

 
 Legal Sidebari 
 
Court Rules Dakota Access Pipeline Needs 
Further Environmental Review 
Updated February 1, 2021 
UPDATE: On January 26 2021, the U.S. Court of Appeals for the D.C. Circuit affirmed the district 
court’s decision requiring the Army Corps of Engineers to prepare an Environmental Impact Statement 
(EIS) prior to issuance of an easement across federal land for the Dakota Access Pipeline, but reversed 
the district court’s injunction prohibiting the operation of the Pipeline and directing that it be emptied of 
oil. The original Sidebar discussing the district court case is below. 
The Dakota Access Pipeline (DAPL), a crude oil pipeline developed by Energy Transfer Partners, carries 
crude oil from the Bakken fields in northwest North Dakota to southern Illinois. As discussed in this 
Legal Sidebar, the DAPL has been the subject of extensive debate and media attention, as well as 
prolonged litigation. Much of the attention on the DAPL centers on the portion of the pipeline route that is 
near or runs under Lake Oahe in North Dakota, a lake that has particular significance to Native Americans 
in the region. The U.S. District Court for the District of Columbia (D.C. District Court) recently held that 
this controversial portion of the route needs further environmental review. 
Background on DAPL Environmental Review 
Because the pipeline crosses waters subject to regulation under the Clean Water Act and land controlled 
by the federal government, federal law required the Army Corps of Engineers (Corps) to issue several 
authorizations for the project, including authorization for the stretch of pipeline under Lake Oahe. The 
Corps’ federal actions triggered the National Environmental Policy Act (NEPA), which requires federal 
agencies to assess the environmental impacts of a proposed action before making a decision about that 
action. Under NEPA, agencies considering actions not eligible for “categorical exclusions” must prepare 
Environmental Assessments (EAs). If the federal action will “significantly affect the quality of the human 
environment,” agencies must prepare an EIS. (Sometimes the agency skips the EA and moves directly to 
prepare the EIS.) Despite a previous determination that the Corps should prepare an EIS to assess the 
environmental impacts of the Corps action in depth, a 2017 Presidential Memorandum encouraged the 
Corps to consider a previously published EA–one that concluded with a Finding of No Significant 
Impact– sufficient to satisfy  NEPA. 
Congressional Research Service 
https://crsreports.congress.gov 
LSB10457 
CRS Legal Sidebar 
Prepared for Members and  
 Committees of Congress 
 
  
 
Congressional Research Service 
2 
Litigation over NEPA Compliance 
The Corps followed the Presidential Memorandum and did not prepare an EIS. Instead, it finalized its 
decision to issue a right of way under Lake Oahe and notified Congress in February 2017. However, a 
number of groups challenged the Corps’ decision, alleging, among other things, that the Corps had not 
satisfied NEPA’s requirements. The D.C. District Court found flaws in the Corps’ NEPA compliance. As a 
result, the court remanded the matter to the Corps for further administrative proceedings to address these 
NEPA shortcomings. 
The Corps completed its efforts on remand in February 2019, maintaining its position that an EIS was not 
required for this federal action. In response, several parties again petitioned the court to declare the Corps’ 
NEPA compliance efforts insufficient. A number of Indian tribes claimed that the Corps failed to address 
flaws in their NEPA analysis previously noted by the court, while other parties re-raised claims that the 
Corps had not complied with the National Historic Preservation Act (even though the court previously 
rejected those claims) and other issues. 
March 2020 Decision 
In its March 2020 decision, the D.C. District Court found that, on remand, the Corps had not adequately 
addressed the shortcomings in its NEPA analysis identified in the 2017 decision. 
The opinion focused on the argument that the Corps failed to address adequately whether the project was 
“highly controversial,” a designation that would require an EIS because it would automatically deem the 
project “significant” under NEPA regulations (40 C.F.R. §1508.27(b)(4)). Citing precedent, the court 
noted that federal actions are “controversial” where “substantial dispute exists as to the size, nature, or 
effect of the major federal action rather than to the existence of opposition to a use,” but also that 
“something more is required besides the fact that some people may be highly agitated and be willing to go 
to court over the matter.” Based on this precedent, the court concluded that “the significant public protests 
near Lake Oahe do not transform the pipeline’s approval into a highly controversial action within the 
meaning of 40 C.F.R. § 1508.27(b)(4).”  
Nevertheless, the court found that an EIS was required because the DAPL project was “highly 
controversial” for other reasons. Before identifying those reasons, the court set out to determine the scope 
of the inquiry. Quoting National Parks Conservation Association v. Semonite, a recent decision by the 
U.S. Court of Appeals for the District of Columbia, the court noted that “consistent and strenuous 
opposition, often in the form of concrete objections to the Corps’s analytical process and findings, from 
agencies entrusted with preserving historic resources and organizations with subject-matter expertise,” 
was enough to trigger an EIS under the “highly controversial” criteria. A number of public and private 
actors with subject matter expertise had raised similar objections to the Corps’ findings with respect to the 
DAPL. The appeals court in Semonite also rejected the argument that simply acknowledging and 
attempting to address the controversial aspects of the federal action was sufficient to satisfy NEPA, noting 
that agencies must provide adequate reasoning to support their decision making, which the Corps had 
arguably failed to do with respect to DAPL. Furthermore, as the D.C. District Court noted, in this case the 
Corps “has had an additional chance to respond to these renewed criticisms during the remand.” Based on 
the Semonite decision, the court in this case found it “prudent to analyze the substance of expert 
comments made both before and during the remand to determine whether they ‘succeed’ in resolving the 
points of scientific controversy that continue to be raised by experts.” 
The court divided these expert criticisms and comments by subject matter. First, the court reviewed 
concerns related to the DAPL’s leak-detection system. Some of the tribes’ experts pointed to a Pipeline 
and Hazardous Materials Safety Administration study finding that the type of leak-detection system 
deployed by DAPL had an 80% failure rate, and that, even as designed, the system would fail to detect 
  
Congressional Research Service 
3 
smaller leaks. The court found that the Corps had failed to address these concerns on remand. The court 
said that “[s]tating that [the Corps] had considered the information was a good start, but, while the Corps 
did indicate the type of monitoring devices that were used, it did not mention their locations, and, most 
critically, it did not point to any analysis that did in fact take these two details into consideration.” 
Next, the court turned to the safety record of the DAPL’s operator. Several experts argued that the Corps’ 
initial analysis had not addressed the operator’s safety record. These experts argued that a safety record 
review was an important part of a risk analysis because of its possible impact on the likelihood and 
severity of a potential pipeline spill. Experts also questioned the safety record of the DAPL’s designated 
operator, Sunoco/ETP (the two companies completed a merger during the litigation). One expert 
contended that Sunoco had “one of the lower performing safety records of any operator in the industry for 
spills and releases.” The court noted that the Corps’ response on remand “focused its responses on 
defending the operator’s performance record itself rather than on justifying its decision to not incorporate 
that record into its analysis,” and that “[i]t did not directly reply to the comment that it had not explained 
‘why historic shutdown discharges from other Sunoco/ETP pipeline incidents are not discussed or 
relevant.’” The court concluded that this response did not adequately address the operator issues raised by 
experts. 
The court next turned to concerns related to how winter conditions in North Dakota could affect the 
DAPL. Some experts questioned the Corps’ claim in the original EA that icy conditions would “serve as a 
natural barrier to the spread of oil,” and alleged that the Corps had not sufficiently addressed concerns 
about ice interfering with oil recovery in the event of a winter spill. The Corps defended their efforts to 
address this issue on remand, but the court found these efforts insufficient, noting that they had not 
resolved the controversy as required to satisfy the NEPA requirements for “highly controversial” federal 
projects. 
Finally, the court turned to what it called “the largest area of scientific controversy, particularly during 
remand”:  the Corps’ consideration of the Worst Case Discharge (WCD). The WCD analysis requires 
agencies to consider the impacts of the maximum discharge flow and length if met with the slowest 
potential response time. The court addressed whether the Corps resolved three perceived flaws in its 
analysis: leak detection timing, post-incident shutdown timing, and the impact of adverse weather and 
other adverse conditions on the WCD. In each case, the court held that the Corps had failed to address 
issues and gaps in its analysis raised by experts. 
In sum, the court concluded that the Corps’ efforts to rebut the experts’ comments were insufficient to 
resolve the controversy surrounding the project: 
The many commenters in this case pointed to serious gaps in crucial parts of the Corps’ analysis—
to  name  a  few,  that  the  pipeline’s  leak-detection  system  was  unlikely  to  work,  that  it  was  not 
designed to catch slow spills, that the operator’s serious history of incidents had not been taken into 
account, and that the worst-case scenario used by the Corps was potentially only a fraction of what 
a realistic figure would be—and the Corps was not able to fill any of them. 
As a result, the court found that the Corps violated NEPA by determining an EIS was unnecessary even 
though one of the EIS-triggering factors was met. At the same time, the court declined to address other 
challenges to the DAPL. The court considered it unnecessary to address the impact of a hypothetical oil 
spill on the Tribe’s fishing and hunting rights or the environmental-justice effects of the project, given 
that the finding that the project remained “highly controversial” for NEPA purposes already triggered the 
EIS requirement. The court also dismissed the Tribes’ non-NEPA-based claims. 
What’s Next for the DAPL? 
The Corps is likely to move forward with both the EIS and an appeal of the D.C. District Court’s 
decision. In the meantime, the court asked the parties to brief the issue of whether the court must vacate
  
Congressional Research Service 
4 
the easement across Lake Oahe that allows the pipeline to flow until the review on remand is completed 
or the issue is otherwise resolved. As those judicial and administrative proceedings move forward, 
legislators also have the option of superseding judicial or agency action with legislative action related to 
the DAPL and NEPA obligations. 
 
Author Information 
 
Adam Vann 
   
Legislative Attorney 
 
 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff 
to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of 
Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of 
information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. 
CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United 
States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, 
as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the 
permission of the copyright holder if you wish to copy or otherwise use copyrighted material. 
 
LSB10457 · VERSION 5 · UPDATED