The Navy began procuring a small surface combatant called the Littoral Combat Ship (LCS) in
FY2005, and a total of 35 LCSs have been procured through FY2019, including three in FY2019.
The total of 35 LCSs is three more than the 32 the Navy says are required under its 355-ship
force-level goal. The Navy wants FY2019 to be the final year of LCS procurement, and it has not
requested the procurement of any additional LCSs in its FY2020 budget submission.
The Navy wants to shift procurement of small surface combatants in FY2020 to a new frigate
called the FFG(X). The Navy’s proposed FY2020 budget requests funding for the procurement of
the first FFG(X). Five industry teams are currently competing for the FFG(X) program. Two of
these teams are offering designs for the FFG(X) that are modified versions of the two LCS
designs that the Navy has procured in prior years. The other three industry teams are offering
designs for the FFG(X) that are based on other existing ship designs. One of these three other
industry teams is proposing to build its design at one of the LCS shipyards. The Navy plans to
announce the outcome of the FFG(X) competition in the fourth quarter of FY2020. The FFG(X)
program is covered in detail in another CRS report.
The Navy’s 355-ship force-level goal is the result of a Force Structure Analysis (FSA) that the
Navy conducted in 2016. The 2016 FSA established a force-level goal for a 355-ship Navy with
52 small surface combatants, including 32 LCSs and 20 frigates. The Navy conducts a new or
updated FSA every few years, and is currently conducting a new FSA that is scheduled to be
completed by the end of 2019. Navy officials have stated that this new FSA will likely not reduce
the required number of small surface combatants, and might increase it. Navy officials have also
suggested that the Navy in coming years may shift to a new fleet architecture that will include,
among other thing, a larger proportion of small surface combatants.
The LCS is a relatively inexpensive surface combatant equipped with modular mission packages.
The LCS program includes two very different LCS designs. One, called the LCS-1 or Freedom-
class design, was developed by an industry team led by Lockheed. The other, called the LCS-2 or
Independence-class design, was developed by an industry team that was then led by General
Dynamics. LCS procurement has been divided more or less evenly between the two designs. The
LCS-1 design is built at the Marinette Marine shipyard at Marinette, WI, with Lockheed as the
prime contractor. The LCS-2 design is built at the Austal USA shipyard at Mobile, AL, with
Austal USA as the prime contractor.
The LCS program has been controversial over the years due to past cost growth, design and
construction issues with the first LCSs, concerns over the survivability of LCSs (i.e., their ability
to withstand battle damage), concerns over whether LCSs are sufficiently armed and would be
able to perform their stated missions effectively, and concerns over the development and testing
of the modular mission packages for LCSs. The Navy’s execution of the program has been a
matter of congressional oversight attention for several years.
A current issue for Congress is whether to procure any LCSs in FY2020, and if so, how many.
Opponents could argue that the total number of LCSs procured in prior years exceeds the Navy’s
stated requirement, and that adding funding to the Navy’s FY2020 shipbuilding account for
procuring one or more additional LCSs could reduce FY2020 funding for other Navy programs.
Supporters could argue that procuring additional LCSs in FY2020 could provide a hedge against
delays in the FFG(X) program and help the Navy achieve its small surface combatant force-level
goal more quickly. Another issue for Congress concerns future workloads and employment levels
at the two LCS shipyards if one or both of these yards are not involved in building FFG(X)s.
Congressional Research Service

link to page 5 link to page 5 link to page 5 link to page 5 link to page 5 link to page 6 link to page 6 link to page 7 link to page 7 link to page 8 link to page 9 link to page 9 link to page 10 link to page 10 link to page 10 link to page 10 link to page 10 link to page 12 link to page 13 link to page 13 link to page 13 link to page 14 link to page 14 link to page 16 link to page 16 link to page 8 link to page 7 link to page 14 link to page 18 link to page 20 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Contents
Introduction ..................................................................................................................................... 1
Background ..................................................................................................................................... 1

Navy’s Force of Small Surface Combatants (SSCs) ................................................................. 1
SSC Definition .................................................................................................................... 1
SSC Force Levels ................................................................................................................ 1

LCS Program ............................................................................................................................. 2
Overview ............................................................................................................................. 2
Annual Procurement Quantities .......................................................................................... 3
Two Designs Built by Two Shipyards ................................................................................. 3
Two Block Buy Contracts for Ships 5-26 ........................................................................... 4
Modular Mission Packages ................................................................................................. 5
Manning and Deployment ................................................................................................... 5
Potential Foreign Sales ....................................................................................................... 6
FY2020 Funding Request ................................................................................................... 6

Issues for Congress for FY2020 ...................................................................................................... 6
Procurement of LCSs in FY2020 .............................................................................................. 6
Future Workloads and Employment Levels at the Two LCS Shipyards ................................... 6
Navy Plans for Retrofitting LCSs with Additional Weapons .................................................... 8
Survivability, Lethality, Technical Risk, and Test and Evaluation Issues ................................. 9
Legislative Activity for FY2020 ...................................................................................................... 9
Summary of Congressional Action on FY2020 Funding Request ............................................ 9
FY2020 National Defense Authorization Act (S. 1790).......................................................... 10
Senate ................................................................................................................................ 10
FY2020 DOD Appropriations Act (H.R. 2968) ...................................................................... 12
House ................................................................................................................................ 12

Figures
Figure 1. Lockheed Design (Top) and General Dynamics Design (Bottom) .................................. 4

Tables
Table 1. Annual LCS Procurement Quantities ................................................................................. 3
Table 2. Congressional Action on FY2020 Procurement Funding Request .................................. 10

Appendixes
Appendix A. Manning and Deployment of LCSs.......................................................................... 14
Appendix B. Defense-Acquisition Policy Lessons........................................................................ 16

Congressional Research Service

link to page 21 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Contacts
Author Information ........................................................................................................................ 17

Congressional Research Service

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Introduction
This report provides background information and issues for Congress on the Navy’s Littoral
Combat Ship (LCS) program. A total of 35 LCSs have been procured through FY2019. The Navy
wants FY2019 to be the final year of LCS procurement, and it has not requested the procurement
of any additional LCSs in its FY2020 budget submission.
The Navy wants to shift procurement of small surface combatants in FY2020 from the LCS to a
new frigate called the FFG(X). The Navy’s proposed FY2020 budget requests funding for the
procurement of the first FFG(X). The FFG(X) program is covered in detail in CRS Report
R44972, Navy Frigate (FFG[X]) Program: Background and Issues for Congress, by Ronald
O'Rourke.
A current issue for Congress regarding the LCS program is whether to procure any additional
LCSs in FY2020, and if so, how many. Another issue for Congress concerns future workloads and
employment levels at the two LCS shipyards if one or both of these yards are not involved in
building FFG(X)s. Congress’s decisions on the LCS program will affect Navy capabilities and
funding requirements, and the shipbuilding industrial base.
For an overview of the strategic and budgetary context in which the LCS program and other Navy
shipbuilding programs may be considered, see CRS Report RL32665, Navy Force Structure and
Shipbuilding Plans: Background and Issues for Congress
, by Ronald O'Rourke.1
Background
Navy’s Force of Small Surface Combatants (SSCs)
SSC Definition
In discussing its force-level goals and 30-year shipbuilding plans, the Navy organizes its surface
combatants into large surface combatants (LSCs), meaning the Navy’s cruisers and destroyers,
and small surface combatants (SSCs), meaning the Navy’s frigates, LCSs, mine warfare ships,
and patrol craft.2 SSCs are smaller, less capable in some respects, and individually less expensive
to procure, operate, and support than LSCs. SSCs can operate in conjunction with LSCs and other
Navy ships, particularly in higher-threat operating environments, or independently, particularly in
lower-threat operating environments.
SSC Force Levels
In December 2016, the Navy released a goal to achieve and maintain a Navy of 355 ships,
including 52 SSCs, of which 32 are to be LCSs and 20 are to be FFG(X)s. Although patrol craft
are SSCs, they do not count toward the 52-ship SSC force-level goal, because patrol craft are not

1 See also CRS Report R43838, A Shift in the International Security Environment: Potential Implications for Defense—
Issues for Congress
, by Ronald O'Rourke, and CRS Report R44891, U.S. Role in the World: Background and Issues for
Congress
, by Ronald O'Rourke and Michael Moodie.
2 See, for example, CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for
Congress
, by Ronald O'Rourke.
Congressional Research Service

1

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

considered battle force ships, which are the kind of ships that count toward the quoted size of the
Navy and the Navy’s force-level goal.3
At the end of FY2018, the Navy’s force of SSCs totaled 27 battle force ships, including 0 frigates,
16 LCSs, and 11 mine warfare ships. Under the Navy’s FY2020 30-year (FY2020-FY2049)
shipbuilding plan, the SSC force is to grow to 52 ships (34 LCSs and 18 FFG[X]s) in FY2034,
reach a peak of 62 ships (30 LCSs, 20 FFG[X]s, and 12 SSCs of a future design) in FY2040, and
then decline to 50 ships (20 FFG[X]s and 30 SSCs of a future design) in FY2049.
LCS Program
Overview
The LCS is a relatively inexpensive Navy surface combatant that is to be equipped with modular
“plug-and-fight” mission packages, including unmanned vehicles (UVs).4 The Navy announced
the start of the LCS program on November 1, 2001.5 The first LCS was procured in FY2005, and
a total of 35 have been procured through FY2018, including three in FY2019. As noted above, of
the 35 that have been procured through FY2019, 16 had entered service as of the end of FY2018.
The LCS was designed to operate in contested littoral waters in conjunction with other Navy
forces. The LCS’s primary missions are antisubmarine warfare (ASW), mine countermeasures
(MCM), and surface warfare (SUW) against small boats (including so-called “swarm boats”),
particularly in littoral (i.e., near-shore) waters.6 The LCS program includes the development and
procurement of ASW, MCM, and SUW modular mission packages. Additional potential missions
for LCSs include peacetime engagement and partnership-building operations; intelligence,
surveillance, and reconnaissance (ISR) operations; maritime security and intercept operations
(including anti-piracy operations); support of Marines or special operations forces; and homeland
defense operations. An LCS might perform these missions at any time, regardless of its installed

3 For additional discussion of battle force ships, see CRS Report RL32665, Navy Force Structure and Shipbuilding
Plans: Background and Issues for Congress
, by Ronald O'Rourke.
4 Rather than being a fully multimission ship like the Navy’s larger surface combatants, the LCS is to be a focused-
mission ship, meaning a ship equipped to perform one primary mission at any given time. The ship’s primary mission
orientation can be changed by changing out its mission package, although under the Navy’s latest plans for operating
LCSs, that might not happen very frequently, or at all, for a given LCS.
The LCS displaces about 3,000 tons, making it about the size of a corvette (i.e., a light frigate) or a Coast Guard cutter.
It has a maximum speed of more than 40 knots, compared to something more than 30 knots for the Navy cruisers and
destroyers. The LCS has a shallower draft than Navy cruisers and destroyers, permitting it to operate in certain coastal
waters and visit certain shallow-draft ports that are not accessible to Navy cruisers and destroyers.
5 On November 1, 2001, the Navy stated that it was replacing a destroyer-development effort called the DD-21
program, which the Navy had initiated in the mid-1990s, with a new Future Surface Combatant Program aimed at
developing and acquiring a family of three new classes of surface combatants
a destroyer called DD(X) for the precision long-range strike and naval gunfire mission;
a cruiser called CG(X) for the air defense and ballistic missile mission; and
a smaller combatant called the Littoral Combat Ship (LCS) to counter submarines, small surface
attack craft, and mines in heavily contested littoral (near-shore) areas.
For more on the DD(X) program, which was subsequently renamed the DDG-1000 program, see CRS Report
RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress, by Ronald
O'Rourke. For more on the CG(X) program, which was subsequently terminated, see CRS Report RL34179, Navy
CG(X) Cruiser Program: Background for Congress
, by Ronald O'Rourke.
6 These three primary missions appear oriented toward countering, among other things, some of the littoral anti-
access/area-denial (A2/AD) capabilities that have been fielded in recent years by Iran, although they could also be used
to counter similar A2/AD capabilities that might be fielded by other countries.
Congressional Research Service

2

link to page 7 link to page 8 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

mission package, although an installed mission package might enhance an LCS’s ability to
perform some of these missions.
The LCS program has been controversial over the years due to past cost growth, design and
construction issues with the first LCSs, concerns over the survivability of LCSs (i.e., their ability
to withstand battle damage), concerns over whether LCSs are sufficiently armed and would be
able to perform their stated missions effectively, and concerns over the development and testing
of the modular mission packages for LCSs. The LCS program has been modified or restructured
several times over the years, in part to address these issues. The Navy’s execution of the program
has been a matter of congressional oversight attention for several years, particularly for a period
of about 10 years starting around 2007, when significant cost growth in the program came to
light.
Annual Procurement Quantities
Table 1 shows past annual procurement quantities for LCSs. The Navy wants FY2019 to be the
final year of LCS procurement, and it has not requested the procurement of any additional LCSs
in its FY2020 budget submission.
Table 1. Annual LCS Procurement Quantities
FY05
FY06
FY07
FY08
FY09
FY10
FY11
FY12
FY13
FY14
1
1
0
0
2
2
2
4
4
4
FY15
FY16
FY17
FY18
FY19
FY20
FY21
FY22
FY23
FY24
3
3
3
3
3
0
0
0
0
0
Source: Prepared by CRS based on FY2020 and prior-year Navy budget submissions.
Notes: The two ships shown in FY2005 and FY2006 were funded through Navy’s research and development
account rather than the Navy’s shipbuilding account. Figures for FY2006-FY2008 do not include five LCSs (two in
FY2006, two in FY2007, and one in FY2008) that were funded in those years but later canceled by the Navy.
Two Designs Built by Two Shipyards
The LCS program includes two very different LCS designs (see Figure 1). One, called the LCS-1
or Freedom-class design, was developed by an industry team led by Lockheed. The other, called
the LCS-2 or Independence-class design, was developed by an industry team that was then led by
General Dynamics. The LCS-1 design is based on a steel semi-planing monohull (with an
aluminum superstructure), while the LCS-2 design is based on an all-aluminum trimaran hull.
The two LCS designs also use different built-in combat systems (i.e., different collections of
built-in sensors, computers, software, and tactical displays) that were designed by each industry
team. The Navy states that both LCS designs meet the Key Performance Parameters (KPPs) for
the LCS program.
LCS procurement has been divided more or less evenly between the two designs. The LCS-1
design is built at the Fincantieri/Marinette Marine shipyard at Marinette, WI,7 with Lockheed as
the prime contractor; these ships are designated LCS-1, LCS-3, LCS-5, and so on. The LCS-2
design is built at the Austal USA shipyard at Mobile, AL, with Austal USA as the prime
contractor;8 these ships are designated LCS-2, LCS-4, LCS-6, and so on.

7 In 2009, Fincantieri Marine Group, an Italian shipbuilding firm, purchased Manitowoc Marine Group, the owner of
Marinette Marine and two other shipyards. Lockheed is a minority investor in Marinette Marine.
8 Austal USA was created in 1999 as a joint venture between Austal Limited of Henderson, Western Australia, and
Bender Shipbuilding & Repair Company of Mobile, AL, with Austal Limited as the majority owner.
Congressional Research Service

3


Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Figure 1. Lockheed Design (Top) and
General Dynamics Design (Bottom)

Source: U.S. Navy file photo accessed by CRS at http://www.navy.mil/list_al .asp?id=57917 on January 6, 2010.
Two Block Buy Contracts for Ships 5-26
Ships 1 through 4 in the program were procured with single-ship contracts. The next 22 ships in
the program (ships 5 through 26) were procured under two 10-ship block buy contracts that the
Navy awarded to the two LCS builders in December 2010, and which were later extended in each
Congressional Research Service

4

link to page 18 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

case to include an 11th ship. The Navy sought and received legislative authority from Congress in
2010 to award these block buy contracts.9
Modular Mission Packages
Current Navy plans call for procuring a total of 44 LCS mission packages (10 ASW, 24 MCM,
and 10 SUW).10 The Navy has not announced whether the figure of 44 mission packages will be
adjusted upward to account for the procurement of a total of 35 rather than 32 LCSs. LCS mission
packages have been under development since the early days of the LCS program. The Navy’s
plan is to develop and deploy initial versions of these packages, followed by development and
procurement of more capable versions. The development, testing, and certification of LCS
mission packages has been a significant and continuing oversight issue for Congress for the LCS
program. The Navy states that
The Navy achieved Initial Operating Capability (IOC) of the final component of the SUW
Mission Package (MP), the Surface to Surface Missile module. The Navy worked with the
Director, Operational Test and Evaluation to improve the test design, employ best
practices, and make data driven decisions. The team jointly delivered a fully compliant test
outcome, while simultaneously reducing the number of developmental test and operational
test raid events. As a result, the Department reduced costs while completing operational
tests of the SUW MP two months early. The ASW Mission Package Pre-Production Test
Article was delivered in November 2018 and ASW MP conducted end-to-end testing at the
Navy's Atlantic Undersea Test and Evaluation Center in January 2019. All of the MCM
Mission Package aviation systems have reached IOC and are being delivered to the Fleet.
The modular nature of the Mission Packages enables the Navy to deliver these capabilities
now, while continuing to mature the remainder of the systems. Additionally, the Navy
continues to evaluate employment of the MCM Mission Package off of Vessels of
Opportunity.11
Manning and Deployment
The LCS employs automation to achieve a reduced-sized crew. An LCS with an embarked MCM
mission package and an aviation detachment to operate the ship’s embarked aircraft might total
about 88 sailors, compared to more than 200 for a Navy frigate and more than 300 for a Navy
cruiser or destroyer. In general, most LCSs are to be operated with alternating dual crews so as to
increase the percentage of time they can be deployed. For additional information on the manning
and deployment of LCSs, see Appendix A.

9 Congress granted the authority for the block buy contracts in Section 150 of H.R. 3082/P.L. 111-322 of December 22,
2010, an act that, among other things, funded federal government operations through March 4, 2011. For more on block
buy contracts, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense
Acquisition: Background and Issues for Congress
, by Ronald O'Rourke and Moshe Schwartz.
10 U.S. Navy, Report to Congress for the Littoral Combat Ship Mission Modules Program, Annual Report With the
President’s Budget Fiscal Year 2019
, February 8, 2018, with cover letters dated February 12, 2018, posted at USNI
News April 4, 2018, p. 3.
11 Statement of the Honorable James F. Geurts, Assistant Secretary of the Navy for Research, Development and
Acquisition ASN(RD&A) and Vice Admiral William R. Merz, Deputy Chief of Naval Operations for Warfare Systems
(OPNAV N9) and Lieutenant General David H. Berger, Deputy Commandant, Combat Development and Integration &
Commanding General, Marine Corps Combat Development Command, before the Subcommittee on Seapower of the
Senate Armed Services Committee on the Department of the Navy Fiscal Year 2020 Budget Request for Shipbuilding
Programs, March 27, 2019, p. 10.
Congressional Research Service

5

link to page 14 link to page 13 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Potential Foreign Sales
Industry has marketed various modified versions of the LCS to potential foreign buyers. Saudi
Arabia has purchased four modified LCSs.12
FY2020 Funding Request
The Navy wants FY2019 to be the final year of LCS procurement, and it has not requested any
finding for the procurement of additional LCSs in its FY2020 budget submission. The Navy’s
proposed FY2020 does request $14 million in procurement funding to cover cost growth on LCSs
procured in prior fiscal years. And as shown in Table 2 in the “Legislative Activity for FY2020”
section of this report, the Navy’s proposed FY2020 budget requests funding for the procurement
of LCS mission packages. The Navy’s FY2020 budget submission estimates the combined
procurement cost of the three LCSs procured in FY2019 at $1,571.2 million, or an average of
about $523.7 million each.
Issues for Congress for FY2020
Procurement of LCSs in FY2020
One issue for Congress is whether to procure any LCSs in FY2020, and if so, how many. As
noted above, the Navy wants FY2019 to be the final year of LCS procurement, and it has not
requested the procurement of any additional LCSs in its FY2020 budget submission.
Opponents of procuring one or more LCSs in FY2020 could argue that the total number of LCSs
procured in prior years exceeds the Navy’s stated requirement, and that adding funding to the
Navy’s FY2020 shipbuilding account for procuring one or more additional LCSs could reduce
FY2020 funding for other Navy programs. Supporters of procuring one or more LCSs could
argue that it could provide a hedge against delays in the FFG(X) program and help the Navy
achieve its small surface combatant force-level goal more quickly.
Future Workloads and Employment Levels at the Two LCS
Shipyards
Another issue for Congress concerns future workloads and employment levels at the two LCS
shipyards if one or both of these yards are not involved in building FFG(X)s. As noted earlier, the
Navy wants to shift procurement of small surface combatants in FY2020 to a new frigate called
the FFG(X). The Navy’s proposed FY2020 budget requests funding for the procurement of the
first FFG(X). Five industry teams are currently competing for the FFG(X) program. Two of these
teams are offering designs for the FFG(X) that are modified versions of the two LCS designs that
the Navy has procured in prior years. The other three industry teams are offering designs for the
FFG(X) that are based on other existing ship designs. One of these three other industry teams is
proposing to build its design at the LCS-1 shipyard. The Navy plans to announce the outcome of
the FFG(X) competition in the fourth quarter of FY2020. The FFG(X) program is covered in

12 See Paul McLeary, “Saudis Save Wisconsin Shipbuilder: Fills Gap Between LCS & Frigates At Marinette,”
Breaking Defense, January 17, 2019; “Saudi Ships,” Defense Daily, March 12, 2018: 3; Lee Hudson, “Navy Establishes
LCS Program Office to Support Saudi Arabia Buy,” Inside the Navy, December 11, 2017; Sam LaGrone, “Lockheed
Martin Awarded First Contract for New Saudi Frigates,” USNI News, November 30, 2017; Aaron Mehta, “Revealed:
Trump’s $110 Billion Weapons List for the Saudis,” Defense News, June 8, 2017; Anthony Capaccio and Margaret
Talev, “Saudis to Make $6 Billion Deal for Lockheed’s Littoral Ships,” Bloomberg, May 18, 2017.
Congressional Research Service

6

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

detail in CRS Report R44972, Navy Frigate (FFG[X]) Program: Background and Issues for
Congress
, by Ronald O'Rourke.
If a design proposed for construction at one of the LCS shipyards is chosen as the winner of the
FFG(X) competition, then other things held equal (e.g., without the addition of new work other
than building LCSs), workloads and employment levels at the other LCS shipyard (the one not
chosen for the FFG(X) program), as well as supplier firms associated with that other LCS
shipyard, would decline over time as the other LCS shipyard’s backlog of prior-year-funded
LCSs is completed and not replaced with new FFG(X) work. If no design proposed for
construction at an LCS shipyard is chosen as the FFG(X)—that is, if the winner of the FFG(X)
competition is a design to be built at a shipyard other than the two LCS shipyards—then other
things held equal, employment levels at both LCS shipyards and their supplier firms would
decline over time as their backlogs of prior-year-funded LCSs are completed and not replaced
with FFG(X) work.13
The Navy’s current baseline plan for the FFG(X) program is to build FFG(X)s at a single
shipyard. One possible alternative would be to build FFG(X)s at two or three shipyards, including
one or both of the LCS shipyards. One possible approach for doing this, for example, would be to
select a winner in the FFG(X) competition and begin procuring that design in FY2020, as the
Navy currently plans, but also build FFG(X)s at one or both of the LCS yards. Supporters of this
option might argue that it could
 boost FFG(X) production from the currently planned two ships per year to as
many as many as four to six ships per year, substantially accelerating the date for
attaining the Navy’s small surface combatant force-level goal;
 permit the Navy to use competition (either competition for quantity at the margin,
or competition for profit [i.e., Profit Related to Offers, or PRO, bidding])14 to
help restrain FFG(X) prices and ensure production quality and on-time deliveries;
and
 complicate adversary defense planning by presenting potential adversaries with
multiple FFG(X) designs, each with its own specific operating characteristics.
Opponents of this plan might argue that it could
 weaken the FFG(X) competition by offering the winner a smaller prospective
number of FFG(X)s and essentially guaranteeing the LCSs yard that they will
build some number of FFG(X)s;
 substantially increase annual FFG(X) procurement funding requirements so as to
procure as many as four to six FFG(X)s per year rather than two per year, which
in a situation of finite Department of Defense (DOD) funding could require
offsetting reductions in other Navy or DOD programs; and
 reduce production economies of scale in the FFG(X) program by dividing
FFG(X) among two or three designs, and increase downstream Navy FFG(X)
operation and support (O&S) costs by requiring the Navy to maintain two or
three FFG(X) logistics support systems.

13 For additional discussion, see, for example, Roxana Tiron, “Shipyards Locked in ‘Existential’ Duel for Navy’s New
Frigate,” Bloomberg, February 20, 2019; Paul McLeary, “Saudis Save Wisconsin Shipbuilder: Fills Gap Between LCS
& Frigates At Marinette,” Breaking Defense, January 17, 2019.
14 For more on PRO bidding, see Statement of Ronald O’Rourke, Specialist in Naval Affairs, Congressional Research
Service, before the House Armed Services Committee on Case Studies in DOD Acquisition: Finding What Works, June
24, 2014, p. 7.
Congressional Research Service

7

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Another possible alternative to the Navy’s plan to end LCS procurement in FY2019 and shift to
FFG(X) procurement starting in FY2020 would be would be to select a winner in the FFG(X)
competition and begin procuring that design in FY2020, as the Navy currently plans, but shift
Navy shipbuilding work at one of the LCS yards (if the other wins the FFG(X) competition) or at
both of the LCS yards (if neither wins the FFG(X) competition) to the production of sections of
larger Navy ships (such as DDG-51 destroyers or amphibious ships) that undergo final assembly
at other shipyards. Under this option, in other words, one or both of the LCS yards would be
converted into feeder yards supporting the production of larger Navy ships that undergo final
assembly at other shipyards. This option might help maintain workloads and employment levels
at one or both of the LCS yards, and might alleviate capacity constraints at other shipyards,
permitting certain parts of the Navy’s 355-ship force-level objective to be achieved sooner. The
concept of feeder yards in naval shipbuilding was examined at length in a 2011 RAND report.15
Navy Plans for Retrofitting LCSs with Additional Weapons
Another issue for Congress concerns the Navy’s plans for retrofitting LCSs with additional
weapons, so as to give them capabilities more like those of the FFG(X). The Navy states that it
“is beginning to retrofit an Over the Horizon Weapon System (OTH WS) on all LCS for increased
lethality. The award in May 2018 of the Naval Strike Missile contract for OTH WS brings a
technologically mature weapons system and extends the offensive capability of the ship.”16

15 Laurence Smallman et al., Shared Modular Build of Warships, How a Shared Build Can Support Future
Shipbuilding
, RAND, Santa Monica, CA, 2011 (report TR-852), 81 pp. The Navy in recent years has made some use of
the concept

All Virginia-class attack submarines have been produced jointly by General Dynamics’ Electric Boat division
(GD/EB) and Huntington Ingalls Industries’ Newport News Shipbuilding (HII/NNS), with each yard in effect
acting as a feeder yard for Virginia-class boats that undergo final assembly at the other yard.

Certain components of the Navy’s three Zumwalt (DDG-1000) class destroyers were produced by HII’s
Ingalls Shipyard (HII/Ingalls) and then transported to GD’s Bath Iron Works (GD/BIW), the primary builder
and final assembly yard for the ships.

San Antonio (LPD-17) class amphibious ships were built at the Ingalls shipyard at Pascagoula, MS, and the
Avondale shipyard near New Orleans, LA. These shipyards were owned by Northrop and later by HII. To
alleviate capacity constraints at Ingalls and Avondale caused by damage from Hurricane Katrina in 2005,
Northrop subcontracted the construction of portions of LPDs 20 through 24 (i.e., the fourth through eighth
ships in the class) to other shipyards on the Gulf Coast and East Coast, including shipyards not owned by
Northrop.
For more on the Virginia-class joint production arrangement, see CRS Report RL32418, Navy Virginia (SSN-774)
Class Attack Submarine Procurement: Background and Issues for Congress
, by Ronald O'Rourke. Regarding the LPD-
17 program, see Laurence Smallman et al., Shared Modular Build of Warships, How a Shared Build Can Support
Future Shipbuilding, RAND, Santa Monica, CA, 2011 (report TR-852), pp. 45-48. See also David Paganie, “Signal
International positions to capture the Gulf,” Offshore, June 1, 2006; Peter Frost, “Labor Market, Schedule Forces
Outsourcing of Work,” Newport News Daily Press, April 1, 2008; Holbrook Mohr, “Northrop Gets LPD Help From
General Dynamics,” NavyTimes.com, April 1, 2008; and Geoff Fein, “Northrop Grumman Awards Bath Iron Works
Construction Work On LPD-24,” Defense Daily, April 2, 2008.
16 Statement of the Honorable James F. Geurts, Assistant Secretary of the Navy for Research, Development and
Acquisition ASN(RD&A) and Vice Admiral William R. Merz, Deputy Chief of Naval Operations for Warfare Systems
(OPNAV N9) and Lieutenant General David H. Berger, Deputy Commandant, Combat Development and Integration &
Commanding General, Marine Corps Combat Development Command, before the Subcommittee on Seapower of the
Senate Armed Services Committee on the Department of the Navy Fiscal Year 2020 Budget Request for Shipbuilding
Programs, March 27, 2019, p. 10. See also Sam LaGrone, “Shipbuilders Studying Adding More Punch to Littoral
Combat Ships,” USNI News, May 21, 2019.
Congressional Research Service

8

link to page 14 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Survivability, Lethality, Technical Risk, and Test and
Evaluation Issues
A broad oversight area for Congress for the LCS program for the past several years concerns
survivability, lethality, technical risk, and test and evaluation issues relating to LCSs and their
mission packages. Over the years, the annual report from DOD’s Director, Operational Test and
Evaluation (DOT&E) has contained extensive comments, many of them very critical, regarding
numerous aspects of LCSs and LCS mission packages. DOT&E’s January 2018 report for
FY2017 contains such comments.17 Similarly, over the years, GAO has provided numerous
reports and testimony about the LCS program that have raised a variety of issues with the
program.18 GAO also provides a summary assessment of risk in the LCS mission packages in an
annual report it publishes that surveys selected DOD weapon acquisition programs.19 A July 25,
2018, DOD Inspector General (IG) report on LCS MCM mission package systems stated that “the
Navy declared IOC [initial operational capability] for the three MCM mission package systems
reviewed prior to demonstrating that the systems were effective and suitable for their intended
operational uses.”20
Legislative Activity for FY2020
Summary of Congressional Action on FY2020 Funding Request
Table 2
summarizes congressional action on the Navy’s FY2020 procurement funding request for
the LCS program.

17 See Department of Defense, Director, Operational Test & Evaluation, FY 2017 Annual Report, January 2018, pp.
187-191.
18 Recent examples include Government Accountability Office, Littoral Combat Ship and Frigate[:] Slowing Planned
Frigate Acquisition Would Enable Better-Informed Decisions
, GAO-17-279T, December 8, 2016, 22 pp. (Testimony
Before the Subcommittee on Oversight and Investigations, Committee on Armed Services, House of Representatives,
Statement of Michele Mackin, Director, Acquisition and Sourcing Management); Government Accountability Office,
Littoral Combat Ship and Frigate[:] Congress Faced with Critical Acquisition Decisions, GAO-17-262T, December 1,
2016, 18 pp. (Testimony Before the Committee on Armed Services, U.S. Senate, Statement of Paul L. Francis,
Managing Director, Acquisition and Sourcing Management); Government Accountability Office, Littoral Combat
Ship[:] Need to Address Fundamental Weaknesses in LCS and Frigate Acquisition Strategies
, GAO-16-356, June
2016, 56 pp.; Government Accountability Office, Littoral Combat Ship[:] Knowledge of Survivability and Lethality
Capabilities Needed Prior to Making Major Funding Decisions
, GAO-16-201, December 2015, 39 pp.; Government
Accountability Office, Littoral Combat Ship[:] Navy Complied with Regulations in Accepting Two Lead Ships, but
Quality Problems Persisted after Delivery
, GAO-14-827, September 2014, 35 pp.; Government Accountability Office,
Littoral Combat Ship[:] Additional Testing and Improved Weight Management Needed Prior to Further Investments,
GAO-14-749, July 2014, 54 pp.; and Government Accountability Office, Littoral Combat Ship[:] Deployment of USS
Freedom Revealed Risks in Implementing Operational Concepts and Uncertain Costs
, GAO-14-447, July 2014, 57 pp.
19 Government Accountability Office, Weapon Systems Annual Assessment[:] Limited Use of Knowledge-Based
Practices Continues to Undercut DOD’s Investments
, GAO-19-336SP, May 2019, pp. 114.
20 Department of Defense Inspector General, Acquisition of the Navy’s Mine Countermeasures Mission Package,
Report No. DODIG-2018-140, July 25, 2018, p. i. Report originally prepared in FOUO (for official use only) form,
then redacted by DOD and posted at the DOD IG website in redacted form, accessed July 31, 2018, at
http://www.dodig.mil/reports.html/Article/1586520/acquisition-of-the-navys-mine-countermeasures-mission-package/.
See also Rich Abott, “DoD IG: Navy Improperly Declared IOC For 3 LCS MCM Systems,” Defense Daily, July 31,
2018: 7-8.
Congressional Research Service

9

link to page 14 link to page 14 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Table 2. Congressional Action on FY2020 Procurement Funding Request
Figures in millions, rounded to nearest tenth
Authorization
Appropriation

Request
HASC
SASC
Conf.
HAC
SAC
Conf.
Shipbuilding and Conversion, Navy (SCN) appropriation account
Procurement of additional LCSs
0

0

0


(Procurement quantity)
(0)

(0)

(0)


Other Procurement, Navy (OPN) appropriation account
Line 29: LCS common mission modules equipment
51.6

51.6

38.7


Line 30: LCS MCM mission modules
197.1

67.3

163.6


Line 31: LCS ASW mission modules
27.8

27.8

24.6


Line 32: LCS SUW mission modules
26.6

26.6

14.6


Line 33: LCS in-service modernization
85.0

85.0

85.7


Source: Table prepared by CRS based on FY2020 Navy budget submission, committee and conference reports,
and explanatory statements on the FY2020 National Defense Authorization Act and the FY2020 DOD
Appropriations Act.
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is
House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference agreement.
FY2020 National Defense Authorization Act (S. 1790)
Senate
The Senate Armed Services Committee, in its report (S.Rept. 116-48 of June 11, 2019) on S.
1790, recommended the funding levels shown in the SASC column of Table 2. The
recommended reduction of $129.8 million in line 30 is for “Procurement ahead of satisfactory
testing.” (Page 435) S.Rept. 116-48 further states:
Littoral Combat Ship mine countermeasures mission modules
The budget request included $197.1 million in line number 30 of Other Procurement, Navy
(OPN), for the procurement of Littoral Combat Ship mine countermeasures mission
module equipment.
The committee notes that the Navy is requesting funding to purchase equipment that has
not yet undergone operational testing, which is an approach that, as the Government
Accountability Office has shown, leads to cost growth and schedule delays. The committee
believes that the following requested systems would constitute excessive procurement
ahead of satisfactory testing: 6 unmanned surface vehicle and minesweeping payload
delivery systems, 4 minehunting payload delivery systems (new), 3 minehunting payload
delivery systems (backfit), and 2 buried minehunting modules, including support
equipment.
Therefore, the committee recommends a decrease of $129.8 million in line number 30 of
OPN. (Page 26)
Regarding an LCS-related weapons-procurement funding line item that is not shown in Table 2,
S.Rept. 116-48 states:
LCS Over-the-Horizon missile
The budget request included no funding in line number 19 of Weapons Procurement, Navy
(WPN), for the Littoral Combat Ship (LCS) Over-the-Horizon (OTH) Missile.
Congressional Research Service

10

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

The committee notes that the OTH missile acquisition strategy is accelerated and contains
unnecessary risk.
Therefore, the committee recommends a decrease of $20.0 million in line number 19 of
WPN for the LCS OTH Missile. (Page 20)
Regarding a research and development funding line item that is not shown in Table 2, S.Rept.
116-48 states:
Littoral Combat Ship mission modules
The budget request included $20.3 billion in Research, Development, Test, and Evaluation
(RDT&E), Navy, of which $108.5 million was for PE 63596N Littoral Combat Ship (LCS)
mission modules.
The committee notes that an operational testing period of the surface warfare mission
package was delayed from fiscal year 2018 to fiscal year 2019.
Accordingly, the committee recommends a decrease of $5.0 million, for a total of $103.5
million, in RDT&E, Navy, for PE 63596N for LCS mission modules. (Pages 82-83)
Section 126 of S. 1790 as reported by the committee states:
SEC. 126. Limitation on availability of funds for the Littoral Combat Ship.
(a) Limitation.—None of the amounts authorized to be appropriated by this Act or
otherwise made available for the Department of Defense for fiscal year 2020 may be used
to exceed the total procurement quantity listed in revision five of the Littoral Combat Ship
acquisition strategy unless the Under Secretary of Defense for Acquisition and Sustainment
submits to the congressional defense committees the certification described in subsection
(b).
(b) Certification.—The certification described in this subsection is a certification by the
Under Secretary that awarding a contract for the procurement of a Littoral Combat Ship
that exceeds the total procurement quantity listed in revision five of the Littoral Combat
Ship acquisition strategy—
(1) is in the national security interests of the United States;
(2) will not result in exceeding the low-rate initial production quantity approved in the
Littoral Combat Ship acquisition strategy in effect as of the date of the certification; and
(3) is necessary to maintain a full and open competition for the Guided Missile Frigate
(FFG(X)) with a single source award in fiscal year 2020.
(c) Definition.—The term “revision five of the Littoral Combat Ship acquisition strategy”
means the fifth revision of the Littoral Combat Ship acquisition strategy approved by the
Under Secretary of Defense for Acquisition and Sustainment on March 26, 2018.
Regarding Section 126, S.Rept. 116-48 states:
Limitation on availability of funds for the Littoral Combat Ship (sec. 126)
The committee recommends a provision that would prohibit funds from being used to
exceed the total procurement quantity listed in revision five of the Littoral Combat Ship
(LCS) acquisition strategy unless the Under Secretary of Defense for Acquisition and
Sustainment submits to the congressional defense committees a certification.
The committee notes that the Navy force structure assessment requirement and LCS
acquisition strategy total procurement quantity of 32 LCSs was met in fiscal year 2018.
Three additional LCSs were authorized and appropriated by the Congress in fiscal year
2019.
Congressional Research Service

11

link to page 14 Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Accordingly, the provision would require that, before further LCS procurement, the Under
Secretary of Defense for Acquisition and Sustainment certify to the congressional defense
committees that such procurement: (1) Is in the national security interests of the United
States; (2) Will not result in exceeding the low rate initial production quantity approved in
the LCS acquisition strategy in effect at the time of the certification; and (3) Is necessary
to maintain a full and open competition for the guided missile frigate (FFG(X)) with a
single source award in fiscal year 2020. (Pages 9-10)
Section 1018 of S. 1790 as reported by the committee states:
SEC. 1018. Permanent authority for sustaining operational readiness of Littoral Combat
Ships on extended deployment.
Section 8680(a)(2) of title 10, United States Code, is amended by striking subparagraph
(D).
Regarding Section 1018, S.Rept. 116-48 states:
Permanent authority for sustaining operational readiness of Littoral Combat Ships
on extended deployment (sec. 1018)

The committee recommends a provision that would amend section 8680 of title 10, United
States Code, to provide the Secretary of the Navy with additional flexibility to maintain
Littoral Combat Ships (LCS) by allowing government or contractor personnel to conduct
maintenance on deployed LCS vessels regardless of ship location.
This provision would codify the authorities successfully employed in a pilot program
authorized by section 1025 of the Carl Levin and Howard P. "Buck" McKeon National
Defense Authorization Act for Fiscal Year 2015 (P.L. 113-291).
The pilot program was conducted to evaluate maintenance options for LCS vessels on
extended deployments from December 2014 to September 2016. The Navy's assessment
of the pilot program, which was submitted in a March 2017 report to the Congress, stated,
"Based on the pilot program results, cost savings are expected to be notable. Even more
importantly, the flexibility to provide timely maintenance in support of schedule changes
and mission execution is crucial to long-term success of the LCS Fleet[.]"
The committee concurs with the Navy's assessment of the pilot program and recommends
codifying the associated authorities in title 10, United States Code. (Pages 240-241)
FY2020 DOD Appropriations Act (H.R. 2968)
House
The House Appropriations Committee, in its report (H.Rept. 116-84 of May 23, 2019) on H.R.
2968, recommended the funding levels shown in the HAC column of Table 2.
The recommended reduction of $12.823 million for line 29 is for “CMPT MPTS tech
modernization unjustified growth” ($1.931 million), “EMM/ANSQS-62 [sonar] training
equipment unjustified request” ($3.692 million), and “Mission bay training devices—ASW
unjustified request” ($7.2 million). (Page 185)
The recommended reduction of $33.494 million for line 30 is for “Unmanned minesweeping
module unit cost growth” ($3.334 million), “Knifefish [unmanned underwater vehicle] unit cost
growth” ($1.8 million), and “AN/AQS-20C [sonar] early to need ($28.36 million). (Page 185)
The recommended reduction of $3.137 million for line 31 is for “Variable depth sonar unit cost
growth.” (Page 185)
Congressional Research Service

12

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

The recommended reduction of $11.968 million for line 32 is for “Surface-to-surface missile
module excess to need.” (Page 185)
The recommended net increase of $0.742 million for line 33 includes a reduction for
“Habitability mod (Freedom variant) unit cost growth” ($2.972 million), a reduction for “LCS
modernization (Independence variant) installation cost growth” ($3.286 million), and an increase
for “Program increase—modernization of combat and communication systems and installation
acceleration” ($7.0 million). (Page 185)
H.Rept. 116-84 also states:
LETHALITY AND SURVIVABILITY OF LITTORAL COMBAT SHIPS
The Committee supports Navy efforts to increase both the lethality and the survivability of
Littoral Combat Ships but is concerned by the slow pace of improvements. The Committee
directs the Secretary of the Navy to submit a report to the congressional defense
committees not later than 90 days after the enactment of this Act on the specific lethality
and survivability upgrades to be incorporated on Littoral Combat Ships, the timeline of
installation of the upgrades, and any resources required. (Page 264)

Congressional Research Service

13

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Appendix A. Manning and Deployment of LCSs
This appendix provides additional background information on the manning and deployment of
LCSs.
The Navy originally planned to maintain three crews for each two LCSs, and to keep one of those
two LCSs forward deployed—an approach Navy officials referred to as the 3-2-1 plan. Under this
plan, LCSs were to be deployed at forward station (such as Singapore) for 16 months at a time,
and crews were to rotate on and off deployed ships at 4- to 6-month intervals. The 3-2-1 plan was
intended to permit the Navy to maintain 50% of the LCS force in deployed status at any given
time—a greater percentage than would be possible under the traditional approach of maintaining
one crew for each LCS and deploying LCSs for seven months at a time. The Navy planned to
forward-station three LCSs in Singapore and additional LCSs at another Western Pacific location,
such as Sasebo, Japan, and at Bahrain.
In September 2016, the Navy announced a new plan for crewing and operating the first 28 LCSs.
Key elements of the new plan include the following:
 the first four LCSs (LCSs 1 through 4) will each by operated by a single crew
and be dedicated to testing and evaluating LCS mission packages (though they
could be deployed as fleet assets if needed on a limited basis);
 the other 24 LCSs (LCSs 5 through 28) will be divided into six divisions (i.e.,
groups) of four ships each;
 three of the divisions (i.e., 12 of the 24 ships), all of them built to the LCS-1
design, will be homeported at Mayport, FL;
 the other three divisions (i.e., the remaining 12 ships), all of them built to the
LCS-2 design, will be homeported at San Diego, CA;
 among the three divisions on each coast, one division will focus on MCM, one
will focus on ASW, and one will focus on SUW;
 in each of the six divisions, one ship will be a designated training ship, and will
focus on training and certifying the crews of the other three ships in the division;
 the other three ships in each division will each be operated by dual crews (i.e.,
Blue and Gold crews), like the Navy’s ballistic missile submarines;
 the crews for the 24 ships in the six divisions will be permanently fused with
their associated mission package crews—the distinction between core crew and
mission package crew will be eliminated;
 the 24 ships in the six divisions will experience changes in their mission
packages (and thus in their mission orientations) infrequently, if at all; and
 at program maturity (i.e., by about FY2023), 13 of the 24 ships in the six
divisions (i.e., more than 50%) are to be forward stationed at any given point for
periods of 24 months, with 3 at Singapore, 3 at another Western Pacific location,
such as Sasebo, Japan, and 7 at Bahrain.21

21 Source: Navy briefing on new LCS crewing and operating plan given to CRS and CBO on September 26, 2016, and
Navy information paper dated May 31, 2018, provided by Navy Office of Legislative Affairs to CRS on June 1, 2018.
See also “Navy Adjusts LCS Class Crewing, Readiness and Employment,” Navy News Service, September 8, 2016;
Sam LaGrone, “Results of New LCS Review is Departure from Original Vision,” USNI News, September 8, 2016;
Sydney J. Freedberg Jr., “Navy Sidelines First 4 LCS; Overhauls Deployment, Crewing,” Breaking Defense, September
Congressional Research Service

14

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

The Navy states that this crewing and operating plan is intended to
 reduce disruptions to the deployment cycles of the 24 LCSs in the six divisions
that under the 3-2-1 plan would have been caused by the need to test and evaluate
LCS mission packages;
 improve training and proficiency of LCS crews;
 enhance each LCS crew’s sense of ownership of (and thus responsibility for
taking good care of) the ship on which it operates; and
 achieve a percentage of LCSs in deployed status, and numbers of forward-
stationed LCSs, similar to or greater than what the Navy aimed to achieve under
the 3-2-1 plan.
The Navy further states that as the fleet continues to accumulate experience in operating and
maintaining LCSs, elements of this new plan might be modified.22

8, 2016; Justin Doubleday, “Navy Introduces Major Change to Littoral Combat Ship Operations,” Inside the Navy,
September 9, 2016; David B. Larter, “Rebooting LCS: Hundreds More Sailors Needed in Sweeping Overhaul,” Navy
Times
, September 9, 2016; Justin Doubleday, “Navy Begins Implementing Changes to Littoral Combat Ship Program,”
Inside the Navy, October 10, 2016.
22 See, for example, Sydney J. Freedberg Jr., “Navy Sidelines First 4 LCS; Overhauls Deployment, Crewing,” Breaking
Defense
, September 8, 2016.
Congressional Research Service

15

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress

Appendix B. Defense-Acquisition Policy Lessons
In reviewing the LCS program, one possible question concerns what defense-acquisition policy
lessons, if any, the program may offer to policymakers, particularly in terms of the rapid
acquisition strategy that the Navy pursued for the LCS program, which aimed at reducing
acquisition cycle time (i.e., the amount of time between starting the program and getting the first
ship into service).
One possible perspective is that the LCS program demonstrated that reducing acquisition cycle
time can be done. Supporters of this perspective might argue that under a traditional Navy ship
acquisition approach, the Navy might have spent five or six years developing a design for a new
frigate or corvette, and perhaps another five years building the lead ship, for a total acquisition
cycle time of perhaps 10 to 11 years. For a program announced in November 2001, this would
have resulted in the first ship entering service in between late 2011 and late 2012. In contrast,
supporters of this perspective might argue, LCS-1 entered service on November 8, 2008, about
seven years after the program was announced, and LCS-2 entered service on January 16, 2010, a
little more than eight years after the program announced. Supporters of this perspective might
argue that this reduction in acquisition cycle time was accomplished even though the LCS
incorporates major innovations compared to previous larger Navy surface combatants in terms of
reduced crew size, “plug-and fight” mission package modularity, high-speed propulsion, and (in
the case of LCS-2) hull form and hull materials.
Another possible perspective is that the LCS program demonstrated the risks or consequences of
attempting to reduce acquisition cycle time. Supporters of this perspective might argue that the
program’s rapid acquisition strategy resulted in design-construction concurrency (i.e., building
the lead ships before their designs were fully developed), a practice long known to increase risks
in defense acquisition programs. Supporters of this perspective might argue that the cost growth,
design issues, and construction-quality issues experienced by the first LCSs were due in
substantial part to design-construction concurrency, and that these problems embarrassed the
Navy and reduced the Navy’s credibility in defending other acquisition programs. They might
argue that the challenges the Navy faces today in terms of developing an LCS concept of
operations (CONOPS),23 LCS manning and training policies, and LCS maintenance and logistics
plans were increased by the rapid acquisition strategy, because these matters were partly deferred
to later years (i.e., to today) while the Navy moved to put LCSs into production. Supporters of
this perspective might argue that the costs of the rapid acquisition strategy are not offset by very
much in terms of a true reduction in acquisition cycle time, because the first LCS to be equipped
with a mission package that had reached IOC (initial operational capability) did not occur until
late FY2014—almost 13 years after the LCS program was announced. Supporters of this
perspective could argue that the Navy could have avoided many of the program’s early problems
and current challenges—and could have had a fully equipped first ship enter service in 2011 or
2012—if it had instead pursued a traditional acquisition approach for a new frigate or corvette.
They could argue that the LCS program validated, for defense acquisition, the guideline from the
world of business management that if an effort aims at obtaining something fast, cheap, and good,
it will succeed in getting no more than two of these things,24 or, more simply, that the LCS
program validated the general saying that haste makes waste.

23 A CONOPS is a detailed understanding of how to use the ship to accomplish various missions.
24 The guideline is sometimes referred to in the business world as “Fast, cheap, good—pick two.”
Congressional Research Service

16

Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress


A third possible perspective is that the LCS program offers few if any defense-acquisition policy
lessons because the LCS differs so much from other Navy ships and the Navy (and DOD
generally) consequently is unlikely to attempt a program like the LCS in the future. Supporters of
this perspective might argue that the risks of design-construction concurrency have long been
known, and that the experience of the LCS program did not provide a new lesson in this regard so
much as a reminder of an old one. They might argue that the cost growth and construction delays
experienced by LCS-1 were caused not simply by the program’s rapid acquisition strategy, but by
a variety of factors, including an incorrectly made reduction gear25 from a supplier firm that
forced the shipbuilder to build the lead ship in a significantly revised and suboptimal construction
sequence.



Author Information

Ronald O'Rourke

Specialist in Naval Affairs



Disclaimer
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other
than public understanding of information that has been provided by CRS to Members of Congress in
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or
material from a third party, you may need to obtain the permission of the copyright holder if you wish to
copy or otherwise use copyrighted material.


25 A ship’s reduction gear is a large, heavy gear that reduces the high-speed revolutions of the ship’s turbine engines to
the lower-speed revolutions of its propulsors.
Congressional Research Service
RL33741 · VERSION 246 · UPDATED
17