from the warranty are commensurate
with the cost of the warranty, the CO [contracting officer] should consider placing it in the
contract. In determining whether a warranty is appropriate for a specific acquisition, FAR
Subpart 46.703 requires the CO to consider the nature and use of the supplies and services,
the cost, the administration and enforcement, trade practices, and reduced requirements.
The rationale for using a warranty should be documented in the contract file....
In determining the value of a warranty, a CBA [cost-benefit analysis] is used to measure
the life cycle costs of the system with and without the warranty. A CBA is required to
determine if the warranty will be cost beneficial. CBA is an economic analysis, which
basically compares the Life Cycle Costs (LCC) of the system with and without the warranty
to determine if warranty coverage will improve the LCCs. In general, five key factors will
drive the results of the CBA: cost of the warranty + cost of warranty administration +
compatibility with total program efforts + cost of overlap with Contractor support +
intangible
savings.
Effective
warranties
integrate
reliability,
maintainability,
supportability, availability, and life-cycle costs. Decision factors that must be evaluated
include the state of the weapon system technology, the size of the warranted population,
the likelihood that field performance requirements can be achieved, and the warranty
period of performance.42
41 It can also be noted that the country’s two largest builders of Navy ships—General Dynamics (GD) and Huntington
Ingalls Industries (HII)—derive about 60% and 96%, respectively, of their revenues from U.S. government work. (See
General Dynamics, 2016 Annual Report, page 9 of Form 10-K [PDF page 15 of 88]) and Huntington Ingalls Industries,
2016 Annual Report, page 5 of Form 10-K [PDF page 19 of 134]). These two shipbuilders operate the only U.S.
shipyards currently capable of building several major types of Navy ships, including submarines, aircraft carriers, large
surface combatants, and amphibious ships. Thus, even if a warranty in a shipbuilding contract with one of these firms
were to somehow mean that the government did not have pay under the terms of that contract—either up front or later
on—for fixing problems with earlier work done under that contract, there would still be a question as to whether the
government would nevertheless wind up eventually paying much of that cost as part of the price of one or more future
contracts the government may have that firm.
42 Department of Defense, Department of Defense Warranty Guide, Version 1.0, September 2009, accessed July 13,
2017, at https://www.acq.osd.mil/dpap/pdi/uid/docs/departmentofdefensewarrantyguide[1].doc.
Congressional Research Service
25
Navy Constellation (FFG-62) Class Frigate Program: Background and Issues for Congress
In response to a draft version of GAO’s August 2019 report, the Navy stated
As a part of the planning for the procurement of detail design and construction for FFG(X),
the Navy determined that a guaranty, rather than a commercial-type warranty, will be
implemented for the program. As a part of the FFG(X) detail design and construction
request for proposals [RFP] released on June 20, 2019, the Navy asked contractors to
include a limit of liability of at least $5 million per ship and a guaranty period of 18 months
beyond preliminary acceptance of each ship. Further, the solicitation allows offerors to
propose as additional limit of liability amount beyond the required $5 million amount, up
to and including an unlimited liability. This arrangement represents an appropriate balance
between price considerations and risks, ensuring that the shipbuilder is accountable for the
correction of defects that follow preliminary acceptance, while allowing each shipbuilder
to use its own business judgement in proposing the value of the limit of liability. The Navy
released the solicitation prior to this GAO recommendation and is unable to modify the
current solicitation because it would cause an unacceptable delay to the FFG(X) program.
To support the GAO recommendation to request pricing for an unlimited warranty, the
Navy will request pricing for unlimited warranty before exercising the first ship option and
evaluate the business case.43
Author Information
Ronald O'Rourke
Specialist in Naval Affairs
Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.
43 Government Accountability Office, Guide Missile Frigate[:] Navy Has Taken Steps to Reduce Acquisition Risk, but
Opportunities Exist to Improve Knowledge for Decision Makers, GAO-19-512, August 2019 (revised September 5,
2019 to include an omitted page in the report section, [and] comments from the Department of Defense), pp. 44-45.
Congressional Research Service
R44972 · VERSION 108 · UPDATED