

 
 Legal Sidebari 
 
COVID-19 Pandemic’s Effect on Government 
Contracts 
March 24, 2020 
The COVID-19 pandemic and related mandates and recommendations to practice social distancing, work 
from home, shelter in place, and self-quarantine impact government contracts by disrupting supply chains 
and business operations. These disruptions may make it difficult and potentially impossible for some 
federal contractors to perform government procurement contracts as originally contemplated. Disruptions 
will likely alter government procurement priorities and have prompted questions about how the novel 
COVID-19 pandemic might affect federal acquisitions and government contractor performance. The 
pandemic’s effect on existing federal contracts will depend in large part upon agency needs, the duration 
of pandemic response actions, and each contract’s type and terms. Legal principles underlying standard 
contract clauses that often must be incorporated in procurement contracts under the Federal Acquisition 
Regulation (FAR) and agency-specific FAR supplements like the Department of Defense’s (DoD’s) 
Defense Federal Acquisition Regulation Supplement (DFARS) will likely guide how agencies and 
contractors respond to the pandemic. Additionally, federal emergency response laws, such as the Robert T. 
Stafford Disaster Relief and Emergency Assistance Act (Stafford Act) and the Defense Production Act of 
1950 (DPA), could impact how agencies acquire goods and services to respond to the COVID-19 
outbreak. 
OMB Guidance on Contract Performance 
On March 20, the Office of Management and Budget (OMB) issued guidance on “steps to help ensure [] 
safety while maintaining continued contract performance in support of agency missions, wherever 
possible and consistent with [public health] precautions.” Although contractors establish many of their 
own workplace standards, the guidance recommends that agencies “work with their contractors . . . to 
evaluate and maximize telework for contractor employees, wherever possible.” It also encourages 
agencies to be flexible when administering contracts by providing extensions on deadlines when 
necessary because of “COVID-19 related interruptions.” The guidance also notes that agencies should 
evaluate “whether it is beneficial to keep skilled professionals or key personnel in a mobile ready state for 
activities the agency deems critical to national security or other high priorities.” Finally, the guidance 
urges agencies, when appropriate, to use procurement law flexibilities triggered when the President 
declared the COVID-19 outbreak an emergency under the Stafford Act.   
Congressional Research Service 
https://crsreports.congress.gov 
LSB10428 
CRS Legal Sidebar 
Prepared for Members and  
 Committees of Congress 
 
  
 
Congressional Research Service 
2 
Under some circumstances, an agency can use more streamlined procurement procedures, called 
“simplified acquisition procedures,” for small-dollar purchases. The thresholds for simplified acquisition 
procedures are higher for procurements that support a federally declared major disaster or emergency. 
Additionally, the Competition in Contracting Act of 1984 (CICA) permits agencies to make sole-source 
(i.e., noncompetitive) awards when justified, including when the need for the service or good is of such an 
“unusual and compelling urgency” that the government potentially could suffer serious harm if it 
followed typical competition procedures. Agency acquisitions in response to the COVID-19 pandemic 
might trigger circumstances that justify sole-source awards.  
Legal Mechanisms to Address COVID-19-Related Performance 
Several standard federal procurement contract provisions provide processes by which the government and 
contractors can adapt to COVID-19-related unexpected circumstances. The clauses include Excusable 
Delay provisions, Changes clauses, Stop-Work Order provisions, Termination for Convenience clauses, 
and Continuation of Essential Contractor Services provisions. Use of these clauses could affect the cost 
and timing of contract performance. 
Excusable Delays 
The FAR requires that many federal contracts include an Excusable Delay contract provision. This 
provision provides contractors protections from default liability for delays triggered by events outside a 
contractor’s or contracting agency’s control. Triggering events can include “acts of God,” “unusually 
severe weather,” as well as “epidemics” and “quarantine restrictions.” This clause potentially could 
authorize contractors who cannot perform work on time because of the COVID-19 pandemic more time 
to complete performance without suffering contractual consequences (such as payment of liquidated 
damages). While some contractors might receive schedule relief (i.e., more time to perform) under this 
clause, it likely would not authorize additional compensation, even if the COVID-19 pandemic increases 
contract costs. However, other contract provisions potentially could allow COVID-19-related cost relief, 
under other contract clauses described below. 
Changes Clauses 
Federal procurement contracts generally must include some variation of a Changes clause. These clauses 
authorize contracting officers to enter into a change order to address changed realities that were not 
contemplated at contract consummation. In some cases, the parties can negotiate an “equitable 
adjustment” to account for reasonable increases or decreases in costs associated with such changes, when 
warranted. Depending on the facts and circumstances, some contracts might need to be performed during 
the COVID-19 pandemic, while other contracts could be curtailed or terminated.  
The Department of Homeland Security’s Cybersecurity and Infrastructure Security Agency, for example, 
issued guidance identifying essential critical infrastructure contractors that are “needed to maintain the 
services and functions Americans depend on daily and that need to be able to operate resiliently during 
the COVID-19 pandemic response.” The guidance identifies essential operations in several industries, 
including healthcare, public health, communications, information technology, and law enforcement. If a 
contract is performed but is subject to COVID-19-related adjustments, those adjustments might justify 
reasonable cost increases or schedule relief under a Changes clause. For example, if a contractor must 
comply with new, agency-mandated COVID-19 security and sanitation protocols, the contractor might be 
able to recover the reasonable cost increases of following the heightened standards.  
In other instances, the pandemic could reduce the government’s need for supplies or services. These 
circumstances might warrant a reduction in contractor compensation. For example, if virtually all 
employees that would normally work in a building are working remotely because of COVID-19’s health 
  
Congressional Research Service 
3 
risks, it may be unnecessary and contrary to the health-based telework policy for contractors to perform 
non-essential administrative services in federal buildings during the COVID-19 pandemic. Similarly, an 
agency might not need the same quantity of supplies originally contemplated with the bulk of its 
employees working remotely. This could prompt agencies, unilaterally or through negotiations, to execute 
changes to contracts to reflect the reduced need for supplies and services, along with reduced costs 
commensurate with those changes.  
Stop-Work Orders 
In some cases, an agency might order a contractor to suspend or delay performance on a specific contract 
under a Stop-Work Order clause. These clauses, which are required in certain non-construction contracts, 
permit agency personnel to order a contractor to “stop all, or any part, of the work called for by this 
contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to 
which the parties may agree.” When Stop-Work Order clauses are triggered, contractors generally have a 
right to an “equitable adjustment” of the contract to receive reasonable costs associated with halting and 
restarting the contract. When implementing stop-work orders, contractors also are generally required to 
“take all reasonable steps to minimize the incurrence of costs” to the government, which could force 
contractors to reassign employees to other projects, place employees on unpaid leave, or terminate 
employees, at least temporarily.  
Termination for Convenience  
Contracting officers, in some cases, can exercise the right to terminate a contract for the government’s 
convenience. For example, a commonly required Termination for Convenience clause states, in its 
entirety:  
The Contracting Officer, by written notice, may terminate this contract, in whole or in part, when it 
is in the Government's interest. If this contract is terminated, the Government shall be liable only 
for payment under the payment provisions of this contract for services rendered before the effective 
date of termination. 
After terminating for convenience, the government is generally only required to pay for work performed 
before the termination.  
Continuation of Contractor Services to DoD 
The COVID-19 pandemic also could trigger contractor responsibilities under a Continuation of Essential 
Contractor Services clause included in certain DoD contracts. The clause generally requires contractors 
that perform an essential contractor service or mission-essential functions for DoD to execute plans to 
continue providing those services, “during periods of crisis,” which potentially could include the COVID-
19 pandemic. The clause defines “essential contractor service” as a “service provided by a firm or 
individual under contract to DoD to support mission-essential functions, such as support of vital 
systems.” Under the clause, “[s]ervices are essential if the effectiveness of defense systems or operations 
has the potential to be seriously impaired by the interruption of these services.” The clause defines 
mission-essential functions as “those organizational activities that must be performed under all 
circumstances to achieve DoD component missions or responsibilities.” A contractor that may not be able 
to continue performance of these essential functions must inform agency personnel “as expeditiously as 
possible and use its best efforts to cooperate with the Government in the Government’s efforts to maintain 
the continuity of operations.” The DFARS authorizes the parties to make reasonable cost adjustments to 
the contract to account for any increase or decrease in “costs incurred in continuing performance of 
essential services in a crisis situation.” 
  
Congressional Research Service 
4 
 
Defense Production Act 
On Wednesday, March 18, the President issued an executive order (EO) delegating certain powers under 
the DPA to account for the national security concerns posed by the COVID-19 outbreak. The DPA 
authorizes the federal government to mobilize private industry to provide the government with various 
supplies and services necessary to support the national defense. The law defines the term national defense 
to cover various military activities, “homeland security, stockpiling, space, and any directly related 
activity,” including public health emergency preparedness activities under the Stafford Act. The DPA 
authorizes the President, among other things, to require private businesses to accept and prioritize federal 
government procurement contracts and to incentivize private industry to produce goods and materials 
needed to support the national defense, through purchase commitments, loans, loan guarantees, and other 
mechanisms.  
In the DPA EO, the President delegated certain DPA authorities to the Secretary of Health and Human 
Services (HHS), in consultation with other agency heads, to establish “the proper nationwide priorities 
and allocation of all health and medical resources, including controlling the distribution of such materials 
(including applicable services) in the civilian market, for responding to the spread of COVID-19 within 
the United States.” Observers have discussed the potential that the HHS Secretary could exercise this 
delegated DPA authority to enter into contracts with private businesses to acquire medical supplies used in 
treating COVID-19 patients that reportedly are in short supply in the United States. Additional CRS 
products on the DPA are available in this CRS Report, Insight, and Legal Sidebar. 
 
Author Information 
 
David H. Carpenter 
   
Legislative Attorney 
 
 
 
 
Disclaimer 
This document was prepared by the Congressional Research Service (CRS). CRS serves as nonpartisan shared staff 
to congressional committees and Members of Congress. It operates solely at the behest of and under the direction of 
Congress. Information in a CRS Report should not be relied upon for purposes other than public understanding of 
information that has been provided by CRS to Members of Congress in connection with CRS’s institutional role. 
CRS Reports, as a work of the United States Government, are not subject to copyright protection in the United 
States. Any CRS Report may be reproduced and distributed in its entirety without permission from CRS. However, 
as a CRS Report may include copyrighted images or material from a third party, you may need to obtain the 
permission of the copyright holder if you wish to copy or otherwise use copyrighted material. 
 
LSB10428 · VERSION 1 · NEW