Navy Force Structure and Shipbuilding Plans:
Background and Issues for Congress

December 16, 2019
Congressional Research Service
https://crsreports.congress.gov
RL32665




Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Summary
The current and planned size and composition of the Navy, the rate of Navy ship procurement,
and the prospective affordability of the Navy’s shipbuilding plans have been oversight matters for
the congressional defense committees for many years.
On December 15, 2016, the Navy released a force-structure goal that calls for achieving and
maintaining a fleet of 355 ships of certain types and numbers. The 355-ship force-level goal is the
result of a Force Structure Assessment (FSA) conducted by the Navy in 2016. A new FSA—
referred to as the Integrated Naval FSA (INFSA), with the term naval referring to both the Navy
and Marine Corps (i.e., the two naval services)—is now underway as the successor to the 2016
FSA. The Acting Secretary of the Navy states that he expects the INFSA to be published no later
than January 15, 2020.
Statements from Department of the Navy (DON) officials suggest that the INFSA could result in
a once-in-a-generation change in the Navy’s fleet architecture, meaning the mix of ships that
make up the Navy and how those ships are combined into formations and used to perform various
missions. DON officials suggest that the INFSA could shift the fleet to a more distributed
architecture that includes a reduced proportion of larger ships, an increased proportion of smaller
ships, and a newly created category of large unmanned surface vehicles (USVs) and large
unmanned underwater vehicles (UUVs). Such a change in fleet architecture could alter, perhaps
substantially, the mix of ships to be procured for the Navy and the distribution of Navy
shipbuilding work among the nation’s shipyards.
The Navy’s proposed FY2020 budget requests funding for the procurement of 12 new ships,
including one Gerald R. Ford (CVN-78) class aircraft carrier, three Virginia-class attack
submarines, three DDG-51 class Aegis destroyers, one FFG(X) frigate, two John Lewis (TAO-
205) class oilers, and two TATS towing, salvage, and rescue ships. The Navy’s FY2020 five-year
(FY2020-FY2024) shipbuilding plan includes 55 new ships, or an average of 11 new ships per
year.
The Navy’s FY2020 30-year (FY2020-FY2049) shipbuilding plan includes 304 ships, or an
average of about 10 per year. If the FY2020 30-year shipbuilding plan is implemented, the Navy
projects that it will achieve a total of 355 ships by FY2034. This is about 20 years sooner than
projected under the Navy’s FY2019 30-year shipbuilding plan—an acceleration primarily due to
a decision announced by the Navy in April 2018, after the FY2019 plan was submitted, to
increase the service lives of all DDG-51 destroyers to 45 years. Although the Navy projects that
the fleet will reach a total of 355 ships in FY2034, the Navy in that year and subsequent years
will not match the composition called for in the FY2016 FSA.
One issue for Congress is how the INFSA will change the Navy’s fleet architecture, the Navy’s
current 355-ship force-level goal, the mix of Navy ships to be procured, and the distribution of
Navy shipbuilding work among the nation’s shipyards. A related issue for Congress is the degree
to which the results of the INFSA will be incorporated into the Navy’s proposed FY2020 budget,
and how Congress should assess the Navy’s proposed FY2020 budget if additional aspects of the
INFSA will not become clear until the Navy submits its proposed FY2022 budget or its proposed
FY2023 budget. Another issue for Congress concerns the prospective affordability of the Navy’s
30-year shipbuilding plan. Another issue for Congress concerns the potential impacts on FY2020
Navy shipbuilding programs of using one or more continuing resolutions to fund DOD operations
for at least some portion of FY2020. Decisions that Congress makes regarding Navy force
structure and shipbuilding plans can substantially affect Navy capabilities and funding
requirements and the U.S. shipbuilding industrial base.
Congressional Research Service

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress


Congressional Research Service

link to page 6 link to page 7 link to page 7 link to page 7 link to page 7 link to page 8 link to page 8 link to page 8 link to page 8 link to page 8 link to page 10 link to page 12 link to page 14 link to page 16 link to page 16 link to page 16 link to page 17 link to page 19 link to page 20 link to page 20 link to page 21 link to page 22 link to page 25 link to page 25 link to page 25 link to page 25 link to page 25 link to page 25 link to page 26 link to page 27 link to page 27 link to page 29 link to page 31 link to page 31 link to page 32 link to page 32 link to page 32 link to page 34 link to page 35 link to page 39 link to page 39 link to page 40 link to page 42 link to page 42 link to page 45 link to page 52 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Contents
Introduction ..................................................................................................................................... 1
Background ..................................................................................................................................... 2
Navy’s 355-Ship Ship Force-Structure Goal ............................................................................ 2
Introduction ......................................................................................................................... 2
355-Ship Goal Resulted from 2016 Force Structure Assessment (FSA) ............................ 2
355-Ship Goal Made U.S. Policy by FY2018 NDAA ........................................................ 3
Large Unmanned Vehicles and Navy Ship Count ............................................................... 3

New FSA Now Underway Could Change Fleet Architecture and Distribution of
Shipbuilding Work ................................................................................................................. 3
Overview ............................................................................................................................. 3
Potential New Surface Combatant Force Architecture ....................................................... 5
Potential New Amphibious Ship Architecture .................................................................... 7
Potential New Aircraft Carrier/Naval Aviation Force Architecture .................................... 9
Potential New Combat Logistics Force (CLF) Architecture .............................................. 11
Potential New Undersea Force Architecture ...................................................................... 11
Rationale for a More Distributed Fleet Architecture ......................................................... 11
Distributed Maritime Operations (DMO) ......................................................................... 12
Expeditionary Advanced Base Operations (EABO) ......................................................... 14
Navy’s Five-Year and 30-Year Shipbuilding Plans ................................................................. 15
FY2020 Five-Year (FY2020-FY2024) Shipbuilding Plan ................................................ 15
FY2020 30-Year (FY2020-FY2049) Shipbuilding Plan ................................................... 16
Projected Force Levels Under FY2020 30-Year Shipbuilding Plan ................................. 17
Issues for Congress ........................................................................................................................ 20
How INFSA Will Change Fleet Architecture, 355-Ship Goal, Mix of Ships to Be
Procured, and Distribution of Shipbuilding Work................................................................ 20
Degree to Which INFSA Is Incorporated into FY2020 Budget .............................................. 20
Affordability of 30-Year Shipbuilding Plan ............................................................................ 20

Overview ........................................................................................................................... 20
Concern Regarding Potential Impact of Columbia-Class Program .................................. 21
Potential for Cost Growth on Navy Ships ......................................................................... 22
CBO Estimate ................................................................................................................... 22
Sustainment Cost .............................................................................................................. 24
Recent Navy Statements About Not Being Able to Afford More Than 310 Ships
at Current Funding Levels ............................................................................................. 26
Potential Impacts of a CR on FY2020 Navy Shipbuilding Programs ..................................... 27
DOD Operations Currently Being Funded by a CR (H.R. 3055/P.L. 116-69) .................. 27
Summary of Potential Impacts on FY2020 Navy Shipbuilding Programs ....................... 27
October 30, 2019, Department of Navy Fact Sheet on CR Impacts ................................. 29
Press Reports ..................................................................................................................... 30
Legislative Activity for FY2020 .................................................................................................... 34
CRS Reports Tracking Legislation on Specific Navy Shipbuilding Programs ....................... 34
Summary of Congressional Action on FY2020 Funding Request .......................................... 35
FY2020 National Defense Authorization Act (H.R. 2500/S. 1790) ........................................ 37
House ................................................................................................................................ 37
Senate ................................................................................................................................ 40
Conference ........................................................................................................................ 47
Congressional Research Service

link to page 61 link to page 61 link to page 62 link to page 10 link to page 24 link to page 26 link to page 28 link to page 7 link to page 21 link to page 22 link to page 23 link to page 28 link to page 41 link to page 67 link to page 88 link to page 89 link to page 63 link to page 67 link to page 69 link to page 72 link to page 82 link to page 83 link to page 85 link to page 87 link to page 90 link to page 96 link to page 99 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

FY2020 DOD Appropriations Act (H.R. 2968/S. 2474) ......................................................... 56
House ................................................................................................................................ 56
Senate ................................................................................................................................ 57

Figures
Figure 1. Navy Briefing Slide on Surface Combatant Force Architecture ...................................... 5
Figure 2. Projected Size of Navy Under FY2019 and FY2020 30-Year Shipbuilding Plans ........ 19
Figure 3. Navy Estimate of Funding Requirements for FY2020 30-Year Plan ............................. 21
Figure 4. CBO Estimate of Funding Requirements for 30-Year Plan ........................................... 23

Tables
Table 1. 355-Ship Force-Level Goal ............................................................................................... 2
Table 2. FY2020 Five-Year (FY2020-FY2024) Shipbuilding Plan............................................... 16
Table 3. FY2020 30-Year (FY2020-FY2049) Shipbuilding Plan .................................................. 17
Table 4. Projected Force Levels Resulting from FY2020 30-Year Shipbuilding Plan .................. 18
Table 5. Navy and CBO Estimates of Cost of 30-Year Shipbuilding Plan .................................... 23
Table 6. Summary of Congressional Action on FY2020 Funding Request ................................... 36

Table B-1. Earlier Navy Force-Structure Goals Dating Back to 2001 .......................................... 62
Table H-1. Total Number of Ships in Navy Since FY1948 ........................................................... 83
Table H-2. Battle Force Ships Procured or Requested, FY1982-FY2024 ..................................... 84

Appendixes
Appendix A. Strategic and Budgetary Context ............................................................................. 58
Appendix B. Earlier Navy Force-Structure Goals Dating Back to 2001 ....................................... 62
Appendix C. Comparing Past Ship Force Levels to Current or Potential Future Levels .............. 64
Appendix D. Industrial Base and Employment Aspects of Additional Shipbuilding Work .......... 67
Appendix E. A Summary of Some Acquisition Lessons Learned for Navy Shipbuilding ............ 77
Appendix F. Some Considerations Relating to Warranties in Shipbuilding Contracts .................. 78
Appendix G. Avoiding Procurement Cost Growth vs. Minimizing Procurement Costs ............... 80
Appendix H. Size of the Navy and Navy Shipbuilding Rate ........................................................ 82
Appendix I. Potential Impacts of CRs on Navy Shipbuilding Programs ...................................... 85
Appendix J. October 30, 2019, Department of Navy Fact Sheet on FY2020 CR Impacts ........... 91

Contacts
Author Information ........................................................................................................................ 94

Congressional Research Service

link to page 63 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Introduction
This report presents background information and issues for Congress concerning the Navy’s force
structure and shipbuilding plans. The current and planned size and composition of the Navy, the
rate of Navy ship procurement, and the prospective affordability of the Navy’s shipbuilding plans
have been oversight matters for the congressional defense committees for many years.
The Navy’s proposed FY2020 budget requests funding for the procurement of 12 new ships,
including 1 Gerald R. Ford (CVN-78) class aircraft carrier, 3 Virginia-class attack submarines, 3
DDG-51 class Aegis destroyers, 1 FFG(X) frigate, 2 John Lewis (TAO-205) class oilers, and 2
TATS towing, salvage, and rescue ships.
The issue for Congress is whether to approve, reject, or modify the Navy’s proposed FY2020
shipbuilding program and the Navy’s longer-term shipbuilding plans. Decisions that Congress
makes on this issue can substantially affect Navy capabilities and funding requirements, and the
U.S. shipbuilding industrial base.
Detailed coverage of certain individual Navy shipbuilding programs can be found in the
following CRS reports:
 CRS Report R41129, Navy Columbia (SSBN-826) Class Ballistic Missile
Submarine Program: Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report RL32418, Navy Virginia (SSN-774) Class Attack Submarine
Procurement: Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program:
Background and Issues for Congress, by Ronald O'Rourke. (This report also
covers the issue of the Administration’s FY2020 budget proposal, which the
Administration withdrew on April 30, to not fund a mid-life refueling overhaul
[called a refueling complex overhaul, or RCOH] for the aircraft carrier Harry S.
Truman
[CVN-75], and to retire CVN-75 around FY2024.)
 CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs:
Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report R44972, Navy Frigate (FFG[X]) Program: Background and Issues
for Congress, by Ronald O'Rourke.
 CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background
and Issues for Congress, by Ronald O'Rourke.
 CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship
Programs: Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report R43546, Navy John Lewis (TAO-205) Class Oiler Shipbuilding
Program: Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report R45757, Navy Large Unmanned Surface and Undersea Vehicles:
Background and Issues for Congress, by Ronald O'Rourke.
For a discussion of the strategic and budgetary context in which U.S. Navy force structure and
shipbuilding plans may be considered, see Appendix A.
Congressional Research Service

1

link to page 67 link to page 7 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Background
Navy’s 355-Ship Ship Force-Structure Goal
Introduction
On December 15, 2016, the Navy released a force-structure goal that calls for achieving and
maintaining a fleet of 355 ships of certain types and numbers. The 355-ship force-level goal
replaced a 308-ship force-level goal that the Navy released in March 2015. The 355-ship force-
level goal is the largest force-level goal that the Navy has released since a 375-ship force-level
goal that was in place in 2002-2004. In the years between that 375-ship goal and the 355-ship
goal, Navy force-level goals were generally in the low 300s (see Appendix B). The force level of
355 ships is a goal to be attained in the future; the actual size of the Navy in recent years has
generally been between 270 and 290 ships. Table 1 shows the composition of the 355-ship force-
level objective.
Table 1. 355-Ship Force-Level Goal
Ship Category
Number of ships
Ballistic missile submarines (SSBNs)
12
Attack submarines (SSNs)
66
Aircraft carriers (CVNs)
12
Large surface combatants (i.e., cruisers [CGs] and destroyers [DDGs])
104
Small surface combatants (i.e., frigates [FFGs], Littoral Combat Ships, and mine warfare ships)
52
Amphibious ships
38
Combat Logistics Force (CLF) ships (i.e., at-sea resupply ships)
32
Command and support ships
39
TOTAL
355
Source: U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, Table A-1 on page 10.
355-Ship Goal Resulted from 2016 Force Structure Assessment (FSA)
The 355-ship force-level goal is the result of a Force Structure Assessment (FSA) conducted by
the Navy in 2016. An FSA is an analysis in which the Navy solicits inputs from U.S. regional
combatant commanders (CCDRs) regarding the types and amounts of Navy capabilities that
CCDRs deem necessary for implementing the Navy’s portion of the national military strategy and
then translates those CCDR inputs into required numbers of ships, using current and projected
Navy ship types. The analysis takes into account Navy capabilities for both warfighting and day-
to-day forward-deployed presence.1 Although the result of the FSA is often reduced for
convenience to single number (e.g., 355 ships), FSAs take into account a number of factors,
including types and capabilities of Navy ships, aircraft, unmanned vehicles, and weapons, as well
as ship homeporting arrangements and operational cycles. The Navy conducts a new FSA or an

1 For further discussion, see U.S. Navy, Executive Summary, 2016 Navy Force Structure Assessment (FSA), December
15, 2016, pp. 1-2.
Congressional Research Service

2

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

update to the existing FSA every few years, as circumstances require, to determine its force-
structure goal.
355-Ship Goal Made U.S. Policy by FY2018 NDAA
Section 1025 of the FY2018 National Defense Authorization Act, or NDAA (H.R. 2810/P.L. 115-
91 of December 12, 2017), states the following:
SEC. 1025. Policy of the United States on minimum number of battle force ships.
(a) Policy.—It shall be the policy of the United States to have available, as soon as
practicable, not fewer than 355 battle force ships, comprised of the optimal mix of
platforms, with funding subject to the availability of appropriations or other funds.
(b) Battle force ships defined.—In this section, the term “battle force ship” has the meaning
given the term in Secretary of the Navy Instruction 5030.8C.
The term battle force ships in the above provision refers to the ships that count toward the quoted
size of the Navy in public policy discussions about the Navy.2
Large Unmanned Vehicles and Navy Ship Count
Because large unmanned vehicles can be deployed directly from pier to perform missions that
might otherwise be assigned to manned ships and submarines, some observers have a raised a
question as to whether the large UVs covered in this report should be included in the top-level
count of the number of ships in the Navy. Navy officials state that they have not yet decided
whether to modify the top-level count of the number of ships in the Navy to include these large
UVs.
New FSA Now Underway Could Change Fleet Architecture and
Distribution of Shipbuilding Work

Overview
New FSA, Called an Integrated FSA (INFSA), Now Underway
A new FSA—referred to as the Integrated Naval FSA (INFSA), with the term naval referring to
both the Navy and Marine Corps (i.e., the two naval services)—is now underway as the successor
to the 2016 FSA.3 Department of the Navy (DON) officials state that the INFSA will take into
account the Trump Administration’s December 2017 National Security Strategy document and its

2 The battle force ships method for counting the number of ships in the Navy was established in 1981 by agreement
between the Secretary of the Navy and the Secretary of Defense, and has been modified somewhat over time, in part by
Section 1021 of the Carl Levin and Howard P. “Buck” McKeon National Defense Authorization Act for Fiscal Year
2015 (H.R. 3979/P.L. 113-291 of December 19, 2014).
3 A September 27, 2019, press report stated that on September 6, 2019, the Chief of Naval Operations and the
Commandant of the Marine Corps signed a memorandum stating that the two services will develop a “comprehensive
naval force architecture” to inform the new FSA, and that the new FSA will be developed as an integrated naval (i.e.,
Navy-Marine Corps) FSA (INFSA). (Mallory Shelbourne, “Navy, Marine Corps Conducting Integrated Force-Structure
Assessment,” Inside Defense, September 27, 2019. See also Otto Kreisher, “New Force Structure Assessment Will
Address Needs of ‘Great Power Competition,’ Two Top Requirements Officers Say,” Seapower, October 22, 2019,
and the section under the subheader “Naval Integrated Force Structure Assessment” in Megan Eckstein, “Navy Marines
Wargaming New Gear to Support Emerging Warfare Concepts,” USNI News, October 23, 2019.)
Congressional Research Service

3

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

January 2018 National Defense Strategy document, both of which put an emphasis on renewed
great power competition with China and Russia, as well as updated information on Chinese and
Russian naval and other military capabilities and recent developments in new technologies,
including those related to unmanned vehicles (UVs).4
INFSA Could Result in Once-in-a-Generation Change in Fleet Architecture and
Distribution of Shipbuilding Work
Statements from DON officials suggest that the INFSA could result in a once-in-a-generation
change in the Navy’s fleet architecture, meaning the mix of ships that make up the Navy and how
those ships are combined into formations and used to perform various missions. As detailed
below, statements from DON officials suggest that the INFSA could shift the fleet to a more
distributed architecture that includes a reduced proportion of larger ships, an increased proportion
of smaller ships, and a newly created category of large unmanned surface vehicles (USVs) and
large unmanned underwater vehicles (UUVs). Such a change in fleet architecture could alter,
perhaps substantially, the mix of ships to be procured for the Navy and the distribution of Navy
shipbuilding work among the nation’s shipyards.
INFSA to be Published No Later than January 15, 2020
Through much of 2019, Navy officials stated that the INFSA was to be completed by the end of
2019. A September 27, 2019, press report stated that an interim version was to be completed by
September 2019, in time to inform programmatic decisions on the FY2022 Program Objective
Memorandum (POM), meaning the in-house DOD planning document that will guide the
development of DOD’s FY2022 budget submission.5 A December 6, 2019, memorandum from
Acting Secretary of the Navy Thomas Modly6 stated that he expects the final INFSA to be
published no later than January 15, 2020. Some aspects of the INFSA might be incorporated into
the Navy’s proposed FY2021 budget, which is to be submitted to Congress in February 2020.
In his December 6, 2019, memorandum, Acting Secretary Modly stated that “my staff and I will
become involved” in the INFSA, and that one of his five immediate objectives as acting secretary
is to “establish an Integrated Plan to achieve a [fleet of] 355 (or more) ships, Unmanned
Underwater Vehicles (UUVs), and Unmanned Surface Vehicles (USVs) for greater global naval
power, within 10 years.”

4 See, for example, Marcus Weisgerber, “US Navy Re-Evaluating 355-Ship Goal,” Defense One, February 1, 2019;
Paul McLeary, “Navy Rethinks 355-Ship Fleet: CNO Richardson,” Breaking Defense, February 1, 2019; Mallory
Shelbourne, “CNO: Navy Expects New Force-Structure Assessment ‘Later This Year,’” Inside the Navy, February 4,
2019.
5 Mallory Shelbourne, “Navy, Marine Corps Conducting Integrated Force-Structure Assessment,” Inside Defense,
September 27, 2019. See also Otto Kreisher, “New Force Structure Assessment Will Address Needs of ‘Great Power
Competition,’ Two Top Requirements Officers Say,” Seapower, October 22, 2019, and the section under the subheader
“Naval Integrated Force Structure Assessment” in Megan Eckstein, “Navy Marines Wargaming New Gear to Support
Emerging Warfare Concepts,” USNI News, October 23, 2019.
6 Memorandum for distribution from Acting Secretary of the Navy Thomas B. Modly, subject “SecNav Vector !,”
dated December 6, 2019. See also David B. Larter, “Acting US Navy Secretary: Deliver Me a 355-Ship Fleet by 2030,”
Defense News, December 9, 2019.
Congressional Research Service

4

link to page 10
Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Potential New Surface Combatant Force Architecture
Statements from Navy officials suggest that the new FSA might shift the Navy’s surface
combatant force to a more distributed architecture that includes a reduced proportion of large
surface combatants (i.e., cruisers and destroyers), an increased proportion of small surface
combatants (i.e., frigates and LCSs), and a newly created third tier of unmanned surface vehicles
(USVs). In presenting its proposed FY2020 budget, the Navy highlighted its plans for developing
and procuring USVs in coming years.
Figure 1 provides, for the surface combatant portion of the Navy,7 a conceptual comparison of
the current fleet architecture (shown on the left as the “ship centric force”) and the new, more
distributed architecture (shown on the right as the “distributed/nodal force”). The figure does not
depict the entire surface combatant fleet, but rather a representative portion of it.
Figure 1. Navy Briefing Slide on Surface Combatant Force Architecture
Each sphere represents a ship or unmanned surface vehicle (USV)

Source: Il ustration accompanying Megan Eckstein, “Sea Hunter Unmanned Ship Continues Autonomy Testing
as NAVSEA Moves Forward with Draft RFP,” USNI News, April 29, 2019. The il ustration was also included as
Slide 2 in a Navy briefing entitled “Designing & Building the Surface Fleet: Unmanned and Small Combatants,” by
Rear Admiral Casey Moton at a June 20, 2019, conference of the American Society of Naval Engineers (ASNE).
Notes: Each sphere represents a ship or a USV. LSC means large surface combatant (i.e., cruiser or destroyer),
and SSC means small surface combatant (i.e., frigate or Littoral Combat Ship). As shown in the color coding, the
LSCs and SSCs are equipped with a combination of sensors (green), command and control (C2) equipment (red),

7 Other major parts of the Navy include submarines, aircraft carriers, amphibious ships, logistics (resupply) ships, and
support ships.
Congressional Research Service

5

link to page 10 link to page 10 link to page 10 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

and payloads other than sensors and C2 equipment, meaning principally weapons (blue). LUSVs and MUSVs, in
contrast, are equipped primarily with weapons (blue) or sensors (green).
In the figure, each sphere represents a manned ship or USV. As shown in the color coding, under
both the current fleet architecture and the more distributed architecture, the manned ships (i.e., the
LSCs and SSCs) are equipped with a combination of sensors (green), command and control (C2)
equipment (red), and payloads other than sensors and C2 equipment, meaning principally
weapons (blue).
Under the more distributed architecture, the manned ships would be on average smaller (because
a greater share of them would be SSCs), and this would be possible because some of the surface
combatant force’s weapons and sensors would be shifted from the manned ships to USVs, with
weapon-equipped Large USVs (LUSVs) acting primarily as adjunct weapon magazines and
sensor-equipped Medium USVs (MUSVs) contributing to the fleet’s sensor network.
As shown in Figure 1, under the Navy’s current surface combatant force architecture, there are to
be 20 LSCs for every 10 SSCs (i.e., a 2:1 ratio of LSCs to SSCs), with no significant contribution
from LUSVs and MUSVs. This is consistent with the Navy’s current force-level objective, which
calls for achieving a 355-ship fleet that includes 104 LSCs and 52 SSCs (a 2:1 ratio). Under the
more distributed architecture, the ratio of LSCs to SSCs would be reversed, with 10 LSCs for
every 20 SSCs (a 1:2 ratio), and there would also now be 30 LUSVs and 40 MUSVs.
A January 15, 2019, press report states
The Navy plans to spend this year taking the first few steps into a markedly different future,
which, if it comes to pass, will upend how the fleet has fought since the Cold War. And it
all starts with something that might seem counterintuitive: It’s looking to get smaller.
“Today, I have a requirement for 104 large surface combatants in the force structure
assessment; [and] I have [a requirement for] 52 small surface combatants,” said Surface
Warfare Director Rear Adm. Ronald Boxall. “That’s a little upside down. Should I push
out here and have more small platforms? I think the future fleet architecture study has
intimated ‘yes,’ and our war gaming shows there is value in that.”8
Another way of summarizing Figure 1 would be to say that the surface combatant force
architecture (reading vertically down the figure) would change from 20+10+0+0 (i.e., a total of
30 surface combatant platforms, all manned) for a given portion of the surface combatant force,
to 10+20+30+40 (i.e., a total of 100 surface combatant platforms, 70 of which would be LUSVs
and MUSVs) for a given portion of the surface combatant force. The Navy refers to the more
distributed architecture’s combination of LSCs, SSCs, LUSVs, and MUSVs as the Future Surface
Combatant Force (FSCF).
Figure 1 is conceptual, so the platform ratios for the more distributed architecture should be
understood as notional or approximate rather than exact. The point of the figure is not that
relative platform numbers under the more distributed architecture would change to the exact
ratios shown in the figure, but that they would evolve over time toward something broadly
resembling those ratios.9

8 David B. Larter, “US Navy Moves Toward Unleashing Killer Robot Ships on the World’s Oceans,” Defense News,
January 15, 2019.
9 For further discussion, see CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs: Background
and Issues for Congress
, by Ronald O'Rourke, CRS Report R44972, Navy Frigate (FFG[X]) Program: Background
and Issues for Congress
, by Ronald O'Rourke, and CRS Report R45757, Navy Large Unmanned Surface and Undersea
Vehicles: Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service

6

link to page 7 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Potential New Amphibious Ship Architecture
Statements from the Commandant of the Marine Corps suggest strongly that the new FSA might
change the Navy’s amphibious ship force to an architecture based on a new amphibious lift target
and a new mix of amphibious ships.
The current 38-ship amphibious ship force-level goal shown in Table 1 is intended to meet a
requirement for having enough amphibious lift to lift the assault echelons of two Marine
Expeditionary Brigades (MEBs), a requirement known as the 2.0 MEB lift requirement. The 2.0
MEB lift requirement dates to 2006. The translation of this lift requirement into a Marine Corps-
preferred force-level goal of 38 ships dates to 2009, and the Navy’s formal incorporation of the
38-ship goal (rather than a more fiscally constrained goal of 33 or 34 ships) into the Navy’s
overall ship force-structure goal dates to the 2016 FSA, the results of which were released in
December 2016.10
In July 2019, General David H. Berger, the Commandant of the Marine Corps, released a
document entitled Commandant’s Planning Guidance that states that the Marine Corps wants to,
among other things, move away from the 38-ship amphibious ship force-level goal and the 2.0
MEB lift force-planning metric, and shift to a new and different mix of amphibious ships that
includes not only LHA/LHD-type amphibious assault ships and LPD/LPD-type amphibious
ships, but other kinds of ships as well, including smaller amphibious ships, ships like the Navy’s
Expeditionary Sea Base (ESB) and Expeditionary Fast Transport (EPF) ships (referred to
collectively as E-class ships), ships based on commercial-ship hull designs, and unmanned
surface vehicles (USVs). The Commandant’s Planning Guidance, which effectively announces a
once-in-a-generation change in Marine Corps thinking on this and other issues relating to the
Marine Corps, states in part (emphasis as in the original):
Our Nation’s ability to project power and influence beyond its shores is increasingly
challenged by long-range precision fires; expanding air, surface, and subsurface threats;
and the continued degradation of our amphibious and auxiliary ship readiness. The ability
to project and maneuver from strategic distances will likely be detected and contested from
the point of embarkation during a major contingency. Our naval expeditionary forces must
possess a variety of deployment options, including L-class [amphibious ships] and E-class
[expeditionary ships] ships, but also increasingly look to other available options such as
unmanned platforms, stern landing vessels, other ocean-going connectors, and smaller
more lethal and more risk-worthy platforms. We must continue to seek the affordable
and plentiful at the expense of the exquisite and few when conceiving of the future
amphibious portion of the fleet.

We must also explore new options, such as inter-theater connectors and commercially
available ships and craft that are smaller and less expensive, thereby increasing the
affordability and allowing acquisition at a greater quantity. We recognize that we must
distribute our forces ashore given the growth of adversary precision strike capabilities, so
it would be illogical to continue to concentrate our forces on a few large ships. The
adversary will quickly recognize that striking while concentrated (aboard ship) is the
preferred option. We need to change this calculus with a new fleet design of smaller, more
lethal, and more risk-worthy platforms. We must be fully integrated with the Navy to
develop a vision and a new fleet architecture that can be successful against our peer
adversaries while also maintaining affordability. To achieve this difficult task, the Navy
and Marine Corps must ensure larger surface combatants possess mission agility across sea

10 For additional discussion of the 2.0 MEB lift goal and earlier amphibious lift goals dating back to 1980, see
Appendix A of CRS Report RL34476, Navy LPD-17 Amphibious Ship Procurement: Background, Issues, and Options
for Congress
, by Ronald O'Rourke.
Congressional Research Service

7

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

control, littoral, and amphibious operations, while we concurrently expand the quantity of
more specialized manned and unmanned platforms….
We will no longer use a “2.0 MEB requirement” as the foundation for our arguments
regarding amphibious ship building, to determine the requisite capacity of vehicles
or other capabilities, or as pertains to the Maritime Prepositioning Force. We will no
longer reference the 38-ship requirement memo from 2009, or the 2016 Force
Structure Assessment, as the basis for our arguments and force structure
justifications.
The ongoing 2019 Force Structure Assessment will inform the amphibious
requirements based upon this guidance. The global options for amphibs [types of
amphibious ships] include many more options than simply LHAs, LPDs, and LSDs. I will
work closely with the Secretary of the Navy and Chief of Naval Operations (CNO) to
ensure there are adequate numbers of the right types of ships, with the right capabilities, to
meet national requirements.
I do not believe joint forcible entry operations (JFEO) are irrelevant or an operational
anachronism; however, we must acknowledge that different approaches are required given
the proliferation of anti-access/area denial (A2AD) threat capabilities in mutually contested
spaces. Visions of a massed naval armada nine nautical miles off-shore in the South China
Sea preparing to launch the landing force in swarms of ACVs [amphibious combat
vehicles], LCUs [utility landing craft], and LCACs [air-cushioned landing craft]are
impractical and unreasonable. We must accept the realities created by the proliferation of
precision long-range fires, mines, and other smart-weapons, and seek innovative ways to
overcome those threat capabilities. I encourage experimentation with lethal long-range
unmanned systems capable of traveling 200 nautical miles, penetrating into the adversary
enemy threat ring, and crossing the shoreline—causing the adversary to allocate resources
to eliminate the threat, create dilemmas, and further create opportunities for fleet maneuver.
We cannot wait to identify solutions to our mine countermeasure needs, and must make
this a priority for our future force development efforts….
Over the coming months, we will release a new concept in support of the Navy’s
Distributed Maritime Operations (DMO) Concept and the NDS called – Stand-in Forces.
The Stand-in Forces concept is designed to restore the strategic initiative to naval forces
and empower our allies and partners to successfully confront regional hegemons that
infringe on their territorial boundaries and interests. Stand-in Forces are designed to
generate technically disruptive, tactical stand-in engagements that confront aggressor
naval forces with an array of low signature, affordable, and risk-worthy platforms
and payloads.
Stand-in forces take advantage of the relative strength of the contemporary
defense and rapidly-emerging new technologies to create an integrated maritime defense
that is optimized to operate in close and confined seas in defiance of adversary long-range
precision “stand-off capabilities.”
Creating new capabilities that intentionally initiate stand-in engagements is a disruptive
“button hook” in force development that runs counter to the action that our adversaries
anticipate. Rather than heavily investing in expensive and exquisite capabilities that
regional aggressors have optimized their forces to target, naval forces will persist forward
with many smaller, low signature, affordable platforms that can economically host a dense
array of lethal and nonlethal payloads.
By exploiting the technical revolution in autonomy, advanced manufacturing, and artificial
intelligence, the naval forces can create many new risk-worthy unmanned and minimally-
manned platforms that can be employed in stand-in engagements to create tactical
dilemmas that adversaries will confront when attacking our allies and forces forward.11

11 U.S. Marine Corps, Commandant’s Planning Guidance, 38th Commandant of the Marine Corps, undated, released
July 2019, pp. 4-5, 10. See also Megan Eckstein, “New Commandant Berger Sheds 38-Amphib Requirement in Quest
Congressional Research Service

8

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Potential New Aircraft Carrier/Naval Aviation Force Architecture
Statements from Navy officials suggest that the Navy is considering moving to a new aircraft
carrier/naval aviation force architecture that might supplement today’s large-deck, nuclear
powered aircraft carriers (CVNs) with smaller and perhaps nonnuclear-powered aircraft carriers.
One option for a smaller carrier is the so-called Lighting Carrier, a term referring to an LHA-type
amphibious assault ship equipped with an air wing consisting largely of F-35B Joint Strike
Fighters (JSFs). (The alternate name for the F-35 is the Lighting II. The B variant of the F-35,
which is currently being procured for the Marine Corps, is short takeoff, vertical landing
[STOVL] variant that can be operated off of ships with flight decks that are shorter than the flight
decks of CVNs.) The Navy and Marine Corps are currently experimenting with the Lightning
Carrier concept.12
Another option for a smaller carrier is one whose air wing would consist mostly or entirely of
unmanned aerial vehicles (UAVs). The Navy in recent years has periodically studied the potential
of UAV carriers.
A February 15, 2019, press report stated the following:
Under Secretary of the Navy Thomas Modly said now that the Navy found a way to build
two new Gerald R. Ford-class aircraft carriers [CVN-80 and CVN-81] while saving money
it is starting to look at future carrier procurement, which might be very different.…
Modly said Secretary of the Navy Richard Spencer sees $13 billion carriers as not
sustainable going forward and the service will be looking at ways to further reduce costs
or keep the carrier capabilities more affordable in future ship procurements.
“There was general conclusion that those two for sure would be built” and once that was
determined “that was going to happen,” Modly said during the AFCEA [Armed Forces
Communications and Electronics Association] West 2019 conference here [in San
Diego].…
After the CVN-80 and -81 [procurement] decision was made, “I think a lot of derivative
decisions still need to be made. So the secretary [Spencer] would like to take a look at
‘O.K. now that we made that decision, and that second one that comes will be in quite a
few years from now, we need to start thinking now about what’s the next one look like.’”

to Modernize USMC for High-End Fight,” USNI News, July 18, 2019; Paul McLeary, “Sacred Cows Die As Marine
Commandant Changes Course On Amphibs,” Breaking Defense, July 26, 2019; David Ignatius, “The Marines’ New
Commandant Has Set the Bar for Real Military Reform,” Washington Post, August 8, 2019; Megan Eckstein, “Marine
Planners Using Commandant’s Guidance to Start Crafting Future of the Corps,” USNI News, September 18, 2019;
Shawn Snow, “An Unmanned Ship That Can Travel 500 Nautical Miles Without Resupply—the Corps Is Looking at
It,” Marine Corps Times, September 19, 2019; Megan Eckstein, “Marines, Navy Both Considering Something Like an
Offshore Support Vessel to Supplement Amphibs,” USNI News, September 20, 2019; David Axe, “U.S. Navy and
Marine Corps Want Small Ships to Land Troops in a War,” National Interest, September 21, 2019; Megan Eckstein,
“Navy, Marines Rethinking How to Build Future Fleet with Unmanned, Expeditionary Ships,” USNI News, September
26, 2019; David Barno and Nora Bensahel, “A Striking New Vision for the marines, and a Wakeup Call for the Other
Services,” War on the Rocks, October 1, 2019; Megan Eckstein, “Berger: Marine 2030 Force Design Is Nearly
Complete; Concepts Now Being Modeled, Tested,” USNI News, October 3, 2019; Patrick Tucker, “The Future of the
Marines Is Smaller, More Robotic, More Naval,” Defense One, October 3, 2019; Otto Kreisher, “‘Great Power’ Fight
Might Require Different Blend of Vessels, But Marines Won’t Shun Amphibious Operations, NDIA Speakers Say,”
Seapower, October 24, 2019; Megan Eckstein, “Marines, Navy Considering ‘Alternate’ Amphibs to Supplement
Today’s Fleet,” USNI News, October 26, 2019.
12 See, for example, Megan Eckstein, “Marines Test ‘Lightning Carrier’ Concept, Control 13 F-35Bs from Multiple
Amphibs,” USNI News, October 23, 2019.
Congressional Research Service

9

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Modly told reporters they are asking questions like “Is it going to be advanced as this one?
Or is it going to be smaller or are we going to buy two smaller ones or maybe shift air
power to other forms of delivery. And we don’t know the answers of that but we’re looking
at this.”13
An October 24, 2019, press report stated:
The secretary of the U.S. Navy said the sea service is looking ahead to determine what the
follow-on aircraft carrier design will look like, even as work continues to get the new USS
Gerald R. Ford [CVN-78] out to regular operations at sea.
“With the [recent] two-carrier [CVN-80 and CVN-81] buy, what will the next carrier look
like? We’re having discussions on that as we speak, and we will see what happens,” Navy
Secretary Richard V. Spencer said, speaking Oct. 23 at the Brookings Institution, a
Washington think tank. “I think we actually whiteboard this thing. What will it look like in
10 to 15 years? Is it a floating platform for electrically charged unmanned aircraft? I don’t
know.”
Spencer said the Navy is looking at the “lightning carrier” concept, deploying 20 F-35B
Lightning II strike fighters on an amphibious assault ship. Recently the USS America
operated in the eastern Pacific Ocean with 13 F-35Bs of Marine Fighter Attack Squadron
(VMFA) 122, the Corps’ most recently equipped F-35B squadron. Earlier this year, USS
Wasp operated for a short period with 10 F-35Bs of VMFA-121 on board.
“My cost performance there is tremendous,” Spencer said. “Does it have the same punch?
No, it doesn’t. But it has a very interesting sting to it.”
Such lightning carriers would lack airborne early warning aircraft unless the Navy
developed a capability for these smaller decks. The sea service is developing an aerial
refueling tanker capability to be installed in the MV-22 Osprey tilt-rotor aircraft to refuel
the F-35Bs.
During the opening phase of Operation Iraqi Freedom in 2003, the amphibious assault ship
USS Bataan operated as a “Harrier carrier,” equipped with two full squadrons of AV-8B
Harrier II attack aircraft, which the F-35B is replacing, rather than the usual six aircraft.
The concept might get a serious workout in a couple of years.
“In 2021, you will see a Marine Corps F-35B squadron on the Queen Elizabeth, which we
are very excited about,” Spencer said, speaking of the plan to operate a Marine Corps F-
35B squadron alongside a British F-35B squadron on the new Royal Navy aircraft carrier.14
An October 30, 2019, press report about remarks made by Secretary Spencer at a media
roundtable event held that day at the Heritage Foundation stated that
The secretary embraced [Marine Corps Commandant General David] Berger’s proposal to
use large-deck amphibious ships loaded with F-35B “Lightning II” strike fighters. He said:
“Does it have the same strike capability as a carrier? No, it doesn’t. But if part of the
mission of the carrier is presence and forward deployability … lightning carriers [are] a
great option to augment what the requirement might be.”15
A December 5, 2019, press report states:

13 Rich Abott, “Navy Starts Looking At Carriers After CVN-81,” Defense Daily, February 15, 2019.
14 Richard R. Burges, “Secretary: Navy Discussing Next-Gen Carrier Concepts, Including ‘Lightning Carrier,’”
Seapower, October 24, 2019. See also Wesley Morgan, “Navy Secretary Accuses Congressional Critics of
'Disinformation' on Ford Carrier,” Politico Pro, October 23, 2019.
15 Otto Kreisher, “Spencer Lauds Tight Integration of Navy, Marine Forces in ‘Great Power Competition,’” Seapower,
October 27, 2019. Ellipsis as in original.
Congressional Research Service

10

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The Navy is unclear how it will proceed with its next generation of aviation combatants
following the introduction of the F-35C Lighting II Joint Strike Fighter into the carrier air
wing, Chief of Naval Operations Adm. Mike Gilday said on Thursday [December 5]….
Gilday indicated the Navy is still working on the question of what the next [aviation]
combatant after F-35 will be, or even if it will be launched from an aircraft carrier.
“I do think we need an aviation combatant, but what the aviation combatant of the future
looks like? I don’t know yet. I think there’s going to be a requirement to continue to deliver
a seaborne launched vehicle through the air that’ll deliver an effect downrange,” Gilday
said at U.S. Naval Institute’s Defense Forum Washington conference.
“I do think that that will likely be a mix of manned and unmanned. The platform which
they launch from? I’m not sure what that’s going to look like.”16
Potential New Combat Logistics Force (CLF) Architecture
The Navy’s FY2020 30-year shipbuilding plan suggests that shifting to a more distributed fleet
architecture could increase required numbers of Combat Logistics Force (CLF) ships—meaning
the oilers, ammunition ships, and dry cargo ships that transport fuel, ammunition, and supplies
Navy combat ships that are operating at sea—and augment today’s CLF ships with additional
“smaller, faster, multi-mission transports.”17
Potential New Undersea Force Architecture
The new FSA might also change the Navy’s undersea force to a more distributed architecture that
includes, in addition to attack submarines (SSNs) and bottom-based sensors, a new element of
extra-large unmanned underwater vehicles (XLUUVs), which might be thought of as unmanned
submarines. In presenting its proposed FY2020 budget, the Navy highlighted its plans for
developing and procuring UUVs in coming years.18
Rationale for a More Distributed Fleet Architecture
Some observers have long urged the Navy to shift to a more distributed fleet architecture, on the
grounds that the Navy’s current architecture—which concentrates much of the fleet’s capability
into a relatively limited number of individually larger and more expensive surface ships—is
increasingly vulnerable to attack by the improving maritime anti-access/area-denial (A2/AD)
capabilities (particularly anti-ship missiles and their supporting detection and targeting systems)
of potential adversaries, particularly China.19 Shifting to a more distributed architecture, these
observers have argued, would
 complicate an adversary’s targeting challenge by presenting the adversary with a
larger number of Navy units to detect, identify, and track;

16 Sam LaGrone, “Navy Still Mulling Post-F-35C Aviation Combatant; Could be Mix of Manned, Unmanned Aircraft,”
USNI News, December 5, 2019.
17 U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, pp. 7, 15, 17, 24. The quoted phrase is from page 24.
18 For further discussion, see CRS Report R45757, Navy Large Unmanned Surface and Undersea Vehicles:
Background and Issues for Congress
, by Ronald O'Rourke.
19 For more on China’s maritime A2/AD capabilities, see CRS Report RL33153, China Naval Modernization:
Implications for U.S. Navy Capabilities—Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service

11

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

 reduce the loss in aggregate Navy capability that would result from the
destruction of an individual Navy platform;
 give U.S. leaders the option of deploying USVs and UUVs in wartime to sea
locations that would be tactically advantageous but too risky for manned ships;
and
 increase the modularity and reconfigurability of the fleet for adapting to changing
mission needs.20
For a number of years, DON leaders acknowledged the views of those observers but continued to
support the current fleet architecture. More recently, however, DON leaders appear to have
shifted their thinking toward support for moving the fleet to a more distributed architecture. DON
leaders appear to have shifted their thinking in favor of a more distributed architecture because
they now appear to believe that such an architecture will be
operationally necessary, as the observers have long argued, to respond
effectively to the improving maritime A2/AD capabilities of other countries,
particularly China;21
technically feasible as a result of advances in technologies for UVs and for
networking widely distributed maritime forces that include significant numbers
of UVs; and
affordable—no more expensive, and possibly less expensive, than the current
architecture, so as to fit within future Navy budgets that Navy officials expect to
be flat or declining in real (i.e., inflation-adjusted) terms compared to the Navy’s
current budget.
The more distributed architecture that Navy leaders now appear to support may differ in its
details from distributed architectures that the observers have been advocating, but the general idea
of shifting to a more distributed architecture, and of using large UVs as a principal means of
achieving that, appears to be similar. The Department of Defense (DOD) states that
The FY 2020 budget request diversifies and expands sea power strike capacity through
procurement of offensively armed Unmanned Surface Vessels (USVs). The USV
investment, paired with increased investment in long-range maritime munitions, represents
a paradigm shift towards a more balanced, distributed, lethal, survivable, and cost-
imposing naval force that will better exploit adversary weaknesses and project power into
contested environments.22
Distributed Maritime Operations (DMO)
Shifting to a more distributed force architecture, Navy officials have suggested, could be
appropriate for implementing the Navy’s new overarching operational concept, called Distributed
Maritime Operations (DMO). The Navy’s FY2020 30-year shipbuilding plan mentions DMO,23
and a December 2018 document from the Chief of Naval Operations states that the Navy will

20 See, for example, Arthur H. Barber, “Redesign the Fleet,” U.S. Naval Institute Proceedings, January 2019.
21 See, for example, David B. Larter, “With China Gunning for Aircraft Carriers, US Navy Says It Must Change How It
Fights,” Defense News, December 6, 2019.
22 Department of Defense, Office of the Undersecretary of Defense (Comptroller)/Chief Financial Officer, Defense
Budget Overview, United States Department of Defense, Fiscal Year 2020 Budget Request
, March 2019, pp. 4-5 to 4-6.
23 U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, March 2019, pp. 3, 4, 7, 8, 15, 17, 24.
Congressional Research Service

12

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

“Continue to mature the Distributed Maritime Operations (DMO) concept and key supporting
concepts” and “Design and implement a comprehensive operational architecture to support
DMO.”24 While Navy officials have provided few details in public about DMO, then-Chief of
Naval Operations Admiral John Richardson, in explaining DMO, stated in December 2018 that
Our fundamental force element right now in many instances is the [individual] carrier strike
group. We’re going to scale up so our fundamental force element for fighting is at the
fleet[-wide] level, and the [individual] strike groups plug into those [larger] numbered
fleets. And they will be, the strike groups and the fleet together, will be operating in a
distributed maritime operations way.25
In its FY2020 budget submission, the Navy states that “MUSV and LUSV are key enablers of the
Navy’s Distributed Maritime Operations (DMO) concept, which includes being able to forward
deploy (alone or in teams/swarms), team with individual manned combatants or augment battle
groups.”26 The Navy states in its FY2020 budget submission that a Navy research and
development effort focusing on concept generation and concept development (CG/CD) will
Continue CG/CD development efforts that carry-over from FY[20]19: Additional concepts
and CONOPs [concepts of operation] to be developed in FY[20]20 will be determined
through the CG/CD development process and additional external factors. Concepts under
consideration include Unmanned Systems in support of DMO, Command and Control in
support of DMO, Offensive Mine Warfare, Targeting in support of DMO, and Advanced
Autonomous/Semi-autonomous Sustainment Systems.27
The Navy also states in its FY2020 budget submission that a separate Navy research and
development effort for fleet experimentation activities will include activities that “address key
DMO concept action plan items such as the examination of Fleet Command and Maritime
Operation Center (MOC) capabilities and the employment of unmanned systems in support of
DMO.”28
A May 16, 2019, press report states
The Deputy Chief of Naval Operations for Warfare Systems said Wednesday [May 15] he
thinks the upcoming Force Structure Assessment (FSA) will focus on smaller surface
combatants as the service looks to build up to a 355-ship Navy.
“I certainly don’t see that [FSA fleet] number going down, but it is going to be more
reflective of the DMO [Distributed Maritime Operations] construct and it includes not just
the battle force ships, but the logistics ships, the trainers, the maritime operations centers,

24 U.S. Navy, Chief of Naval Operations, A Design for Maintaining Maritime Superiority, Version 2.0, December 2018,
pp. 8, 10.
25 (Chief of Naval Operations Admiral John Richardson, as quoted in Megan Eckstein, “Navy Planning for Gray-Zone
Conflict; Finalizing Distributed Maritime Operations for High-End Fight,” USNI News, December 19, 2018.)
26 Department of Defense, Fiscal Year (FY) 2020 Budget Estimates, Navy Justification Book Volume 2 of 5, Research,
Development, Test & Evaluation, Navy, Budget Activity 4
, March 2019, p. 202. See also Kevin Eyer and Steve
McJessy, “Operationalizing Distributed Maritime Operations,” Center for International Maritime Security (CIMSEC),
March 5, 2019; Christopher H. Popa, et al, Distributed Maritime Operations and Unmanned Systems Tactical
Employment
, Naval Postgraduate School, June 2018, 171 pp. (Systems Engineering Capstone Report); Lyla Englehorn,
Distributed Maritime Operations (DMO) Warfare Innovation Continuum (WIC) Workshop September 2017 After
Action Report
, Naval Postgraduate School, December 2017, 99 pp.
27 Department of Defense, Fiscal Year (FY) 2020 Budget Estimates, Navy Justification Book Volume 2 of 5, Research,
Development, Test & Evaluation, Navy, Budget Activity 4
, March 2019, p. 1385. See also pp. 1382, 1384, 1443, 1445.
28 Department of Defense, Fiscal Year (FY) 2020 Budget Estimates, Navy Justification Book Volume 4 of 5, Research,
Development, Test & Evaluation, Navy Budget Activity 6
, March 2019, p. 290.
Congressional Research Service

13

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

everything that we pull together to keep this machine running,” Vice Adm. William Merz
said during an event at the Center for Strategic and International Studies.
“What we think is going to happen with this FSA is there will be more emphasis on the
smaller surface combatants, mostly because the frigate looks like it’s coming along very
well and it’s going to be more lethal than we had planned,” Merz said.
Merz explained the likely outcome by comparing it to how Rear Adm. Ron Boxall, director
of surface warfare (N96), talks about how the Navy has too many large surface combatants
and needs to get more balanced.
“When you look at the lethality of the frigate, yeah that makes sense. So we’ll see how the
FSA handles the lethality of that – and then how does that bleed over into the other
accounts,” Merz said….
Merz revealed there will also be “a hard look at the logistics side” because while some
logistics ships count as battle force ships some do not. He said the FSA will make an
opinion on the non-battle force logistics vessels as well because it does not limit itself to
those strict definitions.
The FSA will also take into account the evolution of the air wing, the length of the air wing,
the range of the air wing on carriers and amphibious vessels, and how the Navy will cover
its responsibilities.29
Expeditionary Advanced Base Operations (EABO)
In parallel with DMO, the Marine Corps has developed a new operational concept, called
Expeditionary Advanced Base Operations (EABO), that appears related to the earlier-quoted
passage from the Commandant’s Planning Guidance about changing the amphibious lift goal and
the amphibious force architecture. Regarding EABO, the Commandant’s Planning Guidance
states the following (emphasis as in the original):
The 2016 Marine Corps Operating Concept (MOC) predates the current set of national
strategy and guidance documents, but it was prescient in many ways. It directed partnering
with the Navy to develop two concepts, Littoral Operations in a Contested Environment
(LOCE) and Expeditionary Advanced Base Operations (EABO) that nest exceptionally
well with the current strategic guidance. It is time to move beyond the MOC itself,
however, and partner with the Navy to complement LOCE and EABO with classified,
threat-specific operating concepts that describe how naval forces will conduct the range of
missions articulated in our strategic guidance….
EABO complement the Navy’s Distributed Maritime Operations Concept and will
inform how we approach missions against peer adversaries
….
EABO are driven by the aforementioned adversary deployment of long-range precision
fires designed to support a strategy of “counter-intervention” directed against U.S. and
coalition forces. EABO, as an operational concept, enables the naval force to persist
forward within the arc of adversary long-range precision fires to support our treaty partners
with combat credible forces on a much more resilient and difficult to target forward basing
infrastructure. EABO are designed to restore force resiliency and enable the persistent
naval forward presence that has long been the hallmark of naval forces. Most significantly,
EABO reverse the cost imposition that determined adversaries seek to impose on the joint
force. EABO guide an apt and appropriate adjustment in future naval force development
to obviate the significant investment our adversaries have made in long-range precision
fires. Potential adversaries intend to target our forward fixed and vulnerable bases, as well
as deep water ports, long runways, large signature platforms, and ships. By developing a

29 Rich Abott, “Merz Says FSA To Emphasize Smaller Ships,” Defense Daily, May 16, 2019.
Congressional Research Service

14

link to page 21 link to page 21 link to page 21 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

new expeditionary naval force structure that is not dependent on concentrated, vulnerable,
and expensive forward infrastructure and platforms, we will frustrate enemy efforts to
separate U.S. Forces from our allies and interests. EABO enable naval forces to partner
and persist forward to control and deny contested areas where legacy naval forces cannot
be prudently employed without accepting disproportionate risk….
In February of 2019, the Commandant and Chief of Naval Operations co-signed the
concept for EABO. The ideas contained in this document are foundational to our future
force development efforts and are applicable in multiple scenarios.30
Navy’s Five-Year and 30-Year Shipbuilding Plans
FY2020 Five-Year (FY2020-FY2024) Shipbuilding Plan
Table 2 shows the Navy’s FY2020 five-year (FY2020-FY2024) shipbuilding plan. The table also
shows, for reference purposes, the ships funded for procurement in FY2019. The figures in the
table reflect a Navy decision to show the aircraft carrier CVN-81 as a ship to be procured in
FY2020 rather than a ship that was procured in FY2019. Congress, as part of its action on the
Navy’s proposed FY2019 budget, authorized the procurement of CVN-81 in FY2019.31
As shown in Table 2, the Navy’s proposed FY2020 budget requests funding for the procurement
of 12 new ships, including one Gerald R. Ford (CVN-78) class aircraft carrier, three Virginia-
class attack submarines, three DDG-51 class Aegis destroyers, one FFG(X) frigate, two John
Lewis (TAO-205) class oilers, and two TATS towing, salvage, and rescue ships. If the Navy had
listed CVN-81 as a ship procured in FY2019 rather than a ship to be procured in FY2020, then
the total numbers of ships in FY2019 and FY2020 would be 14 and 11, respectively.
As also shown in Table 2, the Navy’s FY2020 five-year (FY2020-FY2024) shipbuilding plan
includes 55 new ships, or an average of 11 new ships per year. The Navy’s FY2019 budget
submission also included a total of 55 ships in the period FY2020-FY2024, but the mix of ships
making up the total of 55 for these years has been changed under the FY2020 budget submission
to include one additional attack submarine, one additional FFG(X) frigate, and two (rather than
four) LPD-17 Flight II amphibious ships over the five-year period. The FY2020 submission also
makes some changes within the five-year period to annual procurement quantities for DDG-51
destroyers, ESBs, and TAO-205s without changing the five-year totals for these programs.
Compared to what was projected for FY2020 itself under the FY2019 budget submission, the
FY2020 request accelerates from FY2023 to FY2020 the aircraft carrier CVN-81 (as a result of
Congress’s action to authorize the ship in FY2019), adds a third attack submarine, accelerates
from FY2021 into FY2020 a third DDG-51, defers from FY2020 to FY2021 an LPD-17 Flight II
amphibious ship to FY2021, defers from FY2020 to FY2023 an ESB ship, and accelerates from
FY2021 to FY2020 a second TAO-205 class oiler.

30 U.S. Marine Corps, Commandant’s Planning Guidance, 38th Commandant of the Marine Corps, undated, released
July 2019, pp. 9, 11, 19. See also Jim Lacey, “The ‘Dumbest Concept Ever’ Just Might Win Wars,” War on the Rocks,
July 29, 2019; Megan Eckstein, “How to Seize Islands, Set Up a Forward Refueling Point: Marine Corps Recipes for
Exspeditionary Operations,” USNI News, September 13, 2019.
31 For further discussion, see CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program:
Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service

15

link to page 22 link to page 22 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Table 2. FY2020 Five-Year (FY2020-FY2024) Shipbuilding Plan
FY2019 shown for reference
FY20-
FY19
FY20
FY24

(enacted) (req.) FY21 FY22 FY23 FY24 Total
Columbia (SSBN-826) class ballistic missile submarine


1


1
2
Gerald R. Ford (CVN-78) class aircraft carrier

1




1
Virginia (SSN-774) class attack submarine
2
3
2
2
2
2
11
Arleigh Burke (DDG-51) class destroyer
3
3
2
2
3
3
13
Littoral Combat Ship (LCS)
3





0
FFG(X) frigate

1
2
2
2
2
9
LHA amphibious assault ship





1
1
LPD-17 Fight II amphibious ship


1

1

2
Expeditionary Sea Base (ESB) ship
1



1

1
Expeditionary Fast Transport (EPF) ship
1





0
John Lewis (TAO-205) class oiler
2
2
1
1
2
1
7
TATS towing, salvage, and rescue ship
1
2
1
1
1

5
TAGOS(X) ocean surveillance ship



1
1
1
3
TOTAL
13
12
10
9
13
11
55
Source: Table prepared by CRS based on FY2020 Navy budget submission.
Notes: Ships shown are battle force ships—ships that count against 355-ship goal. The figures in the table reflect
a Navy decision to show the aircraft carrier CVN-81 as a ship to be procured in FY2020 rather than a ship that
was procured in FY2019. Congress, as part of its action on the Navy’s proposed FY2019 budget, authorized the
procurement of CVN-81 in FY2019.
FY2020 30-Year (FY2020-FY2049) Shipbuilding Plan
Table 3 shows the Navy’s FY2020-FY2049 30-year shipbuilding plan. In devising a 30-year
shipbuilding plan to move the Navy toward its ship force-structure goal, key assumptions and
planning factors include but are not limited to ship construction times and service lives, estimated
ship procurement costs, projected shipbuilding funding levels, and industrial-base considerations.
As shown in Table 3, the Navy’s FY2020 30-year shipbuilding plan includes 304 new ships, or
an average of about 10 per year.
Congressional Research Service

16

link to page 23 link to page 22 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Table 3. FY2020 30-Year (FY2020-FY2049) Shipbuilding Plan
FY
CVNs
LSCs
SSCs SSNs
LPSs
SSBNs
AWSs
CLFs Supt Total
20
1
3
1
3



2
2
12
21

2
2
2

1
1
1
1
10
22

2
2
2



1
2
9
23

3
2
2


1
2
3
13
24

3
2
2

1
1
1
1
11
25

3
2
2


1
1
2
11
26

2
2
2

1
1
1
2
11
27

3
2
2

1
2
1
1
12
28
1
2
2
2

1
1
1
1
11
29

3
2
2

1
1
1
1
11
30

2
1
2

1
1
1
2
10
31

3
2
2

1
2
1
2
13
32
1
2
2
2

1
1
1
2
12
33

3
2
2

1
1
1
2
12
34

2
2
2

1
2

2
11
35

3
2
2

1


1
9
36
1
2
2
2
1




8
37

3
2
2





7
38

2
2
2


1


7
39

3
2
2
1




8
40
1
2
2
2


1


8
41

3
2
2


1


8
42

2
2
2
1

1


8
43

3
2
2



1

8
44
1
2
2
2


1


8
45

3
2
2
1

2
2

12
46

2
2
2


1
2

9
47

3
2
2


1
2

10
48
1
2
2
2
1

2
2

12
49

3
2
2


1
2
3
13
Total
7
76
58
61
5
12
28
27
30
304
Source: U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, Table A2-1 on page 13.
Key: FY = Fiscal Year; CVNs = aircraft carriers; LSCs = surface combatants (i.e., cruisers and destroyers);
SSCs = small surface combatants (i.e., Littoral Combat Ships [LCSs] and frigates [FFG(X)s]); SSNs = attack
submarines; LPSs = large payload submarines; SSBNs = ballistic missile submarines; AWSs = amphibious
warfare ships; CLFs = combat logistics force (i.e., resupply) ships; Supt = support ships.
Projected Force Levels Under FY2020 30-Year Shipbuilding Plan
Overview
Table 4 shows the Navy’s projection of ship force levels for FY2020-FY2049 that would result
from implementing the FY2020 30-year (FY2020-FY2049) 30-year shipbuilding plan shown in
Table 3.
Congressional Research Service

17

link to page 23 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Table 4. Projected Force Levels Resulting from FY2020 30-Year Shipbuilding Plan

CVNs LSCs SSCs SSNs SSGN/LPSs SSBNs AWSs CLFs Supt Total
355-ship
12
104
52
66
0
12
38
32
39
355
goal
FY20
11
94
30
52
4
14
33
29
34
301
FY21
11
92
33
53
4
14
34
30
34
305
FY22
11
93
33
52
4
14
34
31
39
311
FY23
11
95
32
51
4
14
35
31
41
314
FY24
11
94
35
47
4
14
36
32
41
314
FY25
10
95
35
44
4
14
37
32
42
313
FY26
10
96
36
44
2
14
38
31
43
314
FY27
9
100
38
42
1
13
37
32
44
316
FY28
10
102
41
42

13
38
32
44
322
FY29
10
104
43
44

12
36
32
44
325
FY30
10
107
45
46

11
36
32
44
331
FY31
10
110
47
48

11
36
32
43
337
FY32
10
112
49
49

11
36
32
44
343
FY33
10
115
50
51

11
38
32
44
351
FY34
10
117
52
53

11
36
32
44
355
FY35
10
114
55
54

11
34
32
45
355
FY36
10
109
57
56

11
35
32
45
355
FY37
10
107
58
58

10
35
32
45
355
FY38
10
108
59
57

10
35
32
44
355
FY39
10
105
61
58

10
37
32
42
355
FY40
9
105
62
59

10
37
32
41
355
FY41
10
104
61
59

11
37
32
41
355
FY42
9
106
60
61

12
36
32
39
355
FY43
9
108
57
61
1
12
36
32
39
355
FY44
9
109
55
62
1
12
36
32
39
355
FY45
10
107
55
63
1
12
36
32
39
355
FY46
9
106
54
64
2
12
37
32
39
355
FY47
9
107
54
65
2
12
35
32
39
355
FY48
9
109
51
66
2
12
35
32
39
355
FY49
10
108
50
67
3
12
35
31
39
355
Source: U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, Table A2-4 on page 13.
Note: Figures for support ships include five JHSVs transferred from the Army to the Navy and operated by the
Navy primarily for the performance of Army missions.
Key: FY = Fiscal Year; CVNs = aircraft carriers; LSCs = surface combatants (i.e., cruisers and destroyers);
SSCs = small surface combatants (i.e., frigates, Littoral Combat Ships [LCSs], and mine warfare ships); SSNs =
attack submarines; SSGNs/LPSs = cruise missile submarines/large payload submarines; SSBNs = ballistic
missile submarines; AWSs = amphibious warfare ships; CLFs = combat logistics force (i.e., resupply) ships;
Supt = support ships.
As shown in Table 4, if the FY2020 30-year shipbuilding plan is implemented, the Navy projects
that it will achieve a total of 355 ships by FY2034. This is about 20 years sooner than projected
under the Navy’s FY2019 30-year shipbuilding plan. This is not primarily because the FY2020
30-year plan includes more ships than did the FY2019 plan: The total of 304 ships in the FY2020
Congressional Research Service

18

link to page 24 link to page 23 link to page 23 link to page 24 link to page 23 link to page 24 link to page 23
Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

plan is only 3 ships higher than the total of 301 ships in the FY2019 plan. Instead, it is primarily
due to a decision announced by the Navy in April 2018, after the FY2019 budget was submitted,
to increase the service lives of all DDG-51 destroyers—both those existing and those to be built
in the future—to 45 years. Prior to this decision, the Navy had planned to keep older DDG-51s
(referred to as the Flight I/II DDG-51s) in service for 35 years and newer DDG-51s (the Flight
II/III DDG-51s) for 40 years. Figure 2 shows the Navy’s projections for the total number of ships
in the Navy under the Navy’s FY2019 and FY2020 budget submissions. As can be seen in the
figure, the Navy projected under the FY2019 plan that the fleet would not reach a total of 355
ships any time during the 30-year period.
Figure 2. Projected Size of Navy Under FY2019 and FY2020 30-Year
Shipbuilding Plans

Source: U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, Figure A2-1 on page 14. PB2020 and PB2019 mean President’s Budget (i.e., the Administration’s proposed
budget) for FY2020 and FY2019, respectively.
Adjustment Needed for Withdrawn Proposal Regarding CVN-75 RCOH
The projected number of aircraft carriers in Table 4, the projected total number of all ships in
Table 4, and the line showing the total number of ships under the Navy’s FY2020 budget
submission in Figure 2 all reflect the Navy’s proposal, under its FY2020 budget submission, to
not fund the mid-life nuclear refueling overhaul (called a refueling complex overhaul, or RCOH)
of the aircraft carrier Harry S. Truman (CVN-75), and to instead retire CVN-75 around FY2024.
On April 30, 2019, however, the Administration announced that it was withdrawing this proposal
from the Navy’s FY2020 budget submission. The Administration now supports funding the CVN-
75 RCOH and keeping CVN-75 in service past FY2024.
As a result of the withdrawal of its proposal regarding the CVN-75 RCOH, the projected number
of aircraft carriers and consequently the projected total number of all ships are now one ship
higher for the period FY2022-FY2047 than what is shown in Table 4, and the line in Figure 2
would be adjusted upward by one ship for those years.32 (The figures in Table 4 are left
unchanged from what is shown in the FY2020 budget submission so as to accurately reflect what
is shown in that budget submission.)

32 For additional discussion of the now-withdrawn proposal concerning the CVN-75 RCOH, see CRS Report RS20643,
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress, by Ronald O'Rourke.
Congressional Research Service

19

link to page 23 link to page 26 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

355-Ship Total Attained 20 Years Sooner; Mix Does Not Match FSA Mix
As shown in Table 4, although the Navy projects that the fleet will reach a total of 355 ships in
FY2034, the Navy in that year and subsequent years will not match the composition called for in
the FY2016 FSA. Among other things, the Navy will have more than the required number of
large surface combatants (i.e., cruisers and destroyers) from FY2030 through FY2040 (a
consequence of the decision to extend the service lives of DDG-51s to 45 years), fewer than the
required number of aircraft carriers through the end of the 30-year period, fewer than the required
number of attack submarines through FY2047, and fewer than the required number of amphibious
ships through the end of the 30-year period. The Navy acknowledges that the mix of ships will
not match that called for by the 2016 FSA but states that if the Navy is going to have too many
ships of a certain kind, DDG-51s are not a bad type of ship to have too many of, because they are
very capable multi-mission ships.
Issues for Congress
How INFSA Will Change Fleet Architecture, 355-Ship Goal, Mix of
Ships to Be Procured, and Distribution of Shipbuilding Work
One issue for Congress is how the INFSA will change the Navy’s fleet architecture, the Navy’s
current 355-ship force-level goal, the mix of Navy ships to be procured, and the distribution of
Navy shipbuilding work among the nation’s shipyards.
Degree to Which INFSA Is Incorporated into FY2020 Budget
A related issue for Congress is the degree to which the results of the INFSA will be incorporated
into the Navy’s proposed FY2020 budget, and how Congress should assess the Navy’s proposed
FY2020 budget if additional aspects of the INFSA will not become clear until the Navy submits
its proposed FY2022 budget or its proposed FY2023 budget.
Affordability of 30-Year Shipbuilding Plan
Overview
Another oversight issue for Congress has concerned the prospective affordability of the Navy’s
30-year shipbuilding plan. This issue has been a matter of oversight focus for several years, and
particularly since the enactment in 2011 of the Budget Control Act, or BCA (S. 365/P.L. 112-25
of August 2, 2011). Aspects of this issue could change if the INFSA shifts the Navy to a new fleet
architecture and a changed mix of ships to be procured in coming years. The discussion below is
based on the Navy’s current fleet architecture.
Based on the Navy’s current fleet architecture, observers have been particularly concerned about
the 30-year shipbuilding plan’s prospective affordability during the decade or so from the mid-
2020s through the mid-2030s, when the plan calls for procuring Columbia-class ballistic missile
submarines as well as replacements for large numbers of retiring attack submarines, cruisers, and
destroyers.33 Figure 3 shows, in a graphic form, the Navy’s estimate of the annual amounts of

33 The Navy’s 30-year plans in recent years have spotlighted for policymakers the substantial increase in Navy
shipbuilding funding that would be required to implement the 30-year plan during the decade or so from the mid-2020s
Congressional Research Service

20


Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

funding that would be needed to implement the Navy’s FY2020 30-year shipbuilding plan. The
figure shows that during the period from the mid-2020s through the mid-2030s, the Navy
estimates that implementing the FY2020 30-year shipbuilding plan would require roughly $24
billion per year in shipbuilding funds.
Figure 3. Navy Estimate of Funding Requirements for FY2020 30-Year Plan
Constant FY2019 dollars, in millions

Source: U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, Figure A4-1 on page 18.
Concern Regarding Potential Impact of Columbia-Class Program
As discussed in the CRS report on the Columbia-class program,34 the Navy since 2013 has
identified the Columbia-class program as its top program priority, meaning that it is the Navy’s
intention to fully fund this program, if necessary at the expense of other Navy programs,
including other Navy shipbuilding programs. This led to concerns that in a situation of finite
Navy shipbuilding budgets, funding requirements for the Columbia-class program could crowd
out funding for procuring other types of Navy ships. These concerns in turn led to the creation by
Congress of the National Sea-Based Deterrence Fund (NSBDF), a fund in the DOD budget that is
intended in part to encourage policymakers to identify funding for the Columbia-class program
from sources across the entire DOD budget rather than from inside the Navy’s budget alone.
Several years ago, when concerns arose about the potential impact of the Columbia-class program
on funding available for other Navy shipbuilding programs, the Navy’s shipbuilding budget was

through the mid-2030s. As discussed in CRS testimony in 2011, a key function of the 30-year shipbuilding plan is to
alert policymakers well ahead of time to periods of potentially higher funding requirements for Navy shipbuilding. (See
Statement of Ronald O’Rourke, Specialist in Naval Affairs, Congressional Research Service, before the House Armed
Services Committee, Subcommittee on Oversight and Investigations, hearing on the Department of Defense’s 30-Year
Aviation and Shipbuilding Plans, June 1, 2011, 8 pp.)
34 CRS Report R41129, Navy Columbia (SSBN-826) Class Ballistic Missile Submarine Program: Background and
Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service

21

link to page 26 link to page 26 link to page 28 link to page 26 link to page 28 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

roughly $14 billion per year, and the roughly $7 billion per year that the Columbia-class program
is projected to require from the mid-2020s to the mid-2030s (see Figure 3) represented roughly
one-half of that total. With the Navy’s shipbuilding budget having grown in more recent years to
a total of roughly $24 billion per year, the $7 billion per year projected to be required by the
Columbia-class program during those years does not loom proportionately as large as it once did
in the Navy’s shipbuilding budget picture. Even so, some concerns remain regarding the potential
impact of the Columbia-class program on funding available for other Navy shipbuilding
programs.
Potential for Cost Growth on Navy Ships
If one or more Navy ship designs turn out to be more expensive to build than the Navy estimates,
then the projected funding levels shown in Figure 3 would not be sufficient to procure all the
ships shown in the 30-year shipbuilding plan. As detailed by CBO35 and GAO,36 lead ships in
Navy shipbuilding programs in many cases have turned out to be more expensive to build than
the Navy had estimated. Ship designs that can be viewed as posing a risk of being more expensive
to build than the Navy estimates include Gerald R. Ford (CVN-78) class aircraft carriers,
Columbia-class ballistic missile submarines, Virginia-class attack submarines equipped with the
Virginia Payload Module (VPM), Flight III versions of the DDG-51 destroyer, FFG(X) frigates,
LPD-17 Flight II amphibious ships, and John Lewis (TAO-205) class oilers, as well as other new
classes of ships that the Navy wants to begin procuring years from now.
CBO Estimate
The statute that requires the Navy to submit a 30-year shipbuilding plan each year (10 U.S.C.
231) also requires CBO to submit its own independent analysis of the potential cost of the 30-year
plan (10 U.S.C. 231[d]). Figure 4 shows, in a graphic form, CBO’s estimate of the annual
amounts of funding that would be needed to implement the Navy’s FY2020 30-year shipbuilding
plan. This figure can be compared to the Navy’s estimate of its FY2020 30-year plan as shown in
Figure 3.
CBO analyses of past Navy 30-year shipbuilding plans have generally estimated the cost of
implementing those plans to be higher than what the Navy estimated. Consistent with that past
pattern, as shown in Table 5, CBO’s estimate of the cost to implement the Navy’s FY2020 30-
year shipbuilding plan is about 31% higher than the Navy’s estimated cost for the FY2020 plan.
More specifically, as shown in the table, CBO estimated that the cost of the first 10 years of the
FY2020 30-year plan would be about 2% higher than the Navy’s estimate; that the cost of the
middle 10 years of the plan would be about 21% higher than the Navy’s estimate; and that the
cost of the final 10 years of the plan would be about 41% higher than the Navy’s estimate.37
Treatment of Inflation
The growing divergence between CBO’s estimate and the Navy’s estimate as one moves from the
first 10 years of the 30-year plan to the final 10 years of the plan is due in part to a technical

35 See Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2019 Shipbuilding Plan, October 2018, p.
25, including Figure 10.
36 See Government Accountability Office, Navy Shipbuilding[:] Past Performance Provides Valuable Lessons for
Future Investments
, GAO-18-238SP, June 2018, p. 8.
37 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2020 Shipbuilding Plan, October 2019, Table 4
on page 13.
Congressional Research Service

22


Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

difference between CBO and the Navy regarding the treatment of inflation. This difference
compounds over time, making it increasingly important as a factor in the difference between
CBO’s estimates and the Navy’s estimates the further one goes into the 30-year period. In other
words, other things held equal, this factor tends to push the CBO and Navy estimates further apart
as one proceeds from the earlier years of the plan to the later years of the plan.38
Figure 4. CBO Estimate of Funding Requirements for 30-Year Plan
Constant FY2019 dollars, in billions

Source: Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2020 Shipbuilding Plan, October 2019,
Figure 8 on page 16.
Table 5. Navy and CBO Estimates of Cost of 30-Year Shipbuilding Plan
Funding for new-construction ships, in billions of constant FY2019 dollars
Middle 10
Entire 30
First 10 years
years of the
Final 10 years
years of the

of the plan
plan
of the plan
plan
Navy estimate
20.3
24.4
21.8
22.0
CBO estimate
20.7
29.7
30.7
28.8
% difference between Navy
2
21
41
31
and CBO estimates

38 For additional discussion of how CBO estimates the costs of new Navy ships, see Congressional Budget Office, How
CBO Estimates the Cost of New Ships
, April 2018, 6 pp.
Congressional Research Service

23

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Source: Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2020 Shipbuilding Plan, October 2019,
Table 4 on page 13.
Notes: The figures shown for “% difference” are those presented in the CBO report, which are derived from
dol ar figures for the Navy and CBO estimates that were subsequently rounded off by CBO for presentation in
its report. This is why the figure for “% difference” for the middle 10 years of the plan shows as 21% rather than
22%.
Designs of Future Classes of Ships
The growing divergence between CBO’s estimate and the Navy’s estimate as one moves from the
first 10 years of the 30-year plan to the final 10 years of the plan is also due to differences
between CBO and the Navy about the costs of certain ship classes, particularly classes that are
projected to be procured starting years from now. The designs of these future ship classes are not
yet determined, creating more potential for CBO and the Navy to come to differing conclusions
regarding their potential cost.
For the FY2020 30-year plan, the largest source of difference between CBO and the Navy
regarding the costs of individual ship classes is a new class of SSNs that the Navy wants to begin
procuring in FY2031 as the successor to the Virginia-class SSN design. This new class of SSNs,
CBO says, accounts for 34% of the difference between the CBO and Navy estimates for the
FY2020 30-year plan, in part because there are a substantial number of these SSNs in the plan,
and because those ships occur in the latter years of the plan, where the effects of the technical
difference between CBO and the Navy regarding the treatment of inflation show more strongly.
The second-largest source of difference between CBO and the Navy regarding the costs of
individual ship classes is a new class of large surface combatant (i.e., cruiser or destroyer) that the
Navy wants to begin procuring in FY2025, which accounts for 33% of the difference, for reasons
that are similar to those mentioned above for the new class of SSNs.
The third-largest source of difference is the new class of frigates (FFG[X]s) that the Navy wants
to begin procuring in FY2020, which accounts for 10% of the difference.
The remaining 23% of difference between the CBO and Navy estimates is accounted for
collectively by several other shipbuilding programs, each of which individually accounts for
between 1% and 4% of the difference. The Columbia-class program, which accounts for 4% of
the difference, is one of the programs in this final group.39
Sustainment Cost
In addition to the issue of the cost to build new ships, the Navy in its FY2020 30-year
shipbuilding plan highlighted a concern over the potential costs to sustain a larger fleet. On this
issue, the FY2020 30-year shipbuilding plan states in part
Coincident with the relatively new dynamic of purchasing more ships to grow the force
instead of simply replacing ships or shrinking the force, is the responsibility to “own” the
additional inventory when it arrives.
Consistent annual funding in the shipbuilding account is foundational for an efficient
industrial base in support of steady growth and long-term maintenance planning, but
equally important is the properly phased, additional funding needed for operations and
sustainment accounts as each new ship is delivered—the much larger fiscal burden over
the life of a ship and the essence of the challenge to remain balanced across the three

39 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2020 Shipbuilding Plan, October 2019, Table
A-1 on page 29.
Congressional Research Service

24

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

integral elements of readiness–capability–capacity. Because the Navy [until recently] has
been shrinking not growing, and because of the disconnected timespan from purchase to
delivery, often five years or more and often beyond the FYDP, there is risk of
underestimating the aggregate sustainment costs looming over the horizon that must now
be carefully considered in fiscal forecasting.
For a ship, the rough rule of thumb for cost is 30 percent for procurement and 70 percent
for operating and sustainment; for example, a ship that costs $1B to buy costs $3.3B to
own, amortized over its lifespan. Accordingly, multi-ship deliveries can add hundreds of
millions of dollars to a budget year, and then require the same funding per year thereafter,
compounded by additional deliveries in subsequent years and only offset by ship
retirements, which lag deliveries when growing the force. A similar dynamic occurs when
the life of a ship is extended. Sustainment resources programmed to shift from a retiring
ship to a new ship must now stay in place – for the duration of the extension. The burden
continues to grow until equilibrium is reached at the desired higher inventory, when
deliveries match retirements and all resourcing accounts reach steady-state at a higher,
enduring sustainment cost.
For perspective, the current budget, among the largest ever, supports a modern fleet of
approximately 300 ships, nearly 20 percent fewer than the goal of 355. The battle force
inventory… rises from 301 ships in FY2020 to [a projected figure of] 314 ships in FY2024,
and then 355 in FY2034. The programmed sustainment cost… is $24B [billion] in FY2020
and rises to $30B [billion in FY2024 in TY$ [then-year dollars]. When the battle force
inventory reaches 355 in FY2034, [the] estimated cost to sustain that fleet will approach
$40B (TY$), 32% higher than in FY2024. For now, included in this sustainment estimate
are only personnel, planned maintenance, and some operations; representing those costs
tied directly to owning and operating a ship, easily modeled today, and already line-item
accounted for in the budget. Equally important additional costs, but not yet included in the
future estimate, are those not easily associated with individual ships and require complex
modeling for long-term forecasting (beyond 3 to 5 years), such as the balance of the
operations accounts (market and schedule driven), modernization and ordnance (threat and
technology driven), infrastructure and training (services spread across many ships),
aviation detachments, networks and cyber support, plus others….
Less of a challenge when shrinking the force, the Navy is now working towards developing
the complex model needed to capture indirect costs for growing the force. Until then, macro
ratios are helpful in estimating rough orders of magnitude beyond the FYDP and for
identifying future areas of concern. Similar to procurement, estimates will be less precise
deeper into the plan. Recovering from the long-term investment imbalance has proven to
be costly, particularly in the readiness accounts. As readiness becomes more accurately
defined, the modeling will improve and so will the ability to more accurately forecast.
However, no matter the method, the anticipated cost of sustaining the proper mix of 355
ships is anticipated to be substantial, and reform efforts and balanced scalability will
continue to be the drivers going forward.40
A May 15, 2019, press report states:
The service [the navy] is also getting some sobering feedback on how much it will cost to
sustain a significantly larger fleet— something it hasn’t had to do in decades.
As the Navy plans for more ships, Vice Adm. William Merz Deputy Chief Of Naval
Operations For Warfare Systems said Wednesday, “we’re also coming to realize what that
is going to cost, and how you’re going to sustain today’s fleet while continuing to grow.”

40 U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year
2020
, pp. 19-20.
Congressional Research Service

25

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The planning process is “much more challenging than anyone realized,” he said, “but we’re
much smarter about our business” than just a few years ago….
… taking the fleet from under 300 ships to at least 355 is a daunting task, Merz said at the
Center for Strategic and International Studies. “We don’t have the complex modeling to
even understand what all of these costs are going to materialize to over the next 20 years,”
he said, but the service is “working hard to converge on a model” to sustain the ships over
the long haul.41
Recent Navy Statements About Not Being Able to Afford More Than 310 Ships
at Current Funding Levels

Navy officials in September and October 2019 stated that if Navy budgets in coming years
remain at current levels in real (i.e., inflation-adjusted terms), the Navy would not be able to
properly maintain a fleet of more than 302 to 310 ships.
A September 16, 2019, press report quoted Under Secretary of the Navy Thomas Modly as stating
in a speech on that date: “I will tell you it is going to be very, very difficult for us to get to that
number [355 ships] in any reasonable amount of time.” According to the press report, Modly
stated: “If you look at our funding in the [Navy] and straight line that on our current budget
projections, we can probably get to about 305 to 308 ships and sustain that over time without a
significant increase in our budget.” The press report stated that “the under secretary said the
service [i.e., the Navy] would likely need $20 billion to $30 billion more annually to achieve a
355-ship fleet ‘quickly, and when I say “quickly” I mean within five to 10 years.’”42
An October 27, 2019, press report, reporting on remarks made by Under Secretary Modly on
October 25, stated:
The size of the current fleet, the high cost of new ships and the likely lack of growth in
future budgets will make it difficult for the Navy to reach the current goal of a 355-ship
battle fleet, the Navy’s number two civilian leader [Modly] said….
Modly went through the top 10 issues that keep him up at night, three of which dealt with
the problem of buying and sustaining enough ships to get the size fleet the U.S. Navy will
need for the possible future conflicts. The effort to get from the current 290-ship force to
the 355 goal faces “a math problem,” he said, because future defense budgets are not likely
to grow enough to buy all those ships.43
An October 28, 2019, press report stated:
The Navy is unlikely to field a 355-ship fleet in the near- or even mid-term future if funding
doesn’t change dramatically, the department’s top leadership said during a pair of
appearances last week.
The 355-ship Navy is a nice target; however, ship readiness is more critical for the service
as it plans how the fleet will look in the future, Vice Chief of Naval Operations Adm.
Robert Burke said Friday [October 25] while speaking with reporters at the Military
Reporters and Editors conference.

41 Paul McLeary, “Navy Wary of Growing Costs While It Ramps Up Ops,” Breaking Defense, May 15, 2019.
42 Justin Katz, “Modly Acknowledges 355 Ships Won’t Happen in ‘Reasonable’ Amount of Time,” Inside Defense,
September 16, 2019.
43 Otto Kreisher, “Modly Doubts Future Budgets Will Allow for 355-Ship Fleet,” Seapower, October 27, 2019.
Congressional Research Service

26

link to page 90 link to page 90 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

“Will we get to 355-ships?” Burke said. “I think with today’s fiscal situation, where the
Navy’s top line is right now, we can keep around 305 to 310 ships whole, properly manned,
properly maintained, properly equipped, and properly ready.”…
“If our top line does not go up, if it remains where it is now and is projected to remain in
the future defense plans, that’s about where we can get to and do it right, in terms of man
those ships and maintain them and have all the ordnance for them and generate readiness,”
Burke said. “We would need an increased top line.”44
Potential Impacts of a CR on FY2020 Navy Shipbuilding Programs
Another issue for Congress concerns the potential impacts on FY2020 Navy shipbuilding
programs of using one or more continuing resolutions (CRs) to fund DOD operations for at least
some portion of FY2020. For general background information on the potential impacts of CRs on
Navy shipbuilding programs, see Appendix I.
DOD Operations Currently Being Funded by a CR (H.R. 3055/P.L. 116-69)
Federal government agency operations, including DOD operations, are currently being funded in
FY2020 under a CR (H.R. 3055/P.L. 116-69 of November 21, 2019, the Further Continuing
Appropriations Act, 2020, and Further Health Extenders Act of 2019). Consistent with CRs that
have been used to fund federal government agency operations during parts of prior fiscal years,
H.R. 3055/P.L. 116-69, as the successor to a previous CR, includes, among other things,
prohibitions for DOD on
 new program starts (“new starts”), meaning the initiation of new program efforts
that did not exist in the prior year—a prohibition that includes not only the
initiation of new acquisition programs, but also the shifting of an existing
acquisition program from its research and development phase to its procurement
phase;
 an increase in procurement quantity for a program compared to that program’s
procurement quantity in the prior year; and
 the signing of new multiyear procurement (MYP) contracts.
In addition, as discussed in Appendix I, programs funded through the Navy’s shipbuilding
budget (the Shipbuilding and Conversion, Navy, or SCN, appropriation account) are—uniquely
among DOD acquisition programs—subject to being impacted by year-to-year misalignments in
line-item funding levels, because under a CR, SCN funding is managed at the line-item level, not
at the account level, as it is for the DOD acquisition programs.
H.R. 3055/P.L. 116-69 no anomalies (i.e., program-specific legislative provisions) to protect
specific Navy shipbuilding programs from the potential impacts of the CR.
Summary of Potential Impacts on FY2020 Navy Shipbuilding Programs
Potential impacts of DOD operations being funded under a CR on FY2020 Navy shipbuilding
program as identified by CRS are summarized below. The items listed below are not necessarily
the only potential CR-related impacts on FY2020 Navy shipbuilding programs.

44 Ben Werner, “Admiral: Navy Can Afford to Field a 310-Ship Fleet, Not 355,” USNI News, October 28, 2019. See
also Rich Abott, “Navy Says Current Funding Only Supports 310 Ships,” Defense Daily, October 28, 2019; Paul
McLeary, “Navy May Scrap Goal of 355 Ships; 310 Is Likely,” Breaking Defense, October 25, 2019.
Congressional Research Service

27

link to page 90 link to page 90 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

As discussed in Appendix I, the military services have observed that in many cases in recent
years, CRs have been used to fund DOD for the first few months of the fiscal year. As an apparent
adaptation, DOD program managers are now structuring their programs to reduce the potential
impacts of DOD being funded during the first few months of the fiscal year by CRs.
Consequently, if DOD operations are funded under a CR for less than 90 days of FY2020, the
potential impacts listed below might be relatively limited.
Potential impacts during the period of CR funding would appear to include the following:
Impacts related to prohibition on new starts. FY2020 Navy shipbuilding
programs that may be affected by the CR’s prohibition on new starts include the
following:
FFG(X) frigate program. The CR’s prohibition on new starts would appear
to prohibit the Navy from using CR-provided funding for procuring the
requested first FFG(X) frigate in FY2020. The Navy plans to award the
contract for the detail design and construction (DD&C) of this ship in July
2020 (i.e., the fourth quarter of FY2020).
Cost-to-complete (CTC) funding for prior-year ships. The CR’s
prohibition on new starts would appear to prohibit the Navy from using CR-
provided funding for completing the construction of certain ships that were
procured in prior fiscal years, since, as discussed in Appendix I, CTC work
is considered to be a new start. Programs that would appear to be affected,
since they are the programs for which the Navy requested CTC funding for
FY2020, include
 the Expeditionary Support Base (ESB) ship program,
 the Littoral Combat Ship (LCS) program, and
 the TAO-205 class oiler program.
Impacts related to prohibition on increasing a program’s procurement
quantity. FY2020 Navy shipbuilding programs not already listed above that may
be affected by the CR’s prohibition on increasing a program’s procurement
quantity include the following:
Gerald R. Ford (CVN-78) class aircraft carrier program. Based on the
Navy’s FY2020 budget submission, the CR’s prohibition on increasing a
program’s procurement quantity would appear to prohibit the Navy from
using CR-provided funding for procuring CVN-81, the Ford-class carrier that
is presented in the budget submission as being requested for procurement for
FY2020, since under the budget submission’s presentation, no Ford-class
carrier was procured in FY2019. Such an impact could affect not only CVN-
81 itself, but more generally the executability of the current two-carrier
contract for CVN-80 and CVN-81, which in turn could affect the
construction sequence and construction cost of CVN-80. As discussed in the
CRS report on the CVN-78 program,45 however, Congress’s action on the
Navy’s FY2019 budget provides grounds for arguing that CVN-81 is a ship
that was procured in FY2019, and that the Navy’s FY2020 budget
submission is mistaken in presenting it as a ship requested for procurement in
FY2020. If Congress decides to treat CVN-81 as a ship that was procured in

45 See CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for
Congress
, by Ronald O'Rourke.
Congressional Research Service

28

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

FY2019, then the CR’s prohibition on increasing a program’s procurement
quantity might have no impact on the CVN-78 program in FY2020.
Nimitz (CVN-68) class aircraft carrier refueling complex overhaul
(RCOH) program. The CR’s prohibition on increasing a program’s
procurement quantity would appear to prohibit the Navy from using CR-
provided funding for starting the RCOH (i.e., mid-life nuclear-refueling
overhaul) of the aircraft carrier CVN-74 that the Navy is requesting for
FY2020, since no RCOH was authorized in FY2019.
Virginia-class attack submarine program. The CR’s prohibition on
increasing a program’s procurement quantity would appear to prohibit the
Navy from using CR-provided funding for procuring the third of the three
Virginia-class submarines requested for FY2020, since two Virginia-class
submarines were procured in FY2019.
TATS towing, salvage, and rescue ship program. The CR’s prohibition on
increasing a program’s procurement quantity would appear to prohibit the
Navy from using CR-provided funding for procuring the second of the two
TATS ships requested for FY2020, since one TATS ship was procured in
FY2019.
LCU 1700 landing craft program. The CR’s prohibition on increasing a
program’s procurement quantity would appear to prohibit the Navy from
using CR-provided funding for procuring the third and fourth of the four
LCU 1700 landing craft requested for FY2020, since two LCU 1700 craft
were procured in FY2019.
Impacts related to line-item funding misalignments. FY2020 Navy
shipbuilding programs not already listed above that may be affected by the CR
because the amount of funding provided for the program in FY2019 is
substantially less in percentage terms than the amount requested for the program
in FY2020 include the following:
Gerald R. Ford (CVN-78) class aircraft carrier program. As mentioned
above, if Congress decides to treat CVN-81 as a ship that was procured in
FY2019, then the CR’s prohibition on increasing a program’s procurement
quantity might have no impact on the CVN-78 program in FY2020. In that
case, however, the program could nevertheless be affected by the CR because
the amount of procurement funding provided for the program in FY2019
($1,573.2 million) is equivalent to about 67% of the amount requested for
FY2020 ($2,347.0 million).
Outfitting of ships procured in prior years. The CR could affect the
Navy’s FY2020 program for outfitting ships procured in prior years because
the amount of funding provided for this line item in FY2019 ($550.0 million)
is equivalent to about 73% of the amount requested for FY2020 ($754.7
million).
October 30, 2019, Department of Navy Fact Sheet on CR Impacts
Consistent with the above discussion, an October 30, 2019, Department of the Navy (DON) two-
page fact sheet on CR impacts on FY2020 DON programs stated, regarding shipbuilding
programs, that
 a six-month CR would delay the execution of
Congressional Research Service

29

link to page 96 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

 the mid-life refueling overhaul (called a refueling complex overhaul, or
RCOH) of the aircraft carrier CVN-74,
 one Virginia-class attack submarine,
 one TATS towing, rescue, and salvage ship, and
 two LCU 1700 landing craft; and that
 a 12-month CR without anomalies (i.e., special legislative provisions for
protecting individual programs from CR impacts) would prevent the awarding of
contracts for
 the CVN-74 RCOH,
 one Virginia-class attack submarine,
 the first FFG(X) frigate,
 one TATS towing, rescue, and salvage ship, and
 two LCU-1700 landing craft, and
 would additionally prevent the continuation of construction work on five
prior-year-funded ships whose completion is to be funded with FY2020 cost-
to-complete (CTC) funding.46
The two-page DON fact sheet is reprinted in Appendix J.
Press Reports
An October 8, 2019, press report stated:
[Assistant Secretary of the Navy (Research, Development and Acquisition) James] Geurts
said [on October 8 that] there was no one particular program that was most threatened by
starting FY 2020 with a CR, but he said the cumulative effect is that the CR halts Navy
progress in doing its business more efficiently.
“A CR always causes inefficiencies for us, whether it’s delaying new starts until we get
new start authority like with the [helicopter trainer replacement] program, or in ship
maintenance having to split up different awards,” he said.
“It’s an opportunity lost, which we showed last year we could really exploit to great value.
But we’ll figure out how to deal with the CR.”
He noted that the Navy had taken many steps over the years to mitigate the effects of
starting the year without a proper spending plan, such as not planning to award major
contracts in the first quarter of the fiscal year. But not having a spending plan and defense
policy bill passed into law at the start of the fiscal year can have consequences later in the
year, too.
The frigate program is supposed to downselect to a single contractor who will design and
build the ships by the end of FY 2020. But, Geurts said, the program office might not be
able to do some leg work today as planned because “there’s terms and conditions and
there’s provisos right now that need to be conferenced. Depending on the outcome, some
of those positions between the House and the Senate can have large impacts on the
program, and not knowing what the conference result will be creates uncertainty, and
uncertainty creates inefficiency. So for instance, there are provisions regarding sources for
frigate which need to be conferenced; until we know the output of the final conference

46 Department of the Navy, Office of Budget, FY 2020 DON CR Impacts, Fact Sheet, October 30, 2019, p. 1
Congressional Research Service

30

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

position, we won’t know the impact on the program. So what I would always say is,
uncertainty generates inefficiency and perceived risk; perceived risk costs us.”47
An October 30, 2019, press report stated:
The Secretary of the Navy has directed plans to prepare for a potential one-year continuing
resolution (CR), should delayed defense appropriations not get resolved by the end of the
year.
“We have done planning for a short—the stated CR—and then I have made sure that we
are now looking at a one-year CR, it looks like,” Secretary Richard Spencer told reporters
today at a Heritage Foundation press roundtable….
Spencer said all of the Navy’s plans are “dismal, it comes to prioritization…we have the
tools of anomalies, but anomalies will probably be difficult also.”…
He said the Pentagon is “pretty good at being MacGuyvers and figuring out how to deal
with the situation.” Ten CRs later the military still operates its missions, “albeit in various
different stages of readiness but we get out the door.”
“So in some cases we’re our own worst enemy because Congress turns around and goes
fine, you know what, one year, they’ll get through it, they’ll figure it out. Yeah we will,
but what will we look like on the other side?”
Spencer said one of his biggest concerns with CRs and budget issues is how it affects the
industrial supply chain.
“Look what happened at some of these CRs early on. You had people leaving the
shipbuilding industry and going into some other form of construction and/or manufacturing
because they said ‘Look the auto industry is at least saying I’ll be building cars for the next
5 years. The Navy keeps saying oop, on off on off, I can’t live through his uncertainty,’ so
you lost talent and you lose your supply chain strength.”
“That’s the biggest concern, is the secondary and tertiary effects that happen from this,”
Spencer added.48
A November 15, 2019, press report stated:
The Navy is already making hard decisions—curtailing training for air wings not
imminently deploying, canceling planned ship maintenance availabilities—as the specter
of a full-year continuing resolution looms….
… Fiscal Year 2019 was in many ways a high water mark for Navy spending on readiness
enablers like maintenance, spare parts and training hours—and yet the Navy is looking at
having to cancel as many as 14 ship maintenance availabilities and shutting down carrier
air wings and expeditionary squadrons not heading into a deployment despite the relatively
healthy budget the service would have under a full-year CR. Leadership says this is the
only choice the Navy has amid so much fiscal uncertainty.
For example, in the ship maintenance account, the Navy requested $10.426 billion for ship
depot maintenance in FY 2020 compared to $9.758 billion received in FY 2019, for a
difference of $668 million or about a 6.4-percent reduction in funding the Navy would get
for ship maintenance under a full-year CR. So why does this put 14 ships at risk for having
their planned maintenance canceled?

47 Megan Eckstein, “Navy’s FY 2019 Contracting Showed Efficiency Improvements, CR May Hamper Progress,”
USNI News, October 8, 2019. See also Justion Katz, “Geurts Says Navy’s Major Programs Will Not Suffer Severe
Impacts from CR,” Inside Defense, October 8, 2019.
48 Rich Abott, “Navy Preparing For Year-Long CR,” Defense Daily, October 30, 2019.
Congressional Research Service

31

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Two top Navy civilian leaders say the contracts for these availabilities are the only
“variable” costs within this line item, and therefore they are the only levers the Navy can
control amid so much uncertainty about whether the service will get its full requested sum
of money for the year or will see about a 10-percent decrease in spending levels under a
full-year CR.
Similarly, on flight hours, the Navy has requested $5.682 billion in FY 2020 compared to
the $5.712 billion given in FY 2019, meaning the service would actually have more money
for flight hours than it needs; but it requested $2.284 billion for the related fleet air training
account, compared to the $1.988 billion given in FY 2019, creating a 13-percent deficit in
this enabler account….
Thomas Harker, the assistant secretary of the Navy for financial management and
comptroller, told reporters today that, “at the line item level, we may have small
incremental changes, things like [operations and maintenance], something like flight hours
or ship depot maintenance: you may say, oh, well you’re not going to really be hurt that
much because that’s not scheduled to increase that much (from FY 2019 to FY 2020). The
problem is, you have to address these entire amounts across the fiscal year and look at how
they affect a lot of our costs, and in many cases our costs are fixed. So we have things—
civilian payroll, shipyard workers, they still need to get paid—so it’s the other things we
can’t do. So the impact is greater because it’s the variable costs that have to pay for all the
impact.”
James Geurts, the assistant secretary of the Navy for research, development and
acquisition, added that, in the ship maintenance example, the service will pay for the
infrastructure and personnel costs at the Navy’s four public shipyards first, for example,
leaving less money available for the one variable cost: contracts awarded to private yards
for maintenance and upgrades on destroyers, cruisers and amphibious ships.
Being unsure today whether Congress will enact a defense spending bill or if the Navy will
be stuck with the CR that effectively trims the Navy’s spending by 10 percent compared to
its requested levels, Geurts said, “when the fleet looks at all the things they’ve got to be
able to do with the first increment of money they have, we say, well I don’t really want to
move a ship availability to the right, but that’s my only option because I can’t get enough
money to pay for all of that availability, and I can’t just start a week’s worth of it. And so
they start making hard choices,” Geurts said.
This has already happened, even under this first short-term CR that expires next week.
Maintenance contracts for Arleigh Burke-class guided-missile destroyers USS Bainbridge
(DDG-96) and USS Gonzalez (DDG-66) were set to be awarded last week to private yards
on the East Coast, but the Navy is choosing not to. This is partly because, after paying fixed
costs, it doesn’t have the full sum of money to pay for the repair work. It is also partly a
hedge against emergencies later in the year, if the CR stretches the full year; it is a desire
to repair these ships now, but there could be a more pressing need for maintenance dollars
later in the year if a ship set for deployment had an unexpected issue arise, and the Navy
doesn’t want to be caught without the funds to respond.
“What’s frustrating me: one of the things you’ve heard when we talk ship maintenance is,
hey, we want to get our planning set, we want to award the contract early; [Bainbridge]
was one of them we had all set, we backed the planning up, had 120 days ready in advance,
the team was ready to go, we had the materials all ready to go, and then suddenly, oh, we
can’t do it now because we’re in a CR. The real challenge: we don’t know how long the
next CR is, when [the contract] is going to get awarded.”
Geurts conceded that cutting 14 ship availabilities over a 6-percent funding cut to that line
item may sound “more drastic” than is necessary, but he made clear “it’s because you’ve
got to cover a lot of the fixed cost, and then the only thing to move around is some of these
variable ones.”
Congressional Research Service

32

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The Navy has made a concerted effort to get maintenance on ships and aircraft done in a
more timely manner, as massive backlogs at both public and private shipyards and at Navy
aircraft depots has hurt fleet readiness in recent years. Better planning and new processes
have been put in place already, USNI News has reported, but interruptions in cash flow
and the ability to get contracts awarded on schedule will undo much of what the Navy has
accomplished, officials fear.
Geurts said that, under a full-year CR, some of the 14 availabilities would be deferred and
some would be canceled altogether if a ship was still operable without the maintenance
period. That deferral of work—as the Navy has learned the hard way many times
throughout its history—will ultimately cost more in the end to fix than it would if the
scheduled maintenance was performed as planned.
If the Navy starts deferring this work this year, Geurts said, “then we get back into the
condition we were in during sequestration where we were deferring maintenance. We’ve
been working hard over the last two or three years to get all of our ships back onto their
class maintenance plan, as opposed to deferring maintenance,” he said. Continuing to
operate the ships after skipping the availabilities means “you have this installed liability
that, eventually that bill comes to roost. And that’s been what we’ve been for the last two
or three years trying to dig our way out of, and now we’ve picked up the shovels again and
we’re digging.”
Harker said that, across the entire Navy budget, a “climate of scarcity” is already setting
in, and offices are reluctant to spend money they typically would because they are unsure
what the rest of the year will look like for them. Under a normal budget, the fiscal year is
about 12 percent through already and so 12 percent of funds for flight hours and steaming
hours, for example, would have already been used.
“Right now we’re significantly less than that because people are holding on, thinking, okay,
I need to be more guarded with my resources,” Harker said.
“So you don’t see them making the investments. And then the impact on the training is,
you look at the flight hours: okay, fleet commanders have to manage across their whole
portfolios. So if they back away from executing things that are good to do but not critically
necessary for the training for workups for someone who’s about to deploy, that gives them
more flexibility to deal with potential casualties or engine problems” or other contingencies
that may arise later in the year.
On the acquisition side, Geurts said the Navy did not plan any major contract awards for
the first quarter of the year, as a hedge against short-term CRs. But if the CR stretches
much longer, the service will have to ask for “anomalies,” or the authority to make an
exception and start a new program or increase a procurement quantity despite the rules of
a CR. Harker’s and Geurts’ offices are working on a list of anomalies they’d want to request
if the CR stretches into the longer term.
For top-priority programs like the Columbia-class ballistic missile submarine, the Navy
would certainly ask for an anomaly that is almost certain to be approved by the Secretary
of Defense and then by Congress, since it is well recognized as among the most important
acquisition programs in the Defense Department and is on a tight schedule as is.
But, Harker said, “a lot of the anomalies we would be asking for and the movements we
would be asking for, they’re going to say, live with it. That’s the risk, and that’s what we’re
fearful of. So how do we manage that? That’s why you see a lot of the different people that
have funds out in the Navy and the Marine Corps executing carefully, because they worry,
if I’m going to be stuck with this 10-percent cut, how am I going to absorb that?”
Geurts added that, “if we’re in a full-year CR with no anomaly approval and we’re 10
percent down on budget, we will fund Columbia; funding their 100-percent [need] will
mean that 10 percent of [Columbia’s] budget will come out of somewhere else.”
Congressional Research Service

33

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Under that worst-case scenario, Columbia funding would be preserved in full, as likely
would be funding for the two-ship buy made last year for the Ford-class aircraft carrier and
multiyear procurement contracts for must-haves like the Virginia-class submarine and
Arleigh Burke-class destroyer. But the more programs the Navy protects, the greater the
impact other programs would face, seeing well above a 10-percent cut in their funding or
even being canceled altogether.
Geurts said he and Harker are looking closely at the entire portfolio to make the best
decisions under the circumstance, to keep the Navy best on track to grow in size and
readiness and to modernize.
“My fear of that is, we’re doing that, we’re not managing contracts. And so are companies,”
Geurts said of all the time spent looking at how to mitigate the pain of a CR.
“So this uncertainty just takes attention away from executing the work as effectively and
efficiently as we can.”49
Legislative Activity for FY2020
CRS Reports Tracking Legislation on Specific Navy Shipbuilding
Programs
Detailed coverage of legislative activity on certain Navy shipbuilding programs (including
funding levels, legislative provisions, and report language) can be found in the following CRS
reports:
 CRS Report R41129, Navy Columbia (SSBN-826) Class Ballistic Missile
Submarine Program: Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report RL32418, Navy Virginia (SSN-774) Class Attack Submarine
Procurement: Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program:
Background and Issues for Congress, by Ronald O'Rourke. (This report also
covers the issue of the Administration’s FY2020 budget proposal, which the
Administration withdrew on April 30, to not fund a mid-life refueling overhaul
[called a refueling complex overhaul, or RCOH] for the aircraft carrier Harry S.
Truman
[CVN-75], and to retire CVN-75 around FY2024.)
 CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs:
Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report R44972, Navy Frigate (FFG[X]) Program: Background and Issues
for Congress, by Ronald O'Rourke.
 CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background
and Issues for Congress, by Ronald O'Rourke.
 CRS Report R43543, Navy LPD-17 Flight II and LHA Amphibious Ship
Programs: Background and Issues for Congress, by Ronald O'Rourke.

49 Megan Eckstein, “Continuing Resolution Forcing Navy to Delay Ship Maintenance, Curtail Training,” USNI News,
November 15, 2019. See also Matthew Beinart, “Officials: Navy Could Face $20.6 Billion Impact Under A Potential
Year-Long CR,” Defense Daily, November 15, 2019; Wesley Morgan, “Navy Delays Ship Maintenance But New Ships
Not Yet Affected by CR,” Politico Pro Defense, November 15, 2019.
Congressional Research Service

34

link to page 41 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

 CRS Report R43546, Navy John Lewis (TAO-205) Class Oiler Shipbuilding
Program: Background and Issues for Congress, by Ronald O'Rourke.
 CRS Report R45757, Navy Large Unmanned Surface and Undersea Vehicles:
Background and Issues for Congress, by Ronald O'Rourke.
Legislative activity on individual Navy shipbuilding programs that are not covered in detail in the
above reports is covered below.
Summary of Congressional Action on FY2020 Funding Request
The Navy’s proposed FY2020 budget requests funding for the procurement of 12 new ships:
 1 Gerald R. Ford (CVN-78) class aircraft carrier;
 3 Virginia-class attack submarines;
 3 DDG-51 class Aegis destroyers;
 1 FFG(X) frigate;
 2 John Lewis (TAO-205) class oilers; and
 2 TATS towing, salvage, and rescue ships.
As noted earlier, the above list of 12 ships reflects a Navy decision to show the aircraft carrier
CVN-81 as a ship to be procured in FY2020 rather than a ship that was procured in FY2019.
Congress, as part of its action on the Navy’s proposed FY2019 budget, authorized the
procurement of CVN-81 in FY2019.
The Navy’s proposed FY2020 shipbuilding budget also requests funding for ships that have been
procured in prior fiscal years, and ships that are to be procured in future fiscal years, as well as
funding for activities other than the building of new Navy ships.
Table 6 summarizes congressional action on the Navy’s FY2020 funding request for Navy
shipbuilding. The table shows the amounts requested and congressional changes to those
requested amounts. A blank cell in a filled-in column showing congressional changes to requested
amounts indicates no change from the requested amount.











Congressional Research Service

35

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Table 6. Summary of Congressional Action on FY2020 Funding Request
Millions of dollars, rounded to nearest tenth; totals may not add due to rounding
Congressional changes to requested amounts
Line
numb
Authorization
Appropriation
er
Program
Request
HASC
SASC
Conf.
HAC
SAC
Conf.
Shipbuilding and Conversion, Navy (SCN) appropriation account
001
Columbia-class SSBN AP
1,698.9
125.0
125.0
123.0
-86.9
123.0

002
CVN-78 aircraft carrier
2,347.0
-395.0

-1,305.0
-281.0
-1,285.0

002X
CVN-78 aircraft carrier (CVN-81)
0


1,285.0

1,174.8

003
Virginia-class SSN
7,155.9
-550.0
-2,464.0
-1,710.0
-2,963.6
-1,800.0

004
Virginia-class SSN AP
2,769.6

1,500.0
200.0
1,497.0
200.0

005
CVN refueling overhaul
647.9
-211.0
-50.0
-16.0
20.0
-33.3

006
CVN refueling overhaul AP
0
17.0
16.9
16.9
16.9
16.9

007
DDG-1000
155.9


-66.0



008
DDG-51
5,099.3
-86.0
-20.0

-84.0


009
DDG-51 AP
224.0

260.0
260.0

555.0

010
LCS
0






011
FFG(X)
1,281.2
-15.0





012
LPD-17 Flight II
0
100.0
525.0
525.0

747.1

013
LPD-17 Flight II AP
247.1
-100.0
-247.1
-247.1
-247.1
-247.1

014
ESB
0






015
LHA
0

650.0
650.0

650.0

016
LHA AP
0






017
EPF
0
49.0



261.0

018
TAO-205
981.2
-374.0





019
TAO-205 AP
73.0
-73.0





020
TATS
150.3




-62.1

021
Oceanographic ships
0






022
LCU 1700 landing craft
85.7



-2.0


023
Outfitting
754.7
-111.1
-50.0
-49.0
-18.4
-40.3

024
Ship-to-shore connector (SSC)
0
84.8

65.0
65


024A
Ship-to-shore connector (SSC) (AP)
0

40.4




025
Service craft
56.3

25.5
25.5

25.5

026
LCAC landing craft
0






027
USCG icebreakers AP
0






028
Completion of prior-year ships
55.7
-30.0
49.0
49.0

49.0

XX
Unmanned surface vessels
0




248.2

TOT

23,783.7
-1,569.3
360.7
-193.7
-2,084.2
582.7

AL
Source: Table prepared by CRS based on Navy FY2020 budget submission, committee reports, and explanatory
statements on the FY2020 National Defense Authorization Act and FY2020 DOD Appropriations Act.
Notes: Mil ions of dol ars, rounded to nearest tenth. A blank cell indicates no change to requested amount.
Totals may not add due to rounding. AP is advance procurement funding; HASC is House Armed Services
Committee; SASC is Senate Armed Services Committee; HAC is House Appropriations Committee; SAC is
Senate Appropriations Committee; Conf. is conference report.
Congressional Research Service

36

link to page 41 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

FY2020 National Defense Authorization Act (H.R. 2500/S. 1790)
House
The House Armed Services Committee, in its report (H.Rept. 116-120 of June 19, 2019) on H.R.
2500, recommended the funding levels shown in the HASC column of Table 6.
Section 118 of H.R. 2500 as reported by the committee states
SEC. 118. NATIONAL DEFENSE RESERVE FLEET VESSEL.
(a) In General.--Subject to the availability of appropriations, the Secretary of the Navy,
acting through the executive agent described in subsection (e), shall seek to enter into a
contract for the construction of one sealift vessel for the National Defense Reserve Fleet.
(b) Delivery Date.--The contract entered into under subsection (a) shall specify a delivery
date for the sealift vessel of not later than September 30, 2026.
(c) Design and Construction Requirements.--
(1) Use of existing design.--The design of the sealift vessel shall be based on a domestic or
foreign design that exists as of the date of the enactment of this Act.
(2) Commercial standards and practices.--Subject to paragraph (1), the sealift vessel shall
be constructed using commercial design standards and commercial construction practices
that are consistent with the best interests of the Federal Government.
(3) Domestic shipyard.--The sealift vessel shall be constructed in a shipyard that is located
in the United States.
(d) Certificate and Endorsement.--The sealift vessel shall meet the requirements necessary
to receive a certificate of documentation and a coastwise endorsement under chapter 121
of tile 46, United States Code, and the Secretary of the Navy shall ensure that the completed
vessel receives such a certificate and endorsement.
(e) Executive Agent.--
(1) In general.--The Secretary of the Navy shall seek to enter into a contract or other
agreement with a private-sector entity under which the entity shall act as executive agent
for the Secretary for purposes of the contract under subsection (a).
(2) Responsibilities.--The executive agent described in paragraph (1) shall be responsible
for--
(A) selecting a shipyard for the construction of the sealift vessel;
(B) managing and overseeing the construction of the sealift vessel; and
(C) such other matters as the Secretary of the Navy determines to be appropriate
(f) Use of Incremental Funding.--With respect to the contract entered into under subsection
(a), the Secretary of the Navy may use incremental funding to make payments under the
contract.
(g) Sealift Vessel Defined.--In this section, the term ``sealift vessel'' means the sealift
vessel constructed for the National Defense Reserve Fleet pursuant to the contract entered
into under subsection (a).
Section 806 of H.R. 2500 as reported by the committee states
SEC. 806. REQUIREMENT THAT CERTAIN SHIP COMPONENTS BE
MANUFACTURED IN THE NATIONAL TECHNOLOGY AND INDUSTRIAL BASE.
Congressional Research Service

37

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

(a) Additional Procurement Limitation.--Section 2534(a) of title 10, United States Code, is
amended by adding at the end the following new paragraph:
``(6) Components for auxiliary ships.--Subject to subsection (k), the following
components:
``(A) Auxiliary equipment, including pumps, for all shipboard services.
``(B) Propulsion system components, including engines, reduction gears, and propellers.
``(C) Shipboard cranes.
``(D) Spreaders for shipboard cranes.''.
(b) Implementation.--Such section is further amended by adding at the end the following
new subsection:
``(k) Implementation of Auxiliary Ship Component Limitation.--Subsection (a)(6) applies
only with respect to contracts awarded by the Secretary of a military department for new
construction of an auxiliary ship after the date of the enactment of the National Defense
Authorization Act for Fiscal Year 2020 using funds available for National Defense Sealift
Fund programs or Shipbuilding and Conversion, Navy. For purposes of this subsection, the
term `auxiliary ship' does not include an icebreaker.''.
Section 1022 of H.R. 2500 as reported by the committee states
SEC. 1022. USE OF NATIONAL DEFENSE SEALIFT FUND FOR PROCUREMENT
OF TWO USED VESSELS.
Pursuant to section 2218(f)(3) of title 10, United States Code, and using amounts
authorized to be appropriated for Operation and Maintenance, Navy, for fiscal year 2020,
the Secretary of the Navy shall seek to enter into a contract for the procurement of two
used vessels.
Section 1024 of H.R. 2500 as reported by the committee states
SEC. 1024. REPORT ON SHIPBUILDER TRAINING AND THE DEFENSE
INDUSTRIAL BASE.
Not later than 180 days after the date of the enactment of this Act, the Secretary of Defense
shall submit to the Committees on Armed Services of the Senate and House of
Representatives a report on shipbuilder training and hiring requirements necessary to
achieve the Navy's 30-year shipbuilding plan and to maintain the shipbuilding readiness of
the defense industrial base. Such report shall include each of the following:
(1) An analysis and estimate of the time and investment required for new shipbuilders to
gain proficiency in particular shipbuilding occupational specialties, including detailed
information about the occupational specialty requirements necessary for construction of
naval surface ship and submarine classes to be included in the Navy's 30-year shipbuilding
plan.
(2) An analysis of the age demographics and occupational experience level (measured in
years of experience) of the shipbuilding defense industrial workforce.
(3) An analysis of the potential time and investment challenges associated with developing
and retaining shipbuilding skills in organizations that lack intermediate levels of
shipbuilding experience.
(4) Recommendations concerning how to address shipbuilder training during periods of
demographic transition, including whether emerging technologies, such as augmented
reality, may aid in new shipbuilder training.
Congressional Research Service

38

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

(5) Recommendations concerning how to encourage young adults to enter the defense
shipbuilding industry and to develop the skills necessary to support the shipbuilding
defense industrial base.
Section 3118 of H.R. 2500 as reported by the committee states
SEC. 3118. PROGRAM FOR RESEARCH AND DEVELOPMENT OF ADVANCED
NAVAL NUCLEAR FUEL SYSTEM BASED ON LOW-ENRICHED URANIUM.
(a) Establishment.--Not later than 60 days after the date of the enactment of this Act, the
Administrator for Nuclear Security shall establish a program to assess the viability of using
low-enriched uranium in naval nuclear propulsion reactors, including such reactors located
on aircraft carriers and submarines, that meet the requirements of the Navy.
(b) Activities.--In carrying out the program under subsection (a), the Administrator shall
carry out activities to develop an advanced naval nuclear fuel system based on low-
enriched uranium, including activities relating to--
(1) down-blending of high-enriched uranium into low-enriched uranium;
(2) manufacturing of candidate advanced low-enriched uranium fuels;
(3) irradiation tests and post-irradiation examination of these fuels; and
(4) modification or procurement of equipment and infrastructure relating to such activities.
(c) Report.--Not later than 120 days after the date of the enactment of this Act, the
Administrator shall submit to the congressional defense committees a plan outlining the
activities the Administrator will carry out under the program established under subsection
(a), including the funding requirements associated with developing a low-enriched uranium
fuel.
Regarding Section 3118, a July 9, 2019, Statement of Administration Policy regarding H.R. 2500
stated the following:
Low-Enriched Uranium Naval Nuclear Fuel R&D Program (Section 3118). The
Administration objects to the bill’s direction to establish a program for development of
high-density, low-enriched fuels that could replace highly enriched uranium for naval
applications. In 2018, the Secretaries of Energy and the Navy jointly determined that the
United States should not pursue research and development of an advanced naval nuclear
fuel system based on low-enriched uranium since such a system would result in a reactor
design that is inherently less capable, more expensive, and unlikely to support the
significant cost savings associated with life-of-ship submarine reactors. To fully execute a
development effort of this magnitude would also incur significant risk and compete for
resources against other defense priorities.50
H.Rept. 116-120 states
Low-Enriched Uranium Fuel for Naval Reactors
The committee notes that since September 11, 2001, the U.S. Government has sought to
remove weapons-usable highly enriched uranium (HEU) containing 20 percent or more
uranium-235 from as many locations as possible because of concerns related to nuclear
terrorism. The committee notes that the primary focus of this strategy has been on replacing
HEU civilian research reactor fuel and targets used in the production of medical
radioisotopes, with non-weapons-usable low-enriched uranium (LEU) fuel and targets.
This program to reduce the use of HEU for civilian purposes has been successful in
reducing the amount of HEU worldwide that could have been at risk of theft of diversion.

50 Executive Office of the President, Statement of Administration Policy, H.R. 2500—National Defense Authorization
Act for Fiscal Year 2020
, July 9, 2019, pp. 8-9.
Congressional Research Service

39

link to page 41 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

However, this effort did not address the use of HEU for military purposes. Naval reactors
account for the largest share of global HEU use other than nuclear weapons, and in the
United States, the fuel is fabricated in civilian, not military, facilities. The committee has
been supportive of efforts to assess the feasibility of using low-enriched uranium for naval
reactors as such use would not only benefit nuclear non-proliferation efforts but also
maintain the research and development skills necessary to sustain innovation and expertise
with regard to naval fuel as research and development efforts on the Columbia-class reactor
end. The committee continues to support efforts to assess the feasibility of using LEU in
naval reactors to meet military requirements for aircraft carriers and submarines.
The National Defense Authorization Act for Fiscal Year 2018 (Public Law 115–91)
required a nuclear submarine study. However, this study lacked sufficient detail to respond
to the congressional mandate. Therefore, the committee directs the Administrator for
Nuclear Security, in coordination with the Secretary of the Navy, to provide a report to the
congressional defense committees not later than December 15, 2019, assessing the
feasibility of a design of the reactor module of the Virginia-Class replacement nuclear
powered attack submarine that retains the existing hull diameter but leaves sufficient space
for an LEU-fueled reactor with a life of the ship core, possibly with an increased module
length. If a life of the ship core is unattainable, the report should include the feasibility of
a reactor design with the maximum attainable core life and a configuration that enables
rapid refueling. (Page 343)
H.Rept. 116-120 also states
Future Fleet Architecture
The committee notes that the National Defense Strategy indicates that the United States is
in a great powers competition to include the Russian Federation and the People’s Republic
of China. The committee also believes that this great powers competition will heavily rely
on our naval force structure to optimally address Russia and China in both the Pacific and
the Arctic, as well as impending tensions with the Iranian regime in the Persian Gulf. The
committee believes that it is imperative to include a larger long-term force structure to
address these global challenges. The committee also believes that to ensure a continued
projection of naval power around the world, the Navy should include in their forthcoming
2019 Force Structure Assessment necessary vessels to address sufficient operations in the
Arctic. Therefore, the committee directs the Secretary of the Navy to brief the House
Committee on Armed Services by December 31, 2019 regarding the force structure plan to
compete with adversaries in the Pacific and Arctic Oceans and the Persian Gulf. This
briefing should also address the defense industrial base and any associated maritime sector
weaknesses that need to be addressed to support the expanded force structure. (Pages 18-
19)
H.Rept. 116-120 also states
Sourcing of Domestic Components for U.S. Navy Ships
The committee is concerned with the sourcing of non-domestic components on U.S. Navy
ships. The committee directs the Secretary of the Navy to provide a report to the
congressional defense committees by December 1, 2019, on the feasibility of sourcing
domestic components such as: auxiliary equipment, including pumps; propulsion system
components, including engines, reduction gears, and propellers; shipboard cranes and
spreaders for shipboard cranes; and other components on all Navy ships. (Page 186)
Senate
The Senate Armed Services Committee, in its report (S.Rept. 116-48 of June 11, 2019) on S.
1790, recommended the funding levels shown in the SASC column of Table 6. S.Rept. 116-48
states
Congressional Research Service

40

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Outfitting
The budget request included $754.7 million in line number 23 of Shipbuilding and
Conversion, Navy (SCN), for outfitting.
Based on planned delivery dates, the committee notes that post-delivery funding is early-
to-need for LCS-21 ($5.0 million). The committee also notes the unjustified outfitting cost
growth for SSN-793, SSN-794, SSN-795, and SSN-796 ($20.0 million). The committee
further notes unjustified post-delivery cost growth for DDG-1000 ($25.0 million).
Therefore, the committee recommends a decrease of $50.0 million in line number 23 of
SCN.
Service craft
The budget request included $56.3 million in line number 25 of Shipbuilding and
Conversion, Navy (SCN), for service craft.
In order to increase training opportunities for Surface Warfare Officer candidates from all
accession sources, the committee believes that the Navy should replace the six YP-676
class craft slated for disposal with upgraded YP-703 class craft that incorporate
modernization, training, and habitability improvements derived from lessons learned with
existing YP-703 craft.
The committee urges the Secretary of the Navy to release a request for proposals for the
detail design and construction of upgraded YP-703 class craft not later than fiscal year
2020. The committee notes that the Navy's current cost estimate for acquisition of the first
upgraded YP-703 class craft is $25.5 million.
Therefore, the committee recommends an increase of $25.5 million in line number 25 of
SCN.
Expeditionary Fast Transport (T-EPF 14) conversion
The budget request included $55. 7 million in line number 28 of Shipbuilding and
Conversion, Navy (SCN), for completion of prior year shipbuilding programs.
The committee notes that the Chief of Naval Operations' unfunded priority list states that
additional funding could provide for the conversion of an Expeditionary Fast Transport (T-
EPF 14) into an Expeditionary Medical Transport to better fulfill distributed maritime
medical requirements.
Therefore, the committee recommends an increase of $49.0 million in line number 28 of
SCN.
Ship to shore connector advance procurement
The budget request included no funding in line number 29 of Shipbuilding and Conversion,
Navy (SCN), for ship to shore connector advance procurement.
The committee understands that additional funding could provide needed stability for
certain suppliers in the ship to shore connector program.
Therefore, the committee recommends an increase of $40.4 million in line number 29 of
SCN. (Pages 24-25)
Section 821 of S. 1790 as reported by the committee states
SEC. 821. Naval vessel certification required before Milestone B approval.
Section 2366b(a) of title 10, United States Code, is amended—
(1) in paragraph (3)(O), by striking “; and” and inserting a semicolon;
(2) in paragraph (4), by striking the period at the end and inserting “; and”; and
Congressional Research Service

41

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

(3) by adding at the end the following new paragraph:
“(5) in the case of a naval vessel program, certifies compliance with the requirements of
section 8669b of this title.”
Section 861 of S. 1790 as reported by the committee states the following:
SEC. 861. Notification of Navy procurement production disruptions.
(a) In general.—Chapter 137 of title 10, United States Code, is amended by adding at the
end the following new section:
Ҥ 2339b. Notification of Navy procurement production disruptions
“(a) Requirement for contractor To provide notice of delays.—The Secretary of the Navy
shall require prime contractors of any Navy procurement program to report within 15
calendar days any stop work order or other manufacturing disruption of 15 calendar days
or more, by the prime contractor or any sub-contractor, to the respective program manager
and Navy technical authority.
“(b) Quarterly reports.—The Secretary of the Navy shall submit to the congressional
defense committees not later than 15 calendar days after the end of each quarter of a fiscal
year a report listing all notifications made pursuant to subsection (a) during the preceding
quarter.”
(b) Clerical amendment.—The table of sections at the beginning of chapter 137 of title 10,
United States Code, is amended by inserting after the item relating to section 2339a the
following new item:
“2339b. Notification of Navy procurement production disruptions.”
Regarding Section 861, S.Rept. 116-48 states
Notification of Navy procurement production disruptions (sec. 861)
The committee recommends a provision that would require the Secretary of the Navy to
require prime contractors of any Navy procurement program to report, within 15 calendar
days of any contractor or subcontractor stop work order or within 15 days of a contractor
or subcontractor manufacturing disruption that has lasted 15 calendar days, to the
respective program manager and Navy technical authority. The provision would also
require the Secretary of the Navy to provide a quarterly notification of such disruptions to
the congressional defense committees.
The committee is concerned by the delay in reporting of recent stop work orders and other
manufacturing disruptions to Navy program management officials. The committee notes
that multiple shipbuilding programs have been negatively impacted by unacceptable delays
in reporting such disruptions. The committee believes that more timely notifications of
such disruptions will decrease the time required to initiate and complete corrective actions
necessary to resume production. (Page 221)
Section 1016 of S. 1790 as reported by the committee states
SEC. 1016. Modification of authority to purchase vessels using funds in National
Defense Sealift Fund.

(a) In general.—Section 2218(f)(3)(E) of title 10, United States Code, is amended—
(1) in clause (i), by striking “ten new sealift vessels” and inserting “ten new vessels that
are sealift vessels, auxiliary vessels, or a combination of such vessels”; and
(2) in clause (ii), by striking “sealift”.
(b) Effective date.—The amendments made by subsection (a) shall take effect on October
1, 2019, and shall apply with respect to fiscal years beginning on or after that date.
Congressional Research Service

42

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Section 1017 of S. 1790 as reported by the committee states
SEC. 1017. Senior Technical Authority for each naval vessel class.
(a) Senior Technical Authority for each class required.—Chapter 863 of title 10, United
States Code, is amended by inserting after section 8669a the following new section:
Ҥ 8669b. Senior Technical Authority for each naval vessel class
“(a) Senior Technical Authority.—
“(1) DESIGNATION FOR EACH VESSEL CLASS REQUIRED.—The Secretary of the
Navy shall designate, in writing, a Senior Technical Authority for each class of naval
vessels as follows:
“(A) In the case of a class of vessels which has received Milestone A approval, an approval
to enter into technology maturation and risk reduction, or an approval to enter into a
subsequent Department of Defense or Department of the Navy acquisition phase as of the
date of the enactment of the National Defense Authorization Act for Fiscal Year 2020, not
later than 30 days after such date of enactment.
“(B) In the case of any class of vessels which has not received any approval described in
subparagraph (A) as of such date of enactment, at or before the first of such approvals.
“(2) PROHIBITION ON DELEGATION.—The Secretary may not delegate designations
under paragraph (1).
“(3) INDIVIDUALS ELIGIBLE FOR DESIGNATION.—Each individual designated as a
Senior Technical Authority under paragraph (1) shall be an employee of the Navy in the
Senior Executive Service in an organization of the Navy that—
“(A) possesses the technical expertise required to carry out the responsibilities specified in
subsection (b); and
“(B) operates independently of chains-of-command for acquisition program management.
“(4) TERM.—Each Senior Technical Authority shall be designated for a term, not fewer
than six years, specified by the Secretary at the time of designation.
“(5) REMOVAL.—An individual may be removed involuntarily from designation as a
Senior Technical Authority only by the Secretary. Not later than 15 days after the
involuntary removal of an individual from designation as a Senior Technical Authority, the
Secretary shall notify, in writing, the congressional defense committees of the removal,
including the reasons for the removal.
“(b) Responsibilities and authority.—Each Senior Technical Authority shall be responsible
for, and have the authority to, establish, monitor, and approve technical standards, tools,
and processes for the class of naval vessels for which designated under this section in
conformance with applicable Department of Defense and Department of the Navy policies,
requirements, architectures, and standards.
“(c) Limitation on obligation of funds on lead vessel in vessel class.—
“(1) IN GENERAL.—On or after October 1, 2020, funds authorized to be appropriated for
Shipbuilding and Conversion, Navy or Other Procurement, Navy may not be obligated for
the first time on the lead vessel in a class of naval vessels unless the Secretary of the Navy
certifies as described in paragraph (2).
“(2) CERTIFICATION ELEMENTS.—The certification on a class of naval vessels
described in this paragraph is a certification containing each of the following:
“(A) The name of the individual designated as the Senior Technical Authority for such
class of vessels, and the qualifications and professional biography of the individual so
designated.
Congressional Research Service

43

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

“(B) A description by the Senior Technical Authority of the systems engineering,
technology, and ship integration risks for such class of vessels.
“(C) The designation by the Senior Technical Authority of each critical hull, mechanical,
electrical, propulsion, and combat system of such class of vessels, including systems
relating to power generation, power distribution, and key operational mission areas.
“(D) The date on which the Senior Technical Authority approved the systems engineering,
engineering development, and land-based engineering and testing plans for such class of
vessels.
“(E) A description by the Senior Technical Authority of the key technical knowledge
objectives and demonstrated system performance of each plan approved as described in
subparagraph (D).
“(F) A determination by the Senior Technical Authority that such plans are sufficient to
achieve thorough technical knowledge of critical systems of such class of vessels before
the start of detail design and construction.
“(G) A determination by the Senior Technical Authority that actual execution of activities
in support of such plans as of the date of the certification have been and continue to be
effective and supportive of the acquisition schedule for such class of vessels.
“(H) A description by the Senior Technical Authority of other technology maturation and
risk reduction efforts not included in such plans for such class of vessels taken as of the
date of the certification.
“(I) A certification by the Senior Technical Authority that each critical system covered by
subparagraph (C) has been demonstrated through testing of a prototype or identical
component in its final form, fit, and function in a realistic environment.
“(J) A determination by the Secretary that the plans approved as described in subparagraph
(D) are fully funded and will be fully funded in the future-years defense program for the
fiscal year beginning in the year in which the certification is submitted.
“(K) A determination by the Secretary that the Senior Technical Authority will approve, in
writing, the ship specification for such class of vessels before the request for proposals for
detail design, construction, or both, as applicable, is released.
“(3) DEADLINE FOR SUBMITTAL OF CERTIFICATION.—The certification required
by this subsection with respect to a class of naval vessels shall be submitted, in writing, to
the congressional defense committees not fewer than 30 days before the Secretary obligates
for the first time funds authorized to be appropriated for Shipbuilding and Conversion,
Navy or Other Procurement, Navy for the lead vessel in such class of naval vessels.
“(d) Definitions.—In this section:
“(1) The term ‘class of naval vessels’—
“(A) means any group of similar undersea or surface craft procured with Shipbuilding and
Conversion, Navy or Other Procurement, Navy funds, including manned, unmanned, and
optionally-manned craft; and
“(B) includes—
“(i) a substantially new class of craft (including craft procured using ‘new start’
procurement); and
“(ii) a class of craft undergoing a significant incremental change in its existing class (such
as a next ‘flight’ of destroyers or next ‘block’ of attack submarines).
“(2) The term ‘future-years defense program’ has the meaning given that term in section
221 of this title.
Congressional Research Service

44

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

“(3) The term ‘Milestone A approval’ has the meaning given that term in section 2431a of
this title.”
(b) Clerical amendment.—The table of sections at the beginning of chapter 863 of such
title is amended by inserting after the item relating to section 8669a the following new
item:
“8669b. Senior Technical Authority for each naval vessel class.”
Regarding Section 1017, S.Rept. 116-48 states
Senior Technical Authority for each naval vessel class (sec. 1017)
The committee recommends a provision that would require the designation of a Senior
Technical Authority for each class of naval vessels.
The committee notes the Government Accountability Office (GAO) published a report on
June 6, 2018, titled "Navy Shipbuilding: Past Performance Provides Valuable Lessons for
Future Investments" (GA0-18-238SP), which assessed Navy shipbuilding performance
over the past 10 years and concluded that "[the Navy] has received $24 billion more in
funding than originally planned but has 50 fewer ships in its inventory today, as compared
to the goals it first established in [2007.] ... Ship costs exceed[ed] estimates by over $11
billion during this time frame."
This report found that lead ships in new classes of naval vessels regularly failed to meet
expectations. For the 8 most recently delivered lead combatant ships (CVN-78, DDG-1000,
LCS-1, LCS-2, LHA-6, LPD-17, SSN-774, and SSN-775), the report found that: a total of
$8 billion more than the initial budget was required to construct these ships; each lead ship
experienced cost growth of at least 10 percent, and 3 lead ships exceeded their initial
budgets by 80 percent or more; each lead ship was delivered to the fleet at least 6 months
late with 5 lead ships delayed by more than 2 years; and most lead ships had dozens of
uncorrected deficiencies when accepted by the Navy.
As this report highlights, a key step in successful shipbuilding programs is technology
development: the maturation of key technologies into actual system prototypes and
demonstration of them in a realistic environment prior to the detailed design of the lead
ship. This type of technology maturation was not performed effectively on the CVN-78,
DDG-1000, LCS-1, LCS-2, and LPD-17 programs.
The committee also notes that the Navy is planning the largest fleet expansion in over 30
years with several costly and complex acquisitions planned for the coming years, including
the Columbia-class ballistic missile submarines and new classes of guided missile frigates
and fast attack submarines. The Chief of Naval Operations has also called for the first Large
Surface Combatant, Large Unmanned Surface Vehicle, Future Small Auxiliary, and Future
Large Auxiliary (CHAMP) to each be on contract in 2023. Additionally, large and extra
large undersea vehicles are projected to transition from research and development to
procurement within the next decade.
While recognizing the importance of modernizing the fleet to face growing threats, the
committee finds the Comptroller General's findings to be compelling and believes that
additional actions are needed to improve shipbuilding cost, schedule, and performance
outcomes, particularly of lead ships.
If such outcomes are not improved, the committee is concerned that the trends of the past
10 years will continue and that the Navy battle force could lack the capability and capacity
necessary to prevail in great power competition as described in the National Defense
Strategy.
Accordingly, this provision would establish a Senior Technical Authority (STA) for each
class of naval vessels. Each STA would be responsible for establishing, monitoring, and
approving technical standards, tools, and processes for the class of naval vessels for which
Congressional Research Service

45

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

he or she is designated under this section in conformance with applicable Department of
Defense and Department of the Navy policies, requirements, architectures, and standards.
In addition, beginning on October 1, 2020, funds authorized to be appropriated for
Shipbuilding and Conversion, Navy, could not be obligated on the lead vessel in a new
class of naval vessels until the Secretary of the Navy has submitted a certification
containing information from the STA on such class of vessels.
The committee recognizes that implementation of this provision may require additional
government employees, including senior executives, in the Naval Systems Engineering
Directorate of the Naval Sea Systems Command (SEA 05) and would support such
increases as may be warranted. (Pages 239-240)
Section 3115 of S. 1790 as reported by the committee states
SEC. 3115. Prohibition on use of funds for advanced naval nuclear fuel system based
on low-enriched uranium.

None of the funds authorized to be appropriated for the National Nuclear Security
Administration for fiscal year 2020 or any fiscal year thereafter may be obligated or
expended to conduct research and development of an advanced naval nuclear fuel system
based on low-enriched uranium until the following certifications are submitted to the
congressional defense committees:
(1) A joint certification of the Secretary of Energy and the Secretary of Defense that the
determination made by the Secretary of Energy and the Secretary of the Navy pursuant to
section 3118(c)(1) of the National Defense Authorization Act for Fiscal Year 2016 (Public
Law 114–92; 129 Stat. 1196) and submitted to the congressional defense committees on
March 25, 2018, that the United States should not pursue such research and development,
no longer reflects the policy of the United States.
(2) A certification of the Secretary of the Navy that an advanced naval nuclear fuel system
based on low-enriched uranium would not reduce vessel capability, increase expense, or
reduce operational availability as a result of refueling requirements.
Regarding Section 3115, S.Rept. 116-48 states
Prohibition on use of funds for advanced naval nuclear fuel system based on low-
enriched uranium (sec. 3115)

The committee recommends a provision that would prohibit the obligation or expenditure
of any funds at the National Nuclear Security Administration to conduct research and
development of an advanced naval nuclear fuel system based on low-enriched uranium
unless the Secretary of Defense, the Secretary of Energy, and the Secretary of the Navy
submit certain certifications to the congressional defense committees.
The committee notes that section 3118(c) of the National Defense Authorization Act for
Fiscal Year 2016 (P.L. 114-92) required the Secretary of Energy and the Secretary of the
Navy to submit a determination as to whether the United States should continue to pursue
such research and development. Pursuant to this section, in a letter to the congressional
defense committees dated March 25, 2018, the Secretaries of Energy and the Navy stated
that such a research and development effort would cost about $1 billion over a 10-to-15
year period, "with success not assured." It would also result in a reactor design that would
be "less capable, more expensive, and unlikely to support current life-of-ship submarine
reactors," which would reduce operational availability due to mid-life refueling
requirements. As a result, the Secretaries of Energy and the Navy determined that the
United States should not pursue such research and development. (Page 384)
S.Rept. 116-48 also states
Forward-deployed naval forces in Europe
Congressional Research Service

46

link to page 41 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The committee supports the continued forward-basing of four United States Navy
destroyers in Rota, Spain. These ships are among the most dynamically-employed naval
forces-performing ballistic missile defense missions, carrying out strikes in Syria, boosting
U.S. presence across the European theater in support of allies and partners, and monitoring
increasing Russian naval activities. At the same time, these ships have maintained high
readiness, in part due to rigorous maintenance practices.
In a January 14, 2019, interview, the Commander, U.S. Sixth Fleet, stated that the forward
presence provided by the four destroyers at Rota "is the bedrock of our ability to reassure
allies and respond to any threats that come up." She added, "There is no sub stitute for
having that kind of forward presence in Europe." The Commander also observed that the
"solid" operational model for these ships has enabled them to maintain "exceptional"
readiness as well as their training and certifications. Furthermore, the four ships have been
able to "conduct all the intermediate maintenance and the extended maintenance
availabilities [needed] to stay ready and stay focused while on patrol."
The committee is concerned about increasing Russian naval activity in the European
theater, which is now at its highest level since the Cold War. The committee is also aware
of the significant advances in Russian naval capability, especially as it relates to its attack
submarines.
Due in part to these developments, the Commander, U.S. European Command, testified to
the committee on March 5, 2019, that he has recommended adding two destroyers at Rota,
Spain. The Commander stated that, in order "to remain dominant in the maritime domain
and particularly under sea," the United States "need[s] greater capability, particularly given
the modernization and the growth of the Russian fleets in Europe." Furthermore, the
President's nominee to be the next commander of U.S. European Command testified to the
committee on April 2, 2019, that he agreed with the current commander's recommendation.
Therefore, not later than October 1, 2019, the committee directs the Chief of Naval
Operations and the Commander, U.S. European Command, to provide a joint briefing to
the Committees on Armed Services of the Senate and House on the merit and feasibility of
basing two additional destroyers at Rota, Spain, including an assessment of whether such
an enhancement to U.S. force posture in Europe would enhance the ability of the United
States to deter aggression, flexibly and proactively shape the strategic environment,
improve readiness to respond to contingencies, and ensure long-term warfighting
readiness. (Pages 279-280)
Conference
The conference report (H.Rept. 116-333 of December 9, 2019) on S. 1790 recommends the
funding levels shown in the authorization conference column of Table 6.
Section 128 of H.Rept. 116-333 states:
SEC. 128. STRATEGIC SEALIFT FLEET VESSEL.
(a) IN GENERAL.—Subject to the availability of appropriations, the Secretary of the Navy
shall seek to enter into a contract for the construction of one sealift vessel.
(b) DELIVERY DATE.—The contract entered into under subsection (a) shall specify a
delivery date for the sealift vessel of not later than September 30, 2026.
(c) DESIGN AND CONSTRUCTION REQUIREMENTS.—
(1) USE OF EXISTING DESIGN.—The design of the sealift vessel shall be based on a
domestic or foreign design that exists as of the date of the enactment of this Act.
(2) COMMERCIAL STANDARDS AND PRAC
Congressional Research Service

47

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

TICES.—Subject to paragraph (1), the sealift vessel may be constructed using commercial
design standards and commercial construction practices that are consistent with the best
interests of the Federal Government.
(3) DOMESTIC SHIPYARD.—The sealift vessel shall be constructed in a shipyard that is
located in the United States.
(d) CERTIFICATE AND ENDORSEMENT.—The sealift vessel shall meet the
requirements necessary to receive a certificate of documentation and a coastwise
endorsement under chapter 121 of tile 46, United States Code, and the Secretary of the
Navy shall ensure that the completed vessel receives such a certificate and endorsement.
(e) EXECUTIVE AGENT.—
(1) IN GENERAL.—The Secretary of the Navy may seek to enter into a contract or other
agreement with a private-sector entity under which the entity may act as executive agent
for the Secretary for purposes of the contract under subsection (a).
(2) RESPONSIBILITIES.—The executive agent described in paragraph (1) may be
responsible for—
(A) selecting a shipyard for the construction of the sealift vessel;
(B) managing and overseeing the construction of the sealift vessel; and
(C) such other matters as the Secretary of the Navy determines to be appropriate
(f) USE OF INCREMENTAL FUNDING.—With respect to the contract entered into under
subsection (a), the Secretary of the Navy may use incremental funding to make payments
under the contract.
(g) SEALIFT VESSEL DEFINED.—In this section, the term ‘‘sealift vessel’’ means the
sealift vessel constructed pursuant to the contract entered into under subsection (a).
Section 357 of H.Rept. 116-333 states:
SEC. 357. PILOT PROGRAM TO TRAIN SKILLED TECHNICIANS IN CRITICAL
SHIPBUILDING SKILLS.
(a) ESTABLISHMENT.—The Secretary of the Navy may carry out a pilot program to train
individuals to become skilled technicians in critical shipbuilding skills such as welding,
metrology, quality assurance, machining, and additive manufacturing.
(b) PARTNERSHIPS.—In carrying out the pilot program under this section, the Secretary
may partner with existing Federal or State projects relating to investment and infrastructure
in training and education or workforce development, such as the National Network for
Manufacturing Innovation, the Industrial Base Analysis and Sustainment program of the
Department of Defense, and the National Maritime Educational Council.
(c) TERMINATION.—The authority to carry out a pilot program under this section shall
terminate on September 30, 2025.
(d) BRIEFINGS.—If the Secretary carries out a pilot program under this section, the
Secretary shall provide briefings to the Committees on Armed Services of the Senate and
the House of Representatives as follows:
(1) Not later than 30 days before beginning to implement the pilot program, the Secretary
shall provide a briefing on the plan, cost estimate, and schedule for the pilot program.
(2) Not less frequently than annually during the period when the pilot program is carried
out, the Secretary shall provide briefings on the progress of the Secretary in carrying out
the pilot program.
Section 363 of H.Rept. 116-333 states:
Congressional Research Service

48

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

SEC. 363. REPORT ON NAVY SHIP DEPOT MAINTENANCE BUDGET.
(a) IN GENERAL.—Not later than March 1 of each of 2020, 2021, and 2022, the Secretary
of the Navy shall submit to the Committees on Armed Services of the Senate and House
of Representatives a report on the Operation and Maintenance, Ship Depot Maintenance
budget sub-activity group.
(b) ELEMENTS.—The report required under subsection (a) shall include each of the
following elements:
(1) A breakdown of funding, categorized by class of ship, requested for ship and submarine
maintenance.
2) A description of how the requested funding, categorized by class of ship, compares to
the identified ship maintenance requirement.
3) The amount of funds appropriated for each class of ship for the preceding fiscal year.
(4) The amount of funds obligated and expended for each class of ship for each of the three
preceding fiscal years.
(5) The cost, categorized by class of ship, of unplanned growth work for each of the three
preceding fiscal years.
Section 820 of H.Rept. 116-333 states:
SEC.
820.
NOTIFICATION
OF
NAVY
PROCUREMENT
PRODUCTION
DISRUPTIONS.
(a) IN GENERAL.—Chapter 137 of title 10, United States Code, is amended by adding at
the end the following new section:
‘‘§ 2339b. Notification of Navy procurement production disruptions
‘‘(a) REQUIREMENT FOR CONTRACTOR TO PROVIDE NOTICE OF DELAYS.—
The Secretary of the Navy shall require prime contractors of any Navy procurement
program funded under either the Shipbuilding and Conversion, Navy account or the Other
Procurement, Navy account to report within 15 calendar days any stop work order or other
manufacturing disruption of 15 calendar days or more, by the prime contractor or any
subcontractor, to the respective program manager and Navy technical authority.
‘‘(b) QUARTERLY REPORTS.—The Secretary of the Navy shall submit to the
congressional defense committees not later than 15 calendar days after the end of each
quarter of a fiscal year a report listing all notifications made pursuant to subsection (a)
during the preceding quarter.’’.
(b) CLERICAL AMENDMENT.—The table of sections at the beginning of chapter 137
of title 10, United States Code, is amended by inserting after the item relating to section
2339a the following new item:
‘‘2339b. Notification of Navy procurement production disruptions.’’.
Regarding Section 820, H.Rept. 116-333 states:
Notification of Navy procurement production disruptions (sec. 820)
The Senate bill contained a provision (sec. 861) that would require the Secretary of the
Navy to require prime contractors of any Navy procurement program to report, within 15
calendar days of any contractor or subcontractor stop work order or within 15 days of a
contractor or subcontractor manufacturing disruption that has lasted 15 calendar days, to
the respective program manager and Navy technical authority.
The House amendment contained no similar provision.
Congressional Research Service

49

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The House recedes with an amendment that would limit such notifications to programs
procured with funds from the Shipbuilding and Conversion, Navy and Other Procurement,
Navy accounts.
The conferees direct the Secretary to submit a report to the congressional defense
committees not later than 60 days after the date of enactment of this Act that details the
plan to implement this provision as soon as possible.
Section 833 of H.Rept. 116-333 states:
SEC. 833. NAVAL VESSEL CERTIFICATION REQUIRED BEFORE MILESTONE B
APPROVAL.
Section 2366b(a) of title 10, United States Code, is amended—
(1) in paragraph (3)(O), by striking ‘‘; and’’ and inserting a semicolon;
(2) in paragraph (4), by striking the period at the end and inserting ‘‘; and’’; and
(3) by adding at the end the following new paragraph:
‘‘(5) in the case of a naval vessel program, certifies compliance with the requirements of
section 8669b of this title.’’.
Section 853 of H.Rept. 116-333 states:
SEC. 853. REQUIREMENT THAT CERTAIN SHIP COMPONENTS BE
MANUFACTURED IN THE NATIONAL TECHNOLOGY AND INDUSTRIAL BASE.
(a) ADDITIONAL PROCUREMENT LIMITATION.—Section 2534(a) of title 10, United
States Code, is amended by adding at the end the following new paragraph:
‘‘(6) COMPONENTS FOR AUXILIARY SHIPS.— Subject to subsection (k), large
medium-speed diesel engines.’’.
(b) IMPLEMENTATION.—Such section is further amended by adding at the end the
following new subsection:
‘‘(k) IMPLEMENTATION OF AUXILIARY SHIP COMPONENT LIMITATION.—
Subsection (a)(6) applies only with respect to contracts awarded by the Secretary of a
military department for new construction of an auxiliary ship after the date of the enactment
of the National Defense Authorization Act for Fiscal Year 2020 using funds available for
National Defense Sealift Fund programs or Shipbuilding and Conversion, Navy. For
purposes of this subsection, the term ‘auxiliary ship’ does not include an icebreaker or a
special mission ship.’’.
Regarding Section 853, H.Rept. 116-333 states:
Requirement that certain ship components be manufactured in the national technology and
industrial base (sec. 853)

The House amendment contained a provision (sec. 806) that would amend section 2534 of
title 10, United States Code, and would require certain auxiliary ship components to be
procured from a manufacturer in the national technology and industrial base.
The Senate bill contained no similar provision.
The Senate recedes with an amendment that would require large medium speed diesel
engines for certain auxiliary ships to be procured from a manufacturer in the national
technology and industrial base.
The conferees direct the Secretary of Defense to submit a report to the congressional
defense committees not later than 60 days after the date of enactment of this Act that details
Congressional Research Service

50

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

the plan to implement section 844 of the John S. McCain National Defense Authorization
Act (Public Law 115-232) as soon as possible.
Section 1031 of H.Rept. 116-333 states:
SEC. 1031. MODIFICATION OF AUTHORITY TO PURCHASE VESSELS USING
FUNDS IN NATIONAL DEFENSE SEALIFT FUND.
(a) IN GENERAL.—Section 2218(f)(3)(E) of title 10, United States Code, is amended—
(1) in clause (i), by striking ‘‘ten new sealift vessels’’ and inserting ‘‘ten new vessels that
are sea lift vessels, auxiliary vessels, or a combination of such vessels’’; and
(2) in clause (ii), by striking ‘‘sealift’’.
(b) EFFECTIVE DATE.—The amendments made by subsection (a) shall take effect on
October 1, 2019, and shall apply with respect to fiscal years beginning on or after that date.
Section 1032 of H.Rept. 116-333 states:
SEC. 1032. USE OF NATIONAL DEFENSE SEALIFT FUND FOR PROCUREMENT
OF TWO USED VESSELS.
Pursuant to section 2218(f)(3) of title 10, United States Code, and using amounts
authorized to be appropriated for Operation and Maintenance, Navy, for fiscal year 2020,
the Secretary of the Navy shall seek to enter into a contract for the procurement of two
used vessels.
Section 1034 of H.Rept. 116-333 states:
SEC. 1034. SENIOR TECHNICAL AUTHORITY FOR EACH NAVAL VESSEL
CLASS.
(a) SENIOR TECHNICAL AUTHORITY FOR EACH CLASS REQUIRED.—Chapter
863 of title 10, United States Code, is amended by inserting after section 8669a the
following new section:
‘‘§ 8669b. Senior Technical Authority for each naval vessel class
‘‘(a) SENIOR TECHNICAL AUTHORITY.—‘‘(1) DESIGNATION FOR EACH
VESSEL CLASS REQUIRED.—The Secretary of the Navy shall designate, in writing, a
Senior Technical Authority for each class of naval vessels as follows:
‘‘(A) In the case of a class of vessels which has received Milestone A approval, an approval
to enter into technology maturation and risk reduction, or an approval to enter into a
subsequent Department of Defense or Department of the Navy acquisition phase as of the
date of the enactment of the National Defense Authorization Act for Fiscal Year 2020, not
later than 30 days after such date of enactment.
‘‘(B) In the case of any class of vessels which has not received any approval described in
subparagraph (A) as of such date of enactment, at or before the first of such approvals.
‘‘(2) INDIVIDUALS ELIGIBLE FOR DESIGNATION.—Each individual designated as
a Senior Technical Authority under paragraph (1) shall be an employee of the Navy in the
Senior Executive Service in an organization of the Navy that—
‘‘(A) possesses the technical expertise required to carry out the responsibilities specified
in subsection (b); and
‘‘(B) operates independently of chains-of command for acquisition program management.
‘‘(3) TERM.—Each Senior Technical Authority shall be designated for a fixed term, not
shorter than the time anticipated to establish demonstrated successful performance of the
Congressional Research Service

51

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

class of vessels concerned in accordance with its approved capabilities document, as
determined by the Secretary at the time of designation.
‘‘(4) VOLUNTARY DEPARTURE.—If an individual designated as a Senior Technical
Authority voluntarily departs the position before demonstrated successful performance of
the class of vessels concerned, the Secretary shall designate, in writing, a replacement, and
shall notify, in writing, the congressional defense committees not later than 90 days after
such departure.
‘‘(5) REMOVAL.—An individual may be removed involuntarily from designation as a
Senior Technical Authority only by the Secretary. Not later than 15 days after the
involuntary removal of an individual from such designation, the Secretary shall notify, in
writing, the congressional defense committees of the removal, including the reasons for the
removal. Not later than 90 days after the involuntary removal, the Secretary shall designate,
in writing, a replacement, and shall notify, in writing, the congressional defense
committees of such designation.
‘‘(6) REASSIGNMENT FOR MISSION NEEDS.—Subject to paragraphs (4) and (5), the
Secretary may reassign a Senior Technical Authority or remove an individual from
designation as a Senior Technical Authority in furtherance of Department of the Navy
mission needs.
‘‘(b) RESPONSIBILITIES AND AUTHORITY.—Each Senior Technical Authority shall
be responsible for, and have the authority to, establish, monitor, and approve technical
standards, tools, and processes for the class of naval vessels for which designated under
this section in conformance with applicable laws and Department of Defense and
Department of the Navy policies, requirements, architectures, and standards.
‘‘(c) LIMITATION ON OBLIGATION OF FUNDS ON LEAD VESSEL IN VESSEL
CLASS.—
‘‘(1) IN GENERAL.—On or after January 1, 2021, funds authorized to be appropriated for
Ship building and Conversion, Navy or Other Procurement, Navy may not be obligated for
the first time on the lead vessel in a class of naval vessels unless the Secretary of the Navy
certifies as described in paragraph (2).
‘‘(2) CERTIFICATION ELEMENTS.—The certification on a class of naval vessels
described in this paragraph is a certification containing each of the following:
‘‘(A) The name or names of the individual or individuals designated as the Senior
Technical Authority for such class of vessels, and the qualifications and professional
biography or biographies of the individual or individuals so designated.
‘‘(B) A description by the Senior Technical Authority of the systems engineering,
technology, and ship integration risks for such class of vessels.
‘‘(C) The designation by the Senior Technical Authority of each critical hull, mechanical,
electrical, propulsion, and combat system of such class of vessels, including systems
relating to power generation, power distribution, and key operational mission areas.
‘‘(D) The date on which the Senior Technical Authority approved the systems engineering,
engineering development, and land-based engineering and testing plans for such class of
vessels.
‘‘(E) A description by the Senior Technical Authority of the key technical knowledge
objectives and demonstrated system performance of each plan approved as described in
subparagraph (D).
‘‘(F) A determination by the Senior Technical Authority that such plans are sufficient to
achieve thorough technical knowledge of critical systems of such class of vessels before
the start of detail design and construction.
Congressional Research Service

52

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

‘‘(G) A determination by the Senior Technical Authority that actual execution of activities
in support of such plans as of the date of the certification have been and continue to be
effective and supportive of the acquisition schedule for such class of vessels.
‘‘(H) A description by the Senior Technical Authority of other technology maturation and
risk reduction efforts not included in such plans for such class of vessels taken as of the
date of the certification.
‘‘(I) A certification by the Senior Technical Authority that each critical system covered by
subparagraph (C) has been demonstrated through testing of a prototype or identical
component in its final form, fit, and function in a realistic environment.
‘‘(J) A determination by the Secretary that the plans approved as described in subparagraph
(D) are fully funded and will be fully funded in the future-years defense program for the
fiscal year beginning in the year in which the certification is submitted.
‘‘(K) A determination by the Secretary that the Senior Technical Authority will approve,
in writing, the ship specification for such class of vessels before the request for proposals
for detail design, construction, or both, as applicable, is released.
‘‘(3) DEADLINE FOR SUBMITTAL OF CERTIFICATION.—The certification required
by this subsection with respect to a class of naval vessels shall be submitted, in writing, to
the congressional defense committees not fewer than 30 days before the Secretary obligates
for the first time funds authorized to be appropriated for Shipbuilding and Conversion,
Navy or Other Procurement, Navy for the lead vessel in such class of naval vessels.
‘‘(d) DEFINITIONS.—In this section:
‘‘(1) The term ‘class of naval vessels’—
‘‘(A) means any group of similar undersea or surface craft procured with Shipbuilding and
Conversion, Navy or Other Procurement, Navy funds, including manned, unmanned, and
op tionally-manned craft; and
‘‘(B) includes—
‘‘(i) a substantially new class of craft (including craft procured using ‘new start’
procurement); and
‘‘(ii) a class of craft undergoing a significant incremental change in its existing class (such
as a next ‘flight’ of destroyers or next ‘block’ of attack submarines).
‘‘(2) The term ‘future-years defense program’ has the meaning given that term in section
221 of this title.
‘‘(3) The term ‘Milestone A approval’ has the meaning given that term in section 2431a of
this title.’’.
(b) CLERICAL AMENDMENT.—The table of sections at the beginning of chapter 863
of such title is amended by inserting after the item relating to section 8669a the following
new item:
‘‘8669b. Senior Technical Authority for each naval vessel class.’’.
Regarding Section 1034, H.Rept. 116-333 states:
Senior Technical Authority for each naval vessel class (sec. 1034)
The Senate bill contained a provision (sec. 1017) that would require the designation of a
Senior Technical Authority (STA) for each class of naval vessels.
The House amendment contained no similar provision.
The House recedes with an amendment that would remove the prohibition on delegation
of the authority to designate STAs and adjust STA tenure requirements.
Congressional Research Service

53

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The conferees’ intent is that STAs are primarily or entirely employees of the Naval Sea
Systems Command engineering directorate (code 05) with the STA designation and
associated duties as primary or collateral responsibilities.
Section 1037 of H.Rept. 116-333 states:
SEC. 1037. REPORT ON SHIPBUILDER TRAINING AND THE DEFENSE
INDUSTRIAL BASE.
Not later than 180 days after the date of the enactment of this Act, the Secretary of Defense,
in coordination with the Secretary of Labor, shall submit to the Committee on Armed
Services and the Committee on Health, Education, Labor, and Pensions of the Senate and
the Committee on Armed Services and the Committee on Education and Labor of the
House of Representatives a report on shipbuilder training and hiring requirements
necessary to achieve the Navy’s 30-year shipbuilding plan and to maintain the shipbuilding
readiness of the defense industrial base. Such report shall include each of the following:
(1) An analysis and estimate of the time and investment required for new shipbuilders to
gain proficiency in particular shipbuilding occupational specialties, including detailed
information about the occupational specialty requirements necessary for construction of
naval surface ship and submarine classes to be included in the Navy’s 30-year shipbuilding
plan.
(2) An analysis of the age demographics and occupational experience level (measured in
years of experience) of the shipbuilding defense industrial workforce.
(3) An analysis of the potential time and investment challenges associated with developing
and retaining shipbuilding skills in organizations that lack intermediate levels of
shipbuilding experience.
(4) Recommendations concerning how to address shipbuilder training during periods of
demographic transition, including whether emerging technologies, such as augmented
reality, may aid in new shipbuilder training.
(5) Recommendations concerning how to encourage young adults to enter the defense ship
building industry and to develop the skills necessary to support the shipbuilding defense
industrial base.
Section 1039 of H.Rept. 116-333 states:
SEC. 1039. REPORT ON EXPANDING NAVAL VESSEL MAINTENANCE.
(a) REPORT REQUIRED.—Not later than May 1, 2020, the Secretary of the Navy shall
submit to the congressional defense committees a report on the feasibility and advisability
of allowing maintenance to be performed on a naval vessel at a shipyard other than a
homeport shipyard of the vessel.
(b) ELEMENTS.—The report required under subsection (a) shall include the following:
(1) An assessment of the ability of homeport shipyards to meet the current naval vessel
maintenance demands.
(2) An assessment of the ability of homeport shipyards to meet the naval vessel
maintenance demands of the force structure assessment requirement of the Navy for a 355-
ship navy.
(3) An assessment of the ability of non-home port firms to augment repair work at
homeport ship yards, including an assessment of the following:
(A) The capability and proficiency of shipyards in the Great Lakes, Gulf Coast, East Coast,
West Coast, and Alaska regions to perform technical repair work on naval vessels at
locations other than their homeports.
Congressional Research Service

54

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

(B) The improvements to the capability and capacity of shipyards in the Great Lakes, Gulf
Coast, East Coast, West Coast, and Alaska regions that would be required to enable
performance of technical repair work on naval vessels at locations other than their
homeports.
(C) The types of naval vessels (such as noncombatant vessels or vessels that only need
limited periods of time in shipyards) best suited for repair work performed by shipyards in
locations other than their homeports.
(D) The potential benefits to fleet readiness of expanding shipyard repair work to include
shipyards not located at the homeports of naval vessels.
(E) The ability of non-homeport firms to maintain surge capacity when homeport ship
yards lack the capacity or capability to meet homeport requirements.
(4) An assessment of the potential benefits of expanding repair work for naval vessels to
shipyards not eligible for short-term work in accordance with section 8669a(c) of title 10,
United States Code.
(5) Such other related matters as the Secretary of the Navy considers appropriate.
(c) RULES OF CONSTRUCTION.—
(1) REQUIREMENTS RELATING TO CONSTRUCTION OF COMBATANT AND
ESCORT VESSELS AND AS SIGNMENT OF VESSEL PROJECTS.—Nothing in this
section may be construed to override the requirements of section 8669a of title 10, United
States Code.
(2) NO FUNDING FOR SHIPYARDS OF NON-HOMEPORT FIRMS.—Nothing in this
section may be construed to authorize funding for shipyards of non-homeport firms.
(d) DEFINITIONS.—In this section:
(1) HOMEPORT SHIPYARD.—The term ‘‘home port shipyard’’ means a shipyard
associated with a firm capable of being awarded short-term work at the homeport of a naval
vessel in accordance with section 8669a(c) of title 10, United States Code.
(2) SHORT-TERM WORK.—The term ‘‘short term work’’ has the meaning given that
term in section 8669a(c)(4) of such title.
In connection with Section 131 of H.Rept. 116-333—a section relating to a future class of surface
combatant51—H.Rept. 116-333 states:
The conferees note that over the last 10 years, the Comptroller General of the United States
has issued at least 26 reports that identified shipbuilding best practices and made 67
recommendations to help the Navy improve shipbuilding outcomes.
In a June 2018 report, the Government Accountability Office found that the Navy, in many
cases, has not taken steps based upon these shipbuilding best practices.
In order to better understand the key aspects of ship design necessary to provide confidence
in a program’s cost, schedule, and reliability targets, the conferees direct the Comptroller
General to conduct a review of shipbuilding design practices. This review shall include an
examination of the Navy’s design practices for shipbuilding major defense acquisition
programs to assess measures of the lead ship or lead ship of a major ship modification’s
design maturity and stability sufficient to inform an understanding of the construction costs
and the effort needed to execute the design, and any other related matters. The Comptroller
General shall provide a briefing and report to the congressional defense committees not

51 For the text of Section 131, see the legislative activity section of CRS Report RL32109, Navy DDG-51 and DDG-
1000 Destroyer Programs: Background and Issues for Congress
, by Ronald O'Rourke.
Congressional Research Service

55

link to page 41 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

later than April 1, 2020 and January 1, 2021, respectively, that describe the findings of the
review.
H.Rept. 116-333 also states:
Program for research and development of advanced naval nuclear fuel system based on
low-enriched uranium

The Senate bill contained a provision (sec. 3115) that would prohibit the obligation or
expenditure of any funds for fiscal year 2020 or thereafter for the National Nuclear Security
Administration to conduct research and development for an advanced naval nuclear fuel
system based on low-enriched uranium (LEU) unless the Secretary of Defense, Secretary
of Energy, and Secretary of the Navy submit certain certifications to the congressional
defense committees.
The House amendment contained a provision (sec. 3118) that would require the
Administrator for Nuclear Security to establish a program to assess the viability of using
LEU in naval nuclear propulsion reactors, including reactors located on aircraft carriers
and submarines, that meet the requirements of the Navy. The provision would require this
program to include down-blending of high-enriched uranium (HEU) into LEU,
manufacturing of candidate fuels, irradiation tests and postirradiation examination
capabilities, and modification or procurement of equipment and infrastructure related to
these activities. Finally, the provision would require the Administrator to submit a plan to
carry out this program, including the funding requirements associated.
The House amendment also contained a provision (sec. 3122) that would authorize to be
appropriated $20.0 million for low-enriched uranium research and development within the
defense nuclear nonproliferation account.
The conference agreement does not include any of these provisions.
FY2020 DOD Appropriations Act (H.R. 2968/S. 2474)
House
The House Appropriations Committee, in its report (H.Rept. 116-84 of May 23, 2019) on H.R.
2968, recommended the funding levels shown in the HAC column of Table 6. Regarding
recommended changes from requested ship quantities for FY2020, the committee recommended
funding for the procurement of
 two Virginia-class attack submarines, rather than the three that the Navy had
requested (i.e., -1); and
 one ship-to-shore connector (SSC) landing craft—the Navy had not requested the
procurement of such a craft in FY2020 (+1).
H.Rept. 116-84 states
EXPEDITIONARY SEA BASE
The Expeditionary Sea Base is a mature, affordable shipbuilding program that provides
combatant commanders with the flexibility to respond to immediate threats around the
world. The fiscal year 2020 budget request projects procurement funding for the next
Expeditionary Sea Base in fiscal years 2022 and 2023, three years later than the fiscal year
2019 budget request and shipbuilding plan had projected. The Committee encourages the
Secretary of the Navy to accelerate the procurement of the next Expeditionary Sea Base to
achieve the required capability, while allowing for greater affordability and stability for the
industrial base. (Page 176)
Congressional Research Service

56

link to page 41 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Senate
The Senate Appropriations Committee, in its report (S.Rept. 116-103 of September 12, 2019) on
S. 2474, recommended the funding levels shown in the SAC column of Table 6. Regarding
recommended changes from requested ship quantities for FY2020, the committee recommended
funding for the procurement of
 two Virginia-class attack submarines, rather than the three that the Navy had
requested (i.e., -1);
 one LPD-17 Flight II amphibious ship—the acceleration of a ship that the Navy
had planned to procure in FY2021 (+1);
 one LHA amphibious assault ship—the acceleration of a ship that the Navy had
planned to procure in FY2024 (+1);
 one Expeditionary Fast Transport (EPF) ship—the Navy had not requested the
procurement of such a ship in FY2020 (+1);
 one towing, salvage, and rescue ship (TATS), rather than the two that the Navy
had requested (-1);
 one service craft—the Navy had not requested the procurement of such a craft in
FY2020 (+1); and
 two unmanned service vessels (USVs)—the transfer into the Navy’s shipbuilding
account of USVs that the Navy had requested for procurement through the
Navy’s research and development account (+2 for the shipbuilding account;
neutral for the Navy’s budget as a whole).
S.Rept. 116-103 states
Shipbuilding Manufacturing.—The Committee recognizes the importance of building
strong partnerships among Department of Navy research labs, academia and naval
shipyards that construct our nation’s submarines. The Committee encourages the Navy to
coordinate manufacturing efforts with industrial base partners to ensure that funded
research projects are relevant to specific engineering and manufacturing needs, as well as
defined systems capabilities. Partnerships with academia should focus on well-defined
submarine and autonomous undersea vehicle research needs, accelerated technology
transition projects and workforce development to help ensure a sustainable industrial base.
The Committee believes that all manufacturing efforts should focus on reducing the cost
of manufacturing and sustaining the submarine fleet. (Page 200)

Congressional Research Service

57

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix A. Strategic and Budgetary Context
This appendix presents some brief comments on elements of the strategic and budgetary context
in which U.S. Navy force structure and shipbuilding plans may be considered.
Shift in International Security Environment
World events in recent years have led observers, particularly since late 2013, to conclude that the
international security environment in recent years has undergone a shift from the post-Cold War
era that began in the late 1980s and early 1990s, also sometimes known as the unipolar moment
(with the United States as the unipolar power), to a new and different situation that features,
among other things, renewed great power competition with China and Russia and challenges by
these two countries and others to elements of the U.S.-led international order that has operated
since World War II. This situation, which has multiple potential implications for U.S. defense
plans and programs, is discussed further in another CRS report.52
World Geography, U.S. Grand Strategy, and U.S. Naval Forces53
From a U.S. perspective on grand strategy and geopolitics,54 it can be noted that most of the
world’s people, resources, and economic activity are located not in the Western Hemisphere, but
in the other hemisphere, particularly Eurasia. In response to this basic feature of world geography,
U.S. policymakers for the past several decades have chosen to pursue, as a key element of U.S.
national strategy, a goal of preventing the emergence of a regional hegemon in one part of Eurasia
or another, on the grounds that such a hegemon could represent a concentration of power strong
enough to threaten vital U.S. interests by, for example, denying the United States access to some
of the other hemisphere’s resources and economic activity. Although U.S. policymakers have not
often stated this key national strategic goal explicitly in public, U.S. military (and diplomatic)
operations in recent decades—both wartime operations and day-to-day operations—can be
viewed as having been carried out in no small part in support of this key goal.
The traditional U.S. goal of preventing the emergence of a regional hegemon in one part of
Eurasia or another has been a major reason why the U.S. military is structured with force
elements that enable it to cross broad expanses of ocean and air space and then conduct sustained,

52 CRS Report R43838, Renewed Great Power Competition: Implications for Defense—Issues for Congress, by Ronald
O'Rourke.
53 For a stand-alone CRS product covering much of the same material presented in this section, see CRS In Focus
IF10485, Defense Primer: Geography, Strategy, and U.S. Force Design, by Ronald O'Rourke.
54 The term grand strategy generally refers in foreign policy discussions to a country’s overall approach for securing its
interests and making its way in the world, using all the national instruments at its disposal, including diplomatic,
informational, military, and economic tools (sometimes abbreviated in U.S. government parlance as DIME). A
country’s role in the world can be viewed as a visible expression of its grand strategy. For the United States, grand
strategy can be viewed as a design or blueprint at a global or interregional level, as opposed to U.S. approaches for
individual regions, countries, or issues.
The term geopolitics is often used as a synonym for international politics or for strategy relating to international
politics. More specifically, it refers to the influence of basic geographic features on international relations, and to the
analysis of international relations from a perspective that places a strong emphasis on the influence of such geographic
features. Basic geographic features involved in geopolitical analysis include things such as the relative sizes and
locations of countries or land masses; the locations of key resources such as oil or water; geographic barriers such as
oceans, deserts, and mountain ranges; and key transportation links such as roads, railways, and waterways.
For additional discussion, see CRS Report R44891, U.S. Role in the World: Background and Issues for Congress, by
Ronald O'Rourke and Michael Moodie.
Congressional Research Service

58

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

large-scale military operations upon arrival. Force elements associated with this goal include,
among other things, an Air Force with significant numbers of long-range bombers, long-range
surveillance aircraft, long-range airlift aircraft, and aerial refueling tankers, and a Navy with
significant numbers of aircraft carriers, nuclear-powered attack submarines, large surface
combatants, large amphibious ships, and underway replenishment ships.
The United States is the only country in the world that has designed its military to cross broad
expanses of ocean and air space and then conduct sustained, large-scale military operations upon
arrival. The other countries in the Western Hemisphere do not design their forces to do this
because they cannot afford to, and because the United States has been, in effect, doing it for them.
Countries in the other hemisphere do not design their forces to do this for the very basic reason
that they are already in the other hemisphere, and consequently instead spend their defense
money on forces that are tailored largely for influencing events in their own local region.
The fact that the United States has designed its military to do something that other countries do
not design their forces to do—cross broad expanses of ocean and air space and then conduct
sustained, large-scale military operations upon arrival—can be important to keep in mind when
comparing the U.S. military to the militaries of other nations. For example, in observing that the
U.S. Navy has 11 aircraft carriers while other countries have no more than one or two, it can be
noted other countries do not need a significant number of aircraft carriers because, unlike the
United States, they are not designing their forces to cross broad expanses of ocean and air space
and then conduct sustained, large-scale military operations upon arrival.
As another example, it is sometimes noted, in assessing the adequacy of U.S. naval forces, that
U.S. naval forces are equal in tonnage to the next dozen or more navies combined, and that most
of those next dozen or more navies are the navies of U.S. allies. Those other fleets, however, are
mostly of Eurasian countries, which do not design their forces to cross to the other side of the
world and then conduct sustained, large-scale military operations upon arrival. The fact that the
U.S. Navy is much bigger than allied navies does not necessarily prove that U.S. naval forces are
either sufficient or excessive; it simply reflects the differing and generally more limited needs that
U.S. allies have for naval forces. (It might also reflect an underinvestment by some of those allies
to meet even their more limited naval needs.)
Countries have differing needs for naval and other military forces. The United States, as a country
located in the Western Hemisphere that has adopted a goal of preventing the emergence of a
regional hegemon in one part of Eurasia or another, has defined a need for naval and other
military forces that is quite different from the needs of allies that are located in Eurasia. The
sufficiency of U.S. naval and other military forces consequently is best assessed not through
comparison to the militaries of other countries, but against U.S. strategic goals.
More generally, from a geopolitical perspective, it can be noted that that U.S. naval forces, while
not inexpensive, give the United States the ability to convert the world’s oceans—a global
commons that covers more than two-thirds of the planet’s surface—into a medium of maneuver
and operations for projecting U.S. power ashore and otherwise defending U.S. interests around
the world. The ability to use the world’s oceans in this manner—and to deny other countries the
use of the world’s oceans for taking actions against U.S. interests—constitutes an immense
asymmetric advantage for the United States. This point would be less important if less of the
world were covered by water, or if the oceans were carved into territorial blocks, like the land.
Most of the world, however, is covered by water, and most of those waters are international
waters, where naval forces can operate freely. The point, consequently, is not that U.S. naval
forces are intrinsically special or privileged—it is that they have a certain value simply as a
consequence of the physical and legal organization of the planet.
Congressional Research Service

59

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Potential Change in U.S. Role in the World
The U.S. role in the world refers to the overall character, purpose, or direction of U.S.
participation in international affairs and the country’s overall relationship to the rest of the world.
The U.S. role in the world can be viewed as establishing the overall context or framework for
U.S. policymakers for developing, implementing, and measuring the success of U.S. policies and
actions on specific international issues, and for foreign countries or other observers for
interpreting and understanding U.S. actions on the world stage.
While descriptions of the U.S. role in the world since the end of World War II vary in their
specifics, it can be described in general terms as consisting of four key elements: global
leadership; defense and promotion of the liberal international order; defense and promotion of
freedom, democracy, and human rights; and prevention of the emergence of regional hegemons in
Eurasia.
A change in the U.S. role could have significant and even profound effects on U.S. security,
freedom, and prosperity. It could lead to a change in U.S. grand strategy (see previous section),
which in turn could lead to significant changes to U.S. defense plans and programs, including
plans and programs relating to the Navy.
Some observers, particularly critics of the Trump Administration, argue that under the Trump
Administration, the United States is substantially changing the U.S. role in the world. Other
observers, particularly supporters of the Trump Administration, while acknowledging that the
Trump Administration has changed U.S. foreign policy in a number of areas compared to policies
pursued by the Obama Administration, argue that under the Trump Administration, there has been
less change and more continuity regarding the U.S. role in the world. The situation is discussed
further in another CRS report.55
Declining U.S. Technological and Qualitative Edge
DOD officials have expressed concern that the technological and qualitative edge that U.S.
military forces have had relative to the military forces of other countries is being narrowed by
improving military capabilities in other countries. China’s improving military capabilities are a
primary contributor to that concern.56 Russia’s rejuvenated military capabilities are an additional
contributor. DOD in recent years has taken a number of actions to arrest and reverse the decline in
the U.S. technological and qualitative edge.57
China’s Naval Modernization Effort
Observers of Chinese and U.S. military forces view China’s improving naval capabilities as
posing a potential challenge in the Western Pacific to the U.S. Navy’s ability to achieve and
maintain control of blue-water ocean areas in wartime—the first such challenge the U.S. Navy
has faced since the end of the Cold War.58 More broadly, these observers view China’s naval

55 See CRS Report R44891, U.S. Role in the World: Background and Issues for Congress, by Ronald O'Rourke and
Michael Moodie.
56 For more on China’s naval modernization effort, see CRS Report RL33153, China Naval Modernization:
Implications for U.S. Navy Capabilities—Background and Issues for Congress
, by Ronald O'Rourke.
57 For additional discussion, see CRS Report R43838, Renewed Great Power Competition: Implications for Defense—
Issues for Congress
, by Ronald O'Rourke.
58 The term “blue-water ocean areas” is used here to mean waters that are away from shore, as opposed to near-shore
Congressional Research Service

60

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

capabilities as a key element of an emerging broader Chinese military challenge to the long-
standing status of the United States as the leading military power in the Western Pacific.
Constraints on Defense Spending
Constraints on defense spending, combined with some of the considerations above, have led to
discussions among observers about how to balance competing demands for finite U.S. defense
funds, and about whether programs for responding to China’s military modernization effort can
be adequately funded while also adequately funding other defense-spending priorities, such as
initiatives for responding to Russia’s actions in Ukraine and elsewhere in Europe and U.S.
operations for countering challenges to U.S. interests in the Middle East.

(i.e., littoral) waters. Iran is viewed as posing a challenge to the U.S. Navy’s ability to quickly achieve and maintain sea
control in littoral waters in and near the Strait of Hormuz.
Congressional Research Service

61

link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 67 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 link to page 68 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix B. Earlier Navy Force-Structure Goals
Dating Back to 2001
The table below shows earlier Navy force-structure goals dating back to 2001. The 308-ship
force-level goal of March 2015, shown in the first column of the table, is the goal that was
replaced by the 355-ship force-level goal released in December 2016.
Table B-1. Earlier Navy Force-Structure Goals Dating Back to 2001
Changes
Early-2005
2002-
to
Navy goal
2004
2001
~310-
Revised
February
February
for fleet of
Navy QDR
308-
306-
316
313-ship
2006 313-
2006
260-325
goal
goal
ship
ship
ship
goal of
ship goal
Navy
ships
for
for
goal of goal of
goal of
Septem-
announced
goal for
375-
310-
March January
March
ber
through
313-ship
260-
325-
ship
ship
Ship type
2015
2013
2012
2011
mid-2011
fleet
ships ships Navya Navy
Ballistic missile submarines
12b
12b
12-14b
12b
12b
14
14
14
14
14
(SSBNs)
Cruise missile submarines
0c
0c
0-4c
4c
0c
4
4
4
4
2 or
(SSGNs)
4d
Attack submarines (SSNs)
48
48
~48
48
48
48
37
41
55
55
Aircraft carriers
11e
11e
11e
11e
11e
11f
10
11
12
12
Cruisers and destroyers
88
88
~90
94
94g
88
67
92
104
116
Frigates
0
0
0
0
0
0
0
0
0
Littoral Combat Ships (LCSs)
52
52
~55
55
55
55
63
82
56
0
Amphibious ships
34
33
~32
33
33h
31
17
24
37
36
MPF(F) shipsi
0j
0j
0j
0j
0j
12i
14i
20i
0i
0i
Combat logistics (resupply) ships
29
29
~29
30
30
30
24
26
42
34
Dedicated mine warfare ships
0
0
0
0
0
0
0
0
26k
16
Joint High Speed Vessels (JHSVs)
10l
10l
10l
10l
21l
3
0
0
0
0
Otherm
24
23
~23
16
24n
17
10
11
25
25
Total battle force ships
308
306
~310-
313
328
313
260
325
375
310
316
or
312
Sources: Table prepared by CRS based on U.S. Navy data.
Notes: QDR is Quadrennial Defense Review. The “~” symbol means approximately.
a. Initial composition. Composition was subsequently modified.
b. The Navy plans to replace the 14 current Ohio-class SSBNs with a new class of 12 next-generation SSBNs.
For further discussion, see CRS Report R41129, Navy Columbia (SSBN-826) Class Ballistic Missile Submarine
Program: Background and Issues for Congress
, by Ronald O'Rourke.
c. Although the Navy plans to continue operating its four SSGNs until they reach retirement age in the late
2020s, the Navy does not plan to replace these ships when they retire. This situation can be expressed in a
table like this one with either a 4 or a 0.
d. The report on the 2001 QDR did not mention a specific figure for SSGNs. The Administration’s proposed
FY2001 DOD budget requested funding to support the conversion of two available Trident SSBNs into
SSGNs, and the retirement of two other Trident SSBNs. Congress, in marking up this request, supported a
plan to convert all four available SSBNs into SSGNs.
Congressional Research Service

62

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

e. With congressional approval, the goal has been temporarily be reduced to 10 carriers for the period
between the retirement of the carrier Enterprise (CVN-65) in December 2012 and entry into service of the
carrier Gerald R. Ford (CVN-78), currently scheduled for September 2015.
f.
For a time, the Navy characterized the goal as 11 carriers in the nearer term, and eventually 12 carriers.
g. The 94-ship goal was announced by the Navy in an April 2011 report to Congress on naval force structure
and missile defense.
h. The Navy acknowledged that meeting a requirement for being able to lift the assault echelons of 2.0 Marine
Expeditionary Brigades (MEBs) would require a minimum of 33 amphibious ships rather than the 31 ships
shown in the February 2006 plan. For further discussion, see CRS Report RL34476, Navy LPD-17 Amphibious
Ship Procurement: Background, Issues, and Options for Congress
, by Ronald O'Rourke.
i.
Today’s Maritime Prepositioning Force (MPF) ships are intended primarily to support Marine Corps
operations ashore, rather than Navy combat operations, and thus are not counted as Navy battle force
ships. The planned MPF (Future) ships, however, would have contributed to Navy combat capabilities (for
example, by supporting Navy aircraft operations). For this reason, the ships in the planned MPF(F) squadron
were counted by the Navy as battle force ships. The planned MPF(F) squadron was subsequently
restructured into a different set of initiatives for enhancing the existing MPF squadrons; the Navy no longer
plans to acquire an MPF(F) squadron.
j.
The Navy no longer plans to acquire an MPF(F) squadron. The Navy, however, has procured or plans to
procure some of the ships that were previously planned for the squadron—specifically, TAKE-1 class cargo
ships, and Mobile Landing Platform (MLP)/Afloat Forward Staging Base (AFSB) ships. These ships are
included in the total shown for “Other” ships. AFSBs are now called Expeditionary Support Base ships
(ESBs).
k. The figure of 26 dedicated mine warfare ships included 10 ships maintained in a reduced mobilization status
called Mobilization Category B. Ships in this status are not readily deployable and thus do not count as
battle force ships. The 375-ship proposal thus implied transferring these 10 ships to a higher readiness
status.
l.
Totals shown include 5 ships transferred from the Army to the Navy and operated by the Navy primarily
for the performance of Army missions.
m. This category includes, among other things, command ships and support ships.
n. The increase in this category from 17 ships under the February 2006 313-ship goal to 24 ships under the
apparent 328-ship goal included the addition of one TAGOS ocean surveillance ship and the transfer into
this category of six ships—three modified TAKE-1 class cargo ships, and three Mobile Landing Platform
(MLP) ships—that were previously intended for the planned (but now canceled) MPF(F) squadron.

Congressional Research Service

63

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix C. Comparing Past Ship Force Levels to
Current or Potential Future Levels
In assessing the appropriateness of the current or potential future number of ships in the Navy,
observers sometimes compare that number to historical figures for total Navy fleet size. Historical
figures for total fleet size, however, can be a problematic yardstick for assessing the
appropriateness of the current or potential future number of ships in the Navy, particularly if the
historical figures are more than a few years old, because
 the missions to be performed by the Navy, the mix of ships that make up the
Navy, and the technologies that are available to Navy ships for performing
missions all change over time; and
 the number of ships in the fleet in an earlier year might itself have been
inappropriate (i.e., not enough or more than enough) for meeting the Navy’s
mission requirements in that year.
Regarding the first bullet point above, the Navy, for example, reached a late-Cold War peak of
568 battle force ships at the end of FY1987,59 and as of November 1, 2019, included a total of
291 battle force ships. The FY1987 fleet, however, was intended to meet a set of mission
requirements that focused on countering Soviet naval forces at sea during a potential multitheater
NATO-Warsaw Pact conflict, while the November 2019 fleet is intended to meet a considerably
different set of mission requirements centered on influencing events ashore by countering both
land- and sea-based military forces of China, Russia, North Korea, and Iran, as well as nonstate
terrorist organizations. In addition, the Navy of FY1987 differed substantially from the November
2019 fleet in areas such as profusion of precision-guided air-delivered weapons, numbers of
Tomahawk-capable ships, and the sophistication of C4ISR systems and networking capabilities.60
In coming years, Navy missions may shift again, and the capabilities of Navy ships will likely
have changed further by that time due to developments such as more comprehensive
implementation of networking technology, increased use of ship-based unmanned vehicles, and
the potential fielding of new types of weapons such as lasers or electromagnetic rail guns.
The 568-ship fleet of FY1987 may or may not have been capable of performing its stated
missions; the 291-ship fleet of November 2019 may or may not be capable of performing its
stated missions; and a fleet years from now with a certain number of ships may or may not be
capable of performing its stated missions. Given changes over time in mission requirements, ship
mixes, and technologies, however, these three issues are to a substantial degree independent of
one another.

59 Some publications have stated that the Navy reached a peak of 594 ships at the end of FY1987. This figure, however,
is the total number of active ships in the fleet, which is not the same as the total number of battle force ships. The battle
force ships figure is the number used in government discussions of the size of the Navy. In recent years, the total
number of active ships has been larger than the total number of battle force ships. For example, the Naval History and
Heritage Command (formerly the Naval Historical Center) states that as of November 16, 2001, the Navy included a
total of 337 active ships, while the Navy states that as of November 19, 2001, the Navy included a total of 317 battle
force ships. Comparing the total number of active ships in one year to the total number of battle force ships in another
year is thus an apples-to-oranges comparison that in this case overstates the decline since FY1987 in the number of
ships in the Navy. As a general rule to avoid potential statistical distortions, comparisons of the number of ships in the
Navy over time should use, whenever possible, a single counting method.
60 C4ISR stands for command and control, communications, computers, intelligence, surveillance, and reconnaissance.
Congressional Research Service

64

link to page 88 link to page 67 link to page 67 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

For similar reasons, trends over time in the total number of ships in the Navy are not necessarily a
reliable indicator of the direction of change in the fleet’s ability to perform its stated missions. An
increasing number of ships in the fleet might not necessarily mean that the fleet’s ability to
perform its stated missions is increasing, because the fleet’s mission requirements might be
increasing more rapidly than ship numbers and average ship capability. Similarly, a decreasing
number of ships in the fleet might not necessarily mean that the fleet’s ability to perform stated
missions is decreasing, because the fleet’s mission requirements might be declining more rapidly
than numbers of ships, or because average ship capability and the percentage of time that ships
are in deployed locations might be increasing quickly enough to more than offset reductions in
total ship numbers.
Regarding the second of the two bullet points above, it can be noted that comparisons of the size
of the fleet today with the size of the fleet in earlier years rarely appear to consider whether the
fleet was appropriately sized in those earlier years (and therefore potentially suitable as a
yardstick of comparison), even though it is quite possible that the fleet in those earlier years
might not have been appropriately sized, and even though there might have been differences of
opinion among observers at that time regarding that question. Just as it might not be prudent for
observers years from now to tacitly assume that the 286-ship Navy of September 2018 was
appropriately sized for meeting the mission requirements of 2018, even though there were
differences of opinion among observers on that question, simply because a figure of 286 ships
appears in the historical records for 2018, so, too, might it not be prudent for observers today to
tacitly assume that the number of ships of the Navy in an earlier year was appropriate for meeting
the Navy’s mission requirements that year, even though there might have been differences of
opinion among observers at that time regarding that question, simply because the size of the Navy
in that year appears in a table like Table H-1.
Previous Navy force structure plans, such as those shown in Table B-1, might provide some
insight into the potential adequacy of a proposed new force-structure plan, but changes over time
in mission requirements, technologies available to ships for performing missions, and other force-
planning factors, as well as the possibility that earlier force-structure plans might not have been
appropriate for meeting the mission demands of their times, suggest that some caution should be
applied in using past force structure plans for this purpose, particularly if those past force
structure plans are more than a few years old. The Reagan-era goal for a 600-ship Navy, for
example, was designed for a Cold War set of missions focusing on countering Soviet naval forces
at sea, which is not an appropriate basis for planning the Navy today, and there was considerable
debate during those years as to the appropriateness of the 600-ship goal.61

61 Navy force structure plans that predate those shown in Table B-1 include the Reagan-era 600-ship goal of the 1980s,
the Base Force fleet of more than 400 ships planned during the final two years of the George H. W. Bush
Administration, the 346-ship fleet from the Clinton Administration’s 1993 Bottom-Up Review (or BUR, sometimes
also called Base Force II), and the 310-ship fleet of the Clinton Administration’s 1997 QDR. The table below
summarizes some key features of these plans.
Features of Recent Navy Force Structure Plans
Plan
600-ship
Base Force
1993 BUR
1997 QDR
Total ships
~600
~450/416a
346
~305/310b
Attack submarines
100
80/~55c
45-55
50/55d
Aircraft carriers
15e
12
11+1f
11+1f
Surface combatants
242/228g
~150
~124
116
Amphibious ships
~75h
51i
41i
36i
Congressional Research Service

65

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress


Source: Prepared by CRS based on DOD and U.S. Navy data.
a. Commonly referred to as 450-ship goal, but called for decreasing to 416 ships by end of FY1999.
b. Original total of about 305 ships was increased to about 310 due to increase in number of attack submarines to 55
from 50.
c. Plan originally included 80 attack submarines, but this was later reduced to about 55.
d. Plan originally included 50 attack submarines but this was later increased to 55.
e. Plus one additional aircraft carrier in the service life extension program (SLEP).
f. Eleven active carriers plus one operational reserve carrier.
g. Plan originally included 242 surface combatants but this was later reduced to 228.
h. Number needed to lift assault echelons of one Marine Expeditionary Force (MEF) plus one Marine Expeditionary
Brigade (MEB).
i. Number needed to lift assault echelons of 2.5 MEBs. Changing numbers needed to meet this goal reflect in part
changes in the design and capabilities of amphibious ships.
Congressional Research Service

66

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix D. Industrial Base and Employment
Aspects of Additional Shipbuilding Work
This appendix presents background information on the ability of the industrial base to take on the
additional shipbuilding work associated with achieving and maintaining the Navy’s 355-ship
force-level goal and on the employment impact of additional shipbuilding work.
Industrial Base Ability
The U.S. shipbuilding industrial base has some unused capacity to take on increased Navy
shipbuilding work, particularly for certain kinds of surface ships, and its capacity could be
increased further over time to support higher Navy shipbuilding rates. Navy shipbuilding rates
could not be increased steeply across the board overnight—time (and investment) would be
needed to hire and train additional workers and increase production facilities at shipyards and
supplier firms, particularly for supporting higher rates of submarine production. Depending on
their specialties, newly hired workers could be initially less productive per unit of time worked
than more experienced workers.
Some parts of the shipbuilding industrial base, such as the submarine construction industrial base,
could face more challenges than others in ramping up to the higher production rates required to
build the various parts of the 355-ship fleet. Over a period of a few to several years, with
investment and management attention, Navy shipbuilding could ramp up to higher rates for
achieving a 355-ship fleet over a period of 20-30 years.
An April 2017 CBO report stated that
all seven shipyards [currently involved in building the Navy’s major ships] would need to
increase their workforces and several would need to make improvements to their
infrastructure in order to build ships at a faster rate. However, certain sectors face greater
obstacles in constructing ships at faster rates than others: Building more submarines to
meet the goals of the 2016 force structure assessment would pose the greatest challenge to
the shipbuilding industry. Increasing the number of aircraft carriers and surface combatants
would pose a small to moderate challenge to builders of those vessels. Finally, building
more amphibious ships and combat logistics and support ships would be the least
problematic for the shipyards. The workforces across those yards would need to increase
by about 40 percent over the next 5 to 10 years. Managing the growth and training of those
new workforces while maintaining the current standard of quality and efficiency would
represent the most significant industrywide challenge. In addition, industry and Navy
sources indicate that as much as $4 billion would need to be invested in the physical
infrastructure of the shipyards to achieve the higher production rates required under the
[notional] 15-year and 20-year [buildup scenarios examined by CBO]. Less investment
would be needed for the [notional] 25-year or 30-year [buildup scenarios examined by
CBO].62
A January 13, 2017, press report states the following:
The Navy’s production lines are hot and the work to prepare them for the possibility of
building out a much larger fleet would be manageable, the service’s head of acquisition
said Thursday.
From a logistics perspective, building the fleet from its current 274 ships to 355, as
recommended in the Navy’s newest force structure assessment in December, would be

62 Congressional Budget Office, Costs of Building a 355-Ship Navy, April 2017, pp. 9-10.
Congressional Research Service

67

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

straightforward, Assistant Secretary of the Navy for Research, Development and
Acquisition Sean Stackley told reporters at the Surface Navy Association’s annual
symposium.
“By virtue of maintaining these hot production lines, frankly, over the last eight years, our
facilities are in pretty good shape,” Stackley said. “In fact, if you talked to industry, they
would say we’re underutilizing the facilities that we have.”
The areas where the Navy would likely have to adjust “tooling” to answer demand for a
larger fleet would likely be in Virginia-class attack submarines and large surface
combatants, the DDG-51 guided missile destroyers—two ship classes likely to surge if the
Navy gets funding to build to 355 ships, he said.
“Industry’s going to have to go out and procure special tooling associated with going from
current production rates to a higher rate, but I would say that’s easily done,” he said.
Another key, Stackley said, is maintaining skilled workers—both the builders in the yards
and the critical supply-chain vendors who provide major equipment needed for ship
construction. And, he suggested, it would help to avoid budget cuts and other events that
would force workforce layoffs.
“We’re already prepared to ramp up,” he said. “In certain cases, that means not laying off
the skilled workforce we want to retain.”63
A January 17, 2017, press report states the following:
Building stable designs with active production lines is central to the Navy’s plan to grow
to 355 ships. “if you look at the 355-ship number, and you study the ship classes (desired),
the big surge is in attack submarines and large surface combatants, which today are DDG-
51 (destroyers),” the Assistant Secretary of the Navy, Sean Stackley, told reporters at last
week’s Surface Navy Association conference. Those programs have proven themselves
reliable performers both at sea and in the shipyards.
From today’s fleet of 274 ships, “we’re on an irreversible path to 308 by 2021. Those ships
are already in construction,” said Stackley. “To go from there to 355, virtually all those
ships are currently in production, with some exceptions: Ohio Replacement, (we) just got
done the Milestone B there (to move from R&D into detailed design); and then upgrades
to existing platforms. So we have hot production lines that will take us to that 355-ship
Navy.”64
A January 24, 2017, press report states the following:
Navy officials say a recently determined plan to increase its fleet size by adding more new
submarines, carriers and destroyers is “executable” and that early conceptual work toward
this end is already underway....
Although various benchmarks will need to be reached in order for this new plan to come
to fruition, such as Congressional budget allocations, Navy officials do tell Scout Warrior
that the service is already working—at least in concept—on plans to vastly enlarge the
fleet. Findings from this study are expected to inform an upcoming 2018 Navy
Shipbuilding Plan, service officials said.65
A January 12, 2017, press report states the following:

63 Hope Hodge Seck, “Navy Acquisition Chief: Surge to 355 Ships ‘Easily Done,’” DoD Buzz, January 13, 2017.
64 Sydney J. Freedberg Jr., “Build More Ships, But Not New Designs: CNO Richardson To McCain,” Breaking
Defense
, January 17, 2017.
65 Kris Osborn, “Navy: Larger 355-Ship Fleet—‘Executable,’” Scout Warrior, January 24, 2017.
Congressional Research Service

68

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Brian Cuccias, president of Ingalls Shipbuilding [a shipyard owned by Huntington Ingalls
Industries (HII) that builds Navy destroyers and amphibious ships as well as Coast Guard
cutters], said Ingalls, which is currently building 10 ships for four Navy and Coast Guard
programs at its 800-acre facility in Pascagoula, Miss., could build more because it is using
only 70 to 75 percent of its capacity.66
A March 2017 press report states the following:
As the Navy calls for a larger fleet, shipbuilders are looking toward new contracts and
ramping up their yards to full capacity....
The Navy is confident that U.S. shipbuilders will be able to meet an increased demand,
said Ray Mabus, then-secretary of the Navy, during a speech at the Surface Navy
Association’s annual conference in Arlington, Virginia.
They have the capacity to “get there because of the ships we are building today,” Mabus
said. “I don’t think we could have seven years ago.”
Shipbuilders around the United States have “hot” production lines and are manufacturing
vessels on multi-year or block buy contracts, he added. The yards have made investments
in infrastructure and in the training of their workers.
“We now have the basis ... [to] get to that much larger fleet,” he said....
Shipbuilders have said they are prepared for more work.
At Ingalls Shipbuilding—a subsidiary of Huntington Ingalls Industries—10 ships are under
construction at its Pascagoula, Mississippi, yard, but it is under capacity, said Brian
Cuccias, the company’s president.
The shipbuilder is currently constructing five guided-missile destroyers, the latest San
Antonio-class amphibious transport dock ship, and two national security cutters for the
Coast Guard.
“Ingalls is a very successful production line right now, but it has the ability to actually
produce a lot more in the future,” he said during a briefing with reporters in January.
The company’s facility is currently operating at 75 percent capacity, he noted....
Austal USA—the builder of the Independence-variant of the littoral combat ship and the
expeditionary fast transport vessel—is also ready to increase its capacity should the Navy
require it, said Craig Perciavalle, the company’s president.
The latest discussions are “certainly something that a shipbuilder wants to hear,” he said.
“We do have the capability of increasing throughput if the need and demand were to arise,
and then we also have the ability with the present workforce and facility to meet a different
mix that could arise as well.”
Austal could build fewer expeditionary fast transport vessels and more littoral combat
ships, or vice versa, he added.
“The key thing for us is to keep the manufacturing lines hot and really leverage the
momentum that we’ve gained on both of the programs,” he said.
The company—which has a 164-acre yard in Mobile, Alabama—is focused on the
extension of the LCS and expeditionary fast transport ship program, but Perciavalle noted
that it could look into manufacturing other types of vessels.

66 Marc Selinger, “Navy Needs More Aircraft to Match Ship Increase, Secretary [of the Navy] Says,” Defense Daily,
January 12, 2017. See also Lee Hudson, “Ingalls Operating at About 75 Percent Capacity, Provided Info to Trump
Team,” Inside the Navy, January 16, 2017.
Congressional Research Service

69

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

“We do have excess capacity to even build smaller vessels … if that opportunity were to
arise and we’re pursuing that,” he said.
Bryan Clark, a naval analyst at the Center for Strategic and Budgetary Assessments, a
Washington, D.C.-based think tank, said shipbuilders are on average running between 70
and 80 percent capacity. While they may be ready to meet an increased demand for ships,
it would take time to ramp up their workforces.
However, the bigger challenge is the supplier industrial base, he said.
“Shipyards may be able to build ships but the supplier base that builds the pumps … and
the radars and the radios and all those other things, they don’t necessarily have that ability
to ramp up,” he said. “You would need to put some money into building up their capacity.”
That has to happen now, he added.
Rear Adm. William Gallinis, program manager for program executive office ships, said
what the Navy must be “mindful of is probably our vendor base that support the shipyards.”
Smaller companies that supply power electronics and switchboards could be challenged,
he said.
“Do we need to re-sequence some of the funding to provide some of the facility
improvements for some of the vendors that may be challenged? My sense is that the
industrial base will size to the demand signal. We just need to be mindful of how we
transition to that increased demand signal,” he said.
The acquisition workforce may also see an increased amount of stress, Gallinis noted. “It
takes a fair amount of experience and training to get a good contracting officer to the point
to be [able to] manage contracts or procure contracts.”
“But I don’t see anything that is insurmountable,” he added.67
At a May 24, 2017, hearing before the Seapower subcommittee of the Senate Armed Services
Committee on the industrial-base aspects of the Navy’s 355-ship goal, John P. Casey, executive
vice president–marine systems, General Dynamics Corporation (one of the country’s two
principal builders of Navy ships) stated the following:
It is our belief that the Nation’s shipbuilding industrial base can scale-up hot production
lines for existing ships and mobilize additional resources to accomplish the significant
challenge of achieving the 355-ship Navy as quickly as possible....
Supporting a plan to achieve a 355-ship Navy will be the most challenging for the nuclear
submarine enterprise. Much of the shipyard and industrial base capacity was eliminated
following the steep drop-off in submarine production that occurred with the cancellation
of the Seawolf Program in 1992. The entire submarine industrial base at all levels of the
supply chain will likely need to recapitalize some portion of its facilities, workforce, and
supply chain just to support the current plan to build the Columbia Class SSBN program,
while concurrently building Virginia Class SSNs. Additional SSN procurement will
require industry to expand its plans and associated investment beyond the level today....
Shipyard labor resources include the skilled trades needed to fabricate, build and outfit
major modules, perform assembly, test and launch of submarines, and associated support
organizations that include planning, material procurement, inspection, quality assurance,
and ship certification. Since there is no commercial equivalency for Naval nuclear
submarine shipbuilding, these trade resources cannot be easily acquired in large numbers
from other industries. Rather, these shipyard resources must be acquired and developed
over time to ensure the unique knowledge and know-how associated with nuclear

67 Yasmin Tadjdeh, “Navy Shipbuilders Prepared for Proposed Fleet Buildup,” National Defense, March 2017.
Congressional Research Service

70

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

submarine shipbuilding is passed on to the next generation of shipbuilders. The
mechanisms of knowledge transfer require sufficient lead time to create the proficient,
skilled craftsmen in each key trade including welding, electrical, machining, shipfitting,
pipe welding, painting, and carpentry, which are among the largest trades that would need
to grow to support increased demand. These trades will need to be hired in the numbers
required to support the increased workload. Both shipyards have scalable processes in place
to acquire, train, and develop the skilled workforce they need to build nuclear ships. These
processes and associated training facilities need to be expanded to support the increased
demand. As with the shipyards, the same limiting factors associated with facilities,
workforce, and supply chain also limit the submarine unique first tier suppliers and sub-
tiers in the industrial base for which there is no commercial equivalency....
The supply base is the third resource that will need to be expanded to meet the increased
demand over the next 20 years. During the OHIO, 688 and SEAWOLF construction
programs, there were over 17,000 suppliers supporting submarine construction programs.
That resource base was “rationalized” during submarine low rate production over the last
20 years. The current submarine industrial base reflects about 5,000 suppliers, of which
about 3,000 are currently active (i.e., orders placed within the last 5 years), 80% of which
are single or sole source (based on $). It will take roughly 20 years to build the 12 Columbia
Class submarines that starts construction in FY21. The shipyards are expanding strategic
sourcing of appropriate non-core products (e.g., decks, tanks, etc.) in order to focus on core
work at each shipyard facility (e.g., module outfitting and assembly). Strategic sourcing
will move demand into the supply base where capacity may exist or where it can be
developed more easily. This approach could offer the potential for cost savings by
competition or shifting work to lower cost work centers throughout the country. Each
shipyard has a process to assess their current supply base capacity and capability and to
determine where it would be most advantageous to perform work in the supply base....
Achieving the increased rate of production and reducing the cost of submarines will require
the Shipbuilders to rely on the supply base for more non-core products such as structural
fabrication, sheet metal, machining, electrical, and standard parts. The supply base must be
made ready to execute work with submarine-specific requirements at a rate and volume
that they are not currently prepared to perform. Preparing the supply base to execute
increased demand requires early non-recurring funding to support cross-program
construction readiness and EOQ funding to procure material in a manner that does not hold
up existing ship construction schedules should problems arise in supplier qualification
programs. This requires longer lead times (estimates of three years to create a new
qualified, critical supplier) than the current funding profile supports....
We need to rely on market principles to allow suppliers, the shipyards and GFE material
providers to sort through the complicated demand equation across the multiple ship
programs. Supplier development funding previously mentioned would support non-
recurring efforts which are needed to place increased orders for material in multiple market
spaces. Examples would include valves, build-to-print fabrication work, commodities,
specialty material, engineering components, etc. We are engaging our marine industry
associations to help foster innovative approaches that could reduce costs and gain
efficiency for this increased volume....
Supporting the 355-ship Navy will require Industry to add capability and capacity across
the entire Navy Shipbuilding value chain. Industry will need to make investment decisions
for additional capital spend starting now in order to meet a step change in demand that
would begin in FY19 or FY20. For the submarine enterprise, the step change was already
envisioned and investment plans that embraced a growth trajectory were already being
formulated. Increasing demand by adding additional submarines will require scaling
facility and workforce development plans to operate at a higher rate of production. The
nuclear shipyards would also look to increase material procurement proportionally to the
increased demand. In some cases, the shipyard facilities may be constrained with existing
Congressional Research Service

71

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

capacity and may look to source additional work in the supply base where capacity exists
or where there are competitive business advantages to be realized. Creating additional
capacity in the supply base will require non-recurring investment in supplier qualification,
facilities, capital equipment and workforce training and development.
Industry is more likely to increase investment in new capability and capacity if there is
certainty that the Navy will proceed with a stable shipbuilding plan. Positive signals of
commitment from the Government must go beyond a published 30-year Navy Shipbuilding
Plan and line items in the Future Years Defense Plan (FYDP) and should include
 Multi-year contracting for Block procurement which provides stability in the industrial
base and encourages investment in facilities and workforce development
 Funding for supplier development to support training, qualification, and facilitization
efforts—Electric Boat and Newport News have recommended to the Navy funding of
$400M over a three-year period starting in 2018 to support supplier development for the
Submarine Industrial Base as part of an Integrated Enterprise Plan Extended Enterprise
initiative
 Acceleration of Advance Procurement and/or Economic Order Quantities (EOQ)
procurement from FY19 to FY18 for Virginia Block V
 Government incentives for construction readiness and facilities / special tooling for
shipyard and supplier facilities, which help cash flow capital investment ahead of
construction contract awards
 Procurement of additional production back-up (PBU) material to help ensure a ready
supply of material to mitigate construction schedule risk....
So far, this testimony has focused on the Submarine Industrial Base, but the General
Dynamics Marine Systems portfolio also includes surface ship construction. Unlike
Electric Boat, Bath Iron Works and NASSCO are able to support increased demand without
a significant increase in resources.....
Bath Iron Works is well positioned to support the Administration’s announced goal of
increasing the size of the Navy fleet to 355 ships. For BIW that would mean increasing the
total current procurement rate of two DDG 51s per year to as many as four DDGs per year,
allocated equally between BIW and HII. This is the same rate that the surface combatant
industrial base sustained over the first decade of full rate production of the DDG 51 Class
(1989-1999)....
No significant capital investment in new facilities is required to accommodate delivering
two DDGs per year. However, additional funding will be required to train future
shipbuilders and maintain equipment. Current hiring and training processes support the
projected need, and have proven to be successful in the recent past. BIW has invested
significantly in its training programs since 2014 with the restart of the DDG 51 program
and given these investments and the current market in Maine, there is little concern of
meeting the increase in resources required under the projected plans.
A predictable and sustainable Navy workload is essential to justify expanding
hiring/training programs. BIW would need the Navy’s commitment that the Navy’s plan
will not change before it would proceed with additional hiring and training to support
increased production.
BIW’s supply chain is prepared to support a procurement rate increase of up to four DDG
51s per year for the DDG 51 Program. BIW has long-term purchasing agreements in place
for all major equipment and material for the DDG 51 Program. These agreements provide
for material lead time and pricing, and are not constrained by the number of ships ordered
in a year. BIW confirmed with all of its critical suppliers that they can support this
increased procurement rate....
Congressional Research Service

72

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The Navy’s Force Structure Assessment calls for three additional ESBs. Additionally,
NASSCO has been asked by the Navy and the Congressional Budget Office (CBO) to
evaluate its ability to increase the production rate of T-AOs to two ships per year. NASSCO
has the capacity to build three more ESBs at a rate of one ship per year while building two
T-AOs per year. The most cost effective funding profile requires funding ESB 6 in FY18
and the following ships in subsequent fiscal years to avoid increased cost resulting from a
break in the production line. The most cost effective funding profile to enable a production
rate of two T-AO ships per year requires funding an additional long lead time equipment
set beginning in FY19 and an additional ship each year beginning in FY20.
NASSCO must now reduce its employment levels due to completion of a series of
commercial programs which resulted in the delivery of six ships in 2016. The proposed
increase in Navy shipbuilding stabilizes NASSCO’s workload and workforce to levels that
were readily demonstrated over the last several years.
Some moderate investment in the NASSCO shipyard will be needed to reach this level of
production. The recent CBO report on the costs of building a 355-ship Navy accurately
summarized NASSCO’s ability to reach the above production rate stating, “building more
… combat logistics and support ships would be the least problematic for the shipyards.”68
At the same hearing, Brian Cuccias, president, Ingalls Shipbuilding, Huntington Ingalls Industries
(the country’s other principal builder of Navy ships) stated the following:
Qualifying to be a supplier is a difficult process. Depending on the commodity, it may take
up to 36 months. That is a big burden on some of these small businesses. This is why
creating sufficient volume and exercising early contractual authorization and advance
procurement funding is necessary to grow the supplier base, and not just for traditional
long-lead time components; that effort needs to expand to critical components and
commodities that today are controlling the build rate of submarines and carriers alike.
Many of our suppliers are small businesses and can only make decisions to invest in people,
plant and tooling when they are awarded a purchase order. We need to consider how we
can make commitments to suppliers early enough to ensure material readiness and
availability when construction schedules demand it.
With questions about the industry’s ability to support an increase in shipbuilding, both
Newport News and Ingalls have undertaken an extensive inventory of our suppliers and
assessed their ability to ramp up their capacity. We have engaged many of our key suppliers
to assess their ability to respond to an increase in production.
The fortunes of related industries also impact our suppliers, and an increase in demand
from the oil and gas industry may stretch our supply base. Although some low to moderate
risk remains, I am convinced that our suppliers will be able to meet the forecasted Navy
demand....
I strongly believe that the fastest results can come from leveraging successful platforms on
current hot production lines. We commend the Navy’s decision in 2014 to use the existing
LPD 17 hull form for the LX(R), which will replace the LSD-class amphibious dock
landing ships scheduled to retire in the coming years. However, we also recommend that
the concept of commonality be taken even further to best optimize efficiency, affordability
and capability. Specifically, rather than continuing with a new design for LX(R) within the
“walls” of the LPD hull, we can leverage our hot production line and supply chain and
offer the Navy a variant of the existing LPD design that satisfies the aggressive cost targets
of the LX(R) program while delivering more capability and survivability to the fleet at a

68 John P. Casey, Executive Vice President – Marine Systems, General Dynamics Corporation, Testimony before the
Senate Armed Services Committee, Subcommittee on Seapower, 115th Congress, Supporting the 355-Ship Navy with
Focus on Submarine Industrial Base, Washington, DC, May 24, 2017, pp. 3-18. See also Marjorie Censer, “BWX
Technologies Weighs When To Ready for Additional Submarines,” Inside the Navy, May 29, 2017.
Congressional Research Service

73

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

significantly faster pace than the current program. As much as 10-15 percent material
savings can be realized across the LX(R) program by purchasing respective blocks of at
least five ships each under a multi-year procurement (MYP) approach. In the aggregate,
continuing production with LPD 30 in FY18, coupled with successive MYP contracts for
the balance of ships, may yield savings greater than $1 billion across an 11-ship LX(R)
program. Additionally, we can deliver five LX(R)s to the Navy and Marine Corps in the
same timeframe that the current plan would deliver two, helping to reduce the shortfall in
amphibious warships against the stated force requirement of 38 ships.
Multi-ship procurements, whether a formal MYP or a block-buy, are a proven way to
reduce the price of ships. The Navy took advantage of these tools on both Virginia-class
submarines and Arleigh Burke-class destroyers. In addition to the LX(R) program
mentioned above, expanding multi-ship procurements to other ship classes makes sense....
The most efficient approach to lower the cost of the Ford class and meet the goal of an
increased CVN fleet size is also to employ a multi-ship procurement strategy and construct
these ships at three-year intervals. This approach would maximize the material
procurement savings benefit through economic order quantities procurement and provide
labor efficiencies to enable rapid acquisition of a 12-ship CVN fleet. This three-ship
approach would save at least $1.5 billion, not including additional savings that could be
achieved from government-furnished equipment. As part of its Integrated Enterprise Plan,
we commend the Navy’s efforts to explore the prospect of material economic order
quantity purchasing across carrier and submarine programs.69
At the same hearing, Matthew O. Paxton, president, Shipbuilders Council of America (SCA)—a
trade association representing shipbuilders, suppliers, and associated firms—stated the following:
To increase the Navy’s Fleet to 355 ships, a substantial and sustained investment is required
in both procurement and readiness. However, let me be clear: building and sustaining the
larger required Fleet is achievable and our industry stands ready to help achieve that
important national security objective.
To meet the demand for increased vessel construction while sustaining the vessels we
currently have will require U.S. shipyards to expand their work forces and improve their
infrastructure in varying degrees depending on ship type and ship mix – a requirement our
Nation’s shipyards are eager to meet. But first, in order to build these ships in as timely
and affordable manner as possible, stable and robust funding is necessary to sustain those
industrial capabilities which support Navy shipbuilding and ship maintenance and
modernization....
Beyond providing for the building of a 355-ship Navy, there must also be provision to fund
the “tail,” the maintenance of the current and new ships entering the fleet. Target fleet size
cannot be reached if existing ships are not maintained to their full service lives, while
building those new ships. Maintenance has been deferred in the last few years because of
across-the-board budget cuts....
The domestic shipyard industry certainly has the capability and know-how to build and
maintain a 355-ship Navy. The Maritime Administration determined in a recent study on
the Economic Benefits of the U.S. Shipyard Industry that there are nearly 110,000 skilled
men and women in the Nation’s private shipyards building, repairing and maintaining
America’s military and commercial fleets.1 The report found the U.S. shipbuilding
industry supports nearly 400,000 jobs across the country and generates $25.1 billion in
income and $37.3 billion worth of goods and services each year. In fact, the MARAD
report found that the shipyard industry creates direct and induced employment in every

69 Statement of Brian Cuccias, President, Ingalls Shipbuilding, Huntington Ingalls Industries, Subcommittee on
Seapower, Senate Armed Services Committee, May 24, 2017, pp. 4-11.
Congressional Research Service

74

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

State and Congressional District and each job in the private shipbuilding and repairing
industry supports another 2.6 jobs nationally.
This data confirms the significant economic impact of this manufacturing sector, but also
that the skilled workforce and industrial base exists domestically to build these ships. Long-
term, there needs to be a workforce expansion and some shipyards will need to reconfigure
or expand production lines. This can and will be done as required to meet the need if
adequate, stable budgets and procurement plans are established and sustained for the long-
term. Funding predictability and sustainability will allow industry to invest in facilities and
more effectively grow its skilled workforce. The development of that critical workforce
will take time and a concerted effort in a partnership between industry and the federal
government.
U.S. shipyards pride themselves on implementing state of the art training and
apprenticeship programs to develop skilled men and women that can cut, weld, and bend
steel and aluminum and who can design, build and maintain the best Navy in the world.
However, the shipbuilding industry, like so many other manufacturing sectors, faces an
aging workforce. Attracting and retaining the next generation shipyard worker for an
industry career is critical. Working together with the Navy, and local and state resources,
our association is committed to building a robust training and development pipeline for
skilled shipyard workers. In addition to repealing sequestration and stabilizing funding the
continued development of a skilled workforce also needs to be included in our national
maritime strategy....
In conclusion, the U.S. shipyard industry is certainly up to the task of building a 355-ship
Navy and has the expertise, the capability, the critical capacity and the unmatched skilled
workforce to build these national assets. Meeting the Navy’s goal of a 355-ship fleet and
securing America’s naval dominance for the decades ahead will require sustained
investment by Congress and Navy’s partnership with a defense industrial base that can
further attract and retain a highly-skilled workforce with critical skill sets. Again, I would
like to thank this Subcommittee for inviting me to testify alongside such distinguished
witnesses. As a representative of our nation’s private shipyards, I can say, with confidence
and certainty, that our domestic shipyards and skilled workers are ready, willing and able
to build and maintain the Navy’s 355-ship Fleet.70
Employment Impact
Building the additional ships that would be needed to achieve and maintain the 355-ship fleet
could create many additional manufacturing and other jobs at shipyards, associated supplier
firms, and elsewhere in the U.S. economy. A 2015 Maritime Administration (MARAD) report
states
Considering the indirect and induced impacts, each direct job in the shipbuilding and
repairing industry is associated with another 2.6 jobs in other parts of the US economy;
each dollar of direct labor income and GDP in the shipbuilding and repairing industry is
associated with another $1.74 in labor income and $2.49 in GDP, respectively, in other
parts of the US economy.71

70 Testimony of Matthew O. Paxton, President, Shipbuilders Council of America, before the United States Senate
Committee on Armed Services, Subcommittee on Seapower, [on] Industry Perspectives on Options and Considerations
for Achieving a 355-Ship Navy, May 24, 2017, pp. 3-8.
71 MARAD, The Economic Importance of the U.S. Shipbuilding and Repairing Industry, November 2015, pp. E-3, E-4,
For another perspective on the issue of the impact of shipbuilding on the broader economy, see Edward G. Keating et
al., The Economic Consequences of Investing in Shipbuilding, Case Studies in the United States and Sweden, RAND
Corporation, 2015.
Congressional Research Service

75

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

A March 2017 press report states, “Based on a 2015 economic impact study, the Shipbuilders
Council of America [a trade association for U.S. shipbuilders and associated supplier firms]
believes that a 355-ship Navy could add more than 50,000 jobs nationwide.”72 The 2015
economic impact study referred to in that quote might be the 2015 MARAD study discussed in
the previous paragraph. An estimate of more than 50,000 additional jobs nationwide might be
viewed as a higher-end estimate; other estimates might be lower. A June 14, 2017, press report
states the following: “The shipbuilding industry will need to add between 18,000 and 25,000 jobs
to build to a 350-ship Navy, according to Matthew Paxton, president of the Shipbuilders Council
of America, a trade association representing the shipbuilding industrial base. Including indirect
jobs like suppliers, the ramp-up may require a boost of 50,000 workers.”73

72 Yasmin Tadjdeh, “Navy Shipbuilders Prepared for Proposed Fleet Buildup,” National Defense, March 2017.
Similarly, another press report states the following: “The Navy envisioned by Trump could create more than 50,000
jobs, the Shipbuilders Council of America, a trade group representing U.S. shipbuilders, repairers and suppliers, told
Reuters.” (Mike Stone, “Missing from Trump’s Grand Navy Plan: Skilled Workers to Build the Fleet,” Reuters, March
17, 2017.)
73 Jaqueline Klimas, “Growing Shipbuilding Workforce Seen as Major Challenge for Trump’s Navy Buildup,” Politico,
June 14, 2017.
Congressional Research Service

76

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix E. A Summary of Some Acquisition
Lessons Learned for Navy Shipbuilding
This appendix presents a general summary of lessons learned in Navy shipbuilding, reflecting
comments made repeatedly by various sources over the years. These lessons learned include the
following:
At the outset, get the operational requirements for the program right.
Properly identify the program’s operational requirements at the outset. Manage
risk by not trying to do too much in terms of the program’s operational
requirements, and perhaps seek a so-called 70%-to-80% solution (i.e., a design
that is intended to provide 70%-80% of desired or ideal capabilities). Achieve a
realistic balance up front between operational requirements, risks, and estimated
costs.
Impose cost discipline up front. Use realistic price estimates, and consider not
only development and procurement costs, but life-cycle operation and support
(O&S) costs.
Employ competition where possible in the awarding of design and construction
contracts.
Use a contract type that is appropriate for the amount of risk involved, and
structure its terms to align incentives with desired outcomes.
Minimize design/construction concurrency by developing the design to a high
level of completion before starting construction and by resisting changes in
requirements (and consequent design changes) during construction.
Properly supervise construction work. Maintain an adequate number of
properly trained Supervisor of Shipbuilding (SUPSHIP) personnel.
Provide stability for industry, in part by using, where possible, multiyear
procurement (MYP) or block buy contracting.
Maintain a capable government acquisition workforce that understands what
it is buying, as well as the above points.
Identifying these lessons is arguably not the hard part—most if not all these points have been
cited for years. The hard part, arguably, is living up to them without letting circumstances lead
program-execution efforts away from these guidelines.
Congressional Research Service

77

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix F. Some Considerations Relating to
Warranties in Shipbuilding Contracts
This appendix presents some considerations relating to warranties in shipbuilding contracts and
other defense acquisition.
In discussions of Navy (and also Coast Guard) shipbuilding, one question that sometimes arises is
whether including a warranty in a shipbuilding contract is preferable to not including one. The
question can arise, for example, in connection with a GAO finding that “the Navy structures
shipbuilding contracts so that it pays shipbuilders to build ships as part of the construction
process and then pays the same shipbuilders a second time to repair the ship when construction
defects are discovered.”74
Including a warranty in a shipbuilding contract (or a contract for building some other kind of
defense end item), while potentially valuable, might not always be preferable to not including
one—it depends on the circumstances of the acquisition, and it is not necessarily a valid criticism
of an acquisition program to state that it is using a contract that does not include a warranty (or a
weaker form of a warranty rather than a stronger one).
Including a warranty generally shifts to the contractor the risk of having to pay for fixing
problems with earlier work. Although that in itself could be deemed desirable from the
government’s standpoint, a contractor negotiating a contract that will have a warranty will
incorporate that risk into its price, and depending on how much the contractor might charge for
doing that, it is possible that the government could wind up paying more in total for acquiring the
item (including fixing problems with earlier work on that item) than it would have under a
contract without a warranty.
When a warranty is not included in the contract and the government pays later on to fix problems
with earlier work, those payments can be very visible, which can invite critical comments from
observers. But that does not mean that including a warranty in the contract somehow frees the
government from paying to fix problems with earlier work. In a contract that includes a warranty,
the government will indeed pay something to fix problems with earlier work—but it will make
the payment in the less-visible (but still very real) form of the up-front charge for including the
warranty, and that charge might be more than what it would have cost the government, under a
contract without a warranty, to pay later on for fixing those problems.
From a cost standpoint, including a warranty in the contract might or might not be preferable,
depending on the risk that there will be problems with earlier work that need fixing, the potential
cost of fixing such problems, and the cost of including the warranty in the contract. The point is
that the goal of avoiding highly visible payments for fixing problems with earlier work and the
goal of minimizing the cost to the government of fixing problems with earlier work are separate
and different goals, and that pursuing the first goal can sometimes work against achieving the
second goal.75

74 See Government Accountability Office, Navy Shipbuilding[:] Past Performance Provides Valuable Lessons for
Future Investments
, GAO-18-238SP, June 2018, p. 21. A graphic on page 21 shows a GAO finding that the
government was financially responsible for shipbuilder deficiencies in 96% of the cases examined by GAO, and that
the shipbuilder was financially responsible for shipbuilder deficiencies in 4% of the cases.
75 It can also be noted that the country’s two largest builders of Navy ships—General Dynamics (GD) and Huntington
Ingalls Industries (HII)—derive about 60% and 96%, respectively, of their revenues from U.S. government work. (See
General Dynamics, 2016 Annual Report, page 9 of Form 10-K [PDF page 15 of 88]) and Huntington Ingalls Industries,
Congressional Research Service

78

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The Department of Defense’s guide on the use of warranties states the following:
Federal Acquisition Regulation (FAR) 46.7 states that “the use of warranties is not
mandatory.” However, if the benefits to be derived from the warranty are commensurate
with the cost of the warranty, the CO [contracting officer] should consider placing it in the
contract. In determining whether a warranty is appropriate for a specific acquisition, FAR
Subpart 46.703 requires the CO to consider the nature and use of the supplies and services,
the cost, the administration and enforcement, trade practices, and reduced requirements.
The rationale for using a warranty should be documented in the contract file....
In determining the value of a warranty, a CBA [cost-benefit analysis] is used to measure
the life cycle costs of the system with and without the warranty. A CBA is required to
determine if the warranty will be cost beneficial. CBA is an economic analysis, which
basically compares the Life Cycle Costs (LCC) of the system with and without the warranty
to determine if warranty coverage will improve the LCCs. In general, five key factors will
drive the results of the CBA: cost of the warranty + cost of warranty administration +
compatibility with total program efforts + cost of overlap with Contractor support +
intangible
savings.
Effective
warranties
integrate
reliability,
maintainability,
supportability, availability, and life-cycle costs. Decision factors that must be evaluated
include the state of the weapon system technology, the size of the warranted population,
the likelihood that field performance requirements can be achieved, and the warranty
period of performance.76

2016 Annual Report, page 5 of Form 10-K [PDF page 19 of 134]). These two shipbuilders operate the only U.S.
shipyards currently capable of building several major types of Navy ships, including submarines, aircraft carriers, large
surface combatants, and amphibious ships. Thus, even if a warranty in a shipbuilding contract with one of these firms
were to somehow mean that the government did not have pay under the terms of that contract—either up front or later
on—for fixing problems with earlier work done under that contract, there would still be a question as to whether the
government would nevertheless wind up eventually paying much of that cost as part of the price of one or more future
contracts the government may have that firm.
76 Department of Defense, Department of Defense Warranty Guide, Version 1.0, September 2009, accessed July 13,
2017, at https://www.acq.osd.mil/dpap/pdi/uid/docs/departmentofdefensewarrantyguide[1].doc.
Congressional Research Service

79

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix G. Avoiding Procurement Cost Growth
vs. Minimizing Procurement Costs
This appendix presents some considerations relating to avoiding procurement cost growth vs.
minimizing procurement costs in shipbuilding and other defense acquisition.
The affordability challenge posed by the Navy’s shipbuilding plans can reinforce the strong
oversight focus on preventing or minimizing procurement cost growth in Navy shipbuilding
programs, which is one expression of a strong oversight focus on preventing or minimizing cost
growth in DOD acquisition programs in general. This oversight focus may reflect in part an
assumption that avoiding or minimizing procurement cost growth is always synonymous with
minimizing procurement cost. It is important to note, however, that as paradoxical as it may seem,
avoiding or minimizing procurement cost growth is not always synonymous with minimizing
procurement cost, and that a sustained, singular focus on avoiding or minimizing procurement
cost growth might sometimes lead to higher procurement costs for the government.
How could this be? Consider the example of a design for the lead ship of a new class of Navy
ships. The construction cost of this new design is uncertain, but is estimated to be likely
somewhere between Point A (a minimum possible figure) and Point D (a maximum possible
figure). (Point D, in other words, would represent a cost estimate with a 100% confidence factor,
meaning there is a 100% chance that the cost would come in at or below that level.) If the Navy
wanted to avoid cost growth on this ship, it could simply set the ship’s procurement cost at Point
D. Industry would likely be happy with this arrangement, and there likely would be no cost
growth on the ship.
The alternative strategy open to the Navy is to set the ship’s target procurement cost at some
figure between Points A and D—call it Point B—and then use that more challenging target cost to
place pressure on industry to sharpen its pencils so as to find ways to produce the ship at that
lower cost. (Navy officials sometimes refer to this as “pressurizing” industry.) In this example, it
might turn out that industry efforts to reduce production costs are not successful enough to build
the ship at the Point B cost. As a result, the ship experiences one or more rounds of procurement
cost growth, and the ship’s procurement cost rises over time from Point B to some higher
figure—call it Point C.
Here is the rub: Point C, in spite of incorporating one or more rounds of cost growth, might
nevertheless turn out to be lower than Point D, because Point C reflected efforts by the
shipbuilder to find ways to reduce production costs that the shipbuilder might have put less
energy into pursuing if the Navy had simply set the ship’s procurement cost initially at Point D.
Setting the ship’s cost at Point D, in other words, may eliminate the risk of cost growth on the
ship, but does so at the expense of creating a risk of the government paying more for the ship than
was actually necessary. DOD could avoid cost growth on new procurement programs starting
tomorrow by simply setting costs for those programs at each program’s equivalent of Point D.
But as a result of this strategy, DOD could well wind up leaving money on the table in some
instances—of not, in other words, minimizing procurement costs.
DOD does not have to set a cost precisely at Point D to create a potential risk in this regard. A risk
of leaving money on the table, for example, is a possible downside of requiring DOD to budget
for its acquisition programs at something like an 80% confidence factor—an approach that some
observers have recommended—because a cost at the 80% confidence factor is a cost that is likely
fairly close to Point D.
Congressional Research Service

80

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Procurement cost growth is often embarrassing for DOD and industry, and can damage their
credibility in connection with future procurement efforts. Procurement cost growth can also
disrupt congressional budgeting by requiring additional appropriations to pay for something
Congress thought it had fully funded in a prior year. For this reason, there is a legitimate public
policy value to pursuing a goal of having less rather than more procurement cost growth.
Procurement cost growth, however, can sometimes be in part the result of DOD efforts to use
lower initial cost targets as a means of pressuring industry to reduce production costs—efforts
that, notwithstanding the cost growth, might be partially successful. A sustained, singular focus
on avoiding or minimizing cost growth, and of punishing DOD for all instances of cost growth,
could discourage DOD from using lower initial cost targets as a means of pressurizing industry,
which could deprive DOD of a tool for controlling procurement costs.
The point here is not to excuse away cost growth, because cost growth can occur in a program for
reasons other than DOD’s attempt to pressurize industry. Nor is the point to abandon the goal of
seeking lower rather than higher procurement cost growth, because, as noted above, there is a
legitimate public policy value in pursuing this goal. The point, rather, is to recognize that this goal
is not always synonymous with minimizing procurement cost, and that a possibility of some
amount of cost growth might be expected as part of an optimal government strategy for
minimizing procurement cost. Recognizing that the goals of seeking lower rather than higher cost
growth and of minimizing procurement cost can sometimes be in tension with one another can
lead to an approach that takes both goals into consideration. In contrast, an approach that is
instead characterized by a sustained, singular focus on avoiding and minimizing cost growth may
appear virtuous, but in the end may wind up costing the government more.
Congressional Research Service

81

link to page 88 link to page 69 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix H. Size of the Navy and Navy
Shipbuilding Rate

Size of the Navy
Table H-1
shows the size of the Navy in terms of total number of ships since FY1948; the
numbers shown in the table reflect changes over time in the rules specifying which ships count
toward the total. Differing counting rules result in differing totals, and for certain years, figures
reflecting more than one set of counting rules are available. Figures in the table for FY1978 and
subsequent years reflect the battle force ships counting method, which is the set of counting rules
established in the early 1980s for public policy discussions of the size of the Navy.
As shown in the table, the total number of battle force ships in the Navy reached a late-Cold War
peak of 568 at the end of FY1987 and began declining thereafter.77 The Navy fell below 300
battle force ships in August 2003 and as of November 1, 2019, included 291 battle force ships.
As discussed in Appendix C, historical figures for total fleet size might not be a reliable
yardstick for assessing the appropriateness of proposals for the future size and structure of the
Navy, particularly if the historical figures are more than a few years old, because the missions to
be performed by the Navy, the mix of ships that make up the Navy, and the technologies that are
available to Navy ships for performing missions all change over time, and because the number of
ships in the fleet in an earlier year might itself have been inappropriate (i.e., not enough or more
than enough) for meeting the Navy’s mission requirements in that year.
For similar reasons, trends over time in the total number of ships in the Navy are not necessarily a
reliable indicator of the direction of change in the fleet’s ability to perform its stated missions. An
increasing number of ships in the fleet might not necessarily mean that the fleet’s ability to
perform its stated missions is increasing, because the fleet’s mission requirements might be
increasing more rapidly than ship numbers and average ship capability. Similarly, a decreasing
number of ships in the fleet might not necessarily mean that the fleet’s ability to perform stated
missions is decreasing, because the fleet’s mission requirements might be declining more rapidly
than numbers of ships, or because average ship capability and the percentage of time that ships
are in deployed locations might be increasing quickly enough to more than offset reductions in
total ship numbers.

77 Some publications have stated that the Navy reached a peak of 594 ships at the end of FY1987. This figure, however,
is the total number of active ships in the fleet, which is not the same as the total number of battle force ships. The battle
force ships figure is the number used in government discussions of the size of the Navy. In recent years, the total
number of active ships has been larger than the total number of battle force ships. For example, the Naval History and
Heritage Command (formerly the Naval Historical Center) states that as of November 16, 2001, the Navy included a
total of 337 active ships, while the Navy states that as of November 19, 2001, the Navy included a total of 317 battle
force ships. Comparing the total number of active ships in one year to the total number of battle force ships in another
year is thus an apples-to-oranges comparison that in this case overstates the decline since FY1987 in the number of
ships in the Navy. As a general rule to avoid potential statistical distortions, comparisons of the number of ships in the
Navy over time should use, whenever possible, a single counting method.
Congressional Research Service

82

link to page 88 link to page 88 link to page 88 link to page 88 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Table H-1. Total Number of Ships in Navy Since FY1948
FYa
Number
FYa
Number
FYa
Number
FYa
Number
1948
737
1970
769
1992
466
2014
289
1949
690
1971
702
1993
435
2015
271
1950
634
1972
654
1994
391
2016
275
1951
980
1973
584
1995
373
2017
279
1952
1,097
1974
512
1996
356
2018
286
1953
1,122
1975
496
1997
354


1954
1,113
1976
476
1998
333


1955
1,030
1977
464
1999
317


1956
973
1978
468
2000
318


1957
967
1979
471
2001
316


1958
890
1980
477
2002
313


1959
860
1981
490
2003
297


1960
812
1982
513
2004
291


1961
897
1983
514
2005
282


1962
959
1984
524
2006
281


1963
916
1985
541
2007
279


1964
917
1986
556
2008
282


1965
936
1987
568
2009
285


1966
947
1988
565
2010
288


1967
973
1989
566
2011
284


1968
976
1990
547
2012
287


1969
926
1991
526
2013
285


Source: Compiled by CRS using U.S. Navy data. Numbers shown reflect changes over time in the rules
specifying which ships count toward the total. Figures for FY1978 and subsequent years reflect the battle force
ships counting method, which is the set of counting rules established in the early 1980s for public policy
discussions of the size of the Navy.
a. Data for earlier years in the table may be for the end of the calendar year (or for some other point during
the year), rather than for the end of the fiscal year.


Congressional Research Service

83

link to page 89 Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Shipbuilding Rate
Table H-2
shows past (FY1982-FY2019) and requested or programmed (FY2020-FY2024) rates
of Navy ship procurement.
Table H-2. Battle Force Ships Procured or Requested, FY1982-FY2024
(Procured in FY1982-FY2019; requested for FY2020, and programmed for FY2021-FY2024)
82 83 84 85 86 87 88 89 90 91 92 93
94 95 96 97 98 99 00
17 14 16 19 20 17 15 19 15 11 11
7
4
4
5
4
5
5
6
01 02 03 04 05 06 07 08 09 10 11 12
13 14 15 16 17 18 19
6
6
5
7
8
4
5
3
8
7
10
11
11
8
8
9
9
9
13
20 21 22 23 24














12 10
9
13 11














Source: CRS compilation based on Navy budget data and examination of defense authorization and
appropriation committee and conference reports for each fiscal year. The table excludes nonbattle force ships
that do not count toward the 355-ship goal, such as certain sealift and prepositioning ships operated by the
Military Sealift Command and oceanographic ships operated by agencies such as the National Oceanic and
Atmospheric Administration (NOAA).
Notes: (1) The totals shown for FY2006, FY2007, and FY2008, reflect the cancellation two LCSs funded
in FY2006, another two LCSs funded in FY2007, and an LCS funded in FY2008.
(2) The total shown for FY2012 includes two JHSVs—one that was included in the Navy’s FY2012 budget
submission, and one that was included in the Army’s FY2012 budget submission. Until FY2012, JHSVs were being
procured by both the Navy and the Army. The Army was to procure its fifth and final JHSV in FY2012, and this
ship was included in the Army’s FY2012 budget submission. In May 2011, the Navy and Army signed a
Memorandum of Agreement (MOA) transferring the Army’s JHSVs to the Navy. In the FY2012 DOD
Appropriations Act (Division A of H.R. 2055/P.L. 112-74 of December 23, 2011), the JHSV that was in the
Army’s FY2012 budget submission was funded through the Shipbuilding and Conversion, Navy (SCN)
appropriation account, along with the JHSV that the Navy had included in its FY0212 budget submission. The
four JHSVs that were procured through the Army’s budget prior to FY2012, however, are not included in the
annual totals shown in this table.
(3) The figures shown for FY2019 and FY2020 reflect a Navy decision to show the aircraft carrier CVN-81
as a ship to be procured in FY2020 rather than a ship that was procured in FY2019. Congress, as part of its
action on the Navy’s proposed FY2019 budget, authorized the procurement of CVN-81 in FY2019.
Congressional Research Service

84

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix I. Potential Impacts of CRs on Navy
Shipbuilding Programs
This appendix provides general background information on the potential impacts of continuing
resolutions (CRs) on Navy shipbuilding programs.
Potential Impacts of CRs on DOD Acquisition Programs, Including
Navy Shipbuilding78

No New Starts, Quantity Increases, or Signing of New MYP Contracts
CRs can lead to challenges in the execution of DOD acquisition programs (i.e., research and
development programs and procurement programs), including Navy shipbuilding programs,
because they typically prohibit the following:
 new program starts (“new starts”), meaning the initiation of new program efforts
that did not exist in the prior year—a prohibition that includes not only the
initiation of new acquisition programs, but also the shifting of an existing
acquisition program from its research and development phase to its procurement
phase;
 an increase in procurement quantity for a program compared to that program’s
procurement quantity in the prior year; and
 the signing of new multiyear procurement (MYP) contracts.79
Larger Contracts Broken into Smaller Contracts
Under a CR, DOD financial managers might dole out funding to DOD acquisition program
managers, including managers of Navy shipbuilding programs, in an incremental, piecemeal
fashion. This can require a program manager to divide an intended single contract into multiple
smaller contracts, which can increase the total cost of the effort by reducing economies of scale
within each of the smaller contracts and increasing Navy and contractor administrative costs.
R&D Efforts That Support Ongoing Procurement Programs
Ongoing DOD procurement programs, including Navy shipbuilding programs, are frequently
supported by ongoing research and development (R&D) work. R&D work on an existing
procurement program can, for example, support the development and integration of new systems
or components intended to improve the end item’s capability, reliability, or maintainability, or
reduce its operation and support (O&S) costs.
Under a CR, R&D funding is managed at the account level, giving service officials some
flexibility in applying available R&D funding so as to protect high-priority R&D efforts,
particularly those that might require more funding in the current fiscal year than they received in
the previous fiscal year. Doing that, however, can reduce funding available under the CR for other

78 For a general discussion of the potential impacts of CRs on DOD, see CRS Report R45870, Defense Spending Under
an Interim Continuing Resolution: In Brief
, coordinated by Pat Towell.
79 For more on MYP contracts, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in
Defense Acquisition: Background and Issues for Congress
, by Ronald O'Rourke and Moshe Schwartz.
Congressional Research Service

85

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

R&D efforts, including those supporting ongoing procurement programs, such as Navy
shipbuilding programs, which can lead to program-execution challenges for those programs.
Additional Potential Impacts of CRs Specific to Navy
Shipbuilding Programs

Line-Item Funding Misalignments
Unlike all other DOD acquisition accounts, the Navy’s shipbuilding account, known formally as
the Shipbuilding and Conversion, Navy (SCN) appropriation account, is funded in the annual
DOD appropriations act not just with a total appropriated amount for the entire account, but also
with specific appropriated amounts at the line-item level. SCN line items in the DOD
appropriations act are not just specific to individual shipbuilding programs—they also distinguish
between procurement funding and advance procurement (AP) funding within those programs.
As a consequence, under a CR, SCN funding is managed not at the account level (like funding is
under a CR for other DOD acquisition accounts), but at the line-item level. For the SCN
account—uniquely among DOD acquisition accounts—this can lead to line-by-line funding
misalignments (excesses and shortfalls) for individual shipbuilding programs, compared to the
amounts those shipbuilding programs received in the prior year. The shortfalls in particular can
lead to program-execution challenges in shipbuilding programs, particularly under an extended or
full-year CR. This unique situation of line-by-line funding misalignments is an important
distinction between the potential impacts of CRs on shipbuilding programs and the potential
impacts of CRs on other DOD acquisition activities.
Cost-to-Complete (CTC) Funding
Cost-to-complete (CTC) funding is funding that the Navy requests as a line item in the SCN
account to cover cost growth on the construction of Navy ships that were funded in prior fiscal
years. The line item is known more formally as the completion of prior-year (PY) shipbuilding
programs line. CTC funding is requested in specific amounts for individual ships that are under
construction. CTC work is considered to be a new start and is therefore typically prohibited under
a CR,80 perhaps on the grounds that CTC work is funded through a line item that is used
exclusively to fund CTC work, and which is therefore separate from the line items that were used
to originally fund the procurement of the ships in question.
The deeming of CTC work as a new start, and therefore prohibited under a CR, could lead to
situations under a CR in which ships under construction sit in shipyards without undergoing work
needed to complete their construction—something that could not only delay the completion of
those ships, but might also increase their total construction costs, because a ship under
construction is charged, for each day that it is in its construction shipyard, some of the fixed
overhead costs of that shipyard.

80 Source: Navy FY2018 program briefing to CRS and CBO, September 20, 2017.
Congressional Research Service

86

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Avoiding or Mitigating Potential Impacts of CRs
Anomalies Can Avoid or Mitigate Potential Impacts
The potential impacts described above can be avoided or mitigated if the CR includes special
provisions, called anomalies, for exempting individual programs or groups of programs from the
general provisions of the CR, or if the CR includes expanded authorities for DOD for
reprogramming and transferring funds.
DOD Has Adapted to Likelihood of CRs to Avoid or Mitigate Impacts
The potential impacts described above can also be mitigated if the agency (in this case, the Navy)
anticipates that one or more CRs will likely be used to fund DOD for the first few months of the
fiscal year, and consequently decides to structure acquisition programs to avoid, during those
months, planned contract signings or other actions that would be prohibited by a CR. The military
services have observed that in many cases in recent years, CRs have been used to fund DOD for
the first few months of the fiscal year. As an apparent adaptation, DOD program managers are
now structuring their programs to reduce the potential impacts of DOD being funded during the
first few months of the fiscal year by CRs.
For example, in connection with the use of a CR to fund the first part of FY2017, a September 29,
2016, press report stated the following:
The Navy has planned for and can mitigate the effects of [a CR], as long as Congress passes
a proper Fiscal Year 2017 budget by Dec. 9, 2016.
The Navy planned for most of its major acquisition milestones to take place in the second
quarter of the fiscal year rather than the first quarter, predicting that the year would likely
start off with a continuing resolution, Navy spokeswoman Lt. Kara Yingling told USNI
News. Under a continuing resolution, the previous year’s funding levels carry over,
meaning that new budget items are not funded and programs expecting a significant
funding boost would continue to operate at the previous year’s lower levels.
“The Navy has many new starts and program increases planned in FY ‘17. However, a CR
through December 9th is manageable because more of the initial contracts are scheduled
in Quarter 2 [of the fiscal year] and the Navy can take mitigating action for the first three
months of FY ’17,” Yingling said today....
Though program managers and Navy acquisition officials often note that stable and
sufficient funding would help them better keep their programs on track, Yingling said the
service would manage the impact of this six-week CR....
“Due to historical CRs, most FY ‘17 contracts are planned for Q2,” Yingling said, and if
the second quarter of the fiscal year is also governed by a CR then the Navy would look at
potentially awarding smaller contracts to get programs started—a contracting burden that
would cost more and potentially slow down programs’ progress.81
As another example, in connection with the use of a CR to fund the first part of FY2018, a
September 11, 2017, press report stated the following:
Pentagon plans to ramp up production of about two-dozen major weapon systems in fiscal
year 2018 would be largely unaffected by the stopgap spending bill President Trump and
congressional leaders hope to enact, funding the federal government from Oct. 1 to Dec. 8.

81 Megan Eckstein, “Navy Can Weather 6-Week Continuing Resolution, But Extension Would Delay Columbia
Submarine Class, Other Programs,” USNI News, September 29, 2016.
Congressional Research Service

87

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Nearly all of the big-ticket programs that aim to increase procurement rates in FY-18
compared to FY-17—including deals for a new aircraft carrier, more armored vehicles,
tank upgrades, precision munitions and aircraft—have set target dates to execute contract
awards after that 10-week window, according to a review of Pentagon budget documents.82
Similarly, an October 6, 2017, press report about the use of a CR to fund the first part of FY2018
stated the following: “The Navy tends to avoid planning contract actions in the first quarter of the
fiscal year, since the last nine years have begun under a continuing resolution.”83
At a September 19, 2017, hearing before the Senate Armed Services Committee on recent Navy
ship collisions, the following exchange occurred (emphasis added):
SENATOR JEANNE SHAHEEN (continuing):
... I wonder if you could talk in detail about the impact of continuing resolutions, budget
cycle after budget cycle, and how they affect maintenance and training plans for ships. And
are forward deployed ships affected more than ships stateside? Can you—is there any
correlation there?
ADMIRAL JOHN M. RICHARDSON, CHIEF OF NAVAL OPERATIONS
Ma’am, as I said, we will prioritize our resources to those forces that are forward deployed
and that will deploy forward. And so we will not leave those teams short of resources.
Having said that, the uncertainty that they can—well actually—it’s become actually
certain. We’re certain that we're not going to get a budget in the first quarter [of the
fiscal year]. And so...

(CROSSTALK)
SHAHEEN:
Which is a sad commentary on the budget situation.
RICHARDSON:
... behaviors have adapted. And so we don't put anything in the important in the first
quarter of the [fiscal] year, and we have to compete three out of four quarters of the
game.

And, in addition to just that fact, the—what happens is you have to double your contracting,
right? You have to write a tiny little contract for the length of the continuing resolution,
and then you have to write another one for the rest of the year. As you know, nothing new
can start, and so we try not to schedule anything new in that first quarter.

The maintenance and training—those are the hardest things. And so, as those—as the
uncertainty, you know, injects itself, it is always—the things on the bubble [i.e., at risk of
being affected] are maintenance periods, particularly surface ship maintenance periods.
It is, you know, "How many steaming hours am I going to get? How many flying hours am
I going to get? $150 million per month shortfall—how do I manage that?" These are the
effects of the continuing resolutions.84
A September 28, 2017, press report states the following:

82 Jason Sherman, “DOD Procurement Plans Largely Safe Under Short-Term FY-18 CR,” Inside the Navy, September
11, 2017.
83 Megan Eckstein, “Top Navy Procurement Programs Facing Slow Start In FY 2018 Due to Continuing Resolution,”
USNI News, October 6, 2017
84 Source: Transcript of hearing.
Congressional Research Service

88

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

The Navy has gotten creative in dealing with budget uncertainties and continuing
resolutions, developing a new ship maintenance contract structure to keep 11 ship
availabilities on track at the beginning of Fiscal Year 2018 that would otherwise face major
delays due to the impending CR, the head of surface ship maintenance told USNI News.
Rear Adm. Jim Downey, commander of Navy Regional Maintenance Centers and deputy
commander for surface warfare at Naval Sea Systems Command (NAVSEA) told USNI
News today that up to a third of the ship maintenance workload can be put at risk when the
fiscal year starts with a CR. This year, the Pentagon has already said 11 ship availabilities
are at risk....
To avoid these delays, Downey said the Navy is now awarding contracts that are structured
differently, to leverage the fact that maintenance work is typically funded with one-year
money—use-it-or-lose-it money which must be spent in the year it is appropriated by
lawmakers—whereas modernization efforts are typically paid for with three-year money.
In essence, the planning and early work for a ship availability can get started as a ship
modernization effort, with planning and early activities paid for with three-year money
already in the Navy’s accounts, and one-year maintenance work can be added in later, once
the availability is already underway and Congress eventually gives the Navy its full-year
appropriations.
“We’ve worked very hard on how we structure our funding to get the planning to keep all
those ships in play, and to keep them in play to their schedule, expecting that the funding
is going to come just in time,” Downey said.
“So we do the planning for them. … And then we go ahead and structure that contract to
deal with the continuing resolution. So the base work now may be more modernization-
related because I have that money, and I’m going to lay the maintenance work in as an
option. So I’m going to award you the contract; I may not be 100-percent funded but I am
funded for this part. I’m going to award the contract to you—we’re currently referring to
it as a split-CLIN approach—so that you’ve got the work and you know that the rest of the
work is coming, you’re going to be able to bid against it, we’re going to exercise those
options if we get the budget approved.”
Downey told USNI News that he can’t change how Congress appropriates money—the
Department of Defense has begun every fiscal year since FY 2010 under a continuing
resolution, during which time the Navy cannot fund new projects and cannot ramp up
spending above the previous year’s levels – but he can best set up the Navy to succeed in
this kind of new normal. Though the Navy has already largely stopped planning acquisition
contract actions during the first quarter of the year, ship maintenance, modernization and
repair work must take place throughout the year to maintain even workloads at the yards
and to address emergent issues, and therefore required a creative solution to get around the
CRs.
“The first issue is, if you don’t have all the money, especially with single-year
appropriations in maintenance, how do you do that? So we’re getting as legally creative as
we can. So then you get a repair yard that says, okay, so I’m betting on this other work.
Then you go to, historically, when have we not had a budget ultimately? It’s going to come
through at some point,” he said.85
Although structuring acquisition programs to avoid, during the first few months of a fiscal year,
planned contract signings or other actions that would be prohibited by CRs can mitigate the
potential impacts of CRs on the execution of DOD acquisition programs, it might also lead to a
risk, from DOD’s perspective, of a creating a so-called “moral hazard”—that is, of taking an
action that might be well-intentioned, but which, as a consequence of adapting to an undesired

85 Megan Eckstein, “Navy Using ‘Legally Creative’ Contract Structure to Keep Ship Availabilities On track Despite
Continuing Resolutions,” USNI News, September 28, 2017.
Congressional Research Service

89

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

behavior by another party (in this case, Congress’s use of CRs to fund DOD at the start of fiscal
years), might encourage more of that behavior from the other party in the future.
Navy Statements
December 2017 Navy Statement About $4 Billion Impact of CRs Since 2011
In a December 4, 2017, speech at a defense symposium, Secretary of the Navy Richard Spencer
stated the following: “Continuing resolutions have cost the Department of the Navy about $4
billion since 2011.”86 Spencer did not state in the speech how that number was calculated. CRS
asked the Navy for the source of the $4 billion figure and for details on how it was calculated. In
response, the Navy provided CRS with an information paper that stated the following in part:
CRs have averaged 106 days per year in the last decade, or 29% of each year. This means
over one quarter of every year is lost or has to be renegotiated for over 100,000 DON
[Department of the Navy] contracts (conservative estimate) and billions of dollars.
Contractors translate this CR uncertainty into the prices they charge the government.
-- The cost factors at work here are: price uncertainty caused by the CR and reflected in
higher rates charged to the government; government time to perform multiple incremental
payments or renegotiate; and contractor time to renegotiate or perform unnecessary re-
work caused by the CR. These efforts are estimated at approximately 1/7th of a man-year
for all stakeholders or $26K [$26,000] per average contract.
-- $26K x 100,000 contracts = $2.6B [$2.6 billion] per year. While the estimate for each
contract would be different, it can readily be seen that this is a low but reasonable
estimate.87
April 2019 Navy Statement About Potential Impacts of CR in FY2020
An April 11, 2019 press report stated the following:
A potential continuing resolution for the next fiscal year would constrain $20.4 billion of
the Navy’s FY-20 budget, according to the service’s acquisition chief.
“That is for FY-20. If we have a CR the entire year, there’s $20.4 billion of effort we are
not going to be able to execute,” Navy Assistant Secretary for Research, Development and
Acquisition Hondo Geurts told the Senate Armed Services seapower subcommittee
yesterday.
Geurts told lawmakers a continuing resolution would limit $9.9 billion in growing
programs. It would also restrict approximately $5.3 billion for increased production rates
and $5.2 billion in new-start programs, he added.88

86 Secretary of the Navy Richard V. Spencer, [address to] USNI [U.S. Naval Institute]—Defense Forum Washington,
Washington, DC, December 4, 2017, remarks as prepared, p. 6.
87 Navy information paper entitled “Characterizing Costs of the Budget Control Act & Continuing Resolution,”
undated, received by CRS from Navy Office of legislative Affairs, December 15, 2017. The information paper also
includes a discussion of how caps on defense spending under the Budget Control Act (BCA) have increased Navy
procurement costs by reducing annual procurement rates for programs such as Navy aircraft procurement programs.
Cost increases of this kind, however, are generally a separate matter from cost impacts due to CRs.
88 Mallory Shelbourne, “Geurts: CR Would Affect $20.4 Billion in FY-20 Navy Budget,” Inside Defense, April 11,
2019.
Congressional Research Service

90

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress

Appendix J. October 30, 2019, Department of Navy
Fact Sheet on FY2020 CR Impacts
This appendix reprints an October 30, 2019, Department of the Navy (DON) two-page fact sheet
on CR impacts on FY2020 DON programs.
Congressional Research Service

91


Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress


Congressional Research Service

92


Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress


Congressional Research Service

93

Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress




Author Information

Ronald O'Rourke

Specialist in Naval Affairs


Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.