EPA Water Infrastructure Funding in the 
July 24, 2020 
American Recovery and Reinvestment Act of 
Jonathan L. Ramseur 
2009 
Specialist in Environmental 
Policy 
As part of the federal response to the “Great Recession,” Congress passed the American 
  
Recovery and Reinvestment Act of 2009 (ARRA, P.L. 111-5) to stimulate the economy and 
Elena H. Humphreys 
address a range of other policy objectives. ARRA included tax relief and incentives and provided 
Analyst in Environmental 
hundreds of billions of dollars in mandatory and discretionary spending, including funding for 
Policy 
wastewater and drinking water infrastructure projects. As Congress considers options to mitigate 
  
the economic impacts of Coronavirus Disease 2019 (COVID-19), infrastructure funding is 
receiving increased attention. ARRA implementation experience may be relevant as 
 
policymakers consider options to stimulate the economy through increased infrastructure 
spending.  
ARRA delivered wastewater and drinking water infrastructure funding primarily through two U.S. Environmental Protection 
Agency (EPA) programs—the Clean Water State Revolving Fund (CWSRF) program under the Clean Water Act (CWA) and 
the Drinking Water State Revolving Fund (DWSRF) program under the Safe Drinking Water Act (SDWA). These programs 
help publicly owned treatment works and public water systems finance infrastructure improvements needed to comply with 
water quality or public health requirements and for other statutory purposes. Using annual appropriations, EPA makes grants 
to states to capitalize state revolving loan funds. States in turn primarily provide subsidized loans to eligible recipients. 
ARRA provided $4.0 billion for the CWSRF and $2.0 billion for the DWSRF in supplemental funding in FY2009. The 
ARRA SRF funding was more than double the appropriations for FY2008.  
Congress applied several conditions to the ARRA funding for the CWSRF and DWSRF programs that differed from the 
existing statutory requirements. ARRA required states to give priority to projects that were “ready to proceed to construction 
within 12 months” of enactment, and it required that all ARRA SRF funds must be under contract or used for construction by 
February 17, 2010. ARRA required states to use at least 50% of ARRA grants to “provide additional subsidization to eligible 
recipients” and use not less than 20% of ARRA grants “for projects to address green infrastructure, water or energy 
efficiency improvements or other environmentally innovative activities.” In addition, recipients of ARRA funding were 
subject to Davis-Bacon Act wage requirements and “Buy American” provisions. Congress has applied versions of some 
ARRA requirements to the SRFs in subsequent EPA appropriations acts and through amendments to the CWA and SDWA.  
Pursuant to ARRA reporting requirements, the U.S. Government Accountability Office (GAO) reported that all 50 states met 
the 12-month deadline to have ARRA-funded projects under contract by February 17, 2010. GAO also reported that states 
met the act’s requirement to use at least 20% of the funds for green infrastructure, water and/or energy efficiency, and other 
innovative environmental projects and that states used 76% of CWSRF funds and 70% of DWSRF funds to provide 
additional subsidies (e.g., forgiveness of loan principal or grants).  
The ARRA SRF funding results and implementation experience may be relevant in the 116th Congress as policymakers 
consider legislative options to stimulate the economy and/or meet other policy objectives through increases in water 
infrastructure spending. Key considerations involve the broad policy objectives of stimulus legislation and how to efficiently 
achieve such objectives. Some policy objectives may involve trade-offs among competing priorities and may require 
differing tools for evaluation. In the case of funding wastewater and drinking water infrastructure as a means of achieving 
these or other policy goals, the practicalities of wastewater and drinking water infrastructure projects may be informative. In 
general, water infrastructure projects often involve complicated planning and construction efforts that span multiple years. 
Other policy considerations include whether to provide funding through existing programs, such as the SRF programs, or 
through new programs. Policymakers may also consider whether to apply certain requirements to the funding, as occurred 
with ARRA, and the trade-offs that may result from certain funding conditions. Although states met ARRA’s deadline and 
funding conditions, the one-year funding deadline combined with the added funding conditions presented implementation 
challenges for EPA, states, and local governments. In some cases, the ARRA funding deadline and conditions changed states’ 
SRF funding priorities for their previously ranked projects. 
Congressional Research Service 
 
 link to page 4  link to page 6  link to page 8  link to page 9  link to page 11  link to page 11  link to page 14  link to page 16  link to page 17  link to page 17  link to page 18  link to page 19  link to page 20  link to page 8  link to page 8  link to page 9  link to page 13  link to page 13  link to page 14  link to page 10  link to page 19  link to page 22 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
Contents 
Introduction ..................................................................................................................................... 1 
Background: State Revolving Fund Programs ................................................................................ 3 
ARRA Funding for the SRFs ........................................................................................................... 5 
ARRA Requirements for the SRF Programs ................................................................................... 6 
Funding Results and Implementation Experience ........................................................................... 8 
One-Year Funding Deadline ...................................................................................................... 8 
Green Reserve Requirement..................................................................................................... 11 
Additional Subsidization Requirement ................................................................................... 13 
“Buy American” Requirements ............................................................................................... 14 
Davis-Bacon Requirements ..................................................................................................... 14 
Reporting Requirements .......................................................................................................... 15 
Subsequent Changes to the SRF Programs ............................................................................. 16 
Concluding Observations .............................................................................................................. 17 
 
Figures 
Figure 1. Comparison of Water Infrastructure Capital Spending  by Level of Government 
(1957-2017) .................................................................................................................................. 5 
Figure 2. CWSRF and DWSRF Appropriations: FY2000-FY2020 ................................................ 6 
Figure 3. Cumulative Percentage of ARRA SRF Funding Based on Year of Project 
Completion ................................................................................................................................. 10 
Figure 4. Breakdown of ARRA Green Reserve Project Funding ................................................... 11 
  
Tables 
Table 1. ARRA Requirements That Applied to the SRFs ................................................................ 7 
Table 2. ARRA Requirements for States and Subsequent Changes to the SRFs ........................... 16 
  
Contacts 
Author Information ........................................................................................................................ 19 
 
Congressional Research Service 
 
EPA Water Infrastructure Funding in ARRA 
 
Introduction 
The condition of the nation’s wastewater and drinking water infrastructure and related financing 
challenges, as well as the federal role in helping communities meet those challenges, have been 
perennial subjects of debate and attention in Congress. The U.S. Environmental Protection 
Agency (EPA) estimates that the capital cost of wastewater and drinking water infrastructure 
needed to meet statutory water quality and public health requirements and objectives exceeds 
$744 billion over a 20-year period.1 A broader water infrastructure survey conducted by the 
American Water Works Association estimated that, for drinking water alone, the cost to repair 
aging infrastructure and expand water service to meet growing demand would be $1 trillion over 
20 years.2  
In the 116th Congress, Members have introduced numerous bills that would support existing and 
create new water infrastructure assistance programs. In addition, as efforts to contain the 
Coronavirus Disease 2019 (COVID-19) have contributed to economic decline and significant job 
losses, some Members from both the House and Senate have linked these and other infrastructure 
bills to future economic recovery efforts. For example, the Department of the Interior, 
Environment, and Related Agencies Appropriations Act, 2021 (H.R. 7612), would provide more 
than $10 billion in emergency supplemental appropriations for wastewater and drinking water 
infrastructure. Further, the House-passed Moving Forward Act (H.R. 2) contains provisions that 
would authorize billions of dollars in wastewater and drinking water infrastructure spending. The 
chairman of the House Committee on Energy and Commerce, Frank Pallone, linked this bill to 
economic recovery efforts, saying, “There is no better way to stimulate our economy and create 
millions of good paying jobs than to modernize our badly aging infrastructure.”3 In the Senate, 
the Committee on Environment and Public Works reported the America’s Water Infrastructure 
Act of 2020 (S. 3591) and the Drinking Water Infrastructure Act of 2020 (S. 3590) on May 11, 
2020. The committee chairman, John Barrasso, stated that these bills “will be critical to our 
economic recovery after the immediate pandemic response is behind us.”4 
                                                 
1 This estimate includes $271 billion for wastewater infrastructure and $473 billion for drinking water infrastructure. 
See EPA, Clean Watersheds Needs Survey (CWNS) Report to Congress—2012, 2016, https://www.epa.gov/cwns; and 
EPA, Drinking Water Infrastructure Needs Survey and Assessment: Sixth Report to Congress, 2018, 
https://www.epa.gov/dwsrf/what-infrastructure-needs-survey-and-assessment. 
2 American Water Works Association (AWWA), “Buried No Longer: Confronting America’s Water Infrastructure 
Challenge,” 2012, p. 3. Unlike EPA’s drinking water needs assessment, the AWWA estimate included the cost for 
additional distribution lines investments anticipated to meet projected population growth, regional population shifts, 
and service area growth through 2050, as well as the costs for investments needed for statutory compliance and for 
repairs to aging water infrastructure.  
3 House Committee on Energy and Commerce, “Pallone Applauds Passage of the Moving Forward Act,” press release, 
July 2, 2020, https://energycommerce.house.gov/newsroom/press-releases/pallone-applauds-passage-of-the-moving-
forward-act. 
4 Senate Committee on Environment and Public Works, “Barrasso: Infrastructure Will Be Critical to Economic 
Recovery After Pandemic Is Behind Us,” press release, May 6, 2020, https://www.epw.senate.gov/public/index.cfm/
press-releases-republican?ID=F22B94C0-71BB-42CB-8963-4A2EB2249DCE. 
Congressional Research Service 
1 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
As part of the federal government’s response to the “Great Recession,”5 Congress enacted the 
American Recovery and Reinvestment Act of 2009 (ARRA, P.L. 111-5) on February 17, 2009.6 
ARRA was the largest fiscal stimulus measure passed by Congress to address the economic 
impacts of the Great Recession.7 Among the purposes identified in ARRA were (1) preservation 
and creation of jobs and promotion of U.S. economic recovery and (2) investment in 
transportation, environmental protection, and other infrastructure that would provide long-term 
economic benefits.8 To support these and other policy objectives, ARRA included revenue 
provisions and provided hundreds of billions of dollars in mandatory and discretionary spending, 
including funding for infrastructure projects in transportation, energy, and other sectors.  
This report discusses the ARRA provisions regarding wastewater and drinking water 
infrastructure funding, which was delivered through the Clean Water State Revolving Fund 
(CWSRF) and Drinking Water State Revolving Fund (DWSRF) programs.9 The first section 
provides background information on the CWSRF and DWSRF programs. The second section 
discusses the ARRA funding levels provided to these two programs in the context of historical 
and recent funding levels. The third section discusses the ARRA funding requirements and how 
Congress continued to apply many of these requirements in some form to SRF funds after ARRA. 
The fourth section discusses the funding results and selected observations from EPA and states 
regarding ARRA implementation challenges.10 The final section provides concluding 
observations. 
This report does not evaluate the economic impacts associated with the increased ARRA funding 
for the CWSRF and DWSRF programs. Other studies have examined ARRA’s overall economic 
impacts, including impacts to the U.S. gross domestic product and unemployment.11 
                                                 
5 The National Bureau of Economic Research (NBER) defines a recession as “a significant decline in economic activity 
spread across the economy, lasting more than a few months, normally visible in production, employment, real income, 
and other indicators.” According to the NBER, the Great Recession began in December 2007 and ended in June 2009. 
During that time, the U.S. economy experienced its longest recession since the Great Depression of the 1930s. For 
more details, see NBER, “US Business Cycle Expansions and Contractions,” https://www.nber.org/cycles.html. 
6 For more information, see CRS Report R40537, American Recovery and Reinvestment Act of 2009 (P.L. 111-5): 
Summary and Legislative History, by Clinton T. Brass et al.  
7 Other measures included the Economic Stimulus Act of 2008 (P.L. 110-185) and the Tax Relief, Unemployment 
Insurance Reauthorization, and Job Creation Act of 2010 (P.L. 111-312). 
8 P.L. 111-5, §3. Other purposes were to assist those most impacted by the recession and to stabilize state and local 
government budgets. 
9 Various other federal programs provide financial assistance for wastewater and drinking water infrastructure. In 
particular, the U.S. Department of Agriculture’s Rural Utilities Service provides loans and grants for wastewater and 
drinking water projects in rural communities. For information on these and other water infrastructure programs, see 
CRS Report RL30478, Federally Supported Water Supply and Wastewater Treatment Programs, coordinated by 
Jonathan L. Ramseur. 
10 ARRA required the U.S. Government Accountability Office (GAO) and the inspector general offices of federal 
departments or agencies to report the use of funds. ARRA included reporting and evaluation requirements that applied 
to federal agencies as well as others. This report relies on these reports, as sources. 
11 For example, see Congressional Budget Office (CBO), “Estimated Impact of the American Recovery and 
Reinvestment Act on Employment and Economic Output in 2014,” 2014. See also CRS Report R46343, Transportation 
Infrastructure Investment as Economic Stimulus: Lessons from the American Recovery and Reinvestment Act of 2009, 
by William J. Mallett. 
Congressional Research Service 
2 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
Background: State Revolving Fund Programs 
The Clean Water Act (CWA)12 and the Safe Drinking Water Act (SDWA)13 respectively authorize 
parallel complementary financial assistance programs—the CWSRF and DWSRF—that help 
finance wastewater and drinking water infrastructure projects needed for compliance and other 
statutory purposes.14 The CWSRF program provides financial assistance to a range of eligible 
recipients—including municipalities, state agencies, and certain private and nonprofit entities—to 
support a range of eligible projects and activities. These include construction of wastewater 
treatment works and stormwater systems, management of nonpoint source pollution, and 
replacement of decentralized systems (e.g., septic tanks), among others.15 The DWSRF program 
provides assistance to community water systems and nonprofit noncommunity water systems for 
projects needed to maintain SDWA compliance or to further the act’s health protection goals, 
among other activities. Eligible projects include installation and replacement of treatment 
facilities, distribution systems, and certain storage facilities construction, among others.16  
Using annual appropriations, EPA makes grants to states to capitalize state revolving loan funds.17 
EPA allots CWSRF funds among states based on a CWA statutory formula, which provides a 
minimum share of 0.5% to each state and has effectively been in place since the beginning of the 
program in 1987.18 DWSRF state allotments are based on the proportional share of each state’s 
needs identified in the quadrennial drinking water infrastructure needs survey, except that no state 
may receive less than 1% of available funds.19 Each year, each state must match 20% of its annual 
capitalization grant and, for each SRF, develop an intended use plan (IUP) indicating how the 
allotted funds will be used.20 As outlined in their plans, states provide primarily subsidized loans 
to publicly owned treatment works (CWSRF) or public water systems (DWSRF), which reduce 
the cost of such infrastructure projects to communities. Communities repay loans into the fund, 
thus making resources available for projects in other communities. Over time, the federal grants 
and state match—combined with funds from loan repayments, leveraged bonds, and other 
                                                 
12 The statutory name is the Federal Water Pollution Control Act, as amended, codified at Title 33, Section 1251 et seq 
of the United States Code. For more information, see CRS Report RL30030, Clean Water Act: A Summary of the Law, 
by Laura Gatz. 
13 The SDWA is codified generally at Title 42, Sections 300f-300j of the U.S. Code. For more information, see CRS 
Report RL31243, Safe Drinking Water Act (SDWA): A Summary of the Act and Its Major Requirements, by Mary 
Tiemann. 
14 42 U.S.C. §300j-12. For more details regarding the history of the DWSRF, see CRS Report 96-647, Water 
Infrastructure Financing: History of EPA Appropriations, by Jonathan L. Ramseur and Mary Tiemann. 
15 33 U.S.C. §§1381-1387. For more details regarding the history of the CWSRF and its predecessor grant program in 
CWA Title II, see CRS Report 96-647, Water Infrastructure Financing: History of EPA Appropriations, by Jonathan L. 
Ramseur and Mary Tiemann. 
16 For more information, see CRS Report R45304, Drinking Water State Revolving Fund (DWSRF): Overview, Issues, 
and Legislation, by Mary Tiemann. 
17 The 50 U.S. states and Puerto Rico operate SRF programs. The CWA and SDWA require EPA to provide direct 
grants to the District of Columbia, the U.S. Virgin Islands, American Samoa, Guam, the Commonwealth of Northern 
Marianas, and Indian tribes for wastewater and drinking water infrastructure improvements (33 U.S.C. §1362 and 
§1377; 42 U.S.C. 300j-12(i) and (j)). The funding for the District of Columbia, U.S. territories, and Indian tribes is part 
of the SRF appropriations to EPA. 
18 For more information, see CRS Report RL31073, Allocation of Wastewater Treatment Assistance: Formula and 
Other Changes, by Jonathan L. Ramseur. 
19 33 U.S.C. §1384 and §1285(c); 42 U.S.C. §300j-12(a)(1)(D)(ii). 
20 33 U.S.C. §1386; 42 U.S.C. §300j-12(e). 
Congressional Research Service 
3 
 link to page 8 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
sources—are intended to generate an ongoing, revolving source of water infrastructure funding at 
the state level. 
States may also use the DWSRF and CWSRF to provide “additional subsidization”—such as 
principal forgiveness and/or negative interest loans—to disadvantaged communities to make 
projects affordable.21 In addition, states can use CWSRF grants to provide additional 
subsidization for specific types of infrastructure projects, including those that address water or 
energy efficiency.22  
Both the CWA and SDWA require states to report specific information to EPA regarding the 
implementation of their respective SRF programs. States are required to submit to EPA an annual 
report on the CWSRF and a biennial report on the DWSRF. In addition, both statutes require EPA 
to annually review states’ implementation activities and periodically audit state programs.23  
As context, while the SRF programs are the two key federal financial assistance programs for 
wastewater and drinking water infrastructure, the federal contribution of total public spending is 
less than some other “infrastructure” sectors.24 According to analysis from the Congressional 
Budget Office (CBO), state and local governments contribute the vast majority of public funding 
for wastewater and drinking water infrastructure projects.25 In CBO’s analysis, federal spending 
includes the EPA SRF programs as well as other federal programs (e.g., the U.S. Department of 
Agriculture’s Rural Utilities Service water and waste loan and grant program).26 Infrastructure 
spending analyzed by CBO includes both spending on capital (e.g., treatment plants, pipes and 
equipment) and spending on operation and maintenance (O&M) activities. In 2017, CBO data 
indicate that capital spending accounted for $31 billion and O&M spending accounted for $80 
billion in this sector.27 State and local governments contribute the vast majority of spending on 
O&M activities, as these are generally not eligible for funding by the SRF programs. Figure 1 
compares the capital spending (adjusted for inflation) on wastewater and drinking water 
infrastructure between state and local governments and the federal government. The figure 
indicates that in 2017, the state and local share of such spending was 89%, while the federal 
contribution was 11%.28 
                                                 
21 33 U.S.C. §1383(i); 42 U.S.C. §300j-12(d). 
22 33 U.S.C. §1383(i)(1)(B). 
23 42 U.S.C. §300j-12(g)(4); 33 U.S.C. §1386. 
24 CBO, Public Spending on Transportation and Water Infrastructure, 1956 to 2017, 2018, p. 22, https://www.cbo.gov/
publication/54539. 
25 CBO, Public Spending on Transportation and Water Infrastructure, 1956 to 2017, p. 22. 
26 7 U.S.C. §1926. 
27 CBO, Public Spending on Transportation and Water Infrastructure, 1956 to 2017, Supplemental Data Tables. 
28 Authorized in 1987, the CWSRF replaced the construction grant program authorized by Title II of the Clean Water 
Act Amendments of 1972 (P.L. 92-500). Title II of P.L. 92-500 authorized grants to states for wastewater treatment 
plant construction under a program administered by EPA. Federal funds were provided through annual appropriations 
under a state-by-state allocation formula contained in the act. For more information, see CRS Report 96-647, Water 
Infrastructure Financing: History of EPA Appropriations, by Jonathan L. Ramseur and Mary Tiemann. 
Congressional Research Service 
4 
 link to page 9 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
Figure 1. Comparison of Water Infrastructure Capital Spending  
by Level of Government (1957-2017) 
Does not include spending for operation and maintenance activities 
 
Source: CBO, Public Spending on Transportation and Water Infrastructure, 1956 to 2017, 2018, Supplemental Data 
Tables, https://www.cbo.gov/publication/54539. 
Notes: For details on CBO’s methodology, see CBO, Public Spending on Transportation and Water Infrastructure, 
2010, Appendix B, https://www.cbo.gov/publication/21902. 
ARRA Funding for the SRFs 
ARRA provided funding for infrastructure in a range of sectors. Depending on how one defines 
infrastructure, the aggregate infrastructure funding totaled between $100 billion and $150 
billion.29 ARRA provided $4.0 billion for the CWSRF and $2.0 billion for the DWSRF in 
FY2009. The Omnibus Appropriations Act, 2009 (P.L. 111-8), enacted on March 11, 2009, 
provided an additional $689 million for the CWSRF and $829 million for the DWSRF in 
FY2009. Therefore, the total FY2009 funding for the CWSRF was $4.7 billion and, for the 
DWSRF, was $2.8 billion. The stimulus funding for the CWSRF and DWSRF was four times 
larger and 2.5 times larger, respectively, than the FY2008 appropriations for these programs. 
Unlike regular CWSRF and DWSRF grants from EPA, ARRA waived the requirement for states 
to provide a 20% match to the federal capitalization grant.30  
As a point of comparison, from FY2000 through FY2009, annual appropriations averaged about 
$1.1 billion for the CWSRF and about $833 million for the DWSRF. Figure 2 illustrates the 
annual appropriations for the CWSRF and DWSRF programs for FY2000-FY2020, including the 
                                                 
29 For example, programs administered by the U.S. Department of Transportation received a total of $48.1 billion. 
Other public works infrastructure funding in ARRA included $4.6 billion for Army Corps of Engineers civil works 
projects and $2.5 billion for four major federal land management agencies. In addition, authority for state and local 
governments to issue tax credit bonds for capital spending represented an additional federal subsidy of about $36 
billion. For a further discussion, see CRS Report R46343, Transportation Infrastructure Investment as Economic 
Stimulus: Lessons from the American Recovery and Reinvestment Act of 2009, by William J. Mallett.  
30 ARRA provided funds to U.S. territories and the District of Columbia in a similar manner to the annual SRF 
appropriations. ARRA required EPA to reserve up to 1.5% of the appropriation for CWSRF capitalization grants for 
grants to Indian tribes.  
Congressional Research Service 
5 

Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
ARRA funding in FY2009. In nominal dollars (i.e., not adjusted for inflation), the annual 
appropriations for these programs—especially for the CWSRF—increased after ARRA. Between 
FY2010 and FY2020, the annual appropriations averaged about $1.6 billion for the CWSRF and 
about $1.0 billion for the DWSRF. 
Figure 2. CWSRF and DWSRF Appropriations: FY2000-FY2020 
Not adjusted for inflation 
 
Source: Prepared by CRS using information from annual appropriations acts, ARRA, committee reports, and 
explanatory statements presented in the Congressional Record. Amounts reflect applicable rescissions but do not 
include recent supplemental appropriations for specific locations in P.L. 116-20 and P.L. 116-113 or special 
purpose project grants (often referred to as “earmarks”), which ended in FY2011. For more information, see 
CRS Report 96-647, Water Infrastructure Financing: History of EPA Appropriations, by Jonathan L. Ramseur and Mary 
Tiemann. 
ARRA Requirements for the SRF Programs 
A key purpose of ARRA was to stimulate the economy quickly. To support this objective, 
Congress delivered wastewater and drinking water infrastructure funding through existing 
programs. In ARRA, Congress applied a range of new conditions for the funding of the CWSRF 
and DWSRF programs that differed from the SRF’s statutory requirements that applied at the 
time. As discussed below, in some cases these new funding conditions “created extensive 
challenges for EPA, states and funding recipients.”31 
In support of the act’s overarching objective to stimulate the economy, ARRA generally required 
that funds be obligated by September 30, 2010. However, the act included shorter deadlines for 
the SRF program funding. The act directed states to give priority to wastewater and drinking 
water projects that were “ready to proceed to construction within 12 months” of enactment (i.e., 
by February 17, 2010)—often described as “shovel-ready”—and required that all SRF funds must 
                                                 
31 EPA, U.S. Environmental Protection Agency (EPA) and Major Partners’ Lessons Learned from Implementing EPA’s 
Portion of the American Recovery and Reinvestment Act: Factors Affecting Implementation and Program Success: 
Funds Management, September 2013, https://www.epa.gov/sites/production/files/2015-09/documents/lessons-learned-
arra-funds-management.pdf. 
Congressional Research Service 
6 
 link to page 10 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
be under contract or construction within that time frame. Further, ARRA directed EPA to 
reallocate funds to other states if any SRF capitalization grant funds were not under contract or 
construction by February 17, 2010. As discussed below, EPA did not need to reallocate the ARRA 
funding. 
Additionally, Congress applied several new programmatic requirements to ARRA funding to 
support specific policy objectives. Among these conditions, states were required to use at least 
50% of ARRA funds for additional subsidization (e.g., grants) and 20% for “green projects.” 
Projects receiving ARRA funding were required to use American iron, steel, and manufactured 
goods32 and comply with Davis-Bacon Act prevailing wage provisions.33 Table 1 discusses these 
requirements and provides their location in ARRA. 
Table 1. ARRA Requirements That Applied to the SRFs 
ARRA Requirements 
Section/Account of P.L. 111-5 
One-Year Funding Time Frame: EPA was required to reallocate 
Division A, Title VII, State and Tribal 
ARRA SRF funding if projects were not under contract or construction 
Assistance Grants Account 
within 12 months of February 17, 2009. States were required to prioritize 
projects on their IUPs that were ready to proceed to construction within 
12 months of February 17, 2009. 
Additional Subsidization: States were required to use at least 50% of 
Division A, Title VII, State and Tribal 
ARRA grants to “provide additional subsidization to eligible recipients in 
Assistance Grants Account 
the form of forgiveness of principal, negative interest loans or grants or 
any combination of these.” 
Green Reserve: States were required to use not less than 20% of ARRA  Division A, Title VII, State and Tribal 
grants “to the extent there are sufficient eligible project applications … 
Assistance Grants Account 
for projects to address green infrastructure, water or energy efficiency 
improvements or other environmentally innovative activities.” 
Buy American: ARRA funding was available only if all iron, steel, and 
Division A, Title XVI, Section 1605 
manufactured goods used in a project were produced in the United 
States. This section allowed federal agencies, with limited exceptions and 
applied consistently with U.S. international obligations, to waive this "Buy 
American" requirement if doing so was in the public interest because 
there were insufficient American supplies or if the use of American 
supplies would have increased the cost of the project by more than 25%. 
Davis-Bacon Prevailing Wages: States were required to ensure that 
Division A, Title XVI, Section 1606 
ARRA-funded projects complied with the prevailing wage requirements of 
the Davis-Bacon Act. 
Reporting: Recipients of ARRA funds were required to submit to federal  Division A, Title XV, Sections 1512, 
agencies quarterly reports on expenditure of funds and provide job 
1514, and 1515 
creation estimates. Federal agencies were required to report on a 
quarterly basis on implementation. Inspector general offices of federal 
departments or agencies were required to report on the use of funds. 
Source: Prepared by CRS. 
In addition, ARRA included reporting and evaluation requirements that applied to federal 
agencies, state and local implementing agencies, and ARRA funding recipients. These 
requirements were intended to provide transparency and accountability for the increased 
                                                 
32 P.L. 111-5, §1605.  
33 P.L. 111-5, §1606. This section directed that all projects funded directly by or assisted in whole or in part by ARRA 
shall comply with prevailing wage requirements of the Davis-Bacon Act. 
Congressional Research Service 
7 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
spending.34 EPA was directed to submit, within 30 days of enactment, a report to the House and 
Senate Committees on Appropriations containing a general plan for expenditure of funds 
provided by the legislation and, within 90 days, another report providing detailed project-level 
information associated with the general plan. Federal agencies were required to report on a 
quarterly basis on implementation.35 Recipients of ARRA funds were required to submit to EPA 
quarterly reports on expenditure of funds and provide job creation estimates.36  
Further, ARRA required the U.S. Government Accountability Office (GAO) and the inspector 
general offices of federal departments or agencies to report on the use of funds. Inspectors general 
were required to review any concerns raised by the public about specific investments using 
ARRA funds and relay findings to department or agency heads and post the findings of such 
reviews or audits on the internet.37 GAO was required to conduct bimonthly reviews on the use of 
ARRA funds by selected states and localities.38 
Funding Results and Implementation Experience 
Pursuant to ARRA reporting directives, GAO issued multiple reports assessing ARRA 
implementation and documenting how the funds were used. In addition, EPA issued several 
“lessons learned” reports describing funding outcomes and recounting experiences and challenges 
from the states concerning implementation.  
An evaluation of the economic impacts associated with the increased ARRA funding for the 
CWSRF and DWSRF programs is beyond the scope of this report. Other studies have examined 
ARRA’s overall economic impacts, including impacts to the U.S. gross domestic product and 
unemployment.39 This section discusses the funding results and selected observations from EPA 
and states regarding ARRA implementation challenges. 
One-Year Funding Deadline 
In a 2010 report,40 GAO cited EPA as stating that all 50 states met the deadline to have ARRA-
funded projects under contract by February 17, 2010 (i.e., one year after enactment). As discussed 
above, ARRA waived the 20% state match requirement for ARRA SRF funds in order to 
“expedite the use of funds” by the recipients.41 The waived matching requirement likely 
                                                 
34 Office of Management and Budget (OMB), “Requirements for Implementing Sections 1512, 1605, and 1606 of the 
American Recovery and Reinvestment Act of 2009 for Financial Assistance Awards,” 74 Federal Register 18449, 
April 23, 2009. 
35 P.L. 111-5, Title XV, §1512. 
36 P.L. 111-5, Title XV, §1512. During ARRA implementation, the website, recovery.gov, contained recipient 
information reported on a grant-by-grant basis under EPA Recipient Reporting. EPA produced quarterly reports that 
can be found at https://archive.epa.gov/recovery/web/html/plans.html#quarterly. 
37 P.L. 111-5, Title XV, §§1514 and 1515. EPA Office of Inspector General reports are available at 
https://www.epa.gov/office-inspector-general.  
38 P.L. 111-5, Title IX, §§901 and 902. 
39 See, for example, CBO, “Estimated Impact of the American Recovery and Reinvestment Act on Employment and 
Economic Output in 2014,” 2014. See also CRS Report R46343, Transportation Infrastructure Investment as 
Economic Stimulus: Lessons from the American Recovery and Reinvestment Act of 2009, by William J. Mallett. 
40 GAO, Recovery Act: States’ and Localities’ Uses of Funds and Actions Needed to Address Implementation 
Challenges and Bolster Accountability, GAO-10-604, May 2010, https://www.gao.gov/assets/310/304678.pdf.  
41 U.S. Congress, Conference Committee, Making Supplemental Appropriations for Job Preservation and Creation, 
Infrastructure Investment, Energy Efficiency and Science, Assistance to the Unemployed, and State and Local Fiscal 
Congressional Research Service 
8 
 link to page 13 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
contributed to states meeting the one-year time frame. Without such a waiver, some states may 
have required current-year budget increases in order to provide a match, which may have needed 
state legislative approval.  
ARRA funds supported more than 3,000 water infrastructure projects.42 CWSRF projects 
included wastewater treatment, sanitary sewer overflow, and new sewers. DWSRF projects 
included construction of transmission and distribution lines and projects to treat and store 
drinking water. 
In 2011, GAO reported that two years after ARRA enactment, states had drawn down from the 
Treasury approximately 80% of the CWSRF funding and 83% of the DWSRF funding of the 
ARRA provided funds.43 This may indicate that, in some circumstances, a project that met the 
ARRA time frame for contracting may still have been months away from actual construction or 
implementation. Specific ARRA-funded projects likely had varying time frames for construction. 
Wastewater and drinking water projects can take multiple years to complete. Figure 3 illustrates 
the rate at which ARRA-funded projects were completed under the CWSRF and DWSRF 
programs. As the figure indicates, at the end of FY2013, funding recipients had completed 66% of 
the CWSRF projects and 83% of the DWSRF projects funded through ARRA.44 Certain ARRA-
funded projects, such as water meter installations, may have had shorter timelines than other 
ARRA-funded projects, such as water treatment plant construction or sewer line replacement. 
                                                 
Stabilization, for Fiscal Year Ending September 30, 2009, and for other Purposes, conference report to accompany H.R. 
1, 111th Cong., 1st sess., H.Rept. 111-16 (Washington, DC: GPO, 2009), p. 443. 
42 GAO, Recovery Act: Funds Supported Many Water Projects, and Federal and State Monitoring Shows Few 
Compliance Problems, GAO-11-608, June 2011, https://www.gao.gov/assets/330/320224.pdf.  
43 GAO, Recovery Act: Funds Supported Many Water Projects. 
44 EPA’s website contained such quarterly reporting through the fourth quarter of 2013. See EPA, American Recovery 
and Reinvestment Act, Quarterly Performance Report, FY2013 Quarter 4, 2013, https://archive.epa.gov/recovery/web/
html/. 
Congressional Research Service 
9 

Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
Figure 3. Cumulative Percentage of ARRA SRF Funding Based on Year of Project 
Completion 
As of September 30, 2013 
 
Source: Prepared by CRS with data from EPA, American Recovery and Reinvestment Act, Quarterly Performance 
Report, FY2013 Quarter 4, 2013, https://archive.epa.gov/recovery/web/html/. 
Both EPA and GAO reported that the added requirements for ARRA funds and the statutory 
deadline for contracting changed states’ SRF funding priorities. In some cases, the changes 
resulted in previously prioritized projects being bypassed for the projects that were consistent 
with ARRA funding conditions. For example, states reported postponing projects with greater 
environmental or public health benefits in favor of projects that could meet the 12-month 
contracting deadline. In addition, an EPA report stated that the one-year deadline “made it 
difficult for water projects to take advantage of green infrastructure or innovative technology 
options.”45 According to this report, these ARRA requirements were complex, EPA clarified 
guidance as questions arose to address implementation issues, and the workload for states and 
EPA associated with the mandates alone was significant.  
In addition, EPA stated that the scale of funding provided by ARRA and the associated 
requirements, including the one-year time frame for contracting, posed significant workload 
challenges for states and EPA.46 Relatedly, the 2011 GAO report found that “the deadline was the 
single most important factor hindering the ability of [economically disadvantaged communities] 
from receiving funding … because these communities typically do not have funds to plan and 
develop projects.” 
                                                 
45 EPA, U.S. Environmental Protection Agency (EPA) and Major Partners’ Lessons Learned from Implementing EPA’s 
Portion of the American Recovery and Reinvestment Act: Factors Affecting Implementation and Program Success, A 
Summary of Six Specific Reports, September 2013, p. 21, https://www.epa.gov/sites/production/files/2015-09/
documents/lessons-learned-arra-six-report-summary.pdf. The Science Applications International Corporation 
conducted these assessments on behalf of EPA. 
46 EPA, Lessons Learned: A Summary of Six Specific Reports, p. 2. 
Congressional Research Service 
10 
 link to page 14 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
Green Reserve Requirement 
ARRA required states to use at least 20% of the funds be reserved for “green” projects. Although 
GAO reported that states met (or exceeded) this requirement, this funding requirement presented 
implementation challenges. ARRA identified general categories of green reserve projects, 
including “green infrastructure, water or energy efficiency improvements or other 
environmentally innovative activities.” As illustrated in Figure 4, expenditures involving energy 
efficiency in the CWSRF and water efficiency in the DWSRF accounted for more than half of the 
green reserve projects funded by ARRA. The wastewater sector offers a wider range of project 
opportunities to improve energy efficiency (particularly at wastewater treatment plants) and more 
opportunities for “green” infrastructure (e.g., stormwater runoff reduction projects). As discussed 
below, most of the DWSRF water efficiency projects supported by ARRA funding were water 
meter installations.  
Figure 4. Breakdown of ARRA Green Reserve Project Funding 
Dollars in millions 
 
Source: Reproduced from GAO, Recovery Act: Funds Supported Many Water Projects, and Federal and State 
Monitoring Shows Few Compliance Problems, GAO-11-609, June 2011, https://www.gao.gov/assets/330/320224.pdf.  
As with many of the other ARRA funding conditions, the green reserve provision was a new 
requirement for both EPA and state agencies, as the SRF provisions in the CWA and SDWA did 
not require a portion of funds to be used for “green” projects. The green reserve provision in 
ARRA included general categories of project types; it did not include definitions for the terms or 
categories (e.g., green infrastructure and environmentally innovative activities). Consequently, 
state agencies were uncertain as to which projects would satisfy the green reserve condition. EPA 
published guidance that addressed green project reserve eligibilities on March 2, 2009, and 
subsequently issued four additional documents to clarify its initial guidance on green project 
reserve.47 A 2010 inspector general report found that a lack of clear EPA guidance on the “green 
                                                 
47 EPA, Lessons Learned: Funds Management, p. 62. 
Congressional Research Service 
11 
 link to page 14 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
requirement” caused confusion and disagreements as to which projects were eligible.48 In 
addition, according to the 2011 GAO report, “in certain cases state officials said they had to 
choose between a green water project and a project that was otherwise ranked higher to address 
water quality problems.” That is, states selected “green projects” over projects that were 
prioritized for SRF financial assistance based on compliance with water quality or public health 
requirements. 
To receive an ARRA capitalization grant, states were required to submit an IUP reflecting the 
green project reserve and other ARRA funding requirements.49 In contrast to ARRA, the CWA 
and SDWA criteria for SRF project prioritization emphasized compliance, water quality or public 
health benefits, and economic need and did not target “green” infrastructure projects 
specifically.50 Given the one-year time frame, EPA encouraged states to use their existing IUPs to 
identify projects that would be eligible for the ARRA green reserve. Most states did not have a 
sufficient number of conforming projects in their existing IUPs to fulfill the 20% “green 
reserve.”51 In the absence of sufficient projects, EPA required states to issue solicitations for green 
project applications.52 Several states reported re-issuing solicitations for green projects after EPA 
clarified its initial guidance,53 which resulted in further implementation delays. Some 38 states 
had to conduct additional solicitations to attract clean water “green” projects, and 35 states had to 
solicit to attract drinking water green reserve projects.54 To attract participation, 15 states offered 
100% subsidization for clean water green projects.55  
The green reserve requirement was particularly challenging under the DWSRF program, which is 
focused on public health. In general, state agencies implementing DWSRFs had fewer project 
options to satisfy the green reserve conditions than did agencies implementing CWSRF 
programs.56 This is, in part, due to the CWSRF project eligibilities, as some green projects more 
directly support the environmental quality objectives of the CWA.57 As Figure 4 indicates, water 
efficiency projects accounted for the majority of green reserve projects in the DWSRF, and “new 
water meters in previously unmetered areas [accounted] for a substantial percentage of these 
                                                 
48 EPA, Office of Inspector General, EPA Needs Definitive Guidance for Recovery Act and Future Green Reserve 
Projects, 2010, https://www.epa.gov/sites/production/files/2015-11/documents/20100201-10-r-0057.pdf. 
49 EPA, Award of Capitalization Grants with Funds Appropriated by P.L. 111-5, the “American Recovery and 
Reinvestment Act of 2009,” March 2, 2009. 
50 EPA, U.S. Environmental Protection Agency (EPA) and Major Partners’ Lessons Learned from Implementing EPA’s 
Portion of the American Recovery and Reinvestment Act: Factors Affecting Implementation and Program Success: 
Green Project Reserve, September 2013, p. 2, https://www.epa.gov/sites/production/files/2015-09/documents/lessons-
learned-arra-green-project-reserve.pdf. 
51 EPA, Office of Inspector General, EPA Needs Definitive Guidance for Recovery Act and Future Green Reserve 
Projects. 
52 EPA, Award of Capitalization Grants with Funds Appropriated by P.L. 111-5. 
53 EPA, Office of Inspector General, EPA Needs Definitive Guidance for Recovery Act and Future Green Reserve 
Projects. 
54 EPA, Office of Inspector General, EPA Needs Definitive Guidance for Recovery Act and Future Green Reserve 
Projects. 
55 EPA, ARRA: Clean Water State Revolving Fund Green Project Reserve Report, June 2012, p. 8, 
https://nepis.epa.gov/Exe/ZyPURL.cgi?Dockey=P100MF4Y.txt. 
56 EPA, Award of Capitalization Grants with Funds Appropriated by P.L. 111-5. States could submit a business case 
for projects not specifically identified in the guidance. At least one state reported that it forewent the business case 
option for green projects due to the one-year time frame. 
57 At the time, the CWSRF eligible uses included treatment works construction (e.g., sewer and stormwater systems), 
nonpoint source management program implementation (e.g., infrastructure to address nonpoint discharges and 
stormwater runoff), and national estuary plan implementation.  
Congressional Research Service 
12 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
water efficiency projects.”58 These water meter installation projects helped states achieve their 
“green reserve” funding requirement for the DWSRF and meet the one-year time frame for 
contracting. As stated by EPA, “water meter projects were quickly able to meet shovel-ready 
status, as compared to projects that involve intensive planning, such as water and wastewater 
treatment.”59 
Additional Subsidization Requirement 
ARRA required states to use at least 50% of their allotment of funds for the SRFs as additional 
subsidization (e.g., forgiveness of principal, negative interest loans, or grants). According to the 
ARRA conference report: 
[T]his  provision  provides  relief  to  communities  by  requiring  a  greater  Federal  share  for 
local  clean  and  drinking  water  projects  and  provides  flexibility  for  States  to  reach 
communities that would otherwise not have the resources to repay a loan with interest.60  
States exceeded the requirement that 50% of the funds be provided as additional subsidies. Of the 
total ARRA funds awarded, GAO reported that states provided 76% of CWSRF funds and 70% of 
DWSRF as additional subsidies (e.g., forgiveness of principal or grants).61  
State approaches to the additional subsidization requirements for ARRA funds varied. Under 
SDWA, states have discretion to offer additional subsidization in their DWSRF programs. While 
some states had offered additional subsidization prior to ARRA, other states had to adopt 
legislative changes to authorize SRF programs to provide assistance other than loans.62 Other 
states emphasized loans in order to build the “revolving” capacity of their DWSRFs.  
Some states opted to offer 100% of ARRA funds in principal forgiveness.63 One state reported 
that additional subsidization expedited the contracting process as applicants did not have to 
complete credit reviews.64 In the long term, as subsidy recipients do not repay funds to the SRF, 
offering 100% of ARRA funds as subsidies limits the future availability of repayments for loans 
for other infrastructure projects. On the other hand, ARRA’s additional subsidization requirement 
was intended to support water infrastructure projects in communities that otherwise may not have 
the resources to repay a loan with interest.65 
                                                 
58 EPA, Drinking Water State Revolving Fund, Green Project Reserve Funding Status, 2010. 
59 EPA, Lessons Learned: Green Project Reserve. 
60 U.S. Congress, Conference Committee, Making Supplemental Appropriations for Job Preservation and Creation, 
Infrastructure Investment, Energy Efficiency and Science, Assistance to the Unemployed, and State and Local Fiscal 
Stabilization, for Fiscal Year Ending September 30, 2009, and for other Purposes, conference report to accompany H.R. 
1, 111th Cong., 1st sess., H.Rept. 111-16 (Washington, DC: GPO, 2009), p. 443. 
61 GAO, Recovery Act: Funds Supported Many Water Projects, and Federal and State Monitoring Shows Few 
Compliance Problems. 
62 EPA, Lessons Learned: Funds Management, p. 29. 
63 EPA, Lessons Learned: Funds Management, p. 34. 
64 EPA, Lessons Learned: Funds Management, p. 33. 
65 U.S. Congress, Conference Committee, Making Supplemental Appropriations for Job Preservation and Creation, 
Infrastructure Investment, Energy Efficiency and Science, Assistance to the Unemployed, and State and Local Fiscal 
Stabilization, for Fiscal Year Ending September 30, 2009, and for other Purposes, conference report to accompany H.R. 
1, 111th Cong., 1st sess., H.Rept. 111-16 (Washington, DC: GPO, 2009), p. 443. 
Congressional Research Service 
13 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
“Buy American” Requirements 
Congress required the use of American-produced iron, steel, and manufactured goods in projects 
that received ARRA funding.66 As with some of the other ARRA funding requirements, EPA and 
the states had little previous experience implementing these funding conditions.67 In April 2009, 
the Office of Management and Budget (OMB) published government-wide guidance in the 
Federal Register to assist agencies in implementing this and other ARRA requirements.68 Several 
days later, EPA issued its guidance for implementing the “Buy American” requirements under the 
SRF programs.69 EPA subsequently published additional clarifying guidance documents, some of 
which were revised on several occasions.70  
According to an EPA study, although participant support for the “concept of buying American-
made products was strong … participants noted many instances in which the Buy American 
requirements were so resource intensive and time consuming that projects were delayed simply to 
meet the requirement.”71 
As states used their existing IUPs to identify projects, such project applications had to be 
amended to include the ARRA “Buy American” requirements, which may have contributed to 
delays in contracting.72 Some project funding recipients sought waivers of these requirements, 
which EPA could grant on a project-by-project basis.73 EPA found that offering a waiver for a 
product (e.g., wind turbine) rather than a project may have assisted with a more expeditious 
obligation of funds.74  
Davis-Bacon Requirements 
A number of state agency officials had prior experience with the Davis-Bacon provisions, as these 
labor requirements applied to CWSRF projects in the beginning years of the program (FY1989-
                                                 
66 P.L. 111-5, §1605. None of the funds appropriated or made available by ARRA were to be used for construction, 
alteration, maintenance, or repair projects unless all of the iron, steel, and manufactured goods used in the project were 
produced in the United States, with certain exceptions. 
67 GAO, Recovery Act: States’ and Localities’ Uses of Funds and Actions Needed to Address Implementation 
Challenges and Bolster Accountability. 
68 OMB, “Requirements for Implementing Sections 1512, 1605, and 1606 of the American Recovery and Reinvestment 
Act of 2009 for Financial Assistance Awards,” 74 Federal Register 18449, April 23, 2009. 
69 EPA, Memorandum to Regional Directors, “Implementation of Buy American provisions of P.L. 111-5, the 
‘American Recovery and Reinvestment Act of 2009,’” April 28, 2009. 
70 EPA, “Buy American Provisions of ARRA Section 1605, Questions and Answers,” Part 1, July 2, 2009 (revised 
September 22, 2009 and May 27, 2010). 
71 EPA, Lessons Learned: Funds Management, p. 45. 
72 EPA, Lessons Learned: Funds Management. 
73 See for example, EPA, “Notice of a Regional Project Waiver of Section 1605 (Buy American) of the American 
Recovery and Reinvestment Act of 2009 (ARRA) to the Town of Falmouth, MA,” 75 Federal Register 22129-22131, 
April 27, 2010. 
74 EPA, Lessons Learned: Funds Management. 
Congressional Research Service 
14 
Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
FY1995) and in the CWA Title II Construction Grants program (the precursor to the CWSRF 
program).75 In addition, some states had experience with their own fair labor wage standards.76  
Some stakeholders observed that Davis-Bacon and other ARRA mandates hindered the “the push 
to obligate and spend funds quickly.”77 Part of the implementation challenge may have been due 
to uncertainty regarding the requirements. According to an EPA report, “all states and funding 
recipients complained about the onerous and confusing Davis-Bacon process.”78 Applications for 
SRF funding from states’ existing IUPs had to be amended to include the Davis-Bacon 
requirements, which further challenged efforts to use existing projects from state IUPs to meet the 
one-year time frame for contracting.79 In addition, some states identified eligible parties who 
chose not to apply for or withdrew from the ARRA funding process due to the additional costs 
related to the ARRA funding requirements, such as the Davis-Bacon requirements.80 
Reporting Requirements 
As discussed above, ARRA required quarterly reporting from federal agencies that were in charge 
of implementing ARRA funding programs. States were required to submit weekly reports on 
usage of ARRA funds, and EPA published weekly reports to a website specifically for ARRA.81 
Some states noted the importance of transparency and publicly available data. Others questioned 
the utility of the added reporting data, observing that the data they were providing under the SRF 
program was broadly duplicative to existing SRF reporting requirements.  
ARRA also required recipients of funds to provide quarterly reports on spending details and 
estimates of job creation provided by the ARRA funding. In general, states conducted the 
recipient reporting requirements for the SRF programs. While most of the required data elements 
were relatively “straightforward and familiar,” state officials noted that the ARRA requirement to 
report jobs data, coupled with quarterly deadlines, presented implementation challenges for the 
states.82 In addition, the OMB guidance describing the method for calculating jobs data changed 
several times during ARRA implementation.83 States noted that these changes led to confusion 
and required additional time to implement, as the new guidance was discussed among EPA 
regions, states, and local recipients.84 
                                                 
75 Prior to ARRA, the CWA contained Davis-Bacon requirements for CWSRF projects that were constructed before 
FY1995 (33 U.S.C. §1382(b)(6) as in effect before the Water Resources Reform and Development Act of 2014 
changes). Some policymakers and stakeholders sought to apply Davis-Bacon provisions to CWSRF projects after 
FY1995. For more information on the history of these provisions and developments, see CRS Report R41469, Davis-
Bacon Prevailing Wages and State Revolving Loan Programs Under the Clean Water Act and the Safe Drinking Water 
Act, by Gerald Mayer and Jon O. Shimabukuro. In addition, state officials may have encountered these requirements 
while managing other government-funded construction projects. 
76 EPA, Lessons Learned: Funds Management. 
77 EPA, Lessons Learned: A Summary of Six Specific Reports. 
78 EPA, Lessons Learned: Funds Management. 
79 EPA, Lessons Learned: Funds Management. 
80 GAO, Recovery Act: Funds Supported Many Water Projects, and Federal and State Monitoring Shows Few 
Compliance Problems. 
81 EPA, Award of Capitalization Grants with Funds Appropriated by P.L. 111-5, the “American Recovery and 
Reinvestment Act of 2009.” 
82 EPA, Lessons Learned: Funds Management. 
83 EPA, Lessons Learned: Funds Management. 
84 EPA, Lessons Learned: Funds Management. 
Congressional Research Service 
15 
 link to page 19  link to page 20  link to page 20 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
Subsequent Changes to the SRF Programs 
In the years following ARRA, Congress has variously applied versions of ARRA requirements to 
the SRF programs in specific years through appropriations acts and, in some cases, has 
incorporated similar provisions into the underlying statutes. These requirements and the 
subsequent changes to the CWSRF and DWSRF are identified in Table 2.  
Table 2. ARRA Requirements for States and Subsequent Changes to the SRFs 
ARRA Requirements 
Subsequent Changes 
 
CWSRF 
DWSRF 
Additional Subsidization: 
Appropriations acts subsequent to ARRA 
SDWA had authorized, but not 
States were required to use 
regularly required 10% of the CWSRF 
required, states to use up to 30% of 
at least 50% of ARRA grants 
grants to be used for additional 
their capitalization grants to 
to “provide additional 
subsidization. 
provide additional subsidies to 
subsidization to eligible 
The Water Resources Reform and 
disadvantaged communities. 
recipients in the form of 
Development Act of 2014 (WRRDA 
Appropriations acts subsequent to 
forgiveness of principal, 
2014, P.L. 113-121) amended the CWA to  ARRA regularly required states to 
negative interest loans or 
authorize states to provide additional 
use 20% of their capitalization 
grants or any combination of  subsidization under certain conditions and  grants for additional subsidies.b 
these.” 
limitations.a 
America’s Water Infrastructure Act 
of 2018 (AWIA 2018, P.L. 115-270) 
amended the DWSRF provisions of 
SDWA to increase the portion 
(from 30% to 35%) of a state's 
capitalization grant that states may 
dedicate to additional subsidization 
while conditionally requiring states 
to use at least 6% of their grants for 
these subsidies.  
Green Reserve: States 
Appropriations acts subsequent to ARRA 
Starting with the FY2012 
were required to use not less  have included provisions requiring a 
appropriations act, states, at their 
than 20% of ARRA grants “to 
percentage of CWSRF grants be used for 
own discretion, could use DWSRF 
the extent there are sufficient  such projects. Since the FY2012 
grants for green infrastructure 
eligible project applications 
appropriations act, subsequent 
projects. 
… for projects to address 
appropriations acts have required 10% of 
green infrastructure, water 
the grants be used for this purpose. 
or energy efficiency 
WRRDA 2014 expanded CWSRF project 
improvements or other 
eligibility to specifically include some 
environmentally innovative 
“green reserve” projects (e.g., energy and 
activities.”  
water efficiency). 
Buy American: ARRA 
Appropriations acts subsequent to ARRA 
Appropriations acts subsequent to 
funding was available only if 
have included provisions requiring 
ARRA have included provisions 
all iron, steel, and 
CWSRF-financed projects to comply with 
requiring DWSRF-financed projects 
manufactured goods used in a  narrower requirements to use American 
to comply with narrower AIS 
project were produced in the  iron and steel (AIS). 
requirements.  
United States.  
WRRDA 2014 added AIS requirements to  In 2016, the Water Infrastructure 
CWSRF provisions of the CWA. 
Improvements for the Nation Act 
(P.L. 114-322) amended SDWA 
DWSRF provisions to apply AIS 
requirements for FY2017.  
AWIA 2018 amended the DWSRF 
provisions to renew the AIS 
requirements for FY2019-FY2023. 
Congressional Research Service 
16 
 link to page 20 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
ARRA Requirements 
Subsequent Changes 
 
CWSRF 
DWSRF 
Davis-Bacon Prevailing 
In the Consolidated Appropriations Act, 
In the Consolidated Appropriations 
Wages: States were 
2012 (P.L. 112-74), Congress applied 
Act, 2012, Congress applied Davis-
required to ensure that 
Davis-Bacon prevailing wage requirements  Bacon prevailing wage requirements 
ARRA-funded projects 
to CWSRF program funding for FY2012 
to DWSRF program funding for 
complied with the prevailing 
and all future years.c 
FY2012 and all future years. 
wage requirements of the 
WRRDA 2014 added Davis-Bacon 
AWIA 2018 amended the SDWA 
Davis-Bacon Act. 
prevailing wage to CWSRF provisions. 
DWSRF provisions to add Davis-
Bacon prevailing wage 
requirements.  
Source: Prepared by CRS. 
a.  WRRDA 2014 added CWA Section 603(i) to authorize states to provide additional subsidization to 
municipalities and other eligible entities that meet affordability criteria or other specified conditions. States 
may provide additional subsidization “only if the total amount appropriated for making capitalization grants 
to all States under this title for the fiscal year exceeds $1,000,000,000.” With limitations, states may 
generally use as much as 30% of their annual capitalization grant for providing additional subsidization.  
b.  Since the DWSRF program was established in 1996, states were authorized, but not required, to provide up 
to 30% of their capitalization grants as additional subsidization to disadvantaged communities (42 U.S.C. 
§300j-12(d)).  
c.  At the time ARRA was enacted, the CWA contained Davis-Bacon requirements that applied to CWSRF 
projects constructed before FY1995 (see the provisions in 33 U.S.C. §1382(b)(6)) before they were 
amended by WRRDA 2014. Some policymakers and stakeholders sought to apply Davis-Bacon provisions to 
CWSRF projects after FY1995. For more information on the history of these provisions and developments, 
see CRS Report R41469, Davis-Bacon Prevailing Wages and State Revolving Loan Programs Under the Clean 
Water Act and the Safe Drinking Water Act, by Gerald Mayer and Jon O. Shimabukuro. 
Concluding Observations 
To address the economic impacts of the Great Recession, ARRA provided hundreds of billions of 
dollars in mandatory and discretionary spending delivered through both new and existing 
programs. A primary objective of ARRA was economic stimulus to preserve and create jobs. To 
support this objective, ARRA provided funding for infrastructure in a range of sectors, including 
$6 billion in supplemental appropriations for the CWSRF and DWSRF programs. Congress may 
consider the degree to which funding such projects would help achieve their specific policy goals. 
Whether federal dollars could provide more of a stimulus by supporting other economic policy 
tools (e.g., tax cuts) is beyond the scope of this report. Below are several points involving the 
experience with ARRA specific to the EPA SRF programs that may be informative for 
policymakers considering future economic stimulus measures. 
In contrast to the CWSRF and DWSRF capitalization grants provided through annual 
appropriations, ARRA SRF funds did not require a 20% match from the states. This waiver likely 
contributed to states’ success in meeting the one-year contracting requirement. Without the 
waiver, some states may have required current-year budget increases in order to provide a match, 
which would have generally required state legislative approval. Without the ARRA waiver, the 
20% state match may have leveraged an additional $1.2 billion for the SRF programs above the 
appropriated amount in ARRA. If policymakers consider substantial funding increases for the 
SRF programs in future stimulus proposals, a state-match waiver may raise issues for 
consideration, including the feasibility of states to provide additional funds within a fiscal year 
and the trade-off between the increased amount of available funds provided by a state 
contribution and the spending time frame. During the Great Recession, states may not have had 
Congressional Research Service 
17 
 link to page 19 Wastewater and Drinking Water Infrastructure Funding in ARRA 
 
sufficient funds to match ARRA’s funding due to reduced revenue from state tax sources and/or 
potential limitations on borrowing from state-level balanced budget requirements.  
In addition to the one-year contracting deadline, ARRA funding included several new conditions 
and priorities that differed from the existing statutory requirements. Subsequent to ARRA, 
Congress applied versions of many of the ARRA funding requirements to the SRF programs 
through appropriations acts and, subsequently, through amendments to the underlying statutes 
(see Table 2). State and federal SRF program administrators now have more than a decade of 
experience implementing many of the funding conditions included in ARRA, although some of 
the details of the conditions have changed over time. For example, both SRFs now include a 
narrower requirement to use American-made iron and steel products in SRF funded projects, with 
certain exceptions. Davis-Bacon prevailing wage requirements now apply to projects receiving 
assistance from either SRF. In terms of the green reserve condition, annual appropriations 
provisions have directed states to use a percentage (e.g., 10% in the Further Consolidated 
Appropriations Act, 2020 [P.L. 116-94]) of their CWSRF capitalization grants for “green” 
projects, while under the DWSRF program, states have discretionary authority to finance such 
projects.  
Although states met ARRA’s deadline and funding conditions, stakeholders reported that the one-
year contracting deadline combined with the added funding conditions presented substantial 
implementation challenges for EPA, states, and local governments. For example, according to one 
report, “it took a tremendous amount of extra effort from all stakeholders to attain EPA’s ARRA 
goals.”85 In addition to the implementation challenges, in some cases the ARRA funding deadline 
and funding conditions altered states’ SRF funding priorities (at least temporarily) for their 
previously ranked projects or selected projects needed for compliance with water quality or 
public health requirements.  
The ARRA SRF funding results and implementation experience may be relevant in the 116th 
Congress as policymakers consider legislative options to stimulate the economy and/or meet other 
policy objectives through increases in water infrastructure spending. Considerations involve the 
broad policy objectives of stimulus legislation and how to efficiently achieve such objectives, 
perhaps while supporting other policy goals, including statutory priorities such as protecting 
public health and environment and infrastructure assistance. Policy options to achieve certain 
objectives vary and may depend on the degree and nature of the economic impacts being 
addressed (e.g., recovery from COVID-19-related economic impacts). Some policy objectives 
may involve trade-offs among competing priorities and may require differing tools for evaluation. 
In the case of funding wastewater and drinking water infrastructure as a means of achieving 
policy goals, the practicalities of wastewater and drinking water infrastructure projects may be 
relevant. In general, water infrastructure projects often involve complicated planning and 
construction efforts that span multiple years. Regarding the objective of quickly stimulating the 
economy, one consideration is whether to provide funding through existing programs, such as the 
SRF programs, or through new programs. For existing programs, a consideration is whether or 
how to apply new conditions to the funding to further certain policy objectives, as occurred with 
ARRA. If funding were to be delivered through new programs, various considerations―program 
structure, development time frames, rulemakings, or other related implementation 
considerations―may arise.  
                                                 
85 EPA, Lessons Learned: A Summary of Six Specific Reports, p. 2. 
Congressional Research Service 
18 
EPA Water Infrastructure Funding in ARRA 
 
 
Author Information 
 
Jonathan L. Ramseur 
  Elena H. Humphreys 
Specialist in Environmental Policy 
Analyst in Environmental Policy 
    
    
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan 
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and 
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other 
than public understanding of information that has been provided by CRS to Members of Congress in 
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not 
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in 
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or 
material from a third party, you may need to obtain the permission of the copyright holder if you wish to 
copy or otherwise use copyrighted material. 
 
Congressional Research Service  
R46464 · VERSION 1 · NEW 
19