

 
Navy LPD-17 Flight II Amphibious Ship 
Program: Background and Issues for Congress 
Updated June 18, 2019 
Congressional Research Service 
https://crsreports.congress.gov 
R43543 
 
  
 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
Summary 
The Navy wants to procure a total of 13 LPD-17 Flight II amphibious ships. LPD-17 Flight II 
ships cost roughly $1.8 billion each to procure. The first LPD-17 Flight II ship, LPD-30, was 
procured in FY2018. As part of its action on the Navy’s proposed FY2019 budget, Congress 
provided $350 million in unrequested advance procurement (AP) funding for a second LPD-17 
Flight II ship, LPD-31, to be procured in FY2020. This was consistent with the Navy’s FY2019 
budget submission, under which LPD-31 was planned for procurement in FY2020 and the 
remainder of its procurement cost was to be requested in FY2020. The Navy’s FY2020 budget 
submission, however, proposes deferring the procurement of LPD-31 by one year, to FY2021, 
and the Navy’s proposed FY2020 budget, rather than requesting the remainder of LPD-31’s 
procurement cost, instead requests $247.1 million in AP funding for the ship. 
Navy officials state that if no LPD-17 Flight II ship is procured in FY2020, the $350 million in 
FY2019 AP funding that Congress provided for the LPD-17 program would become 
unexecutable, because that funding was provided specifically for use in building an LPD-17 
Flight II ship procured in FY2020, not an LPD-17 Flight II ship procured in FY2021. The $350 
million in FY2019 AP funding can be made executable by procuring LPD-31 in FY2020 or by 
passing legislation permitting the FY2019 AP funding to be used for an LPD-17 Flight II ship 
procured in FY2021. One alternative for procuring LPD-31 in FY2020 would be to do so with 
full funding (i.e., with the remainder of the ship’s procurement cost provided in FY2020). 
Another alternative would be to pass legislation giving the Navy the authority to procure LPD-31 
in FY2020 using incremental funding. Navy officials state that under the latter alternative, the 
amount of procurement funding needed for LPD-31 in FY2020 would be, at a minimum, roughly 
$200 million, and not more than the requested amount of $247.1 million. 
As part of its action on the Navy’s proposed FY2019 budget, Congress also provided $350 
million in unrequested AP funding for a different kind of amphibious ship—an amphibious 
assault ship called LHA-9. This ship is considerably larger and more expensive than an LPD-17 
Flight II ship. The Navy’s FY2020 budget submission estimates LHA-9’s procurement cost at 
$4,076.4 million (i.e., about $4.1 billion). Under the Navy’s FY2019 budget submission, LHA-9 
was planned for procurement in FY2024. The $350 million in FY2019 AP funding that Congress 
provided was intended to encourage the Navy to accelerate the procurement of LHA-9 from 
FY2024 to an earlier fiscal year, such as FY2020 or FY2021. Under the Navy’s FY2020 budget 
submission, the Navy continues to show LHA-9 as a ship planned for procurement in FY2024, 
and the Navy’s proposed FY2020 budget does not request any additional procurement or AP 
funding for the ship. 
Issues for Congress include whether to procure LPD-31 in FY2020 or FY2021; whether to 
procure LPD-31 (if it is procured in FY2020) with full funding or incremental funding; the 
amount of procurement or AP funding to provide for LPD-31 and LHA-9 in FY2020; more 
generally whether the Navy is placing too much, too little, or about the right amount of emphasis 
on amphibious ships in its FY2020 budget submission, particularly compared to other Navy 
shipbuilding programs; and technical risk in the LPD-17 Flight II and LHA programs.
Congressional Research Service 
 link to page 5  link to page 5  link to page 5  link to page 5  link to page 6  link to page 6  link to page 7  link to page 7  link to page 7  link to page 7  link to page 8  link to page 9  link to page 9  link to page 10  link to page 10  link to page 10  link to page 12  link to page 12  link to page 12  link to page 14  link to page 16  link to page 16  link to page 16  link to page 16  link to page 20  link to page 20  link to page 8  link to page 9  link to page 11  link to page 10  link to page 10  link to page 12  link to page 16  link to page 20 Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
Contents 
Introduction ..................................................................................................................................... 1 
Background ..................................................................................................................................... 1 
Amphibious Ships in General ................................................................................................... 1 
Roles and Missions ............................................................................................................. 1 
Types of Amphibious Ships ................................................................................................ 2 
Amphibious Lift Goal ......................................................................................................... 2 
Current and Projected Force Levels .................................................................................... 3 
Existing LSD-41/49 Class Ships ......................................................................................... 3 
LPD-17 Flight II Program ......................................................................................................... 3 
Program Name .................................................................................................................... 3 
Design ................................................................................................................................. 4 
Procurement Quantity ......................................................................................................... 5 
Procurement Schedule ........................................................................................................ 5 
Procurement Cost ................................................................................................................ 6 
Program Funding ................................................................................................................ 6 
LHA-9 Amphibious Assault Ship .............................................................................................. 6 
Amphibious Warship Industrial Base ........................................................................................ 8 
Issues for Congress .......................................................................................................................... 8 
FY2020 Procurement and Funding Issues ................................................................................ 8 
Technical Risk in LPD-17 Flight II and LHA Programs ......................................................... 10 
Legislative Activity for FY2020 .................................................................................................... 12 
Summary of Congressional Action on FY2020 Funding Request .......................................... 12 
FY2020 National Defense Authorization Act (S. 1790).......................................................... 12 
Senate ................................................................................................................................ 12 
FY2020 DOD Appropriations Act (H.R. 2968) ...................................................................... 16 
House ................................................................................................................................ 16 
 
Figures 
Figure 1. LSD-41/49 Class Ship ...................................................................................................... 4 
Figure 2. LPD-17 Flight II Design .................................................................................................. 5 
Figure 3. LHA-8 Amphibious Assault Ship..................................................................................... 7 
  
Tables 
Table 1. LPD-17 Flight II Annual Procurement Quantities for FY2020-FY2024 ........................... 6 
Table 2. LPD-17 Flight II Funding for FY2020-FY2024 ................................................................ 6 
Table 3. LHA-9 Funding for FY2020-FY2024 ............................................................................... 8 
Table 4. Summary of Congressional Action on FY2020 Funding Request ................................... 12 
  
Contacts 
Author Information ........................................................................................................................ 16 
Congressional Research Service 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
 
Congressional Research Service 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
Introduction 
This report provides background information and issues for Congress on the LPD-17 Flight II 
amphibious ship program. The Navy’s FY2020 budget submission defers the planned 
procurement of the second LPD-17 Flight II ship, LPD-31, by one year, to FY2021, and requests 
$247.1 million in advance procurement (AP) funding for the ship.  
This report also discusses LHA-9, a different kind of amphibious ship that the Navy wants to 
procure in FY2024. The Navy’s proposed FY2020 budget does not request any procurement or 
AP funding for this ship. 
Issues for Congress include whether to procure LPD-31 in FY2020 or FY2021; whether to 
procure LPD-31 (if it is procured in FY2020) with full funding or incremental funding; the 
amount of procurement or AP funding to provide for LPD-31 and LHA-9 in FY2020; and more 
generally whether the Navy is placing too much, too little, or about the right amount of emphasis 
on amphibious ships in its FY2020 budget submission, particularly compared to other Navy 
shipbuilding programs. Congress’s decisions on these issues could affect Navy capabilities and 
funding requirements and the shipbuilding industrial base. 
For an overview of the strategic and budgetary context in which the LPD-17 Flight II program 
and other Navy shipbuilding programs may be considered, see CRS Report RL32665, Navy Force 
Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke. 
Background 
Amphibious Ships in General 
Roles and Missions 
Navy amphibious ships are operated by the Navy, with crews consisting of Navy personnel. The 
primary function of Navy amphibious ships is to lift (i.e., transport) embarked U.S. Marines and 
their equipment and supplies to distant operating areas, and enable Marines to conduct 
expeditionary operations ashore in those areas. Although amphibious ships are designed to 
support Marine landings against opposing military forces, they are also used for operations in 
permissive or benign situations where there are no opposing forces. Due to their large storage 
spaces and their ability to use helicopters and landing craft to transfer people, equipment, and 
supplies from ship to shore without need for port facilities,1 amphibious ships are potentially 
useful for a range of combat and noncombat operations.2 
                                                 
1 Amphibious ships have berthing spaces for Marines; storage space for their wheeled vehicles, their other combat 
equipment, and their supplies; flight decks and hangar decks for their helicopters and vertical take-off and landing 
(VTOL) fixed-wing aircraft; and well decks for storing and launching their landing craft. (A well deck is a large, 
garage-like space in the stern of the ship. It can be flooded with water so that landing craft can leave or return to the 
ship. Access to the well deck is protected by a large stern gate that is somewhat like a garage door.) 
2 Amphibious ships and their embarked Marine forces can be used for launching and conducting humanitarian-
assistance and disaster-response (HA/DR) operations; peacetime engagement and partnership-building activities, such 
as exercises; other nation-building operations, such as reconstruction operations; operations to train, advise, and assist 
foreign military forces; peace-enforcement operations; noncombatant evacuation operations (NEOs); maritime-security 
operations, such as anti-piracy operations; smaller-scale strike and counter-terrorism operations; and larger-scale 
ground combat operations. Amphibious ships and their embarked Marine forces can also be used for maintaining 
Congressional Research Service  
 
1 
 link to page 5 Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
On any given day, some of the Navy’s amphibious ships, like some of the Navy’s other ships, are 
forward-deployed to various overseas operating areas. Forward-deployed U.S. Navy amphibious 
ships are often organized into three-ship formations called amphibious ready groups (ARGs).3 On 
average, two or perhaps three ARGs might be forward-deployed at any given time. Amphibious 
ships are also sometimes forward-deployed on an individual basis to lower-threat operating areas, 
particularly for conducting peacetime engagement activities with foreign countries or for 
responding to smaller-scale or noncombat contingencies. 
Types of Amphibious Ships 
Navy amphibious ships can be divided into two main groups—the so-called “big-deck” 
amphibious assault ships, designated LHA and LHD, which look like medium-sized aircraft 
carriers, and the smaller (but still sizeable) amphibious ships designated LPD or LSD, which are 
sometimes called “small-deck” amphibious ships.4 The LHAs and LHDs have large flight decks 
and hangar decks for embarking and operating numerous helicopters and vertical or short takeoff 
and landing (V/STOL) fixed-wing aircraft, while the LSDs and LPDs have much smaller flight 
decks and hangar decks for embarking and operating smaller numbers of helicopters. The LHAs 
and LHDs, as bigger ships, in general can individually embark more Marines and equipment than 
the LSDs and LPDs. 
Amphibious Lift Goal 
The Navy’s 355-ship force-level goal, released in December 2016, calls for achieving and 
maintaining a 38-ship amphibious force that includes 12 LHA/LHD-type ships, 13 LPD-17 class 
ships, and 13 LSD/LPD-type ships (12+13+13).5 The goal for achieving and maintaining a force 
of 38 amphibious ships relates primarily to meeting wartime needs for amphibious lift. Navy and 
Marine Corps officials have testified that fully meeting U.S. regional combatant commander 
requests for day-to-day forward deployments of amphibious ships would require a force of 50 or 
more amphibious ships.6 
                                                 
forward-deployed naval presence for purposes of deterrence, reassurance, and maintaining regional stability. 
3 An ARG notionally includes three amphibious ships—one LHA or LHD, one LSD, and one LPD. These three 
amphibious ships together can embark a Marine expeditionary unit (MEU) consisting of about 2,200 Marines, their 
aircraft, their landing craft, their combat equipment, and about 15 days’ worth of supplies. ARGs can operate in 
conjunction with carrier strike groups (CSGs) to form larger naval task forces; ARGs can also be broken up into 
individual ships that are sent to separate operating areas. 
4 U.S. Navy amphibious ships have designations starting with the letter L, as in amphibious landing. LHA can be 
translated as landing ship, helicopter-capable, assault; LHD can be translated as landing ship, helicopter-capable, well 
deck; LPD can be translated as landing ship, helicopter platform, well deck; and LSD can be translated as landing ship, 
well deck. Whether noted in the designation or not, almost all these ships have well decks. The exceptions are LHAs 6 
and 7, which do not have well decks and instead have expanded aviation support capabilities. For an explanation of 
well decks, see footnote 1. 
5 For more on the Navy’s 355-ship force-level goal, see CRS Report RL32665, Navy Force Structure and Shipbuilding 
Plans: Background and Issues for Congress, by Ronald O'Rourke. For a more detailed review of the 38-ship force 
structure requirements, see Appendix A of CRS Report RL34476, Navy LPD-17 Amphibious Ship Procurement: 
Background, Issues, and Options for Congress, which is an archived report. 
6 For example, in testimony to the Seapower and Projection Forces subcommittee of the House Armed Services 
Committee on February 25, 2015, Marine Corps Lieutenant General Kenneth J. Glueck, Jr., Deputy Commandant for 
Combat Development and Integration and Commanding General of the Marine Corps Combat Development Command, 
stated that the number needed to fully meet regional combatant commander demands for forward-deployed amphibious 
ships is “close to 54.” (Source: Spoken testimony of Lieutenant General Glueck, as reflected in transcript of hearing.) 
Congressional Research Service  
 
2 
 link to page 8 Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
Current and Projected Force Levels 
The Navy’s force of amphibious ships at the end of FY2018 included 32 ships, including 9 
amphibious assault ships (1 LHA and 8 LHDs), 11 LPD-17 Flight I ships, and 12 LSD-41/49 
class ships. The LSD-41/49 class ships, which are the ships to be replaced by LPD-17 Flight II 
ships, are discussed in the next section. 
The Navy’s FY2020 30-year (FY2020-FY2049) shipbuilding plan projects that the Navy’s force 
of amphibious ships will increase gradually to 38 ships by FY2026, remain at a total of 36 to 38 
ships in FY2027 to FY2034, decline to 34 or 35 ships in FY2035-FY2038, increase to 36 or 37 
ships in FY2039-FY2046, and remain at 35 ships in FY2047-FY2049. Over the entire 30-year 
period, the force is projected to include an average of about 35.8 ships, or about 94% of the 
required figure of 38 ships, through resulting amount of lift capability provided by the ships 
would not necessarily equate to about 94% of the amphibious lift goal, due to the mix of ships in 
service at any given moment and their individual lift capabilities. 
Existing LSD-41/49 Class Ships 
The Navy’s 12 aging Whidbey Island/Harpers Ferry (LSD-41/49) class ships (Figure 1) were 
procured between FY1981 and FY1993 and entered service between 1985 and 1998.7 The class 
includes 12 ships because they were built at a time when the Navy was planning a 36-ship 
(12+12+12) amphibious force. They have an expected service life of 40 years; the first ship will 
reach that age in 2025. The Navy’s FY2020 30-year shipbuilding plan projects that the 12 ships 
will retire between FY2026 and FY2038. 
LPD-17 Flight II Program 
Program Name 
The Navy decided in 2014 that the LSD-41/49 replacement ships would be built to a variant of 
the design of the Navy’s San Antonio (LPD-17) class amphibious ships. (A total of 13 LPD-17 
class ships [LPDs 17 through 29] were procured between FY1996 and FY2017.) Reflecting that 
decision, the Navy announced on April 10, 2018, that the replacement ships would be known as 
the LPD-17 Flight II ships.8 By implication, the Navy’s original LPD-17 design became the LPD-
17 Flight I design.  
                                                 
7 The class was initially known as the Whidbey Island (LSD-41) class. The final four ships in the class, beginning with 
Harpers Ferry (LSD-49), were built to a modified version of the original LSD-41 design, prompting the name of the 
class to be changed to the Harpers Ferry/Whidbey Island (LSD-41/49) class. Some sources refer to these 12 ships as 
two separate classes. The first three were built by Lockheed Shipbuilding of Seattle, WA, a firm that subsequently 
exited the Navy shipbuilding business. The final nine were built by Avondale Shipyards of New Orleans, LA, a 
shipyard that eventually became part of the shipbuilding firm Huntington Ingalls Industries (HII). Avondale, like 
Lockheed Shipbuilding, no longer builds Navy ships. HII wound down Navy shipbuilding operations at Avondale in 
2014, after Avondale finished building LPD-25, the ninth LPD-17 class ship. HII continues to operate two other 
shipyards that build Navy ships—Ingalls Shipbuilding in Pascagoula, MS (HII/Ingalls), and Newport News 
Shipbuilding in Newport News, VA (HII/NNS). HII’s construction of amphibious ships, previously divided between 
Avondale and Ingalls, now takes place primarily at Ingalls. 
8 Megan Ecsteain, “Navy Designates Upcoming LX(R) Amphibs as San Antonio-Class LPD Flight II,” USNI News, 
April 11, 2018. Within a program to build a class of Navy ships, the term flight refers to a group of ships within the 
class that are built to a particular version of the class design. The LPD-17 Fight II program was previously known as 
the LX(R) program. In the designation LX(R), the X meant that the exact design of the ship had not yet been 
determined, and the R meant that the ships are intended as replacements for the LSD-41/49 class ships. Prior to being 
Congressional Research Service  
 
3 
 link to page 9 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
Figure 1. LSD-41/49 Class Ship 
 
Source: U.S. Navy photo accessed May 7, 2014, at http://www.navy.mil/gallery_search_results.asp?terms=
lsd+52&page=4&r=4. The Navy’s caption for the photo states that the photo is dated July 13, 2013, and that it 
shows the Pearl Harbor (LSD-52) anchored off Majuro atol  in the Republic of the Marshall Islands during an 
exercise called Pacific Partnership 2013. 
The first LPD-17 Flight II ship is designated LPD-30. Subsequent LPD-17 Flight II ships are to 
be designated LPD-31, LPD-32, and so on. Whether the LPD-17 Flight II ships constitute their 
own shipbuilding program or an extension of the original LPD-17 shipbuilding program might be 
a matter of perspective. As a matter of convenience, this CRS report refers to the Flight II 
shipbuilding effort as a separate program. Years from now, LPD-17 Flight I and Flight II ships 
might come to be known collectively as either the LPD-17 class, the LPD-17/30 class, or the 
LPD-17 and LPD-30 classes. 
Design 
Compared to the LPD-17 Flight I design, the LPD-17 Flight II design (Figure 2) is somewhat 
less expensive to procure, and in some ways less capable—a reflection of how the Flight II design 
was developed to meet Navy and Marine Corps operational requirements while staying within a 
unit procurement cost target that had been established for the program.9 In many other respects, 
                                                 
referred to as the LX(R) program, the program was referred to as the LSD(X) program, meaning an LSD-type ship 
whose design had not yet been determined. The program’s designation was changed to LX(R) in 2012 to signal that the 
replacement for the existing LSD-41/49 class ships would be an amphibious ship that would best meet future Navy and 
Marine Corps needs, regardless of whether that turned out to be a ship that one might refer to as an LSD. For an article 
discussing this earlier change in the program’s designation, see Christopher P. Cavas, “Different Missions Might Await 
New USN Amphib,” Defense News, November 12, 2012. 
9 The Navy’s unit procurement cost targets for the LPD-17 Flight II program were $1,643 million in constant FY2014 
dollars for the lead ship, and an average of $1,400 million in constant FY2014 dollars for ships 2 through 11. (Source: 
Navy briefing on LX(R) program to CRS and CBO, March 23, 2015.) The cost target for the lead ship was greater than 
the cost target for the subsequent ships primarily because the procurement cost of the lead ship incorporates much or all 
of the detail design and nonrecurring engineering (DD/NRE) costs for the program. Incorporating much or all of the 
Congressional Research Service  
 
4 
 link to page 10 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
however, the LPD-17 Flight II design is similar in appearance and capabilities to the LPD-17 
Flight I design. Of the 13 LPD-17 Flight I ships, the final two (LPDs 28 and 29) incorporate some 
design changes that make them transitional ships between the Flight I design and the Flight II 
design. 
Figure 2. LPD-17 Flight II Design 
Artist’s rendering 
 
Source: Huntington Ingalls Industries rendering accessed April 22, 2019, at 
https://www.huntingtoningalls.com/lpd-flight-i /. 
Procurement Quantity 
Consistent with the Navy’s 38-ship amphibious force-level goal, the Navy wants to procure a 
total of 13 LPD-17 Flight II ships. 
Procurement Schedule 
The first LPD-17 Flight II ship, LPD-30, was procured in FY2018. Under the Navy’s FY2019 
budget submission, the second LPD-17 Flight II ship, LPD-31, was to be procured in FY2020,10 
and the remaining 11 were to be procured at a rate of one per year starting in FY2022. The 
Navy’s FY2020 budget submission proposes deferring the procurement of LPD-31 to FY2021 
and the procurement of the third ship (LPD-32) to FY2023, with the final 10 ships to be procured 
at a rate of one per year starting in FY2025. As shown in Table 1, when compared to the Navy’s 
                                                 
DD/NRE costs of for a shipbuilding program into the procurement cost of the lead ship in the program is a traditional 
Navy shipbuilding budgeting practice. 
10 The Navy had planned to procure the first LPD-17 Flight II ship in FY2020. Congress, as part of its action on the 
Navy’s proposed FY2018 budget, accelerated the procurement of the first LPD17 Flight II ship to FY2018. The Navy’s 
FY2019 budget submission, which was submitted before Congress finalized its action on the Navy’s FY2018 budget, 
programmed the procurement of an LPD-17 Flight II ship in FY2020. Under the Navy’s original plan, the ship 
programmed for procurement in FY2020 was to be the first Flight II ship. With the first Flight II ship having been 
procured in FY2018, the Flight II ship scheduled for procurement in FY2020 became the second Flight II ship. 
Congressional Research Service  
 
5 
 link to page 10  link to page 11 Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
FY2019 budget submission, the Navy’s FY2020 budget submission reduces from four to two the 
total number of LPD-17 Flight II ships to be procured during the period FY2020-FY2024. 
Table 1. LPD-17 Flight II Annual Procurement Quantities for FY2020-FY2024 
As shown in Navy’s FY2019 and FY2020 budget submissions 
Budget 
FY20-FY24 
Submission 
FY20 
FY21 
FY22 
FY23 
FY24 
Total 
FY2019 submission 
1 
0 
1 
1 
1 
4 
FY2020 submission 
0 
1 
0 
1 
0 
2 
Source: Table prepared by CRS based on Navy’s FY2019 and FY2020 budget submissions. 
Procurement Cost 
Under the Navy’s FY2020 budget submission, LPD-17 Flight II ships cost roughly $1.8 billion 
each to procure. 
Program Funding 
Table 2 shows LPD-17 Flight II procurement and advance procurement (AP) funding for 
FY2020-FY2024 as presented in the Navy’s FY2020 budget submission. 
Table 2. LPD-17 Flight II Funding for FY2020-FY2024 
Millions of dollars, rounded to nearest tenth 
FY20 
FY21 
FY22 
FY23 
FY24 
 
(req.)  (proj.) 
(proj.)  (proj.)  (proj.) 
Procurement 
0 
1,590.9 
0 
1,738.9 
0 
Advance procurement (AP) 
247.1 
0 
0 
0 
0 
Total 
247.1 
1,590.9 
0 
1,738.9 
0 
(Procurement quantity) 
(0) 
(1) 
(0) 
(1) 
(0) 
Source: Table prepared by CRS based on Navy’s FY2020 budget submission. 
LHA-9 Amphibious Assault Ship 
The most recently procured LHA/LHD-type amphibious assault ship is LHA-8 (Figure 3), which 
was procured in FY2017 and is scheduled under the Navy’s FY2020 budget submission to be 
delivered in January 2024. 
The Navy wants to procure the next LHA/LHD-type ship, LHA-9, in FY2024. LHA/LHD-type 
ships are considerably larger and more expensive than LPDs. The Navy’s FY2020 budget 
submission estimates LHA-9’s procurement cost at $4,076.4 million (i.e., about $4.1 billion). 
Some in Congress and elsewhere are interested in the potential for accelerating the procurement 
of LHA-9 from FY2024 to an earlier year, such as FY2020 or FY2021, in part to achieve better 
production learning curve benefits in shifting from production of LHA-8 to LHA-9 and thereby 
reduce LHA-9’s procurement cost in real (i.e., inflation-adjusted) terms. For example, the Senate 
Armed Services Committee’s report (S.Rept. 115-262 of June 5, 2018) on the John S. McCain 
National Defense Authorization Act for Fiscal Year 2019 (S. S. 2987) stated: 
Congressional Research Service  
 
6 
 link to page 12 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
The  committee  remains  concerned  with  the  Navy  procurement  profile  for  large  deck 
amphibious  assault  ships,  which  includes  a  span  of  7  years  until  the  next  large  deck 
amphibious assault ship (LHA–9) is procured in 2024. 
The committee notes that efficiencies could be gained by reducing this span, which could 
enable  a  steadier  workforce  with  an  increased  learning  curve,  material  and  equipment 
suppliers on more reliable and fixed delivery contracts, and a more effective continuous 
improvement schedule. 
The committee urges the Secretary of the Navy to accelerate procurement of LHA–9 to not 
later than 2021…. (Pages 82-83)11 
Figure 3. LHA-8 Amphibious Assault Ship 
Artist’s rendering 
 
Source: Photo accompanying Tyler Rogoway, “The Next America Class Amphibious Assault Ship Wil  Almost 
Be In a Class of its Own,” The Drive, April 17, 2018. A note on the photo credits the photo to HII. 
As part of its action on the Navy’s proposed FY2019 budget, Congress provided $350 million in 
unrequested AP funding for LHA-9, in part to encourage the Navy to accelerate the procurement 
of LHA-9 from FY2024 to an earlier fiscal year, such as FY2020 or FY2021.  
Under the Navy’s FY2020 budget submission, the Navy continues to show LHA-9 as a ship 
planned for procurement in FY2024, and the Navy’s proposed FY2020 budget does not request 
any additional procurement or AP funding for the ship. Consistent with past practice for procuring 
LHA/LHD-type amphibious ships, the Navy’s FY2020 budget submission anticipates using two-
year incremental funding (i.e., split funding) to procure LHA-9, with the bulk of the ship’s 
procurement cost to be divided between FY2024 and FY2025. Table 3 shows FY2020-FY2024 
funding for the ship under the Navy’s FY2020 budget submission. 
                                                 
11 See also Mallory Shelbourne, “HII Ready to Accelerate LHA-9 Construction Three Years Ahead of Navy Schedule,” 
Inside Defense, March 15, 2019. 
Congressional Research Service  
 
7 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
Table 3. LHA-9 Funding for FY2020-FY2024 
Millions of dollars, rounded to nearest tenth 
FY20 
FY21 
FY22 
FY23 
FY24 
 
(req.)  (proj.) 
(proj.)  (proj.)  (proj.) 
Procurement 
0 
0 
0 
0  1,617.8 
Advance procurement (AP) 
0 
0 
0 
170.6 
0 
Total 
0 
0 
0 
170.6  1,617.8 
(Procurement quantity) 
(0) 
(0) 
(0) 
(0) 
(1) 
Source: Table prepared by CRS based on Navy’s FY2020 budget submission. 
Amphibious Warship Industrial Base 
Huntington Ingalls Industries/Ingalls Shipbuilding (HII/Ingalls) of Pascagoula, MS, is the Navy’s 
current builder of both LPDs and LHA/LHD-type ships, although other U.S. shipyards could also 
build amphibious ships.12 The amphibious warship industrial base also includes many supplier 
firms in numerous U.S. states that provide materials and components for Navy amphibious ships. 
HII states that the supplier base for its LHA production line, for example, includes 457 companies 
in 39 states.13 
Issues for Congress 
FY2020 Procurement and Funding Issues 
FY2020 procurement and funding issues for Congress for FY2020 include the following: 
  whether to procure LPD-31 in FY2020 or FY2021; 
  whether to procure LPD-31 (if it is procured in FY2020) with full funding or 
incremental funding; 
  the amount of procurement or AP funding to provide for LPD-31 and LHA-9 in 
FY2020; and 
  more generally whether the Navy is placing too much, too little, or about the 
right amount of emphasis on amphibious ships in its FY2020 budget submission, 
particularly compared to other Navy shipbuilding programs. 
Regarding the first issue above, supporters of procuring LPD-31 in FY2020 could argue that it 
could put the Navy on a path to achieving the 38-ship amphibious ship force-level goal sooner 
than FY2026, permit the $350 million in AP funding that Congress provided for the program in 
FY2019 to be executed as intended, and leave more budgetary room in FY2021 for funding other 
Navy programs. Supporters of procuring LPD-31 in FY2021 could argue that FY2026 is an 
acceptable date for achieving the 38-ship amphibious ship force-level objective, particularly 
                                                 
12 Amphibious ships could also be built by U.S. shipyards such as HII/Newport News Shipbuilding (HII/NNS) of 
Newport News, VA; General Dynamics/National Steel and Shipbuilding Company (GD/NASSCO) of San Diego, CA; 
and (for LPDs at least) General Dynamics/Bath Iron Works (GD/BIW) of Bath, ME. The Navy over the years has from 
time to time conducted competitions among shipyards for contracts to build amphibious ships. 
13 Source: HII statement as quoted in Frank Wolfe, “Navy Budget Plan Delays Buy of Amphibious Ships,” Defense 
Daily, March 15, 2019. 
Congressional Research Service  
 
8 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
given the challenges the Navy faces for meeting some of its other force-level goals in coming 
years (such as those for attack submarines and aircraft carriers); that in a situation of finite Navy 
or Department of Defense (DOD) funding, procuring LPD-31 in FY2020 might require 
reductions in funding for other Navy or DOD programs, with an uncertain net result on Navy or 
DOD capabilities; and that Congress can make the FY2019 AP funding executable by passing 
legislation permitting the funding to be used on an LPD-17 Flight II ship procured in FY2021. 
Regarding the second issue above, supporters of procuring LPD-31 with full funding could argue 
that it would leave more budgetary room in FY2021 and perhaps one or more years beyond that 
for funding other Navy programs, and that Navy surface ships other than aircraft carriers and 
LHA/LHD-type amphibious assault ships have generally been procured with full funding rather 
than incremental funding. Supporters of funding LPD-31 with incremental funding could argue 
that doing so would reduce FY2020 funding needs for LPD-31, preserving more FY2020 funding 
for other Navy or DOD programs, and that there have been a few instances over the years in 
which Navy surface ships other than aircraft carriers and LHA/LHD-type amphibious assault 
ships have been procured with incremental funding. 
Regarding the third issue above, factors that Congress may consider include whether the Navy 
has properly scheduled and accurately estimated the work on these ships it is proposing to do in 
FY2020, and how the type and amount of work to be done on these ships in FY2020 would 
change if LPD-31 were procured in FY2020 instead of FY2021, and if procurement of LHA-9 
were accelerated from FY2024 to an earlier fiscal year, such as FY2020 or FY2021. 
Regarding the fourth issue above, supporters of amphibious ships might argue that by deferring 
the procurement of LPD-31 to FY2021, reducing the number of LPD-17 Flight II ships to be 
procured in FY2020-FY2024, and not accelerating the procurement of LHA-9 from FY2024 to an 
earlier fiscal year, the Navy’s FY2020 budget submission is placing a reduced emphasis on 
amphibious ships in its shipbuilding plans, particularly compared to other type of Navy ships, 
such as attack submarines, destroyers, and frigates, all of which experienced additions or 
accelerations in FY2020 or FY2021 under the Navy’s FY2020 budget submission.14 Amphibious 
ships, they could argue, are as important as these other types of ships, and are in high demand by 
U.S. regional combatant commanders. Other observers, while acknowledging the value of 
amphibious ships, might argue that within a finite Navy budget, the Navy needs to make difficult 
choices about what type of ships to procure; that attack submarines, destroyers, and frigates are 
critical for countering China’s improving naval capabilities and for performing other missions; 
and that the Navy currently has substantial shortfalls in attack submarines, large surface 
combatants (such as destroyers), and small surface combatants (such as frigates) relative to its 
force-level goals for those types of ships. 
A Navy information paper on options for funding the procurement of LPD-31 (the second LPD-
17 Flight II ship) states: 
QUESTION: Explain the end cost to build LPD 31 under the following conditions: 
a. FY19 ($350M), FY20 ($247M), and FY21 funding are all available 
b. FY19 ($350M) and FY21 funding are available (FY20 $247M is not available) 
c. Only FY20 ($247M) and FY21 funding are available (FY19 $350M is not available) 
                                                 
14 See, for example, Megan Eckstein, “LPD Flight II Amphib Delayed in Favor of 3rd Attack Sub in FY 2020,” USNI 
News, March 14, 2019; Frank Wolfe, “Navy Budget Plan Delays Buy of Amphibious Ships,” Defense Daily, March 15, 
2019. 
 
Congressional Research Service  
 
9 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
RESPONSE:… 
Scenarios: 
Option  (a)  represents  the  most  affordable  scenario  with  no  increase  in  end  cost.  This 
scenario assumes access to FY19 Advance Procurement (AP) funds in the Summer 2019 
to initiate LPD 31 LLTM procurements, which will mitigate inflation impacts. The funding 
may also be used to leverage Government Furnished Equipment (GFE) quantity buys. This 
most affordable scenario assumes incremental funding authority and the appropriation of 
FY20 as Full Funding with the balance in FY21. That approach would enable the Navy to 
put  LPD  31  under  contract  in  FY20  and  start  construction  on  the  optimized  18-month 
center. The authority to proceed to proposal, negotiations, and award earlier will maximize 
the ability to leverage the recently awarded LPD 30 and mitigate the impacts associated 
with a delayed contract negotiation and award timeline. 
Option (b) represents the medium-cost scenario with a potential end cost increase of ~2% 
relative to the PB19 profile. This scenario assumes access to FY19 AP funds in the Summer 
2019  to  initiate  LPD  31  LLTM  procurements  and  may  also  be  used  to  leverage  GFE 
quantity  buys.  The  construction  contract  would  be  awarded  upon  authorization  and 
appropriation of the FY21 ship. Although this scenario may allow the shipbuilder to start 
LPD  31  construction  on  the  optimized  18-month  center  and  minimize  loss  of  learning 
relative to prior ships, it carries the potential for inflation impacts and increased overhead 
rates.  Additionally,  the  contractor  may  include  increased  risk  in  their  LPD  31  pricing 
depending on shipyard loading, future business projections, and lessons learned from ships 
currently in production. 
Option (c) represents the most costly scenario with a potential end cost increase of  ~6% 
relative to the PB19 profile. This scenario assumes that LPD 31 LLTM procurement would 
not  begin  until  the  FY20  authorization  and  appropriations  bills  are  enacted.  The 
construction contract would be awarded upon authorization and appropriation of the FY21 
ship. Due to LLTM requirements, ship construction would start at least 6-9 months later 
than  the  optimal  18-month  centers  (i.e.  24+  months  after  LPD  30).  This  scenario  also 
introduces the potential for additional inflation impacts, increased overhead rates, and loss 
of learning.15 
Technical Risk in LPD-17 Flight II and LHA Programs 
Another potential issue for Congress is technical risk in the LPD-17 Flight II and LHA programs. 
A May 2019 Government Accountability Office (GAO) report—the 2019 edition of GAO’s 
annual report surveying DOD major acquisition programs—states the following about the LPD-
17 Flight II program: 
Current Status 
The Navy planned to accelerate purchase of LPD 30—the first fully configured Flight II 
ship—after Congress appropriated $1.8 billion above the fiscal year 2018 budget request, 
according to program officials. The Navy reported that it awarded contracts in August 2018 
for LPD 30 long lead time materials and in March 2019 for lead ship construction. 
The Navy based the Flight II design on Flight I,  with  modifications to reduce costs and 
meet new requirements. According to program officials, roughly 200 design changes will 
distinguish  the  two  flights  including  replacing  the  composite  mast  with  a  steel  stick. 
Officials stated that the design would not rely on any new technologies. However, the Navy 
plans  to  install  a  new  radar,  the  Enterprise  Air  Surveillance  Radar,  which  is  still  in 
development. The Navy expects live radar system testing through November 2019, with a 
                                                 
15 Navy information paper dated June 4, 2019, received from Navy Office of Legislative Affairs on June 7, 2019. 
Congressional Research Service  
 
10 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
complete  radar  prototype  in  February  2020.  Although  program  officials  consider  these 
activities  to  be  low  risk,  the  Navy  will  make  its  decision  to  begin  ship  construction  by 
December 2019 without incorporating lessons learned from radar testing into the design. 
Starting construction before stabilizing the design could require the Navy to absorb costly 
design changes and rework during ship construction. 
The Navy initially pursued a limited competition for LX(R), but now has a non-competitive 
acquisition strategy for LPD 17 Flight II. The Navy plans to award sole-source contracts 
to Huntington Ingalls—the only shipbuilder of Flight I ships—for Flight II construction. 
Further, the program did not request a separate independent cost estimate for Flight II prior 
to awarding the LPD 30 detail design and construction contract. At the same time, the Navy 
identified no plans to establish a cost baseline specific to Flight II. Without this baseline, 
the Navy would report full LPD 17 program costs—rather than Flight II specific costs—
constraining visibility into Flight II. 
Program Office Comments 
We provided a draft of this assessment to the program office for review and comment. The 
program office provided technical comments, which we incorporated as appropriate The 
program office stated that LPD Flight II is included under the existing LPD 17 acquisition 
program baseline, and that no other viable contractor responded to a public notice regarding 
the Navy’s plan to award Huntington Ingalls the LPD 30 construction contract.16 
The May 2019 GAO report stated the following about the LHA program: 
Current Status 
In June 2017, the Navy exercised a contract option for detail design and construction of the 
LHA 8. The LHA 8 incorporates significant design changes from earlier ships in the LHA 
6  class,  but  Navy  officials  were  unable  to  quantify  the  changes.  The  Navy  started 
construction in October 2018 and LHA 8 is scheduled to be delivered in January 2024. 
The LHA 8 program office has not identified any critical technologies. However, the ship 
is relying on technology that is currently being developed by another Navy program, the 
Enterprise Air Surveillance Radar (EASR), with delivery expected in August 2021. EASR, 
intended to provide self-defense and situational awareness capabilities, is derived from the 
pre-existing Air and Missile Defense Radar program, but will be a different size and will 
rotate.  LHA  8  program  officials  have  identified  the  radar  as  the  program’s  highest 
development risk. If the radar is not delivered on schedule, Navy officials report that this 
could  lead  to  out-of-sequence  design  and  delayed  installation  and  testing.  Officials 
responsible for developing the radar, however, stated that the radar is approaching maturity 
and is on schedule to be delivered to the shipbuilder when needed. 
The  Navy  began  construction  with  about  61  percent  of  the  LHA  8  product  model 
completed—an approach inconsistent with shipbuilding best practices. These best practices 
call  for  100  percent  completion  of  3D  product  modeling  prior  to  construction  start  to 
minimize the likelihood of costly re-work and out of sequence work that can drive schedule 
delays. The Navy, however, estimates that the LHA 8 shipbuilder will not complete 100 
percent of the ship’s 3D product model until June 2019, almost 8 months after the start of 
construction. 
Program Office Comments 
We provided a draft of this assessment to the program office for review and comment. The 
program office provided technical comments, which we incorporated where appropriate. 
                                                 
16 Government Accountability Office, Weapon Systems Annual Assessment, Limited Use of Knowledge-Based 
Practices Continues to Undercut DOD’s Investments, GAO-19-336SP, May 2019, p. 134. 
Congressional Research Service  
 
11 
 link to page 16  link to page 16 Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
The program office stated that the Navy understands all design changes incorporated on 
the LHA 8, such as reintroducing the well deck and incorporating EASR. According to the 
program office, the Navy does not begin construction on any section of the LHA 8 ship 
before completing that respective section’s design.17 
Legislative Activity for FY2020 
Summary of Congressional Action on FY2020 Funding Request 
Table 4 summarizes congressional action on the Navy’s FY2020 funding request for the LPD-17 
Flight II and LHA-9 programs. 
Table 4. Summary of Congressional Action on FY2020 Funding Request 
Millions of dollars, rounded to nearest tenth 
Authorization 
Appropriation 
 
Request 
HASC 
SASC 
Conf. 
HAC 
SAC 
Conf. 
LPD-17 Flight II program 
Procurement 
0 
 
525.0 
 
0 
 
 
Advance procurement (AP) 
247.1 
 
0 
 
0 
 
 
(Procurement quantity) 
(0) 
 
(1) 
 
(0) 
 
 
LHA-9 amphibious assault ship 
Procurement 
0 
 
650.0 
 
0 
 
 
Advance procurement (AP) 
0 
 
0 
 
0 
 
 
(Procurement quantity) 
(0) 
 
(1) 
 
(0) 
 
 
Source: Table prepared by CRS based on Navy’s FY2020 budget submission, committee and conference 
reports, and explanatory statements on FY2020 National Defense Authorization Act and FY2020 DOD 
Appropriations Act. 
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is 
House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference agreement. 
FY2020 National Defense Authorization Act (S. 1790) 
Senate 
The Senate Armed Services Committee, in its report (S.Rept. 116-48 of June 11, 2019) on S. 
1790, recommended the funding levels shown in the SASC column of Table 4. Regarding these 
recommended funding levels, S.Rept. 116-48 states: 
LPD-class amphibious transport ship 
The budget request included no funding in line number 12 of Shipbuilding and Conversion, 
Navy (SCN), for procurement of LPD Flight II-class amphibious transport ships. 
The  committee  notes  that  the  Navy  has  identified  LPD-30,  which  was  authorized  and 
appropriated in fiscal year 2018, as the first Flight II LPD. In the fiscal year 2019 budget 
                                                 
17 Government Accountability Office, Weapon Systems Annual Assessment, Limited Use of Knowledge-Based 
Practices Continues to Undercut DOD’s Investments, GAO-19-336SP, May 2019, p. 133. 
Congressional Research Service  
 
12 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
request, the Navy planned to procure the next Flight II LPD, LPD-31, in fiscal year 2020. 
The committee is concerned that the fiscal year 2020 budget request's delay of procurement 
of LPD-31 to fiscal year 2021 could result in production inefficiency, increased cost, and 
delay in reaching the Navy's requirement for 38 amphibious ships. 
Therefore, the committee recommends an increase of $525.0 million in line number 12 of 
SCN for incremental funding of the amphibious transport ship designated LPD-31. 
The committee's intent is for the Navy to use the $350.0 million appropriated in SCN line 
number 13 in fiscal year 2019 and additional fiscal year 2020 funds in SCN line number 
12 to procure LPD-31 long-lead material and start construction as efficiently as possible. 
Consistent with the budget request, the committee expects the Navy to request the balance 
of costs for LPD-31 in fiscal year 2021. 
LPD-class amphibious transport ship advance procurement 
The  budget  request  included  $247.1  million  in  line  number  13  of  Shipbuilding  and 
Conversion,  Navy  (SCN),  for  advance  procurement  of  LPD  Flight  II-class  amphibious 
transport ships. 
The committee recommends transferring the funds requested in line number 13 of SCN to 
line number 12 of SCN to  support incremental funding of the amphibious transport ship 
designated LPD-31. 
Therefore, the committee recommends a decrease of $247.1 million in line number 13 of 
SCN for advance procurement of LPD Flight II-class amphibious transport ships. 
LHA replacement amphibious assault ship 
The budget request included no funding in line number 15 of Shipbuilding and Conversion, 
Navy (SCN), for procurement of LHA replacement amphibious assault ships. 
The  committee  remains  concerned  with  the  Navy  procurement  profile  for  large  deck 
amphibious  assault  ships,  which  includes  a  span  of  7  years  until  the  next  large  deck 
amphibious assault ship (LHA-9) would be procured in fiscal year 2024. 
The  committee  notes  that  efficiencies  could  be  gained  by  reducing  this  span,  including 
steadier workflow with an increased learning curve, material and equipment suppliers with 
more  predictable  delivery  contracts,  and  a  more  effective  continuous  improvement 
schedule. 
The  committee  urges  the  Secretary  of  the  Navy  to  accelerate  procurement  of  LHA-9, 
including  putting  the  $356.0  million  appropriated  in  fiscal  year  2019  for  this  ship  on 
contract  to  procure  long  lead-time  material  as  soon  as  possible  and  leveraging  the 
incremental funding authority provided elsewhere in this Act to start construction and build 
LHA-9 as efficiently as possible. 
Therefore, the committee recommends an increase of $650.0 million in line number 15 of 
SCN. (Pages 23-24) 
Section 122 of S. 1790 as reported by the committee states: 
SEC.  122.  Capabilities  based  assessment  for  naval  vessels  that  carry  fixed-wing 
aircraft. 
(a)  In  general.—Not  later  than  30  days  after  the  date  of  the  enactment  of  this  Act,  the 
Secretary of the Navy shall initiate a capabilities based assessment to begin the process of 
identifying requirements for the naval vessels that will carry fixed-wing aircraft following 
the ships designated CVN–81 and LHA–9. 
(b) Elements.—The assessment shall— 
Congressional Research Service  
 
13 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
(1)  conform  with  the  Joint  Capabilities  Integration  and  Development  System,  including 
Chairman of the Joint Chiefs of Staff Instruction 5123.01H; and 
(2) consider options for the vessels described under subsection (a) that would enable greater 
commonality  and  interoperability  of  naval  aircraft  embarked  on  such  naval  vessels, 
including aircraft arresting gear and launch catapults. 
(c)  Notification  requirement.—Not  later  than  15  days  after  initiating  the  assessment 
required  under  subsection  (a),  the  Secretary  of  the  Navy  shall  notify  the  congressional 
defense  committees  of  such  action  and  the  associated  schedule  for  completing  the 
assessment and generating an Initial Capabilities Document. 
Regarding Section 122, S.Rept. 116-48 states: 
Capabilities  based  assessment  for  naval  vessels  that  carry  fixed-wing  aircraft  (sec. 
122) 
The committee recommends a provision that would require the Secretary of the Navy to 
conduct a capabilities-based assessment to clarify the future requirements for naval vessels 
that carry fixed-wing aircraft. 
The committee notes that the budget request's proposal to retire the USS Harry S. Truman 
(CVN-75)  early  would  yield  a  force  with  10  or  fewer  aircraft  carriers  for  more  than  20 
years.  The  budget  request  also  includes  a  7-year  gap  until  the  funding  of  the  next 
amphibious  assault  ship,  LHA-9,  which  will  likely  result  in  a  production  break.  The 
committee is concerned that both the CVN-75 and LHA-9 proposals are contrary to current 
Navy  force  structure requirements and  will result in significant negative impacts for the 
shipbuilding industrial base. 
The committee also notes that the Under Secretary of the Navy stated in February 2019, 
"If $13 billion is  unaffordable . . .  what's the  next carrier look like? Is it going  to be as 
advanced as [the USS Gerald R. Ford] or is it going to be smaller? . . . We don't know the 
answers to that, but we're looking at those." 
The committee also notes that all three future fleet platform architecture studies required 
by section 1067 of the National Defense Authorization Act for Fiscal Year 2016 (P.L. 114-
92) recommended that the Navy pursue a class of aircraft carriers smaller than the Ford-
class.  The  committee  believes  that  smaller  aircraft  carriers  could  both  increase  aircraft 
carrier capacity and provide a more efficient means to conduct a range of missions with 
lower sortie requirements, including support for amphibious operations. 
Accordingly,  the  committee  directs  the  Secretary  of  the  Navy  to  consult  the  fleet 
architecture studies, as well as the report on alternative aircraft carrier options required by 
section 128 of the National Defense Authorization Act for Fiscal Year 2016 (P.L. 114-92), 
and initiate a capabilities-based assessment to begin the process of identifying requirements 
for  the  naval  vessels  that  will  carry  fixed-wing  aircraft  following  CVN-81  and  LHA-9. 
(Page 8) 
Section 124 of S. 1790 as reported by the committee states: 
SEC. 124. Design and construction of amphibious transport dock designated LPD–
31. 
(a) In general.—The Secretary of the Navy  may enter into a contract for the design and 
construction  of  the  amphibious  transport  dock  designated  LPD–31  using  amounts 
authorized  to  be  appropriated  for  the  Department  of  Defense  for  Shipbuilding  and 
Conversion, Navy. 
(b) Use of incremental funding.—With respect to the contract entered into under subsection 
(a), the Secretary may use incremental funding to make payments under the contract with 
amounts authorized to be appropriated in fiscal years 2019, 2020, and 2021. 
Congressional Research Service  
 
14 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
(c) Condition for out-year contract payments.—The contract entered into under subsection 
(a) shall provide that any obligation of the United States to make a payment under such 
contract  for  any  fiscal  year  after  fiscal  year  2020  is  subject  to  the  availability  of 
appropriations for that purpose for such fiscal year. 
Regarding Section 124, S.Rept. 116-48 states: 
Design and construction of amphibious transport dock designated LPD-31 (sec. 124) 
The committee recommends a provision that would authorize the Secretary of the Navy to 
enter into and incrementally fund a contract for design and construction of the amphibious 
transport dock designated LPD-31. 
The committee notes that in testimony before the Senate Armed Services Committee on 
April  7,  2019,  the  Secretary  of  the  Navy  and  Chief  of  Naval  Operations  supported 
incremental funding authority for LPD-31. (Page 9) 
Section 125 of S. 1790 as reported by the committee states: 
SEC. 125. LHA Replacement Amphibious Assault Ship Program. 
(a) Authority to use incremental funding.—The Secretary of the Navy may enter into and 
incrementally fund a contract for detail design and construction of the LHA replacement 
ship  designated  LHA  9  and,  subject  to  subsection  (b),  funds  for  payments  under  the 
contract may be provided from amounts authorized to be appropriated for the Department 
of Defense for Shipbuilding and Conversion, Navy, for fiscal years 2019 through 2025. 
(b) Condition for out-year contract payments.—A contract entered into under subsection 
(a)  shall  provide  that  any  obligation  of  the  United  States  to  make  a  payment  under  the 
contract for any subsequent fiscal  year is subject to the availability of appropriations for 
that purpose for such subsequent fiscal year. 
(c)  Repeal  of  obsolete  authority.—Section  125  of  the  John  Warner  National  Defense 
Authorization Act for Fiscal Year 2007 (Public Law 109–364; 120 Stat. 2106) is repealed. 
Regarding Section 125, S.Rept. 116-48 states: 
LHA Replacement Amphibious Assault Ship Program (sec.125) 
The committee recommends a provision that would authorize the Secretary of the Navy to 
enter  into  and  incrementally  fund  a  contract  for  design  and  construction  of  the  LHA 
replacement ship designated LHA-9. 
The committee notes that in testimony before the Senate Armed Services Committee on 
April  7,  2019,  the  Secretary  of  the  Navy  and  Chief  of  Naval  Operations  supported 
incremental funding authority for LHA-9. 
The  provision  would  also  repeal  section  125  of  the  John  Warner  National  Defense 
Authorization Act for Fiscal Year 2007 (P.L. 109-364). (Page 9) 
S.Rept. 116-48 also states: 
Acquisition strategy for LHA-9 and LHA-10 
The committee notes that the Navy estimates that $4.0 billion will be saved using a block 
buy acquisition strategy for the procurement of CVN-80 and CVN-81. 
The  committee  believes  that  such  an  approach  for  LHA-9  and  LHA-10  could  provide 
substantial cost savings as  well as needed stability and predictability  for the shipbuilder 
and its vendor base.  
Accordingly,  not  later  than  October  1,  2019,  the  committee  directs  the  Secretary  of  the 
Navy to submit a report to the congressional defense committees on the merits of pursuing 
a block buy acquisition strategy for LHA-9 and LHA-10.  
Congressional Research Service  
 
15 
 link to page 16 Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
This report shall include a business case analysis comparing the cost and schedule of single 
ship contracts for LHA-9 and LHA-10 with a block buy contract for such ships as well as 
a description of other key considerations that the Secretary deems appropriate. 
If the business case analysis shows that pursuing a block buy strategy for LHA-9 and LHA-
10 has merit, the committee strongly encourages the Secretary to consider inclusion of such 
a proposal in the Navy's budget request for fiscal year 2021. 
Acquisition strategy for LPD Flight II-class ships 
The committee notes that the Navy estimates that $4.0 billion will be saved using a block 
buy acquisition strategy for the procurement of CVN-80 and CVN-81. 
The committee believes that a block buy or multiyear procurement approach for LPD Flight 
II-class amphibious transport ships could provide substantial cost savings as well as needed 
stability and predictability for the shipbuilder and its vendor base. 
Accordingly,  not  later  than  October  1,  2019,  the  committee  directs  the  Secretary  of  the 
Navy to submit a report to the congressional defense committees on the merits of pursuing 
a block buy or multiyear procurement acquisition strategy for LPD Flight II-class ships. 
This report shall include a business case analysis comparing the cost and schedule of single 
ship contracts with a block buy or multiyear contract for such ships as well as a description 
of other key considerations that the Secretary deems appropriate. 
If the business case analysis  shows that pursuing a block  buy or  multiyear procurement 
strategy  for  LPD  Flight  II-class  ships  has  merit,  the  committee  strongly  encourages  the 
Secretary to consider inclusion of such a proposal in the Navy's budget request for fiscal 
year 2021. (Pages 33-34) 
FY2020 DOD Appropriations Act (H.R. 2968) 
House 
The House Appropriations Committee, in its report (H.Rept. 116-84 of May 23, 2019) on H.R. 
2968, recommended the funding levels shown in the HAC column of Table 4. The recommended 
reduction of $247.1 million in LPD-17 Flight II advance procurement funding (the entire 
requested amount) is for “Advance procurement [that was] funded in fiscal year 2019.” (Page 
175) 
 
 
Author Information 
 
Ronald O'Rourke 
   
Specialist in Naval Affairs 
    
 
 
Congressional Research Service  
 
16 
Navy LPD-17 Flight II Amphibious Ship Program: Background and Issues for Congress 
 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan 
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and 
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other 
than public understanding of information that has been provided by CRS to Members of Congress in 
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not 
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in 
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or 
material from a third party, you may need to obtain the permission of the copyright holder if you wish to 
copy or otherwise use copyrighted material. 
Congressional Research Service  
R43543 · VERSION 58 · UPDATED 
17