Navy Frigate (FFG[X]) Program: Background and Issues for Congress

December 8, 2017 (R44972)
Jump to Main Text of Report

Contents

Figures

Tables

Appendixes

Summary

As part of its FY2018 budget submission, the Navy has initiated a new program, called the FFG(X) program, to build a new class of 20 guided-missile frigates (FFGs). The Navy wants to procure the first FFG(X) in FY2020, the second in FY2021, and the remaining 18 at a rate of two per year in FY2022-FY2030. Given current Navy force-structure goals, the Navy wants to procure a notional total of 20 FFG(X)s. The Navy's proposed FY2018 budget requests $143.5 million in research and development funding for the program.

U.S. Navy frigates are smaller, less capable, and less expensive to procure and operate than U.S. Navy destroyers and cruisers. In contrast to cruisers and destroyers, which are designed to operate in higher-threat areas, frigates are generally intended to operate more in lower-threat areas. The Navy envisages the FFG(X) as a multimission ship capable of conducting anti-air warfare (aka air defense) operations, anti-surface warfare operations (meaning operations against enemy surface ships and craft), antisubmarine warfare operations, and electromagnetic maneuver warfare (EMW) operations. (EMW is a new term for electronic warfare.)

Although the Navy has not yet determined the design of the FFG(X), given the desired capabilities just mentioned, the ship will likely be larger in terms of displacement, more heavily armed, and more expensive to procure than the Navy's Littoral Combat Ships (LCSs). The Navy envisages developing no new technologies or systems for the FFG(X)—the ship is to use systems and technologies that already exist or are already being developed for use in other programs.

The Navy's desire to procure the first FFG(X) in FY2020 does not allow enough time to develop a completely new design (i.e., a clean-sheet design) for the FFG(X). (Using a clean-sheet design might defer the procurement of the first ship to about FY2023.) Consequently, the Navy intends to build the FFG(X) to a modified version of an existing ship design—an approach called the parent-design approach. The parent design could be a U.S. ship design or a foreign ship design. The Navy intends to conduct a full and open competition to select the builder of the FFG(X), including proposals based on either U.S. or foreign ship designs. Given the currently envisaged procurement rate of two ships per year, the Navy envisages using a single builder to build the ships.

The FFG(X) program presents several potential oversight issues for Congress, including the following:


Navy Frigate (FFG[X]) Program: Background and Issues for Congress

Introduction

This report provides background information and discusses potential issues for Congress regarding the Navy's FFG(X) program, a program to procure a new class of 20 guided-missile frigates (FFGs). The FFG(X) program was initiated as part of the Navy's FY2018 budget submission. The Navy wants to procure the first FFG(X) in FY2020. The Navy's proposed FY2018 budget requests $143.5 million in research and development funding for the program.

The FFG(X) program presents several potential oversight issues for Congress. Congress's decisions on the program could affect Navy capabilities and funding requirements and the shipbuilding industrial base.

This report focuses on the FFG(X) program. A related Navy shipbuilding program, the Littoral Combat Ship (LCS) program, is covered in a separate CRS report.1 Other CRS reports discuss the strategic context within which the FFG(X) program and other Navy acquisition programs may be considered.2

Background

U.S. Navy Surface Combatants in General

U.S. Navy surface combatants are multimission ships equipped to conduct various peacetime and wartime missions. The Navy's large surface combatants include guided-missile cruisers (CGs) and guided-missile destroyers (DDGs).3 The Navy's small surface combatants include patrol craft, mine warfare ships,4 Littoral Combat Ships (LCSs), and frigates.5 LCSs might be thought of as light frigates (FFLs) or corvettes, which are terms used to refer to ships that are bigger than patrol craft and smaller than frigates.

U.S. Navy Frigates in General

U.S. Navy frigates are smaller, less capable, and less expensive to procure and operate than U.S. Navy destroyers and cruisers. In contrast to cruisers and destroyers, which are designed to operate in higher-threat areas, frigates are generally intended to operate more in lower-threat areas. U.S. Navy frigates perform many of the same peacetime and wartime missions as U.S. Navy cruisers and destroyers, but since frigates are intended to do so in lower-threat areas, they are equipped with fewer weapons, less-capable radars and other systems, and less engineering redundancy and survivability than cruisers and destroyers.

Compared to cruisers and destroyers, frigates can be a more cost-effective way to perform missions that do not require the use of a higher-cost cruiser or destroyer. In the past, the Navy's combined force of higher-capability, higher-cost cruisers and destroyers and lower-capability, lower-cost frigates has been referred to as an example of a so-called high-low force mix. High-low mixes have been used by the Navy and the other military services in recent decades as a means of balancing desires for individual platform capability against desires for platform numbers in a context of varied missions and finite resources.

Peacetime missions performed by frigates can include, among other things, engagement with allied and partner navies, maritime security operations (such as anti-piracy operations), and humanitarian assistance and disaster response (HA/DR) operations. Intended wartime operations of frigates include escorting (i.e., protecting) military supply and transport ships and civilian cargo ships that are moving through potentially dangerous waters. In support of intended wartime operations, frigates are designed to conduct anti-air warfare (AAW—aka air defense) operations, anti-surface warfare (ASuW) operations (meaning operations against enemy surface ships and craft), and antisubmarine warfare (ASW) operations. U.S. Navy frigates are designed to operate in larger Navy formations or as solitary ships. Operations as solitary ships can include the peacetime operations mentioned above.

The most recent class of frigates operated by the Navy was the Oliver Hazard Perry (FFG-7) class (Figure 1). A total of 51 FFG-7 class ships were procured between FY1973 and FY1984. The ships entered service between 1977 and 1989, and were decommissioned between 1994 and 2015.6 In their final configuration, the ships were about 455 feet long and had full load displacements of roughly 3,900 tons to 4,100 tons. (By comparison, the Navy's Arleigh Burke [DDG-51] class destroyers are about 510 feet long and have full load displacements of roughly 9,300 tons.)7 Following their decommissioning, a number of FFG-7 class ships, like certain other decommissioned U.S. Navy ships, have been transferred to the navies of U.S. allied and partner countries.

Small Surface Combatant Force Level

Force-Level Goal

The U.S. Navy's force-level goal, released in December 2016, calls for achieving and maintaining a fleet of 355 ships, including 104 large surface combatants (i.e., cruisers and destroyers) and 52 small surface combatants.8 Although patrol craft are small surface combatants, the 52-ship force-level goal for small surface combatants refers specifically to the total number of frigates, LCSs, and mine warfare ships, excluding patrol craft.9

Figure 1. Oliver Hazard Perry (FFG-7) Class Frigate

Source: Photograph accompanying Dave Werner, "Fighting Forward: Last Oliver Perry Class Frigate Deployment," Navy Live, January 5, 2015, accessed September 21, 2017, at http://navylive.dodlive.mil/2015/01/05/fighting-forward-last-oliver-perry-class-frigate-deployment/.

Current Force Level

Following the decommissioning of the FFG-7 class ships, the Navy's inventory of small surface combatants has been well below the 52-ship force-level goal for small surface combatants. At the end of FY2017, the Navy had 24 small surface combatants, including 13 LCSs, 11 mine warfare ships, and no frigates. At the end of FY2018, the Navy projects it will have 28 small surface combatants, including 17 LCSs, 11 mine warfare ships, and no frigates. In FY2019 and subsequent years, the number of LCSs is to continue to grow toward a total of about 32, and the mine warfare ships are to be decommissioned.

Navy FFG(X) Program10

Meaning of Designation FFG(X)

In the program designation FFG(X), FF means frigate,11 G means guided-missile ship (indicating a ship equipped with an area-defense AAW system),12 and (X) indicates that the design of the ship has not yet been determined. FFG(X) thus means a guided-missile frigate whose design has not yet been determined.13

Program Origin

The FFG(X) program can be viewed as an outgrowth of the LCS program, as follows:

At a May 3, 2017, hearing on the LCS and FFG(X) programs before the Seapower and Projection Forces subcommittee of the House Armed Services Committee, the Navy testified that

As maritime threats have evolved, the Navy is placing greater emphasis on distributed operations, highlighting the need for a full complement of SSCs [small surface combatants] and increasing the need for a Frigate with improved lethality and survivability. The Navy is defining the requirements for the Frigate to improve its ability to operate in a more contested environment than LCS, enhancing its role in distributed maritime operations. In this role, both LCS and Frigate will free up our large surface combatants to focus on their primary missions including area air defense, land strike, and ballistic missile defense. The Navy is also seeking to leverage Fleet-wide commonality of combat system elements wherever possible to deliver capability and flexibility in the most cost effective manner.

To accomplish this, the Navy has established a Frigate Requirement Evaluation Team to update the previous Frigate analysis performed in 2014 and investigate the feasibility of incorporating additional capabilities and enhanced survivability features into the current Frigate designs, as well as explore other hull forms. The results of this analysis will inform the top level Frigate requirements based on cost and capability trades involved. The Navy's revised acquisition strategy is under development and will ensure designs are mature prior to entering into a detail design and construction (DD&C) contract. The Navy will engage with industry in order to support an aggressive conceptual design effort, leading to a Request for Proposals to award the DD&C contract in FY 2020.

As we work through the requirements and acquisition processes for the Frigate, we will endeavor to transition from LCS to Frigate in a manner that maximizes the competitive field for our shipbuilding industrial base. We understand the potential implications of future acquisition strategies to our shipyards and their workforces, and these are considerations we do not take lightly. We are committed to delivering increased capability to our sailors at the best value for the American taxpayer, and that includes maintaining a competitive and healthy industrial base.14

In its FY2018 budget submission, the Navy states the following:

As directed by the Secretary of Defense (SECDEF) in 2014, the Navy via the Small Surface Combatant Task Force (SSCTF) reviewed the capabilities of Littoral Combat Ship (LCS) and explored alternatives to provide a more lethal and survivable ship to meet future missions. The SSCTF recommendations served as the foundation for the revised requirements for the modified LCS (designated as the Frigate (FF)) and an award no later than FY2019. Previous budgets and schedules supported the plan to develop the FF.

As a result of the Navy's 2016 Force Structure Assessment and to address increasingly complex threats in the global maritime environment, the Navy is reassessing the capabilities required to ensure the Frigate paces future threats. The Navy desires to maximize the capability of the future Guided Missile Frigate (FFG(X)) in antisurface warfare (SUW), anti-submarine warfare (ASW) and local air defense (LAD) mission areas, while keeping the ship affordable and part of a "high-low" mix of surface combatants. Our updated assessment will be completed to support finalization of FFG(X) requirements by Spring 2017.15

Program Quantity

A total of 29 LCSs have been procured through FY2017. The Navy's FY2018 budget submission, as amended, requests two more LCSs in FY2018 and projects a request for one final LCS in FY2019. Funding those three ships in FY2018 and FY2019 would make for a total of 32 LCSs. The Navy wants to procure a notional total of 20 FFG(X)s, which in combination with 32 LCSs would meet the Navy's 52-ship force-level goal for small surface combatants.

Procurement Schedule

Following a final year of LCS procurement in FY2019, wants to procure the first FFG(X) in FY2020, the second in FY2021, and the remaining 18 at a rate of two per year in FY2022-FY2030.

Ship Capabilities and Design

As mentioned above, the (X) in the program designation FFG(X) means that the design of the ship has not yet been determined. In general, the Navy envisages the FFG(X) as follows:

Given the above, the FFG(X) design will likely be larger in terms of displacement, more heavily armed, and more expensive to procure than either the LCS or the FF concept that emerged from the February 2014 LCS program restructuring.

A November 2, 2017, Navy information paper on the combat system to be used by the FFG(X) states the following:

In considering multiple options (Lockheed Martin's COMBATSS-21, General Dynamics' Integrated Combat Management System, and Raytheon's Ship Self Defense System) for the Frigate's Combat Management System (CMS), the following criteria were analyzed:

--Commonality—the degree to which the CMS was common across variants of LCS and the rest of the Navy.

--Performance—demonstrated ability to deliver a certifiable CMS able to meet LCS requirements, with respect to mission area capabilities.

--Cost—the total cost to design, develop, deliver, test and sustain the CMS.

A derivation of the AEGIS combat system widely used throughout the Navy and half of the LCS platforms, the Navy selected COMBATSS-21 as the Frigate CMS. It offered the highest level of commonality, best performance, and lowest cost of the three options.

Similar to the original FF, the primary mission areas for the FFG(X) will be Anti-Submarine Warfare, Surface Warfare, and Electromagnetic Maneuver Warfare. In addition, the FFG(X) will provide upgraded Air Warfare capability and improved lethality and survivability that include a scaled SPY-6 Fixed Array Radar, Standard Missile, Evolved Sea Sparrow Missile, full Surface Electronic Warfare Improvement Program Block 2 capability, and a Cooperative Engagement Capability. The CMS capabilities required to bring these enhancements are already included in Aegis; and thus, they are much simpler to cost effectively incorporate into COMBATSS-21.16

Target Unit Procurement Cost

Follow-On Ships

The Navy wants the follow-on ships in the FFG(X) program (i.e., ships 2 through 20) to have an average unit procurement cost of not more than $950 million each in constant 2018 dollars.17 By way of comparison, the two LCSs that the Navy has requested for FY2018 have an estimated average unit procurement cost of about $568 million each, and the two DDG-51 class destroyers that the Navy has requested for FY2018 have an estimated average unit procurement cost of about $1,750 million each.

On July 10, 2017, the Navy released a Request for Information (RFI) to industry to solicit information for better understanding potential trade-offs between cost and capability in the FFG(X) design.18 On July 25, the Navy continued that effort by holding an industry day event. On July 28, the Navy posted its briefing slides for that event; some of those slides are reprinted in the Appendix.19 Responses to the RFI were due by August 24, 2017. The Navy states that it "received a very robust response to the FFG(X) RFI inclusive of [i.e., including] domestic and foreign ship designs and material vendor solutions."20 The Navy folded information gained through that RFI into its determination of the target unit procurement cost for the FFG(X).

Lead Ship

The Navy has not yet established a target unit procurement cost for the lead ship in the program. The lead ship will be considerably more expensive than the follow-on ships in the program, because the lead ship's procurement cost will incorporate most or all of the detailed design/nonrecurring engineering (DD/NRE) costs for the class. (It is a traditional Navy budgeting practice to attach most or all of the DD/NRE costs for a new ship class to the procurement cost of the lead ship in the class.)

Acquisition Strategy

Parent-Design Approach

The Navy's desire to procure the first FFG(X) in FY2020 does not allow enough time to develop a completely new design (i.e., a clean-sheet design) for the FFG(X). (Using a clean-sheet design might defer the procurement of the first ship to about FY2023.) Consequently, the Navy intends to build the FFG(X) to a modified version of an existing ship design—an approach called the parent-design approach. The parent design could be a U.S. ship design or a foreign ship design.21

Using the parent-design approach can reduce design time and design cost, and can also reduce technical, schedule, and cost risk in building the ship. The Coast Guard and the Navy are currently using the parent-design approach for the Coast Guard's polar icebreaker program.22 The parent-design approach has also been used in the past for other Navy and Coast Guard ships, including Navy mine warfare ships23 and the Coast Guard's new Fast Response Cutters (FRCs).24

No New Technologies or Systems

As an additional measure for reducing technical, schedule, and cost risk in the FFG(X) program, the Navy envisages developing no new technologies or systems for the FFG(X)—the ship is to use systems and technologies that already exist or are already being developed for use in other programs.

Full and Open Competition

The Navy intends to conduct a full and open competition to select the builder of the FFG(X), including proposals based on either U.S. or foreign ship designs. The Navy wants to award multiple conceptual design contracts for the program in FY2018—a November 3, 2017, press report states that the Navy expects to award up to five contracts25—and a detailed design and construction (DD&C) contract for the program in FY2020. Being a recipient of a conceptual design contract is not a requirement for competing for the DD&C contract.

On November 7, 2017, the Navy issued a Request for Proposals (RFP) for the conceptual design contracts. Responses to the RFP are due by December 18, 2017. On October 16, 2017, the Navy posted a presolicitation notice for this RFP that stated the following:

The Naval Sea Systems Command (NAVSEA) intends to issue a full and open competitive solicitation in November 2017 for design development activities to address technical solutions for the Guided Missile Frigate (FFG(X)). The overall objective of this early industry involvement is to enable the Government to reduce FFG(X) risk by maturing industry designs to meet the FFG(X) capability. The Government intends to award multiple contracts resulting from this solicitation....

The competitive solicitation intended for release in November 2017 will provide for Conceptual Design (CD) in accordance with the Government developed FFG(X) System Specification.... All future FFG(X) ship construction shall be conducted in a U.S. shipyard. In order to be eligible for CD, offerors must have a parent design from which to start. A parent design is defined as a design of a ship that has been through production and demonstrated (full scale) at sea. Offerors will only be allowed to submit one proposal as a prime contractor, and each prime contractor will only be eligible for a single award. However, offerors may be subcontractors under a prime in multiple proposals.

On October 20, 2017, the Navy posted an update to the notice stating the following:

The purpose of this update is to provide clarification with respect to the parent design definition and prime contractor requirements noted within the original synopsis posting as follows:

The parent design, from which an offeror's FFG(X) solution would be developed, must have been constructed and demonstrated at sea. A "clean sheet", "paper", or developmental parent design would not qualify under this definition and would not be accepted for consideration under the Conceptual Design solicitation.

There is no requirement for the prime contractor to be a US shipyard for purposes of Conceptual Design. A US shipyard may participate as a part of multiple teams consistent with the prime and subcontractor restrictions outlined within the original synopsis.26

Builder

Given the currently envisaged procurement rate of two ships per year, the Navy envisages using a single builder to build the ships. Consistent with U.S. law,27 the ship is to be built in a U.S. shipyard, even if it is based on a foreign design. Using a foreign design might thus involve cooperation or a teaming arrangement between a U.S. builder and a foreign developer of the parent design.

Block Buy Contracting

As a means of reducing their procurement cost, the Navy envisages using one or more fixed-price block buy contracts to procure the ships.28

Program Funding

Table 1 shows funding for the FFG(X) program under the Navy's FY2018 budget submission. Figures for FY2019 and subsequent years, particularly for procurement costs, are nominal placeholder figures pending the determination of the design of the FFG(X), and are thus subject to change in future Navy budget submissions. The figures shown in Table 1 may not reflect the target unit procurement cost that the Navy has established for the FFG(X) program.

Table 1. FFG(X) Program Funding

Millions of then-year dollars, rounded to nearest tenth.

 

FY16

FY17

FY18

FY19

FY20

FY21

FY22

Research and development

29.0

84.9

143.5

141.6

73.4

76.5

71.1

Procurement

0

0

0

655.0

1,201.1

1,155.0

2,061.2

(Procurement quantity)

 

 

 

 

(1)

(1)

(2)

TOTAL

29.0

84.9

143.5

796.6

1,274.5

1,231,5

2,132.3

Source: Navy briefing on FFG(X) program given to CRS and the Congressional Budget Office (CBO) on September 20, 2017.

Notes: Research and development funding is located in PE (Program Element) 0603599N, Frigate Development (Navy research and development account line 57 in the FY2018 budget submission), and additionally (for FY2016 only), PE 0603581, Littoral Combat Ship.

Issues for Congress

FY2018 Funding Request

One potential oversight issue for Congress is whether to approve, reject, or modify the Navy's FY2018 funding request for the program. In assessing this question, Congress may consider, among other things, whether the work the Navy is proposing to do in the program in FY2018 is appropriate, and whether the Navy has accurately priced that work.

Analytical Basis for Capability Gaps/Mission Needs

Another potential oversight issue for Congress is whether the Navy has accurately identified the capability gaps and mission needs to be addressed by the program, particularly in light of recent changes in the international security environment and debate over the future U.S. role in the world,29 and whether the Navy has performed a formal, rigorous analysis of this issue, as opposed to relying solely on the subjective judgments of Navy and DOD leaders.

Subjective judgments can be helpful, particularly in terms of capturing knowledge and experience that is not easily reduced to numbers, in taking advantage of the "wisdom of the crowd," and in coming to conclusions and making decisions quickly. On the other hand, a process that relies heavily on subjective judgments can be vulnerable to groupthink (i.e., a situation in which a group acts in a way that discourages creativity or individual responsibility), can overlook counterintuitive results regarding capability gaps and mission needs (i.e., results that go against the conventional wisdom), and, depending on the leaders involved, can emphasize those leaders' understanding of the Navy's needs in the nearer term, as opposed to what a formal intelligence projection of future adversary capabilities—such as those used in formal, rigorous analyses—might indicate what the Navy will need years from now, when the new ships will actually be in the fleet.

A December 4, 2017, press report states:

Rear Adm. Ron Boxall [the Navy's director of surface warfare] told USNI News today at the American Society of Naval Engineers' annual Combat Systems Symposium that the 60-day effort by the FFG Requirements Evaluation Team helped each stakeholder understand how their needs interacted with others' to affect cost, schedule, operational effectiveness and more..

"I was very pleased with where we came out because some of the decisions were much more about the concept of what we're getting instead of the actual platform we're getting," Boxall told USNI News during a question and answer period after his remarks....

... Boxall said the process the 60-day requirements evaluation teams have used is also very exciting for the requirements community. In some past cases, such as the CG(X) next-generation cruiser, requirements officers have spent years on a program, only to have it ultimately canceled.30 With this new process that brings together all stakeholders right at the start, along with computer tools that allow them to generate numerous iterations of a ship design, the Navy can work through a program's requirements much faster and come up with a more mature and technologically informed set of requirements.

"What's exciting about this [is] we're starting to create a repository of knowledge that we can use to reiterate as we need to go along," he told USNI News after the event.

"We've not done a good job of doing that in the past, it's was kind of resident in the requirements officers and the acquisition team; now we're actually doing it with the models—here's what this combination of capabilities proves to get to us, and as we learn things or technology improves or costs more or less, we can make adjustments a lot more quickly."

Asked about applying this methodology to more programs, like the Future Surface Combatant family of systems that followed the canceled CG(X), Boxall said those discussions have already begun.

"We actually took some of the work we're doing with Future Surface Combatant and brought that back (to the FFG Requirements Evaluation Team); we said hey, the Future Surface Combatant is about where we're going with the whole family of ships, so if we're going to be producing an FFG of the future that's going to be kind of at the small surface combatant size, then we don't want that to be disconnected," he said. And moving forward with the large, small and unmanned surface combatants the Navy is considering for the Future Surface Combatant family, Boxall said the designs that have already been iterated can be used as a good starting point for future efforts.31

A December 5, 2017, press report, reporting on the same symposium, stated:

The Navy is convening a team similar to one used to help create the guided-missile future frigate FFG(X) to also alter the direction of the Zumwalt-class [DDG-1000] destroyers, Rear Adm. Ronald Boxall, director of Surface Warfare, said here at the 2017 Combat Systems Symposium organized by the American Society of Naval Engineers (ASNE)....

When working out new frigate requirements, the Navy looked to see what capabilities they could take from its predecessor, the Littoral Combat Ship (LCS) to help make it ready to be on contract by fiscal year (FY) 2020. He said that process involved meetings involving officials in the Navy's requirements, acquisition, and fleet teams.

Personnel "learned why they were stupid" from the perspective of the other components, he said. Each component thought the other made serious mistakes, but also learned what those teams thought of them.

Boxall said the fleet personnel would say what the warfighters need to accomplish a certain mission, the acquisition teams would draw up what they asked for and more, "then the price goes through the roof."

He said to resolve the high price versus requirements problems there has to be a voice of "hey, I want that but it's really expensive. And you say, well, here's where we can get 'tastes great and less filling'" to balance priorities and price.

Boxall said he was very pleased with the decisions the Navy made going into the FFG(X) requirements and now they decided to try it again with the Zumwalt-class.32

Analytical Basis for Addressing Capability Gaps/Mission Needs with an FFG

Another potential oversight issue for Congress is whether procuring a new class of FFGs is the best or most promising general approach for addressing the identified capability gaps and mission needs, and whether the Navy has performed a formal, rigorous analysis of this issue, as opposed to relying solely on subjective judgments of Navy or DOD leaders. Similar to the points made in the previous section, subjective judgments, though helpful, can overlook counterintuitive results regarding the best or most promising general approach. Potential alternative general approaches for addressing identified capability gaps and mission needs in this instance include (to cite a few possibilities) modified LCSs, FFs, destroyers, aircraft, unmanned vehicles, or some combination of these platforms.

A formal, rigorous analysis to determine the best or most promising general approach for addressing a set of capability gaps or mission needs was in the past sometimes referred to as an analysis of multiple concepts (AMC), or more generally as competing the mission. It could also be called an analysis of alternatives (AOA), though that term can also be applied to an analysis for refining the desired capabilities of the best or most promising approach that has been identified by an AMC.

As discussed in CRS reports on the LCS program over the years, the Navy did not perform a formal, rigorous analysis of this kind prior to announcing the start of the LCS program in November 2001, and this can be viewed as a root cause of much of the debate and controversy the that attended the LCS program, and of the program's ultimate restructurings in February 2014 and December 2015.33

See also the passages from the December 4 and 5, 2017, press reports that are quoted in the previous section.

Parent-Design Approach

Another potential oversight issue for Congress concerns the Navy's proposed acquisition strategy for the program, including the Navy's intent to use a parent-design approach for the program. The alternative would be to use a clean-sheet design approach, under which procurement of the FFG(X) would begin about FY2023 and procurement of LCSs might be extended through about 2022.

As mentioned earlier, using the parent-design approach can reduce design time and design cost, and can also reduce technical, schedule, and cost risk in building the ship. A clean-sheet design approach, on the other hand, might result in a design that more closely matches the Navy's desired capabilities for the FFG(X), which might make the design more cost-effective for the Navy over the long run. It might also provide more work for the U.S. ship design and engineering industrial base.

Industrial-Base Implications

Another potential oversight issue for Congress concerns the potential implications of the FFG(X) program for the U.S. shipbuilding industrial base. A key question concerns the two current LCS builders—Fincantieri/Marinette Marine of Marinette, WI, and Austal USA of Mobile, AL. Building LCSs is the primary line of business at both of these shipyards, supporting more than 1,000 manufacturing jobs at each yard (plus additional jobs at associated supplier firms located in various other U.S. locations).

Under the Navy's plan to have a single builder of FFG(X)s, and to use a parent design for the FFG(X) that may or may not be one of the current LCS designs, LCS-related workloads and employment levels at one or both of the two LCS shipyards would decline after FY2019, as the backlog of LCSs procured in FY2019 and prior fiscal years is worked down. LCS-related job losses at one or both of these two shipyards would be offset by FFG(X)-related job gains at the FFG(X) builder, which might or might not be one of the two current LCS builders.

As mentioned in the previous section, another potential industrial-base implication of the FFG(X) concerns the amount of work that the program will provide to the U.S. ship design and engineering industrial base under the Navy's parent-design approach, compared to the amount that might be provided by a clean-sheet design approach.

Potential Impact on Requirements for Cruisers and Destroyers

Another potential oversight issue for Congress is whether the initiation of the FFG(X) program has any implications for required numbers or capabilities of U.S. Navy cruisers and destroyers. The Navy's goal to achieve and maintain a force of 104 cruisers and destroyers and 52 small surface combatants was determined in 2016, and may reflect the earlier plan to procure FFs, rather than the new plan to procure more-capable FFG(X)s. If so, a question might arise as to whether the new plan to procure FFG(X)s would permit a reduction in the required number of cruisers and destroyers, or in the required capabilities of those cruisers and destroyers.

Legislative Activity for FY2018

Summary of Congressional Action on FY2018 Funding Request

Table 2 summarizes congressional action on the Navy's FY2018 funding request for the LCS program.

Table 2. Congressional Action on FY2018 FFG(X) Program Funding Request

Figures in Millions, Rounded to Nearest Tenth

 

 

Authorization

Appropriation

 

Request

HASC

SASC

Conf.

HAC

SAC

Conf.

Research and development

143.5

143.5

143.5

143.5

141.1

113.5

 

Procurement

0

0

0

0

0

0

 

Source: Table prepared by CRS based on FY2018 Navy budget submission, committee and conference reports, and explanatory statements on the FY2018 National Defense Authorization Act and the FY2018 DOD Appropriations Act.

Notes: HASC is House Armed Services Committee; SASC is Senate Armed Services Committee; HAC is House Appropriations Committee; SAC is Senate Appropriations Committee; Conf. is conference agreement. Research and development funding is located in PE (Program Element) 0603599N, Frigate Development, which is line 57 in the Navy's FY2018 research and development account.

FY2018 National Defense Authorization Act (H.R. 2810/S. 1519)

House

The House Armed Services Committee, in its report (H.Rept. 115-200 of July 6, 2017) on H.R. 2810, recommended the funding levels for the FFG(X) program shown in the HASC column of Table 2. H.Rept. 115-200 states the following:

Littoral Combat Ships capability enhancements

The committee believes that the Littoral Combat Ship and the Frigate will continue to play a critical role in the mix of warships necessary for Distributed Maritime Operations and believe the Navy should begin Frigate construction as soon as possible. To better expand Frigate capabilities, the committee notes that the Chief of Naval Operations initiated an Independent Review Team to assess Frigate requirements. The committee further notes that the Navy intends to leverage the proposed capabilities of the original Frigate program while adding: increased air warfare capability in both self-defense and escort roles; enhanced survivability; and increased electromagnetic maneuver warfare. The committee supports the Navy's intent to increase the lethality and survivability of the Frigate and further supports backfit options that will provide appropriate enhancements to the existing Littoral Combat Ships. (Page 23)

Senate

The Senate Armed Services Committee, in its report (S.Rept. 115-125 of July 10, 2017) on S. 1519, recommended the funding levels for the FFG(X) program shown in the SASC column of Table 2.

Conference

The conference report (H.Rept. 115-404 of November 9, 2017) on H.R. 2810 recommended the funding levels for the FFG(X) program shown in the authorization conference column of Table 2.

FY2018 DOD Appropriations Act (Division A of H.R. 3219/S. XXXX)

House

H.R. 3219 as reported by the House Appropriations Committee (H.Rept. 115-219 of July 13, 2017) was the FY2018 DOD Appropriations Act. H.R. 3219 as passed by the House is called the Make America Secure Appropriations Act, 2018, and includes the FY2018 DOD Appropriations Act as Division A and four other appropriations acts as Divisions B through E. The discussion below relates to Division A.

The House Appropriations Committee, in its report (H.Rept. 115-219 of July 13, 2017) on H.R. 3219, recommended the funding levels for the FFG(X) program shown in the HAC column of Table 2. The recommended reduction of $2.319 million is for "Program management support excess growth." (Page 240)

Senate

On November 21, 2017, the Senate Appropriations Committee released a Chairman's recommendation and explanatory statement for the FY2018 DOD Appropriations Act, referred to here as S. XXXX. The explanatory statement recommended the funding levels shown in the SAC column of Table 2. The recommended net reduction of $30 million includes an increase of $20 million for "Program increase: Government and industry source selection preparation" and a reduction of $50 million for "Restoring acquisition accountability: Accelerate FFG (X) program." (Page 169) The explanatory statement states:

FFG (X) Acquisition.—The fiscal year 2018 President's budget request includes $143,450,000 in Research, Development, Test and Evaluation, Navy for the conceptual design and development of the Navy's FFG (X) Frigate, a multi-mission platform designed for operation in littoral and blue water environments. The Committee understands that Frigate capabilities will include an increased air warfare capability in both self-defense and escort roles, enhanced survivability specifically focused on reduced vulnerability, and increased electromagnetic maneuver warfare capability. The Committee further understands that these capabilities were added to the Frigate program due to a changing threat environment that impacts naval concepts of operations. Therefore, the Committee is concerned that with submission of the fiscal year 2018 President's budget, the Navy changed the Littoral Combat Ship (LCS)/Frigate acquisition strategy by extending the period for Frigate conceptual design and studies and delaying the acquisition of FFG (X) Frigates by one year. Given the contested threat environment, the Committee recommends accelerating the Frigate acquisition program and recommends an increase of $20,000,000 to advance Government and industry source selection efforts in support of a competitive FFG (X) acquisition. (Pages 172-173)

Appendix. Navy Briefing Slides from July 25, 2017, FFG(X) Industry Day Event

This appendix reprints some of the briefing slides that the Navy presented at its July 25, 2017, industry day event on the FFG(X) program, which was held in association with the RFI that the Navy issued on July 25 to solicit information for better understanding potential trade-offs between cost and capability in the FFG(X) design (see "Target Unit Procurement Cost"). The reprinted slides begin on the next page.

Slides from Navy FFG(X) Industry Day Briefing

Source: Slides from briefing posted on July 28, 2017, at RFI: FFG(X) - US Navy Guided Missile Frigate Replacement Program, https://www.fbo.gov/index?s=opportunity&mode=form&tab=core&id=d089cf61f254538605cdec5438955b8e&_cview=0, accessed August 11, 2017.

Author Contact Information

[author name scrubbed], Specialist in Naval Affairs ([email address scrubbed], [phone number scrubbed])

Footnotes

1.

See CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress, by [author name scrubbed].

2.

See CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by [author name scrubbed]; CRS Report R43838, A Shift in the International Security Environment: Potential Implications for Defense—Issues for Congress, by [author name scrubbed]; and CRS Report R44891, U.S. Role in the World: Background and Issues for Congress, by [author name scrubbed] and [author name scrubbed].

3.

For more on Navy destroyers, see CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs: Background and Issues for Congress, by [author name scrubbed]. Some Navy cruisers and destroyers are equipped for ballistic missile defense (BMD) operations. For more on the BMD capabilities of Navy cruisers and destroyers, see CRS Report RL33745, Navy Aegis Ballistic Missile Defense (BMD) Program: Background and Issues for Congress, by [author name scrubbed]. The largest surface combatants are battleships; the Navy has not operated battleships since 1992.

4.

The U.S. Navy's mine warfare ships are not generally considered multimission ships—they have a singular primary mission of countering mines.

5.

The term surface combatant is sometimes applied more broadly, so as to include not only the large and small surface combatants listed here, but also aircraft carriers and amphibious warfare ships.

6.

The ships are commonly referred to as the Perry-class ships or the "fig-7s."

7.

Displacement is a measure of a ship's size—specifically, it is the amount or weight of water that would fill the volume displaced by a floating ship.

8.

For more on the Navy's 355-ship force-level goal, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by [author name scrubbed].

9.

The Navy's 355-ship force-level goal is a goal for the total number of battle force ships, which are ships that count toward the quoted size of the Navy. Patrol craft are not counted as battle force ships. For additional discussion, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by [author name scrubbed].

10.

Unless stated otherwise, this section draws on information provided by a briefing on the FFG(X) program given to CRS and the Congressional Budget Office (CBO) on September 20, 2017.

11.

The designation FF, with two Fs, means frigate in the same way that the designation DD, with two Ds, means destroyer. FF is sometimes translated less accurately as fast frigate. FFs, however, are not particularly fast by the standards of U.S. Navy combatants—their maximum sustained speed, for example, is generally lower than that of U.S. Navy aircraft carriers, cruisers, and destroyers. In addition, there is no such thing in the U.S. Navy as a slow frigate.

12.

Some U.S. Navy surface combatants are equipped with a point-defense AAW system, meaning a short-range AAW system that is designed to protect the ship itself. Other U.S. Navy surface combatants are equipped with an area-defense AAW system, meaning a longer-range AAW system that is designed to protect no only the ship itself, but other ships in the area as well. U.S. Navy surface combatants equipped with an area-defense AAW system are referred to as guided-missile ships and have a "G" in their designation.

13.

When the ship's design has been determined, the program's designation might be changed to the FFG-62 program, since FFG-61 was the final ship in the FFG-7 program. It is also possible, however, that the Navy could choose a different designation for the program at that point. Based on Navy decisions involving the Seawolf (SSN-21) class attack submarine and the Zumwalt (DDG-1000) class destroyer, other possibilities might include FFG-1000, FFG-2000, or FFG-2100. (A designation of FFG-21, however, might cause confusion, as FFG-21 was used for Flatley, an FFG-7 class ship.) A designation of FFG-62 would be consistent with traditional Navy practices for ship class designations.

14.

Statement of RADM Ron Boxall, USN, Deputy Chief of Naval Operations, Director, Surface Warfare Division, and RADM John P. Neagley, USN, Program Executive Officer, Littoral Combat Ships, before the House Committee on Armed Services Subcommittee on Seapower and Projection Forces, on Littoral Combat Ships and the Transition to Frigate Class, May 3, 2017, pp. 2-3. See also Christopher P. Cavas, "US Navy Considers a More Powerful Frigate," Defense News, April 10, 2017; Marc Selinger, "Navy Studying Adding Air Defense, Enhanced Survivability To Future Frigate," Defense Daily, April 11, 2017: 1; Sam LaGrone, "Navy Considering More Hulls for Frigate Competition, Expanding Anti-Air Capability," USNI News, April 12, 2017; Sydney J. Freedberg Jr., "LCS Frigate: Delay A Year To Study Bigger Missiles?" Breaking Defense, April 19, 2017; Sydney J. Freedberg Jr., "Beyond LCS: Navy Looks To Foreign Frigates, National Security Cutter," Breaking Defense, May 11, 2017; Megan Eckstein, "Stackley: More Capable Frigate Requires Full and Open Competition, But LCS Builders May Have Cost Advantage," USNI News, May 12, 2017.

15.

Department of the Navy, Department of Defense Fiscal Year (FY) 2018 Budget Estimates, Navy Justification Book, Volume 2 of 5, Research, Development, Test & Evaluation, Navy, Budget Activity 4, May 2017, p. 515 (PDF page 598 of 1055).

16.

Navy information paper dated November 2, 2017, provided to CRS and CBO by Navy Legislative Affairs Office on November 15, 2017.

17.

The Navy states that

The average follow threshold cost for FFG(X) has been established at $950 million (CY18$). The Navy expects that the full and open competition will provide significant downward cost pressure incentivizing industry to balance cost and capability to provide the Navy with a best value solution. FFG(X) cost estimates will be reevaluated during the Conceptual Design phase to ensure the program stays within the Navy's desired budget while achieving the desired warfighting capabilities. Lead ship unit costs will be validated at the time the Component Cost Position is established in 3rd QTR FY19 prior to the Navy awarding the Detail Design and Construction contract.

(Navy information paper dated November 7, 2017, provided by Navy Office of Legislative Affairs to CRS and CBO on November 8, 2017.)

The Navy wants the average basic construction cost (BCC) of ships 2 through 20 in the program to be $495 million per ship in constant 2018 dollars. BCC excludes costs for government furnished combat or weapon systems and change orders. (Source: Navy briefing slides for FFG(X) Industry Day, November 17, 2017, slide 11 of 16, entitled "Key Framing Assumptions.")

18.

The original notice for the RFI is posted here (accessed August 11, 2017): https://www.fbo.gov/index?s=opportunity&mode=form&id=cdf24447b8015337e910d330a87518c6&tab=core&tabmode=list&=.

19.

RFI: FFG(X) - US Navy Guided Missile Frigate Replacement Program, accessed August 11, 2017, at https://www.fbo.gov/index?s=opportunity&mode=form&tab=core&id=d089cf61f254538605cdec5438955b8e&_cview=0.

20.

Email dated September 22, 2017, from Navy Office of Legislative Affairs to CRS and CBO. For additional discussion of the RFI, the industry day event, and the Navy's preliminary concepts for the frigate, see David B. Larter, "Frigate Competition Wide Open: Navy Specs Reveal Major Design Shift," Defense News, July 10, 2017; Sydney J. Freedberg Jr., "Navy Steers Well Away From An LCS Frigate," Breaking Defense, July 10, 2017; David B. Larter, "Exclusive Interview: The Navy's Surface Warfare Director Talks Frigate Requirements," Defense News, July 11, 2017; Megan Eckstein, "Navy Hosts Guided-Missile Frigate Industry Day; Analysts Worried About Early FFG(X) Requirements," USNI News, July 27, 2017; and David B. Larter, "Experts Question the US Navy's Ideas for A New Frigate, Defense News, July 28, 2017. For earlier reports, see Christopher P. Cavas, "US Navy Considers A More Powerful Frigate, Defense News, April 10, 2017; and Sydney J. Freedberg Jr., "Beyond LCS: Navy Looks To Foreign Frigates, National Security Cutter," Breaking Defense, May 11, 2017.

21.

For articles about reported potential parent designs for the FFG(X), see, for example, Chuck Hill, "OPC Derived Frigate? Designed for the Royal Navy, Proposed for USN," Chuck Hill's CG [Coast Guard] Blog, September 15, 2017; David B. Larter, "BAE Joins Race for New US Frigate with Its Type 26 Vessel," Defense News, September 14, 2017; "BMT Venator-110 Frigate Scale Model at DSEI 2017," Navy Recognition, September 13, 2017; David B. Larter, "As the Service Looks to Fill Capabilities Gaps, the US Navy Eyes Foreign Designs," Defense News, September 1, 2017; Lee Hudson, "HII May Offer National Security Cutter for Navy Future Frigate Competition," Inside the Navy, August 7, 2017; Sydney J. Freedberg Jr., "Beyond LCS: Navy Looks To Foreign Frigates, National Security Cutter," Breaking Defense, May 11, 2017.

22.

For more on the polar icebreaker program, including the parent-design approach, see CRS Report RL34391, Coast Guard Polar Icebreaker Modernization: Background and Issues for Congress, by [author name scrubbed].

23.

The Navy's Osprey (MCM-51) class mine warfare ships are an enlarged version of the Italian Lerici-class mine warfare ships.

24.

The FRC design is based on a Dutch patrol boat design, the Damen Stan Patrol Boat 4708.

25.

Sydney J. Freedberg, Jr., "Frigate RFP Pioneers New Shipbuilding Approach," Breaking Defense, November 3, 2017.

26.

"Guided Missile Frigate (FFG(X)) Conceptual Design, Solicitation Number: N0002418R2300," October 16, 2017, updated October 20, 2017, posted at https://www.fbo.gov, accessed October 26, 2017. See also Richard Abott, "Navy To Issue FFG(X) Solicitation in November," Defense Daily, October 18, 2017.

27.

10 U.S.C. 7309 requires that, subject to a presidential waiver for the national security interest, "no vessel to be constructed for any of the armed forces, and no major component of the hull or superstructure of any such vessel, may be constructed in a foreign shipyard." In addition, the paragraph in the annual DOD appropriations act that makes appropriations for the Navy's shipbuilding account (the Shipbuilding and Conversion, Navy account) typically contains these provisos: " ... Provided further, That none of the funds provided under this heading for the construction or conversion of any naval vessel to be constructed in shipyards in the United States shall be expended in foreign facilities for the construction of major components of such vessel: Provided further, That none of the funds provided under this heading shall be used for the construction of any naval vessel in foreign shipyards.... "

28.

For more on block buy contracting, see CRS Report R41909, Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress, by [author name scrubbed] and [author name scrubbed].

29.

For additional discussion of changes in the international security environment and debate over the U.S. role in the world, see CRS Report R43838, A Shift in the International Security Environment: Potential Implications for Defense—Issues for Congress, by [author name scrubbed], and CRS Report R44891, U.S. Role in the World: Background and Issues for Congress, by [author name scrubbed] and [author name scrubbed].

30.

The CG(X) program was canceled in 2010. For more on the CG(X) cruiser program, see CRS Report RL34179, Navy CG(X) Cruiser Program: Background for Congress, by [author name scrubbed]. This report was archived in January 2011.

31.

Megan Eckstein, "New Requirements for DDG-1000 Focus on Surface Strike," USNI News, December, 4, 2017.

32.

Richard Abott, "Navy Will Focus Zumwalt On Offensive Surface Strike," Defense Daily, December 5, 2017.

33.

See, for example, the update of May 12, 2017, to CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for Congress, by [author name scrubbed], pp. 20-22.