

 
Navy Ford (CVN-78) Class Aircraft Carrier 
Program: Background and Issues for Congress 
Updated November 16, 2023 
Congressional Research Service 
https://crsreports.congress.gov 
RS20643 
 
  
 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Summary 
The aircraft carriers CVN-78, CVN-79, CVN-80, and CVN-81 are the first four ships in the 
Navy’s new Gerald R. Ford (CVN-78) class of nuclear-powered aircraft carriers (CVNs). The 
Navy’s proposed FY2024 budget requests $2,540.4 million (i.e., about $2.5 billion) in 
procurement funding for Ford-class ships, including $624.6 million for CVN-79, $1,115.3 million 
for CVN-80, and $800.5 million for CVN-81. 
CVN-78 (Gerald R. Ford) was procured in FY2008. The ship’s procurement final cost was 
$13,316.5 million (i.e., about $13.3 billion) in then-year dollars. The ship was commissioned into 
service on July 22, 2017, and achieved initial operational capability in December 2021. The 
ship’s first deployment was delayed by a need to complete work on the ship’s weapons elevators 
and correct other technical problems aboard the ship. The first deployment—a two-month 
“service-retained deployment” in Atlantic waters that served as an operational stress test—
reportedly began on October 4, 2022, more than five years after the ship was commissioned into 
service, and ended on November 26, 2022. The ship reportedly will make its first full-length 
deployment in 2023. 
CVN-79 (John F. Kennedy) was procured in FY2013. The Navy’s proposed FY2024 budget 
estimates the ship’s procurement cost at $12,700.0 million (i.e., $12.7 billion) in then-year 
dollars. The ship is being built with an improved shipyard fabrication and assembly process that 
incorporates lessons learned from the construction of CVN-78. CVN-79 is scheduled for delivery 
to the Navy in July 2025. 
CVN-80 (Enterprise) was procured in FY2018. The Navy’s proposed FY2024 budget estimates 
the ship’s procurement cost at $12,812.9 million (i.e., about $12.8 billion) in then-year dollars. 
The ship is scheduled for delivery to the Navy in March 2028. 
CVN-81 (Doris Miller) is treated in this report as a ship that was procured in FY2019, consistent 
with congressional action on the Navy’s FY2019 budget. (The Navy’s FY2024 budget 
submission, like its FY2021-FY2023 submissions, shows CVN-81 as a ship that was procured in 
FY2020.) The Navy’s FY2024 budget submission estimates the ship’s procurement cost at 
$12,929.1 million (i.e., about $12.9 billion) in then-year dollars. The ship is scheduled for 
delivery to the Navy in February 2032. 
CVN-80 and CVN-81 are being procured under a two-ship block buy contract that was authorized 
by Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (H.R. 5515/P.L. 115-232 of August 13, 2018). The use of the two-ship block buy contract 
reduced the combined estimated procurement cost of the two ships. 
Oversight issues for Congress for the CVN-78 program include the following: 
•  the future aircraft carrier force level; 
•  cost growth in the CVN-78 program, Navy efforts to stem that growth, and Navy 
efforts to manage costs so as to stay within the program’s cost caps;  
•  the delay in CVN-78’s first deployment; 
•  additional CVN-78 program issues that were raised in a January 2023 report from 
the Department of Defense’s (DOD’s) Director of Operational Test and 
Evaluation (DOT&E) and a June 2023 Government Accountability Office (GAO) 
report on DOD weapon systems; and 
•  the procurement of aircraft carriers after CVN-81.
Congressional Research Service 
 link to page 5  link to page 5  link to page 5  link to page 5  link to page 5  link to page 5  link to page 6  link to page 6  link to page 6  link to page 6  link to page 7  link to page 7  link to page 7  link to page 8  link to page 8  link to page 8  link to page 9  link to page 10  link to page 11  link to page 11  link to page 11  link to page 12  link to page 12  link to page 13  link to page 15  link to page 15  link to page 16  link to page 16  link to page 16  link to page 17  link to page 20  link to page 20  link to page 20  link to page 22  link to page 24  link to page 24  link to page 24  link to page 30  link to page 31  link to page 33  link to page 33  link to page 33  link to page 33  link to page 34  link to page 34  link to page 34 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Contents 
Introduction ..................................................................................................................................... 1 
Background ..................................................................................................................................... 1 
Current Navy Aircraft Carrier Force ......................................................................................... 1 
Statutory Requirements for Carriers and Carrier Air Wings ..................................................... 1 
Requirement to Maintain Not Less Than 11 Carriers ......................................................... 1 
Prohibition on Retiring Nuclear-Powered Aircraft Carriers Prior to Refueling .................. 1 
Requirement to Maintain a Minimum of Nine Carrier Air Wings ...................................... 2 
Navy’s Aircraft Carrier Force-Level Goal ................................................................................ 2 
Current Aircraft Carrier Force-Level Goal ......................................................................... 2 
Emerging Aircraft Carrier Force-Level Goal ...................................................................... 2 
Projected Number of Aircraft Carriers ...................................................................................... 3 
Incremental Funding Authority for Aircraft Carriers ................................................................ 3 
Aircraft Carrier Construction Industrial Base ........................................................................... 3 
Gerald R. Ford (CVN-78) Class Program ................................................................................. 4 
Overview ............................................................................................................................. 4 
CVN-78 (Gerald R. Ford) .................................................................................................. 4 
CVN-79 (John F. Kennedy) ................................................................................................ 5 
CVN-80 (Enterprise) .......................................................................................................... 6 
CVN-81 (Doris Miller) ....................................................................................................... 7 
Two-Ship Block Buy Contract for CVN-80 and CVN-81 .................................................. 7 
Interest in Potential Two-Ship Block Buy Contract for CVN-82 and CVN-83 .................. 7 
Program Procurement Cost Cap .......................................................................................... 8 
Program Procurement Funding ........................................................................................... 8 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget .............................. 9 
Issues for Congress for FY2024 ..................................................................................................... 11 
Future Aircraft Carrier Force Level ......................................................................................... 11 
Cost Growth ............................................................................................................................ 12 
Overview ........................................................................................................................... 12 
CVN-78 ............................................................................................................................. 12 
CVNs 79, 80, and 81 ......................................................................................................... 13 
Delay in CVN-78’s First Deployment ..................................................................................... 16 
Overview ........................................................................................................................... 16 
Weapons Elevators ............................................................................................................ 16 
Other Technical Challenges .............................................................................................. 18 
Potential Oversight Questions ........................................................................................... 20 
Issues Raised in DOT&E and GAO Reports .......................................................................... 20 
January 2023 DOT&E Report .......................................................................................... 20 
June 2023 GAO Report ..................................................................................................... 26 
Procurement of Aircraft Carriers After CVN-81 ..................................................................... 27 
Legislative Activity for FY2024 .................................................................................................... 29 
Summary of Congressional Action on FY2024 Funding Request .......................................... 29 
FY2024 National Defense Authorization Act (H.R. 2670/S. 2226) ........................................ 29 
House ................................................................................................................................ 29 
Senate ................................................................................................................................ 30 
FY2024 DOD Appropriations Act (H.R. 4365/S. 2587) ......................................................... 30 
House ................................................................................................................................ 30 
Congressional Research Service 
 link to page 34  link to page 8  link to page 9  link to page 10  link to page 13  link to page 14  link to page 33  link to page 35  link to page 38 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Senate ................................................................................................................................ 30 
 
Figures 
Figure 1. USS Gerald R. Ford (CVN-78) ....................................................................................... 4 
Figure 2. USS Gerald R. Ford (CVN-78) ....................................................................................... 5 
Figure 3. USS Gerald R. Ford (CVN-78) ....................................................................................... 6 
  
Tables 
Table 1. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2028 ............................. 9 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 .......................... 10 
Table 3. Congressional Action on FY2024 Procurement Funding Request .................................. 29 
  
Appendixes 
Appendix. Background Information on Two-Ship Block Buy for CVN-80 and CVN-81 ............ 31 
 
Contacts 
Author Information ........................................................................................................................ 34 
 
Congressional Research Service 
 link to page 5 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Introduction 
This report provides background information and potential oversight issues for Congress on the 
Gerald R. Ford (CVN-78) class nuclear-powered aircraft carrier (CVN) aircraft carrier program. 
The Navy’s proposed FY2024 budget requests $2,540.4 million (i.e., about $2.5 billion) in 
procurement funding for the program. Congress’s decisions on the CVN-78 program could 
substantially affect Navy capabilities and funding requirements and the shipbuilding industrial 
base. 
Background 
Current Navy Aircraft Carrier Force 
The Navy’s current aircraft carrier force consists of 11 CVNs,1 including 10 Nimitz-class ships 
(CVNs 68 through 77) that entered service between 1975 and 2009, and one Gerald R. Ford 
(CVN-78) class ship that was commissioned into service on July 22, 2017.2  
Statutory Requirements for Carriers and Carrier Air Wings 
Requirement to Maintain Not Less Than 11 Carriers 
10 U.S.C. 8062(b) requires the Navy to maintain a force of not less than 11 operational aircraft 
carriers.3 The requirement for the Navy to maintain not less than a certain number of operational 
aircraft carriers was established by Section 126 of the FY2006 National Defense Authorization 
Act (H.R. 1815/P.L. 109-163 of January 6, 2006), which set the number at 12 carriers. The 
requirement was changed from 12 carriers to 11 carriers by Section 1011(a) of the FY2007 John 
Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006).4 
Prohibition on Retiring Nuclear-Powered Aircraft Carriers Prior to Refueling 
Section 1054 of the FY2021 National Defense Authorization Act (NDAA) (H.R. 6395/P.L. 116-
283) amended 10 U.S.C. 8062 to create a new subsection (f) stating: “A nuclear powered aircraft 
carrier may not be retired before its first refueling.’’ 
 
1 The Navy’s last remaining conventionally powered carrier (CV), Kitty Hawk (CV-63), was decommissioned on 
January 31, 2009. 
2 The commissioning into service of CVN-78 on July 22, 2017, ended a period during which the carrier force had 
declined to 10 ships—a period that began on December 1, 2012, with the inactivation of the one-of-a-kind nuclear-
powered aircraft carrier Enterprise (CVN-65), a ship that entered service in 1961. 
3 10 U.S.C. 8062 was previously numbered as 10 U.S.C. 5062. It was renumbered as 10 U.S.C. 8062 by Section 807 of 
the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-232 of August 13, 
2018), which directed a renumbering of sections and titles of Title 10 relating to the Navy and Marine Corps. (Sections 
806 and 808 of P.L. 115-232 directed a similar renumbering of sections and titles relating to the Air Force and Army, 
respectively.) 
4 As mentioned in footnote 2, the carrier force dropped from 11 ships to 10 ships between December 1, 2012, when 
Enterprise (CVN-65) was inactivated, and July 22, 2017, when CVN-78 was commissioned into service. Anticipating 
the gap between the inactivation of CVN-65 and the commissioning of CVN-78, the Navy asked Congress for a 
temporary waiver of 10 U.S.C. 8062(b) to accommodate the period between the two events. Section 1023 of the 
FY2010 National Defense Authorization Act (H.R. 2647/P.L. 111-84 of October 28, 2009) authorized the waiver, 
permitting the Navy to have 10 operational carriers between the inactivation of CVN-65 and the commissioning of 
CVN-78. 
Congressional Research Service  
 
1 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Requirement to Maintain a Minimum of Nine Carrier Air Wings 
10 U.S.C. 8062(e), which was added by Section 1042 of the FY2017 National Defense 
Authorization Act (S. 2943/P.L. 114-328 of December 23, 2016), requires the Navy to maintain a 
minimum of nine carrier air wings.5 
Navy’s Aircraft Carrier Force-Level Goal 
Current Aircraft Carrier Force-Level Goal 
In December 2016, the Navy released a force-level goal for achieving and maintaining a fleet of 
355 ships, including 12 aircraft carriers6—one more than the minimum of 11 carriers required by 
10 U.S.C. 8062(b). 
Emerging Aircraft Carrier Force-Level Goal 
The Navy and Department of Defense (DOD) have been working since 2019 to develop a new 
force-level goal to replace the 355-ship force-level goal of 2016. Studies of this emerging force-
level goal that have been released by the Navy in summary form suggest that the new force-level 
goal could call for achieving and maintaining a Navy with a carrier force of 8 to 12 carriers, to be 
supplemented (in the case of the lower end of that range) by up to 6 light aircraft carriers 
(CVLs).7 
Given the time needed to build a carrier and the projected retirement dates of existing carriers, 
increasing the carrier force from 11 ships to 12 ships on a sustained basis would take a number of 
years. Under the Navy’s FY2020 30-year shipbuilding plan, for example, carrier procurement 
would shift from five-year centers (i.e., one carrier procured each five years) to four-year centers 
after the procurement of CVN-82 in FY2028, and a 12-carrier force would be achieved on a 
sustained basis in the 2060s.8 
 
5 10 U.S.C. 8062(e) states the following: 
The Secretary of the Navy shall ensure that- 
(1) the Navy maintains a minimum of 9 carrier air wings until the earlier of- 
(A) the date on which additional operationally deployable aircraft carriers can fully support a 10th 
carrier air wing; or 
(B) October 1, 2025; 
(2) after the earlier of the two dates referred to in subparagraphs (A) and (B) of paragraph (1), the 
Navy maintains a minimum of 10 carrier air wings; and 
(3) for each such carrier air wing, the Navy maintains a dedicated and fully staffed headquarters. 
6 For more on the 355-ship force-level goal, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: 
Background and Issues for Congress, by Ronald O'Rourke.  
7 For the effort to develop a successor to the 355-ship goal of 2016, including the studies that the Navy has released in 
summary form, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for 
Congress, by Ronald O'Rourke.  
8 The projected size of the carrier force in the Navy’s FY2020 30-year (FY2020-FY2049) shipbuilding plan reflected 
the Navy’s now-withdrawn FY2020 budget proposal to not fund the RCOH for the aircraft carrier CVN-75 (Harry S. 
Truman), and to instead retire the ship around FY2024. With the withdrawal of this budget proposal, the projected size 
of the carrier force became, for the period FY2022-FY2047, one ship higher than what is shown in the Navy’s FY2020 
budget submission. The newly adjusted force-level projection, reflecting the withdrawal of the proposal to retire CVN-
75 around FY2024, were as follows: The force is projected to include 11 ships in FY2020-FY2021, 12 ships in 
FY2022-FY2024, 11 ships in FY2025-FY2026, 10 ships in FY2027, 11 ships in FY2028-FY2039, 10 ships in FY2040, 
(continued...) 
Congressional Research Service  
 
2 
 link to page 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Projected Number of Aircraft Carriers 
The Navy’s FY2024 30-year (FY2024-FY2053) shipbuilding plan includes three alternative 30-
year shipbuilding profiles for the period FY2029-FY2053. Under all the three profiles, the carrier 
force is projected to include 11 carriers in most years between FY2024 and FY2039. Under the 
first and second profiles, the carrier force is to include 10 carriers from FY2040 until FY2045, 
and then 9 or sometimes 10 carriers from FY2046 through FY2053. Under the third profile, the 
carrier force is projected to include 10 carriers in most years from FY2040 through FY2053. 
Incremental Funding Authority for Aircraft Carriers 
Congress since the 1990s has authorized DOD to use incremental funding for procuring certain 
Navy ships, most notably aircraft carriers.9 Under incremental funding, some of the funding 
needed to fully fund a ship is provided in one or more years after the year in which the ship is 
procured.10 
Aircraft Carrier Construction Industrial Base 
All U.S. aircraft carriers procured since FY1958 have been built by Huntington Ingalls 
Industries/Newport News Shipbuilding (HII/NNS), of Newport News, VA. HII/NNS is the only 
U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The aircraft carrier 
construction industrial base as of 2019 also included roughly 2,000 supplier firms in 46 states.11 
 
11 ships in FY2041, 10 ships in FY2042-FY2044, 11 ships in FY2045, 10 ships in FY2046-FY2047, 9 ships in 
FY2048, and 10 ships in FY2049. 
9 The provisions providing authority for using incremental funding for procuring Ford-class carriers are as follows: 
Section 121 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 
2006) granted the Navy the authority to use four-year incremental funding for CVNs 78, 79, and 80. Under this 
authority, the Navy could fully fund each of these ships over a four-year period that includes the ship’s year of 
procurement and three subsequent years. 
Section 124 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 112-81 of December 31, 2011) 
amended Section 121 of P.L. 109-364 to grant the Navy the authority to use five-year incremental funding for CVNs 
78, 79, and 80. Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice originally applied to 
CVNs 79 and 80, although as discussed in the footnote to Table 1, the Navy made use of the authority in connection 
with an FY2020 reprogramming action that reprogrammed $86.0 million of funding into FY2012 for CVN-78. 
Section 121 of the FY2013 National Defense Authorization Act (H.R. 4310/P.L. 112-239 of January 2, 2013) amended 
Section 121 of P.L. 109-364 to grant the Navy the authority to use six-year incremental funding for CVNs 78, 79, and 
80. Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice applies to CVNs 79 and 80. 
Section 121(c) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-
232 of August 13, 2018) authorized incremental funding to be used for making payments under the two-ship block buy 
contract for the construction of CVN-80 and CVN-81. This provision does not limit the total number of years across 
which incremental funding may be used to procure either ship. 
10 For more on full funding and incremental funding, see CRS Report RL31404, Defense Procurement: Full Funding 
Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report 
RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by 
Ronald O'Rourke. 
11 Source: Jennifer Boykin, president of HII/NNS, as quoted in Marcus Weisgerber, “US Navy Places First 2-Carrier 
Order in Three Decades,” Defense One, January 31, 2019. 
Congressional Research Service  
 
3 
 link to page 8  link to page 9  link to page 10 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Gerald R. Ford (CVN-78) Class Program 
Overview 
The Gerald R. Ford (CVN-78) class carrier design (Figure 1, Figure 2, and Figure 3) is the 
successor to the Nimitz-class carrier design. The Ford-class design uses the basic Nimitz-class hull 
form but incorporates several improvements, including features permitting the ship to generate 
more aircraft sorties per day, more electrical power for supporting ship systems, and features 
permitting the ship to be operated by several hundred fewer sailors than a Nimitz-class ship, 
reducing 50-year life-cycle operating and support (O&S) costs for each ship by about $4 billion 
compared to the Nimitz-class design, the Navy estimates. Navy plans call for procuring at least 
four Ford-class carriers—CVN-78, CVN-79, CVN-80, and CVN-81. 
Figure 1. USS Gerald R. Ford (CVN-78) 
 
Source: Cropped version of U.S. Navy photograph 170408-N-WZ792-198, showing CVN-78 on April 8, 2017. 
Accessed March 17, 2021, at https://www.navy.mil/Resources/Photo-Gallery/igphoto/2001728935/. 
CVN-78 (Gerald R. Ford) 
CVN-78, which was named Gerald R. Ford in 2007,12 was procured in FY2008. The ship’s final 
procurement cost was $13,316.5 million (i.e., about $13.3 billion) in then-year dollars. The ship 
was commissioned into service on July 22, 2017, and achieved initial operational capability 
(IOC) in December 2021.13 The ship’s first deployment was delayed by a need to complete work 
on the ship’s weapons elevators and correct other technical problems aboard the ship. The first 
deployment—a two-month “service-retained deployment” in Atlantic waters that served as an 
operational stress test—reportedly began on October 4, 2022, more than five years after the ship 
 
12 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of 
Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced that 
CVN-78 would be so named. CVN-78 and other carriers built to the same design are consequently referred to as Ford 
(CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for 
Congress, by Ronald O'Rourke. 
13 See, for example, Marcus Weisgerber, “Surprise! The Navy Declared Its Newest Carrier Battle-Ready Last Year,” 
Defense One, April 5, 2022. 
Congressional Research Service  
 
4 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
was commissioned into service, and ended on November 26, 2022.14 The ship reportedly began 
its first full-length deployment on May 2, 2023.15 
Figure 2. USS Gerald R. Ford (CVN-78) 
 
Source: U.S. Navy photograph 200515-N-QI093-1151, showing CVN-78 on May 15, 2020, with the oiler USNS 
Patuxent (T-AO 201) alongside. Accessed March 17, 2021, at https://allhands.navy.mil/Media/Gallery/igphoto/
2002340124/. 
CVN-79 (John F. Kennedy) 
CVN-79, which was named John F. Kennedy on May 29, 2011,16 was procured in FY2013. The 
Navy’s proposed FY2024 budget estimates the ship’s procurement cost at $12,700.0 million (i.e., 
$12.7 billion) in then-year dollars. On August 10, 2023, the Navy notified the congressional 
defense committees that, using authority granted by Section 121 of the FY2020 National Defense 
 
14 See, for example, Nick Wilson, “First-in-Class Ford Aircraft Carrier Completes Inaugural Deployment,” Inside 
Defense, November 29, 2022; Sam LaGrone, “Video: USS Gerald R. Ford Back in Norfolk After Two Months in the 
Atlantic,” USNI News, November 26 (updated November 27), 2022; Diana Stancy Correll, “USS Gerald R Ford Slated 
to Wrap Up First Deployment,” Navy Times, November 23, 2022. 
15 See, for example, Diana Stancy Correll, “USS Gerald R Ford Leaves Norfolk for First Full-Length Deployment,” 
Navy Times, May 2, 2023; Aaron-Matthew Lariosa, “Aircraft Carrier USS Gerald R. Ford Departs Norfolk for 
Worldwide Deployment,” USNI News, May 2, 2023. 
16 See “Navy Names Next Aircraft Carrier USS John F. Kennedy,” Navy News Service, May 29, 2011, accessed online 
on June 1, 2011, at http://www.navy.mil/search/display.asp?story_id=60686. See also Peter Frost, “U.S. Navy’s Next 
Aircraft Carrier Will Be Named After The Late John F. Kennedy,” Newport News Daily Press, May 30, 2011. CVN-79 
is the second ship to be named for President John F. Kennedy. The first, CV-67, was the last conventionally powered 
carrier procured for the Navy. CV-67 was procured in FY1963, entered service in 1968, and was decommissioned in 
2007. 
Congressional Research Service  
 
5 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Authorization Act (S. 1790/P.L. 116-92 of December 20, 2019), the Navy was increasing the cost 
limitation baseline (aka cost cap) for CVN-79 by $236 million, to $12,936 million, to support full 
ship delivery efforts. (For further information on procurement cost caps for the CVN-78 program, 
see “Program Procurement Cost Cap” below.) CVN-79 is being built with an improved shipyard 
fabrication and assembly process that incorporates lessons learned from the construction of CVN-
78. CVN-79 is scheduled for delivery to the Navy in July 2025. 
Figure 3. USS Gerald R. Ford (CVN-78) 
 
Source: Cropped version of photograph accompanying Megan Eckstein, “Navy Removes Ford Carrier Program 
Manager, Citing Performance Over Time,” USNI News, July 2, 2020. The caption credits the photograph to the 
U.S. Navy and states that it shows CVN-78 on June 4, 2020. 
CVN-80 (Enterprise) 
CVN-80, which was named Enterprise on December 1, 2012,17 was procured in FY2018. The 
Navy’s proposed FY2024 budget estimates the ship’s procurement cost at $12,812.9 million (i.e., 
 
17 The Navy made the announcement of CVN-80’s name on the same day that it deactivated the 51-year-old aircraft 
carrier CVN-65, also named Enterprise. (“Enterprise, Navy’s First Nuclear-Powered Aircraft Carrier, Inactivated,” 
Navy News Service, December 1, 2012; Hugh Lessig, “Navy Retires One Enterprise, Will Welcome Another,” Newport 
(continued...) 
Congressional Research Service  
 
6 
 link to page 35 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
about $12.8 billion) in then-year dollars. The ship is scheduled for delivery to the Navy in March 
2028. 
CVN-81 (Doris Miller) 
CVN-81, which was named Doris Miller on January 20, 2020,18 is treated in this report as a ship 
that was procured in FY2019, consistent with congressional action on the Navy’s FY2019 budget. 
(The Navy’s FY2024 budget submission, like its FY2021-FY2023 submissions, shows CVN-81 
as a ship that was procured in FY2020.) The Navy’s FY2024 budget submission estimates the 
ship’s procurement cost at $12,929.1 million (i.e., about $12.9 billion) in then-year dollars. The 
ship is scheduled for delivery to the Navy in February 2032. 
Two-Ship Block Buy Contract for CVN-80 and CVN-81 
CVN-80 and CVN-81 are being procured under a two-ship block buy contract that was authorized 
by Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (H.R. 5515/P.L. 115-232 of August 13, 2018). The provision permitted the Navy to add 
CVN-81 to the existing contract for building CVN-80 after DOD made certain certifications to 
Congress. DOD made the certifications on December 31, 2018, and the Navy announced the 
award of the contract on January 31, 2019. Prior to the awarding of the two-ship block buy 
contract, CVN-81 was scheduled to be procured in FY2023. 
Compared to the estimated procurement costs for CVN-80 and CVN-81 in the Navy’s FY2019 
budget submission, the Navy estimated under its FY2020 budget submission that the two-ship 
block buy contract will reduce the cost of CVN-80 by $246.6 million and the cost of CVN-81 by 
$2,637.3 million, for a combined reduction of $2,883.9 million (i.e., about $2.9 billion).19 (DOD 
characterized the combined reduction as “nearly $3 billion.”20) Using higher estimated baseline 
costs for CVN-80 and CVN-81 taken from a December 2017 Navy business case analysis, the 
Navy estimated under its FY2020 budget submission that the two-ship contract will reduce the 
cost of CVN-80 by about $900 million and the cost of CVN-81 by about $3.1 billion, for a 
combined reduction of about $4.0 billion.21 These figures are all expressed in then-year dollars, 
meaning dollars that are not adjusted for inflation. For additional background information on the 
two-ship block buy contract, see the Appendix. 
Interest in Potential Two-Ship Block Buy Contract for CVN-82 and CVN-83 
Some observers reportedly are interested in the option of using another two-ship block buy 
contract to procure two additional Ford-class carriers, which would be CVN-82 and CVN-83.22 
 
News Daily Press, December 2, 2012.) CVN-65 was the eighth Navy ship named Enterprise; CVN-80 is to be the 
ninth. 
18 Doris Miller was an African American enlisted sailor who received the Navy Cross for his actions during the 
Japanese attack on Pearl Harbor on December 7, 1941. For further discussion of the naming of CVN-81 for Doris 
Miller, see CRS Report RS22478, Navy Ship Names: Background for Congress, by Ronald O'Rourke. 
19 Source: CRS calculation based on costs for single-ship purchases as presented in Navy’s FY2019 budget submission 
and costs for two-ship purchase as presented in the Navy’s FY2020 budget submission. 
20 Source: Navy information paper on estimated cost savings of two-ship carrier buy provided to CRS by Navy Office 
of Legislative Affairs on June 20, 2019. 
21 Navy information paper provided to CRS by Navy Office of legislative Affairs on June 20, 2019. 
22 See, for example, Megan Eckstein, “US Navy Mulls Timing of New Double-Carrier Award Amid Enterprise Delay,” 
Defense News, October 26, 2023; Loren Thompson, “The Right Way To Buy The U.S. Navy’s New Generation Of 
(continued...) 
Congressional Research Service  
 
7 
 link to page 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The Navy’s FY2024 30-year (FY2024-FY2053) shipbuilding plan shows the next two carriers 
after CVN-81 as scheduled for procurement in FY2028 and either FY2032 or FY2033. 
Section 132 of the FY2023 NDAA (H.R. 7776/P.L. 117-263 of December 23, 2022) required the 
Navy to submit a report to the congressional defense committees not later than March 1, 2023, on 
advance procurement funding for CVN-82 and CVN-83 under single-carrier and two-carrier 
acquisition strategies. 
Program Procurement Cost Cap 
Congress between established and subsequently amended procurement cost caps for Ford-class 
aircraft carriers.23 
Program Procurement Funding 
Table 1 shows procurement funding for CVNs 78, 79, 80, and 81 through FY2028, the final year 
of funding programmed for CVN-81, under the Navy’s FY2024 budget submission. As shown in 
the table, the Navy’s proposed FY2024 budget requests $2,540.4 million (i.e., about $2.5 billion) 
in procurement funding for Ford-class ships, including $624.6 million for CVN-79, $1,115.3 
million for CVN-80, and $800.5 million for CVN-81. 
 
Supercarriers,” Forbes, September 30, 2022; Mike Gooding, “Block-Buy for New Aircraft Carriers Will Save 
Taxpayers Billions of Dollars,” 13 News Now, August 30 (updated August 31), 2022; Megan Eckstein, “Navy, HII 
Pitch Congress for Another Two-Carrier Contract,” Defense News, August 29, 2022; Sam LaGrone, “HII Argues for 
Aircraft Carrier Block Buy as New Enterprise Takes Shape,” USNI News, August 28, 2022; Justin Katz, “Ahead of 
Shipyard Ceremony, Navy and Industry Advocate for Another Aircraft Carrier ‘Block Buy,’” Breaking Defense, 
August 26, 2022. 
23 The provisions that established and later amended the cost caps are as follows: 
Section 122 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 
2006) established a procurement cost cap for CVN-78 of $10.5 billion, plus adjustments for inflation and other factors, 
and a procurement cost cap for subsequent Ford-class carriers of $8.1 billion each, plus adjustments for inflation and 
other factors. The conference report (H.Rept. 109-702 of September 29, 2006) on P.L. 109-364 discusses Section 122 
on pages 551-552. 
Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 113-66 of December 26, 2013) 
amended the procurement cost cap for the CVN-78 program to provide a revised cap of $12,887.0 million for CVN-78 
and a revised cap of $11,498.0 million for each follow-on ship in the program, plus adjustments for inflation and other 
factors (including an additional factor not included in original cost cap). 
Section 122 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015) further 
amended the cost cap for the CVN-78 program to provide a revised cap of $11,398.0 million for each follow-on ship in 
the program, plus adjustment for inflation and other factors, and with a new provision stating that, if during 
construction of CVN-79, the Chief of Naval Operations determines that measures required to complete the ship within 
the revised cost cap shall result in an unacceptable reduction to the ship’s operational capability, the Secretary of the 
Navy may increase the CVN-79 cost cap by up to $100 million (i.e., to $11.498 billion). If such an action is taken, the 
Navy is to adhere to the notification requirements specified in the cost cap legislation. 
Section 121(a) of the FY2018 National Defense Authorization Act (H.R. 2810/P.L. 115-91 of December 12, 2017) 
further amended the cost cap for the CVN-78 program to provide a revised cap of $12,568.0 million for CVN-80 and 
subsequent ships in the program, plus adjustment for inflation and other factors. (The cap for CVN-79 was kept at 
$11,398.0 million, plus adjustment for inflation and other factors.) The provision also amended the basis for adjusting 
the caps for inflation, and excluded certain costs from being counted against the caps. 
Section 121 of the FY2020 National Defense Authorization Act (S. 1790/P.L. 116-92 of December 20, 2019) further 
amended the cost cap for the CVN-78 program to provide revised caps of $13,224.0 million for CVN-78, $11,398.0 
million for CVN–79, $12,202.0 million for CVN–80, and $12,451.0 million for CVN–81. The provision directs the 
Navy to exclude from these figures costs for CVN–78 class battle spares, interim spares, and increases attributable to 
economic inflation after December 1, 2018. 
Congressional Research Service  
 
8 
 link to page 7  link to page 14 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 1. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2028 
(Millions of then-year dollars, rounded to nearest tenth) 
FY 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
Total 
FY01 
21.7 (AP) 
0 
0 
0 
21.7 
FY02 
135.3 (AP) 
0 
0 
0 
135.3 
FY03 
395.5 (AP) 
0 
0 
0 
395.5 
FY04 
1,162.9 (AP) 
0 
0 
0 
1,162.9 
FY05 
623.1 (AP) 
0 
0 
0 
623.1 
FY06 
618.9 (AP) 
0 
0 
0 
618.9 
FY07 
735.8 (AP) 
52.8 (AP) 
0 
0 
788.6 
FY08 
2,685.0 (FF) 
123.5 (AP) 
0 
0 
2,808.5 
FY09 
2,687.0 (FF) 
1,210.6 (AP) 
0 
0 
3,897.6 
FY10 
851.3 (FF) 
482.9 (AP) 
0 
0 
1,334.2 
FY11  
1,848.1 (FF) 
902.5 (AP) 
0 
0 
2,750.6 
FY12  
86.0 (FF)* 
554.8 (AP) 
0 
0 
640.8 
FY13 
0 
491.0 (FF) 
0 
0 
491.0 
FY14  
588.1 (CC) 
917.6 (FF) 
0 
0 
1,505.7 
FY15 
663.0 (CC) 
1,219.4 (FF) 
0 
0 
1,882.4 
FY16 
123.8 (CC) 
1,569.5 (FF) 
862.4 (AP) 
0 
2,555.7 
FY17  
0 
1,241.8 (FF) 
1,370.8 (AP) 
0 
2,612.6 
FY18 
20.0 (CC) 
2,556.4 (FF) 
1,569.6 (FF) 
0 
4,146.0 
FY19 
0 
0 
929.1 (FF) 
643.0 (FF) 
1,572.1 
FY20 
0 
0 
1,062.0 (FF) 
1,214.5 (FF) 
2,276.5 
FY21 
71.0 (CC) 
0 
958.9 (FF) 
1,606.4 (FF) 
2,636.3 
FY22 
0 
291.0 (CC) 
1,062.0 (FF) 
1,287.7 (FF) 
2,640.7 
FY23 
0 
461.7 (CC) 
1,465.9 (FF) 
1,052.0 (FF) 
2,995.2 
FY24 (requested) 
0 
624.6 (CC) 
1,115.3 (FF) 
800.5 (FF) 
2,540.4 
FY25 (programmed) 
0 
 
2416.7 (FF) 
666.0 (FF) 
3,082.7 
FY26 (programmed) 
0 
 
 
1,922.1 (FF) 
1,922.1 
FY27 (programmed) 
0 
 
 
2,011.8 (FF) 
2,011.8 
FY28 (programmed) 
0 
 
 
1,725.0 (FF) 
1,725.0 
Total 
13,316.5 
12,700.0 
12,812.9 
12,929.1 
51,758.5 
Source: Table prepared by CRS based on Navy’s FY2024 budget submission and prior-year submissions. 
Notes: Figures may not add due to rounding. AP is advance procurement funding; FF is ful  funding; CC is cost-
to-complete funding (i.e., funding to cover cost growth), which is sometimes abbreviated in Navy documents as 
CTC. Regarding the * notation for the FY2012 funding figure for CVN-78, even though FY2012 is after FY2011 
(CVN-78’s original final year of ful  funding), the Navy characterizes the $86.0 mil ion reprogrammed into 
FY2012 as ful  funding rather than cost-to-complete funding on the grounds that in the years since FY2011, as 
discussed earlier in this report (see footnote 9), the authority to use incremental funding for procuring aircraft 
carriers has been expanded by Congress to permit more than the four years of incremental funding that were 
permitted at the time that CVN-78 was initially funded. 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget 
Table 2 shows changes in the estimated procurement costs of CVNs 78, 79, 80, and 81 since the 
budget submission for FY2008—the year of procurement for CVN-78. 
Congressional Research Service  
 
9 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 
(As shown in FY2008-FY2024 budgets, in millions of then-year dollars) 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
Est. 
Scheduled/
Est. 
Scheduled/ 
Est. 
Scheduled/
Est. 
Scheduled/
proc. 
actual FY 
proc. 
actual FY 
proc. 
actual FY 
proc. 
actual FY 
Budget 
cost 
of proc. 
cost 
of proc. 
cost 
of proc. 
cost 
of proc. 
FY08 
10,488.9 
FY08 
9,192.0 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY09 
10,457.9 
FY08 
9,191.6 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY10 
10,845.8 
FY08 
n/a 
FY13 
n/a 
FY18 
n/a 
FY23 
FY11 
11,531.0 
FY08 
10,413.1 
FY13 
13,577.0 
FY18 
n/a 
FY23 
FY12 
11,531.0 
FY08 
10,253.0 
FY13 
13,494.9 
FY18 
n/a 
FY23 
FY13 
12,323.2 
FY08 
11,411.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY14 
12,829.3 
FY08 
11,338.4 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY15 
12,887.2 
FY08 
11,498.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY16 
12,887.0 
FY08 
11,347.6 
FY13 
13,472.0 
FY18 
n/a 
FY23 
FY17 
12,887.0 
FY08 
11,398.0 
FY13 
12,900.0 
FY18 
n/a 
FY23 
FY18 
12,907.0 
FY08 
11,377.4 
FY13 
12,997.6 
FY18 
n/a 
FY23 
FY19 
12,964.0 
FY08 
11,341.4 
FY13 
12,601.7 
FY18 
15,088.0 
FY19 
FY20 
13,084.0 
FY08 
11,327.4 
FY13 
12,335.1 
FY18 
12,450.7 
FY19 
FY21 
13,316.5 
FY08 
11,397.7 
FY13 
12,321.3 
FY18 
12,450.7 
FY19 
FY22 
13,316.5 
FY08 
11,929.7 
FY13 
12,405.5 
FY18 
12,483.6 
FY19 
FY23 
13,316.5 
FY08 
12,700.0 
FY13 
12,832.9 
FY18 
12,930.0 
FY19 
FY24 
13,316.5 
FY08 
12,700.0 
FY13 
12,812.9 
FY19 
12,929.1 
FY19 
Annual % change 
FY08 to FY09 
-0.3 
 
0% 
 
0% 
 
n/a 
 
FY09 to FY10 
+3.7 
 
n/a 
 
n/a 
 
n/a 
 
FY10 to FY11 
+6.3 
 
n/a 
 
n/a 
 
n/a 
 
FY09 to FY11 
 
 
 
 
+26.7% 
 
 
 
FY11 to FY12 
0% 
 
-1.5% 
 
-0.1% 
 
n/a 
 
FY12 to FY13 
+6.9% 
 
+11.3% 
 
+2.8% 
 
n/a 
 
FY13 to FY14 
+4.1% 
 
-0.6% 
 
0% 
 
n/a 
 
FY14 to FY15 
+0.5% 
 
+1.4% 
 
0% 
 
n/a 
 
FY15 to FY16 
0% 
 
-1.3% 
 
-2.9% 
 
n/a 
 
FY16 to FY17 
0% 
 
+0.4% 
 
-4.2% 
 
n/a 
 
FY17 to FY18 
+0.2% 
 
-0.2% 
 
+0.7% 
 
n/a 
 
FY18 to FY19 
+0.4% 
 
-0.3% 
 
-3.0% 
 
n/a 
 
FY19 to FY20 
+0.9% 
 
-0.1% 
 
-2.1% 
 
-17.5% 
 
FY20 to FY21 
+1.8% 
 
+0.6% 
 
-0.1% 
 
0% 
 
FY21 to FY22 
0% 
 
+4.7% 
 
+0.7% 
 
+0.3% 
 
FY22 to FY23 
0% 
 
+6.5% 
 
+3.4% 
 
+3.6% 
 
FY23 to FY24 
0% 
 
0% 
 
-0.156% 
 
-0.007% 
 
Cumulative % change through FY24 from actual procurement dates of FY08, FY13, FY18, and FY19 
Since FY08 
+27.0% 
 
+38.2% 
 
+19.6% 
 
n/a 
 
Since FY13 
+8.1% 
 
+11.3% 
 
-7.7% 
 
n/a 
 
Since FY18 
+3.2% 
 
+11.6% 
 
-1.4% 
 
n/a 
 
Since FY19 
+2.7% 
 
+12.0% 
 
+1.7% 
 
-14.3% 
 
Source: Table prepared by CRS based on FY2008-FY2024 Navy budget submissions.  
Notes: n/a means not available. The FY2010 budget submission did not show estimated procurement costs or 
scheduled years of procurement for CVNs 79 and 80. The scheduled years of procurement for CVNs 79 and 80 
shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for procuring 
Congressional Research Service  
 
10 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference regarding 
recommendations for the FY2010 defense budget. 
Issues for Congress for FY2024 
Future Aircraft Carrier Force Level 
One issue for Congress concerns the future aircraft carrier force level. Decisions on this issue 
could have implications for the service lives of existing aircraft carriers and/or plans for procuring 
new aircraft carriers. The future aircraft carrier force level has been a frequent matter of 
discussion over the years, and (correctly or not) is often the starting point or the center of broader 
discussions over the future size and composition of the Navy.Factors involved in discussions 
about the future aircraft carrier force level include but are not limited to the following: 
•  the capabilities and costs (including procurement costs and life-cycle operation 
and support [O&S] costs) of aircraft carriers and their embarked air wings, and 
how those capabilities and costs compare to those of other U.S. military forces; 
•  the prospective survivability of aircraft carriers in conflicts against adversaries 
(such as China) with highly capable anti-ship missiles; 
•  the numbers of carriers needed to support policymaker-desired levels of day-to-
day aircraft carrier forward presence in various regions around the world; and 
•  the utility of carriers for purposes other than high-end combat, including 
deterrence of potential regional adversaries, reassurance of allies and partners, 
signaling U.S. commitment and resolve, and noncombat operations such as 
humanitarian assistance/disaster response (HA/DR) operations. 
As discussed earlier, the Navy and DOD have been working since 2019 to develop a new force-
level goal to replace the 355-ship force-level goal of 2016. Studies of this emerging force-level 
goal that have been released by the Navy in summary form suggest that the new force-level goal 
could call for achieving and maintaining a Navy with a carrier force of 8 to 12 carriers, to be 
supplemented (in the case of the lower end of that range) by up to 6 light aircraft carriers 
(CVLs).24 
An aircraft carrier force-level goal that includes fewer than 11 CVNs could lead to Navy 
proposals for one or more of the following: 
•  accelerated retirements for one or more Nimitz-class carriers that have already 
received their mid-life nuclear refueling overhauls (which are called Refueling 
Complex Overhauls, or RCOHs); 
•  a deferral or cancellation of the procurement of the next aircraft carrier after 
CVN-81, which under the Navy’s FY2024 30-year shipbuilding plan is scheduled 
for FY2028; and/or 
•  the deferral or cancellation of the construction of CVN-81, which could require 
modifying the current two-ship construction contract for CVN-80 and CVN-81. 
 
24 For the effort to develop a successor to the 355-ship goal of 2016, including the studies that the Navy has released in 
summary form, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for 
Congress, by Ronald O'Rourke.  
Congressional Research Service  
 
11 
 link to page 14  link to page 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Cost Growth 
Overview 
Another issue for Congress concerns cost growth in the CVN-78 program, which the Navy has 
worked for years to control. Navy efforts to stem cost growth and manage costs in the CVN-78 
program so as to stay within the program’s cost caps have been a continuing oversight issue for 
Congress. Congress has passed legislation on the issue that is in addition to the earlier-mentioned 
legislation that established and amended cost caps for the ships.25 
As shown in Table 2, the estimated procurement costs of CVN-78, CVN-79, and CVN-80 have 
grown 27.0%, 38.2%, and 19.6%, respectively, since the submission of the FY2008 budget. As 
shown in Table 1, cost growth on CVN-78 and CVN-79 has required the Navy to request 
$2,843.2 million (i.e., about $2.8 billion) in cost-to-complete (CC) procurement funding to cover 
cost growth on the two ships, including $1,465.9 million for CVN-78 and $1,377.3 million for 
CVN-79. 
CVN-78 
A primary source of past cost growth for CVN-78 appears to have been an unrealistically low 
original cost estimate for the ship in the FY2008 budget submission, which might have reflected 
an underestimate of the intrinsic challenges of building the then-new Ford-class design compared 
to those of building the previous and well understood Nimitz-class design.26 
 
25 This additional legislation includes the following: 
Section 128 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015), which 
established a limitation on availability of funds for CVN–79 until certain conditions were met; 
Section 126 of the FY2017 National Defense Authorization Act (S. 2943/P.L. 114-328 of December 23, 2016), which 
established a limitation on availability of funds for procurement of CVN–80 until certain conditions were met; 
Section 121(b) of the FY2018 National Defense Authorization Act (H.R. 2810/P.L. 115-91 of December 12, 2017), 
which provided for a waiver on the limitation of availability of funds for CVN–79; and 
Section 122 of the FY2020 National Defense Authorization Act (S. 1790/P.L. 116-92 of December 20, 2020), which 
modified the above-listed Section 126 of P.L. 114-328 regarding an annual report on cost targets for Ford-class carriers. 
26 The Congressional Budget office (CBO) in 2008 and GAO in 2007 questioned the accuracy of the Navy’s cost 
estimate for CVN-78. CBO reported in June 2008 that it estimated that CVN-78 would cost $11.2 billion in constant 
FY2009 dollars, or about $900 million more than the Navy’s estimate of $10.3 billion in constant FY2009 dollars, and 
that if “CVN-78 experienced cost growth similar to that of other lead ships that the Navy has purchased in the past 10 
years, costs could be much higher still.” CBO also reported that, although the Navy publicly expressed confidence in its 
cost estimate for CVN-78, the Navy had assigned a confidence level of less than 50% to its estimate, meaning that the 
Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office, 
Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in 
August 2007 that 
Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate, 
which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be 
built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s 
target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for 
construction was 22 percent higher than the Navy’s cost target, which was based on the budget. 
Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to 
build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage 
issues that affect cost suffers from insufficient cost surveillance. Without effective cost 
surveillance, the Navy will not be able to identify early signs of cost growth and take necessary 
corrective action. 
(Government Accountability Office, Defense Acquisitions[:] Navy Faces Challenges Constructing 
(continued...) 
Congressional Research Service  
 
12 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
In addition to this general cause of past cost growth, secondary and more-specific past risks of 
cost growth for CVN-78 included certain new systems to be installed on the ship. These included 
a new type of aircraft catapult called the Electromagnetic Launch System (EMALS), a new 
aircraft arresting system called the Advanced Arresting Gear (AAG), and the ship’s primary radar, 
called the Dual Band Radar (DBR). Congress followed these and other sources of risk of cost 
growth on CVN-78 for years. 
CVNs 79, 80, and 81 
Impact of Original CVN-78 Cost Estimate 
An unrealistically low cost estimate for CVN-78 may have led to similarly unrealistically low 
cost estimates for CVN-79 and CVN-80 in the FY2008 budget submission, since the cost 
estimates for CVN-79 and CVN-80 would have been derived from the estimate for CVN-78. 
Confidence Levels 
The Navy stated in June 2019 that its confidence levels for its estimated procurement costs (not 
including costs for class-wide spare parts) for CVNs 79, 80, and 81 were 36%, 22%, and 20%, 
respectively, meaning that the Navy as of June 2019 estimated that the risk of future cost growth 
on CVNs 79, 80, and 81 were 64%, 78%, and 80%, respectively.27 
October 2023 CBO Report 
An October 2023 Congressional Budget Office (CBO) report on the potential cost of the Navy’s 
FY2024 30-year shipbuilding plan states: 
The Navy estimates that [CVN-79] will cost $14.8 billion (in [constant FY]2023 dollars, 
or $12.7 billion in nominal dollars). CBO’s estimate for the ship is almost the same: $14.9 
billion (in [constant FY]2023 dollars)…. 
In the 2024 budget, under the two-carrier [CVN-80 and CVN-81] buy, the Navy estimated 
that the CVN-80 will cost $12.3 billion (in [constant FY]2023 dollars, or $12.6 billion in 
nominal  dollars).  By  contrast,  CBO  is  less  certain  about  the  savings  the  two-carrier 
purchase will generate. On the basis of the costs of the two previous ships, CBO estimates 
that the CVN-80 will cost $14.0 billion (in [constant FY]2023 dollars), about 13 percent 
more than the Navy’s estimate. Similarly, the Navy estimates that the CVN-81 will cost 
$12.0  billion  (in  [constant  FY]2023  dollars,  or  $12.9  billion  in  nominal  dollars).  By 
contrast,  CBO  estimates  that  the  CVN-81  will  cost  $13.6  billion  (in  [constant  FY]2023 
dollars), which is also 13 percent more than the Navy’s estimate. 
The Navy’s estimates for future carriers are much higher than its estimates for the CVN-
80 or CVN-81. In the [Navy’s] 2024 [30-year] shipbuilding plan, the Navy estimates that 
the 6 carriers purchased under [30-year] Alternatives 1 and 2 would each cost about $17 
billion (in [constant FY]2023 dollars), on average, and the 7 carriers purchased under [30-
year] Alternative 3 would each cost about $16 billion…. The difference between those two 
estimates for the alternatives is driven largely by the effect of building carriers every five 
 
the Aircraft Carrier Gerald R. Ford within Budget, GAO-07-866, August 2007, summary page. See 
also Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed 
to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and 
Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary 
Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), 
p. 15.) 
27 Source: Navy information paper provided to CRS by Navy Office of legislative Affairs on June 20, 2019. 
Congressional Research Service  
 
13 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
years under the first two alternatives versus every four years under the third alternative. 
The Navy expects that if future carriers can be purchased repeatedly using the two-carrier 
buy  strategy  over  the  next  30  years,  then  the  costs  could  be  lower  than  the  estimates 
provided in the [FY]2024 [30-year shipbuilding] plan. 
In a report to the Congress, the Navy estimates that a two-ship buy strategy would save 
about  7  percent,  if  the  carriers  were  purchased  every  five  years.  If  those  ships  were 
purchased every four years, then the estimated savings would double, to about 14 percent 
under Alternatives 1 and 2. Under Alternative 3, the savings would be a little less than 7 
percent  because  the  Navy  already  envisions  buying  carriers  every  four  years  under  that 
alternative. Even so, the Navy’s recent estimates suggest that the industry is experiencing 
growth in real costs. The increase in its estimates for the [FY]2024 [30-year shipbuilding] 
plan, compared with those in the [FY]2023 [30-year shipbuilding] plan, amounts to roughly 
$500 million more per ship than is accounted for by shipbuilding inflation alone (using the 
same assumptions about how frequently the Navy would buy the ships). 
CBO estimates that under the first two alternatives, carriers would cost, on average, $16.6 
billion—3  percent  less  than  the  Navy’s  estimate.  CBO’s  estimate  for  carrier  purchases 
under  the  third  alternative  is  $15.7  billion  per  ship—2  percent  less  than  the  Navy’s 
estimate.  Although  using  the  two-carrier  buy  strategy  should  generate  savings,  it  is  not 
clear that the large savings the Navy anticipates would occur. The savings that could be 
realized with two-carrier buys will be better understood once the CVN-80 and CVN-81 are 
complete.28 
CVN-79 
Navy officials have stated that they are working to control the cost of CVN-79 by equipping the 
ship with a less expensive primary radar,29 by turning down opportunities to add features to the 
ship that would have made the ship more capable than CVN-78 but would also have increased 
CVN-79’s cost, and by using a build strategy for the ship that incorporates improvements over the 
build strategy that was used for CVN-78. These build-strategy improvements, Navy officials have 
said, include the following items, among others: 
•  achieving a higher percentage of outfitting of ship modules before modules are 
stacked together to form the ship; 
•  achieving “learning inside the ship,” which means producing similar-looking ship 
modules in an assembly line-like series, so as to achieve improved production 
learning curve benefits in the production of these modules; and 
•  more economical ordering of parts and materials including greater use of batch 
ordering of parts and materials, as opposed to ordering parts and materials on an 
individual basis as each is needed. 
As noted earlier, on August 10, 2023, the Navy notified the congressional defense committees 
that, using authority granted by Section 121 of the FY2020 National Defense Authorization Act 
(S. 1790/P.L. 116-92 of December 20, 2019), the Navy was increasing the cost limitation baseline 
(aka cost cap) for CVN-79 by $236 million, to $12,936 million, to support full ship delivery 
efforts. 
 
28 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2024 Shipbuilding Plan, October 2023, p. 24. 
29 See, for example, Megan Eckstein, “PEO Carriers: CVN-79 Will Have a New Radar, Save $180M Compared to 
[CVN-78’s] Dual Band Radar,” USNI News, March 17, 2015; Christopher P. Cavas, “Dual Band Radar Swapped Out 
In New Carriers,” Defense News, March 17, 2015; Christopher P. Cavas, “New US Carrier Radar Enters the Picture,” 
Defense News, March 23, 2015. 
Congressional Research Service  
 
14 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
A March 7, 2022, press report stated 
Aircraft  carrier  manufacturer Newport  News  Shipbuilding  is  revamping  its  processes  to 
become more efficient as it builds the Gerald R. Ford class of carriers, a company official 
said. 
Brian Fields, the vice president of aircraft carrier construction for CVN-80 and CVN-81, 
told reporters Feb.  18 the company had a plan going into construction on the Gerald R. 
Ford,  but  lessons  learned  are  driving  down  cost  and  schedule  as  the  company  works 
through the John F. Kennedy and now the Enterprise. 
One lesson relates to crane lifts of large modules or supermodules. Given the immense size 
of aircraft carriers, the workforce builds the steel framing for segments of the ship, which 
can then be outfitted with pipes and cables. These modules are then lifted by crane and put 
into place on the hull. 
Fields said the company has learned to use even larger supermodules, therefore needing 
fewer crane lifts to put the pieces into place. 
“Some of our super lifts [on Enterprise] have incorporated what on [Ford and Kennedy] 
were in some cases 10, 15 erections with a  crane—building one large supermodule,” he 
said.  “We’re  seeing  a  lot  more  opportunity  to  outfit  earlier  in  the  build  process,  which 
provides a lot of efficiencies just based on where the work is being performed.” 
Fields said the company is also trying to group steel structures into “unit families,” where 
the  pieces aren’t identical  but similar enough that  lessons can still be  applied from one 
piece  to  the  next.  The  sequencing  on  Ford  and  Kennedy  had  been  based  on  what  steel 
pieces were needed in what order to form modules that could be stacked in the right order. 
The new changes on Enterprise mean some steel pieces are built early to need—but Fields 
said “localized learning” could happen when similar pieces were built consecutively in a 
“batch manufacturing process.” 
Fields said the company is seeing similar learning happening at its 2,500 suppliers around 
the country.... 
Fields also noted the Ford class was designed in a digital 3D environment, rather than using 
traditional  blueprint  drawings.  The  associated  step-by-step  digital  work  instructions 
weren’t ready for the first two ships, so Ford and Kennedy were built by craftspeople using 
paper drawings derived from the digital plans—though Kennedy was used to experiment 
with early digital work instructions and get employee feedback. 
Starting with Enterprise, workers at the shipyard used laptops with digital work instructions 
for each step, with 3D images that can be enlarged and rotated. 
“It provides the mechanics a lot clearer picture of what they’re expected to be doing. It 
helps with first-time quality. It helps the younger craftspeople, who sometimes, we find it 
takes as much time to learn to read drawings as it does to develop the craft skills,” Fields 
said. 
Enterprise and Doris Miller will be fully built with these digital work instructions, in a first 
for the Navy. 
Fields said the Navy invested significantly in getting the 3D product model and the digital 
work instructions right, as they will be the basis of not only construction of carriers and 
submarines at Newport News but also for lifecycle maintenance work at the Navy’s four 
public shipyards. 
Fields  said  Newport  News  Shipbuilding  made  a  “generational  investment”  in  buying 
laptops for all hourly workers so they could access the digital work instructions. But, he 
said,  the  investment  is  yielding  other  benefits,  giving  workers  immediate  access  to 
Congressional Research Service  
 
15 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
resources like procedures, troubleshooting manuals and more, as well as better access to 
their supervisors.30 
Delay in CVN-78’s First Deployment  
Overview 
Another oversight issue for Congress concerns the delay in CVN-78’s first deployment that was 
caused by a need to complete work on the ship’s weapons elevators and correct other technical 
problems aboard the ship. As noted earlier, the ship’s first deployment occurred in October and 
November 2022, more than five years after it was commissioned into service. The delay in the 
ship’s first deployment lengthened a period during which the Navy attempted to maintain 
policymaker-desired levels of carrier forward deployments with its 10 other carriers—a situation 
that may have added to operational strains on those 10 carriers and their crews. 
Weapons Elevators 
The ship’s 11 weapons elevators—referred to as Advanced Weapons Elevators (AWEs)—move 
missiles and bombs from the ship’s weapon magazines up to the ship’s flight deck, so that they 
can be loaded onto aircraft that are getting ready to take off from the ship. A lack of working 
weapons elevators can substantially limit an aircraft carrier’s ability to conduct combat 
operations. Challenges in completing the construction, testing, and certification of the ship’s 
AWEs were first reported in November 2018,31 and the issue became a matter of continuing 
congressional oversight. Navy officials stated that the 11th and final weapon elevator was 
completed, tested, and certified on December 22, 2021. 
Following the initial press report about the ship’s AWEs in November 2018, the Navy struggled 
to meet promises it repeatedly made to the defense oversight committees to get the AWEs 
completed, tested, and certified. Reported developments included the following: 
•  For much of 2019, the Navy continued to report that two of the 11 AWEs were 
completed, tested, and certified.32 
 
30 Megan Eckstein, “Navy Says Digital Work Instructions, Lessons Learned Are Improving Construction of Third 
Ford-Class Carrier,” Defense News, March 7, 2022. 
31 See Anthony Capaccio, “U.S. Navy’s Costliest Carrier Was Delivered Without Elevators to Lift Bombs,” 
Bloomberg, November 2, 2018. 
32 Sam LaGrone, “Carrier Ford Will Only Have Two Weapon Elevators Ready When it Leaves Shipyard,” USNI News, 
October 9, 2019. See also Anthony Capaccio, “On Costliest U.S. Warship Ever, Navy Can’t Get Munitions on Deck,” 
Bloomberg, July 30, 2019. (The article was also published by Bloomberg with the title “Flawed Elevators on $13 
Billion Carrier Miss Another Deadline.”) Ben Werner, “Navy Says More Experts Coming to Work Ford Carrier 
Elevator Delays,” USNI News, July 5, 2019; Navy Research, Development and Acquisition Public Affairs Office, 
“Navy Full Court Press on USS Gerald R. Ford Weapons Elevators,” Navy News Service, July 1, 2019; Mark D. Faram, 
“The Navy’s New Plan to Fix Ford’s Elevators Failures,” Navy Times, July 1, 2019; Paul McLeary, “Navy Calls In 
Outsiders To Fix Troubled Ford Carrier,” Breaking Defense, July 1, 2019; Ben Werner and Sam LaGrone, “USS 
Gerald R. Ford Weapons Elevator Certifications Will Extend Pat October,” USNI News, May 29, 2019. See also Paul 
McLeary, “Will Trump Fire SecNav? Super Carrier USS Ford Suffers New Setback,” Breaking Defense, May 29, 
2019; Rich Abott, “Ford Elevator Work Prioritized And Extending Past October,” Defense Daily, June 3, 2019; Megan 
Eckstein, “Navy Building a Land-Based Test Site for Ford-Class Weapons Elevators, But Timing Won’t Help CVN-
78,” USNI News, May 31, 2019. 
For earlier press reports, see Anthony Capaccio, “U.S. Navy’s Costliest Carrier Was Delivered Without Elevators to 
Lift Bombs,” Bloomberg, November 2, 2018; Anthony Capaccio, “Flawed Bomb Elevators Leave Inhofe Leery of 
Buying Two Carriers,” Bloomberg, December 5, 2019; Megan Eckstein, “SECNAV to Trump: Ford Carrier Weapons 
(continued...) 
Congressional Research Service  
 
16 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
•  On October 23, 2019, the Navy reported that the figure had increased to four of 
11.33  
•  On April 22, 2020, the Navy announced that the fifth AWE had been certified, 
that the sixth was scheduled to be certified in the fourth quarter of FY2020, and 
that the remaining five were scheduled to be certified by the time that the ship 
underwent Full Ship Shock Trials (FSSTs), which was then scheduled for the 
third quarter of FY2021.34  
•  On July 23, 2020, the Navy announced that the sixth AWE had been certified.35  
•  In November 2020, it was reported that the seventh AWE was scheduled to be 
certified before the end of calendar year 2020, and that the remaining four would 
be completed by the end of April 2021.36  
•  On March 16, 2021, it was reported that seventh AWE had been delivered in 
early March, that the eighth elevator was in testing and was scheduled to be 
delivered in April, that work on all the AWE considered together was 93% or 
94% complete, and that the remaining three AWEs would be completed during 
2021.37  
•  On March 23, 2021, Navy Admiral John Aquilino testified that nine of the 11 
AWEs had been “repaired.”38 
 
Elevators Will Be Fixed by Summer, or ‘Fire Me,’” USNI News, January 8, 2019; USS Gerald R. Ford Public Affairs, 
“USS Gerald R. Ford Accepts First Advanced Weapons Elevator,” Navy News Service, January 16, 2019; Christopher 
Woody, “The Navy’s Newest Aircraft Carrier Got a Long-Missing Piece of Gear in December, Helping to Solve a 
Problem the Navy Secretary Has Bet His Job on Fixing,” Business Insider, January 20, 2019; Richard Sisk, “Navy 
Finally Has One Weapons Elevator Working on Its Newest Carrier,” Military.com, January 22, 2019; Mark D. Faram, 
“Once Beleaguered by Critics, the Ford Gets a Lift,” Navy Times, January 23, 2019; USS Gerald R. Ford (CVN 78) 
Public Affairs, “USS Gerald R. Ford Accepts Second Advanced Weapons Elevator,” Navy News Service, March 6, 
2019; Mark D. Faram, “Why the Once-Maligned Flattop Ford Is Finally Getting a Lift (or 11),” Navy Times, March 7, 
2019; Rich Abott, “Carrier Elevator Test Site Will Procure New Elevator, Ford Accepts Second Elevator,” Defense 
Daily, March 7, 2019; Rich Abott, “Navy To Build Land-Based Carrier Elevator Test Site,” Defense Daily, February 
21, 2019. 
33 Wesley Morgan, “Navy Secretary Accuses Congressional Critics of ‘Disinformation’ on Ford Carrier,” Politico Pro, 
October 23, 2019. See also Sam LaGrone, “Carrier Ford May Not Deploy Until 2024, 3rd Weapons Elevator Certified,” 
USNI News, October 22, 2019; Anthony Capaccio, “Trump Lets Navy’s Chief Off the Hook Over an Offer to ‘Fire 
Me,’” Bloomberg, November 2, 2019. 
34 Program Executive Office Aircraft Carriers Public Affairs, “Fifth Advanced Weapons Elevator certified aboard USS 
Gerald R. Ford (CVN 78),” Navy News Service, April 22, 2020. See also Megan Eckstein, “Ford’s 5th Weapons 
Elevator Done With Testing; All 11 Should Be Done By Next Summer’s Shock Trials,” USNI News, April 16, 2020. 
On January 16, 2020, a Navy official reportedly stated that work on all 11 elevators will be completed by May 2021, 
although the official acknowledged that there is some risk in that schedule. (Mallory Shelbourne, “Navy Confident 
CVN-78 Will Have All Weapons Elevators by May 2021,” Inside Defense, January 16, 2020.) 
35 Gina Harkins, “Supercarrier Ford Could Soon Have More Than Half of Its Weapons Elevators Working,” 
Military.com, June 19, 2020. 
36 Mallory Shelbourne, “USS Gerald R. Ford Making Steady Progress Ahead of Deployment,” USNI News, November 
24, 2020. 
37 Michael Fabey, “US Navy Reports Progress on Key Carrier Ford Systems,” Jane’s Navy International, March 16, 
2021; Megan Eckstein, “As USS Gerald R. Ford Nears Shock Trials, Carrier Remains Busy With Testing, Fleet 
Support,” USNI News, March 12, 2021. See also Kara Dixon, “USS Gerald R. Ford Moving Toward Completion of 
Post-Delivery Tests and Trials,” WAVY.com, March 10, 2021. 
38 See Rich Abott, “Aquilino Says Nine Of 11 Ford Elevators Finished,” Defense Daily, March 23, 2021; Aidan 
Quigley, “Aquilino: Ford ‘Through’ Technological Challenges, All but Two Elevators Finished,” Inside Defense, 
March 23, 2021. 
Congressional Research Service  
 
17 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
•  On May 13, 2021—about four years after the ship was delivered to the Navy—it 
was reported that four of the 11 AWEs would not be certified until later in 2021.39 
•  On July 21, 2021, the Chief of Naval Operations (CNO), Admiral Michael 
Gilday, reportedly stated: “We’ll deliver two more [of the AWEs] in early fall 
[2021] and then the remaining two by the end of 2021, so the elevators will be 
complete. And that’s going very, very well.”40 
•  The Navy stated that the 11th and final AWE was completed, tested, and certified 
on December 22, 2021.41 
The Navy stated in 2020 that lessons learned in building, testing, and certifying CVN-78’s AWEs 
will be applied to the AWEs of subsequent Ford-class carriers.42 
Other Technical Challenges 
In addition to challenges in building, testing, and certifying the ship’s weapon elevators, the Navy 
reportedly worked to address problems with other systems on the ship. A January 21, 2022, press 
report stated 
Four years after the U.S. Navy’s costliest warship was hobbled by a flaw in its propulsion 
system,  prime  contractor  Huntington  Ingalls  Industries  Inc.  and  subcontractor  General 
Electric Co. are still haggling over who will pay for fixing the defect. 
The $13 billion USS Gerald R. Ford was forced to return to port during post-delivery sea 
trials  in  early  2018  after  the  failure  of  a  main  thrust  bearing,  a  key  propulsion  system 
component that’s made by GE. 
Huntington Ingalls has repaired the faulty gear, and the Navy advanced funds for the work. 
The  “actual  root  cause”  of  the  defective  part  was  “machining  errors”  by  GE  workers, 
according to Navy documents. The bearing, one of four that transfers thrust from the ship’s 
four propeller shafts, overheated but “after securing the equipment to prevent damage, the 
ship safely returned to port,” the Navy said in a March 2018 memo to Congress. 
The Ford returned to sea for additional trials after the damage was contained.... 
Vice  Admiral  Thomas  Moore,  then  head  of  the  Naval  Sea  Systems  Command,  told 
reporters in 2019 that the Navy was paying for the repairs until GE and Huntington “figure 
out who has the liability for it. At some point you’ve got to pay them to get the work done.” 
 
39 Aidan Quigley, “Ford Missed Elevator Certification Timeline Goal but Moves into Shock Trials on Time,” Inside 
Defense, May 10, 2021. See also Craig Hooper, “Despite Promises, USS Ford Heads to Shock Trials with 4 Broken 
Elevators,” Forbes, May 13, 2021; Peter Suciu, “The Navy’s New, Powerful Aircraft Carrier Is Heading to ‘Shock 
Trials,’” Business Insider, May 24, 2021. 
40 As quoted in Rich Abott, “CNO Says Final Ford Elevators Delivered By End Of Year, Identifies Lessons Learned,” 
Defense Daily, July 21, 2021. See also Aidan Quigley, “Navy Says Final Four Ford Elevators to be Complete by End of 
Year,” Inside Defense, August 3, 2021; Konstantin Toropin, “All of Aircraft Carrier Ford’s Weapons Elevators Will Be 
Ready by End of Year Despite Long Delay, Navy Says,” Military.com, August 10, 2021. 
41 See, for example, Megan Eckstein, “US Navy Completes Final Weapons Elevator on Aircraft Carrier Gerald R. 
Ford,” Defense News, December 23, 2021; Sam LaGrone, “HII Delivers Final Advanced Weapons Elevator Aboard 
USS Gerald R. Ford,” USNI News, December 23, 2021; Craig Hooper, “The Navy Gets A Christmas Present: All 11 
USS Ford Weapons Elevators Delivered,” Forbes, December 24, 2021; Anthony Capaccio, “Navy’s Costly Carrier 
Finally Has Its Bomb-Lifting Elevators,” Bloomberg, December 30, 2021. 
42 See, for example, David B. Larter, “US Navy Makes Progress on Aircraft Carrier Ford’s Bedeviled Weapons 
Elevators,” Defense News, July 23, 2020; Mallory Shelbourne, “Navy Verifies USS Gerald R. Ford’s Sixth Advanced 
Weapons Elevator,” USNI News, July 23, 2020; Rich Abott, “Navy Certifies Second [Lower-Stage] Ford Magazine 
Elevator,” Defense Daily, July 23, 2020; Gina Harkins, “Navy Carrier Ford Now Has 6 Working Weapons Elevators,” 
Military.com, July 24, 2020. 
Congressional Research Service  
 
18 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The  Navy  has  declined  to  say  how  much  it  paid  Huntington,  although  in  2018  it  asked 
Congress to shift $30 million from other accounts to start work.  
The companies are still hashing things out. 
“We are continuing to work on a final agreement with GE to resolve this claim,” Danny 
Hernandez, a spokesman for Newport News, Virginia-based Huntington Ingalls, said in a 
statement. Sean Smith, a spokesman for Boston-based GE, said “we continue working with 
the U.S. Navy and Huntington Ingalls to resolve this issue.” GE hasn’t commented publicly 
on the Navy’s contention that its workers were at fault.43 
An April 28, 2021, press report stated 
The  Advanced  Arresting  Gear  (AAG)  and  Electromagnetic  Aircraft  Launch  System 
(EMALS)  achieved  8,000  aircraft  recoveries  and  launches  aboard  USS  Gerald  R.  Ford 
(CVN 78) on April 19, during the final independent steaming event of her 18-month Post 
Delivery Test & Trials (PDT&T) period, the Naval Air Systems Command said in an April 
26 release.  
Capt.  Kenneth  Sterbenz,  Aircraft  Launch  and  Recovery  Equipment  (ALRE)  program 
manager (PMA-251) for EMALS and AAG, said ALRE finished PDT&T strong, and they 
are ready for the next step, as Ford prepares for Full Ship Shock Trials, which is scheduled 
to begin summer 2021.  
“ALRE’s support of EMALS and AAG was admirable throughout the rigorous testing of 
PDT&T  operations,”  said  Sterbenz.  “On  the  way  to  reaching  8,000  launches  and 
recoveries, we saw many Ford crew trained, learned a great deal about the systems, and 
laid invaluable groundwork for future Ford-class ships.”  
As  CVN  78  moved  through PDT&T,  ALRE  had  the  opportunity  to directly  support  the 
fleet, as 351 Naval aviators were qualified using EMALS and AAG throughout 2020 and 
2021. Time and training also enabled a great increase in the efficiency of flight operations. 
More  than 7,000 of Ford’s total launches and recoveries were  completed in the  last 18 
months.44 
An April 27, 2021, press report stated 
The efforts of USS Gerald R. Ford sailors during the carrier’s 18 months of post-delivery 
tests and trials look set to cut the time before the Navy’s newest carrier is ready to deploy—
possibly by a year or more. 
Rear  Adm.  Craig  Clapperton,  commander  of  the  Ford’s  carrier  strike  group,  said  the 
group’s latest exercises show the Ford would be ready to deploy 12 to 18 months earlier 
that its current—a schedule that was in its turn roughly two years later than the Navy had 
hoped when it started working on the carrier nearly two decades ago. 
After a set of live-fire exercises over the past several weeks at sea, the Ford has certified 
the missiles and cannons that are its last line of a defense. 
The  Ford  and  the  ships  and  air  wing  in  its  strike  group  also  completed  a  long  distance 
maritime strike exercise, a critical war-gaming test in which it had to escape from another 
task force seeking to disable it and then attack in its turn. 
 
43 Anthony Capaccio, “Priciest U.S. Warship Spurs Haggling on Who Pays for Crucial Fix,” Bloomberg, January 21, 
2022. 
44 Seapower Staff, “EMALS, AAG Hit 8,000 Aircraft Recoveries, Launches on Ford,” Seapower, April 28, 2021. See 
also Rich Abott, “Ford Finishes Combat Systems Ship Trials, Reaches 8,000 Aircraft Launches/Recoveries,” Defense 
Daily, April 26, 2021; Rich Abott, “Navy Completes Ford Carrier Post-Delivery Trials, Touts Success and Outlines 
Next Steps,” Defense Daily, May 5, 2021; Aidan Quigley, “Ford Missed Elevator Certification Timeline Goal but 
Moves into Shock Trials on Time,” Inside Defense, May 10, 2021. 
Congressional Research Service  
 
19 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
“We have accelerated the timeline for Gerald R. Ford,” Clapperton said…. 
During the Ford’s latest at-sea exercise, its 18th since starting post delivery tests and trials, 
its  electromagnetic  catapult,  for  launching  planes,  and  arresting  gear,  for  keeping  them 
from plunging into the sea when landing, hit the 8,000 launch-and-recovery cycle mark, 
said Capt. Joshua Sager, air wing commander. 
That’s a key measure, since that is roughly the number of sorties an air-wing will fly during 
the several months of a deployment overseas. 
Sager said the new electromagnetic technology means the air-wing can get into the air—
and return to the battle after rearming and refueling—faster than with the traditional steam-
and-hydraulics systems that have been the mainstay for decades. 
“Now we’ve gone past the point of showing the Ford can do what Nimitz class can do…. 
Now we’re at the point of taking it to the next level,” he said, referring the class of 10 
nuclear carriers now in service.45 
Potential Oversight Questions 
Potential oversight questions for Congress include the following: 
•  Why did the Navy accept delivery of CVN-78 from the shipbuilder and 
commission the ship into service if most or all of its weapon elevators were not 
completed, tested, and certified? 
•  What steps did the Navy take following the delivery of CVN-78 to the Navy on 
May 31, 2017, to keep Congress informed of challenges regarding the ship’s 
weapon elevators and other ship systems? 
•  Why did it take so long, and how much did it cost, to complete, test, and certify 
the weapon elevators? 
•  How much additional operational stress did the delay in CVN-78’s first 
deployment place on the Navy’s 10 other aircraft carriers? 
•  What steps is the Navy taking to ensure that a similar situation does not arise 
regarding the construction and initial deployments of CVN-79, CVN-80, and 
CVN-81? 
Issues Raised in DOT&E and GAO Reports 
Another oversight issue for Congress concerns CVN-78 program issues raised in a January 2023 
report from DOD’s Director, Operational Test and Evaluation (DOT&E)—DOT&E’s annual 
report for FY2022—and in the 2023 edition of the Government Accountability Office’s (GAO’s) 
annual report surveying selected DOD weapon acquisition programs, which was published in 
June 2023. 
January 2023 DOT&E Report 
Regarding the CVN-78 program, the January 2023 DOT&E report stated the following in part: 
TEST ADEQUACY 
The Navy began CVN 78 IOT&E [Initial Operational Test and Evaluation] in September 
2022.  The  Navy  is  conducting  IOT&E  in  accordance  with  TEMP  [Test  and  Evaluation 
 
45 Dave Ress, “Ford Crew’s Efforts Set to Shorten Time Until the Carrier Is Ready to Deploy, Strike Group CO Says,” 
Newport News Daily Press, April 27, 2021. 
Congressional Research Service  
 
20 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
master Plan] Revision E and the IOT&E Test Plan, which involves 10 underway periods 
(including integrated test), extensive modeling, and spans 2 years.  
The  first  of  three  land-based  cyber  survivability  tests  was  completed  on  the 
Electromagnetic Aircraft Launch System (EMALS) and Advanced Arresting Gear (AAG) 
in June 2022. This test was executed in accordance with a DOT&E-approved test plan and 
DOT&E observed the test. The planned test was limited in scope due to the Navy’s lack of 
robust cyber testing capability on industrial control systems that are common on modern 
ships. The Navy Surface Warfare Center Philadelphia Division’s Strategic Cyber- Physical 
Initiative is attempting to address this limitation. Land-based cyber testing will continue in 
FY23, and a shipboard test is scheduled for FY24.  
The Navy conducted self-defense testing against unmanned aerial vehicles and unmanned 
small  boats  in  July  2022,  in  accordance  with  a  DOT&E-approved  test  plan  that  was 
executed during Combat Systems Operational Rehearsal Event Phase 2. DOT&E observed 
the testing, and the results are still undergoing analysis. 
Additionally, CVN 78 conducted sea trials after its PIA [Planned Incremental Availability 
(PIA, a 6-month maintenance period] and six underway periods that included fixed-wing 
flight operations, two of which were in accordance with a DOT&E-approved test plan and 
one was observed by DOT&E. Four of these underway periods involved training squadrons 
and two involved a portion of its carrier air wing. To date, CVN 78 has conducted 10,826 
catapult launches (2,699 of which were in FY22) and 10,826 arrested landings (2,699 of 
which  were  in  FY22).  During  these  underway  periods,  the  crew  also  performed  two 
ammunition  onloads  and  a  RAM  [Rolling  Airframe  Missile]  live  fire.  One  of  the 
ammunition onloads was part of a DOT&E-approved test plan, and the live fire was part 
of  a  Carrier  Strike  Group  12  self-defense  exercise.  DOT&E  observed  one  ammunition 
onload and the RAM live fi re. Although not part of the IOT&E test plan, the data from the 
RAM  live  fire  will  be  adjudicated  for  score  and  is  planned  to  contribute  to  the  PRA 
[Probability of Raid Annihilation] model. 
In  April  2022,  DOT&E  submitted  a  classified  report  to  Congress  detailing  system 
performance  during  planned  test  events  against  the  Self  Defense  Test  Ship  (SDTS) 
configured to represent CVN 78’s capability. This report covers testing between December 
2018 and December 2020, during which the Navy completed three of the four planned test 
events  against  the  SDTS  [self-defense  test  ship],  including  the  employment  of  RAMs 
and/or ESSMs [Evolved Sea Sparrow Missiles]. 
There may not be enough data to determine the operational effectiveness and suitability of 
the self-defense capability of CVN 78 against anti-ship cruise missiles (ASCMs) due to 
test data that will not be available for reasons discussed in the Ship Self-Defense System 
article of this Annual Report. The self-defense tests planned in the Revision E TEMP will 
provide the only remaining live fire self-defense data points in IOT&E, and will not inform 
performance  against  some  types  of  ASCM  threats.  It  is  vital  that  the  Navy  successfully 
verify, validate, and accredit the high-fidelity PRA model being developed by the Program 
Executive Office for Integrated Warfare Systems in order to gain adequate understanding 
of the Anti-Air Warfare mission capability by completion of IOT&E. 
The Navy plans to eventually upgrade the combat systems suite on CVN 78 to match CVN 
79 and follow-on ships. Due to the differences between the combat systems, and the fact 
that CVN 79 will be the enduring self-defense configuration for the class, it is imperative 
that CVN 79 self-defense capabilities are adequately tested. 
PERFORMANCE 
EFFECTIVENESS 
Combat System 
Congressional Research Service  
 
21 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
In April 2022, DOT&E submitted a classified interim report to Congress on the operational 
effectiveness of CVN 78’s self-defense capability against ASCMs.  
Regarding the self-defense testing against unmanned aerial vehicles and unmanned small 
boats  in  July  2022,  no  preliminary  assessment  is  available  because  analysis  is  not  yet 
complete. 
Sortie Generation 
The  reliability  of  CVN  78  catapults,  arresting  gear,  and  jet  blast  deflectors  (JBDs) 
continues to have an adverse effect on sortie generation and flight operations efficiency. 
During an underway period in August of 2022, the ship returned early due to unexpected 
problems with its JBDs. The early return was necessary to facilitate JBD repairs and did 
not  allow  completion  of  CQ.  The  ongoing  reliability  problems  with  these  critical 
subsystems  remains  the  primary  risk  to  the  successful  completion  of  CVN  78  IOT&E. 
Executing the planned sortie generation-rate testing, as outlined in the Revision E TEMP, 
will  be  crucial  to  evaluating  the  ship’s  combat  effectiveness  and  accrediting  the  high-
fidelity Sea Strike/Sea Basing Aviation Model, an essential tool for evaluating the sortie 
generation rate key performance parameter and supporting life-of-class upgrades. 
SUITABILITY 
The  low  or  unproven  reliability  of  the  following  five  CVN  78  systems  pose  the  most 
significant challenge to flight operations: 
EMALS [Electromagnetic Aircraft Launch System] 
During  testing  from  March  through  June  2022  (after  the  PIA),  EMALS  achieved  a 
reliability  of  614  mean  cycles  between  operational  mission  failures  (MCBOMF)  during 
1,841 catapult launches (where a cycle is the launch of one aircraft). While this reliability 
is well below the requirement of 4,166 MCBOMF, EMALS showed slight improvement 
in reliability from FY21 (460 MCBOMF throughout 1,758 catapults). However, during the 
first underway of IOT&E in September 2022, EMALS reliability appeared to regress and 
slowed CQ. While the data are still being analyzed, the adverse effect to operations on two 
of the ten days of CQ was significant. Naval Air Systems Command is working on short- 
and  long-term  improvements  to  address  EMALS  reliability  degraders.  Short-term 
improvements  are  focused  on  improving  component  reliability  and  are  expected  to  be 
incorporated on Gerald R. Ford by the end of FY23. 
AAG [Advanced Arresting Gear] 
During testing from March through June 2022 (after the PIA), AAG achieved a reliability 
of 460 MCBOMF during 1,841 aircraft recoveries (where a cycle is the recovery of a single 
aircraft). While this reliability is well below the requirement of 16,500 MCBOMF, AAG 
showed  slight  improvement  in  reliability  from  FY21  (115  MCBOMF  throughout  1,758 
catapults).  However,  during  the  first  underway  of  IOT&E  in  September  2022,  AAG 
reliability appeared to regress and slowed CQ. While the data are still being analyzed, the 
adverse  effect  to  operations  on  three  of  the  ten  days  of  CQ  was  significant.  Naval  Air 
Systems  Command  is  working  on  short-  and  long-term  improvements  to  address  AAG 
reliability degraders. Short-term improvements are focused on improving indications and 
software and are expected to be incorporated on Gerald R. Ford by the end of 2QFY23 
[second quarter of FY2023]. 
JBDs 
During early developmental testing, reliability concerns were identified with the Electro 
Mechanical Actuators (EMA) that are used to raise and lower the JBDs on the Ford class. 
Several modifications were implemented on CVN 78 during the PIA to improve reliability. 
During the August 2022 CQ, the ship experienced EMA failures on all four JBDs, which 
caused the ship to cancel the  remainder of CQ and return early. The cause of the EMA 
Congressional Research Service  
 
22 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
failures was corroded fasteners in various components of the EMA. The root cause of the 
fastener corrosion is being addressed, and repairs were completed prior to September’s CQ 
[carrier  qualification].  During  the  September  CQ,  JBD  performance  did  not  adversely 
affect flight operations. 
Advanced Weapons Elevators (AWE)  
The  Navy  conducted  a  partial  ammunition  onload  in  April  2022  and  a  full  ammunition 
onload in September 2022. DOT&E observed the September ammunition onload; data are 
still being analyzed. Observation of the lower stage AWE performance was very promising 
as the ordnance was transferred from the hangar bay to the magazines more efficiently than 
on  a  Nimitz-class  carrier.  Through  the  first  19,767  elevator  dispatches,  109  individual 
elevator  failures  were  reported.  AWE  system  reliability  will  be  critical  as  the  Navy 
develops standard procedures for moving ordnance from magazines to the flight deck. The 
Navy’s  planned  service-retained  employment  of  CVN  78  in  1QFY23  [first  quarter  of 
FY2023] will provide the first operationally representative opportunity to fully stress the 
AWE system. 
DBR [dual-band radar] 
Through  June  2022,  DBR  demonstrated  a  reliability  of  100  hours  mean  time  between 
operational  mission  failures,  which  does  not  meet  the  minimum  threshold  of  339  hours 
mean time between operational mission failures. DBR was operationally available 94% of 
the time, compared to the 98% requirement. 
SURVIVABILITY 
An  adequate  survivability  assessment  depends  upon  a  combination  of  Full  Ship  Shock 
Trials (FSST), extensive modeling based on surrogate testing, and a total-ship survivability 
test  (TSST).  Sufficient  data  to  assess  ship  survivability  against  close-aboard  explosions 
should be available by the end of FY23. 
From  June-August  2021,  the  Navy  conducted  FSST  on  CVN  78  including  three  shock 
events  of  increasing  effect.  The  FSST  identified  several  survivability  improvement 
opportunities for CVN 78 against underwater threat engagements. In 1QFY23, DOT&E 
will publish a classified FSST report that details these results. 
The  Navy  plans  for  the  Naval  Surface  Warfare  Center  Carderock  Division  to  provide 
model-based vulnerability assessment reports that assess the class’s vulnerability to threat 
weapons in 2QFY23. 
The  TSST  is  scheduled  for  3QFY23  [third  quarter  of  FY2023].  TSST  is  an  onboard, 
extensive damage-control test of both the crew and associated systems.  
The Revision E TEMP outlines a strategy to use land-based cyber testing in 2022 and 2023 
to build up to a shipboard cybersecurity test in 2024. The first cybersecurity test event was 
a  cyber-survivability  assessment  of  EMALS  and  AAG,  using  systems  installed  at  Joint 
Base  McGuire-Dix-Lakehurst,  New  Jersey  in  June  2022.  Many  subsystems  on  the  ship 
were tested to various degrees in both developmental and operational testing on other ship 
platforms.  However,  required  CVN  78  platform-level  testing  has  not  yet  occurred,  and 
some systems specific to CVN 78 have yet to undergo any operational cyber survivability 
assessments. 
The  survivability  of  CVN  78  in  a  contested  and  congested  electromagnetic  spectrum 
environment has not been evaluated. Tests to do so in FY24 are part of the second phase 
of the test plan. 
RECOMMENDATIONS 
The Navy should: 
1. Continue to improve reliability for EMALS, AAG, JBDs, DBR, and AWE. 
Congressional Research Service  
 
23 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
2. Execute planned sortie generation and self-defense tests, as outlined in the Revision E 
TEMP and the IOT&E Test Plan. 
3.  Address  combat  system  deficiencies  identified  in  the  classified  USS  Gerald  R.  Ford 
(CVN 78) Self-Defense Interim Assessment report, dated April 2022. 
4. Continue to develop more robust capabilities to test the cyber survivability of shipboard 
industrial control systems. 
5. Fund the modeling and simulation suite required to assess the CVN 78 PRA requirement. 
6. Upon release of DOT&E’s CVN 78 FSST report, develop and resource a way forward 
to correct deficiencies and provide it to DOT&E. 
7.  Complete  and  deliver  the  vulnerability  assessment  reports  and  supporting 
documentation. 
8.  Update  the  CVN  78  TEMP  to  complete  the  test  strategy  and  provide  resources  for 
requirements to adequately test the combat system on CVN 79. 
9. Continue to fund the maintenance availability for the SDTS to ensure its readiness to 
support CVN 79 combat systems testing. 
10. Update the IOT&E Test Plan to complete the test requirements and scheduling for the 
second phase of IOT&E.46 
A March 7, 2023, opinion piece stated: 
While the Navy puts on a brave face on the carrier’s well-publicized technical problems, 
balancing  the  drumbeat  of  bad  news  with  morale-boosting  press  visits,  credulous  “gee-
whiz” media coverage, and showpiece deployments, the IOT&E tests, when completed in 
late  FY  2024,  are  likely  to  carry  a  far  less  positive  message  about  the  USS  Ford’s 
warfighting capabilities—the ultimate business case for what will be, at a minimum, a class 
of four expensive vessels.... 
To  be  blunt,  the  USS  Ford  has  yet  to  demonstrate  the  ability  to  operate  at  sea—
uninterrupted and without a port call—for more than 35 days at a  stretch. It also  seems 
unable—or  the  Navy  is  simply  unwilling—to  even  carry  out  a  standard  set  of  sortie-
generation tests—allowing an easy “apples-to-apples” comparison with the Navy’s legacy 
Nimitz class carriers. 
The fact remains that the USS Ford, 6 years after delivery, still appears unable to match 
the  sortie  generation  performance  a  World  War  II-era  carrier,  USS  Midway  (CV-41) 
exhibited during Desert Storm. 
It is a big problem—and it won’t go away anytime soon.... 
DOT&E  has  been  very  clear  about  linking  the  carrier’s  technical  problems  to  concrete 
measures  of  carrier  performance.  The  testing  agency,  in  their  2023  annual  report,  did  a 
great  job  of  tying  pilot  certification  challenges  to  the  USS  Ford’s  unreliable  flight  deck 
systems.  The  message  was  clear—the  Ford’s  reliability  challenges  inflict  real 
consequences on naval missions. 
The  Navy,  obviously  uncomfortable  with  DOT&E’s  focus  on  mission  accountability, 
grasped for a positive spin. It abruptly shifted gears on the media, introducing a reliability 
metric  that  it  has  never  used before  in  public  discussions  of  the  aircraft  carrier’s  poor-
performing electromagnetic launch (EMALS) and recovery systems (Advanced Arresting 
Gear, or AAG). 
 
46 Department of Defense, Director, Operational Test & Evaluation, January 2023, pp. 168-171. 
Congressional Research Service  
 
24 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Tellingly, the Navy’s new reliability metric indicated “improvement in the reliability of the 
catapult  and  arresting  gear  systems”  but  it  somehow  lacked  a  direct  tie  to  carrier 
performance. 
The Navy, when pressed for clarification, said, it “has addressed EMALS and AAG issues 
via a reliability growth plan that has resulted in an average Operational Availability of ~ 
0.98 for the last 5,500 (~45%) launches and recoveries across both systems.” 
And yet, somehow, the carrier, despite great operational availability scores, struggled to 
qualify pilots. 
This gets at the root of the problem. Essentially, the Navy seems content to merely field 
something that looks and acts like a carrier. And by introducing another metric, the Service 
is  refusing  to  even  acknowledge  the  launch-and-recovery  problems  exist,  effectively 
discrediting Pentagon weapons testers by muddying their very real concerns about the USS 
Ford’s  ability  to  accomplish  the  platform’s  central  mission—generating  more  aircraft 
sorties faster than any previous U.S. aircraft carrier.... 
The Navy, in a statement that took nine days to generate, focused on the DOT&E’s primary 
measurement of EMALS and AAG reliability, or, in the technological lingo, “Mean cycles 
Between Operational Mission Failures”. The unsophisticated measure tallies the number 
of launches and recoveries that occur between system failures, and then averages them. As 
a  mean,  the  Pentagon’s  testing  measure  isn’t  perfect,  and  can  be  overly  influenced  by 
outliers. 
For the Navy, “the reliability requirements for EMALS and AAG are expressed in terms 
of ‘Operational Availability’, which is the measure of how often a system is available to 
perform a mission versus not.” 
The  Navy’s  statement  continued,  explaining  that  “EMALS  and  AAG  Operational 
Availability measures the amount of time the system is available for operational use and is 
a ratio of system uptime divided by total time uptime and downtime. Downtime is a result 
of failures which prevent the system from accomplishing its mission. Total downtime is a 
function of time required to diagnose the issue, complexity of repair, and availability of 
spare parts.” 
DOT&E  responded,  issuing  a  statement  saying  that  the  organization  will  continue  to 
“collect  operationally  representative  effectiveness  and  suitability  data  from  flight 
operations”. 
The Pentagon said it focused on mean cycles between operational mission failure because 
the testing organization considers it “to be the most applicable metric during developmental 
test, and it remains applicable during operational test” and that “no combat representative 
scenarios have been scored to date” where operational availability might matter. 
The Pentagon statement put the focus right back onto the mission, saying that “the ship and 
air wing have additional operational metrics” that add context to the measurements cited 
by both DOT&E and the Navy, cautioning that a “combination of all three are needed to 
best capture how reliability and availability may impact combat flight operations.” 
In short, the Navy—unless it can get its act together—is soon going to face the music about 
their troubled aircraft carrier. It needs to show that the positive metrics it has proffered to 
the press can translate into the basic mission of launching and recovering aircraft. 
The smart money is on DOT&E’s concerns over the Ford’s battle readiness. With a history 
of broken performance promises, public relations games, little accountability, and an active 
“revolving  door”  of  high-level  carrier  decision-makers  going  to  work  for  the  carrier’s 
Congressional Research Service  
 
25 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
builder, America’s sea service hasn’t exactly covered itself in glory during the USS Ford’s 
acquisition process.47 
June 2023 GAO Report 
A June 2023 GAO report—the 2023 edition of GAO’s annual report assessing selected major 
weapon acquisition programs—stated the following about the CVN-78 program: 
Technology Maturity, Design Stability, and Production Readiness 
The Navy continues to face challenges with demonstrating the reliability of key systems, 
and the CVN 78 program remains about a decade away from demonstrating their reliability. 
Consequently, the ship may not meet a key performance requirement by the planned end 
of operational testing in November 2023. 
Metrics  used  to  assess  system  reliability  for  the  electromagnetic  aircraft  launch  system 
(EMALS) and advanced arresting gear (AAG) are slowly increasing. CVN 78 completed 
multiple at-sea events, including thousands of aircraft launches and recoveries or landings. 
These launch and recovery cycles help the program demonstrate system reliability, conduct 
testing, and certify aircraft on the systems. However, the Director, Operational Test and 
Evaluation, continues to highlight reliability as a risk to CVN 78’s ability to rapidly launch 
and recover aircraft. 
The Navy expects to install the first Enterprise Air Surveillance Radar (EASR) on CVN 
79, which it is currently developing for other ship classes. EASR, along with other systems, 
will replace the program’s original Dual Band Radar. The Navy has delivered EASR to the 
shipyard as it continues testing. However, CVN 79 delivery, planned for late in fiscal year 
2024, could be delayed if EASR problems discovered during testing require rework. 
The Director, Operational Test and Evaluation, approved the April 2022 CVN 78 Test and 
Evaluation Master Plan, after the program implemented changes to the test strategy. The 
Navy  subsequently  began  operational  testing  in  August  2022.  Given  that  operational 
testing  is  ongoing,  CVN  78  has  yet  to  demonstrate  that  it  is  operationally  effective  and 
suitable for combat. Any deficiencies discovered during operational testing may lead to a 
backlog of maintenance issues that the fleet will need to address during future maintenance 
periods. 
Software and Cybersecurity 
The CVN 78 program’s software and cybersecurity approach has not changed since last 
year.  According  to  program  officials,  the  program  conducted  an  evaluation  of  potential 
cybersecurity vulnerability for EMALS and AAG in June 2022. They stated that other ship 
systems will undergo cybersecurity assessments in fiscal years 2023 through 2025. 
Other Program Issues 
Since our report last year, program costs increased by $3.8 billion. Some of the main drivers 
are CVN 79 contract overruns and EMALS and AAG configuration changes on CVN 80 
and CVN 81. 
The Navy reported final CVN 78 construction costs of $13.2 billion. Maintenance or other 
funding  categories  will  cover  any  additional  costs.  For  example,  according  to  program 
officials,  the  Navy  is  considering  replacing  the  Dual  Band  Radar  with  EASR  during  a 
maintenance period to ensure a more reliable supply chain for maintenance. The Navy only 
 
47 Craig Hooper, “Put Up Or Shut Up Time For America’s Troubled New Aircraft Carrier,” Forbes, March 7, 2023. 
See also Sam LaGrone, “VIDEO: Navy’s Newest Carrier USS Gerald R. Ford Faces Toughest Test Yet,” USNI News, 
March 11 (updated March 12), 2023. 
Congressional Research Service  
 
26 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
has one operational Dual Band Radar unit—installed on CVN 78—which makes sourcing 
and procuring spare parts more expensive, according to program officials. 
In August 2021, the Navy increased CVN 79’s cost baseline by $1.3 billion to $12.7 billion, 
primarily due to contract overruns. At over 88 percent complete, CVN 79 is in the complex, 
final phases of construction when cost growth is most likely. Program officials stated that 
they do not expect CVN 79 would require additional funding. However, our analysis shows 
that, based on current performance, the shipbuilder is unlikely to achieve its cost estimate 
at completion. 
The Navy reported saving $4 billion by concurrently awarding contracts for CVN 80 and 
CVN 81, compared with buying the ships individually. CVN 80 is 25 percent complete, 
and  the  Navy  requested  additional  funding  to  complete  the  transition  from  using  paper 
drawings for construction to a digital model. The Navy estimated the new model would 
reduce production labor hours by 5 to 7 percent. However, program officials indicated that 
it is too early to determine if the shipbuilder will achieve this target. Additionally, program 
officials reported that industrial base issues, including supply chain delays and inflation of 
material costs, could contribute to the unlikelihood of it achieving anticipated savings. 
Program Office Comments 
We provided a draft of this assessment to the program office for review and comment. The 
program office provided technical comments, which we incorporated where appropriate. 
According to the program office, CVN 78 completed ship construction at a total cost of 
$13.2 billion. It stated that from October to November 2022, CVN 78 conducted an at-sea 
deployment and completed more than 1,250 aircraft flights, expended 78 tons of weaponry, 
and  completed  13  resupply  efforts  at  sea.  The  program  office  noted  that  CVN  79  costs 
increased  due  to  the  transition  to  a  new  delivery  schedule  in  January  2022  to  enable 
delivery of the ship with its complete warfare systems. It added that costs also increased 
due to modifications to ensure CVN 79 will be capable of operating and deploying F-35C 
aircraft upon the completion of the next maintenance period. CVN 80 conducted its keel 
laying ceremony in August 2022 and the CVN 81 keel laying is scheduled for fiscal year 
2026. The program office stated that it expects that the two-ship acquisition strategy for 
CVN 80 and CVN 81 will deliver significant savings to the government compared with the 
Navy’s cost estimate to procure these ships separately.48 
Procurement of Aircraft Carriers After CVN-81 
Another issue for Congress concerns the procurement of aircraft carriers after CVN-81. The 
question of whether the Navy should shift at some point from procuring CVNs like the Ford-class 
carriers to procuring smaller and perhaps nonnuclear-powered aircraft carriers has been a 
recurrent matter of discussion and Navy study over the years. 
As mentioned earlier, the Navy’s FY2024 30-year shipbuilding plans shows the next aircraft 
carrier after CVN-81 being procured in FY2028. The Navy has not stated that this ship would be 
something other than CVN-82 (i.e., a fifth Ford-class carrier). 
As also mentioned earlier, studies of the emerging new force-level goal that have been released 
by the Navy in summary form suggest that the new force-level goal could call for achieving and 
maintaining a Navy with a carrier force of 8 to 12 carriers, to be supplemented (in the case of the 
lower end of that range) by up to 6 light aircraft carriers (CVLs). The Navy does not currently 
operate CVLs. The Navy in recent years has experimented with the concept of using an LHA-
 
48 Government Accountability Office, Weapon Systems Annual Assessment[:] Programs Are Not Consistently 
Implementing Practices That Can Help Accelerate Acquisitions, GAO-23-106059, June 2023, p. 142. 
Congressional Research Service  
 
27 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
type amphibious assault ship with an embarked group of F-35B Joint Strike Fighters as a CVL.49 
A February 1, 2021, press report, for example, states 
The Navy’s engineering community has already started conducting light carrier design and 
engineering studies, even as the Navy and the joint force still consider whether they’d even 
want to invest in a CVL to supplement supercarriers to bring more distributed capability to 
the fleet for less cost. 
The idea of a light carrier resurfaced last summer as a Pentagon-led Future Naval Force 
Study was nearing  its completion. The idea hadn’t appeared in Navy and Marine Corps 
plans,  but  then-Defense  Secretary  Mark  Esper  had  a  growing  interest  in  the  topic  as  he 
sought  ways  to  keep  future  shipbuilding  and  sustainment costs  down  and  as he  worried 
about the Navy’s ability to conduct maintenance on its nuclear-powered aircraft carriers at 
Navy-run public shipyards. 
The FNFS and the plan it produced, Battle Force 2045, ultimately recommended between 
zero and six light carriers and noted much more study would need to be done. 
That work is already happening at Naval Sea Systems Command within the engineering 
and logistics directorate (SEA 05). 
Rear Adm. Jason Lloyd, the SEA 05 commander and deputy commander for ship design, 
integration  and  engineering,  said  last  week  that  his  Cost  Engineering  and  Industrial 
Analysis team has been studying different options to understand what operational utility 
the Navy would get out of each design and for what cost compared to the Ford-class carrier, 
“and then let the operators really, and the Navy, decide, hey, do we want that capability for 
that cost?” 
“We have looked at an America-class possibility,50 we have looked at a Ford-class-light,51 
we’ve looked at various different options and done cost studies on all those options. There 
are also capabilities studies on all those options,” Lloyd said last week while speaking at a 
virtual event hosted by the American Society of Naval Engineers.52 
Advocates of smaller carriers traditionally have argued that they are individually less expensive 
to procure, that the Navy might be able to employ competition between shipyards in their 
procurement (something that the Navy cannot do with large-deck, nuclear-powered carriers like 
the Ford-class carrier, because only one U.S. shipyard, HII/NNS, can build aircraft carriers of that 
size), and that today’s aircraft carriers concentrate much of the Navy’s striking power into a 
relatively small number of expensive platforms that adversaries could focus on attacking in time 
of war. 
Supporters of CVNs traditionally have argued that smaller carriers, though individually less 
expensive to procure, are less cost-effective in terms of dollars spent per aircraft embarked or 
aircraft sorties that can be generated; that it might be possible to use competition in procuring 
certain materials and components for large-deck, nuclear-powered aircraft carriers; and that 
 
49 See CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship Programs: Background and Issues for 
Congress, by Ronald O'Rourke. 
50 This is a reference to a CVL whose design is based on that of the America (LHA-6) class amphibious assault ship. 
51 This is a reference to a carrier whose design is similar to that of the CVN-78 design, but with some of the CVN-78 
design’s features reduced or removed, resulting in a ship whose procurement cost and capability are less than that of the 
CVN-78 design. 
52 Megan Eckstein, “Light Carrier Studies Already Underway As Navy Considers Role for CVLs in Future Fleet,” 
USNI News, February 1, 2021. See also Joseph Trevithick, “Navy Looking At America And Ford Class Derivatives In 
New Light Aircraft Carrier Studies,” The Drive, February 2, 2021. 
Congressional Research Service  
 
28 
 link to page 33  link to page 33 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
smaller carriers, though perhaps affordable in larger numbers, would be individually less 
survivable in time of war than CVNs.53 
Section 128(d) of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of 
November 25, 2015) required the Navy to submit a report on potential requirements, capabilities, 
and alternatives for the future development of aircraft carriers that would replace or supplement 
the Ford-class aircraft carrier. The report, which was conducted for the Navy by the RAND 
Corporation, was delivered to the congressional defense committees in classified form in July 
2016. An unclassified version of the report was then prepared and issued in 2017 as a publicly 
released RAND report.54 The question of whether to shift to smaller aircraft carriers was also 
addressed in three studies on future fleet architecture that were required by Section 1067 of the 
FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015). 
Legislative Activity for FY2024 
Summary of Congressional Action on FY2024 Funding Request 
Table 3 summarizes congressional action on the FY2024 procurement funding request for the 
CVN-78 program. The request for CVN-79 is for cost-to-complete (CC) funding to cover cost 
growth on CVN-79 following the completion in FY2018 of the ship’s original full funding. 
Table 3. Congressional Action on FY2024 Procurement Funding Request 
(Millions of dollars, rounded to nearest tenth)  
Authorization 
Appropriation 
 
Request 
HASC 
5ASC 
Final 
HAC 
SAC 
Final 
CVN-79 
624.6 
624.6 
624.6 
 
624.6 
624.6 
 
CVN-80 
1,115.3 
1,275.3 
1,115.3 
 
1,104.4 
1,115.3 
 
CVN-81 
800.5 
800.5 
800.5 
 
800.5 
800.5 
 
Total above 
2,540.4  2,700.4 
2,540.4 
 
2529.5 
2,540.4 
 
Source: Table prepared by CRS based on Navy’s FY2024 budget submission, committee and conference 
reports, and explanatory statements on FY2024 National Defense Authorization Act and FY2024 DOD 
Appropriations Act. 
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is 
House Appropriations Committee; SAC is Senate Appropriations Committee. The request for CVN-79 is for 
cost-to-complete (CC) funding to cover cost growth on CVN-79 fol owing the completion in FY2018 of the 
ship’s original ful  funding.  
FY2024 National Defense Authorization Act (H.R. 2670/S. 2226) 
House 
The House Armed Services Committee, in its report (H.Rept. 118-125 of June 30, 2023) on H.R. 
2670, recommended the funding levels shown in the HASC column of Table 3. The 
 
53 See, for example, Talbot Manvel, “The Lightning Carrier Isn’t Either,” U.S. Naval Institute Proceedings, July 2023. 
54 Bradley Martin and Michael McMahon, Future Aircraft Carrier Options, Santa Monica, CA, RAND Corporation, 
2017, 87 pp. 
Congressional Research Service  
 
29 
 link to page 33  link to page 33  link to page 33 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
recommended increase of $160.0 million for CVN-80 is for “Navy [FY2024] UPL [Unfunded 
Priorities List]—CVN 75 and CVN 80 SEWIP [Surface Electronic Warfare Improvement 
Program] BLK III.” (Page 445) 
Senate 
The Senate Armed Services Committee, in its report (S.Rept. 118-58 of July 12, 2023) on S. 
2226, recommended the funding levels shown in the SASC column of Table 3. 
Section 121 of S. 2226 would amend 10 USC 8062(e) to require the Navy to maintain a 
minimum of nine carrier air wings until the date on which additional operationally deployable 
aircraft carriers can fully support a 10th carrier air wing, after which point the Navy is to maintain 
a minimum of 10 carrier air wings. 
Regarding Section 121, S.Rept. 118-58 states: 
Reduction in the minimum number of Navy carrier air wings and carrier air wing 
headquarters required to be maintained (sec. 121) 
The  committee  recommends  a  provision  that  would  amend  section  8062(e)  of  title  10, 
United States Code, to relieve the Navy of a requirement to maintain 10 carrier air wings. 
The  Department  of  Defense  has  asked  for  relief  from  the  requirements  of  this  section, 
which  directs  the  Secretary  of  the  Navy  to  ensure  that  the  Navy  maintains  9  carrier  air 
wings until additional deployable aircraft carriers can fully support 10 carrier air wings, or 
October 1, 2025, whichever is earlier. Thereafter, the Navy would be required to maintain 
10 carrier air wings. 
The  Navy  intends  to  maintain  9  carrier  air  wings  as  the  fleet  returns  to  11  operational 
aircraft carriers. The Navy argues that even with 11 operational aircraft carriers, two of 
those  carriers  are  regularly  unavailable  for  worldwide  deployment  due  to  routine  or 
scheduled  maintenance  or  repair  to  include  refueling  and  complex  overhauls,  docking 
planned incremental availabilities, or planned incremental availabilities. Thus, the Navy 
believes that maintaining 9 carrier air wings is sufficient to support 11 operational aircraft 
carriers and that maintaining 10 carrier air wings is unnecessary. (Page 7) 
FY2024 DOD Appropriations Act (H.R. 4365/S. 2587) 
House 
The House Appropriations Committee, in its report (H.Rept. 118-121 of June 27, 2023) on H.R. 
4365, recommended the funding levels shown in the HAC column of Table 3. The recommended 
reduction of $10.876 million for CVN-80 is for “Joint precision aircraft landing system early to 
need.” (Page 145) 
Senate 
The Senate Appropriations Committee, in its report (S.Rept. 118-81 of July 27, 2023) on S. 2587, 
recommended the funding levels shown in the SAC column of Table 3. 
 
Congressional Research Service  
 
30 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Appendix. Background Information on Two-Ship 
Block Buy for CVN-80 and CVN-81 
This appendix presents additional background information on the two-ship block buy contract for 
CVN-80 and CVN-81. 
The option for procuring two Ford-class carriers under a two-ship block buy contract had been 
discussed in this CRS report since April 2012.55 In earlier years, the discussion focused on the 
option of using a block buy contract for procuring CVN-79 and CVN-80. In subsequent years, 
interest among policymakers focused on the option of using a block buy contract for procuring 
CVN-80 and CVN-81. 
On March 19, 2018, the Navy released a request for proposal (RFP) to Huntington Ingalls 
Industries/Newport News Shipbuilding (HII/NNS) regarding a two-ship buy of some kind for 
CVN-80 and CVN-81. A March 20, 2018, Navy News Service report stated the following: 
The Navy released a CVN 80/81 two-ship buy Request for Proposal (RFP) to Huntington 
Ingalls Industries—Newport News Shipbuilding (HII-NNS) March 19 to further define the 
cost savings achievable with a two-ship buy. 
With lethality and affordability a top priority, the Navy has been working with HII-NNS 
over the last several months to estimate the total savings associated with procuring CVN 
80 and CVN 81 as a two-ship buy. 
“In keeping with the National Defense Strategy, the Navy developed an acquisition strategy 
to  combine  the  CVN  80  and  CVN  81  procurements  to  better  achieve  the  Department’s 
objectives of building a more lethal force with greater performance and affordability,” said 
James F. Geurts, Assistant Secretary of the Navy, Research Development and Acquisition. 
“This  opportunity  for  a  two-ship  contract  is  dependent  on  significant  savings  that  the 
shipbuilding  industry  and  government  must  demonstrate.  The  Navy  is  requesting  a 
proposal from HII-NNS in order to evaluate whether we can achieve significant savings.” 
The two-ship buy is a contracting strategy the Navy has effectively used in the 1980s to 
procure  Nimitz-class  aircraft  carriers  and  achieved  significant  acquisition  cost  savings 
compared  to  contracting  for  the  ships  individually.  While  the  CVN  80/81  two-ship  buy 
negotiations transpire, the Navy is pursuing contracting actions necessary to continue CVN 
80 fabrication in fiscal year (FY) 2018 and preserve the current schedule. The Navy plans 
to award the CVN 80 construction contract in early FY 2019 as a two-ship buy pending 
Congressional approval and achieving significant savings.56 
Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/P.L. 115-232 of August 13, 2018) permitted the Navy, after DOD made certain 
certifications to Congress, to add CVN-81 to the existing contract for building CVN-80. DOD 
provided the required certification on December 31, 2018. On January 31, 2019, the Navy 
 
55 See the section entitled “Potential Two-Ship Block Buy on CVN-79 and CVN-80” in the April 4, 2012, version of 
CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress, by 
Ronald O'Rourke. In more recent years, this section was modified to discuss the option in connection with CVN-80 and 
CVN-81. 
56 Naval Sea Systems Command Public Affairs, “Navy Seeks Savings, Releases Two-Carrier RFP,” Navy News, March 
20, 2018. See also Megan Eckstein, “UPDATED: Navy, Newport News Taking Steps Towards Two-Carrier Buy,” 
USNI News, March 19, 2018. 
Congressional Research Service  
 
31 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
announced that it had awarded a two-ship fixed-price incentive (firm target) (FPIF) contract for 
CVN-80 and CVN-81 to HII/NNS.57 
The two-ship contract for CVN-80 and CVN-81 can be viewed as a block buy contract because 
the two ships are being procured in different fiscal years (CVN-80 was procured in FY2018 and 
CVN-81 was procured in FY2019 [or, according to the Navy’s FY2021-FY2024 budget 
submissions, in FY2020]).58 The Navy’s previous two-ship aircraft carrier procurements occurred 
in FY1983 (for CVN-72 and CVN-73) and FY1988 (for CVN-74 and CVN-75). In each of those 
two earlier cases, however, the two ships were fully funded within a single fiscal year, making 
each of these cases a simple two-ship purchase (akin, for example, to procuring two Virginia-
class attack submarines or two DDG-51 class destroyers in a given fiscal year) rather than a two-
ship block buy (i.e., a contract spanning the procurement of end items procured across more than 
one fiscal year). 
Compared to DOD’s estimate that the two-ship block buy contract for CVN-80 and CVN-81 
would produce savings of $3.9 billion (as measured from estimated costs for the two ships in the 
December 2017 Navy business case analysis), DOD states that “the Department of Defense’s 
Office of Cost Assessment and Program Evaluation (CAPE) developed an Independent Estimate 
of Savings for the two-ship procurement and forecast savings of $3.1 billion ([in] Then-Year 
[dollars]), or approximately 11 percent.... The primary differences between [the] CAPE and Navy 
estimates of savings are in Government Furnished Equipment59 and production change orders.”60 
Within the total estimated combined reduction in cost, HII/NNS reportedly expects to save up to 
$1.6 billion in contractor-furnished equipment.61 
A November 2018 DOD report to Congress that was submitted as an attachment to DOD’s 
December 31, 2018, certification stated the following regarding the sources of cost reduction for 
the two-ship contract: 
The  CVN  80  and  CVN  81  two-ship  buy  expands  and  improves  upon  the  affordability 
initiatives  identified  in  the  Annual  Report  on  Cost  Reduction  Efforts  for  JOHN  F. 
KENNEDY (CVN 79) and ENTERPRISE (CVN 80) as required by section 126(c) of the 
National  Defense  Authorization  Act  for  Fiscal  Year  2017  (P.L.  114-328).  Production 
saving initiatives for single-ship buys included use of unit families in construction, pre-
outfitting  and  complex  assemblies  which  move  work  to  a  more  efficient  workspace 
environment,  reduction  in  the  number  of  superlifts,62  and  facility  investments  which 
improve the shipbuilder trade effectiveness. A two-ship buy assumes four years between 
 
57 See Office of the Navy Chief of Information, “Navy Awards Contract for Construction of Two Carriers,” Navy News 
Service, January 31, 2019; Megan Eckstein, “UPDATED: Navy Awards 2-Carrier Contract to Newport News 
Shipbuilding,” USNI News, January 31, 2019; Marcus Weisgerber, “US Navy Places First 2-Carrier Order in Three 
Decades,” Defense One, January 31, 2019; David B. Larter, “US Navy Signs Mammoth Contract with Huntington 
Ingalls for Two Aircraft Carriers,” Defense News, January 31, 2019; Rich Abott, “Navy Awards HII $15 Billion In 
Two Carrier Buy,” Defense Daily, February 1, 2019. 
58 For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy 
Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke. 
59 Government-furnished equipment (GFE) is equipment that the government purchases from supplier firms and then 
provides to the shipbuilder for incorporation into the ships. 
60 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 8-9. 
61 Rich Abott, “Navy Awards HII $15 Billion In Two Carrier Buy,” Defense Daily, February 1, 2019. Contractor-
furnished equipment (CFE) is equipment that the contractor (in this case, HII/NNS) purchases from supplier firms for 
incorporation into the ships. 
62 A superlift is the use of a crane to move a very large section of the ship from the land into its final position on the 
ship. 
Congressional Research Service  
 
32 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
ship  deliveries  which  allows  more  schedule  overlap,  and  therefore  more  shop-level  and 
assembly-level production efficiencies than two single-ship buys. 
Procuring two ships to a single technical baseline reduces the requirement for engineering 
labor  hours  when  compared  to  single-ship  estimates.  The  ability  to  rollover  production 
support  engineering  and  planning  products  maximizes  savings  while  recognizing  the 
minimum amount of engineering labor necessary to address obsolescence and regulatory 
changes on CVN 81. The two-ship agreement with the shipbuilder achieves a 55 percent 
reduction in construction support engineering hours on CVN 81 and greater than 18 percent 
reduction in production support and planning hours compared to single ship procurements. 
The two-ship procurement strategy allows for serial production opportunities that promote 
tangible learning and reduced shop and machine set-up times. It allows for efficient use of 
production facilities, re-use of production jigs and fixtures, and level loading of key trades. 
The continuity of work allows for reductions in supervision, services and support costs. 
The result of these efficiencies is a production man-hours step down that is equivalent to 
an 82 percent learning curve since CVN 79. 
Key  to  achieving  these  production  efficiencies  is  Integrated  Digital  Shipbuilding  (iDS). 
The Navy’s Research, Development, Test, and Evaluation (RDT&E) and the shipbuilder’s 
investment  in  iDS,  totaling  $631  million,  will  reduce  the  amount  of  production  effort 
required to build FORD Class carriers. The two-ship buy will accelerate the benefits of this 
approach. The ability to immediately use the capability on CVN 81 would lead to a further 
reduction in touch labor and services in affected value streams. The two-ship agreement 
with  the  shipbuilder  represents  a  production man-hours reduction  of  over  seven  percent 
based  on  iDS  efficiencies.  Contractual  authority  for  two  ships  allows  the  shipbuilder  to 
maximize  economic  order  quantity  material  procurement.  This  allows  more  efficient 
ordering and scheduling of material deliveries and will promote efficiencies through earlier 
ordering,  single  negotiations,  vendor  quotes,  and  cross  program  purchase  orders.  These 
efficiencies  are  expected  to  reduce  material  costs  by  about  six  percent  more  when 
compared  to  single-ship  estimates.  Improved  material  management  and  flexibility  will 
prevent costly production delays. Furthermore, this  provides stability within the nuclear 
industrial base, de-risking the COLUMBIA and VIRGINIA Class programs. The two-ship 
buy would provide economic stability to approximately 130,000 workers across 46 States 
within the industrial base. 
Change  order  requirements  are  likewise  reduced  as  Government  Furnished  Equipment 
(GFE) providers will employ planning and procurement strategies based on the common 
technical baseline that minimize configuration changes that must be incorporated on the 
follow ship. Change order budget allocations have been reduced over 25 percent based on 
two-ship strategies. 
In addition to the discrete savings achieved with the shipbuilder, the two-ship procurement 
authority provides our partner GFE providers a similar opportunity to negotiate economic 
order quantity savings and achieve cross program savings when compared to single-ship 
estimates.63 
An April 16, 2018, press report stated the following: 
If  the  Navy  decides  to  buy  aircraft  carriers  CVN-80  and  81  together,  Newport  News 
Shipbuilding will be able to maintain a steady workload that supports between 23,000 and 
25,000 workers at the Virginia yard for the next decade or so, the shipyard president told 
reporters last week. 
 
63 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 6-7. 
Congressional Research Service  
 
33 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Part of the appeal of buying the two carriers together is that the Navy would also buy them 
a bit closer together: the ships would be centered about three-and-a-half or four years apart, 
instead of the five-year centers for recent carrier acquisition, Newport News Shipbuilding 
President Jennifer Boykin told reporters. 
Boykin said the closer ship construction centers would allow her to avoid a “labor valley” 
where the workforce levels would dip down after one ship and then have to come back up, 
which is disruptive for employees and costly for the company. 
If this two-carrier buy goes through, the company would avoid the labor valley altogether 
and ensure stability in its workforce, Boykin said in a company media briefing at the Navy 
League’s  Sea  Air  Space  2018  symposium.  That  workforce  stability  contributes  to  an 
expected $1.6 billion in savings on the two-carrier buy from Newport News Shipbuilding’s 
portion of the work alone, not including government-furnished equipment.... 
Boykin said four main things contribute to the expected $1.6 billion in savings from the 
two-carrier buy. First, “if you don’t have the workforce valley, there’s a labor efficiency 
that represents savings.” 
Second,  “if  you  buy  two  at  once,  my  engineering  team  doesn’t  have  to  produce  two 
technical baselines, two sets of technical products; they only have to produce one, and the 
applicability is to both, so there’s savings there. When we come through the planning, the 
build plan of how we plan to build the ship, the planning organization only has to put out 
one plan and the applicability is to both, so there’s savings there.” 
The third savings is a value of money over time issue, she said, and fourth is economic 
order quantity savings throughout the entire supply chain.64 
 
 
Author Information 
 
Ronald O'Rourke 
   
Specialist in Naval Affairs 
    
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan 
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and 
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other 
than public understanding of information that has been provided by CRS to Members of Congress in 
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not 
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in 
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or 
material from a third party, you may need to obtain the permission of the copyright holder if you wish to 
copy or otherwise use copyrighted material. 
 
 
64 Megan Eckstein, “Newport News Would Save $1.6 Billion, Maintain Stable Workforce of 25,000 Under 2 Proposed 
Carrier Buy,” USNI News, April 16, 2018. See also Rich Abott, “HII Sees Two Carrier Buy Saving $1.6 Billion Before 
GFE,” Defense Daily, April 11, 2018: 10-11. 
Congressional Research Service  
RS20643 · VERSION 279 · UPDATED 
34