
 
 
September 22, 2021
National Environmental Policy Act: Judicial Review 
and Remedies
According to the U.S. Department of Justice, the National 
right to challenge an action in court, including by having 
Environmental Policy Act of 1969 (NEPA) is the most 
standing. 
frequently litigated federal environmental statute. A 2020 
study estimated that, between 2001 and 2013, plaintiffs 
Common NEPA Claims 
challenged 1 in 450 agency actions taken to comply with 
In general, NEPA claims challenge an agency’s level of 
NEPA, with an average of 115 NEPA cases annually. 
NEPA analysis or the sufficiency of its documented review.  
Although NEPA does not provide for judicial review, 
courts allow challenges under the Administrative Procedure 
Failure to Prepare an EIS. Federal actions not resulting in 
Act (APA). This In Focus describes how the federal courts 
significant environmental impacts do not require an EIS. 
have interpreted and limited the availability of judicial 
When an agency approves a proposed action without 
review for claims against federal agencies and established 
preparing an EIS, plaintiffs often challenge the agency’s 
remedies for successful claims. 
decision, asserting that the action will result in significant 
impacts and therefore requires preparation of an EIS. For 
Background 
example, if an agency prepares an EA and then issues a 
NEPA requires federal agencies to analyze the impacts of 
FONSI, a court may examine whether agencies took the 
proposed “major Federal actions significantly affecting the 
requisite “hard look” at the environmental effects to decide 
quality of the human environment.” 42 U.S.C. 
whether the agency should have prepared an EIS. In one 
§ 4332(2)(C). This requirement serves the dual purpose of 
such case, the U.S. Court of Appeals for the Ninth Circuit 
informing the agency decisionmaking process, although not 
concluded that a single sentence analysis of a proposed 
demanding agencies to change their proposed actions, and 
whale hunt quota’s effects on the overall whale population 
informing the public of a proposed action’s effects. The 
did not justify issuance of a FONSI and ordered the agency 
level of analysis required depends on the environmental 
to prepare an EIS. Anderson v. Evans, 314 F.3d 1006 (9th 
impacts’ significance. Agencies prepare environmental 
Cir. 2002).  
impact statements (EISs) if there are significant impacts. 
An agency may also draft an environmental assessment 
Improper Reliance on Categorical Exclusions. An 
(EA) to determine whether to prepare an EIS. Based on an 
agency may determine that a proposed action falls into a 
EA, an agency will prepare an EIS or issue a “Finding of 
“categorical exclusion” (CE or CX). CXs are actions that 
No Significant Impacts” (FONSI). NEPA also established 
generally do not have significant impacts and therefore do 
the Council on Environmental Quality (CEQ), which issues 
not require an EIS absent extraordinary circumstances. 
regulations and guidance detailing how federal agencies 
Some disputes involve an agency’s decision to rely on a CX 
must implement NEPA. For more details, see CRS In Focus 
rather than prepare an EA or EIS. Courts may scrutinize 
IF11549, The Legal Framework of the National 
whether the type of project at issue falls within the scope of 
Environmental Policy Act. 
a CX. For example, the Ninth Circuit held that the Federal 
Highway Administration improperly relied on a CX to 
Basis for Judicial Review 
approve a highway interchange, as the magnitude of the 
NEPA does not provide for judicial review of federal 
project went beyond the scope of projects eligible for a CX. 
agency compliance with the act. Instead, the federal courts 
West v. Sec’y of Dep’t of Transp., 206 F.3d 920 (9th Cir. 
allow challenges to NEPA compliance under the APA. 
2000). In addition, when an agency fails to explain the 
Generally, plaintiffs claim that an agency’s actions were 
decision to rely on a CX or why “extraordinary 
“arbitrary, capricious, an abuse of discretion, or otherwise 
circumstances” that would trigger further review do not 
not in accordance with law” because of an agency’s failure 
exist, courts have found an APA violation. See, e.g., United 
to meet NEPA’s requirements. For more information, see 
States v. Coal. for Buzzards Bay, 644 F.3d 26 (1st Cir. 
CRS Legal Sidebar LSB10558, Judicial Review Under the 
2011); Alaska Ctr. for Env’t v. U.S. Forest Serv., 189 F.3d 
Administrative Procedure Act (APA). 
851 (9th Cir. 1999).  
A number of factors constrain judicial review. First, the 
Inadequate Analysis in an EIS. After an agency issues a 
disputed action must be “final,” and the legal challenge to 
decision based on an EIS or EA, stakeholders have 
that action brought within six years, as set out by the APA. 
challenged the adequacy of the environmental review 
Second, Congress may limit the scope of NEPA claims, 
supporting the decision. Such parties often argue that the 
either directly by addressing the availability of judicial 
agency failed to consider certain impacts or failed to fully 
review or indirectly by limiting NEPA’s applicability to a 
consider the weight of the impacts reviewed. In these cases, 
particular federal action. Third, the plaintiff must have the 
courts review the agency’s NEPA analysis to determine 
whether the agency’s decision was arbitrary or capricious 
https://crsreports.congress.gov 
National Environmental Policy Act: Judicial Review and Remedies 
under the APA. For example, the Ninth Circuit ruled that 
less likely to vacate the agency action if they find that the 
the Bureau of Ocean Energy Management violated the APA 
agency will likely cure the violation or that vacatur would 
by failing to quantify in its EIS the indirect greenhouse gas 
result in substantially disruptive effects on the project. 
emissions that would result from offshore oil exploration 
Compare Vecinos para el Bienestar de la Comunidad 
and production along the coast of Alaska. Ctr. for 
Costera v. FERC, 2021 WL 3354747 (D.C. Cir. 2021) 
Biological Diversity v. Bernhardt, 982 F.3d 723 (9th Cir. 
(remanding without vacatur), with Standing Rock Sioux 
2020). See also Am. Rivers & Ala. Rivers Alliance v. FERC, 
Tribe v. USACE, 985 F.3d 1032 (D.C. Cir. 2021) 
895 F.3d 32 (D.C. Cir. 2018) (holding that FERC’s NEPA 
(upholding district court decision to vacate based on prior 
analysis failed to consider the cumulative impact of 
failures to cure NEPA violations).   
previous power plant operations when considering licensing 
a hydroelectric project).  
In some cases, vacating an agency decision does not grant 
full relief to plaintiffs. In these cases, courts may grant 
Failure to Prepare a Supplemental EIS. CEQ’s 
injunctions to stay part or all of a project while an agency 
regulations require agencies to prepare an SEIS when the 
completes the requisite NEPA analysis. Before issuing an 
agency makes substantial changes to a proposal or learns of 
injunction, courts generally consider whether a plaintiff has 
“significant new circumstances or information relevant to 
demonstrated (1) irreparable injury; (2) other remedies are 
environmental concerns” after completion of a draft or final 
inadequate to compensate for the injury; (3) the balance of 
EIS. 40 C.F.R. § 1502.9. Plaintiffs sometimes allege that an 
the hardships demonstrate that equitable relief is warranted; 
agency’s failure to draft a supplemental EIS (SEIS) violates 
and (4) the public interest would not be disserved by an 
the APA. Not all new pieces of information or changes 
injunction. See, e.g., W. Watersheds Project v. Abbey, 719 
require an SEIS. Rather, the Supreme Court instructs 
F.3d 1035, 1054 (9th Cir. 2013) (citing Monsanto Co. v. 
agencies to apply the “rule of reason” to decide whether to 
Geertson Seed Farms, 561 U.S. 139, 156-57 (2010)); 
prepare an SEIS. Marsh v. Oregon Nat. Res. Council, 490 
Wyoming v. U.S. Dep’t of Agric., 661 F.3d 1209, 1272 
U.S. 360, 370-71 (1989).  
(10th Cir. 2011). Courts sometimes grant narrow 
injunctions when an agency can address site-specific issues 
Some lower courts interpreting CEQ’s regulations hold that 
within a project independently of other aspects or when a 
an agency must prepare an SEIS when a new proposal 
project has already received approval or is near completion 
“present[s] a seriously different picture of the 
when a lawsuit is filed. See, e.g., Sierra Club v. Bosworth, 
environmental impact.” See, e.g., Ark. Wildlife Fed’n v. 
510 F.3d 1016 (9th Cir. 2007). 
U.S. Army Corps of Eng’rs, 431 F.3d 1096, 1102 (8th Cir. 
2005). Applying this test, the First Circuit ordered an SEIS 
Preliminary Injunctions. Courts may grant preliminary 
when an agency adopted an alternative proposal not 
injunctions during litigation, which may bar all or part of a 
considered in earlier documents or distributed for public 
proposed action during the litigation. In a NEPA case 
comment. DuBois v. U.S. Dep’t of Agric., 102 F.3d 1273 
involving the Navy’s sonar training exercises, the Supreme 
(1st Cir. 1996). By contrast, some courts have declined to 
Court stated that plaintiffs must demonstrate (1) likelihood 
order an SEIS when the documentation showed that the 
of success on the merits; (2) likelihood of irreparable harm 
agencies sufficiently consulted with experts about 
in the absence of preliminary relief; (3) the balance of the 
potentially new effects or concluded no new significant 
equities tips in their favor; and (4) an injunction is in the 
effects existed. See, e.g., Laguna Greenbelt, Inc. v. U.S. 
public interest. Winter v. Natural Res. Defense Council, 
Dep’t of Transp., 42 F.3d 517 (9th Cir. 1994).  
Inc., 555 U.S. 7, 20 (2008). The Court also clarified that 
plaintiffs must show that irreparable harm is “likely in the 
Remedies in NEPA Litigation 
absence of an injunction,” not just a “possibility.” 
Plaintiffs may not seek damages under NEPA. Instead, 
plaintiffs generally seek declaratory relief, which is a court 
Remedies Under NEPA Regulations 
determination that an agency’s actions taken to comply with 
In 2020, CEQ finalized revisions to its 1978 NEPA 
NEPA violated the APA. As a remedy for such violations, a 
regulations. 85 Fed. Reg. 43,304 (July 16, 2020). The 2020 
court generally remands the case to the agency for further 
rules added a judicial remedies section, stating that CEQ 
proceedings, and it may specify what those further 
does not intend for a violation of NEPA to be presumed to 
proceedings must include. The broader effect of a remand 
be “a basis for injunctive relief or for a finding of 
on the affected project, however, varies depending on 
irreparable harm” and that “minor, non-substantive errors” 
whether a court orders equitable relief—i.e., vacates the 
that have no effect an agency’s decision are “considered 
agency action or issues an injunction. Neither of these 
harmless and shall not invalidate an agency action.” 40 
remedies is granted automatically in NEPA cases. These 
C.F.R. § 1500.3(d). It is unlikely that these statements of 
equitable remedies can be significant, as absent such relief, 
intent would have any legal effect on judicial authority to 
agencies may be able to implement projects before the 
issue injunctive relief for NEPA violations. The courts have 
additional NEPA procedures are complete. 
stayed litigation challenging the 2020 rules pending CEQ’s 
review and revision of them. 
While vacating the federal action may be the “ordinary” 
remedy, courts consider the “seriousness” of the NEPA 
Nina M. Hart, Legislative Attorney   
deficiencies and the “disruptive consequences” of vacating 
Linda Tsang, Legislative Attorney   
the order. See Black Warrior Riverkeeper, Inc. v. U.S. Army 
Corps of Eng’rs
IF11932
, 781 F.3d 1271 (11th Cir. 2015) 
(describing federal court practice). In general, courts are 
https://crsreports.congress.gov 
National Environmental Policy Act: Judicial Review and Remedies 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff to 
congressional committees and Members of Congress. It operates solely at the behest of and under the direction of Congress. 
Information in a CRS Report should not be relied upon for purposes other than public understanding of information that has 
been provided by CRS to Members of Congress in connection with CRS’s institutional role. CRS Reports, as a work of the 
United States Government, are not subject to copyright protection in the United States. Any CRS Report may be 
reproduced and distributed in its entirety without permission from CRS. However, as a CRS Report may include 
copyrighted images or material from a third party, you may need to obtain the permission of the copyright holder if you 
wish to copy or otherwise use copyrighted material. 
 
https://crsreports.congress.gov | IF11932 · VERSION 1 · NEW