

 
Navy Ford (CVN-78) Class Aircraft Carrier 
Program: Background and Issues for Congress 
Updated March 14, 2019 
Congressional Research Service 
https://crsreports.congress.gov 
RS20643 
 
  
 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Summary 
CVN-78, CVN-79, CVN-80, and CVN-81 are the first four ships in the Navy’s new Gerald R. 
Ford (CVN-78) class of nuclear-powered aircraft carriers (CVNs).  
CVN-78 (named for Gerald R. Ford) was procured in FY2008. The Navy’s proposed FY2019 
budget estimates the ship’s procurement cost at $12,964.0 million (i.e., about $13.0 billion) in 
then-year dollars. The ship received advance procurement (AP) funding in FY2001-FY2007 and 
was fully funded in FY2008-FY2011 using congressionally authorized four-year incremental 
funding. To help cover cost growth on the ship, the ship received an additional $1,394.9 million 
in FY2014-FY2016 and FY2018 cost-to-complete procurement funding. The ship was delivered 
to the Navy on May 31, 2017, and was commissioned into service on July 22, 2017. 
CVN-79 (named for John F. Kennedy) was procured in FY2013. The Navy’s proposed FY2019 
budget estimates the ship’s procurement cost at $11,341.4 million (i.e., about $11.3 billion) in 
then-year dollars. The ship received AP funding in FY2007-FY2012, and was fully funded in 
FY2013-FY2018 using congressionally authorized six-year incremental funding. The ship is 
scheduled for delivery to the Navy in September 2024. 
CVN-80 (named Enterprise) was procured in FY2018. The Navy’s proposed FY2019 budget 
estimated the ship’s procurement cost at $12,601.7 million (i.e., about $12.6 billion) in then-year 
dollars. The ship received AP funding in FY2016 and FY2017, and the Navy plans to fully fund 
the ship in FY2018-FY2023 using congressionally authorized six-year incremental funding. The 
Navy’s proposed FY2019 budget requested $1,598.2 million in procurement funding for the ship. 
The ship is scheduled for delivery to the Navy in September 2027. 
CVN-81 (not yet named) was scheduled to be procured in FY2023, but the Navy’s FY2020 
budget submission changes the ship’s year of procurement to FY2020 as a consequence of the 
two-ship procurement of CVN-80 and CVN-81 discussed in the next paragraph. The Navy’s 
FY2019 budget submission, which predated the two-ship procurement for CVN-80 and CVN-81, 
estimated the ship’s procurement cost at $15,088.0 million (i.e., about $15.1 billion) in then-year 
dollars. Under the Navy’s FY2019 budget submission, the Navy planned to request AP funding 
for CVN-81 in FY2021 and FY2022, and then fully fund the ship in FY2023-FY2028 using 
congressionally authorized six-year incremental funding. Under the Navy’s FY2019 budget 
submission, the ship was scheduled for delivery to the Navy in September 2032. 
Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/P.L. 115-232 of August 13, 2018) permits the Navy, after the Department of Defense 
(DOD) makes certain certifications to Congress, to add CVN-81 to the existing contract for 
building CVN-80. DOD provided the required certification on December 31, 2018. On January 
31, 2019, the Navy announced that it had awarded a two-ship fixed-price contract for CVN-80 
and CVN-81 to Huntington Ingalls Industries/Newport News Shipbuilding (HII/NNS), the 
shipyard that builds the Navy’s aircraft carriers. This two-ship contract can be viewed as a two-
ship block buy contract. 
Compared to the estimated procurement costs shown above, DOD estimates that the two-ship 
contract will reduce the cost of CVN-80 by $399.7 million and the cost of CVN-81 by $2,637.0 
million, for a combined reduction of $3,036.7 million (i.e., about $3.0 billion). Using higher 
estimated baseline costs for CVN-80 and CVN-81 taken from a December 2017 Navy business 
case analysis, DOD estimates that the two-ship contract will reduce the cost of CVN-80 by $924 
million and the cost of CVN-81 by $3,086 million, for a combined reduction of $4,010 million 
(i.e., about $4.0 billion). 
Congressional Research Service 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Oversight issues for Congress for the CVN-78 program for FY2019 include the following: 
  whether to approve, reject, or modify the Navy’s FY2020 procurement funding 
request for the CVN-78 program; 
  the Navy’s proposal, as part of its FY2020 budget submission, to not fund the 
mid-life nuclear refueling overhaul (called a Refueling Complex Overhaul, or 
RCOH) for the aircraft carrier Harry S. Truman (CVN-75), and to instead retire 
the ship around FY2024 and also deactivate one of the Navy’s carrier air wings at 
about the same time; 
  the date for achieving the Navy’s 12-ship force-level goal for aircraft carriers; 
  cost growth in the CVN-78 program, Navy efforts to stem that growth, and Navy 
efforts to manage costs so as to stay within the program’s cost caps; 
  Navy efforts to complete the construction, testing, and certification of the weapon 
elevators on CVN-78; 
  additional CVN-78 program issues that were raised in a December 2018 report 
from the Department of Defense’s (DOD’s) Director of Operational Test and 
Evaluation (DOT&E); 
  whether to conduct the shock trial for the CVN-78 class in the near term, on the 
lead ship in the class, or years later, on the second ship in the class; and 
  whether the Navy should shift at some point from procuring large-deck, nuclear-
powered carriers like the CVN-78 class to procuring smaller aircraft carriers. 
Congressional Research Service 
 link to page 6  link to page 6  link to page 6  link to page 6  link to page 6  link to page 7  link to page 7  link to page 7  link to page 7  link to page 8  link to page 9  link to page 9  link to page 9  link to page 9  link to page 10  link to page 11  link to page 11  link to page 11  link to page 14  link to page 15  link to page 16  link to page 18  link to page 18  link to page 18  link to page 18  link to page 21  link to page 21  link to page 21  link to page 22  link to page 24  link to page 25  link to page 29  link to page 32  link to page 33  link to page 33  link to page 34  link to page 35  link to page 38  link to page 38  link to page 38  link to page 39  link to page 39  link to page 39  link to page 39  link to page 43  link to page 44 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Contents 
Introduction ..................................................................................................................................... 1 
Background ..................................................................................................................................... 1 
Current Navy Aircraft Carrier Force ......................................................................................... 1 
Statutory Requirements for Numbers of Carriers and Carrier Air Wings ................................. 1 
Requirement to Maintain Not Less Than 11 Carriers ......................................................... 1 
Requirement to Maintain a Minimum of Nine Carrier Air Wings ...................................... 2 
Navy Force-Level Goal of 12 Carriers ...................................................................................... 2 
12-Carrier Goal Established December 2016 ..................................................................... 2 
Planned and Potential Dates for Achieving 12-Carrier Force ............................................. 2 
Incremental Funding Authority for Aircraft Carriers ................................................................ 3 
Aircraft Carrier Construction Industrial Base ........................................................................... 4 
Gerald R. Ford (CVN-78) Class Program ................................................................................. 4 
Overview ............................................................................................................................. 4 
CVN-78 (Gerald R. Ford) .................................................................................................. 4 
CVN-79 (John F. Kennedy) ................................................................................................ 5 
CVN-80 (Enterprise) .......................................................................................................... 6 
CVN-81 (Not Yet Named) .................................................................................................. 6 
Two-Ship Contract for CVN-80 and CVN-81 .................................................................... 6 
Program Procurement Funding ........................................................................................... 9 
Program Procurement Cost Cap ........................................................................................ 10 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget ............................. 11 
Issues for Congress for FY2020 .................................................................................................... 13 
FY2020 Funding Request ....................................................................................................... 13 
Reported FY2020 Proposal to Not Fund CVN-75 Refueling Complex Overhaul 
(RCOH) and Deactivate a Carrier Air Wing ........................................................................ 13 
Date for Achieving a 12-Carrier Force .................................................................................... 16 
Cost Growth and Managing Costs within Program Cost Caps ............................................... 16 
Overview ........................................................................................................................... 16 
Recent Related Legislative Provisions .............................................................................. 17 
Sources of Risk of Cost Growth and Navy Actions to Control Cost ................................ 19 
CVN-78 Weapons Elevators ................................................................................................... 20 
Issues Raised in December 2018 DOT&E Report .................................................................. 24 
Shock Trial .............................................................................................................................. 27 
Navy Study on Smaller Aircraft Carriers ................................................................................ 28 
Overview ........................................................................................................................... 28 
Navy Study Initiated in 2015 ............................................................................................ 29 
Report Required by Section 128 of P.L. 114-92 ............................................................... 30 
February 2019 Press Report .............................................................................................. 33 
Legislative Activity for FY2019 .................................................................................................... 33 
July 11, 2018, Reprogramming Request ................................................................................. 33 
Summary of Congressional Action on FY2019 Funding Request .......................................... 34 
National Defense Authorization Act for Fiscal Year 2019/John S. McCain National 
Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/S. 2987/P.L. 115-232) ........... 34 
House Committee Report .................................................................................................. 34 
House Floor Action ........................................................................................................... 38 
Senate ................................................................................................................................ 39 
Congressional Research Service 
 link to page 47  link to page 52  link to page 52  link to page 52  link to page 53  link to page 53  link to page 54  link to page 10  link to page 15  link to page 17  link to page 19  link to page 39  link to page 55  link to page 61  link to page 90  link to page 108 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Conference ........................................................................................................................ 42 
FY2019 DOD Appropriations Act (H.R. 6157/S. 3159/Division A of H.R. 6157/P.L. 
115-245) ............................................................................................................................... 47 
House Committee Report .................................................................................................. 47 
House Floor Action ........................................................................................................... 48 
Senate ................................................................................................................................ 48 
Conference ........................................................................................................................ 49 
 
Figures 
Figure 1. USS Gerald R. Ford (CVN-78) ....................................................................................... 5 
  
Tables 
Table 1. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2023 ........................... 10 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 .......................... 12 
Table 3. Funding for CVN-75 RCOH in FY2019 Budget Submission ......................................... 14 
Table 4. Congressional Action on FY2019 Funding Request........................................................ 34 
  
Appendixes 
Appendix A. Background Information on Two-Ship and Three-Ship Block Buys ....................... 50 
Appendix B. Cost Growth and Managing Costs Within Program Cost Caps ............................... 56 
Appendix C. March 2013 Navy Report to Congress on Construction Plan for CVN-79 .............. 85 
 
Contacts 
Author Information ...................................................................................................................... 103 
 
Congressional Research Service 
 link to page 6 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Introduction 
This report provides background information and potential oversight issues for Congress on the 
Gerald R. Ford (CVN-78) class aircraft carrier program. The Navy’s proposed FY2019 budget 
requested a total of $1,598.2 million in procurement funding for the program. Congress’s 
decisions on the CVN-78 program could substantially affect Navy capabilities and funding 
requirements and the shipbuilding industrial base. 
For an overview of the strategic and budgetary context in which the CVN-78 class program and 
other Navy shipbuilding programs may be considered, see CRS Report RL32665, Navy Force 
Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke.1 
Background 
Current Navy Aircraft Carrier Force 
The Navy’s current aircraft carrier force consists of 11 nuclear-powered ships, including 10 
Nimitz-class ships (CVNs 68 through 77) that entered service between 1975 and 2009, and one 
Gerald R. Ford (CVN-78) class ship that was commissioned into service on July 22, 2017.2  
Statutory Requirements for Numbers of Carriers and Carrier Air 
Wings 
Requirement to Maintain Not Less Than 11 Carriers  
10 U.S.C. 8062(b) requires the Navy to maintain a force of not less than 11 operational aircraft 
carriers.3 The requirement for the Navy to maintain not less than a certain number of operational 
aircraft carriers was established by Section 126 of the FY2006 National Defense Authorization 
Act (H.R. 1815/P.L. 109-163 of January 6, 2006), which set the number at 12 carriers. The 
requirement was changed from 12 carriers to 11 carriers by Section 1011(a) of the FY2007 John 
Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006).4 
                                                 
1 See also CRS Report R43838, A Shift in the International Security Environment: Potential Implications for Defense—
Issues for Congress, by Ronald O'Rourke, and CRS Report R44891, U.S. Role in the World: Background and Issues for 
Congress, by Ronald O'Rourke and Michael Moodie.  
2 The George H. W. Bush (CVN-77), the final Nimitz-class ship, was procured in FY2001 and commissioned into 
service on January 10, 2009. CVN-77 replaced Kitty Hawk (CV-63), which was the Navy’s last remaining 
conventionally powered carrier. (The Kitty Hawk was decommissioned on January 31, 2009.) The commissioning into 
service of CVN-78 ended a period during which the carrier force had declined to 10 ships that began on December 1, 
2012, with the inactivation of the one-of-a-kind nuclear-powered aircraft carrier Enterprise (CVN-65), a ship that 
entered service in 1961. 
3 10 U.S.C. 8062 was previously numbered as 10 U.S.C. 5062. It was renumbered as 10 U.S.C. 8062 by Section 807 of 
the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-232 of August 13, 
2018), which directed a renumbering of sections and titles of Title 10 relating to the Navy and Marine Corps. (Sections 
806 and 808 of P.L. 115-232 directed a similar renumbering of sections and titles relating to the Air Force and Army, 
respectively.) 
4 As mentioned in footnote 2, the carrier force dropped from 11 ships to 10 ships between December 1, 2017, when 
Enterprise (CVN-65) was inactivated, and July 22, 2017, when CVN-78 was commissioned into service. Anticipating 
the gap between the inactivation of CVN-65 and the commissioning of CVN-78, the Navy asked Congress for a 
temporary waiver of 10 U.S.C. 8062(b) to accommodate the period between the two events. Section 1023 of the 
Congressional Research Service  
 
1 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Requirement to Maintain a Minimum of Nine Carrier Air Wings 
10 U.S.C. 8062(e), which was added by Section 1042 of the FY2017 National Defense 
Authorization Act (S. 2943/P.L. 114-328 of December 23, 2016), requires the Navy to maintain a 
minimum of nine carrier air wings.5 
Navy Force-Level Goal of 12 Carriers 
12-Carrier Goal Established December 2016 
In December 2016, the Navy released a force-level goal for achieving and maintaining a fleet of 
355 ships, including 12 aircraft carriers6—one more than the minimum of 11 carriers required by 
10 U.S.C. 8062(b). This was the first Navy force-level goal to call for 12 (rather than 11) carriers 
since a 2002-2004 Navy force-level goal for a fleet of 375 ships.7 
Planned and Potential Dates for Achieving 12-Carrier Force 
Given the time needed to build a carrier and the projected retirement dates of existing carriers, 
increasing the carrier force from 11 ships to 12 ships on a sustained basis would take a number of 
years: 
  Procuring carriers on 3-year centers—that is, procuring one carrier every three 
years—would achieve a 12-carrier force on a sustained basis by about 2030, 
unless the service lives of one or more existing carriers were substantially 
extended. 
  Procuring carriers on 3.5-year centers (i.e., a combination of 3- and 4-year 
centers) would achieve a 12-carrier force on a sustained basis no earlier than 
about 2034, unless the service lives of one or more existing carriers were 
substantially extended. 
  Procuring carriers on 4-year centers would achieve a 12-carrier force on a 
sustained basis by about 2063—almost 30 years later than under 3.5-year 
                                                 
FY2010 National Defense Authorization Act (H.R. 2647/P.L. 111-84 of October 28, 2009) authorized the waiver, 
permitting the Navy to have 10 operational carriers between the inactivation of CVN-65 and the commissioning of 
CVN-78. 
5 10 U.S.C. 8062(e) states the following: 
The Secretary of the Navy shall ensure that- 
(1) the Navy maintains a minimum of 9 carrier air wings until the earlier of- 
(A) the date on which additional operationally deployable aircraft carriers can fully support a 10th 
carrier air wing; or 
(B) October 1, 2025; 
(2) after the earlier of the two dates referred to in subparagraphs (A) and (B) of paragraph (1), the 
Navy maintains a minimum of 10 carrier air wings; and 
(3) for each such carrier air wing, the Navy maintains a dedicated and fully staffed headquarters. 
6 For more on the 355-ship force-level goal, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: 
Background and Issues for Congress, by Ronald O'Rourke.  
7 See the appendix entitled “Earlier Navy Force-Structure Goals Dating Back to 2001” in CRS Report RL32665, Navy 
Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke. 
Congressional Research Service  
 
2 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
centers—unless the service lives of one or more existing carriers were 
substantially extended.8 
The Navy’s FY2019 30-year (FY2019-FY2048) shipbuilding plan shifts aircraft carrier 
procurement from 5-year centers to 4-year centers following the planned procurement of CVN-82 
in FY2028 (i.e., the next carrier would be procured in FY2032, the one after that in FY2036, and 
so on). Consistent with the final bullet point above, Navy officials state that under this plan, a 12-
carrier force would be achieved on a sustained basis in the 2060s, unless the service lives of one 
or more existing carriers were substantially extended. More specifically, the Navy projects that 
under the FY2019 30-year shipbuilding plan, the carrier force would reach 12 ships in FY2022-
FY2024, then drop back to 11 ships and remain there in subsequent years, except for FY2040, 
FY2042-FY2044, and FY2046-FY2047, when it would drop to 10 carriers, and FY2048 (the final 
year in the 30-year period), when it would drop to 9 carriers.9  
Incremental Funding Authority for Aircraft Carriers 
Under incremental funding, some of the funding needed to fully fund a ship is provided in one or 
more years after the year in which the ship is procured. In recent years, Congress has authorized 
DOD to use incremental funding for procuring certain Navy ships, most notably aircraft 
carriers:10 
  Section 121 of the FY2007 John Warner National Defense Authorization Act 
(H.R. 5122/P.L. 109-364 of October 17, 2006) granted the Navy the authority to 
use four-year incremental funding for CVNs 78, 79, and 80. Under this authority, 
the Navy could fully fund each of these ships over a four-year period that 
includes the ship’s year of procurement and three subsequent years. 
  Section 124 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 
112-81 of December 31, 2011) amended Section 121 of P.L. 109-364 to grant the 
Navy the authority to use five-year incremental funding for CVNs 78, 79, and 80. 
Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice 
applied to CVNs 79 and 80. 
  Section 121 of the FY2013 National Defense Authorization Act (H.R. 4310/P.L. 
112-239 of January 2, 2013) amended Section 121 of P.L. 109-364 to grant the 
Navy the authority to use six-year incremental funding for CVNs 78, 79, and 80. 
Since CVN-78 was fully funded in FY2008-FY2011, the provision in practice 
applies to CVNs 79 and 80. 
  Section 121(c) of the John S. McCain National Defense Authorization Act for 
Fiscal Year 2019 (H.R. 5515/ P.L. 115-232 of August 13, 2018) authorized 
incremental funding to be used for making payments under a contract for the 
construction of CVN-81. 
                                                 
8 Source for 2063 date in relation to four-year centers: Congressional Budget Office (CBO), in a telephone consultation 
with CRS on May 18, 2017. 
9 For a table showing projected navy force levels under the Navy’s 30-year shipbuilding plan, see CRS Report 
RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by Ronald O'Rourke. 
10 For more on full funding and incremental funding, see CRS Report RL31404, Defense Procurement: Full Funding 
Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report 
RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by 
Ronald O'Rourke. 
Congressional Research Service  
 
3 
 link to page 10 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Aircraft Carrier Construction Industrial Base 
All U.S. aircraft carriers procured since FY1958 have been built by Huntington Ingalls 
Industries/Newport News Shipbuilding (HII/NNS), of Newport News, VA. HII/NNS is the only 
U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The aircraft carrier 
construction industrial base also includes roughly 2,000 supplier firms in 46 states.11 
Gerald R. Ford (CVN-78) Class Program 
Overview 
The Gerald R. Ford (CVN-78) class carrier design (Figure 1) is the successor to the Nimitz-class 
carrier design.12 The Ford-class design uses the basic Nimitz-class hull form but incorporates 
several improvements, including features permitting the ship to generate more aircraft sorties per 
day, more electrical power for supporting ship systems, and features permitting the ship to be 
operated by several hundred fewer sailors than a Nimitz-class ship, reducing 50-year life-cycle 
operating and support (O&S) costs for each ship by about $4 billion compared to the Nimitz-class 
design, the Navy estimates. Navy plans call for procuring at least four Ford-class carriers—CVN-
78, CVN-79, CVN-80, and CVN-81. 
CVN-78 (Gerald R. Ford) 
CVN-78, which was named for President Gerald R. Ford in 2007,13 was procured in FY2008. The 
Navy’s proposed FY2019 budget estimates the ship’s procurement cost at $12,964.0 million (i.e., 
about $13.0 billion) in then-year dollars. The ship received advance procurement (AP) funding in 
FY2001-FY2007 and was fully funded in FY2008-FY2011 using congressionally authorized 
four-year incremental funding. To help cover cost growth on the ship, the ship received an 
additional $1,394.9 million in FY2014-FY2016 and FY2018 cost-to-complete procurement 
funding. The ship was delivered to the Navy on May 31, 2017, and was commissioned into 
service on July 22, 2017. 
In addition to the funding discussed in the previous paragraph, a DOD reprogramming request 
dated July 11, 2018, requested that $62.7 million be reprogrammed to the CVN-78 program to 
cover cost growth on CVN-78.14 
                                                 
11 Source for figures of 2,000 supplier firms in 46 states: Jennifer Boykin, president of HII/NNS, as quoted in Marcus 
Weisgerber, “US Navy Places First 2-Carrier Order in Three Decades,” Defense One, January 31, 2019. 
12 The CVN-78 class was earlier known as the CVN-21 class, which meant nuclear-powered aircraft carrier for the 21st 
century.  
13 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of 
Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced that 
CVN-78 would be so named. CVN-78 and other carriers built to the same design are consequently referred to as Ford 
(CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: Background for 
Congress, by Ronald O'Rourke. 
14 The $62.7 million includes 
 
$12.7 million for “re-baselining the Advanced Weapons Elevator program to address continuing technical 
difficulties”; 
 
$30.0 million for “engineering, tooling, and repair of Main Thrust Bearings” in the ship’s propulsion train; 
 
$11.0 million for “emergent technical issues and correction of deficiencies identified during operational 
testing and extension of the Post-Shakedown Availability [PSA] duration to accomplish required scope and 
Congressional Research Service  
 
4 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Figure 1. USS Gerald R. Ford (CVN-78) 
 
Source: Navy photograph dated April 8, 2017, accessed October 3, 2017, at http://www.navy.mil/
view_image.asp?id=234835. 
CVN-79 (John F. Kennedy) 
CVN-79, which was named for President John F. Kennedy on May 29, 2011,15 was procured in 
FY2013. The Navy’s proposed FY2019 budget estimates the ship’s procurement cost at 
$11,341.4 million (i.e., about $11.3 billion) in then-year dollars. The ship received AP funding in 
FY2007-FY2012, and was fully funded in FY2013-FY2018 using congressionally authorized six-
year incremental funding. The ship is scheduled for delivery to the Navy in September 2024. 
                                                 
repair of the propulsion train components”; and 
 
$9.0 million “to cover the increase cost of deferred work, labor and material.” 
The $62.7 million would be reprogrammed from FY2011 procurement funding for the DDG-51 destroyer program. 
(See page 85 of 85 [i.e., the final page] of the reprogramming request. The document was posted by InsideDefense.com 
[subscription required] on July 16, 2018. See also David B. Larter, “US Navy Asks Congress to Shift Millions of 
Dollars to Fix High-Tech Supercarrier,” Defense News, July 18, 2018; Jason Sherman, “Pentagon Seeks Additional 
Funding for CVN-78, Breaching Current Statutory Cost Cap,” Inside Defense [Daily News], July 19, 2018.) 
15 See “Navy Names Next Aircraft Carrier USS John F. Kennedy,” Navy News Service, May 29, 2011, accessed online 
on June 1, 2011, at http://www.navy.mil/search/display.asp?story_id=60686. See also Peter Frost, “U.S. Navy’s Next 
Aircraft Carrier Will Be Named After The Late John F. Kennedy,” Newport News Daily Press, May 30, 2011. CVN-79 
is the second ship to be named for President John F. Kennedy. The first, CV-67, was the last conventionally powered 
carrier procured for the Navy. CV-67 was procured in FY1963, entered service in 1968, and was decommissioned in 
2007. 
Congressional Research Service  
 
5 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
CVN-80 (Enterprise) 
CVN-80, which was named Enterprise on December 1, 2012,16 was procured in FY2018. The 
Navy’s proposed FY2019 budget estimates the ship’s procurement cost at $12,601.7 million (i.e., 
about $12.6 billion) in then-year dollars.17 The ship received AP funding in FY2016 and FY2017, 
and the Navy plans to fully fund the ship in FY2018-FY2023 using congressionally authorized 
six-year incremental funding. The Navy’s proposed FY2019 budget requested $1,598.2 million in 
procurement funding for the ship. The ship is scheduled for delivery to the Navy in September 
2027. 
CVN-81 (Not Yet Named) 
CVN-81 (not yet named) was scheduled to be procured in FY2023, but the Navy’s FY2020 
budget submission changes the ship’s year of procurement to FY2020 as a consequence of the 
two-ship procurement of CVN-80 and CVN-81 discussed in the next section.18 The Navy’s 
FY2019 budget submission, which predated the two-ship procurement for CVN-80 and CVN-81, 
estimated the ship’s procurement cost at $15,088.0 million (i.e., about $15.1 billion) in then-year 
dollars. Under the Navy’s FY2019 budget submission, the Navy planned to request AP funding 
for CVN-81 in FY2021 and FY2022, and then fully fund the ship in FY2023-FY2028 using 
congressionally authorized six-year incremental funding. Under the Navy’s FY2019 budget 
submission, the ship was scheduled for delivery to the Navy in September 2032. 
Two-Ship Contract for CVN-80 and CVN-81 
Section 121(a)(2) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/ P.L. 115-232 of August 13, 2018) permits the Navy, after the Department of Defense 
(DOD) makes certain certifications to Congress, to add CVN-81 to the existing contract for 
building CVN-80. DOD provided the required certification on December 31, 2018. On January 
31, 2019, the Navy announced that it had awarded a two-ship fixed-price incentive (firm target) 
(FPIF) contract for CVN-80 and CVN-81 to Huntington Ingalls Industries/Newport News 
Shipbuilding (HII/NNS), the shipyard that builds the Navy’s aircraft carriers.19 
                                                 
16 The Navy made the announcement of CVN-80’s name on the same day that it deactivated the 51-year-old aircraft 
carrier CVN-65, also named Enterprise. (“Enterprise, Navy’s First Nuclear-Powered Aircraft Carrier, Inactivated,” 
Navy News Service, December 1, 2012; Hugh Lessig, “Navy Retires One Enterprise, Will Welcome Another,” Newport 
News Daily Press, December 2, 2012.) CVN-65 was the eighth Navy ship named Enterprise; CVN-80 is to be the 
ninth. 
17 The Department of the Navy states that “the Department of Navy’s PB 2019 SCN end cost position for CVN 80 is 
$12,601.713M as explained on the P -40 SCN budget exhibit note in the description section. It stated: ‘CVN 80 end 
cost to be reduced $300M with expected FY18 Congressional adjustment in enacted appropriations bill. End cost is 
$12,601.713M after reduction.’” Source: Navy table of annual funding for CVNs 78 through 81 for FY2001-FY2023, 
provided to CRS by Navy Office of Legislative Affairs, June 19, 2018. 
18 As discussed in the next section, Congress granted the Navy authority for the two-ship procurement as part of the 
John S. McCain National Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-232 of August 13, 
2018), and the Navy awarded the two-ship contract on January 31, 2019 (i.e., during FY2019). On this basis, DOD 
arguably could have designated FY2019 as the year of procurement for CVN-81. DOD instead chose to designate 
FY2020 as the ship’s year of procurement, perhaps because DOD’s FY2020 budget submission was the first DOD 
budget submission to reflect the implementation of the two-ship procurement. 
19 See Office of the Navy Chief of Information, “Navy Awards Contract for Construction of Two Carriers,” Navy News 
Service, January 31, 2019; Megan Eckstein, “UPDATED: Navy Awards 2-Carrier Contract to Newport News 
Shipbuilding,” USNI News, January 31, 2019; Marcus Weisgerber, “US Navy Places First 2-Carrier Order in Three 
Decades,” Defense One, January 31, 2019; David B. Larter, “US Navy Signs Mammoth Contract with Huntington 
Congressional Research Service  
 
6 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
This two-ship contract can be viewed as a two-ship block buy contract, since CVN-80 was 
procured in FY2018 and CVN-81 is recorded as a ship procured in FY2020.20 The option for 
procuring two CVN-78 class carriers under a two-ship block buy contract has been discussed in 
this CRS report since April 2012.21 The Navy’s previous two-ship aircraft carrier procurements 
occurred in FY1983 (for CVN-72 and CVN-73) and FY1988 (for CVN-74 and CVN-75). In both 
of those cases, however, the two ships were fully funded within a single fiscal year, making them 
simple two-ship purchases (akin, for example, to procuring two Virginia-class attack submarines 
or two DDG-51 class destroyers in a given fiscal year) rather than two-ship block buys (i.e., 
contracts spanning the procurement of end items procured across more than one fiscal year). 
Compared to figures in the Navy’s FY2019 budget submission, DOD estimates that the two-ship 
contract will reduce the cost of CVN-80 by $399.7 million and the cost of CVN-81 by $2,637.0 
million, for a combined reduction of $3,036.7 million (i.e., about $3.0 billion).22 (DOD 
characterizes the combined reduction as “nearly $3 billion.”23) Using higher estimated baseline 
costs for CVN-80 and CVN-81 taken from a December 2017 Navy business case analysis, DOD 
estimates that the two-ship contract will reduce the cost of CVN-80 by $924 million and the cost 
of CVN-81 by $3,086 million, for a combined reduction of $4,010 million (i.e., about $4.0 
billion).24 These figures are all expressed in then-year dollars, meaning dollars that are not 
adjusted for inflation. 
Regarding the difference between a savings of about $3.0 billion from the figures in the Navy’s 
FY2019 budget submission and a savings of about $4.0 billion from the December 2017 Navy 
business case analysis, a February 5, 2019, press report quoted a Navy spokesman as stating that 
the Navy’s FY2019 budget submission “already accounted for at least $1B [$1 billion] of 
potential savings, a two-CVN buy would save an additional $3B [$3 billion].”25 This suggests 
that the Navy, in preparing its FY2019 budget submission, may have anticipated that it would 
receive from Congress authority for implementing some kind of combined purchase (such as, 
perhaps, a combined purchase of materials) for CVN-80 and CVN-81. 
DOD further states that “the Department of Defense’s Office of Cost Assessment and Program 
Evaluation (CAPE) developed an Independent Estimate of Savings for the two-ship procurement 
                                                 
Ingalls for Two Aircraft Carriers,” Defense News, January 31, 2019; Rich Abott, “Navy Awards HII $15 Billion In 
Two Carrier Buy,” Defense Daily, February 1, 2019. 
20 For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy 
Contracting in Defense Acquisition: Background and Issues for Congress, by Ronald O'Rourke and Moshe Schwartz. 
21 See the section entitled “Potential Two-Ship Block Buy on CVN-79 and CVN-80” in the April 4, 2012, version of 
CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress, by 
Ronald O'Rourke. In more recent years, this section was modified to discuss the option in connection with CVN-80 and 
CVN-81. 
22 Source: CRS calculation based on costs for single-ship purchases as presented in Navy’s FY2019 budget submission 
and costs for two-ship purchase as presented in Department of Defense, FORD Class Aircraft Carrier Certification, 
CVN 80 and CVN 81 Two Ship Procurement Authority, as Required by Section 121(b) of the John S. McCain National 
Defense Authorization Act for Fiscal Year 2019 (P.L. 115-232), November 2018, p. 4 (Table 1). 
23 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, p. 4. 
24 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, p. 4 (Table 1). 
25 Justin Katz, “CAPE Estimates Navy’s Two-Ship Buy Will Save $3.1B--$900 Million Less Than Service 
Projections,” InsideDefense.com, February 5, 2019 (subscription required). 
Congressional Research Service  
 
7 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
and forecast savings of $3.1 billion ([in] Then-Year [dollars]), or approximately 11 percent.... The 
primary differences between [the] CAPE and Navy estimates of savings are in Government 
Furnished Equipment26 and production change orders.”27 Within the total estimated combined 
reduction in cost, HII/NNS reportedly expects to save up to $1.6 billion in contractor-furnished 
equipment.28 
A November 2018 report that was submitted as an attachment to DOD’s December 31, 2018, 
certification stated the following regarding the sources of cost reduction for the two-ship contract: 
The  CVN  80  and  CVN  81  two-ship  buy  expands  and  improves  upon  the  affordability 
initiatives  identified  in  the  Annual  Report  on  Cost  Reduction  Efforts  for  JOHN  F. 
KENNEDY (CVN 79) and ENTERPRISE (CVN 80) as required by section 126(c) of the 
National  Defense  Authorization  Act  for  Fiscal  Year  2017  (Public  Law  114-328). 
Production  saving  initiatives  for  single-ship  buys  included  use  of  unit  families  in 
construction, pre-outfitting and complex assemblies which move work to a more efficient 
workspace environment, reduction in the number of superlifts,29 and facility investments 
which  improve  the  shipbuilder  trade  effectiveness.  A  two-ship  buy  assumes  four  years 
between  ship  deliveries  which  allows  more  schedule  overlap,  and  therefore  more  shop-
level and assembly-level production efficiencies than two single-ship buys. 
Procuring two ships to a single technical baseline reduces the requirement for engineering 
labor  hours  when  compared  to  single-ship  estimates.  The  ability  to  rollover  production 
support  engineering  and  planning  products  maximizes  savings  while  recognizing  the 
minimum amount of engineering labor necessary to address obsolescence and regulatory 
changes on CVN 81. The two-ship agreement with the shipbuilder achieves a 55 percent 
reduction in construction support engineering hours on CVN 81 and greater than 18 percent 
reduction in production support and planning hours compared to single ship procurements. 
The two-ship procurement strategy allows for serial production opportunities that promote 
tangible learning and reduced shop and machine set-up times. It allows for efficient use of 
production facilities, re-use of production jigs and fixtures, and level loading of key trades. 
The continuity of  work allows for reductions in supervision, services and support costs. 
The result of these efficiencies is a production man-hours step down that is equivalent to 
an 82 percent learning curve since CVN 79. 
Key  to  achieving  these  production  efficiencies  is  Integrated  Digital  Shipbuilding  (iDS). 
The Navy's Research, Development, Test, and Evaluation (RDT&E) and the shipbuilder's 
investment  in  iDS,  totaling  $631  million,  will  reduce  the  amount  of  production  effort 
required to build FORD Class carriers. The two-ship buy will accelerate the benefits of this 
approach. The ability to immediately use the capability on CVN 81 would lead to a further 
reduction in touch labor and services in affected value streams. The two-ship agreement 
with  the  shipbuilder  represents  a  production  man-hours  reduction  of  over  seven  percent 
based  on  iDS  efficiencies.  Contractual  authority  for  two  ships  allows  the  shipbuilder  to 
maximize  economic  order  quantity  material  procurement.  This  allows  more  efficient 
ordering and scheduling of material deliveries and will promote efficiencies through earlier 
                                                 
26 Government-furnished equipment (GFE) is equipment that the government purchases from supplier firms and then 
provides to the shipbuilder for incorporation into the ships. 
27 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 8-9. 
28 Rich Abott, “Navy Awards HII $15 Billion In Two Carrier Buy,” Defense Daily, February 1, 2019. Contractor-
furnished equipment (CFE) is equipment that the contractor (in this case, HII/NNS) purchases from supplier firms for 
incorporation into the ships. 
29 A superlift is the use of a crane to move a very large section of the ship from the land into its final position on the 
ship. 
Congressional Research Service  
 
8 
 link to page 55  link to page 15 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
ordering,  single  negotiations,  vendor  quotes,  and  cross  program  purchase  orders.  These 
efficiencies  are  expected  to  reduce  material  costs  by  about  six  percent  more  when 
compared  to  single-ship  estimates.  Improved  material  management  and  flexibility  will 
prevent costly production delays.  Furthermore, this provides stability  within the  nuclear 
industrial base, de-risking the COLUMBIA and VIRGINIA Class programs. The two-ship 
buy would provide economic stability to approximately 130,000 workers across 46 States 
within the industrial base. 
Change  order  requirements  are  likewise  reduced  as  Government  Furnished  Equipment 
(GFE) providers will employ planning and procurement strategies based on the common 
technical baseline that minimize configuration changes that must be incorporated on the 
follow ship. Change order budget allocations have been reduced over 25 percent based on 
two-ship strategies. 
In addition to the discrete savings achieved with the shipbuilder, the two-ship procurement 
authority provides our partner GFE providers a similar opportunity to negotiate economic 
order quantity savings and achieve cross program savings when compared to single-ship 
estimates.30 
For additional background information on options for two-ship or three-ship carrier block buys 
that was presented in the main part of this CRS report prior to DOD’s December 31, 2018, two-
ship certification and the Navy’s January 31, 2019, two-ship contract award, see Appendix A. 
Program Procurement Funding 
Table 1 shows procurement funding for CVNs 78, 79, 80, and 81 through FY2023. This table 
does not include the $62.7 million reprogramming request of July 11, 2018, discussed in the 
above section on CVN-78. 
 
 
                                                 
30 Department of Defense, FORD Class Aircraft Carrier Certification, CVN 80 and CVN 81 Two Ship Procurement 
Authority, as Required by Section 121(b) of the John S. McCain National Defense Authorization Act for Fiscal Year 
2019 (P.L. 115-232), November 2018, pp. 6-7. 
Congressional Research Service  
 
9 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 1. Procurement Funding for CVNs 78, 79, 80, and 81 Through FY2023 
(Millions of then-year dollars, rounded to nearest tenth) 
FY 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
Total 
FY01 
21.7 (AP) 
0 
0 
0 
21.7 
FY02 
135.3 (AP) 
0 
0 
0 
135.3 
FY03 
395.5 (AP) 
0 
0 
0 
395.5 
FY04 
1,162.9 (AP) 
0 
0 
0 
1,162.9 
FY05 
623.1 (AP) 
0 
0 
0 
623.1 
FY06 
618.9 (AP) 
0 
0 
0 
618.9 
FY07 
735.8 (AP) 
52.8 (AP) 
0 
0 
788.6 
FY08 
2,685.0 (FF) 
123.5 (AP) 
0 
0 
2,808.5 
FY09 
2,684.6 (FF)  1,210.6 (AP) 
0 
0 
3,895.2 
FY10 
794.0 (FF) 
482.9 (AP) 
0 
0 
1,276.9 
FY11  
1,712.5 (FF) 
902.5 (AP) 
0 
0 
2,615.0 
FY12  
0 
554.8 (AP) 
0 
0 
554.8 
FY13 
0 
491.0 (FF) 
0 
0 
491.0 
FY14  
588.1 (CC) 
917.6 (FF) 
0 
0 
1,505.7 
FY15 
663.0 (CC) 
1,219.4 (FF) 
0 
0 
1,882.4 
FY16 
123.8 (CC) 
1,569.5 (FF) 
862.4 (AP) 
0 
2,555.7 
FY17  
0 
1,241.8 (FF)  1,370.8 (AP) 
0 
2,612.6 
FY18 
20.0 (CC) 
2,561.1 (FF) 
1,569.6 (FF) 
0 
4,150.7 
FY19 (requested) 
0 
0 
1,598.2 (FF) 
0 
1,598.2 
FY20 (programmed) 
0 
0 
2,146.5 (FF) 
0 
2,146.5 
FY21 (programmed) 
0 
0 
2,244.6 (FF) 
995.0 (AP) 
3,239.6 
FY22 (programmed) 
0 
0 
1,343.1(FF) 
1,567.4 (AP) 
2,910.5 
FY23 (projected) 
0 
0 
1,455.5 (FF) 
1,922.9 (FF) 
3,378.4 
Total of above 
12,964.0 
11,327.4 
12,590.6 
4,485.3 
41,367.7 
Ship’s total 
12,964.0 
11,341.4 
12,601.7 
15,088.0 
51,995.1 
estimated cost in 
FY2019 budget 
Source: Table prepared by CRS based on information provided to CRS by Navy Office of Legislative Affairs, 
June 19, 2018. 
Notes: Figures may not add due to rounding. “AP” is advance procurement funding; “FF” is ful  funding; “CC” is 
cost to complete funding (i.e., funding to cover cost growth), which is sometimes abbreviated in Navy documents 
as CTC. The Department of the Navy states that “the Department of Navy's PB 2019 SCN end cost position for 
CVN 80 is $12,601.713M as explained on the P -40 SCN budget exhibit note in the description section. It stated: 
‘CVN 80 end cost to be reduced $300M with expected FY18 Congressional adjustment in enacted 
appropriations bil . End cost is $12,601.713M after reduction.’” Source: Navy table of annual funding for CVNs 
78 through 81 for FY2001-FY2023, provided to CRS by Navy Office of Legislative Affairs, June 19, 2018. 
Program Procurement Cost Cap 
Congress has established procurement cost caps for CVN-78 class aircraft carriers: 
  Section 122 of the FY2007 John Warner National Defense Authorization Act 
(H.R. 5122/P.L. 109-364 of October 17, 2006) established a procurement cost cap 
for CVN-78 of $10.5 billion, plus adjustments for inflation and other factors, and 
a procurement cost cap for subsequent Ford-class carriers of $8.1 billion each, 
plus adjustments for inflation and other factors. The conference report (H.Rept. 
Congressional Research Service  
 
10 
 link to page 17 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
109-702 of September 29, 2006) on P.L. 109-364 discusses Section 122 on pages 
551-552. 
  Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 
113-66 of December 26, 2013) amended the procurement cost cap for the CVN-
78 program to provide a revised cap of $12,887.0 million for CVN-78 and a 
revised cap of $11,498.0 million for each follow-on ship in the program, plus 
adjustments for inflation and other factors (including an additional factor not 
included in original cost cap). 
  Section 122 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 
114-92 of November 25, 2015) further amended the cost cap for the CVN-78 
program to provide a revised cap of $11,398.0 million for each follow-on ship in 
the program, plus adjustment for inflation and other factors, and with a new 
provision stating that, if during construction of CVN-79, the Chief of Naval 
Operations determines that measures required to complete the ship within the 
revised cost cap shall result in an unacceptable reduction to the ship’s operational 
capability, the Secretary of the Navy may increase the CVN-79 cost cap by up to 
$100 million (i.e., to $11.498 billion). If such an action is taken, the Navy is to 
adhere to the notification requirements specified in the cost cap legislation. 
  Section 121(a) of the FY2018 National Defense Authorization Act (H.R. 
2810/P.L. 115-91 of December 12, 2017) further amended the cost cap for the 
CVN-78 program to provide a revised cap of $12,568.0 million for CVN-80 and 
subsequent ships in the program, plus adjustment for inflation and other factors. 
(The cap for CVN-79 was kept at $11,398.0 million, plus adjustment for inflation 
and other factors.) The provision also amended the basis for adjusting the caps 
for inflation, and excluded certain costs from being counted against the caps. 
In an August 2, 2017, letter to the congressional defense committees, then-Acting Secretary of the 
Navy Sean Stackley notified the committees that under subsection (b)(7) of Section 122 of P.L. 
114-92 as amended by Section 121 of P.L. 113-66—a subsection allowing increases to the cost 
cap for CVN-78 for “the amounts of increases or decreases in costs of that ship that are 
attributable solely to an urgent and unforeseen requirement identified as a result of the shipboard 
test program”—he had increased the cost cap for CVN-78 by $20 million, to $12,907.0 million. 
In a May 8, 2018, letter to the congressional defense committees, Secretary of the Navy Richard 
Spencer notified the committees that under subsections (b)(6) and (b)(7) of Section 122 of P.L. 
114-92 as amended by Section 121 of P.L. 113-66—subsections allowing increases to the cost cap 
for CVN-78 for “the amounts of increases or decreases to cost required to correct deficiencies 
that may affect the safety of the ship and personnel or otherwise preclude the ship from safe 
operation and crew certification” and for “the amounts of increases or decreases in costs of CVN 
78 that are attributable solely to an urgent and unforeseen requirement identified as a result of the 
shipboard test program,” respectively—he had increased the cost cap for CVN-78 by $120 
million, to $13,027 million.31 
Changes in Estimated Unit Procurement Costs Since FY2008 Budget 
Table 2 shows changes in the estimated procurement costs of CVNs 78, 79, 80, and 81 since the 
budget submission for FY2008—the year of procurement for CVN-78. 
                                                 
31 A copy of the May 8, 2018, letter was provided to CRS and CBO by the Navy Office of Legislative Affairs on July 
19, 2018. 
Congressional Research Service  
 
11 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, 80, and 81 
(As shown in FY2008-FY2018 budgets, in millions of then-year dollars) 
Budget 
CVN-78 
CVN-79 
CVN-80 
CVN-81 
Est. 
Est. 
Est. 
Schedule
Est. 
proc. 
Scheduled 
proc. 
Scheduled 
proc. 
d FY of 
proc. 
Scheduled 
 
cost 
FY of proc. 
cost 
FY of proc. 
cost 
proc. 
cost 
FY of proc. 
FY08 
10,488.9 
FY08 
9,192.0 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY09 
10,457.9 
FY08 
9,191.6 
FY12 
10,716.8 
FY16 
n/a 
FY21 
FY10 
10,845.8 
FY08 
n/a 
FY13 
n/a 
FY18 
n/a 
FY23 
FY11 
11,531.0 
FY08 
10,413.1 
FY13 
13,577.0 
FY18 
n/a 
FY23 
FY12 
11,531.0 
FY08 
10,253.0 
FY13 
13,494.9 
FY18 
n/a 
FY23 
FY13 
12,323.2 
FY08 
11,411.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY14 
12,829.3 
FY08 
11,338.4 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY15 
12,887.2 
FY08 
11,498.0 
FY13 
13,874.2 
FY18 
n/a 
FY23 
FY16 
12,887.0 
FY08 
11,347.6 
FY13 
13,472.0 
FY18 
n/a 
FY23 
FY17 
12,887.0 
FY08 
11,398.0 
FY13 
12,900.0 
FY18 
n/a 
FY23 
FY18 
12,907.0 
FY08 
11,377.4 
FY13 
12,997.6 
FY18 
n/a 
FY23 
FY19 
12,964.0 
FY08 
11,341.4 
FY13 
12,601.7 
FY18 
15,088.0 
FY23 
Annual % change 
FY08 to FY09 
-0.3 
 
0% 
 
0% 
 
n/a 
 
FY09 to FY10 
+3.7 
 
n/a 
 
n/a 
 
n/a 
 
FY10 to FY11 
+6.3 
 
n/a 
 
n/a 
 
n/a 
 
FY11 to FY12 
0% 
 
-1.5% 
 
-0.1% 
 
n/a 
 
FY12 to FY13 
+6.9% 
 
+11.3% 
 
+2.8% 
 
n/a 
 
FY13 to FY14 
+4.1% 
 
-0.6% 
 
0% 
 
n/a 
 
FY14 to FY15 
+0.5% 
 
+1.4% 
 
0% 
 
n/a 
 
FY15 to FY16 
0% 
 
-1.3% 
 
-2.9% 
 
n/a 
 
FY16 to FY17 
0% 
 
+0.4% 
 
-4.2% 
 
n/a 
 
FY17 to FY18 
+0.2% 
 
-0.2% 
 
+0.7% 
 
n/a 
 
FY18 to FY19 
+0.4% 
 
-0.3% 
 
-3.0% 
 
n/a 
 
Cumulative % change through FY19 
Since FY08 
+23.6% 
 
+23.4% 
 
+17.6% 
 
n/a 
 
(CVN-78 year 
of proc.) 
Since FY13 
+5.2% 
 
-0.6% 
 
-9.2% 
 
n/a 
 
(CVN-79 year 
of proc.) 
Since FY18 
+0.4% 
 
-0.3% 
 
-3.0% 
 
n/a 
 
(CVN-80 year 
of proc.) 
Source: Table prepared by CRS based on FY2008-FY2018 Navy budget submissions. n/a means not available. 
Notes: (1) The FY2010 budget submission did not show estimated procurement costs for CVNs 79 and 80. (2) 
The FY2010 budget submission did not show scheduled years of procurement for CVNs 79 and 80; the dates 
shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for procuring 
carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference regarding 
recommendations for the FY2010 defense budget. (3) Although the FY2013 budget did not change the scheduled 
years of procurement for CVN-79 and CVN-80 compared to what they were under the FY2012 budget, it 
Congressional Research Service  
 
12 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
lengthened the construction period for each ship by two years (i.e., each ship was scheduled to be delivered two 
years later than under the FY2012 budget). (4) The Department of the Navy states that “the Department of 
Navy's PB 2019 SCN end cost position for CVN 80 is $12,601.713M as explained on the P -40 SCN budget 
exhibit note in the description section. It stated: ‘CVN 80 end cost to be reduced $300M with expected FY18 
Congressional adjustment in enacted appropriations bil . End cost is $12,601.713M after reduction.’” Source: 
Navy table of annual funding for CVNs 78 through 81 for FY2001-FY2023, provided to CRS by Navy Office of 
Legislative Affairs, June 19, 2018. 
Issues for Congress for FY2020 
FY2020 Funding Request 
One issue for Congress for FY2020 is whether to approve, reject, or modify the Navy’s FY2020 
procurement funding requests for CVN-78 program. In assessing this question, Congress could 
consider various factors, including whether the Navy has accurately priced the work it is 
proposing to do on the CVN-78 program in FY2020. 
Reported FY2020 Proposal to Not Fund CVN-75 Refueling Complex 
Overhaul (RCOH) and Deactivate a Carrier Air Wing 
The Navy’s FY2020 budget submission proposes to not fund the mid-life nuclear refueling 
overhaul (called a Refueling Complex Overhaul, or RCOH) for the aircraft carrier Harry S. 
Truman (CVN-75), and to instead retire the ship around FY2024 and also deactivate one of the 
Navy’s carrier air wings at about the same time. 
Performing an RCOH on a carrier is needed for the carrier to be able to operate for the second 
half of its intended 50-year service life.32 Not performing an RCOH on CVN-75 would mean that, 
instead of remaining in service for the second half of its intended 50-year service life, the ship 
would be decommissioned, permanently removed from service, and eventually dismantled. Other 
things held equal, this would reduce the size of the carrier force by one ship for the following 20 
to 25 years compared to what the size of the carrier force would have been had the ship received 
an RCOH. 
Under the Navy’s FY2019 budget submission, CVN-75’s RCOH was scheduled to start in 
FY2024 and be completed in FY2028. Given the projected size of the carrier force under the 
Navy’s FY2019 30-year (FY2019-FY2048) shipbuilding plan, not performing an RCOH on 
CVN-75 would mean that for the period FY2024-FY2048, the carrier force would in most years 
have 10 carriers rather than 11, and in most of those years consequently would not be in 
compliance with the requirement under 10 U.S.C. 8062(b) for the Navy to maintain a force of not 
less than 11 operational aircraft carriers. 
As an associated action, the Navy’s FY2020 budget submission also proposes deactivating one of 
the Navy’s carrier air wings around FY2024. This would reduce the number of carrier air wings 
from nine to eight meaning that the Navy would no longer be in compliance with the requirement 
under 10 U.S.C. 8062(e) to maintain a minimum of nine carrier air wings. 
                                                 
32 To operate for a full 50-year life, existing Nimitz (CVN-68) class nuclear-powered carriers are given a mid-life 
nuclear refueling overhaul, called a refueling complex overhaul (RCOH), when they are 20 to 25 years old, which is 
when their original nuclear fuel core has been exhausted. The RCOH gives the ship a new nuclear fuel core sufficient 
to power the ship for the remainder of its 50-year life. The RCOH also involves a significant amount of other overhaul, 
repair, and modernization work on the ship. An RCOH requires about 44 months from contract award to delivery. 
RCOHs are funded through the Navy’s shipbuilding account. 
Congressional Research Service  
 
13 
 link to page 19 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 3 shows funding for the CVN-75 RCOH in the Navy’s FY2019 budget submission. As 
shown in the table, the estimated FY2019-FY2023 cost of the CVN-75 in the FY2019 budget 
submission was about $5.6 billion. In addition to this cost, the Navy states that it has expended 
$538 million in prior-year funding to procure the two nuclear fuel cores intended for the CVN-75 
RCOH. (CVN-75, like all Nimitz-class carriers, has two nuclear reactors, each of which would 
need a new fuel core. The Navy states that it procured one of the needed cores in FY2008 and the 
other in FY2011.)33 Adding this $538 million cost would increase the total estimated cost of the 
CVN-75 RCOH to about $6.1 billion. If CVN-75 does not receive an RCOH, these two fuel cores 
could be used for the CVN-76 RCOH or the CVN-77 RCOH, or alternatively be kept in storage 
as emergency replacement cores for a Nimitz-class carrier.34 
Table 3. Funding for CVN-75 RCOH in FY2019 Budget Submission 
Millions of dollars 
To 
FY2019 
FY2020 
FY2021 
FY2022 
FY2023 
complete 
Total 
0 
16.9 
234.7 
539.0 
752.0 
4,035.4 
5,578.0 
Source: Table prepared by CRS using data from Navy’s FY2019 budget submission. 
If CVN-75 does not receive an RCOH and is instead decommissioned, the savings from not 
funding the RCOH would be partially offset by the cost to deactivate and dismantle CVN-75. The 
Navy estimates the cost to deactivate and dismantle CVN-75 at about $1.5 billion. The initial 
increments of this approximate $1.5-billion cost would occur in FY2023 ($130.3 million) and 
FY2024 ($247.2 million.)35 The estimated net savings from not funding the RCOH and instead 
deactivating and dismantling the ship would thus be about $4.1 billion (i.e., about $5.6 billion 
less about $1.5 billion). The Navy states that there would also be 20 to 25 years of additional 
annual savings of about $1 billion per year in the form of avoided annual operation and support 
(O&S) costs for CVN-75 and the deactivated carrier air wing.36 
The reported FY2020 proposal to not fund CVN-75’s RCOH and to deactivate a carrier air wing 
reportedly is a decision of the Office of the Secretary of Defense (OSD). Reportedly, OSD wants 
to begin redirecting Navy investments to things other than aircraft carriers.37 
RCOHs are done primarily at Huntington Ingalls Industries/Newport News Shipbuilding 
(HII/NNS) in Newport News, VA, and form a significant part of HII/NNS’s business base, along 
with construction of new nuclear-powered aircraft carriers and construction of new nuclear-
powered submarines. RCOHs in recent years have been scheduled in a more or less heel-to-toe 
fashion at HII/NNS—when one RCOH is done, the next one is scheduled to begin soon 
thereafter. RCOHs are done in a particular dry dock at HII/NNS, so a carrier undergoing an 
                                                 
33 Source: Remarks by Rear Admiral Randy Crites, Deputy Assistant Secretary of the Navy for Budget, at a DOD’s 
press briefing on the Navy’s FY2020 budget submission, March 12, 2019, as shown in DOD’s transcript of the 
briefing. 
34 Source: Navy remarks at Navy briefing for congressional staff on the Navy’s FY2020 budget submission, March 14, 
2019. 
35 Source: Navy remarks at Navy briefing for congressional staff on the Navy’s FY2020 budget submission, March 14, 
2019. 
36 Source: Navy remarks at Navy briefing for congressional staff on the Navy’s FY2020 budget submission, March 14, 
2019. 
37 See the sources cited in footnote Error! Bookmark not defined.. 
Congressional Research Service  
 
14 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
RCOH in that dry dock must be ready to depart the dry dock before the following carrier can be 
moved into the dry dock for its RCOH. 
A proposal in the Navy’s FY2020 budget submission to not fund CVN-75’s RCOH and instead 
decommission the ship would raise a number of potential oversight issues for Congress, including 
the following: 
  The central purpose of 10 U.S.C. 8062(b) and 8062(e) are to act as mandates to 
the executive branch to support a force of not less than 11 carriers and a 
minimum of 9 carrier air wings in executive branch planning. It represents a 
direction from Congress for the Navy to provide the funding needed to maintain 
an 11-carrier, 9-carrier-air-wing force, regardless of limitations on the Navy’s 
overall budget or other considerations. A proposed budget from the Navy that is 
inconsistent with these provisions might thus be viewed as a challenge to 
Congress’s Article 1 power to set policy and to determine the composition of 
federal spending (i.e., Congress’s constitutional power of the purse). If DOD 
were to treat the requirements in 10 U.S.C. 8062(b) and 8062(e) as optional 
matters rather than mandates, would this create a precedent for the executive 
branch to treat similar provisions in the U.S. Code as optional matters rather than 
mandates? For example, would it create a precedent for DOD, if it so desired, to 
begin treating as an optional matter the long-standing requirement in 10 U.S.C. 
8063(a) that the Marine Corps “shall be so organized as to include not less than 
three combat divisions and three air wings, and such other land combat, aviation, 
and other services as may be organic therein?” If the executive branch were to 
begin treating statutory provisions like 10 U.S.C. 8062(b) and 8062(e) as optional 
matters rather than mandates, what implications might this have for policy and 
program execution, for Congress’s power to legislatively establish policy and 
program goals, and for Congress’s power of the purse? 
  What would be the operational impact for the Navy of reducing the carrier force 
and the number of carrier air wings by one ship and one air wing for a period of 
20 to 25 years starting around FY2024? What impact would this have on the 
Navy’s ability to fulfill its missions? 
  If CVN-75’s RCOH were funded and the carrier air wing were not deactivated, 
what other defense programs might have their funding reduced, and what would 
be the impact of these funding reductions on DOD’s ability to fulfill its missions? 
  The Navy’s 2016 Force Structure Assessment (FSA) led to a Navy force-level 
requirement for a fleet of 355 ships that includes 12 aircraft carriers. OSD 
allowed the Navy to present that FSA to the Congress, and to program 
shipbuilding and other actions in support of achieving the 355-ship force-level 
goal. OSD did not publicly object to the FSA’s 12-carrier requirement (or any 
other part of the 355-ship force-level goal). What is the analytical basis for an 
action that would reduce the size of the carrier from 11 to 10, instead of helping it 
to eventually increase from 11 to 12? 
  A proposal to not fund the CVN-75 RCOH and to deactivate a carrier air wing 
represents a notable change from prior DOD force-structure planning and 
budgeting. Is it appropriate for such a change to be proposed by DOD during a 
time when DOD has an acting Secretary of Defense rather than a Senate-
confirmed Secretary of Defense? 
Congressional Research Service  
 
15 
 link to page 17 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
  What would be the impact on HII/NNS and the other parts of the aircraft carrier 
industrial base if CVN-75 were inactivated rather than given an RCOH? What 
impact, if any, would this have on the cost of other work performed at HII/NNS 
during these years, and on the eventual cost of the CVN-76 RCOH? 
The Navy’s FY2015 budget submission proposed not funding the RCOH for the aircraft carrier 
George Washington (CVN-73). The proposal raised oversight issues for Congress broadly similar 
to those listed above. Congress, in acting on the Navy’s proposed FY2015 budget, rejected the 
proposal to not fund CVN-73’s RCOH.38 The RCOH was funded and is currently underway. 
Date for Achieving a 12-Carrier Force 
Another issue for Congress for FY2019 concerns the date for achieving the Navy’s 12-ship force-
level goal for aircraft carriers. As noted earlier, under the Navy’s FY2019 30-year shipbuilding 
plan, carrier procurement would shift from 5-year centers to 4-year centers after the procurement 
of CVN-82 in FY2028, and a 12-carrier force would be achieved on a sustained basis in the 
2060s. As also noted earlier, shifting carrier procurement to 3- or 3.5-year centers could achieve a 
12-carrier fleet as soon as the 2030s, unless the service lives of one or more existing carriers were 
substantially extended. Other things held equal, procuring carriers on 3- or 3.5-year centers rather 
than 4-year centers would increase Navy funding requirements during the period of the 30-year 
shipbuilding plan for procuring aircraft carriers and for operating and supporting a 12-carrier 
force rather than a force of 11 or fewer carriers. 
Cost Growth and Managing Costs within Program Cost Caps 
Overview 
For the past several years, cost growth in the CVN-78 program, Navy efforts to stem that growth, 
and Navy efforts to manage costs so as to stay within the program’s cost caps have been 
continuing oversight issues for Congress on the CVN-78 program.39 As shown in Table 2, the 
                                                 
38 See Appendix B of the December 22, 2014, version of CRS Report RS20643, Navy Ford (CVN-78) Class Aircraft 
Carrier Program: Background and Issues for Congress, by Ronald O'Rourke. 
39 The Congressional Budget office (CBO) in 2008 and GAO in 2007 questioned the accuracy of the Navy’s cost 
estimate for CVN-78. CBO reported in June 2008 that it estimated that CVN-78 would cost $11.2 billion in constant 
FY2009 dollars, or about $900 million more than the Navy’s estimate of $10.3 billion in constant FY2009 dollars, and 
that if “CVN-78 experienced cost growth similar to that of other lead ships that the Navy has purchased in the past 10 
years, costs could be much higher still.” CBO also reported that, although the Navy publicly expressed confidence in its 
cost estimate for CVN-78, the Navy had assigned a confidence level of less than 50% to its estimate, meaning that the 
Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office, 
Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in 
August 2007 that: 
Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate, 
which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be 
built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s 
target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for 
construction was 22 percent higher than the Navy’s cost target, which was based on the budget. 
Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to 
build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage 
issues that affect cost suffers from insufficient cost surveillance. Without effective cost 
surveillance, the Navy will not be able to identify early signs of cost growth and take necessary 
corrective action. 
(Government Accountability Office, Defense Acquisitions[:] Navy Faces Challenges Constructing 
Congressional Research Service  
 
16 
 link to page 15  link to page 17  link to page 17  link to page 17 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
estimated procurement costs of CVN-78, CVN-79, and CVN-80 have grown 23.6%, 23.4%, and 
17.6%, respectively, since the submission of the FY2008 budget. Cost growth on CVN-78 
required the Navy to program $1,394.9 million in cost-to-complete procurement funding for the 
ship in FY2014-FY2016 and FY2018 (see Table 1). As also shown in Table 2, however, cost 
growth on CVN-78, CVN-79, and CVN-80 more or less stopped in FY2013 and FY2014: 
  while the estimated cost of CVN-78 grew considerably between the FY2008 
budget (the budget in which CVN-78 was procured) and the FY2014 budget, 
since the FY2014 budget, it has grown by only a small amount (about 1%); 
  while the estimated cost of CVN-79 grew considerably between the FY2008 
budget and the FY2013 budget (in part because the procurement date for the ship 
was deferred by one year in the FY2010 budget),40 since the FY2013 budget it 
has declined by a small amount (less than 1%); and 
  while the estimated cost of CVN-79 grew considerably between the FY2008 
budget and the FY2013 budget (in part because the procurement date for the ship 
was deferred by two years in the FY2010 budget),41 since the FY2013 budget it 
has declined by about 9%. 
Recent Related Legislative Provisions 
Section 128 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of 
November 25, 2015) states the following: 
SEC. 128. Limitation on availability of funds for U.S.S. John F. Kennedy (CVN–79). 
(a) Limitation.—Of the funds authorized to be appropriated by this Act or otherwise made 
available for fiscal year 2016 for procurement for the U.S.S. John F. Kennedy (CVN–79), 
$100,000,000 may not be obligated or expended until the date on which the Secretary of 
the  Navy  submits  to  the  congressional  defense  committees  the  certification  under 
subsection  (b)(1)  or  the  notification  under  paragraph  (2)  of  such  subsection,  as  the  case 
may be, and the reports under subsections (c) and (d).... 
(c) Report on costs relating to CVN–79 and CVN–80.— 
(1) IN GENERAL.—Not later than 90 days after the date of the enactment of this Act, the 
Secretary of the Navy shall submit to the congressional defense committees a report that 
evaluates  cost  issues  related  to  the  U.S.S.  John  F.  Kennedy  (CVN–79)  and  the  U.S.S. 
Enterprise (CVN–80). 
(2) ELEMENTS.—The report under paragraph (1) shall include the following: 
(A) Options to achieve ship end cost of no more than $10,000,000,000. 
                                                 
the Aircraft Carrier Gerald R. Ford within Budget, GAO-07-866, August 2007, summary page. See 
also Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed 
to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and 
Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary 
Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), 
p. 15.) 
40 Deferring the ship’s procurement from FY2012 to FY2013 put another year of inflation into the ship’s estimated cost 
in then-year dollars (which are the type of dollars shown in Table 2), and may have reduced production learning curve 
benefits in shifting from production of CVN-78 to production of CVN-79. 
41 Deferring the ship’s procurement from FY2016 to FY2018 put additional years of inflation into the ship’s estimated 
cost in then-year dollars (which are the type of dollars shown in Table 2), and may have reduced production learning 
curve benefits in shifting from production of CVN-79 to production of CVN-80. 
Congressional Research Service  
 
17 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(B) Options to freeze the design of CVN–79 for CVN–80, with exceptions only for changes 
due to full ship shock trials or other significant test and evaluation results. 
(C) Options to reduce the plans cost for CVN–80 to less than 50 percent of the CVN–79 
plans cost. 
(D)  Options  to  transition  all  non-nuclear  Government-furnished  equipment,  including 
launch and arresting equipment, to contractor-furnished equipment. 
(E) Options to build the ships at the most economic pace, such as four years between ships. 
(F) A business case analysis for the Enterprise Air Search Radar modification to CVN–79 
and CVN–80. 
(G) A business case analysis for the two-phase CVN–79 delivery proposal and impact on 
fleet deployments. 
Section 126 of the FY2017 National Defense Authorization Act (S. 2943/P.L. 114-328 of 
December 23, 2016) states the following: 
SEC. 126. Limitation on availability of funds for procurement of U.S.S. Enterprise (CVN–
80). 
(a) Limitation.—Of the funds authorized to be appropriated by this Act or otherwise made 
available  for  fiscal  year  2017  for  advance  procurement  or  procurement  for  the  U.S.S. 
Enterprise (CVN–80), not more than 25 percent may be obligated or expended until the 
date on which the Secretary of the Navy and the Chief of Naval Operations jointly submit 
to the congressional defense committees the report under subsection (b). 
(b)  Initial  report  on  CVN–79  and  CVN–80.—Not  later  than  December  1,  2016,  the 
Secretary  of  the  Navy  and  the  Chief  of  Naval  Operations  shall  jointly  submit  to  the 
congressional defense committees a report that includes a description of actions that may 
be carried out (including de-scoping requirements, if necessary) to achieve a ship end cost 
of— 
(1) not more than $12,000,000,000 for the CVN–80; and 
(2) not more than $11,000,000,000 for the U.S.S. John F. Kennedy (CVN–79). 
(c) Annual report on CVN–79 and CVN–80.— 
(1) IN GENERAL.—Together with the budget of the President for each fiscal year through 
fiscal year 2021 (as submitted to Congress under section 1105(a) of title 31, United States 
Code) the Secretary of the Navy and the Chief of Naval Operations shall submit a report 
on the efforts of the Navy to achieve the ship end costs described in subsection (b) for the 
CVN–79 and CVN–80. 
(2)  ELEMENTS.—The  report  under  paragraph  (1)  shall  include,  with  respect  to  the 
procurement of the CVN–79 and the CVN–80, the following: 
(A) A description of the progress made toward achieving the ship end costs described in 
subsection (b), including realized cost savings. 
(B) A description of low value-added or unnecessary elements of program cost that have 
been reduced or eliminated. 
(C) Cost savings estimates for current and planned initiatives. 
(D) A schedule that includes— 
(i) a plan for spending with phasing of key obligations and outlays; 
(ii) decision points describing when savings may be realized; and 
(iii) key events that must occur to execute initiatives and achieve savings. 
Congressional Research Service  
 
18 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(E) Instances of lower Government estimates used in contract negotiations. 
(F)  A  description  of  risks  that  may  result  from  achieving  the  procurement  end  costs 
specified in subsection (b). 
(G) A description of incentives or rewards provided or planned to be provided to prime 
contractors for meeting the procurement end costs specified in subsection (b). 
Section 121(b) of the FY2018 National Defense Authorization Act (H.R. 2810/P.L. 115-91 of 
December 12, 2017) states the following: 
SEC. 121. Aircraft carriers. 
... 
(b) Waiver on limitation of availability of funds for CVN–79.—The Secretary of Defense 
may waive subsections (a) and (b) of section 128 of the National Defense Authorization 
Act for Fiscal Year 2016 (Public Law 114–92; 129 Stat. 751) after a period of 60 days has 
elapsed  following  the  date  on  which  the  Secretary  submits  to  the  congressional  defense 
committees a written notification of the intent of the Secretary to issue such a waiver. The 
Secretary shall include in any such notification the following: 
(1) The rationale of the Secretary for issuing the waiver. 
(2) The revised test and evaluation master plan that describes when full ship shock trials 
will be held on Ford-class aircraft carriers. 
(3) A certification that the Secretary has analyzed and accepted the operational risk of the 
U.S.S. Gerald R. Ford deploying without having conducted full ship shock trials, and that 
the Secretary has not delegated the decision to issue such waiver. 
Sources of Risk of Cost Growth and Navy Actions to Control Cost 
Sources of risk of cost growth on CVN-78 included, among other things, certain new systems to 
be installed on CVN-78 whose development, if delayed, could delay the completion of the ship. 
These systems included a new type of aircraft catapult called the Electromagnetic Launch System 
(EMALS), a new aircraft arresting system called the Advanced Arresting Gear (AAG), and the 
ship’s primary radar, called the Dual Band Radar (DBR). Congress has followed these and other 
sources of risk of cost growth for years. 
In July 2016, the DOD Inspector General issued a report critical of the Navy’s management of the 
AAG development effort.42 In January 2017, it was reported that after conducting a review of 
potential alternative systems, the Navy had decided to continue stay with its plan to install 
EMALs and AAG on the first three Ford-class carriers.43 Section 125 of the FY2017 National 
Defense Authorization Act (S. 2943/P.L. 114-328 of December 23, 2016) limited the availability 
of funds for the AAG program until certain conditions are met. 
                                                 
42 Inspector General, U.S. Department of Defense, Advanced Arresting Gear Program Exceeded Cost and Schedule 
Baselines, Report No DODIG-2016-107, July 5, 2016, 29 pp. For press reports about the DOD IG report, see Justin 
Doubleday, “DOD IG: Navy Mismanaged Development, Testing of Advanced Arresting Gear,” Inside the Navy, July 
11, 2016; Christopher P. Cavas, “Pentagon Finds Navy Mismanaged Arresting Gear Program,” Defense News, July 11, 
2016. 
43 Sydney J. Freedberg Jr., “Navy Commits To High-Tech Catapults, Arresting Gear For All 3 Ford Carriers,” Breaking 
Defense, January 17, 2017. See also David B. Larter, “Advanced Arresting Gear Is Coming Along,” Defense News, 
June 25, 2018; Paul McLeary, “Navy’s troubled Ford Carrier Makes Modest Progress,” Breaking Defense, June 25, 
2018. 
Congressional Research Service  
 
19 
 link to page 61  link to page 90 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Navy officials have stated that they are working to control the cost of CVN-79 by equipping the 
ship with a less expensive primary radar,44 by turning down opportunities to add features to the 
ship that would have made the ship more capable than CVN-78 but would also have increased 
CVN-79’s cost, and by using a build strategy for the ship that incorporates improvements over the 
build strategy that was used for CVN-78. These build-strategy improvements, Navy officials have 
said, include the following items, among others: 
  achieving a higher percentage of outfitting of ship modules before modules are 
stacked together to form the ship; 
  achieving “learning inside the ship,” which means producing similar-looking ship 
modules in an assembly line-like series, so as to achieve improved production 
learning curve benefits in the production of these modules; and 
  more economical ordering of parts and materials including greater use of batch 
ordering of parts and materials, as opposed to ordering parts and materials on an 
individual basis as each is needed. 
For additional background information on cost growth in the CVN-78 program, Navy efforts to 
stem that growth, and Navy efforts to manage costs so as to stay within the program’s cost caps, 
see Appendix B and Appendix C. 
CVN-78 Weapons Elevators 
Another oversight issue for Congress concerns Navy efforts to complete the construction, testing, 
and certification of the weapons elevators on CVN-78. (The ship’s weapons elevators transport 
missiles and bombs from the ship’s weapon magazines to the ship’s flight deck, so that they can 
be loaded onto aircraft that are getting ready to take off from the ship.) A November 2, 2018, 
press report states the following: 
The  $13  billion  Gerald  R.  Ford  aircraft  carrier,  the  U.S.  Navy’s  costliest  warship,  was 
delivered last year without elevators needed to lift bombs from below deck magazines for 
loading on fighter jets. 
Previously  undisclosed  problems  with  the  11  elevators  for  the  ship  built  by  Huntington 
Ingalls  Industries  Inc.  add  to  long-standing  reliability  and  technical  problems  with  two 
other core systems -- the electromagnetic system to launch planes and the arresting gear to 
catch them when they land. 
The Advanced Weapons Elevators, which are moved by magnets rather than cables, were 
supposed to be installed by the vessel’s original delivery date in May 2017. Instead, final 
installation was delayed by problems including four instances of unsafe “uncommanded 
movements” since 2015, according to the Navy. 
While progress was being made on the carrier’s other flawed systems, the elevator is “our 
Achilles heel,” Navy Secretary Richard Spencer told reporters in August without providing 
details.... 
The Navy says that the first carrier will be fully combat-capable, including the elevators, 
by July -- the end of its current 12-month pier-side shakedown period in Virginia. 
                                                 
44 See, for example, Megan Eckstein, “PEO Carriers: CVN-79 Will Have a New Radar, Save $180M Compared to 
[CVN-78’s] Dual Band Radar,” USNI News, March 17, 2015; Christopher P. Cavas, “Dual Band Radar Swapped Out 
In New Carriers,” Defense News, March 17, 2015; Christopher P. Cavas, “New US Carrier Radar Enters the Picture,” 
Defense News, March 23, 2015. 
Congressional Research Service  
 
20 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Navy weapons buyer James Geurts cited what  he called “considerable progress” on the 
Ford, including on the elevators, in a July 6 memo to Pentagon acquisition head Ellen Lord. 
The Navy in May requested permission from Congress in May to increase the Ford’s cost 
cap by $120 million, partly to fix elevator issues “to preclude any effect on the safety of 
the ship and personnel.” The safety issues related to the uncommanded movements, the 
Navy said in an email.... 
Beci Brenton, a spokeswoman for Newport News, Virginia-based Huntington Ingalls, said 
“all  the  elevators  are  installed.”  She  said  the  weapons  elevator  is  among  “the  most 
advanced technologies being incorporated into” the carrier and “its completion has been 
delayed due to a number of first-in-class issues,” Brenton said. 
“We are committed to working through the remaining technical challenges,” she said. 
William Couch, a spokesman for the Naval Sea Systems Command, said the elevators are 
“in varying levels of construction and testing.” 
Six are far enough along to be operated by the shipbuilder, and testing has started on two 
of those, he said. All 11 “should have been completed and delivered with the ship delivery,” 
according to Couch. 
He  said  the  contractor  has  corrected  “all  issues,”  including  the  “four  uncommanded 
movements over the last three years that were discovered during the building, operational 
grooming, or testing phases.”... 
A  November  2010  program  on  PBS’s  “Nova”  science  series  extolled  the  “Elevator  of 
Tomorrow” being developed by Federal Equipment Co., a Cincinnati-based subcontractor 
to Huntington Ingalls. 
Doug Ridenour, president of Federal Equipment Co., said the elevator’s key technologies 
“have been consistently demonstrated for years” in a test unit in the company’s plant and 
any programming or software-related issues have been fixed. 
But “shipboard integration involves many other technology insertions not controlled by” 
his company, he said.45 
At a November 27, 2018, hearing on Navy shipbuilding programs before the Seapower 
subcommittee of the Senate Armed Services Committee, the following exchange occurred: 
SENATOR TIM KAINE (continuing):  
There have been challenges with the advanced weapons elevators on the CVN, some of the 
technical  difficult[ies]  seem  similar  to  those  that  were  experienced  earlier  on  both  the 
[aircraft]  launch  and  arresting  systems.  I  think  that  the  Navy  put  together  independent 
review teams to tackle those issues and provide solutions. Are we at a point where that may 
be needed on the weapons elevators or are we in a position where we think the progress on 
the weapons elevators is satisfactory? 
JAMES  F.  GEURTS,  ASSISTANT  SECRETARY  OF  THE  NAVY  FOR  RESEARCH, 
DEVELOPMENT AND ACQUISITION: 
Yes, sir. So there are 11 weapons elevators [and] each one of them we have to produce, 
test and then certify. The first two of those have been produced, the first one’s been through 
test  and  certification.  The  second  one  is  about  94  percent  through  test.  We  are  making 
progress to get through all of the elevators during this availability. 
I am likely to do an independent review team not on the immediate construction for CVN-
78 but looking at the longer-term sustainability, resilience, reliability to make sure we are 
                                                 
45 Anthony Capaccio, “U.S. Navy’s Costliest Carrier Was Delivered Without Elevators to Lift Bombs,” Bloomberg, 
November 2, 2018. 
Congressional Research Service  
 
21 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
in a position to support those elevators for the long term, that we’ve got all of the training 
and all of the reliability built into those. We’ve done so many independent reviews for the 
[CVN-]78 elevator design as they are so we won’t do one on the current efforts on [CVN-
]78. We've got a dedicated team working our way through those issues. 
KAINE:  
And is your timing on that testing and certification on [CVN-]78—you have this 12-month 
period  where  you  are  testing—[do]  you  think  you  will  get  through  the  testing  and 
certification of all of the 11 elevators in that year one? 
GEURTS:  
My current assessment is we will get through all of the production and much of the testing. 
We may have some of the certification issues to go. I am watching it very closely and we 
will keep you and your staff informed on progress there.46 
A December 5, 2018, press report stated the following: 
The  Navy  plans  to  complete  installation  and  testing  of  the  11  elevators  before  the  Ford 
completes its post-delivery shakedown phase in July, Captain Danny Hernandez, a Navy 
spokesman, said in an email. Six will also be certified for use by then, but five won’t be 
completed until after July, he said. “A dedicated team is engaged on these efforts and will 
accelerate this certification work and schedule where feasible,” he said. 
Huntington spokeswoman Beci Brenton said via email that company officials had a “very 
productive meeting” with Inhofe that included both the elevators and benefits of a two-
carrier contract. 
The  elevator’s  completion  “has  been  delayed  due  to  a  number  of  first-in-class  issues 
associated with the first-time installation, integration and test of this new technology,” she 
said. “However, we are making substantial substantial progress in resolving the remaining 
technical challenges.” 
A January 6, 2019, press report stated the following: 
The  Navy  Secretary  has  committed  that  the  service  and  its  industry  partners  will  have 
working weapons elevators on aircraft carrier USS Gerald  R. Ford (CVN-78) by the end 
of the summer--and the secretary’s job is now on the line over that issue. 
The Navy accepted delivery of the first-in-class carrier and commissioned it into the fleet 
without  any  functioning  weapons  elevators.  The  carrier  is  now  in  its  post-shakedown 
availability at builder Newport News Shipbuilding, after spending a year at sea running the 
ship to discover any potential flaws. 
Though the Navy already said the elevators would be addressed during this PSA period, 
the  stakes  are  now  higher:  Navy  Secretary  Richard  V.  Spencer  told  President  Donald 
Trump that the elevators would be installed and working by the time the carrier returns to 
sea, or else the president can use his famous “you’re fired” line on the service secretary. 
Spencer said this morning at an event hosted by the Center for a New American Security 
that  he  spoke  to  Trump  at  length  last  month  at  the  Army-Navy  football  game  in 
Philadelphia. 
“I asked him to stick his hand out; he stuck his hand out. I said, let’s do this like corporate 
America. I shook his hand and said, the elevators will be ready to go when she pulls out or 
you can fire me,” Spencer said, adding that someone had to take accountability over the 
ongoing elevator challenges. 
                                                 
46 Source: CQ.com transcript of hearing. 
Congressional Research Service  
 
22 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
“We’re going to get it done. I know I’m going to get it done. I haven’t been fired yet by 
anyone; being fired by the president really isn’t on the top of my list.”... 
The elevator issue has plagued the carrier for years, even if it garnered less attention than 
other  high-profile  new  technologies  on  the  carrier,  such  as  the  new  Electromagnetic 
Aircraft Launch System (EMALS) and the Advanced Arresting Gear, both of which had 
their own fair share of technical problems. 
In 2016, the late Sen. John McCain (R-Ariz.), who then chaired the Senate Armed Services 
Committee, railed against the Ford-class program, noting that Ford was already overdue to 
be delivered to the Navy and still was facing ongoing technical difficulties. 
“The Navy’s announcement of another two-month delay in the delivery of CVN-78 further 
demonstrates  that  key  systems  still  have  not  demonstrated  expected  performance.  The 
advanced  arresting  gear  (AAG)  cannot  recover  airplanes.  Advanced  weapons  elevators 
cannot  lift  munitions.  The  dual-band  radar  cannot  integrate  two  radar  bands.  Even  if 
everything  goes according to the  Navy’s plan, CVN-78  will be  delivered  with  multiple 
systems unproven,” McCain said in a July 2016 hearing. 
A month later the Pentagon announced a 60-day review of the Ford program, with a specific 
focus on five technology areas, including the elevators. 
Ford ultimately delivered to the Navy in June 2017 and commissioned a month later, still 
without working weapons elevators. 
In July 2018, when Ford entered PSA, the Navy said the maintenance availability had been 
extended from a planned eight months to a full year, to accommodate both the typical work 
that  arises  in  PSA  but  also  deferred  work  such  as  the  construction  and  installation  of 
weapons  elevators  and  an  upgrade  to  the  AAG,  whose  technical  challenges  greatly 
contributed to the delayed delivery and commissioning of the ship.47 
A January 16, 2019, press report stated the following: 
The Navy’s newest aircraft carrier, USS Gerald R. Ford (CVN 78), closed out 2018 on a 
high note with the acceptance of the ship’s first advanced weapons elevator (AWE), setting 
the tone for more positive developments in the year ahead. 
AWE  Upper  Stage  #1  was  turned  over  to  the  ship  on  Dec.  21,  following  testing  and 
certification  by  engineers  at  Huntington  Ingalls  Industries-Newport  News  Shipbuilding, 
where the  ship is currently  working through its post-shakedown availability (PSA). The 
acceptance marks a major milestone for the ship and the Ford-class of aircraft carriers to 
follow.... 
Though  the  first  elevator  has  been  accepted,  work  still  remains  on  the  remaining  10. 
Currently,  all  shipboard  installation  and  testing  activities  of  the  AWEs  are  due  to  be 
completed prior to the end of Ford’s PSA, scheduled for July. However, some remaining 
certification  documentation  will  be  performed  for  five  of  the  11  elevators  after  PSA 
completion.48 
A March 6, 2019, press report stated the following: 
                                                 
47 Megan Eckstein, “SECNAV to Trump: Ford Carrier Weapons Elevators Will Be Fixed by Summer, or ‘Fire Me,’” 
USNI News, January 8, 2019. 
48 USS Gerald R. Ford Public Affairs, “USS Gerald R. Ford Accepts First Advanced Weapons Elevator,” Navy News 
Service, January 16, 2019. See also Christopher Woody, “The Navy’s Newest Aircraft Carrier Got a Long-Missing 
Piece of Gear in December, Helping to Solve a Problem the Navy Secretary Has Bet His Job on Fixing,” Business 
Insider, January 20, 2019; Richard Sisk, “Navy Finally Has One Weapons Elevator Working on Its Newest Carrier,” 
Military.com, January 22, 2019; Mark D. Faram, “Once Beleaguered by Critics, the Ford Gets a Lift,” Navy Times, 
January 23, 2019. 
Congressional Research Service  
 
23 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Nearly one month following the acceptance of its first advanced weapons elevator (AWE), 
the Navy’s newest aircraft carrier, USS Gerald R. Ford (CVN 78), has accepted its second. 
AWE  Upper  Stage  #3  was  turned  over  to  the  ship  February  14,  following  testing  and 
certification  by  engineers  at  Huntington  Ingalls  Industries-Newport  News  Shipbuilding 
(NNS), where the ship is currently working through its post-shakedown availability (PSA). 
According to Ford’s Weapons Officer, Cmdr. Joe  Thompson, acceptance of the  second 
AWE  offers  an  opportunity  for  Ford  Sailors  to  become  acquainted  with  the  equipment 
during the PSA. 
“This  gives  us  more  time  to  learn  and  become  subject  matter  experts,”  explained 
Thompson. “All of us are learning on brand new systems and brand new concepts. This 
acceptance gives us the opportunity to have that ‘run time’ on the physical aspects of the 
elevator,  but  also  in  evaluating  the  technical  manuals,  and  learning  the  maintenance 
required to keep them operational.” 
With two elevators in hand, Thompson explained that Sailors training on these new systems 
will be able to apply the lessons learned from the first elevator, Upper Stage #1, and apply 
them  to  Upper  Stage  #3,  thereby  streamlining  the  learning  process  and  lessening  the 
learning curve. 
“This is going to allow us to progress faster,” he explained. “As we get smarter on one, we 
move  on  to  the  next  and  apply  the  lessons  learned  not  only  with  regard  to  elevator 
operation, but also in the testing and certification, and maintenance processes.”… 
Acceptance of the elevator was accelerated due to a merging of the test programs between 
NNS and the Naval Surface Warfare Center (NSWC), which removed redundant steps and 
moved certification up by 10 days. The team has identified other areas where redundancy 
can be removed to make the acceptance timelines more efficient.49 
Issues Raised in December 2018 DOT&E Report 
Another oversight issue for Congress concerns CVN-78 program issues raised in a December 
2018 report from DOD’s Director, Operational Test and Evaluation (DOT&E)—DOT&E’s 
annual report for FY2018. Regarding the CVN-78 program, the report stated the following in 
part: 
Assessment 
•  The  delays  in  the  ship  development  and  initial  trials  pushed  both  phases  of  initial 
operational testing until FY21 and FY22. The delay in the ship’s delivery and development 
added approximately 2 years to the timeline. As noted in previous annual reports, the CVN 
78 test schedule has been aggressive, and the development of EMALS [Electromagnetic 
Aircraft  Launch  System],  AAG  [Advanced  Arresting  gear],  AWE  [Advanced  Weapons 
Elevator], DBR [Dual Band Radar], and the Integrated Warfare System delayed the ship’s 
first deployment to FY22. 
Reliability 
• Four of CVN 78’s new systems stand out as being critical to flight operations: EMALS, 
AAG, DBR, and AWEs. Overall, the poor reliability demonstrated by AAG and EMALS 
and  the  uncertain  reliability  of  DBR  and  AWEs  could  delay  CVN  78  IOT&E  [Initial 
Operational Test and Evaluation]. The Navy continues to test all four of these systems in 
their shipboard configurations aboard CVN 78. Reliability estimates derived from test data 
                                                 
49 USS Gerald R. Ford (CVN 78) Public Affairs, “USS Gerald R. Ford Accepts Second Advanced Weapons Elevator,” 
Navy News Service, March 6, 2019. See also Rich Abott, “Navy To Build Land-Based Carrier Elevator Test Site,” 
Defense Daily, February 21, 2019. 
Congressional Research Service  
 
24 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
for EMALS and AAG are discussed in following subsections. For DBR and AWE, only 
engineering reliability estimates have been provided.  
EMALS 
• Testing to date involved 747 shipboard launches and demonstrated EMALS capability to 
launch aircraft planned for the CVN 78 Air Wing. 
• Through the first 747 shipboard launches, EMALS suffered 10 critical failures. This is 
well below the requirement of 4,166 Mean Cycles Between Critical Failures, where a cycle 
represents the launch of one aircraft.  
•  The  reliability  concerns  are  exacerbated  by  the  fact  that  the  crew  cannot  readily 
electrically isolate EMALS components during flight operations due to the shared nature 
of the Energy Storage Groups and Power Conversion Subsystem inverters onboard CVN 
78. The process for electrically isolating equipment is time-consuming; spinning down the 
EMALS  motor/generators  takes  1.5  hours  by  itself.  The  inability  to  readily  electrically 
isolate equipment precludes EMALS maintenance during flight operations. 
AAG 
•  Testing  to  date  included  763  attempted  shipboard  landings  and  demonstrated  AAG 
capability to recover aircraft planned for the CVN 78 air wing. 
• The Program Office redesigned major components that did not meet system specifications 
during  land-based  testing.  Through  the  first  763  attempted  shipboard  landings,  AAG 
suffered  10  operational  mission  failures  (which  includes  one  failure  of  the  barricade 
system). This reliability estimate falls well below the re-baselined reliability growth curve 
and  well  below  the  requirement  of  16,500  Mean  Cycles  Between  Operational  Mission 
Failures, where a cycle represents the recovery of one aircraft. 
• The reliability concerns are magnified by the current AAG design that does not allow 
electrical  isolation  of  the  Power  Conditioning  Subsystem  equipment  from  high  power 
buses, limiting corrective maintenance on below-deck equipment during flight operations. 
Combat System 
• Results of SBDT [sea-based developmental testing] events indicate good SSDS [ship self-
defense  system]  performance  in  scheduling  and  launching  simulated  RAMs  [Rolling 
Airframe  Missiles]  and  ESSMs  [Evolved  Sea  Sparrow  Missiles],  as  well  as  scheduling 
DBR directives for ESSM acquisition and target illumination. Insufficient interoperability 
testing with a CEC [Cooperative Engagement Capability] network and Link 16 prevents 
an estimate of performance in this area. It is unknown if the integration problems between 
SSDS and Surface Electronic Warfare Improvement Program (SEWIP) Block 2 identified 
during engineering testing at Wallops Island have been resolved because SEWIP Block 2 
was not installed on the ship during these SBDT events. 
• CVN 78’s combat system testing on the SDTS [self-defense test ship] is at risk due to 
schedule constraints, lack of funding, and insufficient planned developmental testing. 
DBR 
• Throughout the five CVN 78 SBDTs, DBR was plagued by extraneous false and close-
in dual tracks adversely affecting its performance. 
•  Integration  of  the  DBR  electronic  protection  capabilities  remains  incomplete  and 
unfunded. With modern threats, a lack of electronic protection places the ship in a high-
risk scenario if deployed to combat. 
• The Navy analysis noted that DBR performance needs to be improved to support carrier 
air traffic control center certification. 
Sortie Generation Rate 
Congressional Research Service  
 
25 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
• CVN 78 is unlikely to achieve its SGR [sortie generation rate] requirement. The target 
threshold  is  based  on  unrealistic  assumptions  including  fair  weather  and  unlimited 
visibility, and that aircraft emergencies, failures of shipboard equipment, ship maneuvers, 
and  manning  shortfalls  will  not  affect  flight  operations.  During  the  2013  operational 
assessment,  DOT&E  conducted  an  analysis  of  past  aircraft  carrier  operations  in  major 
conflicts.  The  analysis  concludes  that  the  CVN  78  SGR  requirement  is  well  above 
historical levels. 
• DOT&E plans to assess CVN 78 performance during IOT&E by comparing it to the SGR 
requirement as well as to the demonstrated performance of the Nimitz-class carriers. 
• Poor reliability of key systems that support sortie generation on CVN 78 could cause a 
cascading series of delays during flight operations that would affect CVN 78’s ability to 
generate sorties. The poor or unknown reliability of these critical subsystems represents 
the most risk to the successful completion of CVN 78 IOT&E. 
Manning 
• Based on current expected manning, the berthing capacity for officers and enlisted will 
be exceeded by approximately 100 personnel with some variability in the estimates. This 
also leaves no room for extra personnel during inspections, exercises, or routine face-to-
face turnovers. 
• Planned ship manning requires filling 100 percent of the billets. This is not the Navy’s 
standard practice on other ships, and the personnel and training systems may not be able to 
support  100  percent  manning.  Additionally,  workload  estimates  for  the  many  new 
technologies such as catapults, arresting gear, radar, and weapons and aircraft elevators are 
not yet well understood. 
Electromagnetic Compatibility 
•  Developmental  testing  identified  significant  EMI  [electromagnetic  interference]  and 
radiation  hazard  problems.  The  Navy  continues  to  characterize  and  develop  mitigation 
plans for the problems, but some operational limitations and restrictions are expected to 
persist into IOT&E and deployment. The Navy will need to develop capability assessments 
at  differring  levels  of  system  utilization  in  order  for  commanders  to  make  informed 
decisions on system employment. 
Live Fire Test & Evaluation 
• The vulnerability of CVN 78’s many new critical systems to underwater threat-induced 
shock is unknown. The program plans to complete shock testing on EMALS, AAG, and 
the AWE components during CY19, but because of a scarcity of systems, shock testing of 
DBR components lags and will likely not be completed before the FSSTs [full ship shock 
trials]. 
• The Vulnerability Assessment Report provides an assessment of the ship’s survivability 
to  air-delivered  threat  engagements.  The  classified  findings  in  the  report  identify  the 
specific equipment that  most  frequently  would lead to mission capability loss. In FY19, 
the Navy is scheduled to deliver additional report volumes that will assess vulnerability to 
underwater threats and compliance with Operational Requirements Document survivability 
criteria. 
Recommendations 
The Navy should: 
1. Provide schedule, funding, and an execution strategy for assessing SGR. This strategy 
should  specify  which  testing  will  be  accomplished  live,  a  process  for  accrediting  the 
Seabasing/Seastrike Aviation Model for operational testing, and a method for comparing 
CVN 78 performance with that of the Nimitz class. 
Congressional Research Service  
 
26 
 link to page 22 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
2. Continue to characterize the electromagnetic environment onboard CVN 78 and develop 
operating procedures to maximize system effectiveness and maintain safety. As applicable, 
the Navy should utilize the lessons learned from CVN 78 to inform design modifications 
for CVN 79 and future carriers. 
3. Develop and implement DBR electronic protection to enhance ship survivability against 
modern threats. 
4. Submit an updated TEMP.50 
Shock Trial 
Another issue for Congress is whether to conduct the shock trial for the CVN-78 class in the near 
term, on the lead ship in the class, or years later, on the second ship in the class. 
A shock trial, known formally as a full ship shock trial (FSST) and sometimes called a shock test, 
is a test of the combat survivability of the design of a new class of ships. A shock trial involves 
setting off one or more controlled underwater charges near the ship being tested, and then 
measuring the ship’s response to the underwater shock caused by the explosions. The test is 
intended to verify the ability of the ship’s structure and internal systems to withstand shocks 
caused by enemy weapons, and to reveal any changes that need to be made to the design of the 
ship’s structure or its internal systems to meet the ship’s intended survivability standard. Shock 
trials are nominally to be performed on the lead ship in a new class of ships, but there have also 
been cases where the shock trial for a new class was done on one of the subsequent ships in the 
class. 
The question of whether to conduct the shock trial for the CVN-78 class in the near term, on the 
lead ship in the class, or years later, on the second ship in the class, has been a matter of 
disagreement at times between the Navy and the office of the Secretary of Defense (OSD). The 
Navy has wanted to perform the shock trial on the second ship in the class, because performing it 
on the lead ship in the class, the Navy has argued, will cause a significant delay in the first 
deployment of the lead ship, effectively delaying the return of the carrier force to an 11-ship force 
level and increasing the operational strain on the other 10 carriers. The Navy has argued that the 
risks of delaying the shock trial on the CVN-78 to the second ship in the class are acceptable, 
because the CVN-78 class hull design is based on the Nimitz (CVN-68) class aircraft carrier hull 
design, whose survivability against shocks is understood, because systems incorporated into the 
CVN-78 design have been shock tested at the individual component level, and because computer 
modeling can simulate how the CVN-78 design as a whole will respond to shocks. 
OSD has argued that the risks of delaying the CVN-78 class shock trial to the second ship in the 
class are not acceptable, because the CVN-78 design is the first new U.S. aircraft carrier design in 
four decades; because the CVN-78 design has many internal design differences compared to the 
CVN-68 design, including new systems not present in the CVN-68 class design; and because 
computer modeling can only do so much to confirm how a complex new platform, such as an 
aircraft carrier and all its internal systems, will respond to shocks. The risk of delaying the shock 
trial, OSD has argued, outweighs the desire to avoid a delay in the first deployment of the lead 
ship in the class. OSD in 2015 directed the Navy to plan for conducting a shock trial on the lead 
ship. The Navy complied with this direction but has also sought to revisit the issue with OSD. 
The issue of the shock trial for the CVN-78 class has been a matter of legislative activity—see the 
provisions shown earlier in “Recent Related Legislative Provisions,” particularly the most recent 
                                                 
50 Department of Defense, Director, Operational Test & Evaluation, FY2018 Annual Report, December 2018, pp. 133-
134. 
Congressional Research Service  
 
27 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
such provision, Section 121(b) of the FY2018 National Defense Authorization Act (H.R. 
2810/P.L. 115-91 of December 12, 2017). 
An April 5, 2018, press report states the following: 
The  Pentagon’s  No.  2  civilian  has  said  the  Navy  should  perform  shock-testing  soon  to 
determine  how  well  its  new  $12.9  billion  aircraft  carrier—the  costliest  warship  ever—
could withstand an attack, affirming the service’s recent decision to back down from a plan 
for delay. 
“We agree with your view that a test in normal sequence is more prudent and pragmatic,” 
Deputy Defense Secretary Patrick Shanahan said in a newly released March 26 letter to 
Senate Armed Services Committee Chairman John McCain. The Arizona Republican and 
Senator Jack Reed, the panel’s top Democrat, pressed for the shock-testing to go ahead as 
originally planned. 
James Guerts, the Navy’s chiefs weapons buyer, told reporters last month that the Navy 
was acquiescing to the testing after initially asking Defense Secretary James Mattis to delay 
it for at least six years. In its push to maintain an 11-carrier fleet, the Navy wanted to wait 
and perform the test on a second carrier in the class rather than on the USS Gerald Ford.51 
Navy Study on Smaller Aircraft Carriers 
Overview 
Another oversight issue for Congress is whether the Navy should shift at some point from 
procuring large-deck, nuclear-powered carriers like the CVN-78 class to procuring smaller 
aircraft carriers. The issue has been studied periodically by the Navy and other observers over the 
years. To cite one example, the Navy studied the question in deciding on the aircraft carrier 
design that would follow the Nimitz (CVN-68) class. 
Advocates of smaller carriers argue that they are individually less expensive to procure, that the 
Navy might be able to employ competition between shipyards in their procurement (something 
that the Navy cannot do with large-deck, nuclear-powered carriers like the CVN-78 class, because 
only one U.S. shipyard, HII/NNS, can build aircraft carriers of that size), and that today’s aircraft 
carriers concentrate much of the Navy’s striking power into a relatively small number of 
expensive platforms that adversaries could focus on attacking in time of war. 
Supporters of large-deck, nuclear-powered carriers argue that smaller carriers, though 
individually less expensive to procure, are less cost-effective in terms of dollars spent per aircraft 
embarked or aircraft sorties that can be generated, that it might be possible to use competition in 
procuring certain materials and components for large-deck, nuclear-powered aircraft carriers, and 
that smaller carriers, though perhaps affordable in larger numbers, would be individually less 
survivable in time of war than large-deck, nuclear-powered carriers. 
                                                 
51 Anthony Capaccio, “Pentagon Endorses Shock-Testing Carrier After Navy Backs Down,” Bloomberg, April 5, 2018. 
See also Jason Sherman and Lee Hudson, “Navy to Conduct Full Ship Shock Trials of CVN-78 in ’19 or ’20,” Inside 
the Navy, March 26, 2018; Anthony Capaccio, “Navy Presses Mattis to Delay ‘Shock Testing’ Costliest Carrier,” 
Bloomberg, February 7, 2018; Jason Sherman, “Lawmakers Rraise Ford-Class Carrier Cost Cap, Grant Navy Wiggle 
Room to Avoid Shock Testing,” Inside the Navy, November 13, 2017. 
Congressional Research Service  
 
28 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Navy Study Initiated in 2015 
At a March 18, 2015, hearing on Navy shipbuilding programs before the Seapower subcommittee 
of the Senate Armed Services Committee, the Navy testified that it had initiated a new study on 
the question. At the hearing, the following exchange occurred: 
SENATOR  JOHN  MCCAIN,  CHAIRMAN,  SENATE  ARMED  SERVICES 
COMMITTEE, ATTENDING EX OFFICIO: 
And you are looking at additional options to the large aircraft carrier as we know it. 
SEAN  STACKLEY,  ASSISTANT  SECRETARY  OF  THE  NAVY  FOR  RESEARCH, 
DEVELOPMENT,AND ACQUISITION:  
We’ve initiated a study and I think you’ve discussed this with the CNO [Chief of Naval 
Operations] and that’s with the frontend of that study. Yes, sir.52  
Later in the hearing, the following exchange occurred: 
SENATOR ROGER WICKER, CHAIRMAN, SEAPOWER SUBCOMMITTEE: 
Well,  Senator  McCain  expressed  concern  about  competition  [in  Navy  shipbuilding 
programs]. And I think that was with, in regard to aircraft carriers. 
SEAN J. STACKLEY, ASSISTANT SECRETARY OF THE NAVY FOR RESEARCH, 
DEVELOPMENT,AND ACQUISITION: 
Yes, Sir. 
WICKER:  
Would you care to respond to that? 
STACKLEY:  
He made a generic comment that we need competition to help control cost in our programs 
and we are absolutely in agreement there. With specific regards to the aircraft carrier, we 
have been asked and we are following suit to conduct a study to look at alternatives to the 
Nimitz and Ford class size and type of aircraft carriers, to see if it make sense. 
We've done this in the past. We're not going to simply break out prior studies, dust them 
off  and  resubmit  it.  We're  taking  a  hard  look  to  see  is  there—is  there  a  sweet  spot, 
something different other than today's 100,000 ton carrier that would make sense to provide 
the power projection that we need, that we get today from our aircraft carriers, but at the 
same time put us in a more affordable position for providing that capability. 
WICKER:  
OK. But right now, he's—he's made a correct factual statement with regard to the lack of 
competition. 
STACKLEY:  
Yes,  Sir.  There  is—yes,  there  is  no  other  shipyard  in  the  world  that  has  the  ability  to 
construct a Ford or a Nimitz nuclear aircraft carrier other than what we have in Newport 
News  and  the  capital  investment  to  do  that  is  prohibitive  to  set  up  a  second  source,  so 
obviously  we are—we are content, not  with the lack of competition, but  we are content 
with knowing that we're only going to have one builder for our aircraft carriers.53 
On March 20, 2015, the Navy provided the following additional statement to the press: 
                                                 
52 Source: Transcript of hearing. 
53 Transcript of hearing. 
Congressional Research Service  
 
29 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
As  indicated  in  testimony,  the  Navy  has  an  ongoing  study  to  explore  the  possible 
composition  of  our  future  large  deck  aviation  ship  force,  including  carriers.  There  is  a 
historical precedent for these type[s] of exploratory studies as we look for efficiencies and 
ways  to  improve  our  war  fighting  capabilities.  This  study  will  reflect  our  continued 
commitment to reducing costs across all platforms by matching capabilities to projected 
threats and Also [sic] seeks to identify acquisition strategies that promote competition in 
naval ship construction. While I can’t comment on an ongoing study, what I can tell you is 
that the results will be used to inform future shipbuilding budget submissions and efforts, 
beyond what is currently planned.54 
Report Required by Section 128 of P.L. 114-92 
Section 128 of the FY2016 National Defense Authorization Act (S. 1356/P.L. 114-92 of 
November 25, 2015) states the following: 
SEC. 128. Limitation on availability of funds for U.S.S. John F. Kennedy (CVN–79). 
(a) Limitation.—Of the funds authorized to be appropriated by this Act or otherwise made 
available for fiscal year 2016 for procurement for the U.S.S. John F. Kennedy (CVN–79), 
$100,000,000 may not be obligated or expended until the date on which the Secretary of 
the  Navy  submits  to  the  congressional  defense  committees  the  certification  under 
subsection  (b)(1)  or  the  notification  under  paragraph  (2)  of  such  subsection,  as  the  case 
may be, and the reports under subsections (c) and (d).... 
(d) Report on future development.— 
(1) IN GENERAL.—Not later than April 1, 2016, the Secretary of the Navy shall submit 
to the congressional defense committees a report on potential requirements, capabilities, 
and  alternatives  for  the  future  development  of  aircraft  carriers  that  would  replace  or 
supplement the CVN–78 class aircraft carrier. 
(2) ELEMENTS.—The report under paragraph (1) shall include the following: 
(A) A description of fleet, sea-based tactical aviation capability requirements for a range 
of operational scenarios beginning in the 2025 timeframe. 
(B)  A  description  of  alternative  aircraft  carrier  designs  that  meet  the  requirements 
described under subparagraph (A). 
(C) A description of nuclear and non-nuclear propulsion options. 
(D) A description of tonnage options ranging from less than 20,000 tons  to greater than 
100,000 tons. 
(E) Requirements for unmanned systems integration from inception. 
(F) Developmental, procurement, and lifecycle cost assessment of alternatives. 
(G) A notional acquisition strategy for the development and construction of alternatives. 
(H)  A  description  of  shipbuilding  industrial  base  considerations  and  a  plan  to  ensure 
opportunity for competition among alternatives. 
(I) A description of funding and timing considerations related to developing the  Annual 
Long-Range Plan for Construction of Naval Vessels required under section 231 of title 10, 
United States Code. 
The report required by Section 128(d) of P.L. 114-92, which was conducted for the Navy by the 
RAND Corporation, was delivered to the congressional defense committees in classified form in 
                                                 
54 As printed in Sam LaGrone, “Navy Conducting Alternative Carrier Study,” USNI News, March 23, 2015. 
Congressional Research Service  
 
30 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
July 2016. An unclassified version of the report was then prepared and issued in 2017 as a 
publicly released RAND report. The executive summary of that report states the following 
(emphasis as in original): 
We analyzed the feasibility of adopting four aircraft carrier concept variants as follow-ons 
to the Ford-class carrier following USS Enterprise (CVN 80) or the as-yet-unnamed CVN 
81.  Among  these  options  are  two  large-deck  carrier  platforms  that  would  retain  the 
capability to launch and recover fixed-wing aircraft using an on-deck catapult and arresting 
gear system and two smaller carrier platforms capable of supporting only short takeoff and 
vertical landing (STVOL) aircraft. Specifically, the four concept variants are as follows: 
• a follow-on variant continuing the current 100,000-ton Ford-class carrier but with two 
life-of-the-ship reactors and other equipment and system changes to reduce cost (we refer 
to this design concept as CVN 8X) 
• a 70,000-ton USS Forrestal–size carrier with an updated flight deck and hybrid nuclear-
powered integrated propulsion plant with capability to embark the current large integrated 
air  wing  but  with  reduced  sortie  generation  capability,  survivability,  and  endurance 
compared with the Ford class (we refer to this design concept as CVN LX) 
•  a  43,000-ton  variant  of  the  USS  America–class,  fossil  fuel–powered  and  arranged  to 
support  only  STOVL  operations  but  at  a  higher  tempo  than  the  current  LHA  6  (USS 
America) (we refer to this design concept as CV LX). This variant would incorporate the 
larger ship’s beam excursion the Navy examined in the LHA 8–class flight 1 studies. 
• a 20,000-ton variant that will resemble escort carriers that some allied navies currently 
operate (we refer to this design concept as CV EX). Similar to the 43,000-ton variant, it 
will be conventionally powered and will operate STOVL aircraft.... 
Our analyses of the carrier variants illuminated capability shortfalls in some instances. Our 
overall findings are as follows: 
• The CVN 8X, the descoped Ford-class carrier, offers similar warfighting capability to 
that  of  the  Ford-class  carrier  today.  There  might  be  opportunities  to  reduce  costs  by 
eliminating costly features that only marginally improve capability, but similar tradeoffs 
are likely to be made in the current program as well. 
• The CVN LX concept variant offers an integrated, current air wing with capabilities near 
current levels but  with less organic  mission endurance for weapons and aviation fuel. It 
will  not  generate  the  same  SGR  as  the  Ford-class  carrier,  but  this  is  not  a  significant 
limitation  for  stressing  warfighting  scenarios.  It  will  be  less  survivable  in  some 
environments and have less redundancy than the Ford program-of-record ship, and these 
factors  might  drive  different  operation  concepts.  Although  we  do  not  characterize  the 
impact  of  decreased  survivability,  this  is  an  important  limitation  that  will  have  to  be 
weighed against the potential cost savings. The major means of reducing cost is through 
engineering redundancy, speed, and air wing fuel capacity, and these could affect mobility 
and theater closure. 
• The concept variant CV LX, which is a version of the LHA 6 platforms, might be a low-
risk, alternative pathway for the Navy to reduce carrier costs if such a variant were procured 
in greater numbers than the current carrier shipbuilding plan; our analysis suggests a two-
to-one replacement. Over the long term, however, as the current carrier force is retired, the 
CV  LX  would  not  be  a  viable  option  for  the  eventual  carrier  force  unless  displaced 
capabilities were reassigned to new aircraft or platforms in the joint force, which would be 
costly. This platform would be feasible for a subset of carrier missions but, even for those 
missions, could require an increase in the number of platforms. This concept variant might, 
if procured in sufficient numbers, eventually enable the Navy to reduce the number of Ford-
class  carriers  in  the  overall  force  structure,  but  more-extensive  analysis  of  missions, 
operations, and basing of such a variant and the supported air combat element is required. 
Congressional Research Service  
 
31 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
• The smallest concept variants reviewed, the CV EX 20,000-ton sea-based platforms, do 
not provide either a significant capacity or an integrated air wing and, thus, force reliance 
on other legacy platforms or land-based assets to provide key elements of capability—in 
particular, AEW. As a result, this concept variant is not really a  replacement for current 
aircraft  carrier  capability  and  would  require  other  platforms,  aircraft,  weapons,  and 
capabilities in the joint force. These platforms  would be a viable pathway only in broad 
fleet architecture transformation providing a narrow mission set, perhaps regionally, and 
would  require  extensive  analysis.  Given  that  such  a  concept  variant  is  not  a  viable 
replacement  for  an  aircraft  carrier,  such  analysis  would  be  required  to  see  whether  any 
adjustment on the current aircraft carrier program would be feasible.... 
The overall results of our cost comparison are as follows: 
•  The  descoped  Ford-class  carrier,  the  CVN  8X,  might  generate  fewer  sorties  than  the 
current  key  performance  parameter  values  for  the  Ford  class  and  might  have  only 
incremental reduction in overall platform cost. The analysis examining cost reduction with 
transition to a life-of-the-ship reactor, such that being done on submarine programs, does 
not appear to be cost effective. Between the developmental costs and a reduced service life, 
there is little cost advantage in this variant. 
• The CVN LX concept would allow considerable savings across the ship’s service life and 
appears to be a viable alternative to consider for further concept exploration. Construction 
costs would be lower; design changes and life-cycle costs would reflect the lessons already 
applied in the Ford class. The reliance on hybrid drive with fewer mechanical parts than 
legacy platforms is likely to further reduce maintenance cost. However, CVN LX would 
be a new design that would require a significant investment in nonrecurring engineering in 
the near term to allow timely delivery in the 2030s. 
• CV LX, although it requires a larger force structure to maintain air capabilities, might 
still  reduce  overall  construction  costs  if  large  carrier  numbers  were  reduced.  But,  as 
described  in  the  report,  reducing  carrier  numbers  with  the  resulting  loss  of  capability 
should not be pursued without extensive further analysis for all displaced missions in the 
joint  force  execution  of  warfighting  scenarios  and,  potentially,  regional  basing  and 
narrowly focused missions for these platforms. Any cost savings would likely be offset to 
an unknown degree by requirements for additional systems to mitigate loss of capability 
associated with this variant. 
• CV EX, the smallest variant, is not a practical variant at all without considerable revision 
of the Navy warfighting concept of operations. Although the same is to a degree true with 
CV LX, the impact of an even larger number of low-sortie ships with small and limited air 
wings is even more pronounced with this variant. CV EX has all of the shortfalls of CV 
LX and will pose even greater issues of mutual support and logistics sustainment.... 
Conclusions 
Our analysis points to potential options for replacing the Nimitz-class carrier as these ships 
reach expected service life that have lower procurement costs than the Ford-class carriers. 
However, most of these options come with reduced capability that might require changes 
in the concept of operations to deliver sea-based aircraft capability comparable to that of 
carriers in the fleet today. If a new platform is introduced in the  mid-2030s, the Navy’s 
force structure will still contain a large legacy force of Nimitz- and Ford-class carriers, at 
least  until  the  mid-2050  time  frame,  which  might  lower  the  risks  of  introducing  a  new 
carrier for some period of time. But, ultimately, if a new carrier variant is selected, it will 
define  the  carrier  force  and  constitute  the  supported  capability  available  to  the  Navy. 
Capability  shortfalls  can  be  mitigated,  to  some  degree,  with  changes  in  operational 
concepts  or  by  adding  additional  platforms  to  the  force  structure—which  introduces 
additional  cost  that  might  offset  anticipated  cost  savings.  In  addition,  if  the  Navy  stops 
Congressional Research Service  
 
32 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
procuring large-deck nuclear carriers, the ability to reconstitute the industrial base at some 
time in the future comes with substantial risk. 
Although  SGR  [sortie  generation  rate]  was  a  central  variable  in  comparing  the  carrier 
variants, our analysis suggests that there is room to make trade-offs in aircraft sortie rate 
capacity between the Ford-class carrier and a lower-cost platform. However, it is important 
to  consider  that,  whatever  threats  complicate  carrier  operations,  they  might  even  more 
significantly affect land-based tactical air operations. Carriers can move; have defensive 
support  from  escorts;  can  readily  replenish;  and  might,  in  fact,  be  more  survivable  than 
their land-based counterparts. This is an important factor for Congress and the Department 
of Defense to consider before a trade-off is made to give up the supported air wing sortie 
generation capacity in the overall sea-based force.55 
The question of whether to shift to smaller aircraft carriers was also addressed in three studies on 
future fleet architecture that were required by Section 1067 of the FY2016 National Defense 
Authorization Act (S. 1356/P.L. 114-92 of November 25, 2015). These three studies are discussed 
in more detail in another CRS report.56 
February 2019 Press Report 
A February 15, 2019, press report stated the following: 
Under Secretary of the Navy Thomas Modly said now that the Navy found a way to build 
two new Gerald R. Ford-class aircraft carriers while saving money it is starting to look at 
future carrier procurement, which might be very different.… 
Modly  said  Secretary  of  the  Navy  Richard  Spencer  sees  $13  billion  carriers  as  not 
sustainable going forward and the service will be looking at ways to further reduce costs 
or keep the carrier capabilities more affordable in future ship procurements. 
“There was general conclusion that those two for sure would be built” and once that was 
determined  “that  was  going  to  happen,”  Modly  said  during  the  AFCEA  West  2019 
conference here [in San Diego].… 
After the CVN-80 and -81 [procurement] decision was made, “I think a lot of derivative 
decisions  still  need  to  be  made.  So  the  secretary  [Spencer]  would  like  to  take  a  look  at 
‘O.K. now that we made that decision, and that second one that comes will be in quite a 
few years from now, we need to start thinking now about what’s the next one look like.’” 
Modly told reporters they are asking questions like “Is it going to be advanced as this one? 
Or is it  going to be smaller or are  we  going to buy two smaller ones or  maybe  shift air 
power to other forms of delivery. And we don’t know the answers of that but we’re looking 
at this.”57 
Legislative Activity for FY2019 
July 11, 2018, Reprogramming Request 
In addition to congressional action on the FY2019 funding request for the CVN-78 program 
discussed below, a DOD reprogramming request dated July 11, 2018, requested that $62.7 million 
                                                 
55 Bradley Martin and Michael McMahon, Future Aircraft Carrier Options, Santa Monica, CA, RAND Corporation, 
2017, pp. xi-xviii. The report was provided by Navy Office of Legislative Affairs to CRS and CBO on October 2, 2017. 
56 See CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by 
Ronald O'Rourke. 
57 Rich Abott, “Navy Starts Looking At Carriers After CVN-81,” Defense Daily, February 15, 2019. 
Congressional Research Service  
 
33 
 link to page 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
be reprogrammed to the CVN-78 program to cover cost growth on CVN-78. The $62.7 million 
includes 
  $12.7 million for “re-baselining the Advanced Weapons Elevator program to 
address continuing technical difficulties”; 
  $30.0 million for “engineering, tooling, and repair of Main Thrust Bearings” in 
the ship’s propulsion train; 
  $11.0 million for “emergent technical issues and correction of deficiencies 
identified during operational testing and extension of the Post-Shakedown 
Availability [PSA] duration to accomplish required scope and repair of the 
propulsion train components”; and 
  $9.0 million “to cover the increase cost of deferred work, labor and material.” 
The $62.7 million would be reprogrammed from FY2011 procurement funding for the DDG-51 
destroyer program.58 
Summary of Congressional Action on FY2019 Funding Request 
Table 4 summarizes congressional action on the FY2019 procurement and advance procurement 
funding request for the CVN-78 program. 
Table 4. Congressional Action on FY2019 Funding Request 
Millions of dollars, rounded to nearest tenth.  
Authorization 
Appropriation 
 
Request 
HASC 
SASC 
Conf. 
HAC 
SAC 
Conf. 
Procurement 
1,598.2 
1,549.1 
1,598.2 
1,598.2 
1,598.2 
1,573.2 
1,573.2 
Source: Table prepared by CRS based on Navy’s FY2019 budget submission, committee and conference 
reports, and explanatory statements on FY2018 National Defense Authorization Act and FY2019 DOD 
Appropriations Act. 
Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is 
House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference agreement. 
National Defense Authorization Act for Fiscal Year 2019/John S. 
McCain National Defense Authorization Act for Fiscal Year 2019 
(H.R. 5515/S. 2987/P.L. 115-232) 
House Committee Report 
The House Armed Services Committee, in its report (H.Rept. 115-676 of May 15, 2018) on H.R. 
5515, recommended the funding level for the CVN-78 program shown in the HASC column of 
                                                 
58 See page 85 of 85 (i.e., the final page) of the reprogramming request. The document was posted by 
InsideDefense.com (subscription required) on July 16, 2018. See also David B. Larter, “US Navy Asks Congress to 
Shift Millions of Dollars to Fix High-Tech Supercarrier,” Defense News, July 18, 2018; Jason Sherman, “Pentagon 
Seeks Additional Funding for CVN-78, Breaching Current Statutory Cost Cap,” Inside Defense (Daily News), July 19, 
2018. 
Congressional Research Service  
 
34 
 link to page 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 4. The recommended reduction of $49.1 million is for “Excess change order rate.” (Page 
344) 
Section 121 of H.R. 5515 as reported by the committee states the following: 
SEC. 121. Increase in number of operational aircraft carriers of the Navy.  
(a) Findings.—Congress finds the following:  
(1) The aircraft carrier can fulfill the Navy’s core missions of forward presence, sea control, 
ensuring safe sea lanes, and power projection as well as providing flexibility and versatility 
to execute a wide range of additional missions. 
(2) Forward airpower is integral to the security and joint forces operations of the United 
States. Carriers play a central role in delivering forward airpower from sovereign territory 
of the United States in both permissive and nonpermissive environments. 
(3)  Aircraft  carriers  provide  our  Nation  the  ability  to  rapidly  and  decisively  respond  to 
national  threats,  as  well  as  conducting  worldwide,  on-station  diplomacy  and  providing 
deterrence against threats to the United States allies, partners, and friends. 
(4) Since the end of the cold war, aircraft carrier deployments  have increased  while the 
aircraft carrier force structure has declined. 
(5) Considering the increased array of complex threats across the globe, the Navy aircraft 
carrier is operating at maximum capacity, increasing deployment lengths and decreasing 
maintenance periods in order to meet operational requirements. 
(6)  To  meet  global  peacetime  and  wartime  requirements,  the  Navy  has  indicated  a 
requirement to maintain two aircraft carriers deployed overseas and have three additional 
aircraft carriers capable of deploying within 90 days. However, the Navy has indicated that 
the existing aircraft carrier force structure cannot support these military requirements. 
(7) Despite the requirement to maintain an aircraft carrier strike group in both the United 
States  Central  Command  and  the  United  States  Pacific  Command,  the  Navy  has  been 
unable to generate sufficient capacity to support combatant commanders and has developed 
significant carrier gaps in these critical areas. 
(8) Because of the continuing use of a diminished aircraft carrier force structure, extensive 
maintenance availabilities result which typically exceed program costs and increase time 
in shipyards. These expansive maintenance availabilities exacerbate existing carrier gaps. 
(9) Developing an alternative design to the Ford-class aircraft carrier is not cost beneficial. 
A  smaller  design  is  projected  to  incur  significant  design  and  engineering  cost  while 
significantly  reducing  magazine  size,  carrier  air  wing  size,  sortie  rate,  and  on-station 
effectiveness, among other vital factors, as compared to the Ford-class. Furthermore, a new 
design will delay the introduction of future aircraft carriers, exacerbating existing carrier 
gaps and threatening the national security of the United States. 
(10) The 2016 Navy Force Structure Assessment states “A minimum of 12 aircraft carriers 
are  required  to  meet  the  increased  warfighting  response  requirements  of  the  Defense 
Planning Guidance Defeat/Deny force sizing direction.”. 
(b) Sense of congress.—It is the sense of Congress that—  
(1) the United States should expedite delivery of 12 aircraft carriers; and 
(2) an aircraft carrier should be authorized every three years. 
(c) Increase in number of operational aircraft carriers of the navy.—  
Congressional Research Service  
 
35 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(1) INCREASE.—Section 5062(b) of title 10, United States Code,59 is amended by striking 
“11 operational aircraft carriers” and inserting “12 operational aircraft carriers”. 
(2)  EFFECTIVE  DATE.—The  amendment  made  by  paragraph  (1)  shall  take  effect  on 
September 30, 2022. 
Section 122 of H.R. 5515 as reported by the committee states the following: 
SEC. 122. Procurement authority for Ford class aircraft carrier program.  
(a) Contract authority.—  
(1) PROCUREMENT AUTHORIZED.—The Secretary of the Navy may enter into one or 
more contracts, beginning with the fiscal year 2019 program year, for the procurement of 
one Ford class aircraft carrier to be designated CVN–81. 
(2)  PROCUREMENT  IN  CONJUNCTION  WITH  CVN–80.—The  aircraft  carrier 
authorized  to  be  procured  under  subsection  (a)  may  be  procured  as  an  addition  to  the 
contract covering the Ford class aircraft carrier designated CVN–80 that is authorized to 
be constructed under section 121 of the John Warner National Defense Authorization Act 
for Fiscal Year 2007 (Public Law 109–364; 120 Stat. 2104). 
(b) Use of incremental funding.—With respect to a contract entered into under subsection 
(a), the Secretary of the Navy may use incremental funding to make payments under the 
contract. 
(c)  Liability.—A  contract  entered  into  under  subsection  (a)  shall  provide  that  the  total 
liability to the Government for termination of the contract entered into shall be limited to 
the total amount of funding obligated at the time of termination. 
(d) Condition for out-year contract payments.—A contract entered into under subsection 
(a)  shall  provide  that  any  obligation  of  the  United  States  to  make  a  payment  under  the 
contract for a fiscal year is subject to the availability of appropriations for that purpose for 
such fiscal year. 
Section 123 of H.R. 5515 as reported by the committee states the following: 
SEC. 123. Full ship shock trial for Ford class aircraft carrier.  
The Secretary of the Navy shall ensure that full ship shock trials results are incorporated 
into the construction of the Ford class aircraft carrier designated CVN–81. 
Section 220 of H.R. 5515 as reported by the committee states the following: 
SEC.  220.  Modification  of  CVN–73  to  support  fielding  of  MQ–25  unmanned  aerial 
vehicle.  
The  Secretary  of  the  Navy  shall  ensure  that  the  aircraft  carrier  designated  CVN–73  is 
modified to support the fielding of the MQ–25 unmanned aerial vehicle before the date on 
which the refueling and complex overhaul of the aircraft carrier is completed. 
Section 1024(c)(2) of H.R. 5515 as reported by the committee states the following: 
(2) MODIFICATION OF ADVANCE PROCUREMENT FUNDING.—Section 124 of the 
National Defense Authorization Act for Fiscal Year 2010 (Public Law 111–84; 123 Stat. 
2214; 10 U.S.C. 7291 note) is amended—  
                                                 
59 As noted earlier, 10 U.S.C. 5062 was renumbered as 10 U.S.C. 8062 by Section 807 of the John S. McCain National 
Defense Authorization Act for Fiscal Year 2019 (H.R. 5515/P.L. 115-232 of August 13, 2018), which directed a 
renumbering of sections and titles of Title 10 relating to the Navy and Marine Corps. (Sections 806 and 808 of P.L. 
115-232 directed a similar renumbering of sections and titles relating to the Air Force and Army, respectively.) 
Congressional Research Service  
 
36 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(A) by striking subsection (a); and 
(B) by redesignating subsections (b) and (c) as subsections (a) and (b), respectively.60 
H.Rept. 115-676 states the following: 
Nimitz-class aircraft carrier service life extension 
In December 2016, the Secretary of the Navy determined that a 355-ship Navy is required 
to support force structure demands. A part of this force structure requirement is a power 
projection  requirement  of  12  aircraft  carriers.  With  the  delivery  of  the  USS  John  F. 
Kennedy  (CVN  79)  in  2023,  the  Navy  will  reach  their  12  aircraft  carrier  goal  but  will 
quickly lose this overall capacity with the programmed retirement of USS  Nimitz (CVN 
68) in fiscal year 2023. 
The committee believes that there are several options to retain required aircraft carrier force 
structure to include accelerating construction of the Ford-class carriers. Additionally, the 
committee believes that service life extension options may be available for USS  Nimitz. 
Therefore,  the  committee  directs  the  Secretary  of  the  Navy  to  provide  a  briefing  to  the 
House Committee on Armed Services by March 1, 2019, on options that exist to extend 
the service life of USS Nimitz, to include the extension of major components. Additionally, 
such a briefing should include cost estimates and major modernization components. (Pages 
17-18) 
H.Rept. 115-676 also states the following: 
Carrier Presence in the Middle East 
The committee recognizes the importance of maintaining an aircraft carrier strike group in 
the U.S. Central Command (CENTCOM) area of operations to deter the Islamic Republic 
of Iran, support ongoing missions in the Republic of Iraq, the Syrian Arab Republic, and 
the Islamic Republic of Afghanistan, provide assurance to regional partners, and maintain 
the capacity to flexibly respond to a variety of crises across the volatile region. The Navy 
currently struggles to meet combatant commander presence requirements in CENTCOM 
and a recent gap in carrier presence there temporarily limited CENTCOM’s capacity to 
address these security challenges. In an effort to more quickly reach the requirement for 12 
                                                 
60 Section 124 of the FY2010 National Defense Authorization Act (H.R. 2647/P.L. 111-84 of October 28, 2009) states 
the following: 
SEC. 124. ADVANCE PROCUREMENT FUNDING. 
(a) Advance Procurement.--With respect to a naval vessel for which amounts are authorized to be 
appropriated or otherwise made available for fiscal year 2010 or any fiscal year thereafter for 
advance procurement in shipbuilding and conversion, Navy, the Secretary of the Navy may enter 
into a contract, in advance of a contract for construction of any vessel, for any of the following: 
(1) Components, parts, or materiel. 
(2) Production planning and other related support services that reduce the overall procurement lead 
time of such vessel. 
(b) Aircraft Carrier Designated CVN-79.--With respect to components of the aircraft carrier 
designated CVN-79 for which amounts are authorized to be appropriated or otherwise made 
available for fiscal year 2010 or any fiscal year thereafter for advance procurement in shipbuilding 
and conversion, Navy, the Secretary of the Navy may enter into a contract for the advance 
construction of such components if the Secretary determines that cost savings, construction 
efficiencies, or workforce stability may be achieved for such aircraft carrier through the use of such 
contract. 
(c) Condition of Out-year Contract Payments.--A contract entered into under subsection (b) shall 
provide that any obligation of the United States to make a payment under such contract for any 
fiscal year after fiscal year 2010 is subject to the availability of appropriations for that purpose for 
such fiscal year. 
Congressional Research Service  
 
37 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
aircraft carriers identified in the  most recent Force Structure Assessment and to achieve 
greater  cost  savings,  the  committee  authorized  an  acceleration  of  the  next  Ford-class 
aircraft carrier designated CVN–81 in fiscal year 2019. The committee also recommends 
that the Navy assess options to extend the service life of USS Nimitz (CVN 68) to mitigate 
potential gaps, which could affect CENTCOM’s regional force presence. (Pages 194-195) 
A May 22, 2018, statement of Administration policy on H.R. 5515 states the following: 
The Administration appreciates the Committee’s support for increasing the size of the fleet 
and shares the Committee’s desire to increase our submarine and carrier force. However, 
the  Administration  objects  to  specific  provisions  which  may  inadvertently  restrict  the 
ability to invest in our fleet in a responsible and sustainable manner. For instance.... section 
122(b)  provides  incremental  funding  authority  over  an  indefinite  period  for  CVN-81  as 
well as CVN-80, which is inconsistent with acquisition best practices. Additionally, section 
121 increases the requirement for operational aircraft carriers from 11 to 12, which may 
not be sustainable within the Navy’s current topline. The Administration looks forward to 
working with Congress to determine the most cost-effective and fiscally responsible path 
forward to deliver the Navy the Nation needs.61 
House Floor Action 
On May 24, 2018, as part of its consideration of H.R. 5515, the House agreed to by voice vote 
H.Amdt. 659, an en bloc amendment that included, inter alia, amendment number 156 as printed 
in H.Rept. 115-702 of May 22, 2018, on H.Res. 908, providing for the further consideration of 
H.R. 5515. Amendment number 156 added the following section to H.R. 5515: 
SEC. 338. Report on relocation of steam turbine production from Nimitz-class and Ford-
class aircraft carriers, and Virginia-class and Columbia-class submarines.  
Not later than 180 days after the date of the enactment of this Act, the Secretary of Defense, 
in  consultation  with  the  Under  Secretary  of  Defense  for  Acquisition,  Technology,  and 
Logistics, and Assistant Secretary of the Navy for Research, Development and Acquisition, 
shall develop and submit to Congress a report describing the potential impacts on national 
defense and the manufacturing base resulting from contractors or subcontracts relocating 
steam  turbine  production  for  Nimitz-class  and  Ford-class  aircraft  carriers,  and  Virginia-
class and Columbia-class submarines. Such report shall address each of the following: 
(1) The overall risk of moving production on our national security including likelihood of 
production delay or reduction in quality of steam turbines. 
(2)  The  impact  on  natural  security  from  a  delay  in  production  of  aircraft  carriers  and 
submarines.  
(3) The impacts on regional suppliers the current production of steam turbines draw on and 
their ability to perform other contracts should a relocation happen. 
(4) The impact on the national industrial and manufacturing base and loss of a critically 
skilled workforce resulting from a relocation of production. 
(5) The risk of moving production on total cost of the acquisition. 
                                                 
61 Executive Office of the President, Statement of Administration Policy, H.R. 5515—National Defense Authorization 
Act for Fiscal Year 2019, May 22, 2018, p. 3. 
Congressional Research Service  
 
38 
 link to page 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Senate 
The Senate Armed Services Committee, in its report (S.Rept. 115-262 of June 5, 2018) on S. 
2987, recommended the funding level for the CVN-78 program shown in the SASC column of 
Table 4. 
Section 127 of S. 2987 as reported states the following: 
SEC. 127. Nuclear refueling of aircraft carriers. 
(a) Authorization To procure nuclear refueling  materials.—Pursuant to section 7314a of 
title 10, United States Code, as added by section 1014 of this Act, the Secretary of the Navy 
may procure naval nuclear reactor power units and associated reactor components for the 
following aircraft carriers:  
(1) U.S.S. John C. Stennis (CVN–74). 
(2) U.S.S. Harry S. Truman (CVN–75). 
(3) U.S.S. Ronald Reagan (CVN–76). 
(4) U.S.S. George H.W. Bush (CVN–77). 
(b) Condition for out-year payments.—Any contract entered into under subsection (a) shall 
provide that any obligation of the United States to make a payment under the contract for 
a  fiscal  year  after  fiscal  year  2019  is  subject  to  availability  of  appropriations  for  that 
purpose for that later fiscal year. 
Regarding Section 127, S.Rept. 115-262 states the following: 
Nuclear refueling of aircraft carriers (sec. 127) 
The  committee  recommends  a  provision  that  would  authorize  the  procurement  of  naval 
nuclear reactor power units and associated reactor components for the nuclear refueling of 
the  following  aircraft  carriers:  USS  John  C.  Stennis  (CVN–74),  USS  Harry  S.  Truman 
(CVN–75), USS Ronald Reagan (CVN–76), and USS George H.W. Bush (CVN–77). 
The committee notes that the procurement lead time for some nuclear components required 
to conduct a nuclear refueling precedes the authorization for the associated aircraft carrier 
refueling by several years. 
Accordingly, pursuant to section 7314a of title 10, United States Code, as added by section 
1014  of  this  Act  [see  discussion  below],  in  order  to  maintain  appropriate  oversight  of 
program execution of the nuclear refueling of aircraft carriers, the committee recommends 
the authorizations contained in this provision. (Page 10) 
Section 1014 of S. 2987 as reported states the following: 
SEC. 1014. Specific authorization requirement for nuclear refueling of aircraft carriers. 
(a) In general.—Chapter 633 of title 10, United States Code, is amended by inserting after 
section 7314 the following new section: 
 “§ 7314a. Nuclear refueling of aircraft carriers: specific authorization required 
“Funds may not be obligated or expended for the procurement of a naval nuclear reactor 
power unit or associated reactor components for the nuclear refueling of an aircraft carrier 
unless such refueling is specifically authorized, by ship name and hull number, by statute.”. 
(b) Clerical amendment.—The table of sections at the beginning of chapter 633 of such 
title is amended by inserting after the item relating to section 7314 the following new item: 
“7314a. Nuclear refueling of aircraft carriers: specific authorization required.”. 
Congressional Research Service  
 
39 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Regarding Section 1014, S.Rept. 115-262 states the following: 
Specific  authorization  requirement  for  nuclear  refueling  of  aircraft  carriers  (sec. 
1014) 
The  committee  recommends  a  provision  that  would  require  a  specific  authorization  by 
statute before funds may be obligated or expended for the procurement of a naval nuclear 
reactor power unit or associated reactor components for the nuclear refueling of an aircraft 
carrier. 
The committee notes that the procurement lead time for some nuclear components required 
to conduct a nuclear refueling precedes the authorization for the associated aircraft carrier 
refueling by several years. 
Accordingly,  in  order  to  maintain  appropriate  oversight  of  program  execution,  the 
committee believes that the Department of Defense should obtain a specific authorization 
for such nuclear components. (Page 261) 
Section 1015 of S. 2987 as reported states the following: 
SEC. 1015. Dismantlement and disposal of nuclear-powered aircraft carriers. 
(a) In general.—Chapter 633 of title 10, United States Code, is amended by adding at the 
end the following new section: 
“§ 7320. Nuclear-powered aircraft carriers: dismantlement and disposal 
“(a) In general.—Not less than 90 days before the award of a contract for the dismantlement 
and  disposal  of  a  nuclear-powered  aircraft  carrier,  or  the  provision  of  funds  to  a  naval 
shipyard  for  the  dismantlement  and  disposal  of  a  nuclear-powered  aircraft  carrier,  the 
Secretary of the Navy shall submit to the congressional defense committees a report setting 
forth the following:  
“(1)  A  cost  and  schedule  baseline  for  the  dismantlement  and  disposal  approved  by  the 
service  acquisition  executive  of  the  Department  of  the  Navy  and  the  Chief  of  Naval 
Operations. 
“(2)  An  independent  cost  estimate  of  the  dismantlement  and  disposal  prepared  by  the 
Office of Cost Analysis and Program Evaluation. 
“(3)  A  description  of  the  regulatory  framework  applicable  to  the  management  of 
radioactive  materials  in  connection  with  the  dismantlement  and  disposal,  including,  in 
cases in which the Navy intends to have another government entity serve as the regulatory 
enforcement authority—  
“(A) a certification from that entity of its agreement to serve as the regulatory enforcement 
authority; and 
“(B) a description of the legal basis for the authority of that entity to serve as the regulatory 
enforcement authority. 
“(b) Supplemental information with budgets.—In the materials submitted to Congress by 
the  Secretary  of  Defense  in  support  of  the  budget  of  the  President  for  a  fiscal  year  (as 
submitted to Congress under section 1105(a) of title 31), the Secretary of the Navy shall 
include  information  on  each  dismantlement  and  disposal  of  a  nuclear-powered  aircraft 
carrier occurring or planned to occur during the period of the future-years defense program 
submitted to Congress with that budget. Such information shall include, by ship concerned, 
the following:  
“(1)  A  summary  of  activities  and  significant  developments  in  connection  with  such 
dismantlement and disposal. 
Congressional Research Service  
 
40 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
“(2)  If  applicable,  a  detailed  description  of  cost  and  schedule  performance  against  the 
baseline  for  such  dismantlement  and  disposal  established  pursuant  to  subsection  (a), 
including a description of and explanation for any variance from such baseline. 
“(3) A description of the amounts requested, or intended or estimated to be requested, for 
such dismantlement and disposal for each of the following:  
“(A) Each fiscal year covered by the future-years defense program. 
“(B) Any fiscal years before the fiscal years covered by the future-years defense program. 
“(C) Any fiscal years after the end of the period of the future-years defense program. 
“(c) Future-years defense program defined.—In this section, the term ‘future-years defense 
program’ means the future-years defense program required by section 221 of this title.”. 
(b) Clerical amendment.—The table of sections at the beginning of chapter 633 of such 
title is amended by adding at the end the following new item: 
“7320. Nuclear-powered aircraft carriers; dismantlement and disposal.”. 
Regarding Section 1015, S.Rept. 115-262 states the following: 
Dismantlement and disposal of nuclear-powered aircraft carriers (sec. 1015) 
The committee recommends  a provision that  would require a report be submitted to the 
congressional  defense  committees  prior  to  awarding  a  contract  for  dismantlement  and 
disposal of a nuclear-powered aircraft carrier or providing funding to a naval shipyard for 
dismantlement and disposal of a nuclear-powered aircraft carrier. 
The provision would also require additional information be provided on the dismantlement 
and  disposal  of  nuclear-powered  aircraft  carriers  with  the  materials  submitted  to  the 
Congress by the Secretary of Defense in support of the budget of the President for each 
fiscal year. 
The committee notes that in response to the Senate report accompanying S. 1519 (S. Rept. 
115–125)  of  the  National  Defense  Authorization  Act  for  Fiscal  Year  2018  (Public  Law 
115–91) the U.S. Government Accountability Office (GAO) has briefed the committee on 
the Navy’s considerations for the dismantlement and disposal of the ex-USS Enterprise 
nuclear-powered aircraft carrier. 
The committee further notes GAO’s preliminary analysis indicates that the anticipated cost 
and  schedule  for  dismantlement  and  disposal  of  the  Navy’s  nuclear-powered  aircraft 
carriers  are  comparable  to  large  Department  of  Defense  (DOD)  acquisition  programs, 
which have structured oversight to support transparency and accountability; however, ship 
dismantlement and disposal has no specific reporting requirements under DOD or Navy 
policy. 
The  committee  believes  information  provided  on  dismantlement  and  disposal  as  part  of 
annual budget requests currently lacks sufficient detail to inform oversight of ship-specific 
activities.  As  the  Navy  has  yet  to  dismantle  and  dispose  of  a  nuclear-powered  aircraft 
carrier,  the  committee  further  believes  establishing  formal  requirements  will  set  a 
precedent to enable sufficient oversight for these large-scale dismantlement and disposal 
efforts. (Pages 261-262) 
S.Rept. 115-262 also states the following: 
Aircraft carrier acquisition 
The Department of Defense has been able to achieve program efficiencies and cost-savings 
by  using  multiyear  and  block  buy  contracting  with  many  weapons  programs,  to  include 
shipbuilding. Section 2306b of title 10, United States Code, sets forth criteria for requesting 
and  evaluating  multiyear  contracting  proposals.  Although  similar  criteria  for  block  buy 
Congressional Research Service  
 
41 
 link to page 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
authorities  are  not  codified,  the  committee  expects  the  Department  to  conduct  rigorous 
analysis of proposals and provide that analysis to the Congress, and that the Department’s 
analysis  will  show  a  sound  business  case  with  substantial  savings  from  committing  the 
government to a longer term contract. 
Earlier this year, the Navy issued a request for proposal soliciting information on a potential 
block  buy  to  acquire  two  Ford-class  aircraft  carriers  (CVN–80  and  CVN–81).  The 
committee will review any information that the Navy provides related to such an approach 
as consideration of the National Defense Authorization Act for Fiscal Year 2019 continues. 
(Pages 39-40) 
S.Rept. 115-262 also states the following: 
Ford-class sustainment and product support 
The committee notes that with the delivery of the USS Gerald R. Ford (CVN–78) in May 
2017, sustainment and product support of this new class of aircraft carriers will be critical 
to mission effectiveness and operational availability. As the Ford-class program continues 
with testing and delivery of additional aircraft carriers, the committee believes life cycle 
sustainment planning must be properly funded to maintain hull, mechanical, electrical, and 
combat systems to the class’ 50-year service life. 
Accordingly, the committee is concerned that the budget request included no funding for 
maintaining Electromagnetic Aircraft Launch System software. The committee urges the 
Navy to plan for and appropriately fund sustainment and product support for Ford-class 
aircraft carriers, particularly systems critical to mission accomplishment. (Page 44) 
S.Rept. 115-262 also states the following: 
Nimitz-class aircraft carrier service life assessment 
The committee notes that the first Nimitz-class aircraft carrier, USS Nimitz (CVN–68) is 
planned  to  decommission  in  fiscal  year  2025  at  its  expected  service  life  of  50  years  of 
service. The committee further notes that the Navy has extended the service lives of many 
ship classes,  including  Ohio-class  nuclear-powered ballistic  missile  submarines  from 30 
years to 42 years. Recognizing the policy of the United States to achieve a 355-ship Navy 
includes  12  aircraft  carriers,  the  committee  is  interested  in  better  understanding  the 
technical and engineering feasibility of extending Nimitz-class aircraft carriers beyond the 
class’ 50-year planned service life. 
Therefore,  the  committee  directs  the  Secretary  of  the  Navy  to  submit  a  report  to  the 
congressional defense committees not later than January 1, 2019, on the options to extend 
the  service  lives  of  Nimitz-class  aircraft  carriers.  This  report  shall  include  each  of  the 
following:  (1)  The  technical  and  engineering  feasibility  of  extending  the  service  life  of 
each  Nimitz-class  aircraft  carrier;  (2)  The  duration  of  such  service  life  extensions;  (3) 
Notional  cost  and  schedule  estimates  for  Nimitz-class  aircraft  carrier  service  life 
extensions;  (4)  Public  or  private  shipyard  availability  to  accomplish  such  service  life 
extensions; and (5) An assessment by the Secretary on the merits of implementing such 
options. (Page 277) 
Conference 
The conference report (H.Rept. 115-874 of July 25, 2018) on H.R. 5515/P.L. 115-232 of August 
13, 2018, recommended the funding level for the CVN-78 program in the authorization 
conference column of Table 4. 
Section 121 of H.R. 5515 states the following: 
SEC. 121. PROCUREMENT AUTHORITY FOR FORD CLASS AIRCRAFT CARRIER 
PROGRAM. 
Congressional Research Service  
 
42 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(a) CONTRACT AUTHORITY.— 
(1) PROCUREMENT AUTHORIZED.—The Secretary of the Navy may enter into one or 
more contracts, beginning with the fiscal year 2019 program year, for the procurement of 
one Ford class aircraft carrier to be designated CVN–81. 
(2)  PROCUREMENT  IN  CONJUNCTION  WITH  CVN–80.—The  aircraft  carrier 
authorized  to  be  procured  under  paragraph  (1)  may  be  procured  as  an  addition  to  the 
contract covering the Ford class aircraft carrier designated CVN–80 that is authorized to 
be constructed under section 121 of the John Warner National Defense Authorization Act 
for Fiscal Year 2007 (Public Law 109–364; 120 Stat. 2104). 
(b) CERTIFICATION REQUIRED.—A contract may not be entered into under subsection 
(a) unless the Secretary of Defense certifies to the congressional defense committees, in 
writing, not later than 30 days before entry into the contract, each of the following, which 
shall  be  prepared  by  the  milestone  decision  authority  for  the  Ford  class  aircraft  carrier 
program: 
(1)  The  use  of  such  a  contract  will  result  in  significant  savings  compared  to  the  total 
anticipated costs of carrying out the program through annual contracts. In certifying cost 
savings  under  the  preceding  sentence,  the  Secretary  shall  include  a  written  explanation 
of— 
(A) the estimated obligations and expenditures by fiscal year for CVN–80 and CVN–81, 
by hull, without the authority provided in subsection (a); 
(B) the estimated obligations and expenditures by fiscal year for CVN–80 and CVN–81, 
by hull, with the authority provided in subsection (a); 
(C) the estimated cost savings or increase by fiscal year for CVN–80 and CVN–81, by hull, 
with the authority provided in subsection (a); 
(D) the discrete actions that will accomplish such cost savings or avoidance; and 
(E) the contractual actions that will ensure the estimated cost savings are realized. 
(2) There is a reasonable expectation that throughout the contemplated contract period the 
Secretary of  Defense  will request  funding  for the contract  at the level required to avoid 
contract cancellation. 
(3)  There  is  a  stable  design  for  the  property  to  be  acquired  and  that  the  technical  risks 
associated with such property are not excessive. 
(4) The estimates of both the cost of the contract and the anticipated cost avoidance through 
the use of a contract authorized under subsection (a) are realistic. 
(5) The use of such a contract will promote the national security of the United States. 
(6) During the fiscal year in which such contract is to be awarded, sufficient funds will be 
available to perform the contract in such fiscal year, and the future-years defense program 
(as  defined  under  section  221  of  title  10,  United  States  Code)  for  such  fiscal  year  will 
include the funding required to execute the program without cancellation. 
(7) The contract will be a fixed price type contract. 
(c) USE OF INCREMENTAL FUNDING.—With respect to a contract entered into under 
subsection (a), the Secretary of the Navy may use incremental funding to make payments 
under the contract. No such payments  may be obligated after the date that is 11 months 
after the date on which the fitting out of the aircraft carrier associated with the contract is 
completed. 
Congressional Research Service  
 
43 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(d) LIABILITY.—A contract entered into under subsection (a) shall provide that the total 
liability to the Government for termination of the contract entered into shall be limited to 
the total amount of funding obligated at the time of termination. 
(e) CONDITION FOR OUT-YEAR CONTRACT PAYMENTS.—A contract entered into 
under  subsection  (a)  shall  provide  that  any  obligation  of  the  United  States  to  make  a 
payment under the contract for a fiscal year is subject to the availability of appropriations 
for that purpose for such fiscal year. 
(f)  MILESTONE  DECISION  AUTHORITY  DEFINED.—In  this  section,  the  term 
‘‘milestone decision authority’’ has the meaning given that term in section 2366a(d) of title 
10, United States Code. 
Regarding Section 121, H.Rept. 115-874 states the following: 
Procurement authority for Ford-class aircraft carrier program (sec. 121) 
The House bill contained a provision (sec. 122) that would authorize the construction of 
one Ford-class aircraft carrier designated CVN–81. 
The Senate amendment contained no similar provision. 
The Senate recedes with an amendment that would require a certification prior to awarding 
a contract authorized by this provision. The conferees note that the Department of Defense 
has  been  able  to  achieve  program  efficiencies  and  cost  savings  by  using  multiyear  and 
block  buy  contracting  with  many  weapons  programs,  to  include  shipbuilding.  If  the 
Department of the Navy intends to pursue a two-ship procurement of CVN–80 and CVN–
81  outside  the  title  10,  United  States  Code,  parameters  for  a  multiyear  contract,  the 
conferees expect that entering into such contract would be based on rigorous analysis with 
a sound business case and substantial savings. 
Earlier this year, the Navy issued a request for proposal soliciting information on a potential 
contract to acquire two Ford-class aircraft carriers (CVN–80 and CVN–81). The conferees 
are  disappointed  that  no  related  information  was  provided  to  the  congressional  defense 
committees  to  enable  fulsome  consideration  of  the  associated  required  legislative 
authorities during the development of the National Defense Authorization Act for Fiscal 
Year 2019. 
Nonetheless, the conferees believe a two-ship procurement of CVN–80 and CVN–81 could 
result in significant cost savings. Accordingly, this provision would provide the necessary 
authorities  for  implementing  such  an  approach,  if  the  Secretary  of  Defense  certifies 
supporting  analysis  prepared  and  provided  by  the  milestone  decision  authority  for  the 
carrier  replacement  program,  which  is  the  Department  of  the  Navy  Service  Acquisition 
Executive. 
It is the conferees’ intent that the Secretary of Defense review such analysis and, if the 
Secretary deems it appropriate, make the certification without performing any separate cost 
assessments  or  analyses.  The  conferees  view  such  a  process  as  consistent  with  ongoing 
efforts to reduce the time associated with acquisition decisions, push acquisition authorities 
and  accountability  to  the  Services,  and  ensure  that  the  Secretary  of  Defense  retains 
visibility and ultimate authority over acquisition matters in the Department. (Page 800) 
Section 122 of H.R. 5515 states the following: 
SEC. 122. FULL SHIP SHOCK TRIAL FOR FORD CLASS AIRCRAFT CARRIER. 
The Secretary of the Navy shall ensure that full ship shock trials results are incorporated 
into the construction of the Ford class aircraft carrier designated CVN–81. 
Section 123 of H.R. 5515 states the following: 
Congressional Research Service  
 
44 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
SEC.  123.  SENSE  OF  CONGRESS  ON  ACCELERATED  PRODUCTION  OF 
AIRCRAFT CARRIERS. 
It is the sense of Congress that the United States should accelerate the production of aircraft 
carriers to rapidly achieve the Navy’s goal of having 12 operational aircraft carriers. 
Section 219 of H.R. 5515 states the following: 
SEC.  219.  MODIFICATION  OF  CVN–73  TO  SUPPORT  FIELDING  OF  MQ–25 
UNMANNED AERIAL VEHICLE. 
The Secretary of the Navy shall— 
(1) modify the compartments and infrastructure of the aircraft carrier designated CVN–73 
to support the fielding of the MQ–25 unmanned aerial vehicle before the date on which the 
refueling and complex overhaul of the aircraft carrier is completed; and 
(2) ensure such modification is sufficient to complete the full installation of MQ–25 in no 
more than a single maintenance period after such overhaul. 
Regarding Section 219, H.Rept. 115-874 states the following: 
Modification of CVN–73 to support fielding of MQ–25 unmanned aerial vehicle (sec. 219) 
The  House  bill  contained  a  provision  (sec.  220)  that  would  require  the  Navy  to  modify 
CVN–73 during its Refueling and Complex Overhaul (RCOH) to support the fielding of 
the MQ–25 unmanned aerial vehicle. 
The Senate amendment contained no similar provision. 
The  Senate  recedes  with  an  amendment  that  would  require  the  Navy  to  complete  the 
necessary  modifications  to  CVN–73’s  compartments  and  infrastructure  for  MQ–25 
alterations during the ship’s RCOH in order to allow completion of MQ–25 modifications 
and receipt of MQ–25 equipment in a single follow-on ship maintenance period. 
The conferees believe that once fielded, the Navy should prioritize deploying the MQ–25 
to the Pacific area of operations. In order to enable such deployments, the conferees believe 
that it is imperative that CVN–73, as the potential next forward deployed aircraft carrier, 
undergo the necessary  modifications and alterations during its RCOH to enable MQ–25 
operations as soon as practicable. However, the conferees are aware that completing all of 
the necessary modifications during the RCOH might put its timely completion at risk. 
Therefore, the conferees direct the Navy to complete the necessary MQ–25 modifications 
during CVN–73’s RCOH that would enable the completion of modifications and receipt of 
equipment  during  a  single  follow-on  maintenance  availability.  Nothing  in  this  language 
should  be  interpreted  as  prohibiting  the  full  installation  of  MQ–25  alterations  and 
equipment during RCOH should developments allow it. 
Additionally, the conferees expect future Navy budgets will support this plan. (Page 811) 
Section 338 of H.R. 5515 states the following: 
SEC. 338. REPORT ON RELOCATION OF STEAM TURBINE PRODUCTION FROM 
NIMITZ-CLASS  AND  FORD-CLASS  AIRCRAFT  CARRIERS  AND  VIRGINIA-
CLASS AND COLUMBIA-CLASS SUBMARINES. 
Not later than 180 days after the date of the enactment of this Act, the Secretary of Defense, 
in  consultation  with  the  Under  Secretary  of  Defense  for  Acquisition,  Technology,  and 
Logistics  and  the  Assistant  Secretary  of  the  Navy  for  Research,  Development,  and 
Acquisition, shall develop and submit to Congress a report describing the potential impacts 
on  national  defense  and  the  manufacturing  base  resulting  from  contractors  or 
subcontractors relocating steam turbine production for Nimitz-class and Ford-class aircraft 
Congressional Research Service  
 
45 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
carriers and Virginia-class and Columbia-class submarines. Such report shall address each 
of the following: 
(1) The overall risk of  moving production on the  national  security of the United  States, 
including the likelihood of production delay or reduction in quality of steam turbines. 
(2)  The  impact  on  national  security  from  a  delay  in  production  of  aircraft  carriers  and 
submarines. 
Section 1016 of H.R. 5515 states the following: 
SEC.  1016.  DISMANTLEMENT  AND  DISPOSAL  OF  NUCLEAR-POWERED 
AIRCRAFT CARRIERS. 
(a) IN GENERAL.—Chapter 633 of title 10, United States Code, as amended by section 
323, is further amended by adding after section 7320, as added by such section 323, the 
following new section:  
‘‘§ 7321. Nuclear-powered aircraft carriers: dismantlement and disposal 
‘‘(a)  IN  GENERAL.—Not  less  than  90  days  before  the  award  of  a  contract  for  the 
dismantlement and disposal of a nuclear-powered aircraft carrier, or the provision of funds 
to  a  naval  shipyard  for  the  dismantlement  and  disposal  of  a  nuclear-powered  aircraft 
carrier, the Secretary of the Navy shall submit to the congressional defense committees a 
report setting forth the following: 
‘‘(1) A cost and schedule  baseline  for the  dismantlement and disposal  approved by the 
service  acquisition  executive  of  the  Department  of  the  Navy  and  the  Chief  of  Naval 
Operations. 
‘‘(2)  A  description  of  the  regulatory  framework  applicable  to  the  management  of 
radioactive  materials  in  connection  with  the  dismantlement  and  disposal,  including,  in 
cases in which the Navy intends to have another government entity serve as the regulatory 
enforcement authority— 
‘‘(A) a certification from that entity of its agreement to serve as the regulatory enforcement 
authority; and 
‘‘(B) a description of the legal basis for the authority of that entity to serve as the regulatory 
enforcement authority. 
‘‘(b)  SUPPLEMENTAL  INFORMATION  WITH  BUDGETS.—In  the  materials 
submitted to Congress by the Secretary of Defense in support of the budget of the President 
for a fiscal year (as submitted to Congress under section 1105(a) of title 31), the Secretary 
of the Navy shall include information on each dismantlement and disposal of a nuclear-
powered aircraft carrier occurring or planned to occur during the period of the future-years 
defense program submitted to Congress with that budget. Such information shall include, 
by ship concerned, the following: 
‘‘(1)  A  summary  of  activities  and  significant  developments  in  connection  with  such 
dismantlement and disposal. 
‘‘(2)  If  applicable,  a  detailed  description  of  cost  and  schedule  performance  against  the 
baseline  for  such  dismantlement  and  disposal  established  pursuant  to  subsection  (a), 
including a description of and explanation for any variance from such baseline. 
‘‘(3) A description of the amounts requested, or intended or estimated to be requested, for 
such dismantlement and disposal for each of the following: 
‘‘(A) Each fiscal year covered by the future-years defense program. 
‘‘(B) Any fiscal years before the fiscal years covered by the future-years defense program. 
‘‘(C) Any fiscal years after the end of the period of the future-years defense program. 
Congressional Research Service  
 
46 
 link to page 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
‘‘(c)  FUTURE-YEARS  DEFENSE  PROGRAM  DEFINED.—In  this  section,  the  term 
‘future-years  defense  program’  means  the  future-years  defense  program  required  by 
section 221 of this title.’’. 
(b) CLERICAL AMENDMENT.—The table of sections at the beginning of chapter 633 
of  such  title,  as  amended  by  section  323,  is  further  amended  by  adding  at  the  end  the 
following new item: 
‘‘7321. Nuclear-powered aircraft carriers: dismantlement and disposal.’’. 
Section 1018 of H.R. 5515 states the following: 
SEC.  1018.  INCLUSION  OF  AIRCRAFT  CARRIER  REFUELING  OVERHAUL 
BUDGET REQUEST IN ANNUAL BUDGET JUSTIFICATION MATERIALS. 
The Secretary of Defense shall include in the budget justification materials submitted to 
Congress by the Secretary in support of the budget of the President for fiscal year 2020 and 
each subsequent fiscal year, as part of the budget request for Shipbuilding and Conversion, 
Navy,  a  detailed  aircraft  carrier  refueling  overhaul  budget  request,  by  hull  number, 
including all funding requested for reactor power units and reactor components. 
Regarding Section 1018, H.Rept. 115-874 states the following: 
Inclusion  of  aircraft  carrier  refueling  overhaul  budget  request  in  annual  budget 
justification materials (sec. 1018) 
The  Senate  amendment  contained  a  provision  (sec.  1014)  that  would  require  a  specific 
authorization by statute before funds may be obligated or expended for the procurement of 
a  naval  nuclear  reactor  power  unit  or  associated  reactor  components  for  the  nuclear 
refueling of an aircraft carrier. 
The House bill contained no similar provision. 
The  House  recedes  with  an  amendment  that  would  require  the  Secretary  of  Defense  to 
include, as part of the budget request for Shipbuilding and Conversion, Navy, a detailed 
aircraft carrier refueling overhaul request, by hull number, including all funding requested 
for reactor power units and reactor components. 
The  conferees  intent  is  the  procurement  of  nuclear  reactor  power  units  and  associated 
reactor components necessary for the nuclear refueling of each aircraft carrier be requested 
in the Shipbuilding and Conversion, Navy account, instead of the Other Procurement, Navy 
account. (Pages 940-941) 
FY2019 DOD Appropriations Act (H.R. 6157/S. 3159/Division A of 
H.R. 6157/P.L. 115-245) 
House Committee Report 
The House Appropriations Committee, in its report (H.Rept. 115-769 of June 20, 2018) on H.R. 
6157, recommended the funding level for the CVN-78 program shown in the HAC column of 
Table 4. 
H.Rept. 115-769 states the following: 
STEAM TURBINE PRODUCTION 
The Committee understands that the production of steam turbines is vital for the Navy’s 
30-year  shipbuilding  plan  and  has  concerns  that  any  disruption  to  this  production  could 
have major ramifications. The Committee directs the Secretary of the Navy to provide a 
report to the congressional defense committees not later than 180 days after the enactment 
Congressional Research Service  
 
47 
 link to page 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
of this Act that describes the current industrial base for steam turbines for Navy ships, how 
a temporary halt in production would impact shipbuilding, and any steps the Navy is taking 
to increase the domestic steam turbine industrial base. (Page 162) 
House Floor Action 
On June 27, 2018, as part of its consideration H.R. 6157, the House agreed to by voice vote 
H.Amdt. 839, which was amendment number 26 as printed in H.Rept. 115-785 of June 26, 2018, 
on H.Res. 964, providing for the further consideration of H.R. 6157. H.Amdt. 839 struck “(CVN 
80)” from the line in the bill as reported that provides procurement funding for the CVN-78 class 
program. The line read: “Carrier Replacement Program (CVN 80), $1,598,181,000,” meaning 
that the funding is made available specifically for CVN-80, and for no other carriers in the CVN-
78 program. Striking “(CVN 80)” from the line permits the funding to be used for the CVN-78 
class program in general, permitting the Navy, for example, to use the funding in part for CVN-
81, as part of a two-carrier block buy contract for CVN-80 and CVN-81. 
Senate 
The Senate Appropriations Committee, in its report (S.Rept. 115-290 of June 28, 2018) on S. 
3159, recommended the funding level for the CVN-78 program shown in the SAC column of 
Table 4. The recommended reduction of $25.0 million is for “Transfer funding to RDN, line 84: 
CVN 78 Full Ship Shock Trial.” (Page 105)62 In connection with this recommended transfer, 
S.Rept. 115-290 states the following: 
CVN 78 Full Ship Shock Trials.—The fiscal year 2019 President’s budget request includes 
no funds to conduct Full Ship Shock Trials [FSST] on CVN 78. The Committee notes that 
full-scale ship shock trials on CVN 78 were included in the original CVN 78 test plans and 
that the need for FSST was subsequently reaffirmed by the Director, Operational Test and 
Evaluation, the then-Under Secretary of Defense (Acquisition, Technology and Logistics) 
and Congress. The Committee notes that  subsequent to the fiscal year 2019 President’s 
budget submission, the Secretary of Defense denied a request by the Navy to waive CVN 
78  FSST  in  accordance  with  section  121(b)  of  the  Fiscal  Year  2018  National  Defense 
Authorization Act, and that the Navy now plans to conduct FSST on CVN 78, as directed. 
The  Committee  understands  that  this  requires  $25,000,000  in  fiscal  year  2019  and 
recommends transferring those funds from other CVN programs, as delineated in the tables 
for  Committee  Recommended  Adjustments  for  the  Research,  Development,  Test  and 
Evaluation,  Navy  and  Shipbuilding  and  Conversion,  Navy  accounts.  The  Committee 
further  understands  that  the  Navy  will  fully  budget  for  additional  CVN  78  FSST 
requirements in the fiscal year 2020 President’s budget request. (Page 174) 
S.Rept. 115-290 also states the following: 
CVN 80.—The fiscal year 2019 President’s budget request includes $1,598,181,000 for the 
Aircraft Carrier Replacement Program. The Committee supports the funding requested to 
maintain  the  aircraft  carrier  fleet  consistent  with  the  Navy’s  30  year  shipbuilding  plan. 
However, the Committee understands that the Navy may pursue block buy authority for a 
two-ship-buy, to include CVN 81, and notes that the construction award for CVN 80 has 
slipped from March 2018 to December 2018 while negotiations between the Navy and the 
shipbuilder  are  ongoing.  To  date,  the  Committee  has  not  received  any  documentation 
related to a block buy proposal. The Committee notes that an accurate independent cost 
                                                 
62 “RDN, line 84” is a reference to line 84 in the Navy’s research and development account, known more formally as 
the Research, Development, Test, and Evaluation, Navy (RDT&EN) account. Line 84 in this account funds RDT&E 
work for the CVN-78 program. The recommended transfer of the $25.0 million into line 84 is also noted on page 169 
of S.Rept. 115-290. 
Congressional Research Service  
 
48 
 link to page 39 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
estimate and Navy budget profile are required for the congressional defense committees to 
make  an  informed  decision  on  the  proposal.  Therefore,  the  Committee  designates  the 
funding appropriated for the Carrier Replacement Program funding line be applied only to 
CVN  80  and  directs  that  no  funds  provided  in  fiscal  year  2019  be  applied  to  the 
procurement of CVN 81 components. (Pages 105-106) 
S.Rept. 115-290 also states the following: 
CVN  78  Sortie  Generation  Rate.—The  Committee  notes  that  the  sortie  generation  rate 
[SGR] is a significant driver of the CVN 78 design. The Committee understands that the 
reliability of key systems may impact SGR and that the SGR demonstration schedule and 
execution  are  under  review.  The  Program  Executive  Officer,  Aircraft  Carriers,  in 
coordination with the Director, Operational Test and Evaluation is directed to provide, with 
the fiscal year 2020 President’s budget request, to the congressional defense committees 
an updated plan for the SGR demonstration schedule and test requirements. The Assistant 
Secretary of the Navy (Financial Management and Comptroller) is directed to certify SGR 
demonstration full  funding  with the  fiscal  year 2020 President’s budget  request.  (Pages 
174-175) 
Conference 
In final action, the FY2019 DOD Appropriations Act became Division A of the Department of 
Defense and Labor, Health and Human Services, and Education Appropriations Act, 2019, and 
Continuing Appropriations Act, 2019 (H.R. 6157/P.L. 115-245 of September 28, 2018). 
The joint explanatory statement for H.R. 6157/P.L. 115-245 specified the funding levels shown in 
the appropriations conference column of Table 4. The reduction of $25.0 million is for “CVN-78 
full ship shock trial – transfer to RDT&E,N [the research, development, test and evaluation, Navy 
appropriation account] line 84.” (PDF page 176 of 559) 
The paragraph in Division A of H.R. 6157/P.L. 115-245 that makes appropriations for the Navy’s 
shipbuilding account (the Shipbuilding and Conversion, Navy, or SCN, appropriation account) 
includes the following proviso: 
... Provided further, That the funds made available by this Act for the Carrier Replacement 
Program  (CVN–80)  may  be  available  to  modify  or  enter  into  a  new  contract  for  the 
procurement of a Ford-class aircraft carrier designated CVN–81 pursuant to section 121 of 
the John S. McCain National Defense Authorization Act for Fiscal Year 2019. 
The joint explanatory statement for H.R. 6157/P.L. 115-245 states the following: 
FORD CLASS AIRCRAFT CARRIER PROCUREMENT 
The conferees include a proviso consistent with section 121 of the John S. McCain National 
Defense Authorization Act for Fiscal Year 2019, which allows the Secretary of the Navy 
to  potentially  use  fiscal  year  2019  funds  to  enter  into  a  contract  for  an  aircraft  carrier 
designated CVN-81 if certain requirements are met by the Secretary of Defense. 
However, the conferees note that the congressional defense committees have not received 
information  justifying  the  validity  of  a  proposed  "two  carrier  block  buy,"  including  an 
Independent Cost Estimate, an analysis of the impact on other Navy shipbuilding programs, 
an updated future years defense program, or an extended planning range budget. 
This language replaces the language under the heading "CVN 80" in S.Rept. 115-290. (PDF 
page 178 of 559) 
Congressional Research Service  
 
49 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Appendix A. Background Information on Two-Ship 
and Three-Ship Block Buys 
This appendix presents background information on options for two-ship or three-ship carrier 
block buys that was presented in the main part of this CRS report prior to DOD’s December 31, 
2018, two-ship certification and the Navy’s January 31, 2019, two-ship contract award. 
Accelerated Procurement of CVN-81, Block Buy, or Combined 
Material Buy 
Overview 
One potential issue for Congress for FY2019 was whether to accelerate the procurement of CVN-
81 from FY2023 to an earlier year, or use a block buy contract to procure multiple aircraft 
carriers, or pursue a combined material buy for multiple aircraft carriers, or do some combination 
of these things. In general, supporters of these options could argue that they could help accelerate 
the attainment of a 12-carrier force and reduce aircraft carrier unit procurement costs, while 
opponents could argue that they would increase near-term aircraft carrier procurement funding 
requirements and reduce congressional flexibility for changing aircraft carrier procurement plans 
in coming years in response to changing strategic or budgetary circumstances. 
Accelerating Procurement of CVN-81 
Accelerating procurement of CVN-81 from FY2023 to an earlier year such as FY2021 or FY2022 
could make a start toward accelerating the attainment of a 12-carrier force. It could also reduce 
the procurement cost of CVN-81 in real (inflation-adjusted) terms by improving shipyard 
production learning curve benefits in shifting from production of CVN-80 to production of CVN-
81, and by improving spreading of shipyard and supplier-firm fixed overhead costs. Accelerating 
procurement of CVN-81, however, would also increase near-term aircraft carrier procurement 
funding requirements. Accelerating the procurement of CVN-81 could be done while maintaining 
the current plan to contract separately for the procurement of CVN-80 and CVN-81, or could be 
done as part of a new plan to procure CVN-80 with a block-buy contract covering one or two 
additional carriers (see next section). 
Delaying the procurement of CVN-80 one year, to FY2019, and accelerating the procurement of 
CVN-81 to FY2019 could permit both ships to be procured in the same year. This would permit 
the Navy to procure the two ships as a simple two-ship buy—an approach that would achieve 
savings similar to those achievable under a block buy contract without requiring the use of a 
block buy contract. (A block buy contract is necessary if the ships are procured in separate fiscal 
years.) The Navy made two-ship carrier buys in FY1983 (CVN-72 and CVN-73) and again in 
FY1988 (CVN-74 and CVN-75).63 
                                                 
63 When the FY1983 two-carrier buy was proposed, the Navy estimated that the block buy would reduce the combined 
cost of CVN-72 and CVN-73 by 5.6% in real terms. (See General Accounting Office, Request to Fully Fund Two 
Nuclear Aircraft Carriers in Fiscal Year 1983, MASAD-82-87 (B-206847), March 26, 1982, 10 pp. The figure of 5.6% 
was derived by dividing $450 million in non-inflation cost avoidance shown on page 5 of the Government 
Accountability Office (GAO) report by the combined estimated cost of the two ships (absent a block buy) of $8,024 
million shown on page 4.) 
Congressional Research Service  
 
50 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Block Buy Contract for Multiple Carriers 
Overview 
Using a single block buy contract64 to procure multiple carriers procured in separate fiscal years 
would do the following: 
  reduce the unit procurement costs of the carriers covered by the contract through 
the use of Economic Order Quantity (EOQ) purchases (i.e., up-front batch 
orders) of materials and components for the ships, and by giving the shipyard and 
supplier firms the confidence they need about future aircraft carrier construction 
to invest in optimizing their workforces and capital plants for a multiple-ship 
production run; and 
  increase near-term aircraft carrier procurement funding requirements and reduce 
congressional flexibility for changing aircraft carrier procurement plans in 
coming years in response to changing strategic or budgetary circumstances. 
Congress would need to approve the use of a block buy contract through a legislative provision, 
and making EOQ purchases under the contract could not occur unless the legislative provision 
granting authority for the block buy contract explicitly included authority for making EOQ 
purchases. A block buy contract could be done either without accelerating procurement of CVN-
81 from FY2023 to an earlier year, or in combination with accelerating CVN-81’s procurement to 
an earlier year. 
                                                 
The Navy proposed the procurement of CVN-74 and CVN-75 in the FY1988 budget submission as a block buy that 
would involve procuring CVN-74 in FY1990 and CVN-75 in FY1993. Congress, in acting on the FY1988 budget, 
decided to accelerate the procurement of both CVN-74 and CVN-75 to FY1988. (See CRS Issue Brief IB87043, 
Aircraft Carriers (Weapons Facts), 13 pp., updated February 10, 1988, and archived March 24, 1988, by Ronald 
O’Rourke. The report is out of print and available to congressional clients directly from the author.) 
When the FY1988 block buy was proposed, the Navy estimated that the block buy would reduce the combined cost of 
CVN-74 and CVN-75 by a considerably larger percentage than the 5.6% the Navy estimated for the FY1983 two-ship 
buy. GAO stated that the savings would be considerably less than the Navy estimated, but agreed that a two-ship 
acquisition strategy is less expensive than a single-ship acquisition strategy, and that some savings would occur in a 
two-ship strategy for CVN-74 and CVN-75. (See General Accounting Office, Procurement Strategy For Acquiring 
Two Nuclear Aircraft Carriers, Statement of Frank Conahan, Assistant Comptroller General, National Security and 
International Affairs Division, Before the Conventional Forces and Alliance Defense Subcommittee and Projection 
Forces and Regional Defense Subcommittee of the Senate Armed Services Committee, April 7, 1987, T-NSIAD-87-28, 
5 pp. The testimony states on page 2 that “A single ship acquisition strategy is more expensive because materials are 
bought separately for each ship rather than being combined into economic order quantity buys under a multi-ship 
procurement.” The report discounted the Navy’s estimated savings of $1,100 million based on this effect on the 
grounds that if CVN-74 and CVN-75 were not procured in the proposed two-ship block buy, with CVN-74 procured in 
FY1990 and CVN-75 procured FY1993, it was likely that CVN-74 and CVN-75 would subsequently be procured in a 
two-ship block buy, with CVN-74 procured in FY1994 and CVN-75 procured in FY1996. For the discussion here, 
however, the comparison is between the Navy’s current plan to procure CVN-80 and CVN-81 separately and the 
potential alternative of procuring them together in a block buy. The GAO report commented on an additional $700 
million in savings that the Navy estimated would be derived from improving production continuity between CVN-73, 
CVN-74, and CVN-75 by stating on page 3 that “It is logical to assume that savings are possible through production 
continuity but the precise magnitude of such savings is difficult to calculate because of the many variables that affect 
the outcome.”) 
64 For more on block buy contracts, which the Navy has used in other shipbuilding programs, see CRS Report R41909, 
Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for 
Congress, by Ronald O'Rourke and Moshe Schwartz. 
Congressional Research Service  
 
51 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Two-Ship Block Buy 
The option of using a block buy contract for procuring two carriers has been discussed over the 
years in this CRS report. In earlier years, the discussion focused on the option of using a block 
buy contract for procuring CVN-79 and CVN-80. In more recent years, interest among 
policymakers has focused on the option of using a block buy contract for procuring CVN-80 and 
CVN-81. 
Three-Ship Block Buy 
Discussions of the option of using a block buy contract have focused on using it to procure two 
carriers in part because carriers have been procured on 5-year centers, meaning that two carriers 
could be included in a block-buy contract spanning 6 years—the same number of years originally 
planned for the two block buy contracts that were used to procure most of the Navy’s Littoral 
Combat Ships.65 
It can be noted, however, that there is no statutory limit on the number of years that a block buy 
contract can cover, and that the LCS block buy contracts were subsequently amended to cover 
LCSs procured in a seventh year. This, and the possibility of procuring carriers on 3- or 3.5-year 
centers, raises the possibility of using a block buy contract to procure three aircraft carriers: For 
example, if procurement of aircraft carriers were shifted to 3- or 3.5-year centers, a block buy 
contract for procuring CVN-80, CVN-81, and CVN-82 could span seven years (with the three 
ships being procured in FY2018, FY2021, and FY2024) or eight years (with the three ships being 
procured in FY2018, FY2021 or FY2022, and FY2025, respectively). 
The percentage cost reduction possible under a three-ship block buy contract would likely be 
greater than that possible under a two-ship block buy contract, but the offsetting issue of reducing 
congressional flexibility for changing aircraft carrier procurement plans in coming years in 
response to changing strategic or budgetary circumstances would also be greater. 
Combined Materials Purchase 
Another option for Congress would be to approve a combined materials purchase for two or more 
carriers, so as to improve production economies of scale for those materials and thereby reduce 
their procurement cost. This option might be viewed as a mini or partial block buy—a block buy 
for the purchased materials, but not for the ships as a whole. The savings under this approach 
would be less than those under a block buy contract covering whole ships, particularly since 
much of the material for CVN-80 has already been purchased, but the offsetting issue of reducing 
congressional flexibility for changing aircraft carrier procurement plans in coming years in 
response to changing strategic or budgetary circumstances would also be reduced. 
Resulting Options for Congress 
Based on the above discussion, resulting options available to Congress include (but are not 
necessarily limited to) the following: 
  Accelerate CVN-81; no block buy. Accelerate procurement of CVN-81 from 
FY2023 to an earlier year, such as FY2021 or FY2022, but contract for it 
separately from CVN-80, as currently planned. 
                                                 
65 For more on the LCS block buy contracts, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: 
Background and Issues for Congress, by Ronald O'Rourke. 
Congressional Research Service  
 
52 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
  Two-ship block buy; no acceleration of CVN-81. Use a block buy contract for 
procuring CVN-80 and CVN-81, but maintain the current plan to procure CVN-
81 in FY2023. 
  Accelerate CVN-81 and two-ship block buy. Accelerate the procurement of 
CVN-81 from FY2023 to an earlier year, such as FY2021 or FY2022, and also 
use a block buy contract for procuring both CVN-80 and CVN-81. 
  Accelerate CVN-81 and CVN-82 and three-ship block buy. Accelerate the 
procurement of CVN-81 to FY2021 or FY2022, and the procurement of CVN-82 
(currently planned for FY2028) to FY2024 or FY2025, and use a three-ship 
block buy contract for procuring CVN-80, CVN-81, and CVN-82. 
  Two-ship buy for CVN-80 and CVN-81. Defer procurement of CVN-80 to 
FY2019, accelerate procurement of CVN-81 to FY2019, and procure both ships 
under a single FY2019 contract as a simple two-ship buy, without need for a 
block-buy contract. 
  Combined material purchase; no acceleration of CVN-81. Pursue a combined 
material purchase for CVN-80 and CVN-81, but maintain the current plan to 
procure CVN-81 in FY2023. 
  Combined material purchase; accelerate CVN-81. Pursue a combined material 
purchase for CVN-80 and CVN-81, and accelerate procurement of CVN-81 from 
FY2023 to an earlier year, such as FY2021 or FY2022. 
Potential Savings 
The potential savings from the above options would vary from option to option, and the savings 
for any given option could vary depending on the particulars of how it was implemented. In 
general, the potential savings of the above options might be said to range from a few percent to 
perhaps something in the range of 10%. A figure of about 10% has sometimes been mentioned in 
discussions of a two-ship buy, and might be viewed as a preliminary rough estimate of the 
combined savings from accelerating the procurement of CVN-81 and using a block buy contract 
to procure both CVN-80 and CVN-81 (i.e., of using the third option above). 
An April 16, 2018, press report stated the following: 
If  the  Navy  decides  to  buy  aircraft  carriers  CVN-80  and  81  together,  Newport  News 
Shipbuilding will be able to maintain a steady workload that supports between 23,000 and 
25,000 workers at the Virginia yard for the next decade or so, the shipyard president told 
reporters last week. 
Part of the appeal of buying the two carriers together is that the Navy would also buy them 
a bit closer together: the ships would be centered about three-and-a-half or four years apart, 
instead of the five-year centers for recent carrier acquisition, Newport News Shipbuilding 
President Jennifer Boykin told reporters. 
Boykin said the closer ship construction centers would allow her to avoid a “labor valley” 
where the workforce levels would dip down after one ship and then have to come back up, 
which is disruptive for employees and costly for the company. 
If this two-carrier buy goes through, the company would avoid the labor valley altogether 
and ensure stability in its workforce, Boykin said in a company media briefing at the Navy 
League’s  Sea  Air  Space  2018  symposium.  That  workforce  stability  contributes  to  an 
expected $1.6 billion in savings on the two-carrier buy from Newport News Shipbuilding’s 
portion of the work alone, not including government-furnished equipment.... 
Congressional Research Service  
 
53 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Boykin said four main things contribute to the expected $1.6 billion in savings from the 
two-carrier buy. First, “if you don’t have the workforce valley, there’s a labor efficiency 
that represents savings.” 
Second,  “if  you  buy  two  at  once,  my  engineering  team  doesn’t  have  to  produce  two 
technical baselines, two sets of technical products; they only have to produce one, and the 
applicability is to both, so there’s savings there. When we come through the planning, the 
build plan of how we plan to build the ship, the planning organization only has to put out 
one plan and the applicability is to both, so there’s savings there.” 
The third savings is a value of  money over time issue, she  said, and fourth is economic 
order quantity savings throughout the entire supply chain.66 
Navy Interest and RFP 
Navy officials in 2017 and 2018 have expressed interest in somehow combining the procurement 
of CVN-80 with that of CVN-81 so as to reduce carrier procurement costs, and have stated that 
they have been exploring options for doing this. On March 19, 2018, the Navy released a request 
for Proposal (RFP) to HII/NNS regarding a two-ship buy of some kind for CVN-80 and CVN-81. 
A March 20, 2018, Navy News Service report stated the following: 
The Navy released a CVN 80/81 two-ship buy Request for Proposal (RFP) to Huntington 
Ingalls Industries—Newport News Shipbuilding (HII-NNS) March 19 to further define the 
cost savings achievable with a two-ship buy. 
With lethality and affordability a top priority, the Navy has been working with HII-NNS 
over the last several months to estimate the total savings associated with procuring CVN 
80 and CVN 81 as a two-ship buy. 
"In keeping with the National Defense Strategy, the Navy developed an acquisition strategy 
to  combine  the  CVN  80  and  CVN  81  procurements  to  better  achieve  the  Department's 
objectives of building a more lethal force with greater performance and affordability," said 
James F. Geurts, Assistant Secretary of the Navy, Research Development and Acquisition. 
"This  opportunity  for  a  two-ship  contract  is  dependent  on  significant  savings  that  the 
shipbuilding  industry  and  government  must  demonstrate.  The  Navy  is  requesting  a 
proposal from HII-NNS in order to evaluate whether we can achieve significant savings." 
The two-ship buy is a contracting strategy the Navy has effectively used in the 1980s to 
procure  Nimitz-class  aircraft  carriers  and  achieved  significant  acquisition  cost  savings 
compared  to  contracting  for  the  ships  individually.  While  the  CVN  80/81  two-ship  buy 
negotiations transpire, the Navy is pursuing contracting actions necessary to continue CVN 
80 fabrication in fiscal year (FY) 2018 and preserve the current schedule. The Navy plans 
to award the CVN 80 construction contract in early FY 2019 as a two-ship buy pending 
Congressional approval and achieving significant savings.67 
October 2018 Press Report 
An October 19, 2018, press report states the following: 
                                                 
66 Megan Eckstein, “Newport News Would Save $1.6 Billion, Maintain Stable Workforce of 25,000 Under 2 Proposed 
Carrier Buy,” USNI News, April 16, 2018. See also Rich Abott, “HII Sees Two Carrier Buy Saving $1.6 Billion Before 
GFE,” Defense Daily, April 11, 2018: 10-11. 
67 Naval Sea Systems Command Public Affairs, “Navy Seeks Savings, Releases Two-Carrier RFP,” Navy News, March 
20, 2018. See also Megan Eckstein, “UPDATED: Navy, Newport News Taking Steps Towards Two-Carrier Buy,” 
USNI News, March 19, 2018. 
Congressional Research Service  
 
54 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The Pentagon’s No. 2 civilian is reviewing a Navy proposal to buy the third and fourth 
vessels in the Gerald R. Ford aircraft carrier program under one contract to assess whether 
the arrangement will save money as the service claims. 
“We  are  conducting  an  evaluation  to  ensure  we  have  the  warfighting  capabilities  to 
compete  and  win,”  Deputy  Defense  Secretary  Pat  Shanahan  said  in  a  statement  to 
Bloomberg  News.  “Any  decision  will  factor  in  strengthening  the  industrial  base  and 
delivering best value for taxpayers.” 
Navy  Secretary  Richard  Spencer  told  reporters  in  August  that  the  Navy’s  preliminary 
estimate is that a two-vessel contracting purchase could save the service $2.5 billion, and 
“we are trying to get it higher.” Captain Danny Hernandez, a Navy spokesman, said in an 
email that the proposal is still under review and “we expect to have a decision in mid-fall.” 
Beci Brenton, a spokeswoman for Newport News, Virginia-based Huntington Ingalls, said 
in an email that “we are still negotiating” with the Navy.68 
 
                                                 
68 Anthony Capaccio, “Navy Proposal to Buy Two Carriers Draws Scrutiny From Pentagon,” Bloomberg, October 19, 
2018. See also Justin Katz, “Spencer: Two-Ship Buy Analysis May Be Sent to Congress by ‘Mid-Fall,’” Inside the 
Navy, August 10, 2018. 
Congressional Research Service  
 
55 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Appendix B. Cost Growth and Managing Costs 
Within Program Cost Caps 
This appendix presents additional background information on cost growth in the CVN-78 
program, Navy efforts to stem that growth, and Navy efforts to manage costs so as to stay within 
the program’s cost caps. 
October 2018 CBO Report 
An October 2018 CBO report on the potential cost of the Navy’s 30-year shipbuilding plan states 
the following regarding the CVN-78 program: 
The Navy’s current estimate of the total cost of the Gerald R. Ford, the lead ship of the 
CVN-78 class, is $13.0 billion in nominal dollars appropriated over the period from 2001 
to 2018, an amount that is equal to the cost cap set in law. CBO used the Navy’s inflation 
index for naval shipbuilding to convert that figure to $15.5 billion in 2018 dollars, or 23 
percent more than the corresponding estimate when the ship was first authorized in 2008. 
Neither the Navy’s nor CBO’s estimate includes the $5 billion in research and development 
costs that apply to the entire class. 
Because construction of the lead ship is finished, CBO used the Navy’s estimate for that 
ship to estimate the cost of successive ships in the class. But not all of the cost risk has 
been eliminated; in particular, the ship’s power systems and advanced arresting gear (the 
system  used  to  recover  fixed-wing  aircraft  landing  on  the  ship)  are  not  yet  working 
properly.  It  is  not  clear  how  much  those  problems  will  cost  to  fix,  but  current  Navy 
estimates suggest that it will be several tens of millions of dollars or more. CBO does not 
have enough information to estimate those final repair costs. 
The next carrier after the CVN-78 will be the CVN-79, the John F. Kennedy. Funding for 
that ship began in 2007, the Congress officially authorized its construction in 2013, and the 
planned appropriations for it were completed in 2018. The shipbuilder expects to complete 
construction  of  the  CVN-79  in  2024  and  deploy  it  for  the  first  time  in  2026. The  Navy 
estimates that the ship will cost $11.3 billion in nominal dollars (or $11.6 billion in 2018 
dollars). The Navy’s selected acquisition report on the CVN-79 states that “the Navy and 
shipbuilder have made fundamental changes in the manner in which the CVN 79 will be 
built to incorporate lessons learned from CVN 78 and eliminate the key contributors to cost 
performance challenges realized in the construction of CVN 78.” Nevertheless, the Navy 
informed CBO that there is a greater than 60 percent chance that the ship’s final cost will 
be  more  than  the  current  estimate.  Although  CBO  expects  the  Navy  to  achieve  a 
considerable cost reduction in the CVN-79 compared with the CVN-78, as is typical with 
the second ship of a class, CBO’s estimate is higher than the Navy’s. Specifically, CBO 
estimates that the ship will cost $11.7 billion in nominal dollars (or $12.0 billion in 2018 
dollars), about 4 percent more than the Navy’s estimate. 
In 2018, the Congress authorized the third carrier of the class, the Enterprise (CVN-80). 
Appropriations for that ship began in 2016 and are expected to be complete by 2023. The 
Navy estimates that the ship will cost $12.6 billion in nominal dollars (or $11.5 billion in 
2018 dollars). However, as with CVN-79, the Navy told CBO that there is a greater than 
60 percent chance that the ship’s final cost will be more than the current estimate. CBO 
estimates that the ship will cost $13.0 billion in nominal dollars (or $11.8 billion in 2018 
dollars), about 3 percent more than the Navy’s estimate. 
The  Navy  estimates  an  average  cost  of  $12.4  billion  (in  2018 dollars)  for  the  7  carriers 
(CVN-81 through CVN-87) in the 2019 shipbuilding plan. CBO’s estimate is $12.8 billion 
per ship.... The gap between the estimates has narrowed since the 2017 plan: The Navy’s 
Congressional Research Service  
 
56 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
has increased by $500 million per ship, and CBO’s has dropped by $200 million per ship. 
It is not clear why the Navy’s estimates increased, but CBO’s estimates fell mainly because 
the  agency  projects  somewhat  less  growth  in  real  costs  of  the  shipbuilding  industry  in 
future years.69 
August 2018 Press Report 
An August 17, 2018, press report states the following: 
Huntington Ingalls Industries  Inc., the sole U.S. builder of aircraft carriers, continues to 
fall short of the Navy’s demand to cut labor expenses to stay within an $11.39 billion cost 
cap mandated by Congress on the second in a new class of warships. 
With about 47 percent of construction complete on the USS John F. Kennedy, Navy figures 
show the contractor isn’t yet meeting the goal it negotiated with the service: reducing labor 
hours by 18 percent from the first carrier, the USS Gerald Ford.... 
It took about 49 million hours of labor to build the Ford, according to the U.S. Government 
Accountability  Office.  The  Navy’s  goal  for  the  Kennedy  is  to  reduce  that  to  about  40 
million hours. 
Huntington  Ingalls’s  performance  “remains  stable  at  approximately  16  percent”  less, 
William Couch, spokesman for the Naval Sea Systems Command, said in an email. He said 
“key production milestones and the ship’s preliminary acceptance date remain on track” 
and there are “ample opportunities” for improvement “with nearly four years until contract 
delivery and over 70 percent of assembly work” remaining on the vessel’s superstructure. 
But  the  Pentagon’s  naval  warfare  division,  which  reports  to  Ellen  Lord,  the  Defense 
Department’s  chief  weapons  buyer,  is  less  sanguine.  It  said  in  a  July  assessment  that 
Huntington Ingalls “is unlikely to fully recover the needed 18 percent” reduction.... 
On  the  effort  to  meet  the  18  percent  labor-hour  reduction  for  the  Kennedy,  the  Navy’s 
program manager “assesses that although difficult, the shipbuilder can still attain” it, Couch 
said. 
Beci Brenton, a spokeswoman for Newport News, Virginia-based Huntington Ingalls, said 
“we  are  seeing  the  benefits  associated  with  significant  build  strategy  changes  and 
incorporation of lessons learned” from the first vessel. 
Brenton  said  “the  current  production  performance”  is  16  percent  less  than  the  Ford’s 
estimate at the time of contract award for the second vessel but the reduction is 17 percent 
when compared with the first vessel’s current cost.... 
But Shelby Oakley, a director with the GAO who monitors Navy shipbuilding, said “with 
so much of the program underway, it is unlikely that the Navy will regain efficiency.” In 
later  phases  of  a  shipbuilding  contract,  she  said,  “performance  typically  degrades,  not 
improves.” 
It’s also “unclear how the lessons learned” from the first ship “could help regain efficiency 
when they are already baked in to the Navy’s overly optimistic estimate for the program,” 
she said.70 
 
                                                 
69 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2019 Shipbuilding Plan, October 2018, pp. 17-
18. 
70 Anthony Capaccio, “Navy’s Troubled $11 Billion Carrier Falters on Another Milestone,” Bloomberg, August 17, 
2018. 
Congressional Research Service  
 
57 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
June 2018 Press Report 
A June 19, 2018, press report stated the following: 
Huntington  Ingalls  Industries  Inc.  is  asking  General  Electric  Co.  to  compensate  it  for 
damage  caused  by  flawed  workmanship  during  installation  of  propulsion  system 
components on the U.S. Navy’s $13 billion aircraft carrier Gerald R. Ford. 
The problem, which forced the most expensive U.S. warship back to port in January,  has 
yet to be fully resolved although the carrier is once again at sea.... 
Huntington  Ingalls,  a  shipbuilder  based  in  Newport  News,  Virginia,  “has  notified  the 
original manufacturer of the shipyard’s intent to seek compensation,” Naval Sea Systems 
Command spokesman William Couch said in an email. Beci Brenton, a spokeswoman for 
Huntington said, “We continue to work with appropriate stakeholders to support resolution 
of this situation.” 
Perry Bradley, a spokesman for Boston-based GE, said “we’re not going to comment on 
specifics other than to say” that “GE is working closely with” Huntington’s Newport News 
Shipyard unit and “the U.S. Navy to resolve the issue.”... 
The  episode  in  January  was  the  second  failure  in  less  than  a  year  with  a  “main  thrust 
bearing” that’s part of the carrier’s propulsion system. The first occurred in April 2017, 
during  sea  trials  a  month  before  the  vessel’s  delivery.  The  ship  has  been  sailing  in  a 
shakedown period to test systems and work out bugs. It’s now scheduled to be ready for 
initial combat duty in 2022. 
The Navy’s carrier program office said in an assessment that an inspection of the carrier’s 
four  main  thrust  bearings  after  the  January  failure  revealed  “machining  errors”  by  GE 
workers at a Lynn, Massachusetts, facility during the original manufacturing as “the actual 
root cause.” 
The bearing overheated, the Navy said in a March 8 memo to Congress, and “after securing 
the equipment to prevent damage, the ship safely returned to port." A failure review board 
is identifying “modifications required to preclude recurrence,” it said. The bearing is one 
of four that transfers thrust from the ship’s four propeller shafts. 
“The costs associated with repairing” the thrust bearings “are currently being assessed” and 
“this will include recovery of costs from the manufacturer of the Main Reduction Gear, 
General Electric (Lynn), as appropriate,” the Navy said in the memo. 
Couch said the Navy doesn’t expect similar propulsion problems with the next vessel in 
the  class,  the  John  F.  Kennedy,  because  a  different  manufacturer  made  that  carrier’s 
propulsion train components. 
“Any  propulsion  train  deficiencies  identified”  with  the  Ford  “will  be  corrected  and 
implemented” in “future ships of the class as necessary,” he said.71 
May 2018 Press Report 
A May 11, 2018, press report stated the following: 
The  Navy’s  costliest  vessel  ever  just  got  pricer,  breaching  a  $12.9  billion  cap  set  by 
Congress by $120 million, the service told lawmakers this week. 
The extra money for the U.S.S. Gerald R. Ford built by Huntington Ingalls Industries Inc. 
is needed to replace faulty propulsion components damaged in a January failure, extend 
the vessel’s post-delivery repair phase to 12 months from the original eight months and 
                                                 
71 Anthony Capaccio, “Huntington Ingalls Asks General Electric to Pay for Carrie Flaw,” Bloomberg, June 19, 2018. 
Congressional Research Service  
 
58 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
correct deficiencies with the “Advanced Weapons Elevators” used to move munitions from 
deep in the ship to the deck. 
The elevators on the ship, designated CVN 78, need to be fixed “to preclude any effect on 
the safety of the ship and personnel,” the Naval Sea Systems Command said in a statement 
to Bloomberg News on Friday. “Once the adjustment is executed, the cost for CVN 78 will 
stand at $13.027” billion, the Navy said. 
In addition to informing Congress that the spending lid has been breached, the Navy will 
have to let lawmakers know how it will shift funds to make up the difference. 
Navy officials didn’t disclose the propulsion failure or elevator problems during budget 
hearings before Congress in recent weeks, and House and Senate  lawmakers didn’t ask 
about it.... 
The Ford’s propulsion system and elevator flaws are separate from reliability issues on its 
troubled aircraft launch and recovery systems. 
After  its  delivery  last  May,  the  ship  operated  for  70  days  and  completed  747  shipboard 
aircraft launches and recoveries, exceeding the goal of about 400, the Navy said. 
None of the 11 weapons elevators are operational but at least two are being used for testing 
“to identify many of the remaining developmental issues for this first-of-class system,” the 
Navy  has  said.  The  command  said  all  11  elevators  “should  have  been  complete  and 
delivered with the ship delivery” in May 2017.72 
April 2018 Press Report 
An April 16, 2018, press report stated the following: 
Huntington  Ingalls  Industries’  Newport  News  Shipbuilding  President  Jennifer  Boykin 
provided  an  update  on  the  various  stages  of  construction  on  several  major  Navy 
shipbuilding programs during the Navy League’s Sea Air Space Expo last week. 
The  future  USS  John  F.  Kennedy  (CVN-79)  is  about  43  percent  complete,  with  launch 
planned for the fourth quarter of 2019 and delivery set for 2022. Boykin said the company 
has achieved about 75 percent of the ship erected and they are on track for an 18 percent 
man-hour budget reduction. 
Boykin provided these updates during a press briefing at the conference. 
Boykin revealed that undocking of CVN-79 in the fourth quarter of 2019 will occur three 
months earlier than originally planned.73 
April 2018 GAO Report 
An April 2018 Government Accountability Office (GAO) report assessing major DOD weapon 
acquisition programs stated the following regarding the status of the CVN-78 program: 
Technology, Design, and Production Maturity 
                                                 
72 Anthony Capaccio, “U.S. Navy’s Costliest Vessel Just Got Even Pricier,” Bloomberg, May 11, 2018. See also Mark 
D. Faram, “Why the Navy’s Newest Aircraft Carrier Was Forced Back into Port,” Navy Times, May 23, 2018; 
Anthony Capaccio, “U.S. Navy’s Costliest Warship Suffers New Failure at Sea,” Bloomberg, May 8, 2018. The May 
23, 2018, article includes quotes from Colleen O’Rourke, a spokeswoman for the Navy Sea Systems Command. 
Colleen O’Rourke is no relation to Ronald O’Rourke. 
73 Rich Abott, “Huntington Ingalls Updates Ships Statuses, Reactivates Ingalls East Bank,” Defense Daily, April 16, 
2018: 16-17. 
Congressional Research Service  
 
59 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
In  May  2017,  the  Navy  accepted  delivery  of  the  lead  ship  in  the  Ford  class  (CVN  78), 
despite  the  carrier’s  reliance  on  immature  technologies  and  struggle  to  demonstrate  the 
reliability of mature systems. CVN 78 began construction with immature technologies and 
an incomplete design, leading to cost and schedule growth. The ship delivered 20 months 
later  than  the  Navy  planned,  with  construction-related  work  still  remaining  and  over  40 
serious  deficiencies  that  could  impact  ship  operation  or  safety.  As  of  January  2018,  the 
Navy reported 11 of the program’s 13 critical technologies are mature. Shipboard testing 
continues  for  several  critical  systems,  including  the  advanced  weapons  elevators, 
electromagnetic  aircraft  launch  system  (EMALS),  advanced  arresting  gear  (AAG),  and 
dual band radar (DBR). The elevators, AAG, and DBR are struggling to meet reliability 
targets  the  Navy  uses  in  assessing  ship  performance.  If  these  systems  cannot  show 
reliability, CVN 78 may not demonstrate it can rapidly launch and recover aircraft—a key 
requirement  for  the  new  class  of  carriers.  The  Navy  reported  EMALS  is  now  meeting 
reliability targets; however, the Director, Operational Test and Evaluation, raised concerns 
because the Navy lowered the EMALS reliability target. This lower target will also prevent 
the ship from meeting the program’s aircraft launch and recovery requirement. 
Until  the  Navy  fully  matures  the  CVN  78  class  critical  technologies,  the  form  of  these 
technologies and how they fit on the ship could evolve. Such changes, which are typical 
outcomes  of  technology  development,  could  introduce  the  need  for  additional  design 
changes to CVN 78 class ships. Despite this, construction continues on the second ship, 
CVN 79, which is 34 percent complete and the Navy will soon review proposals for the 
third ship, CVN 80. CVN 79 uses the CVN 78 design with some modifications—that the 
Navy  considers  complete—most  notably,  replacement  of  DBR  with  the  Enterprise  Air 
Surveillance Radar (EASR), which is still in development and completed its critical design 
review in August 2017. The Navy does not identify this new system as a critical technology 
in the Ford Class because it derives from the pre-existing Air and Missile Defense Radar. 
The Navy plans to procure two EASR units for CVNs 79 and 80 and install the CVN 79 
unit during that ship’s second phase of delivery. The Navy expects to receive and review 
shipbuilder  proposals  for  CVN  80  in  early  2018.  The  shipbuilder  is  already  procuring 
materials for the third ship under the advance procurement contract the Navy reported it 
awarded in May 2016. 
Other Program Issues 
In 2007, Congress established a procurement cost cap of $10.5 billion for CVN 78, but lead 
ship procurement costs have since increased by 23 percent to the current cost cap of $12.9 
billion. The National Defense Authorization Act (NDAA)  for Fiscal Year 2016 reduced 
the cap for follow-on ships, including CVN 79 to $11.4 billion, although costs for this ship 
may also increase. In a prior report, we found that the funds the Navy budgeted for CVN 
79  are  likely  to  be  insufficient  to  complete  ship  construction.  Previously,  the  Navy 
expressed  confidence  that  CVN  79  would  deliver  within  its  cost  cap,  which  assumes 
unprecedented  construction  efficiency—namely  that  CVN  79  production  hours  will  be 
over 18 percent lower than CVN 78. However, recent construction performance reporting 
shows  the  shipbuilder  is  not  meeting  this  goal.  If  the  shipbuilder  cannot  achieve  its 
predicted efficiency gain, CVN 79 is at risk of exceeding its current $11.4 billion cost cap. 
The NDAA for Fiscal Year 2018 raises the cost cap for ships that follow CVN 79 to $12.6 
billion. 
The NDAA for Fiscal Year 2018 also provides the Secretary of Defense with another way 
to waive a fiscal year 2016 NDAA limitation on funding for CVN 79 that would not require 
a certification that the full ship shock trial be completed on CVN 78. The Navy originally 
planned  to  defer  this  test  until  after  CVN  78’s  initial  deployment.  In  a  prior  report,  we 
raised concerns about the Navy’s plan to delay this trial because such tests can identify 
potential  mission-critical failures before the ship is in an active combat environment. In 
2015, the Deputy Secretary of Defense for Acquisition ordered the Navy to conduct the 
trial before the first deployment. 
Congressional Research Service  
 
60 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Program Office Comments 
We provided a draft of this assessment to the program office for review and comment. The 
program office provided technical comments, which we incorporated where appropriate. 
In addition, the program office stated that CVN 78 delivered in late May 2017, though with 
deficiencies, after completing trials. According to the program office, correction of these 
deficiencies is ahead of schedule. The ship has performed well at sea through January 2018, 
according the the program, completing hundreds of aircraft launches and recoveries using 
EMALS  and  AAG,  supported  by  DBR.  This  activity  contributes  to  required  reliability 
metrics for these systems. 
The program office also stated that CVN 79 construction cost performance remains below 
the level needed to achieve the planned reduction in production hours from CVN 78, but 
is improving. The program expects shipbuilder performance to remain stable as it continues 
to  work  through  the  residual  effects  of  shortages  in  some  construction  materials,  which 
contributed  to  its  earlier  cost  performance  issues.  According  to  the  program  office,  the 
Navy  plans  to  deliver  a  complete  and  deployable  ship  on  schedule  in  September  2024, 
within its cost cap and on a timeline that maintains an 11-carrier force structure.74 
September 2017 Press Report 
A September 26, 2017, press report states the following: 
Huntington Ingalls Industries Inc. is falling short of a U.S. Navy goal to reduce hours of 
labor on the second ship in the new Ford class of aircraft carriers in a drive to reduce costs, 
according to service documents. 
With 34 percent of construction complete on the USS John F. Kennedy, Huntington Ingalls 
estimates  it  will  be  able  to  reduce  labor  hours  by  16  percent  from  the  hours  needed  to 
construct the  first  vessel, the  Gerald R. Ford. That’s less than the 17 percent reduction 
reported at the end of last year and the 18 percent goal the Navy negotiated in the primary 
construction contract for the carrier. 
The “recent degradation in cost performance stems largely from the delayed availability of 
certain  categories  of  material,”  such  as  pipe  fittings,  controllers,  actuators  and  valves, 
according to the  Navy’s annual  report on the  program and updated figures obtained by 
Bloomberg News.... 
“We acknowledge that the cost reduction target for CVN-79,” relative to the first carrier, 
“is challenging,” Huntington Ingalls spokeswoman Beci Brenton said in an email, referring 
to the Kennedy by its Navy designation. “While it is still early in the ship’s schedule, we 
are seeing positive results from” new initiatives to keep costs in check, she said.... 
Navy  Secretary  Richard  Spencer  told  reporters  last  week  that  he  will  stay  involved  in 
monitoring the CVN-79’s construction trends. “This is my personal approach—the CEO 
has to be involved.” 
A  close  watch  is  required  “because  there  are  so  many  moving  parts  and  so  many 
opportunities to do things in a more efficient manner,” Spencer said. 
The Navy has been working with the contractors “to mitigate technical risks and impacts 
of late material,” Navy spokesman Victor Chen in an email. “The overall volume of late 
material items and associated impact to construction performance is declining. The Navy 
has  hired  third-party  experts  who  are  working  collaboratively  with  the  shipbuilder  to 
                                                 
74 Government Accountability Office, Weapon Systems Annual Assessment[:] Knowledge Gaps Pose Risks to 
Sustaining Recent Positive Trends, GAO-17-360SP, April 2018, p. 85. 
Congressional Research Service  
 
61 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
identify manufacturing opportunities for efficiency gains” and to assist in implementing 
improvements.... 
The  18 percent  reduction  in  labor  hours  was  “quite  optimistic”  from  the  start,  Michele 
Mackin,  a  Government  Accountability  Office  director  who  oversees  its  shipbuilding 
assessments, said in an email. “Even based on that assumption, the $11.4 billion cost cap 
was  unlikely  to  be  met,”  she  said.  “If  those  labor-hour  efficiencies  are  in  fact  not 
materializing, costs will go higher. 
Also, “with the ship being over 30 percent complete, it’s unlikely the shipbuilder can get 
back enough efficiencies to further reduce labor hours—the more complicated work is yet 
to come,” she said.75 
June 2017 Navy Testimony 
At a June 15, 2017, hearing before the Senate Armed Services Committee on the Department of 
the Navy’s proposed FY2018 budget, the following exchange occurred: 
SENATOR JOHN MCCAIN (CHAIRMAN) (continuing):  
Secretary Stackley, the Navy broached a cost cap for CVN-78. Do you believe that it has? 
SEAN STACKLEY, ACTING SECRETARY OF THE NAVY:  
Sir, right now our estimate for CVN-78, we're trying to hold it within the $12.887 billion 
number  that  was  established  several  years  ago.  We  have  included  a  $20  million 
[procurement funding] request in this budget pending our determination regarding repairs 
that required for the... 
MCCAIN:  
Is that a breach of Nunn-McCurdy?76 
STACKLEY:  
Not at this point in time, sir, we're continuing to evaluate whether that additional funding 
will be required. We're doing everything we can to stay within the existing cap and we'll 
keep Congress informed as we complete our post-delivery assessment. 
MCCAIN:  
Problem  is  we  haven't  been  informed.  So  either  you  bust  the  cap  and  breach  Nunn-
McCurdy—Nunn-McCurdy or you notify us. You haven't done either one. 
STACKLEY:  
Sir, we've been submitting monthly reports regarding the carrier, we've alerted the concern 
regarding the repairs that are being required for the motor turbine generator set and we've 
acknowledged the risk associated with those repairs. However, what we’re trying to do is 
not incur those costs, avoid cost by other means, and as of right now we're not ready to trip 
that cost cap. 
MCCAIN:  
                                                 
75 Anthony Capaccio, “U.S. Aircraft Carrier’s Labor Costs Missing Navy’s Savings Goal,” Bloomberg, September 26, 
2017. See also Lee Hudson, “NNS Slightly Lagging Expected Efficiencies with CVN-79 30 Percent Constructed,” 
Inside the Navy, July 24, 2017. 
76 This is a reference to the Nunn-McCurdy provision, a statute relating to cost growth in DOD acquisition programs. 
For more on the Nunn-McCurdy provision, see CRS Report R41293, The Nunn-McCurdy Act: Background, Analysis, 
and Issues for Congress, by Moshe Schwartz and Charles V. O'Connor. 
Congressional Research Service  
 
62 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Well, it's either not allowable or it's allowable. It's not allowable, then you take a certain 
course of action. If it's allowable then you're required to notify Congress. You have done 
neither. 
STACKLEY:  
If we need to incur those costs, they will be allowable costs. We're trying to avoid that at 
this stage of time, sir. 
MCCAIN:  
I  agree,  but  we  were  supposed  to be  notified—OK.  I  can  tell  you  that  you  are  either  in 
violation of Nunn-McCurdy or you are in violation of the requirement that we be notified. 
You have done neither. There's two scenarios. 
STACKLEY:  
Sir, we have not broached the cost cap. If it becomes apparent that we'll need to go above 
the  cost  cap,  we  will  notify  Congress  within—within  the  terms  that  you  all  have 
established. 
MCCAIN:  
OK. Well, I'll get it to you in writing but you still haven't answered the question because 
when there's a $20 million cost overrun, it's either allowable and then we have to be notified 
in one way. If it's not allowable, Nunn-McCurdy is—is reached. But anyway, maybe you 
can give us a more satisfactory explanation in writing, Mr. Secretary.77 
June 2017 GAO Report 
A June 2017 GAO report states the following: 
The cost estimate for the second Ford-Class aircraft carrier, CVN 79, is not reliable and 
does  not  address  lessons  learned  from  the  performance  of  the  lead  ship,  CVN  78.  As  a 
result, the estimate does not demonstrate that the program can meet its $11.4 billion cost 
cap. Cost growth for the lead ship was driven by challenges with technology development, 
design, and construction, compounded by an optimistic budget estimate. Instead of learning 
from the mistakes of CVN 78, the Navy developed an estimate for CVN 79 that assumes a 
reduction in labor hours needed to construct the ship that is unprecedented in the past 50 
years of aircraft carrier construction.... 
After developing the program estimate, the Navy negotiated 18 percent fewer labor hours 
for CVN 79 than were required for CVN 78. CVN 79’s estimate is optimistic compared to 
the labor hour reductions calculated in independent cost reviews conducted in 2015 by the 
Naval  Center  for  Cost  Analysis  and  the  Office  of  Cost  Assessment  and  Program 
Evaluation.  Navy  analysis  shows  that  the  CVN  79  cost  estimate  may  not  sufficiently 
account  for  program  risks,  with  the  current  budget  likely  insufficient  to  complete  ship 
construction. 
The Navy’s current reporting mechanisms, such as budget requests and annual acquisition 
reports  to  Congress,  provide  limited  insight  into  the  overall  Ford  Class  program  and 
individual ship costs. For example, the program requests funding for each ship before that 
ship  obtains  an  independent  cost  estimate.  During  an  11-year  period  prior  to  2015,  no 
independent  cost  estimate  was  conducted  for  any  of  the  Ford  class  ships;  however,  the 
program  received  over  $15  billion  in  funding.  In  addition,  the  program’s  Selected 
Acquisition Reports (SAR)—annual cost, status, and performance reports to Congress—
                                                 
77 Transcript of hearing as posted at CQ.com. 
Congressional Research Service  
 
63 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
provide only aggregate program cost for all three ships currently in the class, a practice that 
limits transparency into individual ship costs. As a result, Congress has diminished ability 
to oversee one of the most expensive programs in the defense portfolio.78 
February 2016 Navy Testimony 
The Navy testified in 2016 that 
The Navy is committed to delivering the lead ship of the class, Gerald R Ford (CVN 78) 
within  the  $12.887  billion  congressional  cost  cap.  Sustained  efforts  to  identify  cost 
reductions and drive improved cost and schedule performance on this first-of-class aircraft 
carrier  have  resulted  in  highly  stable  cost  performance  since  2011.  Based  on  lessons 
learned  on  CVN  78,  the  approach  to  carrier  construction  has  undergone  an  extensive 
affordability review and the Navy and the shipbuilder have made significant changes on 
CVN 79 to reduce the cost to build the ship. The benefits of these changes in build strategy 
and  resolution  of  first-of-class  impacts  experienced  on  CVN  78  are  evident  in  early 
production  labor  metrics  on  CVN  79.  These  efforts  are  ongoing  and  additional  process 
improvements continue to be identified. 
Alongside the Navy’s efforts to reduce the cost to build CVN 79, the FY 2016 National 
Defense Authorization Act reduced the cost cap for follow ships in the CVN 78 class from 
$11,498 million to $11,398 million. To this end, the Navy has further emphasized stability 
in  requirements,  design,  schedule,  and  budget,  in  order  to  drive  further  improvement  to 
CVN 79 cost. The FY 2017 President’s Budget requests funding for the most efficient build 
strategy for this ship and we look for Congress’ full support of this request to enable CVN 
79 procurement at the lowest possible cost.... 
...  The  Navy  will  deliver  the  CVN  79  within  the  cost  cap  using  a  two-phased  strategy 
wherein select ship systems and compartments that are more efficiently completed at a later 
stage  of  construction  -  to  avoid  obsolescence  or  to  leverage  competition  or  the  use  of 
experienced installation teams - will be scheduled for completion in the ship’s second phase 
of  production  and  test.  Enterprise  (CVN  80)  began  construction  planning  and  long  lead 
time material procurement in January 2016 and construction is scheduled to begin in 2018. 
The  FY 2017 President’s Budget  request re-phases CVN  80 funding to support a  more 
efficient production profile, critical to performance, below the cost cap. CVN 80 planning 
and construction  will continue to leverage class lessons learned to achieve cost and risk 
reduction, including efforts to accelerate production work to earlier phases of construction, 
where work is more cost efficient.79 
October 2015 Senate Armed Services Committee Hearing 
Cost growth and other issues in the CVN-78 program were reviewed at an October 1, 2015, 
hearing before the Senate Armed Services Committee. Below are excerpts from the prepared 
statements of the witnesses at the hearing. 
                                                 
78 Government Accountability Office, Ford-Class Aircraft Carrier[:] Follow-On Ships Need More Frequent and 
Accurate Cost Estimates to Avoid Pitfalls of Lead Ship, GAO-17-575, June 2017, summary page. See also Jason 
Sherman, “DOD Plans Independent Cost Estimates for All Follow-On Ford Class Ships,” Inside the Navy, June 19, 
2017. 
79 Statement of the Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and 
Acquisition), and Vice Admiral Joseph P. Mulloy, Deputy Chief of Naval Operations for Integration of Capabilities 
and Resources, and Lieutenant General Robert S. Walsh, Deputy Commandant, Combat Development and Integration 
& Commanding General, Marine Corps Combat Development Command, before the Subcommittee on Seapower and 
Projection Forces of the House Armed Services Committee on Department of the Navy Seapower and Projection 
Forces Capabilities, February 25, 2016, pp. 8-9. 
Congressional Research Service  
 
64 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
OSD ASD Testimony 
The prepared statement of the Assistant Secretary of Defense (Acquisition) within the Office of 
the Secretary of Defense (OSD) states the following in part: 
By 2000, the CVN(X) Acquisition Strategy that had been proposed by the Navy was an 
evolutionary,  three-step  development  of  the  capabilities  planned  for  the  CVN.  This 
evolutionary  strategy  intending  to  mature  technology  and  align  risk  with  affordability 
originally involved using the last ship of the CVN 68 NIMITZ Class, USS GEORGE H. 
W.  BUSH  (CVN  77),  as  the  starting  point  for  insertion  of  some  near  term  technology 
improvements including information  network technology and the new Dual Band Radar 
(DBR) system from the DD(X) (now DDG 1000) program, to create an integrated warfare 
system that combined the ship’s combat system and air wing mission planning functions. 
However, the then incoming Secretary of Defense Donald Rumsfeld in 2002 directed re-
examination  of  the  CVN  program,  among  others,  to  reduce  the  overall  spend  of  the 
department  and  increase  the  speed  of  delivery  to  the  warfighters.  As  a  result  of  the 
SECDEF’s direction, the Navy proposed to remove the evolutionary approach and included 
a new and enlarged flight deck, an increased allowance for future technologies (including 
electric  weapons), and an additional  manpower reduction of 500 to 800 fewer sailors to 
operate.  On  December  12,  2002,  a  Program  Decision  Memorandum  approved  by  then 
Deputy  Secretary of Defense  Paul Wolfowitz codified this Navy proposal and gave this 
direction back to the DOD enterprise. The ship was renamed the CVN-21 to highlight these 
changes. By Milestone B in April 2004, the Navy had evaluated the technologies intended 
for three ships, removed some of them, and consolidated the remaining ones into a single 
step  of  capability  improvement  on  the  lead  ship.  The  new  plan  acknowledged 
technological, cost, and schedule challenges were being put on a single ship, but assessed 
this  was  achievable.  The  Acting  USD  AT&L  (Michael  Wynne)  at  that  milestone  also 
directed  the  Navy  to  use  a  hybrid  of  the  Service  Cost  Position  and  Independent  Cost 
Estimate (ICE) to baseline the program funding in lieu of the ICE, (although one can easily 
argue even the ICE was optimistic given these imposed circumstances). 
By 2004, DOD and Congressional leadership had lost confidence in the acquisition system, 
and  Deputy  Secretary  of  Defense  Gordon  England  established  the  Defense  Acquisition 
Performance Assessment (DAPA) panel to conduct a sweeping and integrated assessment 
of “every aspect” of acquisition. The result was the discovery that the Industrial Base had 
consolidated,  that  excessive  oversight  and  complex  acquisition  processes  were  cost  and 
schedule drivers, and a focus on requirements stability was key to containing costs. From 
this, a review of the requirements of the CVN resulted in a revised and solidified “single 
ship” Operational Requirements Document (ORD) for the FORD Class as defined today, 
with the CVN 78 as lead ship. 
On  the  heels  of  a  delay  because  of  the  budgetary  constraints  in  2006,  the  start  of  the 
construction of CVN 78  was  delayed until 2008, but the schedule  for delivery  was held 
constant,  further  compounding  risks  and  costs.  The  Navy’s  testimony  covers  these 
technical and schedule risks and concurrency challenges well. 
By 2009, this Committee had issued a floor statement in support of the Weapon Systems 
Acquisition Reform Act (WSARA). Congress was now united in its pursuit of acquisition 
reform and, in concert, USD AT&L re-issued and updated the Department of Defense’s 
acquisition  instruction  (DoDI  5000.2)  in  2008.  WSARA  included  strengthening  of  the 
‘Nunn-McCurdy” process with requires DOD to report to Congress when cost growth on 
a major program breaches a critical cost growth threshold. This legislation required a root-
cause  assessment  of  the  program  and  assumed  program  termination  within  60  days  of 
notification unless DOD certified in writing that the program remained essential to national 
security. 
Congressional Research Service  
 
65 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
WSARA had real impact on the CVN 78, as by 2008 and 2009 the results of all the previous 
decisions were instantiated in growth of cost and schedule. Then USD AT&L John Young 
required the Navy to provide a list of descoping efforts and directed the Navy to have an 
off-ramp  back  to  steam  catapults  if  the  Electromagnetic  Aircraft  Launching  System 
(EMALS) remained a problem for the program. He also directed an independent review of 
all of the CVN 78 technologies by a Defense Support Team (DST). Prior to the DST, the 
Navy had chartered a Program Assessment Review (PAR) with USD (AT&L) participation 
of EMALS/Advanced Arresting Gear (AAG) versus steam. One of the key PAR findings 
was converting the EMALS and AAG production contracts to firm, fixed price contracts 
to cap cost growth and imposed negative incentives for late delivery. 
The Dual Band Radar (DBR) cost and risk growth was a decision by-product of the DDG 
1000 program Nunn-McCurdy critical unit cost breach in 2010. Faced with a need to reduce 
cost  on  the  DDG  1000  program  and  the  resultant  curtailment  of  the  program,  the 
expectation of development costs being borne by the DDG 1000 program was no longer 
the case and all of the costs associated with the S-band element development and a higher 
share of the X-band element then had to be supported by the CVN 78 program. 
The design problems encountered with AAG development have had the most deleterious 
effects on CVN 78 construction of any of the three major advanced technologies including 
EMALS and DBR. Our view of AAG is that these engineering design problems are now 
in  the  past  and  although  delivery  of  several  critical  components  have  been  delayed,  the 
system will achieve its needed capabilities before undergoing final operational testing prior 
to  deployment  of  the  ship.  Again,  reliability  growth  is  a  concern,  but  this  cannot  be 
improved until a fully functional system is installed and operating at the Lakehurst, New 
Jersey land based test site, and on board CVN 78. 
With the 2010 introduction by then USD AT&L Ashton Carter (now in its third iteration 
by  under  USD  AT&L  Frank  Kendall)  of  the  continuous  process  improvement  initiative 
that was founded in best business practices and WSARA called “Better Buying Power,” 
the  CVN  underwent affordability, “Should Cost,” and requirements assessment.  Navy’s 
use of the “Gate” process has stabilized the cost growth and reset good business practices. 
However, there is still much to do. We are in the testing phase of program execution prior 
to deployment and we had been concerned about the timing of the Full Ship Shock Trial 
(FSST).  After  balancing  the  operational  and  technical  risks,  the  Department  decided  to 
execute FSST on CVN 78 prior to deployment. 
EMALS  and  AAG  are  also  a  concern  with  regard  to  final  operational  testing  stemming 
from the development difficulties that each experienced. The Navy still needs to complete 
a significant amount of land-based testing to enable certification of the systems to launch 
and recover the full range of aircraft that it is required to operate under both normal and 
emergency conditions. This land-based testing is planned to complete before the final at-
sea operational testing for these systems begins.... 
USD  AT&L  continues  to  work  with  Navy  to  tailor  the  program  and  ensure  appropriate 
oversight at both the Navy Staff level as well as OSD. Our review of the Navy’s plan for 
maintaining control of the cost for CVN 79 included an understanding of the application 
of lessons learned from the construction of CVN 78 along with the application of a more 
efficient  construction  plan  for  the  ship  including  introduction  of  competition  where 
possible. We have established an excellent relationship with the Navy to work together to 
change process and policies that have impacted the ability of the program to succeed, to 
include revitalizing the acquisition workforce and their skills. 
We are confident in the Navy’s plan for CVN 79 and CVN 80 and, as such, Under Secretary 
Kendall recently authorized the Navy to enter into the detail design and construction phase 
for CVN 79 and to enter into advanced procurement for long lead time materials for CVN 
Congressional Research Service  
 
66 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
80 construction. OSD and the Navy are committed to delivering CVN 79 within the limits 
of the cost cap legislated for this ship.80 
OSD DOT&E Testimony 
The prepared statement of the Director, Operational Test & Evaluation (DOT&E), within OSD 
states the following in part: 
The  Navy  intends  to  deliver  CVN  78  early  in  calendar  year  2016,  and  to  begin  initial 
operational test and evaluation (IOT&E) in late calendar year 2017. However, the Navy is 
in  the  process  of  developing  a  new  schedule,  so  some  dates  may  change.  Based  on  the 
current  schedule,  between  now  and  the  beginning  of  IOT&E,  the  CVN  78  program  is 
proceeding on an aggressive schedule to finish development, testing, troubleshooting, and 
correction of deficiencies for a number of new, complex systems critical to the warfighting 
capabilities  of  the  ship.  Low  or  unknown  reliability  and  performance  of  the  Advanced 
Arresting Gear (AAG), the Electromagnetic Aircraft Launch System (EMALS), the Dual 
Band Radar (DBR), and the Advanced Weapons Elevators (AWE) are significant risks to 
a  successful  IOT&E  and  first  deployment,  as  well  as  to  achieving  the  life-cycle  cost 
reductions the Navy has estimated will accrue for the Ford-class carriers. The maturity of 
these systems is generally not at the level that would be desired at this stage in the program; 
for  example,  the  CVN  78  test  program  is  revealing  problems  with  the  DBR  typical  of 
discoveries in early developmental testing. Nonetheless, AAG, EMALS, DBR, and AWE 
equipment  is  being  installed  on  CVN  78,  and  in  some  cases,  is  undergoing  shipboard 
checkout.  Consequently,  any  significant  issues  that  testing  discovers  before  CVN  78’s 
schedule-driven  IOT&E  and  deployment  will  be  difficult,  or  perhaps  impossible,  to 
address. 
Resolving the uncertainties in the reliability and performance of these systems is critical to 
CVN 78’s primary function of conducting combat operations. CVN 78 has design features 
intended to enhance its ability to launch, recover, and service aircraft. EMALS and AAG 
are key systems planned to provide new capabilities for launching and recovering aircraft 
that  are  heavier  and  lighter  than  typically  operated  on  Nimitz-class  carriers.  DBR  is 
intended to enhance radar coverage on CVN 78 in support of air traffic control and ship 
self-defense. DBR is planned to reduce some of the known sensor limitations on Nimitz-
class carriers that utilize legacy radars. The data currently available to my office indicate 
EMALS is unlikely to achieve the Navy’s reliability requirements. (The Navy indicates 
EMALS reliability is above its current growth curve, which is true; however, that growth 
curve was revised in 2013, based on poor demonstrated performance, to achieve EMALS 
reliability  on  CVN  78  a  factor  of  15  below  the  Navy’s  goal.)  I  have  no  current  data 
regarding  DBR  or  AWE  reliability,  and  data  regarding  the  reliability  of  the  re-designed 
AAG are also not available. (Poor AAG reliability in developmental testing led to the need 
to  re-design  components  of  that  system.)  In  addition,  performance  problems  with  these 
systems are continuing to be discovered. If the current schedule for conducting the ship’s 
IOT&E  and  first  deployment  remain  unchanged,  reliability  and  performance  shortfalls 
could degrade CVN 78’s ability to conduct flight operations. 
Due to known problems with current aircraft carrier combat systems, there is significant 
risk CVN 78 will not achieve its self-defense requirements. Although the CVN 78 design 
incorporates  several  combat  system  improvements  relative  to  the  Nimitz-class,  these 
improvements (if achieved) are unlikely to correct all of the known shortfalls. Testing on 
other  ships  with  similar  combat  systems  has  highlighted  deficiencies  in  weapon 
employment timelines, sensor coverage, system track management, and deficiencies with 
                                                 
80 Statement of Hon Katharina McFarland, Assistant Secretary of Defense (Acquisition), Before the Senate Armed 
Services Committee on Procurement, Acquisition, Testing and Oversight of the Navy’s Gerald R. Ford Class Aircraft 
Carrier Program, October 1, 2015, 5 pp. 
Congressional Research Service  
 
67 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
the recommended engagement tactics. Most of these limitations are likely to affect CVN 
78 and I continue to view this as a significant risk to the CVN 78’s ability to defend itself 
against attacks by the challenging anti-ship cruise  missile and other threats proliferating 
worldwide. 
The Navy’s previous decision to renege on its original commitment to conduct the Full 
Ship Shock Trial (FSST) on CVN 78 before her first deployment would have put CVN 78 
at risk in combat operations.  This decision  was reversed in  August 2015 by the Deputy 
Secretary of Defense. Historically, FSSTs for new ship classes have identified for the first 
time numerous mission-critical failures the Navy had to address to ensure the new ships 
were survivable in combat. We can expect that CVN 78’s FSST results will have significant 
and substantial implications on future carriers in the Ford-class and any subsequent new 
class of carriers. 
I also have concerns with manning and berthing on CVN 78. The Navy designed CVN 78 
to have reduced manning to reduce life-cycle costs, but Navy analyses of manning on CVN 
78 have identified problems in manning and berthing. These problems are similar to those 
seen on other recent ship classes such as DDG 1000 and the Littoral Combat Ship (LCS).... 
There  are  significant  risks  to  the  successful  completion  of  the  CVN  78  IOT&E  and  the 
ship’s  subsequent  deployment  due  to  known  performance  problems  and  the  low  or 
unknown reliability of key systems. For AAG, EMALS, AWE and DBR, systems that are 
essential to the primary missions of the ship, these problems, if uncorrected, are likely to 
affect CVN 78’s ability to conduct effective flight operations and to defend itself in combat. 
The  CVN  78  test  schedule  leaves  little  or  no  time  to  fix  problems  discovered  in 
developmental  testing  before  IOT&E  begins  that  could  cause  program  delays.  In  the 
current program schedule, major developmental test events overlap IOT&E. This overlap 
increases the likelihood problems will be discovered during  CVN 78’s IOT&E, with the 
attendant risk to the successful completion of that testing and to the ship’s first deployment. 
The  inevitable  lessons  we  will  learn  from  the  CVN  78  FSST  will  have  significant 
implications  for  CVN  78  combat  operations,  as  well  as  for  the  construction  of  future 
carriers  incorporating  the  ship’s  advanced  systems;  therefore,  the  FSST  should  be 
conducted on CVN 78 as soon as it is feasible to do so.81 
Navy Testimony 
The prepared statement of the Navy witnesses at the hearing states the following in part: 
In  June  2000,  the  Department  of  Defense  (DOD)  approved  a  three-ship  evolutionary 
acquisition approach starting with the last NIMITZ Class carrier (CVN 77) and the next 
two  carriers  CVNX1  (later  CVN  78)  and  CVNX2  (later  CVN  79).  This  approach 
recognized  the  significant  risk  of  concurrently  developing  and  integrating  new 
technologies into a new ship design incrementally as follows: 
•  The  design  focus  for  the  evolutionary  CVN  77  was  to  combine  information  network 
technology  with  a  new  suite  of  multifunction  radars  from  the  DDG  1000  program  to 
transform the ship’s combat systems and the air wing’s mission planning process into an 
integrated warfare system. 
•  The  design  focus  for  the  evolutionary  CVNX1  (future  CVN  78)  was  a  new  Hull, 
Mechanical and Electrical (HM&E) architecture within a NIMITZ Class hull that included 
a new reactor plant design, increased electrical generating capacity, new zonal electrical 
distribution,  and  new  electrical  systems  to  replace  steam  auxiliaries  under  a  redesigned 
flight deck employing new Electromagnetic Aircraft Launch System (EMALS) catapults 
                                                 
81 Statement by J. Michael Gilmore, Director, Operational Test and Evaluation, Office of the Secretary of Defense, 
Before the Senate Armed Services Committee, [October 1, 2015], 19 pp. 
Congressional Research Service  
 
68 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
together with aircraft ordnance and fueling “pit-stops”. Design goals for achieving reduced 
manning and improved maintainability were also defined. 
• The design focus for the evolutionary CVNX2 (future CVN 79) was a potential “clean-
sheet” design to “open the aperture” for capturing new but immature technologies such as 
the Advanced Arresting Gear (AAG) and Advanced Weapons Elevators (AWE) that would 
be ready in time for the third ship in the series; and thereby permit the experience gained 
from design and construction of the first two ships (CVN 77 and CVN 78) to be applied to 
the third ship (CVN 79). 
Early in the last decade, however, a significant push  was  made  within DOD  for a  more 
transformational approach to delivering warfighting capability. As a result, in 2002, DOD 
altered the program acquisition strategy by transitioning to the new aircraft carrier class in 
a single transformational leap vice an incremental three ship strategy. Under the revised 
strategy, CVN 77 reverted back to a “modified-repeat” NIMITZ Class design to minimize 
risk  and  construction  costs,  while  delaying  the  integrated  warfare  system  to  CVN  78. 
Further, due to budget constraints, CVN 78 would start construction a year later (in 2007) 
with a NIMITZ Class hull form but would entail a major re-design to accommodate all the 
new technologies from the three ship evolutionary technology insertion plan. 
This  leap  ahead  in  a  single  ship  was  captured  in  a  revised  Operational  Requirements 
Document (ORD) in 2004, which defined a new baseline that is the FORD Class today, 
with  CVN  78  as  the  lead  ship.  The  program  entered  system  development  and 
demonstration, containing the shift to a single ship acquisition strategy. The start of CVN 
78 construction was then delayed by an additional year until 2008 due to budget constraints. 
As a result, the traditional serial evolution of technology development, ship concept design, 
detail  design,  and  construction  –  including  a  total  of  23  developmental  systems 
incorporating  new  technologies  originally  planned  across  CVN  77,  CVNX1,  CVNX2  - 
were compressed and overlapped within the program baseline for the CVN 78. Today, the 
Navy is confronting the impacts of this compression and concurrency, as well as changes 
to assumptions made in the program planning more than a decade ago.... 
Given the lengthy design, development, and build span associated  with  major  warships, 
there is a certain amount of overlap or concurrency that occurs between the development 
of new systems to be delivered with the first ship, the design information for those new 
systems, and actual construction. Since this overlap poses cost and schedule risk for the 
lead ship of the class, program management activities are directed at mitigating this overlap 
to the maximum extent practicable. 
In the case of the FORD Class, the incorporation of 23 developmental systems at various 
levels of technical maturity (including EMALS, AAG, DBR, AWE, new propulsion plant, 
integrated control systems) significantly compounded the inherent challenges associated 
with accomplishing the first new aircraft carrier design in 40-years. The cumulative impact 
of this high degree of concurrency significantly exceeded the risk attributed to any single 
new system or risk issue and ultimately manifested itself in terms of delay and cost growth 
in  each  element  of  program  execution;  development,  design,  material  procurement 
(government and contractor), and construction.... 
Shipbuilder  actions  to  resolve  first-of-class  issues  retired  much  of  the  schedule  risks  to 
launch, but at an unstable cost. First-of-class construction and material delays led the Navy 
to revise the launch date in March 2013 from July 2013 to November 2013. Nevertheless, 
the four-month delay in launch allowed increased outfitting and ship construction that were 
most economically done prior to ship launch, such as completion of blasting and coating 
operations  for  all  tanks  and  voids,  installation  of  the  six  DBR  arrays,  and  increased 
installations  of  cable  piping,  ventilation,  electrical  boxes,  bulkheads  and  equipment 
foundations.  As  a  result,  CVN  78  launched  at  70  percent  complete  and  77,000  tons 
displacement – the highest levels  yet achieved in aircraft carrier construction. This high 
state  of  completion  at  launch  enabled  improved  outfitting,  compartment  completion,  an 
Congressional Research Service  
 
69 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
efficient  transition  into  the  shipboard  test  program,  and  the  on-time  completion  of  key 
milestones such as crew move aboard. 
With the advent of the shipboard test program, first time energization and grooming of new 
systems have required more time than originally planned. As a result, the Navy expects the 
sea trial schedule to be delayed about six to eight weeks. The exact impact on ship delivery 
will be determined based on the results of these trials. The Navy expects no schedule delays 
to CVN 78 operational testing and deployability due to the sea trials delay and is managing 
schedule delays within the $12.887 billion cost cap. 
Additionally, at delivery, AAG will not have completed its shipboard test program. The 
program  has  not  been  able  to  fully  mitigate  the  effect  of  a  two-year  delay  in  AAG 
equipment deliveries to the ship. All AAG equipment has been delivered to the ship and 
will be fully installed on CVN 78 at delivery.  The AAG shipboard test and certification 
program  will  complete  in  time  to  support  aircraft  launch  and  recovery  operations  in 
summer 2016.... 
The  Navy,  in  coordination  with  the  shipbuilder  and  major  component  providers, 
implemented a series of actions and initiatives in the management and oversight of CVN 
78 that crossed the full span of contracting, design, material procurement, GFE, production 
planning,  production  management  and  oversight.  The  Secretary  of  the  Navy  directed  a 
detailed review of the CVN 78 program build plan to improve end-to-end aircraft carrier 
design, material procurement, production planning, build and test, the results of which are 
providing benefit across all carriers. These corrective measures include: 
• CVN 78 design was converted from a ‘level of effort, fixed fee’ contract to a completion 
contract with a firm target and incentive fee. Shipbuilder cost performance has been on-
target or better since this contract change. 
• CVN 78 construction fee was reduced, consistent with contract provisions. However, the 
shipbuilder  remains  incentivized  by  the  contract  shareline  to  improve  upon  current  cost 
performance. 
•  Contract  design  changes  are  under  strict  control;  authorized  only  for  safety,  damage 
control, and mission-degrading deficiencies. 
• Following a detailed “Nunn-McCurdy-like” review in 2008-2009, the Navy converted 
the  EMALS  and  AAG  production  contract  to  a  firm,  fixed  price  contract,  capping  cost 
growth to each system. 
• In 2011, Naval Sea Systems Command completed a review of carrier specifications with 
the  shipbuilder,  removing  or  improving  upon  overly  burdensome  or  unneeded 
specifications that impose unnecessary cost on the program. Periodic reviews continue. 
Much of the impact to cost performance was attributable to shipbuilder and government 
material  cost  overruns.  The  Navy  and  shipbuilder  have  made  significant  improvements 
upon material ordering and delivery to the shipyard to mitigate the significant impact of 
material delays on production performance. 
These actions include: 
•  The  Navy  and  shipbuilder  instituted  optimal  material  procurement  strategies  and  best 
practices  (structuring  procurements  to  achieve  quantity  discounts,  dual-sourcing  to 
improve  schedule  performance  and  leveraging  competitive  opportunities)  from  outside 
supply chain management experts. 
• The shipbuilder assigned engineering and material sourcing personnel to each of their key 
vendors to expedite component qualifications and delivery to the shipyard. 
• The shipbuilder inventoried all excess material procured on CVN 78 for transfer to CVN 
79. 
Congressional Research Service  
 
70 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
•  The  Program  Executive  Officer  (Carriers)  has  conducted  quarterly  Flag-level  GFE 
summits  to  drive  cost  reduction  opportunities  and  ensure  on-time  delivery  of  required 
equipment and design information to the shipbuilder. 
The  CVN  78  build  plan,  consistent  with  the  NIMITZ  Class,  had  focused  foremost  on 
completion of structural and critical path work to support launching the ship on-schedule. 
Achieving the program’s cost improvement targets required that CVN 78 increase its level 
of completion at launch, from 60 percent to 70 percent. To achieve this and drive greater 
focus on system completion: 
• The Navy fostered a collaborative build process review by the shipbuilder with other Tier 
1  private  shipyards  in  order  to  benchmark  its  performance  and  identify  fundamental 
changes that are yielding marked improvement. 
• The shipbuilder established specific launch metrics by system and increased staffing for 
waterfront  engineering  and  material  expediters  to  support  meeting  those  metrics.  This 
ultimately delayed launch, but drove up pre-outfitting to the highest levels for CVN new 
construction which has helped stabilize cost and improve test program and compartment 
completion performance relative to CVN 77. 
• The shipbuilder linked all of these processes within a detailed integrated master schedule 
that has provided greater visibility to performance and greater ability to control cost and 
schedule performance across the shipbuilding disciplines. 
These initiatives, which summarize a more detailed list of actions being implemented and 
tracked as a result of the end-to-end review, were accompanied by important management 
changes. 
•  In  2011,  the  Navy  assigned  a  second  tour  Flag  Officer  with  considerable  carrier 
operations,  construction,  and  program  management  experience  as  the  new  Program 
Executive Officer (PEO). 
• The new PEO established a separate Program Office, PMS 379, to focus exclusively on 
CVN 79 and CVN 80, which enables the lead ship Program Office, PMS 378, to focus on 
cost control, schedule performance and the delivery of CVN 78. 
• In 2012, the shipbuilder assigned a new Vice President in charge of CVN 78, a new Vice 
President in charge of material management and purchasing, and a number of new general 
ship foremen to strengthen CVN 78 performance. 
•  The  new  PEO  and  shipyard  president  began  conducting  bi-weekly  launch  readiness 
reviews focused on cost performance, critical path issues and accomplishment of the targets 
for launch completion. These bi-weekly reviews will continue through delivery. 
•  Assistant  Secretary  of  the  Navy  (Research,  Development,  and  Acquisition)  (ASN 
(RD&A)) conducts quarterly reviews of program progress and performance with the PEO 
and shipbuilder to ensure that all that can be done to improve on cost performance is being 
done. 
The series of actions taken by the Navy and the shipbuilder are achieving the desired effect 
of  arresting  cost  growth,  establishing  stability,  and  have  resulted  in  no  changes  in  the 
Government’s estimate at completion over the past four years. The Department of the Navy 
is  continuing  efforts  to  identify  cost  reductions,  drive  improved  cost  and  schedule 
performance, and manage change. The Navy has established a rigorous process with the 
shipbuilder  that  analyzes  each  contract  change  request  to  approve  only  those  change 
categories  allowed  within  the  2010  ASN(RD&A)  change  order  management  guidance. 
This  guidance  only  allows  changes  for  safety,  contractual  defects,  testing  and  trial 
deficiencies, statutory and regulatory changes that are accompanied by funding and value 
engineering change proposals with instant contract savings. While the historical average 
for contractual change level is approximately 10 percent of the construction cost for the 
Congressional Research Service  
 
71 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
lead ship of a new class, CVN 78 has maintained a change order budget of less than four 
percent to date despite the high degree of concurrent design and development. 
Finally, the Navy has identified certain areas of the ship whose completion is not required 
for  delivery,  such  as  berthing  spaces  for  the  aviation  detachment,  and  has  removed  this 
work  from  the  shipbuilder’s  contract.  This  deferred  work  will  be  completed  within  the 
ship’s  budgeted  end  cost  and  is  included  within  the  $12,887  million  cost  estimate.  By 
performing this deferred work in the post-delivery period using CVN 78 end cost funding, 
it can be competed and accomplished at lower cost and risk to the overall ship delivery 
schedule.... 
The CVN 79 cost cap was established in 2006 and adjusted by the Secretary of the Navy 
in 2013, primarily  to address inflation between 2006 and 2013 plus $325 million of the 
allowed increase for non-recurring engineering to incorporate design improvements for the 
CVN 78 Class construction. 
The  Navy  and  the  shipbuilder  conducted  an  extensive  affordability  review  of  carrier 
construction and made significant changes to deliver CVN 79 at the lowest possible cost. 
These  changes  are  focused  on  eliminating  the  largest  impacts  to  cost  performance 
identified during the construction of CVN 78 as well as furthering improvements in future 
carrier construction. The Navy outlined cost savings initiatives in its Report to Congress in 
May, 2013, and is executing according to plan. 
Stability  in  requirements,  design,  schedule,  and  budget,  are  essential  to  controlling  and 
improving CVN 79 cost, and therefore is of highest priority for the program. Requirements 
for CVN 79 were “locked down” prior to the commencement of CVN 79 construction. The 
technical baseline and allocated budget for these requirements were agreed to by the Chief 
of Naval Operations and  ASN(RD&A) and  further changes to the baseline require their 
approval, which ensures design stability and increases effectiveness during production. At 
the time of construction contract award, CVN 79 has 100 percent of the design product 
model complete (compared to 65 percent for CVN 78) and 80 percent of initial drawings 
released. Further, CVN 79 construction benefits from the maturation of virtually all new 
technologies inserted on CVN 78. In the case of EMALS and AAG, the system design and 
procurement costs are understood, and CVN 79 leverages CVN 78 lessons learned.... 
A completed FORD Class design enabled the shipbuilder to fully understand the “whole 
ship”  bill  of  materials  for  CVN  79  construction  and  to  more  effectively  manage  the 
procurement of those  materials  with the  knowledge of  material lead times and qualified 
sources  accrued  from  CVN  78  construction.  The  shipbuilder  is  able  to  order  ship-set 
quantities  of  material,  with  attendant  cost  benefits,  and  to  ensure  CVN  79  material  will 
arrive  on  time  to  support  construction  need.  Extensive  improvements  have  been  put  in 
place for CVN 79 material procurement to drive both cost reductions associated with more 
efficient  procurement  strategies  and  production  labor  improvements  associated  with 
improved material availability. Improved material availability is also a critical enabler to 
many construction efficiency improvements in CVN 79. 
The  shipbuilder  has  developed  an  entirely  new  material  procurement  and  management 
strategy for CVN 79. This new strategy consists of eight separate initiatives.... 
The shipbuilder and the Navy have performed a comprehensive review of the build strategy 
and processes used in construction of CVN 78 Class aircraft carriers as well as consulted 
with other Navy shipbuilders on best practices. As a result, the shipbuilder has identified 
and  implemented  a  number  of  changes  in  the  way  they  build  aircraft  carriers,  with  a 
dedicated  focus  on  executing  construction  activities  where  they  can  most  efficiently  be 
performed.  The  CVN  79  build  sequence  installs  20  percent  more  parts  in  shop,  and  30 
percent more parts on the final assembly platen, as compared to CVN 78. This work will 
result  in  an  increase  in  pre-outfitting  and  work  being  pulled  to  earlier  stages  in  the 
construction process where it is most efficiently accomplished.... 
Congressional Research Service  
 
72 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
In  conjunction  with  the  Navy  and  the  shipbuilder’s  comprehensive  review  of  the  build 
strategy and processes used in construction of CVN 78 Class aircraft carriers, a number of 
design changes were identified that would result in more affordable construction. Some of 
these design changes were derived from lessons learned in the construction of CVN 78 and 
others seek to further simplify the construction process and drive cost down.... 
In  addition  to  the  major  focus  discussed  above,  the  shipbuilder  continues  to  implement 
capital improvements to facilities that serve to reduce risk and improve productivity.... 
To enhance CVN 79 build efficiency and affordability, the Navy is implementing a two-
phase delivery plan. The two-phase strategy will allow the basic ship to be constructed and 
tested in the most efficient manner by the shipbuilder (Phase I) while enabling select ship 
systems and compartments to be completed in Phase II, where the work can be completed 
more affordably through competition or the use of skilled installation teams.... 
The CVN 80 planning and construction will continue to leverage class lessons learned in 
the effort to achieve cost and risk reduction for remaining FORD Class ships. The CVN 80 
strategy seeks to improve on CVN 79 efforts to frontload as much work as possible to the 
earliest phases of construction, where work is both predictable and more cost efficient.... 
While delivery of the first-of-class FORD has involved challenges, those challenges are 
being addressed and this aircraft carrier class will provide great value to our Nation with 
unprecedented and greatly needed warfighting capability at overall lower total ownership 
cost  than  a  NIMITZ  Class  CVN.  The  Navy  has  taken  major  steps  to  stem  the  tide  of 
increasing costs and drive affordability into carrier acquisition.82 
GAO Testimony 
The prepared statement of the GAO witness at the hearing states the following in part: 
The Ford-class aircraft carrier’s lead ship began construction with an unrealistic business 
case. A sound business case  balances the necessary resources and  knowledge needed to 
transform a chosen concept into a product. Yet in 2007, GAO found that CVN 78 costs 
were underestimated and critical technologies were immature—key risks that would impair 
delivering  CVN  78  at  cost,  on-time,  and  with  its  planned  capabilities.  The  ship  and  its 
business  case  were  nonetheless  approved.  Over  the  past  8  years,  the  business  case  has 
predictably decayed in the form of cost growth, testing delays, and reduced capability—in 
essence,  getting  less  for  more.  Today,  CVN  78  is  more  than  $2  billion  over  its  initial 
budget. Land-based tests of key technologies have been deferred by years while the ship's 
construction schedule has largely held fast. The CVN 78 is unlikely to achieve promised 
aircraft launch and recovery rates as key systems are unreliable. The ship must complete 
its  final,  more  complex,  construction  phase  concurrent  with  key  test  events.  While 
problems are likely to be encountered, there is no margin for the unexpected. Additional 
costs are likely. 
Similarly,  the  business  case  for  CVN  79  is  not  realistic.  The  Navy  recently  awarded  a 
construction contract for CVN 79 which it believes will allow the program to achieve the 
current $11.5 billion legislative cost cap. Clearly, CVN 79 should cost less than CVN 78, 
as  it  will  incorporate  lessons  learned  on  construction  sequencing  and  other  efficiencies. 
While it may cost less than its predecessor, CVN 79 is likely to cost more than estimated. 
As GAO found in November 2014, the Navy’s strategy to achieve the cost cap relies on 
                                                 
82 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and 
Acquisition), Rear Admiral Donald E. Gaddis, Program Executive Officer, Tactical Aircraft, Department of the Navy, 
Rear Admiral Thomas J. Moore, Program Executive Officer, Aircraft Carriers, Department of the Navy, Rear Admiral 
Michael C. Manazir, Director, Air Warfare (OPNAV), Before the Senate Armed Services Committee on Procurement, 
Acquisition, Testing, and Oversight of the Navy’s Gerald R. Ford Class Aircraft Carrier Program, October 1, 2015, 22 
pp. 
Congressional Research Service  
 
73 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
optimistic  assumptions  of  construction  efficiencies  and  cost  savings—including 
unprecedented  reductions  in  labor  hours,  shifting  work  until  after  ship  delivery,  and 
delivering the ship with the same baseline capability as CVN 78 by postponing planned 
mission system upgrades and modernizations until future maintenance periods. 
Today, with CVN 78 over 92 percent complete as it reaches delivery in May 2016, and the 
CVN  79  on  contract,  the  ability  to  exercise  oversight  and  make  course  corrections  is 
limited. Yet, it is not too late to examine the carrier’s acquisition history to illustrate the 
dynamics of shipbuilding—and weapon system—acquisition and the challenges they pose 
to acquisition reform. The carrier’s problems are by no means unique; rather, they are quite 
typical  of  weapon  systems.  Such  outcomes  persist  despite  acquisition  reforms  the 
Department of Defense and Congress have put forward—such as realistic estimating and 
“fly  before  buy.”  Competition  with  other  programs  for  funding  creates  pressures  to 
overpromise  performance  at  unrealistic  costs  and  schedules.  These  incentives  are  more 
powerful than policies to follow best acquisition practices and oversight tools. Moreover, 
the  budget  process  provides  incentives  for  programs  to  be  funded  before  sufficient 
knowledge  is  available  to  make  key  decisions.  Complementing  these  incentives  is  a 
marketplace  characterized  by  a  single  buyer,  low  volume,  and  limited  number  of  major 
sources.  The  decades-old  culture  of  undue  optimism  when  starting  programs  is  not  the 
consequence  of  a  broken  process,  but  rather  of  a  process  in  equilibrium  that  rewards 
unrealistic business cases and, thus, devalues sound practices.83 
July 2015 Press Report 
A July 2, 2015, press report states the following: 
The  Navy  plans  to  spend  $25  million  per  year  beginning  in  2017  as  a  way  to  invest  in 
lowering the cost of building the services’ new Ford-class aircraft carriers, service officials 
said. 
“We  will  use  this  design  for  affordability  to  make  new  improvements  in  cost  cutting 
technologies that will go into our ships,” said Rear Adm. Michael Manazir, Director, Air 
Warfare.... 
“We just awarded a contract to buy long lead item materials [for CVN-79] and lay out an 
allocated budget for each of the components of that ship. We want to build the ship in the 
most efficient manner possible,” Rear Adm. Thomas Moore, Program Executive Officer, 
Carriers, said. 
Navy leaders say the service is making positive strides regarding the cost of construction 
for  the  USS  Kennedy  and  plans  to  stay  within  the  congressional  cost  cap  of  $11.498 
billion.... 
The $25 million design for affordability initiative is aimed at helping to uncover innovative 
shipbuilding techniques and strategies that will accomplish this and lower costs. 
Moore said the goal of the program is to, among other things, remove $500 million from 
the cost of the third Ford-class carrier, the USS Enterprise, CVN 80. 
“It is finding a million here and a million there and eventually that is how you get a billion 
dollars out of the ship from (CVN) 78 to (CVN) 79. The goal is to get another $500 million 
out of CVN 80. The $25 million dollars is a pretty prudent investment if we can continue 
to drive the cost of this class of ship down,” Moore told reporters recently. 
                                                 
83 Government Accountability Office, Ford Class Aircraft Carrier[:] Poor Outcomes Are the Predictable 
Consequences of the Prevalent Acquisition Culture, GAO-16-84T, October 1, 2015, summary page. (Testimony Before 
the Committee on Armed Services, U.S. Senate, Statement of Paul L. Francis, Managing Director Acquisition and 
Sourcing Management.) 
Congressional Research Service  
 
74 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Moore explained that part of the goal is to get to the point where a Ford-class carrier can 
be  built  for  the  same  amount  of  man-hours  it  took  to  build  their  predecessor  ships,  the 
Nimitz-class carriers. 
“We want to get back to the goal of being able to build it for historical Nimitz class levels 
in terms of man hours for a ship that is significantly more capable and more complex to 
build,” Moore added. 
The money will invest in new approaches and explore the processes that a shipyard can use 
to build the ship, Moore added. 
“They’ve  made  a  significant  investment  in  these  new  welding  machines.  These  new 
welding machines allow the welder to use different configurations. This has significantly 
improved the throughput that the shipyard has,” Moore said, citing an example of the kind 
of thing the funds would be used for. 
The funds will also look into whether new coatings for the ship or welding techniques can 
be used and whether millions of feet of electrical cabling can be installed in a more efficient 
manner, Moore added. 
Other  cost  saving  efforts  assisted  by  the  funding  include  the  increased  use  of  complex 
assemblies,  common  integrated  work  packages,  automated  plate  marking,  weapons 
elevator door re-design and vertical build strategies, Navy officials said. 
Shipbuilders could also use a new strategy of having work crews stay on the same kind of 
work for several weeks at a time in order to increase efficiency, Moore said. Also, some of 
the construction work done on the USS Ford while it was in dry dock is now being done in 
workshops and other areas to improve the building process, he added.84 
June 2015 Press Reports 
A June 29, 2015, press report states the following: 
Newport News Shipbuilding will see cost reduction on the order of 18 percent fewer man 
hours overall from the first Ford-class aircraft carrier to the second, according to a company 
representative. 
Ken Mahler, Newport News vice president of Navy programs, touted the shipyard's cost 
savings on the John F. Kennedy (CVN-79) during a June 15 interview with Inside the Navy. 
This  reduction  was  facilitated  by  the  investments  the  shipyard  is  making  in  carrier 
construction, as well as lessons learned from the first ship, the Gerald R. Ford (CVN-78), 
which will deliver next year.85 
A June 23, 2015, press report states the following: 
The Pentagon’s cost-assessment office  now says the  Navy’s second aircraft carrier in a 
new class will exceed a congressionally mandated cost cap by $235 million. 
That’s down from an April estimate that the USS John F. Kennedy, the second warship in 
the new Ford class, would bust a $11.498 billion cap set by lawmakers by $370 million.86 
The Navy maintains that it can deliver the ship within the congressional limit. 
                                                 
84 Kris Osborn, “Navy Launches New Affordability Plan for Ford-Class Carriers,” DOD Buzz, July 2, 2015. 
85 Lara Seligman, “Newport News See 18 Percent Fewer Man Hours On Second Ford Carrier,” Inside the Navy, June 
29, 2015. 
86 See Anthony Capaccio, “Aircraft Carrier $370 Million Over Congressional Cost Cap,” Bloomberg News, May 19, 
2015. 
Congressional Research Service  
 
75 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
“The original figure was a draft based on preliminary information,” Navy Commander Bill 
Urban, a spokesman for the Pentagon’s Cost Assessment and Program Evaluation office, 
said in an e-mail. As better information, such as updated labor rates, became available, the 
office “revised its estimate to a more accurate number,” he said.87 
A June 15, 2015, press report states the following: 
[Rear  Admiral  Tom]  Moore  [program  executive  officer  for  aircraft  carriers].  said  the 
program would save a billion dollars by decreasing the man hours needed to construct the 
ship by 18 percent from CVN-78 to 79—down to about 44 million manhours. He said this 
reduction is only a first step in taking cost ouot of the carrier program. The future Enterprise 
(CVN-80) will take about 4 million manhours out, or another 10 percent reduction, for a 
savings of about $500 million. 
But  beyond  seeking  ways  to  take  cost  out,  the  contract  itself  reduces  the  risk  to  the 
government, Moore said. 
“The main construction of the ship is now in a fixed price environment, so that switchover 
really limits the government’s liability,” he said. 
Without getting into specific dollar amounts due to business sensitivities, Moore explained 
that “this is the lowest target fee we’ve ever had on any CVN new construction. Look at 
tghe shape of the share [government-contractor cost] share lines, because the share lines at 
the end of the day are a measure of risk. So where we’d like to get quickly to [a] 50/50 
[share  line],  in  past  carrier  contracts  we’ve  been  out  at  85/15,  90/10—which  basically 
means  for  every  dollar  over  [the  target  cost  figure,  up  to  the  ceiling  cost  figure],  the 
government picks up 85 cents on the dollar. And this contract very quickly gets to 50/50. 
The  other  thing  is  ceiling  price—on  a  fixed-price  contract,  the  ceiling  price  is  the 
government’s maximum liability. And on this particular contract, again, it is the lowest 
ceiling price we’ve ever had [for a CVN].”88 
February 2015 Navy Testimony 
At a February 25, 2015, hearing on Department of the Navy acquisition programs, Department of 
the Navy officials testified the following: 
The Navy is committed to delivering  CVN 78  within the $12.887 billion Congressional 
cost cap. Sustained efforts to identify cost reductions and drive improved cost and schedule 
on this first-of-class aircraft carrier have resulted in highly stable performance since 2011. 
Parallel efforts by the Navy and shipbuilder are driving down and stabilizing aircraft carrier 
construction costs for the future John F Kennedy (CVN 79) and estimates for the future 
Enterprise (CVN 80). As a result of the lessons learned on CVN 78, the approach to carrier 
construction  has  undergone  an  extensive  affordability  review.  The  Navy  and  the 
shipbuilder have made significant changes on CVN 79 to reduce the cost to build the ship 
as detailed in the 2013 CVN 79 report to Congress. The benefits of these changes in build 
strategy and resolution of first-of-class impacts on CVN 79 are evident in metrics showing 
significantly  reduced  man-hours  for  completed  work  from  CVN  78.  These  efforts  are 
ongoing and additional process improvements continue to be identified. 
The  Navy  extended  the  CVN  79  construction  preparation  contract  into  2015  to  enable 
continuation of ongoing planning, construction, and material procurement while capturing 
lessons learned associated with lead ship construction and early test results. The continued 
                                                 
87 Anthony Capaccio, “Second New Carrier Now Seen Busting a Cost Cap by $235 Million,” Bloomberg News, June 
23, 2015. 
88 Megan Eckstein, “Navy: CVN-79 Contract Has Lowest Ceiling Price Ever; R&D Investment Will Take Out Further 
Cost,” USNI News, June 15, 2015. 
Congressional Research Service  
 
76 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
negotiations of the detail design and construction (DD&C) contract afford an opportunity 
to  incorporate  further  construction  process  improvements  and  cost  reduction  efforts. 
Award of the DD&C contract is expected in third quarter FY 2015. This will be a fixed 
price-type contract. 
Additionally, the Navy will deliver the CVN 79 using a two-phased strategy. This enables 
select ship systems and compartments to be completed in a second phase, wherein the work 
can  be  completed  more  efficiently  through  competition  or  the  use  of  skilled  installation 
teams  responsible  for  these  activities.  This  approach,  key  to  delivering  CVN  79  at  the 
lowest cost, also enables the Navy to procure and install shipboard electronic systems at 
the latest date possible. 
The FY 2014 NDAA adjusted the CVN 79 and follow ships cost cap to $11,498 million to 
account  for  economic  inflation  and  non-recurring  engineering  for  incorporation  of  lead 
ship  lessons  learned  and  design  changes  to  improve  affordability.  In  transitioning  from 
first-of-class to first follow ships, the Navy has maintained Ford class requirements and the 
design is highly stable. Similarly, we have imposed strict interval controls to drive changes 
to the way we do business in order to ensure CVN 79 is delivered below the cost cap. To 
this same end, the FY 2016 President’s Budget request aligns funding to the most efficient 
build strategy for this ship and we look for Congress’ full support of this request to enable 
CVN 79 to be procured at the lowest possible cost. 
Enterprise (CVN 80) will begin long lead time material procurement in FY 2016. The FY 
2016 request re-phases CVN 80 closer to the optimal profile, therefore reducing the overall 
ship cost. The Navy will continue to investigate and will incorporate further cost reduction 
initiatives, engineering efficiencies, and lessons learned from CVN 78 and CVN 79. Future 
cost  estimates  for  CVN  80  will  be  updated  for  these  future  efficiencies  as  they  are 
identified.89 
May 2013 Navy Testimony 
In its prepared statement for a May 8, 2013, hearing on Navy shipbuilding programs before the 
Seapower subcommittee of the Senate Armed Services Committee, the Navy stated that 
In 2011, the Navy identified spiraling cost growth [on CVN-78] associated  with first of 
class  non-recurring  design,  contractor  and  government  furnished  equipment,  and  ship 
production issues on the lead ship. The Navy completed an end-to-end review of CVN 78 
construction  in  December  2011  and,  with  the  shipbuilder,  implemented  a  series  of 
corrective  actions  to  stem,  and  to  the  extent  possible,  reverse  these  trends.  While  cost 
performance has stabilized, incurred cost growth is irreversible.... 
As  a  result  of  lessons  learned  on  CVN  78,  the  approach  to  carrier  construction  has 
undergone an extensive affordability review; and the Navy and the shipbuilder have made 
significant  changes  on  CVN  79  that  will  reduce  the  cost  to  build  the  ship.  CVN  79 
construction  will  start  with  a  complete  design,  firm  requirements,  and  material 
economically  procured  and  on  hand  in  support  of  production  need.  The  ship’s  build 
schedule also provides for increased completion levels at each stage of construction with 
resulting improved production efficiencies.... 
Inarguably, this new class of aircraft carrier brings forward tremendous capability and life-
cycle cost advantages compared to the NIMITZ-class it will replace. However, the design, 
                                                 
89 Statement of the Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and 
Acquisition) and Vice Admiral Joseph P. Mulloy, Deputy Chief of Naval Operations for Integration of Capabilities and 
Resources and Lieutenant General Kenneth J. Glueck, Jr., Deputy Commandant, Combat Development and Integration 
& Commanding General, Marine Corps Combat Development Command, Before the Subcommittee on Seapower and 
Projection Forces of the House Armed Services Committee on Department of the Navy Seapower and Projection 
Forces Capabilities, February 25, 2015, pp. 5-6. 
Congressional Research Service  
 
77 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
development  and  construction  efforts  required  to  overcome  the  technical  challenges 
inherent to these advanced capabilities have significantly impacted cost performance on 
the lead ship. The Navy continues implementing actions from the 2012 detailed review of 
the FORD-Class build plan to control cost and improve performance across lead and follow 
ship contracts. This effort, taken in conjunction with a series of corrective actions with the 
shipbuilder  on  the  lead  ship,  will  not  recover  costs  to  original  targets  for  GERALD  R. 
FORD [CVN-78], but should improve performance on the lead ship while fully benefitting 
CVN 79 and following ships of the class.90 
In the discussion portion of the hearing, Sean Stackley, the Assistant Secretary of the Navy for 
Research, Development and Acquisition (i.e., the Navy’s acquisition executive), testified that 
First, the cost growth on the CVN-78 is unacceptable. The cost growth dates back in time 
to the very basic concepts that went into take in the Nimitz-class and doing a total redesign 
of the Nimitz class to get to a level of capability and to reduce operating and support cost 
for the future carrier. Far too much risk was carried into the design of the first of the Ford-
class. 
Cost growth stems to the design  was moving at the time production started. The vendor 
base that was responsible for delivering new components and material to support the ship 
production was (inaudible) with new developments in the vendor base and production plan 
do not account for the material ordering difficulties, the material delivery difficulties and 
some  of  the  challenges  associated  with  building  a  whole  new  design  compared  to  the 
Nimitz.... 
Sir, for CVN-79, we have—we have held up the expenditures on CVN-79 as we go through 
the details of—one, ensuring that the design of the 78 is complete and repeated for the 79s 
[sic] that we start with a clean design. 
Two,  we're  going  through  the  material  procurement.  We  brought  a  third  party  into 
assessment material-buying practices at Newport News to bring down the cost of material. 
And we're metering out the dollars for buying material until it hits the objectives that we're 
setting for CVN-79 through rewriting the build plan on CVN-79. 
If  you  take  a  look  at  how  the  78  is  being  constructed,  far  too  much  work  is  being 
accomplished late in the build cycle. So we are rewriting the build plan for CVN-79, do 
more work in the shops where it’s more efficient, more work in the buildings where it’s 
more efficient, less work in the dry dock, less work on the water. And then we're going 
after the rates—the labor rates and the investments needed by the shipbuilder to achieve 
these efficiencies.91 
Later in the hearing, Stackley testified that 
the history in shipbuilding is since you don't have a prototype for a new ship, the first of 
class referred to as the lead ship is your prototype. And so you carry a lot of risk into the 
construction of that first of class. 
Also, given the nature that there’s a lengthy design development and build span associated 
with ships, so there is a certain amount of overlap or concurrency that occurs between the 
development of new systems that need to be delivered with the first ship, the incorporation 
                                                 
90 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and 
Acquisition) and Vice Admiral Allen G. Myers, Deputy Chief of Naval Operations for Integration of Capabilities and 
Resources and Vice Admiral Kevin M. McCoy, Commander, Naval Sea Systems Command, Before the Subcommittee 
on Seapower of the Senate Armed Services Committee on Department of the Navy Shipbuilding Programs, May 8, 
2013, p. 8. 
91 Transcript of hearing. 
Congressional Research Service  
 
78 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
of the design of those new systems and the actual construction. And so to the extent that 
there is change in a new ship class then the risk goes up accordingly. 
In  the  case  of  the  CVN-78,  the  degree  of  change  compared  to  the  Nimitz  was  fairly 
extraordinary  all  for  good  reasons,  good  intentions,  increased  capability,  increased 
survivability,  significant  reduction  in  operating  and  support  costs.  So  there  was  a 
determination that will take on this risk in order to get those benefits, and the case of the 
CVN-78, those risks are driving a lot of the cost growth on the lead ship. 
When you think about the follow ships, now you've got a stable design, now your vendor 
base has got a production line going to support the production. Now you've got a build plan 
and a workforce that has climbed up on the learning curve to drive cost down. So you can 
look at—you can look at virtually every shipbuilding program and you'll see a significant 
drop-off in cost from that first of class to the follow ships. 
And then you look for a stable learning curve to take over in the longer term production of 
a ship class. 
Carriers  are  unique  for  a  number  of  reasons,  one  of  which  we  don't  have  an  annual 
procurement of carriers. They're spread out over a five and, in fact, in the case of 78 as 
much  as  seven-year  period.  So  in  order  to  achieve  that  learning,  there  are  additional 
challenges  associated  with  achieving  that  learning.  And  so  we're  going  at  it  very 
deliberately on the CVN-79 through the build plan with the shipbuilder to hit the line that 
we've got to have—the cost reductions that we've got to have on the follow ships of the 
class.92 
March 2013 Navy Report 
A March 2013 report to Congress on the Navy’s plan for building CVN-79 that was released to 
the public on May 16, 2013, states the following in its executive summary: 
As  a  result  of  the  lessons  learned  on  CVN  78,  the  approach  to  carrier  construction  has 
undergone an extensive affordability review and the Navy and the shipbuilder have made 
significant  changes  on  CVN  79  that  will  significantly  reduce  the  cost  to  build  the  ship. 
These include four key construction areas: 
—  CVN 79 construction will start with a complete design and a complete bill of material 
—  CVN 79 construction will start with a firm set of stable requirements 
—  CVN  79  construction  will  start  with  the  development  complete  on  a  host  of  new 
technologies  inserted  on  CVN  78  ranging  from  the  Electromagnetic  Aircraft  Launch 
System (EMALS), the Dual Band Radar, and the reactor plant, to key valves in systems 
throughout the ship 
—  CVN  79  construction  will  start  with  an  ‘optimal  build’  plan  that  emphasizes  the 
completion of work and ship outfitting as early as possible in the construction process to 
optimize cost and ultimately schedule performance. 
In addition to these fundamentals, the Navy and the shipbuilder are tackling cost through a 
series of other changes that when taken over the entire carrier will have a significant impact 
on construction costs. The Navy has also imposed cost targets and is aggressively pursuing 
cost  reduction  initiatives  in  its  government  furnished  systems.  A  detailed  accounting  of 
these actions is included in this report. 
                                                 
92 Transcript of hearing. 
Congressional Research Service  
 
79 
 link to page 90 Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The actions discussed in this report are expected to reduce the material cost of CVN 79 by 
10-20% in real terms from CVN 78, to reduce the number of man-hours required to build 
the  CVN 79 by 15-25% from CVN 78, and to reduce the  cost of  government furnished 
systems by 5-10% in real terms from CVN 78.93 
For the full text of the Navy’s report, see the Appendix C. 
March 2012 Navy Letter to Senator McCain 
Secretary of the Navy Ray Mabus, in a letter with attachment sent in late March 2012 to Senator 
John McCain on controlling cost growth in CVN-78, stated the following: 
Dear Senator McCain:  
Thank you for your letter of March 21, 2012, regarding the first-of-class aircraft carrier, 
GERALD R. FORD (CVN 78). Few major programs carry greater importance or greater 
impact  on  national  security,  and  no  other  major  program  comprises  greater  scale  and 
complexity  than  the  Navy’s  nuclear  aircraft  carrier  program.  Accordingly,  successful 
execution of this program carries the highest priority within the Department of the Navy.  
I have shared in the past my concern when I took office and learned the full magnitude of 
new technologies and design change being brought to the FORD. Requirements drawn up 
more than a decade prior for this capital ship  drove development of a new reactor plant, 
propulsion  system,  electric  plant  and  power  distribution  system,  first  of  kind 
electromagnetic  aircraft  launching  system,  advanced  arresting  gear,  integrated  warfare 
system including a new radar and communications suite, air conditioning plant, weapons 
elevators, topside design, survivability improvements, and all new interior arrangements. 
CVN 78 is a near-total redesign of the NIMITZ Class she replaces. Further, these major 
developments, which were to be incrementally introduced in the program, were directed in 
2002  to  be  integrated  into  CVN  78  in  a  single  step.  Today  we  are  confronting  the  cost 
impacts of these decisions made more than a decade ago.  
In my August 29, 2011 letter, I provided details regarding these cost impacts. At that time, 
I  reported  the  current  estimate  for  the  Navy’s  share  of  the  shipbuilder’s  construction 
overrun, $690 million, and described that I had directed an end-to-end review to identify 
the changes necessary to improve cost for carrier design, material procurement, planning, 
build and test. The attached white paper provides the findings of that review and the steps 
we are taking to drive affordability into the remaining CVN 78 construction effort. Pending 
the results of these efforts, the Navy  has  included the  ‘fact of life’ portion of the stated 
overrun in the Fiscal Year 2013 President’s Budget request. The review also highlighted 
the compounding effects of applying traditional carrier build planning to a radically new 
design; the challenges inherent to low-rate, sole-source carrier procurement; and the impact 
of external economic factors accrued over 15 years of CVN 78 procurement—all within 
the  framework  of  cost-plus  contracts.  The  outlined  approach  for  ensuring  CVN  79  and 
follow  ship  affordability  focuses  equally  upon  tackling  these  issues  while  applying  the 
many lessons learned in the course of CVN 78 procurement.  
 As always, if I may be of further assistance, please let me know. 
Sincerely, [signed] Ray Mabus 
Attachment: As stated  
                                                 
93 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, p. 3. An annotation on 
the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was 
posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To 
Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013. 
Congressional Research Service  
 
80 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Copy to: The Honorable Carl Levin, Chairman 
[Attachment] 
Improving Cost Performance on CVN 78  
CVN 78 is nearing 40 percent completion. Cost growth to-date is attributable to increases 
in  design,  contractor  furnished  material,  government  furnished  material  (notably,  the 
Electromagnetic Aircraft Launching System (EMALS), Advanced Arresting Gear (AAG), 
and the Dual Band Radar (DBR)), and production labor performance. To achieve the best 
case outcome, the program must execute with zero additional cost growth in design and 
material  procurement,  and  must  improve  production  performance.  The  Navy  and  the 
shipbuilder have implemented a series of actions and initiatives in the  management and 
oversight of CVN 78 that cross the full span of contracting, design, material procurement, 
government  furnished  equipment,  production  planning,  production,  management  and 
oversight. 
CVN  78  is  being  procured  within  a  framework  of  cost-plus  contracts.  Within  this 
framework,  however,  the  recent  series  of  action  taken  by  the  Navy  to  improve  contract 
effectiveness are achieving the desired effect of incentivizing improved cost performance 
and reducing government exposure to further cost growth.  
  CVN 78 design has been converted from a ‘level of effort, fixed fee’ contract to a 
completion contract with a firm target and incentive fee. Shipbuilder cost performance 
has been on-target or better since this contract was changed.  
  CVN  78 construction fee  has been retracted, consistent  with contract performance. 
However,  the  shipbuilder  is  incentivized  by  the  contract  shareline  to  improve  upon 
current performance to meet agreed-to cost goals.  
  Contract design changes are under strict control; authorized only for safety, damage 
control,  mission-degrading  deficiencies,  or  similar.  Adjudicated  changes  have  been 
contained to less than 1 percent of contract target price.  
  The Navy converted the EMALS and AAG production contract to a firm, fixed price 
contract, capping cost growth to that system and imposing negative incentives for late 
delivery.  
  Naval Sea Systems Command is performing a review of carrier specifications with the 
shipbuilder,  removing  or  improving  upon  overly  burdensome  or  unneeded 
specifications that impose unnecessary cost on the program.  
The single largest impact to cost performance to-date has been contractor and government 
material  cost  overruns.  These  issues  trace  to  lead  ship  complexity  and  CVN  78 
concurrency,  but  they  also  point  to  inadequate  accountability  for  carrier  material 
procurement, primarily during the ship’s advance procurement period (2002-2008).  
These effects cannot be reversed on CVN 78, but it is essential to improve upon material 
delivery to the shipyard to mitigate the significant impact of material delays on production 
performance. Equally important, the systemic material procurement deficiencies must be 
corrected  for  CVN  79.  To  this  end,  the  Navy  and  shipbuilder  have  taken  the  following 
actions.  
  The Navy has employed outside supply chain management experts to develop optimal 
material  procurement  strategies.  The  Navy  and  the  shipbuilder  are  reviewing 
remaining  material  requirements  to  employ  these  best  practices  (structuring 
procurements  to  achieve  quantity  discounts,  dual-sourcing  to  improve  schedule 
performance and leverage competitive opportunities, etc.).  
  The shipbuilder has assigned engineering and material sourcing personnel to each of 
their key vendors to expedite component qualifications and delivery to the shipyard.  
Congressional Research Service  
 
81 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
  The shipbuilder is inventorying all excess material procured on CVN 78 for transfer 
to CVN 79 (cost reduction to CVN 78), as applicable.  
  The  Program  Executive  Officer  (Carriers)  is  conducting  quarterly  flag-level 
government  furnished  equipment  summits  to  drive  cost  reduction  opportunities  and 
ensure  on-time  delivery  of  required  equipment  and  design  information  to  the 
shipbuilder. 
The most important finding regarding CVN 78 remaining cost is that the CVN 78 build 
plan, consistent with the NIMITZ class, focuses foremost on completion of structural and 
critical path work to support launching the ship on-schedule. This emphasis on structure 
comes at the expense of completing  ship systems, outfitting, and furnishing early  in the 
build process and results in costly, labor-intensive system completion activity during later; 
more costly stages of production. Achieving the program’s cost improvement targets will 
require that CVN 78 increase its level of completion at launch, from current estimate of 60 
percent to no less than 65 percent. To achieve this goal and drive greater focus on system 
completion:  
  the Navy fostered a collaborative build process review by the shipbuilder with other 
Tier  1  private  shipyards  in  order  to  benchmark  its  performance  arid  identify 
fundamental changes that would yield marked improvement;  
  the  shipbuilder  has  established  specific  launch  metrics  by  system  (foundations, 
machinery, piping, power panels, vent duct, lighting, etc.) and increased staffing for 
waterfront engineering and material expediters to support meeting these metrics;  
  the shipbuilder has linked all of these processes within a detailed integrated master 
schedule,  providing  greater  visibility  to  current  performance  and  greater  ability  to 
control future cost and schedule performance across the shipbuilding disciplines; 
  the Navy and shipbuilder are conducting Unit Readiness Reviews of CVN 78 erection 
units to ensure that the outfitted condition of each hull unit being lifted into the dry-
dock contains the proper level of outfitting.  
These initiatives, which summarize a more detailed list of actions being implemented and 
tracked  as  result  of  the  end-to-end  review,  are  accompanied  by  important  management 
changes.  
  The shipbuilder has assigned a new Vice President in charge of CVN 78, a new Vice 
President  in  charge  of  material  management  and  purchasing,  and  a  number  of  new 
general shop foreman to strengthen CVN 78 performance.  
  The Navy has assigned a second tour Flag Officer with considerable carrier operations, 
construction,  and  program  management  experience  as  the  new  Program-Executive 
Officer (PEO).  
  The PEO and shipyard president conduct bi-weekly launch readiness reviews focusing 
on cost performance, critical path issues and accomplishment of the target for launch 
completion.  
  The  Assistant  Secretary  of  the  Navy  (Research,  Development,  and  Acquisition) 
conducts a monthly review of program progress and performance with the PEO and 
shipbuilder, bringing to bear the full weight of the Department, as needed, to ensure 
that all that can be done to improve on cost performance is being done.  
Early  production  performance  improvements  can  be  traced  directly  to  these  actions, 
however, significant further improvement is required. To this end, the Navy is conducting 
a line-by-line review of all ‘cost to-go’ on CVN 78 to identify further opportunity to reduce 
cost and to mitigate risk.  
Improving Cost Performance on CVN 79  
Congressional Research Service  
 
82 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
CVN  79  Advance  Procurement  commenced  in  2007  with  early  construction  activities 
following in 2011. Authorization for CVN 79 procurement is requested in Fiscal Year 2013 
President’s Budget request with the first year of incremental funding. Two years have been 
added to the CVN 79 production schedule in this budget request, afforded by the fact that 
CVN 79 will replace CVN 68 when she inactivates. To improve affordability for CVN 79, 
the  Navy  plans  to  leverage  this  added  time  by  introducing  a  fundamental  change  to  the 
carrier  procurement  approach  and  a  corresponding  shift  to  the  carrier  build  plan,  while 
incorporating CVN 78 lessons learned.  
The two principal ‘documents’ which the Navy and shipbuilder must ensure are correct 
and complete at the outset of CVN 79 procurement are the design and the build plan.  
Design is governed by rules in place that no changes will be considered for the follow ship 
except changes necessary to correct design deficiencies on the lead ship, fact of life changes 
to correct obsolescence issues, or changes that  will result in reduced cost for the follow 
ship. Exceptions to these rules must be approved by the JROC, or designee. Accordingly, 
the Navy is requesting procurement authority for CVN 79 with the Design Product Model 
complete  and  construction  drawings  approximately  95  percent  complete  (compared  to 
approximately 30 percent complete at time of lead ship authorization).  
As well, first article testing and certification will be complete for virtually all major new 
equipments  introduced  in  the  FORD  Class.  At  this  point  in  time,  the  shipbuilder  has 
developed  a  complete  bill  of  material  for  CVN  79.  The  Navy  is  working  with  the 
shipbuilder to ensure that the contractor’s material estimates are in-line with Navy ‘should 
cost’ estimates; eliminating non-recurring costs embedded in lead ship material, validating 
quantities, validating escalation indices, incorporating lead ship lessons learned. The Navy 
has  increased  its  oversight  of  contractor  furnished  material  procurement,  ensuring  that 
material procurement is competed (where competition is available); that it is fixed priced; 
that commodities are bundled to leverage economic order quantity opportunities; and that 
the  vendor base capacity and  schedule  for receipt supports  the optimal build plan being 
developed for production.  
In  total,  the  high  level  of  design  maturity  and  material  certification  provides  a  stable 
technical  baseline  for  material  procurement  cost  and  schedule  performance,  which  are 
critical to developing and executing an improved, reliable build plan.  
In order to significantly improve production labor performance, based on timely receipt of 
design and material, the Navy and shipbuilder are reviewing and implementing changes to 
the CVN 79 build plan and affected facilities. The guiding principles are:  
  maximize planned work in the shops and early stages of construction;  
  revise  sequence  of  structural  unit  construction  to  maximize  learning  curve 
performance through ‘families of units’ and work cells;  
  incorporate design changes to improve FORD Class producibility;  
  increase the size of erection units to eliminate disruptive unit breaks and improve unit 
alignment and fairness;  
  increase outfitting levels for assembled units prior to erection in the dry-dock;  
  increase overall ship completion levels at each key event.  
The shipbuilder is working on detailed plans for facility improvements that will improve 
productivity, and the Navy  will consider incentives for capital improvements that would 
provide targeted return on investment, such as:  
  increasing the amount of temporary and permanent covered work areas;  
  adding ramps and service towers for improved access to work sites and the dry-dock;  
Congressional Research Service  
 
83 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
  increasing lift capacity to enable construction of larger, more fully outfitted super-lifts:  
An incremental improvement to carrier construction cost will fall short of the improvement 
necessary  to  ensure  affordability  for  CVN  79  and  follow  ships.  Accordingly,  the 
shipbuilder  has  established  aggressive  targets  for  CVN  79  to  drive  the  game-changing 
improvements needed for carrier construction. These targets include:  
  75 percent Complete at Launch (15 percent> [i.e., 15 percent greater than] FORD);  
  85-90 percent of cable pulled prior to Launch (25-30 percent> FORD);  
  30 percent increase in front-end shop work (piping details, foundations, etc);  
  All structural unit hot work complete prior to blast and paint;  
  25 percent increase to work package throughput;  
  100  percent  of  material  available  for  all  work  packages  in  accordance  with  the 
integrated master schedule;  
  zero delinquent engineering and planning products;  
  resolution of engineering problems in < 8 [i.e., less than 8] hours.  
In  parallel  with  efforts  to  improve  shipbuilder  costs,  the  PEO  is  establishing  equally 
aggressive  targets  to  reduce  the  cost  of  government  furnished  equipment  for  CVN  79; 
working equipment item by equipment item with an objective to reduce overall GFE costs 
by ~$500 million. Likewise, the Naval Sea Systems Command is committed to continuing 
its  ongoing  effort  to  identify  specification  changes  that  could  significantly  reduce  cost 
without compromising safety and technical rigor. 
The output of these efforts comprises the optimal build plan for CVN 79 and follow, and 
will be incorporated in the detail design and construction baseline for CVN 79. CVN 79 
will be procured using a fixed price incentive contract.94 
 
                                                 
94 Letter and attachment from Secretary of the Navy Ray Mabus to Senator John McCain, undated but posted at 
InsideDefnse.com (subscription required) on March 27, 2012. InsideDefense.com’s description of the letter states that it 
is dated March 26, 2012. 
Congressional Research Service  
 
84 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Appendix C. March 2013 Navy Report to Congress 
on Construction Plan for CVN-79 
This appendix reprints a March 2013 Navy report to Congress on the Navy’s construction plan 
for CVN-79.95 
                                                 
95 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, 17 pp. An annotation on 
the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was 
posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To 
Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013. 
Congressional Research Service  
 
85 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service  
 
86 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
87 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
88 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
89 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
90 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
91 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
92 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
93 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
94 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
95 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
96 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
97 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
98 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
99 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
100 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
101 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Congressional Research Service  
 
102 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Author Information 
 
Ronald O'Rourke 
   
Specialist in Naval Affairs 
    
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan 
shared staff to congressional committees and Members of Congress. It operates solely at the behest of and 
under the direction of Congress. Information in a CRS Report should not be relied upon for purposes other 
than public understanding of information that has been provided by CRS to Members of Congress in 
connection with CRS’s institutional role. CRS Reports, as a work of the United States Government, are not 
subject to copyright protection in the United States. Any CRS Report may be reproduced and distributed in 
its entirety without permission from CRS. However, as a CRS Report may include copyrighted images or 
material from a third party, you may need to obtain the permission of the copyright holder if you wish to 
copy or otherwise use copyrighted material. 
 
Congressional Research Service  
RS20643 · VERSION 195 · UPDATED 
103