link to page 1 

Updated December 21, 2022
Coast Guard Waterways Commerce Cutter (WCC) Program:
Background and Issues for Congress
Introduction
central and eastern United States, the rivers in question are
The Coast Guard’s Waterways Commerce Cutter (WCC)
referred to by the Coast Guard as the western rivers.
program envisages procuring 30 replacements for the Coast
Guard’s 35 aging river buoy tenders (WLRs), inland
As of 2019, the 13 WLICs were based at cities along the
construction tenders (WLICs), and inland buoy tenders
U.S. East and Gulf coasts in Alabama, Florida (three
(WLIs). The Coast Guard wants to have the first new WCC
cutters), Louisiana (two cutters), Maryland, North Carolina,
be in service by 2025. On October 5, 2022, the Coast Guard
South Carolina, Texas (three cutters), and Virginia. As of
awarded a contract to Birdon America, Inc. of Denver, CO,
2019, the four WLIs were based at locations in Alaska,
to build up to 16 WLRs and 11 WLICs The Coast Guard’s
Michigan, Oregon, and North Carolina.
proposed FY2023 budget requests $77.0 million in
procurement funding for the WCC program. The issue for
Figure 1. Coast Guard River Buoy Tender (WLR)
Congress is whether to approve, reject, or modify the Coast
Guard’s proposed acquisition strategy and funding requests
for the program.
Terminology
Cutters are Coast Guard vessels that are more than 65 feet
long and have accommodations for a crew. (Those less than
65 feet long are called boats.) Waterways refers here to the
intra-coastal waterways along the U.S. East and Gulf
coasts, and to U.S. inland waterways such as the
Mississippi River. Tenders are vessels whose primary
mission is to maintain or repair something. Coast Guard
Source: Coast Guard photograph.
tender designations begin with WL, meaning Coast Guard
vessel (W) and tender (L). (The W in the acronym WCC,
Rationale for Building New WCCs
however, stands for waterways.)
The Coast Guard states in its FY2023 budget submission
that it wants to replace the 35 existing waterways cutters
WCC Missions
with new WCCs because “[i]n addition to age concerns and
WCCs perform three primary missions under the Coast
the associated equipment obsolescence issues, the legacy
Guard’s statutory role of providing aids to navigation
fleet presents other sustainment challenges, including
(ATON): river buoy tending; inland construction tending
hazardous materials stemming from the use of asbestos and
(which involves driving and removing piles and erecting
lead paint during construction of these assets. Outdated
and repairing range towers and major lights); and inland
technology and vessel designs have also led to crew safety
buoy tending. WCCs are used for maintaining more than
concerns, maintenance cost increases, and non-compliance
28,200 marine aids to navigation on 12,000 miles of inland
with environmental regulations. Finally, legacy vessel
waterways on which 630 million tons of cargo move each
configuration does not allow the assignment of mixed
year. Additional WCC missions include search and rescue
gender crews in accordance with the Coast Guard’s
(SAR), marine safety, marine environmental protection, and
workforce goals.”
ports, waterways, and coastal security.
WCC Program
Existing Waterways Cutters
The Coast Guard’s 35 existing WCCs (one of which is
Program Initiation and Name
shown in Figure 1), are built to nine different designs, and
The WCC program was initiated in the Coast Guard’s
include 18 WLRs, 13 WLICs, and 4 WLIs. As of 2022, the
FY2018 budget submission. It was earlier called the Inland
35 vessels were an average of 57 years old.
Waterways and Western Rivers Tender (or Cutter) program.
Geographic Distribution
Acquisition Strategy
As of 2019, the 18 WLRs were based at cities along the
The Coast Guard wants to replace the 35 existing waterway
Mississippi and other inland rivers in Alabama, Arkansas,
commerce cutters with 30 new WCCs, including 16 WLRs,
Illinois, Iowa, Kentucky (two cutters), Mississippi (three
11 WLICs, and 3 WLIs. The Coast Guard states that the
cutters), Missouri, Nebraska, Oklahoma, Pennsylvania, and
WCC program
Tennessee (four cutters). Although these locations are in the
partnered with the [U.S. Navy’s] Naval Sea
Systems Command to conduct an independent
https://crsreports.congress.gov
link to page 2 link to page 2 

Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for Congress
alternatives analysis to evaluate materiel and non-
and inland construction tenders. The initial award is
materiel solutions to meet mission needs within cost
worth $28.49 million. The contract includes options
and schedule constraints. Additionally, the WCC
for the construction of a total of 16 river buoy
Program released nine requests for information to
tenders [WLRs] and 11 inland construction tenders
conduct market research and has conducted
[WLICs]. If all contract line items are exercised, the
engineering trade studies and design analysis,
total contract value is estimated at $1.19 billion.
including development of indicative designs.
A total contract value of $1.19 billion for 27 WLRs and
Based on this analysis, the program has determined
WLICs equates to an average cost of about $44.1 million
that three WCC variants will best meet mission
each.
needs. All three variants will be monohull ships,
meaning self-propelled cutters instead of tug and
Figure 3. Coast Guard Notional Designs for WLR,
barge configurations. The river buoy tender and
WLIC, and WLI
inland construction tender variants will be acquired
on one contract; these variants are expected to be
common except for hull length, working deck
layouts, and deck equipment, including the crane.
The inland buoy tender will be procured separately
from the other two variants.…
The WCC Program is working under an accelerated
program schedule to reach initial operational
capability by 2025…. Full operational capability …
is planned for 2030, although this date may change
based on Coast Guard capital investment planning.
(U.S. Coast Guard, “Waterways Commerce
Cutter,” accessed May 12, 2021.)
Figure 2 and Figure 3 show notional Coast Guard designs
for the WCCs. The winner of the WLR/WLIC contract (see
below) will be able to compete for the WLI contract.
Figure 2. Coast Guard Notional Designs for WLR,
WLIC, and WLI
Source: Coast Guard il ustration showing indicative (i.e., notional)
designs for the WLR (top), WLIC (middle), and WLI (bottom).
September 2021 Request for Information
(RFI) on Boats for WCCs
On September 29, 2021, the Coast Guard released a request
for information (RFI) for up to 56 boats that are to be
carried aboard the WCCs. Responses to the RFI were due
by November 1, 2021.
FY2023 Funding
The Coast Guard’s proposed FY2023 budget requests $77.0
Source: Coast Guard il ustration showing indicative (i.e., notional)
million in procurement funding for the WCC program, to be
designs for the WLR (right), WLIC (middle), and WLI (left).
used for the detailed design and construction (DD&C)
April 2021 Request for Proposals (RFP)
contract of the initial articles of the WLR and WLIC.
On April 30, 2021, the Coast Guard released a request for
The explanatory report for the FY2023 DHS
proposals (RFP) for the design and construction of an
Appropriations Act (Division F of H.R. 2617) as released
estimated 27 WLRs and WLICs. Responses to the RFP
by the Senate Appropriations Committee on December 19,
were due by July 30, 2021.
2022, approves the Coast Guard’s FY2023 procurement
October 2022 Contract Award
funding request for the WCC program and states that, for
the WCC program, “the Coast Guard shall maintain
On October 5, 2022, the Coast Guard announced that it had
consistent oversight of the procurement process including
today awarded Birdon America, Inc. of Denver, an
adherence to the small business set aside arrangement
indefinite-delivery, indefinite-quantity firm fixed
throughout the duration of the program (PDF page 49 of
price contract with economic price adjustments for
163).
the detail design and construction of its river buoy
https://crsreports.congress.gov
Coast Guard Waterways Commerce Cutter (WCC) Program: Background and Issues for Congress
IF11672
Ronald O'Rourke, Specialist in Naval Affairs
Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress.
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you
wish to copy or otherwise use copyrighted material.
https://crsreports.congress.gov | IF11672 · VERSION 25 · UPDATED