link to page 1  link to page 1  link to page 2 

 
 
October 19, 2020
Federal Telecommunications Modernization: Transitioning 
from Networx to Enterprise Infrastructure Solutions
Background 
GSA is providing assistance through— 
Periodically, the General Services Administration (GSA) 
  a Transition Coordination Center to provide assistance 
negotiates new contracts through which federal agencies 
with inventory validation, transition planning, and 
can acquire their telecommunications services. Current 
solicitation development; and  
contracts—known as Networx, Washington Interagency 
  Transition Ordering Assistance for requirements 
Telecommunications System 3, and Regional Local Service 
development, source selection, and proposal 
Agreements—are scheduled to end on May 31, 2023. Each 
evaluation. 
of these contracts has been extended twice. In FY2019, 
agencies spent about $2.5 billion on services acquired 
The Transition Coordination Center was put in place in 
through these contracts, with about $2 billion going to 
January 2016. Transition Ordering Assistance was finalized 
Networx. 
in March 2017.  
EIS Overview 
Figure 1. Enterprise Infrastructure Solutions Timeline 
The new GSA telecommunications services acquisition 
contract vehicle is Enterprise Infrastructure Solutions (EIS). 
On August 1, 2017, the GSA announced that it had awarded 
EIS contracts to 10 vendors. These contracts have a 
combined value of up to $50 billion and are for a possible 
period of up to 15 years—one 5-year base period and two 
5-year option periods. According to the Government 
Accountability Office (GAO), more than 135 agencies will 
transition 32 types of services and millions of voice and 
data lines to the new contract. EIS is intended to deliver— 
  cost savings resulting from increased supplier 
competition and price transparency; 
  qualified industry suppliers who can deliver a 
complete portfolio of cyber-security solutions; 
  an ability to incorporate emerging technologies as 
they become available; and  
  flexibility to address unique agency requirements. 
The Transition to EIS 
In 2017, GSA identified several critical milestones (Figure 
1) that agencies should meet to ensure they will have 
completely transitioned to EIS before their current contracts 
expire. These dates were set in an effort to avoid the costly 
delays associated with previous transitions. 
Agencies have principal responsibility for the transition. 
According to GSA, agencies must— 
  identify key personnel for the transition; 
  engage expertise from agency leadership to build a 
transition team of telecommunications managers, 
acquisition experts, and financial staff; 
  conduct an inventory of services to be transitioned; 
  develop a transition plan and schedule that includes 
GSA’s major transition milestones;
 
 
Source: CRS based on General Services Administration data. 
  prepare solicitations for task orders; 
  place task and service orders; and 
In April 2020, GAO testified that the majority of the 19 
  develop a process to review, accept/reject, and pay for 
federal agencies it had studied had not met the two 2019 
services. 
milestones and were not on track to meet the final (2022) 
milestone (Table 1). 
 
https://crsreports.congress.gov 
 link to page 1  link to page 2 
Federal Telecommunications Modernization: Transitioning from Networx to Enterprise Infrastructure Solutions 
Table 1. Status and Plans for Completing EIS 
achieved in this initial assessment, the better positioned an 
Transition Activities by GSA Milestone Dates (as of 
agency is expected to be to fully transition to EIS and 
April 2020) 
achieve 100% transition by the September 30, 2022, 
milestone date.  
Agencies 
Agencies 
that 
that did not 
Table 2. Percent Transition to Enterprise 
completed 
or do not 
Infrastructure Solutions by Agency (as of April 2020) 
GSA’s 
or plan to 
plan to 
milestone 
complete 
complete 
EIS 
date to 
activity by 
activity by 
transition 
complete 
milestone 
milestone 
activity 
activity 
date 
date 
Milestone 1 
3/31/2019 
5 
14 
Milestone 2 
9/30/2019 
1 
18 
Milestone 3 
9/30/2022 
8 
11 
Source: Government Accountability Office analysis of data provided 
by agency officials. Telecommunications: Ful y Implementing 
Established Transition Planning Practices Would Help Agencies 
Reduce Risk of Costly Delays, GAO-20-458T, March 4, 2020, 
https://www.gao.gov/products/GAO-20-458T. 
Note: For milestone definitions, see Figure 1. 
Comparison to Previous Transitions  
GSA’s establishment of early transition milestone dates was 
in response to the significant delays that occurred during 
the last two contract transitions. GAO found that those 
delays led to “hundreds of millions of dollars in increased 
costs and missed savings.” Delays associated with the 
transition that began in 1998 resulted in an estimated $74 
million in missed savings. The transition to Networx, which 
began in 2007, took 33 months longer than planned, and the 
majority of agencies experienced transition delays. In 2013, 
GAO reported that these delays resulted in an increase of 
$66.4 million in costs to GSA. The delays also resulted in 
an estimated $329 million in lost savings because agencies 
continued to order services from the previous contract even 
after the same services were available through Networx, 
 
generally at lower rates. At the time, GAO attributed the 
Source: FITARA 10.0 Scorecard, https://oversight.house.gov/sites/
delays to inadequate project planning. 
democrats.oversight.house.gov/files/Scorecard%2010%20-
Legislative Review of Transition  
%20USAID%20corrected.pdf. 
In August 2020, the House Committee on Oversight and 
Note: Percentages at or above 70% are shown in green; percentages 
Reform’s Subcommittee on Government Operations added 
at or below 30% are shown in red. 
EIS transition status to its “scorecard,” which it publishes 
Additional Legislative Activity: 116th 
twice a year to assess compliance with the Federal 
Congress 
Information Technology Acquisition Reform Act 
The House Committee on Oversight and Reform’s 
(FITARA). The subcommittee assessed, by percentage, the 
Subcommittee on Government Operations held a hearing, 
extent to which 24 agencies had moved off expiring 
“Making IT a Priority for the Federal Government,” on 
contracts (Table 2). The new EIS category was not used in 
March 4, 2020. The hearing examined several initiatives of 
agencies’ final grade in August 2020, but it may be a factor 
GSA’s Federal Acquisition Service. The service operates 
in future scoring.  
several programs to help agencies modernize their existing 
The highest reported EIS transition percentages, at or over 
information technology infrastructure and adopt new 
70%, were at the Nuclear Regulatory Commission, National 
technologies. EIS was one of the three topics for the 
Science Foundation, and Department of the Treasury. The 
hearing. No legislation has been introduced in the 116th 
lowest percentages, at or under 30% transitioned, were at 
Congress that would directly impact current 
the Department of State, Department of Defense, 
telecommunications modernization efforts. 
Department of Homeland Security, Department of 
Commerce, Small Business Administration, Office of 
Patricia Moloney Figliola, Specialist in Internet and 
Personnel Management, and National Aeronautics and 
Telecommunications Policy   
Space Administration. Overall, six out of 24 agencies 
IF11668
reported over 50% EIS adoption. The higher the percentage 
https://crsreports.congress.gov 
Federal Telecommunications Modernization: Transitioning from Networx to Enterprise Infrastructure Solutions 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to 
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. 
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has 
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the 
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be 
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include 
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you 
wish to copy or otherwise use copyrighted material. 
 
https://crsreports.congress.gov | IF11668 · VERSION 1 · NEW