link to page 1 


 
 INSIGHTi  
Line 5 Pipeline: Replacement/Tunnel Project 
November 9, 2021 
The Line 5 Pipeline is a 30-inch, 645-mile pipeline  owned by Enbridge carrying up to 540,000 barrels per 
day of crude oil and natural gas liquids from Superior, WI, to Sarnia, Ontario (Figure 1). A key segment 
of Line 5 is an underwater crossing at the Straits of Mackinac—between Michigan’s upper and lower 
peninsulas—where the pipeline runs for approximately four miles across the lakebed. This crossing has 
been an environmental concern due to the risk it poses of a “worst case” oil spil  into the Great Lakes. 
Figure 1. Enbridge Line 5 Pipeline 
 
Source: CRS using data from  Platts, and Esri Data & Maps 2019. 
Under the terms of various state agreements, Enbridge plans to replace this pipeline segment with a new 
one constructed through a tunnel beneath the lakebed—which requires federal approval. Enbridge 
continues operating the existing pipeline in the meantime. However, the state of Michigan has ordered 
Line 5 to shut down. Whether the pipeline should continue operating in its current configuration, and 
whether the federal government should grant a tunnel permit for a replacement crossing, have been the 
subject of litigation, federal oversight, and a U.S.-Canada treaty dispute. 
Congressional Research Service 
https://crsreports.congress.gov 
IN11798 
CRS INSIGHT 
Prepared for Members and  
 Committees of Congress 
 
  
 
Congressional Research Service 
2 
Michigan Easement Challenges 
Line 5 was constructed in 1953 as part of a pipeline system linking oil fields in Alberta, Canada, to 
refinery markets in the Great Lakes region. (The pipeline currently carries products from both Canadian 
and domestic sources.) Enbridge’s predecessor—Lakehead Pipe Line Company—was granted an 
easement at the time of construction by the State of Michigan to cross the Straits of Mackinac. In October 
2018, Michigan and Enbridge entered an agreement whereby Enbridge would construct a tunnel under the 
straits, replace the existing Line 5 segment with a new pipeline segment through the tunnel, and 
“permanently deactivate” the old segment. The agreement also provided that the state would be 
“expressly confirming Enbridge’s rights to operate the [existing pipeline] under the terms of the Easement 
during the construction of the Straits Tunnel and Line 5 Replacement.” The agreement was followed by a 
December 11, 2018, state statute creating the Mackinac Straits Corridor Authority, which approved tunnel 
construction on December 19, 2018. 
On November 13, 2020, under a new gubernatorial administration, state officials notified Enbridge that 
the 1953 easement was being revoked on safety grounds, requiring the Line 5 segment across the straits to 
cease operating by May 2021. On November 24, 2020, Enbridge filed a chal enge in federal court to the 
state’s pipeline safety jurisdiction and shutdown order. In March 2021, the court ordered mediation 
between the two parties to resolve the dispute, but as of October 2021, that mediation was reported to be 
unsuccessful. The court has not yet ruled on the case. Absent a federal court order, Enbridge continues to 
operate the pipeline  across the straits. 
U.S.-Canada Pipeline Treaty 
The Canadian government has ardently supported the continued operation of Line 5. Canada has sought to 
intervene though public statements and court filings, citing a 1977 pipeline  treaty with the United States 
which prohibits a “public authority in the territory of either” from instituting “any measures ... which are 
intended to, or which would have the effect of, impeding, diverting, redirecting or interfering with in any 
way the transmission of hydrocarbon in transit.” On October 4, 2021, Canada announced that it was 
formal y invoking the dispute settlement provision of the treaty regarding Line 5. On November 9, the 
White House Deputy Press Secretary stated that “both the U.S. and Canada wil  engage constructively” in 
Line 5 negotiations and that shutting down the existing pipeline  “is something that we’re not going to 
do.” 
Army Corps Tunnel Permit 
In 2020, Enbridge filed a joint application with the U.S. Army Corps of Engineers (Corps) and the 
Michigan Department of Environment, Great Lakes, and Energy (EGLE) to build a tunnel below the 
lakebed for a new Line 5 pipeline  crossing. The Corps has statutory authority over the proposed Line 5 
tunnel pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344), under which the Corps permits 
activities that may discharge dredge or fil  material into waters of the United States, including wetlands. 
(Although Michigan is one of three states that administer their own Section 404 permits, the Corps retains 
jurisdiction over certain waters, such as the Straits of Mackinac.) The agency also has authority pursuant 
to Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403), under which the Corps permits 
structures and work in or affecting navigable waters. 
In carrying out its authorities, the Corps must identify and consider the environmental impacts of the 
agency’s proposed actions (e.g., issuing a tunnel permit) pursuant to the National Environmental Policy 
Act (NEPA; 42 U.S.C. §§4321 et seq.) among other statutory requirements. On June 23, 2021, the Corps 
announced that it would be preparing an Environmental Impact Statement (EIS), to “ensure al  potential
  
Congressional Research Service 
3 
impacts and reasonable alternatives associate d with this project are thoroughly analyzed and wil  
ultimately support a decision on the permit application.” The Corps states that its environmental review 
“is limited to the proposed crossing of the Straits of Mackinac and adjacent wetlands.” However, it is not 
clear to what extent the Corps’ NEPA review may consider the greenhouse gas (GHG) emissions 
associated with the fossil fuels passing through pipeline segment, as cal ed for by some advocates. The 
agency has not set a deadline to complete the EIS. 
On January 29, 2021, EGLE announced that it had approved Enbridge’s application for permits required 
to build  the tunnel. Although EGLE  “acknowledged public concerns about the existing oil pipeline and 
affirmed ... that the current pipeline ... poses an unacceptable risk to the Great Lakes,” the agency 
concluded that “the proposed tunnel could comply with state environmental laws.” The tunnel project stil  
requires approval from the Michigan Public Service Commission, which has ruled that it must consider 
GHG emissions caused by products transported by Line 5. The commission’s review is ongoing.  
 
 
 
 
Author Information 
 
Paul W. Parfomak 
   
Specialist in Energy Policy 
 
 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff 
to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of 
Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of 
information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. 
CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United 
States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, 
as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the 
permission of the copyright holder if you wish to copy or otherwise use copyrighted material. 
 
IN11798 · VERSION 1 · NEW