Coast Guard Cutter Procurement:
Background and Issues for Congress

Updated April 13, 2022
Congressional Research Service
https://crsreports.congress.gov
R42567




Coast Guard Cutter Procurement: Background and Issues for Congress

Summary
The Coast Guard’s program of record (POR), which dates to 2004, calls for procuring 8 National
Security Cutters (NSCs), 25 Offshore Patrol Cutters (OPCs), and 64 Fast Response Cutters
(FRCs) as replacements for 90 aging Coast Guard high-endurance cutters, medium-endurance
cutters, and patrol craft. The total of 64 FRCs includes 58 for domestic use and 6 for use by the
Coast Guard in the Persian Gulf.
NSCs are the Coast Guard’s largest and most capable general-purpose cutters; they are replacing
the Coast Guard’s 12 Hamilton-class high-endurance cutters. NSCs have an estimated average
procurement cost of about $670 million per ship. Congress has fully funded the procurement of
11 NSCs—three more than the 8 in the Coast Guard’s POR—including the 10th and 11th in
FY2018, which (like the 9th NSC) were not requested by the Coast Guard. In FY2020, Congress
provided $100.5 million for procurement of long lead time materials (LLTM) for a 12th NSC, so
as to preserve the option of procuring a 12th NSC while the Coast Guard evaluates its future
needs. The Coast Guard’s proposed FY2023 budget requests $60.0 million in procurement
funding for the NSC program. This request does not include further funding for a 12th NSC; it
does include funding for closing out NSC procurement activities and transitioning to sustainment
of in-service NSCs. Nine NSCs have entered service; the ninth was commissioned into service on
March 19, 2021.
OPCs are to be less expensive and in some respects less capable than NSCs; they are intended to
replace the Coast Guard’s 29 aged medium-endurance cutters. Coast Guard officials describe the
OPC program and the Polar Security Cutter (PSC) program as the service’s highest acquisition
priorities. (The PSC program is covered in another CRS report.) The Coast Guard’s FY2020
budget submission estimated the total acquisition cost of the 25 ships at $10.270 billion, or an
average of about $411 million per ship. The first OPC was funded in FY2018. The first four
OPCs are being built by Eastern Shipbuilding Group (ESG) of Panama City, FL. On October 11,
2019, the Department of Homeland Security (DHS), of which the Coast Guard is a part,
announced that DHS had granted extraordinary contractual relief to ESG under P.L. 85-804 as
amended (50 U.S.C. 1431-1435), a law that authorizes certain federal agencies to provide certain
types of extraordinary relief to contractors who are encountering difficulties in the performance of
federal contracts or subcontracts relating to national defense. The Coast Guard is holding a full
and open competition for a new contract to build OPCs 5 through 15. On January 29, 2021, the
Coast Guard released a Request for Proposals (RFP) for this Stage 2 contract, as it is called.
Responses to the RFP were due by May 28, 2021. The Coast Guard plans to award the Stage 2
contract in the second quarter of FY2022. The Coast Guard’s proposed FY2023 budget requests
$650.0 million in procurement funding for the 5th OPC, LLTM for the 6th, and other program
costs.
FRCs are considerably smaller and less expensive than OPCs; they are intended to replace the
Coast Guard’s 49 aging Island-class patrol boats. The Coast Guard’s FY2020 budget submission
estimated the total acquisition cost of the 58 cutters intended for domestic use at $3.748.1 billion,
or an average of about $65 million per cutter. A total of 64 FRCs were funded through FY2021.
The Coast Guard’s proposed FY2022 budget did not request funding for the procurement of
additional FRCs. In acting on the Coast Guard’s proposed FY2022 budget, Congress added $130
million in FRC procurement funding for the construction of up to two additional FRCs and
associated class-wide activities. If built, the two additional FRCs would be the 65th and 66th
FRCs. As of April 13, 2022, 46 FRCs have been commissioned into service. The Coast Guard’s
proposed FY2023 budget requests $16.0 million in procurement funding for the FRC program;
this request does not include funding for any additional FRCs.
Congressional Research Service

link to page 5 link to page 5 link to page 5 link to page 6 link to page 7 link to page 9 link to page 9 link to page 13 link to page 13 link to page 15 link to page 17 link to page 18 link to page 18 link to page 20 link to page 20 link to page 21 link to page 23 link to page 24 link to page 25 link to page 25 link to page 25 link to page 26 link to page 26 link to page 27 link to page 28 link to page 29 link to page 30 link to page 30 link to page 30 link to page 30 link to page 31 link to page 31 link to page 32 link to page 32 link to page 7 link to page 8 link to page 10 link to page 10 link to page 11 link to page 11 link to page 12 Coast Guard Cutter Procurement: Background and Issues for Congress

Contents
Introduction ..................................................................................................................................... 1
Background ..................................................................................................................................... 1

Older Ships to Be Replaced by NSCs, OPCs, and FRCs .......................................................... 1
Missions of NSCs, OPCs, and FRCs ........................................................................................ 2
NSC Program ............................................................................................................................ 3
OPC Program ............................................................................................................................ 5
Overview ............................................................................................................................. 5
Original Competition and September 2016 Contract Award .............................................. 9
October 2019 Contractual Relief and Program Restructuring ............................................ 9
Stage 2 Competition ........................................................................................................... 11
Notional Construction Schedule and Resulting Ages of Ships Being Replaced ............... 13
Appendices with Additional Information .......................................................................... 14
FRC Program .......................................................................................................................... 14
Issues for Congress ........................................................................................................................ 16
Planned Procurement Quantities Under 2004 Program of Record .......................................... 16
Whether 2004 Program of Record Should Be Updated .......................................................... 17
Use of FY2022 FRC Procurement Funding ............................................................................ 19
Procurement of a 12th NSC ..................................................................................................... 20
Cost and Schedule Risk in OPC Program ............................................................................... 21
November 2020 GAO Report ........................................................................................... 21
Procurement Cost Growth on OPCs 1 Through 4 ............................................................. 21
Risk of Procurement Cost Growth on OPCs 5-25 ............................................................ 22
August 2021 House Committee Request for GAO Review .............................................. 22

Stage 2 Competition for OPC Program ................................................................................... 23
Annual OPC Procurement Rate............................................................................................... 24
Annual or Multiyear (Block Buy) Contracting for OPCs ....................................................... 25
Legislative Activity for FY2023 .................................................................................................... 26
Summary of Appropriations Action on FY2023 Procurement Funding Request .................... 26
Coast Guard Authorization Act of 2022 (H.R. 6865) .............................................................. 26

House ................................................................................................................................ 26
FY2022 National Defense Authorization Act (H.R. 4350) ..................................................... 27
House ................................................................................................................................ 27
Unwavering Support for Our Coast Guard Act (S. 1845) ....................................................... 28
Senate ................................................................................................................................ 28

Figures
Figure 1. National Security Cutter ................................................................................................... 3
Figure 2. National Security Cutter ................................................................................................... 4
Figure 3. Offshore Patrol Cutter ...................................................................................................... 6
Figure 4. Offshore Patrol Cutter ...................................................................................................... 6
Figure 5. Offshore Patrol Cutter ...................................................................................................... 7
Figure 6. Offshore Patrol Cutter ...................................................................................................... 7
Figure 7. Offshore Patrol Cutter Functional Design ........................................................................ 8
Congressional Research Service

link to page 18 link to page 19 link to page 36 link to page 30 link to page 34 link to page 34 link to page 35 link to page 37 link to page 33 link to page 39 link to page 43 link to page 45 link to page 51 link to page 53 Coast Guard Cutter Procurement: Background and Issues for Congress

Figure 8. Fast Response Cutter ...................................................................................................... 14
Figure 9. Fast Response Cutter ...................................................................................................... 15

Figure A-1. Projected Mission Demands vs. Projected Capability/Performance .......................... 32

Tables
Table 1. Summary of Appropriations Action on FY2023 Procurement Funding Request ............ 26

Table A-1. Program of Record Compared to Objective Fleet Mix ................................................ 30
Table A-2. POR Compared to FMAs 1 Through 4 ........................................................................ 30
Table A-3. Force Mixes and Mission Performance Gaps .............................................................. 31
Table A-4. POR Compared to Objective Mixes in FMA Phases 1 and 2 ...................................... 33

Appendixes
Appendix A. Planned Procurement Quantities Under 2004 Program of Record .......................... 29
Appendix B. Requested Funding Levels in PC&I Account .......................................................... 35
Appendix C. Some Considerations Relating to Warranties in Shipbuilding ................................. 39
Appendix D. Impact of Hurricane Michael on OPC Program at Eastern Shipbuilding ................ 41
Appendix E. November 25, 2019, House Committee Letter Regarding OPC Program ............... 47

Contacts
Author Information ........................................................................................................................ 49

Congressional Research Service

Coast Guard Cutter Procurement: Background and Issues for Congress

Introduction
This report provides background information and potential oversight issues for Congress on the
Coast Guard’s programs for procuring 8 National Security Cutters (NSCs), 25 Offshore Patrol
Cutters (OPCs), and 64 Fast Response Cutters (FRCs). The Coast Guard’s proposed FY2023
budget requests $60.0 million, $650.0 million, and $16.0 million in procurement funding,
respectively, for the NSC, OPC, and FRCs programs.
The issue for Congress is whether to approve, reject, or modify the Coast Guard’s funding
requested and acquisition strategies for the NSC, OPC, and FRC programs. Congress’s decisions
on these three programs could substantially affect Coast Guard capabilities and funding
requirements, and the U.S. shipbuilding industrial base.
The NSC, OPC, and FRC programs have been subjects of congressional oversight for many
years, and were previously covered in other CRS reports dating back to 1998 that are now
archived.1 The Coast Guard’s plans for modernizing its fleet of polar icebreakers are covered in a
separate CRS report.2
Background
Older Ships to Be Replaced by NSCs, OPCs, and FRCs
NSCs, OPCs, and FRCs are intended to replace 90 older Coast Guard ships—12 high-endurance
cutters (WHECs), 29 medium-endurance cutters (WMECs), and 49 110-foot patrol craft (WPBs).3
The Coast Guard’s 12 Hamilton (WHEC-715) class high-endurance cutters entered service
between 1967 and 1972.4 The Coast Guard’s 29 medium-endurance cutters included 13 Famous
(WMEC-901) class ships that entered service between 1983 and 1991,5 14 Reliance (WMEC-
615) class ships that entered service between 1964 and 1969,6 and 2 one-of-a-kind cutters that
originally entered service with the Navy in 1944 and 1971 and were later transferred to the Coast

1 This CRS report was first published on June 13, 2012. The earlier CRS reports were Coast Guard Deepwater
Acquisition Programs: Background, Oversight Issues, and Options for Congress, by Ronald O’Rourke (first version
December 18, 2006, final [i.e., archived] version January 20, 2012); CRS Report RS21019, Coast Guard Deepwater
Program: Background and Issues for Congress, by Ronald O’Rourke
(first version September 25, 2001, final [i.e.,
archived] version December 8, 2006); and CRS Report 98-830 F, Coast Guard Integrated Deepwater System:
Background and Issues for Congress
, by Ronald O’Rourke (first version October 5, 1998, final [i.e., archived] version
June 1, 2001). From the late 1990s until 2007, the Coast Guard’s efforts to acquire NSCs, OPCs, and FRCs were parts
of a larger, integrated Coast Guard acquisition effort aimed at acquiring several new types of cutters and aircraft that
was called the Integrated Deepwater System (IDS) program, or Deepwater for short. In 2007, the Coast Guard broke up
the Deepwater effort into a series of individual cutter and aircraft acquisition programs, but continued to use the term
Deepwater as a shorthand way of referring collectively to these now-separated programs. In its FY2012 budget
submission, the Coast Guard stopped using the term Deepwater as a way of referring to these programs.
2 CRS Report RL34391, Coast Guard Polar Security Cutter (Polar Icebreaker) Program: Background and Issues for
Congress
, by Ronald O'Rourke.
3 In the designations WHEC, WMEC, and WPB, W means Coast Guard ship, HEC stands for high-endurance cutter,
MEC stands for medium-endurance cutter, and PB stands for patrol boat.
4 Hamilton-class cutters are 378 feet long and have a full load displacement of about 3,400 tons.
5 Famous-class cutters are 270 feet long and have a full load displacement of about 1,800 tons.
6 Reliance-class cutters are 210 feet long and have a full load displacement of about 1,100 tons.
Congressional Research Service

1

Coast Guard Cutter Procurement: Background and Issues for Congress

Guard.7 The Coast Guard’s 49 110-foot Island (WPB-1301) class patrol boats entered service
between 1986 and 1992.8
Many of these 90 ships are manpower-intensive and increasingly expensive to maintain, and have
features that in some cases are not optimal for performing their assigned missions.9 The high-
endurance cutters and Island-class patrol boats have been or are being removed from service as
they are replaced by NSCs and FRCs. The last of the Coast Guard’s 12 Hamilton-class high-
endurance cutters was decommissioned on April 24, 2021.10
Missions of NSCs, OPCs, and FRCs
NSCs, OPCs, and FRCs, like the ships they are intended to replace, are to be multimission ships
for routinely performing 7 of the Coast Guard’s 11 statutory missions, including
 search and rescue (SAR);
 drug interdiction;
 migrant interdiction;
 ports, waterways, and coastal security (PWCS);
 protection of living marine resources;
 other/general law enforcement; and
 defense readiness operations.11
Smaller Coast Guard patrol craft and boats contribute to the performance of some of these seven
missions close to shore. NSCs, OPCs, and FRCs perform them both close to shore and in the
deepwater environment, which generally refers to waters more than 50 miles from shore.

7 These were the Acushnet (WMEC-167), which originally entered service with the Navy in 1944, and the Alex Haley
(WMEC-39), which originally entered service with the Navy in 1971. The Acushnet served in the Navy from until
1946, when it was transferred to the Coast Guard. The ship was about 214 feet long and had a displacement of about
1,700 tons. The Alex Haley served in the Navy until 1996. It was transferred to the Coast Guard in 1997, converted into
a cutter, and reentered service with the Coast Guard in 1999. It is 282 feet long and has a full load displacement of
about 2,900 tons.
8 Island-class boats are 110 feet long and have a full load displacement of about 135 to 170 tons.
9 A July 2012 Government Accountability Office (GAO) report discussed the generally poor physical condition and
declining operational capacity of the Coast Guard’s older high-endurance cutters, medium-endurance cutters, and 110-
foot patrol craft; see Government Accountability Office, Coast Guard[:]Legacy Vessels’ Declining Conditions
Reinforce Need for More Realistic Operational Targets
, GAO-12-741, July 2012, 71 pp.
10 See, for example, Seapower Staff, “Coast Guard Decommissions Service’s Final High-Endurance Cutter,” Seapower,
April 26, 2021; Associated Press, “US Coast Guard Decommissions Storied Cutter in Alaska,” Associated Press, April
28, 2021. See also Patricia Kime, “The Coast Guard Is Retiring Its Last Hamilton-Class High Endurance Cutter,”
Military.com, April 22, 2021.
11 The four statutory Coast Guard missions that are not to be routinely performed by NSCs, OPCs, and FRCs are
marine safety, aids to navigation, marine environmental protection, and ice operations. These missions are performed
primarily by other Coast Guard ships. The Coast Guard states, however, that “while [NSCs, OPCs, and FRCs] will not
routinely conduct [the] Aids to Navigation, Marine Safety, or Marine Environmental Protection missions, they may
periodically be called upon to support these missions (i.e., validate the position of an Aid to Navigation, transport
personnel or serve as a Command and Control platform for a Marine Safety or Marine Environmental Response
mission, etc.).” (Source: Coast Guard information paper provided to CRS on June 1, 2012.)
Congressional Research Service

2

link to page 7 link to page 8
Coast Guard Cutter Procurement: Background and Issues for Congress

NSC Program
National Security Cutters (Figure 1 and Figure 2)—also known as Legend (WMSL-750)12 class
cutters because they are being named for legendary Coast Guard personnel13—are the Coast
Guard’s largest and most capable general-purpose cutters.14 They are larger and technologically
more advanced than Hamilton-class cutters, and are built by Huntington Ingalls Industries’ Ingalls
Shipbuilding of Pascagoula, MS (HII/Ingalls).
Figure 1. National Security Cutter

Source: Cropped version of photograph accompanying Huntington Ingalls Industries, “National Security Cutter
Kimball (WMSL 756),” December 22, 2018.

12 In the designation WMSL, W means Coast Guard ship and MSL stands for maritime security cutter, large.
13 For a Coast Guard news release that mentions the naming rule for the class, see U.S. Coast Guard, “Acquisition
Update: Keel Authenticated for the Fifth National Security Cutter,” May 17, 2013.
14 The NSC design is 418 feet long and has a full load displacement of about 4,500 tons. The displacement of the NSC
design is about equal to that of Navy’s now-retired Oliver Hazard Perry (FFG-7) class frigates, which were 453 feet
long and had a full load displacement of about 4,200 tons. The Coast Guard’s three polar icebreakers are much larger
than NSCs, but are designed for a more specialized role of operations in polar waters. The Coast Guard states that
The largest and most technologically advanced of the Coast Guard’s newest classes of cutters, the
NSCs replace the aging 378-foot high endurance cutters, which have been in service since the
1960s. Compared to legacy cutters, the NSCs’ design provides better sea-keeping and higher
sustained transit speeds, greater endurance and range, and the ability to launch and recover small
boats from astern, as well as aviation support facilities and a flight deck for helicopters and
unmanned aerial vehicles.
(“National Security Cutter,” accessed April 19, 2018, at https://www.dcms.uscg.mil/Our-
Organization/Assistant-Commandant-for-Acquisitions-CG-9/Programs/Surface-Programs/National-
Security-Cutter/.)
Congressional Research Service

3


Coast Guard Cutter Procurement: Background and Issues for Congress

Figure 2. National Security Cutter

Source: Cropped version of photograph accompanying Huntington Ingalls Industries, “Bertholf (WMSL 750)
Builder's Trials,” March 22, 2019. The caption to the photograph states that it was taken on December 4, 2007.
The Coast Guard’s acquisition program of record (POR)—the service’s list, established in 2004,
of planned procurement quantities for various new types of ships and aircraft—calls for procuring
8 NSCs as replacements for the service’s 12 Hamilton-class high-endurance cutters. The Coast
Guard’s FY2020 budget submission estimated the total acquisition cost of a nine-ship NSC
program at $6.030 billion, or an average of about $670 million per ship.15
Congress has fully funded the procurement of 11 NSCs—three more than the 8 in the Coast
Guard’s POR—including the 10th and 11th in FY2018, which (like the 9th NSC) were not
requested by the Coast Guard. In FY2020, Congress provided $100.5 million for procurement of
long lead time materials (LLTM) for a 12th NSC, so as to preserve the option of procuring a 12th
NSC while the Coast Guard evaluates its future needs.
The Coast Guard’s proposed FY2023 budget requests $60.0 million in procurement funding for
the NSC program. This request does not include further funding for a 12th NSC; it does include
funding for closing out NSC procurement activities and transitioning to sustainment of in-service
NSCs.
Nine NSCs have entered service; the ninth was commissioned into service on March 19, 2021.
The 10th and 11th are under construction.

15 Source: Coast Guard Five-Year (FY2020-FY2024) Capital Investment Plan (CIP) funding table for the Procurement,
Construction and Improvements (PC&I) account.
Congressional Research Service

4

link to page 10 link to page 10 link to page 11 link to page 11 link to page 12 link to page 12 Coast Guard Cutter Procurement: Background and Issues for Congress

OPC Program
Overview
Coast Guard officials describe the Offshore Patrol Cutter (PSC) program and the Polar Security
Cutter (PSC) program16 as the service’s two highest acquisition priorities. The Coast Guard’s
POR calls for procuring 25 OPCs as replacements for the service’s 29 medium-endurance cutters.
The first four OPCs are being built by Eastern Shipbuilding Group (ESG) of Panama City, FL.
OPCs (Figure 3, Figure 4, Figure 5, Figure 6, and Figure 7)—also known as Heritage
(WMSM-915)17 class cutters because they are being named for past cutters that played a
significant role in the history of the Coast Guard and the Coast Guard’s predecessor
organizations18—are to be less expensive and in some respects less capable than NSCs.19 OPCs
are to have a length of 360 feet, which will make them about 86% as long as NSCs, which have a
length of 418 feet. OPCs were earlier estimated to have a full load displacement of 3,500 tons to
3,730 tons, which would have made them about 80% as large in terms of full load displacement
as NSCs, which have a full load displacement of about 4,500 tons20 As the OPC design matured,
however, its estimated displacement grew to about 4,500 tons, making it essentially as large as the
NSC in terms of full load displacement.21

16 For more on the PSC program, see CRS Report RL34391, Coast Guard Polar Security Cutter (Polar Icebreaker)
Program: Background and Issues for Congress
, by Ronald O'Rourke.
17 In the designation WMSM, W means Coast Guard ship and MSM stands for maritime security cutter, medium.
18 For the naming rule for the class and a list of the names of the first 11 OPCs, see U.S. Coast Guard, “The Offshore
Patrol Cutter (OPC) Is The Coast Guard’s Highest Investment Priority and Will Play A Critical Role in the Service’s
Future,” undated, accessed August 15, 2017, at http://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-
for-Acquisitions-CG-9/Newsroom/OPC_Day/. See also Sam LaGrone, “Coast Guard Celebrates Birthday by Naming
11 Planned Offshore Patrol Cutters,” USNI News, August 4, 2017 (updated August 5, 2017).
19 The service states that OPCs:
The OPCs will provide the majority of offshore presence for the Coast Guard’s cutter fleet,
bridging the capabilities of the 418-foot national security cutters, which patrol the open ocean, and
the 154-foot fast response cutters, which serve closer to shore. The OPCs will conduct missions
including law enforcement, drug and migrant interdiction, search and rescue, and other homeland
security and defense operations. Each OPC will be capable of deploying independently or as part of
task groups and serving as a mobile command and control platform for surge operations such as
hurricane response, mass migration incidents and other events. The cutters will also support Arctic
objectives by helping regulate and protect emerging commerce and energy exploration in Alaska.
(“Offshore Patrol Cutter,” accessed April 20, 2018, https://www.dcms.uscg.mil/Our-Organization/
Assistant-Commandant-for-Acquisitions-CG-9/Programs/Surface-Programs/Offshore-Patrol-
Cutter/Offshore-Patrol-Cutter-Program-Profile/.)
20 As of May 26, 2017, the OPC’s light ship displacement (i.e., its “empty” displacement, without fuel, water, ballast,
stores, and crew) was preliminarily estimated at about 2,640 to 2,800 tons, and its full load displacement was
preliminarily estimated at about 3,500 to 3,730 tons. (Source: Figures provided to CRS by Cost Guard liaison office,
May 26, 2017.) In terms of full load displacement, this would have made OPCs roughly 80% as large as NSCs.
21 Source: Email from Coast Guard liaison office to CRS, November 25, 2019. See also Figure 7.
Congressional Research Service

5



Coast Guard Cutter Procurement: Background and Issues for Congress

Figure 3. Offshore Patrol Cutter
Artist’s rendering

Source: Photograph accompanying Kirk Moore, “Coast Guard’s Birthday Present: Naming the Next Cutters,”
WorkBoat, August 4, 2017. A caption to the rendering credits the rendering to Eastern Shipbuilding Group.
Figure 4. Offshore Patrol Cutter
Artist’s rendering

Source: “Offshore Patrol Cutter Notional Design Characteristics and Performance,” accessed September 16,
2016, at https://www.dcms.uscg.mil/Portals/10/CG-9/Surface/OPC/OPC%20Placemat%2036x24.pdf?ver=2018-10-
02-134225-297.
Congressional Research Service

6



Coast Guard Cutter Procurement: Background and Issues for Congress

Figure 5. Offshore Patrol Cutter
Artist’s rendering

Source: Eastern Shipbuilding Group (http://www.easternshipbuilding.com/), accessed September 9, 2019.
Figure 6. Offshore Patrol Cutter
Artist’s rendering

Source: Image received from Coast Guard liaison office, May 25, 2017.
Congressional Research Service

7


Coast Guard Cutter Procurement: Background and Issues for Congress

Figure 7. Offshore Patrol Cutter Functional Design
“Placemat” summary from Coast Guard

Source: Slide 11 from Coast Guard presentation at OPC Industry Day, December 11, 2019, updated December
13, 2019, accessed December 17, 2019, at https://beta.sam.gov/opp/bf0b9b0a1fe2428e9a73043259641c13/view.
The Coast Guard’s FY2020 budget submission estimated the total acquisition cost of the 25 ships
at $10.270 billion, or an average of about $411 million per ship.22 The first OPC was funded in
FY2018. The Coast Guard’s proposed FY2023 budget requests $650.0 million in procurement
funding for the 5th OPC, LLTM for the 6th, and other program costs.
The Coast Guard’s initial Request for Proposals (RFP) for the OPC program, released on
September 25, 2012, established an affordability requirement for the program of an average unit
price of $310 million per ship, or less, in then-year dollars (i.e., dollars that are not adjusted for
inflation) for ships 4 through 9 in the program.23 This figure represents the shipbuilder’s portion
of the total cost of the ship; it does not include the cost of government-furnished equipment

22 Source: Coast Guard Five-Year (FY2020-FY2024) Capital Investment Plan (CIP) funding table for the Procurement,
Construction and Improvements (PC&I) account.
23 Source: Section C.5 of the RFP, accessed October 31, 2012, at http://www.uscg.mil/ACQUISITION/newsroom/
updates/opc092512.asp.
Congressional Research Service

8

Coast Guard Cutter Procurement: Background and Issues for Congress

(GFE) on the ship,24 or other program costs—such as those for program management, system
integration, and logistics—that contribute to the above-cited figure of $411 million per ship.25
Original Competition and September 2016 Contract Award
In response to the September 25, 2012, RFP, at least eight shipyards expressed interest in the OPC
program.26 On February 11, 2014, the Coast Guard announced that it had awarded Preliminary
and Contract Design (P&CD) contracts to three of those eight firms—Bollinger Shipyards of
Lockport, LA; Eastern Shipbuilding Group (ESG) of Panama City, FL; and General Dynamics’
Bath Iron Works (GD/BIW) of Bath, ME.27 On September 15, 2016, the Coast Guard announced
that it had awarded the detail design and construction (DD&C) contract to ESG. The contract
covered detail design and production of up to 9 OPCs and had a potential value of $2.38 billion if
all options were exercised.28
October 2019 Contractual Relief and Program Restructuring
On October 11, 2019, the Department of Homeland Security (DHS), of which the Coast Guard is
a part, announced that DHS had granted extraordinary contractual relief to ESG under P.L. 85-
804 as amended (50 U.S.C. 1431-1435), a law originally enacted in 1958 that authorizes certain
federal agencies to provide certain types of extraordinary relief to contractors who are
encountering difficulties in the performance of federal contracts or subcontracts relating to

24 GFE is equipment that the government procures and then delivers to the shipyard for installation on the ship.
25 Source: Coast Guard emails to CRS dated June 25, 2013.
26 The firms were the following: Bollinger Shipyards of Lockport, LA; Eastern Shipbuilding Group of Panama City,
FL; General Dynamics Bath Iron Works (GD/BIW) of Bath, ME; Huntington Ingalls Industries (HII) of Pascagoula,
MS; Marinette Marine Corporation of Marinette, WS; General Dynamics National Steel and Shipbuilding Company
(GD/NASSCO) of San Diego, CA; Vigor Shipyards of Seattle, WA; and VT Halter Marine of Pascagoula, MS.
(Source: U. S. Coast Guard Offshore Patrol Cutter (OPC) List of Interested Contractors Updated July 2012, accessed
October 23, 2012, at http://www.uscg.mil/ACQUISITION/opc/pdf/companiesinterested.pdf; and Kevin Brancato and
Anne Laurent, Coast Guard’s $12 Billion Cutter Competition Spurs Eight Shipyards to Dive In, Bloomberg
Government Study, November 8, 2012, 6 pp. The Coast Guard document states that these firms “expressed interest in
the Offshore Patrol Cutter acquisition and have agreed to their names provided on the Coast Guard website.” See also
Stew Magnuson, “New Coast Guard Cutter Sparks Fierce Competition Among Shipbuilders,” National Defense
(www.nationaldefensemagazine.org), April 2013, accessed March 26, 2013, at
http://www.nationaldefensemagazine.org/articles/2013/4/1/2013april-new-coast-guard-cutter-sparks-fierce-
competition-among-shipbuilders.)
27 “Acquisition Update: U.S. Coast Guard Awards Three Contracts for Offshore Patrol Cutter Preliminary and Contract
Design,” February 11, 2014, accessed February 14, 2014, at https://www.dcms.uscg.mil/Portals/10/CG-9/Newsroom/
In%20The%20News%20Archives/2014/opc021114.pdf?ver=2017-05-23-145011-727. HII and VT Halter Marine
reportedly filed protests of the Coast Guard’s award decision on February 24 and 25, respectively. The Coast Guard
issued stop work orders to Bollinger, Eastern, and GD/BIW pending GAO’s rulings on the protests. (Calvin Biesecker,
“Coast Guard Issues Stop Work Orders On OPC Following Protests,” Defense Daily, February 28, 2014: 2-3. See also
Christopher P. Cavas, “Ingalls Protesting US Coast Guard Cutter Contract,” DefenseNews.com, February 26, 2014.) On
June 5, 2014, it was reported that GAO had rejected the protests, and that the Coast Guard had directed Bollinger,
Eastern, and GD/BIW to resume their work. (Calvin Biesecker, “Coast Guard Directs Design Work Continue On OPC
After GAO Denies Protests,” Defense Daily, June 5, 2014: 1; Christopher P. Cavas, “US Coast Guard Cutter Award
Upheld,” Defense News (http://www.defensenews.com), June 5, 2014. For the text of the decision, see Government
Accountability Office, Decision in the Matter of Huntington Ingalls Industries, Inc.; VT Halter Marine, Inc., June 2,
2014.)
28 “Acquisition Update: Coast Guard Selects Offshore Patrol Cutter Design,” September 15, 2016; “Acquisition
Update: Coast Guard Moves Forward To Next Phase Of OPC Acquisition,” October 5, 2016. See also “Coast Guard
Exercises Long Lead Time Materials Option For First Offshore Patrol Cutter,” September 7, 2017.
Congressional Research Service

9

link to page 51 Coast Guard Cutter Procurement: Background and Issues for Congress

national defense.29 ESG reportedly submitted a request for extraordinary relief on June 30, 2019,
after ESG’s shipbuilding facilities were damaged by Hurricane Michael, which passed through
the Florida panhandle on October 10, 2018.
The Coast Guard announced that the contractual relief would be limited to the first four hulls in
the OPC program, and that the OPC program would be restructured to include a competition for a
new contract to build subsequent OPCs,30 identified later as OPCs 5 through 15. Under P.L. 85-
804 as amended, Congress had 60 days of continuous session to review the announced
contractual relief, with the 60-day period in this case starting October 11, 2019.31 The Coast
Guard refers to the follow-on competition as the Stage 2 competition.
A November 25, 2019, letter to the Acting Secretary of DHS from the Chair and Ranking
Member of the House Transportation and Infrastructure Committee and the Chair and Ranking
Member of that committee’s Coast Guard and Maritime Transportation subcommittee regarding
the OPC program posed a number of questions regarding the Coast Guard’s October 2019
contractual relief and restructuring of the OPC program. The text of this letter, including these
questions, is presented in Appendix E.

29 50 U.S.C. 1431 states in part
The President may authorize any department or agency of the Government which exercises
functions in connection with the national defense, acting in accordance with regulations prescribed
by the President for the protection of the Government, to enter into contracts or into amendments or
modifications of contracts heretofore or hereafter made and to make advance payments thereon,
without regard to other provisions of law relating to the making, performance, amendment, or
modification of contracts, whenever he deems that such action would facilitate the national defense.
The authority conferred by this section shall not be utilized to obligate the United States in an
amount in excess of $50,000 without approval by an official at or above the level of an Assistant
Secretary or his Deputy, or an assistant head or his deputy, of such department or agency, or by a
Contract Adjustment Board established therein.
For more on P.L. 85-804 as amended, see CRS Report 76-261, Extraordinary Contractual Relief Under Public Law 85-
804
, April 28, 1976, by Andrew C. Mayer. The report was prepared at the request of the House Armed Services
Committee and converted by the committee into a committee print (70-905 O), dated May 10, 1976, that can be viewed
at https://ufdc.ufl.edu/AA00022546/00001/1j. See also David H. Peirez, “Public Law 85-804: Contractual Relief for the
Government Contractor,” Administrative Law Review, Vol. 16 (Summer 1964): 248-264, accessed October 11, 2019, at
https://www.jstor.org/stable/40708469; and “Presidential Power: Public Law 85-804 (50 U.S.C. §§ 1431-35),” Brennan
Center for Justice, undated, accessed October 11, 2019, at https://www.brennancenter.org/sites/default/files/analysis/
50%20USC%201431-1435.pdf. (Although it is undated, it appears to have been written no earlier than 2014, as it
includes three references to the year 2014, including one that states, “As of 2014….”) The text of P.L. 85-804 as
originally enacted is posted at https://www.govinfo.gov/content/pkg/STATUTE-72/pdf/STATUTE-72-Pg972.pdf.
30 Department of Homeland Security, “DHS Extends Contract Relief for Offshore Patrol Cutter,” October 11, 2019;
U.S. Coast Guard, “Department of Homeland Security Approves Limited Extraordinary Relief for Offshore Patrol
Cutter Contract,” October 11, 2019; “DHS, Coast Guard Extend Limited Contract Relief for Offshore Patrol Cutter,”
Coast Guard News (coastguardnews.com), October 11, 2019.
31 50 U.S.C. 1431 states in part
The authority conferred by this section may not be utilized to obligate the United States in any
amount in excess of $25,000,000 unless the Committees on Armed Services of the Senate and the
House of Representatives have been notified in writing of such proposed obligation and 60 days of
continuous session of Congress have expired following the date on which such notice was
transmitted to such Committees. For purposes of this section, the continuity of a session of
Congress is broken only by an adjournment of the Congress sine die at the end of a Congress, and
the days on which either House is not in session because of an adjournment of more than 3 days to
a day certain, or because of an adjournment sine die other than at the end of a Congress, are
excluded in the computation of such 60-day period.
Congressional Research Service

10

Coast Guard Cutter Procurement: Background and Issues for Congress

In the FY2021 National Defense Authorization Act (H.R. 6395/P.L. 116-283 of January 1, 2021),
Division G is the Elijah E. Cummings Coast Guard Authorization Act of 2020. Section 8221 of
Division G of H.R. 6395/P.L. 116-283 states
SEC. 8221. MODIFICATION OF ACQUISITION PROCESS AND PROCEDURES.
(a) EXTRAORDINARY RELIEF.—
(1) IN GENERAL.—Subchapter III of chapter 11 of title 14, United States Code, is
amended by adding at the end the following:
‘‘§ 1157. Extraordinary relief
‘‘(a) IN GENERAL.—With respect to any prime contracting entity receiving extraordinary
relief pursuant to the Act entitled ‘An Act to authorize the making, amendment, and
modification of contracts to facilitate the national defense’, approved August 28, 1958
(Public Law 85–804; 50 U.S.C. 1432 et seq.) for a major acquisition, the Secretary shall
not consider any further request by the prime contracting entity for extraordinary relief
under such Act for such major acquisition.
‘‘(b) INAPPLICABILITY TO SUBCONTRACTORS.—The limitation under subsection
(a) shall not apply to subcontractors of a prime contracting entity.
‘‘(c) QUARTERLY REPORT.—Not less frequently than quarterly during each fiscal year
in which extraordinary relief is approved or provided to an entity under the Act referred to
in subsection (a) for the acquisition of Offshore Patrol Cutters, the Commandant shall
provide to the Committee on Commerce, Science, and Transportation of the Senate and the
Committee on Transportation and Infrastructure of the House of Representatives a report
that describes in detail such relief and the compliance of the entity with the oversight
measures required as a condition of receiving such relief.’’.
(3) ANALYSIS FOR CHAPTER 11.—The analysis for chapter 11 of title 14, United States
Code, is amended by inserting after the item relating to section 1156 the following:
‘‘1157. Extraordinary relief.’’.
(b) NOTICE TO CONGRESS WITH RESPECT TO BREACH OF CONTRACT.—
Section 1135 of title 14, United States Code, is amended by adding at the end the following:
‘‘(d) NOTICE TO CONGRESS WITH RESPECT TO BREACH OF CONTRACT.—Not
later than 48 hours after the Commandant becomes aware that a major acquisition contract
cannot be carried out under the terms specified in the contract, the Commandant shall
provide a written notification to the Committee on Commerce, Science, and Transportation
of the Senate and the Committee on Transportation and Infrastructure of the House of
Representatives that includes—
‘‘(1) a description of the terms of the contract that cannot be met; and
‘‘(2) an assessment of whether the applicable contract officer has issued a cease and desist
order to the contractor based on the breach of such terms of the contract.’’.
Stage 2 Competition
March 2020 Contract Awards for Industry Studies
On January 10, 2020, the Coast Guard released an RFP for industry studies in connection with the
Stage 2 competition, with responses due by January 31, 2020. On March 20, 2020, the Coast
Guard announced that it had awarded nine Stage 2 industry study contracts to the following firms:
 Austal USA of Mobile, AL;
Congressional Research Service

11

Coast Guard Cutter Procurement: Background and Issues for Congress

 General Dynamics/Bath Iron Works (GD/BIW) of Bath, ME;
 Bollinger Shipyards Lockport of Lockport, LA;
 Eastern Shipbuilding Group (ESG) of Panama City, FL;
 Fincantieri Marinette Marine (F/MM) of Marinette, WS;
 General Dynamics/National Steel and Shipbuilding Company (GD/NASSCO) of
San Diego, CA;
 Huntington Ingalls Industries/Ingalls Shipbuilding (HII/Ingalls) of Pascagoula,
MS:
 Philly Shipyard of Philadelphia, PA; and
 VT Halter Marine Inc. of Pascagoula, MS.32
October 2020 Draft Request for Proposals (RFP)
On October 9, 2020, the Coast Guard released a draft RFP for the Stage 2 competition. Responses
to the draft RFP, which helped inform the Coast Guard’s drafting of the final version of the RFP,
were due by November 23, 2020. The notional schedule that accompanied the draft RFP called
for long leadtime materials (LLTM) for OPC 5 to be procured at the end of FY2022/start of
FY2023, for construction of OPC 5 to begin at the end of FY2023, and for construction to be
complete at the end of FY2026. OPCs 6 through 15 follow in annual quantities of 1-1-2-2-2-2,
with LLTM for OPCs 14 and 15 to be procured at the start of the fourth quarter of FY2029, and
for construction of those two ships to be complete by the start of the fourth quarter of FY2032.
Contract Award Planned for Second Quarter of FY2022
On January 29, 2021, the Coast Guard released the RFP for the Stage 2 competition, with
responses due by May 28, 2021. The Coast Guard plans to award the Stage 2 contract in the
second quarter of FY2022.33 The contract is to be a Fixed Price Incentive Firm (FPIF) contract for
detail design and construction of up to 11 OPCs, including Long Lead Time Materials (LLTM), as
well as logistics, training, and life-cycle engineering. One observer stated on March 29, 2021, that

32 Most of the contracts had a base award value of $2.0 million and a total potential value of $3.0 million. The
exceptions were the contract awarded to ESG, which had a base award value of $1.1 million and a total potential value
of $1.2 million (a difference that appeared to reflect ESG’s status as the builder of the first four OPCs), and the contract
awarded to VT Halter, which has a total potential value of $2.9 million. The Coast Guard stated in its contract-award
announcement that
Under their respective contracts, the awardees will assess OPC design and technical data, provided
by the Coast Guard, and the program’s construction approach. Based on their analyses, the
awardees will recommend to the Coast Guard potential strategies and approaches for the follow-on
detail design and construction (DD&C). The awardees will also discuss how they would prepare
the OPC functional design for production. The awardees may also identify possible design or
systems revisions that would be advantageous to the program if implemented, with strategies to
ensure those revisions are properly managed.
The Coast Guard will use the industry studies results to further inform its follow-on acquisition
strategy and promote a robust competitive environment for the DD&C award. Participation in
industry studies is not a pre-requisite for submitting a DD&C proposal.
(U.S. Coast Guard, “Coast Guard Awards Nine Contracts for Offshore Patrol Cutter Industry
Studies,” March 20, 2020.)
33 In January 2022, the Coast Guard confirmed that it plans to award the contract in the spring of 2022. (Cal Biesecker,
“Coast Guard Still Planning On Spring Award For OPC Phase 2 Contract,” Defense Daily, January 12, 2022.)
Congressional Research Service

12

Coast Guard Cutter Procurement: Background and Issues for Congress

In the current 11-ship [Stage 2] proposal, the Coast Guard is giving interested shipyards an
enormous amount of leeway to redesign the cutter’s innards, a tactic that, according to
stakeholders, facilitates increased competition. Newly proposed ships must look generally
the same [as ESG’s OPC design] from the outside, but almost everything “under the
hood”—outside of a few major components—can be changed, shifted or modified.34
In June 2021, it was reported that firms that had publicly disclosed that they are bidders for the
Stage 2 competition include ESG, Huntington Ingalls Industries (HII), and Bollinger Shipyards.35
(It is possible that other firms chose to not publicly disclose that they are bidders.)
Notional Construction Schedule and Resulting Ages of Ships Being Replaced
The posting for the RFP for the Stage 2 industry studies included an attached notional timeline for
building the 25 OPCs. Under the timeline, OPCs 1 through 7 (i.e., OPCs 1-4, to be built by ESG,
plus OPCs 5-7, which are the first three OPCs to be built by the winner of the Stage 2
competition) are to be built at a rate of one per year, with OPC-1 completing construction in
FY2022 and OPC-7 completing construction in FY2028. The remaining 18 OPCs (i.e., OPCs 8
through 25) are to be built at a rate of two per year, with OPC-8 completing construction in
FY2029 and OPC-25 completing construction in FY2038.
Using these dates—which are generally 10 months to about two years later than they would have
been under the Coast Guard’s previous (i.e., pre-October 11, 2019) timeline for the OPC
program36—the Coast Guard’s 14 Reliance-class 210-foot medium-endurance cutters would be
replaced when they would be (if still in service) about 54 to 67 years old, and the Coast Guard’s
13 Famous-class 270-foot medium-endurance cutters would be replaced when they would be (if
still in service) about 42 to 52 years old.37

34 Craig Hooper, “U.S. Coast Guard Seeks Builders For Big New Cutters,” Forbes, March 29, 2021.
35 Cal Biesecker, “Eastern Shipbuilding, Huntington Ingalls Also Bid On Coast Guard OPC Program,” Defense Daily,
June 14, 2021.
36 Source for ships 1-4: An October 15, 2019, press report states
Under the new plan, the Coast Guard intends for Eastern Shipbuilding Group (ESG) to build up to
four OPCs rather than the minimum of nine contracted for a year ago, with the first ship now
delayed 10 to 12 months and the three subsequent ships about nine to 10 months each from that
point, Shultz said at an event hosted by the Center for Strategic and International Studies. Delivery
of the first OPC, which began construction in January, has been pushed back to 2022.
(Cal Biesecker, “Decision To Reopen OPC Competition Will Stretch Out Acquisition,” Defense
Daily
, October 15, 2019. See also Gina Harkins, “Despite Hurricane Damage, Coast Guard
Pressing On with Next-Gen Cutter Construction,” Military.com, October 15, 2019; Ben Werner,
“Coast Guard Seeks To Bring Bidders Onto Modified Offshore Patrol Cutter Contract,” USNI
News
, October 15, 2019.)
Source for ships 5 through 25: CRS comparison of notional timeline’s completion dates with those shown in Figure 4
on page 17 of Government Accountability Office, Coast Guard Recapitalization[:] Matching Needs and Resources
Continue to Strain Acquisition Efforts
, GAO-17-654 T, June 7, 2017. (Testimony Before the Subcommittee on Coast
Guard and Maritime Transportation, Committee on Transportation and Infrastructure, House of Representatives,
Statement of Marie A. Mak, Director, Acquisition and Sourcing Management.)
37 Source: CRS estimate based on replacement sequence shown in Government Accountability Office, Coast Guard
Recapitalization[:] Matching Needs and Resources Continue to Strain Acquisition Efforts
, GAO-17-654 T, June 7,
2017. (Testimony Before the Subcommittee on Coast Guard and Maritime Transportation, Committee on
Transportation and Infrastructure, House of Representatives, Statement of Marie A. Mak, Director, Acquisition and
Sourcing Management.)
Congressional Research Service

13

link to page 45 link to page 51 link to page 18 link to page 19
Coast Guard Cutter Procurement: Background and Issues for Congress

Appendices with Additional Information
For additional background information on the impact of Hurricane Michael on the OPC program
at ESG, see Appendix D. As mentioned earlier, for the text of a November 25, 2019, letter to the
Acting Secretary of DHS from the Chair and Ranking Member of the House Transportation and
Infrastructure Committee and the Chair and Ranking Member of that committee’s Coast Guard
and Maritime Transportation subcommittee regarding the October 2019 contractual relief and
restructuring of the OPC program under P.L. 85-804, see Appendix E.
FRC Program
Fast Response Cutters (Figure 8 and Figure 9) are considerably smaller and less expensive than
OPCs, but are larger than the Coast Guard’s older patrol boats.38 FRCs, which are built by
Bollinger Shipyards of Lockport, LA, are also called Sentinel (WPC-1101)39 class patrol boats
because they are being named for enlisted leaders, trailblazers, and heroes of the Coast Guard and
its predecessor services of the U.S. Revenue Cutter Service, U.S. Lifesaving Service, and U.S.
Lighthouse Service.40
Figure 8. Fast Response Cutter
With an older Island-class patrol boat behind

Source: U.S. Coast Guard photo accessed May 4, 2012, at http://www.flickr.com/photos/coast_guard/
6871815460/sizes/l/in/set-72157629286167596/.
The Coast Guard’s POR calls for procuring 64 FRCs as replacements for the service’s 49 Island-
class patrol boats, including 58 for domestic use and 6 for use by the Coast Guard in the Persian

38 FRCs are 154 feet long and have a full load displacement of 353 tons.
39 In the designation WPC, W means Coast Guard ship and PC stands for patrol craft.
40 Source for class naming rule: U.S. Coast Guard bulletin, “ALCOAST 349/17 - Nov 2017 New Fast Response Cutters
Named for Coast Guard heroes,” November 22, 2017, accessed November 20, 2017, at
https://content.govdelivery.com/accounts/USDHSCG/bulletins/1c6c844.
Congressional Research Service

14


Coast Guard Cutter Procurement: Background and Issues for Congress

Gulf as elements of a Bahrain-based Coast Guard unit, called Patrol Forces Southwest Asia
(PATFORSWA), which is the Coast Guard’s largest unit outside the United States.41
Figure 9. Fast Response Cutter

Source: Photograph accompanying Mallory Shelbourne, “Coast Guard Takes Delivery of Sixth Bahrain-Based
Fast Response Cutter,” USNI News, January 6, 2022. The article credits the photograph to Bol inger Shipyards.
The Coast Guard’s FY2020 budget submission estimated the total acquisition cost of the 58
cutters intended for domestic use at $3.748.1 billion, or an average of about $65 million per
cutter.
A total of 64 FRCs were funded through FY2021. The Coast Guard’s proposed FY2022 budget
did not request funding for the procurement of additional FRCs. In acting on the Coast Guard’s
proposed FY2022 budget, Congress added $130 million in FRC procurement funding for the
construction of up to two additional FRCs and associated class-wide activities.42 If built, the two
additional FRCs would be the 65th and 66th FRCs. The Coast Guard stated on April 13, 2022, that
The Joint Explanatory Statement that accompanied the FY 2022 [DHS] appropriation [act]
specified that $130 million was appropriated “for the construction of up to two Fast
Response Cutters and associated class-wide activities.” At this time, the FRC Program of

41 For additional information on PATFORSWA, see U.S. Coast Guard, “Patrol Forces Southwest Asia,
PATFORSWA,” accessed April 13, 2022, at https://www.atlanticarea.uscg.mil/Our-Organization/Area-Units/
PATFORSWA/, U.S. Coast Guard, “CG Patrol Forces SWA Org Chart,” accessed April 13, 2022, at
https://www.atlanticarea.uscg.mil/Our-Organization/Area-Units/PATFORSWA/Departments/; Edward H. Lundquist,
“PATFORSWA Serves Forward in the Arabian Gulf,” Defense Media Network, March 19, 2018; Eric D. Nielsen
(posted by Connie Terrell), “PATFORSWA: Guardians of the Arabian Gulf,” Coast Guard Compass, August 22, 2016.
42 The joint explanatory statement for the FY2022 DHS appropriations act (Division F of H.R. 2471/P.L. 117-103 of
March 15, 2022) states (emphasis added):
The agreement provides an increase of $391,000,000 above the request [for the Coast Guard’s
Procurement, Construction, and Improvements (PC&I) appropriation account], including the
following: $130,000,000 for the construction of up to two Fast Response Cutters and
associated class-wide activities
; $128,000,000 for the HC-130J aircraft program; $98,000,000 to
recapitalize MH-60T aircraft with new hulls; and two information technology systems on the Coast
Guard's UPL [unfunded priorities list]: $20,000,000 for Coast Guard management system
recapitalization and $9,000,000 for Vessel Traffic System and Command and Control
modernization. (PDF page 47 of 157)
Congressional Research Service

15

Coast Guard Cutter Procurement: Background and Issues for Congress

Record remains 64. The Coast Guard is working to determine how the FY 2022
appropriation may impact the FRC Program of Record.43
The Coast Guard’s proposed FY2023 budget requests $16.0 million in procurement funding for
the FRC program; this request does not include funding for any additional FRCs.
Issues for Congress
Planned Procurement Quantities Under 2004 Program of Record
One issue for Congress is whether the planned procurement quantities for NSCs, OPCs, and
FRCs under the Coast Guard’s 2004 program of record (POR) are too high, too low, or about
right. The POR’s planned force of NSCs, OPCs, and FRCs is comparable in number to the Coast
Guard’s legacy force of 90 high-endurance cutters, medium-endurance cutters, and 110-foot
patrol craft. NSCs, OPCs, and FRCs, moreover, are to be individually more capable than the older
ships they are to replace. Even so, a Coast Guard fleet mix analysis conducted in 2011 (the most
recent such analysis that the Coast Guard has released) concluded that the then-planned total of
91 NSCs, OPCs, and FRCs (including 58 FRCs rather than 64) would provide 61% of the cutters
that would be needed to fully perform the service’s statutory missions in coming years, in part
because Coast Guard mission demands were projected to be greater in coming years than they
were in the past.
In the FY2021 National Defense Authorization Act (H.R. 6395/P.L. 116-283 of January 1, 2021),
Division G is the Elijah E. Cummings Coast Guard Authorization Act of 2020. Section 8261 of
Division G of H.R. 6395/P.L. 116-283 states
SEC. 8261. REPORT ON FAST RESPONSE CUTTERS, OFFSHORE PATROL
CUTTERS, AND NATIONAL SECURITY CUTTERS.
(a) IN GENERAL.—Not later than 90 days after the date of the enactment of this Act, the
Commandant shall submit to the Committee on Commerce, Science, and Transportation of
the Senate and the Committee on Transportation and Infrastructure of the House of
Representatives a report on the combination of Fast Response Cutters, Offshore Patrol
Cutters, and National Security Cutters necessary to carry out Coast Guard missions.
(b) ELEMENTS.—The report required by subsection (a) shall include—
(1) an updated cost estimate for each type of cutter described in such subsection; and
(2) a cost estimate for a Sensitive Compartmented Information Facility outfitted to manage
data in a manner equivalent to the National Security Cutter Sensitive Compartmented
Information Facilities.
The joint explanatory statement for the FY2022 DHS Appropriations Act (Division F of H.R.
2471/P.L. 117-103 of March 15, 2022, the Consolidated Appropriations Act, 2022) states
Fleet Mix Analysis.—The Coast Guard shall provide to the Committees within 180 days of
the date of enactment of this Act, a comprehensive analysis that provides a fleet mix
sufficient to carry out the assigned missions of the Coast Guard and other emerging mission
requirements. The Coast Guard shall brief the Committees within 60 days of the date of
enactment of this Act on its plans to carry out this requirement. (PDF page 48 of 157)

43 Source: Coast Guard email to CRS, April 13, 2022.

Congressional Research Service

16

link to page 33 Coast Guard Cutter Procurement: Background and Issues for Congress

For further discussion of this issue, about which CRS has testified and reported on since 2005,44
see Appendix A.
Whether 2004 Program of Record Should Be Updated
A related issue for Congress is whether the Coast Guard’s 2004 POR, including its planned
procurement quantities for NSCs, OPCS, and FRCs, should be updated. As discussed in the CRS
overview report on Navy force structure and shipbuilding plans, the Navy since 2004 has updated
its ship force-level goals several times since 2004.45
The Navy’s force-level goals may require more frequent updating than the Coast Guard’s POR,
because the Navy’s force-level goals are sensitive to ongoing developments affecting the
maritime military capabilities of foreign countries, particularly China,46 whereas the Coast
Guard’s program of record is arguably rooted more in geographic considerations (such as the
sizes of sea areas to be patrolled) that are subject to less change over time. Even so, some of the
Coast Guard’s planning factors might change over time; potential examples include factors
relating to
 how cutters are based, crewed, and operated, which can affect the number of days
per year that a cutter spends at sea;
 emergent mission needs resulting from the actions of others; and
 changes in the role of the Coast Guard in implementing overall U.S. national
strategy.
Regarding the second and third items above, some observers see a potential for increased illegal
fishing in certain U.S. fisheries, such as those in the central Pacific,47 and the Coast Guard has
recently been highlighting its deployments of cutters to the Western Pacific to operate in
conjunction with U.S. Navy ships as part of a U.S. effort to counter China’s increasing
capabilities and operations in those waters.48

44 See Statement of Ronald O’Rourke, Specialist in National Defense, Congressional Research Service, Before the
Senate Commerce, Science, and Transportation Committee, Subcommittee on Fisheries and the Coast Guard, Hearing
on The Coast Guard’s Revised Deepwater Implementation Plan, June 21, 2005, pp. 1-5.
45 See CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by
Ronald O'Rourke, particularly the Background section and Table A-1.
46 For additional discussion, see CRS Report RL33153, China Naval Modernization: Implications for U.S. Navy
Capabilities—Background and Issues for Congress
, by Ronald O'Rourke.
47 A February 2020 press report, for example, states, “For the first time in eight years, the U.S. Coast Guard has
intercepted illegal fishing vessels within American EEZ [Exclusive Economic Zone] areas in the Central and Western
Pacific. Fishing boat interdiction is a common task for the Coast Guard off the coast of Texas, where Mexican ‘lancha’
fishing boats are routinely intercepted in U.S. waters, but IUU [illegal, unreported, and unregulated] fishing by foreign
vessels is almost unheard of in America’s far-flung Pacific Ocean EEZ regions.” (Maritime Executive, “USCG
Intercepts Illegal Fishing Vessels Off Guam and Hawaii,” Maritime Executive, February 24, 2021.) See also Ralph
Espach, “A New Great Game Finds the South Atlantic,” War on the Rocks, March 22, 2021.
48 See, for example, Christopher Woody, “On the Front Lines Against China, the US Coast Guard Is Taking on
Missions the US Navy Can’t Do,” Business Insider, January 11, 2022; Adam Stahl and Bradley A. Thayer, “The Coast
Guard Is Vital to Defending Taiwan Against China,” The Hill, October 31, 2021; Alex Wilson, “Coast Guard Cutter
Munro Arrives for Patrol with 7th Fleet in Western Pacific,” Stars and Stripes, August 17, 2021; Richard R. Burgess,
“Coast Guard Increasing Engagement with Pacific Allies, Partners, U.S. Navy,” Seapower, June 28, 2021; Cal
Biesecker, “Biden Says U.S. Coast Guard Will Take On More Global Missions; Highlights Indo-Pacific Region,”
Defense Daily, May 19, 2021; William Cole (Honolulu Star-Advertiser), “Cutter Deployments Point to Bigger US
Military Role in Western Pacific,” Military.com, April 5, 2021; Peter Suciu, “The Military’s New Weapon Against
China And Russia: The Coast Guard?” 19FortyFive, March 17, 2021 (a similar article was published as “The Military’s
Congressional Research Service

17

Coast Guard Cutter Procurement: Background and Issues for Congress

A February 24, 2021, letter to the Commandant of the Coast Guard from the Chair and Ranking
Member of the House Transportation and Infrastructure Committee and the Chair and Ranking
Member of the committee’s Coast Guard and Maritime Transportation subcommittee states
We are concerned that past Fleet Mix Analyses conducted by the United States Coast
Guard (Service, USCG, or Coast Guard) are outdated. As such, those analyses no longer
reflect the current global threat environment, the growing mission requirements facing the
Coast Guard (particularly those related to the current global threat environment), or the
Coast Guard’s hard-won operating experience with Fast Response Cutters (FRCs) and
National Security Cutters (NSCs).
As the Coast Guard fulfills its requirements under Section 8261, Report on Fast Response
Cutters, Offshore Patrol Cutters, and National Security Cutters, of the Elijah E. Cummings
Coast Guard Authorization Act of 2020 (Division G of P.L. 116-283), we urge you to
consider the following operational developments which have created additional demands
for USCG cutter assets worldwide:
- U.S. Indo-Pacific Command rotational deployments of multiple NSCs to U.S. Naval
Surface Group Western Pacific over the past two years;
- Expanding requirements that justified homeporting three FRCs to Guam;
- Russian Navy exercises that disrupted the U.S. fishing fleet legitimately operating within
the U.S. Exclusive Economic Zone in the Bering Sea;
- Increased deployments to U.S. Southern Command’s area of responsibility for drug
interdiction in support of surge operations announced in April 2020;
- NSC Illegal, Unreported and Unregulated (IUU) fishing enforcement patrol with the
Ecuadorian Navy targeting the massive Chinese distant water fishing fleet operating in or
near the Galapagos Islands Exclusive Economic Zone;
- Expanding requirements that justified replacing the six 110’ Island Class patrol boats with
FRCs in Bahrain;
- Anticipated NSC deployments in support of U.S. 5th Fleet and U.S. 6th Fleet; and
- A recent NSC deployment to South America for IUU fishing enforcement with Brazil &
Argentina.
All the operational developments noted above are important for our national defense and
security, and all occurred after the release of the last Fleet Mix Analysis which was
conducted in 2011. Such new missions have placed additional demands on the Coast
Guard, its people, its platforms, and its budgets, none of which are reflected in the 2011
Fleet Mix Analysis.
While there were updates to the Fleet Mix Analyses in 2011 and 2019, the Congressional
Research Service (CRS) concluded that even the 91 cutters in the USCG’s 2004 Program
of Record were not enough to meet Coast Guard mission needs back then. In fact, that
cutter fleet, when fully built out, was only expected to meet 61 percent of envisioned Coast
Guard missions. As the Coast Guard reports its resultant Fleet Mix requirement numbers,
we would like to understand what percentage of missions will be met and, importantly,
what it would take to meet 100 percent of the Service’s anticipated offshore missions.

New Weapon Against China and Russia: the Coast Guard?” National Interest, March 22, 2021, with a byline of Caleb
Larson but an author’s background note suggesting that the author is actually Peter Suciu); Lucy Craymer and Ben
Kesling, “U.S. Deploys Coast Guard Far From Home to Counter China, The Service Has Gotten Increasingly Active in
the Western Pacific as Chinese Fishing Fleets Expand into New Waters,” Wall Street Journal, March 15, 2021; Gidget
Fuentes, “Schultz: Coast Guard Units Remain in High Demand as Forces Stretches to Meet Needs,” USNI News, March
15, 2021; Paul McLeary, “Coast Guard Deploying More Ships To Pacific, Arctic,” Breaking Defense, March 11 2021.
Congressional Research Service

18

Coast Guard Cutter Procurement: Background and Issues for Congress

Additionally, we would like the Coast Guard to provide answers to the following questions
in the Section 8261 report:
1. Which USCG assets are best equipped to deal with peer competition at sea, including
organic self-defense capability and interoperability with the U.S. Navy?
2. What additional resources will the USCG need for day-to-day engagement in support of
Combatant Commanders?
3. What effect has the increased commitment to provide USCG assets in support of DoD
combatant commands across the globe had on domestic mission needs, considering these
support operations are only partially funded by DoD? Specifically, provide a summary of
assets that have been deployed internationally in support of Combatant Commanders,
including an analysis of the types of activities they have been engaged in, and a breakdown
of the time those assets spent executing domestic and/or international missions over the
past eight years.
4. What are the IUU fishing hot spots (i.e., areas of emphasis) around the world and what
additional USCG maritime domain awareness and response resources are needed to address
U.S. concerns in these areas?
5. Given the increased presence of Russian and Chinese vessels in the Arctic, is the USCG
exploring a mix of assets, including ice-hardened cutters, to execute USCG missions within
the U.S. EEZ off the coast of Alaska (i.e., Gulf of Alaska, Bering Sea, Arctic Ocean)? What
additional assets are needed to have a robust presence in the Arctic to meet current and
future USCG missions?
6. What is the status of the offshore patrol cutter (OPC) program and what assurances can
you provide that the first OPC will be delivered in 2022? What is the current shipbuilder
cost (i.e., total contract awards to date) and expected final cost of the first OPC, including
nonrecurring costs? What is the current shipbuilder cost and expected final cost of the
second OPC? How many cutters’ years have been lost due to the Department of Homeland
Security decision to reset the program in October 2019?
As we continue our oversight of the U.S. Coast Guard and provide for the future fleet, we
thank you in advance for your consideration and response to this additional direction as
part of the report required by Section 8261 of the Elijah E. Cummings Coast Guard
Authorization Act of 2020 (Division G of P.L. 116-283), which is due to Congress no later
than 90 days after the date of enactment. If you have questions please contact [deleted]
Subcommittee on Coast Guard and Maritime Transportation [deleted].49
Use of FY2022 FRC Procurement Funding
Another issue for Congress concerns the use of the $130 million that Congress appropriated in
FY2022 for the construction of up to two additional FRCs and associated class-wide activities. If
built, the two additional FRCs would be the 65th and 66th FRCs. As noted earlier, the Coast Guard
on April 13, 2022, stated that “at this time, the FRC Program of Record remains 64. The Coast

49 Letter dated February 24, 2021, Admiral Karl Schultz, Commandant, United States Coast Guard, from
Representative Peter A. DeFazio, Representative Sam Graves, Representative Salud Carbajal, and Representative Bob
Gibbs accessed March 15, 2021, at https://transportation.house.gov/imo/media/doc/2021-02-
24%20Big%204%20LTR%20to%20USCG%20Commandant%20ADM%20Schultz_%20Fleet%20Mix%20Analysis.p
df. See also Cal Biesecker, “House Panel Wants Updated Coast Guard Fleet Analysis To Factor In New Demands,”
Defense Daily, March 2, 2021.
Congressional Research Service

19

link to page 33 link to page 33 Coast Guard Cutter Procurement: Background and Issues for Congress

Guard is working to determine how the FY 2022 appropriation may impact the FRC Program of
Record.”50
Procurement of a 12th NSC
Another issue for Congress is whether to procure a 12th NSC. Supporters of procuring a 12th NSC
could argue that
 a total of 12 NSCs would provide one-for-one replacements for the 12 retiring
Hamilton-class cutters;
 Coast Guard analyses showing a need for no more than 8 or 9 NSCs assumed that
NSCs would be operated with 4:3 rotational crewing (i.e., four crews for every
three ships)51—a plan that the Coast Guard in February 2018 told the
Government Accountability Office (GAO) that it had abandoned;52
 the Coast Guard’s POR record includes only about 61% as many new cutters as
the Coast Guard has calculated would be required to fully perform the Coast
Guard’s anticipated missions in coming years (see Appendix A);
 the Coast Guard has recently been highlighting its deployments of cutters to the
Western Pacific to operate in conjunction with U.S. Navy ships as part of a U.S.
effort to counter China’s increasing capabilities and operations in those waters—
deployments that could increase demands for NSCs beyond what the Coast
Guard anticipated when it established its program of record in 2004;53 and
 the increase in the estimated displacement of the OPC to 4,500 tons—a figure
about equal to the displacement of NSCs—makes procuring additional NSCs
more suitable as a near-term measure for responding to potential delays in the
restructured OPC program.
Skeptics or opponents of procuring a 12th NSC could argue that
 the Coast Guard’s 2004 POR includes only 8 NSCs;
 the Coast Guard’s fleet mix analyses (see Appendix A) have not shown a
potential need for more than 9 NSCs;

50 Source: Coast Guard email to CRS, April 13, 2022.

51 GAO testified in 2017 that “to achieve 230 days away from homeport [per year for each NSC], the Coast Guard
plans to use a ‘crew rotational concept’ in which four crews staff and operate three [NSC] cutters on a rotating basis.”
(Government Accountability Office, Coast Guard Recapitalization[:] Matching Needs and Resources Continue to
Strain Acquisition Efforts
, GAO-17-654T, Testimony Before the Subcommittee on Coast Guard and Maritime
Transportation, Committee on Transportation and Infrastructure, House of Representatives, Statement of Marie A.
Mak, Director, Acquisition and Sourcing Management, June 7, 2017, p. 6 [note a to Table 1].)
52 A 2018 GAO report stated
In February 2018, USCG officials told GAO they abandoned the crew rotational concept because
the concept did not provide the USCG with the expected return on investment. Instead, USCG
officials said a new plan has been implemented that does not rotate crew and is anticipated to
increase the days away from home port from the current capability of 185 days to 200 days.
(Government Accountability Office, Homeland Security Acquisitions[:] Leveraging Programs’
Results Could Further DHS’s Progress to Improve Portfolio Management
, GAO-18-339SP, May
2018, p. 92.)
53 See, for example, Dan Goure, “New U.S. Maritime Strategy Makes Case for More Coast Guard Cutters,” National
Interest
, January 6, 2021.
Congressional Research Service

20

Coast Guard Cutter Procurement: Background and Issues for Congress

 the Coast Guard intends to move expeditiously to proceed with its restructured
effort to procure OPCs; and
 in a situation of finite Coast Guard budgets, procuring a 12th NSC might reduce
funding available for other Coast Guard programs, including the OPC and PSC
programs.
Cost and Schedule Risk in OPC Program
Another potential oversight issue for Congress concerns cost and schedule risk in the OPC
program following the Coast Guard’s restructuring of the program.
November 2020 GAO Report
A November 2020 GAO report on the OPC program states
The Coast Guard’s determination to deliver the OPCs in a timely manner has driven the
program through key acquisition decisions despite significant design, testing, schedule, and
cost risks, which remained or were exacerbated after the hurricane….
Unstable Design. The Coast Guard authorized the start of construction for the first two
OPCs despite not having a stable design, which is inconsistent with shipbuilding best
practices. Proceeding towards OPC 3 construction before stabilizing the design—including
maturing the design drawings of major ship systems—increases the risk of construction
rework if changes are needed. This could further delay schedules and increase costs.
Deficient and Optimistic Schedule. Prior to the construction award for OPC 1, the OPC
program’s schedule has contained significant deficiencies that are contrary to what is called
for in best practices for developing schedules that GAO identified. Further, the revised
post-hurricane delivery dates for the first four OPCs are optimistic and do not fully
incorporate schedule risks, increasing the likelihood that the OPCs will not be delivered
when promised.
Incomplete Cost Estimate. The cost estimate used to inform the program’s new cost goals
did not include key analyses called for in best practices for developing cost estimates GAO
identified. These key analyses include varying assumptions to determine how sensitive the
estimates are to various factors and quantifying the effects of potential risks. Omitting these
analyses undermines the credibility of the estimated program costs, increasing the risk that
decision makers do not have a complete picture of the full range of costs the program could
incur.54
Procurement Cost Growth on OPCs 1 Through 4
The Coast Guard stated that as of mid-April 2020, the combined estimated procurement cost of
OPCs 1 through 4 had increased by a total of between $300 million and $400 million since the
Coast Guard’s 2017 Life Cycle Cost Estimate (LCCE) for the program, with the increase on the
cost OPC-1 being larger than the increases on the costs of OPCs 2 through 4, and that almost all
of the increase is attributable to relief provided under P.L. 85-804.55 A combined increase of $300
million to $400 million for OPCS 1 through 4 would represent an increase of 18% to 24% above
the $411 million average procurement cost for each of 25 OPCs as estimated under the Coast

54 Government Accountability Office, Coast Guard Acquisitions[:] Opportunities Exist to Reduce Risk for the Offshore
Patrol Cutter Program
, GAO-21-9, October 2020, summary page.
55 Source: Coast Guard email to CRS, April 15, 2020.
Congressional Research Service

21

Coast Guard Cutter Procurement: Background and Issues for Congress

Guard’s FY2020 budget submission. The November 2020 GAO report on the OPC program
states
As of May 2020, the Coast Guard used the granted relief to increase ESG’s contract ceiling
price for detail design and construction of the first two OPCs by 38 percent, from $779
million to $1.07 billion. In July 2020, Coast Guard officials told us that they plan to modify
the contract prices for OPCs 3 and 4 by no later than June 2021 and June 2022,
respectively.56
Potential oversight questions for Congress include the following:
 Of the increase of $300 million to $400 million in the combined estimated
procurement cost of OPCs 1 through 4, how much was due to the effects of
Hurricane Michael?
 What potential, if any, is there for further cost growth on OPCs 1 through 4?
 What implications, if any, does the cost growth on OPCs 1 through 4 have for the
potential for cost growth on subsequent OPCs?
Risk of Procurement Cost Growth on OPCs 5-25
Another issue for Congress is the risk of procurement cost growth on OPCs 5 through 25,
particularly given the increase in the OPC’s estimated full load displacement from 3,500 to 3,730
tons as of May 2017 to 4,500 tons as of November 2019—an increase of more than 20%—and
how this risk might affect the probability that OPCs can be built within the Coast Guard’s
affordability requirement for the OPC program of an average unit price of $310 million per ship,
or less, in then-year dollars for ships 4 through 9 in the program for the shipbuilder’s portion of
the ship’s total cost. Since, as a general matter, the cost of a ship of a given type is roughly
proportional to its displacement, the increase of more than 20% in the OPC’s estimated full load
displacement raises a possibility that the cost to build OPCs may have increased, perhaps
substantially, from earlier estimates. The draft statement of work (SOW) for the Coast Guard’s
intended follow-on competition for the OPC program that the Coast Guard posted on November
22, 2019, required contractors responding to the RFI to provide, among other things, “a risk
assessment of achieving the OPC Program’s previously established affordability target for
production OPCs.”
August 2021 House Committee Request for GAO Review
In a letter dated August 16, 2021, the House Transportation and Infrastructure Committee
requested GAO to review the management of the OPC program and the Coast Guard’s efforts for
managing its existing medium endurance cutters. The letter stated the following:
Initially projected to cost about $12 billion over its 30-year life cycle, the [OPC] program
recently experienced significant cost and schedule delays….
In addition to construction of the OPC, the Committee continues to remain concerned about
the operational gap between the end of service life for the aging Medium Endurance Cutters
and the delayed delivery of the OPCs….
Given the significant budgetary commitment that the Congress, DHS, and Coast Guard
have made for the OPC program to date, continued oversight is necessary to ensure the
OPC program does not continue to experience cost growth or additional schedule delays.

56 Government Accountability Office, Coast Guard Acquisitions[:] Opportunities Exist to Reduce Risk for the Offshore
Patrol Cutter Program
, GAO-21-9, October 2020, p. 12.
Congressional Research Service

22

Coast Guard Cutter Procurement: Background and Issues for Congress

As such, the Committee requests that the Government Accountability Office (GAO) review
the management of the OPC and Medium Endurance Cutters acquisition programs
including, but not limited to:
• The status of the Phase 1 (the first four hulls) and Phase 2 (hulls 5 through 25) OPC
acquisition programs, including what steps are being taken to manage the program within
the revised cost and schedule commitments; and
• The status of the Medium Endurance Cutters and level of maintenance needed to keep
the fleet operating to minimize the operational gap until the OPCs are incrementally
delivered.57
Stage 2 Competition for OPC Program
Another potential oversight issue for Congress concerns the Coast Guard’s Stage 2 competition
for OPCs 5 through 15. As mentioned earlier, the Coast Guard reportedly wants Stage 2 bidders
to retain ESG’s basic outer hull design for the OPC while permitting bidders the option of altering
the design’s interior details. Potential oversight issues for Congress include but are not
necessarily limited to the following:
 How much of a production learning curve advantage will ESG have in the Stage
2 competition as a result of having some amount of experience in building its
OPC design?
 To what degree would such an advantage be reduced by permitting Stage 2
bidders to alter the interior details (but not the basic outer hull design) of ESG’s
OPC design?
 How would a new OPC design that employs a different outer hull form compare
with an OPC design that retains ESG’s basic outer hull design while perhaps
altering interior details in terms of
 capability;
 costs, including design cost, procurement cost, and life-cycle operation and
support (O&S) cost; and
 force-management considerations, including crew training and assignment
and logistic support?
One observer stated on March 29, 2021, that
A good bit of the current competition rests upon just how much confidence the Coast Guard
has in the cutter design Eastern created before the 2016 award.…
The only problem is that the “new” Cutters acquired from the current solicitation will still
be derived from Eastern’s detailed design—a design that is still incomplete and still pretty
much proprietary to Eastern. Quite a few in the shipbuilding community believe that
Eastern could only have won the original Offshore Patrol Cutter contract by underbidding
a poorly-proofed basic design. Today, some potential bidders are reluctant to even think

57 Letter dated August 16, 2021, from Representative Peter A. DeFazio, Chairman, and Representative Sam Graves,
Ranking Member, House Committee on Transportation and Infrastructure, to The Honorable Gene Dodaro,
Comptroller General, Government Accountability Office, accessed August 17, 2021, at
https://transportation.house.gov/imo/media/doc/2021-08-
16%20GAO%20Request%20Letter%20for%20OPC%20Follow%20On%20Review%20FINAL.pdf. See also House
Transportation and Infrastructure Committee, “T&I Committee Leaders Ask GAO to Review Delays in Delivery of
Critical Additions to Coast Guard Fleet,” press release, August 16, 2021, and Cal Biesecker, “House Transportation
Leaders Want GAO To Review Coast Guard OPC, PSC Programs,” Defense Daily, August 16, 2021.
Congressional Research Service

23

link to page 39 Coast Guard Cutter Procurement: Background and Issues for Congress

about advancing and modifying a basic design they don’t have detailed information about
and still don’t fully trust. This uncertainty—combined with the slow pace of third-party
certification of Eastern’s detailed design work—leaves some industry observers wondering
if the eleven-ship proposal is actually a thinly-disguised opportunity for Eastern
Shipbuilding Group to fix their existing design and re-baseline their original aggressive
2016 Offshore Patrol Cutter pricing.
While the Coast Guard admits that the current Heritage class cutter [i.e., OPC] opportunity
is poorly-timed due to the Hurricane-driven delays, Coast Guard stakeholders insist that
the contract opportunity maximizes competition. Rather than fret about introducing
extensive changes in the Heritage class design, Coast Guard sources point to the 210-foot
Reliance class, a 60’s-era mid-sized cutter. While all the ships of the Reliance class appear
to be similar, the Coast Guard changed the ship’s entire propulsion system in the middle
of a 16-ship production run, eliminating design weaknesses that plagued the first six ships
and threatened the future of the entire Reliance cutter class. The redesign worked, and the
Reliance class cutters are still going strong, some 50-60 years later.58
Annual OPC Procurement Rate
Another oversight issue for Congress concerns the planned OPC procurement rate in relation to
the ages of the medium-endurance cutters that the OPCs are to replace. The current procurement
profile for the OPC, which reaches a maximum projected annual rate of two ships per year, would
deliver OPCs many years after the end of the originally planned service lives of the medium-
endurance cutters. As mentioned earlier, under the Coast Guard’s new notional timeline, the
Coast Guard’s 14 Reliance-class 210-foot medium-endurance cutters would be replaced when
they would be (if still in service) about 54 to 67 years old, and the Coast Guard’s 13 Famous-
class 270-foot medium-endurance cutters would be replaced when they would be (if still in
service) about 42 to 52 years old. These ages, particularly for the Reliance-class cutters, would be
very high, raising questions as to whether the ships could be made to last that long, and whether
they would be able to cost effectively perform their missions at such ages.
Coast Guard officials have testified that the service plans to extend the service lives of the
medium-endurance cutters until they are replaced by OPCs. There will be maintenance and repair
expenses associated with operating aged medium-endurance cutters, particularly during their final
years of intended service, and if the Coast Guard does not also make investments to increase the
capabilities of these ships, the ships may have less capability in certain regards than OPCs.59
One possible option for addressing this situation would be to increase the maximum annual OPC
procurement rate from the currently planned two ships per year to three or four ships per year.
Doing this could result in the 25th OPC being delivered a few to several years sooner than under
the currently planned maximum rate. Increasing the OPC procurement rate to three or four ships
per year could require a substantial increase to the Coast Guard’s Procurement, Construction, and
Improvements (PC&I) account,60 an issue discussed in Appendix B, and/or providing additional
funding for the procurement of OPCs through the Navy’s budget.
Increasing the maximum procurement rate for the OPC program could, depending on the exact
approach taken, reduce OPC unit acquisition costs due to improved production economies of
scale. It might also expand opportunities for using competition in the program. Notional

58 Craig Hooper, “U.S. Coast Guard Seeks Builders For Big New Cutters,” Forbes, March 29, 2021.
59 For further discussion, see Government Accountability Office, Coast Guard Acquisitions[:] Actions Needed to
Address Longstanding Portfolio Management Challenges
, GAO 18-454, July 2018, pp. 32-36.
60 Prior to FY2019, the PC&I account was called the Acquisition, Construction, and Improvements (AC&I) account.
Congressional Research Service

24

Coast Guard Cutter Procurement: Background and Issues for Congress

alternative approaches for increasing the OPC procurement rate to three or four ships per year
include but are not necessarily limited to the following:
 increasing the production rate to three or four ships per year at a single
shipyard—an option that would depend on that shipyard’s production capacity;
 using two shipyards for building OPCs to a single OPC design;
 using two shipyards for building OPCs to two designs, with each shipyard
building OPCs to its own design—an option that would result in two OPC classes
(similar to how the Coast Guard currently operates two primary classes of
medium-endurance cutters); or
 building additional NSCs in the place of some of the planned OPCs—an option
that might include de-scoping equipment on those NSCs where possible to
reduce their acquisition cost and make their capabilities more like that of the
OPC.
The fourth alternative above—which could be viewed as broadly similar to how the Navy is using
a de-scoped version of the San Antonio (LPD-17) class amphibious ship as the basis for its LPD-
17 Flight II (LPD-30) class amphibious ships61—could be pursued in combination with one of the
first three alternatives.
Annual or Multiyear (Block Buy) Contracting for OPCs
Another issue for Congress is whether to acquire OPCs 5 through 25 using annual contracting or
multiyear contracting. The Coast Guard typically uses contracts with options for its shipbuilding
programs. Although a contract with options may look like a form of multiyear contracting, it
operates more like a series of annual contracts. Contracts with options do not achieve the kinds of
reductions in acquisition costs that are possible with multiyear contracting. Using multiyear
contracting involves accepting certain trade-offs.62
One form of multiyear contracting, called block buy contracting, can be used at the start of a
shipbuilding program, beginning with the first ship. (Indeed, this was a principal reason why
block buy contracting was in effect invented in FY1998, as the contracting method for procuring
the Navy’s first four Virginia-class attack submarines.63) Section 311 of the Frank LoBiondo
Coast Guard Authorization Act of 2018 (S. 140/P.L. 115-282 of December 4, 2018) provides
permanent authority for the Coast Guard to use block buy contracting with economic order

61 For additional discussion, see CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship Programs:
Background and Issues for Congress
, by Ronald O'Rourke.
62 These trade-offs include the following:
- reduced congressional control over year-to-year spending, and tying the hands of future Congresses;
- reduced flexibility for making changes in Coast Guard acquisition programs in response to unforeseen changes in
strategic or budgetary circumstances (which can cause any needed funding reductions to fall more heavily on
acquisition programs not covered by multiyear contracts);
- a potential need to shift funding from later fiscal years to earlier fiscal years to fund economic order quantity
(EOQ) purchases (i.e., up-front batch purchases) of components;
- the risk of having to make penalty payments to shipbuilders if multiyear contracts need to be terminated due to
unavailability of funds needed for the continuation of the contracts; and
- the risk that materials and components purchased for ships to be procured in future years might go to waste if
those ships are not eventually procured.
63 For additional discussion, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in
Defense Acquisition: Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service

25

link to page 30 Coast Guard Cutter Procurement: Background and Issues for Congress

quantity (EOQ) purchases (i.e., up-front batch purchases) of components in its major acquisition
programs. The authority is codified at 14 U.S.C. 1137.
CRS estimates that if the Coast Guard were to use block buy contracting with EOQ purchases of
components for acquiring the first several OPCs beginning with OPC 5, and either block buy
contracting with EOQ purchases or another form of multiyear contracting known as multiyear
procurement (MYP)64 with EOQ purchases for acquiring the remaining ships in the program, the
savings on the total acquisition cost of the 25 OPCs (compared to costs under contracts with
options) could amount to hundreds of millions of dollars.
Legislative Activity for FY2023
Summary of Appropriations Action on FY2023 Procurement
Funding Request
Table 1
summarizes appropriations action on the Coast Guard’s request for FY2023 procurement
funding for the NSC, OPC, and FRC programs.
Table 1. Summary of Appropriations Action on FY2023 Procurement
Funding Request
Figures in millions of dollars, rounded to nearest tenth
Request
Request
HAC
SAC
Enacted
NSC program
60.0



OPC program
650.0



FRC program
16.0



Source: Table prepared by CRS, based on Coast Guard’s FY2023 budget submission, HAC and SAC committee
reports, and conference report or explanatory statement on FY2023 DHS Appropriations Act. HAC is House
Appropriations Committee; SAC is Senate Appropriations Committee.
Coast Guard Authorization Act of 2022 (H.R. 6865)
House
Section 104(a) and (b) of H.R. 6865 as passed by the House on March 29, 2022, states
SEC. 104. AVAILABILITY OF AMOUNTS FOR ACQUISITION OF ADDITIONAL
CUTTERS.
(a) In General.—Of the amounts authorized to be appropriated under—
(1) section 4902(2)(A)(i) of title 14, United States Code, as amended by section 101 of this
title, for fiscal year 2022;
(A) $300,000,000 shall be authorized for the acquisition of a twelfth National Security
Cutter; and
(B) $210,000,000 shall be authorized for the acquisition of 3 Fast Response Cutters; and
(2) section 4902(2)(A)(ii) of title 14, United States Code, as amended by section 101 of
this title, for fiscal year 2023;

64 For more on MYP, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense
Acquisition: Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service

26

Coast Guard Cutter Procurement: Background and Issues for Congress

(A) $300,000,000 shall be authorized for the acquisition of a twelfth National Security
Cutter; and
(B) $210,000,000 shall be authorized for the acquisition of 3 Fast Response Cutters.
(b) Treatment Of Acquired Cutter.—Any cutter acquired using amounts authorized under
subsection (a) shall be in addition to the National Security Cutters and Fast Response
Cutters approved under the existing acquisition baseline in the program of record for the
National Security Cutter and Fast Response Cutter.
Section 212 states
SEC. 212. STUDY ON LAYDOWN OF COAST GUARD CUTTERS.
Not later than 120 days after the date of enactment of this Act, the Secretary of Homeland
Security, in consultation with the Secretary of Transportation, shall conduct a study on the
laydown of Coast Guard Fast Response Cutters to assess Coast Guard mission readiness
and to identify areas of need for asset coverage.
FY2022 National Defense Authorization Act (H.R. 4350)
House
The House Armed Services Committee’s report (H.Rept. 117-118 of September 10, 2021) on
H.R. 4350 states
Sentinel-class Fast Response Cutter
The committee looks forward to reviewing the Navy’s updated force structure assessment
and shipbuilding plan. The committee understands the Navy intends to change the fleet
architecture reflected in the 355-ship force-level goal to reflect a more distributed fleet mix
with a smaller proportion of larger ships and a larger proportion of smaller manned ships
as well as unmanned vessels. The committee supports incorporating a mix of smaller
manned ships into the fleet and encourages the Navy to consider the capabilities the U.S.
Coast Guard’s Sentinel-class Fast Response Cutter could provide to the fleet and the
concept of operations and associated requirements that would support acquisition of these
vessels.
Further, the committee is aware the U.S. Coast Guard has contract options for 12 additional
Sentinel-class Fast Response Cutters with firm fixed pricing in place until May of 2023.
Exercising these contract options in advance of their expiration would lock in favorable
pricing on Sentinel-class Fast Response Cutters should the Navy determine that they add
value to the fleet.
Given the successes of the U.S. Coast Guard’s Sentinel-class Fast Response Cutter in
support of the Navy’s Fifth Fleet as a part of Patrol Forces Southwest Asia, the committee
believes there are similar roles for Sentinel-class Fast Response Cutters in other areas of
responsibility. Therefore, the committee directs the Secretary of the Navy to submit a report
to the congressional defense committees not later than February 1, 2022, that details the
current mission sets and operating requirements for the Sentinel-class Fast Response Cutter
and expands on how successes in the U.S. Central Command area of responsibility would
translate to other regions, including the U.S. Indo-Pacific Command. Further, the
committee directs the Secretary of the Navy to assess the requisite upgrades to the Sentinel-
class Fast Response Cutter required to meet Navy standards and evaluate the concept of
operations for employing these vessels in Southeast Asia. This report should be
unclassified but may include a classified annex. (Page 21)
Congressional Research Service

27

Coast Guard Cutter Procurement: Background and Issues for Congress

Unwavering Support for Our Coast Guard Act (S. 1845)
Senate
S. 1845 was introduced on May 26, 2021. Section 5 of S. 1845 states
SEC. 5. FLEET MIX ANALYSIS.
(a) IN GENERAL.—The Commandant of the Coast Guard (referred to in this Act as the
‘‘Commandant’’) shall conduct an updated fleet mix analysis that provides for a fleet mix
sufficient, as determined by the Commandant—
(1) to carry out—
(A) the missions of the Coast Guard; and
(B) emerging mission requirements; and
(2) to address—
(A) national security threats; and
(B) the global deployment of the Coast Guard to counter great power competitors.
(b) REPORT.—Not later than 1 year after the date of the enactment of this Act, the
Commandant shall submit to Congress a report on the results of the updated fleet mix
analysis required by subsection (a).65


65 Source: Text of bill accessed June 8, 2021, at https://www.commerce.senate.gov/services/files/EE424A5F-2029-
4330-A471-F08DAF26EEAB.
Congressional Research Service

28

link to page 39 Coast Guard Cutter Procurement: Background and Issues for Congress

Appendix A. Planned Procurement Quantities
Under 2004 Program of Record
This appendix provides further discussion on the issue of the planned procurement quantities for
NSCs, OPCs, and FRCs under the Coast Guard’s 2004 POR.
Overview
The Coast Guard’s 2004 POR for NSCs, OPCs, and FRCs (including 58 rather than 64 FRCs)
includes only about 61% as many cutters as the Coast Guard calculated in 2011 would be needed
to fully perform its projected future missions. (The Coast Guard’s 2011 analysis is the most
recent such analysis that the Coast Guard has released.) Except for the subsequent addition of 6
cutters to the planned FRC total (with those 6 ships to be used in the Persian Gulf), the Coast
Guard’s planned force levels for NSCs, OPCs, and FRCs have remained unchanged since 2004.
In contrast, the Navy since 2004 has adjusted its ship force-level goals several times since 2004.66
Although the Coast Guard’s strategic situation and resulting mission demands may not have
changed as much as the Navy’s have since 2004, the Coast Guard’s budgetary circumstances may
have changed since 2004. The 2004 program of record was heavily conditioned by Coast Guard
expectations in 2004 about future funding levels in the PC&I account. Those expectations may
now be different, as suggested by the willingness of Coast Guard officials in 2017 to begin
regularly mentioning the need for a PC&I funding level of $2 billion per year (see Appendix B).
It can also be noted that continuing to, in effect, use the Coast Guard’s 2004 expectations of
future funding levels for the PC&I account as an implicit constraint on planned force levels for
NSCs, OPCs, and FRCs can encourage an artificially narrow view of Congress’s options
regarding future Coast Guard force levels and associated funding levels, depriving Congress of
agency in the exercise of its constitutional power to provide for the common defense and general
welfare of the United States, and to set funding levels and determine the composition of federal
spending.
2009 Coast Guard Fleet Mix Analysis
The Coast Guard estimated in 2009 that with the POR’s then-planned force of 91 NSCs, OPCs,
and FRCs (including 58 rather than 64 FRCs), the service would have capability or capacity
gaps67 in 6 of its 11 statutory missions—search and rescue (SAR); defense readiness; counterdrug
operations; ports, waterways, and coastal security (PWCS); protection of living marine resources
(LMR); and alien migrant interdiction operations (AMIO). The Coast Guard judged that some of
these gaps would be “high risk” or “very high risk.”
Public discussions of the POR frequently mention the substantial improvement that the POR
force would represent over the legacy force. Only rarely, however, have these discussions
explicitly acknowledged the extent to which the POR force would nevertheless be smaller in
number than the force that would be required, by the Coast Guard’s 2011 estimate, to fully
perform the Coast Guard’s statutory missions in coming years. Discussions that focus on the
POR’s improvement over the legacy force while omitting mention of the considerably larger

66 See CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by
Ronald O'Rourke, particularly Table A-1.
67 The Coast Guard uses capability as a qualitative term, to refer to the kinds of missions that can be performed, and
capacity as a quantitative term, to refer to how much (i.e., to what scale or volume) a mission can be performed.
Congressional Research Service

29

link to page 34 link to page 34 link to page 34 Coast Guard Cutter Procurement: Background and Issues for Congress

number of cutters that would be required, by Coast Guard estimate, to fully perform the Coast
Guard’s statutory missions in coming years could encourage audiences to conclude, contrary to
Coast Guard estimates, that the POR’s planned force of NSCs, OPCs, and FRCs would be
capable of fully performing the Coast Guard’s statutory missions in coming years.
In a study completed in December 2009 called the Fleet Mix Analysis (FMA) Phase 1, the Coast
Guard calculated the size of the force that in its view would be needed to fully perform the
service’s statutory missions in coming years. The study referred to this larger force as the
objective fleet mix. Table A-1 compares planned numbers of NSCs, OPCs, and FRCs in the POR
to those in the objective fleet mix.
Table A-1. Program of Record Compared to Objective Fleet Mix
From Fleet Mix Analysis Phase 1 (2009)
Objective
Objective Fleet Mix
Fleet Mix
compared to POR
Program of
From FMA
Ship type
Record (POR)
Phase 1
Number
%
NSC
8
9
+1
+13%
OPC
25
57
+32
+128%
FRC
58
91
+33
+57%
Total
91
157
+66
+73%
Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13.
As can be seen in Table A-1, the objective fleet mix includes 66 additional cutters, or about 73%
more cutters than in the 2004 POR. Stated the other way around, the 2004 POR includes about
58% as many cutters as the 2009 FMA Phase I objective fleet mix.
As intermediate steps between the POR force and the objective fleet mix, FMA Phase 1
calculated three additional forces, called FMA-1, FMA-2, and FMA-3. (The objective fleet mix
was then relabeled FMA-4.) Table A-2 compares the POR to FMAs 1 through 4.
Table A-2. POR Compared to FMAs 1 Through 4
From Fleet Mix Analysis Phase 1 (2009)
Program
FMA-4
of Record
(Objective
Ship type
(POR)
FMA-1
FMA-2
FMA-3
Fleet Mix)
NSC
8
9
9
9
9
OPC
25
32
43
50
57
FRC
58
63
75
80
91
Total
91
104
127
139
157
Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13.
FMA-1 was calculated to address the mission gaps that the Coast Guard judged to be “very high
risk.” FMA-2 was calculated to address both those gaps and additional gaps that the Coast Guard
judged to be “high risk.” FMA-3 was calculated to address all those gaps, plus gaps that the Coast
Guard judged to be “medium risk.” FMA-4—the objective fleet mix—was calculated to address
all the foregoing gaps, plus the remaining gaps, which the Coast Guard judge to be “low risk” or
Congressional Research Service

30

link to page 35 link to page 35 link to page 35 link to page 35 link to page 35 link to page 35 link to page 35 link to page 36 Coast Guard Cutter Procurement: Background and Issues for Congress

“very low risk.” Table A-3 shows the POR and FMAs 1 through 4 in terms of their mission
performance gaps.
Table A-3. Force Mixes and Mission Performance Gaps
From Fleet Mix Analysis Phase 1 (2009)—an X mark indicates a mission performance gap
Risk levels of Program
these
of
FMA-4
Missions with performance
performance
Record
FMA-
(Objective
gaps
gaps
(POR)
1
FMA-2
FMA-3
Fleet Mix)
Search and Rescue (SAR)
Very high
X




capability
Defense Readiness capacity
Very high
X




Counter Drug capacity
Very high
X




Ports, Waterways, and Coastal
High
X
X



Security (PWCS) capacitya
Living Marine Resources (LMR)
High
X
X


[all gaps
capability and capacitya
addressed]
PWCS capacityb
Medium
X
X
X


LMR capacityc
Medium
X
X
X


Alien Migrant Interdiction
Low/very low
X
X
X
X

Operations (AMIO) capacityd
PWCS capacitye
Low/very low
X
X
X
X

Source: Fleet Mix Analysis Phase 1, Executive Summary, page ES-11 through ES-13.
Notes: In the first column, The Coast Guard uses capability as a qualitative term, to refer to the kinds of
missions that can be performed, and capacity as a quantitative term, to refer to how much (i.e., to what scale or
volume) a mission can be performed.
a. This gap occurs in the Southeast operating area (Coast Guard Districts 7 and 8) and the Western operating
area (Districts 11, 13, and 14).
b. This gap occurs in Alaska.
c. This gap occurs in Alaska and in the Northeast operating area (Districts 1 and 5).
d. This gap occurs in the Southeast and Western operating areas.
e. This gap occurs in the Northeast operating area.
Figure A-1, taken from FMA Phase 1, depicts the overall mission capability/performance gap
situation in graphic form. It appears to be conceptual rather than drawn to precise scale. The black
line descending toward 0 by the year 2027 shows the declining capability and performance of the
Coast Guard’s legacy assets as they gradually age out of the force. The purple line branching up
from the black line shows the added capability from ships and aircraft to be procured under the
POR, including the 91 planned NSCs, OPCs, and FRCs. The level of capability to be provided
when the POR force is fully in place is the green line, labeled “2005 Mission Needs Statement.”
As can be seen in the graph, this level of capability is substantially below a projection of Coast
Guard mission demands made after the terrorist attacks of September 11, 2001 (the red line,
labeled “Post-9/11 CG Mission Demands”), and even further below a Coast Guard projection of
future mission demands (the top dashed line, labeled “Future Mission Demands”). The dashed
blue lines show future capability levels that would result from reducing planned procurement
quantities in the POR or executing the POR over a longer time period than originally planned.
Congressional Research Service

31

link to page 34 link to page 34 link to page 37 link to page 37
Coast Guard Cutter Procurement: Background and Issues for Congress

Figure A-1. Projected Mission Demands vs. Projected Capability/Performance
From Fleet Mix Analysis Phase 1, Executive Summary

Source: Fleet Mix Analysis Phase 1, Executive Summary, Figure ES-1 on p. ES-2.
FMA Phase 1 was a fiscally unconstrained study, meaning that the larger force mixes shown in
Table A-2 were calculated primarily on the basis of their capability for performing missions,
rather than their potential acquisition or life-cycle operation and support (O&S) costs.
Although the FMA Phase 1 was completed in December 2009, the figures shown in Table A-2
were generally not included in public discussions of the Coast Guard’s future force structure
needs until April 2011, when GAO presented them in testimony.68 GAO again presented them in a
July 2011 report.69
The Coast Guard completed a follow-on study, called Fleet Mix Analysis (FMA) Phase 2, in May
2011. Among other things, FMA Phase 2 includes a revised and updated objective fleet mix called
the refined objective mix. Table A-4 compares the POR to the objective fleet mix from FMA
Phase 1 and the refined objective mix from FMA Phase 2.
As can be seen in Table A-4, compared to the objective fleet mix from FMA Phase 1, the refined
objective mix from FMA Phase 2 includes 49 OPCs rather than 57. The refined objective mix
includes 58 additional cutters, or about 64% more cutters than in the 2004 POR. Stated the other
way around, the POR includes about 61% as many cutters as the refined objective mix.


68 Government Accountability Office, Coast Guard[:]Observations on Acquisition Management and Efforts to
Reassess the Deepwater Program, Testimony Before the Subcommittee on Coast Guard and Maritime Transportation,
Committee on Transportation and Infrastructure, House of Representatives, Statement of John P. Hutton, Director
Acquisition and Sourcing Management
, GAO-11-535T, April 13, 2011, p. 10.
69 Government Accountability Office, Coast Guard[:]Action Needed As Approved Deepwater Program Remains
Unachievable
, GAO-11-743, July 2011, p. 46.
Congressional Research Service

32

link to page 34 link to page 37 link to page 5 link to page 34 link to page 37 link to page 35 Coast Guard Cutter Procurement: Background and Issues for Congress

Table A-4. POR Compared to Objective Mixes in FMA Phases 1 and 2
From Fleet Mix Analysis Phase 1 (2009) and Phase 2 (2011)
Refined
Objective
Objective
Program of
Fleet Mix
Mix from
Record
from FMA
FMA Phase
Ship type
(POR)
Phase 1
2
NSC
8
9
9
OPC
25
57
49
FRC
58
91
91
Total
91
157
149
Source: Fleet Mix Analysis Phase 1, Executive Summary, Table ES-8 on page ES-13, and Fleet Mix Analysis Phase
2, Table ES-2 on p. iv.
Compared to the POR, the larger force mixes shown in Table A-2 and Table A-4 would be more
expensive to procure, operate, and support than the POR force. Using the average NSC, OPC, and
FRC procurement cost figures presented earlier (see “Background”), procuring the 58 additional
cutters in the Refined Objective Mix from FMA Phase 2 might cost an additional $10.7 billion, of
which most (about $7.8 billion) would be for the 24 additional FRCs. (The actual cost would
depend on numerous factors, such as annual procurement rates.) O&S costs for these 58
additional cutters over their life cycles (including crew costs and periodic ship maintenance costs)
would require billions of additional dollars.70
The larger force mixes in the FMA Phase 1 and 2 studies, moreover, include not only increased
numbers of cutters, but also increased numbers of Coast Guard aircraft. In the FMA Phase 1
study, for example, the objective fleet mix included 479 aircraft—93% more than the 248 aircraft
in the POR mix. Stated the other way around, the POR includes about 52% as many aircraft as the
objective fleet mix. A decision to procure larger numbers of cutters like those shown in Table A-2
and Table A-4 might thus also imply a decision to procure, operate, and support larger numbers
of Coast Guard aircraft, which would require billions of additional dollars. The FMA Phase 1
study estimated the procurement cost of the objective fleet mix of 157 cutters and 479 aircraft at
$61 billion to $67 billion in constant FY2009 dollars, or about 66% more than the procurement
cost of $37 billion to $40 billion in constant FY2009 dollars estimated for the POR mix of 91
cutters and 248 aircraft. The study estimated the total ownership cost (i.e., procurement plus life-
cycle O&S cost) of the objective fleet mix of cutters and aircraft at $201 billion to $208 billion in
constant FY2009 dollars, or about 53% more than the total ownership cost of $132 billion to $136
billion in constant FY2009 dollars estimated for POR mix of cutters and aircraft.71
Potential oversight questions for Congress include the following:
 Under the POR force mix, how large a performance gap, precisely, would there
be in each of the missions shown in Table A-3? What impact would these
performance gaps have on public safety, national security, and protection of
living marine resources?

70 The FMA Phase 1 and Phase 2 studies present acquisition and life-cycle ownership cost calculations for force mixes
that include not only larger numbers of NSC, OPCs, and FRCs, but corresponding larger numbers of Coast Guard
aircraft.
71 Fleet Mix Analysis Phase 1, Executive Summary, Table ES-11 on page ES-19, and Table ES-10 on page ES-18. The
life-cycle O&S cost was calculated through 2050.
Congressional Research Service

33

link to page 35 link to page 35 link to page 35 Coast Guard Cutter Procurement: Background and Issues for Congress

 How sensitive are these performance gaps to the way in which the Coast Guard
translates its statutory missions into more precise statements of required mission
performance?
 Given the performance gaps shown in Table A-3, should planned numbers of
Coast Guard cutters and aircraft be increased, or should the Coast Guard’s
statutory missions be reduced, or both?
 How much larger would the performance gaps in Table A-3 be if planned
numbers of Coast Guard cutters and aircraft are reduced below the POR figures?
 Has the executive branch made sufficiently clear to Congress the difference
between the number of ships and aircraft in the POR force and the number that
would be needed to fully perform the Coast Guard’s statutory missions in coming
years? Why has public discussion of the POR focused mostly on the capability
improvement it would produce over the legacy force and rarely on the
performance gaps it would have in the missions shown in Table A-3?
 What projected mission demands or other factors may have changed since the
Coast Guard’s 2011 Fleet Mix Analysis, and how might these changes affect
future required numbers of Coast Guard cutters and other Coast Guard assets?72

72 For a blog post discussing this issue, see Chuck Hill, “Is Our Fleet Recapitalization on Course? Do We Need to
Change the Destination?” Chuck Hill’s CG Blog, September 8, 2019.
Congressional Research Service

34

Coast Guard Cutter Procurement: Background and Issues for Congress

Appendix B. Requested Funding Levels in PC&I
Account
This appendix provides background information on requested funding levels in the Coast Guard’s
Procurement, Construction, and Improvements (PC&I) account.73
Overview
The Coast Guard has testified that funding the PC&I account at a level of about $1 billion to $1.2
billion per year (the average levels under the FY2014-FY2016 budget submissions) would make
it difficult to fund various Coast Guard acquisition projects, including the PSC program and
improvements to Coast Guard shore installations. Coast Guard plans have called for procuring
OPCs at an eventual rate of two per year. If each OPC costs roughly $400 million, procuring two
OPCs per year in a PC&I account of about $1 billion to $1.2 billion per year, as programmed
under the FY2014-FY2016 budget submissions, would leave about $200 million to $400 million
per year for all other PC&I-funded programs.
Since 2017, Coast Guard officials have been stating more regularly what they stated only
infrequently in earlier years—that executing the Coast Guard’s various acquisition programs fully
and on a timely basis would require the PC&I account to be funded at a level of about $2 billion
per year. Statements from Coast Guard officials on this issue in past years have sometimes put
this figure as high as about $2.5 billion per year.
Using Past PC&I Funding Levels as a Guide for Future PC&I
Funding Levels
In assessing future funding levels for executive branch agencies, a common practice is to assume
or predict that the figure in coming years will likely be close to where it has been in previous
years. While this method can be of analytical and planning value, for an agency like the Coast
Guard, which goes through periods with less acquisition of major platforms and periods with
more acquisition of major platforms, this approach might not always be the best approach, at least
for the PC&I account.
More important, in relation to maintaining Congress’s status as a co-equal branch of government,
including the preservation and use of congressional powers and prerogatives, an analysis that
assumes or predicts that future funding levels will resemble past funding levels can encourage an
artificially narrow view of congressional options regarding future funding levels, depriving
Congress of agency in the exercise of its constitutional power to set funding levels and determine
the composition of federal spending.
Past Coast Guard Statements About Required PC&I Funding Level
At an October 4, 2011, hearing on the Coast Guard’s major acquisition programs before the Coast
Guard and Maritime Transportation subcommittee of the House Transportation and Infrastructure
Committee, the following exchange occurred:
REPRESENATIVE FRANK LOBIONDO:

73 Prior to FY2019, the PC&I account was called the Acquisition, Construction, and Improvements (AC&I) account.
Congressional Research Service

35

Coast Guard Cutter Procurement: Background and Issues for Congress

Can you give us your take on what percentage of value must be invested each year to
maintain current levels of effort and to allow the Coast Guard to fully carry out its
missions?
ADMIRAL ROBERT J. PAPP, COMMANDANT OF THE COAST GUARD:
I think I can, Mr. Chairman. Actually, in discussions and looking at our budget—and I’ll
give you rough numbers here, what we do now is we have to live within the constraints
that we’ve been averaging about $1.4 billion in acquisition money each year.
If you look at our complete portfolio, the things that we’d like to do, when you look at the
shore infrastructure that needs to be taken care of, when you look at renovating our smaller
icebreakers and other ships and aircraft that we have, we’ve done some rough estimates
that it would really take close to about $2.5 billion a year, if we were to do all the things
that we would like to do to sustain our capital plant.
So I’m just like any other head of any other agency here, as that the end of the day, we’re
given a top line and we have to make choices and tradeoffs and basically, my tradeoffs boil
down to sustaining frontline operations balancing that, we’re trying to recapitalize the
Coast Guard and there’s where the break is and where we have to define our spending.74
An April 18, 2012, blog entry stated the following:
If the Coast Guard capital expenditure budget remains unchanged at less than $1.5 billion
annually in the coming years, it will result in a service in possession of only 70 percent of
the assets it possesses today, said Coast Guard Rear Adm. Mark Butt.
Butt, who spoke April 17 [2012] at [a] panel [discussion] during the Navy League Sea Air
Space conference in National Harbor, Md., echoed Coast Guard Commandant Robert Papp
in stating that the service really needs around $2.5 billion annually for procurement.75
At a May 9, 2012, hearing on the Coast Guard’s proposed FY2013 budget before the Homeland
Security subcommittee of the Senate Appropriations Committee, Admiral Papp testified, “I’ve
gone on record saying that I think the Coast Guard needs closer to $2 billion dollars a year [in
acquisition funding] to recapitalize—[to] do proper recapitalization.”76
At a May 14, 2013, hearing on the Coast Guard’s proposed FY2014 budget before the Homeland
Security Subcommittee of the Senate Appropriations Committee, Admiral Papp stated the
following regarding the difference between having about $1.0 billion per year rather than about
$1.5 billion per year in the PC&I account:
Well, Madam Chairman, $500 million—a half a billion dollars—is real money for the
Coast Guard. So, clearly, we had $1.5 billion in the [FY]13 budget. It doesn't get everything

74 Source: Transcript of hearing.
75 David Perera, “The Coast Guard Is Shrinking,” FierceHomelandSecurity.com, April 18, 2012, accessed July 20,
2012, at http://www.fiercehomelandsecurity.com/story/coast-guard-shrinking/2012-04-18.
76 Source: transcript of hearing. Papp may have been referring to remarks he made to the press before giving his annual
state of the Coast Guard speech on February 23, 2012, in which reportedly stated that the Coast Guard would require
about $2 billion per year in acquisition funding to fully replace its current assets. (See Adam Benson, “Coast Guard
Cutbacks Will Cost 1,000 Jobs,” Norwich Bulletin, February 23, 2012, accessed May 31, 2012, at
http://www.norwichbulletin.com/x1138492141/Coast-Guard-cutbacks-will-cost-1-000-jobs. See also “Coast Guard
Leader Calls For More Ships,” MilitaryFeed.com, February 24, 2012, accessed May 31, 2012, at
http://militaryfeed.com/coast-guard-leader-calls-for-more-ships-5/; Associated Press, “Coast Guard Commandant Calls
for New Ships,” TheLog.com, March 10, 2012, accessed May 31, 2012, at http://www.thelog.com/SNW/Article/Coast-
Guard-Commandant-Calls-for-New-Ships-to-Replace-Aging-Fleet; Mickey McCarter, “Congress Poised to Give Coast
Guard More Money Than Requested for FY 2013,” HSToday.us, May 10, 2012, accessed May 31, 2012, at
http://www.hstoday.us/focused-topics/customs-immigration/single-article-page/congress-poised-to-give-coast-guard-
more-money-than-requested-for-fy-2013.html.) See also “Interview, Adm. Robert Papp, US Coast Guard
Commandant,” Defense News, November 11, 2013: 30.
Congressional Research Service

36

Coast Guard Cutter Procurement: Background and Issues for Congress

I would like, but it—it gave us a good start, and it sustained a number of projects that are
very important to us.
When we go down to the $1 billion level this year, it gets my highest priorities in there, but
we have to either terminate or reduce to minimum order quantities for all the other projects
that we have going.
If we're going to stay with our program of record, things that have been documented that
we need for our service, we're going to have to just stretch everything out to the right. And
when we do that, you cannot order in economic order quantities. It defers the purchase.
Ship builders, aircraft companies—they have to figure in their costs, and it inevitably raises
the cost when you're ordering them in smaller quantities and pushing it off to the right.
Plus, it almost creates a death spiral for the Coast Guard because we are forced to sustain
older assets—older ships and older aircraft—which ultimately cost us more money, so it
eats into our operating funds, as well, as we try to sustain these older things.
So, we'll do the best we can within the budget. And the president and the secretary have
addressed my highest priorities, and we'll just continue to go on the—on an annual basis
seeing what we can wedge into the budget to keep the other projects going.77
At a March 12, 2014, hearing on the Coast Guard’s proposed FY2015 budget before the
Homeland Security subcommittee of the House Appropriations Committee, Admiral Papp stated
the following:
Well, that’s what we've been struggling with, as we deal with the five-year plan, the capital
investment plan, is showing how we are able to do that. And it will be a challenge,
particularly if it sticks at around $1 billion [per year]. As I've said publicly, and actually, I
said we could probably—I've stated publicly before that we could probably construct
comfortably at about 1.5 billion [dollars] a year. But if we were to take care of all the Coast
Guard’s projects that are out there, including shore infrastructure that that fleet that takes
care of the Yemen [sic: inland] waters is approaching 50 years of age, as well, but I have
no replacement plan in sight for them because we simply can't afford it. Plus, we need at
some point to build a polar icebreaker. Darn tough to do all that stuff when you're pushing
down closer to 1 billion [dollars per year], instead of 2 billion [dollars per year].
As I said, we could fit most of that in at about the 1.5 billion [dollars per year] level, but
the projections don't call for that. So we are scrubbing the numbers as best we can.78
At a March 24, 2015, hearing on the Coast Guard’s proposed FY2016 budget before the
Homeland Security subcommittee of the House Appropriations Committee, Admiral Paul
Zukunft, Admiral Papp’s successor as Commandant of the Coast Guard, stated the following:
I look back to better years in our acquisition budget when we had a—an acquisition budget
of—of $1.5 billion. That allows me to move these programs along at a much more rapid
pace and, the quicker I can build these at full-rate production, the less cost it is in the long
run as well. But there’s an urgent need for me to be able to deliver these platforms in a
timely and also in an affordable manner. But to at least have a reliable and a predictable
acquisition budget would make our work in the Coast Guard much easier. But when we
see variances of—of 30, 40% over a period of three or four years, and not knowing what
the Budget Control Act may have in store for us going on, yes, we are treading water now
but any further reductions, and now I am—I am beyond asking for help. We are taking on
water.79

77 Transcript of hearing. The remarks were made in response to a question from Sen. Mary Landrieu.
78 Transcript of hearing.
79 Transcript of hearing. The remarks were made in response to a question from Rep. John Culberson.
Congressional Research Service

37

Coast Guard Cutter Procurement: Background and Issues for Congress

An April 13, 2017, press report states the following (emphasis added):
Coast Guard Commandant Adm. Paul Zukunft on Wednesday [April 12] said that for the
Coast Guard to sustain its recapitalization plans and operations the service needs a $2
billion annual acquisition budget that grows modestly overtime to keep pace with inflation.
The Coast Guard needs a “predictable, reliable” acquisition budget “and within that we
need 5 percent annual growth to our operations and maintenance (O&M) accounts,”
Zukunft told reporters at a Defense Writers Group breakfast. Inflation will clip 2 to 3
percent from that, but “at 5 percent or so it puts you on a moderate but positive glide slope
so you can execute, so you can build the force,” he said.80
In an interview published on June 1, 2017, Zukunft said) the following (emphasis added):
We cannot be more relevant than we are now. But what we need is predictable funding.
We have been in over 16 continuing resolutions since 2010. I need stable and repeatable
funding. An acquisition budget with a floor of $2 billion. Our operating expenses as I
said, they’ve been funded below the Budget Control Act floor for the past five years. I need
5 percent annualized growth over the next five years and beyond to start growing some of
this capability back.
But more importantly, we [need] more predictable, more reliable funding so we can execute
what we need to do to carry out the business of the world’s best Coast Guard.81


80 Calvin Biesecker, “Zukunft Wants $2 Billion Baseline Acquisition Budget; Sustained Growth In O&M Funding,”
Defense Daily, April 13, 2017: 1.
81 Jill Aitoro, “Interview: Adm. Paul Zukunft Demands Coast Guard Respect,” Defense News, June 1, 2017.
Congressional Research Service

38

Coast Guard Cutter Procurement: Background and Issues for Congress

Appendix C. Some Considerations Relating to
Warranties in Shipbuilding
This appendix presents some considerations relating to warranties in shipbuilding and other
defense acquisition.82
In discussions of Navy and Coast Guard shipbuilding, one question that sometimes arises is
whether including a warranty in a shipbuilding contract is preferable to not including one.
Including a warranty in a shipbuilding contract (or a contract for building some other kind of
military end item), while potentially valuable, might not always be preferable to not including
one—it depends on the circumstances of the acquisition, and it is not necessarily a valid criticism
of an acquisition program to state that it is using a contract that does not include a warranty (or a
weaker form of a warranty rather than a stronger one).
Including a warranty generally shifts to the contractor the risk of having to pay for fixing
problems with earlier work. Although that in itself could be deemed desirable from the
government’s standpoint, a contractor negotiating a contract that will have a warranty will
incorporate that risk into its price, and depending on how much the contractor might charge for
doing that, it is possible that the government could wind up paying more in total for acquiring the
item (including fixing problems with earlier work on that item) than it would have under a
contract without a warranty.
When a warranty is not included in the contract and the government pays later on to fix problems
with earlier work, those payments can be very visible, which can invite critical comments from
observers. But that does not mean that including a warranty in the contract somehow frees the
government from paying to fix problems with earlier work. In a contract that includes a warranty,
the government will indeed pay something to fix problems with earlier work—but it will make
the payment in the less-visible (but still very real) form of the up-front charge for including the
warranty, and that charge might be more than what it would have cost the government, under a
contract without a warranty, to pay later on for fixing those problems.
From a cost standpoint, including a warranty in the contract might or might not be preferable,
depending on the risk that there will be problems with earlier work that need fixing, the potential
cost of fixing such problems, and the cost of including the warranty in the contract. The point is
that the goal of avoiding highly visible payments for fixing problems with earlier work and the
goal of minimizing the cost to the government of fixing problems with earlier work are separate
and different goals, and that pursuing the first goal can sometimes work against achieving the
second goal.83

82 This appendix is adapted from Appendix C of CRS Testimony TE10019, Options and Considerations for Achieving
a 355-Ship Navy
, by Ronald O'Rourke.
83 It can also be noted that the country’s two largest builders of Navy ships—General Dynamics (GD) and Huntington
Ingalls Industries (HII)—derive about 60% and 96%, respectively, of their revenues from U.S. government work. (See
General Dynamics, 2016 Annual Report, page 9 of Form 10-K [PDF page 15 of 88]) and Huntington Ingalls Industries,
2016 Annual Report, page 5 of Form 10-K [PDF page 19 of 134]). These two shipbuilders operate the only U.S.
shipyards currently capable of building several major types of Navy ships, including submarines, aircraft carriers, large
surface combatants, and amphibious ships. Thus, even if a warranty in a shipbuilding contract with one of these firms
were to somehow mean that the government did not have pay under the terms of that contract—either up front or later
on—for fixing problems with earlier work done under that contract, there would still be a question as to whether the
government would nevertheless wind up eventually paying much of that cost as part of the price of one or more future
contracts the government may have that firm.
Congressional Research Service

39

Coast Guard Cutter Procurement: Background and Issues for Congress

The Department of Defense’s guide on the use of warranties states the following:
Federal Acquisition Regulation (FAR) 46.7 states that “the use of warranties is not
mandatory.” However, if the benefits to be derived from the warranty are commensurate
with the cost of the warranty, the CO [contracting officer] should consider placing it in the
contract. In determining whether a warranty is appropriate for a specific acquisition, FAR
Subpart 46.703 requires the CO to consider the nature and use of the supplies and services,
the cost, the administration and enforcement, trade practices, and reduced requirements.
The rationale for using a warranty should be documented in the contract file....
In determining the value of a warranty, a CBA [cost-benefit analysis] is used to measure
the life cycle costs of the system with and without the warranty. A CBA is required to
determine if the warranty will be cost beneficial. CBA is an economic analysis, which
basically compares the Life Cycle Costs (LCC) of the system with and without the warranty
to determine if warranty coverage will improve the LCCs. In general, five key factors will
drive the results of the CBA: cost of the warranty + cost of warranty administration +
compatibility with total program efforts + cost of overlap with Contractor support +
intangible
savings.
Effective
warranties
integrate
reliability,
maintainability,
supportability, availability, and life-cycle costs. Decision factors that must be evaluated
include the state of the weapon system technology, the size of the warranted population,
the likelihood that field performance requirements can be achieved, and the warranty
period of performance.84

84 Department of Defense, Department of Defense Warranty Guide, Version 1.0, September 2009, accessed July 13,
2017, at https://www.acq.osd.mil/dpap/pdi/uid/docs/departmentofdefensewarrantyguide[1].doc.
Congressional Research Service

40

Coast Guard Cutter Procurement: Background and Issues for Congress

Appendix D. Impact of Hurricane Michael on OPC
Program at Eastern Shipbuilding
This appendix provides additional background information of the impact of Hurricane Michael on
the OPC program at Eastern Shipbuilding Group (ESG).
An August 22, 2019, press released from Eastern Shipbuilding states
On August 16th, 2019 Eastern Shipbuilding Group, a Panama City, Florida shipyard
building both government and commercial vessels, successfully delivered the tug Capt. Jim
McAllister. This is the fifth vessel to be delivered by the shipyard since Hurricane Michael,
a category 5 storm—which devastated the region. This delivery marks another milestone
in Eastern’s accelerated return to normal operations, as well as its commitment to long term
sustained recovery and economic stability for the industrial base of the Florida Panhandle.
Other shipbuilding projects include three Staten Island Ferries, the Coast Guard Offshore
Patrol Cutters, a large commercial fishing trawler, two harbor tugs, and two river
pushboats. Eastern is actively bidding other projects and is poised to maintain its position
as the go to shipyard on the US Gulf. All of these projects support skilled manufacturing
jobs for Northwest Florida and over twenty five other states where Eastern buys material,
equipment, and specialized services.
Since the hurricane, Eastern has repaired or replaced all of its impacted equipment,
buildings, and shipbuilding infrastructure as part of a major company-funded
recapitalization effort. Additionally, Eastern has invested in new technology aimed at
increasing shipbuilding efficiency. Eastern has also partnered with State and local
Governmental agencies to plan additional investments of over $45 Million towards
enhancing shipbuilding efficiency and capacity in both Bay and Gulf Counties in order to
ensure long term stability and growth of the shipbuilding industry in Northwest Florida.
As part of its recovery and growth from a once-in-a-generation storm, Eastern is actively
recruiting and hiring additional personnel to join its team and support its long term
commitment to building the best vessels for its government and commercial customers.
Eastern remains grateful for the unwavering Federal, State, and local support during this
recovery—empowering a devastated area by providing manufacturing and industrial
employment opportunities.85
A July 31, 2019, press report states
A bill needed to continue a long-awaited multi-billion-dollar Coast Guard shipbuilding
project in Panama City sailed through a U.S. Senate committee on Wednesday [July 31].
The bill, which received bipartisan support in the Senate Committee on Commerce,
Science and Transportation, would let the Coast Guard renegotiate its $10.5 billion contract
with Eastern Shipbuilding Group to account for higher labor costs and shortages caused by
Hurricane Michael. The bill should help the project get back on track after the hurricane to
create hundreds of new jobs that are needed more than ever as the area still recovers from
the Category 5 storm, some officials say.
According to a Wednesday news release, the committee approved U.S. Sen. Marco Rubio’s
Restore Coast Guard Capabilities Act [S. 2319] as part of the Coast Guard Reauthorization
Act of 2019. Rubio’s bill would give the Coast Guard the authority to renegotiate the
contract with Eastern Shipbuilding to construct the first series of up to 25 offshore patrol

85 Eastern Shipbuilding, “Eastern Shipbuilding Group, Inc. Successfully Delivers Fifth Vessel Since Hurricane
Michael,” August 22, 2019.
Congressional Research Service

41

Coast Guard Cutter Procurement: Background and Issues for Congress

cutters. Without a way to renegotiate the contract, the project could be delayed by years,
Rubio’s office warned.
The Coast Guard requested the authority to renegotiate, while not exceeding the original
affordability requirement set forth by the government in the existing contract, because of
skyrocketing labor costs caused by the hurricane.
The historic storm, which hit the Panhandle on Oct. 10, significantly damaged Tyndall Air
Force Base. The press release states that the labor needed to rebuild the base is competing
directly with the labor required to fulfill Eastern Shipbuilding’s contract.86
A May 22, 2019, press report states
A Category 5 hurricane that battered Florida’s panhandle region last fall, including
shipbuilder Eastern Shipbuilding Group, will impact the new medium-endurance cutter
ship the company is building for the Coast Guard but at the moment it’s unclear what the

86 Patrick McCreless, “Bill Passes Committee to Renogotiate Panama City Coast Guard Shipbuilding Contract,”
Panama City News Herald, July 31, 2019. The press release mentioned in the article, dated July 31, 2019, states
Today, U.S. Senator Marco Rubio (R-FL) applauded the Senate Committee on Commerce, Science,
and Transportation’s approval of his Restore Coast Guard Capabilities Act (S.2319) as part of the
Coast Guard Reauthorization Act of 2019 (S. 2297). Rubio’s bill would give the U.S. Coast Guard
the authority to take into account the impacts of Hurricane Michael to modify its Offshore Patrol
Cutter (OPC) contract with Panama City-based Eastern Shipbuilding.
On October 10, 2018, Hurricane Michael wreaked havoc in Northwest Florida, and made history as
one of only four category 5 hurricanes to make landfall on the U.S. mainland. The Coast Guard has
requested this authority that would provide much needed flexibility to modify the OPC contract,
while not exceeding the original affordability requirement set forth by the government in the
existing contract, as a result of skyrocketing labor costs due to Hurricane Michael. The Coast
Guard maintains that acquisition of the OPC is its highest investment priority.
“Continuing authorizations for the Coast Guard to protect Florida’s waterways and our nation’s
homeland security is imperative,” Rubio said. “I applaud the Senate Commerce Committee on
approving this larger reauthorization, which includes several of my joint priorities that are critical
to the Coast Guard’s mission readiness. As a result of my partnership with Senator Scott, the bill
now includes our Restore Coast Guard Capabilities Act, which will ensure the Coast Guard has the
tools necessary to safeguard the Offshore Patrol Cutter even after the devastation caused by
Hurricane Michael.”
Today, the Senate Committee on Commerce, Science and Transportation approved the Coast Guard
Reauthorization Act of 2019 (S. 2297), which included several Rubio priorities:
 The Restore Coast Guard Capabilities Act (S. 2319), adopted as an amendment offered by
Senator Scott
 Section 426: Coast Guard Shore Infrastructure Improvement Act
 Section 221: Continuation of Coast Guard pay during lapse in appropriations. Senator Rubio is
a cosponsor of the Pay Our Coast Guard Act (S. 21)
Background:
Eastern Shipbuilding is under contract with the Coast Guard to deliver up to 25 OPCs, the Coast
Guard’s highest priority investment program. However, Hurricane Michael significantly damaged
Tyndall Air Force Base and the labor needed to rebuild the base is competing directly with the
labor to fulfill the OPC contract. As a result, the Coast Guard has requested authorization from
Congress to potentially revisit the contract to take into account the increased labor costs associated
with the category 5 hurricane.
(“Rubio Applauds Commerce Committee Passage of the Restore Coast Guard Capabilities Act to
Build Offshore Patrol Cutters,” July 31, 2019, accessed September 10, 2019, at
https://www.rubio.senate.gov/public/index.cfm/press-releases?ID=52E5D8E4-2559-4F67-AFBD-
D70EE38FC7A5.)
Congressional Research Service

42

Coast Guard Cutter Procurement: Background and Issues for Congress

effects will be on cost and schedule, Coast Guard Commandant Adm. Karl Schultz said on
Tuesday [May 21].
Eastern Shipbuilding’s analysis of Hurricane Michael’s impact on the Offshore Patrol
Cutter (OPC) is due to the Coast Guard by May 31, and from there the service expects to
have an understanding on the way forward with the program before the end of June, Schultz
said in response to questions from Rep. Garret Graves (R-La.), during a hearing hosted by
the House Transportation and Infrastructure Coast Guard and Maritime Transportation
Subcommittee. He said Eastern Shipbuilding will provide “perspectives” on the cost and
schedule and any other impacts.
“It’s safe to say that we understand the impacts of a Category 5 hurricane on Eastern
Shipbuilding Group will have an impact on the OPC program,” Shultz said. He expects
there to be some “puts and takes” after Eastern Shipbuilding submits its analysis.
Rep. Peter DeFazio (D-Ore.), citing a press report earlier in the hearing, said that Sen.
Marco Rubio (R-Fla.) has inserted language in a draft disaster assistance bill allowing the
Coast Guard and Eastern Shipbuilding to renegotiate the firm fixed-price contract the
shipbuilder is working under for the OPC to account for damage to shore side facilities
from Hurricane Michael and increased labor costs.
DeFazio said he is skeptical of the company’s claim, noting, “I’m pretty sure they had
insurance,” and adding that “I question whether or not this has something to do with their
original bid, which some thought was low.” He also said he has concerns that a former
Coast Guard Commandant that works for Eastern Shipbuilding has said he’ll have authority
to negotiate with his former service.
Retired Adm. Robert Papp, the 24th commandant of the Coast Guard, runs Eastern
Shipbuilding’s Washington, D.C., operations.
Eastern Shipbuilding did not respond to a query from Defense Daily about impacts to the
OPC program from Hurricane Michael and any relief it may need from the current contract.
Schultz said that the OPC contract can’t be renegotiated without legislative authorities from
Congress. He said the Coast Guard, in response to an “ask” from Congress, provided
language to help with drafting the proposed legislation related to the OPC in the disaster
bill.
Schultz also said that the Coast Guard is not involved in Eastern Shipbuilding’s lobbying
efforts with Congress.87
A May 17, 2019, press report stated
As the Senate continues to negotiate the particulars of the supplemental disaster relief bill
that seems poised to go to a vote next week, a new provision to save something many likely
didn’t know was at risk has been added.
A new line in the draft bill will let Eastern Shipbuilding Group renegotiate its contract with
the U.S. Coast Guard to build up to 25 new off-shore patrol cutters.
“Under the old contract we were prohibited from negotiating for additional money for
increased costs,” said Admiral Bob Papp, President of Washington Operations for Eastern.
That meant that after Hurricane Michael, they would be unable to negotiate with the Coast
Guard to help cover a slew of new costs associated with both the project and the hurricane,
such as the damage from the Category 5 storm that needed repairs, the prolonged schedule

87 Calvin Biesecker, “Coast Guard Expects Impact To OPC Program From Hurricane Michael, Commandant Says,”
Defense Daily, May 22, 2019.
Congressional Research Service

43

Coast Guard Cutter Procurement: Background and Issues for Congress

and the “skyrocketing” costs of labor, Papp said. The contract—the largest in the Coast
Guard’s history at more than $10 billion—didn’t account for a natural disaster.
It was going to be hard, Papp said, for Eastern to complete the project and to “stay healthy”
without some negotiations. At stake in the community are 900 planned jobs and up to 5,000
indirect jobs officials believe will help jump-start the region’s manufacturing economy.
But an official in Sen. Marco Rubio’s office said the latest version of the supplemental
disaster relief bill now includes a provision that will allow negotiations.
Rubio, according to the official, spoke with the President Donald Trump on Air Force One
following the president’s rally in Panama City Beach last week, helping to secure the
language that made it into the bill.
“We’ve waited far too long (for disaster relief), and we’re also involved in some Florida-
specific issues,” Rubio said in a recent video. “For example, the Hurricane had an impact
on a very important Coast Guard project that’s in Northwest Florida and we want to make
sure that project stays on target and continues to feed jobs because Northwest Florida
desperately needs those jobs to recover. We’re very hopeful. Cautiously optimistic, that
next week can be a very good week.”
Papp thanked the area’s congressional delegation for stepping up to advocate for this
project, saying the company is “honored and delighted” to receive help.88
A January 28, 2019, press release from Eastern Shipbuilding stated
Panama City, FL, Eastern Shipbuilding Group [ESG] reports that steel cutting for the first
offshore patrol cutter (OPC), Coast Guard Cutter ARGUS (WMSM-915), commenced on
January 7, 2019 at Eastern’s facilities. ESG successfully achieved this milestone even with
sustaining damage and work interruption due to Hurricane Michael. The cutting of steel
will start the fabrication and assembly of the cutter’s hull, and ESG is to complete keel
laying of ARGUS later this year. Additionally, ESG completed the placement of orders for
all long lead time materials for OPC #2, Coast Guard Cutter CHASE (WMSM-916).
Eastern’s President Mr. Joey D’Isernia noted the following: “Today represents a
monumental day and reflects the dedication of our workforce - the ability to overcome and
perform even under the most strenuous circumstances and impacts of Hurricane Michael.
ESG families have been dramatically impacted by the storm, and we continue to recover
and help rebuild our shipyard and community. I cannot overstate enough how appreciative
we are of all of our subcontractors and vendors contributions to our families during the
recovery as well as the support we have received from our community partners. Hurricane
Michael may have left its marks but it only strengthened our resolve to build the most
sophisticated, highly capable national assets for the Coast Guard. Today’s success is just
the beginning of the construction of the OPCs at ESG by our dedicated team of shipbuilders
and subcontractors for our customer and partner, the United States Coast Guard. We are
excited for what will be a great 2019 for Eastern Shipbuilding Group and Bay County,
Florida.”89
A November 1, 2018, statement from Eastern Shipbuilding states that the firm
resumed operations at both of its two main shipbuilding facilities just two weeks after
Hurricane Michael devastated Panama City Florida and the surrounding communities….
… the majority of ESG’s [Eastern Shipbuilding Group’s] workforce has returned to work
very quickly despite the damage caused by the storm. “Our employees are a resourceful

88 Katie Landeck, “Provision Added to Disaster Relief Bill to Help Eastern Shipbuilding,” Panama City News Herald,
May 17, 2019.
89 Eastern Shipbuilding press release entitled “Eastern Shipbuilding Group Announces Commencement of Steel Cutting
for USCGC ARGUS (WMSM-915),” January 28, 2019, p. 1.
Congressional Research Service

44

Coast Guard Cutter Procurement: Background and Issues for Congress

and resilient group of individuals with the drive to succeed in the face of adversity. This
has certainly been proven by their ability to bounce back over the two weeks following the
storm. Our employees have returned to work much faster than anticipated and brought with
them an unbreakable spirit, that I believe sets this shipyard and our community apart” said
[Eastern Shipbuilding] President Joey D’Isernia. “Today, our staffing levels exceed 80%
of our pre-Hurricane Michael levels and is rising daily.”
Immediately following the storm, ESG set out on an aggressive initiative to locate all of its
employees and help get them back on the job as soon as practical after they took necessary
time to secure the safety and security of their family and home. Together with its network
of friends, partners, and customers in the maritime community, ESG organized daily
distribution of meals and goods to employees in need. Additionally, ESG created an interest
free deferred payback loan program for those employees in need and has organized Go
Fund Me account to help those employees hardest hit by the storm. ESG also knew
temporary housing was going to be a necessity in the short term and immediately built a
small community located on greenfield space near its facilities for those employees with
temporary housing needs.
ESG has worked closely with its federal, state and commercial partners over the past two
weeks to provide updates on the shipyard as well as on projects currently under
construction. Power was restored to ESG’s Nelson Facility on 10-21-18 and at ESG’s
Allanton Facility on 10-24-18 and production of vessels under contract is ramping back
up. Additionally, all of the ESG personnel currently working on the US Coast Guard’s
Offshore Patrol Cutter contract have returned to work….
“We are grateful to our partners and the maritime business community as a whole for their
support and confidence during the aftermath of this historic storm. Seeing our incredible
employees get back to building ships last week was an inspiration,” said D’Isernia. “While
there is no doubt that the effects of Hurricane Michael will linger with our community for
years to come, I can say without reservation that we are open for business and excited about
delivering quality vessels to our loyal customers.”90
An October 22, 2018, press report states the following:
U.S. Coast Guard officials and Eastern Shipbuilding Group are still assessing the damage
caused by deadly category 4 Hurricane Michael to the Panama City, Fla.-based yard
contracted to build the new class of Offshore Patrol Cutters.
On September 28, the Coast Guard awarded Eastern Shipbuilding a contract to build the
future USCGC Argus (WMSM-915), the first offshore patrol cutter (OPC). The yard was
also set to build a second OPC, the future USCGC Chase (WMSM-916). Eastern
Shipbuilding’s contract is for nine OPCs, with options for two additional cutters.
Ultimately, the Coast Guard plans to buy 25 OPCs.
However, just as the yard was preparing to build Argus, Hurricane Michael struck the
Florida Panhandle near Panama City on October 10. Workers from the shipyard and Coast
Guard project managers evacuated and are just now returning to assess damage to the yard
facilities, Brian Olexy, communications manager for the Coast Guard’s Acquisitions
Directorate, told USNI News.
“Right now we haven’t made any decisions yet on shifts in schedule,” Olexy said….
Since the yard was just the beginning stages of building Argus, Olexy said the hull wasn’t
damaged. “No steel had been cut,” he said.

90 Eastern Shipbuilding news release, November 1, 2018, entitled “Eastern Shipbuilding Group, Inc. Resumes
Operations.”
Congressional Research Service

45

Coast Guard Cutter Procurement: Background and Issues for Congress

Eastern Shipbuilding is still in the process of assessing damage to the yard and trying to
reach its workforce. Many employees evacuated the area and have not returned, or are in
the area but lost their homes, Eastern Shipbuilding spokesman Justin Smith told USNI
News.
At first, about 200 workers returned to work, but by week’s end about 500 were at the yard,
Smith said. The company is providing meals, water, and ice for its workforce.
“Although we were significantly impacted by this catastrophic weather event, we are
making great strides each day thanks to the strength and resiliency of our employees,” Joey
D’Isernia, president of Eastern Shipbuilding, said in a statement.91

91 Ben Werner, “Coast Guard, Shipbuilder Assessing Hurricane Damage to Yard Building Offshore Patrol Cutter,”
USNI News, October 22, 2018. See also Paul McLeary, “Hurricane Michael Hits Coast Guard’s Largest Program,
Leaving Devastation,” Breaking Defense, October 18, 2018; Marex, “Despite Hurricane Michael, Eastern Shipbuilding
Keeps Working,” Maritime Executive, October 16, 2018; Samuel Hill, “Eastern Shipbuilding Hit Hard by Hurricane
Michael,” Workboat, October 16, 2018; Kris Osborn, “How One Shipyard Survived a Hurricane and Built a New Coast
Guard Cutter,” National Interest, January 7, 2021.
Congressional Research Service

46

Coast Guard Cutter Procurement: Background and Issues for Congress

Appendix E. November 25, 2019, House Committee
Letter Regarding OPC Program
This appendix presents text from a November 25, 2019, letter to the Acting Secretary of DHS
from the Chair and Ranking Member of the House Transportation and Infrastructure Committee
and the Chair and Ranking Member of that committee’s Coast Guard and Maritime
Transportation subcommittee regarding the OPC program. The letter states in part
The Committee on Transportation and Infrastructure has reviewed your proposal to provide
extraordinary relief under Public Law 85-804 as requested by Eastern Shipbuilding Group
(ESG) for the construction of the Offshore Patrol Cutter (OPC). We are skeptical that such
truly extraordinary relief is justified given that this “crisis” was foreseeable and mostly
avoidable. Further, we are concerned that this relief sets a damaging precedent that any
current or future contract with the United States Coast Guard (Coast Guard or Service)
could be renegotiated outside the Federal Acquisition Regulations.
As you know, the Coast Guard is in the middle of a rnulti-decade, multi-billion-dollar
recapitalization of its cutter fleets. Last fall, the Service entered into a fixed price contract
with ESG for the largest single acquisition in its history for the OPC. Shortly after entering
into that contract, on October 10, 2018, Hurricane Michael hit the ESG shipyard and
devastated the surrounding Panama City, Florida area where much of the shipyard
workforce lived. The shipyard claims the impacts of the disaster rendered its facilities and
workforce incapable of meeting the terms of the contract. The Department of Homeland
Security (DHS) and the Service now propose to expand the timeframes for the delivery of
each of the first four OPCs, spend up to an additional $659 million to complete those
cutters, and then re-compete the contract earlier than previously planned. The decision to
proceed with the current contractor raises a number of concerns for the Committee.
Foremost among those concerns being the delay in delivering the cutters as well as the use
of the Public Law No. 85-804 authority, which ultimately eliminates the Coast Guard’s
claim of getting the best value through a firm, fixed-price contract. If that were a priority
for the Service, it would make more sense to pivot to a contractor who had competed for
the original contract and is positioned to execute on it rather than create continued
uncertainty around the OPC.
For more than a decade, the Committee has tracked the widening capability gap between
the existing legacy fleet of Medium Endurance Cutters (MECs)—several built during the
Vietnam War—and the commissioning of new OPCs. During that time, the Committee has
repeatedly urged the Coast Guard to undertake a ship life extension program (SLEP) for
the MECs and advocated for the Service to look at alternative methods to acquire new
mission capabilities. Due to limited funding provided for the Coast Guard’s Procurement,
Construction and Improvements account, the Service made the decision to defer initiating
an MEC SLEP to partially offset the loss of MEC capability as those cutters aged out.
Rather than heeding the Committee’s caution, the Service decided to prioritize construction
of the OPCs at the earliest possible time to allow the Coast Guard to continue to effectively
carry out its law enforcement, drug and migrant interdiction, and search and rescue
missions.
The Service then compounded the risks of this “all-or-nothing” strategy by entering into a
contract with ESG; a company that has never built a ship for the Federal government and
whose bid came in at a per-vessel price far below that of other qualified bidders. This action
led many observers to question whether the Coast Guard was taking too great a risk, but
the Service believed, nonetheless, that the risk was acceptable.
Regrettably, ESG began lobbying lawmakers for “relief” from the contract barely six
months after agreeing to its terms. Within nine months, ESG formally notified the Coast
Congressional Research Service

47

Coast Guard Cutter Procurement: Background and Issues for Congress

Guard that they could no longer meet the contractual schedule or deliver the OPC at the
contract price.
In all, it appears the Coast Guard’s initial failure to adequately examine the risks of using
a shipyard with no government shipbuilding experience could be perpetuated by DHS
granting this extraordinary relief under Public Law No, 85-804. The Committee is
concerned that the Coast Guard, along with DHS, embarked on exploring options to
resuscitate ESG and prevent it from defaulting on the OPC contract without first
completing a transparent and objective alternatives analysis. Additionally, the veil of
secrecy regarding its analysis and the absence of any meaningful consultation by the Coast
Guard and DHS with the Committee, provides us scant confidence that any revised OPC
contract will not encounter a similar fate as the original contract.
Accordingly, the Committee would like to know:
 Why did the Coast Guard fail to stop construction on hull #1 as soon as they learned
the contractor was informing lawmakers that it would be unable to meet the terms of
the contract?
 What interim measures are available to mitigate the lost mission capabilities while the
OPC contract is being delayed and recompeted?
 Is the Coast Guard considering the use of leased barges to support helicopter
operations, the acquisition of additional National Security Cutters or Fast Response
Cutters, or other available options?
 What national security missions will be carried out by each of the four OPCs for which
relief is sought?
 What is the status of the ship life extension program for the 270B MECs?
Regarding a revised OPC contract, the Committee would like to know?
 Has the Department requested authority from Congress to expedite the re-compete of
the OPC contract?
 How will the Coast Guard ensure that no additional extraordinary relief will be needed
beyond the potential upward limit of $659 million and the proposed schedule
extensions?
 Are the federal/non-federal share lines for each of the first four OPCs set in the DHS
decision granting limited Public Law No. 85-804 extraordinary relief, and if not, what
are these share lines and what is their justification request?
 In which fiscal years will it be necessary to request funds above the amounts projected
for the OPCs in the Coast Guard’s latest Capital Improvement Plan? In what amounts?
 On what ship design will the re-compete be based?
 Can you confirm that the Coast Guard owns the OPC design?
 How many additional construction hours above the amount on which the initial bid
was based are now anticipated for each of hulls #1-4?
 What controls will be instituted to ensure that there is no excessive overage in
production hours?
 What conditions do the Coast Guard intend to include in a revised contract to ensure
transparency in all financial transactions; accountability with all performance metrics
and timetables for deliverables; certification and notification standards and protocols
before the Coast Guard or DHS exercises an option on hulls #2-4?
Congressional Research Service

48

Coast Guard Cutter Procurement: Background and Issues for Congress

 Given the fact that the contractor is unable to perform under the terms of the original
contract, will any effort be made to receive the performance bond associated with the
contract?
The Committee will continue to investigate these issues and closely monitor this situation.
We are concerned about the impacts any further delays of this contract will have on the
Service’s ability to carry out its critical mission responsibilities and the overall impact the
escalated cost of producing these assets will have on the Coast Guard’s Procurement,
Construction and Improvements account for the foreseeable future. As we begin
negotiations with the Senate on the Coast Guard Authorization Act of 2019, we will
examine if further legislation is necessary to protect U.S. taxpayers from profligate, unwise
spending, notwithstanding the urgent need to provide the Coast Guard with the modern
assets it needs to remain the world’s preeminent Coast Guard.92


Author Information

Ronald O'Rourke

Specialist in Naval Affairs



Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.


92 The letter was accessed November 27, 2019, at https://transportation.house.gov/imo/media/doc/2019-11-
25%20DHS%2085-804%20Big%204%20Letter.pdf.
Congressional Research Service
R42567 · VERSION 147 · UPDATED
49