Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Summary
The U.S. Army Corps of Engineers undertakes activities to maintain navigable channels, reduce
flood and storm damage, and restore aquatic ecosystems. Congress directs the Corps through
authorizations, appropriations, and oversight of its studies, construction projects, and other
activities. This report summarizes congressional authorization and appropriations processes for
the Corps. It also discusses agency activities under general authorities.
Omnibus Authorization Legislation. Congress generally authorizes numerous Corps activities
and provides policy direction in an omnibus Corps authorization bill, typically called the Water
Resources Development Act (WRDA) or more recently the Water Resources Reform and
Development Act (WRRDA). A WRRDA 2014 (P.L. 113-121) was enacted on June 10, 2014.
WRDAs historically are omnibus bills including many provisions for site-specific activities. How
to construct a WRDA bill that complied with House rules related to a moratorium on earmarks
complicated WRDA consideration in the 112th Congress, but these issues were resolved in the
113th Congress.
Agency Appropriations. Federal funding for Corps civil works activities is provided in annual
Energy and Water Development appropriations acts or supplemental appropriations acts. Annual
Corps civil works appropriations have ranged from $4.5 billion to $5.5 billion during the last
decade. An increasing share of the agency’s appropriations is used for operations and
maintenance. Another trend has been increasing emergency supplemental appropriations. From
1987 to 2013, Congress appropriated $32.2 billion in Corps supplemental funding. Of this
funding, $30.8 billion came through acts passed between 2003 and 2013. This funding was more
than half of the Corps’ regular appropriations over the same period ($55 billion). In part because
of competition for funds and because Corps authorizations outpace appropriations, many
authorized activities have not received appropriations. There is a backlog of more than 1,000
authorized studies and construction projects. In recent years, few new studies and new
construction activities have been in either the President’s budget request or enacted
appropriations.
Standard Project Development. The standard process for a Corps project requires two separate
congressional authorizations—one for investigation and one for construction—as well as
appropriations. The investigation phase starts with Congress authorizing a study; if it is funded,
the Corps conducts an initial reconnaissance study followed by a more detailed feasibility study.
Congressional authorization for construction is based on the feasibility study. For most activities,
Congress requires a nonfederal sponsor to share some portion of study and construction costs.
These cost-sharing requirements vary by the type of project. For many project types (e.g., levees),
nonfederal sponsors are responsible for operation and maintenance once construction is complete.
Other Corps Activities and Authorities. Although the project development process just
described is standard, there are exceptions. Congress has granted the Corps some general
authorities to undertake some studies, small projects, technical assistance, and emergency actions
such as flood-fighting, repair of damaged levees, and limited drought assistance. Additionally, the
Corps conducts emergency response actions directed by the Federal Emergency Management
Agency.
Congressional Research Service

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Contents
Army Corps of Engineers ................................................................................................................ 1
Corps Authorizations ....................................................................................................................... 1
Corps Authorization Legislation in Recent Decades ................................................................. 2
Energy and Water Development Appropriations ............................................................................. 2
Standard Corps Project Delivery Process ........................................................................................ 4
Study Authority to Initiate a Corps Project ................................................................................ 5
Reconnaissance Study ............................................................................................................... 6
Feasibility Study and Construction Authorization ..................................................................... 6
Cost Shares for Construction and Operation and Maintenance ........................................... 7
Engineering and Design ............................................................................................................ 7
Changes After Construction Authorization ................................................................................ 7
Study and Project Deauthorization ............................................................................................ 8
Other Corps Activities and Authorities ............................................................................................ 9
Small Projects Under Continuing Authorities Programs ........................................................... 9
Technical Assistance ................................................................................................................ 11
Natural Disaster and Emergency Response Activities ............................................................. 11
National Response Framework Activities Under FEMA .................................................. 11
Flood-Fighting and Emergency Response ........................................................................ 12
Repair of Damaged Levees and Other Flood and Storm Projects ..................................... 12
Environmental Infrastructure/Municipal Water and Wastewater Projects ............................... 13

Tables
Table 1. Corps Project Phases, Average Phase Duration If Fully Funded, and Federal
Cost Share ..................................................................................................................................... 5
Table 2. Standard Cost-Shares for Construction and Operation of New Corps Projects ................. 8
Table 3. Select Corps Continuing Authorities Programs (CAP) for Small Projects ...................... 10
Table 4. Corps Technical Assistance Authorities ........................................................................... 11

Appendixes
Appendix. Evolution of the Its Civil Works Mission ..................................................................... 15

Contacts
Author Contact Information........................................................................................................... 17

Congressional Research Service

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Army Corps of Engineers
The U.S. Army Corps of Engineers is an agency in the Department of Defense with both military
and civil works responsibilities. Under its civil works program, it plans, builds, operates, and
maintains a wide range of water resource facilities. Its civil works responsibilities are principally
to support navigation, reduce flood and storm damage, and protect and restore aquatic
ecosystems.1 The agency attracts congressional attention because its projects can have significant
local and regional economic benefits and environmental effects. The civil works program is led
by a civilian Assistant Secretary of the Army for Civil Works. A military Chief of Engineers
oversees the Corps’ civil and military operations and reports on civil works matters to the
Assistant Secretary for Civil Works. A Director of Civil Works reports to the Chief of Engineers.
The Corps’ civil works responsibilities are organized under eight divisions that are further divided
into 38 districts.2
This report provides an overview of the Corps civil works program, including congressional
authorization and appropriations. The report also covers the standard project development process
for Corps projects and other Corps activities and authorities. For an analysis of the Water
Resources Reform and Development Act of 2014 (WRRDA 2014, P.L. 113-121) and how it
evolved during congressional deliberations, see CRS Report R43298, H.R. 3080 and S. 601:
Comparison of Select Provisions and Conference Developments
, by Nicole T. Carter et al.
Corps Authorizations
The Corps must be authorized to undertake an activity; the authorization can be project-specific,
programmatic, or general.3 While necessary, authorizations are usually insufficient for a Corps
study or construction project to proceed; action on an authorization requires funding.
In recent decades, Congress has legislated on most Corps authorizations in omnibus Water
Resources Development Acts (WRDAs).4 Authorizations at times have appeared in
appropriations or supplemental appropriations legislation, especially in years when a WRDA is
not enacted. If authorizations are included in an appropriations bill, they could be subject to a
point of order on the floor for being non-germane.

1 Other Corps responsibilities include flood emergency and natural disaster response, such as flood-fighting, repair to
damaged levees, and emergency water supply assistance. Congress also has authorized Corps participation in select
environmental infrastructure projects (e.g., municipal water and wastewater treatment systems) and other nontraditional
activities. The Appendix provides more on the evolution of Corps civil works missions and authorities.
2A division map and district links are available at http://www.usace.army.mil/about/Pages/Locations.asp.
3 While most Corps authorizations are in legislation, many studies are undertaken under other authorities. Authorizing
committees can authorize a study to reexamine a geographic area previously studied by the Corps for a similar purpose;
this authority derives from §4 of the Rivers and Harbors Act of 1913 (37 Stat. 801, 33 U.S.C. §542). Similarly, some
studies reviewing operations of completed projects proceed under general study authorizations without congressional
action; this is pursuant to §216 of the Flood Control Act of 1970 (P.L. 91-611, 33 U.S.C. §549a).
4 WRDAs are distinguished from each other by referencing the year of enactment; that is, WRDA 1986 refers to the act
passed in 1986. The authorizing committee generally develops a bill for introduction by the chairperson; alternatively,
the Administration can propose a bill for congressional consideration. Once a committee of jurisdiction—the House
Transportation and Infrastructure Committee or the Senate Environment and Public Works Committee—decides to
consider a WRDA or similar legislation, Members of Congress often may request inclusion of particular provisions. If
the Administration proposes a WRDA, Congress generally receives the proposal at the same time as the President’s
budget. More than a decade has passed since the last Administration-proposed WRDA bill.
Congressional Research Service
1

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

WRDAs, or more recently the Water Resources Reform and Development Act of 2014, authorize
Corps studies, projects, and programs and establish policies for Corps civil works activities (e.g.,
nonfederal cost-share requirements). A WRDA is not a reauthorization bill, but an authorization
bill. That is, WRDAs generally authorize new activities which are added to the pool of existing
authorized activities. Most project-specific authorizations in WRDAs fall into three general
categories: project studies, construction projects, and modifications to existing project
authorizations. WRDAs also may be used to deauthorize projects or establish deauthorization
processes.
WRDAs do not appropriate funds for activities; project funding is provided typically through the
annual appropriations process for the agency. That is, congressional authorizations make certain
projects and activities eligible for receiving federal funding. While use of monies from trust funds
associated with Corps activities generally requires congressional appropriations action (i.e., the
funds are on-budget), a WRDA may be a legislative vehicle for altering trust fund collections and
disbursement policies and procedures.
Corps Authorization Legislation in Recent Decades
Beginning in 1986, a biennial WRDA cycle was loosely followed for a number of years. WRDAs
were enacted in 1988 (P.L. 100-676), 1990 (P.L. 101-640), 1992 (P.L. 102-580), 1996 (P.L. 104-
303), 1999 (P.L. 106-53), 2000 (P.L. 106-541), and 2007 (P.L. 110-114). WRDA 1986 marked the
end of a stalemate between Congress and the executive branch regarding authorizations. It
resolved long-standing disputes related to cost-sharing, user fees, and environmental
requirements. Prior to 1986, disputes over these and other matters had largely prevented
enactment of major civil works legislation since 1970. Biennial authorizations were resumed after
WRDA 1986 to avoid long delays between the planning and execution of projects and so that
Congress could review proposed projects on a regular basis. Pressure to authorize new projects,
increase authorized funding levels, and modify existing projects is often intense, thus promoting a
fairly regular biennial consideration of WRDA, although enactment has been less consistent.
Controversial project authorizations and disagreements over the need for and direction of changes
to the way the Corps plans, constructs, and operates projects contributed to WRDA bills not being
enacted in the 107th, 108th, and 109th Congresses. The 110th Congress enacted WRDA 2007 in
November 2007, overriding a presidential veto. Earmark restrictions complicated WRDA
enactment in the 111th and 112th Congresses. WRRDA 2014 overcame these concerns to authorize
34 construction projects and altered processes and authorization for project delivery, including
expanded opportunities for nonfederal entities to lead projects and for innovative financing. For
more on WRRDA 2014 and how it evolved during congressional deliberations, see CRS Report
R43298, H.R. 3080 and S. 601: Comparison of Select Provisions and Conference Developments,
by Nicole T. Carter et al.
Energy and Water Development Appropriations
The rate of Corps authorizations exceeds the rate of the agency’s annual appropriations.
Consequently, only a subset of authorized activities are included in the President’s budget request
and funded by enacted appropriations. This results in competition for funds among authorized
activities during the appropriations process. To concentrate limited resources and to move
ongoing projects toward completion, budget requests by the George W. Bush and Obama
Administrations have focused funding on projects near completion, and have limited new studies
and projects. Both Administrations also have focused funds on projects within the Corps’ primary
missions of flood and storm damage reduction, navigation, and aquatic ecosystem restoration.
Congressional Research Service
2

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

While this report addresses Corps appropriations in general, the following CRS reports provide
more detailed information and analysis of Corps funding issues:
• CRS Report R43567, Energy and Water Development: FY2015 Appropriations,
coordinated by Carl E. Behrens.
• CRS Report R43069, Energy and Water Development: FY2014 Appropriations,
Preliminary Tables, coordinated by Carl E. Behrens; and
• CRS Report R42841, Army Corps Supplemental Appropriations: Recent History,
Trends, and Policy Issues, by Charles V. Stern and Nicole T. Carter.
Enacted annual Corps civil works appropriations (excluding supplemental appropriations) have
remained steady or increased slightly over the last decade, ranging from $4.5 billion to $5.5
billion in recent years. As the agency’s inventory of infrastructure grows and ages, an increasing
share of the agency’s appropriations is used for operations and maintenance.5
Another trend has been increasing emergency supplemental appropriations for the agency. From
1987 to 2013, Congress appropriated $32.2 billion in supplemental funding to the Corps.6 Of this
funding, $30.8 billion came through supplemental appropriations acts passed between 2003 and
2013. This funding was approximately half of the amount provided to the Corps for regular
appropriations over this same period ($55 billion).
Roughly 85% of the Corps budget is for geographically specified studies or projects. Funding for
geographically specific studies or projects has been requested in the Administration’s budget or
identified in agency-developed work plans (which have been used for FY2011, FY2012, and
FY2013, and FY2014 funding) are not considered congressional earmarks. Prior to FY2011 and
the onset of congressional earmark moratoria, congressional appropriations to the Corps generally
funded a larger set of studies, projects, and maintenance activities (e.g., dredging of low- and
medium-use harbors at specific locations) than proposed by the Administration. This makes the
Corps a significant part of the debate over the impact and efficacy of earmarking (also referred to
as congressionally directed spending).
Most recently, due in part to earmark moratoria, congressionally directed additions have largely
been for broad categories of ongoing activities not included in the President’s budget (e.g.,
additional funding for harbor maintenance), with the Corps responsible for selecting which
projects are funded in agency-developed work plans, based on the direction provided by
Congress.
Few new Corps studies or projects have received funding in recent fiscal years. New activities or
activities that have not recently received funding in Administration requests are often referred to
as “new starts.” Since FY2011, Congress has included in enacted appropriations bills provisions
prohibiting funding for new starts. As a result, the majority of studies and construction projects
authorized in WRDA 2007 remained without federal funding as of 2014. The Consolidated
Appropriations Act, 2014 (P.L. 113-76) provided the Corps with limited funding to initiate a

5 For more information, see U.S. Congress, Senate Energy and Natural Resources, Water and Power, Hearing to
Address Aging Water Resource Infrastructure in the United States
(video), 113th Cong., 1st sess., July 25, 2013,
http://www.energy.senate.gov/public/index.cfm/hearings-and-business-meetings?ID=59c93dec-c9da-4f94-a15f-
be363706c1d4.
6 This includes $5.3 billion in supplemental funds provided for response and recovery related to Hurricane Sandy in
P.L. 113-2.
Congressional Research Service
3

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

maximum of nine new start studies and four new start construction projects. The projects funded
under this provision were subsequently named in the Corps FY2014 work plan.7
Standard Corps Project Delivery Process
The congressional authorization and the appropriations processes are critical steps in a multi-step
process to deliver a Corps project. This section describes the standard study and construction
process for most Corps projects, and some exceptions to the standard process. The standard
process consists of the following basic steps (also see Table 1):
• Study authorization is obtained in WRDA or a committee resolution.
• The Corps performs a preliminary analysis using appropriated funds.8
• The Corps performs a feasibility study if the preliminary analysis is favorable
and funds are appropriated.
• Construction authorization is pursued. The Corps can perform preconstruction
engineering and design while construction authorization is being pursued.
• Congress authorizes construction, and the Corps constructs the project if funds
are appropriated.
The process is not automatic. Appropriations are required to perform studies and undertake
construction; that is, congressional study and construction authorizations are necessary but
insufficient for the Corps to pursue a project. For most activities, the Corps also needs a
nonfederal sponsor to share the study and construction costs. Nonfederal sponsors generally are
state, tribal, county, or local agencies or governments. Although sponsors typically need to have
some taxing authority, some Corps activities can be cost-shared with nonprofit and other entities.
Since WRDA 1986 (P.L. 99-662), nonfederal sponsors are responsible for a significant portion of
the financing of studies, construction, and operation and maintenance (O&M) of most projects.
Generally, projects take longer than the times shown to complete the steps shown in Table 1
because they have to wait for appropriations or congressional authorizations. The Corps has
roughly 200 active feasibility studies; a number are completed or nearing completion.
WRRDA 2014 expanded and consolidated the authorities for nonfederal entities to both perform
studies and construct projects (or elements of projects) that would typically be undertaken by the
Corps and for the cost of these studies and construction to be shared by the federal government
largely as if they had been performed by the Corps. While nonfederal study and project delivery
may increase under these authorities, the process described herein is the standard Corps process
in which the Corps is the manager of the study and project, and the nonfederal sponsor
contributes a portion of the costs and associated real estate, easements, etc.

7 The work plan is available at http://www.usace.army.mil/Portals/2/docs/civilworks/budget/workplan/
fy14wp_cg_rev_5mar14.pdf.
8 Section 1002 of WRRDA 2014 consolidated the contents of the Corps preliminary analysis (which previously was
reported as a separate reconnaissance study) and its feasibility study.
Congressional Research Service
4

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Table 1. Corps Project Phases, Average Phase Duration If Fully Funded,
and Federal Cost Share
Feasibility
Study
(including
Preconstruction
preliminary
Engineering and
Operation &

analysis)

Design (PED)
Construction Maintenance
Avg. Duration (years),
authorized
once congressionally
3a approx.
2 varies
project
authorized and funded
duration
Federal Share of
varies by
varies, see
varies, see
Costs
50%b

project purposec

Table 2

Table 2
Source: CRS.
a. WRRDA 2014 would require most feasibility studies to be completed within three years of initiation and
deauthorize any feasibility study not completed after seven years.
b. Inland waterways feasibility studies are a 100% federal responsibility (33 U.S.C. §2215). These projects are
not considered “local” by their nature. Prior to WRRDA 2014, the preliminary analysis was included within
a reconnaissance study that was produced at 100% federal expenses. Post-WRRDA 2014 cost-sharing of
preliminary analysis has not been clarified. WRDA 2014 established a maximum federal cost of $3 mil ion
for most feasibility studies.
c. Generally PED costs shares are the same as construction cost-shares in Table 2.
Study Authority to Initiate a Corps Project
A Corps project starts with a study of the water resource issue and alternatives to address it. The
purpose of the Corps study process is to inform federal decision-makers on whether there is a
federal interest in authorizing a Corps construction project. The Corps generally requires two
types of congressional action to initiate a study—study authorization and then appropriations.
Interest in Corps assistance with a water resource need often originates with a request from a
local or state government entity or community, business, or other local interests.
If the Corps has performed a study in the geographic area before, a new study can be authorized
by a resolution (known commonly as a “survey resolution”) of either the House Transportation
and Infrastructure Committee or the Senate Environment and Public Works Committee.9 To be
eligible for a resolution authorization, the new study must stay within the scope of the
authorization of the original completed report. If the Corps has not previously investigated,
Congress needs to authorize the study in legislation, typically WRDA.
Once a study is authorized, appropriations are sought through the annual Energy and Water
Development appropriations acts. Within the Corps, projects are largely planned at the district
level, and approved at the division and Corps headquarters. Early in the study process, the Corps
assesses the level of interest and support of nonfederal entities that may be potential sponsors.
The reconnaissance study, feasibility study, and preconstruction engineering and design are
conducted under a single congressional study authorization.

9 To request a study’s inclusion in a resolution, a Member of Congress may send a letter to the chairman of the House
T&I Committee or the Senate EPW Committee. The number of studies authorized by resolution varies by Congress.
The 108th Congress authorized 63 studies via survey resolutions; the 109th Congress authorized 29.
Congressional Research Service
5

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Reconnaissance Study
The reconnaissance study investigates the nature of the water resources problem and assesses the
federal government’s interest. The reconnaissance study also examines the interest of nonfederal
sponsors, who generally are involved in all phases of project delivery. The costs of
reconnaissance studies and their related project study plans generally are limited to $100,000 at
full federal expense. Around one-third of reconnaissance studies eventually lead to feasibility
studies; some 16 of every 100 reconnaissance studies lead to constructed projects.10
Feasibility Study and Construction Authorization
If a nonfederal sponsorship is secured and the Corps recommends proceeding, a feasibility study
begins. The cost of the feasibility study (including related environmental studies) is split equally
between the Corps and the nonfederal project sponsor, as shown in Table 1. The objective of the
feasibility study is to formulate and recommend solutions to the water resources problem
identified in the reconnaissance phase. During the first few months of a feasibility study, the local
Corps district formulates alternative plans, investigates engineering feasibility, conducts benefit-
cost analyses, and assesses environmental impacts under the National Environmental Policy Act
of 1969 (NEPA, 42 U.S.C. §4321).11 The evaluation of federal water resources projects, including
Corps activities, is governed by the 1983 Principles and Guidelines for Water and Related
Resources Implementation Studies
, written by the Water Resources Council, and policy direction
provided in WRDA bills and other enacted legislation.12 An important outcome of the feasibility
analysis is determination of whether the project warrants further federal investment (i.e., whether
it has sufficient national economic development benefits).
The feasibility phase ends when the Chief of Engineers signs a final recommendation on the
project, known as the Chief’s Report. The Corps sends an “informational copy” of the Chief’s
Report to Congress when it transmits the report to the Assistant Secretary and the Office of
Management and Budget (OMB). Since the mid-1990s, Congress has authorized a significant
number of projects based on Chief’s Reports, prior to the projects receiving a full review by the
Assistant Secretary and OMB. At times Congress also has authorized construction of a small set
of projects prior to the availability of informational copies of feasibility studies; these
construction authorizations generally are contingent on a favorable Chief’s Report or a
determination of feasibility by the Secretary of the Army.13

10 General Robert B. Flowers, Army Corps Chief of Engineers, oral statement, Reforms to Address the Corps of
Engineers Feasibility Studies
, hearing before Senate EPW Subcommittee on Transportation and Infrastructure on
March 15, 2001, available at http://epw.senate.gov/stm1_107.htm. More recent statistics are not publicly available.
11 CRS Report R43209, Environmental Requirements Addressed During Corps Civil Works Project Planning:
Background and Issues for Congress
, by Linda Luther, discusses in detail how the Corps study process is combined
with its NEPA compliance process.
12 Available at http://www.usace.army.mil/CECW/Pages/pgr.aspx. Pursuant to WRDA 2007, the Administration is
updating the Principles and Guidelines; information on the revision process is available at http://www.whitehouse.gov/
administration/eop/ceq/initiatives/PandG. In March 2013, Administration’s Council on Environmental Quality (CEQ)
released updated Principles and Guidelines that included a final set of Principles and Requirements that establish broad
principles for federal water resources investments across a number of agencies specified therein, as well as draft
Interagency Guidelines under which agencies like the Corps will develop agency-specific implementation guidelines.
13 WRRDA 2014 authorized 34 new construction projects. Of these 25 had been transmitted by the Assistant Secretary,
and 9 were awaiting the ASA’s transmittal of a completed Chief’s Report when Congress sent the legislation to the
President. WRRDA 2014 did not include authorize any project without a Chief’s Report.
Congressional Research Service
6

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Once construction is authorized and funds appropriated, the Corps typically functions as the
project manager; that is, Corps staff typically are responsible for implementing construction.
While some construction may be performed by Corps personnel and equipment, the majority of
work is contracted out to private engineering and construction contractors. Post-construction
ownership and operations responsibilities depend on the type of project. When construction is
complete, the Corps may own and operate the constructed project (e.g., navigation projects), or
ownership may transfer to the nonfederal sponsor (e.g., most flood damage reduction projects).
Cost Shares for Construction and Operation and Maintenance
The feasibility study also evaluates how construction costs will be split between the federal
government and the nonfederal sponsor. The cost-share responsibilities for construction and
O&M vary by project purpose, as shown in Table 2. Corps projects generally have primary
purposes of navigation, flood and hurricane storm damage reduction, and/or aquatic ecosystem
restoration. The agency also has the authority to undertake activities with other purposes as part
of multi-purpose projects. Table 2 lists these additional project purposes, which can be added to a
project that has at least one of the three primary purposes at its core.
How to allocate the construction and O&M costs of Corps projects among nonfederal sponsors
and the federal government has been debated for decades. WRDA 1986 significantly increased
local cost-share requirements; some subsequent WRDAs made further adjustments in cost
sharing. The waiving of cost-share requirements for individual projects is infrequent and typically
requires specific authorization by Congress.14
Engineering and Design
The study phase—preconstruction engineering and design—that follows the feasibility analysis
takes two years, on average, and is conducted while pursuing congressional authorization for the
project and construction funding (33 U.S.C. §2287). Preconstruction costs are distributed between
the federal and nonfederal sponsor in the same proportion as the cost-share arrangement for the
construction phase. Once the project receives congressional authorization, federal funds for
construction are sought in the annual Energy and Water Development Appropriations Act. The
federal cost share for construction varies by project purpose. Nonfederal parties are responsible
for all operation and maintenance expenses, absent a few exceptions, mainly for harbors and
inland waterways.
Changes After Construction Authorization
A project is likely to undergo some changes after authorization. If project features or the
estimated cost change significantly, additional congressional authorization may be necessary.
Authorization for a significant modification is typically sought in a WRDA. For less significant
modifications, additional authorization is often not necessary. Section 902 of WRDA 1986 as
amended (33 U.S.C. §2280) allows for increases in total project costs of up to 20% without
additional authorization for modifications that do not materially change the project’s scope or
function.

14 Congress has established that the cost shares shall be subject to the nonfederal sponsors’ ability to pay (33 U.S.C.
§2213(m)(2)); however, it is rarely employed. The most recent publicly available guidance on how the Corps
implements the ability to pay provision is from 1989, which is available at http://140.194.76.129/publications/eng-regs/
er1165-2-121/toc.htm. It does not reflect enacted changes in the Corps authority, including those in Section 2019 of
WRDA 2007.
Congressional Research Service
7

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Table 2. Standard Cost-Shares for Construction and Operation
of New Corps Projects
Maximum Federal
Maximum Federal
Project Purpose
Share of Construction
Share of O&M
Navigation


Coastal
Ports—


<20
ft.
harbor
80%a
100%b


20-50 ft. harbor
65%a
100%b
>50
ft.
harbor
40%a
50%b
Inland
Waterways
100%c
100%
Flood and Hurricane Damage Reduction


Inland Flood Control
65%
0%
Coastal Hurricane and Storm Damage Reduction
65%
0%
except Periodic Beach Renourishment
50%
0%
Repair of Damaged Flood and Coastal Storm Projects


Local y Constructed Flood Projects
not applicable
80%d
Federal y Constructed Flood and Coastal Projects
not applicable
100%d
Aquatic Ecosystem Restoration
65% 0%
Multi-Purpose Project Components


Hydroelectric Power
0%e
0%
Municipal and Industrial Water Supply Storage
0%
0%
Agricultural Water Supply Storage
65%f 0%
Recreation at Corps Facilities
50%
0%
Aquatic Invasive Species Control and Prevention
not applicable
30%
Environmental Infrastructure (typically municipal
75%g
0%
water and wastewater infrastructure)
Source: 33 U.S.C. §§2211-2215, unless otherwise specified below.
a. These percentages reflect that the nonfederal sponsors pay 10%, 25%, or 30% during construction and an
additional 10% over a period not to exceed 30 years.
b. Appropriations from the Harbor Maintenance Trust Fund, which is funded by col ections on commercial
cargo imports at federally maintained ports, are used for 100% of these costs.
c. Appropriations from the Inland Waterway Trust Fund, which is funded by a fuel tax on vessels engaged in
commercial transport on designated waterways, are used for 50% of these costs.
d. 33 U.S.C. §701n. Repair assistance is restricted to projects eligible for and participating in the Corps’
Rehabilitation and Inspection Program and to fixing damage caused by natural events.
e. Capital costs initial y are federally funded and are repaid by fees collected from power customers.
f.
For the 17 western states where reclamation law applies, irrigation costs initially are funded by the Corps
but repaid by nonfederal water users.
g. Most environmental infrastructure projects are authorized with a 75% federal cost share; a few have a 65%.
Study and Project Deauthorization
Although WRDAs largely are authorization bills, Congress at times has used WRDAs to
deauthorize projects and establish deauthorization processes. Authorizations of Corps
Congressional Research Service
8

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

construction projects generally are not time-limited; however, there are processes for
deauthorizing them. These include the following:
• WRRDA 2014 created a one-time deauthorization process aimed at deauthorizing
projects that have federal costs to complete of $18 billion; this process is
restricted to project authorized prior to WRDA 2007.
• WRRDA 2014 requires that for projects authorized in WRRDA 2014 projects are
automatically deauthorized if after seven years of enactment no funding had been
obligated for its construction.
• Under 33 U.S.C. Section 579a(b)(2), the Secretary is directed to annually
transmit to Congress a list of authorized projects and project elements with no
obligations of funding during the last full five fiscal years. The project
deauthorization list is published in the Federal Register. If funds are not
obligated for the planning, design, or construction of the project or element
during the next fiscal year, the project or element is deauthorized.15
For studies, there are two deauthorization processes:
• WRRDA 2014 requires that any feasibility study that is not completed seven
years after initiation is automatically deauthorized.
• Under 33 U.S.C. Section 2264, every year the Secretary of the Army is directed
to transmit a list to Congress of incomplete authorized studies that have not
received appropriations for five full fiscal years. The study list is not published in
the Federal Register. Congress has 90 days after submission of the study list to
appropriate funds; otherwise the study is deauthorized16
Other Corps Activities and Authorities
Although the project delivery process described above is standard, there are exceptions. The
Corps has some general authorities to undertake small projects, technical assistance, and
emergency actions. Congress also has specifically authorized the Corps to undertake numerous
municipal water and wastewater projects. These exceptions are described herein.
Small Projects Under Continuing Authorities Programs
The Corps’ authorities to undertake small projects are called Continuing Authorities Programs
(CAPs). Projects under these authorities can be conducted without obtaining a project-specific
study or construction authorization or project-specific appropriations; these activities can be
performed at the discretion of the Corps. For most CAP authorities, Congress has limited the size
and scope of the projects, as shown in Table 3.17 The CAPs are typically referred to by the section
number in the bill where the CAP was first authorized.

15 The Secretary last transmitted a new list of construction projects eligible for deauthorization in 2007; those
deauthorizations became final in 2009. Without a secretarial transmittal of a list, the deauthorization process is not
initiated. There have been no deauthorizations under this authority since 2009.
16 . CRS has no data indicating that studies have been deauthorized through this process in recent years.
17 There is also an authority under 33 U.S.C. §610 for the Corps to control noxious aquatic plant growths at a 70%
federal - 30% nonfederal cost share; the authority is capped at $15 million annually. This authority has not been
operated as a CAP. Most, but not all, of the work under this authority has been for research.
Congressional Research Service
9


Table 3. Select Corps Continuing Authorities Programs (CAP) for Small Projects
(in $ millions)
2011 Est.
2011 Est.
Common
Per-
Annual
Federal
Federal
Name of
Max. Federal
Project
Federal
FY2012
FY2013
Backlog of
Backlog of
the CAP
Construction
Federal
Program
Work
Work
FY2014
Active
Un-started
Authority Eligible
Activities

Cost Share
Limit
Limit
Plan
Plan

Projectsa
Projectsb
§14
Streambank and shoreline
65% $5.0
$20.0
$3.9
$10.1
$4.0
$66.1
$19.1
erosion of public works
and nonprofit services
§103
Beach erosion/ hurricane
65% $5.0
$30.0
$0.9
$0
$2.5
$42.1
$.2
storm damage reduction
§107
Navigation improvements Commercial navigation
$10.0 $50.0 $2.9 $0 $4.7 $119.3 $39.4
varies (see Table 2);
50% for recreational
§111 Prevention/mitigation
of
Same as the project
$10.0 Not $2.9 $0.5 $1.3 $48.6
$0.1
shore damage by federal
causing the damage
Applicable
navigation projects
§204, §207, Regional sediment
65%
$10.0 $50.0 $3.9 $3.8 $7.0 $65.2
$3.2
§993
management/beneficial
use of dredged material
§205 Flood
control
65%
$10.0
$55.0
$18.7
$10.5
$15.0
$312.4 $206.0
§206 Aquatic
ecosystem
65% $10.0
$50.0
$7.9
$19.7
$8.0
$422.6
$142.0
restoration
§208
Removal of obstructions,
65% $0.5
$7.5
$0
$0
$0
$0.4
$1.4
clearing channels for
flood control
§1135
Project modifications for
75% $10.0
$40.0
$7.9
$10.4
$10.5
$166.6
$84.6
improvement of the
environment
Source: CRS, compiled from H.Rept. 111-278; Corps Work Plans for FY2012 and FY2013; Rules Committee Print 113-32 accompanying Consolidated Appropriations Act,
2014 (P.L. 113-76); and other Corps documents, including Appendix F of Planning Guidance Notebook, Engineering Regulation 1105-2-100, and Corps-provided data to
CRS in November 2011.
a. Federal share of active CAP projects (i.e., projects that have received some CAP funds in the last four fiscal years) as of the end of FY2011.
b. Federal share of un-started CAP projects (i.e., nonfederal sponsors have approached the Corps but the project had received no CAP funding as of the end of FY2011.
CRS-10

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

In recent years, Congress has reduced the Corps’ discretion in managing the CAPs by directing
funds to particular CAP projects. Congress also increasingly has authorized specific CAP
projects. Some of these project-specific authorizations under the CAPs are used to apply special
requirements to a project or to ensure that a project is considered eligible under a particular CAP.
WRRDA 2014 requires the Assistant Secretary of the Army to publish prioritization criteria for
the CAP projects and an annual CAP report.
Technical Assistance
Congress has also granted the Corps some general authorities to provide technical assistance. The
Corps does not need project-specific authority to undertake activities that are eligible under the
authorities listed in Table 4.

Table 4. Corps Technical Assistance Authorities
(in $ millions)
Federal
Max.
Share
Annual
Federal
Per-
Federal
FY2012
FY2013
Activities
Cost
Project
Program
Work
Work
Program
Authorized
Share
Limit
Limit
Plan
Plan FY2014
Planning
Technical assistance to
varies $5.0
$30
$5.284 $6.077 $4.0
Assistance
states and communities
annual y
million for
to States
for regional water
per state
state
resources planning,
for state
assistance,
and eligible levee
assistance
$15
system evaluations of
million for
federally authorized
technical
levees
assistance
Flood Plain
Technical assistance on
100% for
Not
$50.0 $9.110 $14.187 $8.0
Management flood and floodplain
eligible
Applicable
Service
issues
activities
Tribal
Studies of water
50%a $1.0 Not $0.957 $0.698 $1.0
Partnership
projects that benefit
Applicable
Program
Indian tribes
Source: CRS, compiled from H.Rept. 111-278; Corps Work Plans for FY2012 and FY2013; Rules Committee
Print 113-32, accompanying Consolidated Appropriations Act, 2014 (P.L. 113-76); and other Corps documents,
including Appendix G of Planning Guidance Notebook, Engineering Regulation 1105-2-100.
a. Section 203 of WRDA 2000 (P.L. 106-541) states that cost sharing shal be subject to the ability of the
nonfederal entity to pay. A draft “Ability to Pay” rule is under development. If finalized, this rule would
apply to these studies. Until then, reductions in nonfederal costs are not to be applied.
Natural Disaster and Emergency Response Activities
National Response Framework Activities Under FEMA
The Stafford Act (42 U.S.C. §5170b) authorizes the Federal Emergency Management Agency
(FEMA) to direct the Department of Defense to provide assistance for a major disaster or under
an emergency declaration by the President. Under the National Response Framework, the Corps
coordinates emergency support for public works and engineering. This includes technical
assistance, engineering, and construction management as well as emergency contracting, power,
Congressional Research Service
11

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

and repair of public water and wastewater and solid waste facilities. The Corps also assists in
monitoring and stabilizing damaged structures and demolishing structures designated as
immediate hazards to public health and safety. It also provides technical assistance in clearing,
removing, and disposing of contaminated and uncontaminated debris from public property, and
establishing ground and water routes into affected areas; contaminated debris management is
coordinated with the U.S. Environmental Protection Agency. The Corps’ funding for these
activities is provided through FEMA appropriations, often through supplemental appropriations.
Flood-Fighting and Emergency Response
In addition to work performed as part of the National Response Framework, Congress has given
the Corps its own emergency response authority. This authority is commonly referred to as the
Corps’ P.L. 84-99 authority, based on the act in which it was originally authorized, the Flood
Control and Coastal Emergency Act. P.L. 84-99 (33 U.S.C. §701n) authorizes the Corps to
perform emergency response and disaster assistance.18 P.L. 84-99 authorizes disaster
preparedness, advance measures, emergency operations (disaster response and post-flood
response), rehabilitation of flood control works threatened by floods, protection or repair of
federally authorized shore protection works threatened by coastal storms, emergency dredging,
and flood-related rescue operations. These activities are limited to actions to save lives and
protect improved property (public facilities/services and residential or commercial
developments). The Corps also has some authorities to assist with select activities during drought.
Most of the Corps disaster response work performed (including the repair program described
below) generally is funded through supplemental appropriations provided directly to the Corps.
Until supplemental appropriations are provided, Congress has provided the Corps with authority
in 33 U.S.C. Section 701n to transfer money from ongoing Corps projects to emergency
operations.
Repair of Damaged Levees and Other Flood and Storm Projects
In P.L. 84-99, Congress also authorized the Corps to rehabilitate damaged flood control works
(e.g., levees) and federally constructed hurricane or shore protection projects (e.g., federal beach
nourishment projects) and to conduct related inspections. This authority is referred to as the
Rehabilitation and Inspection Program (RIP). To be eligible for rehabilitation assistance, the
project must be in active status at the time of damage by wind, wave, or water action other than
ordinary nature.19 Active RIP status is maintained by proper project maintenance as determined
during an annual or semiannual inspection and by the correction of deficiencies identified during
periodic inspections.20 Approximately 14,000 miles of levees participate in RIP—2,250 miles of

18 The Corps also has other limited authorities related to emergency response (e.g., an Emergency Streambank and
Shoreline Erosion Protection program) and recovery (e.g., a Snagging and Clearing for Flood Control program).
19 33 U.S.C. §701n. For more on RIP, see U.S. Army Corps of Engineers, Engineer Regulation 500-1-1, Emergency
Employment of Army and Other Resources Civil Emergency Management Program
.
20 An aspect of RIP implementation receiving attention is the Corps’ guidance on vegetation on levees. Some levee
owners are having difficulty conducting regular maintenance and emergency repairs while also complying with
environmental laws, such as the Endangered Species Act. In some areas, the vegetation on and near levees provides
species habitat and other environmental benefits. WRRDA 2014 provided congressional direction regarding updating
and content of guidance associated with vegetation on levees. This and other environmental issues associated with
levee maintenance are beyond the scope of this report.
Congressional Research Service
12

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

locally constructed and operated levees; 9,650 miles of Corps-constructed, locally operated
levees; and 2,100 miles of federally operated levees.21
For locally constructed projects, 80% of the cost to repair the damage is paid using federal funds
and 20% by the levee owner (as shown in Table 2). For federally constructed projects, the repair
cost is entirely a federal responsibility (except for cost of obtaining the sand or other material
used in the repair). For damage to be repaired, the Corps must determine that repair has a
favorable benefit-cost ratio. Local sponsors assume any rehabilitation cost for damage to an
active project attributable to deficient maintenance.
Environmental Infrastructure/Municipal Water and
Wastewater Projects
Since 1992 Congress has authorized and provided the Corps with funds to assist with design and
construction of municipal drinking water and wastewater infrastructure projects (including
treatment facilities such as recycling and desalination plants, and distribution and collection
facilities such as stormwater collection and recycled water distribution) and surface water
protection and development projects. These projects are broadly labeled environmental
infrastructure
. Although no Administration has included environmental infrastructure in a Corps
budget request since the first authorization in 1992, Congress regularly includes Corps
environmental infrastructure funds in appropriations bills. Environmental infrastructure projects
repeatedly have been called out by various Administrations as a low priority for the agency and
by the co-chairs of the National Commission on Fiscal Responsibility and Reform.22
Most Corps environmental infrastructure projects are authorized for a specific geographic
location (e.g., city or county) under Section 219 of WRDA 1992 (P.L. 102-580), as amended;
however, other similar authorities, sometimes covering regions or states, exist in multiple sections
of WRDAs and in select Energy and Water Development appropriations acts. Management of the
Corps and nonfederal financing varies according to the specifics of the authorization. Under
Section 219, the Corps performs the authorized work; for environmental infrastructure projects
authorized in other provisions, the Corps often can use appropriated funds to reimburse
nonfederal sponsors for work they perform.
Since 1992, Congress has authorized the Corps to contribute to more than 400 of these projects
and programs, with authorized appropriations totaling more than $5 billion. WRRDA 2014
expanded authorizations and their authorization of appropriations for specific environmental
infrastructure activities in multiple states. The Corps received $140 million for environmental
infrastructure projects in FY2010 and $200 million in the American Recovery and Reinvestment
Act of 2009 (P.L. 111-5). The Administration did not fund any environmental infrastructure
activities in its FY2013 work plan. Congress recommended $44 million for these projects in
Rules Committee Print 113-32, accompanying the Consolidated Appropriations Act, 2014 (P.L.
113-76).
Because environmental infrastructure activities are not traditional Corps water resources projects,
they are not subject to the Corps planning process (e.g., a benefit-cost analysis is not performed),

21 Corps data provided to CRS on April 30, 2010. In January 2009, the Corps published a temporary extension of RIP
to locally operated levees with deficient conditions if the owner is making system-wide improvements. It is available at
http://www.iwr.usace.army.mil/nfrmp/docs/HQS-ECOPY3I50-Exchange-01132009-162045.pdf.
22 National Commission on Fiscal Responsibility, CoChairs’ Proposal: $200 Billion in Illustrative Savings, Draft
Document
, November 12, 2010, http://www.fiscalcommission.gov/news/cochairs-proposal.
Congressional Research Service
13

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

or to the deauthorization process previously described. The projects, however, are subject to
federal laws, such as the National Environmental Policy Act. As indicated in Table 2, most Corps
environmental infrastructure financing is 75% federal and 25% nonfederal.
Congressional Research Service
14

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Appendix. Evolution of the Its Civil Works Mission
The Corps’ oldest civil responsibilities are creating navigable channels and flood control projects.
Navigation projects include river deepening, channel widening, lock expansion, dam operations,
and disposal of dredged material. Flood control projects are intended to reduce riverine and
coastal storm damage; these projects range from levees and floodwalls to dams and river
channelization. Many Corps projects are multipurpose—that is, they provide water supply,
recreation, and hydropower in addition to navigation or flood control. Its environmental activities
involve wetlands and aquatic ecosystem restoration and environmental mitigation activities for
Corps facilities. The agency’s regulatory responsibility for navigable waters extends to issuing
permits for private actions that might affect wetlands and other waters of the United States.
Navigation and Flood Control (1802-1950s)
In the 19th century, the Corps’ mission evolved into civil and military building for the nation. In
1824, Congress passed legislation charging military engineers with planning roads and canals to
move goods and people. In 1850, Congress directed the Corps to engage in its first planning
exercise—flood control for the lower Mississippi River. During the 1920s, Congress expanded
the Corps’ ability to incorporate hydropower into multipurpose projects and authorized the
agency to undertake comprehensive surveys to establish river-basin development plans. The
modern era of federal flood control emerged with the Flood Control Act of 1936 (49 Stat. 1570),
which declared flood control a “proper” federal activity in the national interest. The 1944 Flood
Control Act (33 U.S.C. §708) significantly augmented the Corps’ involvement in large
multipurpose projects and authorized agreements for the temporary use of surplus water. The
Flood Control Act of 1950 (33 U.S.C. §701n) began the Corps’ emergency operations through
authorization for flood preparedness and emergency operations.23 The Water Supply Act of 1958
(43 U.S.C. §390b) gave the Corps authority to include some storage for municipal and industrial
water supply in reservoir projects at 100% local cost.
Changing Priorities (1960-1986)
By the late 1960s, construction of major waterworks had declined. Changing national priorities
and local needs, increasing construction costs, and completed projects at most prime locations
decreased the attractiveness of water projects. Water supply for traditional off-stream uses, such
as domestic, commercial, industrial, and agricultural uses, was increasingly in direct competition
with in-stream uses, such as recreation, fisheries, and wildlife habitat. From 1970 to 1985,
Congress authorized no major water projects, scaled back several authorized projects, and passed
laws that altered project operations and water delivery programs to protect the environment. The
1970s marked a transformation in Corps project planning. The 1969 National Environmental
Policy Act and the Endangered Species Act of 1973 (16 U.S.C. §1531) required federal agencies
to consider environmental impacts, increase public participation in planning, and consult with
other federal agencies. Executive orders (E.O. 11988 and E.O. 11990) united the goals of
reducing flood losses and environmental damage by recognizing the value of wetlands and
required federal agencies to evaluate potential effects of actions on floodplains and to minimize
impacts on wetlands.

23 Emergency response activities are also conducted under the Disaster Relief Act of 1974 (42 U.S.C. §5121), also
known as the Stafford Disaster and Emergency Assistance Act.
Congressional Research Service
15

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Corps Regulatory Activities: Permits and Their Authorities
The Corps has several regulatory responsibilities and issues several different types of permits. Sections 10 and 13 of
the Rivers and Harbors Act of 1899 (22 U.S.C. §407) require that a permit be obtained from the Corps for alteration
or obstruction of and refuse discharge in U.S. navigable waters. The Corps also has regulatory responsibilities under
other laws, notably Section 404 of the Clean Water Act (33 U.S.C. §1344), which requires a permit for dredging or
fil ing activities into waters of the United States. Since the mid-1960s, court decisions and administrative actions have
altered the jurisdictional reach of the Corps’ regulatory program. For more information on the Corps’ Clean Water
Act authorities, see CRS Report 97-223, The Army Corps of Engineers’ Nationwide Permits Program: Issues and Regulatory
Developments
, by Claudia Copeland and CRS Report RL33483, Wetlands: An Overview of Issues, by Claudia Copeland.
The Corps also regulates and authorizes disposal of materials into the ocean under the Marine Protection Research
and Sanctuaries Act; for more information, see CRS Report RS20028, Ocean Dumping Act: A Summary of the Law, by
Claudia Copeland.
Environmental Mission and Local Responsibility (1986-2000)
Congress fundamentally transformed the rules for Corps water project planning and funding
through WRDA 1986 (33 U.S.C. §2211); it established new cost-share formulas, resulting in
greater financial and decision-making roles for local stakeholders. WRDA 1986 reestablished the
tradition of biennial consideration of an omnibus Corps civil works authorization bill. WRDA
1986 also provided the Corps with authority to determine if changes can be made in existing
structures or operations to improve environmental quality. WRDA 1990 (33 U.S.C. §§1252,
2316) explicitly expanded the Corps’ mission to include environmental protection and increased
the Corps’ responsibility for contamination cleanup, dredged material disposal, and hazardous
waste management. WRDA 1992 (33 U.S.C. §2326) authorized the Corps to use the “spoils”
from dredging in implementing projects for protecting, restoring, and creating aquatic and
ecologically related habitats, including wetlands. WRDA 1996 (33 U.S.C. §2330) gave the Corps
the authority to undertake aquatic ecosystem restoration projects. While the Corps has been
involved with numerous environmental restoration projects in recent years, WRDA 2000
approved a restoration program for the Florida Everglades that represented the agency’s first
multiyear, multibillion-dollar effort of this type. These legislative changes gave the Corps an
aquatic ecosystem restoration and environmental protection mission.
Evolving Demands and Processes (2001-present)
The agency’s aging infrastructure and efforts to enhance the security of its infrastructure from
terrorism and natural threats have expanded Corps activities in infrastructure rehabilitation,
maintenance, and protection. WRDA 2007 continued the expansion of the Corps’ ecosystem
restoration activities by authorizing billions of dollars for ecosystem restoration activities,
including large-scale efforts in coastal Louisiana and in the Upper Mississippi River. The Corps
also retooled its long-standing flood control mission to use a flood risk management approach.
This was undertaken in response to congressional direction in WRDA 2007 and disasters like
Hurricanes Katrina, Rita, and Ike and the significant floods in the Midwest. This approach
emphasizes a greater appreciation for the shared responsibilities across levels of government for
managing flood. The regularity with which the Corps has received significant congressional
appropriations for natural disaster response (e.g., Hurricane Sandy) has increased attention to its
role in emergency response, infrastructure repair, and post-disaster recovery. WRRDA 2014
expanded opportunities for nonfederal participation in project delivery and financing and aimed
to improve the efficiency of Corps planning activities.

Congressional Research Service
16

Army Corps of Engineers: Water Resource Authorizations, Appropriations, and Activities

Author Contact Information

Nicole T. Carter
Charles V. Stern
Specialist in Natural Resources Policy
Specialist in Natural Resources Policy
ncarter@crs.loc.gov, 7-0854
cstern@crs.loc.gov, 7-7786


Congressional Research Service
17