

 
Navy Ford (CVN-78) Class Aircraft Carrier 
Program: Background and Issues for Congress 
Updated December 28, 2021 
Congressional Research Service 
https://crsreports.congress.gov 
RS20643 
 
  
 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Summary 
The aircraft carriers CVN-78, CVN-79, CVN-80, and CVN-81 are the first four ships in the 
Navy’s new Gerald R. Ford (CVN-78) class of nuclear-powered aircraft carriers (CVNs). The 
Navy’s proposed FY2022 budget requests $2,659.5 million (i.e., about $2.7 billion) in 
procurement funding for CVN-78 class ships, including $291.0 million for CVN-79, $1,068.7 
million for CVN-80, and $1,299.8 million for CVN-81. 
CVN-78 (Gerald R. Ford) was procured in FY2008. The Navy’s proposed FY2022 budget 
estimates the ship’s procurement cost at $13,316.5 million (i.e., about $13.3 billion) in then-year 
dollars. The ship was commissioned into service on July 22, 2017. The Navy is currently working 
to complete construction, testing, and certification of the ship’s 11 weapons elevators. 
CVN-79 (John F. Kennedy) was procured in FY2013. The Navy’s proposed FY2022 budget 
estimates the ship’s procurement cost at $11,929.7 million (i.e., about $11.9 billion) in then-year 
dollars. The ship is being built with an improved shipyard fabrication and assembly process that 
incorporates lessons learned from the construction of CVN-78. CVN-79 is scheduled for delivery 
to the Navy in June 2024. 
CVN-80 (Enterprise) was procured in FY2018. The Navy’s proposed FY2022 budget estimates 
the ship’s procurement cost at $12,405.5 million (i.e., about $12.4 billion) in then-year dollars. 
The ship is scheduled for delivery to the Navy in March 2028. 
CVN-81 (Doris Miller) is treated in this report as a ship that was procured in FY2019, consistent 
with congressional action on the Navy’s FY2019 budget. The Navy’s FY2022 budget 
submission, like its FY2021 submission, shows CVN-81 as a ship that was procured in FY2020. 
The Navy’s FY2022 budget submission estimates the ship’s procurement cost at $12,483.6 
million (i.e., about $12.5 billion) in then-year dollars. The ship is scheduled for delivery to the 
Navy in February 2032. 
CVN-80 and CVN-81 are being procured under a two-ship block buy contract that was authorized 
by Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (H.R. 5515/P.L. 115-232 of August 13, 2018). The use of the two-ship block buy contract 
reduced the combined estimated procurement cost of the two ships. Oversight issues for Congress 
for the CVN-78 program include the following: 
  the future aircraft carrier force level; 
  the procurement of aircraft carriers after CVN-81; 
  a delay in CVN-78’s first deployment due to the need to complete work on the 
ship’s weapons elevators and correct other technical problems aboard the ship; 
  the transfer of parts intended for CVN-79 to CVN-78; 
  the potential impact of the COVID-19 pandemic on the execution of U.S. 
military shipbuilding programs, including the CVN-78 program; 
  cost growth in the CVN-78 program, Navy efforts to stem that growth, and Navy 
efforts to manage costs so as to stay within the program’s cost caps; and 
  additional CVN-78 program issues that were raised in a January 2021 report from 
the Department of Defense’s (DOD’s) Director of Operational Test and 
Evaluation (DOT&E) and a June 2020 Government Accountability Office (GAO) 
report on DOD weapon systems. 
Congressional Research Service 
 link to page 5  link to page 5  link to page 5  link to page 5  link to page 5  link to page 6  link to page 6  link to page 6  link to page 6  link to page 7  link to page 7  link to page 7  link to page 7  link to page 7  link to page 8  link to page 8  link to page 8  link to page 8  link to page 10  link to page 11  link to page 11  link to page 11  link to page 11  link to page 12  link to page 12  link to page 13  link to page 15  link to page 15  link to page 15  link to page 17  link to page 17  link to page 18  link to page 20  link to page 20  link to page 21  link to page 23  link to page 23  link to page 24  link to page 25  link to page 25  link to page 26  link to page 26  link to page 29  link to page 29  link to page 33  link to page 34 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Contents 
Introduction ..................................................................................................................................... 1 
Background ..................................................................................................................................... 1 
Current Navy Aircraft Carrier Force ......................................................................................... 1 
Statutory Requirements for Numbers of Carriers and Carrier Air Wings ................................. 1 
Requirement to Maintain Not Less Than 11 Carriers ......................................................... 1 
Prohibition on Retiring Nuclear-Powered Aircraft Carriers Prior to Refueling .................. 2 
Requirement to Maintain a Minimum of Nine Carrier Air Wings ...................................... 2 
Navy Force-Level Goal ............................................................................................................. 2 
Current 12-Carrier Force-Level Goal within 355-Ship Plan of December 2016 ................ 2 
December 9, 2020, Document Presented Potential New Goal of 8 to 11 Large 
Carriers and 0 to 6 Light Carriers .................................................................................... 3 
June 17, 2021, Document Presents Potential New Goal of 9 to 11 Aircraft 
Carriers ............................................................................................................................ 3 
Comparison of Aircraft Carrier Force-Level Goals ............................................................ 3 
Incremental Funding Authority for Aircraft Carriers ................................................................ 4 
Aircraft Carrier Construction Industrial Base ........................................................................... 4 
Gerald R. Ford (CVN-78) Class Program ................................................................................ 4 
Overview ............................................................................................................................. 4 
CVN-78 (Gerald R. Ford) ................................................................................................... 6 
CVN-79 (John F. Kennedy) ................................................................................................ 7 
CVN-80 (Enterprise) ........................................................................................................... 7 
CVN-81 (Doris Miller) ....................................................................................................... 7 
Two-Ship Block Buy Contract for CVN-80 and CVN-81 .................................................. 7 
Program Procurement Cost Cap .......................................................................................... 8 
Program Procurement Funding ........................................................................................... 8 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget .............................. 9 
Issues for Congress for FY2022 ..................................................................................................... 11 
Future Aircraft Carrier Force Level ......................................................................................... 11 
Procurement of Aircraft Carriers After CVN-81 ...................................................................... 11 
Delay in CVN-78’s Deployment Due to Weapon Elevators and Other Challenges ................ 13 
Overview ........................................................................................................................... 13 
Weapons Elevators ............................................................................................................ 14 
Other Technical Challenges .............................................................................................. 16 
Change in Program Manager ............................................................................................ 16 
Navy Efforts to Address Technical Challenges ................................................................. 17 
Potential Oversight Questions ........................................................................................... 19 
Transfer of Parts Intended for CVN-79 to CVN-78 ................................................................ 19 
Potential Impact of COVID-19 Pandemic .............................................................................. 20 
Cost Growth and Managing Costs within Program Cost Caps ............................................... 21 
Overview ........................................................................................................................... 21 
CVN-78 ............................................................................................................................. 22 
CVNs 79, 80, and 81 ......................................................................................................... 22 
Issues Raised in DOT&E and GAO Reports .......................................................................... 25 
January 2021 DOT&E Report .......................................................................................... 25 
June 2021 GAO Report ..................................................................................................... 29 
Legislative Activity for FY2022 .................................................................................................... 30 
Congressional Research Service 
 link to page 34  link to page 35  link to page 35  link to page 35  link to page 37  link to page 38  link to page 38  link to page 38  link to page 9  link to page 9  link to page 10  link to page 7  link to page 13  link to page 14  link to page 35  link to page 39  link to page 43 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Summary of Congressional Action on FY2022 Funding Request .......................................... 30 
FY2022 National Defense Authorization Act (H.R. 4350/S. 2792/S. 1605) ........................... 31 
House ................................................................................................................................ 31 
Senate ................................................................................................................................ 31 
HASC-SASC-Negotiated Proposal ................................................................................... 33 
FY2022 DOD Appropriations Act (H.R. 4432/S. XXXX) ...................................................... 34 
House ................................................................................................................................ 34 
Senate ................................................................................................................................ 34 
 
Figures 
Figure 1. USS Gerald R. Ford (CVN-78) ....................................................................................... 5 
Figure 2. USS Gerald R. Ford (CVN-78) ....................................................................................... 5 
Figure 3. USS Gerald R. Ford (CVN-78) ....................................................................................... 6 
  
Tables 
Table 1. Current and Potential Aircraft Carrier Force-Level Goals ................................................. 3 
Table 2. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2028.............................. 9 
Table 3. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 .......................... 10 
Table 4. Congressional Action on FY2022 Procurement Funding Request .................................. 31 
  
Appendixes 
Appendix. Background Information on Two-Ship Block Buy for CVN-80 and CVN-81 ............ 35 
 
Contacts 
Author Information ........................................................................................................................ 39 
 
Congressional Research Service 
 link to page 5 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Introduction 
This report provides background information and potential oversight issues for Congress on the 
Gerald R. Ford (CVN-78) class nuclear-powered aircraft carrier (CVN) aircraft carrier program. 
The Navy’s proposed FY2022 budget requests $2,659.5 million (i.e., about $2.7 billion) in 
procurement funding for the program. Congress’s decisions on the CVN-78 program could 
substantially affect Navy capabilities and funding requirements and the shipbuilding industrial 
base. 
Background 
Current Navy Aircraft Carrier Force 
The Navy’s current aircraft carrier force consists of 11 CVNs,1 including 10 Nimitz-class ships 
(CVNs 68 through 77) that entered service between 1975 and 2009, and one Gerald R. Ford 
(CVN-78) class ship that was commissioned into service on July 22, 2017.2  
Statutory Requirements for Numbers of Carriers and 
Carrier Air Wings 
Requirement to Maintain Not Less Than 11 Carriers 
10 U.S.C. 8062(b) requires the Navy to maintain a force of not less than 11 operational aircraft 
carriers.3 The requirement for the Navy to maintain not less than a certain number of operational 
aircraft carriers was established by Section 126 of the FY2006 National Defense Authorization 
Act (H.R. 1815/P.L. 109-163 of January 6, 2006), which set the number at 12 carriers. The 
requirement was changed from 12 carriers to 11 carriers by Section 1011(a) of the FY2007 John 
Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006).4 
                                                 
1 The Navy’s last remaining conventionally powered carrier (CV), Kitty Hawk (CV-63), was decommissioned on 
January 31, 2009. 
2 The commissioning into service of CVN-78 on July 22, 2017, ended a period during which the carrier force had 
declined to 10 ships—a period that began on December 1, 2012, with the inactivation of the one-of-a-kind nuclear-
powered aircraft carrier Enterprise (CVN-65), a ship that entered service in 1961. 
3 10 U.S.C. 8062 was previously numbered as 10 U.S.C. 5062. It was renumbered as 10 U.S.C. 8062 by Section 807 of 
the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-232 of August 13, 
2018), which directed a renumbering of sections and titles of Title 10 relating to the Navy and Marine Corps. (Sections 
806 and 808 of P.L. 115-232 directed a similar renumbering of sections and titles relating to the Air Force and Army, 
respectively.) 
4 As mentioned in footnote 2, the carrier force dropped from 11 ships to 10 ships between December 1, 2012, when 
Enterprise (CVN-65) was inactivated, and July 22, 2017, when CVN-78 was commissioned into service. Anticipating 
the gap between the inactivation of CVN-65 and the commissioning of CVN-78, the Navy asked Congress for a 
temporary waiver of 10 U.S.C. 8062(b) to accommodate the period between the two events. Section 1023 of the 
FY2010 National Defense Authorization Act (H.R. 2647/P.L. 111-84 of October 28, 2009) authorized the waiver, 
permitting the Navy to have 10 operational carriers between the inactivation of CVN-65 and the commissioning of 
CVN-78. 
Congressional Research Service  
 
1 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Prohibition on Retiring Nuclear-Powered Aircraft Carriers Prior to Refueling 
Section 1054 of the FY2021 National Defense Authorization Act (NDAA) (H.R. 6395/P.L. 116-
283) amended 10 U.S.C. 8062 to create a new subsection (f) stating: “ A nuclear powered aircraft 
carrier may not be retired before its first refueling.’’ 
Requirement to Maintain a Minimum of Nine Carrier Air Wings 
10 U.S.C. 8062(e), which was added by Section 1042 of the FY2017 National Defense 
Authorization Act (S. 2943/P.L. 114-328 of December 23, 2016), requires the Navy to maintain a 
minimum of nine carrier air wings.5 
Navy Force-Level Goal 
Current 12-Carrier Force-Level Goal within 355-Ship Plan of December 2016 
In December 2016, the Navy released a force-level goal for achieving and maintaining a fleet of 
355 ships, including 12 aircraft carriers6—one more than the minimum of 11 carriers required by 
10 U.S.C. 8062(b). 
Given the time needed to build a carrier and the projected retirement dates of existing carriers, 
increasing the carrier force from 11 ships to 12 ships on a sustained basis would take a number of 
years.7 Under the Navy’s FY2020 30-year shipbuilding plan, carrier procurement would shift 
from five-year centers (i.e., one carrier procured each five years) to four-year centers after the 
procurement of CVN-82 in FY2028, and a 12-carrier force would be achieved on a sustained 
basis in the 2060s.8 
                                                 
5 10 U.S.C. 8062(e) states the following: 
The Secretary of the Navy shall ensure that- 
(1) the Navy maintains a minimum of 9 carrier air wings until the earlier of- 
(A) the date on which additional operationally deployable aircraft carriers can fully support a 10th 
carrier air wing; or 
(B) October 1, 2025; 
(2) after the earlier of the two dates referred to in subparagraphs (A) and (B) of paragraph (1), the 
Navy maintains a minimum of 10 carrier air wings; and 
(3) for each such carrier air wing, the Navy maintains a dedicated and fully staffed headquarters. 
6 For more on the 355-ship force-level goal, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: 
Background and Issues for Congress, by Ronald O'Rourke.  
7 Procuring carriers on three-year centers would achieve a 12-carrier force on a sustained basis by about 2030, unless 
the service lives of one or more existing carriers were substantially extended. Procuring carriers on 3.5-year centers 
(i.e., a combination of three- and four-year centers) would achieve a 12-carrier force on a sustained basis no earlier than 
about 2034, unless the service lives of one or more existing carriers were substantially extended. Procuring carriers on 
four-year centers would achieve a 12-carrier force on a sustained basis by about 2063—almost 30 years later than under 
3.5-year centers—unless the service lives of one or more existing carriers were substantially extended. (Source for 
2063 date in relation to four-year centers: Congressional Budget Office (CBO), in a telephone consultation with CRS 
on May 18, 2017.) 
8 The projected size of the carrier force in the Navy’s FY2020 30-year (FY2020-FY2049) shipbuilding plan reflected 
the Navy’s now-withdrawn FY2020 budget proposal to not fund the RCOH for the aircraft carrier CVN-75 (Harry S. 
Truman), and to instead retire the ship around FY2024. With the withdrawal of this budget proposal, the projected size 
of the carrier force became, for the period FY2022-FY2047, one ship higher than what is shown in the Navy’s FY2020 
budget submission. The newly adjusted force-level projection, reflecting the withdrawal of the proposal to retire CVN-
75 around FY2024, were as follows: The force is projected to include 11 ships in FY2020-FY2021, 12 ships in 
Congressional Research Service  
 
2 
 link to page 7 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The Navy and the Department of Defense (DOD) since 2019 have been working to develop a new 
Navy force-level goal to replace the current 355-ship force-level goal. 
December 9, 2020, Document Presented Potential New Goal of 8 to 11 Large 
Carriers and 0 to 6 Light Carriers 
On December 9, 2020, the Trump Administration released a long-range Navy shipbuilding 
document that called for a Navy with a more distributed fleet architecture, including 382 to 446 
manned ships and 143 to 242 large surface and underwater unmanned vehicles (UVs). Within the 
total of 382 to 446 manned ships, the document called for a total of 8 to 11 CVNs and 0 to 6 
smaller aircraft carriers called light aircraft carriers (CVLs). The Navy does not currently operate 
CVLs. 
June 17, 2021, Document Presents Potential New Goal of 9 to 11 Aircraft 
Carriers 
On June 17, 2021, the Biden Administration released a long-range Navy shipbuilding document 
that calls for a Navy with a more distributed fleet architecture, including 321 to 372 manned ships 
and 77 to 140 large surface and underwater UVs. Within the total of 321 to 372 manned ships, the 
document calls for a total of 9 to 11 aircraft carriers. The document states: “New capability 
concepts like a light aircraft carrier continue to be studied and analyzed to fully illuminate their 
potential to execute key mission elements in a more distributed manner and to inform the best 
mix of a future force.”9 
Comparison of Aircraft Carrier Force-Level Goals 
Table 1 compares the current aircraft carrier force-level goal within the 355-ship plan to the 
potential aircraft carrier force-level goals from the June 17, 2021, and December 9, 2020, long-
range Navy shipbuilding documents. 
Table 1. Current and Potential Aircraft Carrier Force-Level Goals 
Current force-
December 9, 
June 17, 2021, 
level goal within 
2020, shipbuilding 
shipbuilding 
 
355-ship plan  
document 
document 
Aircraft carriers 
12 
n/a a 
9 to 11 
Large aircraft carriers (CVNs 
12 
8 to 11a 
n/a 
Light aircraft carriers (CVLs) 
0 
0 to 6 b 
n/ac 
Source: Table prepared by CRS based on U.S. Navy data. n/a means not available. 
a.  The document states: “Lower [end of the CVN] range may be enabled by acquisition of cost-effective CVL.” 
b.  The document states: “Further study of cost-effective CVL capabilities and capacity required.” 
                                                 
FY2022-FY2024, 11 ships in FY2025-FY2026, 10 ships in FY2027, 11 ships in FY2028-FY2039, 10 ships in FY2040, 
11 ships in FY2041, 10 ships in FY2042-FY2044, 11 ships in FY2045, 10 ships in FY2046-FY2047, 9 ships in 
FY2048, and 10 ships in FY2049. 
9 U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year 
2022, June 2021, p. 4. 
Congressional Research Service  
 
3 
 link to page 9  link to page 9  link to page 35  link to page 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
c.  The document states: “New capability concepts like a light aircraft carrier continue to be studied and 
analyzed to fully illuminate their potential to execute key mission elements in a more distributed manner 
and to inform the best mix of a future force.” 
Incremental Funding Authority for Aircraft Carriers 
In recent years, Congress has authorized DOD to use incremental funding for procuring certain 
Navy ships, most notably aircraft carriers.10 Under incremental funding, some of the funding 
needed to fully fund a ship is provided in one or more years after the year in which the ship is 
procured.11 
Aircraft Carrier Construction Industrial Base 
All U.S. aircraft carriers procured since FY1958 have been built by Huntington Ingalls 
Industries/Newport News Shipbuilding (HII/NNS), of Newport News, VA. HII/NNS is the only 
U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The aircraft carrier 
construction industrial base also includes roughly 2,000 supplier firms in 46 states.12 
Gerald R. Ford (CVN-78) Class Program 
Overview 
The Gerald R. Ford (CVN-78) class carrier design (Figure 1, Figure 2, and Table 4) is the 
successor to the Nimitz-class carrier design. The Ford-class design uses the basic Nimitz-class hull 
form but incorporates several improvements, including features permitting the ship to generate 
more aircraft sorties per day, more electrical power for supporting ship systems, and features 
permitting the ship to be operated by several hundred fewer sailors than a Nimitz-class ship, 
reducing 50-year life-cycle operating and support (O&S) costs for each ship by about $4 billion 
                                                 
10 The provisions providing authority for using incremental funding for procuring CVN-78 class carriers are as follows: 
Section 121 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 
2006) granted the Navy the authority to use four-year incremental funding for CVNs 78, 79, and 80. Under this 
authority, the Navy could fully fund each of these ships over a four-year period that includes the ship’s year of 
procurement and three subsequent years. 
Section 124 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 112-81 of December 31, 2011) 
amended Section 121 of P.L. 109-364 to grant the Navy the authority to use five-year incremental funding for CVNs 
78, 79, and 80. Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice originally applied to 
CVNs 79 and 80, although as discussed in the footnote to Table 2, the Navy made use of the authority in connection 
with an FY2020 reprogramming action that reprogrammed $86.0 million of funding into FY2012 for CVN-78. 
Section 121 of the FY2013 National Defense Authorization Act (H.R. 4310/P.L. 112-239 of January 2, 2013) amended 
Section 121 of P.L. 109-364 to grant the Navy the authority to use six-year incremental funding for CVNs 78, 79, and 
80. Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice applies to CVNs 79 and 80. 
Section 121(c) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-
232 of August 13, 2018) authorized incremental funding to be used for making payments under the two-ship block buy 
contract for the construction of CVN-80 and CVN-81. This provision does not limit the total number of years across 
which incremental funding may be used to procure either ship. 
11 For more on full funding and incremental funding, see CRS Report RL31404, Defense Procurement: Full Funding 
Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report 
RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by 
Ronald O'Rourke. 
12 Source for figures of 2,000 supplier firms in 46 states: Jennifer Boykin, president of HII/NNS, as quoted in Marcus 
Weisgerber, “US Navy Places First 2-Carrier Order in Three Decades,” Defense One, January 31, 2019. 
Congressional Research Service  
 
4 


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
compared to the Nimitz-class design, the Navy estimates. Navy plans call for procuring at least 
four Ford-class carriers—CVN-78, CVN-79, CVN-80, and CVN-81. 
Figure 1. USS Gerald R. Ford (CVN-78) 
 
Source: Cropped version of U.S. Navy photograph 170408-N-WZ792-198, showing CVN-78 on April 8, 2017. 
Accessed March 17, 2021, at https://www.navy.mil/Resources/Photo-Gallery/igphoto/2001728935/. 
Figure 2. USS Gerald R. Ford (CVN-78) 
 
Source: U.S. Navy photograph 200515-N-QI093-1151, showing CVN-78 on May 15, 2020, with the oiler USNS 
Patuxent (T-AO 201) alongside. Accessed March 17, 2021, at https://allhands.navy.mil/Media/Gallery/igphoto/
2002340124/. 
Congressional Research Service  
 
5 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Figure 3. USS Gerald R. Ford (CVN-78) 
 
Source: Cropped version of photograph accompanying Megan Eckstein, “Navy Removes Ford Carrier Program 
Manager, Citing Performance Over Time,” USNI News, July 2, 2020. The caption credits the photograph to the 
U.S. Navy and states that it shows CVN-78 on June 4, 2020. 
CVN-78 (Gerald R. Ford) 
CVN-78, which was named Gerald R. Ford in 2007,13 was procured in FY2008. The Navy’s 
proposed FY2022 budget estimates the ship’s procurement cost at $13,316.5 million (i.e., about 
$13.3 billion) in then-year dollars. The ship was commissioned into service on July 22, 2017. The 
Navy is currently working to complete construction, testing, and certification of the ship’s 11 
weapons elevators. 
                                                 
13 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of 
Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced that 
CVN-78 would be so named. CVN-78 and other carriers built to the same design are consequently referred to as Ford 
(CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for 
Congress, by Ronald O'Rourke. 
Congressional Research Service  
 
6 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
CVN-79 (John F. Kennedy) 
CVN-79, which was named John F. Kennedy on May 29, 2011,14 was procured in FY2013. The 
Navy’s proposed FY2022 budget estimates the ship’s procurement cost at $11,929.7 million (i.e., 
about $11.9 billion) in then-year dollars. The ship is being built with an improved shipyard 
fabrication and assembly process that incorporates lessons learned from the construction of CVN-
78. CVN-79 is scheduled for delivery to the Navy in June 2024. 
CVN-80 (Enterprise) 
CVN-80, which was named Enterprise on December 1, 2012,15 was procured in FY2018. The 
Navy’s proposed FY2022 budget estimates the ship’s procurement cost at $12,405.5 million (i.e., 
about $12.4 billion) in then-year dollars. The ship is scheduled for delivery to the Navy in March 
2028. 
CVN-81 (Doris Miller) 
CVN-81, which was named Doris Miller on January 20, 2020,16 is treated in this report as a ship 
that was procured in FY2019, consistent with congressional action on the Navy’s FY2019 budget. 
The Navy’s FY2022 budget submission, like its FY2021 submission, shows CVN-81 as a ship 
that was procured in FY2020. The Navy’s FY2022 budget submission estimates the ship’s 
procurement cost at $12,483.6 million (i.e., about $12.5 billion) in then-year dollars. The ship is 
scheduled for delivery to the Navy in February 2032. 
Two-Ship Block Buy Contract for CVN-80 and CVN-81 
CVN-80 and CVN-81 are being procured under a two-ship block buy contract that was authorized 
by Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (H.R. 5515/P.L. 115-232 of August 13, 2018). The provision permitted the Navy to add 
CVN-81 to the existing contract for building CVN-80 after DOD made certain certifications to 
Congress. DOD made the certifications on December 31, 2018, and the Navy announced the 
award of the contract on January 31, 2019. Prior to the awarding of the two-ship block buy 
contract, CVN-81 was scheduled to be procured in FY2023. 
Compared to the estimated procurement costs for CVN-80 and CVN-81 in the Navy’s FY2019 
budget submission, the Navy estimated under its FY2020 budget submission that the two-ship 
block buy contract will reduce the cost of CVN-80 by $246.6 million and the cost of CVN-81 by 
                                                 
14 See “Navy Names Next Aircraft Carrier USS John F. Kennedy,” Navy News Service, May 29, 2011, accessed online 
on June 1, 2011, at http://www.navy.mil/search/display.asp?story_id=60686. See also Peter Frost, “U.S. Navy’s Next 
Aircraft Carrier Will Be Named After The Late John F. Kennedy,” Newport News Daily Press, May 30, 2011. CVN-79 
is the second ship to be named for President John F. Kennedy. The first, CV-67, was the last conventionally powered 
carrier procured for the Navy. CV-67 was procured in FY1963, entered service in 1968, and was decommissioned in 
2007. 
15 The Navy made the announcement of CVN-80’s name on the same day that it deactivated the 51-year-old aircraft 
carrier CVN-65, also named Enterprise. (“Enterprise, Navy’s First Nuclear-Powered Aircraft Carrier, Inactivated,” 
Navy News Service, December 1, 2012; Hugh Lessig, “Navy Retires One Enterprise, Will Welcome Another,” Newport 
News Daily Press, December 2, 2012.) CVN-65 was the eighth Navy ship named Enterprise; CVN-80 is to be the 
ninth. 
16 Doris Miller was an African American enlisted sailor who received the Navy Cross for his actions during the 
Japanese attack on Pearl Harbor on December 7, 1941. For further discussion of the naming of CVN-81 for Doris 
Miller, see CRS Report RS22478, Navy Ship Names: Background for Congress, by Ronald O'Rourke. 
Congressional Research Service  
 
7 
 link to page 39  link to page 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
$2,637.3 million, for a combined reduction of $2,883.9 million (i.e., about $2.9 billion).17 (DOD 
characterized the combined reduction as “nearly $3 billion.”18) Using higher estimated baseline 
costs for CVN-80 and CVN-81 taken from a December 2017 Navy business case analysis, the 
Navy estimated under its FY2020 budget submission that the two-ship contract will reduce the 
cost of CVN-80 by about $900 million and the cost of CVN-81 by about $3.1 billion, for a 
combined reduction of about $4.0 billion.19 These figures are all expressed in then-year dollars, 
meaning dollars that are not adjusted for inflation. For additional background information on the 
two-ship block buy contract, see the Appendix. 
Program Procurement Cost Cap 
Congress has established and subsequently amended procurement cost caps for CVN-78 class 
aircraft carriers.20 
Program Procurement Funding 
Table 2 shows procurement funding for CVNs 78, 79, 80, and 81 through FY2028, the final year 
of funding programmed for CVN-81, under the Navy’s FY2022 budget submission. As shown in 
the table, the Navy’s proposed FY2022 budget requests $2,659.5 million (i.e., about $2.7 billion) 
in procurement funding for CVN-78 class ships, including $291.0 million for CVN-79, $1,068.7 
million for CVN-80, and $1,299.8 million for CVN-81. 
                                                 
17 Source: CRS calculation based on costs for single-ship purchases as presented in Navy’s FY2019 budget submission 
and costs for two-ship purchase as presented in the Navy’s FY2020 budget submission. 
18 Source: Navy information paper on estimated cost savings of two-ship carrier buy provided to CRS by Navy Office 
of Legislative Affairs on June 20, 2019. 
19 Navy information paper provided to CRS by Navy Office of legislative Affairs on June 20, 2019. 
20 The provisions that established and later amended the cost caps are as follows: 
Section 122 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 
2006) established a procurement cost cap for CVN-78 of $10.5 billion, plus adjustments for inflation and other factors, 
and a procurement cost cap for subsequent Ford-class carriers of $8.1 billion each, plus adjustments for inflation and 
other factors. The conference report (H.Rept. 109-702 of September 29, 2006) on P.L. 109-364 discusses Section 122 
on pages 551-552. 
Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 113-66 of December 26, 2013) 
amended the procurement cost cap for the CVN-78 program to provide a revised cap of $12,887.0 million for CVN-78 
and a revised cap of $11,498.0 million for each follow-on ship in the program, plus adjustments for inflation and other 
factors (including an additional factor not included in original cost cap). 
Section 122 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015) further 
amended the cost cap for the CVN-78 program to provide a revised cap of $11,398.0 million for each follow-on ship in 
the program, plus adjustment for inflation and other factors, and with a new provision stating that, if during 
construction of CVN-79, the Chief of Naval Operations determines that measures required to complete the ship within 
the revised cost cap shall result in an unacceptable reduction to the ship’s operational capability, the Secretary of the 
Navy may increase the CVN-79 cost cap by up to $100 million (i.e., to $11.498 billion). If such an action is taken, the 
Navy is to adhere to the notification requirements specified in the cost cap legislation. 
Section 121(a) of the FY2018 National Defense Authorization Act (H.R. 2810/P.L. 115-91 of December 12, 2017) 
further amended the cost cap for the CVN-78 program to provide a revised cap of $12,568.0 million for CVN-80 and 
subsequent ships in the program, plus adjustment for inflation and other factors. (The cap for CVN-79 was kept at 
$11,398.0 million, plus adjustment for inflation and other factors.) The provision also amended the basis for adjusting 
the caps for inflation, and excluded certain costs from being counted against the caps. 
Section 121 of the FY2020 National Defense Authorization Act (S. 1790/P.L. 116-92 of December 20, 2019) further 
amended the cost cap for the CVN-78 program to provide revised caps of $13,224.0 million for CVN-78, $11,398.0 
million for CVN–79, $12,202.0 million for CVN–80, and $12,451.0 million for CVN–81. The provision directs the 
Navy to exclude from these figures costs for CVN–78 class battle spares, interim spares, and increases attributable to 
economic inflation after December 1, 2018. 
Congressional Research Service  
 
8 
 link to page 8  link to page 14 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 2. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2028 
(Millions of then-year dollars, rounded to nearest tenth) 
FY 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
Total 
FY01 
21.7 (AP) 
0 
0 
0 
21.7 
FY02 
135.3 (AP) 
0 
0 
0 
135.3 
FY03 
395.5 (AP) 
0 
0 
0 
395.5 
FY04 
1,162.9 (AP) 
0 
0 
0 
1,162.9 
FY05 
623.1 (AP) 
0 
0 
0 
623.1 
FY06 
618.9 (AP) 
0 
0 
0 
618.9 
FY07 
735.8 (AP) 
52.8 (AP) 
0 
0 
788.6 
FY08 
2,685.0 (FF) 
123.5 (AP) 
0 
0 
2,808.5 
FY09 
2,687.0 (FF) 
1,210.6 (AP) 
0 
0 
3,897.6 
FY10 
851.3 (FF) 
482.9 (AP) 
0 
0 
1,334.2 
FY11  
1,848.1 (FF) 
902.5 (AP) 
0 
0 
2,750.6 
FY12  
86.0 (FF)* 
554.8 (AP) 
0 
0 
640.8 
FY13 
0 
491.0 (FF) 
0 
0 
491.0 
FY14  
588.1 (CC) 
917.6 (FF) 
0 
0 
1,505.7 
FY15 
663.0 (CC) 
1,219.4 (FF) 
0 
0 
1,882.4 
FY16 
123.8 (CC) 
1,569.5 (FF) 
862.4 (AP) 
0 
2,555.7 
FY17  
0 
1,241.8 (FF) 
1,370.8 (AP) 
0 
2,612.6 
FY18 
20.0 (CC) 
2,556.4 (FF) 
1,569.6 (FF) 
0 
4,146.0 
FY19 
0 
0 
929.1 (FF) 
643.0 (FF) 
1,572.1 
FY20 
0 
0 
1,062.0 (FF) 
1,214.5 (FF) 
2,276.5 
FY21 
71.0 (CC) 
0 
958.9 (FF) 
1,606.4 (FF) 
2,636.3 
FY22 (requested) 
0 
291.0 (CC) 
1,068.7 (FF) 
1,299.8 (FF) 
2,659.5 
FY23 (programmed) 
0 
172.9 (CC) 
1,188.6 (FF) 
731.4 (FF) 
2,092.9 
FY24 (programmed) 
0 
143.1 (CC) 
1,053.5 (FF) 
637.5 (FF) 
1,834.1 
FY25 (programmed) 
0 
0 
2,341.9 (FF) 
566.4 (FF) 
2,908.3 
FY26 (projected) 
0 
0 
0 
2,087.2 (FF) 
2,087.2 
FY27 (projected) 
0 
0 
0 
2,026.8 (FF) 
2,026.8 
FY28 (projected) 
0 
0 
0 
1,670.7 (FF) 
1,670.7 
Total 
13,316.5 
11,929.7 
12,405.5 
12,483.6 
50,135.3 
Source: Table prepared by CRS based on Navy’s FY2022 budget submission. 
Notes: Figures may not add due to rounding. “AP” is advance procurement funding; “FF” is full funding; “CC” is 
cost-to-complete funding (i.e., funding to cover cost growth), which is sometimes abbreviated in Navy 
documents as CTC. Regarding the * notation for the FY2012 funding figure for CVN-78, even though FY2012 is 
after FY2011 (CVN-78’s original final year of full funding), the Navy characterizes the $86.0 million 
reprogrammed into FY2012 as full funding rather than cost-to-complete funding on the grounds that in the years 
since FY2011, as discussed earlier in this report (see footnote 10), the authority to use incremental funding for 
procuring aircraft carriers has been expanded by Congress to permit more than the four years of incremental 
funding that were permitted at the time that CVN-78 was initially funded. 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget 
Table 3 shows changes in the estimated procurement costs of CVNs 78, 79, 80, and 81 since the 
budget submission for FY2008—the year of procurement for CVN-78. 
Congressional Research Service  
 
9 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 3. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 
(As shown in FY2008-FY2020 budgets, in millions of then-year dollars) 
Budget 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
Est. 
Est. 
Est. 
Schedule
Est. 
proc. 
Scheduled 
proc. 
Scheduled 
proc. 
d FY of 
proc. 
Scheduled 
 
cost 
FY of proc. 
cost 
FY of proc. 
cost 
proc. 
cost 
FY of proc. 
FY08 
10,488.9 
FY08 
9,192.0 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY09 
10,457.9 
FY08 
9,191.6 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY10 
10,845.8 
FY08 
n/a 
FY13 
n/a 
FY18 
n/a 
FY23 
FY11 
11,531.0 
FY08 
10,413.1 
FY13 
13,577.0 
FY18 
n/a 
FY23 
FY12 
11,531.0 
FY08 
10,253.0 
FY13 
13,494.9 
FY18 
n/a 
FY23 
FY13 
12,323.2 
FY08 
11,411.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY14 
12,829.3 
FY08 
11,338.4 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY15 
12,887.2 
FY08 
11,498.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY16 
12,887.0 
FY08 
11,347.6 
FY13 
13,472.0 
FY18 
n/a 
FY23 
FY17 
12,887.0 
FY08 
11,398.0 
FY13 
12,900.0 
FY18 
n/a 
FY23 
FY18 
12,907.0 
FY08 
11,377.4 
FY13 
12,997.6 
FY18 
n/a 
FY23 
FY19 
12,964.0 
FY08 
11,341.4 
FY13 
12,601.7 
FY18 
15,088.0 
FY23 
FY20 
13,084.0 
FY08 
11,327.4 
FY13 
12,335.1 
FY18 
12,450.7 
FY19 
FY21 
13,316.5 
FY08 
11,397.7 
FY13 
12,321.3 
FY18 
12,450.7 
FY19 
FY22 
13,316.5 
FY08 
11,929.7 
FY13 
12,405.5 
FY18 
12,483.6 
FY19 
Annual % change 
FY08 to FY09 
-0.3 
 
0% 
 
0% 
 
n/a 
 
FY09 to FY10 
+3.7 
 
n/a 
 
n/a 
 
n/a 
 
FY10 to FY11 
+6.3 
 
n/a 
 
n/a 
 
n/a 
 
FY09 to FY11 
 
 
 
 
+26.7% 
 
 
 
FY11 to FY12 
0% 
 
-1.5% 
 
-0.1% 
 
n/a 
 
FY12 to FY13 
+6.9% 
 
+11.3% 
 
+2.8% 
 
n/a 
 
FY13 to FY14 
+4.1% 
 
-0.6% 
 
0% 
 
n/a 
 
FY14 to FY15 
+0.5% 
 
+1.4% 
 
0% 
 
n/a 
 
FY15 to FY16 
0% 
 
-1.3% 
 
-2.9% 
 
n/a 
 
FY16 to FY17 
0% 
 
+0.4% 
 
-4.2% 
 
n/a 
 
FY17 to FY18 
+0.2% 
 
-0.2% 
 
+0.7% 
 
n/a 
 
FY18 to FY19 
+0.4% 
 
-0.3% 
 
-3.0% 
 
n/a 
 
FY19 to FY20 
+0.9% 
 
-0.1% 
 
-2.1% 
 
-17.5% 
 
FY20 to FY21 
+1.8% 
 
+0.6% 
 
-0.1% 
 
0% 
 
FY21 to FY22 
0% 
 
+4.7% 
 
+0.7% 
 
+0.3% 
 
Cumulative % change through FY22 
Since FY08 
+27.0% 
 
+29.8% 
 
+15.8% 
 
n/a 
 
Since FY13 
+8.1% 
 
+4.5% 
 
-10.6% 
 
n/a 
 
Since FY18 
+3.2% 
 
+4.9% 
 
-4.6% 
 
n/a 
 
Since FY19 
+2.7% 
 
+5.2% 
 
-1.6% 
 
-17.3% 
 
Source: Table prepared by CRS based on FY2008-FY2022 Navy budget submissions. n/a means not available. 
Notes: The FY2010 budget submission did not show estimated procurement costs or scheduled years of 
procurement for CVNs 79 and 80. The scheduled years of procurement for CVNs 79 and 80 shown here for the 
FY2010 budget submission are inferred from the shift to five-year intervals for procuring carriers that was 
announced by Secretary of Defense Gates in his April 6, 2009, news conference regarding recommendations for 
the FY2010 defense budget. 
Congressional Research Service  
 
10 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Issues for Congress for FY2022 
Future Aircraft Carrier Force Level 
One issue for Congress concerns the future aircraft carrier force level. Decisions on this issue 
could have implications for the service lives of existing aircraft carriers and/or plans for procuring 
new aircraft carriers. The future aircraft carrier force level has been a frequent matter of 
discussion over the years, and (correctly or not) is often the starting point or the center of broader 
discussions over the future size and composition of the Navy. Factors involved in discussions 
about the future aircraft carrier force level include but are not limited to the following: 
  the capabilities and costs (including procurement costs and life-cycle operation 
and support [O&S] costs) of aircraft carriers and their embarked air wings, and 
how those capabilities and costs compare to those of other U.S. military forces; 
  the prospective survivability of aircraft carriers in conflicts against adversaries 
(such as China) with highly capable anti-ship missiles; 
  the numbers of carriers needed to support policymaker-desired levels of day-to-
day aircraft carrier forward presence in various regions around the world; and 
  the utility of carriers for purposes other than high-end combat, including 
deterrence of potential regional adversaries, reassurance of allies and partners, 
signaling U.S. commitment and resolve, and noncombat operations such as 
humanitarian assistance/disaster response (HA/DR) operations. 
As discussed earlier, the December 9, 2020, long-range Navy shipbuilding document submitted 
by the Trump Administration called for a future fleet with 8 to 11 CVNs and 0 to 6 light aircraft 
carriers (CVLs), and the June 17, 2021, long-range Navy shipbuilding document calls for a future 
fleet with 9 to 11 aircraft carriers. An aircraft carrier force-level goal that includes fewer than 11 
CVNs could lead to Navy proposals for one or more of the following: 
  accelerated retirements for one or more Nimitz-class carriers that have already 
received their mid-life nuclear refueling overhauls (which are called Refueling 
Complex Overhauls, or RCOHs); 
  the cancellation of one or more planned RCOHs for Nimitz-class carriers that 
have not yet received RCOHs, and the consequent early retirement of one or 
more of these ships; 
  a deferral or cancellation of the procurement of CVN-82, which under the Navy’s 
FY2020 30-year shipbuilding plan was scheduled for FY2028; and/or 
  the deferral or cancellation of the construction of CVN-81, which could require 
modifying the current two-ship construction contract for CVN-80 and CVN-81. 
Procurement of Aircraft Carriers After CVN-81 
A related issue for Congress concerns the procurement of aircraft carriers after CVN-81. The 
question of whether the Navy should shift at some point from procuring CVNs like the CVN-78 
class to procuring smaller and perhaps nonnuclear-powered aircraft carriers has been a recurrent 
matter of discussion and Navy study over the years, and is currently an active discussion in the 
Navy. 
Congressional Research Service  
 
11 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The Navy’s FY2020 30-year shipbuilding plan called for procuring the next carrier in FY2028 
and for that carrier to be a CVN, which would make it CVN-82. The December 9, 2020, long-
range Navy shipbuilding document called for procuring the next aircraft carrier in FY2028. The 
June 17, 2021, long-range Navy shipbuilding document does not include projected procurements 
of aircraft carriers (or any other Navy ship type) for FY2023 or subsequent years. 
As mentioned earlier, the Navy does not currently operate CVLs. As discussed in another CRS 
report, however, the Navy in recent years has experimented with the concept of using an LHA-
type amphibious assault ship with an embarked group of F-35B Joint Strike Fighters as a CVL.21 
A February 1, 2021, press report states 
The Navy’s engineering community has already started conducting light carrier design and 
engineering studies, even as the Navy and the joint force still consider whether they’d even 
want to invest in a CVL to supplement supercarriers to bring more distributed capability to 
the fleet for less cost. 
The idea of a light carrier resurfaced last summer as a Pentagon-led Future Naval Force 
Study was nearing its completion. The idea hadn’t appeared in Navy and Marine Corps 
plans,  but  then-Defense  Secretary  Mark  Esper  had  a  growing  interest  in  the  topic  as he 
sought  ways to  keep  future shipbuilding  and  sustainment  costs down and  as he worried 
about the Navy’s ability to conduct maintenance on its nuclear-powered aircraft carriers at 
Navy-run public shipyards. 
The FNFS and the plan it produced, Battle Force 2045, ultimately recommended between 
zero and six light carriers and noted much more study would need to be done. 
That work is already happening at Naval Sea Systems Command within the engineering 
and logistics directorate (SEA 05). 
Rear Adm. Jason Lloyd, the SEA 05 commander and deputy commander for ship design, 
integration  and  engineering,  said  last  week  that  his  Cost  Engineering  and  Industrial 
Analysis team has been studying different options to understand what operational utility 
the Navy would get out of each design and for what cost compared to the Ford-class carrier, 
“and then let the operators really, and the Navy, decide, hey, do we want that capability for 
that cost?” 
“We have looked at an America-class possibility,22 we have looked at a Ford-class-light,23 
we’ve looked at various different options and done cost studies on all those options. There 
are also capabilities studies on all those options,” Lloyd said last week while speaking at a 
virtual event hosted by the American Society of Naval Engineers.24 
Advocates of smaller carriers traditionally have argued that they are individually less expensive 
to procure, that the Navy might be able to employ competition between shipyards in their 
procurement (something that the Navy cannot do with large-deck, nuclear-powered carriers like 
the CVN-78 class, because only one U.S. shipyard, HII/NNS, can build aircraft carriers of that 
size), and that today’s aircraft carriers concentrate much of the Navy’s striking power into a 
                                                 
21 See CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship Programs: Background and Issues for 
Congress, by Ronald O'Rourke. 
22 This is a reference to a CVL whose design is based on that of the America (LHA-6) class amphibious assault ship. 
23 This is a reference to a carrier whose design is similar to that of the CVN-78 design, but with some of the CVN-78 
design’s features reduced or removed, resulting in a ship whose procurement cost and capability are less than that of the 
CVN-78 design. 
24 Megan Eckstein, “Light Carrier Studies Already Underway As Navy Considers Role for CVLs in Future Fleet,” 
USNI News, February 1, 2021. See also Joseph Trevithick, “Navy Looking At America And Ford Class Derivatives In 
New Light Aircraft Carrier Studies,” The Drive, February 2, 2021. 
Congressional Research Service  
 
12 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
relatively small number of expensive platforms that adversaries could focus on attacking in time 
of war. 
Supporters of CVNs traditionally have argued that smaller carriers, though individually less 
expensive to procure, are less cost-effective in terms of dollars spent per aircraft embarked or 
aircraft sorties that can be generated; that it might be possible to use competition in procuring 
certain materials and components for large-deck, nuclear-powered aircraft carriers; and that 
smaller carriers, though perhaps affordable in larger numbers, would be individually less 
survivable in time of war than CVNs. 
Section 128(d) of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of 
November 25, 2015) required the Navy to submit a report on potential requirements, capabilities, 
and alternatives for the future development of aircraft carriers that would replace or supplement 
the CVN-78 class aircraft carrier. The report, which was conducted for the Navy by the RAND 
Corporation, was delivered to the congressional defense committees in classified form in July 
2016. An unclassified version of the report was then prepared and issued in 2017 as a publicly 
released RAND report.25 The question of whether to shift to smaller aircraft carriers was also 
addressed in three studies on future fleet architecture that were required by Section 1067 of the 
FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015). 
Delay in CVN-78’s Deployment Due to Weapon Elevators and 
Other Challenges 
Overview 
Another oversight issue for Congress concerns a delay in CVN-78’s first deployment due to the 
need to complete the construction, testing, and certification of the ship’s 11 weapons elevators 
and to correct other technical problems aboard the ship.26 Challenges in completing the 
construction, testing, and certification of the ship’s weapon elevators were first reported in 
November 2018,27 and the issue became a matter of continuing oversight attention. The Navy 
stated that 11th and final weapon elevator was completed, tested, and certified on December 22, 
2021. 
Technical issues regarding the weapon elevators and other ship systems have delayed the ship’s 
first operational tasking to 2022,28 which would be about five years after the ship was 
commissioned into service. The delay in the ship’s first operational tasking has lengthened a 
period during which the Navy is attempting to maintain policymaker-desired levels of carrier 
forward deployments with its 10 other carriers—a situation that can lead to operational strains on 
those 10 carriers and their crews. 
                                                 
25 Bradley Martin and Michael McMahon, Future Aircraft Carrier Options, Santa Monica, CA, RAND Corporation, 
2017, 87 pp. 
26 See, for example, Dave Ress, “Years Late and Billions More: The USS Gerald R. Ford Is a Lesson in How the Navy 
Builds Ships,” Newport News Daily Press, May 23, 2021. 
27 See Anthony Capaccio, “U.S. Navy’s Costliest Carrier Was Delivered Without Elevators to Lift Bombs,” 
Bloomberg, November 2, 2018. 
28 See, for example, John M. Doyle, “After 3 Explosive Events of its Shock Trial, USS Gerald R. Ford Will be on 
Track for Operational Tasking in 2022, NAVSEA Says,” Seapower, August 3, 2021. 
Congressional Research Service  
 
13 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Weapons Elevators 
The ship’s 11 weapons elevators—referred to as Advanced Weapons Elevators (AWEs)—move 
missiles and bombs from the ship’s weapon magazines up to the ship’s flight deck, so that they 
can be loaded onto aircraft that are getting ready to take off from the ship. A lack of working 
weapons elevators can substantially limit an aircraft carrier’s ability to conduct combat 
operations. The Navy has struggled since November 2018 to meet promises it has repeatedly 
made to the defense oversight committees to get the elevators completed, tested, and certified. 
Reported developments include the following: 
  For much of 2019, the Navy continued to report that two of the 11 weapon 
elevators were completed, tested, and certified.29 
  On October 23, 2019, the Navy reported that the figure had increased to four of 
11.30  
  On April 22, 2020, the Navy announced that the fifth elevator had been certified, 
that the sixth was scheduled to be certified in the fourth quarter of FY2020, and 
that the remaining five were scheduled to be certified by the time that the ship 
undergoes Full Ship Shock Trials (FSSTs) in the third quarter of FY2021.31  
                                                 
29 Sam LaGrone, “Carrier Ford Will Only Have Two Weapon Elevators Ready When it Leaves Shipyard,” USNI News, 
October 9, 2019. See also Anthony Capaccio, “On Costliest U.S. Warship Ever, Navy Can’t Get Munitions on Deck,” 
Bloomberg, July 30, 2019. (The article was also published by Bloomberg with the title “Flawed Elevators on $13 
Billion Carrier Miss Another Deadline.”) Ben Werner, “Navy Says More Experts Coming to Work Ford Carrier 
Elevator Delays,” USNI News, July 5, 2019; Navy Research, Development and Acquisition Public Affairs Office, 
“Navy Full Court Press on USS Gerald R. Ford Weapons Elevators,” Navy News Service, July 1, 2019; Mark D. Faram, 
“The Navy’s New Plan to Fix Ford’s Elevators Failures,” Navy Times, July 1, 2019; Paul McLeary, “Navy Calls In 
Outsiders To Fix Troubled Ford Carrier,” Breaking Defense, July 1, 2019; Ben Werner and Sam LaGrone, “USS 
Gerald R. Ford Weapons Elevator Certifications Will Extend Pat October,” USNI News, May 29, 2019. See also Paul 
McLeary, “Will Trump Fire SecNav? Super Carrier USS Ford Suffers New Setback,” Breaking Defense, May 29, 
2019; Rich Abott, “Ford Elevator Work Prioritized And Extending Past October,” Defense Daily, June 3, 2019; Megan 
Eckstein, “Navy Building a Land-Based Test Site for Ford-Class Weapons Elevators, But Timing Won’t Help CVN-
78,” USNI News, May 31, 2019. 
For earlier press reports, see Anthony Capaccio, “U.S. Navy’s Costliest Carrier Was Delivered Without Elevators to 
Lift Bombs,” Bloomberg, November 2, 2018; Anthony Capaccio, “Flawed Bomb Elevators Leave Inhofe Leery of 
Buying Two Carriers,” Bloomberg, December 5, 2019; Megan Eckstein, “SECNAV to Trump: Ford Carrier Weapons 
Elevators Will Be Fixed by Summer, or ‘Fire Me,’” USNI News, January 8, 2019; USS Gerald R. Ford Public Affairs, 
“USS Gerald R. Ford Accepts First Advanced Weapons Elevator,” Navy News Service, January 16, 2019; Christopher 
Woody, “The Navy’s Newest Aircraft Carrier Got a Long-Missing Piece of Gear in December, Helping to Solve a 
Problem the Navy Secretary Has Bet His Job on Fixing,” Business Insider, January 20, 2019; Richard Sisk, “Navy 
Finally Has One Weapons Elevator Working on Its Newest Carrier,” Military.com, January 22, 2019; Mark D. Faram, 
“Once Beleaguered by Critics, the Ford Gets a Lift,” Navy Times, January 23, 2019; USS Gerald R. Ford (CVN 78) 
Public Affairs, “USS Gerald R. Ford Accepts Second Advanced Weapons Elevator,” Navy News Service, March 6, 
2019; Mark D. Faram, “Why the Once-Maligned Flattop Ford Is Finally Getting a Lift (or 11),” Navy Times, March 7, 
2019; Rich Abott, “Carrier Elevator Test Site Will Procure New Elevator, Ford Accepts Second Elevator,” Defense 
Daily, March 7, 2019; Rich Abott, “Navy To Build Land-Based Carrier Elevator Test Site,” Defense Daily, February 
21, 2019. 
30 Wesley Morgan, “Navy Secretary Accuses Congressional Critics of ‘Disinformation’ on Ford Carrier,” Politico Pro, 
October 23, 2019. See also Sam LaGrone, “Carrier Ford May Not Deploy Until 2024, 3rd Weapons Elevator Certified,” 
USNI News, October 22, 2019; Anthony Capaccio, “Trump Lets Navy’s Chief Off the Hook Over an Offer to ‘Fire 
Me,’” Bloomberg, November 2, 2019. 
31 Program Executive Office Aircraft Carriers Public Affairs, “Fifth Advanced Weapons Elevator certified aboard USS 
Gerald R. Ford (CVN 78),” Navy News Service, April 22, 2020. See also Megan Eckstein, “Ford’s 5th Weapons 
Elevator Done With Testing; All 11 Should Be Done By Next Summer’s Shock Trials,” USNI News, April 16, 2020. 
On January 16, 2020, a Navy official reportedly stated that work on all 11 elevators will be completed by May 2021, 
Congressional Research Service  
 
14 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
  On July 23, 2020, the Navy announced that the sixth elevator had been 
certified.32  
  In November 2020, it was reported that the seventh elevator was scheduled to be 
certified before the end of calendar year 2020, and that the remaining four would 
be completed by the end of April 2021.33  
  On March 16, 2021, it was reported that seventh elevator had been delivered in 
early March, that the eighth elevator was in testing and was scheduled to be 
delivered in April, that work on all the elevators considered together was 93% or 
94% complete, and that the remaining three elevators would be completed during 
2021.34  
  On March 23, 2021, Navy Admiral John Aquilino testified that nine of the 11 
elevators had been “repaired.”35 
  On May 13, 2021—about four years after the ship was delivered to the Navy—it 
was reported that four of the 11 elevators would not be certified until later in 
2021.36 
  On July 21, 2021, the Chief of Naval Operations (CNO), Admiral Michael 
Gilday, reportedly stated: “We’ll deliver two more [of the elevators] in early fall 
[2021] and then the remaining two by the end of 2021, so the elevators will be 
complete. And that’s going very, very well.”37 
  The Navy stated that 11th and final weapon elevator was completed, tested, and 
certified on December 22, 2021.38 
                                                 
although the official acknowledged that there is some risk in that schedule. (Mallory Shelbourne, “Navy Confident 
CVN-78 Will Have All Weapons Elevators by May 2021,” Inside Defense, January 16, 2020.) 
32 Gina Harkins, “Supercarrier Ford Could Soon Have More Than Half of Its Weapons Elevators Working,” 
Military.com, June 19, 2020. 
33 Mallory Shelbourne, “USS Gerald R. Ford Making Steady Progress Ahead of Deployment,” USNI News, November 
24, 2020. 
34 Michael Fabey, “US Navy Reports Progress on Key Carrier Ford Systems,” Jane’s Navy International, March 16, 
2021; Megan Eckstein, “As USS Gerald R. Ford Nears Shock Trials, Carrier Remains Busy With Testing, Fleet 
Support,” USNI News, March 12, 2021. See also Kara Dixon, “USS Gerald R. Ford Moving Toward Completion of 
Post-Delivery Tests and Trials, WAVY.com, March 10, 2021. 
35 See Rich Abott, “Aquilino Says Nine Of 11 Ford Elevators Finished,” Defense Daily, March 23, 2021; Aidan 
Quigley, “Aquilino: Ford ‘Through’ Technological Challenges, All but Two Elevators Finished,” Inside Defense, 
March 23, 2021. 
36 Aidan Quigley, “Ford Missed Elevator Certification Timeline Goal but Moves into Shock Trials on Time,” Inside 
Defense, May 10, 2021. See also Craig Hooper, “Despite Promises, USS Ford Heads to Shock Trials with 4 Broken 
Elevators,” Forbes, May 13, 2021; Peter Suciu, “The Navy’s New, Powerful Aircraft Carrier Is Heading to ‘Shock 
Trials,’” Business Insider, May 24, 2021. 
37 As quoted in Rich Abott, “CNO Says Final Ford Elevators Delivered By End Of Year, Identifies Lessons Learned,” 
Defense Daily, July 21, 2021. See also Aidan Quigley, “Navy Says Final Four Ford Elevators to be Complete by End of 
Year,” Inside Defense, August 3, 2021; Konstantin Toropin, “All of Aircraft Carrier Ford’s Weapons Elevators Will Be 
Ready by End of Year Despite Long Delay, Navy Says,” Military.com, August 10, 2021. 
38 See, for example, Megan Eckstein, “US Navy Completes Final Weapons Elevator on Aircraft Carrier Gerald R. 
Ford,” Defense News, December 23, 2021; Sam LaGrone, “HII Delivers Final Advanced Weapons Elevator Aboard 
USS Gerald R. Ford,” USNI News, December 23, 2021; Craig Hooper, “The Navy Gets A Christmas Present: All 11 
USS Ford Weapons Elevators Delivered,” Forbes, December 24, 2021. 
Congressional Research Service  
 
15 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The Navy states that lessons learned in building, testing, and certifying CVN-78’s AWEs will be 
applied to the AWEs of subsequent CVN-78 class carriers.39 In November 2020, it was reported 
that HII/NNS had formed a single team to fix and install the elevators on both CVN-78 and CVN-
79.40 
Other Technical Challenges 
In addition to challenges in building, testing, and certifying the ship’s weapon elevators, the Navy 
reportedly has been working to address problems with other systems on the ship, including its 
propulsion and electrical systems. 
Change in Program Manager 
A July 2, 2020, press report stated 
The Navy removed its program manager for the first-in-class USS Gerald R. Ford (CVN-
78), as Navy acquisition chief James Geurts looks to boost performance in the new carrier 
program. 
Capt.  Ron  Rutan  has  been  moved  from  the  program  office  to  the  Naval  Sea  Systems 
(NAVSEA)  staff,  and  Capt.  Brian  Metcalf  has  taken  over  the  program  office.  Metcalf 
previously served as the San Antonio-class amphibious transport dock (LPD-17) program 
manager and was working as the executive assistant to the commander of NAVSEA prior 
to his reassignment to the CVN-78 program office (PMS 378). 
“Readiness of USS Gerald R. Ford (CVN-78) is the Navy’s top priority, and the progress 
the team made during the Post Shakedown Availability (PSA) met requirements while the 
subsequent eight months of CVN 78’s post-delivery test and trials (PDT&T) period has 
been impressively ahead of plan. Even in the face of a global pandemic, the team has kept 
a lightning pace, and we will continue to do so, for our Navy and our nation, until USS 
Gerald R. Ford completes her post-delivery obligations and is fully available and ready for 
tasking by the Fleet,” NAVSEA spokesman Rory O’Connor told USNI News. 
Still, he said, “with 10 months left in PDT&T, followed by full-ship shock trials in [Fiscal 
Year 2021], we must ensure that the team takes the opportunity to recharge and allow for 
fresh eyes on upcoming challenges as required. While there is no perfect time for leadership 
transitions, it is prudent to bring in renewed energy now to lead the CVN 78 team through 
the challenges ahead. Capt. Metcalf’s proven program management acumen and extensive 
waterfront experience will be a tremendous asset to the CVN 78 team in the months ahead.” 
Metcalf took command of the program office on July 1. 
O’Connor reiterated that there was no specific incident or causal factor that led to Geurts’ 
decision to remove Rutan from the office and bring Metcalf in, but rather it was reflective 
of the program’s performance over time.41 
                                                 
39 See, for example, David B. Larter, “US Navy Makes Progress on Aircraft Carrier Ford’s Bedeviled Weapons 
Elevators,” Defense News, July 23, 2020; Mallory Shelbourne, “Navy Verifies USS Gerald R. Ford’s Sixth Advanced 
Weapons Elevator,” USNI News, July 23, 2020; Rich Abott, “Navy Certifies Second [Lower-Stage] Ford Magazine 
Elevator,” Defense Daily, July 23, 2020; Gina Harkins, “Navy Carrier Ford Now Has 6 Working Weapons Elevators,” 
Military.com, July 24, 2020. 
40 Michael Fabey, “Newport News Shipbuilding Forms One Team for Ford-class Weapons Elevators,” Jane’s, 
November 23, 2020. 
41 Megan Eckstein, “Navy Removes Ford Carrier Program Manager, Citing Performance Over Time,” USNI News, July 
2, 2020. See also Geoff Ziezulewicz, “Navy Fires Program Manager for Troubled Ford Aircraft Carrier,” Navy Times, 
July 7, 2020. 
Congressional Research Service  
 
16 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Navy Efforts to Address Technical Challenges 
A February 2, 2021, opinion column by two Navy admirals states 
As  the  USS  Gerald  R.  Ford  (CVN  78)  steamed  off  the  coast  of  Virginia  last  week—
qualifying  naval  aviators  from  fleet  replacement  squadrons—The  Virginian-Pilot  and 
Daily Press published a Jan. 28 editorial offering a dated and inaccurate assessment of the 
aircraft  carrier’s  performance  and  operational  accomplishments  over  the  last  several 
months. Ford is in month 16 of its Post-Delivery Test and Trials (PD&T) period, testing a 
host  of  combat  systems,  while  serving  as  the  primary  East  Coast  carrier  qualification 
platform for fleet naval aviators. 
The  ship  has  conducted  nine  underway  periods  since  beginning  PDT&T  in  November 
2019, and yet the editorial cited a “new assessment,” which omitted data from the last three 
underways  logged  in  late  2020—a  critical  period  in  the  development  of  both  the  ship’s 
systems and the crew. 
In November, for instance, Ford was at sea with her entire Carrier Strike Group (CSG) for 
integrated  operations.  During  this  underway,  CSG-12,  Carrier  Air  Wing  (CVW)  8, 
Destroyer  Squadron  Two  and  elements  from  the  group’s  Air  and  Missile  Defense  and 
Information Warfare teams conducted operations consistent with a CSG’s pre-deployment 
training cycles. As previously reported in the newspaper, Ford was “averaging some 50 
sorties a day,” with a partial air wing of roughly 35 aircraft flying, approximately 50% of 
a  fully  outfitted  air  wing  using  Electromagnetic  Aircraft  Launch  System  (EMALS)  and 
Advanced Arresting Gear (AAG) with great success. 
Ford has successfully launched and recovered aircraft nearly 6,500 times, and in December, 
the  crew  completed  more  than  840  launches  and  arrestments  while  qualifying  58  new 
aviators.  The  ship  also  recorded  a  new  single-day  record  of  170  launches  and  175 
arrestments  in  an  eight-and-a-half-hour  period,  eclipsing  Ford’s  previous  record  set  in 
April. In 2020, FORD completed 5,700 aircraft launches and recoveries across six at-sea 
periods, which was a sevenfold increase from the ship’s totals in 2018. 
The editorial also overlooked Ford’s progress in testing the ship’s command and control 
systems  during  strike  group  readiness  exercises,  which  play  a  crucial  role  in  preparing 
Ford’s crew and systems for operational employment well ahead of the timeline stated in 
the  editorial.  These  integrated  strike  group  operations  were  conducted  in  parallel  with 
planned  ship  testing  and  trials,  accelerating  the  Navy’s  ability  to  exercise  the  ship’s 
command and control capability prior to full ship shock trials scheduled for this summer 
and the follow-on planned incremental availability. 
As the hard-working shipbuilders of Newport News Shipbuilding and countless citizens of 
this region have likely seen in local news reports, Ford and her exceptional crew have been 
marking  significant  planned  milestones  since  completing  the  aircraft  carrier’s  Post-
Shakedown Availability in  October 2019. These  milestones  include certifying  the flight 
deck, completing  aircraft compatibility  testing,  embarking  the  strike  group  and  airwing, 
qualifying  more  than  400  naval  aviators,  and  conducting  combat  systems  certification 
preparations during approximately 200 days underway. 
Ford is providing significant operational readiness to the fleet commanders, even while in 
a  test  and  trial  status.  In  each  of  Ford’s  at-sea  periods,  the  ship’s  crew  and  embarked 
squadrons  continue  to  validate  and  to  refine  Ford’s  technological  innovations—
technologies never realized before on any combatant of its kind…. 
While  the  editors  are  right  that  it  is  not  unusual  for  the  first  ship  of  a  class  to  have 
unexpected  challenges  and  delays,  Ford  is  vigorously  testing  its  new  technology  and 
Congressional Research Service  
 
17 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
aggressively resolving issues. Ford-class aircraft carriers will serve as the centerpiece of 
strike group operations through the 21st century, supporting national strategic objectives.42 
An April 27, 2021, press report stated 
The efforts of USS Gerald R. Ford sailors during the carrier’s 18 months of post-delivery 
tests and trials look set to cut the time before the Navy’s newest carrier is ready to deploy—
possibly by a year or more. 
Rear  Adm.  Craig  Clapperton,  commander  of  the  Ford’s  carrier  strike  group,  said  the 
group’s latest exercises show the Ford would be ready to deploy 12 to 18 months earlier 
that its current—a schedule that was in its turn roughly two years later than the Navy had 
hoped when it started working on the carrier nearly two decades ago. 
After a set of live-fire exercises over the past several weeks at sea, the Ford has certified 
the missiles and cannons that are its last line of a defense. 
The  Ford  and  the  ships  and  air  wing  in  its  strike  group  also  completed  a  long  distance 
maritime strike exercise, a critical war-gaming test in which it had to escape from another 
task force seeking to disable it and then attack in its turn. 
“We have accelerated the timeline for Gerald R. Ford,” Clapperton said…. 
During the Ford’s latest at-sea exercise, its 18th since starting post delivery tests and trials, 
its  electromagnetic  catapult,  for  launching  planes,  and  arresting  gear,  for  keeping  them 
from plunging into the sea when landing, hit the 8,000 launch-and-recovery cycle mark, 
said Capt. Joshua Sager, air wing commander. 
That’s a key measure, since that is roughly the number of sorties an air-wing will fly during 
the several months of a deployment overseas. 
Sager said the new electromagnetic technology means the air-wing can get into the air—
and return to the battle after rearming and refueling—faster than with the traditional steam-
and-hydraulics systems that have been the mainstay for decades. 
“Now we’ve gone past the point of showing the Ford can do what Nimitz class can do…. 
Now we’re at the point of taking it to the next level,” he said, referring the class of 10 
nuclear carriers now in service.43 
An April 28, 2021, press report stated 
The  Advanced  Arresting  Gear  (AAG)  and  Electromagnetic  Aircraft  Launch  System 
(EMALS)  achieved  8,000  aircraft  recoveries  and  launches  aboard  USS  Gerald  R.  Ford 
(CVN 78) on April 19, during the final independent steaming event of her 18-month Post 
Delivery Test & Trials (PDT&T) period, the Naval Air Systems Command said in an April 
26 release.  
Capt.  Kenneth  Sterbenz,  Aircraft  Launch  and  Recovery  Equipment  (ALRE)  program 
manager (PMA-251) for EMALS and AAG, said ALRE finished PDT&T strong, and they 
are ready for the next step, as Ford prepares for Full Ship Shock Trials, which is scheduled 
to begin summer 2021.  
“ALRE’s support of EMALS and AAG was admirable throughout the rigorous testing of 
PDT&T  operations,”  said  Sterbenz.  “On  the  way  to  reaching  8,000  launches  and 
                                                 
42 John Meier and Craig Clapperton, “Opinion: Cutting-Edge USS Ford Cruising Toward Certification,” Virginian-
Pilot, February 2, 2021. 
43 Dave Ress, “Ford Crew’s Efforts Set to Shorten Time Until the Carrier Is Ready to Deploy, Strike Group CO Says,” 
Newport News Daily Press, April 27, 2021. 
Congressional Research Service  
 
18 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
recoveries, we saw many Ford crew trained, learned a great deal about the systems, and 
laid invaluable groundwork for future Ford-class ships.”  
As  CVN 78 moved  through PDT&T, ALRE  had  the opportunity to directly  support  the 
fleet, as 351 Naval aviators were qualified using EMALS and AAG throughout 2020 and 
2021. Time and training also enabled a great increase in the efficiency of flight operations. 
More  than  7,000  of Ford’s  total  launches and  recoveries  were  completed  in  the  last  18 
months.44 
Potential Oversight Questions 
Potential oversight questions for Congress include the following: 
  Why did the Navy accept delivery of CVN-78 from the shipbuilder and 
commission the ship into service if most or all of its weapon elevators were not 
completed, tested, and certified? 
  What steps has the Navy taken since CVN-78 was delivered to the Navy on May 
31, 2017, to keep Congress informed of challenges regarding the ship’s weapon 
elevators and other ship systems? 
  Why is it taking so long to complete, test, and certify the weapon elevators? 
  How much is it costing to complete, test, and certify the weapon elevators, and 
will the Navy include all of this cost in the ship’s total reported procurement 
cost? 
  When will the ship start its first deployment, and how much of a delay will that 
represent compared to the ship’s original schedule for starting its first 
deployment? 
  How much additional operational stress is the delay in CVN-78’s first 
deployment placing on the Navy’s 10 other aircraft carriers? 
  What steps is the Navy taking to ensure that a similar situation does not arise 
regarding the construction and initial deployments of CVN-79, CVN-80, and 
CVN-81? 
Transfer of Parts Intended for CVN-79 to CVN-78 
Regarding the construction of CVN-79, a November 15, 2021, press report states: 
The Navy is taking parts from an aircraft carrier currently under construction and placing 
them on USS Gerald R. Ford (CVN-78) so the lead ship is ready to deploy next year, USNI 
News has learned. 
The parts are coming from the future USS John F. Kennedy (CVN-79), the second ship in 
the Ford class of aircraft carriers that is currently under construction at Huntington Ingalls 
Industries’ Newport News Shipbuilding in Newport News, Va. 
Capt. Clay Doss, the Navy’s acquisition spokesman, told USNI News the parts taken from 
Kennedy for Ford range from pumps to limit switches. 
                                                 
44 Seapower Staff, “EMALS, AAG Hit 8,000 Aircraft Recoveries, Launches on Ford,” Seapower, April 28, 2021. See 
also Rich Abott, “Ford Finishes Combat Systems Ship Trials, Reaches 8,000 Aircraft Launches/Recoveries,” Defense 
Daily, April 26, 2021; Rich Abott, “Navy Completes Ford Carrier Post-Delivery Trials, Touts Success and Outlines 
Next Steps,” Defense Daily, May 5, 2021; Aidan Quigley, “Ford Missed Elevator Certification Timeline Goal but 
Moves into Shock Trials on Time,” Inside Defense, May 10, 2021. 
Congressional Research Service  
 
19 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
“Examples of parts include HMI screens for stores elevators as well as motor controllers, 
power  supplies,  small  pumps,  limit  switches  and  valve  actuators  for  various  systems 
throughout the ship,” Doss said. “This is not unusual early in a program and will occur less 
often as supply support matures.” 
Doss described the decision to take parts from Kennedy for Ford as a “project management 
tool” the service uses across programs. 
“It occurred only after confirming the parts or materials were not available in the supply 
system  and/or  that  alternate  sources  were  not  available,”  Doss  told  USNI  News.  “A 
replacement plan was also required in each case. None of the parts transferred to CVN 78 
are projected to impact the CVN 79 construction schedule.” 
In a separate statement, Naval Sea Systems Command said the procedures were in line with 
Navy maintenance rules. 
“In  accordance  with  the  Navy’s  Joint  Fleet  Maintenance  Manual,  cannibalizations  are 
being used as part of the process to augment readiness of CVN 78, and are only initiated 
after non-availability of materials has been established in the supply system or verification 
that alternate sources are not available,” Naval Sea Systems Command spokesman Alan 
Baribeau told USNI News in a statement.... 
A spokesperson for HII said the shipbuilder and the Navy are creating a supply network 
for the carrier class so the ships have access to spare parts. 
“A common shipbuilding practice for the first ship in class is to share parts between ships 
in  order  to  maximize  readiness  until  a  class-wide  supply  system  is  established,”  Duane 
Bourne told USNI News. “A relatively small volume of materials from the aircraft carrier 
John F. Kennedy (CVN 79) has been used on first-of-class U.S.S. Gerald R. Ford (CVN 
78) without impacting schedules. We are working with our Navy customer to build a supply 
system to include spare parts for the Ford class.”45 
Potential Impact of COVID-19 Pandemic 
Another issue for Congress concerns the potential impact of the COVID-19 pandemic on the 
execution of U.S. military shipbuilding programs, including the CVN-78 program. An August 13, 
2020, press report stated 
The Navy’s top acquisition official said the service is reassessing the timeline for the future 
aircraft carrier USS John F. Kennedy (CVN-79) due to both the COVID-19 pandemic and 
the switch from a dual to single-phase delivery plan. 
James Geurts told reporters during a phone press roundtable Wednesday [August 12] that 
“obviously we are watching with some concern, the workforce levels at all our shipyards, 
but  in  particular  at  Newport  News  there,  given  the  relatively  high  number  of  cases  in 
there.”… 
Geurts said the Navy is trying to understand the impacts from both COVID and moving to 
a single-phase delivery for CVN-79 and then “understanding the opportunity that going to 
                                                 
45 Mallory Shelbourne, “USS Gerald R. Ford Needs Parts from Carrier Kennedy for Repairs; Navy Says 
‘Cannibalization’ Won’t Delay JFK Schedule,” USNI News, November 15, 2021. See also Ryan Pickrell, “US Navy 
Pulls Parts off an Under-Construction Aircraft Carrier to Get USS Gerald R. Ford Ready to Deploy,” Business Insider, 
November 16, 2021; Rich Abott, “CVN-78 Taking Parts From CVN-79, Navy Says No Delays To Construction,” 
Defense Daily, November 18, 2021; Geoff Ziezulewicz and Diana Stancy Correll, “Kennedy Carrier Cannibalized to 
Ensure USS Gerald R. Ford Is Ready to Go Next Year,” Navy Times, November 19, 2021. 
Congressional Research Service  
 
20 
 link to page 14  link to page 13 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
a single phase delivery puts together and then leveraging that opportunity to build a more 
efficient schedule from here on out for that ship.”46 
Another August 13, 2020, press report stated 
Geurts told reporters during a telephone news conference that he was particularly worried 
about Newport News Shipbuilding, the Huntingtin Ingalls Industries (HII) yard in Virginia, 
“given the relatively high number of cases in there”…. 
The USN is trying to assess what the impacts of the workforce reductions will mean to the 
schedule of the aircraft carrier John F. Kennedy (CVN 79), the Ford-class ship recently 
launched at Newport News Shipbuilding…. 
After  the  media  call,  Geurts  told  Janes,  “While  we  still  are  seeing  major  reductions  in 
labour hours in CVN 79 versus CVN 78, we are also looking for opportunities to mitigate 
some of the Covid impacts as we shift to a single-phase delivery plan for that ship. Single-
phase delivery will allow us to adjust some of the manpower and trade skill phasing to take 
into account the Covid impacts to date. We are working on those adjustments.”47 
For additional discussion of the potential impact of the pandemic on the execution of U.S. 
military shipbuilding programs, see CRS Report RL32665, Navy Force Structure and 
Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke. 
Cost Growth and Managing Costs within Program Cost Caps 
Overview 
Another issue for Congress concerns cost growth in the CVN-78 program. Navy efforts to stem 
that growth and manage costs so as to stay within the program’s cost caps have been a continuing 
oversight issue for Congress several years. Congress in recent years has passed legislation on the 
issue that is in addition to the earlier-mentioned legislation that established and amended cost 
caps for the ships.48 
As shown in Table 3, the estimated procurement costs of CVN-78, CVN-79, and CVN-80 have 
grown 27.0%, 29.8%, and 15.8%, respectively, since the submission of the FY2008 budget. As 
shown in Table 2, cost growth on CVN-78 required the Navy to program $1,465.9 million in 
cost-to-complete (CC) procurement funding for the ship in FY2014-FY2016, FY2018, and 
                                                 
46 Rich Abott, “Navy Reassessing CVN-79 Schedule Due To Pandemic And Phase Change,” Defense Daily, August 13, 
2020. 
47 Michael Fabey, “Covid-19: Virus Impacts Force US Navy Schedule Reassessments for Carrier Kennedy and Other 
Programmes,” Jane’s Navy International, August 13, 2020. 
48 This additional legislation includes the following: 
Section 128 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015), which 
established a limitation on availability of funds for CVN–79 until certain conditions were met; 
Section 126 of the FY2017 National Defense Authorization Act (S. 2943/P.L. 114-328 of December 23, 2016), which 
established a limitation on availability of funds for procurement of CVN–80 until certain conditions were met; 
Section 121(b) of the FY2018 National Defense Authorization Act (H.R. 2810/P.L. 115-91 of December 12, 2017), 
which provided for a waiver on the limitation of availability of funds for CVN–79; and 
Section 122 of the FY2020 National Defense Authorization Act (S. 1790/P.L. 116-92 of December 20, 2020), which 
modified the above-listed Section 126 of P.L. 114-328 regarding an annual report on cost targets for CVN-78 class 
carriers. 
Congressional Research Service  
 
21 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
FY2021 and to request and program $607.0 million in CC funding for CVN-79 for FY2022-
FY2024. 
CVN-78 
A primary source of past cost growth on CVN-78 appears to have been an unrealistically low 
original cost estimate for the ship in the FY2008 budget submission, which might have reflected 
an underestimate of the intrinsic challenges of building the then-new Ford-class design compared 
to those of building the previous and well understood Nimitz-class design.49 
In addition to this general cause of past cost growth, additional and more-specific past risks of 
cost growth for CVN-78 included certain new systems to be installed on the ship. These included 
a new type of aircraft catapult called the Electromagnetic Launch System (EMALS), a new 
aircraft arresting system called the Advanced Arresting Gear (AAG), and the ship’s primary radar, 
called the Dual Band Radar (DBR). Congress followed these and other sources of risk of cost 
growth on CVN-78 for years. 
CVNs 79, 80, and 81 
Confidence Levels 
The Navy states that it is working to control cost growth on CVNs 79, 80, and 81. Even so, the 
Navy states that its confidence levels for its estimated procurement costs (not including costs for 
class-wide spare parts) for CVNs 79, 80, and 81 were 36%, 22%, and 20% as of June 2019, 
respectively, meaning that the Navy as of June 2019 estimated that the risk of future cost growth 
on CVNs 79, 80, and 81 were 64%, 78%, and 80%, respectively.50 
                                                 
49 The Congressional Budget office (CBO) in 2008 and GAO in 2007 questioned the accuracy of the Navy’s cost 
estimate for CVN-78. CBO reported in June 2008 that it estimated that CVN-78 would cost $11.2 billion in constant 
FY2009 dollars, or about $900 million more than the Navy’s estimate of $10.3 billion in constant FY2009 dollars, and 
that if “CVN-78 experienced cost growth similar to that of other lead ships that the Navy has purchased in the past 10 
years, costs could be much higher still.” CBO also reported that, although the Navy publicly expressed confidence in its 
cost estimate for CVN-78, the Navy had assigned a confidence level of less than 50% to its estimate, meaning that the 
Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office, 
Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in 
August 2007 that 
Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate, 
which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be 
built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s 
target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for 
construction was 22 percent higher than the Navy’s cost target, which was based on the budget. 
Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to 
build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage 
issues that affect cost suffers from insufficient cost surveillance. Without effective cost 
surveillance, the Navy will not be able to identify early signs of cost growth and take necessary 
corrective action. 
(Government Accountability Office, Defense Acquisitions[:] Navy Faces Challenges Constructing 
the Aircraft Carrier Gerald R. Ford within Budget, GAO-07-866, August 2007, summary page. See 
also Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed 
to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and 
Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary 
Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), 
p. 15.) 
50 Source: Navy information paper provided to CRS by Navy Office of legislative Affairs on June 20, 2019. 
Congressional Research Service  
 
22 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
October 2019 CBO Report 
An October 2019 CBO report on the potential cost of the Navy’s 30-year shipbuilding plan states 
the following regarding the CVN-78 program: 
The Navy’s current estimate of the total cost of the USS Gerald R. Ford, the lead ship of 
the CVN-78 class, is $13.1 billion in nominal dollars appropriated over the period from 
2001 to 2018. CBO used the Navy’s inflation index for naval shipbuilding to convert that 
figure to $16.2 billion in 2019 dollars, or 25 percent more than the corresponding estimate 
when the ship was first authorized in 2008. Neither the Navy’s nor CBO’s estimate includes 
the $5 billion in research and development costs that apply to the entire class. 
Because construction of the lead ship is finished, CBO used the Navy’s estimate for that 
ship to estimate the cost of successive ships in the class. But not all of the cost risk has 
been  eliminated;  in  particular,  the  ship’s  power  systems,  advanced  arresting  gear  (the 
system used to recover fixed-wing aircraft landing on the ship), and weapons elevators are 
not  yet  working  properly.  It  is  not  clear  how  much  those  problems  will  cost  to  fix,  but 
current Navy estimates suggest that it will be several tens of millions of dollars or more. 
CBO does not have enough information to independently estimate those final repair costs. 
The next carrier after the CVN-78 is the CVN-79, the John F. Kennedy, which is expected 
to be completed in 2024 and deployed in 2026. Funding for the ship began in 2007, the 
Congress officially authorized its construction in 2013, and the planned appropriations for 
it  were  completed  in  2018.  The  Navy  estimates  that  the  ship  will  cost  $11.3  billion  in 
nominal dollars (or $11.9 billion in 2019 dollars). The Navy’s 2014 selected acquisition 
report  on  the  CVN-79  states  that  “the  Navy  and  shipbuilder  have  made  fundamental 
changes in the manner in which the CVN 79 will be built to incorporate lessons learned 
from CVN 78 and eliminate the key contributors to cost performance challenges realized 
in  the  construction  of  CVN  78.”  Nevertheless,  the  Navy  informed  CBO  that  there  is  a 
greater  than  60  percent  chance  that  the  ship’s  final  cost  will  be  more  than  the  current 
estimate. Although CBO expects the Navy to achieve a considerable cost reduction in the 
CVN-79 compared with the CVN-78, as is typical with the second ship of a class, CBO’s 
estimate is higher than the Navy’s. Specifically, CBO estimates that the ship will cost $12.4 
billion in nominal dollars (or $12.9 billion in 2019 dollars), about 9 percent more than the 
Navy’s estimate. 
In 2018, the Congress authorized the third carrier of the class, the Enterprise (CVN-80). 
Appropriations for that ship began in 2016 and are expected to be complete by 2025. In 
2019, the Congress authorized the Navy to purchase materials jointly for the CVN-80 and 
the next ship, the CVN-81, to save money by buying in greater quantity. It also authorized 
the  Navy  to  change  the  sequencing  involved  in  building  the  ships  to  gain  greater 
efficiencies  in  their  construction.  Although  that  legislative  action  is  known  as  a  “two-
carrier  buy,”  the  Navy  would  not  be  building  both  ships  at  exactly  the  same  time. 
Purchasing the two ships together would accelerate the CVN-81’s construction by only one 
year compared with buying the ships individually as envisioned in the 2019 shipbuilding 
plan. 
In  the  2020  budget,  the  Navy  estimated  that  the  CVN-80  would  cost  $12.3  billion  in 
nominal dollars (or $11.4 billion in 2019 dollars). That represents a savings of $300 million 
compared with the Navy’s estimate in the 2019 budget. In contrast, CBO estimates that the 
CVN-80  would  cost  $13.6  billion  in  nominal  dollars  (or  $12.4  billion  in  2019  dollars), 
about 9 percent more than the Navy’s estimate. In information provided to CBO as part of 
the 2019 budget presentation, the Navy indicated that there was a greater than 60 percent 
chance that the ship’s final cost will be more than it estimated; in contrast, with the 2020 
budget, the Navy puts that figure at 78 percent. Thus, it is not clear whether the service’s 
2020  estimates  incorporate  savings  stemming  from  a  two-carrier  buy  or  simply  an 
acceptance of increased risk of future cost growth. 
Congressional Research Service  
 
23 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
With respect to the CVN-81, the pattern is similar. In the 2019 budget, the Navy estimated 
the CVN-81 at $15.1 billion in nominal dollars. In the 2020 budget with the two-carrier 
buy, the Navy estimated the cost of the ship at $12.6 billion in nominal dollars (or $10.5 
billion in 2019 dollars), for a savings of $2.5 billion. However, the Navy also told CBO 
that there is an 80 percent chance that the final cost will be higher than the current estimate, 
compared with the roughly 40 percent chance indicated in the 2019 budget. CBO estimates 
that  the  CVN-81  would  cost  $14.4  billion  in  nominal  dollars  (or  $11.9  billion  in  2019 
dollars), or 14 percent more than the Navy’s estimate. 
Overall,  the  Navy  estimates  an  average  cost  of  $12.7  billion (in  2019  dollars)  for  the  7 
carriers (CVN-81 through CVN-87) in the 2020 shipbuilding plan. CBO’s estimate is $13.0 
billion per ship….51 
CVN-79 
Navy officials have stated that they are working to control the cost of CVN-79 by equipping the 
ship with a less expensive primary radar,52 by turning down opportunities to add features to the 
ship that would have made the ship more capable than CVN-78 but would also have increased 
CVN-79’s cost, and by using a build strategy for the ship that incorporates improvements over the 
build strategy that was used for CVN-78. These build-strategy improvements, Navy officials have 
said, include the following items, among others: 
  achieving a higher percentage of outfitting of ship modules before modules are 
stacked together to form the ship; 
  achieving “learning inside the ship,” which means producing similar-looking ship 
modules in an assembly line-like series, so as to achieve improved production 
learning curve benefits in the production of these modules; and 
  more economical ordering of parts and materials including greater use of batch 
ordering of parts and materials, as opposed to ordering parts and materials on an 
individual basis as each is needed. 
An August 5, 2020, press report stated 
The Navy vowed that a runaway budget wouldn’t be allowed again after the USS Gerald 
Ford, the first in a new class of aircraft carriers, cost a record $13.3 billion. Now, the price 
for the second ship is creeping up. 
The  service’s  estimate  for  shipbuilder  Huntington  Ingalls  Industries  Inc.  to  design  and 
construct the USS John F. Kennedy has increased to $3.58 billion, up 7% from the $3.35 
billion contract awarded in 2015, according to the carrier program’s Selected Acquisition 
Report for fiscal 2021. 
That underscores previous warnings that the fully outfitted carrier may exceed an $11.4 
billion cost cap imposed by Congress. The contractor is falling short by a key measure of 
labor efficiency, the Navy said in the report obtained by Bloomberg News. 
Its workforce performed 91 cents of work for every Navy dollar spent in the last year, down 
from the more acceptable level of 95 cents per dollar over the same timeframe, according 
to the report. 
                                                 
51 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2020 Shipbuilding Plan, October 2019, 
pp. 17-19. 
52 See, for example, Megan Eckstein, “PEO Carriers: CVN-79 Will Have a New Radar, Save $180M Compared to 
[CVN-78’s] Dual Band Radar,” USNI News, March 17, 2015; Christopher P. Cavas, “Dual Band Radar Swapped Out 
In New Carriers,” Defense News, March 17, 2015; Christopher P. Cavas, “New US Carrier Radar Enters the Picture,” 
Defense News, March 23, 2015. 
Congressional Research Service  
 
24 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Huntington Ingalls also is falling short of a Navy goal to reduce cumulative labor hours by 
at least 18% from the first ship. With the vessel 69% complete, the Kennedy is performing 
at a 16% improvement over the Ford at the same point, Captain Danny Hernandez, a Navy 
spokesman, said in an email. 
Hernandez said the cost report’s figures stem in part from changes such as improvements 
in warfare capability and lessons learned from the Ford’s recent post-delivery “shakedown” 
sea  trials.  There  are  additional  costs  “from  congressional  direction”  requiring  that  the 
Kennedy be capable of deploying with F-35 jets by mid-2025, he said. 
The cost increases are also “due to delays relating to electrical, sheet metal, painting and 
platform engineering work,” the Navy said in the Selected Acquisition Report. The JFK is 
expected to be delivered in 2024…. 
But the report warned that “if the current cost performance continues, then the budget will 
be  exhausted  prior  to  the  completion”  of  the  carrier.  That  could  force  the  Defense 
Department to make the case to lawmakers for easing the cost cap. 
Beci Brenton, a spokeswoman for Newport News, Virginia-based Huntington Ingalls, said 
the  carrier’s  construction  is  about  72%  complete.  The  company  “continues  to  see  the 
benefits  associated  with  significant  build  strategy  changes  and  incorporation  of  lessons 
learned” from its predecessor. 
“We  track  cost  and  schedule  trends  continuously  and  share  that  information  with  our 
customer,” the Navy, Brenton said.53 
Issues Raised in DOT&E and GAO Reports 
Another oversight issue for Congress concerns CVN-78 program issues raised in a January 2021 
report from DOD’s Director, Operational Test and Evaluation (DOT&E)—DOT&E’s annual 
report for FY2020—and the 2020 edition of the Government Accountability Office’s (GAO’s) 
annual report surveying selected DOD weapon acquisition programs, which was published in 
June 2020. 
January 2021 DOT&E Report 
Regarding the CVN-78 program, the January 2021 DOT&E report stated the following in part: 
Assessment 
• As noted in previous annual reports, the test schedule has been aggressive. The extension 
in PSA [post-shakedown availability]54 delayed both phases of initial operational testing 
until FY22. 
• TEMP [test and evaluation master plan] Revision D outlines the Navy’s cybersecurity 
strategy to test CVN 78, but has not translated the strategy into an actionable test plan. 
Reliability 
• Four of CVN 78’s new systems stand out as critical to flight operations: EMALS, AAG, 
DBR, and AWE. Overall, the low reliability demonstrated by AAG, EMALS, and DBR, 
along with the uncertain reliability of AWE, could further delay the CVN 78 IOT&E [initial 
operational test and evaluation]. Reliability estimates derived from test data for EMALS, 
                                                 
53 Anthony Capaccio, “Next Carrier’s Cost Creeps Up After First One Hit $13.3 Billion,” Bloomberg, August 5, 2020. 
54 A post-shakedown availability is a maintenance availability (i.e., a maintenance period) that takes place after a ship’s 
shakedown cruise, which an initial cruise that is intended in part to identify problems with the ship’s construction and 
equipment. 
Congressional Research Service  
 
25 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
AAG, and DBR are discussed in following subsections. For AWE, preliminary reliability 
estimates have been provided on 6 of the 11 elevators, the only ones certified. 
EMALS55 
• The delivery of the EMALS launch bulletins allows CVN 78 to launch all aircraft in the 
ship’s Air Wing. 
•  During  the  3,975  catapult  launches  conducted  post  PSA  through  ISE  [independent 
steaming  event]  11,  EMALS  demonstrated  an  achieved  reliability  of  181  mean  cycles 
between  operational  mission  failure  (MCBOMF),  where  a  cycle  is  the  launch  of  one 
aircraft. This reliability is well below the requirement of 4,166 MCBOMF. 
• During ISE 8, two separate failures caused individual EMALS catapults to go down for 
3 days. One of the failures was attributed to a legacy component. 
•  The  reliability  concerns  are  exacerbated  by  the  fact  that  the  crew  cannot  readily 
electrically isolate EMALS components during flight operations due to the shared nature 
of the Energy Storage Groups and Power Conversion Subsystem inverters on board CVN 
78. The process for electrically isolating equipment is time-consuming; spinning down the 
EMALS motor/generators takes 1.5 hours by itself. This inability precludes EMALS high 
power maintenance during flight operations. 
AAG 
•  Through  the  first  3,975  recoveries,  AAG  demonstrated  an  achieved  reliability  of  48 
MCBOMF, where a cycle is the recovery of a single aircraft. This reliability estimate falls 
well below the requirement of 16,500 MCBOMF.  
•  While  in  port  prior  to  ISE  9,  during  maintenance  troubleshooting,  the  AAG  system 
experienced  a  failure  of  an  Energy  Storage  Capacitor  Bank,  which  rendered  all  three 
engines inoperative. It took the Navy 7 days to investigate the failure and bring AAG back 
into  service  by  mechanically  isolating  the  failed  capacitor  bank.  The  failed  parts  were 
repaired during a later in-port period. 
• The reliability concerns are magnified by the current AAG design that does not allow 
electrical  isolation  of  the  Power  Conditioning  Subsystem  equipment  from  high  power 
buses, limiting corrective maintenance on below-deck equipment during flight operations. 
Combat System 
• Post-PSA sea-based developmental test events show the DBR still experiences clutter 
tracks, but to a smaller extent and of a different origin than previously reported. The events 
also show that CEC [cooperative engagement capability],56 in certain conditions, provides 
inaccurate tracking of air contacts. During these events, SEWIP [surface electronic warfare 
improvement program]57 Block 2 created undesired emitter tracks that could cause the ship 
to  expend  more  ESSMs  [Evolved  Sea  Sparrow  Missiles]  and  RAMs  [Rolling  Airframe 
Missiles] than necessary to destroy incoming threats. 
                                                 
55 For additional discussion regarding the reliability of EMALS, see Sam LaGrone, “USS Gerald Ford EMALS 
Launching System Suffers Fault During Testing Period,” USNI News, June 8 (updated June 12), 2020; Rich Abott, 
“Ford EMALS Went Down During Testing At Sea,” Defense Daily, June 8, 2020; Mallory Shelbourne, “EMALS 
Aboard Ford Went Out, Interrupting Flight Operations,” Inside Defense, June 9, 2020; Gina Harkins, “Navy Carrier 
Ford’s High-Tech EMALS Catapult System Breaks During Sea Trials,” Military.com, June 11, 2020; Mallory 
Shelbourne, “Geurts: Navy Still Working to Diagnose Problem That Caused EMALS Failure on Ford,” Inside Defense, 
June 18, 2020; Megan Eckstein, “Navy Unsure If Recent EMALS Fault Was Equipment or Procedure Problem, But 
Workaround Has Been Validated,” USNI News, June 19, 2020. 
56 The CEC system permits data from sensors on multiple ships to be fused together, so as to improve radar tracking 
and target engagement. 
57 The SEWIP system is the Navy’s new surface-ship electronic warfare system. 
Congressional Research Service  
 
26 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
• The Navy is satisfied with the DBR track support for Air Traffic Control (ATC) after 
post-PSA at-sea testing. The DBR successfully suppresses the disclosure of the majority 
of environmental tracks when it sends tracks to [the] TPX-42 [shipboad air traffic control 
(ATC) system]. The Navy does not plan to conduct any further ATC-type aircraft flights 
during sea-based developmental testing. 
• During the August 2020 missile firing operational test on SDTS [self-defense test ship], 
the system demonstrated good tracking performance of the targets by MFR [multi-function 
radar]  and  CEC,  and  good engagement  support  by  the  SSDS  [ship  self-defense system] 
MK  2  Mod  6  element,  which  correctly  provided  scheduling  and  weapon  assignments. 
SEWIP  Block  2  emitter  reporting  interfered  with  optimal  engagements  against  threats. 
Several  problems  contributed  to  the failure of some  ESSMs  and  RAMs  to  destroy  their 
intended targets. 
• Results of live testing completed to date indicate that CVN 78 has limited self-defense 
capability  against  ASCM  [anti-ship  cruise  missile]  surrogates,  but  several  challenges 
persist with respect to the efficacy of the ship’s combat system. 
• Post PSA through ISE 11, DBR demonstrated a mean time between operational mission 
failures (MTBOMF) of 100 hours, below the requirement of 339 hours. 
• Preliminary results of EASR’s [enterprise air surveillance radar]58 early developmental 
testing  indicate  that  electromagnetic  interference,  tracking  performance,  electronic 
protection, and power compliance testing are focal areas for ongoing system developmental 
work  and  improvements.  Until  operationally  relevant  reliability  data  are  supplied  to 
DOT&E,  system  reliability  remains  a  significant  risk  area  for  EASR.  EASR’s  combat 
system integration remains untested. 
• Planned operational tests of the CVN 78 combat system continue to be delayed or have 
been canceled. In the 2006 Capstone Enterprise Air Warfare Ship Self-Defense TEMP, the 
Navy planned to leverage commonality between the DDG 1000 [destroyer] and CVN 78 
combat systems to reduce the number of operational test events conducted on each ship. 
However,  subsequent  changes  to  the  DDG  1000  combat  system  reduced  commonality 
between the two ships and negated the ability to leverage testing and resources across the 
two combat systems. 
•  DOT&E  recognizes  that  the  CVN  78  Air  Warfare  test  program  is  resource-limited 
because the Enterprise Air Warfare approach was not executable due to the divergence of 
the DDG  1000 and  CVN 78 combat systems.  DOT&E  accepts  this limitation expecting 
that the Navy will plan and execute an adequate air warfare test program for CVN 79. The 
CVN  79  test  campaign  is  also  intended  to  inform  CVN  78  combat  system  performance 
once it is retrofitted with planned changes. 
SGR 
• CVN 78 is unlikely to achieve its SGR [sortie generation rate] requirement. The target 
threshold  is  based  on  unrealistic  assumptions  including  fair  weather  and  unlimited 
visibility, and that aircraft emergencies, failures of shipboard equipment, ship maneuvers, 
and  manning  shortfalls  will  not  affect  flight  operations.  During  the  2013  operational 
assessment,  DOT&E  conducted  an  analysis  of  past  aircraft  carrier  operations  in  major 
conflicts.  The  analysis  concludes  that  the  CVN  78  SGR  threshold  requirement  is  well 
above historical levels. 
• DOT&E plans to assess CVN 78 performance during IOT&E by comparing it to the SGR 
requirement, as well as to the demonstrated performance of the Nimitz-class carriers. 
                                                 
58 The use of the word enterprise in this context is not a reference to the name of CVN-80; it is instead a reference to 
the surface ship community, or enterprise. The use term in the radar’s name denotes that the Navy envisages installing 
the radar on multiple ship classes within the community. 
Congressional Research Service  
 
27 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
• Poor reliability of key systems that support sortie generation on CVN 78 could cause a 
cascading series of delays during flight operations that would affect CVN 78’s ability to 
generate sorties. The poor or unknown reliability of these critical subsystems represents 
the most risk to the successful completion of CVN 78 IOT&E. 
Manning 
• Reduced manning requirements drove the design of CVN 78. The berthing capacity is 
4,660, or 1,100 fewer than Nimitz-class carriers. Based on current expected manning, the 
berthing capacity for officers and enlisted will be exceeded with some variability in the 
estimates depending on the specific scenario examined. 
Electromagnetic Compatibility 
•  Developmental  testing  identified  significant  electromagnetic  radiation  hazard  and 
interference problems. The Navy implemented some mitigation measures and conducted 
follow-on  characterization  testing  during  ISEs,  but  some  operational  limitations  and 
restrictions are expected  to persist into IOT&E  and deployment.  The Navy will  need to 
develop capability assessments at differing levels of system use in order for commanders 
to make informed decisions on system employment. 
Live Fire Test & Evaluation 
• In FY20, the Navy continued with the shock qualification testing of CVN 78 components 
to support the survivability evaluation of CVN 78 to underwater threat engagements. Due 
to  scarcity  of  test  assets,  some  components  and  systems  (e.g.,  DBR)  will  not  be  shock 
qualified before the FSST [full-ship shock trial].  
• Adequate use of M&S [modeling and simulation] in the vulnerability evaluation of the 
ship  against  underwater  threats  is  at  risk.  Challenges  with  the  Navy  Enhanced  Sierra 
Mechanics  M&S  tool  prompted  the  Navy  to  switch  back  to  the  Dynamic  Systems 
Mechanics  Advanced  Simulation  M&S  tool  to  complete  the  vulnerability  assessment 
report. While necessary, the change will require additional verification and validation to 
ensure the credibility of the survivability evaluation. 
Recommendations 
The Navy should: 
1. Continue to characterize the electromagnetic environment on board CVN 78 and develop 
operating procedures to maximize system effectiveness and maintain safety. As applicable, 
the Navy should use the lessons learned from CVN 78 to inform design modifications for 
CVN 79 and future carriers. 
2. Implement the required software changes to multiple combat system elements to allow 
cueing  from external  sources necessary to  conduct  one  of the two remaining  SDTS  test 
events. 
3. Conduct both remaining SDTS combat system test events for CVN 78. 
4. Correct the cause of combat system failures that led to ESSMs and RAMs missing their 
intended targets, and demonstrate the correction in a future phase of operational testing. 
5.  Fund  the  CVN  78  lead  ship  combat  system  operational  testing  and  the  M&S  suite 
required  to  support  assessment  of  the  CVN  78  PRA  [probability  of  raid  annihilation]59 
requirement. 
6. Conduct an operational assessment of EASR at Wallops Island, Virginia. This testing 
should evaluate EASR’s contributions to the air traffic control and self‑defense missions, 
                                                 
59 PRA is a measurement of the ship’s ability to defeat (i.e., annihilate) an attack (i.e., raid) consisting of multiple 
enemy anti-ship missiles. 
Congressional Research Service  
 
28 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
as well as provide an early assessment of electromagnetic interference and radiation hazard 
concerns. 
7. Update TEMP 1610 to include cybersecurity testing on CVN 78 and CVN 79 testing 
driven by the changes to the ship’s combat system, including the introduction of EASR. 
8.  Complete  validation  of  the  M&S  tools  supporting  the  LFT&E  [live-fire  test  and 
evaluation]  assessment,  including  comparison  of  the  FSST  data  to  relevant  M&S 
predictions. 
9. Continue to improve availability and reliability for EMALS, AAG, DBR, and AWE.60 
June 2021 GAO Report 
A June 2021 GAO report—the 2021 edition of GAO’s annual report assessing selected major 
weapon acquisition programs—stated the following: 
Technology Maturity, Design Stability, and Production Readiness 
Although Navy officials report that the program’s 12 critical technologies are fully mature, 
challenges  persist  with  using  these  technologies  and  demonstrating  their  reliability.  For 
example, as of October 2020, the Navy had certified only six of the 11 elevators to operate 
on  the  ship.  Further,  according  to  Navy  officials,  while  six  elevators  are  currently 
operational—three Upper Stage, one utility elevator, and two Lower Stage—only the two 
Lower Stage elevators are capable of delivering munitions to the main deck. The Navy is 
working with the shipbuilder to complete the five remaining elevators—all Lower Stage 
units—by the spring of 2021. The Navy plans to begin testing at a land-based site in early 
2022—following  a  one-year  delay  due  to  contract  issues—to  assess  the  elevators’ 
performance and reliability. With units already operating on CVN 78, any changes to the 
elevators resulting from land-based testing are likely to be costly and time-consuming for 
the Ford-class program. 
The Navy also continues to struggle with achieving the reliability of the electromagnetic 
aircraft launch system (EMALS) and Arresting Gear (AAG) in support of its requirement 
to  rapidly  deploy  aircraft.  The  Navy  is  conducting  shipboard  testing  as  it  prepares  for 
operational  testing  to  begin  in  the  summer  of  2022.  However,  if  these  systems  do  not 
reliably  function  during  this  test  phase,  CVN  78  may  not  be  able  to  demonstrate  it  can 
rapidly deploy aircraft. The Navy also does not expect EMALS and AAG to demonstrate 
their required reliability until after CVN 78 has begun deploying to the fleet. 
Since  2013,  we  have  identified  concerns  with  the  Ford  Class  test  schedule,  which  have 
been borne out as the start of operational testing has now been delayed by over 5 years to 
a planned date of August 2022. Most recently, program officials confirmed that the lead 
ship (CVN 78) will reach initial capability in July 2021—4 months later than they reported 
last  year—to  align  with  the  completion  of  post-delivery  testing.  The  Navy  will  declare 
initial  capability  without  demonstrating  capability  or  performance  through  successful 
operational  testing,  missing  an  opportunity  to  determine  whether  the  ship  is  capable  of 
conducting  mission  operations.  The  Navy  plans  to  complete  operational  testing  in 
November 2023. 
Further, the 2013 test and evaluation master plan is no longer current and program officials 
told us they anticipate sending the revised plan for Navy leadership review in early 2021. 
Without an approved test plan, we cannot comment on the Navy’s test events and whether 
current areas of technical risk inform the plan. We found past test plans to be optimistic, 
                                                 
60 Department of Defense, Director, Operational Test & Evaluation, FY2020 Annual Report, January 2021, 
pp. 137-139. 
Congressional Research Service  
 
29 
 link to page 35 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
with  little  margin  for  delays.  Program  officials  stated  that  test  plan  revisions  are  not 
delaying any required testing. 
Software and Cybersecurity 
Separate  program  offices  manage  software  development  for  CVN  78’s  critical 
technologies. The CVN 78 program is scheduled to complete an evaluation for potential 
cybersecurity  vulnerabilities  connected  with  section  1647  of  the  National  Defense 
Authorization Act for Fiscal Year 2016 in May 2022. 
Other Program Issues 
The lead ship (CVN 78) cost cap is currently $13.2 billion, more than $2.7 billion higher 
than its initial cap. Program officials do not believe they will need additional funding to 
correct deficiencies found in CVN 78’s acceptance trials. However, until CVN 78’s testing 
is completed, the risk of discovering more costly deficiencies persists. 
The  Navy  is unlikely  to obtain  planned  cost  savings  on  CVN  79  due  to several  factors. 
CVN 79 is 74 percent complete, but as of June 2020, ship construction is lagging behind 
cost  saving  goals.  Further,  according  to  program  officials,  the  shipbuilder’s  COVID-19 
pandemic  mitigations  also  reduced  construction  efficiency.  Officials  also  explained  that 
the Navy is making additional changes for CVN 79, including integrating F-35 aircraft and 
adjusting to a new single-phase delivery schedule, but has yet to assess how these factors 
will affect cost and schedule. The Navy reported awarding fixed-price contracts for CVNs 
80  and  81  in  January  2019,  which  it  expects  to  limit  cost  liability  and  incentivize 
shipbuilder  performance.  The  Navy  made  optimistic  assumptions  that  this  two-ship 
contract will save over $4 billion. We previously reported that the Navy’s own cost analysis 
showed that CVNs 80 and 81 have a high likelihood of cost overruns, which aligns with 
our findings on CVN 78 and CVN 79 cost growth. 
Program Office Comments 
We provided a draft of this assessment to the program office for review and comment. The 
program office provided technical comments, which we incorporated where appropriate. 
The program office stated that CVN 78 has completed 15 of 18 months of the ship’s post-
delivery test schedule. It added that during this time, CVN 78 recorded nearly 6,400 aircraft 
launches  and  recoveries.  According  to  the  program  office,  the  ship  completed  carrier 
qualification  for  over  400  aviators  and  cleared  99  percent  of  discrepancies  from  its 
acceptance  trials.  The  program  office  noted  that  CVN  78  broke  records  for  number  of 
aircraft  landings  in  one  day  and  for  consecutive  days  at  sea.  Additionally,  the  program 
office  stated  that  CVN  80  will  start  construction  in  February  2022.  Lastly,  the  program 
office reported that COVID-19 continues to affect construction performance.61 
Legislative Activity for FY2022 
Summary of Congressional Action on FY2022 Funding Request 
Table 4 summarizes congressional action on the FY2022 procurement funding request for the 
CVN-78 program. 
                                                 
61 Government Accountability Office, Weapon Systems Annual Assessment[:] Updated Program Oversight Approach 
Needed, GAO-21-222, June 2021, p. 169. 
Congressional Research Service  
 
30 
 link to page 35  link to page 35 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 4. Congressional Action on FY2022 Procurement Funding Request 
(Millions of dollars, rounded to nearest tenth)  
Authorization 
Appropriation 
HASC-
 
Request 
HASC 
SASC 
HAC 
SAC 
Conf. 
SASC 
CVN-78 
0 
0 
0 
0 
0 
0 
 
CVN-79 
291.0 
291.0 
291.0 
291.0 
291.0 
291.0 
 
CVN-80 
1,068.7 
1,062.2 
1,068.7 
1,062.2 
1,062.2 
1,068.7 
 
CVN-81 
1,299.8 
1,287.7 
1,299.8 
1,287.7 
1,287.7 
1,299.8 
 
Total above 
2,659.5 
2,640.9 
2,659.5 
2,640.9 
2,640.9 
2,659.5 
 
Source: Table prepared by CRS based on Navy’s FY2022 budget submission, committee and conference 
reports, and explanatory statements on FY2022 National Defense Authorization Act and FY2022 DOD 
Appropriations Act. 
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is 
House Appropriations Committee; SAC is Senate Appropriations Committee, HASC-SASC is HASC-SASC-
negotiated proposal, Conf. is conference agreement. 
FY2022 National Defense Authorization Act (H.R. 4350/S. 2792/S. 
1605) 
House 
The House Armed Services Committee, in its report (H.Rept. 117-118 of September 10, 2021) on 
H.R. 4350, recommended the funding levels shown in the HASC column of Table 4. The 
recommended reduction of $6.5 million for CVN-80 is for “Program decrease.” The 
recommended reduction of $12.405 million for CVN-81 is for “Program decrease.” (Page 373) 
Senate 
The Senate Armed Services Committee, in its report (S.Rept. 117-39 of September 22 [legislative 
day, September 21], 2021) on S. 2792, recommended the funding levels shown in the SASC 
column of Table 4. 
Section 136 of S. 2792 as reported by the committee states 
SEC.  136.  ACQUISITION,  MODERNIZATION,  AND  SUSTAINMENT  PLAN  FOR 
CARRIER AIR WINGS. 
(a) PLAN REQUIRED.—Not later than February 1, 2022, the Secretary of the Navy shall 
submit to the congressional defense committees a 15-year acquisition, modernization, and 
sustainment plan for the carrier air wings of the Navy. 
(b) ELEMENTS.—The plan required by subsection (a) shall include the following: 
(1) An assessment of how well the capabilities and composition of the carrier air wings 
meet  the  requirements  of  the  National  Defense  Strategy  and  a  plan  to  address  known 
shortfalls such as with respect to tanker capacity and strike fighter range. 
(2) An identification of the role of autonomous aircraft, including the MQ–25 aircraft, and 
other potential future capabilities and platforms in future carrier air wings. 
Congressional Research Service  
 
31 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(3)  An  assessment  of  whether  nine  carrier  air  wings  is  the  correct  force  structure, 
considering— 
(A) whether the composition of aircraft and squadrons within a carrier air wing as of the 
date on which the plan is submitted is adequate; and 
(B)  whether  ten  carrier  air  wings,  the  minimum  number  to  be  maintained  under  section 
8062(e)  of  title  10,  United  States  Code,  after  the  earlier  of  the  two  dates  referred  to  in 
subparagraphs (A) and (B) of paragraph (1) of such section, is adequate. 
(4) An identification of the appropriate modernization plan to maximize operational use of 
platforms in existence as of the date on which the report is submitted, particularly the EA–
18G  aircraft  and  the  E–2D  aircraft,  by  leveraging  available  technologies  such  as  Next 
Generation Jammer. 
Regarding Section 136, S.Rept. 117-39 states 
Acquisition, modernization, and sustainment plan for carrier air wings (sec. 136) 
The committee recommends a provision that would require the Navy to develop a 15-year 
acquisition,  modernization,  and  sustainment  plan  for  the  entire  carrier  air  wing  (CVW), 
building  off  the  requirement  in  the  William  M.  (Mac)  Thornberry  National  Defense 
Authorization Act for Fiscal Year 2021 (Public Law 116–283) to produce a fighter force 
structure acquisition strategy. The provision would require the Secretary of the Navy to 
provide the plan to the congressional defense committees not later than February 1, 2022. 
In order to meet the challenges of great power competition, the Navy’s carrier air wings 
must have the right capabilities and sufficient aircraft inventories. Although smaller scale 
efforts  have  looked  at  components  of  the  CVW,  such  as  fighter  force  structure,  a 
comprehensive plan based on current and projected requirements is necessary to maintain 
U.S. naval air superiority. The plan should: 
(1)  Assess  how  well  CVW  capabilities  and  composition  meet  National  Defense 
Strategy requirements, and plan to address known shortfalls such as tanker capacity 
and strike fighter range; 
(2) Identify the role of autonomous aircraft in future CVWs, to include the MQ–25 but 
also consider other potential future capabilities and platforms; 
(3) Assess whether nine CVWs is the correct force structure; 
(4) Consider whether the current composition of aircraft and squadrons within a CVW 
is adequate; 
(5)  Consider  whether  10  CVWs,  the  current  legal  requirement  to  be  achieved  by 
October 1, 2025, under section 8062 of title 10, United States Code, is adequate; and 
(6) Identify the appropriate modernization plan to maximize operational use of current 
platforms, particularly the EA–18G and E–2D, by leveraging available technologies 
such as the Next Generation Jammer. (Page 8) 
S.Rept. 117-39 also states (emphasis added) 
Submarine industrial base development 
The budget request included $1.6 billion in line number 2 of Shipbuilding and Conversion, 
Navy (SCN), for advance procurement for the Columbia-class submarine program. 
The  nuclear  shipbuilding  industrial  base  continues  to  struggle  to  support  the  increased 
demand associated with the Navy’s future shipbuilding plan. This presents significant risk 
to  the  Columbia-class  submarine,  the  Virginia-class  submarine  with  Virginia  Payload 
Module, and aircraft carrier programs. It is critical to further develop existing industrial 
capacity and qualify new suppliers now, in advance of the increased demand. 
Congressional Research Service  
 
32 
 link to page 35 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The  committee  believes  additional  funding  is  needed  to  increase  capacity,  qualify  new 
suppliers, add resiliency and create competition for critical components, and identify points 
in the supply chain where shortfalls exist. 
Therefore, the committee recommends an increase of $130.0 million in line number 2 of 
SCN for submarine industrial base supplier development efforts. (Page 15) 
HASC-SASC-Negotiated Proposal 
The joint explanatory statement for the HASC-SASC-negotiated proposal for the FY2022 
National Defense Authorization Act (S. 1605) that was released on December 7, 2021, 
recommends the funding levels shown in the HASC-SASC column of Table 4. The 
recommended reduction of $6.5 million for CVN-80 is for “Program decrease.” The 
recommended reduction of $12.405 million for CVN-81 is for “Program decrease.” (PDF page 
456 of 670) 
Section 126 of the HASC-SASC-negotiated proposal for S. 1605 states: 
SEC.  126.  ACQUISITION,  MODERNIZATION,  AND  SUSTAINMENT  PLAN  FOR 
CARRIER AIR WINGS. 
(a)  PLAN  REQUIRED.—Not  later  than  April  1,  2022,  the  Secretary  of  the  Navy  shall 
submit to the congressional defense committees a 15-year acquisition, modernization, and 
sustainment plan for the carrier air wings of the Navy. 
(b) ELEMENTS.—The plan required by subsection (a) shall include the following: 
(1)(A)  An  assessment  of  whether  and  to  what  extent  the  capabilities,  capacity,  and 
composition  of  the  carrier  air  wings  in  existence  as  of  the  date  of  plan  meet  the 
requirements of the National Defense Strategy; and 
(B) a plan to address any known shortfalls of such carrier wings, including shortfalls with 
respect to aerial refueling aircraft capacity and strike-fighter combat radius. 
(2) An operational risk assessment and risk mitigation plan regarding the nine carrier air 
wings that, as of the date of the plan, support combatant commander steady-state peacetime 
and potential major contingency requirements. 
(3) An explanation of when the Secretary of the Navy will field a minimum of 10 carrier 
air wings in accordance with section 8062(e) of title 10, United States Code. 
(4)  An  identification  and  explanation  of  the  role  of  autonomous  and  remotely-piloted 
aircraft,  including  the  MQ–25  aircraft,  and  other  potential  capabilities  and  platforms 
planned to be fielded in future carrier air wings. 
(5) A detailed deck and hangar space plan that supports realistic peacetime steady-state or 
contingency  surge  level  fixed-wing  aircraft  and  rotorcraft  preparation  activities,  flight 
operations,  and  onboard  unit-level  maintenance,  repair,  and  sustainment  activities  for 
future carrier air wings. 
(6)  An  appropriate  modernization  plan  to  maximize  operational  use  of  platforms  in 
existence as of the date of the plan, particularly the EA–18G aircraft and the E–2D aircraft, 
by leveraging available technologies such as Next Generation Jammer. 
(7) An identification of the logistics supply chain support and modernization plan required 
during  peacetime  steady-state  and  contingency  operations  for  future  carrier  air  wings, 
particularly as it relates to implementing the organic C–130 and C–40 logistics tethering 
strategy. 
Congressional Research Service  
 
33 
 link to page 35  link to page 35 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(8) A detailed explanation for the Secretary of the Navy’s decision to modify carrier air 
wing composition to one squadron of 14 F–35C aircraft instead of the originally planned 
two squadrons of 10 F–35C aircraft. 
FY2022 DOD Appropriations Act (H.R. 4432/S. XXXX) 
House 
The House Appropriations Committee, in its report (H.Rept. 117-88 of July 15, 2021) on H.R. 
4432, recommended the funding levels shown in the HAC column of Table 4. The recommended 
reduction of $6.5 million in procurement funding for CVN-80 is for “Basic construction growth,” 
while the recommended reduction of $12.045 million for CVN-81 is for “Automatic carrier 
landing system early to need” ($7.872 million) and “Air traffic control system early to need” 
($4.173 million). (Page 185) 
H.Rept. 117-88 states 
CVN–81 ELECTROMAGNETIC AIRCRAFT LAUNCHING SYSTEM AND 
ADVANCED ARRESTING GEAR ACQUISITION STRATEGY 
The  Committee  is  concerned  by  the  continued  delays  in  the  Navy’s  approval  of  the 
acquisition  strategy  for  the  Electromagnetic  Aircraft  Launching  System  and  Advanced 
Arresting Gear for CVN–81. The National Defense Authorization Act for Fiscal Year 2018 
authorized a dual-hull buy which allowed for equipment and shipsets to be procured earlier 
in the acquisition of CVN–80 and CVN–81, with a goal of realizing significant savings. 
However,  the  three-year  delay  in  approving  an  acquisition  strategy  and  contracting  for 
these main mission components of the carrier is causing a disruption to the production and 
manufacturing  processes  of  these  essential  components,  impacting  the  construction  and 
increasing the cost growth of CVN–81. The Committee encourages the Secretary of the 
Navy to prioritize consideration and approval of an acquisition strategy to procure these 
components. (Page 186)62 
Senate 
The Senate Appropriations Committee, in the explanatory statement it released on October 18, 
2021, for the FY2022 DOD Appropriations Act (S. XXXX), recommended the funding levels 
shown in the SAC column of Table 4. 
 
 
                                                 
62 See also Anthony Capaccio, “Navy Contractor Fumes Over Slow Award on System Scorned by Trump,” Bloomberg, 
July 13, 2021; Aidan Quigley, “Navy to Award Doris Miller EMALS and AAG Pre-Production Planning Contract by 
End of Year,” Inside Defense, July 22, 2021. 
Congressional Research Service  
 
34 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Appendix. Background Information on Two-Ship 
Block Buy for CVN-80 and CVN-81 
This appendix presents additional background information on the two-ship block buy contract for 
CVN-80 and CVN-81. 
The option for procuring two CVN-78 class carriers under a two-ship block buy contract had 
been discussed in this CRS report since April 2012.63 In earlier years, the discussion focused on 
the option of using a block buy contract for procuring CVN-79 and CVN-80. In more recent 
years, interest among policymakers focused on the option of using a block buy contract for 
procuring CVN-80 and CVN-81. 
On March 19, 2018, the Navy released a request for proposal (RFP) to Huntington Ingalls 
Industries/Newport News Shipbuilding (HII/NNS) regarding a two-ship buy of some kind for 
CVN-80 and CVN-81. A March 20, 2018, Navy News Service report stated the following: 
The Navy released a CVN 80/81 two-ship buy Request for Proposal (RFP) to Huntington 
Ingalls Industries—Newport News Shipbuilding (HII-NNS) March 19 to further define the 
cost savings achievable with a two-ship buy. 
With lethality and affordability a top priority, the Navy has been working with HII-NNS 
over the last several months to estimate the total savings associated with procuring CVN 
80 and CVN 81 as a two-ship buy. 
“In keeping with the National Defense Strategy, the Navy developed an acquisition strategy 
to  combine  the  CVN  80  and  CVN  81  procurements  to  better  achieve  the  Department’s 
objectives of building a more lethal force with greater performance and affordability,” said 
James F. Geurts, Assistant Secretary of the Navy, Research Development and Acquisition. 
“This  opportunity  for  a  two-ship  contract  is  dependent  on  significant  savings  that  the 
shipbuilding  industry  and  government  must  demonstrate.  The  Navy  is  requesting  a 
proposal from HII-NNS in order to evaluate whether we can achieve significant savings.” 
The two-ship buy is a contracting strategy the Navy has effectively used in the 1980s to 
procure  Nimitz-class  aircraft  carriers  and  achieved  significant  acquisition  cost  savings 
compared  to  contracting  for  the  ships  individually.  While  the  CVN  80/81  two-ship  buy 
negotiations transpire, the Navy is pursuing contracting actions necessary to continue CVN 
80 fabrication in fiscal year (FY) 2018 and preserve the current schedule. The Navy plans 
to award the CVN 80 construction contract in early FY 2019 as a two-ship buy pending 
Congressional approval and achieving significant savings.64 
Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/P.L. 115-232 of August 13, 2018) permitted the Navy, after DOD made certain 
certifications to Congress, to add CVN-81 to the existing contract for building CVN-80. DOD 
provided the required certification on December 31, 2018. On January 31, 2019, the Navy 
                                                 
63 See the section entitled “Potential Two-Ship Block Buy on CVN-79 and CVN-80” in the April 4, 2012, version of 
CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress, by 
Ronald O'Rourke. In more recent years, this section was modified to discuss the option in connection with CVN-80 and 
CVN-81. 
64 Naval Sea Systems Command Public Affairs, “Navy Seeks Savings, Releases Two-Carrier RFP,” Navy News, March 
20, 2018. See also Megan Eckstein, “UPDATED: Navy, Newport News Taking Steps Towards Two-Carrier Buy,” 
USNI News, March 19, 2018. 
Congressional Research Service  
 
35 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
announced that it had awarded a two-ship fixed-price incentive (firm target) (FPIF) contract for 
CVN-80 and CVN-81 to HII/NNS.65 
The two-ship contract for CVN-80 and CVN-81 can be viewed as a block buy contract because 
the two ships are being procured in different fiscal years (CVN-80 was procured in FY2018 and 
CVN-81 is shown in the Navy’s FY2020 budget submission as a ship procured in FY2020).66 The 
Navy’s previous two-ship aircraft carrier procurements occurred in FY1983 (for CVN-72 and 
CVN-73) and FY1988 (for CVN-74 and CVN-75). In each of those two earlier cases, however, 
the two ships were fully funded within a single fiscal year, making each of these cases a simple 
two-ship purchase (akin, for example, to procuring two Virginia-class attack submarines or two 
DDG-51 class destroyers in a given fiscal year) rather than a two-ship block buy (i.e., a contract 
spanning the procurement of end items procured across more than one fiscal year). 
Compared to DOD’s estimate that the two-ship block buy contract for CVN-80 and CVN-81 
would produce savings of $3.9 billion (as measured from estimated costs for the two ships in the 
December 2017 Navy business case analysis), DOD states that “the Department of Defense’s 
Office of Cost Assessment and Program Evaluation (CAPE) developed an Independent Estimate 
of Savings for the two-ship procurement and forecast savings of $3.1 billion ([in] Then-Year 
[dollars]), or approximately 11 percent.... The primary differences between [the] CAPE and Navy 
estimates of savings are in Government Furnished Equipment67 and production change orders.”68 
Within the total estimated combined reduction in cost, HII/NNS reportedly expects to save up to 
$1.6 billion in contractor-furnished equipment.69 
A November 2018 DOD report to Congress that was submitted as an attachment to DOD’s 
December 31, 2018, certification stated the following regarding the sources of cost reduction for 
the two-ship contract: 
The  CVN  80  and  CVN  81  two-ship  buy  expands  and  improves  upon  the  affordability 
initiatives  identified  in  the  Annual  Report  on  Cost  Reduction  Efforts  for  JOHN  F. 
KENNEDY (CVN 79) and ENTERPRISE (CVN 80) as required by section 126(c) of the 
National  Defense  Authorization  Act  for  Fiscal  Year  2017  (P.L.  114-328).  Production 
saving initiatives for single-ship buys included use of unit families  in construction, pre-
outfitting  and  complex  assemblies  which  move  work  to  a  more  efficient  workspace 
environment,  reduction  in  the  number  of  superlifts,70  and  facility  investments  which 
improve the shipbuilder trade effectiveness. A two-ship buy assumes four years between 
                                                 
65 See Office of the Navy Chief of Information, “Navy Awards Contract for Construction of Two Carriers,” Navy News 
Service, January 31, 2019; Megan Eckstein, “UPDATED: Navy Awards 2-Carrier Contract to Newport News 
Shipbuilding,” USNI News, January 31, 2019; Marcus Weisgerber, “US Navy Places First 2-Carrier Order in Three 
Decades,” Defense One, January 31, 2019; David B. Larter, “US Navy Signs Mammoth Contract with Huntington 
Ingalls for Two Aircraft Carriers,” Defense News, January 31, 2019; Rich Abott, “Navy Awards HII $15 Billion In 
Two Carrier Buy,” Defense Daily, February 1, 2019. 
66 For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy 
Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke. 
67 Government-furnished equipment (GFE) is equipment that the government purchases from supplier firms and then 
provides to the shipbuilder for incorporation into the ships. 
68 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 8-9. 
69 Rich Abott, “Navy Awards HII $15 Billion In Two Carrier Buy,” Defense Daily, February 1, 2019. Contractor-
furnished equipment (CFE) is equipment that the contractor (in this case, HII/NNS) purchases from supplier firms for 
incorporation into the ships. 
70 A superlift is the use of a crane to move a very large section of the ship from the land into its final position on the 
ship. 
Congressional Research Service  
 
36 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
ship  deliveries  which  allows  more  schedule  overlap,  and  therefore  more  shop-level  and 
assembly-level production efficiencies than two single-ship buys. 
Procuring two ships to a single technical baseline reduces the requirement for engineering 
labor  hours  when  compared  to  single-ship  estimates.  The  ability  to  rollover  production 
support  engineering  and  planning  products  maximizes  savings  while  recognizing  the 
minimum amount of engineering labor necessary to address obsolescence and regulatory 
changes on CVN 81. The two-ship agreement with the shipbuilder achieves a 55 percent 
reduction in construction support engineering hours on CVN 81 and greater than 18 percent 
reduction in production support and planning hours compared to single ship procurements. 
The two-ship procurement strategy allows for serial production opportunities that promote 
tangible learning and reduced shop and machine set-up times. It allows for efficient use of 
production facilities, re-use of production jigs and fixtures, and level loading of key trades. 
The continuity of work allows for reductions in supervision, services and support costs. 
The result of these efficiencies is a production man-hours step down that is equivalent to 
an 82 percent learning curve since CVN 79. 
Key  to  achieving  these  production  efficiencies  is  Integrated  Digital  Shipbuilding  (iDS). 
The Navy’s Research, Development, Test, and Evaluation (RDT&E) and the shipbuilder’s 
investment  in  iDS,  totaling  $631  million,  will  reduce  the  amount  of  production  effort 
required to build FORD Class carriers. The two-ship buy will accelerate the benefits of this 
approach. The ability to immediately use the capability on CVN 81 would lead to a further 
reduction in touch labor and services in affected value streams. The two-ship agreement 
with  the  shipbuilder  represents  a production  man-hours reduction  of over  seven  percent 
based  on  iDS  efficiencies.  Contractual  authority  for  two  ships  allows  the  shipbuilder  to 
maximize  economic  order  quantity  material  procurement.  This  allows  more  efficient 
ordering and scheduling of material deliveries and will promote efficiencies through earlier 
ordering,  single  negotiations,  vendor  quotes,  and  cross  program  purchase  orders.  These 
efficiencies  are  expected  to  reduce  material  costs  by  about  six  percent  more  when 
compared  to  single-ship  estimates.  Improved  material  management  and  flexibility  will 
prevent  costly production delays.  Furthermore,  this provides  stability within  the  nuclear 
industrial base, de-risking the COLUMBIA and VIRGINIA Class programs. The two-ship 
buy would provide economic stability to approximately 130,000 workers across 46 States 
within the industrial base. 
Change  order  requirements  are  likewise  reduced  as  Government  Furnished  Equipment 
(GFE) providers will employ planning and procurement strategies based on the common 
technical baseline that minimize configuration changes that must be incorporated on the 
follow ship. Change order budget allocations have been reduced over 25 percent based on 
two-ship strategies. 
In addition to the discrete savings achieved with the shipbuilder, the two-ship procurement 
authority provides our partner GFE providers a similar opportunity to negotiate economic 
order quantity savings and achieve cross program savings when compared to single-ship 
estimates.71 
An April 16, 2018, press report stated the following: 
If  the  Navy  decides  to  buy  aircraft  carriers  CVN-80  and  81  together,  Newport  News 
Shipbuilding will be able to maintain a steady workload that supports between 23,000 and 
25,000 workers at the Virginia yard for the next decade or so, the shipyard president told 
reporters last week. 
                                                 
71 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 6-7. 
Congressional Research Service  
 
37 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Part of the appeal of buying the two carriers together is that the Navy would also buy them 
a bit closer together: the ships would be centered about three-and-a-half or four years apart, 
instead of the five-year centers for recent carrier acquisition, Newport News Shipbuilding 
President Jennifer Boykin told reporters. 
Boykin said the closer ship construction centers would allow her to avoid a “labor valley” 
where the workforce levels would dip down after one ship and then have to come back up, 
which is disruptive for employees and costly for the company. 
If this two-carrier buy goes through, the company would avoid the labor valley altogether 
and ensure stability in its workforce, Boykin said in a company media briefing at the Navy 
League’s  Sea  Air  Space  2018  symposium.  That  workforce  stability  contributes  to  an 
expected $1.6 billion in savings on the two-carrier buy from Newport News Shipbuilding’s 
portion of the work alone, not including government-furnished equipment.... 
Boykin said four main things contribute to the expected $1.6 billion in savings from the 
two-carrier buy. First, “if you don’t have the workforce valley, there’s a labor efficiency 
that represents savings.” 
Second,  “if  you  buy  two  at  once,  my  engineering  team  doesn’t  have  to  produce  two 
technical baselines, two sets of technical products; they only have to produce one, and the 
applicability is to both, so there’s savings there. When we come through the planning, the 
build plan of how we plan to build the ship, the planning organization only has to put out 
one plan and the applicability is to both, so there’s savings there.” 
The third savings is a value of money over time issue, she said, and fourth is economic 
order quantity savings throughout the entire supply chain.72 
Discussions of the option of using a block buy contract for procuring carriers have focused on 
using it to procure two carriers in part because carriers have been procured on five-year centers, 
meaning that two carriers could be included in a block-buy contract spanning six years—the same 
number of years originally planned for the two block buy contracts that were used to procure 
mnay of the Navy’s Littoral Combat Ships.73 
It can be noted, however, that there is no statutory limit on the number of years that a block buy 
contract can cover, and that the LCS block buy contracts were subsequently amended to cover 
LCSs procured in a seventh year. This, and the possibility of procuring carriers on 3- or 3.5-year 
centers, raises the possibility of using a block buy contract to procure three aircraft carriers: For 
example, if procurement of aircraft carriers were shifted to 3- or 3.5-year centers, a block buy 
contract for procuring CVN-80, CVN-81, and CVN-82 could span seven years (with the first ship 
procured in FY2018, and the third ship procured in FY2024) or eight years (with the first ship 
procured in FY2018 and the third ship procured in FY2025). 
The percentage cost reduction possible under a three-ship block buy contract could be greater 
than that possible under a two-ship block buy contract, but the offsetting issue of reducing 
congressional flexibility for changing aircraft carrier procurement plans in coming years in 
response to changing strategic or budgetary circumstances could also be greater. 
                                                 
72 Megan Eckstein, “Newport News Would Save $1.6 Billion, Maintain Stable Workforce of 25,000 Under 2 Proposed 
Carrier Buy,” USNI News, April 16, 2018. See also Rich Abott, “HII Sees Two Carrier Buy Saving $1.6 Billion Before 
GFE,” Defense Daily, April 11, 2018: 10-11. 
73 For more on the LCS block buy contracts, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: 
Background and Issues for Congress, by Ronald O'Rourke. 
Congressional Research Service  
 
38 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Author Information 
 
Ronald O'Rourke 
   
Specialist in Naval Affairs 
    
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan 
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and 
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other 
than public understanding of information that has been provided by CRS to Members of Congress in 
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not 
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in 
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or 
material from a third party, you may need to obtain the permission of the copyright holder if you wish to 
copy or otherwise use copyrighted material. 
 
Congressional Research Service  
RS20643 · VERSION 260 · UPDATED 
39