Navy Ford (CVN-78) Class Aircraft Carrier 
Program: Background and Issues for Congress 
Ronald O'Rourke 
Specialist in Naval Affairs 
September 6, 2013 
Congressional Research Service 
7-5700 
www.crs.gov 
RS20643 
CRS Report for Congress
Pr
  epared for Members and Committees of Congress        
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Summary 
CVN-78, CVN-79, and CVN-80 are the first three ships in the Navy’s new Gerald R. Ford (CVN-
78) class of nuclear-powered aircraft carriers (CVNs). 
CVN-78 was procured in FY2008. The Navy’s proposed FY2014 budget estimates the ship’s 
procurement cost at $12,829.3 million (i.e., about $12.8 billion) in then-year dollars. The ship 
received advance procurement funding in FY2001-FY2007 and was fully funded in FY2008-
FY2011 using congressionally authorized four-year incremental funding. The Navy did not 
request any procurement funding for the ship in FY2012 and FY2013. The Navy is requesting 
$588.1 million in procurement funding in FY2014, and plans to request another $729.0 million in 
procurement funding in FY2015, to cover cost growth on the ship. 
CVN-79 is scheduled to be procured in FY2013. The ship received advance procurement funding 
in FY2007-FY2012, and the Navy plans to fully fund the ship in FY2013-FY2018 using 
congressionally authorized six-year incremental funding. The Navy’s proposed FY2014 budget 
estimates CVN-79’s procurement cost at $11,338.4 million (i.e., about $11.3 billion) in then-year 
dollars, and requests $944.9 million in procurement funding for the ship. 
CVN-80 is scheduled to be procured in FY2018. The Navy’s proposed FY2014 budget estimates 
the ship’s procurement cost at $13,874.2 million (i.e., about $13.9 billion) in then-year dollars. 
Under the Navy’s proposed FY2014 budget, the ship is to receive advance procurement funding 
in FY2016-FY2017 and be fully funded in FY2018-FY2023 using congressionally authorized 
six-year incremental funding. 
Oversight issues for Congress for the CVN-78 program include the following: 
•  the impact on Navy shipbuilding programs of the March 1, 2013, sequester on 
FY2013 funding and unobligated prior-year funding; 
•  the potential impact on Navy shipbuilding programs of a possible sequester later 
this year or early next year on FY2014 funding and unobligated prior-year 
funding; 
•  cost growth in the CVN-78 program; 
•  where the estimated procurement costs of CVNs 78, 79, and 80 now stand in 
relation to the legislated procurement cost caps for the ships, and whether the 
cost caps should be amended; 
•  the potential for a two-ship block buy on CVN-79 and CVN-80; and 
•  CVN-78 program issues that were raised in a December 2012 report from the 
Department of Defense’s (DOD’s) Director of Operational Test and Evaluation 
(DOT&E). 
 
Congressional Research Service 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Contents 
Introduction ...................................................................................................................................... 1 
Background ...................................................................................................................................... 1 
The Navy’s Aircraft Carrier Force ............................................................................................. 1 
Statutory Requirement to Maintain Not Less Than 11 Carriers ................................................ 1 
Origin of Requirement ........................................................................................................ 1 
Waiver for Period Between CVN-65 and CVN-78 ............................................................. 1 
Funding and Procuring Aircraft Carriers ................................................................................... 2 
Some Key Terms ................................................................................................................. 2 
Incremental Funding Authority for Aircraft Carriers .......................................................... 2 
Aircraft Carrier Construction Industrial Base............................................................................ 3 
Gerald R. Ford (CVN-78) Class Program ................................................................................. 3 
CVN-78 ............................................................................................................................... 4 
CVN-79 ............................................................................................................................... 4 
CVN-80 ............................................................................................................................... 4 
Program Procurement Funding ........................................................................................... 5 
Increases in Estimated Unit Procurement Costs Since FY2008 Budget ............................. 6 
Program Procurement Cost Cap .......................................................................................... 7 
Issues for Congress .......................................................................................................................... 8 
Impact of March 1, 2013, Sequester on FY2013 Funding ........................................................ 8 
Potential Impact of Possible Late 2013/Early 2014 Sequester on FY2014 Funding ................. 8 
Cost Growth............................................................................................................................... 8 
September 2013 GAO Report ............................................................................................. 9 
June 2013 Press Report ..................................................................................................... 12 
March 2013 Report to Congress (Released May 2013) .................................................... 14 
December 31, 2012, SAR (Released May 2013) .............................................................. 15 
May 2013 Navy Testimony ............................................................................................... 17 
March 2013 GAO Report .................................................................................................. 19 
November 2012 Press Report ............................................................................................ 20 
July 2012 CBO Report ...................................................................................................... 21 
March 2012 Navy Letter to Senator McCain .................................................................... 22 
CVN-78 Program Procurement Cost Caps .............................................................................. 27 
Potential Two-Ship Block Buy on CVN-79 and CVN-80 ....................................................... 28 
Issues Raised in December 2012 DOT&E Report .................................................................. 33 
Legislative Activity for FY2014 .................................................................................................... 38 
FY2014 Funding Request ........................................................................................................ 38 
FY2014 National Defense Authorization Act (H.R. 1960/S. 1197) ........................................ 38 
House (Committee Report) ............................................................................................... 38 
House (Floor Consideration) ............................................................................................. 41 
Senate ................................................................................................................................ 42 
FY2014 DOD Appropriations Act (H.R. 2397/S. 1429) ......................................................... 45 
House ................................................................................................................................. 45 
Senate ................................................................................................................................ 45 
 
Congressional Research Service 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Figures 
Figure 1. Navy Illustration of CVN-78 ............................................................................................ 3 
 
Tables 
Table 1. Procurement Funding for CVNs 78, 79, and 80 Through FY2018 .................................... 5 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, and 80 ................................... 7 
 
Appendixes 
Appendix. March 2013 Report To Congress on Construction Plan for CVN-79 .......................... 47 
 
Contacts 
Author Contact Information........................................................................................................... 65 
 
Congressional Research Service 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Introduction 
This report provides background information and potential oversight issues for Congress on the 
Gerald R. Ford (CVN-78) class aircraft carrier program. Congress’s decisions on the CVN-78 
program could substantially affect Navy capabilities and funding requirements and the 
shipbuilding industrial base. 
Background 
The Navy’s Aircraft Carrier Force 
The Navy’s current aircraft carrier force consists of 10 nuclear-powered Nimitz-class ships 
(CVNs 68 through 77) that entered service between 1975 and 2009. Until recently, the Navy’s 
aircraft carrier force included an 11th aircraft carrier—the one-of-a-kind nuclear-powered 
Enterprise (CVN-65), which entered service in 1961. CVN-65 was inactivated on December 1, 
2012, reducing the Navy’s carrier force from 11 ships to 10. The most recently commissioned 
carrier, George H. W. Bush (CVN-77), the final Nimitz-class ship, was procured in FY2001 and 
commissioned into service on January 10, 2009. CVN-77 replaced Kitty Hawk (CV-63), which 
was the Navy’s last remaining conventionally powered carrier.1 
Statutory Requirement to Maintain Not Less Than 11 Carriers 
Origin of Requirement 
10 U.S.C. 5062(b) requires the Navy to maintain a force of not less than 11 operational aircraft 
carriers. The requirement for the Navy to maintain not less than a certain number of operational 
aircraft carriers was established by Section 126 of the FY2006 National Defense Authorization 
Act (H.R. 1815/P.L. 109-163 of January 6, 2006), which set the number at 12 carriers. The 
requirement was changed from 12 carriers to 11 carriers by Section 1011(a) of the FY2007 John 
Warner National Defense Authorization Act (H.R. 5122/P.L. 109-364 of October 17, 2006). 
Waiver for Period Between CVN-65 and CVN-78 
As mentioned above, the carrier force dropped from 11 ships to 10 ships when Enterprise (CVN-
65) was inactivated on December 1, 2012. The carrier force is to return to 11 ships when its 
replacement, Gerald R. Ford (CVN-78), is commissioned into service. CVN-78 was originally 
scheduled to be delivered in September 2015, but its construction has been running behind 
schedule, and the Navy in May 2013 announced that the ship’s delivery date has been postponed 
to February 2016.2 Anticipating the gap between the inactivation of CVN-65 and the 
commissioning of CVN-78, the Navy asked Congress for a temporary waiver of 10 U.S.C. 
5062(b) to accommodate the period between the two events. Section 1023 of the FY2010 
                                                                  
1 The Kitty Hawk was decommissioned on January 31, 2009. 
2 Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for FY2014, May 2013, p. 13. 
Congressional Research Service 
1 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
National Defense Authorization Act (H.R. 2647/P.L. 111-84 of October 28, 2009) authorized the 
waiver, permitting the Navy to have 10 operational carriers between the inactivation of CVN-65 
and the commissioning of CVN-78. 
Funding and Procuring Aircraft Carriers 
Some Key Terms 
The Navy procures a ship (i.e., orders the ship) by awarding a full-ship construction contract to 
the firm building the ship. 
Part of a ship’s procurement cost might be provided through advance procurement (AP) funding. 
AP funding is funding provided in one or more years prior to (i.e., in advance of) a ship’s year of 
procurement. AP funding is used to pay for long-leadtime components that must be ordered ahead 
of time to ensure that they will be ready in time for their scheduled installation into the ship. AP 
funding is also used to pay for the design costs for a new class of ship. These design costs, known 
more formally as detailed design/non-recurring engineering (DD/NRE) costs, are traditionally 
incorporated into the procurement cost of the lead ship in a new class of ships. 
Fully funding a ship means funding the entire procurement cost of the ship. If a ship has received 
AP funding, then fully funding the ship means paying for the remaining portion of the ship’s 
procurement cost. 
The full funding policy is a Department of Defense (DOD) policy that normally requires items 
acquired through the procurement title of the annual DOD appropriations act to be fully funded in 
the year they are procured. In recent years, Congress has authorized DOD to use incremental 
funding for procuring certain Navy ships, most notably aircraft carriers. Under incremental 
funding, some of the funding needed to fully fund a ship is provided in one or more years after 
the year in which the ship is procured.3 
Incremental Funding Authority for Aircraft Carriers 
Section 121 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 
109-364 of October 17, 2006) granted the Navy the authority to use four-year incremental 
funding for CVNs 78, 79, and 80. Under this authority, the Navy could fully fund each of these 
ships over a four-year period that includes the ship’s year of procurement and three subsequent 
years. 
Section 124 of the FY2012 National Defense Authorization Act (H.R. 1540/P.L. 112-81 of 
December 31, 2011) amended Section 121 of P.L. 109-364 to grant the Navy the authority to use 
five-year incremental funding for CVNs 78, 79, and 80. Since CVN-78 was fully funded in 
FY2008-FY2011, the provision in practice applied to CVNs 79 and 80. 
                                                                  
3 For more on full funding, incremental funding, and AP funding, see CRS Report RL31404, Defense Procurement: 
Full Funding Policy—Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and 
CRS Report RL32776, Navy Ship Procurement: Alternative Funding Approaches—Background and Options for 
Congress, by Ronald O'Rourke. 
Congressional Research Service 
2 



Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Section 121 of the FY2013 National Defense Authorization Act (H.R. 4310/P.L. 112-239 of 
January 2, 2013) amended Section 121 of P.L. 109-364 to grant the Navy the authority to use six-
year incremental funding for CVNs 78, 79, and 80. Since CVN-78 was fully funded in FY2008-
FY2011, the provision in practice applies to CVNs 79 and 80. 
Aircraft Carrier Construction Industrial Base 
All U.S. aircraft carriers procured since FY1958 have been built by Newport News Shipbuilding 
(NNS), of Newport News, VA, a shipyard that is part of Huntington Ingalls Industries (HII). NNS 
is the only U.S. shipyard that can build large-deck, nuclear-powered aircraft carriers. The aircraft 
carrier construction industrial base also includes hundreds of subcontractors and suppliers in 
various states. 
Gerald R. Ford (CVN-78) Class Program 
The Gerald R. Ford (CVN-78) class carrier design (Figure 1) is the successor to the Nimitz-class 
carrier design.4 
Figure 1. Navy Illustration of CVN-78 
 
Source: Navy image accessed at http://www.navy.mil/management/photodb/photos/060630-N-0000X-001.jpg on 
April 20, 2011. 
                                                                  
4 The CVN-78 class was earlier known as the CVN-21 class, which meant nuclear-powered aircraft carrier for the 21st 
century.  
Congressional Research Service 
3 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The Ford-class design uses the basic Nimitz-class hull form but incorporates several 
improvements, including features permitting the ship to generate about 25% more aircraft sorties 
per day, more electrical power for supporting ship systems, and features permitting the ship to be 
operated by several hundred fewer sailors than a Nimitz-class ship, significantly reducing life-
cycle operating and support (O&S) costs. 
Navy plans call for procuring at least three Ford-class carriers—CVN-78, CVN-79, and CVN-80. 
CVN-78 
CVN-78, which was named for President Gerald R. Ford in 2007,5 was procured in FY2008. The 
Navy’s proposed FY2013 budget estimates the ship’s procurement cost at $12,829.3 million (i.e., 
about $12.8 billion) in then-year dollars. Of the ship’s total procurement cost, about $3.3 billion is 
for detailed design/non-recurring engineering (DD/NRE) costs for the class, and about $9.5 
billion is for construction of the ship itself. 
CVN-78 received advance procurement funding in FY2001-FY2007 and was fully funded in 
FY2008-FY2011 using congressionally authorized four-year incremental funding. The Navy did 
not request any procurement funding for the ship in FY2012 and FY2013. The Navy is requesting 
$588.1 million in procurement funding in FY2014, and plans to request another $729.0 million in 
procurement funding in FY2015, to cover cost growth on the ship. 
CVN-79 
CVN-79, which was named for President John F. Kennedy on May 29, 2011,6 is scheduled to be 
procured in FY2013. The ship received advance procurement funding in FY2007-FY2012, and 
the Navy plans to fully fund the ship in FY2013-FY2018 using congressionally authorized six-
year incremental funding. The Navy’s proposed FY2014 budget estimates CVN-79’s procurement 
cost at $11,338.4 million (i.e., about $11.3 billion) in then-year dollars, and requests $944.9 
million in procurement funding for the ship. 
CVN-80 
CVN-80, which was named Enterprise on December 1, 2012,7 is scheduled to be procured in 
FY2018. The Navy’s proposed FY2014 budget estimates the ship’s procurement cost at $13,874.2 
                                                                  
5 §1012 of the FY2007 defense authorization act (H.R. 5122/P.L. 109-364 of October 17, 2006) expressed the sense of 
the Congress that CVN-78 should be named for President Gerald R. Ford. On January 16, 2007, the Navy announced 
that CVN-78 would be so named. CVN-78 and other carriers built to the same design will consequently be referred to 
as Ford (CVN-78) class carriers. For more on Navy ship names, see CRS Report RS22478, Navy Ship Names: 
Background for Congress, by Ronald O’Rourke. 
6 See “Navy Names Next Aircraft Carrier USS John F. Kennedy,” Navy News Service, May 29, 2011, accessed online 
on June 1, 2011 at http://www.navy.mil/search/display.asp?story_id=60686. See also Peter Frost, “U.S. Navy’s Next 
Aircraft Carrier Will Be Named After The Late John F. Kennedy,” Newport News Daily Press, May 30, 2011. CVN-79 
is the second ship to be named for President John F. Kennedy. The first, CV-67, was the last conventionally powered 
carrier procured for the Navy. CV-67 was procured in FY1963, entered service in 1968, and was decommissioned in 
2007. 
7 The Navy made the announcement of CVN-80’s name on the same day that it deactivated the 51-year-old aircraft 
carrier CVN-65, also named Enterprise. (“Enterprise, Navy’s First Nuclear-Powered Aircraft Carrier, Inactivated,” 
Navy News Service, December 1, 2012; Hugh Lessig, “Navy Retires One Enterprise, Will Welcome Another,” Newport 
(continued...) 
Congressional Research Service 
4 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
million (i.e., about $13.9 billion) in then-year dollars. Under the Navy’s proposed FY2014 
budget, the ship is to receive advance procurement funding in FY2016-FY2017 and be fully 
funded in FY2018-FY2023 using congressionally authorized six-year incremental funding. 
Program Procurement Funding 
Table 1 shows procurement funding for CVNs 78, 79, and 80 through FY2018. 
Table 1. Procurement Funding for CVNs 78, 79, and 80 Through FY2018 
(Millions of then-year dollars, rounded to nearest tenth) 
FY CVN-78 
CVN-79 
CVN-80 
Total 
FY01 21.7 
(AP) 0 0 
21.7 
FY02 135.3 
(AP)  0  0 
135.3 
FY03 395.5 
(AP)  0  0 
395.5 
FY04 1,162.9 
(AP)  0  0 
1,162.9 
FY05 623.1 
(AP)  0  0 
623.1 
FY06 618.9 
(AP)  0  0 
618.9 
FY07 
735.8 (AP) 
52.8 (AP) 
0 
788.6 
FY08 
2,685.0 (FF) 
123.5 (AP) 
0 
2,808.6 
FY09 
2,684.6 (FF) 
1,210.6 (AP) 
0 
3,895.1 
FY10 
737.0 (FF) 
482.9 (AP) 
0 
1,219.9 
FY11  
1,712.5 (FF) 
903.3 (AP) 
0 
2,615.8 
FY12  
0 
554.8 (AP) 
0 
554.8 
FY13 (requested)a 0 
608.2 
(FF) 
0 
608.2 
FY14 (requested) 
588.1b 
 944.9 (FF) 
0 
1,533.0 
FY15 (projected) 
729.0b 1,834.1 
(FF) 
0 
2,563.1 
FY16 (projected) 
0 
1,235.6 (FF) 
682.8 (AP) 
1,918.4 
FY17 (projected) 
0 
1,496.0 (FF) 1,043.8 
(AP) 
2,539.8 
FY18 (projected) 
0 
1,891.8 (FF) 1,062.6 
(FF) 
2,954.4 
Source: FY2009-FY2014 Navy budget submissions. 
Notes: Figures may not add due to rounding. “AP” is advance procurement funding; “FF” is ful  funding.  
a.  The FY2013 column in the Navy’s FY2014 budget submission simply shows the figure that was requested 
for FY2013, not the final appropriated figure for FY2013. The figures shown in the table do not reflect the 
March 1, 2013, sequester on FY2013 funding and on FY2012 and prior-year funding that was unobligated on 
March 1, 2013.  
b.  Additional “cost to complete” funding to cover cost growth on CVN-78. 
                                                                  
(...continued) 
News Daily Press, December 2, 2012.) CVN-65 was the eighth Navy ship named Enterprise; CVN-80 is to be the 
ninth. 
Congressional Research Service 
5 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Increases in Estimated Unit Procurement Costs Since FY2008 Budget 
Table 2 shows changes in the estimated procurement costs of CVNs 78, 79, and 80 since the 
FY2008 budget submission.8 
                                                                  
8 CBO in 2008 and the Government Accountability Office (GAO) in 2007 questioned the accuracy of the Navy’s cost 
estimate for CVN-78. CBO reported in June 2008 that it estimated that CVN-78 would cost $11.2 billion in constant 
FY2009 dollars, or about $900 million more than the Navy’s estimate of $10.3 billion in constant FY2009 dollars, and 
that if “CVN-78 experienced cost growth similar to that of other lead ships that the Navy has purchased in the past 10 
years, costs could be much higher still.” CBO also reported that, although the Navy publicly expressed confidence in its 
cost estimate for CVN-78, the Navy had assigned a confidence level of less than 50% to its estimate, meaning that the 
Navy believed there was more than a 50% chance that the estimate would be exceeded. (Congressional Budget Office, 
Resource Implications of the Navy’s Fiscal Year 2009 Shipbuilding Plan, June 9, 2008, p. 20.) GAO reported in August 
2007 that: 
Costs for CVN 78 will likely exceed the budget for several reasons. First, the Navy’s cost estimate, 
which underpins the budget, is optimistic. For example, the Navy assumes that CVN 78 will be 
built with fewer labor hours than were needed for the previous two carriers. Second, the Navy’s 
target cost for ship construction may not be achievable. The shipbuilder’s initial cost estimate for 
construction was 22 percent higher than the Navy’s cost target, which was based on the budget. 
Although the Navy and the shipbuilder are working on ways to reduce costs, the actual costs to 
build the ship will likely increase above the Navy’s target. Third, the Navy’s ability to manage 
issues that affect cost suffers from insufficient cost surveillance. Without effective cost 
surveillance, the Navy will not be able to identify early signs of cost growth and take necessary 
corrective action. 
(Government Accountability Office, Defense Acquisitions[:] Navy Faces Challenges Constructing 
the Aircraft Carrier Gerald R. Ford within Budget, GAO-07-866, August 2007, summary page. See 
also Government Accountability Office, Defense Acquisitions[:] Realistic Business Cases Needed 
to Execute Navy Shipbuilding Programs, Statement of Paul L. Francis, Director, Acquisition and 
Sourcing Management Team, Testimony Before the Subcommittee on Seapower and Expeditionary 
Forces, Committee on Armed Services, House of Representatives, July 24, 2007 (GAO-07-943T), 
p. 15.) 
Congressional Research Service 
6 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Table 2. Changes in Estimated Procurement Costs of CVNs 78, 79, and 80 
(As shown in FY2008-FY2014 budgets, in millions of then-year dol ars) 
Budget 
CVN-78 CVN-79 CVN-80 
Estimated 
Scheduled 
Estimated 
Scheduled 
Estimated 
Scheduled 
procurement 
fiscal year of 
procurement 
fiscal year of 
procurement 
fiscal year of 
 
cost 
procurement 
cost 
procurement 
cost 
procurement 
FY08 
budget 
10,488.9 FY08  9,192.0  FY12 10,716.8 FY16 
FY09 
budget 
10,457.9 FY08  9,191.6  FY12 10,716.8 FY16 
FY10 budget 
10,845.8 
FY08 
n/aa FY13b n/aa FY18b 
FY11 
budget 
11,531.0 FY08 10,413.1 FY13 13,577.0 FY18 
FY12 
budget 
11,531.0 FY08 10,253.0 FY13 13,494.9 FY18 
FY13 budget 
12,323.2 
FY08 
11,411.0 
FY13c 13,874.2 FY18c 
FY14 
budget 
12,829.3 FY08 11,338.4 FY13 13,874.2 FY18 
% change: 
 
 
 
 
 
 
FY08 budget to 
-0.3  
Almost no 
 No 
change  
FY09 budget 
change 
FY09 budget to 
+3.7  n/a  n/a  
FY10 budget 
FY10 budget to 
+6.3  n/a  n/a  
FY11 budget 
FY11 budget to 
No change 
 
- 1.5 
 
- 0.1 
 
FY12 budget 
FY12 budget to 
+6.9%  +11.3%  +2.8%  
FY13 budget 
FY13 budget to 
+4.1%  - 
0.6%  
No 
change 
 
FY14 budget 
FY08 budget to 
+22.3%  +23.4%  +29.5%  
FY14 budget 
Source: FY2008-FY2014 Navy budget submissions. 
a.   n/a means not available; the FY2010 budget submission did not show estimated procurement costs for 
CVNs 79 and 80. 
b.   The FY2010 budget submission did not show scheduled years of procurement for CVNs 79 and 80; the 
dates shown here for the FY2010 budget submission are inferred from the shift to five-year intervals for 
procuring carriers that was announced by Secretary of Defense Gates in his April 6, 2009, news conference 
regarding recommendations for the FY2010 defense budget. 
c.  Although the FY2013 budget did not change the scheduled years of procurement for CVN-79 and CVN-80 
compared to what they were under the FY2012 budget, it lengthened the construction period for each ship 
by two years (i.e., each ship is scheduled to be delivered two years later than under the FY2012 budget). 
Program Procurement Cost Cap 
Section 122 of the FY2007 John Warner National Defense Authorization Act (H.R. 5122/P.L. 
109-364 of October 17, 2006) established a procurement cost cap for CVN-78 of $10.5 billion, 
plus adjustments for inflation and other factors, and a procurement cost cap for subsequent Ford-
class carriers of $8.1 billion each, plus adjustments for inflation and other factors. The conference 
report (H.Rept. 109-702 of September 29, 2006) on P.L. 109-364 discusses Section 122 on pages 
551-552. 
Congressional Research Service 
7 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Issues for Congress 
Impact of March 1, 2013, Sequester on FY2013 Funding 
One issue for Congress concerns the impact on the CVN-78 program of the March 1, 2013, 
sequester on FY2013 funding and unobligated prior-year funding. DOD’s June 2013 report to 
Congress on the March 1, 2013, sequester states that the sequester reduced FY2013 and prior-
year procurement funding for the CVN-78 program by $74.5 million.9 A June 21, 2013, press 
report states: 
So far, sequestration has not hindered test and evaluation efforts on [CVN-78’s] new 
technologies in the same way that some other programs have been affected, Rear Adm. Tom 
Moore [the program executive officer for aircraft carriers] said June 17.... 
Because [CVN-78] had no funding for construction in FY-13 because that funding was in 
previous budgets, the ship's construction wasn't hurt.... 
But [CVN-79] hasn't been so lucky.... 
"[CVN-]79's being funded over several years and so as long as the out-year money shows up, 
it really becomes more of a cash-flow issue," Moore said. "We'll probably have to slow some 
things down that we would have preferred to do in '13 but we'll have to catch up on and do 
later."10 
Potential Impact of Possible Late 2013/Early 2014 Sequester on 
FY2014 Funding 
Another potential issue for Congress concerns the potential impact on the CVN-78 program of a 
possible sequester on FY2014 funding and unobligated prior-year funding that might occur in late 
2013 or early 2014 under the terms of the Budget Control Act of 2011 (S. 365/P.L. 112-25 of 
August 2, 2011). 
Cost Growth 
Another issue for Congress concerns the cost growth on CVNs 78, 79, and 80 shown in Table 2, 
and the potential for further cost growth on the ships. As can be seen in the table, the estimated 
cost of CVN-78 has grown 22.3% since the submission of the FY2008 budget, and 4.1% since the 
submission of the FY2013 budget. As shown in Table 1, cost growth on CVN-78 has prompted 
the Navy to program $1,317.1 million in additional procurement funding for the ship in FY2014 
and FY2015. 
                                                                  
9 Department of Defense Report on the Joint Committee Sequestration for Fiscal Year 2013, June 2013, p. 36A (pdf 
page 86 of 438). 
10 Megan Eckstein, “Navy Sees Sequestration Hurting CVN-79 Construction, CVN-72 Refueling,” Inside the Navy, 
June 24, 2013. 
Congressional Research Service 
8 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Most of the cost growth on CVN-78 since the submission of the FY2013 budget was expected: 
The Navy stated in March 2012 that future budget submissions would show an additional $417 
million in cost growth on CVN-78 that was not captured in the FY2013 budget because this cost 
growth emerged late in the process for preparing the FY2013 budget, and because the Navy 
hoped that actions being taken to restrain cost growth in the CVN-78 program would reduce the 
figure to something less than $417 million before the FY2014 budget was submitted to 
Congress.11 The $417 million in anticipated cost growth equates to about 82% of the $506.1 
million in cost growth that has occurred on CVN-78 since the FY2013 budget. 
September 2013 GAO Report 
A September 2013 Government Accountability Office (GAO) report on the CVN-78 program 
stated the following regarding the potential for further cost growth on CVN-78: 
While construction of CVN 78 is more than halfway complete, the Navy and shipbuilder 
must still overcome significant technology development, design, and construction challenges 
in order to deliver a fully functional ship to the fleet at the currently budgeted cost of $12.8 
billion and the February 2016 delivery date. However, several critical technologies—
provided to the shipbuilder by the Navy—have encountered developmental delays and, 
subsequently, have not yet reached a level of maturity that will enable them to be effectively 
incorporated onto the ship. These delays are most evident in the land-based test programs for 
these technologies, which are lagging significantly behind schedule. At the same time, the 
ship’s design stability—a key factor in controlling future cost growth—is contingent on 
critical technologies maturing in the configurations currently anticipated. In addition, 
construction inefficiencies at the shipyard have delayed—and threaten additional delays to—
ship launch and delivery. These combined challenges and uncertainties suggest that more 
cost growth could occur for CVN 78.... 
Prior to the CVN 78 detail design contract award, the Navy had only built, tested, and 
integrated prototype components of the volume search radar in controlled laboratory 
environments. As we previously reported, these tests revealed deficiencies related to key 
components of the radar. Under the Navy’s 2008 program schedule, the volume search radar 
was to be developed and tested as part of the Zumwalt-class destroyer program and was 
expected to approach maturity following land-based testing in fiscal year 2009. The radar 
would then participate in combat system integration testing with the other major component 
of the dual band radar, the multifunction radar, and eventually demonstrate maturity as part 
of Zumwalt-class destroyer at-sea testing in fiscal year 2014. In 2010, however, to reduce 
Zumwalt-class construction costs, the Navy removed the volume search radar from the 
destroyer program and suspended remaining land-based testing, leaving key Ford-class 
testing requirements unaddressed. The Navy subsequently transferred remaining 
development work to the Ford class program and planned to resume land-based testing in 
fiscal year 2012 using an actual production unit of the radar—but contracting delays pushed 
the start of this testing out to fiscal year 2013. As a result of this delay, and the Navy’s desire 
not to slow down the current radar installation schedule for CVN 78, remaining land-based 
testing will be completed in fiscal year 2014, 4.5 years later than originally planned, using a 
less capable developmental radar array than the actual production configuration that will be 
installed on CVN 78. The Navy has also scheduled shipboard testing beginning in fiscal year 
2016 to complete additional volume search radar testing not executed on land. This testing 
schedule increases the risk that discovery of problems with the system will trigger costly 
design changes and rework aboard the ship.... 
                                                                  
11 Source: Navy meeting with CRS and CBO on the CVN-78 program, March 6, 2012. 
Congressional Research Service 
9 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Unlike the other critical technologies discussed above, [the EMALS] system was 
approaching maturity prior to the CVN 78 detail design contract award because the Navy had 
built and tested competitive prototypes of the system as part of the contractor selection 
process for EMALS development in 2004. Under the Navy’s 2008 program schedule, land-
based testing for the system was scheduled to occur between fiscal years 2008 and 2011. 
However, technical issues affecting the EMALS power interface and conversion systems, 
among other deficiencies, have slowed progress. The Navy’s 2012 development schedule 
calls for land-based testing to continue into fiscal year 2014, which, upon completion, the 
Navy expects will mature the EMALS technology. In the meantime, however, significant 
numbers of EMALS components have already been produced, delivered to the shipbuilder, 
and installed on CVN 78—even though the functional requirements, performance, and 
suitability of the system remain unproven.... 
The CVN 78 shipbuilder completed its 3D product model in November 2009—over a year 
after the construction contract was awarded. At contract award, 76 percent of the model was 
complete and the shipbuilder had already begun construction of at least 25 percent of its 
structural units under the previous construction preparation contract. While the model is now 
considered functionally complete, maintaining design stability depends on the critical 
technologies discussed above fitting within the space, weight, cooling, and power 
reservations allotted them. To date, evolving information about the attributes of these 
technologies has produced a weight/stability configuration for CVN 78 that leaves little 
margin to incorporate additional weight growth high up in the ship without making 
corresponding weight trade-offs elsewhere or compromising the future growth potential of 
the ship. Shipbuilder representatives have recently expressed concern about this possibility, 
particularly regarding additional design changes to critical technologies still in 
development—including the volume search radar, advanced arresting gear, and EMALS 
technologies. According to shipbuilder representatives, additional weight growth to the 
advanced arresting gear was of particular concern and could trigger a need for future 
structural and space modifications around the installed system. Further, until the advanced 
weapons elevators, joint precision approach and landing system, and evolved sea sparrow 
missile weapons link each demonstrate maturity, the likelihood of additional design changes 
to CVN 78 persists.... 
The Navy has taken steps to limit cost growth for EMALS and the advanced arresting gear, 
which are being developed and produced under contracts separate from the CVN 78 detail 
design and construction contract. Most notably, in 2010, the Navy negotiated firm fixed-
price contracts for production of these systems for CVN 78. According to the Navy, these 
contracts have helped cap cost growth for these systems and have incentivized more timely 
deliveries to the shipyard. While EMALS is farther along in development than both the dual 
band radar and advanced arresting gear systems, all have experienced significant cost 
growth, and costs are likely to increase, given the remaining work needed to fully develop, 
test, and integrate the systems on CVN 78. This potential for additional cost growth is also 
apparent based on the Navy’s experience with the most recent Nimitz-class carrier, CVN 77. 
That ship experienced cost growth during its system integration, even though that effort 
employed mostly nondevelopmental systems. 
Aside from the risk of cost growth stemming from the integration of critical technology 
systems into the ship, the shipbuilder’s cost and schedule performance under the detail 
design and construction contract suggests additional overruns are looming. Our review of the 
contractor’s earned value management data for the program indicates that shipbuilder cost 
pressures remain high and additional costs are likely, especially as key developmental items 
are integrated onto the ship. We reviewed 18 months of earned value management data for 
the CVN 78 ship program during the period of July 2011 through December 2012. During 
this time, the shipbuilder increased its estimate of the number of labor hours required to 
construct CVN 78 from 44.4 million to 47.3 million. Consequently, the shipbuilder’s 
Congressional Research Service 
10 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
budgeted cost grew substantially, from $4,758 million to $5,266 million (an increase of $508 
million). Our analysis shows that, as of December 2012, the contractor was forecasting an 
overrun at contract completion of over $913 million. This cost growth is attributable to the 
shipbuilder not accomplishing work as planned. The Navy has largely, but not fully, funded 
this cost growth within CVN 78’s $12.8 billion procurement budget. 
Further, the Navy’s current budget estimate of $12.8 billion for completing CVN 78 is 
optimistic because it assumes the shipbuilder will maintain its current level of performance 
throughout the remainder of construction. This assumption is inconsistent with historical 
Navy shipbuilding experiences for recent lead ships, which have suffered from performance 
degradation late in construction. Our previous work has shown that the full extent of cost 
growth does not usually manifest itself until after the ship is more than 60 percent complete, 
when key systems are being installed and integrated. In April 2013, the ship was 56 percent 
complete. The Director of DOD’s Cost Assessment and Program Evaluation office and the 
Congressional Budget Office—as well as Navy cost analysts and a Navy-commissioned 
expert panel—have also projected higher than budgeted procurement costs for CVN 78, with 
cost estimates ranging from $13.0 to $14.2 billion.12 
The report stated the following regarding the potential for further cost growth on CVN-79: 
The Navy and shipbuilder are implementing changes to the build strategy for CVN 79 aimed 
at reducing that ship’s costs before the construction contract is awarded, currently planned 
for September 2013. These changes include increased time allotted to construct the ship and 
in-yard construction process improvements. Remaining technical and design risks with CVN 
78, however, could interfere with the Navy’s ability to achieve its desired cost savings for 
CVN 79. These uncertainties also affect the Navy and contractor’s ability to assess the likely 
CVN 79 costs ahead of contract award and, when coupled with the existing sole source 
environment for aircraft carrier construction, compromise the government’s negotiating 
position for CVN 79. 
The Navy and its shipbuilder have learned valuable lessons from CVN 78 construction that 
have the potential to improve cost outcomes for the construction of the first follow-on ship, 
CVN 79. The shipbuilder plans to employ a new build strategy for CVN 79 that (1) allots 
more time to fund and construct the ship compared to CVN 78 and (2) implements process 
improvements aimed at completing more work earlier in the build process—steps that the 
Navy anticipates will achieve construction efficiency improvements as compared to CVN 78. 
However, remaining technical and design risks in the program could undermine the Navy’s 
ability to realize cost savings on CVN 79.... 
The Navy’s decision to fund CVN 79 construction over 6 years was coupled with a decision 
to increase the build time for the ship as compared to CVN 78. According to the Navy, it will 
use the additional time to improve CVN 79’s construction sequence and implement cost 
reduction initiatives. Further, Ford class shipbuilders report that the increased time afforded 
to CVN 79 construction provides additional opportunities to apply lessons learned from lead 
ship construction. The Navy expects the combined savings from these actions to more than 
offset the increased costs associated with extending the funding of the ship by 2 years. Figure 
9 compares CVN 78 and CVN 79 construction schedules.... 
                                                                  
12 Government Accountability Office, Ford-Class Carriers[:] Lead Ship Testing and Reliability Shortfalls Will Limit 
Initial Fleet Capabilities, GAO-13-396, September 2013, pp. 11, 16-17, 18, 20-21, 27-28. 
Congressional Research Service 
11 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
As part of CVN 79 construction, the shipbuilder plans to implement process improvements 
aimed at reducing the labor hours—and cost—required to construct the ship, as compared to 
CVN 78.... 
The core of the shipbuilder’s strategy for CVN 79 is moving more planned work—including 
complex ship assemblies—earlier in the build process so that it can be completed in shipyard 
workshops. Generally, the earlier work can be sequenced in the build process, the more 
efficiently it can be completed.... 
Although the Navy and shipbuilder expect CVN 79’s design to be virtually the same as that 
of the lead ship—another step toward improving follow-on ship outcomes—remaining 
developmental and design risks in the program could undermine the actual realization of cost 
savings. As discussed above, these risks are exemplified by key ship systems not progressing 
through their land-based test programs at the pace the Navy anticipated—delays largely 
attributable to persisting technical deficiencies. Navy and shipbuilder efforts to resolve these 
deficiencies on CVN 78—concurrent with follow-on ship construction—are likely to lead to 
redesign and potentially costly out of sequence work or rework for CVN 79. If these 
discoveries and fixes disrupt CVN 79 construction and offset planned improvements, they 
could jeopardize the Navy’s ability to complete the ship within planned cost and schedule 
estimates. 
The Navy’s cost estimate for CVN 79 detail design and construction is closely linked to 
CVN 78 outcomes and reflects an expectation that the shipbuilder will deliver the lead ship 
within current labor hour estimates. One key component of the CVN 79 cost estimate is a 
Navy assumption that 15 percent fewer labor hours will be required to construct the follow-
on ship as compared to the lead ship. This estimate is also underpinned by expectations that 
the shipbuilder’s current level of performance will persist between now and lead ship 
delivery. Further, the Navy’s budget for CVN 79 is predicated on even higher performance 
gains than those forecast in the cost estimate—notably, 20 percent fewer labor hours in 
construction as compared to CVN 78. Yet, as we previously detailed, the Navy’s 
understanding of the costs required to construct and deliver CVN 78 remains incomplete. 
These knowledge gaps add risk and uncertainty to CVN 79 cost and budget estimates.13 
June 2013 Press Report 
A June 27, 2013, press report stated: 
The U.S. Navy should delay the award of a multibillion-dollar contract to Huntington Ingalls 
Industries Inc.to build the second aircraft carrier in a new class as the first one faces failings 
from its radar to the gear that launches planes, congressional investigators said. 
“Technical, design and construction challenges” with the first carrier, the USS Gerald R. 
Ford, have caused “significant cost increases and reduce the likelihood that a fully functional 
ship will be delivered on time,” the Government Accountability Office said in a draft report 
obtained by Bloomberg News.... 
Delays and “reliability deficiencies” with the flattop’s new dual-mission radar, 
electromagnetic launch system and arresting gear for aircraft mean that the Ford “will likely 
face operational limitations that extend past commissioning” in March 2016 and “into initial 
deployments,” the agency said. 
                                                                  
13 Government Accountability Office, Ford-Class Carriers[:] Lead Ship Testing and Reliability Shortfalls Will Limit 
Initial Fleet Capabilities, GAO-13-396, September 2013, pp. 41-42, 43, 44-45. 
Congressional Research Service 
12 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The GAO, the investigative arm of Congress, said that’s reason enough to delay the contract 
that’s scheduled to be issued this year for the second ship, the USS John F. Kennedy.... 
 “It will be important to avoid repeating mistakes” in the contract for the Kennedy, the GAO 
said. “Staying within budget” will require the Navy to reduce “significant risk mainly by 
completing land-based testing for critical technologies before negotiating a contract” with 
Newport News, Virginia-based Huntington Ingalls. 
Beci Brenton, a company spokeswoman, said in a telephone interview that “it would not be 
appropriate to comment on a draft report.” Naval Sea Systems Command spokeswoman 
Colleen O’Rourke14 said in a statement that “as the Navy is currently working with the GAO 
on this report, it would be inappropriate to comment on any draft findings at this time. When 
the report is finalized, it will include Navy comments.” 
The Navy remains committed to the Ford-class carrier as a needed capability, said a Navy 
official who declined to be identified before the GAO releases its final report. The Navy is 
confident that the first vessel will be delivered on schedule and that lessons learned from 
building it will be applied to reduce the cost of the second ship, the official said.... 
While the GAO said that the Navy and Huntington Ingalls are taking steps to control costs 
for the Ford, most increases occur after a vessel is 60 percent complete and key systems are 
installed and integrated. The Ford is now 56 percent complete. 
Even the current $12.8 billion estimate is “optimistic because it assumes the shipbuilder will 
maintain its current level of performance throughout the remainder of construction,” the 
GAO said.... 
The Pentagon’s independent cost-estimating office, the Congressional Budget Office and a 
Navy-commissioned panel project final costs as high as $14.2 billion, the GAO said.... 
“As it now stands, the Navy will not be positioned to deliver a fully capable ship at the 
time,” the GAO said.  
“Reliability shortfalls facing key Ford-class systems cloud the Navy’s ability to forecast 
when, or if” the carrier will meet the aircraft sortie rates and reduced manning requirements 
that distinguish it from the older Nimitz class, the GAO said. O’Rourke, the Naval Sea 
Systems Command spokeswoman, wouldn’t comment on the specific value of the potential 
detailed design and construction contract to Huntington Ingalls for the Kennedy that the 
GAO said is due in September.... 
The largest share of the cost increase for the Ford, 38 percent, stemmed from technologies 
delivered by the Navy, including the radar, launch system and arresting gear, according to 
the GAO. 
The electromagnetic launch system made by San Diego-based General Atomics has 
increased to $742.6 million, up 134 percent since 2008, the GAO said. The cost of arresting 
gear also made by the company increased 125 percent to $169 million. 
Raytheon Co.’s dual-band radar has increased 140 percent to $484 million, according to data 
cited by the GAO. Twenty-seven percent of the cost growth was pegged to shipbuilder 
design issues and another 27 percent to construction, both attributed to Huntington Ingalls.  
                                                                  
14 Colleen O’Rourke is not related to Ronald O’Rourke. 
Congressional Research Service 
13 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Huntington Ingalls is building the Ford under a $4.9 billion detailed design contract that 
covers the shipbuilder’s portion of constructing the vessel. It doesn’t cover other costs, such 
as the nuclear reactor to power the ship and other government-furnished equipment.... 
The GAO said its analysis indicates that Huntington Ingalls “was forecasting an overrun at 
contract completion of over $913 million” that it said stemmed from “the shipbuilder not 
accomplishing work as planned.” 
Huntington’s Brenton said in an e-mail in May that, “as the first new design carrier 
beginning construction in more than 40 years,” the Ford “is designed to provide increased 
capability and reduced total ownership cost by about $4 billion compared to Nimitz-class 
carriers.” 
“For this first-of-class ship, construction commenced in parallel with design completion 
based on earlier decisions at Department of Defense,” she said. “Ongoing design during the 
construction process caused delay and inefficiencies in procurement, manufacturing, and 
assembly.”15 
March 2013 Report to Congress (Released May 2013) 
A March 2013 report to Congress on the Navy’s plan for building CVN-79 that was released to 
the public on May 16, 2013, states in its executive summary: 
As a result of the lessons learned on CVN 78, the approach to carrier construction has 
undergone an extensive affordability review and the Navy and the shipbuilder have made 
significant changes on CVN 79 that will significantly reduce the cost to build the ship. These 
include four key construction areas: 
--  CVN 79 construction will start with a complete design and a complete bill of material 
--  CVN 79 construction will start with a firm set of stable requirements 
--  CVN 79 construction will start with the development complete on a host of new 
technologies inserted on CVN 78 ranging from the Electromagnetic Aircraft Launch System 
(EMALS), the Dual Band Radar, and the reactor plant, to key valves in systems throughout 
the ship 
--  CVN 79 construction will start with an ‘optimal build’ plan that emphasizes the 
completion of work and ship outfitting as early as possible in the construction process to 
optimize cost and ultimately schedule performance. 
In addition to these fundamentals, the Navy and the shipbuilder are tackling cost through a 
series of other changes that when taken over the entire carrier will have a significant impact 
on construction costs. The Navy has also imposed cost targets and is aggressively pursuing 
cost reduction initiatives in its government furnished systems. A detailed accounting of these 
actions is included in this report. 
The actions discussed in this report are expected to reduce the material cost of CVN 79 by 
10-20% in real terms from CVN 78, to reduce the number of man-hours required to build the 
                                                                  
15 Tony Capaccio, “Navy Should Delay Next Carrier Amid Troubles, GAO Says,” Bloomberg.com, June 27, 2013. 
Congressional Research Service 
14 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
CVN 79 by 15-25% from CVN 78, and to reduce the cost of government furnished systems 
by 5-10% in real terms from CVN 78.16 
For the full text of the navy’s report, see Appendix. 
December 31, 2012, SAR (Released May 2013) 
The December 31, 2012, Selected Acquisition Report (SAR) for the CVN-78 program, which was 
released in May 2013, states: 
The CVN 78 is experiencing cost growth due to “first of class” material availability (i.e., 
valves, actuators), construction labor inefficiencies, and challenges associated with 
concurrent development and integration of new Government Furnished Equipment (GFE) 
and Contractor Furnished Equipment (CFE) systems during lead ship design and 
construction. For material costs, the variance reflects challenges associated with a shrinking 
supplier base, procurement of developmental contractor furnished components, and vendor 
qualification on CVN 78 unique items. Labor inefficiencies are the result of “first of class” 
challenges. The effect of new and thinner steels on structural erection was greater than 
expected, slowing production and requiring more hours than planned for straightening, 
temporary structure and rigging. HII-NNS also experienced “first of class” learning 
associated with the new CVN 78 Class modular build strategy, including movement, blast 
and coat, and assembly area footprint difficulties for larger, reconfigured CVN 78 structural 
units. Delays in the delivery of new developmental components as well as engineering 
products required to develop construction work package also inhibited labor performance. 
During 2012, HII-NNS continued its design and production efforts on CVN 78. Quarterly 
Progress Reviews were held to manage and assess the status of design and production on 
CVN 78. As of February 17, 2013, the construction effort was 67.3% complete based on 
contract dollars. The landing of the island occurred on January 26, 2013. The shipbuilder has 
proposed a revised Estimate at Completion (EAC) increasing Direct Labor from 43.9 to 47.3 
million man hours that incorporates their assessment of performance trends and associated 
recovery efforts for both construction and support areas. The Navy is evaluating this 
proposed increase with emphasis on mitigating key cost and schedule drivers. The Navy 
continues to work with the Participating Acquisition Resource Managers (PARMs) to 
identify and remove barriers to improve cost and schedule performance for the new 
developmental GFE systems. HII-NNS has rescheduled the CVN 78 launch from July 2013 
to November 2013. Although shipbuilder actions to resolve “first of class” issues have 
retired some technical and schedule risk, HII-NNS has been unable to retire all schedule risk, 
resulting in a four month delay to the launch of CVN 78, with associated impact to delivery. 
The Navy agrees with the delay to launch. Delivery is expected to be delayed until 
approximately 2nd Quarter FY 2016. 
The Navy is submitting reports to the four defense committees addressing cost performance 
of the CVN 78 detail design and construction in response to Senator John McCain’s letter of 
August 11, 2011. At the direction of the Assistant Secretary of the Navy for Research, 
Development and Acquisition (ASN(RD&A)), an independent team conducted an end-to-end 
assessment of CVN 78 cost variance that included opportunities to prevent further increases. 
Recommendations from the report, briefed to ASN(RD&A) on December 21, 2011, are 
                                                                  
16 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, p. 3. An annotation on 
the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was 
posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To 
Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013. 
Congressional Research Service 
15 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
being implemented. Recommendations from the CVN 78 end to end reviews have been 
consolidated into 38 actionable items that are been tracked to completion. As of March 18, 
2013, 17 recommendations have been implemented with 21 recommendations in progress. 
All recommendations are expected to be implemented by September 2014. The review team 
reconvened in 2012 and concluded the program offices action plan adequately addresses 
their recommendations. 
The high level of design maturity and material certification for the CVN 79 provides a stable 
technical baseline for material procurement cost and schedule performance, which supports 
the development and execution of an improved and reliable build plan. The Construction 
Preparation (CP) Contract for CVN 79 advance procurement research, design, and 
engineering was awarded on January 15, 2009. An extension to CP efforts through FY 2013 
was awarded in March 2013. 
To enable full ship-set material buys for cost reduction benefits and to ensure material 
availability, two material procurement contract modifications were awarded to HII-NNS 
during FY 2012. A third material procurement award was executed in March 2013. CVN 79 
affordability is being driven through several areas. The CVN 79 is a design roll-over from 
CVN 78, with changes for improved producibility, reduced cost, and limited fact-of-life 
obsolescence issues. Lessons learned during the construction of CVN 78 are resulting in 
changes to the CVN 79 build plan to improve production efficiency. In addition, production 
improvements are being achieved through implementation of several initiatives aimed at 
driving work to be executed at the most efficient time (typically in the shop or on the platen 
rather than in the dry-dock or after launch), as well as driving learning curve performance 
into subsets of the ship construction (creation of “families of units” and work cells). In the 
aggregate, the plan for CVN 79 construction will substantially drive down costs. 
The CVN 79 DD&C Request for Proposal (RFP) was provided to HII-NNS on October 2, 
2012. The CVN 79 DD&C contract is planned for award in September 2013. Unlike the 
CVN 78 DD&C which is a Cost Plus Incentive Fee (CPIF) contract, the Navy plans to 
negotiate a Fixed Price Incentive (FPI) contract with a simplified structure for CVN 79.17 
The SAR also states: 
The CVN 79 is budgeted at an aggressive but achievable target. 
The Navy and shipbuilder have made fundamental change in the manner in which the CVN 
79 will be built to incorporate lessons learned from CVN 78 and eliminate the key 
contributors to cost performance challenges realized in the construction of CVN 78. The 
approach to carrier construction has undergone an extensive affordability review, the results 
of which are reflected in the CVN 79 budget. Further improvements are planned for CVN 80 
but have not yet been incorporated into the CVN 80 cost estimates. The Navy is committed 
to driving down aircraft carrier construction costs, and fully expects future estimates for 
CVN 80 to reflect a continued downward trend.18 
Regarding a contract that NNS has with the Navy for detailed design and construction (DD&C) 
work on CVN-78—a contract that accounts for a portion of the ship’s total cost—the SAR states 
that the value of the contract has grown from an initial price of $4,910.5 million to a current price 
of $5,885.6 million, and that NNS and the Navy estimate that the price will grow further, to 
                                                                  
17 Department of Defense, Selected Acquisition Report (SAR), CVN 78 Class, December 31, 2012, pp. 5-6. 
18 Department of Defense, Selected Acquisition Report (SAR), CVN 78 Class, December 31, 2012, p. 30. 
Congressional Research Service 
16 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
$6,665.6 (NNS’s estimate) or $6,638.7 million (the Navy’s estimate) by the time the contract is 
completed (i.e., estimated price at completion).19 In discussing these figures, the SAR states: 
The unfavorable net change in the cost variance is due to material cost growth (86%), labor 
inefficiencies (25%), Overhead improvement (-3%), and Facilities Capital Cost of Money 
(FCCM) improvement (-8%). The material variances are due to market forces, unanticipated 
impacts of a "first of class" specification on contractor furnished material costs (e.g. valves, 
electrical components, steel and other commodities), and refined understanding of material 
requirements as the ship design matured. Labor inefficiencies are the result of "first of class" 
challenges including producibility issues (e.g. thin plate steel, weld distortion, and the 
increased use of temporary structures and rigging). Additionally, increased supervision has 
been required to manage the above challenges and a developing workforce. 
The favorable net change in the schedule variance is due to improvement in material 
availability and the overall decrease in design hold ups, which have resulted in a significant 
increase in workable work packages available to the assembly trades. This increase in 
available work, coupled with the significant increase in manning and improved performance 
of the assembly trades, has resulted in an overall improvement in schedule performance.20 
May 2013 Navy Testimony 
In its prepared statement for a May 8, 2013, hearing on Navy shipbuilding programs before the 
Seapower subcommittee of the Senate Armed Services Committee, the Navy stated that 
In 2011, the Navy identified spiraling cost growth [on CVN-78] associated with first of class 
non-recurring design, contractor and government furnished equipment, and ship production 
issues on the lead ship. The Navy completed an end-to-end review of CVN 78 construction 
in December 2011 and, with the shipbuilder, implemented a series of corrective actions to 
stem, and to the extent possible, reverse these trends. While cost performance has stabilized, 
incurred cost growth is irreversible.... 
As a result of lessons learned on CVN 78, the approach to carrier construction has undergone 
an extensive affordability review; and the Navy and the shipbuilder have made significant 
changes on CVN 79 that will reduce the cost to build the ship. CVN 79 construction will 
start with a complete design, firm requirements, and material economically procured and on 
hand in support of production need. The ship’s build schedule also provides for increased 
completion levels at each stage of construction with resulting improved production 
efficiencies.... 
Inarguably, this new class of aircraft carrier brings forward tremendous capability and life-
cycle cost advantages compared to the NIMITZ-class it will replace. However, the design, 
development and construction efforts required to overcome the technical challenges inherent 
to these advanced capabilities have significantly impacted cost performance on the lead ship. 
The Navy continues implementing actions from the 2012 detailed review of the FORD-Class 
build plan to control cost and improve performance across lead and follow ship contracts. 
This effort, taken in conjunction with a series of corrective actions with the shipbuilder on 
the lead ship, will not recover costs to original targets for GERALD R. FORD [CVN-78], but 
                                                                  
19 Department of Defense, Selected Acquisition Report (SAR), CVN 78 Class, December 31, 2012, p. 56. 
20 Department of Defense, Selected Acquisition Report (SAR), CVN 78 Class, December 31, 2012, p. 56. 
Congressional Research Service 
17 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
should improve performance on the lead ship while fully benefitting CVN 79 and following 
ships of the class.21 
In the discussion portion of the hearing, Sean Stackley, the Assistant Secretary of the Navy for 
Research, Development and Acquisition (i.e., the Navy’s acquisition executive), testified that 
First, the cost growth on the CVN-78 is unacceptable. The cost growth dates back in time to 
the very basic concepts that went into take in the Nimitz-class and doing a total redesign of 
the Nimitz class to get to a level of capability and to reduce operating and support cost for 
the future carrier. Far too much risk was carried into the design of the first of the Ford-class. 
Cost growth stems to the design was moving at the time production started. The vendor base 
that was responsible for delivering new components and material to support the ship 
production was (inaudible) with new developments in the vendor base and production plan 
do not account for the material ordering difficulties, the material delivery difficulties and 
some of the challenges associated with building a whole new design compared to the 
Nimitz.... 
Sir, for CVN-79, we have—we have held up the expenditures on CVN-79 as we go through 
the details of—one, ensuring that the design of the 78 is complete and repeated for the 79s 
[sic] that we start with a clean design. 
Two, we're going through the material procurement. We brought a third party into 
assessment material-buying practices at Newport News to bring down the cost of material. 
And we're metering out the dollars for buying material until it hits the objectives that we're 
setting for CVN-79 through rewriting the build plan on CVN-79. 
If you take a look at how the 78 is being constructed, far too much work is being 
accomplished late in the build cycle. So we are rewriting the build plan for CVN-79, do more 
work in the shops where it’s more efficient, more work in the buildings where it’s more 
efficient, less work in the dry dock, less work on the water. And then we're going after the 
rates—the labor rates and the investments needed by the shipbuilder to achieve these 
efficiencies.22 
Later in the hearing, Stackley testified that 
the history in shipbuilding is since you don't have a prototype for a new ship, the first of 
class referred to as the lead ship is your prototype. And so you carry a lot of risk into the 
construction of that first of class. 
Also, given the nature that there’s a lengthy design development and build span associated 
with ships, so there is a certain amount of overlap or concurrency that occurs between the 
development of new systems that need to be delivered with the first ship, the incorporation of 
the design of those new systems and the actual construction. And so to the extent that there is 
change in a new ship class then the risk goes up accordingly. 
                                                                  
21 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and 
Acquisition) and Vice Admiral Allen G. Myers, Deputy Chief of Naval Operations for Integration of Capabilities and 
Resources and Vice Admiral Kevin M. McCoy, Commander, Naval Sea Systems Command, Before the Subcommittee 
on Seapower of the Senate Armed Services Committee on Department of the Navy Shipbuilding Programs, May 8, 
2013, p. 8. 
22 Transcript of hearing. 
Congressional Research Service 
18 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
In the case of the CVN-78, the degree of change compared to the Nimitz was fairly 
extraordinary all for good reasons, good intentions, increased capability, increased 
survivability, significant reduction in operating and support costs. So there was a 
determination that will take on this risk in order to get those benefits, and the case of the 
CVN-78, those risks are driving a lot of the cost growth on the lead ship. 
When you think about the follow ships, now you've got a stable design, now your vendor 
base has got a production line going to support the production. Now you've got a build plan 
and a workforce that has climbed up on the learning curve to drive cost down. So you can 
look at—you can look at virtually every shipbuilding program and you'll see a significant 
drop-off in cost from that first of class to the follow ships. 
And then you look for a stable learning curve to take over in the longer term production of a 
ship class. 
Carriers are unique for a number of reasons, one of which we don't have an annual 
procurement of carriers. They're spread out over a five and, in fact, in the case of 78 as much 
as seven-year period. So in order to achieve that learning, there are additional challenges 
associated with achieving that learning. And so we're going at it very deliberately on the 
CVN-79 through the build plan with the shipbuilder to hit the line that we've got to have—
the cost reductions that we've got to have on the follow ships of the class.23 
March 2013 GAO Report 
A March 2013 GAO report assessing major DOD weapon acquisition programs stated the 
following regarding the status of the CVN-78 program, including the potential for cost growth: 
Technology Maturity 
According to the Navy, 6 of CVN 78’s 13 critical technologies are mature, and the remaining 
7 are approaching maturity. Delays developing and producing the dual band radar (DBR) and 
advanced arresting gear (AAG) have driven inefficient, out of sequence construction work 
and caused the Navy to defer some key tests until after installation. The Navy’s decision to 
remove DBR’s volume search radar (VSR) component from the DDG 1000 destroyer shifted 
responsibility for maturing DBR to CVN 78, and the resulting restart of testing has been 
slow. Further, because a fully configured, production unit VSR is unavailable, the Navy is 
using a less robust, lower powered prototype to complete testing. At present, the first test of 
a fully configured, integrated DBR will be aboard CVN 78 after ship delivery—a strategy 
that introduces risks. Malfunctions in the water twisters, components used to absorb energy 
created when arresting aircraft, have slowed the development of AAG. To support 
construction, the Navy plans to produce and install AAG aboard CVN 78 prior to completing 
system development, which may risk retrofits late in construction. The electromagnetic 
aircraft launch system (EMALS) has successfully launched a wide range of aircraft during 
land based testing using a single launcher and four motor generators. The shipboard system 
will employ a more complex configuration of four launchers and 12 generators sharing a 
power interface. Both EMALS and AAG face reliability challenges, and neither system is 
expected to attain minimum required reliability until more than 10 years after CVN 78 
delivery. 
Design Maturity 
                                                                  
23 Transcript of hearing. 
Congressional Research Service 
19 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
CVN 78 completed its 3D product model in November 2009—over a year after the 
construction contract award. At contract award, 76 percent of the model was complete and 
the shipbuilder had already begun construction of at least 25 percent of structural units under 
a previous construction preparation contract. While the model is now considered functionally 
complete, maintaining design stability depends on technologies fitting within the space, 
weight, cooling, and power reservations allotted them. Shipboard testing may reveal a need 
for design changes. In addition, as construction progresses, the shipbuilder is discovering 
“first-of-class” type design changes, which it will use to update the model prior to CVN 79 
construction. 
Production Maturity 
According to program officials, CVN 78 is approximately 51 percent complete. Procurement 
costs for the lead ship have grown by over 17 percent since authorization of construction in 
fiscal year 2008, largely due to problems encountered in construction. Specifically, the new 
steel plating used for ship decks excessively warped and flexed during construction, which 
contributed to lower than desired levels of preoutfitting. In addition, the shipbuilder has 
experienced a shortage of the new valves critical for installing and testing different piping 
systems within the ship, and lagging government-furnished equipment deliveries have 
required deviation from the planned build sequence. 
Other Program Issues 
As requested, we reviewed whether individual subcontracting reports from the prime 
contractor for the program were accepted on eSRS [Electronic Subcontracting Reporting 
System]. The government uses subcontracting reports on eSRS as one method of monitoring 
small business participation. As of December 2012, eSRS indicated that none of the 
associated subcontracting reports for CVN 78’s two contracts have been accepted. 
Program Office Comments 
In commenting on a draft of this assessment, the program office stated that the shipbuilder is 
applying lessons learned from CVN 78 construction to improve production strategies and 
reduce labor hours needed to construct follow-on ships (CVN 79 and CVN 80). Further, the 
program office does not expect to repeat CVN 78’s “first of class” design and production 
challenges on CVN 79 and CVN 80. Program officials also stated that using a 
nonproduction-representative VSR prototype for DBR land-based testing has mitigated much 
of the impact of the DDG 1000 descope of VSR and will be beneficial in exhibiting dual 
band functionality prior to ship delivery. In addition, program officials stated that the 12 
current critical technologies in the program have met their system maturity goals, noting that 
an oversight team led by the Office of the Secretary of Defense disbanded in 2012 once each 
of these technologies was determined to be approaching maturity or mature. The program 
office also provided technical comments, which were incorporated where deemed 
appropriate.24 
November 2012 Press Report 
A November 29, 2012, press report stated: 
                                                                  
24 Government Accountability Office, Defense Acquisitions[:] Assessments of Selected Weapon Programs, GAO-13-
294SP, March 2013, p. 70. See also Michael Welles Shapiro, “Valve Shortage Drives Up Cost Of Shipyard’s Ford 
Carrier,” Newport News Daily Press, March 30, 2013. 
Congressional Research Service 
20 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Huntington Ingalls Industries Inc. will miss its 2012 target for reducing costs on the USS 
Gerald R. Ford, the aircraft carrier that will be the most expensive U.S. warship. 
The shipbuilder will fall short of getting 86 cents of planned work accomplished for every 
dollar spent, in part because of late component deliveries from subcontractors, according to 
the Navy admiral responsible for carrier development and construction.... 
 “They have continued to improve in the right direction, but they did not make it to 86” 
percent, Rear Admiral Thomas Moore, the Navy’s program executive officer for aircraft 
carriers, said in a phone interview. The Navy hopes the company will eventually get $1 of 
value from every $1 spent, he said.... 
“There are many challenges” in building a prototype that’s also the first production vessel of 
a three-ship class, Beci Brenton, a spokeswoman for the Newport News, Virginia-based 
company, said in an e-mailed statement. 
The company “has developed and implemented a host of improvement actions” this year, she 
said. “We have continued to advance the shipbuilding industry in tooling, material controls 
and craft performance through the use of innovation in technology, process changes and 
teaming.”... 
Huntington Ingalls’ cost efficiency goals have been “challenging but attainable, and they met 
them and did well in 2011,” Moore said. “They did not meet all those goals in 2012, and we 
will sit down and figure out where we are going with them in 2013.” 
Reaching the 86 percent mark would have helped reduce what’s now an estimated $884 
million overrun on the design and construction contract. The Navy’s share is $690 million. 
Huntington’s share is $194 million, which would be forfeited if the overrun isn’t reduced. 
Moore said Huntington Ingalls’ failure to hit its efficiency goal this year won’t increase the 
cost estimate for the next carrier in the class, the USS John F. Kennedy. 
“My expectation is that we are starting with a clean sheet of paper,” he said. “I fully expect” 
the second carrier’s costs “to be significantly below where we end up on,” the Ford, he 
said.25 
July 2012 CBO Report 
A July 2012 CBO report on the potential cost of the Navy’s FY2012 30-year shipbuilding plan 
states (with costs expressed in constant FY2012 dollars): 
The Navy’s projected cost of the lead ship of the CVN-78 class grew by 18 percent between 
the President’s budget requests for 2008 and 2013. The Navy’s budget now projects the lead 
ship’s cost to be $13.1 billion (about what CBO estimated in its analysis of the Navy’s 2011 
plan), but further increases are likely. According to information provided by the Navy, in 
fiscal year 2014 the service will request an extra $497 million ($564 million in 2014 dollars) 
to cover additional cost growth and additional tooling and vendor services. Including that 
money in the Navy’s estimate boosts the expected cost of the lead ship to $13.6 billion. (That 
                                                                  
25 Tony Capaccio, “Huntington Ingalls Aircraft Carrier To Miss Cost-Reduction Goal,” Bloomberg Government 
(bgov.com), November 29, 2012. 
Congressional Research Service 
21 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
amount does not include $4.7 billion in research and development costs that apply to the 
entire class.) 
To estimate the cost of the lead ship of the CVN-78 class, CBO used the actual costs of the 
previous carrier—the CVN-77—and then adjusted them for higher costs for government-
furnished equipment and for more than $3 billion in costs for nonrecurring engineering and 
detail design (the plans, drawings, and other one-time items associated with the first ship of a 
new class). CBO estimates that completing the lead CVN-78 will cost $14.2 billion. 
Subsequent ships of that class will not require as much funding for one-time items, although 
they will incur the higher costs for government-furnished equipment. Altogether, CBO 
estimates the average cost of the 6 carriers in the 2013 plan at $13.0 billion, compared with 
the Navy’s estimate of $10.9 billion.... 
The final cost of the CVN-78 could be even higher than CBO’s estimate, for several reasons. 
First, many lead ships built in the past 20 years have experienced cost growth of more than 
30 percent. CBO’s estimate for the lead ship already falls within the range of cost growth in 
lead ships, but construction is only about 40 percent complete. Historically, more cost 
growth has occurred in the latter stages of ship construction, when systems are being 
installed and integrated. Second, with the increase in the Navy’s estimate, the Navy, in a 
written response to CBO and the Congressional Research Service, stated that the service has 
budgeted the CVN-78 to a “greater than 50th” percentile of possible cost outcomes. Because 
the Navy has not reported a precise probability, the service’s view of the probability that the 
final cost will exceed its estimate is unclear. Third, a number of critical technologies that are 
supposed to be incorporated into the ship, such as a new electromagnetic catapult system for 
launching aircraft, remain under development and will require integration as the ship nears 
the final stages of construction. Difficulties in completing that integration could arise and 
increase costs, and those increases would also probably affect the costs for subsequent ships 
of the class. However, the Navy and the shipbuilder recognize those issues and are actively 
managing the CVN-78 program to reduce costs and prevent further growth. If they succeed, 
then the cost of the lead ship could be less than CBO’s estimate.26 
March 2012 Navy Letter to Senator McCain 
Secretary of the Navy Ray Mabus, in a letter with attachment sent in late March 2012 to Senator 
John McCain on controlling cost growth in the CVN-78, stated: 
Dear Senator McCain:  
Thank you for your letter of March 21, 2012, regarding the first-of-class aircraft carrier, 
GERALD R. FORD (CVN 78). Few major programs carry greater importance or greater 
impact on national security, and no other major program comprises greater scale and 
complexity than the Navy’s nuclear aircraft carrier program. Accordingly, successful 
execution of this program carries the highest priority within the Department of the Navy.  
I have shared in the past my concern when I took office and learned the full magnitude of 
new technologies and design change being brought to the FORD. Requirements drawn up 
more than a decade prior for this capital ship drove development of a new reactor plant, 
propulsion system, electric plant and power distribution system, first of kind electromagnetic 
aircraft launching system, advanced arresting gear, integrated warfare system including a 
new radar and communications suite, air conditioning plant, weapons elevators, topside 
                                                                  
26 Congressional Budget Office, An Analysis of the Navy’s Fiscal Year 2013 Shipbuilding Plan, July 2012, p. 16. 
Congressional Research Service 
22 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
design, survivability improvements, and all new interior arrangements. CVN 78 is a near-
total redesign of the NIMITZ Class she replaces. Further, these major developments, which 
were to be incrementally introduced in the program, were directed in 2002 to be integrated 
into CVN 78 in a single step. Today we are confronting the cost impacts of these decisions 
made more than a decade ago.  
In my August 29, 2011 letter, I provided details regarding these cost impacts. At that time, I 
reported the current estimate for the Navy’s share of the shipbuilder’s construction overrun, 
$690 million, and described that I had directed an end-to-end review to identify the changes 
necessary to improve cost for carrier design, material procurement, planning, build and test. 
The attached white paper provides the findings of that review and the steps we are taking to 
drive affordability into the remaining CVN 78 construction effort. Pending the results of 
these efforts, the Navy has included the ‘fact of life’ portion of the stated overrun in the 
Fiscal Year 2013 President’s Budget request. The review also highlighted the compounding 
effects of applying traditional carrier build planning to a radically new design; the challenges 
inherent to low-rate, sole-source carrier procurement; and the impact of external economic 
factors accrued over 15 years of CVN 78 procurement—all within the framework of cost-
plus contracts. The outlined approach for ensuring CVN 79 and follow ship affordability 
focuses equally upon tackling these issues while applying the many lessons learned in the 
course of CVN 78 procurement.  
 As always, if I may be of further assistance, please let me know. 
Sincerely, [signed] Ray Mabus 
Attachment: As stated  
Copy to: The Honorable Carl Levin, Chairman 
[Attachment] 
Improving Cost Performance on CVN 78  
CVN 78 is nearing 40 percent completion. Cost growth to-date is attributable to increases in 
design, contractor furnished material, government furnished material (notably, the 
Electromagnetic Aircraft Launching System (EMALS), Advanced Arresting Gear (AAG), 
and the Dual Band Radar (DBR)), and production labor performance. To achieve the best 
case outcome, the program must execute with zero additional cost growth in design and 
material procurement, and must improve production performance. The Navy and the 
shipbuilder have implemented a series of actions and initiatives in the management and 
oversight of CVN 78 that cross the full span of contracting, design, material procurement, 
government furnished equipment, production planning, production, management and 
oversight. 
CVN 78 is being procured within a framework of cost-plus contracts. Within this framework, 
however, the recent series of action taken by the Navy to improve contract effectiveness are 
achieving the desired effect of incentivizing improved cost performance and reducing 
government exposure to further cost growth.  
•  CVN 78 design has been converted from a ‘level of effort, fixed fee’ contract to a 
completion contract with a firm target and incentive fee. Shipbuilder cost performance 
has been on-target or better since this contract was changed.  
Congressional Research Service 
23 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
•  CVN 78 construction fee has been retracted, consistent with contract performance. 
However, the shipbuilder is incentivized by the contract shareline to improve upon 
current performance to meet agreed-to cost goals.  
•  Contract design changes are under strict control; authorized only for safety, damage 
control, mission-degrading deficiencies, or similar. Adjudicated changes have been 
contained to less than 1 percent of contract target price.  
•  The Navy converted the EMALS and AAG production contract to a firm, fixed price 
contract, capping cost growth to that system and imposing negative incentives for late 
delivery.  
•  Naval Sea Systems Command is performing a review of carrier specifications with the 
shipbuilder, removing or improving upon overly burdensome or unneeded specifications 
that impose unnecessary cost on the program.  
The single largest impact to cost performance to-date has been contractor and government 
material cost overruns. These issues trace to lead ship complexity and CVN 78 concurrency, 
but they also point to inadequate accountability for carrier material procurement, primarily 
during the ship’s advance procurement period (2002-2008).  
These effects cannot be reversed on CVN 78, but it is essential to improve upon material 
delivery to the shipyard to mitigate the significant impact of material delays on production 
performance. Equally important, the systemic material procurement deficiencies must be 
corrected for CVN 79. To this end, the Navy and shipbuilder have taken the following 
actions.  
•  The Navy has employed outside supply chain management experts to develop optimal 
material procurement strategies. The Navy and the shipbuilder are reviewing remaining 
material requirements to employ these best practices (structuring procurements to 
achieve quantity discounts, dual-sourcing to improve schedule performance and 
leverage competitive opportunities, etc.).  
•  The shipbuilder has assigned engineering and material sourcing personnel to each of 
their key vendors to expedite component qualifications and delivery to the shipyard.  
•  The shipbuilder is inventorying all excess material procured on CVN 78 for transfer to 
CVN 79 (cost reduction to CVN 78), as applicable.  
•  The Program Executive Officer (Carriers) is conducting quarterly flag-level government 
furnished equipment summits to drive cost reduction opportunities and ensure on-time 
delivery of required equipment and design information to the shipbuilder. 
The most important finding regarding CVN 78 remaining cost is that the CVN 78 build plan, 
consistent with the NIMITZ class, focuses foremost on completion of structural and critical 
path work to support launching the ship on-schedule. This emphasis on structure comes at 
the expense of completing ship systems, outfitting, and furnishing early in the build process 
and results in costly, labor-intensive system completion activity during later; more costly 
stages of production. Achieving the program’s cost improvement targets will require that 
CVN 78 increase its level of completion at launch, from current estimate of 60 percent to no 
less than 65 percent. To achieve this goal and drive greater focus on system completion:  
Congressional Research Service 
24 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
•  the Navy fostered a collaborative build process review by the shipbuilder with other Tier 
1 private shipyards in order to benchmark its performance arid identify fundamental 
changes that would yield marked improvement;  
•  the shipbuilder has established specific launch metrics by system (foundations, 
machinery, piping, power panels, vent duct, lighting, etc.) and increased staffing for 
waterfront engineering and material expediters to support meeting these metrics;  
•  the shipbuilder has linked all of these processes within a detailed integrated master 
schedule, providing greater visibility to current performance and greater ability to 
control future cost and schedule performance across the shipbuilding disciplines; 
•  the Navy and shipbuilder are conducting Unit Readiness Reviews of CVN 78 erection 
units to ensure that the outfitted condition of each hull unit being lifted into the dry-dock 
contains the proper level of outfitting.  
These initiatives, which summarize a more detailed list of actions being implemented and 
tracked as result of the end-to-end review, are accompanied by important management 
changes.  
•  The shipbuilder has assigned a new Vice President in charge of CVN 78, a new Vice 
President in charge of material management and purchasing, and a number of new 
general shop foreman to strengthen CVN 78 performance.  
•  The Navy has assigned a second tour Flag Officer with considerable carrier operations, 
construction, and program management experience as the new Program-Executive 
Officer (PEO).  
•  The PEO and shipyard president conduct bi-weekly launch readiness reviews focusing 
on cost performance, critical path issues and accomplishment of the target for launch 
completion.  
•  The Assistant Secretary of the Navy (Research, Development, and Acquisition) 
conducts a monthly review of program progress and performance with the PEO and 
shipbuilder, bringing to bear the full weight of the Department, as needed, to ensure that 
all that can be done to improve on cost performance is being done.  
Early production performance improvements can be traced directly to these actions, 
however, significant further improvement is required. To this end, the Navy is conducting a 
line-by-line review of all ‘cost to-go’ on CVN 78 to identify further opportunity to reduce 
cost and to mitigate risk.  
Improving Cost Performance on CVN 79  
CVN 79 Advance Procurement commenced in 2007 with early construction activities 
following in 2011. Authorization for CVN 79 procurement is requested in Fiscal Year 2013 
President’s Budget request with the first year of incremental funding. Two years have been 
added to the CVN 79 production schedule in this budget request, afforded by the fact that 
CVN 79 will replace CVN 68 when she inactivates. To improve affordability for CVN 79, 
the Navy plans to leverage this added time by introducing a fundamental change to the 
carrier procurement approach and a corresponding shift to the carrier build plan, while 
incorporating CVN 78 lessons learned.  
Congressional Research Service 
25 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The two principal ‘documents’ which the Navy and shipbuilder must ensure are correct and 
complete at the outset of CVN 79 procurement are the design and the build plan.  
Design is governed by rules in place that no changes will be considered for the follow ship 
except changes necessary to correct design deficiencies on the lead ship, fact of life changes 
to correct obsolescence issues, or changes that will result in reduced cost for the follow ship. 
Exceptions to these rules must be approved by the JROC, or designee. Accordingly, the 
Navy is requesting procurement authority for CVN 79 with the Design Product Model 
complete and construction drawings approximately 95 percent complete (compared to 
approximately 30 percent complete at time of lead ship authorization).  
As well, first article testing and certification will be complete for virtually all major new 
equipments introduced in the FORD Class. At this point in time, the shipbuilder has 
developed a complete bill of material for CVN 79. The Navy is working with the shipbuilder 
to ensure that the contractor’s material estimates are in-line with Navy ‘should cost’ 
estimates; eliminating non-recurring costs embedded in lead ship material, validating 
quantities, validating escalation indices, incorporating lead ship lessons learned. The Navy 
has increased its oversight of contractor furnished material procurement, ensuring that 
material procurement is competed (where competition is available); that it is fixed priced; 
that commodities are bundled to leverage economic order quantity opportunities; and that the 
vendor base capacity and schedule for receipt supports the optimal build plan being 
developed for production.  
In total, the high level of design maturity and material certification provides a stable 
technical baseline for material procurement cost and schedule performance, which are 
critical to developing and executing an improved, reliable build plan.  
In order to significantly improve production labor performance, based on timely receipt of 
design and material, the Navy and shipbuilder are reviewing and implementing changes to 
the CVN 79 build plan and affected facilities. The guiding principles are:  
•  maximize planned work in the shops and early stages of construction;  
•  revise sequence of structural unit construction to maximize learning curve performance 
through ‘families of units’ and work cells;  
•  incorporate design changes to improve FORD Class producibility;  
•  increase the size of erection units to eliminate disruptive unit breaks and improve unit 
alignment and fairness;  
•  increase outfitting levels for assembled units prior to erection in the dry-dock;  
•  increase overall ship completion levels at each key event.  
The shipbuilder is working on detailed plans for facility improvements that will improve 
productivity, and the Navy will consider incentives for capital improvements that would 
provide targeted return on investment, such as:  
•  increasing the amount of temporary and permanent covered work areas;  
•  adding ramps and service towers for improved access to work sites and the dry-dock;  
•  increasing lift capacity to enable construction of larger, more fully outfitted super-lifts:  
Congressional Research Service 
26 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
An incremental improvement to carrier construction cost will fall short of the improvement 
necessary to ensure affordability for CVN 79 and follow ships. Accordingly, the shipbuilder 
has established aggressive targets for CVN 79 to drive the game-changing improvements 
needed for carrier construction. These targets include:  
•  75 percent Complete at Launch (15 percent> [i.e., 15 percent greater than] FORD);  
•  85-90 percent of cable pulled prior to Launch (25-30 percent> FORD);  
•  30 percent increase in front-end shop work (piping details, foundations, etc);  
•  All structural unit hot work complete prior to blast and paint;  
•  25 percent increase to work package throughput;  
•  100 percent of material available for all work packages in accordance with the 
integrated master schedule;  
•  zero delinquent engineering and planning products;  
•  resolution of engineering problems in < 8 [i.e., less than 8] hours.  
In parallel with efforts to improve shipbuilder costs, the PEO is establishing equally 
aggressive targets to reduce the cost of government furnished equipment for CVN 79; 
working equipment item by equipment item with an objective to reduce overall GFE costs by 
~$500 million. Likewise, the Naval Sea Systems Command is committed to continuing its 
ongoing effort to identify specification changes that could significantly reduce cost without 
compromising safety and technical rigor. 
The output of these efforts comprises the optimal build plan for CVN 79 and follow, and will 
be incorporated in the detail design and construction baseline for CVN 79. CVN 79 will be 
procured using a fixed price incentive contract.27 
CVN-78 Program Procurement Cost Caps 
Another issue for Congress is where the estimated procurement costs of CVNs 78, 79, and 80 
now stand in relation to the legislated procurement cost caps for the ships (see “Program 
Procurement Cost Cap” in “Background”), and whether the cost caps should be amended. The 
Navy in 2012 stated that in 2013 it would request an increase in the cost cap for CVN-78, but not 
for CVN-79.28 In its prepared statement for a May 8, 2013, hearing on Navy shipbuilding 
                                                                  
27 Letter and attachment from Secretary of the Navy Ray Mabus to Senator John McCain, undated but posted at 
InsideDefnse.com (subscription required) on March 27, 2012. InsideDefense.com’s description of the letter states that it 
is dated March 26, 2012. 
28 A Navy information paper provided to CRS and CBO on March 19, 2012, states that 
Beginning in fiscal year 2014, the estimated cost to complete GERALD R. FORD (CVN 78) will 
exceed the cap for causes requiring legislative relief. Accordingly, the Navy intends to submit a 
legislative proposal for a CVN 78 cost cap increase beginning in Fiscal Year 2014. For follow ships 
of the CVN78 Class, the cost cap is still under evaluation. 
(Undated Navy information paper on CVN-78 program provided to CRS and CBO on March 19, 
2012.) 
(continued...) 
Congressional Research Service 
27 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
programs before the Seapower subcommittee of the Senate Armed Services Committee, the Navy 
stated that 
the Fiscal Year 2014 President’s Budget includes funding for the cost growth [on CVN-78] 
identified in 2011 and requests that the cost cap [for the ship] be correspondingly increased 
to $12.887 billion.... The associated cost cap for CVN 79 is also being updated with this 
budget request [i.e., the cost cap figure for CVN-79 is being adjusted upward under clauses 
in the cap that permit such adjustments for certain factors] to account for economic inflation 
and non-recurring engineering for incorporation of lead ship lessons learned and design 
changes to improve affordability.29 
Potential Two-Ship Block Buy on CVN-79 and CVN-80 
Another issue for Congress concerns the potential for procuring CVN-79 and CVN-80 together in 
a two-ship block buy. The Navy currently plans to procure CVN-79 and CVN-80 separately, as 
one-ship procurements. Procuring the two ships together in a block buy could reduce their 
combined procurement cost. 
Procuring two aircraft carriers together in a two-ship block buy has been done on two previous 
occasions. The Navy procured two Nimitz (CVN-68) class aircraft carriers (CVN-72 and CVN-
73) together in a block buy in FY1983, and procured another two Nimitz-class aircraft carriers 
(CVN-74 and CVN-75) together in a block buy in FY1988. The Navy proposed these block buys 
in the FY1983 and FY1988 budget submissions.30 
When the FY1983 block buy was proposed, the Navy estimated that the block buy would reduce 
the combined cost CVN-72 and CVN-73 by 5.6% in real terms.31 When the FY1988 block buy 
was proposed, the Navy estimated that the block buy would reduce the combined cost of CVN-74 
and CVN-75 by a considerably larger percentage. GAO stated that the savings would be 
considerably less than the Navy estimated, but agreed that a two-ship acquisition strategy is less 
                                                                  
(...continued) 
Secretary of the Navy Ray Mabus, when asked by Senator John McCain at a March 15, 2012, hearing before the Senate 
Armed Services Committee whether the Navy will ask for legislative relief on the CVN-78 cost cap, replied: “Senator, 
not this year, but I'm certain we will be asking next year.” In response to a follow-up question from Senator McCain on 
aircraft carrier program costs, Secretary Mabus stated in part: 
The one thing that we are absolutely committed to and the one thing that we will not go forward 
with [on] CVN-79 is that we will take the lessons learned here. We will have a firm price and we 
will not come back to the Senate to ask for—or Congress to ask for raising the cost cap on the 
follow-on ship, the John F. Kennedy CVN-79. 
(Transcript of hearing.) 
29 Statement of The Honorable Sean J. Stackley, Assistant Secretary of the Navy (Research, Development and 
Acquisition) and Vice Admiral Allen G. Myers, Deputy Chief of Naval Operations for Integration of Capabilities and 
Resources and Vice Admiral Kevin M. McCoy, Commander, Naval Sea Systems Command, Before the Subcommittee 
on Seapower of the Senate Armed Services Committee on Department of the Navy Shipbuilding Programs, May 8, 
2013, p. 8. 
30 It can also be noted that the Air Force is procuring two Advanced EHF (AEHF) satellites under a two-satellite block 
buy that the Air Force proposed and Congress approved in FY2012. 
31 See General Accounting Office, Request to Fully Fund Two Nuclear Aircraft Carriers in Fiscal Year 1983, 
MASAD-82-87 (B-206847), March 26, 1982, 10 pp. The figure of 5.6% was derived by dividing $450 million in non-
inflation cost avoidance shown on page 5 by the combined estimated cost of the two ships (absent a block buy) of 
$8,024 million shown on page 4. 
Congressional Research Service 
28 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
expensive than a single-ship acquisition strategy, and that some savings would occur in a two-
ship strategy for CVN-74 and CVN-75.32 
The FY1983 and FY1988 block buys each involved procuring two aircraft carriers in a single 
year. Procuring two carriers in the same year, however, is not mandatory for a two-ship aircraft 
carrier block buy. The Navy, for example, proposed the block buy for CVN-74 and CVN-75 in 
the FY1988 budget submission as something that would involve procuring CVN-74 in FY1990 
and CVN-75 in FY1993. (Congress, in acting on the FY1988 budget, decided to not only approve 
the two-ship block buy, but also accelerate the procurement of both CVN-74 and CVN-75 to 
FY1988.)33 A block buy on CVN-79 and CVN-80 could leave intact the FY2013 procurement 
date for CVN-79 and the FY2018 procurement date for CVN-80. This would permit the funding 
for the two ships to be spread out over the same fiscal years as currently planned, although the 
amounts of funding in individual years would likely change. 
It is too late to implement a complete block buy on CVN-79 and CVN-80, because some of CVN-
79, particularly its propulsion plant, has already been purchased. Consequently, the option would 
be to implement a partial block buy that would include the remaining part of CVN-79 and all of 
CVN-80. 
To illustrate the notional scale of the savings that might result from using a block buy strategy on 
CVN-79 and CVN-80, it can be noted that if such a block buy were to achieve one-third as much 
percentage cost reduction as the FY1983 block buy—that is, if it were to reduce the combined 
procurement cost of CVN 79 and 80 by about 1.9%—that would equate to a savings of roughly 
$470 million on the currently estimated combined procurement cost of CVN-79 and CVN-80. 
More refined estimates might be higher or lower than this notional figure of $470 million. 
                                                                  
32 See General Accounting Office, Procurement Strategy For Acquiring Two Nuclear Aircraft Carriers, Statement of 
Frank Conahan, Assistant Comptroller General, National Security and International Affairs Division, Before the 
Conventional Forces and Alliance Defense Subcommittee and Projection Forces and Regional Defense Subcommittee 
of the Senate Armed Services Committee, April 7, 1987, T-NSIAD-87-28, 5 pp. The testimony states on page 2 that “A 
single ship acquisition strategy is more expensive because materials are bought separately for each ship rather than 
being combined into economic order quantity buys under a multi-ship procurement.” The report discounted the Navy’s 
estimated savings of $1,100 million based on this effect on the grounds that if CVN-74 and CVN-75 were not procured 
in the proposed two-ship block buy, with CVN-74 procured in FY1990 and CVN-75 procured FY1993, it was likely 
that CVN-74 and CVN-75 would subsequently be procured in a two-ship block buy, with CVN-74 procured in FY1994 
and CVN-75 procured in FY1996. For the discussion here, however, the comparison is between the Navy’s current plan 
to procure CVN-79 and CVN-80 separately and the potential alternative of procuring them together in a block buy. 
The GAO report commented on an additional $700 million in savings that the Navy estimated would be derived from 
improving production continuity between CVN-73, CVN-74, and CVN-75 by stating on page 3 that “It is logical to 
assume that savings are possible through production continuity but the precise magnitude of such savings is difficult to 
calculate because of the many variables that affect the outcome.” It is not clear how significant savings from production 
continuity might be in a two-ship block buy for CVN-79 and CVN-80 if the procurement dates for the two ships 
(FY2013 and FY2018, respectively) are not changed. 
The GAO report noted that the Navy estimated $500 million in additional savings from avoided configuration changes 
on CVN-74 and CVN-75 if the ships were procured in FY1990 and FY1993 rather than FY1994 and FY1996. It is not 
clear how significant the savings from avoided configuration changes might be for a two-ship block buy for CVN-79 
and CVN-80. 
See also CRS Issue Brief IB87043, Aircraft Carriers (Weapons Facts), 13 pp., updated February 10, 1988, and 
archived March 24, 1988, by Ronald O’Rourke. The report includes a discussion of the above GAO report. The report 
is out of print and available directly from the author. 
33 See CRS Issue Brief IB87043, Aircraft Carriers (Weapons Facts), 13 pp., updated February 10, 1988, and archived 
March 24, 1988, by Ronald O’Rourke. The report is out of print and available directly from the author. 
Congressional Research Service 
29 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
At a March 19, 2012, briefing for CRS and CBO on the CVN-78 program, CRS asked the Navy 
whether it was considering the possibility of a block buy on CVN-79 and CVN-80. The Navy 
stated that it had looked into a narrower option of doing joint purchases of some materials for the 
two ships. 
Implementing a block buy on CVN-79 and CVN-80 would require committing to the 
procurement of CVN-80. Whether Congress would want to commit to the procurement of CVN-
80, particularly in light of current uncertainty over future levels of defense spending, is a factor 
that Congress may consider in assessing the option of doing a block buy. If budgetary 
circumstances were to lead to a decision to end procurement of Ford-class carriers after CVN-79, 
then much or all of the funding spent procuring materials for CVN-80 could go to waste. 
At a March 29, 2012, hearing on Navy shipbuilding programs before the Seapower and Projection 
Forces subcommittee of the House Armed Services Committee, Sean Stackley, the Assistant 
Secretary of the Navy for Research, Development, and Acquisition (i.e., the Navy’s acquisition 
executive), stated the following when asked by Representative Robert Wittman about the 
possibility of a two-ship block buy on CVN-79 and CVN-80: 
Yes, sir. Let me focus on affordability of the CVN-78 class. We are right now about 40 
percent complete construction of the CVN-78 and we’re running into some very difficult 
cost growth issues across the full span—design, material procurement, and production—
material procurement on both contractor and government side. 
So our first focus right now is to stabilize the lead ship. Let’s get cost under control so we 
can complete this ship as close to schedule at the lowest cost possible. 
But in parallel, the Navy is working very closely with the shipbuilder to take a step back and 
say, one, what are all the lessons we just learned on CVN-78? Two, CVN-78 is a very 
different ship from the Nimitz [CVN-68]; we cannot expect to build the [CVN-]78 the way 
we build the [CVN-]68 and—and get to an affordable ship construction plan. So we’re 
pressing on the way the carrier is built—the build plan for the carrier—to arrive at a more 
affordable CVN-79. 
Now, in the process of doing that we’ll take a hard look at what opportunity there is across 
[CVN-]79 and [CVN-]80, recognizing that we’re going to be limited, again, by [budget] top 
line. But there are going to be some opportunities that jump out at us. We don’t want to have 
to replan each carrier. We have a vendor base that is stretched out with the carrier build cycle 
that for some components that are carrier-unique, that vendor base is—is just struggling to 
hold on between the five-year gaps. 
So we have to take a hard look at where does it make sense after we’ve gotten to what I’m 
calling an optimal build plan for CVN-79 and then be able to come back and—and say, OK, 
here—on CVN-79 here are some opportunities that if we could, in fact, reach out to CVN-80 
we can either avoid a gap in a production line or avoid unnecessary cost growth on that 
follow ship.34 
Later in the hearing, the following exchange occurred: 
REPRESENTATIVE RICK LARSEN:  
                                                                  
34 Source: transcript of hearing. 
Congressional Research Service 
30 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Finally, we had some discussion about this question with regard to CVNs and trying to find a 
way to squeeze some costs out, and one of the ideas was to do some—do block buy of 
certain components of—of—of CVN components. And have you considered that, and what’s 
your thought on that on block buy on components from [CVN-]79 to [CVN-]80, or whatever, 
[CVN-]79, [CVN-]79 to [CVN-]80, and so on? 
ASSISTANT SECRETARY OF THE NAVY SEAN STACKLEY:  
Yes, sir. At this point in time the Navy and the shipbuilder are sitting side by side putting 
together a build plan for CVN-79. We’re 40 percent complete construction of the [CVN-]78; 
we’ve got a lot that we’ve got to, I’ll say, do different on the [CVN-]79 and follow from the 
lead ship. It’s a very different ship class [compared to the Nimitz class]. 
So we’re taking a hard look at the build plan [for CVN-78]. We need to get that locked 
down. And associated with that is the complete bill of materials for the Ford class. 
At that point in time we'll be able to take a look at... 
LARSEN:  
On this, call it bill of materials, what does it make sense—what makes sense in terms of 
looking long term, beyond the immediate ship? 
STACKLEY:  
Right. 
LARSEN:  
Are there areas of the industrial base that are stressed to the point that it does make sense to 
look at coupling the CVN-79 and CVN-80 buy? 
STACKLEY:  
We’re not at that point yet. I described earlier that I think after we get through this build plan 
review then we'll be able to come back in ‘14 [FY2014] and identify potential critical items 
that warrant a block buy approach.35 
Later in the hearing, Matthew Mulherin, president of NNS and corporate vice president of HII, 
stated the following when asked by Representative Robert Wittman about the possibility of a two-
ship block buy on CVN-79 and CVN-80: 
Yes, sir. You know, historically you go back, you were exactly right, if you look at the 
contracts that bought the CVN- 72 and [CVN-]73 there was huge savings that flowed to the 
second ship, both in the ability to go buy materials, a block buy and get—get discounts there, 
but also that you did the engineering up front the first time for both hulls so the second ship 
you really just had the answer, problem, paper [sic] and some of those kind of things the—
the kind of the normal course of business to support the waterfront. 
So I wouldn’t see any different. I think if we were able to do it both for material, for—for the 
engineering to be able to go pump out drawings that had two-ship applicability—plus, I think 
                                                                  
35 Source: Transcript of hearing. 
Congressional Research Service 
31 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
it brings the—the—the CVN—if we were to do a two-ship buy for [CVN-]79 and [CVN-]80 
it would ensure CVN-80 was a copy of CVN-79, no change into the contract or very 
minimal, you’re not having a—on the material side you get economic order savings, you 
don’t have to deal with obsolescence. 
So absolutely. I think there’s huge opportunity to go do that. You know, you talk to the—the 
vendor base. They would love to see it. It gives them the ability to go look at—at what 
investments they need, what work is out in front of them, and go invest in—in training and 
tools to—to be able to go support that.36 
At the March 19, 2012, briefing for CRS and CBO on the CVN-78 program, CRS asked the Navy 
to examine the option of a block buy on CVN-79 and CVN-80, and inform CRS and CBO of the 
Navy’s estimate of how much it might reduce the combined procurement cost of CVN-79 and 
CVN-80. The Navy’s response, dated April 22, 2012, was sent to CRS on May 10, 2012 (i.e., just 
after the House Armed Services Committee completed its markup of H.R. 4310, the FY2013 
National Defense Authorization Act). The response stated: 
There are several options for procuring aircraft carriers that differ from the current practice; 
two ship buys and block buys. Navy experience with aircraft carrier two ship buys includes 
procurement of the CVN 72 and CVN 73 (awarded in FY83), and the CVN 74 and CVN 75 
(awarded in FY88). The actual cost returns for these procurements support significant 
savings compared to other NIMITZ Class single ship buys. This conclusion is based on a 
comparison of the NIMITZ Class two ship buys (CVN72, 73, 74 & 75) with single ship buys 
(CVN71 and CVN76). The total ship man-hour comparison shows a 9% reduction. The total 
ship material comparison in constant dollars shows an 8% reduction. The NIMITZ- Class 
two ship buys took advantage of a single year of full funding for the combined procurement, 
and less than three years between the deliveries of each ship. Having both ships fully funded 
in one year enabled the Navy and shipbuilder to take advantage of two ship-set Economic 
Order Quantity (EOQ) market savings for material items, and also allowed the shipbuilder to 
optimize production trades management. The short time between deliveries also resulted in 
design stability, minimized potential obsolescence, and greater opportunities for learning. 
Given hard budget constraints in FY13 and FY14, CVN 79 and CVN 80 cannot benefit from 
a multiyear construct, similar to those requested in PB13 for VIRGINIA Class Submarine 
and ARLIEGH BURKE Class Destroyers. By the end of FY14, 75% of CVN 79 material 
will be under contract with suppliers, leaving limited opportunities to implement material 
savings with multiyear incremental funding. 75% of CVN 80 material would also be 
incapable of achieving savings, as the material purchases would be placed after CVN 79.  
CVN 80/81 would present the first opportunity to potentially consider this strategy.37 
The Navy’s response states, “Having both ships fully funded in one year enabled the Navy and 
shipbuilder to take advantage of two ship-set Economic Order Quantity (EOQ) market savings for 
material items.... ” It can be noted that ships funded in separate years can also take advantage of 
EOQ savings, provided that the authorizing legislation permits the use of EOQ, and that the 
FY1988 block buy of CVN-74 and CVN-75 was originally proposed by the Navy as a block buy 
in which CVN-74 would be procured in FY1990 and CVN-75 in FY1993. 
                                                                  
36 Source: Transcript of hearing. 
37 Navy information paper dated April 25, 2012, sent to CRS on May 10, 2012. 
Congressional Research Service 
32 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
The Navy’s response states, “Given hard budget constraints in FY[20]13 and FY[20]14, CVN 79 
and CVN 80 cannot benefit from a multiyear construct, similar to those requested in PB[20]1338 
for VIRGINIA Class Submarine and ARLIEGH BURKE Class Destroyers.” It can be noted that a 
block buy on CVN-79 and CVN-80 would not necessarily be a multiyear procurement (MYP) 
contract, like those requested for the Virginia-class submarine program and the Arleigh Burke 
(DDG-51) destroyer programs. It can also be noted that Congress may decide to work within 
budget constraints for FY2013 and FY2014 that might differ from those on which is DOD basing 
its planning. 
The Navy’s response states, “By the end of FY14, 75% of CVN 79 material will be under 
contract with suppliers, leaving limited opportunities to implement material savings with 
multiyear incremental funding. 75% of CVN 80 material would also be incapable of achieving 
savings, as the material purchases would be placed after CVN 79.” CRS on May 10, 2012, asked 
the Navy what percent of the material for CVN-79 would be under contract by the end of 
FY2012. The Navy’s response, dated May 22, 2012, was sent to CRS on May 25, 2012 (i.e., the 
same day that the House Appropriations Committee reported H.R. 5856, the FY2013 DOD 
Appropriations Act). The response stated, “Approximately 47% of CVN 79 direct material will be 
under contract by the end of FY[20]12.”39 
The Navy’s response states that “CVN 80/81 would present the first opportunity to potentially 
consider this [block buy] strategy.” This statement appears to refer to a strategy of a complete 
block buy involving 100% of the material for both carriers. Based on the Navy’s response dated 
May 22, 2012, a partial block buy on CVN-79 and CVN-80 involving as much as 53% of the 
material on CVN-79 might be possible, if the block buy were authorized and implemented as part 
of the FY2013 defense budget. 
Issues Raised in December 2012 DOT&E Report 
Another issue for Congress concerns CVN-78 program issues that were raised in a December 
2012 report from DOD’s Director, Operational Test and Evaluation (DOT&E)—DOT&E’s annual 
report for FY2012. The report stated, in its section on the CVN-78 program, that 
Assessment 
Test Planning 
• The current state of the Virtual Carrier model does not fully provide for an accurate 
accounting of SGR [sortie generation rate] due to a lack of fidelity regarding manning and 
equipment/aircraft availability. Spiral development of the Virtual Carrier model continues in 
order to ensure that the required fidelity will be available to support the SGR assessment 
during IOT&E [initial operational test and evaluation]. 
• The current TEMP [test and evaluation master plan] does not adequately address whole 
platform-level developmental testing. The Program Office has begun to address the problem 
and has refined the Post Delivery Test and Trials schedule. The details are unclear on the 
extent of any additional integrated platform-level CVN-78 developmental tests. Lack of 
                                                                  
38 This is a reference to the President’s budget for FY2013—that is, the Administration’s requested budget for FY2013. 
39 Navy information paper dated May 22, 2012, sent to CRS on May 25, 2012. 
Congressional Research Service 
33 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
platform-level developmental testing significantly raises the likelihood of the discovery of 
platform-level problems during IOT&E. 
• The Navy plans to deliver CVN-78 in September 2015.40 Current progress supports this 
plan; however, the EMALS [electromagnetic aircraft launch system] , AAG [advanced 
arresting gear], DBR [dual band radar], and Integrated Warfare Systems remain pacing items 
for successful delivery of the ship. 
EMALS [electromagnetic aircraft launch system] 
• DOT&E holds moderate concern regarding the performance risk generated by the inability 
to test the full four-catapult electrical distribution system prior to initial trials aboard ship. 
This concern is partially mitigated by the current phase of test using a simulated shared 
electrical storage and shared power conversion at the EMALS system functional design test 
site in Joint Base McGuire-Dix-Lakehurst, New Jersey. 
AAG [advanced arresting gear] 
• Significant redesign of multiple components has slowed development of AAG 
development. The program will begin performance testing in FY13. 
JSF [Joint Strike Fighter] 
• JBD testing identified no deficiencies for catapult launch operations of JSF at military rated 
thrust. The tests did, however, determine that additional JBD [jet blast deflector] side panel 
cooling (SPC) and other adjustments are required for operations at combat rated thrust, i.e., 
with afterburner. The existing JBD panels will need to be replaced with new panels with SPC 
to be fully JSF-compatible. JBD panels with SPC are form, fit, and function replacements 
and will be installed after CVN-78 delivers. 
—JSF data flow aboard ship via the Autonomic Logistics Information System (ALIS) is 
critical to proper F-35 maintenance. Currently, the ALIS system has provided all required 
parametric information to interface properly with CANES [Consolidated Afloat Networks 
and Enterprise Services], but CANES is not fully developed yet, as the contract was awarded 
in August 2012. ALIS is expected to undergo Application Integration Process testing in 
FY13 to ensure proper interface with CANES. DOT&E will be able to better assess the 
impact on JSF operations aboard CVN-78 after the test. Currently, data are planned to be 
exchanged manually until ALIS and CANES properly interface. 
—In 2007, the Program Office identified discrepancies with the integration of the JSF’s 
F135 engine onto aircraft carriers. The weight of the F135 power module, approximately 
10,000 pounds, exceeds the limit of current underway replenishment (UNREP) systems. 
Although CVN-78 will include a heavy UNREP system that will allow transfer of 12,000 
pounds, supply ships must include the new system for power module transfer to occur. The 
Navy’s plan to install heavy UNREP systems on resupply ships has slipped eight years. 
• Navy Fleet Force’s JSF “day-in-the-life” analysis identified a significant number of 
aircraft-ship interface deficiencies that must be accomplished by the Navy in post-delivery 
ship modification. They include the following:  
                                                                  
40 As noted earlier, the Navy announced in May 2013 that the ship’s delivery date has been postponed to February 
2016. 
Congressional Research Service 
34 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
—JSF battle damage assessment and non-traditional Intelligence, Surveillance, and 
Reconnaissance information captured on the Portable Memory Device or cockpit video 
recorder cannot be shared real-time with the Distributed Common Ground System-Navy 
(DCGS-N). This prevents assessment by shipboard intelligence analysts for inclusion in 
mission reports. 
—Ships are unable to receive and display Link 16 imagery; this problem is not unique to 
JSF. The Combatant Commanders have stated a need to display imagery to intelligence 
analysts and operations command and control nodes to enhance engagement decisions. 
—Limited shipboard capabilities exist with expeditionary Link 16. The Navy is considering 
a program of record to distribute imagery to analysts and maritime operations command and 
control nodes (e.g., carriers and amphibious ships). This would be a temporary workaround 
for the DCGS-N post-flight data gap. 
—The JSF Prognostic Health Maintenance (PHM) downlink design for ships is not mature. 
The uncertainty in the technical characteristics of the final design means that there are 
potential challenges to integrating PHM into current shipboard communications suites and 
networks. These challenges include unidentified Information Assurance considerations and 
unidentified waveform hosting and interfacing. 
—The JSF wheel supplier’s recent rim inspection requirement may force a significant 
increase in shipboard tire and wheel storage requirements. The JSF Program Office is 
currently working to determine the effect of this deficiency and the need for inspection by 
the wheel supplier. 
DBR 
• Previous testing of Navy combat systems similar to CVN-78’s revealed numerous 
integration problems that degrade the performance of the combat system. The previous 
results emphasize the necessity of maintaining a DBR / CVN-78 combat system asset at 
Wallops Island. The Navy is considering long-term plans (i.e., beyond FY15) for testing 
DBR at Wallops Island, Virginia, but it is not clear if a Multi-Functional Radar and funding 
will be available. Such plans are critical to delivering a fully capable combat system and 
ensuring lifecycle support after CVN-78 delivery in 2015. 
LFT&E [live fire test and evaluation] 
• While the Navy has made substantial effort in component and surrogate testing, this work 
does not obviate the need to conduct the FSST [full-ship shock trial] to gain the critical 
empirical data that past testing has repeatedly demonstrated are required to rigorously 
evaluate the ship’s ability to withstand shock and survive in combat. Shock Trials conducted 
on both the Nimitz class aircraft carrier and the San Antonio class Amphibious Transport 
Dock demonstrated the need for and substantial value of conducting the FSST. Postponing 
the FSST until CVN-79 would cause a five- to seven-year delay in obtaining the data critical 
to evaluating the survivability of the CVN-78 and would preclude timely modification of 
subsequent ships of this class to assure their survivability. 
• The Navy proposes delaying the shock trial by five to seven years because of the 
approximately four- to six-month delay required to perform the FSST. The delay is not a 
sufficient reason to postpone the shock trial, since the shock trial could reveal valuable 
lessons, including previously unknown vulnerabilities. 
• DOT&E has requested the Navy adequately fund and complete the actions necessary to 
conduct the TSST on the CVN-78. This includes updating the Damage Scenario Based 
Congressional Research Service 
35 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Engineering Analyses (DSBEA) from prior Vulnerability Assessment Reports and enough 
new DSBEAs, including machinery spaces, to conduct an adequately scoped TSST [total 
ship survivability trial]. DOT&E expects this will require five or six TSST drills. While 
progress has been made toward reaching consensus on the scope of the TSST, there is still 
work to be done, mainly to include the machinery spaces, and the budget has not been 
adjusted to adequately support the TSST. 
Recommendations 
• Status of Previous Recommendations. The Navy addressed one of eight previous 
recommendations but the following seven remain valid: 
1. Adequately test and address integration challenges with JSF; specifically logistics (storage 
of spare parts and engines, transport of support equipment and spares to / from the carrier), 
changes required to JBDs, changes (due to heat and or noise) to flight deck procedures, and 
ALIS integration. 
2. Finalize plans that address CVN-78 integrated warfare system engineering and ship’s self-
defense system discrepancies prior to the start of IOT&E. 
3. Continue aggressive EMALS and AAG risk-reduction efforts to maximize opportunity for 
successful system design and test completion in time to meet required in-yard dates for 
shipboard installation of components. 
4. Continue development of a realistic model for determining CVN-78’s SGR, while 
utilizing realistic assumptions regarding equipment availability, manning, and weather 
conditions for use in the IOT&E. 
5. Provide scheduling, funding, and execution plans to DOT&E for the live SGR test event 
during the IOT&E. 
6. Continue to work with the Navy’s Bureau of Personnel to ensure adequate depth and 
breadth of required personnel to ensure that the 100 percent Navy Enlisted Classification fit / 
fill manning requirements of CVN-78 are met. 
7. Conduct system-of-systems developmental testing to preclude discovery of deficiencies 
during IOT&E. 
• FY12 Recommendations. None.41 
Regarding the full ship shock test (FSST) discussed, above, an August 9, 2012, press report 
states: 
The Navy is inappropriately delaying or scaling back $70 million in needed combat testing 
of the USS Gerald R. Ford [CVN-78], an aircraft carrier that may cost $14.2 billion, in the 
name of cutting costs, according to the Pentagon’s top weapons tester. 
A test that would “rigorously evaluate the ship’s ability to withstand shock and survive in 
combat” would be postponed until a second carrier in the new Ford class [CVN-79] is built 
and may not be completed for seven years, Michael Gilmore, the Defense Department’s 
                                                                  
41 Department of Defense, Director, Operational Test & Evaluation, FY2012 Annual Report, released January 2013, pp. 
144-146. 
Congressional Research Service 
36 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
director of operational test and evaluation, told Navy Secretary Ray Mabus in a July 12 
memo obtained by Bloomberg News.... 
 “I recognize the need to expend resources wisely for all purposes, including testing, in the 
existing constrained fiscal environment,” Gilmore said in the memo. “I consider these test 
costs well-justified, particularly when considered in the context of the $27.8 billion cost to 
design and build the first three of these new carriers, clearly one of the most expensive 
combat systems the department has ever acquired.”... 
The dispute centers on the Navy’s decision to change the agreed-upon test plan for the first 
carrier in the class without Gilmore’s approval. The Navy wants to shift “full ship shock 
trial” evaluations to the John F. Kennedy, the second carrier, in the move Gilmore says 
would delay conducting the tests and gathering needed data for five to seven years. 
The tests, estimated to cost about $60 million, are designed to evaluate a ship’s ability to 
perform its mission after absorbing repeated shock waves from underwater explosions using 
live ammunition detonated at a distance. 
Gilmore rescinded approval of the test plan on July 12 and that decision remains in place, he 
said in an e-mail through his spokeswoman Cheryl Irwin. Gilmore also said he has informed 
Defense Secretary Leon Panetta’s staff of his concerns. 
Gilmore said in the e-mail that the delay “is not appropriate” because the tests “provide 
information key to assuring a ship’s survivability in combat.” 
Captain Cate Mueller, a Navy spokeswoman, said in an e-mailed statement that “the Navy 
and test office are committed to providing the most capable and survivable carrier.” The 
service’s differences with Gilmore “are in the technical aspects and phasing of the shock 
trials,” she said. 
Conducting the full shock test “is a high-cost event with schedule impact,” she said. The 
Navy also has been under pressure due to environmental impact concerns “to identify 
alternative means to validate ship shock design,” Mueller said. 
The Ford carrier’s hull form “has been subject to extensive survivability modeling and 
simulation, robust equipment and system component testing,” she said, and the Navy’s 
decision to delay the full shock testing “is fully consistent with past practices for new ship 
classes.” 
Gilmore wrote Mabus that postponing the full shock tests until they can be performed on the 
Kennedy “would preclude timely modification of subsequent ships of this class to ensure 
survivability.” 
Conducting the tests on the first ship as originally planned would cause about a two-month 
delay in fielding the carrier, according to Gilmore. 
“The data to be gained and risk mitigated are, in my view, clearly valuable enough to justify 
this delay,” Gilmore wrote Mabus. 
Gilmore wrote Mabus that he also disagreed with a second Navy decision that would “limit 
the scope” of “total ship survivability trials” on the first carrier. These tests, at an estimated 
cost of $10 million, are designed to demonstrate the ability of the ship and crew to control 
damage resulting from simulated anti-ship weapons and continue fighting. 
Congressional Research Service 
37 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
“I cannot accept elimination of key and essential survivability analyses,” including proposals 
to eliminate analysis of the carrier’s machinery spaces, “simply to satisfy budget reductions,” 
Gilmore said.42 
Legislative Activity for FY2014 
FY2014 Funding Request 
As shown in Table 1, the Navy’s proposed FY2014 budget requests $588.1 million in 
procurement funding to cover cost growth on CVN-78, and $944.9 million in procurement 
funding for CVN-79. 
FY2014 National Defense Authorization Act (H.R. 1960/S. 1197) 
House (Committee Report) 
The House Armed Services Committee, in its report (H.Rept. 113-102 of June 7, 2013) on H.R. 
1960, recommends approving the Navy’s requests for $588.1 million in procurement funding to 
cover cost growth on CVN-78 and $944.9 million in procurement funding for CVN-79 (page 
387).43 
Section 122 of H.R. 1960 as reported states: 
SEC. 122. COST LIMITATION FOR CVN-78 AIRCRAFT CARRIERS. 
(a) In General- Section 122 of the John Warner National Defense Authorization Act for 
Fiscal Year 2007 (P.L. 109-364; 120 Stat. 2104) is amended to read as follows: 
`SEC. 122. ADHERENCE TO NAVY COST ESTIMATES FOR CVN-78 CLASS OF 
AIRCRAFT CARRIERS. 
`(a) Limitation-  
`(1) LEAD SHIP- The total amount obligated from funds appropriated or otherwise made 
available for Shipbuilding and Conversion, Navy, or for any other procurement account, for 
the aircraft carrier designated as CVN-78 may not exceed $12,887,000,000 (as adjusted 
pursuant to subsection (b)). 
`(2) FOLLOW-ON SHIPS- The total amount obligated from funds appropriated or otherwise 
made available for Shipbuilding and Conversion, Navy, or for any other procurement 
account, for the construction of any ship that is constructed in the CVN-78 class of aircraft 
carriers after the lead ship of that class may not exceed $11,411,000,000 (as adjusted 
pursuant to subsection (b)). 
                                                                  
42 Tony Capaccio, “Navy Delays Combat Tests Needed For Carrier, Weapons Tester Says,” Bloomberg Government 
(bgov.com), August 9, 2012. 
43 The request for $588.1 million in procurement funding to cover cost growth on CVN-78 is included in the $625.8 
million requested in line item 020, Completion of PY [prior-year] Shipbuilding Programs. 
Congressional Research Service 
38 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
`(b) Adjustment of Limitation Amount- The Secretary of the Navy may adjust the amount set 
forth in subsection (a) for any ship constructed in the CVN-78 class of aircraft carriers by the 
following: 
`(1) The amounts of increases or decreases in costs attributable to economic inflation after 
September 30, 2013. 
`(2) The amounts of increases or decreases in costs attributable to compliance with changes 
in Federal, State, or local laws. 
`(3) The amounts of outfitting costs and post-delivery costs incurred for that ship. 
`(4) The amounts of increases or decreases in costs of that ship that are attributable to 
insertion of new technology into that ship, as compared to the technology baseline as it was 
defined in the approved acquisition program baseline estimate of December 2005. 
`(5) The amounts of increases or decreases to nonrecurring design and engineering cost 
attributable to achieving compliance with the cost limitation. 
`(6) The amounts of increases or decreases to cost required to correct deficiencies that may 
affect the safety of the ship and personnel or otherwise preclude the ship from safe 
operations and crew certification. 
`(7) With respect to the aircraft carrier designated as CVN-78, the amounts of increases or 
decreases in costs of that ship that are attributable to the shipboard test program. 
`(c) Limitation on Technology Insertion Cost Adjustment- The Secretary of the Navy may 
use the authority under paragraph (4) of subsection (b) to adjust the amount set forth in 
subsection (a) for a ship referred to in that subsection with respect to insertion of new 
technology into that ship only if-- 
`(1) the Secretary determines, and certifies to the congressional defense committees, that 
insertion of the new technology would lower the life-cycle cost of the ship; or 
`(2) the Secretary determines, and certifies to the congressional defense committees, that 
insertion of the new technology is required to meet an emerging threat and the Secretary of 
Defense certifies to those committees that such threat poses grave harm to national security. 
`(d) Notice-  
`(1) REQUIREMENT- The Secretary of the Navy shall submit to the congressional defense 
committees each year, at the same time that the budget is submitted under section 1105(a) of 
title 31, United States Code, for the next fiscal year, written notice of-- 
`(A) any change in the amount set forth in subsection (a) during the preceding fiscal year that 
the Secretary has determined to be associated with a cost referred to in subsection (b); and 
`(B) the most accurate estimate possible of the Secretary with respect to the total cost 
compared to the amount set forth in subsection (a), as adjusted by subsection (b), and the 
steps the Secretary is taking to reduce the costs below such amount. 
`(2) EFFECTIVE DATE- The requirement in paragraph (1) shall become effective with the 
budget request for the year of procurement of the first ship referred to in subsection (a).'. 
Congressional Research Service 
39 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(b) Conforming Amendment- The table of contents at the beginning of such Act is amended 
by striking the item relating to section 122 and inserting the following: 
`Sec. 122. Adherence to Navy cost estimates for CVN-78 class of aircraft carriers.'. 
Regarding Section 122, H.Rept. 113-102 states: 
Section 122—Cost Limitation for CVN–78 Aircraft Carriers 
This section would amend the statutory cost cap for the aircraft carrier designated as CVN–
78 that was imposed by subsection (a)(1) of section 122 of the John Warner National 
Defense Authorization Act for Fiscal Year 2007 (Public Law 109–364). The cost cap for 
CVN–78 is currently $11.755 billion, having been adjusted by the Secretary of the Navy in 
2010 using the authority granted by subsection (b) of section 122 of Public Law 109–364. 
This section would raise the cost cap to the Program Manager’s most likely Estimate at 
Completion, as reported in the 2011 Selected Acquisition Report, to $12.9 billion. This 
section would also update the cost cap associated with CVN–79 and later Ford-class aircraft 
carriers. 
The committee notes the receipt of a report to Congress required by section 124 of the 
National Defense Authorization Act for Fiscal Year 2013 (Public Law 112–239) that 
provides cost-saving details that the Navy intends to incorporate into the acquisition strategy 
to provide better cost stability in CVN–78 and eventual incorporation into CVN–79 
procurement process. 
The committee remains concerned about the continued escalation in costs associated with 
Gerald R. Ford-class aircraft carrier and the negative consequences associated with this 
continued escalation on the entirety of the ship construction accounts. This escalation, when 
taken in the context of the 30-year shipbuilding plan that includes significant costs associated 
with the Ohio-class ballistic missile submarine replacement, is unsustainable. (Page 40) 
Section 1233 of H.R. 1960 as reported states: 
SEC. 1233. SENSE OF CONGRESS ON THE DEFENSE OF THE ARABIAN GULF. 
(a) Findings- Congress finds the following: 
(1) In response to U.S. Central Command requirements, the United States Navy has 
maintained, on average, more than one aircraft carrier in the Arabian Gulf for more than five 
years. 
(2) In February 2013, the senior leadership of the Department of Defense elected to reduce 
the number of aircraft carriers deployed to the Arabian Gulf in light of budget constraints and 
limitation of the overall carrier force structure to support the two aircraft carrier requirement. 
(3) In reference to the decision to indefinitely delay the deployment of the USS Harry 
Truman, CVN 75, and the USS Gettysburg, its cruiser escort, Chairman of the Joint Chiefs, 
General Martin Dempsey stated, `We're trying to stretch our readiness out by keeping this 
particular carrier in homeport in our global response force, so if something happens 
elsewhere in the world, we can respond to it. Had we deployed it and `consumed' that 
readiness, we could have created a situation where downstream we wouldn't have a carrier 
present in certain parts of the world at all.'. 
Congressional Research Service 
40 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
(4) Highlighting the risks of having only one aircraft carrier in the region and relying on 
land-based aircraft, General Dempsey stated, `When you have carrier-based aircraft, you 
have complete autonomy and control over when you use them. When you use land-based 
aircraft, you often have to have host-nation permission to use them.'. 
(5) Addressing the perception of the United States commitment to the region, General James 
Mattis, Commander of U.S. Central Command, testified in March 2013, `Perhaps the 
greatest risk to U.S. interests in the region is a perceived lack of an enduring U.S. 
commitment to collective interests and the security of our regional partners.'. He went on to 
testify that, `The drawdown of our forces can be misinterpreted as a lack of attention, a lack 
of commitment to the region.'. 
(b) Sense of Congress- It is the sense of Congress that-- 
(1) maintaining only one aircraft carrier battle group in the Arabian Gulf constrains United 
States' options and could put at risk the ability to have diversified platforms from which to 
defend the Arabian Gulf and, if necessary, to conduct military operations to prevent Iran 
from threatening the United States, United States allies, or Iran's neighbors with nuclear 
weapons; 
(2) it is in the interests of the United States to maintain both land-based and sea-based 
capabilities in the region to project force; 
(3) land-based locations in the region could restrict United States military options and 
critically impact the operational capability if required to conduct a defense of the Arabian 
Gulf because the United States has not finalized bilateral security agreements with key Gulf 
Cooperation Council countries; 
(4) as a result of these and other critical limitations associated with maintaining one aircraft 
carrier battle group in the Arabian Gulf, United States military commanders have expressed 
concerns about the operational constraints, the increasing uncertainty among United States 
allies, and the emboldening of potential adversaries such as Iran; 
(5) regarding the ability of the United States Navy to maintain a two aircraft carrier presence 
in the Arabian Gulf, the Chief of Naval Operations, Admiral Jonathan Greenert, stated, `We 
need 11 carriers to do the job. That's been pretty clearly written, and that's underwritten in 
our defense strategic guidance.'. 
(6) the United States should construct and sufficiently sustain a fleet of at least eleven 
aircraft carriers and associated battle force ships in order to meet current and future 
requirements and to support at least a two aircraft carrier battle group presence in the 
Arabian Gulf, in addition to meeting other operational requirements; and 
(7) the United States should finalize bilateral agreements with key Gulf Cooperation Council 
countries that support the Defense of the Arabian Gulf requirements, at the earliest possible 
date. 
House (Floor Consideration) 
On June 13, 2013, as part of its consideration of H.R. 1960, the House rejected, 106-318, 
H.Amdt. 142, which would have amended 10 U.S.C. 5062(b) to reduce from 11 to 10 the 
minimum number of operational aircraft carriers required to be maintained by the Navy. (As a 
conforming action, H.Amdt. 142 would also have repealed Section 1023 of the FY2010 National 
Congressional Research Service 
41 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Defense Authorization Act [H.R. 2647/P.L. 111-84 of October 28, 2009], the provision that 
permits the Navy to maintain a force of 10 rather than 11 operational carriers during the period 
between the inactivation of CVN-65 and the commissioning of CVN-78.) 
Senate 
The Senate Armed Services Committee, in its report (S.Rept. 113-44 of June 20, 2013) on S. 
1197, recommends approving the Navy’s requests for $588.1 million in procurement funding to 
cover cost growth on CVN-78 and $944.9 million in procurement funding for CVN-79 (pages 
295-296).44 
Section 122 of the bill as reported states: 
SEC. 122. CVN-78 CLASS AIRCRAFT CARRIER PROGRAM. 
(a) Cost Limitation Baseline for Lead Ship- Subsection (a)(1) of section 122 of the John 
Warner National Defense Authorization Act for Fiscal Year 2007 (P.L. 109-364; 120 Stat. 
2104) is amended by striking `$10,500,000,000' and inserting `$12,887,000,000'. 
(b) Additional Factor for Adjustment of Limitation Amount- Subsection (b) of such section 
is amended by adding at the end the following new paragraph: 
`(7) The amounts of increases or decreases in costs of that ship that are attributable to the 
shipboard test program.'. 
(c) Hull Number- Such section is further amended in subsections (a)(1), (a)(2), and (b), by 
striking `CVN-21' and inserting `CVN-78'. 
(d) Requirements for CVN-79- Such section is further amended by adding at the end the 
following new subsection: 
`(e) Requirements for CVN-79- 
`(1) QUARTERLY COST ESTIMATE- The Secretary of the Navy shall submit to the 
congressional defense committees on a quarterly basis a report setting forth the most current 
cost estimate for CVN-79 (as estimated by the program manager). Each cost estimate shall 
include the current percentage of completion of the program, the total costs incurred, and an 
estimate of costs at completion for ship construction, government-furnished equipment, and 
engineering and support costs. 
`(2) LIMITATION- If any report under paragraph (1) includes a cost estimate for CVN-79 in 
excess of the amount specified in subsection (a)(2), the Secretary may not make any payment 
of fees under any cost-type or incentive fee contract associated with CVN-79 until the 
program manager determines that the cost estimate for CVN-79 no longer exceeds the 
amount specified in subsection (a)(2).'. 
(e) Conforming Amendment- The heading of such section is amended to read as follows: 
                                                                  
44 The request for $588.1 million in procurement funding to cover cost growth on CVN-78 is included in the $625.8 
million requested in line item 020, Completion of PY [prior-year] Shipbuilding Programs. 
Congressional Research Service 
42 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
`SEC. 122. ADHERENCE TO NAVY COST ESTIMATES FOR CVN-78 CLASS OF 
AIRCRAFT CARRIERS.'. 
Regarding Section 122, S.Rept. 113-44 states: 
CVN–78 class aircraft carrier program (sec. 122) 
The committee recommends a provision that would amend section 122 of the John Warner 
National Defense Authorization Act for Fiscal Year 2007 (Public Law 109–364) by: (1) in 
subsection (a)(1), striking ‘‘$10,500,000,000’’ and inserting ‘‘$12,887,000,000;’’ (2) in 
subsection (b), adding a new factor for adjustment allowing increases or decreases in the cost 
of the ship that are attributable to the shipboard test program; and (3) changing the heading 
of the subsection to reflect that the name of the program has changed from CVN–21 to 
CVN–78. 
The provision would require a quarterly report providing the CVN–79 program manager’s 
cost estimate for CVN–79. The provision would require the Navy to halt payment of fee on 
any cost-type or incentive fee contract associated with CVN–79 until such time that the 
variance between the total program cost estimate and the mandated cost cap has been 
corrected. 
The changes in the CVN–78 cost cap are related to three major areas: 
(1) reflecting allowable changes in the original cost cap due to economic inflation, changes 
in federal, state, or local laws, changes in nonrecurring design and engineering costs 
attributable to achieving compliance with the cost limitation, and changes to correct 
deficiencies that may affect the safety of the ship and personnel; 
(2) cost increases from the shipyard, resulting from increases in labor costs, material costs, 
and design costs, offset by a reduction in shipyard’s fee; and 
(3) cost increases in government-furnished equipment. 
The cost increases in the latter two categories are changes outside the original, allowable 
changes in the cost cap, and are troublesome. The Navy had envisioned the CVN–78 and 
CVN–79 (then called “CVNX–1” and “CVNX–2”) as evolutionary ships that would 
implement new technologies gradually as they matured. However, the Department of 
Defense determined that planned incremental improvements for CVNX–1 did not justify the 
significant investments nor match the pace of technology, given the length of time needed to 
build the carrier. Instead, the CVNX–1 and CVNX–2 designs were combined into a single, 
transformational ship design, called ‘‘CVN–21,’’ with the intent to skip a generation of 
technology, while meeting operational timelines for delivery. 
This has resulted in cost increases in the shipyard, and costs increases in the new 
technologies developed and designed to be installed as government-furnished equipment. 
The shipyard has not been as efficient as it could be, but combining these two ships and 
maintaining the original construction schedule for operational reasons has resulted in reduced 
productivity and inefficiencies in the shipyard’s effort. All told, this has resulted in roughly 
40 percent of the reason to raise the cost cap. 
There have also been cost increases in the equipment beyond the control of the shipyard. 
These include the “transformational” technologies of the electromagnetic aircraft launch 
system (EMALS), the dual-band radar (DBR), and advanced arresting gear (AAG). While 
each of these technologies represents an improvement in capability and promise substantial 
Congressional Research Service 
43 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
reductions in life cycle costs, collectively, these technologies resulted in roughly one third of 
the increase to the total construction costs of CVN–78. 
As a result of the scrutiny of the CVN–78 program, the Navy believes that they and the 
shipyard can deliver the CVN–79 within the cost cap for the program recently adjusted by 
the Secretary of the Navy. This derives from a number of factors, including: 
(1) CVN–79 construction will start with a complete design and a complete bill of material; 
(2) CVN–79 construction will start with a firm set of stable requirements; 
(3) CVN–79 construction will start with the development complete on a host of new 
technologies inserted on CVN 78 ranging from the EMALS and DBR, to key valves in 
systems throughout the ship; and 
(4) CVN–79 construction will start with a revised construction plan that emphasizes the 
completion of work and ship outfitting as early as possible in the construction process to 
optimize cost and ultimately schedule performance. 
The Administration and Congress chose to ignore the lessons repeatedly and painfully 
learned in previous shipbuilding programs that resulted in delays and cost increases. A 
decision to skip a generation of technology must be accompanied by an operational 
assessment of the need date for the operational capability and a plan to ensure new 
generations of technologies are developed, tested, and ready for installation at the optimum 
time during the construction of the ship. Unfortunately, the decision on the construction 
cycle for CVN–78 construction was driven more by the need to replace the USS Enterprise 
at the end of her service life and the need to maintain workload and the industrial base of 
suppliers for the sole U.S. builder of aircraft carriers. The committee is committed to 
working with the Department of the Navy to ensure these lessons are not learned again in 
future Navy vessel construction. (Pages 9-11) 
S.Rept. 113-44 also states: 
Comptroller General review of the Ford-class aircraft carrier program 
The Navy is developing the Ford-class nuclear powered aircraft carrier (CVN–78) to serve as 
the future centerpiece of the carrier strike group. Ford-class carriers will introduce several 
advanced technologies that are intended to create operational efficiencies while enabling 
higher sortie rates with reduced manpower compared to current carriers. As discussed 
elsewhere in this report, however, these new technologies have led to cost and schedule 
problems in constructing the first ship of the class. 
The Government Accountability Office (GAO) has recently reported on significant 
technology delays, construction inefficiencies, testing shortfalls, and cost and schedule 
pressures currently facing CVN–78. The committee remains concerned that these issues 
could delay and limit demonstration of eventual CVN–78 capabilities and potentially affect 
cost, schedule, and performance outcomes for the next ship, CVN–79. 
Section 124 of the National Defense Authorization Act for Fiscal Year 2013 (Public Law 
112–239) required the Secretary of the Navy to report what program management and cost 
control measures the Navy will employ in constructing the second Ford-class aircraft carrier. 
The Secretary of the Navy’s report in response to that requirement identified a number of 
changes in the way CVN–79 will be built that will help improve on the performance on 
CVN–78. 
Congressional Research Service 
44 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
In light of these concerns, the committee directs the GAO to undertake a follow-on review of 
Ford-class carrier acquisition program. Specifically, the committee directs the Comptroller 
General to review: 
(1) program management and cost control measures the Navy plans to employ in 
constructing the CVN–79 ship, as identified in its May 2013 report to Congress, in order to 
determine the extent to which these may be effective in controlling costs. As part of this 
analysis, the Comptroller General should evaluate the Navy’s plans for executing the detail 
design and construction contract for CVN–79, and should pay particular attention to 
components of the Navy’s plan intended to accommodate remaining schedule risk in the 
CVN–78 building program; 
(2) sufficiency of the Navy’s post-delivery test plans for CVN–78 in facilitating timely 
demonstration of ship capabilities. As part of this analysis, the Comptroller General should 
evaluate the extent to which land-based testing delays for critical ship technologies have 
complicated the Navy’s planned post-delivery testing activities and schedule; 
(3) Department of Defense (DOD) analysis underpinning the Navy’s current capability 
estimates for CVN–78, progress made in meeting the ship’s capability requirements, and 
gaps that may exist between the likely performance of the ship and its major capability 
requirements; and 
(4) maturity and implementation of plans by the shipbuilder to manage the workforce during 
concurrent construction of CVN–78 and CVN–79. 
The committee further directs the Comptroller General to submit a report on his review to 
the congressional defense committees by April 30, 2014. (Pages 21-22) 
FY2014 DOD Appropriations Act (H.R. 2397/S. 1429) 
House 
The House Appropriations Committee, in its report (H.Rept. 113-113 of June 17, 2013) on H.R. 
2397, recommends approving the Navy’s requests for $588.1 million in procurement funding to 
cover cost growth on CVN-7845 and $944.9 million in procurement funding for CVN-79 (page 
163). 
Senate 
The Senate Appropriations Committee, in its report (S.Rept. 113-85 of August 1, 2013) on S. 
1429, recommends approving the Navy’s request for $588.1 million in procurement funding to 
cover cost growth on CVN-7846 and reducing by $27.313 million the Navy request for $944.9 
million in procurement funding for CVN-79, with $16.2 million of the reduction being for 
“Restoring acquisition accountability: Reduction in change orders” and $11.113 million of the 
                                                                  
45 This request is included in the $625.8 million requested in line item 20, Completion of PY [prior-year] Shipbuilding 
Programs. 
46 This request is included in the $625.8 million requested in line item 20, Completion of PY [prior-year] Shipbuilding 
Programs. 
Congressional Research Service 
45 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
reduction being for “Maintaining program affordability: SEWIP [Surface Electronic Warfare 
Improvement Program] Block 3 excessive cost growth” (pages 100 and 101). 
Congressional Research Service 
46 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Appendix. March 2013 Report To Congress on 
Construction Plan for CVN-79 
This appendix reprints a March 2013 report to Congress on the Navy’s construction plan for 
CVN-79.47 
                                                                  
47 Aircraft Carrier Construction, John F Kennedy (CVN 79), Report to Congress, March 2013, 17 pp. An annotation on 
the report’s cover page indicates that the report was authorized for public release on May 16, 2013. The report was 
posted at InsideDefense.com (subscription required) on June 21, 2013. See also Megan Eckstein, “Navy Plan To 
Congress Outlines New Strategies To Save On CVN-79,” Inside the Navy, June 24, 2013. 
Congressional Research Service 
47 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
48 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
49 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
50 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
51 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
52 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
53 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
54 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
55 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
56 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
57 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
58 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
59 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
60 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
61 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
62 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
Congressional Research Service 
63 

Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
 
 
Congressional Research Service 
64 
Navy Ford (CVN-78) Class Aircraft Carrier Program: Background and Issues for Congress 
 
Author Contact Information 
 
Ronald O'Rourke 
   
Specialist in Naval Affairs 
rorourke@crs.loc.gov, 7-7610 
 
 
Congressional Research Service 
65