Navy Ford (CVN-78) Class Aircraft Carrier
Program: Background and Issues for Congress

Ronald O'Rourke
Specialist in Naval Affairs
December 22, 2014
Congressional Research Service
7-5700
www.crs.gov
RS20643


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Summary
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN-
78) class of nuclear-powered aircraft carriers (CVNs).
CVN-78 was procured in FY2008. The Navy’s proposed FY2015 budget estimates the ship’s
procurement cost at $12,887.2 million (i.e., about $12.9 billion) in then-year dollars. The ship
received advance procurement funding in FY2001-FY2007 and was fully funded in FY2008-
FY2011 using congressionally authorized four-year incremental funding. The Navy did not
request any procurement funding for the ship in FY2012 and FY2013. To help cover cost growth
on the ship, the ship received an additional $588.1 million in procurement funding in FY2014,
and the Navy is requesting another $663.0 million in procurement funding for FY2015.
CVN-79 was procured in FY2013. The ship received advance procurement funding in FY2007-
FY2012, and the Navy plans to fully fund the ship in FY2013-FY2018 using congressionally
authorized six-year incremental funding. The Navy’s proposed FY2015 budget estimates CVN-
79’s procurement cost at $11,498.0 million (i.e., about $11.5 billion) in then-year dollars, and
requests $1,300 million in procurement funding for the ship.
CVN-80 is scheduled to be procured in FY2018. The Navy’s proposed FY2015 budget estimates
the ship’s procurement cost at $13,874.2 million (i.e., about $13.9 billion) in then-year dollars.
Under the Navy’s proposed FY2015 budget, the ship is to receive advance procurement funding
in FY2016-FY2017 and be fully funded in FY2018-FY2023 using congressionally authorized
six-year incremental funding.
Oversight issues for Congress for the CVN-78 program include the following:
• cost growth in the CVN-78 program;
• CVN-78 program issues that were raised in a January 2014 report from the
Department of Defense’s (DOD’s) Director of Operational Test and Evaluation
(DOT&E); and
• the potential for a two-ship block buy on CVN-79 and CVN-80.
An additional issue relating to aircraft carriers that has been raised by the Navy’s proposed
FY2015 budget concerns funding for the mid-life nuclear refueling overhaul of the aircraft carrier
George Washington (CVN-73).

Congressional Research Service

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Contents
Introduction ...................................................................................................................................... 1
Background ...................................................................................................................................... 1
The Navy’s Aircraft Carrier Force ............................................................................................. 1
Statutory Requirement to Maintain Not Less Than 11 Carriers ................................................ 1
Origin of Requirement ........................................................................................................ 1
Waiver for Period Between CVN-65 and CVN-78 ............................................................. 1
Funding and Procuring Aircraft Carriers ................................................................................... 2
Some Key Terms ................................................................................................................. 2
Incremental Funding Authority for Aircraft Carriers .......................................................... 2
Aircraft Carrier Construction Industrial Base............................................................................ 3
Gerald R. Ford (CVN-78) Class Program ................................................................................. 3
CVN-78 ............................................................................................................................... 4
CVN-79 ............................................................................................................................... 5
CVN-80 ............................................................................................................................... 5
Program Procurement Funding ........................................................................................... 5
Increases in Estimated Unit Procurement Costs Since FY2008 Budget ............................. 6
Program Procurement Cost Cap .......................................................................................... 8
Issues for Congress .......................................................................................................................... 8
Cost Growth............................................................................................................................... 8
Overview ............................................................................................................................. 8
December 2014 CBO Report .............................................................................................. 9
November 2014 GAO Report ........................................................................................... 10
Navy Response to November 2014 GAO Report ............................................................. 11
March 2014 GAO Report .................................................................................................. 13
March 2013 Navy Report to Congress (Released May 2013) ........................................... 15
May 2013 Navy Testimony ............................................................................................... 15
March 2012 Navy Letter to Senator McCain .................................................................... 17
Issues Raised in January 2014 DOT&E Report ...................................................................... 22
Potential Two-Ship Block Buy on CVN-79 and CVN-80 ....................................................... 27
Legislative Activity for FY2015 .................................................................................................... 32
FY2015 Funding Request ........................................................................................................ 32
FY2015 National Defense Authorization Act (H.R. 3979) ...................................................... 32
House ................................................................................................................................. 32
Senate ................................................................................................................................ 33
Final Version ..................................................................................................................... 36
FY2015 DOD Appropriations Act (Division C of H.R. 83/P.L. 113-235) ............................... 37
House ................................................................................................................................. 37
Senate ................................................................................................................................ 38
Final Version ..................................................................................................................... 39

Figures
Figure 1. Navy Illustration of CVN-78 ............................................................................................ 4

Congressional Research Service

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Tables
Table 1. Procurement Funding for CVNs 78, 79, and 80 Through FY2019 .................................... 6
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, and 80 ................................... 7

Appendixes
Appendix A. March 2013 Navy Report to Congress on Construction Plan for CVN-79 .............. 40
Appendix B. Refueling Complex Overhaul (RCOH) for George Washington (CVN-73) ............. 58

Contacts
Author Contact Information........................................................................................................... 62

Congressional Research Service

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Introduction
This report provides background information and potential oversight issues for Congress on the
Gerald R. Ford (CVN-78) class aircraft carrier program. Congress’s decisions on the CVN-78
program could substantially affect Navy capabilities and funding requirements and the
shipbuilding industrial base.
An additional issue relating to aircraft carriers that has been raised by the Navy’s proposed
FY2015 budget concerns funding for the mid-life nuclear refueling overhaul of the aircraft carrier
George Washington (CVN-73). This issue is discussed in Appendix B.
Background
The Navy’s Aircraft Carrier Force
The Navy’s current aircraft carrier force consists of 10 nuclear-powered Nimitz-class ships
(CVNs 68 through 77) that entered service between 1975 and 2009. Until December 2012, the
Navy’s aircraft carrier force included an 11th aircraft carrier—the one-of-a-kind nuclear-powered
Enterprise (CVN-65), which entered service in 1961. CVN-65 was inactivated on December 1,
2012, reducing the Navy’s carrier force from 11 ships to 10. The most recently commissioned
carrier, George H. W. Bush (CVN-77), the final Nimitz-class ship, was procured in FY2001 and
commissioned into service on January 10, 2009. CVN-77 replaced Kitty Hawk (CV-63), which
was the Navy’s last remaining conventionally powered carrier.1
Statutory Requirement to Maintain Not Less Than 11 Carriers
Origin of Requirement
10 U.S.C. 5062(b) requires the Navy to maintain a force of not less than 11 operational aircraft
carriers. The requirement for the Navy to maintain not less than a certain number of operational
aircraft carriers was established by Section 126 of the FY2006 National Defense Authorization
Act (H.R. 1815/P.L. 109-163 of January 6, 2006), which set the number at 12 carriers. The
requirement was changed from 12 carriers to 11 carriers by Section 1011(a) of the FY2007 John
Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006).
Waiver for Period Between CVN-65 and CVN-78
As mentioned above, the carrier force dropped from 11 ships to 10 ships when Enterprise (CVN-
65) was inactivated on December 1, 2012. The carrier force is to return to 11 ships when its
replacement, Gerald R. Ford (CVN-78), is commissioned into service. CVN-78 was originally
scheduled to be delivered in September 2015, but its construction has been running behind
schedule, and the Navy in May 2013 announced that the ship’s delivery date had been postponed

1 The Kitty Hawk was decommissioned on January 31, 2009.
Congressional Research Service
1

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

to February 2016.2 The Navy’s FY2015 budget submission shows a delivery date of March 2016.
Anticipating the gap between the inactivation of CVN-65 and the commissioning of CVN-78, the
Navy asked Congress for a temporary waiver of 10 U.S.C. 5062(b) to accommodate the period
between the two events. Section 1023 of the FY2010 National Defense Authorization Act (H.R.
2647/P.L. 111-84 of October 28, 2009) authorized the waiver, permitting the Navy to have 10
operational carriers between the inactivation of CVN-65 and the commissioning of CVN-78.
Funding and Procuring Aircraft Carriers
Some Key Terms
The Navy procures a ship (i.e., orders the ship) by awarding a full-ship construction contract to
the firm building the ship.
Part of a ship’s procurement cost might be provided through advance procurement (AP) funding.
AP funding is funding provided in one or more years prior to (i.e., in advance of) a ship’s year of
procurement. AP funding is used to pay for long-leadtime components that must be ordered ahead
of time to ensure that they will be ready in time for their scheduled installation into the ship. AP
funding is also used to pay for the design costs for a new class of ship. These design costs, known
more formally as detailed design/non-recurring engineering (DD/NRE) costs, are traditionally
incorporated into the procurement cost of the lead ship in a new class of ships.
Fully funding a ship means funding the entire procurement cost of the ship. If a ship has received
AP funding, then fully funding the ship means paying for the remaining portion of the ship’s
procurement cost.
The full funding policy is a Department of Defense (DOD) policy that normally requires items
acquired through the procurement title of the annual DOD appropriations act to be fully funded in
the year they are procured. In recent years, Congress has authorized DOD to use incremental
funding
for procuring certain Navy ships, most notably aircraft carriers. Under incremental
funding, some of the funding needed to fully fund a ship is provided in one or more years after
the year in which the ship is procured.3
Incremental Funding Authority for Aircraft Carriers
Section 121 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L.
109-364 of October 17, 2006) granted the Navy the authority to use four-year incremental
funding for CVNs 78, 79, and 80. Under this authority, the Navy could fully fund each of these
ships over a four-year period that includes the ship’s year of procurement and three subsequent
years.

2 Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for FY2014, May 2013, p. 13.
3 For more on full funding, incremental funding, and AP funding, see CRS Report RL31404, Defense Procurement:
Full Funding Policy—Background, Issues, and Options for Congress
, by Ronald O'Rourke and Stephen Daggett, and
CRS Report RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for
Congress
, by Ronald O'Rourke.
Congressional Research Service
2

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Section 124 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 112-81 of
December 31, 2011) amended Section 121 of P.L. 109-364 to grant the Navy the authority to use
five-year incremental funding for CVNs 78, 79, and 80. Since CVN-78 was fully funded in
FY2008-FY2011, the provision in practice applied to CVNs 79 and 80.
Section 121 of the FY2013 National Defense Authorization Act (H.R. 4310/P.L. 112-239 of
January 2, 2013) amended Section 121 of P.L. 109-364 to grant the Navy the authority to use six-
year incremental funding for CVNs 78, 79, and 80. Since CVN-78 was fully funded in FY2008-
FY2011, the provision in practice applies to CVNs 79 and 80.
Aircraft Carrier Construction Industrial Base
All U.S. aircraft carriers procured since FY1958 have been built by Newport News Shipbuilding
(NNS), of Newport News, VA, a shipyard that is part of Huntington Ingalls Industries (HII). NNS
is the only U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The aircraft
carrier construction industrial base also includes hundreds of subcontractors and suppliers in
various states.
Gerald R. Ford (CVN-78) Class Program
The Gerald R. Ford (CVN-78) class carrier design (Figure 1) is the successor to the Nimitz-class
carrier design.4

4 The CVN-78 class was earlier known as the CVN-21 class, which meant nuclear-powered aircraft carrier for the 21st
century.
Congressional Research Service
3




Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Figure 1. Navy Illustration of CVN-78

Source: Navy image accessed at http://www.navy.mil/management/photodb/photos/060630-N-0000X-001.jpg on
April 20, 2011.
The Ford-class design uses the basic Nimitz-class hull form but incorporates several
improvements, including features permitting the ship to generate about 25% more aircraft sorties
per day, more electrical power for supporting ship systems, and features permitting the ship to be
operated by several hundred fewer sailors than a Nimitz-class ship, significantly reducing life-
cycle operating and support (O&S) costs.
Navy plans call for procuring at least three Ford-class carriers—CVN-78, CVN-79, and CVN-80.
CVN-78
CVN-78, which was named for President Gerald R. Ford in 2007,5 was procured in FY2008. The
Navy’s proposed FY2015 budget estimates the ship’s procurement cost at $12,887.2 million (i.e.,
about $12.9 billion) in then-year dollars. Of the ship’s total procurement cost, about $3.3 billion is
for detailed design/non-recurring engineering (DD/NRE) costs for the class, and about $9.6
billion is for construction of the ship itself.

5 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of
Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced that
CVN-78 would be so named. CVN-78 and other carriers built to the same design will consequently be referred to as
Ford (CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names:
Background for Congress
, by Ronald O’Rourke.
Congressional Research Service
4

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

CVN-78 received advance procurement funding in FY2001-FY2007 and was fully funded in
FY2008-FY2011 using congressionally authorized four-year incremental funding. The Navy did
not request any procurement funding for the ship in FY2012 and FY2013. To help cover cost
growth on the ship, the ship received an additional $588.1 million in procurement funding in
FY2014, and the Navy is requesting another $663.0 million in procurement funding for FY2015.
CVN-79
CVN-79, which was named for President John F. Kennedy on May 29, 2011,6 was procured in
FY2013. The ship received advance procurement funding in FY2007-FY2012, and the Navy
plans to fully fund the ship in FY2013-FY2018 using congressionally authorized six-year
incremental funding. The Navy’s proposed FY2015 budget estimates CVN-79’s procurement cost
at $11,498.0 million (i.e., about $11.5 billion) in then-year dollars, and requests $1,300 million in
procurement funding for the ship.
CVN-80
CVN-80, which was named Enterprise on December 1, 2012,7 is scheduled to be procured in
FY2018. The Navy’s proposed FY2014 budget estimates the ship’s procurement cost at $13,874.2
million (i.e., about $13.9 billion) in then-year dollars. Under the Navy’s proposed FY2015
budget, the ship is to receive advance procurement funding in FY2016-FY2017 and be fully
funded in FY2018-FY2023 using congressionally authorized six-year incremental funding.
Program Procurement Funding
Table 1 shows procurement funding for CVNs 78, 79, and 80 through FY2018.

6 See “Navy Names Next Aircraft Carrier USS John F. Kennedy,” Navy News Service, May 29, 2011, accessed online
on June 1, 2011 at http://www.navy.mil/search/display.asp?story_id=60686. See also Peter Frost, “U.S. Navy’s Next
Aircraft Carrier Will Be Named After The Late John F. Kennedy,” Newport News Daily Press, May 30, 2011. CVN-79
is the second ship to be named for President John F. Kennedy. The first, CV-67, was the last conventionally powered
carrier procured for the Navy. CV-67 was procured in FY1963, entered service in 1968, and was decommissioned in
2007.
7 The Navy made the announcement of CVN-80’s name on the same day that it deactivated the 51-year-old aircraft
carrier CVN-65, also named Enterprise. (“Enterprise, Navy’s First Nuclear-Powered Aircraft Carrier, Inactivated,”
Navy News Service, December 1, 2012; Hugh Lessig, “Navy Retires One Enterprise, Will Welcome Another,” Newport
News Daily Press
, December 2, 2012.) CVN-65 was the eighth Navy ship named Enterprise; CVN-80 is to be the
ninth.
Congressional Research Service
5

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Table 1. Procurement Funding for CVNs 78, 79, and 80 Through FY2019
(Millions of then-year dollars, rounded to nearest tenth)
FY CVN-78
CVN-79
CVN-80
Total
FY01 21.7
(AP) 0 0
21.7
FY02 135.3
(AP) 0 0
135.3
FY03 395.5
(AP) 0 0
395.5
FY04 1,162.9
(AP) 0 0
1,162.9
FY05 623.1
(AP) 0 0
623.1
FY06 618.9
(AP) 0 0
618.9
FY07
735.8 (AP)
52.8 (AP)
0
788.6
FY08
2,685.0 (FF)
123.5 (AP)
0
2,808.6
FY09
2,684.6 (FF)
1,210.6 (AP)
0
3,895.1
FY10
737.0 (FF)
482.9 (AP)
0
1,219.9
FY11
1,712.5 (FF)
903.3 (AP)
0
2,615.8
FY12
0
554.8 (AP)
0
554.8
FY13 0
491.0
(FF)
0
491.0
FY14
588.1 (CC)
917.6 (FF)
0
1,505.7
FY15 (requested)
663.0 (CC) 1,300.0
(FF)
0
1,963.0
FY16 (projected)
124.0 (CC)
2,193.0 (FF)
683.2 (AP)
3,000.2
FY17 (projected)
0
1,245.6 (FF) 1,045.2
(AP)
2,290.8
FY18 (projected)
0
2,023.8 (FF)
825.5 (FF)
2,849.3
FY19 (projected)
0
0
1,864.5 (FF)
1,864.5
Source: Table prepared by CRS based on FY2009-FY2015 Navy budget submissions.
Notes: Figures may not add due to rounding. “AP” is advance procurement funding; “FF” is ful funding; “CC” is
cost to complete funding (i.e., funding to cover cost growth).
Increases in Estimated Unit Procurement Costs Since FY2008 Budget
Table 2 shows changes in the estimated procurement costs of CVNs 78, 79, and 80 since the
FY2008 budget submission.8

8 CBO in 2008 and the Government Accountability Office (GAO) in 2007 questioned the accuracy of the Navy’s cost
estimate for CVN-78. CBO reported in June 2008 that it estimated that CVN-78 would cost $11.2 billion in constant
FY2009 dollars, or about $900 million more than the Navy’s estimate of $10.3 billion in constant FY2009 dollars, and
that if “CVN-78 experienced cost growth similar to that of other lead ships that the Navy has purchased in the past 10
years, costs could be much higher still.” CBO also reported that, although the Navy publicly expressed confidence in its
cost estimate for CVN-78, the Navy had assigned a confidence level of less than 50% to its estimate, meaning that the
Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office,
Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in August
2007 that:
Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate,
which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be
built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s
target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for
construction was 22 percent higher than the Navy’s cost target, which was based on the budget.
Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to
build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage
issues that affect cost suffers from insufficient cost surveillance. Without effective cost
(continued...)
Congressional Research Service
6

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, and 80
(As shown in FY2008-FY2015 budgets, in millions of then-year dol ars)
Budget CVN-78
CVN-79
CVN-80
Estimated
Scheduled
Estimated
Scheduled
Estimated
Scheduled
procurement
fiscal year of
procurement
fiscal year of
procurement
fiscal year of

cost
procurement
cost
procurement
cost
procurement
FY08 budget
10,488.9
FY08
9,192.0
FY12
10,716.8
FY16
FY09 budget
10,457.9
FY08
9,191.6
FY12
10,716.8
FY16
FY10 budget
10,845.8
FY08
n/aa
FY13b
n/aa FY18b
FY11 budget
11,531.0
FY08
10,413.1
FY13
13,577.0
FY18
FY12 budget
11,531.0
FY08
10,253.0
FY13
13,494.9
FY18
FY13 budget
12,323.2
FY08
11,411.0
FY13c
13,874.2 FY18c
FY14 budget
12,829.3
FY08
11,338.4
FY13
13,874.2
FY18
FY15 budget
12,887.2
FY08
11,498.0
FY13
13,874.2
FY18
% change:



FY08 budget to
-0.3
Almost no
No change
FY09 budget
change
FY09 budget to
+3.7 n/a
n/a
FY10 budget
FY10 budget to
+6.3 n/a
n/a
FY11 budget
FY11 budget to
No change

- 1.5
- 0.1
FY12 budget
FY12 budget to
+6.9%
+11.3%
+2.8%
FY13 budget
FY13 budget to
+4.1%
- 0.6%
No
change
FY14 budget
FY14 budget to
+0.5%
+1.4%
No
change
FY15 budget
FY08 budget to
+22.9%
+25.1%
+29.5%
FY15 budget
Source: Table prepared by CRS based on FY2008-FY2015 Navy budget submissions.
a. n/a means not available; the FY2010 budget submission did not show estimated procurement costs for
CVNs 79 and 80.
b. The FY2010 budget submission did not show scheduled years of procurement for CVNs 79 and 80; the
dates shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for
procuring carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference
regarding recommendations for the FY2010 defense budget.

(...continued)
surveillance, the Navy will not be able to identify early signs of cost growth and take necessary
corrective action.
(Government Accountability Office, Defense Acquisitions[:] Navy Faces Challenges Constructing
the Aircraft Carrier Gerald R. Ford within Budget, GAO-07-866, August 2007, summary page. See
also Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed
to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and
Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary
Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T),
p. 15.)
Congressional Research Service
7

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

c. Although the FY2013 budget did not change the scheduled years of procurement for CVN-79 and CVN-80
compared to what they were under the FY2012 budget, it lengthened the construction period for each ship
by two years (i.e., each ship is scheduled to be delivered two years later than under the FY2012 budget).
Program Procurement Cost Cap
Section 122 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L.
109-364 of October 17, 2006) established a procurement cost cap for CVN-78 of $10.5 billion,
plus adjustments for inflation and other factors, and a procurement cost cap for subsequent Ford-
class carriers of $8.1 billion each, plus adjustments for inflation and other factors. The conference
report (H.Rept. 109-702 of September 29, 2006) on P.L. 109-364 discusses Section 122 on pages
551-552.
Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 113-66 of
December 26, 2013) amended the procurement cost cap for the CVN-78 program to provide a
revised cap of $12,887.0 million for CVN-78 and a revised cap of $11,498.0 million for each
follow-on ship in the program, plus adjustments for inflation and other factors (including an
additional factor not included in original cost cap).
Issues for Congress
Cost Growth
Overview
Cost growth has been a continuing oversight issue for Congress on the CVN-78 program. As
shown in Table 2, the estimated procurement costs of CVNs 78 and 79 have grown 22.9% and
25.1%, respectively, since the submission of the FY2008 budget. As also shown in the table,
CVNs 78, 79, and 80 experienced little or no cost growth from the FY2014 budget to the FY2015
budget. As shown in Table 1, cost growth on CVN-78 has prompted the Navy to program
$1,375.1 million in additional cost-to-complete procurement funding for the ship in FY2014-
FY2016.
Section 121 of the FY2014 National Defense Authorization Act (H.R. 3304/P.L. 113-66 of
December 26, 2013), in addition to amending the procurement cost cap for the CVN-78 program
(see previous section), requires the Navy to submit
on a quarterly basis a report setting forth the most current cost estimate for the aircraft carrier
designated as CVN-79 (as estimated by the program manager). Each cost estimate shall
include the current percentage of completion of the program, the total costs incurred, and an
estimate of costs at completion for ship construction, Government-furnished equipment, and
engineering and support costs.
Section 121 also states that
The Secretary [of the Navy] shall ensure that each prime contract for the aircraft carrier
designated as CVN-79 includes an incentive fee structure that will, throughout the period of
performance of the contract, provide incentives for each contractor to meet the portion of the
cost of the ship, as limited by subsection (a)(2) and adjusted pursuant to subsection (b) [i.e.,
Congressional Research Service
8

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

the amended procurement cost cap for the program], for which the contractor is
responsible.’.
Navy officials have stated that they are working to control the cost of CVN-79 using a build
strategy for the ship that incorporates improvements over the build strategy that was used for
CVN-78. These improvements, Navy officials have said, include the following items, among
others:
• achieving a higher percentage of outfitting of ship modules before modules are
stacked together to form the ship;
• achieving “learning inside the ship,” which means producing similar-looking ship
modules in an assembly line-like series, so as to achieve improved production
learning curve benefits in the production of these modules; and
• more economical ordering of parts and materials including greater use of batch
ordering of parts and materials, as opposed to ordering parts and materials on an
individual basis as each is needed.
The following sections present discussions of the cost growth issue from the Department of
Defense (DOD), the Navy, the Congressional Budget Office (CBO), and the Government
Accountability Office (GAO).
December 2014 CBO Report
A December 2014 CBO report on the potential cost of the Navy’s FY2015 30-year shipbuilding
plan states:
The Navy currently projects that the total cost of the lead ship of the CVN-78 class will be
$12.9 billion in nominal dollars over the period from 2001 to 2016, an amount equal to the
Congressional cost cap.20 Using the Navy’s inflation index for naval shipbuilding, CBO
converted that figure to $14.3 billion in 2014 dollars. That amount is 23 percent more than
the amount requested in the President’s budget when the ship was first authorized in 2008.
The Navy’s estimate does not include $4.7 billion in research and development costs that
apply to the entire class.
CBO estimates that the total cost of the lead ship of the CVN-78 class will be $13.5 billion in
nominal dollars and $14.8 billion in 2014 dollars. To generate that estimate, CBO used the
actual costs of the previous carrier—the CVN-77—and adjusted them for the higher costs of
government-furnished equipment in the newer configuration and for more than $3 billion in
costs for nonrecurring engineering and detail design (the plans, drawings, and other one-time
items associated with the first ship of a new class). Subsequent ships of the CVN-78 class
will not require as much funding for onetime items, although they will incur the same costs
for government-furnished equipment. All together, CBO estimates the average cost of the 6
carriers in the 2015 plan at $12.8 billion, compared with the Navy’s estimate of $12.5
billion....
The final cost of the CVN-78 could be higher or lower than CBO’s estimate. Possible
reasons for a higher cost include the following:
— The costs of many lead ships built in the past 20 years have increased by more than 30
percent from the original budgeted estimates. CBO’s estimate of the cost of the CVN-78
incorporates an amount of growth that falls within the range of historical cost growth for lead
ships, and the costs reported for the roughly 80 percent of construction completed to date
Congressional Research Service
9

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

are consistent with that estimate—but costs have tended to rise more in the latter stages of
ship construction, when systems are being installed and integrated. For example, the test
program for the carrier could reveal one or more major and possibly expensive problems.
— The Navy has stated that there is a 50 percent probability that the cost of the CVN-78
will exceed its estimate. Specifically, in its most recent selected acquisition report, the Navy
stated that it has budgeted an amount for the CVN-78 that covers up to the 50th percentile of
possible cost outcomes.
Possible reasons for a lower cost than CBO’s estimate include the following:
— The Navy and the builder of the CVN-78 recognize that cost growth for lead ships is a
significant concern, and they are actively managing the CVN-78 program to restrain costs.
— All of the materials for the CVN-78 have been purchased, and much of the equipment
for the vessel is being purchased under fixed-price contracts; those factors essentially
eliminate the risk of further cost growth for about half of the projected cost of the carrier.
— The test program might reveal only minor problems. In that case, the cost of the ship
would probably be less than CBO’s estimate, although it might still exceed the Navy’s
estimate.
The next carrier following the CVN-78 will be the CVN-79, the John F. Kennedy. Funding
for that ship began in 2007, the Congress officially authorized its construction in 2013, and
appropriations for it are expected to be complete by 2018. The Navy estimates that the ship
will cost $11.5 billion in nominal dollars ($160 million more than the estimate under the
President’s 2014 budget) and $10.6 billion in 2014 dollars. In its selected acquisition report
on the CVN-79, the Navy describes its cost estimate as an “aggressive but achievable target.”
In contrast, CBO estimates that the cost of the ship will be $12.6 billion in nominal dollars
and $11.5 billion in 2014 dollars, about 8 percent more than the Navy’s estimate.9
November 2014 GAO Report
A November 2014 GAO report on the CVN-78 program stated:
The extent to which the lead Ford-class ship, CVN 78, will be delivered by its current March
2016 delivery date and within the Navy’s $12.9 billion estimate is dependent on the Navy’s
plan to defer work and costs to the post-delivery period. Lagging construction progress as
well as ongoing issues with key technologies further exacerbate an already compressed
schedule and create further cost and schedule risks. With the shipbuilder embarking on one
of the most complex phases of construction with the greatest likelihood for cost growth, cost
increases beyond the current $12.9 billion cost cap appear likely. In response, the Navy is
deferring some work until after ship delivery to create a funding reserve to pay for any
additional cost growth stemming from remaining construction risks. This strategy will result
in the need for additional funding later, which the Navy plans to request through its post-
delivery and outfitting budget account. However, this approach obscures visibility into the
true cost of the ship and results in delivering a ship that is less complete than initially
planned.

9 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2015 Shipbuilding Plan, December 2014, pp. 21,
23.
Congressional Research Service
10

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

CVN 78 will deploy without demonstrating full operational capabilities because it cannot
achieve certain key requirements according to its current test schedule. Key requirements—
such as increasing aircraft launch and recovery rates—will likely not be met before the ship
is deployment ready and could limit ship operations. Further, CVN 78 will not meet a
requirement that allows for increases to the size of the crew over the service life of the ship.
In fact, the ship may not even be able to accommodate the likely need for additional crew to
operate the ship without operational tradeoffs. Since GAO’s last report in September 2013,
post-delivery plans to test CVN 78’s capabilities have become more compressed, further
increasing the likelihood that CVN 78 will not deploy as scheduled or will deploy without
fully tested systems.
The Navy is implementing steps to achieve the $11.5 billion congressional cost cap for the
second ship, CVN 79, but these are largely based on ambitious efficiency gains and reducing
a significant amount of construction, installation, and testing—work traditionally completed
prior to ship delivery. Since GAO last reported in September 2013, the Navy extended CVN
79’s construction preparation contract to allow additional time for the shipbuilder to reduce
cost risks and incorporate lessons learned from construction of CVN 78. At the same time,
the Navy continues to revise its acquisition strategy for CVN 79 in an effort to ensure that
costs do not exceed the cost cap, by postponing installation of some systems until after ship
delivery, and deferring an estimated $200 million - $250 million in previously planned
capability upgrades of the ship’s combat systems to be completed well after the ship is
operational. Further, if CVN 79 construction costs should grow above the legislated cost cap,
the Navy may choose to use funding intended for work to complete the ship after delivery to
cover construction cost increases. As with CVN 78, the Navy could choose to request
additional funding through post-delivery budget accounts not included in calculating the
ship’s end cost. Navy officials view this as an approach to managing the cost cap. However,
doing so impairs accountability for actual ship costs.10
Navy Response to November 2014 GAO Report
A Navy information paper responding to the November 2014 GAO report states (bold font as in
original):
The Navy cost estimate to complete CVN 78 is $12.887B. Cost performance on the
ship has been stable since this estimate was established in 2011, thus providing confidence
that the Navy will deliver the ship within the cost cap.
— This cost estimate accounts for inflation and cost growth associated with completing
the ship design, ship construction (material and labor), and government furnished equipment.
The inflation impact (cost associated with economic impacts during the period of
performance, 2006-2016) was not included in the original $10.5B cost cap.
— Performance-related cost growth is largely due to the lack of maturity of the design
and development at the point in time when the estimate was established and the impact of
concurrency of design, development and construction in the early stages of this first of class
aircraft carrier.
The significant new design features incorporated in the CVN 78 class provide for
increased warfighting capability, increased survivability, increased service life margins
to handle weapons of the future, and most notably, reduced operating and support cost


10 Government Accountability Office, Ford-Class Aircraft Carrier[:] Congress Should Consider Revising Cost Cap
Legislation to Include All Construction Costs
, GAO-15-22, November 2014, summary page.
Congressional Research Service
11

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

throughout the carrier‘s life. The advanced design enables increased sortie generation rates
(SGR) and a reduction of up to 1200 crew and airmen which, alongside other new design
features, results in an estimated $4B reduction per aircraft carrier in its service life. Current
Navy SGR model results and manpower analysis indicate these requirements will be met.
The Navy has provided monthly reports to Congress since the fall of 2011 and has
testified regarding progress on the ship’s completion, including the risk of future cost
growth associated with shipboard testing of the significant new capabilities designed
into this first of class carrier.
The Navy believes it has an effective plan to mitigate the risk,
which places primary emphasis on a ‘build-to-test’ strategy for completing the highest risk
systems, but cannot discount that there is potential for test issues that could impact the
carrier’s completion.
In order to alleviate some of the cost and schedule pressures associated with
completing CVN 78, the Navy has identified certain areas of the ship whose completion
is not required for delivery—such as berthing spaces for the aviation detachment—and
has removed this work from the shipbuilder’s contract. This deferred work will be
completed within the ship’s budgeted end cost and is included within both the $12.887B
cost estimate and cost cap.

By performing this deferred work in the post-delivery period using CVN 78 end
cost funding, it can be competed and accomplished at lower cost and risk to the overall
ship delivery schedule. Importantly, this action uniquely introduces competition within
the otherwise sole-source cost-plus environment at the shipyard and is the type of
action necessary to complete the ship at the lowest cost possible.

— The Navy intends to continue to seek these types of opportunities to drive down the
cost and risk of aircraft carrier new construction.
— Outfitting/Post Delivery funding will not be used to accomplish this deferred work
on CVN 78.
The cost estimate and cost cap for CVN 79 was established in 2006. This estimate
did not include adjustment for the near-decade of inflation that would occur between
2006 and the timeframe when CVN 79 would be procured. The CY$2006 $8.1B
estimate for CVN 79, escalated to the ships actual years of procurement, equates to the
$11.498B budget and cost cap established for CVN 79.
The cost cap established in 2006
for CVN 79 and follow ships did not account for:
— Potential revision to the cost estimate as a result of experience gained through
completion of design, development, construction, and test of the first of class ship, or
— Potential upgrades, modernization, or new requirements subsequent to establishing
the 2006 CVN 78 design baseline.
The Navy is proceeding with a two-phased plan to deliver CVN 79 as an
operationally deployable CVN 78-like repeat under the $11.498M cost cap.
The two-
phased strategy will allow the basic ship to be constructed and tested in the most efficient
manner by the shipbuilder (phase I) while enabling select ship systems and compartments to
be completed in a second phase wherein the work can be completed more efficiently through
competition or the use of skilled installation teams responsible for these activities. Critically,
this two-phased approach also enables the Navy to procure and install at the latest date
possible shipboard electronic systems which otherwise would be subject to obsolescence
prior to CVN 79’s first deployment in the 2027 timeframe. Both phase I and phase II are
Congressional Research Service
12

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

funded within the CVN 79 budgeted end cost and are included within both the $11.498B cost
estimate and cost cap.
— Outfitting/Post Delivery funding will not be used to procure or install systems
planned for phase II on CVN 79.
Capability beyond that contained in CVN 78 will be considered using established
Navy procedures for ship modernization.

— Navy will take these actions consistent with the Congressional cost cap and existing
regulations, and will continue to do so with full transparency to ensure there is no cause for
confusion or concern regarding obscuring the cost of our aircraft carriers.
The Navy strongly recommends against any change by Congress that would
include Post-Delivery and Outfitting within the cost cap because of the potential direct
and deleterious impact this may have on training, certification and making these ships
ready for operations and deployment.
Separate and distinct from ship ‘end cost’, funding
is budgeted within a centrally managed account for Navy ships to provide for ship’s
outfitting material and spares, crew support and certifications, shipyard services and support
(pier services, material handling, security, technical assistance, etc), and correction of
government responsible test and trial deficiencies during the post-Delivery period. In certain
cases, modernization may be conducted during this post-Delivery period to update/upgrade
ship systems based on requirements that have emerged since the ship was originally
contracted. This Outfitting/Post Delivery fund is highly variable, by-hull, is not used for ship
completion, and accordingly is not included by Congress in the ship’s cost cap.11
March 2014 GAO Report
A March 2014 GAO report assessing major DOD weapon acquisition programs stated the
following regarding the status of the CVN-78 program, including the potential for cost growth:
Technology Maturity
According to the Navy, 7 of the 13 critical technologies for CVN 78 are mature, and the
remaining 6 are approaching maturity. To meet required installation dates aboard CVN 78,
the Navy produced several of these technologies, such as the volume search radar (VSR),
prior to demonstrating their maturity—a strategy GAO’s prior work has shown introduces
risk of late and costly design changes and rework. The VSR is a component of the dual band
radar (DBR), which has been delivered to CVN 78, and is undergoing design modifications
needed to complete shipboard integration. According to the Navy, testing in the spring of
2015 will show whether these modifications were successful or a more extensive redesign of
the system is required, which could delay DBR deliveries by up to 4 years. Deficiencies
affecting water twister components—used to absorb energy when arresting aircraft—of the
advanced arresting gear (AAG) technology continue to disrupt the system’s development.
Recent water twister redesign proved unsuccessful in testing last year. The Navy resolved
problems with the redesign and is planning for concurrent testing. Despite these steps, the
Navy forecasts AAG land-based testing to be complete in August 2016—a new delay of
nearly two years—and after the Navy has accepted CVN 78 delivery. The electromagnetic

11 Navy information paper entitled “Navy Response to GAO Report on CVN 78 Class (GAO 15-22, Nov [20]14),”
December 3, 2014, provided by Navy Office of Legislative Affairs to CRS and CBO on December 17, 2014. See also
Jason Sherman, “Navy To Seek OSD Approval To Revamp CVN-79 Acquisition In Wake Of ‘Affordability’ Review,”
Inside the Navy, December 1, 2014.
Congressional Research Service
13

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

aircraft launch system (EMALS) has successfully launched aircraft during land-based testing
using a single launcher and four motor generators. The shipboard system will employ a more
complex configuration with more launchers and generators sharing a power interface.
Design Maturity
CVN 78 completed its 3D product model in November 2009—over a year after the
construction contract award. While the model is now considered functionally complete,
maintaining design stability depends on technologies fitting within the space, weight,
cooling, and power reservations allotted them. Shipboard testing may reveal a need for
design changes. Also, as construction progresses, the shipbuilder is discovering “first-of-
class” type design changes, which it is using to update the model prior to CVN 79
construction.
Production Maturity
According to program officials, CVN 78 is approximately 70 percent complete. Lead ship
procurement costs for the lead ship have grown by over 22 percent since construction
authorization in fiscal year 2008 due in part to problems encountered in construction. Out-of-
sequence work driven largely by material shortfalls, engineering challenges, and delays
developing and installing certain critical technologies the Navy provides to the shipbuilder
for installation has affected construction progress.
Other Program Issues
The Navy deferred award of the CVN 79 detail design and construction contract from late
fiscal year 2013 to the first quarter of fiscal year 2015. According to the Navy, continuing
contract negotiations provide an opportunity to incorporate process improvements into
construction plans. The Navy has undertaken an in-depth review of CVN 79 requirements
and capabilities to identify cost trades, which it hopes can facilitate an agreement on contract
terms. These actions are consistent with recommendations we made in September 2013 to
defer the CVN 79 construction contract and to conduct a cost-benefit analysis on Ford-class
capability requirements and the time and money needed to field systems to provide these
capabilities.
Program Office Comments
According to the program office, CVN 78 displaced 77,000 tons and was 70 percent
complete at launch—the highest levels achieved in aircraft carrier new construction. The
program office also reported that labor inefficiencies during ship erection are past and the
principal risk remaining is in shipboard testing. Concerns over system integration within
platform space, weight, and power reservations have been resolved. Land based testing for
EMALS and DBR has progressed enough that program officials do not anticipate significant
redesign. Further, the AAG test schedule remains on track to support ship delivery and sea
trials. Lastly, the Navy plans to modify the CVN 79 construction preparation contract to
extend the terms of the contract and avoid a production break during negotiations on the
detail design and construction contract without delaying ship delivery. Program officials also
provided technical comments that were incorporated where deemed appropriate.12

12 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-14-
340SP, March 2014, p. 74.
Congressional Research Service
14

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

March 2013 Navy Report to Congress (Released May 2013)
A March 2013 report to Congress on the Navy’s plan for building CVN-79 that was released to
the public on May 16, 2013, states in its executive summary:
As a result of the lessons learned on CVN 78, the approach to carrier construction has
undergone an extensive affordability review and the Navy and the shipbuilder have made
significant changes on CVN 79 that will significantly reduce the cost to build the ship. These
include four key construction areas:
— CVN 79 construction will start with a complete design and a complete bill of material
— CVN 79 construction will start with a firm set of stable requirements
— CVN 79 construction will start with the development complete on a host of new
technologies inserted on CVN 78 ranging from the Electromagnetic Aircraft Launch System
(EMALS), the Dual Band Radar, and the reactor plant, to key valves in systems throughout
the ship
— CVN 79 construction will start with an ‘optimal build’ plan that emphasizes the
completion of work and ship outfitting as early as possible in the construction process to
optimize cost and ultimately schedule performance.
In addition to these fundamentals, the Navy and the shipbuilder are tackling cost through a
series of other changes that when taken over the entire carrier will have a significant impact
on construction costs. The Navy has also imposed cost targets and is aggressively pursuing
cost reduction initiatives in its government furnished systems. A detailed accounting of these
actions is included in this report.
The actions discussed in this report are expected to reduce the material cost of CVN 79 by
10-20% in real terms from CVN 78, to reduce the number of man-hours required to build the
CVN 79 by 15-25% from CVN 78, and to reduce the cost of government furnished systems
by 5-10% in real terms from CVN 78.13
For the full text of the navy’s report, see Appendix A.
May 2013 Navy Testimony
In its prepared statement for a May 8, 2013, hearing on Navy shipbuilding programs before the
Seapower subcommittee of the Senate Armed Services Committee, the Navy stated that
In 2011, the Navy identified spiraling cost growth [on CVN-78] associated with first of class
non-recurring design, contractor and government furnished equipment, and ship production
issues on the lead ship. The Navy completed an end-to-end review of CVN 78 construction
in December 2011 and, with the shipbuilder, implemented a series of corrective actions to
stem, and to the extent possible, reverse these trends. While cost performance has stabilized,
incurred cost growth is irreversible....

13 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, p. 3. An annotation on
the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was
posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To
Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013.
Congressional Research Service
15

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

As a result of lessons learned on CVN 78, the approach to carrier construction has undergone
an extensive affordability review; and the Navy and the shipbuilder have made significant
changes on CVN 79 that will reduce the cost to build the ship. CVN 79 construction will
start with a complete design, firm requirements, and material economically procured and on
hand in support of production need. The ship’s build schedule also provides for increased
completion levels at each stage of construction with resulting improved production
efficiencies....
Inarguably, this new class of aircraft carrier brings forward tremendous capability and life-
cycle cost advantages compared to the NIMITZ-class it will replace. However, the design,
development and construction efforts required to overcome the technical challenges inherent
to these advanced capabilities have significantly impacted cost performance on the lead ship.
The Navy continues implementing actions from the 2012 detailed review of the FORD-Class
build plan to control cost and improve performance across lead and follow ship contracts.
This effort, taken in conjunction with a series of corrective actions with the shipbuilder on
the lead ship, will not recover costs to original targets for GERALD R. FORD [CVN-78], but
should improve performance on the lead ship while fully benefitting CVN 79 and following
ships of the class.14
In the discussion portion of the hearing, Sean Stackley, the Assistant Secretary of the Navy for
Research, Development and Acquisition (i.e., the Navy’s acquisition executive), testified that
First, the cost growth on the CVN-78 is unacceptable. The cost growth dates back in time to
the very basic concepts that went into take in the Nimitz-class and doing a total redesign of
the Nimitz class to get to a level of capability and to reduce operating and support cost for
the future carrier. Far too much risk was carried into the design of the first of the Ford-class.
Cost growth stems to the design was moving at the time production started. The vendor base
that was responsible for delivering new components and material to support the ship
production was (inaudible) with new developments in the vendor base and production plan
do not account for the material ordering difficulties, the material delivery difficulties and
some of the challenges associated with building a whole new design compared to the
Nimitz....
Sir, for CVN-79, we have—we have held up the expenditures on CVN-79 as we go through
the details of—one, ensuring that the design of the 78 is complete and repeated for the 79s
[sic] that we start with a clean design.
Two, we're going through the material procurement. We brought a third party into
assessment material-buying practices at Newport News to bring down the cost of material.
And we're metering out the dollars for buying material until it hits the objectives that we're
setting for CVN-79 through rewriting the build plan on CVN-79.
If you take a look at how the 78 is being constructed, far too much work is being
accomplished late in the build cycle. So we are rewriting the build plan for CVN-79, do more
work in the shops where it’s more efficient, more work in the buildings where it’s more
efficient, less work in the dry dock, less work on the water. And then we're going after the

14 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and
Acquisition) and Vice Admiral Allen G. Myers, Deputy Chief of Naval Operations for Integration of Capabilities and
Resources and Vice Admiral Kevin M. McCoy, Commander, Naval Sea Systems Command, Before the Subcommittee
on Seapower of the Senate Armed Services Committee on Department of the Navy Shipbuilding Programs, May 8,
2013, p. 8.
Congressional Research Service
16

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

rates—the labor rates and the investments needed by the shipbuilder to achieve these
efficiencies.15
Later in the hearing, Stackley testified that
the history in shipbuilding is since you don't have a prototype for a new ship, the first of
class referred to as the lead ship is your prototype. And so you carry a lot of risk into the
construction of that first of class.
Also, given the nature that there’s a lengthy design development and build span associated
with ships, so there is a certain amount of overlap or concurrency that occurs between the
development of new systems that need to be delivered with the first ship, the incorporation of
the design of those new systems and the actual construction. And so to the extent that there is
change in a new ship class then the risk goes up accordingly.
In the case of the CVN-78, the degree of change compared to the Nimitz was fairly
extraordinary all for good reasons, good intentions, increased capability, increased
survivability, significant reduction in operating and support costs. So there was a
determination that will take on this risk in order to get those benefits, and the case of the
CVN-78, those risks are driving a lot of the cost growth on the lead ship.
When you think about the follow ships, now you've got a stable design, now your vendor
base has got a production line going to support the production. Now you've got a build plan
and a workforce that has climbed up on the learning curve to drive cost down. So you can
look at—you can look at virtually every shipbuilding program and you'll see a significant
drop-off in cost from that first of class to the follow ships.
And then you look for a stable learning curve to take over in the longer term production of a
ship class.
Carriers are unique for a number of reasons, one of which we don't have an annual
procurement of carriers. They're spread out over a five and, in fact, in the case of 78 as much
as seven-year period. So in order to achieve that learning, there are additional challenges
associated with achieving that learning. And so we're going at it very deliberately on the
CVN-79 through the build plan with the shipbuilder to hit the line that we've got to have—
the cost reductions that we've got to have on the follow ships of the class.16
March 2012 Navy Letter to Senator McCain
Secretary of the Navy Ray Mabus, in a letter with attachment sent in late March 2012 to Senator
John McCain on controlling cost growth in CVN-78, stated:
Dear Senator McCain:
Thank you for your letter of March 21, 2012, regarding the first-of-class aircraft carrier,
GERALD R. FORD (CVN 78). Few major programs carry greater importance or greater
impact on national security, and no other major program comprises greater scale and
complexity than the Navy’s nuclear aircraft carrier program. Accordingly, successful
execution of this program carries the highest priority within the Department of the Navy.

15 Transcript of hearing.
16 Transcript of hearing.
Congressional Research Service
17

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

I have shared in the past my concern when I took office and learned the full magnitude of
new technologies and design change being brought to the FORD. Requirements drawn up
more than a decade prior for this capital ship drove development of a new reactor plant,
propulsion system, electric plant and power distribution system, first of kind electromagnetic
aircraft launching system, advanced arresting gear, integrated warfare system including a
new radar and communications suite, air conditioning plant, weapons elevators, topside
design, survivability improvements, and all new interior arrangements. CVN 78 is a near-
total redesign of the NIMITZ Class she replaces. Further, these major developments, which
were to be incrementally introduced in the program, were directed in 2002 to be integrated
into CVN 78 in a single step. Today we are confronting the cost impacts of these decisions
made more than a decade ago.
In my August 29, 2011 letter, I provided details regarding these cost impacts. At that time, I
reported the current estimate for the Navy’s share of the shipbuilder’s construction overrun,
$690 million, and described that I had directed an end-to-end review to identify the changes
necessary to improve cost for carrier design, material procurement, planning, build and test.
The attached white paper provides the findings of that review and the steps we are taking to
drive affordability into the remaining CVN 78 construction effort. Pending the results of
these efforts, the Navy has included the ‘fact of life’ portion of the stated overrun in the
Fiscal Year 2013 President’s Budget request. The review also highlighted the compounding
effects of applying traditional carrier build planning to a radically new design; the challenges
inherent to low-rate, sole-source carrier procurement; and the impact of external economic
factors accrued over 15 years of CVN 78 procurement—all within the framework of cost-
plus contracts. The outlined approach for ensuring CVN 79 and follow ship affordability
focuses equally upon tackling these issues while applying the many lessons learned in the
course of CVN 78 procurement.
As always, if I may be of further assistance, please let me know.
Sincerely, [signed] Ray Mabus
Attachment: As stated
Copy to: The Honorable Carl Levin, Chairman
[Attachment]
Improving Cost Performance on CVN 78
CVN 78 is nearing 40 percent completion. Cost growth to-date is attributable to increases in
design, contractor furnished material, government furnished material (notably, the
Electromagnetic Aircraft Launching System (EMALS), Advanced Arresting Gear (AAG),
and the Dual Band Radar (DBR)), and production labor performance. To achieve the best
case outcome, the program must execute with zero additional cost growth in design and
material procurement, and must improve production performance. The Navy and the
shipbuilder have implemented a series of actions and initiatives in the management and
oversight of CVN 78 that cross the full span of contracting, design, material procurement,
government furnished equipment, production planning, production, management and
oversight.
CVN 78 is being procured within a framework of cost-plus contracts. Within this framework,
however, the recent series of action taken by the Navy to improve contract effectiveness are
achieving the desired effect of incentivizing improved cost performance and reducing
government exposure to further cost growth.
Congressional Research Service
18

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

• CVN 78 design has been converted from a ‘level of effort, fixed fee’ contract to a
completion contract with a firm target and incentive fee. Shipbuilder cost performance
has been on-target or better since this contract was changed.
• CVN 78 construction fee has been retracted, consistent with contract performance.
However, the shipbuilder is incentivized by the contract shareline to improve upon
current performance to meet agreed-to cost goals.
• Contract design changes are under strict control; authorized only for safety, damage
control, mission-degrading deficiencies, or similar. Adjudicated changes have been
contained to less than 1 percent of contract target price.
• The Navy converted the EMALS and AAG production contract to a firm, fixed price
contract, capping cost growth to that system and imposing negative incentives for late
delivery.
• Naval Sea Systems Command is performing a review of carrier specifications with the
shipbuilder, removing or improving upon overly burdensome or unneeded specifications
that impose unnecessary cost on the program.
The single largest impact to cost performance to-date has been contractor and government
material cost overruns. These issues trace to lead ship complexity and CVN 78 concurrency,
but they also point to inadequate accountability for carrier material procurement, primarily
during the ship’s advance procurement period (2002-2008).
These effects cannot be reversed on CVN 78, but it is essential to improve upon material
delivery to the shipyard to mitigate the significant impact of material delays on production
performance. Equally important, the systemic material procurement deficiencies must be
corrected for CVN 79. To this end, the Navy and shipbuilder have taken the following
actions.
• The Navy has employed outside supply chain management experts to develop optimal
material procurement strategies. The Navy and the shipbuilder are reviewing remaining
material requirements to employ these best practices (structuring procurements to
achieve quantity discounts, dual-sourcing to improve schedule performance and
leverage competitive opportunities, etc.).
• The shipbuilder has assigned engineering and material sourcing personnel to each of
their key vendors to expedite component qualifications and delivery to the shipyard.
• The shipbuilder is inventorying all excess material procured on CVN 78 for transfer to
CVN 79 (cost reduction to CVN 78), as applicable.
• The Program Executive Officer (Carriers) is conducting quarterly flag-level government
furnished equipment summits to drive cost reduction opportunities and ensure on-time
delivery of required equipment and design information to the shipbuilder.
The most important finding regarding CVN 78 remaining cost is that the CVN 78 build plan,
consistent with the NIMITZ class, focuses foremost on completion of structural and critical
path work to support launching the ship on-schedule. This emphasis on structure comes at
the expense of completing ship systems, outfitting, and furnishing early in the build process
and results in costly, labor-intensive system completion activity during later; more costly
stages of production. Achieving the program’s cost improvement targets will require that
Congressional Research Service
19

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

CVN 78 increase its level of completion at launch, from current estimate of 60 percent to no
less than 65 percent. To achieve this goal and drive greater focus on system completion:
• the Navy fostered a collaborative build process review by the shipbuilder with other Tier
1 private shipyards in order to benchmark its performance arid identify fundamental
changes that would yield marked improvement;
• the shipbuilder has established specific launch metrics by system (foundations,
machinery, piping, power panels, vent duct, lighting, etc.) and increased staffing for
waterfront engineering and material expediters to support meeting these metrics;
• the shipbuilder has linked all of these processes within a detailed integrated master
schedule, providing greater visibility to current performance and greater ability to
control future cost and schedule performance across the shipbuilding disciplines;
• the Navy and shipbuilder are conducting Unit Readiness Reviews of CVN 78 erection
units to ensure that the outfitted condition of each hull unit being lifted into the dry-dock
contains the proper level of outfitting.
These initiatives, which summarize a more detailed list of actions being implemented and
tracked as result of the end-to-end review, are accompanied by important management
changes.
• The shipbuilder has assigned a new Vice President in charge of CVN 78, a new Vice
President in charge of material management and purchasing, and a number of new
general shop foreman to strengthen CVN 78 performance.
• The Navy has assigned a second tour Flag Officer with considerable carrier operations,
construction, and program management experience as the new Program-Executive
Officer (PEO).
• The PEO and shipyard president conduct bi-weekly launch readiness reviews focusing
on cost performance, critical path issues and accomplishment of the target for launch
completion.
• The Assistant Secretary of the Navy (Research, Development, and Acquisition)
conducts a monthly review of program progress and performance with the PEO and
shipbuilder, bringing to bear the full weight of the Department, as needed, to ensure that
all that can be done to improve on cost performance is being done.
Early production performance improvements can be traced directly to these actions,
however, significant further improvement is required. To this end, the Navy is conducting a
line-by-line review of all ‘cost to-go’ on CVN 78 to identify further opportunity to reduce
cost and to mitigate risk.
Improving Cost Performance on CVN 79
CVN 79 Advance Procurement commenced in 2007 with early construction activities
following in 2011. Authorization for CVN 79 procurement is requested in Fiscal Year 2013
President’s Budget request with the first year of incremental funding. Two years have been
added to the CVN 79 production schedule in this budget request, afforded by the fact that
CVN 79 will replace CVN 68 when she inactivates. To improve affordability for CVN 79,
the Navy plans to leverage this added time by introducing a fundamental change to the
Congressional Research Service
20

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

carrier procurement approach and a corresponding shift to the carrier build plan, while
incorporating CVN 78 lessons learned.
The two principal ‘documents’ which the Navy and shipbuilder must ensure are correct and
complete at the outset of CVN 79 procurement are the design and the build plan.
Design is governed by rules in place that no changes will be considered for the follow ship
except changes necessary to correct design deficiencies on the lead ship, fact of life changes
to correct obsolescence issues, or changes that will result in reduced cost for the follow ship.
Exceptions to these rules must be approved by the JROC, or designee. Accordingly, the
Navy is requesting procurement authority for CVN 79 with the Design Product Model
complete and construction drawings approximately 95 percent complete (compared to
approximately 30 percent complete at time of lead ship authorization).
As well, first article testing and certification will be complete for virtually all major new
equipments introduced in the FORD Class. At this point in time, the shipbuilder has
developed a complete bill of material for CVN 79. The Navy is working with the shipbuilder
to ensure that the contractor’s material estimates are in-line with Navy ‘should cost’
estimates; eliminating non-recurring costs embedded in lead ship material, validating
quantities, validating escalation indices, incorporating lead ship lessons learned. The Navy
has increased its oversight of contractor furnished material procurement, ensuring that
material procurement is competed (where competition is available); that it is fixed priced;
that commodities are bundled to leverage economic order quantity opportunities; and that the
vendor base capacity and schedule for receipt supports the optimal build plan being
developed for production.
In total, the high level of design maturity and material certification provides a stable
technical baseline for material procurement cost and schedule performance, which are
critical to developing and executing an improved, reliable build plan.
In order to significantly improve production labor performance, based on timely receipt of
design and material, the Navy and shipbuilder are reviewing and implementing changes to
the CVN 79 build plan and affected facilities. The guiding principles are:
• maximize planned work in the shops and early stages of construction;
• revise sequence of structural unit construction to maximize learning curve performance
through ‘families of units’ and work cells;
• incorporate design changes to improve FORD Class producibility;
• increase the size of erection units to eliminate disruptive unit breaks and improve unit
alignment and fairness;
• increase outfitting levels for assembled units prior to erection in the dry-dock;
• increase overall ship completion levels at each key event.
The shipbuilder is working on detailed plans for facility improvements that will improve
productivity, and the Navy will consider incentives for capital improvements that would
provide targeted return on investment, such as:
• increasing the amount of temporary and permanent covered work areas;
Congressional Research Service
21

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

• adding ramps and service towers for improved access to work sites and the dry-dock;
• increasing lift capacity to enable construction of larger, more fully outfitted super-lifts:
An incremental improvement to carrier construction cost will fall short of the improvement
necessary to ensure affordability for CVN 79 and follow ships. Accordingly, the shipbuilder
has established aggressive targets for CVN 79 to drive the game-changing improvements
needed for carrier construction. These targets include:
• 75 percent Complete at Launch (15 percent> [i.e., 15 percent greater than] FORD);
• 85-90 percent of cable pulled prior to Launch (25-30 percent> FORD);
• 30 percent increase in front-end shop work (piping details, foundations, etc);
• All structural unit hot work complete prior to blast and paint;
• 25 percent increase to work package throughput;
• 100 percent of material available for all work packages in accordance with the
integrated master schedule;
• zero delinquent engineering and planning products;
• resolution of engineering problems in < 8 [i.e., less than 8] hours.
In parallel with efforts to improve shipbuilder costs, the PEO is establishing equally
aggressive targets to reduce the cost of government furnished equipment for CVN 79;
working equipment item by equipment item with an objective to reduce overall GFE costs by
~$500 million. Likewise, the Naval Sea Systems Command is committed to continuing its
ongoing effort to identify specification changes that could significantly reduce cost without
compromising safety and technical rigor.
The output of these efforts comprises the optimal build plan for CVN 79 and follow, and will
be incorporated in the detail design and construction baseline for CVN 79. CVN 79 will be
procured using a fixed price incentive contract.17
Issues Raised in January 2014 DOT&E Report
Another issue for Congress concerns CVN-78 program issues that were raised in a January 2014
report from DOD’s Director, Operational Test and Evaluation (DOT&E)—DOT&E’s annual
report for FY2013. The report stated the following in its section on the CVN-78 program:
Assessment
Test Planning

17 Letter and attachment from Secretary of the Navy Ray Mabus to Senator John McCain, undated but posted at
InsideDefnse.com (subscription required) on March 27, 2012. InsideDefense.com’s description of the letter states that it
is dated March 26, 2012.
Congressional Research Service
22

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

• The current state of the VCVN [Virtual CVN] model does not fully provide for an accurate
accounting of SGR [Sortie Generation Rate] due to a lack of fidelity regarding manning and
equipment/aircraft availability. Spiral development of the VCVN model continues in order to
ensure that the required fidelity will be available to support the SGR assessment during
IOT&E [Initial Operational Test and Evaluation].
• A new TEMP [Test and Evaluation Master Plan] is under development to address problems
with the currently-approved TEMP. The current TEMP does not adequately address
platform-level developmental testing. The Program Office has begun to refine the Post
Delivery Test and Trials schedule, but that schedule still lacks sufficient details to ensure
reasonable developmental testing. Lack of platform-level developmental testing significantly
raises the likelihood of the discovery of platform-level problems during IOT&E.
• The Navy plans to deliver CVN-78 in February 2016. The ship’s post-shipyard shakedown
availability will follow delivery in 2016. During the post-shipyard shakedown availability
installations of some systems will be completed. The first at-sea operational test and
evaluation of CVN-78 will begin in July 2017.
Reliability
• CVN-78 includes several systems that are new to aircraft carriers; four of these systems
stand out as being critical to flight operations: EMALS [Electromagnetic Aircraft Launch
System], AAG [Advanced Arresting Gear], DBR [Dual Band Radar], and the Advanced
Weapons Elevators (AWEs). Overall, the uncertain reliability of these four systems is the
most significant risk to the CVN-78 IOT&E. All four of these systems will be tested for the
first time in their shipboard configurations aboard CVN-78. Reliability estimates derived
from test data are available for EMALS and AAG and are discussed below. For DBR and
AWE, estimates based on test data are not available and only engineering reliability
estimates are available.
SGR
• It is unlikely that CVN-78 will achieve its SGR requirement. The target threshold is based
on unrealistic assumptions including fair weather and unlimited visibility, and that aircraft
emergencies, failures of shipboard equipment, ship maneuvers (e.g., to avoid land), and
manning shortfalls will not affect flight operations. DOT&E plans to assess CVN-78
performance during IOT&E by comparing to the demonstrated performance of the Nimitz
class carriers. A demonstrated SGR less than the requirement but equal to or greater than the
performance of the Nimitz class could potentially be acceptable.
• During the operational assessment, DOT&E conducted an analysis of past aircraft carrier
operations in major conflicts. The analysis concludes that the CVN-78 SGR requirement is
well above historical levels and that CVN-78 is unlikely to achieve that requirement. There
are concerns with the reliability of key systems that support sortie generation on CVN-78.
Poor reliability of these critical systems could cause a cascading series of delays during flight
operations that would affect CVN-78’s ability to generate sorties, make the ship more
vulnerable to attack, or create limitations during routine operations. DOT&E assesses the
poor or unknown reliability of these critical subsystems will be the most significant risk to
CVN-78’s successful completion of IOT&E. The analysis also considered the operational
implications of a shortfall and concluded that as long as CVN-78 is able to generate sorties
Congressional Research Service
23

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

comparable to Nimitz class carriers, the operational implications of CVN-78 will be similar
to that of a Nimitz class carrier.18
Manning
• Current manning estimates have shortages of bunks for Chief Petty Officers (CPOs) and do
not provide the required 10 percent SLA. Per Office of the Chief of Naval Operations
Instruction 9640.1B, Shipboard Habitability Program, all new ships are required to have a
growth allowance of 10 percent of the ship’s company when the ship delivers. The SLA
provides empty bunks to allow for changes in the crew composition over CVN-78’s expected
50-year lifespan and provides berthing for visitors and Service members temporarily
assigned to the ship.
EMALS
• EMALS is one of the four systems critical to flight operations. While testing to date has
demonstrated that EMALS should be able to launch aircraft planned for CVN-78’s air wing,
the system’s reliability is uncertain. At the Lakehurst, New Jersey, test site, over 1,967
launches have been conducted and 201 chargeable failures have occurred. Based on available
data, the program estimates that EMALS has approximately 240 Mean Cycles Between
Critical Failure in the shipboard configuration, where a cycle represents the launch of one
aircraft. Based on expected reliability growth, the failure rate is presently five times higher
than should be expected.
AAG
• AAG is another system critical to flight operations. Testing to date has demonstrated that
AAG should be able to recover aircraft planned for the CVN-78 air wing, but as with
EMALS, AAG’s reliability is uncertain. At the Lakehurst, New Jersey test site, 71
arrestments were conducted earlier this year and 9 chargeable failures occurred. The Program
Office estimates that AAG has approximately 20 Mean Cycles Between Operational Mission
Failure in the shipboard configuration, where a cycle represents the recovery of one aircraft.
Based on expected reliability growth, the failure rate is presently 248 times higher than
should be expected.
DBR
• Previous testing of Navy combat systems similar to CVN-78’s revealed numerous
integration problems that degrade the performance of the combat system. Many of these
problems are expected to exist on CVN-78. The previous results emphasize the necessity of
maintaining a DBR/CVN-78 combat system asset at Wallops Island. The Navy is
considering long-term plans (i.e., beyond FY15) for testing DBR at Wallops Island, Virginia,
but it is not clear if resources and funding will be available. Such plans are critical to
delivering a fully-capable combat system and ensuring lifecycle support after CVN-78
delivery in 2016.
JPALS [Joint Precision Approach and Landing System]
• The Navy has proposed to the USD(AT&L) Milestone Decision Authority that the program
be restructured from its current, land- and sea-based, multiple-increment structure to a single

18 The issue of the sortie generation rate was also discussed in Tony Capaccio, “Hagel Told New Carrier Unlikely to
Meet Aircraft Goals,” Bloomberg News, January 10, 2014.
Congressional Research Service
24

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

increment focusing on sea-based requirements primarily supporting JSF [Joint Strike Fighter;
aka F-35] and future Unmanned Carrier Launched Airborne Surveillance and Strike aircraft.
Under this proposed restructuring scheme, there will be no retrofitting of JPALS on legacy
aircraft and the Navy will need to maintain both the legacy approach and landing system and
JPALS onboard each aircraft-capable ship.
JSF
• The arresting hook system remains an integration risk as the JSF development schedule
leaves no time for discovering new problems. The redesigned tail hook has an increased
downward force as well as sharper design that may induce greater than anticipated wear on
the flight deck.
• JSF noise levels remain moderate to high risk in JSF integration and will require modifi ed
carrier flight deck procedures.
- Flight operations normally locate some flight deck personnel in areas where double hearing
protection would be insufficient during F-35 operations. To partially mitigate noise concerns,
the Navy will procure new hearing protection with active noise reduction for flight deck
personnel.
- Projected noise levels one level below the flight deck (03 level), which includes mission
planning spaces, will require at least single hearing protection that will make mission
planning difficult. The Navy is working to mitigate the effects of the increased noise levels
adjacent to the flight deck.
• Storage of the JSF engine is limited to the hangar bay, which will affect hangar bay
operations. The impact on the JSF logistics footprint is not yet known.
• Lightning protection of JSF aircraft while on the flight deck will require the Navy to
modify nitrogen carts to increase their capacity. Nitrogen is used to fill fuel tank cavities
while aircraft are on the flight deck.
• JSF remains unable to share battle damage assessment and non-traditional Intelligence,
Surveillance, and Reconnaissance information captured on the aircraft portable memory
device or cockpit voice recorder in real-time. In addition, the CVN-78 remains unable to
receive and display imagery transmitted through Link 16 because of bandwidth limitations.
These capability gaps were identified in DOT&E’s FY12 Annual Report. The Combatant
Commanders have requested these capabilities to enhance decision-making.
LFT&E [Live Fire Test and Evaluation]
• While the Navy has made substantial effort in component and surrogate testing, this work
does not obviate the need to conduct the FSST [Full Ship Shock Trial] to gain the critical
empirical data that past testing has repeatedly demonstrated are required to rigorously
evaluate the ship’s ability to withstand shock and survive in combat. Shock Trials conducted
on both the Nimitz class aircraft carrier and the San Antonio class Amphibious Transport
Dock demonstrated the need for and substantial value of conducting the FSST. Postponing
the FSST until CVN-79 would cause a five- to seven-year delay in obtaining the data critical
to evaluating the survivability of the CVN-78 and would preclude timely modification of
subsequent ships of this class to assure their survivability.
• CVN-78 has many new critical systems that have not undergone shock trials on other
platforms. Unlike past tests on other new classes of ships with legacy systems, the
performance of CVN-78’s new critical systems under test is unknown.
Congressional Research Service
25

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

• The Navy proposes delaying the shock trial by five to seven years because of the
approximately four- to six-month delay required to perform the FSST. The benefit of having
test data to affect the design of future carriers in the class outweighs the delay in delivery of
CVN-78 to the fleet to conduct this test. The delay is not a sufficient reason to postpone the
shock trial.
Recommendations
• Status of Previous Recommendations. The Navy should continue to address the seven
remaining FY10 and FY11 recommendations.
1. Adequately test and address integration challenges with JSF; specifically:
- Logistics (unique concerns for storage and transportation)
- Changes required to JBDs [Jet Blast Deflectors]
- Changes to flight deck procedures due to heat and noise
- Autonomic Logistics Information System integration
2. Finalize plans that address CVN-78 Integrated Warfare System engineering and ship’s
self-defense system discrepancies prior to the start of IOT&E.
3. Continue aggressive EMALS and AAG risk-reduction efforts to maximize opportunity for
successful system design and test completion in time to meet required in-yard dates for
shipboard installation of components.
4. Continue development of a realistic model for determining CVN-78’s SGR, while
utilizing realistic assumptions regarding equipment availability, manning, and weather
conditions for use in the IOT&E.
5. Provide scheduling, funding, and execution plans to DOT&E for the live SGR test event
during the IOT&E.
6. Continue to work with the Navy’s Bureau of Personnel to achieve adequate depth and
breadth of required personnel to sufficiently meet Navy Enlisted Classification fit/fill
manning requirements of CVN-78.
7. Conduct system-of-systems developmental testing to preclude discovery of deficiencies
during IOT&E.
• FY13 Recommendations. The Navy should:
1. Address the uncertain reliability of EMALS, AAG, DBR, and AWE. These systems are
critical to CVN-78 flight operations, and are the largest risk to the program.
2. Conduct fully integrated, robust, end-to-end testing of the proposed JPALS, to include
operations in neutral and potentially hostile electronic warfare environments.19

19 Department of Defense, Director, Operational Test & Evaluation, FY2013 Annual Report, released January 2014, pp.
157-159. See also Olga Belogolova, “Navy Pushes Back On DOT&E Reliability Concerns For Ford-Class Carrier,”
Inside the Navy, February 24, 2014.
Congressional Research Service
26

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Potential Two-Ship Block Buy on CVN-79 and CVN-80
Another issue for Congress concerns the potential for procuring CVN-79 and CVN-80 together in
a two-ship block buy. The Navy currently plans to procure CVN-79 and CVN-80 separately, as
one-ship procurements. Procuring the two ships together in a block buy could reduce their
combined procurement cost.
Procuring two aircraft carriers together in a two-ship block buy has been done on two previous
occasions. The Navy procured two Nimitz (CVN-68) class aircraft carriers (CVN-72 and CVN-
73) together in a block buy in FY1983, and procured another two Nimitz-class aircraft carriers
(CVN-74 and CVN-75) together in a block buy in FY1988. The Navy proposed these block buys
in the FY1983 and FY1988 budget submissions.20
When the FY1983 block buy was proposed, the Navy estimated that the block buy would reduce
the combined cost of CVN-72 and CVN-73 by 5.6% in real terms.21 When the FY1988 block buy
was proposed, the Navy estimated that the block buy would reduce the combined cost of CVN-74
and CVN-75 by a considerably larger percentage. GAO stated that the savings would be
considerably less than the Navy estimated, but agreed that a two-ship acquisition strategy is less
expensive than a single-ship acquisition strategy, and that some savings would occur in a two-
ship strategy for CVN-74 and CVN-75.22

20 It can also be noted that the Air Force is procuring two Advanced EHF (AEHF) satellites under a two-satellite block
buy that the Air Force proposed and Congress approved in FY2012.
21 See General Accounting Office, Request to Fully Fund Two Nuclear Aircraft Carriers in Fiscal Year 1983,
MASAD-82-87 (B-206847), March 26, 1982, 10 pp. The figure of 5.6% was derived by dividing $450 million in non-
inflation cost avoidance shown on page 5 by the combined estimated cost of the two ships (absent a block buy) of
$8,024 million shown on page 4.
22 See General Accounting Office, Procurement Strategy For Acquiring Two Nuclear Aircraft Carriers, Statement of
Frank Conahan, Assistant Comptroller General, National Security and International Affairs Division, Before the
Conventional Forces and Alliance Defense Subcommittee and Projection Forces and Regional Defense Subcommittee
of the Senate Armed Services Committee, April 7, 1987, T-NSIAD-87-28, 5 pp. The testimony states on page 2 that “A
single ship acquisition strategy is more expensive because materials are bought separately for each ship rather than
being combined into economic order quantity buys under a multi-ship procurement.” The report discounted the Navy’s
estimated savings of $1,100 million based on this effect on the grounds that if CVN-74 and CVN-75 were not procured
in the proposed two-ship block buy, with CVN-74 procured in FY1990 and CVN-75 procured FY1993, it was likely
that CVN-74 and CVN-75 would subsequently be procured in a two-ship block buy, with CVN-74 procured in FY1994
and CVN-75 procured in FY1996. For the discussion here, however, the comparison is between the Navy’s current plan
to procure CVN-79 and CVN-80 separately and the potential alternative of procuring them together in a block buy.
The GAO report commented on an additional $700 million in savings that the Navy estimated would be derived from
improving production continuity between CVN-73, CVN-74, and CVN-75 by stating on page 3 that “It is logical to
assume that savings are possible through production continuity but the precise magnitude of such savings is difficult to
calculate because of the many variables that affect the outcome.” It is not clear how significant savings from production
continuity might be in a two-ship block buy for CVN-79 and CVN-80 if the procurement dates for the two ships
(FY2013 and FY2018, respectively) are not changed.
The GAO report noted that the Navy estimated $500 million in additional savings from avoided configuration changes
on CVN-74 and CVN-75 if the ships were procured in FY1990 and FY1993 rather than FY1994 and FY1996. It is not
clear how significant the savings from avoided configuration changes might be for a two-ship block buy for CVN-79
and CVN-80.
See also CRS Issue Brief IB87043, Aircraft Carriers (Weapons Facts), 13 pp., updated February 10, 1988, and
archived March 24, 1988, by Ronald O’Rourke. The report includes a discussion of the above GAO report. The report
is out of print and available directly from the author.
Congressional Research Service
27

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

The FY1983 and FY1988 block buys each involved procuring two aircraft carriers in a single
year. Procuring two carriers in the same year, however, is not mandatory for a two-ship aircraft
carrier block buy. The Navy, for example, proposed the block buy for CVN-74 and CVN-75 in
the FY1988 budget submission as something that would involve procuring CVN-74 in FY1990
and CVN-75 in FY1993. (Congress, in acting on the FY1988 budget, decided to not only approve
the two-ship block buy, but also accelerate the procurement of both CVN-74 and CVN-75 to
FY1988.)23 A block buy on CVN-79 and CVN-80 could leave intact the FY2013 procurement
date for CVN-79 and the FY2018 procurement date for CVN-80. This would permit the funding
for the two ships to be spread out over the same fiscal years as currently planned, although the
amounts of funding in individual years would likely change.
It is too late to implement a complete block buy on CVN-79 and CVN-80, because some of CVN-
79, particularly its propulsion plant, has already been purchased. Consequently, the option would
be to implement a partial block buy that would include the remaining part of CVN-79 and all of
CVN-80.
To illustrate the notional scale of the savings that might result from using a block buy strategy on
CVN-79 and CVN-80, it can be noted that if such a block buy were to achieve one-third as much
percentage cost reduction as the FY1983 block buy—that is, if it were to reduce the combined
procurement cost of CVN 79 and 80 by about 1.9%—that would equate to a savings of roughly
$470 million on the currently estimated combined procurement cost of CVN-79 and CVN-80.
More refined estimates might be higher or lower than this notional figure of $470 million.
At a March 19, 2012, briefing for CRS and CBO on the CVN-78 program, CRS asked the Navy
whether it was considering the possibility of a block buy on CVN-79 and CVN-80. The Navy
stated that it had looked into a narrower option of doing joint purchases of some materials for the
two ships.
Implementing a block buy on CVN-79 and CVN-80 would require committing to the
procurement of CVN-80. Whether Congress would want to commit to the procurement of CVN-
80, particularly in light of current uncertainty over future levels of defense spending, is a factor
that Congress may consider in assessing the option of doing a block buy. If budgetary
circumstances were to lead to a decision to end procurement of Ford-class carriers after CVN-79,
then much or all of the funding spent procuring materials for CVN-80 could go to waste.
At a March 29, 2012, hearing on Navy shipbuilding programs before the Seapower and Projection
Forces subcommittee of the House Armed Services Committee, Sean Stackley, the Assistant
Secretary of the Navy for Research, Development, and Acquisition (i.e., the Navy’s acquisition
executive), stated the following when asked by Representative Robert Wittman about the
possibility of a two-ship block buy on CVN-79 and CVN-80:
Yes, sir. Let me focus on affordability of the CVN-78 class. We are right now about 40
percent complete construction of the CVN-78 and we’re running into some very difficult
cost growth issues across the full span—design, material procurement, and production—
material procurement on both contractor and government side.

23 See CRS Issue Brief IB87043, Aircraft Carriers (Weapons Facts), 13 pp., updated February 10, 1988, and archived
March 24, 1988, by Ronald O’Rourke. The report is out of print and available directly from the author.
Congressional Research Service
28

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

So our first focus right now is to stabilize the lead ship. Let’s get cost under control so we
can complete this ship as close to schedule at the lowest cost possible.
But in parallel, the Navy is working very closely with the shipbuilder to take a step back and
say, one, what are all the lessons we just learned on CVN-78? Two, CVN-78 is a very
different ship from the Nimitz [CVN-68]; we cannot expect to build the [CVN-]78 the way
we build the [CVN-]68 and—and get to an affordable ship construction plan. So we’re
pressing on the way the carrier is built—the build plan for the carrier—to arrive at a more
affordable CVN-79.
Now, in the process of doing that we’ll take a hard look at what opportunity there is across
[CVN-]79 and [CVN-]80, recognizing that we’re going to be limited, again, by [budget] top
line. But there are going to be some opportunities that jump out at us. We don’t want to have
to replan each carrier. We have a vendor base that is stretched out with the carrier build cycle
that for some components that are carrier-unique, that vendor base is—is just struggling to
hold on between the five-year gaps.
So we have to take a hard look at where does it make sense after we’ve gotten to what I’m
calling an optimal build plan for CVN-79 and then be able to come back and—and say, OK,
here—on CVN-79 here are some opportunities that if we could, in fact, reach out to CVN-80
we can either avoid a gap in a production line or avoid unnecessary cost growth on that
follow ship.24
Later in the hearing, the following exchange occurred:
REPRESENTATIVE RICK LARSEN:
Finally, we had some discussion about this question with regard to CVNs and trying to find a
way to squeeze some costs out, and one of the ideas was to do some—do block buy of
certain components of—of—of CVN components. And have you considered that, and what’s
your thought on that on block buy on components from [CVN-]79 to [CVN-]80, or whatever,
[CVN-]79, [CVN-]79 to [CVN-]80, and so on?
ASSISTANT SECRETARY OF THE NAVY SEAN STACKLEY:
Yes, sir. At this point in time the Navy and the shipbuilder are sitting side by side putting
together a build plan for CVN-79. We’re 40 percent complete construction of the [CVN-]78;
we’ve got a lot that we’ve got to, I’ll say, do different on the [CVN-]79 and follow from the
lead ship. It’s a very different ship class [compared to the Nimitz class].
So we’re taking a hard look at the build plan [for CVN-78]. We need to get that locked
down. And associated with that is the complete bill of materials for the Ford class.
At that point in time we'll be able to take a look at...
LARSEN:
On this, call it bill of materials, what does it make sense—what makes sense in terms of
looking long term, beyond the immediate ship?
STACKLEY:

24 Source: transcript of hearing.
Congressional Research Service
29

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Right.
LARSEN:
Are there areas of the industrial base that are stressed to the point that it does make sense to
look at coupling the CVN-79 and CVN-80 buy?
STACKLEY:
We’re not at that point yet. I described earlier that I think after we get through this build plan
review then we'll be able to come back in ‘14 [FY2014] and identify potential critical items
that warrant a block buy approach.25
Later in the hearing, Matthew Mulherin, president of NNS and corporate vice president of HII,
stated the following when asked by Representative Robert Wittman about the possibility of a two-
ship block buy on CVN-79 and CVN-80:
Yes, sir. You know, historically you go back, you were exactly right, if you look at the
contracts that bought the CVN- 72 and [CVN-]73 there was huge savings that flowed to the
second ship, both in the ability to go buy materials, a block buy and get—get discounts there,
but also that you did the engineering up front the first time for both hulls so the second ship
you really just had the answer, problem, paper [sic] and some of those kind of things the—
the kind of the normal course of business to support the waterfront.
So I wouldn’t see any different. I think if we were able to do it both for material, for—for the
engineering to be able to go pump out drawings that had two-ship applicability—plus, I think
it brings the—the—the CVN—if we were to do a two-ship buy for [CVN-]79 and [CVN-]80
it would ensure CVN-80 was a copy of CVN-79, no change into the contract or very
minimal, you’re not having a—on the material side you get economic order savings, you
don’t have to deal with obsolescence.
So absolutely. I think there’s huge opportunity to go do that. You know, you talk to the—the
vendor base. They would love to see it. It gives them the ability to go look at—at what
investments they need, what work is out in front of them, and go invest in—in training and
tools to—to be able to go support that.26
At the March 19, 2012, briefing for CRS and CBO on the CVN-78 program, CRS asked the Navy
to examine the option of a block buy on CVN-79 and CVN-80, and inform CRS and CBO of the
Navy’s estimate of how much it might reduce the combined procurement cost of CVN-79 and
CVN-80. The Navy’s response, dated April 22, 2012, was sent to CRS on May 10, 2012 (i.e., just
after the House Armed Services Committee completed its markup of H.R. 4310, the FY2013
National Defense Authorization Act). The response stated:
There are several options for procuring aircraft carriers that differ from the current practice;
two ship buys and block buys. Navy experience with aircraft carrier two ship buys includes
procurement of the CVN 72 and CVN 73 (awarded in FY83), and the CVN 74 and CVN 75
(awarded in FY88). The actual cost returns for these procurements support significant
savings compared to other NIMITZ Class single ship buys. This conclusion is based on a
comparison of the NIMITZ Class two ship buys (CVN72, 73, 74 & 75) with single ship buys

25 Source: Transcript of hearing.
26 Source: Transcript of hearing.
Congressional Research Service
30

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

(CVN71 and CVN76). The total ship man-hour comparison shows a 9% reduction. The total
ship material comparison in constant dollars shows an 8% reduction. The NIMITZ- Class
two ship buys took advantage of a single year of full funding for the combined procurement,
and less than three years between the deliveries of each ship. Having both ships fully funded
in one year enabled the Navy and shipbuilder to take advantage of two ship-set Economic
Order Quantity (EOQ) market savings for material items, and also allowed the shipbuilder to
optimize production trades management. The short time between deliveries also resulted in
design stability, minimized potential obsolescence, and greater opportunities for learning.
Given hard budget constraints in FY13 and FY14, CVN 79 and CVN 80 cannot benefit from
a multiyear construct, similar to those requested in PB13 for VIRGINIA Class Submarine
and ARLIEGH BURKE Class Destroyers. By the end of FY14, 75% of CVN 79 material
will be under contract with suppliers, leaving limited opportunities to implement material
savings with multiyear incremental funding. 75% of CVN 80 material would also be
incapable of achieving savings, as the material purchases would be placed after CVN 79.
CVN 80/81 would present the first opportunity to potentially consider this strategy.27
The Navy’s response states, “Having both ships fully funded in one year enabled the Navy and
shipbuilder to take advantage of two ship-set Economic Order Quantity (EOQ) market savings for
material items.... ” It can be noted that ships funded in separate years can also take advantage of
EOQ savings, provided that the authorizing legislation permits the use of EOQ, and that the
FY1988 block buy of CVN-74 and CVN-75 was originally proposed by the Navy as a block buy
in which CVN-74 would be procured in FY1990 and CVN-75 in FY1993.
The Navy’s response states, “Given hard budget constraints in FY[20]13 and FY[20]14, CVN 79
and CVN 80 cannot benefit from a multiyear construct, similar to those requested in PB[20]1328
for VIRGINIA Class Submarine and ARLIEGH BURKE Class Destroyers.” It can be noted that a
block buy on CVN-79 and CVN-80 would not necessarily be a multiyear procurement (MYP)
contract, like those requested for the Virginia-class submarine program and the Arleigh Burke
(DDG-51) destroyer programs. It can also be noted that Congress may decide to work within
budget constraints for FY2013 and FY2014 that might differ from those on which is DOD basing
its planning.
The Navy’s response states, “By the end of FY14, 75% of CVN 79 material will be under
contract with suppliers, leaving limited opportunities to implement material savings with
multiyear incremental funding. 75% of CVN 80 material would also be incapable of achieving
savings, as the material purchases would be placed after CVN 79.” CRS on May 10, 2012, asked
the Navy what percent of the material for CVN-79 would be under contract by the end of
FY2012. The Navy’s response, dated May 22, 2012, was sent to CRS on May 25, 2012 (i.e., the
same day that the House Appropriations Committee reported H.R. 5856, the FY2013 DOD
Appropriations Act). The response stated, “Approximately 47% of CVN 79 direct material will be
under contract by the end of FY[20]12.”29
The Navy’s response states that “CVN 80/81 would present the first opportunity to potentially
consider this [block buy] strategy.” This statement appears to refer to a strategy of a complete

27 Navy information paper dated April 25, 2012, sent to CRS on May 10, 2012.
28 This is a reference to the President’s budget for FY2013—that is, the Administration’s requested budget for FY2013.
29 Navy information paper dated May 22, 2012, sent to CRS on May 25, 2012.
Congressional Research Service
31

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

block buy involving 100% of the material for both carriers. Based on the Navy’s response dated
May 22, 2012, a partial block buy on CVN-79 and CVN-80 involving as much as 53% of the
material on CVN-79 might be possible, if the block buy were authorized and implemented as part
of the FY2013 defense budget.
Legislative Activity for FY2015
FY2015 Funding Request
As shown in Table 1, the Navy’s proposed FY2014 budget requested $663.0 million in
procurement funding to cover cost growth on CVN-78, and $1,300.0 million in procurement
funding for CVN-79. The Navy’s request for $663.0 million in procurement funding to cover cost
growth on CVN-78 forms part of a request for $1,007.3 million in cost-to-complete funding for
various prior-year-funded Navy shipbuilding programs.
FY2015 National Defense Authorization Act (H.R. 3979)
House
CVN-78 Program
The House Armed Services Committee, in its report (H.Rept. 113-446 of May 13, 2014) on the
FY2015 National Defense Authorization Act (H.R. 4435), recommends approving the Navy’s
request for FY2015 procurement funding for the CVN-78 program. (Page 395, line 001, and page
396, line 021).
CVN-73 RCOH
The report also recommends $483.6 million for the refueling complex overhaul (RCOH) of the
aircraft carrier George Washington (CVN-73). (Page 395, line 004.) As discussed in Appendix B,
FY2015 funding for an RCOH for CVN-73 has emerged as an issue in Congress’s review of
DOD’s proposed FY2015 budget.
Section 1024 of H.R. 4435 as reported states:
SEC. 1024. LIMITATION ON EXPENDITURE OF FUNDS UNTIL COMMENCEMENT
OF PLANNING OF REFUELING AND COMPLEX OVERHAUL OF THE U.S.S.
GEORGE WASHINGTON.
Not more than 50 percent of the funds authorized to be appropriated or otherwise made
available under section 301 of this Act for the Office of the Secretary of Defense for fiscal
year 2015 may be obligated or expended until the Secretary of Defense obligates funds to
commence the planning and long lead time material procurement associated with the
refueling and complex overhaul of the U.S.S. George Washington (CVN-73).
Congressional Research Service
32

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Senate
CVN-78 Program
The Senate Armed Services Committee, in its report (S.Rept. 113-176 of June 2, 2014) on the
FY2015 National Defense Authorization Act (S. 2410), recommends approving the Navy’s
request for FY2015 procurement funding for the CVN-78 program. (Page 323, line 1, and page
324, line 21).
CVN-73 RCOH
The report recommends in effect transferring from the Operation and Maintenance, Navy (OMN)
account to the Shipbuilding and Conversion, Navy (SCN) account the Navy’s request for $46
million in FY2015 funding for defueling the aircraft carrier George Washington (CVN-73), so as
to support a refueling complex overhaul (RCOH) for that ship. (Page 323, line 04.) As discussed
in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as an issue in
Congress’s review of DOD’s proposed FY2015 budget. Regarding this transfer of funds, S.Rept.
113-176 states:
Aircraft carrier defueling planning funds
The budget request included $46.0 million in the Operation and Maintenance, Navy (OMN)
account for advance planning funding for defueling of the USS George Washington (CVN–
73) in fiscal year 2017.
It is the committee’s intent that the Navy proceed with the refueling and complex overhaul of
the USS George Washington (CVN–73) should additional funds be made available in fiscal
year 2015 for that purpose.
Therefore, the committee recommends a reduction of $46.0 million in OMN, and an increase
of $46.0 million for CVN Refueling Overhauls in the Shipbuilding and Conversion, Navy
account. (Page 72)
Section 123 of S. 2410 as reported states:
SEC. 123. AUTHORITY TO TRANSFER CERTAIN FUNDS FOR REFUELING OF
AIRCRAFT CARRIER AND CONSTRUCTION OF AMPHIBIOUS SHIP.
(a) In General- To the extent provided in appropriations Acts, upon a determination
described in subsection (b), the Secretary of the Navy is authorized to transfer funds
available in Shipbuilding and Conversion, Navy or any other Navy procurement account for
either or both of the following purposes:
(1) Up to $650,000,000 to conduct a refueling and complex overhaul of the U.S.S. George
Washington (CVN-73).
(2) Up to $650,000,000 for the ship construction of a San Antonio class amphibious ship.
(b) Determination- A determination described in this subsection is a determination by the
Secretary of the Navy that—
Congressional Research Service
33

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

(1) unobligated balances are available in the program or programs from which funds will be
transferred pursuant to subsection (a) due to slower than expected program execution; and
(2) the transfer of funds will fill a high priority military need and is in the best interest of the
Department of the Navy.
(c) Contingent Authorization- The Secretary of the Navy is authorized to enter into a contract
for the procurement of one San Antonio class amphibious ship beginning in fiscal year 2015,
and to use incremental funding for the procurement of that ship, if additional funds are made
available for such purpose in fiscal year 2015 and the Secretary determines that such
procurement will fill a high priority military need and is in the best interests of the
Department of the Navy.
(d) Effect on Authorization Amounts- A transfer made from one account to another under the
authority of this section shall be deemed to increase the amount authorized for the account to
which the amount is transferred by an amount equal to the amount transferred.
(e) Construction of Authority- The transfer authority under this section is in addition to any
other transfer authority provided in this Act.
Regarding Section 123, S.Rept. 113-176 states:
Authority to transfer certain funds for refueling of aircraft carrier and construction of
amphibious ship (sec. 123)

The committee recommends a provision that would authorize the Secretary of the Navy to
transfer funds available in the Shipbuilding and Conversion, Navy (SCN), or other Navy
procurement account for either or both of the following purposes:
(1) Up to $650.0 million to conduct a refueling and complex overhaul of the USS
George Washington (CVN–73).
(2) Up to $650.0 million to build a San Antonio-class amphibious ship.
The provision would require that the Secretary make a determination that unobligated
balances to be transferred are available due to slower than expected program execution, and
the transfer of funds will fill a high priority military need and is in the best interest of the
Department of the Navy.
It is the committee’s intent that the Navy proceed with the refueling and complex overhaul of
the USS George Washington (CVN–73) should additional funds be made available in fiscal
year 2015 for that purpose.
Finally, the provision would authorize the Secretary to use incremental funding for a San
Antonio-class ship if additional funds are made available in fiscal year 2015 for that purpose
and the Secretary determines that such procurement will fill a high priority military need and
is in the best interest of the Department of the Navy.
The committee expects that, if the Secretary chooses to transfer funds for the San Antonio-
class program in fiscal year 2015, the Secretary will use funds from fiscal year 2015 and
fiscal year 2016 to fully fund any new San Antonio-class ship put on contract during fiscal
year 2015 or fiscal year 2016. (Pages 8-9)
Section 1021 of S. 2410 as reported states:
Congressional Research Service
34

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

SEC. 1021. LIMITATION ON USE OF FUNDS FOR INACTIVATION OF U.S.S.
GEORGE WASHINGTON.
No funds authorized to be appropriated by this Act or otherwise made available for fiscal
year 2015 for the Navy may be obligated or expended to conduct tasks connected to the
inactivation of the U.S.S. George Washington (CVN-73) unless such tasks are identical to
tasks that would be necessary to conduct a refueling and complex overhaul of the vessel.
Regarding Section 1021, S.Rept. 113-176 states:
Limitation on use of funds for inactivation of U.S.S. George Washington (sec. 1021)
The committee recommends a provision that would prevent the Navy from obligating or
expending any funds in fiscal year 2015 on inactivating the U.S.S. George Washington
(CVN–73) unless such obligation or expenditure is to support tasks that are identical to tasks
that would be necessary to conduct a refueling complex overhaul (RCOH) of the ship.
The Navy had planned to conduct an RCOH on CVN–73, beginning in fiscal year 2016. The
fiscal year 2015 budget request altered that plan to drop the RCOH and inactivate CVN–73.
Congress has already authorized and appropriated $329.7 million for the CVN–73 RCOH.
The plan for fiscal year 2015 submitted with the fiscal year 2014 budget for the Navy was to
request another $491.1 million for advance procurement of the CVN–73 RCOH.
In lieu of the plan, the fiscal year 2015 budget request and the future years defense program
(FYDP) supports inactivation of CVN–73. Department of Defense (DOD) officials have
stated DOD will defer the decision until 2016 on whether to refuel and maintain CVN–73 or
inactivate the ship.
The committee is concerned that DOD submitted a fiscal year 2015 budget request and
FYDP that are inconsistent with DOD’s stated intent to defer a decision on the refueling, and
with the requirement of section 5062(b) of title 10, United States Code, that the Navy
maintain 11 operational aircraft carriers.
In testimony, Secretary of Defense Charles Hagel confirmed that 11 carriers are a statutory
requirement saying, “We follow the authorization and appropriations direction of Congress.
We follow the law.” Secretary Hagel explained the dichotomy between an avowed plan to
maintain 11 operational aircraft carriers and the FYDP by saying he was waiting for a sign
from someone, presumably Congress, that DOD would get the partial relief from the effects
of sequestration reflected in the FYDP.
The committee has seen no evidence that the requirement for maintaining 11 operational
carriers has diminished. In fact, senior Navy leaders have repeatedly stated the need for 11
carriers as the minimum number required to execute the President’s National Military
Strategy. Senior military officers have testified that global requirements argue for an even
larger number of aircraft carriers. The Commander of U.S. Pacific Command noted that,
“Based on the world as it is, about 11 aircraft carriers is just—is just barely making it today.”
The aircraft carrier remains the most visible projection of military force abroad and is an
effective instrument for shaping the perception of allies and potential foes alike. The
committee is concerned that inactivating an aircraft carrier with 20 to 30 years of useful
service life remaining is a very inefficient use of defense resources and would be inconsistent
with implementing the administration’s strategic shift toward the Asia-Pacific region, and
such an action would send the wrong signals about our determination to support that shift.
Congressional Research Service
35

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Complying with the letter of this section requires that the administration either submit a
budget that supports a fleet with 11 operational aircraft carriers or submit a legislative
proposal to amend title 10 to readjust the requirement. The administration has done neither.
This provision would ensure that the Navy maintains a path of obligations and expenditures
consistent with the statutory requirement to maintain 11 operational aircraft carriers.
The committee directs the Secretary of the Navy to report on the effect on capabilities for
power projection and global engagement, as it affects the Navy’s ability to meet the Defense
Strategic Guidance, moving to a permanent force structure of fewer than 11 operational
carriers. This report should include a classified annex that describes the Navy’s ability to
meet the combatant commanders’ requirements, both at the current force level and the
impact of a force level with fewer than the required 11 operational carriers. This report
should also specify what the effects of such action would be on operational deployments,
overall readiness, and on sailors and their families. The report should identify potential
effects on the shipbuilding industrial base, on the remainder of the RCOH program, on other
shipbuilding programs, and on other acquisition programs. The Secretary of the Navy should
submit that report with the fiscal year 2016 budget request. (Pages 164-165)
Final Version
CVN-78 Program
The joint explanatory statement for the FY2015 National Defense Authorization Act (H.R. 3979)
recommends approving the Navy’s request for FY2015 procurement funding for the CVN-78
program (PDF page 375 of 513, lines 001 and 021).
CVN-73 RCOH
The joint explanatory statement also recommends $483.6 million for the refueling complex
overhaul (RCOH) of the aircraft carrier George Washington (CVN-73) (PDF page 375 of 513,
line 004). As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged
as an issue in Congress’s review of DOD’s proposed FY2015 budget.
Section 1023 of H.R. 3979 states:
SEC. 1023. LIMITATION ON USE OF FUNDS FOR INACTIVATION OF U.S.S.
GEORGE WASHINGTON.
No funds authorized to be appropriated by this Act or otherwise made available for fiscal
year 2015 for the Navy may be obligated or expended to conduct tasks connected to the
inactivation of the U.S.S. George Washington (CVN-73) unless such tasks are identical to
tasks that would be necessary to conduct a refueling and complex overhaul of the vessel.
Regarding Section 1023, the joint explanatory statement states:
Limitation on use of funds for inactivation of U.S.S. George Washington (sec. 1023)
The House bill contained a provision (sec. 1024) that would prohibit spending more than 50
percent of the funds authorized and appropriated for the Office of the Secretary of Defense
until the Secretary of Defense obligates funds for commencing, planning, and buying long
lead time materials for the refueling and complex overhaul of the USS George Washington
(CVN-73).
Congressional Research Service
36

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

The Senate committee-reported bill contained a similar provision (sec. 1021) that would
prohibit spending any funds for inactivation of the USS George Washington unless such
tasks are identical to tasks that would be necessary to conduct a refueling and complex
overhaul of the vessel.
The agreement includes the Senate provision.
We note that the administration did not include a budget request to support the nuclear
refueling and complex overhaul of the USS George Washington (CVN-73) in fiscal year
2015. In a report to Congress titled “Estimated Impacts of Sequestration- Level Funding”
dated April 2014, the Department of Defense indicated that “if Congress acts to support
outyear funding at the PB15 level, the additional $6.3B necessary to retain CVN 73 would be
reflected in next year’s budget.”
Consistent with section 5062 of title 10, United States Code, and multiple testimonies from
the combatant commanders, we believe that Congress has been unambiguous about the
support of 11 operational aircraft carriers and have provided sufficient authorization of
appropriations in this Act to maintain this carrier force structure. We fully anticipate that the
administration will support a budget request for fiscal year 2016 that is consistent with title
10, United States Code. (PDF pages 155-156 of 513.)
FY2015 DOD Appropriations Act (Division C of H.R. 83/P.L. 113-
235)

House
CVN-78 Program
The House Appropriations Committee, in its report (H.Rept. 113-473 of June 13, 2014) on the
FY2015 DOD Appropriations Act (H.R. 4870), recommends reducing by $10.575 million the
Navy’s request for FY2015 procurement funding for the CVN-78 program, with the reduction
being for “CANES [Consolidated Afloat Networks and Enterprise Services] cost growth” ($2.051
million); “CANES system engineering growth” ($1.543 million); “Digital modular radio cost
growth” ($1.092 million); “IFF [Identification Friend or Foe system] cost growth” ($1.573
million); SPN-46 [radar] cost growth” ($1.473 million); and “Technical engineering services
growth” ($2.843 million). (Page 163, lines 1 and 21, and page 164, line 1.)
CVN-73 RCOH
The report recommends $491.1 million for the refueling complex overhaul (RCOH) of the aircraft
carrier George Washington (CVN-73). (Page 163, unnumbered line below line 3, and page 164,
line 5.) As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as
an issue in Congress’s review of DOD’s proposed FY2015 budget.
H.Rept. 113-473 states:
AIRCRAFT CARRIER REFUELING
The Navy includes no funding in the fiscal year 2015 budget request for the refueling of the
aircraft carrier USS George Washington (CVN–73). While the Secretary of the Navy
Congressional Research Service
37

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

explained this as a cost saving measure and a deferral of the actual refueling decision, the
Committee believes it to be a shortsighted position since the Congress has already
appropriated in excess of $500,000,000 towards the effort. The George Washington will
have half of its service life remaining after being refueled. Nearly $3,000,000,000 was
invested for the construction of the George Washington in 1983, and the Committee believes
that walking away from the George Washington halfway through its service life is
shortsighted. The Committee is also concerned with the Navy’s lack of budgetary discipline,
sending a fiscally broken program to Congress for the second consecutive year. Last year,
the Secretary of the Navy did not fully fund the procurement of the two submarines
requested, forcing Congress to provide nearly $1,000,000,000 to fully fund the program.
Again this year, the Committee must provide $789,300,000 to maintain the CVN–73
refueling schedule, despite the Navy’s claim it can simply defer the decision to fiscal year
2016. Therefore, the Committee provides $789,300,00030 to maintain the CVN–73 refueling
schedule, and directs the Secretary of the Navy to fully fund the remaining cost of the CVN–
73 refueling in fiscal year 2016. (Pages 165-166)
Senate
CVN-78 Program
The Senate Appropriations Committee, in its report (S.Rept. 113-211 of July 7, 2014) on H.R.
4870, recommends reducing by $70 million the Navy’s request for FY2015 procurement funding
for the CVN-78 program (page 138, line 1), with the reduction being for “Restoring acquisition
accountability: Contracting efficiencies” (page 139, line1).
S.Rept. 113-211 states:
CVN 79.—The Committee understands that in light of significant cost overruns on CVN 78,
USS Ford, the Navy is working diligently to reduce costs of the follow-on ship of the class,
CVN 79, USS Kennedy. The Committee further understands that this includes innovative
contracting strategies leading to greater competition. The Committee commends the Navy
for this approach and believes that additional savings could be achieved as a result of
increased competitive acquisition strategies. (Page 140)
CVN-73 RCOH
The report recommends $483.6 million for the refueling complex overhaul (RCOH) of the aircraft
carrier George Washington (CVN-73). (Page 138, unnumbered line below line 3, and page 139,
line 5.) As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has emerged as
an issue in Congress’s review of DOD’s proposed FY2015 budget. S.Rept. 113-211 states:
CVN 73 REFUELING AND COMPLEX OVERHAUL [RCOH]
The fiscal year 2015 budget request includes no funds to continue the refueling and complex
overhaul of CVN 73, USS George Washington. The Committee notes that $329,700,000 has
previously been appropriated in the Shipbuilding and Conversion, Navy account for the
CVN 73 RCOH to support the aircraft carrier’s drydock induction in September 2016. With

30 This figure includes $491.1 million in the Shipbuilding and Conversion, Navy (SCN) appropriation account plus
additional funding elsewhere in the Navy’s budget that supports the CVN-73 RCOH.
Congressional Research Service
38

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

the fiscal year 2015 budget submission, the Navy announced its intention to make a decision
with the fiscal year 2016 budget submission as to whether to refuel or prematurely retire
CVN 73. The Committee understands that deferring this decision creates significant
programmatic and operational schedule delays for the RCOH.
CVN 73 has more than 20 years of service life remaining, and the Navy cannot meet all U.S.
combatant commanders’ requirements with the current aircraft carrier fleet. Furthermore,
U.S. law requires the Navy to maintain not less than 11 operational aircraft carries. The
Committee notes that contrary to its previously stated position, the Navy has now decided to
immediately continue CVN 73 RCOH with previously appropriated funds. The Committee
fully supports this decision. Therefore, the Committee recommendation includes an
additional $849,800,000 in the Navy’s military personnel, operation and maintenance,
shipbuilding, and other procurement accounts to fully fund the fiscal year 2015 requirement
for CVN 73 RCOH, which will mitigate the schedule delays caused by the Navy’s inaction.
The Committee expects the Navy to include all remaining funds required to complete the
CVN 73 RCOH in the Future Years Defense Program accompanying the fiscal year 2016
budget submission. (Page 10)
Final Version
CVN-78 Program
The explanatory statement for the FY2015 DOD Appropriations Act (Division C of H.R. 83/P.L.
113-235 of December 16, 2014) reduces the Navy’s request for FY2015 procurement funding for
the CVN-78 program by $80.575 million, consisting of $2.051 million for “CANES
[Consolidated Afloat Networks and Enterprise Services] cost growth,” $1.543 million for
“CANES system engineering growth,” $1.092 million for “Digital modular radio cost growth,”
$1.573 million for “IFF [Identification Friend or Foe system] cost growth,” $1.473 million for
“SPN-46 [radar] cost growth,” $2.843 million for “Technical engineering services growth,” and
$70 million for “Contracting efficiencies” (PDF page 162 of 368, line 1 [where the reductions
occurred] and line 21).
CVN-73 RCOH
The explanatory statement for Division C of H.R. 83/P.L. 113-235 provides $483.6 million for the
refueling complex overhaul (RCOH) of the aircraft carrier George Washington (CVN-73) (PDF
162 of 368, line 5). As discussed in Appendix B, FY2015 funding for an RCOH for CVN-73 has
emerged as an issue in Congress’s review of DOD’s proposed FY2015 budget.

Congressional Research Service
39

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Appendix A. March 2013 Navy Report to Congress
on Construction Plan for CVN-79

This appendix reprints a March 2013 Navy report to Congress on the Navy’s construction plan for
CVN-79.31

31 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, 17 pp. An annotation on
the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was
posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To
Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013.
Congressional Research Service
40


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
41


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
42


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
43


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
44


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
45


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
46


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
47


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
48


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
49


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
50


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
51


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
52


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
53


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
54


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
55


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
56


Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Congressional Research Service
57

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

Appendix B. Refueling Complex Overhaul (RCOH)
for George Washington
(CVN-73)
An additional issue relating to aircraft carriers that has been raised by the Navy’s proposed
FY2015 budget concerns funding for the mid-life nuclear refueling overhaul of the aircraft carrier
George Washington (CVN-73). This appendix presents background information and potential
oversight questions for Congress relating to this issue.
To operate for a full 50-year life, existing Nimitz (CVN-68) class nuclear-powered carriers are
given a mid-life nuclear refueling overhaul, called a refueling complex overhaul (RCOH), when
they are 20 to 25 years old, which is when their original nuclear fuel core has been exhausted.
The RCOH gives the ship a new nuclear fuel core sufficient to power the ship for the remainder
of its 50-year life. The RCOH also involves a significant amount of other overhaul, repair, and
modernization work on the ship. An RCOH requires about 44 months from contract award to
delivery. RCOHs are funded through the Navy’s shipbuilding account (the Shipbuilding and
Conversion, Navy [SCN] appropriation account).
RCOHs are done primarily at Huntington Ingalls Industries/Newport News Shipbuilding
(HII/NNS) in Newport News, VA, and form a significant part of HII/NNS’s business base, along
with construction of new nuclear-powered aircraft carriers and construction of new nuclear-
powered submarines. RCOHs in recent years have been scheduled in a more or less heel-to-toe
fashion at HII/NNS—when one RCOH is done, the next one is scheduled to begin soon
thereafter. RCOHs are done in a particular dry dock at HII/NNS, so a carrier undergoing an
RCOH in that dry dock must have its work finished and depart the dry dock before the following
carrier can be moved into the dry dock for its RCOH.
The next carrier scheduled for an RCOH is the George Washington (CVN-73). The total
estimated cost of the CVN-73 RCOH in the Navy’s FY2014 budget submission was $4,738.2
million (i.e., about $4.7 billion).
Until the FY2015 budget submission, the CVN-73 RCOH was scheduled for FY2016. The CVN-
73 RCOH received $12 million in advance procurement (AP) funding in FY2012, $69.9 million
in AP funding in FY2013, and $245.8 million in AP funding in FY2014. Under the Navy’s
FY2014 budget submission, another $491.1 million in AP funding was projected for FY2015, and
the balance of the RCOH’s estimated cost of $4,738.2 million was to be provided in FY2016 and
FY2017.
As part of its FY2015 budget submission, DOD removed funding for the CVN-73 RCOH from
the FY2015-FY2019 Future Years Defense Plan (FYDP) and is proposing to defer the question of
whether to proceed with the CVN-73 RCOH until next year, when Congress will consider the
FY2016 defense budget. The Navy’s proposed FY2015 budget includes about $46 million in
funding in the Operation and Maintenance, Navy (OMN) appropriation account to defuel CVN-
73. Defueling the ship (i.e., removing the original nuclear fuel core) is an initial step to be
performed on the ship at NNS, regardless of whether the ship is to undergo an RCOH or be
inactivated.
DOD and Navy officials state that if Congress provides an indication this year that it supports the
defense spending levels in the FY2015-FY2019 FYDP, which are higher than those called for in
the Budget Control Act of 2011 as amended, then the FYDP would be reformulated for FY2016
Congressional Research Service
58

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

and subsequent years to include the roughly $7.0 billion in additional funding that would be
needed over the FYDP to fund the CVN-73 RCOH and keep the ship and its associated carrier air
wing in service.32 Of this $7.0 billion in additional funding, $796.2 million would be required in
FY2015.33
DOD and Navy officials state that if Congress does not provide an indication this year that it
supports the defense spending levels in the FYDP, CVN-73 would instead be inactivated (i.e.,
permanently retired from service), and its associated air wing would be disestablished. Other
things held equal, inactivating CVN-73 would reduce the Navy’s carrier force to 10 ships for the
next 25 years or so (i.e., the period of time that CVN-73 would have remained in service if it had
received an RCOH).
The Navy states that, of the funding for the CVN-73 RCOH that was provided in FY2012 and
FY2013, $20.6 million represent sunk costs that would not be recoverable if CVN-73 were not to
receive an RCOH. The Navy states that this $20.6 million “primarily supported prime contractor
and government initial planning efforts for the refueling overhaul as well as some initial
modernization GFI [government-furnished information] development efforts.”34
Navy officials state that deferring until next year the decision on whether to proceed with the
CVN-73 RCOH would mean that the RCOH, if were to occur, would be delayed some number of
months from the schedule shown in the Navy’s FY2014 budget submission, and consequently
would likely become an FY2017 action rather than an FY2016 action. Navy officials state that if
the delay in the start of the RCOH were not more than a certain number of months, it would not
cause a cascading delay in the schedule for the following RCOH (to be done on CVN-74),
because there is currently some slack time on the back end of the CVN-73 RCOH period to
absorb some delay in the CVN-73 RCOH without affecting the schedule for the CVN-74 RCOH.
10 U.S.C. 5062(b) states that “The naval combat forces of the Navy shall include not less than 11
operational aircraft carriers.” The requirement as stated in this statute is not contingent on the
DOD budget being at a certain level in coming years. To the contrary, the central purpose of 10
U.S.C. 5062(b) is to act as a mandate to the executive branch to support force of not less than 11
carriers in executive branch planning, regardless of budgetary or other circumstances. DOD has
not, as part of its FY2015 budget submission, requested that 10 U.S.C. 5062(b) be amended or
repealed.
Potential oversight questions for Congress include the following:
• Is DOD’s proposal to treat the issue of whether to proceed with the CVN-73
RCOH (and consequently whether there are to be 10 or 11 carriers for the next 25

32 The estimated total cost to perform the CVN-73 RCOH and retain the carrier and its associated air wing is about $8.1
billion. (This figure includes about $5.9 to perform the RCOH and keep the ship in service, about $1.4 billion to retain
the air wing, and about $800 million for associated logistics, manpower, and training costs.) The FY2015-FY2019
FYDP currently includes about $1.1 billion to support the inactivation of CVN-73. Reprogramming this $1.1 billion in
inactivation funding to support the RCOH would leave a requirement for about $7.0 billion in additional funding.
Source: Navy information paper provided to CRS by Navy Office of Legislative Affairs on April 7, 2014.
33 The total estimated requirement for FY2015 is $842.2 million. This figure includes the $46 million currently in the
budget for the ship’s defueling, leaving a net requirement of $796.2 million in additional funding for FY2015. Source:
Navy information paper provided to CRS by Navy Office of Legislative Affairs on April 7, 2014.
34 Source: Navy information paper dated March 13, 2014, and provided to CRS by the Navy Office of Legislative
Affairs on April 17, 2014.
Congressional Research Service
59

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

years or so) as a question to be decided next year, depending on indications of
congressional support for a certain DOD budget level in coming years, consistent
with 10 U.S.C. 5062(b)? Does DOD’s proposal in effect treat the 11-carrier
requirement in 10 U.S.C. 5062(b) as an optional matter rather than a mandate? If
so, would this create a precedent for the executive branch to treat similar
provisions in the U.S. Code as optional matters rather than mandates? For
example, would it create a precedent for DOD, if it so desired, to begin treating
as an optional matter the long-standing requirement in 10 U.S.C. 5063(a) that the
Marine Corps “shall be so organized as to include not less than three combat
divisions and three air wings, and such other land combat, aviation, and other
services as may be organic therein?” If the executive branch were to begin
treating statutory provisions like 10 U.S.C. 5062(b) as optional matters rather
than mandates, what implications might this have for policy and program
execution, and for Congress’s power to legislatively establish policy and program
goals?
• What would be the operational impact for the Navy of reducing the carrier force
to 10 ships for the next 25 years or so (and also eliminating its associated carrier
air wing)? What impact would it have on the Navy’s ability to fulfill its missions?
• If the FDYP were reformulated to include the $7 billion in additional funding
needed to keep CVN-73 and its associated air wing, what other defense programs
would have their funding reduced, and what would be the impact of these
reductions on DOD’s ability to fulfill its missions?
• What would be the impact on HII/NNS and the other parts of the aircraft carrier
industrial base if CVN-73 were inactivated rather than given an RCOH? What
impact, if any, would this have on the cost of other work performed at NNS
during these years, and on the eventual cost of the CVN-74 RCOH?35
A July 7, 2014, press report states:
The Navy will move forward with the refueling of the aircraft carrier George Washington,
reversing a previous plan to decide next year whether to retire the vessel.
“We are moving forward to begin the [refueling and complex overhaul] process,” a Navy
official told Inside the Navy July 1. “We have had several senators express interest in the
carrier and therefore we are able to move forward.”36
A July 11, 2014, press report states:
The U.S. Navy’s chief shipbuilder told Congress the service plans to reshuffle $7 billion in
funds to refuel and maintain the nuclear aircraft carrier USS George Washington (CVN-73).

35 For press reports discussing the industrial-base aspects of the issue, see Lara Seligman, “Shipbuilder: Navy’s
Timeline For CVN-73 ‘Not In Accordance With Our Plan,’” Inside the Navy, March 24, 2014; Olga Belogolova, “PEO
Carriers: A Cut From 11 To 10 Carriers Would Impact Industrial Base,” Inside the Navy, February 24, 2014; Michael
Fabey, “Foregoing Carrier RCOH Won’t Disrupt Future Work, HII CEO Says,” Aerospace Daily & Defense Report,
March 25, 2014: 4; Rick Giannini and Darrell Grow, “Why Aircraft Carrier Workers Deserve a Better Plan from the
Pentagon,” Defense One (www.defenseone.com), March 23, 2014.
36 Lara Seligman, “Navy Reverses Course, Plans To Begin GW Carrier Refueling Process,” Inside the Navy, July 7,
2014.
Congressional Research Service
60

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress

The fate of the carrier was an open question at the start of the year due to ongoing military
funding pressures.
“We are today making every effort to replan near $7 billion required across the [Future Years
Defense Plan] to refuel the carrier plus maintain its airwing, manpower and support,” Sean
Stackley, Assistant Secretary of the Navy for Research, Development & Acquisition (RDA),
told the House Armed Services Subcommittee on Seapower and Projection Forces in a
Thursday [July 10] hearing.
“We’ve released the balance of advance procurement funding for 2014 to continue planning
efforts in order to best maintain our options and retain skilled labor at the shipyard while we
await determination by Congress regarding sequestration in 2016. Yet, this also increases the
pressure on other programs.”...
Stackley said since Hagel’s February announcement there were enough positive signs from
Congress to allow the Navy to go ahead with the RCOH plan as part of its FY 2016 budget—
currently being prepared by the service.
“The signal today is strong enough that says we need to go ahead and proceed to the next
step of releasing funding and go into the negotiations with the ship yard to start the planning
effort per the refueling portion of a complex overhaul,” Stackley told USNI News following
the Thursday hearing.
“We’re in the middle of the 2016 budget bill today and we’re in the process of building a
budget that anticipates Congress’ action that will support a change to BCA and sequestration.
We’re moving out in anticipation of a future congressional action because we can’t wait until
a year from now to build that budget.[”]...
Representatives from Huntington Ingalls Industries, the company the contractor for the four
year RCOH, was cautiously optimistic following Stackley’s comments.
“While we are pleased to see positive momentum toward funding the RCOH, however this is
a complex process that we will continue to monitor,” according to a HII statement provided
to USNI News.37
An August 11, 2014, press report states:
The [Navy] has released the balance of fiscal year 2014 funds appropriated for the advanced
planning contract, and expects to execute the full refueling and complex overhaul (RCOH)
for the ship in March 2017, Navy spokesman Dale Eng wrote in a statement emailed to
Inside the Navy on Aug. 4.
“The Department of the Navy has released the balance of FY-14 funds appropriated for the
advanced planning contract for USS George Washington (CVN-73) and awarded the contract
for this effort. Pending authorization and appropriation of future year funding, we expect to
execute the George Washington [RCOH] in March 2017,” Eng wrote.38

37 Sam LaGrone, “Stackley: Navy Plans to Refuel Carrier George Washington,” USNI News (http://news.usni.org), July
10 (updated July 11), 2014. See also Christopher P. Cavas, “A Reprieve for GW?” Defense News
(www.defensenews.com)
, June 30, 2014.
38 Lara Seligman, “Navy Awards HII $49.6 Million Contract To Begin Work On Carrier Defueling,” Inside the Navy,
August 11, 2014.
Congressional Research Service
61

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress


Author Contact Information

Ronald O'Rourke

Specialist in Naval Affairs
rorourke@crs.loc.gov, 7-7610


Congressional Research Service
62