
 
Updated July 10, 2023
Coast Guard Waterways Commerce Cutter (WCC) Program: 
Background and Issues for Congress
Introduction 
As of 2019, the 13 WLICs were based at cities along the 
The Coast Guard’s Waterways Commerce Cutter (WCC) 
U.S. East and Gulf coasts in Alabama, Florida (three 
program envisages procuring 30 replacements for the Coast 
cutters), Louisiana (two cutters), Maryland, North Carolina, 
Guard’s 35 aging river buoy tenders (WLRs), inland 
South Carolina, Texas (three cutters), and Virginia. As of 
construction tenders (WLICs), and inland buoy tenders 
2019, the four WLIs were based at locations in Alaska, 
(WLIs). The Coast Guard wants to have the first new WCC 
Michigan, Oregon, and North Carolina. 
be in service by 2025. On October 5, 2022, the Coast Guard 
awarded a contract to Birdon America, Inc. of Denver, CO, 
Rationale for Building New WCCs 
to build up to 16 WLRs and 11 WLICs. The Coast Guard’s 
The Coast Guard states in its FY2024 budget submission 
proposed FY2024 budget requests $98.0 million in 
that it wants to replace the 35 existing waterways cutters 
procurement funding for the WCC program. 
with new WCCs because “[i]n addition to age concerns and 
the associated equipment obsolescence issues, the legacy 
Terminology 
fleet presents other sustainment challenges, including 
Cutters are Coast Guard vessels that are more than 65 feet 
hazardous materials stemming from the use of asbestos and 
long and have accommodations for a crew. (Those less than 
lead paint during construction of these assets. Outdated 
65 feet long are called boats.) Waterways refers here to the 
technology and vessel designs have also led to crew safety 
intra-coastal waterways along the U.S. East and Gulf 
concerns, maintenance cost increases, and non-compliance 
coasts, and to U.S. inland waterways such as the 
with environmental regulations. Finally, legacy vessel 
Mississippi River. Tenders are vessels whose primary 
configuration does not allow the assignment of mixed 
mission is to maintain or repair something. Coast Guard 
gender crews in accordance with the Coast Guard’s 
tender designations begin with WL, meaning Coast Guard 
workforce goals.” 
vessel (W) and tender (L). (The W in the acronym WCC, 
however, stands for waterways.) 
WCC Program 
WCC Missions 
Program Initiation and Name 
WCCs perform three primary missions under the Coast 
The WCC program was initiated in the Coast Guard’s 
Guard’s statutory role of providing aids to navigation 
FY2018 budget submission. It was earlier called the Inland 
(ATON): river buoy tending; inland construction tending 
Waterways and Western Rivers Tender (or Cutter) program. 
(which involves driving and removing piles and erecting 
and repairing range towers and major lights); and inland 
Acquisition Strategy 
buoy tending. WCCs are used for maintaining more than 
The Coast Guard wants to replace the 35 existing waterway 
28,200 marine aids to navigation on 12,000 miles of inland 
commerce cutters with 30 new WCCs, including 16 WLRs, 
waterways on which 630 million tons of cargo move each 
11 WLICs, and 3 WLIs. The Coast Guard states that the 
year. Additional WCC missions include search and rescue 
WCC program 
(SAR), marine safety, marine environmental protection, and 
ports, waterways, and coastal security. 
determined that three WCC variants will best meet 
mission needs. All three variants will be monohull 
Existing Waterways Cutters 
ships, meaning self-propelled cutters instead of tug 
The Coast Guard’s 35 existing WCCs are built to nine 
and  barge  configurations.  The  River  Buoy  Tender 
different designs, and include 18 WLRs, 13 WLICs, and 4 
[WLR]  and  Inland  Construction  Tender  [WLIC] 
WLIs. As of 2022, the 35 vessels were an average of 57 
variants  will  be  acquired  on  one  contract;  these 
years old. 
variants  will  maximize  commonality  with  notable 
exceptions for hull length, working deck layout, and 
Geographic Distribution 
deck equipment, including the crane. 
As of 2019, the 18 WLRs were based at cities along the 
The Inland Buoy Tender will be acquired separately 
Mississippi and other inland rivers in Alabama, Arkansas, 
from the other two variants. In June 2021, the WCC 
Illinois, Iowa, Kentucky (two cutters), Mississippi (three 
cutters), Missouri, Nebraska, Oklahoma, Pennsylvania, and 
Program  began  partnering  with  the  U.S.  Army 
Tennessee (four cutters). Although these locations are in the 
Corps  of  Engineers  Marine  Design  Center,  which 
central and eastern United States, the rivers in question are 
has experience with similar acquisitions, to develop 
referred to by the Coast Guard as the western rivers. 
a  Government-led  design  for  the  Inland  Buoy 
Tender  variant.  The  Inland  Buoy  Tender  will  be 
contractor-built. 
https://crsreports.congress.gov 
 link to page 2  link to page 2 

Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for Congress 
(U.S.  Coast  Guard,  “Waterways  Commerce 
price contract with economic price adjustments for 
Cutter,” accessed March 23, 2023.) 
the detail design and construction of its river buoy 
and  inland  construction  tenders  [WLRs  and 
Figure 1 and Figure 2 show renderings of WCCs. The 
WLICs]. The initial award is worth $28.49 million. 
winner of the WLR/WLIC contract (see below) will be able 
to compete for the WLI contract. 
The  contract  includes  options  for  the  construction 
of a total of 16 river buoy tenders [WLRs] and 11 
Figure 1. Notional Rendering of WLIC and WLR 
inland construction tenders [WLICs]. If all contract 
line items are exercised, the total contract value is 
estimated at $1.19 billion. 
A total contract value of $1.19 billion for 27 WLRs and 
WLICs equates to an average cost of about $44.1 million 
each. 
April 2023 GAO Report 
The April 2023 GAO report states 
The  contract  award  for  the  detailed  design  and 
construction  contract  for  segment  1  [for  the 
 
procurement  of  the  WLRs  and  WLICs]  and  the 
Source: Notional vendor rendering of WLIC (left) and WLR (right), 
shown at U.S. Coast Guard, “Waterways Commerce Cutter,” 
acquisition  decision  event  (ADE)  2B  milestone 
accessed March 23, 2023. 
have  been  delayed  following  a  pre-award 
challenge.… 
Figure 2. Coast Guard Notional Designs for WLR, 
The  program  plans  to  achieve  initial  operational 
WLIC, and WLI 
capability (IOC) before adjudicating the full results 
of  initial  operational  testing.  This  raises  the 
possibility of rework if testing identifies problems, 
such  as  design  flaws,  on  cutters  that  have  already 
been produced. The Coast Guard plans to mitigate 
this risk by using the preliminary results from initial 
testing  to  inform  its  initial  operational  capability 
decision. (GAO Report 23-106701, p. 52; see page 
53 for additional discussion.) 
FY2024 Funding 
The Coast Guard’s proposed FY2024 budget requests $98.0 
million in procurement funding for the WCC program, to be 
used for commencing production of WLIC #1 and WLR #1; 
procuring long leadtime materials (LLTM) for WLIC #2 
and WLR #2; and other program activities. The House 
Appropriations Committee, in its report (H.Rept. 118-123 
 
of June 27, 2023) on the FY2024 DHS Appropriations Act 
Source: Coast Guard il ustration showing indicative (i.e., notional) 
(H.R. 4367), recommends approving the FY2024 
designs for the WLI (top), WLIC (middle), and WLR (bottom), 
procurement funding request for the WCC program.  
shown at U.S. Coast Guard, “Waterways Commerce Cutter,” 
accessed March 23, 2023. 
Section 244 of H.R. 4367 as reported states: “None of the 
funds appropriated or otherwise made available by this Act 
Procurement Cost 
or previous appropriations Acts under the heading ‘Coast 
An April 2023 Government Accountability Office (GAO) 
Guard—Procurement, Construction, and Improvements’ 
report on major Department of Homeland Security (DHS) 
that remain available for obligation in fiscal year 2024 
acquisition programs states that as of June 2022, the WCC 
within the Waterways Commerce Cutter Program may be 
program’s total estimated procurement cost was $922 
used to enter into or carry out a procurement contract with 
million, or an average of about $30.7 million per cutter. 
any entity deemed not eligible for an award from a size 
(GAO Report 23-106701, p. 52.) 
standpoint by the Small Business Administration.” 
Contract Award 
H.Rept. 118-123 states: “The Committee is disappointed in 
On October 5, 2022, following a Request for Proposals 
the lack of professionalism demonstrated by acquisition 
(RFP) released on April 30, 2021, the Coast Guard 
staff responsible for this project and expects the Coast 
announced that it had  
Guard to take substantive action to improve the quality of 
its acquisition work and related communications” (pp. 49-
today awarded Birdon America, Inc. of Denver, an 
50).
indefinite-delivery,  indefinite-quantity  firm  fixed 
https://crsreports.congress.gov 
Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for Congress 
 
IF11672
Ronald O'Rourke, Specialist in Naval Affairs   
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to 
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. 
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has 
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the 
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be 
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include 
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you 
wish to copy or otherwise use copyrighted material. 
 
https://crsreports.congress.gov | IF11672 · VERSION 30 · UPDATED