Multiyear Procurement (MYP) and Block Buy 
Contracting in Defense Acquisition: 
Background and Issues for Congress 
Ronald O'Rourke 
Specialist in Naval Affairs 
Moshe Schwartz 
Specialist in Defense Acquisition 
December 20, 2012 
Congressional Research Service 
7-5700 
www.crs.gov 
R41909 
CRS Report for Congress
Pr
  epared for Members and Committees of Congress        
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Summary 
Multiyear procurement (MYP) and block buy contracting (BBC) are special contracting 
mechanisms that Congress permits the Department of Defense (DOD) to use for a limited number 
of defense acquisition programs. Compared to the standard or default approach of annual 
contracting, MYP and BBC have the potential for reducing weapon procurement costs by several 
percent. 
Under annual contracting, DOD uses one or more contracts for each year’s worth of procurement 
of a given kind of item. Under MYP, DOD instead uses a single contract for two to five years’ 
worth of procurement of a given kind of item without having to exercise a contract option for 
each year after the first year. DOD needs congressional approval for each use of MYP. There is a 
permanent statute governing MYP contracting—10 U.S.C. 2306b. Under this statute, a program 
must meet several criteria to qualify for MYP. 
Compared with estimated costs under annual contracting, estimated savings for programs being 
proposed for MYP have ranged from less than 5% to more than 15%, depending on the 
particulars of the program in question, with many estimates falling in the range of 5% to 10%. In 
practice, actual savings from using MYP rather than annual contracting can be difficult to observe 
or verify because of cost growth during the execution of the contract due to changes in the 
program independent of the use of MYP rather than annual contracting.  
BBC is similar to MYP in that it permits DOD to use a single contract for more than one year’s 
worth of procurement of a given kind of item without having to exercise a contract option for 
each year after the first year. BBC is also similar to MYP in that DOD needs congressional 
approval for each use of BBC. BBC differs from MYP in the following ways: 
•  There is no permanent statute governing the use of BBC. 
•  There is no requirement that BBC be approved in both a DOD appropriations act 
and an act other than a DOD appropriations act. 
•  Programs being considered for BBC do not need to meet any legal criteria to 
qualify for BBC, because there is no permanent statute governing the use of BBC 
that establishes such criteria. 
•  A BBC contract can cover more than five years of planned procurements. 
•  Economic order quantity (EOQ) authority—the authority to bring forward 
selected key components of the items to be procured under the contract and 
purchase the components in batch form during the first year or two of the 
contract—does not come automatically as part of BBC authority because there is 
no permanent statute governing the use of BBC that includes EOQ authority as 
an automatic feature. 
•  BBC contracts are less likely to include cancellation penalties. 
Potential issues for Congress concerning MYP and BBC include whether to use MYP and BBC in 
the future more frequently, less frequently, or about as frequently as they are currently used, and 
whether to create a permanent statute to govern the use of BBC, analogous to the permanent 
statute that governs the use of MYP. 
Congressional Research Service 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Contents 
Introduction ...................................................................................................................................... 1 
Issues for Congress .................................................................................................................... 1 
Terminology and Scope of Report ............................................................................................. 1 
Block Buy Contracting vs. Air Force’s Block Buy of Two AEHF Satellites ...................... 1 
Funding Approaches vs. Contracting Mechanisms ............................................................. 1 
Scope of Report ................................................................................................................... 2 
Background ...................................................................................................................................... 2 
Multiyear Procurement (MYP) .................................................................................................. 2 
MYP in Brief ....................................................................................................................... 2 
Potential Savings Under MYP ............................................................................................ 3 
Permanent Statute Governing MYP .................................................................................... 5 
Potential Consequences of Not Fully Funding an MYP Contract ....................................... 7 
Effect on Flexibility for Making Procurement Changes ..................................................... 7 
Congressional Approval ...................................................................................................... 7 
Block Buy Contracting (BBC) .................................................................................................. 8 
BBC in Brief ....................................................................................................................... 8 
Terminology Alert: Block Buy Contracting vs. Block Buys ............................................... 9 
Potential Savings Under BBC ........................................................................................... 10 
Frequency of Use of BBC ................................................................................................. 10 
Using BBC Rather than MYP ........................................................................................... 10 
MYP and BBC vs. Contracts with Options ............................................................................. 11 
Issues for Congress ........................................................................................................................ 11 
Frequency of Using MYP and BBC ........................................................................................ 11 
Permanent Statute for BBC ..................................................................................................... 12 
Legislative Activity for FY2013 .................................................................................................... 13 
MYP Proposals in DOD’s FY2013 Budget ............................................................................. 13 
FY2013 National Defense Authorization Act (H.R. 4310/S. 3254) ........................................ 13 
House ................................................................................................................................. 13 
Senate ................................................................................................................................ 14 
Conference ........................................................................................................................ 16 
FY2013 DOD Appropriations Bill (H.R. 5856) ...................................................................... 16 
House ................................................................................................................................. 16 
Senate ................................................................................................................................ 16 
 
Tables 
Table A-1. Programs Approved for MYP in Annual DOD Appropriations Acts Since 
FY1990 ....................................................................................................................................... 17 
 
Appendixes 
Appendix. Programs Approved for MYP in Annual DOD Appropriations Acts Since 
FY1990 ....................................................................................................................................... 17 
Congressional Research Service 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
 
Contacts 
Author Contact Information........................................................................................................... 19 
 
Congressional Research Service 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Introduction 
Issues for Congress 
This report provides background information and issues for Congress on multiyear procurement 
(MYP) and block buy contracting (BBC),1 which are special contracting mechanisms that 
Congress permits the Department of Defense (DOD) to use for a limited number of defense 
acquisition programs. Compared to the standard or default approach of annual contracting, MYP 
and BBC have the potential for reducing weapon procurement costs by several percent. 
Potential issues for Congress concerning MYP and BBC include whether to use MYP and BBC in 
the future more frequently, less frequently, or about as frequently as they are currently used, and 
whether to create a permanent statute to govern the use of BBC, analogous to the permanent 
statute (10 U.S.C. 2306b) that governs the use of MYP. Congress’s decisions on these issues 
could affect defense acquisition practices, defense funding requirements, and the defense 
industrial base. 
Terminology and Scope of Report 
Block Buy Contracting vs. Air Force’s Block Buy of Two AEHF Satellites 
For FY2013, the Air Force is requesting continued procurement funding for two Advanced 
Extremely High Frequency (AEHF) satellites that were procured and partially funded in FY2012. 
Although the Air Force refers to this two-satellite procurement as a block buy, it is not an 
example of block buy contracting as discussed in this report. The Air Force in this instance is 
using the term block buy to mean something different. For further discussion of this different use 
of the term block buy, see “Terminology Alert: Block Buy Contracting vs. Block Buys” below. 
Funding Approaches vs. Contracting Mechanisms 
In discussing MYP and BBC, it can be helpful to distinguish funding approaches from contracting 
mechanisms. The two are often mixed together in discussions of DOD acquisition, sometimes 
leading to confusion. Stated briefly: 
•  Funding approaches are ways that Congress can appropriate funding for 
weapon procurement programs, so that DOD can then put them under contract. 
Examples of funding approaches include traditional full funding (the standard or 
default approach), incremental funding, and advance appropriations.2 Any of 
                                                 
1 MYP is an established acronym for multiyear procurement. BBC is not an established acronym for block buy 
contracting, but is used in this CRS report for purposes of convenience. 
2 For more on these three funding approaches, see CRS Report RL31404, Defense Procurement: Full Funding Policy—
Background, Issues, and Options for Congress, by Ronald O'Rourke and Stephen Daggett, and CRS Report RL32776, 
Navy Ship Procurement: Alternative Funding Approaches—Background and Options for Congress, by Ronald 
O'Rourke. Advance appropriations, which are not to be confused with advance procurement (AP) funding (see footnote 
3), are essentially a legislatively locked-in form of incremental funding. Unlike incremental funding, advance 
appropriations qualify under budgeting regulations as a form of full funding. 
Congressional Research Service 
1 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
these funding approaches might make use of advance procurement (AP) 
funding.3 
•  Contracting mechanisms are ways for DOD to contract for the procurement of 
weapons systems, once funding for those systems has been appropriated by 
Congress. Examples of contracting mechanisms include annual contracting (the 
standard or default approach), MYP, and BBC. 
The use of a particular funding approach in a defense acquisition program does not dictate the use 
of a particular contracting mechanism. Defense acquisition programs consequently can be 
implemented using various combinations of funding approaches and contracting mechanisms. 
Most DOD weapon acquisition programs use a combination of traditional full funding and annual 
contracting. A few programs, particularly certain Navy shipbuilding programs, use incremental 
funding as their funding approach. A limited number of DOD programs use MYP as their 
contracting approach, and to date at least two defense acquisition programs (both Navy 
shipbuilding programs) use or have used BBC as their contracting approach. 
Scope of Report 
This report focuses on the contracting approaches of MYP and BBC and how they compare to 
annual contracting. Other CRS reports discuss the funding approaches of traditional full funding, 
incremental funding, and advance appropriations.4 
This report does not discuss the Air Force’s proposed procurement of two Advanced Extremely 
High Frequency (AEHF) satellites in FY2012, except, as noted above, to explain why it is not an 
example of block buy contracting as discussed in this report. 
Background 
Multiyear Procurement (MYP) 
MYP in Brief 
What is MYP, and how does it differ from annual contracting? MYP, also known as multiyear 
contracting, is an alternative to the standard or default DOD approach of annual contracting. 
Under annual contracting, DOD uses one or more contracts for each year’s worth of procurement 
of a given kind of item. Under MYP, DOD instead uses a single contract for two to five years’ 
                                                 
3 AP funding is provided in one or more years prior to the year of procurement of a weapon system for the procurement 
of long-leadtime components—components with long construction times. Such components must be funded prior to the 
procurement of the remainder of the weapon system if they are to be ready for installation in the weapon system at the 
appropriate point in the construction process. AP funding is a permitted exception to the full funding provision. AP 
funding is not to be confused with advance appropriations (see footnote 2). 
4 See footnote 2 for citations to these reports. Appropriating funding for a program and placing a program under 
contract are steps in a larger sequence of budget-related events that includes authorization, appropriation, obligation, 
and outlays. For a general discussion of this sequence, see CRS Report 98-721, Introduction to the Federal Budget 
Process, coordinated by Bill Heniff Jr. 
Congressional Research Service 
2 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
worth of procurement of a given kind of item, without having to exercise a contract option for 
each year after the first year. DOD needs congressional approval for each use of MYP. 
To illustrate the basic difference between MYP and annual contracting, consider a hypothetical 
DOD program to procure 20 single-engine aircraft of a certain kind over the five-year period 
FY2013-FY2017, at a rate of four aircraft per year: 
•  Under annual contracting, DOD would issue one or more contracts for each 
year’s procurement of four aircraft. After Congress funds the procurement of the 
first four aircraft in FY2013, DOD would issue one or more contracts (or 
exercise a contract option) for those four aircraft. The next year, after Congress 
funds the procurement of the next four aircraft in FY2013, DOD would issue one 
or more contracts (or exercise a contract option) for those four aircraft, and so on. 
•  Under MYP, DOD would issue one contract covering all 20 aircraft to be 
procured during the five-year period FY2013-FY2017. DOD would award this 
contract in FY2013, at the beginning of the five-year period, following 
congressional approval to use MYP for the program, and congressional 
appropriation of the FY2013 funding for the program. To continue the 
implementation of the contract over the next four years, DOD would request the 
FY2014 funding for the program as part of DOD’s proposed FY2014 budget, the 
FY2015 funding as part of DOD’s proposed FY2015 budget, and so on. 
Potential Savings Under MYP 
How much can MYP save? Compared with estimated costs under annual contracting, estimated 
savings for programs being proposed for MYP have ranged from less than 5% to more than 15%, 
depending on the particulars of the program in question, with many estimates falling in the range 
of 5% to 10%. In practice, actual savings from using MYP rather than annual contracting can be 
difficult to observe or verify because of cost growth during the execution of the contract that was 
caused by developments independent of the use of MYP rather than annual contracting. 
A February 2012 briefing by the Cost Assessment and Program Evaluation (CAPE) office within 
the Office of the Secretary of Defense (OSD) states that “MYP savings analysis is difficult due to 
the lack of actual costs on the alternative acquisition path, i.e., the path not taken.”5 The briefing 
states that CAPE up to that point had assessed MYP savings for four aircraft procurement 
programs—F/A-18E/F strike fighters, H-60 helicopters, V-22 tilt-rotor aircraft, and CH-47F 
helicopters—and that CAPE’s assessed savings ranged from 2% to 8%.6 
A 2008 Government Accountability Office (GAO) report stated that 
DOD does not have a formal mechanism for tracking multiyear results against original 
expectations and makes few efforts to validate whether actual savings were achieved by 
                                                 
5 Slide 10 from briefing entitled “Multiyear Procurement: A CAPE Perspective,” given at DOD cost analysis 
symposium, February 15-17, 2012, posted at InsideDefense.com (subscription required) May 14, 2012. 
6 Slide 12 from briefing entitled “Multiyear Procurement: A CAPE Perspective,” given at DOD cost analysis 
symposium, February 15-17, 2012, posted at InsideDefense.com (subscription required) May 14, 2012. Slide 12 also 
stated that these assessed savings were based on comparing CAPE’s estimate of what the programs would cost under 
annual contracting (which the briefing refers to as single-year procurement or SYP) to the contractor’s MYP proposal. 
Congressional Research Service 
3 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
multiyear procurement. It does not maintain comprehensive central records and historical 
information that could be used to enhance oversight and knowledge about multiyear 
performance to inform and improve future multiyear procurement (MYP) candidates. DOD 
and defense research centers officials said it is difficult to assess results because of the lack 
of historical information on multiyear contracts, comparable annual costs, and the dynamic 
acquisition environment.7 
How does MYP potentially save money? Compared to annual contracting, using MYP can in 
principle reduce the cost of the weapons being procured in two primary ways: 
•  Contractor optimization of workforce and production facilities. An MYP 
contract gives the contractor (e.g., an airplane manufacturer or shipbuilder) 
confidence that a multiyear stream of business of a known volume will very 
likely materialize. This confidence can permit the contractor to make investments 
in the firm’s workforce and production facilities that are intended to optimize the 
facility for the production of the items being procured under the contract. Such 
investments can include payments for retaining or training workers, or for 
building, expanding, or modernizing production facilities. Under annual 
contracting, the manufacturer might not have enough confidence about its future 
stream of business to make these kinds of investments, or might be unable to 
convince its parent firm to finance them. 
•  Economic order quantity (EOQ) purchases of selected long-leadtime 
components. Under an MYP contract, DOD is permitted to bring forward 
selected key components of the items to be procured under the contract and to 
purchase the components in batch form during the first year or two of the 
contract. In the hypothetical example introduced earlier, using MYP could permit 
DOD to purchase, say, the 20 engines for the 20 aircraft in the first year or two of 
the five-year contract. Procuring selected components in this manner under an 
MYP contract is called an economic order quantity (EOQ) purchase.8 EOQ 
purchases can reduce the procurement cost of the weapons being procured under 
the MYP contract by allowing the manufacturers of components to take 
maximum advantage of production economies of scale that are possible with 
batch orders.9 
                                                 
7 Government Accountability Office, Defense Acquisitions[:] DOD’s Practices and Processes for Multiyear 
Procurement Should Be Improved, GAO-08-298, February 2008, p. 3. 
8 The term EOQ is occasionally used in discussions of defense acquisition, somewhat loosely, to refer to any high-
quantity or batch order of items, even those that do not take place under MYP or BBC. As a general matter, however, 
EOQs as described here occur only within MYP and block buy contracts. 
9 A 2008 Government Accountability Office (GAO) report on multiyear contracting lists five areas of savings, most of 
which are covered in the two general areas of savings outlined above. One of GAO’s five areas of savings—limited 
engineering changes due to design stability—can also occur in programs that use annual contracting. The GAO report 
states: 
Multiyear procurement can potentially save money and improve the defense industrial base by 
permitting the more efficient use of a contractor’s resources. Multiyear contracts are expected to 
achieve lower unit costs compared to annual contracts through one or more of the following 
sources: (1) purchase of parts and materials in economic order quantities (EOQ), (2) improved 
production processes and efficiencies, (3) better utilized industrial facilities, (4) limited engineering 
changes due to design stability during the multiyear period, and (5) cost avoidance by reducing the 
burden of placing and administering annual contracts. Multiyear procurement also offers 
opportunities to enhance the industrial base by providing defense contractors a longer and more 
(continued...) 
Congressional Research Service 
4 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
What gives the contractor confidence that the multiyear stream of business will materialize? At 
least two things give the contractor confidence that DOD will not terminate an MYP contract and 
that the multiyear stream of business consequently will materialize: 
•  For a program to qualify for MYP, DOD must certify, among other things, that 
the minimum need for the items to be purchased is expected to remain 
substantially unchanged during the contract in terms of production rate, 
procurement rate, and total quantities. 
•  Perhaps more important to the contractor, MYP contracts include a cancellation 
penalty intended to reimburse a contractor for costs that the contractor has 
incurred (i.e., investments the contractor has made) in anticipation of the work 
covered under the MYP contract. The undesirability of paying a cancellation 
penalty acts as a disincentive for the government against canceling the contract. 
(And if the contract is canceled, the cancellation penalty helps to make the 
contractor whole.)10 
Permanent Statute Governing MYP 
Is there a permanent statute governing MYP contracting? There is a permanent statute 
governing MYP contracting—10 U.S.C. 2306b. The statute was created by Section 909 of the 
FY1982 Department of Defense Authorization Act (S. 815/P.L. 97-86 of December 1, 1981), 
revised and reorganized by Section 1022 of the Federal Acquisition Streamlining Act of 1994 (S. 
1587/P.L. 103-355 of October 13, 1994), and further amended on several occasions since. DOD’s 
use of MYP contracting is further governed by DOD acquisition regulations. 
Under this statute, what criteria must a program meet to qualify for MYP? 10 U.S.C. 2306b(a) 
states that to qualify for MYP, a program must meet several criteria, including the following. 
•  Substantial savings. DOD must estimate that using an MYP contract would 
result in “substantial savings” compared with using annual contracting. 
•  Realistic cost estimates. DOD’s estimates of the cost of the MYP contract and 
the anticipated savings must be realistic.  
•  Stable need for the items. DOD must expect that its minimum need for the 
items will remain substantially unchanged during the contract in terms of 
production rate, procurement rate, and total quantities. 
                                                                  
(...continued) 
stable time horizon for planning and investing in production and by attracting subcontractors, 
vendors, and suppliers. However, multiyear procurement also entails certain risks that must be 
balanced against potential benefits, such as the increased costs to the government should the 
multiyear contract be changed or canceled and decreased annual budget flexibility for the program 
and across DOD’s portfolio of weapon systems. Additionally, multiyear contracts often require 
greater budgetary authority in the earlier years of the procurement to economically buy parts and 
materials for multiple years of production than under a series of annual buys. 
Government Accountability Office, Defense Acquisitions[:] DOD’s Practices and Processes for Multiyear 
Procurement Should Be Improved, GAO-08-298, February 2008, pp. 4-5. 
10 Annual contracts can also include cancellation penalties. 
Congressional Research Service 
5 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
•  Stable design for the items. The design for the items to be acquired must be 
stable, and the technical risks associated with the items must not be excessive. 
Section 811 of the FY2008 National Defense Authorization Act (H.R. 4986/P.L. 110-181 of 
January 28, 2008) amended 10 U.S.C. 2306b to require the Secretary of Defense to certify in 
writing, by no later than March 1 of the year in which DOD requests MYP authority for a 
program, that these and certain other criteria have been met. It also requires that the Secretary 
provide the congressional defense committees with the basis for this determination, as well as a 
cost analysis performed by DOD’s office of Cost Assessment and Program Evaluation (CAPE) 
that supports the findings.11 Section 811 further amended 10 U.S.C. 2306b to require the 
following: 
•  Sufficient prior deliveries to determine whether estimated unit costs are 
realistic. A sufficient number of the type of item to be acquired under the 
proposed MYP contract must have been delivered under previous contracts at or 
within the most current estimates of the program acquisition unit cost or 
procurement unit cost to determine whether current estimates of such unit costs 
are realistic. 
•  No Nunn-McCurdy critical cost growth breaches within the last five years. 
The system being proposed for an MYP contract must not have experienced 
within five years of the anticipated award date of the MYP contract a critical cost 
growth breach as defined under the Nunn-McCurdy act (10 U.S.C. 2433).12 
•  Fixed-price type contract. The proposed MYP contract must be a fixed-price 
type contract. 
What is meant by “substantial savings”? The meaning of “substantial savings” is open to 
interpretation and might depend on the circumstances of the program in question. In practice, 
estimated savings of at least 5% might be judged substantial, and estimated savings in the range 
of 10% (or more) are more likely to be judged substantial. The amount of savings required under 
10 U.S.C. 2306b to qualify has changed over time; the requirement for “substantial savings” was 
established by Section 808(a)(2) of the FY1991 National Defense Authorization Act (H.R. 
4739/P.L. 101-510 of November 5, 1990), which amended 10 U.S.C. 2306b in this regard.13 
What is meant by “stable design”? The term “stable design” is generally understood to mean that 
the design for the items to be procured is not expected to change substantially during the period 
of the contract. Having a stable design is generally demonstrated by having already built at least a 
few items to that design (or in the case of a shipbuilding program, at least one ship to that design) 
and concluding, through testing and operation of those items, that the design does not require any 
substantial changes during the period of the contract. 
                                                 
11 §811 states that the cost analysis is to be performed by DOD’s Cost Analysis Improvement Group (CAIG). In a 
subsequent DOD reorganization, CAIG was made part of CAPE. 
12 For more on the Nunn-McCurdy provision, see CRS Report R41293, The Nunn-McCurdy Act: Background, 
Analysis, and Issues for Congress, by Moshe Schwartz. 
13 For a discussion of the evolution of the savings requirement under 10 U.S.C. 2306b, including a figure graphically 
summarizing the legislative history of the requirement, see Government Accountability Office, Defense Acquisitions[:] 
DOD’s Practices and Processes for Multiyear Procurement Should Be Improved, GAO-08-298, February 2008, pp. 21-
22, including Figure 3 on p. 22. 
Congressional Research Service 
6 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Potential Consequences of Not Fully Funding an MYP Contract 
What happens if Congress does not provide the annual funding requested by DOD to continue 
the implementation of the contract? If Congress does not provide the funding requested by DOD 
to continue the implementation of an MYP contract, DOD would be required to renegotiate, 
suspend, or terminate the contract. Terminating the contract could require the government to pay 
a cancellation penalty to the contractor. Renegotiating or suspending the contract could also have 
a financial impact. 
Effect on Flexibility for Making Procurement Changes 
What effect does using MYP have on flexibility for making procurement changes? A principal 
potential disadvantage of using MYP is that it can reduce Congress’s and DOD’s flexibility for 
making changes (especially reductions) in procurement programs in future years in response to 
changing strategic or budgetary circumstances, at least without incurring cancellation penalties. 
In general, the greater the portion of DOD’s procurement account that is executed under MYP 
contracts, the greater the potential loss of flexibility. The use of MYP for executing some portion 
of the DOD procurement account means that if policymakers in future years decide to reduce 
procurement spending below previously planned levels, the spending reduction might fall more 
heavily on procurement programs that do not use MYP, which in turn might result in a less-than-
optimally balanced DOD procurement effort. 
Congressional Approval 
How does Congress approve the use of MYP? Congress approves the use of MYP on a case-by-
case basis, typically in response to requests by DOD.14 Congressional approval for MYP contracts 
with a value of more than $500 million must occur in two places: an annual DOD appropriations 
act15 and an act other than the annual DOD appropriations act.16 
In annual DOD appropriations acts, the provision permitting the use of MYP for one or more 
defense acquisition programs is typically included in the title containing general provisions, 
which typically is Title VIII. 
An annual defense authorization act is usually the act other than an appropriations act in which 
provisions granting authority for using MYP contracting on individual defense acquisition 
programs are included. Such provisions typically occur in Title I of the defense authorization act, 
the title covering procurement programs. 
                                                 
14 The Anti-Deficiency Act (31 U.S.C. 1341) prohibits the making of contracts in advance of appropriations. A 
multiple-year commitment may be made when authorized by Congress by entering into a firm commitment for one 
year and making the government’s liability for future years contingent on funds becoming available. 
15 Paragraph (3) of subsection (l) of 10 U.S.C. 2306b states, “The head of an agency may not initiate a multiyear 
procurement contract for any system (or component thereof) if the value of the multiyear contract would exceed 
$500,000,000 unless authority for the contract is specifically provided in an appropriations Act.” 
16 Paragraph (3) of subsection (i) of 10 U.S.C. 2306b states, “In the case of the Department of Defense, a multiyear 
contract in an amount equal to or greater than $500,000,000 may not be entered into for any fiscal year under this 
section unless the contract is specifically authorized by law in an Act other than an appropriations Act.” 
Congressional Research Service 
7 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Provisions in which Congress approves the use of MYP for a particular defense acquisition 
program may include specific conditions for that program in addition to the requirements and 
conditions of 10 U.S.C. 2306b. 
How often is MYP used? MYP is used for a limited number of DOD acquisition programs. As 
shown in the Appendix, annual DOD appropriations acts since FY1990 typically have approved 
the use of MYP for one or a few DOD programs each year. 
A February 2012 briefing by the Cost Assessment and Program Evaluation (CAPE) office within 
the Office of the Secretary of Defense (OSD) shows that the total dollar value of DOD MYP 
contracts has remained more or less stable between FY2000 and FY2012 at roughly $7 billion to 
$13 billion per year. The briefing shows that since the total size of DOD’s procurement budget 
has increased during this period, the portion of DOD’s total procurement budget accounted for by 
programs using MYP contracts has declined from about 17% in FY2000 to less than 8% in 
FY2012.17 The briefing also shows that the Navy makes more use of MYP contracts than does the 
Army or Air Force, and that the Air Force made very little use of MYP in FY2010-FY2012.18 
A 2008 Government Accountability Office (GAO) report stated: 
Although DOD had been entering into multiyear contracts on a limited basis prior to the 
1980s, the Department of Defense Authorization Act, [for fiscal year] 1982,19 codified the 
authority for DOD to procure on a multiyear basis major weapon systems that meet certain 
criteria. Since that time, DOD has annually submitted various weapon systems as multiyear 
procurement candidates for congressional authorization. Over the past 25 years, Congress 
has authorized the use of multiyear procurement for approximately 140 acquisition 
programs, including some systems approved more than once.20 
Block Buy Contracting (BBC) 
BBC in Brief 
What is BBC, and how does it compare to MYP? BBC is similar to MYP in that it permits DOD 
to use a single contract for more than one year’s worth of procurement of a given kind of item 
without having to exercise a contract option for each year after the first year.21 BBC is also 
similar to MYP in that DOD needs congressional approval for each use of BBC. 
                                                 
17 Slide 4 from briefing entitled “Multiyear Procurement: A CAPE Perspective,” given at DOD cost analysis 
symposium, February 15-17, 2012, posted at InsideDefense.com (subscription required) May 14, 2012. 
18 Slide 5 from briefing entitled “Multiyear Procurement: A CAPE Perspective,” given at DOD cost analysis 
symposium, February 15-17, 2012, posted at InsideDefense.com (subscription required) May 14, 2012. 
19 S. 815/P.L. 97-86 of December 1, 1981, §909. 
20 Government Accountability Office, Defense Acquisitions[:] DOD’s Practices and Processes for Multiyear 
Procurement Should Be Improved, GAO-08-298, February 2008, p. 5. 
21 Using the hypothetical example introduced earlier involving the procurement of 20 aircraft over the five-year period 
FY2013-FY2017, DOD would follow the same general path as it would under MYP: DOD would issue one contract 
covering all 20 aircraft in FY2013, at the beginning of the five-year period, following congressional approval to use 
BBC for the program, and congressional appropriation of the FY2013 funding for the program. To continue the 
implementation of the contract over the next four years, DOD would request the FY2014 funding for the program as 
part of DOD’s proposed FY2014 budget, the FY2015 funding as part of DOD’s proposed FY2015 budget, and so on. 
Congressional Research Service 
8 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
BBC differs from MYP in the following ways: 
•  There is no permanent statute governing the use of BBC. 
•  There is no requirement that BBC be approved in both a DOD appropriations act 
and an act other than a DOD appropriations act. 
•  Programs being considered for BBC do not need to meet any legal criteria to 
qualify for BBC because there is no permanent statute governing the use of BBC 
that establishes such criteria. 
•  A BBC contract can cover more than five years of planned procurements. The 
BBC contracts currently being used by the Navy for procuring Littoral Combat 
Ships (LCSs), for example, cover a period of six years (FY2011-FY2016). 
•  Economic order quantity (EOQ) authority does not come automatically as part of 
BBC authority because there is no permanent statute governing the use of BBC 
that includes EOQ authority as an automatic feature. To provide EOQ authority 
as part of a BBC contract, the provision granting authority for using BBC in a 
program may need to state explicitly that the authority to use BBC includes the 
authority to use EOQ. 
•  BBC contracts are less likely to include cancellation penalties. 
Given the one key similarity between BBC and MYP (the use of a single contract for more than 
one year’s worth of procurement), and the various differences between BBC and MYP, BBC 
might be thought of as a less formal stepchild of MYP. 
When and why was BBC invented? BBC was invented by Section 121(b) of the FY1998 
National Defense Authorization Act (H.R. 1119/P.L. 105-85 of November 18, 1997), which 
granted the Navy the authority to use a single contract for the procurement of the first four 
Virginia (SSN-774) class attack submarines. The four boats were scheduled to be procured during 
the five-year period FY1998-FY2002 in annual quantities of 1-1-0-1-1. Congress provided the 
authority granted in Section 121(b) at least in part to reduce the combined procurement cost of the 
four submarines. Using MYP was not an option for the Virginia-class program at that time 
because the Navy had not even begun, let alone finished, construction of the first Virginia-class 
submarine, and consequently could not demonstrate that it had a stable design for the program. 
When Section 121(b) was enacted, there was no name for the contracting authority it provided. 
The term block buy contracting came into use later, when observers needed a term to refer to the 
kind of contracting authority that Congress authorized in Section 121(b). As discussed in the next 
section, this can cause confusion, because the term block buy was already being used in 
discussions of DOD acquisition to refer to something else. 
Terminology Alert: Block Buy Contracting vs. Block Buys 
What’s the difference between block buy contacting and block buys? In discussions of defense 
procurement, the term “block buy” by itself (without “contracting” at the end) is sometimes used 
to refer to something quite different from block buy contracting—namely, the simple act of 
funding the procurement of more than one copy of an item in a single year, particularly when no 
more than one item of that kind might normally be funded in a single year. For example, when 
Congress funded the procurement of two aircraft carriers in FY1983, and another two in FY1988, 
these acts were each referred to as block buys, because aircraft carriers are normally procured one 
Congressional Research Service 
9 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
at a time, several years apart from one another. This alternate meaning of the term block buy 
predates by many years the emergence of the term block buy contracting. 
The term block buy is still used in this alternate manner, which can lead to confusion in 
discussions of defense procurement. For example, for FY2013, the Air Force is requesting 
continued procurement funding for two Advanced Extremely High Frequency (AEHF) satellites 
that were procured and partially funded in FY2012. (An alternative approach would have been to 
procure one of the satellites in FY2012 and another in a subsequent year.) The Air Force is 
referring to this two-satellite procurement as a block buy—which it is, under the older use of the 
term. But it is not an example of block buy contracting. 
At the same time, Navy officials sometimes refer to the use of block buy contracts for the first 
four Virginia-class submarines, and currently in the LCS program, as block buys, when they 
might be more specifically referred to as instances of block buy contracting. 
Potential Savings Under BBC 
How much can BBC save, compared with MYP? Potential savings under BBC can be less than 
those under MYP, for at least two reasons: 
•  The authority to use BBC might not include authority to use EOQ purchasing, 
which, as discussed earlier (see “Potential Savings Under MYP”), is one of the 
two principal sources of savings under an MYP contract. The block buy contract 
for the first four Virginia-class boats and the current block buy contracts for the 
LCS program do not include authority for EOQ purchasing. 
•  A BBC contract might not include a cancellation penalty (or might include a 
more limited one). This can give the contractor less confidence than would be the 
case under an MYP contract that the future stream of business will materialize as 
planned, which in turn might reduce the amount of money the contractor invests 
to optimize its workforce and production facilities for producing the items to be 
procured under the contract. 
Frequency of Use of BBC 
How frequently has BBC been used? Since its use at the start of the Virginia-class program, 
BBC has been used very rarely. The Navy did not use it again in a shipbuilding program until 
December 2010, when it awarded two block buy contracts, each covering 10 LCSs to be procured 
over the six-year period FY2010-FY2015, to the two LCS builders.22 
Using BBC Rather than MYP 
When might BBC be suitable as an alternative to MYP? BBC might be particularly suitable as 
an alternative to MYP in cases where using a multiyear contract can reduce costs, but the program 
in question cannot meet all the statutory criteria needed to qualify for MYP. As shown in the case 
of the first four Virginia-class boats, this can occur at or near the start of a procurement program, 
                                                 
22 For further discussion, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and 
Issues for Congress, by Ronald O'Rourke. 
Congressional Research Service 
10 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
when design stability has not been demonstrated through the production of at least a few of the 
items to be procured (or, for a shipbuilding program, at least one ship). 
MYP and BBC vs. Contracts with Options 
What’s the difference between an MYP or block buy contract and a contract with options? The 
military services sometimes use contracts with options to procure multiple copies of an item that 
are procured over a period of several years. The Navy, for example, used a contract with options 
to procure Lewis and Clark (TAKE-1) class dry cargo ships that were procured over a period of 
several years. A contract with options can be viewed as somewhat similar to an MYP or block 
buy contract in that a single contract is used to procure several years’ worth of procurement of a 
given kind of item. 
There is, however, a key difference between an MYP or block buy contract and a contract with 
options: In a contract with options, the service is under no obligation to exercise any of the 
options, and a service can choose to not exercise an option without having to make a penalty 
payment to the contractor. In contrast, in an MYP or block buy contract, the service is under an 
obligation to continue implementing the contract beyond the first year, provided that Congress 
appropriates the necessary funds. If the service chooses to terminate an MYP or block buy 
contract, and does so as a termination for government convenience rather than as a termination 
for contractor default, then the contractor can, under the contract’s termination for convenience 
clause, seek a payment from the government for cost incurred for work that is complete or in 
process at the time of termination, and may include the cost of some of the investments made in 
anticipation of the MYP or block buy contract being fully implemented. The contractor can do 
this even if the MYP or block buy contract does not elsewhere include a provision for a 
cancellation penalty.23 
Issues for Congress 
Potential issues for Congress concerning MYP and BBC include whether to use MYP and BBC in 
the future more frequently, less frequently, or about as frequently as they are currently used, and 
whether to create a permanent statute to govern the use of BBC, analogous to the permanent 
statute that governs the use of MYP. 
Frequency of Using MYP and BBC 
Should MYP and BBC in the future be used more frequently, less frequently, or about as 
frequently as they are currently used? Supporters of using MYP and BBC more frequently in the 
future might argue the following: 
•  Since MYP and BBC can reduce procurement costs, making greater use of MYP 
and BBC can help DOD get more value out of its available procurement funding. 
                                                 
23 Source: Telephone discussion with Elliott Branch, Deputy Assistant Secretary of the Navy for Acquisition & 
Procurement, October 3, 2011, and email from Navy Office of legislative Affairs, October 11, 2011. Under the 
termination for convenience clause, the contractor can submit a settlement proposal to the service, which would 
become the basis for a negotiation between the contractor and the service on the amount of the payment. 
Congressional Research Service 
11 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
This can be particularly important if DOD’s budget in real (i.e., inflation-
adjusted) terms remains flat or declines in coming years, as many observers 
anticipate. 
•  The risks of using MYP have been reduced by Section 811 of the FY2008 
National Defense Authorization Act (H.R. 4986/P.L. 110-181 of January 28, 
2008), which amended 10 U.S.C. 2306b to strengthen the process for ensuring 
that programs proposed for MYP meet certain criteria (see “Permanent Statute 
Governing MYP”). Since the value of MYP contracts equated to less than 8% of 
DOD’s procurement budget in FY2012, compared to about 17% of DOD’s 
procurement budget in FY2000, MYP likely could be used more frequently 
without exceeding past experience regarding the share of DOD’s procurement 
budget accounted for by MYP contracts. 
Supporters of using MYP and BBC less frequently in the future, or at least no more frequently 
than now, might argue the following: 
•  Using MYP and BBC more frequently would further reduce Congress’s and 
DOD’s flexibility for making changes in DOD procurement programs in future 
years in response to changing strategic or budgetary circumstances. The risks of 
reducing flexibility in this regard are increased now because of uncertainties in 
the current strategic environment and because efforts to reduce federal budget 
deficits could include reducing DOD spending, which could lead to a 
reassessment of U.S. defense strategy and associated DOD acquisition programs. 
•  Since actual savings from using MYP and BBC rather than annual contracting 
can be difficult to observe or verify, it is not clear that the financial benefits of 
using MYP or BBC more frequently in the future would be worth the resulting 
further reduction in Congress’s and DOD’s flexibility for making changes in 
procurement programs in future years in response to changing strategic or 
budgetary circumstances. 
Permanent Statute for BBC 
Should Congress create a permanent statute to govern the use of BBC, analogous to the 
permanent statute (10 U.S.C. 2306b) that governs the use of MYP? Supporters of creating a 
permanent statute to govern the use of BBC might argue the following: 
•  Such a statute could encourage greater use of BBC, and thereby increase savings 
in DOD procurement programs by giving BBC contracting a formal legal 
standing and by establishing a clear process for DOD program managers to use in 
assessing whether their programs might be considered suitable for BBC. 
•  Such a statute could make BBC more advantageous by including a provision that 
automatically grants EOQ authority to programs using BBC, as well as 
provisions establishing qualifying criteria and other conditions intended to reduce 
the risks of using BBC. 
Opponents of creating a permanent statute to govern the use of BBC might argue the following: 
•  A key advantage of BBC is that it is not governed by a permanent statute. The 
lack of such a statute gives DOD and Congress full flexibility in determining 
Congressional Research Service 
12 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
when and how to use BBC for programs that may not qualify for MYP, but for 
which a multiyear contract of some kind might produce substantial savings. 
•  Such a statute could encourage DOD program managers to pursue their programs 
using BBC rather than MYP. This could reduce discipline in DOD multiyear 
contracting if the qualifying criteria in the BBC statute are less demanding than 
the qualifying criteria in 10 U.S.C. 2306b. 
Legislative Activity for FY2013 
MYP Proposals in DOD’s FY2013 Budget 
DOD for FY2013 is requesting congressional approval for the following MYP arrangements, 
some of which would be successors to earlier MYP arrangements for the same programs: 
•  CH-47F helicopters to be procured in FY2013-FY2017; 
•  Arleigh Burke (DDG-51) Aegis destroyers and associated equipment to be 
procured beginning in FY2013;24 
•  V-22 Ospey tilt-rotor aircraft to be procured in FY2013-FY23017; 25 
•  Virginia (SSN-774) class attack submarines to be procured in FY2014-FY2018;26 
and 
•  a one-year extension of the current MYP arrangement for procuring F/A-18E, 
F/A-18F, and EA-18G aircraft, so that the arrangement, which currently covers 
FY2010-FY2013, would now include FY2014 as well.27 
FY2013 National Defense Authorization Act (H.R. 4310/S. 3254) 
House 
H.R. 4310 as reported by the House Armed Services Committee (H.Rept. 112-479 of May 11, 
2012) would authorize MYP arrangements for CH-47 helicopters (Section 111), V-22 Osprey tilt-
rotor aircraft (Section 124), DDG-51 destroyers (Section 125), and Virginia-class attack 
submarines (Section 126). The bill as reported would also authorize a one-year extension for the 
MYP arrangement for F/A-18E, F/A-18F, and EA-18G aircraft (Section 123). 
                                                 
24 For more on the DDG-51 program, see CRS Report RL32109, Navy DDG-51 and DDG-1000 Destroyer Programs: 
Background and Issues for Congress, by Ronald O'Rourke. 
25 For more on the V-22 program, see CRS Report RL31384, V-22 Osprey Tilt-Rotor Aircraft Program, by Jeremiah 
Gertler. 
26 DOD states that it would be helpful for contract negotiation purposes to receive authority this year for an MYP 
arrangement that would cover Virginia-class attack submarines scheduled for procurement in FY2014-FY2018. For 
more on the Virginia-class program, see CRS Report RL32418, Navy Virginia (SSN-774) Class Attack Submarine 
Procurement: Background and Issues for Congress, by Ronald O'Rourke. 
27 For more on the F/A-18E/F and EA-18G program, see CRS Report RL30624, Navy F/A-18E/F and EA-18G Aircraft 
Program, by Jeremiah Gertler. 
Congressional Research Service 
13 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Senate 
S. 3254 as reported by the Senate Armed Services Committee (S.Rept. 112-173 of June 4, 2012) 
would authorize MYP arrangements for CH-47 helicopters (Section 111), Virginia-class attack 
submarines (Section 124), DDG-51 destroyers (Section 125), and V-22 Osprey tilt-rotor aircraft 
(Section 151). 
Regarding Section 111, S.Rept. 112-173 states: 
Multiyear procurement authority for Army CH–47F helicopters (sec. 111) 
The committee recommends a provision that would authorize the Secretary of the Army to 
enter a multiyear procurement contract in accordance with section 2306b of title 10, United 
States Code, for up to 5 years for Army CH–47F Chinook helicopters. 
The committee has taken the position that committing the Department of Defense, Congress, 
and the taxpayers to multiyear contracts is justified only when the multiyear contract results 
in substantial savings that would not be achieved by annual contracts and meets other 
statutory criteria. In this case, the Army is projecting savings for this next multiyear contract, 
if authorized, to be just over 10 percent. The committee recommends supporting the request 
for multiyear contract authority, but directs the Secretary of the Army to provide the 
congressional defense committees with an annual briefing during the execution of this 
contract on progress achieved in meeting or exceeding the projected savings used to justify 
granting this authority. This briefing shall accompany the Army’s annual budget request. 
(Page 11) 
Regarding Section 124, the report states: 
Multiyear procurement authority for Virginia-class submarine program (sec. 124) 
The committee recommends a provision that would authorize the Secretary of the Navy to 
buy Virginia-class submarines under a multiyear procurement contract. This would be the 
third multiyear contract for the Virginia-class program. The Navy estimates that the previous 
two multiyear procurement contracts (fiscal years 2003–2008 and fiscal years 2009–2013) 
achieved savings of greater than 10 percent as compared to annual procurements. For the 
third contract (for fiscal years 2014–2018), the Navy is estimating that the expected savings 
will be 14 percent for the multiyear approach as compared to annual procurement contracts. 
The Navy is expecting that the number of attack submarines will fall short of meeting the 
requirement in each of the 13 years (2022–2034), starting in the next decade, when the 
inventory of attack submarines will be below the requirement of 48 boats. The committee 
appreciates that fiscal year 2014 is the only year for the foreseeable future where we might 
afford to buy an additional attack submarine to mitigate that shortfall. In other years, we are 
already buying two boats or more, or a single attack submarine and a ballistic missile 
submarine. The next opportunity where the Navy intends to buy only one boat is 2036, far 
too late to have any effect on the projected requirements shortfall. 
Therefore, the provision would also permit the Navy to use incremental funding within the 
second and third multiyear for the explicit purpose of buying an extra boat in 2014. During 
budget deliberations surrounding the fiscal year 2013 budget, the Navy had to delete one of 
the two boats planned for fiscal year 2014 due to top line pressures on the budget, not due to 
any schedule or cost performance issues. The Navy believes that, if the Navy were allowed 
to incrementally fund the boats within these years, the Navy could buy an additional and 
restore the rate of two per year in 2014 without requiring additional resources. This would 
Congressional Research Service 
14 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
have two-fold benefit of stabilizing production at a more affordable rate, and reducing the 
planned shortfall of attack submarines in each of the 13 years when the Navy attack 
submarine inventory falls short of requirements, and would be consistent with congressional 
authorization in section 2308 of title 10, United States Code, for the Secretary to buy-to-
budget. 
The committee appreciates that multiyear procurement authority already represents a 
departure from the full funding policy. In addition to the normal advance procurement 
(which is a lesser departure from full funding in itself), multiyear procurement authority 
allows the Department to contract for parts and construction effort on procurement items for 
which full funding has not been provided. The committee believes that, facing the choice 
between living with a shortfall in requirements and with a very stable production program, 
departing from the full funding policy for this very important program is an appropriate step 
at this time. The committee also recommends an increase of $777.7 million in advance 
procurement to provide a down payment on the second boat in fiscal year 2014. (Pages 12-
13) 
Regarding Section 125, the report states: 
Multiyear procurement authority for Arleigh Burke-class destroyers and associated 
systems (sec. 125) 
The committee recommends a provision that would authorize the Secretary of the Navy to 
buy up to 10 Arleigh Burke-class Flight IIA destroyers under a multiyear procurement 
contract. This would be the third multiyear contract for the Arleigh Burke-class program. 
The Navy estimates that the previous two multiyear procurement contracts (fiscal years 
1998–2001 and fiscal years 2002–2005) achieved savings of greater than $1.0 billion, as 
compared to annual procurements. For the third contract (for fiscal years 2013–2017), the 
Navy is estimating that the expected savings will be 8.7 percent, or in excess of $1.5 billion, 
for the multiyear approach as compared to annual procurement contracts. 
While the Navy’s shipbuilding plan currently provides for only nine Arleigh Burke-class 
destroyers during the period of the planned multiyear contract, the committee understands 
from the Navy that competition between the two shipyards in fiscal year 2011 and 2012 has 
led to significant savings in the program compared to the original budget request. The Navy 
program office believes that competition for the multiyear contract starting in fiscal year 
2013 could also yield additional savings, and that the sum total of those savings might be 
sufficient to purchase an additional destroyer in fiscal year 2014. The committee is 
recommending approval of a multiyear authority for up to 10 ships with the prospect that the 
Navy may be able to combine the savings from fiscal years 2011, 2012, and 2013 and buy an 
additional destroyer, which is consistent with congressional authorization in section 2308 of 
title 10, United States Code, for the Secretary to buy-to-budget. 
The committee believes that continued production of Arleigh Burke-class destroyers is 
critical to provide required forces for seabased ballistic missile defense (BMD) capabilities. 
The Navy envisions that, if research and development activities yield an improved radar suite 
and combat systems capability, they would like to install those systems on the destroyers in 
fiscal years 2016 and 2017, at which time the designation for those destroyers would be 
Flight III. Should the Navy decide to move forward with the integration of an engineering 
change proposal (ECP) to incorporate a new BMD capable radar and associated support 
systems during execution of this multiyear procurement, the Secretary of the Navy shall 
submit a report to the congressional defense committees, no later than with the budget 
request for the year of contract award of such an ECP. The report will contain a description 
of the final scope of this ECP, as well as the level of maturity of the new technology to be 
incorporated on the ships of implementation and rationale as to why the maturity of the 
Congressional Research Service 
15 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
technology and the capability provided justify execution of the change in requirements under 
that ECP during the execution of a multiyear procurement contract. (Pages 13-14) 
Conference 
The conference report (H.Rept. 112-705, filed on December 18, 2012) on the FY2013 National 
Defense Authorization Act (H.R. 4310) authorizes MYP arrangements for CH-47 helicopters 
(Section 111), Virginia-class attack submarines (Section 122), DDG-51 destroyers (Section 123), 
and V-22 Osprey tilt-rotor aircraft (Section 151). 
FY2013 DOD Appropriations Bill (H.R. 5856) 
House 
Section 8010 of H.R. 5856 as reported by the House Appropriations Committee (H.Rept. 112-493 
of May 25, 2012) would permit MYP arrangements for F/A-18E, F/A-18F, and EA-18G aircraft, 
DDG-51 destroyers, Virginia-class attack submarines, CH-47 helicopters, and V-22 Osprey tilt-
rotor aircraft. 
Senate 
Section 8010 of H.R. 5856 as reported by the Senate Appropriations Committee (S.Rept. 112-196 
of August 2, 2012) would permit MYP arrangements for F/A-18E, F/A-18F, and EA-18G aircraft; 
up to 10 DDG-51 Arleigh Burke class Flight IIA guided missile destroyers, as well as the AEGIS 
Weapon Systems, MK 41 Vertical Launching Systems, and Commercial Broadband Satellite 
Systems associated with those vessels; SSN-774 Virginia class submarine and government-
furnished equipment; CH-47 Chinook helicopter; and V-22 Osprey aircraft variants. 
Congressional Research Service 
16 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Appendix. Programs Approved for MYP in Annual 
DOD Appropriations Acts Since FY1990 
Table A-1. Programs Approved for MYP in Annual DOD Appropriations Acts 
Since FY1990 
Fiscal 
Year 
Bill/Law 
Section on MYP 
Program(s) Approved for MYP 
2012 
H.R. 2055/P.L. 112-74 
Section 8010 of Division A 
UH–60M/HH–60M and MH–60R/MH–60S Helicopter 
Airframes 
MH–60R/S Mission Avionics and Common Cockpits 
2011 
H.R. 1473/P.L. 112-10 
Section 8010 of Division A 
Navy MH-60R/S helicopter systems 
2010 
H.R. 3326/P.L. 111-118 
Section 8011 of Division A 
F-18 aircraft variants 
2009 
H.R. 2638/P.L. 110-329 
Section 8011 of Division C 
SSN Virginia class submarine 
2008 
H.R. 3222/P.L. 110-116 
Section 8010 of Division A 
Army CH-47 Chinook helicopter 
M1A2 Abrams System Enhancement Package 
upgrades 
M2A3/M3A3 Bradley upgrades 
SSN Virginia Class submarine 
2007 
H.R. 5631/P.L. 109-289 
Section 8008 of Division A 
C-17 Globemaster 
F-22A 
MH-60R Helicopters 
MH-60R Helicopter mission equipment 
V-22 Osprey 
2006 
H.R. 2863/P.L. 109-148 
Section 8008 of Division A 
UH-60/MH-60 helicopters 
C-17 Globemaster 
Apache Block II Conversion 
Modernized Target Acquisition Designation 
Sight/Pilot Night Vision Sensor (MTADS/PNVS) 
2005 
H.R. 4613/P.L. 108-287 
Section 8008 
Lightweight 155mm Howitzer 
2004 
H.R. 2658/P.L. 108-87 
Section 8008 
F/A-18 aircraft 
E-2C aircraft 
Tactical Tomahawk missile 
Virginia Class submarine 
2003 
H.R. 5010/P.L. 107-248 
Section 8008 
C-130 aircraft 
FMTV 
F/A-18E and F engine 
2002 
H.R. 3338/P.L. 107-117 
Section 8008 of Division A 
UH-60/CH-60 aircraft 
C-17 
F/A-18E and F engine 
Congressional Research Service 
17 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Fiscal 
Year 
Bill/Law 
Section on MYP 
Program(s) Approved for MYP 
2001 
H.R. 4576/P.L. 106-259 
Section 8008 
Javelin missile 
M2A3 Bradley fighting vehicle 
DDG-51 destroyer 
UH-60/CH-60 aircraft 
2000 
H.R. 2561/P.L. 106-79 
Section 8008 
Longbow Apache helicopter 
Javelin missile 
Abrams M1A2 Upgrade 
F/A-18E/F aircraft 
C-17 aircraft 
F-16 aircraft 
1999 
H.R. 4103/P.L. 105-262 
Section 8008 
E-2C aircraft 
Longbow Hellfire missile 
Medium Tactical Vehicle Replacement (MTVR) 
1998 
H.R. 2266/P.L. 105-56 
Section 8008 
Apache Longbow radar 
AV-8B aircraft 
Family of Medium Tactical Vehicles 
1997 
H.R. 3610/P.L. 104-208 
Section 8009 of Section 
Javelin missiles 
101(b) of Title I of Division A  Army Tactical Missile System (ATACMS) 
Mk19-3 grenade machine guns 
M16A2 rifles 
M249 Squad Automatic Weapons 
M4 carbine rifles 
M240B machine guns 
Arleigh Burke (DDG-15 [sic:51] class destroyers 
1996 
H.R. 2126/P.L. 104-61 
Section 8010 
UH-60 Blackhawk helicopter 
Apache Longbow helicopter 
M1A2 tank upgrade 
1995 
H.R. 4650/P.L. 103-335 
Section 8010 
MK19-3 grenade machine guns 
M16A2 rifles 
M249 Squad Automatic Weapons 
M4 carbine rifles 
1994 
H.R. 3116/P.L. 103-139 
Section 8011 
[none] 
1993 
H.R. 5504/P.L. 102-396 
Section 9013a 
Defense Support Satellites 23, 24 and 25 
Enhanced Modular Signal Processor 
Congressional Research Service 
18 
Multiyear Procurement and Block Buy Contracting in Defense Acquisition 
 
Fiscal 
Year 
Bill/Law 
Section on MYP 
Program(s) Approved for MYP 
1992 
H.R. 2521/P.L. 102-172 
Section 8013 
MK-48 ADCAP Torpedo 
UH-60 Black Hawk helicopter 
Army Tactical missile 
1991 
H.R. 5803/P.L. 101-511 
Section 8014 
Line of Sight-Rear (Avenger)—Pedestal Mounted 
Stinger 
Family of Medium Tactical Vehicles (FMTV) 
LCAC Landing Craft 
LHD Amphibious Ship 
MK-45 Gun Mount/MK-6 Ammo Hoist 
NAVSTAR Global Positioning Satellite (GPS) 
Defense Support Program Satellites 22 and 23 
1990 
H.R. 3072/P.L. 101-165 
Section 9021a 
M-1 tank engines 
M-1 tank fire control 
Bradley Fighting Vehicle 
Family of Heavy Tactical Vehicles 
Maverick Missile (AGM-65D) 
SH-60B/F helicopter 
DDG-51 destroyer (two years) 
Source: Table prepared by CRS based on text of bills. 
a.  In H.R. 5504/P.L. 102-396 and H.R. 2072/P.L. 101-165, the general provisions title was Title IX. 
 
Author Contact Information 
 
Ronald O'Rourke 
  Moshe Schwartz 
Specialist in Naval Affairs 
Specialist in Defense Acquisition 
rorourke@crs.loc.gov, 7-7610 
mschwartz@crs.loc.gov, 7-1463 
 
 
Congressional Research Service 
19