

 
Stormwater Permits: Status of EPA’s 
Regulatory Program 
Claudia Copeland 
Specialist in Resources and Environmental Policy 
March 21, 2014 
Congressional Research Service 
7-5700 
www.crs.gov 
97-290 
 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
Summary 
The Environmental Protection Agency (EPA) and states are implementing a federally mandated 
program for controlling stormwater discharges from industrial facilities and municipalities. Large 
cities and most industry sources are subject to rules issued in 1990, and EPA issued permit rules 
to cover smaller cities and other industrial sources and construction sites in 1999. Because of the 
large number of affected sources and deadline changes that led to confusion, numerous questions 
have arisen about this program. Impacts and costs of the program’s requirements, especially on 
cities, are a continuing concern.  
The 109th Congress enacted omnibus energy legislation (P.L. 109-58, the Energy Policy Act of 
2005) that included a provision giving the oil and gas industry regulatory relief from some 
stormwater control requirements. In May 2008, a federal court vacated an EPA rule implementing 
this provision. EPA intends to issue a revised rule that repeals the one that was vacated by the 
court and codifies the statutory exemption in P.L. 109-58, but the agency does not have a specific 
schedule for doing so. In the 111th Congress, the House passed a bill that included a provision that 
would repeal the exemption in P.L. 109-58, but the Senate took no action. Similar legislation has 
been introduced in the 113th Congress (H.R. 1175). 
Congress often looks to federal agencies to lead or test new policy approaches, a fact reflected in 
legislation enacted in the 110th Congress. Section 438 of the Energy Independence and Security 
Act (P.L. 110-140, EISA) requires federal agencies to implement strict stormwater runoff 
requirements for development or redevelopment projects involving a federal facility in order to 
reduce stormwater runoff and associated pollutant loadings. EPA has issued technical guidance 
for federal agencies to use in meeting these requirements. 
In 2009 the National Research Council issued a report calling for major changes to strengthen 
EPA’s stormwater regulatory program, which it criticized as being inconsistent nationally and 
failing to adequately control all sources of stormwater discharge that contribute to waterbody 
impairment. In response, EPA began efforts to expand regulations and strengthen the current 
program with a revised rule. Agency officials said that the new rule would focus on stormwater 
discharges from newly developed and redeveloped, or post-construction, sites, such as 
subdivisions, roadways, industrial facilities, and commercial buildings or shopping centers. The 
rule was originally due to be proposed in 2011, but EPA missed that and several subsequent 
deadlines, due to analytic problems associated with developing the rule. In March 2014, the 
agency announced that it is deferring action on a rule and instead will provide incentives, 
technical assistance, and other approaches for cities to address stormwater runoff themselves. 
 
Congressional Research Service 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
Contents 
Background ...................................................................................................................................... 1 
Industrial Facilities .................................................................................................................... 2 
Municipalities ............................................................................................................................ 3 
Phase I ................................................................................................................................. 3 
Phase II ................................................................................................................................ 4 
Congressional Interest...................................................................................................................... 6 
Oil and Gas Facilities ................................................................................................................ 6 
Stormwater Management at Federal Facilities .......................................................................... 7 
Recent Developments: EPA’s Stormwater Rulemaking ................................................................... 9 
 
Contacts 
Author Contact Information........................................................................................................... 11 
 
Congressional Research Service 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
Background 
Stormwater discharge systems are the pipes and sewer lines that carry rainwater or snow melt, but 
not domestic sanitary wastes, away from urban areas and commercial and industrial facilities. For 
many years the focus of the nation’s water quality programs was on controlling pollutants 
associated with industrial process wastewaters and municipal sewage discharges. More diffuse 
and episodic discharges (such as rainfall runoff from farm lands and urban runoff) and discharges 
believed to be relatively uncontaminated received less attention from policymakers and 
regulators. 
However, as the traditional sources of water pollution have become better controlled through laws 
and regulations, attention has increasingly focused on remaining problems that continue to 
prevent attainment of state and tribal water quality standards. Stormwater is one such source of 
pollution. For some time, it was generally believed that stormwater was largely clean, or 
uncontaminated. However, studies have demonstrated that this type of discharge—from rainfall 
and snow melt—carries with it large amounts of organic and toxic pollutants that can harm water 
quality, including oil and grease, heavy metals, pesticides, soil, and sediment.  
In urban areas, widespread residential and commercial development results in the removal of 
vegetation cover and building of impervious structures such as roads and parking lots. These 
activities may change natural drainage patterns in an area, causing higher runoff flows during wet 
weather events. Urbanization and the human alteration of landscapes and land uses that is 
associated with it have resulted in the degradation of conditions in downstream waterbodies. 
States report that stormwater discharges, including urban runoff, industrial activity, construction, 
and mining, are a significant source of surface water quality problems today. But control of 
stormwater discharges and other sources of wet weather pollution, including overflows from 
combined and separate sewer systems, is complicated because discharges generally are 
intermittent and are less amenable to “end of pipe” solutions than conventional industrial and 
municipal water pollution. 
Recognition of the water quality problems of stormwater runoff led Congress in 1987, when it 
last comprehensively amended the Clean Water Act (CWA), to direct EPA to implement a specific 
permit program for stormwater discharges from industrial sources and municipalities (P.L. 100-4). 
Even before the 1987 amendments, the issue of how to regulate stormwater discharges had a 
lengthy history of regulatory proposals, delays, legal challenges, and court decisions. Still, EPA 
had been unable to devise a comprehensive and flexible administrative process for regulating 
stormwater discharges before requirements were legislated in 1987. In that legislation, Congress 
established a phased and tiered approach to permitting of stormwater discharges that 
fundamentally redesigned the CWA’s approach to stormwater discharges. Congress recognized 
that EPA’s difficulties in addressing sources of stormwater stemmed in part from the large number 
of sources potentially subject to regulation, so the 1987 legislation adopted a procedure that 
would enable the major contributors of stormwater pollutants to be addressed first, and all 
remaining stormwater discharges in later phases. 
EPA initially issued regulations to implement Congress’s legislative mandate in 1990, utilizing a 
series of phased requirements.1 Phase I applied to large dischargers: those associated with 
                                                                  
1 U.S. Environmental Protection Agency, “National Pollutant Discharge Elimination System Application Regulations 
for Storm Water Discharges,” 55 Federal Register 47990-48091, November 16, 1990. 
Congressional Research Service 
1 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
industrial activities, municipal separate storm sewer systems serving 100,000 people or more, and 
construction projects disturbing more than 5 acres. Smaller sources were slated for possible 
regulation under Phase II of the program (discussed below) and included cities and towns with 
separate storm sewer systems serving fewer than 100,000 people, commercial operations, and 
smaller construction projects. Stormwater requirements are one element of the comprehensive 
permit program, the National Pollutant Discharge Elimination System (NPDES), authorized in 
Section 402 of the act. Under the act, it is illegal to discharge pollutants from point sources (e.g., 
industrial plant pipes, sewage treatment plants, or storm sewers) into the nation’s waters without 
an NPDES permit—permits are the fundamental compliance and enforcement mechanism of the 
law. EPA manages the NPDES stormwater program in four states (Idaho, Massachusetts, New 
Hampshire, and New Mexico), plus the District of Columbia and most U.S. territories, and has 
delegated that authority to the remaining 46 states and the Virgin Islands. 
An estimated 123,000 industrial facilities (twice the number of industrial sources subject to the 
base NPDES program) and 220 municipalities and counties were covered by the 1990 permit 
rules for Phase I of the program. The initial procedures and deadlines were complex and were 
made more confusing by subsequent deadline extensions.2 
The 1987 CWA amendments directed delegated states (or EPA) to issue stormwater permits not 
later than four years after enactment of that legislation. This would have required permits to be 
issued by February 4, 1991, but this did not occur, in part because EPA’s 1990 rule was issued 21 
months after the statutory deadline. Regulated sources must comply with stormwater permits 
within three years of their issuance. 
Permits require dischargers, at a minimum, to implement pollution prevention plans, although 
remediation or additional treatment of runoff may also be required. Permits issued to 
municipalities require cities to develop, implement, and enforce a stormwater management 
program that addresses key areas such as public education, eliminating illicit connections to storm 
sewers, good housekeeping of municipal operations, and control of erosion and sedimentation 
from construction sites. 
Prior to implementation of the stormwater regulatory program, the universe of NPDES permittees 
nationwide was less than 70,000 industrial and municipal facilities. The addition of stormwater 
permittees greatly expanded this regulatory program. EPA estimates that the total number of 
stormwater permittees at any one time exceeds half a million—thus, NPDES stormwater 
permittees outnumber wastewater permittees more than five-fold. 
Industrial Facilities 
Industries that manufacture, process, or store raw materials and which collect and convey 
stormwater associated with those activities were required to apply for an NPDES permit under the 
Phase I program. Several industries were specifically identified in EPA’s 1990 regulation: mining 
operations; lumber and wood products; paper and allied products; printing, chemical products, 
                                                                  
2 Moreover, the 1990 regulations themselves were challenged by an environmental group, the Natural Resources 
Defense Council. In 1992, a federal appeals court ruled that EPA had failed to meet certain deadlines specified in the 
1987 legislation and had been improper in exempting from regulation light industry and construction sites that affect 
less than 5 acres of land. Natural Resources Defense Council v. EPA, 966 F.2d 1292 (9th Cir. 1992). 
Congressional Research Service 
2 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
paints, varnishes, and lacquers; stone, clay, glass, and concrete; metals; petroleum bulk terminals; 
hazardous waste treatment facilities; salvage operations; and powerplants. 
Industrial facilities had several options to comply with these permit requirements. Chiefly, they 
could obtain either individual or group permits. Applications for individual facility permits were 
due to be submitted by October 1, 1992. For group permits (covering multiple facilities with 
similar stormwater discharges), a two-step process applied: submitting a list of facilities to be 
covered by September 30, 1991, and submitting more detailed information, such as sampling data 
on 10% of facilities in the group and a description of a stormwater management program, by 
October 1, 1992.3 
EPA also provided a third option for industrial facilities, through a general permit procedure. A 
general permit is one that covers discharges from more than one facility, thus making the large 
number of stormwater permittees more manageable. Sources are only required to submit a Notice 
of Intent to be covered by a general permit, rather than the detailed application for an individual 
permit. EPA expected that general stormwater permits will make for a less costly and burdensome 
permitting process through less extensive testing and control requirements, as well as minimal 
monitoring and reporting. For most sources, general permits require preparation of a pollution 
prevention plan, and compliance with the plan six months later. EPA has issued general permits 
for stormwater discharges associated with industrial and construction activities that disturb 5 
acres or more, which apply in the four states where EPA is the permitting authority for the 
stormwater program. Using the EPA general permit as a model, most other states that have been 
delegated permitting responsibility use similar general permits to reduce the administrative 
burden of the industrial stormwater permit program. 
Since 1987, Congress has twice addressed the deadlines for stormwater permitting of industrial 
facilities. Congress first extended aspects of the deadlines for group applications by industrial 
facilities (P.L. 102-27, Dire Emergency Supplemental Appropriations Act of 1991), and in the 
1991 Surface Transportation Act (P.L. 102-240), Congress clarified the deadlines applicable to 
industrial activities that are municipally owned or operated (such as airports or powerplants). 
Municipalities 
Phase I 
Much of the controversy about stormwater requirements has focused on impacts on cities, not 
industrial sources. Municipalities with separate storm sewer systems (called MS4s) were subject 
to EPA’s regulations under staggered deadlines based on the size of population served. In the 
1990 Phase I regulations that apply to industrial activities, EPA also regulated discharges from 
medium-size and large cities (covering those with populations greater than 100,000 persons). The 
Phase 1 regulations are primarily application requirements that identify components that must be 
addressed in permit applications. The rules require large and medium MS4s to develop a 
stormwater management program, track and oversee industries facilities that are regulated under 
                                                                  
3 The same deadlines also applied to industrial activities owned or operated by municipalities with a population of 
250,000 or more. For industrial activities owned or operated by municipalities with populations of more than 100,000 
but less than 250,000, the respective deadlines were May 18, 1992, and May 17, 1993. Certain government-owned or -
operated activities (airports, powerplants, and uncontrolled sanitary landfills) also were subject to the May 1992 and 
May 1993 deadlines, even if the unit of government has a population of less than 100,000. 
Congressional Research Service 
3 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
the stormwater program, conduct monitoring, and submit periodic reports. The regulations 
specified deadlines for these cities to provide regulators with information on legal authority over 
stormwater discharges and to provide detailed information on source identification and 
monitoring data. EPA identified 173 cities and parts of 47 urban counties as covered by Phase I. 
Phase II 
The 1987 CWA amendments exempted smaller cities (with populations of fewer than 100,000) 
from any stormwater permit requirements until October 1, 1992, and directed EPA to develop a 
suitable approach to address them under Phase II of the stormwater regulatory program. Because 
of problems in formulating a permitting strategy, EPA did not issue regulations by the 1992 
deadline, nor did it meet the deadline in a one-year extension that Congress provided in P.L. 102-
580. In 1995, EPA convened an advisory committee of stakeholders to assist in developing rules 
by March 1, 1999, a deadline set in a judicial consent order in Natural Resources Defense 
Council v. EPA (Civ. No. 95-0634 PFL [DDC, Apr. 6, 1995]) that required EPA to clarify the 
scope of coverage and control mechanisms for the Phase II program. Based in part on extensive 
discussions with the stakeholder advisory committee and with another court-approved extension, 
EPA issued a final Phase II rule in 1999.4 EPA estimated that the rule would make approximately 
3,000 more river miles safe for boating annually and protect up to 500,000 people a year from 
illness due to swimming in contaminated waters. 
The 1999 Phase II rule extended Phase I by requiring permits of two additional classes of 
dischargers on a nationwide basis: (1) operators of MS4s serving populations of less than 100,000 
persons in urbanized areas as defined by the Bureau of the Census, and (2) operators of 
construction activities that disturb greater than 1 and less than 5 acres of land (larger construction 
sites are covered by the Phase I rules). Separate storm sewer systems such as those serving 
military bases, universities, large hospital or prison complexes, and highways are also included in 
the definition of small MS4. EPA estimated that 5,040 small cities are covered by Phase II, along 
with about 110,200 construction starts per year.5 
Waivers from coverage are available both for small cities (those with fewer than 10,000 persons) 
and construction activities if the discharges are not causing water quality impairment. At the same 
time, additional small municipal systems and construction sites may be brought into the 
stormwater program on a case-by-case basis, if permitting authorities determine that they are 
significant contributors to water pollution. Under the 1999 rule, covered facilities were required 
to apply for NPDES permit coverage by March 2003 (most under a general rather than an 
individual permit) and implement stormwater management programs that include six minimum 
management controls that effectively reduce or prevent pollutant discharges into receiving waters, 
such as pollution prevention and eliminating illicit discharge connections for municipal 
operations. The rule also provided that municipally operated industrial activities not previously 
                                                                  
4 U.S. Environmental Protection Agency, “National Pollutant Discharge Elimination System—Regulations for Revision 
of the Water Pollution Control Program for Storm Water Discharges,” 64 Federal Register 68721-68851, December 8, 
1999. 
5 Although precise numbers are not available, EPA now estimates that the number of regulated MS4s is about 7,000 
(including 1,000 under Phase I and 6,000 under Phase II). The number of industrial permittees is estimated to be around 
100,000. The construction site portion of the program each year covers about 200,000 permittees under Phase I (5 acres 
or greater) and another 200,000 under Phase II (1 to 5 acres). See National Research Council of the National Academy 
of Sciences, Water Science and Technology Board, Urban Stormwater Management in the United States, The National 
Academies Press, Washington, DC, 2009, p. 36. 
Congressional Research Service 
4 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
regulated were required to apply for permit coverage under the same schedule as other facilities 
covered by Phase II. 
In the final Phase II rule, EPA attempted to balance statutory requirements for a nationally 
applicable program with sufficient administrative flexibility to focus on significant water quality 
impairments. For example, EPA encouraged permitting authorities to use general rather than 
individual permits for the majority of covered dischargers. The agency’s decision to not include 
construction sites smaller than 1 acre was based on the belief that regulating the smallest of such 
sites would overwhelm the resources of permitting authorities and might not yield corresponding 
water quality benefits. Further, EPA modified the previous Phase I rule to exclude industrial 
facilities that have “no exposure” of their activities (such as raw materials) to stormwater, thus 
reducing coverage by an estimated 76,000 facilities that have no industrial stormwater discharges. 
These efforts to provide flexibility notwithstanding, many regulated entities continued to criticize 
the scope of the stormwater program, saying that EPA had greatly underestimated the cost of the 
Phase II rules (projected to be $297 million annually for small cities and $505 million annually 
for construction activities).  
Cities of all sizes have complained about the costs and difficulties of complying with EPA’s 
regulations, especially because there is no specific CWA grant or other type of assistance program 
to help pay for developing and implementing local stormwater programs. Many contend that 
cities already are burdened with numerous environmental compliance requirements and lack 
adequate resources to address stormwater controls in addition to drinking water, solid waste, 
wastewater treatment, and sludge disposal problems. Where cities need to construct or install 
technology to control stormwater discharges, the principal source of financial assistance is the 
CWA’s state revolving fund (SRF) loan program that is administered by states. However, SRF 
assistance is not restricted to meeting just stormwater project needs, competition for available 
funds for all types of eligible projects is intense.6 
Many municipal and industrial dischargers covered by the Phase I and Phase II programs have 
reached the end of their initial permit terms (NPDES permits are issued for five-year terms). For 
permit renewals, the agency is implementing a streamlined reapplication process that will not 
require the extensive information collection that characterized the first round of permitting. 
Implementation of permits (i.e., translating permits into specific steps to manage stormwater 
runoff) is now the challenge for permitting authorities and permittees. According to a 2001 
Government Accountability Office (GAO) report, local governments are primarily using best 
management practices (BMPs, sometimes called stormwater control measures, or SCMs) to 
prevent or slow stormwater from quickly reaching nearby waterbodies and degrading water 
quality, rather than requiring that stormwater be transported to treatment facilities.7 BMPs include 
nonstructural measures to minimize contaminants getting into stormwater (e.g., street sweeping) 
and structural practices such as detention ponds to separate contaminants from stormwater. GAO 
criticized EPA for not establishing systematic efforts or measurable goals to evaluate the 
effectiveness of the program in reducing stormwater pollution or to determine its costs, which 
                                                                  
6 For additional information, see CRS Report 98-323, Wastewater Treatment: Overview and Background, by Claudia 
Copeland. 
7 U.S Government Accountability Office, Water Quality, Better Data and Evaluation of Urban Runoff Programs 
Needed to Assess Effectiveness, GAO-01-679, June 2001. 
Congressional Research Service 
5 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
local governments have portrayed as high. In the 1999 rules, EPA set a goal of beginning to 
evaluate implementation of Phase II of the program in 2012. 
In a 2007 report, GAO examined implementation of the stormwater regulatory program by 
municipalities.8 GAO found that implementation of both Phases I and II has been slow: nearly 
11% of communities were not permitted as of 2006; and even in communities with permits, 
delays occurred due to litigation or other disputes. Thus, GAO reported that because many 
communities are still in the early stages of implementation, it is too early to determine the overall 
program burden. While EPA’s regulations provide flexibility, which could limit program burden, 
increased burden could result if communities are required by states or EPA to expand stormwater 
management activities or meet more stringent specific permit conditions in the future. GAO 
found that EPA is not collecting complete and consistent cost and other data, which hampers 
assessment of program burden. 
Congressional Interest 
Prior to issuance of the final Phase II rule in 1999, Congress included language in EPA’s FY2000 
appropriation bill (P.L. 106-74) directing the agency not to issue the final rule before submitting a 
detailed impact analysis to Congress. To meet a court-ordered deadline for the regulation, EPA 
released the report concurrently with the Phase II rule.9 In the 106th Congress, legislation was 
introduced to exempt construction sites of less than 5 acres and certain above-ground drainage 
ditches from stormwater permitting requirements (S. 2139/H.R. 3625). At an October 1999 
Senate hearing, EPA witnesses opposed the bill, saying that above-ground drainage ditches and 
small construction sites are significant sources of water pollution and thus should be subject to 
stormwater management requirements. No further action occurred. 
In response to concerns about program impacts and costs, the 107th Congress enacted legislation 
allowing states to use Section 319 grant funds, which are used for projects to manage nonpoint 
sources of water pollution, for projects or activities related to developing and implementing a 
Phase II stormwater program (§301 of P.L. 107-303). This authority only applied to Section 319 
funds in FY2003. Legislation to extend this authority beyond FY2003 was introduced in the 108th 
Congress, but was not enacted (S. 1716/H.R. 3528). 
Oil and Gas Facilities 
As the March 2003 Phase II deadline approached (affecting small municipalities and construction 
sites), EPA proposed a two-year extension of the rule for small oil and gas exploration and 
production facility construction sites to allow the agency to assess the rule’s economic impact on 
that industry. EPA had initially assumed that most oil and gas facilities would be smaller than one 
acre in size and thus excluded from Phase II rules, but newer data indicated that up to 30,000 new 
sites per year would be of sizes subject to the rule. In March 2005 EPA extended the exemption 
until June 2006 for further study and said it would issue a specific rule for small oil and gas 
                                                                  
8 U.S. Government Accountability Office, Clean Water, Further Implementation and Better Cost Data Needed to 
Determine Impact of EPA’s Storm Water Program on Communities, GAO-07-479, May 2007. 
9 U.S. Environmental Protection Agency, Office of Water, Report to Congress on the Phase II Storm Water 
Regulations, EPA 833-R-99-001, September 1999, http://www.epa.gov/npdes/pubs/ReptoCong_PhII_SWR.pdf. 
Congressional Research Service 
6 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
construction sites by that date. The postponement did not affect other industries, construction 
sites, or small cities covered by the 1999 rule. Under the 1987 amendments to the CWA, the 
operations of facilities involved in oil and gas exploration and production generally were 
exempted from compliance with stormwater runoff regulations (so long as the runoff is 
uncontaminated by pollutants), but the construction of associated facilities was not.  
Omnibus energy legislation enacted in the 109th Congress (P.L. 109-58, the Energy Policy Act of 
2005) included a provision addressing this issue. Section 323 amends the CWA to specifically 
include construction activities at all oil and gas development and production sites, regardless of 
size (including sites larger than 5 acres, previously covered by Phase I), in the law’s general 
statutory exemption for oil and gas facilities from stormwater rules. Its intention was to exempt 
from the CWA all uncontaminated stormwater discharges that occur while setting up drilling 
operations. 
Oil and gas officials, who supported the provision, said that the existing EPA stormwater rules 
create time-consuming permitting requirements, even though the short construction period for 
drilling sites carries little potential for stormwater runoff pollution. Opponents argued that the 
provision did not belong in the omnibus energy legislation and that there is no evidence that 
construction at oil and gas sites causes less pollution than other construction activities, which are 
regulated under EPA’s stormwater program. 
EPA promulgated a rule to implement Section 323 in 2006.10 The rule was criticized by some 
interest groups and Members of Congress who argued that EPA had exceeded its authority by 
broadly defining the scope of contamination that is exempted by the rule beyond the statutory 
language to also include stormwater discharges contaminated solely with sediment. In May 2008, 
a federal court held that the rule is arbitrary and capricious, and it vacated the rule.11 EPA 
petitioned the court to rehear the case, but the request was denied—thus, the exemption is no 
longer in effect. EPA intends to issue a revised rule that would remove the 2006 rule from the 
Code of Federal Regulations consistent with the court vacatur and codify the statutory exemption 
in P.L. 109-58, but the agency has not announced a specific schedule for doing so. Legislation to 
repeal Section 323 was introduced in the 109th Congress (H.R. 4541), but no further action 
occurred. 
In the 111th Congress, legislation to repeal the exemption that was enacted in P.L. 109-58 passed 
the House (the provision was Section 728 of H.R. 3534, the Consolidated Land, Energy, and 
Aquatic Resources Act), but there was no further action on this bill. In the 113th Congress, a bill 
has been introduced to repeal the oil and gas exemption enacted in P.L. 109-58. The new bill, 
H.R. 1175, also would direct the Secretary of the Interior to conduct a study of stormwater runoff 
from oil and gas operations that may result in contamination. 
Stormwater Management at Federal Facilities 
Congress often looks to federal agencies to lead or test new policy approaches, a fact reflected in 
legislation passed in 2007. Section 438 of P.L. 110-140, the Energy Independence and Security 
                                                                  
10 U.S. Environmental Protection Agency, “Amendments to the National Pollutant Discharges Elimination System 
(NPDES) Regulations for Storm Water Discharges Associated with Oil and Gas Exploration, Production, Processing, 
or Treatment Operations, or Transmission Facilities,” 71 Federal Register 33628-33640, June 12, 2006. 
11 Natural Resources Defense Council v. U.S. Environmental Protection Agency, 526 F.3d 591 (9th Cir. 2008). 
Congressional Research Service 
7 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
Act (EISA), requires federal agencies to implement strict stormwater runoff requirements for 
development or redevelopment projects involving a federal facility in order to reduce stormwater 
runoff and associated pollutant loadings to water resources. The legislation requires agencies to 
use site planning, construction, and other strategies to maintain or restore, to the maximum extent 
technically feasible, the predevelopment hydrology of the property. 
To assist agencies in meeting these requirements, EPA issued technical guidance.12 The guidance 
provides two options for meeting the performance objective of preserving or restoring the 
hydrology of a site: retaining the 95th percentile rainfall event (i.e., managing rainfall on-site for 
storm events whose precipitation total is less than or equal to 95% of all storm events over a 
given period of record), or site-specific hydrologic analysis (i.e., using site-specific analysis to 
determine predevelopment runoff conditions). According to the guidance, using a performance-
based approach rather than prescriptive requirements is intended to give site designers maximum 
flexibility in selecting appropriate control practices. Issuance of the guidance also fulfilled an 
element of an October 2009 executive order that formally assigned to EPA the responsibility to 
issue the Section 438 guidance, in coordination with other agencies, and to do so by December 5, 
2009.13 
In December 2010 Congress passed legislation requiring federal agencies to pay local fees for 
treating and managing stormwater runoff. The legislation amends CWA Section 313, which 
requires federal agencies to comply with all federal, state, and local water pollution control 
requirements as nongovernmental entities, including the payment of reasonable service charges. 
The issue emerged earlier in 2010 when several federal agencies announced that they would not 
pay stormwater fees assessed by the District of Columbia, claiming that the fees amounted to a 
tax that the agencies were not required to pay, because the waiver of sovereign immunity in 
Section 313 applies to fees and charges, but not a tax. The legislation was intended to clarify 
uncertainty over whether federal agencies must pay local stormwater fees. President Obama 
signed the legislation in January 2011 (P.L. 111-378). 
A continuing aspect of the issue of interest in a few locations is the scope of P.L. 111-378 and 
whether it requires the government to pay local stormwater fees retroactively. After the 
Bonneville Power Administration had objected to paying retroactive stormwater fees imposed by 
two Washington localities following passage of the federal facility amendment, the matter ended 
up in federal court. The government took the position in the litigation that the legislative change 
amounted to a redefinition of “service charges,” instead of a clarification of Congress’s original 
intent, and would only apply prospectively. In May 2012, a federal district court rejected the 
government’s position and held that the CWA amendment was merely a clarification of the statute 
and thus is entitled to retroactive effect.14 The federal government did not appeal this ruling. A 
similar case in Georgia was dismissed following a settlement agreement between the parties, but 
the settlement did not resolve lingering questions whether stormwater charges are fees for 
“reasonable services provided” or taxes, an issue of concern more broadly than just regarding 
government facilities. 
                                                                  
12 U.S. Environmental Protection Agency, Office of Water, Technical Guidance on Implemementing the Stormwater 
Runoff Requirements for Federal Projects Under Section 438 of the Energy Independence and Security Act, EPA 841-
B-09-001, December 2009, http://www.epa.gov/owow/NPS/lid/section438/pdf/final_sec438_eisa.pdf. 
13 Executive Order 13514, “Federal Leadership in Environmental Energy and Economic Performance,” 71 Federal 
Register 52117-52127, October 8, 2009. 
14 United States v. Renton, W.D. Wash., No. C11-1156JLR, May 25, 2012. 
Congressional Research Service 
8 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
Recent Developments: EPA’s Stormwater 
Rulemaking 
In 2006 EPA requested the National Research Council of the National Academy of Sciences 
(NRC) to conduct a review of the existing stormwater regulatory program. The resulting report, 
issued in 2009, called for major changes to EPA’s stormwater control program that would focus 
on the flow volume of stormwater runoff instead of just its pollutant load. The committee 
observed that— 
stormwater discharges would ideally be regulated through direct controls on land use, strict 
limits on both the quantity and quality of stormwater runoff into surface waters, and rigorous 
monitoring of adjacent waterbodies to ensure that they are not degraded by stormwater 
discharge.... Presently, however, the regulation of stormwater is hampered by its association 
with a statute that focuses primarily on specific pollutants and ignores the volume of 
discharges.15  
The NRC report recommended that EPA adopt a watershed-based permitting system 
encompassing all discharges—stormwater and wastewater—that could affect waterways in a 
particular drainage basin, rather than individual permits that do not account for cumulative 
conditions from multiple sources in the same watershed. Under the proposed watershed 
permitting strategy, responsibility to implement watershed-based permits and control all types of 
municipal, industrial, and construction stormwater discharges would reside with MS4 permittees. 
The report criticized EPA’s current approach, which leaves much discretion to regulated entities 
to set their own standards through stormwater management plans and to self-monitor. As a result, 
enforcement is difficult and variable, and information to assess the water quality benefits of the 
regulatory program is limited. The report also noted that adequate resources, including new levels 
of public funds, will likely be required to operate a more comprehensive and effective stormwater 
permitting program. 
Subsequently, EPA initiated information-gathering and public dialogue activities as a prelude to 
possible regulatory changes that would respond to the NRC’s criticism of inconsistency in 
stormwater requirements nationally and embrace the report’s recommendation to adequately 
control all sources of stormwater discharge that contribute to waterbody impairment. EPA 
proposed to collect data from MS4s, states, and industry entities involved in developing or 
redeveloping sites on the scope of the current regulatory program and management practices, as 
well as information on control, pollution prevention technologies, and BMPs applied to 
stormwater discharges from newly developed and redeveloped sites.16 
In response to the NRC report, EPA began work to develop a rule to revise the existing 
stormwater regulatory program. The rule also results from a 2010 settlement agreement between 
EPA and environmental litigants, which calls for EPA to revise existing rules “to expand the 
universe of regulated stormwater discharges and to control, at a minimum, stormwater discharges 
                                                                  
15 Supra note 5, p. 3. 
16 U.S. Environmental Protection Agency, “Agency Information Collection Activities; Proposed Collection; Comment 
Request; Stormwater Management Including Discharges from Newly Developed and Redeveloped Sites; EPA ICR No. 
2366.01, OMB Control No. 2040-NEW,” 74 Federal Register 56191-56193, October 30, 2009. 
Congressional Research Service 
9 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
from newly developed and redeveloped sites.”17 EPA also committed to consider supplemental 
provisions as part of the national rule that would apply only to the Chesapeake Bay watershed, a 
region where municipal stormwater discharges are a significant cause of water quality impairment 
and are one of the only sources of pollutants with increasing loads to the Bay and its tributaries.  
In early 2010 EPA held a series of listening sessions across the country as part of a process 
seeking public comments on potential considerations for regulatory changes.18 The agency also 
sent survey questionnaires to property owners and developers, municipal sewer system 
authorities, state regulators, and EPA regional offices to obtain their input. Some industry groups 
reportedly criticized possible expansion of the current program, saying that EPA’s authority to 
regulate stormwater does not extend to regulation of post-construction discharges. Some states 
also said that EPA lacks the technical knowledge to regulate stormwater across the nation, while 
states with comprehensive regulations, such as Florida and Maryland, demonstrate that regulation 
is best done at the state and local level, because of locational differences in stormwater 
discharges. EPA officials have noted that a number of states have been developing their own 
stormwater management programs, particularly in the Northeast, where lawsuits have pushed 
regulators, and also in some high-precipitation states in the Northwest. A number of commenters 
urged EPA to ensure that performance standards designed to reduce storm runoff be flexible so 
that communities can create requirements appropriate to their stormwater needs. Cost is a key 
issue raised by some states and municipalities concerned about the possibility of mandatory 
retrofit requirements that would impose a significant economic burden on cities.19 Some state and 
local government representatives—while they are concerned about details of a rule—believe that 
a national rule would provide needed uniformity and consistency in stormwater programs across 
the nation.  
During development of the national rule, EPA explored regulatory options that would strengthen 
the regulatory program by establishing specific post-construction requirements for stormwater 
discharges from new development and redevelopment, which currently are not regulated. While 
MS4s are required to address stormwater discharges from new development and redevelopment 
in their management plans, EPA rules do not include specific management practices or standards 
to be implemented. Other options that EPA considered include expanding the area defined as 
MS4s to include rapidly developing areas, devising a single set of consistent regulations for all 
MS4s, and requiring MS4s to address stormwater discharges in areas of existing development 
through retrofit practices. EPA officials said that the rule would focus on stormwater discharges 
from developed, or post-construction, sites, such as subdivisions, roadways, industrial facilities, 
and commercial buildings or shopping centers, and to seek to ensure that even after development 
projects are completed, runoff levels from sites are equivalent to pre-construction hydrology. The 
proposal, referred to as the “post-construction rule,” likely would set a first-time stormwater 
retention performance standard to limit runoff that would otherwise enter an MS4 system. By 
retaining a portion of rainfall on-site, the discharge of pollutants for that volume is prevented 
from entering the sewer system. Requirements in the post-construction rule, once finalized, would 
be incorporated into MS4 permits as the permits come up for renewal. 
                                                                  
17 Fowler v. EPA, D.D.C. No. 1:09-cv-5, May 11, 2010, pp. 18-19. 
18 U.S. Environmental Protection Agency, “Stakeholder Input; Stormwater Management Including Discharges from 
New Development and Redevelopment,” 74 Federal Register 68617-68622, December 28, 2009. 
19 Examples of urban retrofits include breaking up concrete and installing stones, thereby replacing an impermeable 
surface with a permeable one that will absorb runoff; and adding vegetation and trees to parking lots. 
Congressional Research Service 
10 
Stormwater Permits: Status of EPA’s Regulatory Program 
 
The stormwater rulemaking has drawn some interest from Members of Congress. In May 2013, 
Republican members of the Senate Environment and Public Works Committee urged EPA to 
suspend work on the rulemaking until the agency seeks meaningful input from small businesses 
and provides a report to Congress on the necessity for new stormwater regulations.20 
Under the 2010 settlement with environmentalists, EPA was initially due to propose a national 
rule by September 2011 and complete the rule in 2014. Since 2011, the deadlines have been 
renegotiated three times, with the latest deadline of June 17, 2013, for proposal. EPA missed that 
deadline, and on June 18, the environmental plaintiffs notified the agency that it is in breach of 
the legal settlement. At that point, EPA and the plaintiffs had reached a legal impasse; EPA 
reportedly continued to work on the rule, while the environmental groups considered further legal 
action. Finalizing a rule with national application was complicated by a number of analytic issues, 
particularly how to calculate costs and benefits of the proposal and how to incorporate flexibility, 
such as possibly including lengthy implementation plans for retrofit projects and allowing states 
with equivalent stormwater programs to regulate in lieu of EPA. 
In mid-March 2014, EPA announced that it is deferring action on the post-construction 
stormwater rule and instead will provide incentives, technical assistance, and other approaches for 
cities to address stormwater runoff themselves. In particular, the agency will leverage existing 
requirements to strengthen municipal stormwater permits and will continue to promote green 
infrastructure as an integral part of stormwater management.21 In the area of incentives and 
technical assistance, EPA’s FY2015 budget request includes $5 million and adds 30 staff positions 
to strengthen its green infrastructure activities. EPA expects to be able to assist up to 100 
communities to implement cost-effective and sustainable approaches to water management. 
Unclear for now is whether the environmental plaintiffs that entered into the 2010 settlement 
agreement will reopen the lawsuit against EPA. 
 
 
Author Contact Information 
 
Claudia Copeland 
   
Specialist in Resources and Environmental Policy 
ccopeland@crs.loc.gov, 7-7227 
 
 
                                                                  
20 Letter from Senator David Vitter et al., Ranking Member, Senate Committee on Environment and Public Works, to 
Nancy K. Stoner, Acting Assistant Administrator, U.S. EPA, May 20, 2013, http://www.epw.senate.gov/public/
index.cfm?FuseAction=Minority.PressReleases&ContentRecord_id=c2a6e50c-0104-72a4-684d-f05928092fa0&
Region_id=&Issue_id=. 
21 For additional information, see CRS Report R43131, Green Infrastructure and Issues in Managing Urban 
Stormwater, by Claudia Copeland. 
Congressional Research Service 
11